Activities for planning and scheduling of a building construction (building utility) project
can be categorized as follows:-
1 Engineering
2 Construction
3 Testing & Commissioning
All construction activities are basically distributed into three types of installation groups:
First fix activities are those activities which start along with block work and continue till
completion of plaster work.
Second fix activities are the major part of the building utility systems. These activities are starts
after completion of plaster. Most of the civil construction activities are depends upon these
activities. For example to start the false ceiling grid work, building utility high level work must
finish.
Final fix activities generally cover all the exposed items i.e. electrical light fixtures, grilles &
diffusers, sprinkler etc.
Final fix- fixing fire alarm & light fittings, fixing switches, socket & accessories.