You are on page 1of 1351

APPLICABLE PERCENTAGES

Sl. No. Description of Labour Rate (Rs.)

1 Contractors profit & Overheads for Road Works 12.5%

2 Contractors profit & Overheads for Bridge Works 20%

3 Contractors profit & Overheads Bridge Works (Rehabilitation) 20%

4 GST, Labour Welfare Cess etc. -

GST:
LWC
Swatch Bharat:
Total:
BASIC APPROACH AND GENERAL CONDITIONS
AND ASSUMPTIONS FOR THE PREPARATION OF STANDARD DATA BOOK

The basic approach for the preparation of Standard Data Book for Rural Roads is indicated as under:
1 Description of items: The description of items is given briefly and linked with the relevant Clauses of the
Ministry of Rural Development’s (MORD) Specifications wherever feasible, which may be referred for
detailed description, provisions and interpretation

2 Use of Machinery
2.1. The Standard Data Book is based on the assumption that Rural Roads in our country are to be
constructed with intermediate technology, i.e., manual means with medium input of machinery,
wherever required to ensure the required quality of work.

2.2. For rolling, use of static roller has been generally considered. However, use of vibratory pneumatic
tyre roller has been considered wherever required as per provisions of MORD Specifications.

3 Working Conditions
3.1. Rates have been analysed for average working conditions prevailing in the country.
3.2. Average achievable outputs of machines and labour have been considered taking into account the
job and management factors.
3.3. However, the output of machineries and labour reduces substantially in hilly areas as the altitude
increases. Therefore, for hilly areas reduced outputs have been considered as indicated in the
preamble of Chapter 8.
4 Overheads and contractors' profit :The overheads and contractors' profit is considered @12.5% (per
cent) for items of road works and 20% (per cent) for items of bridge works.

4.1 The overheads are considered as per provision of Data Book considering additional percentage as
indicated in the Data Book for prevailing rate of tax in the state,This is assumed to include interalia th
following elements.
i. Site accomodation,setting up plant,accessroad,water supply,electricity and general site
arrangements.
ii. Site office infrastructure.
iii. Expenditure on:
Corporate office of the Contractor
Site supervision by the Contractor
Preparation of "as built" drawings
iv. Mobilization/demobilization of sources.
v. Labour camps with minimum amenities, required as per labour laws.
vi Setting up of laboratories for quality control,field and laboratory testing for control of quality of various
items of
and documentation of test result as per requrement of MORD specifications.
vii Minor tools and plants(T&P) including needle vibrator requred for concrete work.

viii Survey instruments and the task of setting out of works including verification of line and dimensions
(but excluding construction of bench marks and reference pillars which are separate items under
setting out).

ix Taking of trial pits and bore holes


x Watch and ward
xi Arrangement for traffic and traffic management during construction
xii Expenditure on safe guarding environment during construction.
xiii Sundries
xiv Financing expenditure of the contractor.
xv Work insurance/compensation.

5 GST, Labour Welfare Cess, Swatch Bharat etc.


5.1 Overall 0 (percent) has been considered in the analysis towards GST, Labour Welfare Cess,
Swatch Bharat etc. as follows:

i. GST is not considered in the Analysis of Rates. GST applicable is to be provided separately in the
Estimates.

ii. Assam building and other construction workers welfare cess is not considered in the Analysis
of Rates and to be provided separately in the Estimates.

iii. Swatch Bharat cess is not considered in the Analysis of Rates and to be provided separately
in the Estimates.

6 General:
6.1. The section and clause numbers refer to the MORD specifications for Rural roads 2004

6.2. Additional assumptions made for analysing different items have been indicated in respective
Chapters in the form of preamble and notes/footnotes wherever required.

6.3. For some of the items, certain size/specifications have been assumed. If size/specifications other
than the same are adopted, corresponding modifications may be made in the inputs of analysis.

6.4 The sources of all materials and samples of materials are required to be approved by the Engineer
before start of such work.
6.5 For reinforcing steel both HYSD and TMT bars conforminf to IS:1786 have been considered.
6.6 For pipe culverts both NP3 and NP4 pipes have been considered.
6.7 A premium of 10% may be considered in the estimates only in emergency works within city
area and whereever required only after being duly certified byrespective S.E. Concerned.

6.8 As per latest revised version of MoRD specification for rural Roads Specific importance to
some new items like cold mix,Semi dense Biituminous concrete,soil stabilization in subgrade
and Base,use of locally available marginal materials,Industrial wastes,provisions of proper
road signs and other traffic control devices,Geosynthetics,Jute geo textiles alongwith
construction of long span Bridges has been given and incorporated in this edition as per
version of MORTH.

6.9 Quality control of work shall be governed by the relevent MORD specifications.

6.10 Apremium in percentage over the S.O.R. 2015-16 as indicated below may be allowed over the rates
of this S.O.R.for preparation of estimates of work to be executed in the following areas to cater for the
probable extra cost involved due to the remotness of these places from the marketing centres of key
construction materials,difficulties in transportation of materials and dearth of skilled labourers.

Sl No. District/Sub-division Premium in % Remarks


1. Dhemaji District 5% 1. These premiums are
2. Karbialong District 10% applicable for preparation

3. Dima Hasao. 10% of Estimates only.


4. Majuli Sub-Division 10% 2.These premiums are not
5. Sadia Sub division 10% meant for tendering and
billing purposes.
billing purposes
7 Basic Inputs
7.1. The Standard Data Book is based on the requirements of basic inputs of materials, labour and
machineries for various items.
7.2. The labour wages are as per rate fixed by the state government.The rates of material are asper the
prevailing market rate.

7.3. The basic rates of materials, such as, stone boulders, stone for masonry, stone ballast (hand
broken/machine broken), crushed aggregate, stone dust, moorum, gravel, lime, manure, sludge,
quarry sweep, kankar, bricks, brick ballast, crushed slag, etc. at quarry/crusher sites shall be fixed by
the respective states for various zones from time to time.

8 Plants and Equipment:


8.1. Keeping in view the job and managerial factors and the age factor of machines, the output of plant
and equipment is taken approximately 70 per cent of the rated capacity given by manufacturer under
ideal conditions.

8.2. The requirement of machinery has been worked out assuming working period of 6 hours per shift of 8
hours.
8.3. Certain equipment, like, road rollers, are required to be available at site for complete period of the
shift, though from the consideration of their output, they may be required only for 3 to 4 hours. This is
necessitated to match with the output of other associate machine like HMP,Paver,etc.In such cases
the hire chargees of Road rollers have been multipied with a factor of 0.65 to account for the idle
period whereever considered appropriate.

8.4. Though electrically operated equipment, like, concrete mixers and vibrators have been provided,
diesel operated equipment can be used where electricity is not available.

8.5. Wherever electric generator has not been provided to run a plant or equipment, it is assumed that it is
fitted with a diesel engine.
8.6. For small jobs where loading and unloading is required to be done manually, tractor-trolley has been
considered for carriage instead of tipper.

8.7. Output of plant &equipment considered for the compacted quantities.


8.8. A water tank of 6 KL capacity which is commonly used at construction sites has been considered.

8.9. The usage charges for machines include ownership charges, cost of repair and maintenance
including replacement of tyres and running and operating charges which includes crew, fuel and
lubricants.
9 Labour:
9.1 One mate has been provided for 25 labours for all items of works.

9.2 The labour wages should be as per rates fixed by state Government.
10 Materials:
10.1. Quantities of materials considered in the rate analysis are approximate for the purpose of estimation
and include normal wastages. Actual consumption would depend on mix design.

10.2. The rates of material include basic cost at locations of stone crushers/ factory/ rail head and cost of
its carriage to the site of work/plant including loading, unloading and stacking.
10.3. The supply of materials will be taken either at the location of mixing plant or at the work site as per
requirement of use.
10.4. Contractor will make his own arrangements for borrowing earth from private land. For
borrowing Earth from Govt. land Forest Royality is to be paid by the contractor.
10.5. Credit for Dismantled Material: The dismantled materials should be examined and a realistic
assessment made for credit for such materials, which can be utilized for works or auctioned.
10.6. The basic rates include all octroi charges, toll tax, sale tax, VAT, municipal taxes,Forest royalityand
other local taxes, etc.including loading and unloading.
11 Items of Culverts:

Items in Chapters 11, 12 & 13 on Foundation, Substructure and Superstructure cover both minor bridge
works as well as slab culverts as per Chapter 1200 of MORD Specifications. Items of pipe culverts are,
however, covered separately in Chapter 9.
12 Concrete Items:
12.1. For concrete work,the grades of concrete covered by the Data Book in accordance with MORD
specification are
I) PCC M-15 grade to M-25 for structures (For lean concrete under foundation M-10 can be used).
ii) RCC grade M-20, M-25 and M-30 for structures
iii) Design mix concrete – M-25 and M-30 and M40 for concrete pavement
12.2. The rates accounts for input of material by weight and use of ordinary mixer
12.3. Use of vibrator for all concreting work has been included in the items.
12.4. Ten per cent extra cement may be provided for concreteing under water, where require.
12.5. Quantities of cement in various grades of cement concrete are to be as per nominal mix/ design mix.
Grade of cement may also be adopted as per mix design.
12.6. Quantities of cement in various grades of cement concrete for structures have been taken as per
IRC:21:2000 & IRC:78:2000.
12.7. Steel reinforcement for cement concrete work is required to be provided separately. The rate for the
same has been analysed separately.
12.8. As per the MORD Specifications, the type of superstructure envisaged for rural roads are RCC slabs
and box culverts not exceeding 15 m span as well brick/stone masonry arches and composite girder
type of superstructure. RCC arches provided for in IRC:SP:
13 Measurement and Rates
13.1 Measurement of various items and their units shall be defined in the respective clauses of MORD
specifaction.
13.2 The rates of various items of work shall include all sub items defined in the respective clauses of
MORD specifications.
specifications.
14 Privileged Document
The Schedule of Rates is for Department use ONLY. It should not be produced in any court of law as
reference/Authority and to that extent it is a privileged document.
PREAMBLE

Chapter Description

1 Carriage of Materials

2 Site Clearance and Setting Out

3 Earthwork Erosion Control and Drainage

4 Sub Bases, Bases (Non-Bituminous) and Shoulders

5 Bases and Surface Courses (Bituminous)

6 Cement Concrete Pavement

7 Causeway and Submersible Bridges

8 Hill Road

9 Pipe Culverts

10 Traffic Signs, Markings & Other Road Appurtenances

11 Foundation

12 Substructure

13 Superstructure

14 Protection works

15 Maintenance of Roads
BASIC RATES
(B) USAGE RATES OF PLANT & MACHINERY

Description of Output of Machine


Sr. No.

Machine Activity Unit

PM-001 Air Compressor 210 cfm Supplying compressed air cfm

PM-002 Batch mix HMP 40-60 TPH BM, DBM, SDBC, PM t/h

PM-003 Batch type HMP 30/40 TPH BM, DBM, SDBC, PM t/h

Batching and mixing plant(a)30cum capacity concrete mixing cum/hour

Batching and mixing plant(b)15-20cum


concrete mixing cum/hour
capacitycapacity

Bitumen pressure distributor Applying bitumen tack coat sqm/hour

PM-004 Bitumen boiler oil fired

200 litre Heating of bitumen litre / h

1000 litre litre / h

PM-005 Bitumen emulsion pressure distributor Applying bitumen tack coat sqm/h

Concrete pump of 45&30 cum capacity Pumping of concrete cum/hour

Concrete bucket For pouring concrete /cum

PM-006 Concrete mixer 0.28/0.4 cum Mixing of ingradients cum/h

Crane (a) 80 t0n Lifting purpose

Crane(b)35 ton Lifting purpose

Crane(c)3 ton Lifting purpose

PM-007 Crane upto 8T Lifting of materials

PM-008 cum/h
Dozer D 50 Dozing cutting
cum/h

D-80-A-12 Spreading/cutting/clearing cum/h

B-7
Description of Output of Machine
Sr. No.

Machine Activity Unit


Drum mix plant for cold mixes of appropriate
per hour
capacity but not less than 75 tonnes/hour.

PM-009 Electric generator set, 125 KVA Electricity generation KVA

PM-010 Emulsion Sprayer with Tractor Spraying of Emulsion

PM-011 Loading Aggregates cum/h


Front end-loader 1 cum bucket capacity @ 45
cum/hour
Loading Soil cum/h

Hot mix plant 120 TPH DBM/BM/SDC/Premix cum/h

Hot mix plant 100TPH DBM/BM/SDC/Premix cum/h

Hot mix plant 60 t0 90TPH DBM/BM/SDC/Premix cum/h

PM-012 Hydraulic broom with tractor Surface cleaning sqm/h

Hydraulic Excavator 1 bucket Excavation hour

PM-013 Hydraulic Excavator 0.9 cum Excavation cum/h

PM-014 Hydraulic self propelled chip spreader Surface Dressing sqm/h

PM-015 Joint Cutting Machine with 2-3 blades Cutting of Joints h

Mastic cooker Mastic wearing coat Ton

PM-016 Mixall 6-10 t capacity Mixing of bituminous materials t/h

PM-017
Motor Grader Scarifier & levelling cum/h

PM-018 Needle vibrator Vibrating cement concrete mix cum/h

Paver finisher Hydrostatic with sensor control 100 Paving of


cum/h
TPH DBM/BM/SDC/Premix

Pneumatic sinking plant Pneumatic sinking of wells cum/h

.75 dia to 1.2m attatchment dia


Piling rig with bantonite pump Rm/hour
boring

B-8
Description of Output of Machine
Sr. No.

Machine Activity Unit

Prestressing Jack with access. Stressing of steel wire/strands

PM-019 Paver finisher Laying/spreading t/h

PM-020 Plate compactor Compaction cum/h

PM-021 Plate vibrator Compaction cum/h

Rotavator Scarifying cum/h

Ripper Scarifying cum/h

Road marking machine Road marking Sqm/hr

PM-022 Screed vibrator Compaction cum/h

Compaction of Sub-base/
PM-023 Smooth wheeled 80-100 kN tandem roller cum/h
Asphalt

PM-024 Stone crusher (Integrated) of 200 TPH Crushing of Spalls t/h

PM-025 Three wheel 80-100 kN Static Roller Compaction/ Rolling


Earth:- Embankment or sub-
grade cum/h

Sub-base G-I cum/h

Sub-base G-II/G-III cum/h

WMM cum/h

BUSG cum/h

BM 50/75 mm cum/h

Premix 20 mm sqm/h

Seal Coat sqm/h

Surface Dressing 1st Coat sqm/h

Surface Dressing 2ndCoat sqm/h

B-9
Description of Output of Machine
Sr. No.

Machine Activity Unit

PM-026 Tipper 5.5 cum/10 t Carriage cum/trip

PM-027 Tractor with Disc Harrows Pulverisation of soil cum/h

Ripping Pavements, uprooting


PM-028 Tractor with ripper @ 60 cum per hour cum/h
trees

PM-029 Tractor with trolley Transportation of materials t/trip

PM-030 Tractor with Rotavator Scarifier cum/h

Tractor with Grader Grading cum/h

Transit mixure 4.0/4.5cum Transportation of concrete mix cum/h

Transit mixure 4.0/4.5cum Transportation of concrete mix cum/h

PM-031 Truck 10 t capacity Carriage cum/trip

PM-032 Compaction of soil WMM cum/h


Vibratory roller 80-100 kN
Compaction of BM cum/h

PM-033 Water tanker 6 kl capacity (Truck Mounted) Carriage of water litre / h

PM-034 Wet mix plant (Pug Mill) Wet Mix cum/h

B-10
BASIC RATES
GE RATES OF PLANT & MACHINERY
Hire charge
per hour in
Usage rate per
Rs
Output of Machine hour in Rs
(Excluding
(Including Fuel)
fuel)

Output Unit Rate

210.00 per hour 435.00

50.00 per hour 12,379.00

35.00 per hour 6,584.00

20.00 per hour 1,957.00

13.00 per hour 1,590.00

1750.00 per hour 954.00

400.00 per hour 164.00 212.00

2000.00 per hour 2,120.00

1750.00 per hour 954.00

1.50 per hour 234.00

1.00 per hour 15.00

2.50 per hour 162.00 188.00

per hour 1,136.00

per hour 759.00

per hour 318.00

per hour 685.00

200.00 2096.00 2,260.00


per hour
100.00

300/150/250 3,194.00

B-11
Hire charge
per hour in
Usage rate per
Rs
Output of Machine hour in Rs
(Excluding
(Including Fuel)
fuel)

Output Unit Rate

1,859.00

100.00 per hour 437.00 2,073.00

per hour 717.00

45.00 511.00 1,341.00


per hour
100.00

40.00 22,823.00
per hour
30.00 16,575.00

25.00 14,115.00

1250.00 337.00
per hour

60/60/60 1006.00 1,500.00


per hour
100.00 1,635.00

1500.00 per hour 2,380.00

per hour 150.00

1.00 per hour 56.00

8.00 per hour 445.00 1,686.00

200.00 2276.00 3,075.00


per hour
50.00

3.50 per hour 101.00

40.00 per hour 1,129.00

1.5 to 2.00 per hour 3,453.00

2 to 3 per hour 4,665.00

B-12
Hire charge
per hour in
Usage rate per
Rs
Output of Machine hour in Rs
(Excluding
(Including Fuel)
fuel)

Output Unit Rate

per hour 113.00

75.00 per hour 883.00

per hour 218.00

per hour 218.00

25.00 per hour 22.00

60.00 per hour 31.00

100.00 per hour 192.00

per hour

30.00 per hour 1,039.00

200.00 per hour 14,389.00

652.00

80/70 652.00

10.00 652.00

8.00 652.00

16.00 652.00

10.00 per hour 652.00

12.00 652.00

250.00 652.00

500.00 652.00

400.00 652.00

500.00 652.00

B-13
Hire charge
per hour in
Usage rate per
Rs
Output of Machine hour in Rs
(Excluding
(Including Fuel)
fuel)

Output Unit Rate

5.50 per hour 850.00

80.00 per hour

60.00 per hour 440.00

3 to 5 per hour 409.00

25.00 per hour 431.00

25.00 per hour 431.00

4.50 per hour 828.00

4.50 Ton/km 40.00

5.50 per hour 825.00

100.00 1,687.00
per hour
60.00

12000.00 per hour 440.00

25.00 per hour 1,149.00

B-14
BASIC RATES
(A) Labour

Sl. No. Description of Labour Unit Rate (Rs.)

L-01 Bhisti day 244.56

L-02 Bitumen Sprayer day 244.56

L-03 Blacksmith day 458.55

L-04 Blaster day 356.65

L-05 Carpenter 1st Class day 458.55

L-06 Chips spreader day 244.56

L-07 Chiseller day 285.32

L-08 Dresser (Skilled) day 356.65

L-09 Driller day 356.65

L-10 Electrician day 458.55

L-11 Fitter day 458.55

L-12 Mason (1st class) day 458.55

L-13 Mason (2nd Class) day 285.32

L-14 Mate day 356.65

L-15 Mazdoor (Unskilled) day 244.56

L-16 Mazdoor (Semi skilled) day 285.32

L-17 Mazdoor (Skilled) day 356.65

L-18 Painter (Ist class) day 458.55

L-19 Plumber day 458.55

L-20 Surveyor day 458.55

L-21 White Washer day 285.32

A-15
BASIC RATES
(C) Material

Sl. No. Description Unit

M-001 AC pipe 100 mm m

M-002 Aggregate - For 37.5 mm Maximum size - 22.4 mm to 5.6 mm cum

M-003 Aggregate - For 37.5 mm Maximum size - 45 mm to 22.5 mm cum

M-004 Aggregate - For 37.5 mm Maximum size - Below 5.6 mm cum

M-005 Aggregate - For 53 mm Maximum size - 22.5 mm to 5.6 mm cum

M-006 Aggregate - For 53 mm Maximum size - 63 mm to 45 mm cum

M-007 Aggregate - For 53 mm Maximum size - Below 5.6 mm cum

M-008 Aggregate - Grading I (40 mm nominal Size) 10 mm - 5 mm cum

M-009 Aggregate - Grading I (40 mm nominal Size) 25 mm – 10 mm cum

M-010 Aggregate - Grading I (40 mm nominal Size) 37.25 mm - 25 mm cum

M-011 Aggregate - Grading I (40 mm nominal Size) 5 mm and below cum

M-012 Aggregate - Grading II (19 mm nominal Size) 10 mm - 5 mm cum

M-013 Aggregate - Grading II (19 mm nominal Size) 25 mm – 10 mm cum

M-014 Aggregate - Grading II (19 mm nominal Size) 5 mm and below cum

M-015 Aggregate 10 mm cum

M-016 Aggregate 20 mm cum

M-017 Aggregate 40 mm cum

M-018 Aggregate 10 mm (Natural Gravel) cum

M-019 Aggregate 20 mm (Natural Gravel) cum

M-020 Aggregate 40 mm (Natural Gravel) cum

M-021 Aggregate- Crushable type such as moorum or Gravel for Grading I cum

M-022 Aggregate- Crushable type such as moorum or Gravel for Grading II cum

M-023 Aggregate- Crushable type such as moorum or Gravel for Grading III cum

M-024 Aggregate-Grading I 90 mm to 45 mm cum

M-025 Aggregate-Grading II 63 mm to 45 mm cum

M-026 Aggregate-Grading III 53 mm to 22.4 mm cum

C-16
Sl. No. Description Unit

M-027 Aggregates 22.4 mm to 2.36 mm for wet mix macadam cum

M-028 Aggregates 45 mm to 22.4 mm for wet mix macadam cum

M-029 Aluminium sheeting (1.5 mm thick) sqm

M-030 Aluminium Studs 100 mm x 100 mm fitted with lense reflectors Nos.

M-031 Bamboo (1st Class) 85 mm - 100 mm dia, 2.0 m long No.

M-032 Bamboo (1st Class) 85 mm - 100 mm dia, 2.5 m long No.

M-033 Bamboo (1st Class) 85 mm - 100 mm dia, 3.0 m long No.

M-034 Bamboo (1st Class) 85 mm - 100 mm dia, 4.5 m - 5.5 m long No.

M-035 Bamboo (2nd Class) 75mm dia, 1.8 m - 2.5 m long No.

M-036 Bamboo (2nd Class) 75mm dia, 2.1 m - 3.0 m long No.

M-037 Barbed wire kg

M-038 Binding Material cum

M-039 Binding wire kg

M-040 Bitumen (Crumb Rubber Modified) tonne

M-042 Bitumen (Polymer Modified) tonne

M-043 Bitumen (S-65) tonne

M-044 Bitumen (S-90) tonne

M-045 Bitumen Emulsion (RS-1) tonne

M-046 Bitumen Emulsion (SS-1) tonne

M-047 Bitumen Emulsion (MS) tonne

M-048 Bituminous sealant litre

M-049 Blasted rubble cum

M-050 Blasting material kg

M-051 Bond stone (400 mm x 150 mm x 150 mm) No.

M-052 Brick 1st Class No.

M-053 Cement t

M-054 Cement Primer litre

M-055 Compensation for earth taken from private land cum

C-17
Sl. No. Description Unit

M-056 Compressible Fibre Board sqm

M-057 Copper plate kg

M-058 Corbelling Stones (300 mm x 150 mm x 150 mm) No.

M-059 Quarried Stone 150-200 mm size kg

M-060 Credit for excavated rock found suitable for use cum

M-061 Crow bars 40 mm dia (hire charges) hour

M-062 Crushed Sand or Grit Passing 2.36 mm and retained on 180 micron cum

M-063 Crushed Slag cum

M-064 Crushed Stone Aggregate 26.5 mm to 75 micron cum

M-065 Crushed Stone Chipping 13.2mm nominal size cum

Crushed Stone Chipping 6.7 mm size 100% passing 11.2 mm and retained
M-066 cum
on 2.36 mm

Crushed Stone Chipping 6.7 mm size 100% passing 9.5 mm and retained
M-067 cum
on 2.36 mm

M-068 Crushed Stone chipping 9.5 mm nominal size cum

M-069 Crushed Stone Coarse Aggregate Passing 53 mm and retained on 2.8 mm cum

M-070 Curing compound litre

M-071 Edge Stone (450 mm x 350 mm x 100 mm) No.

M-072 Edge Stone (450 mm x 350 mm x 200 mm) No.

M-073 Electric Detonator each

M-074 Epoxy Paint litre

M-075 Epoxy Primer litre

M-076 Farmyard manure cum

M-077 Fevicol adhesive kg

M-078 Filter media cum

M-079 Fine aggregate/Crushed sand 2.36 mm to 75 micron cum

M-080 Galvanised angle kg

M-081 Galvanised angle Section 100 mm x 100 mm of 12 mm thickness kg

M-082 Gelatine 80 per cent kg

C-18
Sl. No. Description Unit

M-083 GI Pipe 100 mm dia m

M-084 GI Pipe 50 mm dia m

M-085 GI wires kg

M-086 Graded stone aggregate cum

Granular material (Natural occuring, soil gravel mixture / quarry waste,


M-087 cum
kankar, laterite, dhandla

M-088 Hand Broken Metal 40 mm size cum

M-089 Jute netting, open weave 25 mm square opening sqm

M-090 Jute rope 12 mm dia m

M-091 Key Aggregates passing 22.4 mm and retained on 2.8 mm cum

M-092 Lime t

M-093 Lime putty t

M-094 Local Wood Piles (1st Class) 150-200 mm dia ,6m long No.

M-095 Local Wood Piles (1st Class) 100 mm x 75 mm cum

M-096 Loose stone cum

M-097 MS clamps Nos.

M-098 MS Flat / Structural Steel t

M-099 MS Sheet Tube (47 mm x 47 mm x 12 SWG Sheet) kg

M-100 MS Sheet 1.5 mm thick sqm

M-101 MS Sheet 2 mm thick sqm

M-102 Nuts, Bolts and Rivets t

M-103 Paint (Synthetic Enamel) litre

M-104 Plasticizer litre

M-105 Polythene sheet (125 micron) sqm

M-106 Polythene Sheething Nos.

M-107 Quarried Stone 150-200 mm size cum

M-108 RCC Pipe NP3 (1200 mm dia) m

M-109 RCC Pipe NP3 (1000 mm dia) m

C-19
Sl. No. Description Unit

M-110 RCC Pipe NP4 (1200 mm dia) m

M-111 RCC Pipe NP4 (1000 mm dia) m

M-112 RCC Pipe NP3 (600 mm dia) m

M-113 Red-oxide Primer litre

M-114 Road marking paint litre

M-115 Sand (Coarse) cum

M-116 Sand (Fine) cum

M-117 Seeds kg

M-118 Steel Pipe 50 mm dia m

M-119 TMT - IS 1786 (Fe-500 D) Primary Producer t

M-120 MS bar - IS 1786 (Fe-500 ) Primary Producer t

M-121 TMT - IS 1786 (Fe-500 D) Secondary Producer t

M-122 Stone Boulder of size 150 mm and below cum

M-123 Stone Chips 12 mm size cum

M-124 Stone Chips 6.7 mm size cum

M-125 Stone Chips 13.2 mm to 5.6 mm cum

M-126 Stone Crushed Aggregate 11.2 mm to 0.09 mm cum

M-127 Stone for Coarse Rubble Masonry 1st Sort cum

M-128 Stone for Coarse Rubble Masonry 2nd Sort cum

M-129 Stone for Random Rubble Masonry cum

M-130 Stone for Stone Set Pavement (300 mm x 200 mm x 150 mm) No.

M-131 Stone Screening - Type A 13.2 mm for Grading-1 cum

M-132 Stone Screening - Type A 13.2 mm for Grading-2 cum

M-133 Stone Screening - Type B 11.2 mm for Grading-2 cum

M-134 Stone Screening - Type B 11.2 mm for Grading-3 cum

M-135 Stone spall cum

M-136 Traffic cones No.

M-137 Water kl

C-20
Sl. No. Description Unit

M-138 Well graded Granular Base Material - Grading A 2.36 mm below cum

M-139 Well graded Granular Base Material - Grading A 26.5 mm to 4.75 mm cum

M-140 Well graded Granular Base Material - Grading A 53 mm to 26.5 mm cum

M-141 Well graded Granular Base Material - Grading B 2.36 mm below cum

M-142 Well graded Granular Base Material - Grading B 26.5 mm to 4.75 mm cum

M-143 Well graded Granular Base Material - Grading C 2.36 mm below cum

M-144 Well graded Granular Base Material - Grading C 9.5 mm to 4.75 mm cum

M-145 Well Graded Material for Sub-Base - Grading I 2.36 mm below cum

M-146 Well Graded Material for Sub-Base - Grading I 53 mm to 9.5 mm cum

M-147 Well Graded Material for Sub-Base - Grading I 9.5 mm to 2.36 mm cum

M-148 Well Graded Material for Sub-Base - Grading II 2.36 mm below cum

M-149 Well Graded Material for Sub-Base - Grading II 26.5 mm to 9.5 mm cum

M-150 Well Graded Material for Sub-Base - Grading II 9.5 mm to 2.36 mm cum

M-151 Well Graded Material for Sub-Base - Grading III 2.36 mm below cum

M-152 Well Graded Material for Sub-Base - Grading III 4.75 mm to 2.36 mm cum
M-153 Well Graded Material for Sub-Base - Grading III 9.5 mm to 4.75 mm cum

M-154 Wooden sleepers (250 mm x 250 mm x 125 mm) (hire charges) No.

C-21
BASIC RATES
(C) Material

Rate at Plant
(Rs.)

60.00

1,440.50

1,623.00

1,104.00

1,140.50

1,936.00

1,104.00

1,510.00

1,827.00

1,619.00

1,104.00

1,846.50

1,827.00

1,104.00

1,916.00

1,777.00

1,500.00

1,364.00

1,463.00

1,221.00

1,029.00

1,029.00

1,029.00

1,837.00

1,936.00

2,035.00

C-22
Rate at Plant
(Rs.)

1,440.50

1,623.00

438.00

438.00

200.00

200.00

200.00

200.00

120.00

120.00

78.00

220.00

80.00

36,420.00

32,880.00

39,783.00

38,826.00

28,229.00

27,509.00

28,429.00

18.36

650.00

64.00

54.00

8.00

6,200.00

120.00

C-23
Rate at Plant
(Rs.)

976.00

585.00

30.00

70.00

168.00

10.00

698.00

550.00

1,827.00

1,599.50

1,510.00

1,807.00

1,510.00

1,174.50

80.00

80.00

15.00

410.00

373.00

56.00

230.00

1,013.00

698.00

70.00

450.00

120.00

C-24
Rate at Plant
(Rs.)

900.00

450.00

75.00

1,554.00

698.00

1,500.00

76.00

90.00

1,440.50

6,608.00

7,000.00

7,000.00

32,400.00

1,500.00

19.00

60,000.00

83.00

55.00

65.00

80,000.00

250.00

102.00

12.00

12.00

898.00

8,570.00

6,340.00

C-25
Rate at Plant
(Rs.)

10,370.00

8,579.00

2,618.00

165.00

90.00

950.00

850.00

31.00

131.00

40,763.00

41,525.00

34,492.00

1,055.00

1,510.00

1,807.00

1,599.50

1,510.00

1,135.00

1,135.00

1,135.00

170.00

799.50

799.50

710.00

710.00

987.00

1,229.00

40.00

C-26
Rate at Plant
(Rs.)

698.00

1,089.00

1,124.00

698.00

1,089.00

698.00

1,084.00

698.00

1,119.00

1,041.50

698.00

1,101.00

1,041.50

698.00

1,029.00
1,041.50

45.00

C-27
CHAPTER-1

LOADING, UNLOADING,CARRIAGE,CRUSHING OF MATERIALS AND SETTING OUT


Preamble:

6
CHAPTER-1

LOADING, UNLOADING,CARRIAGE,CRUSHING OF MATERIALS AND SETTING OUT


Preamble:

The rates of loading and unloading of various items include stacking.

The rates for loading and unloading has been given both by manual and mechanical means. Means of
loading/unloading appropriate to the work and site is to be adopted

The rates for haulage of materials has been provided in terms of tonne-kilo metre (tkm) for ease of adoption
depending upon the lead in km and load in tonnes.

The cost of carriage will vary depending upon the riding surface of the road.Provision has accordingly been
made considering surfaced roads,subsurface gravel roadsand katcha tracks.

Rates for carriage of materials is exclusive of the loading ,unloading and stacking and this has to be added as
applicable.

Carriage of materials if done by boats shall be paid at the same rates as given for carriage of materials by road.
Chapter – 2

SITE CLEARANC
Preamble:

10

11

12

13
Chapter – 2

SITE CLEARANCE
Preamble:

Unless otherwise stated, the rates include sorting and disposal of unserviceable material and stacking of serviceable
material with all lifts and upto a lead of 1000 m.

The rates include Tools & Plants (T&P) and scaffolding required for items of dismantling.

Carriage of dismantled materials, bushes, branches of tree, etc. has been catered with a tractor-trolley of 3 tonnes
capacity with manual loading and unloading @ 2 trips per hour within a lead of 1000 m. This will be economical for
such works as compared with a tipper.

Where only grass wild growth is met with, rate of item No.2.1, i.e., clearing grass and removal of rubbish can be
applied.

The dismantling of structures has been catered both by manual and mechanical means. The Engineer can use his
discretion depending upon quantum of work and particular site conditions.

Rate analysis for removing of stumps and roots has also been provided separately.

Dismantling of Hume pipes has been catered manually as pipes can be easily rolled by men to a suitable stacking
place within the right-of-way.

For dismantling of structures, which remain submerged in water, the cost may be enhanced by 50 per cent. If site
conditions warrant lowering of water level to facilitate dismantling, the cost may be enhanced by additional 25 per
cent.

Dismantling of utilities, like, water supply lines, electric and telephone lines is required to be done under the
supervision of concerned departments with prior information to the user public.

In certain items of dismantling, like, pipe culverts, utilities, etc. excavation in earth and dismantling of masonary
works is not included in this analysis for which suitable notes have been inserted in respective Chapters. These
items are required to be priced separately based on actual quantities at site and nature of work.

The dismantled materials should be examined and a realistic assessment and provision should be made after due
process for the salvage value for such materials, which can be utilized for works or auctioned.

In case where lead for disposal is more than 1000 m, extra cost of carriage is required to be added based on tonne-
kilometerage as per Chapter 1.

All minor Tools & Plants (T&P) items required for dismantling have been considered to have been included in
overhead charges.
Chapter – 3

EARTHWORK, EROSION CONTR


Preamble:

10

11

12

13

14

15

16
Chapter – 3

EARTHWORK, EROSION CONTROL AND DRAINAGE


Preamble:

The rates have been analysed using mechanical means. Manual means for certain items have also been provided
which can be used for areas inaccessible to machines and also for small jobs.

In the rate analyses of earthwork, compacted volume of earth has been considered.

Cutting of earth by dozer has been proposed where the cut earth can be utilized for filling for embankment within a
lead upto 100 m.

Where lead for transporting of earth is more than 100 m, excavator and tipper have been provided.

The rate caters for disposal of unsuitable soil only upto a distance of 1 km. The cost of transportation beyond the
initial lead of 1 km will be paid separately based on tonne-kilometerage.

The replacement of unsuitable soil by suitable soil shall be provided separately in the estimate. The rate analysis for
removal of unsuitable soil does not provide for replacement by suitable soil.

In cases where embankment is constructed with earth taken from roadway, the cost of depositing the earth at the site
of embankment is already included in the disposal of excavated earth and, therefore, the input of dozer for spreading
earth can be deleted.

For narrow and restricted areas, plate compactor has been proposed for compaction to achieve the desired density.

In case excavated rock is found suitable for incorporation in works, suitable credit for the available rock shall be given.

For excavation of structures refer to Chapter 11 dealing with items of Foundation.

The possibility of using the blasted rock fragments for backfilling behind structures or backfilling of foundation pits or
filling in medians/separators or use in service road shall be examined before proposing disposal of excavated rock.

For inhabited areas, controlled blasting with limited charges of explosives has been provided. This involves smaller
drill holes and additional requirement of electric detonators. Provision has been made accordingly.

Any work involved for crossing of water courses for irrigation purpose, etc. will be priced under respective items, like,
excavation, grubbing, clearing, etc. for which rate analysis have separately been made.

Earth excavated from drains can be used in roadway berms. Hence carriage for disposal of same is not provided.

In case of rock fill embankment, it is assumed that material is available at site from rock cutting.

For widening of existing pavement less than 1.8 m, the rates for all items of this Chapter may be increased by 30 per
cent.
Chapter – 4

GRANULAR SUB-BASES, BASES (NON-BITUMINOUS) AND SHOULDERS

Preamble:

1 For construction of sub-base, two alternatives as under have been provided.

a. Mix in place method

2 Construction of shoulders: - Earthen, Hard and Paved shoulders have been considered,
the rates applicable are for subgrade, sub-base and different layers of pavement
respectively.

3 In the case of improvement of subgrade with lime stabilization, soil is assumed to be


available at the site and has not been provided for. Only lime has been catered. In the
case of lime stabilization of sub-base, soil has been provided to form the sub-base

4 While providing for the rate of materials, detailed local enquires should be made and
prevailing market rates ascertained from concerned suppliers in the area keeping in view
the location of crushing plants and lead involved.

5 The quantities considered in the output are the compacted quantities.


Chapter – 5

BASES AND SURFACE COURSES (BITUMINOUS)


Preamble:

10

11
Chapter – 5

BASES AND SURFACE COURSES (BITUMINOUS)


Preamble:

Various alternatives for machines and materials have been provided. The one that suits a particular situation and
design may be adopted.

The outputs considered for construction equipment are for compacted quantities of relevant items and not for loose
quantities.

In case of prime coat and tack coat, average quantities of binder indicated in specifications have been taken.

Tack coat and prime coat, wherever provided, are required to be measured and paid separately.

Cleaning of surface is a part of the item of prime coat and tack coat. As such cleaning of surface has not been
provided for bituminous courses as the same is already catered in prime/tack coat. However, for those cases where
such coats are not required to be done, cleaning of surface shall be included and paid.

Rolling of bituminous courses is required to be done as per Clause 504.3.6 of MORD Specifications. Provision in the
analysis has been made accordingly. It has been observed during actual practice at work sites, that the availability of
road roller is generally inadequate. As compaction is the key to good construction, this point is being specifically
highlighted to ensure that adequate number of road rollers as per provision in the rate analysis are deployed at site.

Spreading of bituminous materials shall be done by mechanical means except in areas where a mechanical paver
cannot have access.

Hot Mazdoor is the one who work for Bitumen heating/spreading or spreading of hot bituminous mix. He will be paid
the same wages. However, he will be provided safety kits containing normally gumboots, hand gloves, dark goggles,
barnol, country soap, coconut oil, tarring outfits, etc. For this purpose, additional 0.5 per cent sundries have been
provided in the analysis of rates in addition to the normal sundries covered by overheads.

Where the proposed aggregates fail to pass the stripping value test, an approved adhesion agent shall be added to
the binder as per Clause 507.2.4 with the approval of the Engineer and cost of the adhesion agent shall be added
under the subhead of materials.

The Factor for usage of rollers has been taken as 0.65 in case of Bituminous Macadam only.

