Professional Documents
Culture Documents
Sheath Strand
Grease
Unbonded PT tendon
Bonded PT components
Figure 1c: Bonded system before pouring concrete. Figure 1d: Components of PT
Courtesy of Freyssinet.
4 POST-TENSIONED CONCRETE FLOORS
Term Definition
Under an applied load, a prestressed element will bend, reducing the
built-in compression stresses; when the load is removed, the prestressing Device to lock the strand at a
force causes the element to return to its original condition, illustrating the Anchorage pre-determined tensile force, which induces
compressive stress in the concrete.
resilience of prestressed concrete. Furthermore, tests have shown that a
virtually unlimited number of such reversals of the loading can be carried Dead-end
An anchorage where no jacking takes place.
out without affecting the element’s ability to carry its working load or anchorage
impairing its ultimate load capacity. In other words prestressing endows the
element with a high degree of resistance to fatigue. Metal or plastic tube through which the strand is
Duct
passed for the bonded system.
If the tensile stress due to applied load is less than the prestress plus the tensile
Distance between the centroid of the concrete section
capacity of the concrete, the concrete will not crack in the tension zone. Eccentricity
and the centre of the strand.
However, depending on the environment it may be acceptable to have some
cracking. Even after an element has been loaded to beyond its working load, Live The anchorage at the jacking end of the strand. Both
and well towards its ultimate capacity, removal of the load results in closing of anchorage ends of the strand can be live.
the cracks and they will not reappear under working load.
Geometric shape of the tendon in elevation, often
Profile
parabolic.
There are two methods of applying prestress to a concrete member. These are:
¢¢ Post-tensioning – where the concrete is placed around sheaths or ducts Plastic extrusion moulded directly to the strand. A
Sheath layer of grease between the strand and the sheath
containing unstressed tendons. Once the concrete has gained sufficient
prevents bonding.
strength the tendons are stressed against the concrete and locked
off by special anchor grips, known as split wedges. In this system, all
Strands High strength steel reinforcement.
tendon forces are transmitted directly to the concrete. Since no stresses
are applied to the formwork, conventional formwork may be used.
¢¢ Pre-tensioning – where the concrete is placed around previously stressed Tendon One or more strands in a common duct or sheath.
tendons. As the concrete hardens, it grips the stressed tendons and
when it has obtained sufficient strength the tendons are released, thus
a) b)
Prestressed concrete can most easily be defined as precompressed Under load, the stresses in the beam will be compressive in the top
concrete. This means that a compressive stress is put into a concrete and tensile in the bottom. We can expect the beam to crack at the
member before it begins its working life, and is positioned to be in bottom, even with a relatively small load, because of concrete’s low
areas where tensile stresses would otherwise develop under working tensile strength. There are two ways of countering this low tensile
load. Consider a beam of plain concrete carrying a load. strength - by using steel reinforcement or by prestressing.
c) d)
In reinforced concrete, reinforcement in the form of steel bars is placed in In prestressed concrete, compressive stresses are introduced into
areas where tensile stresses will develop under load. The reinforcement areas where tensile stresses will develop under load to resist or annul
carries all the tension and, by limiting the stress in this reinforcement, the these tensile stresses. So the concrete now behaves as if it had a high
cracking of the concrete is kept within acceptable limits. tensile strength of its own.
Flexibility The positions of the tendons can be marked on the slab’s soffit and topside
Flexibility of layout can be achieved as PT concrete can cope with irregular
to aid identification for future openings. Alternatively, tendons can be
grids and unusual geometry, including curves.
located using C.A.T cable detection equipment.
10
09
Acoustics
Additional finishings to floors are often required to meet the requirements
Figure 4: Vibration control - increase in floor thickness for hospital wards of Approved Document E. The inherent mass of concrete means additional
and theatres compared to office spaces finishings are minimised or even eliminated. Independent testing of
Vibration control: Increase in floor thickness 250mm thick concrete floors in a block
of student accommodation gave results
exceeding requirements by more than
50% 5dB for both airborne and impact sound
insulation [3]. Further acoustic test results
40% are available at www.concretecentre.com/
% increase
acoustics.
