SILVER PROJECT
Wednesday 30 - 04 - 2019
DETAIL SCHEDULE OF SILVER PROJECT PT.UNILEVER INDONESIA (PERIMETER, STAIR,MOSQUE & R&D ROOM)
DATE ISUED = 30-04-2019
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
I ICE AREA
I ROAD
1 FRONT ROAD
Site Clearing
100% DONE
Excavation
100% DONE
Backfill
Compaction
100% DONE
Pouring Concrete
100% DONE
2 MIDDLE ROAD
Site Clearing
100% DONE
Excavation
100% DONE
Backfill
100% DONE
Compaction
100% DONE
Pouring Concrete
100% DONE
3 BACK ROAD
Site Clearing
100% DONE
Excavation
100% DONE
Backfill
100% DONE
Compaction
100% DONE
Pouring Concrete
100% DONE
II FENCE
1 BACK UTILITY BUILDING
100% DONE
III BUILDING
1 STAIR
Demolition of Existing Stair
100% DONE
Modification of Existing Stair
100% DONE
2 IT BUILDING
Site Clearing 100% DONE
Beam, Top Slab & Faschia (Until Curing time & Minimum
concrete grade reached for formwork reshoring)
100% DONE
Floor (Related with reshoring time)
100% DONE
Wall
100% DONE
Door & Window (Related with reshoring time) FABRIKASI INSTALL
100% DONE
Lighting (Related with reshoring time)
100% DONE ` ;/
II SCC AREA
I ROAD
1 BACK ROAD (Trash Building Area)
Site Clearing
100% DONE
Excavation
100% DONE
Backfill
100% DONE
Compaction
100% DONE
Pouring Concrete
100% DONE
II FENCE
1 ICE - SCC
100% DONE
2 TRASH BUILDING AREA
100% DONE
3 CARD BOARD BOX AREA
100% DONE
4 SCC - TBB
100% DONE
III BUILDING
1 MOSQUE ROOM
Inner Wall
100% DONE
Outter Wall
100% DONE
Doors & Windows
100% DONE
Ceiling
100% DONE
Floor
100% DONE OFF AUDIT
Lighting
100% DONE
Inner Stair & Platform Railing
100% DONE
Outter Platform
100% DONE
Canopy
100% DONE
Sanitary
100% DONE
II ROAD
Site Clearing
100% DONE
Excavation
100% DONE
Backfill
100% DONE
Compaction
100% DONE
Pouring Concrete
100% DONE
III BUILDING
1 CHRUSER
Site Clearing
100% DONE
Excavation
100% DONE
Back Fill
100% DONE
Compaction
100% DONE
Foundation
100% DONE
Tie Beam
100% DONE
Column
100% DONE
Beam
100% DONE
Slab
100% DONE
MEP works
100% DONE
2 BEDENG ASET & NON ASET
Site Clearing
100% DONE
Excavation
100% DONE
Back Fill
100% DONE
Compaction
100% DONE
Foundation
100% DONE
Tie Beam
100% DONE
Column
100% DONE
Beam
100% DONE
Slab
100% DONE
MEP works
100% DONE
3 DRIVER SHELTER
Site Clearing
100% DONE
Excavation
100% DONE
Back Fill
100% DONE
Compaction
100% DONE
Foundation
100% DONE
Tie Beam
100% DONE
Column
100% DONE
Beam
100% DONE
Slab
100% DONE
Driver table plate
100% DONE
100% DONE
NOTE/ISSUE :
NOTE :
- Stair ICE will be executed after Middel Road Ice was done
PLAN = - Fence of back utility building was waiting for instruction
ACTUAL =
EXTEND SCH. =
No. Dok. : FM/19-01/CONS
No. Rev. :
DOCUMENTATION OF CONSTRUCTION PROGRESS Tgl Rev. :
REPORT PROGRESS
POURING CONCRETE FINISH STAIR MODIFICATION WORK AT IC-WALLS AREA PAINTING OF IT ROOM INTERNAL WALL
WATERPROOFING IT ROOM BUILDING BASE PAINTING OF IT ROOM EXTERNAL WALL IT BUILDING RAMP
FINISHING BRICK AT IT BUILDING DUCT INSTALL WINDOWS AT IT BUILDING INSTALL DOORS AT IT BUILDING