Rate analysis has been given separately using various types of bitumen, i.e., penetrations grade S90, S65, Polymer
Modified Bitumen and Natural Rubber Modified Bitumen to facilitate preparation of Standard Schedule of Rates.
Chapter-6
CEMENT CONCRETE PAVEMENT
Preamble:
1
Use of Cement concrete pavement for rural roads is likely to be limited to small stretches.These
will ,therfore, have to be constructed without use of heavy equipment,like,high capacity
batching/mixing plant and slip form pavers.Accordingly,the rate analysis is based on concrete
mixer of suitanle capacity with weigh batcher,fixed side forms and screed,plate and needle
vibrators.
2 Provision of plasticizer admixture to improve workability with reduced water cement ratio has been
made.
3 The rates of materials taken in the analysis are at site.The concrete mixture placement is also
assured close to the site of work so that transporting and placement of concrete can be done by
labour alone.
4 The rates of earthwork ,subgrade and sub-base may be adopted from chapters-3and 4 as
appropriate.
5 A Carriage cost of 50Km has been provided in the analysis for the items Interlocking Concrete
Block pavement and Edge Block.
Chapter – 7

CAUSEWAY AND SUBMERSIBLE BRIDGES


Preamble:

5
Chapter – 7

CAUSEWAY AND SUBMERSIBLE BRIDGES


Preamble:

The quantities of various items may be worked out from the design and drawings.

Rate analysis of various items involved in the construction of concrete causeway may be taken from relevant
Chapters.

RCC Hume Pipes of NP-3 and NP-4 (non-pressure types) have been considered in the analysis.

Rate analysis for items of submersible bridges may be based on the respective items of Chapters 11, 12 and 13
dealing with bridges. Rates for guide posts may be taken from Chapter 8.

Rate analysis of item of river training and protection works may be based on the respective items in Chapter 14
(Protection Works).
Chapter – 8

HILL ROADS
Preamble:

1 1. The Chapter covers only the analysis of rates for items which are peculiar to hill roads. For other items, referen
may be made to relevant Chapters and analysis modified as suggested in note 2 below.

2 Extra Provision for High Altitude Areas

Since there is no place at an altitude of 2100 m and above in Assam extra provision for man power as well
machines are not considered.
are peculiar to hill roads. For other items, reference
sted in note 2 below.

Assam extra provision for man power as well as


Chapter – 9

PIPE CULVERTS
Preamble:

6
Chapter – 9

PIPE CULVERTS
Preamble:

Pipe culverts of sizes 750 mm, 1000 mm and 1200 mm dia in single row and double row which are generally used on
roads, have been included. Providing and laying of pipe has been included in the rate analysis. Items of auxiliary
works such as excavation, bedding, backfilling, concrete and masonry shall be analysed, as provided under the
respective sections and paid for separately.

Analysis has been given separately for NP3 and NP4 pipes for ease of adoption.

Cost of any river training and protection work like stone pitching, apron, curtain wall etc. may be analysed under the
respective item included in Chapter 14.

The joining of pipes is proposed by collar joints.

Chain & pulley for lifting the pipes is considered part of overheads.

The thickness of first class bedding has been taken as 150 mm. The height of bedding has been taken as 1 of overall
height of pipe in the analysis. This may be modified as per thickness indicated in the approved drawing.
Chapter–10

TRAFFIC SIGNS, MARKINGS AND OTHER APPURTENANCES


Preamble:

7
Chapter–10

TRAFFIC SIGNS, MARKINGS AND OTHER APPURTENANCES


Preamble:

Rate analysis for fencing provides for Barbed wire fencing with R.C.C. M 15 grade concrete post.

Backfilling of foundation of boundary pillars has been proposed with stone spalls, tightly packed and compacted.

The item pertaining to road traffic signals has not been analysed as this is a specialized work and rates can be
obtained from firms having specialisation for design and installation of this work.

Two supports have been provided for direction and place identification signs where size is more than 0.9 square
metres. Only one support is provided for size upto 0.9 square metres.

The traffic signs proposed are of retro-reflectorised types made of encapsulated lens type reflective sheeting fixed
over aluminum sheeting and semi-reflective type on M.S. sheet.

The size and location of traffic signs shall be as per IRC:67.

Separate rate analysis has been made for tubular steel railing with RCC posts and MS steel posts.
Chapter – 11

FOUNDATION
Preamble:

10

11
Chapter – 11

FOUNDATION
Preamble:

Excavation for structures has been provided by and large by manual means.

The earth excavated from foundation has been proposed to be backfilled in the foundation trenches except for
marshy soil where disposal has been provided.

For excavation in marshy soil, extra provision of labour for filling with carted earth has been provided in a separate
item. Cost of carted earth may be worked out separately if the same is not available from the adjoining area.

The rock surface for foundations is to be prepared which has been analysed accordingly.

In case of rock, excavation has been considered upto a depth of 1500 mm for rock of ultimate crushing strength of 10
Mpa or more, which shall be reckoned as hard rock.

Dewatering has been provided in excavation for foundation on percentage basis. In case less dewatering is required
or is not required at all for a particular site condition, the same may be reduced/omitted.

Mixing of cement concrete has been considered by using concrete mixer with weigh batching facility fitted with water
measuring device. It is preferable to use concrete mixes fitted with load cells for weigh batching.

In remote areas, for isolated slab culvert/box culvert upto 2 m span, concrete can be hand mixed in accordance with
Clause 806 of MORD Specifications. Therefore, in the analysis, for items of concrete, the alternative of hand mixing
has also been considered.

Steel reinforcement for cement concrete work is required to be provided separately. The rate for the same has been
analysed using HYSD and TMT bars.

Necessary safety precautions shall be taken for excavation for open foundation for which guidance may be taken from
IS:3764. Cost of shoring and shuttering has been provided on percentage basis, which may be adjusted according to
site condition.

For brick masonry work, clay fly ash bricks of approved type can be used in accordance with Section 600 of MORD
Specifications and rate may be adopted accordingly.
Chapter – 12

SUBSTRUCTURE
Preamble:

10
Chapter – 12

SUBSTRUCTURE
Preamble:

The cost of formwork will vary with the height and cross-section of the substructure. Provision has been made
accordingly.

As the higher grade of concrete is costlier, the provision made for formwork on percentage basis has been suitably
adjusted to make it compatible with other grades.

Filter media and backfilling behind abutment are required to be provided as per guidelines in IRC:78- 2000.

Bearing shall be set truly level so as to have full and even seating.

The bearing should be procured only from those manufacturers who have been pre-qualified by MORTH.

For spans in gradient, the soffit shall be made horizontal specially at the supports and the bearing, where provided,
shall be placed horizontally.

Weep holes shall be provided as per specifications.

For elastomeric bearings, the concrete surface shall be leveled such that the variation is not more than 1.5 mm from a
straight edge placed in any direction across the area.

Note Nos. 7 to 12 of Chapter 11 will hold good for this Chapter also.
Chapter – 13

SUPERSTRUCTURE
Preamble:

1 The rate for wearing coat has been analysed as under in accordance with the provisions of MORD Specifications:

a.

b.

2 The rate analysis has been done for the following types of railings & parapet:

i.

ii.

iii.

iv.

v.

vi.

3 As per the MORD Specifications, the type of superstructure envisaged for minor bridges and culverts for rural r
are R.C.C. slabs and box culverts not exceeding 15 m span, rates for which have been analysed. Stone/Brick mas
arches can be adopted where hard strata is available at shallow depth. R.C.C. arches can also be adopted as
IRC:SP:20. Hence rates for these types of arches for span length upto 15 m have been analysed.

4 For composite type of superstructure, comprising of steel beams/built-up sections & R.C.C. deck slab, analysis
been done for steel section separately.

5 For slab culverts and minor bridges of spans not more than 10 m, buried joint/filler joint may be adequate.
relatively longer spans and for highly seismic intensity areas, elastomeric slab seal/compression seal joint ma
provided as per the MORD Specifications. Rates have been analysed accordingly.

6 In remote areas, for slab culverts and box culverts upto 2 m span, concrete used in superstructure can be hand m
with 10 per cent extra cement at contractor’s cost in accordance with Clause 806 of MORD Specifications. H
mixing shall not be otherwise permitted.

7 Slab seal/compression seal expansion joints are specialised items commercially produced by a number of firms.
rates for such items must be ascertained from firms pre-qualified by MORTH. Overheads for the above specia
manufactured items have been considered as 30 per cent instead of the usual 20 per cent for other items of b
works.

8
Chapter – 13

SUPERSTRUCTURE

The rate for wearing coat has been analysed as under in accordance with the provisions of MORD Specifications:

Bituminous type

Cement concrete

The rate analysis has been done for the following types of railings & parapet:

R.C.C. railing

M.S. railing

Pipe railing (suitable for submersible bridges)

Brick masonry parapet

Stone masonry parapet

P.C.C. parapet

As per the MORD Specifications, the type of superstructure envisaged for minor bridges and culverts for rural roads
are R.C.C. slabs and box culverts not exceeding 15 m span, rates for which have been analysed. Stone/Brick masonry
arches can be adopted where hard strata is available at shallow depth. R.C.C. arches can also be adopted as per
IRC:SP:20. Hence rates for these types of arches for span length upto 15 m have been analysed.

For composite type of superstructure, comprising of steel beams/built-up sections & R.C.C. deck slab, analysis has
been done for steel section separately.

For slab culverts and minor bridges of spans not more than 10 m, buried joint/filler joint may be adequate. For
relatively longer spans and for highly seismic intensity areas, elastomeric slab seal/compression seal joint may be
provided as per the MORD Specifications. Rates have been analysed accordingly.

In remote areas, for slab culverts and box culverts upto 2 m span, concrete used in superstructure can be hand mixed
with 10 per cent extra cement at contractor’s cost in accordance with Clause 806 of MORD Specifications. Hand
mixing shall not be otherwise permitted.

Slab seal/compression seal expansion joints are specialised items commercially produced by a number of firms. The
rates for such items must be ascertained from firms pre-qualified by MORTH. Overheads for the above specialized
manufactured items have been considered as 30 per cent instead of the usual 20 per cent for other items of bridge
works.
Chapter – 14

PROTECTION WORKS
Preamble:

1 Three types of aprons as under have been catered for:

a.

b.

c.

2 Pitching proposed is of the following types:

a.

b.

c.

3 A toe wall for toe protection of pitching can be either in random rubble masonry or in nominal mix cement
concrete M 10, or in brick masonry. Depending upon the design, the rates may be adopted.

4 Flooring has been proposed in dry rubble stone, rubble stone laid in cement mortar 1:3, cement concrete
blocks M 15 and brick on edge laid in cement mortar (CM) 1:3.

5 Curtain walls proposed are of the following types:

a.

b.

c.

6 Lead for stone materials from quarry to be considered in case of pitching and apron works.
Chapter – 14

PROTECTION WORKS
Preamble:

Three types of aprons as under have been catered for:

Boulder apron laid dry

Boulder apron laid in wire crates

Apron laid in cement concrete blocks of M 15 grade

Pitching proposed is of the following types:

Brick pitching

Boulder pitching

CC Block pitching

A toe wall for toe protection of pitching can be either in random rubble masonry or in nominal mix cement
concrete M 10, or in brick masonry. Depending upon the design, the rates may be adopted.

Flooring has been proposed in dry rubble stone, rubble stone laid in cement mortar 1:3, cement concrete
blocks M 15 and brick on edge laid in cement mortar (CM) 1:3.

Curtain walls proposed are of the following types:

Brick masonry in CM 1:4

Coursed rubble stone masonry (1st sort) is CM 1:3

Cement concrete M-10 grade

Lead for stone materials from quarry to be considered in case of pitching and apron works.
Chapter – 15

MAINTENANCE OF R
Preamble:

5
Chapter – 15

MAINTENANCE OF ROADS
Preamble:

In the case of rain cuts, it has been assumed that some material cut by rain, approximately 25 per cent will be
available at site which can be retrieved and re-used and the balance 75 per cent is required to be provided as fresh
material.

For making up earthen shoulders, it has been assumed that on an average 150 mm filling will be required. Similarly,
for stripping of excess soil from shoulder, an average depth of 75 mm has been assumed.

Pothole repairs and patchwork are provided to be done by using Mixall 6/10 M.T.

In case of maintenance of Gravel and W.B.M. surfaces, it has been assumed that 25 per cent material will be
available at site, which can be retrieved and re-used and the balance 75 per cent is required to be provided as fresh
material.
The items of periodical renewal by premix carpet and surface coating have also been included in the rate analysis
for guidance of field Engineers. The detailed analysis of various items of bituminous works is given in Chapter 5 and
rates can be taken from there as appropriate. Additional provision of patch repair and profile correction varying from
10 per cent to 30 per cent of the material of premix carpet/surface dressing may be made in the estimate of
periodical renewal.
1

3
3
Chapter-16

Miscellaneous items

Preamble

This Chapter includes various miscellaneous items, which are not covered by
MORD specification for Rural Road 2004.
A number of need items for Road works and Bridge work have been
incorporated in this chapter as per MoSRT&H specification for Road and Bridge
works also.

As per latest revised version of MoRD specification for rural RoadsSpecific


importance to some new items alongwith few new technologies like cold
mix,Semi dense Biituminous concrete,soil stabilization in subgrade and
Base,use of locally available marginal materials,Industrial wastes,provisions of
proper road signs and other traffic control devices,Geosynthetics,Jute geo
textiles alongwith construction of long span Bridges as per version of MORTH
has been included in this edition.

General:

a) The clauses of MoSRT&H specifications for Roads and Bridge


works,which have been mentioned for each item,may be referred to detail
specifications and construction procedure.The specifications mentioned here
are only brief description

b) Quality control works shall be goverened by section 900 of Mosrt&H


specifications

c) The classification of of soil shall be as per clause 301.2 of MoSRT&H


specifications.

d) The specification of materials shall be governed by section 1000 of


MoSRT&H specifications for Road and Bridge works.

e) Quantities of cement in various grade of cement concrete have been


taken as per IRC:21-2000 and IRC:18-2000.
f) The coarse and fine aggregate shall confirm to IS:383.
Road Works:
a) The machinary and equipment included in various analysis are as per
various specifications of MoSRT&H are mandatory.

b) Choice of grade of Bitumen shall be made as per the guidelines given in


Appendix-4 of MoSRT&H specifications.
c) The specification and requirement for modified binder with various type of
modifier have been laid down in clause 521 of MoRST&H specification and
IRC:SP:53-2002 which shall be followed.

d) The guideline given vide Annexure-A to clause 501 of MoSRT&H


specification in regard to protection of environment shall be followed for a
particular situation.

e) The quantities taken as output of the item in the rate are the compacted
quantities.
Bridge Works:
General:

a)The description of items is given briefly and linked with relevant clause of
MoSRT&H specification for Road&Bridge works, which may be refered for
detailed description, provisions and interpretation.

b)For concrete works admixtures has been used to provide best solution in
construction of superstructure of bridge works.Water reducing plasticizing
admixture such as Master plast PL-1 or its equivalent is used for concrete
works below M-25 grade concrete @ 100ml-200ml per bag of cement (50 kg
per bag). However super plasticizer such as Master plus SPL-2 or its equivalent
has been used for concrete above M-25 Grade @0.2 to 1.2 lit per bag of
cement to improve workability of concretre.Use of admixture should be made
with prior approval of the concerned Executive Engineer.
c) Normal method of curing has been covered in the schedule.Steam curing
has been included in the items of precast concrete PSC beams

d) The items do not cover all components of bridge projects for all
situations.There may be specialised items for specific cases,which need to be
analyzed keeping in view the basic approach.

Foundation:
a) Mixing of Cement concrete has been considered both by using concrete
mixure and batching plant.

b)Concrete batching plant is considered to be placed within 10 km of the


bridge site.

c)The coarse and fine aggregate for cement for cement concrete shall be as
per IS:383.

d)Pneumatic sinking is a specialized job.All safety bprecaution as per


IS:4138 are required to be taken.

e)The levelling course below pile cap is proposed with M 15 grade concrete.

f)Appendix-4 of IRC:78-2000 has to be referred regarding precaution to be


taken during sinking of well.
g)The concrete mix used in boottom plug shall have minimum cenment
content of 330kg/cum and a slum of vabout 150mm.

h)Necessary safety precautions shall be taken for excavation on open


foundations for which guidence may be taken from IS:3764
i) A levelling course of 100mm thickness in M10(1:3:6) shall be provided
before lying open fondations.
j) The well curb shall be in RCC of mix not leaner than M25 grade with
minimum steel reinforcement of 72kg/cum excluding bond rods.
k)The top of bottom plug shall be at least 300mm above top of curb.
l)In case of cement concrete piles, the minimum grade of concrete shall be
M35 with minimum cement content of 400kg/cum

m)The guidence for piles is to be obtained from IS:2911.32

n)In the items for well foundation, provision for normal island/temporarey
protection, deep islands/coffer-dams with wooden bellies and sheet piles have
been made.
Substructure:

a)Filter media and backfilling behind abutments are required to be provided


as per guidelines given in IRC:78-2000.
b)Weep holes shall be provided as per clause 2706 of MoSRT&H
specification.

c)In case of roller-cum-rocker bearings, only full circullar rollers are to be


provided

d)All bearings shall be set truly level so as to have full and even seating.

e)For elastomeric bearing pads, the concrete surface shall be levelled such
that the variation is not more than 1.5mm from a straight edge placed in any
direction across the area.

f)For spans in grade, the bearing shall be placed horizontal by using sole
plates for suitably designed RCC pedestals.
Superstructure:

a) The rate for anti-corrosive treatment is ascertained from firms specilized


in this work.In this connection circular No RW/NH-34041/44/91-S&R
dt.21.3.2000 of Ministry of Road Transport and Highways may be referred for
further details.
b) MoSR&TH's letter no RW/NH-34059/1/96/S&R dt 30.11.2000 and
subsequent corrigendum dt.25.1.2001 may be referred for detailed specification
and provisions for various types of expansion joints.
B)Cement concrete pavement.
a)High capacities batch mix plants of 75cum/hour (effective output) has
been considered in the rate analysis of cement concrete pavement works.
b)Super plasticizer admixture has been provided to improve workability with
reduced water cement ratio.
c)Cement 43 grades have been catered for cement concrete
pavement.However for dry lean concrete cement of 33 grade may be prefered.

C) The head Repairs


in works and Rehabilitation
where mixing includes
plant are used theinclusive
rates are items as of
foollows:
an initial
lead of 10km from mixing plant to work site.

D) Overheads and contractors profit: Due to usage of higher output of


plant and machineries, Overheads are considered @10%for item of road
works and 20%for items of Bridge works.Contractors profit is considered
@10% for both Road works and Bridge works.

E) VAT @ 5 % and Assam building and other construction workers welfare cess @
1%has been added in the analysis over above.

The other items includes Cold weather bridge ,Bamboo bridge,Timber


bridge, etc in APWD works which are not covered by MORD and MoSRT&H
Data book.
Summary of Rate Analysis

Item Description Unit Rate


No. (Rs.)

Chapter 1 - LOADING, UNLOADING, CARRIAGE CRUSHING OF MATERIALS AND SETTING OUT

1.1 Loading and Unloading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed
Slag, Stone for Masonry Work by Manual Means

(I) Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for Masonry cum 110.80
Work by manual means including a lead upto 30 m

(ii) Loading of Earth, Sand, Moorum, Manure, Flyash by manual means including a lead upto 30 m cum 55.40

(iii) Unloading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for cum 55.40
Masonry Work by manual means including a lead upto 30 m

(iv) Unloading of Earth,Sand, Moorum,Manure,Fly ash, by manual means including lead upto 30M cum 34.60

1.2 Loading and Unloading Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed
Slag, Stone for Masonry Work by Mechanical Means

I Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for Masonry cum 63.40
Work by mechanical means including a lead upto 30 m

ii Loading of earth,sand,moorum,manure,fly ash by mechanical means including a lead upto 30 M cum 33.30

iii Unloading of Earth, Sand, Lime, Moorum, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Manure, cum 13.90
Crushed Slag, Flyash, Stone for Masonry Work by mechanical means.

1.3 Loading, Unloading and Stacking of Bricks by Manual Means

I Loading of Bricks by manual means including a lead upto 30 m 1000 Nos. 189.50

ii Unloading and Stacking of Bricks by manual means including a lead upto 30 m 1000 Nos. 189.50

1.4 Loading and Unloading of Cement by Manual Means

I Loading of Cement by manual means including a lead upto 30 m t 682.40

ii Unloading of Cement by manual means including a lead upto 30 m t 136.50

1.5 Loading and Unloading of Structural Steel and Steel Bars by manual means

I Loading of Structural Steel, Steel Bars by manual means including a lead upto 30 m t 145.10

ii Unloading of Structural Steel, Steel Bars by manual means including a lead upto 30 m t 145.10

1.6 Loading and Unloading of Bitumen Drums by Manual Means

I Loading of Bitumen Drums by manual means including a lead upto 30 m t Err:508

ii Unloading of Bitumen Drums by Manual Means including a lead upto 30 m t 151.00

1.7 Loading and Unloading of Timber by Manual Means

I Loading of Timber by manual means including a lead upto 30 m t 243.90

ii Unloading of Timber by manual means including a lead upto 30 m t 243.90

1.8 Loading and Unloading of C.C. Blocks, Kerb, etc.

I Loading with care C.C. Blocks, km Stone, 200 m Stone, Boundary Pillar, Kerb, Channel, Bond Stone, etc. by manual cum 359.00
means including a lead upto 30 m

ii Unloading with care C.C. Blocks, km Stone, 200 m Stone, Boundary Pillar, Kerb, Channel, Bond Stone, etc. by manual cum 359.00
means including a lead upto 30 m

1.9 Loading and Unloading of Hume Pipes


Item Description Unit Rate
No. (Rs.)

I Loading of RCC Hume pipes by mechanical means including a lead upto 30 m

A. 1000 / 1200 mm dia Hume pipe per pipe 78.50

B. 750 mm dia Hume pipe per pipe 47.10

C. 600/450 mm dia Hume pipe per pipe 33.60

II Unloading of RCC Hume pipe by manual means including a lead upto 30 m

A 1000/1200 mm dia RCC Hume pipes per pipe 447.50

B. 750 mm dia Hume pipe per pipe 372.90

C. 600/450 mm dia Hume pipe per pipe 279.70

III Unloading of RCC Hume pipes by mechanical means including a lead upto 30 m

A 1000/1200 mm dia Hume pipe per pipe 53.90

B 750 mm dia Hume pipe per pipe 32.40

C. 600/450 mm dia Hume pipe per pipe 23.10

1.10 Haulage excluding Loading & Unloading

Haulage of materials by tipper excluding cost of loading, unloading and stacking.

Case-I : Surfaced Road t.km 8.20

Cum/km 14.90

Case-II: Unsurfaced Gravel Road t.km 10.20

Cum/km 18.50

Case-III: Katcha Track and Track in River Bed/Nallah Bed and Choe Bed t.km 16.00

Cum/km 29.10

1.11 Supply of Quarried stone and hand breaking


Supply of quarried stone and hand breaking into coarse aggregate to Grading 1 (90 mm to 45 mm) as per Table 400.8 of cum 1,461.00
Technical Specifications.

Supply of quarried stone and hand breaking into coarse aggregate to Grading 2 (63 mm to 45 mm) as per Table 400.8 of cum 1,548.00
Technical Specifications.

Supply of quarried stone and hand breaking into coarse aggregate to Grading 3 (53 mm to 22.4 mm) as per Table 400.8 of cum 1,635.00
Technical Specifications.

1.12 Crushing of Stone Aggregates 100 per cent passing through 53 mm sieve as per Table 500.6 of Technical Specifications.

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 t/h capacity comprising of primary cum 1,248.60
and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates 100 per cent passing
through 53 mm sieve as per Table 500.6 of Technical Specifications including the cost of stone.

1.13 Crushing of Stone Aggregates 100 per cent passing through 22.4 mm sieve as per Table 500.6 of Technical Specifications.

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 t/h capacity comprising of primary cum 1,446.80
and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates 100 per cent passing
through 22.4 mm sieve as per Table 500.6 of Technical Specifications including the cost of stone.

1.14 Crushing of Stone Aggregates Nominal Size 13.2 mm as per Table 500.9 of Technical Specifications.

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 t/h capacity comprising of primary cum 1,705.00
and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 13.2 mm nominal size as
per Table 500.9 of Technical Specifications including the cost of stone.
Item Description Unit Rate
No. (Rs.)

1.15 Crushing of Stone Aggregates 9.5 mm Nominal Size as per Table 500.9 of Technical Specifications.

1.16 Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 t/h capacity comprising of primary
Setting Out cum 1,705.00
and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 9.5 mm nominal size as
per Table 500.9 of Technical Specifications including the cost of stone.
Unit=1Km

The analysis of rate per km shall account for the following:

(I) Reference benchmark one no.

(ii) Working benchmark 4 nos. per Km and near all drainage

structure and bridges.

(iii0 Reference pillars/Burjees @ 50 m interval on both sides of

formation width.

(iv) The marking of centre line setting out curves and recording

of levels,etc. by the surveyor will be incidental to the work and

no extra payment shall be made for the same.

(v) Typical benchmark as per Drawing 200.1 each 6911.10

(vi)Typical reference pillar as per Drawing 200.2 each 3437.90

Chapter 2 - SITE CLEARANCE

2.1 Clearing Grass and Removal of Rubbish

Clearing grass and removal of rubbish up to a distance of 30 m outside the periphery of the area as per Technical
Specification Clause 201.

By Manual Means hectare 11,647.20

2.2 Clearing and Grubbing Road Land

Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth
upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not
exceeding 150 mm in thickness as per Technical Specification Clause 201.

(I) By Manual Means


(A) In area of non thorny jungle hectare 42,648.30
In area of thorny jungle hectare 61,247.30
(ii) By Mechanical Means

In area of non-thorny jungle hectare 23,724.00


In area of thorny jungle hectare 28,954.10
2.3 Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps

Cutting of trees, including cutting of trunks, branches and removal of stumps & roots, refilling, compaction of backfilling and
stacking of serviceable material by manual means with all lifts as per Technical Specification Clause 201.

A Lead upto 100 m

I Girth above 300 mm to 600 mm each 206.90

ii Girth above 600 mm to 900 mm each 358.70

iii Girth above 900 mm to 1800 mm each 711.20

iv Girth above 1800 mm to 2700 mm each 1,358.00

v Girth above 2700 mm to 4500 mm each 2,789.60

vi Girth above 4500 mm each 8,199.70

B Lead upto 1000 m

I Girth above 300 mm to 600 mm each 220.70

ii Girth above 600 mm to 900 mm each 400.10

iii Girth above 900 mm to 1800 mm each 766.40

iv Girth above 1800 mm to 2700 mm each 1,440.80


Item Description Unit Rate
No. (Rs.)

v Girth above 2700 mm to 4500 mm each 2,881.60

vi Girth above 4500 mm each 8,429.80

2.4 Uprooting and Removing Stumps & Roots

Uprooting and removing stumps & roots,compaction of backfilling and staking of


servicable material by manual means as per Technical Specification clause 201.
as per Technical Specification Clause 201
A Lead upto 100 m

I Girth above 300 mm to 600 mm each 124.80

ii Girth above 600 mm to 900 mm each 197.70

iii Girth above 900 mm to 1800 mm each 419.40

iv Girth above 1800 mm to 2700 mm each 826.60

v Girth above 2700 mm to 4500 mm each 1,665.70

vi Girth above 4500 mm each 4,712.80

B Lead upto 1000 m

I Girth above 300 mm to 600 mm each 128.00

ii Girth above 600 mm to 900 mm each 209.20

iii Girth above 900 mm to 1800 mm each 433.20

iv Girth above 1800 mm to 2700 mm each 845.00

v Girth above 2700 mm to 4500 mm each 1,688.70

vi Girth above 4500 mm each 4,827.80

2.5 Dismantling of Structures


Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement
concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material,
disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical
Specification Clause 202.

I By Manual Means
(A) Lime Concrete cum 288.30
(B) Cement Concrete cum 365.60

© Reinforced Cement Concrete cum 978.30

II By Mechanical Means
(A) Cement Concrete cum 376.90
(B) Reinforced Cement Concrete cum 591.20

2.6 Dismantling Brick/Tile Work


Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry,
including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per
Technical Specification Clause 202.

(A) Lime mortar cum 171.80


(B) Cement mortar cum 226.40
© Mud Mortar Mud Morter cum 155.90
(D) Dry Brick Pitching or Brick Soling cum 144.20

2.7 Dismantling Stone Masonry as per Technical Specification Clause 202.

Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry,
including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per
Technical Specification Clause 202.

(A) Rubble Stone Masonry in Lime Mortar cum 220.70

(B) Rubble Stone Masonry in Cement Mortar cum 175.00

© Rubble Stone Masonry in Mud Mortar cum 171.80

(D) Dry Rubble Masonry cum 160.20

(E) Dismantling Stone Pitching / Dry Stone Spalls cum 159.50


Item Description Unit Rate
No. (Rs.)

(F) Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials cum 197.50

2.8 Dismantling Wood Work Wrought and Planed Fixed in Frames of Trusses upto a height of 5 m above Plinth Level cum 501.60
as per Technical Specification Clause 202.

2.9 Dismantling Steel Work in all Types of Sections upto a height of 5 m above Plinth Level excluding Cutting of rivet
as per Technical Specification Clause 202.

(A) Including dismembering t 1,341.60

(B) Excluding dismembering t 947.70

© Extra over Items (A) and (B) for cutting rivets t 10.70

2.10 Scraping of bricks dismantled from brick work including stacking as per Technical Specification Clause 202. 1000 Nos. 1,019.10

2.11 Scraping of Stone from Dismantled Stone Masonry as per Technical Specification Clause 202.

In Cement or Lime Mortar cum 409.30

2.12 Scraping Plaster in Lime or Cement Mortar from Brick / Stone Masonry as per Technical Specification Clause 202. sqm 13.10

2.13 Removing all types of Hume pipes and stacking within a lead of 1000 m including Earthwork and Dismantling of
Masonry Works as per Technical Specification Clause 202.

(A) Upto 600 mm dia Hume pipe m 151.10


(B) Above 600 mm to 900 mm dia Hume pipe m 204.60
(C) Above 900 mm dia Hume pipe m 350.20
Note : 1. The excavation of earth,dismantling of stone masonary
work in head walls and protection works is not included which is
to be measured and paid seperately.
2. Credit for retrives stone from masonary work may be
taken as per actual availability.
2.14 Dismantling of Flexible Pavements

Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 100 m, stacking serviceable and
unserviceable materials separately as per Technical Specification Clause 202

I By Manual Means
(A) Bituminous Courses cum 531.80
(B) Granular Courses cum 388.00
II By Mechanical Means
(A) Bituminous Courses cum 226.50
2.15 Dismantling of Cement Concrete Pavements as per Technical Specification Clause 202.

Dismantling of cement concrete pavements by mechanical means using pneumatic tools breaking to pieces not exceeding cum 1,010.40
0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials upto a lead of 1000 m,
stacking serviceable and unserviceable materials separately

2.16 Dismantling Guard Rails


Dismantling guard rails by manual means and disposal of dismantled material with all lifts and upto a lead of 1000 m, running m 58.40
stacking serviceable materials and unserviceable materials separately as per Technical Specification Clause 202.

2.17 Dismantling Kerb Stones


Dismantling kerb stones by manual means and disposal of dismantled material with all lifts and upto a lead of 1000 m as running m 11.40
per Technical Specification Clause 202.

2.18 Dismantling Kerb Stone Channels


Dismantling kerb stone channels by manual means and disposal of dismantled material with all lifts and upto a lead of running m 17.50
1000 m as per Technical Specification Clause 202.

2.19 Dismantling Kilometre Stones

Dismantling of kilometre stones including cutting of earth, foundation and disposal of dismantled material with all lifts and
lead upto 1000 m and backfilling of pit as per Technical Specification Clause 202.

(A) 5th km Stone m 287.40


(B) Ordinary km Stones m 180.10
© 200 m Stones m 35.60
Item Description Unit Rate
No. (Rs.)

2.20 Dismantling of Fencing

Dismantling of barbed wire fencing / wire mesh fencing including posts, foundation concrete, backfilling of pit by manual running m 44.70
means including disposal of dismantled material with all lifts and upto a lead of 1000 m, stacking serviceable material and
unserviceable material separately as per Technical Specification Clause 202.

2.21 Dismantling of CI Water Pipe Line

Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead upto 1000 m and stacking of running m 111.20
serviceable material and unserviceable material separately under supervision of concerned department as per Technical
Specification Clause 202.

2.22 Removal of Cement Concrete Pipe of Sewer Gutter


Removal of cement concrete pipe of sewer gutter 1500 mm dia under the supervision of concerned department including running m 188.70
disposal with all lifts and upto a lead of 1000 m and stacking of serviceable and unserviceable material separately but
excluding earth excavation and dismantling of masonry works as per Technical Specification Clause 202.

2.23 Removal of Telephone/Electric Poles and Lines


Removal of telephone/electric poles with wires including excavation and dismantling of foundation concrete and lines each 150.90
under the supervision of concerned department, disposal with all lifts and upto a lead of 1000 m and stacking the
serviceable and unserviceable material separately as per Technical Specification Clause 202.

Chapter 3-EARTHWORK, EROSION CONTROL AND DRAINAGE


3.1 Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means

a Manual means

Scarifying existing granular surface to a depth of 50 mm and disposal of scarified material with a lift upto 3 m and leads sqm 18.50
upto 1000 m as per Technical Specification Clause 301.4.

b Mechanical means
Scarifying existing granular surface to adepth of 50mm and disposal of scarified material sqm 7.10
with a lift upto 3 m and lead upto 1000m as per Technical specification Clause 301.4

3.2 Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical Means


Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3 m sqm 6.50
and lead upto 1000 m as per Technical Specification Clause 301.4.

3.3 Construction of Embankment with Material Obtained from Roadway Cutting

Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain cum 58.00
and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical
Specification Clause 301.5

3.4 Construction of Embankment with Material Obtained from Borrow Pits

Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site,
spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000
m as per Technical Specification Clause 301.5

(I) Private Land cum 230.60


(ii) Govt. Land cum 230.60
3.5 Excavation in Cutting in Soil by manual means with lead upto 50 m
Excavation for roadway in soil using manual means for carrying of cut earth to embankment site with a lift upto 1.5 m and cum 109.20
lead upto 50 m as per Technical Specification Clause 302.3 (Manual should be use where machines can not be deployed
due to site condition)

ii Excavation in Soil with Dozer with lead upto 100 m

Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a cum 54.10
distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-
sections.

iii Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m

Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in cum 59.90
tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and
transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause
302.3
Item Description Unit Rate
No. (Rs.)

3.6 Excavation in Marshy Soil


Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity including cutting and loading in cum 65.50
tippers and disposal with a lift upto 1.5 m and lead upto 1000 m, trimming of bottom and side slopes in accordance with
requirements of lines, grades and cross- sections as per Technical Specification Clause 302.3.6.

3.7 Removal of Unsuitable Soil with Disposal upto 1000 m


Removal of unsuitable soil including excavation, loading and disposal upto 1000 m lead but excluding compaction ground cum 59.90
supporting embankment subgrade replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as
per Technical Specification Clause 302.3.11

Note: This item does not include replacement of unsuitable soil by suitable soil
Replacement,Where required, is to be provided and paid seperately under Clause
303.5.2
3.8 Excavation in ordinary Rock by manual means

I Excavation in ordinary rock using manual means including loading in a truck and carrying of excavated material to cum 169.90
embankment site with a lift upto 1.5 m and lead upto 50 m as per Technical Specification Clause 302.3.5. (Manual means
should be use where machines can not be deployed due to site condition)

ii Excavation in Ordinary Rock with Dozer with lead upto 100 m

Excavation for roadway in ordinary rock by deploying a dozer D-50 including cutting and pushing the cut earth to site of cum 58.90
embankment upto a distance of 100 m (average lead 50 m), trimming bottom and side slopes in accordance with the
requirements of lines, grades and cross-sections with lift upto 1.5 m.

iii Excavation in Ordinary Rock using Hydraulic Excavator and Tippers with disposal upto 1000 m

Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading cum 88.30
in tippers, transporting to embankment site with a lift upto 1.5 m and lead upto 1000 m, trimming bottom and side slopes in
accordance with requirements of lines, grades and cross-sections as per Technical Specification Clause 302.3.5

3.9 Excavation in Hard Rock (requiring blasting) with disposal upto 1000 m
1000M
I Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom and side cum 215.00
slopes in accordance with requirements of lines, grades and cross-sections, loading and disposal of cut rock with a lift upto
1.5 m and leads upto 1000 m as per Technical Specification Clause 302.3.5

ii Excavation in Hard Rock (blasting prohibited)

Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and
disposal with a lift upto 1.5 m and lead upto 200 metres, trimming bottom and side slopes in accordance with requirements
of lines, grades and cross- sections as per Technical Specification Clause 302.3.5

A Manual Means cum 897.90

B Mechanical Means cum 447.00

iii Excavation in Hard Rock (controlled blasting) with disposal upto 1000 m

Excavation for roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming of bottom and side cum 233.30
slopes in accordance with requirements of lines, grades and cross-sections, loading and disposal of cut rock with a lift upto
1.5 m and leads upto 1000 m as per Technical Specification Clause 302.3.5

3.10 Stripping, Storing and Relaying Top Soil from Right-of-Way (R.O.W) cum 171.00

S Striping,storing and preservatio of top soil by keeping it damp in stock piles and keep
wet till it is used by road side at 15 M interval and reapplication on embankment
slopes,cut slopes and other areas in localities where the available embankment mate

3.11 Stripping,Storing and Relaying Top soil from Borrow areas in Agricultural fields.
Stripping of top soil from borrow areas located in agriculture fields, storing at a suitable place, spreading and relaying after cum 114.00
taking the borrow earth to maintain fertility of the agricultural field, finishing it to the required levels to the satisfaction of the
farmer/land owner as per Technical Specification Clause 302.3.2.

3.12 Turfing with Sods


Item Description Unit Rate
No. (Rs.)

Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other locations sqm 19.80
shown on the drawing or as directed by the Engineer including preparation of ground, fetching of sods and watering as per
Technical Specification Clause 309.

3.13 Seeding and Mulching


Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer, mulching material, applying sqm 93.40
bituminous emulsion @ 0.23 litre per sqm and laying and fixing jute netting, including watering for 3 months all as per
Technical Specification Clause 310.

3.14 Construction of Subgrade and Earthen Shoulders


Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto
1000 m as per Technical Specification Clause 303.1.

(I) Private Land cum 286.30


(ii) Govt. land cum 286.00
3.15 Compacting Original Ground
(I) Compacting original ground supporting embankment

Loosening, Levelling and Compacting original ground supporting embankment to facilitate placement of first layer of cum 19.80
embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve
minimum dry density as given in Tables 300.1 and 300.2 for embankment construction as per Technical Specification
Clause 301.4.1.

(ii) Compacting original ground supporting subgrade

Loosening of the ground upto a level of 300 mm below the subgrade level, watered, graded and compacted in layers to cum 30.80
meet requirement of Tables 300.1 and 300.2 for subgrade construction as per Technical Specification Clause 303.5.2.

3.16 Repairs of damages caused by rain/spillage of water

Preparation and surface treatment of formation by removing mud and slurry, watering to the extent needed to maintain the sqm 1.70
desired moisture content, trimming to the required line, grade, profile and rolling with three wheel 80-100 kN static roller,
complete as per Technical Specification Clause 301.5.5.1

3.17 Presplitting Rock Excavation Slopes

Carrying out excavation in hard rock to achive a specified slope of the rock face by controlled use of explosives and sqm 129.60
blasting accessories in properly aligned and spaced drill holes, collection of the excavated rock by a D-50 dozer, loading
in tipper by a front end loader and disposing of the material with a lift upto 1.5 m and lead upto 1000 m as per Technical
Specification Clause 304.3

3.18 Construction of Embankment with Flyash/Pond ash available from Coal or Lignite Burning Thermal Plants as
Waste Material
Construction of embankment with flyash conforming to Table 1 of IRC:SP:58 obtained from coal or lignite burning thermal cum 197.20
power stations as waste material, spread and compacted in layer of 200 mm thickness each at OMC, all as specified in
IRC:SP:58 and as per approved plans with lead upto 1000 m as per Technical Specification Clause 306.

