Professional Documents
Culture Documents
Design Guidelines
Prepared For
Document Control Sheet
Final Report
Issue Authorised
Date Description/Amendment Checked Reviewed
No for Issue
This report has been prepared solely for the benefit of Abu Dhabi Transmission and Despatch Company
(TRANSCO). No liability is accepted by this company or any employee or sub-Consultant of this company
This disclaimer shall apply notwithstanding that the report may be made available to other persons for
Table of Contents
1 Introduction .................................................................................................................................... 5
2 Resource Documents ...................................................................................................................... 6
3 Studies ............................................................................................................................................. 7
3.1 Hydraulics ..................................................................................................................... 7
3.2 Geotechnical & Geophysical Studies ............................................................................ 23
3.3 Environmental Studies ................................................................................................ 69
3.4 Pipe Wall Thickness Determination.............................................................................. 71
3.5 Pipe Stress Analysis ..................................................................................................... 75
3.6 Power Supply .............................................................................................................. 81
4 General Design Requirements ...................................................................................................... 82
4.1 Design Life Cycle.......................................................................................................... 82
4.2 Demand Calculations ................................................................................................... 82
4.3 Material Selection ....................................................................................................... 82
4.4 Design Loads ............................................................................................................... 83
4.5 Drawing Requirements ................................................................................................ 83
4.6 Approvals ................................................................................................................... 89
4.7 Health Safety Environment & Quality (HSEQ) ............................................................... 89
4.8 HAZID / HAZOP ........................................................................................................... 91
4.9 Operation & Control Philosophy (OCP)......................................................................... 91
4.10 Value Engineering ....................................................................................................... 95
4.11 Risk Management ....................................................................................................... 95
5 Civil Works .................................................................................................................................... 96
5.1 Design Codes............................................................................................................... 96
5.2 Topographic Survey ..................................................................................................... 97
5.3 Geotechnical Investigations ......................................................................................... 97
5.4 General Civil / Structural Requirements – Pump Stations.............................................. 98
5.5 General Civil / Structural Requirements – Reservoirs .................................................. 111
5.6 Drawing Requirements .............................................................................................. 119
5.7 Design Data............................................................................................................... 120
6 Electrical Works .......................................................................................................................... 128
6.1 Introduction .............................................................................................................. 128
6.2 Design Philosophy ..................................................................................................... 129
6.3 Concept Design ......................................................................................................... 130
Page 2 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
6.4 Preliminary Design .................................................................................................... 131
6.5 Design Requirements ................................................................................................ 132
6.6 Studies ...................................................................................................................... 146
6.7 Small power and Lighting .......................................................................................... 153
7 Mechanical Works....................................................................................................................... 156
7.1 Design Codes............................................................................................................. 156
7.2 Water Transmission Pump ......................................................................................... 156
7.3 Pump Station Piping .................................................................................................. 159
7.4 Mechanical Work ...................................................................................................... 163
7.5 Storage Tank System ................................................................................................. 166
7.6 Electro Chlorination Systems ..................................................................................... 168
7.7 Surge Protection Systems .......................................................................................... 170
7.8 Motor Cooling System ............................................................................................... 172
7.9 Anti-Flooding System ................................................................................................ 173
7.10 Fire Fighting System .................................................................................................. 174
7.11 HVAC System ............................................................................................................ 176
7.12 Well System .............................................................................................................. 182
7.13 Tap-Off Station system .............................................................................................. 183
7.14 Diesel Fuel Storage and Transfer ................................................................................ 185
8 I&C Works ................................................................................................................................... 187
8.1 Introduction .............................................................................................................. 187
8.2 Preliminary design..................................................................................................... 189
8.3 Final design ............................................................................................................... 190
8.4 Design Criteria........................................................................................................... 191
8.5 Control System Architecture ...................................................................................... 193
8.6 Process Requirements and Field Devices .................................................................... 194
8.7 Major Automation Hardware and Software ............................................................... 200
8.8 Telecommunications Requirements ........................................................................... 207
8.9 Security..................................................................................................................... 209
9 Pipelines ...................................................................................................................................... 211
9.1 Introduction .............................................................................................................. 211
9.2 Design Codes............................................................................................................. 211
9.3 Input Data................................................................................................................. 212
9.4 Topographical Survey ................................................................................................ 213
9.5 Geotechnical Survey & Soil Tests ............................................................................... 213
9.6 Material Selection ..................................................................................................... 214
Page 3 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
9.7 Design of Ductile Iron Pipelines ................................................................................. 214
9.8 Design of Carbon Steel Pipelines ................................................................................ 217
9.9 Design of High Density Polyethylene Pipelines ........................................................... 218
9.10 Alignment Selection .................................................................................................. 220
9.11 Pipe Profile ............................................................................................................... 221
9.12 Valves ....................................................................................................................... 222
9.13 Fittings & Accessories ................................................................................................ 224
9.14 Pipe Installation ........................................................................................................ 226
9.15 Thrust Restraint ........................................................................................................ 229
9.16 Corrosion Protection ................................................................................................. 231
9.17 Contamination & Permeation Protection ................................................................... 232
9.18 Testing & Commissioning .......................................................................................... 232
Page 4 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
1 Introduction
These TRANSCO Design Guidelines were developed under project N-14054, commencing in July 2016
by the appointed Consultant, MWH Global. The Design Guidelines were developed in conjunction with
the TRANSCO Particular Specifications and Standard Detail Drawings.
Prior to the development of these guidelines, TRANSCO was communicating design requirements to
external entities individually. These guidelines take into consideration previously established and
applied practises, and build upon them based on the institutional knowledge within TRANSCO’s
various departments which has developed over many years of practical experience. These guidelines
also include improvements based on internationally accepted best practices.
These guidelines are applicable to the design of water infrastructure for TRANSCO. They are applicable
to the project lifecycle from the planning / concept stage, to design, and construction. These
guidelines are applicable internally and externally, including to Consultants, Contractors, and other
entities responsible to the design and construction of TRANSCO assets.
The guidelines are set out in 9 sections plus Appendices. Each of these sections are described as
follows:
• Section 1 Introduction
• Section 2 Resource Documents –This section lists the related documents of ADWEA and other
stakeholders which are to be read in conjunction with the design guidelines
• Section 3 Studies - covers the areas of hydraulic steady state and transient modelling,
geotechnical and geophysical investigations, environmental planning and regulatory
requirements, pipe stress analysis and power supply studies
• Section 4 General Design - sets out the general requirements of demand calculations, design
loads, operation and control philosophy, drawing requirements, approvals, HSEQ, and
HAZID/HAZOP studies
• Section 5 Civil Works Design - covers the civil aspects of TRANSCOs facilities including pump
stations, reservoirs, pipelines and interface points
• Section 6 Electrical Design - sets out the electrical requirements for the pumping station and
associated facilities
• Section 7 Mechanical Design - sets out the mechanical aspects of pump stations, pipelines and
reservoirs
• Section 8 Instrumentation and Control - sets out the control requirements as well as SCADA
and communications requirements to operate the system
• Section 9 Pipelines design - sets out the requirements for design of Carbon Steel, Ductile Iron
and HDPE pipelines
Page 5 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
2 Resource Documents
These guidelines shall be considered in conjunction with the ADWEA Standard Specifications,
TRANSCO Specifications, Standard Detail Drawings, the scope of works for individual projects, and the
reference documents detailed herein.
These guidelines were developed in general accordance with stipulations of the following documents:
In addition to the above documents, Designers of TRANSCO projects should take into account
guidelines from stakeholder organisations such as Abu Dhabi Urban Planning Council Manuals and
Guidelines, Abu Dhabi Municipality Manuals and Guidelines and similar documents from elsewhere in
the UAE.
If a conflict occurs between these Guidelines and the reference documents, the Guidelines shall
generally take precedence subject to agreement with TRANSCO Engineer.
Page 6 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
3 Studies
3.1 Hydraulics
These guidelines are issued for the use of Consultants and Contractors on design and construction
contracts for TRANSCO. They are to be read in conjunction with the latest versions of the following
documents:
Hydraulic calculations and modelling are required at the following stages of project development:
This document explains the process for conducting hydraulic modelling and covers three aspects of
the hydraulic design process:
There are common data requirements and approaches for all three aspects. These are addressed in
the following sections.
Page 7 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Air vessels data (operation levels, controls & dimensions)
TRANSCO’s preferred steady state hydraulic modelling software is InfoWater (Innovyze Inc., USA). The
latest version of InfoWater software shall be used for all calculations. Water quality modelling shall
also be conducted using InfoWater software.
Where approved by TRANSCO, steady state hydraulic modelling may be conducted in EPANET (EPA,
USA) or any other software which is compatible with EPANET or Infowater.
TRANSCO’s surge (transient) modelling software is WANDA (Deltares, Netherlands). All design surge
calculations shall be conducted in WANDA. However, other surge modelling software which are
compatible with WANDA can be used for basic surge simulations subject to approval of TRANSCO.
Approval would be subject to comparison by test case. Test case to be proposed by the designer and
should include a comparison from Streeter and Wylie plus one comparison involving air valve opening
and closing.
A copy of all hydraulic, water quality and surge models shall be provided to TRANSCO on completion
of design studies. Models shall be delivered in WANDA files format for surge and in INFOWATER or
EPANET format for steady state whichever is available with TRANSCO.
If another surge software is used with TRANSCO permission, all surge models provided to TRANSCO
shall be compatible to WANDA and shall run on TRANSCO system without any error or alerts. All such
conversions shall be performed prior to the submission and TRANSCO may allow Consultants Engineer
to have these conversions in TRANSCO office subject to availability of licence. Duration of such
permission will not exceed one week. No computer will be provided by TRANSCO and no design work
will be allowed in TRANSCO office.
Models shall be submitted with all submissions and works that are related to hydraulics and surge and
for which TRANSCO review is required. Models shall be delivered in WANDA files format for surge and
in INFOWATER or EPANET format for steady state whichever is available with TRANSCO.
All surge models compatible to WANDA format shall be provided. All scenarios/cases analysed by the
Consultant shall be submitted and separate files shall be provided with complete data to TRANSCO.
All components in WANDA e.g. pipes, pumps, valves, vessels etc. shall include notes indicating the
necessary details not limited to the following;
Pipeline
Equipment
Page 8 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
3.1.3 General Design Parameters
3.1.3.1 Pipe Roughness
Losses in the pipeline depends on the roughness of the internal surface of the pipeline. Roughness will
vary with pipe material, type of coating and age of the pipeline. Pipeline hydraulic calculations shall
use the Darcy Weisbach - Colebrook-White equation for calculating the friction losses.
H L = f L V2 / 2gD
Where
f = friction factor (symbol “l” lambda also used for friction factor in some references)
L = length, m
V = velocity, m/sec
D = diameter of pipeline
Friction factor ‘f’ shall be calculated using Colebrook White equation which is given below
Where,
f = friction factor
d = diameter, m
R e = Reynolds Number
k s = roughness of pipe, m
Page 9 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Ductile Iron lined with Cement 0.15 0.05 – 0.30
Mortar
Polyethylene
0.06 0.01 – 0.15
Polyurethane
0.02 -
Control valve characteristics (Minor Loss or Kv against Position) shall be determined from
manufacturer data. Consultant shall provide the head loss and flow values against various percentages
of openings and the required values of Kv, Xf (cavitation index) for the equipment selection. Other
minor loss coefficients may be obtained from appropriate industry look-up tables. A table of typical
values for common network fittings is given in Table 3.2 below.
Table 3.2 – Minor Fittings Loss Coefficients.
Page 10 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Fitting Loss Coefficient ‘K’ Fitting Loss Coefficient ‘K’
Note: minor losses can also be taken from tables in WANDA software. Examples from WANDA include
Bends(R/D=1.5)
Minor losses through the fittings can be calculated using the loss coefficient given in Table 3.2 and
using the following formula
h m = K V2 / 2g
Where
V = velocity, m/sec
K = loss coefficient (“xi” also used for loss coefficient in some references)
For discrete losses, handbook of Hydraulic Resistance by Idelchik shall be used and reference shall be
provided. However, if any other similar book is proposed by the Consultant, it shall be first approved
from the TRANSCO and two (2) copies of reference shall be provided to TRANSCO for approval.
Page 11 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
For proposed/new systems the pump curves shall be obtained from the pump manufacturer and same
shall be used in the analysis.
For existing system, in addition to the manufacturer data, the in situ pump curves shall also be plotted
and evaluated. The in situ curves can be plotted by taking the measurements of the pump
head/pressure against various flow rates by varying the system resistance. If in situ (site
measurement) curve is different than the original design, the actual measurements shall be used with
prior approval from TRANSCO.
Pump and motor inertia shall be obtained from the manufacturer and combined inertia shall be used.
In case these are not available at initial stage, these shall be calculated using the below equations for
pumps and motors. However, in detailed design actual inertia from manufacturer shall be used.
0.844
P
I P = 0.03407 3
N
Where
P = Pump power, KW
In transmission systems, the minimum steady state pressure is commonly governed by system
topography. At local high points or at Terminal Stations, the minimum pressure shall be maintained
between 3 and 5 metres, in order to maintain sufficient positive pressure to (a) prevent contaminant
intrusion and (b) ensure correct seat of air valves on the line. When designing for steady state
conditions, consideration should be given to transients possibly causing lower pressure at local high
points. Pressure should be determined relative to top of pipe (soffit) or air valve float as appropriate.
Page 12 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Maximum steady state pressure in transmission systems is determined by the designer and designated
as Design Pressure (DP). The Design Pressure should encompass the envelope of all normal operating
conditions, such as pump on, pump off, static system, maximum demand and minimum demand at all
design horizons (e.g. current and future years).
Definitions of various Pressure terms and abbreviations are given in Table 3.3 below.
Table 3.3 - Various Pressure terms, abbreviations and definitions
Site Test Pressure (STP) is the pressure at which system shall be tested at the site. The requirements
of Site Test Pressure (STP) for various pipe materials are given below.
For Ductile Iron, Carbon Steel and GRP pipes, the Site Test Pressure (STP) shall be considered equal to
the pressure rating of the pipeline. The pipe pressure rating shall not be less than 1.5 times the
maximum operating pressure in the system.
For HDPE pipelines, the Site Test Pressure (STP) shall be considered equal to the rated pressure of the
pipeline. Note that while selecting the pipe pressure class, temperature de-rating shall be considered
as per manufacturer recommendations and pipe pressure rating at design temperature (after applying
temperature de-rating factor) shall not be less than 1.5 times the maximum operating pressure in the
system.
All thrust blocks, anchor blocks and restraining systems on the pipelines shall be designed for the Site
Test Pressure (STP).
For long pipelines which have high static head, the site tests can be carried out in segments of the
pipeline with proper isolation. Individual segments shall be tested at STP, any valves and other
equipment in the test section shall be suitable to withstand the applied pressure. Additionally, any
pipe segments with low levels shall be specially checked against any additional pressure due to
topography. All individual segments shall be tested at the selected STP. All thrust blocks shall be
designed considering the STP of the pipeline.
All as built drawings shall include the information of Design Pressure (DP), Maximum Design Pressure
(MDP) and Site Test Pressure (STP) of the pipelines.
Page 13 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
3.1.3.7 Boundary Conditions
The hydraulic model should encompass defined hydraulic boundaries such as tank, customer
discharge, levels, elevations, pressures, etc. as necessary for accurate analysis of the system. The
designer should be aware of the contractual boundary between TRANSCO and DISCO assets but the
model should not be limited to this extent artificially. Simplification of the DSCO network is permitted
in the model when insufficient data are available for a more detailed representation.
The designer shall liaise with the appropriate Stakeholders to obtain information on the downstream
distribution system. The Designer shall collect all necessary information, prepare files, complete forms
and agree with the consumer.
Specifically in the case of direct connection with either new or modification of connection with
customer the designer needs to ensure that he collects all necessary paramaters as requested in Direct
Connection Procedures. He needs to have the Direct Connection Application Form signed and stamped
by DISCO.
In calculation of wave speed ignore the concrete lining thickness. Typical Young Modulus values for
various materials are given in Table 3.4 below. These can be used in the analysis.
Table 3.4 – Typical Youngs Modulus Values for Various Materials
Asbestos cement 23 – 24
Concrete 14 – 30
Concrete (reinforced) 30 – 60
GRP 11 - 13
GRE 13 - 15
Page 14 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
3.1.4.2 Valves
The properties of all types of valves e.g. flow control valves, non-return/check valves, pressure
regulating valve, air valves etc. included in the system, shall be obtained from the manufacturer and
same shall be used in the analysis. Inlet and outlet of the air valves shall be properly designed to avoid
negative pressure in the pipeline and shall not result air slam due to rapid expulsion of air during surge
event or priming/pump start up. The adopted properties of all types of valves and their operational
ranges shall be included in the report.
Check Valve
When selecting the check valve type, consideration shall be given to check valve dynamic closing
characteristics and consequence of check valve slam on surge. Ideally, valves shall be selected based
on their surge response following surge analysis. Recommendations of the surge report shall include
appropriate check valve type (instead of selecting the check valve first and then trying to mitigate
surge effects caused by that particular valve). A fast acting non slam type check valve is preferred.
Reverse velocity characteristic of the selected check valves shall be obtained from manufacturer to
allow for modelling of the valve dynamic characteristics in surge software.
Pressure relief valves are to be located in a chamber with instrumentation to monitor water level to
ensure the chamber is not full and is ready to receive additional flow from the pressure relief valve.
Minimum surge pressure shall be 0 bar gauge (atmospheric) with a target pressure of 3 to 5 metres at
air valves, if economically achievable (Case 1). This will prevent air entry into the pipeline. Negative
pressure is not allowed in any segment of the pipeline including the high points. If design is
uneconomical TRANSCO may advise to apply Case 2, e.g. by allowing air entrapment particularly on
pipeline with challenging profile/sections)
At critical locations e.g. high points along the pipeline profile, the inlets and out lets of the air valves
shall be properly sized. Air valves shall be sized to prevent any negative pressure in the pipeline during
surge event. Special consideration shall be given to the sizing of outlets of air valves and these shall
be designed to avoid air slam due to rapid air expulsion including during start-up of pumps. . At high
points (if required) additional air valves can be provided to prevent the negative pressure, however,
air outlet capacities shall be checked against start up conditions to prevent air valve slam due to rapid
air release. All such special cases are subject to TRANSCO approval.
Page 15 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Additionally, all air valves along the pipeline shall be adequately sized and shall allow normal operation
of the washouts in case of pipe draining during maintenance.
The Consultants shall provide all surge analysis scenarios for the following two cases;
Case-1: If communication system e.g. SCADA control, Fibre Optic Cable (FOC) is available.
Case-2: If communication system e.g. SCADA control, Fibre Optic Cable (FOC) is not working due
to any reason.
As mentioned above, the negative pressure in the pipeline is not allowed. However, only in Case-2
when communication system (No FOC, SCADA) is not available and negative pressure cannot be
avoided, a negative pressure up to -5 m may be allowed subject to TRANSCO approval and structural
stability of the pipeline.
For suction pipelines, minimum allowable pressure during surge event is -5 m. All pipes, pipe supports,
bends, joints shall be designed to withstand the resulting pressure and detailed calculations shall be
submitted to TRANSCO for approval.
Definitions of various pressure terms are presented in Table 3.3 in earlier section. All new pipelines
shall be tested at the pipe pressure rating as described in Section 3.3.3.6 and accordingly all thrust
blocks on the pipeline shall be designed for the Site Test Pressure (STP). For further details of thrust
blocks design refer to Section 5.
The Maximum Design Pressure (MDP) is the maximum operating pressure including surge. MDP must
always be less than System Test Pressure (STP). Maximum surge pressure should be less than 1 bar
below STP (ref BS EN 805), the equation of BS EN 805 is given below.
Maximum Design Pressure including surge Calculated (MDP) = System Test Pressure (STP) - 1 bar
Pipelines should be structurally designed to at least STP (positive pressure) and full vacuum (negative
pressure). Hence, all pipes and fittings on the project should be rated to at least STP.
Page 16 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The designer should be cognisant of the minimum pressure limits for pipelines. This normally
precludes the use of air valves for surge protection. However, in exceptional circumstances air valves
may be designed specifically for surge control. These circumstances include intermediate high points
(consider rerouting pipelines to avoid) or locations above hydraulic grade when the system is at rest.
The designer should ensure that suitable air valve types are specified (e.g. anti-shock or anti-slam type)
and the required locations are identified in the design report. Consideration should be given for in-
built redundancy of air valves (i.e. N+1 design philosophy) where the surge control relies on these
devices. Software used for the surge analysis shall be capable to simulate the air valves inlet and out
let air flow vs pressure curves provided by the manufacturer.
Surge Vessel:
System shall be designed considering one surge vessel out of operation so an in built redundancy of
surge vessels (i.e. N+1 design philosophy) shall be adopted. Surge vessels air charge should be
provided considering one vessel out of operation.
Surge vessel air management systems comprise; mass control, 5-point level control, variable level
control, fixed mass (bladder), P-V or PV-T control. TRANSCO’s preference is for mass control. The
designer should justify selection of the recommended method of air control in their surge analysis
report.
Surge vessel designs should be optimised for minimum acceptable total vessel volume (i.e. minimum
cost) at each location. Consultant shall provide the details of surge vessels e.g. operation levels,
control philosophy and dimensions of the vessels. In the report all operational levels e.g. High high
level, high level, low level, low low levels etc. and actions associated with these levels shall be
Page 17 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
described in detail. Air release from the surge vessel shall be automatic, compressor & air release
system shall be designed accordingly.
Air Compressor:
Air Compressor and air piping design (for air vessels) should consider requirements for; initial filling
and commissioning, daily operation, and occasional maintenance, which will require markedly
different air flow rates. Initial filling of surge vessels can be by mobile compressor whereas the daily
operation shall be by in-situ compressor. In-situ compressor shall have a capacity that re-filling of one
surge vessel can be accomplished in 4 hrs in case of maintenance.
The following table sets out the design criteria for compressors
Table 3.5 – Design Criteria for compressors
Dissolution of air Very small volume (similar to a dive bottle Unscheduled activity
4
into water compressors Infrequent (<monthly)
Page 18 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
demonstrate compliance with the Regulations. This is normally achieved using the InfoWater water
quality modelling option.
The key parameter governing chlorine decay in pipe networks is the bulk decay constant (when using
the first order decay algorithm). Typical values can be obtained from TRANSCO however TRANSCO
require the designer to establish the relevant bulk decay constant via laboratory testing. A procedure
for laboratory testing (black bottle test) including sampling, initial testing, incubation, post incubation
testing etc. is to be agreed with TRANSCO. The value of bulk decay constant to be used for chlorine
residual modelling after black bottle test shall be approved from TRANSCO.
InfoWater water quality modelling algorithms also allow pipe wall decay to be considered. For
transmission pipelines, the wall decay coefficient can be considered as zero (0). However, where
appropriate, wall decay constants may be established by field testing and model calibration. Reference
should be made to industry standard procedures for water quality modelling (e.g. Characterization of
Decay …., Vasconcelos, Boulos, et al). Water quality modelling simulations shall be carried out at early
year and for the milestone years between early year and the planning horizon.
Water Quality modelling shall be carried out in the detailed design stage. However, if significant
difference is expected in WQ requirements in various design options of preliminary design, a focused
study shall be included in the Preliminary Design Report (PDR). Detailed Design Report (DDR) shall
include complete WQM, design of proposed system and specifications of proposed equipment.
Maximum chlorine levels should be controlled in order to limit potential for formation of Disinfection
By-Products (DBPs).
The steady state design should consider the full operating range of pressure and flow for the project
design horizons (i.e. current and future cases). This includes minimum demand, average demand and
maximum design demand (see Section 3.1.3.5). Normal and emergency cases should be examined.
The objective of steady state design cases is to ensure that the complete range of operating conditions
is considered in analysis. Hence it is sufficient for the designer to address cases that define the
operating envelope. However, for pump selection purposes the normal operating cases should also
be analysed.
Preliminary Design Report (PDR) shall include the hydraulic analysis of all scenarios and details of
equipment. Detailed Design and Final Design Report shall incorporate the final profiles of the pipelines
and final selection of the equipment.
Page 19 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The design report should include:
a. Hydraulic Profile
Comprising longitudinal section of pipeline with ground elevation / pipe profile, normal, maximum
and minimum hydraulic grade line (HGL) above datum
b. Pressure/Head Profile
Comprising pressure-distance plot along pipeline with normal, maximum and minimum pressure,
and pipe Standard Test Pressure superimposed.
Comprising pump(s) and system curve for normal, maximum and minimum static head
d. Valves
Comprising details of Flow Control Valves (FCV) and Pressure Control Valves (PCV), operating
range (minimum & maximum), operational requirements and hydraulic characteristics against
various flow conditions (20 % to 100%) e.g. Kv, Xf (cavitation index) etc. Control valve opening
below 5% is not acceptable.
Reporting
The Steady State Hydraulics Report shall contain the following sections as a minimum:
• Criteria
• Executive Summary
• Document Tracking
• Project Objectives
• Data Collection
• Design Case Definition (includes design flows)
• Description of Model Build
• Modelling Outcomes (including hydraulic profile, pressure /head profile, pump and system
curves, valves, tanks at high and low water levels)
• Proposed System Requirements (pumps, surge equipment, water quality, pressures, control
philosophy, summary table for control valves SCADA, equipment etc.)
• Conclusions and Recommendations
The surge design cases shall be selected to cover the full envelope of maximum and minimum pressure
in the system under consideration. Surge analysis shall be carried out in both the final design stage
and detailed design stage. However, if significant difference in the surge vessel requirements is
expected in design options of preliminary design stage (due to topography, route etc.), a focused study
shall be included in the Preliminary design Report (PDR). In both Final design and Detailed design,
Consultant shall carry out the complete surge analysis. The Detailed Design Report (DDR) shall include
the detailed surge analysis, plus design of equipment and their specifications.
Page 20 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Consultant shall analyse the critical, emergency and typical operational scenarios under their design.
Typically this will include consideration of:
TRANSCO can ask for any additional project specific scenarios in addition to above. Proposed
equipment (valves, vessels, air valves) shall be able to work in all scenarios, however, these shall
be designed considering the critical scenarios associated with the equipment performance. Some
of the typical scenarios and basis of design of typical equipment is shown in Table 3.5 below.
Table 3.6: Some typical scenarios and equipment design basis
Full Pump Trip FTP Surge vessel, check valve & air valve
Pump Stop & Re-start PSRS Air valve inlet and outlet
• Air vessel water level (e.g. Low, Low Level and High, High Level)
• Gas Expansion Coefficient (Laplace Coefficient) from adiabatic to isothermal
Where necessary, the designer should also carry out a sensitivity test for unknown parameters (see
Section 3.1.3.1).
Reporting
In addition to the requirements set out under steady state reporting, the Surge Analysis Report shall
contain the following sections as a minimum:
Page 21 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Proposed Surge System requirements
• Conclusions and Recommendations
Modelling for water quality (chlorine residual) should consider the full range of operating scenarios
for current and future design horizons. It is sufficient to ensure that the envelope of maximum and
minimum water quality is addressed for each design phase. Water Quality modelling shall be carried
out in the detailed design stage. However, if significant difference is expected in WQ requirements in
various options of preliminary design, a focused study shall be included in the Preliminary Design
Report (PDR). Detailed Design Report (DDR) shall include complete WQM, design of proposed system
and specifications of proposed equipment.
Reporting
The Water Quality Report shall contain the following sections as a minimum:
Page 22 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
As such these standards and practices are to be followed as the minimum and more details, standards
or specifications may be required dependent on the specifics of the project. The Consultant shall
perform Geotechnical soil Investigation and Geophysical investigation in line with ADWEA Standard
Specification Ref. W – C – SS – 002. Consultant's services include performance of subsurface
exploration by borings involve performing the Standard Penetration Tests, the Rock Quality
Designation and the Shear Vane Test (SPT, RQD & SVT) where found necessary. Sampling, cone
penetration tests, test/trial pits, field and laboratory testing, geotechnical analysis and the preparation
of preliminary and final geotechnical reports.
The Geotechnical and Geophysical soil investigations work under these Guidelines shall consist of
conducting a complete soil investigation for the adequate design and construction of the entire civil
works belong to the water works.
Before designing the investigation programme, the available information and documents should be
evaluated in a desk study.
Examples of information and documents that can be used are, but not limited to:
Page 23 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Topographical maps.
Ground investigations should provide a description of ground conditions relevant to the proposed
works and establish a basis for the assessment of the geotechnical parameters relevant for all
construction stages.
The information obtained should enable assessment of the following aspects, but not limited to:
• The suitability of the site with respect to the proposed construction and the level of acceptable
risks;
• The deformation of the ground caused by the structure or resulting from construction works,
its spatial distribution and behavior over time;
• The safety with respect to limit states (e.g. subsidence, ground heave, uplift, slippage of soil
and rock masses, buckling of piles, etc.);
• The loads transmitted from the ground to the structure (e.g. lateral pressures on piles) and
the extent to which they depend on its design and construction;
• The foundation methods (e.g. ground improvement, whether it is possible to excavate,
drivability of piles, drainage);
• The capacity of the ground to absorb water injected during construction work;
• Whether it is possible to use local groundwater, given its chemical constitution, for
construction purposes.
3.2.2.2 Sequence of Ground Investigations
1. Desk studies;
2. Preliminary investigations (from CONSULTANTS);
3. Design investigations;
4. Supervision of construction;
5. Controlling and monitoring.
Page 24 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
3.2.2.3 Desk Studies
The primary objectives of the desk study are to evaluate the ground conditions based upon available
information on geology and ground water conditions, both locally and regionally, in order to plan the
extent of subsequent stages of ground investigation. During the desk study stage, the information
may be collected from published literature such as:
• Geological maps.
• Geological memoirs.
The actual location, spacing, and depth of borings should be dictated by the topography, geologic
conditions, visible soil conditions, and design considerations, and in accordance with the practices set
forth herein.
The allowable soil bearing capacity shall be calculated to cater for preventing soil shear failure under
the foundation base and to tolerate the settlement to acceptable limit over a depth of at least 1.5 B
below the formation level (where B is the breadth of the foundation). The depth of investigations shall
be extended to all strata that will affect the project or are affected by the construction.
Borings should extend through any unsuitable or questionable foundation materials and sufficiently
deep into stable soils so that the potential for settlement from compression of that layer or that the
deeper underlying soils can be determined. If deep excavations are required for building the structure,
the explorations should be carried to at least 1.5 times the depth of the excavation in order to locate
and determine groundwater levels in any aquifers that may exist below the level of excavation. This is
Page 25 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
necessary to plan and design a dewatering system that may be required in deep excavations and to
avoid heave or disturbance to the bottom of the excavations.
Often borings are made in several stages. In the first stage, relatively few borings are made. Based
upon these findings, additional borings may be made between the initial borings to define soil
conditions in greater detail. The selection of sample type and frequency is determined by soil
conditions and requirements of the structure. Where soil conditions are favorable, especially for small
structures, all borings are often completed in the first phase of the investigation. If soil conditions are
well known with fairly thick individual layers of consistent physical properties, relatively widely spaced
borings may be sufficient. If, however, soil conditions vary appreciably from place to place, more
closely spaced borings will be required. The number and spacing must be determined by engineering
judgment as the work progresses. Sufficient number of borings should be done to determine the
stratification and interrelation of the soils to the extent economically feasible. The exploration should
be conducted considering the requirements of the structure. All soil data necessary for the selection
of the foundation and its design must be obtained.
As guideline for a preliminary study, CONSULTANTS should refer to the Table in Appendix E– Guideline
for preliminary investigation for Consultant. The Table provides the minimum soil investigation
required to understand and define the local geology.
The most important step in geotechnical design is to conduct an adequate subsurface investigation.
The number, depth, spacing, and character of borings, sampling, and testing to be made in an
individual exploration program are dependent upon site conditions and the type of project and its
requirements, so no "rigid" rules may be established. Usually the extent of work is established as the
site investigation progresses in the field. However, the following are considered reasonable
"guidelines" to follow to produce the minimum subsurface data needed to allow cost-effective
geotechnical design and construction and to minimize claim problems.
When selecting the locations of investigation points, the following should be observed:
• The investigation points should be arranged in such a pattern that the stratification can be
assessed across the site;
• The investigation points for a building or structure should be placed at critical points relative
to the shape, structural behavior and expected load distribution (e.g. at the corners of the
foundation area);
• For linear structures, investigation points should be arranged at adequate offsets to the center
line, depending on the overall width of the structure, such as an embankment footprint or a
cutting;
• For structures on or near slopes and steps in the terrain (including excavations), investigation
points should also be arranged outside the project area, these being located so that the
stability of the slope or cut can be assessed;
• Where anchorages are installed, due consideration should be given to the likely stresses in
their load transfer zone;
• The investigation points should be arranged so that they do not present a hazard to the
structure, the construction work, or the surroundings (e.g. they may cause changes to the
ground and groundwater conditions);
Page 26 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• The area considered in the design investigations should extend into the neighboring area to a
distance where no harmful influence on the neighboring area is expected;
• For groundwater measuring points, the possibility of using the equipment installed during the
ground investigation for continued monitoring during and after the construction period
should be considered.
The depth of investigations should be extended to all strata that should affect the project or are
affected by the construction.
• For dams, weirs and excavations below groundwater level, and where dewatering work is
involved, the depth of investigation should also be selected as a function of the hydro-
geological conditions;
• Slopes and steps in the terrain should be explored to depths below any potential slip surface.
