Professional Documents
Culture Documents
1 Q/IP/NCR/183/001-15
Jan 14B12030 14B12030
2 Q/IP/NCR/184/001-15
Jan 14B12030 14B12030
14B12030 (LV
4 Q/IP/NCR/186/01-15Jan 14B12030 Winding)
9 Q/IP/NCR/191/02-15
Feb 14B12030 14B12030
10 Q/IP/NCR/192/02-15
Feb 14B12030 14B12030
15 Q/IP/NCR/197/02-15
Feb 14B12031 14B12031
16 Q/IP/NCR/198/02-15
Feb 14B12013 14B12013
17 Q/IP/NCR/199/02-15
Feb 14B12031 14B12031
18 Q/IP/NCR/200/02-15
Feb 14B12031 14B12031
19 Q/IP/NCR/201/02-15
Feb 14B12031 14B12031
20 Q/IP/NCR/202/02-15
Feb 14B12032 14B12032
21 Q/IP/NCR/203/02-15
Feb 14B12031 14B12031
22 Q/IP/NCR/204/02-15
Feb 14B12031 14B12031
23 Q/IP/NCR/205/02-15
Feb 14B12031 14B12031
NCR
24 Q/IP/NCR206/02-15
Cancelle NCR Cancelled NCR Cancelled
d
NCR
25 Cancelle NCR Cancelled NCR Cancelled
Q/IP/NCR/207/02-15d
26 Q/IP/NCR/208/02-15
March 14B12031 14B12031
14B12032& 14B12032&
27 Q/IP/NCR/209/03-15
March 15B01002 15B01002
13B07259(ICT
28 Q/IP/NCR/210/03-15
March 13B07259 Repair)
14B12031
29 Q/IP/NCR/211/03-15
March 14B12031 APTRANSCO
14B12031
30 Q/IP/NCR/212/03-15
March 14B12031 APTRANSCO
15B01004 /5th
31 Q/IP/NCR/213/03-15
March 15B01004 Unit [LV
Wdg]
15B01002
32 Q/IP/NCR/214/03-15
March 15B01002 APTRANSCO
14B12032,
33 March 14B12032,15B010
Q/IP/NCR/215/03-15 15B01002,15B0
02, 15B01003 1003
14B12031
34 Q/IP/NCR/216/03-15
March 14B12031 APTRANSCO
36 Q/IP/NCR/218/03-15
March 13B07332 13B12332
15B01002
37 Q/IP/NCR/219/03-15
March 15B01002 APTRANSCO
38 Q/IP/NCR/220/03-15
March 15B01003 15B01003
40 Q/IP/NCR/222/03-15
March 15B01007 15B01007
41 Q/IP/NCR/223/03-15
March 15B01005 15B01005
14B12026(Tech
42 Q/IP/NCR/224/04-15
April 14B12026 no Power)
14B12026 &
43 Q/IP/NCR/225/04-15
April 14B12026 14B12027(Tech
no Power)
14B12026 &
14B12026,
44 Q/IP/NCR/226/04-15
April 14B12027(Tech
14B12027 no Power)
14B12026 &
14B12026,
45 Q/IP/NCR/227/04-15
April 14B12027(Tech
14B12027 no Power)
46 Q/IP/NCR/228/04-15
April 14B12031 14B12031
47 Q/IP/NCR/229/04-15
April 14B12032 14B12032
13B07259(ICT
48 Q/IP/NCR/230/04-15
April 13B07259 Repair)
14B12031, 32,
Q/IP/NCR/232/ 15B01002,03,04,0 APTRANSCO All
50 April
04-15 Units
5,06,07,08
14B12026,14B120
Q/IP/NCR/234/
52 May 27,14B12028,14B1 Techno Power
05-15 2029
TECHNO Power
53 Q/IP/NCR/235/05-15
May 14B12028 14B12028
APTRANCO
54 Q/IP/NCR/236/05-15
May 14B12032 14B12032
( 2nd Unit)
TSTRANSCO
55 Q/IP/NCR/237/05-15
May 15B05075 15B05075
( 3rd Unit)
APTRANCO
56 Q/IP/NCR/238/05-15
May 14B12032 14B12032
( 2nd Unit)
M/s UPPTCL
57 Q/IP/NCR/239/06-15
June 15B02011 15B02011
M/s TSTRANSCO
58 Q/IP/NCR/240/06-15
June 15B06076 (15B06076) 4th
Unit
59 Q/IP/NCR/241/06-15
June 14B12029 14B12029
60 Q/IP/NCR/242/06-15
June 15B05075 15B05075
14B12026,14B120
61 Q/IP/NCR/243/06-15
June 27,14B12028,14B1 14B12026,27,28
,29
2029
14B12026,14B120
62 Q/IP/NCR/244/06-15
June 27,14B12028,14B1 14B12026,27,28
,29
2029
63 Q/IP/NCR/245/06-15
June 13B07259 13B07259(ICT)
64 Q/IP/NCR/246/06-15
June 13B07259 13B07259 (ICT)
65 Q/IP/NCR/247/06-15
June 15B02011 15B02011
66 Q/IP/NCR/248/06-15
June 15B04009 15B04009
67 Q/IP/NCR/249/06-15
June 15B01007 15B01007
68 Q/IP/NCR/250/06-15
June 15B04009 15B04009
69 Q/IP/NCR/251/06-15
June 15B04009 15B04009
70 Q/IP/NCR/252/06-15
June 15B04009 15B04009
71 Q/IP/NCR/253/06-15
June 15B04009 15B04009
72 Q/IP/NCR/254/06-15
June 15B04009 15B04009
73 Q/IP/NCR/255/06-15
June 15B04009 15B04009
14B12026,14B120
74 Q/IP/NCR/256/06-15
June 27,14B12028,14B1 14B12026-29
2029
14B12026,14B120
75 Q/IP/NCR/257/06-15
June 27,14B12028,14B1 14B12026-29
2029
76 Q/IP/NCR/258/06-15