3.19 Surface Drains in Soil

(I) Construction of unlined surface drains of average cross-sectional area 0.40 sqm in soil to specified lines, grades, levels
and dimensions. Excavated material to be used in embankment with a lift upto 3m and lead of 50 m (average lead 25 m)
as per Technical Specification Clause 307.

(A) Manual Means m 58.20


(B) Mechanical Means m 25.70
(II) Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross-sectional area 0.4 sqm in ordinary rock to specified lines, grades,
levels and dimensions as per approved design and Technical Specification Clause 307. Excavated material to be used in
embankment at site.

(A) Manual Means m 87.40

(B) Mechanical Means m 33.00

(III) Surface Drains in Hard Rock

Rate per m may be worked out based on quantity of hard rock as per design.

For rate of hard rock cutting refer releavant item in this chapter.

Note: Where lining of drain is provided,quantity shall be worked out based on approved
design and drawing and priced on rate
Item Description Unit Rate
No. (Rs.)

3.20 Chute Drains

A Providing chute drains across embankment slopes in approches of bridges and on horizontal curves as per drawings.

(a)Earthwork in exavation for foundation of structure as per drawings and technical


specification clause 307 including setting out construction of shoring and bracing
deleterious matter, dressing of sides and bottom and backfilling with approved material(

Rate as per item No. 11.1 of Chapter 11. Cum


(b)Providing and laying plain cement concrete M15 grade Rate as per 12.5 of Chapter cum
12
© Brick masonry in cement morter 1:5. Rate asper item no 12.1 (iii) of Chapter 12 cum 6,888.20

(d)Plastering with cement morter 1:4. Rate as per item no 12.3 of Chapter 12. cum 1,211.70
(e)Providing P.C.C. M 20 coping on the top of chute walls. As per item no 12.13 of cum
Chapter 12.
B Providing chute drains across embankment slopes in approches of bridges and on horizontal curves as per m -
drawings.

(a) Earthwork in exacavation for foundation of structure as per drawing and technical
specifications clause 307 including setting out construction of shoring and bracing
deleterious matter, dressing of sides and backfilling with approved material (By manual
means)
Rate as per item no 11.1 of chapter 11. cum

(b) Providing and laying plain cement concrete M 15 Grade

Rate as item No.12.5 of Chapter 12. cum


© Coursed ruble stone masonary (2 nd sort) in cement morter 1:4

Rate as item No.12.4 II of Chapter 12. cum

(d) Plastering with cement morter 1:4

Rate as per item No. 12.3 of Chapter 12. cum

(e) Providing P.C.C. M 20 Coping on the top of chute walls


Rate as per item No. 12.13 of chapter 12 cum

Chapter 4 - GRANULAR SUB-BASES, BASES (NON-BITUMINOUS) AND SHOULDERS

4.1 Granular Sub-base with Well Graded Material (Table 400.1)


(Only for PMGSY work)
(A) By Mix in Place Method

Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to
achieve the desired density, complete as per Technical Specification Clause 401.

(I) For Grading I Material cum 1,544.80

(ii) For Grading II Material cum 1,466.00

(iii) For Grading III Material cum 1,373.60

4.2 Gravel/Soil-Aggregate Base (Table 400.2) Grading A


(Only for PMGSY work)
I) Construction of gravel/soil-aggregate base by providing well graded material, spreading in uniform layers with motor cum 1,608.60
grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-
100 kN static roller to achieve the desired density, complete as per Technical Specifications Clause 402

ii) Gravel/Soil-Aggregate Base (Table 400.2) Grading B


Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on cum 1,562.80
prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100 kN
static roller capacity to achieve the desired density, complete as per Technical Specification Clause 402

iii) Gravel/Soil-Aggregate Base (Table 400.2) Grading C cum 1,509.70

Construction of granular sub-base by providing well graded material,

spreading in uniform
layers with motor grader on prepared surface,mixing by mix

in place method with rotavator at OMC, and compacting with three wheel 80-100
kn static roller capacity to achieve
the desired density,complete as per Technical
specification Clause 402.
Item Description Unit Rate
No. (Rs.)

iv) cum
Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 80 mm (Table 2.3 of IRC SP 77-2008 1168.00

Construction of Gravel/soil aggregate sub-base/Base by providing well graded material


of nominal size grading 80 mm as per Table 2.3 of IRC SP 77-2008, spreading in
uniform layers with tractor mount appropriate grading arrangement on prepared
surface,mixing by mix in place method at OMC with tractor mount appropriate rotavator
attachment and compaction with three wheel 80-100 Kn capacity to achieve complete as
per specification contained in para 2.2,3.6,3.7 of IRC SP 77-2008.
v) cum 1117.00
Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 40 mm (Table 2.3 of IRC SP 77-2008

Construction of Gravel/soil aggregate sub-base/Base by providing well graded material


of nominal size grading 40 mm as per Table 2.3 of IRC SP 77-2008, spreading in
uniform layers with tractor mount appropriate grading arrangement on prepared
surface,mixing by mix in place method at OMC with tractor mount approprite rotavator
attachment and compaction with three wheel 80-100 kn static roller capacity to achieve
the desired density complete as per specification contained in para 2.2,3.6 and 3.7 of
IRC SP 77-2008
vi) cum 1073.00
Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 20 mm (Table 2.3 of IRC SP 77-2008

Construction of Gravel/soil aggregate sub-base/Base by providing well graded material


of nominal size grading 40 mm as per Table 2.3 of IRC SP 77-2008, spreading in
uniform layers with tractor mount appropriate grading arrangement on prepared
surface,mixing by mix in place method at OMC with tractor mount approprite rotavator
attachment and compaction with three wheel 80-100 kn static roller capacity to achieve
the desired density complete as per specification contained in para 2.2,3.6 and 3.7 of
IRC SP 77-2008
4.3 Gravel/Soil-Aggregregate surface course (table 400.3)
(Only for PMGSY work)
I Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on cum 1,278.40
prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100 kN
static roller capacity to achieve the desired density, complete as per Technical Specification Clause 402

ii cum 981.00
Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 10 mm (Table 2.3 of IRC SP 77-2008

C0nstruction of Gravel/Soil aggregrete Base/Surface by providing well graded material


of nominal maximum size grading 10 mm as per Table 2.3 of IRC SP 77-2008,spreading
in uniform layers with tractor mount appropriate grading arrangement on prepared
surface,mixing by mix in place method at OMC with tractor mount appropriate rotavator
attachment and compaction with three wheel 80-100kn static roller capacity to achieve
the desired density complete as per specifications contained in para 2.2,3.6 and 3.7 of
IRC SP 77-2008.
iii) cum 937.00
Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 5 mm (Table 2.3 of IRC SP 77-2008

Construction of Gravel/Soil aggregrete Base/Surface by providing well graded material


of nominal maximum size grading 5 mm as per Table 2.3 of IRC SP 77-2008, spreading
in uniform layers with tractor mount appropriate grading arrangement opn prepared
surface,mixing by mix in place method at OMc with tractor mount appropriate rotavator
attachment compacted with three wheel 80-100kn static roller capacity to achieve the
desired density complete asper para 2.2,3.6 and 3.7 of IRC SP 77-2008.
4.4 Lime Stabilisation for Improving Subgrade

Laying and spreading available soil in the subgrade on a prepared surface, pulverising, mixing the spread soil in place with
rotavator with 2 per cent slaked lime having minimum 70 per cent of contents of CaO, grading with motor grader and
compacting with the smooth wheel road roller at OMC to the desired density to form a layer of improved Sub-grade as per
Technical Specification Cluase 403.

(A) By Manual Means cum 356.40

(B) By Mechanical Means cum 321.40

4.5 Lime Treated Soil for Sub-Base

Providing, laying and spreading soil on a prepared sub-grade, pulverising, mixing the spread soil in place with rotavator cum 584.50
with 4 per cent slaked lime with minimum content of 70 per cent of CaO, grading with motor grader and compacting with
the road roller at OMC to achieve atleast 98 per cent of the max dry density to form a layer of sub-base as per Technical
Specification Clause 403.

4.6 Cement Treated Soil Sub-Base/Base


Item Description Unit Rate
No. (Rs.)

Providing, laying and spreading soil on a prepared sub-grade, pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to form a layer of sub-base/base as per Technical Specification
Clause 404.

For 4 per cent quantity of cement by weight of soil cum 628.40

4.7 Water Bound Macadam Sub-base/base


(Only for PMGSY work)
1) WBM Grading 1
Using stone screening Type-A 13.2 mm for Gr.I
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper
grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate,
watering and compacting to the required density Grading 1 as per Technical Specification Clause 404.

(A) By Manual Means cum 2,580.30

(B) By Mechanical Means cum 2,625.50

2) WBM Grading 2
Using stone screening Type-B 11.2 mm for Gr.II
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper
grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate,
watering and compacting to the required density grading 2 as per Technical Specification Clause 405.

(A) By Manual Means cum 2,732.70

(B) By Mechanical Means cum 2,455.60

3) WBM Grading 3
Using stone screening Type-B 11.2 mm for Gr.III
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper
grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and
compacting to the required density Grading 3 as per Technical Specification Clause 405.

(A) By Manual Means cum 2,764.60

(B) By Mechanical Means cum 2,581.10

4.8 Water Bound Macadam with Crushable Screenings


(Only for PMGSY work)
1) WBM Grading 1
Using crushable screening such as moorum gravel for Gr.I
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper
grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and
compacting to the required density Grading 1 as per Technical Specification Clause 405.

A) By Manual Means cum 2,427.10


B) By Mechanical Means cum 2,155.40
2) WBM Grading 2
Using crushable screening such as moorum gravel for Gr.II
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper
grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and
compacting to the required density Grading 2 as per Technical Specification Clause 405.

(A) By Manual Means cum 2,414.20

(B) By Mechanical Means cum 2,233.80

3) WBM Grading 3

Using crushable screening such as moorum gravel for Gr.III


Item Description Unit Rate
No. (Rs.)

Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper
grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and
compacting to the required density Grading 3 as per Technical Specification Clause 405.

(A) By Manual Means cum 2,523.00

(B) By Mechanical Means cum 2,301.70

4.9 Wet Mix Macadam

Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including
premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site,
laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of
80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per
Tables 400.11 & 400.12 and Technical Specification Clause 406.

By Mechanical Means with 1 km lead cum 2,113.70

4.10 Construction of Shoulders as per Technical Specification Clause 407.

A Earthen Shoulders

The rate as applicable for sub-grade construction may be adopted.

B Hard Shoulders

Rate as applicable for sub-base and/or base may be adopted as per approved design.

C Paved Shoulders

The rates may be adopted as applicable for different layers of pavement depending upon approved design of paved
shoulders.

4.11 Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal Construction of
granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by
mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density
complete as per Clause 401.4 as per Technical Specification Clause 408.

I Using naturally occuring gravel cum 630.20


ii Using Gravel mix soil using cum 477.50
4.12 Construction of Water Bound Macadam using locally available material (Table 400.13)

Providing, laying spreading and compacting local material in block or large discrete particles, such as kankar, Laterite, cum 1,117.00
Dhandla etc. as per Table 400.13 to water bound macadam specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming
requisite type of screening /binding materials to fill-up the interstices of laid material watering and compacting to the
required density as per Clause 405.3 and Technical Specification Cluase 408.

4.13 Lime-Flyash Stablised Soil Sub-base


Construction of sub-base using lime-flyash admixture with granular soil, free from organic matter/deleterious material or
clayey silts and low plasticity clays having PI between 5 and 20 and liquid limit less than 25 and commercial dry lime,
slaked at site or pre-slaked with CaO content not less than 50 per cent, flyash to conform to gradation as per Clause 4.3 of
IRC:SP:20, lime+flyash content ranging between 10 to 30 per cent, the minimum un-confined compressive strength and
CBR value after 28-days curing and 4-days soaking to be 0.75 MPa and 25 per cent respectively, all as specified in IRC:88
including a lead upto 1000 m as per Technical Specification Cluase 409.

(A) For earth taken from Private source cum 522.00

(B)For earth taken from Govt.Land cum 522.00

4.14 Construction of Sub-base/Course Using Crushed Slag as per Table 400.19

Construction of Sub-base by providing crushed slag spreading in uniform layer with motor grader on prepared surface cum 910.00
mixing by mix-in-place method with Rotavator @ OMC, and compacting with three wheel 80-100 kN static roller to achieve
the desired density complete as per Technical Specifications Cluase 402.4 and 410.3.2

4.15 Water Bound Macadam using crushed slag


Item Description Unit Rate
No. (Rs.)

Providing, laying, spreading and compacting crushed slag to water Bound Macadam specification including spreading in cum 1,212.60
uniform thickness, hand packing rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber,
applying and brooming requisite type of screening/binding materials to fill up the interstees of crushed slag watering and
compacting to the required density as per Clause 405.3 and Technical Specification Cluase 410.3.2.

4.16 Cement Bound Granular Material sub-base/base


Providing laying and spreading granulated blast furnace slag on a prepared sub-grade pulverising adding the designed cum 665.50
quantitity of cement to the spread granulated blast furnace slag mixing in place with rotavator grading with the mortar
grader and compacting with smooth wheel roller 80-100 kN at OMC to achieve the desired unconfined compressive
strength and to form a layer of sub-base/base as per Technical Specification Clauses 404.3 and 410.4.2.

4.17 Crusher Run Macadam Base


Providing crushed run stone aggregate greading conforming to table 400.20 depositing on a prepared surface by hauling
vehicles, spreading and mixing with a motor grader, watering and compacting with a three wheel 80-100 kN static roller
as per Technical Specification Clause 411 to form a layer of sub-base/base

A) By mix-in-place method

I With 53 mm maximum size of aggregates cum 2,189.10

ii With 37.5 mm maximum size of aggregates cum 1,980.20

(B) By mixing plant method

I With 53 mm maximum size of aggregates cum 2,413.90

ii With 37.5 mm maximum size of aggregates cum 2,054.70

4.18 Brick Soling


Laying brick soling layer on prepared sub-grade with brick on end edging according to lines, graded and cross-section sqm 631.70
shown on the drawing filling joints with sand and earth, spreading 25 mm thick layer of earth over brick soling, watering
and rolliing the same with three wheel road roller 80-100 kN as per Technical Specification Clause 412

4.19 Stone Set Pavement


Providing and laying stone set pavement on prepared surface with sub-base 100 mm thick compacted Granular Sub-base sqm 786.70
as per Clause 401.4 and base 75 mm thick compacted water bound macadam grading 2 as per Clause 405.3. The 150
mm thick hammer desired stones are laid in the herring one or stretched bond pattern. The stones are compacted into the
bedding sand of 40 mm over the WBM base bounded by edge stone using suitable compacting device. The gaps are filled
with fine sand stone dust as per Technical Specification Clause 413.4

Chapter 5 - BASES AND SURFACE COURSES (BITUMINOUS)

5.1 Prime Coat


I) Low porosity
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning sqm 27.90
of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification
Clause 502

ii) Medium porosity


Providing and applying primer coat with Bitumen emulsion (SS-1) on prepared surface of granular base including cleaning sqm 34.20
of road surface and spraying primer at the rate of 0.90- 1.2 kg/sqm using mechanical means as per Technical Specification
Clause 502.

iii) High porosity

Providing and applying primer coat with Bitumen emulsion (SS-1) on prepared surface of granular base including cleaning sqm 43.80
of road surface and spraying primer at the rate of 1.2-1.5 kg/sqm using mechanical means as per Technical Specification
Clause 502.

5.2 Tack Coat


I) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.25 kg per sqm 8.60
sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.

ii) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm 10.20
sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification
Clause 503.

iii) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg sqm 10.20
per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical
Specification Clause 503.
Item Description Unit Rate
No. (Rs.)

iv) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion pressure distributor at the rate of 0.30 to sqm 11.80
0.35 kg per sqm on the prepared non-bituminous surfaces (cement concrete pavement) cleaned with Hydraulic broom as
per Technical Specification Clause 503.

5.3 Bituminous Macadam

(i) Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 cum 7,257.90
premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with
paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical
Specification Clause 504.

(ii) Providing and laying Cold Mix bituminous macadam with Drum mix plant using cum 7,213.00
crushed aggregates of grading as per Table 500.4 premixed with Cold mix binder,
transported to site upto a lead of 1000 m laid over a previously prepared surface with
paver finisher to the required grade, level and alignment and rolled to achieve the
desired compaction as per Technical Specification (IRC:SP:100-2014)

5.4 Built-Up Spray Grout


Providing, laying and rolling of built-up spray grout layer over prepared base consisting of a two layer composite
construction of crushed coarse aggregates using motor grader for aggregates. Key stone chips spreader may be used with
application of bituminous binder after each layer, and with key aggregates placed on top of the second layer to serve as a
base, conforming to the line, grades and cross-section specified, the compacted layer thickness being 75 mm as per
Technical Specification Clause 505.

A By Manual Means

I Bitumen (S-90) sqm 359.50

ii Bitumen (S-65) sqm 362.70

B By Mechanical Means(S90) sqm 303.10

5.5 Modified Penetration Macadam


Construction of penetration macadam over prepared base by providing a layer of compacted crushed coarse aggregate
using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a three wheel 80-
100 kN static roller to achieve the desired degree of compaction as per Technical Specification Clause 506.

A 50 mm thick
I) Bitumen (S-90) sqm 220.80

B 75 mm thick

I) Bitumen (S-90) sqm 284.30

ii) Bitumen (S-65) sqm 286.50

5.6 Surface Dressing using Bituminous (Penetrations grade / modified bitumen) Binder

Providing and laying surface dressing as wearing course consisting of a layer of bituminous binder laid on the prepared
surface, followed by a cover of crushed stone aggregates of specified size and rolling with three wheel 80-100 kN static
roller including cleaning the road surface as per Technical Specification Clause 507.

A By Manual Means

Case – I: Nominal chipping size 13.2 mm

I) (I) Bitumen (S-90) sqm 89.90

ii) (II) Bitumen (S-65) sqm 91.00

iii) (III) Polymer Modified Bitumen sqm 83.20

iv) (IV) Crumb Rubber Modified Bitumen sqm 87.20

Case – II: Nominal chipping size 9.5 mm

I) (I) Bitumen (S-90) sqm 78.30

ii) (II) Bitumen (S-65) sqm 79.30

iii) (III) Polymer Modified Bitumen sqm 72.00


Item Description Unit Rate
No. (Rs.)

iv) (IV) Crumb Rubber Modified Bitumen sqm 75.90

B By Mechanical Means

Case – I: Nominal chipping size 13.2 mm

I) (I) Bitumen (S-90) sqm 72.40

ii) (II) Bitumen (S-65) sqm 69.70

iii) (III) Polymer Modified Bitumen sqm 61.90

iv) (IV) Crumb Rubber Modified Bitumen sqm 65.90

Case – II: Nominal chipping size 9.5 mm

I) (I) Bitumen (S-90) sqm 60.50

ii) (II) Bitumen (S-65) sqm 61.50

iii) (III) Polymer Modified Bitumen sqm 54.50

iv) (IV) Crumb Rubber Modified Bitumen sqm 58.10


5.7 Surface Dressing using Bitumen Emulsion

Providing and laying surface dressing as wearing course consisting of a layer of bitumen emulsion laid on the prepared
surface, followed by a cover of crushed stone chippings of specified size and rolling with 80-100 kN roller including
cleaning the road surface as per Technical Specification Clause 507.

A By Manual Means

Case – I: Nominal aggregate size 13.2 mm sqm 88.30

Case – II: Nominal chipping size 9.5 mm sqm 78.80

B By Mechanical Means

Case – I: Nominal chipping size 13.2 mm sqm 72.60

Case – II: Nominal chipping size 9.5 mm sqm 65.60

5.8 Pre-coating Chips


Pre-coating of chips with 1 per cent of paving bitumen by weight of chips in a suitable mixer duly heated to 160 degree C
as per Technical Specification Clause 507.2.5

I) Bitumen (S-90) cum 1,700.80

ii) Bitumen (S-65) cum 1,718.00

5.9 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade/modified bitumen) Binder

Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm
aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing
course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN
static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C
as per Technical Specification Clause 508.

Case - I By Manual Means

I) Bitumen (S-90) sqm 165.80

ii) Bitumen (S-65) sqm 164.70

iii) Polymer Modified Bitumen sqm 153.30

iv) Crumb Rubber Modified Bitumen sqm 158.60

Case - II By Mechanical Means

I) Bitumen (S-90) sqm 132.80

ii) Bitumen (S-65) sqm 134.40

iii) Polymer Modified Bitumen sqm 123.10


Item Description Unit Rate
No. (Rs.)

iv) Crumb Rubber Modified Bitumen sqm 128.90

5.10 20mm thick Open-Graded Premix Carpet using Bitumen Emulsion as per Technical Specification clause 508.2 sqm 125.00

Providing, laying and rolling of open-graded premix carpet of 20 mm thickness


composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or
emulsion to required line, grade and level to serve as wearing course on a previously
prepared base, including mixing in a suitable plant, laying and rolling with a three wheel
80-100 kN static roller capacity, finished to required level and grades to be followed by
seal coat of either Type A or Type B or Type C as per Technical Specification Clause
508.

(ii) Using Cold mix Binder (Tailor made as per IRC:SP:100-2014) sqm 161.00

5.11 Mix Seal Surfacing

Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.9
mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration grade bitumen to required line, grade and level
to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a
three wheel 8-10 kN static roller and finishing to required level and grades as per Technical Specification Clause 509

By Manual Means
Type A Type A
I) (I) Bitumen (S-90) sqm 218.30
ii) (II) Bitumen (S-65) sqm 220.70
iii) (III) Polymer Modified Bitumen sqm 203.60
iv) (IV) Crumb Rubber Modified Bitumen sqm 212.40
(v) Using Cold mix Binder (Tailor made as per IRC:SP:100-2014) sqm 209.00

Type B Type B
I) (I) Bitumen (S-90) sqm 205.20
ii) (II) Bitumen (S-65) sqm 207.30
iii) (III) Polymer Modified Bitumen sqm 192.50
iv) (IV) Crumb Rubber Modified Bitumen sqm 200.10
(v) Using Cold mix Binder (Tailor made as per IRC:SP:100-2014) sqm 204.00

By Mechanical Means

Type A Type A

I) (I) Bitumen (S-90) sqm 165.50

ii) (II) Bitumen (S-65) sqm 167.90

iii) (III) Polymer Modified Bitumen sqm 150.80

iv) (IV) Crumb Rubber Modified Bitumen sqm 159.60

Type B Type B

I) (I) Bitumen (S-90) sqm 152.50

ii) (II) Bitumen (S-65) sqm 154.50

iii) (III) Polymer Modified Bitumen sqm 139.70

iv) (IV) Crumb Rubber Modified Bitumen sqm 147.30

5.12 Seal Coat

Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall
using Type A, Type B and Type C as per Technical Specification Clause 510

A By Manual Means

Case - I : Type A

I) (I) Bitumen (S-90) sqm 68.00


Item Description Unit Rate
No. (Rs.)

ii) (II) Bitumen (S-65) sqm 69.00

iii) (III) Polymer Modified Bitumen sqm 61.40

iv) (IV) Crumb Rubber Modified Bitumen sqm 65.30

(V)

Case - II : Type B

I) (I) Bitumen (S-90) sqm 50.10

ii) (II) Bitumen (S-65) sqm 50.30

iii) (III) Polymer Modified Bitumen sqm 45.00

iv) (IV) Crumb Rubber Modified Bitumen sqm 52.80

(V)

Case - III : Type C

I) (I) Bitumen (S-90) sqm 60.60

ii) (II) Bitumen (S-65) sqm 61.30

iii0 (III) Polymer Modified Bitumen sqm 55.90

iv) (IV) Crumb Rubber Modified Bitumen sqm 58.80

B. By Mechanical Means

Case - I : Type A

I) (I) Bitumen (S-90) sqm 64.80

ii) (II) Bitumen (S-65) sqm 65.80

iii) (III) Polymer Modified Bitumen sqm 58.20

iv) (IV) Crumb Rubber Modified Bitumen sqm 62.10

Case - II : Type B

I) (I) Bitumen (S-90) sqm 42.30

ii) (II) Bitumen (S-65) sqm 43.00

iii) (III) Polymer Modified Bitumen sqm 37.70

iv) (IV) Crumb Rubber Modified Bitumen sqm 42.90

Case - III : Type C

I) (I) Bitumen (S-90) sqm 53.40

ii) (II) Bitumen (S-65) sqm 54.10

iii) (III) Polymer Modified Bitumen sqm 49.00

iv) (IV) Crumb Rubber Modified Bitumen sqm 51.60

Competitive market rates to be ascertained. Alternatively, rates for stone crushing given in Chapter 1 may be adopted, if
found economical. In case for supply of aggregates at site are not available, nearest crusher site may be ascertained.
Loading and unloading charges and cost of carriage may be added to these rates to arrive at the cost at site.

Chapter 6 - CEMENT CONCRETE PAVEMENT


6.1 Granual Sub-base

Rate as per item No.4.1 of Chapter 4

6.2 Lime Treated Soil

Rate as per item No.4.5 of Chapter 4


Item Description Unit Rate
No. (Rs.)

6.3 Water Bound Macadam (WBM) - Sub-base


(A) By Manual Means
As per item No.4.7 of Chapter 4
(B) By Mechnical Means
As per item No.4.7 of Chapter 4
6.4 Cement concrete pavement

Construction of un reinforced, dowel jointed at expansion and construction joint cum 6,150.20
only,plain cement concrete pavement, thickness as per design,over a prepared sub
base,with 43 grade cement or any other type as per clause 1501.2.2 M30 grade ,coarse
and fine aggregrette conforming to is:383,maximum size of coarse aggregate not
exceeding 25 mm,mixed in a concrete mixer of not less than 0.2 cum capacity and
appropriate weigh batcher using approved mix design, laid in approved fixed side
formwork (steel channel,laying and fixing of 125 micron thick polythene
film,wedges,steel plates including levelling the formwork as per drawing) spreading the
concrete with shovels,rakes,compacted using needle,screed and plate vibrator and
finished in continuous operation including provision of contraction and
expansion,construction joints,applying debonding strips,primer,sealant,dowelbars,near
approaches to bridge/culverts and construction joints,admixture as approved,curingof
concrete slabs for 14 days.

6.5 Roller Compacted Concrete Pavement

Construction of Roller Compacted Concrete Pavement (RCCP) with coarse and fine aggregates conforming to IS:383, the cum 5,453.80
size of coarse aggregate not exceeding 25 mm with minimum aggregate cement ratio of 5:1 mm and with minimum cemnt
content of 310 kg per cum, aggregate gradation to be as per Table 602.2 after blending, mixing in concrete mixer at
optimum moisture content, transporting to site, laying with wheel barrows or steel pans or with mechanical paver,
compacting with 80-100 kN smooth wheel, tandem vibratory roller, to achieve, the designed flexural strength, finishing and
curing as per drawings and Technical Specification Clause 1502

Note: Carraige of c.c block to site of is payable seperately as per chapter of carriage of
materials from manufacturing site to the site of work

6.6 Rectangular Concrete Block Pavement

Manufacturing, laying of cement concrete blocks of size 0.450 m x 0.300 m x 0.15 m of Cement Concrete (C.C.) M30 sqm 1,987.90
garde and spreading 25 mm thick sand under neath and filling joints with sand on existing W.B.M. base as per Technical
Specification Clause 1503.

6.7 Inter locking concrete Block pavement

(A) Interlocking pavement block

(i) ding Providing and laying interlocking concrete block pavement (M40) having thickness
80mm as per technical specification clause 1504 complete including carriage.

a) Including Edge block/ Edge restraints sqm 918.70

b) Excluding Edge block/ Edge restraints sqm 723.60

(ii) ding Providing and laying interlocking concrete block pavement (M40) having thickness
60mm as per technical specification clause 1504 complete including carriage.

a) ding Including Edge block/ Edge restraints sqm 743.50

b) Excluding Edge block/ Edge restraints sqm 548.40

(B) Interlocking Edge block/ Edge restraints

(i) Providing and laying Concrete Edge block/ Edge restraints (M40 Grade) of size 300mm no 135.00
x 300mm x 150mm including carriage complete as per Technical specification clause
1504.

Note: i. The rates for sub-grade, sub-base course to be measured and paid separately
(as per Chapter 3 & 4)

Chapter 7 - CAUSEWAY AND SUBMERSIBLE BRIDGES

7.1 Construction of Cut-off Walls/Head Walls

I Earthwork in excavation for structures as per drawing and technical specification Clause 305.

Rate as per item No.11.1 of Chapter 11 cum


Item Description Unit Rate
No. (Rs.)

ii Plain cement concrete M15 grade


Rate as per item No.11.4 (ii) of Chapter 11 cum
iii) Brick masonry in cement mortar 1:4
Rate as per item No.11.5 (ii) of Chapter 11 cum
iv) Stone masonry in cement mortar 1:4
Rate as per item No.11.6 (ii) of Chapter 11 cum
v Providing P.C.C M20 architectural coping on top of wall
Rate as per item No.12.13 of Chapter 12 m
7.2 Preparation of Subgrade
Rate as per item No.3.15 of Chapter 3 cum
7.3 Granular Sub-base
Rate as per item No.4.1 of Chapter 4 cum
7.4 W.B.M. Base Course
Rate as per item No.4.7 of Chapter 4 cum
7.5 Cement Concrete Slab
Rate as per item No.6.4 of Chapter 6 cum 6,150.20
7.6 Providing and Laying Apron with Stone Boulders as per Drawings & Technical Specification Clause 1301

Rate as per item No.14.1 of Chapter 14 cum

ii Providing and Laying of Boulder Apron Laid in Wire Crates as per Drawing and Technnical Specification Clause 1301

Rate as per item No.14.2 of Chapter 14 cum


iii) Providing and Laying of Apron with Cement Concrete Blocks as per Drawing and Technical Specification Clause 1301

Rate as per item No.14.3 of Chapter 14 cum


7.7 Guide Posts

Construction of R.C.C. guide posts of 250 mm dia, M25 grade as per drawing and technical specification Clause 1401.6

Rate as per item No.8.8 of Chapter 8 cum

7.8 Bedding for Causeway

I Type A (concrete cradle) Bedding Clause 1402.5

As per item No.9.2 of Chapter 9 cum

ii Type B (first class) Bedding Clause 1402.5

As per item No.9.2 of Chapter 9 cum

7.9 Laying Reinforced Cement Concrete Pipe NP3 as per drawing and technical specification Clause 1402.6

As per item No.9.3 of Chapter 9 m

7.10 Laying Reinforced Cement Concrete Pipe NP4 as per technical specification Clause 1402.6

As per item No.9.4 of Chapter 9 m

Chapter 8 - HILL ROADS

8.1 Site Clearance


8.2 Setting Out
1) Construction of reference pillars as per Fig. 1600.1 (b) as per drawing and Technical Specification Clause 1602.1 per Km 5,879.20

2) Construction of back piller as per Fig. 1600.1( c) as per drawing and Technical Specification Clause 1602.3 per Km 13,985.80

3) Construction of Job pillers as per Fig. 1600.1 (d) and Technical Specification Clause 1602.4 each 550.50

8.3 Earthwork in Hill Road


I) Excavation in Hilly Areas in Soil by manual means.
A) Excavation in soil in Hilly Area by manual means including cutting and trimming of side slopes and disposing of excavated cum 145.60
earth with a lift upto 1.5 m and a lead upto 20 m as per drawing and Technical Specification Clause 1603.1 (Manual means
should be use where machines can not be deployed due to site condition)

B) Extra for Every Additional Lift of 1.5 m or Part thereof cum 15.10
Item Description Unit Rate
No. (Rs.)

ii) Excavation in Hilly Areas in Soil by mechanical means


A) Excavation in soil in Hilly Area by mechanical means including cutting and trimming of side slopes and disposing of cum 94.80
excavated earth with a lift upto 1.5 m and a lead upto 20 m as per Technical Specification Clause 1603.1

B) Extra for Every Additional Lift of 1.5 m or Part thereof cum 15.10
iii) Excavation in Hilly Area in Ordinary Rock by manual means

A) Excavation in ordinary rock using manual means including loading in a truck and carrying of excavated material to cum 320.30
embankment site with a lift upto 1.5 m and lead upto 20 m as per Clause 1603.2. (Manual means should be use where
machines can not be deployed due to site condition)

B) Extra for Every Additional Lift of 1.5 m or Part thereof cum 23.70

iv) Excavation in Hilly Areas in Ordinary Rock by mechanical means not requiring blasting

A) Excavation in hilly area in ordinary rock not requiring blasting by mechanical means including cutting and trimming of cum 146.80
slopes and disposal of cut material with a lift upto 1.5 m and lead upto 20 m as per Clause 1603.2.

v) Excavation in Hilly Areas in Hard Rock requiring blasting


A) Excavation in hilly areas in hard rock requiring blasting, by mechanical means, lift upto 1.5 m and disposal of excavated cum 323.20
rock upto a lead of 20 m as per Clause 1603.2.

B) Extra for Every Additional Lift of 1.5 m or Part thereof cum 29.70

vi) Excavation in Hard Rock (blasting prohibited)


Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and
disposal with a lift upto 1.5 m and lead upto 200 metres, trimming bottom and side slopes in accordance with requirements
of lines, grades and cross- sections as per Technical Specification Clause 302.3.5

a) Manual Means cum 830.00


b) Mechanical Means cum 496.20
8.4 Retaining Walls / Breast Walls
Construction of retaining walls/breast walls in cement mortar 1:5 as per drawing and technical specifications Clause 1604

I) Earthwork in excavation for structures


Rate as per item No.11.1 of Chapter 11 cum
ii) Plain cement concrete M 10 grade
Rate as per item No.11.4 of Chapter 11 cum
iii) Stone masonry in cement mortar 1:5
Rate as per item No. 12.4 (III) (iii) of Chapter 12 cum
iv) Pointing with cement mortar 1:3
Rate as per item No.12.2 of Chapter 12 sqm
v) Providing P.C.C. M 20 architectural coping on top of retaining wall/breast wall
Rate as per item No.12.13 of Chapter 12 m
vi) Filter material behind retaining wall / breast wall as per Specification 1204.3.8 in a width of 600 m

Rate as per item No. 12.11 of Chapter 12 cum

vii) Back filling behind retaining wall/breast wall


Rate as per item No. 12.10 of Chapter 12 cum

8.5 Construction of Hill side Drain

Construction of Hill side drain in accordance with the requrement of


of specification true to lines and grades. Dimensions and other particulars as per
drawing and technical specification. Clause 1606.1

I) Earthwork in excavation for structures as per drawing and technical specification.

Rate as per item no 11.1 of chapter 11 cum

ii) Plain cement concrete M10 grade

Rate as per item no 11.4of chapter 11 cum

iii) Stone masonary in cement morter 1:5

Rate as per item no 12.4(iii) (iii) of chapter 12 cum


Item Description Unit Rate
No. (Rs.)

(iv) Plain cement concrete M15 grade

Rate as per item 11.4 of chapter 11 cum

(v) Cement plaster 15 mm thick 1:4 on stone masonary

Rate as per item no 12.3 of chapter 12 cum

(vi) Providing P.C.C. M 20 Architectural coping on top of wall


Rate as per item no.12.13 of chapter 12 cum
Rate per m length (I+II+III+IV+V+VI) m
Note:
1.Quantities of material/work shall be as per Design and Drawing.

2.Earth work in excavation may be taken as per site conditions.


It may coprise of a number of sub-items depending upon the type
typy of soil/rock.

8.6 Construction of catch water/Intercepting drain.

Construction of catch water/Intercepting drain in Random ruble masonary in 1:5 cement


morter true to the specified lines grades lavel and dimensions as per the requirements of
the specification Clause 1606.2

Unit=1M

I) Earthwork in excavation for structure as per drawing and technical specificatuion

Rate as per item no 11.2 of chapter 11 cum

ii) Plain cement concrete M10 grade


Rate as per 11.4 of chapter 11. cum
iii) Stone masonary in cement morter 1:5
Rateas per item no 12.4 (III) (iii) of chapter 12 cum
iv) Plain cement cioncrete M 15 grade
Rate as per 11.4 of chapter 11. cum
v) Cement plaster 15 mm thick 1:4 on stone masonary
Rate as per 12.3 of chapter 12. sqm
vi) Providing P.C.C. M20 architectural coping on top of wall
Rate as per item No. 12.3 of chapter 12 cum

Note: 1. Quantities of material/work shall beas per design and drawings.


2. Earth work in excavation may be taken as per site condition.It may comprise of a
number of sub-items depending upon the type of soil/rock encountered.

8.7 Construction of Scupper

Construction of scupper with dry stone masonry as per drawing and technical specifications as per Clause 1606.5. Running m 30,257.00

8.8 Construction of RCC guide posts of 250 mm dia M15 grade cast-in-situ with 20 mm nominal size aggregate, true to line
and grade, tolerance of vertical RCC posts not to exceed 1 in 500 as per drawing and Technical Specification Clause
1608.2

I) Earth work in excavation for structures

Rates as per item No. 11.1 of Chapter 11 cum

ii) RCC M15 grade


Rate as per item No. 11.4 of Chapter 11 cum
iii) HYSD steel bars

Rate as per item No. 12.6 of Chapter 12 t


iv) Painting two coats including prime coat on new concrete surface

Rate as per item No.10.5 of Chapter 10 sqm


8.9 Providing edge stones on valley side of formation as per drawing and Technical Specification Clause 1608.2.6 m 263.30

8.10 Turfing with Sods

Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other locations sqm 20.90
shown on the drawing or as directed by the Engineer including preparation of ground, stacking the sods and watering as
per Clause 309
8.11 Seeding and Mulching
Item Description Unit Rate
No. (Rs.)

Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer, multching material, applying sqm 271.10
bituminous emulsion at the rate of 0.23 l per sqm and laying and fixing jute netting, including watering for 3 months all as
per Clause 310.

Chapter 9 - PIPE CULVERTS

9.1 Excavation for Structures

Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and technical specification Clause
1104 includding setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing
of sides and bottom and backfilling with approved material.

Rate as per item No.11.1 of Chapter 11 cum 102.00

9.2 Bedding for Pipe Bedding of pipe


(A) Type A (Concrete Cradle) Bedding

i) Laying concrete cradle bedding with M15 Grade Cement Concrete as per Clause 1105 (i)

Rate as per Item No.11.4 (II)(i) of Chapter 11 cum 5,085.60

(B) Type B (First Class) Bedding

Laying (First Class) bedding on well compacted sand, moorum as per Clause 1105 (ii)

i) Laying (First Class) bedding on well compacted sand, moorum as per Clause 1105 (ii) cum 1,129.00

ii) Laying (First Class) bedding on well compacted approved granular material as per Clause 1105 (ii) cum 1,369.05

9.3 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row

Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single
row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets Clause 1106.

1200 mm dia m 9,864.70


1000 mm dia m 6,880.50

600 mm dia m 2,886.80


9.4 Providing and Laying Reinforced Cement Concrete Pipe NP4 as per design in Single Row

Providing and laying reinforced cement concrete pipe NP4 for culverts on first class bedding of granular material in single
row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets Clause 1106.

1200 mm dia m 11,889.70


9.5 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per Design in Double Row

Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in
double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets as per Clause 1106.

A) 1200 mm dia m 19,791.60

B) 1000 mm dia m 14,560.10

9.6 Providing and Laying Reinforced Cement Concrete Pipe NP4 as per Design in Double Row

Providing and laying reinforced cement concrete pipe NP4 for culverts on first class bedding of granular material in
double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets as per Clause 1106.

