You are on page 1of 88

E1915 V9

Public Disclosure Authorized


Public Disclosure Authorized
Public Disclosure Authorized

Environmental and Social Due Diligence Report


for
Public Disclosure Authorized

Kakinada Deep Water Port

November 2014

Submitted by:

HaskoningDHV Consulting Pvt. Ltd.


Green Boulevard, Plot B 9A, Tower B, 4th Floor, Sector 62, Noida - 201301, India
T +91 120 4016100, F +91 120 4260165, Email: info.india@rhdhv.com

Page 1 of 88
TABLE OF CONTENTS

1 INTRODUCTION.......................................................................................................................................... - 4 -

1.1 SUB PROJECT LOCATION & REGIONAL SETTINGS .................................................................................... - 4 -

1.2 SUB-PROJECT DESCRIPTION ......................................................................................................................... - 6 -

1.3 SCOPE OF SERVICES UNDER THE CURRENT ASSIGNMENT................................................................... - 7 -

1.4 STRUCTURE OF THE REPORT ........................................................................................................................ - 8 -

2 ENVIRONMENTAL COMPLIANCE STATUS.......................................................................................... - 10 -

2.1 APPRAISAL OF CONCESSION AGREEMENT .............................................................................................. - 10 -

2.2 APPRAISAL OF ENVIRONMENTAL CLEARANCE – 4TH BERTH & OSV TERMINAL ................................ - 11 -

2.3 APPRAISAL OF THE EIA DOCUMENT (5TH, 6TH & 7TH BERTH) ................................................................... - 14 -

2.4 WATER SUPPLY AND WASTE WATER GENERATION ............................................................................... - 14 -

2.5 EMERGENCY PREPAREDNESS & RESPONSE PLAN ................................................................................ - 15 -

2.5.1 FIRE FIGHTING .............................................................................................................................................. - 15 -

2.5.2 ONSITE AND OFF SITE DISASTER MANAGEMENT PLAN ...................................................................... - 16 -

2.6 ENVIRONMENTAL MONITORING PROGRAMME ........................................................................................ - 16 -

2.7 DREDGING & LAND RECLAIMATION ACTIVITIES ............................................................................................17

2.8 GREEN BELT DEVELOPMENT ............................................................................................................................17

2.9 STATUS OF STATUTORY COMPLIANCE– ENVIRONMENTAL .......................................................................18

2.10 PUBLIC HEARING AND DISCLOSURE OF INFORMATION FOR 5TH, 6TH & 7TH BERTH ...............................21

2.11 SITE OBSERVATIONS ..........................................................................................................................................22

2.12 CONCLUSIONS ......................................................................................................................................................24

3 SOCIAL COMPLIANCE & ISSUES ..............................................................................................................25

3.1 FRAMEWORK FOR SOCIAL DUE DILIGENCE ..................................................................................................25

3.2 PROJECT STRUCTURE AND DELINEATION OF PROJECT AREA ................................................................27

3.3 LAND ACQUISITION AND RESETTLEMENT IMPACTS UNDER THE PROJECT ..........................................29

3.4 COMMUNITIES IN THE PROJECT AREA - THE IMPACT .................................................................................32

3.5 PUBLIC CONSULTATIONS AND HEARING IN THE PROJECT ........................................................................35

3.6 EMPLOYMENT GENERATION AND SAFEGUARDS FOR EMPLOYEES ........................................................35

3.7 CSR INITATIVES BY KSPL ...................................................................................................................................36

-2-
3.8 CONCLUSIONS ......................................................................................................................................................37

LIST OF ANNEXURES ATTACHED

ANNEXURE 2-1: EC FOR 4TH BERTH & OSV ......................................................................................................40

ANNEXURE 2-2: EC FOR 5TH, 6TH, & 7TH BERTH ................................................................................................44

ANNEXURE 2-3: WATER CESS FORM 1.............................................................................................................50

ANNEXURE 2-4: ENVIRONMENTAL STATEMENT YEARLY SUBMITTED ON SEPT 2014............................52

ANNEXURE-3.1: PUBLIC HEARING UNDER EIA .......................................................................................... - 80 -

ANNEXURE-3.2: CASE STUDY OF KAKINADA DEEP WATER PORT ........................................................ - 82 -

ANNEXURE-3.3: CSR DETAILS FROM APR 2010 TO MAR 2014 ................................................................ - 84 -

ANNEXURE-3.4: GUIDELINES ON CORPORATE SOCIAL RESPONSIBILITY FUND, DISTRICT


COLLECTOR EAST GODAVARI DISTRICT, 1 JUNE 2013 ............................................................................ - 87 -

ANNEXURE-3.5: COMPANIES (CORPORATE SOCIAL RESPONSIBILITY POLICY) RULES, 2014, GOI,


MINISTRY OF CORPORATE AFFAIRS ........................................................................................................... - 88 -

-3-
1 INTRODUCTION

1. The India Infrastructure Finance Company Ltd (IIFCL) was constituted in 2006 with a mandate to
increase the availability of long term financing for public private partnership (PPP) infrastructure
projects in India. The IIFCL further revised its objectives in 2013, for strengthening its capacity for
infrastructure PPP financing through piloting instruments and implementation approaches.

2. Primarily, IIFCL focuses on two types of financing, direct financing (funding undertaken directly by
IIFCL to the developers during the construction stage) and post construction refinancing, also called the
“Takeout” financing. The two sectors pre-identified and agreed by IIFCL for “Takeout” financing entail
roads & port terminal.

3. The current assignment for preparation of Environmental and Social Due Diligence reports by
HaskoningDHV Consulting Private Limited (HDC) for a maximum of six sub-projects (Kakinada Deep
Water Port being one of them) acts as a groundwork (under the takeout financing component) ensuring
that there are no pending legacy issues or other reputational risks with regard to environmental and
social aspects.

4. The current draft environmental and social due diligence report presents the findings of the
appraisal for the first sub project i.e. Kakinada deep water port terminal1. The project details are
provided in the subsequent sections.

1.1 SUB PROJECT LOCAT ION & REG IONAL SETT INGS

5. Owing to its strategic location in the East Godavari district of Andhra Pradesh, Kakinada Deep
Water Port (KDWP) constitutes a part of Kakinada port (the second largest port in the state after
Vishakhapatnam). The Latitudinal and Longitudinal extent of the port entail 16°58’05.69’’N
to16°57.36.86”N and 82°16’56.82’’E to 82°16’50.97’’E respectively.

6. The port is well connected and accessible from all major Indian cities and enjoys multi-modal
connectivity by road, rail, air and pipelines (for liquid cargo). The nearest major settlement to the port is
Kakinada town at a distance of 10 km. The port is situated between Vishakhapatnam (170 km in north)
and Chennai (650 km in south) and forms the gateway for the rich agricultural belt of East Godavari,
West Godavari and Krishna Districts of Andhra Pradesh (Refer Figure 1-1).

7. From the regional perspective, the port development over the years coupled with good transport
network comprising connectivity through important roads (NH-214/ NH5 – part of the Golden
Quadrilateral Network), railways (railway station within port area) and air routes (nearest airports at
Rajahmundry – 65 Kms and Vishakhapatnam - 170 Km) has given impetus to industrial activities in the

1 Terminal at the port shall mean an unit consisting of berth or berths with or without the associated land (leased, acquired, reclaimed etc) and water area

and the facilities provided therein by the promoter including but not limited to cargo handling equipments/system, storage, inter modal transfer systems and
utilities.
-4-
region and further consolidated its position as one of the most important intermediate (non- major) ports
in the eastern region of the country.

Figure 1-1: Regional Linkages for the Kakinada Port

8. The bifurcation of the erstwhile state of Andhra Pradesh and a proposal to develop a new capital
town between Vijayawada and Guntur towns has provided additional focus to the region.

9. In addition to the Kakinada Deep Water Port, there is one additional minor port in vicinity i.e.
Kakinada Anchorage Port operated by Department of Ports, Government of Andhra Pradesh. An
additional port i.e. Kakinada SEZ port is
also proposed in vicinity to be developed
by GMR on 2,100 acres out of the 10,500
acres available with KSEZ, at an
investment of around INR 500 million. The
location of the Port is about 15 km North
of Kakinada Deep Water Port and is an all
together separate entity with no links to
the existing Kakinada Deep Water Port.
The location of these three ports in
Kakinada is depicted figure 1-2.

10. GMR has also established barge-


Figure 1-2: Location of Port
mounted gas-power plant at Kakinada

-5-
after the Reliance Industries began natural gas production in KG-D6 block but is currently not
operational as observed during the site visit.

1.2 SUB-PROJECT DESCRIPT ION

11. Kakinada Sea Ports Limited (KSPL) is the appointed concessionaire by the Government of Andhra
Pradesh (GoAP) for operation, maintenance and management of the terminal in accordance with the
terms of the concession2 agreement and its subsequent amendments. The port was originally
developed as an all-weather port by GoAP with financial assistance from Asian Development Bank and
was commissioned during 1997. GoAP operated the facilities for two years prior to privatizing and
concessionising to KSPL in March, 1999.

12. KSPL began its commercial operations upon signing of the concession agreement for “four berth
terminal”. Four Berth Terminal as defined in the concessionaire agreement implies a terminal with the
existing three shore connected berths (610 m long) and a future berth (300m long) to be constructed
contiguous to the above three berths for handling all containerized cargo of any type, liquid cargo, LPG,
heavy machinery and equipment, over dimensional cargo and steel material with arrangement of any
type developed and operated by concessionaire on the premises for receiving, shipping and
transshipping of cargo to and from vessels including
ships and barges in domestic and international service,
onshore transportation arrangements, storage and The Takeout Agreement for subproject between
the Novator, Takeout Lender and Borrower has
onshore transfer from or to railways, road and inland
been designed under the Phase I and Phase II.
waterways.
This agreement was signed in July 2012 between
13. The components of Four Berth Terminal shall the Borrower/Concessionaire (KSPL) and
include but not be limited to berths, open stockyards, Novators (State Bank of Patiala (SBoP)) and
storage sheds, railway yards, handling systems, Union Bank of India (UBI) and the Novatee /
utilities such as water supply, power supply, fire Takeout Lender (IIFCL). Under the agreement,
fighting and safety facilities, communication facilities the Borrower, KSPL requested IIFCL to sanction

and all other engineering structures/facilities on the financial assistance up to an aggregate amount
of Two Billion Two Hundred Sixty Seven Million
premises.
Five Hundred Thousand Rupees by way of
14. IIFCL has sanctioned financial assistance for takeout financing for meeting the outstanding
Phase 13 and Phase 24 developments post (at least Phase 1 and part of Phase 2 loans of SBoP and
one year) start of commercial operations date (COD) UBI under loan facility by IIFCL as Takeout
as per the guidelines under “takeout” financing. lender.

15. The Port operation was initiated by the KSPL-SPV

2 The Concession grants exclusive right and authority to KSPL for Operation, Maintenance and Management of Terminal with Four Shore connected Berths
at Kakinada Port through Concessionaire’s own investment together with a right to levy, collect and retain appropriate charges for Services by
Concessionaire during the concession period.
3 Phase 1 Development shall mean development of that part of the Package which makes the existing three berths fully developed for cargo handling,

storage etc.
4 Phase 2 development shall mean construction of the fourth berth (300 meters long) contiguous to South of the three berths and providing of cargo

handling and storage arrangements and other associated facilities.


-6-
in April 1999 and fourth berth was commissioned in March 2008 and two additional berths (fifth and
sixth berths) were commissioned in 2012. It may be observed that Kakinada Deep Water Port (KDWP)
since its inception¸ has witnessed series of development and, expansion activities are still ongoing as
per the proposed port master plan.

16. The ongoing expansion activities includes construction of 7th Berth contiguous to the 6th Berth,
dredging the berth pockets at 7th Berth, reclamation and development of back up area behind 7th Berth,
construction of drainages, roads, installation of lighting system and development of other infrastructural
activities, laying of railway sidings, doubling of existing main line to the port main station, widening and
deepening of Channel from 13.5m to 16m from break water to 5th and 6th and 7th Berths. These above
mentioned tasks are expected to be completed by December 2017.

17. The port operations started with an initial land parcel of 65 acres owned by the Government of
Andhra Pradesh. During the process of expansion, KSPL has reclaimed an area of about 360 acres
and further plans to reclaim additional 153 acres for future developments. Figure 1-3 below shows the
expansion activities in the port terminal area over the years starting 2005 till 2014 based on the Google
Earth data.

Figure 1-3: Development and expansion of the port area

1.3 SCOPE OF SERVICES UNDER T HE CURRENT ASSIGNMENT

18. By emphasizing on achieving a balance between developmental imperatives and environmental


sustainability and social well-being, IIFCL endeavors to avoid, minimize, mitigate environmental and
social adverse impacts/risks in their operations and is committed to comply with all relevant

-7-
Government of India (GoI) and state level statutory requirements and also remains responsive to E & S
safeguard policy requirements of DFIs (Development Finance Institutions) wherever DFI’s Line of credit
is involved.

19. The scope of work of the study will mainly encompass the following:

• To review whether the sub-project is in compliance with applicable national & state statutory
requirements and regulations related to social and environmental aspects only.

• To review that there is no significant outstanding legal or legacy issues pending based on the
information in public domain and no significant outstanding risks for either IIFCL or the World
Bank.

• To review whether the social and environmental plans have been implemented during the post
COD phase of sub-projects as per national policies on safeguards and

• To confirm and report in ESDD, if any safeguard covenants or issues identified as part of
appraisal process are implemented.

20. Under Takeout financing, the financing is akin to post-COD refinancing of a lender as it does not
finance any construction stage activities, and differs considerably from typical project financing. It
contributes to improving (through reduced debt service burden and reduced interest rate) funding for
the operation and maintenance activities (including debt servicing) without financing any new capital
assets, any construction, or any purchase of land, etc.

21. The safeguard implementation during the construction stage as per the applicable policy
provisions has been reviewed based on the available information in public domain to identify
residual issues, if any. However, the current environmental and social due diligence study
focuses on the phase-1 and phase-2 post COD activities wherein IIFCL has sanctioned financial
assistance. Certain facilities / activities / services provided by the developer for the complete port area
are also appraised as part of the current study as these activities cannot be considered in isolation e.g.
the disaster mitigation plan, etc

22. Being a post COD due diligence study, the focus of the assignment mainly entail review of
environment and social management/action plans under the applicable clauses of the Concessionaire
Agreement, environmental and social safeguard compliance post COD and highlight the compliances
and gaps.

23. This report is based on the reconnaissance field visit observations, data collated and analyzed for
the activities having related environmental and social measures, review of the available compliance
reports/ document, EIA/EMP documents for expansion activities undertaken in the past as per the
availability.

1.4 ST RUCT URE OF T HE REPORT

24. Chapter 1 provides a brief background about the project, description of the sub-project and scope of
the assignment. Chapter 2 provides the details of the due diligence carried out for the environmental
-8-
compliance of the sub-project and concludes with any non-compliance and pending statutory
requirements or legacy issues if any identified during the appraisal. Chapter 3 provides the due
diligence of the social safeguards including status of the land and public consultations conducted.

-9-
2 ENVIRONMENTAL COMPLIANCE STATUS

25. The Environmental due diligence task focuses on the status of the applicable environmental
regulatory clearance obtained as on date; the compliance and /or compliance reporting with the
regulatory clearance conditions; review of the EIA documents including compliance of clearance
conditions and address residual environmental impacts of significance especially related to
community/common property resources, natural habitats, and cultural properties etc. The ESDD study
for takeout shall also focus on impacts during operation phase of the sub-project.

26. As part of the environmental due diligence under TFS5 (Take-out Financing), the compliance to the
project was reviewed w.r.t the following:

• Environmental plans implementation during operation phase.


• Outstanding or pending legal or legacy issues
• Compliance to applicable national social and environmental laws
• Institutional arrangements in place for implementation and monitoring of environmental
mitigation measures
• EHS related clauses in O & M agreement
• Emergency preparedness and Response plan during operation phase
• Status of plantation and compensatory plantation; and current arrangements for
maintenance and replacement of casualties.
• Accident / incident reporting
• Health and work safety measures
• Outcome of implementation status of public hearing proceedings

27. Reconnaissance site visit was conducted by the consultant along with the IIFCL’s safeguard team.
The site visit focussed on understanding the port terminal activities; applicable environmental and social
aspects in the KSPL Deep Water Port operations; informal interactions with the fishing community in
immediate vicinity; Port officials including the environmental and safety department team members;
understanding efforts undertaken by KSPL as part of their mandatory CSR commitments; and gather
requisite information available in public domain & discussions with the developer for preparation of the
environmental and social due diligence report.

