You are on page 1of 3

A post-tensioned concrete slab

cantilevering 6.50 m

Dezsõ Hegyi - András Árpád Sipos

We designed a post-tensioned concrete cantilever with a 6.50 m free span supported by columns for a villa
near Pécs. The shape and number of the bonded strands were determined to balance the dead load of the
structure by the transversal component of the prestressing force. The deflections measured on finished
structure are in good agreement with the approximated values of the structural calculation.
Keywords: post tensioning, cantilever

states HEA400 beams should have been placed in 400 mm


1. Introduction distance. This is a rather slender structure for such a cantilever
We took part as structural engineers in the design works of a but with the additional stone coatings it was even too thick
villa in the suburbs of Pécs. From the structural point of view regarding the architectural vision. Another difficulty of this
the most challenging task was to design a flat cantilevered slab approach is how to establish the point-like supports. The idea
over one of the terraces of the building (Fig. 1). In the vision of the post-tensioned structure seemed to be a more appropriate
of the architect designers the slab should appear as a heavy, answer in the given situation.
monolithic, but in the same time narrow element. Furthermore, We carried out the structural calculations according to
the slab is covered by stone-surfacing in all its sides, reducing the prescriptions of the Eurocode 2. Slabs with large span
the available space of the load bearing structure. Not only or cantilevering are typically difficult to design in the terms
the 6.50 m free span made the structural design difficult, but of deflections and crack widths and not in the terms of load
forming supports was challenging too, because the terrace is bearing capacity. Even in the case of a long cantilever and
neighboured by a large, open room allowing only columns to high loads one can determine a cross-section satisfying the
be placed under the slab. design rules in the Ultimate Limit States (ULS), but due to the
During the preparation of the construction plans the idea increase in the weight of the structure the deflections increase
of a post-tensioned concrete slab occurred. According to the rapidly. Basically, a prestressed concrete structure is not more
preliminary calculations 300-350 mm thickness seemed to efficient according to its load bearing capacity compared to a
satisfy both the structural requirements and the architectural conventionally reinforced concrete structure (Bölcskei and
expectations. Finally we decided to process this solution in Tassi, 1970). Only the higher concrete class leads to a slightly
details. The structure was constructed in December 2008 and higher bending resistance. (In the case of unbonded tendons the
the deflections measured since then are in good agreement with membrane effect increases the load bearing capacity slightly
the calculated values. as well, but this is generally neglected in the calculations.)
However, in the case of a cantilever the material constants,
2. Design and Structural especially the terms describing the time-dependent deflections
are uncertain.
Calculations In the case of post-tensioning typically the application of
As a first step we designed a structure of steel beams. To fulfill unbonded tendons is more efficient. In this case leading the
the requirements both in the serviceability and ultimate limit tendon along the curve obtained by reflecting the bending
moment diagram to the horizontal plane gives a good first
Fig. 1: Bottom view of the cantilever after the formwork had been removed approximation for the detailed design (fib, 2005).
In the case of bonded tendons the deformations in the
concrete influence the stress in the tendons and the losses due
to friction. In the mechanical point of view the structure with
bonded tendons cannot lose stability if it is loaded only by the
prestress. Although in the case of unbonded tendons losing
stability is theoretically possible, the postcritical behaviour is
still advantageous.
During the calculation we found that the most efficient
way of design is determining the number of the strands
and the initial prestress from the assumption that they must
balance the characteristic value of the rather high dead-load
(approximately qk=14.00 kN/m2), i.e. no deflection occurs. To
provide resistance against the extra bending moments from the

