PETRONAS TECHNICAL GUIDELINES

Progress Measurement System

PTG 19.80.04
May 2015

© 2015 PETROLIAM NASIONAL BERHAD (PETRONAS)


All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or
by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright
owner. PETRONAS Technical Standards are Company’s internal standards and meant for authorized users only.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 2 of 456

FOREWORD

PETRONAS Technical Guidelines (PTG) has been developed based on the accumulated knowledge,
experience, Lessons Learnt and Best Practices of the PETRONAS group supplementing PETRONAS
Technical Standards (PTS), National and International standards where appropriate. The key objective
of PTG is to guide the implementation of technical practices across the PETRONAS group.

Compliance to PTG should be adhered to across the Group. The PTG shall remain confidential within the
PETRONAS Group and shall not be issued to Contractors / Manufacturers / Suppliers. Issuance of PTG to
third parties shall be subjected to G-TA approval.

y
nl
In issuing and making the PTG available, PETRONAS is not making any warranty on the accuracy or

O
completeness of the information contained in PTG. The end-users shall ensure accuracy and

se
completeness of the PGT used for the intended application.
lU
PETRONAS is the sole copyright holder of PTG. No part of this document may be reproduced, stored in
na

a retrieval system or transmitted in any form or by any means (electronic, mechanical, recording or
otherwise) or be disclosed by users to any company or person whomsoever, without the prior written
er

consent of PETRONAS.
nt
-I

The PTG shall be used exclusively for the authorised purpose. The users shall arrange for PTG to be kept
in safe custody and shall ensure its secrecy is maintained and provide satisfactory information to
AS

PETRONAS that this requirement is met.


N
O
TR
PE
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 3 of 456

Table of Contents

1.0 INTRODUCTION ........................................................................................................5


1.1 SCOPE ............................................................................................................................... 5
1.2 GLOSSARY OF TERM ......................................................................................................... 5
1.3 SUMMARY OF CHANGES .................................................................................................. 6
2.0 GENERAL ..................................................................................................................7
2.1 PRINCIPLES OF PMS ......................................................................................................... 7

y
nl
3.0 PROGRESS MEASUREMENT METHODOLOGY.............................................................8

O
4.0 BIBLIOGRAPHY ....................................................................................................... 10

se
APPENDIX 1: Upstream PMS-WEIGHT FACTOR CALCULATION ............................................ 11
lU
APPENDIX 2: Upstream PMS- FEL 1 .................................................................................... 32
na

APPENDIX 3: Upstream PMS- FEL 2 .................................................................................... 43


er

APPENDIX 4: Upstream PMS- FEL3 ..................................................................................... 61


nt
-I

APPENDIX 5: Upstream PMS-DETAIL ENGINEERING ............................................................ 92


AS

APPENDIX 6: Upstream PMS- PROCUREMENT SUPPLY BY COMPANY ............................... 105


APPENDIX 7: Upstream PMS- PROCUREMENT .................................................................. 110
N
O

APPENDIX 8: Upstream PMS-FABRICATION ...................................................................... 114


TR

APPENDIX 9: Upstream PMS- CONSTRUCTION ................................................................. 144


PE

APPENDIX 10: Upstream PMS-INSTALLATION................................................................... 257


APPENDIX 11: Upstream PMS-HOOK-UP AND COMMISSIONING ...................................... 264
APPENDIX 12: UPSTREAM PMS-DRILLING ........................................................................ 267
APPENDIX 13: Upstream PMS- PROJECT CLOSURE ............................................................ 272
APPENDIX 14: Downstream PMS- WEIGHT FACTOR CALCULATION ................................... 274
APPENDIX 15: Downstream PMS- FEL 1 ............................................................................ 294
APPENDIX 16: Downstream PMS- FEL 2 ............................................................................ 301
APPENDIX 17: Downstream PMS- FEL3 ............................................................................ 309
APPENDIX 18: Downstream PMS- DETAIL ENGINEERING .................................................. 322
APPENDIX 19: Downstream PMS- PROCUREMENT SUPPLY BY COMPANY ......................... 329
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 4 of 456

APPENDIX 20: Downstream PMS- PROCUREMENT ........................................................... 334


APPENDIX 21: Downstream PMS- CONSTRUCTION ........................................................... 338
APPENDIX 22: Downstream PMS- COMMISSIONING (D8) ................................................. 449
APPENDIX 23: Downstream PMS- PROJECT CLOSURE ....................................................... 451

y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 5 of 456

1.0 INTRODUCTION
This PTS provides technical requirements in the development of Progress Measurement System
(PMS). The primary objective of this PTS is to provide the methodology in establishing the
progress base (weight factor), to measure and calculate the progress of the actual work done
for all project in PETRONAS.

1.1 SCOPE
This PTS specifies the requirement and methodology for developing the project weighting and
measuring system up to work package level required at various phases of the project from
project initiation to project close out. It provides an overview of the entire scope of
developing a weighting system and progress measuring methodology covering Overall, Phase,
Sub-Phase, Facility, Control account and work package Level. This PTS is intended to be used in
different types of projects.

y
nl
1.2 GLOSSARY OF TERM

O
1.2.1 General Definition of Terms & Abbreviations

se
Refer to PTS Requirements, General Definition of Terms, Abbreviations & Reading Guide PTS
lU
00.01.03 for General Definition of Terms & Abbreviations.
na

1.2.2 Specific Definition of Terms


er

None.
nt

1.2.3 Specific Abbreviations


-I

No Abbreviation Description
AS

1 CCE Cost Control Engineer


N
O

2 DFCE Department for Cost Engineering


TR

3 DPP Development Project Planning


PE

4 FEL Front End Loading

5 FDP Field Development Plan

6 FEED Front End Engineering and Design

7 HUC Hook Up and Commissioning

8 PCPP Project Control Planning Package

9 PED Petroleum Engineering Division

10 PGSS Project Generation Selection and Sequencing

11 PM Project Manager
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 6 of 456

No Abbreviation Description

12 PMT Project Management Team

13 PMO Project Management Office

14 PPMS PETRONAS Project Management System

15 WBS Work Breakdown Structure

16 WPB Work Program and Budget

1.3 SUMMARY OF CHANGES


This is a new PTS.

y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 7 of 456

2.0 GENERAL

2.1 PRINCIPLES OF PMS


The entire work scope of project is categorized under 5 major phases. This level will be referred
as Level 1:

i. Milestones
ii. FEL 1 - Initiation
iii. FEL 2 - Scope Selection
iv. FEL3 – Scope Definition
v. Execution

All phases except Milestone are divided to contracting which includes contracting in house and
Contract No; this level will be referred as Level 2.

y
nl
Each of these phases is divided into different sub-phases, i.e. execution Phase includes 12 sub-

O
phases such as Detail Design, Procurement, Fabrication, Construction, HUC, etc. This level will
be referred as Level 3.

se
lU
These sub-phases are divided into facilities; this level will be referred as Level 4.
na

These facilities are divided into control account; this level will be referred as Level 5.
er

Control account with or without asset is broken down into work packages. Work packages level
nt

will be referred as Level 6.


-I

Finally, work packages are broken down into sub-work packages. Sub work packages level will
AS

be referred as Level 7 which is applicable for Construction and Fabrication only.


N

The following assumptions shall be considered before using PMS methodology:


O

i. The weightage of the entire project at different levels shall be calculated based on
TR

the Cost
ii. If any changes occur in the project, actual progress shall be calculated against whole
PE

work volume including all changes not only to measure Engineering, Procurement,
and Fabrication, HUC or drilling progress effectively but also to monitor remaining
work accurately. In case that the work quantity is increased or decreased from
original quantity due to the changes, weight value for each work item shall be
adjusted in proportion to the work quantity
iii. In case of re-work, the Actual physical progress shall be freeze at their latest
reported step and shall not be moved (forward or backward) until the progress has
again reached the correct progress
iv. Any changes in WBS, e.g. modification in the structure of WBS, the calculation of
weightages and progress measuring shall remain the same
v. All the budgets amounts in budget column are examples only
vi. Any missing item of this PMS shall be agreed with PMT
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 8 of 456

3.0 PROGRESS MEASUREMENT METHODOLOGY


To measure the actual progress, a bottom-up approach should be followed; i.e. the
measurement and calculation sequence should be in the below order (from left to right):

Activity  Sub Work Package  Work Package  Control Account  Facility  Sub Phase 
Contracting  Phase  Project

Start

Calculate Activity

y
nl
Progress

O
se
lU
Calculate Work Package
Progress
na
er
nt

Calculate Control
-I

Account Progress
AS
N
O

Calculate Facility
TR

Progress
PE

Calculate Sub Phase


Progress

Calculate Contracting
Progress

Calculate Phase
Progress

Finish
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 9 of 456

For each level, there is a specific Weight Factor according to table below:

Sub
Work
Sub Control Work
Level Project Phase Contracting Facility Package
Phase Account Package
/
Activity

L1 L4
Weight Factor 100% L2 WF% L3 WF% L5 WF% L6 WF% L7 WF%
WF% WF%

Physical Overall
P1% P2% P3% P4% P5% P6% P7%
Progress %Complete Progress

y
The weightages for each level shall be calculated. For calculating the overall progress follows

nl
the steps as below:

O
se
lU
Sub Work
na

Work Control Contracti Project


Package/ Facility Sub Phase Phase
Package Account ng Overall
Activity
er
nt
-I
AS
N
O
TR
PE
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 10 of 456

4.0 BIBLIOGRAPHY

In this PTS, reference is made to the following Standards/Publications. Unless specifically


designated by date, the latest edition of each publication shall be used, together with any
supplements/revisions thereto:

PETRONAS TECHNICAL STANDARDS


Index to PTS PTS 00.01.01
Requirements, General Definition of Terms, Abbreviations & PTS 00.01.03
Reading Guide

y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 11 of 456

APPENDIX 1: Upstream PMS-WEIGHT FACTOR CALCULATION


OVERALL PROJECT PROGRESS

The physical progress for the overall project is obtained by summing up the physical weighted progress
of each phase:

 FEL 1 – Initiation
 FEL 2 – Scope Selection
 FEL 3 – Scope Definition
 Execution

The corresponding weight factors are determined initially in accordance with the respective cost values,
as defined by the project cost breakdown structure.

y
For calculating the Level 1 Weight Factor (L1 WF) for each phase follows these steps:

nl
O
1. Find the project total budget. In this example the total is RM1,000,000
2. Find the budget of each phase

se
3. To calculate the phase weight factor use this formula:
lU
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑃ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1) = × 100%
na

𝑃𝑟𝑜𝑗𝑒𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
er

Example:
nt
-I

𝑅𝑀 45,000
𝐹𝐸𝐸𝐷 𝑊𝐹 (𝐿1) = × 100% = 4.5%
𝑅𝑀 1,000,000
AS

Budget
N

Level 1 Weight
No. Phase
O

Factor (L1 WF)%


(RM '000)
TR

1 Project Management 25,000 2.5


PE

2 Initiation 10,000 1.00

3 Conceptual Engineering Services 20,000 2.00

4 FEED 45,000 4.5

5 Execution 900,000 90.00

Total 1,000,000 100.00

Note: The summation of L1 WF for all phases has to be 100%


PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 12 of 456

Project Management

Project Management is broken down in 10 sub phases. For calculating Level 2 Weight Factor (L2 WF):

1. Find the phase budget. In this example the total is RM 25,000.


2. Find the budget of each sub phase.
3. To calculate the sub phase weight factor use this formula:

𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡


𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 (𝑑𝑖𝑠𝑐𝑖𝑝𝑙𝑖𝑛𝑒) 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 4,500
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 18%
𝑅𝑀 25,000

y
nl
4. (L1 WF) for sub phase/discipline is its share portion at Project level rather than its parent level

O
WF (i.e. Phase) it can be calculated.

se
(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
lU
𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 (𝑑𝑖𝑠𝑐𝑖𝑝𝑙𝑖𝑛𝑒) 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
na

Example:
er

(18% × 2.5%)
nt

𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 (𝐿1 𝑊𝐹) = = 0.45%


100%
-I
AS

Budget Budget
Phase (L1 WF)% Sub-Phase / Discipline (L2 WF)% (L1 WF)%
(RM '000) (RM '000)
N

Project
25000 2.5
O

Management
TR

Initiation 1000 4 0.1


Conceptual
4500 18 0.45
PE

Engineering
FEED 1750 7 0.18
Detail Engineering 3000 12 0.3
Procurement PCSB
2000 8 0.2
Supplied Materials
Fabrication 3750 15 0.38
Installation 1500 6 0.15
HUC 1750 7 0.18
Drilling 3250 13 0.33
Project Closure 2500 10 0.25

Total 25000 100.00 2.5


PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 13 of 456

Initiation

Initiation is broken down to two contracts. Same as phase level each contract has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. For calculating Level 2 Weight Factor (L2WF):

1. Find the phase budget. In this example the total is RM 10,000


2. Find the budget of each contract.
3. To calculate the contract weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

y
𝑅𝑀 10,000

nl
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 100.00%
𝑅𝑀 10,000

O
se
Phase Budget (RM '000) (L1 WF)%
lU
Contracting Budget (RM '000) (L2 WF)% (L1 WF)%
na

Initiation 10,000 1 - - - -
er
nt

In House 10,000 100.00 1.00


-I

Total 10,000 100.00 1.00


AS

For in house services there are some sub phases. Same as Phase level each sub-phase has its own budget
N

(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
O

their own weight factor. Contract No.1 is broken up in 4 sub-phases. For calculating Level 3 Weight
TR

Factor (L3 WF):


PE

1. Find the Contract total budget. In this example the Total for contract in house is RM 10,000
and for In house service is RM 10,000

2. Find the budget of each Sub phase.

3. To calculate the Sub phase weight factor use this formula:

𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 2,000
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 20.00%
𝑅𝑀 10,000

4. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 14 of 456

(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(20% × 100%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿2 𝑊𝐹) = = 20.00%
100%

5. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(20% × 1%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿1 𝑊𝐹) = = 0.20%

y
100%

nl
O
Budget (L3WF)
Contracting Budget (RM '000) (L2 WF)% Sub-Phase / Discipline (L2 WF)% (L1 WF)%

se
(RM '000) %

In House 10,000 100.00


lU
Pre Bidding 0 0.00 0.00 0.00
na

Bid/Evaluate/Award 0 0.00 0.00 0.00


er

Conceptual
2000 20.00 20.00 0.20
Development
nt

PMT Deliverable 1500 15.00 15.00 0.15


-I

Petroleum
3000 30.00 30.00 0.30
AS

Economics
Feasibility Studies 3500 35.00 35.00 0.35
N

Total 10,000 100.00 100.00 1.00


O
TR

Level 4 WF: Not Applicable in WBS


PE

For calculating Level 5 Weight Factor (L5 WF):

1. Find the Sub phase total budget. In this example the Total for facilities feasibility studies is
RM 3,500.
2. Find the budget of each Control Account.
3. To calculate the Control account weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝐵𝑢𝑑𝑔𝑒𝑡


𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:
𝑅𝑀 350
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100% = 10%
𝑅𝑀 3,500

4. (L3 WF) for control account is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 15 of 456

(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:
(10% × 35%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙(𝐿3 𝑊𝐹) = = 3.5%
100%

5. (L2 WF) for control account is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

Example:
(10% × 35%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 (𝐿2𝑊𝐹) = = 3.5%

y
100%

nl
O
6. (L1 WF) for control account is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

se
lU
(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
na

Example:
er

(10% × 0.35%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 (𝐿1 𝑊𝐹) = = 0.04 %
nt

100%
-I
AS

Budget
Budget (L3 Control (L3WF)
Sub-Phase (RM (L5WF)% (L2 WF)% (L1 WF)%
(RM '000) WF)% Account %
'000)
N
O

Facilities
TR

Feasibility 3,500 35.00


Studies
PE

3.5 3.5 0.04


General 350 10.00

HSE 1050 30.00 10.5 10.5 0.11

Facility 21 21 0.20
2100 60.00
Assessment
Total 3,500 100.00 35.00 35.00 0.35

For calculating Level 6 Weight Factor (L6 WF):

1. Find the control account total budget. In this example the Total for general is RM 350.
2. Find the budget of each work package.
3. To calculate the work packages weight factor use this formula:
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 16 of 456

𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡

Example:

272
Preliminary Concept Development 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100 = 40 %
350

4. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%

y
Example:

nl
O
(40% × 10%)
Preliminary Concept Development(𝐿5 𝑊𝐹) = =4%
100%

se
5. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
lU
(i.e. Phase) It can be calculated.
na

(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
er

100%
nt

Example:
-I

(40% × 3.50%)
AS

Preliminary Concept Development (𝐿3 𝑊𝐹) = = 1.40 %


100%
N

6. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
O

(i.e. Phase) It can be calculated.


TR

(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
PE

𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =


100%

Example:

(40% × 3.5%)
Preliminary Concept Development (𝐿2 𝑊𝐹) = = 1.40 %
100%

7. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(40% × 0.04%)
Preliminary Concept Development(𝐿1 𝑊𝐹) = = 0.01 %
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 17 of 456

Budget (L5 Budget


Control (L2 (L1
(RM WF) Work Package (RM (L6WF) (L5WF) (L3W
Account WF)% WF)%
'000) % '000) % % F)%
General 350 10
Preliminary
140
Concept 40.00 4.00 1.40 1.40 0.01
Development
Environment
Preliminary 210
60.00 6.00 2.10 2.10 0.03
Assessment &
Report
Total 350 100.00 10.00 3.50 3.50 0.04

y
Conceptual Engineering Services

nl
O
Conceptual Engineering Services is broken down to two contracts. Same as phase level each contract
has its own budget (accessible from budget estimation from cost control/finance dept.) and accordingly

se
each of them has their own weight factor. For calculating Level 2 Weight Factor (L2WF):
lU
1. Find the phase budget. In this example the total is RM 20,000
na

2. Find the budget of each contract.


3. To calculate the contract weight factor use this formula:
er
nt

𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
-I

𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
AS

Example:
N

𝑅𝑀 3,000
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑆𝑒𝑟𝑣𝑖𝑐𝑒𝑠 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 15.00%
O

𝑅𝑀 20,000
TR

𝑅𝑀 17,000
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 85.00%
PE

𝑅𝑀 20,000

4. (L1 WF) for sub phase/discipline is its share portion at Project level rather than its parent level
WF (i.e. Phase) it can be calculated.
(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 (𝑑𝑖𝑠𝑐𝑖𝑝𝑙𝑖𝑛𝑒) 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(85% × 2%)
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 (𝐿1 𝑊𝐹) = = 1.70%
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 18 of 456

Budget (L1 Budget


Phase Contracting (L2 WF)% (L1 WF)%
(RM '000) WF)% (RM '000)

Conceptual
Engineering 20,000 2 - - - -
Services
In House 3,000 15.00 0.30

Contract No.1 17,000 85.00 1.70

Total 20,000 100.00 2.00

For each contract there are some sub phases. Same as Phase level each sub-phase has its own budget

y
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has

nl
their own weight factor. Contract No.1 is broken up in 4 sub-phases. For calculating Level 3 Weight

O
Factor (L3 WF):

se
1. Find the Contract total budget. In this example the Total for contract No.1 is RM 17,000 and
lU
for In house service is RM 3,000
2. Find the budget of each Sub phase.
na

3. To calculate the Sub phase weight factor use this formula:


er
nt

𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
-I

𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
AS

Example:
N

𝑅𝑀5,950
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 35.00%
O

𝑅𝑀 17,000
TR

4. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
PE

Phase) It can be calculated


(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(35% × 85%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿2 𝑊𝐹) = = 29.75%
100%
5. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(35% × 1.7%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿1 𝑊𝐹) = = 0.60%
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 19 of 456

Budget (RM (L2 Budget (RM (L3WF) (L2 (L1


Contracting Sub-Phase / Discipline
'000) WF)% '000) % WF)% WF)%

In House 3,000 15.00


Planning & Scoping 1500 50.00 7.5 0.15
Concept Select 1500 50.00 7.5 0.15
Total 3,000 100.00 15.00 0.30

Budget (RM (L2 Budget (RM (L3WF) (L2 (L1


Contracting Sub-Phase / Discipline
'000) WF)% '000) % WF)% WF)%

FEL2 17,000 85.00


4.25 0.09
Pre Bidding 850 5.00

y
4.25 0.09
Bid/Evaluate/Award 850 5.00

nl
O
21.25 0.43
Sub surface Modeling 4250 25.00

se
Conceptual 29.75 0.60
5950 35.00
Development
lU
Appraisal/Learning 25.50 0.51
5100 30.00
na

well drilling
Total 17,000 100.00 85.00 1.70
er
nt

Only Applicable in WBS for Appraisal /Learning Well Drilling


-I

For calculating Level 4 Weight Factor (L4 WF): Only Applicable in WBS for Appraisal /Learning
AS

Well Drilling
N

1. Find the sub phase total budget. In this example the Total budget for Appraisal/Learning
O

Well Drilling is RM5100.


TR

2. Find the budget of each facility.


3. To calculate the facility weight factor use this formula:
PE

𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝐵𝑢𝑑𝑔𝑒𝑡
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿4𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 5,100
𝑂𝑓𝑓𝑠ℎ𝑜𝑟𝑒 𝐷𝑟𝑖𝑙𝑙𝑖𝑛𝑔 𝑊𝐹 (𝐿4𝑊𝐹) = × 100% = 100%
𝑅𝑀 5,100

4. (L3 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿4𝑊𝐹 × 𝐿3𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 20 of 456

Example:

(100% × 30.0%)
𝑂𝑓𝑓𝑠ℎ𝑜𝑟𝑒 𝐷𝑟𝑖𝑙𝑖𝑛𝑔 (𝐿3 𝑊𝐹) = = 30.00 %
100%

5. (L2 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿4𝑊𝐹 × 𝐿2𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

Example:

(100% × 25.50%)
𝑂𝑓𝑓𝑠ℎ𝑜𝑟𝑒 𝐷𝑟𝑖𝑙𝑙𝑖𝑛𝑔 (𝐿2𝑊𝐹) = = 25.50 %

y
100%

nl
O
6. (L1 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

se
lU
(𝐿4𝑊𝐹 × 𝐿1𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿1 𝑊𝐹) =
na

100%
er

Example:
nt
-I

(100% × 0.51%)
𝑂𝑓𝑓𝑠ℎ𝑜𝑟𝑒 𝐷𝑟𝑖𝑙𝑙𝑖𝑛𝑔 (𝐿1 𝑊𝐹) = = 0.51 %
100%
AS
N
O
TR

Budget Budget
Sub-Phase (L3 WF)% Facility (L4WF)% (L3WF)% (L2 WF)% (L1 WF)%
(RM '000) (RM '000)
PE

Appraisal 5,100 30
Offshore
5,100 100.00 30.00 25.50 0.51
Drilling
Onshore
0 0.00 0.00 0.00 0.00
Drilling
Total 5,100 100.00 30.00 25.50 0.51

For calculating Level 5 Weight Factor (L5 WF):

1. Find the Sub phase or Facility total budget. In this example the Total for concept select is RM
1,500.
2. Find the budget of each Control Account.
3. To calculate the Control account weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝐵𝑢𝑑𝑔𝑒𝑡


𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡/𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 21 of 456

Example:
𝑅𝑀 300
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿5 𝑊𝐹) = × 100% = 20%
𝑅𝑀 1,500

4. (L3 WF) for control account is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:
(20% × 50%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠(𝐿3 𝑊𝐹) = = 10%
100%

5. (L2 WF) for control account is its share portion at Project level rather than its parent level WF

y
nl
(i.e. Phase) It can be calculated.

O
(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)

se
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
lU
Example:
na

(20% × 7.50%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿2𝑊𝐹) = = 1.5%
100%
er
nt

6. (L1 WF) for control account is its share portion at Project level rather than its parent level WF
-I

(i.e. Phase) It can be calculated.


AS

(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
N
O

Example:
TR

(20% × 0.15%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿1 𝑊𝐹) = = 0.03 %
100%
PE
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 22 of 456

Budget Budget
Control (L5WF) (L3WF)
Sub-Phase (RM (L3 WF)% (RM (L2 WF)% (L1 WF)%
Account % %
'000) '000)

Concept Select 1,500 50.00


PMT 5.00 0.76 0.01
150 10.00
Deliverables
Facilities
10.00 1.50 0.03
Conceptual 300 20.00
Design
Pre FEED 10.00 1.50 0.03
300 20.00
Activities
Sub Surface
12.50 1.87 0.04
Conceptual 375 25.00

y
Design

nl
Petroleum 12.50 1.87 0.04

O
375 25.00
Economics

se
Total 1,500 100.00 50.00 7.50 0.15
lU
na

For calculating Level 6 Weight Factor (L6 WF):


er

1. Find the control account total budget. In this example the Total for general is RM 150.
nt

2. Find the budget of each work package.


-I

3. To calculate the work packages weight factor use this formula:


AS

𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100%
N

𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡
O

Example:
TR

37.5
PE

Project Risk Analysis 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100% = 25.00%


150

4. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%

Example:

(25% × 10%)
Project Risk Analysis (𝐿5 𝑊𝐹) = = 2.5 %
100%

5. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 23 of 456

(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:

(25% × 5%)
Project Risk Analysis (𝐿3 𝑊𝐹) = = 1.25%
100%

6. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

y
nl
Example:

O
(25% × 0.76%)
Project Risk Analysis (𝐿2 𝑊𝐹) = = 0.19 %

se
lU 100%

7. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
na
er

(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
nt

100%
-I

Example:
AS

(25% × 0.01%)
Project Risk Analysis(𝐿1 𝑊𝐹) = = 0.0025 %
N

100%
O
TR

Control Budget (RM Budget (L6WF)% (L5WF)% (L3WF)%


(L5 WF)% Work Package (L2 WF)% (L1 WF)%
Account '000) (RM '000)
PE

PMT
Deliverable
150 10
Project Risk 37.5 25.00 2.5 1.25 0.19 0.0025
Analysis
37.5 25.00 2.5 1.25 0.19 0.0025
QRA

Preparation 37.5 25.00 2.5 1.25 0.19 0.0025


of PCPP
37.5 25.00 2.5 1.25 0.19 0.0025
OCS

Total 150 100.00 10.00 5.00 0.76 0.01

FEED

All Level weight factors for FEED will be calculated same as Conceptual design services and Execution
phase.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 24 of 456

EXECUTION

For Execution phase there are two contracts. Same as phase level each contract has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. For calculating Level 2 Weight Factor (L2WF):

1. Find the phase budget. In this example the total is RM 900,000


2. Find the budget of each contract.
3. To calculate the contract weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

y
nl
𝑅𝑀 210,000
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑆𝑒𝑟𝑣𝑖𝑐𝑒𝑠 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 23.33%

O
𝑅𝑀 900,000

se
𝑅𝑀 595,000
𝐸𝑃𝐶𝐼𝐶 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 66.11%
𝑅𝑀 900,000
lU
𝑅𝑀 95,000
na

𝐷𝑟𝑖𝑙𝑙𝑖𝑛𝑔 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 10.56%


𝑅𝑀 900,000
er

4. (L1 WF) for contracting is its share portion at Project level rather than its parent level WF (i.e.
nt

Phase) It can be calculated.


-I
AS

(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
N
O

Example:
TR

(66.11% × 90%)
𝐸𝑃𝐶𝐼𝐶 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 (𝐿1 𝑊𝐹) = = 59.5%
PE

100%

Budget
Phase (L1 WF)% Sub-Phase / Discipline Budget (RM '000) (L2 WF)% (L1 WF)%
(RM '000)

Execution 900,000 90 - - - -

In House 210,000 23.33 21.00

EPCIC Contract No. 1 595,000 66.11 59.50

Drilling Contract No. 2 95,000 10.56 9.50

Total 900,000 100.00 90


PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 25 of 456

For each contract there are some sub phases. Same as Phase level each sub-phase has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. EPCIC Package is broken up in 7 sub-phases. For calculating Level 3 Weight
Factor (L3 WF):

1. Find the Contract total budget. In this example the Total for contract No.1 is RM 595,000 and
for contract No.2 is RM 95,000
2. Find the budget of each Sub phase.
3. To calculate the Sub phase weight factor use this formula:

𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

y
𝑅𝑀 47,000

nl
𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑎𝑡𝑖𝑜𝑛 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 7.9%
𝑅𝑀 595,000

O
se
4. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated lU
(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
na

100%
er

Example:
nt

(7.9% × 66.11%)
-I

𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑎𝑡𝑖𝑜𝑛 (𝐿2 𝑊𝐹) = = 5.22%


100%
AS

5. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
N

Phase) It can be calculated.


O
TR

(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
PE

100%

Example:

(7.9% × 59.5%)
𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑎𝑡𝑖𝑜𝑛 (𝐿1 𝑊𝐹) = = 4.7%
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 26 of 456

Budget
Contracting (L2 WF)% Sub-Phase / Discipline Budget (RM '000) (L3WF)% (L2 WF)% (L1 WF)%
(RM '000)

EPCIC 595,000 66.11


Detail Engineering 40,000 6.72 4.44 4.00
Procurement 177,000 29.75 19.67 17.70
Fabrication 272,000 45.71 30.22 27.20
Installation 47,000 7.90 5.22 4.70
HUC 50,000 8.40 5.56 5.00
Contract Closure
9,000 1.51 1.00 0.90
Report
Total 595,000 100.00 66.11 59.5

y
nl
O
Budget Budget
Contracting (L2WF)% Sub-Phase / Discipline (L3WF)% (L2 WF)% (L1 WF)%
(RM '000) (RM '000)

se
Drilling 95,000 10.56 lU
Drilling 90,000 94.74 10.00 9.00
Contract Closure
na

5,000 5.26 0.56 0.50


Report
er

Total 95,000 100 10.56 9.5


nt
-I

For each sub-phase there are facility, Control account and work packages. Same as Phase level and Sub-
AS

phase, each facility has its own budget (accessible from budget estimation from cost control, finance
and contract dept.) and accordingly each of them has their own weight factor. In this example
N

Fabrication is broken up in 2 facilities.


O
TR

For calculating Level 4 Weight Factor (L4 WF):


PE

1. Find the Sub phase total budget. In this example the Total for Fabrication is RM 272,000.
2. Find the budget of each facility.
3. To calculate the facility weight factor use this formula:

𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝐵𝑢𝑑𝑔𝑒𝑡
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿4 𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 190,400
𝑊𝐻𝑃 𝑊𝐹 (𝐿4 𝑊𝐹) = × 100% = 70%
𝑅𝑀 272,000

4. (L3 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 27 of 456

(𝐿4𝑊𝐹 × 𝐿3𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:

(70% × 45.71%)
𝑊𝐻𝑃 (𝐿3 𝑊𝐹) = = 32 %
100%

5. (L2 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿4𝑊𝐹 × 𝐿2𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

y
Example:

nl
O
(70% × 30.22%)
𝑊𝐻𝑃 (𝐿2𝑊𝐹) = = 21.15 %
100%

se
lU
6. (L1 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
na
er

(𝐿4𝑊𝐹 × 𝐿1𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿1 𝑊𝐹) =
nt

100%
-I

Example:
AS

(70% × 27.2%)
𝑊𝐻𝑃 (𝐿1 𝑊𝐹) = = 19.04 %
N

100%
O
TR
PE

Budget Budget (RM


Sub-Phase (L3 WF)% Facility (L4WF)% (L3WF)% (L2 WF)% (L1 WF)%
(RM '000) '000)

Fabrication 272,000 45.71


WHP 190,400 70.00 32.00 21.15 19.04
Offshore
81,600 30.00 13.71 9.07 8.16
Pipeline
Total 272,000 100.00 45.71 30.22 27.20

For each facility there are Control accounts. Same as Phase level and Sub-phase each control accounts
has its own budget (accessible from budget estimation from cost control, finance and Contract dept.)
and accordingly each of them has their own weight factor. In this example WHP is broken up in 7 control
accounts.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 28 of 456

For calculating Level 5 Weight Factor (L5 WF):

1. Find the facility total budget. In this example the Total for WHP is RM 190,400.
2. Find the budget of each control account.
3. To calculate the control account weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100%
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦

Example:

135,400
𝐹𝑎𝑏𝑟𝑖𝑐𝑎𝑡𝑖𝑜𝑛 𝑌𝑎𝑟𝑑 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100 = 71.11 %
190,400

y
4. (L4 WF) for Control Account is its share portion at Project level rather than its parent level

nl
WF (i.e. Phase) It can be calculated.

O
se
(𝐿5𝑊𝐹 × 𝐿4𝑊𝐹)
𝑊𝐹 (𝐿4 𝑊𝐹) =
lU
100%
na

Example:
er

(71.11% × 70%)
nt

𝐹𝑎𝑏𝑟𝑖𝑐𝑎𝑡𝑖𝑜𝑛 𝑌𝑎𝑟𝑑 (𝐿4 𝑊𝐹) = = 49.78 %


100%
-I

5. (L3 WF) for Control Account is its share portion at Project level rather than its parent level
AS

WF (i.e. Phase) It can be calculated.


N
O

(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
TR

100%
PE

Example:

(71.11% × 32%)
𝐹𝑎𝑏𝑟𝑖𝑐𝑎𝑡𝑖𝑜𝑛 𝑌𝑎𝑟𝑑 (𝐿3 𝑊𝐹) = = 22.76 %
100%

6. (L2 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

Example:

(71.11% × 21.15%)
𝐹𝑎𝑏𝑟𝑖𝑐𝑎𝑡𝑖𝑜𝑛 𝑌𝑎𝑟𝑑 (𝐿2 𝑊𝐹) = = 15.04 %
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 29 of 456

7. (L1 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(71.11% × 19.04%)
𝐹𝑎𝑏𝑟𝑖𝑐𝑎𝑡𝑖𝑜𝑛 𝑌𝑎𝑟𝑑 (𝐿1 𝑊𝐹) = = 13.54 %
100%

Budget Budget (L5WF)% (L4WF) (L3WF)%


Facility (L4 WF)% Control Account (L2 WF)% (L1 WF)%
(RM '000) (RM '000) %

y
WHP 190,400 70

nl
Front End

O
Activities/Mob 4,500 2.36 1.65 0.76 0.50 0.45
ilization

se
Preparation 4,500 2.36
lU 1.65 0.76 0.50 0.45
Engineering
10,000 5.25 3.68 1.68 1.11 1.00
/Shop Drawing
na

Yard
135,400 71.11 49.78 22.76 15.04 13.54
Fabrication
er

Pre
7,000 3.68 2.57 1.18 0.78 0.70
nt

commissioning
-I

Load Out &


25,000 13.13 9.19 4.20 2.78 2.50
Sea Fastening
AS

Final
4,000 2.10 1.47 0.67 0.44 0.40
Documentation
N

Total 190,400 100.00 70.00 32.00 21.15 19.04


O
TR

For each control account there are work packages. Same as Phase level and Sub-phase, each work
PE

package has its own budget (accessible from budget estimation from cost control, finance and contract
dept.) and accordingly each of them has their own weight factor. In this example yard fabrication is
broken up in 8 work packages.

For calculating Level 6 Weight Factor (L6 WF):

1. Find the control account or facility total budget. In this example the Total for Yard
Fabrication is RM 135,400.
2. Find the budget of each work package.
3. To calculate the work package weight factor use this formula:

𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝐵𝑢𝑑𝑔𝑒𝑡

Example:
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 30 of 456

67,700
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100% = 50 %
135,400

4. (L5 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%

Example:

(50% × 71.11%)
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 (𝐿5 𝑊𝐹) = = 35.56 %
100%

5. (L4 WF) for work package is its share portion at Project level rather than its parent level WF

y
(i.e. Phase) It can be calculated.

nl
O
(𝐿6𝑊𝐹 × 𝐿4𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿4 𝑊𝐹) =

se
100%
lU
Example:
na

(50% × 49.78%)
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 (𝐿4 𝑊𝐹) = = 24.89 %
100%
er
nt

6. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
-I

(i.e. Phase) It can be calculated.


AS

(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
N
O

Example:
TR

(50% × 22.76%)
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 (𝐿3 𝑊𝐹) = = 11.38 %
PE

100%

7. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

Example:

(50% × 15.04%)
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 (𝐿2 𝑊𝐹) = = 7.52 %
100%

8. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 31 of 456

(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(50% × 13.54%)
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 (𝐿1 𝑊𝐹) = = 6.77 %
100%

Budget
Control Work Budget (L6WF)% (L5WF)% (L4WF)% (L3WF)%
(RM (L5 WF)%
Packages (RM '000)
(L2 WF)% (L1 WF)%
Account
'000)
Yard
135,400 71.11
Fabrication
Structural 67,700 50 35.56 24.89 11.38 7.52 6.77

y
Piping 13,540 10 7.11 4.98 2.28 1.50 1.35

nl
Pipeline 13,160 9.72 6.91 4.84 2.21 1.46 1.32

O
Mechanical 23,000 16.99 12.08 8.46 3.87 2.55 2.30

se
Electrical 7,000 5.17
lU 3.68 2.57 1.18 0.78 0.70
Instrument 5,000 3.69 2.63 1.84 0.84 0.56 0.50
Blasting 4,500 3.32 2.36 1.65 0.76 0.50 0.45
na

Insulation 1,500 1.11 0.79 0.55 0.25 0.17 0.15


er

Total 135,400 100.00 71.11 49.78 22.76 15.04 13.54


nt
-I
AS

Weight factor for Level 7 shall be calculated based on budgeted cost/man hour.
N
O
TR
PE
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 32 of 456

APPENDIX 2: Upstream PMS- FEL 1

Sub Phase: A1- Pre-Bidding

Weight

y
Sub

nl
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase

O
Code.
Base

se
Progress of each pre-bidding item is calculated as per

lU
following stages:

na
WF for
Stages Description
Stages

er
nt
-I
Tender Plan & ITB Preparation
Stage 1 -If the Tender Plan is issued equal to 35%

AS
- A1 Man-Hour Pre-Bidding Work Step 100% otherwise 0%
N
O
Stage 2 Tender Plan Approval 15%
TR
PE

ITB
Stage 3 - If the ITB is issued equal to 100% 50%
otherwise 0%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 33 of 456

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base

Progress of each bidding item is calculated as per following

y
stages:

nl
WF for

O
Stages Description
Stages

se
RFQ
Stage 1 - If the Inquiry is issued equal to 10%

lU
Bidding/ 100% otherwise 0%

na
- A2 Man-Hour Evaluate/ Work Step TBE
Award Stage 2 - If the TBE is performed equal to 25%

er
100% otherwise 0%

nt
CBE

-I
Stage 3 -, If the CBE is performed equal to 25%
100% otherwise 0%

AS
PETRONAS Approval of Award
- If the vendor/contractor is selected
Stage 4 40%
N
and PO place equal to 100%
O
otherwise 0%
TR

Control Account:
Geoscience & Reservoir
PE

Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base

AA 111 Man-hour Data Gathering Milestone Milestone Description WF for


stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 34 of 456

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Step 1 Start 5.00%
Step 2 Finish 95.00%

y
nl
O
Milestone Description WF for
Evaluate
geological & stages

se
112 geophysical
Milestone
Step 1 Start 5.00%
interpretation

lU
Step 2 Finish 95.00%

na
Milestone Description WF for

er
stages
Reservoir initial Step 1 Start 5.00%

nt
113 Evaluation
Milestone
Step 2 Finish 95.00%

-I
AS
Milestone Description WF for
N Report resources stages
114 & production Milestone
Step 1 Start 5.00%
profiles
O
Step 2 Finish 95.00%
TR

Control Account: Project Control


Initiation
PE

Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base
Schedule &
BA 121 Man-Hour Budget Work Step Work Step Description WF for
Development stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 35 of 456

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Step 1 Schedule Baseline development 65.00%
Step 2 Cost Baseline Development 35.00%

y
nl
Work Step

O
Description WF for
Schedule Risk stages

se
122 Analysis
Work Step
Step 1 SRA session conducting 60.00%

lU
Step 2 SRA Report Issuance 40.00%

na
Deliverable Description WF for
stages

er
I. PCPP Compliance

nt
-I
1.1 Planning & Scheduling 67
Project Scope of Work and

AS
1.1.1 2.53
Objectives
3.79
N 1.1.2 Schedule Basis Memorandum (SBM)
O
Preparation of 1.1.3 3.79
123 PCPP
Deliverable Work Breakdown Structure (WBS)
TR

Organization Breakdown Structure


1.1.4 3.79
(OBS)
PE

Project Management Team (PMT)


1.1.5 6.32
Manpower Plan
Project Execution Schedule
1.1.6 16.43
(Baseline Schedule)
1.1.7 Quantitative Risk Analysis (QRA) 12.64
1.1.8 Critical Path 2.53
1.1.9 Progress Base 3.79
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 36 of 456

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
1.1.10 Progress S-Curve 2.53
1.1.11 2.53

y
Progress Measurement Format

nl
1.1.12 Resource Plan 2.53

O
1.1.13 Project Roadmap 1.26

se
1.1.14 Project Progress Report 1.26
1.1.15 Project Close-Out Report 1.26

lU
1.2 Cost Control 23

na
1.2.1 Cost Breakdown Structure (CBS) 0.88
1.2.2 2.65

er
Project Total Budget
1.2.3 7.08

nt
Work Program & Budget (WPB)
1.2.4 7.08

-I
Corporate Plan & Budget (CPB)
1.2.5 Approved For Expenditure 0.88

AS 1.2.6 Additional Budget (Budget Transfer 0.88


and Supplementary Budget)
N
1.2.7 0.88
O
Additional Budget Request
1.2.8 0.88
TR

Change Order Register


1.2.9 Monthly Cost Report 0.88
PE

1.2.10 Project Close-Out Report 0.88


II TP & PMO Endorsement 5
PCPP Reviewed and Endorsed by TP
2.1 5.00
and PMO (DPP)
III PM Approval 5
PCPP Reviewed and Approved by
3.1 5.00
PM
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 37 of 456

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Total Progress Achievement 100.00

y
Control Account: Project Management Initiation

nl
O
Weight
Work
Factor Description of

se
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.

lU
Base

na
Work Step Description WF for
Project Risk stages

er
124 Man-Hour Analysis
Work Step
Step 1 PRA session conducting 60.00%

nt
Step 2 PRA Report Issuance 40.00%

-I
BB

AS
Work Step Description WF for
Project Charter stages
125 Man-Hour Work Step
N Development
Step 1 Prepared 90.00%
O
Step 2 Approved 10.00%
TR

Control Account: Business Framing


PE

Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base

Business Case
BC 126 Man-Hour Development
Milestone Milestone Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 38 of 456

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
1 Start 0.00%
2 Finish 100.00%

y
nl
O
Milestone Description WF for
Opportunity
127 Man-Hour Milestone stages

se
Framing
1 Start 0.00%

lU
2 Finish 100.00%
Control Account: Data Gathering

na
Weight

er
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula

nt
Calculation Work Package
Code.

