You are on page 1of 24

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/257199056

Anatomy of a Decision Trap in Complex New Product Development Projects

Article  in  The Academy of Management Journal · February 2013


DOI: 10.5465/amj.2010.0742

CITATIONS READS
48 786

4 authors, including:

Henk Akkermans Kim E. Van Oorschot


Tilburg University BI Norwegian Business School
95 PUBLICATIONS   2,265 CITATIONS    51 PUBLICATIONS   431 CITATIONS   

SEE PROFILE SEE PROFILE

Luk Van Wassenhove


INSEAD
373 PUBLICATIONS   23,558 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Design Science View project

Health Care dynamics View project

All content following this page was uploaded by Henk Akkermans on 27 May 2014.

The user has requested enhancement of the downloaded file.


娀 Academy of Management Journal
2013, Vol. 56, No. 1, 285–307.
http://dx.doi.org/10.5465/amj.2010.0742

ANATOMY OF A DECISION TRAP IN COMPLEX NEW


PRODUCT DEVELOPMENT PROJECTS
KIM E. VAN OORSCHOT
BI Norwegian Business School

HENK AKKERMANS
University of Tilburg

KISHORE SENGUPTA
LUK N. VAN WASSENHOVE
INSEAD, France

We conducted a longitudinal process study of one firm’s failed attempt to develop a


new product. Our extensive data analysis suggests that teams in complex dynamic
environments characterized by delays are subject to multiple “information filters” that
blur their perception of actual project performance. Consequently, teams do not realize
their projects are in trouble and repeatedly fall into a “decision trap” in which they
stretch current project stages at the expense of future stages. This slowly and gradually
reduces the likelihood of project success. However, because of the information filters,
teams fail to notice what is happening until it is too late.

In new product development (NPD) projects, per- deviations from plan as early as possible. With
formance problems such as slipping schedules, these early warning systems, organizations can
budget overruns, missed specifications, “firefight- save considerable sums of money by identifying
ing,” and “scope creep” are widespread (Bohn, failing projects while they are still in the early
2000; Mihm, Loch, & Huchzermeier, 2003). In some stages of development (Keil & Montealegre, 2000).
cases, these problems lead to the termination of But each year millions of dollars are spent on failed
projects. For example, in 2002, $55 billion was technology projects (Dilts & Pence, 2006), which
wasted in terminated information technology proj- indicates that it still takes considerable time to
ects in the United States (Pan & Pan, 2006). Bould- terminate a project. These findings motivate our
ing, Morgan, and Staelin (1997) and Hitsch (2006) overall research question: Why does it take teams
cited project failure rates of at least 35 percent so long to realize that a project is in trouble and
across different industries. Barczak, Griffin, and should be terminated, despite the availability of
Kahn (2009) found that only about 59 percent of sophisticated project management tools and
newly commercialized products are considered to techniques?
be successful. This rate of success remained largely To increase our understanding of how a project
unchanged between 1990 and 2004, even though management team uses information when making
the number of firms using formal processes, meth- decisions, and to analyze the effects of these de-
ods, and techniques to improve new product devel- cisions on project outcomes, we conducted a lon-
opment increased from 54 to 69 percent during the gitudinal, in-depth qualitative process study of
same period. Over the years, decision making has an NPD project team. Our data provide evidence
been professionalized, leading to the development that the team was indeed sensitive and respon-
of tools and procedures for guiding organizations sive to information revealing small deviations
toward desired outcomes (March, 2006). Barczak et from the project plan and that the decisions the
al. (2009) reported that the best-performing firms in team made in response to those deviations were,
their research sample used more formal processes, in fact, aimed at correcting the course of the
tools, and techniques, but their survey did not clar- project. However, these decisions turned out to
ify how and why this relationship was positive. be counterproductive in the long run. It took
Furthermore, even the best-performing firms had a 53 weeks before the team noticed that their deci-
failure rate of 25 percent. sions resulted in using up all the slack in the
Decisions to terminate a project may occur at project plan. This led to a renegotiation with the
different points in the project (Dilts & Pence, 2006). customer to postpone the final due date by a
Project management tools are intended to detect year—at the cost of increased project scope but
285
Copyright of the Academy of Management, all rights reserved. Contents may not be copied, emailed, posted to a listserv, or otherwise transmitted without the copyright holder’s express
written permission. Users may print, download, or email articles for individual use only.
286 Academy of Management Journal February

without an increased budget. Yet because of the tively derived from the study of the phenomenon it
increased scope, the extra time did not help: the represents (Strauss & Corbin, 1990: 23). Thus we do
company terminated the project in week 85 after not begin with a theory that we aim to prove; rather,
an investment of more than €20 million. we allow hypotheses to emerge from the process
The project was implemented by an organization study. The basic steps in such a study include (a)
in the semiconductor industry for a customer in the observing processes of stability and change over
automotive industry. This context was appropriate time, (b) sorting data into meaningful categories, (c)
for our study for a number of reasons. First, the developing hypotheses explaining the observa-
organization had all the required project manage- tions, and (d) corroborating these hypotheses using
ment tools and techniques in place, and team mem- a different sample or using the same sample at a
bers were highly experienced and trained to use different time (Van de Ven, 2007). The researcher
them. Second, due dates of NPD projects in the in a process study becomes a “fly on the wall” in
automotive industry are often, as they were in this order to observe closely—in this case, to observe a
case, fixed to a one-year cycle, the model year project’s decision-making process.
(MY): either a project is completed on time, or the
due date is postponed by one year, which usually
Setting
means that the particular design linked to the proj-
ect is doomed. Since being on time is of the utmost In 2007, a multinational organization, referred to
importance, we expected project teams to have a here as “TechCo,” initiated a large NPD project.
strong focus on meeting deadlines. Thus, we ex- TechCo is a leading semiconductor manufacturing
pected teams to be sensitive and responsive to proj- company founded more than 50 years ago. Head-
ect information revealing even small problems in quartered in Europe, the company has about 30,000
their project that could affect the schedule. employees working in more than 25 countries and
Our analysis of the case data provides insight had net revenues of €3.1 billion in 2010. TechCo
into why the project was terminated, despite the makes semiconductors that are widely used in TVs,
use of sophisticated project management tools mobile phones, and cars. It invests almost €400 mil-
and techniques. We show how managers uninten- lion annually in R&D and employs about 3,000
tionally but repeatedly shifted the burden for- engineers in various countries.
ward by preferring short-term, symptomatic fixes The NPD project of interest, “TechCar,” which
of problems rather than fundamental solutions. was of strategic importance to TechCo, consisted of
Hypotheses are derived that explain why, in this six subprojects involving more than 100 full-time
dynamically complex situation characterized by equivalent employees (FTEs) located in four differ-
delays, the team we studied did not realize that ent countries. Because of its size and importance,
the project was in trouble. We show how “infor- TechCar was an excellent candidate for our process
mation filters” (Russo, Carlson, Meloy, & Yong, study. Furthermore, TechCo was already at level 3
2008) confused decision makers and describe a of the Capability Maturity Model (CMM)1 and as-
“decision trap” (Russo & Schoemaker, 1989) that pired to reach the next level. As a result, during the
led the team toward project termination. Our period of our study, the company was devoting
analysis and the resulting hypotheses contribute significant attention to examining how TechCar’s
to the existing literature on project termination, project planning and tracking processes could be
perceptual errors, and decision making in com- improved. After we explained our research interest,
plex and ambiguous environments. TechCar’s program manager invited the first author
to attend the project’s core team meetings; these
meetings were meant for discussing all important
METHODS
project information and for making decisions. (The
This research originated from the authors’ com-
mon interest in management decision making in
1
NPD projects. Any analysis of how project manag- Especially in the information technology industry,
ers make decisions—and of how their decisions the CMM is a widely adopted framework (Galin & Avra-
hami, 2006; Harter, Krishnan, & Slaughter, 2000; Paulk,
affect project outcomes—requires an in-depth
1995) that classifies an organization’s software develop-
study with a long-term perspective. Therefore, we ment process into five maturity levels. Improvements in
performed a process study using the grounded the- cycle time, costs, and quality can be simultaneously at-
ory methodology. A process study is the study of tained by increasing the maturity level of a software
the temporal order and sequence of change events organization (Harter et al., 2000). An organization at
based on a story or narrative (Van de Ven, 2007: CMM level 3 is one whose processes are defined (docu-
196), and a grounded theory is one that is induc- mented and standardized).
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 287

core team consisted of the program manager, the These strings of words are either sentences that we
project leader, the project planner, and six subproj- literally copied from the project mailings or quotes
ect leaders.) These meetings were not meant to that we recorded during the core team meetings or
discuss the project’s technical details, which were interviews and then transcribed. We presented the
handled in separate technical meetings within sub- transcribed quotes to core team members for final
projects. The core team meetings provided us with inspection before coding. This procedure led to a
an excellent opportunity to examine the project’s final set of 344 events: 181 events (53%) from the
main issues or problems, how problems were per- project mailings, 153 events (44%) from the core
ceived, how decisions were made, and the short- team meetings, and 10 events (3%) from the inter-
and long-term effects of those decisions. As an in- views. We coded the 344 events using the concepts
troduction, the first author interviewed all core defined in the Appendix. To check for intercoder
team members (nine interviews), three members of reliability (Miles & Huberman, 1994), we asked a
the steering committee (three interviews), and second coder (not part of the research team) to code
TechCar’s strategy consultant (one interview). The 10 percent of the total set of events (34 events).
company also gave us access to project data on Agreement on the coding of this subset was 87.1
staffing levels and due dates as well as to all general percent, well in excess of the 80 percent reliability
e-mail messages intended for the entire project threshold suggested by Miles and Huberman. The
team that announced major breakthroughs or prob- next steps in the research process entailed indenti-
lems regarding time, costs, or functionality (25 of- fying meaningful events from the qualitative inci-
ficial mailings). After the start of this research proj- dent data, analyzing temporal relationships or pat-
ect, the first author acted as a silent and discreet terns of events, and developing a narrative.
observer of 29 core team meetings lasting two hours
each (there were 3 meetings that the author did not
THE NARRATIVE
attend because of illness or holidays). During the
research project, the four authors held quarterly TechCo executes over 1,500 NPD projects con-
meetings with the organization’s strategy consul- currently. The top 50 projects consist of the 10 most
tant (who served as the core team’s representative) critical projects in each of the firm’s five business
to discuss preliminary findings. lines. Our focal project, TechCar, was one of this
top 50 and therefore also one of the top 10 of its
business line. TechCar started in April 2007 with a
Data Analysis
planned development phase of three years. At the
A prerequisite to collecting longitudinal data is a start of the project, a lead customer in the automo-
set of core concepts that provides a selective focus tive industry was identified; this customer needed
for observing a change process (Van de Ven, 2007). the product by mid 2010 for integration into a new
These concepts can be viewed as “sensitizing cat- automotive product in MY2012.
egories” (Glaser & Strauss, 1967). In this study, we TechCo employs a “stage gate” approach to man-
use five core concepts to reflect the central factors aging projects (Cooper, 2008). That is, a project is
of concern to innovation managers (Van de Ven, divided into a number of stages, separated by
1986; Van de Ven & Poole, 1990): ideas, people, “gates,” milestones at which a steering committee
transactions, outcomes, and contexts. Ideas reflect (not part of the project’s core team) reviews the
the content (scope) of a project. People represent project’s overall status. At each gate, the steering
the perceptions and emotions of the core project committee decides whether to continue with the
team about the project’s status in terms of time, project or to terminate it (makes a go/no-go deci-
costs, quality, staff, or the project in general. Trans- sion). Intermediate gates create a high sense of ur-
actions describe the engagements people make gency for a team even when the final gate is well in
with others to implement ideas and to make the the future. For the TechCar project, the planned
adaptations required for achieving desired out- gates and their initial schedules were as follows:
comes. Context reflects the changes in the environ- project gate 1 was the end of the conceptual design
ment that may influence a project or even its firm stage (15 weeks from start); project gate 2 was the
(here, TechCar, TechCo). Outcomes represent ac- end of the detailed design stage (27 weeks from
tual deviations from a project plan in terms of time, start); project gate 3 was the end of the test stage
costs, and quality. The Appendix more fully de- (67 weeks from start); project gate 4 was the end of
fines these concepts. the component verification stage (85 weeks from
During the study, we recorded each qualitative start); project gate 5 was the end of the product
datum, defined as “a bracketed string of words verification stage (94 weeks from start); and project
about a discrete incident” (Van de Ven, 2007: 218). gate 6 was the end of the project and transfer to
288 Academy of Management Journal February

