Professional Documents
Culture Documents
GROUP 1
Contents
1. Introduction ........................................................................................................................................ 4
2. Conceptual Design .............................................................................................................................. 5
2.1) Description of structural arrangement .................................................................................. 5
2.1.1) Transfer of lateral loads ........................................................................................................ 6
2.2 Appraisal of alternative schemes ............................................................................................ 7
2.21) Conceptual Design 1 .............................................................................................................. 7
2.22) Conceptual Design 2 .............................................................................................................. 7
2.23) Conceptual Design 3 .............................................................................................................. 9
2.24) Justification for final proposed design ................................................................................. 10
2.24)a) Aesthetics ......................................................................................................................... 12
2.24)b) Imaginative and innovative use of structural steelwork .................................................. 13
2.3 Outline of design process ....................................................................................................... 14
3. Loading .............................................................................................................................................. 14
3.1 Loads ....................................................................................................................................... 14
3.2 Load combinations ................................................................................................................. 15
3.31 Summary of actions .............................................................................................................. 16
4. Economic Design ............................................................................................................................... 16
4.3 Design Selection .......................................................................................................................... 17
5. Frame Analysis .................................................................................................................................. 18
5.1 SAP2000 Results ......................................................................................................................... 18
6. Frame Design .................................................................................................................................... 19
6.1 Member Design ........................................................................................................................... 19
6.2 Design Checks ............................................................................................................................. 21
6.2.4 Column Bases ....................................................................................................................... 22
6.3 Assessment of sway sensitivity ................................................................................................... 22
7. Buildability ........................................................................................................................................ 24
7.1 Safety in Construction Sequence ................................................................................................ 25
7.2 Construction Method .................................................................................................................. 26
7.3 Detailed method of construction of elements............................................................................ 27
7.3.1Base plates ............................................................................................................................ 27
7.3.2Columns ................................................................................................................................ 28
7.3.3 Rafters .................................................................................................................................. 29
7.3.4 Bays ...................................................................................................................................... 31
7.3.5 Panels ................................................................................................................................... 32
7.4 Problems during construction..................................................................................................... 33
CIVE4106 Page 2 of 39
Group 1
CIVE4106 Page 3 of 39
Group 1
1. Introduction
The project brief requires the design of an aquatics centre able to house an Olympic sized
swimming pool as well as an ice rink as the primary requirement. The spatial requirements of these
elements need to be satisfied allowing appropriate dimensions to be formulated for the centre.
This project is to be carried out in a regional city in the UK. The aquatics centre is to also
include secondary volumes such as such as offices, plant rooms, stores, toilets and changing
facilities. Furthermore, the brief also required the inclusion of an upper floor café and not to
mention features such as flumes, Jacuzzis and etc. to attract more visitors.
The structure is to be constructed utilising structural steel. Steel structures have become
more predominantly used in the construction industry over the recent years. Structural steel offers a
range of lightweight but structurally stable structures and with the combination of creative
innovation and the pursuit of excellence, the use of steel structures will only continue to grow. There
is a plethora of reasons why steel was opted for instead of concrete. Steel has considerably higher
strength than concrete allowing for large spanning structures to be built. Steel also does not buckle
easily.
The content of the report outlines a detailed overview of several design schemes proposed
with focus on the final chosen scheme. Detailed drawings and calculations will be done for the final
scheme. Likewise, other aspects related to the project such as construction method, wind forces
assessment, sustainability and buildability will also be considered. The design of the members
CIVE4106 Page 4 of 39
Group 1
2. Conceptual Design
A symmetrical portal frame with a pitched roof was utilized as the main structural system for the
proposed construction of the aquatic centre in the UK. Portal frames were chosen for its obvious
benefits ranging from structural efficiency, cost effectiveness to ease of maintenance. The
longitudinal span for the structure is supported by 15 steel columns; with a span of 9m for columns.
