Republic of the Philippines

NORTHWEST SAMAR STATE UNIVERSITY


Main Campus, Calbayog City

COLLEGE OF ENGINEERING AND TECHNOLOGY

JOSE B. NACIONALES JR. PROJECT


BSCE - 5 CE 513
DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018

page 1 of 1
PROGRAM OF WORK
Project Title Source of Fund
TWO (2) - STOREY RESIDENTIAL BUILDING JOSE B. NACIONALES JR./PROJECT OWNER
Location Project Duration
MAGSAYSAY EXTENSION, CALBAYOG CITY DAYS
Project Category Site Area
RESIDENTIAL 240 SQ.M.
Project Description
CONSTRUCTION OF TWO (2) - STOREY RESIDENTIAL BUILDING
LOCATED AT MAGSAYSAY EXTENSION, CALBAYOG CITY

ESTIMATED COST OF PROPOSED OF WORK


Item No. Description % of Total Unit Quantity Unit Cost Amount
I Earthworks 10% cu.m. 0
II Reinforcing Steel Bars 10% kg 0
III Carpentry Works 10% ls 0
IV Structural Concrete Class A 10% cu.m. 0
V Masonry Works 10% sq.m. 0
VI Truss and Roofing 10% sq.m. 0
VII Plumbing Works 10% ls 0
VIII Ceiling Works 10% ls 0
IX Doors and Windows 10% ls 0
X Electrical Works 10% ls 0
XI Painting Works 10% sq.m. 0
XII Tile Works 10% sq.m. 0
XIII Finishes and Accessories 10% sq.m. 0
TOTAL ESTIMATED DIRECT COST PHP 0
Republic of the Philippines
NORTHWEST SAMAR STATE UNIVERSITY
Main Campus, Calbayog City

COLLEGE OF ENGINEERING AND TECHNOLOGY

JOSE B. NACIONALES JR. PROJECT


BSCE - 5 CE 513
DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018

page 1 of 1
ITEMS OF WORK
I. EARTHWORKS VII. PLUMBING WORKS
A. CLEARING AND GRUBBING Y. SEPTIC TANK
B. STAKING Z. WATER LINE
C. EXCAVATION AND FILL AA. SEWER LINE
II. REINFORCING STEEL BARS BB. CATCH BASIN
D. FOOTING REINFORCEMENT VIII. CEILING WORKS
E. WALL FOOTING REINFORCEMENT CC. GYPSUM BOARD INSTALLATION
F. COLUMN REINFORCEMENT IX. DOORS AND WINDOWS
G. BEAM REINFORCEMENT DD. DOORS INSTALLATION
H. SLAB REINFORCEMENT EE. WINDOWS INSTALLATION
I. STAIR REINFORCEMENT X. ELECTRICAL WORKS
J. STIRRUPS AND LATERAL TIES FF. WIRES INSTALLATION
III. CARPENTRY WORKS GG. OUTLETS INSTALLATION
K. SCAFOLDINGS XI. PAINTING WORKS
L. FORMWORKS HH. WALLS
IV. STRUCTURAL CONCRETE CLASS A II. CEILING
M. COLUMNS FOOTING JJ. COLUMNS
N. WALLS FOOTING XII. TILE WORKS
O. COLUMNS KK. HOMOGENOUS TILES INSTALLATION
P. BEAMS LL. CERAMIC TILES INSTALLATION
Q. STAIR XIII. FINISHES AND ACCESSORIES
R. SLABS MM. ACCESSORIES INSTALLATION
V. MASONRY WORKS NN. CLEANING
S. STAKING OF CHB
T. MORTARING AND PLASTERING
U. PLAIN CEMENT FINISH
VI. TRUSS AND ROOFING
V. TRUSSES
W. PURLINS
X. CORRUGATED ROOF
Republic of the Philippines
NORTHWEST SAMAR STATE UNIVERSITY
Main Campus, Calbayog City