2.1 APPRAISAL OF CONCESSION AG REEMENT

28. The concession agreement was signed between the Government of Andhra Pradesh (Transport,
Roads & Buildings Department) and International Seaports Pte Limited, Singapore (currently
represented by SPV in the name of KSPL) on March 19, 1999 at Hyderabad. The Government of

5
TFS will deal with sub projects which are at post construction/ operational phase. As assistance under TFS is sanctioned only after minimum of one year
after the start of commercial operations date (COD), it is expected that the safeguard issues as per applicable state, national guidelines/regulations would
have been addressed by then.
- 10 -
Andhra Pradesh (GoAP) granted permission to the concessionaire to take over the existing
three berths with all the existing infrastructure facilities, construct an additional berth
contiguous to the existing three berths, operate and maintain the facilities and provide services
at its sole cost and expenses. The land reclaimed and waterfront shall always be owned by GoAP
however the concessionaire shall be the owner of the assets only for duration of concession period.
The concession agreement was originally signed for a period of 20 years and has been extended
based on the revised agreements between the GoAP and concessionaire. The key aspects stated in
the concession agreement pertinent to environmental due diligence includes:

• Obtaining of all statutory and non-statutory clearances required for the package
development of all government and other agencies and authorities and the cost for
obtaining such clearances shall be the responsibility of concessionaire.
• All plans and designs of the package development shall be reviewed by GoAP prior to
implementation to ensure conformity with the total development plan and accepted
engineering design codes and practices.
• Concessionaire shall take all necessary measures to ensure compliance with all
environmental laws and laws relating to pollution and shall be entirely liable to any
violations or breaches thereof attributable to concessionaire.

29. Supplementary agreements to the concession agreement were signed between GoAP and KSPL
on 25-Aug-2003 and 28-Jan-2009 modifying some of the clauses under the original agreement taking
into account, the overall circumstances and long term viability of the package. The key points being :

• The concessionaire shall have the freedom to develop new berths / facilities within the
Deep Water Port. However, GoAP can construct and operate their berth(s). In all other
cases concessionaire has first right of refusal.
• Additionally the supplementary agreements states that the land if any available and also in
future as and when any lease agreements entered with GoAP by the port users expire, first
right of refusal may be offered to KSPL, in deep water port except the areas earmarked for
ship-building units, fishing harbour and land being used for government purpose.
• KSPL has been granted permission to establish the ship building activity in the earmarked
land as per the approved master plan of Kakinada port for land use and water front.
Currently KSPL is also undertaking the construction of the 5th, 6th and 7th Berth (berth 5th
and 6th completed). Other future expansion activities include setting up of a floating LNG
terminal.

2.2 APPRAISAL OF ENVIRONMENT AL CLEARANCE – 4 T H BERT H & OSV


T ERMINAL

30. The documents related to the Environmental Clearance granted by MoEF for the 4th berth & OSV
facility (Refer Annexure 2-1) was reviewed. The status of the compliance to the specific conditions
subject to which the clearances has been granted is reported below. It may be noted that specific
conditions under which the environmental clearance was granted relate to “during construction stage”
- 11 -
activities. The below mentioned compliance reporting is based on the information shared by the
developer during the site visit and documents shared depicting the status of activities carried out in the
past.

SR SPECIFIC CONDITIONS COMPLIANCE STATUS


1 The dredged material from the maintenance dredging Complied - The dredged material from maintenance
activity should be dumped at the same location where the dredging disposed into the ongoing dumping site only. The
dumping is ongoing. The height of the dumping should dumping site did not exceed more than 25 meter height.
not exceed 30 mts.
2 The reclamation should be carried out using the sand Complied - For reclamation sand was used from the sand
from sand trap. trap.
3 Geo textile base should be provided to prevent Complied– Already provided at stacking yard.
percolation at the stacking and storage site.
4. Drill oil, metal cuttings during construction should be Minute quantities of drill oil, metal cuttings which aroused
properly collected and disposed at approved disposal from the construction activity collected with care and
areas identified by APPCB. disposed to recyclers
5 Adequate precautions should be taken to contain spillage Complied as reported by KSPL
and pollution of the coastal water as per the standard
practices observed in the port.
6 The impact of the project on Coringa should be studied As per NIO (National Institute of Oceanography) report
by NIO and the recommendations should be (report not available with the consultants) there was no
implemented. Steps should be taken to promote impact on the Coringa and mangrove plantation.
additional mangrove plantation in the Coringa mangroves
including opening up of the freshwater sources to be
provided.
7 Measures to prevent spontaneous combustion of the coal Complied with - All coal yards are arranged in such a way
in the yard. that water sprinkler should meet the corner position also.
Further temperature recording for minimizing the risk of
spontaneous combustion in the coal yards.
8 Measure to prevent the dispersion of dust should be Implementing dust suppressions measures like continuous
implemented. sprinkling of coal stacks / wetting of roads / usage of max
sweeper (dust sweeping machines) etc
9 The NIOT report on erosion, littoral drift study along with Implemented the recommendations of NIO during the
the recommendations of the study should be provided construction stage as reported by KSPL
and the recommendations should be implemented.
10 All the recommendations listed in the Environmental Implemented the recommendations of EMP document.
Management Plan, Environmental Impact Assessment (Water sprinklers arranged, Road sweeper for control of
report prepared by NIO should be strictly implemented. fugitive emissions, Restriction of vehicular movement, Oil
spill control, Proper disposal of dredge material, Using of
sand in the sand trap for reclamation works as reported by
KSPL)
11 The dredged material obtained should be utilized for Complied with - The capital dredged material was used for
filling up of back up area. filling the backup area wherever feasible.
12 The recommendations of CWPRS (Central Water & Implemented the recommendations of CWPRS.
Power Research Station) mathematical model studies
with respect to hydrodynamics should be implemented.
13 Appropriate shore erosion measures should be taken up As per NIO report there is no specific shore erosion impact
as indicated in the report of NIO. due to our project.

14 All the conditions stipulated by the Andhra Pradesh Complied as reported by KSPL
Pollution Control Board in their consent order No.
APPCB/VSP/RJY/451/CFE/HO/2006, dated: 6-7-2006
should be effectively implemented.
15 Sewage arising in the port area should be disposed off Septic tank followed by soak pit for the disposal of sewage
through septic tank – soak pit system or shall be treated wastewater, and further STP provided and treated water
along with the industrial effluents to conform to the used for on land irrigation for small part of the green belt.
standards stipulated by APPCB and shall be utilized/re-

- 12 -
SR SPECIFIC CONDITIONS COMPLIANCE STATUS
cycled for gardening, plantation and irrigation.
16 Adequate plantation should be carried out along the Ongoing Activity - Avenue plantation all along the road
roads of the port premises and a green belt should be and blocked plantation in vacant premises.
developed. (Proposed 10-meter green belt along the periphery of the
Backup area of the 4th berth and OSV complex)
17 There should be no withdrawal of ground water in CRZ The fresh water for construction activity was supplied
area, for this project. The proponent should ensure that through tankers by an external party. No withdrawal of
as a result of the proposed constructions, ingress of ground water from CRZ area for this project was
saline water into ground water does not take place. undertaken and it is only through third party suppliers.
piezometers should be installed for regular monitoring for
this purpose at appropriate locations on the project site. Piezo wells were installed for monitoring of ground water/
leachate collection.
18 The project should not be commissioned till the requisite All necessary approvals from the concerned departments
water supply and electricity to the project are provided by and all applicable clearances were obtained.
the PWD/Electricity Department.
19 Specific arrangements for rain water harvesting should Rain water structures were already provided at all water
be made in the project design and the rain water so flowing / collecting areas as reported by KSPL during the
harvested should be optimally utilized. Details in this interactions.
regard should be furnished this Ministry’s Regional Office
at Bangalore within 3 months. The copies of reports submitted to the MoEF’s office were
not available.
20 All development activities and the facilities to be All the construction activities were carried out according to
constructed in CRZ area as part of this project should be the CRZ rules only.
strictly in conformity with the provisions of the CRZ
Notification, 1991 as amended subsequently.
21 Green buffer zone should be provided all around the
The development of the green belt is ongoing currently
project area in consultation with local forest department
and additional green areas are being developed by the
and the report submitted to this Ministry’s Regional Office
concessionaire.
at Bangalore.
22 No product other than those permissible in the Coastal Being Complied with as reported by KSPL
Regulation Zone Notification, 1991 should be stored in
the Coastal Regulation Zone area.
23 The project proponent should undertake up activities to KSPL has been arranging drinking water in the nearby
improve the quality of life of the local people living along wards / fishing community and residents of Hope Island for
the project site. The activities should include supply of the consumption of the general public, and also RO plants
drinking water, providing rainwater harvesting structure. installed under the mandatory CSR initiatives.
24 The relocation of the fishermen community should be No relocation was required for this project during the project
done strictly in accordance with the norms prescribed by construction stage as no habitation was covered within the
the State Government. The relocated fishermen project area.
community if any will be provided with all facilities
including health care, education, sanitation and
livelihood.

The general conditions under the EC granted were also adequately complied by the concessionaire /
KSPL as informed during interactions with the officials of KSPL.

31. There are no pending non - compliances against the general & specific conditions under
which the EC has been granted. However the tasks for development of the proposed green belt
(10-meter green belt along the periphery of the Backup area of the 4th berth and OSV complex)
are yet to be completed. The KSPL officials did highlight the low survival rate of saplings and
not so favourable soil conditions as reasons for slow progress on the development of green belt
but confirmed its commitment to develop the same as per the statutory requirements.

- 13 -
2.3 APPRAISAL OF T HE EIA DOCUMENT (5 T H , 6 T H & 7 T H BERT H)

32. The review of the EIA document reveals that the area is predominantly agriculture oriented with
crops like sugarcane and paddy as predominant crops. The area has predominantly agricultural
labourers and industrial workers. The proposed project area is devoid of any major natural vegetation.

33. There is no anticipated rehabilitation of the village / community due to the proposed expansion of
the port. The following activities are being carried out by KSPL towards environmental management
during the port operations:

• Green belt development in the port area

• Dust suppression

• Ambient environmental quality monitoring

34. The port terminal area is not in vicinity of any ecologically sensitive zones like an estuary or
mangrove forest areas. No significant irreversible impacts are identified in the EIA study. The impacts
identified are short term, localized impacts mainly during the construction stage both for marine-side
and land-side. The construction stage impacts include:

1. Changes in the current pattern

2. Increased turbidity levels and DO levels

3. Suspended sediment

35. No impacts are envisioned for the fishing activity being carried out from the fishing harbour located
north of the existing facility and also near the anchorage port. The dredging activity is confined
within the immediate vicinity of the port hence no significant impacts are envisioned. The monitoring
reports shared by KSPL also confirm that the impacts due to increased sediment and turbidity
levels are restricted to construction site / berth only.

2.4 WAT ER SUPPLY AND WAST E WAT ER GENERAT ION

36. As per the information shared by KSPL, the waste water generation is domestic in nature and no
hazardous waste water is generated, and for treatment of domestic waste water, a STP is installed and
treated water is used for gardening or irrigation within the STP area. An ETP is under construction and
is expected to be completed by Nov 2015. The treated water from STP is being used for gardening,
plantation purposes. The estimated waste water generation (KLD) after implementation of expansion
shall not exceed the following:

Quantity (KLD)
Sl.No Source
Existing Expansion Total after expansion
a) Domestic 25 KLD 20 KLD 45 KLD

37. There is no extraction of ground water, and water supply is through third party supplier as
mentioned in the table below:

- 14 -
Sl.No Purpose Quantity (KLD)
Total after
Existing Expansion
expansion
a) Dust suppression 500 KLD 100 KLD 600 KLD
B) Domestic & Gardening 90 KLD 55 KLD 145 KLD
Total 590 KLD 155 KLD 745 KLD

38. KSPL is complying with the statutory requirements by ensuring that no ground water
extraction is being undertaken; the water requirements for domestic purposes, offices, dust
suppression etc are met through an external third party supplier, ensuring that the domestic
waste water generated is treated and reused after treatment in gardening & plantation related
activities.

2.5 EMERG ENCY PREPAREDNESS & RESPONSE PL AN

39. The port complex is equipped with adequate water storage and other fire fighting facilities in all fire
prone areas. The details of the facilities and manpower to handle emergencies round the clock are
mentioned in the subsequent subsections:

2.5.1 FIRE F IGHT ING

40. KSPL is having a 20 member Fire Emergency Team for Fire Fighting which operates on shift basis
round the clock. In addition to this a separate Safety Team comprising of 7 members, also work on shift
basis round the clock to tackle any emergencies. Apart from this 24X7 Emergency Ambulance Service,
Dock Inspectors, Mechanical Staff, Marine Operational Staff and in-house Security are all trained to co-
ordinate Emergency Situations in Port. The list of firefighting equipment with KSPL is as follows:

• Main Fire pumps : 3 No’s • Nozzles : 11 Nos Fixed Jet type


• Jockey Pump : 1 No. (30HP) & 4 Nos Universal type
• Cooling Water pump : 1 No (7.5 HP) • International shore coupling: 02 Nos
• Tower Monitors : 2 Nos • Foam Making Branch : 01 No
• Foam Tanks : 2 Nos (Each tank • Siren : 01 No
capacity 3000 Ltrs.) • 10 kg DCP Extinguishers : 61 Nos
• Water curtains : 2 Nos • 75kg DCP Extinguishers : 04 Nos
• Motor Operated Valves : 3 Nos • 05kg DCP Extinguishers : 03 Nos
• Ground Monitors : 4 Nos • 3.2kg DCP Extinguishers : 02 Nos
• Double Hydrants : 5 Nos • 4.5kg CO2 Extinguishers : 31 Nos
• Single Hydrants : 12 Nos • 09 lts Mechanical Foam : 21 Nos
• Hose Boxes : 17 Nos • Fire Entry Suits : 02 Nos
• Hoses : 34 Nos Canvas hoses • Breathing Apparatus : 04 Nos
& 10 Nos Synthetic Rubber Hoses
41. Apart from above, a dedicated & sophisticated multipurpose Fire Tender is available to combat fire
emergencies in & around the port with 9 member dedicated team which operates round the clock on
shift basis.

- 15 -
42. No major fire incidents have been reported in the past within the Port terminal area except one
instance of fire in the conveyor belts for coal transfer due to excessive heating. KSPL has also
responded to fire emergencies outside the port area as part of their Corporate Social Responsibility.

2.5.2 ONSITE AND OFF SITE D ISASTER MAN AGEMENT PLAN

43. The risk assessment & emergency response manual provides guidelines for dealing with natural
(storms / earthquake) and man-made disasters (fire, explosions, terrorist attacks, and discharge of
effluents to water, collision and escape of inflammable or toxic gases). The manual provides guidelines
for minimizing losses to life, environment and property; systematic response to the crisis situations.

44. The manual lays down the institutional setup, roles and responsibilities of the KSPL staff on duty to
handle emergency scenarios. It was observed during the site visits that adequate signs depicting
assembly areas, hardhat areas etc and emergency numbers are displayed adequately within the port
premises. KSPL also conducts regular training and mock drills (at least twice a year) to train staff and
workers in handling emergency situations.

KSPL is adequately complying with the emergency response management in case of natural
and man-made disasters and have a trained manpower to undertake such tasks with a sound
institutional mechanism for implementation.