Inside of the structure, there are a total of 15 steel columns which are 9m apart from each other
with the exception of the mezzanine floors to support the upper floor café. This allows an open
space concept to be fully realized and ensures that movement throughout the entire structure flows
smoothly with no obstructions. This will then provide good accessibility for audiences, clients and
players to walk through the ground floor of the aquatic centre. It was proposed that a concrete wall
is to be constructed to separate the swimming pool and the ice rink and provides thermal and
acoustic separation. This wall also improves the overall stability by carrying some of the load applied
Cross bracings will be installed on both sides of the frame. The function of a bracing is to resist
lateral loads such as wind and earthquakes as well as transferring the loads from these forces
efficiently to the building foundations. The bracings will be installed diagonally to prevent the
Wind bracings also takes the large amount of the heavy ceilings and floors and transfer it to one
another. Rather than building an auxiliary support structures, cross bracings utilises and applies the
support already available. In addition, purlins and side rails will be installed to help support the sheet
CIVE4106 Page 5 of 39
Group 1
cladding. It is believed that purlins are the perfect material to cover your open space gracefully and
2.1.1) Transfer of lateral loads Commented [AJ2]: Where is transfer through frame?
Lateral loadings are generated from wind or an earthquake. Wind loads will hit the side of
the building horizontally. To encounter this load, cross bracings are designed and implemented into
our design to resist lateral wind loads acting on the proposed aquatic centre. Structural integrity for
lateral loads in the longitudinal direction is proven by proving the integrity of the elements of the
Railing - As for the longitudinal lateral stability, rails transfer wind loads to the structural system.
These members are mainly subjected to bending moments and should be checked as beams both in
ULS and SLS. These members should also be checked for lateral buckling. These members are
arranged vertically on the end frame to ensure the lowest span possible with a spacing of 2 m.
Longitudinal beams - The beams transfer the lateral wind load hitting the end of the building to the
wind bracing system in the end of the building. These members are mainly subjected to compression
loading as well as bending moment when wind on the other side of the building is considered. The
beams should be checked as columns subjected to one-directional bending. These members should
CIVE4106 Page 6 of 39
Group 1
also be checked for buckling. Two beams go around the full circumference of the building to ensure
a low span for railings as well as provide buckling support for the columns in the portal frame
system.
Wind bracing - The flat steel bracing system transfer the lateral loads from the longitudinal beams to
the foundation. These members can only be subjected to tension loading and should be checked as
normal tension bars. Two elements working in opposite directions are placed in all four corners of
the building to ensure structural integrity for lateral loads in both directions. Fly bracings are to be
2.2 Appraisal of alternative schemes Commented [AJ3]: Reduce in size – valued low in grading
In our design process, we have come up with a few ideas to include different types of
structural systems such as trusses, portal frames, 2D and 3D space frames to ensure we produce the
preferred economical and sustainable design. There are 3 conceptual designs that will be explained
below. We have identified the advantages and disadvantages of each conceptual designs and came
Note: Refer to Progress Report 1 regarding the pros and cons of each design scheme.
CIVE4106 Page 7 of 39
Group 1
Truss and cable systems were proposed in this conceptual design. Trusses are defined as an
interconnection of triangular structures that gives strength to withstand more heavy and dynamic
loads. The cable system will be anchored on tall columns and will support a lightweight and flexible
tent-like roofing structure. The cable system will be supported by the internal truss system.
One of its advantage is that trusses are extremely strong as it can resist both compression and
tension besides being able to withstand extreme conditions. However, columns bearing cables will
need to be internal thus restricting the open space of the arena. Regarding this issue, it will definitely
not be suitable for our design as space is limited in the aquatic centre.
As for conceptual design 2, we explored the possibility of including space frames in our
design. The design utilizes a 3D space frame bended in two directions which allows for a bold
architectural expression. The design utilizes heavy internal concrete walls for lateral stability.
Space frames helps in utilizing spaces as it can provide freedom of movement due to having minimal
columns. Throughout our research, space frames will be more preferable because the deflections
are lesser as compared to trusses. This proves that space frames can withstand heavier loads with
CIVE4106 Page 8 of 39
Group 1
Figure 2.5: Cross section showing bracings and triangular configuration columns and beams
For design 3, we considered a combination between a portal frame system and 2D space frames as
the main structural elements. The space frame replaces the elements of the portal frame so that we
can make use of their lightweight attributes which are well suited for the long span required for the
aquatic center, while still maintaining the practicality of the portal frames.