A) 1200 mm dia m 23,841.60

B) 1000 mm dia m 19,597.90

9.7 Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course below open foundation of Head walls as per
drawings & Technical Specification Clause 1109
Item Description Unit Rate
No. (Rs.)

Rate as per item No.11.4 of Chapter 11 cum

9.8 Brick Masonry Work in cement mortar in foundation of Head walls complete exculding pointing and plastering as
per drawing and technical specification Clause 1109

A Brick Masonry in 1:4 cement mortar

Rate as per item No.11.5 (ii) Chapter 11 cum

B In cement-lime mortar (1:0.5:4.5)

Rate as per item No.11.5 (iii) Chapter 11 cum

9.9 Stone Masonry Work in cement mortar in foundation of Head walls complete as per drawing and technical
specification Clasue 1109

A In 1:4 cement mortar

Rate as per item No.11.6 (II) (ii) Chapter 11 cum

B In cement-lime mortar (1:0.5:4.5)

Rate as per item No.11.6 (II) (iii) Chapter 11 cum

9.10 Pointing with Cement Mortar (1:3) on brickwork as per technical specification Clause 613.3

Rate as per item No.12.2 of Chapter 12 sqm


9.11 Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification

Rate as per item No.12.3 of Chapter 12 sqm


9.12 Backfilling in Foundation Trenches as per drawing and technical specification Clause 1108

Rate as per Item No.11.2 of Chapter 11 cum


9.13 Providing PCC M20 Architectural Coping on the top of wing wall, return wall etc. complete as per drawing and technical
specification Clause 615

Rate as per Item No.12.13 of Chapter 12 m


Chapter 10 - TRAFFIC SIGNS, MARKINGS AND OTHER ROAD APPURTENANCES

10.1 Printing New Letters and Figures of any Shade

Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even
shade as per drawings and Technical Specification Clause 1701

I Hindi (Matras commas and the like not to be measured and paid for. Half letters shall be counted as half only) per cm 0.92
height per
letter

ii English and Roman per cm 0.59


height per
letter

10.2 Traffic Signs

A Retro-reflectorised Traffic Signs

I Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated
lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15
grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical
Specification Clause 801

i 900mm equilateral triangle each 5,541.40

ii 600mm equilateral triangle each 3,723.40

iii 600mm circular each 4,913.60

iv 800mm x 600mm rectangular each 6,759.70

v 600mm x 450mm rectangular each 4,791.70

vi 600mm x 600mm square each 5,635.10


Item Description Unit Rate
No. (Rs.)

vii 900mm side octagon each 8,559.00

II Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated
lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 1.5 mm thick supported on GI pipe 50
mm dia firmly fixed to the ground by means of properly designed foundation with M-15 grade cement concrete 450 mm x
450 mm x 600 mm, 600 mm below ground level as per drawings and Technical Specification Clause 1701

i 900mm equilateral triangle each 5,607.50

ii 600mm equilateral triangle each 3,789.50

iii 600mm circular each 4,979.60

iv 800mm x 600mm rectangular each 6,825.80

v 600mm x 450mm rectangular each 4,857.80

vi 600mm x 600mm square each 5,701.20

vii 900mm side octagon each 9,562.20

III Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated
lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 1.5 mm thick supported on RCC Post
100 mm x 100 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete
450 mm x 450 mm x 600 mm, 600 mm below ground level as per approved drawing Clause 1701

i 900mm equilateral triangle each 4,755.40

ii 600mm equilateral triangle each 2,937.30

iii 600mm circular each 4,127.50

iv 800mm x 600mm rectangular each 5,973.60

v 600mm x 450mm rectangular each 4,005.70

vi 600mm x 600mm square each 4,849.10

vii 900mm side octagon each 7,772.90

Please ensure that area of aluminium plate of required size is entered in the analysis
item

(B) Semi Reflective Traffic Signs


I Providing and fixing of semi reflective cautionary, mandatory and informatory sign board as per IRC:67 made of 1.5 mm
thick MS Sheet duly stove white colour in front and gray colour on back with red reflective border of 65 mm width and
required letters and figures with reflective tape engineering grade as per Clause 1701.3.9 of MORD for Rural Roads of
required shade and colour supported and welded on 47mm x 47 mm x 12 SWG sheet tube firmly fixed to the ground by
mean of properly designed foundations with M-15 grade cement concrete 450x450x600 mm, 600 mm below ground level
as per approved drawing Clause 1701.2.2

i 900mm equilateral triangle each 4,265.00

ii 600mm equilateral triangle each 2,957.20

iii 600mm circular each 3,813.30

iv 800mm x 600mm rectangular each 5,141.30

v 600mm x 450mm rectangular each 3,725.70

vi 600mm x 600mm square each 4,332.40

vii 900mm side octagon each 7,109.70

10.3 Direction and Place Identification signs upto 0.9 sqm size board

A Retro-reflectorised Traffic Signs


(I) Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of encapsulated lens sqm 12,165.20
type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means of properly designed
foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600 mm below ground level as per approved drawing
and Technical Specification Clause 1701
Item Description Unit Rate
No. (Rs.)

(ii) Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of encapsulated lens sqm 11,231.20
type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on 2 inch dia GI Pipe firmly fixed to the ground by means of properly designed foundation with M-15 grade
cement concrete 450 x 450 x 600 mm, 600 mm below ground level as per approved drawing and Tehnical Specification
Clause 1701.

(iii) Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of encapsulated lens sqm 10,985.70
type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on RCC Post 100 mm x 100 mm firmly fixed to the ground by means of properly designed foundation with M-15
grade cement concrete 450 x 450 x 600 mm, 600 mm below ground level as per approved drawing and Technical
Specification Clause 1701

B Semi-Reflective Traffic signs


Direction and place indentification signs up to 0.9 sqm size board

(I) Providing and erecting direction and place identifications of semi reflective sign boards as per IRC:67 made of 2 mm thick sqm 8,591.40
M.S. Sheet duly stove enameled paint in white colour in front and grey colour on back with red reflective border of 70 mm
width and required message, letters, figures with reflective engineering grade tape as per MORD specifications of required
shade and colour. Supported and welded on 47 mm x 47mm of 12 SWG Square tube of 3050 mm height duly
strengthened by 25 mm x 5 mm M/s flat iron on edges on back firmly fixed to the ground by means of properly designed
foundations with M-15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per approved
drawing and Technical Specification Clause 1701

10.4 Direction and Place Identification signs with size more than 0.9 sqm size board
A Retro-reflectorised Traffic Signs
(I) Providing and erecting direction and place identification retro-\reflectorised sign as per IRC:67 made of encapsulated lens sqm 12,655.40
type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm
supported on mild steel angle iron posts 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly
designed foundation with M-15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per
approved drawing and Technical Specification Clause 1701

(ii) Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of encapsulated lens sqm 12,754.00
type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm
supported on dia GI Pipe firmly fixed to the ground by means of properly designed foundation with M-15 grade cement
concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per approved drawing and Technical Specification
Clause 1701

(iii) Providing and erecting direction and place identification retro- reflectorised sign as per IRC:67 made of encapsulated lens sqm 11,302.50
type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm
supported on RCC Posts 100 mm x 100 mm firmly fixed to the ground by means of properly designed foundation with M 15
grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per approved drawing and Technical
Specification Clause 1701

B Semi-Reflective Traffic Signs

Direction and place identification signs more than 0.90 sqm sign board

Providing and erecting direction and place identification of semi reflective sign boards as per IRC-67 made of 2 mm thick sqm 9,723.80
M.S. Sheet duly stove enameled paint white colour in front and grey colour on back with reflective border of 70 mm width
and required message, letters, figures with reflective tape of engineering grade as per MORD specifications of required
shade and colour. Supported and welded on two nos. 47 mm x 47 mm of 12 SWG square tube of 3050 mm height duly
strengthened by 25 mm x 5 mm MS flat iron on edges on back firmly fixed to the ground by means of properly designed
foundations with M-15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per approved
drawing and Technical Specification Clause 1701

10.5 Painting Two Coats on New Concrete Surfaces

Painting two coats including primer coat after filling the surface with synthetic enamel paint in all shades on new, sqm 65.40
plastered / concrete surfaces as per drawing and Technical Specification Clause 1701

10.6 Painting on Steel Surfaces

Providing and applying two coats of ready mix paint including primer coat of approved brand on steel surface after through sqm 66.90
cleaning of surface to give an even shade as per drawing and Technical Specification Clause 1701
Item Description Unit Rate
No. (Rs.)

10.7 Painting on Concrete/Steel Surfaces with Epoxy


Painting two coats including prime coat with epoxy paint of approved brand on concrete/steel surfaces after through sqm 121.50
cleaning of surface to give an even shade as per drawing and Technical Specification Clause 1701

10.8 Painting lines, Dashes, Arrows, etc. on Road in Two Coats on New Work
Painting lines, dashes, arrows, etc. on roads in two coats on new work with ready mixed road marking paint conforming to sqm 78.50
IS:164 on bituminous/concrete surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control as per drawing and Technical Specification Clause 1702

10.9 Painting lines, Dashes, Arrows, etc. on Roads in Two Coats on Old Work

Painting lines, dashes, arrows, etc. on roads in two coats on old work with ready mixed road marking paint conforming to sqm 61.40
IS:164 on bituminous/concrete surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control as per drawing and technical specification Clause 1702

10.10 Kilometre Stone


Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in position
including painting and printing, etc as per drawing and Technical Specification Clause 1703

I) 5th Kilometre Stone (precast) each 3,524.80

ii) Ordinary Kilometer Stone (Precast) each 2,116.40

iii) 200 m stone (precast) each 563.20

10.11 Boundary Pillar

Reinforced cement concrete M15 grade boundary pillars/local stone of standard design as per IRC:25, fixed in position each 605.40
including finishing and lettering but excluding painting as per drawing and Technical Specification Clause 1704

10.12 G.I Barbed Wire Fencing 1.2 m high

Providing and fixing 1.2 m high GI barbed wire fencing with 1.8 m RCC posts 150 mm x 150 mm placed every 3 m centre- Running m 243.90
to-centre founded in M15 grade cement concrete, 0.6 m below ground level, every 15th post, last but one end post and
corner post shall be strutted on both sides and end post on one side only and provided with 9 horizontal lines and 2
diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc. complete as per Clause 1705.

10.13 G.I Barbed Wire Fencing 1.8 m high


Providing and fixing 1.8 m high GI barbed wire fencing with 2.4 m RCC M15 grade 150 mm x 150 mm concrete post Running m 404.80
placed every 3 m centre-to-centre founded in M15 grade cement concrete, 0.6 m below ground level, every 15th post, last
but one end post and corner post shall be strutted on both sides and end post on one side only and provided with 12
horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc. complete as per
Clause 1705.

10.14 Tubular Steel Railing on Medium Weight Steel Channel (ISMC series) 100 mm x 50 mm

Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC Running m 1,581.50
series) 100 mm x 50 mm, 1.2 m high above ground, 2 m centre-to-centre, complete as per approved drawings Clause
1706

10.15 Tubular Steel Railing on Precast RCC posts, 1.2 m high above Ground Level

Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M-20 grade RCC vertical posts Running m Err:509
175 mm x 175 mm x 1.8 m high (1.2 m above Gl) with 3 holes 50 mm dia for pipe, fixed 2 m centre-to- centre complete as
per approved drawings Clause 1706

10.16 Providing and Fixing 'Logo' of PMGSY Project


Item Description Unit Rate
No. (Rs.)

Providing and fixing of typical PMGSY informatory sign board with Logo as per MORD specifications and drawing. Three each 21,457.90
MS Plates of 1.6 mm thick, top and middle plate duly welded with MS flat iron 25mm x 5m size on back on edges. The
lower plate will be welded with MS angle iron frame of 25mm x 25mm x 5mm. The angle iron frame of the lower most plate
and flat iron frame of middle plate will be welded to 2 nos. 75mm x 75 mm of 12 SWG sheet tubes posts duly embedded in
cement concrete M-15 grade blocks of 450mm x 450mm x 600mm, 600mm below ground level. The top most diamond
plate will be welded to middle plate by 47mm x 47mm of 12 SWG steel plate tube. All M.S. will be stove enameled on both
sides. Lettering and printing arrows, border etc. will be painted with ready mixed synthetic enamel paint of superior quality
in required shade and colour. All sections of framed posts and steel tube will be painted with primer and two coats of
epoxy paint as per drawing Clause 1701 and Annexure 1700.1

10.17 Traffic Cone

Provision of red fluorescent with white reflective sleeve traffic cone made of Low Density Polyethylene (LDPE) material each 1,344.80
with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per
BS:873

10.18 Rumble Strips

Provision of 15 n0s.rumble strips covered with premix bituminous carpet,15.2 mm high


at centre,250mm wide placed at 1m centre to centre at approved location to control
speed, marked with white strips of road marking paint.

The rate per sqm of premix carpet and road marking may be adopted from Chapters
5&10 respectively for the quantities calculated from approved drawings.
10.19 Safety Device and sign in Construction Zones

Provision and fixing of traffic sign for limited period at a suitable location in construction
zone comprising of warning zone,approach transition zone,working zoneand terminal
transition zone with a minimunm distance of 2-3 m from the edgeof the carraige way.The
bottom edge of the lowest sign plate to be not less than 2 M above the road level, fixed
on 600mx600mx6mm angle iron post,founded and installed as per approved design and
drawings,removed and disposed ofafter completion of construction work, all as per
IRC:SP 55-2001

Following types of signs are required to be fixed in construction zones for safety of
traffic.

a) Diversion one km ahead

b) Traffic sign ahead

c) Road ahead closed

d)Men at work

e)Road narrow

f)Un even road

g)slipery road

h)Loose chipping

I)Diversion

J)Do not enter

k)Road closed

l)Stop

k)Slow

Speed limit

Note: The rate for traffic signs are already worked out and given elsewhere in this
chapter.The same may be adopted

10.20 Road Markers/Road Stud with Lens Reflector


Providing and fixing of road stud 100 x 100 mm die cast in aluminium, resistant to corrosive effect of salt and grit, fitted each 547.80
with lense reflectors, installed in concrete or asphaltic surface by drilling holes 30 mm upto a depth of 600 mm and bedded
in a suitable bituminous grout or epoxy mortar, all as per BS:873 (Part 4) 1973.

Chapter 11 - FOUNDATION

11.1 Excavation for Structures


Item Description Unit Rate
No. (Rs.)

Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m,
dressing of sides and bottom and backfilling in trenches with excavated suitable material.

I Ordinary soil

Upto 3 m depth cum 102.00


3 m to 6 m depth cum 148.30

II Ordinary rock (not requiring blasting)

Upto 3 m depth cum 163.90

III Hard rock (requiring blasting) cum 390.70

IV Hard rock (blasting prohibited) cum 386.90

V Marshy soil cum 465.90

11.2 Fillling in foundation trenches as per drawing and technical specification Clause 305.3.9

I Sand filling cum 1,411.80

ii Earth filling (For marshy soil) cum 161.00

11.3 Filling annular space around footing in rock as per technical specification Clause 1203.4.3.

P.C.C grade M 15
A. With crushed Stone cum 4,844.60
B With natural Gravel cum 99.20
11.4 Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications
Clause 802, 803, 1202 & 1203

A. With crushed stone.


I P.C.C grade M 10
Nominal mix 1:3:6 cum 5,216.60
Nominal mix 1:3.6 (Hand mixing) cum 5,240.10
II P.C.C grade M 15
Nominal mix (1:2.5:5) cum 5,085.60
Nominal mix 1:2.5:5 (Hand mixing) cum 5,109.10
III P.C.C. grade M 20
Nominal mix (1:2:4) cum 5,756.20
Nominal mix 1:2:4 (Hand mixed) cum 5,779.70
IV R.C.C grade M 20 cum 6,108.90
V R.C.C. grade M 25 cum 6,510.70
B. With Natural Gravel
I C P.C.C Grade M 10
Nominal mix 1:3:6 cum 4,869.00
Nominal mix 1:3:6 (Hand mixing) cum 4,855.00
II C P.C.C Grade M15
Nominal mix 1:2.5:5 cum 4,849.00
Nominal mix 1:2.5:5 (Hand mixing) cum 4,835.00
III C P.C.C Grade M 20
Nominal mix (1:2:4) cum 5,528.00
Nominal mix 1:2:4 (Hand mixed) cum 5,903.00
IV R.C.C. M 20 cum 5,824.00
V R.C.C. M 25 cum 6,309.00
11.5 Brick masonry work in cement mortar in foundation complete excluding pointing and plastering as per drawing and
technical specifications Clauses 600, 1202 & 1203

I. Brick masonry in 1:3 cement mortar cum 6,672.80

ii Brick masonry in 1:4 cement mortar cum 6,464.40

iii Brick masonry in 1:6 cement mortar cum 6,375.20


Item Description Unit Rate
No. (Rs.)

11.6 Stone masonry work in cement mortar in foundation complete as per drawing and technical specifications Clauses 702,
704, 1202 & 1203.

I Coursed rubble masonry (1st sort)

In 1:3 cement mortar cum 4,441.40

In 1:4 cement mortar cum 4,160.20

in 1:6 Cement morter cum 738.15

II Coursed rubble masonry (2nd sort)

In 1:3 cement mortar cum 5,159.10

In 1:4 cement mortar cum 3,786.30

in 1:6 Cement morter cum 603.75

III Random Rubble Masonry

In 1:3 cement mortar cum 5,670.80

In cement mortar 1:4 cum 3,978.30

in 1:6 Cement morter cum 2,456.00

11.7 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal t 54,969.90
steel/Shyam steel/RINL) in foundation complete as per drawings and technical specifications Clauses 1000 and 1202

11.8 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (Other ISI approved TMT reinforcement bar t 47,068.50
(SAI/BISCON/THERMAX or equivalent)) in foundation complete as per drawings and technical specifications Clauses
1000 and 1202

11.9 Supplying, fitting and placing MS bar (Fe-500 ) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal t 55,930.00
steel/Shyam steel/RINL) in foundation complete as per drawings and technical specifications Clauses 1000 and 1202

Chapter 12 - SUBSTRUCTURE

12.1 Brick masonry work in cement mortar in substructure complete excepting pointing and plastering, as per drawing
and technical specification Clauses 602, 603, 604, 1202 & 1204

I In 1:3 cement mortar cum 7,137.90

ii In 1:4 Cement mortar cum 6,925.70

iii In 1:5 cement mortar cum 6,888.20

12.2 Pointing with cement mortar (1:3) on brickwork as per drawing and technical specification Clauses 613.3 and 1204 10 sqm 583.50

12.3 Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification Clauses 613.4 10 sqm 1,211.70
& 1204

12.4 Stone masonry in cement mortar for substructure complete as per drawing & technical specification Clauses 702, 704,
1202 and 1204

I Coursed rubble masonry (1st sort)

In 1:3 cement mortar cum 4,878.00

In 1:4 cement mortar cum 4,582.70

In cement mortar (1:5) cum 4,394.10

In 1:6 Cement morter cum 0.00

II Coursed Rubble masonry (2nd sort)

In cement mortar (1:3) cum 4,859.30

In 1:4 cement mortar cum 4,443.70

In cement mortar (1:5) cum 4,384.30

In 1:6 cement morter cum 23.66

III Random rubble masonry


Item Description Unit Rate
No. (Rs.)

In cement mortar (1:3) cum 5,414.70

In 1:4 cement mortar cum 4,889.80

In cement mortar (1:5) cum 4,814.80

In1:6 Cement morter cum 240.00

12.5 Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804,
805, 806, 807, 1202 ans 1204

A. With Crushed Stone

I P.C.C grade M 15

I) Nominal mix (1:2.5:5) cum 5,379.00

ii) Nominal mix 1:2.5:5 (Hand mixing) cum 5,403.90

II P.C.C. grade M 20

I) Nominal mix (1:2:4) cum 6,088.30

ii) Nominal mix 1:2:4 (Hand mixed) cum 6,113.20

III RCC Grade M20 for height upto 5 m cum Err:508

ii) For height above 5 m upto 10 m cum Err:508

IV RCC Grade M25 for height upto 5 m cum Err:508

ii) For height above 5 m upto 10 m cum Err:508

B. With Natural Gravel

I C P.C.C grade M15

Nomi I)Nominal mix (1:2.5:5) cum 4,990.00

Nomi ii)Nominal mix 1:2.5:5) Hand mixing cum 4,928.00

II C P.C.C Grade M20

Nomi I)Nominal mix(1:2:4) cum 5,847.00

Nomi ii)Nomimix(1:2:4) Hand mix cum 5,770.00

III C R.C.C Grade M20

For I) Forheight up to 5M cum 6,160.00

For ii)Forheight above 5M upto 10M cum 6,272.00

IV C R.C.C.Grade M 25

For I)Height upto 5M cum 6,356.00

For ii)Height above 5 M upto 10 m cum 6,471.00

12.6 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal t 55,091.00
steel/Shyam steel/RINL) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 &
1202

12.7 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (Other ISI approved TMT reinforcement bar t 47,189.50
(SAI/BISCON/THERMAX or equivalent)) in substructrue complete as per drawings and technical specification Clauses
1002, 1005, 1010 & 1202

12.8 Supplying, fitting and placing MS Bar (Fe-500 ) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal t 56,051.10
steel/Shyam steel/RINL) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 &
1202

12.9 Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 Nos. 117.70
mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete
as per drawing and technical specification Clauses 614, 709, 1204.3.7

12.10 Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8

I Granular material cum 1,280.40

ii Sandy material cum 1,576.00


Item Description Unit Rate
No. (Rs.)

12.11 Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 cum 1,797.00
mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind
abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical
specification Clause 1204.3.8

12.12 Supplying, fitting and fixing in position true to line and level elastomeric bearing
conforming to IRC:83 (Part-II) Section IX complete, including all accessories as per
drawings and technical specification Clause 1207.1 cu cm 1.59

12.13 Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and technical
specification Clauses 615, 710 and 1204.3.11

I With Crushed stone Running m 395.10

ii With Natural Gravel Running m 379.00

12.14 Providing pressure relief pipes 100 mm dia in bottom slab of box cell on a filter media base of 500 mm x 500 mm as per Nos. 606.10
drawing and technical specification Clause 1205.5.7

Chapter 13 - SUPERSTRUCTURE

13.1 Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses
800, 1205.4 and 1205.5

A With crushed stone

I R.C.C grade M 20

(I) For nominal mix 1:2:4

a) (a) Height upto 5 M cum 6,997.70

b) (b) Height from 5m to 10M cum 0.00

c) (c0 Height above 10 M cum 0.00

II For nominal mix 1:2:4 (Hand mixed)

a) (a) Height upto 5 M cum Err:508

b) (b) Height 5m to 10M cum Err:508

c) © Height above 10M cum Err:508

III For design mix RCC M 20

a) (a) Height upto 5M cum Err:508

b) (b) Height 5Mto 10 M cum Err:508

c) © Height above 10 M cum Err:508

IV R.C.C M 25

a) Height upto 5M cum Err:508

b) Height from 5M to 10 M cum Err:508

c) Height above 10 M cum Err:508

V R.C.C. Grade M 30

a) Height upto 5M cum Err:508

b) Height from 5M to 10M cum Err:508

c) Height above 10M cum Err:508

B. B. With Natural Gravel

I Grad R.C.C. grad M 20

(I) For For Nominal mix 1:2:4

a) Height upto 5M cum 6,720.00

b) Height from 5M to 10M cum 7,000.00

c) Height above 10M cum 7,280.00

II For Nominal mix 1:2:4 (Hand Mixed)


Item Description Unit Rate
No. (Rs.)

a) Height upto 5M cum 6,671.00

b) Height from 5M to 10M cum 6,949.00

c) Height above 10M cum 7,227.00

(III) For For Design mix RCC M 20

a) Height upto 5 M cum 6,515.00

b) Height from 5m to 10M cum 6,786.00

c) Height above 10 M cum 7,058.00

II R.C.C M25

a) Height upto 5M cum 7,254.00

b) Height from 5M to 10M cum 7,556.00

c) Height above 10M cum 7,859.00

III Grad R.C.C M30

a) Height upto 5M cum 7,575.00

b) Height from 5M to 10 M cum 7,890.00

c) Height above 10 M cum 8,206.00

13.2 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar . (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal t 56,316.20
steel/Shyam steel/RINL) in superstructure complete as per drawing and technical specifications Clauses 1002, 1010 and
1202

13.3 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar . (Other ISI approved TMT reinforcement bar t 48,414.80
(SAI/BISCON/THERMAX or equivalent)) in superstructure complete as per drawing and technical specifications Clauses
1002, 1010 and 1202

13.4 Supplying, fitting and placing MS Bar (Fe-500) reinforcement bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal t 57,276.40
steel/Shyam steel/RINL) . in superstructure complete as per drawing and technical specifications Clauses 1002, 1010 and
1202

13.5 Providing and laying cement concrete wearing course M 30 grade including reinforcement complete as per drawing and
technical specifications Clauses 800 and 1206.3

A With crushed stone cum 12,407.50

B With Natural Gravel cum 13,214.00

13.6 Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm nominal size aggregate, true to line and grade, Running m 2,397.00
tolerance of vertical railing post not to exceed 1 in 500, centre-to-centre spacing between vertical posts not to exceed 2000
mm as per drawing and technical specifications Clauses 800, 900 and 1208.3

13.7 Providing fitting and fixing mild steel railing complete as per drawing and technical specifications Clause 1208.2 Running m 3,593.70

13.8 Providing and fixing in position pipe railing consisting of IS Rolled steel joist posts designation IS MB 100 (100x75) at 2.5 Running m 1,544.80
m interval and three rows of 50 mm dia steel pipes (light) including fixing in position on bridge deck complete as per
drawing and technical specifications Clause 1208.2

13.9 Brick masonry work in cement mortar 1:3 in parapet excluding pointing and plastering as per drawing and technical cum 6,716.00
specifications Clauses 600, 900 and 1208.4

13.10 Drainage spouts complete as per drawing and technical specifications Clause 1209 Nos. 1,640.90

13.11 P.C.C. M 15 ordinary grade (1:2.5:5) levelling course below approach slab complete as per drawing and technical
specifications Clauses 800 and 1211

A With crushed stone

I Nominal mix (1:2.5:5) cum 4,890.00

ii Nominal mix 1:2.5:5 (Hand mixing) cum 4,875.40

B With Natural Gravel

I nal mix(1:2.5:5) cum 4,963.00


Item Description Unit Rate
No. (Rs.)

ii nal mix(1:2.5:5)Hand mixed cum 4,949.00

13.12 Reinforced Cement Concrete M 25 grade approach slab including reinforcement and formwork complete as per
drawing and technical specifications Clauses 800 and 1211

A With crushed stone cum 10,310.60

B With Natural Gravel cum 10,784.00

13.13 Providing and laying of an elastomeric slab seal expansion joint compleate as per Running m 16,461.00
approved drawing and approved specification to be installed by manufacturer/supplier
or their authorised representative ensuring compliance to the manufacturers instructuion
for instalation and as per technical specification clause 1207.2.5

13.14 Providing and laying of ancompression seal consisting of steel armoured nosing at two 15,931.00
edges of the joint gapsuitably anchored to the deck concrete and a preformed
chloroprene elastomer or closed cell foam joint sealer compressed and formed intothe
joint gap with special adhesive binder as per drawing and technical specification Clause
1207.2.4

13.15 Providing and laying a buried expansion joint, covered with 12 mm thick, 200 mm wide galvanised weldable structrual steel Running m 1,717.50
plate as per IS:2062, placed symmetrical to centre line of the joint, resting freely over the top surface of the deck concrete,
welding of 8 mm dia, 100 mm long galvanised nails spaced 300 mm c/c along the centre line of the plate, as per technical
specifications Clauses 1207.2.3

13.16 Filler Joint

I Providing and fixing 2 mm thick corrugated copper plate in expansion joint as per drawing and technical specifications Running m 946.70
Clause 1207.2.2

ii Providing and fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing and technical Running m 254.20
specifications

iii Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for Running m 285.00
fixedends of simply supported spans,covered with sealant complete as per drawing and
technical specification.

iv Providing and fillling joint sealing compound as per drawings and technical specifications with coarse sand and 6 per cent Running m 21.00
bitumen by weight.

iv
13.17 Stone masonry in cement mortar 1:3 for parapet complete as per drawing and technical specifications Clauses 700 and
1208.4

I Random rubble masonry cum 5,414.70

II Coursed rubble masonry (1st sort) cum 4,878.00

13.18 Pointing with cement mortar (1:3) on brickwork in parapet as per technical specifications Clauses 613.3 and 1208.4 10 sqm 583.50

13.19 Plastering with cement mortar (1:3) 15 mm thick on brickwork in parapet as per technical specifications Clauses 613.4 and 10 sqm 1,211.70
1208.4

13.20 Providing and laying parapet with PCC M 15 as per drawing & technical specifications Clauses 800 and 1208.4

A With crushed stone

I Nominal mix 1:2.5:5 (Hand mixing) cum 5,379.00

ii Nominal mix (1:2.5:5) cum 5,403.90

B With Natural Gravel

I nal Mix 1:2.5:5(Hand mixing) cum 5,274.00

ii nal Mix (1:2.5:5) cum 5,333.00

13.21 Providing bituminous wearing coat comprising of 20 mm thick premix carpet with 5 mm thick seal coat Type B for culverts
as per drawing and technical specifications Clauses 1206.2 and 500

I Rate for wearing coat as per item No. 5.9 of Chapter 5 sqm

ii Rate for seal coat Type B as per item No. 5.12 of Chapter 5 sqm
Item Description Unit Rate
No. (Rs.)

13.22 Providing bituminous wearing coat comprising of 50 mm thick bituminous macadam overlaid by 20 mm thick premix carpet
with 5 mm thick seal coat Type B

I Rate for BM layer may be analysed as per item No 5.3 of Chapter 5 cum

ii Rate of 20 mm premix carpet wearing course as per item No.5.9 of Chapter 5 sqm

iii Rate of seal coat Type B as per item No. 5.12 of Chapter 5 sqm

13.23 Brickwork in arches in cement mortar 1:4 complete including centering and shuttering excluding pointing and plastering as cum 15,283.80
per drawing and technical specifications Clauses 606 and 1205.1

13.24 Coursed rubble stone masonry arch (Ist sort) in cement mortar (1:4) complete including centering etc. complete as per
drawing and technical specifications Clauses 706 and 1205.1

I Arch For arch above 6Mspan cum 10,671.10

ii For Arch 4 m to 6 m span cum 9,604.00


iii For Arch less than 4 m span cum 8,003.30
13.25 Providing & Laying reinforced cement concrete arch complete including centering and shuttering excluding
reinforcement as per drawings and technical specifications Clauses 800, 900 and 1205.1

A With crushed stone


I RCC grade M20 (1:2.4) nominal mix

a) For arch above 6 m span cum 8,907.30

b) For arch 4 m to 6 m span cum 8,313.50

c) For arch less than 4 m span cum 7,719.70

II RCC Grade M 25

a) For arch above 6 m span cum Err:508

b) For arch 4 m to 6 m span cum Err:508

c) For arch less than 4 m span cum Err:508

B B With Natural Gravel

I Grad R.C.C.Grade M20 (1:2:4) nominal mix

I For Arch above 6M cum 9,108.00

ii For Arch 4M to 6M span cum 8,501.00

iii For Arch less than 4M span cum 7,894.00

II Grae R.C.C Grade M25

I For Arch above 6M span cum 9,922.00

ii For Arch 4M to 6M span cum 9,261.00

iii For Arch less than 4 M span cum 8,599.00

13.26 Providing steel R.S.Jst/ built-up steel sections including cutting, welding/ rivetting, hoisting, fixing in position for composite
girders with shear connectors complete with painting as per drawing and technical specifications Clause 1205.6

Steel section quintal 9,014.10

Chapter 14 - PROTECTION WORKS

14.1 Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as per Table cum 1,349.50
1300.1, no fragment weighing less than 25 kg laid dry complete as per drawing and technical specifications Clause 1301

14.2 Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire conforming to IS:280 and IS:4826 in 100 cum 2,178.20
mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing
not less than 25 kg each as per drawing and technical specifications Clause 1301

14.3 Providing and laying of apron with cement concrete blocks of size as per Table 1300.1 cast-in-situ and made with nominal cum 5,062.80
mix of M-15 grade cement concrete as per drawing and technical specifications Clause 1301
Item Description Unit Rate
No. (Rs.)

14.4 Single bamboo palasiding / walling of whole 2nd class bamboo (Jati or Bethua) 75mm dia and closely packed & driven
including fitting fixing with half bamboo kamis horizontally in three rows with cane or tying with wire complete and struts 1.5
m apart longitudinally and providing brush wood as per drawing and technical specifications Clause 1302.5

Driven at least 900 mm below ground and 1200 mm above ground Running m 782.20

Driven at least 900 mm below ground and 900 mm above ground on average Running m 737.20
14.5 Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical
specifications Clause 1302

I Stone/Boulder cum 1,349.50

I Cement concrete blocks of size as per Table 1300.2 cast in cement concrete of grade M 15

ii Concrete grade M 15 cum 5,187.30

iii Brick pitchng set in cement mortar 1:4 cum 5,848.70

14.6 Providing and laying filter material underneath pitching in slopes complete as per drawing and technical cum 1,768.60
specifications Clause 1302

14.7 Providing and laying flooring laid over cement concrete bedding complete as per drawing and technical specification
Clause 1303

I Rubble stone laid in cement mortar 1:3 cum 3,731.00

ii Cement conrete blocks grade M 15 cum 5,650.10

ii Brick on edge laid in cement mortar (1:3) cum 4,843.00

Note : Cement concrete bedding to be measured and paid extra.

14.8 Providing and laying of dry rubble flooring complete as per drawings and technical specifications Clause 1303.3 cum 2,216.80

14.9 Providing and laying curtain walls complete as per drawing and technical specification Clause 1304

I Brick masonry in cement mortar (1:4) cum 7,110.90

ii Coursed rubble masonary (2nd sort) in cement mortar (1:4) cum 4,443.70

iii Cement concrete grade M 10 cum 4,955.80

14.10 Construction of flexible apron 1 m thick comprising of loose stone boulders weighing not less then 25 kg beyond curtain cum 1,128.30
wall

14.11 Construction of toe walls for protection of slopes as per drawing and technical specifications Clause 1302.5

I Random rubble masonry in case of stone pitching laid with cement mortar (1:5) cum 3,988.60

ii Brick masonry in cement mortar 1:4 in case of brick pitching cum 5,742.70

iii Cement concrete grade M 10 in case of concrete block pitching cum 5184.00

Nominal mix 1:3:6

14.12 Single bamboo spur and palisading of whole 2nd class bamboo (jati or Bethua) 65 mm to 75 mm dia and closely packed &
driven, including fitting, fixing with half bamboo kamis horrizontally in three rows with cane or tying wire complete and struts
1500 mm apart longitudinally and providing brush wood as per drawing and technical specifications Clause 1302.5

I Driven at least 900 mm below ground and 1800 mm above ground on average Running m 917.20

ii Driven at least 900 mm below ground and 900 mm above ground on average Running m 740.90

14.13 Single bamboo spur and palisading of whole 1st class bamboo (Bholuka or Barua) 85 mm to 100 mm dia. Closely packed
& driven including fitting, fixing with half 2nd class bamboo (jati or Bethua) horizontally in three rows with cane or tying wire
complete and struts 1500 mm apart longitudinally and providing brush wood in the spur as per drawings and technical
specifications

A Driven at least 900 mm below ground and 1800 mm above ground Running m 1,343.70

B Driven at least 900 mm below ground and 900 mm above ground on average Running m 926.60
Item Description Unit Rate
No. (Rs.)

C Driven at least 600 mm below ground and 1200 mm above ground on average. Running m 851.60

14.14 Bamboo spur 'A' type with whole bamboo 85mm-100mm dia, placed 230 mm centre to centre driven 900 mm below
ground and 1200 mm to 1500 mm above ground tied with 2nd class bamboo (jati or Bethua) on either side at 450 mm
apart horizontally with galvanised wire etc. complete as per drawings and technical specifications

A 2nd class bamboo (jati or Bethua) 75 mm dia Running m 948.30

B 1st class bamboo (Bholuka or Barua ) 85 mm to 100 mm dia Running m 893.90

14.15 Providing 'A' type single spur with 1st class bamboo (Bholuka or Barua) 85 mm to 100 mm dia. Driven closely placed 3m to Running m 1,619.30
4m above ground and 1200 mm to 1500 mm below ground tied with cane or coir string, half 2nd class bamboo (jati or
Bethua) horizontally on both face placed not more than one metre apart including whole bamboo struts inside one metre
apart and 2 nos. of purlin at top and bottom fitted with vertical struts at 1500 mm apart and filling with brushwood or jungle
wood inside the spur complete as per drawing and technical specifications

14.16 Providing close bamboo toe walling consisting of 65mm to 75mm dia bamboos of length ranging from 1.2 m to 3m driven Running m 1,079.60
at 150 mm centre to centre and provided with three horizontal split bamboo runner fixed with nails. All bamboos to be duly
protected by coal tar painting.

14.17 Double timber spur with two rows at 800 mm c/c apart of 1st class local wood piles with timber of Azar/Nahar/Nageswar / Running m 23,770.60
Zarul wood 150 mm to 200 mm dia driven 2000 mm minimum below ground and 3600 mm above ground average placed
at 800 mm belts, bracings etc. of 100 mm x 75 mm size 1st class local wood longitudinally & crosswiswe at ends fitted with
10 mm dia bolts and nuts etc. including coaltarring of timber members and cost of necessary bamboo stagings etc. as
directed by the Engineer as per drawing and technical specifications

14.18 Supplying and filling up hollows of the timber spur to an average height of 3600 mm above ground with jungle wood Running m 69.90
branches as per drawing and technical specifications as directed by the Engineer.

Chapter 15 - MAINTENANCE OF ROADS

15.1 Restoration of Rain Cuts

Restoration of rain cuts with soil, moorum gravel or a mixture of these, clearing the loose soil, benching for 300mm width
laying fresh material in layers not exceeding 250 mm and compaction with plate compactor or power rammer to restore the
original alignment, level and slopes as per drawings and technical specifications Clause 1902

A Manual Means cum 130.50

B Mechanical Means cum 110.20

15.2 Maintenance of Earthen shoulder (filling with fresh selected soil)

1 Making up loss of material/irregularities on shoulders to the design level by adding fresh approved selected soil and sqm 72.10
compacting it with appropriate equipment at OMC upto a lead of 1000 m as per technical specification Clause 1903

Maintenance of Earhen shoulder (stripping of excess soil)

2 Stripping excess soil from the shoulder surface to achieve the approved level and compacting with plate compactor at sqm 15.60
OMC as per drawings and Technical Specification Clause 1903

15.3 Maintenance of Bituminous surface road

I Repair to pot holes by removal of failed material,trimming the sides to vertical and cum 7,396.20
levelling the bottom,cleaning the same with compressed air or any appropriate method
filled with 75 mm B.M. applying bitumen emulsion prime coat at the bottom and bitumen
emulsion tack coat on sides and on bottom as per technical specification Clause 502
and 503

ii Patch repair on already filled pot holes with 75 mm BM with 20 mm premix carpet and seal coat Type B as per drawings sqm 173.20
and technical specification Clause 1904.2

iii Repair to pot holes and removal of loose material, trimming of sides, cleaning of surface by providing tack coat, 20 mm sqm 162.90
thick pre-mix carpet and seal coat type B specification Clause 1904.2

iv Repair to pot holes and removal of loose material, trimming of sides, cleaning of surface by providing tack coat with sqm 173.70
bitumen emulsion, 20 mm thick pre-mix carpet using catonic bitumen emulsion and seal coat type B with bitumen emulsion

15.4 Maintenance of Gravel Road


Item Description Unit Rate
No. (Rs.)