2.6 ENVIRONMENT AL MONIT ORING PRO GRAMME

45. The monitoring is being carried out on monthly basis through a third party consultant. The
monitoring locations and plans which have been deduced in consultation with Regional Office of
Andhra Pradesh Pollution Control Board (APPCB) Kakinada are as follows:

I. Stack Monitoring for SO2, NOx & SPM b. OSV Berth II


a. 5 DG sets: 125 KVA & 250 KVA & c. Near OSV Sub Station
03x500 KVA capacities.
d. Outside OSV DG Set room
II. Ambient air Quality Monitoring for SO2, NOx,
e. OSV Gate
PM10 & PM2.5
f. Vth Berth area
a. Top of Fire Pump House
g. Vth Berth Back Up area
b. Top of Control Room Building
h. VIth Berth area
c. Near Cairn Office Building
i. VIth Berth Back Up area
d. Near Customs Office Building
j. Gate 4 entrance
e. VIth Berth area
VI. Sediment Quality
f. VIth Berth Back Up area
a. VIth Berth area
III. Domestic Waste Water Quality Monitoring
a. At inner Canteen Area (STP Inlet)
b. STP Outlet
IV. Marine Water Monitoring
a. VIth Berth Area during Low Tide
V. Noise Monitoring
a. OSV-Berth I

- 16 -
KSPL is adhering to the guidelines for regular monitoring and reporting on the ambient
air quality monitoring (stack emissions), waste water monitoring, noise monitoring and
marine water quality by hiring the services of an approved testing laboratory services.
The monitoring results for May 2014, June 2014, July 2014, Aug 2014 and Oct 2014
declared by the laboratory were shared with the consultants and found to be within
permissible limits for all parameters. The KSPL officials also shared the yearly
compliance reports submitted on Sept 2013 and Sept 2014 and the reports were found to
be satisfactory.

2.7 DREDGING & L AN D RECL AIMAT ION ACT IVIT IES

46. The dredge material disposal and dredging tasks were carried out as per the EMP
guidelines. As per the EIA document and information shared by KSPL, the dredged material
from the sand trap is being used for reclamation of the backup areas for the multipurpose berth.

47. About 80% of the maintenance dredge material from the channel and berths area is being
used for beach nourishment and transferred to the northern side to maintain the continuity of the
littoral drift. The remaining dredged material is being disposed at the designated site 15 kms
north of the Deep Water Sea Port. As regards the 5th, 6th & 7th berth EC, the proponent is
complying with the following as informed during the site visits:

S No Solid Waste Quantity Treatment & disposal


1 Capital dredging material 3.2 million cum. Back filling at disposal site as
Maintenance dredge approved by the competent
2 0.66 m3/year authorities.
material
To disposed to recyclers authorized
3 Waste Oil 300 Lts/year
by APPCB.

2.8 GREEN BELT DEVELOPMENT

48. A total of 12 acres of green belt has been developed by KSPL as per the following details:

• 5 m wide along the periphery of the back-up area of the multipurpose berth at S-
Bund internal Road.
• Along the length of the main approach road.
• Along the OSV Internal Road.
• Along ADB road about 2.5 km stretch (recently undertaken)
• Opposite all port offices viz., Operations, HSE, Projects, Security etc.

-17-
49. As per the information shared by the concessionaire, an area of approximately 12 acres has
been converted to green areas within port complex. Additionally 5 acres at Port Administrative
Building and 2 acre at existing vacant pockets in the port are planted. The concessionaire plans
to develop 45 acres of green plantation areas within the port area as per the conditions under
which NOC has been granted. The details of the 12 acres of green belt is mentioned below:

50. Owing to the saline conditions and black soil the development of the green belt is slow and
difficult. As per the information shared by KSPL, 27,667 saplings have been planted and more
plantations are proposed to be planted. The development of green belt is currently under way to
meet the requirements.

KSPL would need to put in additional efforts to ensure early completion of the targeted
green cover based on which the two EC’s has been granted for 4th Berth and 5th, 6th & 7th
Berth separately.

2.9 ST AT US OF ST AT UT ORY COMPLIAN CE– ENVIRO N MENT AL

51. The table below provides an outline of the applicable regulatory requirements and overall
representation of the statutory compliance followed by the concessionaire. The status is based
on the information shared by KSPL, review of the documents shared by IIFCL/KSPL and
interactions held with the KSPL officials during the site visit.

Statutory Remarks / Status


Requirements

Environmental • EC from CRZ & EIA notifications for 4th Berth and OSV facility
Clearance (EC) and granted on 31 Jan 2007 to handle iron and coal.
CRZ clearances for • NOC from AP Pollution Control Board granted on 06 July 2006
construction of 4th
• Copy of EIA / EMP documents was not made available to the
Berth
consultants – hence could not be reviewed.
• 10-meter green belt along the periphery of the backup area of
the 4th Berth and OSV complex. (Ongoing activity at present)
(Refer Annexure 2-1)
• Year wise expenditure statements on environmental safeguards.
SPECIFIC CONDITIONS FOR GRANT OF NOC
• Adequate plantation along the roads of the port premises and
green belt to be developed. (Ongoing activity at present)

Environmental • EIA Report pertaining to 5th, 6th and 7th Berth at existing facility
Clearance (EC) and (April 2010) - Reviewed.
CRZ clearances for 5th, • EC from CRZ & EIA notifications granted for 5th, 6th and 7th Berths
6th and 7th Berths
(Refer Annexure 2-2)

-18-
Statutory Remarks / Status
Requirements

Consent to Establish • Based on the review of the documents shared, consent granted
Under Water & Air Act under section 25/26 of Water Act; Section 21 of Air Act was valid till
30th Sept 2014. Renewal application filed by developer on
26.08.2014, reply still awaited (expected by mid Feb. 2015)
• STP is operational and ETP is expected to be operational by Oct
2015 as per the information shared by the developer.
• Based on the information provided by the developer, water supply is
through an external third party supplier and no ground water
extraction is undertaken by KSPL.

6 - Monthly report • Reports submitted for the half year ending Sept 2013 were reviewed
submissions and found satisfactory.
Water Cess (Form – 1) • Form 1 for Nov 2014 shared by the developer and found
returns satisfactory.
Labour Licence • Registered under the Contract Labour (regulation & abolition) Act
1970 till 31-12-2014

Accident Risk and • Certificate issued by Bharti AXA valid till 31-03-2015
Group Health
Insurance
Minimum Wages Act KSPL is complying with the Minimum Wages Act as informed during
the site visit.
Child Labour KSPL is complying with the requirements under the Act as informed
(Prohibition and during the visit.
Regulation) Act, 1986 No child labour was seen during the site visits.

The building and Other As the construction activities are being carried out by the contractor
Construction Workers and not directly by the developer, the liability to pay cess rests with the
(Regulation of contractor.
Employment and
Conditions of Service) However KSPL ensures that the contractor has paid the cess as per
Act 1996 and the Cess the regulatory requirements before payments are released to the
Act of 1996 contractor by developer.
Factories Act 1948, Factories Act is not applicable to KSPL operations as informed by
with AP State Rules KSPL

Environment, Health Occupational Health, Safety and Environment Management Plan in


and Safety Provisions place including accident reporting,

Forest Diversion / No Forest land diversion was undertaken for the port terminal area.
Clearance

Handling and Storage • Authorization granted under HW (MH & TM) Rules 2008

-19-
Statutory Remarks / Status
Requirements
of Hazardous • Annual Hazardous Waste Filing (Form-4), submitted on 28-06-2014
Substances for year ending March 2014
Public Liability • The insurance policy documents received from the developer are
Insurance valid till April 2015.

Consent for handling • Individual parties handling Hazardous Cargo obtain these licenses
hazardous materials separately. KSPL is not directly handling such cargo.
and hazardous waste • The Pollution Control Board license granted to KSPL is inclusive of
Hazardous License for Port.

Consent for diesel • In order to control the noise levels in vicinity of the operational DG
storage and operation sets, the State Pollution Control Board has suggested certain
of DG sets up to a mitigation measures which are being compiled by KSPL.
capacity of 800KW

Provision of cargo • The review of the document states that the consent has been
storage and wind granted for maximum height up to 8 meters & wind barrier of 12
barrier meters around cargo storage areas.
• It was observed during the site visit that additional mitigation
measures are required around the coal terminal area to control
dust suppression.
Mechanized fully • The review of the documents reveals that the mechanized systems
closed conveyor belt are in place for coal and fertilizers at 5th and 6th Berth operations.
with water sprinkling • For the 4th Berth, handling is being done in a semi-mechanized
arrangements for dust manner.
suppression
• During site visit period the mechanized conveyor belts were under
maintenance.
• Dust suppression by sprinkling water on Roads, Berth and yard
areas is practiced.
• All the vehicle involved in transportation of cargo shall be covered
with tarpaulin –
• It was observed during site visits that provisions were
undertaken to control dust suppressions. However additional
measures are required to fully control dust suppressions.
• All the transfer point, loading / unloading points and conveyer
systems are housed completely with leak proof arrangements.
Adequate dust suppression and containment measures need to be
implemented for effective control of fugitive emissions.

Onsite and Offsite • The onsite emergency and disaster management plan is adopted by
disaster management KSPL
plan

-20-
Statutory Remarks / Status
Requirements

Fire Emergency Team • Dedicated and trained 20 member fire emergency team working in
shifts round the clock to tackle any crisis
• Safety audit and training conducted at regular basis as informed by
KSPL.

Development of green • As per the CFE (Consent For Establishment) conditions, the port
belt within one year shall develop within one year properly designed green belt giving
giving due due consideration to dust generation and meteorological conditions
consideration to with minimum width as committed in letter dated 30.04.2014 and
sources of dust report compliance every three months to RO-Kakinada.
generation and • The development of the green belt is currently ongoing. New
metrological conditions plantations have been undertaken along the ADB road giving
due consideration to dust generating areas near the dry cargo
handling facilities.
Submission of • Environmental Monitoring being carried out by a third party.
environmental • Results of the marine and ambient environmental quality monitoring
statement on a yearly (ambient air quality, marine water sample, sediment sample for 6th
basis berth area) for month of year 2014 was shared by the developer.
• Environmental statement submitted in Sept 2013 & Sept 2014
shared by KSPL
Disposal of the Dredge • Undertaken at a designated site (at Uppada) in sea approximately
Materials 15 km north of the port area.
• A visit to the site could not be conducted due to the turbulent sea
conditions and absence of permission from the coast guards.
Reclamation of land • A part of the dredge spoil is used for backfilling and remaining is
parcels for expansion being dumped at the disposal ground.
of port terminal

2.10 PUBL IC H EAR ING AN D D ISCLOSU RE OF INFOR MAT ION FOR


5 T H , 6 T H & 7 T H B ERT H

52. As per the information shared by KSPL and minutes of the public hearing meetings (as part
of the EIA requirements for 5th, 6th and 7th Berth) no special demands were raised by the Public.
The issues raised during the public hearing for EIA were predominantly focused on the
measures to improve the environment and employment opportunities for the local people. The
other environmental issues highlighted by the participants during the hearing was with regard to
safety and health problems of workers; allowing fishermen fishing in the ocean and adequate
measures in disposing the dredged waste materials.

-21-
53. The issues raised by the local community are addressed by the KSPL by way of providing
employment to the local fishing community, conducting regular health checkup camps for the
workers, and ensuring the fishermen community that there are no restrictions on fishing by them
from KSPL. The avenue street lighting for beach road emerged as one of the key expectations in
the hearing which has already been implemented by KSPL.

2.11 SIT E OBSER VAT ION S

54. The following key observations are concluded based on the site visit and available
documents including interactions with the KSPL officials:

• The environmental clearance for 4th Berth & OSV facility and 5th, 6th and 7th berth were
obtained under EIA and CRZ notifications.
• The port terminal does not require any clearances under the Forest Conservation Act as
no forest land parcel was ever acquired. Most of the land has been reclaimed.
• The details about the borrow areas / quarry sites (site locations, closure plans and its
implementation etc) were not made available to the consultant.
• The port terminal has obtained necessary clearances from MoEF / State Pollution Control
Board under Air & Water
Acts and other regulatory
organizations and has
been complying with the
reporting requirements
based on the information
shared by KSPL.
• It was observed during the
site visit that the basic
facilities provided by the
contractor to the
construction labourers at labour camps (for ongoing port expansion activities) are
inadequate and needs further strengthening as depicted in the snaps below. KSPL has the
overall responsibility to ensure compliance to the regulatory requirements for themselves
as well as the sub lease partners/ sub contractors/ any third party operating within the Port
terminal area.
• The health and safety compliance are kept as contractor’s responsibility in sub contracting
by KSPL.
• The development of green belt and additional plantations are being undertaken by KSPL.

-22-
• During the field visit it was observed that the workers were seen wearing safety gears at
work site, adequate safety related signs were displayed at various locations in the port
terminal area.

• Water sprinkling was being done on a regular basis as observed during site visit in areas
handling dry cargo and on the main access roads.
• Fire extinguishers are installed and adequate training programs and mock drills are
conducted by KSPL on a regular basis for the staff and workers as observed during site
visit.
• The sub project did
not impact any eco
sensitive zones /
critical natural
habitats. None of
such impacts are
expected in the port
expansion activities.
The land
requirements are met
through land
reclamation only.
• Periodic environmental quality monitoring including marine environment is carried out
regularly by third party agency appointed by KSPL.

-23-
55. Project developer has confirmed that hazardous materials wastes are being
handled by a third party and disposed in an environmentally safe manner. Majority of
these activities are applicable for the complete port terminal area and cannot be looked in
isolation for the due diligence tasks. Overall the development of the port during phase 1
and phase 2 did not have any noticeable adverse impacts.

2.12 CONCL USIO NS

56. Based on the review of the available information, reconnaissance site visits,
interactions with the KSPL officials and local fishermen community in vicinity of the port
area, it can be established that the concessionaire i.e. KSPL is adhering to the statutory
requirements as per the national and state regulations and is committed to protection of
the environment while performing its activities.

57. A random internet search also did not reveal any pending legacy issues related to the
Kakinada Deep Water Port or its operations. As part of the CSR initiatives, KSPL has also
responded to the fire emergences beyond the port area in the past.

58. KSPL however need to strength their efforts in establishing green cover in the port area
as per the conditions stipulated under the EC granted.

-24-
3 SOCIAL COMPLIANCE & ISSUES

3.1 FRAMEWOR K FOR SOC IAL DUE D IL IGENC E

59. The Terms of Reference for the ESDD envisage review of the following aspects as part of
Social Due Diligence

• Magnitude of land acquisition and resettlement impacts in the project;


• Outcomes of Resettlement and Tribal Development Plan implementation, if
applicable;
• Outstanding grievances and complaints, if any;
• Any court reference cases on land acquisition matters and pending compensation
payments; and
• Summary of consultations held in affected villages and with other stakeholders
during construction phase, if available and based on this, assessment of
implementation status of outcomes of public hearings/ consultations.

60. The ToR also anticipate ESDD to cover any proposal for the preparation and implementation
of a “Community Development Plan” to meet the pressing and priority needs of the villagers in
the Project Area under their CSR initiatives during the construction and operation phase.

61. In light of the anticipated due diligence requirements of the study, there are four critical
elements:

• Delineating the project area for the purpose of study and understanding the project
structure
• Assessment of development activities, the land requirements and its procurement
under the project
• Social impact of the project in the project area including achievement of recorded
community expectations as part of the public hearing/ consultation process
• Initiatives by the project developer to address the community needs as part of the
CSR Initiatives as well as integration of communities in the project development
process

62. Social Due Diligence for the Kakinada Deep Water Port (KDWP) Project has been carried
out on the basis of review of project documents and documents available in the public domain
including:

-25-
• Concession Agreement for Four Shore Connected Berths at Kakinada Port signed
between GoAP and ISPL, Singapore dated March 19, 1999
• Supplementary Agreement to the Concession Agreement for Four Shore Connected
Berths at Kakinada Port signed between GoAP and KSPL (SPV constituted by ISPL
in the name of Cocanada Port Company Limited and Assignment Deed signed in
favour of CCPL on April 2, 1999, CCPL was renamed as Kakinada Seaports Limited
on September 18, 2001) dated August 25, 2003
• Second Supplementary Agreement to the Concession Agreement for Four Shore
Connected Berths at Kakinada Port signed between GoAP and KSPL dated January
28, 2009
• Project Agreement dated August 10, 1990 between Asian Development Bank and
the Government of Andhra Pradesh. The loan agreement was applicable for
financing the initial development of Births 1-3 by the GoAP.
• Government Orders issued by GoAP with regard to KDWP and other Port Projects
in the State
• Report No. 3 of 2013 Government of Andhra Pradesh - Report of the Comptroller
and Auditor General of India on Economic Sector
• Environmental Impact Assessment (EIA) Report (for proposed multi-purpose berths
V, VI and VII at existing facility), April 2010 including Compliance of Public Hearing
Points
• Take-out Agreement signed between KSPL, IIFCL, State Bank of Patiala and Union
Bank of India dated July 27, 2012
• Guidelines of Corporate Social Responsibility Funds, District Collector East
Godavari District dated June 1, 2013
• PPP TOOLKIT for Improving PPP Decision-Making Processes, Ministry of Finance,
GoI, Case Study of Kakinada Port

63. The following information has been provided by the Developer with regard to the
implementation of social safeguards and the corporate social responsibility.

