Professional Documents
Culture Documents
June 2013
Version history
ATTACHMENTS .......................................................................................................................................1
ATTACHMENT 1 ..................................................................................................................................3
GBRMP Zone Map...........................................................................................................................3
ATTACHMENT 2 ..................................................................................................................................7
Plan of Existing Clump Point Jetty ...................................................................................................7
ATTACHMENT 3 ................................................................................................................................11
Marine Parks Permit.......................................................................................................................11
ATTACHMENT 4 ................................................................................................................................17
Review of Marine Environmental Factors at Clump Point (1998)...................................................17
ATTACHMENT 5 ................................................................................................................................19
Clump Point Sea Floor Survey (2012)............................................................................................19
ATTACHMENT 6 ................................................................................................................................21
Hydrographic Survey......................................................................................................................21
ATTACHMENT 7 ................................................................................................................................25
EPBC MNES Report ......................................................................................................................25
ATTACHMENT 8 ................................................................................................................................41
Community Consultation Report ....................................................................................................41
ATTACHMENT 9 ................................................................................................................................43
Cultural Heritage Assessment Report ............................................................................................43
Project Title: Clump Point Jetty Demolition, Installation, Operation and Maintenance
Project
Project Objective: To provide a new, safer and more-resilient jetty structure at Clump Point to
replace the existing structure damaged in Cyclone Yasi and better service
the local community
Description: The project involves removal and replacement of existing Clump Point Jetty
with a new, wider and more robust jetty structure approximately 170m in
length and 5m in width and capable of surviving a 1 in 500 year storm event
with minimal structural damage
The jetty is an important piece of community infrastructure with multiple community and commercial
uses. The State and Federal Governments allocated special funding for reconstruction of both the
Clump Point and Dunk Island jetties under Natural Disaster Relief and Recovery Arrangements
(NDRRA). After investigating various repair and replacement options, and taking into account the needs
of the community, replacement of the existing jetty was selected as the preferred option and was
subsequently approved by the Queensland Reconstruction Authority (QRA).
This project will remove the old jetty and construct a new jetty in a position immediately to the south of
the existing jetty. The new position is similar in location to a previous jetty demolished in 1995. The new
jetty will result in a new infrastructure footprint on the natural environment.
Access to Clump Point Jetty from the land side is via Alexandra Drive which runs north along the
coastline from the Mission Beach township. South of the jetty at Clump Point itself, there is a boat ramp
and small floating pontoon protected by a rock groyne. This facility is intended primarily for recreational
use.
After assessment of the damage, repair costs, risks of similar damage in the future, expected remaining
life of the structure and functional deficiencies of the existing structure, it was decided that the existing
jetty should be replaced with a new, stronger, safer, more resilient structure.
The new structure will be 175m long and 5.0m wide, with a total of seventeen 10m long spans. The jetty
will be widened to 6.0m at the jetty head. The jetty deck will be approximately 0.5m higher than the
existing jetty. Stairs and landings will be provided for use by smaller vessels and a new storm surge
gauge and supporting structure will be installed. Power, water, lighting and fire safety facilities will be
provided.
The substructure for the new jetty will consist of 18 pile bents consisting of two 610mm diameter steel
piles with precast concrete headstocks. Piles will be pre-coated with a protective coating (Interzone 954)
specifically developed for use in marine environments.
A total of 36 main piles and 7 shorter, stand-alone fender piles will be installed. Design length of main
piles is between 19 and 24 metres based on expected embedment lengths between 14 and 20 metres.
Design length of fender piles is 14 metres based on expected embedment lengths of 5 to 6 metres.
The new structure has been designed by a Registered Professional Engineer, Queensland (RPEQ) to
conform to the requirements of Australian Standard AS4997-2005 – Guidelines for the design of
maritime structures and other relevant Australian Standards.
The existing jetty will be demolished once the new structure becomes operational.
1. Not repairing the jetty. This option was not adopted as the jetty is a vital piece of
infrastructure for locals, visitors to the area, and for providing access for other legal commercial
activities. In addition, the jetty would remain susceptible to structural failure and damage in
future storm events .
2. Installation of a floating jetty structure. This option was not adopted due to its unsuitability
for use in this location, as well financial constraints.
3. Relocating the jetty to an alternative location. Investigations showed that the current
location provided the best overall outcomes for stakeholders
4. Protecting the jetty with wave barriers to calm the waters and allow use of floating
pontoons. Alternate designs were considered during consultation and project planning. These
2.3.2 Program
The reconstruction of Clump Point jetty is being undertaken in conjunction with and generally following
reconstruction of Dunk Island jetty. Construction works for the Clump Point jetty are programmed over a
five month period as follows:
Proposed work activities and expected durations for the works are as follows:
1. Establishment - 7 days
2. Structural works (piling, headstocks, girders, deck) - 108 days (6 days per span x 17 spans)
3. Miscellaneous works (railing, stairs, furniture) - 60 days (concurrent with structural wk)
4. Fender piles - 6 days
5. Landside access - 4 days
6. Demolition works - 10 days
The jetty will be constructed on a span-by-span basis from the shore. Each span cycle is expected to
take 6 working days (7 to 8 calendar days) depending on the weather and other influencing factors.
Each cycle will involve the following activities and estimated durations:
2.3.4 Materials
The principal materials to be used for construction of the new jetty are steel and concrete. Piles will be
steel and other major components will be precast concrete.
Steel piles will be coated with a protective coating specifically developed for marine environments
(Interzone 954). The coating will be applied to piles off site prior to delivery to site.
Major components will be manufactured or prefabricated off-site and transported to site by road and
stored in designated storage areas where required. Alternative off-site storage may be used if
necessary. Components will be removed from storage and installed as required.
Piles will be hollow-ended steel tubular piles transported to site in lengths to suit. A 12 metre section at
the top of the pile would be blasted and given a protective coating prior to transport to site. Pile lengths
of 16 to 24 m are expected. For the longer piles, sections of pile will be joined by welding on site to
achieve the required pile length. A 1 m long, 25 mm pile shoe will be welded to the bottom of the pile
prior to driving.
Piles will be driven using a crane and vibrating or drop hammer. Due to varying geotechnical conditions,
pile driving times are expected to vary from a few hours in favourable conditions to several hours where
conditions are unfavourable. It is planned to set and drive both piles at each pier using the vibrating
hammer, before completing driving with the drop hammer. Breaks of 30 to 60 minutes will occur to swap
the hammers from one pile to the other and to change from the vibrating hammer to the drop hammer.
Piles for the abutment and initial piers will be driven from the ground. Piles for subsequent piers will be
driven from the previously completed deck. Once the initial piles are driven, precast headstocks will be
installed and girders and deck for the first spans completed.
For subsequent spans, the temporary pile frame will be suspended from the headstock and piles of the
previous span as shown in the diagram below. For the initial spans, temporary excavation of beach
sand may be necessary to provide sufficient clearance to install the pile frame. Consultation with
Queensland Parks and Wildlife Service (QPWS) will be undertaken for approval for the excavation of
beach sand. The pile frame will cantilever from the completed pier to the next pier to locate and support
the next set of piles. The crane will be supported by the completed deck. Once the piles are driven, the
top of the pile will be cut back and top plates welded to the top of the pile. A new precast concrete
headstock will be lowered into position and secured by bolts to the pile top plate.
Once the headstock has been secured, the cantilever frame will be removed and a temporary walkway
placed as a working platform to facilitate installation of precast girders. Precast girders will be lowered
into position and secured with stainless steel anchor bars grouted into headstocks. The temporary
walkway will be removed and precast deck units installed and bolted to the girders using stainless steel
hold down bolts.
After the deck is installed the crane will move forward on the newly completed deck and the cantilever
frame installed to commence the next span. A semi trailer or “franna” crane would be driven along the
new jetty deck to supply precast components to the crane for placement.
Once the jetty is constructed to deck level, the installation of furniture and services can commence.
Floating plant (small work boat or barge) may be used for some underdeck work, but most work will be
undertaken from above deck.
The benefits of the cantilevered frame is that work is less weather dependant and works can continue
during periods of bad weather when floating plant may find it difficult to operate. This gives increased
certainty that works will be completed in the shortest possible time frame. The process can be used
from the start of works and reduces the need to have plant working in the tidal zone or working from
barges. If it becomes necessary to carry out work in the tidal zone, an amphibious excavator which can
operate in up to 1.5 m of water before it will float is available and could be used.
Once all jetty works are complete permanent access for vehicles and pedestrians onto the jetty will be
reinstated. This will involve breaking back and removing an existing concrete slab near the approach to
the jetty, minor excavation of existing material and installation of a small area of sealed pavement.
Demolition will be carried out by CivilPlus Constructions - a licensed demolition company. Arrangements
for the removal and disposal of waste materials will be in place prior to commencing demolition.
Demolition of the jetty structure will take place after all services are removed from the structure.
Structural components will be removed from the top down in reverse order to the original construction
sequence as follows:
• Timber Deck:
Unbolt and remove deck planks, carry or crane to designated storage area prior to transporting
to the Tully Council depot for use by Council
• Steel Headstocks:
Cut off with suitable steel cutting equipment, secure load, crane to designated storage area
• Steel Piles:
Piles will be pulled from the ground using either a 36 Tonne CAT Excavator and/or crane
operating from either the ground or the new jetty deck. Vibrating equipment will be attached to
the top of the pile to facilitate pile removal where necessary.
Given the depth of the piles and nature of the existing substrate, it expected this methodology above will
achieve a pull force greater than the pile resistance enabling piles to be successfully removed.
