You are on page 1of 50

4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Flat 15% OFF | Sitewide | Use Coupon - WHIZOFFER15 (https://www.whizlabs.com/) 


 (https://www.whizlabs.com/learn)  My Courses (https://www.whizlabs.com/learn/my-courses)
 Professional Scrum Master I (https://www.whizlabs.com/learn/course/psm-i-practice-tests#section-1)
 Diagnostic Test (https://www.whizlabs.com/learn/course/psm-i-practice-tests/quiz/14890)  Report

DIAGNOSTIC TEST

Attempt 1

Marks Obtained 42 / 80

Your score is 52.5%

Mode Exam

Completed on Monday , 22 April 2019 , 06:04 PM

Time Taken 00 H 44 M 50 S

Result Fail

Domains / Skills wise Quiz Performance Report

S-No: 1

Topic: Scrum Events

Total-Questions: 16

Right: 9

Wrong: 7

Unattempted1: 0

Markedforreview: 0

S-No: 2
https://www.whizlabs.com/learn/course/quiz-result/29340 1/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Topic: Sprint Scenarios

Total-Questions: 15

Right: 8

Wrong: 7

Unattempted1: 0

Markedforreview: 2

S-No: 3

Topic: Scrum Artifacts

Total-Questions: 9

Right: 4

Wrong: 5

Unattempted1: 0

Markedforreview: 0

S-No: 4

Topic: Scrum Team

Total-Questions: 15

Right: 6

Wrong: 9

Unattempted1: 0

Markedforreview: 0

S-No: 5

Topic: Scrum Theory

Total-Questions: 17

Right: 10

Wrong: 7

Unattempted1: 0

Markedforreview: 1

S-No: 6
https://www.whizlabs.com/learn/course/quiz-result/29340 2/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Topic: Sprint Goal

Total-Questions: 1

Right: 1

Wrong: 0

Unattempted1: 0

Markedforreview: 0

S-No: 7

Topic: Definition of Done

Total-Questions: 5

Right: 3

Wrong: 2

Unattempted1: 0

Markedforreview: 0

S-No: 8

Topic: Other

Total-Questions: 1

Right: 0

Wrong: 1

Unattempted1: 0

Markedforreview: 0

S-No: 9

Topic: Velocity

Total-Questions: 1

Right: 1

Wrong: 0

Unattempted1: 0

Markedforreview: 0

Total: Total
https://www.whizlabs.com/learn/course/quiz-result/29340 3/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

All Domain: All Domain

Total Questions: 80

Correct: 42

Incorrect: 38

Unattempted: 0

Unattempted: 3

Show Answers

All

QUESTION 1 INCORRECT SCRUM EVENTS

Daily Scrum is a key inspect and adapt meeting– True or False?

A. True 

B. False 

Explanation :
The correct answer is true.
 
Daily Scrum is an important inspect and adapt meeting. It provides an opportunity to the
development team to identify any deviation and take remedial actions, every day.
 
Reference:
More details on Daily Scrum can be found at :
https://scrumguides.org/scrum-guide.html#events-daily (https://scrumguides.org/scrum-
guide.html#events-daily)

Ask our Experts

 

QUESTION 2 INCORRECT SCRUM EVENTS


https://www.whizlabs.com/learn/course/quiz-result/29340 4/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Which of the following are discussed in Sprint review meeting? (Select all that
apply).

A. Development team discusses what went well during the Sprint, problems it ran into and how they were
resolved 

 B. Development Team demonstrates the work done in the Sprint 

 C. Product Owner explains which items are "Done" and which items are not "Done" 

 D. Review of the deliverable product 

Explanation :
The correct answer is Options A, B and C.
 
Sprint review in an informal meet to demonstrate the work done and elicit feedback. During Sprint
Review, the team also discusses what went well during the sprint, and the problems and their solutions
that they might have encountered. It is also an opportunity for the PO to review the available budget.
 
Reference:
More details on Sprint review can be found at :
https://scrumguides.org/scrum-guide.html#events-review (https://scrumguides.org/scrum-
guide.html#events-review)

Ask our Experts

 

QUESTION 3 MARKED AS REVIEW INCORRECT SPRINT SCENARIOS

What happens when a Sprint is cancelled? (Select all that apply)

A. Any completed and “Done” Product Backlog items are reviewed 

 B. All incomplete Product Backlog Items are re-estimated and put back on the Product Backlog 

 C. If part of the work is potentially releasable, the Product Owner typically accepts it 

 D. Several top Product Backlog Items are taken into the Sprint Backlog to replace the obsolete items 

Explanation :
https://www.whizlabs.com/learn/course/quiz-result/29340 5/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
p
The correct answer is Options A, B and C.
 
In the unlikely event where a Sprint is cancelled, the normal course of action includes reviewing of
“done” items, re-estimating the incomplete items and placing them back in the backlog and if the work
is potentially releasable, the PO usually accepts it.

Ask our Experts

 

QUESTION 4 CORRECT SCRUM EVENTS

User story point system is the best method for estimating user stories for all the
scrum teams – True or False?

A. True

B. False 

Explanation :
The correct answer is Option B (False).
 
User story point system is one of the popular ways for estimating user stories, but it depends on the
individual scrum teams which method suits them the best. Another example of a method for
estimating user stories is T-Shirt sizing.

Ask our Experts

 

QUESTION 5 INCORRECT SCRUM ARTIFACTS

Who determines when it is appropriate to update the Sprint Backlog during a


Sprint?

