You are on page 1of 1

KING FAISAL SPECIALIST HOSPITAL-

JEDDAH, KSA D O CU MEN T SU BMI T TAL S HEET


Co nt in u at i on she e t

Project Ref. Contractor No. Rev


CN1169 Saudi Bin Ladin Group - PBAD DS/CN1169P01/14894 02
SUBMITTAL CONTENTS DESCRIPTION Date: Sheet 2 of 2
LEVEL 3M WATER SUPPLY SYSTEM LAYOUT MASTER PLAN SEGMENT F1 20-03-2019

COMMENTS

1. The review of this Shop Drawing is limited to checking the correctness of the changes shown in the
clouded areas only however the drawing outside of the clouded area is checked for any
inadequacies too.
2. This review supersedes the previously approved and coded-B Shop drawing # 1169-01-Z1-F1-L3M-
SD-P-WS-2106170-01. All comments given in the previously approved shop drawing however hold
good and shall be complied in toto. Therefore review comments for this shop drawing shall be
read in conjunction with the review comments on the previously approved shop drawing.
3. Holding design integrity in the final installation of work shown in this shop drawing through spatial
coordination of this work with other trade’s installations at site is contractor responsibility.
4. Any Technical integrity engineering required in the preparation of shop drawings to uphold the
design intent of the project is contractor responsibility.
5. Provide compensation for harmful stresses in the piping due to temperature changes (expansion-
contraction of pipe) and support it with calculations.
6. Provide seismic restraints with supporting calculations.
7. Installation shall be as per project specifications, approved method of statement and
manufacturer recommendations.
8. Installation of all final fix shall meet the architectural requirement is the contractor responsibility
9. Separate drawings installation / connection details of plumbing fixtures and specialties and
sectional drawings showing spatial coordination with other trades shall be submitted per project
specifications
10. Refer to comments on the Drawings.

Form Ref: PM-07 Rev.00

You might also like