All projects and schedules are subject to change pending weather, contractor/supplier schedule and emergencies.
Weather has already been a major setback.
Already/still going:
Various roads, County-wide: Tree work, ditching
CR-77 Brokaw Rd in the Town of Nunda, from Kendall to Scipio: Tree work ongoing, drainage work starts this week
(5/13). Cold In-Place Recycle (CIPR) and culvert replacement expected late July/early August
BR-93 Faulkner Rd in the Town of Ossian: continue backfill, install new beams, bearings, deck and rail, construct new
alignment. Expected opening late Fall.
BR-02 Papermill Rd bridge replacement in the Town of Avon: (C.P. Ward) finished paving, re-opened road last week,
grading/seeding to be completed in next few weeks
Pennemite Rd bridge replacement, Town of Livonia: (Ramsey) finish paving, re-open road- expected to open 5/31
BR-75 Applinville Rd bridge replacement in the Towns of Sparta and West Sparta: (Ramsey) install new deck, complete
new alignment, expected to open early July
Upcoming:
CR-50 Federal Road in the Town of York, from NY-63 to York Rd West: drainage, shoulders, pavement repairs- starting
May 20th
CR-2 Groveland Hill Rd in the Town of Groveland, from Lattimore Rd to Hunt's Corners: milling and paving- starting late
June/Early July
CR-11 Rock Spring Hill in the Town of West Sparta, from Presbyterian to Kysorville-Byersville Rd: Full depth recycle and
culvert replacement late July/early August