In the event that this methodology is unsuccessful, the following options may be employed:
• an additional excavator or crane will be used to increase the pull force
• an amphibious excavator will be used to excavate material from around the top of the pile
• an air/water sparge ring may be attached to the piles and lowered down to loosen material
from the top of the pile
Should these additional actions be unsuccessful, it is proposed that the piles be cut off at a minimum
depth of 1.0 metre below the existing bed level. This would be achieved by excavating to a suitable
depth the expose the cutting point, and cutting of the pile using either above-water oxy-acetylene cutting
equipment or special underwater cutting equipment.
Where it is likely that debris may enter the water during the removal works, the sections of the jetty will
be encapsulated to ensure no waste materials or pollutants enter the Marine Park.
Prior to demolition a detailed risk assessment will be provided to the Managing Agency for approval as
part of a schedule of works (as per condition 9 of Marine Parks permit G12/35298.1). The risk
assessment will include but not be limited to:
• potential impacts from cutting piles and excavating the benthos including
turbidity monitoring during excavation;
• management of Potential Acid Sulphate Soils (PASS),
• management of benthic disturbance including direct removal of
seagrass/coral, live organisms;
• potential subsidence of the seafloor due to the removal of piles from depth;
• details of a post works site survey (commercial diver inspection) which
ensures the site has been cleaned up appropriately following works.
The jetty is located within the Boat Bay area to the north of Clump Point. It will extend approximately
170m from the shore to locate the jetty head at a point where the bed level is approximately 2m below
the lowest astronomical tide (LAT). Rocky habitat, hard corals, intertidal and sub-tidal sand/mud areas
are known to exist in the vicinity of the site. Clump Point is the only mainland Cainozoic basalt headland
in the region.
A hydrological survey of the site undertaken shows current bed level almost identical to the bed level
shown on 1995 drawings for the existing jetty, indicating that there has been limited natural erosion or
deposition. This hydro-graphic and topographic survey was conducted in March of 2012. A plan
showing the sea bed contours derived from the survey can be found in Attachment 4.
It is not expected that the structure will have any significant impact on natural erosion and deposition
processes due to the small footprint of the piles at the seabed and the lack of any significant erosion or
deposition associated with the existing jetty.
Clump Point is located on Boat Bay in the wet tropical region of North Queensland. Boat Bay is zoned
as a Habitat Protection Zone under the Great Barrier Reef Marine Park Zoning Plan 2003 and the Great
Barrier Reef Marine Park Zoning Plan 2004 (Queensland) and supports a number of significant species
and communities including:
A visual survey of benthic communities was undertaken in June 2012. In this survey divers mapped the
sea floor by moving a 1 m² metal frame along the sea floor in a pre-designated grid pattern. All objects
or features found in each 1 m² lot were recorded, resulting in a grid survey of the proposed jetty site.
This survey found that:
• no coral structures were located in the project footprint or within 10 m of the jetty
• sea grasses were found in 190 of the survey squares under the footprint of the new jetty
The survey indicates that potentially 190 m² of sea grass may be impacted by the jetty footprint. A copy
of the survey report and map of the sea floor is included as Attachment 6. Potentially offsetting this loss,
approximately 100 m2 of the seabed in the zone where seagrasses are evident will be released from
beneath the footprint of the old jetty when the old jetty is demolished.
A search of Australian Government and Queensland Government information sources shows that there
are many significant species that are known to inhabit or use the Clump Point area. This includes six
turtle species, four whale species, seven dolphin species, and the Dugong. The area is also known
habitat for many other important species such as sea snakes and kraits, sea horses, sharks, pipefish,
and many other fish species. A list of marine species that may be found in the area is provided in
Attachment 7.
Closer to shore the fringing intertidal mangroves and extensive intertidal areas provide feeding grounds
for many sea birds. The reefs are home to a diverse range of marine life.
The Clump Point terrestrial environment is also significant with the region being renowned for being
where the ‘rainforest meets the reef’. The vegetation found along the foreshore of Clump Point is
remnant complex mesophyll vine forest or mangrove open forest. The Regional Ecosystem found at the
jetty access point is RE: 7.8.1, Complex mesophyll vine forest on well drained basalt lowlands and
foothills. This regional ecosystem is classed as ‘Least Concern’ under the Vegetation Management Act
1999. This regional ecosystem is also deemed ‘essential habitat’ for the Southern Cassowary Casuarius
casuarius johnsonii. As the entry area to the jetty is clear no native terrestrial vegetation will need to be
cleared.
The existing jetty is an important part of the fabric of the local community and is used by a range of
commercial enterprises, tourists and members of the local community for a range of activities including:
commercial vessels, primarily in the tourism industry, for loading and unloading passengers
and goods associated with their commercial activities
tourists and locals for various recreational activities including strolling, sightseeing, fishing and
viewing marine life.
The Djiru Indigenous Traditional Owners have a strong cultural connection with this area. There are
several archaeological sites located in and around Boat Bay, which is culturally important for hunting
and fishing, seagrass meadows, ceremonial grounds and the cultural landscape.
Consultation with local Indigenous communities was undertaken as a part of this project and an
assessment of cultural heritage values and concerns at the jetty site was undertaken. The assessment
concluded that:
(i) No issues were identified with the development and that it should proceed as proposed;
(ii) (the proponent) retains a “cultural heritage duty of care” under the Aboriginal Cultural
Heritage Act 2003 and it is important that personnel working within the study area have an
understanding of the significance of cultural heritage; and
(iii) If (construction) personnel locate any items or sites which they suspect may be Aboriginal
cultural heritage they should contact Girringun Aboriginal Corporation immediately:
A copy of the Cultural Heritage Assessment report dated July 2012 is attached (Attachment 9).
A site inspection for native plant species will be undertaken before starting works to determine if any of
these species are present within the works area. Areas where significant vegetation has been located
will be clearly marked to protect against damage by plant and equipment.
Proposed works are to remove the existing jetty structure and construct a new jetty several metres to
the south. The works are short-term and, once complete, are expected to have no long-term impacts.
Materials and construction methodologies proposed for the work have been selected in part as they are
low impact on the marine environment.
The marine environment surrounding Clump Point is classed as Habitat Protection Zone. The objectives
to be achieved for the habitat protection zone are—
(a) to provide for the conservation of the areas of the Marine Park within the zone through the
protection and management of sensitive habitats that are generally free from potentially
damaging activities; and
(b) subject to the objective mentioned in paragraph (a), to provide opportunities for reasonable
use of the areas.
The provision of the Clump Point jetty meets the objective of providing opportunities for reasonable use.
The project will be undertaken in a manner that ensures the conservation values protected by the
marine park zoning are not subject to any significant negative that will decrease these values.
A risk assessment was carried out to identify the key impacts and associated risks and identify
mitigating actions to reduce risks associated with these activities. The risk assessment outcomes are
summarised in the table in Appendix C.
• Noise and vibration caused by construction, including driving piles and the noise of machinery
and construction vessels.
• Collisions between marine animals and vessels/equipment.
• Disturbance of sediment during works and the impact of resulting sediment plumes and
increased turbidity in the water.
• Pollution of surrounding environment from hydrocarbons and from other toxic substances
disturbed during works.
• Impact on habitat including direct disturbance of the benthic environment.
General actions to reduce the risk posed by these potential impacts include;
Impacts on people living close to the jetty is expected to be moderate due to the intermittent nature of
pile driving and the low number of houses in the immediate vicinity of the jetty. To mitigate negative
impacts, the public will be advised that pile driving will be occurring during construction and pile driving
will generally be programmed to avoid driving early in the morning or late in the day. Specific notification
will be given should driving outside these hours be required.
Bird and land-based animals are expected to easily move away from the noises likely to disturb or
cause harm.
Noise and vibration from pile driving in water has the potential to cause harm to marine animals in the
marine environment. To decrease risks during pile driving, the following actions will be taken:
• Where possible, piles will be driven during low tide phases to minimise direct contact with the
water
• Where piles can be driven with a vibrating hammer, a vibrating hammer shall be used
• A “soft-start” procedure will be used to alert marine animals to vacate the area
• Piles shall not be driven in water when marine mammals are observed within 300m of the
works
• When marine turtles or other protected species are observed within 300 metres of the works,
they shall be monitored. Works will cease if any signs of physical distress are observed.
Pile driving will be undertaken in accordance with the Clump Point Marine Mammal and Protected
Species Management Plan (Appendix D). The procedure for piles driven in water shall be as follows:
• A 300m observation zone will be established around the works during pile driving activity.
• At least 30 minutes before pile driving commences a Marine Mammal and Protected Species
Observer will conduct a survey of the observation zone to identify whether marine mammals or
other protected species are present.
• If no marine mammals are sighted within the observation zone then works will commence with
a ‘soft start procedure’. In the soft start procedure the power of the activity (E.G. pile driving)
starts at the lowest impact and gradually increases a period of time to normal operating level.
The ‘soft start’ procedure aims to alert marine animals to the activity and provide them with an
opportunity to depart the area to a safe distance
• During pile driving the Marine Mammal and Protected Species Observer will remain on duty
constantly monitoring the observation zone for marine mammals. In the event that a marine
Noise and vibration may also affect fish swimming within a short distance of the works area. Fish will
generally swim away from noise during the “soft start” procedure to a safe distance where they are
unlikely to suffer harm. However, should pile driving results in any fish mortalities, the works will be
suspended immediately and reported to the managing agencies for advice.
During pile extraction activity associated with the demolition of the old jetty, a vibrating pile driver head
will be used to assist with loosening the pile to reduce the uplift force required by the pulling gear. Noise
and vibration during this activity will be lower than the levels that occur during pile driving.