A. Product Owner

https://www.whizlabs.com/learn/course/quiz-result/29340 6/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

B. Project Manager

C. Scrum Master 

D. Development Team 

Explanation :
Correct Answer –D
Development team is the owner of the Sprint backlog, and seeing that they are also self-organizing, they
decide when it is appropriate the Sprint backlog.
More details on Sprint backlog can be found at h ps://scrumguides.org/scrum-guide.html#ar facts-
sprintbacklog (h ps://scrumguides.org/scrum-guide.html#ar facts-sprintbacklog)

Ask our Experts

 

QUESTION 6 INCORRECT SCRUM TEAM

Development teams larger than 9 members are not advised by Scrum because
_______. (Select all that apply)

A. It requires too much co-ordina on 

 B. Too much complexity is generated 

 C. It becomes difficult for the Scrum Master to manage a large team 

D. Scrum does not men on any specific upper limit for Development Team size

Explanation :
Correct Answer – A, B
Large development teams usually bring in more complexity and requires too much co-ordina on. Scrum
has found that development teams larger than 9 members usually face these issues.
More details on the Development team can be found at h ps://scrumguides.org/scrum-
guide.html#team-dev (h ps://scrumguides.org/scrum-guide.html#team-dev)

Ask our Experts

 
https://www.whizlabs.com/learn/course/quiz-result/29340 7/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
 

QUESTION 7 CORRECT SPRINT SCENARIOS

If some tasks or user stories are not completed in the current sprint, what is to be
done?

A. The incomplete tasks/user stories are pushed to the next Sprint over and above the planned tasks

B. The tasks/user stories are moved to Product backlog and are re-evaluated by the Product Owner,
who then decides the next course of ac on 

C. The user stories/tasks are pushed to the bo om of the product backlog and is worked upon when
other items are completed

D. The tasks/user stories are cancelled

Explanation :
Correct Answer – B
If some tasks or user stories are completed in the current sprint, i.e. you have sprint leakage, they are
moved to the Product Backlog and the PO decides what needs to done with them.

Ask our Experts

 

QUESTION 8 CORRECT SCRUM THEORY

Scrum is founded on_______.

A. Six Sigma principles

B. Empiricism 

C. Common Sense

D. Lean

Explanation :
Correct Answer – B
f d d l
https://www.whizlabs.com/learn/course/quiz-result/29340 l h 8/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
Scrum is founded on empirical process control theory or empiricism.

Ask our Experts

 

QUESTION 9 INCORRECT SCRUM EVENTS

What are the mandatory questions that are asked in the Daily Scrum Call?

A. What was done yesterday? 

B. What will be done today?

C. Are there any impediments?

D. None of them 

Explanation :
The correct answer is D
The structure of the meeting is set by the Development Team and can be conducted in different ways
if it focuses on progress toward the Sprint Goal. Some Development Teams will use questions, some
will be more discussion based. Here is an example of what might be used:

What did I do yesterday that helped the Development Team meet the Sprint Goal?

What will I do today to help the Development Team meet the Sprint Goal?

Do I see any impediment that prevents me or the Development Team from meeting the
Sprint Goal?

So as such, there are no mandatory questions to be answered during Daily Scrum.


More details on the Daily Scrum can be found at http://www.scrumguides.org/scrum-
guide.html#events-daily (http://www.scrumguides.org/scrum-guide.html#events-daily)

Ask our Experts

 

QUESTION 10 CORRECT SCRUM THEORY

Scrum is composed of_____? (Select all that apply)


https://www.whizlabs.com/learn/course/quiz-result/29340 9/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

 A. Roles 

 B. Artifacts 

 C. Events 

D. Sprint

Explanation :
Correct Answer – A, B, C
Scrum consists of roles, events, artifacts, and the rules that bind them together.

Ask our Experts

 

QUESTION 11 CORRECT SCRUM THEORY

There should not be a separate backlog refinement session as it is an overhead


causing wastage – True or False?

A. True

B. False 

Explanation :
Correct Answer – B
 
Backlog refinement session has been found to be very effective by a lot of scrum teams. It helps in
clearing up a lot of unknowns which further help in Sprint planning.

Ask our Experts

 

QUESTION 12 CORRECT SPRINT SCENARIOS


https://www.whizlabs.com/learn/course/quiz-result/29340 10/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Inspection can done at any time during a Sprint, but adaptation should always be
reserved for the next sprint as it might break the rhythm of the development team
– True or False

A. True

B. False 

Explanation :
Correct Answer – B
Adaptation should be done at the earliest possible opportunity, and unless it endangers the Sprint
Goal, it should be done as soon as possible.

Ask our Experts

 

QUESTION 13 MARKED AS REVIEW INCORRECT SCRUM THEORY

How did Scrum possibly came up with the number of development team size of 3-9
members?

A. Scrum founders thought this range is appropriate and enforced it. 

B. Most scrum teams follow this so it became used as the standard.

C. Empiricism was used to come to this range. 

D. It must have been just an abstract range that was used to begin with, and scrum stuck with it.

Explanation :
Correct Answer – C
Empiricism is basically taking decisions based on what is known. This is at the heart of the Scrum, and
everything that we follow in Scrum comes from the experiences of many industry best prac ces, and the
problems that was faced, and the route taken to subsequently overcome it.
Similarly it was observed that a team size between 3 and 9 members gave the desirable results of having
all the skills within the team, and also keeping the disadvantages of a large team at bay.

https://www.whizlabs.com/learn/course/quiz-result/29340 11/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Ask our Experts

 

QUESTION 14 INCORRECT SCRUM TEAM

Development team exhibits these characteris cs: (Select all that apply)

A. Individual accountability

 B. self-organizing 

 C. un-structured 

 D. cross-func onal 

Explanation :
Correct Answer – B, D
Development team is self-organizing and cross-func onal.

Ask our Experts

 

QUESTION 15 CORRECT SCRUM TEAM

Who ensures that the Development Team understands the items in the Product
Backlog to the level needed?