66 2011  •  CONCRETE STRUCTURES


to the plane of slab at the cantilevered
Fig. 2: The arrangement of the cables end (Fig. 2). Since the segments are
and the structural dimensions parabolic, the transversal component of
the prestressing force is constant along
one segment (the second derivative of
the shape function along one segment
is constant). Taking into account the
transversal component among the
dead loads we determined the needed
cross sectional area of the tendons
and the number of cables (8 strands
each with a 150 mm2 cross sectional
area for a 1.00 m width are placed,
they are arranged in 2 cables) and the
initial prestress (σp0=1250 MPa), too.
In this arrangement the prestressing
completely balances the weight of
structure along the cantilever.
As we mentioned above, we
approximated the amount of rebars
on a simplified model substituting
the prestress by its transversal effect.
This means that in each parabolic
segment the vertical component of
the prestressing force is applied as an
external load on the structure and the
axial load is neglected. Based on the
results of the approximation we finished
live loads we placed nonprestressed rebars into the structure. the detailing by a calculation in a FE code where all the loads
For concrete structures typically the major part of loads is the in the prescribed combinations and the prestressing force with
self weight, thus we aimed a structure which has no deflections its varying eccentricity along the cables were included.
under the dead loads long time after construction (i.e the We found that the simplified model above is rather accurate
prestress was taken into account with its time dependent losses compared to the FE results in the terms of the amount of
and the material constants were determined for the infinite the reinforcement. However, in the simplified model the
time as well). In this case the live loads induce a rather small application of the external force alters the resultant load thus
final deformation of the structure in service. However, one can the reactions at the supports are underestimated. The cross
expect an upward deformation after applying the prestress since sections were checked under eccentric compression, including
generally the highest prestressing force is acting on a concrete the limitation of stresses in the SLS, which turned out to be
which has not reached its designed strength yet (Nilson and crucial in such a highly loaded case.
Winter, 1987). The design of the anchorage devices requires the highest
The pure application of post-tensioned strands (i.e. care. As we mentioned above 4 strands are placed in one
by providing such a strand cross section, which fulfil the cable, the distance between the cables (500 mm) exceeded the
requirements in the ULS) would result in an upward deflection prescribed minimum of 400 mm by the manufacturer. Based on
of the structure even long time after construction due to the the advice of the specialist we chose an anchorage accepting
high dominancy of the dead loads. The drafted strategy does 4 strands. In this case about Pm0=750,0 kN force is transferred
not only help to avoid this outcome, but it leads to a lower to the slab at one anchorage at the time of application of
amount of steel usage, too. prestressing. To avoid splitting a dense (Ø10/60) reinforcement
As we mentioned above in the ideal case the curve of and a beamlike longitudinal reinforcement were applied.
the tendons follows the reflected bending moment diagram,
however, in practice this shape is impossible. For example,
above supports the tendon must be led along a curve instead of 3. Construction
forming a sharp edge (Fig. 2). The tendon is typically placed The construction started in autumn, the cantilever was
between the upper and lower layers of reinforcement. As an constructed in December. The formwork and the reinforcement
additional condition on the shape in the case of a cantilever were placed by the building contractor but the anchorages
the tendon should be finished at the centreline of the free end and the cables were placed (Fig. 3) by the specialist (Pannon-
and its tangent must be parallel to the plane of the slab to Freyssinet Ltd.). It is crucial to place the cables along the
avoid local failure and undesired increments in the deflections prescribed curves since according to the above explanation a
(Nilson, 1987). slight difference from the prescribed (parabolic) shape leads
As a first estimation on the cable layout we determined to a high error in the transversal load arising from prestress. A
a curve consisting of more, smoothly connected parabolic special care is needed to avoid the segments with horizontal
segments in such a way, that it is kept between the lower tangents or small curvatures getting an opposite curvature
and upper surface of the 350 mm thick slab. Altogether 3 compared to the designed shape. This leads to an opposite
segments were needed to produce the layout of tendons along direction of the transverse load. In our case at the ends of the
the slab, the connections of the segments are the inflexion cantilever more modifications were needed to really produce
points of the final curve. The determined curve is tangential the designed shape.