COLLEGE OF ENGINEERING AND TECHNOLOGY

JOSE B. NACIONALES JR. PROJECT


BSCE - 5 CE 513
DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018

page 1 of 2
DURATION AND ACTIVITIES
DURATION ACTIVITY
ITEMS OF WORK
(DAYS) PRECEDES FOLLOWS
I. EARTHWORKS
A. CLEARING AND GRUBBING
B. STAKING
C. EXCAVATION AND FILL
II. REINFORCING STEEL BARS
D. FOOTING REINFORCEMENT
E. WALL FOOTING REINFORCEMENT
F. COLUMN REINFORCEMENT
G. BEAM REINFORCEMENT
H. SLAB REINFORCEMENT
I. STAIR REINFORCEMENT
J. STIRRUPS AND LATERAL TIES
III. CARPENTRY WORKS
K. SCAFOLDINGS
L. FORMWORKS
IV. STRUCTURAL CONCRETE CLASS A
M. COLUMNS FOOTING
N. WALLS FOOTING
O. COLUMNS
P. BEAMS
Q. STAIR
R. SLABS
V. MASONRY WORKS
S. STAKING OF CHB
T. MORTARING AND PLASTERING
U. PLAIN CEMENT FINISH
VI. TRUSS AND ROOFING
V. TRUSSES
W. PURLINS
X. CORRUGATED ROOF
Republic of the Philippines
NORTHWEST SAMAR STATE UNIVERSITY
Main Campus, Calbayog City

COLLEGE OF ENGINEERING AND TECHNOLOGY

JOSE B. NACIONALES JR. PROJECT


BSCE - 5 CE 513
DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018

page 2 of 2
DURATION AND ACTIVITIES
DURATION ACTIVITY
ITEMS OF WORK
(DAYS) PRECEDES FOLLOWS
VII. PLUMBING WORKS
Y. SEPTIC TANK
Z. WATER LINE
AA. SEWER LINE
BB. CATCH BASIN
VIII. CEILING WORKS
CC. GYPSUM BOARD INSTALLATION
IX. DOORS AND WINDOWS
DD. DOORS INSTALLATION
EE. WINDOWS INSTALLATION
X. ELECTRICAL WORKS
FF. WIRES INSTALLATION
GG. OUTLETS INSTALLATION
XI. PAINTING WORKS
HH. WALLS
II. CEILING
JJ. COLUMNS
XII. TILE WORKS
KK. HOMOGENOUS TILES INSTALLATION
LL. CERAMIC TILES INSTALLATION
XIII. FINISHES AND ACCESSORIES
MM. ACCESSORIES INSTALLATION
NN. CLEANING
Republic of the Philippines
NORTHWEST SAMAR STATE UNIVERSITY
Main Campus, Calbayog City

COLLEGE OF ENGINEERING AND TECHNOLOGY

JOSE B. NACIONALES JR. PROJECT JOSE B. NACIONALES JR.


BSCE - 5 CE 513 BSCE - 5
DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018 DR. MARCIANO B. APILAD

page 1 of 8
QUANTITY TAKE - OFF
I. EARTHWORKS II. REINFORCING STEEL B
EXCAVATION = 40.5 cubic meter MARK
MARK LENGTH WIDTH DEPTH UNIT VOLUME
C1 1.5 1.5 1.5 11 37.125
FOOTING FOOTING
C2 1.5 1.5 1.5 1 3.375
TOTAL 40.5

BACK FILL = 22.788 cubic meter


COLUMN
MARK LENGTH WIDTH DEPTH UNIT VOLUME
C1 1.5 1.5 0.3 11 7.425
C2 1.5 1.5 0.3 1 0.675
FOOTING
WALL 9.6 0.4 0.2 3 2.304
WALL 6 0.4 0.2 4 1.92
1 0.4 0.2 1.2 11 1.056
COLUMN
2 0.3 0.3 1.2 1 0.108 BEAM
9.6 0.2 0.4 3 2.304
BEAM GROUND
6 0.2 0.4 4 1.92
TOTAL 17.712

FILL = 17.28 cubic meter


WALL
MARK LENGTH WIDTH DEPTH UNIT VOLUME
BUILDING AREA 9.6 6 0.3 1 17.28
TOTAL 17.28 SLAB

STAIRS

STIRRUPS
Republic of the Philippines
NORTHWEST SAMAR STATE UNIVERSITY NORT
Main Campus, Calbayog City

COLLEGE OF ENGINEERING AND TECHNOLOGY COLLEGE

JOSE B. NACIONALES JR. PROJECT JOSE B. NACIONALES JR.