A. Scrum Master

B. Product Owner 

C. Technical advisor

D. Domain expert

Explanation :
Correct Answer – B
h ’ bl k
https://www.whizlabs.com/learn/course/quiz-result/29340 h h d l d d h h 12/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
It is the PO’s responsibility to make sure that the development team understands the items in the
product backlog to the required level.
More details on PO and his responsibili es can be found at h ps://scrumguides.org/scrum-
guide.html#team-po (h ps://scrumguides.org/scrum-guide.html#team-po)

Ask our Experts

 

QUESTION 16 CORRECT SCRUM THEORY

According to the Scrum Guide, what are the roles in the Scrum team? (Select all that
apply)

A. Business Analyst

 B. Product Owner 

C. Automa on Testers

 D. Scrum Master 

Explanation :
Correct Answer – B, D
According to the Scrum Guide, there are three roles in the Scrum team : Product Owner, Scrum Master
and the Development Team.

Ask our Experts

 

QUESTION 17 INCORRECT SCRUM TEAM

According to Scrum, Product owner is ALWAYS a single person – True or False?

A. True 

B. False 

https://www.whizlabs.com/learn/course/quiz-result/29340 13/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Explanation :
Correct Answer – A
Yes, Product Owner is always is single person, though he may represent mul ple stakeholders.
More about PO can be found at
h ps://scrumguides.org/scrum-guide.html#team-po (h ps://scrumguides.org/scrum-guide.html#team-
po)

Ask our Experts

 

QUESTION 18 INCORRECT SPRINT SCENARIOS

It is normal to have a “hardening” Sprint to remove all technical debt and prepare
the Product for upcoming release – True or False?

A. True 

B. False 

Explanation :
 
Correct Answer – B
Explanation:
Scrum does not prescribe any “hardening” Sprint, or the likes for the removal of technical debt or for
regression testing, for instance. A Sprint in Scrum should result in an increment of the product. So if a
Sprint does not add any feature, or any work that is being done does not result in an increment, is not
advised by Scrum. To answer the natural question that may arise related to technical debt, Scrum
suggests to alter the definition of “Done” to include the non-creation of technical debt at the point of
work done. In other words, Scrum advocates quality over quantity, and if something that needs to be
re-worked later, then it is seen as a waste, similar to the LEAN principles.
 

Ask our Experts

 

https://www.whizlabs.com/learn/course/quiz-result/29340 14/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

QUESTION 19 CORRECT SCRUM EVENTS

Prescribed Scrum Events does not include ______? (Select all that apply)

 A. Mid-Sprint sync mee ng 

 B. Backlog Grooming Mee ng 

C. Sprint Retrospec ve

D. Daily Scrum

Explanation :
Correct Answer – A, B
There are only four prescribed scrum events – Sprint planning, Daily Scrum, Sprint Review and Sprint
Retrospec ve.

Ask our Experts

 

QUESTION 20 CORRECT SPRINT SCENARIOS

On the last day of the Sprint, there are only two events that are held, they are the
Sprint Review and Sprint Retrospec ve – True or False

A. True

B. False 

Explanation :
Correct Answer – B
Incorrect, daily scrum is also held on the last day of the scrum.

Ask our Experts

 
https://www.whizlabs.com/learn/course/quiz-result/29340 15/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
 

QUESTION 21 CORRECT SPRINT SCENARIOS

The best time in the day for conducting daily scrum meeting is morning - True or
False ?

A. True

B. False 

Explanation :
Correct Answer – B
 
The best time for the daily scrum is the time as decided by the development team. In geographically
distributed team, it may not be necessarily morning time for everyone when daily scrum is held.

Ask our Experts

 

QUESTION 22 CORRECT SCRUM EVENTS

User Stories are assigned to development team members by either the Scrum
Master or a member of the development team – True or False

A. True

B. False 

Explanation :
Correct Answer – B
User Stories are not assigned to the development team members by anybody. The members themselves
decide how they want to work on them. Development team is self-organizing.
More details on Development team can be found at h ps://scrumguides.org/scrum-guide.html#team-
dev (h ps://scrumguides.org/scrum-guide.html#team-dev)

https://www.whizlabs.com/learn/course/quiz-result/29340
A k E t 16/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
Ask our Experts

 

QUESTION 23 INCORRECT SCRUM TEAM

Development Team members are supposed to work themselves, and do not require
a manager/lead to manage/plan the ac vi es for them in the Sprint – True or False?

A. True 

B. False 

Explanation :
Correct Answer – A
True. Development Team is self-organizing, which means that they are empowered to decide how to
work and do not need anyone outside the development team to manage the work for them.
More details on the development team can be found at h ps://scrumguides.org/scrum-
guide.html#team-dev (h ps://scrumguides.org/scrum-guide.html#team-dev)

Ask our Experts

 

QUESTION 24 CORRECT SCRUM THEORY

What is the container for all the Scrum Events?

A. Agile Release Train

B. Release cycle

C. Sprint 

D. Product Backlog

Explanation :
Correct Answer – C
h f ll h
https://www.whizlabs.com/learn/course/quiz-result/29340 17/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
Sprint is the container for all the Scrum Events.

Ask our Experts

 

QUESTION 25 INCORRECT SCRUM THEORY

Sprint is me-boxed – True or False?

A. True 

B. False 

Explanation :
Correct Answer – A
Yes, Sprint is also me-boxed.

Ask our Experts

 

QUESTION 26 CORRECT SCRUM EVENTS

Product owner is not mandated to a end the Sprint Retrospec ve mee ng – True or
False?

A. True

B. False 

Explanation :
Correct Answer – B

PO should be a part of the Sprint Retrospec ve mee ng. It is not uncommon for the PO to provide some
d l h bl
https://www.whizlabs.com/learn/course/quiz-result/29340 h h d l h h h dd h l 18/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
very good solu ons to the problems that the development team might have had during the Sprint. Also
this is also an opportunity for the PO to bring up any issues that he/she might have faced.
More details on Sprint Retrospec ve can be found at h ps://scrumguides.org/scrum-guide.html#events-
retro (h ps://scrumguides.org/scrum-guide.html#events-retro)

Ask our Experts

 

QUESTION 27 CORRECT SCRUM EVENTS

In a geographically distributed team, it is acceptable for some of the members to


miss the Sprint Planning Mee ng?