30%
Air-tightness
20% Part L of the Building Regulations requires
pre-completion pressure testing. Failing
these tests means a time consuming process
10%
of inspecting joints and interfaces, resealing
Operating thea where necessary. Concrete edge details are
0% tre simpler to seal, with less failure risk. Some
Night ward
contractors have switched to concrete
e Office
o sit ck
frames on this criterion alone.
mp de lab b
Co Sli
m
lats sla
Cf PT
R
POST-TENSIONED CONCRETE FLOORS 7
Partitions Recycling
Sealing and fire stopping at partition heads is simplest with flat soffits. Concrete can be specified with recycled aggregate and, at the end of its
Significant savings of up to 10% of the partitions package can be made life, both the concrete and steel tendons from demolished PT floors are
compared to the equivalent dry lining package abutting a profiled soffit 100% recyclable.
with downstands. This can represent up to 4% of the frame cost, and a
significant reduction in programme length. Concrete mix
Modern concretes generally contain cement replacements which lower the
Minimal maintenance embodied CO2 and use by-products from other industries. Care should be
Unlike other materials, concrete does not need any toxic coatings or paint exercised to balance the environmental benefits of cement replacements
to protect it against deterioration or fire. Properly designed and installed with their slower strength gain, which delays the initial prestress. For
concrete is maintenance free. more information on alternative mix constituents, download Specifying
Sustainable Concrete from www.concretecentre.com.
Structural forms
The economic range for PT floors is 6m to 20m, depending The solid flat slab is economic for spans between 6m and 13m, which
on the structural form used. The shorter limit is based on makes it suitable as an alternative for many current frame options (see
the practical minimum economic depth of PT slab being Figure 5 below). Further details on flat slabs are given on page 9. For longer
spans, ribbed slabs or band beams are more economic and are described
200mm.
on pages 10 and 11.
There are three main structural forms used in the UK:
Figure 6 provides typical span-to-depth for PT floors. More detailed
¢¢ Solid flat slab guidance on sizing PT floors can be found in The Concrete Centre’s guide
¢¢ Ribbed slab Economic Concrete Frame Elements [4].
¢¢ Band beam and slab
Span (m)
5 6 7 8 9 10 11 12 13 14 15 16 17 18
Key
RC FLAT SLAB
RC WAFFLE
PT FLAT SLAB
PT RIBBED
PT WAFFLE
Key
Band Beam Ribbed Slab Flat Slab One-way Slab supported by a Band Beam
POST-TENSIONED CONCRETE FLOORS 9
PT flat slab
An efficient post-tensioned design can be achieved with
a solid flat slab which is ideally suited to multi-storey
construction where there is a regular column grid.
Points to note
Design
The depth of a flat slab is usually controlled by deflection requirements or
by the punching shear capacity around the column.
Economics
Flat slabs are particularly appropriate for areas where tops of partitions
need to be sealed to the slab soffit for acoustic or fire reasons. It is often
the reason that flat slabs are considered to be faster and more economic
than other forms of construction, as partition heads do not need to be cut
around downstand beams or ribs.
Flat slabs can be designed with a good surface finish to the soffit, allowing
exposed soffits to be used. This allows exploitation of the building’s thermal
mass in the design of heating, ventilation and cooling (HVAC) requirements,
increasing energy efficiency, and reducing energy consumption in use.
Speed on site
Speed of construction will vary from project to project, but a useful guide
is approximately 500m2/ crane/week. Once the final prestress is applied the
formwork can be struck.
Holes through the slab close to the column head affect the design shear
perimeter of the column head. Holes next to the column should ideally be
small and limited to two. These should be on opposite sides rather than on
adjacent sides of the column. It is worth setting out rules for the size and
location of these holes early in the design stage to allow coordination.
As with traditionally reinforced slabs, large service holes should be located A typical bonded PT flat slab prior to concrete pour.
away from the column strips and column heads in the centre of the bays. Courtesy of Freyssinet.
Again, location and size of any holes should be agreed early in the design.
10 POST-TENSIONED CONCRETE FLOORS
For large two-way spans, waffle slabs give a very material-efficient option
capable of supporting high loads. Waffle slabs tend to be deeper than the
equivalent ribbed slab. Waffle slabs have a thin topping slab and narrow
Ribbed slab
ribs spanning in both directions between column heads or band beams.
The column heads are the same depth as the ribs. The major drawback
with post-tensioning waffle slabs is that it is necessary to ‘weave’ the pre-
stressing tendons.
Points to note
Design
Waffle slabs work best with a square grid. Ribbed slabs should be
orientated so that the ribs span the longer distance, and the band beams
the shorter distance. The most economic layout is an aspect ratio of 4:3.