CE 513 BSCE - 5
DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018 DR. MARCIANO B. APILADO

page 2 of 8
QUANTITY TAKE - OFF
II. REINFORCING STEEL BARS III. CARPENTRY WORKS
MARK STEEL Ø LENGTH UNIT UNIT WT. QUANTITY FORMWORKS =
COLUMN 1 16mmØ 24.3 11 1.5790 422.0667 MARK
COLUMN 2 16mmØ 24.3 1 1.5790 38.3697
12mmØ 9.6 3 0.888 25.5744 COLUMN 1
WALL FOOTING
12mmØ 6 4 0.888 21.312 COLUMN 2
16mmØ 23.2 11 1.5790 402.9608 1
1 COLUMN
12mmØ 23.2 11 0.888 226.6176 2
16mmØ 23.2 1 1.5790 36.6328
2 BEAM GROUND
12mmØ 23.2 1 0.888 20.6016
12mmØ 57.6 3 0.888 153.4464 SLAB
GROUND
12mmØ 36 4 0.888 127.872
16mmØ 96 3 1.5790 454.752 1
1 COLUMN
16mmØ 60 4 1.5790 378.96 2
16mmØ 76.8 3 1.5790 363.8016
2 1
16mmØ 48 4 1.5790 303.168
BEAM
12mmØ 22.2 1 0.888 19.7136 CANTILEVER
3
12mmØ 21 1 0.888 18.648 3
CANTILEVER 16mmØ 7 4 1.5790 44.212 SLAB
10mmØ 360 3 0.616 665.28
WALL
10mmØ 225 4 0.616 554.4
BEAM 2
10mmØ 230.4 1 0.616 141.9264
SLAB 12mmØ 384 1 0.888 340.992
10mmØ 192 1 0.616 118.272
12mmØ 15 1 0.888 13.32 1. Columns
STAIRS
10mmØ 75 1 0.616 46.2 Total length of column =
STIRRUPS 10mmØ 422.2 1 0.616 260.0752 2. Using 2" x 3" vertical support, multiply:
Steel Bar (10mmØ) = 1786.1536 kg 60 x 7 = 420 Bd. Ft. 2" x 3" x 14" lumbe
Steel Bar (12mmØ) = 968.0976 kg 3. Using 2" x 2" horizontal support, multiply:
Steel Bar (16mmØ) = 2444.9236 kg 60 x 21 = 1260 Bd. Ft. 2" x 2" lumber
4. Diagonal braces, multiply:
60 x 11.7 = 702 Bd. Ft. 2" x 2"lumber

3. Slab
Area of concrete floor slab = 115.2 sq.m.
Using 2" x 3"
Republic of the Philippines Republic
NORTHWEST SAMAR STATE UNIVERSITY NORTHWEST SAM
Main Campus, Calbayog City Main Cam

COLLEGE OF ENGINEERING AND TECHNOLOGY COLLEGE OF ENGIN

CIONALES JR. PROJECT JOSE B. NACIONALES JR.


CE 513 BSCE - 5
ANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018 DR. MARCIANO B. APILADO

