PTG 19.80.04
May 2015
FOREWORD
PETRONAS Technical Guidelines (PTG) has been developed based on the accumulated knowledge,
experience, Lessons Learnt and Best Practices of the PETRONAS group supplementing PETRONAS
Technical Standards (PTS), National and International standards where appropriate. The key objective
of PTG is to guide the implementation of technical practices across the PETRONAS group.
Compliance to PTG should be adhered to across the Group. The PTG shall remain confidential within the
PETRONAS Group and shall not be issued to Contractors / Manufacturers / Suppliers. Issuance of PTG to
third parties shall be subjected to G-TA approval.
y
nl
In issuing and making the PTG available, PETRONAS is not making any warranty on the accuracy or
O
completeness of the information contained in PTG. The end-users shall ensure accuracy and
se
completeness of the PGT used for the intended application.
lU
PETRONAS is the sole copyright holder of PTG. No part of this document may be reproduced, stored in
na
a retrieval system or transmitted in any form or by any means (electronic, mechanical, recording or
otherwise) or be disclosed by users to any company or person whomsoever, without the prior written
er
consent of PETRONAS.
nt
-I
The PTG shall be used exclusively for the authorised purpose. The users shall arrange for PTG to be kept
in safe custody and shall ensure its secrecy is maintained and provide satisfactory information to
AS
Table of Contents
y
nl
3.0 PROGRESS MEASUREMENT METHODOLOGY.............................................................8
O
4.0 BIBLIOGRAPHY ....................................................................................................... 10
se
APPENDIX 1: Upstream PMS-WEIGHT FACTOR CALCULATION ............................................ 11
lU
APPENDIX 2: Upstream PMS- FEL 1 .................................................................................... 32
na
y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 5 of 456
1.0 INTRODUCTION
This PTS provides technical requirements in the development of Progress Measurement System
(PMS). The primary objective of this PTS is to provide the methodology in establishing the
progress base (weight factor), to measure and calculate the progress of the actual work done
for all project in PETRONAS.
1.1 SCOPE
This PTS specifies the requirement and methodology for developing the project weighting and
measuring system up to work package level required at various phases of the project from
project initiation to project close out. It provides an overview of the entire scope of
developing a weighting system and progress measuring methodology covering Overall, Phase,
Sub-Phase, Facility, Control account and work package Level. This PTS is intended to be used in
different types of projects.
y
nl
1.2 GLOSSARY OF TERM
O
1.2.1 General Definition of Terms & Abbreviations
se
Refer to PTS Requirements, General Definition of Terms, Abbreviations & Reading Guide PTS
lU
00.01.03 for General Definition of Terms & Abbreviations.
na
None.
nt
No Abbreviation Description
AS
11 PM Project Manager
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 6 of 456
No Abbreviation Description
y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 7 of 456
2.0 GENERAL
i. Milestones
ii. FEL 1 - Initiation
iii. FEL 2 - Scope Selection
iv. FEL3 – Scope Definition
v. Execution
All phases except Milestone are divided to contracting which includes contracting in house and
Contract No; this level will be referred as Level 2.
y
nl
Each of these phases is divided into different sub-phases, i.e. execution Phase includes 12 sub-
O
phases such as Detail Design, Procurement, Fabrication, Construction, HUC, etc. This level will
be referred as Level 3.
se
lU
These sub-phases are divided into facilities; this level will be referred as Level 4.
na
These facilities are divided into control account; this level will be referred as Level 5.
er
Control account with or without asset is broken down into work packages. Work packages level
nt
Finally, work packages are broken down into sub-work packages. Sub work packages level will
AS
i. The weightage of the entire project at different levels shall be calculated based on
TR
the Cost
ii. If any changes occur in the project, actual progress shall be calculated against whole
PE
work volume including all changes not only to measure Engineering, Procurement,
and Fabrication, HUC or drilling progress effectively but also to monitor remaining
work accurately. In case that the work quantity is increased or decreased from
original quantity due to the changes, weight value for each work item shall be
adjusted in proportion to the work quantity
iii. In case of re-work, the Actual physical progress shall be freeze at their latest
reported step and shall not be moved (forward or backward) until the progress has
again reached the correct progress
iv. Any changes in WBS, e.g. modification in the structure of WBS, the calculation of
weightages and progress measuring shall remain the same
v. All the budgets amounts in budget column are examples only
vi. Any missing item of this PMS shall be agreed with PMT
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 8 of 456
Activity Sub Work Package Work Package Control Account Facility Sub Phase
Contracting Phase Project
Start
Calculate Activity
y
nl
Progress
O
se
lU
Calculate Work Package
Progress
na
er
nt
Calculate Control
-I
Account Progress
AS
N
O
Calculate Facility
TR
Progress
PE
Calculate Contracting
Progress
Calculate Phase
Progress
Finish
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 9 of 456
For each level, there is a specific Weight Factor according to table below:
Sub
Work
Sub Control Work
Level Project Phase Contracting Facility Package
Phase Account Package
/
Activity
L1 L4
Weight Factor 100% L2 WF% L3 WF% L5 WF% L6 WF% L7 WF%
WF% WF%
Physical Overall
P1% P2% P3% P4% P5% P6% P7%
Progress %Complete Progress
y
The weightages for each level shall be calculated. For calculating the overall progress follows
nl
the steps as below:
O
se
lU
Sub Work
na
4.0 BIBLIOGRAPHY
y
nl
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 11 of 456
The physical progress for the overall project is obtained by summing up the physical weighted progress
of each phase:
FEL 1 – Initiation
FEL 2 – Scope Selection
FEL 3 – Scope Definition
Execution
The corresponding weight factors are determined initially in accordance with the respective cost values,
as defined by the project cost breakdown structure.
y
For calculating the Level 1 Weight Factor (L1 WF) for each phase follows these steps:
nl
O
1. Find the project total budget. In this example the total is RM1,000,000
2. Find the budget of each phase
se
3. To calculate the phase weight factor use this formula:
lU
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑃ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1) = × 100%
na
𝑃𝑟𝑜𝑗𝑒𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
er
Example:
nt
-I
𝑅𝑀 45,000
𝐹𝐸𝐸𝐷 𝑊𝐹 (𝐿1) = × 100% = 4.5%
𝑅𝑀 1,000,000
AS
Budget
N
Level 1 Weight
No. Phase
O
Project Management
Project Management is broken down in 10 sub phases. For calculating Level 2 Weight Factor (L2 WF):
Example:
𝑅𝑀 4,500
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 18%
𝑅𝑀 25,000
y
nl
4. (L1 WF) for sub phase/discipline is its share portion at Project level rather than its parent level
O
WF (i.e. Phase) it can be calculated.
se
(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
lU
𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 (𝑑𝑖𝑠𝑐𝑖𝑝𝑙𝑖𝑛𝑒) 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
na
Example:
er
(18% × 2.5%)
nt
Budget Budget
Phase (L1 WF)% Sub-Phase / Discipline (L2 WF)% (L1 WF)%
(RM '000) (RM '000)
N
Project
25000 2.5
O
Management
TR
Engineering
FEED 1750 7 0.18
Detail Engineering 3000 12 0.3
Procurement PCSB
2000 8 0.2
Supplied Materials
Fabrication 3750 15 0.38
Installation 1500 6 0.15
HUC 1750 7 0.18
Drilling 3250 13 0.33
Project Closure 2500 10 0.25
Initiation
Initiation is broken down to two contracts. Same as phase level each contract has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. For calculating Level 2 Weight Factor (L2WF):
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
y
𝑅𝑀 10,000
nl
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 100.00%
𝑅𝑀 10,000
O
se
Phase Budget (RM '000) (L1 WF)%
lU
Contracting Budget (RM '000) (L2 WF)% (L1 WF)%
na
Initiation 10,000 1 - - - -
er
nt
For in house services there are some sub phases. Same as Phase level each sub-phase has its own budget
N
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
O
their own weight factor. Contract No.1 is broken up in 4 sub-phases. For calculating Level 3 Weight
TR
1. Find the Contract total budget. In this example the Total for contract in house is RM 10,000
and for In house service is RM 10,000
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 2,000
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 20.00%
𝑅𝑀 10,000
4. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 14 of 456
(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(20% × 100%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿2 𝑊𝐹) = = 20.00%
100%
5. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(20% × 1%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿1 𝑊𝐹) = = 0.20%
y
100%
nl
O
Budget (L3WF)
Contracting Budget (RM '000) (L2 WF)% Sub-Phase / Discipline (L2 WF)% (L1 WF)%
se
(RM '000) %
Conceptual
2000 20.00 20.00 0.20
Development
nt
Petroleum
3000 30.00 30.00 0.30
AS
Economics
Feasibility Studies 3500 35.00 35.00 0.35
N
1. Find the Sub phase total budget. In this example the Total for facilities feasibility studies is
RM 3,500.
2. Find the budget of each Control Account.
3. To calculate the Control account weight factor use this formula:
Example:
𝑅𝑀 350
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100% = 10%
𝑅𝑀 3,500
4. (L3 WF) for control account is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 15 of 456
(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(10% × 35%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙(𝐿3 𝑊𝐹) = = 3.5%
100%
5. (L2 WF) for control account is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(10% × 35%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 (𝐿2𝑊𝐹) = = 3.5%
y
100%
nl
O
6. (L1 WF) for control account is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
se
lU
(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
na
Example:
er
(10% × 0.35%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 (𝐿1 𝑊𝐹) = = 0.04 %
nt
100%
-I
AS
Budget
Budget (L3 Control (L3WF)
Sub-Phase (RM (L5WF)% (L2 WF)% (L1 WF)%
(RM '000) WF)% Account %
'000)
N
O
Facilities
TR
Facility 21 21 0.20
2100 60.00
Assessment
Total 3,500 100.00 35.00 35.00 0.35
1. Find the control account total budget. In this example the Total for general is RM 350.
2. Find the budget of each work package.
3. To calculate the work packages weight factor use this formula:
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 16 of 456
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡
Example:
272
Preliminary Concept Development 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100 = 40 %
350
4. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%
y
Example:
nl
O
(40% × 10%)
Preliminary Concept Development(𝐿5 𝑊𝐹) = =4%
100%
se
5. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
lU
(i.e. Phase) It can be calculated.
na
(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
er
100%
nt
Example:
-I
(40% × 3.50%)
AS
6. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
O
(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
PE
Example:
(40% × 3.5%)
Preliminary Concept Development (𝐿2 𝑊𝐹) = = 1.40 %
100%
7. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(40% × 0.04%)
Preliminary Concept Development(𝐿1 𝑊𝐹) = = 0.01 %
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 17 of 456
y
Conceptual Engineering Services
nl
O
Conceptual Engineering Services is broken down to two contracts. Same as phase level each contract
has its own budget (accessible from budget estimation from cost control/finance dept.) and accordingly
se
each of them has their own weight factor. For calculating Level 2 Weight Factor (L2WF):
lU
1. Find the phase budget. In this example the total is RM 20,000
na
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
-I
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
AS
Example:
N
𝑅𝑀 3,000
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑆𝑒𝑟𝑣𝑖𝑐𝑒𝑠 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 15.00%
O
𝑅𝑀 20,000
TR
𝑅𝑀 17,000
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 85.00%
PE
𝑅𝑀 20,000
4. (L1 WF) for sub phase/discipline is its share portion at Project level rather than its parent level
WF (i.e. Phase) it can be calculated.
(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 (𝑑𝑖𝑠𝑐𝑖𝑝𝑙𝑖𝑛𝑒) 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(85% × 2%)
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 (𝐿1 𝑊𝐹) = = 1.70%
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 18 of 456
Conceptual
Engineering 20,000 2 - - - -
Services
In House 3,000 15.00 0.30
For each contract there are some sub phases. Same as Phase level each sub-phase has its own budget
y
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
nl
their own weight factor. Contract No.1 is broken up in 4 sub-phases. For calculating Level 3 Weight
O
Factor (L3 WF):
se
1. Find the Contract total budget. In this example the Total for contract No.1 is RM 17,000 and
lU
for In house service is RM 3,000
2. Find the budget of each Sub phase.
na
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
-I
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
AS
Example:
N
𝑅𝑀5,950
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 35.00%
O
𝑅𝑀 17,000
TR
4. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
PE
(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(35% × 1.7%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿1 𝑊𝐹) = = 0.60%
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 19 of 456
y
4.25 0.09
Bid/Evaluate/Award 850 5.00
nl
O
21.25 0.43
Sub surface Modeling 4250 25.00
se
Conceptual 29.75 0.60
5950 35.00
Development
lU
Appraisal/Learning 25.50 0.51
5100 30.00
na
well drilling
Total 17,000 100.00 85.00 1.70
er
nt
For calculating Level 4 Weight Factor (L4 WF): Only Applicable in WBS for Appraisal /Learning
AS
Well Drilling
N
1. Find the sub phase total budget. In this example the Total budget for Appraisal/Learning
O
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝐵𝑢𝑑𝑔𝑒𝑡
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿4𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 5,100
𝑂𝑓𝑓𝑠ℎ𝑜𝑟𝑒 𝐷𝑟𝑖𝑙𝑙𝑖𝑛𝑔 𝑊𝐹 (𝐿4𝑊𝐹) = × 100% = 100%
𝑅𝑀 5,100
4. (L3 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿4𝑊𝐹 × 𝐿3𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 20 of 456
Example:
(100% × 30.0%)
𝑂𝑓𝑓𝑠ℎ𝑜𝑟𝑒 𝐷𝑟𝑖𝑙𝑖𝑛𝑔 (𝐿3 𝑊𝐹) = = 30.00 %
100%
5. (L2 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿4𝑊𝐹 × 𝐿2𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(100% × 25.50%)
𝑂𝑓𝑓𝑠ℎ𝑜𝑟𝑒 𝐷𝑟𝑖𝑙𝑙𝑖𝑛𝑔 (𝐿2𝑊𝐹) = = 25.50 %
y
100%
nl
O
6. (L1 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
se
lU
(𝐿4𝑊𝐹 × 𝐿1𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿1 𝑊𝐹) =
na
100%
er
Example:
nt
-I
(100% × 0.51%)
𝑂𝑓𝑓𝑠ℎ𝑜𝑟𝑒 𝐷𝑟𝑖𝑙𝑙𝑖𝑛𝑔 (𝐿1 𝑊𝐹) = = 0.51 %
100%
AS
N
O
TR
Budget Budget
Sub-Phase (L3 WF)% Facility (L4WF)% (L3WF)% (L2 WF)% (L1 WF)%
(RM '000) (RM '000)
PE
Appraisal 5,100 30
Offshore
5,100 100.00 30.00 25.50 0.51
Drilling
Onshore
0 0.00 0.00 0.00 0.00
Drilling
Total 5,100 100.00 30.00 25.50 0.51
1. Find the Sub phase or Facility total budget. In this example the Total for concept select is RM
1,500.
2. Find the budget of each Control Account.
3. To calculate the Control account weight factor use this formula:
Example:
𝑅𝑀 300
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿5 𝑊𝐹) = × 100% = 20%
𝑅𝑀 1,500
4. (L3 WF) for control account is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(20% × 50%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠(𝐿3 𝑊𝐹) = = 10%
100%
5. (L2 WF) for control account is its share portion at Project level rather than its parent level WF
y
nl
(i.e. Phase) It can be calculated.
O
(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
se
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
lU
Example:
na
(20% × 7.50%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿2𝑊𝐹) = = 1.5%
100%
er
nt
6. (L1 WF) for control account is its share portion at Project level rather than its parent level WF
-I
(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
N
O
Example:
TR
(20% × 0.15%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿1 𝑊𝐹) = = 0.03 %
100%
PE
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 22 of 456
Budget Budget
Control (L5WF) (L3WF)
Sub-Phase (RM (L3 WF)% (RM (L2 WF)% (L1 WF)%
Account % %
'000) '000)
y
Design
nl
Petroleum 12.50 1.87 0.04
O
375 25.00
Economics
se
Total 1,500 100.00 50.00 7.50 0.15
lU
na
1. Find the control account total budget. In this example the Total for general is RM 150.
nt
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100%
N
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡
O
Example:
TR
37.5
PE
4. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%
Example:
(25% × 10%)
Project Risk Analysis (𝐿5 𝑊𝐹) = = 2.5 %
100%
5. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 23 of 456
(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(25% × 5%)
Project Risk Analysis (𝐿3 𝑊𝐹) = = 1.25%
100%
6. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
y
nl
Example:
O
(25% × 0.76%)
Project Risk Analysis (𝐿2 𝑊𝐹) = = 0.19 %
se
lU 100%
7. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
na
er
(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
nt
100%
-I
Example:
AS
(25% × 0.01%)
Project Risk Analysis(𝐿1 𝑊𝐹) = = 0.0025 %
N
100%
O
TR
PMT
Deliverable
150 10
Project Risk 37.5 25.00 2.5 1.25 0.19 0.0025
Analysis
37.5 25.00 2.5 1.25 0.19 0.0025
QRA
FEED
All Level weight factors for FEED will be calculated same as Conceptual design services and Execution
phase.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 24 of 456
EXECUTION
For Execution phase there are two contracts. Same as phase level each contract has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. For calculating Level 2 Weight Factor (L2WF):
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
y
nl
𝑅𝑀 210,000
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑆𝑒𝑟𝑣𝑖𝑐𝑒𝑠 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 23.33%
O
𝑅𝑀 900,000
se
𝑅𝑀 595,000
𝐸𝑃𝐶𝐼𝐶 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 66.11%
𝑅𝑀 900,000
lU
𝑅𝑀 95,000
na
4. (L1 WF) for contracting is its share portion at Project level rather than its parent level WF (i.e.
nt
(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
N
O
Example:
TR
(66.11% × 90%)
𝐸𝑃𝐶𝐼𝐶 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 (𝐿1 𝑊𝐹) = = 59.5%
PE
100%
Budget
Phase (L1 WF)% Sub-Phase / Discipline Budget (RM '000) (L2 WF)% (L1 WF)%
(RM '000)
Execution 900,000 90 - - - -
For each contract there are some sub phases. Same as Phase level each sub-phase has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. EPCIC Package is broken up in 7 sub-phases. For calculating Level 3 Weight
Factor (L3 WF):
1. Find the Contract total budget. In this example the Total for contract No.1 is RM 595,000 and
for contract No.2 is RM 95,000
2. Find the budget of each Sub phase.
3. To calculate the Sub phase weight factor use this formula:
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
y
𝑅𝑀 47,000
nl
𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑎𝑡𝑖𝑜𝑛 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 7.9%
𝑅𝑀 595,000
O
se
4. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated lU
(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
na
100%
er
Example:
nt
(7.9% × 66.11%)
-I
5. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
N
(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
PE
100%
Example:
(7.9% × 59.5%)
𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑎𝑡𝑖𝑜𝑛 (𝐿1 𝑊𝐹) = = 4.7%
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 26 of 456
Budget
Contracting (L2 WF)% Sub-Phase / Discipline Budget (RM '000) (L3WF)% (L2 WF)% (L1 WF)%
(RM '000)
y
nl
O
Budget Budget
Contracting (L2WF)% Sub-Phase / Discipline (L3WF)% (L2 WF)% (L1 WF)%
(RM '000) (RM '000)
se
Drilling 95,000 10.56 lU
Drilling 90,000 94.74 10.00 9.00
Contract Closure
na
For each sub-phase there are facility, Control account and work packages. Same as Phase level and Sub-
AS
phase, each facility has its own budget (accessible from budget estimation from cost control, finance
and contract dept.) and accordingly each of them has their own weight factor. In this example
N
1. Find the Sub phase total budget. In this example the Total for Fabrication is RM 272,000.
2. Find the budget of each facility.
3. To calculate the facility weight factor use this formula:
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝐵𝑢𝑑𝑔𝑒𝑡
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿4 𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 190,400
𝑊𝐻𝑃 𝑊𝐹 (𝐿4 𝑊𝐹) = × 100% = 70%
𝑅𝑀 272,000
4. (L3 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 27 of 456
(𝐿4𝑊𝐹 × 𝐿3𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(70% × 45.71%)
𝑊𝐻𝑃 (𝐿3 𝑊𝐹) = = 32 %
100%
5. (L2 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿4𝑊𝐹 × 𝐿2𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
y
Example:
nl
O
(70% × 30.22%)
𝑊𝐻𝑃 (𝐿2𝑊𝐹) = = 21.15 %
100%
se
lU
6. (L1 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
na
er
(𝐿4𝑊𝐹 × 𝐿1𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿1 𝑊𝐹) =
nt
100%
-I
Example:
AS
(70% × 27.2%)
𝑊𝐻𝑃 (𝐿1 𝑊𝐹) = = 19.04 %
N
100%
O
TR
PE
For each facility there are Control accounts. Same as Phase level and Sub-phase each control accounts
has its own budget (accessible from budget estimation from cost control, finance and Contract dept.)
and accordingly each of them has their own weight factor. In this example WHP is broken up in 7 control
accounts.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 28 of 456
1. Find the facility total budget. In this example the Total for WHP is RM 190,400.
2. Find the budget of each control account.
3. To calculate the control account weight factor use this formula:
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100%
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦
Example:
135,400
𝐹𝑎𝑏𝑟𝑖𝑐𝑎𝑡𝑖𝑜𝑛 𝑌𝑎𝑟𝑑 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100 = 71.11 %
190,400
y
4. (L4 WF) for Control Account is its share portion at Project level rather than its parent level
nl
WF (i.e. Phase) It can be calculated.
O
se
(𝐿5𝑊𝐹 × 𝐿4𝑊𝐹)
𝑊𝐹 (𝐿4 𝑊𝐹) =
lU
100%
na
Example:
er
(71.11% × 70%)
nt
5. (L3 WF) for Control Account is its share portion at Project level rather than its parent level
AS
(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
TR
100%
PE
Example:
(71.11% × 32%)
𝐹𝑎𝑏𝑟𝑖𝑐𝑎𝑡𝑖𝑜𝑛 𝑌𝑎𝑟𝑑 (𝐿3 𝑊𝐹) = = 22.76 %
100%
6. (L2 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(71.11% × 21.15%)
𝐹𝑎𝑏𝑟𝑖𝑐𝑎𝑡𝑖𝑜𝑛 𝑌𝑎𝑟𝑑 (𝐿2 𝑊𝐹) = = 15.04 %
100%
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 29 of 456
7. (L1 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(71.11% × 19.04%)
𝐹𝑎𝑏𝑟𝑖𝑐𝑎𝑡𝑖𝑜𝑛 𝑌𝑎𝑟𝑑 (𝐿1 𝑊𝐹) = = 13.54 %
100%
y
WHP 190,400 70
nl
Front End
O
Activities/Mob 4,500 2.36 1.65 0.76 0.50 0.45
ilization
se
Preparation 4,500 2.36
lU 1.65 0.76 0.50 0.45
Engineering
10,000 5.25 3.68 1.68 1.11 1.00
/Shop Drawing
na
Yard
135,400 71.11 49.78 22.76 15.04 13.54
Fabrication
er
Pre
7,000 3.68 2.57 1.18 0.78 0.70
nt
commissioning
-I
Final
4,000 2.10 1.47 0.67 0.44 0.40
Documentation
N
For each control account there are work packages. Same as Phase level and Sub-phase, each work
PE
package has its own budget (accessible from budget estimation from cost control, finance and contract
dept.) and accordingly each of them has their own weight factor. In this example yard fabrication is
broken up in 8 work packages.
1. Find the control account or facility total budget. In this example the Total for Yard
Fabrication is RM 135,400.
2. Find the budget of each work package.
3. To calculate the work package weight factor use this formula:
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 30 of 456
67,700
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100% = 50 %
135,400
4. (L5 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%
Example:
(50% × 71.11%)
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 (𝐿5 𝑊𝐹) = = 35.56 %
100%
5. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
y
(i.e. Phase) It can be calculated.
nl
O
(𝐿6𝑊𝐹 × 𝐿4𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿4 𝑊𝐹) =
se
100%
lU
Example:
na
(50% × 49.78%)
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 (𝐿4 𝑊𝐹) = = 24.89 %
100%
er
nt
6. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
-I
(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
N
O
Example:
TR
(50% × 22.76%)
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 (𝐿3 𝑊𝐹) = = 11.38 %
PE
100%
7. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(50% × 15.04%)
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 (𝐿2 𝑊𝐹) = = 7.52 %
100%
8. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
PTG 19.80.04
May 2015
PROGRESS MEASUREMENT SYSTEM
Page 31 of 456
(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(50% × 13.54%)
𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑎𝑙 (𝐿1 𝑊𝐹) = = 6.77 %
100%
Budget
Control Work Budget (L6WF)% (L5WF)% (L4WF)% (L3WF)%
(RM (L5 WF)%
Packages (RM '000)
(L2 WF)% (L1 WF)%
Account
'000)
Yard
135,400 71.11
Fabrication
Structural 67,700 50 35.56 24.89 11.38 7.52 6.77
y
Piping 13,540 10 7.11 4.98 2.28 1.50 1.35
nl
Pipeline 13,160 9.72 6.91 4.84 2.21 1.46 1.32
O
Mechanical 23,000 16.99 12.08 8.46 3.87 2.55 2.30
se
Electrical 7,000 5.17
lU 3.68 2.57 1.18 0.78 0.70
Instrument 5,000 3.69 2.63 1.84 0.84 0.56 0.50
Blasting 4,500 3.32 2.36 1.65 0.76 0.50 0.45
na
Weight factor for Level 7 shall be calculated based on budgeted cost/man hour.
N
O
TR
PE
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 32 of 456
Weight
y
Sub
nl
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
O
Code.
Base
se
Progress of each pre-bidding item is calculated as per
lU
following stages:
na
WF for
Stages Description
Stages
er
nt
-I
Tender Plan & ITB Preparation
Stage 1 -If the Tender Plan is issued equal to 35%
AS
- A1 Man-Hour Pre-Bidding Work Step 100% otherwise 0%
N
O
Stage 2 Tender Plan Approval 15%
TR
PE
ITB
Stage 3 - If the ITB is issued equal to 100% 50%
otherwise 0%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 33 of 456
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
y
stages:
nl
WF for
O
Stages Description
Stages
se
RFQ
Stage 1 - If the Inquiry is issued equal to 10%
lU
Bidding/ 100% otherwise 0%
na
- A2 Man-Hour Evaluate/ Work Step TBE
Award Stage 2 - If the TBE is performed equal to 25%
er
100% otherwise 0%
nt
CBE
-I
Stage 3 -, If the CBE is performed equal to 25%
100% otherwise 0%
AS
PETRONAS Approval of Award
- If the vendor/contractor is selected
Stage 4 40%
N
and PO place equal to 100%
O
otherwise 0%
TR
Control Account:
Geoscience & Reservoir
PE
Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Step 1 Start 5.00%
Step 2 Finish 95.00%
y
nl
O
Milestone Description WF for
Evaluate
geological & stages
se
112 geophysical
Milestone
Step 1 Start 5.00%
interpretation
lU
Step 2 Finish 95.00%
na
Milestone Description WF for
er
stages
Reservoir initial Step 1 Start 5.00%
nt
113 Evaluation
Milestone
Step 2 Finish 95.00%
-I
AS
Milestone Description WF for
N Report resources stages
114 & production Milestone
Step 1 Start 5.00%
profiles
O
Step 2 Finish 95.00%
TR
Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base
Schedule &
BA 121 Man-Hour Budget Work Step Work Step Description WF for
Development stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 35 of 456
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Step 1 Schedule Baseline development 65.00%
Step 2 Cost Baseline Development 35.00%
y
nl
Work Step
O
Description WF for
Schedule Risk stages
se
122 Analysis
Work Step
Step 1 SRA session conducting 60.00%
lU
Step 2 SRA Report Issuance 40.00%
na
Deliverable Description WF for
stages
er
I. PCPP Compliance
nt
-I
1.1 Planning & Scheduling 67
Project Scope of Work and
AS
1.1.1 2.53
Objectives
3.79
N 1.1.2 Schedule Basis Memorandum (SBM)
O
Preparation of 1.1.3 3.79
123 PCPP
Deliverable Work Breakdown Structure (WBS)
TR
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
1.1.10 Progress S-Curve 2.53
1.1.11 2.53
y
Progress Measurement Format
nl
1.1.12 Resource Plan 2.53
O
1.1.13 Project Roadmap 1.26
se
1.1.14 Project Progress Report 1.26
1.1.15 Project Close-Out Report 1.26
lU
1.2 Cost Control 23
na
1.2.1 Cost Breakdown Structure (CBS) 0.88
1.2.2 2.65
er
Project Total Budget
1.2.3 7.08
nt
Work Program & Budget (WPB)
1.2.4 7.08
-I
Corporate Plan & Budget (CPB)
1.2.5 Approved For Expenditure 0.88
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Total Progress Achievement 100.00
y
Control Account: Project Management Initiation
nl
O
Weight
Work
Factor Description of
se
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
lU
Base
na
Work Step Description WF for
Project Risk stages
er
124 Man-Hour Analysis
Work Step
Step 1 PRA session conducting 60.00%
nt
Step 2 PRA Report Issuance 40.00%
-I
BB
AS
Work Step Description WF for
Project Charter stages
125 Man-Hour Work Step
N Development
Step 1 Prepared 90.00%
O
Step 2 Approved 10.00%
TR
Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base
Business Case
BC 126 Man-Hour Development
Milestone Milestone Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 38 of 456
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
1 Start 0.00%
2 Finish 100.00%
y
nl
O
Milestone Description WF for
Opportunity
127 Man-Hour Milestone stages
se
Framing
1 Start 0.00%
lU
2 Finish 100.00%
Control Account: Data Gathering
na
Weight
er
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
nt
Calculation Work Package
Code.
