Professional Documents
Culture Documents
Contract Price
Lump-Sum Contract
1
Unit-Price Contract
Cost-Plus Contract
Cost-plus contracts are often used when the scope of work is not fully defined,
or certain elements of the work are hard to determine. In a cost-plus contract,
the owner pays for the actual cost of the work plus either a fixed fee or a fixed
percentage of the construction costs. The owner only pays for the work that is
actually performed, and avoids paying for contingencies that do not
materialize. The contractor, however, has little incentive to minimize costs. As a
result of this concern, the cost-plus contract with a guaranteed maximum price
(“GMP”) emerged.
The cost-plus contract with a GMP is almost identical to the cost-plus contract --
with one significant exception: the risk of excess costs shifts to the contractor if
the costs exceed the Guaranteed Maximum Price. This arrangement gives the
contractor a strong incentive to perform within the GMP. Additionally, this kind
of contract frequently provides that the parties share savings when the cost of
the work is less than the GMP … an additional incentive to the contractor to
keep costs within the owner’s budget.
Contract payment provisions define the form of the request and documents
(e.g. lien releases, schedule updates) required from the contractor. They
determine when a contractor is entitled to request payment, how the amount of
the payment will be computed, who will review the request, when the payment
will be made, and what rights and remedies (e.g., interest, penalties, the right to
stop work) the contractor will have if payment is not received when due.
2
Construction contracts typically provide for payment of the contract price
through progress payments during the course of construction. In lump-sum
contracts, payments are typically calculated based upon the overall
percentage of completion of all work in place, or upon a predetermined value
when designated milestones are completed (e.g., foundation, framing, roofing,
etc.). In cost-plus contracts, the contractor is required to submit records of
actual costs incurred, and is also entitled to overhead and profit, typically
calculated as a percentage of costs.
Contract Time
The contract time clause establishes the duration or deadline for completion of
the work. This time period may be expressed by a number of days from a
“Notice to Proceed”, or in terms of a fixed calendar date. Contractors should
be wary of clauses with a fixed calendar date for completion, especially when
contract negotiations are protracted, design is incomplete, or there is some
constraint on commencement (e.g., permit pending).
When reviewing provisions for time extensions, contractors should analyze what
events are listed as grounds for a time extension (an excusable delay), and
3
what procedures must be followed to submit the request for a time extension
(notice provision). Likewise, the contractor must consider whether the contract
includes a “no damages for delay” clause or a liquidated damages clause. If
these clauses are included, the contractor may be responsible for extra non-
compensable expenses, such as extended job site general conditions costs, if
the duration of the contract is extended -- even assuming that a time extension
is granted. Furthermore, the liquidated damages clause will obligate the
contractor to pay a predetermined amount to the owner if a contract milestone
completion date is not met. These potential costs must be carefully evaluated
by the contractor to estimate the total cost of performance.
Changes
The changes clause in construction contracts is unique to the industry, because
this clause allows the owner to make unilateral changes to the scope of work
without invalidating the contract. Further, the contractor must perform the
changed work, provided it is within the general scope of work contemplated by
the contract.
It is essential that the owner has the right to make changes in the work, so he
can deal with the issues that occur on a daily basis on almost every project. If
the changed work is outside the general scope of the original contract, or if the
owner issues numerous changes resulting in the final work being significantly
different than described in the original contract, the contractor may file a claim
that such changes represent a “cardinal change” or an “abandonment” of the
contract. The contractor does this to avoid the risk that is inherent in a fixed-
price or guaranteed maximum price contract, and recover damages based on
a total cost.
Construction contracts normally allow the terms within the contract only to be
modified through an approved change order, made in writing and signed by
the owner or the owner’s representative. It is important that the contractor
request a written change order for any work not specified in the contract.
Proceeding with a change prior to actually receiving the change order places
the contractor at risk of not receiving payment.
4
If the owner and the contractor cannot agree on a price before the contractor
must perform a change, the contract should specify an alternative method for
determining the compensation to be paid (e.g., time and materials) to the
contractor for the added or changed work (and/or the credit for deleted work).
The contract should also require that the contractor maintain daily records of all
labor and material costs for the changed work, segregated from the base
contract work. The owner usually has a contractual right to issue a unilateral
change directive if the parties are unable to agree on the terms of a change
order, and to direct the contractor to proceed with the work pending the
resolution of any dispute.
5
Termination of Contractor
Construction contracts typically give the owner broad authority to terminate the
contractor either for convenience or for cause (i.e., default). The “termination
for convenience” clause permits the owner to terminate without a reason, and
specifies the method of calculating the amount due the contractor. Typically,
termination for convenience allows the contractor to be compensated for the
contract value of the work in place, overhead and profit on work performed,
and costs of demobilizing and canceling subcontracts.
The “termination for cause” provisions in the construction contract afford the
owner the right to terminate the contractor upon certain events such as: failure
to supply enough skilled workers or proper materials; failure to pay
subcontractors and suppliers; disregard of applicable laws; or substantial breach
of a provision of the contract.
After written notice of the grounds for default and contractor’s failure to cure,
the owner may terminate the contractor. The owner then may enter the site,
exclude the contractor from the site, and take possession of the contractor’s
tools, equipment, and material. Once the contractor has been terminated for
cause, he is not entitled to receive any further payments until the work is
complete. The owner is allowed to offset any amounts owed to the contractor
by the costs incurred in completing the work. If the cost to complete the project
exceeds the unpaid contract balance, the owner can recover the excess as
damages from the contractor.
Summary
6
understanding the key issues and resulting responsibilities and risks will assist the
parties in tailoring contract clauses to clearly guide the parties through the
project.