June 14B12030 14B12030
77 Q/IP/NCR/259/06-15
June 14B12030 14B12030
14B12028,14B120
78 Q/IP/NCR/260/06-15
June 14B12028,29
29
79 Q/IP/NCR/261/06-15
June 14B12030 14B12030
Q/IP/NCR/262/
80 June 15B04009 15B04009
06-15
81 Q/IP/NCR/263/06-15
June 15B04009 15B04009
82 Q/IP/NCR/264/06-15
June 15B06077 15B06077
UPPTCL,
83 Q/IP/NCR/265/06-15
June 15B02011 15B02011
84 Q/IP/NCR/266/06-15
June 15B01007 AP-8, 15B01007
3 Q/IP/NCR/267/06-15
June 14B12030 14B12030
86 Q/IP/NCR/268/06-15
June 15B01007 AP-8, 15B01007
Techno Power,
87 Q/IP/NCR/269/06-15
June 14B12029 14B12029
14B12030
88 Q/IP/NCR/270/06-15
June 14B12030 Bhushan
14B12019
89 Q/IP/NCR/271/07-15
July 14B12019 ( M/s Niger )
TATA Power
90 Q/IP/NCR/272/07-15
July 15B04009 15B04009
15B02011
91 Q/IP/NCR/273/07-15
JULY 15B02011 ( M/s Upptcl)
M/s Niger 30
92 Q/IP/NCR/274/07-15
JULY 14B12020 MVA 2nd unit
93 Q/IP/NCR/275/07-15
JULY 14B12030 14B12030
94 Q/IP/NCR/276/07-15
JULY 14B12030 14B12030
14B12026,14B120
95 Q/IP/NCR/277/07-15
JULY M/s TECHNO
27
96 Q/IP/NCR/278/07-15
JULY 15B04009 15B04009
UPPTCL
97 Q/IP/NCR/279/07-15
JULY 15B02011 15B02011
NCR
Q/IP/NCR/280/ Cancelle
98 NCR Cancelled NCR Cancelled
07-15 d
15B04009
101 Q/IP/NCR/281/07-15
JULY 15B04009 ( M/s TATA
POWER)
UPPTCL
102 Q/IP/NCR/282/07-15
JULY 15B02011 15B02011
UPPTCL
101 Q/IP/NCR/283/07-15
JULY 15B02011 15B02011
15B04009
102 Q/IP/NCR/284/07-15
JULY 15B04009 ( M/s TATA
POWER)
103 Q/IP/NCR/285/07-15
JULY 14B12019 14B12019
Bhushan Steel
104 Q/IP/NCR/286/07-15
JULY 14B12030 14B12030
TSTRANSCO
105 Q/IP/NCR/287/07-15
JULY 15B06076 15B06076
M/s Niger
106 Q/IP/NCR/288/07-15
JULY 14B12019 14B12019
M/s Niger,
107 Q/IP/NCR/289/07-15
JULY 14B12020 14B12020
M/s Niger,
108 Q/IP/NCR/290/07-15
JULY 14B12021 14B12021
M/s TS Transco
109 Q/IP/NCR/291/07-15
JULY 15B05074 15B05074
111 Q/IP/NCR/293/07-15
JULY 14B12019 14B12019
112 Q/IP/NCR/294/07-15
JULY 14B12020 14B12020
113 Q/IP/NCR/295/07-15
JULY 14B12021 14B12021
TATA Power
115 Q/IP/NCR/297/07-15
JULY 15B04009 15B04009
14B12034 M/s
Skipper Tap
116 Q/IP/NCR/298/07-15
JULY 14B12034 Winding
Cylinder
(3 Nos)
14B12019;20;21
14B12019,14B120 ( M/s NIGER
117 Q/IP/NCR/299/07-15
JULY 20,14B12021 Winding Coil
( HV;LV;TV)
Niger, 63
118 Q/IP/NCR/300/07-15
JULY 14B12016 MVA,unit 2 U,
TV winding
Niger, 63
119 Q/IP/NCR/301/07-15
JULY 14B12016 MVA,unit 2 V,
TV winding
Niger, 63
120 Q/IP/NCR/302/07-15
JULY 14B12016 MVA,unit 2 W,
TV winding
14B12034,
121 Q/IP/NCR/303/07-15
JULY 14B12034 Skipper Unit 1
14B12015 M/s
122 Q/IP/NCR/304/07-15
JULY 14B12015 Niger 63 MVA
14B12034
123 Aug 14B12034 Skipper
Q/IP/NCR/305/08-15
14B12015 M/s
124 Aug 14B12015 Niger 63 MVA
Q/IP/NCR/306/08-15
14B12017, M/s
125 Q/IP/NCR/307/08-15
Aug 14B12017 Niger
14B12018, M/s
126 Q/IP/NCR/308/08-15
Aug 14B12018 Niger
127 Q/IP/NCR/309/08-15
Aug 14B12019 14B12019
Niger 40 MVA,
128 Q/IP/NCR/310/08-15
Aug 14B12017 Unit 1 V phase
14B12015,14B120 14B12015,14B1
129 Q/IP/NCR/311/08-15
Aug 16 2016
15B06076, TSTRANSCO ,
4 Q/IP/NCR/312/08-15
Aug 15B06077 15B06077
UPPTCL,
131 Q/IP/NCR/313/08-15
Aug 15B02011 15B02011
UPPTCL,
132 Q/IP/NCR/314/08-15
Aug 15B02011 15B02011
UPPTCL,
133 Q/IP/NCR/315/08-15
Aug 15B02011 15B02011
UPPTCL,
134 Aug 15B02011 15B02011
Q/IP/NCR/316/08-15
UPPTCL,
135 Q/IP/NCR/317/08-15
Aug 15B02011 15B02011
Niger 63 MVA ,
136 Q/IP/NCR/318/08-15
Aug 14B12016 Unit 2
Skipper Unit 1,
137 Q/IP/NCR/319/08-15
Aug 14B12034 14B12034
Niger 63 MVA
138 Q/IP/NCR/320/08-15
Aug 14B12015 unit 1 14B12015
139 Q/IP/NCR/321/08-15
Aug 15B02011 15B02011
140 Q/IP/NCR/322/08-15
Aug 14B12034 14B12034