For the spacing of investigation points and investigation depths, the values given in Table 3.7 should
be used as guidance (Reference: "Subsurface Investigations" FHWA HI-97-021 and Eurocode 7 part2,
modified and adapted):
• For high-rise and industrial structures, a grid pattern with points at 15 m to 40 m distance;
• For large-area structures, a grid pattern with points at not more than 60 m distance;
• For linear structures (roads, railways, channels, pipelines, dikes, tunnels, retaining walls), a
spacing of 20 m to 200 m, and max. 500 m;
• For special structures (e.g. bridges, stacks, machinery foundations), two to six investigation
points per foundation;
Structure
1 per substructure Spread footings: 2B where L< 2B, 4B where L > 2B and
Foundation
unit under 30 m (100 interpolate for L between 2B and 4B
ft) in width (B)
For raft foundations and structures with several
2 per substructure foundation elements whose effects in deeper strata are
unit over 30 m (100 superimposed on each other: ≥ 1.5B (where B is the
ft) in width smaller side of the structure)
(B)Additional borings
in areas of erratic Deep foundations: 6m (20ft) below tip elevation or L two
subsurface times maximum pile group dimension, whichever is
conditions greater
Page 27 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
− Z a ≥1,0b g
− Z a ≥5,0 m
− Z a ≥3D F
Retaining Borings spaced every Extend borings to depth of 0.75 to 1.5 times wall height
Structures 30 to 60 m (100 to
200 ft). Some When stratum indicates potential deep stability or
borings should be at settlement problem, extend borings to hard stratum
the front of and
some in back of the
wall face.
Bridge Approach When approach Extend borings into competent material and to a depth
Embankments embankments are to where added stresses due to embankment load is less
over Soft Ground be placed over soft than 10% of existing effective overburden stress or 3 m
ground, at least one (10 ft) into bedrock if encountered at a shallower depth
boring should be
made at each Additional shallower explorations (hand auger holes)
embankment to taken at approach embankment locations to determine
determine the depth and extent of unsuitable surface soils or topsoil.
problems associated
with stability and If only soft soil encountered, the larger value of the
settlement of the following conditions should be met:
embankment.
Typically, test
For dams: 0,8h < Z a < 1,2h or Z a ≥6m where h is the
borings taken for the
embankment height.
approach
embankments are
located at the For cuttings: Z a ≥2,0 m or Z a ≥0,4h, where h is the dam
proposed abutment height or depth of cutting.
locations to serve a
dual function.
Page 28 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Centreline Cuts Borings typically Cuts: (1) in stable materials extend borings minimum 5 m
and spaced every 60 m (15 ft) below depth of cut at the ditch line and, (2) in weak
Embankments (200 ft) (erratic soils extend borings below grade to firm materials or to
conditions) to 120 m twice the depth of cut whichever occurs first.
(400 ft) (uniform
conditions) with at Embankments: Extend borings to a hard stratum or to a
least one boring depth of twice the embankment height.
taken in each
separate landform.
Page 29 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
− Z a ≥(1,0⋅H + 2,0) m
− Z a ≥(t + 2,0) m
Page 30 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Silt or Clay Soils SPT and "undisturbed" thin wall tube samples should be taken at 1.5 m (5 ft)
intervals or at significant changes in strata. Take alternate SPT and tube samples
in same boring or take tube samples in separate undisturbed boring. Tube
samples should be sent to lab to allow consolidation testing (for settlement
analysis) and strength testing (for slope stability and foundation bearing capacity
Analysis). Field vane shear testing is also recommended to obtain in-place shear
strength of soft clays, silts and well-rotted peat.
Rock Continuous cores should be obtained in rock or shales using double or triple tube
core barrels. In structural foundation investigations, core a minimum of 3 m (10
ft) into rock to insure it is bedrock and not a boulder. Core samples should be
sent to the lab for possible strength testing (unconfined compression) if for
foundation investigation. Percent core recovery and RQD value should be
determined in field or lab for each core run and recorded on boring log.
Groundwater Water level encountered during drilling, at completion of boring, and at 24 hours
after completion of boring should be recorded on boring log. In low permeability
soils such as silts and clays, a false indication of the water level may be obtained
when water is used for drilling fluid and adequate time is not permitted after
boring completion for the water level to stabilize (more than one week may be
required). In such soils, a plastic pipe water observation well should be installed
to allow monitoring of the water level over a period of time. Seasonal
fluctuations of water table should be determined where fluctuation will have
significant impact on design or construction (e.g., borrow source, footing
excavation, excavation at toe of landslide, etc.). Artesian pressure and seepage
zones, if encountered, should also be noted on the boring log. In landslide
investigations, slope inclinometer casings can also serve as water observations
wells by using "leaky" couplings (either normal aluminium couplings or PVC
couplings with small holes drilled through them) and pea gravel backfill. The top
0.3 m (1 ft) or so of the annular space between water observation well pipes and
borehole wall should be backfilled with grout, bentonite, or sand-cement
mixture to prevent surface water inflow which can cause erroneous
groundwater level readings.
Soil Borrow Exploration equipment that will allow direct observation and sampling of the
Sources subsurface soil layers is most desirable for material site investigations. Such
equipment that can consist of backhoes, dozers, or large diameter augers, is
preferred for exploration above the water table. Below the water table, SPT
borings can be used. SPT samples should be taken at 1.5 m (5 ft) intervals or at
significant changes in strata. Samples should be sent to lab for classification
testing to verify field visual identification. Groundwater level should be
recorded. Observations wells should be installed to monitor water levels where
significant seasonal fluctuation is anticipated.
Quarry Sites Rock coring should be used to explore new quarry sites. Use of double or triple
tube core barrels is recommended to maximize core recovery. For riprap source,
spacing of fractures should be carefully measured to allow assessment of rock
Page 31 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
sizes that can be produced by blasting. For aggregate source, the amount and
type of joint infilling should be carefully noted. If assessment is made on the
basis of an existing quarry site face, it may be necessary to core or use
geophysical techniques to verify that nature of rock does not change behind the
face or at depth. Core samples should be sent to lab for quality tests to
determine suitability for riprap or aggregate.
Trial Pits
The depth and spacing of trial pits should be such as to give a true picture of the underlying soil, with
regard to any major changes in thickness, depth or properties of the strata over the base area of the
structure and in its immediate vicinity. Only a preliminary estimate of spacing is made first. This may
be decreased or increased depending upon the information revealed by borings.
According to Standard, the following specifications are laid down in this regard:
1. For a compact building site covering an area of about 0.4 hectare (i.e. 4000 m2), one trial pit
in each corner and one in the center (i.e. 5 trial pits in all) should be adequate;
2. For smaller areas and less important buildings even one trial pit in the center should be
sufficient;
3. For very large areas covering industrial and residential colonies, the geological nature of the
terrain should help in deciding the number of trial pits. Dynamic or static cone penetration
tests may be performed at every 100 meters by dividing the area in a grid pattern and numbers
of bore holes or trial pits are decided by examining the variation in the penetration curves;
4. For exploration purposes, the minimum depth is taken as 1.5 m because the weathering
processes affect the soil up to this depth. But where industrial processes affect the soil
characteristics this depth may be more;
5. Along pipeline routes, one (1) Trial Pit every 500 m should be adequate in uniform soil, and
every 200 m in average soil.
For preliminary estimate, the spacing may be adopted as presented in the following Table 3.8.
Table 3.8 – Number and Depth of Trial Pits Investigation.
Large areas (>100,000 m2) Every 100 meters in a grid Every 100 meters in a grid
Page 32 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Multi-storeyed buildings 30 – 60 m 15 – 30 m
When the bed rock is found, the surface should be plotted by a number of borings or surroundings in
order to locate any depressions. For this purpose, a few borings and sub-surface soundings (See
geophysical investigation section) are first made at large intervals and intermediate values, if needed,
can be normally obtained by soundings, or by further borings in case of unpredictable profile nature.
For identification and classification of the ground, at least one borehole or trial pit with sampling
should be available. Samples should be obtained from every separate ground layer influencing the
behavior of the structure. ASTM Standards (See Appendix A) should be applied.
Samples should be taken at any change of stratum and/or at a specified spacing, usually not larger
than 3 m. In inhomogeneous soil, or if a detailed definition of the ground conditions is required,
continuous sampling by drilling should be carried out or samples recovered at very short intervals.
Samples should contain all the mineral constituents of the strata from which they have been taken.
They should not be contaminated by any material from other strata or from additives used during the
sampling procedure.
Undisturbed samples (samples of quality class 1) from bound and organic layers should be taken as
instructed by the site engineer. They are to be taken from the undisturbed section underneath the
casing and should be documented in the drilling logs. The sampling should ensure that the soil
properties remain unchanged during sampling and handling, transport and storage, and should
identify the following:
• Particle size;
• Water content;
Page 33 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
include record of the borehole, date and depth. Disturbed samples should be taken in each case of
material/layer changes (e.g. change in grain size distribution, quality or colour), at least however every
meter. Recovery depths of the samples should be documented in the drilling logs.
Origin of samples should be clearly identified with indication of:
• Drilling Contractor;
• Section / Location;
Samples to be tested should be representative, i.e. they should be similar in characteristics to most of
the stratum from which they come, or be an average of the range of materials present. If this appears
difficult because of variations in the stratum, it may be necessary to consider subdivisions of the
stratum for sampling, testing, and design purposes. In general, tests on samples of mixed or stratified
material, such as varved clay, should be avoided; usually such results are not indicative of material
characteristics; and better data for analysis can be obtained by testing the different materials
separately. Undisturbed samples for structural properties tests must be treated with care to avoid
disturbance; an "undisturbed" sample found to be disturbed before testing normally should not be
tested. Fine-grained cohesive samples naturally moist in the ground should not be allowed to dry
before testing, as irreversible changes can occur; organic soils are particularly sensitive. Soils with
chemical salts in the pore water may change if water is added, diluting the salt concentration, or if
water is removed, concentrating or precipitating the salt. Organic soils require long-term low
temperature (60deg.C) drying to avoid severe oxidation (burning) of the organic material.
A number of checks and additional tests should be made during the construction and execution of the
project, when relevant, in order to check that the ground conditions agree with those determined in
the design investigations and that the properties of the delivered construction materials and the
construction works correspond to those assumed or specified.
Page 34 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The following control measures should be applied:
Significant fluctuations in the location of ground water table should be anticipated throughout the
year, depending upon the amount of precipitation, evaporation, tidal variation and surface runoff. The
following monitoring program should take place:
1. Right of Entry. Unless otherwise agreed, Client should furnish right-of-entry and obtain
permits as required to perform the fieldwork at no cost to CONTRACTOR;
2. Site management; drilling rigs positioning and access, storage of drilling accessories, provide
all water supplies that may be needed for drilling operations and management of the water
that would be produced as part of the drilling operation which may require creating of
channels to drain the water from the drilling site and preparing temporary storage for it. This
water is anticipated to be encountered only during drilling within the shallow aquifer system;
3. Damage to Property. CONTRACTOR should take reasonable precautions to minimize damage
to land, equipment and other property contained therein caused by operations, and have to
repair such damage;
4. Toxic and Hazardous Materials. Client should provide CONTRACTOR with all information
within his possession or knowledge as to the potential occurrence of toxic or hazardous
materials at the site being investigated. If unanticipated toxic or hazardous materials are
encountered, Contractor reserve the right to demobilize their field operations. Remobilization
should proceed following consultation with our safety coordinator and Client’s acceptance of
proposed safety measures and fee adjustments.
5. Utilities and Pipelines. While performing fieldwork, CONTRACTOR should take reasonable
precautions to avoid damage to subterranean and sub-aqueous structures, pipelines and
utilities.
3.2.2.9 QHSE
HSE, Quality Management, NOIs are covered under Section 4-General Design Requirements.
Investigation Methods.
Page 35 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Geophysical testing methods are non-destructive testing procedures which can provide general
information on the general subsurface profile, depth to bedrock and water table, bedrock engineering
properties (i.e. from seismic refraction), presence of karst features (i.e. from Electrical Resistivity
Tomography (ERT)), extent of peat deposits, or presence of voids and buried utilities.
These methods should be combined with the aim of providing both the vertical and horizontal
variations in the subsurface material to a maximum depth of 25 m to 30 m below ground surface to
highlight potential anomalous areas associated with open or partially filled cavities.
These testing methods may also be used to evaluate existing bridge decks, foundations, and
pavements, and should be used to confirm borehole drillings location.
Seismic refraction 240m and MASW (Multi Channel Analysis of Surface Waves)
General Settings
The acquisition to ensure a continuous seismic profile should be carried out using:
• MASW sections;
For the 240 m spread, one cable, 48 geophones, 5 m between each geophone should be used, with
11 shots per spread, with 30 m between each shot.
For the seismic refraction and MASW, either a weight drop, 8000 Joules (for 240m spread) or the
sledge hammer should be used if there is enough energy. The choice between these two sources
would be confirmed after tests.
To ensure a good quality of data, geophones are required to be driven/stuck/buried into the ground.
The estimate production is 960 m/day for the 240 m spread.
Page 36 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The listing in the following Table 3.9 provides specifications for the refraction and MASW acquisitions.
Table 3.9 – Specifications for the refraction and MASW.
Trace spacing 5m
Geophones 48 x 4.5 Hz
• 1 engineer Geophysicist.
• 1 observers.
• 1 geophysicist junior.
• 4 workers.
Page 37 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• 2 drivers.
• 1 surveyor.
• 2 QC.
QA/QC & Processing for seismic refraction and MASW
During acquisition, particular attention should be given on the coherence of the zero-time.
• ABC Interpretation;
• Export to SeisImager file format;
• Tomographic inversion;
• Conversion to layered model.
For MASW processing, the sequence should be as follow:
Page 38 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Deliverables
• Interpretative report;
• Alignment chart, with all the geotechnical parameters calculated from MASW and seismic
refraction results;
• Shear wave velocity variations.
Electrical Resistivity Tomography (ERT)
General Settings
ERT is carried out to characterize the resistivity of the soil on the top 25 meters covering the area of a
building site (line spacing 100 m) or along the whole proposed pipeline route. It aims to detect water
table, the structural extension of the different geological layers and precisely identify the location and
extension of fractured zones in the near surface.
For the 475 m active lines, one cable, 96 active electrodes, 5 m between each electrode should be
used.
With this technique, the apparent electrical resistivity distribution of the subsurface is measured using
an array of four electrodes. By injecting a dc or very low frequency ac current (I) between a pair of
electrodes and measuring the resulting potential difference (ΔV) with a second pair of electrodes, it is
possible to calculate the apparent resistivity using a derivation of Ohms law (R=ΔV/I). This approach is
known as galvanic resistivity.
For the same geometry array, Wenner-Schlumberger and dipole-dipole procedures should be
performed to resolve, respectively, vertical and lateral changes. These are set out below:
Resistivity equations:
ρE = measured apparent soil resistivity (Ωm) ρE = measured apparent soil resistance (Ωm)
a = electrode spacing (m) a = electrode spacing (between voltage
b = depth of the electrodes (m) probes) (m)
RW = Wenner resistance b = depth of the electrodes (m)
c = electrode spacing (between voltage and
current probes) (m)
RS = Schlumberger resistance
A roll-along should be done to ensure lateral coherence on the same line. A half line (48 electrodes)
overlap should be done.
Due to this double acquisition procedure, an estimated production of 1000 m/day per team should be
applicable.
Page 39 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The typical initial acquisition design should be as follows:
• Active electrodes: 96
• Total active line: 475 meters
• Levels of acquisition: 31
• Investigation Depth: 55 meters
• Quadripoles: 2018p
The minimum required crew should be:
• 1 engineer Geophysicist
• 4 observers
• 4 geophysicist junior
• 16 workers
• 3 drivers
• 1 surveyor
QA/QC & Processing for ERT
Before each measurement, a line check should be done to verify that each electrodes is connected
and has a good contact resistance. Electrodes with bad contact resistance, which often happens in
extremely dry soil, should be watered with salted water which has proved to be a remarkably
conductive medium.
During data treatment, points with noise or interference can be removed to improve quality.
While measuring, the instrument is able to do a noise monitoring with a pre-injection control
consisting of a DC digital voltmeter function. The standard deviation between measurements is also
display to give an indication of the noise level during the measurement.
The data should be processed with the Res2DInv software from Geotomo Software. This software
should be used for field QC processing to determine the quality of field data:
Models and calibration site results should be used to test interpretations and geometries, particularly:
Page 40 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Resolution issues;
• Noise or interference problems;
• Geometric constraints.
Deliverables
• Interpretative report;
• Resistivity model as the below Figure 3.4.
The Contractor should carry out a soil resistivity survey to determine the corrosivity of the soil along
the pipeline routes. Soil resistivity readings should be taken at approximately 500 m spacing along the
pipeline or at the position as instructed by the ENGINEER using the Wenner 4-Electrode method.
Readings should be taken at each test location in order to reflect the resistivity at a depth of 1, 2 and
3 times the pipe’s diameter. The resistivity of the soil at each depth should be recorded in ohm-cm.
Soil resistivity readings should be presented throughout the route in graphical form. The Contractor
should provide four sets of pipeline route plans marked up to show the variations in resistivity along
the pipeline routes within the following bands:
If the soil is highly aggressive and/or moderately aggressive, an additional protection is required for
the pipeline.
The previous geophysical investigation should be calibrated using a drilled borehole in the area of
exploration for direct calibration. Data from core description and SPT should be used in addition to a
downhole seismic testing.
Downhole seismic testing measures vertical changes in seismic velocity by placing a source at the top
of a borehole and measuring travel-times at multiple intervals in the borehole, usually with a 3-
component geophone. Common applications include:
Page 41 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Bridge/dam foundation analysis;
• Insitu materials testing;
• Soil and rock mechanics;
• Earthquake engineering;
The results of a downhole seismic survey should include travel time plots and velocity graphs for both
p- and shear-waves.
For structures assigned to Seismic Design Category C, D, E or F in accordance with Section 1613, a
geotechnical investigation shall be conducted, and shall include an evaluation of all of the following
potential geologic and seismic hazards:
1. Slope instability.
2. Liquefaction.
3. Differential settlement.
For structures assigned to Seismic Design Category D, E or F in accordance with Section 1613, the
geotechnical investigation required by Section 1803.5.11, shall also include:
1. The determination of lateral pressures on foundation walls and retaining walls due to earthquake
motions.
2. The potential for liquefaction and soil strength loss evaluated for site peak ground accelerations,
magnitudes and source characteristics consistent with the design earthquake ground motions. Peak
ground acceleration shall be permitted to be determined based on a site‐specific study taking into
account soil amplification effects, as specified in Chapter21 of ASCE 7, or, in the absence of such a
study, peak ground accelerations shall be assumed equal to SDS/2.5, where SDS is determined in
accordance with Section 1613.5.4.
3. An assessment of potential consequences of liquefaction and soil strength loss, including estimation
of differential settlement, lateral movement, lateral loads on foundations, reduction in foundation
soil‐bearing capacity, increases in lateral pressures on retaining walls and flotation of buried
structures.
4. Discussion of mitigation measures such as, but not limited to, ground stabilization, selection of
appropriate foundation type and depths, selection of appropriate structural systems to accommodate
anticipated displacements and forces, or any combination of these measures and how they shall be
considered in the design of the structure.
Page 42 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
3.2.2.12 Trial Test Pits
Trial Test Pits (PT) should be excavated until they are minimum 1.5 m x 1.5 m in base plan, to confirm
findings of the desk study, in terms of geotechnical properties and average soil profile.
The trial pit should terminate at either a maximum depth of 3 m or refusal; on encountering rockhead,
or on encountering groundwater and at whichever is encountered first. In case of groundwater, the
trial pit should be immediately backfilled to a level above the water table, before the pit floods),
All excavations deeper than 1.2 m should be carried out by personnel trained in confined space entry
and pit sides should be sloped or shored to ensure stability.
Trial Pits are to be excavated by hand or with a wheeled backhoe excavator capable of digging down
to at least 3 m below ground level. A toothless bucket should be used for the first 1.5 m to protect
services and utilities unless hand excavation is specified. The pit should be advanced in layers and a
suitably experienced geologist or technician supervise the excavation and produce a field log in
accordance with "Geological Society Engineering Group Working Party Report on The Logging of Rock
Cores for Engineering Purposes" &"Code of Practice for Site Investigation: BS 5930" and ASTM D5434.
The geotechnical logs (detailed stratigraphy) of trial pits together with photographs are to be attached
to the report
Bulk samples are to be recovered from trial pits for geotechnical laboratory testing, i.e. one (1) sample
per soil type should be taken for laboratory tests (see below) and one (1) sample of water if
encountered.
The trial pits are to be kept as small as practicably possible. Sidewalls should be shored if necessary to
protect adjacent structures and foundations, and to ensure pit stability.
All trial pits should be then backfilled with adequate compaction with layer thickness 300 mm using
backhoe bucket immediately after completion of investigation.
Since groundwater affects many elements of the foundation design and construction, groundwater
observations should be presented on the trial test pit logs.
3.2.2.13 Soakage testing or percolation testing in Trial Test Pits (TP) or at defined locations
One (1) permeability test per trial pit is required on sites where it is intended to use a soakaway.
The test determines the rate at which the ground absorbs a known volume of water. The test ensures
that the ground is suitable for a soakaway and that the soakaway is designed properly. Typically,
soakaways are used to collect surface runoff prior to being discharged into the surrounding soil. They
are usually used in areas where the surface run-off cannot be disposed into existing sewers or
watercourses. There are a number of permeability tests for measuring the rate of flow and
determining whether soakaways may work effectively at a site. These range from small to large scale.
Small-scale soakage tests are only applicable to draining relatively small areas. We recommend
applying a large-scale test as per follows:
• BRE Digest 365: 1991; Falling Head Test in Trial Pits (Large-scale)
The results of this test can be also used for the design of any projected dewatering system.
Page 43 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
tungsten drill bits and water flush would be undertaken in rock at minimum 122 mm to recover cores
of 76 mm minimum nominal diameter, to the required depths.
102 mm diameter undisturbed samples are to be obtained in cohesive material utilizing thin-walled
samplers and split spoon samples are to be obtained in non-cohesive materials. Disturbed bulk
samples are to be also obtained within non-cohesive materials.
During drilling, drilling fluid losses incl. flushing water returns should be recorded, and as soon as
groundwater has been reached in the borehole, the groundwater level should be recorded
immediately; a water sample should be taken for measurement of field parameters (temperature, pH,
conductivity and dissolved oxygen). Furthermore groundwater levels are to be re-checked and
documented again when works are interrupted (e.g. casing is taken out or before refilling) and after
long breaks during work.
Increases or decreases in groundwater level, the timing and specific depths in relation to where or
how these variations occur are to be recorded as well as addition of water to the drilling. All records
related to groundwater should be integrated in the drilling logs provided to TRANSCO.
All recovered samples and cores should be logged and photographed by an experienced degree-
qualified geologist / engineer. Data presentation should be in the form of borehole logs, generated in
the GINT software format.
Core samples should be stored in core boxes to allow long-term and secured storage. Length of core
boxes should allow to store one and half meter of recovered core in one separate section. Labelling at
both ends and on the lid of the core boxes should have the following format and contain the following
information:
• Drilling Contractor
• Section / Location
• Investigation stage and date
• Drilling identification no.
• Core Box Nr.:
• Meter from …… to ……
Page 44 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Core sample boxes from the field should be taken to the laboratory for testing on a daily basis. Rock
and core samples should be examined, described, classified, identified and coded by experienced
geotechnical engineers and the descriptions should be prepared according to BS 5930:1999 + A2 2010.
All actual core losses should be recorded and photographic documentation should be carried out.
The core boxes should be then accessible to be transported to a central storage facility of the Client
choice.
Inspection pits for services in advance of boreholes should be hand-excavated in the minimum
practicable dimensions up to a maximum depth of 1.2 m and in the pit floor a post hole should be
advanced, with a specialised split spoon spade (“post hole digger”), to 1.5 m below ground level.
If a utility is encountered, its depth and orientation should be noted and the location should be moved
to an adjacent position with the Client’s approval. Bulk samples should be recovered from inspection
pits for geotechnical laboratory testing.
Borehole Abandonment
After coring, the boreholes not to be used as groundwater monitoring stations (i.e. installation of
piezometers) should be properly abandoned by backfilling following industry standards for well
abandonment methods. Boreholes should be filled and plugged in a way that no voids remain, no
settlement of the surface can happen, no open connection exists between ground surface-natural
groundwater table and no damages on third party property can occur. Appropriate filling material
with an expanding and sealing character (e.g. bentonite-cement mix or special clay pellets) should be
used. After filling previously broken up surface, pavement etc. should be restored to its original state.
Monitoring wells should also be installed. Some of the drilled wells should be completed with one
standpipe piezometer. The standpipe tube should have a maximum length that is the same as the
depth of the borehole itself. The number of piezometers to be installed should be specific to the
project and borehole accessibility.
A minimum of one (1) piezometer is required by site, and a minimum of one (1) every 2000 m along a
pipeline route.
The standpipe piezometers should comprise of 50mm ID (2”) PVC threaded pipe with plain and slotted
sections.
Generally, the slotted section should be based on the lithology penetrated or groundwater depth, but
should be at least 3 meters in length, surrounded by fine gravel to about 1.0m above and below the
slotted section. The slotted section of the PVC pipe should be protected by a 0.02mm diameter geo-
textile socks to prevent slots clogging. Detailed installation information as per the attached Piezo
sketch below.
The top of each standpipe should either protrude approximately 600mm above the surrounding
ground level and should be encased in concrete, fitted with a threaded screw top for protection and
ease of access, OR it should be cut slightly below ground level and fitted with a flush lockable cover,
based on Contractor request. Should the Contractor require no protection, the piezometer should
Page 45 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
protrude from the GL to approximately 300mm above, whereby it should be fitted with a screw cap
only, creating a simple groundwater monitoring station.
• The 4‐inch inner diameter casing should be driven to the required test depth (refer to soil
boring procedure for allowable equipment). The space (annulus) between the casing and
borehole must be kept at a minimum. If the casing cannot be driven and a larger hole is first
bored to allow for the casing, the annulus must be properly sealed before any water is
introduced for testing into the casing;
• Measure the depth to the bottom of the hole to the nearest inch;
• Ensure that the depth to the bottom of the hole is within 1 inch of the depth to the bottom of
the casing;
• Place approximately 6 ‐ 8 inches of coarse sand (4.75mm – 2mm) at the bottom of the casing;
• Wash out casing using a continuous flow of clean water at low water pressure (the water
should not disturb the coarse sand layer at the bottom of the casing) until the water exiting
the casing runs clear;
• Saturate the soil beneath the bottom of the casing for at least thirty (30) minutes using clean
water;
• Fill casing to the top with clean water and record the temperature of the water;
• Record the time at the beginning of the test;
• Record the falling water level in the casing at 1, 2, 3, 4, 5, 10, and 15 minutes after the
beginning of the test or until the water level in the casing has stopped falling.
• At the conclusion of the test, fill the casing to the top with clean water and maintain the water
at this level for five (5) minutes.
• Repeat the test once for each PT depth using the same procedure.
Clean water must be used to conduct PTs; PTs conducted using “dirty water” creates faulty results and
should be rejected.
If a soil boring was conducted within 20 ft of a planned PT location, the borehole from the soil boring
must be completely backfilled before the PT is commenced.
The Contractor should maintain continuous data of PTs and report them accurately in Permeability
Test Logs (PT Logs).
Packer tests consist of isolating specific sections (usually 10 ft) of a bedrock borehole with inflatable
packers (bladders) so that water-quality samples can be collected and aquifer tests can be conducted.
A series of such tests allows definition of the vertical distribution of water quality (usually
contaminants) and hydraulic conductivity (pathways for water and contaminant movement) in an
aquifer. Monitoring water levels in nearby wells while pumping packed intervals can identify
Page 46 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
permeable intervals within the aquifer. Information from the packer tests should be used to properly
site the future location of monitoring wells.
Smaller packers designed to fit a submersible sampling pump can be used isolate the lower part of a
monitoring well. Isolation by the packer allows reduced water volumes to be purged prior to sampling.
This reduction can be beneficial because it can reduce purge times and may limit the handling and
disposal of contaminated water.
Methodology
• Develop entire length of borehole to ensure test intervals don’t contain water and fines from
drilling;
• Decontaminate packer equipment before use;
Table 3.10 presents a partial list of the major in-situ tests and their perceived applicability for use in
different ground conditions.
Page 47 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Table 3.10 – Applicability and usefulness of in-situ tests (Lunne, Robertson & Powell, 1997, updated by Robertson, 2012).
Standard-Penetration-Test (SPT)
In each soil boring location, a Standard Penetration Test (SPT) should be conducted continuously in
accordance with ASTM D1586 (i.e. a 24‐inch long, 2‐inch outside diameter split‐barrel sampler driven
by blows from a 140‐pound hammer falling freely from a height of 30 inches) up to refusal (i.e.
bedrock).
The number of blows required to drive the 24‐inch split‐barrel sampler every 6‐inch increment should
be recorded. The Standard Penetration Resistance (N‐value) should be determined as the sum of the
blows required to drive the sampler to the second and third 6‐inch increments. Before testing, the
borehole should be cleared of sludge. Results should be recorded and incorporated in drilling logs.
Cone Penetration Tests (CPT) should be conducted continuously in accordance with ASTM D3441 –
16. The spacing of CPT should be such as to give a true picture of the underlying soil, with regard to
any major changes in thickness, depth or properties of the strata over the base area of the structure
and in its immediate vicinity. Only a preliminary estimate of spacing is made first. This may be
decreased or increased depending upon the information revealed by borings, i.e. post drilling CPT to
confirm horizontal changes. The depth of CPT should be the depth of refusal.
1. For a compact building site covering an area of about 0.4 hectare (i.e. 4000 m2), one CPT in
each corner and one in the center (i.e. five (5) CPT in all) should be adequate;
2. For smaller areas and less important buildings even one (1) CPT in the center should be
sufficient;
3. For very large areas covering industrial and residential colonies CPT may be performed at
every 100 meters in very uniform soils by dividing the area in a grid pattern, and every 100
m for average soil;
Page 48 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
4. Along pipeline routes, one (1) CPT every 500 m should be adequate in uniform soil, and
every 200 m in average soil.
For preliminary estimate, the spacing may be adopted as presented in the following Table 3.11:
Table 3.11– Number of CPT
Large areas (>100,000 m2) Every 100 meters in a grid Every 50 meters in a grid
Multi-storeyed buildings 30 – 60 m 15 – 30 m
Standard Test Method for Field Vane Shear Test in Saturated Fine-Grained Soils.
Field Vane Shear Test (FVST) should be conducted continuously in accordance with ASTM D2573 /
D2573M – 15. This test method provides an indication of in-situ undrained shear strength of saturated
fine-grained soils (clays and silts) or other saturated fine-grained geomaterials, such as mine tailings
and organic muck. The test is applicable to soils with undrained strengths of less than 200 kPa [2 tsf].
Very sensitive soils can be remoulded during vane insertion. This method should be checked or
compared with other methods of measuring undrained shear strength, such as Cone Penetrometer
Tests (Test Method D5778) and Unconsolidated Undrained Triaxial Compression (D2850) tests.
The quantity and spacing may be adopted as presented in the following Table 3.12.
Table 3.12 – Number and Depth of Field Vane Shear Test
Large areas (>100,000 m2) Every 100 meters in a grid Every 50 meters in a grid
Page 49 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Multi-storeyed buildings 30 – 60 m 15 – 30 m
In-situ testing of soils and rocks for strength and stiffness parameters should be carried out through
Pre-bored Pressuremeter Testing (PMT) following ASTM D4719-07 standards.
This test method covers pressuremeter testing of soils. A pressuremeter test is an in situ stress-strain
test performed on the wall of a borehole using a cylindrical probe that is expanded radially. To obtain
viable test results, disturbance to the borehole wall must be minimized.
The procedure for drilling the borehole, inserting the probe, and conducting pressuremeter tests in
both granular and cohesive soils should follow ASTM D4719-07 standards.
Note that the knowledge of the type of soil in which each pressuremeter test is to be made is necessary
for assessment of (1) the method of boring or probe placement, or both, (2) the interpretation of the
test data, and (3) the reasonableness of the test results.
The quantity and spacing may be adopted as presented in the following Table 3.13.
Table 3.13 – Number and Depth of Pre-bored Pressuremeter Testing
Large areas (>100,000 m2) Every 100 meters in a grid Every 50 meters in a grid
Multi-storeyed buildings 30 – 60 m 15 – 30 m
Page 50 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The dynamic properties of soil are strain dependent, so their best estimates and ranges of variation
can be obtained only by carrying out various types of field and laboratory tests (see for Method for
Load Controlled Cyclic Triaxial Strength of Soil (ASTM D5311 / D5311M – 13 in the next section).
Therefore, low strain dynamic tests such as seismic cross hole survey or high strain dynamic tests such
as block resonance tests or cyclic plate load tests should be performed at the site.
The dynamic Soil parameters shall be addressed in the detailed geotechnical investigation report by
the Contractor which are:
Site investigations for offshore structures, nearshore structures and dredging works are necessary to
acquire data that should facilitate successful foundation design, site or route selection, choice of
foundation type, dimensioning, installation and operational integrity of the proposed structure.
Success depends on a well-prepared budget, good planning, and attention to quality and safety to
develop an acceptable risk profile.
• Slope instability;
• Earthquake susceptibility;
• Presence of shallow gas or hydrates.
The type and quantity of data required should depend upon factors that include:
Page 51 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Project phase, e.g. feasibility study or final design;
• Acceptable risk to people and the environment;
• Type of foundation loads.
The range of modern geotechnical and geophysical instruments available to surveyors and engineers
is extensive and their capabilities manifold. Only the briefest treatment of the more common systems
is given here and the reader is referred to the many excellent textbooks and other sources of
information available.
