Professional Documents
Culture Documents
Providing box type waterproofing treatment to RCC raft, wall, footings, columns, beams in basement
by fixing rough shahabad stone slabs of about 25 mm thickness in C:M. 1:3 with waterproofing layer
in between shahabad stone and slab bottom/ wall surfaces well pointed with cement plaster mixed
with waterproofing compound carefully well pressed and cured. The said treatment shall be carried
out at the hands of approved waterproofing agency.
2 Labours :
Masons for laying tiles & finishing 0.15 No. 150.00 22.50
Unskilled labour 0.30 No. 80.00 24.00
4 Others
0.00 0.00 0.00
TOTAL (A)
514.73
5 Tools & Plants Charges 2.00% on total (A) 10.29
6 Water charges 0.50% on total (A) 2.57
7 Electricity Charges 0.00% on total (A) 0.00
TOTAL (B)
527.59
8 Over head & Profit 15.00% on total (B) 79.14
TOTAL 606.73
Prepared by :
Providing & laying brick bat coba of required thickness in C:M. 1:4 over the specified area including
rubbing and cleaning the base formwork if necessary giving proper slope compacting and curing etc.
complete, (in sunk portion of toilets) including providing and fixing 1" dia GI water escape pipe etc.
complete.
2 Labours :
Laying of brickbats & finishing
Mason 0.50 No. 200.00 100.00
Helper 0.50 No. 80.00 40.00
3 Others
Lift 1.00 Cum 17.75 17.75
Rate analysis
Providing and laying cement bonded waterproofing treatment using brick bats fixed in concrete 1:2:4
in required slope and finishing top with neat cement punning, marking lines at 300 mm c/c including
providing and mixing waterproofing compound ( work to be carried out at the hands of approved
nominated sub contractors) including curing, testing against watertightness
2 Labours :
Laying of brickbats & finishing
Mason 0.40 No. 200.00 80.00
Helper 0.40 No. 80.00 32.00
3 Others
Lift 0.12 Cum 17.75 2.04
TOTAL 348.88
Say Rs. 349 /- Per per sqm
Prepared by :
Rate analysis
2 Labours :
4 Others
TOTAL 327.32
Say Rs. 327 /- Per per sqm
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/1 Unit : per sqm
Providing and applying white wash to walls and ceilings , to concrete / brick /block/ stone surfaces
including preparing the surface by cleaning, including scaffolding of required type, all labour and
material complete.
2 Labours :
3 Others
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/2 Unit : per sqm
Providing and applying dry distemper of approved make, colour and shade to walls and ceilings , to
concrete / brick /block/ stone surfaces including preparing the surface by cleaning, including
scaffolding of required type, all labour and material complete.
2 Labours :
3 Others
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/3 Unit : per sqm
Providing and applying oil bound distemper of approved make,colour and shade to walls and
ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and material
complete.
2 Labours :
3 Others
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/4 Unit : per sqm
Providing and applying synthetic enamel paint of approved make,colour and shade to walls and
ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and material
complete.
Sr.No. Particulars Quantity Unit Rate per Amount
Assuming 10sqm of area
1 Materials :
a) Synthetic enamel 1.50 Kg. 141.75 212.63
b) Primer 0.85 lts. 60.90 51.77
c) Glue 80.00 Gram 0.05 3.91
d) Whitning 1.00 Kg. 20.00 20.00
e) Putty 0.20 Kg. 40.95 8.19
2 Labours :
3 Others
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/6 Unit : per sqm
Providing and applying lustre paint of approved make,colour and shade to walls and ceilings , to
concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks,
putty filling, rubbing etc including scaffolding of required type, all labour and material complete.
2 Labours :
3 Others
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/7 Unit : per sqm
Providing and applying cement paint of approved make,colour and shade to walls and wherever
required to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour and
material complete.
Sr.No. Particulars Quantity Unit Rate per Amount
Assuming 10sqm of area
1 Materials :
a) Cement paint 4.00 Kg. 49.35 197.40
b) Putty 0.15 Kg. 40.95 6.14
2 Labours :
For 10 sqm. Area , labour required
= (0.25+0.15) for first coat &
(0.2+.1) for second coat
Painter 0.45 No. 150.00 67.50
Helper 0.25 No. 80.00 20.00
Unskilled 0.20 No. 80.00 16.00
3 Others
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/8 Unit : per sqm
Providing and applying sandtex paint of approved make,colour and shade to walls and wherever
required to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour and
material complete.
Sr.No. Particulars Quantity Unit Rate per Amount
Assuming 10sqm of area
1 Materials :
a) Sandtex paint 4.50 Kg. 86.36 388.63
b) Cement paint 1.50 Kg. 49.35 74.03
c) Putty 0.20 Kg. 40.95 8.19
2 Labours :
For 10 sqm. Area , labour required
= (0.3+0.1) for first coat & (0.25+.1)
for second coat
Painter 0.65 No. 150.00 97.50
Helper 0.20 No. 80.00 16.00
Unskilled 0.20 No. 80.00 16.00
3 Others
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/9 Unit : per sqm
Providing and applying anti fungal paint of approved make,colour and shade to walls to concrete /
brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty filling,
rubbing , curing etc including scaffolding of required type, all labour and material complete.
2 Labours :
For 10 sqm. Area , labour required
= (0.3+0.1) for first coat & (0.25+.1)
for second coat
Painter 0.65 No. 150.00 97.50
Helper 0.30 No. 80.00 24.00
Unskilled 0.20 No. 80.00 16.00
3 Others
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/5 Unit : per sqm
Providing and applying plastic emulsion paint of approved make,colour and shade to walls and
ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and material
complete.
2 Labours :
3 Others
Prepared by :
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/1 Unit : per Sqm.
Providing and fixing in position AC sheet roofing with 6mm thick Trafford sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.
2 Labours :
For fixing the sheets 60.00 Sqm. 35.00 2100.00
3 Others
Nil 0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/2 Unit : per Rmt.
Providing and fixing in positional AC ridges as required including all fixing accessories complete
2 Labours :
For fixing the sheets 1.00 Rmt 25.00 25.00
3 Others
Nil 0.00 0.00 0.00
TOTAL 163.15
Say Rs. 163 /- Per per Rmt.
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/3 Unit : per Sqm.
Providing and fixing in position AC sheet roofing with 6mm thick Trafford sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For
Cladding, flashing etc.
2 Labours :
For fixing the sheets 1.00 Sqm. 42.00 42.00
3 Others
Nil 0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/4 Unit : per Rmt.
Description : Ac gutter
Providing and fixing in required slope AC gutter including fixing with MS flat brackets at 600 mm c/c
of required size, filling the joints with polysulphide sealants etc with all labour and material and
testing against watertightness. (MS bracket to be measured & paid separately)
2 Labours :
For fixing the sheets 1.00 Rmt 25.00 25.00
3 Others
Nil 0.00 0.00 0.00
TOTAL 176.15
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/5 Unit : per Sqm.
Providing and fixing in position MS precoated sheet roofing of 0.55 mm thickness of ISPAT or any
other equivalent make at all required levels including fixing with 'J' hooks, bitumen washers,etc
complete with all labour and material.
2 Labours :
For fixing the sheets 84.00 Sqm. 72.80 6115.20
3 Others
Nil 0.00 0.00 0.00
TOTAL (A) 37829.41
4 Tools & Plants Charges 2.00% on total (A) 756.59
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 189.15
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/2 Unit : per Rmt.
Providing and fixing in position MS precoated ridges as required including all fixing accessories
complete
2 Labours :
For fixing the sheets 1.00 Rmt 55.00 55.00
3 Others
Nil 0.00 0.00 0.00
TOTAL 306.19
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/3 Unit : per Sqm.
Providing and fixing in position MS precoated sheet roofing of 0.55 mm thickness of ISPAT or any
other equivalent make at all required levels including fixing with 'J' hooks, bitumen washers,etc
complete with all labour and material. For Cladding
3 Others
Nil 0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/4 Unit : per Rmt.
Providing and fixing in required slope precoated sheet gutter including fixing with MS flat brackets
at 600 mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and
material and testing against watertightness. (MS bracket to be measured & paid separately)
3 Others
Nil 0.00 0.00 0.00
TOTAL 390.33
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/5 Unit : per Sqm.
Providing and fixing in position aluminium sheet roofing with 0.6 mm thick sheets at all required
levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.
2 Labours :
For fixing the sheets 84.00 Sqm. 72.80 6115.20
4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
Prepared by :
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/10 Unit : per Rmt.
Providing and fixing in position aluminium ridges as required including all fixing accessories
complete
2 Labours :
For fixing the sheets 1.00 Rmt 55.00 55.00
4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 374.26
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/11 Unit : per Sqm.
Providing and fixing in position aluminium sheet roofing with 0.6 mm thick sheets at all required
levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.
For cladding
4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/12 Unit : per Rmt.
Providing and fixing in required slope aluminium gutter including fixing with MS flat brackets at 600
mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material
and testing against watertightness. (MS bracket to be measured & paid separately)
Providing and fixing in required slope aluminium gutter including fixing with MS flat brackets at 600
mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material
and testing against watertightness. (MS bracket to be measured & paid separately)
2 Labours :
For fixing the sheets 1.00 Rmt 90.00 90.00
4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 497.21
Prepared by :
Name : _________________________________ Sign: ________________
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/13 Unit : per Sqm.
Providing and fixing in position FRP sheet of 1.5 mm thick of Finoram or any other approved make
at all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour
and material.
2 Labours :
For fixing the sheets 84.00 Sqm. 72.80 6115.20
4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/14 Unit : per Rmt.
Providing and fixing in position FRP ridges as required including all fixing accessories complete
4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 263.96
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/15 Unit : per Sqm.
2 Labours :
For fixing the sheets 32.00 Sqm. 90.00 2880.00
4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/16 Unit : per Rmt.
Providing and fixing in required slope FRP gutter including fixing with MS flat brackets at 600 mm
c/c of required size, filling the joints with polysulphide sealants etc with all labour and material and
testing against watertightness. (MS bracket to be measured & paid separately)
2 Labours :
For fixing the sheets 1.00 Rmt 105.00 105.00
TOTAL 413.90
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/13 Unit : per Sqm.
Providing and fixing in position polycarbonate sheet roof as per detail design and drawing with
minimum thickness of sheet as 2 mm of Lexan or any other approved make including making the
joints waterproof with all labour and material and accessories to complete the work.