Maintenance of gravel road including making up the loss of profile, rectifying corrugated surface, filling up of depressions, sqm 347.50
pot holes and erosion gullies by adding fresh material and compacting it with appropriate equipment or to strip excess of
material from the road surface as per drawings and technical specification Clause 1905

15.5 Maintenance of WBM Road

Maintenance of WBM road including filling up of pot holes, ruts and rectifying corrugated surface, damaged edges and sqm 290.20
ravelling as per technical specification Clause 1906.

15.6 Maintenance of Drains

The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side drains as m 2.30
well as catch water drains as per technical specification Clause 1907.

15.7 Maintenance of Culverts

I Maintenance of Hume pipe Culvert by way of Clearing, Cleaning, Erosion repair, repairs to cracks, parapet wall and One No. 1,439.60
protection work as per drawing and technical specification Clause 1908 Hume Pipe

ii Maintenance of Culverts Slab type

Maintenance of Slab type Culverts by way of clearing, Cleaning, Erosion repair, repairs to cracks, parapet walls and Culvert 2,851.80
Protection works as per drawing and technical specification Clasue 1908

15.8 Maintenance of Causeway

Maintenance of Causeway by way of minor Surface repairs, replacing Guide Posts, repair of flood gauges, removal of m 65.50
debris, providing boulders and protection work and painting as per technical specification Clause 1909

15.9 Maintenance of Road Signs

Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place km 1,100.90
identifications sign board as perdrawings and technical specification Clause 1910

15.10 Maintenance of steel and RCC Railing

I Repair of steel railing to bring it to original shape cleaning and repainting as per drawing and technical specification Clause
1911
Steel Railing Running m 319.40
ii Repair of RCC railing to bring it to the original shape, cleaning and repainting as per drawings and technical specification
Clause 1911

RCC Railing m 137.20

15.11 Maintenance of 200 metre and km stones

Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and
lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912

I Painting two coats with synthetic enamel paint sqm 123.90

ii Printing letters and figures of any shade with synthtic enamel paint of any approved colour to give an even shade km 524.40

15.12 Cutting of branches of trees shrubs and trimming of grass and weeds

I Cutting of branches of trees and shrubs from the road way or with in R.O.W including disposal of wood and leaves to one tree 100.00
suitable location as per technical specification Clause 1914

ii Cutting of shrubs from the road way or with in R.O.W and disposal of shrubs to suitable locations as per technical each 5.80
specifications Clause 1914

iii Trimming of grass and weeds from the shoulders/berms and disposing off the same to suitable locations as per technical sqm 1.90
specifications Clause 1914

15.13 White washing of parapet walls of CD work and tree truncks

White washing two coats on parapet walls and tree trunks including preparation of surface by cleaning scraping etc. as per sqm 16.50
technical specifications Clause 1915

15.14 Periodical Renewal to existing bituminous surface

1 Open graded Premix carpet 20 mm thick


I) Tack coat
Item Description Unit Rate
No. (Rs.)

Rates as per item 5.2 (ii) sqm

ii) Pre-mix carpet using bituminous (penetration grade modified bitumen) binder
Rates as per item No. 5.9 sqm

OR
iii) Premix carpet using bitumen Emulsion

Rates as per item No. 5.10 sqm

iv) Seal coat Type A, B or C

Rates as per item No. 5.11 sqm

2 Surface dressing single coat/first coat or 2nd coat


Rates as per item No. 5.6 sqm
Summary of Rate Analysis

Item Unit Rate


No. (Rs.)

Chapter 1 - LOADING, UNLOADING, CARRIAGE CRUSHING OF MATERIALS AND SETTING OUT

1.1 Loading and Unloading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish,
Crushed Slag, Stone for Masonry Work by Manual Means

(I) Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone cum 110.80
for Masonry Work by manual means including a lead upto 30 m

(ii) Loading of Earth, Sand, Moorum, Manure, Flyash by manual means including a lead upto 30 m cum 55.40

(iii) Unloading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, cum 55.40
Stone for Masonry Work by manual means including a lead upto 30 m

(iv) Unloading of Earth,Sand, Moorum,Manure,Fly ash, by manual means including lead upto 30M cum 34.60

1.2 Loading and Unloading Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed
Slag, Stone for Masonry Work by Mechanical Means

I Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone cum 63.40
for Masonry Work by mechanical means including a lead upto 30 m

ii Loading of earth,sand,moorum,manure,fly ash by mechanical means including a lead upto 30 M cum 33.30

iii Unloading of Earth, Sand, Lime, Moorum, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building cum 13.90
Rubbish, Manure, Crushed Slag, Flyash, Stone for Masonry Work by mechanical means.

1.3 Loading, Unloading and Stacking of Bricks by Manual Means

I Loading of Bricks by manual means including a lead upto 30 m 1000 Nos. 189.50

ii Unloading and Stacking of Bricks by manual means including a lead upto 30 m 1000 Nos. 189.50

1.4 Loading and Unloading of Cement by Manual Means

I Loading of Cement by manual means including a lead upto 30 m t 682.40

ii Unloading of Cement by manual means including a lead upto 30 m t 136.50

1.5 Loading and Unloading of Structural Steel and Steel Bars by manual means

I Loading of Structural Steel, Steel Bars by manual means including a lead upto 30 m t 145.10

ii Unloading of Structural Steel, Steel Bars by manual means including a lead upto 30 m t 145.10

1.6 Loading and Unloading of Bitumen Drums by Manual Means

I Loading of Bitumen Drums by manual means including a lead upto 30 m t 3.60

ii Unloading of Bitumen Drums by Manual Means including a lead upto 30 m t 151.00

1.7 Loading and Unloading of Timber by Manual Means

I Loading of Timber by manual means including a lead upto 30 m t 243.90

ii Unloading of Timber by manual means including a lead upto 30 m t 243.90

1.8 Loading and Unloading of C.C. Blocks, Kerb, etc.

I Loading with care C.C. Blocks, km Stone, 200 m Stone, Boundary Pillar, Kerb, Channel, Bond Stone, etc. by cum 359.00
manual means including a lead upto 30 m

ii Unloading with care C.C. Blocks, km Stone, 200 m Stone, Boundary Pillar, Kerb, Channel, Bond Stone, etc. by cum 359.00
manual means including a lead upto 30 m
Item Unit Rate
No. (Rs.)

1.9 Loading and Unloading of Hume Pipes

I Loading of RCC Hume pipes by mechanical means including a lead upto 30 m

A. 1000 / 1200 mm dia Hume pipe per pipe 78.50

B. 750 mm dia Hume pipe per pipe 47.10

C. 600/450 mm dia Hume pipe per pipe 33.60

II Unloading of RCC Hume pipe by manual means including a lead upto 30 m

A 1000/1200 mm dia RCC Hume pipes per pipe 447.50

B. 750 mm dia Hume pipe per pipe 372.90

C. 600/450 mm dia Hume pipe per pipe 279.70

III Unloading of RCC Hume pipes by mechanical means including a lead upto 30 m

A 1000/1200 mm dia Hume pipe per pipe 53.90

B 750 mm dia Hume pipe per pipe 32.40

C. 600/450 mm dia Hume pipe per pipe 23.10

1.10 Haulage excluding Loading & Unloading

Haulage of materials by tipper excluding cost of loading, unloading and stacking.

Case-I : Surfaced Road t.km 8.20

0 Cum/km 14.90

Case-II: Unsurfaced Gravel Road t.km 10.20

0 Cum/km 18.50

Case-III: Katcha Track and Track in River Bed/Nallah Bed and Choe Bed t.km 16.00

0 Cum/km 29.10

1.11 Supply of Quarried stone and hand breaking


Supply of quarried stone and hand breaking into coarse aggregate to Grading 1 (90 mm to 45 mm) as per cum 1,461.00
Table 400.8 of Technical Specifications.

Supply of quarried stone and hand breaking into coarse aggregate to Grading 2 (63 mm to 45 mm) as per cum 1,548.00
Table 400.8 of Technical Specifications.

Supply of quarried stone and hand breaking into coarse aggregate to Grading 3 (53 mm to 22.4 mm) as per cum 1,635.00
Table 400.8 of Technical Specifications.

1.12 Crushing of Stone Aggregates 100 per cent passing through 53 mm sieve as per Table 500.6 of Technical
Specifications.

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 t/h capacity comprising cum 1,248.60
of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates 100
per cent passing through 53 mm sieve as per Table 500.6 of Technical Specifications including the cost of
stone.

1.13 Crushing of Stone Aggregates 100 per cent passing through 22.4 mm sieve as per Table 500.6 of Technical
Specifications.

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 t/h capacity comprising cum 1,446.80
of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates 100
per cent passing through 22.4 mm sieve as per Table 500.6 of Technical Specifications including the cost of
stone.

1.14 Crushing of Stone Aggregates Nominal Size 13.2 mm as per Table 500.9 of Technical Specifications.
Item Unit Rate
No. (Rs.)

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 t/h capacity comprising cum 1,705.00
of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of
13.2 mm nominal size as per Table 500.9 of Technical Specifications including the cost of stone.

1.15 Crushing of Stone Aggregates 9.5 mm Nominal Size as per Table 500.9 of Technical Specifications.

Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 t/h capacity comprising cum 1,705.00
of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 9.5
mm nominal size as per Table 500.9 of Technical Specifications including the cost of stone.

1.16 Setting Out

Unit=1Km

The analysis of rate per km shall account for the following:

(I) Reference benchmark one no.

(ii) Working benchmark 4 nos. per Km and near all drainage

structure and bridges.

(iii) Reference pillars/Burjees @ 50 m interval on both sides of

formation width.

(iv) The marking of centre line setting out curves and recording

of levels,etc. by the surveyor will be incidental to the work and

no extra payment shall be made for the same.

(v) Typical benchmark as per Drawing 200.1 each 6911.10

(vi) Typical reference pillar as per Drawing 200.2 each 3437.90

Chapter 2 - SITE CLEARANCE

2.1 Clearing Grass and Removal of Rubbish

Clearing grass and removal of rubbish up to a distance of 30 m outside the periphery of the area as per
Technical Specification Clause 201.

By Manual Means hectare 11,647.20

2.2 Clearing and Grubbing Road Land

Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees
of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and
stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal
of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201.

(I) By Manual Means


(A) In area of non thorny jungle hectare 42,648.30
In area of thorny jungle hectare 61,247.30
(ii) By Mechanical Means

In area of non-thorny jungle hectare 23,724.00


In area of thorny jungle hectare 28,954.10
2.3 Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps

Cutting of trees, including cutting of trunks, branches and removal of stumps & roots, refilling, compaction of
backfilling and stacking of serviceable material by manual means with all lifts as per Technical Specification
Clause 201.
A Lead upto 100 m

I Girth above 300 mm to 600 mm each 206.90

ii Girth above 600 mm to 900 mm each 358.70

iii Girth above 900 mm to 1800 mm each 711.20


Item Unit Rate
No. (Rs.)

iv Girth above 1800 mm to 2700 mm each 1,358.00

v Girth above 2700 mm to 4500 mm each 2,789.60

vi Girth above 4500 mm each 8,199.70

B Lead upto 1000 m

I Girth above 300 mm to 600 mm each 220.70

ii Girth above 600 mm to 900 mm each 400.10

iii Girth above 900 mm to 1800 mm each 766.40

iv Girth above 1800 mm to 2700 mm each 1,440.80

v Girth above 2700 mm to 4500 mm each 2,881.60

vi Girth above 4500 mm each 8,429.80

2.4 Uprooting and Removing Stumps & Roots

Uprooting and removing stumps & roots,compaction of backfilling and staking of servicable material by manual
means as per Technical Specification clause 201.
as per Technical Specification Clause 201
A Lead upto 100 m

I Girth above 300 mm to 600 mm each 124.80

ii Girth above 600 mm to 900 mm each 197.70

iii Girth above 900 mm to 1800 mm each 419.40

iv Girth above 1800 mm to 2700 mm each 826.60

v Girth above 2700 mm to 4500 mm each 1,665.70

vi Girth above 4500 mm each 4,712.80

B Lead upto 1000 m

I Girth above 300 mm to 600 mm each 128.00

ii Girth above 600 mm to 900 mm each 209.20

iii Girth above 900 mm to 1800 mm each 433.20

iv Girth above 1800 mm to 2700 mm each 845.00

v Girth above 2700 mm to 4500 mm each 1,688.70

vi Girth above 4500 mm each 4,827.80

2.5 Dismantling of Structures


Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of
masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting
the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts
and lead of 1000 m as per Technical Specification Clause 202.

I By Manual Means
(A) Lime Concrete cum 288.30
(B) Cement Concrete cum 365.60

© Reinforced Cement Concrete cum 978.30

II By Mechanical Means
(A) Cement Concrete cum 376.90
(B) Reinforced Cement Concrete cum 591.20

2.6 Dismantling Brick/Tile Work


Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick
masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and
lead of 1000 m as per Technical Specification Clause 202.

(A) Lime mortar cum 171.80


(B) Cement mortar cum 226.40
© Mud Morter cum 155.90
(D) Dry Brick Pitching or Brick Soling cum 144.20
Item Unit Rate
No. (Rs.)

2.7 Dismantling Stone Masonry as per Technical Specification Clause 202.

Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone
masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and
lead of 1000 m as per Technical Specification Clause 202.

(A) Rubble Stone Masonry in Lime Mortar cum 220.70

(B) Rubble Stone Masonry in Cement Mortar cum 175.00

© Rubble Stone Masonry in Mud Mortar cum 171.80

(D) Dry Rubble Masonry cum 160.20

(E) Dismantling Stone Pitching / Dry Stone Spalls cum 159.50

(F) Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials cum 197.50

2.8 Dismantling Wood Work Wrought and Planed Fixed in Frames of Trusses upto a height of 5 m above Plinth cum 501.60
Level as per Technical Specification Clause 202.

2.9 Dismantling Steel Work in all Types of Sections upto a height of 5 m above Plinth Level excluding Cutting of
rivet as per Technical Specification Clause 202.

(A) Including dismembering t 1,341.60

(B) Excluding dismembering t 947.70

© Extra over Items (A) and (B) for cutting rivets t 10.70

2.10 Scraping of bricks dismantled from brick work including stacking as per Technical Specification 1000 Nos. 1,019.10
Clause 202.

2.11 Scraping of Stone from Dismantled Stone Masonry as per Technical Specification Clause 202.

In Cement or Lime Mortar cum 409.30

2.12 Scraping Plaster in Lime or Cement Mortar from Brick / Stone Masonry as per Technical Specification sqm 13.10
Clause 202.

2.13 Removing all types of Hume pipes and stacking within a lead of 1000 m including Earthwork and
Dismantling of Masonry Works as per Technical Specification Clause 202.

(A) Upto 600 mm dia Hume pipe m 151.10


(B) Above 600 mm to 900 mm dia Hume pipe m 204.60
(C) Above 900 mm dia Hume pipe m 350.20
Note : 1. The excavation of earth,dismantling of stone masonary
work in head walls and protection works is not included which is
to be measured and paid seperately.
2. Credit for retrives stone from masonary work may be
taken as per actual availability.
2.14 Dismantling of Flexible Pavements

Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 100 m, stacking
serviceable and unserviceable materials separately as per Technical Specification Clause 202

I By Manual Means
(A) Bituminous Courses cum 531.80
(B) Granular Courses cum 388.00
II By Mechanical Means
(A) Bituminous Courses cum 226.50
2.15 Dismantling of Cement Concrete Pavements as per Technical Specification Clause 202.

Dismantling of cement concrete pavements by mechanical means using pneumatic tools breaking to pieces cum 1,010.40
not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled
materials upto a lead of 1000 m, stacking serviceable and unserviceable materials separately

2.16 Dismantling Guard Rails


Dismantling guard rails by manual means and disposal of dismantled material with all lifts and upto a lead of running m 58.40
1000 m, stacking serviceable materials and unserviceable materials separately as per Technical Specification
Clause 202.
2.17 Dismantling Kerb Stones
Item Unit Rate
No. (Rs.)

Dismantling kerb stones by manual means and disposal of dismantled material with all lifts and upto a lead of running m 11.40
1000 m as per Technical Specification Clause 202.

2.18 Dismantling Kerb Stone Channels


Dismantling kerb stone channels by manual means and disposal of dismantled material with all lifts and upto a running m 17.50
lead of 1000 m as per Technical Specification Clause 202.

2.19 Dismantling Kilometre Stones

Dismantling of kilometre stones including cutting of earth, foundation and disposal of dismantled material with
all lifts and lead upto 1000 m and backfilling of pit as per Technical Specification Clause 202.

(A) 5th km Stone m 287.40


(B) Ordinary km Stones m 180.10
© 200 m Stones m 35.60
2.20 Dismantling of Fencing

Dismantling of barbed wire fencing / wire mesh fencing including posts, foundation concrete, backfilling of pit running m 44.70
by manual means including disposal of dismantled material with all lifts and upto a lead of 1000 m, stacking
serviceable material and unserviceable material separately as per Technical Specification Clause 202.

2.21 Dismantling of CI Water Pipe Line

Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead upto 1000 m and running m 111.20
stacking of serviceable material and unserviceable material separately under supervision of concerned
department as per Technical Specification Clause 202.

2.22 Removal of Cement Concrete Pipe of Sewer Gutter


Removal of cement concrete pipe of sewer gutter 1500 mm dia under the supervision of concerned running m 188.70
department including disposal with all lifts and upto a lead of 1000 m and stacking of serviceable and
unserviceable material separately but excluding earth excavation and dismantling of masonry works as per
Technical Specification Clause 202.

2.23 Removal of Telephone/Electric Poles and Lines


Removal of telephone/electric poles with wires including excavation and dismantling of foundation concrete each 150.90
and lines under the supervision of concerned department, disposal with all lifts and upto a lead of 1000 m and
stacking the serviceable and unserviceable material separately as per Technical Specification Clause 202.

Chapter 3-EARTHWORK, EROSION CONTROL AND DRAINAGE


3.1 Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means

a Manual means

Scarifying existing granular surface to a depth of 50 mm and disposal of scarified material with a lift upto 3 m sqm 18.50
and leads upto 1000 m as per Technical Specification Clause 301.4.

b Mechanical means
Scarifying existing granular surface to adepth of 50mm and disposal of scarified material with a lift upto 3 m sqm 7.10
and lead upto 1000m as per Technical specification Clause 301.4

3.2 Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical Means


Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a sqm 6.50
lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4.

3.3 Construction of Embankment with Material Obtained from Roadway Cutting

Construction of embankment with approved materials deposited at site from roadway cutting and excavation cum 58.00
from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and
300.2 as per Technical Specification Clause 301.5

3.4 Construction of Embankment with Material Obtained from Borrow Pits

Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m,
transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1
and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5

(I) Private Land cum 230.60


(ii) Govt. Land cum 230.60
3.5 Excavation in Cutting in Soil by manual means with lead upto 50 m
Item Unit Rate
No. (Rs.)

Excavation for roadway in soil using manual means for carrying of cut earth to embankment site with a lift upto cum 109.20
1.5 m and lead upto 50 m as per Technical Specification Clause 302.3 (Manual should be use where machines
can not be deployed due to site condition)

ii Excavation in Soil with Dozer with lead upto 100 m

Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of cum 54.10
embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with
requirements of lines, grades and cross-sections.

iii Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m

Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and cum 59.90
loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and
cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per
Technical Specification Clause 302.3

3.6 Excavation in Marshy Soil


Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity including cutting and cum 65.50
loading in tippers and disposal with a lift upto 1.5 m and lead upto 1000 m, trimming of bottom and side slopes
in accordance with requirements of lines, grades and cross- sections as per Technical Specification Clause
302.3.6.

3.7 Removal of Unsuitable Soil with Disposal upto 1000 m


Removal of unsuitable soil including excavation, loading and disposal upto 1000 m lead but excluding cum 59.90
compaction ground supporting embankment subgrade replacement by suitable soil, which shall be paid
separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11

Note: This item does not include replacement of unsuitable soil by suitable soil Replacement,Where required,
is to be provided and paid seperately under Clause 303.5.2

3.8 Excavation in ordinary Rock by manual means

I Excavation in ordinary rock using manual means including loading in a truck and carrying of excavated cum 169.90
material to embankment site with a lift upto 1.5 m and lead upto 50 m as per Technical Specification Clause
302.3.5. (Manual means should be use where machines can not be deployed due to site condition)

ii Excavation in Ordinary Rock with Dozer with lead upto 100 m

Excavation for roadway in ordinary rock by deploying a dozer D-50 including cutting and pushing the cut earth cum 58.90
to site of embankment upto a distance of 100 m (average lead 50 m), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross-sections with lift upto 1.5 m.

iii Excavation in Ordinary Rock using Hydraulic Excavator and Tippers with disposal upto 1000 m

Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting cum 88.30
and loading in tippers, transporting to embankment site with a lift upto 1.5 m and lead upto 1000 m, trimming
bottom and side slopes in accordance with requirements of lines, grades and cross-sections as per Technical
Specification Clause 302.3.5

3.9 Excavation in Hard Rock (requiring blasting) with disposal upto 1000 m
I Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom cum 215.00
and side slopes in accordance with requirements of lines, grades and cross-sections, loading and disposal of
cut rock with a lift upto 1.5 m and leads upto 1000 m as per Technical Specification Clause 302.3.5

ii Excavation in Hard Rock (blasting prohibited)

Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in
tippers and disposal with a lift upto 1.5 m and lead upto 200 metres, trimming bottom and side slopes in
accordance with requirements of lines, grades and cross- sections as per Technical Specification Clause
302.3.5

A Manual Means cum 897.90

B Mechanical Means cum 447.00

iii Excavation in Hard Rock (controlled blasting) with disposal upto 1000 m
Item Unit Rate
No. (Rs.)

Excavation for roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming of cum 233.30
bottom and side slopes in accordance with requirements of lines, grades and cross-sections, loading and
disposal of cut rock with a lift upto 1.5 m and leads upto 1000 m as per Technical Specification Clause 302.3.5

3.10 Stripping, Storing and Relaying Top Soil from Right-of-Way (R.O.W) cum 171.00

Striping,storing and preservatio of top soil by keeping it damp in stock piles and keep wet till it is used by road
side at 15 M interval and reapplication on embankment slopes,cut slopes and other areas in localities where
the available embankment mate

3.11 Stripping,Storing and Relaying Top soil from Borrow areas in Agricultural fields.
Stripping of top soil from borrow areas located in agriculture fields, storing at a suitable place, spreading and cum 114.00
relaying after taking the borrow earth to maintain fertility of the agricultural field, finishing it to the required
levels to the satisfaction of the farmer/land owner as per Technical Specification Clause 302.3.2.

3.12 Turfing with Sods


Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other sqm 19.80
locations shown on the drawing or as directed by the Engineer including preparation of ground, fetching of
sods and watering as per Technical Specification Clause 309.

3.13 Seeding and Mulching


Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer, mulching sqm 93.40
material, applying bituminous emulsion @ 0.23 litre per sqm and laying and fixing jute netting, including
watering for 3 months all as per Technical Specification Clause 310.

3.14 Construction of Subgrade and Earthen Shoulders


Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts
and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of
Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.

(I) Private Land cum 286.30


(ii) Govt. land cum 286.00
3.15 Compacting Original Ground
(I) Compacting original ground supporting embankment

Loosening, Levelling and Compacting original ground supporting embankment to facilitate placement of first cum 19.80
layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling
so as to achieve minimum dry density as given in Tables 300.1 and 300.2 for embankment construction as per
Technical Specification Clause 301.4.1.

(ii) Compacting original ground supporting subgrade

Loosening of the ground upto a level of 300 mm below the subgrade level, watered, graded and compacted in cum 30.80
layers to meet requirement of Tables 300.1 and 300.2 for subgrade construction as per Technical Specification
Clause 303.5.2.

3.16 Repairs of damages caused by rain/spillage of water

Preparation and surface treatment of formation by removing mud and slurry, watering to the extent needed to sqm 1.70
maintain the desired moisture content, trimming to the required line, grade, profile and rolling with three wheel
80-100 kN static roller, complete as per Technical Specification Clause 301.5.5.1

3.17 Presplitting Rock Excavation Slopes

Carrying out excavation in hard rock to achive a specified slope of the rock face by controlled use of sqm 129.60
explosives and blasting accessories in properly aligned and spaced drill holes, collection of the excavated rock
by a D-50 dozer, loading in tipper by a front end loader and disposing of the material with a lift upto 1.5 m and
lead upto 1000 m as per Technical Specification Clause 304.3

3.18 Construction of Embankment with Flyash/Pond ash available from Coal or Lignite Burning Thermal Plants as
Waste Material
Construction of embankment with flyash conforming to Table 1 of IRC:SP:58 obtained from coal or lignite cum 197.20
burning thermal power stations as waste material, spread and compacted in layer of 200 mm thickness each
at OMC, all as specified in IRC:SP:58 and as per approved plans with lead upto 1000 m as per Technical
Specification Clause 306.

3.19 Surface Drains in Soil


Item Unit Rate
No. (Rs.)

(I) Construction of unlined surface drains of average cross-sectional area 0.40 sqm in soil to specified lines,
grades, levels and dimensions. Excavated material to be used in embankment with a lift upto 3m and lead of
50 m (average lead 25 m) as per Technical Specification Clause 307.

(A) Manual Means m 58.20


(B) Mechanical Means m 25.70
(II) Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross-sectional area 0.4 sqm in ordinary rock to specified
lines, grades, levels and dimensions as per approved design and Technical Specification Clause 307.
Excavated material to be used in embankment at site.

(A) Manual Means m 87.40

(B) Mechanical Means m 33.00

(III) Surface Drains in Hard Rock

Rate per m may be worked out based on quantity of hard rock as per design.

For rate of hard rock cutting refer releavant item in this chapter.

Note: Where lining of drain is provided,quantity shall be worked out based on approved design and drawing
and priced on rate
3.20 Chute Drains

A Providing chute drains across embankment slopes in approches of bridges and on horizontal curves as per
drawings.

(a) Earthwork in exavation for foundation of structure as per drawings and technical specification clause 307
including setting out construction of shoring and bracing deleterious matter, dressing of sides and bottom and
backfilling with approved material(

Rate as per item No. 11.1 of Chapter 11. cum


(b) Providing and laying plain cement concrete M15 grade Rate as per 12.5 of Chapter 12 cum

(c) Brick masonry in cement morter 1:5. Rate asper item no 12.1 (iii) of Chapter 12 cum

(d) Plastering with cement morter 1:4. Rate as per item no 12.3 of Chapter 12. cum
(e) Providing P.C.C. M 20 coping on the top of chute walls. As per item no 12.13 of Chapter 12. cum

B Providing chute drains across embankment slopes in approches of bridges and on horizontal curves m -
as per drawings.

(a) Earthwork in exacavation for foundation of structure as per drawing and technical specifications clause 307
including setting out construction of shoring and bracing deleterious matter, dressing of sides and backfilling
with approved material (By manual means)

Rate as per item no 11.1 of chapter 11. cum

(b) Providing and laying plain cement concrete M 15 Grade

Rate as item No.12.5 of Chapter 12. cum


(c) Coursed ruble stone masonary (2 nd sort) in cement morter 1:4

Rate as item No.12.4 II of Chapter 12. cum

(d) Plastering with cement morter 1:4

Rate as per item No. 12.3 of Chapter 12. cum

(e) Providing P.C.C. M 20 Coping on the top of chute walls


Rate as per item No. 12.13 of chapter 12 cum
Chapter 4 - GRANULAR SUB-BASES, BASES (NON-BITUMINOUS) AND SHOULDERS

4.1 Granular Sub-base with Well Graded Material (Table 400.1)


(Only for PMGSY work)
(A) By Mix in Place Method

Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor
grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with
smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401.

(I) For Grading I Material cum 1,544.80


Item Unit Rate
No. (Rs.)

(ii) For Grading II Material cum 1,466.00

(iii) For Grading III Material cum 1,373.60

4.2 Gravel/Soil-Aggregate Base (Table 400.2) Grading A


(Only for PMGSY work)
I) Construction of gravel/soil-aggregate base by providing well graded material, spreading in uniform layers cum 1,608.60
with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting
with three wheel 80-100 kN static roller to achieve the desired density, complete as per Technical
Specifications Clause 402

ii) Gravel/Soil-Aggregate Base (Table 400.2) Grading B


Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor cum 1,562.80
grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three
wheel 80-100 kN static roller capacity to achieve the desired density, complete as per Technical Specification
Clause 402

iii) Gravel/Soil-Aggregate Base (Table 400.2) Grading C cum 1,509.70

Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor
grader on prepared surface,mixing by mix in place method with rotavator at OMC, and compacting with three
wheel 80-100 KN static roller capacity to achieve the desired density,complete as per Technical specification
Clause 402.

iv) Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 80 mm (Table 2.3 of IRC SP 77-2008 cum
1107.20
Construction of Gravel/soil aggregate sub-base/Base by providing well graded material of nominal size grading
80 mm as per Table 2.3 of IRC SP 77-2008, spreading in uniform layers with tractor mount appropriate grading
arrangement on prepared surface,mixing by mix in place method at OMC with tractor mount appropriate
rotavator attachment and compaction with three wheel 80-100 Kn capacity to achieve complete as per
specification contained in para 2.2,3.6,3.7 of IRC SP 77-2008.

v) Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 40 mm (Table 2.3 of IRC SP 77-2008 cum 1059.40

Construction of Gravel/soil aggregate sub-base/Base by providing well graded material of nominal size grading
40 mm as per Table 2.3 of IRC SP 77-2008, spreading in uniform layers with tractor mount appropriate grading
arrangement on prepared surface,mixing by mix in place method at OMC with tractor mount approprite
rotavator attachment and compaction with three wheel 80-100 kn static roller capacity to achieve the desired
density complete as per specification contained in para 2.2,3.6 and 3.7 of IRC SP 77-2008

vi) Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 20 mm (Table 2.3 of IRC SP 77-2008 cum 1017.70

Construction of Gravel/soil aggregate sub-base/Base by providing well graded material of nominal size grading
40 mm as per Table 2.3 of IRC SP 77-2008, spreading in uniform layers with tractor mount appropriate grading
arrangement on prepared surface,mixing by mix in place method at OMC with tractor mount approprite
rotavator attachment and compaction with three wheel 80-100 kn static roller capacity to achieve the desired
density complete as per specification contained in para 2.2,3.6 and 3.7 of IRC SP 77-2008

vii) Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 10 mm (Table 2.3 of IRC SP 77-2008

Construction of Gravel/Soil aggregrete Base/Surface by providing well graded material of nominal maximum cum 931.50
size grading 10 mm as per Table 2.3 of IRC SP 77-2008,spreading in uniform layers with tractor mount
appropriate grading arrangement on prepared surface,mixing by mix in place method at OMC with tractor
mount appropriate rotavator attachment and compaction with three wheel 80-100kn static roller capacity to
achieve the desired density complete as per specifications contained in para 2.2,3.6 and 3.7 of IRC SP 77-
2008.

viii) Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 5 mm (Table 2.3 of IRC SP 77-2008

Construction of Gravel/Soil aggregrete Base/Surface by providing well graded material of nominal maximum cum 889.80
size grading 5 mm as per Table 2.3 of IRC SP 77-2008, spreading in uniform layers with tractor mount
appropriate grading arrangement opn prepared surface,mixing by mix in place method at OMc with tractor
mount appropriate rotavator attachment compacted with three wheel 80-100kn static roller capacity to achieve
the desired density complete asper para 2.2,3.6 and 3.7 of IRC SP 77-2008.

4.3 Gravel/Soil-Aggregregate surface course (table 400.3)


(Only for PMGSY work)
Item Unit Rate
No. (Rs.)

I Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor cum 1,278.40
grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three
wheel 80-100 kN static roller capacity to achieve the desired density, complete as per Technical Specification
Clause 402

4.4 Lime Stabilisation for Improving Subgrade

Laying and spreading available soil in the subgrade on a prepared surface, pulverising, mixing the spread soil
in place with rotavator with 2 per cent slaked lime having minimum 70 per cent of contents of CaO, grading
with motor grader and compacting with the smooth wheel road roller at OMC to the desired density to form a
layer of improved Sub-grade as per Technical Specification Cluase 403.

(A) By Manual Means cum 356.40

(B) By Mechanical Means cum 321.40

4.5 Lime Treated Soil for Sub-Base

Providing, laying and spreading soil on a prepared sub-grade, pulverising, mixing the spread soil in place with cum 584.50
rotavator with 4 per cent slaked lime with minimum content of 70 per cent of CaO, grading with motor grader
and compacting with the road roller at OMC to achieve atleast 98 per cent of the max dry density to form a
layer of sub-base as per Technical Specification Clause 403.

4.6 Cement Treated Soil Sub-Base/Base

Providing, laying and spreading soil on a prepared sub-grade, pulverising, adding the designed quantity of
cement to the spread soil, mixing in place with rotavator, grading with the motor grader and compacting with
the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-
base/base as per Technical Specification Clause 404.

For 4 per cent quantity of cement by weight of soil cum 628.40

4.7 Water Bound Macadam Sub-base/base


(Only for PMGSY work)
1) WBM Grading 1
Using stone screening Type-A 13.2 mm for Gr.I
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static
roller in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-
up the interstices of coarse aggregate, watering and compacting to the required density Grading 1 as per
Technical Specification Clause 404.

(A) By Manual Means cum 2,580.30

(B) By Mechanical Means cum 2,625.50

2) WBM Grading 2
Using stone screening Type-B 11.2 mm for Gr.II
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100
kN in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-up
the interstices of coarse aggregate, watering and compacting to the required density grading 2 as per
Technical Specification Clause 405.

(A) By Manual Means cum 2,732.70

(B) By Mechanical Means cum 2,455.60

3) WBM Grading 3
Using stone screening Type-B 11.2 mm for Gr.III
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100
kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of
coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification
Clause 405.

(A) By Manual Means cum 2,764.60

(B) By Mechanical Means cum 2,581.10

4.8 Water Bound Macadam with Crushable Screenings


(Only for PMGSY work)
Item Unit Rate
No. (Rs.)

1) WBM Grading 1
Using crushable screening such as moorum gravel for Gr.I
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static
roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the
interstices of coarse aggregate, watering and compacting to the required density Grading 1 as per Technical
Specification Clause 405.

A) By Manual Means cum 2,427.10


B) By Mechanical Means cum 2,155.40
2) WBM Grading 2
Using crushable screening such as moorum gravel for Gr.II
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static
roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the
interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical
Specification Clause 405.

(A) By Manual Means cum 2,414.20

(B) By Mechanical Means cum 2,233.80

3) WBM Grading 3

Using crushable screening such as moorum gravel for Gr.III


Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static
roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the
interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical
Specification Clause 405.

(A) By Manual Means cum 2,523.00

(B) By Mechanical Means cum 2,301.70

4.9 Wet Mix Macadam

Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification
including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material
by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and
compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting,
barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification
Clause 406.

By Mechanical Means with 1 km lead cum 2,113.70

4.10 Construction of Shoulders as per Technical Specification Clause 407.

A Earthen Shoulders

The rate as applicable for sub-grade construction may be adopted.

B Hard Shoulders

Rate as applicable for sub-base and/or base may be adopted as per approved design.

C Paved Shoulders

The rates may be adopted as applicable for different layers of pavement depending upon approved design of
paved shoulders.

4.11 Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method
normal Construction of granular sub-base by providing local material spreading in uniform layers with
motor grader on prepared surface, mixing by mix in place method with rotavator at once and
compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as
per Technical Specification Clause 408.

I Using naturally occuring gravel cum 630.20


ii Using Gravel mix soil using cum 477.50
4.12 Construction of Water Bound Macadam using locally available material (Table 400.13)
Item Unit Rate
No. (Rs.)

Providing, laying spreading and compacting local material in block or large discrete particles, such as kankar, cum 1,117.00
Laterite, Dhandla etc. as per Table 400.13 to water bound macadam specification including spreading in
uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and
camber, applying and brooming requisite type of screening /binding materials to fill-up the interstices of laid
material watering and compacting to the required density as per Clause 405.3 and Technical Specification
Cluase 408.

4.13 Lime-Flyash Stablised Soil Sub-base


Construction of sub-base using lime-flyash admixture with granular soil, free from organic matter/deleterious
material or clayey silts and low plasticity clays having PI between 5 and 20 and liquid limit less than 25 and
commercial dry lime, slaked at site or pre-slaked with CaO content not less than 50 per cent, flyash to conform
to gradation as per Clause 4.3 of IRC:SP:20, lime+flyash content ranging between 10 to 30 per cent, the
minimum un-confined compressive strength and CBR value after 28-days curing and 4-days soaking to be
0.75 MPa and 25 per cent respectively, all as specified in IRC:88 including a lead upto 1000 m as per
Technical Specification Cluase 409.

(A) For earth taken from Private source cum 522.00

(B) For earth taken from Govt.Land cum 522.00

4.14 Construction of Sub-base/Course Using Crushed Slag as per Table 400.19

Construction of Sub-base by providing crushed slag spreading in uniform layer with motor grader on prepared cum 910.00
surface mixing by mix-in-place method with Rotavator @ OMC, and compacting with three wheel 80-100 kN
static roller to achieve the desired density complete as per Technical Specifications Cluase 402.4 and 410.3.2

4.15 Water Bound Macadam using crushed slag


Providing, laying, spreading and compacting crushed slag to water Bound Macadam specification including cum 1,212.60
spreading in uniform thickness, hand packing rolling with smooth wheel roller 80-100 kN in stages to proper
grade and camber, applying and brooming requisite type of screening/binding materials to fill up the interstees
of crushed slag watering and compacting to the required density as per Clause 405.3 and Technical
Specification Cluase 410.3.2.

4.16 Cement Bound Granular Material sub-base/base


Providing laying and spreading granulated blast furnace slag on a prepared sub-grade pulverising adding the cum 665.50
designed quantitity of cement to the spread granulated blast furnace slag mixing in place with rotavator
grading with the mortar grader and compacting with smooth wheel roller 80-100 kN at OMC to achieve the
desired unconfined compressive strength and to form a layer of sub-base/base as per Technical Specification
Clauses 404.3 and 410.4.2.

4.17 Crusher Run Macadam Base


Providing crushed run stone aggregate greading conforming to table 400.20 depositing on a prepared surface
by hauling vehicles, spreading and mixing with a motor grader, watering and compacting with a three wheel
80-100 kN static roller as per Technical Specification Clause 411 to form a layer of sub-base/base

A) By mix-in-place method

I With 53 mm maximum size of aggregates cum 2,189.10

ii With 37.5 mm maximum size of aggregates cum 1,980.20

(B) By mixing plant method

I With 53 mm maximum size of aggregates cum 2,413.90

ii With 37.5 mm maximum size of aggregates cum 2,054.70

4.18 Brick Soling


Laying brick soling layer on prepared sub-grade with brick on end edging according to lines, graded and cross- sqm 631.70
section shown on the drawing filling joints with sand and earth, spreading 25 mm thick layer of earth over brick
soling, watering and rolliing the same with three wheel road roller 80-100 kN as per Technical Specification
Clause 412

4.19 Stone Set Pavement


Providing and laying stone set pavement on prepared surface with sub-base 100 mm thick compacted sqm 786.70
Granular Sub-base as per Clause 401.4 and base 75 mm thick compacted water bound macadam grading 2
as per Clause 405.3. The 150 mm thick hammer desired stones are laid in the herring one or stretched bond
pattern. The stones are compacted into the bedding sand of 40 mm over the WBM base bounded by edge
stone using suitable compacting device. The gaps are filled with fine sand stone dust as per Technical
Specification Clause 413.4

Chapter 5 - BASES AND SURFACE COURSES (BITUMINOUS)

5.1 Prime Coat


Item Unit Rate
No. (Rs.)