• Implementation Status of Compliance of Public Hearing Points as reported by the


KSPL
• Information regarding CSR activities undertaken by KSPL

64. In addition to the documents reviewed and the information provided by the Developer, the
community in the project area was contacted to understand the project impact and also the
selected CSR initiatives taken up by the Developer were visited and the beneficiary community
consulted regarding the benefits.

-26-
3.2 PROJECT ST RUCT URE AND D EL INEAT ION OF PROJ ECT AR EA

65. Kakinada Port comprises of Kakinada Anchorage Port and Kakinada Fishing Harbour
(managed departmentally by the Director of Ports), and Kakinada Deep Water Port (developed
by GoAP and handed over to a private developer KSPL). The present study is limited to the
Kakinada Deep Water Port being managed by KSPL. However, from the perspective of impact
area, parts of Kakinada municipal area (mainly the fisherman colonies), Village Suryapet and
fishing harbor community falls within the immediate surroundings of the Project area (KDWP) on
the land side and Hope Island fisherman community on the water side. The major interventions
made as part of the community development activities under the CSR concentrate on these
areas.

The GOAP recognized the importance of port development due to major developments in power
sector, industrial development, agricultural activities, fisheries development and mineral
exploitation etc in light of the initiation of liberalization process in the Indian economy in early
1990’s. Kakinada Deep Water Port (KDWP), located in East Godavari District and comprising
three berths and other related infrastructure, was developed by GoAP between 1993 and 1996.
GOAP decided to operate the three existing shore connected berths, develop and operate one
more berth contiguous to the existing three berths and perform certain aspects of operation
maintenance and management of common facilities of the entire port through private
participation.

66. The Government of Andhra Pradesh had initiated the process for privatization of Kakinada in
1994 and finally the process could be successfully culminated in March 1999 with the award of 3
+ 1 berths at KDWP to the International Seaports Pte Limited, Singapore (ISPL) consortium, led
by Larsen & Toubro (India) Ltd., on Operate, Maintain, Share and Transfer (OMST –for three
berths)/Build Operate, Share and Transfer (BOST- for fourth berth) basis. Posts signing of
Concession Agreement in March 1999, the project facilities at existing three births for operations
were handed over to the SPV and the operations were commenced by the SPV with effect from
April 1, 1999.

67. As per the Concession Agreement, the development was envisaged to be completed in two
phases. The Phase 1 Development included making the existing three berths fully developed for
cargo handling, storage etc and Phase 2 development involved construction of the fourth berth
(300 meters long) contiguous to South of the three berths and providing of cargo handling and
storage arrangements and other associated facilities. The developer was required to prepare
plan for execution of Phase 2 Development (addition of fourth berth) on achievement of berth
occupancy of 65% for a year and complete the execution within 24 months of its
commencement. The Fourth Birth was commissioned in March 2008.
-27-
68. KDWP project was amongst the first private sector port projects in the country and was
launched at a time when such experience was not available in the country related to Concession
Agreements for the Port Projects and also in terms of defining the risk sharing mechanisms.
Based on the experiences gained during the execution of Agreement, several issues were
identified in the Concession Agreement including the ones emerging due to policy changes and
signing of concession agreement for other ports. In view of factors affecting the viability of the
project (primarily due to the non-realization of estimated traffic and the high component of MGA
that the developer had to pay to GoAP and the advantageous position for the other Competitor
Port Operators who entered agreements at later dates with different terms and conditions of the
Concession Agreement), several discussions and negotiations took place between the GoAP
and KSPL based on which two supplementary agreements to the original concession agreement
have been signed during 2003 and 2009 respectively.

69. The major changes as mutually agreed between GoAP and KSPL include revision in
concession period, freedom for future development, revisions in revenue sharing and removal of
minimum guarantee provisions, revision in provisions related to requirement of additional lands.
Following the amendments in the Concession Agreement in 2009, KSPL initiated the process for
3 additional births, out of which two additional berths (fifth and sixth berths) were commissioned
in 2011-12 and the seventh is under commissioning.

Figure-3.1: Master Plan for Kakinada Port for Land use and Water Front (2020)

Berth-1 to 4
Phase-1 and Phase-2

70. Figure-3.1 shows the Master Plan for Kakinada Port for Land use and Water Front (2020)
prepared by the Government of Andhra Pradesh, which clearly shows that majority of the Port

-28-
related activities are concentrated on the eastern side of the Samalkota-Kakinada Bypass except
for a narrow strip of proposed activities on the western side of the road. The Outline of the
Master Plan area (red outline) has been superimposed on the google earth image along with
demarcation of existing KDWP boundary of development (blue outline) in Figure-3.2. The
chronological development of KDWP over a period of 2005 to 2014 is already explained in
Section 1.1 also clearly shows that majority of the development has started coming up post
2009.

Figure-3.2: Master Plan and KDWP Boundaries on Google Earth

71. The safeguard implementation during the construction stage as per applicable policy
provisions has been reviewed to identify any residual issues based on the information available
in public domain. The extent and scope is limited to post COD Phase-1 and Phase-2 activities
included as part of takeout financing by IIFCL. Being a post COD due diligence study, the focus
of the social due diligence is more on the compliance of provisions under the Concessionaire
Agreement and the prevailing national laws related to social safeguards.

3.3 LAND ACQU ISIT ION AND R ESETT LEMENT IMPACT S UND ER
T HE PROJECT

72. The Project involved transfer of land under the existing Port developed by the GoAP during
the period 1993-96 which became operational in 1997 and was being operated by GoAP till it
was transferred to KSPL in 1999. The Port was built primarily in the submerged and partially
reclaimed land in the coast area falling in the jurisdictions of the Government as is clearly evident

-29-
from Clause 3.2 of the Concession Agreement regarding the land area leased which reads as
follows:

73. “Clause 3.2: The land areas (including the submerged areas) to be leased by the GOAP to
CONCESSIONAIRE upon execution of this Agreement are indicated in Annexure C (Figure 3.3
below). The partially reclaimed area behind the three berths will be treated as land area for the
purposes of lease charges.”

Figure 3.3: Project Area as per Concession Agreement (Four Berth Terminal)

74. The Clause 3.2 of the Concession Agreement has been amended as per the Second
Supplementary Agreement signed in 2009 and now reads:

75. “The land area (including the submerged areas) to be released by the GoAP to
Concessionaire upon execution of this Agreement, area indicated in Annexure-C of the
Concession Agreement dated 19.3.1999. The partially reclaimed areas behind the three berths
will be treated as land area for the purpose of lease charges.

76. GoAP shall offer land if any available and also in future as and when any lease agreements
entered with GoAP by the port users expire (both annual and long term), first right of refusal may
be offered In KSPL, in deep water port, except the areas earmarked for ship- building units,

-30-
fishing harbour and land being used for Government purpose." The area excluded from the
purview of the Concession Agreement is marked with green circle in Figure 3.1.

77. The issue related to land status and ownership was also confirmed during the site visit from
the Developer and the residents of surrounding fishing harbour settlement (settlement has come
up on government land) and it has been confirmed that the land under the KDWP belonged to
the government and no private land was acquired for the KDWP.

78. The Concession Agreement does not provide the exact extent of land (except the map) area
including the submerged area that was transferred to KSPL as part of initial Three Berth Port
handed over in 1999. As informed by KSPL, the GoAP had transferred about 65 Acres of land
(including submerged land) at the time of initial transfer.

79. During the process of expansion, KSPL reclaimed an area of about 360 acres and further
plans to reclaim an additional 153 acres for future developments, which can be seen in Figure
3.4 below.

Figure-3.4: Layout of KDWP including Future Berths

80. Clause 2.25 of the Concession Agreement defines the term Premises as:

“The Premises means and includes (1) land (including submerged land) given on lease by the
GOAP to the CONCESSIONAIRE (2) all structures and facilities constructed or provided by the
GOAP on Premises sub component (1) above; (3) land reclaimed by the CONCESSIONAIRE
during the pendency of this Agreement; (4) all structures and facilities including modifications
constructed or provided by the CONCESSIONAIRE or its sub-contractors or any other assignees

-31-
on the Premises sub components (1) to (3) above during the pendency of this Agreement and
(5) Tugs, pilot launches and other flotilla for providing services to the ships, all above within limits
of Kakinada Port.”

81. It clearly establishes that except for the initial government land leased by the GoAP
(including submerged land), the remaining land has to be reclaimed by the Developer. Under this
project, the acquisition of land was not anticipated and hence there is no clause in the
Concession Agreement which refers to any land to be acquired and the associated
responsibilities of the Developer with regard to the social safeguards. The second important
factor is that the Concession Agreement was signed back in 1999, where the policies and
process for private port agreements were in the evolving stages. Since there was no land
acquisition involved in the project, there were no issues associated with the resettlement
impacts. Even the future expansion of births Container Zone and Cargo Zone is proposed only
through reclaimed land. Hence, no resettlement impacts are anticipated. The review of
documents available in public domain and discussions with the stakeholders clearly
reveals that there are no residual issues with regard to social safeguards implementation.

82. The subsequent Agreements for other Private Ports signed by the GoAP involving land
acquisition had provisions for the R&R package. The Government of Andhra Pradesh has come-
up with privatization guidelines to encourage the private sector in Port development. The specific
provisions related to land for private ports in the policy are:

• Government will assist in acquisition of land on payment by the investor. Wherever port
land is available, it will be provided to the parties at the rates prescribed by the
Government.

• Land required for those industries which need to be located close to a port to take
advantage of bulk handling of their materials/products, can be acquired on the basis of
feasibility report made by the investor. If the investor wants to own the land and lease out
to industries, such land can be acquired on market price under Land Acquisition Act.

3.4 COMMUN IT IES IN T HE PROJ ECT AREA - T HE IMPACT

83. As can be observed from Figure-3.4, there is an existing Fishing Harbour (green boundary in
Figure-3.5) in the north of KDWP boundary which was constructed back in 1984. In addition to
the Fishing Harbour, several huts have come-up on the harbor area (yellow boundary in Map-
3.5). The fishing harbor community resides outside the land allotted to KSPL for the purpose of
Kakinada Deep Water Port (blue boundary in Figure-3.5). As per the Master Plan for the
Kakinada Port, the fishing harbor is proposed to be relocated to further north of the existing
harbor (refer Figure-3.1) beyond the proposed break water structure and the current fishing
-32-
harbor area is proposed for future ship building activity as per the Master Plan Proposal. The
issue was discussed with the representatives of KSPL and they mentioned that decision
regarding relocation of fishing harbor is not within their purview as it falls under the Department
of Port of the state government. The operations of fishing harbor do not affect the functioning of
KDWP and they don’t intend to disturb the harbor. If the state government decides to relocate
the fishing harbor, KSPL has no controls over the decision. As per the provisions of the Second
Supplementary Agreement, “GoAP shall offer land if any available and also in future as and
when any lease agreements entered with GoAP by the port users expire (both annual and long
term), first right of refusal may be offered In KSPL, in deep water port, except the areas
earmarked for ship- building units, fishing harbour and land being used for Government
purpose". The Fishing Harbor does not fall under the purview of KSPL and hence has no
direct impact on the KSPL operations.

Figure-3.5: Fishing Harbour and Fishing Harbour Colony

84. In the initial stages of the privatization process, the stakeholder consultations were not
carried out and as a result, the two major stakeholders, i.e. the fisherman and the port workers at
Anchorage Port had lot of apprehensions with regard to loss of livelihood due to expansion of
KDWP.

85. The Fishermen working on the Fishing Harbour also had apprehensions in the initial stages
of the project regarding the likely impact on their business and livelihood. The KSPL adopted an

-33-
approach of inclusive and participative development. It worked with the people and also
explained them about the project and assured the community of not affecting their shipping
operations for fishing. The fishing harbour operations and the port navigation channel do not
conflict each other. KSPL has not put any restrictions on fishing ships crossing the navigation
channel. The KSPL has also made a provision to get the navigation channel before any ship is
brought into the channel by using the pilot boats to avoid any risks of accidents.

86. The tender documents issued by the GoAP had made certain projections with regard to the
cargo mix that included agri centric cargo like fertilizers, oil extractions, sugar, rice and wheat
that constituted 70% of the projected volumes at the time of bid. However, there were instances
of the anchorage port workers going on strike in protest of the deep water port handling agri
commodities such as wheat. The final negotiated Concession Agreement signed with the
Developer introduced a Clause which was not in line with the original tender conditions. Clause
2.19.1 (part) clause restricted the Developer to handle cargo handled by Anchorage Port, which
reads as follows:

87. “The concessionaire would also be permitted to handle any bulk cargo of the kind not
previously or presently handled by the Anchorage Port. Further, all cargo generated exclusively
by the Concessionaire through their own efforts may be handled by the Deep Water Port.”

88. The restrictive clause affected the viability of the project and KSPL was unable to meet the
obligations of Minimum Guaranteed Amount (MGA), which resulted in financial closure for

-34-
Phase-1 Development. After several rounds of discussions and negotiations, the government
agreed for rescheduling of payment of MGA ensuring that NPV of the amount to be paid during
the concession period remained the same in 2003 and accordingly the supplementary
concession agreement included these changes. However, even these changes did not make the
project viable and accordingly the second supplementary agreement deleted the clause related
to MGA. Annexure-3.2 provides further details of the Case Study of KDWP available as part of
PPP Toolkit on the web-site of Ministry of Finance, GoI.

3.5 PUBL IC CO NSULT AT ION S AN D HEARING IN T HE PROJ ECT

89. The project does not involve any land acquisition so there were no hearings related to the
land acquisition or resettlement impacts. However, as part of the EIA exercise for V, VI and VII
birth, public hearings were conducted in 2009-2010 where the community representatives had
flagged certain issues and expressed the expectations from the project for the area. The list of
issues and the response from the management along with the status of existing implementation
is enclosed as Annexure-3.1. The issues raised during the public hearing for EIA were
predominantly focused on the measures to improve the environment and employment
opportunities for the local people (discussed in next section). The other social issues raised
during the hearing was with regard to rehabilitation of fishermen who will lose their livelihood,
and it was clarified that the reclamation of land is towards the southern side of the existing port
which does not affect the fishermen livelihood in any way. The avenue street lighting for beach
road emerged as one of the key expectations in the hearing which has already been
implemented as reported.

90. Apart from the above referred Public Hearing minutes, there is no formal documentation
available regarding the specific demands from the community. The community needs for the
surrounding communities are identified more on the basis of word of mouth and then in
consultation with the local community representatives, the developer has executed various
activities under the CSR for social development.

3.6 EMPLOYMENT GENER AT ION AND SAFEGUARD S FOR


EMPLOYEES

91. As per the data provided by the Developer, about 400 members were employed through
construction contractor and his sub contractors during construction phase. During operation
stage, about 100 members are employed. The expansion of port activities with the creation of
additional births would result in further expansion of employment during construction and
operation phase. As per the EIA document prepared for Births 5, 6 and 7, the total direct

-35-
employment is estimated at 600, whereas during construction phase an employment of about
1000 workers and indirect employment is estimated at 1500. KSPL is adhering to the insurance
for employees as per the provisions of the Concession Agreement and the Port requirements for
the employees. In addition, other safeguards for employees with regard to health and safety of
the employees are also being adhered to which are already discussed in Section on
Environmental Due Diligence.