2 Labours :
For fixing the sheets 84.00 Sqm. 72.80 6115.20
4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
1100 1100
1014 950
0.9218181818 0.8636364
sheet width = 1.07m, length = 3.2
15*2*1.07*2.9*1.05
97.7445
(sheets in row + 1) x no. of purlins
area of sheets = 15*2*2.9*1.07 = 93.09
93.09
Purlin spacing = 1.2m
(sheets in row + 1) x no. of purlins
80 hooks
sheets required = 15*1.07*2*1.05
33.705
150.72
4.71
1.536
122.88
7.7 15.4
347908.2 160650
3080 757
73920 97.648613
2587777
2601726.8
538200
6075612
30378.06
15.4
1972.6012987
9863.0064935
Rate analysis
Providing,laying and fixing marble mosaic tiles in grey cement on C.M. 1:6 bed including filling the
joins with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute
acid, waxing etc. complete. Size of tile 25 cm x 25 cm
2 Labours :
a) for fixing & joint grouting 1.00 Sqm 32.00 32.00
b) for polishing (including 3 coats) 1.00 Sqm 20.00 20.00
4 Others
Nil 0.00 0.00 0.00
TOTAL 335.45
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/2 Unit : per sqm
Providing,laying and fixing marble mosaic tiles in grey cement on C.M. 1:6 bed including filling the
joins with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute
acid, waxing etc. complete. Size of tile 30 cm x 30cm
2 Labours :
a) For fixing & joint grouting 1.00 Sqm 32.00 32.00
b) for polishing (including 3
coats) 1.00 Sqm 20.00 20.00
4 Others
Nil 0.00 0.00 0.00
TOTAL 448.57
Prepared by :
Site: 0 Location : 0
Computer Code No. : F1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/2 Unit : per sqm
Providing & laying mosaic tile flooring of 20 to 25 mm thk. & size 25x25cm of White colour in required
positions & set in a bed of 1:6 cement mortor including neat cement float, filling the joint with
appropriate coloured cement slurry, curing, polishing etc. complete
2 Labours :
a) For fixing & joint grouting 1.00 Sqm 32.00 32.00
b) for polishing (including 3
coats) 1.00 Sqm 20.00 20.00
TOTAL 470.13
Prepared by :
Site: 0 Location : 0
Computer Code No. : F1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/2 Unit : per sqm
Providing,laying and fixing marble mosaic tiles in white cement on C.M. 1:6 bed including filling the
joins with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute
acid, waxing etc. complete. Size of tile 30 cm x 30 cm
2 Labours :
a) For fixing & joint grouting 1.00 Sqm 32.00 32.00
b) for polishing (including 3
coats) 1.00 Sqm 20.00 20.00
4 Others
Nil 0.00 0.00 0.00
TOTAL 628.02
Prepared by :
Name : _________________________________ Sign: ________________
Rate analysis
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface
including fixing with C:M 1:4 backing filling the joints with cement slurry, polishing, cleaning complete -
gray mosaic tile skirting 125 mm high
2 Labours :
a) For fixing & joint grouting 1.00 rmt 10.00 10.00
b) for polishing (including 3
coats) 1.00 rmt 9.00 9.00
TOTAL 69.94
Say Rs. 70 /- Per per rmt
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/23 Unit : per rmt
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface
including fixing with C:M 1:4 backing, polishing, cleaning, curing etc complete - gray mosaic tile
skirting 150 mm high
2 Labours :
a) For fixing & joint grouting 1.00 rmt 10.00 10.00
b) for polishing (including 3
coats) 1.00 rmt 9.00 9.00
4 Others
Nil 0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/24 Unit : per rmt
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface
including fixing with C:M 1:4 backing, filling the joints with cement slurry,polishing, cleaning curing etc
complete - white mosaic tile skirting 125 mm high
2 Labours :
a) For fixing & joint grouting 1.00 rmt 10.00 10.00
b) for polishing (including 3
coats) 1.00 rmt 9.00 9.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/25 Unit : per rmt
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface
including fixing with C:M 1:4 backing,filling the joints with cement slurry, cleaning complete - white
mosaic tile skirting 150 mm high
2 Labours :
a) For fixing & joint grouting 1.00 rmt 10.00 10.00
b) for polishing (including 3
coats) 1.00 rmt 9.00 9.00
TOTAL 106.19
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/1 Unit : per sqm
Provding and laying in position IPS flooring 50mm thick in proportion of 1:2:4 laid in proper line and
level including finishing the top surface with cement punning, curing, cleaning etc complete with all
labour and material.
2 Labours :
a) for pouring 1.00 Sqm 16.00 16.00
b) for finishing 1.00 Sqm 23.00 23.00
c) for shuttering 1.00 Sqm 10.56 10.56
TOTAL 215.23
Prepared by :
Rate analysis
Providing and laying ceramic tiles of approved quality of approved colour, size & thickness for flooring
in required position laid on a bed 30mm thk.in 1:6 cement mortor including cement float filling joints
with white/colour cement slurry cleaning curing etc. complete as shown in detailed drawing or as
directed by architect incharge.
2 Labours :
for flooring including fixing, 1.00 Sqm 75.00 75.00
cleaning & curing etc. complete 0.00 0.00 0.00
4 Others
0.00 0.00 0.00
TOTAL 692.58
Prepared by :
Rate analysis
Providing, laying and fixing in position marble slabs for flooring in plain or diamond pattern or as
required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing,
polishing, cleaning etc. complete
2 Labours :
a) for fixing & joint grouting 1.00 Sqm 100.00 100.00
b) for polishing 1.00 Sqm 129.00 129.00
TOTAL 1464.63
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/35 Unit : per Rmt.
Providing and fixing in position dado of tiles / stone as per requirement, including fixing with C:M 1:4
backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete -marble stone
2 Labours :
a) for fixing & joint grouting 1.00 Sqm 110.00 110.00
b) for polishing 1.00 Sqm 148.35 148.35
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/7 Unit : per sqm
Providing, laying and fixing in required position machine cut machine polished Kotah stone flooring of
required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including
cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.
2 Labours :
a) for fixing & polishing 1.00 Sqm 100.00 100.00
TOTAL 608.18
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/27 Unit : per Rmt.
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface
including fixing with C:M 1:4 backing, filling the joints with cement slurry, polishing, cleaning , curing
etc complete - kotah stone 100 mm height
2 Labours :
a) for fixing & polishing 1.00 Sqm 121.00 121.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/9 Unit : per sqm
Providing, laying and fixing in required position machine cut machine polished Tandur stone flooring of
required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including
cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.
2 Labours :
a) for fixing & polishing 1.00 Sqm 86.00 86.00
TOTAL 592.19
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/29 Unit : per Rmt
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface
including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning , curing etc complete
- tandur stone 100 mm height
2 Labours :
a) for fixing & polishing 1.00 Sqm 94.60 94.60
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/8 Unit : per sqm
Providing, laying and fixing in position granite stone for flooring in plain or diamond pattern or as
required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing,
polishing, cleaning etc. complete
2 Labours :
a) For fixing 1.00 Sqm 172.00 172.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/28 Unit : per Rmt.
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface
including fixing with C:M 1:4 backing, filling the joints with white cement, cleaning, curing etc complete
- granite stone / tile 100 mm height
2 Labours :
a) for fixing & polishing 1.00 Sqm 215.00 215.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/11 Unit : per sqm
Providing, laying and fixing in required position machine cut rough shahabad stone flooring of required
size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including cement
float ,filling joints with slurry curing rubbing, polishing and cleaning complete.
2 Labours :
a) For fixing 1.00 Sqm 65.00 65.00
TOTAL 287.48
Say Rs. 287 /- Per per sqm
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/10 Unit : per sqm
Providing, laying and fixing in required position machine cut machine polished shahabad stone
flooring of required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4
including cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.
2 Labours :
a) For fixing 1.00 Sqm 80.00 80.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/13 Unit : per sqm
Providing and fixing in position ceramic tile of various sizes such as 200 x 200 mm, 300 x 300 mm,
200 x 300 etc of approved make, color and shade on C:M 1:6 bedding including filling the joints with
neat cement slurry of matching colour, including cutting the tiles to required size, curing, cleaning etc
complete.
2 Labours :
a) For fixing 1.00 Sqm 75.00 75.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/13 Unit : per sqm
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface
including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc
complete - ceramic tiles of approved make and type and given height.
2 Labours :
a) For fixing 1.00 Sqm 90.00 90.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/33 Unit : per Rmt
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface
including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc
complete - ceramic tiles of approved make and type and colour 100 mm height
2 Labours :
a) For fixing 1.00 Sqm 80.00 80.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/14 Unit : per sqm
Providing and fixing in position vitrified tile flooring of approved make,size and shade on bed of
cement mortar 1:6 in required line and level, filling the joints with white cement, cleaning etc complete.
2 Labours :
a) For fixing 1.00 Sqm 80.00 80.00
4 Others
Nil 0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 30 Unit : per sqm
Providing and fixing in position vitrified tile flooring of approved make,size and shade in required line
and level, filling the joints with white cement, cleaning etc complete.
2 Labours :
a) For fixing 1.00 Sqm 96.00 96.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 30 Unit : per Rmt.
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface
including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc
complete -polished vitrified tile 100 mm height
2 Labours :
a) For fixing 1.00 Sqm 85.00 85.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/16 Unit : per sqm
Providing and fixing in position interlocking type designer tiles of approved make, colour and shade,
over bed of 1:6 mortar in proper line and level including finishing, compaction, filling joints cleaning etc
complete.
2 Labours :
a) For fixing 1.00 Sqm 60.00 60.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/17 Unit : per sqm
Providing and fixing in position interlocking type designer tiles of approved make, colour and shade,
on bed of sand in proper line and level including compaction, filling joints with sand and surface
vibrating etc complete. ( of strength M20 - 65 mm thick)
2 Labours :
a) For fixing 1.00 Sqm 30.00 30.00
TOTAL 401.79
Say Rs. 402 /- Per per sqm
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/18 Unit : per sqm
Providing and fixing in position interlocking type designer tiles of approved make, colour and shade,
on bed of sand in proper line and level including compaction, filling joints with sand and surface
vibrating etc complete. ( of strength M40 - 65 mm thick)
2 Labours :
a) For fixing 1.00 Sqm 30.00 30.00
TOTAL 580.76
Say Rs. 581 /- Per per sqm
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/19 Unit : per sqm
Providing and laying chequered tiles in required position in proper line and level, on bed of C:M 1:6
including filling the joints with neat cement slurry, cleaning, curing etc complete.
2 Labours :
a) For fixing 1.00 Sqm 60.00 60.00
TOTAL 309.69
Say Rs. 310 /- Per per sqm
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/42 Unit : per sqm
Providing and fixing in position treads and risers of stone as per requirement, including fixing with
C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing,edge polishing, curing nosing
etc complete -kotah stone
2 Labours :
a) for fixing & polishing 1.00 Sqm 400.00 400.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/40 Unit : per Rmt
Providing and fixing in position treads and risers of stone as per requirement, including fixing with
C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, edge polishing, nosing,curing
etc complete -marble stone
2 Labours :
a) for fixing & polishing 1.00 Sqm 167.70 167.70
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/41 Unit : per Rmt
Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry,cleaning,polishing,edge polishing,nosing, curing etc
complete -granite stone of approved colour
2 Labours :
a) for fixing & polishing 1.00 Sqm 223.60 223.60
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/43 Unit : per sqm
Providing and fixing in position treads and risers of stone as per requirement, including fixing with
C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing,edge polishing,nosing, curing
etc complete -tandur stone
2 Labours :
a) for fixing & polishing 1.00 Sqm 111.80 111.80
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/50 Unit : per sqm
2 Labours :
a) for fixing & polishing 1.00 Sqm 132.00 132.00
TOTAL 654.52
Prepared by :
Name : _________________________________ Sign: ________________
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/48 Unit : per sqm
2 Labours :
a) for fixing & polishing 1.00 Sqm 132.00 132.00
4 Others
Nil 0.00 0.00 0.00
TOTAL 1396.53
Prepared by :
Name : _________________________________ Sign: ________________
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/49 Unit : per sqm
2 Labours :
a) for fixing & polishing 1.00 Sqm 258.00 258.00
TOTAL 2683.01
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/51 Unit : per sqm
2 Labours :
a) for fixing & polishing 1.00 Sqm 113.52 113.52
4 Others
Nil 0.00 0.00 0.00
TOTAL 610.16
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/56 Unit : Rmt.
