SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

CHAPTER 13
BILL OF QUANTITY (BOQ)

13.1. GENERAL

The volume of work is the calculation of physical work which will be implemented in
the location. The calculation of the volume of work (BOQ) is one part to estimate the project
budget. Analysis of BOQ will produce a large volume of a building. Output of BOQ analysis
will be used as the basis of calculation of the RAB project, which will produce cost of capital
(Investment Cost).
Unit volume work’s Calculation of adjusted for each work item, item of work that can
be used for PLTG/MG/GU Sorong-2 (50 MW) are work of Site Development, Soil
Improvement, trestle dock etc. This calculation uses cubic unit is in m3, cm3 or more units.
The process of RAB calculation is using the unit m3. The number of jobs in Sorong
PLTG/MG/GU Sorong-2 (50 MW) is calculated using the following formula:

Volume = average area on each piece x distance between each piece

The location of PLTG/MG/GU Sorong-2 (50 MW) that is used for the BOQ’s calculation
is located at Sorong-2.
13.2. BOQ’S PLTG/MG/GU SORONG-2 (50 MW) SORONG LOCATION

Information:
Building 1 is at Cross Section B-B
Building 2 is at Cross section C-C to cross section F-F

FINAL REPORT XIII - 1


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

Cut
Backfill

Figure 13.1. Cross Section B-B

Cut Backfill

Figure 13.2. Cross Section C-C

FINAL REPORT XIII - 2


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

Cut Backfill

Figure 13.3. Cross Section D-D

Cut Backfill

Figure 13.4. Cross Section E-E

FINAL REPORT XIII - 3


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

Cut Backfill

Figure 13.5. Cross Section F-F

FINAL REPORT XIII - 4


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

PLTG/MG/GU SORONG - 2 (50 MW)

Struktur : Ground Leveling Building 1 at level +3,90


Item Pekerjaan : Pekerjaan Tanah

Pekerjaan Galian dan Timbunan Ground Leveling


Area Rata-Rata Area Rata-Rata Area Volume Volume
Area Galian
Timbunan Galian Timbunan Galian Timbunan
Jarak
Potongan
Tanah Biasa Tanah Biasa Tanah Biasa
2 2 2 2 3
(m ) (m ) (m) (m ) (m ) (m ) (m3)

(B-B) - 37.51 96,04 201,07


37,51 96,04 201,07 3.602,46 7.542,14
(B-B) 96,04 201,07
30,80 96,04 201,07 2.958,03 6.192,96
(B-B) + 30.80 96,04 201,07

Total Volume Pekerjaan 6.560,49 13.735,09

PLTG/MG/GU SORONG - 2 (50 MW)

Struktur : Ground Leveling Bangunan 2 at level +3,90


Item Pekerjaan : Pekerjaan Tanah

Pekerjaan Galian dan Timbunan Ground Leveling


Area Rata-Rata Area Rata-Rata Area Volume Volume
Area Galian
Timbunan Galian Timbunan Galian Timbunan
Jarak
Potongan
Tanah Biasa Tanah Biasa Tanah Biasa

(m2) (m2) (m) (m2) (m2) (m3) (m3)

(C-C) - 7.80 73,87 193,35


7,80 73,87 193,35 576,19 1.508,13
(C-C) 73,87 193,35
50,00 73,98 252,98 3.698,75 12.649,00
(D-D) 74,08 312,61
50,00 74,19 316,89 3.709,25 15.844,25
(E-E) 74,29 321,16
50,00 74,63 372,33 3.731,25 18.616,50
(F-F) 74,96 423,50
8,80 37,48 211,75 329,82 1.863,40
(F-F) + 8.80 74,96 423,50

Total Volume Pekerjaan 12.045,26 50.481,28

FINAL REPORT XIII - 5


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

13.2.1. Working of Power Plant’s Road, Drainage and Rip-Rap


1. Road’s Working B = 8 meter
Total Length of Road = 642.97 m

Figure 13.6. Acces Road Working

PLTG/MG/GU SORONG - 2 (50 MW)

