ENR/WL/DB/010/2018-2019 DATE: - 24/04/2019
---------------------------------------------------------------------------------------------------------------------

To,
M/s. SRI RAMSHANKAR SURGICALS,
774/15, North Street,
Chatrapatti – 626 102.
Rajapalayam Via.
.

Dear Sir,

Sub: Offer for 1500 Kg/Hr@10.54 Kg/Sq.cm Horizontal Multi tubular two pass
Dry Back wood Fired IBR Boiler.

We thank you for your enquiry and have pleasure in quoting our
competitive offer for Fabrication and Supply of 1500 Kg/Hr@10.54 Kg/Sq.cm
Horizontal Multi tubular Two Pass Dry Back Wood Fired IBR Boiler including all
Manufacturing IBR formalities, which we hope would meet with your approval.

We trust the Technical specifications described in the enclosed


content sheet meet your need and you would find our offer technically
suitable and price wise competitive.

For ENNAAR ENERGY SYSTEMS

N.Rajamanickam.
Managing Director
Ennaar
R ENNAAR ENERGY SYSTEMS

MAIN SPECIFICATION FOR BOILER

1. Type : Horizontal Multi tubular two


Pass Dry Back IBR Boiler

2. Model : EDWB 15

3. Capacity : 1500 Kg/Hr

4. Working Pressure : 10.54 Kg/sq.cm (g) (150 psi)

5. Steam condition : Dry Saturated

6. Fuel Fired : Fire Wood.

7. Draft : Natural Draft

8. Gross Calorific Value : 3500 Kcal/Kg.

9. Thermal Efficiency on GCV : 68 %  2.

10. Design Code : IBR. With Latest Edition

11. Feed Water arrangement


a) No. of pumps with motor : 2 nos
b) Type : Multi stage, Centrifugal
c) Capacity of pump : 1.25 m3/hr / 121 MLC Head.

12. Other Factors at Full Load


a) Steam Purity : 90 %
b) Excess air : 40 %

13. Total Power Consumption : 4 HP


Ennaar
R ENNAAR ENERGY SYSTEMS

I. SCOPE OF SUPPLY

1. BOILER
a. Shell, furnace, tubular passes & end plates.
b. Front and rear smoke boxes, saddle supports, platform assy, and
charging door.
c. Stationary Grate Assembly for Burning Of Fuel - 1 Set.
d. Platform: Top walkway platform complete
With railing & Ladder -1 Set.

2. ACCESSORIES
Feed pump with motor -2Set.

3. IBR MOUNTINGS AND FITTINGS


a) Main steam stop valve - 1 No
b) Boiler Safety valve - 2 Nos
c) Disk Check valve - 2 Nos
d) Globe valves - 2 Nos
e) Blow down valve - 1 No
f) Air vent valve - 1 No
g) Isolating valve for Pr. Gauge - 1 No

4. CONTROLS AND SAFETIES


a) Water level gauge assembly - 2 Sets
b) Steam pressure gauge - 1 No
c) Fusible plug - 1 No

5. PIPINGS
Feed Water : Feed pump delivery flange to boiler inlet.
Blow Down : From boiler to blow down valve.

6. REFRACTORY
The required Refractory of the boiler, wherever required shall be
provided.
Ennaar
R ENNAAR ENERGY SYSTEMS

II. BATTERY LIMITS

a. Feed Water : Inlet of feed pump suction flange.

b. Fuel : Inlet of fuel charging doors.

c. Steam : Outlet of the main steam valve.

d. Blow down : Outlet of the blow down valve.

e. Safety valve discharge : Outlet flange of safety valves.

f. Drain : Outlet of drain valves.

III. EXCLUSIONS

a. Transport & Transit Insurance.

b. Unloading, Erection and Commissioning of Boiler.

c. Boiler house civil work and foundation.

d. Fuel, feed water, dosing chemicals, first charge lubricants.

e. Incoming electrical connection to the feed pump motors and etc.

f. Erection and Commissioning of Boiler and Pipe line.

g. Insulation Boiler and Pipe line.

h. IBR Formalities and registration of boiler.

j. Supply of Feed water tank, Ducting’s.

k. Control panel Board & AWLC.

k. Taxes and Duties.

l. Spares for operation and maintenance.


Ennaar
R ENNAAR ENERGY SYSTEMS

PRICE SCHEDULE

1. Fabrication and Supply of 1500 Kg/Hr@10.54 Kg/Sq.cm Horizontal Multi


tubular two pass Dry Back Wood Fired IBR Boiler with Suitable Guy
rope Supported Chimney and necessary Mountings Our offer would be
......................@Rs. 9,75,000/-
(Rupees Nine Lakhs Seventy Five Thousand Only)

COMMERCIAL TERMS AND CONDITIONS

1. BASIS OF PRICE: - Ex - our works, Perundurai.

2. GST: - Applicable GST @ 18 % will be charged extra

3. DELIVERY:-
Delivery of the boiler will be within 40 days from the date of
receipt of your technically and commercially clear order with subject to
force majeure conditions.

4. PAYMENT:-
1. 60% advance along with the order.
2. 40% and Tax against Before Delivery of boiler at our site.

5. VALIDITY:-
30 days from the date of this offer.
Thanking you and assuring our best services at all times