2 Labours :
a) for fixing of Kadappa & granite
2.25 Sqm 1506.00 3388.50
(considering labour rate @ 105/-
per rft length I.e = 105/- per 0.75
sft. Rate per sqm =
(105/.75)*10.76 = Rs. 1506
b) For moulding & edge polishing 4.42 Rmt. 246.00 1087.32
c) For Cutout making for sink
fixing 1.00 No. 400.00 400.00
3 Others
Nil 0.00 0.00 0.00
Prepared by :
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/57 Unit : Rmt.
2 Labours :
a) for fixing of Kadappa & Marble
2.25 Sqm 1147.00 2580.75
(considering labour rate @ 80/-
per rft length I.e = 80/- per 0.75
sft. Rate per sqm =
(80/.75)*10.76 = Rs. 1147
b) For edge polishing 4.57 Rmt. 196.80 900.00
c) For Cutout making for sink
fixing 1.00 No. 400.00 400.00
3 Others
Nil 0.00 0.00 0.00
Prepared by :
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/58 Unit : Rmt.
2 Labours :
a) for fixing of Kadappa 2.25 Sqm 860.00 1935.00
(considering labour rate @ 60/-
per rft length I.e = 60/- per 0.75
sft. Rate per sqm =
(60/.75)*10.76 = Rs. 717
b) For moulding & edge polishing 4.57 Rmt. 82.00 375.00
c) For Cutout making for sink
fixing 1.00 No. 250.00 250.00
3 Others
Nil 0.00 0.00 0.00
Prepared by :
Name : _________________________________ Sign: ________________
Rate analysis
Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/43 Unit : per sqm
Providing and fixing in position treads and risers of designer tiles as per requirement, including fixing
with C:M 1:4 backing, filling the joints with cement slurry, cleaning, etc complete -
2 Labours :
a) for fixing & polishing 1.00 Sqm 300.00 300.00
Providing & constructing UCR masonry II sort in cement mortar 1:6 for foundation steps, platforms
etc.below plinth including curing , weepholes if required, including specials such as corners, quions,
headers, through stones etc. dewatering if required, racking out joints 10 mm deep etc. complete.
2 Labours :
for U.C.R. masonry works 1.00 cum 250.00 250.00
4 Others
Nil 0.00 0.00 0.00
TOTAL 2003.94
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/3 Unit : per cum
Providing & constructing UCR masonry II sort in cement mortar 1:6 for foundation for compound wall,
steps, pillars , platforms etc. and wherever required including scaffolding, curing , weepholes if required,
including specials such as corners, quions, headers through stones etc. dewatering if required, racking out
joints 10 mm deep etc. complete.
2 Labours :
for U.C.R. masonry works 1.00 cum 252.00 252.00
4 Others
Scaffolding 1.00 Cum 20.00 20.00
TOTAL 2039.29
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/1 Unit : per cum
Providing & constructing general BB masonry 350 mm (13.5") or above in thickness in C.M. 1:4 in plinth
for steps, or any where as required including racking out joints 1.5 cm deep including scaffolding, curing
etc. complete.
2 Labours :
for brick masonry works 1.00 cum 164.00 164.00
4 Others
Nil 0.00 0.00 0.00
TOTAL 4557.64
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/4 Unit : per cum
Providing & constructing general BB masonry 350 mm (13.5") or above in thickness in C.M. 1:4 in
superstructure at all levels wherever required including raking out joints 1.5 cm deep including scaffolding,
curing etc. complete.
2 Labours :
for brick masonry works 1.00 cum 164.00 164.00
4 Others
Add for scaffolding & sand screening
etc. 1.00 cum 45.60 45.60
TOTAL 4663.25
Rate analysis
Providing & constructing BB masonry of 23 cm thk in 1:4 C.M for walls,etc below plinth wherever required
including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.
2 Labours :
for Brick masonry works 1.00 sqm 38.00 38.00
3 Others
Nil 0.00 0.00 0.00
TOTAL (A) 1769.50
5 Tools & Plants Charges 2.00% on total (A) 35.39
6 Water charges 0.50% on total (A) 8.85
7 Electricity Charges 0.00% on total (A) 0.00
TOTAL 2085.80
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/6 Unit : per cum
Providing & constructing BB masonry of 23 cm thk in 1:4 C.M for walls in superstructure at all levers
wherever required including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.
2 Labours :
for Brick masonry works 1.00 sqm 42.00 42.00
3 Others
Scaffolding / sand screening etc. 1.00 sqm. 9.80 9.80
TOTAL 2153.93
Prepared by :
Rate analysis
Providing & constructing 6" thk, brick masonry using 'Thoklas' bricks in C.M. 1:4, at all levels wherever
required including raking out joints, scaffolding, curing etc,. All complete.
2 Labours :
for Brick masonry works 1.00 Sqm 46.00 46.00
4 Others
Scaffolding / sand screening etc. 0.00 8.23 0.00
TOTAL 181.17
Prepared by :
Rate analysis
Providing & constructing bricks on edges or half brick masonry at all levels in 1:4 C.M. with 8 cm thick
1:2:4 p.c.c. patli using 2 Nos. of dia 6 mm at every one meter height, including scaffolding, curing, racking
out joints to receive plaster etc. complete. If length of wall exceeds4 .25 m then 4"x4.5" x ht, concrete
mullion with 10 mm diameter 4 No. reinforcement is to be provided as stiffner at every 2 meter. ( Concrete
and reinforcement will be paid in items of Columns and reinforcement respectively)
Providing & constructing bricks on edges or half brick masonry at all levels in 1:4 C.M. with 8 cm thick
1:2:4 p.c.c. patli using 2 Nos. of dia 6 mm at every one meter height, including scaffolding, curing, racking
out joints to receive plaster etc. complete. If length of wall exceeds4 .25 m then 4"x4.5" x ht, concrete
mullion with 10 mm diameter 4 No. reinforcement is to be provided as stiffner at every 2 meter. ( Concrete
and reinforcement will be paid in items of Columns and reinforcement respectively)
2 Labours :
for Brick masonry works 1.00 Sqm 41.50 41.50
4 Others
Scaffolding / sand screening etc. 1.00 Sqm. 7.70 7.70
TOTAL 139.51
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/9 Unit : per cum
2 Labours :
For coursed rubble masonary 1.00 cum 253.22 253.22
4 Others
Scaffolding & sand screening 1.00 Cum. 29.71 29.71
TOTAL 1982.76
Prepared by :
Rate analysis
Site: Location :
Computer Code No. : B5 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/11 Unit : per sqm
Providing & constructing 150 mm thick solid concrete block masonry in C.M. 1:4 including cutting if
required, curing, scafflolding, raking out joints etc. complete..
2 Labours :
for C.C.block masonry works 1.00 Sqm 8.23 8.23
4 Others
Scaffolding / sand screening etc. 1.00 Job 8.23 8.23
TOTAL 113.72
Prepared by :
Rate analysis
Site: 0 Location : Pune
Computer Code No. : B5 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/12 Unit : per sqm
Providing & constructing 200 mm thick solid concrete block masonry in C.M. 1:4 including cutting if
required, curing, scafflolding, raking out joints etc. complete..
2 Labours :
for C.C.block masonry works 1.00 Sqm 25.30 25.30
4 Others
Scaffolding / sand screening etc. 1.00 Job 8.76 8.76
0.00 0.00 0.00
TOTAL 136.75
Prepared by :
Site: Location :
Computer Code No. : B5 Default Date :
Revised on Date : 14-08-06
Item No. : 22 / Unit : per sqm
Providing 100mm thk siporex blocks of size 0.1 x 0.1 x 0.2 with c.m. 1:6,in super structure including
striking joints, taking out joints and scaffolding, curing etc. complete.
2 Labours :
for 100mm Siporex block masonry
works 1.00 Sqm 25.30 25.30
4 Others
Scaffolding / sand screening etc. 1.00 Sqm 7.70 7.70
TOTAL 1830.62
Rate analysis
Providing 150mm thk siporex blocks of size 0.15 x 0.15 x 0.3 with c.m. 1:6,in super structure including
striking joints, taking out joints and scaffolding, curing etc. complete.
2 Labours :
for 100mm Siporex block masonry
works 1.00 Sqm 28.06 28.06
4 Others
Scaffolding / sand screening etc. 1.00 Sqm 8.23 8.23
TOTAL 137.09
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B5 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 22 / III 7 Unit : per sqm
Providing 200mm thk Siporex blocks of size 0.2x0.2x0.4 with c.m. 1:6,in super structure including striking
joints, taking out joints and scaffolding, curing etc. complete.
2 Labours :
for 100mm Siporex block masonry
works 1.00 Sqm 28.06 28.06
TOTAL 140.00
Prepared by :
0.04864 0.051072
WELCOME TO RATE ANALYSIS
Enter the data in yellow cells.
For MKS system click MKS For FPS system click FPS
Providing & laying PCC 1:2:4 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.
2 Labours :
a)Mixing & Pouring 1.00 cum 120.00 120.00
b)Levelling & finishing 1.00 cum 7.50 7.50
c) Shuttering 1.00 cum 100.00 100.00
4 Others
Mixer & Vibrator 1.00 cum 25.00 25.00
TOTAL 3882.19
Rate analysis
Site: 0 Location : 0
Computer Code No. : C1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PCC/II/1 Unit : per cum
Description : P.C.C. (1 : 5 : 10 )
Providing & laying PCC 1:5:10 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.
2 Labours :
a)Mixing & Pouring 1.00 cum 120.00 120.00
b)Levelling & finishing 1.00 cum 7.50 7.50
c) Shuttering 1.00 cum 100.00 100.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
TOTAL 2913.26
Prepared by :
Rate analysis
Description : P.C.C. (1 : 4: 8 )
Providing & laying PCC 1:4:8 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.
2 Labours :
for
a)Mixing & Pouring 1.00 cum 120.00 120.00
b)Levelling & finishing 1.00 cum 7.50 7.50
c) Shuttering 1.00 cum 100.00 100.00
TOTAL 3120.03
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PCC/II/6 Unit : per cum
Providing and laying plum concrete of 1:4:8 mix using stone of size not more than 230 mm in size and
proportion of plum to concrete @ 35:65 including curing, formwork if required, etc complete.
2 Labours :
for
a)Mixing & Pouring 1.00 cum 275.00 275.00
b)Levelling & finishing 1.00 cum 7.50 7.50
c) Shuttering 1.00 cum 100.00 100.00
3 Centering & Shuttering
Providing good Specified material/ 1.00 cum 80.00 80.00
erection & dismantling
4
Others
Mixer & Vibrator 1.00 cum 24.75 24.75
TOTAL 2605.75
Prepared by :
Rate analysis
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Footings, pedastals, raft,pilecaps.