A. True

B. False 

Explanation :
Correct Answer – B
Sprint planning mee ng is supposed to be a collec ve effort and therefore it is not acceptable for some
members of the team to miss it, even if they are geographically distributed.
More details on Sprint planning mee ng can be found at h ps://scrumguides.org/scrum-
guide.html#events-planning (h ps://scrumguides.org/scrum-guide.html#events-planning)

Ask our Experts

 

QUESTION 28 CORRECT SPRINT SCENARIOS

In a normal 5-days work week, if the Sprint Retrospective is held on Friday


morning, it means that the next Sprint starts with the Sprint planning on Monday –
True or False?

A. True

https://www.whizlabs.com/learn/course/quiz-result/29340 19/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

B. False 

Explanation :
Correct Answer – B
 
The next Sprint starts as soon as the Sprint Retrospective is over for the ongoing Sprint.
 
Reference : https://www.scrumguides.org/scrum-guide.html#events-sprint
(https://www.scrumguides.org/scrum-guide.html#events-sprint)

Ask our Experts

 

QUESTION 29 MARKED AS REVIEW CORRECT SPRINT SCENARIOS

If there are unplanned leaves by two members of a 7 member development team


for half of the Sprint, the actual velocity achieved at the end of the Sprint should be
adjusted accordingly – True or False?

A. True

B. False 

Explanation :
Correct Answer – B
The velocity should always show the actual user story points completed during the sprint, and should not
be adjusted to show something that might have been achieved in ideal scenarios.

Ask our Experts

 

QUESTION 30 CORRECT SPRINT GOAL

Should the Sprint Goal be measurable?


https://www.whizlabs.com/learn/course/quiz-result/29340 20/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

A. True 

B. False

Explanation :
Correct Answer – A
Yes, Sprint Goal should be measurable. It helps the development team and the stakeholders to
understand what and how much has been achieved.

Ask our Experts

 

QUESTION 31 CORRECT SCRUM THEORY

While the development team is collec vely accountable for delivering an Increment,
it is the responsibility of the en re team to see to its success. True or False?

A. True 

B. False

Explanation :
Correct Answer – A
While accountability is with the development team, the en re scrum team is responsible for the
increment. Everyone needs to perform their part to make sure that the increment meets the Sprint Goal.
The Scrum Master needs to guide the team, and remove any external impediments. Product Owner
should be able to provide all the informa on that is required from his end in the commi ed me frame
to the development team to help them deliver the increment.

Ask our Experts

 

QUESTION 32 INCORRECT SCRUM THEORY


https://www.whizlabs.com/learn/course/quiz-result/29340 21/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

It is okay for backlog refinement to consume more than 10% of the Sprint. True or
False?

A. True 

B. False 

Explanation :
Correct Answer – B
Scrum guide specifically mentions that backlog refinement should not generally consume more than
10% of the sprint time. If it consumes more, inspection should be done and ways identified to keep it
within the time limit.

Ask our Experts

 

QUESTION 33 CORRECT SCRUM ARTIFACTS

Like a Product Backlog, Sprint Backlog can also be shared among different teams if
they are working on the same product – True or False?

A. True

B. False 

Explanation :
Correct Answer – B
While Product Backlog is specific to a product, Sprint backlog is specific to a development team. So,
Sprint backlog cannot be shared among different teams.
More details on Sprint backlog can be found at https://scrumguides.org/scrum-guide.html#artifacts-
sprintbacklog (https://scrumguides.org/scrum-guide.html#artifacts-sprintbacklog)

Ask our Experts

 
https://www.whizlabs.com/learn/course/quiz-result/29340 22/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
 

QUESTION 34 INCORRECT SPRINT SCENARIOS

When is the product released by the Product Owner? Choose the most
appropriate answer.

A. At the end of every Sprint 

B. Mid-Sprint

C. When the whole product is developed

D. When the Product Owner deems suitable 

Explanation :
Correct Answer – D
Product is released by the PO whenever he/she chooses to. It is not necessary that the product be
released at the end of every sprint.

Ask our Experts

 

QUESTION 35 CORRECT SCRUM ARTIFACTS

When does the Product Backlog cease to exist?

A. When the Product Owner wishes

B. When the complete product is developed and released

C. When the product ceases to exist 

D. When a product is moved from development to maintenance and support

Explanation :
Correct Answer – C

Product backlog exists as long as the product exists, therefore only when the product ceases to exist,
th d t b kl g t i t
https://www.whizlabs.com/learn/course/quiz-result/29340 23/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
the product backlog cease to exist.

Ask our Experts

 

QUESTION 36 INCORRECT SCRUM ARTIFACTS

Which is the single most important characteristic of a product backlog item that is
necessary to classify it as "Ready" for selection in Sprint?

A. It should be fully estimated 

B. It should be ordered

C. It can be completed in one sprint 

D. It should be included in the Sprint Backlog

Explanation :
 
Correct Answer – C
Explanation:
According to Scrum, “Product Backlog items that can be “Done” by the Development Team within one
Sprint are deemed “Ready” for selection in a Sprint Planning”.
When an item is deemed “Ready”, it means that it has been broken down sufficiently that it can be
converted into an increment of “Done” within one Sprint.

Ask our Experts

 

QUESTION 37 CORRECT SPRINT SCENARIOS

Can the Scrum master cancel a Sprint?

A. Yes

B. No 

https://www.whizlabs.com/learn/course/quiz-result/29340 24/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Explanation :
Correct Answer – B
 
Only the Product Owner can cancel the Sprint if he or she believes that the Sprint goal will not deliver
business value.
 