Waffle slab
Construction
Both waffle and ribbed slabs are constructed using table forms with
moulds positioned on the table forms. Speed of construction depends Markets: Benefits:
on repetition, so that the moulds on the table forms do not need to be
re-positioned. ¢¢ Vibration critical projects ¢¢ Flexible
¢¢ Hospitals ¢¢ Relatively light, therefore
Exposed finishes
¢¢ Laboratories less foundation costs
Ribbed and waffle slabs can provide a good surface finish to the soffit,
allowing exposed soffits to be used in the final building. This allows ¢¢ Speed
the use of the thermal mass of the building in the design of the HVAC ¢¢ Fairly slim floor depths
requirements, particularly as the soffit surface area of the slab is greater ¢¢ Robustness
than a flat slab, increasing the building’s energy efficiency.
¢¢ Excellent vibration
Speed on site characteristics
This is a slower form of construction than flat slabs. The use of table forms ¢¢ Thermal mass
offers the fastest solution. ¢¢ Good services integration
¢¢ Durable finishes
Where partitions need to be sealed acoustically or for fire, up to the soffit,
ribbed and waffle slabs take longer on site. Lightweight floor blocks can be ¢¢ Fire resistance
placed between the concrete ribs to act as permanent formwork, which
give a flat soffit, although these take away some of the benefits of the
lighter weight slab design. If partition locations are known, the moulds may
be omitted on these lines.
This form of construction is commonly used for irregular grids and long
spans, where flat slabs may be less suitable. It is also used for transferring
loads from columns and walls or from heavy point loads to columns or
walls below.
It is also a popular method for providing a 15.6m clear span for a standard
Band beam and slab
car park configuration with a band beam spanning 15.6m and a one-way
slab spanning 7.2m or 7.5m.
Points to note
Design
The beams will usually be designed to be PT, whereas the slabs can be
designed with conventional reinforcement if the spans are relatively short.
Construction
Using a band beam rather than a deep beam simplifies the formwork.
Design theory
Recommendations for the design of prestressed into account the affect of other elements and to enable different load
concrete are given in Eurocode 2, part 1-1 [7]. Design combinations to be applied, or to carry out both the structural analysis and
methods for post-tensioned flat slabs are relatively prestress design.
straightforward, and detailed guidance, based on
There are currently three software programs which are widely used, but
Eurocode 2, is available in The Concrete Society
other programs also exist. They either use the finite element method to
Technical Report 43 [1]. analyse the whole floor or design strips to analyse bay widths running
across the floor plan in each direction.
At the serviceability condition the concrete section is checked at all
positions to ensure that both the compressive and tensile stresses lie within
The basic principles of prestressed concrete design can be simply
the acceptable limits given in the Codes of Practice. Stresses are checked in
understood by considering the stress distribution in a concrete section
the concrete section at the initial condition when the prestress is applied,
under the action of externally applied forces or loads. It is not intended
and at serviceability conditions when calculations are made to determine
here to provide a detailed explanation of the theory of prestressed
the deflections and crack widths for various load combinations.
concrete design.
a) Consider a beam with a force P applied at each end along the beam’s c) T he stress distribution from the flexure of the beam is calculated from
centre line. M/Z where M is the bending moment and Z the section modulus. By
considering the deflected shape of the beam it can be seen that the
P P bottom surface will be in tension. The corresponding stress diagram
can be drawn. + M/Z
P/A
Compression
M (max)
- M/Z P/A - M/Z
0 0 0
POST-TENSIONED CONCRETE FLOORS 13
The technique known as ‘load balancing’ offers the designer a powerful a) Proposed
tool. In this, forces exerted by the prestressing tendons are modelled as loading
equivalent upward forces on the slab. These forces are then proportioned
to balance the applied downwards forces (see Figure 8). By balancing
a chosen percentage of the applied loading it is possible to control
deflections and also make the most efficient use of the slab depth.
b) Unstressed
slab
In order to use the load balancing technique, the prestressing tendons
must be set to follow profiles that reflect the bending moment envelope
from the applied loadings. Generally parabolic profiles are used. In the case
of flat soffit slabs these are achieved by the use of supporting reinforcing
bars placed on proprietary chairs.
c) Prestressed
In post-tensioned concrete floors, the load balancing technique can enable slab
the optimum depth to be achieved for any given span. The final thickness
of the slab, as with reinforced concrete flat slabs, may also be controlled by
the punching shear around the column.
d) Final
condition
Design considerations
PT floors are fairly straightforward to design, but there Where the walls are unfavourably arranged then a calculation of the
are some aspects which are different to other types of effects of movement should be carried out and suitable measures taken to
reinforced concrete design. These should be considered overcome them. This could involve:
when scheming the project. ¢¢ Using infill strips which are usually cast around 28 days after the
remainder of the floor, to allow initial shrinkage to occur (see Figure 10).