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
TOTAL 3889.72
Prepared by :
Rate analysis
Site: Location :
Computer Code No. : C6 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/2 Unit : per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Columns upto plinth
mild steel/tor steel reinforcement) .---For Columns upto plinth
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 144.00 144.00
b)Levelling & finishing 1.00 cum 0.00 0.00
c) Shuttering 1.00 cum 287.50 287.50
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
TOTAL 5389.36
Prepared by :
Rate analysis
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Columns at all levels
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 176.00 176.00
b)Levelling & finishing 1.00 cum 0.00 0.00
c) Shuttering 1.00 cum 120.00 120.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
TOTAL 5489.45
Prepared by :
Rate analysis
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Floor beams
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 176.00 176.00
b) Levelling & finishing 1.00 cum 15.00 15.00
c) Shuttering 1.00 cum 125.00 125.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 5477.60
Prepared by :
Name : _________________________________ Sign: ________________
Rate analysis
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Floor slabs
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 160.00 160.00
b)Levelling & finishing 1.00 cum 15.00 15.00
c) Shuttering 1.00 cum 150.00 150.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
Prepared by :
Rate analysis
Providing & casting M 200 for RCC staircase upto 17 cm riser 30 cm tread & 20 cm th waist slab but
excluding parapet as per detailed drawing & design at all levels with all leads & lift or as directed
including formwork, centering, scaffolding, machine mixing, & mixing , laying, levelling, vibrating and
finishing rough and broken surfaces with C.M. 1:2 including curing etc. complete (excluding steel
reinforcement)
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 190.00 190.00
b)Levelling & finishing 1.00 cum 17.50 17.50
c) Shuttering 1.00 cum 150.00 150.00
0.00 0.00 0.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 5461.91
Prepared by :
Rate analysis
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For pardis,parapets and fins
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 225.00 225.00
b)Levelling & finishing 1.00 cum 7.50 7.50
c) Shuttering 1.00 cum 120.00 120.00
0.00 0.00 0.00
0.00 0 0.00 0.00
3 Centering & Shuttering 0.00 0.00 0.00
Providing good Specified material/ 1.00 cum 1520.00 1520.00
Fixing & removing
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lifts 1.00 cum 17.75 17.75
TOTAL 6335.48
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/4 Unit : per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Plinth beams
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 176.00 176.00
b)Levelling & finishing 1.00 cum 10.50 10.50
c) Shuttering 1.00 cum 359.38 359.38
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
TOTAL 5441.92
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : Dec 31, 99
Item No. : FDAPL/RCC/III/7&16 Unit : per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For lintels & chajja
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 240.00 240.00
b)Levelling & finishing 1.00 cum 10.50 10.50
c) Shuttering 1.00 cum 575.00 575.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 6085.55
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/6 Unit : per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Grid beams
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Grid beams
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 240.00 240.00
b)Levelling & finishing 1.00 cum 10.50 10.50
c) Shuttering 1.00 cum 575.00 575.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 6497.75
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/8 Unit : per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For lift & Basement walls
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 176.00 176.00
b)Levelling & finishing 1.00 cum 0.00 0.00
c) Shuttering 1.00 cum 460.00 460.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 5600.49
Prepared by :
Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/15 Unit : per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For folded staircase slabs
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 240.00 240.00
b)Levelling & finishing 1.00 cum 37.50 37.50
c) Shuttering 1.00 cum 931.50 931.50
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 6809.87
Say Rs. 6,810 /- Per per cum
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/28 Unit : Rmt.
Providing & fixing in corrent position.line, level 40 mm dia Finolex or equivalent PVC pipe in RCC
members such as columns, beams, slabs, paradi, chajjas etc. including fixing / typing with binding wire
& M.S. rod to secure in position during concrete including all lifts etc. complete.
2 Labours :
a) Cutting & fixing sleeves 1.00 Rmt. 55.90 55.90
0.00 0.00 0.00
TOTAL 138.00
Say Rs. 138 /- Per Rmt.
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/12 Unit : per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For sloping slabs
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 200.00 200.00
b)Levelling & finishing 1.00 cum 19.50 19.50
c) Shuttering 1.00 cum 412.97 412.97
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 5485.56
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/11 Unit : per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For cantilever slabs
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 160.00 160.00
b)Levelling & finishing 1.00 cum 10.50 10.50
c) Shuttering 1.00 cum 363.29 363.29
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL (A) 4742.44
5 Tools & Plants Charges 2.00% on total (A) 94.85
6 Water charges 0.50% on total (A) 23.71
7 Electricity Charges 0.50% on total (A) 23.71
TOTAL 5617.41
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/19 Unit : per cum
Providing and laying in situ C.C. M-20 of trap metal for R.C.C.work of Copings & sills as per
detailed drawings and design or as directed including centering formwork, compacting using vibrator,
curing and roughening the surface if special finish is to be provided etc. complete. (excluding
reinforcement & fitter work).
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 212.80 212.80
b)Levelling & finishing 1.00 cum 66.00 66.00
c) Shuttering 1.00 cum 621.00 621.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 6438.88
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/29 Unit : Rmt.
Welding the reinforcement bars to existing steel or as per the requirement including finishing the
welding work neatly, all labour and material etc complete.
2 Labours :
a)Welder 0.03 No. 150.00 4.50
b)Helper 0.03 No. 100.00 3.00
One welder can do about 30rmt. Of
welding
3 Scaffolding
If required for welding at heights
15.49 Sft. 0.75 11.62
Assuming the area of scaffolding to be
1.2m x1.2m
4 Others
Hire charges of welding machine 0.25 Hr. 31.25 7.81
Assuming the hire charges rate of
250 /-for 8 hrs.
TOTAL 49.76
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/30 Unit : per sqm
Providing & fixing shalitex board expansion joint of 25mm thickness for beams, columns & slab
2 Labours :
a)carpenter 0.37 No. 150.00 55.50
b)Helper 0.37 No. 100.00 37.00
One pair of carp/helper can do about 2
columns as given below.
Assuming the size of column to be
450x230 & joint on 450mm face, Ht. Of
col.of about 3m. Area = 3 x 0.45 =
1.35 sqm.
4 Others
TOTAL 1099.18
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : C10 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/9 Unit : per cum
2 Labours :
a) Mixing & Pouring (Concreting) 0.07 cum 212.00 14.84
b)Levelling & finishing 0.07 cum 66.00 4.62
c) Shuttering 0.07 cum 621.00 43.47
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 253.01
Rate analysis
Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/8 Unit : per cum
Providing & laying M 50 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
Providing & laying M 50 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For lift & Basement walls
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 185.00 185.00
b)Levelling & finishing 1.00 cum 0.00 0.00
c) Shuttering 1.00 cum 486.00 486.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 5605.01
Prepared by :
Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/8 Unit : per cum
Providing & laying M 30 (as per design mix) for Road work using machine crushed metal of approved
quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering
formwork, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with
1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---
2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 185.00 185.00
b)Levelling & finishing 1.00 cum 0.00 0.00
c) Shuttering 1.00 cum 150.00 150.00
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75
TOTAL 4281.86
Rate analysis
Site: 0 Location : 0
Computer Code No. : C4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/2 Unit : per cum
Providing & laying M 300 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Footings, pedastals, raft,pilecaps.
2 Labours :
a) Mixing & Pouring (concreting) 1.00 cum 107.20 107.20
b)Levelling & finishing 1.00 cum 16.50 16.50
c) Shuttering 1.00 cum 86.25 86.25
4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Prepared by :
24.75 17.775
Assign 0.3 hrs
176
15
480.13
992.25
1165.5
254.25
270
100
160
15
310.5
682.5
24.75
17.75
3000.25
150.01
30.0025
30.0025
3210.27
481.54013
3691.81
0.7627911
18.75
12.5
Rate analysis
Site: 0 Location : Pune
Computer Code No. : Default Date : Dec 30, 99
Revised on Date
Item No. : Unit :
Description :
TOTAL 0.00
Prepared by :
35.32
1.71 153.9
156
Excavation upto 1.5 M depth in ordinary soil or soft murum, old foundations etc. in pits, over areas and
in trenches by machinery or otherwise including removing the excavated materials upto a distance of
100 M beyond building premises, stacking as directed dewatering manually or mechanically if required,
shoring, strutting, preparing the bed for foundation and necessary back filling in layers including dry and
wet compaction etc. complete.
2 Labours :
a) Unskilled coolie for excn. 0.56 No 100.00 56.00
b) Labour for backfilling 0.08 No 100.00 8.00
Assuming that one pair
to do excavation of 125 cft.
4 Others
Shoring 1.00 L/S 10.00 10.00
Dewatering 1.00 L/s 2.00 2.00
TOTAL 90.02
Say Rs. 90 /- Per per cum
Prepared by :
Rate analysis
Excavation upto 1.5 M depth in hard murum & boulders etc. in pits, over areas and in trenches by
machinery or otherwise including removing the excavated materials upto a distance of 100 M beyond
building premises, stacking as directed dewatering manually or mechanically if required, shoring,
strutting, preparing the bed for foundation and necessary back filling in layers including dry and wet
compaction etc. complete.
NIL
2 Labours :
a) Unskilled coolie (Male) 0.70 No 100.00 70.00
( It is assumed that 1 m/c + 1 f/c
can excavate nearly 100cft of mu-
rum in a day with specified lead
and lift)
c) Add for backfilling & compaction 0.08 No 100.00 8.00
NIL
4 Others
Shoring 1.00 L/S 10.00 10.00
Dewatering 1.00 L/s 2.00 2.00
TOTAL (A) 90.00
5 Tools & Plants Charges 2.00% on total (A) 1.80
6 Water charges 0.50% on total (A) 0.45
7 Electricity Charges 0.50% on total (A) 0.45
TOTAL 106.61
Prepared by :
Rate analysis
Site: 0 Location : Pune
Computer Code No. : E4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/5 Unit : per cum
Excavation upto 1.5 M depth in soft rock in pits and trenches by machinery or otherwise including
removing the excavated materials upto a distance of 100 M beyond building premises,stacking as
directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for
foundation and necessary back filling in layers including dry and wet compaction etc. complete.
4 Others
Dewatering 1.00 L/s 2.00 2.00
TOTAL 289.25
Prepared by :
Rate analysis
Site: 0 Location : Pune
Computer Code No. : E5 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/8 Unit : per cum
2 Labours :
a)1 Breaker Needle with operator 0.54 Per day 1000.00 540.00
( It is assumed that with a break-
er needle in a day we can excav-
-ate nearly 65cft (1.84cum.)
with lead & lift as specified.)
i.e. For 1 cum. It requires
0.54 days of breaker
4 Others
Dewatering 1.00 L/s 2.00 2.00
TOTAL 777.03
Say Rs. 777 /- Per per cum
Prepared by :
Name : ________________________________ Sign : _______________
Rate analysis
Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/15 Unit : per Sqm
Providing and laying 230 mm thick dry trap rubble soling in plinth including filling the interstices with
murum and stone chips, watering,compacting, ramming etc complete with all labour and material.