-I
Base
131 Man-Hour AS
Finalize
Milestone
Milestone Description WF for
N Economic stages
Assumption
O
1 Start 5.00%
TR
2 Finish 95.00%
CA
PE
2 Finish 95.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 39 of 456
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Control Account: Data Processing & Analysis
y
nl
Milestone Description WF for
O
133 Data Analysis Milestone stages
se
1 Start 5.00%
2 Finish 95.00%
lU
na
Milestone Description WF for
CB 134 Man-Hour Model Building Milestone stages
er
Step 1 Start 5.00%
nt
Step 2 Finish 95.00%
-I
Milestone Description WF for
AS
Develop
135 Economic Milestone stages
1 Start 5.00%
N Scenarios
O
2 Finish 95.00%
TR
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
y
Milestone Description WF for
nl
Make stages
O
137 Conclusion/ Milestone 1 Start 5.00%
Recommendation
se
2 Finish 95.00%
lU
Control Account: General
Weight
na
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
er
Calculation Work Package
Code.
Base
nt
-I
Milestone Description WF for
AS
Preliminary stages
141 Concept Milestone
N Development 1 Start 5.00%
2 Finish 95.00%
O
Man-
TR
DA
Hour
Milestone Description WF for
PE
Environment
Preliminary
stages
142 Assessment &
Work Step 1 Perform Assessment 60.00%
Report
2 Issue Final Report 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 41 of 456
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Control Account: HSE
y
Weight
Work
nl
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
O
Calculation Work Package
Code.
Base
se
lU
Milestone Description WF for
Man- Initial Health &
DB 143 Milestone stages
na
Hour Safety Evaluation
Step 1 Start 5.00%
er
Step 2 Finish 95.00%
nt
Control Account: Facility Assessment
-I
Weight
Work
Factor Description of
AS
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base
N
O
Data Gathering/
144 Milestone stages
Surveying
PE
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
146 Existing Facility Work Step Description WF for
& stages
y
Work Step
Infrastructure Step 1 Perform Assessment 60.00%
nl
Assessment Step 2 Issue Final Report 40.00%
O
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 43 of 456
y
Base
nl
O
Progress of each pre-bidding item is calculated as per
following stages:
se
lU
WF for
Stages Description
Stages
na
er
Tender Plan & ITB Preparation
nt
Stage 1 -If the Tender Plan is issued 35%
-I
equal to 100% otherwise 0%
AS
- B1 Man-Hour Pre-Bidding Work Step
N
Stage 2 Tender Plan Approval 15%
O
TR
PE
ITB
Stage 3 - If the ITB is issued equal to 50%
100% otherwise 0%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 44 of 456
Weight
Sub
Factor Description of Sub-
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Phase
Code.
y
Base
nl
O
Progress of each bidding item is calculated as per following
stages:
se
lU
WF for
Stages Description
Stages
na
RFQ
er
Stage 1 - If the Inquiry is issued equal to 10%
nt
100% otherwise 0%
-I
TBE
Bidding/ Evaluate/ Stage 2 - If the TBE is performed equal to 25%
AS
- B2 Man-Hour Work Step
Award 100% otherwise 0%
N
CBE-, If the CBE is performed
O
Stage 3 25%
equal to 100% otherwise 0%
TR
PE
Control Account : Geology, Geophysics, Reservoir Engineering, Product Technology, Petro physics
Weight
Work
Factor Description of Work
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Package
Code.
Base
y
nl
Work Step Description WF for
O
Data Gathering, load
211 and QC Issue Work Step stages
se
Identification Step 1 Data Gathering 50.00%
lU
Step 2 Issue identification Report 50.00%
na
Milestone Description WF for
er
Analysing Quantity , stages
212 Quality and Milestone
1 Start 5.00%
nt
Uncertainties
2 Finish 95.00%
-I
EA,EB,EC,ED,EE,EF,EG Man-Hour
AS
Work Step Description WF for
stages
N
213 TOR Definition Work Step Step 1 Prepared 90.00%
O
Step 2 Approved 10.00%
TR
PE
Control Account :
Petroleum Economics
Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
Base
y
nl
O
Milestone Description WF for
se
stages
215 Data Gathering Milestone 1 Start 5.00%
lU
na
2 Finish 95.00%
er
nt
Milestone Description WF for
-I
stages
AS
EF Man-Hour 1 Start 5.00%
Data Processing &
216 N Analysis
Milestone
2 Finish 95.00%
O
TR
stages
1 Start 5.00%
Develop Model &
217 Conclusion
Milestone
2 Finish 95.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 47 of 456
y
nl
O
Milestone Description WF for
221 Man-Hour Data Acquisition Milestone stages
se
1 Start 5.00%
lU
2 Finish 95.00%
na
Milestone Description WF for
er
stages
nt
222 Man-Hour Data Processing Milestone 1 Start 5.00%
-I
2 Finish 95.00%
AS
FA1
Milestone Description WF for
N
stages
O
Data
223 Man-Hour Interpretation/Analysis
Milestone 1 Start 5.00%
TR
2 Finish 95.00%
PE
2 Finish 95.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 48 of 456
y
nl
O
Milestone Description WF for
se
stages
225 Data Acquisition Milestone
1 Start 5.00%
lU
2 Finish 95.00%
na
WF for
er
Milestone Description
stages
226 Data Processing Milestone
nt
1 Start 5.00%
-I
2 Finish 95.00%
AS
FA2 Man-Hour
WF for
N
Data Milestone Description
stages
O
227 Interpretation/Analys Milestone
TR
is 1 Start 5.00%
2 Finish 95.00%
PE
WF for
Milestone Description
stages
228 Geological Modelling Work Step 1 2D/3D Static Model 90.00%
Resource Assessment of Modelled
2 Reservoir
10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 49 of 456
y
Base
nl
O
Milestone Description WF for
se
229 Data Acquisition Milestone stages
lU
1 Start 5.00%
2 Finish 95.00%
na
er
Man- Milestone Description WF for
FA3
Hour
nt
230 Data Processing Milestone stages
1 Start 5.00%
-I
2 Finish 95.00%
AS
Milestone Description WF for
stages
N Data
231 Interpretation/Analysis
Milestone
1 Start 5.00%
O
2 Finish 95.00%
TR
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base
y
Step 1 Start 5.00%
nl
Step 2 Finish 95.00%
O
se
lU
234 Interpretation/Analysis Milestone
Milestone Description WF for
na
stages
Step 1 Start 5.00%
er
Step 2 Finish 95.00%
nt
-I
Work Step Description WF for
AS
stages
Step 1 10.00%
Build Analytical Model
N
Step 2 20.00%
O
Streamline Simulation
Step 3 20.00%
TR
Build Simulation
235 Modelling Work Step Step 4 20.00%
Upscale Geological Model &
PE
y
nl
Milestone Description WF for
O
stages
Step 1 Start 5.00%
se
GA NA Man-Hour
lU
NA Milestone
Step 2 Finish 95.00%
na
er
nt
Control Account: Investigate Alternative Development Scenarios
-I
Weight
Work
AS
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
N
Base
O
TR
y
nl
Milestone Description WF for
O
GC NA Man-Hour NA Milestone stages
se
Step 1 Start 5.00%
Step 2 Finish 95.00%
lU
Control Account: Economic Evaluation
na
Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
er
Control Account Code. Package Methodology
Calculation Package Formula
nt
Code.
Base
-I
AS
Milestone Description WF for
GD NA Man-Hour N NA Milestone stages
Step 1 Start 5.00%
O
Step 2 Finish 95.00%
TR
Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
Base
y
Control Account Code. Package Methodology
Calculation Package Formula
nl
Code.
Base
O
se
Work Step Description WF for
lU
241 Man-Hour Project Risk Analysis Work Step stages
Step 1 PRA session conducting 60.00%
na
Step 2 PRA Report Issuance 40.00%
er
Work Step Description WF for
nt
stages
-I
Quantitative Risk Step 1 SRA session conducting 30.00%
242 Man-Hour Analysis
Work Step
AS
Step 2 SRA Report Issuance 20.00%
HA N Step 3 CRA session conducting 30.00%
Step 4 CRA Report Issuance 20.00%
O
Deliverabl Description WF for
TR
e stages
PE
I. PCPP Compliance
1.1.3 3.79
Work Breakdown Structure (WBS)
Organization Breakdown
1.1.4 3.79
Structure (OBS)
Project Management Team (PMT)
1.1.5 6.32
Manpower Plan
Project Execution Schedule
y
1.1.6 16.43
nl
(Baseline Schedule)
O
1.1.7 Quantitative Risk Analysis (QRA) 12.64
1.1.8 Critical Path 2.53
se
1.1.9 Progress Base 3.79
lU
1.1.10 Progress S-Curve 2.53
na
1.1.11 Progress Measurement Format 2.53
1.1.12 2.53
er
Resource Plan
1.1.13 1.26
nt
Project Roadmap
1.1.14 1.26
-I
Project Progress Report
1.1.15 Project Close-Out Report 1.26
AS
1.2
N Cost Control 23
1.2.1 Cost Breakdown Structure (CBS) 0.88
O
1.2.2 Project Total Budget 2.65
TR
y
nl
III PM Approval 5
O
3.1 PCPP Reviewed and Approved by 5.00
se
PM
lU
Total Progress Achievement 100.00
Work Step Description WF for
na
stages
er
Preliminary Overall Step 1 Completed 90.00%
244 Man-Hour Contracting Strategy
Work Step
nt
Step 2 Accepted 10.00%
-I
AS
Control Account: Facilities Conceptual Design & Selection
Weight
Work
N
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
O
Calculation Package Formula
Code.
TR
Base
Work Step Description WF for
PE
stages
245 Man-Hour General Work Step Step 1 Start 10%
HB Step 2 Issued for Information 80%
Step 3 Final Update 10%
Work Step Description WF for
246 Man-Hour Process Work Step
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 56 of 456
y
stages
nl
Stage 1 Start 10%
O
247 Man-Hour Mechanical Work Step
Stage 2 Issued for Review 50%
se
Stage 3 Issue for Approve 30%
lU
Stage 4 Approve for Feed 10%
Work Step Description WF for
na
stages
er
Stage 1 Start 10%
248 Man-Hour Instrumentation Work Step
nt
Stage 2 Issued for Review 50%
-I
Stage 3 Issue for Approve 30%
Stage 4 Approve for Feed 10%
AS
Work Step Description WF for
stages
N
Stage 1 Start 10%
O
249 Man-Hour Electrical Work Step Stage 2 Issued for Review 50%
TR
y
Stage 3 Issue for Approve 30%
nl
Stage 4 Approve for Feed 10%
O
Work Step Description WF for
se
stages
lU
Stage 1 Start 10%
252 Man-Hour Pipeline Work Step Stage 2 Issued for Review 50%
na
Stage 3 Issue for Approve 30%
er
Stage 4 Approve for Feed 10%
nt
Work Step Description WF for
stages
-I
Stage 1 Start 10%
AS
253 Man-Hour Subsea Work Step
Stage 2 Issued for Review 50%
Stage 3 Issue for Approve 30%
N
Stage 4 Approve for Feed 10%
O
TR
y
Step 3 Execution Cost
nl
Step 4 Final Report Cost
O
Work Step Description WF for
se
stages
Step 1
lU
Pre Bidding Cost
256 Cost Site Survey Work Step Step 2 Contract Award Cost
na
Step 3 Execution Cost
er
Step 4 Final Report Cost
nt
Work Step Description WF for
stages
-I
Step 1 Pre Bidding Cost
AS
257 Cost Pipeline Route Survey Work Step Step 2 Contract Award Cost
Step 3 Execution Cost
N
Step 4 Final Report Cost
O
Work Step Description WF for
TR
stages
Step 1
PE
Weight
Work
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
Code.
Base
Work Step Description WF for
stages
y
nl
Drilling Conceptual Step 1 Drilling Concept Selection 25%
259 Man-Hour Study
Work Step
O
Step 2 Conceptual Well Design 55%
se
Step 3 Geo-Mechanic Study 20%
Work Step Description WF for
lU
HD Well Completion stages
260 Man-Hour Work Step Step 1 Completed 90.00%
na
Conceptual Study
Step 2 Accepted 10.00%
er
Work Step Description WF for
nt
stages
261 Man-Hour Reservoir Engineering Work Step
-I
Step 1 Completed 90.00%
Step 2 Accepted 10.00%
AS
Control Account: Petroleum Economics N
Weight
Work
O
Factor Description of Work Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Package Formula
TR
Code.
Base
PE
2 Finish 95.00%
y
Code.
Base
nl
O
Refer to Drilling PMS
se
lU
na
er
nt
-I
AS
N
O
TR
PE
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 61 of 456
y
Code.
Base
nl
O
Progress of each pre-bidding item is calculated as per
following stages:
se
lU
WF for
Stages Description
Stages
na
Tender Plan & ITB Preparation
er
- C1 Man-Hour Pre-Bidding Work Step Stage 1 -If the Tender Plan is issued equal 35%
nt
to 100% otherwise 0%
-I
Stage 2 Tender Plan Approval 15%
AS
N ITB
Stage 3 - If the ITB is issued equal to 100% 50%
O
otherwise 0%
TR
Weight
Sub
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Phase Methodology
Calculation Sub-Phase Formula
Code.
Base
Bidding/ Evaluate/ Progress of each bidding item is calculated as per
- C2 Man-Hour Work Step
Award following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 62 of 456
WF for
Stages Description
Stages
RFQ
Stage 1 - If the Inquiry is issued equal to 10%
y
100% otherwise 0%
nl
TBE
O
Stage 2 - If the TBE is performed equal to 25%
se
100% otherwise 0%
lU
CBE
Stage 3 -, If the CBE is performed equal to 25%
na
100% otherwise 0%
PETRONAS Approval of Award
er
- If the vendor/contractor is
Stage 4 40%
nt
selected and PO place equal to
-I
100% otherwise 0%
AS
Control Account: General, Process, Structural, Mechanical, Piping, Electrical, Instrument and Telecommunication, Civil, Pipelines, Architecture, HSE (Fire
and Safety), HVAC, Others N
Work Weight
O
Packag Factor Description of Calculation Description, Detailed Weight Factor or
TR
y
nl
O
Work Description WF for
se
Step stages
Man- Step 1 SRA session conducting 30.00%
lU
KA NA NA Work Step
Hour Step 2 SRA Report Issuance 20.00%
na
Step 3 CRA session conducting 30.00%
er
Step 4 CRA Report Issuance 20.00%
nt
-I
Control Account: Economics
AS
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
N
Control Account Code. Package Methodology
Calculatio Work Package Formula
O
Code.
n Base
TR
Step stages
Man- Step 1 Run Economic Analysis 60.00%
KB NA NA Work Step
Hour
Step 2 Economic Report 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 64 of 456
y
nl
Work Description WF for
Step stages
O
Man-
KC NA NA Milestone Step 1 Start 5.00%
Hour
se
Step 2 Finish 95.00%
lU
Control Account: FDP
Weight
na
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
er
Calculatio Work Package Formula
Code.
n Base
nt
Work Description WF for
-I
Man- Step stages
KD NA NA Work Step Step 1 FDP Submission 60.00%
AS
Hour
N Step 2 FDP Approval 40.00%
Control Account: OCS
O
Weight
Work
TR
n Base
Work Description WF for
Step stages
Man- Step 1 OCS Submission 60.00%
KE NA NA Work Step
Hour
Step 2 OCS Approval 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 65 of 456
y
Step stages
nl
Man-
KF NA NA Work Step Step 1 Advance Funding Submission 60.00%
O
Hour
Step 2 Sanction Approval 40.00%
se
Control Account: PCPP Preparation
lU
Weight
Work
Factor Description of Work
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
na
Calculatio Package
Code.
n Base
er
nt
Deliver Description WF for
-I
able stages
I. PCPP Compliance
1.1.8 2.53
Critical Path
1.1.9 Progress Base 3.79
1.1.10 Progress S-Curve 2.53
1.1.11 Progress Measurement Format 2.53
y
1.1.12 Resource Plan 2.53
nl
1.26
O
1.1.13 Project Roadmap
1.1.14 Project Progress Report 1.26
se
1.1.15 Project Close-Out Report 1.26
lU
1.2 Cost Control 23
1.2.1
na
Cost Breakdown Structure (CBS) 0.88
1.2.2 Project Total Budget 2.65
er
1.2.3 Work Program & Budget (WPB) 7.08
nt
1.2.4 Corporate Plan & Budget (CPB) 7.08
-I
1.2.5 Approved For Expenditure 0.88
AS
1.2.6 Additional Budget (Budget Transfer 0.88
and Supplementary Budget)
N
1.2.7 Additional Budget Request 0.88
O
1.2.8 Change Order Register 0.88
TR
y
nl
O
Control Account: Preparing well # (1) program
se
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
lU
Control Account Code. Package Methodology
Calculatio Work Package Formula
Code.
n Base
na
Work Description WF for
er
Step stages
Step 1 Start 5.00%
nt
Step 2 Offset Wells Review 5.00%
-I
Step 3 Risk Analysis 5.00%
AS
Man-
LA NA NA Milestone Step 4 Preparation of Drilling Program 35.00%
Hour
Step 5 Preparation of AFE and equipment 10.00%
N
list
O
Step 6 Drilling Program Review by TPs 5.00%
TR
y
nl
O
Control Account: Conducting PTPR 01-Execution
se
Work Weight
Packag Factor Description of Calculation Description, Detailed Weight Factor or
lU
Control Account Code. Methodology
e Calculation Work Package Formula
Code. Base
na
Work Description WF for
er
Step stages
Step 1 Start 5.00%
nt
LC NA Man-Hour NA Milestone
Step 2 Finish 95.00%
-I
AS
N
O
TR
PE
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 69 of 456
FEED
Control Account JA: General
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
y
Progress of general procedures calculated as per following stages:
nl
O
WF for
Stages Description
Stages
se
Man-Hour All Type of documents Work Step Stage 1 Start 10%
lU
Stage 2 Issued for Information 80%
na
Stage 4 Final Update 10%
er
Control Account JB: Process
nt
-I
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
AS Progress of each PFD and P&ID are calculated as per following stages:
N
O
WF for
Stages Description
TR
Stages
y
WF for
Stages Description
nl
Stages
-Procedures
O
-Specification Stage 1 Start 10%
Man-Hour
se
-Work Scope Work Step Stage 2 Issue for Internal Discipline check 30%
-Design Basis
lU
Stage 3 Issued for Review 20%
na
Stage 4 Issued for Design 20%
er
Stage 5 Final Update 20%
nt
Progress of each general specs and reports are calculated as per following
-I
stages:
AS
WF for
Stages Description
N Stages
Stage 1 Start 10%
O
General Specs,
Man-Hour Work Step
TR
Man-Hour Drawings Work Step Progress of each drawings are calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 71 of 456
WF for
Stages Description
Stages
Stage 1 Start 10%
y
nl
Stage 3 Issued for Review 20%
O
Stage 4 Issue for Approve 20%
se
Stage 5 Issued for Detail Design 10%
lU
Stage 6 Final Update 10%
na
Control Account JD: Mechanical
er
nt
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
-I
Document
AS
Progress of each document is calculated as per following stages:
N
WF for
Stages Description
O
Stages
TR
y
nl
Control Account JE: Piping
O
se
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
lU
Progress of each document is calculated as per following stages:
na
WF for
er
Stages Description
Stages
nt
10%
Stage 1 Start
-I
Man-Hour Specification Work Step
40%
AS
Stage 2 Issued for Comment
30%
N Stage 3 Issued for Approval
O
20%
TR
Description of
PE
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
10%
Stage 1 Start
40%
Stage 2 Issued for Comment
30%
Stage 3 Issued for Approval
y
nl
20%
Stage 4 Issue for Detail Design
O
se
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
lU
Progress of each datasheet is calculated as per following stages:
na
WF for
er
Stages Description
Stages
nt
10%
Stage 1 Start
-I
Man-Hour Datasheets Work Step 40%
AS
Stage 2 Issued for Comment
30%
N
Stage 3 Issued for Approval
O
20%
TR
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of Plot Plan is calculated as per following stages:
WF for
Man-Hour Plot Plan Work Step Stages Description
Stages
10%
Stage 1 Start
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 74 of 456
30%
Stage 2 Issue for Internal Discipline Check
10%
Stage 3 Issued for Comment
30%
Stage 4 Issued for Approval
y
nl
20%
Stage 5 Issue for Detail Design
O
se
Control Account JF: Electrical
lU
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
na
Progress of each drawing is calculated as per following stages:
er
WF for
nt
Stages Description
Stages
-I
10%
Stage 1 Start
Man-Hour Drawings ASWork Step Stage 2 Issue for Internal Discipline check
30%
N
O
10%
Stage 3 Issued for Comment
TR
30%
Stage 4 Issued for Approval
PE
20%
Stage 5 Issue for Detail Design
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 75 of 456
WF for
Stages Description
Stages
y
10%
Stage 1 Start
nl
Man-Hour Specifications Work Step
O
40%
Stage 2 Issued for comment
se
30%
lU
Stage 3 Issued for Approval
20%
na
Stage 4 Issue for Detail Design
er
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
nt
-I
Progress of each document is calculated as per following stages:
WF for
AS
Stages Description
N Stages
10%
Stage 1 Start
O
Man-Hour Datasheets Work Step
40%
TR
30%
Stage 3 Issued for Approval
20%
Stage 4 Issue for Detail Design
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour Drawings Work Step Progress of each document is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 76 of 456
WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check
y
nl
10%
Stage 3 Issued for Inquiry
O
40%
se
Stage 4 Issued for Purchase
lU
10%
Stage 5 Final Update
na
Control Account JH: Civil
er
nt
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
-I
AS
Progress of each drawing is calculated as per following stages:
N WF for
Stages Description
O
Stages
10%
TR
Stage 1 Start
Man-Hour Installation Drawings Work Step
PE
30%
Stage 2 Issue for Internal Discipline check
10%
Stage 2 Issued for Comment
20%
Stage 3 Issued for Approval
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 77 of 456
20%
Stage 4 Issue for Detail Design
10%
Stage 5 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
y
Document
nl
O
Progress of each concrete structure is calculated as per following stages:
se
WF for
Stages Description
Stages
lU
10%
Stage 1 Start
na
30%
Stage 2 Issue for Internal Discipline check
er
nt
Man-Hour Concrete Structures Work Step 10%
Stage 3 Issued for Comment
-I
20%
Stage 4 Issued for Approval
AS
20%
Stage 5 Issue for Detail Design
N
10%
O
TR
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
10%
Stage 1 Start
40%
Stage 2 Issued for Comment
20%
Stage 3 Issued for Approval
y
nl
20%
Stage 4 Issue for Detail Design
O
10%
se
Stage 5 Final Update
lU
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
na
Progress of each calculation note is calculated as per following stages:
er
nt
WF for
Stages Description
Stages
-I
10%
Stage 1 Start
AS
Man-Hour Calculation Notes Work Step
80%
Stage 2 Issue for Information
N
O
10%
TR
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour Drawings Work Step Progress of each drawing is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 79 of 456
WF for
Stages Description
Stages
10%
Stage 1 Start
15%
Stage 2 Issued for Inter discipline check
y
nl
25%
Stage 3 Issued for Comment
O
20%
se
Stage 4 Issued for Approval
lU
20%
Stage 5 Issue for Detail Design
na
10%
Stage 6 Final Update
er
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
nt
Document
-I
Man-Hour Specifications Work Step Progress of each document is calculated as per following stages:
AS
WF for
Stages Description
Stages
N
10%
O
Stage 1 Start
TR
40%
Stage 2 Issued for comment
PE
30%
Stage 3 Issued for Approval
20%
Stage 4 Issue for Construction
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 80 of 456
WF for
Stages Description
Stages
10%
Stage 1 Start
y
Man-Hour MR Work Step
nl
40%
Stage 2 Issued for Inquiry
O
40%
se
Stage 3 Issued for Purchase
lU
10%
Stage 4 Final Update
na
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
er
nt
Progress of each document is calculated as per following stages:
-I
WF for
Stages Description
Stages
AS
Man-Hour Reports Work Step 10%
N Stage 1 Start
O
80%
Stage 2 Issued for Information
TR
10%
Stage 3 Final Update
PE
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour Drawings Work Step Progress of each drawing is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 81 of 456
WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check
y
nl
10%
Stage 3 Issued for Comment
O
20%
Stage 4 Issued for Approval
se
lU
Approved for Construction / Approved for Design / 20%
Stage 5
Approved for Bidding
na
10%
Stage 6 Final Update
er
Description of
nt
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
-I
Progress of each spec is calculated as per following stages:
AS
WF for
Stages Description
Stages
N
10%
O
Stage 1 Start
TR
30%
Stage 3 Issued for Approval
20%
Stage 5 Issue for Construction
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 82 of 456
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each MTO is calculated as per following stages:
WF for
Stages Description
Stages
Man-Hour MTO Work Step
Stage 1 Start 10%
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check
Man-Hour Drawings Work Step
10%
Stage 3 Issued for Comment
20%
Stage 4 Issued for Approval
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour Specifications Work Step
40%
Stage 2 Issued for comment
30%
Stage 3 Issued for Approval
20%
Stage 4 Issue for Construction
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour
Progress of each Material Requisition is calculated as per following stages:
MR Work Step
WF for
Stages Description
Stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 84 of 456
10%
Stage 1 Start
40%
Stage 2 Issued for Inquiry
40%
Stage 3 Issued for Purchase
10%
Stage 4 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour Procedures Work Step
50%
Stage 2 Issued for Review
20%
Stage 3 Issued for Construction
20%
Stage 4 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour Calculation Notes Work Step Progress of each calculation note is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 85 of 456
WF for
Stages Description
Stages
10%
Stage 1 Start
80%
Stage 2 Issue for Information
10%
Stage 3 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
10%
Stage 4 Final Update
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 87 of 456
PMT DELIVERABLES
Control
Weight Factor Description of
Account Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Base Control Account
No.
