PVSYST V6.

43 27/01/19 Page 1/4

Grid-Connected System: Simulation parameters

Project : Ghaziabad,U.P
Geographical Site Ghaziabad Country India
Situation Latitude 28.6°N Longitude 77.5°E
Time defined as Legal Time Time zone UT+5.5 Altitude 212 m
Albedo 0.20
Meteo data: Ghaziabad SolarGIS Monthly aver. , period not spec. - Synthetic

Simulation variant : New simulation variant


Simulation date 27/01/19 12h25

Simulation parameters
Collector Plane Orientation Tilt 10° Azimuth -52°
Models used Transposition Perez Diffuse Perez, Meteonorm
Horizon Free Horizon
Near Shadings No Shadings

PV Array Characteristics
PV module Si-poly Model TSM-330PD14
Custom parameters definition Manufacturer Trina Solar
Number of PV modules In series 20 modules In parallel 3 strings
Total number of PV modules Nb. modules 60 Unit Nom. Power 330 Wp
Array global power Nominal (STC) 19.80 kWp At operating cond. 18.63 kWp (40°C)
Array operating characteristics (50°C) U mpp 698 V I mpp 27 A
Total area Module area 116 m² Cell area 105 m²

Inverter Model SG20KTL


Original PVsyst database Manufacturer Sungrow
Characteristics Operating Voltage 480-800 V Unit Nom. Power 20.0 kWac
Inverter pack Nb. of inverters 1 units Total Power 20 kWac

PV Array loss factors


Array Soiling Losses Loss Fraction 3.0 %
Thermal Loss factor Uc (const) 18.0 W/m²K Uv (wind) 0.0 W/m²K / m/s
Wiring Ohmic Loss Global array res. 560 mOhm Loss Fraction 2.0 % at STC
LID - Light Induced Degradation Loss Fraction 2.5 %
Module Quality Loss Loss Fraction 0.0 %
Module Mismatch Losses Loss Fraction 1.0 % at MPP
Incidence effect, ASHRAE parametrization IAM = 1 - bo (1/cos i - 1) bo Param. 0.05

System loss factors


Wiring Ohmic Loss Wires: 3x4.0 mm² 35 m Loss Fraction 2.0 % at STC
Unavailability of the system 1.8 days, 3 periods Time fraction 0.5 %

User's needs : Unlimited load (grid)


PVSYST V6.43 27/01/19 Page 2/4

Grid-Connected System: Main results


Project : Ghaziabad,U.P
Simulation variant : New simulation variant
Main system parameters System type Grid-Connected
PV Field Orientation tilt 10° azimuth -52°
PV modules Model TSM-330PD14 Pnom 330 Wp
PV Array Nb. of modules 60 Pnom total 19.80 kWp
Inverter Model SG20KTL Pnom 20.00 kW ac
User's needs Unlimited load (grid)

Main simulation results


System Production Produced Energy 27.37 MWh/year Specific prod. 1382 kWh/kWp/year
Performance Ratio PR 76.5 %

Normalized productions (per installed kWp): Nominal power 19.80 kWp Performance Ratio PR
8 1.0
PR : Performance Ratio (Yf / Yr) : 0.765
Lc : Collection Loss (PV-array losses) 1.04 kWh/kWp/day
Ls : System Loss (inverter, ...) 0.12 kWh/kWp/day
7 Yf : Produced useful energy (inverter output) 3.79 kWh/kWp/day

0.8
6
Normalized Energy [kWh/kWp/day]

