Professional Documents
Culture Documents
UNSWAGATI CIREBON
JOURNAL
ABSTARCT
Observation of conditions
and implementation in the
Jakarta-Cikampek II
Elevated Toll Road
construction project field
Technical drawings as
planned for the
construction of the
Jakarta-Cikampek II
Elevated Toll Road
Interviews with the
executors of the Jakarta-
Cikampek II Elevated Toll
Road project
3 | Journal of Construction Management Design of Jakarta-Cikampek II Elevated Toll Road Project
(P.186-P.187)
In the preparation of this thesis there :𝐵𝑜𝑟𝑒𝑑 𝑃𝑖𝑙𝑒 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 =
are 2 types of data that have been 0.24𝜋 𝑥 𝐷2 𝑥 ℎ
described in the previous section. The
Detail :
data will be analyzed by several
methods, first the data is analyzed to h = Depth plan (from existing surface to
determine the work network, then end bearing)
some data is analyzed to get the cost D = Bored Pile Diameter
and time for effective and efficient From the specification above we get that :
project implementation. Some of h = 44 m
these methods are, CPM (Critical D = 1200 mm = 1.2 m
Path Method), Bar Chart, S-Curve. So,
𝐵𝑜𝑟𝑒𝑑 𝑃𝑖𝑙𝑒 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 =
3. Analysis and Discussion
0.25𝜋 𝑥 1.22 𝑥 44
3.1. Job Volume Calculation
= 49. 73 𝑚3
In this calculation the bored pile structure After the volume of the structure is
will be the sample. generated, then the number of volumes
can be determined for the sub-work in the
In the bored pile foundation there are
bored pile work such as :
several sub-jobs, therefore the calculation
of volume becomes very important so Drilling Volume
that a construction implementer can
Volume of drilling work equals to h
determine the amount of material,
(depth) of bored pile from existing, and
manpower and tools needed to complete
h = 44 m’
the bored pile foundation work.
PRELIMINARY WORK
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 − 𝐵𝑎𝑟 𝑆𝑡𝑒𝑒𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 SECTION.1 Trafic protection and treatment
SECTION.2 Praparation for Direction
120 - 15.00 1.00
1.00
Ls
Ls
SECTION.4 Mobilization & Demobilization 1.00 Ls
SECTION.5 Measurment & Bowplank 260.00 m'
SOIL WORKS
DRAINAGE WORK
= 49.23 𝑚3 SECTION.1 Deck Drain
+ Installing PVC Pipe
240.00
240.00
m'
m'
SECTION.2 RCP 120.00 m'
+ Installing RCP D= 800 mm 120 120.00 m'
the next step is determining the volume + Drilling Work P.186 D=1,2 m
+ Drilling Work P.187 D=1,2 m
44.00
38.00
398.94
343.95
m3
m3
8 Point
8 Point
+ Re Bar Work Bored Pile P.186 ( 8 point) 41.10 31,650.82 Kg
+ Re Bar Work Bored Pile P.187 ( 8 point) 35.00 1.2 31,085.25 Kg