Work Step Description WF for Stages
1) For Level 1, 2, 3,
and 4 (Phase, Step 1 SRA session conducting 30%
Contracting, Sub
Schedule & Cost SRA Report Issuance
KA phase, and Facility) Work Step Step 2 20%
QRA
is Cost
Step 3 CRA session conducting 30%
OCS Approval
Step 2 40%
WF for
Stages Description
Stages
MR for Main
Man-Hour Work Step 10%
Items Stage 1 Start
40%
Stage 2 Issued for Inquiry
40%
Stage 3 Issued for Purchase
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 93 of 456
10%
Stage 4 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
WF for
Stages Description
Stages
10%
Man-Hour Specifications Work Step Stage 1 Start
40%
Stage 2 Issued for comment
30%
Stage 3 Issued for Approval
20%
Stage 4 Approve for Construction
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour Datasheets Work Step
40%
Stage 2 Issued for comment
30%
Stage 3 Issued for Approval
20%
Stage 4 Approve for Construction
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 94 of 456
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Man-Hour Drawings Work Step Stage 2 Issue for Internal Discipline check
10%
Stage 3 Issued for Inquiry
40%
Stage 4 Issued for Purchase
10%
Stage 5 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
WF for
Stages Description
Stages
Installation 10%
Man-Hour Work Step Stage 1 Start
Drawings
30%
Stage 2 Issue for Internal Discipline check
20%
Stage 2 Issued for Comment
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 95 of 456
10%
Stage 3 Issued for Approval
WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check
Concrete 10%
Man-Hour Work Step Stage 3 Issued for Comment
Structures
20%
Stage 4 Issued for Approval
Approved for Construction / Approved for Design / 20%
Stage 5
Approved for Bidding
10%
Stage 6 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Structural
Man-Hour Work Step Progress of each document is calculated as per following stages:
Steel
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 96 of 456
WF for
Stages Description
Stages
10%
Stage 1 Start
40%
Stage 2 Issued for Comment
20%
Stage 3 Issued for Approval
WF for
Stages Description
Stages
Calculation
Man-Hour Work Step 10%
Notes Stage 1 Start
80%
Stage 2 Issue for Information
10%
Stage 3 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour Drawings Work Step Progress of each drawing is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 97 of 456
WF for
Stages Description
Stages
10%
Stage 1 Start
40%
Stage 2 Issued for Comment
20%
Stage 3 Issued for Approval
Approved for Construction / Approved for Design / 20%
Stage 4
Approved for Bidding
10%
Stage 5 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
10%
Stage 1 Start
Man-Hour Specifications Work Step
40%
Stage 2 Issued for comment
30%
Stage 3 Issued for Approval
20%
Stage 4 Issue for Construction
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Man-Hour MR Work Step Progress of each material requisition is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 98 of 456
WF for
Stages Description
Stages
10%
Stage 1 Start
40%
Stage 2 Issued for Inquiry
40%
Stage 3 Issued for Purchase
10%
Stage 4 Final Update
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
80%
Stage 2 Issued for Information
10%
Stage 3 Final Update
WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Stage 2 Issue for Internal Discipline check
10%
Stage 3 Issued for Comment
20%
Stage 4 Issued for Approval
10%
Stage 6 Final Update
20%
Stage 5 Issue for Construction
WF for
Stages Description
Stages
10%
Stage 1 Start
30%
Man-Hour Drawings Work Step Stage 2 Issue for Internal Discipline check
10%
Stage 3 Issued for Comment
20%
Stage 4 Issued for Approval
Approved for Construction / Approved for Design / 20%
Stage 5
Approved for Bidding
10%
Stage 6 Final Update
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 101 of 456
10%
Stage 4 Final Update
WF for
Stages Description
Stages
Stage 1 Start 10%
Man-Hour Procedures Work Step
Stage 2 Issued for Review 50%
WF for
Stages Description
Stages
Man-Hour Calculation Notes Work Step
Stage 1 Start 10%
Man-Hour Drawings Work Step Progress of each drawing is calculated as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 103 of 456
WF for
Stages Description
Stages
Stage 1 Start 10%
WF for
Stages Description
Stages
WF for
Stages Description
Stages
Stage 1 Start 10%
Man-Hour MR Work Step
Stage 2 Issued for Inquiry 40%
WF for
Stages Description
Stages
Tender Plan
Stage 1 -as per each equipment, if the Tender Plan is issued 30%
411 10% Work Step equal to 100% otherwise 0%
Pre-Bidding
PIR
Stage 2 -as per each equipment, if the PIR is performed equal to 40%
100% otherwise 0%
ITB
Stage 3 -as per each equipment, if the ITB is issued equal to 30%
100% otherwise 0%
TBE
Stage 2 -as per each equipment, if the TBE is performed equal to 25%
100% otherwise 0%
CBE
Stage 3 -as per each equipment, if the CBE is performed equal 25%
to 100% otherwise 0%
WF for
Stages Description
Stages
Manufacturing & Delivery of
413 70% Work Step Engineering
Major Equipment
Stage 1 -If step is done the value would be 100 and if it hasn’t 7%
been done yet, it would be 0.
Procurement
Stage 2 - If step is done the value would be 100 and if it hasn’t 40%
been done yet, it would be 0.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 107 of 456
WF for
Stages Description
Stages
Tender Plan
Stage 1 -as per each equipment, if the Tender Plan is issued out 30%
411 10% Work Step to vendor/manufacturer equal to 100% otherwise 0%
Pre-Bidding
PIR
Stage 2 -as per each equipment, if the PIR is performed equal to 40%
100% otherwise 0%
ITB
Stage 3 -as per each equipment, if the ITB is issued equal to 30%
100% otherwise 0%
WF for
Stages Description
Bid/ Evaluate/ Award of Stages
412 20% Work Step
Contract
RFQ
Stage 1 -as per each equipment, if the Inquiry is issued equal to 10%
100% otherwise 0%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 109 of 456
WF for
Stages Description
Stages
FOB
Manufacturing & Delivery of Stage 1 - If step is done the value would be 100 and if it hasn’t 85%
413 70% Work Step been done yet, it would be 0.
Bulk Material
Delivered at Port
Stage 2 - If step is done the value would be 100 and if it hasn’t 10%
been done yet, it would be 0.
Delivered at Site
5%
Stage 3 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 110 of 456
WF for
Stages Description
Stages
RFQ
Stage 1 -as per each equipment, if the Inquiry is issued equal to 10%
100% otherwise 0%
CBE
Stage 3 -as per each equipment, if the CBE is performed equal 25%
to 100% otherwise 0%
WF for
Stages Description
Stages
Engineering
Stage 1 -If step is done the value would be 100 and if it hasn’t 7%
been done yet, it would be 0.
Procurement
Stage 2 - If step is done the value would be 100 and if it hasn’t 40%
been done yet, it would be 0.
Fabrication
30%
Manufacturing and Delivery of Stage 3 - If step is done the value would be 100 and if it hasn’t
613 80% Work Step been done yet, it would be 0.
Major Equipment
Final Testing (FAT)
5%
Stage 4 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
FOB
3%
Stage 5 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Site
13%
Stage 7 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Close out Report
2%
Stage 8 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 112 of 456
WF for
Stages Description
Stages
RFQ
-as per each equipment, if the Inquiry is issued equal to
Stage 1 10%
100% otherwise 0%
TBE
Bid/ Evaluate/ Award of -as per each equipment, if the TBE is performed equal to
612 20% Work Step Stage 2 25%
Contract 100% otherwise 0%
CBE
-as per each equipment, if the CBE is performed equal
Stage 3 25%
to 100% otherwise 0%
WF for
Stages Description
Stages
FOB
85.0%
Manufacturing & Delivery of Stage 1 - If step is done the value would be 100 and if it hasn’t
613 80% Work Step been done yet, it would be 0.
Bulk Material
Delivered at Port
10.0%
Stage 2 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Site
5.0%
Stage 3 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 114 of 456
Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
Jacket Structure , Buoyancy Tank,
Diaphragm Installation and Boat
Landing
WP-726 to W-
PD Fabrication Tubular - (Number of Dia Progress is calculated based on Fabrication of Tubular and measured as per
734
In per Tubular Size) following stages:
Work Step Description WF for stages
1. 8 in. and below (200mm and Below)
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 120 of 456
5. 58 in. - 80 in (1450mm - 2000mm) Step 4 NDT & Dimensional Report Acceptance 15.00%
Fabrication Structural Members – non-
Progress is calculated based on Fabrication of Structural members and
Tabular (Weld Length per Structural
measured as per following stages:
Member size)
Work Step Description WF for stages
Step 1 Mark & Cut 15.00%
Non-Tabular & Miscellaneous Step 2 Fit Up 40.00%
Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Rolling of Cans - Tubular - (Number of Dia In per Tubular Size)
Progress is calculated based on Rolling of cans and measured as per following
stages:
Work Step Description WF for stages
Rolling of Cans (No. of Plates
Step 1 Rolled 20.00%
required for Tubular)
Step 2 Fit Up 25.00%
Step 3 Welded 30.00%
Step 4 NDT or Acceptance 25.00%
Erection - (Number of Joints/Panels)
Progress is calculated based on Installation / Erection and measured as per
following stages:
Erection ( Number of Joint Panels) Work Step Description WF for stages
Step 1 Lift & Position 20.00%
Step 2 Fit Up 30.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 121 of 456
Progress is calculated based on Blast/ Painting & Coating and measured as per
following stages:
Work Step Description WF for stages
One Coat System (Area)
Step 1 Blasting 50.00%
Step 2 Final Coating 45.00%
Step 3 Acceptance 5.00%
WORK PACKAGE 5: Yard Fabrication - Topside A ( WHP, RISER & CPP,
Piping) Top Deck ,Main Deck, Mezzanine Deck & Cellar Deck
Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
Structural - Fabrication (Plate Girder/Nodes)
Fabrication Tubular - (Number of Dia Progress is calculated based on Fabrication of Tubular and measured as per
In per Tubular Size) following stages:
1. 8 in. and below (200mm and Below) Work Step Description WF for stages
2. 10 in. - 24 in (250mm - 400mm) Step 1 Mark & Cut 15.00%
3. 26 in. - 40 in (650mm - 1000mm) Step 2 Fit Up 40.00%
4. 42 in. - 56 in (1050mm - 1400mm) Step 3 Welding 30.00%
5. 58 in. - 80 in (1450mm - 2000mm) Step 4 NDT & Acceptance 15.00%
WP-726 to W-
734 Fabrication Structural Members -
Progress is calculated based on Fabrication of Structural members and
(Weld Length per Structural Member
measured as per following stages:
size)
1. W8 and Below Work Step Description WF for stages
2. W10 - W18 Step 1 Mark & Cut 15.00%
3. W21 - W27 Step 2 Fit Up 40.00%
4. W30 - W40 Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Erection - (Number of Joints/Panels)
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 125 of 456
Pipeline
Progress is calculated based on pipeline coating and measured as per following
Concrete stages:
Coating/External/Internal/Custom/Field Work Step Description WF for stages
Joint/Internal Field Joint Coating Step 1 Actual - No. of joints 90.00%
Step 2 Accepted- No of joints 10.00%
Mechanical (including Insulation)
Progress is calculated based on fabrication and measured as per following
stages:
Step 1 Mark & Cut 15.00%
Mechanical Equipment Support Step 2 Fit Up 40.00%
Step 3 Welding 30.00%
Step 4 NDT & Acceptance 15.00%
Progress is calculated based on Installation and measured as per following
stages:
Work Step Description WF for stages
Mechanical Equipment Installation Step 1 Lift Up & Placement of Equipment Deck 40.00%
Step 2 Levelling/Alignment 25.00%
Step 3 Tie Down /Bolt tightening 25.00%
Step 4 Acceptance 10.00%
Progress is calculated based on Installation and measured as per following
stages:
Vessel / Piping Insulation Work Step Description WF for stages
Step 1 Complete - No. of Runs / Meter Run 90.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 128 of 456
Siren Progress is calculated based on Siren and measured as per following stages:
Work Step Description WF for stages
Step 1 Support preparation 20.00%
Siren Installation Step 2 Loud speaker installation 40.00%
Step 3 Wiring 30.00%
Step 4 Checks 10.00%
Progress is calculated based on Radio Equipment by Antennae and measured as
Radio System
per following stages:
Work Step Description WF for stages
Step 1 Supports 20.00%
Radio Equipment by Antennae
Step 2 Installation/Connections 70.00%
Step 3 Tests / Checks 10.00%
Work Step Description WF for stages
Step 1 Laying 20.00%
Telecom Cable
Step 2 Terminations 70.00%
Step 3 Checks 10.00%
Progress is calculated based on Instrument Calibration and measured as per
Instrumentation Test
following stages:
Work Step Description WF for stages
Instrument Calibration
Step 1 Calibrate 100.00%
Progress is calculated based on Instrument Test and measured as per following
stages:
Loop Checking Work Step Description WF for stages
Step 1 Checks 100.00%
HVAC/Ducting
Progress is calculated based on Fabrication and measured as per following
HVAC Ducting Support/Hangers
stages:
Fabrication
Work Step Description WF for stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 134 of 456
Progress is calculated based on Blast/ Painting & Coating and measured as per
following stages:
Work Step Description WF for stages
One Coat System (Area) Step 1 Blasting 50.00%
Step 2 Final Coating 45.00%
Step 3 Acceptance 5.00%
Progress is calculated based on Blast/ Painting & Coating and measured as per
following stages:
Work Step Description WF for stages
Step 1 Blasting & Shop Prime 35.00%
Four Coat System (Area) Step 2 2nd Coating 20.00%
Step 3 3rd Coating 20.00%
Step 4 Final Coating 20.00%
Step 5 Line Identification / Acceptance 5.00%
Progress is calculated based on Blast/ Painting & Coating and measured as per
following stages:
Work Step Description WF for stages
Galvanized / CTE (Area) Step 1 Etching 45.00%
Step 2 Galvanizing 35.00%
Step 3 Line Identification / Acceptance 20.00%
WORK PACKAGE 7: Testing & Pre commissioning
Control
Work Package
Account Description of Work Package Calculation Description, Detailed Weight Factor or Formula
No.
No
Progress is calculated based on Pre-commissioning and measured as per
following stages:
PE WP - 735 Electrical Work Step Description WF for stages
Step 1 Power supply and checking 30.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 137 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Drilling/excavation 5.00%
Stage 2 Casing Installation 5.00%
Stage 3 Transport of Excavated material 15.00%
Stage 4 Reinforcement Installation 15.00%
Stage 5 Pouring 45.00%
Stage 6 Casing Recovery 10.00%
Stage 7 Integrity Test 5.00%
Infrastructures (Road, Railway, Drainage, etc.) Progress is subjected to Asphalt laying methods & Yards and
& Landscapes measured as per following stages:
Stage Description WF for
stages
Stage 1 Sub-base preparation 10.00%
Work Step Stage 2 Base rolling 5.00%
Asphalt roads and yards Stage 3 Quarry mix foundation 30.00%
Stage 4 Compacting and Stabilizing 25.00%
WP - 814 Stage 5 Binder 15.00%
Stage 6 Wear surface 10.00%
Stage 7 Misc. finishing 5.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
Earth roads and yards Work Step
stages
Stage 1 Ground preparation 10.00%
Stage 2 Foundation 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 146 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Crushed stones 30.00%
Stage 4 Rolling 10.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Trenching and measured as per
following stages:
Stage Description WF for
stages
Earth and Sand Trenches (Trenching) Work Step
Stage 1 Excavation 50.00%
Stage 2 Sand bed 10.00%
Stage 3 Sand filling 10.00%
Stage 4 Top Brick / Red lean concrete 20.00%
Stage 5 Sand filling 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Areas preparation 10.00%
Stage 2 Roads 60.00%
Stage 3 Fence 30.00%
Progress is calculated based on Work Shop and measured as per
following stages:
Stage Description WF for
Work Shop Work Step stages
Stage 1 Workshops - Building 40.00%
Stage 2 Workshops - Equipment & Facilities 60.00%
Progress is calculated based on Warehouse and measured as per
following stages:
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Fuel Station 10.00%
Stage 3 Parking, Roads & Fences 25.00%
Stage 4 Power Distribution Network 25.00%
Stage 5 Telecommunication Network 15.00%
Stage 6 Water Distribution Network 5.00%
Stage 7 Sewage Network 10.00%
Progress is calculated based on Facilities Demolition & Removal
and measured as per following stages:
Stage Description WF for
Facilities Demolition & Removal Work Step stages
Stage 1 Demolition & Removal 75.00%
Stage 2 Demobilization 25.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Mobilization and Demobilization for 51.17%
Construction Equipment for offshore Works
Stage 3 Mobilization and Demobilization for 7.51%
Construction Equipment for tie-in Works
Stage 4 Pre-commissioning, Commissioning & Hydro 29.79%
testing
Stage 5 Mobilization and Demobilization for 5.89%
Construction Equipment for Line laying
Works
Stage 6 Mobilization and Demobilization for 2.82%
Construction Equipment for other Works
Progress is calculated based on Onshore Logistic support for
pipeline and measured as per following stages:
Stage Description WF for
Sub Work of Onshore Logistic support (Pipeline) Work Step
stages
Stage 1 Logistic Support for Shore Approach 43.10%
Stage 2 Logistic Support for Laying Operations 56.90%
Progress is calculated based on Onshore / Offshore Logistic
support and measured as per following stages:
Sub Work of Mobilization Manual and
Work Step
Stage Description WF for
Demobilization Inspection Construction Equipment stages
Stage 1 Completion of mobilization of Equipment 50.00%
Stage 2 Demobilization of construction EQUIPMENT 50.00%
Progress is calculated based on Utilities & Facilities and measured
as per following stages:
Utilities & Facilities Work Step Stage Description WF for
stages
Stage 1 Water and Effluent Treatment 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 150 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Fuel Station 10.00%
Stage 3 Parking, Roads & Fences 25.00%
Stage 4 Power Distribution Network 25.00%
Stage 5 Telecommunication Network 15.00%
Stage 6 Water Distribution Network 5.00%
Stage 7 Sewage Network 10.00%
Progress is calculated based on Steel net fencing and measured
Site Preparation
as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Work Step Stage 3 10.00%
Formwork
Steel Net Fencing
Stage 4 Reinforcement 10.00%
Stage 5 Pouring 10.00%
WP - 818
Stage 6 Stripping/backfill 5.00%
Stage 7 Fencing installation 50.00%
Stage 8 Misc. finishing work 5.00%
Progress is calculated based on Pre-Fabricated Elements fencing
and measured as per following stages:
Stage Description WF for
Pre-Fabricated Elements fencing Work Step
stages
Stage 1 Complete - in Meter 90.00%
Stage 2 Acceptance - in Meter 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 151 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Gates and measured as per
following stages:
Stage Description WF for
Gates Work Step stages
Stage 1 Complete - No. of Gates 90.00%
Stage 2 Acceptance - No. of Gates 10.00%
Progress is calculated based on Removal of Trees and measured
Earth Works
as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Ground preparation 5.00%
Removal of Trees
Stage 2 Trees cutting 40.00%
Stage 3 Roots removal 35.00%
Stage 4 Transportation 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Ground Preparation 10.00%
Stage 2 Laying Materials/Compaction 70.00%
Stage 3 Final Rolling 20.00%
Progress is calculated based on Sheet piling and dewatering and
measured as per following stages:
Stage Description WF for
stages
Sheet piling and dewatering Work Step
Stage 1 Sheet piles driving 50.00%
Stage 2 Reinforcing beams 20.00%
Stage 3 Dewatering 20.00%
Stage 4 Sheet piles extraction 10.00%
Progress is calculated based on Soil scrubbing and measured as
per following stages:
Stage Description WF for
Soil scrubbing Work Step
stages
Stage 1 Scrubbing 80.00%
Stage 2 Final Grading 20.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
Earth Dykes Work Step stages
Stage 1 Excavation 10.00%
Stage 2 Dyke execution
65.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 153 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Slope profiling
15.00%
Stage 4 10.00%
Finishing work
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 9 Final/Backfill
5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 Wear surface 10.00%
Stage 7 Misc. finishing 5.00%
Progress is calculated based on Earth roads & Yards and
measured as per following stages:
Stage Description WF for
stages
Earth roads and yards Work Step Stage 1 Ground preparation 10.00%
Stage 2 Foundation 40.00%
Stage 3 Crushed stones 30.00%
Stage 4 Rolling 10.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Concrete paving and measured as
per following stages:
Stage Description WF for
Concrete Paving Work Step stages
Stage 1 Prep., slope setting, reinforcement 60.00%
Stage 2 Wire netting installation, pouring 25.00%
Stage 3 Finishing works 15.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
Concrete Cable Trenches Work Step stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 156 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping 5.00%
Stage 7 Sand bed 20.00%
Stage 8 Concrete covers 5.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Pulling Pits Work Step Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 25.00%
Stage 4 Formworks 15.00%
Stage 5 Pouring 35.00%
Stage 6 Formworks stripping & backfill 15.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on issued General Engineering
documents to the COMPANY and measured as per following
stages:
Stage Description WF for
WP - 819 General Work Step
stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 157 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Approval for Construction 40.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Approval for Construction 40.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on issued Other Engineering
documents to the COMPANY and measured as per following
stages:
Stage Description WF for
WP - 826 Other Engineering Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on Cast in situ driven piles and
Piling - Driven in place piles hammered
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Casing Installation 10.00%
Cast in Situ driven piles Stage 2 Reinforcing Installation 30.00%
Stage 3 Pouring 45.00%
Stage 4 Casing Recovery 10.00%
Stage 5 Integrity test 5.00%
WP - 813
Progress is calculated based on Concrete Pre-cuts driven piles
and measured as per following stages:
Stage Description WF for
Concrete Pre-cuts driven piles Work Step stages
Stage 1 Material at Site 20.00%
Stage 2 Installation 75.00%
Stage 3 Integrity test 5.00%
Progress is calculated based on Steel driven Piles and measured
Steel driven piles Work Step
as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 160 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Step 1 Material at Site 20.00%
Step 2 Installation 75.00%
Step 3 Integrity test 5.00%
Progress is calculated based on Wooden driven Piles and
measured as per following stages:
Stage Description WF for
Wooden driven piles Work Step stages
Stage 1 Material at Site 20.00%
Stage 2 Installation 75.00%
Stage 3 Integrity test 5.00%
CIVIL WORKS
Progress is calculated based on Concrete Foundation for
Concrete Works - Foundations
Equipment & Structural and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
WP - 827 Work Step
Stage 3 Reinforcement 25.00%
Concrete Foundation for Equipment & Structural
Stage 4 Formworks 20.00%
Stage 5 Anchor bolts/plates 10.00%
Stage 6 Concrete pouring 15.00%
Stage 7 Formworks stripping, concrete protection &
10.00%
backfill
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 161 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Grouting 10.00%
Progress is calculated based on Prefabrication of concrete
foundations and measured as per following stages:
Stage Description WF for
stages
Prefabrication of concrete foundations Work Step Stage 1 Reinforcement 25.00%
Stage 2 Formworks 20.00%
Stage 3 Anchor bolts/plates 20.00%
Stage 4 Concrete pouring 35.00%
Progress is calculated based on Precast of concrete foundations
installation and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Precast on of concrete foundations installation Work Step Stage 2 Lean concrete 5.00%
Stage 3 Foundation installation 55.00%
Stage 4 Concrete protection & backfill 10.00%
Stage 5 Grouting 10.00%
Stage 6 Finishing 15.00%
Progress is calculated based on Tanks Rings and measured as per
following stages:
Stage Description WF for
Tank Rings Work Step
stages
Stage 1 Excavation 10.00%
Stage 2 Lean concrete 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 162 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping, concrete protection &
15.00%
external backfill
Stage 7 Internal backfilling 10.00%
Progress is calculated based on Tanks Rings and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Surface preparation 10.00%
Concrete small foundations Work Step
Stage 2 Reinforcement/formworks 40.00%
Stage 3 Pouring 30.00%
Stage 4 Grouting 10.00%
Stage 5 Formworks stripping & finishing 10.00%
Progress is calculated based on concrete large massive
foundations and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Concrete large massive foundations Work Step Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 15.00%
Stage 5 Anchor bolts/plates 10.00%
Stage 6 Pouring 25.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 163 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Grouting 10.00%
Stage 8 Formworks stripping & backfill 10.00%
Progress is calculated based on Concrete elevated structures cast
Elevation Concrete
in situ l and measured as per following stages:
Stage Description WF for
stages
Stage 1 Formworks 25.00%
Work Step Stage 2 Reinforcement 25.00%
Concrete elevated structures cast in situ
Stage 3 Anchor bolts/plates 15.00%
Stage 4 Pouring 20.00%
Stage 5 Formworks stripping 10.00%
Stage 6 Finishing works 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Grouting on footings 10.00%
Stage 3 Lengthwise beams installation 20.00%
Stage 4 Transverse beams installation 20.00%
Step 5 Beams grouting 10.00%
Step 6 Finishing works 10.00%
Progress is calculated based on Concrete paving and measured as
Concrete Paving / Roads / Yards
per following stages:
Stage Description WF for
Work Step stages
Concrete Paving Stage 1 Prep., slope setting, reinforcement 60.00%
Stage 2 Wire netting installation, pouring 25.00%
Stage 3 Finishing works 15.00%
U/G civil works ( pits, duct banks, cable Progress is calculated based on Concrete cable trenches and
trenches ) measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Work Step
Stage 3 Reinforcement 20.00%
Concrete cable trenches
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping 5.00%
Stage 7 Sand bed 20.00%
Stage 8 Concrete covers 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 165 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Pulling Pits and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Puling Pits Work Step
Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 25.00%
Stage 5 Pouring 30.00%
Stage 6 Formworks stripping & backfill 15.00%
Progress is calculated based on Duct Banks and measured as per
following stages:
Stage Description WF for
Duct Banks Work Step stages
Stage 1 Excavation 20.00%
Stage 2 PVC conduit positioning 40.00%
Stage 3 Concrete pouring 40.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Lighting poles foundations (cast in
situ) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Lighting poles foundations (cast in situ) Work Step Stage 3 Reinforcement 20.00%
Stage 4 Formworks 15.00%
Stage 5 Anchor Bolt/J-bolt 15.00%
Stage 6 Pouring 20.00%
Stage 7 Formworks stripping 5.00%
Stage 8 Backfilling 5.00%
Stage 9 Grouting 10.00%
Progress is calculated based on cast in situ sleepers and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Backfill 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Joints sealing 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Finishing works 15.00%
Progress is calculated based on Fire proofing for equipment skirts
and measured as per following stages:
Stage Description WF for
Fire proofing for equipment skirts Work Step stages
Stage 1 Welded wire mesh installation 20.00%
Stage 2 Pouring 60.00%
Stage 3 Finishing works 20.00%
Progress is calculated based on Fire proofing for steel structures
and measured as per following stages:
Stage Description WF for
stages
Stage 1 Surface cleaning 5.00%
Fire proofing for steel structures Work Step Stage 2 Supports installation 10.00%
Stage 3 Reinforcement 5.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring /application 30.00%
Stage 6 Formworks stripping 20.00%
Stage 7 Finishing works 10.00%
BUILDINGS Progress is calculated based on subs-station and measured as per
Concrete & Masonry Buildings following stages:
Stage Description WF for
Work Step stages
Substation Stage 1 Concrete foundations 30.00%
Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 170 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on control room and measured as
per following stages:
Stage Description WF for
stages
Control room Work Step Stage 1 Concrete foundations 30.00%
Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Other buildings and measured as
per following stages:
Stage Description WF for
stages
Other buildings
Work Step Stage 1 Concrete foundations 30.00%
(administration, laboratory, canteen ...)
Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Curtain and partition walls and
Building Secondary Works measured as per following stages:
Work Step
Stage Description WF for
stages
Curtain and partition walls
Stage 1 Material at site 10.00%
Stage 2 Hollow block 30.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 171 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Internal plastering 25.00%
Stage 4 Internal painting 25.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Doors & windows and measured
as per following stages:
Stage Description WF for
Doors & windows Work Step stages
Stage 1 Material at site 10.00%
Stage 2 Windows / doors installation 45.00%
Stage 3 Accessories installation 45.00%
Progress is calculated based on Flooring and measured as per
following stages:
Stage Description WF for
stages
Flooring Work Step
Stage 1 Material at site 20.00%
Stage 2 Installation 70.00%
Stage 3 Finishing & cleaning 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Cleaning 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Tests 10.00%
Progress is calculated based on HVAC system and partition walls
HVAC
and measured as per following stages:
Work Description WF for
Step stages
Stage 1
Support Fabrication and Installation 7.00%
Stage 3
Work Step Equipment installation 20.00%
HVAC system
Stage 4 Piping installation 20.00%
Stage 6
Instrument installation 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 Functional checks 5.00%
Progress is calculated based on Lightning system and measured
as per following stages:
Stage Description WF for
Lightning system Work Step
stages
Stage 1 Equipment installation 90.00%
Stage 2 Checks 10.00%
Progress is calculated based on Communication / security
systems and measured as per following stages:
Stage Description WF for
stages
Communication / security systems Work Step Stage 1 Material at site 10.00%
Stage 2 Equipment installation 30.00%
Stage 3 Cable pulling & Connections 50.00%
Stage 4 Functional checks 10.00%
Progress is calculated based on Fire detection and partition walls
Fire detection / fighting
and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Material at site 10.00%
Fire detection
Stage 2 Equipment installation 30.00%
Stage 3 Cable pulling & Connections 50.00%
Stage 4 Functional checks 10.00%
Progress is calculated based on Fire detection and partition walls
and measured as per following stages:
Fire fighting system Work Step
Stage Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 175 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Material at site 5.00%
Stage 2 Piping prefabrication & install. 35.00%
Stage 3 Piping painting 20.00%
Stage 4 Sprinkler installation 20.00%
Stage 5 Functional test 20.00%
STORAGE TANKS AND SILOS Progress is calculated based on Fixed roof tanks (altern.I) and
Steel Tanks - Fixed Roof Tanks measured as per following stages:
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Base 17.00%
Stage 2 Shell 35.00%
Stage 3 Floating plate 25.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Cleaning, testing 10.00%
Progress is calculated based on Double Wall tanks and measured
Cryogenic Tank
as per following stages:
Stage Description WF for
stages
Stage 1 Base 17.00%
Work Step Stage 2 Inner shell (nickel) 28.00%
Double wall tanks
Stage 3 Outer shell (carbon steel) 20.00%
Stage 4 Roof 28.00%
Stage 5 Accessories 3.00%
Stage 6 Testing 4.00%
Progress is calculated based on other tanks and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Bottom Plates 17.00%
Other Tanks Work Step Stage 2 Shell Plates 28.00%
Stage 3 Roof & Cover 20.00%
Stage 4 Accessories & Others 3.00%
Stage 5 Hydro test 3.00%
Stage 6 Painting 4.00%
Hoisting and Equipment (Mechanical) Progress is calculated based on Heavy vessels w fixed lifting and
Erection measured as per following stages:
WP 829 Work Step Stage Description WF for
Heavy Vessels with fixed lifting and assembly stages
Stage 1 Erection on Foundation 60.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 178 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Levelling, plumb adjustment 5.00%
Stage 3 Pneumatic & Hydrostatic testing 25.00%
Stage 4 Final inspect., Manholes closure 10.00%
Progress is calculated based on Heavy vessels w fixed cranage
and measured as per following stages:
Stage Description WF for
Vessels parts lifting and assembly stages
Stage 1 Shell assembly & welding 40.00%
Stage 2 Tracing & Welding of Nozzles and
10.00%
Manholes
Work Step
Stage 3 Tray support installation 5.00%
Stage 4 X-ray examination 5.00%
Stage 5 Installation 20.00%
Stage 6 Circum, welding & x-ray exam 5.00%
Stage 7 Plumb adjustment 5.00%
Stage 8 Final hydrostatic testing 10.00%
FIRE EQUIPMENT ERECTION Progress is calculated based on Heavy vessels w fixed cranage
Furnaces and measured as per following stages:
Stage Description WF for
Work Step stages
Preassembled Furnaces
Stage 1 Erection on Foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt
30.00%
tightening
Stage 3 Final inspect., Manholes closure 20.00%
Progress is calculated based on Heavy vessels w fixed cranage
and measured as per following stages:
Partially preassembled Furnaces Work Step
Stage Description WF for
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 179 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Shell assembly & welding/bolting 20.00%
Stage 2 Refractory panels/mater, erect 15.00%
Stage 3 Coils welding & erection 20.00%
Stage 4 Installation on foundation 10.00%
Stage 5 Stack and Flue ducts weld/bolt 15.00%
Stage 6 Accessories & Structures erect. 10.00%
Stage 7 X-ray examination 8.00%
Stage 8 Final alignment & Final inspection 2.00%
Progress is calculated based on Preassembled boilers and
measured as per following stages:
Stage Description WF for
Preassembled boilers Work Step stages
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Partially preassembled boilers
and measured as per following stages:
Stage Description WF for
stages
Stage 1 Shell assembly & welding/bolting 20.00%
Partially preassembled boilers Work Step Stage 2 Refractory panels/mater erect. 15.00%
Stage 3 Coils welding & erection 20.00%
Stage 4 Installation on foundation 10.00%
Stage 5 Stack and flue ducts weld./bolt. 15.00%
Stage 6 Accessories & structures erect. 10.00%
Stage 7 X-ray examination 8.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 180 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Final alignment final inspection 2.00%
Progress is calculated based on Flares and measured as per
following stages:
Stage Description WF for
stages
Flares Work Step Stage 1 Structure Erection 50.00%
Stage 2 Riser Pipe 20.00%
Stage 3 Alignment 10.00%
Stage 4 Accessories 10.00%
Stage 5 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Belt conveyors and measured as
Machinery ( Not Require for Alignment)
per following stages:
Stage Description WF for
stages
Stage 1 Frames installation 30.00%
Stage 2 Rollers installation 15.00%
Belt conveyors Stage 3 Belt installation 15.00%
Stage 4 Belt joint execution 10.00%
Stage 5 Accessories 10.00%
Stage 6 Counterweight 10.00%
Stage 7 Final check 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Levelling, bolt tightening 10.00%
Stage 3 Prelim. alignment with motor 25.00%
Stage 4 Cold alignment with piping 30.00%
Stage 5 Final inspection 5.00%
Stage 6 Cleaning, maintenance 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Cleaning of cylinder suction valves 10.00%
Stage 8 Final alignment, final inspection 15.00%
Progress is calculated based on Centrifugal compressors and drive
and measured as per following stages:
Stage Description WF for
stages
Centrifugal compressors and drive Work Step Stage 1 Installation on foundation 20.00%
Stage 2 Levelling, bolt tightening 15.00%
Stage 3 Motor installation 10.00%
Stage 4 Prelim. cylinder installation 15.00%
Stage 5 Utility line installation 15.00%
Stage 6 Cleaning of cylinder suction valves 5.00%
Stage 7 Final alignment, final inspection 15.00%
Stage 8 Maintenance 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Tray Installation and measured
Tray Installation
as per following stages:
Stage Description WF for
stages
Stage 1 Transport to jobsite 10.00%
Trays
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Distributors, grids, demisters, etc.
and measured as per following stages:
Stage Description WF for
stages
Distributors, grids, demisters, etc. Work Step Stage 1 Transport to jobsite 10.00%
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Inert Packing and measured as
Filling materials ( catalyst & packing )
per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Transport to jobsite 10.00%
Inert Packing
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Chemicals, desiccant, catalysts
Chemicals, desiccant, catalysts Work Step
and measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 185 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Transport to jobsite 10.00%
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Air coolers erection and
Air Coolers & Cooling Towers
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Ground Structure Pre-Assembly 40.00%
Air Cooler Erection Stage 2 Structure & Bundles erection 10.00%
Stage 3 Fans & Motors Installation 20.00%
Stage 4 Alignment 20.00%
Stage 5 Final Inspection 10.00%
Progress is calculated based on Package and Miscellaneous
Package and Miscellaneous Erection Erection and measured as per following stages:
Stage Description WF for
stages
Stage 1 Installation on foundation 30.00%
Work Step
Stage 2 Assembling of skids/equipment 20.00%
Skid mounted packages
Stage 3 Disassembled parts erection 20.00%
Stage 4 Levelling, bolt tightening 15.00%
Stage 5 Tot skid/package level, bolt tighten. 10.00%
Stage 6 Final inspection 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 186 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Items in one piece and measured
Heavy Lift
as per following stages:
Stage Description WF for
Work Step stages
Items in one piece Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Items in several pieces ( typical
for 3 pieces) and measured as per following stages:
Items in several pieces
Work Step Stage Description WF for
( typical for 3 pieces)
stages
Stage 1 1st Part Erection on foundation 10.00%
Stage 2 2nd Part Erection on foundation 10.00%
Stage 3 Welding & X-ray examination 20.00%
Stage 4 3rd Part Erection on foundation 10.00%
Stage 5 Welding & X-ray examination 20.00%
Stage 6 Levelling, plumb adjustment, bolt tightening 10.00%
Stage 7 Final inspect., manholes closure 20.00%
Progress is calculated based on Vertical vessels/exchangers (shop
Static Equipment
assembled) and measured as per following stages:
Stage Description WF for
Work Step stages
Vertical vessels/exchangers (shop assembled) Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 187 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Horiz. vessels/exchangers (shop assembled) Work Step Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Vert. vessels/exch. (shop
assemble.) with testing and measured as per following stages:
Stage Description WF for
stages
Vert. vessels/exch. (shop assemble.) with testing Work Step
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Testing 20.00%
Stage 4 Final inspect., manholes closure 10.00%
Progress is calculated based on Horiz. vessels/exch. (shop
assemble.) with testing and measured as per following stages:
Stage Description WF for
stages
Horiz. vessels/exch. (shop assemble.) with testing Work Step
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Testing 20.00%
Stage 4 Final inspect., manholes closure 10.00%
STEEL STRUCTURE Progress is calculated based on Trestle structures and measured
Main Structural Steel Erection as per following stages:
WP-830 Work Step Stage Description WF for
Trestle structures stages
Stage 1 Assembly 20.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 188 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Erection 33.00%
Stage 3 Alignment 14.00%
Stage 4 Welding and/or bolting 26.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 3.00%
Progress is calculated based on Process structures and measured
as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 19.00%
Process structures Work Step Stage 2 Erection 37.00%
Stage 3 Alignment 13.00%
Stage 4 Welding and/or bolting 25.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 2.00%
Progress is calculated based on Pipe racks and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Assembly 21.00%
Pipe racks Work Step
Stage 2 Erection 22.00%
Stage 3 Alignment 14.00%
Stage 4 Welding and/or bolting 36.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 3.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 189 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Steel Frames and measured as
per following stages:
Stage Description WF for
stages
Steel frames on concrete structures Work Step Stage 1 Erection 40.00%
Stage 2 Alignment 20.00%
Stage 3 Welding and/or bolting 25.00%
Stage 4 Cleaning 5.00%
Stage 5 Final check 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Adjustment 20.00%
Stage 4 Securing 20.00%
Stage 5 Painting/Touch up 5.00%
Stage 6 Final check 5.00%
Progress is calculated based on Gratings and measured as per
following stages:
Stage Description WF for
stages
Checkered plates Work Step
Stage 1 Erection 43.00%
Stage 2 Securing 36.00%
Stage 3 Cleaning 14.00%
Stage 4 Check 7.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Assembly 23.00%
Stage 2 Erection 23.00%
Stage 3 Alignment 16.00%
Stage 4 Welding and/or bolting 30.00%
Stage 5 Cleaning 5.00%
Stage 6 Final check 3.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 Final check 3.00%
Progress is calculated based on Ladders & Handrails and
CLADDING
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 15.00%
Stage 2 Thermal sheet erection 25.00%
Work Step Stage 3 Thermal sheet fastening 10.00%
Siding and roofing
Stage 4 External sheet erection 20.00%
Stage 5 External sheet bolting/fixing 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Sectioning 25.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Breathers pipe drains 10.00%
Stage 6 X-ray examination, stress relieving hydro test 10.00%
Stage 7 Hydro test 13.00%
Stage 8
Finishing works, Final Check 2.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Anchor blocks 20.00%
Stage 4 Backfiring 20.00%
Stage 5 Finishing 20.00%
Progress is calculated based on underground Piping on site
Fabrication and erection and measured as per following stages:
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on underground Piping on site
Fabrication and erection and measured as per following stages:
Stage Description WF for
stages
Underground piping off site Stage 1 Material Preparation, select & transport 5.00%
Work Step
Stage 2 Pipe fabrication, erection 35.00%
Stage 3 X-ray examination 25.00%
Stage 4 Testing 10.00%
Stage 5 Bitumizing of welded parts 10.00%
Stage 6 Final check 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Excavation 10.00%
Stage 2 Lean concrete 15.00%
Stage 3 Pipe installation 45.00%
Stage 4 Joint sealing 5.00%
Stage 5 Testing 5.00%
Stage 6 Sand covering 10.00%
Stage 7 Backfilling 10.00%
Progress is calculated based on Plastic GRP on site Fabrication
Plastic, GRP and erection and measured as per following stages:
Others
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Excavation 10.00%
Stage 2 Lean concrete 10.00%
Stage 3 Pipe installation 45.00%
Stage 4 Joints sealing 10.00%
Stage 5 Testing 5.00%
Stage 6 Sand covering 10.00%
Stage 7 Backfilling 10.00%
Progress is calculated based on Demolition and measured as per
Demolition
following stages:
Stage Description WF for
Work Step stages
Demolitions Stage 1 Ground Preparation 5.00%
Stage 2 Concrete/Masonry demolition 65.00%
Stage 3 Transportation 30.00%
Progress is calculated based on Steel tubing installation and
Steam Tracing
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Tracer installation 40.00%
Steel tubing installation Stage 2 Pre-insulated tubing installation 40.00%
Stage 3 Trays and supports for tubing 10.00%
Stage 4 Test 5.00%
Stage 5 Final check 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Tracer installation 40.00%
Stage 2 Trays and supports for tubing 25.00%
Stage 3 Pre-insulated tubing installation 25.00%
Stage 4 Test 5.00%
Stage 5 Final check 5.00%
Progress is calculated based on Control valve erection and
Miscellaneous / Accessories- Piping
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Valve erection 80.00%
Control valve erection Stage 2 Bolting 10.00%
Stage 3 Final check 10.00%
Progress is calculated based on Safety valve erection and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection for piping alignment 40.00%
Safety valve erection Work Step Stage 2 Valve dismantling for test 20.00%
Stage 3 Bolting 35.00%
Stage 4 Final check 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Sectioning 35.00%
Stage 2 Assembly, spot welding 25.00%
Stage 3 Welding 35.00%
Stage 4 Transport to storage area 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Inspection and tests 10.00%
Progress is calculated based on Grounding bars and erection and
measured as per following stages:
Stage Description WF for
stages
Grounding bars Work Step Stage 1 Bar installation 30.00%
Stage 2 Stub-up and concrete base 30.00%
Stage 3 Connection execution 30.00%
Stage 4 Tests 8.00%
Stage 5 Final inspection 2.00%
Progress is calculated based on Overhead copper conduits
installation and erection and measured as per following stages:
Stage Description WF for
Overhead copper conduits installation Work Step stages
Stage 1 Fittings installation 10.00%
Stage 2 Cord laying and fixing 85.00%
Stage 3 Final inspection 5.00%
Progress is calculated based on Connections of equip to the
grounding network and erection and measured as per following
stages:
Stage Description WF for
Connections of equip to the grounding network Work Step stages
Stage 1 Connection execution 90.00%
Stage 2 Protective paint 8.00%
Stage 3 Final inspection 2.00%
Progress is calculated based on Installation of plates (earthing
Installation of plates (earthing bus) Work Step
bus) and erection and measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 202 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Plate prefabrication 30.00%
Stage 2 Plate installation 60.00%
Stage 3 Protective paint 5.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Lightning protection system and
erection and measured as per following stages:
Stage Description WF for
stages
Lightning protection system Work Step
Stage 1 Steel plate installation 60.00%
Stage 2 Rods installation 20.00%
Stage 3 Execution of connections 10.00%
Stage 4 Inspection and tests 10.00%
Sub-Station Installation Progress is calculated based on Transformers and measured as
Transformer per following stages:
Stage Description WF for
stages
Stage 1 Transportation and alignment 20.00%
Work Step
Stage 2 Mechanical connections 5.00%
Transformers
Stage 3 Transformer electrical connection 25.00%
Stage 4 Panel electrical connection 30.00%
Stage 5 Tests 10.00%
Stage 6 Final inspection 10.00%
Progress is calculated based on MCC / Switchgears installation
Electrical Equipment Work Step
and measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 203 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Preparation 20.00%
MCC / Switchgears installation Stage 2 Installation 70.00%
Stage 3 Tests / Checks 10.00%
Progress is calculated based on Bus duct installation and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Supports prefabrication 20.00%
Bus duct installation Work Step
Stage 2 Supports installation 30.00%
Stage 3 Bus duct installation 40.00%
Stage 4 Final Alignment 10.00%
Progress is calculated based on Batteries installation and
measured as per following stages:
Stage Description WF for
stages
Batteries installation Work Step
Stage 1 Supports installation 20.00%
Stage 2 Installation 30.00%
Stage 3 Acid Filling 30.00%
Stage 4 Tests / Checks 20.00%
Progress is calculated based on Diesel generators and
measured as per following stages:
Stage Description WF for
Diesel generator Work Step
stages
Stage 1 Erection on foundation 30.00%
Stage 2 Electrical Connections 40.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 204 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Testing 20.00%
Stage 4 Finals inspect. 10.00%
Progress is calculated based on Cable trays and cable ladder
Cable trays in S/S
installation and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Check of tray layout 10.00%
Cable trays and cable ladder installation
Stage 2 Installation of supports 35.00%
Stage 3 Installation of trays 50.00%
Stage 4 Sealing of conduit entering cable room 5.00%
Interconnecting cables connections Progress is calculated based on Interconnecting cables
connection and measured as per following stages:
Stage Description WF for
Work Step
Installation of Interconnecting cables stages
Stage 1 Laying 80.00%
Stage 2 Checks 20.00%
Progress is calculated based on Interconnecting cables
connection and measured as per following stages:
Stage Description WF for
Connection of Interconnecting cables Work Step stages
Stage 1 Terminations 70.00%
Stage 2 Testing 20.00%
Stage 3 Checks 10.00%
ELECTRICAL CABLES
Progress is calculated based on Cable trays and cable ladder
Cable trays and conduits Work Step
installation and measured as per following stages:
Cable trays/ladders installation
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 205 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Prefabrication of supports 20.00%
Stage 2 Installation of supports 32.00%
Stage 3 Installation of trays 39.00%
Stage 4 Grounding of trays 4.00%
Stage 5 Installation of covers 5.00%
Progress is calculated based on Underground conduits
installation and measured as per following stages:
Stage Description WF for
stages
Underground conduits installation
Work Step Stage 1 Placing supports 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit and stub up 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Progress is calculated based on Above ground conduits
installation and measured as per following stages:
Stage Description WF for
stages
Above ground conduits installation Stage 1 Supports installation 15.00%
Work Step
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 206 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on U/G cables and measured as per
Cable pulling
following stages:
Stage Description WF for
stages
Stage 1 Stub up & concrete base 5.00%
Work Step Stage 2 Handling of cable drums 5.00%
U/G cables Stage 3 Laying of cables 65.00%
Stage 4 Cable markers installation 10.00%
Stage 5 Insulation test 10.00%
Stage 6 Cable way markers 4.00%
Stage 7 Final inspection 1.00%
Progress is calculated based on Cables in trays/ladders and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Handling of cable drums 5.00%
Cables in trays/ladders Work Step
Stage 2 Laying of cables 70.00%
Stage 3 Insulation test 10.00%
Stage 4 Markers installation 10.00%
Stage 5 Final inspection 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Conduit cleaning 5.00%
Stage 3 Cable pulling 65.00%
Stage 4 Insulation test 10.00%
Stage 5 Markers installation 10.00%
Step 6 Final inspection 5.00%
Control station installation Progress is calculated based on Control station industrial type
and measured as per following stages:
Stage Description WF for
Work Step stages
Control station Ex type Stage 1 Installation 80.00%
Stage 2 Checks 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Control station industrial type
Power outlets installation
and measured as per following stages:
Stage Description WF for
Work Step stages
Power outlet Ex type Stage 1 Installation 80.00%
Stage 2
Checks 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Checks 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Lighting Installation and
measured as per following stages:
Stage Description WF for
stages
Lighting Installation Work Step Stage 1 Installation of local panels 20.00%
Stage 2 Installation of main junction boxes 20.00%
Stage 3 Install/ connection of lighting fixtures 40.00%
Stage 4 Tests/Checks 20.00%
INSTRUMENT & TELECOMS WORK Progress is calculated based on Panels/marshalling cabinets and
Control Room Installation Works measured as per following stages:
Stage Description WF for
Work Step stages
Panels/marshalling cabinets Stage 1 Preparation 20.00%
Stage 2 Installation 70.00%
Stage 3 Tests / Checks 10.00%
Progress is calculated based on Cable trays in technical/control
rooms and erection and measured as per following stages:
WP-833 Stage Description WF for
Cable trays in technical/control rooms
Work Step
stages
Stage 1 Supports 40.00%
Stage 2 Installation 50.00%
Stage 3 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Laying 80.00%
Stage 2 Checks 20.00%
Progress is calculated based on Interconnecting cables
connections and erection and measured as per following stages:
Stage Description WF for
Interconnecting cables connections
Work Step stages
Stage 1 Terminations 70.00%
Stage 2 Testing 20.00%
Stage 3 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Installation of covers 5.00%
Stage 6 Checks 10.00%
Progress is calculated based on Underground conduits and
measured as per following stages:
Stage Description WF for
stages
Underground conduits Work Step Stage 1 Placing supports 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit and stub up 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Progress is calculated based on Above ground conduits and
measured as per following stages:
Stage Description WF for
stages
Above ground conduits Work Step Stage 1 Supports installation 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Laying of cables 55.00%
Stage 4 Cable markers installation 10.00%
Stage 5 Insulation test 10.00%
Stage 6 Cable way markers 5.00%
Stage 7 Final inspection 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Cables connections in tech. room
and measured as per following stages:
Stage Description WF for
Cables connections in tech. room Work Step stages
Stage 1 Connections 70.00%
Stage 2 Testing 20.00%
Local panels installation & connection Work Step Stage Description WF for
stages
Stage 1 Erection 20.00%
Stage 2 Connections 50.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 215 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Testing 20.00%
Stage 4
Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
Stage 2 Manifold erection 25.00%
Stage 3 Process connection 25.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Cable installation 22.00%
Stage 6 Electrical connections 8.00%
Stage 7 Transmitter circuit check 5.00%
Progress is calculated based on Electronic level instruments
Level instrument
(displacement type) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Manifold erection 20.00%
Stage 3 Process connection 30.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Cable installation 22.00%
Stage 6 Electrical connections 8.00%
Stage 7 Transmitter circuit check 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Erection of supports 12.00%
Stage 2 Manifold erection 20.00%
Stage 3 Process connection 20.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Air distribution 26.00%
Stage 6 Pneumatic connections 9.00%
Stage 7 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Manifold erection 40.00%
Stage 3 Process connection 40.00%
Stage 4 Hydrostatic testing 8.00%
Progress is calculated based on Direct pressure switches and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection 12.00%
Direct pressure switches Work Step
Stage 2 Process diagram 40.00%
Stage 3 Hydrostatic testing 3.00%
Stage 4 Cable installation 25.00%
Stage 5 Electrical connections 10.00%
Stage 6 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Cable installation 40.00%
Stage 4 Electrical connections 10.00%
Stage 5 Checks 10.00%
Progress is calculated based on Local pneumatic temperature
regulators and measured as per following stages:
Stage Description WF for
stages
Local pneumatic temperature regulators Work Step Stage 1 Support erection 20.00%
Stage 2 Capillary arrangement 20.00%
Stage 3 Air distribution 40.00%
Stage 4 Pneumatic connections 10.00%
Stage 5 Checks 10.00%
Progress is calculated based on Local MV electric converters and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of support and repeater 20.00%
Local MV electric converters Work Step
Stage 2 Thermocouple 5.00%
Stage 3 Cable installation 50.00%
Stage 4 Electrical connections 15.00%
Stage 5 Transmitter circuit check 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Erection of traps and elements 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Cable installation 40.00%
Stage 4 Electrical connections 15.00%
Stage 5 Transmitter circuit check 10.00%
Stage 6 Line washing 10.00%
Control valves with I/P and pneum. Positioner Work Step Stage 2 I/p air distribute. & positioner 40.00%
Stage 3 Cable installation 25.00%
Stage 4 Electrical connections 4.00%
Stage 5 Pneumatic connections 10.00%
Stage 6 Line washing 2.00%
Stage 7 Circuit check 4.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Pneumatic tube installation 60.00%
Stage 2 Pneumatic connections 25.00%
Stage 3 Line washing 5.00%
Stage 4 Circuit check 10.00%
Progress is calculated based on Local pneumatic receiver
regulators and measured as per following stages:
Stage Description WF for
stages
Local pneumatic receiver regulators Work Step Stage 1 Erection 25.00%
Stage 2 Air distribution 50.00%
Stage 3 Pneumatic connections 15.00%
Stage 4 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Sub-header distribution 50.00%
Steam tracing for instruments Stage 2 Copper tube steam tracer 20.00%
Stage 3 Condensate discharge manifold 20.00%
Stage 4 Piping connections 5.00%
Stage 5 Checks 5.00%
TELECOMS WORKS
Progress is calculated based on P.A.B.X. and measured as per
Telephone following stages:
Stage Description WF for
stages
Stage 1 Transport on the spot 5.00%
Telephone sets (wall type) installation Work Step Stage Description WF for
stages
Stage 1 Preparation of support 12.00%
Stage 2 Acoustic booth 28.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 225 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Installation of telephone set 20.00%
Stage 4 Wiring 30.00%
Stage 5 Final Tests 10.00%
Public Address Progress is calculated based on Loud speaker and measured as
per following stages:
Stage Description WF for
stages
Work Step Stage 1 Support preparation 5.00%
Loud speakers
Stage 2 Loud speaker installation 40.00%
Stage 3 Wiring 30.00%
Stage 4 Checks 5.00%
Stage 5 Final tests 20.00%
Progress is calculated based on Public address console and
measured as per following stages:
Stage Description WF for
Public address consoles
Work Step
stages
Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%
Stage 3 Tests / Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Wiring 30.00%
Stage 4 Checks 5.00%
Stage 5 Final tests 20.00%
Progress is calculated based on CCTV control system and
erection and measured as per following stages:
Stage Description WF for
CCTV control system
Work Step stages
Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%
Stage 3 Tests / Checks 10.00%
Progress is calculated based on Siren installation and erection
Siren
and measured as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Support preparation 20.00%
Siren installation
Stage 2 Siren installation 40.00%
Stage 3 Wiring 30.00%
Stage 4 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Telecom cables installation and
Telecom Cables
measured as per following stages:
Stage Description WF for
Work Step stages
Telecom cables installation Stage 1 Laying 50.00%
Stage 2 Terminations 30.00%
Stage 3 Checks 20.00%
Progress is calculated based on Calibrate and measured as per
Instrumentation Test
following stages:
Work Step Stage Description WF for
Instruments Calibration stages
Stage 1 Calibrate 100.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Sheeting installation 30.00%
Stage 5 Miscellaneous finishing works 5.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Piping cold insulation and
Cold Insulation Works
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 20.00%
Work Step Stage 2 Scaffolding erection 10.00%
Piping cold insulation Stage 3 Insulating layer installation 15.00%
Stage 4 Vapour barrier 20.00%
Stage 5 Sheeting installation 20.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
Progress is calculated based on Equipment cold insulation and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 20.00%
Equipment cold insulation Work Step Stage 2 Scaffolding erection 10.00%
Stage 3 Insulating layer installation 15.00%
Stage 4 Vapor barrier 20.00%
Stage 5 Sheeting installation 20.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
PAINTING Progress is calculated based on Piping painting (2+2 coats) and
Painting Works measured as per following stages:
Work Step
Stage Description WF for
Piping painting (2+2 coats)
stages
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 230 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Stage 3 2nd primer coat 10.00%
Stage 4 1st finish coat 15.00%
Stage 5 2nd finish coat 15.00%
Stage 6 Numbering or labelling 5.00%
Stage 7 Final cleaning and touch up 10.00%
Stage 8 Final check 5.00%
Progress is calculated based on Piping painting in shop (2 coats)
and measured as per following stages:
Stage Description WF for
stages
Piping painting in shop (2 coats) Work Step Stage 1 Wire brushing or shot blasting 50.00%
Stage 2 1st primer coat 20.00%
Stage 3 2nd primer coat 20.00%
Stage 4 Final check 10.00%
Progress is calculated based on Piping painting in field (2 coats
and measured as per following stages:
Stage Description WF for
stages
Piping painting in field (2 coats) Work Step Stage 1 1st finish coat 35.00%
Stage 2 2nd finish coat 35.00%
Stage 3 Numbering or labelling 10.00%
Stage 4 Final cleaning and touch up 10.00%
Stage 5 Final check 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 231 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Steel structures painting (2+2
coats) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Steel structures painting (2+2 coats) Work Step Stage 3 2nd primer coat 10.00%
Stage 4 Touch up 14.00%
Stage 5 1st finish coat 16.00%
Stage 6 2nd finish coat 15.00%
Stage 7 Touch up 3.00%
Stage 8 Final check 2.00%
Progress is calculated based on Steel structure painting in field (2
coats) and measured as per following stages:
Stage Description WF for
stages
Stage 1 1st finish coat 35.00%
Steel structure painting in field (2 coats) Work Step Stage 2 2nd finish coat 35.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Intermediate coat 35.00%
Stage 2 Final coat 35.00%
Stage 3 Numbering or labelling 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 2nd finish coat 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Compact 15.00%
Stage 4 Test 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted Total No. of Stringing 2-3 10.00%
pipe section
Progress is calculated based on Field Bending and measured as
per following stages:
Stage Description WF for
stages
Laying/Welding & Joint Coating Work Step Stage 1 Laying 20.00%
Stage 2 Welding 40.00%
Stage 3 Joint Coating 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Actual no. of Welding 90.00%
Stage 2 Accepted Total no. of Welding 10.00%
Progress is calculated based on tie-in and measured as per
following stages:
Stage Description WF for
Tie-ins Work Step
stages
Stage 1 Actual No. of Tie-ins 90.00%
Stage 2 Accepted Total No. of Tie-ins 10.00%
Progress is calculated based on NDT and measured as per
following stages:
Stage Description WF for
NDT Work Step
stages
Stage 1 Total No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Field Joint coating and measured
as per following stages:
Stage Description WF for
Field Joint Coating Work Step stages
Stage 1 Actual - No. of Field joints 90.00%
Stage 2 Accepted Total No. of Field Joint 10.00%
Coating
Progress is calculated based on Bedding and measured as per
following stages:
Stage Description WF for
Bedding Work Step
stages
Stage 1 Actual - No. of Bedding 90.00%
Stage 2 Accepted Total No. of Bedding 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 237 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Lowering and measured as per
following stages:
Stage Description WF for
Lowering Work Step stages
Stage 1 Actual - No. of Lowering 90.00%
Stage 2 Accepted Total No. of Lowering 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Formworks 35.00%
Stage 5 Pouring 20.00%
Stage 6 Coating 5.00%
Stage 7 Backfilling 10.00%
Progress is calculated based on Backfilling and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Sand filling 20.00%
Backfilling/Berm Forming Work Step
Stage 2 Backfilling 20.00%
Stage 3 Berm 1st Lay 20.00%
Stage 4 Berm 2nd Lay 20.00%
Stage 5 Berm 3rd Lay 10.00%
Stage 6 Final Inspection 10.00%
Progress is calculated based on Cathodic protection and
measured as per following stages:
Stage Description WF for
Cathodic protection Work Step stages
Stage 1 Actual - No. of Cathodic Protection 90.00%
Stage 2 Accepted Total No. of Cathodic 10.00%
Protection
Progress is calculated based on Pre-Commissioning and
measured as per following stages:
Pre-commissioning Work Step Stage Description WF for
stages
Stage 1 Chemical Cleaning (Pigs or GEL Pigs) 12.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 239 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Helium Leak Detection 10.00%
Stage 3 Bolting 6.00%
Stage 4 Hot Oil Flushing 10.00%
Stage 5 Pipe Freezing 10.00%
Stage 6 Foam Inerting 13.00%
Stage 7 Gauging 20.00%
Stage 8 Filling (Flooding) 9.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Along-Route Road and measured
as per following stages:
Stage Description WF for
Along-Route Road Work Step
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Progress is calculated based on Marker and measured as per
following stages:
Stage Description WF for
Marker Work Step
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Progress is calculated based on Restoration and measured as per
following stages:
Stage Description WF for
Restoration Work Step
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Progress is calculated based on Stockpiling of Pipe and measured
as per following stages:
Stage Description WF for
Stockpiling of Pipe Work Step
stages
Stage 1 Actual - No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Bridge - off take Work Step
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 241 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Bridge - off take and measured
as per following stages:
Stage Description WF for
stages
Stage 1 Actual - No. of Bridge 90.00%
Stage 2 Accepted Total No. of Bridge 10.00%
Progress is calculated based on Valve station and measured as
per following stages:
Stage Description WF for
stages
Stage 1 Ground Levelling (Civil works) 10.00%
Stage 2 Foundation (Civil works) 7.00%
Stage 3 Editing / Welding of Valves (Process 11.00%
works)
Stage 4 Welding of Pipelines (Process works) 8.00%
Stage 5 Coating (Process works) 6.00%
Valve station Work Step Stage 6 Contour of grounding (Electrical 7.00%
works)
Stage 7 TEG Installation (Electrical works) 4.00%
Stage 8 Lightning Protection System 7.00%
( Electrical )
Stage 9 Install Pressure Gauge Transmitter 6.00%
(Instrument works)
Stage Grounds/Gas Temperature 4.00%
10 Transmitter (Instrument works)
Stage PIG Detector (Instrument works) 15.00%
11
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 242 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Optical Cable laying (Instrument 8.00%
12 works)
Stage Installation of Instrument Box 3.00%
13 (Instrument works)
Stage CP Test Connection (Instrument 2.00%
14 works)
Stage Hydro Test / Drying 2.00%
15
Progress is calculated based on Access roads and measured as
per following stages:
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Staking 5.00%
Stage 3 Putting earth embankment 10.00%
Stage 4 Installation slabs 8.00%
Stage 5 Putting mixtures surfacing 10.00%
Stage 6 Sealing of joints 7.00%
Stage 7 Painting 10.00%
Stage 8 Access road 8.00%
Stage 9 Putting earth embankment 10.00%
Stage 10 Construction of roadway surfacing 8.00%
Stage 11 Slope strengthening with soil and 8.00%
grass sowing
Stage 12 Installation vane 8.00%
Progress is calculated based on Appurtenances of pipe and
measured as per following stages:
Stage Description WF for
Appurtenances of pipe Work Step stages
Stage 1 Actual - No. of Appurtenance of Pipe 90.00%
Stage 2 Accepted Total No. of Appurtenance 10.00%
of Pipe
Progress is calculated based on Power supply and measured as
per following stages:
Power supply Work Step Stage Description WF for
stages
Stage 1 Power Supply 100.00%
Progress is calculated based on Road Crossings and measured as
Road Crossings Work Step
per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 244 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Actual - No. of Road Crossing 90.00%
Stage 2 Accepted Total No. of Road Crossing 10.00%
Progress is calculated based on HDD River and measured as per
following stages:
Stage Description WF for
HDD River Work Step
stages
Stage 1 Actual - No. of HDD River 90.00%
Stage 2 Accepted Total No. of HDD River 10.00%
Progress is calculated based on River crossing and measured as
per following stages:
Stage Description WF for
River and water channel crossing Work Step stages
Stage 1 Actual - No. of River and Water channel 90.00%
crossing
Stage 2 Accepted Total No. of River and Water 10.00%
channel crossing
Progress is calculated based on Railway and measured as per
following stages:
Work Description WF for
Railway Work Step
Step stages
Step 1 Actual - No. of Railway 90.00%
Step 2 Accepted Total No. of Railway 10.00%
Progress is calculated based on Road crossing (casing) and
Road crossing (casing) Work Step
measured as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 245 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Actual - No. of Road Crossing (casing) 90.00%
Stage 2 Accepted Total No. of Road Crossing 10.00%
(casing)
Progress is calculated based on Road crossing (excavation) and
measured as per following stages:
Stage Description WF for
Road crossing (excavation) Work Step
stages
Stage 1 Actual - No. of Road Crossing 90.00%
(excavation)
Stage 2 Accepted Total No. of Road Crossing 10.00%
(excavation)
Progress is calculated based on U/G pipeline/cables and
measured as per following stages:
Stage Description WF for
U/G pipeline/cables Work Step stages
Stage 1 Actual - Linear in meters 90.00%
Stage 2 Accepted Total No. of Linear in 10.00%
Meters
Progress is calculated based on Others / Weight Blocks and
measured as per following stages:
Stage Description WF for
Others / Weight Block Work Step stages
Stage 1 Actual - No. of Others / Weight block 90.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on U/G pipeline/cables and
measured as per following stages:
Stage Description WF for
Embankment protection Work Step stages
Stage 1 Actual - No. of Embankment Protection 90.00%
Stage 2 Accepted Total No. of Embankment 10.00%
Protection
Pre-commissioning & Testing
Progress is calculated based on Piping Pre-commissioning ( by
test Package) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Ready for flushing 15.00%
Work Step Stage 2 Flushing 30.00%
Piping Pre-commissioning ( by test
Package) Stage 3 Reinstatement 15.00%
Stage 4 PID conformity 10.00%
Stage 5 Tightness test 15.00%
WP - 8471 Stage 6 Inerting 5.00%
Stage 7 MCC Package Hand-over 10.00%
Instrumentation Progress is calculated based on SAT and measured as per
following stages:
Stage Description WF for
Site Acceptance Tests ( SAT Work Step
stages
Systems)
Stage 1 Complete SAT 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Mini Loop Check and measured
Mini Loop Check Work Step
as per following stages:
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 247 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Mini Loop Check 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Loop Check and measured as per
following stages:
Stage Description WF for
Loop Check Work Step
stages
Stage 1 Loop Check 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Functional check and measured as
per following stages:
Stage Description WF for
Functional Check Work Step
stages
Stage 1 Functional Check 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Building Pre-commissioning
Electrical
and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Power supply and checking 30.00%
Electrical Generator Stage 2 Control System checking 20.00%
Step 3 Motors run 30.00%
Step 4 Energizing 15.00%
Step 5 Certificate 5.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 248 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Building Pre-commissioning and
measured as per following stages:
Stage Description WF for
stages
Transformer tests Work Step
Stage 1 Vector group 30.00%
Stage 2 Energization 50.00%
Stage 3 Leak test 10.00%
Stage 4 MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Electrical Panels (General) and
measured as per following stages:
Stage Description WF for
Electrical Panels (General) Work Step stages
Stage 1 Panels 90.00%
Stage 2
MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Pigging & Drying and measured
as per following stages:
Stage Description WF for
stages
Pigging & Drying
Stage 1
Pigging & Drying 90.00%
Stage 2
MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Reinstatement 25.00%
Stage 3 Final Alignment 15.00%
Stage 4 First Oil Filling 40.00%
Stage 5 Certificate 10.00%
Progress is calculated based on Compressors & Blowers and
measured as per following stages:
Stage Description WF for
Compressors & Blowers Work Step stages
Stage 1 Preparation works 25.00%
Stage 2 Pre-commissioning 65.00%
Stage 3
MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Air coolers load test and
measured as per following stages:
Stage Description WF for
stages
Stage 1
Pre-commissioning 90.00%
Stage 2
MCC Package Hand-over 10.00%
Stage 3
MCC Package Hand-over 10.00%
Stage 2
MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1
Steam Blowing 90.00%
Stage 2
MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Materials Documentation and
measured as per following stages:
Stage Description WF for
stages
WP - 850 Materials Documentation ( No. of Documents) Work Step Stage 1 Submission 65.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on No. of documents and measured
as per following stages:
Stage Description WF for
stages
WP - 853 As-Built Drawings (No. of Documents) Work Step
Stage 1 Submission 65.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on As NDT Radiographic Films and
measured as per following stages:
Stage Description WF for
WP - 856 NDT Radiographic Films (No. of Documents) Work Step stages
Stage 1 Submission 65.00%
Stage 2 Approval 25.00%
Stage 3 Acceptance 10.00%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 257 of 456
Work Package No. WF% Description of Work Package Calculation Description, Detailed Weight Factor or Formula
Procedures & Shop Drawing Progress is calculated according to the procedures and shop Drawing list.
911 Cost
Issuance (Issued/Total)
Work WF for
Description
Step Stages
Step 1 Issue of Purchase Order 25%
based on Monthly manufacturing progress report
Procurement of Installation Step 2 approved by Supply Chain Management or PMT from P/O 55%
912 Cost
Materials issue date until shipment
Step 3 Final Inspection and Release for Shipment 10%
Step 4 Delivery to SITE/ Warehouse 5%
Step 5 VENDOR'S FINAL DOCUMENTATION 5%
913 Preparation Activities When it's done, the progress is 100%.
Cost Mobilization of Transportation Barge
914 When it's done, the progress is 100%.
at Yard
Sail Away and arrive at site
915 Cost When it's done, the progress is 100%.
(Transportation)
916 Cost Mobilization of Derrick Barge When it's done, the progress is 100%.
Work WF for
Description
Step Stages
917 Cost Set Jacket in position Step 1 Positioning of Barge 20%
Step 2 Launching/ Rigging & Lifting 50%
Step 3 Welding 30%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 258 of 456
Based
918 on the Pilling Works (Total No. of Piling performed)/(Total No. of Piles)
Cost
Based
919 on the Installation of Conductors (Total No. of conductor Installed)/(Total No. of Conductors)
Cost
Work WF for
Based Description
Step Stages
920 on the Installation of Boat Landing
Step 1 Rigging & Lifting 50%
Cost
Step 2 Welding 50%
921 Cost Demobilization of Derrick Barge When it's done, the progress is 100%.
922 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)
Work Package No. WF% Description of Work Package Calculation Description, Detailed Weight Factor or Formula
Procedures & Shop Drawing Progress is calculated according to the procedures and shop Drawing list.
923 M/H
Issuance (Issued/Total)
Work WF for
Description
Step Stages
Step 1 Issue of Purchase Order 25%
based on Monthly manufacturing progress report
Procurement of Installation Step 2 approved by Supply Chain Management or PMT from P/O 55%
924 M/H
Materials issue date until shipment
Step 3 Final Inspection and Release for Shipment 10%
Step 4 Delivery to SITE/ Warehouse 5%
Step 5 VENDOR'S FINAL DOCUMENTATION 5%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 259 of 456
925 Cost Preparation Activities When it's done, the progress is 100%.
926 Mobilization of Barge at Yard When it's done, the progress is 100%.
Cost
927 Sail Away and arrive at site When it's done, the progress is 100%.
928 Cost Mobilization of Derrick Barge When it's done, the progress is 100%.
Work WF for
Description
Step Stages
929, 930 Cost Topside Installation & Welding Step 1 Positioning of Barge 20%
Step 2 Rigging & Lifting 50%
Step 3 Welding 30%
931 Cost Demobilization of Derrick Barge When it's done, the progress is 100%.
932 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)
Work Package No. WF% Description of Methodology Calculation Description, Detailed Weight Factor or Formula
Procedures & Shop Drawing Progress is calculated according to the procedures & shop Drawing list.
933 M/H
Issuance (Issued/Total)
Work WF for
Description
Step Stages
Step 1 Issue of Purchase Order 25%
Procurement of Installation
934 M/H Based on Monthly manufacturing progress report approved
Materials
Step 2 by Supply Chain Management or PMT from P/O issue date 55%
until shipment
Step 3 Final Inspection and Release for Shipment 10%
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 260 of 456
943 Cost Demobilization of Derrick Barge When it's done, the progress is 100%.
944 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)
Work Package No. WF% Description of Methodology Calculation Description, Detailed Weight Factor or Formula
Shop Drawing & Procedures Progress is calculated according to the procedures & shop Drawing list.
945 M/H
Issuance (Issued/Total)
Work WF for
Description
Step Stages
Procurement of Installation Step 1 Issue of Purchase Order 25%
946 M/H
Materials Based on Monthly manufacturing progress report approved
Step 2 by Supply Chain Management or PMT from P/O issue date 55%
until shipment
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 261 of 456
963 Cost Demobilize Installation Barge When it's done, the progress is 100%.
964 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 262 of 456
Work Package No. WF% Description of Methodology Calculation Description, Detailed Weight Factor or Formula
Shop Drawing and Procedures Progress is calculated according to the shop Drawing & Procedures list.
965 M/H
Issuance (Issued/Total)
Work WF for
Description
Step Stages
Step 1 Issue of Purchase Order 25%
Based on Monthly manufacturing progress report
Procurement of Installation Step 2 approved by Supply Chain Management or PMT from P/O 55%
966 M/H
Materials issue date until shipment
Step 3 Final Inspection and Release for Shipment 10%
Step 4 Delivery to SITE/ Warehouse 5%
Step 5 VENDOR'S FINAL DOCUMENTATION 5%
967 Preparation Activities When it's done, the progress is 100%.
Cost
968 Mobilization of Barge at Yard When it's done, the progress is 100%.
Cost
969 Sail Away and arrive at site When it's done, the progress is 100%.
Cost Preparation Activities & Mobilization
970, 971 When it's done, the progress is 100%.
of Pipe laying Barge
Cost
972 Lay Pipeline For Pipe lying, progress measurement shall be based on meters of Pipes laid.
Cost
973 Install Jacket Riser When it's done, the progress is 100%.
Cost
974 Install Host Tie-in Riser When it's done, the progress is 100%.
Cost
975 Pipeline Pre-commissioning Based on No. of Test Package.
Cost
976 Demobilization of Pipe laying Barge When it's done, the progress is 100%.
977 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 263 of 456
Work Package : H, I, J, K, M, X
Work Package No. WF% Description of Methodology Calculation Description, Detailed Weight Factor or Formula
Procedures and Shop Drawing Progress is calculated according to the shop Drawing and procedures list.
978 M/H
issuance (Issued/Total)
Work WF for
Description
Step Stages
Step 1 Issue of Purchase Order 25%
Based on Monthly manufacturing progress report approved
Procurement of Installation Step 2 by Supply Chain Management or PMT from P/O issue date 55%
979 M/H
Materials until shipment
Step 3 Final Inspection and Release for Shipment 10%
Step 4 Delivery to SITE/ Warehouse 5%
Step 5 VENDOR'S FINAL DOCUMENTATION 5%
980 Cost Preparation Activities When it's done, the progress is 100%.
981 Mobilization of Barge at Yard When it's done, the progress is 100%.
Cost
982 Sail Away and arrive at site When it's done, the progress is 100%.
Cost Preparation Activities & Mobilization
983, 984 When it's done, the progress is 100%.
of Derrick Barge
985 Cost Installation When it's done, the progress is 100%.
Cost
986 Welding & NDT According to Quantity
Cost
987 Testing & Pre-commissioning According to No. of Test Package
Cost
988 Demobilization of Derrick Barge When it's done, the progress is 100%.
989 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)
990 to 998 M/H Pre Shutdown /Shutdown/Post SD. When it's done, the progress is 100%.
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 264 of 456
Work
Description WF
Step
1116 M/H Commissioning Each subsystem commissioning will be 100% when it is completed. Commissioning
1116 M/H Demobilization of the Boat When it's done, the progress is 100%.
Demob. & Final
Doc.
1117 M/H Final Documentation (Total No. of Documents prepared)/(Total No. of Documents)
11121 to 11129 M/H Pre-shut down Activities When it's done, the progress is 100%. Shut Down
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 266 of 456
11121 to 11129 M/H Shut Down Activities When it's done, the progress is 100%.
11121 to 11129 M/H Post Shut Down Activities When it's done, the progress is 100%.
Activity ID Activity Description MH Needed Progress Earned MH
Air Compressor/Dryer Package
Air Compressor Package
Electrical
123-01-EL-01 Rect. of Elect. Punch of Air Compressor 35 10% 3.5
Air Dryer Package
Instrument
123-02-IN-01 Rect. of Inst. Punch of Air Compressor 20 10% 2
Air Receiver System
Mechanical
123-03-ME-01 Rect. of Inst. Phi. Punch of Air Compressor 40 20% 8
Air Distribution System
Instrument
TA1 0% Noop Preparation Milestone The total progress (100%) will be achieved once the notice of Rig is issued.
WF for
Stages Description
Stages
1. Physical progress for rig up shall be calculated based on the daily progress
Based on the
TA4 Rig up Parametric report.
cost
2. WF of Rig up should be calculated based on the cost
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 268 of 456
This item is depend on the project and Progress of each Well item is
TB3 Well #01
calculated as per following stages:
WF for
Stages Description
Stages
WF for
Stages Description
Stages
Based
TB32 Drilling Operation Work Step
on the
1 Hole Section Drilling cost of
each
section
Based
2 Casing Running and Cementing on the
cost
PTSG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 270 of 456
WF for
Stages Description
Stages
TB33 Formation Evaluation Milestone
Coring progress is on and off and will be 100% after
1 89.00%
completion of the work
The physical progress for the overall project is obtained by summing up the physical weighted progress
of each phase:
FEL 1 – Initiation
FEL 2 – Scope Selection
FEL 3 – Scope Definition
Execution
The corresponding weight factors are determined initially in accordance with the respective cost
values, as defined by the project cost breakdown structure.
For calculating the Level 1 Weight Factor (L1 WF) for each phase follows these steps:
4. Find the project total budget. In this example the total is RM1,000,000
5. Find the budget of each phase
6. To calculate the phase weight factor use this formula:
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑃ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1) = × 100%
𝑃𝑟𝑜𝑗𝑒𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 45,000
𝐹𝐸𝐸𝐷 𝑊𝐹 (𝐿1) = × 100% = 4.5%
𝑅𝑀 1,000,000
Budget
Level 1 Weight
No. Phase
Factor (L1 WF)%
(RM '000)
Project Management
Project Management is broken down in 10 sub phases. For calculating Level 2 Weight Factor (L2 WF):
Example:
𝑅𝑀 6,000
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 24%
𝑅𝑀 25,000
8. (L1 WF) for sub phase/discipline is its share portion at Project level rather than its parent
level WF (i.e. Phase) it can be calculated.
(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 (𝑑𝑖𝑠𝑐𝑖𝑝𝑙𝑖𝑛𝑒) 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(24% × 2.5%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 (𝐿1 𝑊𝐹) = = 0.6%
100%
Budget Budget
Phase (L1 WF)% Sub-Phase / Discipline (L2 WF)% (L1 WF)%
(RM '000) (RM '000)
Project
25000 2.5
Management
Initiation 1000 4.4 0.11
Conceptual
4500 18 0.45
Engineering
FEED 1900 7.6 0.19
Detail Engineering 3000 12 0.30
Procurement PCSB
2500 10 0.25
Supplied Materials
Construction 5000 20 0.50
Initiation
Initiation is broken down to two contracts. Same as phase level each contract has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. For calculating Level 2 Weight Factor (L2WF):
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 10,000
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑆𝑒𝑟𝑣𝑖𝑐𝑒𝑠 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 100.00%
𝑅𝑀 10,000
Initiation 10,000 1 - - - -
For in house services there are some sub phases. Same as Phase level each sub-phase has its own
budget (accessible from budget estimation from cost control/finance dept.) and accordingly each of
them has their own weight factor. Contract No.1 is broken up in 4 sub-phases. For calculating Level 3
Weight Factor (L3 WF):
6. Find the Contract total budget. In this example the Total for contract in house is RM 10,000
and for In house service is RM 10,000
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 3,000
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 30.00%
𝑅𝑀 10,000
9. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 277 of 456
(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(30% × 100%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿2 𝑊𝐹) = = 30.00%
100%
10. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(30% × 1%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿1 𝑊𝐹) = = 0.30%
100%
Budget (L3WF)
Contracting Budget (RM '000) (L2 WF)% Sub-Phase / Discipline (L2 WF)% (L1 WF)%
(RM '000) %
7. Find the Sub phase total budget. In this example the Total for facilities feasibility studies is
RM 4,500.
8. Find the budget of each Control Account.
9. To calculate the Control account weight factor use this formula:
Example:
𝑅𝑀 450
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100% = 10%
𝑅𝑀 4,500
10. (L3 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 278 of 456
Example:
(10% × 45%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙(𝐿3 𝑊𝐹) = = 4.5%
100%
11. (L2 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(10% × 45%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 (𝐿2𝑊𝐹) = = 4.5%
100%
12. (L1 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(10% × 0.45%)
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 (𝐿1 𝑊𝐹) = = 0.05 %
100%
Budget
Budget (L3 Control (L3WF)
Sub-Phase (RM (L5WF)% (L2 WF)% (L1 WF)%
(RM '000) WF)% Account %
'000)
Facilities
Feasibility 4,500 45.00
Studies
General 450 10 4.5 4.5 0.05
HSE 1350 36 16.2 16.2 0.16
Facility
2450 54 24.3 24.3 0.24
Assessment
Total 4,500 100 45 45 0.45
8. Find the control account total budget. In this example the Total for general is RM 450.
9. Find the budget of each work package.
10. To calculate the work packages weight factor use this formula:
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡
Example:
180
Preliminary Concept Development 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100 = 40 %
450
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 279 of 456
11. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%
Example:
(40% × 10%)
Preliminary Concept Development(𝐿5 𝑊𝐹) = =4%
100%
12. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(40% × 4.5%)
Preliminary Concept Development (𝐿3 𝑊𝐹) = = 1.80 %
100%
13. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(40% × 4.5%)
Preliminary Concept Development (𝐿2 𝑊𝐹) = = 1.80 %
100%
14. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(40% × 0.05%)
Preliminary Concept Development(𝐿1 𝑊𝐹) = = 0.02 %
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 280 of 456
Conceptual Engineering Services is broken down to two contracts. Same as phase level each contract
has its own budget (accessible from budget estimation from cost control/finance dept.) and
accordingly each of them has their own weight factor. For calculating Level 2 Weight Factor (L2WF):
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 3,000
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑆𝑒𝑟𝑣𝑖𝑐𝑒𝑠 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 15.00%
𝑅𝑀 20,000
𝑅𝑀 17,000
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 85.00%
𝑅𝑀 20,000
8. (L1 WF) for sub phase/discipline is its share portion at Project level rather than its parent
level WF (i.e. Phase) it can be calculated.
(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏 𝑝ℎ𝑎𝑠𝑒 (𝑑𝑖𝑠𝑐𝑖𝑝𝑙𝑖𝑛𝑒) 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(85% × 2%)
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 (𝐿1 𝑊𝐹) = = 1.70%
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 281 of 456
Conceptual
Engineering 20,000 2 - - - -
Services
Contracting In House 3,000 15.00 0.30
Contract No.1 17,000 85.00 1.70
For each contract there are some sub phases. Same as Phase level each sub-phase has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. Contract No.1 is broken up in 4 sub-phases. For calculating Level 3 Weight
Factor (L3 WF):
8. Find the Contract total budget. In this example the Total for contract No.1 is RM 17,000 and
for In house service is RM 3,000
9. Find the budget of each Sub phase.
10. To calculate the Sub phase weight factor use this formula:
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀10,200
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 60.00%
𝑅𝑀 17,000
11. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated
(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(60% × 85%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿2 𝑊𝐹) = = 51.00%
100%
12. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(60% × 1.7%)
𝐶𝑜𝑛𝑐𝑒𝑝𝑡𝑢𝑎𝑙 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 (𝐿1 𝑊𝐹) = = 1.02%
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 282 of 456
Find the sub phase total budget. In this example the Total budget for Detailed Feasibility
Studies is RM 10200.