14B12018, 40
141 Q/IP/NCR/323/08-15
Aug 14B12018 MVA , LV Coil W
phase Unit 2
142 Q/IP/NCR/324/08-15
Aug 15B05047 15B05047
143 Q/IP/NCR/325/08-15
Aug 14B12015 M/s Niger
144 Q/IP/NCR/326/08-15
Aug 14B12016 M/s Niger
M/s TATA
145 Q/IP/NCR/327/08-15
Aug 15B04009 POWER
M/s TATA
146 Q/IP/NCR/328/08-15
Aug 15B04009 POWER
Testing
147 Q/IP/NCR/329/08-15
Aug 15B05047 Transformer
148 Q/IP/NCR/330/08-15
Aug 15B02011 UPPTCL
Testing
149 Q/IP/NCR/331/08-15
Aug 15B05047 Transformer
150 Q/IP/NCR/332/08-15
Aug 15B02011 UPPTCL
151 Q/IP/NCR/333/08-15
Aug 14B12015 M/s Niger
Testing
152 Q/IP/NCR/334/08-15
Aug 15B05047 Transformer
M/s UPPTCL
153 Q/IP/NCR/335/08-15
Aug 15B02011 15B02011
M/s UPPTCL
154 Q/IP/NCR/336/08-15
Aug 15B02011 15B02011
M/s UPPTCL
155 Q/IP/NCR/337/08-15
Aug 15B02011 15B02011
14B12034--HV
14B12034 V Phase &
156 Q/IP/NCR/338/08-15
Aug 14B12035 14B12035 HV V
& U Phase
Testing
157 Q/IP/NCR/339/08-15
Aug 15B05047 Transformer
14B12034 Skipper, HV
158 Q/IP/NCR/340/08-15
Aug 14B12035 winding
159 Q/IP/NCR/341/08-15
Aug 14B12034 Skipper
Testing
160 Q/IP/NCR/342/08-15
Aug 15B05047 Transformer
Testing
161 Q/IP/NCR/343/08-15
Aug 15B05047 Transformer
162 Q/IP/NCR/344/08-15
Aug 14B12034 Skipper 1st Unit
163 Q/IP/NCR/345/08-15
Aug 14B12034 Skipper
Testing
164 Q/IP/NCR/346/08-15
Aug 15B05047 Transformer
165 Q/IP/NCR/347/08-15
Aug 30624/R PGCIL
166 Q/IP/NCR/348/08-15
Aug 14B12035 Skipper unit 2
167 Q/IP/NCR/349/08-15
Aug 14B12035 Skipper unit 2
Niger 63 MVA
168 Q/IP/NCR/350/08-15
Aug 14B12015 unit 1 14B12015
Niger 63 MVA
170 Q/IP/NCR/351/08-15
Aug 14B12016 unit-2
Testing
171 Q/IP/NCR/352/08-15
Aug 15B05047 Transformer
Q/IP/NCR/353/ Testing
172 Sep 15B05047
09-15 Transformer
Q/IP/NCR/354/
173 Sep 14B12035 Skipper Unit 2
09-15
Q/IP/NCR/355/
174 Sep 15B01001 PGCIL, ICT
09-15
Q/IP/NCR/356/
175 Sep 15B05053 Essel
09-15
M/s ESSEL
Q/IP/NCR/359/
178 Sep 15B05053 (500MVA/400K
09-15 VA) (Unit-1)
Q/IP/NCR/360/ Niger 40 MVA,
179 Sep 14B12017
09-15 Unit 1 V phase
Q/IP/NCR/362/
181 Sep 15B02011 M/s UPPTCL
09-15
M/s ESSEL
Q/IP/NCR/363/
182 Sep 15B05053 (500MVA/400K
09-15 VA) (Unit-1)
M/s ESSEL
Q/IP/NCR/364/
183 Sep 15B05053 (500MVA/400K
09-15 V) (Unit-1)
Q/IP/NCR/366/
185 Sep 15B01001 PGCIL ICT
09-15
Q/IP/NCR/369/
188 Sep 15B02011 M/s UPPTCL
09-15
Q/IP/NCR/370/
189 Sep 15B05049 M/s Essel
09-15
Q/IP/NCR/371/
190 Sep 15B05049 M/s Essel
09-15
Q/IP/NCR/373/
192 Sep 15B05049 M/s Essel
09-15
Q/IP/NCR/376/ Testing
195 Sep 15B05047
08-15 Transformer
Q/IP/NCR/379/
198 Sep 15B01001 PGCIL Sapre ICT
09-15
Q/IP/NCR/380/
199 Sep 15B01001 PGCIL Spare ICT
09-15
Q/IP/NCR/381/
200 Sep 15B05053 Essel Power
09-15
Testing
201 Q/IP/NCR/382/09-15
Sep 15B05047 Transformer
Testing
202 Q/IP/NCR/383/09-15
Sep 15B05047 Transformer
203 Q/IP/NCR/384/10-15
Oct 15B05053 Essel ICT
204 Q/IP/NCR/385/10-15
Oct 15B10081 APTRANSCO
205 Q/IP/NCR/386/10-15
Oct 15B05053 Essel ICT
15B05058
206 Q/IP/NCR/387/10-15
Oct 15B05058 M/s ESSEL ( ICT )
M/s Aptransco
207 Q/IP/NCR/388/10-15
Oct 15B10083 ( 100MVA /
220KV )
PGCIL
208 Q/IP/NCR/389/11-15
Nov 15B09059 Srikakulam Unit
1
PGCIL
209 Q/IP/NCR/390/11-15
Nov 15B09059 Srikakulam Unit
1
PGCIL
210 Q/IP/NCR/391/11-15
Nov 15B09059 Srikakulam Unit
1
Testing
211 Q/IP/NCR/392/11-15
Nov 15B05047 Transformer
212 Q/IP/NCR/393/11-15
Nov 15B10081 Aptransco
213 Q/IP/NCR/394/11-15
Nov -- --
M/s TATA
6 Q/IP/NCR/395/11-15
Nov 15B04009 POWER
M/s TATA
215 Q/IP/NCR/396/11-15
Nov 15B04009 POWER
M/s TATA
7 Q/IP/NCR/397/11-15
Nov 15B04009 POWER
217 Q/IP/NCR/398/11-15
Nov 15B010076 Unnao
218 Q/IP/NCR/399/11-15
