RENCANA KERJA

SIMPLE INSPECTION UNIT #1 01 APRIL S.D 15 APRIL 2016


DEPT. OPERASIONAL BAGIAN BOILER DAN ESP

Man Power Schedule April 2016


No. Kegiatan Simple Inspection
CFK T. Harian total 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
01 Pembuatan andang di dalam furnace 2 4 6
02 Cleaning furnace (water wall) 2 4 6
03 Flushing coal pipe 1 2 3
04 Cleaning coal burner 2 2 4
05 Thickness feed water line, water wall dan superheater tube bersama tim mekanik 1 0 1
06 Pembongkaran andang di dalam furnace 2 2 4
07 Cleaning pipa-pipa superheater 2 2 4
08 Cleaning pipa-pipa Superior Economizer 2 2 4
09 Cleaning superior Air Preheater 2 2 4
10 Cleaning pipa-pipa Subordinate Economizer 2 2 4
11 Cleaning Subordinate Air Preheater 2 2 4
12 Cleaning Ducting Elbow Flue Gas 2 2 4
13 Inspeksi pada ducting IDF A dan B 2 2 4
14 Cleaning Elektroda-elektroda chamber ESP 2 2 4
15 Menguras dan cleaning bak kontrol fan mill A 2 1 3
16 Menguras dan cleaning bak kontrol fan mill B 2 1 3
17 Menguras dan cleaning bak kontrol fan mill C 2 1 3
18 Menutup semua main hole untuk persiapan start-up 2 1 3
19 Cleaning semua area sisa-sisa kegiatan Simple Inspection untuk persiapan start-u 2 6 8

Man Power Schedule April 2016


No. Kegiatan Setelah Simple Inspection
CFK T. Harian total 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
20 Pengecatan-pengecatan area Boiler #1 dan #2 0 4 4
RENCANA KERJA
SIMPLE INSPECTION UNIT #1 01 APRIL S.D 15 APRIL 2016

DEPT. OPERASIONAL BAGIAN TURBIN DAN GENERATOR

Man Power Schedule


No. Kegiatan
CFK T. Harian total 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
01 Cleaning tube condensate tank 2 4 6
02 Cleaning tube oil cooler 1 2 3
03 Cleaning strainer oil cooler 1 2 3
04 Cleaning strainer air generator 1 2 3
05 Cleaning strainer NRV 1 2 3
06 Cleaning strainer magnet BFWP dan Inlet BFWP 1 2 3
07 Cleaning tube air cooler generator 1 2 3
08 Cleaning oil tank 1 2 3
09 Cleaning Deaerator 1 2 3
10 Cleaning Chamber drain CWP 1 2 3
11 Cleaning semua area sisa-sisa kegiatan Simple Inspection untuk persiapan start 2 4 6
RENCANA KERJA
MAJOR INSPECTION UNIT
#1 01-30 MARET 2017
DEPT. PRODUKSI BAGIAN BOILER DAN ESP

Man Power Maret 2017


No. Kegiatan T. tgl
CFK Harian total tgl 1-7 tgl 8-14 tgl 15-21 tgl 22-28
29-30
01 Pembuatan andang di dalam furnace 2 4 6
02 Cleaning furnace (water wall) 2 4 6
03 Flushing coal pipe 1 2 3
04 Cleaning coal burner 2 2 4
05 Thickness feed water line, water wall dan superheater tube 1 0 1
bersama tim mekanik
06 Pembongkaran andang di dalam furnace 2 2 4
07 Cleaning pipa-pipa superheater 2 2 4
08 Cleaning pipa-pipa Superior Economizer 2 2 4
09 Cleaning superior Air Preheater 2 2 4
10 Cleaning pipa-pipa Subordinate Economizer 2 2 4
11 Cleaning Subordinate Air Preheater 2 2 4
12 Cleaning Ducting Elbow Flue Gas 2 2 4
13 Inspeksi pada ducting IDF A dan B 2 2 4
14 Cleaning Elektroda-elektroda chamber ESP 2 2 4
15 Menguras dan cleaning bak kontrol fan mill A 2 1 3
16 Menguras dan cleaning bak kontrol fan mill B 2 1 3
17 Menguras dan cleaning bak kontrol fan mill C 2 1 3
18 Menutup semua main hole untuk persiapan start-up 2 1 3
19 Cleaning semua area sisa-sisa kegiatan Simple Inspection 2 6 8
untuk persiapan start-up
RENCANA KERJA
SIMPLE INSPECTION UNIT #1 01 MEI S.D 15 MEI 2016

DEPT. OPERASIONAL BAGIAN TURBIN DAN GENERATOR

Man Power Schedule Mei 2016


No. Kegiatan
CFK T. Harian total 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
01 Cleaning tube condensate tank 2 4 6
02 Cleaning tube oil cooler 1 2 3
03 Cleaning strainer oil cooler 1 2 3
04 Cleaning strainer air generator 1 2 3
05 Cleaning strainer NRV 1 2 3
06 Cleaning strainer magnet BFWP dan Inlet BFWP 1 2 3
07 Cleaning tube air cooler generator 1 2 3
08 Cleaning oil tank 1 2 3
09 Cleaning Deaerator 1 2 3
10 Cleaning Chamber drain CWP 1 2 3
11 Cleaning semua area sisa-sisa kegiatan Simple Inspection untuk persiapan start 2 4 6