ID Task Mode Task Name Duration Start Finish Predecessors Resource Names
1 Special Events Phase 1.5 11 days Tue 10/16/12 Tue 10/30/12
2 Merge latest code from trunk 1 day Tue 10/16/12 Tue 10/16/12
3 Code-freeze 1 day Thu 10/25/12 Thu 10/25/12
4 Go-live 1 day Tue 10/30/12 Tue 10/30/12
5
6 Special Events Phase 2 11 days? Fri 10/12/12 Fri 10/26/12
7
8 Merge latest code from trunk 1 day Fri 10/26/12 Fri 10/26/12 3 Clement
9
10 Release 1 (Be able to capture online donations for candidate & misc code cleanup) 5 days? Fri 10/12/12 Thu 10/18/12
11 Fundraising Page templates (by Program Group and Participant Type) 0.5 days Fri 10/12/12 Fri 10/12/12
12 Alterian Setup 0.5 days Fri 10/12/12 Fri 10/12/12 Clement
13 Create fundraising pages for existing participants (MWOY candidates) 1 day Fri 10/12/12 Fri 10/12/12 Clement
14 GL Map setup for MWOY 1 day Fri 10/12/12 Fri 10/12/12 Naren
15 Team Membership rules (configured at the Program Group level to define how fundraising teams 2 days Fri 10/12/12 Mon 10/15/12
should behave) by team type/ sub team type
25 Option to join a fundraising team when registering a participant in C360 0.25 days Fri 10/12/12 Fri 10/12/12 Siarhei
26 Why does fundraising detail in the fundraising tab in team details section need to be locked down? 0.5 days Fri 10/12/12 Fri 10/12/12
27 More code cleanup goes here 1 day? Fri 10/12/12 Fri 10/12/12
28 QA Functional testing 5 days Fri 10/12/12 Thu 10/18/12
29
30 Release 2 (Shopping cart admin) 10 days Fri 10/12/12 Thu 10/25/12
Page 1 of 4
Special Events Project Plan
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names
44 JSP coding 10 days Fri 10/12/12 Thu 10/25/12 Amrish
45 Wireframe updates 5 days Fri 10/12/12 Thu 10/18/12 Lulu
46 Etools changes to reflect new widget configurations 3 days Fri 10/12/12 Tue 10/16/12
47 Services 2 days Fri 10/12/12 Mon 10/15/12 Amrish
48 Flex 3 days Fri 10/12/12 Tue 10/16/12 Andriy
49 Fundraising Page widgets/components 5 days Fri 10/12/12 Thu 10/18/12
50 shopping cart 5 days Fri 10/12/12 Thu 10/18/12
51 JSP coding 5 days Fri 10/12/12 Thu 10/18/12 Amrish
52 Donation 5 days? Fri 10/12/12 Thu 10/18/12
53 Ecommerce DB Design for Shopping cart 1 day? Fri 10/12/12 Fri 10/12/12
54 Add shopping cart to Donation Page 5 days Fri 10/12/12 Thu 10/18/12 Naren
55 Thank you message for donation + product purchase (should be one message) 2 days Fri 10/12/12 Mon 10/15/12
56 Services 2 days Fri 10/12/12 Mon 10/15/12 Clement
57 QA Functional testing 5 days Fri 10/12/12 Thu 10/18/12
58
59 Release 4 (Offline funds) 5 days Fri 10/12/12 Thu 10/18/12
60 Offline funds capture 2 days Fri 10/12/12 Mon 10/15/12
61 Add new offline fund types for MWOY and Regatta 1 day Fri 10/12/12 Fri 10/12/12
62 Stored Proc 1 day Fri 10/12/12 Fri 10/12/12 Vijay
63 Link offline fund entry to fundraising plan line item type 2 days Fri 10/12/12 Mon 10/15/12
64 DB Design 0.5 days Fri 10/12/12 Fri 10/12/12 Osman
65 Services 2 days Fri 10/12/12 Mon 10/15/12 Clement