• Bathymetry survey
• Sidescan Sonar Survey
• Seabed profiling using sub-bottom profiler;
• Marine Geotechnical drilling and sampling, using grab sample and in-situ tests;
• Onshore geotechnical Boreholes;
• Marine EIA Survey.
For advanced studies, the following additional geophysical methods should be required:
Acoustic doppler current profilers (ADCPs) in the vicinity of the survey area should be deployed. The
precise locations of the ADCPs should be determined upon project award, based on the specific
requirements of the Client and the recommendations of Contractor’s marine hydrodynamic
specialists.
ADCPs should be deployed for a total of 30 days so as to ensure that the full wave and tidal cycles are
recorded over the course of an entire monthly cycle. The use of Teledyne RD Instruments ADCP with
waves options (Workhorse Sentinel) is preferred. This high frequency ADCP offers a number of
advantages including its light weight, precision and low power consumption. The wave’s option
provides the ability to obtain directional wave arrays. Teledyne WHS are the industry standard for
met-ocean monitoring. The ADCP is mounted in a frame that is deployed by divers, the frame sits on
the seafloor so that it is constantly orientated upwards to the sea surface. The unit should be
configured based on the depth of water with the following parameters being recorded and stored
internally: Current speed, Current Direction, Water Temperature, Water Depth, Wave Height, Wave
Period and Wave Direction. The current output should be every 10 minutes whilst wave data should
be output every 60 minutes.
Page 52 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
This deployment configuration should be suitable for measuring non-directional wave data (e.g.
significant wave height, peak period) for wave periods of approximately 2.2 to 12 sec. Directional wave
data should be suitable for wave periods of approximately 3.5 to 12 sec. Data analysis of all collected
data should be performed according to the EIA requirements, i.e. time series of speed and direction,
wave height, period and direction.
Bathymetry Survey
Minimum requirement includes a multibeam bathymetric survey, which should allow for 100% seabed
cover. For high resolution the R2Sonic 2024 Multibeam Echo sounder (MBES) is preferred.
The instrument for the multibeam bathymetric acquisition should be coupled with an industry
standard motion, heading and positioning solution. The MBES system maintains an excellent bottom
detection solution with clean data delivery in hand with tightly coupled inertial navigation solution
taking control of the motion, heading and positioning. All devices are to be 1PPS time stamped using
the TTL pulse and ZDA time stamp to eliminate latency.
If benchmarks are available, and within RTK range, the survey should be run using a fixed RTK GPS
solution providing near centimetric resolution positioning solution (x, y, z). The base station should
ideally be installed over a known/established BM in a suitable location with line-of-sight coverage of
the entire survey area. Survey lines should be run at approximately 4.5 times water depth parallel to
the breakwaters, or seabed contours to achieve 100% seabed coverage.
The survey should be done as close to high water as possible at shallow areas to maximize coverage.
In areas close to the breakwaters the beams should be focused to one side to allow data to be
collected on slopes or into the shallows.
In the event that any section of the survey area is beyond RTK range, data should be reduced to the
survey datum using tidal records.
An MBES Patch Test (PT) calibration should be conducted to industry standard before the start of the
survey. This should allow for the correction in the alignment for the primary and secondary (if used)
antenna base line computations, and MBES sonar head alignment (PT – roll, pitch and yaw
misalignment).
In addition to the initial static position GPS bench mark (BM) check for the rovers prior to
commencement of survey works, a dynamic position check over a known feature should be performed
daily, prior to commencement of all hydrographic survey works. Sound velocity profiles (SVP) should
be applied to the survey acquisition software for correction of the MBES ray-path tracing though the
water column. At least two (2) SVP casts should be performed on site during each survey day.
QPS QINSy8 survey software should be used for data acquisition. The software is an internationally
recognized software widely utilized in the hydrographic survey industry and has all the necessary
checks and balances in place to provide online QA/QC (including TPU/TPE).
Any areas considered too shallow for multibeam survey (3-5 m) should be covered by single beam
bathymetry at a line spacing of 25 m line spacing.
A Geoacoustics or similar sidescan sonar should be used to scan the seabed within the survey
corridors. The sonar should be towed from the stern of the vessel at a constant speed. Layback
calculations from the GPS positioning system should also logged. Several sweeps should be made to
Page 53 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
ensure full coverage of the survey corridor, with overlap of data on each successive run. Data should
be processed using Coda Geokit or similar.
Sub-bottom Profiling
An Applied Acoustics towed array boomer should be used to gather geophysical data. Lines should be
run at 20 m intervals parallel to the corridor centerline. The acoustic source should be towed astern
of the vessel along with the hydrophone streamer. Data should be logged and processed using Coda
Geokit software or similar. Positioning should be supplied by Trimble DSM 232 single frequency dGPS
utilizing a free-to-air correction signal transmitted by MENAS.
Geotechnical investigations can be done in either seabed mode (where the sampler or in-situ testing
tool is deployed directly from the seabed) or in drilling mode (where the tool is deployed from the
bottom of a borehole). In seabed mode, penetration depths are normally limited between 20 m and
60 m, depending on type of soil and capacity of rig. In drilling mode, great depths are achievable.
Drilling is normally done from vessels or platforms in which case all penetration depths of geotechnical
interest can be investigated.
• Mobilizing and demobilizing marine self-elevating platform (SEP) that can operate in water
depth up to 8 m or boring vessel that can operate with unlimited water depth;(ref. Table 3.14
is presenting recommended drilling systems):
• Drilling one (1) marine near shore borehole every 1000 m up to 10 m below seabed level along
the pipeline route, including SPT/sampling in soil and continuous coring rock;
• in-situ testing methods include (piezo) cone penetration tests ((P)CPT) with pore pressure
measurements;
• Field vane Tests, T-bar and ball probe tests in soft clays;
• Performing physical, mechanical and chemical laboratory testing of soil and/or rock;
• Factual reporting.
Table 3.14 – Water depth and penetration capabilities drilling, sampling and coring systems
Vibrocorer 1000 m 3 m to 8 m
Page 54 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Seabed Push-in Sampler 250 m 1 m to 2 m
Some coring and drilling equipment exists which operate from the seabed. These allow investigations
up to 100 m below seabed.
For undertaking of the marine geotechnical scope of work, a rotary drilling rig, mounted on a Jack-up
Amphibious Pontoon or similar should be mobilized to the survey site. The rig should be equipped
with all attachments and accessories necessary for drilling, sampling and testing.
All collected samples should be taken to the mobile lab on board the jack-up rig, where the following
should be performed:
• Disturbed samples should be taken one (1) for each type of soil;
• Rock core samples should be taken one (1) for each type of rock;
• Groundwater samples should be collected; and
• General soil characteristics descriptions should be made and noted onto a field sheet.
In soft to stiff clays, soil sampling should preferably be performed with piston samplers. When piston
samplers are impractical, thin walled push-samplers should be tried or, in dense sand, hammer
samplers may have to be used. In some cases, such as in boulder clays and cemented soils, rock coring
techniques may be necessary.
Once field work is complete, all samples should be securely transported to the analytical laboratory
along with full CoC documentation. If there is any concern that contamination has occurred, the
sample and container should be discarded and a fresh sample should be collected. Once at the
analytical laboratory, the borehole sample sets should be analyzed for the following parameters
following the ASTM Standards for soil/rock analyses and geological description, see also Laboratory
tests for borehole Section for the details about all methods:
Page 55 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Chemical tests:
o pH;
o Hydrocarbon;
o Sulphate, Calcium, Sodium, Nitrate, Potassium and Chloride;
o Total dissolved solids; and
o Organic materials.
These tests are intended to be minimum requirements for marine geotechnical investigations,
additional tests should be added depending on project specifics.
• Desktop study
• Hydrodynamic modelling;
• Moisture Content; carried out by standard oven drying method in accordance with BS1377:
part 2: clause 3:1990;
Page 56 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Particle Size Distribution with Hydrometer Analysis; the wet sieving plus hydrometer method
used in accordance with BS 1377: part2: clause 9.2, 9.4 & 9.5: 1990. To obtain an accurate
determination of the particle size distribution of the smallest fractions, hydrometer tests
should be conducted on every sample with fines >5% and d10, d30, d50 and d60 should be
reported;
• Standard Chemical Tests of Soil and Water. These tests should include T, pH, dissolved oxygen,
Sulfate as SO 3 and as Chloride Cl- as per BS1377: part3: clause 5.5/9.5:1990 and 8:1990 and
Total Water Soluble Salts for soil tests as per BS1377:Part3 Clause 8:1990;
• Standard Test Method for Load Controlled Cyclic Triaxial Strength of Soil (ASTM D5311 /
D5311M – 13). Cyclic triaxial strength test is a commonly used technique for determining cyclic
soil strength. Results are used for evaluating the ability of a soil to resist the shear stresses
induced in a soil mass due to earthquake or other cyclic loading;
• Standard Test Methods for One-Dimensional Swell or Collapse of Soils ASTM D4546 - 14. This
standard covers two laboratory test methods for measuring the magnitude of one-dimensional
wetting-induced swell or collapse of unsaturated soils and one method for measuring load-
induced compression subsequent to wetting-induced deformation.
In the case where new carriageway construction are planned, the following tests should be carried
out to evaluate the mechanical strength of natural ground, subgrades and base courses beneath:
• Unsoaked and 4-day soaked California bearing ratio (CBR) on specimens compacted at three
(3) levels of compaction (15, 31 and 62 blows). The CBR (soaked & unsoaked) tests performed
in accordance to BS1377: part4: clause 7.2.4.2 using 4.5 kg rammer. The period of soaking was
4 days;
The following laboratory test should be carried out in accordance with BS 1377:1990 "Method of Test
for Soils for Civil Engineering Purposes" in accordance with project specification, and with ASTM
standards.
• Moisture Content; carried out by standard oven drying method in accordance with BS1377:
part 2: clause 3:1990 or Based on ASTM D2216 – 10;
• Particle Size Distribution with Hydrometer Analysis; the wet sieving plus hydrometer method
used in accordance with BS 1377: part2: clause 9.2, 9.4 & 9.5: 1990.To obtain an accurate
determination of the particle size distribution of the smallest fractions, hydrometer tests
Page 57 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
should be conducted on every sample with fines >5% and d10, d30, d50 and d60 should be
reported;
• Cerchar Scratch Test and Determination of Cerchar Abrasivity Index; In order to choose the
excavation method and estimate the excavation rates and wear costs, Cerchar scratch tests
should be performed for different lithologies within structure range or on remarkable abrasive
sample (i.e. chert) in accordance with ASTM D7625 : 2010;
• Method A (ASTM D7012 – 14) - Triaxial Compressive Strength of Undrained Rock Core
Specimens Without Pore Pressure Measurements; Methods A determine the triaxial
compressive strength at different pressures and can be used to determine the angle of internal
friction, angle of shearing resistance and cohesion intercept;
• Method B (ASTM D7012 – 14) – Elastic Moduli of Undrained Rock Core Specimens in Triaxial
Compression without Pore Pressure Measurements; Methods B determine the triaxial
compressive strength at different pressures (as per method A) and can be used to determine
the angle of internal friction, angle of shearing resistance and cohesion intercept. In addition,
Methods B specify the apparatus, instrumentation, and procedures for determining the stress-
axial strain and the stress-lateral strain curves, as well as Young’s modulus and Poisson’s ratio
(as per following method D);
• Method C (ASTM D7012 – 14) – Unconfined Compressive Strength of Intact Rock Core
Specimens; Methods C (Unconfined Compressive Strength (UCS)) determines the unconfined,
uniaxial strength (as per following method D), and is one of the most basic parameters of rock
strength, and the most common determination performed for boreability predictions. It is
measured in accordance with the procedures given in ASTM D7012 – 14 and very important
assessment in mechanical excavation by tunnel boring;
• Method D (ASTM D7012 – 14) - Elastic Moduli of Intact Rock Core Specimens in Uniaxial
Compression; and Option A - Elevated Temperatures. Method D determine the unconfined,
uniaxial strength (as per Method C), and specifies the apparatus, instrumentation, and
procedures for determining the stress-axial strain and the stress-lateral strain curves, as well
as Young’s modulus and Poisson’s ratio (as per method B);
• Direct Shear Test of Soils under Consolidated Drained Conditions (ASTM D3080 / D3080M –
11); this test method covers the determination of the consolidated drained shear strength of a
soil material in direct shear. Generally, three or more specimens are tested, each under a
different normal load, to determine the effects upon shear resistance and displacement, and
strength properties such as Mohr strength envelopes.
• Standard Chemical Tests of Soil and Water; these tests should include T, pH, dissolved oxygen,
Sulfate as SO 3 and as Chloride Cl- as per BS1377: part3: clause 5.5/9.5:1990 and 8:1990 and
Total Water Soluble Salts for soil tests as per BS1377:Part3 Clause 8:1990;
• Packer testing in rock; should be performed in the rock unit mainly for dewatering design, at
the desired depth (i.e. depth of planed foundation or pipeline level). It is suggested that a
revised specification should be adopted (as described in Walthall, Packer testing in
geotechnical engineering, Geological Society, London, Engineering Geology Special
Publications 1990, v. 6, p. 345-350 doi: 10.1144/GSL.ENG.1990.006.01.38), other than that
given in BS 5930 and other standards, in order to improve the quality of the test and the
information obtained. In particular, it is suggested that, wherever possible, outflow testing
Page 58 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
should be used and, under normal conditions, a testing pressure not exceeding 25% of the
hydrostatic head, or 10 m head for deep wells, should be used for reliable measurements. Large
differential heads only should be used to investigate hydraulic fracturing and associated
problems;
• Standard Test Method for Load Controlled Cyclic Triaxial Strength of Soil (ASTM D5311 /
D5311M – 13). Cyclic triaxial strength test is a commonly used technique for determining cyclic
soil strength. Results are used for evaluating the ability of a soil to resist the shear stresses
induced in a soil mass due to earthquake or other cyclic loading;
• Standard Test Methods for One-Dimensional Swell or Collapse of Soils ASTM D4546 - 14. This
standard covers two laboratory test methods for measuring the magnitude of one-dimensional
wetting-induced swell or collapse of unsaturated soils and one method for measuring load-
induced compression subsequent to wetting-induced deformation.
Note: The Standard Test Method for Determination of the Point Load Strength Index of Rock and
Application to Rock Strength Classifications (ASTM D5731 – 08) can be required in some cases. This
test is only used to determine compressive strength of rock specimens. However, it should not be
considered as a priority test, since it is a time-consuming and expensive test that requires significant
specimen preparation, the results may not be available for a long time after the samples are collected,
and the test results should not be used for design or analytical purposes.
• Cohesion;
• Density;
• Friction Angle;
• UCS;
• Elastic Modulus;
• RQD (Rock Quality Designation).
In addition, the following foundation discussion and recommendations should be included, but not
limited to:
The work described herein should include review and correlation of various test results as to
embankment stability, material placement, and other geotechnical engineering considerations.
Sketches, assumptions, calculations, etc., (where applicable) of all final engineering analyses should
be included in the appendix of the report. The source of the analysis, the input and output data
(properly labeled) all should be provided if computerized analysis methods are utilized. The
Page 59 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
geotechnical engineer should also attend all field checks. Methods of analysis should be approved in
the proposed work plan.
Where deep foundations will be used, a geotechnical investigation shall be conducted and shall
include all of the following, unless sufficient data upon which to base the design and installation is
otherwise available:
3. Driving criteria.
4. Installation procedures.
5. Field inspection and reporting procedures (to include procedures for verification of the installed
bearing capacity where required).
3.2.5 Specific Recommendation for Engineering Fill, Soil Replacement & Soil Improvement
Soil replacement is when existing poor quality soil is removed and fresh soil is backfilled and brought
up to grade. Soil improvement on the other hand, is alteration of existing soil properties in order to
improve its engineering characteristics.
Recommendations should be provided on engineering fill, soil replacement and soil improvement and
the following should be undertaken as a minimum:
The suitable engineering materials should be in accordance with the minimum required approved
specifications, degree of compaction, density and moisture content (ASTM D 1557).
Page 60 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Earth filling under floors should be done in layers not more than 150 mm in thickness. The layer should
be compacted properly. Further, the earth used for filling should be free from grass, roots, leaves and
other foreign material. It should be also slightly moist which should help to achieve optimum
compaction.
Compaction should be undertaken by using a roller. As a rule of thumb to obtain the required
compaction effort, the following should be carried out as a minimum:
• The fill material must be homogeneous and isotropic; that is, the soil must be all of same
composition, and the engineering properties must be the same in all directions;
• Where several different types of fill material (all meeting the requirements of Section 2 of this
specification) are to be used, they should be deposited in such a way that all parts or particular
sections of the site receive roughly equal amounts of a given material, in roughly the same
sequence, thus ensuring a uniform distribution of fill types over the whole fill thickness.
• Cobbles, boulders, rock or waste fragments, the largest dimension of which is greater than
two-thirds of the compacted layer thickness (i.e. 150 mm), should not be incorporated into
the fill;
• All fill material should be placed in layers (or lifts) no greater than 150 mm thick;
• The following type is recommended as per Figure 6.1, specification are given in Table 3.15 5.
o 1.5 m of granular fill material.
o 1 m of special fill material.
Table 3.15 – Particle size distribution of fill material
• As guideline, the largest size particle should not be greater than 1/3rd the height of the lift,
that is, 50mm. Each layer should be thoroughly compacted before the next layer is placed. A
minimum of 6 passes to achieve the required compaction effort is generally required by a
suitable machine. Table 3.36 below provides the recommended requirements:
Page 61 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Table 3.36 – Compaction requirements
• The compaction effort achieved should be on average 98% Standard Maximum Dry Density
(MDD) (non-structural fill), for any building constructed on the fill, the compaction should be
95% of ASTM d1587-modified compaction (structural fill). If the range of compaction effort
varies, then it can lead to differential settlements;
• The material should be placed with sufficient moisture to ensure proper compaction. The
moisture content should be in the range of around 11%. If the material is too dry, water
Page 62 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
should be added. If the material is too wet it should be spread and mixed. Compaction test
should have to be performed on the fill material
To determine if proper soil compaction is achieved for any specific construction application,
several methods are used. The most prominent by far is soil density.
• Before each additional 150mm lift, the preceding lift should be scarified to ensure that the
two lifts are properly joined;
• Vehicles with crawler tracks are not suitable, as high compaction levels are not achieved.
Likewise, compaction using a scraper tyre should not be used as the required compaction
effort should not be achieved.
Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort
(56,000 ft-lbf/ft3 (2,700 kN-m/m3)) ASTM D1557 - 12e1 should be used to test the degree of soil
compaction achieved.
The material to be used as Structural Fill shall be granular materials, suitable for use as construction
fill with the following mechanical and chemical properties:
• The material shall be free from organic matters or other deleterious substances.
• The material shall be well graded granular borrow pit mixture with structural quality.
• At least 85 % of material shall be smaller than 38.1 mm in size.
• The percentage passing from sieve size 0.425 mm shall be ranged between 10 % and 60%.
• The material passing sieve size 0.075 mm (# 200) shall be less than 15 %.
• Liquid limit (LL) shall be not more than 20 %
• Maximum Plasticity Index (PI) of 6 % (preferable to be Non‐Plastic).
Page 63 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• The coefficient of curvature “Cc” regarded as the ratio of the square of 30‐percent‐finer than
size (D30) to the product of (D60) by (D10) shall be between 1 and 3.
• The coefficient of uniformity “Cu” regarded as the ratio of the 60‐percent‐finer than size
(D60) to the 10‐percent‐finer than size (D10) shall be greater than 4.
• Maximum Chloride content expressed as Cl shall not excess 0.05 %.
• Maximum Sulphate content expressed as SO3 in 2:1 water: soil extract shall not exceed 1
grams/liter in 2:1 soil water extract.
• Sulphate and Chloride contents shall be determined in accordance with BS 1377.
3.2.6 Specific Recommendation for Deep Structures, Piling, & Stone Columns
If deep foundation are most likely required, recommendations should be provided. Some of the
specifics are given in the following sections.
Figure 3.6 – Approximate formula for the allowable bearing capacity of stone columns (Bowles 1996).
Stone columns should extend through the sand layers of stratum 1 and 2 to the firmest stratum 3 to
control settlements. There is no end bearing in Eq. (21.11) (Figure 3.6) because the principal load
carrying mechanism is local perimeter shear. Settlement is usually the principal concern with stone
columns since bearing capacity is usually quite adequate (Bowles, 1996). There is no method currently
available to compute settlement on a theoretical basis.
Page 64 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
depth to the neutral plane should be estimated and compared to the estimated settlement profile to
consider pile settlement (downdrag).
• Establish benchmarks and topographically survey and inspect routes for interference.
• Provide the preliminary resistivity section and preliminary interpretation result and undertake
drilling of boreholes required for the calibration of the resistivity results.
Page 65 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The determination of elastic parameters such as Young’s modulus and Poisson’s ratio are significant
to demarcate the damage zone around circular opening of tunnels or micro-tunneling, horizontal
directional drilling or other non-disruptive methods.
E Soft Soil Any profile with more than 3 m of soil with the following
characteristics:
• Plastic Index PI ˃20
• Moisture content w ≥ 40%, and
• Undrained shear strength su ˂ 25 kPa
F Others Site specific evaluation required
3.2.9 Reporting
3.2.9.1 General Requirements
All methodology, progress and results of the field investigations and laboratory analysis should be
documented and used to develop comprehensive factual reports.
Ultimately, a geotechnical interpretative report should be created based on data that were collected
in the course of the various site investigations campaign. The geotechnical interpretative report
should contain an assessment on the results of the field works, field and laboratory tests and include
recommendations.
The complete Geotechnical Report (in min. 3 copies), stamped and signed by a Professional Engineer,
must include the following as a minimum:
• Project Description
• Site Conditions (Topographic, Geological, Hydrogeological Setting)
• Geotechnical Surveys Description (scope of work)
• Geotechnical Investigation Results
Page 66 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Geotechnical Engineering Analysis
• Recommendation
• Summary and Conclusion
• Attachments (samples and templates in Appendix)
o Attachment A ‐ Boring Plan Map
o Attachment B ‐ Historical Boring Logs
o Attachment C ‐ Geotechnical Report Summary Table
o Attachment D ‐ Soil Boring Logs (with stratigraphy, SPT, UCS, Shear tests and water
levels, see Appendix C for a Borehole log sample)
o Attachment F ‐ Geological profile and Long- and cross-sections along the pipeline
alignment
(a) Sheet 1 — Title Sheet. This may be a reproducible of the title sheet used by the design
Consultant for the design plans, modified as necessary.
Page 67 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
(d) The geotechnical profile plan and profile sheets with the borings and data should be
plotted to a vertical scale of not more than 1" = 10', and to a horizontal scale of not more than
1" = 100'. Each sheet should be identified by control section, structure number, and project
and route number, and the scale to which it is drawn.
(e) Elevation of subsurface water levels recorded during the boring, at completion of boring,
and 24 hours later, should be indicated by suitable symbols. The use of colour as a symbol will
not be permitted.
(f) Additional sheets as required should be used to plot soil or rock cross sections, peat or
unstable soil profiles, rock profiles, etc.
(2) The geotechnical profile should be prepared in ink on linen, mylar, or other material with prior
approval, to provide permanent originals which will not deteriorate or fade with age.
3.2.10 Supervision
3.2.10.1 General
All phases of the geotechnical investigation, including boring and sampling, laboratory testing,
analyses, and preparation of the geotechnical report, should be under the direct supervision of a
qualified geotechnical engineer.
3.2.10.2 Scheduling
After the preliminary field check, as previously mentioned, the scope of work for the project should
be defined on a tentative basis. The Contractor geotechnical engineer will send in writing a work plan
for the completion of the field work and the date when the complete geotechnical report and profile
will be transmitted to TRANSCO foundation analysis engineer. This will be done immediately after the
preliminary boring location plan is approved. If it appears that the aforementioned schedule has to be
changed during the progress of work, the Contractor geotechnical engineer should send in writing the
revised schedule and a statement explaining the reasons for the schedule change.
Page 68 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
As a first step for obtaining the NOC from EAD, an environmental permit application shall be
completed by the design Consultant for the proposed project and submitted to EAD (Refer Technical
Guidelines for Permit Application on www.ead.ae). The environmental permit application should be
submitted during the preliminary design phase of the project to ensure that alternatives can be
considered and that all the required environmental studies can be completed and approved in a timely
manner without affecting the project schedule.
If an environmental study is requested then EAD requires that the study be carried out by an EAD-
approved and registered Consultant operating within Abu Dhabi Emirate and be independent of the
design Consultant. The EAD approved environmental Consultant shall prepare the environmental
studies (either PER, EIA or SEA) as per EAD technical guidelines prescribed for the specific
environmental study.
The permitting of infrastructure projects shall also comply with the requirements of Abu Dhabi
Occupational Safety and Health System Framework (OSHAD-SF).
The Contractor is to appoint an EAD-approved and registered Consultant to prepare the CEMP. The
CEMP shall be prepared in accordance with EAD’s Technical Guidance Document for CEMP and should
be referenced in Tender Documents.
If an operating permit is required by EAD, then Operation Environmental Management Plan (OEMP)
shall be prepared by an EAD-approved and registered Consultant appointed by the Contractor. For
many infrastructure projects, an OEMP may not be required. If required, the OEMP shall be prepared
in accordance with EAD’s Technical Guidance Document for OEMP.
If a project requires plans to decommissioning of any infrastructure project (or a portion of a project),
the Contractor should submit an environmental permit application to notify EAD of the planned
activities. EAD will likely request a Decommissioning Environmental Management Plan (DEMP).
Additional guidance about the DEMP’s contents can be found in EAD’s document, Technical Guidance
Document for DEMP. All waste generated from decommissioning activities shall be disposed as per
Centre for Waste Management, Abu Dhabi (CWM-AD) requirements.
Page 69 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
3.3.3 Environmental Issues to be covered in the CEMP
The CEMP prepared by Contractors Environmental Consultant should cover management of
discharges from construction activities. Construction projects will generally include construction of
pipeline networks, pump stations and reservoirs. These activities during construction are expected to
generate large amounts of waste and wastewater. Construction activities are expected to generate
waste from dewatering, excavation, land clearing, vehicle and equipment maintenance, demolition,
concrete washout, general sanitary wastes, chemical wastes and other hazardous wastes, etc. The
Contractors Environmental Consultant prior to the commencement of construction phase shall
identify all sources of wastes expected from the construction activities and develop the CEMP and
corresponding environmental control plans including best management practices to avoid any
environmental impacts from construction activities. The CEMP shall also identify pollution prevention
measures to ensure pollutants are not discharged into the environment. As a minimum requirement,
EAD’s ‘BMP Technical Guidance Document for Discharges from Construction Activities’, April 2014
shall be complied by the Contractors.
Page 70 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The requirements for determining pipe wall thickness in steel pipe are set out below.
Line Piping
Where
S = Allowable stress.
Where
E = Weld joint factor (from 0.6 to 1) given in ASME B31.4 Table 402.4.3
Station Piping
Page 71 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Pipe Thickness is determined from the equation
𝑃𝑃𝑃𝑃
𝑡𝑡 =
2(𝑆𝑆𝑆𝑆𝑆𝑆 + 𝑃𝑃𝑃𝑃)
Where:
W = Weld Joint Strength reduction factor as per para. 302.3.5e from ASME B31.3
For Ductile Iron Pipes the wall thickness is defined in EN545 by pressure class
For HDPE Pipes the wall thickness is defined in ISO 4427 by pressure class
Where:
FS = Factor of safety =2
EI = pipe stiffness
D = diameterof pipe mm
For HDPE pipe design for buckling is determined from AWWA M55 Section 5, using the following
equations .
Page 72 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Page 73 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
3.4.2.4 Design for Deflection
Pipeline deflection for steel pipe due to earth loading and traffic loading is calculated as per the
method set out in AWWA M11 Chapter 6. The following equation sets out the calculation method
which is based on the interaction between the deformed pipe and surrounding soil.
Where:
R = Radius mm
Deflection methodology for ductile iron pipe is covered in both EN545 and AWWA M41. Acceptable
depths of cover are presented for the range of pipe diameter, pressure class and trench conditions.
Deflection methodology for HDPE Pipe is set out in AWWA M55 and the relevant equations given
below.
Page 74 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Normal pipeline conditions (buried line piping) where detailed stress analysis may not be
required;
• Specific cases (station piping and non-buried pipelines on supports) where detailed stress
analysis has to be considered.
Much of the content of this section relates to carbon steel pipes and therefore reference should also
be made to ADWEA Standard Specification w-p-ss-002 and the following codes and standards.
Pipelines are classified as either station piping or line piping. Station Piping is defined as pipework
commencing at the pump station site upstream boundary and finishing at the point where the
discharge header exits the pump station site. Line piping is defined as the pipework extending from
the pump station discharge point to the downstream storage tank/reservoir or customer take off
point. This guideline section on pipe stress analysis applies to both line and station piping.
Engineering attributes such as HSE, Quality management, Meteorological and Ambient Conditions etc.
are discussed in Section 4 General Design requirements.
To confirm that piping system stresses and section loads, e.g. at new flange connections are within
the limits allowed by the applicable codes and standards.
To confirm that piping deflections and slopes are within the limits allowed or prescribed by the
applicable codes and standards.
To provide for the piping reaction loads at each support to check the integrity of the structure and to
enable the design of supports, anchors, guides and line stops, etc.;
To confirm that piping loads at connection to existing lines comply with specification requirement.
Page 75 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
To ensure that nozzles loadings on the attached new equipment are within allowable limits specified
by manufacturers or recognized standards.
The stress analysis shall be carried out using a recognized pipe stress analysis software package, such
as CAESAR II, Auto Pipe or equivalent. A stress analysis need to be carried out for piping with
pressure restrained joints only, i.e. welded joints, flanged joints. The piping system should have
sufficient flexibility to prevent thermal expansion or contraction from causing:
The following shall be considered where applicable when analyzing stresses and external loads on
the piping systems.
(13) Solar radiation temperature in combination with an empty pipe (for aboveground piping only).
For support design, combinations of the above loading conditions as applicable shall be considered.
The design/routing of the piping system shall take into account different conditions expected during
operation such as dry‐out, start up, shut down, cold branch etc. When the routing of a piping system
does not inherently provide adequate flexibility, the needed flexibility must be provided by
additional bends, offsets or expansion joints.
The stress analysis model should include all pipes, valves, bends, tees, reducers, nozzles, couplings,
expansion joints and other fittings. This will require the Contractor to obtain the necessary
properties of fittings including basic geometry, wall thickness, end joint details, material properties
and details seam welds, mitres etc.
Page 76 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
3.5.3 Design Loads
Pipeline design should take into account the following loads where applicable with pipe wall thickness
based on the most severe combination of loads:
a) Internal Pressure
• Test pressure
• Surge pressure
• Vacuum condition
b) External Pressure
• Trench loading
c) Friction Loading
The effect of friction shall be calculated based on the following:
• Coefficient of friction between soil and pipe TAN ɸ where ɸ is the soil angle of internal
friction.
• Coefficient of friction between Carbon Steel to Carbon Steel with using PTFE is 0.10
• Coefficient of friction between Carbon Steel to Carbon Steel is 0.30
e) Temperature Stress in restrained pipelines (refer also to Section 4.1 for meteorological
and Ambient Conditions)
f) Dead loads arising from the weight of pipes, valves, service fluid, insulation and any other
permanent loads.
Page 77 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
g) Seismic Effects
Seismic load shall be calculated as per Abu Dhabi International Building Code (ADIBC) and
the related ACI/AISC/ASCE/SDPS. The seismic zone for UAE shall be taken as per the
guidelines of the subject Code and the Contractor shall reconfirm with the concerned
Municipality based on their latest circular in respect of the above.
Therefore the temperature ranges between the installation temperature and both maximum and
minimum temperature will be considered.
Page 78 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
Where:
If a longitudinal stress 𝑆𝑆𝑙𝑙𝑙𝑙 exists near the saddle tips, such as a thermal stress or the beam bending
stress at that depth on the pipe. Then calculate the effective stress, 𝑆𝑆𝑒𝑒 :
The bending stress when the pipe is under pressure is calculated by multiplying 𝑆𝑆𝑐𝑐𝑐𝑐 by a reduction
factor (RF) calculated from
(𝑡𝑡𝑡𝑡𝑡𝑡ℎ𝐴𝐴)
RF =
𝐴𝐴
Where:
Page 79 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
If the pipe is under pressure and the ends are restrained, the Poisson’s ratio effect of the hoop stress
(0.30𝑆𝑆ℎ ) must be added to the beam flexure stress. The total longitudinal stress (𝑆𝑆𝑡𝑡 ) is calculated as
Longitudinal beam deflection is calculated by conventional beam deflection formulae. Foe a single
span the formula is:
For multiple spans of a continuous welded pipe the deflection should be calculated by conventional
structural analysis software.
Page 80 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
For installations where the power supply is at low voltage, the Consultant will follow ADDC/AADC
standard connection procedures
There are two scenarios to consider, a new greenfield site and an expansion of an existing site.
The next step would be to determine the requirements of the distribution company (DISCO) for the
provision of power to the site.
The Consultant would initially write to the distribution company informing them of the project intent
and the estimated maximum power demand and would arrange a meeting with Transco, the
distribution company and the Consultant to discuss the following items.
• The existing capacity of the network, and the extent of any upgrade that would be required.
• Any constraints that could affect the supply of power.
• Any communication requirement
Following the meeting the Consultant shall request the distribution company to provide an initial
estimate for both cost and time frame to supply power to the site and to provide an indication of
any items with long delivery times.
