Professional Documents
Culture Documents
Project
This scoping report is to provide Seascape Oil Networks Limited with an overview of the
proposed 600mm diameter oil pipeline project that will run from a point on the National
Transmission Pipeline north of Winchester to the Regional Transmission Pipeline to the south
and to invite early input from the developers in the identification of key issues, areas of concern
and additional environmental data available in order to inform the detailed Environmental Impact
Assessment (EIA) scoping process.
1. Introduction
This is a desktop constraints report for the impact assessment of a proposed oil pipeline
construction by Seascape Oil Networks Limited. This study aims to identify the significant
environmental, archaeological and socio-economic impacts that will be addressed in the
Environmental Impact Assessment (EIA) process by:
Other supporting legislation includes the EC Directive 85/337/EEC (Assessment of the Effects of
Certain Public and Private Projects on the Environment), EC Directive 92/43/EC (Habitats
Directive), EC Directive 2009/147/EC (Birds Directive), the UK Wildlife and Countryside Act
(1981), Hedgerows Regulations (1997) and the UK Conservation of Species and Habitats
Regulations (2010).
The selected corridor for the construction of the pipeline is influenced by the position of the
connecting pipelines (the National Transmission Pipeline and the Regional Transmission
Pipeline) and the initial engineering feasibility study received.
The primary objective is to select an economically viable route with minimised impacts and risk
to the public and the environment.
This preliminary route selection was conducted using Ordnance Survey mapping, GIS datasets
from statutory consultees (English Heritage, Natural England) and the local council database.
The standard dig trench lay technique is assumed; however, tunnelling and other trenchless
construction techniques will be required at environmentally sensitive areas, river crossings and at
interceptions with major traffic routes.
Pipeline construction is carried out within a 50m working width, which would include a
temporarily fenced corridor for storage of stripped topsoil, trench excavation and access road for
construction traffic. The excavated trench is back-filled with the material taken from it in reverse
order and the working area is returned to original condition as pre-arranged with landowners,
statutory and non-statutory consultees.
2.3 Pipeline Operation
The use of an integrated corrosion protection system to secure pipeline integrity and periodical
monitoring in line with existing maintenance schedules.
3. Environmental Assessment
The UK EIA regulations require a description of potential concerns/environmental aspects that
are expected to be significantly affected (including land use, population, ecology, water, air,
geographic, cultural/materials assets, landscape and the inter-relationship between them) by a
project and the mitigation measures to minimise such effects to be reported in the Environmental
Impact Assessment (EIA).
The significant impacts expected from the development of this project, and which will be
identified in the EIA, have been categorised under the construction and the operational stages.
Table 1 below shows the occurrence and types of impact of these potential concerns.
Construction Operation
Impact type
-ve Unlikely
Landscape and visual impacts
-ve -ve
Land use
-ve Unlikely
Soils and agriculture
-ve Unlikely
Biodiversity and habitats
-ve Unlikely
Water resources and flood risk
-ve Unlikely
Archaeology and cultural heritage
-ve Unlikely
Emissions
-ve Unlikely
Contaminated land and waste
management
-ve unlikely
Traffic and transport management
+ve Unlikely
Socio-economic
The buried nature of the project accounts for most construction impacts. The effects of most of
the impacts are short-lived, occurring for specific periods during construction.
Other concerns that have been scoped out of the EIA for the insignificant impacts that they have
include:
Climate and topography: The project will have no impacts on the climate and
topography of the selected area;
Safety: The pipeline will be designed and constructed in line with relevant codes of
practice;
Geology and mining: The bedrock of the area is dominated mainly by chalk, mixed with
a combination of clay, silt and sand occurring together or in layers. There are no
recorded geological faults and mining activities in the proposed route. However, the
impact of the pipeline construction is limited to a laying depth of 1000mm that affects
mainly the surface topsoils.
The selected corridor has a varied landscape with different features including arable farmland,
clay lowland pastures, chalk downland, river valley and woodland including Avington Park, a
designated Parks and Garden. However, noticeable impacts on the character of the area will
occur during the summer construction phase in the visual range of the pipeline route and its
working areas.
The proposed pipeline is a buried structure, therefore impact is temporary, as restoration to the
original state is done immediately after the pipe is laid.
5 Land Use
A large proportion of land on the proposed route is currently for arable farming and pasture
fields, nature conservation sites and a few built-up urban/residential areas. There is a temporary
land take for construction and it will be kept within the working width.
There will be temporary disruptions on the farms, due to restrictions placed on movement of
livestock and farming machinery by the fenced working width. However, the project is
controlled to ensure proper restoration to the original condition.
Construction activity in the urban areas limits road and street accessibility to residents. All
existing cables and pipes on the route will be located by excavation to confirm their exact
location; however, other utilities including sewage pipes will create constraints.
The project has the potential to restrict future developments on its route.
Other actions to mitigate impact could include refilling of trenches by excavated soil to ensure
quick re-instatement of the land; the use of low ground pressure vehicles and back-actors in soil
stripping to minimise soil compaction.
Construction is a relatively short-term activity spanning a few months and the land would
thereafter be restored to its original condition.