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝐵𝑢𝑑𝑔𝑒𝑡
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿4𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 10,200
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 𝑊𝐹 (𝐿4𝑊𝐹) = × 100% = 100%
𝑅𝑀 10,200
9. (L3 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿4𝑊𝐹 × 𝐿3𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(100% × 60.0%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 (𝐿3 𝑊𝐹) = = 60.00 %
100%
10. (L2 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 283 of 456
(𝐿4𝑊𝐹 × 𝐿2𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(100% × 51%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 (𝐿2𝑊𝐹) = = 51 %
100%
11. (L1 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿4𝑊𝐹 × 𝐿1𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(100% × 1.02%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 (𝐿1 𝑊𝐹) = = 1.02 %
100%
Budget Budget
Sub-Phase (L3 WF)% Facility (L4WF)% (L3WF)% (L2 WF)% (L1 WF)%
(RM '000) (RM '000)
Detailed
Feasibility 10,200 60
Studies
Refinery
10,200 100.00 60.00 51.00 1.02
Facilities
Crude
0 0.00 0.00 0.00 0.00
Distillation
Total 10,200 100.00 60.00 51.00 1.02
7. Find the Sub phase or Facility total budget. In this example the Total for concept select is
RM 1,500.
8. Find the budget of each Control Account.
9. To calculate the Control account weight factor use this formula:
Example:
𝑅𝑀 300
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿5 𝑊𝐹) = × 100% = 20%
𝑅𝑀 1,500
10. (L3 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 284 of 456
(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(20% × 50%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠(𝐿3 𝑊𝐹) = = 10%
100%
11. (L2 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(20% × 7.50%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿2𝑊𝐹) = = 1.5%
100%
12. (L1 WF) for control account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(20% × 0.15%)
𝑃𝑟𝑒 𝐹𝐸𝐸𝐷 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 (𝐿1 𝑊𝐹) = = 0.03 %
100%
Budget Budget
Control (L5WF) (L3WF)
Sub-Phase (RM (L3 WF)% (RM (L2 WF)% (L1 WF)%
Account % %
'000) '000)
6. Find the control account total budget. In this example the Total for PMT Deliverable is RM
150.
7. Find the budget of each work package.
8. To calculate the work packages weight factor use this formula:
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡
Example:
37.5
Project Risk Analysis 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100% = 25.00%
150
9. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%
Example:
(25% × 8%)
Project Risk Analysis (𝐿5 𝑊𝐹) = = 2%
100%
10. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(25% × 4%)
Project Risk Analysis (𝐿3 𝑊𝐹) = = 1%
100%
13. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(25% × 0.6%)
Project Risk Analysis (𝐿2 𝑊𝐹) = = 0.15 %
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 286 of 456
14. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(25% × 0.01%)
Project Risk Analysis(𝐿1 𝑊𝐹) = = 0.0025 %
100%
PMT
Deliverable
150 8
Project Risk
37.5 25.00 2 1 0.15 0.0025
Analysis
QRA 37.5 25.00 2 1 0.15 0.0025
Preparation
37.5 25.00 2 1 0.15 0.0025
of PCPP
OCS 37.5 25.00 2 1 0.15 0.0025
FEED
All Level weight factors for FEED will be calculated same as Conceptual design services and Execution
phase.
EXECUTION
For Execution phase there are two contracts. Same as phase level each contract has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. For calculating Level 2 Weight Factor (L2WF):
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100%
𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 315,000
𝐼𝑛 𝐻𝑜𝑢𝑠𝑒 𝑆𝑒𝑟𝑣𝑖𝑐𝑒𝑠 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 35%
𝑅𝑀 900,000
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 287 of 456
𝑅𝑀 585,000
𝐸𝑃𝐶𝐼𝐶 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) = × 100% = 65%
𝑅𝑀 900,000
8. (L1 WF) for contracting is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿2 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡𝑖𝑛𝑔 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(65% × 90%)
𝐸𝑃𝐶𝐶 𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑁𝑜. 1 (𝐿1 𝑊𝐹) = = 58.5%
100%
Budget
Phase (L1 WF)% Sub-Phase / Discipline Budget (RM '000) (L2 WF)% (L1 WF)%
(RM '000)
Execution 900,000 90 - - - -
For each contract there are some sub phases. Same as Phase level each sub-phase has its own budget
(accessible from budget estimation from cost control/finance dept.) and accordingly each of them has
their own weight factor. EPCC Package is broken up in 4 sub-phases. For calculating Level 3 Weight
Factor (L3 WF):
6. Find the Contract total budget. In this example the Total for EPCC Contract is RM 585,000.
7. Find the budget of each Sub phase.
8. To calculate the Sub phase weight factor use this formula:
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 57,000
𝐶𝑜𝑚𝑚𝑖𝑠𝑠𝑖𝑜𝑛𝑖𝑛𝑔 𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) = × 100% = 9.74%
𝑅𝑀 585,000
9. (L2 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated
(𝐿3 𝑊𝐹 × 𝐿2 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 288 of 456
Example:
(9.74% × 65%)
𝐶𝑜𝑚𝑚𝑖𝑠𝑠𝑖𝑜𝑛𝑖𝑛𝑔 (𝐿2 𝑊𝐹) = = 6.33%
100%
10. (L1 WF) for Sub phase is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿3 𝑊𝐹 × 𝐿1 𝑊𝐹)
𝑆𝑢𝑏𝑝ℎ𝑎𝑠𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(9.74% × 58.5%)
𝐶𝑜𝑚𝑚𝑖𝑠𝑠𝑖𝑜𝑛𝑖𝑛𝑔 (𝐿1 𝑊𝐹) = = 5.7%
100%
Budget
Contracting (L2 WF)% Sub-Phase / Discipline Budget (RM '000) (L3WF)% (L2 WF)% (L1 WF)%
(RM '000)
EPCC 585,000 65
Detail Engineering 60,000 10.26 6.67 6
Procurement 177,000 30.26 19.67 17.7
Construction 272,000 46.50 30.22 27.2
Commissioning 57,000 9.74 6.33 5.7
Contract Closure
19,000 3.25 2.11 1.9
Report
Total 585,000 100 65 58.5
For each sub-phase there are facility, Control account and work packages. Same as Phase level and
Sub-phase, each facility has its own budget (accessible from budget estimation from cost control,
finance and contract dept.) and accordingly each of them has their own weight factor. In this example
Fabrication is broken up in 2 facilities.
7. Find the Sub phase total budget. In this example the Total for Construction is RM 272,000.
8. Find the budget of each facility.
9. To calculate the facility weight factor use this formula:
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝐵𝑢𝑑𝑔𝑒𝑡
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿4 𝑊𝐹) = × 100%
𝑆𝑢𝑏𝑃ℎ𝑎𝑠𝑒 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
𝑅𝑀 190,400
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑖𝑒𝑠 𝑊𝐹 (𝐿4 𝑊𝐹) = × 100% = 70%
𝑅𝑀 272,000
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 289 of 456
10. (L3 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿4𝑊𝐹 × 𝐿3𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(70% × 46.5%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑖𝑒𝑠 (𝐿3 𝑊𝐹) = = 32.55 %
100%
11. (L2 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿4𝑊𝐹 × 𝐿2𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
Example:
(70% × 30.22%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑖𝑒𝑠 (𝐿2𝑊𝐹) = = 21.15 %
100%
12. (L1 WF) for facility is its share portion at Project level rather than its parent level WF (i.e.
Phase) It can be calculated.
(𝐿4𝑊𝐹 × 𝐿1𝑊𝐹)
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(70% × 27.2%)
𝑅𝑒𝑓𝑖𝑛𝑒𝑟𝑦 𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑖𝑒𝑠 (𝐿1 𝑊𝐹) = = 19.04 %
100%
For each facility there are Control accounts. Same as Phase level and Sub-phase each control accounts
has its own budget (accessible from budget estimation from cost control, finance and Contract dept.)
and accordingly each of them has their own weight factor. In this example Refinery is broken up in 9
control accounts.
8. Find the facility total budget. In this example the Total for Refinery is RM 190,400.
9. Find the budget of each control account.
10. To calculate the control account weight factor use this formula:
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100%
𝐹𝑎𝑐𝑖𝑙𝑖𝑡𝑦
Example:
135,400
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝐴𝑟𝑒𝑎 𝑊𝐹 (𝐿5 𝑊𝐹) = × 100 = 71.11 %
190,400
11. (L4 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿4𝑊𝐹)
𝑊𝐹 (𝐿4 𝑊𝐹) =
100%
Example:
(71.11% × 70%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝐴𝑟𝑒𝑎 (𝐿4 𝑊𝐹) = = 49.78 %
100%
12. (L3 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿3𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(71.11% × 32.55%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝐴𝑟𝑒𝑎 (𝐿3 𝑊𝐹) = = 22.76 %
100%
13. (L2 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿2𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 291 of 456
Example:
(71.11% × 21.15%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝐴𝑟𝑒𝑎 (𝐿2 𝑊𝐹) = = 15.04 %
100%
14. (L1 WF) for Control Account is its share portion at Project level rather than its parent level
WF (i.e. Phase) It can be calculated.
(𝐿5𝑊𝐹 × 𝐿1𝑊𝐹)
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(71.11% × 19.04%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝐴𝑟𝑒𝑎 (𝐿1 𝑊𝐹) = = 13.54 %
100%
Budget
Budget (L5WF)% (L4WF) (L3WF)%
Facility (RM (L4 WF)% Control Account (L2 WF)% (L1 WF)%
(RM '000) %
'000)
190
Refinery 70
,400
Front End
Activities/Mob 4,000 2.1 1.47 0.68 0.44 0.4
ilization
Engineering
10,000 5.25 3.68 1.71 1.11 1
/Shop Drawing
Process Area 135,400 71.11 49.78 23.15 15.04 13.54
Utility &
7,000 3.68 2.57 1.2 0.78 0.7
Building
Storage Area 20,000 10.5 7.35 3.42 2.22 2
Offsite 5000 2.63 1.84 0.85 0.56 0.5
Pipeline 4500 2.36 1.65 0.77 0.5 0.45
Pre-
2500 1.31 0.92 0.43 0.28 0.25
commissioning
Final
2,000 1.05 0.74 0.34 0.22 0.2
Documentation
Total 190,400 100 70 32.55 21.15 19.04
For each control account there are work packages. Same as Phase level and Sub-phase, each work
package has its own budget (accessible from budget estimation from cost control, finance and
contract dept.) and accordingly each of them has their own weight factor. In this example yard
fabrication is broken up in 8 work packages.
9. Find the control account or facility total budget. In this example the Total for
Engineering/Shop Drawing is RM 10,000.
10. Find the budget of each work package.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 292 of 456
11. To calculate the work package weight factor use this formula:
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿6𝑊𝐹) = × 100%
𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐴𝑐𝑐𝑜𝑢𝑛𝑡 𝐵𝑢𝑑𝑔𝑒𝑡
Example:
2,150
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 𝑊𝐹 (𝐿6 𝑊𝐹) = × 100% = 21.5 %
10,000
12. (L5 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿5𝑊𝐹)
𝑊𝐹 (𝐿5 𝑊𝐹) =
100%
Example:
(21.5% × 5.25%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 (𝐿5 𝑊𝐹) = = 1.13 %
100%
13. (L4 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿4𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿4 𝑊𝐹) =
100%
Example:
(21.5% × 3.68%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 (𝐿4 𝑊𝐹) = = 0.79 %
100%
14. (L3 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿3𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿3 𝑊𝐹) =
100%
Example:
(21.5% × 1.71%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 (𝐿3 𝑊𝐹) = = 0.37 %
100%
15. (L2 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿2𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿2 𝑊𝐹) =
100%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 293 of 456
Example:
(21.5% × 1.11%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 (𝐿2 𝑊𝐹) = = 0.239 %
100%
16. (L1 WF) for work package is its share portion at Project level rather than its parent level WF
(i.e. Phase) It can be calculated.
(𝐿6𝑊𝐹 × 𝐿1𝑊𝐹)
𝑊𝑜𝑟𝑘 𝑃𝑎𝑐𝑘𝑎𝑔𝑒 𝑊𝐹 (𝐿1 𝑊𝐹) =
100%
Example:
(21.5% × 1%)
𝑃𝑟𝑜𝑐𝑒𝑠𝑠 (𝐿1 𝑊𝐹) = = 0.215 %
100%
Budget
Control Work Budget (L6WF)% (L5WF)% (L4WF)% (L3WF)%
(RM (L5 WF)% (L2 WF)% (L1 WF)%
Account Packages (RM '000)
'000)
Engineering
/Shop 10,000 5.25
Drawing
General 750 7.5 0.39 0.28 0.13 0.083 0.075
Process 2,150 21.5 1.13 0.79 0.37 0.239 0.215
Equipment 1,300 13 0.68 0.48 0.22 0.144 0.13
Civil &
1,100 11 0.58 0.4 0.19 0.122 0.11
Structural
Piping 2,250 22.5 1.18 0.83 0.38 0.25 0.225
Electrical 950 9.5 0.5 0.35 0.16 0.105 0.095
Instrument 1,100 11 0.58 0.4 0.19 0.122 0.11
Other 400 4 0.21 0.15 0.07 0.044 0.04
Total 10,000 100 5.25 3.68 1.71 1.11 1.00
Weight factor for Level 7 shall be calculated based on budgeted cost/man hour.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 294 of 456
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Progress of each pre-bidding item is calculated as per
following stages:
WF for
Stages Description
Stages
ITB
Stage 3 - If the ITB is issued equal to 100% 50%
otherwise 0%
Weight
Sub
Factor Description of
Control Account Code. Phase Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Sub-Phase
Code.
Base
Progress of each bidding item is calculated as per following
Bidding/ stages:
- A2 Man-Hour Evaluate/ Work Step
Award WF for
Stages Description
Stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 295 of 456
RFQ
Stage 1 - If the Inquiry is issued equal to 10%
100% otherwise 0%
TBE
Stage 2 - If the TBE is performed equal to 25%
100% otherwise 0%
CBE
Stage 3 -, If the CBE is performed equal to 25%
100% otherwise 0%
PETRONAS Approval of Award
- If the vendor/contractor is selected
Stage 4 40%
and PO place equal to 100%
otherwise 0%
Control Account: Project Control Initiation
Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base
1 Start 5.00%
2 Finish 95.00%
Environment
Milestone Description WF for
Preliminary
142 Work Step stages
Assessment &
1 Perform Assessment 60.00%
Report
2 Issue Final Report 40.00%
Control Account: HSE
Weight
Work
Factor Description of
Control Account Code. Package Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation Work Package
Code.
Base
WF for
Stages Description
Stages
ITB
Stage 3 - If the ITB is issued equal to 50%
100% otherwise 0%
Sub Phase: B2-Bidding
Weight
Sub
Factor Description of Sub- Calculation Description, Detailed Weight Factor or
Control Account Code. Phase Methodology
Calculation Phase Formula
Code.
Base
Bidding/ Evaluate/ Progress of each bidding item is calculated as per
- B2 Man-Hour Work Step
Award following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 302 of 456
WF for
Stages Description
Stages
RFQ
Stage 1 - If the Inquiry is issued equal 10%
to 100% otherwise 0%
TBE
Stage 2 - If the TBE is performed equal 25%
to 100% otherwise 0%
WF for
Stages Description
Stages
ITB
Stage 3 - If the ITB is issued equal to 50%
100% otherwise 0%
Sub Phase: C2-Bidding
Weight
Sub Description
Factor
Control Account Code. Phase of Sub- Methodology Calculation Description, Detailed Weight Factor or Formula
Calculation
Code. Phase
Base
Progress of each bidding item is calculated as per following
- C2 Man-Hour Work Step
stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 310 of 456
WF for
Stages Description
Stages
RFQ
Stage 1 - If the Inquiry is issued equal to 10%
100% otherwise 0%
Bidding/ TBE
Evaluate/ Stage 2 - If the TBE is performed equal to 25%
Award 100% otherwise 0%
CBE
Stage 3 -, If the CBE is performed equal to 25%
100% otherwise 0%
PETRONAS Approval of Award
- If the vendor/contractor is
Stage 4 40%
selected and PO place equal to
100% otherwise 0%
Control Account: General, Process, Structural, Mechanical, Piping, Electrical, Instrument and Telecommunication, Civil, Pipelines, Architecture, HSE (Fire
and Safety), HVAC, Others
Weight
Work
Factor Description of Calculation Description, Detailed Weight Factor or
Control Account Code. Package Methodology
Calculation Work Package Formula
Code.
Base
DA,DB,DC,DD,DE,DF,DG,DH,DK,
311 Man-Hour CTR Deliverables Work Step Refer Appendix 5
DI,DK,DL, DM
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 311 of 456
FEED
Control Account DA: General
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of general procedures calculated as per following stages:
WF for
Stages Description
All Type of Stages
Man-Hour Work Step
documents Stage 1 Start 10%
Stage 2 Issued for Information 80%
Stage 3 Final Update 10%
Control Account DB: Process
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each PFD and P&ID is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
Man-Hour P&ID, PFD, HMB Work Step Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for HAZOP 10%
Stage 5 Issue for Approval 10%
Stage 6 Approved for Detailed Design 20%
Man-Hour Progress of each document is calculated as per following stages:
Other Process WF for
Work Step Stages Description
Documents Stages
Stage 1 Start 10%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 316 of 456
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
All Type of Stage 1 Start 10%
Man-Hour Work Step
documents Stage 2 Issue for Internal Discipline check 30%
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%
Control Account DH: Civil
Description of
Weight Factor Calculation Base Methodology Calculation Description, Detailed Weight Factor or Formula
Document
Progress of each document is calculated as per following stages:
WF for
Stages Description
Stages
Stage 1 Start 10%
All Type of
Man-Hour Work Step Stage 2 Issue for Internal Discipline check 30%
documents
Stage 3 Issued for Review 20%
Stage 4 Issue for Approval 20%
Stage 5 Approved for Detailed Design 20%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 319 of 456
WF for
Stages Description
Stages
Tender Plan
Stage 1 -as per each equipment, if the Tender Plan is issued 30%
411 10% Work Step equal to 100% otherwise 0%
Pre-Bidding
PIR
Stage 2 -as per each equipment, if the PIR is performed equal to 40%
100% otherwise 0%
ITB
Stage 3 -as per each equipment, if the ITB is issued equal to 30%
100% otherwise 0%
TBE
Stage 2 -as per each equipment, if the TBE is performed equal to 25%
100% otherwise 0%
CBE
Stage 3 -as per each equipment, if the CBE is performed equal 25%
to 100% otherwise 0%
WF for
Stages Description
Stages
Manufacturing & Delivery of
413 70% Work Step Engineering
Major Equipment
Stage 1 -If step is done the value would be 100 and if it hasn’t 7%
been done yet, it would be 0.
Procurement
Stage 2 - If step is done the value would be 100 and if it hasn’t 40%
been done yet, it would be 0.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 331 of 456
WF for
Stages Description
Stages
Tender Plan
Stage 1 -as per each equipment, if the Tender Plan is issued out 30%
411 10% Work Step to vendor/manufacturer equal to 100% otherwise 0%
Pre-Bidding
PIR
Stage 2 -as per each equipment, if the PIR is performed equal to 40%
100% otherwise 0%
ITB
Stage 3 -as per each equipment, if the ITB is issued equal to 30%
100% otherwise 0%
WF for
Stages Description
Bid/ Evaluate/ Award of Stages
412 20% Work Step
Contract
RFQ
Stage 1 -as per each equipment, if the Inquiry is issued equal to 10%
100% otherwise 0%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 333 of 456
WF for
Stages Description
Stages
FOB
Manufacturing & Delivery of Stage 1 - If step is done the value would be 100 and if it hasn’t 85%
413 70% Work Step been done yet, it would be 0.
Bulk Material
Delivered at Port
Stage 2 - If step is done the value would be 100 and if it hasn’t 10%
been done yet, it would be 0.
Delivered at Site
5%
Stage 3 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 334 of 456
WF for
Stages Description
Stages
RFQ
Stage 1 -as per each equipment, if the Inquiry is issued equal to 10%
100% otherwise 0%
CBE
Stage 3 -as per each equipment, if the CBE is performed equal 25%
to 100% otherwise 0%
WF for
Stages Description
Stages
Engineering
Stage 1 -If step is done the value would be 100 and if it hasn’t 7%
been done yet, it would be 0.
Procurement
Stage 2 - If step is done the value would be 100 and if it hasn’t 40%
been done yet, it would be 0.
Fabrication
30%
Manufacturing and Delivery of Stage 3 - If step is done the value would be 100 and if it hasn’t
613 80% Work Step been done yet, it would be 0.