Performance Ratio PR

5
0.6

0.4
3

2
0.2

0 0.0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

New simulation variant


Balances and main results

GlobHor T Amb GlobInc GlobEff EArray E_Grid EffArrR EffSysR


kWh/m² °C kWh/m² kWh/m² MWh MWh % %
January 96.0 13.20 103.7 96.4 1.744 1.691 14.45 14.00
February 122.2 16.20 129.6 121.1 2.121 2.054 14.06 13.61
March 177.1 22.30 185.0 173.5 2.908 2.816 13.50 13.08
April 195.1 29.60 198.4 186.6 2.988 2.892 12.93 12.52
May 196.3 34.50 197.1 185.1 2.926 2.834 12.75 12.35
June 163.9 35.40 162.8 152.5 2.440 2.364 12.87 12.47
July 141.0 32.00 140.5 131.3 2.177 2.109 13.30 12.89
August 148.3 29.80 149.7 140.2 2.329 2.256 13.36 12.95
September 152.7 28.10 156.5 146.7 2.427 2.351 13.32 12.90
October 147.5 24.50 155.9 145.9 2.456 2.380 13.53 13.11
November 111.6 19.50 120.4 112.1 1.962 1.902 13.99 13.57
December 97.8 14.99 106.2 98.6 1.770 1.716 14.32 13.88
Year 1749.5 25.05 1806.1 1689.9 28.247 27.366 13.43 13.02

Legends: GlobHor Horizontal global irradiation EArray Effective energy at the output of the array
T Amb Ambient Temperature E_Grid Energy injected into grid
GlobInc Global incident in coll. plane EffArrR Effic. Eout array / rough area
GlobEff Effective Global, corr. for IAM and shadings EffSysR Effic. Eout system / rough area
PVSYST V6.43 27/01/19 Page 3/4

Grid-Connected System: Loss diagram


Project : Ghaziabad,U.P
Simulation variant : New simulation variant
Main system parameters System type Grid-Connected
PV Field Orientation tilt 10° azimuth -52°
PV modules Model TSM-330PD14 Pnom 330 Wp
PV Array Nb. of modules 60 Pnom total 19.80 kWp
Inverter Model SG20KTL Pnom 20.00 kW ac
User's needs Unlimited load (grid)

Loss diagram over the whole year

1750 kWh/m² Horizontal global irradiation


+3.2% Global incident in coll. plane

-3.5% IAM factor on global

-3.0% Soiling loss factor

1690 kWh/m² * 116 m² coll. Effective irradiance on collectors


efficiency at STC = 17.05% PV conversion

33.55 MWh Array nominal energy (at STC effic.)


+0.1% PV loss due to irradiance level

-11.7% PV loss due to temperature

-2.5% LID - Light induced degradation


-1.0% Module array mismatch loss
-1.3% Ohmic wiring loss
28.25 MWh Array virtual energy at MPP

-2.2% Inverter Loss during operation (efficiency)


0.0% Inverter Loss over nominal inv. power
0.0% Inverter Loss due to power threshold
0.0% Inverter Loss over nominal inv. voltage
0.0% Inverter Loss due to voltage threshold
27.62 MWh Available Energy at Inverter Output

0.0% System unavailability


-0.9% AC ohmic loss

27.37 MWh Energy injected into grid


PVSYST V6.43 27/01/19 Page 4/4

Grid-Connected System: P50 - P90 evaluation


Project : Ghaziabad,U.P
Simulation variant : New simulation variant
Main system parameters System type Grid-Connected
PV Field Orientation tilt 10° azimuth -52°
PV modules Model TSM-330PD14 Pnom 330 Wp
PV Array Nb. of modules 60 Pnom total 19.80 kWp
Inverter Model SG20KTL Pnom 20.00 kW ac
User's needs Unlimited load (grid)

Evaluation of the Production probability forecast


The probability distribution of the system production forecast for different years is mainly dependent
on the meteo data used for the simulation, and depends on the following choices:
Meteo data source SolarGIS Monthly aver. , period not spec.
Meteo data Kind Not defined Year 1995
Specified Deviation Year deviation from aver. 3%
Year-to-year variability Variance 1.0 %

The probability distribution variance is also depending on some system parameters uncertainties
Specified Deviation PV module modelling/parameters 2.0 %
Inverter efficiency uncertainty 0.5 %
Soiling and mismatch uncertainties 1.0 %
Degradation uncertainty 1.0 %
Global variability (meteo + system) Variance 2.7 % (quadratic sum)

Annual production probability Variability 0.74 MWh


P50 27.37 MWh
P90 26.42 MWh
P95 26.16 MWh

Probability distribution
0.50
0.45
P50 = 27366.35 kWh
0.40 E_Grid simul = 27366.35 kWh
0.35
0.30
Probability

0.25
0.20
P90 = 26421.48 kWh
0.15
0.10 P95 = 26155.63 kWh
0.05
0.00
25000 26000 27000 28000 29000 30000
E_Grid system production kWh

You might also like