I) Low porosity
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base sqm 27.90
including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means
as per Technical Specification Clause 502

ii) Medium porosity


Providing and applying primer coat with Bitumen emulsion (SS-1) on prepared surface of granular base sqm 34.20
including cleaning of road surface and spraying primer at the rate of 0.90- 1.2 kg/sqm using mechanical means
as per Technical Specification Clause 502.

iii) High porosity

Providing and applying primer coat with Bitumen emulsion (SS-1) on prepared surface of granular base sqm 43.80
including cleaning of road surface and spraying primer at the rate of 1.2-1.5 kg/sqm using mechanical means
as per Technical Specification Clause 502.

5.2 Tack Coat


I) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to sqm 8.60
0.25 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical
Specification Clause 503.

ii) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 sqm 10.20
to 0.30 kg per sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per
Technical Specification Clause 503.

iii) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 sqm 10.20
to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as
per Technical Specification Clause 503.

iv) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion pressure distributor at the rate sqm 11.80
of 0.30 to 0.35 kg per sqm on the prepared non-bituminous surfaces (cement concrete pavement) cleaned
with Hydraulic broom as per Technical Specification Clause 503.

5.3 Bituminous Macadam

(i) Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per cum 7,257.90
Table 500.4 premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously
prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the
desired compaction as per Technical Specification Clause 504.

(ii) Providing and laying Cold Mix bituminous macadam with Drum mix plant using crushed aggregates of grading cum 9,132.70
as per Table 500.4 premixed with Cold mix binder, transported to site upto a lead of 1000 m laid over a
previously prepared surface with paver finisher to the required grade, level and alignment and rolled to
achieve the desired compaction as per Technical Specification (IRC:SP:100-2014).

5.4 Built-Up Spray Grout


Providing, laying and rolling of built-up spray grout layer over prepared base consisting of a two layer
composite construction of crushed coarse aggregates using motor grader for aggregates. Key stone chips
spreader may be used with application of bituminous binder after each layer, and with key aggregates placed
on top of the second layer to serve as a base, conforming to the line, grades and cross-section specified, the
compacted layer thickness being 75 mm as per Technical Specification Clause 505.

A By Manual Means

I Bitumen (S-90) sqm 359.50

ii Bitumen (S-65) sqm 362.70

B By Mechanical Means(S90) sqm 303.10

5.5 Modified Penetration Macadam


Construction of penetration macadam over prepared base by providing a layer of compacted crushed coarse
aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and
rolling with a three wheel 80-100 kN static roller to achieve the desired degree of compaction as per Technical
Specification Clause 506.

A 50 mm thick
I) Bitumen (S-90) sqm 220.80
Item Unit Rate
No. (Rs.)

B 75 mm thick

I) Bitumen (S-90) sqm 284.30

ii) Bitumen (S-65) sqm 286.50

5.6 Surface Dressing using Bituminous (Penetrations grade / modified bitumen) Binder

Providing and laying surface dressing as wearing course consisting of a layer of bituminous binder laid on the
prepared surface, followed by a cover of crushed stone aggregates of specified size and rolling with three
wheel 80-100 kN static roller including cleaning the road surface as per Technical Specification Clause 507.

A By Manual Means

Case – I: Nominal chipping size 13.2 mm

I) Bitumen (S-90) sqm 89.90

ii) Bitumen (S-65) sqm 91.00

iii) Polymer Modified Bitumen sqm 83.20

iv) Crumb Rubber Modified Bitumen sqm 87.20

Case – II: Nominal chipping size 9.5 mm

I) Bitumen (S-90) sqm 78.30

ii) Bitumen (S-65) sqm 79.30

iii) Polymer Modified Bitumen sqm 72.00

iv) Crumb Rubber Modified Bitumen sqm 75.90

B By Mechanical Means

Case – I: Nominal chipping size 13.2 mm

I) Bitumen (S-90) sqm 72.40

ii) Bitumen (S-65) sqm 69.70

iii) Polymer Modified Bitumen sqm 61.90

iv) Crumb Rubber Modified Bitumen sqm 65.90

Case – II: Nominal chipping size 9.5 mm

I) Bitumen (S-90) sqm 60.50

ii) Bitumen (S-65) sqm 61.50

iii) Polymer Modified Bitumen sqm 54.50

iv) Crumb Rubber Modified Bitumen sqm 58.10


5.7 Surface Dressing using Bitumen Emulsion

Providing and laying surface dressing as wearing course consisting of a layer of bitumen emulsion laid on the
prepared surface, followed by a cover of crushed stone chippings of specified size and rolling with 80-100 kN
roller including cleaning the road surface as per Technical Specification Clause 507.

A By Manual Means

Case – I: Nominal aggregate size 13.2 mm sqm 88.30

Case – II: Nominal chipping size 9.5 mm sqm 78.80

B By Mechanical Means

Case – I: Nominal chipping size 13.2 mm sqm 72.60

Case – II: Nominal chipping size 9.5 mm sqm 65.60

5.8 Pre-coating Chips


Item Unit Rate
No. (Rs.)

Pre-coating of chips with 1 per cent of paving bitumen by weight of chips in a suitable mixer duly heated to 160
degree C as per Technical Specification Clause 507.2.5

I) Bitumen (S-90) cum 1,700.80

ii) Bitumen (S-65) cum 1,718.00

5.9 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade/modified bitumen)
Binder

Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6
mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve
as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a
three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of
either Type A or Type B or Type C as per Technical Specification Clause 508.

Case - I By Manual Means

I) Bitumen (S-90) sqm 165.80

ii) Bitumen (S-65) sqm 164.70

iii) Polymer Modified Bitumen sqm 153.30

iv) Crumb Rubber Modified Bitumen sqm 158.60

Case - II By Mechanical Means

I) Bitumen (S-90) sqm 132.80

ii) Bitumen (S-65) sqm 134.40

iii) Polymer Modified Bitumen sqm 123.10

iv) Crumb Rubber Modified Bitumen sqm 128.90

5.10 20mm thick Open-Graded Premix Carpet using Bitumen Emulsion as per Technical Specification sqm 125.00
clause 508.2

Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm
to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and
level to serve as wearing course on a previously prepared base, including mixing in a suitable plant,
laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and
grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification
Clause 508.

(ii) Using Cold mix Binder (Tailor made as per IRC:SP:100-2014) sqm 161.00

5.11 Mix Seal Surfacing

Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2
mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration grade bitumen to
required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a
suitable plant, laying and rolling with a three wheel 8-10 kN static roller and finishing to required level and
grades as per Technical Specification Clause 509

By Manual Means
Type A
I) Bitumen (S-90) sqm 218.30
ii) Bitumen (S-65) sqm 220.70
iii) Polymer Modified Bitumen sqm 203.60
iv) Crumb Rubber Modified Bitumen sqm 212.40
(v) Using Cold mix Binder (Tailor made as per IRC:SP:100-2014) sqm 227.40

Type B
I) Bitumen (S-90) sqm 205.20
ii) Bitumen (S-65) sqm 207.30
iii) Polymer Modified Bitumen sqm 192.50
iv) Crumb Rubber Modified Bitumen sqm 200.10
Item Unit Rate
No. (Rs.)

(v) Using Cold mix Binder (Tailor made as per IRC:SP:100-2014) sqm 213.10

By Mechanical Means

Type A

I) Bitumen (S-90) sqm 165.50

ii) Bitumen (S-65) sqm 167.90

iii) Polymer Modified Bitumen sqm 150.80

iv) Crumb Rubber Modified Bitumen sqm 159.60

Type B

I) Bitumen (S-90) sqm 152.50

ii) Bitumen (S-65) sqm 154.50

iii) Polymer Modified Bitumen sqm 139.70

iv) Crumb Rubber Modified Bitumen sqm 147.30

5.12 Seal Coat

Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and
cross fall using Type A, Type B and Type C as per Technical Specification Clause 510

A By Manual Means

Case - I : Type A

I) Bitumen (S-90) sqm 68.00

ii) Bitumen (S-65) sqm 69.00

iii) Polymer Modified Bitumen sqm 61.40

iv) Crumb Rubber Modified Bitumen sqm 65.30

Case - II : Type B

I) Bitumen (S-90) sqm 50.10

ii) Bitumen (S-65) sqm 50.30

iii) Polymer Modified Bitumen sqm 45.00

iv) Crumb Rubber Modified Bitumen sqm 52.80

Case - III : Type C

I) Bitumen (S-90) sqm 60.60

ii) Bitumen (S-65) sqm 61.30

iii0 Polymer Modified Bitumen sqm 55.90

iv) Crumb Rubber Modified Bitumen sqm 58.80

B. By Mechanical Means

Case - I : Type A

I) Bitumen (S-90) sqm 64.80

ii) Bitumen (S-65) sqm 65.80

iii) Polymer Modified Bitumen sqm 58.20

iv) Crumb Rubber Modified Bitumen sqm 62.10


Item Unit Rate
No. (Rs.)

Case - II : Type B

I) Bitumen (S-90) sqm 42.30

ii) Bitumen (S-65) sqm 43.00

iii) Polymer Modified Bitumen sqm 37.70

iv) Crumb Rubber Modified Bitumen sqm 42.90

Case - III : Type C

I) Bitumen (S-90) sqm 53.40

ii) Bitumen (S-65) sqm 54.10

iii) Polymer Modified Bitumen sqm 49.00

iv) Crumb Rubber Modified Bitumen sqm 51.60

Competitive market rates to be ascertained. Alternatively, rates for stone crushing given in Chapter 1 may be
adopted, if found economical. In case for supply of aggregates at site are not available, nearest crusher site
may be ascertained. Loading and unloading charges and cost of carriage may be added to these rates to
arrive at the cost at site.

Chapter 6 - CEMENT CONCRETE PAVEMENT


6.1 Granual Sub-base

Rate as per item No.4.1 of Chapter 4

6.2 Lime Treated Soil

Rate as per item No.4.5 of Chapter 4


6.3 Water Bound Macadam (WBM) - Sub-base

(A) By Manual Means

As per item No.4.7 of Chapter 4

(B) By Mechnical Means

As per item No.4.7 of Chapter 4

6.4 Cement concrete pavement

Construction of un reinforced, dowel jointed at expansion and construction joint only,plain cement concrete cum 6,150.20
pavement, thickness as per design,over a prepared sub base,with 43 grade cement or any other type as per
clause 1501.2.2 M30 grade ,coarse and fine aggregrette conforming to is:383,maximum size of coarse
aggregate not exceeding 25 mm,mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate
weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel,laying and fixing
of 125 micron thick polythene film,wedges,steel plates including levelling the formwork as per drawing)
spreading the concrete with shovels,rakes,compacted using needle,screed and plate vibrator and finished in
continuous operation including provision of contraction and expansion,construction joints,applying debonding
strips,primer,sealant,dowelbars,near approaches to bridge/culverts and construction joints,admixture as
approved,curingof concrete slabs for 14 days.

6.5 Roller Compacted Concrete Pavement

Construction of Roller Compacted Concrete Pavement (RCCP) with coarse and fine aggregates conforming to cum 5,453.80
IS:383, the size of coarse aggregate not exceeding 25 mm with minimum aggregate cement ratio of 5:1 mm
and with minimum cemnt content of 310 kg per cum, aggregate gradation to be as per Table 602.2 after
blending, mixing in concrete mixer at optimum moisture content, transporting to site, laying with wheel barrows
or steel pans or with mechanical paver, compacting with 80-100 kN smooth wheel, tandem vibratory roller, to
achieve, the designed flexural strength, finishing and curing as per drawings and Technical Specification
Clause 1502

Note: Carraige of c.c block to site of is payable seperately as per chapter of carriage of materials from
manufacturing site to the site of work

6.6 Rectangular Concrete Block Pavement


Item Unit Rate
No. (Rs.)

Manufacturing, laying of cement concrete blocks of size 0.450 m x 0.300 m x 0.15 m of Cement Concrete sqm 1,987.90
(C.C.) M30 garde and spreading 25 mm thick sand under neath and filling joints with sand on existing W.B.M.
base as per Technical Specification Clause 1503.

6.7 Inter locking concrete Block pavement

(A) Interlocking pavement block

(i) Providing and laying interlocking concrete block pavement (M40) having thickness 80mm as per technical
specification clause 1504 complete including carriage.

a) Including Edge block/ Edge restraints sqm 918.70

b) Excluding Edge block/ Edge restraints sqm 723.60

(ii) Providing and laying interlocking concrete block pavement (M40) having thickness 60mm as per technical
specification clause 1504 complete including carriage.

a) Including Edge block/ Edge restraints sqm 743.50

b) Excluding Edge block/ Edge restraints sqm 548.40

(B) Interlocking Edge block/ Edge restraints

(i) Providing and laying Concrete Edge block/ Edge restraints (M40 Grade) of size 300mm x 300mm x 150mm no 109.50
including carriage complete as per Technical specification clause 1504.

Note: i. The rates for sub-grade, sub-base course to be measured and paid separately (as per Chapter 3 & 4)

Chapter 7 - CAUSEWAY AND SUBMERSIBLE BRIDGES

7.1 Construction of Cut-off Walls/Head Walls

I Earthwork in excavation for structures as per drawing and technical specification Clause 305.

Rate as per item No.11.1 of Chapter 11 cum


ii Plain cement concrete M15 grade
Rate as per item No.11.4 (ii) of Chapter 11 cum
iii) Brick masonry in cement mortar 1:4
Rate as per item No.11.5 (ii) of Chapter 11 cum
iv) Stone masonry in cement mortar 1:4
Rate as per item No.11.6 (ii) of Chapter 11 cum
v Providing P.C.C M20 architectural coping on top of wall
Rate as per item No.12.13 of Chapter 12 m
7.2 Preparation of Subgrade
Rate as per item No.3.15 of Chapter 3 cum
7.3 Granular Sub-base
Rate as per item No.4.1 of Chapter 4 cum
7.4 W.B.M. Base Course
Rate as per item No.4.7 of Chapter 4 cum
7.5 Cement Concrete Slab
Rate as per item No.6.4 of Chapter 6 cum 6,150.20
7.6 Providing and Laying Apron with Stone Boulders as per Drawings & Technical Specification Clause
1301

Rate as per item No.14.1 of Chapter 14 cum

ii Providing and Laying of Boulder Apron Laid in Wire Crates as per Drawing and Technnical Specification
Clause 1301
Rate as per item No.14.2 of Chapter 14 cum
iii) Providing and Laying of Apron with Cement Concrete Blocks as per Drawing and Technical Specification
Clause 1301

Rate as per item No.14.3 of Chapter 14 cum


Item Unit Rate
No. (Rs.)

7.7 Guide Posts

Construction of R.C.C. guide posts of 250 mm dia, M25 grade as per drawing and technical specification
Clause 1401.6

Rate as per item No.8.8 of Chapter 8 cum

7.8 Bedding for Causeway

I Type A (concrete cradle) Bedding Clause 1402.5

As per item No.9.2 of Chapter 9 cum

ii Type B (first class) Bedding Clause 1402.5

As per item No.9.2 of Chapter 9 cum

7.9 Laying Reinforced Cement Concrete Pipe NP3 as per drawing and technical specification Clause 1402.6

As per item No.9.3 of Chapter 9 m

7.10 Laying Reinforced Cement Concrete Pipe NP4 as per technical specification Clause 1402.6

As per item No.9.4 of Chapter 9 m

Chapter 8 - HILL ROADS

8.1 Site Clearance


8.2 Setting Out
1) Construction of reference pillars as per Fig. 1600.1 (b) as per drawing and Technical Specification Clause per Km 5,879.20
1602.1

2) Construction of back piller as per Fig. 1600.1( c) as per drawing and Technical Specification Clause 1602.3 per Km 13,985.80

3) Construction of Job pillers as per Fig. 1600.1 (d) and Technical Specification Clause 1602.4 each 550.50

8.3 Earthwork in Hill Road


I) Excavation in Hilly Areas in Soil by manual means.
A) Excavation in soil in Hilly Area by manual means including cutting and trimming of side slopes and disposing of cum 145.60
excavated earth with a lift upto 1.5 m and a lead upto 20 m as per drawing and Technical Specification Clause
1603.1 (Manual means should be use where machines can not be deployed due to site condition)

B) Extra for Every Additional Lift of 1.5 m or Part thereof cum 15.10
ii) Excavation in Hilly Areas in Soil by mechanical means
A) Excavation in soil in Hilly Area by mechanical means including cutting and trimming of side slopes and cum 94.80
disposing of excavated earth with a lift upto 1.5 m and a lead upto 20 m as per Technical Specification Clause
1603.1

B) Extra for Every Additional Lift of 1.5 m or Part thereof cum 15.10
iii) Excavation in Hilly Area in Ordinary Rock by manual means

A) Excavation in ordinary rock using manual means including loading in a truck and carrying of excavated cum 320.30
material to embankment site with a lift upto 1.5 m and lead upto 20 m as per Clause 1603.2. (Manual means
should be use where machines can not be deployed due to site condition)

B) Extra for Every Additional Lift of 1.5 m or Part thereof cum 23.70

iv) Excavation in Hilly Areas in Ordinary Rock by mechanical means not requiring blasting

A) Excavation in hilly area in ordinary rock not requiring blasting by mechanical means including cutting and cum 146.80
trimming of slopes and disposal of cut material with a lift upto 1.5 m and lead upto 20 m as per Clause 1603.2.

v) Excavation in Hilly Areas in Hard Rock requiring blasting


A) Excavation in hilly areas in hard rock requiring blasting, by mechanical means, lift upto 1.5 m and disposal of cum 323.20
excavated rock upto a lead of 20 m as per Clause 1603.2.

B) Extra for Every Additional Lift of 1.5 m or Part thereof cum 29.70

vi) Excavation in Hard Rock (blasting prohibited)


Item Unit Rate
No. (Rs.)

Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in
tippers and disposal with a lift upto 1.5 m and lead upto 200 metres, trimming bottom and side slopes in
accordance with requirements of lines, grades and cross- sections as per Technical Specification Clause
302.3.5

a) Manual Means cum 830.00


b) Mechanical Means cum 496.20
8.4 Retaining Walls / Breast Walls
Construction of retaining walls/breast walls in cement mortar 1:5 as per drawing and technical specifications
Clause 1604

I) Earthwork in excavation for structures


Rate as per item No.11.1 of Chapter 11 cum
ii) Plain cement concrete M 10 grade
Rate as per item No.11.4 of Chapter 11 cum
iii) Stone masonry in cement mortar 1:5
Rate as per item No. 12.4 (III) (iii) of Chapter 12 cum
iv) Pointing with cement mortar 1:3
Rate as per item No.12.2 of Chapter 12 sqm
v) Providing P.C.C. M 20 architectural coping on top of retaining wall/breast wall
Rate as per item No.12.13 of Chapter 12 m
vi) Filter material behind retaining wall / breast wall as per Specification 1204.3.8 in a width of 600 m

Rate as per item No. 12.11 of Chapter 12 cum

vii) Back filling behind retaining wall/breast wall


Rate as per item No. 12.10 of Chapter 12 cum
0
8.5 Construction of Hill side Drain
0
Construction of Hill side drain in accordance with the requrement of
of specification true to lines and grades. Dimensions and other particulars as per drawing and technical
specification. Clause 1606.1

I) Earthwork in excavation for structures as per drawing and technical specification.

Rate as per item no 11.1 of chapter 11 cum

ii) Plain cement concrete M10 grade

Rate as per item no 11.4of chapter 11 cum

iii) Stone masonary in cement morter 1:5

Rate as per item no 12.4(iii) (iii) of chapter 12 cum

(iv) Plain cement concrete M15 grade

Rate as per item 11.4 of chapter 11 cum

(v) Cement plaster 15 mm thick 1:4 on stone masonary

Rate as per item no 12.3 of chapter 12 cum

(vi) Providing P.C.C. M 20 Architectural coping on top of wall


Rate as per item no.12.13 of chapter 12 cum
Rate per m length (I+II+III+IV+V+VI) m
Note: 0
1.Quantities of material/work shall be as per Design and Drawing.
0
2.Earth work in excavation may be taken as per site conditions.
It may coprise of a number of sub-items depending upon the type
typy of soil/rock.
0
8.6 Construction of catch water/Intercepting drain.
0
Construction of catch water/Intercepting drain in Random ruble masonary in 1:5 cement morter true to the
specified lines grades lavel and dimensions as per the requirements of the specification Clause 1606.2

Unit=1M
Item Unit Rate
No. (Rs.)

0
I) Earthwork in excavation for structure as per drawing and technical specificatuion

Rate as per item no 11.2 of chapter 11 cum


0
ii) Plain cement concrete M10 grade
Rate as per 11.4 of chapter 11. cum
iii) Stone masonary in cement morter 1:5
Rateas per item no 12.4 (III) (iii) of chapter 12 cum
iv) Plain cement cioncrete M 15 grade
Rate as per 11.4 of chapter 11. cum
v) Cement plaster 15 mm thick 1:4 on stone masonary
Rate as per 12.3 of chapter 12. sqm
vi) Providing P.C.C. M20 architectural coping on top of wall
Rate as per item No. 12.3 of chapter 12 cum
0
Note: 1. Quantities of material/work shall beas per design and drawings.
2. Earth work in excavation may be taken as per site condition.It may comprise of a number of sub-items
depending upon the type of soil/rock encountered.
0
8.7 Construction of Scupper

Construction of scupper with dry stone masonry as per drawing and technical specifications as per Clause Running m 30,257.00
1606.5.

8.8 Construction of RCC guide posts of 250 mm dia M15 grade cast-in-situ with 20 mm nominal size
aggregate, true to line and grade, tolerance of vertical RCC posts not to exceed 1 in 500 as per drawing
and Technical Specification Clause 1608.2

I) Earth work in excavation for structures

Rates as per item No. 11.1 of Chapter 11 cum

ii) RCC M15 grade


Rate as per item No. 11.4 of Chapter 11 cum
iii) HYSD steel bars

Rate as per item No. 12.6 of Chapter 12 t


iv) Painting two coats including prime coat on new concrete surface

Rate as per item No.10.5 of Chapter 10 sqm


8.9 Providing edge stones on valley side of formation as per drawing and Technical Specification Clause 1608.2.6 m 263.30

8.10 Turfing with Sods

Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other sqm 20.90
locations shown on the drawing or as directed by the Engineer including preparation of ground, stacking the
sods and watering as per Clause 309
8.11 Seeding and Mulching

Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer, multching sqm 271.10
material, applying bituminous emulsion at the rate of 0.23 l per sqm and laying and fixing jute netting, including
watering for 3 months all as per Clause 310.

Chapter 9 - PIPE CULVERTS

9.1 Excavation for Structures

Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and technical specification
Clause 1104 includding setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and backfilling with approved material.

Rate as per item No.11.1 of Chapter 11 cum 102.00

9.2 Bedding of pipe


(A) Type A (Concrete Cradle) Bedding

i) Laying concrete cradle bedding with M15 Grade Cement Concrete as per Clause 1105 (i)

Rate as per Item No.11.4 (II)(i) of Chapter 11 cum 5,085.60

(B) Type B (First Class) Bedding


Item Unit Rate
No. (Rs.)

Laying (First Class) bedding on well compacted sand, moorum as per Clause 1105 (ii)

i) Laying (First Class) bedding on well compacted sand, moorum as per Clause 1105 (ii) cum 1,129.00

ii) Laying (First Class) bedding on well compacted approved granular material as per Clause 1105 (ii) cum 1,369.05

9.3 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row

Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular
material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and parapets Clause 1106.

1200 mm dia m 9,864.70


1000 mm dia m 6,880.50

600 mm dia m 2,886.80


9.4 Providing and Laying Reinforced Cement Concrete Pipe NP4 as per design in Single Row

Providing and laying reinforced cement concrete pipe NP4 for culverts on first class bedding of granular
material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and parapets Clause 1106.

1200 mm dia m 11,889.70


9.5 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per Design in Double Row

Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular
material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head walls and parapets as per Clause 1106.

A) 1200 mm dia m 19,791.60

B) 1000 mm dia m 14,560.10

9.6 Providing and Laying Reinforced Cement Concrete Pipe NP4 as per Design in Double Row

Providing and laying reinforced cement concrete pipe NP4 for culverts on first class bedding of granular
material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head walls and parapets as per Clause 1106.

A) 1200 mm dia m 23,841.60

B) 1000 mm dia m 19,597.90

9.7 Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course below open foundation of Head walls as
per drawings & Technical Specification Clause 1109

Rate as per item No.11.4 of Chapter 11 cum

9.8 Brick Masonry Work in cement mortar in foundation of Head walls complete exculding pointing and plastering
as per drawing and technical specification Clause 1109

A Brick Masonry in 1:4 cement mortar

Rate as per item No.11.5 (ii) Chapter 11 cum

B In cement-lime mortar (1:0.5:4.5)

Rate as per item No.11.5 (iii) Chapter 11 cum

9.9 Stone Masonry Work in cement mortar in foundation of Head walls complete as per drawing and technical
specification Clasue 1109

A In 1:4 cement mortar

Rate as per item No.11.6 (II) (ii) Chapter 11 cum

B In cement-lime mortar (1:0.5:4.5)

Rate as per item No.11.6 (II) (iii) Chapter 11 cum


Item Unit Rate
No. (Rs.)

9.10 Pointing with Cement Mortar (1:3) on brickwork as per technical specification Clause 613.3

Rate as per item No.12.2 of Chapter 12 sqm


9.11 Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in substructure as per technical
specification

Rate as per item No.12.3 of Chapter 12 sqm


9.12 Backfilling in Foundation Trenches as per drawing and technical specification Clause 1108

Rate as per Item No.11.2 of Chapter 11 cum


9.13 Providing PCC M20 Architectural Coping on the top of wing wall, return wall etc. complete as per
drawing and technical specification Clause 615

Rate as per Item No.12.13 of Chapter 12 m


Chapter 10 - TRAFFIC SIGNS, MARKINGS AND OTHER ROAD APPURTENANCES

10.1 Printing New Letters and Figures of any Shade

Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to
give an even shade as per drawings and Technical Specification Clause 1701

I Hindi (Matras commas and the like not to be measured and paid for. Half letters shall be counted as half only) per cm height 0.92
per letter

ii English and Roman per cm height 0.59


per letter

10.2 Traffic Signs

A Retro-reflectorised Traffic Signs

I Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick
supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of
properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below
ground level as per drawings and Technical Specification Clause 801

i 900mm equilateral triangle each 5,541.40

ii 600mm equilateral triangle each 3,723.40

iii 600mm circular each 4,913.60

iv 800mm x 600mm rectangular each 6,759.70

v 600mm x 450mm rectangular each 4,791.70

vi 600mm x 600mm square each 5,635.10

vii 900mm side octagon each 8,559.00

II Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 1.5 mm thick
supported on GI pipe 50 mm dia firmly fixed to the ground by means of properly designed foundation with M-
15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and
Technical Specification Clause 1701

i 900mm equilateral triangle each 5,607.50

ii 600mm equilateral triangle each 3,789.50

iii 600mm circular each 4,979.60

iv 800mm x 600mm rectangular each 6,825.80

v 600mm x 450mm rectangular each 4,857.80

vi 600mm x 600mm square each 5,701.20


Item Unit Rate
No. (Rs.)

vii 900mm side octagon each 9,562.20

III Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 1.5 mm thick
supported on RCC Post 100 mm x 100 mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per
approved drawing Clause 1701

i 900mm equilateral triangle each 4,755.40

ii 600mm equilateral triangle each 2,937.30

iii 600mm circular each 4,127.50

iv 800mm x 600mm rectangular each 5,973.60

v 600mm x 450mm rectangular each 4,005.70

vi 600mm x 600mm square each 4,849.10

vii 900mm side octagon each 7,772.90

Please ensure that area of aluminium plate of required size is entered in the analysis item

(B) Semi Reflective Traffic Signs


I Providing and fixing of semi reflective cautionary, mandatory and informatory sign board as per IRC:67 made
of 1.5 mm thick MS Sheet duly stove white colour in front and gray colour on back with red reflective border of
65 mm width and required letters and figures with reflective tape engineering grade as per Clause 1701.3.9 of
MORD for Rural Roads of required shade and colour supported and welded on 47mm x 47 mm x 12 SWG
sheet tube firmly fixed to the ground by mean of properly designed foundations with M-15 grade cement
concrete 450x450x600 mm, 600 mm below ground level as per approved drawing Clause 1701.2.2

i 900mm equilateral triangle each 4,265.00

ii 600mm equilateral triangle each 2,957.20

iii 600mm circular each 3,813.30

iv 800mm x 600mm rectangular each 5,141.30

v 600mm x 450mm rectangular each 3,725.70

vi 600mm x 600mm square each 4,332.40

vii 900mm side octagon each 7,109.70

10.3 Direction and Place Identification signs upto 0.9 sqm size board

A Retro-reflectorised Traffic Signs


(I) Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of sqm 12,165.20
encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick
with area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed
to the ground by means of properly designed foundation with M-15 grade cement concrete 450 x 450 x 600
mm, 600 mm below ground level as per approved drawing and Technical Specification Clause 1701

(ii) Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of sqm 11,231.20
encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick
with area not exceeding 0.9 sqm supported on 2 inch dia GI Pipe firmly fixed to the ground by means of
properly designed foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600 mm below ground
level as per approved drawing and Tehnical Specification Clause 1701.

(iii) Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of sqm 10,985.70
encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick
with area not exceeding 0.9 sqm supported on RCC Post 100 mm x 100 mm firmly fixed to the ground by
means of properly designed foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600 mm below
ground level as per approved drawing and Technical Specification Clause 1701

B Semi-Reflective Traffic signs


Item Unit Rate
No. (Rs.)

Direction and place indentification signs up to 0.9 sqm size board

(I) Providing and erecting direction and place identifications of semi reflective sign boards as per IRC:67 made of sqm 8,591.40
2 mm thick M.S. Sheet duly stove enameled paint in white colour in front and grey colour on back with red
reflective border of 70 mm width and required message, letters, figures with reflective engineering grade tape
as per MORD specifications of required shade and colour. Supported and welded on 47 mm x 47mm of 12
SWG Square tube of 3050 mm height duly strengthened by 25 mm x 5 mm M/s flat iron on edges on back
firmly fixed to the ground by means of properly designed foundations with M-15 grade cement concrete 450
mm x 450 mm x 600 mm, 600 mm below ground level as per approved drawing and Technical Specification
Clause 1701

10.4 Direction and Place Identification signs with size more than 0.9 sqm size board
A Retro-reflectorised Traffic Signs
(I) Providing and erecting direction and place identification retro-\reflectorised sign as per IRC:67 made of sqm 12,655.40
encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick
with area exceeding 0.9 sqm supported on mild steel angle iron posts 75 mm x 75 mm x 6 mm, 2 Nos. firmly
fixed to the ground by means of properly designed foundation with M-15 grade cement concrete 450 mm x 450
mm x 600 mm, 600 mm below ground level as per approved drawing and Technical Specification Clause 1701

(ii) Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of sqm 12,754.00
encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick
with area exceeding 0.9 sqm supported on dia GI Pipe firmly fixed to the ground by means of properly
designed foundation with M-15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground
level as per approved drawing and Technical Specification Clause 1701

(iii) Providing and erecting direction and place identification retro- reflectorised sign as per IRC:67 made of sqm 11,302.50
encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick
with area exceeding 0.9 sqm supported on RCC Posts 100 mm x 100 mm firmly fixed to the ground by means
of properly designed foundation with M 15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm
below ground level as per approved drawing and Technical Specification Clause 1701

B Semi-Reflective Traffic Signs

Direction and place identification signs more than 0.90 sqm sign board

Providing and erecting direction and place identification of semi reflective sign boards as per IRC-67 made of sqm 9,723.80
2 mm thick M.S. Sheet duly stove enameled paint white colour in front and grey colour on back with reflective
border of 70 mm width and required message, letters, figures with reflective tape of engineering grade as per
MORD specifications of required shade and colour. Supported and welded on two nos. 47 mm x 47 mm of 12
SWG square tube of 3050 mm height duly strengthened by 25 mm x 5 mm MS flat iron on edges on back
firmly fixed to the ground by means of properly designed foundations with M-15 grade cement concrete 450
mm x 450 mm x 600 mm, 600 mm below ground level as per approved drawing and Technical Specification
Clause 1701

10.5 Painting Two Coats on New Concrete Surfaces

Painting two coats including primer coat after filling the surface with synthetic enamel paint in all shades on sqm 65.40
new, plastered / concrete surfaces as per drawing and Technical Specification Clause 1701

10.6 Painting on Steel Surfaces

Providing and applying two coats of ready mix paint including primer coat of approved brand on steel surface sqm 66.90
after through cleaning of surface to give an even shade as per drawing and Technical Specification Clause
1701

10.7 Painting on Concrete/Steel Surfaces with Epoxy


Painting two coats including prime coat with epoxy paint of approved brand on concrete/steel surfaces after sqm 121.50
through cleaning of surface to give an even shade as per drawing and Technical Specification Clause 1701

10.8 Painting lines, Dashes, Arrows, etc. on Road in Two Coats on New Work
Painting lines, dashes, arrows, etc. on roads in two coats on new work with ready mixed road marking paint sqm 78.50
conforming to IS:164 on bituminous/concrete surface, including cleaning the surface of all dirt, dust and other
foreign matter, demarcation at site and traffic control as per drawing and Technical Specification Clause 1702

10.9 Painting lines, Dashes, Arrows, etc. on Roads in Two Coats on Old Work
Item Unit Rate
No. (Rs.)

Painting lines, dashes, arrows, etc. on roads in two coats on old work with ready mixed road marking paint sqm 61.40
conforming to IS:164 on bituminous/concrete surface, including cleaning the surface of all dirt, dust and other
foreign matter, demarcation at site and traffic control as per drawing and technical specification Clause 1702

10.10 Kilometre Stone


Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in
position including painting and printing, etc as per drawing and Technical Specification Clause 1703

I) 5th Kilometre Stone (precast) each 3,524.80

ii) Ordinary Kilometer Stone (Precast) each 2,116.40

iii) 200 m stone (precast) each 563.20

10.11 Boundary Pillar

Reinforced cement concrete M15 grade boundary pillars/local stone of standard design as per IRC:25, fixed in each 605.40
position including finishing and lettering but excluding painting as per drawing and Technical Specification
Clause 1704

10.12 G.I Barbed Wire Fencing 1.2 m high

Providing and fixing 1.2 m high GI barbed wire fencing with 1.8 m RCC posts 150 mm x 150 mm placed every Running m 243.90
3 m centre-to-centre founded in M15 grade cement concrete, 0.6 m below ground level, every 15th post, last
but one end post and corner post shall be strutted on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc.
complete as per Clause 1705.

10.13 G.I Barbed Wire Fencing 1.8 m high


Providing and fixing 1.8 m high GI barbed wire fencing with 2.4 m RCC M15 grade 150 mm x 150 mm Running m 404.80
concrete post placed every 3 m centre-to-centre founded in M15 grade cement concrete, 0.6 m below ground
level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on
one side only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with
GI staples, turn buckles etc. complete as per Clause 1705.

10.14 Tubular Steel Railing on Medium Weight Steel Channel (ISMC series) 100 mm x 50 mm

Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel Running m 1,581.50
channels (ISMC series) 100 mm x 50 mm, 1.2 m high above ground, 2 m centre-to-centre, complete as per
approved drawings Clause 1706

10.15 Tubular Steel Railing on Precast RCC posts, 1.2 m high above Ground Level

Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M-20 grade RCC Running m Err:509
vertical posts 175 mm x 175 mm x 1.8 m high (1.2 m above Gl) with 3 holes 50 mm dia for pipe, fixed 2 m
centre-to- centre complete as per approved drawings Clause 1706

10.16 Providing and Fixing 'Logo' of PMGSY Project

Providing and fixing of typical PMGSY informatory sign board with Logo as per MORD specifications and each 21,457.90
drawing. Three MS Plates of 1.6 mm thick, top and middle plate duly welded with MS flat iron 25mm x 5m size
on back on edges. The lower plate will be welded with MS angle iron frame of 25mm x 25mm x 5mm. The
angle iron frame of the lower most plate and flat iron frame of middle plate will be welded to 2 nos. 75mm x 75
mm of 12 SWG sheet tubes posts duly embedded in cement concrete M-15 grade blocks of 450mm x 450mm
x 600mm, 600mm below ground level. The top most diamond plate will be welded to middle plate by 47mm x
47mm of 12 SWG steel plate tube. All M.S. will be stove enameled on both sides. Lettering and printing
arrows, border etc. will be painted with ready mixed synthetic enamel paint of superior quality in required
shade and colour. All sections of framed posts and steel tube will be painted with primer and two coats of
epoxy paint as per drawing Clause 1701 and Annexure 1700.1

10.17 Traffic Cone

Provision of red fluorescent with white reflective sleeve traffic cone made of Low Density Polyethylene (LDPE) each 1,344.80
material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m
interval, all as per BS:873

10.18 Rumble Strips


Item Unit Rate
No. (Rs.)

Provision of 15 n0s.rumble strips covered with premix bituminous carpet,15.2 mm high at centre,250mm wide
placed at 1m centre to centre at approved location to control speed, marked with white strips of road marking
paint.

The rate per sqm of premix carpet and road marking may be adopted from Chapters 5&10 respectively for the
quantities calculated from approved drawings.
10.19 Safety Device and sign in Construction Zones

Provision and fixing of traffic sign for limited period at a suitable location in construction zone comprising of
warning zone,approach transition zone,working zoneand terminal transition zone with a minimunm distance of
2-3 m from the edgeof the carraige way.The bottom edge of the lowest sign plate to be not less than 2 M
above the road level, fixed on 600mx600mx6mm angle iron post,founded and installed as per approved design
and drawings,removed and disposed ofafter completion of construction work, all as per IRC:SP 55-2001

Following types of signs are required to be fixed in construction zones for safety of traffic.

a) Diversion one km ahead

b) Traffic sign ahead

c) Road ahead closed

d)Men at work

e)Road narrow

f)Un even road

g)slipery road

h)Loose chipping

I)Diversion

J)Do not enter

k)Road closed

l)Stop

k)Slow

Speed limit

Note: The rate for traffic signs are already worked out and given elsewhere in this chapter.The same may be
adopted

10.20 Road Markers/Road Stud with Lens Reflector


Providing and fixing of road stud 100 x 100 mm die cast in aluminium, resistant to corrosive effect of salt and each 547.80
grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling holes 30 mm upto a depth
of 600 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS:873 (Part 4) 1973.

Chapter 11 - FOUNDATION

11.1 Excavation for Structures

Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal
upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.

I Ordinary soil

Upto 3 m depth cum 102.00


3 m to 6 m depth cum 148.30

II Ordinary rock (not requiring blasting)

Upto 3 m depth cum 163.90

III Hard rock (requiring blasting) cum 390.70

IV Hard rock (blasting prohibited) cum 386.90

V Marshy soil cum 465.90


Item Unit Rate
No. (Rs.)