The selected corridor lies within several conservation areas, including ancient woodlands, Sites
of Importance for Nature Conservation (SINC), Sites of Special Scientific Interest (SSSI) and a
Special Area of Conservation (SAC), as shown in Figure 7.1. The designated conservation areas
are reservoirs for biodiversity and preservation of habitats.
A large portion of land on the proposed route is used for agricultural activities, under the
environmental stewardship scheme to promote farming compatible with the maintenance of the
countryside and protection of the environment.
The major site of ecological importance is found at the River Itchen. This river is a classic chalk
river, which serves as natural habitat for several numbers of national and international priority
species including the water-crowfoot (Ranunculus penicillatus), Otter (Lutra lutra)*, Water vole
(Arvicola terrestris)* and the Southern damselfly. The ecology on the river depends on its flow
and water level, hence any disruption presents a threat to the nature conservation and the
adjoining flood plain.
Other noted fauna recorded in the working area include the Duke of Burgundy (Hamearis
lucina)*, Hazel dormouse (Muscardinus avellanarius)*, Barn owl (Tyto alba), Snipe (Gallinago
gallinago)*, Great crested newt and badgers.
Due to the high sensitivity, consultations with the following groups must take place before and
during construction:
The impact on the areas of conservation would be reduced by the consideration of trenchless
construction methods.
Although trenchless construction techniques are proposed for the River Itchen are, consultation
with and approval from the Environmental Agency is required for the conservation of the river’s
prominent feature as a classic chalk river from aquifer-fed springs.
Figure 8.1: Water resource and flood risk areas in the selected corridor
Construction activity is temporary in nature and would be carried out during periods of low
flooding risk; however, pipelines would be weight-coated to avoid flotation.
There are over 30 listed buildings and 15 scheduled monuments in the selected corridor, as
illustrated in Figure 9.1; however preliminary consultation with the Winchester County
Archaeologist is essential before and during archaeological work.
The proposed pipeline route would be selected to avoid all archaeological and heritage sites in
the working route; however, field evaluation is proposed to reduce the risk of damaging any
archaeological features.
10 Emissions
The pipeline construction has the potential to generate substantial emissions in terms of noise,
vibration, dust generation, air quality impacts, combustion emissions from plants and vehicles,
transfer of mud onto public highways and discharge to watercourses. The extent of impact is
dependent on the efficiency of control measures and the nearness to people and residences.
The emissions are temporary and spatial as they only occur in short periods of time in the work
areas.
11 Contaminated Land and Waste Management
Registered industrial pollution and landfill sites that will be avoided in the selected corridor are
listed below:
A possible case of contaminated land may arise at the old Royal Air Force Base at Worthy Down
Camp. Other potential sources of unrecorded contaminated sites may be present, which will be
mitigated by the use of clay plugs in the pipeline trench.
Waste materials generated as a result of the pipeline construction must be handled in line with
the Code of Practice for waste minimisation and recycling in construction. Suitable disposal
routes and treatment methods will be adopted to mitigate the impact. Minimal impact is expected
as the excavated soil would be reused in covering trenches.
The working area could be limited to one lane on roads and streets to reduce the length of
trenched road at any time. To ensure minimised traffic impacts, all major roads (M3, A272, A31,
A33, A34, B3047) crossings by the pipeline will be constructed using trenchless techniques.
13 Socio-economic Impact
The project would impact positively on the economic activities of the community during the
construction phase. There would be compensation made to farmers and landowners for
temporary and permanent land use, increased local employment opportunities dependent on
contractor requirements and income generation from local procurements and expenditure.
The recommended pipeline route from preliminary study is a 17.8km route from estimated point
of inception to termination as detailed in the subsequent figures.
Figure 14.1: Proposed pipeline route in the selected corridor.
Figure 14.2: Proposed pipeline route in the selected corridor highlighting biodiversity and
habitat.
Figure 14.3: Proposed pipeline route in the selected corridor highlighting water resources and
flood risk.
Figure 14.4: Proposed pipeline route in the selected corridor highlighting archaeological features.
Figure 14.5: Proposed pipeline route in the selected corridor highlighting pollution sites and
landfill areas.
Restrictions of Compensation
future clause in
developments on agreements with
pipeline route landowners
Soil can be
stripped and stored
in layers and back-
filled in reverse
order to ensure
quick
re-instatement
Working width
and hedgerows
will be reptile-
proof fenced to
prevent animals
straying into the
working area
Disturbance to Avoidance of
badgers badger sets
wherever possible;
however, badger
ramps will be
provided over the
pipeline trenches
Further
archaeological
survey of the
pipeline route to
locate any
previously
unknown feature
7 Emissions Construction The use of
noise from plant silenced
and machinery compressors and
acoustic covers on
plant and
machinery. Use of
acoustic barriers
and informing
residents of
expected
increasing noise
levels
Waste
management
plan to identify
likely waste,
handling and
disposal methods
in line with all
relevant
regulations.
9 Traffic and Disruption to Comprehensive
Transport normal traffic traffic
management flow experienced management plan
by residents and to identify road
other road users constraints and
sensitive areas
including schools
and hospitals and
provide
alternatives
Advance warnings
to residents and
other road users of
intended
disruption to road
use.
Use of trenchless
techniques in
pipeline crossings
of the the M3
highway and other
A-class roads.
Income generating
from project’s
local procurement
and expenditure
Employment
opportunities for
the local populace
in the community