customer (161 weeks from start). This plan incor- ting enough work done and having their funds re-
porated about four months of overall slack time that duced. Suddenly, budget issues became the team’s
could be used to accommodate unforeseen events. new priority.

Week 24: “The bottom-up budget indicates that we


Stage 1: Conceptual Design Phase need much more budget for 2008 than currently
available. Detailed budget reviews are ongoing and
In the first two months after the start of TechCar, everyone is challenged to look for opportunities to
the core team performed roughly two activities: reduce the budget within required project timing.”
defining the project (e.g., defining customer re-
quirements, developing a master plan) and ramping Week 29: “The current budget estimate for [Tech-
up the team. The ramp-up had a good start, but it Car] without any additional changes still exceeds
became clear that hiring the right people required the imposed limit. Actions are being taken to reduce
considerably more time than planned. This issue the budget.”
affected the project’s progress, and thus the first These budget problems led the company to re-
gate’s due date began to slip. Quotes are from our structure TechCar. Seeking to increase efficiency,
various data sources, which are detailed above. TechCo took several steps: reducing the number of
Week 4: “We have [our] eye on four to six new key sites involved in the project, using only full-time
people. [The] . . . major concern is currently that the engineers, reusing designs from earlier projects,
possible candidates we interviewed for the position and reducing workload by dropping a number of
of subproject leader did not sufficiently match the minor customer requirements from the project
required profile. Search is continuing, of course, plan. By the end of 2007 (and just before reaching
with highest priority.” gate 1), the team had endured a difficult and tumul-
Week 9: “We are still looking for good people to fill tuous time. Yet the new contours of TechCar were
. . . several important key management roles in now defined, and optimism returned.
[TechCar]. This is now seriously starting to hamper
project progress. . . . As a result of this, the best-case Week 32: “It is our intention to continue [TechCar]
Gate 1 date of week 15 is no longer feasible. . . .” in such a way that the right balance is found be-
tween the various projects within the business line
Week 20: “Actions to create a detailed plan for the and the sites involved in the project. We may not
remainder of Gate 1 are ongoing. The current esti- succeed for 100% but I [the project leader] believe
mates show that the targeted week 33 may not be we are getting very close to this objective.”
feasible.”
Week 35: “The past week, we have spent lot of effort
TechCo is a multiproject organization, and the in gaining momentum in the project and to regain
R&D budget of its business line must be divided focus to enable [the] Gate 1 meeting in week 40. The
among a number of projects. The company allo- current status is positive. If we can step up further,
cates the available R&D budget once each calendar keep the focus on fast decision making and get back
year. Thus, the budget per project in 2008 was on track, then we will meet Gate 1 on time and we
defined at the end of 2007. Initially TechCo will also take a good step forward for Gate 2.”
planned for both stage 1 and stage 2 to be com-
There was hardly any time to recover from this
pleted in 2007, which meant that only stage 3
hectic period. To pass gate 1, the team had to make
would require a budget in 2008. However, as the
a detailed plan for the next stage. This plan re-
gates started to slip, it became clear that not only
vealed that a further ramp-up of the team was nec-
stage 3 would be implemented in 2008 but also all
essary. The struggle for staff started anew.
of stage 2 (and a small part of stage 1). These de-
velopments created problems for the 2008 budget Week 36: “The gate is slipping due to understaffing.
planning process— especially since a multiproject Hiring resources . . . [are] approved but resources
organization does not “roll over” unused project are not available. This will lead to delays.”
budgets, which instead are pooled and made avail-
able again to the entire organization (i.e., so all Week 39: “More capacity is required for configura-
projects can compete for them). For TechCar to tion management. There is a hiring delay. I [a sub-
project leader] cannot make a job offer to a potential
receive more of the 2008 budget than initially
candidate, and because it takes so long, the candi-
planned, the company would have to cut other
date may accept an offer from another company!”
planned projects. In order to protect those projects,
the steering committee forced the TechCar team to Week 41; “There are still critical resourcing issues
focus on cost cutting at the end of 2007. Thus, the pending to be solved on short term to enable achiev-
team faced two setbacks at the same time: not get- ing [the] target date for gate 3.”
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 289

Stage 2: Detailed Design Phase proceed as planned. The most likely scenario is that
we will focus on MY2013, which means postponing
The team successfully passed gate 1 in week 42, the project, because [of] scarcity of resources but
half a year behind schedule. However, the project’s with increased features.”
final due date was still MY2012. Because of this
huge delay with the first gate, the team had already
consumed a large part of the overall project slack. Back to Stage 1: Conceptual Design Phase
Any further delay in gate 2 would also endanger The summer of 2008 was used to restructure the
gate 3, which was the critical gate for realizing project, since TechCo had decided to postpone the
MY2012. These circumstances were a great chal- entire project to MY2013. The company could se-
lenge for the team, which remained understaffed. cure the lead customer’s agreement to this delay
Week 49: “Now, the gate 2 is delayed . . . [by] 6 only by increasing the scope of TechCar—that is, by
weeks. And we are only about 6 weeks after gate 1. accommodating additional customer requirements.
So the average now is 1 week work leads to 1 week However, there was no increase in the project’s
delay! This needs to improve!” budget. A new project plan was devised, and the
Week 51: “There is a risk of delaying gate 3 to week team returned to the conceptual phase. This meant
88. Delaying gate 3 is unacceptable! Gate 3 in week that it was necessary to clear gate 1 once again.
78 is already on the edge of meeting MY2012.” TechCo set week 79 as the new due date for this
gate. Yet because the conceptual work had to be
Week 53: “There is no slack left in the planning. To
improve efficiency and reduce costs, most of the
done first, the team now had a surplus of detail
slack was already taken out of the planning—and designers. The team tried to cut superfluous staff by
now, due to all [the] delays, all slack is gone. [If] . . . firing contractors and reallocating detail designers
we don’t make gate 3 in week 78, we are out of to other projects. What the team needed now was
business.” conceptual designers, but there was a shortage of
staff with these skills.
Week (56) “With the lack of resources I [a subproject
leader] have now, gate 3 can [only] be realized in Week 62: “However, although we shift to MY2013, it
week 103, instead of week 78! If we present this to has to be recognized that there is no additional
[our lead customer], the project will be killed. In budget available for [TechCar] in total; timing
week 78 we can show some functionality. But when should be shifted not more than four to six months
can we show full functionality?” to avoid adding too much risk for meeting MY2013.”
About one month before gate 2, the team was Week 74: “I [a subproject leader] am in need of [an]
confronted with new problems. After stretching extra 2 FTE, but this will be at the expense of other
gate 3 to the last possible date, the team had no projects when 2 FTE are reallocated to my subproj-
slack left in the plan. Any delay in gate 2 would ect. If the resources don’t come, there will be a delay
mean working during nights and weekends to catch of about 9 weeks. We need to focus on stability, on
up. Furthermore, because of project delays, budgets freezing the specs. It . . . [will be] difficult to realize
were tied up in TechCar for much longer than orig- MY2013, even without any changes.”
inally planned. This led to more projects in the Week 80: “Gate 1 was planned for week 79. Now it
business line running concurrently than planned is week 80. Though we are nearly there, officially
(i.e., its planned projects and the late-running proj- the gate is not passed yet. It is planned for Monday,
ect), which created cash flow problems. Not only week 81, so more than [a] one-week delay. Of course
was there no slack in time, there was also no slack gate 2 is left unchanged, for week 94. A lot of work
in the budget, and hence all new hiring was halted. has to be done before gate 1. [Furthermore, TechCar]
will run out of budget. We have to think which
Week 58: “Permanent vacancies are frozen, presum- requirements to leave out.”
ably because of a cash flow problem at [TechCo]. . . .
Of the 46 approved vacancies, only 5 will probably Week 85: “[TechCar] was cancelled yesterday
remain. Also there is a target for the reduction of afternoon.”
contractors.”
Delaying the project’s final due date provided
Week (59) “All signs for one of the subprojects are some relief. However, employee costs remained
red; passing Gate 3 this year is a no-go. Two design- high because of the surplus of detail designers not
ers resigned, and there are still vacancies. The proj- yet moved to other projects. At the same time, there
ect managers and system architects are overloaded. was a shortage of conceptual designers. Hence the
People are in firefighting mode.” extra work that needed to be done before passing
Week (61) “The ‘stop hiring’ scenario is the most the revised gate 1 (i.e., meeting the new require-
likely scenario. This means that [TechCar] cannot ments that the lead customer specified as compen-
290 Academy of Management Journal February