of material that needed to make concrete. + Concrete Cast Bored Pile P.186
+ Concrete Cast Bored Pile P.187
44.00
38.00
398.94
343.95
m3
m3
8 Point
8 Point
SECTION.2 Footing Work
Concrete grade that designed for bored + Preparatory work for Footing Work
+ Excavation for Footing P.186 13.4 3.00 7.4
1.00
297.48
Ls
m3
+ Excavation for Footing P.187 13.4 3.00 7.4 297.48 m3
Volume = W x L x H
= 7.4 x 13.4 x 3
= 297.48 m3
L = 11.4 m 1.B
Equipment coeff./M3
DUMP TRUCK
DumpCapacity
Truck unit needed = (Q1 x Coeff2)
= 1 : Q2 0.1108 Hour
3.31 m3
Unit 4 Truck
Bed V 28.00
COMPLEMENTARY
Equipment TOOLS
Efficiency Factor Fa 0.83
Loaded average speed v1 20.00 Km/h Disturbed by
Need small complementary tools :
Empty average speed v2 40.00 Km/h traffic jam
Productivitycoeff./M3
Equipment determines : EXCAVATOR = 1 : Q2 Q1 29.88 Hour
0.1108 M3/Hour
Dump Truck unit needed = (Q1 x Coeff2) 3.31 Unit 4 Truck
that exceed the dimensions of the pile cap - etc - Foreman f 1.00 Man
IV MANPOWER
Manpower Coefficient/M3 :
structure. This aims to make work space Productivity determines : EXCAVATOR
Digging Productivity/Day
- Worker =
=
(Tw x w) / Qt
Tw x Q1
Q1
Qt
29.88 M3/Hour
0.0669 Hour
209.16 M3/Day
Manpower needed
- Foreman == (Tw x f) / Qt 0.0335 Hour
- worker w 2.00 Man
for workers. Add width (W) = 2 m, and - Foreman f 1.00 Man
Manpower Coefficient/M3 :
II WORK METHOD
Workers are divided into several groups
Workers cut the D-diameter pole manually using a worker tool
The cut pile is lifted to the surface using a crane truck
From the data above, it is known that the
The truncated pile is loaded into the dump truck and then moved to
disposal at a distance L
- Bar Cutter = 4 Unit = 4 x Q1 Q1 796.80 Kg/Hour the work above is a bar cutter and bar
- Bar Bender = 4 Unit = 4 x Q2 Q2 796.80 Kg/Hour
- Bar Roller = 2 Unit = 2 x Q3' Q3 840.00 Kg/Hour
Equipment Coefficient
Equipment Coefficient
=
=
1 : Q1'
1 : Q2'
0.0050 Hour
0.0050 Hour
bender, as well as laborers in this case the
Equipment Coefficient = 1 : Q3' 0.0024 Hour
MAN POWER
Productivity determiner : Bar Bender
Productivity in Day = Tw x Q2
Q2
Qt
796.80 Kg/Hour
5577.60 Kg/Day
foreman, chief artisan, ironworker, and
Manpower required :
- Worker w 16.00 Man
- Tukang Besi
- Kepala Tukang
Ws
Wh
8.00 Man
4.00 Man
worker. So to determine the duration of
- Foreman f 1.00 Man
Manpower coeficient :
- Worker
- Tukang Besi
=
=
( Tw x w ) : Qt
( Tw x Ws ) : Qt
0.0201 Hour
0.0100 Hour
the data required about the value of
- Kepala Tukang = ( Tw x Wh ) : Qt 0.0050 Hour
- Foreman = ( Tw x f ) : Qt 0.0013 Hour
of tools and labor needed to complete the SECTION.3 Preparation for work platform
+ Clearing, Stripping, and Grubbing