-I
Base

131 Man-Hour AS
Finalize
Milestone
Milestone Description WF for
N Economic stages
Assumption
O
1 Start 5.00%
TR

2 Finish 95.00%
CA
PE

Milestone Description WF for


stages
Facilities Data
132 Man-Hour Gathering
Milestone 1 Start 5.00%

2 Finish 95.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 39 of 456

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Control Account: Data Processing & Analysis

y
nl
Milestone Description WF for

O
133 Data Analysis Milestone stages

se
1 Start 5.00%
2 Finish 95.00%

lU
na
Milestone Description WF for
CB 134 Man-Hour Model Building Milestone stages

er
Step 1 Start 5.00%

nt
Step 2 Finish 95.00%

-I
Milestone Description WF for

AS
Develop
135 Economic Milestone stages
1 Start 5.00%
N Scenarios
O
2 Finish 95.00%
TR

Control Account: Model Development & Conclusion


PE

Milestone Description WF for


stages
Run Economics 1 Run Economic Analysis 60.00%
CC 136 Man-Hour & Valuation
Work Step

2 Issue Economic Report 40.00%


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 40 of 456

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base

y
Milestone Description WF for

nl
Make stages

O
137 Conclusion/ Milestone 1 Start 5.00%
Recommendation

se
2 Finish 95.00%

lU
Control Account: General
Weight

na
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula

er
Calculation Work Package
Code.
Base

nt
-I
Milestone Description WF for

AS
Preliminary stages
141 Concept Milestone
N Development 1 Start 5.00%

2 Finish 95.00%
O
Man-
TR

DA
Hour
Milestone Description WF for
PE

Environment
Preliminary
stages
142 Assessment &
Work Step 1 Perform Assessment 60.00%
Report
2 Issue Final Report 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 41 of 456

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Control Account: HSE

y
Weight
Work

nl
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula

O
Calculation Work Package
Code.
Base

se
lU
Milestone Description WF for
Man- Initial Health &
DB 143 Milestone stages

na
Hour Safety Evaluation
Step 1 Start 5.00%

er
Step 2 Finish 95.00%

nt
Control Account: Facility Assessment

-I
Weight
Work
Factor Description of

AS
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base
N
O

Milestone Description WF for


TR

Data Gathering/
144 Milestone stages
Surveying
PE

Step 1 Start 5.00%


DC Man-Hour Step 2 Finish 95.00%
145 Work Step Description WF for
stages
Site Location
Work Step Step 1 Perform Assessment 60.00%
Assessment
Step 2 Issue Final Report 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 42 of 456

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
146 Existing Facility Work Step Description WF for
& stages

y
Work Step
Infrastructure Step 1 Perform Assessment 60.00%

nl
Assessment Step 2 Issue Final Report 40.00%

O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 43 of 456

APPENDIX 3: Upstream PMS- FEL 2


Sub Phase: B1- Pre-Bidding
Weight
Sub
Factor Description of Sub-
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Phase
Code.

y
Base

nl
O
Progress of each pre-bidding item is calculated as per
following stages:

se
lU
WF for
Stages Description
Stages

na
er
Tender Plan & ITB Preparation

nt
Stage 1 -If the Tender Plan is issued 35%

-I
equal to 100% otherwise 0%

AS
- B1 Man-Hour Pre-Bidding Work Step
N
Stage 2 Tender Plan Approval 15%
O
TR
PE

ITB
Stage 3 - If the ITB is issued equal to 50%
100% otherwise 0%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 44 of 456

Sub Phase: B2-Bidding

Weight
Sub
Factor Description of Sub-
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Phase
Code.

y
Base

nl
O
Progress of each bidding item is calculated as per following
stages:

se
lU
WF for
Stages Description
Stages

na
RFQ

er
Stage 1 - If the Inquiry is issued equal to 10%

nt
100% otherwise 0%

-I
TBE
Bidding/ Evaluate/ Stage 2 - If the TBE is performed equal to 25%

AS
- B2 Man-Hour Work Step
Award 100% otherwise 0%
N
CBE-, If the CBE is performed
O
Stage 3 25%
equal to 100% otherwise 0%
TR
PE

PETRONAS Approval of Award


- If the vendor/contractor is
Stage 4 40%
selected and PO place equal to
100% otherwise 0%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 45 of 456

Control Account : Geology, Geophysics, Reservoir Engineering, Product Technology, Petro physics
Weight
Work
Factor Description of Work
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Package
Code.
Base

y
nl
Work Step Description WF for

O
Data Gathering, load
211 and QC Issue Work Step stages

se
Identification Step 1 Data Gathering 50.00%

lU
Step 2 Issue identification Report 50.00%

na
Milestone Description WF for

er
Analysing Quantity , stages
212 Quality and Milestone
1 Start 5.00%

nt
Uncertainties
2 Finish 95.00%

-I
EA,EB,EC,ED,EE,EF,EG Man-Hour

AS
Work Step Description WF for
stages
N
213 TOR Definition Work Step Step 1 Prepared 90.00%
O
Step 2 Approved 10.00%
TR
PE

Milestone Description WF for


stages
Develop study Scope of
1 Start 5.00%
214 Work
Milestone
2 Finish 95.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 46 of 456

Control Account :
Petroleum Economics
Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
Base

y
nl
O
Milestone Description WF for

se
stages
215 Data Gathering Milestone 1 Start 5.00%

lU
na
2 Finish 95.00%

er
nt
Milestone Description WF for

-I
stages

AS
EF Man-Hour 1 Start 5.00%
Data Processing &
216 N Analysis
Milestone
2 Finish 95.00%
O
TR

Milestone Description WF for


PE

stages
1 Start 5.00%
Develop Model &
217 Conclusion
Milestone
2 Finish 95.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 47 of 456

Control Account: Develop Static Model/Geophysics


Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
Base

y
nl
O
Milestone Description WF for
221 Man-Hour Data Acquisition Milestone stages

se
1 Start 5.00%

lU
2 Finish 95.00%

na
Milestone Description WF for

er
stages

nt
222 Man-Hour Data Processing Milestone 1 Start 5.00%

-I
2 Finish 95.00%

AS
FA1
Milestone Description WF for
N
stages
O
Data
223 Man-Hour Interpretation/Analysis
Milestone 1 Start 5.00%
TR

2 Finish 95.00%
PE

Milestone Description WF for


stages
224 Man-Hour Geophysics Modelling Milestone 1 Start 5.00%

2 Finish 95.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 48 of 456

Control Account: Develop Static Model/Geology


Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
Base

y
nl
O
Milestone Description WF for

se
stages
225 Data Acquisition Milestone
1 Start 5.00%

lU
2 Finish 95.00%

na
WF for

er
Milestone Description
stages
226 Data Processing Milestone

nt
1 Start 5.00%

-I
2 Finish 95.00%

AS
FA2 Man-Hour
WF for
N
Data Milestone Description
stages
O
227 Interpretation/Analys Milestone
TR

is 1 Start 5.00%

2 Finish 95.00%
PE

WF for
Milestone Description
stages
228 Geological Modelling Work Step 1 2D/3D Static Model 90.00%
Resource Assessment of Modelled
2 Reservoir
10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 49 of 456

Control Account: Petro physics


Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.

y
Base

nl
O
Milestone Description WF for

se
229 Data Acquisition Milestone stages

lU
1 Start 5.00%
2 Finish 95.00%

na
er
Man- Milestone Description WF for
FA3
Hour

nt
230 Data Processing Milestone stages
1 Start 5.00%

-I
2 Finish 95.00%

AS
Milestone Description WF for
stages
N Data
231 Interpretation/Analysis
Milestone
1 Start 5.00%
O
2 Finish 95.00%
TR

Control Account: Develop Dynamic Model/Reservoir Engineering


PE

Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base

FB1 232 Man-Hour Data Acquisition Milestone Milestone Description WF for


stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 50 of 456

Step 1 Start 5.00%


Step 2 Finish 95.00%

Milestone Description WF for


233 Data Processing Milestone stages

y
Step 1 Start 5.00%

nl
Step 2 Finish 95.00%

O
se
lU
234 Interpretation/Analysis Milestone
Milestone Description WF for

na
stages
Step 1 Start 5.00%

er
Step 2 Finish 95.00%

nt
-I
Work Step Description WF for

AS
stages
Step 1 10.00%
Build Analytical Model
N
Step 2 20.00%
O
Streamline Simulation
Step 3 20.00%
TR

Build Simulation
235 Modelling Work Step Step 4 20.00%
Upscale Geological Model &
PE

Construct Simulation Model


Step 5 10.00%
Initialize and Calibrate Model
Step 6 10.00%
History Matching
Step 7 10.00%
Develop Scenarios & Generate
Production Forecast
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 51 of 456

Control Account: Model Develop Scenarios


Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base

y
nl
Milestone Description WF for

O
stages
Step 1 Start 5.00%

se
GA NA Man-Hour

lU
NA Milestone
Step 2 Finish 95.00%

na
er
nt
Control Account: Investigate Alternative Development Scenarios

-I
Weight
Work

AS
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
N
Base
O
TR

Milestone Description WF for


stages
PE

Step 1 Start 5.00%


GB NA Man-Hour NA Milestone

Step 2 Finish 95.00%


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 52 of 456

Control Account: Optimize Development Plan


Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
Base

y
nl
Milestone Description WF for

O
GC NA Man-Hour NA Milestone stages

se
Step 1 Start 5.00%
Step 2 Finish 95.00%

lU
Control Account: Economic Evaluation

na
Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or

er
Control Account Code. Package Methodology
Calculation Package Formula

nt
Code.
Base

-I
AS
Milestone Description WF for
GD NA Man-Hour N NA Milestone stages
Step 1 Start 5.00%
O
Step 2 Finish 95.00%
TR

Control Account: Develop Concept Report


PE

Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
Base

GE NA Man-Hour NA Milestone Milestone Description WF for


stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 53 of 456

Step 1 Start 5.00%


Step 2 Finish 95.00%

Control Account: PMT Deliverables


Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or

y
Control Account Code. Package Methodology
Calculation Package Formula

nl
Code.
Base

O
se
Work Step Description WF for

lU
241 Man-Hour Project Risk Analysis Work Step stages
Step 1 PRA session conducting 60.00%

na
Step 2 PRA Report Issuance 40.00%

er
Work Step Description WF for

nt
stages

-I
Quantitative Risk Step 1 SRA session conducting 30.00%
242 Man-Hour Analysis
Work Step

AS
Step 2 SRA Report Issuance 20.00%
HA N Step 3 CRA session conducting 30.00%
Step 4 CRA Report Issuance 20.00%
O
Deliverabl Description WF for
TR

e stages
PE

I. PCPP Compliance

243 Man-Hour Preparation of PCPP Deliverable 1.1 Planning & Scheduling 67


Project Scope of Work and
1.1.1 2.53
Objectives
Schedule Basis Memorandum
1.1.2 3.79
(SBM)
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 54 of 456

1.1.3 3.79
Work Breakdown Structure (WBS)
Organization Breakdown
1.1.4 3.79
Structure (OBS)
Project Management Team (PMT)
1.1.5 6.32
Manpower Plan
Project Execution Schedule

y
1.1.6 16.43

nl
(Baseline Schedule)

O
1.1.7 Quantitative Risk Analysis (QRA) 12.64
1.1.8 Critical Path 2.53

se
1.1.9 Progress Base 3.79

lU
1.1.10 Progress S-Curve 2.53

na
1.1.11 Progress Measurement Format 2.53
1.1.12 2.53

er
Resource Plan
1.1.13 1.26

nt
Project Roadmap
1.1.14 1.26

-I
Project Progress Report
1.1.15 Project Close-Out Report 1.26

AS
1.2
N Cost Control 23
1.2.1 Cost Breakdown Structure (CBS) 0.88
O
1.2.2 Project Total Budget 2.65
TR

1.2.3 Work Program & Budget (WPB) 7.08


1.2.4
PE

Corporate Plan & Budget (CPB) 7.08


1.2.5 Approved For Expenditure
0.88
Additional Budget (Budget
1.2.6 Transfer and Supplementary 0.88
Budget)
1.2.7 Additional Budget Request 0.88
1.2.8 Change Order Register 0.88
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 55 of 456

1.2.9 Monthly Cost Report 0.88


1.2.10 Project Close-Out Report 0.88
II TP & PMO Endorsement 5
PCPP Reviewed and Endorsed by
2.1 5.00
TP and PMO (DPP)

y
nl
III PM Approval 5

O
3.1 PCPP Reviewed and Approved by 5.00

se
PM

lU
Total Progress Achievement 100.00
Work Step Description WF for

na
stages

er
Preliminary Overall Step 1 Completed 90.00%
244 Man-Hour Contracting Strategy
Work Step

nt
Step 2 Accepted 10.00%

-I
AS
Control Account: Facilities Conceptual Design & Selection
Weight
Work
N
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
O
Calculation Package Formula
Code.
TR

Base
Work Step Description WF for
PE

stages
245 Man-Hour General Work Step Step 1 Start 10%
HB Step 2 Issued for Information 80%
Step 3 Final Update 10%
Work Step Description WF for
246 Man-Hour Process Work Step
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 56 of 456

Stage 1 Start 10%


Stage 2 Issued for Review 50%
Stage 3 Issue for Approve 30%
Stage 4 Approve for Feed 10%
Work Step Description WF for

y
stages

nl
Stage 1 Start 10%

O
247 Man-Hour Mechanical Work Step
Stage 2 Issued for Review 50%

se
Stage 3 Issue for Approve 30%

lU
Stage 4 Approve for Feed 10%
Work Step Description WF for

na
stages

er
Stage 1 Start 10%
248 Man-Hour Instrumentation Work Step

nt
Stage 2 Issued for Review 50%

-I
Stage 3 Issue for Approve 30%
Stage 4 Approve for Feed 10%

AS
Work Step Description WF for
stages
N
Stage 1 Start 10%
O
249 Man-Hour Electrical Work Step Stage 2 Issued for Review 50%
TR

Stage 3 Issue for Approve 30%


PE

Stage 4 Approve for Feed 10%


Work Step Description WF for
stages
250 Man-Hour Material & Corrosion Work Step Stage 1 Start 10%
Stage 2 Issued for Review 50%
Stage 3 Issue for Approve 30%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 57 of 456

Stage 4 Approve for Feed 10%


Work Step Description WF for
stages
Stage 1 Start 10%
251 Man-Hour HSE Work Step
Stage 2 Issued for Review 50%

y
Stage 3 Issue for Approve 30%

nl
Stage 4 Approve for Feed 10%

O
Work Step Description WF for

se
stages

lU
Stage 1 Start 10%
252 Man-Hour Pipeline Work Step Stage 2 Issued for Review 50%

na
Stage 3 Issue for Approve 30%

er
Stage 4 Approve for Feed 10%

nt
Work Step Description WF for
stages

-I
Stage 1 Start 10%

AS
253 Man-Hour Subsea Work Step
Stage 2 Issued for Review 50%
Stage 3 Issue for Approve 30%
N
Stage 4 Approve for Feed 10%
O
TR

Control Account: Pre FEED Activities


Weight
Work
PE

Factor Description of Work Calculation Description, Detailed Weight Factor or


Control Account Code. Package Methodology
Calculation Package Formula
Code.
Base
Work Step Description WF for
Environmental Impact stages
HC 254 Cost Work Step Step 1
Assessment Pre Bidding Cost
Step 2 Contract Award Cost
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 58 of 456

Step 3 Final Report Cost


Work Step Description WF for
stages
Step 1 Pre Bidding Cost
255 Cost Soil Boring Work Step Step 2 Contract Award Cost

y
Step 3 Execution Cost

nl
Step 4 Final Report Cost

O
Work Step Description WF for

se
stages
Step 1

lU
Pre Bidding Cost
256 Cost Site Survey Work Step Step 2 Contract Award Cost

na
Step 3 Execution Cost

er
Step 4 Final Report Cost

nt
Work Step Description WF for
stages

-I
Step 1 Pre Bidding Cost

AS
257 Cost Pipeline Route Survey Work Step Step 2 Contract Award Cost
Step 3 Execution Cost
N
Step 4 Final Report Cost
O
Work Step Description WF for
TR

stages
Step 1
PE

Preparation for Land Acquisition Cost


Step 2 Application for Land Acquisition Cost
258 Cost Land Acquisition Work Step
Inspection, Gazette and
Step 3 Cost
publication
Step 4 Compensation Payment Cost

Control Account: Sub Surface Conceptual Design


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 59 of 456

Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
Base
Work Step Description WF for
stages

y
nl
Drilling Conceptual Step 1 Drilling Concept Selection 25%
259 Man-Hour Study
Work Step

O
Step 2 Conceptual Well Design 55%

se
Step 3 Geo-Mechanic Study 20%
Work Step Description WF for

lU
HD Well Completion stages
260 Man-Hour Work Step Step 1 Completed 90.00%

na
Conceptual Study
Step 2 Accepted 10.00%

er
Work Step Description WF for

nt
stages
261 Man-Hour Reservoir Engineering Work Step

-I
Step 1 Completed 90.00%
Step 2 Accepted 10.00%

AS
Control Account: Petroleum Economics N
Weight
Work
O
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
TR

Code.
Base
PE

Milestone Description WF for


stages
262 Data Gathering Milestone 1 Start 5.00%
HE 2 Finish 95.00%
Milestone Description WF for
Data Processing & stages
263 Analysis
Milestone
1 Start 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 60 of 456

2 Finish 95.00%

Control Account 1: Pre Drilling Activities


Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula

y
Code.
Base

nl
O
Refer to Drilling PMS

se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 61 of 456

APPENDIX 4: Upstream PMS- FEL3


Sub Phase: C1- Pre-Bidding
Weight
Sub
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Phase Methodology
Calculation Sub-Phase Formula

y
Code.
Base

nl
O
Progress of each pre-bidding item is calculated as per
following stages:

se
lU
WF for
Stages Description
Stages

na
Tender Plan & ITB Preparation

er
- C1 Man-Hour Pre-Bidding Work Step Stage 1 -If the Tender Plan is issued equal 35%

nt
to 100% otherwise 0%

-I
Stage 2 Tender Plan Approval 15%

AS
N ITB
Stage 3 - If the ITB is issued equal to 100% 50%
O
otherwise 0%
TR

Sub Phase: C2-Bidding


PE

Weight
Sub
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Phase Methodology
Calculation Sub-Phase Formula
Code.
Base
Bidding/ Evaluate/ Progress of each bidding item is calculated as per
- C2 Man-Hour Work Step
Award following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 62 of 456

WF for
Stages Description
Stages

RFQ
Stage 1 - If the Inquiry is issued equal to 10%

y
100% otherwise 0%

nl
TBE

O
Stage 2 - If the TBE is performed equal to 25%

se
100% otherwise 0%

lU
CBE
Stage 3 -, If the CBE is performed equal to 25%

na
100% otherwise 0%
PETRONAS Approval of Award

er
- If the vendor/contractor is
Stage 4 40%

nt
selected and PO place equal to

-I
100% otherwise 0%

AS
Control Account: General, Process, Structural, Mechanical, Piping, Electrical, Instrument and Telecommunication, Civil, Pipelines, Architecture, HSE (Fire
and Safety), HVAC, Others N
Work Weight
O
Packag Factor Description of Calculation Description, Detailed Weight Factor or
TR

Control Account Code. Methodology


e Calculation Work Package Formula
Code. Base
PE

Work Description WF for


JA,JB,JC,JD,JE,JF,JG,JH,JK,JI,JK,JL Step stages
311 Man-Hour CTR Deliverables Work Step
,JM Step 1 Start 10.00%
Step 2 Issue for Comment 60.00%
Step 3 Issue for Design 30.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 63 of 456

Control Account: Quantitative Risk Analysis


Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculatio Work Package Formula
Code.
n Base

y
nl
O
Work Description WF for

se
Step stages
Man- Step 1 SRA session conducting 30.00%

lU
KA NA NA Work Step
Hour Step 2 SRA Report Issuance 20.00%

na
Step 3 CRA session conducting 30.00%

er
Step 4 CRA Report Issuance 20.00%

nt
-I
Control Account: Economics

AS
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
N
Control Account Code. Package Methodology
Calculatio Work Package Formula
O
Code.
n Base
TR

Work Description WF for


PE

Step stages
Man- Step 1 Run Economic Analysis 60.00%
KB NA NA Work Step
Hour
Step 2 Economic Report 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 64 of 456

Control Account: Approval (FEL3)


Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculatio Work Package Formula
Code.
n Base

y
nl
Work Description WF for
Step stages

O
Man-
KC NA NA Milestone Step 1 Start 5.00%
Hour

se
Step 2 Finish 95.00%

lU
Control Account: FDP
Weight

na
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology

er
Calculatio Work Package Formula
Code.
n Base

nt
Work Description WF for

-I
Man- Step stages
KD NA NA Work Step Step 1 FDP Submission 60.00%

AS
Hour
N Step 2 FDP Approval 40.00%
Control Account: OCS
O
Weight
Work
TR

Factor Description of Calculation Description, Detailed Weight Factor or


Control Account Code. Package Methodology
Calculatio Work Package Formula
Code.
PE

n Base
Work Description WF for
Step stages
Man- Step 1 OCS Submission 60.00%
KE NA NA Work Step
Hour
Step 2 OCS Approval 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 65 of 456

Control Account: Project Sanction


Weight
Work
Factor Description of Work
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculatio Package
Code.
n Base
Work Description WF for

y
Step stages

nl
Man-
KF NA NA Work Step Step 1 Advance Funding Submission 60.00%

O
Hour
Step 2 Sanction Approval 40.00%

se
Control Account: PCPP Preparation

lU
Weight
Work
Factor Description of Work
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula

na
Calculatio Package
Code.
n Base

er
nt
Deliver Description WF for

-I
able stages
I. PCPP Compliance

AS 1.1 Planning & Scheduling 67


N
Project Scope of Work and
O
1.1.1 2.53
Objectives
TR

Man- Schedule Basis Memorandum


KG NA NA Work Step 3.79
Hour 1.1.2 (SBM)
PE

1.1.3 Work Breakdown Structure (WBS) 3.79


Organization Breakdown Structure
1.1.4 3.79
(OBS)
Project Management Team (PMT)
1.1.5 6.32
Manpower Plan
Project Execution Schedule
1.1.6 16.43
(Baseline Schedule)
1.1.7 Quantitative Risk Analysis (QRA) 12.64
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 66 of 456

1.1.8 2.53
Critical Path
1.1.9 Progress Base 3.79
1.1.10 Progress S-Curve 2.53
1.1.11 Progress Measurement Format 2.53

y
1.1.12 Resource Plan 2.53

nl
1.26

O
1.1.13 Project Roadmap
1.1.14 Project Progress Report 1.26

se
1.1.15 Project Close-Out Report 1.26

lU
1.2 Cost Control 23
1.2.1

na
Cost Breakdown Structure (CBS) 0.88
1.2.2 Project Total Budget 2.65

er
1.2.3 Work Program & Budget (WPB) 7.08

nt
1.2.4 Corporate Plan & Budget (CPB) 7.08

-I
1.2.5 Approved For Expenditure 0.88

AS
1.2.6 Additional Budget (Budget Transfer 0.88
and Supplementary Budget)
N
1.2.7 Additional Budget Request 0.88
O
1.2.8 Change Order Register 0.88
TR

1.2.9 Monthly Cost Report 0.88


PE

1.2.10 Project Close-Out Report 0.88


II TP & PMO Endorsement 5
PCPP Reviewed and Endorsed by TP
2.1 5.00
and PMO (DPP)
III PM Approval 5
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 67 of 456

3.1 PCPP Reviewed and Approved by 5.00


PM

Total Progress Achievement 100.00

y
nl
O
Control Account: Preparing well # (1) program

se
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or

lU
Control Account Code. Package Methodology
Calculatio Work Package Formula
Code.
n Base

na
Work Description WF for

er
Step stages
Step 1 Start 5.00%

nt
Step 2 Offset Wells Review 5.00%

-I
Step 3 Risk Analysis 5.00%

AS
Man-
LA NA NA Milestone Step 4 Preparation of Drilling Program 35.00%
Hour
Step 5 Preparation of AFE and equipment 10.00%
N
list
O
Step 6 Drilling Program Review by TPs 5.00%
TR

Step 7 Finalize drilling program 15.00%


PE

Step 8 issue for drilling 20.00%

Control Account: Conducting DRC 01


Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculatio Work Package Formula
Code.
n Base
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 68 of 456

Work Description WF for


Step stages
Step 1 Start 5.00%
Man-
LB NA NA Milestone
Hour Step 2 Finish 95.00%

y
nl
O
Control Account: Conducting PTPR 01-Execution

se
Work Weight
Packag Factor Description of Calculation Description, Detailed Weight Factor or

lU
Control Account Code. Methodology
e Calculation Work Package Formula
Code. Base

na
Work Description WF for

er
Step stages
Step 1 Start 5.00%

nt
LC NA Man-Hour NA Milestone
Step 2 Finish 95.00%

-I
AS
N
O
TR
PE
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 69 of 456

FEED
Control Account JA: General
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

y
Progress of general procedures calculated as per following stages:

nl
O
WF for
Stages Description
Stages

se
Man-Hour All Type of documents Work Step Stage 1 Start 10%

lU
Stage 2 Issued for Information 80%

na
Stage 4 Final Update 10%

er
Control Account JB: Process

nt
-I
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

AS Progress of each PFD and P&ID are calculated as per following stages:
N
O
WF for
Stages Description
TR

Stages

Stage 1 Start 10%


PE

Man-Hour PFD /P&ID Work Step


Stage 2 Issued for Review 50%

Stage 3 Issue for Approve 20%

Stage 4 Issued for Detail Design 10%


Stage 5 Final Update 10%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 70 of 456

Control Account JC: Structural


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:

y
WF for
Stages Description

nl
Stages
-Procedures

O
-Specification Stage 1 Start 10%
Man-Hour

se
-Work Scope Work Step Stage 2 Issue for Internal Discipline check 30%
-Design Basis

lU
Stage 3 Issued for Review 20%

na
Stage 4 Issued for Design 20%

er
Stage 5 Final Update 20%

nt
Progress of each general specs and reports are calculated as per following

-I
stages:

AS
WF for
Stages Description
N Stages
Stage 1 Start 10%
O
General Specs,
Man-Hour Work Step
TR

Reports Stage 2 Issue for Internal Discipline check 30%

Stage 3 Issued for Review 20%


PE

Stage 4 Issued for Detail Design 20%

Stage 5 Final Update 20%

Man-Hour Drawings Work Step Progress of each drawings are calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 71 of 456

WF for
Stages Description
Stages
Stage 1 Start 10%

Stage 2 Issue for Internal Discipline check 30%

y
nl
Stage 3 Issued for Review 20%

O
Stage 4 Issue for Approve 20%

se
Stage 5 Issued for Detail Design 10%

lU
Stage 6 Final Update 10%

na
Control Account JD: Mechanical

er
nt
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula

-I
Document

AS
Progress of each document is calculated as per following stages:
N
WF for
Stages Description
O
Stages
TR

Stage 1 Start 10%


Man-Hour All type of document Work Step
PE

Stage 2 Issue for Inquiry 20%

Stage 3 TBE 10%

Stage 4 Issue for Purchase 10%

Stage 5 First set vendors drawing approved 15%


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 72 of 456

Stage 6 Detail Vendor Drawings Receipt 15%

Stage 7 Vendor Drawing final check 10%

Stage 8 Final Update 10%

y
nl
Control Account JE: Piping

O
se
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

lU
Progress of each document is calculated as per following stages:

na
WF for

er
Stages Description
Stages

nt
10%
Stage 1 Start

-I
Man-Hour Specification Work Step
40%

AS
Stage 2 Issued for Comment
30%
N Stage 3 Issued for Approval
O
20%
TR

Stage 4 Issue for Detail Design

Description of
PE

Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each document is calculated as per following stages:


Man-Hour Standard Drawings Work Step
WF for
Stages Description
Stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 73 of 456

10%
Stage 1 Start

40%
Stage 2 Issued for Comment
30%
Stage 3 Issued for Approval

y
nl
20%
Stage 4 Issue for Detail Design

O
se
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

lU
Progress of each datasheet is calculated as per following stages:

na
WF for

er
Stages Description
Stages

nt
10%
Stage 1 Start

-I
Man-Hour Datasheets Work Step 40%

AS
Stage 2 Issued for Comment

30%
N
Stage 3 Issued for Approval
O
20%
TR

Stage 4 Issue for Detail Design


PE

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of Plot Plan is calculated as per following stages:
WF for
Man-Hour Plot Plan Work Step Stages Description
Stages
10%
Stage 1 Start
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 74 of 456

30%
Stage 2 Issue for Internal Discipline Check

10%
Stage 3 Issued for Comment
30%
Stage 4 Issued for Approval

y
nl
20%
Stage 5 Issue for Detail Design

O
se
Control Account JF: Electrical

lU
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

na
Progress of each drawing is calculated as per following stages:

er
WF for

nt
Stages Description
Stages

-I
10%
Stage 1 Start

Man-Hour Drawings ASWork Step Stage 2 Issue for Internal Discipline check
30%
N
O
10%
Stage 3 Issued for Comment
TR

30%
Stage 4 Issued for Approval
PE

20%
Stage 5 Issue for Detail Design

Control Account JG: Instrument & Telecommunication

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 75 of 456

Progress of each document is calculated as per following stages:

WF for
Stages Description
Stages

y
10%
Stage 1 Start

nl
Man-Hour Specifications Work Step

O
40%
Stage 2 Issued for comment

se
30%

lU
Stage 3 Issued for Approval
20%

na
Stage 4 Issue for Detail Design

er
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

nt
-I
Progress of each document is calculated as per following stages:
WF for

AS
Stages Description
N Stages
10%
Stage 1 Start
O
Man-Hour Datasheets Work Step
40%
TR

Stage 2 Issued for comment


PE

30%
Stage 3 Issued for Approval

20%
Stage 4 Issue for Detail Design
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour Drawings Work Step Progress of each document is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 76 of 456

WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check

y
nl
10%
Stage 3 Issued for Inquiry

O
40%

se
Stage 4 Issued for Purchase

lU
10%
Stage 5 Final Update

na
Control Account JH: Civil

er
nt
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

-I
AS
Progress of each drawing is calculated as per following stages:
N WF for
Stages Description
O
Stages
10%
TR

Stage 1 Start
Man-Hour Installation Drawings Work Step
PE

30%
Stage 2 Issue for Internal Discipline check

10%
Stage 2 Issued for Comment
20%
Stage 3 Issued for Approval
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 77 of 456

20%
Stage 4 Issue for Detail Design

10%
Stage 5 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula

y
Document

nl
O
Progress of each concrete structure is calculated as per following stages:

se
WF for
Stages Description
Stages

lU
10%
Stage 1 Start

na
30%
Stage 2 Issue for Internal Discipline check

er
nt
Man-Hour Concrete Structures Work Step 10%
Stage 3 Issued for Comment

-I
20%
Stage 4 Issued for Approval

AS
20%
Stage 5 Issue for Detail Design
N
10%
O
TR

Stage 6 Final Update


PE

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each document is calculated as per following stages:


Man-Hour Structural Steel Work Step
WF for
Stages Description
Stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 78 of 456

10%
Stage 1 Start
40%
Stage 2 Issued for Comment
20%
Stage 3 Issued for Approval

y
nl
20%
Stage 4 Issue for Detail Design

O
10%

se
Stage 5 Final Update

lU
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

na
Progress of each calculation note is calculated as per following stages:

er
nt
WF for
Stages Description
Stages

-I
10%
Stage 1 Start

AS
Man-Hour Calculation Notes Work Step
80%
Stage 2 Issue for Information
N
O
10%
TR

Stage 3 Final Update


PE

Control Account JI: Pipelines

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour Drawings Work Step Progress of each drawing is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 79 of 456

WF for
Stages Description
Stages
10%
Stage 1 Start
15%
Stage 2 Issued for Inter discipline check

y
nl
25%
Stage 3 Issued for Comment

O
20%

se
Stage 4 Issued for Approval

lU
20%
Stage 5 Issue for Detail Design

na
10%
Stage 6 Final Update

er
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula

nt
Document

-I
Man-Hour Specifications Work Step Progress of each document is calculated as per following stages:

AS
WF for
Stages Description
Stages
N
10%
O
Stage 1 Start
TR

40%
Stage 2 Issued for comment
PE

30%
Stage 3 Issued for Approval

20%
Stage 4 Issue for Construction
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 80 of 456

Progress of each material requisition is calculated as per following stages:

WF for
Stages Description
Stages
10%
Stage 1 Start

y
Man-Hour MR Work Step

nl
40%
Stage 2 Issued for Inquiry

O
40%

se
Stage 3 Issued for Purchase

lU
10%
Stage 4 Final Update

na
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

er
nt
Progress of each document is calculated as per following stages:

-I
WF for
Stages Description
Stages

AS
Man-Hour Reports Work Step 10%
N Stage 1 Start
O
80%
Stage 2 Issued for Information
TR

10%
Stage 3 Final Update
PE

Control Account JJ: Architecture

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour Drawings Work Step Progress of each drawing is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 81 of 456

WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check

y
nl
10%
Stage 3 Issued for Comment

O
20%
Stage 4 Issued for Approval

se
lU
Approved for Construction / Approved for Design / 20%
Stage 5
Approved for Bidding

na
10%
Stage 6 Final Update

er
Description of

nt
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

-I
Progress of each spec is calculated as per following stages:

AS
WF for
Stages Description
Stages
N
10%
O
Stage 1 Start
TR

Man-Hour Specifications Work Step


40%
Stage 2 Issued for comment
PE

30%
Stage 3 Issued for Approval

20%
Stage 5 Issue for Construction
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 82 of 456

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each MTO is calculated as per following stages:
WF for
Stages Description
Stages
Man-Hour MTO Work Step
Stage 1 Start 10%

Stage 2 Final Update 90%

Control Account JK: HSE

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each Drawing is calculated as per following stages:

WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check
Man-Hour Drawings Work Step
10%
Stage 3 Issued for Comment
20%
Stage 4 Issued for Approval

Approved for Construction / Approved for Design / 20%


Stage 5
Approved for Bidding
10%
Stage 6 Final Update
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 83 of 456

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each spec is calculated as per following stages:

WF for
Stages Description
Stages

10%
Stage 1 Start
Man-Hour Specifications Work Step

40%
Stage 2 Issued for comment

30%
Stage 3 Issued for Approval

20%
Stage 4 Issue for Construction

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Man-Hour
Progress of each Material Requisition is calculated as per following stages:
MR Work Step
WF for
Stages Description
Stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 84 of 456

10%
Stage 1 Start

40%
Stage 2 Issued for Inquiry

40%
Stage 3 Issued for Purchase

10%
Stage 4 Final Update

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each procedure is calculated as per following stages:

WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour Procedures Work Step
50%
Stage 2 Issued for Review
20%
Stage 3 Issued for Construction
20%
Stage 4 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Man-Hour Calculation Notes Work Step Progress of each calculation note is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 85 of 456

WF for
Stages Description
Stages
10%
Stage 1 Start

80%
Stage 2 Issue for Information

10%
Stage 3 Final Update

Control Account JL: HVAC


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each drawing is calculated as per following stages:


WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check
Man-Hour Drawings Work Step 10%
Stage 3 Issued for Comment
20%
Stage 4 Issued for Approval
Approved for Construction / Approved for Design / 20%
Stage 5
Approved for Bidding
10%
Stage 6 Final Update
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 86 of 456

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each datasheet is calculated as per following stages:


WF for
Stages Description
Stages
Man-Hour Datasheets Work Step
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check
10%
Stage 3 Issued for comment
30%
Stage 4 Issued for Approval
20%
Stage 5 Approve for Construction
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each material requisition is calculated as per following stages:
WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour MR Work Step 40%
Stage 2 Issued for Inquiry
40%
Stage 3 Issued for Purchase

10%
Stage 4 Final Update
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 87 of 456

Control Account JM: Final Documentation


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Final Book or Bound 10%
Man-Hour Work Step Stage 1 Start
Book
80%
Stage 2 Issued for Information
10%
Stage 3 Final Update

PMT DELIVERABLES
Control
Weight Factor Description of
Account Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Control Account
No.
Work Step Description WF for Stages
1) For Level 1, 2, 3,
and 4 (Phase, Step 1 SRA session conducting 30%
Contracting, Sub
Schedule & Cost SRA Report Issuance
KA phase, and Facility) Work Step Step 2 20%
QRA
is Cost
Step 3 CRA session conducting 30%

Step 4 CRA Report Issuance 20%


2) For Level 5 Work Step Description WF for Stages
KB (Control Account) Economics Analysis Work Step
is Man-Hour Step 1 Run Economic Analysis 60%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 88 of 456

Step 2 Economic Report 40%

Work Step Description WF for Stages

KD 3) For Level 6 Approvals Milestone Step 1 Start 5%


(Activity or
Step 2 Finish 95%
Document level) is
Man-Hour Progress of FDP Preparation is calculated as per following deliverables based
on required Man-Hours for each project:
Man- Weight
No FDP Items
Hour (%)
1 FDP Preparation
1.1 Geophysics 880 12.50

Deliverable 1.2 Petro physics 800 11.36


KE FDP Preparation
List 1.3 Geology and Static Modelling 1480 21.02
1.4 Reservoir Engineering 1040 14.77
1.5 Production Technology 1240 17.61
1.6 Drilling Engineering 320 4.55
1.7 Facilities Engineering 1120 15.91
1.8 Economics 160 2.27
TOTAL PROGRESS ACHIEVEMENT 7040 100

Work Step Description WF for Stages


OCS Submission
KF OCS Work Step Step 1 60%

OCS Approval
Step 2 40%

KG Project Sanction Work Step Work Step Description WF for Stages


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 89 of 456

Step 1 Advance Funding Submission 60%


Sanction Approval
Step 2 40%

Progress of Planning Package Preparation is calculated as per following


deliverables based on required Man-Hours:
Man- Weight
No Planning Package Items
Hour (%)
I. PCPP Compliance 632 90
1.1 Planning and Scheduling 424 67
1.1.1 Project Scope of Work and Objectives 16 2.53
1.1.2 Schedule Basis Memorandum (SBM) 24 3.79
1.1.3 Work Breakdown Structure (WBS) 24 3.79
Organization Breakdown Structure 24 3.79
1.1.4 (OBS)
Project Management Team (PMT)
40 6.32
Deliverable 1.1.5 Manpower Plan
KH PCPP Preparation Project Execution Schedule (Baseline
List 104 16.43
1.1.6 Schedule)
1.1.7 Quantitative Risk Analysis (QRA) 80 12.64
1.1.8 Critical Path 16 2.53
1.1.9 Progress Base 24 3.79
1.1.10 Progress S-Curve 16 2.53
1.1.11 Progress Measurement Format 16 2.53
1.1.12 Resource Plan 16 2.53
1.1.13 Project Roadmap 8 1.26
1.1.14 Project Progress Report 8 1.26
1.1.15 Project Close-Out Report 8 1.26

1.2. Cost Control 208 23


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 90 of 456

1.2.1 Cost Breakdown Structure (CBS) 8 0.88


1.2.2 Project Total Budget 24 2.65
64 7.08
1.2.3 Work Program & Budget (WPB)
1.2.4 Corporate Plan & Budget (CPB) 64 7.08

1.2.5 Approved For Expenditure


8 0.88
Additional Budget (Budget Transfer and
8 0.88
1.2.6 Supplementary Budget)
1.2.7 Additional Budget Request 8 0.88
1.2.8 Change Order Register 8 0.88
1.2.9 Monthly Cost Report 8 0.88

1.2.10 Project Close-Out Report


8 0.88
II. TP & PMO
Endorsement
35 5
PCPP Reviewed and Endorsed by TP
35 5
2.1 and PMO (DPP)
III. PM
Approval
35 5

3.1 PCPP Reviewed and Approved by PM 35 5


TOTAL PROGRESS ACHIEVEMENT
702 100
(I,II & III)

DETAIL WELL DESIGN


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 91 of 456

Weight Factor Calculation Control Description of Control


Methodology Calculation Description, Detailed Weight Factor or Formula
Base Account No. Account
Physical progress for Preparation Drilling Program shall be
calculated by the milestone method and as per following:
Preparation Drilling Work WF for
LA Milestone Description
Program Step Stages
Step 1 Start 5%
1) For Level 1, 2, 3, and 4 Step 2 Finish 95%
(Phase, Contracting, Sub
phase, and Facility) is Cost Physical progress for Conducting DRC01 shall be calculated by
the milestone method and as per following:
2) For Level 5 (Control
LB Conducting DRC01 Milestone Work WF for
Account) is Man-Hour Description
Step Stages
3) For Level 6 (Activity or Step 1 Start 5%
Document level) is Man- Step 2 Finish 95%
Hour
Physical progress for Conducting PTPRC01 shall be calculated
by the milestone method and as per following:
Work WF for
LC Conducting PTPRC01 Milestone Description
Step Stages
Step 1 Start 5%
Step 2 Finish 95%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 92 of 456

APPENDIX 5: Upstream PMS-DETAIL ENGINEERING

Control Account NA: General


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of general procedures calculated as per following stages:
WF for
Stages Description
Stages

Man-Hour All Type of documents Work Step Stage 1 Start 10%

Stage 2 Issued for Information 80%

Stage 4 Final Update 10%

Control Account NG: Instrument &


Telecommunication
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each MR for main items is calculated as per following stages:

WF for
Stages Description
Stages
MR for Main
Man-Hour Work Step 10%
Items Stage 1 Start
40%
Stage 2 Issued for Inquiry
40%
Stage 3 Issued for Purchase
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 93 of 456

10%
Stage 4 Final Update

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each document is calculated as per following stages:

WF for
Stages Description
Stages
10%
Man-Hour Specifications Work Step Stage 1 Start
40%
Stage 2 Issued for comment
30%
Stage 3 Issued for Approval
20%
Stage 4 Approve for Construction
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour Datasheets Work Step
40%
Stage 2 Issued for comment
30%
Stage 3 Issued for Approval
20%
Stage 4 Approve for Construction
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 94 of 456

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Man-Hour Drawings Work Step Stage 2 Issue for Internal Discipline check
10%
Stage 3 Issued for Inquiry
40%
Stage 4 Issued for Purchase
10%
Stage 5 Final Update

Control Account NH: Civil

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each drawing is calculated as per following stages:

WF for
Stages Description
Stages
Installation 10%
Man-Hour Work Step Stage 1 Start
Drawings
30%
Stage 2 Issue for Internal Discipline check
20%
Stage 2 Issued for Comment
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 95 of 456

10%
Stage 3 Issued for Approval

Approved for Construction / Approved for Design / 20%


Stage 4
Approved for Bidding
10%
Stage 5 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each concrete structure is calculated as per following stages:

WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check
Concrete 10%
Man-Hour Work Step Stage 3 Issued for Comment
Structures
20%
Stage 4 Issued for Approval
Approved for Construction / Approved for Design / 20%
Stage 5
Approved for Bidding
10%
Stage 6 Final Update

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Structural
Man-Hour Work Step Progress of each document is calculated as per following stages:
Steel
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 96 of 456

WF for
Stages Description
Stages
10%
Stage 1 Start
40%
Stage 2 Issued for Comment
20%
Stage 3 Issued for Approval

Approved for Construction / Approved for Design / 20%


Stage 4
Approved for Bidding
10%
Stage 5 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document

Progress of each calculation note is calculated as per following stages:

WF for
Stages Description
Stages
Calculation
Man-Hour Work Step 10%
Notes Stage 1 Start
80%
Stage 2 Issue for Information
10%
Stage 3 Final Update

Control Account NI: Pipelines

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour Drawings Work Step Progress of each drawing is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 97 of 456

WF for
Stages Description
Stages
10%
Stage 1 Start
40%
Stage 2 Issued for Comment
20%
Stage 3 Issued for Approval
Approved for Construction / Approved for Design / 20%
Stage 4
Approved for Bidding
10%
Stage 5 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour Specifications Work Step
40%
Stage 2 Issued for comment
30%
Stage 3 Issued for Approval
20%
Stage 4 Issue for Construction
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour MR Work Step Progress of each material requisition is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 98 of 456

WF for
Stages Description
Stages
10%
Stage 1 Start
40%
Stage 2 Issued for Inquiry
40%
Stage 3 Issued for Purchase
10%
Stage 4 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages

Man-Hour Reports Work Step 10%


Stage 1 Start

80%
Stage 2 Issued for Information
10%
Stage 3 Final Update

Control Account NJ: Architecture

Weight Factor Description of


Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document
Man-Hour Drawings Work Step Progress of each drawing is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 99 of 456

WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check
10%
Stage 3 Issued for Comment
20%
Stage 4 Issued for Approval

Approved for Construction / Approved for Design / 20%


Stage 5
Approved for Bidding

10%
Stage 6 Final Update

Weight Factor Description of


Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document
Progress of each spec is calculated as per following stages:
WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour Specifications Work Step 40%
Stage 2 Issued for comment
30%
Stage 3 Issued for Approval

20%
Stage 5 Issue for Construction

Weight Factor Description of


Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 100 of 456

Progress of each MTO is calculated as per following stages:


WF for
Stages Description
Man-Hour MTO Work Step Stages
Stage 1 Start 10%

Stage 2 Final Update 90%

Control Account NK: HSE

Weight Factor Description of


Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document

Progress of each Drawing is calculated as per following stages:

WF for
Stages Description
Stages

10%
Stage 1 Start
30%
Man-Hour Drawings Work Step Stage 2 Issue for Internal Discipline check
10%
Stage 3 Issued for Comment
20%
Stage 4 Issued for Approval
Approved for Construction / Approved for Design / 20%
Stage 5
Approved for Bidding
10%
Stage 6 Final Update
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 101 of 456

Weight Factor Description of


Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document
Progress of each spec is calculated as per following stages:
WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour Specifications Work Step
40%
Stage 2 Issued for comment
30%
Stage 3 Issued for Approval
20%
Stage 4 Issue for Construction

Weight Factor Description of


Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document

Progress of each Material Requisition is calculated as per following stages:


WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour MR Work Step 40%
Stage 2 Issued for Inquiry
40%
Stage 3 Issued for Purchase

10%
Stage 4 Final Update

Weight Factor Description of


Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 102 of 456

Progress of each procedure is calculated as per following stages:

WF for
Stages Description
Stages
Stage 1 Start 10%
Man-Hour Procedures Work Step
Stage 2 Issued for Review 50%

Stage 3 Issued for Construction 20%

Stage 4 Final Update 20%


Weight Factor Description of
Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document

Progress of each calculation note is calculated as per following stages:

WF for
Stages Description
Stages
Man-Hour Calculation Notes Work Step
Stage 1 Start 10%

Stage 2 Issue for Information 80%

Stage 3 Final Update 10%


Control Account NL:
HVAC
Weight Factor Description of
Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document

Man-Hour Drawings Work Step Progress of each drawing is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 103 of 456

WF for
Stages Description
Stages
Stage 1 Start 10%

Stage 2 Issue for Internal Discipline check 30%

Stage 3 Issued for Comment 10%

Stage 4 Issued for Approval 20%


Approved for Construction / Approved for Design /
Stage 5 20%
Approved for Bidding

Stage 6 Final Update 10%

Weight Factor Description of


Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document

Progress of each datasheet is calculated as per following stages:

WF for
Stages Description
Stages

Stage 1 Start 10%


Man-Hour Datasheets Work Step
Stage 2 Issue for Internal Discipline check 30%

Stage 3 Issued for comment 10%

Stage 4 Issued for Approval 30%

Stage 5 Approve for Construction 20%


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 104 of 456

Weight Factor Description of


Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document

Progress of each material requisition is calculated as per following stages:

WF for
Stages Description
Stages
Stage 1 Start 10%
Man-Hour MR Work Step
Stage 2 Issued for Inquiry 40%

Stage 3 Issued for Purchase 40%

Stage 4 Final Update 10%

Control Account NM: Final Documentation


Weight Factor Description of
Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Final Book or Bound Stage 1 Start 10%
Man-Hour Work Step
Book
Stage 2 Issued for Information 80%
10%
Stage 3 Final Update
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 105 of 456

APPENDIX 6: Upstream PMS- PROCUREMENT SUPPLY BY COMPANY


Procurement is divided to two parts which includes major packages and other equipment. Work step and weight factor of Manufacturing and delivery work
package for both parts will be different.

Work Packages: Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Major Packages (Compressor, GTG, Pumps, De-Hydration, etc.)

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress of each pre-bidding item is calculated as per following stages:

WF for
Stages Description
Stages
Tender Plan
Stage 1 -as per each equipment, if the Tender Plan is issued 30%
411 10% Work Step equal to 100% otherwise 0%
Pre-Bidding
PIR
Stage 2 -as per each equipment, if the PIR is performed equal to 40%
100% otherwise 0%
ITB
Stage 3 -as per each equipment, if the ITB is issued equal to 30%
100% otherwise 0%

Progress of each Bidding item is calculated as per following stages:


Bid/ Evaluate/ Award of
412 20% Work Step
Contract WF for
Stages Description
Stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 106 of 456

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
RFQ
Stage 1 -as per each equipment, if the Inquiry is issued out to 10%
vendor/Manufacturer equal to 100% otherwise 0%

TBE
Stage 2 -as per each equipment, if the TBE is performed equal to 25%
100% otherwise 0%

CBE
Stage 3 -as per each equipment, if the CBE is performed equal 25%
to 100% otherwise 0%

Issue of Purchase Order


Stage 4 -as per each equipment, if the vendor is selected and 40%
PO place equal to 100% otherwise 0%

Progress of each procurement item is calculated as per following stages:

WF for
Stages Description
Stages
Manufacturing & Delivery of
413 70% Work Step Engineering
Major Equipment
Stage 1 -If step is done the value would be 100 and if it hasn’t 7%
been done yet, it would be 0.
Procurement
Stage 2 - If step is done the value would be 100 and if it hasn’t 40%
been done yet, it would be 0.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 107 of 456

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Fabrication
30%
Stage 3 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Final Testing (FAT)
5%
Stage 4 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
FOB
3%
Stage 5 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Port
10%
Stage 6 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Site
3%
Stage 7 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Close out Report
2%
Stage 8 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 108 of 456

Work Packages: Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Other Equipment (Valves, Wellhead, Casing, bulk material, etc.)

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress of each pre-bidding item is calculated as per following stages:

WF for
Stages Description
Stages
Tender Plan
Stage 1 -as per each equipment, if the Tender Plan is issued out 30%
411 10% Work Step to vendor/manufacturer equal to 100% otherwise 0%
Pre-Bidding
PIR
Stage 2 -as per each equipment, if the PIR is performed equal to 40%
100% otherwise 0%
ITB
Stage 3 -as per each equipment, if the ITB is issued equal to 30%
100% otherwise 0%

Progress of each Bidding item is calculated as per following stages:

WF for
Stages Description
Bid/ Evaluate/ Award of Stages
412 20% Work Step
Contract
RFQ
Stage 1 -as per each equipment, if the Inquiry is issued equal to 10%
100% otherwise 0%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 109 of 456

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
TBE
Stage 2 -as per each equipment, if the TBE is performed equal to 25%
100% otherwise 0%
CBE
Stage 3 -as per each equipment, if the CBE is performed equal 25%
to 100% otherwise 0%
Issue of Purchase Order
Stage 4 -as per each equipment, if the vendor is selected and 40%
PO place equal to 100% otherwise 0%
Progress of each manufacturing item is calculated as per following stages:

WF for
Stages Description
Stages
FOB
Manufacturing & Delivery of Stage 1 - If step is done the value would be 100 and if it hasn’t 85%
413 70% Work Step been done yet, it would be 0.
Bulk Material
Delivered at Port
Stage 2 - If step is done the value would be 100 and if it hasn’t 10%
been done yet, it would be 0.
Delivered at Site
5%
Stage 3 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 110 of 456

APPENDIX 7: Upstream PMS- PROCUREMENT


Procurement is divided to two parts which includes major packages and bulk material. Work step and weight factor of Manufacturing and delivery work
package for both parts will be different.

Work Packages: Bid/Evaluate/Award, Manufacturing & Delivery


Major Packages (Compressor, GTG, Pumps, De-Hydration, etc.)

Work Packages : Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress of each Bidding item is calculated as per following stages:

WF for
Stages Description
Stages

RFQ
Stage 1 -as per each equipment, if the Inquiry is issued equal to 10%
100% otherwise 0%

Bid/ Evaluate/ Award of TBE


612 20% Work Step
Contract Stage 2 -as per each equipment, if the TBE is performed equal to 25%
100% otherwise 0%

CBE
Stage 3 -as per each equipment, if the CBE is performed equal 25%
to 100% otherwise 0%

Issue of Purchase Order


Stage 4 -as per each equipment, if the vendor is selected and 40%
PO place equal to 100% otherwise 0%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 111 of 456

Work Packages : Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress of each procurement item is calculated as per following stages:

WF for
Stages Description
Stages
Engineering
Stage 1 -If step is done the value would be 100 and if it hasn’t 7%
been done yet, it would be 0.
Procurement
Stage 2 - If step is done the value would be 100 and if it hasn’t 40%
been done yet, it would be 0.
Fabrication
30%
Manufacturing and Delivery of Stage 3 - If step is done the value would be 100 and if it hasn’t
613 80% Work Step been done yet, it would be 0.
Major Equipment
Final Testing (FAT)
5%
Stage 4 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
FOB
3%
Stage 5 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Site
13%
Stage 7 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Close out Report
2%
Stage 8 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 112 of 456

Work Packages: Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Bulk Material (Valves, Wellhead, Casing, etc.)

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.

Progress of each Bidding item is calculated as per following stages:

WF for
Stages Description
Stages
RFQ
-as per each equipment, if the Inquiry is issued equal to
Stage 1 10%
100% otherwise 0%

TBE
Bid/ Evaluate/ Award of -as per each equipment, if the TBE is performed equal to
612 20% Work Step Stage 2 25%
Contract 100% otherwise 0%

CBE
-as per each equipment, if the CBE is performed equal
Stage 3 25%
to 100% otherwise 0%

Issue of Purchase Order


-as per each equipment, if the vendor is selected and
Stage 4 40%
PO place equal to 100% otherwise 0%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 113 of 456

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.