The 2D space frames are designed as three-chord trusses connected by slanted bars. This design
allows for a good resistance to bending while the triangular shape makes the cross-section resistant
to buckling. This results in a lightweight structural system that is discreet and leaves room for the
spectators to view the sporting events. This solution is however more expensive than an ordinary
portal frame design as we cannot utilize ordinary cross-sections for the rafter.
CIVE4106 Page 9 of 39
Group 1
Note: For the final design, the project was designed as simple portal frames to be able to meet the
Careful consideration was taken and it was decided that conceptual design 3 was to be
chosen as the proposed design for the aquatic centre. Based on the conceptual design 3, it has
strongly proven that there are more pros than the cons as compared to the other conceptual
designs. First and foremost, we can save a lot on the maintenance cost and the project time
completion due to the ease of construction and installation of portal frames as compared to cable
Although space portal frames have a higher construction cost than the conventional portal
frames, it allows the use of a smaller cross section because it can support a larger span. Therefore,
there will be lesser columns in the aquatic centre thus, providing bigger interior space and
minimising costs on constructing columns. Construction of space frames are generally more labour
intensive meaning the cost-benefit analysis would have to take into consideration the labour
The design was also picked due to its overall stability through the provision of a concrete
shear wall in the structure which also encloses and separates the space between the Olympic pool
and the ice rink. Due to its structural indeterminacy, space frames are generally more robust and in
the event of any collapse or accident, the truss will be able to redistribute the loads to the other
Space frames are considerably stronger due to the rigidity of the triangular pattern. Space
frames are only subjected to axial tension and compression not to mention, torsional moment and
bending can be considered insignificant. A common downside to long spanning sections is the
CIVE4106 Page 10 of 39
Group 1
buckling effect; a triangular cross section will counteract this weakness by strengthening the
torsional resistance.
CIVE4106 Page 11 of 39
Group 1
material. With the application of glass windows, it improves the entrance of natural light into the
aquatic centre during the day. Thus, it helps save energy which reduces the overall energy
consumption of the aquatic centre. Glass windows help brighten up the aquatic centre and most
importantly gives a mood boost for all guests. These windows will also provide an unobstructed view
into the open area. Due to its characteristic of being UV stable, it will not experience cracks as it is
not attacked by ultraviolet radiation. Furthermore, through the incorporation of photovoltaic glass
panels, the light intensity entering the building can be controlled. Hence, the temperature of the
structure can be partly controlled based on necessity during different seasons throughout the year
With the use of portal frames in our structural design, it helped maximize the span between
column to column (9m span). Therefore, minimal columns will be used in our design structure which
will then provide an ample space for guests to walk through and carry about their routine in the
aquatic centre. Lesser columns would give a better view of the interior as it will look wide and neat.
The incorporation of glass fiber reinforced concrete (GRC) and aluminium as cladding will further
enhance the structure’s visual appeal. These materials are very malleable and allows various shapes
to be formed. Aluminium also provides a certain degree of thermal insulation as well as weather
resistance to snow, rain, wind and etc. In addition to that, aluminium is lightweight thus reducing the
total load applied on the structure, corrosion resistant and also has recyclable properties. GRC
panels such as the ones shown in the diagram will be installed as cladding to transform the building
into a recognizable icon in the foreseeable future and give it a distinct appearance. The shiny
characteristic of the aluminium cladding will also garner the attention of any passerby.
CIVE4106 Page 12 of 39
Group 1
A composite roof will be utilized and it essentially is a roofing structure that is pre-assembled
and consists of insulation sandwiched between two panels of roofing. The benefit of this type of
roofing is easy assembling and fixing. Likewise, an Ethylene Tetrafluoroethylene (ETFE) film will cover
the surface of the roof. This film has many advantageous benefits such as self-cleaning properties
due to its non-stick surface. This material is also recyclable, durable, has high transparency and very
lightweight. Not to mention, the material also has good corrosion and tear resistance.