3.7 CSR IN IT AT IVES B Y KSPL

92. The year-wise detail of the amount spent by KSPL towards CSR activities is given below.

93. The activities undertaken by KSPL as part of the CSR initiatives ranges from small scale
donations to trusts/ societies working for social causes to large capital intensive contribution of
equipments and vehicles for hospital as per the requirements finalised by the district
administration. The list of activities taken up by KSPL during the past 4 years along with the
amount spent on each activity under CSR is enclosed as Annexure-3.3. The District Collector,
East Godavari District issued the guidelines for implementation of CSR activities in order to
coordinate the development activities in the district. The guidelines are enclosed as Annexure-
3.4. The guidelines were made effective from April 1, 2013 and subsequent implementation of
CSR activities has been made as per the provisions of these guidelines. The CSR provisions
have been notified by the Ministry of Corporate Affairs (“MCA”) on February 27, 2014 giving
effect to Section 135 the new Companies Act, 2013 (“Companies Act”) dealing with CSR read
with Schedule VII (“Schedule”) of the Companies Act covering the revised list of activities and
the Companies (Corporate Social Responsibility) Rules, 2014 (“CSR Rules”), enclosed as
Annexure-3.5 . The said Section, Schedule and CSR Rules will come into effect from the first
day of April, 2014.The CSR provision will be applicable to companies with an annual turnover of
INR 10 billion and more, or a net worth of INR 5 billion and more, or a net profit of INR 0.05
billion or more during any financial year. Companies that trigger any of the aforesaid conditions

-36-
must spend at least two per cent (2%) of their average net profits made during the three
immediately preceding financial years on CSR activities and/or report the reason for spending or
non-expenditure. The provisions related to the monitoring are well laid out in CSR Rules
regarding the implementation of the activities planned and compliance of the reporting
requirements. Based on the information provided by the Developer and visit to some of the CSR
initiatives implemented it can be concluded that the CSR activities are being implemented as per
the statutory requirements.

3.8 CONCL USIO NS

94. The Social due-diligence study for the KDWP project clearly shows that there is no land
acquisition involved in the project and hence no issues related to resettlement and rehabilitation.
The consultants also visited the project site along with the social and environmental experts of
IIFCL during November 2014. The objective of the visit was to get a first hand information and
understanding of the project and the safeguard and social/ community development measures
being undertaken by the developer. The site visit included interactions with the developer, review
the updated documents available with the developer regarding the project activities, understand
the project operations and also interact with the communities in the project area to understand
the social impact of the project.

-37-
• The initial parcel of three births (including submerged land) was part of the existing port
managed by GoAP admeasuring about 65 Acres handed over to KSPL in April 1999 and the
remaining entire land is only through reclamation. Based on the review of the Concession
Agreement, documents and the available information provided by Developer, information
available in public domain and the interaction with the community, the project does not
appear to have any legacy or residual issues related to the social safeguards.

• The project did not have any negative impact on the livelihood of the communities in the
surrounding areas and in fact it has generated employment opportunities for the local people,
both directly and indirectly as confirmed through the interactions with the community in the
surrounding area. The project has helped in generating employment opportunities during
construction and operation stages of project.

• The interactions with the users of Fishing Harbour facility for catching the fishes also
confirmed that there are no conflicts in the port operation and the shipping operation. The
Developer has never stopped movement of fishing ships crossing the navigation channel and
the safety measures are adopted by the KSPL at the time of movement of any ship in the
Channel. The operations at the fishing harbour are managed by the Department of Ports.
The fishing harbour activities were also observed and it was found that both the fishing and
port activities do not conflict each other and hence no impact on the livelihood.

• The fishing harbour community in the fishing harbour area as reported are squatting on the
fishing harbour land which does not fall under the direct purview of KSPL. In addition as per
the provisions of the second supplementary agreement, “the GoAP shall offer land if any
available and also in future as and when any lease agreements entered with GoAP by the
port users expire (both annual and long term), first right of refusal may be offered In KSPL, in
deep water port, except the areas earmarked for ship- building units, fishing harbour and
land being used for Government purpose.".It clearly establishes that the state government
has exempted the Fishing Harbour area from the purview of First right of refusal for KSPL. It
does not conflict the operations of KDWP and any issue of relocation or rehabilitation of this
community does not fall in the purview and action plan of the Developer.

• The community also confirmed the positive impact the project has for the area. The
developer has helped the community living in the fishing harbour area in addressing two
major day to day needs by extending support for improvement in the school building and
daily supply of drinking water through tankers for the community living in the fishing harbour
area huts.

• The Port, being a gated complex with restricted entry due to security and safety reasons,
does not affect the only community in the surrounding areas.
-38-
• The Developer has established systems for health and safety of the staff and workers. The
Developer has taken necessary insurance for the workers.

• The Corporate Social Responsibility activities are being undertaken as per the provisions of
the Company Act, CSR Rules and the guidelines issued by the District Administration with
regard to community development activities. The monitoring mechanisms are already in
place as per the provisions of the CSR Rules, 2014 as well as the guidelines issued by the
district administration and the implementation of CSR activities is being taken up by the
developer as per the directions of the district administration.

Based on the site visits observations and findings based on review of information available in
Public domain, it can be concluded that the project have no residual social safeguard issues
which could have reputational risks for the IIFCL or the World Bank. The Developer is required to
adhere to the statutory requirements of implementation of CSR activities as per the provisions of
the Companies Act and the CSR Rules, for which Developer shall be asked to submit a
certificate of statutory compliance on quarterly basis till the tenure of loan.

-39-
Annexure 2-1: EC for 4 th Berth & OSV

-40-
-41-
-42-
-43-
Annexure 2-2: EC for 5 th , 6 th , & 7 th Berth

-44-
-45-
-46-
-47-
-48-
-49-
Annexure 2-3: Water Cess Form 1

-50-
-51-
Annexure 2-4: Environmental Statement
Yearly submitted on Sept 2014

-52-
-53-
-54-
PURPOSE AND ADVANATGES OF ENVIRONMENTAL STATEMENT STUDIES

The Environmental statement studies serve the following three basic purposes:
i) Compilation of the complete information on the operation of the industrial facility and its potential sources of
pollution through technical inspection. This inspection, which is conducted at a facility, allows the activities that are
programmed and entrusted to the operational branches to be carried out in order to correct the different problems
detected at their source or to force conservation and maintenance measures need to prevent major pollution
problems.
ii) Evaluation of the conditions surrounding the industrial facility in order to estimate possible impacts, which may be
caused, and the suggested recovery measures for such situations.
iii) Preparation and implementation of action plans for better control of the environment, and the environmentally
related industrial activities, including further developmental activities of the areas.
The primary and obvious advantage of preparation of environmental statement is to help and safeguard the
environment and to substantiate compliance with local, regional and national laws and regulations, and with
the company policy and standards. There can be several other benefits, the importance of which may vary
from situation to situation. These benefits include
i)Reduced exposure to litigation and regulatory risk (e.g. prosecutions, penalties etc.) – facilitating comparison and
interchange of information between operations or plants.
ii)Increasing employer awareness of environmental policies and responsibilities.
iii)Identifying potential cost – savings including those resulting from waste minimization.
iv)Evaluating training programmes and providing data to assist in training personnel.
v)Providing an information base for use in emergencies and evaluating the effectiveness of emergency response
arrangements.
vi)Assuring an adequate, up-to-date environmental data base for internal management awareness and decision
making in relation to plant modification, new plants etc.
vii)Enabling management to give credit for good environmental performance.
viii)Helping to assist relations to authorities by convincing them that complete and effective statement are being
undertaken.
ix)Facilitating and obtaining of insurance coverage for environmental impairment liability.
Summary

INTRODUCTION:

The Kakinada Seaports Limited site is on the southern part of East coast of India, 10 Km from Kakinada Town in East
Godavari District. The port is commissioned and started operating from April 1999. The Plant is occupied an area of
145 acres.

Environmental Audit Report is a commitment by M/s. Kakinada Seaports Limited to minimize the impact of its
operations on the environment and is also committed to the principles of cleaner production and waste minimization.

Environmental Audit Report is being developed in conjunction with regulatory authorities, APPCB, and is in full
compliance with relevant Industry codes of practice.

M/s. Kakinada Seaports Limited assigned M/s. SV ENVIRO LABS & CONSULTANTS, Visakhapatnam to provide
consulting services to conduct “Environmental Statement” studies. SV ENVIRO LABS & CONSULTANTS has carried
out an analysis of the activities of port affecting environment.
The subject-matter of the study/analysis are:
• Process audit
• Energy audit
• Stack emissions
• Water and waste water audit
• Compliance audit
• Health and safety audit

-55-
3.8.1.1.1.1.1 METHODOLOGY
Audit programme was carried out at M/s. Kakinada Seaports Limited in 3 phases:
1. Pre-audit activities
2. On-site activities
3. Post-audit activities
3.8.1.1.1.1.2
3.8.1.1.1.1.3
3.8.1.1.1.1.4 SCOPE OF ENVIRONMENTAL AUDIT

The scope of Environmental Statement envisages-


 Facilitating Management Control of Environmental Practices on port’s performance, economical benefit and
environmental situation,
 Assessing compliance with M/s. Kakinada Seaports Limited’s policy and standards, which would include
meeting regulatory requirements.
 Develop and draw recommendations based on material, water and energy balance scenarios.
 Site assessment proceeding specific questionnaires, plant surveys, interviews with the plant staff and the
specific documentation provided by the company on request have been used as work tools to carry out an
environmental analysis.
 The Environmental Statement here reported has considered the activities concerning techno legal
standpoints.
The subject matter of the analysis and the environmental effects connected with:
• Process Audit
• Energy Audit
• Water and Wastewater Audit
• Environmental Quality Audit
• Health and Safety Audit
The work is organized according to chapters concerning the single environmental sections mentioned above, after a
general description of M/s. Kakinada Seaports Limited. Based on the above scenarios, conclusion and
recommendations are included.
3.8.1.1.1.1.5
Environmental Issues
The following environmental issues are addressed in the M/s. Kakinada Seaports Limited Environmental Statement
Report:
• Air Emissions – Vents
• Air – “Fugitive Emissions”
• Water & Waste water – Domestic
• Solid waste
• Noise
METEOROLOGICAL INFORMATION:

The wind speed at Kakinada ranges between 5 to 15 km/hr indicating good dispersion. Wind dispersion
characteristics are with 5.5% and 2.2% calm period. The predominant wind direction is from Northwest and South
direction.
The maximum temperature recorded is 480C, and minimum temperature recorded was 200C. Humidity ranges from 61
to 90 %. The area is prone to cyclones during rainy season, being situated near to the eastern Sea coast of Bay of
Bengal.

SITE PARTICULARS

Climate conditions Annual Max Temp. 460C


Annual Min Temp. 220C
Annual Rainfall 1050 - 1100 mm
Land acquired for the Plant Total Land 205.93Acres
Present Reclaimed land – 122.00 acres
-56-
Green belt area – 12.25 Acres + 6acres by Sep2014
Land use and major crops Dry land scattered with shrubs.
Predominant wind direction NW
Nearest town Kakinada
Major Settlement Kakinada
Nearest Water Bodies Nil
Hills and Mountains Nil
Ecological sensitive zones No reserved forests
No wild life sanctuaries
Historical Places Nil
Wind speed Avg., 6.16 Kmph

IMPLEMENTATION OF AUDIT
The audit was performed at port site during September 2014, according to SV ENVIRO LABS & CONSULTANTS
programme. Mr. KHASIM, Manager HSE of M/s. Kakinada Seaports Limited, representing port’s process development
and environmental issues, functioned as contact persons for the auditors and gave valuable contributions to the audit
results.

The implementation of on-site audit was conducted as follows:


1. Presentation of the port by the Managers of M/s. Kakinada Seaports Limited:
i) Organization
ii) Functions of each and every unit operations
iii) Layout descriptions and flow sheets, etc.,

2. Analysis of the environmental issues:


Presence of authorization to water discharge, temporary dumping of waste and emissions in atmosphere, noise
emissions along with the accomplishments connected with the safety and health aspects and prevention of accidents,

- Description of emissions & Air quality


- Presence of hazardous wastes;
- Presence of bore wells, storage facilities;
- Evaluation of noise levels;
- Evaluation of work atmosphere for health aspects;
- Prevention, internal environment, safety;

3. Documentation concerning the audit purpose


- Plant survey.

TOPO MAP OF 10 KM RADIUS

-57-
3.8.1.1.1.1.6 PROCESS AUDIT

M/s. Kakinada Seaports is engaged in handling /facilitating export and import of sea cargoes and contributes to the
exchequer. The cargo presently being handled consists of:
Import : Liquid Ammonia, Phosphoric acid, Sulphuric acid, POL, Edible Oils,
General/Project Cargoes, Wood Pulp
Export : Iron Ore & General Cargo

On the jetty, GSPC, Transocean, ONGC & Reliance have dedicated installations / storage areas where they keep
their off-shore drilling platform materials like tools, tackles, drilling bits, rigs, store items such as pipes, valves, fittings,
hoses etc and civil construction material prior to transportation to off shore platforms on the sea.

-58-
PORT FACILITIES:
Kakinada Deepwater Port (KDWP) currently has four multi purpose berths in operation. The berths are oriented
approximately in N-S direction. The present water depth in front of berth after completion of maintenance dredging is -
12.0 m chart datum. This can accommodate vessel of about 50000 DWT.

At present the port has 2 no. mobile cranes and 12 no. forklift trucks to handle small capacity break bulk cargoes. POL
and liquid cargoes are handled at the north berth and edible oil is handled at the South berth. Various Port users have
installed their pipelines from KDWP berths to their shore facilities as below.
Organization Product Size
HPCL Naphtha 400/16’’
BPCL HSD 500/20’’
BPCL Furnace Oil 500/20’’
BPCL Naphtha 600/24’’
IMC POL 450/18’’
Gowthami POL 350/14’’
GFCL Ammonia (Main Line) 400/16’’
GFCL Ammonia (Pre cool line) 100/4’’
GFCL Phos / Sulfuric Acid 400/16’’
GFCL Phos / Sulfuric Acid Extension from 400/16’’
NB to MB
IMC Veg. Oil 350/14’’
SSS Veg. Oil 350/14’’
NCS Veg. Oil 350/14’’
RUCHI Veg. Oil 250/10’’
CARGO HANDLING:
The licensed cargos as per APPCB consent order:-
1. Cargo handling - 45,75,000 TPA North(1)
2. Iron and coal cargo handling – 9,60,000 TPA Middle(2)
3. Handling of Alumina - 8,00,000 TPA &South(3)
4. Handling of Bauxite – 10,00,000 TPA Berths
Fourth berth - multipurpose berth to handle Iron ore – 20, 00,000 TPA
& coal - 15, 00,000 TPA IV Berth
OSV facility: To serve offshore exploration activities in KG basin.
……………………………
TOTAL:  10835000 TPA i.e 10.835 Million Tons

 Consent For Operation License Valid Upto 31st Aug 2016 for
1,2,3 Berths, OSV Berths & 04th Berth & NRW Extension Berth

5 & 6 Berths – existing licence Valid till 30th Sep 2014 and renewal under process for:
1. Coal Cargo Handling  1.25 TPA
2. Fertilizer Handling  2.5 TPA
3. Iron Ore Handling  1.667 TPA
……………………………

TOTAL:  5.417 Million Tons


GRAND TOTAL LICENSED CARGO QUANTITIES: 16.252 MTPA

-59-
PRODUCTION DETAILS FROM APRIL’ 2013 – MARCH’ 2014

3.8.1.1.1.1.7 Month 3.8.1.1.1.1.8 Cargo Handling


3.8.1.1.1.1.9 Coal & 3.8.1.1.1.1.10 Granite 3.8.1.1.1.1.11 Other Cargo
Iron Ore Blocks Handling
3.8.1.1.1.1.12 April’ 3.8.1.1.1.1.13 437783 3.8.1.1.1.1.14 275116 3.8.1.1.1.1.15 280101
2013
May’13 3.8.1.1.1.1.16 458987 3.8.1.1.1.1.17 214997 3.8.1.1.1.1.18 532341
June’13 3.8.1.1.1.1.19 569293 3.8.1.1.1.1.20 240905 3.8.1.1.1.1.21 595007
July’13 3.8.1.1.1.1.22 454792 3.8.1.1.1.1.23 274229 3.8.1.1.1.1.24 574358
August’13 3.8.1.1.1.1.25 336393 3.8.1.1.1.1.26 140175 3.8.1.1.1.1.27 616709
September’13 3.8.1.1.1.1.28 260759 3.8.1.1.1.1.29 196324 3.8.1.1.1.1.30 536760
October’13 3.8.1.1.1.1.31 300057 3.8.1.1.1.1.32 74689 3.8.1.1.1.1.33 631263
November’13 3.8.1.1.1.1.34 280619 3.8.1.1.1.1.35 215343 3.8.1.1.1.1.36 570603
December’13 3.8.1.1.1.1.37 532076 3.8.1.1.1.1.38 227555 3.8.1.1.1.1.39 448918
January’14 3.8.1.1.1.1.40 380548 3.8.1.1.1.1.41 216236 3.8.1.1.1.1.42 566097
February’14 3.8.1.1.1.1.43 247413 3.8.1.1.1.1.44 138755 3.8.1.1.1.1.45 487200
March’14 3.8.1.1.1.1.46 353512 3.8.1.1.1.1.47 257911 3.8.1.1.1.1.48 481166

Details of pipe line Connections from KDWP Jetty to Storage Terminals

Berth Organization 3.8.1.1.2 Product Size Length (in KM)


mm / inch To Exchange pit To Terminal
NB HPCL Naphtha 400/16” 0.95 4.3
NB BPCL HSD 500/20” 1.2 4.5
NB BPCL FO 600/24” 1.2 4.5
NB BPCL Naphtha 500/20” 1.2 4.5
NB IMC POL 450/18” 1.2 4.1
NB Gowthami POL 350/14” 1.2 5.5
-60-
SB IMC Veg.Oil 350/14” 0.9 3.9
MB IMC Veg.Oil Extension 350/14” XXXX 0.2
from SB to MB
SB SSS Veg. Oil 350/14” 0.9 3.7
MB SSS Veg.Oil Extension 200/8” XXXX 0.2
from SB to MB
SB NCS Veg. Oil 350/14” 0.9 2.6
SB RUCHI Veg. Oil 250/10” 0.9 2.5
NB GFCL Ammonia 400/16” XXXX 2.7
(Main Line)
NB GFCL Ammonia 100/4” XXXX 2.7
(Pre cool Line)
NB GFCL Phos/Sulphuric Acid 400/16” XXXX 2.7
MB GFCL Phos/Sulphuric Acid 400/16” 0.19
Extension from NB
to MB
NB: North Berth / MB: Middle Berth / SB: South Berth

3.8.1.1.2.1.1 COMPLIANCE ADUIT


This investigates the status of the Environmental Management systems and equipment. The complex embodies a
number of measures to control oil spillage and the 125 KVA & 250 KVA & 500KVA x3 generator’s stack emissions,
etc.
Show cause notice received on 15th May, 2014 and respective compliance is submitted on 23rd May’ 2014.