Progress of each manufacturing item is calculated as per following stages:

WF for
Stages Description
Stages
FOB
85.0%
Manufacturing & Delivery of Stage 1 - If step is done the value would be 100 and if it hasn’t
613 80% Work Step been done yet, it would be 0.
Bulk Material
Delivered at Port
10.0%
Stage 2 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Site
5.0%
Stage 3 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 114 of 456

APPENDIX 8: Upstream PMS-FABRICATION


WORK PACKAGE 1: Front End Activities/Mobilisation
Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
Progress is calculated based on Front End Activities and measured as per
following stages:
WP - 711 Mobilization of PMT Work Step Description WF for stages
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Front End Activities and measured as per
following stages:
WP - 712 Project Plan. & Monitoring Format Work Step Description WF for stages
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Front End Activities and measured as per
PA following stages:
WP - 713 Fabrication of Framing / Support Foundation Work Step Description WF for stages
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Front End Activities and measured as per
following stages:
Work Step Description WF for stages
Step 1 Tender 80.00%
WP - 714 Mobilization of NDT Source Inspection
Step 2 Award 10.00%

Step 3 Mobilise (Ready to commence work) 10.00%


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 115 of 456

Progress is calculated based on Front End Activities and measured as per


following stages:
WP - 715 Mobilization of Structural Sub-Contractor Work Step Description WF for stages
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Front End Activities and measured as per
following stages:
Mobilization of Piping / Plumbing Sub- Work Step Description WF for stages
WP - 716 Contractor
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Front End Activities and measured as per
following stages:
WP - 717 Mobilization of Painting Sub-Contractor Work Step Description WF for stages
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Front End Activities and measured as per
following stages:
WP - 718 Mobilization of E&I Sub-Contractor Work Step Description WF for stages
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Front End Activities and measured as per
following stages:
Mobilization of HVAC / Ducting Sub- Work Step Description WF for stages
WP - 719 Contractor
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Front End Activities and measured as per
following stages:
WP - 720 Mobilization of Architectural Sub-Contractor
Work Step Description WF for stages
Step 1 Completed 80.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 116 of 456

Step 2 Accepted 20.00%


Progress is calculated based on Front End Activities and measured as per
following stages:
Test Panel / Coating System Qualification
WP - 721 Test Work Step Description WF for stages
(Number of Test Panels) Step 1 Tested 70.00%
Step 2 Accepted 30.00%
WORK PACKAGE 2: Yard Preparation
Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
Progress is calculated based on Civil & Yard Preparation for Jacket and
measured as per following stages:
PB 722 Yard Preparation for Jacket Work Step Description WF for stages
Step 1 Mobilisation 20.00%
Step 2 Erection Area 80.00%
Progress is calculated based on Civil & Yard Preparation for Topsides and
measured as per following stages:
Yard Preparation for Topsides Work Step Description WF for stages
Step 1 Mobilisation 20.00%
Step 2 Erection Area 80.00%
Progress is calculated based on Yard Preparation and measured as per following
stages:
Work Step Description WF for stages
Other Yard Preparation Step 1 Welding / NDT 3.00%
Step 2 Structural Works 64.00%
Step 3 Equipment Installation 3.00%
Step 4 Piping pre-fabrication , Erection & Hook Up 11.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 117 of 456

Step 5 Architectural Works 2.00%


Step 6 Mechanical Works 5.00%
Step 7 Electrical Works 2.00%
Step 8 Instrumentation Works 2.00%
Step 9 Telecommunication Telemetry works 1.00%
Step 10 Safety Works (if required) 1.00%
Step 11 Weighing, Load Out & Sea Fastening 6.00%
WORK PACKAGE 3: Fabrication Engineering /Shop Drawings
Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
WP-723 Shop Drawing

Progress is calculated based on issued structural documents to the COMPANY


and measured as per following stages:
Work Step Description WF for stages
WP - 7232 Structural
Step 1 Start 10.00%
Step 2 Issued for Review 40.00%
Step 3 Issued for Construction 50.00%
PC Progress is calculated based on issued Piping / Plumbing documents to the
COMPANY and measured as per following stages:
Work Step Description WF for stages
WP - 7233 Piping / Plumbing
Step 1 Start 10.00%
Step 2 Issued for Review 40.00%
Step 3 Issued for Construction 50.00%
Progress is calculated based on issued Pipeline documents to the COMPANY and
WP - 7234 Pipeline measured as per following stages:
Work Step Description WF for stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 118 of 456

Step 1 Start 10.00%


Step 2 Issued for Review 40.00%
Step 3 Issued for Construction 50.00%
Progress is calculated based on issued Mechanical documents to the COMPANY
and measured as per following stages:
Work Step Description WF for stages
WP - 7235 Mechanical
Step 1 Start 10.00%
Step 2 Issued for Review 40.00%
Step 3 Issued for Construction 50.00%
Progress is calculated based on issued Electrical documents to the COMPANY
and measured as per following stages:
Work Step Description WF for stages
WP - 7236 Electrical
Step 1 Start 10.00%
Step 2 Issued for Review 40.00%
Step 3 Issued for Construction 50.00%
Progress is calculated based on issued Instrument & Communication documents
to the COMPANY and measured as per following stages:
Work Step Description WF for stages
WP - 7237 Instrument & Communication
Step 1 Start 10.00%
Step 2 Issued for Review 40.00%
Step 3 Issued for Construction 50.00%
Progress is calculated based on issued HVAV/Ducting documents to the
COMPANY and measured as per following stages:
Work Step Description WF for stages
WP - 7238 HVAC / Ducting
Step 1 Start 10.00%
Step 2 Issued for Review 40.00%
Step 3 Issued for Construction 50.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 119 of 456

Progress is calculated based on issued Architectural documents to the


COMPANY and measured as per following stages:
Work Step Description WF for stages
WP - 7239 Architectural
Step 1 Start 10.00%
Step 2 Issued for Review 40.00%
Step 3 Issued for Construction 50.00%
Progress is calculated based on issued Others (Paints, Anodes, Fire & Safety &
etc.) documents to the COMPANY and measured as per following stages:
Work Step Description WF for stages
WP - 72310 Other (Paint, Anodes, Fire & Safety etc.)
Step 1 Start 10.00%
Step 2 Issued for Review 40.00%
Step 3 Issued for Construction 50.00%
Progress is calculated based on issued procedures to the COMPANY and
measured as per following stages:
WP-724 Fabrication Procedure
Step 1 Submitted 80.00%
Step 2 Approved 20.00%

WORK PACKAGE 4: Yard Fabrication - Jacket ( WHP-CPP , Riser & LQ)

Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
Jacket Structure , Buoyancy Tank,
Diaphragm Installation and Boat
Landing
WP-726 to W-
PD Fabrication Tubular - (Number of Dia Progress is calculated based on Fabrication of Tubular and measured as per
734
In per Tubular Size) following stages:
Work Step Description WF for stages
1. 8 in. and below (200mm and Below)
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 120 of 456

2. 10 in. - 24 in (250mm - 400mm) Step 1 Mark & Cut 15.00%

3. 26 in. - 40 in (650mm - 1000mm) Step 2 Fit Up 40.00%

4. 42 in. - 56 in (1050mm - 1400mm) Step 3 Welding 30.00%

5. 58 in. - 80 in (1450mm - 2000mm) Step 4 NDT & Dimensional Report Acceptance 15.00%
Fabrication Structural Members – non-
Progress is calculated based on Fabrication of Structural members and
Tabular (Weld Length per Structural
measured as per following stages:
Member size)
Work Step Description WF for stages
Step 1 Mark & Cut 15.00%
Non-Tabular & Miscellaneous Step 2 Fit Up 40.00%
Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Rolling of Cans - Tubular - (Number of Dia In per Tubular Size)
Progress is calculated based on Rolling of cans and measured as per following
stages:
Work Step Description WF for stages
Rolling of Cans (No. of Plates
Step 1 Rolled 20.00%
required for Tubular)
Step 2 Fit Up 25.00%
Step 3 Welded 30.00%
Step 4 NDT or Acceptance 25.00%
Erection - (Number of Joints/Panels)
Progress is calculated based on Installation / Erection and measured as per
following stages:
Erection ( Number of Joint Panels) Work Step Description WF for stages
Step 1 Lift & Position 20.00%
Step 2 Fit Up 30.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 121 of 456

Step 3 Welding 40.00%


Step 4 NDT & Acceptance 10.00%
Trial Fit and Weighing (Number of Handrails/Stairways/Boat landing & Etc.)
Progress is calculated based on Trial Fit / Weighing and measured as per
following stages:
Trial Fit and Weighing (Number of Work Step Description WF for stages
Handrails/Stairways/Boat landing & Etc.)
Step 1 Trial Fit / Weighing 80.00%
Step 2 Acceptance 20.00%
Progress is calculated based on Pipe Support Fabrication and measured as per
following stages:
Work Step Description WF for stages
Pipe support Fabrication Step 1 Mark & Cut 15.00%
Step 2 Fit Up 40.00%
Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Pipe Support Fabrication and measured as per
following stages:
Work Step Description WF for stages
Pipework Fabrication Step 1 Mark & Cut 15.00%
Step 2 Fit Up 40.00%
Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Pipe Support Fabrication and measured as per
following stages:
Work Step Description WF for stages
Pipe support Installation Step 1 Lift & Position 10.00%
Step 2 Fit Up 30.00%
Step 3 Welding 45.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 122 of 456

Step 4 NDT & Acceptance 15.00%


Progress is calculated based on Pipe Support Fabrication and measured as per
following stages:
Work Step Description WF for stages
Pipework Installation Step 1 Lift & Position 15.00%
Step 2 Fit Up 25.00%
Step 3 Welding 45.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Erection/Installation and measured as per
following stages:
Valve Leak Test Work Step Description WF for stages
Step 1 Complete - No. of Pieces 90.00%
Step 2 Acceptance - No. of Pcs 10.00%
Progress is calculated based on Erection/Installation and measured as per
following stages:
Work Step Description WF for stages
Diaphragm Pneumatic Leak Test Step 1 Complete - No. of Pieces 90.00%
Step 2 Acceptance - No. of Pcs 10.00%

Progress is calculated based on Erection/Installation and measured as per


following stages:
Work Step Description WF for stages
Buoyancy Tank Leak Test
Step 1 Complete - No. of Pieces 90.00%

Step 2 Acceptance - No. of Pcs 10.00%

Progress is calculated based on Erection/Installation and measured as per


Valve Installations
following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 123 of 456

Work Step Description WF for stages


Step 1 Complete - No. of Pieces 90.00%
Step 2 Acceptance - No. of Pcs 10.00%
Progress is calculated based on Erection/Installation and measured as per
following stages:
Flushing & Hydro testing (No. of Work Step Description WF for stages
Packages Complete with P & ID and ISO Step 1 Flushing 30.00%
Drawings)
Step 2 Hydro test 50.00%
Step 3 Acceptance 20.00%
Others - Structural
Fabrication
Fabrication of Anodes Casing/Transition Progress is calculated based on Installation / Erection and measured as per
Pieces/Gratings/Riser/Caissons/Mud following stages:
mat / Knee Braces/Surfer Work Step Description WF for stages
Landing/Levelling Trunnions/Lifting Pad Step 1 Mark & Cut 15.00%
eyes/Barge Bumpers/Grouting Step 2 Fit Up 40.00%
Transition Pieces/Sea Water Reject
Step 3 Welding 30.00%
Protector/Riser clamp / Skirt transition
caps/ Buoyancy tank/ boat landing Step 4 NDT & Acceptance 15.00%
Installation
Installation of Anodes Casing/Transition Progress is calculated based on Installation / Erection and measured as per
Pieces/Gratings/Riser/Caissons/Mud following stages:
mat / Knee Braces/Surfer Work Step Description WF for stages
Landing/Levelling Trunnions/Lifting Pad Step 1 Lift & Position 10.00%
eyes/Barge Bumpers/Grouting Step 2 Fit Up 30.00%
Transition Pieces/Sea Water Reject
Step 3 Welding 45.00%
Protector/Riser clamp & Skirt transition
caps/ diaphragm installation/buoyancy Step 4 NDT & Acceptance 15.00%
tank
Blasting & Painting
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 124 of 456

Progress is calculated based on Blast/ Painting & Coating and measured as per
following stages:
Work Step Description WF for stages
One Coat System (Area)
Step 1 Blasting 50.00%
Step 2 Final Coating 45.00%
Step 3 Acceptance 5.00%
WORK PACKAGE 5: Yard Fabrication - Topside A ( WHP, RISER & CPP,
Piping) Top Deck ,Main Deck, Mezzanine Deck & Cellar Deck
Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
Structural - Fabrication (Plate Girder/Nodes)
Fabrication Tubular - (Number of Dia Progress is calculated based on Fabrication of Tubular and measured as per
In per Tubular Size) following stages:
1. 8 in. and below (200mm and Below) Work Step Description WF for stages
2. 10 in. - 24 in (250mm - 400mm) Step 1 Mark & Cut 15.00%
3. 26 in. - 40 in (650mm - 1000mm) Step 2 Fit Up 40.00%
4. 42 in. - 56 in (1050mm - 1400mm) Step 3 Welding 30.00%
5. 58 in. - 80 in (1450mm - 2000mm) Step 4 NDT & Acceptance 15.00%
WP-726 to W-
734 Fabrication Structural Members -
Progress is calculated based on Fabrication of Structural members and
(Weld Length per Structural Member
measured as per following stages:
size)
1. W8 and Below Work Step Description WF for stages
2. W10 - W18 Step 1 Mark & Cut 15.00%
3. W21 - W27 Step 2 Fit Up 40.00%
4. W30 - W40 Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Erection - (Number of Joints/Panels)
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 125 of 456

Progress is calculated based on Installation / Erection and measured as per


following stages:
Work Step Description WF for stages
Erection ( Number of Joint Panels) Step 1 Lift & Position 20.00%
Step 2 Fit Up 30.00%
Step 3 Welding 40.00%
Step 4 NDT & Acceptance 10.00%
Trial Fit and Weighing (Number of Handrails/Stairways/Boat landing & Etc.)
Progress is calculated based on Trial Fit / Weighing and measured as per
following stages:
Trial Fit and Weighing (Number of Work Step Description WF for stages
Handrails/Stairways/Boat landing & Etc.)
Step 1 Trial Fit / Weighing 80.00%
Step 2 Acceptance 20.00%
Progress is calculated based on Pipe Support Fabrication and measured as per
following stages:
Work Step Description WF for stages
Pipe support Fabrication Step 1 Mark & Cut 15.00%
Step 2 Fit Up 40.00%
Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Pipe Support Fabrication and measured as per
following stages:
Work Step Description WF for stages
Pipework Fabrication Step 1 Mark & Cut 15.00%
Step 2 Fit Up 40.00%
Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 126 of 456

Progress is calculated based on Pipe Support Fabrication and measured as per


following stages:
Work Step Description WF for stages
Pipe support Installation Step 1 Lift & Position 10.00%
Step 2 Fit Up 30.00%
Step 3 Welding 45.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Pipe Support Fabrication and measured as per
following stages:
Work Step Description WF for stages
Pipework Installation Step 1 Lift & Position 15.00%
Step 2 Fit Up 25.00%
Step 3 Welding 45.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Erection/Installation and measured as per
following stages:
Valve Leak Test Work Step Description WF for stages
Step 1 Complete - No. of Pieces 90.00%
Step 2 Acceptance - No. of Pcs 10.00%
Progress is calculated based on Erection/Installation and measured as per
following stages:
Valve Installations Work Step Description WF for stages
Step 1 Complete - No. of Pieces 90.00%
Step 2 Acceptance - No. of Pcs 10.00%
Progress is calculated based on Erection/Installation and measured as per
Flushing, Hydro testing and Acid following stages:
Cleaning (No. of Packages Complete Work Step Description WF for stages
with P & ID and ISO Drawings)
Step 1 Flushing 25.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 127 of 456

Step 2 Hydro test 45.00%


Step 3 Acid Cleaning 10.00%
Step 4 Acceptance 20.00%

Pipeline
Progress is calculated based on pipeline coating and measured as per following
Concrete stages:
Coating/External/Internal/Custom/Field Work Step Description WF for stages
Joint/Internal Field Joint Coating Step 1 Actual - No. of joints 90.00%
Step 2 Accepted- No of joints 10.00%
Mechanical (including Insulation)
Progress is calculated based on fabrication and measured as per following
stages:
Step 1 Mark & Cut 15.00%
Mechanical Equipment Support Step 2 Fit Up 40.00%
Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Installation and measured as per following
stages:
Work Step Description WF for stages
Mechanical Equipment Installation Step 1 Lift Up & Placement of Equipment Deck 40.00%
Step 2 Levelling/Alignment 25.00%
Step 3 Tie Down /Bolt tightening 25.00%
Step 4 Acceptance 10.00%
Progress is calculated based on Installation and measured as per following
stages:
Vessel / Piping Insulation Work Step Description WF for stages
Step 1 Complete - No. of Runs / Meter Run 90.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 128 of 456

Step 2 Acceptance - No. of Runs / Meter Run 10.00%


Electrical
Progress is calculated based on Fabrication and measured as per following
stages:
Work Step Description WF for stages
Fabrication of Electrical Support Step 1 Mark & Cut 15.00%
Step 2 Fit Up 40.00%
Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Installation and measured as per following
stages:
Electrical Cable tray/ Ladder/Conduits Work Step Description WF for stages
Installation ( No. of connection point)
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Erection/Installation and measured as per
following stages:
Electrical Cable Pulling (No. of Cable Work Step Description WF for stages
Runs)
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Erection/Installation and measured as per
following stages:
Dressing/Glanding/Tagging/(No of Work Step Description WF for stages
connection point)
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Installation and measured as per following
stages:
Electrical Lighting & Fixtures Installation Work Step Description WF for stages
Step 1 Preparatory Works 15.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 129 of 456

Step 2 Equipment fixtures Installation 50.00%


Step 3 Internal & Wirings and Coiling 25.00%
Step 4 Inspection & Acceptance 10.00%
Progress is calculated based on Installation and measured as per following
stages:
Work Step Description WF for stages
Field Electrical Device Installation (No. of Step 1 Support Preparatory works 10.00%
Units)
Step 2 Handling & Setting 45.00%
Step 3 Levelling & Fixing 30.00%
Step 4 Inspection & Acceptance 15.00%
Progress is calculated based on Erection/Installation and measured as per
following stages:
Work Step Description WF for stages
Installation of Support ( Electrical )
Step 1 Fit Up 30.00%
Step 2 Welding 55.00%
Step 3 Acceptance 15.00%
Instrument & Communication
Progress is calculated based on Fabrication and measured as per following
stages:
Work Step Description WF for stages
Fabrication of Instrument Support Step 1 Mark & Cut 15.00%
Step 2 Fit Up 40.00%
Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Installation and measured as per following
Instrument Cable tray/ Ladder/Conduits stages:
Installation ( No. of Meter runs) Work Step Description WF for stages
Step 1 Completed 80.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 130 of 456

Step 2 Accepted 20.00%


Progress is calculated based on Erection/Installation and measured as per
following stages:
Instrument Cable Pulling (No. of Cable Work Step Description WF for stages
Runs)
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Erection/Installation and measured as per
following stages:
Dressing/Glanding/Tagging/Termination Work Step Description WF for stages
(No of Meter Runs)
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Installation and measured as per following
stages:
Work Step Description WF for stages
Instrument Lighting & Fixtures Step 1 Preparatory Works 15.00%
Step 2 Equipment fixtures Installation 50.00%
Step 3 Internal & Wirings 25.00%
Step 4 Inspection & Acceptance 10.00%
Progress is calculated based on Installation and measured as per following
stages:
Work Step Description WF for stages
Field Instrument Device Installation (No. Step 1 Support Preparatory works 10.00%
of Units)
Step 2 Handling & Setting 45.00%
Step 3 Levelling & Fixing 30.00%
Step 4 Inspection & Acceptance 15.00%
Progress is calculated based on Erection/Installation and measured as per
Installation of Pipe Support
following stages:
( Instrument )
Work Step Description WF for stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 131 of 456

Step 1 Fit Up 30.00%


Step 2 Welding 55.00%
Step 3 Acceptance 15.00%
Progress is calculated based on Installation and measured as per following
stages:
Work Step Description WF for stages
Field Instrument Device Installation (No. Step 1 Support Preparatory works 10.00%
of Units)
Step 2 Handling & Setting 45.00%
Step 3 Levelling & Fixing 30.00%
Step 4 Inspection & Acceptance 15.00%
Progress is calculated based on Installation and measured as per following
stages:
Instrument Tubing / Leak Test Work Step Description WF for stages
Step 1 Complete - No. of loop 80.00%
Step 2 Acceptance - No. of loop 20.00%
Telephone and LAN Work Step Description WF for stages
Step 1 Installation of support frame 15.00%
Step 2 Installation of PABX 25.00%
PABX Installation Step 3 Installation of Batteries and accessories 15.00%
Step 4 Execution of connections 30.00%
Step 5 Tests & Acceptance 15.00%
Progress is calculated based on Telephone Sets - Any type installation and
measured as per following stages:
Work Step Description WF for stages
Telephone Sets - any type Step 1 Preparation of supports 10.00%
Installation
Step 2 Acoustic booth 30.00%
Step 3 Installation of telephone set 20.00%
Step 4 Wiring 30.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 132 of 456

Step 5 Final tests & Acceptance 10.00%


Progress is calculated based on loud speaker and measured as per following
Public Address & General Alarm
stages:
Work Step Description WF for stages
Step 1 Support preparation 5.00%
Step 2 Loud speaker installation 40.00%
Loud Speaker
Step 3 Wiring 30.00%
Step 4 Checks 5.00%
Step 5 Final tests 20.00%
Progress is calculated based on Public address console and measured as per
following stages:
Work Step Description WF for stages
Public address console Step 1 20.00%
Supports
Step 2 Installation/Connections 70.00%
Step 3 Tests / Checks 10.00%
Closed Circuit Television (CCTV) Progress is calculated based on CCTV and measured as per following stages:
Work Step Description WF for stages
Step 1 Support preparation 20.00%
Step 2 CCTV installation 25.00%
CCTV
Step 3 Wiring 30.00%
Step 4 Checks 5.00%
Step 5 Final tests 20.00%
Progress is calculated based on Insulation and measured as per following
stages:
Work Step Description WF for stages
CCTV Control System Step 1 20.00%
Supports
Step 2 Installation/Connections 70.00%
Step 3 Tests / Checks 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 133 of 456

Siren Progress is calculated based on Siren and measured as per following stages:
Work Step Description WF for stages
Step 1 Support preparation 20.00%
Siren Installation Step 2 Loud speaker installation 40.00%
Step 3 Wiring 30.00%
Step 4 Checks 10.00%
Progress is calculated based on Radio Equipment by Antennae and measured as
Radio System
per following stages:
Work Step Description WF for stages
Step 1 Supports 20.00%
Radio Equipment by Antennae
Step 2 Installation/Connections 70.00%
Step 3 Tests / Checks 10.00%
Work Step Description WF for stages
Step 1 Laying 20.00%
Telecom Cable
Step 2 Terminations 70.00%
Step 3 Checks 10.00%
Progress is calculated based on Instrument Calibration and measured as per
Instrumentation Test
following stages:
Work Step Description WF for stages
Instrument Calibration
Step 1 Calibrate 100.00%
Progress is calculated based on Instrument Test and measured as per following
stages:
Loop Checking Work Step Description WF for stages
Step 1 Checks 100.00%
HVAC/Ducting
Progress is calculated based on Fabrication and measured as per following
HVAC Ducting Support/Hangers
stages:
Fabrication
Work Step Description WF for stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 134 of 456

Step 1 Mark & Cut 15.00%


Step 2 Fit Up 40.00%
Step 3 Weld 30.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on counter of piece Installation and measured as
per following stages:
HVAC Ducting Support/Hangers Work Step Description WF for stages
Installation
Step 1 Complete - Piece 80.00%
Step 2 Acceptance -Piece 20.00%
Work Step Description WF for Stages
Duct Spool Installation Step 1 Completed- Meter length 80.00%
Step 2 Accepted- Meter Length 20.00%
Architectural
Progress is calculated based on Architectural and measured as per following
stages:
Wall Partition Panel Installation Work Step Description WF for stages
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Architectural and measured as per following
stages:
Doors & Windows (Number of Units) Work Step Description WF for stages
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Architectural and measured as per following
stages:
Flooring (Including scree ding) Work Step Description WF for stages
Step 1 Completed –m2 80.00%
Step 2 Accepted –m2 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 135 of 456

Progress is calculated based on Architectural and measured as per following


stages:
Install Insulation Pin for any Room Work Step Description WF for stages
Step 1 Completed –m2 80.00%
Step 2 Accepted –m2 20.00%
Progress is calculated based on Architectural and measured as per following
stages:
Install insulation materials Work Step Description WF for stages
Step 1 Completed –m2 80.00%
Step 2 Accepted –m2 20.00%
Progress is calculated based on Architectural and measured as per following
stages:
Install top and bottom profile Work Step Description WF for stages
Step 1 Completed 80.00%
Step 2 Accepted 20.00%
Progress is calculated based on Architectural and measured as per following
stages:
Work Step Description WF for stages
Install of Floor Pedestal on any Room
Step 1 Completed –m2 80.00%
(Including flooring installation)
Step 2 Accepted –m2 20.00%
Progress is calculated based on Architectural and measured as per following
stages:
Progress is calculated based on Architectural and measured as per following
stages:
Install Hangers & False Ceiling Work Step Description WF for stages
Step 1 Completed –on each room by m2 80.00%
Step 2 Accepted –on each room by m2 20.00%
Blasting & Painting
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 136 of 456

Progress is calculated based on Blast/ Painting & Coating and measured as per
following stages:
Work Step Description WF for stages
One Coat System (Area) Step 1 Blasting 50.00%
Step 2 Final Coating 45.00%
Step 3 Acceptance 5.00%
Progress is calculated based on Blast/ Painting & Coating and measured as per
following stages:
Work Step Description WF for stages
Step 1 Blasting & Shop Prime 35.00%
Four Coat System (Area) Step 2 2nd Coating 20.00%
Step 3 3rd Coating 20.00%
Step 4 Final Coating 20.00%
Step 5 Line Identification / Acceptance 5.00%
Progress is calculated based on Blast/ Painting & Coating and measured as per
following stages:
Work Step Description WF for stages
Galvanized / CTE (Area) Step 1 Etching 45.00%
Step 2 Galvanizing 35.00%
Step 3 Line Identification / Acceptance 20.00%
WORK PACKAGE 7: Testing & Pre commissioning
Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
Progress is calculated based on Pre-commissioning and measured as per
following stages:
PE WP - 735 Electrical Work Step Description WF for stages
Step 1 Power supply and checking 30.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 137 of 456

Step 2 Control System checking 20.00%


Step 3 Motor run 30.00%
Step 4 Energizing 15.00%
Step 5 Certificate 5.00%
Progress is calculated based on Pre-commissioning and measured as per
following stages:
Work Step Description WF for stages
WP - 736 Instrument & Communication Step 1 Control checking system 30.00%
Step 2 Loop checking 50.00%
Step 3 Software landing 15.00%
Step 4 Certificate 5.00%
Progress is calculated based on Pre-commissioning and measured as per
following stages:
Work Step Description WF for stages

Step 1 Flushing 15.00%


WP - 737 Piping Step 2 Chemical cleaning 5.00%
Step 3 Re-instatement 10.00%
Step 4 Hydro test 55.00%
Step 5 Final Box 5.00%
Step 6 Drying & Draining 10.00%
Progress is calculated based on Pre-commissioning and measured as per
following stages:
Work Step Description WF for stages
WP - 738 Pipeline
Step 1 Pigging 50.00%
Step 2 Drying 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 138 of 456

Step 3 Handover 10.00%

Progress is calculated based on Pre-commissioning Mechanical Rotating and


Mechanical
measured as per following stages:
Work Step Description WF for stages
Step 1 Chemical cleaning 10.00%
Step 2 Reinstatement 25.00%
Rotating
Step 3 Final Alignment 15.00%
Step 4 First Oil Filling 40.00%
Step 5 Certificate 10.00%
WP - 739
Progress is calculated based on Pre-commissioning Mechanical Static and
measured as per following stages:
Work Step Description WF for stages
Step 1 Flushing 10.00%
Static Step 2 Chemical cleaning 25.00%
Step 3 Drying 15.00%
Step 4 Catalyst loading 40.00%
Step 5 Final Box 10.00%
Work Step Description WF for stages

WP - 740 HVAC Step 1 Static Test 20.00%


Step 2 Panel Test 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 139 of 456

Step 3 Fan / Motor Test 25.00%


Step 4 Pressure Test 25.00%
Step 5 Certificate 10.00%
Progress is calculated based on Conformity checks and measured as per
System Testing
following stages:
Work Step Description WF for stages
Step 1 Platform per AFC Drawings & Specs 10.00%
Step 2 Cable Insulation & continuity Test 15.00%
Conformity Checks - For
Construction Step 3 Coating Test 15.00%
Step 4 ITR' "A" for Construction 35.00%
Step 5 Red Line marked-up as built 25.00%
Progress is calculated based on Conformity checks and measured as per
WP - 741
following stages:
Work Step Description WF for stages
Step 1 Gross Leak Test 10.00%
Step 2 Calibration Checks 10.00%
System Tests - For Pre-
commissioning Step 3 PSV's Re-certifications (If required in 15.00%
Offshore)
Step 4 DCS Calibration 15.00%
Step 5 SS Calibration 15.00%
Step 6 F & G Calibration 15.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 140 of 456

Step 7 ITR - "B" for Pre-commissioning 20.00%

WORK PACKAGE 7: Load Out & Sea Fastening


Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
Progress is calculated based on number of drawings and measured as per
following stages:
Work Step Description WF for stages
WP - 742 Drawings (No. of Drawings)
Step 1 Submission 80.00%
Step 2 Approval 20.00%
Progress is calculated based on Materials (tonnage) and measured as per
following stages:
Work Step Description WF for stages
WP - 743 Materials (Tonnage)
Step 1 Received On Site 70.00%
PF Step 2 Acceptance 30.00%

Progress is calculated based on Weighing and measured as per following stages:


Work Step Description WF for stages

Weighing ( Jacket, Topside, Platform Step 1 Perform Final Survey 20.00%


WP - 744 Modules, Drilling Platform, Handrail,
Stairs & Boat landing & Others) Step 2 1st Weighing of Jacket 35.00%

Step 3 Final Weighing of Jacket 35.00%

Step 4 Acceptance 10.00%


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 141 of 456

Progress is calculated based on Sea Fastening Fabrication and measured as per


following stages:
Work Step Description WF for stages
Step 1 Mark & Cut 10.00%
WP - 745 Sea Fastening Fabrication
Step 2 Fit Up 30.00%
Step 3 Welding 45.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Load out positioning and measured as per
following stages:
Work Step Description WF for stages
WP - 746 Load Out & Positioning
Step 1 Load Out 70.00%
Step 2 Acceptance 30.00%
Progress is calculated based on Tie down Arrangements and measured as per
following stages:
Work Step Description WF for stages

WP - 747 Tie down Arrangements Step 1 Tie-Down 70.00%


Step 2 Ship loose Materials list 20.00%
Step 3 Acceptance 10.00%

WORK PACKAGE 8: Shutdown Activities ( Pre Shutdown /Shutdown/Post


Shut Down Activities)
Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 142 of 456

- - N/A for Fabrication Offshore N/A

WORK PACKAGE 9: Final Documentation


Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
Progress is calculated based on Equipment Dossiers and measured as per
following stages:
Work Step Description WF for stages
Equipment Dossiers (No. of Step 1 Submission 65.00%
WP - 748
Documents)
Step 2 Approval 25.00%
Step 3 Acceptance 10.00%
Progress is calculated based on QA/QC Documents and measured as per
following stages:
QA/QC Documentation (No. of Work Step Description WF for stages
WP - 749 Step 1 Submission 65.00%
PG Documents)
Step 2 Approval 25.00%
Step 3 Acceptance 10.00%
Progress is calculated based on Materials Documentation and measured as per
following stages:
Materials Documentation ( No. of Work Step Description WF for stages
WP - 750 Step 1 Submission 65.00%
Documents)
Step 2 Approval 25.00%
Step 3 Acceptance 10.00%
Progress is calculated based on Testing & Pre-Commissioning Documentations
Testing & Pre-Commissioning and measured as per following stages:
WP - 751
Documentations (No. of Documents)
Work Step Description WF for stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 143 of 456

Step 1 Submission 65.00%


Step 2 Approval 25.00%
Step 3 Acceptance 10.00%
Progress is calculated based on Design data and measured as per following
stages:
Work Step Description WF for stages
WP - 752 Design Data ( No. of Documents ) Step 1 Submission 65.00%
Step 2 Approval 25.00%
Step 3 Acceptance 10.00%
Progress is calculated based on As Built Drawings and measured as per following
stages:
As-Built Drawings (No. of Work Step Description WF for stages
WP - 753 Step 1 Submission 65.00%
Documents)
Step 2 Approval 25.00%
Step 3 Acceptance 10.00%
Progress is calculated based on Ship loose List and measured as per following
stages:
Work Step Description WF for stages
WP - 754 Ship loose Lists (No. Of Documents) Step 1 Submission 65.00%
Step 2 Approval 25.00%
Step 3 Acceptance 10.00%
Progress is calculated based on As NDT Radiographic Films and measured as per
following stages:
NDT Radiographic Films (No. of Work Step Description WF for stages
WP - 755 Step 1 Submission 65.00%
Documents)
Step 2 Approval 25.00%
Step 3 Acceptance 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 144 of 456

APPENDIX 9: Upstream PMS- CONSTRUCTION


Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress of General Management is based upon and
corresponded with Front End Activities (Work Package 811). Total
WP - 811 General Management Milestone progress (100%) of General Management will be achieved once
physical progress of 100% to be achieved.

Progress of Dredging/ Reclamation is based upon and


corresponded with Front End Activities (Work Package 812). Total
WP - 812 Dredging / Reclamation Milestone
progress (100%) of Dredging /Reclamation will be achieved once
physical progress of 100% to be achieved.
Foundation works Progress is calculated based on the quantity of work done and
measured as per following stages:

Stage Description WF for


stages
Work Step Stage 1 Surface preparation 10.00%
Steel Net Fencing Foundation
Stage 2 Reinforcement/formworks 40.00%
WP - 813 Stage 3 Pouring 30.00%
Stage 4 Grouting 10.00%
Stage 5 Formworks stripping & finishing 10.00%
Progress is calculated based on quantity of work done and
Foundation works - Concrete Drilled Piles
measured as per following stages:
Work Step
Stage Description WF for
Concrete Bored Piles
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 145 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Drilling/excavation 5.00%
Stage 2 Casing Installation 5.00%
Stage 3 Transport of Excavated material 15.00%
Stage 4 Reinforcement Installation 15.00%
Stage 5 Pouring 45.00%
Stage 6 Casing Recovery 10.00%
Stage 7 Integrity Test 5.00%
Infrastructures (Road, Railway, Drainage, etc.) Progress is subjected to Asphalt laying methods & Yards and
& Landscapes measured as per following stages:
Stage Description WF for
stages
Stage 1 Sub-base preparation 10.00%
Work Step Stage 2 Base rolling 5.00%
Asphalt roads and yards Stage 3 Quarry mix foundation 30.00%
Stage 4 Compacting and Stabilizing 25.00%
WP - 814 Stage 5 Binder 15.00%
Stage 6 Wear surface 10.00%
Stage 7 Misc. finishing 5.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
Earth roads and yards Work Step
stages
Stage 1 Ground preparation 10.00%
Stage 2 Foundation 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 146 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Crushed stones 30.00%
Stage 4 Rolling 10.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Trenching and measured as per
following stages:
Stage Description WF for
stages
Earth and Sand Trenches (Trenching) Work Step
Stage 1 Excavation 50.00%
Stage 2 Sand bed 10.00%
Stage 3 Sand filling 10.00%
Stage 4 Top Brick / Red lean concrete 20.00%
Stage 5 Sand filling 10.00%

Stage Description WF for


stages
Concrete Road Work Step Stage 1 Excavation 30.00%
Stage 2 Lean Concrete 5.00%
Stage 3 Reinforcement 20.00%
Stage 4 Form Work 20.00%
Stage 5 Main Concrete 25.00%
Progress is calculated based on Site Facilities and measured as
Site Facilities
per following stages:
WP - 815 Work Step
Stage Description WF for
Site Facilities
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 147 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Areas preparation 10.00%
Stage 2 Roads 60.00%
Stage 3 Fence 30.00%
Progress is calculated based on Work Shop and measured as per
following stages:
Stage Description WF for
Work Shop Work Step stages
Stage 1 Workshops - Building 40.00%
Stage 2 Workshops - Equipment & Facilities 60.00%
Progress is calculated based on Warehouse and measured as per
following stages:

Warehouse Work Step Stage Description WF for


stages
Stage 1 Warehouses - Building 40.00%
Stage 2 Warehouses - Equipment & Facilities 60.00%
Progress is calculated based on Offices measured as per following
stages:
Stage Description WF for
Offices Work Step stages
Stage 1 Offices - Building 40.00%
Stage 2 Offices - Equipment 60.00%
Progress is calculated based on Utilities & Facilities and measured
as per following stages:
Utilities & Facilities Work Step Stage Description WF for
stages
Stage 1 Water and Effluent Treatment 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 148 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Fuel Station 10.00%
Stage 3 Parking, Roads & Fences 25.00%
Stage 4 Power Distribution Network 25.00%
Stage 5 Telecommunication Network 15.00%
Stage 6 Water Distribution Network 5.00%
Stage 7 Sewage Network 10.00%
Progress is calculated based on Facilities Demolition & Removal
and measured as per following stages:
Stage Description WF for
Facilities Demolition & Removal Work Step stages
Stage 1 Demolition & Removal 75.00%
Stage 2 Demobilization 25.00%

Progress is calculated based on Mobilization & Demobilization


Mobilization
and measured as per following stages:
Stage Description WF for
Work Step stages
Mobilization & Demobilization Stage 1 Mobilization Manual and Demobilization of 75.00%
Construction Equipment

WP - 817 Stage 2 Onshore / Offshore Logistic support 25.00%


Progress is calculated based on Mobilization Manual and
Inspection Construction Equipment and measured as per
following stages:
Sub Work of Mobilization Manual and
Demobilization of Construction Equipment
Work Step Stage Description WF for
stages
Stage 1 Mobilization and Demobilization for 2.82%
Construction Equipment for on-shore Works
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 149 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Mobilization and Demobilization for 51.17%
Construction Equipment for offshore Works
Stage 3 Mobilization and Demobilization for 7.51%
Construction Equipment for tie-in Works
Stage 4 Pre-commissioning, Commissioning & Hydro 29.79%
testing
Stage 5 Mobilization and Demobilization for 5.89%
Construction Equipment for Line laying
Works
Stage 6 Mobilization and Demobilization for 2.82%
Construction Equipment for other Works
Progress is calculated based on Onshore Logistic support for
pipeline and measured as per following stages:
Stage Description WF for
Sub Work of Onshore Logistic support (Pipeline) Work Step
stages
Stage 1 Logistic Support for Shore Approach 43.10%
Stage 2 Logistic Support for Laying Operations 56.90%
Progress is calculated based on Onshore / Offshore Logistic
support and measured as per following stages:
Sub Work of Mobilization Manual and
Work Step
Stage Description WF for
Demobilization Inspection Construction Equipment stages
Stage 1 Completion of mobilization of Equipment 50.00%
Stage 2 Demobilization of construction EQUIPMENT 50.00%
Progress is calculated based on Utilities & Facilities and measured
as per following stages:
Utilities & Facilities Work Step Stage Description WF for
stages
Stage 1 Water and Effluent Treatment 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 150 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Fuel Station 10.00%
Stage 3 Parking, Roads & Fences 25.00%
Stage 4 Power Distribution Network 25.00%
Stage 5 Telecommunication Network 15.00%
Stage 6 Water Distribution Network 5.00%
Stage 7 Sewage Network 10.00%
Progress is calculated based on Steel net fencing and measured
Site Preparation
as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Work Step Stage 3 10.00%
Formwork
Steel Net Fencing
Stage 4 Reinforcement 10.00%
Stage 5 Pouring 10.00%
WP - 818
Stage 6 Stripping/backfill 5.00%
Stage 7 Fencing installation 50.00%
Stage 8 Misc. finishing work 5.00%
Progress is calculated based on Pre-Fabricated Elements fencing
and measured as per following stages:
Stage Description WF for
Pre-Fabricated Elements fencing Work Step
stages
Stage 1 Complete - in Meter 90.00%
Stage 2 Acceptance - in Meter 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 151 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Gates and measured as per
following stages:
Stage Description WF for
Gates Work Step stages
Stage 1 Complete - No. of Gates 90.00%
Stage 2 Acceptance - No. of Gates 10.00%
Progress is calculated based on Removal of Trees and measured
Earth Works
as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Ground preparation 5.00%
Removal of Trees
Stage 2 Trees cutting 40.00%
Stage 3 Roots removal 35.00%
Stage 4 Transportation 20.00%

Progress is calculated based on General Excavation and


measured as per following stages:
Stage Description WF for
General Excavation Work Step stages
Stage 1 Excavation including temporary shoring/slope 60.00%
protection
Stage 2 Excavated Material transport to 35.00%
designated dumping area
Stage 3 Final grading 5.00%
Progress is calculated based on General Embankment and
General Embankment Work Step
measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 152 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Ground Preparation 10.00%
Stage 2 Laying Materials/Compaction 70.00%
Stage 3 Final Rolling 20.00%
Progress is calculated based on Sheet piling and dewatering and
measured as per following stages:
Stage Description WF for
stages
Sheet piling and dewatering Work Step
Stage 1 Sheet piles driving 50.00%
Stage 2 Reinforcing beams 20.00%
Stage 3 Dewatering 20.00%
Stage 4 Sheet piles extraction 10.00%
Progress is calculated based on Soil scrubbing and measured as
per following stages:
Stage Description WF for
Soil scrubbing Work Step
stages
Stage 1 Scrubbing 80.00%
Stage 2 Final Grading 20.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
Earth Dykes Work Step stages
Stage 1 Excavation 10.00%
Stage 2 Dyke execution
65.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 153 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Slope profiling
15.00%

Stage 4 10.00%
Finishing work

Progress is calculated based on Tanks Pad and measured as per


following stages:
Stage Description WF for
stages
Stage 1 Excavation 20.00%
Tanks Pad Work Step Stage 2 Base rolling 5.00%
Stage 3 Pad formation 55.00%
Stage 4 Surface layer 10.00%
Stage 5 Bitumen layer 3.00%
Stage 6 Pad slope profiling 7.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean Concrete 5.00%
Tanks Foundation Work Step Stage 3 25.00%
Rebar
Stage 4 Form Work 12.00%
Stage 5 Casting Concrete for Foundation 20.00%
Stage 6 Form Work Pedestal 8.00%
Stage 7 Steel Plate 5.00%
Stage 8 Casting Concrete for Pedestal 15.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 154 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 9 Final/Backfill
5.00%

Progress is calculated based on Gravel Finishing and measured as


Roads, Yards, Paving (Asphalt, not concrete)
per following stages:
Stage Description WF for
Work Step stages
Gravel Finishing Stage 1 Excavation 10.00%
Stage 2 Base rolling 20.00%
Stage 3 Gravel or crushed stone laying 70.00%
Progress is calculated based on Acid and measured as per
following stages:
Stage Description WF for
stages
Acid Resistant Lining Work Step Stage 1 Surface cleaning 10.00%
Stage 2 Acid resistant layers or tiles 70.00%
Stage 3 Joint & sealing 15.00%
Stage 4 Finishing 5.00%
Progress is calculated based on Acid Resistant Lining and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Sub-base preparation 10.00%
Asphalts roads and yards Work Step
Stage 2 Base rolling 5.00%
Stage 3 Quarry mix foundation 30.00%
Stage 4 Compacting & Stabilizing 25.00%
Stage 5 Binder 15.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 155 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 Wear surface 10.00%
Stage 7 Misc. finishing 5.00%
Progress is calculated based on Earth roads & Yards and
measured as per following stages:
Stage Description WF for
stages
Earth roads and yards Work Step Stage 1 Ground preparation 10.00%
Stage 2 Foundation 40.00%
Stage 3 Crushed stones 30.00%
Stage 4 Rolling 10.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Concrete paving and measured as
per following stages:
Stage Description WF for
Concrete Paving Work Step stages
Stage 1 Prep., slope setting, reinforcement 60.00%
Stage 2 Wire netting installation, pouring 25.00%
Stage 3 Finishing works 15.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
Concrete Cable Trenches Work Step stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 156 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping 5.00%
Stage 7 Sand bed 20.00%
Stage 8 Concrete covers 5.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Pulling Pits Work Step Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 25.00%
Stage 4 Formworks 15.00%
Stage 5 Pouring 35.00%
Stage 6 Formworks stripping & backfill 15.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on issued General Engineering
documents to the COMPANY and measured as per following
stages:
Stage Description WF for
WP - 819 General Work Step
stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 157 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Approval for Construction 40.00%

Progress is calculated based on issued process documents to the


COMPANY and measured as per following stages:
Stage Description WF for
WP - 820 Process Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Equipment documents to
the COMPANY and measured as per following stages:
Stage Description WF for
stages
WP - 821 Equipment Work Step Stage 1 Start 5.00%

Stage 2 Issued for Review 55.00%

Stage 3 Approval for Construction 40.00%

Progress is calculated based on issued Civil & structural


documents to the COMPANY and measured as per following
stages:
Stage Description WF for
WP - 822 Civil & Structural Work Step
stages
Stage 1 Start 5.00%

Stage 2 Issued for Review 55.00%


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 158 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Approval for Construction 40.00%

Progress is calculated based on issued piping documents to the


COMPANY and measured as per following stages:
Stage Description WF for
WP - 823 Piping Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Electrical documents to
the COMPANY and measured as per following stages:
Stage Description WF for
WP - 824 Electrical Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Instrument &
Communication documents to the COMPANY and measured as
per following stages:
Stage Description WF for
WP - 825 Instrument & Communication Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 159 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on issued Other Engineering
documents to the COMPANY and measured as per following
stages:
Stage Description WF for
WP - 826 Other Engineering Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on Cast in situ driven piles and
Piling - Driven in place piles hammered
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Casing Installation 10.00%
Cast in Situ driven piles Stage 2 Reinforcing Installation 30.00%
Stage 3 Pouring 45.00%
Stage 4 Casing Recovery 10.00%
Stage 5 Integrity test 5.00%
WP - 813
Progress is calculated based on Concrete Pre-cuts driven piles
and measured as per following stages:
Stage Description WF for
Concrete Pre-cuts driven piles Work Step stages
Stage 1 Material at Site 20.00%
Stage 2 Installation 75.00%
Stage 3 Integrity test 5.00%
Progress is calculated based on Steel driven Piles and measured
Steel driven piles Work Step
as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 160 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Step 1 Material at Site 20.00%
Step 2 Installation 75.00%
Step 3 Integrity test 5.00%
Progress is calculated based on Wooden driven Piles and
measured as per following stages:
Stage Description WF for
Wooden driven piles Work Step stages
Stage 1 Material at Site 20.00%
Stage 2 Installation 75.00%
Stage 3 Integrity test 5.00%
CIVIL WORKS
Progress is calculated based on Concrete Foundation for
Concrete Works - Foundations
Equipment & Structural and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
WP - 827 Work Step
Stage 3 Reinforcement 25.00%
Concrete Foundation for Equipment & Structural
Stage 4 Formworks 20.00%
Stage 5 Anchor bolts/plates 10.00%
Stage 6 Concrete pouring 15.00%
Stage 7 Formworks stripping, concrete protection &
10.00%
backfill
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 161 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Grouting 10.00%
Progress is calculated based on Prefabrication of concrete
foundations and measured as per following stages:
Stage Description WF for
stages
Prefabrication of concrete foundations Work Step Stage 1 Reinforcement 25.00%
Stage 2 Formworks 20.00%
Stage 3 Anchor bolts/plates 20.00%
Stage 4 Concrete pouring 35.00%
Progress is calculated based on Precast of concrete foundations
installation and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Precast on of concrete foundations installation Work Step Stage 2 Lean concrete 5.00%
Stage 3 Foundation installation 55.00%
Stage 4 Concrete protection & backfill 10.00%
Stage 5 Grouting 10.00%
Stage 6 Finishing 15.00%
Progress is calculated based on Tanks Rings and measured as per
following stages:
Stage Description WF for
Tank Rings Work Step
stages
Stage 1 Excavation 10.00%
Stage 2 Lean concrete 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 162 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping, concrete protection &
15.00%
external backfill
Stage 7 Internal backfilling 10.00%
Progress is calculated based on Tanks Rings and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Surface preparation 10.00%
Concrete small foundations Work Step
Stage 2 Reinforcement/formworks 40.00%
Stage 3 Pouring 30.00%
Stage 4 Grouting 10.00%
Stage 5 Formworks stripping & finishing 10.00%
Progress is calculated based on concrete large massive
foundations and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Concrete large massive foundations Work Step Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 15.00%
Stage 5 Anchor bolts/plates 10.00%
Stage 6 Pouring 25.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 163 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Grouting 10.00%
Stage 8 Formworks stripping & backfill 10.00%
Progress is calculated based on Concrete elevated structures cast
Elevation Concrete
in situ l and measured as per following stages:
Stage Description WF for
stages
Stage 1 Formworks 25.00%
Work Step Stage 2 Reinforcement 25.00%
Concrete elevated structures cast in situ
Stage 3 Anchor bolts/plates 15.00%
Stage 4 Pouring 20.00%
Stage 5 Formworks stripping 10.00%
Stage 6 Finishing works 5.00%

Progress is calculated based on Concrete structures


prefabrication and measured as per following stages:
Stage Description WF for
stages
Concrete structures prefabrication Work Step
Stage 1 Reinforcement 25.00%
Stage 2 Formworks 20.00%
Stage 3 Anchor bolts/plates 20.00%
Stage 4 concrete pouring 35.00%
Progress is calculated based on Precast concrete structures
erection and measured as per following stages:
Precast concrete structures erection Work Step Stage Description WF for
stages
Stage 1 Columns installation 30.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 164 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Grouting on footings 10.00%
Stage 3 Lengthwise beams installation 20.00%
Stage 4 Transverse beams installation 20.00%
Step 5 Beams grouting 10.00%
Step 6 Finishing works 10.00%
Progress is calculated based on Concrete paving and measured as
Concrete Paving / Roads / Yards
per following stages:
Stage Description WF for
Work Step stages
Concrete Paving Stage 1 Prep., slope setting, reinforcement 60.00%
Stage 2 Wire netting installation, pouring 25.00%
Stage 3 Finishing works 15.00%

U/G civil works ( pits, duct banks, cable Progress is calculated based on Concrete cable trenches and
trenches ) measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Work Step
Stage 3 Reinforcement 20.00%
Concrete cable trenches
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping 5.00%
Stage 7 Sand bed 20.00%
Stage 8 Concrete covers 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 165 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Pulling Pits and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Puling Pits Work Step
Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 25.00%
Stage 5 Pouring 30.00%
Stage 6 Formworks stripping & backfill 15.00%
Progress is calculated based on Duct Banks and measured as per
following stages:
Stage Description WF for
Duct Banks Work Step stages
Stage 1 Excavation 20.00%
Stage 2 PVC conduit positioning 40.00%
Stage 3 Concrete pouring 40.00%

Progress is calculated based on Earth and Sand Trenches and


measured as per following stages:
Stage Description WF for
stages
Earth and Sand Trenches Work Step Stage 1 Excavation 50.00%
Stage 2 Sand bed 10.00%
Stage 3 Sand filling 10.00%
Stage 4 Top-bricks/red lean concrete 20.00%
Stage 5 Backfill 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 166 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Lighting poles foundations (cast in
situ) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Lighting poles foundations (cast in situ) Work Step Stage 3 Reinforcement 20.00%
Stage 4 Formworks 15.00%
Stage 5 Anchor Bolt/J-bolt 15.00%
Stage 6 Pouring 20.00%
Stage 7 Formworks stripping 5.00%
Stage 8 Backfilling 5.00%
Stage 9 Grouting 10.00%
Progress is calculated based on cast in situ sleepers and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%

Stage 2 Lean concrete 5.00%


Cast in situ sleepers Work Step
Stage 3 Formworks 10.00%

Stage 4 Reinforcing 30.00%


Stage 5 Steel insert installation 10.00%
Stage 6 Pouring 30.00%
Stage 7 Formwork stripping 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 167 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Backfill 5.00%

Progress is calculated based on Concrete Basin and measured as


Cooling towers and concrete basins
per following stages:
Stage Description WF for
stages
Stage 1 Excavation 10.00%
Stage 2 Lean concrete 5.00%
Work Step Stage 3 Reinforcement 20.00%
Concrete Basin Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Joints sealing 5.00%
Stage 7 Formworks stripping, concrete protection &
15.00%
backfill
Stage 8 Finishing works 5.00%