Nov 15B01001 PGCIL
219 Q/IP/NCR/400/11-15
Nov 15B12080 CESC
220 Q/IP/NCR/401/11-15
Nov 15B12080 CESC
222 Q/IP/NCR/403/12-15
Dec 15B10083 APTRANSCO
223 Q/IP/NCR/404/12-15
Dec 15B06057 Essel Reactor
224 Q/IP/NCR/405/12-15
Dec Prototype Reactor Unnao
225 Q/IP/NCR/406/12-15
Dec 15B05051 Essel 200 MVA
226 Q/IP/NCR/407/12-15
Dec 15B05051 Essel 200 MVA
PGCIL
227 Q/IP/NCR/408/12-15
Dec 15B09060 Srikakulam Unit-
2
M/s ESSEL
228 Q/IP/NCR/409/12-15
Dec 15B05050 (125MVAR
229 Q/IP/NCR/410/12-15
Dec 15B05049 Essel 125 MVAr
230 Q/IP/NCR/411/12-15
Dec 15B05050 M/s ESSEL
PGCIL
231 Q/IP/NCR/412/12-15
Dec 15B09061 Srikakulam
NCR MONITORING SHEET-INPROCESS QUALITY
Crack was observed at ride over, refer NCR Winding Minor Production Winding
Variation found in filling strips, refer NCR Winding Minor Production Winding
Dimension varion observed in insulation Active Part Assembly Minor Design Design
component
Lifting arrangement is not at appropriate Active Part Assembly Minor Design Design
place, refer NCR
Step block foul with core lamination Core Building Minor SCM SCM
Wraps assembly not found as per Drawing, Winding/Insulation Minor Production Winding
found variatin of around 10 mm
Assembly of Tensile Belt , refer NCR Core Building Minor Design Design
Final
Radiator fins found damaged, Refer NCR Tanking Minor Production Assembly
Step block foul with core lamination Core Building Minor Design Design
Earhing rod not matching with earthing boss Core Building Minor Design Design
Final
Winding Height found more by 19 mm Final Assembly Minor Production Assembly
Item No. 1,2,3,5,6,7 mismatch on flitch plate Core Building Minor SCM SCM
Insulation
ID Rider Block for MV WDG not as per DRG Winding Minor Production Winding
Axial Spacer pasted Wrongly for TV Coil Winding Minor Production Winding
M/s Aptransco ( 2nd Unit )
To be fit in top and bottom frame, as std. Core Building Minor Design Design
practice, Refer NCR
NCR NCR
NCR Cancelled NCR Cancelled Cancelled NCR Cancelled Cancelled
NCR NCR
NCR Cancelled NCR Cancelled Cancelled NCR Cancelled Cancelled
Core &
Refer NCR Core Building Major Production Active part
Core &
Refer NCR Core Building Minor Production Active part
FOS reading shuld match the ambient Winding Major Production Winding
temprature reading
Refer NCR Winding Minor Design Design
Same Work order coil should be assembled Winding Minor Production Winding
in same job
Coil should be completely Oil impgrenated Winding VPD Major Production Processing
during VPD process
Coil should be completely Oil impgrenated Winding VPD Major Production Processing
during VPD process
Core &
Refer NCR Core Building Minor Production Active part
Core &
Vidya Wire is not approved and used. CCA Major Production Active part
Tensile Belt should be regular in shop. Core Assembly Minor Design Design
Vertical Shaft to be matched with DM box. Final Assembly Major Design Design
CCA locking cup Dimension mismatch, refer Tanking Major SCM SCM
NCR
Final
Refer NCR Tanking Minor Production Assembly
Final
CT Turret found Not Blank Tanking Major Production Assembly
Final
Different Make hardware used Tanking Minor Production Assembly
OD Ride Over Not As per Drawing Winding process Major Production Winding
Winding Cylinder should not be damaged Winding process Major Production Winding
Final
Allocated HV, LV , BR not mounted on Job. Tanking Major Production Assembly
LV Axial Strip Height not As per drawing Winding Major Production Winding
Ride over are required without damage and Coil Winding Major Production Winding
sharp edges.
