You are on page 1of 1

1376 SMe Mining engineering handbook

pillar recovery operations and could provide competent muck- was still taught as a preferred method of backfilling in some
ing floors, thereby eliminating the need for timber floors. In mining schools until the late 1960s.
1961, with financial support from the two aforementioned
mining companies, Canada Cement Lafarge Ltd. began a Advantages and Disadvantages
comprehensive study to develop cemented fill technology that Although it has generally been superseded by other meth-
was completed in 1970 with the publication of their findings ods, there are still situations where dry placement of fill has
(Weaver and Luka 1970). advantages over other systems. For example, if a mine does
Pneumatic stowing was introduced in Polish coal mines not have a processing plant on site to provide mill tailings,
in the 1920s and soon afterward adopted in other coal min- other fill options must be considered. Such fills could include
ing areas of Europe. In North America, the use of pneumatic (1) natural surface sands (glacial till in North America, natu-
stowing was promoted by the U.S. Bureau of Mines in the ral dune sands in Australia); (2) open-cut overburden, specifi-
1960s and 1970s but has not generally been adopted. The cally quarried surface rock, or even rock generated in local
method was tested at the Sullivan mine in British Columbia civil works; and (3) underground development waste. Dry fill
(Canada) in the late-1960s and later used in uranium mines is also the preferred option in evaporite and gypsum mines
in Grants, New Mexico (United States), and in gold mines in where the ore or host rock is readily dissolved in water, or in
South Africa. mines in arid locations where water is scarce.
The concept of thickened tailings, developed by Professor Dry placement of fill has two main disadvantages. First,
Robinsky of the University of Toronto and first applied at the it has a relatively low density as placed, which means it can
Kidd Creek mine in Timmins, Ontario (Canada), in the mid- undergo significant compression before it reaches its optimum
1970s, was extended by the late Dave Landriault and others at density to provide stope wall support to prevent spalling of
INCO Metals in the 1980s and later at Golder Paste Technology stope walls and minimize stope wall convergence. Second,
Ltd. to become paste fill when used for backfill underground. depending on stope configuration, it may be difficult to place
In 1975, pump-pack was developed by the British using broken dry fill close to the roof of the opening across the full span of
coal and bentonite, which was a thixotropic material and pumped the stope roof.
like a toothpaste but set like a low-strength concrete (Schmidt et
al. 1976). Paste fill was developed independently in Germany at Transport and Placement of Dry Fill
the Bad Grund mine in the early 1980s (Jewell 2006). The first consideration, as with all types of backfill, is the
“Flowable fill” has been used in recent years by, among means of transport of the dry fill underground. The most effi-
others, the Office of Surface Mining Reclamation and cient means for transport of sand- or gravel-sized particles is
Enforcement (OSMRE) of the U.S. Department of the Interior a borehole from the surface. Selection of the size of the bore-
to remotely backfill near-surface abandoned mines—especially hole depends on two considerations: the required through-
coal mines—that represent a subsidence hazard. Flowable fill put in metric tons per hour, and the size distribution of the
refers to a cementitious slurry consisting of a mixture of fine particles. For coarse material such as gravel, the particle size
aggregate or filler, water, and cementitious material(s) that is will govern, because the diameter of the borehole should, as
used primarily as a backfill in lieu of compacted earth. This a general but not necessarily universally applicable rule, be
mixture is capable of filling all voids in irregular excavations a minimum of three to six times the maximum particle size
and hard-to-reach places (such as under and around pipes), is of the gravel in order to avoid hang-ups. For finer material,
self-leveling, and hardens in a matter of a few hours without the governing concern is the required throughput. In general,
the need for compaction in layers. boreholes with diameters of 150 mm or 200 mm (6 or 8 in.)
will be sufficient for most purposes. However, using this size
TyPeS of BACkfill of pipe, one must never let the pipe fill and possibly bridge,
As indicated in the history section, the different materials as it may plug.
that have been used to backfill mine openings include the The most common method of transporting dry fill to the
following: workings is by haulage vehicles. In conventional, older mines,
this usually meant railcars, which would dump the fill into a
• Dry sand and rock fill
fill raise. More recently, haulage trucks have been used and
• Uncemented hydraulic backfill
belt conveyors are also being used for sand, gravel, or rock.
• Cemented hydraulic backfill
All of these placement methods require good access to the
• Cemented rock fill
workings that need to be filled.
• Paste fill
Another important consideration with dry placement of
• Pneumatic fill
granular fill is the method used to place and compact the fill
• Flowable fill
within the stope. Historically, placement was done by hand,
In subsequent sections of this chapter, each of these alterna- which is slow and costly. If the area to be filled is accessible
tives will be discussed. For each, the method of placement, to mobile equipment, spreading and compaction could be
drainage requirements, if any, equipment requirements, pipe accomplished by means of a hydraulic ram and blade mounted
wear, and other relevant design and operating topics are on a haulage truck or load-haul-dump (LHD) vehicle. (The
considered. blade is pushed laterally against the fill pile by the hydrau-
lic ram to compact it.) Another placement and compaction
Dry Sand and Rock fill method that has been tried is a high-speed throwing belt, the
Dry placement of stope fill materials is often the simplest main disadvantage of which is the limited distance that the fill
method of fill placement and has a long history. In metal travels beyond the discharge point.
mines in North America and Australia that used cut-and-fill or In the case of rock fill, placement is not generally a prob-
square-set stoping, this method dominated until the 1950s and lem if dumping is from the top of the working. Because of

You might also like