+ Land filling and Compaction
120
120 0.40
10.00
10.00
1.00
1,200.00
480.00
Ls
m2
m3
Rp
Rp
19,644.99 Rp
36,794.46 Rp
23,573,988.00
17,661,339.87
SECTION.2 Excavation 0-2 m 240 1.50 1.50 540.00 m3 Rp 74,706.80 Rp 40,341,674.69
DRAINAGE WORK
NO COMPONENT
M'
NO COMPONENT UNIT COEFFICIENT UNIT PRICE (IDR) COST (IDR) + Barrier Formwork 624.00 m2 236,442.21 147,539,940.00
+ Concrete Cast Barrier Line A 20.93 m3 Rp 1,154,049.21 Rp 24,156,248.19
A MATERIAL
TOTAL COST OF MATERIAL + Concrete Cast Barrier Line B 20.93 m3 Rp 1,154,049.21 Rp 24,156,248.19
B MANPOWER
+ Curing Slab Line A 690.00 m2 Rp 7,468.96 Rp 5,153,584.13
1 labor MD 0.0777 IDR 85,500.00 IDR 6,647.23
+ Curing Slab Line B 690.00 m2 Rp 7,468.96 Rp 5,153,584.13
2 Foreman MD 0.0144 IDR 198,000.00 IDR 2,851.20
+ Curing Barrier Line A 312.00 m2 Rp 7,468.96 Rp 2,330,316.30
TOTAL COST OF MANPOWER IDR 9,498.43
+ Curing Barrier Line B 312.00 m2 Rp 7,468.96 Rp 2,330,316.30
C EQUIPMENT
1 Excavator Hour 0.1009 IDR 399,995.71 IDR 40,359.57 TOTAL Rp 9,225,389,351.49
2 Dump Truck Hour 0.7799 IDR 323,103.90 IDR 251,988.73 SECTION.7 AC-WC (0.04 cm)
3 Hoe + Tack Coat 441.00 liter 22,036.50 9,718,096.55
Ls 1.0000 IDR 10,000.00 IDR 10,000.00 856,693.51 99,307,911.79
4 Shovel,etc + AC-WC 115.92 ton
TOTAL COST OF EQUIPMENT IDR 302,348.30 TOTAL Rp 109,026,008.34
SECTION.8 FINISHING
D Total cost of Material, Manpower and Equipment ( A + B + C ) IDR 311,846.73 + Marking 360.00 M' Rp 344,301.52 Rp 123,948,547.42
E Overhead & profit ( 15% X D ) IDR 46,777.01 + Lighting (interval 20 m) 9.00 Point Rp 5,691,392.02 Rp 51,222,528.19
F Job unit price ( D + E ) IDR 358,623.74
+ Traffic Sign 4.00 Point Rp 1,638,835.89 Rp 6,555,343.56
TOTAL Rp 181,726,419.17
the CPM (Critical Path Method) has been Measurement & Bowplank
Site Office
A
B
-
A
2
18
3 SOIL WORK
described in the previous chapter. Site Clearing, Stripping & Grubbing C A 9
Land Filling & Compaction D B,C 1
Before forming a CPM diagram, what Excavation 0-2 m E A 2
4 BORED PILE FOUNDATION
3. Structure
4. Finishing
1 GENERAL WORK -
Traffic Protection and Treatment
Mob and Demob
2 PRELIMINARY WORK -
Measurement & Bowplank A - 2 Yes 0 0 2 2 0
Site Office B A 18 Yes 2 2 20 20 0
3 SOIL WORK 0
Site Clearing, Stripping & Grubbing C A 9 No 2 11 11 20 18
Land Filling & Compaction D B,C 1 Yes 20 20 21 21 0
Excavation 0-2 m E A 2 No 2 4 19 21 4
4 BORED PILE FOUNDATION
Drilling F D,E 10 Yes 21 21 31 31 0
Reinforcement Work G D,E 12 No 21 33 25 37 24
Material Removing H F 10 Yes 31 31 41 41 0
Concrete Structure I F,G 4 No 33 37 37 41 8
5 PILE CAP WORK 0
SSP Driving J H,I 4 Yes 41 41 45 45 0
Footing Excavation ( 2-4 m) K J 4 Yes 45 45 49 49 0