Struktur
Structure : :Road
Jalan 8 meter
8 meter
Item
Item of Works
Pekerjaan : :Road Works Jalan
Pekerjaan

Access Road 10 Meter

Area Volume
Distance
Concrete T Concrete T Lean Concrete T 7
Road Side Lean Concrete T 7 cm Road Side
20 cm 20 cm cm
(m2) (m2) (m2) (m) (m3) (m3) (m3)

0.96 3.24 1.24 642.97 617.25 2083.22 797.28

Total Volume 617.25 2083.22 797.28

FINAL REPORT XIII - 6


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

2. Drainage’s Working
a. Total of drainage of the PLTG/MG/GU = 2 Pieces (right and left shoulder road)
b. Box Culvert 95 x 110 cm
The total of drainage length of the PLTG/MG/GU = 1,272.54 m

Figure 13.7. Drainage of the PLTG/MG/GU

PLTG/MG/GU SORONG - 2 (50 MW)

Structure : Box Culvert 95 x 110 cm


Item of Works : Culvert Works

Length Area Volume


(m) (m2) (m3)

1272,54 0,43 547,19

Total Volume 547,19

FINAL REPORT XIII - 7


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

3. Rip-Rap’s Working
The total of Rip-Rap Length = 208.80 m

Figure 13.8. Rip-Rap

PLTG/MG/GU SORONG - 2 (50 MW)

Struktur : Rip-Rap Dia. 30 cm


Item Pekerjaan : Pekerjaan Batu

Pekerjaan Batu
Area Pasangan Rata-Rata Area
Volume
Batu Pasangan Batu
Jarak
Potongan
Rip-rap Rip -rap Rip - rap

(m2) (m) (m2) (m3)

(B-B) 0.53
50.00 0.53 26.50
(C-C) 0.53
50.00 0.53 26.50
(D-D) 0.53
50.00 0.53 26.50
(E-E) 0.53
50.00 0.53 26.50
(F-F) 0.53
8.80 0.27 2.33
(F-F) + 8.80 0.53

Total Volume Pekerjaan 108.33

FINAL REPORT XIII - 8


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

Segmental of Fence 2 meter


The total length of fence = 1,266.21 m

Figure 13.9. Segmental of Fence

PLTG/MG/GU SORONG - 2 (50 MW)

Structure : Fence
Item of Works : Concrete Works

Area Volume
Distance
Fence Fence

(m2) (m) (m3)

0,87 1266,21 1104,14

Total Volume 1104,14

FINAL REPORT XIII - 9


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

13.2.2. Recapitulation of BOQ PLTG/MG/GU Sorong-2 (50 MW) Located in Sorong


Recapitulation of BOQ PLTG/MG/GU Sorong-2 (50 MW) Located in Sorong shows as table
below:
Table 13.1. Recapitulation of BOQ PLTG/MG/GU Sorong-2 (50 MW) Located in Sorong

Volume
No. Item of Work Unit
Estimation

I. Soil Work
A. Work of Cutting Soil
A.1. Stripping H = 0.50 meter
1 Ground Leveling Building 1 at level + 3.90 (m3) 6,560.49
3
2 Ground Leveling Building 2 at level + 3.90 (m ) 12,045.26
Depth of Striping H = 0.50 m ; Total Volume of Stripping 18,605.75

B. Work of Soil Filling


B.1. Soil Filling
1 Ground Leveling Building 1 at level + 3.90 (m3) 13,735.09
2 Ground Leveling Building 2 at level + 3.90 (m3) 50,481.28
Total Volume of Soil Filling 64,216.37

Work of Roads at the power plant, drainage and


II. Rip-rap
C. Works of road & Drainage
C.1. Work of road, width 8 meter
1 Length of road m 642.97
3
2 Sidewalk (m ) 617.25
3 Concrete T 20 cm (m3) 2,083.22
3
4 Lean Concrete T 7 cm (m ) 797.28