Reference: https://www.scrumguides.org/scrum-guide.html#events-sprint
(https://www.scrumguides.org/scrum-guide.html#events-sprint)

Ask our Experts

 

QUESTION 38 CORRECT DEFINITION OF DONE

If the "Done" is not a convention of the development organization, who will create
the definition of done (DoD)?

A. Development Team 

B. Product Owner

C. Scrum Master

D. Scrum Team

Explanation :
Correct Answer is option A
 
The definition of done(DoD) is created by the development team. Development team is solely
responsible for the DoD. The acceptance criteria has to be confirmed by the product owner.
The Scrum Guide states that:
 
 

https://www.whizlabs.com/learn/course/quiz-result/29340 25/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Reference: https://www.scrumguides.org/scrum-guide.html#artifact-transparency-done
(https://www.scrumguides.org/scrum-guide.html#artifact-transparency-done)
 

Ask our Experts

 

QUESTION 39 INCORRECT SCRUM THEORY

The only thing constant across the Sprints is ____________.

A. Development Team Composition 

B. Product Backlog

C. Sprint Goal

D. None of the above 

Explanation :
Correct Answer – D
Nothing is constant across sprints. Everything can change to accommodate the changing market
dynamics and requirements.

Ask our Experts

 
https://www.whizlabs.com/learn/course/quiz-result/29340 26/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
 

QUESTION 40 INCORRECT SCRUM THEORY

It is acceptable that the frequency of inspection is high enough that inspection can
come in the way of the work of the development team – True or False?

A. True 

B. False 

Explanation :
Correct Answer – B
False, frequency of inspection should be as high as possible, but not coming in the way of work of the
development team.

Ask our Experts

 

QUESTION 41 CORRECT SCRUM EVENTS

Could the Sprint Planning be finished if only work planned for the first days of the
Sprint is decomposed to units of one day or less?

A. Yes 

B. No

Explanation :
 
Correct Answer – A
Explanation:
The purpose of the Sprint Planning meeting is to decide on “What will be done” and “How will the
chosen work done”. To this effect, although the target is to understand completely about all the work
and have it decomposed to units of one day or less, but this is not always the case, because of

dependencies and lack of clarity on some items. It is therefore completely acceptable to finish the
S i t Pl i g ti g l g th
https://www.whizlabs.com/learn/course/quiz-result/29340
k l d f th fi t f d f th S i t i d t d 27/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
Sprint Planning meeting, as long as the work planned for the first few days of the Sprint is understood
and broken down into smaller tasks.
More details on Sprint Planning meeting and its processes can be found at Link:

http://scrumguides.org/scrum-guide.html#events-planning (http://scrumguides.org/scrum-
guide.html#events-planning)

Ask our Experts

 

QUESTION 42 INCORRECT SCRUM TEAM

The product owner(PO) can also be a part of the development team. - Is this
statement true or false?

A. True 

B. False 

Explanation :
The correct answer is - Option A (True).
 
The product owner (PO) can be a part of the development team. It is possible that a developer also
acts as a product owner.

Ask our Experts

 

QUESTION 43 CORRECT SCRUM TEAM

Development team is self-organizing, therefore their composition can be changed


mid-sprint – Is this statement true or false?

A. True

https://www.whizlabs.com/learn/course/quiz-result/29340 28/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

B. False 

Explanation :
Correct answer – False
Development team is self-organizing, but it doesn't mean that they can change their composition
mid-sprint. The composition change can happen between two sprints.
More about development team can be found at https://scrumguides.org/scrum-guide.html#team-
dev (https://scrumguides.org/scrum-guide.html#team-dev)

Ask our Experts

 

QUESTION 44 CORRECT SCRUM EVENTS

The items selected during the Sprint Planning meeting can be re-negotiated
during the Sprint – True or False?

A. True 

B. False

Explanation :
Correct Answer – A
Yes, as more is known, the items selected during the Sprint planning meeting can be re-negotiated.

Ask our Experts

 

QUESTION 45 INCORRECT SCRUM EVENTS

Who conducts the Daily Scrum?

A. Scrum Master 

https://www.whizlabs.com/learn/course/quiz-result/29340 29/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

B. Product Owner

C. Development Team 

D. Any external stakeholder can be chosen for this task

Explanation :
Correct Answer – C
Development team conduct the daily scrum. Scrum Master only makes sure that the development
team is having the daily scrum.

Ask our Experts

 

QUESTION 46 INCORRECT SCRUM EVENTS

Sprint Review is ________________.

A. an informal meeting to present the increment and elicit feedback 

B. a formal status meeting to demonstrate the increment

C. a formal meeting with the stakeholders to show the work done during the Sprint

D. a general purpose meeting to discuss on the performance of the development team during the sprint 

Explanation :
Correct Answer – A
Sprint review is an informal meeting to present the increment and elicit feedback.
More details on Sprint Review can be found at https://scrumguides.org/scrum-guide.html#events-
review (https://scrumguides.org/scrum-guide.html#events-review)

Ask our Experts

 

QUESTION 47 CORRECT SCRUM EVENTS


https://www.whizlabs.com/learn/course/quiz-result/29340 30/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Which Scrum event is an opportunity for inspection and adaption? (Select all that
apply)

A. Daily Scrum

B. Sprint Planning

C. Sprint review

D. All of the above 

Explanation :
Correct Answer – A, B, C, D
 
Scrum prescribes four formal events for inspection and adaptation:

Daily Scrum

Sprint planning

Sprint review

Sprint retrospectice

All the scrum events are an opportunity for inspection and adaptation.

Ask our Experts

 

QUESTION 48 CORRECT SCRUM ARTIFACTS

The product should always be in a potentially releasable condition at the end of


the every Sprint, even if it is the first Sprint – True or False?