CONCRETE STRUCTURES   •  2011 67


Fig. 3: The cables and the rebars before pouring the concrete Fig. 4: Side view of the cantilever after the formwork had been removed

We applied a C30/37 classed concrete. In spite of the Now about 50-60% of the final loading is presented so we
unfavourable weather the test cubes verified that the designed expect the final deflections will still fulfill the requirements
strength was reached in the construction. The prestressing could of the standard. Due to the higher load the stiffness against
be applied just after the prescribed strength of the concrete dynamical effects will increase as well. It is worthy to mention
(23 MPa cylinder strength on specimens) was exceeded. In that the architectural vision of the building is a dynamic
our case this phase happened about one month after pouring appearance by plenty of parallel edges. Due to the inaccuracy of
the concrete. After prestressing the protective sheaths were the construction the final location of more edges differs slightly
grouted. from their designed position. From several viewpoints these
Based on the calculations we expected the slab to have kinds of inaccuracies strengthen the deflection of the cantilever
a 20 mm upward deflection after prestressing. The upward slab visually. We hope that with placing the final coverings
deflection could not be observed, the slab did not separate from the inaccuracy can be reduced. However, it also shows that
the formwork. A higher concrete class with a higher modulus the conservative limits on deflections due to visual reasons
of elasticity can partially explain this result, however, the main in the standard should be handled with care: in some special
reason is the rather high force needed to balance adhesion and architectural arrangements an even stricter limit is needed to
separate the slab and the formwork. fulfill the requirements of the users.
We aimed to measure the deflections after the formwork had
been removed to follow the viscose deflections. Unfortunately
the construction was stopped after the structural works had 5. ACKNOWLEDGEMENTS
been finished so we have no data from the most interesting first
six months. What we know is that at the time of removing the The authors thank Csaba Böhm and Dénes Dalmy from the
formwork there were no observable movements downwards Pannon-Freyssinet Ldt. for their advices and comments on
and after 10 month of prestressing the measured deflection is the plan.
slightly below 20 mm which is 1/650 of the effective span.
Applying a dynamic load (jumping on the slab) it seems to
be very stiff. 6. REFERENCES
Bölcskei E., Tassi G. (1970): “Concrete Structures – Prestressed Structures”
(In Hungarian), Tankönyvkiadó, Budapest
4. CONCLUSION Nilson A.H., Winter G. (1987): “Design of concrete structures” McGraw-Hill
Book Company, New York
Nilson A.H. (1987): “Design of prestressed concrete“ John Wiley and Sons,
We designed a 6.50 m cantilever applying a post-tensioned New York
reinforced concrete slab. During the design we investigated MSZ EN 1992-1-1:2005 Eurocode 2: “Design and Construction of Reinforced and
some other structural possibilities as well and found that Prestressed Concrete Structures Part 1-1”
the 350 mm thick slab is the most efficient solution for the fib Bulletin 31 (2005) “Post-tensioning in buildings”, Technical Report, fib
problem. The final solution is definitely the thinnest compared
to the other variants namely the system of steel beams (HEA Dezső Hegyi (1976) Received his M.Sc. architect degree from the BUTE in
members, the thickness is 400 mm) or a reinforced concrete 1999. He defended his PhD in 2006 about nonlinear analysis of membrane
structures. He is an assistant professor in the Department of Mechanics,
slab strengthened by beams (the thickness is at least 550 mm). Materials and Structures.
Comparing the costs the price of the final solutions was about
50% of the steel system and about 150% of the simple RC András Árpád Sipos (1980) Received his M.Sc. architect degree from the
slab. In Figure 4 beyond our cantilever another cantilevered BUTE in 2003. He defended his PhD in 2007 about the computation of spatial
deformation of RC rods. He is an assistant professor in the Department of
slab made of RC beams is visible as well illustrating the huge Mechanics, Materials and Structures and the member of the Hungarian
difference in the slenderness of the two structural systems. Group of fib.

68 2011  •  CONCRETE STRUCTURES

You might also like