Status
Adequate clearnace should be maintained Final Assembly Changed Design Design
between tank wall and OLTC leads. By Design
Correct Size of vacuum Blocks should be Final Assembly Minor Design Design
called in drawing.
As per drawing ID ride over found without Winding Process Major Production Winding
sharp edges/ damages.
LV ID ride over are required without damge Coil Winding Major Production Winding
and sharp edges.
Correct Size of vacuum Block Required. Final Assembly Minor Design Design
Final
Black Phospate hardware used out side. Tanking Minor Production Assembly
Final
POLG Clamp Found Broken. Tanking Minor Production Assembly
Earthing Boss not fixed in Coller bank Tanking Minor Design Design
assembly.
Bare Copper Conductor observed with Sharp
Marks/Dents & Voids ( Shakti Winding Major SCM SCM
Insulated Wires Pvt Ltd )
Variation in length found in LV rider Block Winding Major Design Design
(OD)
Dimension Variation found in Clamping Core Building Minor Design Design
Insulation ( Lower )
Winding Cylinder should be chamferred , not
damaged /de laminated, should be without Winding Major Production Winding
sharp edges.
Two Drawing No. Obseved with different Tanking Major Design Design
dimenssions having same revision status.
Two Drawing No. Obseved with different Tanking Major Design Design
dimenssions having same revision status.
12*40 mm Dia. Ho;e required in upper clamp Core Building Major Design Design
while 12*24 mm dia is observed.
NCR NCR
NCR Cancelled NCR Cancelled Cancelled NCR Cancelled Cancelled
Width of Tensile belt given in drawing is 120 Core Building Major Design Design
mm while required is 50 mm.
Winding Cylinder should be chamferred , not
damaged /de laminated, should be without Winding Major Production Winding
sharp edges.
POLG Clamp Should not be broken while Final Assembly Minor SCM SCM
tightening.
Base Feet drawing Item no. 2, (Bolt M 24) Core Building Minor SCM SCM
missing.
Base Feet drawing Item no. 2, (Bolt M 24) Core Building Minor SCM SCM
Bluing was missing.
Base Feet drawing Item no. 2, (Bolt M 24) Core Building Minor SCM SCM
Bluing was missing.
Winding Cylinder and top insulation ring Winding Major Production Winding
should not be buldged.
Wimdow width dimension should be within Core Building Minor SCM SCM
tolerance
Winding Cylinder should be over lap as per Winding Major Production Winding
drawing 75 mm, should not be delaminated.
Winding Cylinder should be over lap as per Winding Major Production Winding
drawing 75 mm, should not be delaminated.
Winding Cylinder should be over lap as per Winding Major Production Winding
drawing 75 mm, should not be delaminated.
Pitch of the strip pasted, has to be equal in Winding Major Design Design
all segments.
Winding Copper Conductor should not be
twisted and damaged., After VPD process it Winding Major Production Winding
was found twisted.
Upper Clamp insulation Not Found As per Core Building Minor SCM SCM
Drwaing, Dimension 355 found 335
Bluning Was missing in Bolt M24 , Item no. 2 Core Building Minor SCM SCM
Bluning Was missing in Bolt M24 , Item no. 2 Core Building Minor SCM SCM
Winding Cylinder should be over lap as per Winding Major Production Winding
drawing, not damage, not delaminated.
Status
Valve schedule Plate not matching with exact Final Assembly Changed Design Design
location of valve in main unit. By Design
Paint Should not be peeled off, Paint Peeled Final Assembly Minor SCM SCM
off observed in turrets and CT munting Pipe.
Inspection window cover fouling with Plate Final Assembly Minor Design Design
stiffner.
Non Approved Make Hardware used (PANKAJ Final Assembly Minor SCM SCM
INTL)
Final Paint Observed at Bottom header Pipe Final Assembly Minor SCM SCM
Instead of oil resistant paint.