At the early stages of a project using post-tensioned floors, care must be ¢¢ Using temporary release details (see Figure 11).
taken to avoid the problems of restraint. This is where the free movement in ¢¢ Reducing the stiffness of the restraining elements.
the length of the slab under the prestress forces is restrained, for example
by the unfavourable positioning of shear walls or lift cores (see Figure 9). The effect of the floor shortening on the columns should also be
considered in their design as this may increase their design moments.
All concrete elements shrink due to drying and early thermal effects but,
in addition, prestressing causes elastic shortening and ongoing shrinkage
due to creep. Stiff vertical members such as stability walls restrain the floor
Disproportionate collapse
slab from shrinking, which prevents the prestress from developing and thus
PT floor systems are usually designed to resist disproportionate collapse
reduces the strength of the floor.
through detailing of the tendons and reinforcement. In bonded systems
the tendons can be considered to act as horizontal ties. In unbonded
Where the restraining walls are in a favourable arrangement and the floor
systems, the tendons cannot be relied on and the conventional
is in an internal environment, the maximum length of the floor without
reinforcement acts as the horizontal ties.
movement joints can be up to 50m. However, full consideration should be
given to the effects of shrinkage due to drying, early thermal effects, elastic
shortening and creep in the design.
a) Favourable layout of restraining walls (low restraint) Figure 11: Temporary release detail
Infill later
Post-tensioned slab
Service holes
Openings in slab.
The ducts are formed from spirally-wound or seam-folded galvanised metal Further guidance can be found in How to design concrete structures using
strip. The limit on the curvature or profile that can be achieved with the Eurocode 2 (Getting Started section) [9].
prestressing tendons is dependent on the flexibility of the ducts.
In an unbonded system the tendon is not grouted and remains free to Procurement
move independently of the concrete. This has no effect on the serviceability
PT slabs can be procured using the same routes as any other concrete slab.
design or performance of a structure under normal working conditions. It
The post-tensioning specialist is usually sub-contracted to the concrete frame
does, however, change both the design theory and structural performance
contractor. As post-tensioning has been increasingly used since the mid
at the ultimate limit state.
1990s the concrete frame contractors are now familiar with the technique.
Table 2 summarises the main differences between the two systems. The
It is important that the PT system is supplied and installed by a suitably
greater resistance to accidental damage of bonded construction is often an
experienced company. An industry accreditation scheme is run by UK
important consideration.
CARES and the status of a particular company can be found at
www.ukcares.com. It is recommended that specifications require CARES
Concrete approved PT suppliers and installers to be used.
PT slabs do not require particularly high strength concrete and often class In the UK the PT specialist is often made responsible for the design of the
C32/40 concrete is used. For speed of construction the concrete should floor and detailing the strand and anchorages. In the US, and increasingly in
have high early strength. This allows initial prestress to be carried out as the UK, the consulting engineer undertakes the design.
early as possible, usually after 24 hours to prevent cracking. Final stressing
Whichever route is adopted on a project, it is important to be clear from the
can take place after three days, allowing striking of formwork.
outset where the responsibilities lie. The design codes highlight the need
for a sole engineer to take responsibility for the overall design, ensuring
Durability
that any design carried out by others is compatible with the design of the
The concrete should be specified in accordance with BS 8500 to ensure
remainder of the structure.
good durability. For most building structures with an internal environment
this is not an onerous requirement. However, external structures, and
in particular car parks, require more attention to detail to ensure good Specification
corrosion resistance.
The Post-tensioning Association has produced a model specification for
bonded and unbonded post-tensioned floors [14], and it is recommended
that this guide is referred to. The document is available from
www.posttensioning.co.uk.
Table 2: Comparison of PT systems
Bonded Unbonded
Anchor
An unbonded anchorage. Courtesy of CCL Ltd. Section through a bonded live anchorage.
Courtesy of Strongforce Engineering.