Progress is calculated based on Concrete Retaining Wall and


measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation & lean concrete 10.00%
Concrete Retaining Wall Work Step Stage 2 Foundation formworks 5.00%
Stage 3 Reinforcing 25.00%
Stage 4 Foundation Pouring 5.00%
Stage 5 Elevation formworks 25.00%
Stage 6 Elevation Pouring 15.00%
Stage 7 Formwork stripping 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 168 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Joints sealing 10.00%

Progress is calculated based on Sleepers prefabrication and


Sleepers
measured as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Reinforcement 25.00%
Sleepers prefabrication
Stage 2 Formworks 20.00%
Stage 3 Anchor bolts/plates 20.00%
Stage 4 Concrete pouring 35.00%
Progress is calculated based on Precast sleepers erection and
measured as per following stages:
Stage Description WF for
stages
Precast sleepers erection Work Step Stage 1 Excavation 5.00%
Stage 2 Lean concrete 10.00%
Stage 3 Sleepers installation 60.00%
Stage 4 Backfill 15.00%
Stage 5 Finishing works 10.00%

Progress is calculated based on Fire proofing for equipment


Fireproofing - Dense concrete fire proofing
legs/curbs and measured as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Formworks 30.00%
Fire proofing for equipment legs/curbs
Stage 2 Reinforcement 20.00%
Stage 3 Pouring 30.00%
Stage 4 Formworks stripping 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 169 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Finishing works 15.00%
Progress is calculated based on Fire proofing for equipment skirts
and measured as per following stages:
Stage Description WF for
Fire proofing for equipment skirts Work Step stages
Stage 1 Welded wire mesh installation 20.00%
Stage 2 Pouring 60.00%
Stage 3 Finishing works 20.00%
Progress is calculated based on Fire proofing for steel structures
and measured as per following stages:
Stage Description WF for
stages
Stage 1 Surface cleaning 5.00%
Fire proofing for steel structures Work Step Stage 2 Supports installation 10.00%
Stage 3 Reinforcement 5.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring /application 30.00%
Stage 6 Formworks stripping 20.00%
Stage 7 Finishing works 10.00%
BUILDINGS Progress is calculated based on subs-station and measured as per
Concrete & Masonry Buildings following stages:
Stage Description WF for
Work Step stages
Substation Stage 1 Concrete foundations 30.00%
Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 170 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on control room and measured as
per following stages:
Stage Description WF for
stages
Control room Work Step Stage 1 Concrete foundations 30.00%
Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Other buildings and measured as
per following stages:
Stage Description WF for
stages
Other buildings
Work Step Stage 1 Concrete foundations 30.00%
(administration, laboratory, canteen ...)
Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Curtain and partition walls and
Building Secondary Works measured as per following stages:

Work Step
Stage Description WF for
stages
Curtain and partition walls
Stage 1 Material at site 10.00%
Stage 2 Hollow block 30.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 171 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Internal plastering 25.00%
Stage 4 Internal painting 25.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Doors & windows and measured
as per following stages:
Stage Description WF for
Doors & windows Work Step stages
Stage 1 Material at site 10.00%
Stage 2 Windows / doors installation 45.00%
Stage 3 Accessories installation 45.00%
Progress is calculated based on Flooring and measured as per
following stages:
Stage Description WF for
stages
Flooring Work Step
Stage 1 Material at site 20.00%
Stage 2 Installation 70.00%
Stage 3 Finishing & cleaning 10.00%

Progress is calculated based on Ceiling and measured as per


following stages:
Stage Description WF for
stages
Ceiling Work Step
Stage 1 Material at site 10.00%

Stage 2 Support/Hanger installation and Plastering


40.00%
or False Ceiling
Stage 3 Painting 30.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 172 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Cleaning 20.00%

Progress is calculated based on Ceramic & Quarry Tiling and


measured as per following stages:
Stage Description WF for
Ceramic & Quarry Tiling Work Step
stages
Stage 1 Tiling 90.00%
Stage 2 Jointing/Sealing 10.00%
Progress is calculated based on Plumbing and measured as per
following stages:
Stage Description WF for
Plumbing Work Step stages
Stage 1 Support/Hanger and Equipment installation 30.00%
Stage 2 Water networks 60.00%
Stage 3 Finishing works/tests 10.00%
Progress is calculated based on External Painting and measured
as per following stages:
Stage Description WF for
External Painting Work Step
stages
Stage 1 Coating 90.00%
Stage 2 Touch-up 10.00%
Progress is calculated based on Roof Insulation & Water
Tightness and measured as per following stages:
Stage Description WF for
Roof Insulation & Water Tightness Work Step stages
Stage 1 Insulation 40.00%

Stage 2 Water Tightness 50.00%


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 173 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Tests 10.00%
Progress is calculated based on HVAC system and partition walls
HVAC
and measured as per following stages:
Work Description WF for
Step stages
Stage 1
Support Fabrication and Installation 7.00%

Stage 2 Ducts Installation 20.00%

Stage 3
Work Step Equipment installation 20.00%
HVAC system
Stage 4 Piping installation 20.00%

Stage 5 Electrical installation 13.00%

Stage 6
Instrument installation 10.00%

Stage 7 Duct Insulation 7.00%


Stage 8 Functional checks 3.00%
Progress is calculated based on Power & Lighting and partition
Power / Lighting / Lightning
walls and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Material at site 10.00%
Power & Lighting Stage 2 Cable pulling 30.00%
Stage 3 Lighting fixtures installation 20.00%
Stage 4 Outlets & switches installation 20.00%
Stage 5 Panel installation 15.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 174 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 Functional checks 5.00%
Progress is calculated based on Lightning system and measured
as per following stages:
Stage Description WF for
Lightning system Work Step
stages
Stage 1 Equipment installation 90.00%
Stage 2 Checks 10.00%
Progress is calculated based on Communication / security
systems and measured as per following stages:
Stage Description WF for
stages
Communication / security systems Work Step Stage 1 Material at site 10.00%
Stage 2 Equipment installation 30.00%
Stage 3 Cable pulling & Connections 50.00%
Stage 4 Functional checks 10.00%
Progress is calculated based on Fire detection and partition walls
Fire detection / fighting
and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Material at site 10.00%
Fire detection
Stage 2 Equipment installation 30.00%
Stage 3 Cable pulling & Connections 50.00%
Stage 4 Functional checks 10.00%
Progress is calculated based on Fire detection and partition walls
and measured as per following stages:
Fire fighting system Work Step
Stage Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 175 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Material at site 5.00%
Stage 2 Piping prefabrication & install. 35.00%
Stage 3 Piping painting 20.00%
Stage 4 Sprinkler installation 20.00%
Stage 5 Functional test 20.00%
STORAGE TANKS AND SILOS Progress is calculated based on Fixed roof tanks (altern.I) and
Steel Tanks - Fixed Roof Tanks measured as per following stages:

Stage Description WF for


stages
Work Step
Stage 1 Base 17.00%
Fixed roof tanks
Stage 2 Shell 48.00%
Stage 3 Fixed roof 28.00%
Stage 4 Accessories 3.00%
Stage 5 Testing 4.00%
WP-828 Progress is calculated based on Fixed roof tanks (altern.II) and
measured as per following stages:
Stage Description WF for
stages
Fixed roof tanks (altern.II) Work Step Stage 1 Positioning and tack weld 15.00%
Stage 2 Full weld/fixing 70.00%
Stage 3 X-rays 11.00%
Stage 4 Testing 4.00%
Fixed roof with floating plate tanks (altern.) I) Progress is calculated based on Fixed roof with floating plate
Work Step
tanks (altern. I) and measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 176 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Base 17.00%
Stage 2 Shell 35.00%
Stage 3 Floating plate 25.00%

Stage 4 Fixed roof 16.00%


Stage 5 Accessories 3.00%

Stage 6 Testing 4.00%


Floating Roof tanks Progress is calculated based on Floating roof tanks and
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Base 18.00%
Floating roof tanks
Stage 2 Shell 49.00%
Stage 3 Floating roof 25.00%
Stage 4 Accessories 3.00%
Stage 5 Testing 5.00%
Progress is calculated based on Sphere and measured as per
Sphere Tank
following stages:
Stage Description WF for
stages
Work Step Stage 1 Erection 30.00%
Sphere
Stage 2 Meridian/vertical welds 30.00%
Stage 3 Equatorial/circumferential. welds 10.00%
Stage 4 NDT 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 177 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Cleaning, testing 10.00%
Progress is calculated based on Double Wall tanks and measured
Cryogenic Tank
as per following stages:
Stage Description WF for
stages
Stage 1 Base 17.00%
Work Step Stage 2 Inner shell (nickel) 28.00%
Double wall tanks
Stage 3 Outer shell (carbon steel) 20.00%
Stage 4 Roof 28.00%
Stage 5 Accessories 3.00%
Stage 6 Testing 4.00%
Progress is calculated based on other tanks and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Bottom Plates 17.00%
Other Tanks Work Step Stage 2 Shell Plates 28.00%
Stage 3 Roof & Cover 20.00%
Stage 4 Accessories & Others 3.00%
Stage 5 Hydro test 3.00%
Stage 6 Painting 4.00%

Hoisting and Equipment (Mechanical) Progress is calculated based on Heavy vessels w fixed lifting and
Erection measured as per following stages:
WP 829 Work Step Stage Description WF for
Heavy Vessels with fixed lifting and assembly stages
Stage 1 Erection on Foundation 60.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 178 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Levelling, plumb adjustment 5.00%
Stage 3 Pneumatic & Hydrostatic testing 25.00%
Stage 4 Final inspect., Manholes closure 10.00%
Progress is calculated based on Heavy vessels w fixed cranage
and measured as per following stages:
Stage Description WF for
Vessels parts lifting and assembly stages
Stage 1 Shell assembly & welding 40.00%
Stage 2 Tracing & Welding of Nozzles and
10.00%
Manholes
Work Step
Stage 3 Tray support installation 5.00%
Stage 4 X-ray examination 5.00%
Stage 5 Installation 20.00%
Stage 6 Circum, welding & x-ray exam 5.00%
Stage 7 Plumb adjustment 5.00%
Stage 8 Final hydrostatic testing 10.00%
FIRE EQUIPMENT ERECTION Progress is calculated based on Heavy vessels w fixed cranage
Furnaces and measured as per following stages:
Stage Description WF for
Work Step stages
Preassembled Furnaces
Stage 1 Erection on Foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt
30.00%
tightening
Stage 3 Final inspect., Manholes closure 20.00%
Progress is calculated based on Heavy vessels w fixed cranage
and measured as per following stages:
Partially preassembled Furnaces Work Step
Stage Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 179 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Shell assembly & welding/bolting 20.00%
Stage 2 Refractory panels/mater, erect 15.00%
Stage 3 Coils welding & erection 20.00%
Stage 4 Installation on foundation 10.00%
Stage 5 Stack and Flue ducts weld/bolt 15.00%
Stage 6 Accessories & Structures erect. 10.00%
Stage 7 X-ray examination 8.00%
Stage 8 Final alignment & Final inspection 2.00%
Progress is calculated based on Preassembled boilers and
measured as per following stages:
Stage Description WF for
Preassembled boilers Work Step stages
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Partially preassembled boilers
and measured as per following stages:
Stage Description WF for
stages
Stage 1 Shell assembly & welding/bolting 20.00%

Partially preassembled boilers Work Step Stage 2 Refractory panels/mater erect. 15.00%
Stage 3 Coils welding & erection 20.00%
Stage 4 Installation on foundation 10.00%
Stage 5 Stack and flue ducts weld./bolt. 15.00%
Stage 6 Accessories & structures erect. 10.00%
Stage 7 X-ray examination 8.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 180 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Final alignment final inspection 2.00%
Progress is calculated based on Flares and measured as per
following stages:
Stage Description WF for
stages
Flares Work Step Stage 1 Structure Erection 50.00%
Stage 2 Riser Pipe 20.00%
Stage 3 Alignment 10.00%
Stage 4 Accessories 10.00%
Stage 5 Checks 10.00%

Progress is calculated based on Stack preassembled boilers and


measured as per following stages:
Stage Description WF for
stages
Stack Work Step
Stage 1 Stack Erection 60.00%
Stage 2 Alignment 20.00%
Stage 3 Accessories 10.00%
Stage 4 Checks 10.00%
Progress is calculated based on Module erection and measured as
MODULES FABRICATION AND ERECTION
per following stages:
Stage Description WF for
Work Step stages
WP 829 Stage 1 Erection on foundation 70.00%
Module erection
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Final inspect., manholes closure 10.00%
MACHINERY ERECTION Work Step
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 181 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Belt conveyors and measured as
Machinery ( Not Require for Alignment)
per following stages:
Stage Description WF for
stages
Stage 1 Frames installation 30.00%
Stage 2 Rollers installation 15.00%
Belt conveyors Stage 3 Belt installation 15.00%
Stage 4 Belt joint execution 10.00%
Stage 5 Accessories 10.00%
Stage 6 Counterweight 10.00%
Stage 7 Final check 10.00%

Progress is calculated based on Air Fans and measured as per


Machinery (Require for Alignment)
following stages:
Stage Description WF for
stages
Stage 1 Structure preassembly 5.00%
Work Step
Stage 2 Pack & structure erection 25.00%
Air Fans
Stage 3 Erection of motors & pulleys 30.00%
Stage 4 Blade erection 10.00%
Stage 5 Blade connection & alignment 25.00%
Stage 6 Final inspection 5.00%
Progress is calculated based on Horizontal pumps and drive and
measured as per following stages:
Horizontal pumps and drive Work Step Stage Description WF for
stages
Stage 1 Erection on foundation 25.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 182 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Levelling, bolt tightening 10.00%
Stage 3 Prelim. alignment with motor 25.00%
Stage 4 Cold alignment with piping 30.00%
Stage 5 Final inspection 5.00%
Stage 6 Cleaning, maintenance 5.00%

Progress is calculated based on Vertical, in line, dosing pumps and


drive and drive and measured as per following stages:
Stage Description WF for
stages
Vertical, in line, dosing pumps and drive Work Step
Stage 1 Installation on foundation 25.00%
Stage 2 Levelling, bolt tightening 10.00%
Stage 3 Prelim. alignment with motor 25.00%
Stage 4 Cold alignment with piping 30.00%
Stage 5 Final inspection 5.00%
Stage 6 Cleaning, maintenance 5.00%
Progress is calculated based on Reciprocating compressors and
drive and drive and drive and measured as per following stages:
Stage Description WF for
stages
Stage 1 Installation on foundation 20.00%
Reciprocating compressors and drive Work Step Stage 2 Cylinder installation 10.00%
Stage 3 Levelling, bolt tightening 10.00%
Stage 4 Motor installation 15.00%
Stage 5 Prelim. cylinder installation 10.00%
Stage 6 Utility line installation 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 183 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Cleaning of cylinder suction valves 10.00%
Stage 8 Final alignment, final inspection 15.00%
Progress is calculated based on Centrifugal compressors and drive
and measured as per following stages:
Stage Description WF for
stages
Centrifugal compressors and drive Work Step Stage 1 Installation on foundation 20.00%
Stage 2 Levelling, bolt tightening 15.00%
Stage 3 Motor installation 10.00%
Stage 4 Prelim. cylinder installation 15.00%
Stage 5 Utility line installation 15.00%
Stage 6 Cleaning of cylinder suction valves 5.00%
Stage 7 Final alignment, final inspection 15.00%
Stage 8 Maintenance 5.00%

Progress is calculated based on Mixers and agitators and drive


and measured as per following stages:
Stage Description WF for
stages
Stage 1 Installation on foundation 10.00%
Mixers and agitators Work Step
Stage 2 Shaft/main rotor installation 30.00%
Stage 3 Blades installation 20.00%
Stage 4 Motor installation 20.00%
Stage 5 Accessories installation 15.00%
Stage 6 Final alignment, final inspection 5.00%
Machinery - Internal Installation Work Step
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 184 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Tray Installation and measured
Tray Installation
as per following stages:
Stage Description WF for
stages
Stage 1 Transport to jobsite 10.00%
Trays
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Distributors, grids, demisters, etc.
and measured as per following stages:
Stage Description WF for
stages
Distributors, grids, demisters, etc. Work Step Stage 1 Transport to jobsite 10.00%
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Inert Packing and measured as
Filling materials ( catalyst & packing )
per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Transport to jobsite 10.00%
Inert Packing
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Chemicals, desiccant, catalysts
Chemicals, desiccant, catalysts Work Step
and measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 185 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Transport to jobsite 10.00%
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Air coolers erection and
Air Coolers & Cooling Towers
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Ground Structure Pre-Assembly 40.00%
Air Cooler Erection Stage 2 Structure & Bundles erection 10.00%
Stage 3 Fans & Motors Installation 20.00%
Stage 4 Alignment 20.00%
Stage 5 Final Inspection 10.00%
Progress is calculated based on Package and Miscellaneous
Package and Miscellaneous Erection Erection and measured as per following stages:
Stage Description WF for
stages
Stage 1 Installation on foundation 30.00%
Work Step
Stage 2 Assembling of skids/equipment 20.00%
Skid mounted packages
Stage 3 Disassembled parts erection 20.00%
Stage 4 Levelling, bolt tightening 15.00%
Stage 5 Tot skid/package level, bolt tighten. 10.00%
Stage 6 Final inspection 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 186 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Items in one piece and measured
Heavy Lift
as per following stages:
Stage Description WF for
Work Step stages
Items in one piece Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Items in several pieces ( typical
for 3 pieces) and measured as per following stages:
Items in several pieces
Work Step Stage Description WF for
( typical for 3 pieces)
stages
Stage 1 1st Part Erection on foundation 10.00%
Stage 2 2nd Part Erection on foundation 10.00%
Stage 3 Welding & X-ray examination 20.00%
Stage 4 3rd Part Erection on foundation 10.00%
Stage 5 Welding & X-ray examination 20.00%
Stage 6 Levelling, plumb adjustment, bolt tightening 10.00%
Stage 7 Final inspect., manholes closure 20.00%
Progress is calculated based on Vertical vessels/exchangers (shop
Static Equipment
assembled) and measured as per following stages:
Stage Description WF for
Work Step stages
Vertical vessels/exchangers (shop assembled) Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 187 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Horiz. vessels/exchangers (shop assembled) Work Step Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Vert. vessels/exch. (shop
assemble.) with testing and measured as per following stages:
Stage Description WF for
stages
Vert. vessels/exch. (shop assemble.) with testing Work Step
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Testing 20.00%
Stage 4 Final inspect., manholes closure 10.00%
Progress is calculated based on Horiz. vessels/exch. (shop
assemble.) with testing and measured as per following stages:
Stage Description WF for
stages
Horiz. vessels/exch. (shop assemble.) with testing Work Step
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Testing 20.00%
Stage 4 Final inspect., manholes closure 10.00%
STEEL STRUCTURE Progress is calculated based on Trestle structures and measured
Main Structural Steel Erection as per following stages:
WP-830 Work Step Stage Description WF for
Trestle structures stages
Stage 1 Assembly 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 188 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Erection 33.00%
Stage 3 Alignment 14.00%
Stage 4 Welding and/or bolting 26.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 3.00%
Progress is calculated based on Process structures and measured
as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 19.00%
Process structures Work Step Stage 2 Erection 37.00%
Stage 3 Alignment 13.00%
Stage 4 Welding and/or bolting 25.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 2.00%
Progress is calculated based on Pipe racks and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Assembly 21.00%
Pipe racks Work Step
Stage 2 Erection 22.00%
Stage 3 Alignment 14.00%
Stage 4 Welding and/or bolting 36.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 3.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 189 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Steel Frames and measured as
per following stages:
Stage Description WF for
stages
Steel frames on concrete structures Work Step Stage 1 Erection 40.00%
Stage 2 Alignment 20.00%
Stage 3 Welding and/or bolting 25.00%
Stage 4 Cleaning 5.00%
Stage 5 Final check 10.00%

Progress is calculated based on Ladders & Handrails\ and


Secondary Structural Steel Erection
measured as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 21.00%
Work Step
Stage 2 Erection 36.00%
Ladders and handrails
Stage 3 Alignment 14.00%
Stage 4 Welding and/or bolting 22.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 3.00%

Progress is calculated based on Gratings and measured as per


following stages:

Gratings Work Step Stage Description WF for


stages
Stage 1 Material Selection 15.00%
Stage 2 Erection and Cleaning 35.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 190 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Adjustment 20.00%
Stage 4 Securing 20.00%
Stage 5 Painting/Touch up 5.00%
Stage 6 Final check 5.00%
Progress is calculated based on Gratings and measured as per
following stages:
Stage Description WF for
stages
Checkered plates Work Step
Stage 1 Erection 43.00%
Stage 2 Securing 36.00%
Stage 3 Cleaning 14.00%
Stage 4 Check 7.00%

Progress is calculated based on Platforms & walkways on


equipment and measured as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 25.00%
Platforms & walkways on equipment Work Step
Stage 2 Erection 33.00%
Stage 3 Alignment 17.00%
Stage 4 Welding and/or bolting 17.00%
Stage 5 Cleaning 5.00%
Stage 6 Final check 3.00%
Progress is calculated based on Equipment frames / saddles on
equipment and measured as per following stages:
Equipment frames / saddles Work Step
Stage Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 191 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Assembly 23.00%
Stage 2 Erection 23.00%
Stage 3 Alignment 16.00%
Stage 4 Welding and/or bolting 30.00%
Stage 5 Cleaning 5.00%
Stage 6 Final check 3.00%

Progress is calculated based on Buildings and shelters structures


on equipment and measured as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 19.00%
Buildings and shelters structures Work Step
Stage 2 Erection 37.00%
Stage 3 Alignment 13.00%
Stage 4 Welding and/or bolting 25.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 2.00%
Progress is calculated based on Steelworks erection on vessels
on equipment and measured as per following stages:
Stage Description WF for
stages
Steelworks erection on vessels Work Step Stage 1 Assembly 25.00%
Stage 2 Erection 33.00%
Stage 3 Alignment 17.00%
Stage 4 Welding and/or bolting 17.00%
Stage 5 Cleaning 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 192 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 Final check 3.00%
Progress is calculated based on Ladders & Handrails and
CLADDING
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 15.00%
Stage 2 Thermal sheet erection 25.00%
Work Step Stage 3 Thermal sheet fastening 10.00%
Siding and roofing
Stage 4 External sheet erection 20.00%
Stage 5 External sheet bolting/fixing 10.00%

Stage 6 Accessories erection 15.00%


Stage 7
Final check 5.00%

Progress is calculated based Siding and roofing (Sandwich Panel)


and measured as per following stages:
Stage Description WF for
stages
Siding and roofing (Sandwich Panel) Work Step Stage 1 Prefabrication 15.00%
Stage 2 Panel Installation 55.00%
Stage 3 Panel bolting/fixing 10.00%
Stage 4 Accessories Erection 15.00%
Stage 5 Final Check 5.00%
PIPING WORKS Progress is calculated based on Piping >= 2" prefabrication All
WP-831 Work Step materials and measured as per following stages:
Pre-Fabrication
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 193 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Sectioning 25.00%

Piping >= 2" prefabrication


Stage 2 Assembly, tack welding 20.00%
All materials Stage 3 Welding 30.00%
Stage 4 X-ray examination 10.00%
Stage 5 Stress relieving 10.00%
Stage 6 Transport to storage area 5.00%

Progress is calculated based on Miscellaneous Fitting


prefabrication and measured as per following stages:
Stage Description WF for
stages
Stage 1 Sectioning 25.00%
Miscellaneous Work Step
Fitting prefabrication Stage 2 Assembly, spot welding 20.00%
Stage 3 Welding 30.00%
Stage 4 X-ray examination 10.00%
Stage 5 Stress relieving 10.00%
Stage 6 Transport to storage area 5.00%
Progress is calculated based on Piping up to 2" on site Fabrication
Erection
and erection and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Material Preparation, select &
Piping >= 2" on site 3.00%
transportation
(excl. control valves & safety valves) Stage 2 Erection 17.00%
Stage 3 Alignment, welding 35.00%
Stage 4 Auxiliary supports on pipe 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 194 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Breathers pipe drains 10.00%
Stage 6 X-ray examination, stress relieving hydro test 10.00%
Stage 7 Hydro test 13.00%
Stage 8
Finishing works, Final Check 2.00%

Progress is calculated based on Piping up to 1½" on site


Fabrication and erection and measured as per following stages:

Stage Description WF for


stages
Stage 1 Material Preparation, select &
3.00%
Piping up to 1½" on site transportation
Fabrication and erection Work Step Stage 2 Erection 17.00%
Stage 3 Alignment, welding 35.00%
Stage 4 Auxiliary supports on pipe 10.00%
Stage 5 Breathers pipe drains 10.00%
Stage 6 X-ray examination, stress relieving hydro
10.00%
test
Stage 7 Hydro test 13.00%
Stage 8 Finishing works, Final Check 2.00%
Progress is calculated based on underground Piping on site
U/G Piping Fabrication and erection and measured as per following stages:

Work Step Stage Description WF for


stages
Trench/Backfilling for U/G press. Pipe
Stage 1 Excavation 20.00%
Stage 2 Sand bed/lean concrete 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 195 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Anchor blocks 20.00%
Stage 4 Backfiring 20.00%
Stage 5 Finishing 20.00%
Progress is calculated based on underground Piping on site
Fabrication and erection and measured as per following stages:

Stage Description WF for


stages
Underground piping on site Stage 1 Material Preparation, select & transport 3.00%
Work Step Stage 2 Erection 27.00%
Stage 3 Welding 45.00%
Stage 4 X-ray examination 5.00%
Stage 5 Final check & Testing 10.00%
Stage 6
Wrapping of welded parts 10.00%

Progress is calculated based on underground Piping on site


Fabrication and erection and measured as per following stages:

Stage Description WF for


Underground piping on site up to 1 1/2"
stages
Work Step Stage 1 Transport & Prefabrication 30.00%
Stage 2 Erection 20.00%
Stage 3 Alignment & Welding or threading 25.00%
Stage 4 Testing 10.00%
Stage 5 Bitumizing of welded parts 10.00%
Stage 6 Final check 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 196 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on underground Piping on site
Fabrication and erection and measured as per following stages:
Stage Description WF for
stages
Underground piping off site Stage 1 Material Preparation, select & transport 5.00%
Work Step
Stage 2 Pipe fabrication, erection 35.00%
Stage 3 X-ray examination 25.00%
Stage 4 Testing 10.00%
Stage 5 Bitumizing of welded parts 10.00%
Stage 6 Final check 10.00%

Progress is calculated based on underground Piping on site


Fabrication and erection and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 10.00%
Carbon Steel sewers Work Step Stage 2 Sand bed 10.00%
Stage 3 Pipe installation 30.00%
Stage 4 Welding 20.00%
Stage 5 Testing 10.00%
Stage 6 Continuity check on wrapping 10.00%
Stage 7 Sand cover & backfilling 10.00%
Progress is calculated based on underground Piping on site
Fabrication and erection and measured as per following stages:
Concrete sewers Work Step
Stage Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 197 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Excavation 10.00%
Stage 2 Lean concrete 15.00%
Stage 3 Pipe installation 45.00%
Stage 4 Joint sealing 5.00%
Stage 5 Testing 5.00%
Stage 6 Sand covering 10.00%
Stage 7 Backfilling 10.00%
Progress is calculated based on Plastic GRP on site Fabrication
Plastic, GRP and erection and measured as per following stages:

Stage Description WF for


stages
Stage 1 Excavation 10.00%
Work Step
Stage 2 Lean concrete 15.00%
Plastic material sewers Stage 3 Pipe installation 45.00%
Stage 4 Joints sealing 5.00%
Stage 5 Testing 5.00%
Stage 6 Sand covering 10.00%
Stage 7 Backfilling 10.00%

Others

Progress is calculated based on others on site Fabrication and


erection and measured as per following stages:
Cast Iron sewers Work Step
Stage Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 198 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Excavation 10.00%
Stage 2 Lean concrete 10.00%
Stage 3 Pipe installation 45.00%
Stage 4 Joints sealing 10.00%
Stage 5 Testing 5.00%
Stage 6 Sand covering 10.00%
Stage 7 Backfilling 10.00%
Progress is calculated based on Demolition and measured as per
Demolition
following stages:
Stage Description WF for
Work Step stages
Demolitions Stage 1 Ground Preparation 5.00%
Stage 2 Concrete/Masonry demolition 65.00%
Stage 3 Transportation 30.00%
Progress is calculated based on Steel tubing installation and
Steam Tracing
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Tracer installation 40.00%
Steel tubing installation Stage 2 Pre-insulated tubing installation 40.00%
Stage 3 Trays and supports for tubing 10.00%
Stage 4 Test 5.00%
Stage 5 Final check 5.00%

Progress is calculated based on Copper tubing installation and


Copper tubing installation Work Step
measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 199 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Tracer installation 40.00%
Stage 2 Trays and supports for tubing 25.00%
Stage 3 Pre-insulated tubing installation 25.00%
Stage 4 Test 5.00%
Stage 5 Final check 5.00%
Progress is calculated based on Control valve erection and
Miscellaneous / Accessories- Piping
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Valve erection 80.00%
Control valve erection Stage 2 Bolting 10.00%
Stage 3 Final check 10.00%
Progress is calculated based on Safety valve erection and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection for piping alignment 40.00%
Safety valve erection Work Step Stage 2 Valve dismantling for test 20.00%
Stage 3 Bolting 35.00%
Stage 4 Final check 5.00%

Progress is calculated based on Hot Supports and measured as


Supports - Prefabrication
per following stages:
Work Step
Stage Description WF for
Hot Supports
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 200 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Sectioning 35.00%
Stage 2 Assembly, spot welding 25.00%
Stage 3 Welding 35.00%
Stage 4 Transport to storage area 5.00%

Progress is calculated based on Grounding cable (u/g) with


ELECTRICAL WORKS
connections and measured as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Laying of u/g conductor 65.00%
Grounding cable (u/g) with connections
Stage 2 Cord joints/derivations 27.00%
Stage 3 Tests 6.00%
Stage 4 Final inspection 2.00%

Progress is calculated based on Grounding rods & pits and


erection and measured as per following stages:
WP-832 Stage Description WF for
Grounding rods & pits stages
Work Step
Stage 1 Installation of pit 60.00%
Stage 2 Installation of rods 25.00%
Stage 3 Execution of connections 10.00%
Stage 4 Inspection and tests 5.00%
Progress is calculated based on Grounding rods w/o pits and
measured as per following stages:
Stage Description WF for
Grounding rods w/o pits Work Step
stages
Stage 1 Installation of rods 65.00%
Stage 2 Execution of connections 25.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 201 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Inspection and tests 10.00%
Progress is calculated based on Grounding bars and erection and
measured as per following stages:
Stage Description WF for
stages
Grounding bars Work Step Stage 1 Bar installation 30.00%
Stage 2 Stub-up and concrete base 30.00%
Stage 3 Connection execution 30.00%
Stage 4 Tests 8.00%
Stage 5 Final inspection 2.00%
Progress is calculated based on Overhead copper conduits
installation and erection and measured as per following stages:
Stage Description WF for
Overhead copper conduits installation Work Step stages
Stage 1 Fittings installation 10.00%
Stage 2 Cord laying and fixing 85.00%
Stage 3 Final inspection 5.00%
Progress is calculated based on Connections of equip to the
grounding network and erection and measured as per following
stages:
Stage Description WF for
Connections of equip to the grounding network Work Step stages
Stage 1 Connection execution 90.00%
Stage 2 Protective paint 8.00%
Stage 3 Final inspection 2.00%
Progress is calculated based on Installation of plates (earthing
Installation of plates (earthing bus) Work Step
bus) and erection and measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 202 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Plate prefabrication 30.00%
Stage 2 Plate installation 60.00%
Stage 3 Protective paint 5.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Lightning protection system and
erection and measured as per following stages:
Stage Description WF for
stages
Lightning protection system Work Step
Stage 1 Steel plate installation 60.00%
Stage 2 Rods installation 20.00%
Stage 3 Execution of connections 10.00%
Stage 4 Inspection and tests 10.00%
Sub-Station Installation Progress is calculated based on Transformers and measured as
Transformer per following stages:
Stage Description WF for
stages
Stage 1 Transportation and alignment 20.00%
Work Step
Stage 2 Mechanical connections 5.00%
Transformers
Stage 3 Transformer electrical connection 25.00%
Stage 4 Panel electrical connection 30.00%
Stage 5 Tests 10.00%
Stage 6 Final inspection 10.00%
Progress is calculated based on MCC / Switchgears installation
Electrical Equipment Work Step
and measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 203 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Preparation 20.00%
MCC / Switchgears installation Stage 2 Installation 70.00%
Stage 3 Tests / Checks 10.00%
Progress is calculated based on Bus duct installation and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Supports prefabrication 20.00%
Bus duct installation Work Step
Stage 2 Supports installation 30.00%
Stage 3 Bus duct installation 40.00%
Stage 4 Final Alignment 10.00%
Progress is calculated based on Batteries installation and
measured as per following stages:
Stage Description WF for
stages
Batteries installation Work Step
Stage 1 Supports installation 20.00%
Stage 2 Installation 30.00%
Stage 3 Acid Filling 30.00%
Stage 4 Tests / Checks 20.00%
Progress is calculated based on Diesel generators and
measured as per following stages:
Stage Description WF for
Diesel generator Work Step
stages
Stage 1 Erection on foundation 30.00%
Stage 2 Electrical Connections 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 204 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Testing 20.00%
Stage 4 Finals inspect. 10.00%
Progress is calculated based on Cable trays and cable ladder
Cable trays in S/S
installation and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Check of tray layout 10.00%
Cable trays and cable ladder installation
Stage 2 Installation of supports 35.00%
Stage 3 Installation of trays 50.00%
Stage 4 Sealing of conduit entering cable room 5.00%
Interconnecting cables connections Progress is calculated based on Interconnecting cables
connection and measured as per following stages:
Stage Description WF for
Work Step
Installation of Interconnecting cables stages
Stage 1 Laying 80.00%
Stage 2 Checks 20.00%
Progress is calculated based on Interconnecting cables
connection and measured as per following stages:
Stage Description WF for
Connection of Interconnecting cables Work Step stages
Stage 1 Terminations 70.00%
Stage 2 Testing 20.00%
Stage 3 Checks 10.00%
ELECTRICAL CABLES
Progress is calculated based on Cable trays and cable ladder
Cable trays and conduits Work Step
installation and measured as per following stages:
Cable trays/ladders installation
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 205 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Prefabrication of supports 20.00%
Stage 2 Installation of supports 32.00%
Stage 3 Installation of trays 39.00%
Stage 4 Grounding of trays 4.00%
Stage 5 Installation of covers 5.00%
Progress is calculated based on Underground conduits
installation and measured as per following stages:
Stage Description WF for
stages
Underground conduits installation
Work Step Stage 1 Placing supports 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit and stub up 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Progress is calculated based on Above ground conduits
installation and measured as per following stages:
Stage Description WF for
stages
Above ground conduits installation Stage 1 Supports installation 15.00%
Work Step
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 206 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on U/G cables and measured as per
Cable pulling
following stages:
Stage Description WF for
stages
Stage 1 Stub up & concrete base 5.00%
Work Step Stage 2 Handling of cable drums 5.00%
U/G cables Stage 3 Laying of cables 65.00%
Stage 4 Cable markers installation 10.00%
Stage 5 Insulation test 10.00%
Stage 6 Cable way markers 4.00%
Stage 7 Final inspection 1.00%
Progress is calculated based on Cables in trays/ladders and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Handling of cable drums 5.00%
Cables in trays/ladders Work Step
Stage 2 Laying of cables 70.00%
Stage 3 Insulation test 10.00%
Stage 4 Markers installation 10.00%
Stage 5 Final inspection 5.00%

Progress is calculated based on Cables in conduit and measured


as per following stages:
Cables in conduit Work Step Stage Description WF for
stages
Stage 1 Handling of cable drums 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 207 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Conduit cleaning 5.00%
Stage 3 Cable pulling 65.00%
Stage 4 Insulation test 10.00%
Stage 5 Markers installation 10.00%
Step 6 Final inspection 5.00%

Progress is calculated based on Cable connections and measured


Connections
as per following stages:
Stage Description WF for
Work Step stages
Cable connections Stage 1 Terminations 70.00%
Stage 2 Testing 20.00%
Stage 3 Checks 10.00%

Control station installation Progress is calculated based on Control station industrial type
and measured as per following stages:
Stage Description WF for
Work Step stages
Control station Ex type Stage 1 Installation 80.00%
Stage 2 Checks 20.00%

Progress is calculated based on Power outlet Ex type and


measured as per following stages:

Control station industrial type Work Step


Stage Description WF for
stages
Stage 1 Installation 80.00%
Stage 2 Checks 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 208 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Control station industrial type
Power outlets installation
and measured as per following stages:
Stage Description WF for
Work Step stages
Power outlet Ex type Stage 1 Installation 80.00%
Stage 2
Checks 20.00%

Progress is calculated based on Power outlet industrial type and


measured as per following stages:
Control station industrial type Work Step
Stage Description WF for
stages
Stage 1 Installation 80.00%
Stage 2 Checks 20.00%

Progress is calculated based on Execution of underground joint


Execution of underground joint
and measured as per following stages:
Stage Description WF for
Work Step stages
Execution of underground joint Stage 1 Execution 80.00%

Stage 2 Checks 20.00%

Progress is calculated based on Junction boxes Ex type and


Junction boxes installation
measured as per following stages:
Work Step
Stage Description WF for
Junction boxes Ex type stages
Stage 1 Installation 80.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 209 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Checks 20.00%

Progress is calculated based on Junction boxes industrial type


and measured as per following stages:
Control station industrial type Work Step Work Description WF for
Step stages
Step 1 Installation 80.00%
Step 2 Checks 20.00%
Progress is calculated based on Electrical Tracing and measured
as per following stages:
Stage Description WF for
stages
Electrical Tracing Stage 1 Installation of local panels 10.00%
Work Step
Stage 2 Installation of main junction boxes 10.00%
Stage 3 Heating cable installation 30.00%
Stage 4 Connection of heating cable 30.00%
Stage 5 Tests/Checks 20.00%

Progress is calculated based on Cathodic Protection and


measured as per following stages:
Stage Description WF for
stages
Cathodic Protection Work Step Stage 1 Installation of power supply unit 20.00%
Stage 2 Electrode installation & connection 20.00%
Stage 3 Electrical cable installation 20.00%
Stage 4 Test point installation & connection 20.00%
Stage 5 Tests/Checks 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 210 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Lighting Installation and
measured as per following stages:
Stage Description WF for
stages
Lighting Installation Work Step Stage 1 Installation of local panels 20.00%
Stage 2 Installation of main junction boxes 20.00%
Stage 3 Install/ connection of lighting fixtures 40.00%
Stage 4 Tests/Checks 20.00%
INSTRUMENT & TELECOMS WORK Progress is calculated based on Panels/marshalling cabinets and
Control Room Installation Works measured as per following stages:
Stage Description WF for
Work Step stages
Panels/marshalling cabinets Stage 1 Preparation 20.00%
Stage 2 Installation 70.00%
Stage 3 Tests / Checks 10.00%
Progress is calculated based on Cable trays in technical/control
rooms and erection and measured as per following stages:
WP-833 Stage Description WF for
Cable trays in technical/control rooms
Work Step
stages
Stage 1 Supports 40.00%
Stage 2 Installation 50.00%
Stage 3 Checks 10.00%

Progress is calculated based on Interconnecting cables and


measured as per following stages:
Interconnecting cables Work Step
Stage Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 211 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Laying 80.00%
Stage 2 Checks 20.00%
Progress is calculated based on Interconnecting cables
connections and erection and measured as per following stages:
Stage Description WF for
Interconnecting cables connections
Work Step stages
Stage 1 Terminations 70.00%
Stage 2 Testing 20.00%
Stage 3 Checks 10.00%

Progress is calculated based on DCS/PLC/F&G/packages systems


cabinets and measured as per following stages:
Stage Description WF for
stages
DCS/PLC/F&G/packages systems cabinets Work Step
Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%

Stage 3 Tests / Checks 10.00%

Progress is calculated based on Trays for cables and measured as


per following stages:
Cable Pulling
Stage Description WF for
stages
Work Step
Stage 1 Prefabrication of supports 20.00%

Trays for cables


Stage 2 Installation of supports 20.00%
Stage 3 Installation of trays 40.00%
Stage 4 Grounding of trays 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 212 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Installation of covers 5.00%
Stage 6 Checks 10.00%
Progress is calculated based on Underground conduits and
measured as per following stages:
Stage Description WF for
stages
Underground conduits Work Step Stage 1 Placing supports 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit and stub up 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Progress is calculated based on Above ground conduits and
measured as per following stages:
Stage Description WF for
stages
Above ground conduits Work Step Stage 1 Supports installation 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%

Progress is calculated based on Directly buried cables and


measured as per following stages:
Directly buried cables Work Step Stage Description WF for
stages
Stage 1 Stub up & concrete base 5.00%
Stage 2 Handling of cable drums 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 213 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Laying of cables 55.00%
Stage 4 Cable markers installation 10.00%
Stage 5 Insulation test 10.00%
Stage 6 Cable way markers 5.00%
Stage 7 Final inspection 10.00%

Progress is calculated based on Cables in trays and measured as


per following stages:

Stage Description WF for


stages
Cables in trays Work Step Stage 1 Handling of cable drums 5.00%
Stage 2 Laying of cables 65.00%
Stage 3 Insulation test 10.00%
Stage 4 Markers installation 10.00%
Stage 5 Final inspection 10.00%

Progress is calculated based on Cables in conduits and


measured as per following stages:
Stage Description WF for
stages
Stage 1 Handling of cable drums 5.00%
Cables in conduits Work Step
Stage 2 Conduit cleaning 5.00%
Stage 3 Cable pulling 60.00%
Stage 4 Insulation test 10.00%
Stage 5 Markers installation 10.00%
Stage 6 Final inspection 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 214 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Cables connections in tech. room
and measured as per following stages:
Stage Description WF for
Cables connections in tech. room Work Step stages
Stage 1 Connections 70.00%
Stage 2 Testing 20.00%

Stage 3 Checks 10.00%

Progress is calculated based on Electronic junction boxes and


measured as per following stages:
Junction Box & Local Panels
Stage Description WF for
stages
Stage 1 Erection 5.00%

Work Step Stage 2 Single tube trays/conduit erection 55.00%


Stage 3 Multi core cable connections 10.00%
Electronic junction boxes
Stage 4 Single cable connections 15.00%
Stage 5 Earthing 5.00%

Stage 6 Tests / Checks 10.00%

Progress is calculated based on Local panels installation &


connection and measured as per following stages:

Local panels installation & connection Work Step Stage Description WF for
stages
Stage 1 Erection 20.00%
Stage 2 Connections 50.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 215 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Testing 20.00%
Stage 4
Checks 10.00%

Progress is calculated based on Local flow indicators and


Field Instrument Works
measured as per following stages:

Stage Description WF for


Flow Instruments
stages
Stage 1 Erection of supports 10.00%
Work Step
Stage 2 Manifold erection 28.00%
Stage 3 Process connection 30.00%
Local flow indicators Stage 4 Hydrostatic testing 2.00%
Stage 5 Air distribution 22.00%
Stage 6 Pneumatic connections 4.00%
Stage 7 Checks 4.00%
Progress is calculated based on Local flow indicators and
measured as per following stages:
Stage Description WF for
stages
Magnetic flow transmitters Work Step Stage 1 Converter support erection 20.00%
Stage 2 Power cable installation 30.00%
Stage 3 Signal cable installation 30.00%
Stage 4 Electrical connections 10.00%
Stage 5 Transmitter circuit check 10.00%
Progress is calculated based on Electronic flow transmitters and
Electronic flow transmitters Work Step
measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 216 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
Stage 2 Manifold erection 25.00%
Stage 3 Process connection 25.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Cable installation 22.00%
Stage 6 Electrical connections 8.00%
Stage 7 Transmitter circuit check 5.00%
Progress is calculated based on Electronic level instruments
Level instrument
(displacement type) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection 20.00%

Work Step Stage 2 Discharge header erection 20.00%


Electronic level instruments (displacement type) Stage 3 Hydrostatic testing 5.00%
Stage 4 Repeater support erection 10.00%
Stage 5 Cable installation 25.00%
Stage 6 Electrical connections 10.00%
Stage 7 Transmitter circuit check 10.00%
Progress is calculated based on Electronic level transmitter (diff.
pressure type) and measured as per following stages:
Electronic level transmitter (diff. pressure type) Work Step Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 217 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Manifold erection 20.00%
Stage 3 Process connection 30.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Cable installation 22.00%
Stage 6 Electrical connections 8.00%
Stage 7 Transmitter circuit check 5.00%

Progress is calculated based on Electronic flow transmitters and


measured as per following stages:
Stage Description WF for
Level glass gauges Work Step stages
Stage 1 Erection 40.00%
Stage 2 Discharge header erection 50.00%
Stage 3 Hydrostatic testing 10.00%
Progress is calculated based on Electronic pressure transmitters
Pressure Instrument
and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
Work Step Stage 2 Manifold erection 20.00%
Electronic pressure transmitters Stage 3 Process connection 20.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Cable installation 25.00%
Stage 6 Electrical connections 10.00%
Stage 7 Transmitter circuit check 10.00%
Progress is calculated based on Local pneumatic pressure
Local pneumatic pressure regulators Work Step
regulators and measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 218 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Erection of supports 12.00%
Stage 2 Manifold erection 20.00%
Stage 3 Process connection 20.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Air distribution 26.00%
Stage 6 Pneumatic connections 9.00%
Stage 7 Checks 10.00%

Progress is calculated based on Electronic differential pressure


transmitters and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
Electronic differential pressure transmitters Work Step Stage 2 Manifold erection 13.00%
Stage 3 Process connection 40.00%
Stage 4 Hydrostatic testing 5.00%
Stage 5 Cable installation 18.00%
Stage 6 Electrical connections 6.00%
Stage 7 Transmitter circuit check 6.00%
Progress is calculated based on Local differential pressure gauges
and measured as per following stages:
Local differential pressure gauges Work Step Stage Description WF for
stages
Stage 1 Erection of supports 12.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 219 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Manifold erection 40.00%
Stage 3 Process connection 40.00%
Stage 4 Hydrostatic testing 8.00%
Progress is calculated based on Direct pressure switches and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection 12.00%
Direct pressure switches Work Step
Stage 2 Process diagram 40.00%
Stage 3 Hydrostatic testing 3.00%
Stage 4 Cable installation 25.00%
Stage 5 Electrical connections 10.00%
Stage 6 Checks 10.00%

Progress is calculated based on Manometers and measured as


per following stages:
Stage Description WF for
Manometers Work Step stages
Stage 1 Manifold prefabrication 60.00%
Stage 2 Manifold installation 20.00%
Stage 3 Manometers erection 20.00%
Progress is calculated based on Bulb thermostats and measured
Temperature instrument
as per following stages:
Stage Description WF for
Work Step
stages
Bulb thermostats
Stage 1 Support erection 20.00%
Stage 2 Capillary arrangement 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 220 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Cable installation 40.00%
Stage 4 Electrical connections 10.00%
Stage 5 Checks 10.00%
Progress is calculated based on Local pneumatic temperature
regulators and measured as per following stages:
Stage Description WF for
stages
Local pneumatic temperature regulators Work Step Stage 1 Support erection 20.00%
Stage 2 Capillary arrangement 20.00%
Stage 3 Air distribution 40.00%
Stage 4 Pneumatic connections 10.00%
Stage 5 Checks 10.00%
Progress is calculated based on Local MV electric converters and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of support and repeater 20.00%
Local MV electric converters Work Step
Stage 2 Thermocouple 5.00%
Stage 3 Cable installation 50.00%
Stage 4 Electrical connections 15.00%
Stage 5 Transmitter circuit check 10.00%

Progress is calculated based on Electronic pressure transmitters


and measured as per following stages:
Thermocouples or RTD Work Step
Stage Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 221 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Erection of traps and elements 5.00%

Stage 2 Cable installation 70.00%


Stage 3 Electrical connections 15.00%
Stage 4 Checks 10.00%

Progress is calculated based on Dial thermometers and measured


as per following stages:
Dial thermometers Work Step Stage Description WF for
stages
Stage 1 Trap erection 80.00%
Stage 2 Dial installation 20.00%
Progress is calculated based on Flux stats and measured as per
On line instruments
following stages:
Stage Description WF for
stages
Work Step
Stage 1 Cable installation 70.00%
Flux stats
Stage 2 Electrical connections 20.00%
Stage 3 Checks 10.00%

Progress is calculated based on Electronic flow rate transmitters


and measured as per following stages:

Electronic flow rate transmitters Work Step


Stage Description WF for
stages
Stage 1 Erection check 10.00%
Stage 2 Repeater erection 15.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 222 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Cable installation 40.00%
Stage 4 Electrical connections 15.00%
Stage 5 Transmitter circuit check 10.00%
Stage 6 Line washing 10.00%

Progress is calculated based on Control valves equip, with electro-


pneum, positioner and measured as per following stages:
Stage Description WF for
stages
Control valves equip, with electro-pneum,
positioner
Work Step Stage 1 Air distribution 50.00%
Stage 2 Cable and pneum. tube install. 35.00%
Stage 3 Electrical or pneum. connections 5.00%
Stage 4 Line washing 5.00%
Stage 5 Circuit check 5.00%
Progress is calculated based on Control valves with I/P and
pneum. Positioner and measured as per following stages:
Stage Description WF for
stages
Stage 1 I/p erection 15.00%

Control valves with I/P and pneum. Positioner Work Step Stage 2 I/p air distribute. & positioner 40.00%
Stage 3 Cable installation 25.00%
Stage 4 Electrical connections 4.00%
Stage 5 Pneumatic connections 10.00%
Stage 6 Line washing 2.00%
Stage 7 Circuit check 4.00%