Haunches are used to reinforce the connection between rafters with columns. Haunches are chosen
The haunch is chosen based on a specific depth to ensure that the resistance of the beam is
adequate for the required moment resistance for the member and a specific length to ensure that
The apex haunch may be cut from a rolled section – often from the same size as the rafter, or
fabricated from plate. The apex haunch is not usually modelled in the frame analysis and is only used
to facilitate a bolted connection. Bolted end plate connections were used over cover plate type
CIVE4106 Page 13 of 39
Group 1
connections as it does not require the use of preloaded bolts. Hence, preparation of contact surfaces
The design of the primary members is evidently a vital aspect in the detailed structural
design. Firstly, the loads that will be acting on the structure has to be identified. The primary loads
imposed on a steel portal frame would be; dead, live and wind load. After determination of the
different load cases, then the load combinations will need to be considered referring to the relevant
equations in Eurocode.
A variety of load combinations were inputted into SAP 200 and the most critical load
combinations were determined. The preliminary design of the members will be conducted based
on this critical load combination. Through trial and error, appropriate sections and beams and
3. Loading
3.1 Loads
Self-weight of the members is determined first to be able to start with the analysis. The below data
was collected to pursue the analysis calculations:
Type of load Description Load
CIVE4106 Page 14 of 39
Group 1
Moving on to calculating the total load on the roof using equation 6.10 acquired from euro code.
The critical load combination for our structure after software analysis was Dead Load + Live Load
combination. Although we used the software to model the analysis every analysis and design check
was verified manually using the elastic analysis method. By using the parallel method of both
automated and manual checks for design and analysis we were able to confirm our values as
accurate.
Limit state design was employed for the load combinations. This principle requires the satisfaction of
two criterias; the Ultimate Limit State (ULS) and the Serviceability Limit State (SLS). Structures
designed in correspondence with ULS will be able to sustain all the actions that is likely to occur
during the entire design life and will remain suitable for use.
CIVE4106 Page 15 of 39
Group 1
The adequacy of design calculation was obtained through the 4 load combinations shown in the
B - - - - -1.35
A - - - - -1.89
Table 3.2: Load Combinations summary
4. Economic Design
During the project, three different structural designs were considered after choosing a concept
design. The designs were judged based on the total material (steel) used. The lightest design is
supposed to be the most economic for this coursework (ignoring difference in labour cost). The
three designs will be compared after fulfilling design criteria of both ULS and SLS.
4.1 Loads
1. Initial design. Frame span is 12m spacing between purlin and rails are 1m.
2. Frame spacing 9m, purlin and rail spacing 2m - This design allows for less purlins and a lighter
frame. The design will need more frames on the other hand.
3. Half haunch length – The difference in rafter cross-section is explored in this design. A shorter
haunch allows for more free space in the room in exchange for a heavier rafter.
Only affected members are recalculated and documented for design 2 and 3.
Section forces are calculated in SAP-model with iterative input.
4.2 Results
CIVE4106 Page 16 of 39
Group 1
no. Purlins Rafter Flybracing beams) Bracing Haunch Column Rails SUM
Design 1 is used as a frame of reference. As the span decrease the total weight of the rafters
increase and the total weight of the purlins decrease as the shorter span allow for a larger spacing
and smaller sections. As the weight of the purlins decrease faster than the weight of the
spaceframes the limiting parameter for this design is the maximum spacing of the roofing material
(aluminum). This design proved to be the lightest which means it will be chosen for this project.
Design 3 returned a far heavier rafter than design 2 as expected. The design is the most
inefficient design material wise but could have been chosen if efficient material use was prioritized
lower than architecture. Therefore, design 2 was chosen as the most economical design scheme.
CIVE4106 Page 17 of 39
Group 1
5. Frame Analysis
The portal frame was modelled and designed on SAP 2000 and then, the fixity of bases was
defined which were considered as pinned but the connections were defined as fixed. Subsequently,
the member properties were defined and consequently the load cases and load combinations are
applied.
The model analysis was then run to obtain the reaction forces including the moments and
internal loads for the most critical combinations which in this case is the dead load (DL) + live load
(LL). Based on these values, the main structural members can be designed.
CIVE4106 Page 18 of 39
Group 1
6. Frame Design
Members have been designed in accordance to EN1993-1-1, consult appendix C for detailed
calculations.
Having a plastic section modulus that is approximately 50% larger than the plastic section
Cross-section with high ratio of Iyy to Izz which is in compliance with Class 1 and Class 2
A haunch extending from the column that is at least 10% of the frame span.