Pile Demolition L K 6 No 49 63 55 69 28
Reinforcement Work M K 20 Yes 49 49 69 69 0
Formwork Installation N L,M 2 Yes 69 69 71 71 0
Concrete Cast + Waiting Time O N 6 Yes 71 71 77 77 0
Curing P O 14 Yes 77 77 91 91 0
6 PIER WORK 0
Reinforcement Work Q O 10 No 77 87 87 97 20
Scaffolding + Climbing Platform Instl. R P 6 Yes 91 91 97 97 0
Formwork Installation S Q,R 6 Yes 97 97 103 103 0
Concrete Cast + Waiting Time T S 6 Yes 103 103 109 109 0
Curing U T 14 Yes 109 109 123 123 0
7 PIER HEAD 0
Shoring Installation V U 2 No 123 123 125 125 0
Formwork Installation W V 10 No 125 125 135 135 0
Sosrobahu Tool Installation X W 10 No 135 135 145 145 0
Reinforcement Work Y U 22 Yes 123 123 145 145 0
Concrete Cast + Waiting Time Z W,X,Y 6 Yes 145 145 151 151 0
Curing AA Z 14 Yes 151 151 165 165 0
Erection + Stresssing Tendon AC AA 2 Yes 165 165 167 167 0
Pedestal + Temporary Bearing Instl. AD AA 2 No 165 167 165 167 4
Uninstalling Formwork+Shoring AB AC,AD 7 Yes 167 167 174 174 0
8 STEEEL BOX GIRDER 0
SBG Mobilization AE AB 1 No 174 174 175 175 0
Erection AF AB 1 Yes 174 174 175 175 0
Diaphragm Installation AG AE,AF 6 No 175 198 181 204 46
9 SLAB 0
Reinforcement Work AH AE,AF 46 Yes 175 175 221 221 0
S-Form Installation AI AG 17 No 181 204 198 221 46
Deck Drain AJ AG 2 No 181 219 183 221 76
Concrete Structure AK AH,AI,AJ 3 Yes 221 221 224 224 0
Curing AL AK 7 Yes 224 224 231 231 0
Moving S-Form AM AL 2 No 231 242 233 244 22
10 BARRIER STURCTURE 0
Formwork Installation AN AL 2 Yes 231 231 233 233 0
Concrete Structure AO AN 3 Yes 233 233 236 236 0
Curing AP AO 7 Yes 236 236 243 243 0
11 DRAINAGE 0
2-Jul-18
9-Jul-18
1-Jan-18
8-Jan-18
4-Jun-18
5-Feb-18
2-Apr-18
9-Apr-18
3-Sep-18
1-Oct-18
8-Oct-18
16-Jul-18
23-Jul-18
30-Jul-18
6-Aug-18
5-Mar-18
15-Jan-18
22-Jan-18
29-Jan-18
7-May-18
11-Jun-18
18-Jun-18
25-Jun-18
12-Feb-18
19-Feb-18
26-Feb-18
16-Apr-18
23-Apr-18
30-Apr-18
10-Sep-18
17-Sep-18
24-Sep-18
15-Oct-18
22-Oct-18
13-Aug-18
20-Aug-18
27-Aug-18
12-Mar-18
19-Mar-18
26-Mar-18
14-May-18
21-May-18
28-May-18
1 GENERAL WORK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
Traffic Protection and Treatment 01-Jan-18 23-Oct-18
Mob and Demob 01-Jan-18 23-Oct-18
2 PRELIMINARY WORK -
Measurement & Bowplank A - 2.00 Yes 0 0 2 2 0 08-Jan-18 09-Jan-18
Site Office B A 18.00 Yes 2 2 20 20 0 10-Jan-18 30-Jan-18
3 SOIL WORK ` 0
Site Clearing, Stripping & Grubbing C A 9.00 No 2 11 11 20 18 10-Jan-18 19-Jan-18
Land Filling & Compaction D B,C 1.00 Yes 20 20 21 21 0 31-Jan-18 31-Jan-18
Excavation 0-2 m E A 2.00 No 2 4 19 21 4 10-Jan-18 11-Jan-18
4 BORED PILE FOUNDATION
Drilling F D,E 10.00 Yes 21 21 31 31 0 01-Feb-18 12-Feb-18