In addition the Consultant needs to inform the distribution company what the expected increase in
demand is. This will be required even if the existing infrastructure has sufficient capacity as the
increased load could still affect the network capability and will assist the distribution company in in
their network planning.
If the power supply to the site needs to be increased a discussion with the distribution company will
be required and if necessary a meeting should be held to confirm any requirements for expansion of
the existing substation, additional cabling requirements and any other requirements. Following the
meeting an estimate as described above should be requested.
Page 81 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The weather conditions of the United Arab Emirates comprise of relatively mild (November to April)
and hot with relatively high humidity (May to October). For that, corrosion precautions need to be
highly considered. UAE has low annual precipitation; however, occurrence of sudden thunderstorms
of short durations is a potential and the Contractor needs to be prepared for such incidents. Moreover,
outdoor equipment need to be protected against dust and sand. For more about climatic condition,
refer to section W-G-SS-001 “Specification for General Technical Requirements” of ADWEA
specifications.
Meteorological and ambient conditions shall be identified as per the location of the project from the
concerned Authorities and subject to TRANSCO/Engineer approval, otherwise the standard conditions
contained in W-G-SS-001 will apply, including minimum ambient temperature of 10 C.
1. Current demand projections for individual areas / developments / bulk consumers are to
be obtained from the Abu Dhabi Water and Electricity Company (ADWEC);
2. ADWEC demands for developments and bulk consumers are to be independently verified
with developers and bulk consumers through official correspondence;
3. New projects and developments within the project coverage area are to be identified, and
demand projections collected from developers and bulk consumers through official
correspondence;
4. Any component of the projections that does not extend up to the design horizon is to be
analysed to determine if it is a build out projection. If not, projections are to be
extrapolated up to the design horizon.
Design and choice of construction materials shall consider and ensure minimizing maintenance works,
and therefore, all elements shall be designed to result in a durable construction considering the
sustainable developments.
Page 82 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The number of hardcopies for each submission shall be dictated as per the project contract
documents. The Hard Copies and soft copies shall be matching. In the event of any discrepancy
between hard copy and soft copies, the Consultant / Contractor will be required to reconcile all three
versions and re-submit.
Drawing requirements are subject to the project stage, as summarized in the following Table 4.1.
Table 4.1 – Drawing Requirements for Various Project Phases.
Drawing Type Concept Design Preliminary Design Detailed Design / Shop Drawings / As-
Tender Drawings Built Drawings
General Layout
Sheet Plan
Network Plans
Network Profiles
Facility Layouts
In addition to the above drawing requirements, the Consultant / Contractor will be required to submit
a cover page and drawing list for each individual drawing package submitted. In case of EPC Contractor
/ Consultant, the list of drawings will be project specific and decided by TRANSDCO. The drawing list
will be presented in the same title block as the drawings, and appropriately numbered. The cover page
and drawing lists will also be included in the soft copy submissions. The drawing list will be presented
in soft copy as both a spreadsheet file (MS Excel compatible) and a *.dwg file(s) (AutoCAD compatible).
Page 83 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
4.5.1 PDF Requirements
PDF soft copies shall be an exact reproduction of the hard copy prints, such that TRANSCO can
reproduce identical hardcopies by the PDF with no loss in quality. PDF prints will be electronic prints
(not scanned), in the correct A1 file page size. Each drawing shall be submitted with one (1) normal
resolution “For Viewing” copy, and one (1) high resolution “For Print” copy.
4.5.2 Drafting Requirements
AutoCAD drawings shall be submitted in accordance with the following minimum requirements, in
addition to requirements as stated in contract documents and the specifications:
4. Elevations shall be presented in accordance with the Ras Ghumays height datum in meters;
5. All Title Blocks, External Reference files, and images (including logos), shall be provided with
the electronic submission with the correct file names as referenced;
6. All elements in the drawing shall be flattened (i.e. have no “Z” coordinate) such that all
drawings are 2-Dimensional;
8. An “exploded” copy (complete independent file with no external referencing) of each sheet
shall be provided as an individual CAD (*.dwg) drawing file;
Page 84 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
7. Drawings shall indicate dimensions, elevations, coordinates and labels as applicable;
8. Variable dimensions shall be presented as tables within the drawing;
9. Symbols, hatchings, and line types shall be used such that, to the extent possible, the drawing
can be correctly interpreted in black and white print.
4.5.4 As Built Drawings
As built drawings shall be prepared by the Contractor for the whole WORKS and shall progress with
time at all project stages. These drawings shall follow the standard format and be accurately scaled.
For record, two sets of As-Built Mark-up Prints shall be kept at site and marked with different colouring
to illustrate whether the component has been constructed according to design drawings, constructed
differently, or deleted. The final As Built Drawings shall be submitted to the ENGINEER for approval
and shall be stamped and initialled before being distributed. The submittal of these drawings shall be
using compact disks in DXF/DWG format AutoCAD release 14 or latest.
Refer to section W-G-SS-002 “Specification for Design, Shop & As Built Drawings”.
Page 85 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
1.2.6 Inspection and Test Plans (ITP's)
1.2.7 Factory Inspection Record Dossiers (FIRD's)
1.2.8 Non-Conformance Reports
1.2.9 Project Risk Register
Page 86 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
2.1.1 Water Transmission lines
2.1.2 Building Equipment
2.1.3 Mechanical Equipment
2.1.4 Electrical Equipment
2.1.5 Instrumentation & Control Equipment
2.1.6 HVAC
2.1.7 Hypo-chlorination
2.1.8 Fire Fighting
2.3 List of Equipment/ Material Receiving and Damage Inspection Reports (RCDR)
(Identified with reference to RCDR ref., Material/ Equipment Description, Total Numbers and
BOQ Reference)
3 Construction QCR
Page 87 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
All quality Records maintained & signed off by the Engineer & the Contractor for every
component of the Work as listed in the various sections herein. These documents will be
separated by Lot.
4.4.1 Records generated during plant and pipe lines initial operations
4.4.2 Acceptance/ Performance Tests
5 Handing Over
(List of below documents to be included)
Page 88 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
7.1 PAC-Exception to Completion
7.2 Committee Inspection Report
7.3 PAC-Signed Punch List
4.6 Approvals
Approvals for the design and construction of proposed works are to be undertaken in the following
stages:
Stakeholder NOCs may include, but not be limited to, the following:
The minimum NOC requirements may be defined by the TPD as part of the approval process.
Approvals may also require that Trial pits and Ground Penetration Radar (GPR) surveys be required
prior to construction.
Page 89 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
In addition the Consultant shall take into account the safety requirements of his design. The design
shall include, but not be limited to, the following:
The design Consultant team must integrate Safety in Design requirements into their project lifecycle
from concept through design and construction, to operation, maintenance and decommissioning.
Safety in Design is a strategy for preventing injuries and incidents by integrating hazard identification
and risk assessment methods early in the design process.
The designer must ensure that the project is capable of being constructed to be safe, can be
maintained safely and complies with all relevant occupational safety and health legislation. The
designers and Contractors should refer to the https://www.oshad.ae for the latest updates and
information guidelines. OSHAD-SF- Code of Practice CoP 20.0 - Safety in Design (Construction) should
be referred for safety considerations in design.
A systematic risk based approach should be used to determine the right solution and reduce the risks
as low as reasonably practicable while ensuring that TRANSCO is aware of the residual risks. Hence
the designer has to liaise and sought advice and input from the principal Contractor/Contractor.
Information required by other designers, the principal Contractor, or other Contractors shall be
provided and communicated appropriately. A written workplace hazard control program as per
OSHAD-SF – Element 2 - Risk Management should outline which methods are being used to control
the exposure and how these controls will be monitored for effectiveness.
Managing Health and Safety during Construction
Prior to receiving approval of any required OSH assessments and before any construction activities
begin, the Contractor on behalf of TRANSCO may be required to submit an OSH-CMP Construction
Management Plan as per OSHAD-SF- Codes of Practice CoP 53.1 - OSH Construction Management Plan
to their respective SRA so that they can issue an NOC/permits for construction. Additional guidance
about the OSH-CMP’s contents can be found in OSHAD-SF- Codes of Practice CoP 53.1 - OSH
Construction Management Plan and should be referenced in Tender Documents. Potential hazards
encountered in such construction activities include but not limited to work at height, falls (from
heights), trench collapse, vehicles and traffic routes, scaffold collapse, electric shock and arc flash/arc
blast, fire and other emergencies, failure to use proper personal protective equipment, plant and
lifting equipment, welfare facilities, health hazards and repetitive motion injuries. The Contractor is
required to comply with TRANSCO System Safety rule in addition to the OSHAD-SF laws, regulations,
mechanisms, standards, Code of Practices and Elements that are relevant to the contract operations.
If a project requires plans to decommissioning of any infrastructure project (or a portion of a project),
the Contractor should submit an OHS permit application to notify DMA of the planned activities as per
Section 5.22 Demolition and Decommissioning of OSHAD-SF- Codes of Practice CoP 53.1 - OSH
Construction Management Plan. Following approval of the DEMP and issuance of the NOCs for
decommissioning, the Contractor may begin related decommissioning activities. All waste generated
Page 90 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
from demolition and decommissioning activities shall be disposed as per Centre for Waste
Management (CWM), Abu Dhabi requirements and OSHAD-SF- CoP 54.0 - Waste Management.
Both the HAZID and HAZOP shall be undertaken as workshops with participation from the following
parties:
1. Identify Hazards;
There are various operational indicators like pressure, flow etc. which can be measured by system
components. The management of these system components using instruments like alarm, data
recorders or any other electro mechanical devices should be described. It’s important to include the
management apparatuses and adequately describe their function as well as management for
operation of the system. The interpretation of these information has to be explained so that end user
can understand during operation.
• At the completion of the hydraulic studies a high level OCP shall be developed by the design
Consultant as part of the preliminary design
Page 91 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• At the final design stage the Consultant shall further develop the OCP (including P&IDs) for
incorporation into the tender documents so that the EPC Contractors can fully understand
how the system is to work when they submit tenders
• The Contractor then will expand the OCP at detailed design stage and obtain TRANSCO
approval prior to ordering major equipment. He will finalise the OCP at the commissioning
stage of the contract
The Consultant may also suggest some general practices and established standards for operation. It’s
important to restate the client’s operational intention or any other specific concern in the operational
philosophy, this may include:
• Control system.
• Mechanical features.
• Electrical features.
• Valves.
Specifics of the various components may not be evident during conceptual phase. As the project
progresses through the phases of detail design, construction and then operation more information
will become available which needs to be detailed out in the OCP. For example the actual settings and
performance of the surge vessel will be possible to specify after construction of the project. Examples
Page 92 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
of more operational features that can be considered for OCP after detail design may include the
number of valves, their location and their settings pump controls, chlorine dozing etc.
Typically the components of the project is connected to a larger network. In addition to the operation
of the project components, the document should also contain how it will operate given the overall
system connectivity and its interaction or influence by the overall system.
For each of these scenarios there should be details of the operational setup considered for different
components. During preliminary assessment the operation of the major components can be identified
from these scenarios. After detail design and construction more specifics are finalized regarding the
system and based on that additional scenarios can be analysed to develop the operation of smaller
components. The OCP needs to be updated accordingly.
Details some specific components which can be included in the OCP are given below.
Detail will be provided for the various components i.e. indicators, their function and control and will
include the following. Any backup system available for operation needs to be also included.
Page 93 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
• Pump local control panel.
• Chlorination.
• Surge vessel.
• Limits of operation.
• Description of pump operation control and logic for various hydraulic conditions including
and specific modes of operation. The scenarios from hydraulic analysis can be further
detailed for better understanding.
4.9.4.6 Operation and Control of any Important Connection Points, Tap Offs, Branch Line Control
etc.
The document should include description of important connection points, tap offs and branch line
control and their operation. This will include logic of operation, description of control system, status,
manual operation options, operation of different fixtures like CV, MCV, and PRV etc.
Page 94 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
4.9.4.8 Operation of Control of Surge Vessels and Air Compressors
The number surge vessels and their operational settings has to be described. The parameters typically
used are air pressure, water level, actual temperature, air energy etc. The values for these parameters
related operation of the vessel including design criteria has to be described. Any future change in the
settings for different operation condition will be in the OCP.
Value Engineering needs to be carried out during preparation of the PDR and the FDR. The Consultant
is to carry out workshops as agreed with TRANSCO at both the PDR and FDR stage of the project and
provide a Value Engineering Report following each workshop.
In all stages of the project the Consultant and Contractor shall work with TRANSCO to develop and
maintain a risk register and risk mitigation plan. Workshops are to be held with TRANSCO at each stage
of the project to identify risks, allocate likelihood, impact and mitigation measures. The PDR shall
contain a section on risk management strategy and this is to be further updated through the final
design process and incorporated into the final design report. The risk management process is to be
taken over by the Contractor and managed through to completion of the project.
Page 95 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
5 Civil Works
5.1 Design Codes
Contractor/ Consultant shall perform the structural design based on Abu Dhabi International Building
Code (ADIBC). Alternative design codes (BS, EN, etc…) may be used subject to ADWEA approval.
CIRIA GUIDE -The CIRIA Guide to Concrete Construction in the Gulf Region
ASCE 7 -05 -Minimum Design Loads for Buildings & other Structures.
ACI 318 – All Parts -Building Code Requirements for Structural Concrete Commentary
AISC S100 -07 -North American Specification for the Design of Cold – Formed Steel
Structural Members.
ACI 530.1 -08 -Building Code Requirements and Specification for Masonry
Structures & Related Commentaries.
BS 8004 -Foundations.
Page 96 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
BS 2573 -loads for crane Gantry Girders, BS 2655 'loads due to lifts' and loads
due to machinery, vibration, construction, and test loads etc.
AISC S100 -07 North American Specification for the Design of Cold – Formed Steel
Structural Members.
During the survey, benchmarks should be established to facilitate geotechnical investigations and
construction set out. The number of permanent/ intermediate/ temporary benchmarks should be
agreed with TRANSCO prior to commencement of survey.
The survey report should be in accordance with the ADWEA Standard Specification plus any specific
requirements set out in the terms of reference for the project.
Geotechnical investigations should be carried out in accordance with ADWEA Standard Specification
w-c-ss-002 and more specifically in accordance with Section 3.2 of this design guideline.
Page 97 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
The following guidelines for the type of construction should be followed by the Consultant /
Contractor subject to the specific project requirements and Engineer approval. They should also be
read in conjunction with the mechanical guidelines:
Pump Stations will have some or all of the following facilities:
The service buildings to the pump hall shall be of reinforced concrete structures. The walls shall be of
concrete block for 1 m bottom height and remaining of aluminium sandwich panels cladding. The roof
shall be of reinforced concrete.
Page 98 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
integral with the raft. Where the footing slab is a separate floating slab, then pump footings are
independent of the floor slab being separated by 20mm joint with compressible joint filler and sealant
as per specification.
Concrete reinforced roof shall be provided with waterproofing and heat insulation. The roof shall be
provided with 1m parapet wall and adequately sloped to avoid puddle and drained through rainwater
pipes.
The pump hall will generally be constructed below grade to provide the most advantageous hydraulic
conditions for the pumps. Reservoirs supplying the pumps will normally be located at grade, thus
always providing positive head to the pumps.
Walkways, stairs and access are also described in the Mechanical Works section of this guideline.
There should be adequate space around equipment within the pump hall for access to carry out the
O&M activities. The space requirements shown in the typical drawings in the Appendix will be
followed. The pump hall should have adequate space for loading / unloading of mechanical equipment
/ pumps directly from overhead travelling crane to trucks. The floor should have adequate slope to
eliminate any puddle and connect to a drainage channel and a sump pit.
Access and escape routes shall be in compliance with Civil Defence requirements. Where possible, the
pump hall shall be directly visible from SCADA work station.
There shall be clear pathways to all maintenance points such as gland packings, grease nipples etc.
Pathways shall be without any obstructions and without any need to remove or modify any stairs,
ladders, walkways or platforms for routine maintenance access.
Access platforms shall be installed at a height where equipment can be reached easily and without
the need for additional ladders or platforms.
Easy access to confined spaces shall be discouraged. Openings shall be big enough for easy emergency
rescue of personnel in case of accidents.
Escape routes for personnel shall be different than access routes for equipment. This is to prevent
situations where escape route is blocked by unloading of equipment for example.
Separate escape routes shall be provided for personnel.
An example of that is a roller shutter door in the pump hall for equipment access and a single leaf door
next to it for personnel access and escape.
All perimeter access doors shall open outwards in the direction of escape.
Page 99 of 233
Abu Dhabi Transmission & Despatch Company (TRANSCO)
N-14054
Design Guidelines
5.4.3.2 TRM and QRM Room
TRM / QRM room, if required, shall be provided to house ADDC ring main unit (RMU). As far as
possible, the TRM / QRM room shall be provided on the boundary wall with direct access from outside.
The room shall be provided with dual air-conditioners, each 18000 BTU split air conditioner, and shall
be provided with adequate lighting. The TRM / QRM room shall be of permanent nature constructed
in reinforced concrete and block work. Double access shall be provided, each with minimum 1.5m
wide single leaf door of 3m height. TRM / QRM support shall be provided in line with ADDC
requirements.
The finished floor level shall be kept at minimum 300mm above finished ground level and its minimum
height shall be 3.5m.
A 1m deep cable trench shall be provided as per ADDC requirements.
5.4.3.3 Substation
The provision of substation, whether private or ADDC supplied, is governed by ADDC regulation based
on the total connected load.
In the case, the substation is supplied by ADDC, its location and civil works requirements are also
governed by ADDC. The Consultant/Contractor shall take full cognisance of ADDC standard drawings
and details and ensure compliance.
In the case of private substation, in general the transformer and switchgear rooms shall be adequately
sized with proper room and access for O&M requirements with minimum 2m clearance around
equipment.
The private transformer shall be housed in a permanent structure constructed in reinforced concrete
and blockwork in compliance with local statutory requirements. For, natural ventilation, cross
ventilation of adequate size shall be considered depending on the amount of equipment generated
heat and its allowable temperature rise. The transformer room shall be provided with covered cable
trenches. The cable trench layout shall be designed to avoid any crossing of medium and low voltage
cable trenches. For ease of maintenance, each transformer room shall be provided 3m wide front
verandah with transformer transportable U-channel encased in floor. Where deluge protection is
provided, adequate drainage facility shall be considered. The fireseal of trenches, ducts and sleeves
provided post cable laying shall be capable of restricting water ingress. The trench shall be used for oil
containment in case of any oil leakage form the transformer.
The finished floor level shall be kept at minimum 300mm above finished ground level. Generally, a
minimum 4m wide folding type double-leafed fixed-louvered door shall be considered. However, the
door size shall be governed by the transformer size.
The transformer room shall be adequately sized to accommodate a medium voltage load break switch
wherever required.
A switchgear room in general shall be designed to avoid parallel installation of switchgears. A
switchgear room shall be a permanent structure constructed in reinforced concrete and blockwork.
Its finished floor level shall be kept at minimum 300mm above finished ground level and its minimum
height shall be 4m. The switchgear support shall be strictly in compliance with manufacturer’s
recommended seismic requirement.
The room shall be air-conditioned and shall be provided with adequate lighting, both skylight and
lighting fixtures. Its main access door shall be 2.5m wide and 3m height. Depending on the length of
the switchgear room, escape doors shall also be provided fitted with panic bar latch sets.
A separate battery and battery charger room shall be provided to accommodate battery and battery
charger of medium voltage switchgear.
Accessibility of the building and / or equipment for maintenance by roads and walkways shall be
ensured by the Contractor. This should include accessibility for Fork Lifts, so that heavy equipment
and materials can be moved when required. The building should also have adequate height for
movement of mechanical devices so that materials can be handled easily. GRP grating will used as
floors where required. The building should have good functional HVAC system. HVAC system should
be designed considering ADWEA Standard Specification.
The floor should have adequate slope to eliminate any puddle and connect to a floor drainage system
which ultimately connects to a storm drain or sewer. Each floor drain shall be of heavy duty uPVC with
"S" or "P" trap complete with chrome plated heavy duty, 200 x 200mm, bronze strainer. The strainer
shall be screwed to the body of the drain. All floor drains shall have chrome plated removable covers
to their strainers or heavy duty aluminium cover.
The salt saturator, product tanks area, temporary reverse storage area as well as a salt storage shed
shall be designed as steel structures with portal frame at regular intervals with steel columns
supporting the electrical monorail. The salt storage area shall be enclosed if required by TRANSCO.
The duration of salt storage shall be project specific and shall be decided during design stage.
The location of the storage tank and its capacity will be as per Civil Defence guideline. It has to have
adequate ventilation. It should have a main pumps (electrically and diesel driven) and a jockey pump
to maintain pressure. Where turbine pumps are used, adequate size opening in the roof over the
pump shall be provided with removable GRP cover.
Accessibility of the building and / or equipment for maintenance by roads and walkways shall be
ensured by the Contractor. Overhead travelling crane shall be installed for equipment handling.
The administration building shall be of permanent nature constructed in reinforced concrete and block
work. The finished floor level shall be kept at minimum 200mm above finished ground level and its
minimum height shall be 3.0m.
Equipment foundations should be designed to spread the load of installed machinery on to the ground
so that excessive settlement or tilting of the foundation block relative to the floor or other fixed
installations will not occur; they should have sufficient rigidity to prevent fracture being under stresses
set up by heavy concentrated loads, or by unbalanced rotating or reciprocating machinery; They
should absorb or damp down vibrations in order to prevent damage or nuisance to adjacent
installations or structures.
The foundation to equipment weight ratio shall not be less than 3 to 1. The natural frequency of the
foundation and equipment shall not coincide with any resonant frequency (dynamic excitation
frequency of the equipment) and complying with the codes.
Pipe sleepers are another form of pipe support used for supporting pipe at ground level. These are
either cast on site or can be precast in high-strength steel reinforced concrete. The four main functions
of pipe sleepers are to anchor, guide, absorb shock and support specified loads from a wide variety of
pipeline sizes and weights.
The following loads from piping shall be included in the design of pipe support structures:
a. The thrust pressure based on the specified pipe test pressure acting on the pipe’s tee, bends,
blind flanges, etc. and transmitting the load to the structures.
b. Pipes larger than 300 mm diameter shall be considered as concentrated loads in their actual
locations under empty, normal operation and test conditions, whichever gives the most severe
effect.
c. Piping less than 300 mm diameter shall be considered as a distributed load in the range 0.75 to
1.25 KN/m² over the gross area of the supporting floor. The greatest value shall be assumed
where extensive piping is anticipated. In area of structures where there is no piping, no allowance
should be made.
d. The assumed loads given above are based on ANSI standard pipe and fitting. Where non-standard
pipe and fittings are to be installed, the loads shall be adjusted to suit.
e. Considerations shall be given to pipework where the configuration, operating loads and operating
temperatures may give rise to significant horizontal forces due to friction at supports.
f. The pipe supports for above ground piping system, shall be designed considering the load
outcomes from the pipe stress analysis.
Complete stress analysis for all the pipes below and / or above ground and within the pump hall shall
be performed by the Contractor using computer software.
All below ground cables entering any building / structure shall be provided with cable transit system
(mechanical seal) to prevent water ingress.
Adequate access shall be provided for valve operation. The valve chambers should have enough space
so that the valves can be operated easily. The chamber should have drainage sump and ventilation for
air circulation. The cover should be designed according to standard specification and there should be
clearly visible markings. Covers should be removable to allow maintenance. There should be entry
points for cables.
In case of constructing the valve chamber above the ground (i.e. in a bund), then the soil passive
resistance shall not be entrusted above the original ground level (i.e. to be considered as Zero); whilst
the passive earth pressure shall be considered below the original ground level.
External concrete protection shall be as per W-C-SS-005 Specification for Concrete Section 10.10.2
Protection.
Where:
H – Horizontal V – Vertical NA – Not Applicable
Ɵ – Bend angle in degree
Ɵr – Bend angle in Radian
Ɵt - total angles in degree
Ɵtr - total angles in Radian
Pi = 3.1416
A – Cross sectional area of the pipe (internal for flange joints and external for all other types)
A1 – The reducer bigger pipe cross sectional area
A2 – The reducer smallest pipe cross sectional area
The calculation of the required pipe restrained length shall be carried out in accordance with the pipe
Manufacture recommendations.
The Potable Water Supply is also to be used to supply break tanks and cisterns which serve sanitary
and hot water systems. The Potable Water Supply System also delivers water for service within
buildings.
Minimum storage size as per ADDC; Facilities supplied; Min pipe diameter –ADDC
Potable water system shall be designed in accordance with ADWEA standard specification w-c-ss-012.
• Minimum level in the vessel sufficient to avoid air entrainment into the pipeline
• Positive pressure (above atmospheric) for initial air charge / level in the vessels
The sizing of the surge vessels shall be based on the findings of the surge analysis study and minimize
air compressor and air release operations, in particular in case of restart after trip.
The surge analysis shall utilise an approved computer software package that allows for a detailed
modelling of air vessels dimensions and their control mode. The computer model and results shall be
provided to TRANSCO and shall include the air valves/vacuum breaking valves along the pipeline route.
The air valves / vacuum breaking valves are not allowed to open during the surge unless otherwise
agreed by TRANSCO/ENGINEER.
The Contractor shall provide full surge protection for the system in accordance with the
recommendations of the surge analysis.
The surge protection equipment shall be located as shown on the drawings unless alternative
locations are approved. These alternative locations shall be based on new surge study showing better
performance of surge protection system. It is not anticipated that the alternative locations will be
approved unless the alternative locations are shown to have substantial advantages in the surge
protection systems.
Surge Vessels shall be designed in accordance with ADWEA standard specification w-m-ss-006.
Foundations shall consist of an annular reinforced concrete ring beam and compacted structural fill
base within the concrete ring beam. The ring beam shall be a minimum of 300mm wide and 600mm
deep. The actual beam depth will depend on geotechnical investigations. The steel reinforcing shall
be designed for direct hoop tension resulting from lateral earth pressure in the inside of the ring beam.
The structural fill shall be compacted in accordance with ADWEA standard w-c-ss-004. The finished
surface shall slope at 1:120 downwards from the centre of the tank to the concrete ring beam.
Thickness of the structural fill shall depend on the geotechnical investigations. Structural fill shall have
no sharp angular particles which might damage the corrosion protection of the steel floor plates.
The work for NDRC shall include all services, equipment, materials, tools and labour for the complete
and proper installation, testing, restoration of underground utilities and environmental protection.
The work entails crossing underneath channels, waterways and roads in the Emirate of Abu Dhabi.
The crossings are of variable length and diameter, for the purpose to install potable water pipes,
sewage systems or conduits for electrical cables.
The Contractor shall note the accessibility of both entry and exit pit locations for each and every
crossing and shall further note the likeliness of utilizing marine transport systems for the island works
including but not limited to stringing/ testing/ coating of pipelines, drilling procedures etc. and all
possible requirements as deemed necessary by the Contractor.
The requirements in regard to pipelines welding, installations. Control of pipelines stress, bending,
hydrostatic testing. Flushing, disinfection and commissioning shall be as stated in other sections of the
Tender Documents.
Before starting with the works the Contractor shall provide a desk study / feasibility study. The study
shall list all the parameters used in the design. In case the NDRC shall be conducted for the purpose
installing potable water lines, the calculations have to show wall thickness calculations considering
maximum external and internal forces.
Contractor shall confirm that he is complying with the requirements of Abu Dhabi Municipality and
other concerned authorities if applicable.
NDRC systems shall be designed in accordance with ADWEA standard specification w-c-ss-016 as well
as the following standards:
Earth Retaining Structures can consist of cantilever retaining walls, gravity retaining wall systems and
reinforced earth systems. All Earth retaining Structures shall be designed to prevent failure by
sliding, overturning, settlement or slip circle. Design of retaining structures shall be in accordance
with ADWEA Standard Specification W–C–SS–003–Rev01.
Retaining wall shall be designed to take into consideration dead loads from the wall self-weight,
earth and backfill material; live loads from pipelines, traffic, building loads in accordance with ADIBC;
and other superimposed loads.
Backfill materials shall be in accordance with ADWEA Standard Specification W-C-SS-004 Section 8.2
and placing and compaction shall be in accordance with Sections 8.3 and 8.4. Backfilling immediately
adjacent the wall shall consist of free draining gravel with associated perforated drainage pipe and
geotextile, to prevent any build-up of hydrostatic pressure.
When steel sheet piles are required for shoring or any other purpose required by the Project the
Contractor shall submit detailed stability and adequacy design calculation for TRANSCO/ Engineer
approval.
• Micro piles (with less than 400mm diameter) may be accepted for special cases subject to
ADWEA/ Engineer approval and recommendation of geotechnical investigation.
• The length/depth of pile shall be such that it reaches approved soil firm stable stratum
(preferred N-Value not to be less than 50) and shall not followed by a weak soil.
The bearing capacity of the driven/bored cast-in-place piles shall be defined as follows:
• By using a minimum of two static formulae based on standard penetration test, static
cone penetration test, and soil tests.
• In addition to the static formula, dynamic formula shall be used for estimating the
bearing capacity of the driven cast-in-place piles.
• Preliminary Pile load tests shall be carried out to confirm the results of the static and dynamic
formulae as well as to define the expected settlement under the working load.
The Consultants / Contractor shall decide the Civil / Structural General requirements in line with
ADWEA Standard Specification Ref. W – C – SS – 003.
The Consultants / Contractor shall carry out the Architectural designs and works in line with ADWEA
Standard Specification Ref. W – C – SS – 008.
5.4.22 Earthworks
The pump station should be located to minimise earthworks volumes and excessive depths of fill. It
should also be located to be flood free. Finished ground surface levels should be such that surface
drainage is directed away from the pump station.
• Procurement and supply of material, delivery, transportation, handling and storing at site
• Excavation/backfilling
• All necessary safety measures including locating underground services and working adjacent
to them
All foundations shall be in reinforced concrete. Where the ground is excavated for any reason below
the underside of the proposed foundation the void shall be filled with concrete. Any over excavations
below the foundation blinding level shall be filled with structural backfilling. Any ground water
encountered during the excavation shall be dewatered using proper dewatering system approved by
TRASNCO, prior to any construction work. All such cost of dewatering shall be included in the tender
rates.
• Sewage Water drainage taking discharge from toilets, showers etc. to a septic tank system.
• Contaminated water System taking water from process areas including pump hall,
chlorination rooms, and battery rooms discharging water to a main sump. Disposal from the
site is as specified in the Environmental permitting/ studies.
Gradients shall generally not be steeper than 1 in 75 nor flatter than 1 in 250 generally and with a
permissible deviation not greater than 1/20 of the given gradient. All pipes & fittings to be used on
the project shall comply with the requirements of the latest relevant British/other standards approved
by TRANSCO/ENGINEER. The joint sealing rings shall conform to BS 2494. Products to be procured with
BSI certification. The dimension & pressure rating of the pipes shall be in accordance with ISO 161/1.
Inspection Manholes shall be constructed of reinforced concrete or of solid concrete blocks and shall
be carried out in accordance with the relevant codes and specifications.
Water drainage systems shall be designed in accordance with ADWEA standard specification w-c-ss-
011.
• Contaminated water from industrial source, transformer. Include oil separator, post oil
separation discharge into local SWD system or onsite lagoon.
• Chlorinated water. Include neutralization, post neutralization discharge into local SWD
system or onsite lagoon.
• Flow from surge vessels into local SWD system or onsite lagoon.
All external areas including the road inside the plot shall be lit by pole mounted street light luminaries.
Requirement of site monitoring using CCTV cameras should be evaluated and provided if necessary.
This is further discussed in Instrument and Control System. Fencing Design shall comply with ADWEA
Standard Specification w-c-ss-013.
• Alkali Resistant acrylic based anti- carbonation coating – 100 x 3 coats = 300 microns thick.
And internal coating for potable water pumping station shall be Solvent free 100% solid content
Polyamine based pure Epoxy 300 micron thick + primer system. Painting and Coating shall be in
accordance with ADWEA Standard Specifications w-c-ss-008, w-c-ss-014, and w-c-ss-015.
All structural steel shall be coated with fire resistant paint as per civil defence requirement.
2. Earthworks drawing;
4. Footing Plans
6. Pump Station, Electrical Building and Administration Building - general arrangement showing
plans at different levels, multiple sections encompassing all details and elevations;
Electrical and control building, chlorination building, fire water pump house, compressor
building/room, QRM building, substation / switchgear building, guard house, administration building,
shall be designed in accordance with typical drawings provided in the Appendix.
• Site Location. If the reservoir site is to be located in an existing built up area it could be
expected that land availability is limited and visual impact is important. Therefore the likely
• Life Cycle Cost. Foe the acceptable technical solutions a life cycle cost analysis should be
carried out and reservoir type selected based on lowest Net Present Value.
• ADWEA Standard Specifications for Concrete Works ‐ Specification for Civil/Structure General
Requirements for Water Works
• The latest edition of the BS, BS EN, ASTM, ACI, AASHTO, DIN and CIRIA
• Minimise shrinkage effect by pouring the sections of the work between construction joints in
a sequence such that there will be suitable time delays between adjacent pours.
• Curing methodology
• Single reinforced concrete structural elements are not permitted. Minimum wall thickness of
double reinforced structural elements to be 230mm wide
The size of coarse aggregates in pre-cast concrete shall not be bigger than 20mm. Casting of pre-cast
concrete is done in individual forms and curing can be done by steam curing or continuous water
curing. The curing duration for steam curing (at least 4 days) is less than continuous water curing (at
least 7 days) after which curing membrane is implemented or any other approved method. No
branding is allowed in the finished work of pre-cast concrete elements.
Time of lifting for pre-cast concrete units shall be determined by the supplier but it shall not be less
than 10 days.