sation for the delay) was not completed on time, The Root Cause: Chronic Understaffing
and gate 1 started to slip again. The slipping date of
Figure 1 shows the planned staff (staff required)
the new gate 1, when combined with the high
versus the actual number of FTEs (available staff),
“burn rate” (expended costs per week), was simply
working on TechCar over time (the data are from
too much to handle. The team members could not
the plans maintained by the project’s management).
find a way to cut costs and also speed up the
project, so they were no longer confident that Tech- The plot illustrates the project’s two ramp-up phas-
Car could be completed successfully. The steering es: the start of the first stage (conceptual design) in
committee’s only feasible option was then to kill week 1 and the start of the second stage (detailed
the project. design) in week 43. (Note that Christmas caused the
dip in actual FTEs working on the project in
week 33.)
ANALYSIS: BALANCING AND More importantly, Figure 1 shows that the proj-
REINFORCING LOOPS ect team was chronically understaffed throughout
Why did it take the TechCar team 85 weeks to the project. Especially during the two ramp-up
terminate this project? To address this question, we stages, the actual FTE lagged behind the planned
will examine this pattern more closely (cf. Balogun FTE, leading to the staff-related problems dis-
& Johnson, 2004). We employ the conceptual lens cussed in core team meetings (see the quotes in the
of dynamic decision making and use the tool kit of narrative for weeks 4, 9, and 39). The team was not
system dynamics—in particular, causal loop dia- dramatically understaffed, but the difference was
gramming (Perlow, Okhuysen, & Repenning, 2002; enough to create a widening cumulative perfor-
Repenning & Sterman, 2002; Rudolph & Repen- mance gap between required performance (number
ning, 2002). System dynamics is especially suitable of completed tasks needed to finish the stage on
for situations involving multiple and interacting time) and actual performance (number of com-
processes, time delays, and other nonlinear effects pleted tasks given the available staff). The result
such as feedback loops and thresholds (Davis, was scheduling problems—namely, the risk of
Eisenhardt, & Bingman, 2007). The resulting anal- missing the project’s deadline (see the quotes for
ysis of our case data yields hypotheses about how weeks 36, 41, and 56).
the team used information to make decisions. The causality underlying this argument is shown
These hypotheses offer explanations for what hap- in the balancing “Staffing adjustment loop” (B1) of
pened that are fully consistent with the facts. To- Figure 2. We start on the left-hand side of this
ward this end, we also present figures showing balancing feedback loop: a performance gap caused
various behaviors over time involving different as- by a difference between actual and required perfor-
pects of the project. The figures illustrate graphi- mance. This led to schedule problems because
cally the root cause of the problems encountered, more time was required to complete the planned
how these problems manifested themselves to the tasks. The best way to resolve these schedule prob-
team, and the team’s unsuccessful remedies. lems was to address the corresponding staffing re-

FIGURE 1
Planned and Actual FTE Staff on the Project
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 291

FIGURE 2
Staffing Adjustment Loop and Schedule Slippage Loopa

a
Variables are related by causal links, which are shown as arrows. Each causal link is assigned a polarity: either positive (“⫹”) or
negative (“⫺”). A positive link means that if the cause increases (decreases), then also the effect increases (decreases). A negative link
means that if the cause increases (decreases), then the effect decreases (increases). See Sterman (2000).

quirements—in other words, to hire more people hires joined the project later than planned (hiring
(either internally or externally). However, hiring delay) and were not fully productive at the start
was subject to two kinds of independent delays: (assimilation delay). The team was probably not
Hiring delays reflected the time it took to hire able to calibrate their hiring decisions to match
someone from outside the company (three months these delays. Hence they adopted an additional
was not unusual; see the quote for week 39). As- tactic for solving the performance gap: gate slip-
similation delays occurred because new members page (see the quotes for weeks 36, 56, and 74).
who joined the team had to become familiar with
the company, the team, and the project; this learn-
The Temporary Fix: Allowing Schedules to Slip
ing process took time. Thus, after a decision was
made to hire new team members, it took some time The gap between required and actual perfor-
before those members became experienced enough mance becomes smaller when a schedule is al-
to solve the staffing problems, boost actual perfor- lowed to slip. Postponing a gate’s due date (gate
mance, and close a performance gap. This is why slippage) stretches the duration of a stage (the team
the staffing adjustment loop is balancing: the be- is given more weeks to do the same number of
havior described by this loop is self-correcting (i.e., tasks), which reduces required weekly perfor-
it counteracts change). The team definitely ob- mance. Like the staffing dynamics, this mechanism
served the performance gap caused by the staffing is (in system dynamics parlance) a balancing loop,
problems and tried to hire more staff, but good which means that the action—namely, letting the
people were difficult to recruit. Additionally, new schedule slip—aims to correct the discrepancy be-
292 Academy of Management Journal February

tween actual and required performance. This dy- the team did not realize that TechCar’s final due
namic is shown in the “Schedule slippage loop” date was under increasing threat until after a so-
(B2) of Figure 2. called perception delay. Any belief or perception
Slipping schedules were observed repeatedly in involves a delay because mental models cannot be
the project. depicts the planned due dates for gates updated instantly as new information is received
1, 2, and 3 for the project’s first 61 weeks (until the (Sterman, 2000). It was not until week 53 that the
dramatic events unfolded that would have delayed team finally realized that they had used up all the
the project by a full year). The plot reveals a set of slack (see the quote in the narrative for week 53). In
frequent and relatively small increments in the the “Overall project slack loop” R1 shows that the
planned due dates for these gates. unintended side effect of the “Schedule slippage
Small adjustments in schedules became the loop” (B2) is reinforcing rather than balancing. That
team’s preferred mechanism for dealing with the is, the mechanism used to reduce the schedule
persistently widening gap between actual and re- pressure of one stage causes the overall project
quired progress that staff hiring failed to overcome. schedule pressure (the fundamental issue) to grow
After the gate was allowed to slip and the corre- over time.
sponding stage duration was extended, staffing Increasing budget pressure through project de-
problems temporarily disappeared from the mana- lay. Stages 1 and 2 were initially scheduled for
gerial agenda. 2007. However, when the gates started to slip, all of
stage 2 (and even some of stage 1) were moved to
2008. This created problems for the 2008 budget
Unintended Side Effects
planning. As a result, the steering committee re-
Increasing overall project schedule pressure. quired the team to focus on reducing costs at the
The practice of letting the due date slip addressed end of 2007 (see the quotes in the narrative for
only the symptoms and did not solve the funda- weeks 24, 29, and 32). When gate 2 also started to
mental problem. The final due date of the TechCar slip, the need to lower costs surfaced again in week
project remained fixed. Therefore, every time an 58 (see the quotes for weeks 58, 59, and 61). Given
intermediate gate was delayed, the time remaining the pressure to stay within the given budget, the
for the rest of the project was shortened. Some slack team was cautious about hiring additional team
had been built in to the initial project plan, but that members. In week 61, business line management
slack decreased every time stage 1 was extended went so far as to forbid the hiring of any new team
and gate 1 postponed, reducing the probability of members. In an already understaffed team, this re-
finishing the project on time. However, it took the striction aggravated the personnel and schedule
team a long time to perceive this loss of slack. The problems. This reinforcing vicious cycle is shown
schedule was adjusted in small, gradual steps, and as the “Budget pressure loop” (R2) of Figure 4,

FIGURE 3
Slipping Due Dates of Gate 1 and Gate 2
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 293

FIGURE 4
Overall Project Slack Loop and Budget Pressure Loop

which extends the causal structure displayed in thereby further increasing the schedule pressure for
Figure 2. those subsequent stages. The reinforcing budget
When we combine the four loops presented in pressure loop led to tighter budget constraints,
Figure 4, a dynamic theory of what probably caused which in turn reduced and then eliminated the
this project’s termination emerges. Because of hir- possibility of hiring additional staff, thus increas-
ing and assimilation delays that were longer than ing the schedule pressure even more, until the proj-
anticipated, the team was understaffed from the ect “burst.”
start. Hence the team could not keep up with
planned performance, which led to schedule prob-
lems. A temporary fix that entailed gate slippage DYNAMIC COMPLEXITY: ANATOMY OF A
and extending stage duration circumvented these DECISION TRAP
problems. In the short run, this fix reduced sched-
Why Did They Not See It Coming?
ule problems (balancing schedule slippage loop); in
the long run, however, it only made matters worse. At this point in our analysis, we had a dynamic
Since the final gate of the project was immovable, theory that is consistent with the facts, but this
gate slippage in one stage required reducing the question remained: Why did these highly educated
available time and budget for other stages. As a and rational professionals not see the project termi-
result, the temporary fix caused schedule problems nation coming? Surely the team knew that they
to grow even more. Because of the reinforcing over- could not postpone due dates indefinitely, espe-
all project slack loop, the slack that was used dur- cially in light of the project’s fixed final due date.
ing the first stage was not available for the next, The core team members must also have known that
294 Academy of Management Journal February

