To clearly understand the bar bending schedule of a pile foundation, it is necessary to be familiar about the typical
reinforcement details of a pile foundation. Pile foundation is a common type of deep foundation, used for
supporting heavy loaded structures when the site under consideration have a very weak soil that is compressible
in nature.
Table of Contents
Layout of a Typical Pile Foundation
Structural Specification and Reinforcement Details of a Pile Foundation
Calculation for Bar Bending Schedule of Pile Foundation
Step 1: Length of Vertical Reinforcement
Step 2: Inner Spacing Ring – Number and Length of each Ring
Step 3: Outer Helical Ring – Number and Length of each ring
Step 4: Bar Bending Schedule
https://theconstructor.org/structural-engg/pile-foundation-bar-bending-schedule-calculations/20989/?utm_source=pushengage&utm_medium=push_n… 1/5
12/5/2018 Bar Bending Schedule for Pile Foundation with Calculations
The whole arrangement is clearly understood from the figure-2. The pile cage has vertical reinforcement held
together by outer and inner rings. The Reinforcement in pile construction include:
1. Vertical Reinforcement
The above details are mentioned in the figure-3 below. The Outer rings are provided as helical rings and the inner
is circular or spiral ties.
https://theconstructor.org/structural-engg/pile-foundation-bar-bending-schedule-calculations/20989/?utm_source=pushengage&utm_medium=push_n… 2/5
12/5/2018 Bar Bending Schedule for Pile Foundation with Calculations
The development length ‘Ld’ is provided outside of the column piercing into the pile cap. The anchorage length to
the recommended amount is provided to the bottom of the column as shown in figure-2.
3. Diameter of:
1. Vertical Reinforcement = 20mm – 12nos
https://theconstructor.org/structural-engg/pile-foundation-bar-bending-schedule-calculations/20989/?utm_source=pushengage&utm_medium=push_n… 3/5
12/5/2018 Bar Bending Schedule for Pile Foundation with Calculations
Total Cutting Length for Vertical Reinforcement = Anchorage Length at the bottom of the pile + the
height of the pile + development length (40d) + Lap length (50d) – clear cover provided at the
bottom.
i.e. Lv = 300 + 20000 + 40d +50d -75 = 300 + 20000+ (40 x 12) + (50 x 12) – 75
Note: During tying the bar, it is recommended to tie at the middle, as tying at the ends of the bars will be
subjected to higher stress values.
= [20000/2000] +1 = 11 No’s
The circumference of the ring gives the length of each ring. For this the radius of the ring has to be determined.
Given the radius of the pile, the clear cover, outer ring radius:
The radius of the ring = [Radius of the pile – clear cover – diameter: of outer ring – diameter: of
vertical reinforcement:]/2
https://theconstructor.org/structural-engg/pile-foundation-bar-bending-schedule-calculations/20989/?utm_source=pushengage&utm_medium=push_n… 4/5
12/5/2018 Bar Bending Schedule for Pile Foundation with Calculations
Specification Diameter of Bars (m) No. of Bars (m) Length of rods (m) Total Length (m)
Neenu Arjun
Neenu is a Civil and Structural Engineer and has experience in Design of Concrete and Steel Structures. She is an Author, Editor and Partner at