A. True 

B. False

Explanation :

Correct Answer – A
Y t th d f i t
https://www.whizlabs.com/learn/course/quiz-result/29340
ll i t f th d t tb d l d d th d t 31/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
Yes, at the end of every sprint, a small increment of the product must be developed, and the product
should be in a potentially releasable condition at the end of the sprint.

Ask our Experts

 

QUESTION 49 INCORRECT

Only User stories are part of the Product Backlog. Others like defects are not
represented in the Product Backlog – True or False?

A. True 

B. False 

Explanation :
Correct Answer – B
Every requirement or defect should be captured in the product backlog.

Ask our Experts

 

QUESTION 50 INCORRECT SCRUM ARTIFACTS

A Product Backlog can be considered complete if all the known items in it are
prioritized, estimated and all the details pertaining to them are provided – True or
False?

A. True 

B. False 

Explanation :

Correct Answer – B
A d t b kl g i l t
https://www.whizlabs.com/learn/course/quiz-result/29340
di l i g 32/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
A product backlog is never complete and is ever-evolving.
More details on the product backlog can be found at https://scrumguides.org/scrum-
guide.html#artifacts-productbacklog (https://scrumguides.org/scrum-guide.html#artifacts-
productbacklog)

Ask our Experts

 

QUESTION 51 CORRECT SPRINT SCENARIOS

The act of adding details, estimates and order to the items in the product backlog
is called ________.

A. Sprint Planning

B. Sprint Review

C. Product Backlog refinement 

D. Scoping

Explanation :
Correct Answer – C
The act of adding details, estimates and order to the items in the product backlog is called Product
Backlog Refinement/ backlog grooming.

Ask our Experts

 

QUESTION 52 INCORRECT SCRUM ARTIFACTS

While Product backlog is an ever evolving artifact, the Sprint backlog is fixed at the
start of the Sprint, and remains unchanged throughout the ongoing Sprint – True
or False?

A. True 

https://www.whizlabs.com/learn/course/quiz-result/29340 33/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

B. False 

Explanation :
Correct Answer – B
False, the Sprint backlog also changes and is updated by the development team as more knowledge is
gained on how to achieve the Sprint Goal.
More information on Sprint Backlog can be found at https://scrumguides.org/scrum-
guide.html#artifacts-sprintbacklog (https://scrumguides.org/scrum-guide.html#artifacts-
sprintbacklog)

Ask our Experts

 

QUESTION 53 CORRECT SCRUM EVENTS

The total work remaining is tracked at least in the daily scrum by __________.

A. Scrum Master

B. Product Owner

C. Development team 

D. Any external designated member

Explanation :
Correct Answer – C
The development team tracks the remaining work every day in the daily scrum, and takes appropriate
steps to make sure that all the work gets finished within the Sprint time-box.

Ask our Experts

 

QUESTION 54 INCORRECT SPRINT SCENARIOS

If all the committed user stories are done before the time-box of the Sprint
https://www.whizlabs.com/learn/course/quiz-result/29340 34/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

expires, the Sprint can be considered over – True or False?

A. True 

B. False 

Explanation :
Correct Answer – B
Sprint is over when the time-box expires. If all the committed work is completed before it, and there is
capacity available in the development team, they generally ask the PO if another user story/stories
can be picked.

Ask our Experts

 

QUESTION 55 INCORRECT SCRUM THEORY

If an inspector determines that one or more aspects of a process deviate outside


acceptable limits, when an adjustment must be made?

A. As soon as possible to minimize further deviation 

B. The deviations should be discussed at the Daily Scrum and then an adjustment must be made

C. After clarifying all the details with the Product Owner 

D. After Scrum Master approval

Explanation :
Correct Answer – A
The adjustment should be made as soon as possible without endangering the Sprint Goal

Ask our Experts

 

QUESTION 56 CORRECT DEFINITION OF DONE


https://www.whizlabs.com/learn/course/quiz-result/29340 35/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

The inputs to creating a Definition of Done are ___________. (Select all that apply)

A. Experience of the Product Owner

 B. Definition of "Done" of other Scrum Teams working on the same Product 

C. Definition of "Done" of other Scrum Teams working on other products

 D. Conventions, standards and guidelines of the Organization 

Explanation :
Correct Answer – B, D
There are generally two inputs that a team considers while create of DoD of their own. They are the
DoD of other teams working on the same product and the guidelines and standards followed by the
organization.

Ask our Experts

 

QUESTION 57 INCORRECT SCRUM ARTIFACTS

Who creates the increment?

A. Scrum Master

B. Development Team 

C. Product Owner 

D. Scrum Team

Explanation :
Correct Answer – B
The development team does the work of converting the requirements into an increment.

Ask our Experts

 
https://www.whizlabs.com/learn/course/quiz-result/29340 36/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
 

QUESTION 58 INCORRECT SCRUM THEORY

What/Who guides the Development Team on why it is building an increment?

A. Product Owner 

B. Scrum Master

C. Sprint Goal 

D. Sprint Backlog

Explanation :
Correct Answer – C
Sprint Goal is created with the purpose that it can guide the team on why it is building an increment.

Ask our Experts

 

QUESTION 59 INCORRECT SPRINT SCENARIOS

All scrum teams working on the same product should have sprints start and end at
the same time – True or False?

A. True 

B. False 

Explanation :
Correct Answer – B
No, different scrum teams working on the same product may have different sprint cadence, and
different start and end times.

Ask our Experts

 
https://www.whizlabs.com/learn/course/quiz-result/29340 37/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
 

QUESTION 60 INCORRECT DEFINITION OF DONE

Definition of Done should be fixed – True or False?

A. True 

B. False 

Explanation :
Correct Answer – B
DoD, like all the other Scrum artifacts evolves over time to best reflect the current and desired
position.

Ask our Experts

 

QUESTION 61 CORRECT SCRUM ARTIFACTS

Product Backlog is shared among the teams working on the same product – True
or False?