the underlying problem was slowly and gradually numbed when it was accompanied by positive
gaining strength; as Van de Ven, Polley, Garud, and information.
Venkataraman wrote, “With time, unattended prob-
Week 33: “Progress is a little behind plan, but it is
lems often ‘snowball’ into vicious cycles” (2008: not alarming; the burn rate is also lower, so the
24). To understand how this system went out of progress made is in line with resources used.”
control, we needed to look much closer at how
decisions were made from week to week. Decisions Week 40: “Next week there will be a gate meeting
are subject to perceptual filters (Russo et al., 2008) per subproject; two subprojects are facing a major
challenge to meet all gate requirements, but one of
that can blur actual project status information and
the subprojects is OK.”
thereby lead the team to make the wrong decision.
Hence, we examined the most likely filters as well In any given week, the difference between the net
as how they could influence decisions made by flows of positive and negative news was relatively
the team. small, making it convenient to ignore that week’s
The mixed signals filter: Good news eases the bad news. However, over time the accumulated
pain of bad news. When a team is behind schedule negative news significantly outweighed the accu-
and receives both good and bad news at the same mulated positive news. This fact appears to have
time, it is likely to attribute the delay to bad luck escaped the team’s attention, since these accumu-
that can be overcome in the future; thus, the team lations were not tracked. In other words, the team
focuses on the positive news. But when a team is focused on flows rather than accumulations.
behind schedule and receives mostly bad news, it Prior research demonstrates that decision makers
is forced to acknowledge structural problems and often confuse flows and accumulations (levels) and
to admit that something drastic must be done to treat the former as a surrogate for the latter (Cronin,
alter the course of its project. Gonzalez, & Sterman, 2009). This confusion (or
Figure 5A displays, month by month, the accu- misperception) is one of the primary reasons why it
mulation of events that can be coded as “positive,” is difficult to understand and manage dynamically
“negative,” and “neutral.” From this figure, it is complex situations (Cronin et al., 2009; Sterman,
clear that in most weeks the accumulated positive 1989). We call this phenomenon the mixed signals
events were many fewer than the accumulated neg- filter, and it caused the team to misperceive the
ative events. It might seem that this pattern should weekly flow of ambiguous signals as a valid proxy
have clearly signaled the team that the overall project for the (accumulated) status of the project’s overall
status was negative. Yet when we look at the monthly progress. The mixed signal filter was on when the
change in these events—that is, when we look at the net flow of positive events was not less than the net
flow of events—the picture is quite different. displays flow of negative events; in that case, the team in-
the net flow of positive, negative, and neutral events terpreted the feedback as positive. However, be-
from month to month.2 From this figure, it is much cause the accumulation of negative events was
more difficult to assess what is happening to the greater than that of positive events (Figure 5A), the
project. Especially in the second half of the project, feedback should rather have been interpreted as
increases and decreases in the number of negative negative. The mixed signal filter was off when the
events were matched by like fluctuations in positive net flow of negative events exceeded those of pos-
events. Thus, the team received a nearly continuous itive events—a clear signal that the overall project
stream of mixed signals. The combination of positive status was negative (see also This filter is the basis
and negative signals about performance made it dif- of our first hypothesis.
ficult for the team to make overall sense of the feed-
Hypothesis 1. Teams working in complex dy-
back received and hence to assess adequately
namic environments characterized by delays
whether or not the project was in trouble (Van de Ven
pay less attention to the accumulation of neg-
et al., 2008). As a result, the implications of negative
ative project information and pay more atten-
information were blunted because they were not per-
tion to the (mixed) flow of positive and nega-
ceived as being strongly indicative of a problem (Keil,
tive information. As a result, teams may not
Depledge, & Rai, 2007). In particular, our case data
realize that their projects are in trouble.
suggest that the pain of negative information was
The waterbed filter: The underlying problem
does not manifest itself consistently. To ground
2
Mathematically speaking, the net flow is the deriv- the behavior of problems (and our proposed causal
ative of the accumulation. This means that when the net loop diagram of Figure 4) more solidly on our case
flow is positive (negative), the accumulation increases data, we grouped the qualitative quotes collected
(decreases). from the team meetings and project correspon-
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 295

FIGURE 5
Mixed Signals Filtera

a
Positive events include, for example, a successful meeting with the customer and good progress made in a particular week. These
correspond with codes PEP, PPTO, PPCO, PPOO, and PPRO in the Appendix.
Negative events include all the problems listed in Figure 6 and other negative feelings or outcomes. These correspond with codes PEN,
PPTP, PPCP, PPOP, PPRP, TTG, OTA, OCA, and OOA in the Appendix.
Neutral events include, for example, describing how the project-planning system works and identifying where information can be found
on the intranet. These correspond with codes II, IE, CI, CC, CE, TW, and TP in the Appendix.

dence into three types of topics: staffing problems, lation and net flow of problems, as grouped into
schedule problems, and budget problems. (We used these categories, that the core team faced over time.
these three categories, which comprise the vast ma- The figures allow us to infer two broad patterns
jority of comments made in team meetings and took of dynamic behavior: growth and oscillation. With
up most of the time spent in those meetings. See regard to growth, observe that the total number of
codes PPRP, PPTP, and PPCP, respectively, in the issues the team faced at any one moment fluctuated
Appendix.) Figures 6A and 6B show the accumu- from month to month but, over time, grew steadily:
296 Academy of Management Journal February

FIGURE 6
Waterbed Filter

from 4 ⫹ 5 ⫽ 9 issues in month 1, to 4 ⫹ 4 ⫹ 8 ⫽ in this first phase. Then, during months 4 –7 (weeks
16 issues in month 6, and 7 ⫹ 9 ⫹ 10 ⫽ 26 in month 13–25), schedule problems suddenly became the
15. Miller (1956) demonstrated that increasing the most pressing issue and led to repeated postpone-
number of issues an individual must simultane- ment of the gate 1 due date. In month 8 (around
ously process also increases the risk of compromis- week 29), the focus shifted to budget problems be-
ing performance. Rudolph and Repenning (2002) cause the team concluded that the project would be
illustrated this dynamic complexity in the context too expensive in 2008. Efforts to reduce costs suc-
of disasters. ceeded— but at the expense of even more staffing
With regard to oscillation, it is clear from that the problems during stage 2 (months 9 –11). The pass-
focus of attention for management switched repeat- ing of gate 1 in week 42 (month 11) was immedi-
edly from one area of concern to another. During ately followed by high schedule pressure for real-
the first three months of the project, staffing prob- izing gate 2 and the associated schedule problems.
lems were the biggest issue for the team. Of all the Budget restrictions resurfaced thereafter, and the
quotes in our data concerning problems in the proj- team could not hire any more staff. These problems
ect, about 70 percent dealt with staffing problems were followed by a complete rescheduling of the
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 297

project, including postponement of the final due jumped up that needed attention. This new prob-
date by one year. lem distracted the team from analyzing the root
From a system dynamics perspective, the causal cause of the first problem. This brings us to another
structure mathematically needed to generate the reason why the team misperceived events: the wa-
behavior shown in Figure 6A is similar to that of terbed filter.
the diagram in Figure 4. The pattern in Figure 6A If we assume that the team focused more on the
combines oscillation and amplification. The under- net flow of problems (Figure 6B) than on their
lying mathematical structure for an oscillation that accumulation (Figure 6A), then the waterbed filter
arises endogenously (i.e., not in response to some was on when the net flow of schedule or budget
oscillating input) is one of a balancing feedback problems was not less than the net flow of staffing
loop with at least two independent time delays problems (i.e., when the staffing problem was man-
(Sterman, 2000). In an oscillatory system, the state ifested as some other problem). The waterbed filter
of the system constantly overshoots and under- was off when the net flow of staffing problems was
shoots its goal. The time delays cause corrective not less than the net flow of schedule or budget
actions to continue even after the state of the sys- problems (i.e., when the staffing problem was ob-
tem reaches its goal, forcing the system to adjust too viously manifested as itself; see Table 1). Our next
much and triggering a new correction in the oppo- hypothesis is based on this filter, which follows
site direction (Sterman, 2000: 114). This dynamic directly from the multiple interacting and nonlin-
corresponds to our two balancing loops B1 and B2. ear feedback loops of Figure 4.
The corrective action of hiring additional staff con-
Hypothesis 2. Teams working in complex dy-
tinued until the team was actually overstaffed for a
namic environments characterized by delays
short time (see weeks 25–29 in Figure 1), which
are distracted from recognizing the steadily
reduced staffing problems and schedule problems
growing magnitude of an understaffing prob-
but increased budget problems (see weeks 25–29 in
lem because that problem repeatedly manifests
Figure 6A). The causal structure that generates am-
itself in different ways (e.g., as schedule and/or
plification or exponential growth is that of a rein-
budget problems). As a result, teams may not
forcing feedback loop (Sterman, 2000), such as
realize that their projects are in trouble.
loops R1 and R2 in Figure 4. The budget problems
constrained the hiring of additional personnel who The understaffing filter. The understaffing filter
were required for the next stage, which led to an is related to a team’s actual versus required staffing
acceleration of staffing problems (see week 30 in level. A team that is both understaffed and behind
Figure 6A), followed by schedule problems (see schedule will likely attribute the delay (an unfavor-
week 41). This dynamic is in precise accordance able outcome) to some factor beyond their control
with the causal structure of Figure 4. We can thus (Keil et al., 2007; Langer, 1975; Staw & Ross, 1978;
view the pattern in Figure 6A as capturing case data Zhao & Olivera, 2006). This factor is usually an
in a way that provides additional support for our external event caused by someone or something
causal loop explanation of why events unfolded as outside the team. A shortage of staff could easily be
they did. blamed on a human resources department that is
In a context such as this, where problems come not working fast enough or on the job market,
and go in waves, it may be difficult to see that they which was tight at the beginning of TechCar (see
are all symptoms of the same underlying root the quote in the narrative for weeks 4 and 39).
cause. One can understand why a team busy fight- Hence the team believed that understaffing was the
ing these symptomatic fires might fail to notice a cause of Stage 1’s due date slipping (see the quotes
small but steady increase in the magnitude of the for weeks 9 and 36). The implication is that, with a
underlying core problem. This phenomenon is also sufficiently staffed team, schedule problems could
known as a knowledge-based mistake, which oc- have been avoided in the past and could be pre-
curs when people are unable to analyze a problem vented in the future. Of course, if a team is behind
properly or to recognize the relations among its schedule yet is sufficiently (or over-) staffed, then it
elements (Zhao & Olivera, 2006). In our study, it cannot blame a human resources department or the
was difficult for the team to identify the most im- job market; it must find another and possibly inter-
portant problem because the contours of the prob- nal reason for the delay. This explains why we
lem set kept changing. It was as if the team was expect that decisions made in response to schedule
sleeping on a waterbed: when there was a heavy pressure will differ depending on whether or not
weight on one part of the bed, another part jumped the team is understaffed.
up. As soon as the team focused on one problem During periods in which the team was under-
and managed to solve this, another problem staffed, it had to predict how productive a future,
298 Academy of Management Journal February

TABLE 1
Filters, Decisions, and Results
Project Statusa Decisionb

Filter 1—Mixed Filter 2—Waterbed Filter 3—Understaffing Decision Trap—Stretch Decision—Stretch Result—Project
Week Signals (Figure 5) (Figure 6) (Figure 1) & Squeeze (Figure 3) & Slim (Figure 3) Slack Reducedc

