Professional Documents
Culture Documents
doc
Construction Synopsis
Construction commenced 12.11.2008
Structure completed 9.7.2009
Please refer to the plates from 1 to 26 giving entire views of the structural
construction.
Structural
772
450
level
2472
5750 1000
1250
level
800 150 200
150
5750 750
1250
150 150
600
1789 600
1600 1661 300143 600 150
300
385 200 1677 300
714 1494
2500 200
H all Entry Left Side balcony 464 1494
Right Side balcony
47 49 51 53 55 57 59
1400
2472
200 x 300
1800
2 F2 1000 772
72 70 66 64 62 60 200 x 400
F2 upstand
200 x 300
300
300 x 300 x
600 600
800 F11
F9 1400
1800 200 x 300 2300
Balcony link/Railing
4 300 x
200 x 300
F4 600
F4 589 400
200 x 300 300
F9 F9 F13
200 200 x 300 2499
200 x 300
200 x 300 300 x 200 300 x
5 F5 600 600 F5
1000 F8 F8 F8 F8 F8 F8
1800 1720 1720 1850 1900 1851 1800
200 x 300 200 x 300 200 x 300 200 x 300
200 x 300
200 200 200 200 200 200
150
300
1378 1000 450
200
I nternal Balcony/Railing
400
Balcony passage/Railing
Figure 1
Plot Size 420 sqm
Basement below drawing room hall portion
Ground coverage 55 %
Total coverage added 540 sqm
/conversion/tmp/scratch/420774563.doc
Structural
772
450
level
2472
5750 1000
1250
level
800 150
150
5750 750
1250
200 150 150
600
1789 600
1600 1661 300143 600 150
300
385 200 1677 300
714 1494
2500 200
H all Entry Left Side balcony 464 1494
Right Side balcony
beams
C 200 x 300 mm D
A B 200 x 300 200 x 300
47 49 51 53 55 57 59
1400
2472
200 x 300
1000 1800
F2 772
72 70 66 64 62 60 200 x 400
2 F2 upstand
200 x 300
300
300 x 300 x
600 600
800 F11
F9 1400
1800 200 x 300 2300
1000 3 200 x 300
1000 600
200
200 x 300
200
1000 300 x 300
578
3977 F12
200 x 300
F9 200 1200 2777
200 x 300
4 300 x
F4 F4 589
600
200 x 300 300
F9 F9 F13
200 200 x 300 2499
200 x 300
200 x 300 300 x 200 300 x
5 F5 600 600 F5
1000 F8 F8 F8 F8 F8 F8
1800 1720 1720 1850 1900 1851 1800
200 x 300 200 x 300 200 x 300 200 x 300
200 x 300
200 200 200 200 200 200
Figure 2
6 Excavation carried out by JCB partly & then used donkey stock for
a total excavation quantity of 550 cum. Soil removed from the site.
Structural:
1 On the prepared soil improvement base, a 50 mm thick layer of
blinding concrete was laid.
5 The sketch shows the details of the foundation section 400 x 1200
mm beam with 800 wide spreader embedded in full 200 mm thick
RCC matting under all the beams in both directions. Columns were
revealed from the beams. One 16000 litres capacity water storage
tank has also been provided between the foundation beams.
400.00
Foundation Beam
1000.00
200.00
300.00
Soil I mprovement
Figure 3
suspended slab curing but for the columns & brick walls, I faced the
hard job.
Right Elevation
Elevation
Architectural
500
2125
8.85 sqm 1.56
525 595
297297297297
594 475 475 475 475 300
738
3250
3250
738
738
3.0
737 300
3.24
525
3250
3250
738 3.4
1.37
437
100 300
1625
750
Figure 4
Elevation
Architectural
500
PLOT 430/1A, SECTOR 21B, FARI DABAD-HUDA AREA
3250
1000
OWNERS- SURAJ SI NGH & SUM I TRA
3250
3250
FOR Submission
3250
3750
300
1250
3250
2000 2000
Left Elevation
/conversion/tmp/scratch/420774563.doc
Figure 5
200
349 300
349 698 228
1.82
FOR Submission
349
349
228 2000
666
667
650
650
Architectural
Front Elevation
Elevation
Figure 6
FOR Submission
OWNERS- SURAJ SI NGH & SUMI TRA
PLOT 430/1A, SECTOR 21B, FARI DABAD-HUDA AREA
1371 3759
V1
803
Architectural D1
BED
5559
W1
2450 3507 4764
D2
D
900 850 900 900
V
V3 W
W2
524 D5 900 D4 D3
300
4499
4200 BED
1000 850
D8 D10 W4
V5 900 2052
650
W15 750
1200 D11 1200
1180
250
927 802
W5 47 49 51 53 55 57 59
1070 V6
72 70
927 66 64 62 60
2000
W6 800
1000 W14 1500
W7
1000
Double Height
2000 W8 W132000
SFL +14'-6"
1500
W9
800 W12 1500
D13
2791 2000
W10 W11 1800
Figure 7
A B C 400
300
200
D
Typical 200
200
200
1
100
200
1000
800
2 4 / 12 Ø each in 2 layers 6 / 12 Ø each in 3 layers 4 Legged/8 Ø rings @200 c/c 6 / 12 Ø each in 3 layers
6 / 16 Ø each in 3 layers
2300
6 / 12 Ø in 1 layer
6 / 16 Ø each in 3 layers
3 4 / 12 Ø each in 2 layers 6 / 12 Ø each in 2 layers 4 L egged/8 Ø rings @200 c/c 6 / 12 Ø
6 / 16 Ø each in 3 layers
6 / 12 Ø in 1 layer, 4 in anotherr
6 / 16 Ø each in 4 layers
2777
4 6 / 12 Ø 6 / 16 Ø each in 3 layers 4 Legged/8 Ø rings @200 c/c 4 / 12 Ø in 2 layers
6 / 12 Ø each in 3 layers
6 / 12 Ø each in 3 layers
2499
4 / 12 Ø in 1 layer
Figure 8
2
4'6"1378
2300
31000
12848
17'0" 42'1.5"
Excavation Level -3.125 M
103765177 2777
34'0" 4
2499
5 2699
8'10"
1000
12241
40'2"
13619
44'8"