Weekly Progress Report as on 12.03.

2019
Sub-Contractor- INVENTA

1. As per Target set for 31st May 2019.


2. Total Wall Panels to be erected for cluster-1 – 758 Nos.
3. Total Hollow Core Slabs to be erected for cluster-1 - 1818 Nos.
4. Total Wall Panels to be erected for cluster-2 – 1536 Nos.
5. Total Hollow Core Slabs to be erected for cluster-2 - 4368 Nos.

Cluster-1 (Total Blocks-5)


Wall Panels Erection Status HCS Erection Status
Month- March
Target Short Target Short
2019 Achieved Achieved Reason for Short Fall
Per Fall Per Fall
Week Week
Week -01  Poor Planning
(01.03.19 – 252 97 155 602 211 391  Delay in transportation of
08.03.19) HCS & Wall Panels
Week -02
(09.03.19 –
15.03.19)
Week- 03
(16.03.19 –
22.03.019)
Week- 04
(23.03.19 –
31.03.19)
Cluster-2 (Total Blocks-4)
Wall Panels Erection Status HCS Erection Status
Month- March Target Short Target Short
2019 Per Achieved Fall Per Achieved Fall Reason for Short Fall
Week Week
Week -01
(01.03.19 –
08.03.19)
Week -02
(09.03.19 –
15.03.19)
Week- 03
(16.03.19 –
22.03.019)
Week- 04
(23.03.19 –
31.03.19)

Note: -

Cluster- 1

1. Measures adopted to achieve for week-2 = 221 No. of Wall Panels


2. Measures adopted to achieve for week-2 = 535 No. of Hollow Core Slabs

Cluster- 2

1. Measures adopted to achieve for week-2 =


2. Measures adopted to achieve for week-2 =
Sub-Contractor- PSV

1. As per Target set for 31st May 2019.


2. Total Wall Panels to be erected for Block No. 26 (A & B) – 273 Nos.
3. Total Hollow Core Slabs to be erected for Block No. 26 (A & B) - 707 Nos.

Block No. 26(A & B)


Wall Panels Erection Status HCS Erection Status
Month- March Target Short Target Short
2019 Per Achieved Fall Per Achieved Fall Reason for Short Fall
Week Week
Week -01  Lack of lifting machinery-
(01.03.19 – 77 18 59 168 152 16 Tower Crane is using for
08.03.19) stitch
 Concrete Works- Which
delays in Wall Panel & HCS
Erection.
Week -02
(09.03.19 –
15.03.19)
Week- 03
(16.03.19 –
22.03.019)
Week- 04
(23.03.19 –
31.03.19)

Note: -

Block No. 26(A & B)

1. Measures adopted to achieve for week-2 = 37 No. of Wall Panels


2. Measures adopted to achieve for week-2 = 80 No. of Hollow Core Slabs
Sub-Contractor- PRIME

1. As per Target set for 31st May 2019.


2. Total Wall Panels to be erected for Block No. 29, 30 & 31 – 574 Nos.
3. Total Hollow Core Slabs to be erected for Block No. 29, 30 & 31 - 1414 Nos

Block No. 29, 30 & 31


Wall Panels Erection Status HCS Erection Status
Month- March Target Short Target Short
2019 Per Achieved Fall Per Achieved Fall Reason for Short Fall
Week Week
Week -01  No Proper erection teams
(01.03.19 – 189 49 140 469 101 368 for HCS & Wall Panels
08.03.19) erection.
Week -02
(09.03.19 –
15.03.19)
Week- 03
(16.03.19 –
22.03.019)
Week- 04
(23.03.19 –
31.03.19)

Note: -

Block No. 29, 30 & 31

1. Measures adopted to achieve for week-2 = 82 No. of Wall Panels


2. Measures adopted to achieve for week-2 = 202 No. of Hollow Core Slabs