CALCULO DEL FLETE

OBRA :“CONSTRUCCION DE PUENTE CARROZABLE SOBRE EL RIO HUAMANZAÑA EN EL SECTOR SAN


CARLOS, DISTRITO DE CHAO - VIRU - LA LIBERTAD”

1- DATOS GENERALES

A-POR PESO

MATERIALES UNIDAD AFECTO IGV PESO.UNIT. PESO.TOTAL


FIERRO, CLAVOS, ETC. Kg 42,481.75 1.00 42,481.75
CEMENTO BL. 4,603.08 42.50 195,630.90
MADERA P2 13,592.77 1.50 20,389.16
TUBERIA DE AGUA M 35.00 3.00 105.00
PESO TOTAL 258,606.81

AGREGADOS UNIDAD AFECTO IGV kg/m3 en volquete PESO.TOTAL


PIEDRA CHANCADA m3 356.41 1,059.33 377,555.81
PIEDRA GRANDE DE 8" m3 163.75 1,059.33 173,465.29
ARENA GRUESA m3 191.25 889.83 170,179.99
PESO TOTAL 721,201.09

2. MOVILIZACION DE EQUIPOS

EQUIPO PESO (KG) Nº DE VIAJES TOTAL


RODILLO LISO V. 10,000.00 2.00 20,000.00
MOTONIVELADORA 8,800.00 2.00 17,600.00
RETROEXCAVADORA 11,000.00 2.00 22,000.00
MEZCLADORA 2,200.00 2.00 4,400.00
TOTAL 32,000.00 2.00 64,000.00

3- FLETE TERRESTRE

UNIDAD DE TRANSPORTE
UNIDAD QUE DA COMPROBANTE UNIDAD QUE NO DA COMPROBANTE
PESO TOTAL A MOVILIZAR 979,807.90
CAPACIDAD DEL CAMION ( M3 ) 10.00 CAPACIDAD DEL CAMION ( M3 )
COSTO POR VIAJE S/. 800.00 COSTO POR VIAJE S/.
CAPACIDAD DEL CAMION (KG) 10,000.00 CAPACIDAD DEL CAMION (KG)
FLETE POR KG 0.08

AFECTO IGV SIN IGV FLETE POR PESO =(Peso


FLETE POR PESO 78,384.63 Materialesl+Peso
movilizacion)
COSTO TOTAL FLETE TERR. 78,384.63
AGREGADOS UNIDAD AFECTO IGV
PIEDRA CHANCADA DE 1/2" m3 759.41
PIEDRA GRANDE DE 8" m3 101.34
PIEDRA MEDIANA m3 7.83
AFIRMADO m3 161.28
ARENA GRUESA m3 389.44
HORMIGON (PUESTO EN OBRA) m3 240.75
ARENA FINA m3 129.44
PESO TOTAL
PESO.UNIT. PESO.TOTAL
1.70 1,291.00
1.50 152.01
1.60 12.53
1.40 225.79
1.40 545.22
1.40 337.05
1.40 181.22