Reinforcement Work G D,E 12.00 No 21 33 25 37 24 01-Feb-18 14-Feb-18
Material Removing H F 10.00 Yes 31 31 41 41 0 13-Feb-18 23-Feb-18
Concrete Structure I F,G 4.00 No 33 37 37 41 8 15-Feb-18 19-Feb-18
5 PILE CAP WORK 0
SSP Driving J H,I 4.00 Yes 41 41 45 45 0 24-Feb-18 28-Feb-18
Footing Excavation ( 2-4 m) K J 4.00 Yes 45 45 49 49 0 01-Mar-18 05-Mar-18
Pile Demolition L K 6.00 No 49 63 55 69 28 06-Mar-18 12-Mar-18
Reinforcement Work M K 20.00 Yes 49 49 69 69 0 06-Mar-18 28-Mar-18
Formwork Installation N L,M 2.00 Yes 69 69 71 71 0 29-Mar-18 30-Mar-18
Concrete Cast + Waiting Time O N 6.00 Yes 71 71 77 77 0 31-Mar-18 06-Apr-18
Curing P O 14.00 Yes 77 77 91 91 0 07-Apr-18 23-Apr-18
6 PIER WORK 0
Reinforcement Work Q O 10.00 No 77 87 87 97 20 07-Apr-18 18-Apr-18
Scaffolding + Climbing Platform Instl. R P 6.00 Yes 91 91 97 97 0 24-Apr-18 30-Apr-18
Formwork Installation S Q,R 6.00 Yes 97 97 103 103 0 01-May-18 07-May-18
2. Gantt Chart
Concrete Cast + Waiting Time T S 6.00 Yes 103 103 109 109 0 08-May-18 14-May-18
Curing U T 14.00 Yes 109 109 123 123 0 15-May-18 30-May-18
7 PEKERJAAN PIER HEAD 0
Shoring Installation V U 2.00 No 123 123 125 125 0 31-May-18 01-Jun-18
Formwork Installation W V 10.00 No 125 125 135 135 0 02-Jun-18 13-Jun-18
Sosrobahu Tool Installation X W 10.00 No 135 135 145 145 0 14-Jun-18 25-Jun-18
Reinforcement Work Y U 22.00 Yes 123 123 145 145 0 31-May-18 25-Jun-18
Concrete Cast + Waiting Time Z W,X,Y 6.00 Yes 145 145 151 151 0 26-Jun-18 02-Jul-18
Curing AA Z 14.00 Yes 151 151 165 165 0 03-Jul-18 18-Jul-18
Erection + Stresssing Tendon AC AA 2.00 Yes 165 165 167 167 0 19-Jul-18 20-Jul-18
Pedestal + Temporary Bearing Instl. AD AA 2.00 No 165 167 165 167 4 19-Jul-18 20-Jul-18
Uninstalling Formwork+Shoring AB AC,AD 7.00 Yes 167 167 174 174 0 21-Jul-18 29-Jul-18
8 STEEEL BOX GIRDER 0
SBG Mobilization AE AB 1.00 No 174 174 175 175 0 30-Jul-18 30-Jul-18
Erection AF AB 1.00 Yes 174 174 175 175 0 30-Jul-18 30-Jul-18
Diaphragm Installation AG AE,AF 6.00 No 175 198 181 204 46 31-Jul-18 06-Aug-18
9 SLAB 0
Reinforcement Work AH AE,AF 46.00 Yes 175 175 221 221 0 31-Jul-18 21-Sep-18
S-Form Installation AI AG 17.00 No 181 204 198 221 46 07-Aug-18 26-Aug-18
Deck Drain AJ AG 2.00 No 181 219 183 221 76 07-Aug-18 08-Aug-18
Concrete Structure AK AH,AI,AJ 3.00 Yes 221 221 224 224 0 22-Sep-18 25-Sep-18
Curing AL AK 7.00 Yes 224 224 231 231 0 26-Sep-18 03-Oct-18
Moving S-Form AM AL 2.00 No 231 242 233 244 22 04-Oct-18 05-Oct-18
10 BARRIER STURCTURE 0
Formwork Installation AN AL 2.00 Yes 231 231 233 233 0 04-Oct-18 05-Oct-18
Concrete Structure AO AN 3.00 Yes 233 233 236 236 0 06-Oct-18 09-Oct-18