Cross-section with high ratio of Iyy to Izz which is in compliance with Class 1 and Class 2
Members in frame are designed with section forces from SAP 2000 model.
Section forces for secondary members are calculated by hand.
CIVE4106 Page 19 of 39
Group 1
Critical Load
Purlins 9 9 9
per 2m)
Rails 3 3 3
Secondary beams 9 9 9
Purlin 200 45
Rail 300 15
CIVE4106 Page 20 of 39
Group 1
Column Haunch
Purlin Rails
Total weight of structural system 401 ton including fly bracings and bracing system
Shear failure - Shear capacity has to be proven higher than exposed shear force
Moment failure – Moment capacity has to be proved higher than exposed moment
LTB failure – Reduction factor for moment capacity is calculated for an extended moment check
CIVE4106 Page 21 of 39
Group 1
6.2.2 Columns
Shear failure – Shear capacity has to be proven higher than exposed shear.
Axial load with buckling failure for both strong and weak direction – Reduction factor for normal
LTB failure – Reduction factor for moment capacity is calculated for an extended moment check.
Interaction between axial and moment instabilities – Utilisation of both normal and moment
6.2.3 Bracing
Tension failure – Normal capacity has to be proven higher than exposed normal forces.
Design checks were carried out to check the adequacy of the base plate and concrete foundation.
The shear force (VEd) was also compared to the design resistance per unit length (Fw,Rd) such that VEd
< Fw,Rd. Furthermore, VEd<Fa,Rd= Ff,Rd +4 Fvb,Rd with Ff,Rd being the design friction resistance between
base plate and grout and Fvb,Rd being the design shear resistance of 1 anchor bolt was also a check
done. If any of the design checks does not pass, the base plate grade, bolt grade and bolt class can
It is vital to check whether the entire structure will be able to resist the sway mechanism due
to wind effects. Considering the wind direction is at θ=0°, the loadings because of wind acting on the
structure is anticipated to be fully resisted by the portal frames. In resisting lateral loads, the rigidity
and stability of the portal frame are important determining factors. The deformations that occurs in
members produces additional effects onto the structure which must be taken into account. These
effects may only just be first order effects however, if the geometric deformation has a significant
CIVE4106 Page 22 of 39
Group 1
In regards to our proposed design scheme, If the elastic critical factor is more than 10 then
the structure is to be considered as not sway sensitive. According to design standards, sensitivity to
effects of deformed geometry is measured by critical factor αcr and if it is a large value it indicates
α 𝐻 ℎ
𝑐𝑟 = 𝐸𝑑
𝑉𝐸𝑑 𝛿𝐻,𝐸𝑑
where:
𝐻𝐸𝑑 is the (total) design value of the horizontal reaction at the bottom.
Figure 6.1: Measure of αcr Figure 6.2: Portal frame horizontal displacement
CIVE4106 Page 23 of 39
Group 1
Table 6.1 shows the wind load combination that it is sway sensitive
Table 6.2 shows the critical load (live load + dead load) combination that it is not sway sensitive. The
sway sentsitivity was analysed on SAP 2000 and it was found that node 1 for the wind load
combinations was sensitive. Hence, second order effects need to be accounted for.
7. Buildability
The analysis of the structure will be done via elastic method. The steel Olympic facility is erected by
several steel members (portal frames) and is arranged in a symmetrical geometrical form. The
When considering the buildability of the warehouse, extra attention is given to;
1. Plant and equipment management to save labour, time and prevent any damages.
4. Prefabrication opportunities.
5. Initial works that includes dimensional criteria, space allowances and setting out.
CIVE4106 Page 24 of 39
Group 1
scaffolding.
A huge criterion of on-site practices and potential hazards is covered in buildability. Hence,
Computer Aided Design (CAD) are significantly used in visualizing all aspects of buildability.