C.4. Work of Drainage


1 Box Culvert 95 x 110 (m3) 547.19

D. Works
D.1. Rip-Rap
1 Rip-rap Stone D = 0.30 m (m3) 108.33

Segmental Concrete Fence (Total of Length L =


D.2. 1,266.21 m, height H = 2.0 m)
1 Precast Concrete Panel Fence (m3) 1,104.14

FINAL REPORT XIII - 10


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

Table 13.2. Bill Of Quantity Recapitulation For Piling Works PLTG/MG/GU Sorong-2
(50 MW) Located In Sorong
TOTAL
LENGTH
DESCRIPTION QUANTITY LENGTH
ITEM NO. UNIT OF PILE
CIVIL WORKS (Pcs) OF PILE
(m)
(m)

I CIVIL WORKS
I.1 PILING WORKS

Work specified under this section includes but not limited to


furnishing, delivery, installation, joined, testing of piles,etc.

I.1.1 GAS ENGINE FOUNDATION


Circular hollow pre-stressed concrete piles with 600 mm m' 15 12 180
minimum diameter accordance to site conditions

I.1.2 GAS ENGINE BUILDING

Circular hollow pre-stressed concrete piles with 600 mm m' 504 18 9072
minimum diameter accordance to site conditions

I.1.3 EXHAUST STACK

Circular hollow pre-stressed concrete piles with 400 mm m' 144 18 2592
minimum diameter accordance to site conditions

I.1.4 ADMINISTRATION BUILDING

Circular hollow pre-stressed concrete piles with 400 mm m' 280 18 5040
minimum diameter accordance to site conditions.

I.1.5 GAS FUEL SYSTEM

Circular hollow pre-stressed concrete piles with 400 mm m' 136 12 1632
minimum diameter accordance to site conditions.

I.1.6 HSD FUEL OIL FACILITIES

A. HSD Storage Tank (include dike wall)

Circular hollow pre-stressed concrete piles with 600 mm m' 100 18 1800
minimum diameter accordance to site conditions

B. HSD Daily Tank (include dike wall)

Circular hollow pre-stressed concrete piles with 600 mm m' 64 18 1152


minimum diameter accordance to site conditions

C. Fuel Oil Transfer Pump (include shelter)

[Circular hollow pre-stressed concrete piles with 400 m' 45 18 810


mm minimum diameter accordance to site
conditions.]Sch1.2-6
D. Fuel Oil Forwarding Pump (include shelter)

Circular hollow pre-stressed concrete piles with 400 mm m' 72 18 1296


minimum diameter accordance to site conditions.

E. Fuel Oil Treatment Plant (include shelter)

Circular hollow pre-stressed concrete piles with 400 mm m' 441 18 7938
minimum diameter accordance to site conditions.

F. HSD Fuel Oil Unloading Pump with Loading Arm

FINAL REPORT XIII - 11


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

TOTAL
LENGTH
DESCRIPTION QUANTITY LENGTH
ITEM NO. UNIT OF PILE
CIVIL WORKS (Pcs) OF PILE
(m)
(m)
Circular hollow pre-stressed concrete piles with 400 mm m' 16 18 288
minimum diameter accordance to site conditions.

I.1.7 PLANT WATER FACILITIES

A. Water Tank Facilities

- Raw Water Tank

Circular hollow pre-stressed concrete piles with 600 mm m' 81 18 1458


minimum diameter accordance to site conditions

B. Pump Shelter

Circular hollow pre-stressed concrete piles with 400 mm m' 45 18 810


minimum diameter accordance to site conditions.

I.1.8 COMPRESSED AIR SYSTEM

Circular hollow pre-stressed concrete piles with 400 mm m' 35 18 630


minimum diameter accordance to site conditions.

1.1.9 WASTE WATER TREATMENT PLANT

Circular hollow pre-stressed concrete piles with 400 mm m' 221 18 3978
minimum diameter accordance to site conditions.