Progress is calculated based on Control valves without positioner


Control valves without positioner Work Step
and measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 223 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Pneumatic tube installation 60.00%
Stage 2 Pneumatic connections 25.00%
Stage 3 Line washing 5.00%
Stage 4 Circuit check 10.00%
Progress is calculated based on Local pneumatic receiver
regulators and measured as per following stages:
Stage Description WF for
stages
Local pneumatic receiver regulators Work Step Stage 1 Erection 25.00%
Stage 2 Air distribution 50.00%
Stage 3 Pneumatic connections 15.00%
Stage 4 Checks 10.00%

Progress is calculated based on Solenoid valves and measured as


per following stages:
Stage Description WF for
stages
Solenoid valves Work Step Stage 1 Installation 10.00%
Stage 2 Cable installation 60.00%
Stage 3 Electrical connections 10.00%
Stage 4 Pneumatic connections 10.00%
Stage 5 Checks 10.00%

Progress is calculated based on Steam tracing for instruments


Steam tracing for instruments Work Step
and measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 224 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Sub-header distribution 50.00%

Steam tracing for instruments Stage 2 Copper tube steam tracer 20.00%
Stage 3 Condensate discharge manifold 20.00%
Stage 4 Piping connections 5.00%
Stage 5 Checks 5.00%
TELECOMS WORKS
Progress is calculated based on P.A.B.X. and measured as per
Telephone following stages:
Stage Description WF for
stages
Stage 1 Transport on the spot 5.00%

Work Step Stage 2 Installation of support frame 10.00%

P.A.B.X. Installation Stage 3 Installation of PABX 25.00%

Stage 4 Batteries and accessories 15.00%


Stage 5 Execution of connections 30.00%

Stage 6 Tests 15.00%

Progress is calculated based on Telephone sets (wall type) and


measured as per following stages:

Telephone sets (wall type) installation Work Step Stage Description WF for
stages
Stage 1 Preparation of support 12.00%
Stage 2 Acoustic booth 28.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 225 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Installation of telephone set 20.00%
Stage 4 Wiring 30.00%
Stage 5 Final Tests 10.00%
Public Address Progress is calculated based on Loud speaker and measured as
per following stages:
Stage Description WF for
stages
Work Step Stage 1 Support preparation 5.00%
Loud speakers
Stage 2 Loud speaker installation 40.00%
Stage 3 Wiring 30.00%
Stage 4 Checks 5.00%
Stage 5 Final tests 20.00%
Progress is calculated based on Public address console and
measured as per following stages:
Stage Description WF for
Public address consoles
Work Step
stages
Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%
Stage 3 Tests / Checks 10.00%

Progress is calculated based on CCTV camera installation and


Closed circuit television (CCTV)
erection and measured as per following stages:

Work Step Stage Description WF for


stages
CCTV camera installation
Stage 1 Support preparation 5.00%
Stage 2 Camera Installation 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 226 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Wiring 30.00%
Stage 4 Checks 5.00%
Stage 5 Final tests 20.00%
Progress is calculated based on CCTV control system and
erection and measured as per following stages:
Stage Description WF for
CCTV control system
Work Step stages
Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%
Stage 3 Tests / Checks 10.00%
Progress is calculated based on Siren installation and erection
Siren
and measured as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Support preparation 20.00%
Siren installation
Stage 2 Siren installation 40.00%
Stage 3 Wiring 30.00%
Stage 4 Checks 10.00%

Progress is calculated based on Radio equipment (by antenna)


Radio system
and erection and measured as per following stages:
Stage Description WF for
Work Step stages
Radio equipment (by antenna) Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%
Stage 3 Tests / Checks 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 227 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Telecom cables installation and
Telecom Cables
measured as per following stages:
Stage Description WF for
Work Step stages
Telecom cables installation Stage 1 Laying 50.00%
Stage 2 Terminations 30.00%
Stage 3 Checks 20.00%
Progress is calculated based on Calibrate and measured as per
Instrumentation Test
following stages:
Work Step Stage Description WF for
Instruments Calibration stages
Stage 1 Calibrate 100.00%

Progress is calculated based on Loop Checking and measured as


per following stages:
Stage Description WF for
Loop Checking Work Step stages
Stage 1 Preparation 20.00%
Stage 2 Loop Check 80.00%

INSULATION - OTHER WORKS


Progress is calculated based on Piping hot insulation and
Hot Insulation Works measured as per following stages:
Stage Description WF for
834 Work Step stages
Piping hot insulation Stage 1 Steel sheet prefabrication 10.00%
Stage 2 Scaffolding erection 15.00%
Stage 3 Insulating layer installation 25.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 228 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Sheeting installation 30.00%
Stage 5 Miscellaneous finishing works 5.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%

Progress is calculated based on Equipment hot insulation and


measured as per following stages:
Stage Description WF for
stages
Stage 1 Steel sheet prefabrication 10.00%
Equipment hot insulation Work Step Stage 2 Scaffolding erection 10.00%
Stage 3 Insulating layer installation 30.00%
Stage 4 Sheeting installation 30.00%
Stage 5 Miscellaneous finishing works 5.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
Progress is calculated based on Personnel protection insulation
(for piping) and measured as per following stages:
Stage Description WF for
stages
Personnel protection insulation (for piping) Work Step
Stage 1 Steel sheet prefabrication 20.00%
Stage 2 Insulating layer installation 40.00%
Stage 3 Sheeting installation 30.00%
Stage 4 Finishing 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 229 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Piping cold insulation and
Cold Insulation Works
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 20.00%
Work Step Stage 2 Scaffolding erection 10.00%
Piping cold insulation Stage 3 Insulating layer installation 15.00%
Stage 4 Vapour barrier 20.00%
Stage 5 Sheeting installation 20.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
Progress is calculated based on Equipment cold insulation and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 20.00%
Equipment cold insulation Work Step Stage 2 Scaffolding erection 10.00%
Stage 3 Insulating layer installation 15.00%
Stage 4 Vapor barrier 20.00%
Stage 5 Sheeting installation 20.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
PAINTING Progress is calculated based on Piping painting (2+2 coats) and
Painting Works measured as per following stages:
Work Step
Stage Description WF for
Piping painting (2+2 coats)
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 230 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Stage 3 2nd primer coat 10.00%
Stage 4 1st finish coat 15.00%
Stage 5 2nd finish coat 15.00%
Stage 6 Numbering or labelling 5.00%
Stage 7 Final cleaning and touch up 10.00%
Stage 8 Final check 5.00%
Progress is calculated based on Piping painting in shop (2 coats)
and measured as per following stages:
Stage Description WF for
stages
Piping painting in shop (2 coats) Work Step Stage 1 Wire brushing or shot blasting 50.00%
Stage 2 1st primer coat 20.00%
Stage 3 2nd primer coat 20.00%
Stage 4 Final check 10.00%
Progress is calculated based on Piping painting in field (2 coats
and measured as per following stages:
Stage Description WF for
stages
Piping painting in field (2 coats) Work Step Stage 1 1st finish coat 35.00%
Stage 2 2nd finish coat 35.00%
Stage 3 Numbering or labelling 10.00%
Stage 4 Final cleaning and touch up 10.00%
Stage 5 Final check 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 231 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Steel structures painting (2+2
coats) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Steel structures painting (2+2 coats) Work Step Stage 3 2nd primer coat 10.00%
Stage 4 Touch up 14.00%
Stage 5 1st finish coat 16.00%
Stage 6 2nd finish coat 15.00%
Stage 7 Touch up 3.00%
Stage 8 Final check 2.00%
Progress is calculated based on Steel structure painting in field (2
coats) and measured as per following stages:
Stage Description WF for
stages
Stage 1 1st finish coat 35.00%
Steel structure painting in field (2 coats) Work Step Stage 2 2nd finish coat 35.00%

Stage 3 Numbering or labelling 10.00%

Stage 4 Final cleaning and touch up 10.00%

Stage 5 Final check 10.00%

Progress is calculated based on Equipment painting (2 coats) and


Equipment painting (2 coats) Work Step
measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 232 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Intermediate coat 35.00%
Stage 2 Final coat 35.00%
Stage 3 Numbering or labelling 20.00%

Stage 4 Touch up 5.00%

Stage 5 Final check 5.00%

Progress is calculated based on Equipment painting (final coat)


and measured as per following stages:
Stage Description WF for
Equipment painting (final coat) Work Step stages
Stage 1 Final coat 85.00%
Stage 2 Touch up 10.00%
Stage 3 Final check 50.00%
Progress is calculated based on Tanks and spheres painting (2+2
coats) and measured as per following stages:
Stage Description WF for
stages
Tanks and spheres painting (2+2 coats)
Work Step Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Stage 3 2nd primer coat 10.00%
Stage 4 Touch up 10.00%
Stage 5 1st finish coat 15.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 233 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 2nd finish coat 5.00%

Stage 7 Numbering or labelling 15.00%


Stage 8 Touch up 3.00%
Stage 9 Final check 2.00%
Progress is calculated based on Conformity check and measured
as per following stages:
Stage Description WF for
stages
Stage 1 Facilities constructed per AFC 10.00%
Mechanical Completion drawings & specs
WP - 836 Work Step
Stage 2 Piping flushing & Hydro test 25.00%
Stage 3 Cable insulation & Continuity test 15.00%
Stage 4 Coating Test 10.00%
Stage 5 Inspection Test & Records (ITR) 35.00%
Stage 6 Red Line Marked up as built. 5.00%
Progress is calculated based on Survey and staking and
Pipeline Installation (CROSS-COUNTRY )
measured as per following stages:
Stage Description WF for
Work Step
stages
Survey and staking
Stage 1 Survey 50.00%
WP - 837-846 Stage 2 Staking 50.00%
Progress is calculated based on ROW-Clearing and Grading and
measured as per following stages:
ROW-Clearing and Grading & Access
Work Step Stage Description
Preparation
Stage 1 Clearing & Grading 40.00%
Stage 2 Fill 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 234 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Compact 15.00%
Stage 4 Test 5.00%

Progress is calculated based on Pipe Transportation and


measured as per following stages:
Pipe Transportation Work Step Stage Description WF for
stages
Stage 1 Pipe Transportation 100.00%
Progress is calculated based on Trenching and measured as per
following stages:
Stage Description WF for
Trench Excavation Work Step stages
Stage 1 Actual Trench Excavation in Km 90.00%
Stage 2 Accepted Total no. of Trench 10.00%
Excavation in Km
Progress is calculated based on Pipe stringing single pipe and
measured as per following stages:
Stage Description WF for
Pipe stringing single pipe Work Step
stages
Stage 1 Actual No of Stringing single pipe 90.00%
Stage 2 Accepted Total no. of Stringing 10.00%
Progress is calculated based on Pipe stringing 2-3 pipe section
and measured as per following stages:
Pipe stringing 2-3 pipe section Work Step Stage Description WF for
stages
Stage 1 Actual No. of Stringing 2-3 pipe section 90.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 235 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted Total No. of Stringing 2-3 10.00%
pipe section
Progress is calculated based on Field Bending and measured as
per following stages:
Stage Description WF for
stages
Laying/Welding & Joint Coating Work Step Stage 1 Laying 20.00%
Stage 2 Welding 40.00%
Stage 3 Joint Coating 20.00%

Stage 4 Controls 20.00%


Progress is calculated based on Field Bending and measured as
per following stages:
Stage Description WF for
Field Bending Work Step
stages
Stage 1 Actual no. of Bending 90.00%
Stage 2 Accepted Total no. of Bending 10.00%
Progress is calculated based on Welding of Line pipe - station
and measured as per following stages:
Stage Description WF for
Welding of Line pipe - station Work Step
stages
Stage 1 Actual no. of Welding 90.00%
Stage 2 Accepted Total no. of Welding 10.00%
Progress is calculated based on Welding of Line pipe - station on
site and measured as per following stages:
Welding of Line pipe - onsite Work Step
Stage Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 236 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Actual no. of Welding 90.00%
Stage 2 Accepted Total no. of Welding 10.00%
Progress is calculated based on tie-in and measured as per
following stages:
Stage Description WF for
Tie-ins Work Step
stages
Stage 1 Actual No. of Tie-ins 90.00%
Stage 2 Accepted Total No. of Tie-ins 10.00%
Progress is calculated based on NDT and measured as per
following stages:
Stage Description WF for
NDT Work Step
stages
Stage 1 Total No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Field Joint coating and measured
as per following stages:
Stage Description WF for
Field Joint Coating Work Step stages
Stage 1 Actual - No. of Field joints 90.00%
Stage 2 Accepted Total No. of Field Joint 10.00%
Coating
Progress is calculated based on Bedding and measured as per
following stages:
Stage Description WF for
Bedding Work Step
stages
Stage 1 Actual - No. of Bedding 90.00%
Stage 2 Accepted Total No. of Bedding 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 237 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Lowering and measured as per
following stages:
Stage Description WF for
Lowering Work Step stages
Stage 1 Actual - No. of Lowering 90.00%
Stage 2 Accepted Total No. of Lowering 10.00%

Progress is calculated based on CP test Connection and


measured as per following stages:

CP test Connection Work Step Stage Description WF for


stages
Stage 1 CP Test connection 90.00%
Stage 2 Accepted 10.00%
Progress is calculated based on Padding and measured as per
following stages:
Stage Description WF for
Padding Work Step
stages
Stage 1 Actual - No. of Padding 90.00%
Stage 2 Accepted Total No. of Padding 10.00%
Progress is calculated based on Backfilling and measured as per
following stages:
Stage Description WF for
Box Culvert Works Work Step stages
Stage 1 Excavation 5.00%
Stage 2 Blinding Concrete 5.00%
Stage 3 Reinforcement 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 238 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Formworks 35.00%
Stage 5 Pouring 20.00%
Stage 6 Coating 5.00%
Stage 7 Backfilling 10.00%
Progress is calculated based on Backfilling and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Sand filling 20.00%
Backfilling/Berm Forming Work Step
Stage 2 Backfilling 20.00%
Stage 3 Berm 1st Lay 20.00%
Stage 4 Berm 2nd Lay 20.00%
Stage 5 Berm 3rd Lay 10.00%
Stage 6 Final Inspection 10.00%
Progress is calculated based on Cathodic protection and
measured as per following stages:
Stage Description WF for
Cathodic protection Work Step stages
Stage 1 Actual - No. of Cathodic Protection 90.00%
Stage 2 Accepted Total No. of Cathodic 10.00%
Protection
Progress is calculated based on Pre-Commissioning and
measured as per following stages:
Pre-commissioning Work Step Stage Description WF for
stages
Stage 1 Chemical Cleaning (Pigs or GEL Pigs) 12.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 239 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Helium Leak Detection 10.00%
Stage 3 Bolting 6.00%
Stage 4 Hot Oil Flushing 10.00%
Stage 5 Pipe Freezing 10.00%
Stage 6 Foam Inerting 13.00%
Stage 7 Gauging 20.00%
Stage 8 Filling (Flooding) 9.00%

Stage 9 Acceptance 10.00%


Progress is calculated based on Hydrostatic and measured as per
following stages:
Stage Description WF for
Hydrostatic Test Work Step
stages
Stage 1 Actual - No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Pipeline dry and measured as
per following stages:
Stage Description WF for
Pipe Line dry Work Step
stages
Stage 1 Actual - No. of Pipeline Dry 90.00%
Stage 2 Accepted Total Pipe line Dry 10.00%
Progress is calculated based on Filling with Nitrogen and
measured as per following stages:
Filing with Nitrogen/ Discharging Air Work Step Stage Description WF for
stages
Stage 1 Actual - No. of Joints 90.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 240 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Along-Route Road and measured
as per following stages:
Stage Description WF for
Along-Route Road Work Step
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Progress is calculated based on Marker and measured as per
following stages:
Stage Description WF for
Marker Work Step
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Progress is calculated based on Restoration and measured as per
following stages:
Stage Description WF for
Restoration Work Step
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Progress is calculated based on Stockpiling of Pipe and measured
as per following stages:
Stage Description WF for
Stockpiling of Pipe Work Step
stages
Stage 1 Actual - No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Bridge - off take Work Step
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 241 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Bridge - off take and measured
as per following stages:
Stage Description WF for
stages
Stage 1 Actual - No. of Bridge 90.00%
Stage 2 Accepted Total No. of Bridge 10.00%
Progress is calculated based on Valve station and measured as
per following stages:
Stage Description WF for
stages
Stage 1 Ground Levelling (Civil works) 10.00%
Stage 2 Foundation (Civil works) 7.00%
Stage 3 Editing / Welding of Valves (Process 11.00%
works)
Stage 4 Welding of Pipelines (Process works) 8.00%
Stage 5 Coating (Process works) 6.00%
Valve station Work Step Stage 6 Contour of grounding (Electrical 7.00%
works)
Stage 7 TEG Installation (Electrical works) 4.00%
Stage 8 Lightning Protection System 7.00%
( Electrical )
Stage 9 Install Pressure Gauge Transmitter 6.00%
(Instrument works)
Stage Grounds/Gas Temperature 4.00%
10 Transmitter (Instrument works)
Stage PIG Detector (Instrument works) 15.00%
11
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 242 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Optical Cable laying (Instrument 8.00%
12 works)
Stage Installation of Instrument Box 3.00%
13 (Instrument works)
Stage CP Test Connection (Instrument 2.00%
14 works)
Stage Hydro Test / Drying 2.00%
15
Progress is calculated based on Access roads and measured as
per following stages:

Access roads Work Step


Stage Description WF for
stages
Stage 1 Actual - No. of Access Road 90.00%
Stage 2 Accepted Total No. of Access Road 10.00%
Progress is calculated based on Pig launcher and Receiver
installation and measured as per following stages:
Stage Description WF for
stages
Pig launcher and Receiver Work Step
Stage 1 Quantity of Pig Launcher and Receiver 90.00%
installed
Stage 2 Accepted Total No. of Pig Launcher and 10.00%
Receiver installed
Progress is calculated based on Helicopter landing site and
measured as per following stages:
Helicopter landing site Work Step Stage Description WF for
stages
Stage 1 ROW 8.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 243 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Staking 5.00%
Stage 3 Putting earth embankment 10.00%
Stage 4 Installation slabs 8.00%
Stage 5 Putting mixtures surfacing 10.00%
Stage 6 Sealing of joints 7.00%
Stage 7 Painting 10.00%
Stage 8 Access road 8.00%
Stage 9 Putting earth embankment 10.00%
Stage 10 Construction of roadway surfacing 8.00%
Stage 11 Slope strengthening with soil and 8.00%
grass sowing
Stage 12 Installation vane 8.00%
Progress is calculated based on Appurtenances of pipe and
measured as per following stages:
Stage Description WF for
Appurtenances of pipe Work Step stages
Stage 1 Actual - No. of Appurtenance of Pipe 90.00%
Stage 2 Accepted Total No. of Appurtenance 10.00%
of Pipe
Progress is calculated based on Power supply and measured as
per following stages:
Power supply Work Step Stage Description WF for
stages
Stage 1 Power Supply 100.00%
Progress is calculated based on Road Crossings and measured as
Road Crossings Work Step
per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 244 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Actual - No. of Road Crossing 90.00%
Stage 2 Accepted Total No. of Road Crossing 10.00%
Progress is calculated based on HDD River and measured as per
following stages:
Stage Description WF for
HDD River Work Step
stages
Stage 1 Actual - No. of HDD River 90.00%
Stage 2 Accepted Total No. of HDD River 10.00%
Progress is calculated based on River crossing and measured as
per following stages:
Stage Description WF for
River and water channel crossing Work Step stages
Stage 1 Actual - No. of River and Water channel 90.00%
crossing
Stage 2 Accepted Total No. of River and Water 10.00%
channel crossing
Progress is calculated based on Railway and measured as per
following stages:
Work Description WF for
Railway Work Step
Step stages
Step 1 Actual - No. of Railway 90.00%
Step 2 Accepted Total No. of Railway 10.00%
Progress is calculated based on Road crossing (casing) and
Road crossing (casing) Work Step
measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 245 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Actual - No. of Road Crossing (casing) 90.00%
Stage 2 Accepted Total No. of Road Crossing 10.00%
(casing)
Progress is calculated based on Road crossing (excavation) and
measured as per following stages:
Stage Description WF for
Road crossing (excavation) Work Step
stages
Stage 1 Actual - No. of Road Crossing 90.00%
(excavation)
Stage 2 Accepted Total No. of Road Crossing 10.00%
(excavation)
Progress is calculated based on U/G pipeline/cables and
measured as per following stages:
Stage Description WF for
U/G pipeline/cables Work Step stages
Stage 1 Actual - Linear in meters 90.00%
Stage 2 Accepted Total No. of Linear in 10.00%
Meters
Progress is calculated based on Others / Weight Blocks and
measured as per following stages:
Stage Description WF for
Others / Weight Block Work Step stages
Stage 1 Actual - No. of Others / Weight block 90.00%

Stage 2 Accepted Total No. of Others/Weight 10.00%


Block
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 246 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on U/G pipeline/cables and
measured as per following stages:
Stage Description WF for
Embankment protection Work Step stages
Stage 1 Actual - No. of Embankment Protection 90.00%
Stage 2 Accepted Total No. of Embankment 10.00%
Protection
Pre-commissioning & Testing
Progress is calculated based on Piping Pre-commissioning ( by
test Package) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Ready for flushing 15.00%
Work Step Stage 2 Flushing 30.00%
Piping Pre-commissioning ( by test
Package) Stage 3 Reinstatement 15.00%
Stage 4 PID conformity 10.00%
Stage 5 Tightness test 15.00%
WP - 8471 Stage 6 Inerting 5.00%
Stage 7 MCC Package Hand-over 10.00%
Instrumentation Progress is calculated based on SAT and measured as per
following stages:
Stage Description WF for
Site Acceptance Tests ( SAT Work Step
stages
Systems)
Stage 1 Complete SAT 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Mini Loop Check and measured
Mini Loop Check Work Step
as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 247 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Mini Loop Check 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Loop Check and measured as per
following stages:
Stage Description WF for
Loop Check Work Step
stages
Stage 1 Loop Check 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Functional check and measured as
per following stages:
Stage Description WF for
Functional Check Work Step
stages
Stage 1 Functional Check 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Building Pre-commissioning
Electrical
and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Power supply and checking 30.00%
Electrical Generator Stage 2 Control System checking 20.00%
Step 3 Motors run 30.00%
Step 4 Energizing 15.00%
Step 5 Certificate 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 248 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Building Pre-commissioning and
measured as per following stages:
Stage Description WF for
stages
Transformer tests Work Step
Stage 1 Vector group 30.00%
Stage 2 Energization 50.00%
Stage 3 Leak test 10.00%
Stage 4 MCC Package Hand-over 10.00%

Progress is calculated based on Switchgears & MCC Tests and


measured as per following stages:
Stage Description WF for
stages
Stage 1 Megger tests - Hit pot test- Relay testing 30.00%
Switchgears & MCC Tests Work Step
Stage 2 Incomer A tests 15.00%
Stage 3 Incomer B tests 15.00%
Stage 4 Tie-Breaker 15.00%
Stage 5 Intertripping 15.00%
Stage 6 MCC Package Hand-over 10.00%

Progress is calculated based on UPS / Batteries and measured as


per following stages:
Stage Description WF for
UPS / Batteries Work Step stages
Stage 1 UPS 45.00%
Stage 2 Batteries 45.00%
Stage 3 MCC Package Hand-over 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 249 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Electrical Panels (General) and
measured as per following stages:
Stage Description WF for
Electrical Panels (General) Work Step stages
Stage 1 Panels 90.00%
Stage 2
MCC Package Hand-over 10.00%

Progress is calculated based on Electrical cable and measured as


per following stages:
Stage Description WF for
Electrical Cables Work Step
stages
Stage 1 Tests & Megger tests 90.00%

Stage 2 MCC Package Hand-over 10.00%


Building Progress is calculated based on Building Pre-commissioning and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Civil & Secondary 10.00%
Work Step Stage 2 Power distribution/lighting 15.00%
Building Pre-commissioning
Stage 3 F & G System 20.00%
Stage 4 Inergen 20.00%

Stage 5 HVAC System 25.00%


Stage 6 MCC Package Hand-over 10.00%
Pipeline Work Step
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 250 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Pigging & Drying and measured
as per following stages:
Stage Description WF for
stages
Pigging & Drying
Stage 1
Pigging & Drying 90.00%

Stage 2
MCC Package Hand-over 10.00%

Progress is calculated based on MOV Valves- E/I connections


and measured as per following stages:
Stage Description WF for
MOV Valves- E/I connections Work Step stages
Stage 1 90.00%
MOV Valves- E/I connections
Stage 2 MCC Package Hand-over 10.00%
Equipment
Progress is calculated based on Static Equipment and measured
as per following stages:

Stage Description WF for


Work Step
Static Equipment stages
Stage 1 Cleaning / Inspection 45.00%
Stage 2 Box-up 45.00%
Stage 3 MCC Package Hand-over 10.00%
Progress is calculated based on Rotating Equipment and
measured as per following stages:
Rotating Equipment Work Step Stage Description WF for
stages
Stage 1 Chemical cleaning 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 251 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Reinstatement 25.00%
Stage 3 Final Alignment 15.00%
Stage 4 First Oil Filling 40.00%
Stage 5 Certificate 10.00%
Progress is calculated based on Compressors & Blowers and
measured as per following stages:
Stage Description WF for
Compressors & Blowers Work Step stages
Stage 1 Preparation works 25.00%
Stage 2 Pre-commissioning 65.00%
Stage 3
MCC Package Hand-over 10.00%

Progress is calculated based on Pumps motor no load test and


measured as per following stages:
Stage Description WF for
Pumps motor no load test Work Step
stages
Stage 1 Pre-commissioning 90.00%
Stage 2 MCC Package Hand-over 10.00%
Progress is calculated based on Air coolers no load test and
measured as per following stages:
Stage Description WF for
Air coolers no load test Work Step stages
Stage 1 Pre-commissioning 90.00%

Stage 2 MCC Package Hand-over 10.00%

Air coolers load test Work Step


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 252 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Air coolers load test and
measured as per following stages:
Stage Description WF for
stages
Stage 1
Pre-commissioning 90.00%

Stage 2
MCC Package Hand-over 10.00%

Progress is calculated based on Refractory Dry out / Boil out /


inspection and measured as per following stages:
Stage Description WF for
stages
Refractory Dry out / Boil out / inspection Work Step Stage 1
Refractory Dry out / Boil out / inspection 75.00%

Stage 2 Final inspection 15.00%

Stage 3
MCC Package Hand-over 10.00%

Progress is calculated based on Catalyst loading and measured


as per following stages:
Stages Description WF for
stages
Catalyst loading Work Step
Stage 1
Catalyst loading 90.00%

Stage 2
MCC Package Hand-over 10.00%

Progress is calculated based on Steam Blowing and measured as


Steam Blowing Work Step
per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 253 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1
Steam Blowing 90.00%

Stage 2
MCC Package Hand-over 10.00%

Progress is calculated based on Equipment Dossiers and


measured as per following stages:

Stage Description WF for


WP - 848 Equipment Dossiers (No. of Documents) Work Step
stages
Stage 1 Submission 65.00%

Stage 2 Approval 25.00%


Stage 3 Acceptance 10.00%

Progress is calculated based on QA/QC Documents and measured


as per following stages:
Stage Description WF for
stages
WP - 849 QA/QC Documentation (No. of Documents) Work Step Stage 1 Submission 65.00%

Stage 2 Approval 25.00%


Stage 3 Acceptance 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 254 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Materials Documentation and
measured as per following stages:
Stage Description WF for
stages
WP - 850 Materials Documentation ( No. of Documents) Work Step Stage 1 Submission 65.00%

Stage 2 Approval 25.00%


Stage 3 Acceptance 10.00%

Progress is calculated based on Testing & Pre-Commissioning


Documentations and measured as per following stages:
Stage Description WF for
stages
Testing & Pre-Commissioning Documentations
WP - 851 (No. of Documents)
Work Step Stage 1 Submission 65.00%

Stage 2 Approval 25.00%

Stage 3 Acceptance 10.00%

Progress is calculated based on No. of documents and measured


as per following stages:
Stage Description WF for
WP - 852 Design Data ( No. of Documents ) Work Step stages
Stage 1 Submission 65.00%
Stage 2 Approval 25.00%
Stage 3 Acceptance 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 255 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on No. of documents and measured
as per following stages:
Stage Description WF for
stages
WP - 853 As-Built Drawings (No. of Documents) Work Step
Stage 1 Submission 65.00%

Stage 2 Approval 25.00%


Stage 3 Acceptance 10.00%

Progress is calculated based on Close out Report and measured as


per following stages:
Stage Description WF for
stages
WP - 854 Close out Report Work Step Stage 1 Submission 65.00%

Stage 2 Approval 25.00%

Stage 3 Acceptance 10.00%

Progress is calculated based on no of documents and measured


as per following stages:
Stage Description WF for
stages
WP - 855 Ship loose Lists (No. Of Documents) Work Step
Stage 1 Submission 65.00%
Stage 2 Approval 25.00%
Stage 3 Acceptance 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 256 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on As NDT Radiographic Films and
measured as per following stages:
Stage Description WF for
WP - 856 NDT Radiographic Films (No. of Documents) Work Step stages
Stage 1 Submission 65.00%
Stage 2 Approval 25.00%
Stage 3 Acceptance 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 257 of 456

APPENDIX 10: Upstream PMS-INSTALLATION


Work Package : Jacket Installation

Work Package No. WF% Description of Work Package Calculation Description, Detailed Weight Factor or Formula

Procedures & Shop Drawing Progress is calculated according to the procedures and shop Drawing list.
911 Cost
Issuance (Issued/Total)
Work WF for
Description
Step Stages
Step 1 Issue of Purchase Order 25%
based on Monthly manufacturing progress report
Procurement of Installation Step 2 approved by Supply Chain Management or PMT from P/O 55%
912 Cost
Materials issue date until shipment
Step 3 Final Inspection and Release for Shipment 10%
Step 4 Delivery to SITE/ Warehouse 5%
Step 5 VENDOR'S FINAL DOCUMENTATION 5%
913 Preparation Activities When it's done, the progress is 100%.
Cost Mobilization of Transportation Barge
914 When it's done, the progress is 100%.
at Yard
Sail Away and arrive at site
915 Cost When it's done, the progress is 100%.
(Transportation)
916 Cost Mobilization of Derrick Barge When it's done, the progress is 100%.
Work WF for
Description
Step Stages
917 Cost Set Jacket in position Step 1 Positioning of Barge 20%
Step 2 Launching/ Rigging & Lifting 50%
Step 3 Welding 30%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 258 of 456

Based
918 on the Pilling Works (Total No. of Piling performed)/(Total No. of Piles)
Cost
Based
919 on the Installation of Conductors (Total No. of conductor Installed)/(Total No. of Conductors)
Cost
Work WF for
Based Description
Step Stages
920 on the Installation of Boat Landing
Step 1 Rigging & Lifting 50%
Cost
Step 2 Welding 50%
921 Cost Demobilization of Derrick Barge When it's done, the progress is 100%.

922 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)

Work Package No. Topside Installation

Work Package No. WF% Description of Work Package Calculation Description, Detailed Weight Factor or Formula

Procedures & Shop Drawing Progress is calculated according to the procedures and shop Drawing list.
923 M/H
Issuance (Issued/Total)
Work WF for
Description
Step Stages
Step 1 Issue of Purchase Order 25%
based on Monthly manufacturing progress report
Procurement of Installation Step 2 approved by Supply Chain Management or PMT from P/O 55%
924 M/H
Materials issue date until shipment
Step 3 Final Inspection and Release for Shipment 10%
Step 4 Delivery to SITE/ Warehouse 5%
Step 5 VENDOR'S FINAL DOCUMENTATION 5%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 259 of 456

925 Cost Preparation Activities When it's done, the progress is 100%.
926 Mobilization of Barge at Yard When it's done, the progress is 100%.
Cost
927 Sail Away and arrive at site When it's done, the progress is 100%.

928 Cost Mobilization of Derrick Barge When it's done, the progress is 100%.

Work WF for
Description
Step Stages
929, 930 Cost Topside Installation & Welding Step 1 Positioning of Barge 20%
Step 2 Rigging & Lifting 50%
Step 3 Welding 30%
931 Cost Demobilization of Derrick Barge When it's done, the progress is 100%.

932 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)

Work Package No. C13, D13, E13, F13, G4 Ancillaries Installation

Work Package No. WF% Description of Methodology Calculation Description, Detailed Weight Factor or Formula

Procedures & Shop Drawing Progress is calculated according to the procedures & shop Drawing list.
933 M/H
Issuance (Issued/Total)
Work WF for
Description
Step Stages
Step 1 Issue of Purchase Order 25%
Procurement of Installation
934 M/H Based on Monthly manufacturing progress report approved
Materials
Step 2 by Supply Chain Management or PMT from P/O issue date 55%
until shipment
Step 3 Final Inspection and Release for Shipment 10%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 260 of 456

Step 4 Delivery to SITE/ Warehouse 5%


Step 5 VENDOR'S FINAL DOCUMENTATION 5%
935 Preparation Activities When it's done, the progress is 100%.
Cost
936 Mobilization of Barge at Yard When it's done, the progress is 100%.
937 Cost Sail Away and arrive at site When it's done, the progress is 100%.
Preparation Activities & Mobilization
938, 938 Cost When it's done, the progress is 100%.
of Derrick Barge
939 Cost Set-up & Anchoring of Derrick Barge When it's done, the progress is 100%.
Work WF for
Description
Step Stages
940, 941, 942 Cost Bridge Installation & Welding Step 1 Positioning of Barge 20%
Step 2 Rigging & Lifting 50%
Step 3 Welding 30%

943 Cost Demobilization of Derrick Barge When it's done, the progress is 100%.

944 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)

Work Package: L, Subsea

Work Package No. WF% Description of Methodology Calculation Description, Detailed Weight Factor or Formula

Shop Drawing & Procedures Progress is calculated according to the procedures & shop Drawing list.
945 M/H
Issuance (Issued/Total)
Work WF for
Description
Step Stages
Procurement of Installation Step 1 Issue of Purchase Order 25%
946 M/H
Materials Based on Monthly manufacturing progress report approved
Step 2 by Supply Chain Management or PMT from P/O issue date 55%
until shipment
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 261 of 456

Step 3 Final Inspection and Release for Shipment 10%


Step 4 Delivery to SITE/ Warehouse 5%
Step 5 VENDOR'S FINAL DOCUMENTATION 5%
947 Cost HFL Spooling When it's done, the progress is 100%.
948 Cost Spool Fabrication When it's done, the progress is 100%.
Preparation Activities & Mobilization
949, 950 Cost When it's done, the progress is 100%.
of Derrick Barge
951 Cost Sail Away and arrive at site When it's done, the progress is 100%.
Preparation Activities When it's done, the progress is 100%.
952, 953 Cost
Mobilization of Installation Barge When it's done, the progress is 100%.
954 Cost Post Drilling XMT Installation When it's done, the progress is 100%.
955 Cost Post Drilling Pre Survey When it's done, the progress is 100%.
956 Cost Manifold, PLEM & PLET installation When it's done, the progress is 100%.
957 Cost Umbilical HFL & EFL Installation When it's done, the progress is 100%.
958 Cost Spool & Support Installation When it's done, the progress is 100%.
959 Cost Offshore Pipeline Installation When it's done, the progress is 100%.
960 Cost Tie-In works When it's done, the progress is 100%.
961 Cost Pipeline Pre-commissioning When it's done, the progress is 100%.
962 Cost Install Spool Protection cover When it's done, the progress is 100%.

963 Cost Demobilize Installation Barge When it's done, the progress is 100%.

964 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 262 of 456

Work pack: Pipeline

Work Package No. WF% Description of Methodology Calculation Description, Detailed Weight Factor or Formula

Shop Drawing and Procedures Progress is calculated according to the shop Drawing & Procedures list.
965 M/H
Issuance (Issued/Total)
Work WF for
Description
Step Stages
Step 1 Issue of Purchase Order 25%
Based on Monthly manufacturing progress report
Procurement of Installation Step 2 approved by Supply Chain Management or PMT from P/O 55%
966 M/H
Materials issue date until shipment
Step 3 Final Inspection and Release for Shipment 10%
Step 4 Delivery to SITE/ Warehouse 5%
Step 5 VENDOR'S FINAL DOCUMENTATION 5%
967 Preparation Activities When it's done, the progress is 100%.
Cost
968 Mobilization of Barge at Yard When it's done, the progress is 100%.
Cost
969 Sail Away and arrive at site When it's done, the progress is 100%.
Cost Preparation Activities & Mobilization
970, 971 When it's done, the progress is 100%.
of Pipe laying Barge
Cost
972 Lay Pipeline For Pipe lying, progress measurement shall be based on meters of Pipes laid.
Cost
973 Install Jacket Riser When it's done, the progress is 100%.
Cost
974 Install Host Tie-in Riser When it's done, the progress is 100%.
Cost
975 Pipeline Pre-commissioning Based on No. of Test Package.
Cost
976 Demobilization of Pipe laying Barge When it's done, the progress is 100%.
977 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 263 of 456

Work Package : H, I, J, K, M, X
Work Package No. WF% Description of Methodology Calculation Description, Detailed Weight Factor or Formula
Procedures and Shop Drawing Progress is calculated according to the shop Drawing and procedures list.
978 M/H
issuance (Issued/Total)
Work WF for
Description
Step Stages
Step 1 Issue of Purchase Order 25%
Based on Monthly manufacturing progress report approved
Procurement of Installation Step 2 by Supply Chain Management or PMT from P/O issue date 55%
979 M/H
Materials until shipment
Step 3 Final Inspection and Release for Shipment 10%
Step 4 Delivery to SITE/ Warehouse 5%
Step 5 VENDOR'S FINAL DOCUMENTATION 5%
980 Cost Preparation Activities When it's done, the progress is 100%.
981 Mobilization of Barge at Yard When it's done, the progress is 100%.
Cost
982 Sail Away and arrive at site When it's done, the progress is 100%.
Cost Preparation Activities & Mobilization
983, 984 When it's done, the progress is 100%.
of Derrick Barge
985 Cost Installation When it's done, the progress is 100%.
Cost
986 Welding & NDT According to Quantity
Cost
987 Testing & Pre-commissioning According to No. of Test Package
Cost
988 Demobilization of Derrick Barge When it's done, the progress is 100%.

989 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)

990 to 998 M/H Pre Shutdown /Shutdown/Post SD. When it's done, the progress is 100%.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 264 of 456

APPENDIX 11: Upstream PMS-HOOK-UP AND COMMISSIONING

Work Package: C1, D1, E1, F1


Work Package No. WF% Description of Work Package Calculation Description, Detailed Weight Factor or Formula
Progress is calculated according to the shop Drawing list.
1111 M/H Work order and Shop Drawing Engineering
(Issued/Total)
Work
Description WF
Step
Step 1 Issue of Purchase Order 25%

Monthly manufacturing progress report


Step 2 approved by Supply Chain Management or 45%
1112 M/H Procurement of HUC Materials PMT from P/O issue date until shipment Procurement

Step 3 Final Inspection and Release for Shipment 10%

Step 4 Delivery to SITE/ Warehouse 15%

Step 5 VENDOR'S FINAL DOCUMENTATION 5%


1113 Onshore Preparation Activities When it's done, the progress is 100%.
M/H Prefabrication
1114 Prefabrication When it's done, the progress is 100%.
M/H Preparation Activities When it's done, the progress is 100%.
M/H Mobilization of Work Boat When it's done, the progress is 100%.
1115 M/H Set up Anchor at site When it's done, the progress is 100%. Hook Up
Work
M/H Facilities Hook Up Description WF
Step
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 265 of 456

The WBS shall be broken down to system,


subsystem and Discipline for assigning the
MH required for each activity which is
Step 1 90%
considered as WF for it. The progress of
each activity will be measured according to
Quantity of the work.

Step 2 MCC 10%

Work
Description WF
Step

The WBS shall be broken down to system,


subsystem and Discipline for assigning the
MH required for each activity which is
Post Drilling Hook Up Step 1 90%
considered as WF for it. The progress of
each activity will be measured according to
Quantity of the work.

Step 2 MCC 10%

Flow Line Tie in


Host Tie in

1116 M/H Commissioning Each subsystem commissioning will be 100% when it is completed. Commissioning

1116 M/H Demobilization of the Boat When it's done, the progress is 100%.
Demob. & Final
Doc.
1117 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)

11121 to 11129 M/H Pre-shut down Activities When it's done, the progress is 100%. Shut Down
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 266 of 456

11121 to 11129 M/H Shut Down Activities When it's done, the progress is 100%.

11121 to 11129 M/H Post Shut Down Activities When it's done, the progress is 100%.
Activity ID Activity Description MH Needed Progress Earned MH
Air Compressor/Dryer Package
Air Compressor Package
Electrical
123-01-EL-01 Rect. of Elect. Punch of Air Compressor 35 10% 3.5
Air Dryer Package
Instrument
123-02-IN-01 Rect. of Inst. Punch of Air Compressor 20 10% 2
Air Receiver System
Mechanical
123-03-ME-01 Rect. of Inst. Phi. Punch of Air Compressor 40 20% 8
Air Distribution System

Instrument

123-04-IN-01 Install PSV 15 10% 1.5


110 15
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 267 of 456

APPENDIX 12: UPSTREAM PMS-DRILLING

Control Account TA: Pre Drilling Activities


Control Weight Description of Control
Methodology Calculation Description, Detailed Weight Factor or Formula
Account No. Factor Account

TA1 0% Noop Preparation Milestone The total progress (100%) will be achieved once the notice of Rig is issued.

Progress of each procurement item is calculated as per following stages:

WF for
Stages Description
Stages

Based on the Procurement of Stage


TA2 Work Step Issue of Purchase Order 20%
cost Equipment & Material 1
Manufacturing & Delivery to SITE/ Warehouse (Once the
Stage
material receives on site or warehouse the progress will 75%
2
be 100%)
Stage
VENDOR'S FINAL DOCUMENTATION 5%
3

1. Physical Progress shall be calculated according to the distance (Between 0


Based on the
TA3 Rig mobilization Base Distance to 200 Mile)
cost
2. WF for Rig mobilization should be calculated based on the cost

1. Physical progress for rig up shall be calculated based on the daily progress
Based on the
TA4 Rig up Parametric report.
cost
2. WF of Rig up should be calculated based on the cost
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 268 of 456

Control Account TB: Drilling


Activities
Control Weight Description of Control
Methodology Calculation Description, Detailed Weight Factor or Formula
Account No. Factor Account
Total progress (100%) will be achieved once drilling of the each pertinent
Based on the
TB1 Rig Operation Base Depth hole to be completed. Drilling rig Operation progress is deemed equal to
cost
drilling operation progress in each month.
Progress of each logistic item is calculated as per following:
WF for
Stages Description
Stages
Logistics Base Setup, The total progress (100%) will be
Based
achieved once the Logistics Base requirements including
1 on the
warehouse, yard and office have been setup, equipped
cost
and approved by PCSB.
Logistics Contracts, The total progress (100%) will be
Based
achieved once the Logistics Contracts (Port Services,
2 on the
Supply Boats, Fast Crew Boats & Helicopter Services)
Based on the cost
TB2 Logistic have been awarded and approved by PCSB.
cost
Logistics Operation of Hole, Total progress (100%) will Based
Milestone be achieved once drilling of the each pertinent hole to on the
be completed. cost
Logistics Operation of Well Testing (Appraisal and
Based
Vertical Well), Total progress (100%) will be achieved
on the
3 once testing operation of the appraisal and vertical well
cost
to be completed.
Logistics Operation of Completion, The total progress
Based
(100%) will be achieved once completion operation of
on the
each pertinent well to be performed and should be
cost
ready to handover for production.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 269 of 456

This item is depend on the project and Progress of each Well item is
TB3 Well #01
calculated as per following stages:

WF for
Stages Description
Stages

Well Killing progress is on and off and will be 100% after


1 5.00%
completion of the work
TB31 Plug & Abondment Milestone Tubing Cut & Retrieval progress is on and off and will be
2 35.00%
100% after completion of the work

Plug and Abandonment progress is on and off and will


3 60.00%
be 100% after completion of the work
Based on
the cost
Total progress (100%) will be achieved once drilling of the each pertinent
hole to be completed. (according to the depth drilled)

WF for
Stages Description
Stages
Based
TB32 Drilling Operation Work Step
on the
1 Hole Section Drilling cost of
each
section
Based
2 Casing Running and Cementing on the
cost
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 270 of 456

Progress of each Well item is calculated as per following stages:

WF for
Stages Description
Stages
TB33 Formation Evaluation Milestone
Coring progress is on and off and will be 100% after
1 89.00%
completion of the work

Well Testing progress is on and off and will be 100%


2 11.00%
after completion of the work
The total progress (100%) will be achieved once completion operation of
each pertinent well to be performed and should be ready to handover for
production. Physical progress for each section shall be calculated by the
milestone method which is finishing milestone and after completion each
well completion, aforesaid item will be measured 100% and otherwise
progress is 0%.
WF for
Stages Description
Stages

TB34 Well Completion 1 Scrapper 25.00%

2 Lower Completion 25.00%


Milestone
3 Upper Completion 25.00%

4 Install X-Mas Tree 25.00%


PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 271 of 456

Control Account TC: Post Drilling Activities


Control Weight Description of Control
Methodology Calculation Description, Detailed Weight Factor or Formula
Account No. Factor Account
Physical progress for rig down shall be calculated by the milestone method
Based on the
TC1 Rig Down Milestone which is finishing milestone and after completion of drilling activities ,
cost
aforesaid item will be measured 100% and otherwise progress is 0%.

Physical progress for rig demobilization shall be calculated by the milestone


Based on the
TC2 Rig Demobilization Milestone method which is finishing milestone and after completion rig down,
cost
aforesaid item will be measured 100% and otherwise progress is 0%.

Control Account SD: Management Activities

Control Weight Description of Control


Methodology Calculation Description, Detailed Weight Factor or Formula
Account No. Factor Account
Progress of management is based upon and corresponded with the actual
Management & Offshore/Onshore Drilling Progress ratio. Total progress (100%) of
TD1 Man-Hour -
Supervision Management will be achieved once physical progress of 100% to be
achieved
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 272 of 456

APPENDIX 13: Upstream PMS- PROJECT CLOSURE

Control Account 1: Project Closure Report


Control
Weight
Account Description of Control Account Methodology Calculation Description, Detailed Weight Factor or Formula
Factor
No.
1- Physical progress shall be calculated by the milestone method which is
Obtain Formal Sign off and final finishing milestone, aforesaid item will be measured 100% and otherwise
Milestone
acceptance of the product progress is 0%.
2-WF shall be calculated based on the M/H
1- Physical progress shall be calculated by the milestone method which is
finishing milestone, aforesaid item will be measured 100% and otherwise
Update Project Records Milestone
progress is 0%.
2-WF shall be calculated based on the M/H
1- Physical progress shall be calculated by the milestone method which is
Make final payments and finishing milestone, aforesaid item will be measured 100% and otherwise
UA 50% Milestone
complete Cost records progress is 0%.
2-WF shall be calculated based on the M/H
1- Physical progress shall be calculated by the milestone method which is
Hand off the completed project finishing milestone, aforesaid item will be measured 100% and otherwise
Milestone
deliverables to Operations progress is 0%.
2-WF shall be calculated based on the M/H
1- Physical progress shall be calculated by the milestone method which is
Create and distribute a final finishing milestone, aforesaid item will be measured 100% and otherwise
Milestone
report of project performance progress is 0%.
2-WF shall be calculated based on the M/H
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 273 of 456

Control Account 2: Lessons Learned Documents


Control
Weight
Account Description of Control Account Methodology Calculation Description, Detailed Weight Factor or Formula
Factor
No.
Update corporate processes,
1-Progress is on and off and will be 100% after completion of the work
Procedures, and template based Milestone
2-WF shall be calculated based on the M/H
on the lessons learned
UB 50%
Gather and create final lessons 1-Progress is on and off and will be 100% after completion of the work
Milestone
learned 2-WF shall be calculated based on the M/H
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 274 of 456

APPENDIX 14: Downstream PMS- WEIGHT FACTOR CALCULATION


OVERALL PROJECT PROGRESS

The physical progress for the overall project is obtained by summing up the physical weighted progress
of each phase:

 FEL 1 – Initiation
 FEL 2 – Scope Selection
 FEL 3 – Scope Definition
 Execution

The corresponding weight factors are determined initially in accordance with the respective cost
values, as defined by the project cost breakdown structure.

For calculating the Level 1 Weight Factor (L1 WF) for each phase follows these steps:

4. Find the project total budget. In this example the total is RM1,000,000
5. Find the budget of each phase
6. To calculate the phase weight factor use this formula:

𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑃ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1) = × 100%
𝑃𝑟𝑜𝑗𝑒𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 45,000
𝐹𝐸𝐸𝐷 𝑊𝐹 (𝐿1) = × 100% = 4.5%
𝑅𝑀 1,000,000

Budget
Level 1 Weight
No. Phase
Factor (L1 WF)%
(RM '000)

1 Project Management 25,000 2.5

2 Initiation 10,000 1.00

3 Conceptual Engineering Services 20,000 2.00

4 FEED 45,000 4.5

5 Execution 900,000 90.00

Total 1,000,000 100.00

Note: The summation of L1 WF for all phases has to be 100%


PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 275 of 456

Project Management

Project Management is broken down in 10 sub phases. For calculating Level 2 Weight Factor (L2 WF):

5. Find the phase budget. In this example the total is RM 25,000.


6. Find the budget of each sub phase.
7. To calculate the sub phase weight factor use this formula:

𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡


𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 (𝑑𝑖𝑠𝑐𝑖𝑝𝑙𝑖𝑛𝑒) 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 6,000
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 24%
𝑅𝑀 25,000

8. (L1 WF) for sub phase/discipline is its share portion at Project level rather than its parent
level WF (i.e. Phase) it can be calculated.