During the demolition and construction phases, there may be a moderate increase in vessel activity at
the jetty site due to the use of work boats for some activities. Ongoing jetty operations may also see an
increase in the number of vessel movements, though these are expected to remain relatively low.
Vessels operating commercially within the Great Barrier Reef Marine Park require appropriate permits
to operate. A Clump Point Marine Mammal and Protected Species Management Plan 2012 (Appendix
D) has been developed and work boats used during construction and demolition works will be required
to conform to this plan.
Sightings of marine mammals within 300m of the jetty will be communicated to work boats in the area,
and vessel speeds will be limited to 6 knots when operating within a 300m radius during the time the
marine mammal is in the area.
With mitigation strategies in place, the risk of animal and vessel/equipment collision is considered low.
Prior to commencement of works water testing will be conducted and will form the baseline measure.
Additional water testing will be conducted on each day prior to commencing any in-water works and this
will be used for assessing turbidity levels during works.
The use of sediment curtains to reduce impacts from turbidity has been assessed as a risk to the
environment. Sediment curtains if not maintained (i.e. torn or deflated) do not capture sediment
adequately, cause further damage to the benthos from scouring and dragging during rough weather and
tidal movement and pose risks to marine fauna from entanglement and entrapment when left for periods
of time unattended. . Sediment curtains will therefore not be used where the potential impacts of using
sediment curtains are greater than those of the work activity.
Pile driving activities are considered low risk and sediment curtains will not be used during this activity.
A program of monitoring turbidity levels at various locations before and after pile driving shall, however,
Where there is a possibility of significant sediment release caused by works, particularly during removal
of piles, impacts may be mitigated by incorporating sediment capture methods such as sediment
curtains, but the use of sediment curtains during removal activities will require approval by the
Managing Agency. If sediment curtains are used, water testing shall be carried out intermittently outside
the sediment curtains to ensure sediment is satisfactorily constrained within the sediment curtain.
Sediment curtains will be in good condition and checked prior to use. The curtain will only be used in
weather conditions which do not pose further risks to disturbing the benthic environment from scouring
and dragging and if required to be left in the Marine Park will be monitored frequently to ensure marine
animals are not entangled or entrapped in the net. Where sediment curtains fail to adequately constrain
sediment, works shall cease until the cause of the breach is identified and rectified, including waiting
until prevailing conditions abate sufficiently to allow sediment curtains to function satisfactorily.
Should it be necessary to excavate or disturb material below the seabed during extraction of the piles,
the disturbed material will be contained within a sediment curtain and either returned to the excavated
hole or allowed to settle to the seabed prior to removal of the sediment curtains. Disturbed material will
not be removed from site or be allowed to oxidise if extracted from depth without PASS management
protocols in place or without sediment quality analyses being undertaken prior to works. Sediment
disturbance during pile driving is expected to be minor, therefore sediment curtains will not be used
during pile driving. Sediment disturbance and increases in turbidity will be short term, and relatively
benign with periods of time between disturbances allowing for the settlement of particles to occur in the
immediate vicinity of the piles thus ensuring no long term impacts to corals or seagrass.
Work boats are unlikely to cause major sediment disturbance. With the major plant operating from the
deck, works boats will generally be small work boats undertaking limited movements and tied to the jetty
structure in lieu of anchoring. To mitigate this risk, manoeuvring will be kept to a minimum and vessels
will be secured to the jetty structure where possible. Should anchoring be required, impacts are
expected to be minor due to the small size of vessels. However, only anchor points outside the area
where sea grasses have been identified by divers during seafloor mapping shall be used. If anchoring is
required within the seagrass area, and the sea floor is not visible, divers shall be used to identify
preferred anchor points that will cause least damage.
Apart from driving piles, construction works involve mainly the assembly of prefabricated steel and
concrete components, which mainly involves lifting, cutting, welding, drilling and bolting. The work will
generally be accomplished from above the water utilising the constructed deck, cantilevered frame or
temporary walkway spanning from the completed deck to the next pile bent. Work boats and other
floating plant may be used to facilitate assembly.
The Contractor’s Construction EMP (Appendix E) provides specific details on mitigation strategies for
these risks including storage of fuel and hazardous substances, refuelling procedures, management of
spills, management of blasting and cleaning operations, management of waste and sediment control
procedures.
Works will be conducted in a manner that will minimise habitat loss as a result of construction activity.
Where possible, work boats will tie up to the jetty structure in preference to dropping anchors. Where
anchors are necessary, the seabed survey, supplemented by additional diver checks, will be used to
select the best locations for anchoring to avoid causing damage to seagrasses or coral.
The old jetty will be completely removed once the new jetty is ready for commissioning. Demolition
works will be carried out by a licensed demolition contractor. All waste generated during construction
and demolition will be placed in a designated waste storage area and/or removed from site and
disposed of in an approved manner including recycling or disposal at an approved waste disposal
facility. Salvageable timber will be transported to the Cassowary Coast Regional Council’s depot in Tully
for re-use in other council assets. Documentation showing waste types and destination will be kept and
produced upon the request of an appropriate authority.
The jetty has been designed to accommodate a fuel truck for the possible refuelling of vessels from the
jetty deck. Fuel suppliers will require a permit issued by Cassowary Coast Regional Council in addition
to any other permit required by the Managing Agencies.
The existing Clump Point jetty operates under an existing Great Barrier Reef Marine Park Authority
(GBRMPA) permit. The impact of operations at the new jetty will be similar to past operations at the
existing jetty. Impacts on the listed values of jetty operations were considered as part of the project
environmental risk assessment (Appendix C).
Potential impacts during operation of the jetty that were considered include:
• Debris entering the water due to structural failure of the jetty or its components during major
storm events
• Deleterious material or rubbish entering the water during maintenance works
• Rubbish being dropped from the jetty by jetty users
• Fuel spills during refuelling operations or otherwise associated with berthed vessels or vehicles
• Deleterious material or debris entering the water due to fire on vessels and associated fire-
fighting activities
• Vessels discharging material into the water
Commercial operators using the jetty for commercial operations require separate authority from the
Great Barrier Reef Marine Park Authority (GBRMPA) to operate within the Marine Park. Commercial
operators seeking to use the jetty for commercial operations will be required to hold a permit to operate
in the Marine Park before being given approval to use the jetty for commercial operations.
Regular or routine maintenance and servicing includes activities such as rubbish removal, cleaning and
servicing of equipment and services such as power and water, and minor maintenance works. These
activities are generally minor and carry a low risk to the environment.
The major risks during routine maintenance are that rubbish, debris or other material enters the marine
environment. Maintenance procedures will be developed for rubbish removal, cleaning and minor
maintenance to ensure that rubbish and debris are not allowed to enter the marine environment during
routine maintenance.
Non-routine maintenance and repair will include activities such as restoration of the corrosion protection
system and repairs to components damaged during jetty operations. Potential impacts from these
activities will vary with the specific maintenance activity. Before such work is undertaken, a submission
for approval to carry out the works will be made to the Managing Agencies outlining the proposed
schedule of work, potential impacts and mitigating measures. Where the works or potential impacts are
significant, the submission shall be in the form of an Environmental Management Plan (EMP).
Should emergency works be necessary to protect the environment or to ensure public safety, works
may need to be undertaken without formal submission. In such cases, the proposed works will be
discussed with the Managing Agencies prior to undertaking the works. In the event of an emergency
where action must be initiated urgently, the Managing Agencies shall be contacted as soon as possible
to discuss the actions taken and any additional actions required to mitigate risks.
Further details of maintenance works and procedures are included in Section 7.0 Maintenance and
procedures for routine maintenance are included in Appendix H.
4.5 Potential Impacts and Mitigating Measures - Demolition of the New Jetty
At the end of the jetty’s useful life or in the event the jetty is damaged by a major storm event, vessel
impact or other event, the jetty may need to be demolished and removed from the GBRMP.
Potential impacts during jetty demolition are similar to those identified for construction and include:
• Noise and vibration caused by construction, including the noise of machinery and construction
vessels and vibrations created during removal of piles.
• Collisions between marine animals and vessels/equipment.
• Disturbance of sediment during works and the impact of resulting sediment plumes in the
water.
Demolition work is a regulated activity and demolition would be undertaken by a registered demolition
company. Mitigation measures will vary with the methods adopted for demolition, but would be expected
to include the following:
• Measures to minimise the risk of material and pollutants entering the marine environment
• Measures to ensure debris is recovered and disposed of to an approved waste disposal facility
• Measures to minimise noise and vibration during pile removal activities
• Measures to mitigate potential risks if piles need to be cut off below the sea bed in lieu of
removal
Mitigation methods will be agreed with the Managing Agencies at the time of demolition
Operational procedures include, but are not limited to, the following:
• Rules for commercial operators and other vessels berthing at the jetty, including restrictions on
berthing times, activities while berthed, refuelling operations, incident notification, etc.
• Rules for public use of the jetty, including permitted and restricted activity and rules related to
disposal of rubbish
• Provision of signage regarding use of the jetty and advisory signage on Marine Parks Zoning
• Monitoring of the operation and condition of the jetty through regular and special inspections
• Procedures for refuelling including restrictions and safety requirements
Operational procedures and controls will be reviewed on a regular basis and updated as necessary to
reflect changes over time and to ensure objectives are being met.
Appendix F contains operational procedures and controls currently applicable to the operation of the
Clump Point jetty.
The following general contingency or emergency response plans have been adopted:
Event Response
Chemical or hydrocarbon spill Per documented procedures in the Contractor’s construction EMP
based on the three C’s - control, contain and cleanup (see
Appendix E).