POST-TENSIONED CONCRETE FLOORS 17
Construction considerations
Sequence of installation Concreting
A typical construction sequence is as follows: Care must be taken when concreting to prevent operatives displacing
1 Install soffit and edge formwork tendons or crushing the ducts in bonded construction.
2 Fix bottom reinforcement
Good compaction of the concrete is always important, but it is particularly
3 Fix live anchorages to edge forms
so around anchorages because of the high local stresses in these areas.
4 Install tendons
5 Tape joints in ducts and thread the strands (bonded only)
6 Fix tendon support bars to specified heights (1m centres) Stressing
7 Fix top steel
8 Fix punching shear reinforcement Ideally after 24 hours, when the concrete has attained a strength of typically
12.5 N/mm2, initial stressing of tendons to about 25% of their final jacking
force is carried out. (The actual concrete strength and tendon force will vary
Construction joints depending on loadings, slab type and other requirements.) This controls
restraint stresses.
There are four types of construction joint that can be used between
areas of slab; these are shown in Figure 15. When used they are typically The tendon is stressed with a hydraulic jack, and the resulting force is
positioned in the vicinity of a quarter or third points of the span. The most locked into the tendon by means of a split wedge located in the barrel of
commonly used joint is the infill or closure strip, as this is an ideal method the recessed anchor.
of resolving problems of restraint, and it also provides inboard access
At about three to five days, when the concrete has attained sufficient
for stressing, removing or reducing the need for perimeter access from
design strength, the remaining stress is applied to the tendons.
formwork or scaffolding.
The extension of each tendon under load is recorded and compared
Construction joint with no stressing (Figure 15a) against the calculated value. Provided that it falls within an acceptable
The slab is cast in bays and stressed when all the bays are complete. For tolerance, the tendon is then trimmed. With an unbonded system, a
large slab areas, control of restraint stresses may be necessary and ideally greased cap is placed over the recessed anchor and the remaining void
the next pour should be carried out on the following day. dry-packed. With a bonded system the anchor recess is simply dry-packed
and the tendon grouted.
Construction joint with intermediate stressing (Figure 15b)
On completion of the first pour containing embedded bearing plates,
intermediate anchorages or couplers are fixed to allow the tendons to Back propping
be stressed. After casting of the adjacent pour, the remainder of the
When designing the formwork systems for multi-storey construction, the
tendon is stressed. It is sometimes necessary to leave a pocket around the
use of back-props, through more than one floor to support the floor under
intermediate anchorage to allow the wedges that anchor the tendons
construction, should be considered.
during the first stage of stressing to move during the second stage of
stressing. This option is most suitable for use with unbonded tendons.
Pour size/joints
Large pour areas are possible in post-tensioned slabs, and the application of
an early initial prestress, at a concrete strength of typically 12.5 N/mm2, can
a) No intermediate stressing c) Tensioning at construction
help to control restraint stresses. There are economical limits on the length
joint
of tendons used in a slab. Typically these are 35m for tendons stressed from
one end only and 70m for tendons stressed from both ends.
The slab can be divided into appropriate areas by the use of stop ends
and, where necessary, bearing plates are positioned over the unbonded
b) Intermediate stressing d) Infill or closure strip
tendons to allow for intermediate stressing. (unbonded tendons)
18 POST-TENSIONED CONCRETE FLOORS
Cost comparisons
The frame is the key structural element of any building. Six short span options were developed including a PT flat slab. The PT
Frame choice and design can have an influential role in option is shown in Figure 16. Two long span options were also included
the performance of the final building, and importantly, which included PT band beams and slab (see Figure 17).
also influence people using the building. A programming exercise was carried out and this established that both the
post-tensioned options could be constructed one week faster than a steel
The cost of the frame alone should not dictate frame choice. Many issues
frame with long span composite cellular beams. The study compared the
should be considered when choosing the optimum solution. The Concrete
cost of the various options and found the cost for the PT flat slab option
Centre commissioned a series of cost model studies [10,11,12] to compare
was 1% cheaper than the composite steel option (see Table 3). It also found
the cost of various structural frames for a variety of different buildings. All
that, of the two long span options, PT band beams had the lowest building
the buildings were designed, costed and programmed by independent
cost and the premium for the long spans was 2.2%.
consultants. Selected information for a community hospital, a secondary
school and an office in central London is presented here. Full details of the study are available from Cost Model Study – Commercial
Buildings [10].
All the studies showed that the choice of frame had an influence on the
cost of other elements of the building which should be considered at
the early stages of a project. Whole life costs should also be considered.