9    Yes No
11    Yes No
15  ⴛ  Yes No
24   ⴛ Yes No
26 ⴛ  ⴛ Yes Yes
29 ⴛ ⴛ ⴛ Yes Yes
32  ⴛ  Yes No
35    Yes No
38    Yes No
41 ⴛ  ⴛ Yes Yes
47  ⴛ  Yes No
50    Yes No
51 ⴛ   Yes No
59 ⴛ  ⴛ Yes Yes
60  ⴛ ⴛ Yes Yes

a
The symbol “” indicates a filter was on, and “⫻” indicates it was off. Filter 1—Mixed signals: On when the net flow of positive events
is not less than the net flow of negative events. Off when the net flow of positive events is less than the net flow of negative events. Filter
2—Waterbed: On when the net flow of schedule and/or budget problems is not less than the net flow of staffing problems. Off when the
net flow of schedule and/or budget problems is less than the net flow of staffing problems. Filter 3—Understaffing: On when a team is
understaffed. Off when a team is sufficiently (or over-) staffed.
b
Decision trap—Stretch & squeeze: “Yes” indicates the team decided to stretch a current stage while squeezing future stage(s).
Decision—Stretch & slim: “Yes” indicates the team decided to stretch the current stage while slimming the overall project slack.
c
Result—Project slack reduced: “Yes” indicates overall project slack is reduced. “No” indicates overall project slack is protected
(unchanged).

fully staffed team would be. These predictions tend teams may not realize that their projects are in
to downplay the communication complexity and trouble.
coordination problems that vary as a function of the
Decisions made by the team: Stretch & slim or
size, composition, and experience of teams (Troy,
stretch & squeeze. Now that we have discussed the
Hirunyawipada, & Paswan, 2008). Larger teams re-
three filters that most affected the information per-
quire more coordination (Kessler & Chakrabarti,
ceived by the TechCar team, we turn our focus to the
1999). Furthermore, as discussed in the previous
actual team decisions—which were based on that
section, managers often fail to consider the full
filtered information—to get the project back on track.
negative impact on team productivity of the hiring
From the case data, two types of decisions can be
and assimilation delays associated with initiating
distinguished; we label these as stretch & slim and
or expanding a project team. This means that the
stretch & squeeze. When suffering from high sched-
productivity forecasts for a team that will be fully
ule pressure (i.e., many schedule problems) during a
staffed in the future are higher than the forecasts for
particular stage, the team extended that stage to allow
a team that is fully staffed but is still working
more time. Such extensions are made possible by
through the assimilation process. The understaffing
postponing the stage’s due date, thereby reducing
filter was on when the team was behind schedule
schedule pressure for that stage (balancing schedule
and understaffed, and it made the team more opti-
slippage loop of Figure 4). However, the extra time
mistic about the future productivity of a fully
allocated to a current stage has to come from some-
staffed team. The understaffing filter was off when
where. The first and obvious solution (stretch & slim)
the team was behind schedule and sufficiently
is to take time away from the overall project slack that
staffed, conditions that made the team more realis-
was initially built in to allow for unforeseen circum-
tic about future productivity (Table 1). The case
stances (reinforcing overall project slack loop of Fig-
data thus led us to our third hypothesis.
ure 4). Thus the current stage is stretched, and overall
Hypothesis 3. Understaffed teams working in project slack is reduced—a risky maneuver. So to
complex dynamic environments characterized protect the overall project slack, the team invented a
by delays tend to overestimate the potential second solution to buy more time for its current stage:
productivity of a fully staffed team. As a result, squeezing the planned duration of future stages (i.e.,
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 299

stretch & squeeze). The obvious benefit of this ap- when a delay at the first gate was perceived as
proach is that overall project slack remains un- being caused by external factors (e.g., long hiring
changed, which protects (at least on paper) the proj- delays caused by the human resources depart-
ect’s viability. However, when the duration of future ment), the next stage was expected to proceed
stages is squeezed, less time is available to do the much faster in response to internal factors such as
same amount of work; obviously, this increases efficiency improvements (much as with the “plan-
schedule pressure for those future stages. Hence this ning fallacy” described by Kahneman and Tversky
solution makes sense only if the team can boost its [1979]). The effect of information filters may am-
productivity in future stages. plify the illusion of control, increasing a team’s
Our case data reveal that the team decided to likelihood of misinterpreting the mixed signals, the
stretch and squeeze stages on many occasions. This magnitude of the underlying problem, and the po-
behavior is marked by the shaded areas of Figure 3. tential productivity of a fully staffed team.
The duration of stage 1 (the dark gray area in the
Hypothesis 4. Teams working in complex dy-
graph) gradually grew from 15 to 42 weeks. At the
namic environments characterized by delays
same time, the duration of stage 2 (medium gray
fight project problems by stretching current
area) was squeezed from 12 to 6 weeks during the
project stages at the expense of future stages
first 33 weeks of the project. After week 33, the
(stretch & squeeze) when they do not interpret
team apparently realized that a 6-week schedule for
project information correctly (information fil-
stage 2 was too optimistic; hence the duration of
ters are on). As a result, overall project slack is
stage 2 started to increase again—this time at the
artificially protected, and teams do not realize
expense of stage 3 (light gray area). It seems the
that their projects are in trouble.
team (wishfully) assumed that, during those future
stages, it would be productive enough to recover When information filters are off, a team is more
the lost time and slack. likely to interpret information feedback correctly.
In that case, the illusion of control is therefore
Week 50: “Challenging targets are being used to anticipated to be weaker or even absent. We then
create awareness of the importance of shortening expect that a team would decide to stretch a current
[project time]. Detailed and correct plans, however, stage and take time away from the overall project
are absolutely required to show the possibilities for slack initially built in to its project plan for unfore-
“crunching” or “fast-tracking” while keeping the
seen circumstances (stretch & slim). These remarks
same realism in project planning. It can be surpris-
ing to see the possible [project] time improvements
lead to our final hypothesis:
that can be achieved in this way.” Hypothesis 5. Teams working in complex dy-
A theoretical explanation consistent with the de- namic environments characterized by delays
cision to stretch and squeeze is that of the illusion fight project problems by stretching current
of control. When faced with low performance that project stages at the expense of overall project
was causing high schedule pressure, team members slack (stretch & slim) when they do interpret
retained their (erroneous) impression that termina- project information correctly (information fil-
tion would be prevented by hard work (cf. Simester ters are off). As a result, the overall project
& Zhang, 2010) and that they could influence out- slack is reduced, and teams realize that their
comes toward their desires (Lant, 1992). Langer projects are in trouble.
defined the illusion of control as “an expectancy of
a personal success probability inappropriately
Anatomy of a Decision Trap
higher than the objective probability would war-
rant” (1975: 313). This illusion persists because, By combining the information filters that con-
even though individuals are motivated to control fused decision makers with the two types of deci-
their environment, they are also motivated to avoid sions made by the TechCar team, we can derive the
the negative consequences that accompany the per- so-called anatomy of a decision trap. Table 1 gives
ception of having no control (Langer, 1975). A re- an overview of all filters and decisions.
lated tendency is that of individuals to attribute The table shows under what circumstances the
favorable outcomes to their own skills (internal or team chose to stretch and squeeze stages versus
endogenous factors) while attributing unfavorable choosing to stretch and slim overall project slack.
outcomes to circumstances beyond their control The first choice does not explicitly reduce overall
(external or exogenous factors) (Keil et al., 2007; project slack; the second decision does. In order to
Langer, 1975; Staw & Ross, 1978; Zhao & Olivera, establish how teams chose either of these deci-
2006). In the context of our case, this meant that sions, we must examine the three information fil-
300 Academy of Management Journal February

ters (mixed signals, waterbed, and understaffing). sion maker may be unable to identify what decision
Only by examining the filters and the decisions caused this effect (or that person may have been
made can we unfold the anatomy of the decision assigned to a different project).
trap into which the team fell. When two or more of Note also that projects can be successful despite
the filters were on (weeks 9, 11, 15, 24, 32, 35, 38, poor decisions made by a manager. In such cases, it
47, 50, and 51), the team decided to stretch the is probable that the manager will (wrongly) attri-
current stage and squeeze future stages, thus pro- bute this success to her/his prior decision making
tecting overall project slack. This provides evi- (Langer, 1975). Ross and Staw (1993) argued that,
dence for Hypothesis 4 and indirectly also for Hy- given a history of personal reinforcement, it can be
potheses 1, 2, and 3 because they feed into difficult for a project management team to conceive
Hypothesis 4. When two or more filters were off of a course of action not succeeding— especially
(weeks 26, 29, 41, 59, and 60), the team decided to when the exact causes of previous successes are
stretch the current stage at the expense of overall unknown. Long time lags between actions and out-
project slack. This provides evidence for Hypothe- comes, or causes and effects, slow down the learn-
sis 5. ing cycle; this reduces the ability to accumulate
The recurrent decision to stretch and squeeze experience (Sterman, 1994). As projects become
was, in fact, a decision trap that stemmed from the more complex, managers cease to learn from their
team’s wishful thinking (illusion of control) and experience; in some cases, this leads to the so-
was reinforced by ambiguous information—that is, called experience trap (Sengupta, Abdel-Hamid, &
information distorted by the identified filters. Ac- Van Wassenhove, 2008). The experience trap argu-
tions that in unambiguous conditions would be ment suggests that even an impressive career back-
viewed as deviant may actually become routine in ground does not guarantee that a manager has the
an ambiguous context (Lehman & Ramanujam, ability to oversee complex projects. Absent latent
2009). During the weeks in which the filters were errors, decision makers can learn about a system
off—when the information was consequently less when given enough time, stability, and unambigu-
ambiguous—the team exhibited less wishful think- ous information. Otherwise, however, learning may
ing and the quality of their decisions improved (cf. be difficult (Lant, 1992; Ramanujam & Goodman,
Lant, 1992). It was only during these weeks of rel- 2003). In any case, learning may be compromised
ative clarity that the team chose not to squeeze because memory of past experiences decays with
future stages but instead to take its losses and time (Denrell & March, 2001).
thereby consume overall project slack. The TechCar team suffered from all the impedi-
ments to learning described so far. The project was
dynamically complex, decisions had to be made un-
Why Did the Team Fall Repeatedly
der severe time constraints, and information was am-
into the Decision Trap?
biguous. The team worked hard and tried to solve
In the first 24 weeks of the project, stage 2 was problems as soon as they appeared. Not a single sub-
squeezed from an initial duration of 12 weeks to project leader had the luxury of being either ahead of
– 6 weeks. But in week 35, stage 2 had to be schedule or fully staffed. As a result, the subproject
stretched again—this time at the expense of stage 3. leaders had neither the time nor the energy to focus
This should have signaled to the team that their on the bigger picture and the root cause of the prob-
control was in fact an illusion and that they would lem. This is arguably why the entire team repeatedly
be better served by using overall project slack in- fell into the decision trap described here. Research
stead of squeezing future stages. Yet the team has shown that subjects tend to assign too much
clearly did not learn from this experience. The weight to available and salient features (March, 1991;
decision trap to which the team fell prey can be Repenning & Sterman, 2002). Thus, the easy, salient
characterized as a latent error (Ramanujam & Good- fix of the stretched stage left the underlying problem
man, 2003). Such errors are deviations (from a set in the TechCar project unchanged. While the problem
of expectations) that can create adverse organiza- symptoms cleared up, the underlying problem grew
tional consequences via positive feedback loops. worse (compare the systems archetype known as
However, latent errors are difficult to detect “shifting the burden” as developed by Senge [1990])
(whence “latent”) because direct (short-term) ad- and finally resulted in the project’s termination.
verse consequences are not evident. New product In a project as dynamically complex as Tech-
development projects usually take months or even Car, decision makers are required to become sys-
years to complete, so decisions made in the begin- tem thinkers—in other words, to incorporate
ning can have long-term effects. However, by the feedback and not be limited to linear thinking. In
time such effects are manifested, an original deci- a linear world, any gap between an actual and
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 301