2 Labours :
a) Unskilled coolie (Male) 0.05 No 100.00 5.40
b) Unskilled coolie (Female) 0.05 No 100.00 5.40
Assuming that one pair
to do 200 sft. (18.59 sqm.)Of soling
area
4 Others
NIL 0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 215.93
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/12 Unit : per Cum
Providing & filling in plinth selected murrum obtained from excavation including spreading, levelling,
watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for
payment)
Providing & filling in plinth selected murrum obtained from excavation including spreading, levelling,
watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for
payment)
2 Labours :
a) Unskilled coolie (Male) 0.35 No 100.00 35.00
Assuming that one male coolie
to do100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours 0.09 No 100.00 9.00
Net labour required = (2 / 2.83)/8
TOTAL 63.96
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/13 Unit : per Cum
Providing & filling in plinth murrum brought from outside including spreading, levelling, watering, and
ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)
2 Labours :
a) Unskilled coolie (Male) 0.35 No 100.00 35.00
Assuming that one male coolie
to do100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours 0.09 No 100.00 9.00
Net labour required = (2 / 2.83)/8
TOTAL 1757.80
Prepared by :
Name : _________________________________ Sign: ________________
Rate analysis
Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 1 Unit : per Cum
Providing & filling in plinth with approved sand including spreading, levelling, watering, and ramming (in
layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)
2 Labours :
a) Unskilled coolie (Male) 0.35 No 100.00 35.00
Assuming that one male coolie
to do 100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours 0.09 No 100.00 9.00
Net labour required = (2 / 2.83)/8
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/16 Unit : per Sqm
Providing & applying preconstructional anti termite treatment to bottom and sides of excavated surfaces
by approved agency (MODE of Measurement will be on plinth area basis.)
2 Labours :
TOTAL 42.85
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/17 Unit : Cum
Carting away the unwanted excavated,/ demolished material outside the premises and unloading and
spreading it as and where required as per the rules of local authority including loading, unloading,
carting, spreading etc complete.
2 Labours :
a) Unskilled coolie 2 nos. do filling of
tractor (100cft) in 15 minutes 0.18 No 100.00 18.00
Net labour required = (0.5 / 2.83)
NIL
TOTAL 68.03
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : E5 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/11 Unit : per cum
2 Labours :
4 Others
Compressor for drilling holes 0.50 120 120.00 60.00
TOTAL 353.66
Say Rs. 354 /- Per per cum
Prepared by :
Name : ________________________________ Sign : _______________
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MISC/XI/2 Unit : per Sqm.
Providing, fabricating & erecting & fixing, cutting, bending, grinding, welding the structural steel
work consisting of m.s. plates I beams channels, angles, chequered plates, including fabricating as
per shop drawing including erection to required line and level and providing and fixing buts, bolts
and required appropriate washers etc. complete including painting
2 Labours :
For fabrication & errection 1.00 Mt. 2250.00 2250.00
For painting 1.00 Mt. 450.00 450.00
4 Others
Welding M/C 1.00 Day 250.00 250.00
TOTAL 43578.09
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MISC/XI/3 Unit : per No.
Providing & fixing and securing in position box type fan hooks of 12 mm diameter MS rods 30 cm
long as directed
2 Labours :
For preparing the hook & fixing in
place
Fitter (0.5 hrs.) 0.06 No. 150.00 9.38
Helper (0.5hrs.) 0.06 No. 100.00 6.25
3 Others
TOTAL (A) 26.93
4 Tools & Plants Charges 2.00% on total (A) 0.54
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 0.13
TOTAL 31.75
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MISC/XI/5 Unit : per Sqm.
Providing and erecting in position chain link fencing of GI 18 gauge, 50 mm opening size as
required including fixing the angle supports in bed blocks of C:M 1:3:6 at 2.4 m c/c, ms 6 mm dia at
top, U nails for fixing, etc complete with all labour and material. - 1.2 m high fencing ( Structural
steel for angles,flats will be paid separately)
2 Labours :
For excavation 11 Nos. 5 55.00
For poles errecting (0.5 mason & 0.50 No. 150.00 75.00
0.5 helpers) 0.50 No. 100.00 50.00
For fixing chain link 0.50 No. 150.00 75.00
(.5 mason & 1 helpers) 1.00 No. 100.00 100.00
3 Others
Prepared by :
12.4
33
STANDARD ITEMS OF BOQ
CODE NO BRIEF DESCRIPTION OF ITEMS UNIT
SNJ/EX/ 1 Excavation in soil and soft murum upto 1.5m depth Cum
SNJ/EX/I 2 Excavation in soil and soft murum from 1.51 m to 3.0m depth Cum
SNJ/EX/I 3 Excavation in hard murum and boulders upto 1.5 m depth Cum
SNJ/EX/I 4 Excavation in hard murum and boulders from 1.51 to 3.0 m depth Cum
SNJ/EX/I 5 Excavation in soft rock upto 1.5 m depth Cum
SNJ/EX/I 6 Excavation in soft rock from 1.51 to 3.0 m depth Cum
SNJ/EX/I 7 Excavation in soft rock from 3.1 m to 6.0 m depth Cum
SNJ/EX/I 8 Excavation in hard rock upto 1.5m depth ( by chiselling) Cum
SNJ/EX/I 9 Excavation in hard rock from 1.51m to 3m depth ( by chiselling) Cum
SNJ/EX/I 10 Excavation in hard rock from 3.1m to 6.0m( by Chiselling) Cum
SNJ/EX/I 11 Excavation in hard rock by blasting Cum
SNJ/EX/I 12 Filling in plinth with selected murum obtained from excavation Cum
SNJ/EX/I 13 Filling in plinth with murum brought from outside ( labour+material) Cum
SNJ/EX/I 14 Filling in plinth sand Cum
SNJ/EX/I 15 230 mm thick dry rubble soling in plinth Sqm
SNJ/EX/I 16 Providing preconstructional antitermite treatment to plinth Sqm
SNJ/EX/I 17 Carting away unwanted excavated material outside the premises Cum
SNJ/RCC/III 1 Providing and casting RCC M20 for footings, foundations, combined Cum
footings, eccentric footings, raft, pedastals,pile caps
SNJ/RCC/III 2 Providing and casting RCC M20 for columns ( of any size and Cum
shpe)upto plinth and in basement
SNJ/RCC/III 3 Providing and casting RCC M20 for columns ( fo any size and shape) in Cum
superstructure at all levels
SNJ/RCC/III 4 Providing and casting RCC M20 for plinth beams Cum
SNJ/RCC/III 5 Providing and casting RCC M20 for beams ( of any shape and size) at Cum
all levels
SNJ/RCC/III 6 Providing and casting RCC M20 for beams in grid system Cum
SNJ/RCC/III 7 Providing and casting RCC M20 for lintels Cum
SNJ/RCC/III 8 Providing and casting RCC M20 for piles
SNJ/RCC/III 9 Providing and casting RCC M20 for standard slab(thk upto 200 mm) Cum
SNJ/RCC/III 10 Providing and casting RCC M20 slab for loft Cum
SNJ/RCC/III 11 Providing and casting RCC M20 for cantilever slab upto 2.0 m span Cum
SNJ/RCC/III 12 Providing and casting RCC M20 for sloping slab Cum
SNJ/RCC/III 13 Providing and casting RCC M20 for pyramidal slab Cum
SNJ/RCC/III 14 Providing and casting RCC M20 for hordi slab Cum
SNJ/RCC/III 15 Providing and casting RCC M20 for folded slab upto thickness of Cum
150mm
SNJ/RCC/III 16 Providing and casting RCC M20 for chajjas at any level , of projection Cum
upto 0.75m
SNJ/RCC/III 17 Providing and casting RCC M20 for pardies, parapets, fins, upstands of Cum
thickness upto 100 mm
SNJ/RCC/III 18 Providing and casting RCC M20 for staircase steps and waist slab with Cum
riser upto 170 mm and tread upto 300 mm and waist slab thickness
upto 200 mm.at all levels.
SNJ/RCC/III 19 Providing and constructing RCC M20 for coping at all levels Cum
SNJ/RCC/III 20 Providing and constructing RCC M20 for sills at all levels Cum
SNJ/RCC/III 21 Providing and constructing RCC walls in M20 Cum
SNJ/RCC/III 22 Providing and constructing RCC M20 floor Cum
SNJ/RCC/III 23 Extra for addition or deduction in thickness of the structural members as
mentioned above , excluding form work
SNJ/RCC/III 24 Less for providing concrete of grade M15 in lieu of M20 Cum
SNJ/RCC/III 25 Extra for providing concrete of grade M25 in lieu of M20 Cum
SNJ/RCC/III 26 Extra for providing concrete of grade M30 in lieu of M20 Cum
SNJ/RCC/III 27 Extra for providing concrete of grade M35 in lieu of M20 Cum
SNJ/RCC/III 28 Extra for providing concrete of grade M40 in lieu of M20 Cum
SNJ/RCC/III 29 Providing, cutting, bending, laying reinfocement of mild steel, tor steel of MT
various diameters including binding wire
SNJ/RCC/III 30 Welding of bars to existing reinforcement RM
SNJ/RCC/III 31 Expansion joint for columns RM
SNJ/RCC/III 32 Expansion joint for beams RM
SNJ/RCC/III 33 Expansion joint for slab RM
SNJ/RCC/III 34 Providing post tensioning of beams and slab Sqm
SNJ/RCC/III 35 Providing anticorrosive treatment to reinforcement MT
SNJ/PLAST/V 1 Providing and applying 12 mm thick internal cement plaster C:M 1:4 Sqm
SNJ/PLAST/V 2 Providing and applying 20 mm thick sandface cement plaster C:M 1:5 in Sqm
one coat
SNJ/PLAST/V 3 Providing and applying 12mm back coat plaster behind dado C:M 1:4 Sqm
SNJ/PLAST/V 4 Providing and applying 20 mm thick sand faced cement plaster in two Sqm
coats first coat with 1:5 & second with 1:4
SNJ/PLAST/V 5 Provding and applying 25 mm thick plaster to toilet sunks and sides, Sqm
internally to water tanks with waterproofing compound
SNJ/PLAST/V 6 Providing and applying 20 mm thick rough cast plaster Sqm
SNJ/PLAST/V 7 Providing and applying pebble dash plaster Sqm
SNJ/PLAST/V 8 Providing and applying special finish RENOVO or other such plasters Sqm
SNJ/PLAST/V 9 Providing and making flush groove pointing to brick/block masonry Sqm
SNJ/PLAST/V 10 Providing and making flush groove pointing to stone masonry Sqm
SNJ/PLAST/V 11 Providing and making sunk pointing to stone masonry Sqm
SNJ/FLOOR/VI 1 Providing and laying IPS floor 50 mm thick with ghotai Sqm
SNJ/FLOOR/VI 2 Providing and laying marble mosaic tile flooring 25cmx25cm size - grey Sqm
cement based
SNJ/FLOOR/VI 3 Providing and laying marble mosaic tile flooring 30cmx30cm size - grey Sqm
cement based
SNJ/FLOOR/VI 4 Providing and laying marble mosaic tile flooring 25cmx25cm size - white Sqm
cement based
SNJ/FLOOR/VI 5 Providing and laying marble mosaic tile flooring 30cmx30cm size - white Sqm
cement based
SNJ/FLOOR/VI 6 Providing and laying marble stone flooring Sqm
SNJ/FLOOR/VI 7 Providing and laying Kotah stone flooring Sqm
SNJ/FLOOR/VI 8 Providing and laying granite stone flooring Sqm
SNJ/FLOOR/VI 9 Providing and laying tandur stone flooring Sqm
SNJ/FLOOR/VI 10 Providing and laying polished shahabad flooring Sqm
SNJ/FLOOR/VI 11 Providing and laying rough shahabad flooring Sqm
SNJ/FLOOR/VI 12 Providing and laying Jaisalmer stone flooring Sqm
SNJ/FLOOR/VI 13 Providing and laying ceramic tile flooring Sqm
SNJ/FLOOR/VI 14 Providing and laying vitrified tile flooring Sqm
SNJ/FLOOR/VI 15 Providing and laying rough vitrified tile flooring Sqm
SNJ/FLOOR/VI 16 Providing and laying designer tiles - interlocking type Sqm
SNJ/FLOOR/VI 17 Provding and laying interlocking paving blocks Sqm
SNJ/FLOOR/VI 18 Provding and laying chequered tiles Sqm
SNJ/FLOOR/VI 19 Providing and laying marble mosaic tile skirting 125mm size - grey Sqm
cement based
SNJ/FLOOR/VI 20 Providing and laying marble mosaic tile skirting 150 mm size - grey Sqm
cement based
SNJ/FLOOR/VI 21 Providing and laying marble mosaic tile skirting 125mm size - white Sqm
cement based
SNJ/FLOOR/VI 22 Providing and laying marble mosaic tile skirting 150 mm size - white Sqm
cement based
SNJ/FLOOR/VI 23 Providing and laying marble stone skirting Sqm
SNJ/FLOOR/VI 24 Providing and laying Kotah stone skirting Sqm
SNJ/FLOOR/VI 25 Providing and laying granite stone skirting Sqm
SNJ/FLOOR/VI 26 Providing and laying tandur stone skirting Sqm
SNJ/FLOOR/VI 27 Providing and laying polished shahabad skirting Sqm
SNJ/FLOOR/VI 28 Providing and laying rough shahabad skirting Sqm
SNJ/FLOOR/VI 29 Providing and laying Jaisalmer stone skirting Sqm
SNJ/FLOOR/VI 30 Providing and laying ceramic tile skirting Sqm
SNJ/FLOOR/VI 31 Providing and laying vitrified tile skirting Sqm
SNJ/FLOOR/VI 32 Providing and laying rough vitrified tile skirting Sqm
SNJ/FLOOR/VI 33 Providing and laying ceramic tile dado Sqm
SNJ/FLOOR/VI 34 Providing and laying marble stone dado Sqm
SNJ/FLOOR/VI 35 Providing and laying Kotah stone dado Sqm
SNJ/FLOOR/VI 36 Providing and laying granite stone dado Sqm
SNJ/FLOOR/VI 37 Providing and laying tandur stone dado Sqm
SNJ/FLOOR/VI 38 Providing and laying marble stone for treads and risers Sqm
SNJ/FLOOR/VI 39 Providing and laying Kotah stone for treads and risers Sqm
SNJ/FLOOR/VI 40 Providing and laying granite stone for treads and risers Sqm
SNJ/FLOOR/VI 41 Providing and laying tandur stone for treadsand risers Sqm
SNJ/FLOOR/VI 42 Providing and laying Jaisalmer stone for treads and risers Sqm
SNJ/FLOOR/VI 43 Providing marble for window sills and jambs Sqm
SNJ/FLOOR/VI 44 Provding kotah stone for window sills and jambs Sqm
SNJ/FLOOR/VI 45 Providing granite stone for window sills and jambs Sqm
SNJ/FLOOR/VI 46 Providing tandur stone for window sills and jambs Sqm
SNJ/FLOOR/VI 47 Providing, making and erecting in position kitchen platform with RM
following specifications. Width of platform 2'3" and height 32" top
a. Kadappa slab 40 mm thick as base to granite stone slab.