OIL SPILLAGE AVOIDANCE AND CONTROL PLAN


M/s. Kakinada Seaports Limited handles products & Edible oils. Following precautions are taken towards prevention &
management of Oil spillage if any during the discharge of oils
The cargo receivers / pipe line- terminal operators are advised to use wire reinforced rubber hoses for discharge of
oils. This ensures that the hoses are adequately protected normal wear and tear & abrasion during handling.

The flange joints are inspected for leaks. Drip trays, sawdust, cotton rags are kept standby for attending to any
accidental leaks.
Discharge pressure and flow rates are continuously monitored by the vessel and the receivers to ensure that the lines
are never pressurized.
Continuous walkie-talkie communication is maintained by the pipeline-terminal operators to check and control oil
spillage if any during discharge. Communication is also maintained between the receiving terminal and the vessel to
effect emergency stop of cargo pumping in the event of a leak.
The vessels are advised to comply with all international regulations and effect the mandatory precautions on cargo
discharge.
KSPL maintains about 400 Ltrs of OSD (Oil Spill Dispersant) and dedicated dispersing spray system on board one of
its tug for quick combat of oil if any on the water surface.

WATER AND WASTE WATER ADUIT:


The total water requirement is 590 KLD + 155KLD

-61-
Water balance scenario is developed taking into consideration of the total water drawn from raw water source which is
a third party and its usage in different units, as per the water cess details submitted monthly to APPCB.

ENERGY ADUIT:
Adoption of cleaner and more efficient technological process geared towards greater energy efficiency and production
efficiency help in preventing the loss of energy.

3.8.1.1.2.1.2 ENERGY SUPPLY


A total of 1000 KVA of power is received from AP TRANSCO, and a suitable substation also installed for this purpose.
In addition a power diesel generators of 125 KVA & 250 KVA & 3x500 KVA capacities and the DO’s and DON’T’s are
exhibited. Operational procedures are to be exhibited at terminal powerhouse.
An Electrical / Energy audit is to be taken up by M/s. Kakinada Seaports Limited as a separate module for better
clarity. However the Diesel Consumption with respect to the Electrical aspects during the year was 108595lts.

APEPDCL POWER UTILIZATION OF 2013-2014


Month Jetty Supply (RJY -352) Contracted Demand OSV Supply (RJY -727) – Contracted
(600 KVA) demand (1000 KVA)
Running Demand Units Utilized (KWH) Running Demand Units Utilized
(KVA) (KVA) (KWH)
April ‘13 254.11 64069 448.50 95955
May’13 225.05 65490 540.00 107055
June’13 256.52 72034 568.50 105735
July’13 243.83 72431 628.50 118230
August’13 264.39 93664 559.50 157080
September’13 281.34 100181 598.50 159615
October’13 324.67 104910 531.00 125445
November’13 225.00 91823 628.50 159615
December’13 286.72 89700 628.50 202805
January’14 272.71 90968 513.00 138385
February’14 223.60 90210 474.90 139680
March’14 255.62 89603 443.36 139485

-62-
-63-
GENERATOR UTILIZATION DETAILS OF 2013-2014
Month 500 KVA Generator at Jetty Substation 250 KVA Generator at Shore Substation 500 KVA Generator at OSV
No. of Units Fuel No. of Units Fuel No. of Units Fuel
Running Generated Consumption Running Generated Consumption Running Generated Consumption
Hrs Hrs Hrs
April ‘13 243 19120 8379 224 12352 5795 97.1 11472 4240
May’13 219 18544 7827 230 13053 6481 145.3 18336 6597
June’13 147 11264 5103 146 7481 3992 119.8 16592 5879
July’13 144 13520 5427 139 6690 3548 82.8 10464 3548
August’13 21 1472 785 26 1021 616 19.2 2304 940
September’13 71 5600 2460 65 2729 1568 80.1 10544 3845
October’13 93 6944 3137 98 4181 2277 153.7 19968 7106
November’13 63 3728 1864 51 1855 1066 48.4 4624 1994
December’13 56 5408 2107 16 541 309 32.5 4416 1643
January’14 8 368 264 17 490 324 2.5 336 142
February’14 59 1792 1418 74 2228 1302 61.5 8608 3130
March’14 31 1120 794 42 1710 933 39.9 5120 1885

-64-
BATTERIES DISPOSED DURING 2013-14
Date Capacity of Qty Generated & Location
Battery disposed to recycler
22.07.2013 180 AH 2 Star board Main Engine - Pilot Launch Bhima
22.07.2013 180 AH 2 Port Auxiliary Engine - Tug Jala Kanya.
22.07.2013 180 AH 2 Star board Auxiliary Engine - Tug Jala Kanya.
30.10.2013 180 AH 4 Emergency communication equipment &
lighting - Pilot Launch Bhima.
30.10.2013 180 AH 2 For Emergency communication equipment &
lighting - Tug Jala Tarangini.
19.03.2014 180 AH 2 500 KVA DG-1 - OSV
28.03.2014 180 AH 2 Port Generator - Tug Jala Hamsa.

MECHANICAL EQUIPMENT RUNNING HOURS IN 2013-14


Mobile
Silos Mobile Compressors Maxsweepers Crane & Forklift
S.No Month Rhrs Consumption Rhrs Consumption Rhrs Consumption Rhrs Consumption
1 April'13 223.2 114 148.9 1978 384.85 1048 63 182
2 May'13 154.4 78 108.3 1449 444.61 1145 52 163
3 June'13 274.5 139 183.9 2443 360.07 1052 91 281
4 July'13 416.9 209 192.9 2570 320.87 973 116 405
5 August'13 359.1 181 190.8 2547 423.1 1318 146 463
6 September'13 285.7 142 206.7 2766 403.38 1146 100 340
7 October'13 244.1 124 159.9 2154 112.05 396 95 324
8 November'13 254.9 119 126.2 1688 304.93 984 179 859
9 December'13 440.9 221 191.8 2591 533.74 1641 125 486
10 January'14 338.9 169 186.1 2450 528.49 1661 95 245
11 February'14 456.3 228 207.6 2755 981.51 1341 135 466
12 March'14 517.8 259 247.6 3357 859.43 1893 155 555
TOTAL 3966.7 1983 2150.7 28748 5657.03 14598 1352 4769
COMPLIANCE AUDIT

INTRODUCTION
“Compliance Audit” aims at investigating the status of the Environmental Management Systems and equipments vis-à-vis the
regulatory requirements. Proper operation and maintenance practices helps in reducing emissions from the M/s. Kakinada
Seaports Limited to arrest Environmental Quality deterioration.

AIR QUALITY AND COMPLIANCE


3.8.1.1.2.1.3
3.8.1.1.2.1.4 STACK EMISSIONS
M/s. Kakinada Seaports Limited has generators of 125 KVA, 250 KVA, 500 KVA and two Fire Engines. Flue gas analysis was
carried out for generators and fire engines.

3.8.1.1.2.1.5 AIR QUALITY MONITORING


Ambient Air quality is monitoring at M/s. Kakinada Seaports Limited in four locations within the port area i.e., first location is at
top of Customs Office Building, the second location is at top of the Control Office Building, the third location is at Top of Fire
pump house and the fourth location is at Near Cairn Office for determining the parameters viz., Sulphur Dioxide (SO2),
Nitrogen Oxides (NOX), Particulate Matter10 (size less than 10 um), Particulate Matter2.5 (size less than 2.5 um). In addition to
the above, micrometeorological data like wind speed, wind direction, ambient temperature, barometric pressure are measured
at one location. The table shows the Ambient Air Quality Monitoring (AAQM) levels for SO2, NOX, PM10, PM2.5 at 4 locations
within the M/s. Kakinada Seaports Limited.

-- 65 --
3.8.1.1.2.1.6
3.8.1.1.2.1.7
3.8.1.1.2.1.8
3.8.1.1.2.1.9
3.8.1.1.2.1.10
3.8.1.1.2.1.11
3.8.1.1.2.1.12 NOISE LEVELS

The Noise level measurements were made within the port premises of M/s. Kakinada Seaports Limited to determine the
compliance with respect to ambient noise standards and results are depicted in Table. On Perusal of the results depicts the
fact that the plants have been designed and built so that noise levels are well below the OSHA standards of 90 dB(A) Past
record review indicated that the noise levels recorded at various locations within M/s. Kakinada Seaports Limited range from
50 to 75 dB(A).

BACKGROUND NOISE LEVELS AT


M/S. KAKINADA SEAPORTS LIMITED
RESULT
Sl.No. Location

Day dB(A) Night dB(A)

1. OSV – Berth I 70.0 66.5


2. OSV – Berth II 69.2 63.9
3. Near Sub Station 72.3 66.6
4. Outside of DG Set Room 71.9 69.0
5. OSV Gate 69.9 63.2
STANDARD 75.0 70.0

WATER AND WASTEWATER ADUIT


INTRODUTION
Water and wastewater audit conducted at M/s. Kakinada Seaports Limited aimed at evaluation of raw water intake facilities,
performance evaluation of existing facilities for Domestic & Drinking purposes.

Development of Water Balance Scenario


The total water requirement is 590 KLD + 155KLD
Water balance scenario is developed taking into consideration of the total water drawn from raw water source and its usage in
different units of the M/s. Kakinada Seaports Limited.
M/s. Kakinada Seaports Limited does not have any product-related industry. The main function is to receive or export products
such as Liquid Ammonia, Phosphoric Acid, Sulphuric Acid, edible oils and Generals.
In M/s. Kakinada Seaports Limited potable water is stored in tanks.

WATER & WASTE WATER MONITORING


Water and wastewater monitoring, samples will be collected regularly by the M/s. Kakinada Seaports Limited for the following:
1. Raw water quality
-- 66 --
2. Liquid effluent - Domestic
Characteristics of water, wastewater and soil samples are analyzed and results are formulated in tables, results reveals that all
the concentrations are within the stipulations of CPCB and APPCB Specifications.

SAMPLE PARTICULARS : SOIL ANALYSIS


SOURCE OF COLLECTION :
Soil 1. Opp. to Canteen
DATE OF SAMPLING COLLECTION : Sep 2014

Analysis Soil Samples


S.No. Parameter Unit Concentration
1. pH -- 7.26
2. Conductivity µ mhos 40
3. Sodium as Na Meq/100gm 0.28
4. Potassium as K Meq/100gm 0.21
5. Calcium as Ca Meq/100gm 1.10
6. Magnesium as Mg Meq/100gm 1.23
7. Total Kjedahl Nitrogen as N % BDL
8. Phosphates as P mg/kg 0.072
9. Sulphates as SO4-- mg/kg 0.002
10. Nitrate as N % BDL
Available Metals
11. Zinc as Zn mg/kg 0.003
12. Copper as Cu mg/kg 1.31
13. Iron as Fe mg/kg 10.44
14. Manganese as Mn mg/kg 8.22
Note: BDL denotes below detectable level

SAMPLE PARTICULARS : SOIL ANALYSIS


SOURCE OF COLLECTION :
Soil 2. Near Technical Office
DATE OF SAMPLING COLLECTION : Sep 2014

Analysis Soil Samples

S.No. Parameter Unit Concentration


1. pH -- 7.30
2. Conductivity µ mhos 43
3. Sodium as Na Meq/100gm 0.34
4. Potassium as K Meq/100gm 0.30
5. Calcium as Ca Meq/100gm 1.13
6. Magnesium as Mg Meq/100gm 0.72
7. Total Kjedahl Nitrogen as N % BDL
8. Phosphates as P mg/kg 0.072
9. Sulphates as SO4-- mg/kg 0.003
10. Nitrate as N % BDL
Available Metals
11. Zinc as Zn mg/kg 0.005
12. Copper as Cu mg/kg 1.13
-- 67 --
13. Iron as Fe mg/kg 11.14
14. Manganese as Mn mg/kg 9.02
Note: BDL denotes below detectable level

HEALTH AND SAFETY AUDIT


Kakinada Seaports Ltd has been undertaking inspection and evaluation of health and safety parameters as would be generally
be relevant and appropriate for Port operations.
Essentially it covers the following:
1. Systems to identify hazards.
2. Corrective actions with respect to prevention, control & containment.
3. Compliance with standard safety norms and practices.
With regards to Health and Safety, We carried out an audit of the systems, procedures and activities and the details are as
under:

HEALTH AND SAFETY AUDIT DETAILS:


• Covering of pits, openings in the floors & open yards have been found satisfactory,
• The general safety was found good. Safety equipment have been positioned at various level in the utility areas,
• The electrical equipment, cables have been designed properly with enough safety margin and there is no possibility of
overloading or overheating,
• The statutory requirements of earth resistance monitoring & other electrical checks are being done scrupulously and
records maintained properly,
• Properly tested gloves are made available for working personal,
• Fire fighting pumps, power supply are independent of shore electric supply & have back up genset power,
• Accident report form for reporting electrical accidents is available and to be reported within 24 hours,(till date accidents
are Nil)
• On perusal of M/s. Kakinada Seaports Limited documents, it was observed that the statutory and legal aspects are being
fulfilled.
Reporting and Review
The Management of M/s. Kakinada Seaports Limited routinely report to the A.P. Pollution Control Board on the progress of
improvement of Environmental aspects.
The follow-up action to the Environmental Statement will be reviewed annually by M/s. Kakinada Seaports Limited, to assess
progress and provide input to future improvement goals actions.

ACCIDENT REPORTING
Any accident small or high will be simultaneously reported to following in that order;
• KSPL Jetty Office : Tel 2354170, 2368246, 2349619
• Security Gate :9866556710
• Fire –Pump house : 9000552515
• Ambulance : 7702544401
• GM Operations (Designated Officer) : 9866556688

Whosoever among the above receives first information of accident, will inform others over phone. They will immediately rush
to the spot, as quickly as possible. The person noticing the accident will identify:

i. Spot of the accident


ii. Cause of accident
iii. Seriousness of accident.
According to Hazardous Chemicals (management & handling) rules of 1989 promulgated by Govt. India, it is mandatory for
KSP management to:
• Identity major accidents / hazards and outline steps to be taken to avoid such accidents.
• Notify State Pollution Control Board authorities & Inspectorate of Factories, in the event of any accident.
• Submit a safety report to State Pollution Control Board.
-- 68 --
Protocol for accident reporting will be adopted to ensure compliance with above said rules. Each and every accident, however
small it may will be reported and investigated. Accident report will contain a detailed description of the incident and identify
immediate cause. Accident report will also incorporate information on steps taken to prevent such accidents in future, impact
on accident, if any on the environment and cost estimate of loss.

