CONSTRUCTION OF 2 Nos.

ROLLING STOCK DEPOTS AT RANGE HILL AND VANAZ INCLUDING CIVIL AND E&M
PUNE METRO RAIL

Inspection Test Plan for Concrete structure al elements


Inspection Test Plan No URC/PMRP/PQP/QA/F-012, Rev

INSPECTION & TEST PLAN

Reference
SLNO Activity /Process Characterstics to be checked Methoid of Check Frequency Acceptable tolerance Format of r
documents

Technical
specification Technical specification URC/PMRP/
1 Layout of Excavation Inspection 100% Approved drawing Approved procedure F-007, Rev
Technical
specification Technical specification URC/PMRP/
2 Survey checking Inspection 100% Approved drawing Approved procedure F-006, Rev

Technical
specification Technical specification URC/PMRP/
3 Inspection during Reinforcement Fixing Inspection 100% Approved drawing Approved procedure F-007, Rev
Construction
Technical
specification Technical specification URC/PMRP/
4 Formwork fixing Inspection 100% Approved drawing Approved procedure F-007, Rev

Technical
Concrete prepour Pourcard Post pour specification Technical specification URC/PMRP/
5 inspection Inspection 100% Approved drawing Approved procedure F 008,009

Technical
specification Technical specification
6 Curing Inspection 100% Approved drawing Approved procedure Curing Reg

P- Performer, W-100%Notification in advanceto designated responsible R-100%Review& signedof Report, H- HoldPoint, M-Monitor

0 4/24/2019 For review & Approval

Rev Date Revision Prepared by Reviewed by


&M WORKS FOR

s
Rev 00

Responsibility
of record
URC GEC MAHA

RP/QAQC/
Rev 002 P W M

RP/QAQC/
Rev 001 P W M

RP/QAQC/
Rev 002 P W M

RP/QAQC/
Rev 002 P W M

RP/QAQC/
009,010 P W M

Register P W M