For more details about pre-cast concrete; refer to section W-C-SS-005 “Specification for Concrete” of
ADWEA specifications.
The grade of concrete shall be based on strength requirements for structures/items. However, the
lowest grade of concrete used for structural purposes shall be C40 i.e. concrete having a 28 days cube
compressive strength of 40N/mm2.
The reservoirs shall be designed in accordance with BS 8007, BS 8110 and ADWEA's design guidelines
and standards of water supply systems, and to the approval of the ADWEA/ENGINEER.
Reservoirs shall generally be covered and divided into suitable compartments if required for cleaning
requirements. Compartments shall be made with a full height dividing wall. The dividing wall shall be
designed such that either compartment may remain full of water to under roof soffit whilst the other
compartment is empty.
The minimum free board (top water level) shall be 300 mm to roof soffit or increased to accommodate
structural members (beams).
Reinforcement shall be steel reinforcing bars of minimum yield stress = 460 N/mm2 and conforming
to BS 4449.
The cement to be used throughout the works shall be ASTM Type II cement obtained from
manufacturers approved in writing by the ADWEA/ENGINEER. The cement to be used throughout the
works shall be decided based on the soil investigation report, otherwise, ASTM Type II (MSRC) cement
to be used for substructure (structure in contact with soil), reservoirs or any water retaining structure;
while ASTM Type I (OPC) cement to be used for superstructure or above ground concrete works as
approved by ADWEA/ENGINEER. However, MSRC Cement shall be used for column necks and any
above ground concreting works done as continuity to below ground concrete. MSRC Cement can also
be used for superstructures for Particular rooms exposed to chemicals and /or contaminated drained
water subject to ADWEA/EMGINEER approval. Contractor shall take necessary measures to ensure
that Concrete with OPC cement is not used for any substructures concrete works, until instructed by
ADWEA/ ENGINEER. MSRC Cement shall comply with ASTM C150 Type II, with C3A content of
maximum 8%.
The Contractor shall be required to provide a construction methodology, from his specialised post
tensioned concrete designer, for the acceptance by ADWEA/ENGINEER.
For post tensioned option the floor and wall footing shall be designed and constructed as a continuous
unjointed post tensioned concrete slab thickened below the wall, below column supports, at scour
drop boxes and at pipe penetrations.
The floor shall be laid on two layers of 300 micron polyethylene building film to allow movement
during tensioning. The building film shall be laid on a bedding layer appropriate to the reservoir floor
and, if installed, appropriate to the under floor drainage system. This bedding layer shall also comply
with the post tensioning design subgrade friction requirements.
For reinforced concrete floor slab construction, the concrete should be constructed in square
segments with maximum segment dimension approximately 6 metres. All joints shall have water stop
cast in place or alternatively a hydrophilic water seal such as ‘hydrotite’.
The floor shall be finished by steel trowelling to a smooth surface. The concrete floor and wall footing
shall have 20 mm by 45o chamfer on all exposed, external corners.
Any temporary anchor bolts installed in the floor shall be chemical anchors using 316 stainless steel,
for example, for temporary props used during construction which shall be cut off when no longer
required and then heavily coated with epoxy.
The external surface of the wall footing shall be no more than 300 mm above the finished ground level
so that guardrailing is avoided.
The pre-stressing force shall be checked by reading the jacking pressures and the elongation of the
strands. All gauges shall be calibrated before dispatch to the site, and a chart drawn up plotting gauge
reading versus applied jacking force.
Jacks shall incorporate a provision for hydraulically or manually locking off the wedges to limit draw
in to 8 mm. If the draw in on anchoring is greater than 8 mm, then the strand shall be re-stressed.
2. More than 5% of theoretical extension shall be investigated and reported on by the specialist
designer and will be subject to Icon Water instruction to un-stress and re-stress and/or liable
to rejection.
Cable extensions shall be calculated and measured on the basis that an initial force sufficient to
remove all slack is applied before measurements are commenced.
All stressing tendon ducts shall be grouted after acceptance to do so by ADWEA/ENGINEER is issued.
Where the roof of the reservoir is of concrete slab construction then a bearing pad is also required
between the top of the wall and the roof slab. The bearing pad should be positively secured at the top
of the wall
The reservoir is to be supported by reinforced concrete ring beam around its circumference and
engineered pavement to a thickness determined from the geotechnical and geophysical
investigations. Roof shall be a conical steel structure supported on outside steel wall and roof beams/
trusses with interior columns.
The constructor shall be required to provide detailed design and construction methodology for
acceptance by ADWEA/ENGINEER.
Refer to Mechanical Works section of this guideline for further details of requirements for steel tank
construction.
The inlet pipe shall be designed for maximum inflow rate for the reservoir.
The inlet pipework in the reservoir shall nominally be DI in a post tensioned concrete reservoir and
steel in a welded steel reservoir with surface protection complying with ADWEA Standard
Specifications. An alternative material for both types of reservoir is 316 stainless steel without surface
protection.
The inlet standpipe shall terminate with a flanged connection at 0.7 m above the reservoir floor.
The inlet pipework shall not be used to vent the reservoir bypass pipework.
The reservoir outlet shall be located with its centreline within 2 metres of the reservoir wall and
separated by an arc of 180o from the inlet. The outlet shall be at a level of 150 mm above the reservoir
floor. The lip on the outlet shall be within 2 mm of level all round and shall be 1.6 times the nominal
outlet pipe diameter. The lip level shall be used as the zero point for water level monitoring. The outlet
shall be covered with mesh for personnel protection. Mesh shall be 100x100x3 bars and shall be 316
stainless steel in post tensioned concrete reservoirs and carbon steel with surface protection in steel
reservoirs.
The outlet pipework in the reservoir shall nominally be DI in a post tensioned concrete reservoir and
steel in a welded steel reservoir with surface protection complying with ADWEA Standard
Specifications.
A pressure reducing valve shall be provided to control the pressure in the outlet main to mimic the
reservoir. Where the TWL of the reservoir is below 675 m AHD, a pressure relief pipe is to be provided
via an open ended pipe, with no valves to be installed on the pressure relief pipe.
The reservoir overflow pipe shall not have any valves and shall discharge to the de-chlorination pit.
The overflow pipe shall have a flanged connection 300 mm above the reservoir floor.
The overflow pipework shall be DICL in a post tensioned concrete reservoir and steel in a welded steel
reservoir with surface protection complying with ADWEA Standard Specification.
5.5.5 Accessories
5.5.5.1 Access Manholes and Ladders
Access manholes, 1500 mm x 1500 mm clear opening shall be provided on the roof of the reservoirs
with modified glass reinforced plastic access ladders and safety cages provided at each opening.
External access shall be provided by galvanised mild steel ladders, 450 mm wide, butted against the
wall. Galvanised mild steel safety cages shall be provided for the ladders.
5.5.5.2 Ventilation
150mm diameter pipe with integral deodoriser and mosquito mesh provided for every 400m² of roof.
5.5.6 Earthworks
The following aspects shall be considered in earthworks:
• Procurement and supply of material, delivery, transportation, handling and storing at site
• Excavation/backfilling
• All necessary safety measures including locating underground services and working adjacent
to them
The stormwater drainage of the reservoir site shall be designed to discharge to the low side of the
site. Discharge shall be piped to where the natural slope changes from steep to gradual and from there
shall become surface flow following natural drainage lines.
Storm flow cut off drains shall be provided on the high side of the reservoir site to divert stormwater
runoff away from the base of the reservoir.
Site grading around the edge of the reservoir shall be designed to carry over land storm flow as well
as reservoir roof storm flow. This stormwater flow shall be directed to drainage pits and pipework.
Minimum size of stormwater pipework shall be 160 uPVC. Stormwater pits shall be provided at
changes of direction of pipework. Stormwater pits shall be cast in situ reinforced concrete and shall
be structurally designed and comply with the requirements of ADWEA Standard Specifications for
Concrete.
The reservoir area shall be lit by high mast mounted flood light of minimum 25m and the road inside
the plot shall be lit by pole mounted street light luminaries.
All surfaces to be protective coated using solvent-less high build epoxy shall be blast cleaned. All
surfaces to be protective coated shall be free from rust, mill scale, oil, grease, dust or other
contaminants and shall be thoroughly dry and clean. All irregularities on the surface, including weld
spatter, welding slag etc. shall be removed by grinding flush prior to blasting. Sharp edges shall be
rounded (radius not less than 10 mm) before blasting.
The coating for all internal surfaces shall be two (2) coats of a high build solvent-less epoxy, each coat
consisting of a minimum DFT (Dry Film Thickness) of 250 microns.
The coating for the reservoir external surfaces is to be a zinc epoxy to manufacturer's requirements
with a solvent borne acrylic as the topcoat also to manufacturer's requirements.
While preference is for the inorganic zinc finish, where site aesthetics are required, apply an additional
coating of solvent borne acrylic topcoat to manufactures requirements.
1. Site layout drawings of the whole site including security fence layout;
2. Drainage drawings;
Additional drawings other than those listed may also be specified to be provided as part of the design.
Hydro testing shall only be commenced after completion of the reservoir construction including the
top slab (if it is designed as monolithic with the walls) and before application of any internal or external
coating / water proofing and before commencement of backfilling.
After the construction of the reservoir, the Contractor shall remove all dirt and foreign materials from
inside the reservoir and shall clean down the walls, floor, columns and underside of the roof with
potable water. All debris and water used for cleaning shall be removed from site.
Concrete defects (if any), such as honey combing, cracks, pin holes, etc. shall be repaired as per
approved material and methodology. Internal & external cones of formwork tie rods shall be filled
with approved material. Elastic sealant shall be applied for the joints as per manufacturer instruction.
After completion of the surface preparation & cleaning the reservoir shall be inspected by the ADWEA
/ ENGINEER. Testing and disinfecting of the reservoir or tank shall not commence until written
approval is given by ADWEA /ENGINEER. The entire material to be used for repair works shall be
certified as Non‐Toxic
Initially, a 21 days stabilizing period shall be allowed, while absorption and autogenously healing take
place. After the stabilizing period the level of the water surface should be recorded at 24 hour intervals
for a test period of 7 days. After this 7 days test period if the total permissible drop in level, after
allowing for evaporation and rainfall, does not exceed 1/500th of the average water depth of the full
tank or 10mm whichever is lesser, the tank shall be deemed water tight.
Notwithstanding the satisfactory completion of the test, any evidence of seepage of the water to the
outside faces of the water- retaining wall should be assessed against the requirement of the
specification.
Should the structure not satisfy the 7 days test, then after the completion of the remedial work it
should be refilled and if necessary left for a further stabilizing period; a further test of 7 days duration
should then be undertaken in accordance with the above.
No backfilling around the walls of the reservoirs shall be commenced until the successful completion
of testing.
The Contractor shall provide a warranty for water tightness of reservoirs for 10 years.
Dead Loads shall be taken in accordance to the ADIBC and ASCE 7-05 “Minimum design loads for
buildings & other structures”.
In addition to the aforesaid codes, the following additional live loads shall be taken into account:
• The loads for platforms and chamber cover slabs shall be 5.0 KN/m², or a minimum single point
load of 7.50 KN whichever is more unfavourable for the structure.
Imposed loads shall be taken from the aforementioned Codes and as required by TRANSCO, whichever
contributes to the worst load case. The minimum design live loads on all floors will be based on the
static and dynamic loading from plant and equipment (Data provided by Vendor) plus the relative
imposed load taken from aforementioned codes”. In vicinity of heavy traffic, Surcharge Imposed Live
Load of 33.33 KN/m² (equivalent to SLW 60 single Wheel Load as per DIN 1072) shall be considered at
the side of chamber’s walls, retaining walls, etc.”
The basic wind speed shall be obtained/calculated as per the Code guides, provided that the
mean/and or the maximum wind speed on which the peak wind velocity pressure will be calculated
shall not be less than 160 km/hr. (45 m/sec).
SDPS WS (2008) “Special Design Provisions for Wind & Seismic Standard (ANSI/AF &
PA SDPS – 2008”.
The seismic zone for UAE shall be taken as per the guidelines of the subject Code and the Contractor
shall reconfirm with the concerned Municipality based on their latest circular in respect of the above.
The natural frequency of the foundation and equipment shall not coincide with any resonant
frequency (dynamic excitation frequency of the equipment) and complying with the codes.
The loads pertaining to the equipment to be considered are those given by the
MANUFACTURER/SUPPLIER, together with the conventional loads as listed in this Specification, (dead,
imposed, piping, seismic, wind, erection etc.) as found applicable.
The soil parameters shall be taken from the final geotechnical investigation report. The dynamic Soil
parameters shall be addressed in the detailed geotechnical investigation report by the Contractor
which are:
If the building or structure is founded on isolated footing or isolated pile caps with connecting tie
beams, machinery foundation and the associated pipe supports shall be independent of adjacent
foundations. Surrounding concrete slabs or paving shall be separated from machinery foundation by
a 20 mm joint formed with compressible material and sealed with an approved elastic sealant.
If the building or structure is founded on raft slab foundation or raft slab on piles, machinery
foundation and the associated pipe supports shall be monolithically cast with the said raft slab with
the necessary reinforced concrete plinth.
Reinforcement shall be used at all faces, if the foundation is over 1 m thick, shrinkage reinforcement
should be spaced approximately 600 mm, in three directions (cube reinforcing with minimum bar
diameter of 16 mm).
Buildings, Structures, Foundations and liquid retaining structures (including fireproofing) which are
subject to thermo-mechanical effects shall also be designed for the thermal loads and for any
temperature difference that may occur.
The loads of scaffolding, including the wind loads, due to erection and maintenance shall be taken into
account for the design of the structure.
The design of Gantry girders (Runaway beams) shall be in accordance with Abu Dhabi International
Building Code and the related ACI/AISC/ASCE/SDPS Codes.
Design of foundation shall be carried out by using the limit state design method at the ultimate limit
state for the applicable load combination.
The overall foundation stability, allowable bearing capacity, sliding, overturning, floatation, rotation,
etc.; shall be checked at serviceability limit state with factors of safety Specified in this Specification.
In the sliding check the friction resistance at foundation base shall be considered zero in case of
application of water proofing membrane above the blinding.
In all the cases the active soil pressure can be developed only within a wedge of soil between the wall
and failure plane passing through the lower end of the wall and at angle of (45˚ + ɸ/2) to the
horizontal. Whilst the passive soil pressure can be developed only within a wedge of soil between the
wall and failure plane passing through the lower end of the wall and at angle of (45˚ + ɸ/2) to the
vertical. Where ɸ is the soil angle of internal friction
The recommended allowable soil bearing capacity should be as specified in the Final Detailed
Geotechnical Survey Report approved by ADWEA/ Engineer.
While calculating the stresses on soil, the passive earth pressure shall not be considered fully
developed unless the structure tends to move. The actual passive earth pressure shall be considered
as the total acting forces minus the resistance base friction force. The Contractor can verify the said
actual developed soil passive forces using relevant geotechnical software programme.
The Factor of safety for the uplift resistance is 1.4. Care shall be taken to check the flotation based on
the high tied condition; where the ground water table is at its highest high level. Meteorological data
to be obtained by the Contractor from the concerned Authority prior to commencement of the design.
For all load cases, dead loads of backfill can be taken into account beneficial if it is ensured that the
structure will be backfilled prior to testing the piping. This is reliable for base friction and earth
pressure.
The Consultants / Contractor shall follow the Foundation Design in line with ADWEA Standard
Specification Ref. W – C – SS – 003 – Rev01.
5.7.10 Optimization
Optimization shall be an integral part of design and construction to deliver the best value solution.
Designers / Contractors shall focus on both technical and commercial aspects of the project.
Optioneering and innovation play an important role in optimisation. Whilst optioneering helps in
finding most feasible techno-economical solution, innovation helps in delivering robust and
sustainable solutions.
It encompasses the whole life cycle of a project, from design to completion and beyond. The process
is undertaken in collaboration with the project team, understanding and managing the balance
between cost, time and performance.
The main benefit of VM is that it gives each and every project a clear path to create value through the
understanding of client objectives as well as the needs and wants of the stakeholders. The route to
delivery is agreed and developed with the full project team, with the understanding that solutions to
achieve the objectives are reliable and cost-effective.
a) Design costs
6 Electrical Works
6.1 Introduction
These guidelines are issued for the use of Consultants and Contractors on design and construction
contracts for TRANSCO. They are to be read in conjunction with the latest versions of the following
documents:
• The Electricity Supply Regulations 2007 (Regulation & Supervision Bureau Water, Wastewater
and Electricity Sector Emirate of Abu Dhabi)
• The Electricity Wiring Regulations (3rd Edition) (Regulation & Supervision Bureau Water,
Wastewater and Electricity Sector Emirate of Abu Dhabi)
• ADWEA Standard Electrical Specifications for Water Works (W-E-SS-001 to W-E-SS-014)
• ADWEA/ADDC/ACDC Standard S-AAA-GEN-SFL General Requirements System Characteristics
• UAE Fire and Life Safety Code of Practice 2011 Edition (chapters 5 & 6)
6.1.3 Abbreviations
AFE Active Front End Drives
DB Distribution Board
DE Drive End
LV Low Voltage
MV Medium Voltage
Issues to be considered include are safe egress from switchboard rooms, outward opening doors from
switch-rooms, alternative emergency exit paths (when the fault level is greater than 15kA), exits, a
working access around switchboards and panels, e.g. a minimum of 600mm unimpeded space around
a switchboard when either doors are fully open or equipment is racked out. Safety from falling from
heights when accessing instruments. Consideration of access for replacement of panels, once finishing
joinery has been completed.
The power supply and distribution for the pump stations will be designed with dual feed configuration,
the scheme will provide high speed bus transfer systems and automatic transfer systems, dual
transformers , dual switchboards with bus couplers so that no single fault or loss of power in the
system will compromise the pumping capability of the pump station. Essential and critical LV services
will be backed up by UPS. The intention of this design is that the sub stations, transformers,
switchboards and motor control centres will distribute the critical loads equally on their buses.
In developing the Concept Design the Consultant shall co-ordinate with the relevant distribution
company, ADDC or AADC to confirm the expected load/maximum demand and to ensure the network
has sufficient capacity and to ensure that there is sufficient information to plan and build any required
expansion of the associated network.
The purpose of the preliminary design is to provide detailed enough information to go to tender to
obtain a competitive bid from Contractors who will carry out the detail design.
The Consultant shall carry out preliminary design studies to develop the concept report to confirm
Cables shall be sized taking into account thermal limits and maximum permissible volt drops.
Consideration must be made that under motor starting or locked rotor current conditions the voltage
drops at motor feeder busbars results in the contactor coil dropping out.
The current rating capacity of cables shall take into account de-rating factors that may result from
installation conditions.
Cables shall be sized to withstand short circuits for the protective relay operating time without
damage and for a minimum of one second.
Incomer cables to distribution boards (DBs) and other panels shall be sized the bus bar rating and not
the operating load and shall be at least 125% of the calculated maximum demand of the DB or panel.
Transformer primary and secondary cable current ratings shall be greater than transformer rated
currents.
Motor and feeder cables shall have a current rating greater than the rated full load current.
Distribution Board feeder cables shall have a rated current greater than the calculated maximum
demand of the switchgear plus a spare capacity of 25%.
Bus Ducts should be considered where capacity is greater than 1000A and where greater than 3 cores
per phase are required.
Motor starting studies shall be completed to determine the minimum acceptable voltage for large
motors.
All MV motors shall be VSD driven
Table 6-1 sets out the recommended operating voltages for motors, the final selection of the nominal
voltage needs to take in account the following items
• Motor costs
• VSD costs (including harmonics)
• Cabling Costs dependent on price of copper and Aluminium
• Heat output cost of cooling air conditioning
• Space considerations required switchgear, cable containment systems
• Capex and Opex needs to be considered, for the lifecycle costs the Consultant should consider
a 25 year period.
• Motors
• Drive system
• Motor Cables
• Harmonic mitigation
• Installation Cost
• Cooling system cost
Ambient Temperature 40 45 50 55 60
Temperature Derating Factor 1 .965 .93 .9 .865
Motors will not be installed at altitudes above 1000m therefore altitude de-rating factors are not
required.
The CT classification for motor protection should be as advised by the relay manufacturer, however
the default class is 5P10
Table 6-3 Motor Protection Requirements
6.5.3.4 LV motors
Motors over 15kW should have assisted starting either by soft starters or VSDs. DOL starting may be
considered if the motor starting study of the electrical determines that the network has sufficient
strength that any voltage dips at the main LV bus bars due to the starting currents is within the ADWEA
guidelines.
In the initial design phase the Electrical Consultant will co-ordinate with the hydraulic designer to
determine whether there is a requirement to vary the pump flow and hence the motor speed during
operation and in addition if there is a requirement for soft starting and soft stopping. This will
determine whether for hydraulic/mechanical reasons there are requirements for variable speed drives
or soft starters. Consideration should be taken not only of potential stress to the piping but also stress
to the pumps and motors. It may be that starting or stopping requirements (e.g. long times, variable
ramp up and ramp down characteristics) can only be achieved by a VSD
The distribution company requirement and the load study referred elsewhere in these guidelines will
determine if assisted starting is required for network stability.
If it is determined that there is a need to vary the pump flow a cost benefit analysis should be
undertaken to compare energy savings versus the Capex and Opex of VSDS including all harmonic
mitigation requirements and additional air conditioning requirements.
• Drive system
• Harmonic mitigation
• Installation Cost
• Cooling system cost
6.5.4.3 Cooling
Careful consideration should be given on method of cooling refer to Section 6.6.2.1.1.
Active harmonic filters are not a suitable solution for pumping station applications and are not
accepted by Transco.
Line chokes should still be considered with AFE drives, for pre filtering.
Sine filters are not a preferred solution for new installations as there are issues with voltage drops,
physical space required and maintenance requirements.
• Step 1
Determine the environment type and allowable EMC levels as per IEC? 61800-3:2004
• Step 2
Confirm the maximum permissible drive to motor cable length of all of the Transco pre-approved
VSD to determine location of drives, principle should be to minimise motor cable lengths and
screened multicore symmetrical cable should be mandatory.
• Step 3
Consider best routing of power and signal cables and required separation of the different type of
cables according to sensitivity to RFI & emission of RFI:
• Step 4
Plan the earthing topology and taking into account effect of high frequency currents that will
appear in the earthing network due to grounding requirements of the drives to reduce EMC.
• Step 5
Consider the output filters required, whether filters provided for motors will meet the
requirements for EMC mitigation
6.5.5 Transformers
6.5.5.1 General Design Requirements for Transformers
Refer to the standard specification for Transformers W-E-SS-003.
The transformers feeding duel fed (double ended) switchboards shall have sufficient capacity to supply
the entire board in the circumstance that one transformer is out of service and the bus-tie is closed.
The transformers, other than phase shifting transformers, are to be installed outdoors without shade.
Over current, earth fault and differential protection for transformers will be measured at the
switchboard and details are provided in Table 6-7 Recommended Protection Requirements at MV
Switchgear.
One of the most important considerations with paralleling transformers is the subsequent increase in
short circuit fault levels therefore the switchgear and bus bars must all be rated for the higher
potential fault levels.
The preferred values are: 100kVA, 125kVA, 160 kVA, 200 kVA, 250kVA, 315kVA, 400kVA, 500kVA, 500
kVA, 630 kVA, 800kVA, 1000 kVA and multiples of 10 of these values
6.5.5.5.2 Climate
The service condition for temperature of cooling air at the Transco sites will exceed the normal service
conditions as defined in IEC standard 60076-1 (clause 4.2). Table 6-6 shows as an example the
comparison between IEC normal service conditions of the air temperature and values at the Abu Dhabi
International airport. The Consultant needs to provide the transformer vendor with the values at the
proposed site which can be obtained from the National Centre of Meteorology and Seismology
(NCMS) web site http://www.ncms.ae/en/climate-reports-yearly.html?id=8801.
In addition the equipment must also comply with the stated ambient temperature of 55°C
Table 6-6 Air Temperatures Transformer Insulation
Air temperature IEC Normal Service Abu Dhabi International Airport Values
Conditions
Maximum Temperature 40°C 49°C
6.5.5.5.3 Cooling
The cooling medium shall be air and all transformers should be designed for normal operation to
operate as ONAN with the option to operate as ONAF under abnormal circumstances.
For transformers greater than 10MVA and where there are space constraints, ONAN/OFAF cooling can
be considered.
6.5.5.5.4 Insulation
The transformer insulation options are:
• Mineral Oil:
Mineral oil is the traditional insulating medium and have a good record for providing effective
insulation however regular maintenance should be done to ensure the longevity of the transformers.
Dry type transformers are often used for areas where there are number of people such as shopping
malls and airports as if there is a fire there is no oil to support combustion, other main applications is
where it is imperative to avoid oil spills. The disadvantages are that they need to be larger to achieve
the required insulation levels. The main application at the pump stations would be for the
transformers associated with the MV VSDs.
The default for transformers stepping down to the LV network (400/415V & 690 V), that the secondary
side is solidly earthed, however as described above it is necessary to confirm that this is appropriate,
particularly when the source short circuit power is high.
6.5.6 MV Switchgear
Refer to the standard specification for MV switchboards W-E-SS-001, the design should also include
the following criteria:
• Each Switchboard shall be designed with an electrical capacity to match its respective supply
transformer.
• Provision for a minimum of 1 additional tiers shall be provided at either end of the MV
switchgear (for new installations)
• All switchgear shall be indoor units, including switchgear for onsite MV sub stations.
• MV switchgear shall use SF6 contactors.
• Vacuum or SF6 circuit breakers may be used for motor VSD starting duties where the starting
frequency is low or the capacity is beyond the ratings for contactors.
• Each half of double sided switchboards shall be mirrored with respect to placement of
cubicles.
It should be noted that this is a guide and the final selection of the protection selection will depend
on the protection study and analysis of the behaviour of motors, transformers and drives during faults.
Modern protection relays have multiple functions available, therefore additional functions can be
added with no extra wiring or instrument transformers required.
The protection scheme should still aim to be the simplest that will provide the required protection of
the equipment.
Table 6-7 Recommended Protection Requirements at MV Switchgear
Over Voltage 59
Over Voltage 59
Differential Protection 87
Instrument transformers and relays would be part of the package supplied by the switchboard
manufacturer.
Where the switchgear is sized for future growth the CTs should be provided with Taps for the
appropriate ratios.
When the metering or protection equipment is at the board or when only short pilot wires are
required 5A secondary winding is recommended. However the burden of the secondary cable and
connections a can become significant with 5A secondary’s for longer runs and this will need to be
taken into account.
When estimating the burden on a CT the burden of each device needs to be added (since they are in
series connections) including the burden of the secondary cable and then rounded up to the next
standard value. If the total burden imposed on the CT secondary winding by the connected device(s)
and wiring connections exceed the rated burden of the CT the CT may partly or fully saturate and
therefore the secondary current will no longer be linear with the primary current over the operating
range.
Care should be taken to not over specify the CTS as not only can it make them unnecessarily large with
potential subsequent effects on the size of switchgear but also not necessarily the best design for their
purpose.
Class X CTs are special CTs used mainly in balanced protection systems (including restricted earth fault)
where the system is sensitively dependent on CT accuracy. Further to the general CT specifications,
the manufacturer needs to know:
6.5.6.3 Interlocks
In addition to the specification W-E-SS-001 requirements, the earthing switches shall be interlocked
with its associated MV switch so that closure of the earthing switch is only allowed when the MV is
not in the service position.
The MV switchboards are all double ended, under normal operation each of the incoming breakers
are closed and the bus coupler (sectionaliser) is open with each bus section supplied by its incomer.
In the event of either incomers losing power from either an unexpected outage or from a planned
shut-down of one supply the relevant incoming breaker should open and the sectionaliser close. The
HSBT system enables a fast transfer to take place in a controlled manner so as not to cause mechanical
damage to the motors or connected loads while ensuring the pump station maintains operation
continuity.
Transfers must be blocked on faults (that is if the incoming circuit breaker has tripped because of a
down-stream fault) otherwise the bus sectionaliser will close onto a fault and the whole system could
be lost. Co-ordination between the HSBT supplier and VSD will be required and transient analysis will
need to be carried out to ensure compatibility and optimisation of the transfer.
Retransfer to the original source should be carried out manually by the operators once they have
confirmed all status and protection indications.
The following modes should be available, the first mode described is a closed transition with the
remainder being open transition methods.
The microprocessor unit integrated with HSBT system shall control all different operation modes
based on the program logic, data analysis and operability. The HSBT can be programmed for various
control configurations and different scenarios. Some of the control modes covered by the HSBT
program logic shall be as following:
The transient torques are reduced due to the speed of the transfer. The high speed transfer is
particularly applicable for low inertia loads such as centrifugal pumps to prevent the sudden stopping
of the motor and pump which can cause large stresses on the motor shafts and windings and damage
the pipes from water hammer. The high speed transfer will be blocked if the phase angle between the
bus and the source are out of limits.
In addition a manual transfer can be carried out after a planned shutdown of the motors on one bus
section
The valve stations will have operating voltage of 400V; the switchboards associated with these should
have a generator connection box with terminals ready for generator cables. The change over at the
switchboard should be manual consisting of the main incoming circuit breaker paired with a generator
circuit breaker with mechanical interlock and centre off.
The generator connection box must have the same rating as the main switchboard bus rating. The
connections at the connection box should be sized to take the cable lugs of the mobile generators
6.5.7.2 UPS’s
Back up for critical pump station equipment is from UPS system. The design considerations are
described in the specification W-E-SS009.
• SCADA
• Flow meters
During a power outage, the pumps and VSDs will not be running, most VSDs are rated for 40°C
degrees.
The load list must include static requirements and starting currents of motors including actuated
valves and air conditioning motors.
The Consultant shall estimate the space requirements for the UPS so that the room can be sized
correctly.
6.5.8 LV Switchboards
The switchboards ratings shall be based on the values calculated from the electrical studies, rounded
up to the next standard value as outlined in IEC 60076-1.
In addition they shall have the minimum ratings as outlined in Table 6-10 below.
Table 6-10 LV Switchboard Requirements
6.6 Studies
This section provides guidelines on what would is expected for each of the studies described below
for both the preliminary design stage and for the detailed design stage, the Consultant shall prepare
the requirements for the studies to be undertaken by the Contractor amending as appropriate the
guidelines presented here for the detailed design stage .
Refer to the ADWEA/ADDC/AADC standard S-AAA-GEN-SFL for the system characteristics and fault
levels.
The outcome of the studies carried out at the detailed design phase shall be used as the basis for the
final design.
Outputs should provide in tabulated form for each cable, switchboard / Motor Control Centre (LV)
with detailed curves and circuit diagrams as generated by the modelling tool provided in the Appendix.
The electronic software copy of the study shall be provided to enable verification and the ability to
model the network in the future.
The reports shall include method of analysis, assumptions made and discussion on any issues with co-
ordination
The DC component of the asymmetrical short circuit shall have decayed sufficiently for arc
extinguishment by the time the circuit breaker contacts open
Provide maximum and minimum calculated fault levels at each switchboard and motor control centre
as indicated in the table below.
The Consultant shall determine that the selection and settings of all protection relays specified and
shown on the preliminary design SLDs are satisfactorily co-ordinated. Consideration of the upstream
protection provided by ADDC/AADC shall be included.
The Consultant shall provide a table for each of the relays to be installed showing set points.
Total Harmonic
Switchboard Busbar Total Harmonic Voltage
Current Distortion
Supply Voltage Distortion (%)
at full load (%)
400V , 690V 5
3.3kV, 6.6 kV 3
>11kV 3 3
For HV earthing systems, safe step and touch potentials shall be determined using IEEE80/ESAA EG1.
Duration of earth faults used in calculations shall be based on the time for the back-up protection to
clear the fault.
The earthing system shall be designed to achieve maximum earth path resistance as follows:
The Consultant will take data provided by the project geologist on the type of soil and using tables
from IEC 62305 estimate the soil resistivity which will be used with the preliminary short circuit study
results to produce an earthing single line schematic to complement the power single line. This will
include sizing of earth bars within the switch room, sizing of earth cables.
The Consultant shall also provide a preliminary LV earthing layout of the site which will include the
location of earth electrodes, location of exothermic welded earth connections to the structural
foundations, earth inspection pits. The Consultant shall consult with the structural engineers on any
limitations or requirements with using the foundations for the earthing. The substation earthing
design will be carried out in the detailed design phase.
• Buried Earthing Conductor design including mesh, buried conductors, electrodes any earthing
compound
• Transient voltage design
• Bonding of adjacent structures
• Earthing Impedance (if required to limit earth fault current) of transformer star point
Where there is a 33kV or 22kV substation, the Contractor shall use an earthing computer modelling
software such as CDEGs to carry out a full earthing analysis to produce sub-station design earthing
design to IEC 50522:2010. This will include calculations of the step and touch voltages, earth potential
rise and fall. The CDEGs software using the improved earth impedances it produces will confirm the
earth fault currents as calculated in the short circuit studies.
The Consultant doing the detailed earthing design of the substation should have a proven track record
of substation earthing design and if necessary a sub Consultant should be engaged.
The power earth and lightning earths to be separated but under lightning strike conditions to ensure
potential equalisations surge diverter (e.g. Metal Oxide Varistor MOV) is installed between the main
earth bar and the lightning earth)
An estimate can be made from NASA worldwide lightning maps using data from their optical transient
detector satellite system. (http://geology.com/articles/lightning-map.shtml). This indicates that for
Abu Dhabi Emirate the GFD is less than 0.4 flashes/ square km annually, and for the Northern Emirates
from the mountains to the gulf of Oman the GFD can be as high as 5 Flashes per square kilometre.