11.2 Fillling in foundation trenches as per drawing and technical specification Clause 305.3.9

I Sand filling cum 1,411.80

ii Earth filling (For marshy soil) cum 161.00

11.3 Filling annular space around footing in rock as per technical specification Clause 1203.4.3.

P.C.C grade M 15
A With crushed Stone cum 4,844.60
B With natural Gravel cum 4,563.10
11.4 Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and
technical specifications Clause 802, 803, 1202 & 1203

A With crushed Stone


I P.C.C grade M 10
Nominal mix 1:3:6 cum 5,216.60
Nominal mix 1:3.6 (Hand mixing) cum 5,240.10
II P.C.C grade M 15
Nominal mix (1:2.5:5) cum 5,085.60
Nominal mix 1:2.5:5 (Hand mixing) cum 5,109.10
III P.C.C Grade M20
Nominal mix (1:2:4) cum 5,756.20
Nominal mix 1:2:4 (Hand mixed) cum 5,779.70
IV R.C.C Grade M20 cum 6,108.90
V R.C.C Grade M25 cum 6,510.70
B With natural Gravel
I P.C.C Grade M 10
Nominal mix 1:3:6 cum 4,837.00
Nominal mix 1:3:6 (Hand mixing) cum 4,860.60
II P.C.C Grade M15
Nominal mix 1:2.5:5 cum 4,769.30
Nominal mix 1:2.5:5 (Hand mixing) cum 4,792.90
III P.C.C Grade M20
Nominal mix (1:2:4) cum 5,365.80
Nominal mix 1:2:4 (Hand mixed) cum 5,389.30
IV R.C.C Grade M20 cum 5,648.90
V R.C.C Grade M25 cum 6,052.20
11.5 Brick masonry work in cement mortar in foundation complete excluding pointing and plastering as per
drawing and technical specifications Clauses 600, 1202 & 1203

I. Brick masonry in 1:3 cement mortar cum 6,672.80

ii Brick masonry in 1:4 cement mortar cum 6,464.40

iii Brick masonry in 1:6 cement mortar cum 6,375.20

11.6 Stone masonry work in cement mortar in foundation complete as per drawing and technical
specifications Clauses 702, 704, 1202 & 1203.

I Coursed rubble masonry (1st sort)

In 1:3 cement mortar cum 4,441.40

In 1:4 cement mortar cum 4,160.20

in 1:6 Cement morter cum 4,039.60

II Coursed rubble masonry (2nd sort)

In 1:3 cement mortar cum 5,159.10

In 1:4 cement mortar cum 3,786.30

in 1:6 Cement morter cum 3,630.10


Item Unit Rate
No. (Rs.)

III Random Rubble Masonry

In 1:3 cement mortar cum 5,670.80

In cement mortar 1:4 cum 3,978.30

in 1:6 Cement morter cum 3,857.80

11.7 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: t 54,969.90
TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in foundation complete as per drawings and
technical specifications Clauses 1000 and 1202

11.8 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (Other ISI approved TMT t 47,068.50
reinforcement bar (SAI/BISCON/THERMAX or equivalent)) in foundation complete as per drawings and
technical specifications Clauses 1000 and 1202

11.9 Supplying, fitting and placing MS Bar (Fe-500 ) reinforcement bar (From Primary Producer: t 55,930.00
TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in foundation complete as per drawings and
technical specifications Clauses 1000 and 1202

Chapter 12 - SUBSTRUCTURE

12.1 Brick masonry work in cement mortar in substructure complete excepting pointing and plastering, as per
drawing and technical specification Clauses 602, 603, 604, 1202 & 1204

I In 1:3 cement mortar cum 7,137.90

ii In 1:4 Cement mortar cum 6,925.70

iii In 1:5 cement mortar cum 6,888.20

iv In 1:6 cement mortar cum 6,813.20

12.2 Pointing with cement mortar (1:3) on brickwork as per drawing and technical specification Clauses 10 sqm 583.50
613.3 and 1204

12.3 Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical 10 sqm 1,211.70
specification Clauses 613.4 & 1204

12.4 Stone masonry in cement mortar for substructure complete as per drawing & technical specification
Clauses 702, 704, 1202 and 1204

I Coursed rubble masonry (1st sort)

In 1:3 cement mortar cum 4,878.00

In 1:4 cement mortar cum 4,582.70

In 1:5 cement mortar cum 4,394.10

In 1:6 cement mortar cum 4,309.80

II Coursed Rubble masonry (2nd sort)

In 1:3 cement mortar cum 4,859.30

In 1:4 cement mortar cum 4,443.70

In 1:5 cement mortar cum 4,384.30

In 1:6 cement mortar cum 4,265.50

III Random rubble masonry

In 1:3 cement mortar cum 5,414.70

In 1:4 cement mortar cum 4,889.80

In 1:5 cement mortar cum 4,814.80

In 1:6 cement mortar cum 4,664.80

12.5 Plain/reinforced cement concrete in substructure complete as per drawings and technical specification
Clauses 802, 804, 805, 806, 807, 1202 ans 1204

A With Crushed Stone

I P.C.C grade M 15
Item Unit Rate
No. (Rs.)

i) Nominal mix (1:2.5:5) cum 5,379.00

ii) Nominal mix 1:2.5:5 (Hand mixing) cum 5,403.90

II P.C.C. grade M 20

i) Nominal mix (1:2:4) cum 6,088.30

ii) Nominal mix 1:2:4 (Hand mixed) cum 6,113.20

III RCC Grade M 20

i) For height upto 5 m cum 6,461.00

ii) For height above 5 m upto 10 m cum 6,578.50

IV RCC Grade M 25

i) For height upto 5 m cum 6,903.00

ii) For height above 5 m upto 10 m cum 7,028.50

B With Natural Gravel

I P.C.C grade M 15

i) Nominal mix (1:2.5:5) cum 5,044.50

ii) Nominal mix 1:2.5:5 (Hand mixing) cum 5,069.40

II P.C.C. grade M 20

i) Nominal mix (1:2:4) cum 5,675.40

ii) Nominal mix 1:2:4 (Hand mixed) cum 5,700.20

III RCC Grade M 20

i) For height upto 5 m cum 5,975.00

ii) For height above 5 m upto 10 m cum 6,083.50

IV RCC Grade M 25

i) For height upto 5 m cum 6,417.00

ii) For height above 5 m upto 10 m cum 6,533.50

12.6 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: t 55,091.00
TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in substructrue complete as per drawings and
technical specification Clauses 1002, 1005, 1010 & 1202

12.7 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (Other ISI approved TMT t 47,189.50
reinforcement bar (SAI/BISCON/THERMAX or equivalent)) in substructrue complete as per drawings
and technical specification Clauses 1002, 1005, 1010 & 1202

12.8 Supplying, fitting and placing MS Bar (Fe-500 D) reinforcement bar(From Primary Producer: t 56,051.10
TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in substructrue complete as per drawings and
technical specification Clauses 1002, 1005, 1010 & 1202

12.9 Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, Nos. 117.70
return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of
1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709,
1204.3.7

12.10 Backfilling behind abutment, wing wall and return wall complete as per drawings & technical
specification Clause 1204.3.8

I Granular material cum 1,280.40

ii Sandy material cum 1,576.00

12.11 Providing and laying filter media with granular crushed aggregates as per specification to a thickness cum 1,797.00
of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and
providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted
to firm condition complete as per drawing and technical specification Clause 1204.3.8

12.12 Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC:83 1.59
(Part-II) Section IX complete, including all accessories as per drawings and technical specification
Clause 1207.1 cu cm
Item Unit Rate
No. (Rs.)

12.13 Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per
drawing and technical specification Clauses 615, 710 and 1204.3.11

I With Crushed stone Running m 395.10

ii With Natural Gravel Running m 368.30

12.14 Providing pressure relief pipes 100 mm dia in bottom slab of box cell on a filter media base of 500 mm Nos. 606.10
x 500 mm as per drawing and technical specification Clause 1205.5.7

Chapter 13 - SUPERSTRUCTURE

13.1 Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications
Clauses 800, 1205.4 and 1205.5

A With crushed stone

I R.C.C grade M 20

i For nominal mix 1:2:4

a) Height upto 5 M cum 6,997.71

b) Height from 5m to 10M cum 7,289.28

c) Height above 10 M cum 7,580.85

ii For nominal mix 1:2:4 (Hand mixed)

a) Height upto 5 M cum 7,027.12

b) Height 5m to 10M cum 7,319.92

c) Height above 10M cum 7,612.71

iii For design mix RCC M 20

a) Height upto 5M cum 6,869.83

b) Height 5Mto 10 M cum 7,156.08

c) Height above 10 M cum 7,442.32

II R.C.C grade M 25

a) Height upto 5M cum 7,494.79

b) Height from 5M to 10 M cum 7,807.08

c) Height above 10 M cum 8,119.36

III R.C.C grade M 30

a) Height upto 5M cum 7,762.63

b) Height from 5M to 10M cum 8,086.08

c) Height above 10M cum 8,409.52

B With Natural Gravel

I R.C.C. grade M 20

i For Nominal mix 1:2:4

a) Height upto 5M cum 6,467.38

b) Height from 5M to 10M cum 6,736.86

c) Height above 10M cum 7,006.33

ii Nominal mix 1:2:4 (Hand Mixed)

a) Height upto 5M cum 6,496.80

b) Height from 5M to 10M cum 6,767.50

c) Height above 10M cum 7,038.20

iii For Design mix RCC M 20


Item Unit Rate
No. (Rs.)

a) Height upto 5 M cum 6,339.51

b) Height from 5m to 10M cum 6,603.66

c) Height above 10 M cum 6,867.80

II R.C.C. grade M 25

a) Height upto 5M cum 6,964.47

b) Height from 5M to 10M cum 7,254.66

c) Height above 10M cum 7,544.84

III R.C.C. grade M 30

a) Height upto 5M cum 7,232.31

b) Height from 5M to 10 M cum 7,533.66

c) Height above 10 M cum 7,835.00

13.2 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar . (From Primary Producer: t 56,316.20
TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in superstructure complete as per drawing and
technical specifications Clauses 1002, 1010 and 1202

13.3 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar . (Other ISI approved TMT t 48,414.80
reinforcement bar (SAI/BISCON/THERMAX or equivalent)) in superstructure complete as per drawing
and technical specifications Clauses 1002, 1010 and 1202

13.4 Supplying, fitting and placing MS Bar (Fe-500) reinforcement bar (From Primary Producer: t 57,276.40
TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in superstructure complete as per drawing and
technical specifications Clauses 1002, 1010 and 1202

13.5 Providing and laying cement concrete wearing course M 30 grade including reinforcement complete as
per drawing and technical specifications Clauses 800 and 1206.3

A With crushed stone cum 12,407.50

B With Natural Gravel cum 11,952.30

13.6 Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm nominal size aggregate, true to Running m 2,397.00
line and grade, tolerance of vertical railing post not to exceed 1 in 500, centre-to-centre spacing
between vertical posts not to exceed 2000 mm as per drawing and technical specifications Clauses
800, 900 and 1208.3

13.7 Providing fitting and fixing mild steel railing complete as per drawing and technical specifications Clause 1208.2 Running m 3,593.70

13.8 Providing and fixing in position pipe railing consisting of IS Rolled steel joist posts designation IS MB Running m 1,544.80
100 (100x75) at 2.5 m interval and three rows of 50 mm dia steel pipes (light) including fixing in
position on bridge deck complete as per drawing and technical specifications Clause 1208.2

13.9 Brick masonry work in cement mortar 1:3 in parapet excluding pointing and plastering as per drawing cum 6,716.00
and technical specifications Clauses 600, 900 and 1208.4

13.10 Drainage spouts complete as per drawing and technical specifications Clause 1209 Nos. 1,640.90

13.11 P.C.C. M 15 ordinary grade (1:2.5:5) levelling course below approach slab complete as per drawing and
technical specifications Clauses 800 and 1211

A With crushed stone

I Nominal mix (1:2.5:5) cum 4,890.00

ii Nominal mix 1:2.5:5 (Hand mixing) cum 4,875.40

B With Natural Gravel

I Mix (1:2.5:5) cum 4,585.90

ii Mix 1:2.5:5 (Hand mixed) cum 4,571.30

13.12 Reinforced Cement Concrete M 25 grade approach slab including reinforcement and formwork complete as
per drawing and technical specifications Clauses 800 and 1211
Item Unit Rate
No. (Rs.)

A With crushed stone cum 10,310.60

B With Natural Gravel cum 9,780.30

13.13 Providing and laying of an elastomeric slab seal expansion joint compleate as per approved drawing Running m 15,698.10
and approved specification to be installed by manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturers instructuion for instalation and as per technical
specification clause 1207.2.5

13.14 Providing and laying of a compression seal consisting of steel armoured nosing at two edges of the Running m 16,588.00
joint gap suitably anchored to the deck concrete and a preformed chloroprene elastomer or closed cell
foam joint sealer compressed and formed intothe joint gap with special adhesive binder as per
drawing and technical specification Clause 1207.2.4

13.15 Providing and laying a buried expansion joint, covered with 12 mm thick, 200 mm wide galvanised Running m 1,717.50
weldable structrual steel plate as per IS:2062, placed symmetrical to centre line of the joint, resting
freely over the top surface of the deck concrete, welding of 8 mm dia, 100 mm long galvanised nails
spaced 300 mm c/c along the centre line of the plate, as per technical specifications Clauses 1207.2.3

13.16 Filler Joint

I Providing and fixing 2 mm thick corrugated copper plate in expansion joint as per drawing and technical Running m 946.70
specifications Clause 1207.2.2

ii Providing and fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing and Running m 254.20
technical specifications

iii Providing and fixing 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported Running m 229.30
spans, covered with sealant complete as per drawing and technical specification.

iv Providing and fillling joint sealing compound as per drawings and technical specifications with coarse sand and Running m 21.00
6 per cent bitumen by weight.

13.17 Stone masonry in cement mortar 1:3 for parapet complete as per drawing and technical specifications
Clauses 700 and 1208.4

I Random rubble masonry cum 5,414.70

II Coursed rubble masonry (1st sort) cum 4,878.00

13.18 Pointing with cement mortar (1:3) on brickwork in parapet as per technical specifications Clauses 10 sqm 583.50
613.3 and 1208.4

13.19 Plastering with cement mortar (1:3) 15 mm thick on brickwork in parapet as per technical 10 sqm 1,211.70
specifications Clauses 613.4 and 1208.4

13.20 Providing and laying parapet with PCC M 15 as per drawing & technical specifications Clauses 800 and
1208.4

A With crushed stone

I Nominal mix 1:2.5:5 (Hand mixing) cum 5,379.00

ii Nominal mix (1:2.5:5) cum 5,403.90

B With Natural Gravel

I Mix 1:2.5:5(Hand mixing) cum 5,069.40

ii Mix (1:2.5:5) cum 5,044.50

13.21 Providing bituminous wearing coat comprising of 20 mm thick premix carpet with 5 mm thick seal coat
Type B for culverts as per drawing and technical specifications Clauses 1206.2 and 500

I Rate for wearing coat as per item No. 5.9 of Chapter 5 sqm

ii Rate for seal coat Type B as per item No. 5.12 of Chapter 5 sqm

13.22 Providing bituminous wearing coat comprising of 50 mm thick bituminous macadam overlaid by 20
mm thick premix carpet with 5 mm thick seal coat Type B

I Rate for BM layer may be analysed as per item No 5.3 of Chapter 5 cum
Item Unit Rate
No. (Rs.)

ii Rate of 20 mm premix carpet wearing course as per item No.5.9 of Chapter 5 sqm

iii Rate of seal coat Type B as per item No. 5.12 of Chapter 5 sqm

13.23 Brickwork in arches in cement mortar 1:4 complete including centering and shuttering excluding cum 15,283.80
pointing and plastering as per drawing and technical specifications Clauses 606 and 1205.1

13.24 Coursed rubble stone masonry arch (Ist sort) in cement mortar (1:4) complete including centering etc.
complete as per drawing and technical specifications Clauses 706 and 1205.1

i For arch above 6Mspan cum 10,671.10

ii For Arch 4 m to 6 m span cum 9,604.00

iii For Arch less than 4 m span cum 8,003.30

13.25 Providing & Laying reinforced cement concrete arch complete including centering and shuttering excluding
reinforcement as per drawings and technical specifications Clauses 800, 900 and 1205.1

A With crushed stone


I RCC grade M20 (1:2.4) nominal mix

a) For arch above 6 m span cum 8,907.30

b) For arch 4 m to 6 m span cum 8,313.50

c) For arch less than 4 m span cum 7,719.70

II RCC Grade M 25

a) For arch above 6 m span cum 8,907.34

b) For arch 4 m to 6 m span cum 8,313.52

c) For arch less than 4 m span cum 7,719.69

B With Natural Gravel

I R.C.C.Grade M20 (1:2:4) nominal mix

a) For arch above 6 m span cum 8,244.40

b) For arch 4 m to 6 m span cum 7,694.80

c) For arch less than 4 m span cum 7,145.20

II R.C.C Grade M25

a) For arch above 6 m span cum 8,847.07

b) For arch 4 m to 6 m span cum 8,257.27

c) For arch less than 4 m span cum 7,667.46

13.26 Providing steel R.S.Jst/ built-up steel sections including cutting, welding/ rivetting, hoisting, fixing in
position for composite girders with shear connectors complete with painting as per drawing and
technical specifications Clause 1205.6

Steel section quintal 9,014.10

Chapter 14 - PROTECTION WORKS

14.1 Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight cum 1,349.50
as per Table 1300.1, no fragment weighing less than 25 kg laid dry complete as per drawing and
technical specifications Clause 1301

14.2 Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire conforming to IS:280 cum 2,178.20
and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and
joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical
specifications Clause 1301

14.3 Providing and laying of apron with cement concrete blocks of size as per Table 1300.1 cast-in-situ and cum 5,062.80
made with nominal mix of M-15 grade cement concrete as per drawing and technical specifications
Clause 1301
Item Unit Rate
No. (Rs.)

14.4 Single bamboo palasiding / walling of whole 2nd class bamboo (Jati or Bethua) 75mm dia and closely
packed & driven including fitting fixing with half bamboo kamis horizontally in three rows with cane or
tying with wire complete and struts 1.5 m apart longitudinally and providing brush wood as per
drawing and technical specifications Clause 1302.5

Driven at least 900 mm below ground and 1200 mm above ground Running m 782.20

Driven at least 900 mm below ground and 900 mm above ground on average Running m 737.20
14.5 Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical
specifications Clause 1302

I Stone/Boulder cum 1,349.50

II Cement concrete blocks of size as per Table 1300.2 cast in cement concrete of grade M 15

a) Concrete grade M 15 cum 5,187.30

b) Brick pitchng set in cement mortar 1:4 cum 5,848.70

14.6 Providing and laying filter material underneath pitching in slopes complete as per drawing and cum 1,768.60
technical specifications Clause 1302

14.7 Providing and laying flooring laid over cement concrete bedding complete as per drawing and
technical specification Clause 1303

i Rubble stone laid in cement mortar 1:3 cum 3,731.00

ii Cement conrete blocks grade M 15 cum 5,650.10

iii Brick on edge laid in cement mortar (1:3) cum 4,843.00

Note : Cement concrete bedding to be measured and paid extra.

14.8 Providing and laying of dry rubble flooring complete as per drawings and technical specifications cum 2,216.80
Clause 1303.3

14.9 Providing and laying curtain walls complete as per drawing and technical specification Clause 1304

I Brick masonry in cement mortar (1:4) cum 7,110.90

ii Coursed rubble masonary (2nd sort) in cement mortar (1:4) cum 4,443.70

iii Cement concrete grade M 10 cum 4,955.80

14.10 Construction of flexible apron 1 m thick comprising of loose stone boulders weighing not less then 25 cum 1,128.30
kg beyond curtain wall

14.11 Construction of toe walls for protection of slopes as per drawing and technical specifications Clause
1302.5

I Random rubble masonry in case of stone pitching laid with cement mortar (1:5) cum 3,988.60

ii Brick masonry in cement mortar 1:4 in case of brick pitching cum 5,742.70

iii Cement concrete grade M 10 in case of concrete block pitching cum 5184.00

Nominal mix 1:3:6

14.12 Single bamboo spur and palisading of whole 2nd class bamboo (jati or Bethua) 65 mm to 75 mm dia
and closely packed & driven, including fitting, fixing with half bamboo kamis horrizontally in three
rows with cane or tying wire complete and struts 1500 mm apart longitudinally and providing brush
wood as per drawing and technical specifications Clause 1302.5

I Driven at least 900 mm below ground and 1800 mm above ground on average Running m 917.20

ii Driven at least 900 mm below ground and 900 mm above ground on average Running m 740.90

14.13 Single bamboo spur and palisading of whole 1st class bamboo (Bholuka or Barua) 85 mm to 100 mm
dia. Closely packed & driven including fitting, fixing with half 2nd class bamboo (jati or Bethua)
horizontally in three rows with cane or tying wire complete and struts 1500 mm apart longitudinally
and providing brush wood in the spur as per drawings and technical specifications

A Driven at least 900 mm below ground and 1800 mm above ground Running m 1,343.70
Item Unit Rate
No. (Rs.)

B Driven at least 900 mm below ground and 900 mm above ground on average Running m 926.60

C Driven at least 600 mm below ground and 1200 mm above ground on average. Running m 851.60

14.14 Bamboo spur 'A' type with whole bamboo 85mm-100mm dia, placed 230 mm centre to centre driven
900 mm below ground and 1200 mm to 1500 mm above ground tied with 2nd class bamboo (jati or
Bethua) on either side at 450 mm apart horizontally with galvanised wire etc. complete as per drawings
and technical specifications

A 2nd class bamboo (jati or Bethua) 75 mm dia Running m 948.30

B 1st class bamboo (Bholuka or Barua ) 85 mm to 100 mm dia Running m 893.90

14.15 Providing 'A' type single spur with 1st class bamboo (Bholuka or Barua) 85 mm to 100 mm dia. Driven Running m 1,619.30
closely placed 3m to 4m above ground and 1200 mm to 1500 mm below ground tied with cane or coir
string, half 2nd class bamboo (jati or Bethua) horizontally on both face placed not more than one metre
apart including whole bamboo struts inside one metre apart and 2 nos. of purlin at top and bottom
fitted with vertical struts at 1500 mm apart and filling with brushwood or jungle wood inside the spur
complete as per drawing and technical specifications

14.16 Providing close bamboo toe walling consisting of 65mm to 75mm dia bamboos of length ranging from 1.2 m to Running m 1,079.60
3m driven at 150 mm centre to centre and provided with three horizontal split bamboo runner fixed with nails.
All bamboos to be duly protected by coal tar painting.

14.17 Double timber spur with two rows at 800 mm c/c apart of 1st class local wood piles with timber of Running m 23,770.60
Azar/Nahar/Nageswar / Zarul wood 150 mm to 200 mm dia driven 2000 mm minimum below ground and
3600 mm above ground average placed at 800 mm belts, bracings etc. of 100 mm x 75 mm size 1st
class local wood longitudinally & crosswiswe at ends fitted with 10 mm dia bolts and nuts etc.
including coaltarring of timber members and cost of necessary bamboo stagings etc. as directed by
the Engineer as per drawing and technical specifications

14.18 Supplying and filling up hollows of the timber spur to an average height of 3600 mm above ground Running m 69.90
with jungle wood branches as per drawing and technical specifications as directed by the Engineer.

Chapter 15 - MAINTENANCE OF ROADS

15.1 Restoration of Rain Cuts

Restoration of rain cuts with soil, moorum gravel or a mixture of these, clearing the loose soil, benching for
300mm width laying fresh material in layers not exceeding 250 mm and compaction with plate compactor or
power rammer to restore the original alignment, level and slopes as per drawings and technical specifications
Clause 1902

A Manual Means cum 130.50

B Mechanical Means cum 110.20

15.2 Maintenance of Earthen shoulder (filling with fresh selected soil)

1 Making up loss of material/irregularities on shoulders to the design level by adding fresh approved selected sqm 72.10
soil and compacting it with appropriate equipment at OMC upto a lead of 1000 m as per technical
specification Clause 1903

Maintenance of Earhen shoulder (stripping of excess soil)

2 Stripping excess soil from the shoulder surface to achieve the approved level and compacting with plate sqm 15.60
compactor at OMC as per drawings and Technical Specification Clause 1903

15.3 Maintenance of Bituminous surface road

I Repair to pot holes by removal of failed material,trimming the sides to vertical and levelling the bottom,cleaning cum 7,396.20
the same with compressed air or any appropriate method filled with 75 mm B.M. applying bitumen emulsion
prime coat at the bottom and bitumen emulsion tack coat on sides and on bottom as per technical specification
Clause 502 and 503

ii Patch repair on already filled pot holes with 75 mm BM with 20 mm premix carpet and seal coat Type B as per sqm 173.20
drawings and technical specification Clause 1904.2

iii Repair to pot holes and removal of loose material, trimming of sides, cleaning of surface by providing tack sqm 162.90
coat, 20 mm thick pre-mix carpet and seal coat type B specification Clause 1904.2
Item Unit Rate
No. (Rs.)

iv Repair to pot holes and removal of loose material, trimming of sides, cleaning of surface by providing tack coat sqm 173.70
with bitumen emulsion, 20 mm thick pre-mix carpet using catonic bitumen emulsion and seal coat type B with
bitumen emulsion

15.4 Maintenance of Gravel Road

Maintenance of gravel road including making up the loss of profile, rectifying corrugated surface, filling up of sqm 347.50
depressions, pot holes and erosion gullies by adding fresh material and compacting it with appropriate
equipment or to strip excess of material from the road surface as per drawings and technical specification
Clause 1905

15.5 Maintenance of WBM Road

Maintenance of WBM road including filling up of pot holes, ruts and rectifying corrugated surface, damaged sqm 290.20
edges and ravelling as per technical specification Clause 1906.

15.6 Maintenance of Drains

The maintenance of drains include erosion, repair, clearing, cleaning, reshaping, regrading, deepening of side m 2.30
drains as well as catch water drains as per technical specification Clause 1907.

15.7 Maintenance of Culverts

I Maintenance of Hume pipe Culvert by way of Clearing, Cleaning, Erosion repair, repairs to cracks, parapet One No. 1,439.60
wall and protection work as per drawing and technical specification Clause 1908 Hume Pipe

ii Maintenance of Culverts Slab type

Maintenance of Slab type Culverts by way of clearing, Cleaning, Erosion repair, repairs to cracks, parapet Culvert 2,851.80
walls and Protection works as per drawing and technical specification Clasue 1908

15.8 Maintenance of Causeway

Maintenance of Causeway by way of minor Surface repairs, replacing Guide Posts, repair of flood gauges, m 65.50
removal of debris, providing boulders and protection work and painting as per technical specification Clause
1909

15.9 Maintenance of Road Signs

Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / km 1,100.90
informatory and place identifications sign board as perdrawings and technical specification Clause 1910

15.10 Maintenance of steel and RCC Railing

I Repair of steel railing to bring it to original shape cleaning and repainting as per drawing and technical
specification Clause 1911
Steel Railing Running m 319.40
ii Repair of RCC railing to bring it to the original shape, cleaning and repainting as per drawings and technical
specification Clause 1911

RCC Railing m 137.20

15.11 Maintenance of 200 metre and km stones

Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning,
repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification
Clause 1912

I Painting two coats with synthetic enamel paint sqm 123.90

ii Printing letters and figures of any shade with synthtic enamel paint of any approved colour to give an even km 524.40
shade
15.12 Cutting of branches of trees shrubs and trimming of grass and weeds

I Cutting of branches of trees and shrubs from the road way or with in R.O.W including disposal of wood and one tree 100.00
leaves to suitable location as per technical specification Clause 1914

ii Cutting of shrubs from the road way or with in R.O.W and disposal of shrubs to suitable locations as per each 5.80
technical specifications Clause 1914

iii Trimming of grass and weeds from the shoulders/berms and disposing off the same to suitable locations as sqm 1.90
per technical specifications Clause 1914

15.13 White washing of parapet walls of CD work and tree truncks


Item Unit Rate
No. (Rs.)

White washing two coats on parapet walls and tree trunks including preparation of surface by cleaning sqm 16.50
scraping etc. as per technical specifications Clause 1915

15.14 Periodical Renewal to existing bituminous surface

1 Open graded Premix carpet 20 mm thick


I) Tack coat

Rates as per item 5.2 (ii) sqm

ii) Pre-mix carpet using bituminous (penetration grade modified bitumen) binder
Rates as per item No. 5.9 sqm

OR
iii) Premix carpet using bitumen Emulsion

Rates as per item No. 5.10 sqm

iv) Seal coat Type A, B or C

Rates as per item No. 5.11 sqm

2 Surface dressing single coat/first coat or 2nd coat


Rates as per item No. 5.6 sqm
Chapter 1

LOADING, UNLOADING, CARRIAGE CRUSHING OF MATERIALS AND SETTING OUT

Sr. Reference to Rate


Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

1.1 Loading and Unloading of Lime, Aggregate, Stone Boulder, Brick


Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for
Masonry Work by Manual Means

(i) Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate,


Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work
by manual means including a lead upto 30 m

Unit = cum

Taking output = 5.5 cum

a) Labour

Mate day 0.02 356.65 7.13

Mazdoor (Unskilled) day 0.50 244.56 122.28

b) Machinery

Truck hour 0.50 825.00 412.50

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 67.74

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 5.5 cum = a+b+c+d+e 609.65

Rate per cum = (a+b+c+d+e)/5.5 110.85

(ii) Loading of Earth, Sand, Moorum, Manure, Flyash by manual


means including a lead upto 30 m

Unit = cum

Taking output = 5.5 cum

a) Labour

Mate day 0.01 356.65 3.57

Mazdoor (Unskilled) day 0.25 244.56 61.14

b) Machinery

Truck hour 0.25 825.00 206.25

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 33.87

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 5.5 cum = a+b+c+d+e 304.83

Rate per cum = (a+b+c+d+e)/5.5 55.42

(iii) Unloading of Lime, Aggregate, Stone Boulder, Brick Aggregate,


Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work
by manual means including a lead upto 30 m

Unit = cum

Taking output = 5.5 cum

a) Labour

Mate day 0.01 356.65 3.57

Mazdoor (Unskilled) day 0.25 244.56 61.14

b) Machinery

Truck hour 0.25 825.00 206.25

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 33.87

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 5.5 cum = a+b+c+d+e 304.83

Rate per cum = (a+b+c+d+e)/5.5 55.42

1 - 140
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

(iv) Unloading of Earth, Sand, Moorum, Manure, Flyash by manual


means including a lead upto 30 m

Unit = cum

Taking output = 5.5 cum

a) Labour

Mate day 0.005 356.65 1.78

Mazdoor (Unskilled) day 0.125 244.56 30.57

b) Machinery

Truck hour 0.166 825.00 136.95

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 21.16

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 5.5 cum = a+b+c+d+e 190.47

Rate per cum = (a+b+c+d+e)/5.5 34.63

1.2 Loading and Unloading Lime, Aggregate, Stone Boulder, Brick


Aggregate, Kankar, Building Rubbish, Crushed Slag, Stone for
Masonry Work by Mechanical Means

(i) Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate,


Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work
by mechanical means including a lead upto 30 m

Placing tipper at loading point, loading with front end loader


excluding time for haulage and return trip.

Unit = cum

Taking output = 5.5 cum

Time required for

i) Positioning of tipper at loading point Min 1.00

ii) Loading by front end loader 1 cum bucket capacity @ 45 Min 7.33
cum per hour

iii) Waiting time, unforeseen contingencies, etc. Min 2.00

Total Min 10.33

a) Machinery

(i) Tipper 10 t capacity hour 0.172 850.00 146.20

(ii) Front end-loader 1 cum bucket capacity @ 45 cum per hour 0.122 1,341.00 163.60
hour
b) Contractor’s profit & Overheads @ 12.5% on a 38.73

c) Add GST, LWC etc. @ 0 on a -

Cost for 5.5 cum = a+b+c 348.53

Rate per cum = (a+b+c+d) /5.5 63.37

(ii) Loading of Earth, Sand, Moorum, Manure, Flyash by mechanical


means including a lead upto 30 m.

Placing tipper at loading point, loading with front end loader


excluding time for haulage and return trip.

Unit = cum

Taking output = 5.5 cum

Time required for

i) Positioning of tipper at loading point Min 1.00

ii) Loading by front end loader 1 cum bucket capacity @ 100 Min 3.30
cum per hour

iii) Waiting time, unforeseen contingencies, etc. Min 2.00

Total Min 6.30

1 - 141
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

a) Machinery

(i) Tipper 10 t capacity hour 0.105 850.00 89.25

(ii) Front end-loader 1 cum bucket capacity @ 100 cum per hour 0.055 1,341.00 73.76
hour
b) Contractor’s profit & Overheads @ 12.5% on a 20.38

c) Add GST, LWC etc. @ 0 on a -

Cost for 5.5 cum = a+b+c 183.38

Rate per cum = (a+b+c+d) /5.5 33.34

(iii) Unloading of Earth, Sand, Lime, Moorum, Aggregate, Stone


Boulder, Brick Aggregate, Kankar, Building Rubbish, Manure,
Crushed Slag, Flyash, Stone for Masonry Work by mechanical
means.

Unit = cum

Taking output = 5.5 cum

Placing tipper at unloading point excluding time for haulage and


return trip

Time required for

i) Positioning of tipper at unloading point Min 1.00

ii) Manoeuvering, reversing, dumping and turning for return Min 2.00

iii) Waiting time, unforeseen contingencies, etc. Min 2.00

Total Min 5.00

a) Machinery

Tipper 10 t capacity hour 0.08 850.00 68.00

b) Contractor’s profit & Overheads @ 12.5% on a 8.50

c) Add GST, LWC etc. @ 0 on a -

Cost for 5.5 cum = a+b+c 76.50

Rate per cum = (a+b+c+d) /5.5 13.91

1.3 Loading, Unloading and Stacking of Bricks by Manual Means

(i) Loading of Bricks by manual means including a lead upto 30 m

Unit = 1000 Nos.

Taking output = 2000 Nos.

a) Labour

Mate day 0.01 356.65 3.57

Mazdoor (Unskilled) day 0.25 244.56 61.14

b) Machinery

Truck hour 0.33 825.00 272.25

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 42.12

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 2000 Nos. = a+b+c+d 379.08

Rate per 1000 Nos. = (a+b+c+d)/2 189.54

(ii) Unloading and Stacking of Bricks by manual means including a


lead upto 30 m

Unit = 1000 Nos.

Taking output = 2000 Nos.

a) Labour

Mate day 0.01 356.65 3.57

Mazdoor (Unskilled) day 0.25 244.56 61.14

b) Machinery

1 - 142
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

Truck hour 0.33 825.00 272.25

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 42.12

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 2000 Nos. = a+b+c+d 379.08

Rate per 1000 Nos. = (a+b+c+d)/2 189.54

1.4 Loading and Unloading of Cement by Manual Means

(i) Loading of Cement by manual means including a lead upto 30 m

Unit = t

Taking output = 10 t

a) Labour

Mate day 0.06 356.65 21.40

Mazdoor (Unskilled) day 1.50 244.56 366.84

b) Machinery

Truck hour 1.00 825.00 825.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 151.65

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 2000 Nos. = a+b+c+d 1,364.89

Rate per 1000 Nos. = (a+b+c+d)/2 682.45

(ii) Unloading of Cement by manual means including a lead upto 30 m

Unit = ton

Taking output = 10 t

a) Labour

Mate day 0.06 356.65 21.40

Mazdoor (Unskilled) day 1.50 244.56 366.84

b) Machinery

Truck hour 1.00 825.00 825.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 151.65

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 10 t = a+b+c+d 1,364.89

Rate per tonne = (a+b+c+d)/10 136.49

1.5 Loading and Unloading of Structural Steel and Steel Bars by


manual means

(i) Loading of Structural Steel, Steel Bars by manual means including


a lead upto 30 m

Unit = t

Taking output = 10 t

a) Labour

Mate day 0.07 356.65 24.97

Mazdoor (Unskilled) day 1.80 244.56 440.21

b) Machinery

Truck hour 1.00 825.00 825.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 161.27

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 10 t = a+b+c+d 1,451.45

Rate per tonne = (a+b+c+d)/10 145.14

1 - 143
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

(ii) Unloading of Structural Steel, Steel Bars by manual means


including a lead upto 30 m

Unit = t

Taking output = 10 t

a) Labour

Mate day 0.07 356.65 24.97

Mazdoor (Unskilled) day 1.80 244.56 440.21

b) Machinery

Truck hour 1.00 825.00 825.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 161.27

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 10 t = a+b+c+d 1,451.45

Rate per tonne = (a+b+c+d)/10 145.14

1.6 Loading and Unloading of Bitumen Drums by Manual Means

(i) Loading of Bitumen Drums by manual means including a lead upto


30 m
Unit = t

Taking output = 10 t

a) Labour

Mate day 0.06 356.65 21.40

Mazdoor (Unskilled) day 1.60 244.56 391.30

b) Machinery

Truck hour 1.25 825.00 1,031.25

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 180.49

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 10 t = a+b+c+d 1,624.44

Rate per tonne = (a+b+c+d)/10 162.44

(ii) Unloading of Bitumen Drums by Manual Means including a lead


upto 30 m

Unit = t

Taking output = 10 t

a) Labour

Mate day 0.05 356.65 17.83

Mazdoor (Unskilled) day 1.20 244.56 293.47

b) Machinery

Truck hour 1.25 825.00 1,031.25

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 167.82

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 10 t = a+b+c+d 1,510.37

Rate per tonne = (a+b+c+d)/10 151.04

Note: The rate is inclusive of the self weight of drum

1.7 100 Loading and Unloading of Timber by Manual Means

(i) Loading of Timber by manual means including a lead upto 30 m

Unit = t

Taking output = 5 t

a) Labour

Mate day 0.04 356.65 14.27

1 - 144
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

Mazdoor (Unskilled) day 1.00 244.56 244.56

b) Machinery

Truck hour 1.00 825.00 825.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 135.48

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 5 t = a+b+c+d 1,219.30

Rate per tonne = (a+b+c+d)/5 243.86

(ii) Unloading of Timber by manual means including a lead upto 30 m

Unit = t

Taking output = 5 t

a) Labour

Mate day 0.04 356.65 14.27

Mazdoor (Unskilled) day 1.00 244.56 244.56

b) Machinery

Truck hour 1.00 825.00 825.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 135.48

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 5 t = a+b+c+d 1,219.30

Rate per tonne = (a+b+c+d)/5 243.86

Note: Density of wood has been assumed as 900 kg per cum. If the density is
less the output may be reduced proportionately

1.8 Loading and Unloading of C.C. Blocks, Kerb, etc.

(i) Loading with care C.C. Blocks, km Stone, 200 m Stone, Boundary
Pillar, Kerb, Channel, Bond Stone, etc. by manual means
including a lead upto 30 m

Unit = cum

Taking output = 5.5 cum

a) Labour

Mate day 0.08 356.65 28.53

Mazdoor (Unskilled) day 2.00 244.56 489.12

b) Machinery

Truck hour 1.50 825.00 1,237.50

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 219.39

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 5.5 cum = a+b+c+d 1,974.55

Rate per tonne = (a+b+c+d)/5.5 359.01

(ii) Unloading with care C.C. Blocks, km Stone, 200 m Stone,


Boundary Pillar, Kerb, Channel, Bond Stone, etc. by manual
means including a lead upto 30 m

Unit = cum

Taking output = 5.5 cum

a) Labour

Mate day 0.08 356.65 28.53

Mazdoor (Unskilled) day 2.00 244.56 489.12

b) Machinery

Truck hour 1.50 825.00 1,237.50

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 219.39

1 - 145
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 5.5 cum = a+b+c+d 1,974.55

Rate per tonne = (a+b+c+d)/5.5 359.01

1.9 Loading and Unloading of Hume Pipes

(i) Loading of RCC Hume pipes by mechanical means including a


lead upto 30 m
A. 1000 / 1200 mm dia Hume pipe

Unit = per pipe

Taking output = 9 pipes

a) Labour

Mate day 0.02 356.65 7.13

Mazdoor (Unskilled) day 0.50 244.56 122.28

b) Machinery

Truck hour 0.33 825.00 272.25

Crane hour 0.33 685.00 226.05

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 78.46

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 9 pipes = a+b+c+d 706.18

Rate per pipe = (a+b+c+d)/9 78.46

B. 750 mm dia Hume pipe

Unit = per pipe

Taking output = 15 pipes

a) Labour

Mate day 0.02 356.65 7.13

Mazdoor (Unskilled) day 0.50 244.56 122.28

b) Machinery

Truck hour 0.33 825.00 272.25

Crane hour 0.33 685.00 226.05

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 78.46

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 15 pipes = a+b+c+d 706.18

Rate per pipe = (a+b+c+d)/15 47.08

C. 600/450 mm dia Hume pipe

Unit = per pipe

Taking output = 21 pipe

a) Labour

Mate day 0.02 356.65 7.13

Mazdoor (Unskilled) day 0.50 244.56 122.28

b) Machinery

Truck hour 0.33 825.00 272.25

Crane hour 0.33 685.00 226.05

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 78.46

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 21 pipes = a+b+c+d 706.18

Rate per pipe = (a+b+c+d)/21 33.63

(ii) Unloading of RCC Hume pipe by manual means including a lead


upto 30 m

1 - 146
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

A. 1000/1200 mm dia RCC Hume pipes

Unit = per pipe

Taking output = 5 pipes

a) Labour

Mate day 0.04 356.65 14.27

Mazdoor (Unskilled) day 1.00 244.56 244.56

b) Machinery

Truck hour 2.00 825.00 1,650.00

c) Material

Wooden sleepers 250mm x 250mm x125mm hire hour 2.00 35.00 70.00
charges 3 nos sleeper
Crow bars 2 nos not less than 40 mm dia (hire-charges) hour 2.00 5.00 10.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 248.60

e) Add GST, LWC etc. @ 0 on (a+b+c) -

Cost for 5 pipes = a+b+c+d+e 2,237.43

Rate per pipe = (a+b+c+d+e)/5 447.49

B. 750 mm dia Hume pipe

Unit = per pipe

Taking output = 6 pipes

a) Labour

Mate day 0.04 356.65 14.27

Mazdoor (Unskilled) day 1.00 244.56 244.56

b) Machinery

Truck hour 2.00 825.00 1,650.00

c) Materials

Wooden sleepers 250mm x250mm x 125mm hire hour 2.00 35.00 70.00
charges 3 nos. sleeper
Crow bars 2 nos not less than 40 mm dia hour 2.00 5.00 10.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 248.60

e) Add GST, LWC etc. @ 0 on (a+b+c) -

Cost for 6 pipes = a+b+c+d+e 2,237.43

Rate per pipe = (a+b+c+d+e)/6 372.90

C. 600/450 mm dia Hume pipe

Unit = per pipe

Taking output = 8 pipes

a) Labour

Mate day 0.04 356.65 14.27

Mazdoor (Unskilled) day 1.00 244.56 244.56

b) Machinery

Truck hour 2.00 825.00 1,650.00

c) Materials

Wooden sleepers 250mm x 250mm x 125mm hire hour 2.00 35.00 70.00
charges 3 nos. sleeper
Crow bars 2 nos not less than 40 mm dia hour 2.00 5.00 10.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 248.60

e) Add GST, LWC etc. @ 0 on (a+b+c) -

1 - 147
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

Cost for 8 pipes = a+b+c+d+e 2,237.43

Rate per pipe = (a+b+c+d+e)/8 279.68

(iii) Unloading of RCC Hume pipes by mechanical means including a


lead upto 30 m

A. 1000/1200 mm dia Hume pipe

Unit = per pipe

Taking output = 9 pipes

a) Labour

Mate day 0.02 356.65 7.13

Mazdoor (Unskilled) day 0.50 244.56 122.28

b) Machinery

Truck hour 0.20 825.00 165.00

Crane hour 0.20 685.00 137.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 53.93

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 9 pipes = a+b+c+d 485.34

Rate per pipe = (a+b+c+d)/9 53.93

B. 750 mm dia Hume pipe

Unit = per pipe

Taking output = 15 pipes

a) Labour

Mate day 0.02 356.65 7.13

Mazdoor (Unskilled) day 0.50 244.56 122.28

b) Machinery

Truck hour 0.20 825.00 165.00

Crane hour 0.20 685.00 137.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 53.93

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 15 pipes = a+b+c+d 485.34

Rate per pipe = (a+b+c+d)/15 32.36

C. 600/450 mm dia Hume pipe

Unit = per pipe

Taking output = 21 pipes

a) Labour

Mate day 0.02 356.65 7.13

Mazdoor (Unskilled) day 0.50 244.56 122.28

b) Machinery

Truck hour 0.20 825.00 165.00

Crane hour 0.20 685.00 137.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 53.93

d) Add GST, LWC etc. @ 0 on (a+b) -

Cost for 21 pipes = a+b+c+d 485.34

Rate per pipe = (a+b+c+d)/21 23.11

1.10 Haulage excluding Loading & Unloading

Haulage of materials by tipper excluding cost of loading, unloading and


stacking.