Concrete has inherent benefits – such as fabric energy storage (thermal THE CHOICE OF STRUCTURAL FRAME MAY ALSO
mass), fire resistance and sound insulation – which mean that concrete
AFFECT THE COST OF:
buildings tend to have lower operating costs and lower maintenance
requirements. This is an important consideration, particularly for owner-
¡ CLADDING ¡ PRELIMINARIES
occupiers and PFI consortia.
¡ PARTITIONS ¡ FOUNDATIONS
Commercial Buildings ¡ SERVICES
For this building configuration, post-tensioned and IT MAY ALSO IMPACT ON THE NETT LETTABLE
reinforced concrete were found to be the lowest cost AREA.
options.
The commercial cost model study included a six-storey office building in
central London. The building included some retail areas at ground floor
level to reflect current trends.
Figure 16: PT flat slab for a typical Central London office building (short span)
A B C D E F G H I
9000 9000 9000 9000 9000 9000 9000 9000
1
7500
2
7500
275*
3
9000
4
*This is a slab
7500
thickness used
for scheme
design. Specialist
5 contractors have
advised that a
250mm thick
7500
slab would be
proposed in a
competitive
6 situation.
Figure 17: PT band beams for a typical central London office building (long span)
A B C D E F G H I
225
2
550 x 2500 PT Band Beam (Typ)
550 x 2750 PT Band Beam
6
20 POST-TENSIONED CONCRETE FLOORS
Hospitals Table 4: Elemental costs for local hospital compared (2008 costs)
The hospital buildings cost model study included a local hospital Frame & Upper Floors 121 6.5% 129 6.8%
and a district hospital. Both consisted of a number of wards, Roof finishes 93 5.0% 93 4.9%
identical to the structural arrangement shown in Figure 18. The
Stairs 8 0.4% 8 0.4%
local hospital had four wards plus entrance areas, while the district
hospital had wards spread over three storeys plus entrance areas External Cladding 155 8.3% 164 8.7%
and corridors. External Windows & Doors 22 1.2% 23 1.2%
The whole building costs for six structural options were assessed Internal Planning 92 4.9% 102 5.4%
for these types of hospital. The costs for two of these options Wall Finishes 20 1.1% 23 1.2%
for a local hospital, composite steel frame and PT flat slab, are
Floor Finishes 48 2.6% 48 2.5%
compared in Table 4. This shows that the PT flat slab would have
lower cost than a building using a composite steel frame. The Ceiling Finishes 28 1.5% 28 1.5%
saving comes not only from the frame cost but also the building is Fittings 210 11.2% 210 11.1%
lower and therefore the cladding cost is reduced.
Sanitary 23 1.2% 23 1.2%
All the options were designed to meet vibration criteria for a ward
Mechanical 250 13.3% 255 13.5%
with minimal additional materials.
Electrical 192 10.3% 196 10.4%
Full details of the study are available from Cost Model Study –
Lifts 54 2.9% 54 2.9%
Hospital Buildings [11].
BWIC 47 2.5% 47 2.5%
Contingency 107 5.7% 110 5.8%
Preliminaries 227 12.1% 203 10.7%
Overheads & profit 106 5.7% 107 5.7%
Total 1871 1890
Figure 18: PT flat slab for a single ward
1 2 3 4 5 6 7
7800 7800 7800 7800 9000 6600
A
6600
B
9000
275
C
7800
D
7800
Schools Table 5: Elemental costs for school building compared (2008 costs)
The educational cost model study focused on a secondary Frame / Upper Floors 121 8.3% 122 8.2%
school on a redeveloped school site. The school was a mixture of Roof 83 5.7% 83 5.6%
two-storeys, three-storeys and some double height spaces. Six
Stairs 19 1.3% 19 1.2%
structural options were developed, including a composite steel
frame and a PT flat slab. Details for part of the PT option are shown External Cladding 219 15% 233 15.7%
in Figure 19. The remainder of the two- and three-storey areas in External Windows & Doors 22 1.5% 22 1.5%
the school are of a similar nature. For this study it was decided that
Internal Planning 78 5.4% 86 5.8%
roofs for all the options would be constructed in a similar way.
Wall Finishes 32 2.2% 31 2.1%
The programme prepared (by a contractor) showed that the PT
Floor Finishes 52 3.6% 52 3.5%
flat slab would give the shortest overall construction time; the
frame would be constructed in just eight weeks. Ceiling Finishes 27 1.9% 27 1.8%
The cost comparisons show that the PT flat slab would give Fittings 110 7.5% 110 7.4%
the lowest cost of all six options and a comparison against a Sanitary 11 0.8% 11 0.7%
composite steel frame is shown in Table 5.
