PEKERJAAN ENGINEERING PROCUREMENT ENG CONSULTANT     

AND CONSTRUCTION (EPC) R (Checklist Relevant Dicipline)
PLTM HARJOSARI dan PLTM LAMBUR E CIVIL
DOC REVIEW V MECHANICAL
LOG  DATE I ELECTRICAL
IN COMM. NO. E I & IC
A      APPROVED W SUPPORT
B      APPROVED AS NOTED
C      NOT APPROVED
I      INFORMATION AUTHORIZED
INTIAL 
A SIGN
APPROVED DOES NOT RELIEVE CONTRACTOR P PROJECT MANAGER
FROM RESPONSIBILITY FOR ERROR OR DEVIATION P COUNTERPART TEAM
FORM CONTRACT REQUIREMENT R LEAD ENGINEER
BY DATE O ENGINEER
DATE   25/03/2019 V
LOG  A
COMM. NO. SI-14 SB-PH 190325 Rev-02/PLTM
OUT L
Hjsr/LAPI/III/2019

Perlu memeriksa kembali dimensi-dimensi


Perlu memperhatikan catatan yang ada pada transmital