Construction method is designed in a way as to maximize the speed and minimize the disruption
around the site as much as possible, saving on cost and ensuring efficiency. First off, learning from
past experience then advancing to the step where several methods and plans are modelled. After
In the construction industry many uncertainties arise; hence a higher regard to safety must
be in order. Steel structures offer more safety as they are pre-fabricated and have a longer
serviceability as opposed to the conventional methods of construction. Safety in all aspects have to
1) Considering safety in erection, for instance, having many plants on site congested in one place can
endanger the safety of workers; subsequently, decreasing the efficiency of work done. Therefore,
the right number of plants must be calculated as accurately as possible and there must be plenty
access for the transportation of steel materials, loading and unloading and for the erection itself.
2) During transportation of the pre-fabricated elements from the factory, care should be taken as to
not overload the vehicle. The elements should be properly fastened and secured to prevent it from
moving or falling en-route to the site. Mitigation of this will prevent any unnecessary accidents
CIVE4106 Page 25 of 39
Group 1
which may injure workers or passerbys. Proper measurements of the elements to be done to ensure
3) Furthermore, PPE is required for every worker when entering the site to ensure that the worker is
protected and extreme caution is taken near the roof edges and on scaffoldings. Another important
aspect is the pre-construction training of the human resources must take place in order to ensure
4) Safety lines and railings must be provided for workers at all times. In addition, proper signs must
5) Another approach is the toolbox meetings which are held every day prior to the commencement
6) During roof installation, the roof panels are not to be used as walking platforms because the
unfastened panels cannot support the weight of a person at the edge and can be dangerous.
Therefore, walking platforms must be provided for the workers. Workers not involved should be
directed away from the potential hazard of falling materials until construction is complete.
8) Safety inspectors to be hired to control the safety aspect of the project. Strict penalties and fines
should be imposed on anyone violating safety regulations as per the construction industry to ensure
1) Making sure that the foundation and soil properties are suitable for erection.
CIVE4106 Page 26 of 39
Group 1
2) Utilising plants to place the elements in the correct position as well as inserting the bracings and
connections securely.
3) Checking the alignment of the column bases of the structure and whether the columns are truly
vertical.
4) All connections to be bolted as well as the bracings to ensure that the entire frame is rigid. Then,
Nevertheless, before the construction phase can actually begin, the site must be prepped, materials
must be delivered and stored correctly, adequate erection drawings and method statements should
be prepared and not to mention, safety issues addressed and accounted for.
Since most of the structure of the aquatic centre comprises of steel, hence pre-fabricated steel will
be utilised for the construction of this project. The steel will be transported directly from the factory
7.3.1Base plates
1) Holding down are fixed to the base plate. Each bolt will be casted into the concrete base plate in a
location tube and are fitted with anchor plates to resist pull-out. High strength concrete is to be
2) Stabilisation of columns during construction are achieved through the design of holding systems.
CIVE4106 Page 27 of 39
Group 1
7.3.2Columns
1) The erection of the frame proceeds after all the base plates have been casted into place and
2) The columns will be lifted and placed onto the base plate using a mobile crane.
3) The anchor bolts nuts are tightened when column is in the correct position and the column and
5) Erection of temporary bracing commences to provide stability for the entire structure during the
construction phase.
6) The columns for the first and second frames are erected. Any temporary bracings installed should
7) Scaffolding is to be provided to allow workers to weld the connections. These connections include
8) Side columns that have been erected are joined together through the installation of side rails.
9) Installation of permanent cross bracings from column to column begins on the braced bays. The
column base plate installation is a critical phase as the other erection works cannot begin until the
CIVE4106 Page 28 of 39
Group 1
7.3.3 Rafters
1) After the columns are secured and checked for verticality, installation of the braced bay rafters
commences.
3) Scaffolding is erected to allow workers to carry out the rafter-rafter and column-rafter
connections.
4) Mobile cranes to be used to erect first rafter into position. Other suitable methods taking into
account the weight and size of rafter may be opted for to ease construction.
CIVE4106 Page 29 of 39
Group 1
5) Bolting and welding of the rafter to column connection is done according to the design
specifications.
6) Installation the purlins as per design requirements will tie together the rafters.
7) Cross bracings for the specific braced bay to be installed as laid out in the design scheme.
8) All temporary bracings and side rails have to be installed first before the rafter. This is because the
9) Only when all the connection bolts are tightened and temporary bracings, bracings purlins as well
10) Once all the components have been installed, the frame alignment should be checked to make
CIVE4106 Page 30 of 39
Group 1
11) After this, then only can the bolts and bracings be tightened.