(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 (𝑑𝑖𝑠𝑐𝑖𝑝𝑙𝑖𝑛𝑒) 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(24% × 2.5%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 (𝐿1 𝑊𝐹) = = 0.6%
100%

Budget Budget
Phase (L1 WF)% Sub-Phase / Discipline (L2 WF)% (L1 WF)%
(RM '000) (RM '000)

Project
25000 2.5
Management
Initiation 1000 4.4 0.11
Conceptual
4500 18 0.45
Engineering
FEED 1900 7.6 0.19
Detail Engineering 3000 12 0.30
Procurement PCSB
2500 10 0.25
Supplied Materials
Construction 5000 20 0.50

Commissioning 3000 12 0.30

Project Closure 4000 16 0.40

Total 25000 100.00 2.5


PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 276 of 456

Initiation

Initiation is broken down to two contracts. Same as phase level each contract has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. For calculating Level 2 Weight Factor (L2WF):

4. Find the phase budget. In this example the total is RM 10,000


5. Find the budget of each contract.
6. To calculate the contract weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 10,000
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑆𝑒𝑟𝑣𝑖𝑐𝑒𝑠 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 100.00%
𝑅𝑀 10,000

Budget (L1 Budget


Phase Contracting (L2 WF)% (L1 WF)%
(RM '000) WF)% (RM '000)

Initiation 10,000 1 - - - -

Contracting In House 10,000 100.00 1.00

Total 10,000 100.00 1.00

For in house services there are some sub phases. Same as Phase level each sub-phase has its own
budget (accessible from budget estimation from cost control/finance dept.) and accordingly each of
them has their own weight factor. Contract No.1 is broken up in 4 sub-phases. For calculating Level 3
Weight Factor (L3 WF):

6. Find the Contract total budget. In this example the Total for contract in house is RM 10,000
and for In house service is RM 10,000

7. Find the budget of each Sub phase.

8. To calculate the Sub phase weight factor use this formula:

𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 3,000
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 30.00%
𝑅𝑀 10,000

9. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 277 of 456

(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(30% × 100%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿2 𝑊𝐹) = = 30.00%
100%

10. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(30% × 1%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿1 𝑊𝐹) = = 0.30%
100%

Budget (L3WF)
Contracting Budget (RM '000) (L2 WF)% Sub-Phase / Discipline (L2 WF)% (L1 WF)%
(RM '000) %

In House 10,000 100.00


Pre Bidding 0 0.00 0.00 0.00
Bid/Evaluate/Award 0 0.00 0.00 0.00
Conceptual
3000 30.00 30.00 0.30
Development
PMT Deliverable 2500 25.00 25.00 0.25
Feasibility Studies 4500 45.00 45.00 0.45
Total 10,000 100.00 100.00 1.00

Level 4 WF: Not Applicable in WBS

For calculating Level 5 Weight Factor (L5 WF):

7. Find the Sub phase total budget. In this example the Total for facilities feasibility studies is
RM 4,500.
8. Find the budget of each Control Account.
9. To calculate the Control account weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝐵𝑢𝑑𝑔𝑒𝑡


𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:
𝑅𝑀 450
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100% = 10%
𝑅𝑀 4,500

10. (L3 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 278 of 456

Example:
(10% × 45%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙(𝐿3 𝑊𝐹) = = 4.5%
100%

11. (L2 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

Example:
(10% × 45%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 (𝐿2𝑊𝐹) = = 4.5%
100%

12. (L1 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:
(10% × 0.45%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 (𝐿1 𝑊𝐹) = = 0.05 %
100%

Budget
Budget (L3 Control (L3WF)
Sub-Phase (RM (L5WF)% (L2 WF)% (L1 WF)%
(RM '000) WF)% Account %
'000)

Facilities
Feasibility 4,500 45.00
Studies
General 450 10 4.5 4.5 0.05
HSE 1350 36 16.2 16.2 0.16
Facility
2450 54 24.3 24.3 0.24
Assessment
Total 4,500 100 45 45 0.45

For calculating Level 6 Weight Factor (L6 WF):

8. Find the control account total budget. In this example the Total for general is RM 450.
9. Find the budget of each work package.
10. To calculate the work packages weight factor use this formula:

𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡

Example:

180
Preliminary Concept Development 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100 = 40 %
450
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 279 of 456

11. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%

Example:

(40% × 10%)
Preliminary Concept Development(𝐿5 𝑊𝐹) = =4%
100%

12. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:

(40% × 4.5%)
Preliminary Concept Development (𝐿3 𝑊𝐹) = = 1.80 %
100%

13. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

Example:

(40% × 4.5%)
Preliminary Concept Development (𝐿2 𝑊𝐹) = = 1.80 %
100%

14. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(40% × 0.05%)
Preliminary Concept Development(𝐿1 𝑊𝐹) = = 0.02 %
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 280 of 456

Budget (L5 Budget


Control (L2 (L1
(RM WF) Work Package (RM (L6WF) (L5WF) (L3W
Account WF)% WF)%
'000) % '000) % % F)%
General 450 10
Preliminary
Concept 180 40.00 4.00 1.80 1.80 0.02
Development
Environment
Preliminary
270 60.00 6.00 2.70 2.70 0.03
Assessment &
Report
Total 450 100.0 10.00 4.50 4.50 0.05

Conceptual Engineering Services

Conceptual Engineering Services is broken down to two contracts. Same as phase level each contract
has its own budget (accessible from budget estimation from cost control/finance dept.) and
accordingly each of them has their own weight factor. For calculating Level 2 Weight Factor (L2WF):

5. Find the phase budget. In this example the total is RM 20,000


6. Find the budget of each contract.
7. To calculate the contract weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 3,000
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑆𝑒𝑟𝑣𝑖𝑐𝑒𝑠 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 15.00%
𝑅𝑀 20,000

𝑅𝑀 17,000
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 85.00%
𝑅𝑀 20,000

8. (L1 WF) for sub phase/discipline is its share portion at Project level rather than its parent
level WF (i.e. Phase) it can be calculated.
(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 (𝑑𝑖𝑠𝑐𝑖𝑝𝑙𝑖𝑛𝑒) 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(85% × 2%)
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 (𝐿1 𝑊𝐹) = = 1.70%
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 281 of 456

Budget (RM Budget (RM


Phase (L1 WF)% Contracting (L2 WF)% (L1 WF)%
'000) '000)

Conceptual
Engineering 20,000 2 - - - -
Services
Contracting In House 3,000 15.00 0.30
Contract No.1 17,000 85.00 1.70

Total 20,000 100.00 2.00

For each contract there are some sub phases. Same as Phase level each sub-phase has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. Contract No.1 is broken up in 4 sub-phases. For calculating Level 3 Weight
Factor (L3 WF):

8. Find the Contract total budget. In this example the Total for contract No.1 is RM 17,000 and
for In house service is RM 3,000
9. Find the budget of each Sub phase.
10. To calculate the Sub phase weight factor use this formula:

𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀10,200
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 60.00%
𝑅𝑀 17,000

11. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated
(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(60% × 85%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿2 𝑊𝐹) = = 51.00%
100%
12. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(60% × 1.7%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿1 𝑊𝐹) = = 1.02%
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 282 of 456

Budget (RM (L2 Budget (RM (L3WF) (L2 (L1


Contracting Sub-Phase / Discipline
'000) WF)% '000) % WF)% WF)%

In House 3,000 15.00


Planning 1500 50.00 7.5 0.15
Concept Select 1500 50.00 7.5 0.15
Total 3,000 100.00 15.00 0.30

Budget (RM (L2 Budget (RM (L3WF) (L2 (L1


Contracting Sub-Phase / Discipline
'000) WF)% '000) % WF)% WF)%

FEL2 17,000 85.00


Pre Bidding 3400 20 17 0.34
Bid/Evaluate/Award 3400 20 17 0.34
Detailed Feasibility
10200 60 51 1.02
Studies
Total 17,000 100.00 85.00 1.70

For calculating Level 4 Weight Factor (L4 WF):

Find the sub phase total budget. In this example the Total budget for Detailed Feasibility
Studies is RM 10200.

7. Find the budget of each facility.


8. To calculate the facility weight factor use this formula:

𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝐵𝑢𝑑𝑔𝑒𝑡
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿4𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 10,200
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 𝑊𝐹 (𝐿4𝑊𝐹) = × 100% = 100%
𝑅𝑀 10,200

9. (L3 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿4𝑊𝐹 × 𝐿3𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:

(100% × 60.0%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 (𝐿3 𝑊𝐹) = = 60.00 %
100%

10. (L2 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 283 of 456

(𝐿4𝑊𝐹 × 𝐿2𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

Example:

(100% × 51%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 (𝐿2𝑊𝐹) = = 51 %
100%

11. (L1 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿4𝑊𝐹 × 𝐿1𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(100% × 1.02%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 (𝐿1 𝑊𝐹) = = 1.02 %
100%

Budget Budget
Sub-Phase (L3 WF)% Facility (L4WF)% (L3WF)% (L2 WF)% (L1 WF)%
(RM '000) (RM '000)

Detailed
Feasibility 10,200 60
Studies
Refinery
10,200 100.00 60.00 51.00 1.02
Facilities
Crude
0 0.00 0.00 0.00 0.00
Distillation
Total 10,200 100.00 60.00 51.00 1.02

For calculating Level 5 Weight Factor (L5 WF):

7. Find the Sub phase or Facility total budget. In this example the Total for concept select is
RM 1,500.
8. Find the budget of each Control Account.
9. To calculate the Control account weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝐵𝑢𝑑𝑔𝑒𝑡


𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡/𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦

Example:
𝑅𝑀 300
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿5 𝑊𝐹) = × 100% = 20%
𝑅𝑀 1,500

10. (L3 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 284 of 456

(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:
(20% × 50%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠(𝐿3 𝑊𝐹) = = 10%
100%

11. (L2 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

Example:
(20% × 7.50%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿2𝑊𝐹) = = 1.5%
100%

12. (L1 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:
(20% × 0.15%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿1 𝑊𝐹) = = 0.03 %
100%

Budget Budget
Control (L5WF) (L3WF)
Sub-Phase (RM (L3 WF)% (RM (L2 WF)% (L1 WF)%
Account % %
'000) '000)

Concept Select 1,500 50.00


PMT
120 8 4 0.6 0.01
Deliverables
Facilities
Conceptual 1080 72 36 5.4 0.11
Design
Pre FEED
300 20 10 1.5 0.03
Activities

Total 1,500 100.00 50.00 7.50 0.15


PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 285 of 456

For calculating Level 6 Weight Factor (L6 WF):

6. Find the control account total budget. In this example the Total for PMT Deliverable is RM
150.
7. Find the budget of each work package.
8. To calculate the work packages weight factor use this formula:

𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡

Example:

37.5
Project Risk Analysis 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100% = 25.00%
150

9. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%

Example:

(25% × 8%)
Project Risk Analysis (𝐿5 𝑊𝐹) = = 2%
100%

10. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:

(25% × 4%)
Project Risk Analysis (𝐿3 𝑊𝐹) = = 1%
100%

13. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

Example:

(25% × 0.6%)
Project Risk Analysis (𝐿2 𝑊𝐹) = = 0.15 %
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 286 of 456

14. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(25% × 0.01%)
Project Risk Analysis(𝐿1 𝑊𝐹) = = 0.0025 %
100%

Control Budget (RM Budget (L6WF)% (L5WF)% (L3WF)%


(L5 WF)% Work Package (L2 WF)% (L1 WF)%
Account '000) (RM '000)

PMT
Deliverable
150 8
Project Risk
37.5 25.00 2 1 0.15 0.0025
Analysis
QRA 37.5 25.00 2 1 0.15 0.0025
Preparation
37.5 25.00 2 1 0.15 0.0025
of PCPP
OCS 37.5 25.00 2 1 0.15 0.0025

Total 150 100.00 8.00 4.00 0.60 0.01

FEED

All Level weight factors for FEED will be calculated same as Conceptual design services and Execution
phase.

EXECUTION

For Execution phase there are two contracts. Same as phase level each contract has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. For calculating Level 2 Weight Factor (L2WF):

5. Find the phase budget. In this example the total is RM 900,000


6. Find the budget of each contract.
7. To calculate the contract weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 315,000
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑆𝑒𝑟𝑣𝑖𝑐𝑒𝑠 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 35%
𝑅𝑀 900,000
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 287 of 456

𝑅𝑀 585,000
𝐸𝑃𝐶𝐼𝐶 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 65%
𝑅𝑀 900,000

8. (L1 WF) for contracting is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(65% × 90%)
𝐸𝑃𝐶𝐶 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 (𝐿1 𝑊𝐹) = = 58.5%
100%

Budget
Phase (L1 WF)% Sub-Phase / Discipline Budget (RM '000) (L2 WF)% (L1 WF)%
(RM '000)

Execution 900,000 90 - - - -

Contracting In House 315,000 35 31.50

EPCC Contract 585,000 65 58.50

Total 900,000 100.00 90

For each contract there are some sub phases. Same as Phase level each sub-phase has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. EPCC Package is broken up in 4 sub-phases. For calculating Level 3 Weight
Factor (L3 WF):

6. Find the Contract total budget. In this example the Total for EPCC Contract is RM 585,000.
7. Find the budget of each Sub phase.
8. To calculate the Sub phase weight factor use this formula:

𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 57,000
𝐶𝑜𝑚𝑚𝑖𝑠𝑠𝑖𝑜𝑛𝑖𝑛𝑔 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 9.74%
𝑅𝑀 585,000

9. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated

(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 288 of 456

Example:

(9.74% × 65%)
𝐶𝑜𝑚𝑚𝑖𝑠𝑠𝑖𝑜𝑛𝑖𝑛𝑔 (𝐿2 𝑊𝐹) = = 6.33%
100%

10. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(9.74% × 58.5%)
𝐶𝑜𝑚𝑚𝑖𝑠𝑠𝑖𝑜𝑛𝑖𝑛𝑔 (𝐿1 𝑊𝐹) = = 5.7%
100%

Budget
Contracting (L2 WF)% Sub-Phase / Discipline Budget (RM '000) (L3WF)% (L2 WF)% (L1 WF)%
(RM '000)

EPCC 585,000 65
Detail Engineering 60,000 10.26 6.67 6
Procurement 177,000 30.26 19.67 17.7
Construction 272,000 46.50 30.22 27.2
Commissioning 57,000 9.74 6.33 5.7
Contract Closure
19,000 3.25 2.11 1.9
Report
Total 585,000 100 65 58.5

For each sub-phase there are facility, Control account and work packages. Same as Phase level and
Sub-phase, each facility has its own budget (accessible from budget estimation from cost control,
finance and contract dept.) and accordingly each of them has their own weight factor. In this example
Fabrication is broken up in 2 facilities.

For calculating Level 4 Weight Factor (L4 WF):

7. Find the Sub phase total budget. In this example the Total for Construction is RM 272,000.
8. Find the budget of each facility.
9. To calculate the facility weight factor use this formula:

𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝐵𝑢𝑑𝑔𝑒𝑡
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿4 𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

𝑅𝑀 190,400
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑖𝑒𝑠 𝑊𝐹 (𝐿4 𝑊𝐹) = × 100% = 70%
𝑅𝑀 272,000
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 289 of 456

10. (L3 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿4𝑊𝐹 × 𝐿3𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:

(70% × 46.5%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑖𝑒𝑠 (𝐿3 𝑊𝐹) = = 32.55 %
100%

11. (L2 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿4𝑊𝐹 × 𝐿2𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%

Example:

(70% × 30.22%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑖𝑒𝑠 (𝐿2𝑊𝐹) = = 21.15 %
100%

12. (L1 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.

(𝐿4𝑊𝐹 × 𝐿1𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(70% × 27.2%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑖𝑒𝑠 (𝐿1 𝑊𝐹) = = 19.04 %
100%

Budget (L3 Budget (RM


Sub-Phase Facility (L4WF)% (L3WF)% (L2 WF)% (L1 WF)%
(RM '000) WF)% '000)

Construction 272,000 46.5


Refinery
190,400 70.00 32.55 21.15 19.04
Facilities
LPG
Treating 81,600 30.00 13.95 9.07 8.16
Unit
Total 272,000 100.00 46.5 30.22 27.20
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 290 of 456

For each facility there are Control accounts. Same as Phase level and Sub-phase each control accounts
has its own budget (accessible from budget estimation from cost control, finance and Contract dept.)
and accordingly each of them has their own weight factor. In this example Refinery is broken up in 9
control accounts.

For calculating Level 5 Weight Factor (L5 WF):

8. Find the facility total budget. In this example the Total for Refinery is RM 190,400.
9. Find the budget of each control account.
10. To calculate the control account weight factor use this formula:

𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100%
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦

Example:

135,400
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝐴𝑟𝑒𝑎 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100 = 71.11 %
190,400

11. (L4 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿4𝑊𝐹)
𝑊𝐹 (𝐿4 𝑊𝐹) =
100%

Example:

(71.11% × 70%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝐴𝑟𝑒𝑎 (𝐿4 𝑊𝐹) = = 49.78 %
100%

12. (L3 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:

(71.11% × 32.55%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝐴𝑟𝑒𝑎 (𝐿3 𝑊𝐹) = = 22.76 %
100%

13. (L2 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 291 of 456

Example:

(71.11% × 21.15%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝐴𝑟𝑒𝑎 (𝐿2 𝑊𝐹) = = 15.04 %
100%

14. (L1 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.

(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(71.11% × 19.04%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝐴𝑟𝑒𝑎 (𝐿1 𝑊𝐹) = = 13.54 %
100%

Budget
Budget (L5WF)% (L4WF) (L3WF)%
Facility (RM (L4 WF)% Control Account (L2 WF)% (L1 WF)%
(RM '000) %
'000)
190
Refinery 70
,400
Front End
Activities/Mob 4,000 2.1 1.47 0.68 0.44 0.4
ilization
Engineering
10,000 5.25 3.68 1.71 1.11 1
/Shop Drawing
Process Area 135,400 71.11 49.78 23.15 15.04 13.54
Utility &
7,000 3.68 2.57 1.2 0.78 0.7
Building
Storage Area 20,000 10.5 7.35 3.42 2.22 2
Offsite 5000 2.63 1.84 0.85 0.56 0.5
Pipeline 4500 2.36 1.65 0.77 0.5 0.45
Pre-
2500 1.31 0.92 0.43 0.28 0.25
commissioning
Final
2,000 1.05 0.74 0.34 0.22 0.2
Documentation
Total 190,400 100 70 32.55 21.15 19.04

For each control account there are work packages. Same as Phase level and Sub-phase, each work
package has its own budget (accessible from budget estimation from cost control, finance and
contract dept.) and accordingly each of them has their own weight factor. In this example yard
fabrication is broken up in 8 work packages.

For calculating Level 6 Weight Factor (L6 WF):

9. Find the control account or facility total budget. In this example the Total for
Engineering/Shop Drawing is RM 10,000.
10. Find the budget of each work package.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 292 of 456

11. To calculate the work package weight factor use this formula:

𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝐵𝑢𝑑𝑔𝑒𝑡

Example:

2,150
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100% = 21.5 %
10,000

12. (L5 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%

Example:

(21.5% × 5.25%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 (𝐿5 𝑊𝐹) = = 1.13 %
100%

13. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿4𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿4 𝑊𝐹) =
100%

Example:

(21.5% × 3.68%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 (𝐿4 𝑊𝐹) = = 0.79 %
100%

14. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%

Example:

(21.5% × 1.71%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 (𝐿3 𝑊𝐹) = = 0.37 %
100%

15. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 293 of 456

Example:

(21.5% × 1.11%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 (𝐿2 𝑊𝐹) = = 0.239 %
100%

16. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.

(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%

Example:

(21.5% × 1%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 (𝐿1 𝑊𝐹) = = 0.215 %
100%

Budget
Control Work Budget (L6WF)% (L5WF)% (L4WF)% (L3WF)%
(RM (L5 WF)% (L2 WF)% (L1 WF)%
Account Packages (RM '000)
'000)
Engineering
/Shop 10,000 5.25
Drawing
General 750 7.5 0.39 0.28 0.13 0.083 0.075
Process 2,150 21.5 1.13 0.79 0.37 0.239 0.215
Equipment 1,300 13 0.68 0.48 0.22 0.144 0.13
Civil &
1,100 11 0.58 0.4 0.19 0.122 0.11
Structural
Piping 2,250 22.5 1.18 0.83 0.38 0.25 0.225
Electrical 950 9.5 0.5 0.35 0.16 0.105 0.095
Instrument 1,100 11 0.58 0.4 0.19 0.122 0.11
Other 400 4 0.21 0.15 0.07 0.044 0.04
Total 10,000 100 5.25 3.68 1.71 1.11 1.00

Weight factor for Level 7 shall be calculated based on budgeted cost/man hour.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 294 of 456

APPENDIX 15: Downstream PMS- FEL 1


Sub Phase: A1- Pre-Bidding

Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Progress of each pre-bidding item is calculated as per
following stages:

WF for
Stages Description
Stages

Tender Plan & ITB Preparation


- A1 Man-Hour Pre-Bidding Work Step Stage 1 -If the Tender Plan is issued equal to 35%
100% otherwise 0%

Stage 2 Tender Plan Approval 15%

ITB
Stage 3 - If the ITB is issued equal to 100% 50%
otherwise 0%
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Progress of each bidding item is calculated as per following
Bidding/ stages:
- A2 Man-Hour Evaluate/ Work Step
Award WF for
Stages Description
Stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 295 of 456

RFQ
Stage 1 - If the Inquiry is issued equal to 10%
100% otherwise 0%
TBE
Stage 2 - If the TBE is performed equal to 25%
100% otherwise 0%
CBE
Stage 3 -, If the CBE is performed equal to 25%
100% otherwise 0%
PETRONAS Approval of Award
- If the vendor/contractor is selected
Stage 4 40%
and PO place equal to 100%
otherwise 0%
Control Account: Project Control Initiation
Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base

Schedule & Work Step Description WF for


121 Budget Work Step stages
Development Step 1 Schedule Baseline development 65.00%
AA Man-Hour Step 2 Cost Baseline Development 35.00%

Work Step Description WF for


Schedule Risk stages
122 Work Step
Analysis Step 1 SRA session conducting 60.00%
Step 2 SRA Report Issuance 40.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 296 of 456

Deliverable Description WF for


stages
I. PCPP Compliance
1.1 Planning & Scheduling 67
Project Scope of Work and
2.53
1.1.1 Objectives
1.1.2 Schedule Basis Memorandum (SBM) 3.79
1.1.3 Work Breakdown Structure (WBS) 3.79
Organization Breakdown Structure
3.79
1.1.4 (OBS)
Project Management Team (PMT)
6.32
1.1.5 Manpower Plan
Project Execution Schedule (Baseline
Preparation of 16.43
123 Deliverable 1.1.6 Schedule)
PCPP 1.1.7 Quantitative Risk Analysis (QRA) 12.64
1.1.8 Critical Path 2.53
1.1.9 Progress Base 3.79
1.1.10 Progress S-Curve 2.53
1.1.11 Progress Measurement Format 2.53
1.1.12 Resource Plan 2.53
1.1.13 Project Roadmap 1.26
1.1.14 Project Progress Report 1.26
1.1.15 Project Close-Out Report 1.26
1.2 Cost Control 23
1.2.1 Cost Breakdown Structure (CBS) 0.88
1.2.2 Project Total Budget 2.65
1.2.3 Work Program & Budget (WPB) 7.08
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 297 of 456

1.2.4 Corporate Plan & Budget (CPB) 7.08


1.2.5 Approved For Expenditure 0.88
Additional Budget (Budget Transfer
1.2.6 0.88
and Supplementary Budget)
1.2.7 Additional Budget Request 0.88
1.2.8 Change Order Register 0.88
1.2.9 Monthly Cost Report 0.88
1.2.10 Project Close-Out Report 0.88
II TP & PMO Endorsement 5
PCPP Reviewed and Endorsed by TP
2.1 5.00
and PMO (DPP)
III PM Approval 5
PCPP Reviewed and Approved by
3.1 5.00
PM
Total Progress Achievement 100.00
Control Account: Project Management Initiation
Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base

Project Risk Work Step Description WF for


124 Man-Hour Work Step
AB Analysis stages
Step 1 PRA session conducting 60.00%
Step 2 PRA Report Issuance 40.00%
125 Man-Hour Work Step
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 298 of 456

Work Step Description WF for


Project Charter stages
Development Step 1 Prepared 90.00%
Step 2 Approved 10.00%

Control Account: Business Framing


Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base

Business Case Milestone Description WF for


126 Man-Hour Milestone stages
Development
1 Start 0.00%
2 Finish 100.00%
AC

Opportunity Milestone Description WF for


127 Man-Hour Milestone stages
Framing
1 Start 0.00%
2 Finish 100.00%

Control Account: General


Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base
Preliminary
Man-
BA 141 Concept Milestone Milestone Description WF for
Hour
Development stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 299 of 456

1 Start 5.00%
2 Finish 95.00%

Environment
Milestone Description WF for
Preliminary
142 Work Step stages
Assessment &
1 Perform Assessment 60.00%
Report
2 Issue Final Report 40.00%
Control Account: HSE
Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base

Initial Health & Milestone Description WF for


Man-
BB 143 Safety Milestone stages
Hour
Evaluation Step 1 Start 5.00%
Step 2 Finish 95.00%
Control Account: Facility Assessment
Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base

Data Milestone Description WF for


BC 144 Man-Hour Gathering/ Milestone stages
Surveying Step 1 Start 5.00%
Step 2 Finish 95.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 300 of 456

Work Step Description WF for


Site Location stages
145 Work Step Step 1 Perform Assessment 60.00%
Assessment
Step 2 Issue Final Report 40.00%
Existing Facility Work Step Description WF for
& stages
146 Work Step Step 1 Perform Assessment 60.00%
Infrastructure
Assessment Step 2 Issue Final Report 40.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 301 of 456

APPENDIX 16: Downstream PMS- FEL 2


Sub Phase: B1- Pre-Bidding
Weight
Sub
Factor Description of Sub- Calculation Description, Detailed Weight Factor or
Control Account Code. Phase Methodology
Calculation Phase Formula
Code.
Base
Progress of each pre-bidding item is calculated as per
following stages:

WF for
Stages Description
Stages

Tender Plan & ITB Preparation


- B1 Man-Hour Pre-Bidding Work Step Stage 1 -If the Tender Plan is issued 35%
equal to 100% otherwise 0%

Stage 2 Tender Plan Approval 15%

ITB
Stage 3 - If the ITB is issued equal to 50%
100% otherwise 0%
Sub Phase: B2-Bidding
Weight
Sub
Factor Description of Sub- Calculation Description, Detailed Weight Factor or
Control Account Code. Phase Methodology
Calculation Phase Formula
Code.
Base
Bidding/ Evaluate/ Progress of each bidding item is calculated as per
- B2 Man-Hour Work Step
Award following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 302 of 456

WF for
Stages Description
Stages

RFQ
Stage 1 - If the Inquiry is issued equal 10%
to 100% otherwise 0%
TBE
Stage 2 - If the TBE is performed equal 25%
to 100% otherwise 0%

CBE-, If the CBE is performed


Stage 3 25%
equal to 100% otherwise 0%

PETRONAS Approval of Award


- If the vendor/contractor is
Stage 4 40%
selected and PO place equal
to 100% otherwise 0%
Sub Phase: Detailed Feasibility Studies
Control Account: PMT Deliverables
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base

Work Step Description WF for


Project Risk stages
CA 241 Man-Hour Work Step Step 1 PRA session conducting 60.00%
Analysis
Step 2 PRA Report Issuance 40.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 303 of 456

Work Step Description WF for


stages
Quantitative Risk Step 1 SRA session conducting 30.00%
242 Man-Hour Work Step
Analysis
Step 2 SRA Report Issuance 20.00%
Step 3 CRA session conducting 30.00%
Step 4 CRA Report Issuance 20.00%
Deliverable Description WF for
stages
I. PCPP Compliance

1.1 Planning & Scheduling 67


Project Scope of Work and
2.53
1.1.1 Objectives
Schedule Basis Memorandum
3.79
1.1.2 (SBM)
Work Breakdown Structure
3.79
Preparation of 1.1.3 (WBS)
243 Man-Hour Deliverable
PCPP Organization Breakdown
3.79
1.1.4 Structure (OBS)
Project Management Team
6.32
1.1.5 (PMT) Manpower Plan
Project Execution Schedule
16.43
1.1.6 (Baseline Schedule)
Quantitative Risk Analysis
12.64
1.1.7 (QRA)
1.1.8 Critical Path 2.53
1.1.9 Progress Base 3.79
1.1.10 Progress S-Curve 2.53
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 304 of 456

Progress Measurement 2.53


1.1.11 Format
1.1.12 Resource Plan 2.53
1.1.13 Project Roadmap 1.26
1.1.14 Project Progress Report 1.26
1.1.15 Project Close-Out Report 1.26
1.2 Cost Control 23
1.2.1 Cost Breakdown Structure
0.88
(CBS)
1.2.2 Project Total Budget 2.65
1.2.3 Work Program & Budget
7.08
(WPB)
1.2.4 Corporate Plan & Budget
7.08
(CPB)
1.2.5 Approved For Expenditure 0.88
Additional Budget (Budget
1.2.6 Transfer and Supplementary 0.88
Budget)
1.2.7 Additional Budget Request 0.88
1.2.8 Change Order Register 0.88
1.2.9 Monthly Cost Report 0.88
1.2.10 Project Close-Out Report 0.88
II TP & PMO Endorsement 5
PCPP Reviewed and Endorsed
2.1 5.00
by TP and PMO (DPP)
III PM Approval 5
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 305 of 456

PCPP Reviewed and Approved


3.1 5.00
by PM

Total Progress Achievement 100.00


Work Step Description WF for
Preliminary Overall stages
244 Man-Hour Contracting Work Step Step 1 Completed 90.00%
Strategy
Step 2 Accepted 10.00%
Control Account: Facilities Conceptual Design & Selection
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base
Work Step Description WF for
stages
246 Man-Hour General Work Step Step 1 Start 10%
Step 2 Issued for Information 80%
Step 3 Final Update 10%
Work Step Description WF for
stages
CB Stage 1 Start 10%
247 Man-Hour Process Work Step Stage 2 Inter Discipline Check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approve for Feed 20%
248 Work Step Description WF for
Man-Hour Mechanical Work Step stages
Stage 1 Start 10%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 306 of 456

Stage 2 Inter Discipline Check 30%


Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approve for Feed 20%
Work Step Description WF for
stages
Stage 1 Start 10%
249 Man-Hour Instrumentation Work Step Stage 2 Inter Discipline Check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approve for Feed 20%
Work Step Description WF for
stages
Stage 1 Start 10%
250 Man-Hour Electrical Work Step Stage 2 Inter Discipline Check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approve for Feed 20%
Work Step Description WF for
stages
Stage 1 Start 10%
Material & Stage 2 Inter Discipline Check 30%
251 Man-Hour Work Step
Corrosion
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approve for Feed 20%
Work Step Description WF for
252 Man-Hour HSE Work Step stages
Stage 1 Start 10%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 307 of 456

Stage 2 Issued for Review 50%


Stage 3 Issue for Approve 30%
Stage 4 Approve for Feed 10%
Work Step Description WF for
stages
Stage 1 Start 10%
253 Man-Hour Pipeline Work Step Stage 2 Inter Discipline Check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approve for Feed 20%
Control Account: Pre FEED Activities
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base
Work Step Description WF for
stages
Environmental Step 1 Pre Bidding Cost
256 Cost Work Step
Impact Assessment
Step 2 Contract Award Cost
Step 3 Final Report Cost
Work Step Description WF for
CC stages
Step 1 Pre Bidding Cost
257 Cost Soil Boring Work Step Step 2 Contract Award Cost
Step 3 Execution Cost
Step 4 Final Report Cost
Work Step Description WF for
258 Cost Site Survey Work Step
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 308 of 456

Step 1 Pre Bidding Cost


Step 2 Contract Award Cost
Step 3 Execution Cost
Step 4 Final Report Cost
Work Step Description WF for
stages
Pipeline Route Step 1 Pre Bidding Cost
259 Cost Work Step Step 2
Survey Contract Award Cost
Step 3 Execution Cost
Step 4 Final Report Cost
Work Step Description WF for
stages
Step 1 Preparation for Land
Cost
Acquisition
260 Cost Land Acquisition Work Step Step 2 Application for Land
Cost
Acquisition
Inspection, Gazette and
Step 3 Cost
publication
Step 4 Compensation Payment Cost
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 309 of 456

APPENDIX 17: Downstream PMS- FEL3


Sub Phase: C1- Pre-Bidding
Weight
Sub Description
Factor
Control Account Code. Phase of Sub- Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation
Code. Phase
Base
Progress of each pre-bidding item is calculated as per
following stages:

WF for
Stages Description
Stages

Tender Plan & ITB Preparation


- C1 Man-Hour Pre-Bidding Work Step Stage 1 -If the Tender Plan is issued 35%
equal to 100% otherwise 0%

Stage 2 Tender Plan Approval 15%

ITB
Stage 3 - If the ITB is issued equal to 50%
100% otherwise 0%
Sub Phase: C2-Bidding
Weight
Sub Description
Factor
Control Account Code. Phase of Sub- Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation
Code. Phase
Base
Progress of each bidding item is calculated as per following
- C2 Man-Hour Work Step
stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 310 of 456

WF for
Stages Description
Stages

RFQ
Stage 1 - If the Inquiry is issued equal to 10%
100% otherwise 0%
Bidding/ TBE
Evaluate/ Stage 2 - If the TBE is performed equal to 25%
Award 100% otherwise 0%
CBE
Stage 3 -, If the CBE is performed equal to 25%
100% otherwise 0%
PETRONAS Approval of Award
- If the vendor/contractor is
Stage 4 40%
selected and PO place equal to
100% otherwise 0%
Control Account: General, Process, Structural, Mechanical, Piping, Electrical, Instrument and Telecommunication, Civil, Pipelines, Architecture, HSE (Fire
and Safety), HVAC, Others
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base

DA,DB,DC,DD,DE,DF,DG,DH,DK,
311 Man-Hour CTR Deliverables Work Step Refer Appendix 5
DI,DK,DL, DM
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 311 of 456

Control Account: Schedule and Cost Quantitative Risk Analysis


Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base

Work Description WF for


Step stages
Step 1 SRA session conducting 30.00%
EA NA Man-Hour NA Work Step Step 2 SRA Report Issuance 20.00%

Step 3 CRA session conducting 30.00%

Step 4 CRA Report Issuance 20.00%

Control Account: Economics


Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base

Work Description WF for


Step stages
Step 1 Run Economic Analysis 60.00%
EB NA Man-Hour NA Work Step

Step 2 Economic Report 40.00%


PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 312 of 456

Control Account: Approval (FEL3)


Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base
Work Description WF for
Step stages
EC NA Man-Hour NA Milestone Step 1 Start 5.00%
Step 2 Finish 95.00%

Control Account: OCS


Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base
Work Description WF for
Step stages
ED NA Man-Hour NA Work Step Step 1 OCS Submission 60.00%
Step 2 OCS Approval 40.00%
Control Account: Project Sanction
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base
Work Description WF for
Step stages
EE NA Man-Hour NA Work Step Step 1 Advance Funding Submission 60.00%
Step 2 Sanction Approval 40.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 313 of 456

Control Account: PCPP Preparation


Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base

Deliver Description WF for


able stages
I. PCPP Compliance
1.1 Planning & Scheduling 67
Project Scope of Work and
2.53
1.1.1 Objectives
Schedule Basis Memorandum
3.79
1.1.2 (SBM)
1.1.3 Work Breakdown Structure (WBS) 3.79
Organization Breakdown Structure
3.79
EF NA Man-Hour NA Work Step 1.1.4 (OBS)
Project Management Team (PMT)
6.32
1.1.5 Manpower Plan
Project Execution Schedule
16.43
1.1.6 (Baseline Schedule)
1.1.7 Quantitative Risk Analysis (QRA) 12.64
1.1.8 Critical Path 2.53
1.1.9 Progress Base 3.79
1.1.10 Progress S-Curve 2.53
1.1.11 Progress Measurement Format 2.53
1.1.12 Resource Plan 2.53
1.1.13 Project Roadmap 1.26
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 314 of 456

1.1.14 Project Progress Report 1.26


1.1.15 Project Close-Out Report 1.26
1.2 Cost Control 23
1.2.1 Cost Breakdown Structure (CBS) 0.88
1.2.2 Project Total Budget 2.65
1.2.3 Work Program & Budget (WPB) 7.08
1.2.4 Corporate Plan & Budget (CPB) 7.08
1.2.5 Approved For Expenditure 0.88

1.2.6 Additional Budget (Budget Transfer 0.88


and Supplementary Budget)
1.2.7 Additional Budget Request 0.88
1.2.8 Change Order Register 0.88
1.2.9 Monthly Cost Report 0.88
1.2.10 Project Close-Out Report 0.88
II TP & PMO Endorsement 5
PCPP Reviewed and Endorsed by TP
2.1 5.00
and PMO (DPP)
III PM Approval 5
PCPP Reviewed and Approved by
3.1 5.00
PM

Total Progress Achievement 100.00


PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 315 of 456

FEED
Control Account DA: General
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of general procedures calculated as per following stages:
WF for
Stages Description
All Type of Stages
Man-Hour Work Step
documents Stage 1 Start 10%
Stage 2 Issued for Information 80%
Stage 3 Final Update 10%
Control Account DB: Process
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each PFD and P&ID is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
Man-Hour P&ID, PFD, HMB Work Step Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for HAZOP 10%
Stage 5 Issue for Approval 10%
Stage 6 Approved for Detailed Design 20%
Man-Hour Progress of each document is calculated as per following stages:
Other Process WF for
Work Step Stages Description
Documents Stages
Stage 1 Start 10%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 316 of 456

Stage 2 Issue for Internal Discipline check 30%


Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%
Control Account DC: Structural
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
All Type of Stage 1 Start 10%
Man-Hour Work Step
documents Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%
Control Account DD: Mechanical
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
All Type of Stage 1 Start 10%
Man-Hour Work Step
documents Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 317 of 456

Control Account DE: Piping


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
All Type of Stage 1 Start 10%
Man-Hour Work Step
documents Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%
Control Account DF: Electrical
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%

Stage 5 Approved for Detailed Design 20%


PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 318 of 456

Control Account DG: Instrument and Telecommunication

Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
All Type of Stage 1 Start 10%
Man-Hour Work Step
documents Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%
Control Account DH: Civil
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 319 of 456

Control Account DI: Pipelines


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
All Type of Stage 1 Start 10%
Man-Hour Work Step
documents Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%
Control Account DJ: Architecture
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%

Stage 4 Issue for Approval 20%

Stage 5 Approved for Detailed Design 20%


PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 320 of 456

Control Account DK: HSE


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step
documents Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%

Control Account DL: HVAC


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 321 of 456

Control Account DM: Final Documentation


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
All Type of
Man-Hour Work Step Stage 1 Start 10%
documents
Stage 2 Issue for Information 80%
Stage 3 Final Update 10%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 322 of 456

APPENDIX 18: Downstream PMS- DETAIL ENGINEERING

Control Account GA: General


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of general procedures calculated as per following stages:
WF for
Stages Description
All Type of Stages
Man-Hour Work Step
documents Stage 1 Start 10%
Stage 2 Issued for Information 80%
Stage 3 Final Update 10%
Control Account GB: Process
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each PFD and P&ID is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
Man-Hour P&ID, PFD, HMB Work Step Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for HAZOP 10%
Stage 5 Issue for Approval 10%
Stage 6 Approved for Construction 20%
Man-Hour Progress of each document is calculated as per following stages:
Other Process WF for
Work Step Stages Description
Documents Stages
Stage 1 Start 10%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 323 of 456

Stage 2 Issue for Internal Discipline check 30%


Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Construction 20%
Control Account GC: Structural
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
All Type of Stage 1 Start 10%
Man-Hour Work Step
documents Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Construction 20%
Control Account GD: Mechanical
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
All Type of Stage 1 Start 10%
Man-Hour Work Step
documents Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Construction 20%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 324 of 456

Control Account GE: Piping


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Construction 20%
Control Account GF: Electrical
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%

Stage 5 Approved for Construction 20%


PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 325 of 456

Control Account GG: Instrument and Telecommunication


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%

Stage 4 Issue for Approval 20%


Stage 5 Approved for Construction 20%

Control Account GH: Civil


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Construction 20%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 326 of 456

Control Account GI: Pipelines


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%

Stage 5 Approved for Construction 20%

Control Account GJ: Architecture


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%

Stage 4 Issue for Approval 20%


Stage 5 Approved for Construction 20%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 327 of 456

Control Account GK: HSE


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Construction 20%

Control Account GL: HVAC


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step
documents Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Construction 20%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 328 of 456

Control Account GM: Final Documentation


Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
All Type of Stages
Man-Hour Work Step
documents Stage 1 Start 10%
Stage 2 Issue for Information 80%
Stage 3 Final Update 10%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 329 of 456

APPENDIX 19: Downstream PMS- PROCUREMENT SUPPLY BY COMPANY


Procurement is divided to two parts which includes major packages and other equipment. Work step and weight factor of Manufacturing and delivery work
package for both parts will be different.

Work Packages: Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Major Packages (Compressor, GTG, Pumps, De-Hydration, etc.)

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress of each pre-bidding item is calculated as per following stages:

WF for
Stages Description
Stages
Tender Plan
Stage 1 -as per each equipment, if the Tender Plan is issued 30%
411 10% Work Step equal to 100% otherwise 0%
Pre-Bidding
PIR
Stage 2 -as per each equipment, if the PIR is performed equal to 40%
100% otherwise 0%
ITB
Stage 3 -as per each equipment, if the ITB is issued equal to 30%
100% otherwise 0%

Progress of each Bidding item is calculated as per following stages:


Bid/ Evaluate/ Award of
412 20% Work Step
Contract WF for
Stages Description
Stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 330 of 456

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
RFQ
Stage 1 -as per each equipment, if the Inquiry is issued out to 10%
vendor/Manufacturer equal to 100% otherwise 0%

TBE
Stage 2 -as per each equipment, if the TBE is performed equal to 25%
100% otherwise 0%

CBE
Stage 3 -as per each equipment, if the CBE is performed equal 25%
to 100% otherwise 0%

Issue of Purchase Order


Stage 4 -as per each equipment, if the vendor is selected and 40%
PO place equal to 100% otherwise 0%

Progress of each procurement item is calculated as per following stages:

WF for
Stages Description
Stages
Manufacturing & Delivery of
413 70% Work Step Engineering
Major Equipment
Stage 1 -If step is done the value would be 100 and if it hasn’t 7%
been done yet, it would be 0.
Procurement
Stage 2 - If step is done the value would be 100 and if it hasn’t 40%
been done yet, it would be 0.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 331 of 456

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Fabrication
30%
Stage 3 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Final Testing (FAT)
5%
Stage 4 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
FOB
3%
Stage 5 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Port
10%
Stage 6 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Site
3%
Stage 7 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Close out Report
2%
Stage 8 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 332 of 456

Work Packages: Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Other Equipment (Valves, Wellhead, Casing, bulk material, etc.)

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress of each pre-bidding item is calculated as per following stages:

WF for
Stages Description
Stages
Tender Plan
Stage 1 -as per each equipment, if the Tender Plan is issued out 30%
411 10% Work Step to vendor/manufacturer equal to 100% otherwise 0%
Pre-Bidding
PIR
Stage 2 -as per each equipment, if the PIR is performed equal to 40%
100% otherwise 0%
ITB
Stage 3 -as per each equipment, if the ITB is issued equal to 30%
100% otherwise 0%

Progress of each Bidding item is calculated as per following stages:

WF for
Stages Description
Bid/ Evaluate/ Award of Stages
412 20% Work Step
Contract
RFQ
Stage 1 -as per each equipment, if the Inquiry is issued equal to 10%
100% otherwise 0%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 333 of 456

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
TBE
Stage 2 -as per each equipment, if the TBE is performed equal to 25%
100% otherwise 0%
CBE
Stage 3 -as per each equipment, if the CBE is performed equal 25%
to 100% otherwise 0%
Issue of Purchase Order
Stage 4 -as per each equipment, if the vendor is selected and 40%
PO place equal to 100% otherwise 0%
Progress of each manufacturing item is calculated as per following stages:

WF for
Stages Description
Stages
FOB
Manufacturing & Delivery of Stage 1 - If step is done the value would be 100 and if it hasn’t 85%
413 70% Work Step been done yet, it would be 0.
Bulk Material
Delivered at Port
Stage 2 - If step is done the value would be 100 and if it hasn’t 10%
been done yet, it would be 0.
Delivered at Site
5%
Stage 3 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 334 of 456

APPENDIX 20: Downstream PMS- PROCUREMENT


Procurement is divided to two parts which includes major packages and bulk material. Work step and weight factor of Manufacturing and delivery work
package for both parts will be different.

Work Packages: Bid/Evaluate/Award, Manufacturing & Delivery


Major Packages (Compressor, GTG, Pumps, De-Hydration, etc.)

Work Packages : Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress of each Bidding item is calculated as per following stages:

WF for
Stages Description
Stages

RFQ
Stage 1 -as per each equipment, if the Inquiry is issued equal to 10%
100% otherwise 0%

Bid/ Evaluate/ Award of TBE


612 20% Work Step
Contract Stage 2 -as per each equipment, if the TBE is performed equal to 25%
100% otherwise 0%

CBE
Stage 3 -as per each equipment, if the CBE is performed equal 25%
to 100% otherwise 0%

Issue of Purchase Order


Stage 4 -as per each equipment, if the vendor is selected and 40%
PO place equal to 100% otherwise 0%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 335 of 456

Work Packages : Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress of each procurement item is calculated as per following stages:

WF for
Stages Description
Stages
Engineering
Stage 1 -If step is done the value would be 100 and if it hasn’t 7%
been done yet, it would be 0.
Procurement
Stage 2 - If step is done the value would be 100 and if it hasn’t 40%
been done yet, it would be 0.
Fabrication
30%
Manufacturing and Delivery of Stage 3 - If step is done the value would be 100 and if it hasn’t
613 80% Work Step been done yet, it would be 0.
Major Equipment
Final Testing (FAT)
5%
Stage 4 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
FOB
3%
Stage 5 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Site
13%
Stage 7 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Close out Report
2%
Stage 8 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 336 of 456

Work Packages: Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Bulk Material (Valves, Wellhead, Casing, etc.)

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.

Progress of each Bidding item is calculated as per following stages:

WF for
Stages Description
Stages
RFQ
-as per each equipment, if the Inquiry is issued equal to
Stage 1 10%
100% otherwise 0%

TBE
Bid/ Evaluate/ Award of -as per each equipment, if the TBE is performed equal to
612 20% Work Step Stage 2 25%
Contract 100% otherwise 0%

CBE
-as per each equipment, if the CBE is performed equal
Stage 3 25%
to 100% otherwise 0%

Issue of Purchase Order


-as per each equipment, if the vendor is selected and
Stage 4 40%
PO place equal to 100% otherwise 0%

Manufacturing & Delivery of


613 80% Work Step Progress of each manufacturing item is calculated as per following stages:
Bulk Material
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 337 of 456

Work Packages : Pre Bidding, Bid/Evaluate/Award, Manufacturing & Delivery


Work Package
WF Description of Work Package Methodology Calculation Description, Detailed Weight Factor or Formula
No.

WF for
Stages Description
Stages
FOB
85.0%
Stage 1 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Port
10.0%
Stage 2 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Site
5.0%
Stage 3 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 338 of 456

APPENDIX 21: Downstream PMS- CONSTRUCTION


Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress of General Management is based upon and
corresponded with Front End Activities (Work Package 811). Total
WP - 811 General Management Milestone progress (100%) of General Management will be achieved once
physical progress of 100% to be achieved.