b. Granite stone slab 20 mm thick with polishing,
c. Making hole for single bowl stainless steel sink with edge polishing
to cut surface of stones
d. One shelf of granite below platform
e. 2 no of vertical supports of kadappa stone with both side polish and
edge polish
f. 4" height granite fascia with edge polish
12 As per item no11 above but for door size 900 x 2100 mm RM
17 As per item no 16 above but for door size of 900 x 2100 mm Sq.M
18 As per item no 16 above but for door size of 1000 x 2100 mm Sq.M
19 As per item no 16 above but for double shutter door of size 1200 x 2100
Sq.M
20 As per item no 16 above but for double shutter door of size 1500 x 2100
Sq.M
22 Providing and fixing following MS powder coated fittings and fixtures for
doors
a. Aldrop 250 mm size No
b. Tadipatti No
c. Tower bolts No
d. PVC gattu No
e. Door stopper No
f. D type handles No
23 Providing and fixing following Aluminium fittings and fixtures for doors
26 Providing and fixing night latch of approved brand to door with all
hardware and accessories required No
28 Providing and fixing peep hole / eye piece of approved make to doors
including all labour and material complete
SNJ/WP/VIII 1 Waterproofing of terrace with brick bat coba upto 115 mm thk Sqm
SNJ/WP/VIII 2 Waterproofing of toilet sunks with brick bat coba filling Cum
SNJ/WP/VIII 3 Box type waterproofing for basement walls and wherever required Sqm
SNJ/WP/VIII 4 Chemical waterproofing to terrace and toilet sunks Sqm
SECTION IX - PAINTING
SNJ/MISC/XI 1 Structural steel fabrication and erection wherever required for trusses, MT
stanchions, and such other industrial activities.
SNJ/MISC/XI 2 Box type fan hooks No
SNJ/MISC/XI 3 Anchor fasteners No
SNJ/MISC/XI 4 Fabrication and erection of steel required for railings of balconies, Kg
staircases, terraces etc with painting
SNJ/MISC/XI 5 ACP sheet cladding Sqm
SNJ/MISC/XI 6 Chain link fencing 4' height Sqm
SNJ/MISC/XI 7 Chain link fencing 8' height Sqm
SNJ/MISC/XI 8 Barbed wire fencing Sqm
Rate
90.02
99.02
106.61
117.27
289.25
318.18
350.00
777.03
854.74
940.21
353.66
63.96
1757.80
1272.15
215.93
42.85
68.03
2913.26
3120.03
3882.19
2605.75
3889.72
5389.36
5489.45
5441.92
5477.60
6497.75
6085.55
4839.87
6085.55
5617.41
5485.56
6809.87
6085.55
6335.48
5461.91
6438.88
6438.88
5600.49
331.88
45499.46
49.76
1099.18
1099.18
1099.18
4557.64
2003.94
2039.29
4663.25
2085.80
2153.93
139.51
181.17
1982.76
113.72
136.75
1830.62
137.09
140.00
112.60
137.56
94.45
167.93
269.61
64.14
92.11
90.07
215.23
335.45
448.57
470.13
628.02
1464.63
608.18
2440.25
592.19
359.97
287.48
676.53
1189.24
1189.24
709.42
401.79
309.69
559.56
540.92
700.28
707.94
153.90
68.99
268.77
63.26
71.27
1226.08
1226.08
726.22
162.80
895.36
306.89
73.13
1396.53
654.52
2683.01
610.16
5005.70
3388.69
1800.70
1263.39
580.76
468.35
934.58
579.59
1097.63
1138.66
1284.05
432.01
1018.76
797.86
1274.64
348.88
2599.14
606.73
348.88
4.71
19.39
35.59
46.26
71.68
66.92
36.19
70.77
91.34
1.73
136.42
330.40
Rate analysis
2 Labours :
Carpenter for frame making 0.68 Nos. 200.00 136.00
Helper for frame making 0.27 Nos. 100.00 27.20
(0.5 carp + 0.2 help are required per
cft of frame making) 0.00
Mason for fixing of frame 0.50 Nos. 150.00 75.00
Unskilled labour 0.20 Nos. 80.00 16.00
3 Others
Nil 0.00 0.00 0.00
Prepared by :
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/1 Unit : Rmt.
2 Labours :
Labour rate for cutting, fixing &
moulding of frame 1.77 Sqm. 516.00 913.32
3 Others
Nil 0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/3 Unit : Rmt.
As per item no 01 but with marble door frame of size 170 mm x 20 mm and extra patti for rebate
formation for 35 mm thick shutter. Door size 900x 2100 mm
2 Labours :
Labour rate for cutting, fixing &
moulding of frame 1.77 Sqm. 396.00 700.92
3 Others
Nil 0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/4 Unit : Sqmt.
Description : P/F flush shutter 35mm
Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping
patti, both faces finished with commercial teak ply, including fixing with 4 no of hinges, required
screws etc complete. - single shutter - size of door - 750 x 2100 mm
2 Labours :
Carpenter for fixing shutter 0.20 Nos. 200.00 40.00
Helper for fixing shutter 0.10 Nos. 100.00 10.00
(0.2 carp + 0.2 help are required per
cft of frame making)
4 Others
Nil 0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Sqmt.
Labours :
2 Carpenter for fixing shutter 0.20 Nos. 200.00 40.00
Helper for fixing shutter 0.10 Nos. 100.00 10.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/5 Unit : Sqmt.
2 Labours :
Carpenter for fixing shutter 0.50 Nos. 200.00 100.00
Helper for fixing shutter 0.50 Nos. 100.00 50.00
(0.2 carp + 0.2 help are required per
cft of frame making)
3 Others
Nil 0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/6 Unit : Sqmt.
Providing and fixing laminate of approved colour and shade to doors including all labour and material
Providing and fixing laminate of approved colour and shade to doors including all labour and material
2 Labours :
Carpenter for fixing & polishing of
laminates 0.07 Nos. 200.00 14.00
Helper 0.20 Nos. 100.00 20.00
3 Others
Nil 0.00 0.00 0.00
TOTAL 432.01
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.
Providing and fixing following MS powder coated fittings and fixtures for doors, including Aldrop
250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
Providing and fixing following MS powder coated fittings and fixtures for doors, including Aldrop
250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
2 Labours :
Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.75 Nos. 100.00 75.00
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)
4 Others
Nil 0.00 0.00 0.00
TOTAL 135.56
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.
Providing and fixing following Alluminium fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
Providing and fixing following Alluminium fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
Labours :
2 Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.75 Nos. 100.00 75.00
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)
Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 268.17
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.
Providing and fixing following stainless steel fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
Labours :
2 Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.75 Nos. 100.00 75.00
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)
Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
TOTAL (A) 227.50
5 Tools & Plants Charges 2.00% on total (A) 4.55
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 1.14
TOTAL 268.17
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.
Providing and fixing following Brass fittings and fixtures for doors, including Aldrop 250mm, tadipatti,
towerbolts, PVC gattu, door stopper, D type handle.
Labours :
2 Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.75 Nos. 100.00 75.00
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)
Centering & Shuttering
3 Nil
Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 268.17
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.
Providing and fixing night latch of approved brand to door with all hardware and accessories required
Labours :
2 Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.20 Nos. 100.00 20.00
(0.2 carp + 0.2 help are required for
fixing the latch for one door)
Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 70.73
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.
Providing and fixing in position automatic door closure of approved make including all labour and
material complete.
Providing and fixing in position automatic door closure of approved make including all labour and
material complete.
Labours :
2 Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.20 Nos. 100.00 20.00
(0.2 carp + 0.2 help are required for
fixing )
Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 70.73
Prepared by :
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.
Providing and fixing peep hole / eye piece of approved make to doors including all labour and material
complete
Labours :
2 Carpenter for fixing 0.10 Nos. 200.00 20.00
Helper 0.10 Nos. 100.00 10.00
(0.1 carp + 0.1 help are required for
fixing the latch for one door)
Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Sqm.
2 Labours :
For fabricating & fixing in position 15.00 Kg. 8.00 120.00
Mason for finishing 0.10 No. 200.00 20.00
For powder coating 1.27 Sqm. 161.40 205.62
4 Others
Nil 0.00 0.00 0.00
TOTAL 1018.76
Say Rs. 1,019 /- Per Sqm.
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Sqm.