Environment incident reporting Incidents identified by the Contractor will be reported in
accordance with the procedure in the Contractor’s construction
EMP (Appendix E). Incidents reported to CCRC will be reported to
the Contractor and to Managing Agencies and, where appropriate,
to emergency services.
Injury to a marine mammal or Reported to GBRMPA and QPWS in accordance with the Marine
other protected marine animal Mammal and Protected Species Management Plan (Appendix D)
Recovery of dropped items Dropped items will be recovered from the water or seabed as soon
as possible after the event. If special equipment is required, the
location shall be recorded and the item recovered once the
equipment is available
In addition, the conditions identified in the Marine Parks Permit, G12/35298.1 relating to the notification
of harm will be adhered to at all times.
Operational contingency plans cover events that may occur during jetty operations and include:
Contingency plans for the operation of the jetty were initially developed for the commissioning of the
jetty, but will be reviewed on a regular basis and updated to reflect any changes in operations to ensure
objectives are being met.
Maintenance will include routine maintenance and servicing and non-routine maintenance and repairs.
Regular inspections
Cleaning
Maintenance and servicing of lighting, water services, fire services, etc
Minor repairs to protective coatings
Monitoring and maintenance of corrosion protection systems
Routine maintenance and servicing is generally low impact and will be undertaken on an as-required
basis and in accordance with Council’s overall asset management approach. Specific procedures for
routine maintenance and servicing activity are included in Appendix H.
Non-routine maintenance and repairs to the jetty are expected to occur infrequently and include:
At least 20 business days prior to the commencement of any works including non-routine maintenance,
repair and any decommissioning and/or removal, a schedule of works will be submitted to the Managing
Agency for approval. The schedule will include as a minimum the following:
(i) details of the works to be undertaken including the methods and timeframe for works;
(ii) a risk assessment in accordance with the GBRMPA EAM Risk Management Framework 2009;
(iii) details of the disposal and fate of any equipment, waste products and/or encrusting fauna and
flora; and
(iv) any remediation strategies to rehabilitate and/or clean up the site
Non-routine maintenance will only be carried out after the works have been approved in writing by the
Managing Agencies.
Design Drawings
+&55:3&1-"$&.&/5
$-6.110*/5
.*44*0/#&"$)2-% "RISBANEÚ/FFICE
0HÚ ÚÚÚ
&AX ÚÚÚ
#AIRNSÚ/FFICE
0H ÚÚÚ
&AX ÚÚÚ
-ACKAYÚ/FFICE
0H ÚÚÚ
&AX ÚÚÚ
4OWNSVILLEÚ/FFICE
0H ÚÚÚ
&AX ÚÚÚ
$0/$3&5&"/%3&*/'03$&.&/5 4536$563"-45&&-803, 5&.103"3:803,4 4&37*$&-0"%4 1*-*/(/05&4
"MMDPODSFUFXPSLTIBMMCFJOBDDPSEBODFXJUI"4$PODSFUF "MMTUFFMXPSLJODMVEJOHDPOOFDUPSTTIBMMCFJOBDDPSEBODF 5IFDPOUSBDUPSTIBMMBMMPXGPSBMMDPTUTBTTPDJBUFEXJUIUIFEFTJHO
'VODUJPO$BUFHPSZ /PSNBM
"MMQJMJOHTIBMMCFJOBDDPSEBODFXJUI"41JMJOH$PEFBOE
4USVDUVSFT
XJUI"44UFFM4USVDUVSFT$PEFBOE"4/;4 TVQQMZ
JOTUBMMBUJPOBOESFNPWBMPGBMMUFNQPSBSZCBDLQSPQQJOH
4USVDUVSBM%FTHJO"DUJPOTUP"4/;4
"4 XJUIOPUFTBOEEFUBJMTBTTFUPVUPOUIFESBXJOHT
$PODSFUF4QFDJGJDBUJPOTTIBMMCF $PMEGPSNFETUFFMTUSVDUVSFT TBGFUZTDSFFOT
TDBGGPMEJOHBOEPUIFSSFRVJSFNFOUTPGUIF %FDL6%- L1B 5IFEFUBJMPGUIFQJMFUPCFVTFEBOEUIFNFUIPEPG
&-&.&/5 (3"%& 4-6.1 ."9"(( 4UFFMTIBMMCF"4(SBEFHFOFSBMMZ"4(SBEF DPOTUSVDUJPOQSPDFTT5IFDPOUSBDUPSTIBMMFOHBHFTVJUBCMZRVBMJGJFE %FDL$POD-PBE L/ PQFSBUJPOTIBMMCFTVCNJUUFEUPUIF&OHJOFFSGPSBQQSPWBM
GPSDJSDVMBSIPMMPXTFDUJPOT"4(SBEFGPS FOHJOFFSUPEFTJHO
JOTQFDUBOEDFSUJGZBMMUFNQPSBSZXPSLTBOE $MBTT 1JMFUFTUJOHBOEDPOGJSNBUJPOUIBUQJMFTIBWFBDIJFWFEUIF
&YUFSJPS3$ .1B NN
SFDUBOHVMBSIPMMPXTFDUJPOT#PMUTTIBMMDPNQMZXJUI"4
EFNPMJUJPOXPSLT 7FTTFM -FOHUI -0"
N SFRVJSFEEFQUIBOEDBQBDJUZTIBMMCFDBSSJFEPVUCZUIF
.JOJNVNLHNDFNFOUXDSBUJP %JTQMBDFNFOU 5POOFT
"4
"4"4BTBQQSPQSJBUF8FMETTIBMMDPNQMZ QJMJOHDPOUSBDUPS5IFNFUIPEPGUFTUJOHTIBMMCFTVCNJUUFE
NBYJNVNGMZBTICZNBTTPGCJOEFS %FTJHOXPSLJOHMJGF ZFBST
XJUI"4 5IFDPOUSBDUPSJTUPQSPWJEFBMMUFNQPSBSZXPSLTDPOUSBDUPS UPUIF&OHJOFFSGPSBQQSPWBM
$PWFSUPSFJOGPSDFNFOUTIBMMCF 8JOE"DUJPOTFRVJWBMFOUUP"4/;4
"CSBTJWFDMFBOJOHQSJPSUPQBJOUJOHTIBMMCFUP"4 FOHJOFFSJOHESBXJOHTUPUIFTUSVDUVSBMFOHJOFFSGPSJOGPSNBUJPO -PBECFBSJOHQJMFTIBWFCFFOEFTJHOFEUPXJUITUBOEMPBET
J
'PPUJOHTNNCPUUPN
NNTJEFTBOEUPQ 3FHJPO $
$MBTT1BJOJUOHTIBMMCFPOFDPBUNNUXPQBDL JOEJDBUFEPOUIFQJMJOHQMBO
XJUIBNBYJNVNTFUUMFNFOUPG
JJ
)FBETUPDL(JSEFSTNNUPBMMTVSGBDFT 5FSSBJO$BUFHPSZ
JOPSHBOJDBJSDVSFE[JODTJMJDBUFDPBUJOHBQQMJFEXJUIJOIPVST *UJTUIFDPOUSBDUPSTSFTQPOTJCJMUZUPFOTVSFUIFPWFSBMMTUBCJMJUZPG NNBOEBOFDDFOUSJDJUZPGNN
JJJ
%FDLJOH4MBCTNNUPBMMTVSGBDFT 4IJFMEJOH.VMUJQMJFS.T
PGBCSBTJWFDMFBOJOH
VOMFTTTQFDJGJFEPUIFSXJTF1BJOJUOH UIFTUSVDUVSFXIJMTUVOEFSDPOTUSVDUJPO5IFDPOUSBDUPSTIBMMPCUBJO 5PQPHSBQIJD.VMUJQMJFS.U
JW
$PWFSTIBMMCFNNXIFSFTVSGBDFJTFYUFSJPSBCPWF TIBMMCFUPNBOVGBDUVSFSTTQFDJGJDBUJPOBOEUIFQBJOUFSTIBMM BEWJDFGSPNUIFFOHJOFFS 5FSSBJO)FJHIU.VMUJQMJFS.[
DBU
V 1JMFTTIBMMCFESJWFOCZBQQSPWFEQJMFESJWJOHUFDIOJRVFTUP
HSPVOE FOTVSFUIFNFUIPEPGBQQMJDBUJPOJTDPNQBUJCMFXJUI %FTJHO(VTU8JOE4QFFE7[
