CRONOGRAMA DE AVANCE DE OBRA GENERAL

TIEMPO DE PROGRAMACION
COMPONENTES DE OBRA PRESUPUESTO
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06
I.E.E. N° 30318
1 BLOQUE AB - YANAMUCLO 2,817,973.69 137,412.30 388,324.85 1,090,078.00 823,301.60 301,740.44 77,116.50
2 PATIO CIVICO - YANAMUCLO 118,342.86 43,847.83 74,495.03
3 LOSA DEPORTIVA - YANAMUCLO 246,273.73 163,992.07 62,148.05 20,133.61
4 CERCO PERIMETRICO - YANAMUCLO 692,120.57 252,404.97 258,647.85 107,737.37 73,330.38
5 MOBILIARIO Y EQUIPOS - YANAMUCLO 145,252.27 145,252.27
I.E.E. N° 30319
1 BLOQUE C - MARAVILCA 1,305,799.69 71,902.77 257,624.63 679,705.18 296,567.11
2 PATIO CIVICO - MARAVILCA 32,063.99 32,063.99
3 CERCO PERIMETRICO - MARAVILCA 195,852.06 72,277.91 59,623.68 54,153.14 9,797.33
4 MOBILIARIO Y EQUIPOS - MARAVILCA 154,916.47 154,916.47

MONTO TOTAL PRESUPUESTADO 5,708,595.33 209,315.07 721,861.30 2,168,961.09 1,757,048.78 525,779.00 325,630.09
INCIDENCIA DE AVANCE 100.00% 3.67% 12.65% 37.99% 30.78% 9.21% 5.70%