page 3 of 8
QUANTITY TAKE - OFF QUANTI
NTRY WORKS IV. STRUCTURAL CONCRETE CLASS A
188.208333 pieces (1.2m x 2.4m Marine Plywood) CONCRETE = 45.578
MARK LENGTH WIDTH DEPTH UNIT AREA MARK
1ST FLOOR 1ST FLO
COLUMN 1 1.5 1.5 0.3 11 24.75 COLUMN 1
FOOTING
COLUMN 2 1.5 1.5 0.3 1 2.25 COLUMN 2
1 0.2 0.4 3 11 39.6 1
COLUMN
2 0.3 0.3 3 1 3.6 2
9.6 0.2 0.4 3 34.56
GROUND BEAM GROUND
6 0.2 0.4 4 28.8
SLAB 9.6 6 0.1 2 115.2 SLAB
2ND FLOOR 2ND FLO
1 0.2 0.4 2.8 11 36.96 1
COLUMN
2 0.3 0.3 2.8 1 3.36 2
9.6 0.2 0.4 3 34.56
1 1
6 0.2 0.4 4 28.8
BEAM
CANTILEVER 1 0.2 0.4 2 2.4 CANTILEVER
3 7.2 0.2 0.4 1 8.64 3
SLAB 9.6 6 0.1 2 115.2 SLAB
ROOF BEAM ROOF BE
9.6 0.2 0.4 3 34.56
2 BEAM 2
6 0.2 0.4 4 28.8
TOTAL 542.04
SCAFFOLDING
2. Beams CONCRETE PROPORTION
5*12 = 60m Total length of beam = 1382.4m
Mixture Class Proportion
3" vertical support, multiply: a. Vertical support, 2"x 3" lumber
0 Bd. Ft. 2" x 3" x 14" lumber 1382.4 x 6 = 8294.4 bd. Ft. A 1:02:04
2" horizontal support, multiply: b. Horizontal support, 2" x 2" lumber
260 Bd. Ft. 2" x 2" lumber 1382.4 x 4.7 = 6497.28 bd. Ft. Using 40kg Cement Class A Mixture
races, multiply: Cement : 45.578 6
702 Bd. Ft. 2" x 2"lumber 4. Floor slab forms Sand : 45.578 0.5
115.2/2.88 = 40 4' x 8' marine plywood Gravel : 45.578 1
ete floor slab = 115.2 sq.m.
115.2 x 9.1 = 1048.32 bd. Ft.
Republic of the Philippines Republic of the Philippi
NORTHWEST SAMAR STATE UNIVERSITY NORTHWEST SAMAR STATE
Main Campus, Calbayog City Main Campus, Calbayog

COLLEGE OF ENGINEERING AND TECHNOLOGY COLLEGE OF ENGINEERING AND

PROJECT JOSE B. NACIONALES JR.


CE 513 BSCE - 5
1ST SEMESTER, S.Y. 2017-2018 DR. MARCIANO B. APILADO

page 4 of 8
QUANTITY TAKE - OFF QUANTITY TAKE - O
CRETE CLASS A V. MASONRY WORKS
cubic meter CHB = 264 square meter
LENGTH WIDTH DEPTH UNIT VOLUME MARK LENGTH
1ST FLOOR 1ST FLOOR
1.5 1.5 0.3 11 7.425 9.6
WALL
1.5 1.5 0.3 1 0.675 6
0.2 0.4 4.2 11 3.696 2ND FLOOR
0.3 0.3 4.2 1 0.378 9.6
WALL
9.6 0.2 0.4 3 2.304 6
6 0.2 0.4 4 1.92
9.6 6 0.1 1 5.76
2ND FLOOR CHB = 3300 pieces
0.2 0.4 2.8 11 2.464 1ST FLOOR
0.3 0.3 2.8 1 0.252 1. Dividing the height of the wall by the height of one block, we get the n
9.6 0.2 0.4 3 2.304 Height of Wall = 2.6m Height of Block =
6 0.2 0.4 4 1.92 Layer = 13 layers
1 0.2 0.4 2 0.16 2. Dividing the length of the wall by the length of one blockm we get the
7.2 0.2 0.4 1 0.576 Length of Wall = 52.8m Length of Block =
9.6 6 0.1 2 11.52 Pieces = 132 pieces
ROOF BEAM 3. Multiply the layer and pieces, we get the total number of CHB (0.2by0
9.6 0.2 0.4 3 2.304 CHB Total Number (1st Floor) = 1716
6 0.2 0.4 4 1.92 2ND FLOOR
TOTAL 45.578 1. Dividing the height of the wall by the height of one block, we get the n
Height of Wall = 2.4m Height of Block =
Layer = 12 layers
Cement in Bag Sand Gravel 2. Dividing the length of the wall by the length of one blockm we get the
40kg 50kg cu.m. cu.m. Length of Wall = 52.8m Length of Block =
6 5 0.5 1 Pieces = 132 pieces
3. Multiply the layer and pieces, we get the total number of CHB (0.2by0
CHB Total Number (2nd Floor) = 1584
= 273.468 bags say 274 bags
= 22.789 cu.m. say 23 cu.m.
= 45.578 cu.m. say 46 cu.m.
Republic of the Philippines Republic of the Philippines
ORTHWEST SAMAR STATE UNIVERSITY NORTHWEST SAMAR STATE UNIVERSITY
Main Campus, Calbayog City Main Campus, Calbayog City