66 Flex 2 days Fri 10/12/12 Mon 10/15/12 Clement
67 Eligible amount rules for offline funds 5 days Fri 10/12/12 Thu 10/18/12
68 DB Design 0.5 days Fri 10/12/12 Fri 10/12/12 Osman
69 Assess Impact on data grids, reports 1 day Fri 10/12/12 Fri 10/12/12 Ajay
70 Services 5 days Fri 10/12/12 Thu 10/18/12 Naren
71 Stored Procs 5 days Fri 10/12/12 Thu 10/18/12 Vijay
72 Report queries 5 days Fri 10/12/12 Thu 10/18/12 Ajay
73 Event Adoption 5 days Fri 10/12/12 Thu 10/18/12
74 Add Donation Button Enable Date, Donation Button Disable Date 1 day Fri 10/12/12 Fri 10/12/12
75 DB Design 0.5 days Fri 10/12/12 Fri 10/12/12 Osman
76 Wireframe 1 day Fri 10/12/12 Fri 10/12/12 Lulu
77 Flex 1 day Fri 10/12/12 Fri 10/12/12 Clement
78 Services 1 day Fri 10/12/12 Fri 10/12/12 Clement
79 Add Funds Eligibility Start Date, Funds Eligibility End Date 5 days Fri 10/12/12 Thu 10/18/12
80 DB Design 0.5 days Fri 10/12/12 Fri 10/12/12 Osman
81 Assess Impact on data grids, reports 1 day Fri 10/12/12 Fri 10/12/12 Ajay
82 Wireframe 1 day Fri 10/12/12 Fri 10/12/12 Lulu
83 Flex 1 day Fri 10/12/12 Fri 10/12/12 Clement
84 Services 1 day Fri 10/12/12 Fri 10/12/12 Clement
85 Stored Procs 5 days Fri 10/12/12 Thu 10/18/12 Vijay
86 Report queries 5 days Fri 10/12/12 Thu 10/18/12 Ajay
87 Add an option to create Event Fundraising Page 2 days Fri 10/12/12 Mon 10/15/12
88 DB Design 0.5 days Fri 10/12/12 Fri 10/12/12 Osman
89 Wireframe 1 day Fri 10/12/12 Fri 10/12/12 Lulu
90 Services 2 days Fri 10/12/12 Mon 10/15/12 Naren
91 Sponsorship 2 days Fri 10/12/12 Mon 10/15/12
92 Capture sponsorship at the participant level 2 days Fri 10/12/12 Mon 10/15/12
93 DB Design 1 day Fri 10/12/12 Fri 10/12/12 Osman
94 Flex 2 days Fri 10/12/12 Mon 10/15/12 Andriy
95 Services 2 days Fri 10/12/12 Mon 10/15/12 Naren
96 QA Functional testing 5 days Fri 10/12/12 Thu 10/18/12
Page 2 of 4
Special Events Project Plan
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names
97
98 Release 5 (Event Fundraising) 5 days? Fri 10/12/12 Thu 10/18/12
99 Create event fundraising pages for existing adopted Events 1 day Fri 10/12/12 Fri 10/12/12 Clement
100 Determine funds booking at event level 1 day? Fri 10/12/12 Fri 10/12/12
101 Offline fund entry at event level 1 day? Fri 10/12/12 Fri 10/12/12
102 DB Design 0.5 days Fri 10/12/12 Fri 10/12/12 Osman
103 Allow donors to credit a shopping cart item purchase (table tickets) to a participant (candidate) 0.5 days Fri 10/12/12 Fri 10/12/12
Page 3 of 4
Special Events Project Plan
15 Team Membership rules (configured at the Program Group level to define how fundraising teams should behave) by team type/ sub team type
• Rule 1: Can participant be on another team?
• Rule 2: Number of team member types allowed
• Rule 3: Minimum number of members required
31 DB Design
• Products -> Product Category
• Bundle -> Bundle Category
• Bundle can be part of another Bundle
40 Fundraising Page Widget configuration
by Program Group, Event Member Role Type