Major Equipment
Final Testing (FAT)
5%
Stage 4 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
FOB
3%
Stage 5 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Site
13%
Stage 7 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Close out Report
2%
Stage 8 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 336 of 456
WF for
Stages Description
Stages
RFQ
-as per each equipment, if the Inquiry is issued equal to
Stage 1 10%
100% otherwise 0%
TBE
Bid/ Evaluate/ Award of -as per each equipment, if the TBE is performed equal to
612 20% Work Step Stage 2 25%
Contract 100% otherwise 0%
CBE
-as per each equipment, if the CBE is performed equal
Stage 3 25%
to 100% otherwise 0%
WF for
Stages Description
Stages
FOB
85.0%
Stage 1 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Port
10.0%
Stage 2 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
Delivered at Site
5.0%
Stage 3 - If step is done the value would be 100 and if it hasn’t
been done yet, it would be 0.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 338 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Reinforcement Installation 15.00%
Stage 5 Pouring 45.00%
Stage 6 Casing Recovery 10.00%
Stage 7 Integrity Test 5.00%
Infrastructures (Road, Railway, Drainage, etc.) Progress is subjected to Asphalt laying methods & Yards and
& Landscapes measured as per following stages:
Stage Description WF for
stages
Stage 1 Sub-base preparation 10.00%
Work Step Stage 2 Base rolling 5.00%
Asphalt roads and yards Stage 3 Quarry mix foundation 30.00%
Stage 4 Compacting and Stabilizing 25.00%
Stage 5 Binder 15.00%
Stage 6 Wear surface 10.00%
WP - 814
Stage 7 Misc. finishing 5.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Earth roads and yards Work Step Stage 1 Ground preparation 10.00%
Stage 2 Foundation 40.00%
Stage 3 Crushed stones 30.00%
Stage 4 Rolling 10.00%
Stage 5 Finishing works 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 340 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Trenching and measured as per
following stages:
Stage Description WF for
stages
Earth and Sand Trenches (Trenching) Work Step
Stage 1 Excavation 50.00%
Stage 2 Sand bed 10.00%
Stage 3 Sand filling 10.00%
Stage 4 Top Brick / Red lean concrete 20.00%
Stage 5 Sand filling 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Work Shop and measured as per
following stages:
Stage Description WF for
Work Shop Work Step stages
Stage 1 Workshops - Building 40.00%
Stage 2 Workshops - Equipment & Facilities 60.00%
Progress is calculated based on Warehouse and measured as per
following stages:
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Telecommunication Network 15.00%
Stage 6 Water Distribution Network 5.00%
Stage 7 Sewage Network 10.00%
Progress is calculated based on Facilities Demolition & Removal
and measured as per following stages:
Stage Description WF for
Facilities Demolition & Removal Work Step stages
Stage 1 Demolition & Removal 75.00%
Stage 2 Demobilization 25.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Pre-commissioning, Commissioning & Hydro 29.79%
testing
Stage 5 Mobilization and Demobilization for 5.89%
Construction Equipment for Line laying
Works
Stage 6 Mobilization and Demobilization for 2.82%
Construction Equipment for other Works
Progress is calculated based on Onshore Logistic support for
pipeline and measured as per following stages:
Stage Description WF for
Sub Work of Onshore Logistic support (Pipeline) Work Step
stages
Stage 1 Logistic Support for Shore Approach 43.10%
Stage 2 Logistic Support for Laying Operations 56.90%
Progress is calculated based on Onshore / Offshore Logistic
support and measured as per following stages:
Sub Work of Mobilization Manual and
Work Step
Stage Description WF for
Demobilization Inspection Construction Equipment stages
Stage 1 Completion of mobilization of Equipment 50.00%
Stage 2 Demobilization of construction EQUIPMENT 50.00%
Progress is calculated based on Utilities & Facilities and measured
as per following stages:
Stage Description WF for
stages
Utilities & Facilities Work Step
Stage 1 Water and Effluent Treatment 10.00%
Stage 2 Fuel Station 10.00%
Stage 3 Parking, Roads & Fences 25.00%
Stage 4 Power Distribution Network 25.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 344 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Telecommunication Network 15.00%
Stage 6 Water Distribution Network 5.00%
Stage 7 Sewage Network 10.00%
Progress is calculated based on Steel net fencing and measured
Site Preparation
as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Work Step Stage 3 10.00%
Formwork
Steel Net Fencing
Stage 4 Reinforcement 10.00%
Stage 5 Pouring 10.00%
Stage 6 Stripping/backfill 5.00%
Stage 7 Fencing installation 50.00%
WP - 818 Stage 8 5.00%
Misc. finishing work
Progress is calculated based on Pre-Fabricated Elements fencing
and measured as per following stages:
Stage Description WF for
Pre-Fabricated Elements fencing Work Step
stages
Stage 1 Complete - in Meter 90.00%
Stage 2 Acceptance - in Meter 10.00%
Progress is calculated based on Gates and measured as per
following stages:
Gates Work Step Stage Description WF for
stages
Stage 1 Complete - No. of Gates 90.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 345 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Acceptance - No. of Gates 10.00%
Progress is calculated based on Removal of Trees and measured
Earth Works
as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Ground preparation 5.00%
Removal of Trees
Stage 2 Trees cutting 40.00%
Stage 3 Roots removal 35.00%
Stage 4 Transportation 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Sheet piling and dewatering and
measured as per following stages:
Stage Description WF for
stages
Sheet piling and dewatering Work Step
Stage 1 Sheet piles driving 50.00%
Stage 2 Reinforcing beams 20.00%
Stage 3 Dewatering 20.00%
Stage 4 Sheet piles extraction 10.00%
Progress is calculated based on Soil scrubbing and measured as
per following stages:
Stage Description WF for
Soil scrubbing Work Step
stages
Stage 1 Scrubbing 80.00%
Stage 2 Final Grading 20.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 10.00%
Earth Dykes Work Step
Stage 2 Dyke execution
65.00%
Stage 4 10.00%
Finishing work
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Excavation 20.00%
Stage 2 Base rolling 5.00%
Stage 3 Pad formation 55.00%
Stage 4 Surface layer 10.00%
Stage 5 Bitumen layer 3.00%
Stage 6 Pad slope profiling 7.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean Concrete 5.00%
Stage 3 Rebar 25.00%
Tanks Foundation Work Step
Stage 4 Form Work 12.00%
Stage 5 Casting Concrete for Foundation 20.00%
Stage 6 Form Work Pedestal 8.00%
Stage 7 Steel Plate 5.00%
Stage 8 Casting Concrete for Pedestal 15.00%
Stage 9 Final/Backfill
5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Excavation 10.00%
Stage 2 Base rolling 20.00%
Stage 3 Gravel or crushed stone laying 70.00%
Progress is calculated based on Acid and measured as per
following stages:
Stage Description WF for
stages
Acid Resistant Lining Work Step Stage 1 Surface cleaning 10.00%
Stage 2 Acid resistant layers or tiles 70.00%
Stage 3 Joint & sealing 15.00%
Stage 4 Finishing 5.00%
Progress is calculated based on Acid Resistant Lining and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Sub-base preparation 10.00%
Stage 2 Base rolling 5.00%
Asphalts roads and yards Work Step
Stage 3 Quarry mix foundation 30.00%
Stage 4 Compacting & Stabilizing 25.00%
Stage 5 Binder 15.00%
Stage 6 Wear surface 10.00%
Stage 7 Misc. finishing 5.00%
Progress is calculated based on Earth roads & Yards and
measured as per following stages:
Earth roads and yards Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 349 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Ground preparation 10.00%
Stage 2 Foundation 40.00%
Stage 3 Crushed stones 30.00%
Stage 4 Rolling 10.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Concrete paving and measured as
per following stages:
Stage Description WF for
Concrete Paving Work Step stages
Stage 1 Prep., slope setting, reinforcement 60.00%
Stage 2 Wire netting installation, pouring 25.00%
Stage 3 Finishing works 15.00%
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Concrete Cable Trenches Work Step Stage 3 Reinforcement 20.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping 5.00%
Stage 7 Sand bed 20.00%
Stage 8 Concrete covers 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 350 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on quantity of work done and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Pulling Pits Work Step Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 25.00%
Stage 4 Formworks 15.00%
Stage 5 Pouring 35.00%
Stage 6 Formworks stripping & backfill 15.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on issued General Engineering
documents to the COMPANY and measured as per following
stages:
Stage Description WF for
stages
WP - 819 General Work Step
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Equipment documents to
the COMPANY and measured as per following stages:
Stage Description WF for
stages
WP - 821 Equipment Work Step Stage 1 Start 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Electrical documents to
the COMPANY and measured as per following stages:
Stage Description WF for
WP - 824 Electrical Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Instrument &
Communication documents to the COMPANY and measured as
per following stages:
Stage Description WF for
WP - 825 Instrument & Communication Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on issued Other Engineering
documents to the COMPANY and measured as per following
stages:
Stage Description WF for
WP - 826 Other Engineering Work Step stages
Stage 1 Start 5.00%
Stage 2 Issued for Review 55.00%
Stage 3 Approval for Construction 40.00%
Progress is calculated based on Cast in situ driven piles and
WP - 813 Piling - Driven in place piles hammered Work Step
measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 353 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Casing Installation 10.00%
Cast in Situ driven piles Stage 2 Reinforcing Installation 30.00%
Stage 3 Pouring 45.00%
Stage 4 Casing Recovery 10.00%
Stage 5 Integrity test 5.00%
Progress is calculated based on Concrete Pre-cuts driven piles
and measured as per following stages:
Stage Description WF for
Concrete Pre-cuts driven piles Work Step stages
Stage 1 Material at Site 20.00%
Stage 2 Installation 75.00%
Stage 3 Integrity test 5.00%
Progress is calculated based on Steel driven Piles and measured
as per following stages:
Stage Description WF for
Steel driven piles Work Step stages
Step 1 Material at Site 20.00%
Step 2 Installation 75.00%
Step 3 Integrity test 5.00%
Progress is calculated based on Wooden driven Piles and
measured as per following stages:
Wooden driven piles Work Step Stage Description WF for
stages
Stage 1 Material at Site 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 354 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Installation 75.00%
Stage 3 Integrity test 5.00%
CIVIL WORKS
Progress is calculated based on Concrete Foundation for
Concrete Works - Foundations
Equipment & Structural and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Work Step Stage 3 Reinforcement 25.00%
Concrete Foundation for Equipment & Structural Stage 4 Formworks 20.00%
Stage 5 Anchor bolts/plates 10.00%
Stage 6 Concrete pouring 15.00%
Stage 7 Formworks stripping, concrete protection &
10.00%
WP - 827 backfill
Stage 8 Grouting 10.00%
Progress is calculated based on Prefabrication of concrete
foundations and measured as per following stages:
Stage Description WF for
stages
Prefabrication of concrete foundations Work Step Stage 1 Reinforcement 25.00%
Stage 2 Formworks 20.00%
Stage 3 Anchor bolts/plates 20.00%
Stage 4 Concrete pouring 35.00%
Progress is calculated based on Precast of concrete foundations
Precast on of concrete foundations installation Work Step
installation and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 355 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Stage 3 Foundation installation 55.00%
Stage 4 Concrete protection & backfill 10.00%
Stage 5 Grouting 10.00%
Stage 6 Finishing 15.00%
Progress is calculated based on Tanks Rings and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Excavation 10.00%
Stage 2 Lean concrete 5.00%
Tank Rings Work Step
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping, concrete protection &
15.00%
external backfill
Stage 7 Internal backfilling 10.00%
Progress is calculated based on Tanks Rings and measured as per
following stages:
Stage Description WF for
Concrete small foundations Work Step
stages
Stage 1 Surface preparation 10.00%
Stage 2 Reinforcement/formworks 40.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 356 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Pouring 30.00%
Stage 4 Grouting 10.00%
Stage 5 Formworks stripping & finishing 10.00%
Progress is calculated based on concrete large massive
foundations and measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Concrete large massive foundations Work Step Stage 3 Reinforcement 20.00%
Stage 4 Formworks 15.00%
Stage 5 Anchor bolts/plates 10.00%
Stage 6 Pouring 25.00%
Stage 7 Grouting 10.00%
Stage 8 Formworks stripping & backfill 10.00%
Progress is calculated based on Concrete elevated structures cast
Elevation Concrete
in situ l and measured as per following stages:
Stage Description WF for
stages
Stage 1 Formworks 25.00%
Work Step Stage 2 Reinforcement 25.00%
Concrete elevated structures cast in situ
Stage 3 Anchor bolts/plates 15.00%
Stage 4 Pouring 20.00%
Stage 5 Formworks stripping 10.00%
Stage 6 Finishing works 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 357 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Concrete structures
prefabrication and measured as per following stages:
Stage Description WF for
stages
Concrete structures prefabrication Work Step
Stage 1 Reinforcement 25.00%
Stage 2 Formworks 20.00%
Stage 3 Anchor bolts/plates 20.00%
Stage 4 concrete pouring 35.00%
Progress is calculated based on Precast concrete structures
erection and measured as per following stages:
Stage Description WF for
stages
Stage 1 Columns installation 30.00%
Precast concrete structures erection Work Step Stage 2 Grouting on footings 10.00%
Stage 3 Lengthwise beams installation 20.00%
Stage 4 Transverse beams installation 20.00%
Step 5 Beams grouting 10.00%
Step 6 Finishing works 10.00%
Progress is calculated based on Concrete paving and measured as
Concrete Paving / Roads / Yards
per following stages:
Stage Description WF for
Work Step stages
Concrete Paving Stage 1 Prep., slope setting, reinforcement 60.00%
Stage 2 Wire netting installation, pouring 25.00%
Stage 3 Finishing works 15.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 358 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
U/G civil works ( pits, duct banks, cable Progress is calculated based on Concrete cable trenches and
trenches ) measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 2 Lean concrete 5.00%
Work Step
Stage 3 Reinforcement 20.00%
Concrete cable trenches
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Formworks stripping 5.00%
Stage 7 Sand bed 20.00%
Stage 8 Concrete covers 5.00%
Progress is calculated based on Pulling Pits and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Puling Pits Work Step
Stage 2 Lean concrete 5.00%
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 25.00%
Stage 5 Pouring 30.00%
Stage 6 Formworks stripping & backfill 15.00%
Progress is calculated based on Duct Banks and measured as per
following stages:
Duct Banks Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 359 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Excavation 20.00%
Stage 2 PVC conduit positioning 40.00%
Stage 3 Concrete pouring 40.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on cast in situ sleepers and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Stage 8
Backfill 5.00%
Concrete Basin
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring 20.00%
Stage 6 Joints sealing 5.00%
Stage 7 Formworks stripping, concrete protection &
15.00%
backfill
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 361 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Finishing works 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Lean concrete 10.00%
Stage 3 Sleepers installation 60.00%
Stage 4 Backfill 15.00%
Stage 5 Finishing works 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Reinforcement 5.00%
Stage 4 Formworks 20.00%
Stage 5 Pouring /application 30.00%
Stage 6 Formworks stripping 20.00%
Stage 7 Finishing works 10.00%
BUILDINGS Progress is calculated based on subs-station and measured as per
Concrete & Masonry Buildings following stages:
Stage Description WF for
stages
Work Step Stage 1 Concrete foundations 30.00%
Substation Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on control room and measured as
per following stages:
Stage Description WF for
stages
Control room Work Step Stage 1 Concrete foundations 30.00%
Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Other buildings and measured as
Other buildings per following stages:
Work Step
(administration, laboratory, canteen ...) Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 364 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Concrete foundations 30.00%
Stage 2 Concrete elevated structure 30.00%
Stage 3 Concrete slabs 15.00%
Stage 4 Roof slab 15.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Curtain and partition walls and
Building Secondary Works measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Material at site 10.00%
Curtain and partition walls Stage 2 Hollow block 30.00%
Stage 3 Internal plastering 25.00%
Stage 4 Internal painting 25.00%
Stage 5 Finishing works 10.00%
Progress is calculated based on Doors & windows and measured
as per following stages:
Stage Description WF for
Doors & windows Work Step stages
Stage 1 Material at site 10.00%
Stage 2 Windows / doors installation 45.00%
Stage 3 Accessories installation 45.00%
Progress is calculated based on Flooring and measured as per
following stages:
Stage Description WF for
Flooring Work Step
stages
Stage 1 Material at site 20.00%
Stage 2 Installation 70.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 365 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Finishing & cleaning 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Coating 90.00%
Stage 2 Touch-up 10.00%
Progress is calculated based on Roof Insulation & Water
Tightness and measured as per following stages:
Stage Description WF for
stages
Roof Insulation & Water Tightness Work Step Stage 1 Insulation 40.00%
Stage 5
Electrical installation 13.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 8 Functional checks 3.00%
Progress is calculated based on Power & Lighting and partition
Power / Lighting / Lightning
walls and measured as per following stages:
Stage Description WF for
stages
Stage 1 Material at site 10.00%
Work Step Stage 2 Cable pulling 30.00%
Power & Lighting
Stage 3 Lighting fixtures installation 20.00%
Stage 4 Outlets & switches installation 20.00%
Stage 5 Panel installation 15.00%
Stage 6 Functional checks 5.00%
Progress is calculated based on Lightning system and measured
as per following stages:
Stage Description WF for
Lightning system Work Step
stages
Stage 1 Equipment installation 90.00%
Stage 2 Checks 10.00%
Progress is calculated based on Communication / security
systems and measured as per following stages:
Stage Description WF for
stages
Communication / security systems Work Step Stage 1 Material at site 10.00%
Stage 2 Equipment installation 30.00%
Stage 3 Cable pulling & Connections 50.00%
Stage 4 Functional checks 10.00%
Progress is calculated based on Fire detection and partition walls
Fire detection / fighting Work Step
and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 368 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Material at site 10.00%
Fire detection
Stage 2 Equipment installation 30.00%
Stage 3 Cable pulling & Connections 50.00%
Stage 4 Functional checks 10.00%
Progress is calculated based on Fire detection and partition walls
and measured as per following stages:
Stage Description WF for
stages
Fire fighting system Work Step Stage 1 Material at site 5.00%
Stage 2 Piping prefabrication & install. 35.00%
Stage 3 Piping painting 20.00%
Stage 4 Sprinkler installation 20.00%
Stage 5 Functional test 20.00%
STORAGE TANKS AND SILOS Progress is calculated based on Fixed roof tanks (altern.I) and
Steel Tanks - Fixed Roof Tanks measured as per following stages:
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Positioning and tack weld 15.00%
Stage 2 Full weld/fixing 70.00%
Stage 3 X-rays 11.00%
Stage 4 Testing 4.00%
Progress is calculated based on Fixed roof with floating plate
tanks (altern. I) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Base 17.00%
Fixed roof with floating plate tanks (altern.) I) Stage 2 Shell 35.00%
Work Step
Stage 3 Floating plate 25.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Sphere and measured as per
Sphere Tank
following stages:
Stage Description WF for
stages
Work Step Stage 1 Erection 30.00%
Sphere Stage 2 Meridian/vertical welds 30.00%
Stage 3 Equatorial/circumferential. welds 10.00%
Stage 4 NDT 20.00%
Stage 5 Cleaning, testing 10.00%
Progress is calculated based on Double Wall tanks and measured
Cryogenic Tank
as per following stages:
Stage Description WF for
stages
Stage 1 Base 17.00%
Work Step Stage 2 Inner shell (nickel) 28.00%
Double wall tanks
Stage 3 Outer shell (carbon steel) 20.00%
Stage 4 Roof 28.00%
Stage 5 Accessories 3.00%
Stage 6 Testing 4.00%
Progress is calculated based on other tanks and measured as per
following stages:
Stage Description WF for
stages
Other Tanks Work Step Stage 1 Bottom Plates 17.00%
Stage 2 Shell Plates 28.00%
Stage 3 Roof & Cover 20.00%
Stage 4 Accessories & Others 3.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 371 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Hydro test 3.00%
Stage 6 Painting 4.00%
Hoisting and Equipment (Mechanical) Progress is calculated based on Heavy vessels w fixed lifting and
Erection measured as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Erection on Foundation 60.00%
Heavy Vessels with fixed lifting and assembly
Stage 2 Levelling, plumb adjustment 5.00%
Stage 3 Pneumatic & Hydrostatic testing 25.00%
Stage 4 Final inspect., Manholes closure 10.00%
Progress is calculated based on Heavy vessels w fixed cranage
and measured as per following stages:
Stage Description WF for
Vessels parts lifting and assembly stages
WP 829 Stage 1 Shell assembly & welding 40.00%
Stage 2 Tracing & Welding of Nozzles and
10.00%
Manholes
Work Step
Stage 3 Tray support installation 5.00%
Stage 4 X-ray examination 5.00%
Stage 5 Installation 20.00%
Stage 6 Circum, welding & x-ray exam 5.00%
Stage 7 Plumb adjustment 5.00%
Stage 8 Final hydrostatic testing 10.00%
FIRE EQUIPMENT ERECTION Progress is calculated based on Heavy vessels w fixed cranage
Furnaces and measured as per following stages:
Work Step
Stage Description WF for
Preassembled Furnaces
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 372 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Erection on Foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt
30.00%
tightening
Stage 3 Final inspect., Manholes closure 20.00%
Progress is calculated based on Heavy vessels w fixed cranage
and measured as per following stages:
Stage Description WF for
stages
Stage 1 Shell assembly & welding/bolting 20.00%
Stage 2 Refractory panels/mater, erect 15.00%
Partially preassembled Furnaces Work Step
Stage 3 Coils welding & erection 20.00%
Stage 4 Installation on foundation 10.00%
Stage 5 Stack and Flue ducts weld/bolt 15.00%
Stage 6 Accessories & Structures erect. 10.00%
Stage 7 X-ray examination 8.00%
Stage 8 Final alignment & Final inspection 2.00%
Progress is calculated based on Preassembled boilers and
measured as per following stages:
Stage Description WF for
Preassembled boilers Work Step stages
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Partially preassembled boilers
and measured as per following stages:
Partially preassembled boilers Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 373 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Shell assembly & welding/bolting 20.00%
Stage 2 Refractory panels/mater erect. 15.00%
Stage 3 Coils welding & erection 20.00%
Stage 4 Installation on foundation 10.00%
Stage 5 Stack and flue ducts weld./bolt. 15.00%
Stage 6 Accessories & structures erect. 10.00%
Stage 7 X-ray examination 8.00%
Stage 8 Final alignment final inspection 2.00%
Progress is calculated based on Flares and measured as per
following stages:
Stage Description WF for
stages
Flares Work Step Stage 1 Structure Erection 50.00%
Stage 2 Riser Pipe 20.00%
Stage 3 Alignment 10.00%
Stage 4 Accessories 10.00%
Stage 5 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Module erection and measured as
MODULES FABRICATION AND ERECTION
per following stages:
Stage Description WF for
Work Step stages
Module erection Stage 1 Erection on foundation 70.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Final inspect., manholes closure 10.00%
MACHINERY ERECTION Progress is calculated based on Belt conveyors and measured as
Machinery ( Not Require for Alignment) per following stages:
WP 829
Stage Description WF for
stages
Stage 1 Frames installation 30.00%
Work Step Stage 2 Rollers installation 15.00%
Belt conveyors Stage 3 Belt installation 15.00%
Stage 4 Belt joint execution 10.00%
Stage 5 Accessories 10.00%
Stage 6 Counterweight 10.00%
Stage 7 Final check 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Blade connection & alignment 25.00%
Stage 6 Final inspection 5.00%
Progress is calculated based on Horizontal pumps and drive and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection on foundation 25.00%
Horizontal pumps and drive Work Step
Stage 2 Levelling, bolt tightening 10.00%
Stage 3 Prelim. alignment with motor 25.00%
Stage 4 Cold alignment with piping 30.00%
Stage 5 Final inspection 5.00%
Stage 6 Cleaning, maintenance 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Installation on foundation 20.00%
Stage 2 Cylinder installation 10.00%
Stage 3 Levelling, bolt tightening 10.00%
Stage 4 Motor installation 15.00%
Stage 5 Prelim. cylinder installation 10.00%
Stage 6 Utility line installation 10.00%
Stage 7 Cleaning of cylinder suction valves 10.00%
Stage 8 Final alignment, final inspection 15.00%
Progress is calculated based on Centrifugal compressors and drive
and measured as per following stages:
Stage Description WF for
stages
Centrifugal compressors and drive Work Step Stage 1 Installation on foundation 20.00%
Stage 2 Levelling, bolt tightening 15.00%
Stage 3 Motor installation 10.00%
Stage 4 Prelim. cylinder installation 15.00%
Stage 5 Utility line installation 15.00%
Stage 6 Cleaning of cylinder suction valves 5.00%
Stage 7 Final alignment, final inspection 15.00%
Stage 8 Maintenance 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Blades installation 20.00%
Stage 4 Motor installation 20.00%
Stage 5 Accessories installation 15.00%
Stage 6 Final alignment, final inspection 5.00%
Machinery - Internal Installation Progress is calculated based on Tray Installation and measured
Tray Installation as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Transport to jobsite 10.00%
Trays
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Distributors, grids, demisters, etc.
and measured as per following stages:
Stage Description WF for
stages
Distributors, grids, demisters, etc. Work Step Stage 1 Transport to jobsite 10.00%
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Inert Packing and measured as
Filling materials ( catalyst & packing )
per following stages:
Stage Description WF for
Work Step
stages
Inert Packing
Stage 1 Transport to jobsite 10.00%
Stage 2 Erection 70.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 378 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Chemicals, desiccant, catalysts
and measured as per following stages:
Stage Description WF for
stages
Chemicals, desiccant, catalysts Work Step
Stage 1 Transport to jobsite 10.00%
Stage 2 Erection 70.00%
Stage 3 Cleaning, testing 15.00%
Stage 4 Final inspection 5.00%
Progress is calculated based on Air coolers erection and
Air Coolers & Cooling Towers
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Ground Structure Pre-Assembly 40.00%
Air Cooler Erection Stage 2 Structure & Bundles erection 10.00%
Stage 3 Fans & Motors Installation 20.00%
Stage 4 Alignment 20.00%
Stage 5 Final Inspection 10.00%
Progress is calculated based on Package and Miscellaneous
Package and Miscellaneous Erection Erection and measured as per following stages:
Stage Description WF for
Work Step stages
Skid mounted packages Stage 1 Installation on foundation 30.00%
Stage 2 Assembling of skids/equipment 20.00%
Stage 3 Disassembled parts erection 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 379 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Levelling, bolt tightening 15.00%
Stage 5 Tot skid/package level, bolt tighten. 10.00%
Stage 6 Final inspection 5.00%
Progress is calculated based on Items in one piece and measured
Heavy Lift
as per following stages:
Stage Description WF for
Work Step stages
Items in one piece Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Items in several pieces ( typical
for 3 pieces) and measured as per following stages:
Items in several pieces
Work Step Stage Description WF for
( typical for 3 pieces)
stages
Stage 1 1st Part Erection on foundation 10.00%
Stage 2 2nd Part Erection on foundation 10.00%
Stage 3 Welding & X-ray examination 20.00%
Stage 4 3rd Part Erection on foundation 10.00%
Stage 5 Welding & X-ray examination 20.00%
Stage 6 Levelling, plumb adjustment, bolt tightening 10.00%
Stage 7 Final inspect., manholes closure 20.00%
Progress is calculated based on Vertical vessels/exchangers (shop
Static Equipment
assembled) and measured as per following stages:
Work Step Stage Description WF for
Vertical vessels/exchangers (shop assembled) stages
Stage 1 Erection on foundation 50.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 380 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Stage Description WF for
stages
Horiz. vessels/exchangers (shop assembled) Work Step Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 30.00%
Stage 3 Final inspect., manholes closure 20.00%
Progress is calculated based on Vert. vessels/exch. (shop
assemble.) with testing and measured as per following stages:
Stage Description WF for
stages
Vert. vessels/exch. (shop assemble.) with testing Work Step
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Testing 20.00%
Stage 4 Final inspect., manholes closure 10.00%
Progress is calculated based on Horiz. vessels/exch. (shop
assemble.) with testing and measured as per following stages:
Stage Description WF for
stages
Horiz. vessels/exch. (shop assemble.) with testing Work Step
Stage 1 Erection on foundation 50.00%
Stage 2 Levelling, plumb adjustment, bolt tightening 20.00%
Stage 3 Testing 20.00%
Stage 4 Final inspect., manholes closure 10.00%
STEEL STRUCTURE Progress is calculated based on Trestle structures and measured
Main Structural Steel Erection as per following stages:
WP-830 Work Step
Stage Description WF for
Trestle structures
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 381 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Assembly 20.00%
Stage 2 Erection 33.00%
Stage 3 Alignment 14.00%
Stage 4 Welding and/or bolting 26.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 3.00%
Progress is calculated based on Process structures and measured
as per following stages:
Stage Description WF for
stages
Stage 1 Assembly 19.00%
Process structures Work Step Stage 2 Erection 37.00%
Stage 3 Alignment 13.00%
Stage 4 Welding and/or bolting 25.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 2.00%
Progress is calculated based on Pipe racks and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Assembly 21.00%
Pipe racks Work Step
Stage 2 Erection 22.00%
Stage 3 Alignment 14.00%
Stage 4 Welding and/or bolting 36.00%
Stage 5 Cleaning 4.00%
Stage 6 Final check 3.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 382 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Steel Frames and measured as
per following stages:
Stage Description WF for
stages
Steel frames on concrete structures Work Step Stage 1 Erection 40.00%
Stage 2 Alignment 20.00%
Stage 3 Welding and/or bolting 25.00%
Stage 4 Cleaning 5.00%
Stage 5 Final check 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Securing 20.00%
Stage 5 Painting/Touch up 5.00%
Stage 6 Final check 5.00%
Progress is calculated based on Gratings and measured as per
following stages:
Stage Description WF for
stages
Checkered plates Work Step
Stage 1 Erection 43.00%
Stage 2 Securing 36.00%
Stage 3 Cleaning 14.00%
Stage 4 Check 7.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Erection 23.00%
Stage 3 Alignment 16.00%
Stage 4 Welding and/or bolting 30.00%
Stage 5 Cleaning 5.00%
Stage 6 Final check 3.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Ladders & Handrails and
CLADDING
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 15.00%
Stage 2 Thermal sheet erection 25.00%
Work Step Stage 3 Thermal sheet fastening 10.00%
Siding and roofing
Stage 4 External sheet erection 20.00%
Stage 5 External sheet bolting/fixing 10.00%
Stage 6 Accessories erection 15.00%
Stage 7
Final check 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Sectioning 25.00%
Stage 2 Assembly, tack welding 20.00%
Stage 3 Welding 30.00%
Stage 4 X-ray examination 10.00%
Stage 5 Stress relieving 10.00%
Stage 6 Transport to storage area 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Hydro test 13.00%
Stage 8
Finishing works, Final Check 2.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on underground Piping on site
Fabrication and erection and measured as per following stages:
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Material Preparation, select & transport 5.00%
Stage 2 Pipe fabrication, erection 35.00%
Stage 3 X-ray examination 25.00%
Stage 4 Testing 10.00%
Stage 5 Bitumizing of welded parts 10.00%
Stage 6 Final check 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 Sand covering 10.00%
Stage 7 Backfilling 10.00%
Progress is calculated based on Plastic GRP on site Fabrication