Movable Flap should cover th opening of 150 Final Assembly Minor SCM SCM
NB pipe in PRD
Lamination Dimenssion in step no. 22 should Core Building Major SCM SCM
be as per drawing.
Base Feet drawing Item no. 2, (Bolt M 24) Core Building Minor SCM SCM
Bluing was missing.
Base Feet drawing Item no. 2, (Bolt M 24) Core Building Minor SCM SCM
Bluing was missing.
FOS Routing found not as per drg for HV Coil Winding Major Production Winding
Radiator Sr. no. 11, Fin found damaged Tanking Minor SCM SCM
TBEA Logo Plate mounting Fixture found Tanking Minor SCM SCM
damaged. Logo plate unable to be fixed.
POLG found Missing in OLTC Conservator Final Assembly Minor SCM SCM
Oil Impegrination should be done througth Winding VPD Major Production Processing
the coil.
OD Rider Block between the Disc has to be Winding Major Production Winding
fitted covering the force application section.
Tap Winding, Block Alignment not done, Winding Major Production Winding
Central Lead Exit Hole not done.
W phase , STB top block found loose, not Tanking Major Production Winding
completely clamped after pressing.
Oil Impegrination should be done througth Winding VPD Major Production Processing
the coil.
Windign turns found loose and conductor Winding Major Production Winding
found bare.
Heavy Rust Observed in CRGO Laminations Core Building Minor SCM SCM
Deepankar
Done Closed Not Required Porwal &
Team
Deepankar
Done Closed Not Required Porwal &
Team
Deepankar
Done Closed Not Required Porwal &
Team
Deepankar
Done Closed Not Required Porwal &
Team
Tarun Sharma
Done Closed Not Required & Team
Deepankar
Done Closed Not Required Porwal &
Team
Bhargav
Done Closed Not Required Pandya &
Team
Jagdish Shukla
Done Closed Not Required & Team
Deepankar
Done Closed Not Required Porwal &
Team
Deepankar
Done Closed Not Required Porwal &
Team
Jagdish Shukla
Done Closed Not Required & Team
Tarun Sharma
Done Closed Received & Team
Tarun Sharma
Done Closed Not Required & Team
Deepankar
Done Closed Not Required Porwal &
Team
Deepankar
Done Closed Not Required Porwal &
Team
Deepankar
Done Closed Not Required Porwal &
Team
NCR NCR Cancelled NCR Cancelled NCR Cancelled NCR Cancelled NCR Cancelled
Cancelled
NCR NCR Cancelled NCR Cancelled NCR Cancelled NCR Cancelled NCR Cancelled
Cancelled
Bhargav
Arjun
Done Closed Received Pandya &
Chundawat Team
Bhargav
Done Closed Not Required Pandya &
Team
Deepankar
Done Closed Received Porwal &
Team
Done Closed Not Required Design Team
Deepankar
Done Closed Not Required Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Not Required Porwal &
Team
Deepankar
Done Closed Not Required Porwal &
Team
Deepankar
Done Closed Not Required Porwal &
Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Deepankar
Done Closed Not Required Porwal &
Team
Gouranga
Done Closed Received Biswas &
Team
Shantanu
Done Closed Received Design Team
Tiwari
Deepankar
Done Closed Not Required Porwal &
Team
Gouranga
Done Closed Received Biswas &
Team
Bhargav
Done Closed Not Required Pandya &
Team
Tarun Sharma
Done Closed Not Required & Team
Done Closed Not Required Design Team
Bhargav
Done Closed Received Pandya &
Team
Anil Ram
Done Closed Received Design Team
Prasad
Tarun Sharma
Done Closed Received & Team
Jagdish Shukla
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Jagdish Shukla
Done Closed Not Required & Team
Deepankar
Done Closed Not Required Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Jagdish Shukla
Done Closed Received & Team
Gouranga
Done Closed Received Biswas &
Team
Done Closed Not Required Design Team
Jagdish Shukla
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Jagdish Shukla
Done Closed Received & Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Jagdish Shukla
Done Closed Not Required & Team
Done Closed Not Received Design Team
Jagdish Shukla
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Bhargav
Done Closed Not Required Pandya &
Team
Jagdish Shukla
Done Closed Not Required & Team
Jagdish Shukla
Done Closed Not Required & Team
Jagdish Shukla
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Received & Team
Shantanu
Done Closed Received Design Team
Tiwari
Ashish Shukla
Done Closed Received Vipin Tiwari & Team
Ashish Shukla
Done Closed Received Vipin Tiwari & Team
Jagdish Shukla
Done Closed Not Received & Team
Shantanu
Done Closed Received Design Team
Tiwari
Anil Ram
Done Closed Received Design Team
Prasad
NCR NCR Cancelled NCR Cancelled NCR Cancelled NCR Cancelled NCR Cancelled NCR Cancelled
Cancelled
Shantanu
Done Closed Received Design Team
Tiwari
Shantanu
Done Closed Received Design Team
Tiwari
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Bhargav
Done Closed Not Required Pandya &
Team
Bhargav
Done Closed Not Required Pandya &
Team
Bhargav
Done Closed Not Required Pandya &
Team
Tarun Sharma
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Received & Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Shantanu
Done Closed Received Design Team