Follow the procedure as outlined in IEC 62305-2 determine what lightning protection level (LPL) and
therefore the lightning protection systems (LPS) required including surge protection for the major
areas of the pumping station. This shall include
• Surge vessels
• Electrical Sub stations
• Pump station as a whole
• Any ancillary buildings
• Any internal Lightning protection systems required.
The Consultant shall prepare for the preliminary design report a recommendation for level of lightning
protection system. This shall include a table as illustrated below presenting the tolerable level of risk
is required for each area for:
Surge vessels
Pump station
as a whole
Control room
The report shall include any recommendations of what lightning protection will be required.
This report should include an Engineer’s estimate of what the mitigation costs are.
In assessing the level of protection, where the specifications call for a level of protection such as surge
protection and or equi-potential bonding then this must be taken in account for assessing the risk at
the preliminary design phase.
The design shall follow the Wiring Regulations and IEC 62305 guidelines, if there is any discrepancy
the more stringent requirements will be met.
A report shall be produced which provides the following information for each cable.
i Volt drop No No
l Protective device details for each cable including Yes Final settings after
manufacturer, type, and model and trip unit commissioning
including all adjustable settings.
Provide co-ordination curves between the protections devices, priority should be given to ensure
devices that feed multiple branches have the greatest discrimination.
The Consultant shall provide an initial estimate of the heat loads of the following major equipment so
that the air-conditioning and ventilation requirements can be estimated:
• VSDs
• UPS’s
• Battery Banks
• Switchboards
• Electric Motors
The electrical designer needs to co-ordinate with the mechanical engineer to investigate the following
options:
It is essential that planning for cooling of the VSDs is carried out in the preliminary design stages of
the project as dependent on the solution proposed there needs to be sufficient space in the building
fabric therefore co-ordination will be required with the architect.
The heat loads generated in each of the rooms and the required operating temperature and
ventilation requirements need to be calculated according to the equipment selected so that the air
conditioning detailed design can be carried out by the mechanical works.
All luminaires for both interior and exterior areas including roadway and area light shall be LED type.
Exterior lights shall have zero upward light component unless required for decorative requirements:
The Consultant shall carry out a preliminary emergency lighting layout design based on the fire report
including location of exit signs. The emergency lighting shall meet the UAE Fire and Life Safety Code
of Practice
The voltages at lighting fixtures shall be within ±5% of the rated voltage for the lamp, ballast or driver.
Modelling of large equipment such as pumps, motors, transformers, switchboards and tanks is
required. It is acceptable to model irregular shaped items such as pumps and motors as rectangular
blocks.
For the purpose of this calculation points closer than 200mm (0.2m) to vertical surfaces such as walls
and objects may be ignored.
• Luminaire label (As shown on the calculation and lighting layout drawings
• Description including Manufacturer and Model Number
• Lumens per luminaire
• Light Loss factor
• Quantity of each type of luminaires
The calculation results are required for both normal and emergency lighting requirements and shall
be presented for each area. They may be presented either by Isolux contours or by calculation points,
The Luminaires shown in the calculations shall include the luminaire label and Mounting Height.
Emergency lighting in rooms with essential lighting will be on the essential circuits so that the
emergency lights will only go one once there is no power to the essential lighting.
The table below provides suggested minimum requirements. (SSO = switched socket outlet
Table 6-15 Socket Outlet Requirements
• Indicative small power layout for critical areas such as control rooms, switch rooms, lunch
rooms
• update the socket outlet schedule
• Provide a list of Distribution boards required
• Layout drawing of the pump station showing locations of Distribution boards
• Scope of works for tender documentation.
• Particular specification if required
The Contractor will design the small power circuits including cable sizing, containment, distribution
boards will provide a DB schedule. Refer to Section 6.6.1.6 for requirements.
7 Mechanical Works
This section covers typical mechanical equipment that is part of the pumping station design.
ISO 2531 -Ductile Iron Pipes, Fittings, Accessories and their Joints for
Water Applications
ASHRAE Standard 62-2010 -“Ventilation for the Acceptable Indoor Air Quality”
There are many sources of energy losses when fluid is flowing through the pump. They can be roughly
divided in two categories: Mechanical losses and hydraulic losses.
2. Mixing losses.
3. Recirculation loses.
4. Incidence losses.
6. Leakage losses.
Some of those losses increase as flow increases and some decrease. Some are linear and some are
nonlinear. When adding losses for the full range of flows that pump can achieve, there exists a flow at
which sum of all those loses is minimal and pump curve is closest to the ideal Euler curve. That point
is called the best efficiency point (BEP)
Pumping costs will be lowest if pump operates at the BEP but also, the life span of the pump will be
the longest.
Pumps shall be selected so it operates at BEP if possible. Because of the potentially infinite number of
flow head conditions sometimes (or most of the time) it is not possible to select pump that will operate
exactly at BEP so pump shall than be selected so it operates as close as possible to BEP.
The Table below gives guidance on how much pump operating point shall be allowed to differ from
BEP.
The above figures are for guidance only and manufacturer shall be consulted for each specific pump
selection.
Particular care shall be taken when pumps are operated in parallel arrangement. If they are selected
to operate at BEP when pumping in parallel, when only one pump is operated it will then pump more
flow than when two or more pumps are operated in parallel. This is due to lower friction losses.
So in other words if pump was operated at BEP when pumping in parallel, its operating point will move
to the right of the BEP. Care shall be taken that this increase of flow is within recommended range of
flows for that particular pump.
If pumps are operated via variable frequency drive (VFD) and there is a large static head in the system,
when slowing down the pump its operating point will move to the left of the BEP. Again, care shall be
taken that this decrease of flow is within the recommended range of flows for the particular pump.
If the pump is going to mostly operate at part load condition where its speed is reduced by a VFD then
it shall be selected so its operating point at full load conditions is on the right of the BEP. When slowing
down the pump its operating point will move to the left to the zone of higher efficiency.
So called, “pump control valves” shall not be specified. In the past when soft starters and VFDs did not
exist it was common practice to start pumps against closed isolation valve or pump control valve and
then slowly open the valve to avoid cavitation and vibration of the pumps at start-up.
With the currently available technology there is no longer any need for such start-up philosophy.
7.2.4 NPSH.
Cavitation is the phenomena that can occur at pump suction if total suction head available at the
particular flow is less than required suction head at the same flow.
If absolute pressure at pump suction is lower than vapour pressure of water, water will evaporate and
steam bubbles will form.
When those bubbles implode, localised zones of very high pressures will occur. This can cause pitting
damage to pump impeller. Cavitation damage always occurs on the low pressure side of the impeller.
Vapour pressure head of water for various temperatures is given in Table 7.2 below
Table 7.2 – Vapour Pressure Head of Water
Calculated NPSHa shall be higher than NPSHr by at least 1.5 m for all possible flow conditions.
1. Unlike end suction pumps, they do not have axial loads on the pump shaft. This is due to
cancelation of axial forces because of double suction design.
2. Pump impeller and shaft are easily accessible for maintenance as top casing of the pump
can easily be removed without disturbing suction and discharge pipework.
3. They have lower NPSHr requirements because each impeller eye only handles half of the
flow.
4. Because axial thrust forces on the pump shaft are balanced and cancel each other they
have higher efficiencies than similar end suction pumps. Higher efficiency translates to a
lower operating costs.
5. Relatively higher allowable nozzle loads due to the rigidity of the lower part of the housing
Double suction pumps are more sensitive to piping arrangement around them. Refer to section on
pump suction design for more information.
Where this is not possible of feasible other means of prevention such as constant flow bypass etc.
shall be provided.
Where necessary, a provision for pipe filling shall be provided. Typically a nozzle with flange
connection and isolation valve. This point shall be at lowest point of the pipework to allow air inside
the pipework to be pushed upwards towards the air valve locations
Velocity in the pump suction pipes shall be kept between 0.8 - 1.0 m/s
Velocity at suction pipe inlet shall be kept below 1.5 m/s and it shall be through a bellmouth
arrangement in order to reduce inlet headloss.
Double suction, split casing pumps are particularly sensitive to suction piping arrangement.
Suction pipe material from the supply tanks shall be either DI or Steel, internally and externally coated
as described in Section 7.3.2 Use of these lining materials will ensure that strainers are not required.
Elbows and bends in vertical plane are acceptable but shall be avoided as much as practically possible.
Butterfly valves shall be installed so that valve disc is in the horizontal plane when fully open. This is
to avoid unequal flows reaching pump impellers due to flow disturbance from valve disc.
Since suction piping is almost always bigger diameter than pump nozzle, an eccentric reducer (Flat
portion of the reducer on top) shall be installed upstream of the pump inlet. This is to avoid air
entrapment at the reducer.
Required Submergence of the inlet pipe must be calculated to make sure that there will be no air
entrainment. Following formulas from the IAHR Hydraulic Structures Design Manual 1, 1987 can be
used:
𝑆𝑆
= 1.0 + 𝐹𝐹𝐷𝐷
𝐷𝐷
𝑉𝑉
𝐹𝐹𝐷𝐷 =
�𝑔𝑔𝑔𝑔
Where:
Pipe location Pipe material Pipe internal coating Pipe external coating
Pipework inside Carbon Steel. API 5L Fusion Bonded Epoxy Fusion Bonded Epoxy (FBE)
pumping station. Grades B, X42, X52 (FBE) 300 micron dry 300 micron dry thickness
Installed on pipe thickness
supports above
ground. Coating must be
approved for potable
water use.
Yard pipework buried Carbon Steel. API 5L Fusion Bonded Epoxy For steel pipes:
underground. Grades B, X42, X52 (FBE) 300 micron dry In accordance with DIN
thickness 30670. Three layer of fusion
Or bonded Epoxy, copolymer
adhesive and polyethylene.
Ductile iron pipes to Coating must be
EN 545 approved for potable For Ductile iron pipes:
water use. Layer of metallic Zinc of 20
microns thickness and
bitumen based coating of
thickness not less than 100
microns
Ductile Iron Pipes can be of the following pressure class.
The final selection of pipe material is to be determined based on a Technical and Economical
Assessment to compare the above materials. The assessment will be based on the whole Life Cycle
Costs (WLCC) taking into consideration, but not limited, to the following:
• The difference in failure rate (based on historical performance) for each material;
Wenner or Schlumberger method are acceptable procedures for soil resistivity testing.
Where soil resistivity is low, typically less than 10 Ωm, a cathodic protection system might be required
(for Carbon Steel).
This has to be evaluated on case by case basis via risk analysis and if risk analysis shows that risk is
unacceptably high a sacrificial anode or impressed current type of cathodic protection shall be
provided.
Sacrificial anodes shall be sized for the design life of the pipeline.
Where soil resistivity is higher than 20 Ωm polyethylene sleeving shall be used on DICL
Where soil resistivity is less than 20 Ωm factory applied tape shall be used on DICL.
Low velocities on the other hand mean that pipes are unnecessarily big which results in high capital
costs of pipelines.
Recommended range of velocities is between 0.8 and 1.5 m/s. Absolute maximum velocity shall not
be more that 2 m/s.
When selecting check valve type, consideration shall be given to check valve dynamic closing
characteristics and consequence of check valve slam on surge.
Ideally, valves shall be selected based on their surge response following surge analysis.
Recommendations of the surge report shall include appropriate check valve type (instead of selecting
the check valve first and then trying to mitigate surge effects caused by that particular valve).
Reverse velocity characteristic of the selected check valves shall be readily available to allow for
modelling of the valve dynamic characteristics in surge software.
They shall also be provided along the rising main to allow for isolation of parts of the rising main in
case maintenance is required and sections of the rising main need to be drained.
Gate valves shall be provided for pipe diameters of DN300 and less and Butterfly valves for larger sizes.
However, air valves have moving parts and during transient conditions they can cause secondary surge
effects (air valve slam) and localised damage to pipeline coatings or pipelines themselves. Therefore
they need to be modelled to make sure that their response during surge events will not cause damage
to pipelines.
An isolation valve shall be provided downstream of the air valve to allow for valve maintenance and
replacement.
On larger diameter pipes it might be necessary to install twin air valves if single valve does not have
enough capacity.
Another issue that needs to be considered is that most air valves require between 3-5 m of head in
order to close drip tight. They shall not be used where there is not enough head to keep them closed
at all times. Manual air purge valves must be specified instead.
Preferred type of air valve is double acting, kinetic, multistage, non-slam type air valve. Single acting
valves can be used where there is a need to expel air only and where there is no danger of vacuum
forming during the emptying of the pipeline.
Non slam valve refers to valve property to slowly close during operation. Depending on valve
construction this can be achieved in different ways.
One way to do this for example is to change the size of orifice when air velocity increases (two stage
valves) above certain set point. Smaller orifice will present more resistance to air flow so it will slow
down valve closure.
Number and size of air valves shall be designed based on AWWA M51 standard.
Flow meter material shall be selected such that it is appropriate for the fluid being pumped.
Stainless steel is not appropriate material for flow meters installed in chlorination piping.
Magnetic flow meters have negligible headloss due to their full bore design. However, in some cases
to increase accuracy of measurement, velocity through the meter needs to be increased. This is
achieved by installing a flow meter of smaller diameter than the pipeline.
Magnetic flow meters shall never be installed with supports under the body. This will damage the
meter. Instead, the support shall be on adjoining pipes or via bracket mounted on flow meter flanges.
Magnetic flow meters are not suitable for measuring flow of non-conductive fluids such as reverse
osmosis (RO) permeate or air.
The Crane hook must be able to reach above each piece of equipment to provide straight lift.
Generally, any piece of equipment heavier than 25 kg shall be lifted by crane.
The Crane must have sufficient capacity to lift heaviest piece of equipment inside the pumping station
with appropriate safety factor applied.
The Crane hoist must be powered where capacity of the crane is more than 250 kg
Crane height shall be such that every piece of equipment can be lifted above obstacles to a flat bad
truck.
Crane shall be controlled by a pendant push button device. There must be an emergency stop button
on the pendant.
Access ladders must be provided for crane access for maintenance purposes. Two sets of ladders on
both ends of crane path are required.
7.4.3.2 Monorails.
Monorails shall be provided where load needs to be moved in one direction only, and where traveling
crane installation is either impossible or impractical, or if traveling crane is unable to reach above the
equipment in question.
Storage tanks are used to store water. They provide backup in case of disruption of supply and they
serve to attenuate fluctuations in demand.
Tanks are filled at times of low demand and emptied in times of high demand
Several type of tanks can be used for water storage as described below
They shall be designed as per the API 650 standard that govern plate thickness and other structural
components of the tank.
Inlet and outlet of the tank shall be opposite to each other. This is to ensure elimination of dead spots
of water in the tank.
Tanks shall be provided with air vents. Size of air vents shall be calculated for a maximum water inflow
and outflow.
1. Inlet connection.
2. Outlet connection.
3. Washout connection.
4. Overflow connection.
5. Transfer connection (to allow transfer of water from tank to tank in case of maintenance)
6. Inspection manholes.
7. Air vents.
System shall be designed to protect submerged parts of the tank and tank bottom plate.
Non submerged parts of the tank rely on coating for corrosion protection.
They are typically much smaller than steel welded tanks and are typically used for storage of water for
fire protection.
They can be used for storage of potable water where demands are not high and can be served by a
tanks of smaller capacity.
Care shall be taken to specify non-toxic material for gasket if tank is to be used for storage of potable
water.
1. Inlet connection.
2. Outlet connection.
3. Drain connection.
4. Overflow connection.
5. Manhole opening.
6. Air vents.
7. Instrument nozzles.
For smaller tanks it is good practice to provide two or more compartments so that tank can still be
maintained while in use. If tanks is divided in two or more compartments a balancing line shall be
designed so that contents can be transferred between compartments.
Although chemical processes that occur during electro-chlorination are rather complex they can be
described by the following simplified chemical reaction:
They are safer than gas chlorination systems but there are still significant risks involved with electro-
chlorination systems and careful operation and maintenance are of vital importance for safety.
4. Electrolyser.
9. Control system.
7.6.4 Electrolyser
Electrolyser cells are typically made of clear acrylic and they contain the anode. Brine solution is fed
via pump and electrical current is passed through the anode. This is where sodium hypochlorite is
formed and H 2 gas is released.
It is very important that electrolyser cells have proper ventilation to prevent build-up of H 2 .
Overheating of the anode is another issue that needs to be monitored and prevented.
A Common operational issue is scaling and subsequent failure of the sensors. Regular maintenance is
a must for electro-chlorination systems.
During operation anode will inevitably scale and an automatic detection system for scaling must be
implemented. Typically this is done by monitoring the current through anode. When anode scales,
more current is required to produce same concentration of sodium hypochlorite.
Hydrogen dilution system typically consists of blowers that blow outdoor air through the tank.
Capacity of the fans must be calculated to provide enough dilution capacity.
Capacity of the dosing pumps can be adjusted by varying stroke length, effective stroke length or
stroking speed.
Particular care shall be taken when designing suction piping of dosing pumps.
Piping shall be kept as short as possible and as straight as possible. If long suction piping cannot be
avoided a break tank might be required. This is to avoid issues with insufficient NPSHa.
Piping shall be sized to handle instantaneous peak flow which is 3 times higher than pump rated
capacity. This is due to metering pump pulsation flow characteristics.
Calibration pot shall be installed at pump suction to allow for pump calibration.
Pulsation damper shall be installed as close to the pump discharge as possible. If two or more pumps
are connected to a common header each separate pump shall have its own pulsation damper.
Tank shall be designed as per the ASME Code for boilers and pressure vessels section VIII.
Bladder tank shall be specified with a nylon reinforced bladder and grate at the bladder connection to
prevent bladder being sucked in into pipeline.
Provision for draining the surge vessel shall be designed. In case of large vessels consideration shall be
given to where the content of the vessel is to be drained.
As per the UK code of practice for Food Grade Compressed Air that is in direct contact with food
product, compressors used for compressed air surge tank shall produce air to at least ISO 8573.1: 2010
class 1.2.1. In case of surge vessels for potable water storage air class 1.4.1 is acceptable.
This level of filtration for particulate and oil (both aerosol and vapour) contaminants requires use of
coalesce and activated carbon filters.
Contrary to popular belief, even oil-free compressors will require oil filters in order to remove any oil
contaminants from ambient air.
Compressor shall be sized to fill the tank from empty to design pressure in no more than 4 hours.
𝑉𝑉 ∗ 𝑃𝑃
𝑉𝑉̇ =
𝑃𝑃𝑃𝑃 ∗ 𝑡𝑡
Where:
A pressure relief valve must be installed to protect surge tank from overpressure.
When selecting valve calculations as per the ASME Boiler and Pressure Code Section VIII, Pressure
Vessels, must be done to determine orifice size.
Calculations must account for compressibility of air. Calculations must account for back pressure if the
valve is not vented directly to atmosphere.
Calculations preformed with manufacturer software are acceptable as long as software complies with
ASME Boiler code.
Refer to Section 3.1.4 – Surge Design parameters. Air valves shall normally be designed for Case 1
(perfect condition) and the design is to be verified for Case 2 conditions (survival of the system).
1. Two loop system using chilled water in primary loop and recirculation pump in secondary loop.
Two loops connected via heat exchanger.
2. Single loop system using water from the suction header and recirculating it through the motor
using recirculation pump back to the suction header.
3. Two loop system using water from the suction header and recirculation pump and secondary
loop with recirculating pump pumping water through the motor. Two loops connected via
heat exchanger.
Which type of liquid cooling is to be used will depend on particular circumstances for each pumping
station. Preferred system is system No. 3 because of the lowest risk of contamination.
Heat exchanger frame must be oversized to allow for addition of at least 10% of additional plates.
A basket strainer shall be installed upstream of the heat exchanger to protect it from any debris.
Isolation valves must be provided to allow for dismantling of the heat exchanger without the need to
disconnect pipework.
Heat exchangers should be in duty/standby configuration to allow for servicing without the need to
shut down whole pumping station.
Isolation valve arrangement shall be such that swapping of duty and standby heat exchangers can be
achieved without shutting down the plant.
Drain connection shall be provided to allow for drainage of the standby heat exchanger to prevent
stagnant water.
Since this type of the system is closed loop there will be no static head so pump has to be sized only
to overcome friction loses in the pipework and headloss through various pieces of equipment such as
heat exchangers, strainers, etc.
Centrifugal end suction type pump (close or long coupled) is preferred type of pump for this
application.
Anti-flooding system consists of submersible pumps in duty standby configuration, all the necessary
pipe fittings and instrumentation for automatic operation of the pumps.
Two sump pumps in duty/standby configuration shall be installed to pump out any water that collects
inside the sump.
Pumps shall be submersible type with guide rail and pedestal mount. They shall be specified with
cooling jackets if they are to be operated without full submergence.
For small pumps of less than 25 kg in weight a manual davit shall be provided.
Following types for firefighting equipment shall be installed inside the pumping station as per the
NFPA and civil defence standards
4. Fire hydrants.
As per the NFPA 10 no part of the building shall be more than 30m away from a fire extinguisher. In
high Risk areas this is 15m.
Fire extinguishers shall be wall mounted when installed indoors or in appropriate cabinet where
exposed to elements.
Fire hose reels should normally be installed alongside escape routes. They should be installed in such
a way that whole building is covered by a 30m long hose and 6m water jet.
Fire hose reels shall be installed inside the wall mounted cabinet
CO 2 systems shall not be used for fire protection. Inert gas systems are preferred due to lower risk to
personnel.
Inert gas systems such as FM-200 supress fire by interfering catalytically, whereas CO2 system
supresses fire by reducing concentration of oxygen. Therefore CO2 systems are a greater risk to
people.
Inert gas systems such as FM-200 are preferred way of providing fire protection for electrical and
control rooms where possibility of water damage makes sprinkler and other conventional systems not
acceptable. Also FM-200 requires less space for cylinder storage than CO2.
Panel mounted FM-200 systems are preferred way of fire protection inside the electrical rooms.
They should be located not less than 12m from the structures they are supposed to protect and should
not be spaced more than 75 m apart as per the NFPA 24.
Electrical rooms shall not be protected by an automatic sprinkler system but rather with clear agent
system.
Such systems are not meant to protect transformer itself. Once a transformer catches fire it is lost,
therefore the most common system for transformer fire protection is a deluge system.
Deluge systems have another advantage of cooling and wetting adjacent surfaces making them more
difficult to catch fire.
The problem with deluge systems is that they require a lot of water (10 l/min /m2 as per the NFPA
guidance) since transformers contain oil, in case of fire water will be contaminated and it must not be
dumped into sewage of storm water system.
Oil will also float on top of water and it will take time to extinguish burning oil under the transformer.
Foam on the other hand has the advantage that it sticks to the surface and provides coverage so
burning oil fires are extinguished faster and less water is used.
Therefore the preferred system for transformer protection is deluge with foam.
When designing a deluge system, due consideration shall be given to the fact that water that is
discharged during fire event has to be drained away unless transformer is located in a bund of
sufficient capacity to hold the water. Water cannot just simply be drained to the nearest storm water
outlet because it might contain oil.
It is therefore required to have oil interceptor of sufficient capacity between the transformer
enclosure and discharge point.
A Holding tank of sufficient capacity is also acceptable. After the fire event holding tank can be
emptied and contaminated water properly discharged.
Electrical rooms shall be of sufficient size to keep reasonable number of air changes from air-
conditioning. Generally, no more than 20 ACH shall be allowed. If number of air changes is very high
than the space will be draughty and it will be difficult to deliver air inside the room due to a large
number of diffusers or grilles that would be required.
Battery rooms need to be air conditioned as well, because life of batteries is greatly reduced if they
are not kept at optimal temperature which is between 22-24 °C for most types of batteries.
Plumbing, foul drainage and site storm water drainage shall be incorporated in design. Refer Civil
Design section of this Guideline.
This data shall not be confused with the requirement that outdoor air-conditioning (AC) equipment
must be rated for operation at 52 °C.
Occupied spaces shall be supplied with fresh air as per the ASHRAE standard 62 1.
Since air humidity is typically not controlled, it will vary throughout the year and during part load
conditions. Consideration shall be given to the design of the fresh air system to limit humidity rise to
no more than 60% RH during part load conditions.
Ventilation system shall be designed either to achieve a prescribed rate of air changes per hour or to
keep the temperature rise inside the space to no more than 3 °C higher than the ambient temperature,
whichever results in a higher ventilation rate.
When calculating temperature rise, solar load must be taken into account as well as equipment load.
If not available, equipment thermal load can be calculated based on electrical load and equipment
efficiency. If efficiencies are not known at the time of design they can be estimated. Typical values for
common equipment are given in table below:
Table 7.7 – Typical Equipment Efficiencies.
Required minimum ventilation rates for various spaces are given in a table below:
Table 7.8 –Minimum Ventilation Rates.
Typical examples are VFD rooms or MCC rooms served by one or more AC units, At least one of the
units shall be standby.
1
ASHRAE Standard 62 – 2010 “ Ventilation for the acceptable indoor air quality”
In case of fans additional equipment such as differential pressure transmitter is required to indicate
when fan is not running.
Software shall be able to calculate cooling load on hourly basis for each hour in one year.
Calculations shall be done in SI units.
7.11.5 Equipment.
7.11.5.1 Fans.
Fan type shall be selected based on application and required airflow and external static pressure.
If fans are to be installed inside the spaces where there is a risk of explosion they must be specified as
explosion proof.
Forward curved centrifugal fans shall not be used, only backward curved. This is due to overloading
nature of the power curve of the forward curved fan.
Care shall be taken when connecting two or more fans to the same discharge plenum. If fans are not
selected properly such configuration can cause so called “Hunting” where fans rapidly change state
between two or more operating points on the fan curve. This creates noise and can lead to increased
wear of the fan motors and damage to fan bearings.
7.11.5.2 Ducting.
Ducting shall be designed as per the ASHRAE Handbook 2013 Fundamentals chapter 21 “Duct Design”
Friction loss in ducting shall be calculated using Darcy-Weisbach equation with friction factor
calculated using Colebrook-White equation.
When selecting initial velocity in the ducting for equal friction method, consideration shall be given to
noise criteria in the space served by that particular ducting system.
Acoustic calculations shall be performed to make sure that noise levels inside the spaces comply with
regulations and requirements from the specification.
If rectangular ducts are used, calculations shall be based on circular equivalent as calculated by the
following formula
2
ASHRAE 2013 Handbook Fundamentals
3
CIBSE Guide A Environmental design
Dynamic losses due to duct fittings shall be calculated using local loss coefficient from reliable source
such as ASHRAE duct fitting database or similar.
Duct design shall comply with local fire codes and fire and smoke dampers shall be included where
required.
If required by the local fire code smoke detectors must be installed inside the return air ducting.
Ducts carrying fresh air that pass through the air-conditioned spaces must also be insulated to prevent
condensation.
Ventilation air ducts (supply or exhaust) passing through non air-conditioned spaces do not need to
be insulated.
Where installed outside and externally insulated, ducts shall be cladded. Purpose of cladding is to
protect insulation from elements.
Free area velocity through weather louvers shall not be more than 3 m/s to avoid excessive noise
Face velocity through Sand trap louvers shall not be more than 1 m/s to avoid noise and to maximise
sand capture ratio.
In case of large air flow this will result in large area of the sand trap louvers so coordination between
structural and architectural design is a must.
Grilles shall be specified with opposed blade dampers to allow for airflow balancing.
7.11.5.5 Filters.
Filters shall be designed based on application.
Table below gives guidance on type and grade of filters required for typical applications
Table 7.9 – Filter Design per Application.
Split DX AC units are units where evaporator unit must be installed inside the air-conditioned space.
Split DX AC units shall not be used for air-conditioning of the electrical rooms due to possibility of
leakage of the evaporator units.
Location of the units shall be determined on a case by case basis but generally they should be out of
sight if possible. Pump station roof is typically a good place for AC unit’s location.
Chilled water systems shall be designed as per “ASHRAE handbook HVAC systems and Equipment,
chapter 13, Hydronic heating and cooling”
Type of the chilled water system shall be either constant flow or constant primary-variable secondary
flow.
Variable primary flow chilled water system shall not be used due to its complexity
Chillers shall be designed in N+1 configuration if they are used for cooling mission-critical spaces.
Attention shall be taken to ensure that chilled water circuit has enough water content. If the water
content in the chilled water loop is not sufficient than chiller will achieve design temperature quickly
and compressor will switch off. When water temperature rises again compressor might not be able to
start immediately because of the inbuilt protection that stops compressors from starting too often.
𝑃𝑃 1
𝑄𝑄 = 35.83
∆𝑇𝑇 𝑁𝑁
Where:
If the water content is not sufficient then a buffer vessel of suitable capacity shall be used.
1. They are centralised so one condensing unit can serve multitude of evaporator units.
When designing VRF systems care shall be taken to follow manufacturer’s recommendations about:
Since all evaporator units are connected to one condensing unit, in case of failure of the condensing
unit cooling will be lost so for evaporator units to be redundant, they have to be connected to two
different circuits.
Air intake shall be positioned at least 3m above ground level to avoid dust ingress.
Air intakes shall be positioned at least 6 m away from any source of contaminated air such as generator
exhaust or similar.
Casing shall be of sufficient diameter to allow for insertion of production equipment (Pumps). There
shall be sufficient gap between casing and the motor or pump casing to allow for water flow.
7.12.2 Screen.
Purpose of the screen is to prevent large debris entering the well.
It is typical achieved by cutting slots in the well casing. Size of the slots shall be sufficient allow for
water flow but small enough to prevent debris entering the well.
Where there is a need to prevent ingress of sand inside the well a geotextile sheet shall be used to
wrap around the screen.
Both types, radial and mixed flow, are acceptable. Mixed flow design is typically used when more flow
is required and radial type where there is a high head.
Since ground water in Abu Dhabi can have high content of chloride, corrosion protection of the pump
will generally be required.
There shall be sufficient clearance between pump and the casing of the well. In wells where well
screen is below the motor water has to pass between pump motor and the well casing , in wells where
well screen is above the motor water has to pass between pump body and the wall casing. In any case
if the clearance is not sufficient water passing will create high headloss. This can result in under-
performance of the pump.
Submersible motors must be cooled at a flow rate of not less than 0.15 m/s (that is flow rate past the
motor) or motor life will be shortened. If flow rate of 0.15 m/s cannot be achieved then a cooling
sleeve must be specified.
When selecting valves, cavitation calculations shall be performed for a full range of possible flow, to
confirm that valve will not cavitate.
1. Headloss through nozzle control valve is lower than through other type of valves
2. Main valve seal is located in hydraulically uncritical pressure zone which results in less damage
and longer seal life.
3. They have superior cavitation characteristics compared to other type of valves. This is due to
concentration of flow towards the middle of the pipe so any steam bubbles that form when
imploding will be concentrated towards the middle of the pipe, far from the pipe wall where
they can’t cause any damage.
4. Large number of different valve trims are available to suit almost any flow condition.
5. Stroking range is much wider than for other types of valves so their controllability is superior
for the wider range of opening positions.
Potential for cavitation in globe control valves is much higher than for Nozzle valves so calculations
have to be performed to make sure that valve will not cavitate for the full range of possible flows.
Preferred type of the pressure reducing valve is pilot operated automatic valve.
Pressure reducing valve must be able to close drip tight when downstream pressure exceeds the set
value.
When selecting pressure reducing valve, cavitation calculations must be performed to make sure that
valve will not cavitate under all flow conditions. Various nonstandard trims are typically available to
improve cavitation performance of a typical pressure reducing valve
Pressure sustaining valve must be able to close drip tight when upstream pressure drops below the
set value.
When selecting pressure sustaining valve, cavitation calculations must be performed to make sure
that valve will not cavitate under all flow conditions. Various nonstandard trims are typically available
to improve cavitation performance of the valve.
Pressure relief valve will open when pressure upstream of the valve is higher than the set pressure.
Pressure relief will be achieved by water discharge through the valve.
This type of valves can discharge large amounts of water when fully open so consideration shall be
given to where that water will drain.
Diesel fuel systems shall be designed as per the NFPA 30, Flammable Liquid Code.
Purpose of the day tank is to avoid having large quantities of flammable diesel fuel stored inside the
building.
Capacity of the bulk tank shall be enough to enable the generator to run for 7 days at full capacity.
Capacity of the day tank shall be sufficient to enable the generator to run at full load for 8 hours.
2. Breather/vent pipe.
5. Drain valve.
8. Contents gauge.
Emergency dump valve shall open in case of fire and contents of the tank shall be damped to a storage
sump outside the building
The Day tank shall be located inside a bund. Bund capacity shall be at least 1.5 times volume of the
largest day tank inside the bund.
The Bund shall have sump to enable pumping of diesel fuel with portable pump in case of fuel spillage.
1. Inspection manhole
2. Breather/vent pipes
5. Valved drain
6. Isolating valves
Care shall be taken when selecting location for the diesel tank. It shall comply with requirements of
NFPA 30.
NFPA 30 specifies minimum distances between tank and site boundary or nearby buildings. Distance
depends on tank capacity so it is important to plan location of the tank early in the project.
Diesel pumps shall be positive displacement pumps such as rotary lobe type.
Diesel fuel pumps shall be installed inside the bund. On the suction side of the pumps a duplex, manual
changeover, basket strainer shall be installed.
Pumps shall be located outside of the building and shaded from the sun.
8 I&C Works
8.1 Introduction
8.1.1 Objective
These guidelines are issued for the use of Consultants and Contractors on design and construction
contracts for TRANSCO.