Providing, fabricating and fixing in position for grills & railings in MS tubular sections of all shapes and
size, with weight upto 15 kg / sqm, as per detail design and drawing, painted with one coat of zinc
chromate & two coats of enamel paint,all labour and material complete.
2 Labours :
For fabricating & fixing in position 15.00 Kg. 8.00 120.00
Mason for finishing 0.10 No. 200.00 20.00
For enamel painting 1.27 Sqm. 30.00 38.22
3 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 797.86
Say Rs. 798 /- Per Sqm.
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Sqm.
Description : P/F MS Z section windows
Providing and fixing in position MS glazed windows with Z section, 4 mm thick clear float glass, 10 mm
MS square bars at 120 mm c/c, required springs, putty and two coats of oilpaint etc complete.
2 Labours :
For fabricating & fixing in position
(9.6*1.53+8*.785 = 14.2 kg. 20.97 Kg. 10.00 209.68
Mason for finishing 0.10 No. 200.00 20.00
For enamel painting 1.08 Sqm. 30.00 32.40
For fixing glass 0.32 No. 150.00 47.52
(0.22 glazier reqd. for each Sqm.)
4 Others
Nil 0.00 0.00 0.00
Prepared by :
Carpenter for shuttering ( 2sqm per cum.) 0.2 130 26 One carpenter can do 10 sqm. Per day
Helper for shuttering 0.2 100 20 One helper can do 10 sqm. Per day
Add for deshuttering @ 25% 11.5
57.5 Assuming 75mm thk. For 2x2 size ftg. 2.2 sqm
Con = 2.15*2.15*.075 = 0.35 shutt. =
Material cost of shuttering 2.15*4*.075 = .65 0.0192
Area of shuttering = 2 sqm. Per cum of concrete, For wooden runner
for each Sqm. Cost = 23.5 / .65 = 36.15 add 4 rs. (2.15x4*3.28*4*4/144)*225 = (705) / 30 =
For nails & oil etc. 80 23.5 rs. Per 0.65 sqm. 2.6m
4”x3”Wooden runner at 225/- per cft. =
(4*3/144)*8*5*225/- 939.1392
78.2616
RCC M20 for footings 152.4528
Assuming Size of 1.5x1.5x.4
Labour
For pouring 1.6
Male coolie 0.67 80 53.6 Conc. = 1.5*1.5*.4 = 0.9cum
Female coolie 0.67 80 53.6 shutt = 1.5 * 4 *.4 = 2.4
107.2 shutt / cum = 2.4/0.9 =2.67
0.9
One mason can do finishing of 9 cum. ( 10
Mason for finishing 0.11 150 16.5 ftgs. )
Page 1
backup calculation
Carpenter for shuttering (approx = 3.0 sqm) 0.3 130 39 One carpenter can do 10 sqm. Per day
Helper for shuttering 0.3 100 30 One helper can do 10 sqm. Per day
Add for deshuttering @ 25% 17.25 0.3
86.25
Material cost of shuttering
Carpenter for shuttering (10 sqm. Shutt / cum) 1.25 130 162.5 One carpenter can do 8 sqm. Per day
Helper for shuttering 1.25 100 125 One helper can do 8 sqm. Per day
Add for deshuttering @ 25% 71.875
359.375
Material cost of shuttering 4.98
Page 2
backup calculation
Carpenter for shuttering (10sqm / cum. Of conc.) 1 130 130 One carpenter can do 10 sqm. Per day
Helper for shuttering 1 100 100 One helper can do 10 sqm. Per day
Add for deshuttering @ 25% 57.5
287.5
Material cost of shuttering
Page 3
backup calculation
Mason for finishing 0.1 150 15 One mason can do finishing of 10 cum.
Carpenter for shuttering (10sqm percum.) 1.67 130 217.1 One carpenter can do 6 sqm. Per day
Helper for shuttering 1.67 100 167 One helper can do 6 sqm. Per day
Add for deshuttering @ 25% 96.025
480.125
Material cost of shuttering
Mason for finishing 0.07 150 10.5 One mason can do finishing of 15 cum.
Page 4
backup calculation
Carpenter for shuttering ( 10sqm per cum.) 1.25 130 162.5 One carpenter can do 8 sqm. Per day
Helper for shuttering 1.25 100 125 One helper can do 8 sqm. Per day
Add for deshuttering @ 25% 71.875
359.375
Material cost of shuttering
Mason for finishing 0.07 150 10.5 One mason can do finishing of 15 cum.
1.75
Carpenter for shuttering ( 12sqm per cum.) 2 130 260 One carpenter can do 6 sqm. Per day
Helper for shuttering 2 100 200 One helper can do 6 sqm. Per day
Add for deshuttering @ 25% 115
575
Material cost of shuttering
1000 rs. For plywood + 900 rs. For wooden
Area of shuttering = 12sqm. Per cum of concrete,
runner = (1000+900)/2.88 = 659 rs. Per
for each Sqm. Cost = 731 / 10 =73, add 10/- for
Sqm. + 2x(120/10) for 2 no. for supports
shuttering oil & nails
996 Total = (659+72)
Page 5
backup calculation
Page 6
backup calculation
Helper for shuttering 1.6 100 160 One helper can do 5 sqm. Per day
Add for deshuttering @ 25% 92
460
Material cost of shuttering
1000 rs. For plywood + 900 rs. For wooden
Area of shuttering = 8sqm. Per cum of concrete, runner = (1000+900)/2.88 = 659 rs.
for each Sqm. Cost = 87, add 10/-for shuttering Assuming 12 uses rate Per Sqm. = 54.91,
oil & nails Add 8/- for supports + 24rs for chavis Total
776 = (55+8+24)
4”x3”Wooden runner at 225/- per cft. =
(4*3/144)*8*6*225/-
Mason for finishing 0.1 150 15 One mason can do finishing of 10cum.
1.75
Carpenter for shuttering ( 7sqm per cum.) 1 130 130 One carpenter can do 7 sqm. Per day
Helper for shuttering 1 100 100 One helper can do 7 sqm. Per day
Add for deshuttering @ 35% 80.5
310.5
Material cost of shuttering
Hire charges for plate = 20/- per month, we
Area of shuttering = 7sqm. Per cum of concrete, have two uses per month, i.e rate per sqm
for each Sqm. Cost = 87.5 , add 10/- for = 20, add for wooden runners 4”x4” @ 3no.
shuttering oil & nails per sqm.(37.5/-), add for ballies at
682.5 2.5*120/10(30) = 20+37.5+30 = 87.5/-
Page 7
backup calculation
Mason for finishing 0.05 150 7.5 One mason can do finishing of 20cum.
1.75
Carpenter for shuttering ( 16sqm per cum.) 2 130 260 One carpenter can do 8 sqm. Per day
Helper for shuttering 2 100 200 One helper can do 8 sqm. Per day
Add for deshuttering @ 25% 115
575
Material cost of shuttering
1000 rs. For plywood + 900 rs. For wooden
Area of shuttering = 16sqm. Per cum of concrete, runner = (1000+900)/2.88 = 659 rs. With 12
for each Sqm. Cost = 85 , add 10/- for shuttering uses rate per Sqm. =54.91 Add 6/- for
oil & nails supports + 24rs for chavis Total =
1520 (55+6+24) = 85
Mason for finishing 0.25 150 37.5 One mason can do finishing of 4cum.
Carpenter for shuttering ( 8sqm per cum.) 2 130 260 One carpenter can do 4 sqm. Per day
Helper for shuttering 2 100 200 One helper can do 4 sqm. Per day
Add for deshuttering @ 35% 161
621
Material cost of shuttering
1000 rs. For plywood + 1200 rs. For
Area of shuttering = 8sqm. Per cum of concrete, wooden runner = (1000+1200)/2.88 = 764
for each Sqm. Cost = 89 , add 11/- for shuttering rs. Per Sqm. + 8x(120/10) for 8 no. for
oil & nails supports + 32rs for chavis Total =
800 (764+96+32)
Page 8
backup calculation
892
763.8888888889
Mason for finishing 0.25 150 37.5 One mason can do finishing of 4cum.
Carpenter for shuttering (12sqm per cum.) 3 130 390 One carpenter can do 4 sqm. Per day
Helper for shuttering 3 100 300 One helper can do 4 sqm. Per day
Add for deshuttering @ 35% 241.5
931.5
Material cost of shuttering
1000 rs. For plywood + 1200 rs. For
Area of shuttering = 12sqm. Per cum of concrete, wooden runner = (1000+1200)/2.88 = 764
for each Sqm. Cost = 91 , add 11/- for shuttering rs. Per Sqm. + 8x(120/10) for 8 no. for
oil & nails supports + 48rs for chavis Total =
1224 (764+96+48)
908
Labour 0.4347826087
Page 9
backup calculation
Labour
mason 0.46 150 69 87.7192982456
One mason pair to do 150cft. (I.e.4.245
Unskilled labour ( 2 nos per mason) 1.2 80 96 cum) of UCR
Add for corner stones & 87
add for corner stones preparation ,
assuming 3.0m length & 1.5m height,
corner stones required 30nos @ 5/- for
(.38*3*1.5 = 1.71 cum. I.e 150/1.71 = 87rs.
252 Per cum.
Page 10
backup calculation
Labour 1.2195121951
mason 0.56 150 84 3.5375
One mason pair to do 125ft. (I.e.3.53 cum)
Unskilled labour ( 2 nos per mason) 1 80 80 of BBM
164
Labour
mason 0.35 150 52.5
One mason pair to do 200cft. (I.e.5.66 cum)
Unskilled labour ( 2 nos per mason) 0.7 80 56 of BBM
108.5
Unskilled labour 2 nos. for 1 hour for 10
Scaffolding / sand screening etc. 0.57 80 45.6 sqm area ( 3.5cum.)
Labour
mason 0.108 150 16.2
One mason pair to do 150cft. (I.e.4.25 cum
Unskilled labour ( 2 nos per mason) 0.216 80 17.28 = 18.5 sqm.) of BBM
33.48
Labour
mason 0.162 150 24.3
One mason pair to do 150cft. (I.e.4.25 cum
Unskilled labour ( 2 nos per mason) 0.216 80 17.28 = 18.5 sqm.) of BBM
Page 11
backup calculation
41.58
Labour
mason 0.17 150 25.5
One mason pair & 3 male coolie to do
Unskilled labour (2 nos) 0.2 80 16 12sqm.. Of BBM
41.5
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e .1 x .2 = 0.02 cum of sand
Sand screening 0.02 53 1.1 required. (150 per brass)
7.7
Labour
mason 0.2 150 30
One mason pair & 3 male coolie to do
Unskilled labour (2 nos) 0.2 80 16 10sqm.. Of BBM 0.03
46
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e .15 x .2 = 0.03 cum of sand
Sand screening 0.03 53 1.6 required. (rate 150/- per brass)
Page 12
backup calculation
8.2
Labour
mason 0.46 150 69
One mason pair to do 150cft. (I.e.4.52 cum)
Unskilled labour ( 2 nos per mason) 0.7 80 56 of rubble masonary
Add for corner stones 87
One mason can do 150 cft. Of face
add for face dressing of stones 0.24 175.00 41.22 dressing
Labour
mason 0.11 150 16.5
One mason pair & 2 male coolie to do
Unskilled labour (2 nos) 0.11 80 8.8 18sqm.. Of BBM (2 brass) 18.58736059
25.3
Page 13
backup calculation
Labour
mason 0.11 150 16.5
One mason pair & 2 male coolie to do
Unskilled labour (2 nos) 0.11 80 8.8 18sqm.. Of BBM
25.3
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e .2 x .2 = 0.04 cum of sand
Sand screening 0.04 53 2.1 required. (150 per brass)
8.8
Labour
mason 0.11 150 16.5
One mason pair & 2 male coolie to do
Unskilled labour (2 nos) 0.11 80 8.8 18sqm.. Of BBM (2 brass)
25.3
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e .1 x .2 = 0.02 cum of sand
Sand screening 0.02 53 1.1 required. (150 per brass)
7.7
Page 14
backup calculation
Labour
mason 0.122 150 18.3
One mason pair & 2 male coolie to do
Unskilled labour (2 nos) 0.122 80 9.76 18sqm.. Of BBM (150 sft. = 16.4 Sqm.)