Mechanical 155 10.6% 158 10.6%
Full details of the study are available from Cost Model Study – Electrical 131 9.0% 134 9.0%
School Buildings [12].
Lifts 6 0.4% 6 0.4%
BWIC 35 2.4% 35 2.4%
Contingency 87 6.0% 89 6.0%
Prelims, overheads
210 14.5% 213 14.4%
and profit
Total 1459 1489
Figure 19: PT flat slab for part of a secondary school
A B C D E F G H
7750 8075 8075 8075 8075 7750 5380
1
8250
250
2
8250
3
8250
5
22 POST-TENSIONED CONCRETE FLOORS
End of life
Demolition
There is a small additional risk associated with the demolition of a post-
tensioned structure. The demolition methods are similar to those used
for reinforced concrete (RC) structures, with some modifications as noted
below.
For unbonded slabs, the approach is often to prop the floor and then
release the tension in the tendons by either:
¢¢ Heating the wedges until the tendon slip occurs
¢¢ Breaking out the concrete behind the anchorage until detensioning
occurs
¢¢ De-tensioning the tendon, using jacks
¢¢ Cutting through the strands at high points, whilst protecting around
Demolition of PT bonded slab using conventional demolition
anchorages.
equipment. Courtesy of Freyssinet
It has been shown by testing and from experiences on-site that anchorages
and/or dry packing are not ejected from the slab edge at high velocity. This
steel strand is bonded via the grout and duct to the concrete, so that any
is due to the friction between strand and the sheath which dissipates.
cut through the tendon has a local effect only. At a bond length away the
More detailed guidance can be found in the PTA’s guidance note GN01, tensile strength is unaffected.
Post-Formed Holes Through Post-Tensioned Slabs [13].
A typical procedure for bonded tendons would be as follows:
Demolition of transfer structures should be treated with due consideration. 1 Mark the tendon positions.
The forces involved are significantly higher than for a single floor slab and
2 Using appropriate equipment for the type and size of project, demolish
the prestressing forces may have been increased as additional floors were
the concrete between tendons, taking care to avoid damage to the
constructed. Provided the demolition method takes account of these
tendons.
issues, the risks can be identified and managed.
3 Remove the concrete, leaving the tendons.
4 Cut the tendons to length for the new layout.
Alterations 5 Cast new concrete.
As with demolition, structural alterations are no more difficult than for other
Experience has shown there is no explosive release of energy when the
construction forms, and can be easier to adapt. This means that the benefits
concrete is broken out because the concrete is broken out in relatively
of existing post-tensioned floor construction can be used when altering
small areas. For major refurbishment projects new tendons and anchorages
existing buildings (e.g. redundant office space being reused for residential
can be installed to work in combination with the existing post-tensioning.
accommodation).
Many of the older PT slabs in the UK were constructed using unbonded
When it comes to minor alterations, PT slabs are often easier to work with
tendons, and the techniques for altering these are similar, but require
than other structural forms. They derive their tensile strength from high
slightly more planning and possibly disruption. This is because unbonded
strength steel tendons which are often spaced at well over 1m centres.
construction relies on the anchorages at either end to transmit forces
Depending on the specific circumstances, the concrete can generally be
between the slab and tendons so cutting the tendon releases the tension
cut out between the strands without the need for strengthening. This
throughout its length. Therefore, before breaking out any concrete, the slab
could potentially be an opening of 1m square, or perhaps even larger. An
must be propped throughout the length of the strand to be cut, and then
experienced structural engineer should always be employed to check the
de-tensioning of the strand should be carried out. The same procedure
effects of the proposed alterations.
detailed for a bonded system can then be adopted except that the severed
More substantial alterations can also be undertaken using tried and tested unbonded tendons should be restressed using new anchorages cast into
techniques. Procedures vary slightly depending on whether the PT slab the edge of the opening.
has bonded or unbonded tendons. Currently, bonded tendons are used
for the vast majority of new PT construction in the UK. In this system the
POST-TENSIONED CONCRETE FLOORS 23
Summary
¢¢ There are a number of slab types that can be used to suit individual
projects.