The Design Guidelines describe the design requirement for the instrumentation and controls for the
projects. They are to be read in conjunction with the latest versions of the following documents:
• ADWEA Standard Instrumentation and Control Specifications for Water Works (W-I-SS-001 to
W-I-SS-009)
• As built drawings for P&IDs, control system architecture, etc. (existing systems)
Term Definition
A/M Auto-Manual
H/O/A Hand-Off-Auto
L/O/R Local-Off-Remote
O/A/C Open-Auto-Close
O/S/C Open-Stop-Close
PID Proportional-Integral-Derivative
S/S Start-Stop
8.1.4 Environment
The following minimum climate conditions apply unless advised otherwise by TRANSCO
• Visit the existing facility, or similar facility, and familiarize themselves with the existing
interfaces, PCS equipment including tagging, software, control strategies, and network
architecture to be matched and/or upgraded.
• Review all engineering reports and drawings for the ICA system related to the project.
• Equipment and Instrumentation List - Design equipment and instrumentation to permit full
monitoring and control capability under manual and/or automatic control.
• Servers/PLCs/Network - Review and document all existing hardware affected by the project,
and determine system capacity. Discuss capability for expansion and identify all additional
hardware required for modifications so as to fully integrate the new or expanded works into
the existing system. Identify all obsolete hardware that must be replaced as part of the
upgrading of the existing or expansion of the process control system.
• Control Wiring and Structured Cabling – Review and document all existing control wiring and
network cabling, and identify all additional cabling that will be required so as to fully integrate
the new or expanded works into the existing system.
• Alarm Notification and Security – Review the existing alarm notification and security system
of the facility, and document the proposed modifications and additions to provide the
required services for notification of the critical PCS alarms of the project.
• Process Narrative – Provide a Process Narrative or update existing for each process, clearly
describing how it is to be operated in all modes of process control. Process narratives to
provide a clear understanding of the relationships between the equipment and the process
variables to be monitored/controlled.
• Process Flow Diagrams – Provide a Process Flow Diagram (PFD) or update existing to clearly
illustrate the relationships between the various affected processes and associated
instrumentation.
• Design Alternatives – The Consultant should include a section detailing any alternative
designs that they feel might offer benefits to the Client in terms of cost or functionality.
• Cost Estimate – Include a cost estimate to construct the project according to the guidelines.
• Operation Control Philosophy (OCP) - The Consultant shall update the plant control
philosophy for all new processes. The new control philosophy shall describe the plant and
instrumentation, list all modes of operation, steps for each sequence and define the
interaction of control blocks for each continuous control algorithm. All events and alarm
conditions shall be listed, with details of the trigger, deadbands, timers, alarm priority,
triggered action and reset conditions (including how any manual reset will be carried out).
Interlocks, inhibits and emergency shutdown systems shall be detailed. Systems for protection
of people and the environment shall be subject to a SIL assessment and production of a Safety
Requirements Specification (SRS), in line with IEC 61508 and IEC 61511.
• Tele Information Plan List – The Consultant shall provide a list of data to be provided to local
pumping station SCADA and via telemetry to the Master SCADA (WCC Water SCADA System)
at the LDC.
• Equipment Power Requirements – The Consultant shall provide drawings and specifications
for any power supply upgrades or additions required as a result of new or modified
equipment.
• Cost Estimate – Provide an updated cost estimate.
Note-
1- The final instrument tag list shall be prepared by the EPC Contractor and will be submitted for
review and approval.
2- All the auxiliary systems such as fire alarm, HVAC, fans/blowers, anti-flooding, breakers
open/close status, etc. shall be interfaced with station control system.
Following the final design report (FDR) approval, the Consultant shall submit the Tender documents
for review and approval.
• The system installation approach will be geared toward location of electronic components
within secured facilities to the greatest extent possible. Where electronic components must
be installed outdoors, enclosures will be secured.
• Use of air conditioning units in remote panels will be avoided, if possible: panels components
will be designed for extreme conditions and outdoor panels will be designed to reflect /
radiate heat away from the panel.
• The selected control system equipment will be required to have regional repair, and
configuration support and readily available spare parts.
• Centralized control at the facility will be provided, thereby concentrating key components
within secure areas.
o Use of redundant online power supplies for panels, communication hubs and key
network components.
PLC and remote I/O cabinets will be strategically located in the pump station area. The main process
equipment packages will each be supplied with a main PLC processor, along with either remote I/O
cabinets or additional PLC cabinets which will accommodate all I/O points for that package. Additional
PLC processor with remote I/O cabinets may be provided to handle all other I/O for the facility area
outside of the package systems. Each PLC and remote I/O cabinet will be supplied from an
uninterruptible power supply (UPS).
The fiber optic cables will connect the remote I/O cabinets, remote reservoirs/tanks and tap off
control valves to the central computer system, tying in to an Ethernet switch in the building control
room. The Ethernet switch will provide connection capability for additional PLCs, workstations and
other control interfaces that are anticipated in future phases of the expansion of the project.
Workstations at the control room of the plant will serve as the operation staff's primary “window”
into the process, and will be configured to display all process information. The workstations will enable
the plant staff to monitor, interrogate, manipulate, and document plant processes. HMI terminals at
the PLC cabinets will serve as the secondary “window” into the process for the operations staff, but
are intended primarily for use by the equipment package vendors during testing and startup. The
touch screen HMI terminals will allow the plant staff to locally monitor the individual package
equipment processes for the facility systems. One large screen monitor shall be provided in control
room.
I/O depicted on the P&ID drawings for each process area will be displayed on the human machine
interface (HMI) control screens and all analogue data (as well as alarms and status points) will be
historically collected, recorded and trended. Generated control screens will be consistent in
presentation, quality, colour usage, symbol usage, and navigation options will be developed through
meetings with TRANSCO.
Control panels supplied with vendor-supplied package type equipment, such as sump pumps and
chemical feed pumps, will locally control the equipment in an automatic mode with monitoring
performed through the plant wide SCADA control system.
Local control will typically be performed via control panels and pushbutton control stations. Lock-out,
emergency stop pushbuttons will be provided at each piece of equipment. Where system control
panels or area control panels are required, local monitoring and control of equipment will be provided
via a graphical Human-Machine Interface (HMI) or Graphical User Interface (GUI) panel. These touch
screen panels may be used to display complex local controls at the field panel. The HMI or GUI will
communicate with the local PLC and will be configured to display specific data for the process area
and will allow control of the local equipment. Local manual control will be through the use of
hardwired selector switches and pushbuttons at the equipment.
Field sensors, process control equipment, and final control elements will be directly hard wired to RIO
rack module and PLCs. Control logic will reside in the PLCs. PLC and remote I/O cabinets will be
strategically located throughout the plant. Considerations in selecting locations will be the process
area, reducing conduit and wiring lengths, non-hazardous locations, and non-corrosive locations.
For the typical pump station overall control architecture refer to the Appendices.
Emergency Stops and Emergency Shut Down systems shall only use hardwired circuits acting directly
on the power to the final element, wherever possible. Where necessary, variable speed drive "safe
stop" functions may be considered. For complex shutdown systems (anything more than emergency
stop pushbuttons acting directly on a motor starter), a SIL assessment shall be carried out to determine
the required Safety Integrity Level.
• "Smart" instruments will be utilized where cost effective, with hardwired instruments in all
other cases.
• Analyzers will be reagent less type and equipped with smart sensors.
• Ultrasonic type, or radar type or hydrostatic type level measurement could be used depending
on the process requirement and Client's approval
• Magnetic flow meters will be the preferred flow measurement instrument in primary process.
24VDC or loop-power will be the preferred scheme with quick-connections for signal (and
power where applicable).
The PLC units’ hardware and software employed at all SCADA workstations and operator interfaces
shall comply with the client’s preferred list.
Communications to valve actuators, instruments, and variable frequency drive (VFD) units will be by
network communications when cost effective. For other interfaces and instruments, hard wiring or
owner preferred equipment will be utilized. The inter-building/site communication medium will be
fiber optic cable with redundant pairs. All controllers and control panels will be furnished with
monitored, redundant power supplies and all area equipment groupings will be supported by smart
Uninterruptable Power Supply (UPS) units (with relay-card interface), monitored by the control system
via hardwire connection.
Depending upon the final configuration of a process area, an area flood monitoring switch will be
provided to detect accumulation of water resulting from a high level in a sump or flooded floor. Level
switch digital signals will be taken back to the process area PLC. Hardwired level signals also shall be
used for critical interlocking and inhibits, especially for those inhibits required to prevent equipment
damage if operated in manual mode.
Note: The Contractor shall pay special attention during installation of flow sensor on water pipes. The
minimum straight distance upstream and downstream of Insertion flow sensor shall be according to
manufacturer recommendation.
Settlement metering system- The settlement metering equipment shall be installed inside a chamber
at interface points with ADDC or other customers. To interface with Transco's communication
network, one data logger/RTU and appropriate modem shall be utilized in the local control cabinet
(data logger cabinet). The telecommunication to nearest sub-station (outstation) shall be through
either digital radio or GSM, which shall be decided by Distribution Company (Licensed Operator
Company)
The settlement flow meters shall be in compliance with the latest MDEC requirement.
PUMP SUCTION
Pressure gauge Bourdon Gauge Pump suction 1
Pressure switch Refer to Clause 6.2 in ON-OFF Pump suction 1
WI-SS-001
PUMP DISCHARGE
Pressure gauge Bourdon Gauge Pump discharge 1
before NRV
Flow switch Refer to Clause 5.2 in ON-OFF Pump discharge 1
WI-SS-001
Pressure transmitter Diaphragm. Refer to Analogue 4-20mA Pump discharge 1
Clause 6.3 in WI-SS- before NRV
001
PUMP SET
Vibration sensor Vibration element Interface device Pump set- drive 1
end (DE) bearing
Vibration sensor Vibration element Interface device Pump set- non 1
drive end (NDE)
bearing
Temperature RTD Interface device Pump set- drive 1
measurement end (DE) bearing
Temperature RTD Interface device Pump set- non 1
measurement drive end (NDE)
bearing
Temperature RTD Interface device Pump set- Casing 1
measurement
MOTOR SET
Vibration sensor Vibration element Interface device Motor set- drive 1
end (DE) bearing
Vibration sensor Vibration element Interface device Motor set- non 1
drive end (NDE)
bearing
Temperature RTD Interface device Motor set- drive 1
measurement end (DE) bearing
Temperature RTD Interface device Motor set- non 1
measurement drive end (NDE)
bearing
Bearing oil level Motor set- If
indicator applicable
Heat exchanger Refer to Clause 5.6 in Motor set- If
temperature WE-SS-004 applicable
Temperature RTD Interface device Motor winding 1 for
measurement winding temperature each
RESERVOIR/ TANKS
Level Measurements Ultrasonic or Analogue 4-20mA Reservoir, Tank, 1
Chemical Tanks
Radar or Analogue 4-20mA Chemical Tanks,
Pressurized Tanks
• All the above field instruments except the water quality analyzer and flowmeter transmitter
are loop powered from the RTU.
• The analyzer and the flowmeter transmitter are fed from a UPS supply.
• The water quality analyzer and flow transmitter shall be installed inside the RTU shelter
satisfying the shelter equipment layout drawing.
• The field instruments are connected to a PLC-based RTU (Remote Terminal Unit), programmed
in an IEC 61131 compliant language to achieve the required function of process monitoring
and control/override and protection loops for the Control valve of the interface points as per
TRANSCO requirement as stated in Operation and Control philosophy. The RTU is fed from the
UPS. This control system RTU shall be integrated to the upstream pump station and also to
LDC
• Telecom cabinet and SDH network interface shall be installed in the RTU shelter for
telecommunication of the signal to the other interface point RTUs/Pump station and LDC.
The control system design will achieve a full, high level of redundancy. The failure of any one
component will not stop the process operation. The failure will be reported in the HMI/SCADA.
All the control components shall be replaceable and hot reconfigurable, without interrupting the
power.
The I/O modules shall be either located in process area or in electrical rooms. No I/O card will be
connected directly to the controller. As far as possible, equipment connected to each I/O module shall
be grouped in such a way that failure of one unit will not affect the whole plant operation.
All the controllers and servers will be redundant. The RIO will not be redundant. Only the power supply
and communication coupler (converter) will be redundant for the RIO.
All automation equipment (controllers, I/O, server, PC, switches, etc.) shall be fitted with a redundant
power supply.
The PLCs will match with the Client’s current PLC manufacturer/model preferred list.
As a minimum, the PLCs/RTUs will have the following communication protocol options, however the
Consultant shall coordinate with client prior to final design stage:
• Modbus RS-485
• Profibus DP and PA
• DNP3 Level 3
• IEC 60870-5-101/104
8.7.5 Servers
These shall be specified and configured as defined in ADWEA specification W-I-SS-002, in particular
sections 6.1, 12.2.D and 12.2.I. Intel Xeon servers shall be installed, in a redundant architecture.
Depending on the type, size and complexity of the control system the number and functions of servers
will vary. Typical servers used in pump station facility shall be as following:
• Data servers are designed for recording data (HMI, events, alarms, trends, etc.). Each operator
workstation will be connected to data server to read / write the common parameters / values.
Equipment shall be installed in server panel(s) (bays) 19” in the server room.
• Historian servers are designed for recording data for longer time of operation (HMI, events,
alarms, trends, etc.) from Data server. Each operator workstation will be able to read data
stored in Historian server. A backup disk will be used to store at minimum 10 years of data
and shall be installed in communication racks / server racks (bays) 19”. Equipment shall be
installed in server panel(s) (bays) 19” in the server room
Reporting server shall be provided for creating and recording reports.
• Data warehouse servers. The only allowable connection to the corporate network is at the
LDC, via a demilitarized zone with dual firewalls. However, where a project requires a
connection to the business network, a synchronized copy of the historian shall be provided on
a server in a de-militarized zone (DMZ). See section 8.9.1. All external processes and
workstations using SCADA data shall access the historical data stored in the DMZ, with any
direct access to the servers in the SCADA network zone blocked.
• Operator Settings: Operator set or entered values will be constants that are adjustable or set
from operator displays. Examples of operator set or entered values are controller set points,
batch set points, etc. Specific values that are required to be operator set will be noted in the
process control strategy descriptions.
• Tunable Values: Tunable values will be constants that are adjustable at engineer level displays
without requiring any software reconfiguration. These values will not generally be adjustable
from operator level displays.
• All analogue and discrete inputs to the PLC will be displayed. Both RUNNING and OFF input
states will be displayed.
• All analogue inputs will have instrument failure alarms when the input is below 0 percent or
above 100 percent for a tunable time initially set at 10 seconds.
• All discrete FAIL inputs will be alarmed.
• When alarms are specified in the control strategy descriptions, alarms will be initiated from
the applicable inputs. If discrete inputs are not available, the specified alarms will be initiated
from the applicable analogue input.
• All discrete outputs will generally be maintained outputs. For START/STOP PLC functions, the
PLC will issue a maintained START command until a RUNNING state is no longer detected or
when a STOP command is issued. When a momentary command is required, the PLC will issue
the command for two (2) seconds, and then remove the signal.
• For equipment that is controllable from the PLC, a control mode status signal will be sent to
the PLC to indicate when the PLC is allowed to control the equipment. The PLC will monitor
the control mode status (LOCAL/ REMOTE) and attempt to control only equipment that is in
the REMOTE mode.
• For equipment that the PLC is allowed to control, the PLC will provide a FAIL alarm if the
equipment fails to comply with a PLC command signal (START, STOP, OPEN, CLOSE) that has
been present for more than a tunable time period. In this event, the command will be
removed subsequent to the expiration of the tunable time period.
• All PID control functions (Proportional, Proportional + Integral, and Proportional + Integral
+Derivative) will be provided with standard analogue controller functions and operator
interfaces including the following:
AUTO/MANUAL mode selection: In AUTO, the output of the controller will be based
on the PID control calculation. In MANUAL, the output of the controller will be
operator adjustable. Transfer between operational modes will be bumpless.
When equipment is tagged “OUT OF SERVICE” by the operator, all associated equipment will have
their alarms inhibited until the tagged equipment is re-tagged IN SERVICE.
SCADA software shall be modular. To ensure that the polling and display of data is effectively
predictable, deterministic, and regular, the software modules shall be assigned such that the load is
balanced between several processors.
SCADA software shall operate on Microsoft Windows and a commonly available virtual operating
system (OS). A virtual OS shall be used where possible, to enable dynamic allocation load balancing,
automatic failover to hot standby processes and hot removal and swapping of hardware. Linux may
be used for associated database servers, with appropriate measures for redundancy and protection
of the data.
Direct communication with the Controllers shall be managed by a specific interface communication
unit on dedicated data servers. The exchange mode should be conceived in order to insure high safety
level (no loss of data).
Backgrounds and static graphics shall be grey or muted colour, selected to suit TRANSCO standard
configurations. Dynamic objects and colours shall be selected so that the operator’s attention is drawn
only to those items requiring action, without distraction from animation or saturated colours on other
items.
The alarms shall be assigned proposed priority levels to suit their criticality. The prioritized alarms list
shall then be issued for approval. During commissioning, an audit of “bad actors” shall be carried out
and the alarm grouping and prioritization shall be adjusted to remove these spurious alarm incidents.
• Values of each analogue signal (all measurements), sampling periods to be adjustable for each
or on event (status modification, threshold reached, etc.)
• All events (alarm, operator actions, derivative…etc.)
• Second
• Minute
• 15 minutes
• Hour
• Shift
• Day
• Week
• Month
• Year
The system will include sampling and storage of system variables, analogue variables, status of
discrete data, operator actions and alarm and event messages. States and values of all process data
shall be stored in internal files and refreshed permanently.
The system data historian shall be used for recording control system data on a historical basis and also
for retrieving such data for display, trend graphs or generation of custom reports.
The Consultant shall study the leak detection methods suitable for the application and propose the
most reliable, efficient and cost effective method. As a general, there will be a combination of
hardware devices and software packages driving the LDS operation. The special software package will
be installed in the dedicated station server to monitor continuously the running pipeline system under
steady state flow conditions, by using a mass balance calculation. The intention is to propose a system
to detect the leaks in minimum time with high accuracy. The following methods shall be used
independently from each other for detection and location of leak, however the Consultant shall
propose the other methods as alternative for review and approval:
Leak detection
Pressure monitoring under normal pipeline operation and during stand still.
Leak location
The LDS functionality shall be processed and implemented in the station control system logic
(PLC/SCADA) and/or in the station servers. The pressure, negative pressure wave and level monitoring
are tasks of the station control system. The compensated mass balance, Pressure gradient and leak
location are tasks of the station servers in control centre.
The measured process values such as pressure, level, etc. in remote areas shall be provided and
processed at relevant control stations and transmitted to control centre.
Note- The accuracy, efficiency and cost effectiveness of LDS for each project shall be studied by
Consultant on case by case basis. The approval and adoption of the LDS shall be at the discretion of
Transco.
The project system integrator shall also be responsible for modifications to the configuration of
servers, firewalls and switches to route the new data to the SCADA application server.
Where networks are loaded over 20% or SCADA polling times are compromised, additional
communication paths or capacity shall be provided. Any devices causing bottlenecks shall be
supplemented or replaced, as part of the project.
For typical water DMP scope of work refer to Dwg. N14054/TYP/E-405 in the appendix.
The project specific requirements, including the communication method between settlement RTU and
sub-station outstation, shall be resolved and finalized by Distribution Company (Licensed Operator
Company)
The FOC network between the sub-stations and LDC facility shall be within the scope of work of
Transco
Telecom requirement shall follow the specified ADWEA/TRANSCO specifications listed below:
• S-TR-COM-OPT-SDH (Rev.0-2016)
• S-TR-COM-PCM (Rev.0-2016)
• S-CAB-INST-CONT-FOC-(Rev.0-2016)
• S-TR-CAB-ACC-FOC (Rev.0-2016)
• S-TR-CAB-FOC (Rev.0-2016)
• S-TR-CAB-GEN (Rev 0 -2016)
• S-TR-CAB-MAR-FOC (Rev.0-2016)
• S-TR-CAB-MAR-INST-FOC-PROT-TEL (Rev.0-2016)
• S-TR-CAB-INST-CONT-FOC-GEN (Rev.0-2009)
• S-TR-CIVIL-CAB (Rev.0-2013)
It should be noted that wireless communications are prohibited at certain, sensitive locations such as
palaces and government buildings.
TRANSCO owns and operates SDH fibre optic network, using a combination of 16, 32 and 144 core,
single mode fibre optic cables (FOC) along pipelines and power line optical ground wires (OPGW).
Where a new water station is to be constructed, the network shall be extended to the new installation.
The SDH network operated by TRANSCO connects all of the primary substations and many pumping
stations across Abu Dhabi together and to the LDC, using multicore fiber optic lines. TRANSCO uses
ABB FOX‐515 rack or Alcatel 1660 hardware at each of the nodes on the SDH network.
Connection of pumping stations to the LDC shall be via the SDH network, in all cases. An SDH rack shall
be installed in the pumping station and it shall be connected by multicore fibre optic cable to the
existing SDH network at the nearest primary substation (usually the substation feeding power to the
pumping station) or existing pump station.
The Consultant should select a cost-effective telecommunication option among the SDH or other
means of communication, based on the type, location and topology of new water asset to
communicate with upstream pump station and LDC.
All new radio links will be subject to a radio signal survey, for selection of appropriate hardware, aerial
configuration and radio band.
Digital radio shall be used for the ‘last mile’ connection to all assets other than pumping stations,
which will have a direct, SDH fibre optic connection.
Wireless solutions are only acceptable as a temporary solution, until the permanent, fibre optic
connection is installed and commissioned.
Due to lower security level, the ADWEA mesh WIFI shall not be used for transferring the SCADA signals
in TRANSCO's water assets.
Meshed Wi-Fi network can be used for transmission of SCADA signals in exceptional cases where no
other communication media / means is available, subject to the establishment of a secure VPN and
data encryption for SCADA signal security and ADWEA approval.
Internal MPLS network may be introduced by TRANSCO in future as part of development process. This
can be considered as a possible means of communication in parallel with the existing SDH network.
There is no intention to use MPLS system of other service providers.
The GSM/GPRS shall be considered where there is no FOC/SDH network available in the area.
Connections to the SDH network require ABB FOX-515 or Alcatel 1660 compatible hardware. For
conversion from Ethernet to SDH, an Ethernet interface card can be mounted into the FOX-515 rack.
Where Ethernet switches are installed at existing interface points, they may be used in the network
topology to communicate with each other and to upstream pump station.
8.9 Security
8.9.1 Security of Control and Monitoring Systems
Security of the data and control system shall be assured by compliance with National Electronic
Security Authority (NESA) requirements, along with ICS Cyber-Security best practice guidance
produced by US National Institute of Standards and Technology (NIST) and UK National Cyber Security
Centre (NCSC). In particular the following should be referred to:
• NESA documents, including the UAE National Cyber Security Strategy (NCSS), UAE Information
Assurance Standards (UAE IAS).
• IEC 62443 (incorporating ISA 99, implementing ISO 27001 for Industrial Control Systems (ICS))
• Guide to Industrial Control Systems (ICS) Security – NIST Special Publication 800-82 revision 2.
• NCSC standards, including archived guidelines produced by CPNI
A “defense in depth” approach should be adopted, with multiple layers of security to mitigate the
weaknesses in any one layer.
SCADA networks should be segmented into Trust Zones, with controlled access via a limited number
of conduits, managed by layer 2 and 3 switches and firewalls. Systems and processes on TRANSCO’s
business network should not have direct access to the SCADA servers – All data should pass via an
intermediate data server in a de-militarized zone (DMZ).
Data transmissions over third-party networks and wireless communications shall be provided with
strong AES encryption and VPN tunnels shall be used.
The components should be hardened, with vulnerable ports closed as necessary. Malware and
intrusion detection systems (IDS) should be included. The Consultant shall review options for ICS
protocol-aware firewalls, appliances or protection systems with the Client.
Permanent connections for remote support access to SCADA should be avoided. Where these are
required, they should remain physically disconnected until needed. Connection should be managed
under a procedure which includes authentication and multifactor verification of the remote user’s
identity.
• Gate control
• Access control system
• CCTV system
Security system features that will be evaluated in final design are as follows:
9 Pipelines
9.1 Introduction
Pipelines are classified as either station piping or line piping. Pump Station Piping is defined as
pipework commencing at the pump station site upstream boundary and finishing at the point where
the discharge header exits the pump station site. Line piping is defined as the pipework extending
from the pump station boundary to the downstream storage tank/reservoir or customer take off
point. This section discusses line piping and explains the requirements for the design guidelines for
line pipe and its associated accessories and components, including:
• Conducting surveys;
As a general principle, it is preferred to maximise pipework welding and fabrication in the workshop
and to minimise field fabrication. The reference standards for pipelines are BS/ISO /EN by preference.
ISO 2531/ EN545 -Standard for Ductile-Iron Pipes Fittings and accessories
ISO 4633 -Standard for Rubber Joints Rings for Water Supply Sewerage
and Drainage Pipelines
EN545 -Ductile Iron Pipes, Fittings, Accessories and Their Joints for
Water Pipelines. Requirements and Test Methods
AWWA M51 - Air Valves: Air Release, Air/ Vacuum, and Combination
AWWA C205 - Cement- Mortar Protective Lining and Coating for Steel
Water Pipe 4 In. (100 mm) and Larger- Shop Applied
AD-SDI Data Standard -Spatial Reference System”, Version 1.0, Abu Dhabi Systems
& Information centre (ADSIC), December 2010
The topographical survey shall be conducted in accordance with the ADWEA / TRANSCO standard
specification w-c-ss-001. Surveys intervals along road corridors shall be to a maximum spacing of 20m,
and shall capture the following features, unless otherwise detailed in the specifications:
• Spot Heights;
• Topographical features (e.g. trees, kerb lines, landscaping edges, street lights / signposts etc.);
a. “AD-SDI Data Standard, Spatial Reference System”, Version 1.0, Abu Dhabi Systems &
Information centre (ADSIC), December 2010;
3. Survey shall be presented in accordance with the National Survey Datum in meters.
Where any of the above stated requirements contradict, the most stringent shall apply.
The geotechnical survey & soil testing shall be conducted in accordance with the ADWEA / TRANSCO
standard specifications. Surveys shall capture the following details, unless otherwise detailed in the
specifications:
4. Soil Quality (Redox potential, pH, Chlorides, Sulphates, moisture content at pipe depth, and
above maximum water table);
Details of geotechnical requirements are set out in guideline section for Geotechnical and Geophysical
Studies
Pipe material for any application is to be determined based on a Technical and Economical Assessment
to compare all the above materials. The assessment will be based on the whole Life Cycle Costs (WLCC)
taking into consideration, but not limited, to the following:
• The difference in failure rate (based on historical performance) for each material;
• Suitability of the material for the application (e.g. HDD, sub-sea installation, high pressure /
loads applications, etc.);
Composite solutions may be considered where pipes of different materials are used in combination.
3. ISO4633 Standard for Rubber Joints Rings for Water Supply Sewerage and Drainage
Pipelines;
Pipe design for Ductile Iron Pipes should also consider the following design considerations, in
accordance with EN545:
• Earth Load;
• Truck Loads;
• Deflection Design;
Most manufacturers tabulate safe ranges and loading conditions on ductile iron pipes. This is normally
acceptable and specific load/stress calculations would normally only be required outside the range of
the manufacturers information.
The pipe on the other hand, shall go through several checking to ensure that it can sustain the
overburden pressure, heavy traffic and operation vehicle loads. These checking include pipe collapsing
pressure, pipe allowable buckling pressure, and actual % of pipe deflection. This shall be done in
accordance with AWWA-M11. Moreover, the soil cover of the pipe in case of slab protection shall be
1.5m or above.
In case of crossing with existing or future services, the Contractor shall follow the recommendation of
the concerned Authority whether to cross above or under the respective services and the required
clearance to be left.
The Contractor shall design the said duct to sustain the required loads in accordance with the codes
and ADWEA Standard Specification Ref. W - C - SS – 003 latest revision. For more details Typical
Drawing N14054/TYPGA - 313 shall be considered as a guide for the Contractor design
All concrete external surfaces shall be coated with two layers of Epoxy paint of 300 microns in total.
Duct location and ownership shall be clearly marked by installing duct marker bronze plates at both
ends of the road.
Box culvert protection is also used for open cut road crossings where required by TRANSCO / Engineer
or the concerned Authority.
Box Culvert shall be sealed at each end with solid blocks and shall have ladder extended to the top
ground near to the road shoulder for maintenance accessibility.
In case of crossing with existing or future services, the Contractor shall follow the recommendation of
the concerned Authority whether to cross above or under the respective services and the required
clearance to be left.
The Contractor shall design the said box culvert to sustain the required loads in accordance with the
relative codes and ADWEA Standard Specification Ref. W - C - SS - 003 - Rev. 01. For more details
Typical Drawings N14054/TYPGA – 317 shall be considered as a guide for the Contractor design".
In case of crossing with existing or future services, the Contractor shall follow the recommendation of
the concerned Authority whether to cross above or under the respective services and the required
clearance to be left.
If deflections are made in any partial segments of pipe (pipes shorter than the full standard length e.g.
5.5m or 6.0m), particular attention shall be given to assessment of thrust and allowances for retained
pipe length.
4. DIN30670 –polyethylene coating of steel pipes and fittings – requirements and testing.
• Live Loads;
• Deflection Design;
• Buckling Design;
Equations for calculation of the above loading/stress analysis are presented in Section 3.4 Pipe Stress
Analysis of this guideline
For internal pressure, circumferential tension stress (Hoop stress) shall be based on requirements of
ASME B31.4 as set out in Pipe Stress Analysis Section. No Corrosion allowance is required, as pipes are
protected with suitable linings and coatings and are further supported with cathodic protection.
Consideration shall also be given to constructability in the selection of joints. Steel pipes may be either
rubber ring jointed, or welded. The following allowances are to be made:
1. A suitable distance of un-backfilled pipe shall be maintained before / after welded joints to
allow for localized thermal expansion during welding, to avoid damage to external coatings;
2. “Closure Welds” shall remain exposed for relieving expansion / contraction forces during
construction and normalizing of temperatures after backfilling;
3. For exposed pipes, expansion joints shall be located in between anchor points for flat pipes,
or on the downhill side of anchors for graded pipes;
4. Expansion joints on bridge crossing shall be in parallel to expansion joints on the bridge
structure;
6. Anchor rings shall be used where the pipe passes through concrete chamber, anchor, wall,
etc., and shall be designed with dimensions to resist shear punching;
1. HDPE pipes & fittings shall be protected from prolonged exposure to:
c. High Temperatures;
d. Oxidizing agents.
a. Sharp objects;
4. In all non-buried applications, pipe support shall be continuous along the length of the pipe.
For any elevation or suspension of HDPE pipe on non-continuous supports, design calculations
shall demonstrate that long term deformation under loading will not impede the function or
structural integrity of the pipe;
5. Buoyancy forces are to be taken into consideration for HDPE pipes to be installed beneath the
water table and in sub-sea applications. Design calculations shall demonstrate suitability of
the bedding material to resist buoyancy in the worst case condition, when pipes are empty;
6. For sub-sea applications of HDPE pipe, design calculations shall be used to determine the
required spacing and weight of anchors, during the worst case condition;
7. Steel tape to be installed above buried HDPE pipes, with a small separation space to ensure
the metallic tape does not make contact with the pipe;
8. HDPE pipe entry to any structure or anchor shall be protected from shear force through a
compacted bedding.
o Deflection Design;
o Buckling Design;
Design for wall compressive strength is to take the worst case scenario into consideration, which can
be 1.0 bar vacuum. Refer to Section 3.1 –Hydraulic Studies for minimum internal pressure design
cases. Analysis for internal and external loading will assume each to take place separately.
1. All HDPE pipe joint connections will require fusion welded or mechanically restrained joints.
Unrestrained joints of any kind shall not be acceptable.
2. Small pipe deflections shall not be accommodated through mitred welded joints. Cold
Bending shall be used to accommodate deflections, as detailed the following sub-section;
3. Connections from HDPE pipe to other pipe materials shall be made using flange adaptors;
4. Connections from HDPE pipe to any unrestrained pipe system (other pipe materials) shall be
anchored immediately upstream of the adaptor connection on the HDPE side;
5. Thrust blocks shall not be considered as a suitable restraint against pull-out forces.
In addition to the above design considerations, HDPE pipe shall not be connected to any structure or
anchor until the pipe material is allowed to normalize in the pipe trench.
Minor deflections and curvatures shall be uniformly distributed along pipe lengths as to prevent
kinking in the pipe material.
The selection of the pipe alignment is to be undertaken according to the following steps:
o Permission from utilities and authorities to pass through unused corridors / plots
(where applicable);
o Obtain the No Objection Certificates for the TPD approved route from the relevant
utilities and authorities;
o Undertake Detailed Design based on this information, confirming the final route and
profile;
o Submit Detailed Design and NOCs to the (TPD) of the relevant Municipality(s);
Stakeholder NOCs may include, but not be limited to, the following:
o Developers;
o Contractors;
o Consultants.
The minimum NOC requirements may be defined by the TPD as part of the route approval process.
Approvals may also require that Trial pits and Ground Penetration Radar (GPR) surveys be required
prior to construction.
No maximum pipe gradient is applicable, however pipes laid at gradients steeper than 30° shall be
assessed to determine the requirements for mechanical restraints to prevent movement or excessive
longitudinal stress on the structure or downstream fixtures.
Flat runs are generally not permitted, unless these are necessary over very short distances in order to
navigate obstructions, and where it can be demonstrated to TRANSCO through design calculations
that minimum gradient cannot be achieved, or would be more detrimental to the design.
Shallow pipe installations – where necessary – shall be supported with design calculations for suitable
protection by reinforced concrete cover slab or other means.
Maximum depth shall be determined based on Techno-Economical considerations, such as the effect
on pipe class, excavation depth and associated cost implications, and the spacing of air valves and
washout chambers. Maximum depth shall be supported with design calculations and testing for
several options.
