1x20MW CAPTIVE POWER PLANT

DATE-13-04-2019
A CIVIL WORK PROGRESS

Sl No Building Name DE-Drgs Excavation in Cum PCC in Reinforcement steel RCC in Cum Remarks
Cum (Except in MT
floor PCC)

ACTUAL AS PER ACTUAL ACTUAL


AS PER DRG ACTUAL DONE AS PER DRG AS PER DRG
DONE DRG DONE DONE
TG BUILDING
1 Received 1,300.00 1,212.00 31.39 36.92 73.34 33.50 532.62 237.17 Work Is in progress

2 ACC BUILDING Received 1,350.00 540.00 18.34 6.69 28.00 4.50 307.05 70.32 Work Is in progress/ stone dismentling work is not starts
3 DM TANK Received 120.00 120.00 3.00 2.66 1.90 2.00 29.00 14.58 Work in progress/ water pipe line not shift

4 ACT Received 85.00 85.00 5.10 1.70 1.67 - 18.50 - Work in progress/ FFL changed done 494.5
RAW WATER TANK
5 Received 900.00 250.00 30.00 - 11.13 - 150.00 - overburden removing under progress./ STOPPED 02 DAYS
CHIMNEY-01
Received 200.00 205.00 5.26 3.50 4.00 - 110.20 - ONE COMP AND OTHER IN PROGRESS
CHIMNEY-02
6 Received 200.00 205.00 5.26 3.50 4.00 - 110.20 14.66 ONE COMP AND OTHER IN PROGRESS
TG DECK
7 Received 600.00 600.00 10.00 26.00 24.00 280.80 EXCAVATION UNDER PROGRESS
WTP BUILDING
8 Received 400.00 15.00 6.35 5.51 57.00 EXCAVATION UNDER PROGRESS
TG BUILDING GRID SLAB & TRENCH
9 Received 80.00 73.50 17.31 178.50 WILL START AFTER CELLAR ROOM SLAB CASTING
GUARD POND
10 Received 180.00 8.66 5.50 52.60 LAYOUT UNDER PROGRESS
N PIT
11 Received 190.00 5.10 3.84 35.75 LAYOUT UNDER PROGRESS
HRSCC
12 Received 60.00 4.00 3.96 40.75 LAYOUT UNDER PROGRESS
CLARIFIED WATER STR
13 Received 110.00 5.20 2.89 55.60 LAYOUT UNDER PROGRESS

TOTAL 5,775.00 3,232.00 211.16 80.97 187.05 40.00 1,958.57 336.72


1X

SI.no Description Unit


1 2 3 4 5 6 7 8 9
A Civil
1 Masons No's 1 1 1 1 1 1 1 1 1
2 Masons Helper No's 1 1 1 1 1 1 1 1 1
3 Carpenter No's 6 6 6 6 6 6 2 6 6
4 Car./Helpers No's 6 6 5 5 5 5 2 6 6
5 Barbender No's 6 6 7 7 7 7 2 7 7
6 Bar.helper No's 5 5 6 6 6 6 2 6 6
7 Un skilled No's 21 20 22 21 13 13 5 13 12
9 Others No's 1 1 1 2 2 2 2 2 2
10 Fitter + Welder + HelpeNo's 1 1 1 1 1 1 1 1 1
11 Supervisor No's 1 1 1 1 1 1 1 1 1
12 ELEC/MECH. No's 0 0 0 0 0 0 0 0 0
Total No's 49 48 51 51 43 43 19 44 43
1X20MW CAPTIVE POWER PLANT
Daily Labour report (DLR)
Apr-19
10 11 12 13 14 15 16 17 18 19 20 21 22 23

1 1 1 1
1 0 0 0
0 7 7 7
0 7 7 7
0 7 7 7
0 6 6 6
6 10 10 10
2 1 1 1
0

1 1 1 1
0 0 0
11 40 40 40 0 0 0 0 0 0 0 0 0 0
24 25 26 27 28 29 30

0 0 0 0 0 0 0
POWER PLANT SITE PHOT

TGB PLINTH BEAM


DM TANK EXCAVATION

RAW WATER TANK AREA


NT SITE PHOTOGRAPHS

TG DECK
ACC BUILDING

ACT FOUNDATION

You might also like