PROJECTS PROGRESS OVERVIEW 08-04-2019

Note: TEXT with this colour ■ shows repeated information

Project#01 P.CELL WEST

Sub contractor: Haji Rahib (03003980752)

Building in use.

Project#02 P.CELL EAST

Sub contractor: Haji Rahib (03003980752)

Slab concrete pouring done.

Flooring and rest of the finishing work will be started after removal of formwork.

Project#03

Sub contractor: Tariq (03468052286)

Excavation done.

Footing concrete poured.

Material available

150 Cement bags

1 Crush Dumper

0.5 Sand Dumper

3 tonne steel

Project#04

Sub contractor: SanaUllah (03012165969)

Tiles are being installed on the walls and floor of washrooms.

Next step will be flooring.

Tiling for washrooms completed.

Project#05 MOQ

Sub contractor: Fiaz Ahmad (03411128300)

Excavation has been completed.

Levelling complete

Centre line marked for pcc

Water storage pit completed.

PCC done.

Steel cutting. (in process)


Column steel fixing in process

Footing concrete poured

Material available

6 sand + 0.75,0.75 crush (10,20)

500 cement bags

1 water tank

42 tonne Steel (12 #6, 13 #4, 17 #3) – Bottom mesh steel – column steel

Project#06 FCIU Offices

Sub contractor: Tariq (03468052286)

Excavation completed.

PCC and RCC complete.

Upto phase II (4' above plinth)

Steel has been fixed for ground floor columns.

Blockwork up to lintel level

Lintel beam casted

Project#07 MOQ B05

Sub contractor: Fiaz Ahmad (03411128300)

Alhamdulillah! New project has been awarded.

Project name: MOQ B05

Location: Back to MOQ B04


Award date: 04/04/2019

Layout complete.

Excavation will be done by tomorrow.

Excavation completed