Curing AP AO 7.00 Yes 236 236 243 243 0 10-Oct-18 17-Oct-18
11 DRAINAGE 0
Excavation 0-2 m AQ AM 2.00 No 233 244 235 246 22 06-Oct-18 08-Oct-18
RC Pipe Installation AR AQ 2.00 No 235 246 237 288 62 09-Oct-18 10-Oct-18
12 FINISHING AS AP 5.00 Yes 243 243 248 248 0 18-Oct-18 23-Oct-18
Track Line Marking
AC-WC
Public Road Lighting
WEEKLY TOTAL DURATION 43
MASTER SCHEDULE
WEEKLY S-CURVE
CONCTRUCTION PROJECT OF JAKARTA - CIKAMPEK II ELEVATED TOLL ROAD
ZONE - 5 (P.186 - P.187)
2018
JANUARRY FEBRUARRY MARCH APRIL MAY JUNE JULLY AUGUST SEPTEMBER OKTOBER
4.964 1.227 1.936 0.497 1.915 1.472 18.111 3.666 1.815 0.831
PRECENTA
FINISHING
NO DESCRIPTION UNIT UNIT PRICE COEFFICIENT NOMINAL PRICE
GE (%)
SOIL WORKS
2-Jul-18
9-Jul-18
1-Jan-18
8-Jan-18
4-Jun-18
5-Feb-18
2-Apr-18
9-Apr-18
3-Sep-18
1-Oct-18
8-Oct-18
16-Jul-18
23-Jul-18
30-Jul-18
6-Aug-18
5-Mar-18
15-Jan-18
22-Jan-18
29-Jan-18
7-May-18
11-Jun-18
18-Jun-18
25-Jun-18
12-Feb-18
19-Feb-18
26-Feb-18
16-Apr-18
23-Apr-18
30-Apr-18
10-Sep-18
17-Sep-18
24-Sep-18
15-Oct-18
22-Oct-18
13-Aug-18
20-Aug-18
27-Aug-18
12-Mar-18
19-Mar-18
26-Mar-18
14-May-18
21-May-18
28-May-18
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
DRAINAGE WORK
STRUCTURAL WORK
1 GENERAL
PRELIMINARY WORK
1.1 Traffic Protection and Treatment Ls 2,831,710,274.00 1.00 Rp 2,831,710,274.00 8.37 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195 0.195
1.2 Mob & Demob Ls 3,001,500,000.00 1.00 Rp 3,001,500,000.00 8.87 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206 0.206
2 PRELIMINARY
2.1 Measurement & Bowplank m' 74,767.25 260.00 Rp 19,439,485.00 0.06 0.057
2.2 Site Office Ls 254,859,443.04 1.00 Rp 254,859,443.04 0.75 0.188 0.188 0.188 0.188
3 SOIL, EXCAVATION & DRILLING WORKS
3.1 Site Clearing, Stripping & Grubbing m2 19,644.99 1,200.00 Rp 23,573,988.00 0.07 0.035 0.035
3.2 Land Filling & Compaction m3 36,794.46 480.00 Rp 17,661,339.87 0.05 0.052
3.3 Excavation 0-2 M m3 74,706.80 540.00 Rp 40,341,674.69 0.12 0.060 0.060
3.4 Excavation 2-4 M m3 199,644.46 594.96 Rp 118,780,466.24 0.35 0.176 0.176
3.5 Drilling D1200 m' 151,479.37 656.60 Rp 99,461,355.93 0.29 0.098 0.098 0.098
3.6 Drilling Material Removing m3 358,623.74 742.90 Rp 266,420,141.00 0.79 0.394 0.394
3.7 SSP Driving Sheet 3,280,879.97 134.00 Rp 439,637,915.97 1.30 0.650 0.650
A. Budget Plan
4 REINFORCEMENT WORK
4. Conclusion
4.1 Reinforcement Bored Pile Kg 30,214.46 62,736.06 Rp 1,895,536,281.98 5.60 1.868 1.868 1.868
4.2 Reinforcement Pile Cap Kg 34,073.44 36,315.89 Rp 1,237,407,491.27 3.66 0.915 0.915 0.915 0.915
4.3 Reinforcement Pier Kg 37,678.99 23,184.95 Rp 873,585,333.61 2.58 0.861 0.861 0.861