I.1.10 ELECTRICAL FACILITIES

A. Generator Transformer and Unit Auxiliary Transformer

Circular hollow pre-stressed concrete piles with 600 mm m' 15 18 270


minimum diameter accordance to site conditions

B. Two Transformer Bays 150 kV AIS

Circular hollow pre-stressed concrete piles with 600 mm m' 63 12 756


minimum diameter accordance to site conditions

C. Electrical Building

Circular hollow pre-stressed concrete piles with 600 mm m' 72 18 1296


minimum diameter accordance to site conditions

D. Modifying Substation Control Building

Circular hollow pre-stressed concrete piles with 600 mm m' 126 18 2268
minimum diameter accordance to site conditions

E. MV Switchgear Building

Circular hollow pre-stressed concrete piles with 600 mm m' 4 12 48


minimum diameter accordance to site conditions

F. Underground Cable Duct, CableTrench and Cable


Raceway
Circular hollow pre-stressed concrete piles with 400 mm m' 270 12 3240
minimum diameter accordance to site conditions.

I.1.11 EMERGENCY DIESEL GENERATOR

Circular hollow pre-stressed concrete piles with 400 mm m' 35 18 630


minimum diameter accordance to site conditions.

FINAL REPORT XIII - 12


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

TOTAL
LENGTH
DESCRIPTION QUANTITY LENGTH
ITEM NO. UNIT OF PILE
CIVIL WORKS (Pcs) OF PILE
(m)
(m)
I.1.12 WAREHOUSE AND WORKSHOP

Circular hollow pre-stressed concrete piles with 600 mm m' 280 18 5040
minimum diameter accordance to site conditions

I.1.13 MISCELLANEOUS BUILDINGS & STRUCTURES

A. Fire Fighting Pump Shelter

Circular hollow pre-stressed concrete piles with 400 mm m' 35 18 630


minimum diameter accordance to site conditions.

B. Garage

Circular hollow pre-stressed concrete piles with 400 mm m' 104 18 1872
minimum diameter accordance to site conditions.

C. Laboratory Building

Circular hollow pre-stressed concrete piles with 400 mm m' 35 18 630


minimum diameter accordance to site conditions.

D. Guard House

Circular hollow pre-stressed concrete piles with 400 mm m' 28 18 504


minimum diameter accordance to site conditions.

E. Elevated Security Houses

Circular hollow pre-stressed concrete piles with 400 mm m' 9 12 108


minimum diameter accordance to site conditions.

F. Mosque (N/A)

Circular hollow pre-stressed concrete piles with 400 mm m' 100 18 1800
minimum diameter accordance to site conditions.

FINAL REPORT XIII - 13


SITE INVESTIGATION STUDY OF PLTG/MG/GU SORONG-2 (50 MW)

CHAPTER 13 .......................................................................................................................................................... 1
13.1. GENERAL ................................................................................................................................................ 1
13.2. BOQ’S PLTG/MG/GU SORONG-2 (50 MW) SORONG LOCATION ................................................... 1

Figure 13.1. Cross Section B-B ........................................................................................................................ 2


Figure 13.2. Cross Section C-C ........................................................................................................................ 2
Figure 13.3. Cross Section D-D ........................................................................................................................ 3
Figure 13.4. Cross Section E-E ......................................................................................................................... 3
Figure 13.5. Cross Section F-F ......................................................................................................................... 4
Figure 13.6. Acces Road Working .................................................................................................................... 6
Figure 13.7. Drainage of the PLTG/MG/GU .................................................................................................... 7
Figure 13.8. Rip-Rap ........................................................................................................................................ 8
Figure 13.9. Segmental of Fence ...................................................................................................................... 9

CHAPTER 13 .......................................................................................................................................................... 1
Table 13.1. Recapitulation of BOQ PLTG/MG/GU Sorong-2 (50 MW) Located in Sorong ........................ 10
Table 13.2. Bill Of Quantity Recapitulation For Piling Works PLTG/MG/GU Sorong-2 (50 MW) Located
In Sorong 11

FINAL REPORT XIII - 14