You are on page 1of 1

SAFETY ALERT

CCC CORPORATE HSE GROUP Issue Date: April 7, 2019

Multiple Fatalities – Metallurgical Failure of Spherical Tank (Not CCC)

What Happened? (Incident Description)  Calculations were not completed to select the proper vaporizer
incorporating a standard safety factor to prevent liquid nitrogen from
On March 21st 2019 at approximately 08:00 AM an incident occurred entering the tank.
during the commissioning phase of a Non - CCC Project in Suez, Egypt.
3) Failure to effectively control Simultaneous Activities.
The Incident occurred when a spherical tank ruptured while being purged No permit to work System, No Supervision and No Safety Inspection
with nitrogen prior to putting the tank in service. The tank had successfully was implemented. Other ongoing activities in the tank area were not
passed leak testing at a pressure of 24 bar few days before the incident. stopped during the purging activity.
Due to the “non-availability” of a nearby nitrogen production facility, a
4) Poor site HSE Supervision and Monitoring,
mobile liquid nitrogen tank connected to a liquid nitrogen vaporizer was
The HSE and construction teams either failed to stop other activities
used to generate the needed nitrogen gas for the purging process.
around the tanks during purging activities or were not present.
Two Pressure Relieve Valves (PRVs) were installed on top of the spherical
tank and were tested earlier and it was confirmed the valves could Lessons Learned
withstand a pressure of 10 bar.
1) Ensure Effective Planning by Competent Construction and HSE
The purging plan was to vaporize the liquid nitrogen and pressurize the Engineers
spherical tank using nitrogen in the gaseous form after vaporization with A detailed Method Statement, Risk Assessment, Safe System of Work,
the expectation the PRVs would operate at a pressure of 10 bar as Supervision, HSE Checking and Inspection must be available and
previously tested. properly implemented when performing such activities. The Engineers
who develop the method statement and risk Assessment must have
At a pressure of 4 bar, the spherical tank experienced a metallurgical
sound technical competency and experience to provide informative
failure resulting in flying debris.
and detailed plans.
The scattered flying debris claimed the lives of 25 persons working below
2. Conduct Job Safety Task Instruction (JSTI)
& nearby the tank area.
Effectively communicate control measures using a JTSI to ensure all
involved workers are aware of the hazards and risks associated with
the task.
What Went Wrong? (Causes of the incident)
3) Effective Site Supervision must be enforced by the Senior Project
“Root Cause Analysis (RCA) of the Metallurgical failure revealed that liquid Management.
nitrogen flow rate was higher than the vaporizer capacity, resulting in All activities must be monitored and supervised competently,
the nitrogen reaching the spherical tank in its liquid state (–196°C). The continuously and effectively in terms of safety primarily by construction
liquid nitrogen accumulated in the spherical tank triggering steel ductile supervisors and aided by safety officers.
to brittle transition causing the tank rupture at a pressure of 4 bar”.
4) Communicate the Lessons Learned from this incident (the
content of this Alert) to the project workforce through the
1) Failure to identify the potential hazards following:
The flow rate of the liquid nitrogen was not controlled or restricted to
ensure it never exceeded the vaporizer capacity. The risk associated  A Stand-down to all site workers on site (one-time Stand-down to be
with the use of liquid nitrogen was not adequately foreseen and conducted with all site workers in the presence of Project
mitigated. If the flow rate was adequately controlled, the metallurgical Management)
failure would not have occurred.  The weekly TBT (Tool Box Talk). Designate one TBT to
communicate lessons learned from the incident to all site workers.
2) Failure to Plan correctly for the Task,  The weekly SSMM (Safety Supervisory Management Meeting) for
 The activity started without barricading the area creating a safe managers, engineers and senior supervisors
buffer zone around the purging activity to prevent any unauthorized  The weekly SO Meeting (Safety Officers Meeting) for all Safety
access near the tank. Officers
 The weekly CH Meeting (Charge Hand Meeting) for all Foremen
 No Detailed Risk Assessment or Effective HSE Communication
and Charge-Hand
utilizing a JSTI was conducted.

You might also like