4.4 Reinforcement Pier Head Kg 31,842.37 29,873.39 Rp 951,239,598.28 2.81 0.562 0.562 0.562 0.562 0.562
4.5 Reinforcement Slab Kg 33,637.66 196,941.05 Rp 6,624,635,226.83 19.59 3.264 3.264 3.264 3.264 3.264 3.264
4.6 Reinforcement Barrier Kg 29,873.77 46,571.57 Rp 1,391,268,489.21 4.11 2.057 2.057
DESCRIPTION
5 CONCRETE STRUCTURE
5.1 Concrete Structure f'c 30 Mpa (Bored Pile) m3 1,184,331.88 742.90 Rp 879,835,417.86 2.60 1.301 1.301
5.2 Concrete Structure f'c 30 Mpa (Pile Cap) m3 1,097,442.00 303.17 Rp 332,715,630.67 0.98 0.492 0.492
5.3 Concrete Structure f'c 30 Mpa (Pier) m3 1,278,901.13 156.60 Rp 200,270,417.46 0.59 0.296 0.296
5.4 Concrete Structure f'c 40 Mpa (Pier Head) m3 1,329,532.36 234.94 Rp 312,354,766.87 0.92 0.462 0.462
5.5 Concrete Structure f'c 40 Mpa (Slab) m3 1,324,126.83 497.17 Rp 658,321,390.58 1.95 0.973 0.973
5.6 Concrete Structure f'c 20 Mpa (Barrier) m3 1,154,049.21 41.86 Rp 48,312,496.38 0.14 0.071 0.071
6 DRAINAGE
6.1 Deck Drain m' 161,303.49 240.00 Rp 38,712,836.40 0.11 0.114
B. Schedulling Concept
6.2 Reinforcement Concrete Pipe D100 m' 1,223,987.37 120.00 Rp 146,878,484.76 0.43 0.434
7 SOSROBAHU ls 63,370,737.14 1.000 Rp 63,370,737.14 0.19 0.047 0.047 0.047 0.047
8 FORMWORK
8.1 Formwork Pile Cap m2 258,088.75 168.00 Rp 43,358,910.00 0.13 0.128
8.2 Alsina Climbing Form m2 203,459.89 213.59 Rp 43,456,305.29 0.13 0.064 0.064
8.3 Formwork Pier Head (Shoring) m2 187,630.08 279.73 Rp 52,485,761.86 0.16 0.052 0.052 0.052
NOMINAL PRICE
MONTHLY PROGRESS PLAN CUMULATIVE (%) 10.7876 15.3654 21.4427 26.6672 30.4505 35.0106 55.3204 85.5174 96.8866 100.00
185,591,321.16
81,577,002.56
WEEKLY CASHFLOW RP
135,656,052.88
268,429,569.86
211,157,907.64
199,370,913.64
864,370,126.28
800,655,265.52
928,602,790.30
414,865,243.99
507,554,218.82
448,163,985.70
445,007,925.70
654,724,651.04
594,630,918.69
428,273,103.35
428,273,103.35
147,777,992.15
168,084,205.53
257,519,414.26
237,213,200.88
137,077,992.15
647,767,623.07
343,399,226.49
359,241,910.78
341,746,656.83
497,924,040.26
293,255,375.59
137,077,992.15
171,332,856.44
141,897,552.88
831,290,297.49
613,778,627.44
181,405,077.69
308,112,725.10
282,454,205.91
281,032,266.64
1,373,783,044.95
6,125,609,816.36
6,234,364,308.64
1,429,322,619.90
1,309,803,579.90
1,239,761,924.02
1,239,761,924.02
1,160,450,992.78
the duration of the week is = 33 Weeks. Dawn Sri Handayani, Setiono, and
Winarto. Control of Material
So that it can be concluded that the Costs Method Variant Analysis on
duration of the project implementation Construction.
plan until completion is 295 days, 33 Setiawati, Dwi Novi. 2013. Analysis of
weeks, 10 months. Starting on January Productivity Heavy On Project