VMUJNBUF NT BOBQQSPWFETFUDBMDVMBUFECZUIF)JMFZ'PSNVMB"
3FJOGPSDFNFOUTIBMMCFUJFEJOUPQPTJUJPOBOETVQQPSUFEPO DPOOFDUJPOOUZQFBOEQBJOUTQFDJGJFE 5IFDPOUSBDUPSJTUPIBWFUIFDPOTUSVDUJPONFUIPEPMPHZTUBUFNFOUT DFSUJGJDBUFPGBEFRVBDZGPSQJMFMPBETTIBMMCFTVCNJUUFECZ
BQQSPWFEQMBTUJDBTGPMMPXT &BUIRVBLF-PBETUP"4 UIF1JMJOH$POUSBDUPSUPUIF&OHJOFFSGPSBQQSPWBM
(BMWBOJTJOHTIBMMCFIPUEJQQFEUP"4 QSFQBSFEBOETVCNJUUFEGPSHFOFSBMSFWJFXUPFOTVSFJUJTJO
)B[BSE'BDUPS
J
#BSTVQUP/BOEGBCSJDNNDFOUSFT BDDPSEBODFXJUIUIFEFTJHOJOUFOU "MMQJMFTTIBMMCFESJWFOJOUIFQSPQFSQPTJUJPOTIPXOPOUIF
#PMUTTIBMMCFHBMWBOJTFEBOEPGTVGGJDJFOUMFOHUIUP 1SPCBCJMUZ'BDUPS
JJ
#BST/BOEMBSHFSNNDFOUSFT %FTJHO$BUFHPSZ * ESBXJOHTXJUIBWBSJBUJPOPGOPUNPSFUIBONNJONGSPN
FYDMVEFUIFUISFBEGSPNUIFTIFBSQMBOF"TVJUBCMFXBTIFS
8FMEJOHBOECFOEJOHPGSFJOGPSDFNFOUJTOPUQFSNJUUFE TIBMMCFVTFEVOEFSBMMOVUT "MMWFSUJDBMEJTQMBDFNFOUBOENPWFNFOUTBSFUPCFMJNJUFEUPFOTVSF UIFWFSUJDBM<PSSBLJOHMJOF>XJUIBNBYJNVNWBSJBUJPOBUUIF
VOMFTTTIPXOPOUIFESBXJOHTPSBQQSPWFECZUIF )BOESBJMEFUBJMTBSFUPCFJOBDDPSEBODFXJUINBOVGBDUVSFST IFBEPGUIFQJMFGSPNUIFQPTUJPOTIPXOPOUIFESBXJOHTPG
6OMFTTPUIFSXJTFTQFDJGJFE
UIFGPMMPXJOHTIBMMBQQMZ UIFTUSVDUVSFJTOPUTVCKFDUFEUPMPBETPSNPWFNFOUTDBVTJOH
&OHJOFFS EFTJHOBOEDFSUJGJDBUJPO
JOBDDPSEBODFXJUI"4 NNJOBOZEJSFDUJPOBUUIFDPNNFODJOHTVSGBDF
TUSVDUVSBMEJTUSFTTUPBOZFMFNFOUXIJMFUIFTUSVDUVSFJTCFJOH
-BQTVOMFTTTIPXOPUIFSXJTF J
$MFBUT
CSBDLFUT
TUJGGFOFSTFUDFYNNQMBUF 5IFBCPWFEPOPUJODMVEFMPBETXIJDINBZCFBQQMJFEEVSJOH 7BSJBUJPOTPVUTJEFUIFTFMJNJUTTIBMMCFDBVTFGPSSFKFDUJPO
UFNQPSBSJMZTVQQPSUFE
'BCSJDDPNQMFUFNFTI JJ
8FMEJOHNNDPOUJOVPVTGJMMFUUPGVMMQFSJNFUFSBUDPOUBDU DPOTUSVDUJPO5IFCVJMEFSJTUPNBJOUBJOTUBCJMJUZEVSJOHDPOTUSVDUJPO
/ / JJJ
#PMUIPMFDMFBSBODFNN 1JMFTFUPVUTIBMMCFCZ"VUIPSJTFE4VSWFZPSBOEQJMF
4USVDUVSFUPCFBEFRVBUFMZCSBDFEUPQSFWFOUBOZIPSJ[POUBM 8BWFMPBEJOHCBTFEPOSFQPSU#CZ#POBDDJ(SPVQ 2-%
1UZ-UE MPDBUJPOTTIBMMCFDIFDLFEBOEBEWJTFEUP&OHJOFFSBGUFS
/ / JW
#VUUXFMETTIBMMCFRVBMJGJFEDPNQMFUFQFOFUSBUJPOJO NPWFNFOUPSEFGMFDUJPOT
/ BDDPSEBODFXJUI"4 DPOTUSVDUJPO
)PSJ[POUBMCBSTXJUINPSFUIBONNDPODSFUFVOEFSUIFO W
NNFOEQMBUFTUPBMMIPMMPXNFNCFST 1JMFTTIPVMECFDVUPGGUPMFWFM*NNFEJBUFMZBGUFSNBLJOHUIF
TIBMMIBWFMBQTUJNFTUIFTFMFOHUIT WJ
$POOFDUJPOTNJOJNVNPG.4CPMUT GJOBMDVUPGG
UIFBSFBTIPVMECFDPBUFEXJUIBOBQQSPWFE
$POTUSVDUJPOKPJOUTTIBMMCFTDBCCFEBOEDMFBOFEBOEDPBUFE "MMXFMEJOHUPCF$BUFHPSZ41$POTVNBCMFTTIBMMCF
/6*4"/$& QSPUFDUJWFDPBUJOHPWFSUIFFYQPTFETVSGBDF
XJUIBDFNFOUXBUFSTMVSSZJNNFEJBUFMZBGUFSQSJPSUPQMBDJOH &YYPS8YFMFDUSPEFT 5IFDPOUSBDUPSTIBMMEFWFMPQ
JNQMFNFOUBOEBENJOJTUFSBQMBOUIBU
DPODSFUF XJMMFOTVSFUIFNBOBHFNFOUPGOPJTFBOEWJCSBUJPOSFTVMUJOHGSPN
'BCSJDBUPSTIBMMBMMPXGPSBMMDMFBUTBOEPUIFSGJYJOHT
$PODSFUFTIBMMCFDPNQBDUFEVTJOHNFDIBOJDBMWJCSBUPST SFRVJSFECZUIF4VQFSWJTPS DPOTUSVDUJPOXPSLT
$PODSFUFTIBMMCFDVSFEGPSBNJOJNVNPGEBZTCZBNFUIPE
.PSUBSTIBMMCFDFNFOUTBOENJYFEKVTUNPJTUBOE
BQQSPWFECZUIF&OHJOFFS
SBNNFETPMJE 5IFDPOUSBDUPSXJMMOFFEUPFOTVSFBMMBEKPJOJOHQSPQFSUZ
$POEVJUT
QJQFTFUDNVTUOPUCFQMBDFEJOUIFDPODSFUFDPWFS SFRVJSFNFOUTSFMBUJOHUPOPJTFBOEWJCSBUJPOBSFNFU
(BMWBOJTFEIPUEJQQFEHBMWBOJ[FEPSTUBJOMFTTTUFFMCPMUT
BOEOPIPMFTPSDIBTFTPUIFSUIBOUIPTFTIPXOPOUIF
OVUTBOEXBTIFSTIBMMCFJOBDDPSEBODFXJUI"4
4USVDUVSBMESBXJOHTTIBMMCFNBEFJODPODSFUFNFNCFSTVOMFTT
"QQMZ;JODSPEGJOJTIJOHXFME
TVDIBT#PTT(BMWBOJ[JOH#BS *GJUJTFTUBCMJTIFEUIBUUIFSFBSFOPTJUFTQFDJGJDSFRVJSFNFOUT
UIFO
BQQSPWFECZUIF&OHJOFFS
UPSFJOTUBUFHBMWBOJ[JOHBGUFSXFMEJOHUZQJDBMBMMHBMWBOJ[FE UIFDPOUSBDUPSTIBMMSFGFSUPNJOJNVNSFRVJSFNFOUTGPSBCBUFNFOUPG
'PSNXPSLTIBMMDPNQMZXJUI"4'PSNXPSLGPS$PODSFUF TVSGBDFT OPJTFBOEWJCSBUJPOOPNJOBUFECZSFMFWBOUCZTUBUVUPSZSFRVJSFNFOUT
BOEBMMSFMFWBOU$POTUSVDUJPO4BGFUZ-FHJTMBUJPO6OMFTT
PUIFSXJTFOPUFEGJOJTIFTTIBMMCF$MBTT.JOJNVNGPSNXPSL 5IFDIFDLJOHPGTIPQESBXJOHTJTJODMVEFEJOPVSTDPQFPGXPSLT $0/4536$5*0/*446& +#( "+'
451$POTVMUBOUTXJMMSFRVJSFCVTJOFTTEBZTBGUFSSFDFJWJOHBMM 5IFDPOUSBDUPSXJMMOFFEUPQSFQBSFBOEBEWJTFPONPOJUPSJOHBOE ' "11307"-*446& +#( "+'
TUSJQQJOHUJNFTTIBMMCFJOBDDPSEBODFXJUI5BCMFPG"4
TIPQEFUBJMESBXJOHTGPS451$POTVMUBOUTUPSFUVSODPNNFOUT NBOBHFNFOUPGOPJTFBOEWJCSBUJPOCBTFEPOQSPGFTTJPOBMBEWJDFGSPN & 13&-*.*/"3:*446& +#( "+'
'PSNXPSLPG$PODSFUF
TVJUBCMZRVBMJGJFEQFSTPOPSQFSTPOT % '03"11307"- +#( "+'
$POUSPMKPJOUTTIBMMCFDPOTUSVDUFEBTTQFDJGJFE4BXDVUUJOH $ 5&/%&3*446& +#( "+'
TIBMMCFDBSSJFEPVUXJUIJOIPVSTPGDPODSFUFIBSEFOJOH # 13&-*.*/"3:*446& +#( "+'
$PODSFUFUFTUDZMJOEFSTTIBMMCFQSFQBSFEBTSFRVJSFECZUIF " 13&-*.*/"3:*446& +#( "+'
2EV $ESCRIPTION "Y !PPD $ATE
4VQFSWJTPSBOEUFTUFECZB/"5"SFHJTUFSFEMBCPSBUPSZ !-%.$-%.43
"MMPXBODFTIBMMCFNBEFJOBMMGJOJTIFTGPSNPWFNFOUJO IN ASSOCIATION WITH
DPOTUSVDUJPOKPJOUTBOEFYQBOTJPOKPJOUT
)&"-5)"/%4"'&5:
5IFDPOUSBDUPSTIBMMEFWFMPQ
JNQMFNFOUBOEBENJOJTUFSBXPSLQMBDF
IFBMUIBOETBGFUZQSPHSBNUIBUXJMMFOTVSFUIBUBMMDPOTUSVDUJPO
BDUJWJUJFTBSFQFSGPSNFEUPUIFSFMFWBOUXPSLQMBDFIFBMUIBOETBGFUZ
SFRVJSFNFOUTBOEBOZPUIFSTUBUVUPSZSFRVJSFNFOUT
5IFXPSLQMBDFIFBMUIBOETBGFUZQSPHSBNNVTUCFDPPSEJOBUFEXJUI
BEKPJOJOHQSPQFSUZPXOFSTBOEBMMSFMFWBOUQBSUJFTBTOFDFTTBSZUP
FOTVSFBTBGFCVJMEJOHFOWJSPONFOUBUBMMUJNFT
"RISBANEÚ/FFICE -ACKAYÚ/FFICE
0HÚ ÚÚÚ 0H ÚÚÚ
DN &AX ÚÚÚ &AX ÚÚÚ
DN 3
2 #AIRNSÚ/FFICE 4OWNSVILLEÚ/FFICE
1 0H ÚÚÚ 0H ÚÚÚ
NYN+FUUZ)FBE
0 &AX ÚÚÚ &AX ÚÚÚ
$"5*0
/ /
5:-0 . THIS DRAWING IS COPYRIGHT C DO NOT SCALE DRAWING
*/(+&5
&9*45 ORIGINAL DRAWING IS A1 SIZE.