Plastic, GRP and erection and measured as per following stages:
Others
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Backfilling 10.00%
Progress is calculated based on Demolition and measured as per
Demolition
following stages:
Stage Description WF for
Work Step stages
Demolitions Stage 1 Ground Preparation 5.00%
Stage 2 Concrete/Masonry demolition 65.00%
Stage 3 Transportation 30.00%
Progress is calculated based on Steel tubing installation and
Steam Tracing
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Tracer installation 40.00%
Steel tubing installation Stage 2 Pre-insulated tubing installation 40.00%
Stage 3 Trays and supports for tubing 10.00%
Stage 4 Test 5.00%
Stage 5 Final check 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Control valve erection and
Miscellaneous / Accessories- Piping
measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Valve erection 80.00%
Control valve erection Stage 2 Bolting 10.00%
Stage 3 Final check 10.00%
Progress is calculated based on Safety valve erection and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection for piping alignment 40.00%
Safety valve erection Work Step Stage 2 Valve dismantling for test 20.00%
Stage 3 Bolting 35.00%
Stage 4 Final check 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Laying of u/g conductor 65.00%
Grounding cable (u/g) with connections
Stage 2 Cord joints/derivations 27.00%
Stage 3 Tests 6.00%
Stage 4 Final inspection 2.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Stub-up and concrete base 30.00%
Stage 3 Connection execution 30.00%
Stage 4 Tests 8.00%
Stage 5 Final inspection 2.00%
Progress is calculated based on Overhead copper conduits
installation and erection and measured as per following stages:
Stage Description WF for
Overhead copper conduits installation Work Step stages
Stage 1 Fittings installation 10.00%
Stage 2 Cord laying and fixing 85.00%
Stage 3 Final inspection 5.00%
Progress is calculated based on Connections of equip to the
grounding network and erection and measured as per following
stages:
Stage Description WF for
Connections of equip to the grounding network Work Step stages
Stage 1 Connection execution 90.00%
Stage 2 Protective paint 8.00%
Stage 3 Final inspection 2.00%
Progress is calculated based on Installation of plates (earthing
bus) and erection and measured as per following stages:
Stage Description WF for
stages
Installation of plates (earthing bus) Work Step Stage 1 Plate prefabrication 30.00%
Stage 2 Plate installation 60.00%
Stage 3 Protective paint 5.00%
Stage 4 Final inspection 5.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 395 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Lightning protection system and
erection and measured as per following stages:
Stage Description WF for
stages
Lightning protection system Work Step
Stage 1 Steel plate installation 60.00%
Stage 2 Rods installation 20.00%
Stage 3 Execution of connections 10.00%
Stage 4 Inspection and tests 10.00%
Sub-Station Installation Progress is calculated based on Transformers and measured as
Transformer per following stages:
Stage Description WF for
stages
Stage 1 Transportation and alignment 20.00%
Work Step
Stage 2 Mechanical connections 5.00%
Transformers
Stage 3 Transformer electrical connection 25.00%
Stage 4 Panel electrical connection 30.00%
Stage 5 Tests 10.00%
Stage 6 Final inspection 10.00%
Progress is calculated based on MCC / Switchgears installation
Electrical Equipment
and measured as per following stages:
Stage Description WF for
Work Step stages
MCC / Switchgears installation Stage 1 Preparation 20.00%
Stage 2 Installation 70.00%
Stage 3 Tests / Checks 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 396 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Bus duct installation and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Supports prefabrication 20.00%
Bus duct installation Work Step
Stage 2 Supports installation 30.00%
Stage 3 Bus duct installation 40.00%
Stage 4 Final Alignment 10.00%
Progress is calculated based on Batteries installation and
measured as per following stages:
Stage Description WF for
stages
Batteries installation Work Step
Stage 1 Supports installation 20.00%
Stage 2 Installation 30.00%
Stage 3 Acid Filling 30.00%
Stage 4 Tests / Checks 20.00%
Progress is calculated based on Diesel generators and
measured as per following stages:
Stage Description WF for
stages
Diesel generator Work Step Stage 1 Erection on foundation 30.00%
Stage 2 Electrical Connections 40.00%
Stage 3 Testing 20.00%
Stage 4 Finals inspect. 10.00%
Progress is calculated based on Cable trays and cable ladder
Cable trays in S/S Work Step
installation and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 397 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Check of tray layout 10.00%
Cable trays and cable ladder installation
Stage 2 Installation of supports 35.00%
Stage 3 Installation of trays 50.00%
Stage 4 Sealing of conduit entering cable room 5.00%
Interconnecting cables connections Progress is calculated based on Interconnecting cables
connection and measured as per following stages:
Stage Description WF for
Work Step
Installation of Interconnecting cables stages
Stage 1 Laying 80.00%
Stage 2 Checks 20.00%
Progress is calculated based on Interconnecting cables
connection and measured as per following stages:
Stage Description WF for
Connection of Interconnecting cables Work Step stages
Stage 1 Terminations 70.00%
Stage 2 Testing 20.00%
Stage 3 Checks 10.00%
ELECTRICAL CABLES
Progress is calculated based on Cable trays and cable ladder
Cable trays and conduits
installation and measured as per following stages:
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Grounding of trays 4.00%
Stage 5 Installation of covers 5.00%
Progress is calculated based on Underground conduits
installation and measured as per following stages:
Stage Description WF for
stages
Underground conduits installation
Work Step Stage 1 Placing supports 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit and stub up 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Progress is calculated based on Above ground conduits
installation and measured as per following stages:
Stage Description WF for
stages
Above ground conduits installation Stage 1 Supports installation 15.00%
Work Step
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Laying of cables 65.00%
Stage 4 Cable markers installation 10.00%
Stage 5 Insulation test 10.00%
Stage 6 Cable way markers 4.00%
Stage 7 Final inspection 1.00%
Progress is calculated based on Cables in trays/ladders and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Handling of cable drums 5.00%
Cables in trays/ladders Work Step
Stage 2 Laying of cables 70.00%
Stage 3 Insulation test 10.00%
Stage 4 Markers installation 10.00%
Stage 5 Final inspection 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Cable connections and measured
Connections
as per following stages:
Stage Description WF for
Work Step stages
Cable connections Stage 1 Terminations 70.00%
Stage 2 Testing 20.00%
Stage 3 Checks 10.00%
Control station installation Progress is calculated based on Control station industrial type
and measured as per following stages:
Stage Description WF for
Work Step stages
Control station Ex type Stage 1 Installation 80.00%
Stage 2 Checks 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Power outlet industrial type and
measured as per following stages:
Stage Description WF for
Control station industrial type Work Step
stages
Stage 1 Installation 80.00%
Stage 2 Checks 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Electrical Tracing and measured
as per following stages:
Stage Description WF for
stages
Electrical Tracing Stage 1 Installation of local panels 10.00%
Work Step
Stage 2 Installation of main junction boxes 10.00%
Stage 3 Heating cable installation 30.00%
Stage 4 Connection of heating cable 30.00%
Stage 5 Tests/Checks 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
INSTRUMENT & TELECOMS WORK Progress is calculated based on Panels/marshalling cabinets and
Control Room Installation Works measured as per following stages:
Stage Description WF for
Work Step stages
Panels/marshalling cabinets Stage 1 Preparation 20.00%
Stage 2 Installation 70.00%
Stage 3 Tests / Checks 10.00%
Progress is calculated based on Cable trays in technical/control
rooms and erection and measured as per following stages:
Stage Description WF for
Cable trays in technical/control rooms
Work Step
stages
Stage 1 Supports 40.00%
Stage 2 Installation 50.00%
WP-833 Stage 3 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Progress is calculated based on Above ground conduits and
measured as per following stages:
Stage Description WF for
stages
Above ground conduits Work Step Stage 1 Supports installation 15.00%
Stage 2 Conduit preparation & bending 25.00%
Stage 3 Laying of conduit 40.00%
Stage 4 Identification of conduit 10.00%
Stage 5 Final inspection 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Handling of cable drums 5.00%
Stage 2 Laying of cables 65.00%
Stage 3 Insulation test 10.00%
Stage 4 Markers installation 10.00%
Stage 5 Final inspection 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Electronic junction boxes and
measured as per following stages:
Junction Box & Local Panels
Stage Description WF for
stages
Stage 1 Erection 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Erection of supports 10.00%
Stage 2 Manifold erection 28.00%
Stage 3 Process connection 30.00%
Local flow indicators Stage 4 Hydrostatic testing 2.00%
Stage 5 Air distribution 22.00%
Stage 6 Pneumatic connections 4.00%
Stage 7 Checks 4.00%
Progress is calculated based on Local flow indicators and
measured as per following stages:
Stage Description WF for
stages
Magnetic flow transmitters Work Step Stage 1 Converter support erection 20.00%
Stage 2 Power cable installation 30.00%
Stage 3 Signal cable installation 30.00%
Stage 4 Electrical connections 10.00%
Stage 5 Transmitter circuit check 10.00%
Progress is calculated based on Electronic flow transmitters and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
Electronic flow transmitters Work Step
Stage 2 Manifold erection 25.00%
Stage 3 Process connection 25.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Cable installation 22.00%
Stage 6 Electrical connections 8.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 409 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Transmitter circuit check 5.00%
Progress is calculated based on Electronic level instruments
Level instrument
(displacement type) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Erection 40.00%
Stage 2 Discharge header erection 50.00%
Stage 3 Hydrostatic testing 10.00%
Progress is calculated based on Electronic pressure transmitters
Pressure Instrument
and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of transmitter and repeater
12.00%
supports
Work Step Stage 2 Manifold erection 20.00%
Electronic pressure transmitters Stage 3 Process connection 20.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Cable installation 25.00%
Stage 6 Electrical connections 10.00%
Stage 7 Transmitter circuit check 10.00%
Progress is calculated based on Local pneumatic pressure
regulators and measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of supports 12.00%
Local pneumatic pressure regulators Work Step Stage 2 Manifold erection 20.00%
Stage 3 Process connection 20.00%
Stage 4 Hydrostatic testing 3.00%
Stage 5 Air distribution 26.00%
Stage 6 Pneumatic connections 9.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 411 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Hydrostatic testing 3.00%
Stage 4 Cable installation 25.00%
Stage 5 Electrical connections 10.00%
Stage 6 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Air distribution 40.00%
Stage 4 Pneumatic connections 10.00%
Stage 5 Checks 10.00%
Progress is calculated based on Local MV electric converters and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Erection of support and repeater 20.00%
Local MV electric converters Work Step
Stage 2 Thermocouple 5.00%
Stage 3 Cable installation 50.00%
Stage 4 Electrical connections 15.00%
Stage 5 Transmitter circuit check 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Trap erection 80.00%
Stage 2 Dial installation 20.00%
Progress is calculated based on Flux stats and measured as per
On line instruments
following stages:
Stage Description WF for
stages
Work Step
Stage 1 Cable installation 70.00%
Flux stats
Stage 2 Electrical connections 20.00%
Stage 3 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 3 Electrical or pneum. connections 5.00%
Stage 4 Line washing 5.00%
Stage 5 Circuit check 5.00%
Progress is calculated based on Control valves with I/P and
pneum. Positioner and measured as per following stages:
Stage Description WF for
stages
Stage 1 I/p erection 15.00%
Control valves with I/P and pneum. Positioner Work Step Stage 2 I/p air distribute. & positioner 40.00%
Stage 3 Cable installation 25.00%
Stage 4 Electrical connections 4.00%
Stage 5 Pneumatic connections 10.00%
Stage 6 Line washing 2.00%
Stage 7 Circuit check 4.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Air distribution 50.00%
Stage 3 Pneumatic connections 15.00%
Stage 4 Checks 10.00%
Steam tracing for instruments Stage 2 Copper tube steam tracer 20.00%
Stage 3 Condensate discharge manifold 20.00%
Stage 4 Piping connections 5.00%
Stage 5 Checks 5.00%
TELECOMS WORKS
Progress is calculated based on P.A.B.X. and measured as per
Telephone following stages:
Work Step
Stage Description WF for
P.A.B.X. Installation
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 417 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Transport on the spot 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Final tests 20.00%
Progress is calculated based on Public address console and
measured as per following stages:
Stage Description WF for
Public address consoles
Work Step
stages
Stage 1 Supports 20.00%
Stage 2 Installation/Connections 70.00%
Stage 3 Tests / Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Siren installation and erection
Siren
and measured as per following stages:
Stage Description WF for
stages
Work Step
Stage 1 Support preparation 20.00%
Siren installation
Stage 2 Siren installation 40.00%
Stage 3 Wiring 30.00%
Stage 4 Checks 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Calibrate 100.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Scaffolding erection 10.00%
Stage 3 Insulating layer installation 30.00%
Stage 4 Sheeting installation 30.00%
Stage 5 Miscellaneous finishing works 5.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
Progress is calculated based on Personnel protection insulation
(for piping) and measured as per following stages:
Stage Description WF for
stages
Personnel protection insulation (for piping) Work Step
Stage 1 Steel sheet prefabrication 20.00%
Stage 2 Insulating layer installation 40.00%
Stage 3 Sheeting installation 30.00%
Stage 4 Finishing 10.00%
Progress is calculated based on Piping cold insulation and
Cold Insulation Works
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 20.00%
Work Step Stage 2 Scaffolding erection 10.00%
Piping cold insulation Stage 3 Insulating layer installation 15.00%
Stage 4 Vapour barrier 20.00%
Stage 5 Sheeting installation 20.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 422 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Equipment cold insulation and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Prefabrication 20.00%
Equipment cold insulation Work Step Stage 2 Scaffolding erection 10.00%
Stage 3 Insulating layer installation 15.00%
Stage 4 Vapor barrier 20.00%
Stage 5 Sheeting installation 20.00%
Stage 6 Final inspection 5.00%
Stage 7 Scaffolding dismantling 10.00%
PAINTING Progress is calculated based on Piping painting (2+2 coats) and
Painting Works measured as per following stages:
Stage Description WF for
stages
Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Work Step
Stage 3 2nd primer coat 10.00%
Piping painting (2+2 coats)
Stage 4 1st finish coat 15.00%
Stage 5 2nd finish coat 15.00%
Stage 6 Numbering or labelling 5.00%
Stage 7 Final cleaning and touch up 10.00%
Stage 8 Final check 5.00%
Progress is calculated based on Piping painting in shop (2 coats)
Piping painting in shop (2 coats) Work Step
and measured as per following stages:
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 423 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Wire brushing or shot blasting 50.00%
Stage 2 1st primer coat 20.00%
Stage 3 2nd primer coat 20.00%
Stage 4 Final check 10.00%
Progress is calculated based on Piping painting in field (2 coats
and measured as per following stages:
Stage Description WF for
stages
Piping painting in field (2 coats) Work Step Stage 1 1st finish coat 35.00%
Stage 2 2nd finish coat 35.00%
Stage 3 Numbering or labelling 10.00%
Stage 4 Final cleaning and touch up 10.00%
Stage 5 Final check 10.00%
Progress is calculated based on Steel structures painting (2+2
coats) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Steel structures painting (2+2 coats) Work Step Stage 3 2nd primer coat 10.00%
Stage 4 Touch up 14.00%
Stage 5 1st finish coat 16.00%
Stage 6 2nd finish coat 15.00%
Stage 7 Touch up 3.00%
Stage 8 Final check 2.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 424 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Steel structure painting in field (2
coats) and measured as per following stages:
Stage Description WF for
stages
Stage 1 1st finish coat 35.00%
Steel structure painting in field (2 coats) Work Step Stage 2 2nd finish coat 35.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Final coat 85.00%
Stage 2 Touch up 10.00%
Stage 3 Final check 50.00%
Progress is calculated based on Tanks and spheres painting (2+2
coats) and measured as per following stages:
Stage Description WF for
stages
Stage 1 Wire brushing or shot blasting 30.00%
Stage 2 1st primer coat 10.00%
Tanks and spheres painting (2+2 coats)
Work Step Stage 3 2nd primer coat 10.00%
Stage 4 Touch up 10.00%
Stage 5 1st finish coat 15.00%
Stage 6 2nd finish coat 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 4 Coating Test 10.00%
Stage 5 Inspection Test & Records (ITR) 35.00%
Stage 6 Red Line Marked up as built. 5.00%
Progress is calculated based on Survey and staking and
Pipeline Installation (CROSS-COUNTRY )
measured as per following stages:
Stage Description WF for
Work Step
stages
Survey and staking
Stage 1 Survey 50.00%
Stage 2 Staking 50.00%
Progress is calculated based on ROW-Clearing and Grading and
measured as per following stages:
Stage Description
Stage 1 Clearing & Grading 40.00%
ROW-Clearing and Grading & Access
Work Step Stage 2 Fill 40.00%
Preparation
WP - 837-846 Stage 3 Compact 15.00%
Stage 4 Test 5.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Actual Trench Excavation in Km 90.00%
Stage 2 Accepted Total no. of Trench 10.00%
Excavation in Km
Progress is calculated based on Pipe stringing single pipe and
measured as per following stages:
Stage Description WF for
Pipe stringing single pipe Work Step
stages
Stage 1 Actual No of Stringing single pipe 90.00%
Stage 2 Accepted Total no. of Stringing 10.00%
Progress is calculated based on Pipe stringing 2-3 pipe section
and measured as per following stages:
Stage Description WF for
Pipe stringing 2-3 pipe section Work Step stages
Stage 1 Actual No. of Stringing 2-3 pipe section 90.00%
Stage 2 Accepted Total No. of Stringing 2-3 10.00%
pipe section
Progress is calculated based on Field Bending and measured as
per following stages:
Stage Description WF for
stages
Laying/Welding & Joint Coating Work Step Stage 1 Laying 20.00%
Stage 2 Welding 40.00%
Stage 3 Joint Coating 20.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Actual no. of Bending 90.00%
Stage 2 Accepted Total no. of Bending 10.00%
Progress is calculated based on Welding of Line pipe - station
and measured as per following stages:
Stage Description WF for
Welding of Line pipe - station Work Step
stages
Stage 1 Actual no. of Welding 90.00%
Stage 2 Accepted Total no. of Welding 10.00%
Progress is calculated based on Welding of Line pipe - station on
site and measured as per following stages:
Stage Description WF for
Welding of Line pipe - onsite Work Step
stages
Stage 1 Actual no. of Welding 90.00%
Stage 2 Accepted Total no. of Welding 10.00%
Progress is calculated based on tie-in and measured as per
following stages:
Stage Description WF for
Tie-ins Work Step
stages
Stage 1 Actual No. of Tie-ins 90.00%
Stage 2 Accepted Total No. of Tie-ins 10.00%
Progress is calculated based on NDT and measured as per
following stages:
NDT Work Step Stage Description WF for
stages
Stage 1 Total No. of Joints 90.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 429 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Field Joint coating and measured
as per following stages:
Stage Description WF for
Field Joint Coating Work Step stages
Stage 1 Actual - No. of Field joints 90.00%
Stage 2 Accepted Total No. of Field Joint 10.00%
Coating
Progress is calculated based on Bedding and measured as per
following stages:
Stage Description WF for
Bedding Work Step
stages
Stage 1 Actual - No. of Bedding 90.00%
Stage 2 Accepted Total No. of Bedding 10.00%
Progress is calculated based on Lowering and measured as per
following stages:
Stage Description WF for
Lowering Work Step stages
Stage 1 Actual - No. of Lowering 90.00%
Stage 2 Accepted Total No. of Lowering 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted 10.00%
Progress is calculated based on Padding and measured as per
following stages:
Stage Description WF for
Padding Work Step
stages
Stage 1 Actual - No. of Padding 90.00%
Stage 2 Accepted Total No. of Padding 10.00%
Progress is calculated based on Backfilling and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Excavation 5.00%
Box Culvert Works Work Step Stage 2 Blinding Concrete 5.00%
Stage 3 Reinforcement 20.00%
Stage 4 Formworks 35.00%
Stage 5 Pouring 20.00%
Stage 6 Coating 5.00%
Stage 7 Backfilling 10.00%
Progress is calculated based on Backfilling and measured as per
following stages:
Stage Description WF for
stages
Backfilling/Berm Forming Work Step
Stage 1 Sand filling 20.00%
Stage 2 Backfilling 20.00%
Stage 3 Berm 1st Lay 20.00%
Stage 4 Berm 2nd Lay 20.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 431 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Berm 3rd Lay 10.00%
Stage 6 Final Inspection 10.00%
Progress is calculated based on Cathodic protection and
measured as per following stages:
Stage Description WF for
Cathodic protection Work Step stages
Stage 1 Actual - No. of Cathodic Protection 90.00%
Stage 2 Accepted Total No. of Cathodic 10.00%
Protection
Progress is calculated based on Pre-Commissioning and
measured as per following stages:
Stage Description WF for
stages
Stage 1 Chemical Cleaning (Pigs or GEL Pigs) 12.00%
Stage 2 Helium Leak Detection 10.00%
Stage 3 Bolting 6.00%
Pre-commissioning Work Step
Stage 4 Hot Oil Flushing 10.00%
Stage 5 Pipe Freezing 10.00%
Stage 6 Foam Inerting 13.00%
Stage 7 Gauging 20.00%
Stage 8 Filling (Flooding) 9.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Actual - No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Pipeline dry and measured as
per following stages:
Stage Description WF for
Pipe Line dry Work Step
stages
Stage 1 Actual - No. of Pipeline Dry 90.00%
Stage 2 Accepted Total Pipe line Dry 10.00%
Progress is calculated based on Filling with Nitrogen and
measured as per following stages:
Stage Description WF for
Filing with Nitrogen/ Discharging Air Work Step
stages
Stage 1 Actual - No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Along-Route Road and measured
as per following stages:
Stage Description WF for
Along-Route Road Work Step
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Progress is calculated based on Marker and measured as per
following stages:
Stage Description WF for
Marker Work Step
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Restoration Work Step
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 433 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Restoration and measured as per
following stages:
Stage Description WF for
stages
Stage 1 Actual in km 90.00%
Stage 2 Accepted in km 10.00%
Progress is calculated based on Stockpiling of Pipe and measured
as per following stages:
Stage Description WF for
Stockpiling of Pipe Work Step
stages
Stage 1 Actual - No. of Joints 90.00%
Stage 2 Accepted Total No. of Joints 10.00%
Progress is calculated based on Bridge - off take and measured
as per following stages:
Stage Description WF for
Bridge - off take Work Step
stages
Stage 1 Actual - No. of Bridge 90.00%
Stage 2 Accepted Total No. of Bridge 10.00%
Progress is calculated based on Valve station and measured as
per following stages:
Stage Description WF for
stages
Valve station Work Step Stage 1 Ground Levelling (Civil works) 10.00%
Stage 2 Foundation (Civil works) 7.00%
Stage 3 Editing / Welding of Valves (Process 11.00%
works)
Stage 4 Welding of Pipelines (Process works) 8.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 434 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 5 Coating (Process works) 6.00%
Stage 6 Contour of grounding (Electrical 7.00%
works)
Stage 7 TEG Installation (Electrical works) 4.00%
Stage 8 Lightning Protection System 7.00%
( Electrical )
Stage 9 Install Pressure Gauge Transmitter 6.00%
(Instrument works)
Stage Grounds/Gas Temperature 4.00%
10 Transmitter (Instrument works)
Stage PIG Detector (Instrument works) 15.00%
11
Stage Optical Cable laying (Instrument 8.00%
12 works)
Stage Installation of Instrument Box 3.00%
13 (Instrument works)
Stage CP Test Connection (Instrument 2.00%
14 works)
Stage Hydro Test / Drying 2.00%
15
Progress is calculated based on Access roads and measured as
per following stages:
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Quantity of Pig Launcher and Receiver 90.00%
installed
Stage 2 Accepted Total No. of Pig Launcher and 10.00%
Receiver installed
Progress is calculated based on Helicopter landing site and
measured as per following stages:
Stage Description WF for
stages
Stage 1 ROW 8.00%
Stage 2 Staking 5.00%
Stage 3 Putting earth embankment 10.00%
Stage 4 Installation slabs 8.00%
Helicopter landing site Work Step Stage 5 Putting mixtures surfacing 10.00%
Stage 6 Sealing of joints 7.00%
Stage 7 Painting 10.00%
Stage 8 Access road 8.00%
Stage 9 Putting earth embankment 10.00%
Stage 10 Construction of roadway surfacing 8.00%
Stage 11 Slope strengthening with soil and 8.00%
grass sowing
Stage 12 Installation vane 8.00%
Progress is calculated based on Appurtenances of pipe and
measured as per following stages:
Appurtenances of pipe Work Step
Stage Description WF for
stages
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 436 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Actual - No. of Appurtenance of Pipe 90.00%
Stage 2 Accepted Total No. of Appurtenance 10.00%
of Pipe
Progress is calculated based on Power supply and measured as
per following stages:
Power supply Work Step Stage Description WF for
stages
Stage 1 Power Supply 100.00%
Progress is calculated based on Road Crossings and measured as
per following stages:
Stage Description WF for
Road Crossings Work Step
stages
Stage 1 Actual - No. of Road Crossing 90.00%
Stage 2 Accepted Total No. of Road Crossing 10.00%
Progress is calculated based on HDD River and measured as per
following stages:
Stage Description WF for
HDD River Work Step
stages
Stage 1 Actual - No. of HDD River 90.00%
Stage 2 Accepted Total No. of HDD River 10.00%
Progress is calculated based on River crossing and measured as
per following stages:
River and water channel crossing Work Step Stage Description WF for
stages
Stage 1 Actual - No. of River and Water channel 90.00%
crossing
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 437 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted Total No. of River and Water 10.00%
channel crossing
Progress is calculated based on Railway and measured as per
following stages:
Work Description WF for
Railway Work Step
Step stages
Step 1 Actual - No. of Railway 90.00%
Step 2 Accepted Total No. of Railway 10.00%
Progress is calculated based on Road crossing (casing) and
measured as per following stages:
Stage Description WF for
Road crossing (casing) Work Step stages
Stage 1 Actual - No. of Road Crossing (casing) 90.00%
Stage 2 Accepted Total No. of Road Crossing 10.00%
(casing)
Progress is calculated based on Road crossing (excavation) and
measured as per following stages:
Stage Description WF for
Road crossing (excavation) Work Step
stages
Stage 1 Actual - No. of Road Crossing 90.00%
(excavation)
Stage 2 Accepted Total No. of Road Crossing 10.00%
(excavation)
Progress is calculated based on U/G pipeline/cables and
measured as per following stages:
U/G pipeline/cables Work Step Stage Description WF for
stages
Stage 1 Actual - Linear in meters 90.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 438 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 2 Accepted Total No. of Linear in 10.00%
Meters
Progress is calculated based on Others / Weight Blocks and
measured as per following stages:
Stage Description WF for
Others / Weight Block Work Step stages
Stage 1 Actual - No. of Others / Weight block 90.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 7 MCC Package Hand-over 10.00%
Instrumentation Progress is calculated based on SAT and measured as per
following stages:
Stage Description WF for
Site Acceptance Tests ( SAT Work Step
stages
Systems)
Stage 1 Complete SAT 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Mini Loop Check and measured
as per following stages:
Stage Description WF for
Mini Loop Check Work Step
stages
Stage 1 Mini Loop Check 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Loop Check and measured as per
following stages:
Stage Description WF for
Loop Check Work Step
stages
Stage 1 Loop Check 90.00%
Stage 2 Acceptance 10.00%
Progress is calculated based on Functional check and measured as
per following stages:
Stage Description WF for
Functional Check Work Step
stages
Stage 1 Functional Check 90.00%
Stage 2 Acceptance 10.00%
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 440 of 456
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Building Pre-commissioning
Electrical
and measured as per following stages:
Stage Description WF for
stages
Work Step Stage 1 Power supply and checking 30.00%
Electrical Generator Stage 2 Control System checking 20.00%
Step 3 Motors run 30.00%
Step 4 Energizing 15.00%
Step 5 Certificate 5.00%
Progress is calculated based on Building Pre-commissioning and
measured as per following stages:
Stage Description WF for
stages
Transformer tests Work Step
Stage 1 Vector group 30.00%
Stage 2 Energization 50.00%
Stage 3 Leak test 10.00%
Stage 4 MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 6 MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Civil & Secondary 10.00%
Stage 2 Power distribution/lighting 15.00%
Stage 3 F & G System 20.00%
Stage 4 Inergen 20.00%
Stage 2
MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage 1 Cleaning / Inspection 45.00%
Stage 2 Box-up 45.00%
Stage 3 MCC Package Hand-over 10.00%
Progress is calculated based on Rotating Equipment and
measured as per following stages:
Stage Description WF for
stages
Rotating Equipment Work Step Stage 1 Chemical cleaning 10.00%
Stage 2 Reinstatement 25.00%
Stage 3 Final Alignment 15.00%
Stage 4 First Oil Filling 40.00%
Stage 5 Certificate 10.00%
Progress is calculated based on Compressors & Blowers and
measured as per following stages:
Stage Description WF for
Compressors & Blowers Work Step stages
Stage 1 Preparation works 25.00%
Stage 2 Pre-commissioning 65.00%
Stage 3
MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Progress is calculated based on Air coolers no load test and
measured as per following stages:
Stage Description WF for
Air coolers no load test Work Step stages
Stage 1 Pre-commissioning 90.00%
Stage 2
MCC Package Hand-over 10.00%
Stage 3
MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stages Description WF for
stages
Stage 1
Catalyst loading 90.00%
Stage 2
MCC Package Hand-over 10.00%
Stage 2
MCC Package Hand-over 10.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Submission 65.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Submission 65.00%
Stage 2 Approval 25.00%
Stage 3 Acceptance 10.00%
Progress is calculated based on No. of documents and measured
as per following stages:
Stage Description WF for
stages
WP - 853 As-Built Drawings (No. of Documents) Work Step
Stage 1 Submission 65.00%
Work Package
Description of Methodology Methodology Calculation Description, Detailed Weight Factor or Formula
No.
Stage Description WF for
stages
Stage 1 Submission 65.00%
Stage 2 Approval 25.00%
Stage 3 Acceptance 10.00%
Work Package No. WF% Description of Work Package Calculation Description, Detailed Weight Factor or Formula
Progress is calculated according to the shop Drawing list.
1001 M/H Work order and Shop Drawing Engineering
(Issued/Total)
Work
Description WF
Step
Step 1 Issue of Purchase Order 25%
M/H Pre-shut down Activities When it's done, the progress is 100%.
Pre/Shut/Post
M/H Shut Down Activities When it's done, the progress is 100%.
Down
M/H Post Shut Down Activities When it's done, the progress is 100%.
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 450 of 456
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 451 of 456
Control
Weight
Account Description of Control Account Methodology Calculation Description, Detailed Weight Factor or Formula
Factor
No.
Update corporate processes,
1-Progress is on and off and will be 100% after completion of the work
Procedures, and template based Milestone
2-WF shall be calculated based on the M/H
on the lessons learned
UB 50%
Gather and create final lessons 1-Progress is on and off and will be 100% after completion of the work
Milestone
learned 2-WF shall be calculated based on the M/H
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 453 of 456
Reference
No PTS No. & Title Change Justification
Document
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 454 of 456
Reviewer 1
Reviewer 2
Reviewer 1
Reviewer 2
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 455 of 456
Reviewer 1
Reviewer 2
Reviewer 1
Reviewer 2
PTG 19.80.04
PROGRESS MEASUREMENT SYSTEM May 2015
Page 456 of 456
Reviewer 2
Reviewer 1
Reviewer 2