Tiwari
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Open Received Porwal &
Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Bhargav
Done Closed Not Required Pandya &
Team
Deepankar
Done Closed Received Porwal &
Team
Bhargav
Done Closed Not Required Pandya &
Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Bhargav
Done Closed Received Pandya &
Team
Deepankar
Done Closed Not Required Porwal &
Team
Tarun Sharma
Done Closed Received & Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Open Received Porwal &
Team
Tarun Sharma
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Tarun Sharma
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Tarun Sharma
Done Closed Not Required & Team
Bhargav
Done Closed Not Required Pandya &
Team
Deepankar
Done Closed Received Porwal &
Team
Jagdish Shukla
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Gouranga
Done Closed Received Biswas &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Jagdish Shukla
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Tarun Sharma
Done Closed Received & Team
Jagdish Shukla
Done Closed Received & Team
Deepankar
Done Closed Received Porwal &
Team
Gouranga
Done Closed Received Biswas &
Team
Deepankar
Done Closed Received Porwal &
Team
Tarun Sharma
Done Open Not Required & Team
Bhargav
Done Closed Not Required Pandya &
Team
Deepankar
Done Open Received Porwal &
Team
Disputed NCR,
Bhargav It is not
Done Open Not Received Pandya & Accepted By
Team Addressee
Department
Bhargav
Done Closed Not Required Pandya &
Team
Deepankar
Done Open Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Jagdish Shukla
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Jagdish Shukla
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Jagdish Shukla
Done Closed Not Required & Team
Deepankar
Done Closed Received Porwal &
Team
Bhargav
Done Closed Not Required Pandya &
Team
Tarun Sharma
Done Open Not Required & Team
Bhargav
Done Closed Received Pandya &
Team
Bhargav
Done Closed Not Required Pandya &
Team
Tarun Sharma
Done Open Received & Team
Done Closed Received Vipin Tiwari Design Team
Tarun Sharma
Done Open Not Required & Team
Jagdish Shukla
Done Closed Received & Team
Deepankar
Done Closed Not Required Porwal &
Team
Gouranga
Done Closed Received Biswas &
Team
Gouranga
Done Closed Received Biswas &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Deepankar
Done Closed Received Porwal &
Team
Gouranga
Done Closed Received Biswas &
Team
Deepankar
Done Closed Received Porwal &
Team
Gouranga
Done Open Received Biswas &
Team
Deepankar
Done Closed Received Porwal &
Team
Gouranga
Done Open Not Required Biswas &
Team
Deepankar
Done Closed Received Porwal &
Team
Tarun Sharma
Done Closed Not Required & Team
Jagdish Shukla
Done Closed Not Required & Team
Done Closed Not Received Design Team
Jagdish Shukla
Done Closed Not Required & Team
Jagdish Shukla
Done Closed Not Required & Team
Jagdish Shukla
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Tarun Sharma
Done Closed Not Required & Team
Chandrashekh
Done Open Not Required ar Goswami &
Team
Jagdish Shukla
Done Closed Not Received & Team
Tarun Sharma
Done Closed Received & Team
Chandrashekh
Done Open Not Required ar Goswami &
Team
Jagdish Shukla
Done Closed Not Received & Team
Gouranga
Done Closed Received Biswas &
Team
Total Open Major Minor
Sr. No. Name of the Department Closed NCR
NCRs NCRs NCRs NCRs
4 SCM 42 38 4 10 32
5 Design 44 44 0 21 23
6 VPD/Processing 11 9 2 10 1
7 IED 2 0 2 0 2
10 0 0 0
10 0 0 0
21 0 0 0
10 0 0 0
0 0 0 0
1 1 Jan 1,2 , 3
2 2 Jan 1
3 3 Feb 1
4 4 Feb 1
5 5 Feb 4
7 7 Feb 5
8 8 Feb 13B07308
9 9 Feb 13B07306
10 10 Feb 13B07306
11 11 Feb 13B07313
12 12 Feb 13B07311
14 14 Feb 13B07307
15 15 Feb 13B07308
13B07333
16 16 Feb 13B07334
13B07334
17 17 Feb 13B07335
13B07336
18 18 Mar 13B07337
19 19 Mar 13B07333
20 20 Mar 13B07300
21 21 Mar 13B07309
22 22 APR 13B07339
13B07309,13B07
37 Q/Q/NCR/37/4-14 MAY 310
Q/IQ/NCR/47/06-
47 JUNE 13B07304
14
13B07312,
48 Q/IQ/NCR/48/06-14 JUNE 13B07318
Q/IP/NCR/61/07-
61 JULY 13B07307
14
Q/IP/NCR/62/07-
62 JULY 13B07308
14
Q/IP/NCR/63/07-
63 JULY 13B07310
14
Q/IP/NCR/71/07-
71 JULY 13B07308
14
72 Q/IP/NCR/72/07-14 JULY 13B07310
13B07312 and
77 Q/IP/NCR/77/07-14 JULY 318
13B07312 and
78 Q/IP/NCR/78/08-14 August 318
13B02139
101 Q/IP/NCR/101/08-14 Sep. &12B08122
Q/IP/NCR/109/08
109 -14 Sept. 13B07321
13B07331,
110 Q/IP/NCR/110/09-14 Sept. 13B07319
Q/IP/NCR/115/09
115 Sept. 13B07303
-15
Q/IP/NCR/116/09
116 Sept. 13B07326
-16
Q/IP/NCR/117/09
117 Sept. Storage system
-17
13B07332
136 Q/IP/NCR/136/10-14 OCT &14B07002
Common for
147 Q/IP/NCR/147/10-14 OCT PGCIL jobs
14B12011-
177 Q/IP/NCR/177/12-14 Dec 14B12014
Rust observed in the stress cap and found Active Part Major
improper tag welding Assembly
4 no. holes in marshalling box mounted
on job order no. 13B07340 found not
blanked. During the transportation in Tanking Minor
rainy season watter may accumlate
inside.
