Professional Documents
Culture Documents
Module - 9
Project
Schedule
Management
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 1
If you skip or fast forward any one slide in this presentation, then the system
will display the following error message and it will NOT allow you to take the
practice test on this module
ERROR MESSAGE
“Sorry you have skipped/fast forwarded one/many slide(s) in this module.
Please go back and re-visit this module from the beginning.
Otherwise it will not allow you to take test”
If you complete all the modules, quizzes and the final exam then only
Course completion certificate will be issued.
You should be able to track your course progress and completion through
your student progress report in the ProXalt LMS login system
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 2
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 3
Project Quality Management • Plan Quality Management • Manage Quality • Control Quality
Project Risk Management • Plan Risk Management • Implement Risk Responses • Monitor Risks
• Identify Risks
• Perform Qualitative Risk Analysis
• Perform Quantitative Risk Analysis
• Plan Risk Responses
Project Stakeholder • Identify • Plan Stakeholder Engagement • Manage Stakeholder • Monitor Stakeholder Engagement
Management Stakeholders Engagement
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 4
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 5
Schedule
Management Plan Project Schedule Network Activity Duration
Activity List Diagrams
Milestone List Estimates
Control Schedule
Develop Schedule
Project Schedule
Schedule Baseline
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 6
Project Charter
Scope Management Plan Expert Judgment
Enterprise Environmental Factors Data Analysis
Input
Organizational Process Assets Meetings
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 7
Project Charter
It provides the high level project descriptions and product characteristics from the
project statement of work
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 8
Meetings
Expert Judgment
Expert judgment guided by historical information provides valuable
insight about the environment and information from prior similar
projects
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 9
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 10
Define Activities
Define Activities
Is the process to identify, clarify, and define key schedule activities that need to be
performed to produce deliverables
Activity List
Activity Attributes
Milestone List
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 11
Scope Baseline
WBS + WBS Dictionary + Scope Statement
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 12
Expert Judgment
Refers to input received from knowledgeable and experienced parties
also called subject matter experts (SMEs). Expertise may be provided
by any group or person with specialized education, knowledge, skill,
experience, or training in developing time management plans.
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 13
Activity List
Is a list of everything that needs to be done to complete your project. This list
is lower-level than the WBS
Activity Attributes
Is the description of each activity is kept. All of the information you need to figure out the
order of the work should be here, too
Milestone List
Is nothing but the major deliverables/event.
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 14
Lag Means delay between two tasks. Some time they call it curing time
Ex: Once you pour the concrete you need to wait 2/3 days to
cure. This time period is called curing time/Lag.
PERT Stands for Program Evaluation Review Technique. Also called 3 point estimate.
Using Pessimistic (P) Optimistic (O) and Most Likely (M) numbers to estimate
project duration.
PERT Formula: P+4M+O/6
Sequence Activities
Sequence Activities
Arrange activities in a logical order based on their dependencies
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 16
The activities will represented by nodes/boxes and the dependency will be shown on the
arrow mark
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 17
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 19
Duration Estimates
Basis of Estimates and
Project Document Updates
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 20
Develop Schedule
Develop Schedule Mgmt. Plan
Schedule
Scope Baseline
Activity List & Attributes
Project Schedule Network Diagram Schedule Network Analysis
Activity Resource Requirements Critical Path Method
Project Scope Statement Resource Optimization
Resource Calendar Simulation
Resource Requirements Leads & Lags
Input List
Milestone Schedule Compression
Enterprise Env. Factors PMIS and
Org. Process Assets Agile Release Planning
Develop Schedule
Process of analyzing activity sequences, durations, resource requirements, and
schedule constraints to create the project schedule model for project execution,
monitoring and controlling
Schedule Baseline
Project Schedule
Schedule Data
Project Calendars
Change Requests
Project Plan & Document Updates
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 21
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 22
• Calculates the early start, late start, end dates, and total floats for all the activities
• In this method, resource dependencies are used to determine the critical path
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 23
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 24
Schedule Baseline
The project schedule developed from the schedule network analysis.
It is accepted and approved by the project management team as the schedule baseline
with baseline start dates and baseline finish dates
In simple words Schedule Baseline is the total number hours/days/weeks/months of
the project.
Schedule Data
Is a collection of information for describing and controlling the schedule.
Information such as resource requirements by time period, alternative schedules (ex: best case,
worst case scenario) and contingency reserves
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 25
Bar/Gantt Charts
Milestone Charts
Marks the completion of major deliverables
Project Calendars & Project Plan, Document updates - Please refer to previous modules
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 26
E F D
7
Start B END
K
3 4 3
A G C
Calculating Slack/Float
4 6 5
E F D
7
Start B END
K
3 4 3
A G C
Formula :
[Critical Path Length] - [Longest Non-Critical Path that has ‘X’ in it]
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 28
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 29
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 30
Calculating PERT
PERT P+4M+O/6
Example:
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 31
Example: Let’s say the sum of PERTS = 103 and Project Variance is 5. Based on these
numbers calculate project duration in 68.26 percentile or 1 sigma level
That means this project can be completed between 98 days to 108 days all most 68%
of the time
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 32
Control Schedule
Data Analysis
Iteration Burndown Charts
What-If Scenario Analysis
Schedule Management Plan Earned Value Mgmt. Analysis
Schedule Baseline Trend & Variance Analysis
Scope Baseline Performance Reviews
Performance Baseline Critical Path Method
Project Schedule PMIS
Project Calendars Resource Levelling
Work Performance Data Leads & Lags
Organizational Process Assets Schedule Compression
Control Schedule
Monitoring the project status and controlling changes to the project schedule
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 33
Control Quality
Control Resources
Control Procurements
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 34
Est. Activity
Project Charter
Control Schedule
Develop Schedule
Project Schedule
Schedule Baseline
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 35
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 36
Critical Path Method Calculates early and late start & end dates and total
floats for all activities
Value Analysis Doing the same scope of work for less cost and
possibly improving quality and performance.
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 37
Bottom-up Used when the project work is well defined. It uses WBS
Estimating and Activity List
End of Module
Printing, copying, sharing or re-producing this material in any form of media violates ProXalt®s Copyright® and PMI® Code of Conduct 20118 Rel 6.0 39