9.12 Valves
9.12.1 Valve Arrangement
The minimum requirement for placement of isolation valves shall be as follows:
• On Straight Runs – Distances between isolation valves on straight runs depends on pipe
location and is subject to TRANSCO project requirements. As a guide it is expected that
distance between isolating valves in an urban environment would not exceed 1km and for a
non-urban environment is likely to be in the range of 5km to 10km. Isolation valves shall be
placed strategically on straight runs near high points to facilitate drainage towards washout
points, and should be located to take into account ease of access for maintenance, and
sensitivity of local environment to pipe failure;
• At Pipe Intersections – Isolation valves shall be placed at all pipe intersections based on the
‘n-1’ condition, where ‘n’ is the number of pipes meeting at an intersection. For example, an
intersection of 3 pipes will have isolation valves on 2 of the pipes. Valves at intersections shall
be placed as close to the intersection as possible based on space availability. In general, valves
that are within ‘50D’ of the intersection, where ‘D’ is the diameter of a pipe from the
intersection, shall be considered as effective isolation at the intersection;
• At Key Facilities & Appurtenances – Key facilities such as reservoirs, pump stations, etc. will
have isolation valves at all incoming and outgoing lines in order to facilitate isolation of the
facility. This is in addition to isolation on and between all manifold pipe work in order to
facilitate isolation if individual pumps or reservoir compartments, without interrupting
service of the facility. Valves shall also be installed upstream and downstream of critical
appurtenances, flow meters, and major control valves to permit isolation for maintenance
purposes. Bypasses of facilities and critical appurtenances shall also include an isolation valve.
The Tee-Off branch for Air Valves and Wash outs shall also include an isolation valve. Isolation
valves shall also be provided at all boundaries to the system, such as incoming supply lines
from desalination plants, and outgoing lines for bulk consumers, interface points, etc.;
Control valves are to be placed based on their specific functions as required to fulfil the design. For
example:
• Flow & Pressure Control Valves are to be placed based on their functional requirements to
achieve hydraulic conditions, typically at interface points;
• Check Valves are to be placed as required to prevent backflow through pump stations and
bypass lines;
• Needle Type Control valves are to be placed at each inlet pipe to a reservoir or if unavailable
then altitude valve to be used.
• At the Start and end of Pipelines – A vacuum breaker valve should be installed at the start
and end of pipelines (e.g. immediately after a pump station of incoming flow boundary such
as a desalination plant, or toward a reservoir / pump station or bulk consumer connection);
• At Isolated High Points – A combined Air Valve shall be installed at every isolated high point
along the pipe profile;
• Along Long ascending & Descending Runs – A vacuum breaker valve should be placed on long
ascending runs of constant gradient, and a combination valve on long descending runs of
constant gradient at a maximum spacing of 5km;
• On Either Side of Flat Runs, and NDM/HDD Sections – Although flat runs of pipe are to be
avoided, these may be required in special circumstances in order to pass obstructions. In such
circumstances, and on either side of a HDD of NDM run which cannot accommodate
intermediate air valves, a combination air valve shall be installed at the start and end of such
sections;
The calculation of number and size of air valves is covered under Section 7 Mechanical Design
Guideline. Guidance is also given in AWWA M51.
Where the location of air valves in accordance with the above conditions coincide, air valves may be
considered to satisfy several of the above conditions. Placement of air valves shall also be economized
by purposely locating them such as to satisfy multiple functions.
• At Isolated Low Points – A Washout Chamber shall be installed at every isolated low point
along the pipe profile. In special circumstances such as through HDD sections, it may not be
possible to place a washout at the lowest point in the profile. In such circumstances, the
• Along Long ascending & Descending Runs – A washout chamber shall be placed on long
ascending or descending runs at a maximum spacing of 1km;
Placement of Washout Chambers shall be arranged taking into consideration the location of isolation
valves such that each isolation “cluster” can be drained towards a washout at the lowest point, and
has a vacuum breaker valve at its highest point to facilitate emptying. An isolation cluster is a segment
of a network or pipe that can be completed enclosed from the surrounding network by the closure of
valves bounding it. Spacing of washout valves is to be determined on a case by case basis in discussion
with TRANSCO.
Where ever a line valve is located at a low point, the option to include a washout valve either side of
the line valve (but within the same chamber) should be considered. This will allow draining the pipeline
either side of the line valve.
Washout valves can also be classified as 2 types: - major wash out with large diameter at distinct low
points and; minor washout with smaller diameter at other low points.
At NDRC (non-disruptive road crossing) locations Wash out Facilities should be provided at one side
of the crossing. This should take the form of an access flange at the top point of the crossing to allow
insertion of a submersible drainage pump reaching to the bottom level of the pipeline.
Washout valves should be sized to allow draining of the pipeline at a flow velocity of between 0.3
and 0.6 metres per second. This velocity range is based on minimizing the risk of possible transients.
Refer to AWWA M51 for further information. Refer also to Hydraulics Section 3.1.4.4
Any additional requirements as per the project specifications shall also be applicable. Refer also to
Mechanical section of this guideline.
• Standard Ductile Iron Fittings. These include bends, tees, reducers, crosses and can be either
flanged or spigot and socket jointed. Flanged fittings should be used in chambers when
connecting with valves, meters etc. In general it is preferred not to use flanged fittings in
buried locations although there are some special cases which require a single flanged joint to
connect a straight pipeline between existing structures. If the flanged joint is used then it
needs to be protected with mastic putty covering bolts and then covered with shrink wrapping
• Wrought Carbon Steel Fittings are used in ground and in chambers. Wrought fittings are
preferred by TRANSCO.
• Fabricated Carbon Steel Fittings. These are used both in ground and in chambers on line
piping. In ground the fittings have welded joints and joint protection is as per welded steel
pipe joints. In chambers the fittings can be either welded or flanged jointed. The choice
depends on the function of the fitting and the ability to disassemble to allow removal of
meters, valves etc.
• Joint Fittings (Dismantling Joints, stepped couplings, collars, flange adapters, isolation
couplings). Joint fittings are used inside or outside chambers to connect pipes and fittings and
to allow insertion/removal of valves and meters etc. The choice of fitting depends on available
space, the need for thrust restraint, type of end fitting for connection to valves and pipes and
to a lesser extent the relative cost of the fittings. Inside chambers there is a need for at least
one joint fitting for each valve or meter to facilitate its installation/ removal. Outside the
chamber there would normally be the need to have one joint fitting for each run of pipe
between chambers, although there is nothing to prevent using joint connectors for each pipe
connection to a chamber
• Expansion Joints. Expansion joints can be two basic types-bellows type and slip type. Bellows
type allows for relatively large expansion lengths whereas the slip type normally allow for
smaller longitudinal pipe movement. For water supply systems the thermal expansion is not
normally large and the slip type joint would be sufficient. An example of a slip type joint is a
non-pressure restraining dismantling joint. Expansion joints are commonly used in above
ground locations such as bridge crossings
• Flanged Joints with Cathodic Protection. Cathodic Protection Insulation gasket shall be steel
reinforced rubber with flat steel reinforcing ring cast inside gasket and with no external
protrusion.
o At Interface Points – In accordance with TRANSCO’s standard detail for Interface Points with
generating companies and distribution companies;
o At Key Facilities – Upstream and downstream of major facilities such as Reservoirs and pump
stations;
Permanent Water Quality testing points consist of permanent apparatus to facilitate manual collection
of samples. Samples should be representative of the water quality at different strata in the pipe flow.
Sampling points should permit the collection of samples from live mains.
Sampling points shall be positioned at all incoming boundaries to the TRANSCO system, such as
connections from desalination plants, and upstream of interface points. Also, sampling points shall be
provided upstream and downstream of key facilities such as pump stations and reservoirs, and at
strategic junctures in the transmission system.
In general, sampling points should be provided in vicinity to permanent flow meters, as flow is an
important consideration in the interpretation of water quality data.
• Obstructions or sensitive sites at the surface preventing open trench excavation (e.g. major
roads, facilities, buildings, tourist attractions, etc.);
• Costly re-instatement requirements that would make NDM installation more cost effective;
NDM installations are to be kept to a minimum and shall cease at the nearest distance before and
after an obstruction or condition requiring NDM.
General Design requirements for open trench and NDM methods are presented in the following sub-
sections.
Trench excavations can be expanded locally to facilitate joint sockets, welding, etc. However trench
width shall not be excessively over excavated to prevent dead load from surrounding fill in excess of
the pipe design. In circumstances of over excavation, an engineered compacted fill shall be specified
to maintain distribution of soil loads in accordance with the design assumptions.
Sheet piling and appropriate temporary works will be designed for deep excavations and excavation
below the water table. Dewatering requirements will also be specified in the design.
Pipes shall be designed to sustain maximum axial thrust with a 4.0 factor of safety based on full
effective area and ultimate compressive strength of the pipe material. Pipe joints shall be designed to
avoid projections and should be tested at maximum permissible deflection by being subjected to 2
bars hydrostatic pressure.
The Contractor shall design the thrust and reception pits for minimum dimensions. Interlocking steel
sheet piles shall be used for securing excavations. In order to resist the jacking force in the thrust pit,
a reinforced concrete wall shall be provided at the pit. The Contractor needs to ensure that the pits
are dry during NDM WORKS.
Special design consideration will be given to pipes installed through NDMs, to account for the
following:
3. Maximum curvature (cold bending) for plastic pipes, and deflection at joints for spigot-socket
jointed pipes through excavated sections;
4. Stresses on end capping / anchoring points as a result of thermal expansion / contraction, and
contraction due to internal loading, for pipes run through a tunnelling casing;
5. Spacers to prevent contact between metallic pipes and metallic tunnel casing;
6. Shear Forces at entry / exit transition points to grouted and un-grouted tunnelled sections;
HDPE pipe “pulled” into place for NDM installation is to include “weak links” to protect against
exceeding maximum tensile strength.
The above considerations shall be addressed in detailed design and supported with design calculations
demonstrating the adequacy to accommodate additional stresses and loading to be encountered
during NDM installations. Particular attention shall be given to grouting / non-grouting, and
transitional arrangements at entry / exit to tunnel casings. NDM installations are discussed further
in the Civil Design Guidelines.
o HDD installations need to be “pulled” behind the reaming head, requiring pipe material with
flexible, welded or mechanically restrained joints;
o Pipe materials need to be continuously fed into the tunnel. Materials with joints that cannot
be assembled will need to have sufficient and parallel staging area for preparation of long,
pre-joined pipe lengths;
o The maximum curvature / deflection at joints shall be taken into consideration for the
selection of a pipe material and the vertical and horizontal alignment of the drilling route.
Selection of pipe material, joint types, drilling method, drilling routes, and staging areas shall be
presented with supporting design calculations.
The Contractor has to submit method statement where details about procedure, equipment, labour,
schedule and plan are specified. The Contractor shall also provide A0 size design profiles where drilling
installation coordinates and depths are illustrated.
Equipment of HDD comprise of four (4) main components; drilling system, steering system, and drilling
fluid (mud) system.
1) Site preparation
2) Drill path survey
3) Soil investigation
4) Bathymetric survey
5) Environmental protection adherence
6) Safety adherence
7) Pipe compliance
8) Pilot hole
9) Reaming
10) Steel pipe pulling
The Contractor shall ensure adequate performance of hydrostatic testing on the string of pipelines of
welded pipe joints. In case of failure of any of the sections, the Contractor should point out the cause
of it, fix it, and retest again to ensure that the section is passing.
• Pipes shall be analysed for loading as beams and / or columns, and calculations shall be
presented to determine maximum spacing of supports. Where support spacing is restricted
calculations shall determine any necessary adjustment to pipe wall thickness or material
changes as required to operate as a beam for the required spacing;
• The supports shall be structurally analysed for action as thrust restraints including at individual
joints and fittings. Calculations shall be presented to justify material selection, grade,
dimensions, and anchoring of pipe supports;
• Thermal Expansion / Contraction shall be determined for the length of the expose pipeline,
and the resulting forces on the pipeline and restraints shall be taken into consideration.
Calculations shall be presented to demonstrate the forces exerted on the pipeline, supports,
and adjacent structures;
• Pipe spans on supports will be laid with a minimum grade to avoid pooling between supports
(particularly for HDPE pipes).
Pipes acting as a beam shall be designed to minimize deflection such as to prevent damage to internal
linings and external coatings, and prevent permanent deformation of plastic pipes. Calculations shall
be presented to justify that deflection is within the allowances for the specified linings and coatings.
For plastic pipes, calculations will be presented to justify that the long term deflection of pipes over
the asset service life is within acceptable limits to preserve the function and structural integrity of the
pipe. Joint types will be taken into consideration in these analyses, and the strength of bolts for flanged
joints suitably assessed.
Design calculations are discussed further in the Pipe Stress Analysis in Section 3 of this Guideline.
Methodology for design calculations is also set out in AWWA M11.
Thrust restraint shall be provided for all spigot / socket and mechanical joints that are not restrained
against longitudinal movement and separation. Thrust restraint shall not be required for welded
plastic or steel pipes provided that the surrounding soil interaction provides sufficient resistance to
thrust for continuously welded sections of pipe. The same shall apply to continuous lengths of
mechanically restrained pipe.
Thrust is to be checked at locations where there is a change in flow direction or cross-section, such as
at fittings (reducers, tees, dead-ends, etc.), bends, and appurtenances (valves, meters, filters, etc.).
Thrust protection will be provided where the resistance from surrounding soil interaction is not
sufficient to counteract thrust forces, or where disturbance of the surrounding soil strata is
anticipated.
Where the need for thrust restraint is identified, the following types shall be considered:
4. Line Anchor.
The type of thrust protection to be adopted shall be based on a techno-economical comparison for
individual applications. Specifically, the lowest cost thrust restraint shall be considered, taking into
consideration limitations of space and soil characteristics, which may limit the technically feasible
options. Each type of thrust protection is discussed further in the following sub-sections.
Reinforced concrete thrust blocks are designed based on the concept of distributing thrust force to a
larger cross-sectional area of soil, as sufficient to resist the thrust force, based on the soil’s horizontal
bearing strength. These may also be designed to resist vertical movement by action of gravity on the
concrete block.
Thrust blocks shall be designed to satisfy specific dimensional requirements, in accordance with
AWWA M41, Section 8.3. Where soil is disturbed behind the bearing face, back fill is to be with a
material of equivalent or better bearing strength, and back filling shall be compacted and tested to
achieve a minimum density to be specified in the design.
For vertical thrust forces, a gravity thrust block shall be designed to counteract upward thrust forces.
Downward thrust forces shall be based on the vertical bearing strength of the surrounding strata.
Mechanical Restraining Joints may be used as an alternative to piled thrust blocks where space
limitations or soil characteristics would prevent the adoption of mass concrete thrust blocks.
Since Mechanical restraining joints also depend on interaction with surrounding soil, due
consideration shall be given for any anticipated disruption of the supporting soil strata. Furthermore,
the design of thrust protection using mechanically restrained joints shall exclude lengths of pipe with
no soil interaction, such as lengths of pipe laid through ducting or pipe casing.
In circumstances that would cause deterioration of a High Density Polyethylene (HDPE) pipe, such as
exposure to solvents, chemicals, high temperatures, or regular temperature fluctuations, HDPE shall
not be considered for use.
Corrosion protection requirements shall be determined continuously along pipeline lengths, and
protection may be increased where high risk conditions are identified.
1. Soil Resistivity;
2. pH;
3. Oxidation-Reduction Potential;
6. Moisture Content;
Also, investigations are to be undertaken to identify any direct current applied to adjacent or nearby
pipelines for cathodic protection (e.g. oil & gas lines).
9.16.2 Lining
Internal linings shall be considered for Ductile Iron and carbon steel pipes to protect the material from
the corrosive effects of the potable water.
9.16.2.1 DI Pipes:
DI pipes shall be internally cement mortar (buried) or FBE (exposed) lined in accordance with ADWEA
specification w-p-ss-001
9.16.3 Coating
9.16.3.1 DI Pipes:
Buried DI pipes shall be externally protected by a Metallic zinc and Bituminous Coating and
Polyethylene sheet encasement. The Buried Station Piping shall have FBE internal lining and external
coating. The PE sheet encasement shall be neatly warped and taped to the pipe, to ensure minimum
gap between the outer pipe water and PE sheets. Tape wrapping shall be applied where the soil is
aggressive or highly aggressive; refer to sub section “Resistivity Survey for Corrosivity of Soil along
Pipeline Route” under section 3.2.2.12 “Geophysical Investigation”.
All pipe joints that are coated with polyurethane DI shall be protected by heat shrinkage sleeves. The
function of these sleeves is to provide protection for the joints against corrosion as they have high
shrink ratio and high penetration resistant thick structure. For more details about the minimum
requirements of manufacturing heat shrinkable sleeves, refer to section 8.4.7 in W-P-SS-001 R4 in
ADWEA’s specification.
Carbon Steel pipes used for NDM and HDD applications shall be further protected by an epoxy based
polymer concrete, in order to protect the fusion bonded polyethylene outer coating during pipe
insertion. Fittings and appurtenances on steel pipes that are manufactured of dissimilar metals shall
be wrapped in Polyethylene sheet encasement, and connected to steel pipes using electrically
insulating joints.
For Cathodic Protection applied to Steel pipes, the protected pipe segment shall be made electrically
continuous through the adoption of joint bonding. It shall be applied in conjunction with the standard
external protection of Fusion Bonded Epoxy.
Pipe material fittings, appurtenances and joints (including gaskets) shall be specified that are resistant
to permeation from such substances.
HDPE shall not be used in locations where the presences of these substances in confirmed or exposure
is likely to occur in future.
Pipelines through heavily contaminated soils shall be laid in ducts which are resistant to permeation
and degradation from these substances. The ducting shall extend beyond the contaminated areas with
a safe margin, and ends of the ducts shall be capped to prevent soils and liquids entering.
Furthermore, the placement of air release, vacuum breaker valves, isolation valves, and washout
chambers shall take into consideration the requirements for flushing, testing, disinfection, and filling
of the pipelines for testing and commissioning.
Hydrostatic testing and commissioning will be carried out by the Contractor in accordance with
ADWEA standard specifications w-p-ss-010, w-p-ss-012 and w-p-ss-017 for ductile iron, carbon steel
and HDPE pipelines respectively. Pressure tests are to be carried out in pipeline sections with not more
than 20m elevation difference.
The detailed design shall incorporate a testing and commissioning plan to demonstrate how the
pipeline will be tested, disinfected and commissioned prior to hand over. Disinfection /testing to be
in accordance with AWWA C651. The plan shall take into account:
• Locations of air valves, wash out valves, isolating valves in both the existing and new pipeline
system to be utilised as part of testing and commissioning process
• Means of maintaining the existing system during the testing and commissioning process
APPENDIX A
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
LIST OF DRAWINGS
N14054/TYP/LD-101
NOTES:
18
01 02
03
04
05
06
07
08
09
10
11
12
13
14
15
17 16 02
18
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
DELIVERY SIDE
04
07 15
02 09 12 13 16 02
06
03 08 10 11 14
05
TYPICAL DRAWINGS
SECTION A-A NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-202
Xref .\XREF\X-Frame.dwg
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-203
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-204
GENERATOR CONTROL
PANEL ROOM
GENERATOR
BUILDING
UC001.1
LVSG
BATTERY
ROOM
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-205
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-206
LEGENDS
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-207
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-209
LEGENDS
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-210
MALE TOILET DOCUMENT ROOM
OFFICE ENGINEER OFFICE RECEPTION SERVER/UPS & ETISALAT ROOM RECEPTION
SHOWER
SHOWER
KITCHEN AND
DINING
FEMALE TOILET
MALE TOILET
STORE ROOM
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
ENGINEER OFFICE DOCUMENT ROOM
PRAYER ROOM
MEETING ROOM
OFFICE
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-211
LEGENDS
TYPICAL DRAWINGS
LCD MONITOR
KEYBOARD
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-212
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-213
SHOWER
CORRIDOR MACHINERY
PARKING
KITCHEN
STORAGE ROOM
MASTER CONTROL ROOM
(RAISED FLOOR)
LABORATORY
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-214
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-215
DOOR SCHEDULE WINDOW, LOUVRE & GRILLES SCHEDULE
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
ARCHITECTURAL
SCHEDULE OF DOORS AND WINDOWS
N14054/TYP/GA-216
TABLE OF ROOM FINISHES TABLE OF ROOM FINISHES
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
ARCHITECTURAL
SCHEDULE OF ROOM FINISHES
N14054/TYP/GA-217
NOTES:
TYPE-I (PIPELINES IN BUND FOR WET SOIL CONDITION) TYPE-II (PIPELINES PARTIALLY BURIED FOR WET SOIL CONDITION)
NOTE: NOTE:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
TYPE-IIIB (PIPELINES IN NORMAL / DRY SAND & HARD AREA WITH PROTECTIVE BUND) TYPE-IVB (PIPELINES DIRECTLY BURIED IN TRENCH FOR WET SOIL CONDITION PROTECTIVE BUND))
N 14054 TRANSCO
SCHDULE OF DIMENSIONS SCHDULE OF DIMENSIONS WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-301
NOTES:
TYPE-I (PIPELINES IN BUND FOR WET SOIL CONDITION) TYPE-II (PIPELINES PARTIALLY BURIED FOR WET SOIL CONDITION)
TYPICAL SECTION
TYPICAL SECTION
NOTE: NOTE:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
SCHDULE OF DIMENSIONS
TYPE-IIIB (PIPELINES IN NORMAL / DRY SAND & HARD AREA PROTECTIVE BUND) TYPE-IVB (PIPELINES DIRECTLY BURIED IN TRENCH FOR WET SOIL CONDITION WITH PROTECTIVE BUND)
N 14054 TRANSCO
SCHDULE OF DIMENSIONS SCHDULE OF DIMENSIONS WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-302
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-303
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-304 1
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-305
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-306
NOTES:
LEGENDS
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-308 1
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-309
NOTES:
LEGEND:
2 2
8 8
7 7
4 5 4 3
5 4 TYPICAL DRAWINGS
4
NOT FOR CONSTRUCTION
6
3 1
PLAN
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-310
NOTES:
SECTION B-B
LEGEND:
DETAIL-M
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
SECTION A-A
N 14054 TRANSCO
DETAIL-N WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-311
NOTES:
LEGEND:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
WO
AV
N14054/TYP/GA-312
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-313
NOTES:
LEGENDS
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-314
NOTES:
A A
LEGENDS
PLAN SECTION-A
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
B B
N14054/TYP/GA-315
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-316
SECTION B-B
PLAN
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-317
SECTION B
PLAN
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
SECTION C
SECTION A
N14054/TYP/GA-318
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
TYPICAL DETAILS OF
PIPE RISER
FOR NDRC WORKS
N14054/TYP/GA-319
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-320
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-321
NOTES:
LEGENDS
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-322
NOTES:
LEGENDS
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
TYPICAL DETAILS OF
FIBRE OPTIC CABLE
PULLING PITS, SPLICING AND
ELECTRICAL CABLE PITS
N14054/TYP/GA-324
TOPC TOPC
LEGENDS
TOPC
TOPC
TOPC
TOPC
TOPC
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054-TYP-GA-325
NOTES:
LEGENDS
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
DETAIL - 2
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
DETAIL - 1
TYPICAL DETAILS OF
CONCRETE RESERVOIR FLOOR PLAN
AND GA
N14054/TYP/GA-326
LEGENDS
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-327
NOTES:
LEGENDS
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
TYPICAL DETAILS OF
CONCRETE RESERVOIR
ELEVATIONS
N14054/TYP/GA-328
NOTES:
LEGENDS
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
TYPICAL DETAILS OF
CONCRETE RESERVOIR
CROSS SECTIONS
N14054/TYP/GA-329
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
NO SCALE
N14054/TYP/GA-330
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/GA-331 1
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/E-401
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/E-402
NOTES:
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/E-403
NOTES:
LEGEND :
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/E-404
LEGEND :
DETAIL-A
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
NO SCALE
N14054/TYP/E/405 02
NOTES:
LEGEND :
TYPICAL DRAWINGS
NOT FOR CONSTRUCTION
N 14054 TRANSCO
WATER STANDARD DESIGN GUIDELINES
N14054/TYP/E-406
Geotechnical and Geophysical Studies Guideline_TRANSCO
APPENDIX B
Geotechnical and Geophysical Studies Guideline_TRANSCO
APPENDIX C
Geotechnical and Geophysical Studies Guideline_TRANSCO
APPENDIX D
Geotechnical and Geophysical Studies Guideline_TRANSCO
APPENDIX E
Geotechnical and Geophysical Studies Guideline_TRANSCO
BOD5 (mg/L);
Ammonia (Free as N) or Ammonia (NH3-N) (mg/L);
Dissolved oxygen (DO) (mg/L);
Total suspended solids (TSS) (mg/L);
pH;
Phosphate (PO4) (mg/L);
Sulfides (S) (mg/L);
Nitrate (NO3-N) (mg/L);
Nitrite (NO2-) (mg/L);
Total Dissolved Solids (TDS) (mg/L);
Total Petroleum Hydrocarbons (TPH) (mg/L);
Geotechnical and Geophysical Studies Guideline_TRANSCO
Metals (Al, As, Ba, Cd, Cr, Cu, Fe, Mn, Hg, Ni, Zn, P) (mg/L);
Total bacterial count (MPN/100 ml);
Enterococci (MPN/100 ml); and
Chlorophyll-a (μg/L).
The process of sampling, to storage in coolers should not take more than 15 minutes.
Temperature should be verified via measurement by thermometer and recorded regularly on the
field logs during sampling and transport to laboratory. Samples should be delivered to the
laboratory within 8 hours of sampling.
In-Situ Water Survey
Water quality should be measured in-situ at each location (20 total along both alignments) using
a calibrated YSI 6600V2-4 Multi-Parameter Intelligent Water Quality Logger, or similar. At each
station, readings should be logged at one (1) meter intervals through the water column with
measurements recorded at the surface down to one (1) meter from the seabed. The following
parameters should be recorded:
Floating Particles/Floatable/Debris;
Odour; and
Colour (qualitative- change from background).
Results of the above sampling should be assessed against the relevant ambient water quality
objectives for sea and coastal waters.
Zooplankton and Fish Larvae Survey
Zooplankton tows should be conducted at a total of 10 stations along both of the pipeline
alignments, at 1 km intervals. Tows should be undertaken within the surface 1 m of the water
column, using a plankton net of 100 μm mesh size with a flow meter mounted in the mouth of
the net. A constant and slow towing speed should be adopted to ensure that the net stays at a
uniform depth throughout the duration of the tow (5 minutes total).
Once retrieved, and before removing the cod end, the plankton net should be washed down
with a seawater hose. This should ensure that all of the sampled plankton is concentrated at the
cod end. After rinsing the plankton net, the cod end should be removed and washed thoroughly
internally and externally with seawater to ensure that no plankton has adhered to the sides.
Care should be taken to ensure that all of the plankton in the cod end is transferred into the 250
ml sample container via the built in valve of the cod end. A solution of 10% Formalin buffered
with seawater should then be added to the sample container to preserve the plankton. Sample
containers should be wrapped in tin foil and immediately placed in a dark, cooled storage
container prior to transfer to the analytical laboratory for sorting and analysis. Samples should
be transferred under CoC procedures.
Sediment Quality Survey
Geotechnical and Geophysical Studies Guideline_TRANSCO
Sediment samples should be collected at 20 survey locations, every 500 m along both of the
pipeline alignments. Sediment sampling should be conducted using a Van Veen grab sampler.
As soon as sediment samples are collected, and before their transferal into sample containers,
visual observations should be made and a record of the following should be made:
Sediment color;
Character;
Volume;
Any visual or olfactory indications of contamination;
Any visual presence of biological organisms; and
Photograph.
Sediment should then be transferred to sterilized sample bottles provided by the analytical
laboratory.
Filled samples should then be transferred to coolers with ice and maintained below 4ºC until
received by the analytical laboratory. Sediment samples should be collected, handled, stored
and analyzed in accordance with applicable APHA (American Public Health Association) and
US EPA (specifically; US EPA SOP#EH-02) extraction and test methods.
All sampling equipment should be decontaminated prior to collection of each sample. The time
from sampling to storage in coolers should not take more than 15 minutes. Samples should be
delivered to the laboratory within 8 hours of sampling.
Samples should be sent to an ISO 17025, ENAS accredited and approved laboratory for
analysis of the following parameters:
Ammonia (mg/kg);
Hydrogen sulfide (mg/kg);
Sulfate, SO4 (mg/kg);
Total organic carbon (TOC) (mg/kg);
Organic phosphorous (mg/kg);
Metals (Al, As, Ba, Cd, Cr, Cu, Fe, Mn, Hg, Ni, Zn, P) (mg/kg);
Total Petroleum Hydrocarbons (TPH) (mg/kg);
BTEX (mg/kg);
Phenols (mg/kg);
Sediment oxygen demand (SOD) (mg/kg); and
Total bacterial count (MPN/100 ml).
Pertinent data should be recorded in field data sheets and chain of custody (CoC) records
should be completed. Sediment samples should be stored separately from marine water quality
samples.
Powder-less gloves should be utilized for handling all samples that are appropriate for the
sampled parameters. A clean pair of gloves should be worn for each sampling session, and
gloves should be disposed after the sample is stored in the Cooler.
During the reporting stage of this project, all results should be compared against internationally
and locally recognized standards for assessing the extent of contamination in marine
sediments.
Infaunal Sediment Analysis
A total of 10 benthic in-fauna samples should be collected along both of the pipeline alignments,
at 1 km intervals. Samples should be collected using a Van Veen grab sampler. Benthic infauna
samples should be processed from the whole of the grab. All samples intended for benthic
invertebrate analysis should be initially sieved (100 μm mesh) whilst on site at each station and
in-turn fully analyzed at a later point in a laboratory. Samples should be preserved using a
mixture of 10% buffered formalin. The samples should be kept at room temperature until
reaching the analytical laboratory. All samples for benthic sampling and sieving field work
protocol should be performed in accordance with the ISO/DIS
Geotechnical and Geophysical Studies Guideline_TRANSCO
16665 international standard, and in line with the ROPME (MOOPAM local guidelines).
Visual Ecology Survey
The precise details of the visual ecology survey should be decided based upon the preliminary
results of the geophysical survey. All areas that are of potential interest should be surveyed
further using either drop down video camera or a towed seabed mounted camera. Areas of
interest that should be surveyed are any potential rocky outcrops or potential coral reef areas
that may impact the position of the pipeline alignment. Any potential areas of interest should be
investigated using a drop down video camera where the substrate should be identified and any
sensitive organisms should be noted.
Baited Remote Underwater Video Systems (BRUVS) should be utilized to assess the extent of
demersal fish populations in the study area. BRUVS consist of an underwater video camera and
bait station mounted on a support frame and provides a non-destructive and non-intrusive
method of assessing fish populations. Each BRUVS should be deployed on the seabed for 30
minutes, and any fish that were attracted to the bait plume should be recorded using a high
definition video camera. The recordings provide a quantitative and repeatable measurement of
the abundance and diversity of fish and invertebrates in the immediate area of the deployment.
BRUVS should be specifically deployed in areas adjacent to rocky reef habitat (breakwaters) in
an attempt to capture a broad range of reef associated fishes.
Video footage should be analyzed to determine species richness and maximum abundance.
Maximum abundance should be calculated by counting the maximum number of any one
species present in any one frame (MaxN).
Geotechnical and Geophysical Studies Guideline_TRANSCO
APPENDIX F
Geotechnical and Geophysical Studies Guideline_TRANSCO
APPENDIX G
Geotechnical and Geophysical Studies Guideline_TRANSCO
GW A-1-a GRAVEL Generally Required for Generally not GW, SP, SW & All walls should
Well- Generally, not required spread needed except SP soils be designed to
graded not required if except footings, pile for SC soils or generally provide
cut or fill possibly for or drilled for large, heavy suitable for minimum F.S. =
slope is 1.5H SC soils. shaft structures. backfill behind 2 against
to 1V or foundations. or in retaining overturning &
GP A-1-a GRAVEL flatter, and or reinforced F.S. = 1.5
Poorly- underdrains Empirical soil walls. against sliding
graded are used to Spread correlations with along base.
draw down footings SPT values
GM A-1-b GRAVEL the water generally usually used to GM, GC, SM &
Silty table in a cut adequate estimate SC soils External slope
slope. except settlement generally stability
possibly for suitable if have considerations
GC A-2-6A-2- GRAVEL SC soils less than 15% same as
7 Clayey Erosion of fines. previously given
slopes may for cut slopes &
SW A-1-b SAND be a problem embankments.
Well- for SW or SM Lateral earth
graded soils. pressure
analysis
required using
SP A-3 SAND soil angle of
Poorly- internal friction.
graded
SM A-2-4A-2- SAND
5 Silty
SC A-2-6A-2- SAND
7 Clayey
MH A-5 SILT Required. Required. Required. Required. These soils are All walls should
Inorganic not be designed to
recommended provide
Erosion of Deep Consolidation for use directly minimum F.S. =
slopes may foundation test data behind or in 2 against
be a problem. generally needed to retaining walls. overturning &
required estimate F.S. = 1.5
Geotechnical and Geophysical Studies Guideline_TRANSCO
Rock Fills - not required for Required for Required where Required.
slopes 1.5H to 1V or flatter. spread rock is badly
footings or weathered or
drilled closely Use rock
Cuts - required but shafts. fractured (low backfill angle of
depends on spacing, RQD). internal friction.
orientation and strength of
discontinuities and Empirically
durability of rock related to May require in
RQD3 situ test such as
Pressuremeter.
TRANSCO
Abu Dhabi Transmission & Despatch Company