desired situation can be resolved by a decision dicates two main reasons for why it can take a long
that brings the actual situation closer to the de- time before a team realizes a project is in trouble
sired one. But in a dynamically complex world, and needs to be terminated: escalation of commit-
decisions can have unintended side effects that ment (Staw, 1976) and groupthink (Janis, 1982).
aggravate the initial gap. If these side effects are The theory of escalation of commitment focuses on
ignored or overlooked, then a team’s goals will why managers continue to invest in projects in the
never be realized. The daunting complexity of the face of negative information. The literature on
cognitive task faced by the team in our study groupthink targets teams and interactions within
becomes more obvious still if, in addition to the them. In his seminal study on this phenomenon,
complicating factors listed so far, one recalls that Staw described escalation behavior as a negative
any action taken by managers triggers the multi- reinforcing process: “Due to a need to justify prior
ple and interrelated feedback loops shown in Fig- behavior, a decision maker may increase his com-
ure 4. In sum, it no longer seems so puzzling why mitment in the face of negative consequences, and
the team “didn’t see it coming”: they were in a this higher level of commitment may, in turn, lead
complex dynamic situation characterized by de- to further negative consequences” (1976: 29). Thus,
lays that made them misinterpret project infor- instead of accepting an immediate loss and termi-
mation, causing them to fall into the deci- nating the project, decision makers may commit
sion trap. new and additional resources in terms of funds,
The hypotheses we derived in this section and personnel, or time to it. Escalation of commitment
the resulting anatomy of a decision trap apply to can occur when managers have a strong sense of
the particular team we studied. By moving up the responsibility for a project (Schmidt & Calantone,
ladder of abstraction by inductive reasoning (Osig- 2002; Staw, 1976), for example because they initi-
weh, 1989; Van de Ven, 2007), we can now propose ated it (Green & Welsh, 2003) or because termina-
a hierarchical theory. We extend the breadth of our tion would have negative consequences for their
hypotheses into a more general proposition while careers (Harrison & Harrell, 1993); or it can occur
reducing their connotation (increasing simplicity). when a team suffers from perceptual biases (Voss,
Our general proposition is presented as a chain Rothermund, & Brandtstädter, 2008) that affect in-
argument. formation collection. Negative project status infor-
General proposition: mation is sometimes not available or not attended
to (Keil, Mann, & Rai, 2000; Simester & Zhang,
a. If a system is dynamically complex, it is difficult
2010), or initial positive beliefs are sometimes not
to see through information filters to make sense
updated in the face of negative new information
of the information (that is ambiguous, disguised,
(Biyalogorsky, Boulding, & Staelin, 2006). Optimis-
delayed) received from this system.
tic biases in the interpretation of ambiguous situa-
b. If it is difficult to make sense of information, a
tions have been documented (Voss et al., 2008).
decision trap is likely to occur, i.e. a decision
Biases can lead managers to see only what they
that seems to help in the short term but is coun-
want to see, which is any information indicating
terproductive in the long term.
that the project is on the right track (Balcetis &
c. If a decision trap occurs, it will take longer to
Dunning, 2006).
adequately assess what is actually driving the
Groupthink refers “to a mode of thinking that
behavior of a system.
people engage in when they are deeply involved in
This general proposition allows us to transfer our a cohesive in-group, when the members’ striving
findings to other complex dynamic phenomena in for unanimity override their motivation to realisti-
which this decision trap might apply. cally appraise alternative courses of action” (Janis,
1982: 9). Groupthink is characterized by self-cen-
sorship, illusions of unanimity, direct pressure on
DISCUSSION dissidents, and reliance on self-appointed “mind
guards” (see also Whyte, 1998). Groupthink may
Research Implications
cause a team to agree on issues, develop a prefer-
Termination of a project presents a difficult and ence for risk, and aim for uniformity. Groupthink
complex decision with strategic implications for an makes it difficult for groups to accept the “threat-
organization (Green & Welsh, 2003; Markham, ening” contrary information that is inherent to in-
2000). As a project progresses through the stages of novation projects (Schmidt, Montoya-Weiss, &
development, postponing the termination of a fail- Massey, 2001; Van de Ven, 1986). Whyte (1998)
ing project becomes increasingly expensive argued that groupthink follows from errant percep-
(Schmidt & Calantone, 1998). Previous research in- tions of collective efficacy—that is, overoptimistic
302 Academy of Management Journal February

judgments about a group’s capacity to perform a understaffing filter. The mixed signal filter ac-
specific task. Voss et al. (2008) examined judgmen- counts for the team’s focus on the flows, rather than
tal biases that operate by an asymmetric setting of the accumulations, of positive and negative infor-
thresholds regarding the amount of information mation. Because these flows were mixed, it was
that is required to accept a positive or negative difficult for the team to perceive that the situation
conclusion. was gradually deteriorating (Hypothesis 1). The
However, the results of our data analysis indicate waterbed filter explains why fundamental prob-
that escalation of commitment and groupthink can- lems that seem to be solved reemerge nonetheless
not plausibly explain why it took the team studied in a different manifestation (e.g., staffing problems
here so long to realize that their project was in “disguised” as schedule problems). This oscillating
trouble. With respect to escalation of commitment, between different manifestations of the problem
the team did not commit to requiring (or obtaining) further blurred the team’s view (Hypothesis 2). The
additional resources in terms of either budget or understaffing filter accounts for the difficultly of an
staffing. The team did commit to spending extra understaffed team in forecasting the productivity of
time on a current stage, but this was at the expense a fully staffed team (Hypothesis 3). Misinterpreting
of the time for future stages or the overall project project information (as a result of at least two of the
slack. TechCar’s core team discussed problems re- filters being on), combined with the illusion of
lated to staff, time, and budgets openly and in great control, caused the team to fall into the decision
detail. Moreover, the team certainly attended to trap of stretching the current stage while squeezing
this negative information. Staffing problems were the next, supposing that overall project slack was
addressed by intensifying communication with the protected (Hypothesis 4). When (at least two of) the
human resources manager. Due dates were post- filters were off and so the information was not
poned to accommodate problems with the project misinterpreted, the team decided instead (and cor-
plan. When budget issues arose, the team tried to rectly) to stretch the current stage and slim the
increase efficiency and reused designs from former overall project slack (Hypothesis 5). Together, the
projects. Furthermore, the members of the core filters and the psychological factors discussed here
team were not the initiators of the TechCar project; explain why it took the team so long to recognize
“adverse selection” (Harrison & Harrell, 1993) did the true gravity of the project’s problems. Finally,
not apply; and no incentive schemes were in place. the ambiguity of information and the long time lags
With respect to groupthink, the team was not a between decisions and their effects in this dynam-
closed circle that excluded advice or guidance from ically complex system could not have facilitated
others. Peer reviews were held (people from out- learning, so the team fell repeatedly into the same
side the team were invited to evaluate the team’s decision trap.
progress), and the gatekeepers (the steering com- It is known that people have difficulty in under-
mittee) were not part of the team. standing complex dynamic settings (Cronin et al.,
Because escalation of commitment and group- 2009; Sterman, 1989) and that they often respond to
think cannot answer our research question, we those settings by simplifying decision processes or
need a new theory. Our anatomy of a decision trap cognitive representations (Bourgeois, McAllister, &
goes beyond the research streams of escalation of Mitchell, 1978; Sherman & Keller, 2011), leading to
commitment and groupthink. Our analysis pro- poor performance. However the effect of informa-
vides an explanation of why it took the team so tion filters on this lack of understanding and con-
long to realize the trouble it was in: the difficulty to sequently, on interpreting project information and
see through different information filters which evaluating the status of the project has, to our
caused the team to make the wrong decision, which knowledge, not been examined before. According
in turn made it even more difficult to evaluate what to Green and Welsh (2003), managers need to de-
the actual status of the project was. We introduced vote more attention to understanding advocacy (ex-
a system dynamics lens that allowed us to show the pressing support for a project and assigning it a
periodicity and amplification of three important higher priority) and the role it plays in project
and interconnected problems in NPD—namely, evaluation. “Although such processes have been
staffing, time, and budget. Through this lens, we long recognized in R&D management, they have not
unravel the anatomy of a decision trap that ex- received the systematic attention that has been
plains why this highly skilled team did not see given to trying to understand the financial aspects
project termination coming. This anatomy consists of new product development” (Green & Welsh,
of three information filters that led the team to 2003: 431). The authors conclude that at present
misdiagnose the project’s deteriorating state: the this understanding is not well developed. Our re-
mixed signals filter, the waterbed filter, and the search is an important contribution to this under-
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 303