FLOOR WORK AT IT BUILDING PAINTING OF IT ROOM EXTERNAL FLASHING PLASTER WORK AT IT BUIDING
INSULATION WORK AT IT BUILDING DUCT FINISH TO PAINT EXTERNAL WALL OF IT BUILDING ROOF SCREED OF IT ROOM
PAINTING EXTERNAL WALL AT IT BUILDING PAINTING EXTERNAL WALL AT IT BUILDING DOORS INSTALLATION AT IT ROOM
INSTALL BRC FENCE AT THE BACK OF UTILITY BUILDING INSTALL HEBLE AT THE BACK OF UTILITY BUILDING INSTALL BRC FENCE AT THE BACK OF UTILITY BUILDING
No. Dok. : FM/19-01/CONS
No. Rev. :
DOCUMENTATION OF CONSTRUCTION PROGRESS Tgl Rev. :
REPORT PROGRESS
ELECTRICAL WORK AT BEDENG ASET BUILDING ELECTRICAL WORK AT BEDENG ASET BUILDING FINISH RENDERING BEDENG ASET WALL
CHRUSSER ROOF TOP FINISH RENDERING CHRUSSER WALL TABLE PLATE WORK OF DRIVER SHELTER
BRC HOT DIP WORK OF BEDENG ASET BUILDING FINISH TBB RAMP FINISHING DRIVER SHELTER
TOILET AT DRIVER SHELTE SANITARY WORK AT BEDENG ASET MEP WORK AT DRIVER SHELTER
DRIVER SHELTER TOILET DOOR SANITARY WORK AT DRIVER SHELTER CEILING AND WALL OF DRIVER SHELTERS TOILET
BRC HOT DIP AT BEDENG ASET NON ASET BUILDING BRC HOT DIP AT TRASH DOMESTIC BUILDING
No. Dok. : FM/19-01/CONS
No. Rev. :
DOCUMENTATION OF CONSTRUCTION PROGRESS Tgl Rev. :
REPORT PROGRESS
Wednesday 30 - 04 - 2019
FENCE OF ICE - SCC AREA FENCE OF ICE - SCC AREA FENCE OF ICE - SCC AREA
FENCE OF ICE - SCC AREA FENCE OF TRASH BULDING AREA ROOF OF TRASH BULDING AREA
FENCE OF SCC - TBB AREA FENCE OF SCC - TBB AREA FENCE OF SCC - TBB AREA
INNER STAIR AND RAILING WALL OF OUTTER MOSQUE BUILDING WINDOWS AND DOOR OF MOSQUE ROOM
WALL OF OUTTER MOSQUE BUILDING DOORS OF MOSQUE ROOM WINDOWS AND DOOR OF MOSQUE ROOM
SANITARY OF MOSQUE BUILDING FENCE OF CARD BOARD BOX AREA FENCE OF CARD BOARD BOX AREA
FENCE OF CARD BOARD BOX AREA FINISH SCC FOOT PATH FINISH SCC FOOT PATH
PAINTING SCC TRASH ROOM EXTERIOR WALL RND ROOM PLAFOND PAINTING RND TOILET ROOM TILE WORK
PABRICATION AND INSTALL GUTTER AT SCC TRASH ROOM INSTALL FLASHING TRASH ROOM SCC TRASH ROOM GATE
TRASH ROOM STEEL HOLLOW DOOR PAINTING SCC TRASH ROOM WALL PAINTING SCC TRASH ROOM WALL
ELECTRICAL WORK AT TRASH ROOM PAINTING SCC TRASH ROOM EXTERNAL WALL WALL FINISHING SCC R&D ROOM
TILE WORK AT RND TOILET PAINTING OF RND EXTERNAL WALL GLASS DOORS OF RND ROOM
TRASH ROOM BUILDING EXTERIOR WALL PAINTING FLOOR WORK AT RND TOILET ROOM EMERGENCY DOOR INSTALLATIONS AT RND
FLOOR WORK AT RND TOILET ROOM PLASTR WORK AT RND ROOM RND ROOM
INCREASING BRC FENCE OF SCC FOOT PATH BUNDWALL WORK AT TRASH ROOM SCC MEP WORK AT RND TOILET
RND BUILDING INSTALL RND STAIR POLYCARBONATE INSTALL RND STAIR POLYCARBONATE
RENDERING AT LPG STORAGE ROOM MOSQUE STAIR PAINTING FINISH STAIR WORK AT RND BUILDING
FINISHING MOSQUE COLUMN PAINTING MOSQUE PLATFORM RENDERING AT LPG STORAGE ROOM
INSTALL DOORS FRAME AT LPG STORAGE ROOM INSTALL WASTAFLE INSTALL ROOF FRAME OF LPG STORAGE ROOM
INSTALL DOORS AT LPG STORAGE ROOM FINISHING EXTERNAL WALL OF RND BUILDING FINISHING FLOOR WORK AT LPG STORAGE
ELECTRICAL WORK AT LPG ROOM INSTALL CEILING FRAME AT LPG ROOM PAINTING OF LPG STORAGE ROOM CEILING