TIME SHEET

Name: Period Covered: Signature:


Jason Villa November 30 – December 14, 2016

15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
PROJECT / TASKS Sub-Total Total
Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thur Fri
OFFICE TASK 48.00
Site Supervision (Pastanni) 8 8.00
Absent - -
Material Procurement (Pastanni) 8 8.00
Material Procurement (Pastanni) 6 6.00
Material Procurement (Pastanni) 4 4.00
Material Procurement (Pastanni) 8 8.00
Submitting Permits (Pastanni) 2.00
Site Supervision (Pastanni) 2.00 2.00
Material Procurement (Pastanni) 4.00 4.00
Sketchup Model Dimensioning (Pastanni) 8 8.00

SUNDAY

SUNDAY
OVERTIME -
-
-
-
-
OTHERS -
-
-
-
BREAK TIME - AM & PM Snack 1.00 - 1.00 1.00 - 1.00 1.00 1.00 1.00 1.00 1.00 1.00
DAILY TOTAL 9.00 - 9.00 - 7.00 4.00 9.00 9.00 9.00 1.00 - 1.00 7.50 8.00 73.50
TOTAL 48.00
Note:
Please record the number of hours spent to complete the assigned task.