2 no. holes in marshalling box mounted
on job order no. 13B07340 found not
blanked. During the transportation in Tanking Minor
rainy season watter may accumlate
inside.
2 no. holes in marshalling box mounted
on job order no. 13B07340 found not
blanked. During the transportation in Tanking Minor
rainy season watter may accumlate
inside.
2 no. holes in marshalling box mounted
on job order no. 13B07340 found not
blanked. During the transportation in Tanking Minor
rainy season watter may accumlate
inside.
Expansion bellow mounting found
inadequate in job order no.13B07302 4
no. mounting rods are not used and Tanking Minor
whole pipe weight was coming on
expansion bellow.
Active Part
Bolster Plate found defective Minor
Assembly
Damaged DOF washer in Regulating Coil Winding Minor
Active Part
Core Cheese packet found Damage Assembly Minor
Active Part
Hardware Found Rusty, Refer NCR Minor
Assembly
Gaskets
(Acrylic) used at wall flanges. Dispatch Minor
Tanking Minor
Marshalling Box Name Plate matter paint
peel off.
ZPP (Yellow) hardware used in
Marshalling box support, also in main Tanking Minor
tank., These hardware will catch rust at
site. As per PGCIL only hdg to be used.
Active Part
Core Cheese Packet Assembly Major
NCR Cancelled
2
1
2
3
5
6
7
8
Minor NCR 109
Major NCR 55
Major
Sr. No. Name of the Department Total NCRs Closed NCRs Open NCRs NCRs
Winding (Including
1 Insulation, Coil Clamping & 37 37 0 22
Coil Assembly)
4 SCM 35 35 0 7
5 Design 5 5 0 0
15 22 22
18 3 3
59 24 24
28 7 7
5 0 0
125 56 56
NCR MONITORING S
Essel 200
1 Q/IP/NCR/413/01-2016
Jan 15B05052 MVA , W
Phase, Unit 2
PGCIL
2 Q/IP/NCR/414/01-2016
Jan 15B09062 Srikakulam,
Tap Winding
Essel 80 MVAr
3 Q/IP/NCR/415/01-2016
Jan 15B06053 Core
Jan 15B09059 ,
5 Q/IP/NCR/417/01-2016 15B09060 Srikakulam ICT
6 Q/IP/NCR/418/01-2016
Jan 16B03001 Model ICT
Essel 200
MVA , W
7 Q/IP/NCR/419/01-2016
Jan 15B05052 Phase, Unit 2,
LV Coil, U
phase
8 Q/IP/NCR/420/01-2016
Jan 16B01003 Model ICT
9 Q/IP/NCR/421/01-2016
Jan 15B05052 Essel 200 MVA
10 Q/IP/NCR/422/01-2016
Jan 15B05048 Essel 500 MVA
11 Q/IP/NCR/423/01-2016
Jan 15B05053 Essel 500 MVA
12 Q/IP/NCR/424/01-2016
Jan 15B06054 Essel400
80 MVAr,
kV
13 Q/IP/NCR/425/01-2016
Jan 16B01003 Model ICT
14 Q/IP/NCR/426/01-2016
Jan 16B01003 Model ICT
15 Q/IP/NCR/427/01-2016
Jan 15B05052 Essel 200
16 Q/IP/NCR/428/01-2016
Jan 16B01003 Model ICT
17 Q/IP/NCR/429/01-2016
Jan 16B01003 Model ICT
Q/IP/NCR/430/0
18 Jan
1-2016
19 Jan
20 Jan
21 Jan
22 Jan
23 Jan
24 Jan
25 Jan
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
NCR MONITORING SHEET-INPROCESS QUALITY
Productio Winding
Fire Blanket not used while making Brzing Joint/deburring. Winding Major n
Core
CRGO Lamination found not as per design Major SCM SCM
Building
Vipin Deepankar
Porwal&
Tiwari Team
Deepankar
Shantanu Porwal&
Tiwari Team
Tarun
Vipin Sharma &
Tiwari Team
Jagdish
Vipin Shukla &
Tiwari Team
Jagdish
Vipin Shukla &
Tiwari Team
Tarun
Viral Bhatt Sharma &
Team
Deepankar
Viral Bhatt Porwal&
Team
Deepankar
Shantanu Porwal&
Tiwari Team
Deepankar
Viral Bhatt Porwal&
Team
Jagdish
Vipin Shukla &
Tiwari Team
Deepankar
Viral Bhatt Porwal&
Team
Tarun
Vipin Sharma &
Tiwari Team
Deepankar
Viral Bhatt Porwal&
Team
Viral Bhatt Design Team
Tarun
Viral Bhatt Sharma &
Team