EGE OF ENGINEERING AND TECHNOLOGY COLLEGE OF ENGINEERING AND TECHNOLO

PROJECT JOSE B. NACIONALES JR.


CE 513 BSCE - 5
1ST SEMESTER, S.Y. 2017-2018 DR. MARCIANO B. APILADO

page 5 of 8
QUANTITY TAKE - OFF QUANTITY TAKE - OFF
QUANTITY OF CEMENT AND SAND FOR MORTAR AND PLASTER IN SQUA
square meter No. per Sand
Mixture Class Cement
WIDTH DEPTH UNIT AREA sq.m. cu.m.
1ST FLOOR A 12.50 0.792 0.0435
0.15 2.6 3 74.88 Size of CHB 10cm by 20cm by 40cm
0.15 2.6 4 62.4 Using Cement Class A Mixture
2ND FLOOR Cement : 264 0.792 = 209.088
0.15 2.4 3 69.12 Sand : 264 0.0435 = 11.484
0.15 2.4 4 57.6
TOTAL 264 VI. TRUSS AND ROOFING
TRUSS
Size of CHB 10cm by 20cm by 40cm Bottom Chords: 2L 2" x 2" x 0.25" = 60.296
1ST FLOOR Top Chords: 2L 1.5" x 1.5" x 0.25" = 63.5996391
eight of one block, we get the number of blocks layers Web Members: L 1.5" x 1.5" 0.25" = 96.2807475
Height of Block = 0.2m Length UNIT B.C. T.C. W.M.
Truss 1 2 7.6 8.17068 13.2949671
ength of one blockm we get the number of blocks pieces Truss 2 4 5.374 5.57942 9.9312227
Length of Block = 0.4m Truss 3 1 3.8 4.08534 7.3974835
Truss 4 1 3.5 3.822211 3.5313664
he total number of CHB (0.2by0.4) Truss 5 1 3 3.2252681 6.3488068
pieces Truss 6 7 1.9 1.97254 1.8126094
2ND FLOOR TOTAL = 60.296 63.5996391 96.2807475
eight of one block, we get the number of blocks layers
Height of Block = 0.2m PURLINS
Use 2" x 4" x 1/4" C Purlins spaced at 400mm on center
ength of one blockm we get the number of blocks pieces Length = 273.2965003 meters
Length of Block = 0.4m
0.5mm Thick G.I. Gutter = 39.2 meters
he total number of CHB (0.2by0.4) 0.5mm Thick G.I. Ridge Roll = 34.22 meters
pieces 0.5mm Thick Union Brand Pre-Painted G.I. Roofing Sheets = 92.8 sq.m. = 33
blic of the Philippines Republic of the Philippines
SAMAR STATE UNIVERSITY NORTHWEST SAMAR STATE UNIVERSITY
ampus, Calbayog City Main Campus, Calbayog City

GINEERING AND TECHNOLOGY COLLEGE OF ENGINEERING AND TECHNOLOGY

PROJECT JOSE B. NACIONALES JR. PROJECT


CE 513 BSCE - 5 CE 513
1ST SEMESTER, S.Y. 2017-2018 DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017