-
, #LIENT
+ $*7*- 1 -6 4 $0 / 4 5 3 6 $5 *0 / 4
*
) 0ROJECT
'
( $-6.110*/5
& +&55:3&1-"$&.&/5
NYN+FUUZ4UFN
%
$ 1257+
# 4ITLE
"
4536$563"-/05&4
5 45
&216758&7,21
125
7+
AST
PREC STOCK
HEAD 2
P E
" # $ % & ' ( ) * TY
ATIO
N
EL3EV
ST3.04
/
&
/
$QNV
&
/
&
-0$"5*0/1-"/
/
&
)"5-*/&
1*-*/(1-"/
"/0%&5:1&
$0/4536$5*0/*446& +#( "+'
"/0%&5:1& $0/4536$5*0/*446& +#( "+'
( "11307"-*446& +#( "+'
' 13&-*.*/"3:*446& +#( "+'
Structural Column Schedule & (14-0$"5*0/4"%%&% +#( "+'
Column Location Mark Easting Northing % '03"11307"- +#( "+'
$ 5&/%&3*446& +#( "+'
A-2 405229.552757 8026136.123710 # 13&-*.*/"3:*446& +#( "+'
A-3 405230.440214 8026132.634807 " 13&-*.*/"3:*446& +#( "+'
2EV $ESCRIPTION "Y !PPD $ATE
B-2 405239.235868 8026138.601086 !-%.$-%.43
B-3 405240.128169 8026135.113422 IN ASSOCIATION WITH
C-2 405248.923823 8026141.079700
C-3 405249.816124 8026137.592037
D-2 405258.611777 8026143.558315
D-3 405259.504079 8026140.070651
E-2 405268.299732 8026146.036930
E-3 405269.192034 8026142.549266
/
H-3 405298.255898 8026149.985111
&
I-2 405307.051552 8026155.951389
I-3 405307.943853 8026152.463725
"RISBANEÚ/FFICE -ACKAYÚ/FFICE
J-2 405316.739506 8026158.430004
0HÚ ÚÚÚ 0H ÚÚÚ
J-3 405317.631808 8026154.942340 &AX ÚÚÚ &AX ÚÚÚ
K-2 405326.427461 8026160.908619
UP
#AIRNSÚ/FFICE 4OWNSVILLEÚ/FFICE
DN K-3 405327.319762 8026157.420955
0H ÚÚÚ 0H ÚÚÚ
L-2 405336.115416 8026163.387234 &AX ÚÚÚ &AX ÚÚÚ
L-3 405337.007717 8026159.899570
M-2 405345.803371 8026165.865848 THIS DRAWING IS COPYRIGHT C DO NOT SCALE DRAWING
+ , - . / 0 1 2 3 ORIGINAL DRAWING IS A1 SIZE.
M-3 405346.695672 8026162.378185 #LIENT
N-2 405355.491326 8026168.344463
N-3 405356.383627 8026164.856799
$*7*- 1 -6 4 $0 / 4 5 3 6 $5 *0 / 4
O(5.000)-6 405371.436068 8026166.535407
1*-*/(1-"/ 0ROJECT
O-2 405365.179280 8026170.823078 $-6.110*/5
/05&
O-3
O-6
405366.071582
405366.592091
8026167.335414
8026165.2961
+&55:3&1-"$&.&/5
Ê 1307*%&4503.5*%&(6"(&1-"5'03.)064*/(*/"$$03%"/$&8*5) P(5.000)-6 405381.124023 8026169.014022
%4*5*"41&$*'*$"5*0/ %8(TBOE.*4$
P-2 405374.867235 8026173.301693
4ITLE
Ê 1307*%&'*3&8"5&3)04&3&&-4"54&37*$&-0$"5*0/4"-0/(+&55: P-3 405375.759537 8026169.814029
P-6 405376.280046 8026167.774715 1*-*/(-":0651-"/
Ê 1307*%&108&350+&55:)&"%
Q(5.000)-6 405390.811978 8026171.492637
Ê 1307*%&-*()5*/(50+&55:)&"%
Q-2 405384.555190 8026175.780308
Ê 1307*%&105"#-&8"5&3"5+&55:4&37*$&-0$"5*0/4 Q-3 405385.447491 8026172.292644 $ESIGN "+' $RAWN +#(
Ê 1307*%&"$$&44-"%%&34"-0/(5)&+&55:*/"$$03%"/$&8*5) Q-6 405385.968001 8026170.253329 #HECKED "+' $ATE ./6Ú
20%1Ú.O $ATUM
"4 R-2 405394.243145 8026178.258922
R-3 405395.135446 8026174.771259 !PPROVED
R-6 405395.655955 8026172.731944 *OBÚ.UMBER $RAWINGÚ.O 2EVISION
5 45
&216758&7,21
6MU$BQBDJUZ
$PNQSFTJPO L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/
5FO5FOTJPO L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/
1SPQFSUJFT
%JB NN NN NN NN NN NN NN NN NN NN NN NN NN NN NN NN NN NN
5IJDLOFTT 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1-
%FQUI 3-
$0/4536$5*0/*446& +#( "+'
' "11307"-*446& +#( "+'
" " # # $ $ % % & & ' ' ( ( ) ) * * & 13&-*.*/"3:*446& +#( "+'
$PMVNO-PDBUJPOT
1SPQFSUJFT
% '03"11307"- +#( "+'
%JB NN NN NN NN NN NN NN NN NN NN NN NN NN NN NN NN NN NN $ 5&/%&3*446& +#( "+'
5IJDLOFTT 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- 1- # 13&-*.*/"3:*446& +#( "+'
%FQUI 3-
6MU$BQBDJUZ " 13&-*.*/"3:*446& +#( "+'
$PNQSFTJPO L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ 2EV $ESCRIPTION "Y !PPD $ATE
5FO5FOTJPO L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ L/ !-%.$-%.43
5PQPG1JMF 5PQPG1JMF
IN ASSOCIATION WITH
-"53- -"53-
"RISBANEÚ/FFICE -ACKAYÚ/FFICE
0HÚ ÚÚÚ 0H ÚÚÚ
&AX ÚÚÚ &AX ÚÚÚ
#AIRNSÚ/FFICE 4OWNSVILLEÚ/FFICE
0H ÚÚÚ 0H ÚÚÚ
&AX ÚÚÚ &AX ÚÚÚ
4ITLE
1*-*/(4$)&%6-&
$ESIGN %FTJHOFS $RAWN "VUIPS
#HECKED $IFDLFS $ATE ./6Ú
20%1Ú.O "QQSPWFS $ATUM
!PPROVED
*OBÚ.UMBER $RAWINGÚ.O 2EVISION
5 45
$PMVNO-PDBUJPOT + + , , - - . . / / 0 0 1 1 2 2 3 3 &216758&7,21
3-N 3-N
%FFQFTU %FFQFTU
QPJOUPG QPJOUPG
KFUUZ KFUUZ
3- 3-
1SPQFSUJFT
%JB NN NN NN NN NN NN NN
5IJDLOFTT 1- 1- 1- 1- 1- 1- 1-
6MU$BQBDJUZ
$PNQSFTJPO L/ L/ L/ L/ L/ L/ L/
5FO5FOTJPO L/ L/ L/ L/ L/ L/ L/
"RISBANEÚ/FFICE -ACKAYÚ/FFICE
0HÚ ÚÚÚ 0H ÚÚÚ
&AX ÚÚÚ &AX ÚÚÚ
#AIRNSÚ/FFICE 4OWNSVILLEÚ/FFICE
0H ÚÚÚ 0H ÚÚÚ
&AX ÚÚÚ &AX ÚÚÚ
4ITLE
'&/%&31*-&4
1*-*/(5"#-&
5 45
&216758&7,21
3
2
1
0
/
.