7.3.4 Bays
1) The bay adjacent to the braced bay will be erected next following the same sequence as before.
The remaining frames will be erected bay by bay whilst providing the necessary temporary bracings
2) Once the installation of secondary framing elements of the braced bay has finished as well as the
plumbing and squaring of the bay; then only can wall and roof panelling start.
CIVE4106 Page 31 of 39
Group 1
3) Temporary erection bracing is to be provided and only removed when panelling has been
completed. This is because before completion of the roof and wall panelling, the structure cannot be
7.3.5 Panels
1) Cladding/sheeting to proceed immediately after erection of the main frame finishes. However,
before panel installation can commence, the side rails and purlins have to be checked to ensure that
2) Installation of the roof panels is typically done after the wall panelling. Both sides of the roof are
3) An insulation sheeting will be sandwiched between the roof panels. The roof sheeting installation
is to proceed after the insulation sheeting is done to avoid damage to the structural steelwork due
3) Temporary supports provided will be removed after the roof panel installation.
Figure 7.6: Installation of roof and wall panels Figure 7.7: Insulated panel
CIVE4106 Page 32 of 39
Group 1
Various problems may arise throughout the construction phase and therefore, these problems need
to be identified beforehand and proper measures should be taken to mitigate or eliminate the risk of
these problems. Listed below are some of the problems classified that may occur during
construction.
1) In the case where the structure is left standing without the necessary precautions like temporary
bracings for prolonged periods of time, the members of the frame may get damaged especially the
purlins due to excessive vibrations resulting from wind forces. Henceforth, the roof sheeting must be
installed immediately after completing the insulation sheeting for the roof.
2) Possibility of formwork collapse that may injure surrounding workers as well as damaging the
existing structure. Thus, experienced engineers should handle the design of the formwork including
3) During the roof panelling sequence, the roof panels should not be utilised as walking platforms.
This is because the panels are not able to withstand the workers weight when working at edges.
Consequently, suitable waking platforms should be provided for the workers to do work and the
4) The freestanding frames are subjected to significant stresses due to self-weight and wind even
though the partially erected structure is not withstanding the full design load yet. Therefore,
erection and installation of temporary bracings and purlins should be carried out to provide stability
5) The quality of weld on-site may be influenced by several factors; requiring protection from poor
weather, provision of access areas and the need to test the strength and capacity of the weld by the
CIVE4106 Page 33 of 39
Group 1
structural engineer before proceeding works can start. These issues need to be taken into account
6) Overloading the structure or insufficient erection of temporary bracings may cause structural
failure during erection. Hence, proper and accurate erection drawings should be done for each stage
of the construction phase and should be adhered to strictly. Only the most up to date ‘Issued for
7) When the pre-fabricated elements are transported to site during construction, the materials may
be broken, lost or exposed to various deformations during loading and unloading. To overcome this
issue, orderly loading onto the truck should be performed whereby the elements are properly
fastened and secured tightly on the transportation vehicle. In line with this, the materials should be
handled with care and stored appropriately avoiding interference with site traffic and direct sunlight.
8. Foundation Loads
Generally, the loadings experienced by the roof will be transferred onto the rafters
connecting the roof and subsequently onto the upper floor columns. The cross bracings in the
structure transfer the wind loads directly onto the connecting columns and an assumption that no
axial forces are applied to the connecting beams was made. The column then transmits the loads
The rails distribute the wind load acting on the side of the building to the longitudinal
beams. The longitudinal beams distribute the lateral load to the bracings which could be tension or
compression. In turn, the bracings transfer the loads directly to the foundations of the building.
CIVE4106 Page 34 of 39
Group 1
The rails distribute the transverse wind loads to the frames. The frames achieve lateral
stability from the stiffness of the joints as well as the bending resistance of the members.
Vertical loads are distributed to the frames using purlins. The frame transfers the vertical
loads to the columns using the stiffness of the frame. The columns transfer the loads to the
foundation.