28.06
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e .15 x .2 = 0.03 cum of sand
Sand screening 0.03 53 1.6 required. (150 per brass)
8.2
Labour
mason 0.122 150 18.3
One mason pair & 2 male coolie to do
Unskilled labour (2 nos) 0.122 80 9.76 18sqm.. Of BBM (150 sft. = 16.4 Sqm.)
28.06
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e .2 x .2 = 0.04 cum of sand
Sand screening 0.04 53 2.1 required. (150 per brass)
8.8 18.75
Labour
mason 0.1 200 20
Page 15
backup calculation
Labour
mason 0.13 200 26
One mason can do 7to 8 sqm. Of plaster &
Unskilled labour (2 nos) 0.27 80 21.6 unskilled labour @2 per mason
47.6
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e 1 x .025 = 0.025 cum of sand
Sand screening 0.025 53 1.3 required. (150 per brass)
8.0
Labour
mason 0.2 225 45
One mason can do 5 sqm. Of plaster &
Unskilled labour (2 nos) 0.27 80 21.6 unskilled labour @2 per mason
Unskilled labour at 2 nos can clean upto
Unskilled labour (2 nos) 0.2 80 16 10sqm. Area for receiving plaster
82.6
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
Page 16
backup calculation
Labour
mason 0.1 225 22.5
One mason can do 10 sqm. Of pointing &
Unskilled labour (2 nos) 0.1 80 8 unskilled labour @1 per mason
Unskilled labour at 1 nos can clean upto
Unskilled labour (2 nos) 0.05 80 4 20sqm. Area for receiving poitnting
34.5
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e (1 x .025)*.3 = 0.008 cum of
Sand screening 0.008 53 0.4 sand required. (150 per brass)
7.1
Labour
mason 0.1 225 22.5
One mason can do 7.5 sqm. Of pointing &
Unskilled labour (2 nos) 0.13 80 10.4 unskilled labour @1 per mason
Unskilled labour at 1 nos can clean upto
Unskilled labour (2 nos) 0.05 80 4 20sqm. Area for receiving poitnting
36.9
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e (1 x .025)*.3 = 0.008 cum of
Sand screening 0.008 53 0.4 sand required. (150 per brass)
7.1
Page 17
backup calculation
Labour
mason 0.1 200 20
One mason can do 10 sqm. Of plaster &
Unskilled labour (2 nos) 0.27 80 21.6 unskilled labour @2 per mason
41.6
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e (1 x .02) = 0.02 cum of sand
Sand screening 0.02 53 1.1 required. (150 per brass)
7.7
Labour
mason 0.07 200 14
Unskilled labour (2 nos) 0.2 80 16 One mason can do 15 sqm. Of plaster
30
Unskilled labour 2 nos. for 1 hour for 3 sqm
Scaffolding etc. 0.083 80 6.64 area
For 1sqm. I.e (1 x .012) = 0.012 cum of
Sand screening 0.012 53 0.6 sand required. (150 per brass)
7.3
Labour
mason 0.1 225 22.5
One mason can do 10 sqm. Of plaster &
Unskilled labour (2 nos) 0.1 80 8 unskilled labour @1 per mason
30.5
Unskilled labour 1 nos. for 0.5 hour for
Scaffolding / sand screening etc. 0.1 80 8 4.35 sqm area ( 1 / .23 = 4.35 sqm.)
Page 18
backup calculation
Labour
mason 0.1 225 22.5
One mason can do 10 sqm. Of plaster &
Unskilled labour (2 nos) 0.1 80 8 unskilled labour @1 per mason
30.5
Unskilled labour 1 nos. for 0.5 hour for
Scaffolding / sand screening etc. 0.1 80 8 4.35 sqm area ( 1 / .23 = 4.35 sqm.)
Carpenter for shuttering ( 8sqm per cum.) 1.33 130 172.9 One carpenter can do 6 sqm. Per day
Helper for shuttering 1.33 100 133 One helper can do 6 sqm. Per day
Add for deshuttering @ 35% 107.065
412.965
Material cost of shuttering
Hire charges for plate = 20/- per month, we
Area of shuttering = 7sqm. Per cum of concrete, have two uses per month, i.e rate per sqm
for each Sqm. Cost = 87.5 , add 10/- for = 20, add for wooden runners 4”x4” @ 3no.
shuttering oil & nails per sqm.(37.5/-), add for ballies at
682.5 2.5*120/10(30) = 20+37.5+30 = 87.5/-
Page 19
backup calculation
Carpenter for shuttering ( 7 sqm per cum.) 1.17 130 152.1 One carpenter can do 6 sqm. Per day
Helper for shuttering 1.17 100 117 One helper can do 6 sqm. Per day
Add for deshuttering @ 35% 94.185
363.285
Material cost of shuttering
Hire charges for plate = 20/- per month, we
have two uses per month, i.e rate per sqm
Area of shuttering = 7 sqm. Per cum of concrete,
= 20, add for wooden runners 4”x4” @ 3no.
for each Sqm. Cost = 117.5 , add 10/- for
per sqm.(37.5/-), add for ballies at
shuttering oil & nails
(2.5*120)*2/10 i.e. Rs.(60) = 20+37.5+60 =
892.5 117.5/-
117.5
Carpenter for shuttering (20sqm per cum.) 2 130 260 One carpenter can do 10 sqm. Per day
Helper for shuttering 2 100 200 One helper can do 10 sqm. Per day
Add for deshuttering @ 35% 161
621
Material cost of shuttering
Page 20
backup calculation
Area of shuttering =13 sqm. Per cum of concrete, 1000 rs. For plywood + 1200 rs. For
for each Sqm. Cost = 764 / 15 = 50.93 , add 10/- wooden runner = (1000+1200)/2.88 = 764
for shuttering oil & nails 1220 rs. Per Sqm.
50.9333333333
Page 21
backup calculation
Page 22
backup calculation
23
Page 23
backup calculation
ply
battem
ballies
1.34
Page 24
backup calculation
0.375
1.5625
Page 25
backup calculation
2.0875
Page 26
backup calculation
2.00
1.25
Page 27
Rate analysis
Providing sand faced plaster externally in cement mortor in all position for a coat of 15 to 20mm thk. in
c.m. 1:5 finishing the surface taking out grains and curing for twenty one days scaffolding etc. complete.
2 Labours :
for Plastering 1.00 Sqm 41.60 41.60
4 Others
Scaffolding & sand screening
charges 1.00 Sqm 7.70 7.70
TOTAL 137.56
Rate analysis
Providing & applying 23 mm av. Th 1:3 c.m. sand faced plaster in 2 coats (base coat of 15 mm th and
finishing coat of 8 mm th) to concrete & brick surfaces, risers or otherwise including mixing plasticizers &
waterproofing compound supplied free as directed as including curing, scaffolding, corners, & edges,
bands, splays, grroves, drips, offsets (for which no extra payment will be made) curing etc. complete.
2 Labours :
for Plastering 1.00 Sqm 47.60 47.60
Nil
4 Others
Scaffolding & sand screening
charges 1.00 Sqm 7.97 7.97
TOTAL 167.93
Prepared by :
Rate analysis
Providing & applying av. 12 mm thick 1:4 C.M. plaster with Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves,
offsets etc. for which which no extra payment will be made.
2 Labours :
for Plastering 1.00 Sqm 36.00 36.00
Nil
4 Others
Scaffolding charges 1.00 Sqm 7.28 7.28
TOTAL (A) 95.53
5 Tools & Plants Charges 2.00% on total (A) 1.91
6 Water charges 0.50% on total (A) 0.48
7 Electricity Charges 0.00% on total (A) 0.00
TOTAL 112.60
Prepared by :
Rate analysis
Providing & applying av. 2 cm thick 1:4 C.M. plaster with Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves,
offsets etc. for which which no extra payment will be made.
2 Labours :
for Plastering work 1.00 Sqm 36.00 36.00
TOTAL 137.12
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : P2 Default Date :
Revised on Date : 14-08-06
ITEM NO -
FDAPL/PLAST/V/10 Unit : per sqm
Extra for providing chemical admixtures in plastering for waterproofing as per manufacturer's
specifications.( Pidilite / Laticrete / Roffee/ Fosroc or any other approved make)
4 Others
Sand screening & material
shifting 1.00 Sqm 7.97 7.97
TOTAL 269.61
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : P2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item no - FDAPL/PLAST/V/8 Unit : per sqm
2 Labours :
for Pointing 1.00 Sqm 34.50 34.50
Nil
4 Others
Sand screening & scaffolding 1.00 Sqm 7.06 7.06
TOTAL 64.14
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : P2 Default Date :
Revised on Date : 14-08-06
Item No. : 24 / IV 6 Unit : per sqm
2 Labours :
for Pointing 1.00 Sqm 36.90 36.90
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
Nil
4 Others
Sand screening & scaffolding 1.00 Sqm 7.06 7.06
0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 90.07
Prepared by :
Site: 0 Location : 0
Computer Code No. : P4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 26 / IV 10 Unit : per sqm
2 Labours :
for POP work 1.00 Sqm 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
4 Others
Scaffolding charges 1.00 Sqm 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
TOTAL 0.00
Prepared by :
Rate analysis
Site: 0 Location : 0
Computer Code No. : P4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 26 Unit : per sqm
Providing & applying av. 12 cm thick 1:4 C.M. plaster without Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves,
offsets etc. for which which no extra payment will be made.(behind tile dado)
2 Labours :
for Plastering work 1.00 Sqm 30.00 30.00
4 Others
Scaffolding charges 1.00 Sqm 7.28 7.28
TOTAL 94.45
0.1354
0.034
Rate analysis
Providing and laying in position reinforcemnt steel of various diameters incluidng cutting
bending, binding with binding wire for all RCC work like footings, columns, beams, slabs,
paradise staircases, chajjas, walls, etc. as per RCC Specialist's design & drawing details
with necessary bending, laying, binding, with binding wire, etc. complete. Rate to include
all lead & lift.
2 Labours :
for reinforcement works including 1.00 MT 2143.75 2143.75
cutting, bending, binding etc.
including T & P etc. complete.
4 Others
Prepared by :
Amount
0.00
Err:509
0.00
0.00
0.00
0.00
0.00
Err:509
0.00
Err:509
0.00
Err:509
0.00
Err:509
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Err:509
0.00
0.00
0.00
Err:509
0.00
Err:509
Err:509
Err:509
Err:509
0.00
0.00
0.00
0.00
0.00
0.00
Err:509