standing. The patterns graphed in Figures 5 and 6 are incubated and give off daily warning signals”
are fairly simple and seem self-evident. However, (2006: 517). It is therefore dangerous to interpret
none of the common project management tools and small but anomalous events as normal or accept-
techniques that are used by researchers and practi- able deviations. The main implication for manage-
tioners generate these patterns. In the absence of a ment is that problems—and not symptoms—should
dynamic perspective and periodically tracking and be solved as soon as they appear (i.e., when they are
accumulating positive and negative events and dif- still small). This approach requires a sensitivity or
ferent types of problems, information filters will mindfulness with which a project team pays atten-
continue to prevent project teams from realizing tion to the subtle as well as the dramatic (Senge,
when projects are in trouble. Consequently, project 1990) and reacts to even weak signs of a problem
teams will continue to fall into the decision trap (Coutu, 2003). The staffing problem that TechCar
leading to project termination. faced is typical of many projects, so project teams
On a more abstract level, we have developed a should pay close attention to even slight manifes-
proposition that allows our decision trap to travel tations of this problem. Perhaps management could
beyond the context of new product development ask one person in each big project to keep track of
teams. This proposition states that in a complex the items we tracked in this study and to generate a
dynamic system, it is difficult to see through infor- simple scorecard based on some of our graphs (e.g.,
mation filters and to make sense of the system plotting the frequency with which staffing, sched-
information received. As a result, a decision trap is ule, and budget problems are discussed in team
likely to occur: a decision that seems to help in the meetings).
short term but is counterproductive in the long Furthermore, hasty solutions (“patches”) should
term. When this occurs, it will take longer to ade- not be tolerated; they might cause old problems to
quately assess the drivers of the system’s behavior. reemerge and can even create new problems (Bohn,
There are other complex dynamic systems in which 2000). For TechCo, this approach would have
this decision trap could occur. Think for example meant that, as soon as management realized the
about a weight loss struggle. Suppose someone TechCar project was understaffed (and given that
wants to lose ten pounds in the next ten weeks to be the project’s final due date was fixed), only three
ready for the summer season. It is very likely that courses of action were viable: (1) increase the bud-
this person eats too much in the first weeks, but get to hire more staff (and more quickly), (2) reduce
keeps planning to make up for this in the remaining the project’s scope to decrease workload, or (3) halt
weeks. On paper it seems possible to lose ten the project. However, the relationship between
pounds in five weeks; in reality it will probably higher budgets now and a greater chance of project
never happen, and this failure will increase the success (four years) later was apparently too fuzzy
weight loss struggle. Another application of the to be convincing. Ironically, the actions of the core
decision trap is found in traffic congestion manage- team eventually led to a budget freeze and an in-
ment. A relatively short-term solution to conges- crease in scope: precisely the opposite of what the
tion is building more lanes, which temporarily re- team needed.
duces the problem. However, over the long term the To detect problems as soon as possible, a team
new lanes may increase the attractiveness of using should be aware of the dynamically complex situ-
cars, leading to a growth of the number of cars on ation in which it is operating. Previous research has
the road, which increases congestion again. shown that most individuals lack the capacity to
deal with dynamic complexity (Gonzalez, 2005;
March, 2006; Van de Ven, 1986). However, this
Managerial Implications
capacity can be improved by providing participants
Especially in large, complex NPD projects that with cognitive feedback: information about rela-
employ more than a 100 staff, cost millions of eu- tions in the decision environment, about relations
ros, and take years to complete, it seems a waste of perceived by the person in that environment, and
time to focus managerial attention on a staffing about relations between the environment and that
problem that involves (say) only two FTEs or on a person’s perception of it. Sengupta and Abdel-
stage delay of a single week. Nevertheless, our re- Hamid (1993) demonstrated that cognitive feed-
search confirms the intuition that small problems back can improve performance in dynamic deci-
can snowball into big problems. Because complex sion-making tasks. Gonzalez (2005) argued that
systems are so interdependent, a small glitch in one cognitive “feedforward” (information that helps de-
place can lead to a massive failure elsewhere (Rob- cision makers to analyze the effects of possible
erts, Bea, & Bartles, 2001). But, as Weick and Sut- future decisions) improves performance when dy-
cliffe remarked, “Accidents are not sudden, they namic decision-making tasks are performed in real
304 Academy of Management Journal February

time. Mapping causal relationships (as in Figure 4) ners and researchers would not be witnessing so
also helps decision makers because it forces them many projects being terminated.
to be explicit—not only about relevant variables,
but also about their dynamic properties (Ramanu- REFERENCES
jam & Goodman, 2003). Causal maps provide feed-
Balcetis, E., & Dunning, D. 2006. See what you want to
forward-based heuristics for managing projects in a see: Motivational influences on visual perception.
complex dynamic environment. They indicate Journal of Personality and Social Psychology, 91:
what the underlying problem is in a particular set- 612– 625.
ting (the problem that should be addressed as soon
as it occurs) and also which problems are merely Balogun, J., & Johnson, G. 2004. Organizational restruc-
turing and middle manager sensemaking. Academy
symptoms of the underlying problem.
of Management Journal, 47: 523–549.
This list of managerial implications underscores
the dynamic complexity of managing NPD projects. Barczak, G., Griffin, A., & Kahn, K. B. 2009. Perspective:
Our findings suggest that preventing project termi- Trends and drivers of success in NPD practices—
nation must begin with an understanding of a proj- Results of the 2003 PDMA best practices study. Jour-
ect management problem’s underlying structure. It nal of Product Innovation Management, 26(1):
3–23.
is important to recognize that understaffing is not
the only underlying problem; in our case the prob- Biyalogorsky, E., Boulding, W., & Staelin, R. 2006. Stuck
lems began with an understaffed team, but in other in the past: Why managers persist with new product
projects the problem could originate elsewhere. failures. Journal of Marketing, 70: 108 –121.
Bohn, R. 2000. Stop fighting fires. Harvard Business
Limitations and Future Research Review, 78(4): 82.
Boulding, W., Morgan, R., & Staelin, R. 1997. Pulling the
The results of our analysis are presented with
plug to stop the new product drain. Journal of Mar-
some caveats that are often associated with longi- keting Research, 34: 164 –176.
tudinal process studies. First, selective bias may
result from our exclusive focus on decision making Bourgeois, L. J., McAllister, D. W., & Mitchell, T. R. 1978.
in the studied project. Apart from this focus, how- The effects of different organizational environments
ever, we had no preliminary bias regarding what upon decisions about organizational structure.
Academy of Management Journal, 21: 508 –514.
kind of decisions the team would make. Our re-
search started soon after the project began and long Cooper, R. G. 2008. Perspective: The stage-gate® idea-to-
before any signs of severe problems surfaced, so the launch process-update, what’s new, and nexgen sys-
data collection was not biased toward finding tems. Journal of Product Innovation Management,
causes of project termination. There was no hind- 25: 213–232.
sight bias, either, because we studied the project in Coutu, D. L. 2003. Sense and reliability: A conversation
real time. Second, the study was performed in a with celebrated psychologist Karl E. Weick. Harvard
single organization; this limits our ability to corrob- Business Review, 81(4): 84 –90, 123⫹.
orate our hypotheses with a different sample and Cronin, M. A., Gonzalez, C., & Sterman, J. D. 2009. Why
thereby generalize the results. We were fortunate to don’t well-educated adults understand accumula-
find a repetitive pattern of events in the same or- tion? A challenge to researchers, educators, and cit-
ganization, because this allowed for corroborating izens. Organizational Behavior and Human Deci-
our hypotheses in the same sample but at a differ- sion Processes, 108: 116 –130.
ent time (Van de Ven, 2007).
Davis, J. P., Eisenhardt, K. M., & Bingman, C. B. 2007.
This study opens many opportunities for further Developing theory through simulation methods.
research into the conditions under which projects Academy of Management Review, 32: 480 – 499.
are terminated and how these conditions differ
from those that promote project success. It also Denrell, J., & March, J. G. 2001. Adaptation as informa-
suggests avenues for studies on establishing early tion restriction: The hot stove effect. Organization
Science, 12: 523–538.
detection mechanisms and appropriate measures to
avoid project termination. Furthermore, the role of Dilts, D. M., & Pence, K. R. 2006. Impact of role in the
slack in an overall project schedule is interesting to decision to fail: An exploratory study of terminated
investigate further. Maybe teams without any slack projects. Journal of Operations Management, 24:
pay more attention to small deviations from project 378 –396.
plan. As our data show, the true causes of project Galin, D., & Avrahami, M. 2006. Are CMM program in-
termination lie far beyond the domains of skills, vestments beneficial? Analyzing past studies. IEEE
tools, and techniques. Otherwise, today practitio- Software, 23(6): 81– 87.
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 305

Glaser, B. G., & Strauss, A. L. 1967. The discovery of intelligence. Strategic Management Journal, 27:
grounded theory: Strategies for qualitative re- 201–214.
search. Chicago: Aldine.
Markham, S. K. 2000. Corporate championing and an-
Gonzalez, C. 2005. Decision support for real-time, dy- tagonism as forms of political behavior: An R&D
namic decision-making tasks. Organizational Be- perspective. Organizational Science, 11: 429 – 447.
havior and Human Decision Processes, 96: 142–
154. Mihm, J., Loch, C., & Huchzermeier, A. 2003. Problem-
solving oscillations in complex engineering projects.
Green, S. G., & Welsh, M. A. 2003. Advocacy, perfor- Management Science, 46: 733–750.
mance, and threshold influences on decisions to ter-
minate new product development. Academy of Miles, M. B., & Huberman, M. 1994. Qualitative data
Management Journal, 46: 419 – 434. analysis: A sourcebook of new methods (2nd ed.).
Beverly Hills, CA: Sage.
Harrison, P. D., & Harrell, A. 1993. Impact of “adverse
selection” on managers’ project evaluation deci- Miller, G. A. 1956. The magical number seven plus or
sions. Academy of Management Journal, 36: 635– minus two: Some limits on our capacity for process-
643. ing information. Psychological Review, 63: 81–97.

Harter, D. E., Krishnan, M. S., & Slaughter, S. A. 2000. Osigweh, C. A. B. 1989. Concept fallibility in organiza-
Effects of process maturity on quality, cycle time, tional science. Academy of Management Review,
and effort in software product development. Man- 14: 579 –594.
agement Science, 46: 451– 466. Pan, G., & Pan, S. L. 2006. Examining the coalition dy-
Hitsch, G. J. 2006. An empirical model of optimal dy- namics affecting IS project abandonment decision-
namic product launch and exit under demand un- making. Decision Support Systems, 42: 639 – 655.
certainty. Marketing Science, 25(1): 25–50. Paulk, M. C. 1995. How ISO 9001 compares with the
Janis, I. L. 1982. Groupthink: Psychological studies of CMM. IEEE Software, 12(1): 74 – 83.
policy decisions and fiascoes. Boston: Houghton Perlow, L. A., Okhuysen, G. A., & Repenning, N. P. 2002.
Mifflin. The speed trap: Exploring the relationship between
Kahneman, D., & Tversky, A. 1979. Intuitive prediction: decision making and temporal context. Academy of
Biases and corrective procedures. TIMS Studies in Management Journal, 45: 931–955.
Management Science, 12: 313–327. Ramanujam, R., & Goodman, P. S. 2003. Latent errors and
Keil, M., Depledge, G., & Rai, A. 2007. Escalation: The adverse organizational consequences: a conceptual-
role of problem recognition and cognitive bias. De- ization. Journal of Organizational Behavior, 24:
cision Sciences, 38: 391– 421. 815– 836.