Hence, there will be a total of 15 frames to be erected for the aquatics centre. The foundation loads
for the frames have been obtained from SAP 2000. As the structure is symmetrical, it is known that
the 1st frame has the same foundation load as the 15th frame. However, as only the first frame of the
structure was modelled in SAP 2000, the loadings applied onto the column and then onto the
foundation was assumed to be the same for all the foundations. This is because the foundation load
As such, the external columns were all designed based on this load. Loading combinations in
accordance with EC2 were calculated for the columns as soon as the amount of dead, live and wind
load was determined. Doing so, the foundation loads for the columns can be found
Table 8.1 and 8.2 below shows the summarised loads for the frames.
CIVE4106 Page 35 of 39
Group 1
9. Sustainability
Steel is an incredibly efficient material for sustainable construction.
a) Steel utilization is most cost- effective in comparison with different materials; additionally,
b) Steel can provide strong and lightweight structures with as little material as possible
d) It is relatively smooth and quiet easy to erect and requires few site deliveries.
e) It can be reused over and over again in a recycled process without losing its properties as a
building material
f) Steel framed buildings are easily adaptable and light- weight, as a result avoiding the need to
Several measures are taken in our design to help achieve our aims:
CIVE4106 Page 36 of 39
Group 1
from recycled steel is the type of steel used in roofing systems and its life span can extend even
more with coatings and galvanic-protection techniques, while having low maintenance costs. The
client can recycle it at the end of its performance life. Its installation has less construction waste,
Furthermore, the main material used is aluminium sheeting which is 100% recyclable, which
will help recover some of the initial financial investment in the material used, and cut on any cost
spent in removal of material at the end of the building life and also save on resources.
into several sections and prefabricating parts accordingly to avoid any delay in construction. We
designed a very cost efficient method to increase the construction speed and reduce
disarrangement on site as much as possible. The construction process involves lifting and placing of
In our structure, bolted connections were used as much as possible to ease the process of
making changes in the future if needed. Hence, the demount-ability aspect of the project has been
taken into account. On top of that, a preference towards the hiring of supplier and contractors with
sustainable approaches was adopted to satisfy the green credential of the structure.
having natural ventilation systems which would reduce our operational to construction energy ratio
to 3:1 in just 30 years life span compared to an air conditioned building which would dominate by
CIVE4106 Page 37 of 39
Group 1
1) Rainwater is collected from the roof drains and is stored in rainwater tanks to be used for
2) Only during hot days will the air conditioning be used and is to be installed only in the
offices, which are placed on one side of the building. However, windows are available to
provide natural ventilation during days with good weather and night operations.
3) External Thermal Insulation Composite System that is very durable and cost effective to
4) To help in the reduction of electricity usage, ventilation vents are installed all around the
building in the wall cladding to utilize fresh air to allow air movement.
5) Due to its energy consumption, modern lighting is extra efficient when compared to
6) Insulation boards of 25mm thick are added in walls to reduce energy losses.
7) Roof surfaces must have high emissivity ratings to allow solar energy and heat to dissipate
quickly.
8) Heat from solar radiation entering is reflected and cold air is trapped inside through
installing small windows. Whilst, allowing light to pass through, options vary from expensive
9) To avoid wastage of electricity in areas that are not in use, motion sensors are installed in
the offices.
10) Live load accounted for on the roof for maintenance allows safe installation and fixing of
solar panels. Since their own weight is very small around (0.15kN) per square meters, they
11) Incorporation of photovoltaic glass which converts light into electricity further reducing
energy consumption. PV glass also offers thermal and sound insulation and filters 99% of
harmful UV radiation.
CIVE4106 Page 38 of 39
Group 1
12) Use of light dimmers which allow the light intensity to be adjusted. Low brightness
10. References
5) Steelconstruction.info. (2018). Allowing for the effects of deformed frame geometry. [online]
Available at:
https://www.steelconstruction.info/Allowing_for_the_effects_of_deformed_frame_geometry
[Accessed 9 Dec. 2018].
7) Kristen M. Lechner (2009), Load Paths in a Braced Frame Steel Building, Available at:
http://www.personal.psu.edu/kml5016/blogs/kristen_lechners_eportfolio/Technical%20Description.pd
f [Accessed 20 November 2018.]
CIVE4106 Page 39 of 39