A. True 

B. False

Explanation :
Correct Answer – A
Yes, if there are multiple teams working on the same product, they will have the same product backlog.

Ask our Experts

 

QUESTION 62 INCORRECT SPRINT SCENARIOS


https://www.whizlabs.com/learn/course/quiz-result/29340 38/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Other than the 4 prescribed scrum events and product backlog refinement,
additional meetings are prohibited by Scrum as it is seen as a waste of time – True
or False?

A. True 

B. False 

Explanation :
Correct Answer – B
Scrum does not prohibit additional meetings. It just makes the four scrum events mandatory. It must
be noted though that the additional meetings should serve a purpose and introspection needs to be
done if they are not being effective.

Ask our Experts

 

QUESTION 63 INCORRECT SCRUM EVENTS

All the user stories that are selected for a particular sprint are necessarily
supposed to be decomposed and all details pertaining to them should be known
by the development team at the end of the Sprint Planning – True or False?

A. True 

B. False 

Explanation :
Correct Answer – B
No, not all user stories are required to be decomposed to tasks, or needs to be understood
completely in Sprint planning meeting. It is an ongoing process. The team must take care though that
at least some of the user stories are completely understood and decomposed into tasks so that the
team has work for at least the first couple of days. The rest of the user stories can be detailed as an
ongoing process throughout the sprint.

https://www.whizlabs.com/learn/course/quiz-result/29340
A k E t 39/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
Ask our Experts

 

QUESTION 64 CORRECT SCRUM THEORY

Scrum is designed to optimize flexibility, Creativity and productivity – True or


False

A. True 

B. False

Explanation :
Correct Answer – A
Yes, Scrum has been designed to optimize the flexibility, creativity and productivity of the teams.

Ask our Experts

 

QUESTION 65 INCORRECT SCRUM TEAM

With say five development teams working on the same product, they should have
the same scrum master – True or False?

A. True 

B. False 

Explanation :
Correct Answer – B
Not necessarily. In fact it is common to see multiple scrum masters in multi-team environment. That
is why there is an event “Scrum of Scrums” that becomes necessary for the multiple teams to sync up.

https://www.whizlabs.com/learn/course/quiz-result/29340
A k E t 40/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
Ask our Experts

 

QUESTION 66 INCORRECT DEFINITION OF DONE

Please select all the ways in which Definition of Done helps the scrum team.

 A. DoD ensures artifact transparency 

B. DoD is used to assess when work is complete on the product Increment 

 C. Guides the Development Team in knowing how many Product Backlog items it can select during a Sprint
Planning 

 D. DoD helps to calculate velocity of the Scrum Team 

Explanation :
Correct Answer – A, B, C
All the options are correct except the one that says that it helps the team calculate the velocity of the
scrum team.

Ask our Experts

 

QUESTION 67 INCORRECT SCRUM EVENTS

The Scrum Master does the following regarding the Daily Scrum. (Select all that
apply)

A. Ensures that the Development Team has the meeting 

 B. Is responsible for conducting the Daily Scrum 

 C. Ensures that others (members not part of the development team) do not disrupt the meeting. 

 D. Teaches the Development Team to keep the Daily Scrum within the 15-minute time-box 

Explanation :
https://www.whizlabs.com/learn/course/quiz-result/29340 41/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

Correct Answer – A, C, D
 
Scrum Master ensures that the development team has the daily scrum and makes sure that the
development team members participate in it and keep the daily scrum within the time-box.

Ask our Experts

 

QUESTION 68 CORRECT SCRUM TEAM

Who is responsible for the monitoring of the remaining work towards the Project
Goal?

A. Product Owner 

B. Development Team

C. Scrum Master

D. Business Stakeholders

Explanation :
Correct Answer – A
Monitoring the progress towards the project goal is the responsibility of the product owner.

Ask our Experts

 

QUESTION 69 CORRECT DEFINITION OF DONE

What should be taken into account for the Definition of “Done”? Select all that
apply

A. Experience of the Product Owner

 B. Definition of "Done" of other Scrum Teams working on the same Product 

https://www.whizlabs.com/learn/course/quiz-result/29340 42/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

C. Definition of "Done" of other Scrum Teams working on other products

 D. Conventions, standards and guidelines of the Organization 

Explanation :
 
Correct Answer – B, D
Explanation:
Definition of “Done” or DoD must take into account the DoD of the other Scrum Teams working on the
SAME product. This is to ensure that there is uniformity in the quality of the different parts of the
product.
Organization’s conventions, standards and guidelines should also be taken into consideration for the
DoD, so that the expectations and standards of the organization can be appropriately reflected in the
final product.
More details on DoD can be found at Link:

http://www.scrumguides.org/scrum-guide.html#artifact-transparency-done
(http://www.scrumguides.org/scrum-guide.html#artifact-transparency-done)

Ask our Experts

 

QUESTION 70 CORRECT SCRUM THEORY

Some parts of Scrum can be implemented without implementing the whole Scrum
model – True or False?

A. True 

B. False

Explanation :
Correct Answer – A
True, some parts of Scrum can be implemented without implementing the whole scrum model.
Though it must be understood that part implementation does not mean that Scrum has been
implemented. Scrum exists only in its entirety.

https://www.whizlabs.com/learn/course/quiz-result/29340
A k E t 43/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
Ask our Experts

 

QUESTION 71 INCORRECT SPRINT SCENARIOS

When can the development team add tasks for the user stories during the Sprint?
Choose the most appropriate option.

A. Only during Sprint Planning

B. When the Product Owner or Scrum Master asks the team to

C. During backlog grooming 

D. As soon as possible after they are identified, unless they reflect a scope change in the sprint goals 

Explanation :
Correct Answer – D
The tasks may be added as soon as they are identified.

Ask our Experts

 

QUESTION 72 CORRECT SCRUM THEORY

Backlog grooming should be done with only the senior members of the
Development Team, so that other can keep working on their tasks – True or False?