page 6 of 8
NTITY TAKE - OFF QUANTITY TAKE - OFF
AR AND PLASTER IN SQUARE METER VII. PLUMBING WORKS SEPTIC TANK
BY DIRECT COUNTING ( With Total Wall Area of 60.8 m² )
Plumbing Fixtures and Accessories: No. of CHB 60.8 m² x 13 pcs/m²
Water Closet 8 sets ( Using Class A (1 : 3) Mixture )
Lavatory 8 sets Cement 791 x 0.0734
Kitchen Sink 2 sets Sand 791 x 0.0059
bags say 210 bags Bath Tub 1 set Slab Vol. 2( 0.15mx1.8mx4.0m)
cu.m. say 12 cu.m. Shower head, Valve and Faucet 5 sets Cover Vol. 2( 0.2mx3.0mx1.8 m )
Sanitary pipes and fittings:
Pipes, 100mm dia x 3.00m 12 pcs. Using Class A Concrete Mixture:
Pipes, 75mm dia x 3.00m 10 pcs. Cement
meters Pipes, 50mm dia x 3.00m 16 pcs. Sand
meters Sanitary Tee, 100mm dia 7 pcs. Gravel
meters Sanitary Tee, 50mm dia 8 pcs. ( At average thickness of 12mm, Class A Mix
90 deg. Elbow, 100mm dia 16 pcs. Total Area 60.8 m² + 7.20 m²
90 deg. Elbow, 75mm dia 8 pcs.
90 deg. Elbow, 50mm dia 16 pcs. Cement 68.0 m² x 0.216
Sanitary Wye, 100mm dia 8 pcs. Sand 68.0 m² x 0.012
Coupling,100mm dia 10 pcs. For CHB Wall:
Floor Drain Trap, 50mm dia 24 pcs. Vert. Bars 60.8 m² x 2.13 m/m²
Clean-out w/plug, 100mm dia 8 pcs. Hor. Bars 60.8 m² x 2.15 m/m²
Water Pipes And Fittings, Shedule 40:
Pipe, 12mm dia x 6.00m 20 pcs. No. of Bars = 43.37 pcs.
Elbow 90 deg, 12mm dia 40 pcs. For Concrete Reinforcement: (using 12 mm
Tee, 12mm dia 24 pcs. Total Area 2(1.8mx4m+3mx1.8)
Coupling, 12mm dia 18 pcs. No. of Bars 25.2 m² x 1.980 pcs/m²
Teflon Tape, Big 20 pcs. Equivalent Weigth:
Water meter 1 set 10mm Bar 44 pcs x 3.70 kg/pc.
Gate valve, Bronze finish 1 set 12mm Bar 50 pcs x 5.33 kg/pc.
ng Sheets = 92.8 sq.m. = 33 pcs (1.2m x 2.4m) Faucet, Bronze finish 12 sets
( Using No. 16 Tie Wire at 0.30 cm long )
For CHB Wall:
No. of kg 462.89 m² x 0.032 kg/m²
For Concrete Reinforcement:
No. of kg 60.8 m² x 0.132 kg/m²
ppines Republic of the Philippines
TE UNIVERSITY NORTHWEST SAMAR STATE UNIVERSITY
yog City Main Campus, Calbayog City

AND TECHNOLOGY COLLEGE OF ENGINEERING AND TECHNOLOGY

JOSE B. NACIONALES JR. PROJECT


BSCE - 5 CE 513
1ST SEMESTER, S.Y. 2017-2018 DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018