Keil, M., Mann, J., & Rai, A. 2000. Why software projects Repenning, N. P., & Sterman, J. D. 2002. Capability traps
escalate: An empirical analysis and test of four the- and self-confirming attribution errors in the dynam-
oretical models. MIS Quarterly, 24: 631– 664. ics of process improvement. Administrative Sci-
ence Quarterly, 47: 265–295.
Keil, M., & Montealegre, R. 2000. Cutting your losses:
Extricating your organization when a big project Roberts, K. H., Bea, R., & Bartles, D. L. 2001. Must acci-
goes awry. Sloan Management Review, 41(3): 55– dents happen? Lessons from high-reliability organi-
68. zations. Academy of Management Review, 15: 70 –
79.
Kessler, E. H., & Chakrabarti, A. K. 1999. Speeding up the
pace of new product development. Journal of Prod- Ross, J., & Staw, B. M. 1993. Organizational escalation
uct Innovation Management, 16: 231–247. and exit: Lessons from the Shoreham nuclear power
plant. Academy of Management Journal, 36: 701–
Langer, E. J. 1975. The illusion of control. Journal of
732.
Personality and Social Psychology, 32: 311–328.
Rudolph, J. W., & Repenning, N. P. 2002. Disaster dynam-
Lant, T. K. 1992. Aspiration level adaptation: An empir-
ics: Understanding the role of quantity in organiza-
ical exploration. Management Science, 38: 623–
tional collapse. Administrative Science Quarterly,
644.
47: 1–30.
Lehman, D. W., & Ramanujam, R. 2009. Selectivity in
Russo, J. E., Carlson, K. A., Meloy, M. G., & Yong, K.
organizational rule violations. Academy of Manage-
2008. The goal of consistency as a cause of informa-
ment Review, 34: 643– 657.
tion distortion. Journal of Experimental Psychol-
March, J. G. 1991. Exploration and exploitation in organ- ogy: General, 137: 456 – 470.
izational learning. Organization Science, 2: 71– 87.
Russo, J. E., & Schoemaker, P. J. H. 1989. Decision traps:
March, J. G. 2006. Rationality, foolishness, and adaptive The ten barriers to brilliant decision making and
306 Academy of Management Journal February

how to overcome them. New York: Simon & Schus- success: An empirical investigation of the findings.
ter. Journal of Marketing, 72(6): 132–146.
Schmidt, J. B., & Calantone, R. J. 1998. Are really new Van de Ven, A. H. 1986. Central problems in the man-
product development projects harder to shut down? agement of innovation. Management Science, 32:
Journal of Product Innovation Management, 15: 590 – 607.
111–123. Van de Ven, A. H. 2007. Engaged scholarship: A guide
Schmidt, J. B., & Calantone, R. J. 2002. Escalation of for organizational and social research. New York:
commitment during new product development. Oxford University Press.
Journal of the Academy of Marketing Science, 30: Van de Ven, A. H., Polley, D., Garud, R., & Venkataraman,
103–118. S. 2008. The innovation journey. New York: Oxford
Schmidt, J. B., Montoya-Weiss, M. M., & Massey, A. P. University Press.
2001. New product development decision-making Van de Ven, A. H., & Poole, M. S. 1990. Methods for
effectiveness: Comparing individuals, face-to-face studying innovation development in the Minnesota
teams, and virtual teams. Decision Sciences, 32: Innovation Research Program. Organization Sci-
575– 600. ence, 1: 313–335.
Senge, P. M. 1990. The fifth discipline: The art & prac- Voss, A., Rothermund, K., & Brandtstädter, J. 2008. Inter-
tice of the learning organization. New York: Cur- preting ambiguous stimuli: Separating perceptual
rency Doubleday. and judgmental biases. Journal of Experimental So-
cial Psychology, 44: 1048 –1056.
Sengupta, K., & Abdel-Hamid, T. K. 1993. Alternative
conceptions of feedback in dynamic decision envi- Weick, K. E., & Sutcliffe, K. M. 2006. Mindfulness and
ronments: An experimental investigation. Manage- the quality of organizational attention. Organization
ment Science, 39: 411– 428. Science, 17: 514 –526.

Sengupta, K., Abdel-Hamid, T. K., & Van Wassenhove, Whyte, G. 1998. Recasting Janis’s groupthink model: The
L. N. 2008. The experience trap. Harvard Business key role of collective efficacy in decision fiascoes.
Review, 86(2): 94 –101, 137. Organizational Behavior and Human Decision
Processes, 73: 185–209.
Sherman, J. D., & Keller, R. T. 2011. Suboptimal assessment
Zhao, B., & Olivera, F. 2006. Error reporting in organiza-
of interunit task interdependence: Modes of integra-
tions. Academy of Management Review, 31: 1012–
tion and information processing for coordination per-
1030.
formance. Organization Science, 22: 245–261.
Simester, D., & Zhang, J. 2010. Why are bad products so APPENDIX
hard to kill? Management Science, 56: 1161–1179. Derived Concepts and Codes
Staw, B. M. 1976. Knee-deep in the big muddy: A study All statements and quotations refer to the Tech-
of escalating commitment to a chosen course of ac- Car case.
tion. Organizational Behavior and Human Perfor-
mance, 16: 27– 44. Idea
Idea reflects the content (scope) of the product devel-
Staw, B. M., & Ross, J. 1978. Commitment to a policy opment project.
decision: A multitheoretical perspective. Adminis-
II ⫽ Internal: An idea from the team influencing the
trative Science Quarterly, 23: 40 – 64.
scope (e.g., “We are reviewing the task list to check if we
Sterman, J. D. 1989. Modeling managerial behavior: Mis- can increase the level of reuse”).
perceptions of feedback in a dynamic decision mak- IE ⫽ External: an idea (change request) from the customer
ing experiment. Management Science, 35: 321–339. influencing the scope (e.g., “Latest discussions with [the
lead customer] have led to potentially large changes in
Sterman, J. D. 1994. Learning in and about complex sys- the project”).
tems. Reflections, 1(3): 24 – 49.
People
Sterman, J. D. 2000. Business dynamics—Systems think- People defines the perceptions and emotions of the
ing and modeling for a complex world. Boston: team members related to the project.
Irwin McGraw-Hill. PEP ⫽ General positive emotion about the project (e.g., “I
Strauss, A., & Corbin, J. 1990. Basics of qualitative re- want to thank all of you for the excellent contribution
search—Grounded theory procedures and tech- and dedication as well as in keeping the spirit high”).
niques. Newbury Park, CA: Sage. PEN ⫽ General negative emotion about the project (e.g.,
“I am picking up some important signals regarding team
Troy, L. C., Hirunyawipada, T., & Paswan, A. K. 2008. behavior. It is always easy to look at problems and issues
Cross-functional integration and new product we have”).
2013 van Oorschot, Akkermans, Sengupta, and Van Wassenhove 307

PPTO ⫽ Optimistic perception of time (e.g., “The past OTA ⫽ Actual project delay (e.g., “Gate 1 target is no
week we have spent a lot of effort in gaining momentum longer feasible and set to . . . week 19”).
in the project. . . . The current status is positive”). OCA ⫽ Actual budget overrun (e.g., “[We] exceed the
PPTP ⫽ Pessimistic perception of time (e.g., “There is budget by €700,000”).
some delay in finalizing the software”). OOA ⫽ Actual discovery of rework or extra work (e.g.,
PPCO ⫽ Optimistic perception of costs (e.g., “The cur- “Gate 1 has been postponed by at least 3 weeks due to
rent bottom-up budget for 2008 is close to the required new investigations that have to be closed first”).
limit of €26 million”).
PPCP ⫽ Pessimistic perception of costs (e.g., “The bot-
tom-up budget indicates that we need much more budget
for 2008 than currently available”).
PPOO ⫽ Optimistic perception of output/quality (e.g.,
Kim E. van Oorschot (kim.v.oorschot@bi.no) is an asso-
“Work . . . is progressing very well”).
ciate professor of project management and system dy-
PPOP ⫽ Pessimistic perception of output/quality (e.g.,
namics at BI Norwegian Business School. She received
“Beware of unplanned interrupts!”).
her Ph.D. in industrial engineering from Eindhoven Uni-
PPRO ⫽ Optimistic perception of human resources (e.g.,
versity of Technology. Her research interests include de-
“Most probably we will be able to fill in at least four new
cision making, trade-offs, and tipping points in dynami-
key roles during [the] next week”).
cally complex settings such as new product development
PPRP ⫽ Pessimistic perception of human resources (e.g.,
(NPD) projects.
“We are experiencing growth pains”).
Transactions & Processes Henk Akkermans (ha@uvt.nl) is professor of supply net-
Transactions & processes describe the engagements work dynamics at Tilburg University. He holds a Ph.D. in
people make with others to implement ideas and to industrial engineering from Eindhoven University of
make the adaptations required to achieve desired Technology. His present research interests are in behav-
outcomes. ioral decision-making dynamics in decentralized organ-
izational networks, ranging from decision-making issues
TTG ⫽ Adaptations in team size because of a gap be-
in new service/product development via ramp-ups to
tween actual and planned team size (e.g., “We still need
maintenance/asset management.
a few key roles to be filled in”).
TW ⫽ A statement on the way of working in the team Kishore Sengupta (kishore.sengupta@insead.edu) is an
(e.g., “I am focusing the team more and more to get the associate professor of information systems at INSEAD in
correct planning process ongoing”). Fontainebleau. He received his Ph.D. in business from
TP ⫽ What priority is given to which task (e.g., “Gate 1 in Case Western Reserve University. His research examines
week 40 is top priority”). the role of managerial behaviors in the execution of com-
Context plex projects and the use of information technology at
Context reflects changes in the environment of the individual, group, and organizational levels.
project that may influence the project team.
Luk N. Van Wassenhove (luk.van-wassenhove@insead.
CI ⫽ Internal, within the team (e.g., “A survey was held edu) is professor of operations management and the
within the TechCar team”). Henry Ford Chaired Professor of Manufacturing Technol-
CC ⫽ Customer (e.g., “More potential customers are now ogy and Operations Management at INSEAD in Fon-
getting interested in our proposal”). tainebleau. He received his Ph.D. in industrial manage-
CE ⫽ External, outside the team but inside the firm (e.g., ment from the Catholic University of Leuven. His
“This week we have had a discussion on the project with research is concerned with operational excellence, sup-
senior management”). ply chain management, quality, continual improvement,
Outcomes and learning.
Outcomes capture the actual deviations from the plan
in terms of

View publication stats

You might also like