A. True

B. False 

Explanation :
Correct Answer – B

It is a good practice for the development team to act as one, and in backlog grooming also, it should be
t i d th t th h l d l tt
https://www.whizlabs.com/learn/course/quiz-result/29340
ti i t 44/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
tried that the whole development team participates.

Ask our Experts

 

QUESTION 73 CORRECT VELOCITY

When is the velocity for a sprint calculated?

A. When the product is released

B. When the Sprint is over 

C. At the end of every working day

D. Anytime during a sprint

Explanation :
Correct Answer – B
Velocity of a Sprint is calculated at the end of the Sprint, and only the completed user stories are
considered for its calculation.

Ask our Experts

 

QUESTION 74 CORRECT SCRUM THEORY

The tactics to implement Scrum in different teams is identical and fixed – True or
False

A. True

B. False 

Explanation :
Correct Answer – B
Th t ti f S i l t ti
https://www.whizlabs.com/learn/course/quiz-result/29340
i ith t d th b t f ti i d id d 45/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
The tactics for Scrum implementation varies with team and the best course of action is decided upon
assessing the team.

Ask our Experts

 

QUESTION 75 INCORRECT SCRUM TEAM

What are the core responsibilities of the Product Owner? (Select all that apply)

 A. Maximize the value of the product 

 B. Maximize the value of the work done by the Development Team 

 C. Keeping the external stakeholders from interfering in the activities of the development team 

 D. Making sure all the work is done at the end of the Sprint 

Explanation :
Correct Answer – A, B
The responsibilities of the PO include maximizing the value of the product and the value of the work
done by the development team.
More details on PO and his responsibilities can be found at https://scrumguides.org/scrum-
guide.html#artifacts-sprintbacklog (https://scrumguides.org/scrum-guide.html#artifacts-
sprintbacklog)

Ask our Experts

 

QUESTION 76 CORRECT SCRUM TEAM

Who is responsible to help employees and stakeholders understand and enact


scrum and empirical product development?

A. Product Owner

B. Development Team

https://www.whizlabs.com/learn/course/quiz-result/29340 46/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

C. Scrum Master 

D. All of them

Explanation :
Correct Answer – C
It is the responsibility of the Scrum master. More details on scrum master and his responsibilities can
be found at https://scrumguides.org/scrum-guide.html#team-sm (https://scrumguides.org/scrum-
guide.html#team-sm)

Ask our Experts

 

QUESTION 77 CORRECT SCRUM TEAM

Who facilitates the Scrum Events, whenever requested or as needed?

A. Scrum Master 

B. Product Owner

C. Project Manager

D. Any one

Explanation :
Correct Answer – A
Scrum Master facilitates the Scrum events as required.
More details on Scrum Master can be found at https://scrumguides.org/scrum-guide.html#team-sm
(https://scrumguides.org/scrum-guide.html#team-sm)

Ask our Experts

 

QUESTION 78 INCORRECT SCRUM TEAM


https://www.whizlabs.com/learn/course/quiz-result/29340 47/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

There is provision in Scrum that allows one development team to be broken down
to sub-teams, categorized based on areas of specializations – True or False?

A. True 

B. False 

Explanation :
Correct Answer – B
The development team cannot be broken down into sub-teams, there is no exception to this rule.
More details on the development team can be found at https://scrumguides.org/scrum-
guide.html#team-dev (https://scrumguides.org/scrum-guide.html#team-dev)

Ask our Experts

 

QUESTION 79 INCORRECT SCRUM TEAM

Who ensures that the Product Backlog is visible, transparent, and clear to all?

A. Scrum Master

B. Product Owner 

C. Development Team

D. Business Stakeholders 

Explanation :
Correct Answer – B
Product Owner ensures that the product backlog is visible, transparent and clear to all.
More details on PO can be found at https://scrumguides.org/scrum-guide.html#team-po
(https://scrumguides.org/scrum-guide.html#team-po)

Ask our Experts

 
https://www.whizlabs.com/learn/course/quiz-result/29340 48/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)
 

QUESTION 80 CORRECT SCRUM TEAM

Who does the work of delivering a potentially releasable Increment of “Done”


product at the end of each Sprint?

A. Product Owner

B. Development Team 

C. Scrum Master

D. Scrum Team

Explanation :
Correct Answer – B
The development team does the work of delivering a potentially releasable Increment.
More details on the development team can be found at https://scrumguides.org/scrum-
guide.html#team-dev (https://scrumguides.org/scrum-guide.html#team-dev)

Ask our Experts

 

Finish Review (https://www.whizlabs.com/learn/course/psm-i-practice-tests/quiz/14890)

Certification Company
 Cloud Certification  Support (https://help.whizlabs.com/hc/en-us)
(https://www.whizlabs.com/cloud-
 Discussions (http://ask.whizlabs.com/)
certification-training-courses/)
 Blog (https://www.whizlabs.com/blog/)
 Java Certification
(https://www.whizlabs.com/oracle-java-
certifications/)

 PM Certification
(https://www.whizlabs.com/project-
management-certifications/)
https://www.whizlabs.com/learn/course/quiz-result/29340 49/50
4/22/2019 Whizlabs Online Certification Training Courses for Professionals (AWS, Java, PMP)

 Big Data Certification


(https://www.whizlabs.com/big-data-
certifications/)

Mobile App Follow us


Coming Soon
 Android
Coming Soon

 iOS (https://www.facebook.com/whizlabs.software/)


(https://in.linkedin.com/company/whizlabs-software)


(https://twitter.com/whizlabs?lang=en)


(https://plus.google.com/+WhizlabsSoftware)

© Copyright 2018. Whizlabs Software Pvt. Ltd. All Rights Reserved.

https://www.whizlabs.com/learn/course/quiz-result/29340 50/50

You might also like