In order to evaluate overall safety performance and to draw action plans to improve safety.

OCCUPATIONAL HEALTH/INDUSTRIAL HYGIENE

Spillage of Oil content at Work Place


Spillages of Oil content at work Place are virtually nil, as M/s. Kakinada Seaports Limited is well maintained and leaks are
minimum.

Personal Protective Equipments


During our on –site studies it was observed that all types of personal protective equipments, fire proximity suits, all type of
hand gloves safety helmets/safety shoes etc are maintained.

FIRE PREVENTION AND PROTECTION SYSTEM


LIST OF FIRE FIGHTING FACILITIES AT KAKINADA SEAPORTS PVT.
LIMITED

Fire Pumps:
Description Qty Make Make of Drive Drive Disch. Disch. Rate Total
HP Pressure Head
4 stage vertical 2+1 WPIL 2 nos Engine 230
turbine (Cummins) 8.8 Kg/cm2 410 m3/Hr 96 m

1 no. Motor 220

Jockey Pump 1 no WPIL Motor driven 30 8.8 Kg/cm2 30 m3/Hr 88 m


Cooling Pump 1 no Kirloskar Motor driven 7.5 30 m3/Hr 35 m

Hydrants, Monitors & Water Curtains


Description Qty Size Type Rate Range Rotation Operation
Single head 12 63 mm 900 LPM Manual
Hydrants
Double head 5 63 mm Female Oblique 1800 LPM Manual
Hydrants
Ground Monitors 4 Stand post 2580 LPM 60 meters at 7 H - 3600 Manual
75 NB fixed kg/cm2 V-+85–650
installation
38 nozzle
Tower Monitors 2 200 NB Monitor Trigger 3000 LPM 51 meters at 7 H - 3600 Remote/
135nozzl Teo kg/cm2 V-+85–650 Electrical
e
Water Curtains 2 100 ND Jumbo 3000 LPM 33mHorizontal Electrical
11 m vertical

Branch pipes (Nozzles):


Description Qty Type of Nozzle Nozzle Bore Nominal Bore
Instaneous male end 13 Jet Type 20 mm 63 mm
Universal (Dual Type) 4 Jet & Spray type 108 mm 63 mm
branch pipe

Reinforced Rubber Lined hoses Size: Dia 63mm X 15 M long : 34 Nos.


Fibre Reinforced Plastic Hose Boxes : 17 Nos.

Portable Fire & Safety Equipment:

-- 69 --
1. Dry Chemical Power Extinguishers 75 Kg : 4 Nos.
2. Dry Chemical Power Extinguishers 10 Kg : 4 Nos.
3. Carbon dioxide type Extinguishers 4.5 Kg : 21 Nos.
4. Mechanical Foam type Extinguishers 9 Lts : 21 Nos.
5. AFFF (Aqueous Film Forming Foam) Foam tanks : 2 Nos. Each 3000 Liters
6. Fire Entry suits : 2 Nos.
7. Fire Proximity suits : 10 Nos.
8. Breathing Apparatus : 4 sets

Siren: Horizontal Double mounting type Range 5 Kilometers.

-- 70 --
PETTY INCIDENT/NEAR MISS/ACCIDENT REPORT FOR THE YEAR OF 2013 - 2014
S. No: Description MONTH & YEAR

Apr - Jun Jul - Sep Oct - Dec Jan - Mar


2013 2013 2013 2014 TOTAL
1 Petty incidents 9 6 8 4 27
2 Near Miss 4 3 7 5 19
3 Accidents:
a) Minor 6 8 4 9 27
b) Major

TOTAL 19 17 19 18 73

PETTY INCIDENT/NEAR MISS/ACCIDENT REPORT FOR THE YEAR OF 2014


S. No: Description MONTH & YEAR
Apr - Jun Jul - Sep
2014 2014 TOTAL
1 Petty incidents 3 2 5
2 Near Miss 1 2 3
3 Accidents:
a) Minor 4 3 7
b) Major
TOTAL 8 7 15

-- 71 --
Fire Watch & Ward 2013-2014

Apr-Jun Jul-Sep Oct-Dec Jan-Mar Total


No. of diesel bunkerings 99 129 126 144 498
Hot works 66 81 89 86 322
Hazardous cargo Vessels 24 50 50 30 154

Fire Watch & Ward 2014-2015

Apr-Jun Jul-Sep Oct-Dec Jan-Mar Total


No. of diesel bunkerings 107 114 221
Hot works 81 105 186
Hazardous cargo Vessels 35 31 66

TOOL BOX TALK 2013 - 2014


S. No: NAME MONTH & YEAR
DESCRIPTION OF THE TRAINING/TOOL BOX April - June July - Sep Oct - Dec Jan- Mar
CONDUCTED 2013 2013 2014 2014 TOTAL
No's Participants No's Participants No's Participants No's Participants No's Participants
1 Granite hooking labour 126 1015 110 1042 90 598 64 593 390 3248
2 Coal handling labour 15 147 9 77 12 140 46 232 314 596
3 Bentonite handling labour 10 108 1 9 6 49 17 164 34 330
4 CP Coke handling labour. 1 15 6 51 3 30 0 0 10 96
5 Wood pulp handling labour. 3 30 4 33 2 16 0 0 9 79
6 Wheat handling labour. 1 7 0 0 3 31 9 94 13 132
7 Ballclay handling labour. 1 7 0 0 2 16 0 0 3 23
8 Fertilizer handling labour. 3 26 4 27 13 128 9 75 29 256
9 Feldspar labour 1 12 5 58 1 9 0 0 7 79
10 Lime stone handling labour 0 0 1 6 0 0 0 0 1 6
11 Wood handling labour 0 0 4 38 1 7 6 49 11 94
12 cement clinker handling labour 0 0 0 0 7 65 9 74 16 139
13 Soda ash labour 0 0 0 0 0 0 2 23 2 23
14 Tool box conducted at other yards 0 0 0 0 0 0 6 49 6 49
TOTAL 161 1367 144 1341 140 1089 168 1353 845 5150

-- 72 --
TOOL BOX TALK 2014 - 2015
S. No: NAME MONTH & YEAR
DESCRIPTION OF THE
TRAINING/TOOL BOX April - June July - Sep
CONDUCTED 2014 2014 TOTAL
No's Participants No's Participants No's Participants
1 Granite hooking labour 36 259 95 1427 131 1686
2 Coal handling labour 34 189 27 313 61 502
3 Bentonite handling labour 15 114 4 32 19 146
4 CP Coke handling labour. 3 32 0 0 3 32
5 Wood pulp handling labour. 0 0 1 12 1 12
6 Wheat handling labour. 0 0 0 0 0 0
7 Ballclay handling labour. 0 0 1 20 1 20
8 Fertilizer handling labour. 10 82 16 167 26 249
9 Feldspar labour 0 0 8 114 8 114
10 Lime stone handling labour 0 0 3 32 3 32
11 Wood handling labour 4 36 2 17 6 53
12 Cement clinker handling labour 7 64 8 101 15 165
13 Soda ash labour 0 0 4 50 4 50
14 Tool box conducted at other yards 6 55 0 0 6 55
TOTAL 115 831 169 2285 284 3116

Mock Drills 2013-14


1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Mock Drill April to June July to October to January to
S.N
Descriptio September December March
o
n No.’ Participan No.’ Participan No.’ Participan No.’ Participan No.’ Participan
s ts s ts s ts s ts s ts
1 Hose Drill 01 15 01 10 01 09 02 34 05 68
Portable
Fire
2 04 57 --- --- 04 69 05 182 13 308
Extinguish
ers
3 SCBA --- --- 01 07 --- --- 01 29 02 36
Hydrants,
Monitors &
4 --- --- 01 11 02 30 03 126 06 167
water
curtains
Ammonia
5 Leak --- --- --- --- --- --- 01 11 01 11
Rescue
fire drill
6 with fire --- --- --- --- --- --- 01 28 01 28
Tender
Total 05 72 03 28 07 108 13 410 28 618

-- 73 --
Mock Drills 1st & 2nd Quarter 2014
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
April to June July to September October to January to March
S.N Mock Drill
December
o Description
No.’ Participant No.’ Participant No.’ Participant No.’ Participant No.’ Participant
s s s s s s s s s s
1 Hose Drill 05 71 01 43 --- --- --- --- 06 114
Portable
Fire
2 07 89 07 162 --- --- --- --- 14 251
Extinguisher
s
3 SCBA --- --- 01 13 --- --- --- --- 01 13
Hydrants,
Monitors &
4 02 24 02 43 --- --- --- --- 04 67
Water
curtains
Ammonia
5 Leak --- --- 01 31 --- --- --- --- 01 31
Rescue
fire drill with
6 fire Tender 05 81 04 69 --- --- --- --- 09 150

Oil spill
7 Boom laying --- --- 01 13 --- --- --- --- 01 13

Smoke
8 --- --- 02 28 --- --- --- --- 02 28
Detection
19 265 19 402 --- --- --- --- 38 667

Fires Attended for the period of 2013 - 2014


Inside Port Outside Port Total
Fires Attended
Minor Major Minor Major Minor Major
1st Quarter Apr to Jun 01 03 -- 01 01 04
2nd Quarter Jul to Sep 04 -- -- -- 04 --
3rd Quarter Oct to Dec -- 02 -- 01 -- 03
4th Quarter Jan to Mar 02 01 01 02 03 03
Total 07 06 01 04 08 10

Fires Attended for the period of 2014 - 2015


Inside Port Outside Port Total
Fires Attended
Minor Major Minor Major Minor Major
1st Quarter Apr to Jun 07 -- -- -- 07 --
2nd Quarter Jul to Sep 04 01 01 04 05 05
3 Quarter
rd Oct to Dec -- -- -- -- -- --
4th Quarter Jan to Mar -- -- -- -- -- --
Total 11 01 01 04 12 05

-- 74 --
-- 75 --
GREEN BELT
Green belt developed till 2012-2013 was about 12acres and for 2013-14 another 0.25acres added to the Green Belt and by Sep
2014 about 06 acres more Green Belt Developed.
Plants of native origin, first growing type with thick canopy and large leaf index shall be preferred. The philosophy behind the green
belt developed at M/s. Kakinada Seaports Limited is to improve the ecology and environment of the surrounding of the plant by
extensive afforestation. Appropriate planning techniques have been adopted in selected areas. Greenbelt is a set of rows of trees
planted in such a fashion, to create effective barrier between the port and surroundings. The greenbelt helps to capture the fugitive
emissions, attenuate the noise levels in the port and simultaneously improving aesthetics of the port site.

The greenbelt around the factory compound wall in the reserve site will be developed in keeping view of the following objectives:
1. Planting of trees in each row are in staggered pattern.
2. The short trees are planted in the first two rows and the tall trees in the outer rows around the purview of the project site.
3. Since the trucks of the tall trees are generally devoid of foliage, it will be useful to have shrubs in front of the trees so as
to give coverage to this portion.
4. Sufficient spacing is maintained between the trees to facilitate effective height of the greenbelt.

The photographs of already completed Green Belt, Ongoing & Proposed areas are depicted in the subsequent pages.

-- 76 --
MINISTRY OF ENVIRONMENT AND FORESTS

NOTIFICATION
New Delhi, the 22nd April, 1993

G.S.R. 386(E) – In exercise of the powers conferred by sections 6 and 25 of the Environment (Protection) Act, 1986
(29 of 1986), the Central Government herby makes the following rules further to amend the Environment (Protection) rules,
1986, namely:-
1. (a). These rules may be called the environment (Protection) Amendment rules, 1993.
(b). They shall come into force on the date of the their publication the Official Gazette.
2. In the Environment (Protection) rules, 1986:-
(a). in rule 14 –
i). For the words “audit report” wherever they occur, the word, “Statement” shall be substituted.
ii). For the figures letters and words “15th day of May” the words “30th day of September,” shall be substituted.
(b). In Appendix ‘A’ for FORM V. the following from shall be substituted, namely :-

“FORM V”
(See rule 14)
Environmental Statement for the financial year ending the 31st March 2014

PART A
i. Name and Address of the Owner Occupier of the industry operation of process –
M/s. Kakinada Seaports Limited,
Beach Road, Kakinada – 533 305.
E.G.Dt., A.P.
ii. Industry category Primary (SIC Code) Secondary – (SIC Code)
iii. Production capacity – Enclosed as annexure
iv. Year of establishment - 1996
v. Date of the last environmental statement submitted- September 2013

PART - B
Water and Raw Material Consumption

(i). Water Consumption: Explained under water Requirement


Process - ---
Cooling - ---
Dust suppression - 500 KLD +100KLD
Gardening/irrigation - 70 KLD
Domestic: - 20 KLD+55KLD

Name of Product Process water Consumption per unit of


Product Output

During the previous During the Current


financial year financial year

(1) (2)
(1) Cargo Handling 45, 75,000 TPA As per pg no.9 above
(2) Iron & Coal Cargo Handling 4460000 TPA
(3) Alumina handling 800000 TPA
(4) Bauxite handling 1000000 TPA
There is no process water consumption

Raw Material Consumption: Explained under Raw material consumption


*Name of Raw Name of Consumption of Raw Material per
Materials Products unit of Output

During the Previous During the Current


Financial Year financial year

-- 77 --
There is no Raw Material consumption. It is only Cargo Handling Seaport.

*Industry may use codes if disclosing details of raw materials would violate contractual
obligations; otherwise all industries have to name the raw materials used.
PART – C
Pollution discharged to environment/unit of output
(parameters as specified in the consent issued) Explained under water management
pollutants Quantity of pollutants Concentrations Percentage of
Discharged(mass/day) of Pollutants Variation from
In Discharges prescribed
(mass/day) Standards with
Reasons
a) Water Domestic effluents Analysis Report s enclosed
b) Air Air Quality Analysis Report s enclosed

PART – D
HAZARDOUS WASTE
(as specified under Hazardous Wastes/Management and
Handling rules, 1989)
Hazardous Waste Total Quantity (kg)
During the Previous During the current
Financial year financial year

(a) From Process No Hazardous No Hazardous


(b) From Pollution waste generated waste generated
Control facilities Waste oil generated from generators are being using for
lubricating the machinery. As per Form-4, 300LPA during
current year

PART – E
SOLID WASTE
Total Quantity
During the Previous During the Current
Financial year financial year
(a) From Process - No process Solid waste generated, however domestic solid waste generated

(b) From Pollution


Control facilities 130640kgs
(c) i) Quantity recycled
or reutilized within the unit
ii) Sold
iii) Disposed  Domestic Waste used for filling Low Lying area within port, however KSPL is permitted for Municipal
Dumping of the Domestic waste Generated.
PART – F

Please specify the characterizations (in terms of composition and quantum) of hazardous as well as solid wastes and indicate
disposal practice adopted for both these categories of wastes.
 There is no solid waste generated in the plant
 Waste oil generated from generators is being used for lubricating the machinery parts.

PART – G
Impact of the pollution abatement measures taken on conservation of natural resources and on the cost of production.
 It is not a production unit. There are no fugitive emissions from the plant. The pollution abatement measure is mainly
linked to dust suppression by water sprinkling, which will further improve the surrounding Air Environment, whereas
for development of natural resources, the green belt is continuous developed throughout the port premises.
PART – H
Additional measures/investment proposal for environmental protection including abatement of pollution, prevention of
pollution.

-- 78 --
- Using of Dust Sweeping Machine
- Water sprinklers at all transfer and fugitive emission sources.
- Controlling of Vehicular Speed
- Tarpaulin arrangement for Vehicles.

PART –I
Any other particulars for improving the quality of the environment.
A Green belt area of 12.25 acres developed through out the port area, and further being enhanced as a continuous process.
3.8.1.1.3 APPLICABLE ENVIRONMENTAL LAWS

APPLICABLE ENVIRONMENTAL REGULATIONS

The following statutory requirements applied in the state of Andhra Pradesh have been taken into consideration:

1. Water (Prevention & Control of Pollution) Act, 1974 and the rules made thereunder.
2. Water (Prevention & Control of Pollution) Cess Act, 1977 and the Rules made there under.
3. Air (Prevention & Control of Pollution) Act, 1981 and the rules made there under.
4. Environment (protection) Act, 1986 and the rules made there under.
5. Hazards Waste (Management & Handling) rules, 1989.
6. The public liability Insurance Act, 1991 and the rules made there under.
7. The factories Act 1948 with the Andhra Pradesh State rules.