-
,
+
*
)
(
'
&
%
$
#
"
+&55:'3".*/(1-"/
)&"%450$,5:1&
108&3-0$"5*0/
)&"%450$,5:1&
')
13&$"45%&$,1"/&-5:1&
3
2 -*()5-0$"5*0/
')'*3&):%3"/5-0$"5*0/ 3&'&3
):%3"6-*$$0/4"-5"/54'03 108&3-0$"5*0/ 1
3&26*3&.&/54
0
')3'*3&):%3"/53&&--0$"5*0/ /
3&'&3 ):%3"6-*$$0/4"-5"/54
')3 . "RISBANEÚ/FFICE -ACKAYÚ/FFICE
'033&26*3&.&/54
, #AIRNSÚ/FFICE 4OWNSVILLEÚ/FFICE
0H ÚÚÚ 0H ÚÚÚ
+ &AX ÚÚÚ &AX ÚÚÚ
5 45
&216758&7,21
" # $ % & ' ( )
3".150&9*45*/(
5PQPG)BOESBJM $"31"3,
+FUUZ''-3-N
)"53-
.)843-
-"53-
%FFQFTUQPJOUPGKFUUZ
3-
3-
3-
3-
/035)&3/&-&7"5*0/
* + , - . / 0 1 2 3
5PQPG)BOESBJM
+FUUZ''-3-N
3-N
)"53- $0/4536$5*0/*446& +#( "+'
' "11307"-*446& +#( "+'
& 13&-*.*/"3:*446& +#( "+'
.)843-
% '03"11307"- +#( "+'
$ 5&/%&3*446& +#( "+'
# 13&-*.*/"3:*446& +#( "+'
" 13&-*.*/"3:*446& +#( "+'
2EV $ESCRIPTION "Y !PPD $ATE
-"53-
!-%.$-%.43
IN ASSOCIATION WITH
,&3#
1
ST2.02
.#0-58*5)YY
1-8"4)&35:1
+FUUZ''-3-N 8&#'03(&)"/%3"*-#"4&1-
5PQPG(JSEFS
%&5"*-
(*%&3#&". (*%&3#&". 45
1307*%&$"45*/'&336-&4"5 /501 /501
41&$*'*&%$&/53&4'034&37*$&
53":"/%4&37*$&4 /45*33614
NN$07&3 /45*33614
NN$07&3
1307*%&$"45*/'&336-&4"5
/ &"$)'"$&
/ &"$)'"$&
41&$*'*&%$&/53&4'03'6563&
.1B$0/$3&5&NN .1B$0/$3&5&NN )"/(*/(%*&4&-1*1&-*/&
$07&3"--306/% $07&3"--306/% $- $-
-":&340'/#0550. -":&340'/#0550.
.*/*.6.NN7&3541"$*/( .*/*.6.NN7&3541"$*/(
5PQ0G)FBE4UPDL )&"%450$,
-":&34/501
YY&-"450.&3*$#&"3*/(
1"%48*5)NN%JB)0-&
/ &"$)'"$&
/-*(4!."9$34 .(3"%&5)3&"%&%30%8*5)
.1B$0/$3&5&
NN .(3"%&8*5)YY /65Y428"4)&350501
$07&3"--306/% 1-8"4)&3"/%/654(3065
5PQPG1JMF -":&34/#0550. '*--"'5&3*/45"--"5*0/ 70*%4*/)&"%450$,50#&
(3065'*--&%"'5&3
NN1-"5& )&"%450$,&3&$5*0/
(3"%&
NN$'8 (1&YY8Y
5"$,8&-%/654501-"5&
Y$)41*-&
.(3"%&
!NN$34
5:1*$"-%&5"*-
)&"%450$,3&*/'03$&.&/5 $0/4536$5*0/*446& +#( "+'
' "11307"-*446& +#( "+'
& 13&-*.*/"3:*446& +#( "+'
% '03"11307"- +#( "+'
$ 5&/%&3*446& +#( "+'
3-N # 13&-*.*/"3:*446& +#( "+'
" 13&-*.*/"3:*446& +#( "+'
2EV $ESCRIPTION "Y !PPD $ATE
!-%.$-%.43
IN ASSOCIATION WITH
13&$"45$0/$3&5&%&$,
.1B(3"%&$0/$3&5&
+FUUZ''-3-N
5PQPG(JSEFS
(*%&3#&". (*%&3#&".
/501 /501
#AIRNSÚ/FFICE 4OWNSVILLEÚ/FFICE
0H ÚÚÚ 0H ÚÚÚ
&AX ÚÚÚ &AX ÚÚÚ
5 45
&216758&7,21
/!NN-*(4 /!NN-*(4 /!NN-*(4
/!NN-*(4 /!NN-*(4
'03 '03
'03 '03
Y$)4 (3"%&
Y$)4 (3"%&
8*5)%JB10-:&5):-&/&*/5&3/"-4-&&7& 8*5)%JB10-:&5):-&/&*/5&3/"-4-&&7&
/
.'&336-&4!."9$34 104*5*0/50"70*%45*33614
1&3%&$,1"/&-&"$)4*%& 5PQPG(JSEFS
5PQ0G)FBE4UPDL
YY&-"450.&3*$#&"3*/( /Y-0/(
/Y-0/(
/
/ &"$)'"$&
YY&-"450.&3*$#&"3*/(
1"%48*5)NN%JB)0-& 1"%48*5)NN%JB)0-&
.(3"%&5)3&"%&%30%8*5) .(3"%&5)3&"%&%30%8*5)
/65Y428"4)&350501 /65Y428"4)&350501
5PQPG1JMF
(*%&3#&".&-&7"5*0/
.1B$0/$3&5&NN
2 $07&3"--306/%
ST2.03
NN$'8501&3*.&5&3
NN1-"5&
(3"%&
NN1-"5&5"#4
5046110351-"5&
$'8501*-&
1*-&8"--
#&"3*/(1-"5&%&5"*-
$0/4536$5*0/*446& +#( "+'
70*%4'03.)%#0-54
& "11307"-*446& +#( "+'
%&5"*- % 13&-*.*/"3:*446& +#( "+'
45 $ '03"11307"- +#( "+'
5)*$,
# 5&/%&3*446& +#( "+'
.1B$0/$3&5&%&$, " 13&-*.*/"3:*446& +#( "+'
2EV $ESCRIPTION "Y !PPD $ATE
!-%.$-%.43
IN ASSOCIATION WITH
5:1*$"-%&5"*-
%&$,6/*5
"RISBANEÚ/FFICE -ACKAYÚ/FFICE
0HÚ ÚÚÚ 0H ÚÚÚ
&AX ÚÚÚ &AX ÚÚÚ
#AIRNSÚ/FFICE 4OWNSVILLEÚ/FFICE
0H ÚÚÚ 0H ÚÚÚ
.Y444&54$3&8
3&'&3$03304*0/41&$*"-&4515:-5% .Y444&54$3&88&-%&%501*-& 3&'&3$03304*0/41&$*"-&4515:-5%
$&35*'*&%4,&5$)&4'0341&$*'*$"5*0/4 .06/5"/0%&48*5)413*/(8"4)&3"/%/654 $&35*'*&%4,&5$)&4'0341&$*'*$"5*0/4 0ROJECT
5:1*$"-)"/%3"*-%&5"*- $-6.110*/5
-"5
+&55:3&1-"$&.&/5
4&"#&%
.*/
4ITLE
%&5"*-4
Y.4'-"5#"3Y-0/(
"--6.*/*6."--0:"/0%&YY
"/0%&*/4&35%JB.430%8*5) YY 8*5)'-"5#"3*/4&358&-%50
.&53&&95&/4*0/"/%%3*--&%'-"5 Y'-"5#"3
#"3'03#0-5*/(501*-& "--6.*/*6."--0:"//0%& $ESIGN %FTJHOFS $RAWN "VUIPS
#HECKED $IFDLFS $ATE
./6Ú
20%1Ú.O "QQSPWFS $ATUM
!PPROVED
*OBÚ.UMBER $RAWINGÚ.O 2EVISION
"/0%&5:1& "/0%&5:1& 5 45
&216758&7,21
0 1
UP
DN DN
45"*3-":0651-"/
5PQPG(JSEFS
(*3%&3 #&)*/%
)"53-
5PQ0G)FBE4UPDL
5PQPG1JMF
"RISBANEÚ/FFICE -ACKAYÚ/FFICE
2.770
0HÚ ÚÚÚ 0H ÚÚÚ
.)843- &AX ÚÚÚ &AX ÚÚÚ
#AIRNSÚ/FFICE 4OWNSVILLEÚ/FFICE
0H ÚÚÚ 0H ÚÚÚ
&AX ÚÚÚ &AX ÚÚÚ
4ITLE
45"*3%&5"*-4
%JB70*%4
3&*/'03$&.&/5 3&*/'03$&.&/5
07&3"--
07&3"--
"4/05&%
-*'5&34
$&/530*% 70*%4 %JB70*%4*/,&3# "-5&3/"5*7&3&*/' "-5&3/"5*7&3&*/'
9 :
#"33*&3,&3# "%%*5*0/"-3&*/'03$&.&/5 "%%*5*0/"-3&*/'03$&.&/5
: 9 Y%3"*/"(&70*%4
-&(&/% 1&3*.&5&3#"34 1&3*.&5&3#"34
13&$"45%&$,
T .*/$0/$3&5&$07&3 .*/$0/$3&5&$07&3
T
NN
%&/05&448*'5-*'5 GDU !-*'5
GDU !-*'5
"4/05&%
"3&" "3&"
%&/05&448*'5-*'5 4-501#5. %JB 426"3&.&5&34 426"3&.&5&34
50//&YNN4)035'005
%JB
"/$)03.*/*.6/.1B /#5.