page 7 of 8
- OFF QUANTITY TAKE - OFF
VII. CEILING WORKS
Total Wall Area of 60.8 m² ) Using 2"x2" ceiling joist spaced at 40 x 60 centimeters on center = 808.0992 bd.ft.
60.8 m² x 13 pcs/m² = 790.4 pcs Area of ceiling = 150.4 sq.m.
sing Class A (1 : 3) Mixture ) 150.4 x 5.373 = 808.0992 bd.ft.
791 x 0.0734 = 58.06 bags Using 1.2m x 2.4m plywood = 53 pieces
791 x 0.0059 = 4.67 m³ 150.4 / 2.88 = 53 pcs
2( 0.15mx1.8mx4.0m) = 2.16 m²
2( 0.2mx3.0mx1.8 m ) = 2.16 m² IX. DOORS AND WINDOWS
Total Vol. = 4.32 m² MARK TYPE LENGTH WIDTH UNIT
A Concrete Mixture: 1 Wooden Panel 2.10 1 1
4.32 x 7.85 = 33.91 bags 2 Sliding Glass Door 2.10 1.6 3
4.32 x 0.42 = 1.81 m³ 3 Wooden Panel 2.10 0.8 4
DOOR
4.32 x 0.84 = 3.63 m³ 4 PVC 2.10 0.65 2
hickness of 12mm, Class A Mix ) 5 Wooden Panel 2.10 0.7 1
60.8 m² + 7.20 m² 6 Wooden Panel 2.10 0.65 1
68.0 m² 1 Sliding 1.20 1.6 6
68.0 m² x 0.216 = 14.69 bags 2 Sliding 1.20 0.5 5
68.0 m² x 0.012 = 0.816 m³ 3 Sliding 0.55 0.8 1
WINDOW
( using 10 mm Ø x 6 m ) 4 Awning 0.50 0.5 2
60.8 m² x 2.13 m/m² = 129.50 m 5 Awning 1.64 0.5 1
60.8 m² x 2.15 m/m² = 130.72 m 6 Sliding 1.20 1 1
Total = 260.22 m TOTAL

Reinforcement: (using 12 mm Ø x 6 m) X. ELECTRICAL WORKS XI. PAINTING WORKS


2(1.8mx4m+3mx1.8) = 25.2 m² MARK Unit Area of to be painted = 995.52 square meter
25.2 m² x 1.980 pcs/m² = 49.90 pcs. Pinlight 6 30 sq.m. is equal to 1 gallon
Energy Saver Lamp 23 995.52 / 30 = 34 gallons
44 pcs x 3.70 kg/pc. = 162.80 kg Chandelier 3 If one quart of neutralizer is mixed with 2.5 gallons of wate
50 pcs x 5.33 kg/pc. = 266.50 kg S1 13 34 / 2.5 = 14 quarts of neutralizer
429.30 kg S2 2 XI. TILE WORKS
6 Tie Wire at 0.30 cm long ) S3 2 Area = 115.2 sq.m.
Convenience Outlet 17 115.2 / 0.02 = 5760 pcs 10x20 (4"x8" glazed tiles)
462.89 m² x 0.032 kg/m² = 14.81 kg Panel Board 1 115.2 / 0.04 = 2880 pcs 20x20 (8"x8" unglazed tiles)
Reinforcement: 3.5mm Thick Wire 30m Solving for Cement Mortar
60.8 m² x 0.132 kg/m² = 7.92 kg Cement Mortar: 0.086 10
Total Weight = 22.73 kg. White Cement: 0.5 58
Republic of the Philippines
ITY NORTHWEST SAMAR STATE UNIVERSITY
Main Campus, Calbayog City

OLOGY COLLEGE OF ENGINEERING AND TECHNOLOGY

JOSE B. NACIONALES JR. PROJECT


BSCE - 5 CE 513
TER, S.Y. 2017-2018 DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018