The competent authorities in the application of the mentioned set of statutory requirements (1 to 6) are the “Andhra Pradesh
Pollution Control Board (APPCB) whose headquarters is in Hyderabad and its regional and sub-regional branches are all over
the State.

• The APPCB Engineers/Scientists during their surveys collect samples of the industrial discharges/emissions after the
treatment to be analyzed in their own labs.
• The results of the analytical reports are sent to the M/s. Kakinada Seaports Limited. The M/s. Kakinada Seaports
Limited has been authorized to water discharging, noise and emissions in atmosphere.
• The extensions of the mentioned authorizations have been requested when expired.
• The M/s. Kakinada Seaports Limited has shown that compliance is important to it, displaying a willingness to accept
guidance from A.P. Pollution Control Board in this matter.
• The industry has demonstrated in the past its ability and commitment to work closely with A.P. Pollution Control
Board staff to meet environmental requirements.

-- 79 --
Annexure-3.1: Public Hearing under EIA

Sl. Issues raised by the Public Compliance from Industry (as Implementation Status (as
No. in EIA document) reported by the Developer)
1 Sri. G. Srinivas, Sarpanch, Vakalapudi, Shri Y.S. Prasad, CEO, KSPL At present the port management is
Kakinada welcomed the project and he stated that at present the port conducting the health checkups of
expressed that there will not be much management is conducting the the workers working in the port and
pollution problems due to this project is health checkups of the workers by no fishermen have lost their
away from habitation and further utilizing the services of specialists livelihood due to port development.
requested the management to address in Apollo Hospital and same will
the safety and occupational health be continued
problems of workers working in the port
and to provide employment to the
fishermen community who have lost
their livelihood.
2 Sri. K. Satyanarayana, Sarpanch, The management responded The surrounding industries causing
Suryaraopeta welcomed the project positively and assured to air pollution and ash nuisance is
and requested the Govt. to take complete the task. beyond KSPL purview, and KSPL
remedial action over the surrounding has no control over fishermen to
industries causing air pollution and ash catch fish in the ocean and there is
nuisance. Further requested the port absolutely no objection from KSPL
authorities to allow fishermen to catch over fishermen to catch fish in the
fish in the ocean and also requested to ocean. At present there is no park
modify the park located adjacent to the located adjacent to the port to
port. modify.
3 Sri P.V.V. Satyanarayana, Sarpanch, The management stated that the The generated dredged material
Indrapalem welcomed the project and generated dredged material will partly used for back up area
he requested the port management to be used for back up area development and part disposed at
take precautions in disposing the development and part will be designated dumping site near
dredged material and to take care of disposed at designated dumping Uppada in the sea.
health needs of workers, people and site near Uppada in the sea.
fishermen.
4 Sri. G. Srinivas, Sarpanch, Vakalapudi, The management clarified that the The construction of new berths
welcomed the project and suggested to construction of new births is took place in the southern side and
provide rehabilitation to the fishermen proposed to take place in the no rehabilitation was required.
living in fishing harbour. southern side and as such no
rehabilitation is required
5 Sri. K. Parameswar Rao, Kotha ---- Positive Response –
Kakinada, welcomed the project and Implementation Status Not
requested the Govt. to take measures Applicable in this regard.
to control pollution due to the
surrounding oil units.

-- 80 --
Sl. Issues raised by the Public Compliance from Industry (as Implementation Status (as
No. in EIA document) reported by the Developer)
6 Sri. G. Gurraju, Sarpavaram Junction, The management stated that Positive Response –
welcomed the project and he was presently port is having dust Implementation Status Not
happy with the measures taking by the sweeping unit, sprinklers for dust Applicable in this regard. Anyways
port like dust suppression through suppression and tankers for road Management has procured an
water sprinkling. wetting and further assured to use additional dust sweeping machine.
sophisticated methods to control
pollution
7 Sri. Venkateswara Rao, Kakinada, The management assured to Solar Lights provided on ADB
welcomed the project and stated that provide employment to the local Road, and maintaining the same.
the project is providing employment to people to the most extent.
many people and requested to provide
avenue lighting system in the Beach
road.
8 Sri. P. Adinarayana, Jagannaickpur, The management assured to Positive Response –
welcomed the project and requested protect the environment by Implementation Status Not
the management to protect the takingup more avenue plantation Applicable in this regard, Anyways
environment besides providing along both sides of the road the management is committed to
employment. protect the environment by
adopting all feasible environment
friendly aspects.
9 Sri. G. Soma Raju, Ex. MPTC, The management assured to The management provides
Suryaroapeta, welcomed the project provide employment to the local employment to the local people to
and expressed unhappiness over the people to the most extent. the most extent.
pollution caused by oil units and
requested the port to provide
employment to the locals.
10 Sri. Dasari Sattibabu, Komarigiri, The management assured that The management provides
welcomed the project and dismay over the employment preference will employment to the local people to
not providing of employment and be given to the local people only. the most extent.
requested the management to provide
free power and to adopt the village.
11 Sri. Bhargav, Kakinada, welcomed the The Management has committed The management provides
project and requested the management to contribute Rs. 1 Crore and employment to the local people to
to provide employment to all the skilled CSR for augmenting drinking the most extent & the management
people in the area. While handling Iron water supply to Kakinada Town is committed to protect the
ore, port authorities shall take all besides providing green belt in environment by adopting all
precautions such as coverage of ore, the Mc Laurin High School in feasible environment friendly
dust suppression, etc., Further the port Kakinada aspects.
shall also develop green belt as well as
avenue lighting.

-- 81 --
Annexure-3.2: Case Study of Kakinada Deep
Water Port

PPP TOOLKIT for Improving PPP Decision-Making Processes, Ministry of Finance, GoI

GoAP handed over the project facilities to KSPL in March 1999. All immovable assets were transferred
without any consideration. All movable assets like tugs, cranes and forklifts were transferred at a rate
calculated as per the norms agreed in the concession agreement. Soon after, it was realized that the
project was not likely to be viable on the existing terms of the concession. GoAP reportedly failed to
allow KSPL to handle the cargo mix as mentioned in the tender forms. This included agri-centric cargo
like fertilizers, oil extractions, sugar, rice and wheat that constituted 70 per cent of the projected
volumes at the time of the bid. In fact there was considerable social unrest with respect to handling of
commodities at the anchorage port and the deep water port. There were instances of the anchorage
port workers going on strike in protest of the deep water port handling agri commodities such as wheat.

KSPL thus was unable to meet the obligation of the MGA. This also impacted the financial closure for
the Phase 1 development. Accordingly, there were several rounds of negotiations and discussions
where KSPL requested the government to withdraw the MGA clause and retain only the revenue
sharing clause. In 2003, the Government agreed that the payment of MGA can be rescheduled
ensuring that the net present value of the amount to be paid during the concession period remained the
same. KSPL was thus able to achieve financial closure for the Phase 1 development in 2004 which
envisaged back-up area development, railway line connectivity and procurement of equipment. In 2004,
Salgaocar Mining Industries Pvt. Ltd. (SMIPL) was inducted as a shareholder in KSPL. Subsequently,
KSPL took up the development of the fourth berth and an OSV complex in 2007. The same was
completed in 2008.

Despite the changes in the concession agreement, KSPL continued to experience difficulty in attracting
traffic and paying the MGA to the Government. In addition, the development of the new ports of
Gangavaram and Krishnapatnam, in the vicinity of Kakinada, with modern facilities and a deeper draft,
added to the problems of the KSPL. Accordingly, KSPL once again appealed to the government for
flexibility and amendment in terms and conditions.

After a detailed evaluation and analysis, GoAP, in 2009, agreed to amend the concession agreement
by way of a supplementary agreement. The amendments included an extension in the concession
period from the original tenure of 20 years to 30 years, with a further option for extension by 20 years in
two blocks of 10 years each, elimination of the stipulation with respect to the MGA for revenue sharing
with the GoAP and allowing KSPL to undertake additional/ new developments at the port at the same
terms and conditions of the existing agreement.

In 2009, the principal shareholder L&T sold its stake in KSPL to Kakinada Infrastructure Holdings Pvt.

-- 82 --
Ltd. (KIHPL). KIHPL also purchased the 2% stake held by SMIPL and now holds the single largest
stake in KSPL. The revised shareholding pattern of the company is as follows: KIHPL – 41%; Everlink
Asia Investments Ltd. (owned by the Salgaocar Group) - 30% and Konsortium Ports Pte Ltd. (and its
associate) - 29%. KSPL plans to expand its capacity by 3 million tonnes by constructing an additional
berth with facilities for handling edible oil, other liquid and general cargo at an investment of Rs. 150 –
200 crore.

Key Learning and Observations

Level Playing Field: During the bid process/ tendering stage, the Government had indicated that the
private developer would get complete rights for development of Port. However, during the award of the
project, there were restrictions in terms of the anchorage port that will be operating in parallel. One of
the key reasons for the disputes between KSPL and GoAP was the restrictions on the cargo that KDWP
could handle. In order to protect the volume of cargo at the existing anchorage port, GoAP did not
provide a level playing field to KSPL thus affecting the traffic to an extent. While this issue was resolved
subsequently, ideally it should have been dealt with at the inception stage to prevent an adverse impact
on the project.

MGA to the Government: The revenue maximization approach of the Government by insisting on a
minimum guaranteed amount put substantial pressure on the project and could have derailed it. The
government had to eventually agree to an elimination of this stipulation.

Technical Due Diligence: There were a number of issues with respect to the port assets such as
cavities in the diaphragm wall, additional dredging requirement and requirement for removal of
boulders. Since this was a brownfield asset being privatised, the government should have undertaken a
detailed technical due diligence of the project site to accurately estimate the investment requirement.

Stakeholder Consultation: The project experienced social unrest with strikes by employees of the
anchorage port against the deep water port’s operations. A stakeholder consultation prior to the
appointment of the private operator where various affected parties would have been taken into
confidence could have prevented such disruptions.

Resolution of Issues through Mutual Discussions: The noteworthy learning from this project is the
amendments that were made in the terms of the concession agreement through mutual discussions
without abandoning the project. Despite the nature of the issues such as MGA and the term of the
concession agreement, both GoAP and KSPL mutually agreed to modify the agreement and ensured
continuity of the project.

Competing Facilities and Better Packages: Newer ports such as the Gangavaram Port and the
Krishnapatnam Port have given tough competition to KDWP. Both these ports had competitive
advantages in terms of being Greenfield ports, availability of huge land for future expansion, longer
concession period and better concession terms because of the evolution of concession agreements
and risk sharing mechanisms in the country. Thus while KDWP was at a disadvantage initially, its
concession terms were modified to bridge the gap.

-- 83 --
Annexure-3.3: CSR Details from Apr 2010 to
Mar 2014

Particulars 2010-11 2011-12 2012-13 2013-2014


Donation to Janhit Foundation for 1,800,000 1,000,000 200,000
empowerment of women & children
Donation for Development of cemetery at 500,000
Kakinada
Sensitization Workshop on Safety & health 58,365
to local people
Sensitization Workshop on Security 22,260
Aspects
5000 Saplings plantation drive on the 581,270
occasion of green day on 16.07.10 as part
of the 1 million plantation drive day set by
then Chief Minister A.P
KSPL Set up a techno stall at Kakinada in 199,403
the month of Jan 2011, to educate
Kakinada public on maritime activities
ADB Road Storm Drain Cleaning activity 1,512,990
undertaken as a proactive measure, to
combat flooding of Road outside KDWP in
monsoon season
A modest service oriented initiative of 1,383,740 900,000
providing Ambulance service on 24X7
basis
Provided Solar lamps on ADB Road to 428,000
facilitate the local commuters
Donated an unique Mobile Blood Donor 2,984,000
Van to Indian Red Cross Society Kakinada
Donation to Handicapped & Economically 10,000
poor arranged at tyagaraya gnanasabha at
chikkadpally, Hyd.
Sponsorship for international Coastal 15,000 12,250 20,000
Cleanup Day Conducted by Indian Coast
Guard along with South Asian cooperative
Environment programme (SACEP)
Donation for Durga Puja Celebrations at 100,000
keyes Girls High School, Secunderabad
Financial Assistance for Kakinada Police 408,164
Welfare through DSP Kakinada
Encouraged Fine Arts by Financial 25,000
Assistance to Sri KRKM Memorial
Academy of fine arts, Hyderabad
Donation to Indian Red Cross Society, 30,000 20,000
Kakinada.

-- 84 --
Particulars 2010-11 2011-12 2012-13 2013-2014
Financial assistance for building 1st Floor 2,000,000
of an Auditorium at JNTU Kakinada
through ECK Development trusts
Contribution to Cultural Activities by 50,000
Donation to Hyderabad Bangalee Samiti
Donation for Youth Development activities 1,000,000
through the young men’s Happy Club,
Kakinada
Donation for Development Activities for a 1,000,000
section of women to Sri Sarada niketanam
purva vidardhi (nee) sangham
Uniforms for poor Students (Through 25,000
APPCB Officials)
Financial Assistance for construction of 200,000
library Hall at District Police Office,
Kakinada.
Nilam Cyclone Relief Material Supply 150,000
Encouraging Sports by financial assistance 200,000
to Hyderabad Hockey Association
Encouraging Socio-Cultural Activities by 500,000
providing donation to Swarna Bharathi
Trust
Encouraging Socio-Cultural Activities by 100,000 300,000
providing Sponsorship for Kakinada Beach
Festival at Vakalapudi, through RDO/
District Collector Kakinada
Financial assistance for Police Welfare to 500000
Kakinada Police Fund
Uniforms Distribution through Sri Sai Poor 25,500
People Society Associated with Bharatiya
Mazdoor Sangh Kakinada on 1st May,13 to
Orphan, Blind, Disabled Children
Good News service for the Blind Towards 200,000
Donations
Donation for distribution of cotton cloths for 20,000
old age & poor peoople through social
service worker Mr. L. Chinna Babu,
Kakinada ( cloths purchase from Sri
Dhanalaxmi cut pieces)
Donation under CSR to bring out 2nd 50,000
edition yatra special supplement on east
godavari heritage, traditions, tourism and
industries scenario.
Supply of materials for repairs works to 597,353
Terrace, ceiling of slab, columns & beams
in Ground floor and first floor , Supply and
fixing of Reno Sintex Drinking Water Tank
(2KL) and Supply of Tent House Items for
inauguration of New Drinking Water Tank
Opening at Kumbabishekam temple in
beach road Kakinada.

-- 85 --
Particulars 2010-11 2011-12 2012-13 2013-2014
Distribution of Rice bags for flood Victims 228,615
Area
Hrudaya cure little heart foundation 1,000,000
Free Eye Camp at KDWP on 25.09.2013 16,352
Chandra rajeswara rao foundation 1,000,000
Purchase of Maquet servo-s Upgradeable 4,357,401
Ventilator plat form medical equipment and
other medical equipment for Kakinada
hospital
Sambayya (Security) towards donation for 5,000
heart operation purpose
ISWMAW towards Sponsorship for 100,000
International Conference on Solid Waste
Management(ICO SWM-2014)
Fund Given to Indian Navy Welfare 1,500,000
Service Tax on Sponsorship 241,020
Sponsorship for Coast Guard Week 50,000
Celebrations 2014
Construction & Supply of material for New 220,644
toilets 2No's , 2KL water tank and supply &
Fixing of Iron Structure & Galivaliam Sheet
at M.P.U.P School, Fishing Harbor,
Kakinada
Supply and fixing of play equipment at 230,160
AMG School, Dairy Farm Center, Kakinada
Maintenance charges for KSPL donated 80,000
Blood donar Van
Total 3,589,298 7,468,894 6,837,250 10,262,045

-- 86 --
Annexure-3.4: Guidelines on Corporate
Social Responsibility Fund, District Collector
East Godavari District, 1 June 2013

-- 87 --
Annexure-3.5: Companies (Corporate Social
Responsibility Policy) Rules, 2014, GoI,
Ministry of Corporate Affairs

-- 88 --

You might also like