¢¢ As with all structural solutions, there are a number of considerations to
be aware of and, for PT, restraint of the slab should be considered at the
Post tensioned concrete slabs are a tried and tested form of construction in
early stage of a project.
use throughout the world. PT is popular within the UK with many projects
for designers to refer to. See www.concretecentre.com/casestudies ¢¢ Demolition and alterations of PT slabs should not be seen as being
more difficult than with any other type of design; they all require
¢¢ There are many benefits to be gained from using post-tensioned planning and detailed consideration. There is also plenty of experience
construction: of this type of work amongst UK sub-contractors.
nn Minimum floor thickness ¢¢ For more information on post-tensioning, the Post-Tensioning
nn Long spans Association (PTA) has guidance notes on sustainable construction in
nn Rapid speed of construction post-tensioning, procurement of post-tensioned slabs and concrete
nn Flexibility of layout stress limits for post-tensioned design available to download at
nn Flat soffit www.posttensioning.co.uk
nn Minimum use of materials ¢¢ Further information and guidance on the benefits of using concrete for
nn Cost-effective thermal mass and material efficiency are available from The Concrete
Centre at www.concretecentre.com/publications
References
To download or access many of these publications, visit www.concretecentre.
com/publications. Case studies on post-tensioning can be found at the
website of the Post-tensioning Association – www.posttensioning.co.uk
1. Technical Report no. 43: Post-tensioned Concrete Floors Design 8. BS EN1992-1-2, Eurocode 2: Design of Concrete Structures. General
Handbook (second edition),The Concrete Society, 2005 Rules – structural fire design, British Standards Institution, 2004
2. Hospital Floor Vibration Study – comparison of possible floor structures 9. How to Design Concrete Structures using Eurocode 2, CCIP-06, The
with respect to NHS vibration criteria, Arup, 2004. Download from Concrete Centre, 2007
www.concretecentre.com
10. Cost Model Study - Commercial Buildings, CCIP-010, The Concrete
3. PE Jones, Site Airborne and Impact Sound Insulation Measurements Centre, 2007
Between Rooms in Student Accommodation at Colman House,
11. Cost Model Study - Hospital Buildings, CCIP-012, The Concrete Centre,
University of East Anglia, Norwich (Acoustic Test Report no. 04091),
2009
2004. Download from www.concretecentre.com
12. Cost Model Study - School Buildings, CCIP-011, The Concrete Centre,
4. Economic Concrete Frame Elements (Second Edition), CCIP-025, The
2008
Concrete Centre, 2009
13. GN01 Post-Formed Holes Through Post-Tensioned Slabs, Post-Tensioned
5. How to design reinforced concrete flat slabs using Finite Element
Association, Download from www.posttensioning.co.uk
Analysis, The Concrete Centre, 2006
14. Model Specification for the Design and Performance of Post-Tensioned
6. Practical Yield Line Design, The Concrete Centre, 2004
Concrete Floors in Building Structures, The Post-Tensioning Association,
7. BS EN1992-1-1, Eurocode 2: Design of Concrete Structures. General 2017
Rules and rules for building, British Standards Institution, 2004
The Concrete Centre provides material, For more information and downloads, visit:
design and construction guidance. Our aim www.concretecentre.com/publications
is to enable all those involved in the design, www.concretecentre.com/events
use and performance of concrete to realise www.concretecentre.com/cq
the potential of the material.
Subscribe to our email updates:
The Concrete Centre provides design www.concretecentre.com/register
guidance, seminars, courses, online
resources and industry research to the Follow us on Twitter:
design community. @concretecentre
@thisisconcrete
The Concrete Centre is part of the
Mineral Products Association, the
trade association for the aggregates,
asphalt, cement, concrete, dimension stone,
lime, mortar and silica sand industries.
www.mineralproducts.org
www.concretecentre.com
The Concrete Centre, Gillingham House, 38-44 Gillingham Street, London SW1V 1HU
Ref. TCC/03/33
ISBN 978-1-904818-59-5
First published 2008, updated 2017
© MPA The Concrete Centre 2017
All advice or information from MPA The Concrete Centre is intended only for use in the UK by those who will evaluate
the significance and limitations of its contents and take responsibility for its use and application. No liability (including
that for negligence) for any loss resulting from such advice or information is accepted by the Mineral Products
Association or its subcontractors, suppliers or advisors. Readers should note that the publications from MPA The
Concrete Centre are subject to revision from time to time and should therefore ensure that they are in possession of
the latest version.
Printed onto 9Lives silk comprising 55% recycled fibre with 45% ECF virgin fibre.
Certified by the Forest Stewardship Council.