Progress of Dredging/ Reclamation is based upon and


corresponded with Front End Activities (Work Package 812). Total
WP - 812 Dredging / Reclamation Milestone
progress (100%) of Dredging /Reclamation will be achieved once
physical progress of 100% to be achieved.
Foundation works Progress is calculated based on the quantity of work done and
measured as per following stages:

Stage Description WF for


stages
Work Step Stage 1 Surface preparation 10.00%
Steel Net Fencing Foundation
Stage 2 Reinforcement/formworks 40.00%
Stage 3 Pouring 30.00%

WP - 813 Stage 4 Grouting 10.00%


Stage 5 Formworks stripping & finishing 10.00%
Progress is calculated based on quantity of work done and
Foundation works - Concrete Drilled Piles
measured as per following stages:
Stage Description WF for
Work Step stages
Concrete Bored Piles Stage 1 Drilling/excavation 5.00%
Stage 2 Casing Installation 5.00%
Stage 3 Transport of Excavated material 15.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 339 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Reinforcement Installation 15.00%
Stage 5 Pouring 45.00%
Stage 6 Casing Recovery 10.00%
Stage 7 Integrity Test 5.00%
Infrastructures (Road, Railway, Drainage, etc.) Progress is subjected to Asphalt laying methods & Yards and
& Landscapes measured as per following stages:
Stage Description WF for
stages
Stage 1 Sub-base preparation 10.00%
Work Step Stage 2 Base rolling 5.00%
Asphalt roads and yards Stage 3 Quarry mix foundation 30.00%
Stage 4 Compacting and Stabilizing 25.00%
Stage 5 Binder 15.00%
Stage 6 Wear surface 10.00%
WP - 814
Stage 7 Misc. finishing 5.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Earth roads and yards Work Step Stage 1 Ground preparation 10.00%
Stage 2 Foundation 40.00%
Stage 3 Crushed stones 30.00%
Stage 4 Rolling 10.00%
Stage 5 Finishing works 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 340 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Trenching and measured as per
following stages:
Stage Description WF for
stages
Earth and Sand Trenches (Trenching) Work Step
Stage 1 Excavation 50.00%
Stage 2 Sand bed 10.00%
Stage 3 Sand filling 10.00%
Stage 4 Top Brick / Red lean concrete 20.00%
Stage 5 Sand filling 10.00%

Stage Description WF for


stages
Concrete Road Work Step Stage 1 Excavation 30.00%
Stage 2 Lean Concrete 5.00%
Stage 3 Reinforcement 20.00%
Stage 4 Form Work 20.00%
Stage 5 Main Concrete 25.00%
Progress is calculated based on Site Facilities and measured as
Site Facilities
per following stages:
Stage Description WF for
WP - 815 Work Step stages
Site Facilities Stage 1 Areas preparation 10.00%
Stage 2 Roads 60.00%
Stage 3 Fence 30.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 341 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Work Shop and measured as per
following stages:
Stage Description WF for
Work Shop Work Step stages
Stage 1 Workshops - Building 40.00%
Stage 2 Workshops - Equipment & Facilities 60.00%
Progress is calculated based on Warehouse and measured as per
following stages:

Warehouse Work Step Stage Description WF for


stages
Stage 1 Warehouses - Building 40.00%
Stage 2 Warehouses - Equipment & Facilities 60.00%
Progress is calculated based on Offices measured as per following
stages:
Stage Description WF for
Offices Work Step stages
Stage 1 Offices - Building 40.00%
Stage 2 Offices - Equipment 60.00%
Progress is calculated based on Utilities & Facilities and measured
as per following stages:
Stage Description WF for
stages
Utilities & Facilities Work Step Stage 1 Water and Effluent Treatment 10.00%
Stage 2 Fuel Station 10.00%
Stage 3 Parking, Roads & Fences 25.00%
Stage 4 Power Distribution Network 25.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 342 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Telecommunication Network 15.00%
Stage 6 Water Distribution Network 5.00%
Stage 7 Sewage Network 10.00%
Progress is calculated based on Facilities Demolition & Removal
and measured as per following stages:
Stage Description WF for
Facilities Demolition & Removal Work Step stages
Stage 1 Demolition & Removal 75.00%
Stage 2 Demobilization 25.00%

Progress is calculated based on Mobilization & Demobilization


Mobilization
and measured as per following stages:
Stage Description WF for
Work Step stages
Mobilization & Demobilization Stage 1 Mobilization Manual and Demobilization of 75.00%
Construction Equipment
Stage 2 Onshore / Offshore Logistic support 25.00%
Progress is calculated based on Mobilization Manual and
WP - 817 Inspection Construction Equipment and measured as per
following stages:
Stage Description WF for
Sub Work of Mobilization Manual and stages
Work Step
Demobilization of Construction Equipment Stage 1 Mobilization and Demobilization for 2.82%
Construction Equipment for on-shore Works
Stage 2 Mobilization and Demobilization for 51.17%
Construction Equipment for offshore Works
Stage 3 Mobilization and Demobilization for 7.51%
Construction Equipment for tie-in Works
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 343 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Pre-commissioning, Commissioning & Hydro 29.79%
testing
Stage 5 Mobilization and Demobilization for 5.89%
Construction Equipment for Line laying
Works
Stage 6 Mobilization and Demobilization for 2.82%
Construction Equipment for other Works
Progress is calculated based on Onshore Logistic support for
pipeline and measured as per following stages:
Stage Description WF for
Sub Work of Onshore Logistic support (Pipeline) Work Step
stages
Stage 1 Logistic Support for Shore Approach 43.10%
Stage 2 Logistic Support for Laying Operations 56.90%
Progress is calculated based on Onshore / Offshore Logistic
support and measured as per following stages:
Sub Work of Mobilization Manual and
Work Step
Stage Description WF for
Demobilization Inspection Construction Equipment stages
Stage 1 Completion of mobilization of Equipment 50.00%
Stage 2 Demobilization of construction EQUIPMENT 50.00%
Progress is calculated based on Utilities & Facilities and measured
as per following stages:
Stage Description WF for
stages
Utilities & Facilities Work Step
Stage 1 Water and Effluent Treatment 10.00%
Stage 2 Fuel Station 10.00%
Stage 3 Parking, Roads & Fences 25.00%
Stage 4 Power Distribution Network 25.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 344 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Telecommunication Network 15.00%
Stage 6 Water Distribution Network 5.00%
Stage 7 Sewage Network 10.00%
Progress is calculated based on Steel net fencing and measured
Site Preparation
as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Work Step Stage 3 10.00%
Formwork
Steel Net Fencing
Stage 4 Reinforcement 10.00%
Stage 5 Pouring 10.00%
Stage 6 Stripping/backfill 5.00%
Stage 7 Fencing installation 50.00%
WP - 818 Stage 8 5.00%
Misc. finishing work
Progress is calculated based on Pre-Fabricated Elements fencing
and measured as per following stages:
Stage Description WF for
Pre-Fabricated Elements fencing Work Step
stages
Stage 1 Complete - in Meter 90.00%
Stage 2 Acceptance - in Meter 10.00%
Progress is calculated based on Gates and measured as per
following stages:
Gates Work Step Stage Description WF for
stages
Stage 1 Complete - No. of Gates 90.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 345 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Acceptance - No. of Gates 10.00%
Progress is calculated based on Removal of Trees and measured
Earth Works
as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Ground preparation 5.00%
Removal of Trees
Stage 2 Trees cutting 40.00%
Stage 3 Roots removal 35.00%
Stage 4 Transportation 20.00%

Progress is calculated based on General Excavation and


measured as per following stages:
Stage Description WF for
General Excavation Work Step stages
Stage 1 Excavation including temporary shoring/slope 60.00%
protection
Stage 2 Excavated Material transport to 35.00%
designated dumping area
Stage 3 Final grading 5.00%
Progress is calculated based on General Embankment and
measured as per following stages:
Stage Description WF for
General Embankment Work Step stages
Stage 1 Ground Preparation 10.00%
Stage 2 Laying Materials/Compaction 70.00%
Stage 3 Final Rolling 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 346 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Sheet piling and dewatering and
measured as per following stages:
Stage Description WF for
stages
Sheet piling and dewatering Work Step
Stage 1 Sheet piles driving 50.00%
Stage 2 Reinforcing beams 20.00%
Stage 3 Dewatering 20.00%
Stage 4 Sheet piles extraction 10.00%
Progress is calculated based on Soil scrubbing and measured as
per following stages:
Stage Description WF for
Soil scrubbing Work Step
stages
Stage 1 Scrubbing 80.00%
Stage 2 Final Grading 20.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 10.00%
Earth Dykes Work Step
Stage 2 Dyke execution
65.00%

Stage 3 Slope profiling


15.00%

Stage 4 10.00%
Finishing work

Progress is calculated based on Tanks Pad and measured as per


Tanks Pad Work Step
following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 347 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Excavation 20.00%
Stage 2 Base rolling 5.00%
Stage 3 Pad formation 55.00%
Stage 4 Surface layer 10.00%
Stage 5 Bitumen layer 3.00%
Stage 6 Pad slope profiling 7.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean Concrete 5.00%
Stage 3 Rebar 25.00%
Tanks Foundation Work Step
Stage 4 Form Work 12.00%
Stage 5 Casting Concrete for Foundation 20.00%
Stage 6 Form Work Pedestal 8.00%
Stage 7 Steel Plate 5.00%
Stage 8 Casting Concrete for Pedestal 15.00%
Stage 9 Final/Backfill
5.00%

Progress is calculated based on Gravel Finishing and measured as


Roads, Yards, Paving (Asphalt, not concrete)
per following stages:
Work Step
Stage Description WF for
Gravel Finishing
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 348 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Excavation 10.00%
Stage 2 Base rolling 20.00%
Stage 3 Gravel or crushed stone laying 70.00%
Progress is calculated based on Acid and measured as per
following stages:
Stage Description WF for
stages
Acid Resistant Lining Work Step Stage 1 Surface cleaning 10.00%
Stage 2 Acid resistant layers or tiles 70.00%
Stage 3 Joint & sealing 15.00%
Stage 4 Finishing 5.00%
Progress is calculated based on Acid Resistant Lining and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Sub-base preparation 10.00%
Stage 2 Base rolling 5.00%
Asphalts roads and yards Work Step
Stage 3 Quarry mix foundation 30.00%
Stage 4 Compacting & Stabilizing 25.00%
Stage 5 Binder 15.00%
Stage 6 Wear surface 10.00%
Stage 7 Misc. finishing 5.00%
Progress is calculated based on Earth roads & Yards and
measured as per following stages:
Earth roads and yards Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 349 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Ground preparation 10.00%
Stage 2 Foundation 40.00%
Stage 3 Crushed stones 30.00%
Stage 4 Rolling 10.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Concrete paving and measured as
per following stages:
Stage Description WF for
Concrete Paving Work Step stages
Stage 1 Prep., slope setting, reinforcement 60.00%
Stage 2 Wire netting installation, pouring 25.00%
Stage 3 Finishing works 15.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Concrete Cable Trenches Work Step Stage 3 Reinforcement 20.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping 5.00%
Stage 7 Sand bed 20.00%
Stage 8 Concrete covers 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 350 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Pulling Pits Work Step Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 25.00%
Stage 4 Formworks 15.00%
Stage 5 Pouring 35.00%
Stage 6 Formworks stripping & backfill 15.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on issued General Engineering
documents to the COMPANY and measured as per following
stages:
Stage Description WF for
stages
WP - 819 General Work Step
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%

Stage 3 Approval for Construction 40.00%

Progress is calculated based on issued process documents to the


COMPANY and measured as per following stages:
WP - 820 Process Work Step Stage Description WF for
stages
Stage 1 Start 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 351 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Equipment documents to
the COMPANY and measured as per following stages:
Stage Description WF for
stages
WP - 821 Equipment Work Step Stage 1 Start 5.00%

Stage 2 Issued for Review 55.00%

Stage 3 Approval for Construction 40.00%

Progress is calculated based on issued Civil & structural


documents to the COMPANY and measured as per following
stages:
Stage Description WF for
stages
WP - 822 Civil & Structural Work Step
Stage 1 Start 5.00%

Stage 2 Issued for Review 55.00%


Stage 3 Approval for Construction 40.00%

Progress is calculated based on issued piping documents to the


COMPANY and measured as per following stages:
Stage Description WF for
WP - 823 Piping Work Step
stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 352 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Electrical documents to
the COMPANY and measured as per following stages:
Stage Description WF for
WP - 824 Electrical Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Instrument &
Communication documents to the COMPANY and measured as
per following stages:
Stage Description WF for
WP - 825 Instrument & Communication Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Other Engineering
documents to the COMPANY and measured as per following
stages:
Stage Description WF for
WP - 826 Other Engineering Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on Cast in situ driven piles and
WP - 813 Piling - Driven in place piles hammered Work Step
measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 353 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Casing Installation 10.00%
Cast in Situ driven piles Stage 2 Reinforcing Installation 30.00%
Stage 3 Pouring 45.00%
Stage 4 Casing Recovery 10.00%
Stage 5 Integrity test 5.00%
Progress is calculated based on Concrete Pre-cuts driven piles
and measured as per following stages:
Stage Description WF for
Concrete Pre-cuts driven piles Work Step stages
Stage 1 Material at Site 20.00%
Stage 2 Installation 75.00%
Stage 3 Integrity test 5.00%
Progress is calculated based on Steel driven Piles and measured
as per following stages:
Stage Description WF for
Steel driven piles Work Step stages
Step 1 Material at Site 20.00%
Step 2 Installation 75.00%
Step 3 Integrity test 5.00%
Progress is calculated based on Wooden driven Piles and
measured as per following stages:
Wooden driven piles Work Step Stage Description WF for
stages
Stage 1 Material at Site 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 354 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Installation 75.00%
Stage 3 Integrity test 5.00%
CIVIL WORKS
Progress is calculated based on Concrete Foundation for
Concrete Works - Foundations
Equipment & Structural and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Work Step Stage 3 Reinforcement 25.00%
Concrete Foundation for Equipment & Structural Stage 4 Formworks 20.00%
Stage 5 Anchor bolts/plates 10.00%
Stage 6 Concrete pouring 15.00%
Stage 7 Formworks stripping, concrete protection &
10.00%
WP - 827 backfill
Stage 8 Grouting 10.00%
Progress is calculated based on Prefabrication of concrete
foundations and measured as per following stages:
Stage Description WF for
stages
Prefabrication of concrete foundations Work Step Stage 1 Reinforcement 25.00%
Stage 2 Formworks 20.00%
Stage 3 Anchor bolts/plates 20.00%
Stage 4 Concrete pouring 35.00%
Progress is calculated based on Precast of concrete foundations
Precast on of concrete foundations installation Work Step
installation and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 355 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Stage 3 Foundation installation 55.00%
Stage 4 Concrete protection & backfill 10.00%
Stage 5 Grouting 10.00%
Stage 6 Finishing 15.00%
Progress is calculated based on Tanks Rings and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Excavation 10.00%
Stage 2 Lean concrete 5.00%
Tank Rings Work Step
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping, concrete protection &
15.00%
external backfill
Stage 7 Internal backfilling 10.00%
Progress is calculated based on Tanks Rings and measured as per
following stages:
Stage Description WF for
Concrete small foundations Work Step
stages
Stage 1 Surface preparation 10.00%
Stage 2 Reinforcement/formworks 40.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 356 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Pouring 30.00%
Stage 4 Grouting 10.00%
Stage 5 Formworks stripping & finishing 10.00%
Progress is calculated based on concrete large massive
foundations and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Concrete large massive foundations Work Step Stage 3 Reinforcement 20.00%
Stage 4 Formworks 15.00%
Stage 5 Anchor bolts/plates 10.00%
Stage 6 Pouring 25.00%
Stage 7 Grouting 10.00%
Stage 8 Formworks stripping & backfill 10.00%
Progress is calculated based on Concrete elevated structures cast
Elevation Concrete
in situ l and measured as per following stages:
Stage Description WF for
stages
Stage 1 Formworks 25.00%
Work Step Stage 2 Reinforcement 25.00%
Concrete elevated structures cast in situ
Stage 3 Anchor bolts/plates 15.00%
Stage 4 Pouring 20.00%
Stage 5 Formworks stripping 10.00%
Stage 6 Finishing works 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 357 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Concrete structures
prefabrication and measured as per following stages:
Stage Description WF for
stages
Concrete structures prefabrication Work Step
Stage 1 Reinforcement 25.00%
Stage 2 Formworks 20.00%
Stage 3 Anchor bolts/plates 20.00%
Stage 4 concrete pouring 35.00%
Progress is calculated based on Precast concrete structures
erection and measured as per following stages:
Stage Description WF for
stages
Stage 1 Columns installation 30.00%
Precast concrete structures erection Work Step Stage 2 Grouting on footings 10.00%
Stage 3 Lengthwise beams installation 20.00%
Stage 4 Transverse beams installation 20.00%
Step 5 Beams grouting 10.00%
Step 6 Finishing works 10.00%
Progress is calculated based on Concrete paving and measured as
Concrete Paving / Roads / Yards
per following stages:
Stage Description WF for
Work Step stages
Concrete Paving Stage 1 Prep., slope setting, reinforcement 60.00%
Stage 2 Wire netting installation, pouring 25.00%
Stage 3 Finishing works 15.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 358 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
U/G civil works ( pits, duct banks, cable Progress is calculated based on Concrete cable trenches and
trenches ) measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Work Step
Stage 3 Reinforcement 20.00%
Concrete cable trenches
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping 5.00%
Stage 7 Sand bed 20.00%
Stage 8 Concrete covers 5.00%
Progress is calculated based on Pulling Pits and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Puling Pits Work Step
Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 25.00%
Stage 5 Pouring 30.00%
Stage 6 Formworks stripping & backfill 15.00%
Progress is calculated based on Duct Banks and measured as per
following stages:
Duct Banks Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 359 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Excavation 20.00%
Stage 2 PVC conduit positioning 40.00%
Stage 3 Concrete pouring 40.00%

Progress is calculated based on Earth and Sand Trenches and


measured as per following stages:
Stage Description WF for
stages
Earth and Sand Trenches Work Step Stage 1 Excavation 50.00%
Stage 2 Sand bed 10.00%
Stage 3 Sand filling 10.00%
Stage 4 Top-bricks/red lean concrete 20.00%
Stage 5 Backfill 10.00%

Progress is calculated based on Lighting poles foundations (cast in


situ) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Lighting poles foundations (cast in situ) Work Step Stage 3 Reinforcement 20.00%
Stage 4 Formworks 15.00%
Stage 5 Anchor Bolt/J-bolt 15.00%
Stage 6 Pouring 20.00%
Stage 7 Formworks stripping 5.00%
Stage 8 Backfilling 5.00%
Stage 9 Grouting 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 360 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on cast in situ sleepers and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%

Stage 2 Lean concrete 5.00%

Cast in situ sleepers Work Step Stage 3 Formworks 10.00%

Stage 4 Reinforcing 30.00%


Stage 5 Steel insert installation 10.00%
Stage 6 Pouring 30.00%
Stage 7 Formwork stripping 5.00%

Stage 8
Backfill 5.00%

Progress is calculated based on Concrete Basin and measured as


Cooling towers and concrete basins
per following stages:
Stage Description WF for
stages
Stage 1 Excavation 10.00%

Work Step Stage 2 Lean concrete 5.00%

Concrete Basin
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Joints sealing 5.00%
Stage 7 Formworks stripping, concrete protection &
15.00%
backfill
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 361 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Finishing works 5.00%

Progress is calculated based on Concrete Retaining Wall and


measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation & lean concrete 10.00%
Stage 2 Foundation formworks 5.00%
Concrete Retaining Wall Work Step
Stage 3 Reinforcing 25.00%
Stage 4 Foundation Pouring 5.00%
Stage 5 Elevation formworks 25.00%
Stage 6 Elevation Pouring 15.00%
Stage 7 Formwork stripping 5.00%
Stage 8 Joints sealing 10.00%

Progress is calculated based on Sleepers prefabrication and


Sleepers
measured as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Reinforcement 25.00%
Sleepers prefabrication
Stage 2 Formworks 20.00%
Stage 3 Anchor bolts/plates 20.00%
Stage 4 Concrete pouring 35.00%
Progress is calculated based on Precast sleepers erection and
measured as per following stages:
Precast sleepers erection Work Step Stage Description WF for
stages
Stage 1 Excavation 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 362 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Lean concrete 10.00%
Stage 3 Sleepers installation 60.00%
Stage 4 Backfill 15.00%
Stage 5 Finishing works 10.00%

Progress is calculated based on Fire proofing for equipment


Fireproofing - Dense concrete fire proofing
legs/curbs and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Formworks 30.00%
Fire proofing for equipment legs/curbs Stage 2 Reinforcement 20.00%
Stage 3 Pouring 30.00%
Stage 4 Formworks stripping 5.00%
Stage 5 Finishing works 15.00%
Progress is calculated based on Fire proofing for equipment skirts
and measured as per following stages:
Stage Description WF for
Fire proofing for equipment skirts Work Step stages
Stage 1 Welded wire mesh installation 20.00%
Stage 2 Pouring 60.00%
Stage 3 Finishing works 20.00%
Progress is calculated based on Fire proofing for steel structures
and measured as per following stages:
Stage Description WF for
Fire proofing for steel structures Work Step
stages
Stage 1 Surface cleaning 5.00%
Stage 2 Supports installation 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 363 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Reinforcement 5.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring /application 30.00%
Stage 6 Formworks stripping 20.00%
Stage 7 Finishing works 10.00%
BUILDINGS Progress is calculated based on subs-station and measured as per
Concrete & Masonry Buildings following stages:
Stage Description WF for
stages
Work Step Stage 1 Concrete foundations 30.00%
Substation Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on control room and measured as
per following stages:
Stage Description WF for
stages
Control room Work Step Stage 1 Concrete foundations 30.00%
Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Other buildings and measured as
Other buildings per following stages:
Work Step
(administration, laboratory, canteen ...) Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 364 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Concrete foundations 30.00%
Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Curtain and partition walls and
Building Secondary Works measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Material at site 10.00%
Curtain and partition walls Stage 2 Hollow block 30.00%
Stage 3 Internal plastering 25.00%
Stage 4 Internal painting 25.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Doors & windows and measured
as per following stages:
Stage Description WF for
Doors & windows Work Step stages
Stage 1 Material at site 10.00%
Stage 2 Windows / doors installation 45.00%
Stage 3 Accessories installation 45.00%
Progress is calculated based on Flooring and measured as per
following stages:
Stage Description WF for
Flooring Work Step
stages
Stage 1 Material at site 20.00%
Stage 2 Installation 70.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 365 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Finishing & cleaning 10.00%

Progress is calculated based on Ceiling and measured as per


following stages:
Stage Description WF for
stages
Stage 1 Material at site 10.00%
Ceiling Work Step
Stage 2 Support/Hanger installation and Plastering
40.00%
or False Ceiling
Stage 3 Painting 30.00%

Stage 4 Cleaning 20.00%

Progress is calculated based on Ceramic & Quarry Tiling and


measured as per following stages:
Stage Description WF for
Ceramic & Quarry Tiling Work Step
stages
Stage 1 Tiling 90.00%
Stage 2 Jointing/Sealing 10.00%
Progress is calculated based on Plumbing and measured as per
following stages:
Stage Description WF for
Plumbing Work Step stages
Stage 1 Support/Hanger and Equipment installation 30.00%
Stage 2 Water networks 60.00%
Stage 3 Finishing works/tests 10.00%
Progress is calculated based on External Painting and measured
External Painting Work Step
as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 366 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Coating 90.00%
Stage 2 Touch-up 10.00%
Progress is calculated based on Roof Insulation & Water
Tightness and measured as per following stages:
Stage Description WF for
stages
Roof Insulation & Water Tightness Work Step Stage 1 Insulation 40.00%

Stage 2 Water Tightness 50.00%

Stage 3 Tests 10.00%


Progress is calculated based on HVAC system and partition walls
HVAC
and measured as per following stages:
Work Description WF for
Step stages
Stage 1 Support Fabrication and Installation 7.00%

Stage 2 Ducts Installation 20.00%

Work Step Stage 3


Equipment installation 20.00%
HVAC system
Stage 4 Piping installation 20.00%

Stage 5
Electrical installation 13.00%

Stage 6 Instrument installation 10.00%

Stage 7 Duct Insulation 7.00%


PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 367 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Functional checks 3.00%
Progress is calculated based on Power & Lighting and partition
Power / Lighting / Lightning
walls and measured as per following stages:
Stage Description WF for
stages
Stage 1 Material at site 10.00%
Work Step Stage 2 Cable pulling 30.00%
Power & Lighting
Stage 3 Lighting fixtures installation 20.00%
Stage 4 Outlets & switches installation 20.00%
Stage 5 Panel installation 15.00%
Stage 6 Functional checks 5.00%
Progress is calculated based on Lightning system and measured
as per following stages:
Stage Description WF for
Lightning system Work Step
stages
Stage 1 Equipment installation 90.00%
Stage 2 Checks 10.00%
Progress is calculated based on Communication / security
systems and measured as per following stages:
Stage Description WF for
stages
Communication / security systems Work Step Stage 1 Material at site 10.00%
Stage 2 Equipment installation 30.00%
Stage 3 Cable pulling & Connections 50.00%
Stage 4 Functional checks 10.00%
Progress is calculated based on Fire detection and partition walls
Fire detection / fighting Work Step
and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 368 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Material at site 10.00%
Fire detection
Stage 2 Equipment installation 30.00%
Stage 3 Cable pulling & Connections 50.00%
Stage 4 Functional checks 10.00%
Progress is calculated based on Fire detection and partition walls
and measured as per following stages:
Stage Description WF for
stages
Fire fighting system Work Step Stage 1 Material at site 5.00%
Stage 2 Piping prefabrication & install. 35.00%
Stage 3 Piping painting 20.00%
Stage 4 Sprinkler installation 20.00%
Stage 5 Functional test 20.00%
STORAGE TANKS AND SILOS Progress is calculated based on Fixed roof tanks (altern.I) and
Steel Tanks - Fixed Roof Tanks measured as per following stages:

Stage Description WF for


stages
Work Step
Stage 1 Base 17.00%
Fixed roof tanks
WP-828 Stage 2 Shell 48.00%
Stage 3 Fixed roof 28.00%
Stage 4 Accessories 3.00%
Stage 5 Testing 4.00%
Progress is calculated based on Fixed roof tanks (altern.II) and
Fixed roof tanks (altern.II) Work Step
measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 369 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Positioning and tack weld 15.00%
Stage 2 Full weld/fixing 70.00%
Stage 3 X-rays 11.00%
Stage 4 Testing 4.00%
Progress is calculated based on Fixed roof with floating plate
tanks (altern. I) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Base 17.00%
Fixed roof with floating plate tanks (altern.) I) Stage 2 Shell 35.00%
Work Step
Stage 3 Floating plate 25.00%

Stage 4 Fixed roof 16.00%


Stage 5 Accessories 3.00%

Stage 6 Testing 4.00%


Floating Roof tanks Progress is calculated based on Floating roof tanks and
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Base 18.00%
Floating roof tanks
Stage 2 Shell 49.00%
Stage 3 Floating roof 25.00%
Stage 4 Accessories 3.00%
Stage 5 Testing 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 370 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Sphere and measured as per
Sphere Tank
following stages:
Stage Description WF for
stages
Work Step Stage 1 Erection 30.00%
Sphere Stage 2 Meridian/vertical welds 30.00%
Stage 3 Equatorial/circumferential. welds 10.00%
Stage 4 NDT 20.00%
Stage 5 Cleaning, testing 10.00%
Progress is calculated based on Double Wall tanks and measured
Cryogenic Tank
as per following stages:
Stage Description WF for
stages
Stage 1 Base 17.00%
Work Step Stage 2 Inner shell (nickel) 28.00%
Double wall tanks
Stage 3 Outer shell (carbon steel) 20.00%
Stage 4 Roof 28.00%
Stage 5 Accessories 3.00%
Stage 6 Testing 4.00%
Progress is calculated based on other tanks and measured as per
following stages:
Stage Description WF for
stages
Other Tanks Work Step Stage 1 Bottom Plates 17.00%
Stage 2 Shell Plates 28.00%
Stage 3 Roof & Cover 20.00%
Stage 4 Accessories & Others 3.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 371 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Hydro test 3.00%
Stage 6 Painting 4.00%

Hoisting and Equipment (Mechanical) Progress is calculated based on Heavy vessels w fixed lifting and
Erection measured as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Erection on Foundation 60.00%
Heavy Vessels with fixed lifting and assembly
Stage 2 Levelling, plumb adjustment 5.00%
Stage 3 Pneumatic & Hydrostatic testing 25.00%
Stage 4 Final inspect., Manholes closure 10.00%
Progress is calculated based on Heavy vessels w fixed cranage
and measured as per following stages:
Stage Description WF for
Vessels parts lifting and assembly stages
WP 829 Stage 1 Shell assembly & welding 40.00%
Stage 2 Tracing & Welding of Nozzles and
10.00%
Manholes
Work Step
Stage 3 Tray support installation 5.00%
Stage 4 X-ray examination 5.00%
Stage 5 Installation 20.00%
Stage 6 Circum, welding & x-ray exam 5.00%
Stage 7 Plumb adjustment 5.00%
Stage 8 Final hydrostatic testing 10.00%
FIRE EQUIPMENT ERECTION Progress is calculated based on Heavy vessels w fixed cranage
Furnaces and measured as per following stages:
Work Step
Stage Description WF for
Preassembled Furnaces
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 372 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Erection on Foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt
30.00%
tightening
Stage 3 Final inspect., Manholes closure 20.00%
Progress is calculated based on Heavy vessels w fixed cranage
and measured as per following stages:
Stage Description WF for
stages
Stage 1 Shell assembly & welding/bolting 20.00%
Stage 2 Refractory panels/mater, erect 15.00%
Partially preassembled Furnaces Work Step
Stage 3 Coils welding & erection 20.00%
Stage 4 Installation on foundation 10.00%
Stage 5 Stack and Flue ducts weld/bolt 15.00%
Stage 6 Accessories & Structures erect. 10.00%
Stage 7 X-ray examination 8.00%
Stage 8 Final alignment & Final inspection 2.00%
Progress is calculated based on Preassembled boilers and
measured as per following stages:
Stage Description WF for
Preassembled boilers Work Step stages
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Partially preassembled boilers
and measured as per following stages:
Partially preassembled boilers Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 373 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Shell assembly & welding/bolting 20.00%
Stage 2 Refractory panels/mater erect. 15.00%
Stage 3 Coils welding & erection 20.00%
Stage 4 Installation on foundation 10.00%
Stage 5 Stack and flue ducts weld./bolt. 15.00%
Stage 6 Accessories & structures erect. 10.00%
Stage 7 X-ray examination 8.00%
Stage 8 Final alignment final inspection 2.00%
Progress is calculated based on Flares and measured as per
following stages:
Stage Description WF for
stages
Flares Work Step Stage 1 Structure Erection 50.00%
Stage 2 Riser Pipe 20.00%
Stage 3 Alignment 10.00%
Stage 4 Accessories 10.00%
Stage 5 Checks 10.00%

Progress is calculated based on Stack preassembled boilers and


measured as per following stages:
Stage Description WF for
stages
Stack Work Step
Stage 1 Stack Erection 60.00%
Stage 2 Alignment 20.00%
Stage 3 Accessories 10.00%
Stage 4 Checks 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 374 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Module erection and measured as
MODULES FABRICATION AND ERECTION
per following stages:
Stage Description WF for
Work Step stages
Module erection Stage 1 Erection on foundation 70.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Final inspect., manholes closure 10.00%
MACHINERY ERECTION Progress is calculated based on Belt conveyors and measured as
Machinery ( Not Require for Alignment) per following stages:
WP 829
Stage Description WF for
stages
Stage 1 Frames installation 30.00%
Work Step Stage 2 Rollers installation 15.00%
Belt conveyors Stage 3 Belt installation 15.00%
Stage 4 Belt joint execution 10.00%
Stage 5 Accessories 10.00%
Stage 6 Counterweight 10.00%
Stage 7 Final check 10.00%

Progress is calculated based on Air Fans and measured as per


Machinery (Require for Alignment)
following stages:
Stage Description WF for
stages
Work Step
Stage 1 Structure preassembly 5.00%
Air Fans
Stage 2 Pack & structure erection 25.00%
Stage 3 Erection of motors & pulleys 30.00%
Stage 4 Blade erection 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 375 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Blade connection & alignment 25.00%
Stage 6 Final inspection 5.00%
Progress is calculated based on Horizontal pumps and drive and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection on foundation 25.00%
Horizontal pumps and drive Work Step
Stage 2 Levelling, bolt tightening 10.00%
Stage 3 Prelim. alignment with motor 25.00%
Stage 4 Cold alignment with piping 30.00%
Stage 5 Final inspection 5.00%
Stage 6 Cleaning, maintenance 5.00%

Progress is calculated based on Vertical, in line, dosing pumps and


drive and drive and measured as per following stages:
Stage Description WF for
stages
Vertical, in line, dosing pumps and drive Work Step
Stage 1 Installation on foundation 25.00%
Stage 2 Levelling, bolt tightening 10.00%
Stage 3 Prelim. alignment with motor 25.00%
Stage 4 Cold alignment with piping 30.00%
Stage 5 Final inspection 5.00%
Stage 6 Cleaning, maintenance 5.00%
Progress is calculated based on Reciprocating compressors and
drive and drive and drive and measured as per following stages:
Reciprocating compressors and drive Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 376 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Installation on foundation 20.00%
Stage 2 Cylinder installation 10.00%
Stage 3 Levelling, bolt tightening 10.00%
Stage 4 Motor installation 15.00%
Stage 5 Prelim. cylinder installation 10.00%
Stage 6 Utility line installation 10.00%
Stage 7 Cleaning of cylinder suction valves 10.00%
Stage 8 Final alignment, final inspection 15.00%
Progress is calculated based on Centrifugal compressors and drive
and measured as per following stages:
Stage Description WF for
stages
Centrifugal compressors and drive Work Step Stage 1 Installation on foundation 20.00%
Stage 2 Levelling, bolt tightening 15.00%
Stage 3 Motor installation 10.00%
Stage 4 Prelim. cylinder installation 15.00%
Stage 5 Utility line installation 15.00%
Stage 6 Cleaning of cylinder suction valves 5.00%
Stage 7 Final alignment, final inspection 15.00%
Stage 8 Maintenance 5.00%

Progress is calculated based on Mixers and agitators and drive


and measured as per following stages:
Mixers and agitators Work Step Stage Description WF for
stages
Stage 1 Installation on foundation 10.00%
Stage 2 Shaft/main rotor installation 30.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 377 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Blades installation 20.00%
Stage 4 Motor installation 20.00%
Stage 5 Accessories installation 15.00%
Stage 6 Final alignment, final inspection 5.00%
Machinery - Internal Installation Progress is calculated based on Tray Installation and measured
Tray Installation as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Transport to jobsite 10.00%
Trays
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Distributors, grids, demisters, etc.
and measured as per following stages:
Stage Description WF for
stages
Distributors, grids, demisters, etc. Work Step Stage 1 Transport to jobsite 10.00%
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Inert Packing and measured as
Filling materials ( catalyst & packing )
per following stages:
Stage Description WF for
Work Step
stages
Inert Packing
Stage 1 Transport to jobsite 10.00%
Stage 2 Erection 70.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 378 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Chemicals, desiccant, catalysts
and measured as per following stages:
Stage Description WF for
stages
Chemicals, desiccant, catalysts Work Step
Stage 1 Transport to jobsite 10.00%
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Air coolers erection and
Air Coolers & Cooling Towers
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Ground Structure Pre-Assembly 40.00%
Air Cooler Erection Stage 2 Structure & Bundles erection 10.00%
Stage 3 Fans & Motors Installation 20.00%
Stage 4 Alignment 20.00%
Stage 5 Final Inspection 10.00%
Progress is calculated based on Package and Miscellaneous
Package and Miscellaneous Erection Erection and measured as per following stages:
Stage Description WF for
Work Step stages
Skid mounted packages Stage 1 Installation on foundation 30.00%
Stage 2 Assembling of skids/equipment 20.00%
Stage 3 Disassembled parts erection 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 379 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Levelling, bolt tightening 15.00%
Stage 5 Tot skid/package level, bolt tighten. 10.00%
Stage 6 Final inspection 5.00%
Progress is calculated based on Items in one piece and measured
Heavy Lift
as per following stages:
Stage Description WF for
Work Step stages
Items in one piece Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Items in several pieces ( typical
for 3 pieces) and measured as per following stages:
Items in several pieces
Work Step Stage Description WF for
( typical for 3 pieces)
stages
Stage 1 1st Part Erection on foundation 10.00%
Stage 2 2nd Part Erection on foundation 10.00%
Stage 3 Welding & X-ray examination 20.00%
Stage 4 3rd Part Erection on foundation 10.00%
Stage 5 Welding & X-ray examination 20.00%
Stage 6 Levelling, plumb adjustment, bolt tightening 10.00%
Stage 7 Final inspect., manholes closure 20.00%
Progress is calculated based on Vertical vessels/exchangers (shop
Static Equipment
assembled) and measured as per following stages:
Work Step Stage Description WF for
Vertical vessels/exchangers (shop assembled) stages
Stage 1 Erection on foundation 50.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 380 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Stage Description WF for
stages
Horiz. vessels/exchangers (shop assembled) Work Step Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Vert. vessels/exch. (shop
assemble.) with testing and measured as per following stages:
Stage Description WF for
stages
Vert. vessels/exch. (shop assemble.) with testing Work Step
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Testing 20.00%
Stage 4 Final inspect., manholes closure 10.00%
Progress is calculated based on Horiz. vessels/exch. (shop
assemble.) with testing and measured as per following stages:
Stage Description WF for
stages
Horiz. vessels/exch. (shop assemble.) with testing Work Step
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Testing 20.00%
Stage 4 Final inspect., manholes closure 10.00%
STEEL STRUCTURE Progress is calculated based on Trestle structures and measured
Main Structural Steel Erection as per following stages:
WP-830 Work Step
Stage Description WF for
Trestle structures
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 381 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Assembly 20.00%
Stage 2 Erection 33.00%
Stage 3 Alignment 14.00%
Stage 4 Welding and/or bolting 26.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 3.00%
Progress is calculated based on Process structures and measured
as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 19.00%
Process structures Work Step Stage 2 Erection 37.00%
Stage 3 Alignment 13.00%
Stage 4 Welding and/or bolting 25.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 2.00%
Progress is calculated based on Pipe racks and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Assembly 21.00%
Pipe racks Work Step
Stage 2 Erection 22.00%
Stage 3 Alignment 14.00%
Stage 4 Welding and/or bolting 36.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 3.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 382 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Steel Frames and measured as
per following stages:
Stage Description WF for
stages
Steel frames on concrete structures Work Step Stage 1 Erection 40.00%
Stage 2 Alignment 20.00%
Stage 3 Welding and/or bolting 25.00%
Stage 4 Cleaning 5.00%
Stage 5 Final check 10.00%

Progress is calculated based on Ladders & Handrails\ and


Secondary Structural Steel Erection
measured as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 21.00%
Work Step
Stage 2 Erection 36.00%
Ladders and handrails
Stage 3 Alignment 14.00%
Stage 4 Welding and/or bolting 22.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 3.00%

Progress is calculated based on Gratings and measured as per


following stages:
Stage Description WF for
Gratings Work Step stages
Stage 1 Material Selection 15.00%
Stage 2 Erection and Cleaning 35.00%
Stage 3 Adjustment 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 383 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Securing 20.00%
Stage 5 Painting/Touch up 5.00%
Stage 6 Final check 5.00%
Progress is calculated based on Gratings and measured as per
following stages:
Stage Description WF for
stages
Checkered plates Work Step
Stage 1 Erection 43.00%
Stage 2 Securing 36.00%
Stage 3 Cleaning 14.00%
Stage 4 Check 7.00%

Progress is calculated based on Platforms & walkways on


equipment and measured as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 25.00%
Platforms & walkways on equipment Work Step
Stage 2 Erection 33.00%
Stage 3 Alignment 17.00%
Stage 4 Welding and/or bolting 17.00%
Stage 5 Cleaning 5.00%
Stage 6 Final check 3.00%
Progress is calculated based on Equipment frames / saddles on
equipment and measured as per following stages:
Equipment frames / saddles Work Step Stage Description WF for
stages
Stage 1 Assembly 23.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 384 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Erection 23.00%
Stage 3 Alignment 16.00%
Stage 4 Welding and/or bolting 30.00%
Stage 5 Cleaning 5.00%
Stage 6 Final check 3.00%

Progress is calculated based on Buildings and shelters structures


on equipment and measured as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 19.00%
Buildings and shelters structures Work Step
Stage 2 Erection 37.00%
Stage 3 Alignment 13.00%
Stage 4 Welding and/or bolting 25.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 2.00%
Progress is calculated based on Steelworks erection on vessels
on equipment and measured as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 25.00%
Steelworks erection on vessels Work Step
Stage 2 Erection 33.00%
Stage 3 Alignment 17.00%
Stage 4 Welding and/or bolting 17.00%
Stage 5 Cleaning 5.00%
Stage 6 Final check 3.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 385 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Ladders & Handrails and
CLADDING
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 15.00%
Stage 2 Thermal sheet erection 25.00%
Work Step Stage 3 Thermal sheet fastening 10.00%
Siding and roofing
Stage 4 External sheet erection 20.00%
Stage 5 External sheet bolting/fixing 10.00%
Stage 6 Accessories erection 15.00%
Stage 7
Final check 5.00%

Progress is calculated based Siding and roofing (Sandwich Panel)


and measured as per following stages:
Stage Description WF for
stages
Siding and roofing (Sandwich Panel) Work Step Stage 1 Prefabrication 15.00%
Stage 2 Panel Installation 55.00%
Stage 3 Panel bolting/fixing 10.00%
Stage 4 Accessories Erection 15.00%
Stage 5 Final Check 5.00%
PIPING WORKS Progress is calculated based on Piping >= 2" prefabrication All
Pre-Fabrication materials and measured as per following stages:
WP-831 Work Step
Piping >= 2" prefabrication Stage Description WF for
All materials stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 386 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Sectioning 25.00%
Stage 2 Assembly, tack welding 20.00%
Stage 3 Welding 30.00%
Stage 4 X-ray examination 10.00%
Stage 5 Stress relieving 10.00%
Stage 6 Transport to storage area 5.00%

Progress is calculated based on Miscellaneous Fitting


prefabrication and measured as per following stages:
Stage Description WF for
stages
Stage 1 Sectioning 25.00%
Miscellaneous Work Step
Fitting prefabrication Stage 2 Assembly, spot welding 20.00%
Stage 3 Welding 30.00%
Stage 4 X-ray examination 10.00%
Stage 5 Stress relieving 10.00%
Stage 6 Transport to storage area 5.00%
Progress is calculated based on Piping up to 2" on site Fabrication
Erection
and erection and measured as per following stages:
Stage Description WF for
stages
Stage 1 Material Preparation, select &
3.00%
transportation
Work Step
Piping >= 2" on site Stage 2 Erection 17.00%
(excl. control valves & safety valves) Stage 3 Alignment, welding 35.00%
Stage 4 Auxiliary supports on pipe 10.00%
Stage 5 Breathers pipe drains 10.00%
Stage 6 X-ray examination, stress relieving hydro test 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 387 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Hydro test 13.00%
Stage 8
Finishing works, Final Check 2.00%

Progress is calculated based on Piping up to 1½" on site


Fabrication and erection and measured as per following stages:

Stage Description WF for


stages
Stage 1 Material Preparation, select &
3.00%
Piping up to 1½" on site transportation
Fabrication and erection Work Step Stage 2 Erection 17.00%
Stage 3 Alignment, welding 35.00%
Stage 4 Auxiliary supports on pipe 10.00%
Stage 5 Breathers pipe drains 10.00%
Stage 6 X-ray examination, stress relieving hydro
10.00%
test
Stage 7 Hydro test 13.00%
Stage 8 Finishing works, Final Check 2.00%
Progress is calculated based on underground Piping on site
U/G Piping Fabrication and erection and measured as per following stages:

Stage Description WF for


stages
Work Step Stage 1 Excavation 20.00%
Trench/Backfilling for U/G press. Pipe Stage 2 Sand bed/lean concrete 20.00%
Stage 3 Anchor blocks 20.00%
Stage 4 Backfiring 20.00%
Stage 5 Finishing 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 388 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on underground Piping on site
Fabrication and erection and measured as per following stages:

Stage Description WF for


stages
Underground piping on site Stage 1 Material Preparation, select & transport 3.00%
Work Step Stage 2 Erection 27.00%
Stage 3 Welding 45.00%
Stage 4 X-ray examination 5.00%
Stage 5 Final check & Testing 10.00%
Stage 6
Wrapping of welded parts 10.00%

Progress is calculated based on underground Piping on site


Fabrication and erection and measured as per following stages:

Stage Description WF for


stages
Underground piping on site up to 1 1/2"
Work Step Stage 1 Transport & Prefabrication 30.00%
Stage 2 Erection 20.00%
Stage 3 Alignment & Welding or threading 25.00%
Stage 4 Testing 10.00%
Stage 5 Bitumizing of welded parts 10.00%
Stage 6 Final check 5.00%

Progress is calculated based on underground Piping on site


Underground piping off site Fabrication and erection and measured as per following stages:
Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 389 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Material Preparation, select & transport 5.00%
Stage 2 Pipe fabrication, erection 35.00%
Stage 3 X-ray examination 25.00%
Stage 4 Testing 10.00%
Stage 5 Bitumizing of welded parts 10.00%
Stage 6 Final check 10.00%

Progress is calculated based on underground Piping on site


Fabrication and erection and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 10.00%
Carbon Steel sewers Work Step Stage 2 Sand bed 10.00%
Stage 3 Pipe installation 30.00%
Stage 4 Welding 20.00%
Stage 5 Testing 10.00%
Stage 6 Continuity check on wrapping 10.00%
Stage 7 Sand cover & backfilling 10.00%
Progress is calculated based on underground Piping on site
Fabrication and erection and measured as per following stages:
Stage Description WF for
stages
Concrete sewers Work Step Stage 1 Excavation 10.00%
Stage 2 Lean concrete 15.00%
Stage 3 Pipe installation 45.00%
Stage 4 Joint sealing 5.00%
Stage 5 Testing 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 390 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 Sand covering 10.00%
Stage 7 Backfilling 10.00%
Progress is calculated based on Plastic GRP on site Fabrication
Plastic, GRP and erection and measured as per following stages:

Stage Description WF for


stages
Stage 1 Excavation 10.00%
Work Step
Stage 2 Lean concrete 15.00%
Plastic material sewers Stage 3 Pipe installation 45.00%
Stage 4 Joints sealing 5.00%
Stage 5 Testing 5.00%
Stage 6 Sand covering 10.00%
Stage 7 Backfilling 10.00%

Others

Progress is calculated based on others on site Fabrication and


erection and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 10.00%
Cast Iron sewers Work Step
Stage 2 Lean concrete 10.00%
Stage 3 Pipe installation 45.00%
Stage 4 Joints sealing 10.00%
Stage 5 Testing 5.00%
Stage 6 Sand covering 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 391 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Backfilling 10.00%
Progress is calculated based on Demolition and measured as per
Demolition
following stages:
Stage Description WF for
Work Step stages
Demolitions Stage 1 Ground Preparation 5.00%
Stage 2 Concrete/Masonry demolition 65.00%
Stage 3 Transportation 30.00%
Progress is calculated based on Steel tubing installation and
Steam Tracing
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Tracer installation 40.00%
Steel tubing installation Stage 2 Pre-insulated tubing installation 40.00%
Stage 3 Trays and supports for tubing 10.00%
Stage 4 Test 5.00%
Stage 5 Final check 5.00%

Progress is calculated based on Copper tubing installation and


measured as per following stages:
Stage Description WF for
stages
Copper tubing installation Work Step Stage 1 Tracer installation 40.00%
Stage 2 Trays and supports for tubing 25.00%
Stage 3 Pre-insulated tubing installation 25.00%
Stage 4 Test 5.00%
Stage 5 Final check 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 392 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Control valve erection and
Miscellaneous / Accessories- Piping
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Valve erection 80.00%
Control valve erection Stage 2 Bolting 10.00%
Stage 3 Final check 10.00%
Progress is calculated based on Safety valve erection and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection for piping alignment 40.00%
Safety valve erection Work Step Stage 2 Valve dismantling for test 20.00%
Stage 3 Bolting 35.00%
Stage 4 Final check 5.00%

Progress is calculated based on Hot Supports and measured as


Supports - Prefabrication
per following stages:
Stage Description WF for
stages
Work Step Stage 1 Sectioning 35.00%
Hot Supports
Stage 2 Assembly, spot welding 25.00%
Stage 3 Welding 35.00%
Stage 4 Transport to storage area 5.00%

Progress is calculated based on Grounding cable (u/g) with


WP-832 ELECTRICAL WORKS Work Step
connections and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 393 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Laying of u/g conductor 65.00%
Grounding cable (u/g) with connections
Stage 2 Cord joints/derivations 27.00%
Stage 3 Tests 6.00%
Stage 4 Final inspection 2.00%

Progress is calculated based on Grounding rods & pits and


erection and measured as per following stages:
Stage Description WF for
Grounding rods & pits stages
Work Step
Stage 1 Installation of pit 60.00%
Stage 2 Installation of rods 25.00%
Stage 3 Execution of connections 10.00%
Stage 4 Inspection and tests 5.00%
Progress is calculated based on Grounding rods w/o pits and
measured as per following stages:
Stage Description WF for
Grounding rods w/o pits Work Step stages
Stage 1 Installation of rods 65.00%
Stage 2 Execution of connections 25.00%
Stage 3 Inspection and tests 10.00%
Progress is calculated based on Grounding bars and erection and
measured as per following stages:
Grounding bars Work Step Stage Description WF for
stages
Stage 1 Bar installation 30.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 394 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Stub-up and concrete base 30.00%
Stage 3 Connection execution 30.00%
Stage 4 Tests 8.00%
Stage 5 Final inspection 2.00%
Progress is calculated based on Overhead copper conduits
installation and erection and measured as per following stages:
Stage Description WF for
Overhead copper conduits installation Work Step stages
Stage 1 Fittings installation 10.00%
Stage 2 Cord laying and fixing 85.00%
Stage 3 Final inspection 5.00%
Progress is calculated based on Connections of equip to the
grounding network and erection and measured as per following
stages:
Stage Description WF for
Connections of equip to the grounding network Work Step stages
Stage 1 Connection execution 90.00%
Stage 2 Protective paint 8.00%
Stage 3 Final inspection 2.00%
Progress is calculated based on Installation of plates (earthing
bus) and erection and measured as per following stages:
Stage Description WF for
stages
Installation of plates (earthing bus) Work Step Stage 1 Plate prefabrication 30.00%
Stage 2 Plate installation 60.00%
Stage 3 Protective paint 5.00%
Stage 4 Final inspection 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 395 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Lightning protection system and
erection and measured as per following stages:
Stage Description WF for
stages
Lightning protection system Work Step
Stage 1 Steel plate installation 60.00%
Stage 2 Rods installation 20.00%
Stage 3 Execution of connections 10.00%
Stage 4 Inspection and tests 10.00%
Sub-Station Installation Progress is calculated based on Transformers and measured as
Transformer per following stages:
Stage Description WF for
stages
Stage 1 Transportation and alignment 20.00%
Work Step
Stage 2 Mechanical connections 5.00%
Transformers
Stage 3 Transformer electrical connection 25.00%
Stage 4 Panel electrical connection 30.00%
Stage 5 Tests 10.00%
Stage 6 Final inspection 10.00%
Progress is calculated based on MCC / Switchgears installation
Electrical Equipment
and measured as per following stages:
Stage Description WF for
Work Step stages
MCC / Switchgears installation Stage 1 Preparation 20.00%
Stage 2 Installation 70.00%
Stage 3 Tests / Checks 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 396 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Bus duct installation and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Supports prefabrication 20.00%
Bus duct installation Work Step
Stage 2 Supports installation 30.00%
Stage 3 Bus duct installation 40.00%
Stage 4 Final Alignment 10.00%
Progress is calculated based on Batteries installation and
measured as per following stages:
Stage Description WF for
stages
Batteries installation Work Step
Stage 1 Supports installation 20.00%
Stage 2 Installation 30.00%
Stage 3 Acid Filling 30.00%
Stage 4 Tests / Checks 20.00%
Progress is calculated based on Diesel generators and
measured as per following stages:
Stage Description WF for
stages
Diesel generator Work Step Stage 1 Erection on foundation 30.00%
Stage 2 Electrical Connections 40.00%
Stage 3 Testing 20.00%
Stage 4 Finals inspect. 10.00%
Progress is calculated based on Cable trays and cable ladder
Cable trays in S/S Work Step
installation and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 397 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Check of tray layout 10.00%
Cable trays and cable ladder installation
Stage 2 Installation of supports 35.00%
Stage 3 Installation of trays 50.00%
Stage 4 Sealing of conduit entering cable room 5.00%
Interconnecting cables connections Progress is calculated based on Interconnecting cables
connection and measured as per following stages:
Stage Description WF for
Work Step
Installation of Interconnecting cables stages
Stage 1 Laying 80.00%
Stage 2 Checks 20.00%
Progress is calculated based on Interconnecting cables
connection and measured as per following stages:
Stage Description WF for
Connection of Interconnecting cables Work Step stages
Stage 1 Terminations 70.00%
Stage 2 Testing 20.00%
Stage 3 Checks 10.00%
ELECTRICAL CABLES
Progress is calculated based on Cable trays and cable ladder
Cable trays and conduits
installation and measured as per following stages:

Stage Description WF for


Work Step
stages
Cable trays/ladders installation
Stage 1 Prefabrication of supports 20.00%
Stage 2 Installation of supports 32.00%
Stage 3 Installation of trays 39.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 398 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Grounding of trays 4.00%
Stage 5 Installation of covers 5.00%
Progress is calculated based on Underground conduits
installation and measured as per following stages:
Stage Description WF for
stages
Underground conduits installation
Work Step Stage 1 Placing supports 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit and stub up 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Progress is calculated based on Above ground conduits
installation and measured as per following stages:
Stage Description WF for
stages
Above ground conduits installation Stage 1 Supports installation 15.00%
Work Step
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%

Progress is calculated based on U/G cables and measured as per


Cable pulling
following stages:
Work Step Stage Description WF for
stages
U/G cables
Stage 1 Stub up & concrete base 5.00%
Stage 2 Handling of cable drums 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 399 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Laying of cables 65.00%
Stage 4 Cable markers installation 10.00%
Stage 5 Insulation test 10.00%
Stage 6 Cable way markers 4.00%
Stage 7 Final inspection 1.00%
Progress is calculated based on Cables in trays/ladders and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Handling of cable drums 5.00%
Cables in trays/ladders Work Step
Stage 2 Laying of cables 70.00%
Stage 3 Insulation test 10.00%
Stage 4 Markers installation 10.00%
Stage 5 Final inspection 5.00%

Progress is calculated based on Cables in conduit and measured


as per following stages:
Stage Description WF for
stages
Stage 1 Handling of cable drums 5.00%
Cables in conduit Work Step Stage 2 Conduit cleaning 5.00%
Stage 3 Cable pulling 65.00%
Stage 4 Insulation test 10.00%
Stage 5 Markers installation 10.00%
Step 6 Final inspection 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 400 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Cable connections and measured
Connections
as per following stages:
Stage Description WF for
Work Step stages
Cable connections Stage 1 Terminations 70.00%
Stage 2 Testing 20.00%
Stage 3 Checks 10.00%

Control station installation Progress is calculated based on Control station industrial type
and measured as per following stages:
Stage Description WF for
Work Step stages
Control station Ex type Stage 1 Installation 80.00%
Stage 2 Checks 20.00%

Progress is calculated based on Power outlet Ex type and


measured as per following stages:
Control station industrial type Work Step
Stage Description WF for
stages
Stage 1 Installation 80.00%
Stage 2 Checks 20.00%
Progress is calculated based on Control station industrial type
Power outlets installation
and measured as per following stages:
Stage Description WF for
Work Step stages
Power outlet Ex type Stage 1 Installation 80.00%
Stage 2
Checks 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 401 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Power outlet industrial type and
measured as per following stages:
Stage Description WF for
Control station industrial type Work Step
stages
Stage 1 Installation 80.00%
Stage 2 Checks 20.00%

Progress is calculated based on Execution of underground joint


Execution of underground joint
and measured as per following stages:
Stage Description WF for
Work Step stages
Execution of underground joint Stage 1 Execution 80.00%

Stage 2 Checks 20.00%

Progress is calculated based on Junction boxes Ex type and


Junction boxes installation
measured as per following stages:

Work Step Stage Description WF for


stages
Junction boxes Ex type
Stage 1 Installation 80.00%
Stage 2 Checks 20.00%

Progress is calculated based on Junction boxes industrial type


and measured as per following stages:
Control station industrial type Work Step Work Description WF for
Step stages
Step 1 Installation 80.00%
Step 2 Checks 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 402 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Electrical Tracing and measured
as per following stages:
Stage Description WF for
stages
Electrical Tracing Stage 1 Installation of local panels 10.00%
Work Step
Stage 2 Installation of main junction boxes 10.00%
Stage 3 Heating cable installation 30.00%
Stage 4 Connection of heating cable 30.00%
Stage 5 Tests/Checks 20.00%

Progress is calculated based on Cathodic Protection and


measured as per following stages:
Stage Description WF for
stages
Cathodic Protection Work Step Stage 1 Installation of power supply unit 20.00%
Stage 2 Electrode installation & connection 20.00%
Stage 3 Electrical cable installation 20.00%
Stage 4 Test point installation & connection 20.00%
Stage 5 Tests/Checks 20.00%
Progress is calculated based on Lighting Installation and
measured as per following stages:
Stage Description WF for
stages
Lighting Installation Work Step Stage 1 Installation of local panels 20.00%
Stage 2 Installation of main junction boxes 20.00%
Stage 3 Install/ connection of lighting fixtures 40.00%
Stage 4 Tests/Checks 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 403 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
INSTRUMENT & TELECOMS WORK Progress is calculated based on Panels/marshalling cabinets and
Control Room Installation Works measured as per following stages:
Stage Description WF for
Work Step stages
Panels/marshalling cabinets Stage 1 Preparation 20.00%
Stage 2 Installation 70.00%
Stage 3 Tests / Checks 10.00%
Progress is calculated based on Cable trays in technical/control
rooms and erection and measured as per following stages:
Stage Description WF for
Cable trays in technical/control rooms
Work Step
stages
Stage 1 Supports 40.00%
Stage 2 Installation 50.00%
WP-833 Stage 3 Checks 10.00%

Progress is calculated based on Interconnecting cables and


measured as per following stages:
Stage Description WF for
Interconnecting cables Work Step
stages
Stage 1 Laying 80.00%
Stage 2 Checks 20.00%
Progress is calculated based on Interconnecting cables
connections and erection and measured as per following stages:
Interconnecting cables connections Stage Description WF for
Work Step
stages
Stage 1 Terminations 70.00%
Stage 2 Testing 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 404 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Checks 10.00%

Progress is calculated based on DCS/PLC/F&G/packages systems


cabinets and measured as per following stages:
Stage Description WF for
stages
DCS/PLC/F&G/packages systems cabinets Work Step
Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%

Stage 3 Tests / Checks 10.00%

Progress is calculated based on Trays for cables and measured as


per following stages:
Cable Pulling
Stage Description WF for
stages
Stage 1 Prefabrication of supports 20.00%
Work Step
Stage 2 Installation of supports 20.00%

Trays for cables


Stage 3 Installation of trays 40.00%
Stage 4 Grounding of trays 5.00%
Stage 5 Installation of covers 5.00%
Stage 6 Checks 10.00%
Progress is calculated based on Underground conduits and
measured as per following stages:
Stage Description WF for
Underground conduits Work Step stages
Stage 1 Placing supports 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit and stub up 40.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 405 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Progress is calculated based on Above ground conduits and
measured as per following stages:
Stage Description WF for
stages
Above ground conduits Work Step Stage 1 Supports installation 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%

Progress is calculated based on Directly buried cables and


measured as per following stages:
Stage Description WF for
stages
Stage 1 Stub up & concrete base 5.00%
Directly buried cables Work Step Stage 2 Handling of cable drums 5.00%
Stage 3 Laying of cables 55.00%
Stage 4 Cable markers installation 10.00%
Stage 5 Insulation test 10.00%
Stage 6 Cable way markers 5.00%
Stage 7 Final inspection 10.00%

Progress is calculated based on Cables in trays and measured as


Cables in trays Work Step
per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 406 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Handling of cable drums 5.00%
Stage 2 Laying of cables 65.00%
Stage 3 Insulation test 10.00%
Stage 4 Markers installation 10.00%
Stage 5 Final inspection 10.00%

Progress is calculated based on Cables in conduits and


measured as per following stages:
Stage Description WF for
stages
Stage 1 Handling of cable drums 5.00%
Cables in conduits Work Step
Stage 2 Conduit cleaning 5.00%
Stage 3 Cable pulling 60.00%
Stage 4 Insulation test 10.00%
Stage 5 Markers installation 10.00%
Stage 6 Final inspection 10.00%

Progress is calculated based on Cables connections in tech. room


and measured as per following stages:
Stage Description WF for
Cables connections in tech. room Work Step stages
Stage 1 Connections 70.00%
Stage 2 Testing 20.00%

Stage 3 Checks 10.00%


PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 407 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Electronic junction boxes and
measured as per following stages:
Junction Box & Local Panels
Stage Description WF for
stages
Stage 1 Erection 5.00%

Work Step Stage 2 Single tube trays/conduit erection 55.00%


Stage 3 Multi core cable connections 10.00%
Electronic junction boxes
Stage 4 Single cable connections 15.00%
Stage 5 Earthing 5.00%

Stage 6 Tests / Checks 10.00%

Progress is calculated based on Local panels installation &


connection and measured as per following stages:
Stage Description WF for
stages
Local panels installation & connection Work Step Stage 1 Erection 20.00%
Stage 2 Connections 50.00%
Stage 3 Testing 20.00%
Stage 4
Checks 10.00%

Progress is calculated based on Local flow indicators and


Field Instrument Works
measured as per following stages:
Work Step
Stage Description WF for
Flow Instruments
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 408 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Erection of supports 10.00%
Stage 2 Manifold erection 28.00%
Stage 3 Process connection 30.00%
Local flow indicators Stage 4 Hydrostatic testing 2.00%
Stage 5 Air distribution 22.00%
Stage 6 Pneumatic connections 4.00%
Stage 7 Checks 4.00%
Progress is calculated based on Local flow indicators and
measured as per following stages:
Stage Description WF for
stages
Magnetic flow transmitters Work Step Stage 1 Converter support erection 20.00%
Stage 2 Power cable installation 30.00%
Stage 3 Signal cable installation 30.00%
Stage 4 Electrical connections 10.00%
Stage 5 Transmitter circuit check 10.00%
Progress is calculated based on Electronic flow transmitters and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
Electronic flow transmitters Work Step
Stage 2 Manifold erection 25.00%
Stage 3 Process connection 25.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Cable installation 22.00%
Stage 6 Electrical connections 8.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 409 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Transmitter circuit check 5.00%
Progress is calculated based on Electronic level instruments
Level instrument
(displacement type) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection 20.00%

Work Step Stage 2 Discharge header erection 20.00%


Electronic level instruments (displacement type) Stage 3 Hydrostatic testing 5.00%
Stage 4 Repeater support erection 10.00%
Stage 5 Cable installation 25.00%
Stage 6 Electrical connections 10.00%
Stage 7 Transmitter circuit check 10.00%
Progress is calculated based on Electronic level transmitter (diff.
pressure type) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
Electronic level transmitter (diff. pressure type) Work Step Stage 2 Manifold erection 20.00%
Stage 3 Process connection 30.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Cable installation 22.00%
Stage 6 Electrical connections 8.00%
Stage 7 Transmitter circuit check 5.00%

Progress is calculated based on Electronic flow transmitters and


Level glass gauges Work Step
measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 410 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Erection 40.00%
Stage 2 Discharge header erection 50.00%
Stage 3 Hydrostatic testing 10.00%
Progress is calculated based on Electronic pressure transmitters
Pressure Instrument
and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
Work Step Stage 2 Manifold erection 20.00%
Electronic pressure transmitters Stage 3 Process connection 20.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Cable installation 25.00%
Stage 6 Electrical connections 10.00%
Stage 7 Transmitter circuit check 10.00%
Progress is calculated based on Local pneumatic pressure
regulators and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of supports 12.00%
Local pneumatic pressure regulators Work Step Stage 2 Manifold erection 20.00%
Stage 3 Process connection 20.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Air distribution 26.00%
Stage 6 Pneumatic connections 9.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 411 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Checks 10.00%

Progress is calculated based on Electronic differential pressure


transmitters and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
Electronic differential pressure transmitters Work Step Stage 2 Manifold erection 13.00%
Stage 3 Process connection 40.00%
Stage 4 Hydrostatic testing 5.00%
Stage 5 Cable installation 18.00%
Stage 6 Electrical connections 6.00%
Stage 7 Transmitter circuit check 6.00%
Progress is calculated based on Local differential pressure gauges
and measured as per following stages:
Stage Description WF for
stages
Local differential pressure gauges Work Step
Stage 1 Erection of supports 12.00%
Stage 2 Manifold erection 40.00%
Stage 3 Process connection 40.00%
Stage 4 Hydrostatic testing 8.00%
Progress is calculated based on Direct pressure switches and
measured as per following stages:
Stage Description WF for
Direct pressure switches Work Step
stages
Stage 1 Erection 12.00%
Stage 2 Process diagram 40.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 412 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Hydrostatic testing 3.00%
Stage 4 Cable installation 25.00%
Stage 5 Electrical connections 10.00%
Stage 6 Checks 10.00%

Progress is calculated based on Manometers and measured as


per following stages:
Stage Description WF for
Manometers Work Step stages
Stage 1 Manifold prefabrication 60.00%
Stage 2 Manifold installation 20.00%
Stage 3 Manometers erection 20.00%
Progress is calculated based on Bulb thermostats and measured
Temperature instrument
as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Support erection 20.00%
Bulb thermostats Stage 2 Capillary arrangement 20.00%
Stage 3 Cable installation 40.00%
Stage 4 Electrical connections 10.00%
Stage 5 Checks 10.00%
Progress is calculated based on Local pneumatic temperature
regulators and measured as per following stages:
Local pneumatic temperature regulators Work Step
Stage Description WF for
stages
Stage 1 Support erection 20.00%
Stage 2 Capillary arrangement 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 413 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Air distribution 40.00%
Stage 4 Pneumatic connections 10.00%
Stage 5 Checks 10.00%
Progress is calculated based on Local MV electric converters and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of support and repeater 20.00%
Local MV electric converters Work Step
Stage 2 Thermocouple 5.00%
Stage 3 Cable installation 50.00%
Stage 4 Electrical connections 15.00%
Stage 5 Transmitter circuit check 10.00%

Progress is calculated based on Electronic pressure transmitters


and measured as per following stages:
Stage Description WF for
stages
Thermocouples or RTD Work Step
Stage 1 Erection of traps and elements 5.00%

Stage 2 Cable installation 70.00%


Stage 3 Electrical connections 15.00%
Stage 4 Checks 10.00%

Progress is calculated based on Dial thermometers and measured


as per following stages:
Dial thermometers Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 414 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Trap erection 80.00%
Stage 2 Dial installation 20.00%
Progress is calculated based on Flux stats and measured as per
On line instruments
following stages:
Stage Description WF for
stages
Work Step
Stage 1 Cable installation 70.00%
Flux stats
Stage 2 Electrical connections 20.00%
Stage 3 Checks 10.00%

Progress is calculated based on Electronic flow rate transmitters


and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection check 10.00%
Electronic flow rate transmitters Work Step
Stage 2 Repeater erection 15.00%
Stage 3 Cable installation 40.00%
Stage 4 Electrical connections 15.00%
Stage 5 Transmitter circuit check 10.00%
Stage 6 Line washing 10.00%

Progress is calculated based on Control valves equip, with electro-


pneum, positioner and measured as per following stages:
Control valves equip, with electro-pneum,
Work Step Stage Description WF for
positioner stages
Stage 1 Air distribution 50.00%
Stage 2 Cable and pneum. tube install. 35.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 415 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Electrical or pneum. connections 5.00%
Stage 4 Line washing 5.00%
Stage 5 Circuit check 5.00%
Progress is calculated based on Control valves with I/P and
pneum. Positioner and measured as per following stages:
Stage Description WF for
stages
Stage 1 I/p erection 15.00%

Control valves with I/P and pneum. Positioner Work Step Stage 2 I/p air distribute. & positioner 40.00%
Stage 3 Cable installation 25.00%
Stage 4 Electrical connections 4.00%
Stage 5 Pneumatic connections 10.00%
Stage 6 Line washing 2.00%
Stage 7 Circuit check 4.00%

Progress is calculated based on Control valves without positioner


and measured as per following stages:
Stage Description WF for
stages
Control valves without positioner Work Step
Stage 1 Pneumatic tube installation 60.00%
Stage 2 Pneumatic connections 25.00%
Stage 3 Line washing 5.00%
Stage 4 Circuit check 10.00%
Progress is calculated based on Local pneumatic receiver
regulators and measured as per following stages:
Local pneumatic receiver regulators Work Step Stage Description WF for
stages
Stage 1 Erection 25.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 416 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Air distribution 50.00%
Stage 3 Pneumatic connections 15.00%
Stage 4 Checks 10.00%

Progress is calculated based on Solenoid valves and measured as


per following stages:
Stage Description WF for
stages
Solenoid valves Work Step Stage 1 Installation 10.00%
Stage 2 Cable installation 60.00%
Stage 3 Electrical connections 10.00%
Stage 4 Pneumatic connections 10.00%
Stage 5 Checks 10.00%

Progress is calculated based on Steam tracing for instruments


Steam tracing for instruments
and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Sub-header distribution 50.00%

Steam tracing for instruments Stage 2 Copper tube steam tracer 20.00%
Stage 3 Condensate discharge manifold 20.00%
Stage 4 Piping connections 5.00%
Stage 5 Checks 5.00%
TELECOMS WORKS
Progress is calculated based on P.A.B.X. and measured as per
Telephone following stages:
Work Step
Stage Description WF for
P.A.B.X. Installation
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 417 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Transport on the spot 5.00%

Stage 2 Installation of support frame 10.00%


Stage 3 Installation of PABX 25.00%

Stage 4 Batteries and accessories 15.00%


Stage 5 Execution of connections 30.00%

Stage 6 Tests 15.00%

Progress is calculated based on Telephone sets (wall type) and


measured as per following stages:
Stage Description WF for
stages
Telephone sets (wall type) installation Work Step Stage 1 Preparation of support 12.00%
Stage 2 Acoustic booth 28.00%
Stage 3 Installation of telephone set 20.00%
Stage 4 Wiring 30.00%
Stage 5 Final Tests 10.00%
Public Address Progress is calculated based on Loud speaker and measured as
per following stages:
Stage Description WF for
stages
Work Step
Loud speakers Stage 1 Support preparation 5.00%
Stage 2 Loud speaker installation 40.00%
Stage 3 Wiring 30.00%
Stage 4 Checks 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 418 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Final tests 20.00%
Progress is calculated based on Public address console and
measured as per following stages:
Stage Description WF for
Public address consoles
Work Step
stages
Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%
Stage 3 Tests / Checks 10.00%

Progress is calculated based on CCTV camera installation and


Closed circuit television (CCTV)
erection and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Support preparation 5.00%
CCTV camera installation Stage 2 Camera Installation 40.00%
Stage 3 Wiring 30.00%
Stage 4 Checks 5.00%
Stage 5 Final tests 20.00%
Progress is calculated based on CCTV control system and
erection and measured as per following stages:
Stage Description WF for
CCTV control system
Work Step stages
Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%
Stage 3 Tests / Checks 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 419 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Siren installation and erection
Siren
and measured as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Support preparation 20.00%
Siren installation
Stage 2 Siren installation 40.00%
Stage 3 Wiring 30.00%
Stage 4 Checks 10.00%

Progress is calculated based on Radio equipment (by antenna)


Radio system
and erection and measured as per following stages:
Stage Description WF for
Work Step stages
Radio equipment (by antenna) Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%
Stage 3 Tests / Checks 10.00%

Progress is calculated based on Telecom cables installation and


Telecom Cables
measured as per following stages:
Stage Description WF for
Work Step stages
Telecom cables installation Stage 1 Laying 50.00%
Stage 2 Terminations 30.00%
Stage 3 Checks 20.00%
Progress is calculated based on Calibrate and measured as per
Instrumentation Test
following stages:
Work Step
Stage Description WF for
Instruments Calibration
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 420 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Calibrate 100.00%

Progress is calculated based on Loop Checking and measured as


per following stages:
Stage Description WF for
Loop Checking Work Step stages
Stage 1 Preparation 20.00%
Stage 2 Loop Check 80.00%

INSULATION - OTHER WORKS


Progress is calculated based on Piping hot insulation and
Hot Insulation Works measured as per following stages:
Stage Description WF for
stages
Stage 1 Steel sheet prefabrication 10.00%
Stage 2 Scaffolding erection 15.00%
Work Step
Stage 3 Insulating layer installation 25.00%
Piping hot insulation
Stage 4 Sheeting installation 30.00%
834 Stage 5 Miscellaneous finishing works 5.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%

Progress is calculated based on Equipment hot insulation and


measured as per following stages:
Equipment hot insulation Work Step
Stage Description WF for
stages
Stage 1 Steel sheet prefabrication 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 421 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Scaffolding erection 10.00%
Stage 3 Insulating layer installation 30.00%
Stage 4 Sheeting installation 30.00%
Stage 5 Miscellaneous finishing works 5.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
Progress is calculated based on Personnel protection insulation
(for piping) and measured as per following stages:
Stage Description WF for
stages
Personnel protection insulation (for piping) Work Step
Stage 1 Steel sheet prefabrication 20.00%
Stage 2 Insulating layer installation 40.00%
Stage 3 Sheeting installation 30.00%
Stage 4 Finishing 10.00%
Progress is calculated based on Piping cold insulation and
Cold Insulation Works
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 20.00%
Work Step Stage 2 Scaffolding erection 10.00%
Piping cold insulation Stage 3 Insulating layer installation 15.00%
Stage 4 Vapour barrier 20.00%
Stage 5 Sheeting installation 20.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 422 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Equipment cold insulation and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 20.00%
Equipment cold insulation Work Step Stage 2 Scaffolding erection 10.00%
Stage 3 Insulating layer installation 15.00%
Stage 4 Vapor barrier 20.00%
Stage 5 Sheeting installation 20.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
PAINTING Progress is calculated based on Piping painting (2+2 coats) and
Painting Works measured as per following stages:
Stage Description WF for
stages
Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Work Step
Stage 3 2nd primer coat 10.00%
Piping painting (2+2 coats)
Stage 4 1st finish coat 15.00%
Stage 5 2nd finish coat 15.00%
Stage 6 Numbering or labelling 5.00%
Stage 7 Final cleaning and touch up 10.00%
Stage 8 Final check 5.00%
Progress is calculated based on Piping painting in shop (2 coats)
Piping painting in shop (2 coats) Work Step
and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 423 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Wire brushing or shot blasting 50.00%
Stage 2 1st primer coat 20.00%
Stage 3 2nd primer coat 20.00%
Stage 4 Final check 10.00%
Progress is calculated based on Piping painting in field (2 coats
and measured as per following stages:
Stage Description WF for
stages
Piping painting in field (2 coats) Work Step Stage 1 1st finish coat 35.00%
Stage 2 2nd finish coat 35.00%
Stage 3 Numbering or labelling 10.00%
Stage 4 Final cleaning and touch up 10.00%
Stage 5 Final check 10.00%
Progress is calculated based on Steel structures painting (2+2
coats) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Steel structures painting (2+2 coats) Work Step Stage 3 2nd primer coat 10.00%
Stage 4 Touch up 14.00%
Stage 5 1st finish coat 16.00%
Stage 6 2nd finish coat 15.00%
Stage 7 Touch up 3.00%
Stage 8 Final check 2.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 424 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Steel structure painting in field (2
coats) and measured as per following stages:
Stage Description WF for
stages
Stage 1 1st finish coat 35.00%
Steel structure painting in field (2 coats) Work Step Stage 2 2nd finish coat 35.00%

Stage 3 Numbering or labelling 10.00%

Stage 4 Final cleaning and touch up 10.00%

Stage 5 Final check 10.00%

Progress is calculated based on Equipment painting (2 coats) and


measured as per following stages:

Stage Description WF for


stages
Stage 1 Intermediate coat 35.00%
Equipment painting (2 coats) Work Step
Stage 2 Final coat 35.00%
Stage 3 Numbering or labelling 20.00%

Stage 4 Touch up 5.00%

Stage 5 Final check 5.00%

Progress is calculated based on Equipment painting (final coat)


Equipment painting (final coat) Work Step
and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 425 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Final coat 85.00%
Stage 2 Touch up 10.00%
Stage 3 Final check 50.00%
Progress is calculated based on Tanks and spheres painting (2+2
coats) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Tanks and spheres painting (2+2 coats)
Work Step Stage 3 2nd primer coat 10.00%
Stage 4 Touch up 10.00%
Stage 5 1st finish coat 15.00%
Stage 6 2nd finish coat 5.00%

Stage 7 Numbering or labelling 15.00%


Stage 8 Touch up 3.00%
Stage 9 Final check 2.00%
Progress is calculated based on Conformity check and measured
as per following stages:
Stage Description WF for
Mechanical Completion stages
WP - 836 Work Step
Stage 1 Facilities constructed per AFC 10.00%
drawings & specs
Stage 2 Piping flushing & Hydro test 25.00%
Stage 3 Cable insulation & Continuity test 15.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 426 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Coating Test 10.00%
Stage 5 Inspection Test & Records (ITR) 35.00%
Stage 6 Red Line Marked up as built. 5.00%
Progress is calculated based on Survey and staking and
Pipeline Installation (CROSS-COUNTRY )
measured as per following stages:
Stage Description WF for
Work Step
stages
Survey and staking
Stage 1 Survey 50.00%
Stage 2 Staking 50.00%
Progress is calculated based on ROW-Clearing and Grading and
measured as per following stages:
Stage Description
Stage 1 Clearing & Grading 40.00%
ROW-Clearing and Grading & Access
Work Step Stage 2 Fill 40.00%
Preparation
WP - 837-846 Stage 3 Compact 15.00%
Stage 4 Test 5.00%

Progress is calculated based on Pipe Transportation and


measured as per following stages:
Pipe Transportation Work Step Stage Description WF for
stages
Stage 1 Pipe Transportation 100.00%
Progress is calculated based on Trenching and measured as per
following stages:
Trench Excavation Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 427 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Actual Trench Excavation in Km 90.00%
Stage 2 Accepted Total no. of Trench 10.00%
Excavation in Km
Progress is calculated based on Pipe stringing single pipe and
measured as per following stages:
Stage Description WF for
Pipe stringing single pipe Work Step
stages
Stage 1 Actual No of Stringing single pipe 90.00%
Stage 2 Accepted Total no. of Stringing 10.00%
Progress is calculated based on Pipe stringing 2-3 pipe section
and measured as per following stages:
Stage Description WF for
Pipe stringing 2-3 pipe section Work Step stages
Stage 1 Actual No. of Stringing 2-3 pipe section 90.00%
Stage 2 Accepted Total No. of Stringing 2-3 10.00%
pipe section
Progress is calculated based on Field Bending and measured as
per following stages:
Stage Description WF for
stages
Laying/Welding & Joint Coating Work Step Stage 1 Laying 20.00%
Stage 2 Welding 40.00%
Stage 3 Joint Coating 20.00%

Stage 4 Controls 20.00%


Progress is calculated based on Field Bending and measured as
Field Bending Work Step
per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 428 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Actual no. of Bending 90.00%
Stage 2 Accepted Total no. of Bending 10.00%
Progress is calculated based on Welding of Line pipe - station
and measured as per following stages:
Stage Description WF for
Welding of Line pipe - station Work Step
stages
Stage 1 Actual no. of Welding 90.00%
Stage 2 Accepted Total no. of Welding 10.00%
Progress is calculated based on Welding of Line pipe - station on
site and measured as per following stages:
Stage Description WF for
Welding of Line pipe - onsite Work Step
stages
Stage 1 Actual no. of Welding 90.00%
Stage 2 Accepted Total no. of Welding 10.00%
Progress is calculated based on tie-in and measured as per
following stages:
Stage Description WF for
Tie-ins Work Step
stages
Stage 1 Actual No. of Tie-ins 90.00%
Stage 2 Accepted Total No. of Tie-ins 10.00%
Progress is calculated based on NDT and measured as per
following stages:
NDT Work Step Stage Description WF for
stages
Stage 1 Total No. of Joints 90.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 429 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Field Joint coating and measured
as per following stages:
Stage Description WF for
Field Joint Coating Work Step stages
Stage 1 Actual - No. of Field joints 90.00%
Stage 2 Accepted Total No. of Field Joint 10.00%
Coating
Progress is calculated based on Bedding and measured as per
following stages:
Stage Description WF for
Bedding Work Step
stages
Stage 1 Actual - No. of Bedding 90.00%
Stage 2 Accepted Total No. of Bedding 10.00%
Progress is calculated based on Lowering and measured as per
following stages:
Stage Description WF for
Lowering Work Step stages
Stage 1 Actual - No. of Lowering 90.00%
Stage 2 Accepted Total No. of Lowering 10.00%

Progress is calculated based on CP test Connection and


measured as per following stages:
CP test Connection Work Step
Stage Description WF for
stages
Stage 1 CP Test connection 90.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 430 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted 10.00%
Progress is calculated based on Padding and measured as per
following stages:
Stage Description WF for
Padding Work Step
stages
Stage 1 Actual - No. of Padding 90.00%
Stage 2 Accepted Total No. of Padding 10.00%
Progress is calculated based on Backfilling and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Box Culvert Works Work Step Stage 2 Blinding Concrete 5.00%
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 35.00%
Stage 5 Pouring 20.00%
Stage 6 Coating 5.00%
Stage 7 Backfilling 10.00%
Progress is calculated based on Backfilling and measured as per
following stages:
Stage Description WF for
stages
Backfilling/Berm Forming Work Step
Stage 1 Sand filling 20.00%
Stage 2 Backfilling 20.00%
Stage 3 Berm 1st Lay 20.00%
Stage 4 Berm 2nd Lay 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 431 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Berm 3rd Lay 10.00%
Stage 6 Final Inspection 10.00%
Progress is calculated based on Cathodic protection and
measured as per following stages:
Stage Description WF for
Cathodic protection Work Step stages
Stage 1 Actual - No. of Cathodic Protection 90.00%
Stage 2 Accepted Total No. of Cathodic 10.00%
Protection
Progress is calculated based on Pre-Commissioning and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Chemical Cleaning (Pigs or GEL Pigs) 12.00%
Stage 2 Helium Leak Detection 10.00%
Stage 3 Bolting 6.00%
Pre-commissioning Work Step
Stage 4 Hot Oil Flushing 10.00%
Stage 5 Pipe Freezing 10.00%
Stage 6 Foam Inerting 13.00%
Stage 7 Gauging 20.00%
Stage 8 Filling (Flooding) 9.00%

Stage 9 Acceptance 10.00%


Progress is calculated based on Hydrostatic and measured as per
following stages:
Hydrostatic Test Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 432 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Actual - No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Pipeline dry and measured as
per following stages:
Stage Description WF for
Pipe Line dry Work Step
stages
Stage 1 Actual - No. of Pipeline Dry 90.00%
Stage 2 Accepted Total Pipe line Dry 10.00%
Progress is calculated based on Filling with Nitrogen and
measured as per following stages:
Stage Description WF for
Filing with Nitrogen/ Discharging Air Work Step
stages
Stage 1 Actual - No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Along-Route Road and measured
as per following stages:
Stage Description WF for
Along-Route Road Work Step
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Progress is calculated based on Marker and measured as per
following stages:
Stage Description WF for
Marker Work Step
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Restoration Work Step
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 433 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Restoration and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Progress is calculated based on Stockpiling of Pipe and measured
as per following stages:
Stage Description WF for
Stockpiling of Pipe Work Step
stages
Stage 1 Actual - No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Bridge - off take and measured
as per following stages:
Stage Description WF for
Bridge - off take Work Step
stages
Stage 1 Actual - No. of Bridge 90.00%
Stage 2 Accepted Total No. of Bridge 10.00%
Progress is calculated based on Valve station and measured as
per following stages:
Stage Description WF for
stages
Valve station Work Step Stage 1 Ground Levelling (Civil works) 10.00%
Stage 2 Foundation (Civil works) 7.00%
Stage 3 Editing / Welding of Valves (Process 11.00%
works)
Stage 4 Welding of Pipelines (Process works) 8.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 434 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Coating (Process works) 6.00%
Stage 6 Contour of grounding (Electrical 7.00%
works)
Stage 7 TEG Installation (Electrical works) 4.00%
Stage 8 Lightning Protection System 7.00%
( Electrical )
Stage 9 Install Pressure Gauge Transmitter 6.00%
(Instrument works)
Stage Grounds/Gas Temperature 4.00%
10 Transmitter (Instrument works)
Stage PIG Detector (Instrument works) 15.00%
11
Stage Optical Cable laying (Instrument 8.00%
12 works)
Stage Installation of Instrument Box 3.00%
13 (Instrument works)
Stage CP Test Connection (Instrument 2.00%
14 works)
Stage Hydro Test / Drying 2.00%
15
Progress is calculated based on Access roads and measured as
per following stages:

Access roads Work Step


Stage Description WF for
stages
Stage 1 Actual - No. of Access Road 90.00%
Stage 2 Accepted Total No. of Access Road 10.00%
Progress is calculated based on Pig launcher and Receiver
Pig launcher and Receiver Work Step
installation and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 435 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Quantity of Pig Launcher and Receiver 90.00%
installed
Stage 2 Accepted Total No. of Pig Launcher and 10.00%
Receiver installed
Progress is calculated based on Helicopter landing site and
measured as per following stages:
Stage Description WF for
stages
Stage 1 ROW 8.00%
Stage 2 Staking 5.00%
Stage 3 Putting earth embankment 10.00%
Stage 4 Installation slabs 8.00%
Helicopter landing site Work Step Stage 5 Putting mixtures surfacing 10.00%
Stage 6 Sealing of joints 7.00%
Stage 7 Painting 10.00%
Stage 8 Access road 8.00%
Stage 9 Putting earth embankment 10.00%
Stage 10 Construction of roadway surfacing 8.00%
Stage 11 Slope strengthening with soil and 8.00%
grass sowing
Stage 12 Installation vane 8.00%
Progress is calculated based on Appurtenances of pipe and
measured as per following stages:
Appurtenances of pipe Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 436 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Actual - No. of Appurtenance of Pipe 90.00%
Stage 2 Accepted Total No. of Appurtenance 10.00%
of Pipe
Progress is calculated based on Power supply and measured as
per following stages:
Power supply Work Step Stage Description WF for
stages
Stage 1 Power Supply 100.00%
Progress is calculated based on Road Crossings and measured as
per following stages:
Stage Description WF for
Road Crossings Work Step
stages
Stage 1 Actual - No. of Road Crossing 90.00%
Stage 2 Accepted Total No. of Road Crossing 10.00%
Progress is calculated based on HDD River and measured as per
following stages:
Stage Description WF for
HDD River Work Step
stages
Stage 1 Actual - No. of HDD River 90.00%
Stage 2 Accepted Total No. of HDD River 10.00%
Progress is calculated based on River crossing and measured as
per following stages:
River and water channel crossing Work Step Stage Description WF for
stages
Stage 1 Actual - No. of River and Water channel 90.00%
crossing
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 437 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted Total No. of River and Water 10.00%
channel crossing
Progress is calculated based on Railway and measured as per
following stages:
Work Description WF for
Railway Work Step
Step stages
Step 1 Actual - No. of Railway 90.00%
Step 2 Accepted Total No. of Railway 10.00%
Progress is calculated based on Road crossing (casing) and
measured as per following stages:
Stage Description WF for
Road crossing (casing) Work Step stages
Stage 1 Actual - No. of Road Crossing (casing) 90.00%
Stage 2 Accepted Total No. of Road Crossing 10.00%
(casing)
Progress is calculated based on Road crossing (excavation) and
measured as per following stages:
Stage Description WF for
Road crossing (excavation) Work Step
stages
Stage 1 Actual - No. of Road Crossing 90.00%
(excavation)
Stage 2 Accepted Total No. of Road Crossing 10.00%
(excavation)
Progress is calculated based on U/G pipeline/cables and
measured as per following stages:
U/G pipeline/cables Work Step Stage Description WF for
stages
Stage 1 Actual - Linear in meters 90.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 438 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted Total No. of Linear in 10.00%
Meters
Progress is calculated based on Others / Weight Blocks and
measured as per following stages:
Stage Description WF for
Others / Weight Block Work Step stages
Stage 1 Actual - No. of Others / Weight block 90.00%

Stage 2 Accepted Total No. of Others/Weight 10.00%


Block
Progress is calculated based on U/G pipeline/cables and
measured as per following stages:
Stage Description WF for
Embankment protection Work Step stages
Stage 1 Actual - No. of Embankment Protection 90.00%
Stage 2 Accepted Total No. of Embankment 10.00%
Protection
Pre-commissioning & Testing
Progress is calculated based on Piping Pre-commissioning ( by
test Package) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Ready for flushing 15.00%
WP - 8471 Work Step
Piping Pre-commissioning ( by test Stage 2 Flushing 30.00%
Package)
Stage 3 Reinstatement 15.00%
Stage 4 PID conformity 10.00%
Stage 5 Tightness test 15.00%
Stage 6 Inerting 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 439 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 MCC Package Hand-over 10.00%
Instrumentation Progress is calculated based on SAT and measured as per
following stages:
Stage Description WF for
Site Acceptance Tests ( SAT Work Step
stages
Systems)
Stage 1 Complete SAT 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Mini Loop Check and measured
as per following stages:
Stage Description WF for
Mini Loop Check Work Step
stages
Stage 1 Mini Loop Check 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Loop Check and measured as per
following stages:
Stage Description WF for
Loop Check Work Step
stages
Stage 1 Loop Check 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Functional check and measured as
per following stages:
Stage Description WF for
Functional Check Work Step
stages
Stage 1 Functional Check 90.00%
Stage 2 Acceptance 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 440 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Building Pre-commissioning
Electrical
and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Power supply and checking 30.00%
Electrical Generator Stage 2 Control System checking 20.00%
Step 3 Motors run 30.00%
Step 4 Energizing 15.00%
Step 5 Certificate 5.00%
Progress is calculated based on Building Pre-commissioning and
measured as per following stages:
Stage Description WF for
stages
Transformer tests Work Step
Stage 1 Vector group 30.00%
Stage 2 Energization 50.00%
Stage 3 Leak test 10.00%
Stage 4 MCC Package Hand-over 10.00%

Progress is calculated based on Switchgears & MCC Tests and


measured as per following stages:
Stage Description WF for
stages
Switchgears & MCC Tests Work Step Stage 1 Megger tests - Hit pot test- Relay testing 30.00%
Stage 2 Incomer A tests 15.00%
Stage 3 Incomer B tests 15.00%
Stage 4 Tie-Breaker 15.00%
Stage 5 Intertripping 15.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 441 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 MCC Package Hand-over 10.00%

Progress is calculated based on UPS / Batteries and measured as


per following stages:
Stage Description WF for
UPS / Batteries Work Step stages
Stage 1 UPS 45.00%
Stage 2 Batteries 45.00%
Stage 3 MCC Package Hand-over 10.00%

Progress is calculated based on Electrical Panels (General) and


measured as per following stages:
Stage Description WF for
Electrical Panels (General) Work Step stages
Stage 1 Panels 90.00%
Stage 2
MCC Package Hand-over 10.00%

Progress is calculated based on Electrical cable and measured as


per following stages:
Stage Description WF for
Electrical Cables Work Step
stages
Stage 1 Tests & Megger tests 90.00%

Stage 2 MCC Package Hand-over 10.00%


Building Progress is calculated based on Building Pre-commissioning and
measured as per following stages:
Work Step
Building Pre-commissioning Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 442 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Civil & Secondary 10.00%
Stage 2 Power distribution/lighting 15.00%
Stage 3 F & G System 20.00%
Stage 4 Inergen 20.00%

Stage 5 HVAC System 25.00%


Stage 6 MCC Package Hand-over 10.00%
Pipeline
Progress is calculated based on Pigging & Drying and measured
as per following stages:
Stage Description WF for
Work Step stages
Pigging & Drying Stage 1
Pigging & Drying 90.00%

Stage 2
MCC Package Hand-over 10.00%

Progress is calculated based on MOV Valves- E/I connections


and measured as per following stages:
Stage Description WF for
MOV Valves- E/I connections Work Step stages
Stage 1 90.00%
MOV Valves- E/I connections
Stage 2 MCC Package Hand-over 10.00%
Equipment
Progress is calculated based on Static Equipment and measured
as per following stages:
Work Step
Static Equipment
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 443 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Cleaning / Inspection 45.00%
Stage 2 Box-up 45.00%
Stage 3 MCC Package Hand-over 10.00%
Progress is calculated based on Rotating Equipment and
measured as per following stages:
Stage Description WF for
stages
Rotating Equipment Work Step Stage 1 Chemical cleaning 10.00%
Stage 2 Reinstatement 25.00%
Stage 3 Final Alignment 15.00%
Stage 4 First Oil Filling 40.00%
Stage 5 Certificate 10.00%
Progress is calculated based on Compressors & Blowers and
measured as per following stages:
Stage Description WF for
Compressors & Blowers Work Step stages
Stage 1 Preparation works 25.00%
Stage 2 Pre-commissioning 65.00%
Stage 3
MCC Package Hand-over 10.00%

Progress is calculated based on Pumps motor no load test and


measured as per following stages:
Stage Description WF for
Pumps motor no load test Work Step
stages
Stage 1 Pre-commissioning 90.00%
Stage 2 MCC Package Hand-over 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 444 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Air coolers no load test and
measured as per following stages:
Stage Description WF for
Air coolers no load test Work Step stages
Stage 1 Pre-commissioning 90.00%

Stage 2 MCC Package Hand-over 10.00%

Progress is calculated based on Air coolers load test and


measured as per following stages:
Stage Description WF for
Air coolers load test Work Step
stages
Stage 1
Pre-commissioning 90.00%

Stage 2
MCC Package Hand-over 10.00%

Progress is calculated based on Refractory Dry out / Boil out /


inspection and measured as per following stages:
Stage Description WF for
stages
Refractory Dry out / Boil out / inspection Work Step Stage 1
Refractory Dry out / Boil out / inspection 75.00%

Stage 2 Final inspection 15.00%

Stage 3
MCC Package Hand-over 10.00%

Progress is calculated based on Catalyst loading and measured


Catalyst loading Work Step
as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 445 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stages Description WF for
stages
Stage 1
Catalyst loading 90.00%

Stage 2
MCC Package Hand-over 10.00%

Progress is calculated based on Steam Blowing and measured as


per following stages:
Stage Description WF for
stages
Steam Blowing Work Step Stage 1
Steam Blowing 90.00%

Stage 2
MCC Package Hand-over 10.00%

Progress is calculated based on Equipment Dossiers and


measured as per following stages:

Stage Description WF for


WP - 848 Equipment Dossiers (No. of Documents) Work Step
stages
Stage 1 Submission 65.00%

Stage 2 Approval 25.00%


Stage 3 Acceptance 10.00%

Progress is calculated based on QA/QC Documents and measured


WP - 849 QA/QC Documentation (No. of Documents) Work Step
as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 446 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Submission 65.00%

Stage 2 Approval 25.00%


Stage 3 Acceptance 10.00%

Progress is calculated based on Materials Documentation and


measured as per following stages:
Stage Description WF for
stages
WP - 850 Materials Documentation ( No. of Documents) Work Step Stage 1 Submission 65.00%

Stage 2 Approval 25.00%


Stage 3 Acceptance 10.00%

Progress is calculated based on Testing & Pre-Commissioning


Documentations and measured as per following stages:
Stage Description WF for
stages
Testing & Pre-Commissioning Documentations
WP - 851 (No. of Documents)
Work Step Stage 1 Submission 65.00%

Stage 2 Approval 25.00%

Stage 3 Acceptance 10.00%

Progress is calculated based on No. of documents and measured


WP - 852 Design Data ( No. of Documents ) Work Step
as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 447 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Submission 65.00%
Stage 2 Approval 25.00%
Stage 3 Acceptance 10.00%
Progress is calculated based on No. of documents and measured
as per following stages:
Stage Description WF for
stages
WP - 853 As-Built Drawings (No. of Documents) Work Step
Stage 1 Submission 65.00%

Stage 2 Approval 25.00%


Stage 3 Acceptance 10.00%

Progress is calculated based on Close out Report and measured as


per following stages:
Stage Description WF for
stages
WP - 854 Close out Report Work Step Stage 1 Submission 65.00%

Stage 2 Approval 25.00%

Stage 3 Acceptance 10.00%

Progress is calculated based on no of documents and measured


WP - 855 Ship loose Lists (No. Of Documents) Work Step
as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 448 of 456

Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Submission 65.00%
Stage 2 Approval 25.00%
Stage 3 Acceptance 10.00%

Progress is calculated based on As NDT Radiographic Films and


measured as per following stages:
Stage Description WF for
WP - 856 NDT Radiographic Films (No. of Documents) Work Step stages
Stage 1 Submission 65.00%
Stage 2 Approval 25.00%
Stage 3 Acceptance 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 449 of 456

APPENDIX 22: Downstream PMS- COMMISSIONING (D8)

Work Package No. WF% Description of Work Package Calculation Description, Detailed Weight Factor or Formula
Progress is calculated according to the shop Drawing list.
1001 M/H Work order and Shop Drawing Engineering
(Issued/Total)
Work
Description WF
Step
Step 1 Issue of Purchase Order 25%

Monthly manufacturing progress report


Procurement of Commissioning Step 2 approved by Supply Chain Management or 45%
1002 M/H Procurement
Materials PMT from P/O issue date until shipment
Step 3 Final Inspection and Release for Shipment 10%
Step 4 Delivery to SITE/ Warehouse 15%

Step 5 VENDOR'S FINAL DOCUMENTATION 5%


1003 Preparation Activities When it's done, the progress is 100%.
M/H Prefabrication
1004 Prefabrication When it's done, the progress is 100%.
10081 M/H Commissioning Each subsystem commissioning will be 100% when it is completed. Commissioning
10082 M/H Demobilization of Equipment When it's done, the progress is 100%. Demob. & Final
1010 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents) Doc.

M/H Pre-shut down Activities When it's done, the progress is 100%.
Pre/Shut/Post
M/H Shut Down Activities When it's done, the progress is 100%.
Down
M/H Post Shut Down Activities When it's done, the progress is 100%.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 450 of 456
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 451 of 456

APPENDIX 23: Downstream PMS- PROJECT CLOSURE

Control Account 1: Project Closure Report


Control
Weight
Account Description of Control Account Methodology Calculation Description, Detailed Weight Factor or Formula
Factor
No.
1- Physical progress shall be calculated by the milestone method which is
Obtain Formal Sign off and final finishing milestone, aforesaid item will be measured 100% and otherwise
Milestone
acceptance of the product progress is 0%.
2-WF shall be calculated based on the M/H
1- Physical progress shall be calculated by the milestone method which is
finishing milestone, aforesaid item will be measured 100% and otherwise
Update Project Records Milestone
progress is 0%.
2-WF shall be calculated based on the M/H
1- Physical progress shall be calculated by the milestone method which is
Make final payments and finishing milestone, aforesaid item will be measured 100% and otherwise
UA 50% Milestone
complete Cost records progress is 0%.
2-WF shall be calculated based on the M/H
1- Physical progress shall be calculated by the milestone method which is
Hand off the completed project finishing milestone, aforesaid item will be measured 100% and otherwise
Milestone
deliverables to Operations progress is 0%.
2-WF shall be calculated based on the M/H
1- Physical progress shall be calculated by the milestone method which is
Create and distribute a final finishing milestone, aforesaid item will be measured 100% and otherwise
Milestone
report of project performance progress is 0%.
2-WF shall be calculated based on the M/H
Control Account 2: Lessons Learned Documents
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 452 of 456

Control
Weight
Account Description of Control Account Methodology Calculation Description, Detailed Weight Factor or Formula
Factor
No.
Update corporate processes,
1-Progress is on and off and will be 100% after completion of the work
Procedures, and template based Milestone
2-WF shall be calculated based on the M/H
on the lessons learned
UB 50%
Gather and create final lessons 1-Progress is on and off and will be 100% after completion of the work
Milestone
learned 2-WF shall be calculated based on the M/H
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 453 of 456

Name Position Signature Date

Technical Shervin Specialist, 05th Dec.


Writer Karimianpour Planning & 14
Scheduling
03rd
Co-Writer Mohd Shahimi Project Controller Mar.15

SPECIFICATION DOCUMENT CHANGE RECORD

Reference
No PTS No. & Title Change Justification
Document
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 454 of 456

REVIEW CYCLE 1 (RC1) COMMENT SHEET


DISCIPLINARY REVIEW CYCLE

Name Position Signature Date

Reviewer 1

Reviewer 2

Recommended Writer’s Closeout


Review Findings Reference
Action Remark Status

REVIEW CYCLE 1 (RC1) ENDORSEMENT SHEET

Name Position Signature Date

Reviewer 1

Reviewer 2
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 455 of 456

REVIEW CYCLE 2 (RC2) COMMENT SHEET


INTER-DISCIPLINARY REVIEW

Name Position Signature Date

Reviewer 1

Reviewer 2

Recommended Writer’s Closeout


Review Findings Reference
Action Remark Status

REVIEW CYCLE 2 (RC2) ENDORSEMENT SHEET

Name Position Signature Date

Reviewer 1

Reviewer 2
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 456 of 456

REVIEW CYCLE 3 (RC3) COMMENT SHEET


3RD PARTY VERIFICATION

Name Position Signature Date


Reviewer 1

Reviewer 2

Recommended Writer’s Closeout


Review Findings Reference
Action Remark Status

REVIEW CYCLE 3 (RC3) ENDORSEMENT SHEET

Name Position Signature Date

Reviewer 1

Reviewer 2