70-6.& 70-6.&
$6#*$.&5&34 $6#*$.&5&34
$0/$3&5&453&(5)"5-*'5
8&*()550//&4 8&*()550//&4
T &%(&-*'54 &%(&-*'54
T
Y
Y
'"$&-*'54 '"$&-*'54
Y Y
Y Y
-*'5&34 Y Y
Y Y
Y Y
5:1*$"-$0/'*3(63"5*0/ 1"/&-1-"/ %JB 3&*%3&#"5&%'&336-&4 3&*%3&#"5&%'&336-&4
/54 3#3* 3#3*
)0-%%08/3&#"5&470*%4%&$, 3#3*
3#3*
3#3*
3#3*
%&/05&448*'5-*'5 3&*%5)3&"%&%'&336-&4 3&*%5)3&"%&%'&336-&4
50//&YNN"/$)03 3#5* 3#5*
.*/*.6/.1B$0/$3&5& 3#5* 3#5*
453&(5)"5-*'5 3#5* 3#5*
3#5* 3#5*
-*'5&3"4/05&% $061-&33&*%#"3 $061-&33&*%#"3
3#$ 3#$
%&/05&448*'5-*'5 4-.&4)
NN501$07&3
17$4-&&7& 17$4-&&7&
50//&YNN"/$)03 501 501
.*/*.6/.1B$0/$3&5& #"33*&3,&3# %JB70*%4*/,&3# NN(306556#& NN(306556#&
453&(5)"5-*'5 #5. #5.
3&#"5&4 NN
3&#"5&4 NN
T ¬
%&/05&448*'5-*'5 13015:1& 13015:1&
50//&YNN4)035'005
"/$)03.*/*.6/.1B 1301&''&$5*7&-&/(5) 1301&''&$5*7&-&/(5)
/#0550.&953"1-"$&%0/ 4-.&4)
NN#0550.$07&3
$0/$3&5&453&(5)"5-*'5 .&4)
#&58&&/8*3&4 /05&8*3&104*5*0/ '&336-&4 '&336-&4
')() ')()
')44 ')44
13015:1&
13&$"45%&$,1"/&- 13015:1&/"
13015:1&/"
07&3"--
-*'5&34
"4/05&%
70*%4
$&/530*% -*'5&34 "-5&3/"5*7&3&*/' "-5&3/"5*7&3&*/'
)&"%450$,
9 :
-":&34/501 "%%*5*0/"-3&*/'03$&.&/5 "%%*5*0/"-3&*/'03$&.&/5
:
9
-&(&/% 1&3*.&5&3#"34 1&3*.&5&3#"34
/ &"$)'"$&
/-*(4!."9$34
.1B$0/$3&5&
NN .*/$0/$3&5&$07&3 .*/$0/$3&5&$07&3
$07&3"--306/% NN
%&/05&448*'5-*'5 GDU !-*'5
GDU !-*'5
50//&YNN4)035'005 -":&34/#0550.
.*/*.6.NN7&35*$"-41"$*/( .1B
"/$)03.*/*.6/.1B GD GD
$0/$3&5&453&(5)"5-*'5 .1B
1"/&-5)*$,/&44 1"/&-5)*$,/&44
4&"8"3%'"$&
"4/05&%
"3&" "3&"
%&/05&448*'5-*'5
50//&YNN4)035'005 13&$"45)&"%450$,4&$5*0/ 426"3&.&5&34
426"3&.&5&34
&%(&-*'54 &%(&-*'54
Y
Y
'"$&-*'54 '"$&-*'54
Y Y
%JB70*%4 Y Y
'&336-&4
3&*%3&#"5&%'&336-&4 3&*%3&#"5&%'&336-&4
/54 3#3* 3#3*
)0-%%08/3&#"5&470*%4)&"%450$, 3#3*
3#3*
3#3*
3#3*
%&/05&448*'5-*'5 3&*%5)3&"%&%'&336-&4 3&*%5)3&"%&%'&336-&4
50//&YNN"/$)03
07&3"-- 3#5* 3#5*
.*/*.6/.1B$0/$3&5& -*'5&3"4/05&% 3#5* 3#5*
453&(5)"5-*'5 Y%JB 3#5* 3#5*
70*%4 3#5* 3#5*
'&336-&4 $061-&33&*%#"3 $061-&33&*%#"3
3#$ 3#$
%&/05&448*'5-*'5 17$4-&&7& 17$4-&&7&
Y%JB70*%
50//&YNN"/$)03 501 501
.*/*.6/.1B$0/$3&5& NN(306556#& NN(306556#&
453&(5)"5-*'5 #5. #5.
3&#"5&4 NN
3&#"5&4 NN
T ¬
%&/05&448*'5-*'5
13015:1& 13015:1&
50//&YNN4)035'005
"/$)03.*/*.6/.1B 1301&''&$5*7&-&/(5) 1301&''&$5*7&-&/(5)
$0/$3&5&453&(5)"5-*'5 '&336-&4 '&336-&4
-*'5&34 ')() ')()
')44 ')44
%JB70*%4 13015:1&
13015:1&/"
5:1*$"-&-&7"5*0/ 13015:1&/"
"RISBANEÚ/FFICE -ACKAYÚ/FFICE #LIENT $*7*-1-64$0/4536$5*0/4 $ESIGN !*& THIS DRAWING IS &216758&7,21
0HÚ ÚÚÚ 0H ÚÚÚ $RAWN *"' COPYRIGHT C DO *OBÚ.UMBER $RAWINGÚ.O
0ROJECT $-6.110*/5
&AX ÚÚÚ
#AIRNSÚ/FFICE
&AX ÚÚÚ
4OWNSVILLEÚ/FFICE 4ITLE
$0/4536$5*0/*446&
$0/4536$5*0/*446&
+#(
+#(
"+'
"+'
$ATE
#HECKED
*!.Ú NOT SCALE DRAWING
!*&
ORIGINAL DRAWING IS 5 45
13&$"45)&"%450$,5:1& A3 SIZE.
2EVISION
0H ÚÚÚ 0H ÚÚÚ 2EV $ESCRIPTION "Y !PPD $ATE !PPROVED !*& !PPROVED
&AX ÚÚÚ &AX ÚÚÚ !-%.$-%.43 20%1Ú.O
*/45"-- $)&$,&%
)%3&#"5&70*%4
3&*/'03$&.&/5 3&*/'03$&.&/5
07&3"-- "4/05&%
$&/530*% "-5&3/"5*7&3&*/' "-5&3/"5*7&3&*/'
07&3"--
-*'5&34
-*'5&34
9 :
"%%*5*0/"-3&*/'03$&.&/5 "%%*5*0/"-3&*/'03$&.&/5
: 9
-&(&/% 1&3*.&5&3#"34 1&3*.&5&3#"34
.*/$0/$3&5&$07&3 .*/$0/$3&5&$07&3
.'&336-&
NN
%&/05&448*'5-*'5 GDU !-*'5
GDU !-*'5
50//&YNN4)035'005 )0-%%08/3&#"5&470*%4
.1B
"/$)03.*/*.6/.1B GD GD
$0/$3&5&453&(5)"5-*'5 .1B
13&$"45(*3%&3#&". /05&
1"/&-5)*$,/&44 1"/&-5)*$,/&44
%JB "4/05&%
.*%41"/')()'&336-&4
"3&" "3&"
504&"8"3%4*%&0'(*3%&34
%JB
%&/05&448*'5-*'5 426"3&.&5&34 426"3&.&5&34
0/(3*%0/-:'03'6563&
50//&YNN4)035'005
%&*4&--*/&
"/$)03.*/*.6/.1B 70-6.& 70-6.&
$6#*$.&5&34 $6#*$.&5&34
$0/$3&5&453&(5)"5-*'5 (*%&3#&".
/501 8&*()550//&4 8&*()550//&4
/45*33614
NN$07&3
&%(&-*'54 &%(&-*'54
Y
/ &"$)'"$&
Y
.1B$0/$3&5&NN
$07&3"--306/% '"$&-*'54 '"$&-*'54
Y Y
-":&340'/#0550. Y Y
.*/*.6.NN7&3541"$*/( Y Y
%JB Y Y
Y Y
5:1*$"-$0/'*3(63"5*0/ 13&$"45(*3%&3#&".4&$5*0/ )0-%%08/3&#"5&470*%4(*3%&3 3&*%3&#"5&%'&336-&4 3&*%3&#"5&%'&336-&4
/54 3#3* 3#3*
3#3* 3#3*
3#3* 3#3*
%&/05&448*'5-*'5 3&*%5)3&"%&%'&336-&4 3&*%5)3&"%&%'&336-&4
50//&YNN"/$)03 3#5* 3#5*
.*/*.6/.1B$0/$3&5& 3#5* 3#5*
453&(5)"5-*'5 3#5* 3#5*
3#5* 3#5*
$061-&33&*%#"3 $061-&33&*%#"3
/!NN-*(4
/!NN-*(4
/!-*(4
/!NN-*(4
/!NN-*(4 3#$ 3#$
%&/05&448*'5-*'5 '03 '03 17$4-&&7& 17$4-&&7&
50//&YNN"/$)03 '03 '03 501 501
.*/*.6/.1B$0/$3&5& /
NN(306556#& NN(306556#&
453&(5)"5-*'5 #5. #5.
T ¬
%&/05&448*'5-*'5 13015:1& 13015:1&
50//&YNN4)035'005
"/$)03.*/*.6/.1B 1301&''&$5*7&-&/(5) 1301&''&$5*7&-&/(5)
/Y-0/(
/
/ &"$)'"$&