page 8 of 8
BILL OF MATERIALS
Description Unit Quantity Unit Cost Amount
Steel Bar (10mmdia) kg 1953 135 263655
Steel Bar (12mmdia) kg 1237 205 253585
Steel Bar (16mmdia) kg 2445 380 929100
1.2m x 2.4m Marine Plywood pcs 189 475 89775
2"x3" lumber bd.ft. 1469 40 58760
2"x2" lumber bd.ft. 8460 12 101520
4'x8' plywood pcs 40 800 32000
AREA Cement (40kg) bags 543 240 130320
2.1 sq.m. Sand cu.m. 40 700 28000
10.08 sq.m. Gravel cu.m. 46 800 36800
6.72 sq.m. CHB 10cm x 20cm x 40cm pcs 4091 15 61365
2.73 sq.m. 2L 2" x 2" x 0.25" m 61 250 15250
1.47 sq.m. 2L 1.5" x 1.5" x 0.25" m 64 200 12800
1.365 sq.m. L 1.5" x 1.5" x 0.25" m 97 100 9700
11.52 sq.m. 0.5mm Thick G.I. Gutter m 40 200 8000
3 sq.m. 0.5mm Thick G.I. Ridge Roll m 35 280 9800
0.44 sq.m. 1.2m x 2.4m G.I. Roof Sheets pcs 33 300 9900
0.5 sq.m. 2" x 4" x 1/4" C Purlins m 274 200 54800
0.82 sq.m. Water Closet set 8 4500 36000
1.2 sq.m. Lavatory set 8 2000 16000
41.945 sq.m. Kitchen Sink set 2 1700 3400
Bath Tub set 1 6500 6500
Shower Head, Valve & Faucet set 5 800 4000
995.52 square meter Pipes, 100mm dia x 3.00m pcs 12 420 5040
Pipes, 75mm dia x 3.00m pcs 10 350 3500
Pipes, 50mm dia x 3.00m pcs 16 270 4320
s mixed with 2.5 gallons of water Sanitary Tee, 100mm dia pcs 7 150 1050
Sanitary Tee, 50mm dia pcs 8 90 720
90 deg. Elbow, 100mm dia pcs 16 150 2400
90 deg. Elbow, 75mm dia pcs 8 110 880
10x20 (4"x8" glazed tiles) 90 deg. Elbow, 50mm dia pcs 16 90 1440
20x20 (8"x8" unglazed tiles) Sanitary Wye, 100mm dia pcs 8 150 1200
Coupling,100mm dia pcs 10 120 1200
bags Floor Drain Trap, 50mm dia pcs 24 180 4320
bags Clean-out w/plug, 100mm dia pcs 8 170 1360
Republic of the Philippines
NORTHWEST SAMAR STATE UNIVERSITY
Main Campus, Calbayog City

COLLEGE OF ENGINEERING AND TECHNOLOGY

JOSE B. NACIONALES JR. PROJECT


BSCE - 5 CE 513
DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018

page 1 of 3 page 2 of 3
BILL OF MATERIALS
Description Unit Quantity Unit Cost Amount
Pipe, 12mm dia x 6.00m pcs 20 270 5400
Elbow 90 deg, 12mm dia pcs 40 65 2600
Tee, 12mm dia pcs 24 65 1560
Coupling, 12mm dia pcs 18 85 1530
Teflon Tape, Big pcs 20 30 600
Water meter set 1 1500 1500
Gate valve, Bronze finish set 1 300 300
Faucet, Bronze finish set 12 150 1800
Tie Wire No. 16 kg 23 65 1495
Door 1 set 1 5000 5000
Door 2 set 3 5000 15000
Door 3 set 4 4000 16000
Door 4 set 2 3000 6000
Door 5 set 1 3500 3500
Door 6 set 1 3500 3500
Window 1 set 6 6000 36000
Window 2 set 5 3000 15000
Window 3 set 1 3300 3300
Window 4 set 2 1500 3000
Window 5 set 1 4000 4000
Window 6 set 1 5000 5000
Pinlight set 6 100 600
Energy Saver Lamp set 23 150 3450
Chandelier set 3 450 1350
S1 set 13 90 1170
S2 set 2 100 200
S3 set 2 150 300
Convience Outlet set 17 100 1700
Panel Board set 1 550 550
3.5mm Thick Wire m 30 150 4500
Neutralizer quartz 14 550 7700
Acrylic Latex Paint Primer(W) gallon 34 2200 74800
Acrylic Latex Paint Final(R) gallon 34 2200 74800
4"x8" Glazed Tiles pcs 5760 30 172800
Cement Mortar bag 10 200 2000
Republic of the Philippines
NORTHWEST SAMAR STATE UNIVERSITY
Main Campus, Calbayog City

COLLEGE OF ENGINEERING AND TECHNOLOGY

JOSE B. NACIONALES JR. PROJECT


BSCE - 5 CE 513
DR. MARCIANO B. APILADO 1ST SEMESTER, S.Y. 2017-2018

page 3 of 3
BILL OF MATERIALS
Description Unit Quantity Unit Cost Amount
White Cement bag 58 200 11600
Common Nails (Assorted) kg 350 60 21000
Roof Nails kg 10 65 650
Roller Brush pcs 3 35 105
Palete pcs 3 150 450
3" Paint Brush pcs 3 25 75
TOTAL 2,710,345.00