Unit = t.km

1 - 148
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

Taking output 10 t load and lead 10 km = 100 t.km

Case-I : Surfaced Road

Speed with load: 20 km per hour

Speed while returning empty: 28 km per hour

a) Machinery

Tipper 10 t capacity

Haulage with load hour 0.50 850.00 425.00

Empty return trip hour 0.36 850.00 306.00

b) Contractor’s profit & Overheads @ 12.5% on (a) 91.38

c) Add GST, LWC etc. @ 0 on (a) -

Cost for 100 t.km = a+b+c 822.38

Rate per t.km = (a+b+c)/100 8.20

Note: In case of carriage of Hume pipes, output of truck be taken as 8 t and


the rate for t is to be divided by number of pipes of different diameters
as indicated in item 1.9 to get the rate per pipe.

Case-II: Unsurfaced Gravel Road

Speed with load: 15 km/hour

Speed for empty return trip: 25 km/hour

a) Machinery

Tipper 10 t capacity

Haulage with load hour 0.67 850.00 569.50

Empty return trip hour 0.40 850.00 340.00

b) Contractor’s profit & Overheads @ 12.5% on (a) 113.69

c) Add GST, LWC etc. @ 0 on (a) -

Cost for 100 t.km = a+b+c+d 1,023.19

Rate per t.km = (a+b+c+d)/100 10.20

Note: In case of carriage of Hume pipes, output of truck be taken as 8 t and


the rate per t is to be divided by number of pipes of different diameters
as indicated in item 1.9 to get the rate per pipe.

Case-III: Katcha Track and Track in River Bed/Nallah Bed and


Choe Bed

Speed with load: 10 km per hour

Speed while returning empty: 15 km per hour

a) Machinery

i) Tipper 10 t capacity

Haulage with load hour 1.00 850.00 850.00

Empty return trip hour 0.67 850.00 569.50

b) Contractor’s profit & Overheads @ 12.5% on (a) 177.44

c) Add GST, LWC etc. @ 0 on (a) -

Cost for 100 t.km = a+b+c+d 1,596.94

Rate per t.km = (a+b+c+d)/100 16.00

Note: In case of carriage of Hume pipes, output of truck be taken as 8 t and


the cost for 8 t is to be divided by number of pipes of different diameters
as indicated in item 1.9 to get the rate per pipe.

1.11 Supply of Quarried stone and hand breaking

(i) Supply of quarried stone and hand breaking into coarse aggregate
to Grading 1 (90 mm to 45 mm) as per Table 400.8 of Technical
Specifications.

Unit = cum

1 - 149
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

Taking output = 1 cum

a) Labour

Mate day 0.048 356.65 17.12

Mazdoor (Unskilled) day 1.20 244.56 293.47

b) Material

Supply of quarried stone 150-200 mm size cum 1.10 898.00 987.80

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 162.30

d) Add GST, LWC etc. @ 0 on (a+b) -

Rate per cum = a+b+c+d 1,461.00

(ii) Supply of quarried stone and hand breaking into coarse aggregate
to Grading 2 (63 mm to 45 mm) as per Table 400.8 of Technical
Specifications.

Unit = cum

Taking output = 1 cum

a) Labour

Mate day 0.06 356.65 21.40

Mazdoor (Unskilled) day 1.50 244.56 366.84

b) Material

Supply of quarried stone 150-200 mm size cum 1.10 898.00 987.80

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 172.00

d) Add GST, LWC etc. @ 0 on (a+b) -

Rate per cum = a+b+c+d 1,548.00

(iii) Supply of quarried stone and hand breaking into coarse aggregate
to Grading 3 (53 mm to 22.4 mm) as per Table 400.8 of Technical
Specifications.

Unit = cum

Taking output = 1 cum

a) Labour

Mate day 0.072 356.65 25.68

Mazdoor (Unskilled) day 1.80 244.56 440.21

b) Material

Supply of quarried stone 150-200 mm size cum 1.10 898.00 987.80

c) Contractor’s profit & Overheads @ 12.5% on (a+b) 181.71

d) Add GST, LWC etc. @ 0 on (a+b) -

Rate per cum = a+b+c+d 1,635.00

1.12 Crushing of Stone Aggregates 100 per cent passing through 53 mm


sieve as per Table 500.6 of Technical Specifications.

Crushing of stone boulders of 150 mm size in an integrated stone


crushing unit of 200 t/h capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens to obtain stone
aggregates 100 per cent passing through 53 mm sieve as per Table
500.6 of Technical Specifications including the cost of stone.

Unit = cum

Taking output = 750 cum at crusher location

a) Labour

Mate day 0.76 356.65 271.05

Mazdoor (Skilled) day 2.00 356.65 713.30

Mazdoor (Unskilled) day 17.00 244.56 4,157.52

1 - 150
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

b) Material

Stone Boulder of size 150 mm and below cum 800.00 1,055.00 844,000.00

c) Machinery

Integrated stone crusher of 200 t/h including belt conveyor and hour 6.00 14,389.00 86,334.00
vibrating screens

Front end loader 1 cum bucket capacity hour 20.00 1,341.00 26,820.00

Tipper 5.5 cum capacity hour 20.00 850.00 17,000.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 122,411.98

e) Add GST, LWC etc. @ 0 on (a+b+c) -

Cost for 750 cum = (a+b+c+d+e) x 0.85 936,451.68

Rate per cum =[ (a+b+c+d+e) x 0.85]/ 750 1,248.60

Note: 1 800 cum of stone boulders are needed to get 750 cum of stone
aggregates.

2 85 per cent of above cost will be attributed to the production of


750 cum of stone aggregates of 40 mm size and balance 15 per
cent will be for smaller size aggregates and stone dust which
comes out as a by-product.

3 The integrated stone crusher includes primary and secondary


crushing units.

1.13 Crushing of Stone Aggregates 100 per cent passing through 22.4
mm sieve as per Table 500.6 of Technical Specifications.

Crushing of stone boulders of 150 mm size in an integrated stone


crushing unit of 200 t/h capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens to obtain stone
aggregates 100 per cent passing through 22.4 mm sieve as per Table
500.6 of Technical Specifications including the cost of stone.

Unit = cum

Taking output = 670 cum at crusher location

a) Labour

Mate day 0.76 356.65 271.05

Mazdoor (Skilled) day 2.00 356.65 713.30

Mazdoor (Unskilled) day 17.00 244.56 4,157.52

b) Material

Stone boulder of size 150 mm and below cum 800.00 1,055.00 844,000.00

c) Machinery

Integrated stone crusher of 200 t/h including belt conveyor and hour 6.00 14,389.00 86,334.00
vibrating screens
Front end loader 1 cum bucket capacity hour 10.00 1,341.00 13,410.00

Tipper 5.5 cum capacity hour 10.00 850.00 8,500.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 119,673.23

e) Add GST, LWC etc. @ 0 on (a+b+c) -

Cost for 670 cum = (a+b+c+d+e) x 0.9 969,353.20

Rate per cum =[ (a+b+c+d+e) x 0.9]/ 670 1,446.80

Note: 1 800 cum of stone boulders are needed to get 670 cum of stone
chips of required size.

2 90 per cent of above cost will be attributed to the production of


670 cum of stone aggregate and balance 10 per cent will be for
smaller size aggregates and stone dust which comes out as a by-
product.

3 The integrated stone crusher includes primary and secondary


crushing units.

1 - 151
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

1.14 Crushing of Stone Aggregates Nominal Size 13.2 mm as per Table


500.9 of Technical Specifications.

Crushing of stone boulders of 150 mm size in an integrated stone


crushing unit of 200 t/h capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens to obtain stone
aggregates of 13.2 mm nominal size as per Table 500.9 of Technical
Specifications including the cost of stone.

Unit = cum

Taking output = 600 cum at crusher location

a) Labour

Mate day 0.76 356.65 271.05

Mazdoor (Skilled) day 2.00 356.65 713.30

Mazdoor (Unskilled) day 17.00 244.56 4,157.52

b) Material

Stone Boulder of size 150 mm and below cum 800.00 1,055.00 844,000.00

c) Machinery

Integrated stone crusher of 200 t/h including belt conveyor and hour 6.00 14,389.00 86,334.00
vibrating screens

Front end loader 1 cum bucket capacity hour 10.00 1,341.00 13,410.00

Tipper 5.5 cum capacity hour 10.00 850.00 8,500.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 119,673.23

e) Add GST, LWC etc. @ 0 on (a+b+c) -

Cost for 600 cum = (a+b+c+d+e+f) x 0.95 1,023,206.15

Rate per cum = [(a+b+c+d+e+f) x 0.95]/ 600 1,705.00

Note: 1 800 cum of stone boulders are needed to get 600 cum of stone
chips of size 13.2 mm and 125 cum stone dust.

2 95 per cent of above cost will be attributed to the production of


600 cum of stone chips of 13.2 mm size and balance 5 per cent to
the production of stone dust which comes out as a by-product.

3 The integrated stone crusher includes primary and secondary


crushing units.

4 The analysis for curshing of stone chips of size 11.2 mm will be


same as for 13.2 mm

1.15 Crushing of Stone Aggregates 9.5 mm Nominal Size as per Table


500.9 of Technical Specifications.

Crushing of stone boulders of 150 mm size in an integrated stone


crushing unit of 200 t/h capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens to obtain stone
aggregates of 9.5 mm nominal size as per Table 500.9 of Technical
Specifications including the cost of stone.

Unit = cum

Taking output = 600 cum at crusher location

a) Labour

Mate day 0.76 356.65 271.05

Mazdoor (Skilled) day 2.00 356.65 713.30

Mazdoor (Unskilled) day 17.00 244.56 4,157.52

b) Material

Stone Boulder of size 150 mm and below cum 800.00 1,055.00 844,000.00

c) Machinery

Integrated stone crusher of 200 t/h including belt conveyor and hour 6.00 14,389.00 86,334.00
vibrating screens

1 - 152
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

Front end loader 1 cum bucket capacity hour 10.00 1,341.00 13,410.00

Tipper 5.5 cum capacity hour 10.00 850.00 8,500.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 119,673.23

e) Add GST, LWC etc. @ 0 on (a+b+c) -

Cost for 600 cum = (a+b+c+d+e+f) x 0.95 1,023,206.15

Rate per cum = [(a+b+c+d+e) x 0.95]/ 600 1,705.00

Note: 1 800 cum of stone boulders are needed to get 600 cum of stone
chips of size 9.5 mm and 125 cum stone dust.

2 95 per cent of above cost will be attributed to the production of


600 cum of stone chips of 9.5 mm size and balance 5 per cent to
the production of stone dust which comes out as a by-product.

3 The integrated stone crusher includes primary and secondary


crushing units.

4 Cost of crushing of stone chips of size 6.7 mm will be 10 per cent


extra over that of 9.5 mm size.

1.16 100 Setting Out

Unit = 1 km

The analysis of rate per km shall account for the following:

(i) Reference benchmark one no.

(ii) Working benchmark 4 nos. per km and near all drainage structure
and bridges
(iii) Reference Pillars/Burjees @ 50 m interval on both sides of the
formation width

(iv) The marking of centre line setting out curves and recording of
levels, etc. by the surveyor will be incidental to the work and no
extra payment shall be made for the same

(v) The rate analysis for a typical benchmark as per Drawing 200.1

1. Excavation for structure earthwork in excavation for


foundations as per drawing and technical specification
including dressing of sides and bottom and backfilling in
ordinary soil.

As per item No.11.1 of Chapter 11 cum 0.325 102.00 33.15

2. Plain cement concrete M10 (1:3:6) nominal mix in levelling


course below open foundation as per drawing and technical
specification.

As per item No.11.4 of Chapter 11 cum 0.10 5,216.59 521.66

3. Brick masonry work in cement mortar 1:3 in foundation


complete excluding pointing and plastering as per drawing
and technical specification.

As per item No.11.5 of Chapter 11 cum 0.475 6,672.76 3,169.56

4. Plastering with cement mortar 1:4, 15 mm thick cement


plaster on brick work as per technical specifications.

As per item No.12.3 of Chapter 12 sqm 2.63 1,211.68 3,186.71

Note: Add 5 per cent cost of items No.1 to 4 for white washing, lettering and 6,911.08
painting, etc.

Refer to Figure 200.1. of Standard Data Book

1 - 153
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

(vi) The rate analysis for a typical reference pillar as per Drawing 200.2

1. Excavation for structure earthwork in excavation for


foundations as per drawing and technical specification
including dressing of sides and bottom and backfilling in
ordinary soil.

As per item No.11.1 of Chapter 11 cum 0.192 102.00 19.58

2. Plain cement concrete M10 (1:3:6) nominal mix in levelling


course below open foundation as per drawing and technical
specification.

As per item No.11.4 of Chapter 11 cum 0.06 5,216.59 313.00

3. Brick masonry work in cement mortar 1:3 in foundation


complete excluding pointing and plastering as per drawing
and technical specification.

As per item No.11.5 of Chapter 11 cum 0.193 6,672.76 1,287.84

4. Plastering with cement mortar 1:4, 15 mm thick cement


plaster on brick work as per technical specifications.

As per item No.12.3 of Chapter 12 sqm 1.50 1,211.68 1,817.52

Note: Add 5 per cent cost of items No.1 to 4 for white washing, lettering and 3,437.94
painting, etc.

Refer to Figure 200.2 of Standard Data Book

Note: The cross-section height and material for the Reference Benchmark,
Working Benchmark and Reference Pillars shall be decided depending
upon site conditions and availability of construction material. The cost
thereof shall be worked out based on rates of relevant items of work to
be picked up from relevant chapters of this book

1 - 154
Chapter 2

SITE CLEARANCE
Sr. Reference to
Description Unit Quantity
No. MORD Spec
2.1 201 Clearing Grass and Removal of Rubbish

Clearing grass and removal of rubbish up to a distance of 30 m


outside the periphery of the area as per Technical Specification
Clause 201.

By Manual Means

Unit = hectare

Taking output = 1 hectare

a) Labour

Mate day 1.60

Mazdoor (Unskilled) day 40.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Rate per hectare = a+b+c

2.2 201 Clearing and Grubbing Road Land

Clearing and grubbing road land including uprooting wild


vegetation, grass, bushes, shrubs, saplings and trees of girth
upto 300 mm, removal of stumps of such trees cut earlier and
disposal of unserviceable materials and stacking of serviceable
material to be used or auctioned, upto a lead of 1000 m including
removal and disposal of top organic soil not exceeding 150 mm
in thickness as per Technical Specification Clause 201.

Unit = hectare

Taking output = 1 hectare

(I) By Manual Means

(A) In area of non-thorny jungle

a) Labour

Mate day 8.00

Mazdoor (Unskilled) day 140.00

b) Machinery

Tractor with trolley hour 2.00

2 - 155
Sr. Reference to
Description Unit Quantity
No. MORD Spec
c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per hectare = a+b+c+d+e

(B) In area of thorny jungle

a) Labour

Mate day 8.00

Mazdoor (Unskilled) day 195.00

b) Machinery

Tractor with trolley hour 2.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add( VAT 5%+Labour welfare cess1%)@ 6% on a+b+c

Rate per hectare = a+b+c+d

(II) By Mechanical Means

(A) In area of non-thorny jungle

a) Labour

Mate day 0.16

Mazdoor (Unskilled) day 4.00

b) Machinery

Dozer D 50 with attachment or suitable hour 10.00


machinery for removal of trees & stumps

Tractor with Trolley hour 1.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per hectare = a+b+c+d

(B) In area of thorny jungle

a) Labour

2 - 156
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mate day 0.24

Mazdoor (Unskilled) day 6.00

b) Machinery

Dozer D 50 with attachment for removal of trees hour 12.00


& stumps

Tractor with trolley hour 1.50

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per hectare = a+b+c+d+e

Note: The top soil removed during clearing and grubbing of site, if
suitable for re-use shall be transported, conserved and stacked
as directed by the Engineer and shall be incidental to the work.

2.3 201 Cutting of Trees including Cutting of Trunks, Branches and


Removal of Stumps

Cutting of trees, including cutting of trunks, branches and


removal of stumps & roots, refilling, compaction of backfilling and
stacking of serviceable material by manual means with all lifts as
per Technical Specification Clause 201.

A. Lead upto 100 m

Unit = each

(i) Girth above 300 mm to 600 mm

a) Labour

Mate day 0.024

Mazdoor (Unskilled) day 0.60

b) Machinery

Tractor with trolley hour 0.07

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+cd+e

(ii) Girth above 600 mm to 900 mm

2 - 157
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Labour

Mate day 0.036

Mazdoor (Unskilled) day 0.90

b) Machinery

Tractor with trolley hour 0.21

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+c+d

(iii) Girth above 900 mm to 1800 mm

a) Labour

Mate day 0.08

Mazdoor (Unskilled) day 2.00

b) Machinery

Tractor with trolley hour 0.28

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+c+d+e

(iv) Girth above 1800 mm to 2700 mm

a) Labour

Mate day 0.16

Mazdoor (Unskilled) day 4.00

b) Machinery

Tractor with trolley hour 0.42

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

2 - 158
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate for each tree = a+b+c+d+e

(v) Girth above 2700 mm to 4500 mm

a) Labour

Mate day 0.32

Mazdoor (Unskilled) day 8.00

b) Machinery

Tractor with trolley hour 1.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+c+d+e

(vi) Girth above 4500 mm

a) Labour

Mate day 1.00

Mazdoor (Unskilled) day 25.00

b) Machinery

Tractor with trolley hour 2.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+c+d+e

B. Lead upto 1000 m

Unit = each

(i) Girth above 300 mm to 600 mm

a) Labour

Mate day 0.024

Mazdoor (Unskilled) day 0.60

b) Machinery

2 - 159
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Tractor with trolley hour 0.10

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+c+d+e

(ii) Girth above 600 mm to 900 mm

a) Labour

Mate day 0.036

Mazdoor (Unskilled) day 0.90

b) Machinery

Tractor with trolley hour 0.30

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+c+d+e

(iii) Girth above 900 mm to 1800 mm

a) Labour

Mate day 0.08

Mazdoor (Unskilled) day 2.00

b) Machinery

Tractor with trolley hour 0.40

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+c+d+e

(iv) Girth above 1800 mm to 2700 mm

a) Labour

Mate day 0.16

2 - 160
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Unskilled) day 4.00

b) Machinery

Tractor with trolley hour 0.60

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+c+d+e

(v) Girth above 2700 mm to 4500 mm

a) Labour

Mate day 0.32

Mazdoor (Unskilled) day 8.00

b) Machinery

Tractor with trolley hour 1.20

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+c+d+e

(vi) Girth above 4500 mm

a) Labour

Mate day 1.00

Mazdoor (Unskilled) day 25.00

b) Machinery

Tractor with trolley hour 2.50

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each tree = a+b+c+d+e

2.4 201 Uprooting and Removing Stumps & Roots

2 - 161
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Uprooting and Removing Stumps & roots, compaction of
backfilling and stacking of servicable material by manual means
as per Technical Specification Clause 201.

A. Lead upto 100 m

Unit = each

(i) Girth above 300 mm to 600 mm

a) Labour

Mate 0.016

Mazdoor (Unskilled) 0.40

b) Machinery

Tractor with trolley 0.018

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

(ii) Girth above 600 mm to 900 mm

a) Labour

Mate 0.024

Mazdoor (Unskilled) 0.60

b) Machinery

Tractor with trolley 0.05

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

(iii) Girth above 900 mm to 1800 mm

a) Labour

Mate 0.053

Mazdoor (Unskilled) 1.33

2 - 162
Sr. Reference to
Description Unit Quantity
No. MORD Spec
b) Machinery

Tractor with trolley 0.07

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

(iv) Girth above 1800 mm to 2700 mm

a) Labour

Mate 0.11

Mazdoor (Unskilled) 2.66

b) Machinery

Tractor with trolley 0.11

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

(v) Girth above 2700 mm to 4500 mm

a) Labour

Mate 0.21

Mazdoor (Unskilled) 5.33

b) Machinery

Tractor with trolley 0.25

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

(vi) Girth above 4500 mm

a) Labour

Mate 0.60

2 - 163
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Unskilled) 15.00

b) Machinery

Tractor with trolley 0.75

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

B. Lead upto 1000 m

Unit = each

(i) Girth above 300 mm to 600 mm

a) Labour

Mate 0.016

Mazdoor (Unskilled) 0.40

b) Machinery

Tractor with trolley 0.025

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

(ii) Girth above 600 mm to 900 mm

a) Labour

Mate 0.024

Mazdoor (Unskilled) 0.60

b) Machinery

Tractor with trolley 0.075

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

2 - 164
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate for each stump & root = a+b+c+d+e

(iii) Girth above 900 mm to 1800 mm

a) Labour

Mate 0.053

Mazdoor (Unskilled) 1.33

b) Machinery

Tractor with trolley 0.10

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

(iv) Girth above 1800 mm to 2700 mm

a) Labour

Mate 0.11

Mazdoor (Unskilled) 2.66

b) Machinery

Tractor with trolley 0.15

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

(v) Girth above 2700 mm to 4500 mm

a) Labour

Mate 0.21

Mazdoor (Unskilled) 5.33

b) Machinery

Tractor with trolley 0.30

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

2 - 165
Sr. Reference to
Description Unit Quantity
No. MORD Spec
d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

(vi) Girth above 4500 mm

a) Labour

Mate 0.60

Mazdoor (Unskilled) 15.00

b) Machinery

Tractor with trolley 1.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for each stump & root = a+b+c+d+e

2.5 202 Dismantling of Structures

Dismantling of existing structures like culverts, bridges, retaining


walls and other structure comprising of masonry, cement
concrete, wood work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with
all lifts and lead of 1000 m as per Technical Specification Clause
202.

Unit = cum

Taking output = 1.25 cum

(I) By Manual Means

(A) Lime Concrete

a) Labour

Mate day 0.04

Mazdoor (Unskilled) day 0.80

b) Machinery

Tractor with trolley hour 0.27

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

2 - 166
Sr. Reference to
Description Unit Quantity
No. MORD Spec
d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/1.25

(B) Cement Concrete

a) Labour

Mate day 0.05

Mazdoor (Unskilled) day 1.22

b) Machinery

Tractor with trolley hour 0.22

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/1.25

(C) Reinforced Cement Concrete

a) Labour

Mate day 0.15

Blacksmith day 0.25

Mazdoor (Unskilled) day 3.50

b) Machinery

Tractor with trolley hour 0.27

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c+d+e

Rate per cum = (a+b+c)/1.25

(II) By Mechanical Means

2 - 167
Sr. Reference to
Description Unit Quantity
No. MORD Spec
(A) Cement Concrete

a) Labour

Mate day 0.02

Mazdoor (Unskilled) day 0.20

b) Machinery

Air compressor 210 cfm with 2 leads of hour 0.58


pneumatic breaker @1.5 cum per hour

Tractor with trolley hour 0.27

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c+d+e

Rate per cum = (a+b+c)/1.25

(B) Reinforced Cement Concrete

a) Labour

Mate day 0.05

Mazdoor (Unskilled) day 0.91

Blacksmith day 0.25

b) Machinery

Air compressor 170-210 cfm working with 2 Jack hour 0.44


Hammers simultaneously @1.00 cum per hour

Tractor with trolley hour 0.27

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c+d+e

Rate per cum = (a+b+c)/1.25

2.6 202 Dismantling Brick/Tile Work

2 - 168
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Dismantling of existing structures like culverts, bridges, retaining
walls and other structures comprising of brick masonry, including
disposal of unserviceable material and stacking the serviceable
material with all lift and lead of 1000 m as per Technical
Specification Clause 202.

Unit = cum

Taking output = 1.25

(A) Lime mortar

a) Labour

Mate day 0.02

Mazdoor (Unskilled) day 0.30

b) Machinery

Tractor with trolley hour 0.27

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e) /1.25

(B) Cement mortar

a) Labour

Mate day 0.03

Mazdoor (Unskilled) day 0.55

b) Machinery

Tractor with trolley hour 0.26

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c

Rate per cum = (a+b+c)/1.25

(C) Mud Mortar

2 - 169
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Labour

Mate day 0.016

Mazdoor (Unskilled) day 0.25

b) Machinery

Tractor with trolley hour 0.26

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c+d+e

Rate per cum = (a+b+c)/1.25

(D) Dry Brick Pitching or Brick Soling

a) Labour

Mate day 0.014

Mazdoor (Unskilled) day 0.20

b) Machinery

Tractor with trolley hour 0.26

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c+d+e

Rate per cum = (a+b+c)/1.25

2.7 202 Dismantling Stone Masonry as per Technical Specification


Clause 202.

Dismantling of existing structures like culverts, bridges, retaining


walls and other structure comprising of stone masonry, including
disposal of unserviceable material and stacking the serviceable
material with all lift and lead of 1000 m as per Technical
Specification Clause 202.

Unit = cum

Taking ouput = 1.25 cum

2 - 170
Sr. Reference to
Description Unit Quantity
No. MORD Spec
(A) Rubble Stone Masonry in Lime Mortar

a) Labour

Mate day 0.024

Mazdoor (Unskilled) day 0.60

b) Machinery

Tractor with trolley hour 0.22

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c+d+e

Rate per cum = (a+b+c)/1.25

(B) Rubble Stone Masonry in Cement Mortar

a) Labour

Mate day 0.03

Mazdoor (Unskilled) day 0.30

b) Machinery

Tractor with trolley hour 0.27

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c

Rate per cum = (a+b+c)/1.25

(C) Rubble Stone Masonry in Mud Mortar

a) Labour

Mate day 0.02

Mazdoor (Unskilled) day 0.30

b) Machinery

Tractor with trolley hour 0.27

2 - 171
Sr. Reference to
Description Unit Quantity
No. MORD Spec
c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c

Rate per cum = (a+b+c)/1.25

(D) Dry Rubble Masonry

a) Labour

Mate day 0.018

Mazdoor (Unskilled) day 0.25

b) Machinery

Tractor with trolley hour 0.27

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c

Rate per cum = (a+b+c)/1.25

(E) Dismantling Stone Pitching / Dry Stone Spalls

a) Labour

Mate day 0.016

Mazdoor (Unskilled) day 0.30

b) Machinery

Tractor with trolley hour 0.24

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c

Rate per cum = (a+b+c)/1.25

2 - 172
Sr. Reference to
Description Unit Quantity
No. MORD Spec
(F) Dismantling boulders laid in wire crates including
opening of crates and stacking dismantled materials

a) Labour

Mate day 0.02

Mazdoor (Unskilled) day 0.50

b) Machinery

Tractor with trolley hour 0.22

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c

Rate per cum = (a+b+c)/1.25

2.8 202 Dismantling Wood Work Wrought and Planed Fixed in


Frames of Trusses upto a height of 5 m above Plinth Level
as per Technical Specification Clause 202.

Unit = cum

Taking output = 1.25 cum

a) Labour

Mate day 0.06

Carpenter 1st Class day 0.50

Mazdoor (Unskilled) day 0.88

b) Machinery

Tractor with trolley hour 0.27

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1.25 cum = a+b+c

Rate per cum = (a+b+c)/1.25

2 - 173
Sr. Reference to
Description Unit Quantity
No. MORD Spec
2.9 202 Dismantling Steel Work in all Types of Sections upto a
height of 5 m above Plinth Level excluding Cutting of rivet
as per Technical Specification Clause 202.

Unit = t

Taking output = 1

(A) Including dismembering

a) Labour

Mate day 0.14

Blacksmith day 1.00

Mazdoor (Unskilled) day 2.50

Add 2.5 per cent of cost of labour for gas cutting,


ropes, pulleys, etc.

b) Machinery

Tractor with trolley hour 0.17

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per t = a+b+c+d+e

(B) Excluding dismembering

a) Labour

Mate day 0.10

Mazdoor (Unskilled) day 2.00

Blacksmith day 0.50

Add 2.5 per cent of cost of labour for gas cutting,


ropes, pulleys, etc.

b) Machinery

Tractor with trolley hour 0.17

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

2 - 174
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate per t = a+b+c+d+e

(C) Extra over Items (A) and (B) for cutting rivets

Unit = each

Taking output = 10 rivets

a) Labour

Mate day 0.01

Blacksmith day 0.13

Mazdoor (Unskilled) day 0.13

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 rivets = a+b+c

Rate for each rivet = (a+b+c) /10

2.10 202 Scraping of bricks dismantled from brick work including


stacking as per Technical Specification Clause 202.

Unit = Nos.

Taking output = 1000 Nos.

In Lime/ Cement Mortar

a) Labour

Mate day 0.14

Mazdoor (Unskilled) day 3.50

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Rate per 1000 Nos. = a+b+c+d

2.11 202 Scraping of Stone from Dismantled Stone Masonry as per


Technical Specification Clause 202.

Unit = cum

Taking output = 1 cum

2 - 175
Sr. Reference to
Description Unit Quantity
No. MORD Spec
In Cement or Lime Mortar

a) Labour

Mate day 0.06

Mazdoor (Unskilled) day 1.40

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Rate per cum = a+b+c+d

2.12 202 Scraping Plaster in Lime or Cement Mortar from Brick /


Stone Masonry as per Technical Specification Clause 202.

Unit = sqm

Taking ouput = 100 sqm

a) Labour

Mate day 0.16

Mazdoor (Unskilled) day 4.00

b) Machinery

Tractor with trolley hour 0.32

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 100 sqm = a+b+c+d

Rate per sqm = (a+b+c+d)/100

2.13 202 Removing all types of Hume pipes and stacking within a lead
of 1000 m including Earthwork and Dismantling of Masonry
Works as per Technical Specification Clause 202.

Unit = m

Taking output = 1m

(A) Upto 600 mm dia Hume pipe

a) Labour

2 - 176
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mate day 0.02

Mazdoor (Unskilled) day 0.52

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Rate per m = a+b+c+d

(B) Above 600 mm to 900 mm dia Hume pipe

a) Labour

Mate day 0.03

Mazdoor (Unskilled) day 0.70

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Rate per m = a+b+c+d

(C) Above 900 mm dia Hume pipe

a) Labour

Mate day 0.05

Mazdoor (Unskilled) day 1.20

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Rate per m = a+b+c+d

Note: 1 The excavation of earth, dismantling of stone masonry


work in head walls and protection works is not included
which is to be measured and paid separately.

2 Credit for retrieved stone from masonry work may be taken


as per actual availability.

2.14 202 Dismantling of Flexible Pavements

2 - 177
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Dismantling of flexible pavements and disposal of dismantled
materials upto a lead of 100 m, stacking serviceable and
unserviceable materials separately as per Technical Specification
Clause 202

Unit = cum

Taking output = 1 cum

(I) By Manual Means

(A) Bituminous Courses

a) Labour

Mate day 0.06

Mazdoor (Unskilled) day 1.21

b) Machinery

Tractor with trolley hour 0.38

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

(B) Granular Courses

a) Labour

Mate day 0.04

Mazdoor (Unskilled) day 0.80

b) Machinery

Tractor with trolley hour 0.33

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

(II) By Mechanical Means

(A) Bituminous Courses

2 - 178
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Labour

Mate day 0.01

Mazdoor (Unskilled) day 0.25

b) Machinery

Tractor with trolley hour 0.32

Tractor with ripper @ 60 cum per hour hour 0.013

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

2.15 202 Dismantling of Cement Concrete Pavements as per


Technical Specification Clause 202.

Dismantling of cement concrete pavements by mechanical


means using pneumatic tools breaking to pieces not exceeding
0.02 cum in volume and stock piling at designated locations and
disposal of dismantled materials upto a lead of 1000 m, stacking
serviceable and unserviceable materials separately

Unit = cum

Taking output = 1 cum

a) Labour

Mate day 0.03

Mazdoor (Semi-skilled) day 0.50

Mazdoor (Unskilled) day 0.50

b) Machinery

Air compressor 210 cfm with two leads for pneumatic hour 0.71
cutters / hammers @ 1 cum per hour

Tractor with trolley hour 0.40

Joint Cutting Machine with 2-3 blades hour 1.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

2 - 179
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Rate per cum = a+b+c+d+e

Note: The above analysis is for removal of complete pavement. In


case full depth repair work is required to be done after
dismantling, provision of a concrete saw cutter may be added for
0.25h.

2.16 202 Dismantling Guard Rails

Dismantling guard rails by manual means and disposal of


dismantled material with all lifts and upto a lead of 1000 m,
stacking serviceable materials and unserviceable materials
separately as per Technical Specification Clause 202.

Unit = running m

Taking Output = 1 m

a) Labour

Mate day 0.006

Mazdoor (Unskilled) day 0.12

b) Machinery

Tractor with trolley hour 0.05

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per m = a+b+c+d+e

2.17 202 Dismantling Kerb Stones

Dismantling kerb stones by manual means and disposal of


dismantled material with all lifts and upto a lead of 1000 m as per
Technical Specification Clause 202.

Unit = running m

Taking output = 10 m

a) Labour

Mate day 0.006

Mazdoor (Unskilled) day 0.12

b) Machinery

2 - 180
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Tractor with trolley hour 0.17

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost of 10 m = a+b+c+d+e

Rate per m = (a+b+c)/10

2.18 202 Dismantling Kerb Stone Channels

Dismantling kerb stone channels by manual means and disposal


of dismantled material with all lifts and upto a lead of 1000 m as
per Technical Specification Clause 202.

Unit = running m

Taking output = 10 m

a) Labour

Mate day 0.013

Mazdoor (Unskilled) day 0.200

b) Machinery

Tractor with trolley hour 0.25

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost of 10 m = a+b+c+d+e

Rate per m = (a+b+c)/10

2.19 202 Dismantling Kilometre Stones

Dismantling of kilometre stones including cutting of earth,


foundation and disposal of dismantled material with all lifts and
lead upto 1000 m and backfilling of pit as per Technical
Specification Clause 202.

Unit = each

Taking output = 1 km stone

(A) 5th km Stone

2 - 181
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Quantity of cement concrete = 0.392 cum

a) Labour

Mate day 0.03

Mazdoor (Unskilled) day 0.75

b) Machinery

Tractor with trolley hour 0.15

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for one 5th km stone = a+b+c+d+e

(B) Ordinary km Stones

Quantity of cement concrete = 0.269 cum

a) Labour

Mate day 0.02

Mazdoor (Unskilled) day 0.50

b) Machinery

Tractor with trolley hour 0.08

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for one ordinary km stone = a+b+c+d+e

(C) 200 m Stones

Quantity of cement concrete = 0.048 cum

a) Labour

Mate day 0.004

Mazdoor (Unskilled) day 0.09

b) Machinery

Tractor with trolley hour 0.02

2 - 182
Sr. Reference to
Description Unit Quantity
No. MORD Spec
c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate for one 200 m stone = a+b+cd+e

Note: Rate for boundary pillar will be same as that of 200 m stone

2.20 202 Dismantling of Fencing

Dismantling of barbed wire fencing / wire mesh fencing including


posts, foundation concrete, backfilling of pit by manual means
including disposal of dismantled material with all lifts and upto a
lead of 1000 m, stacking serviceable material and unserviceable
material separately as per Technical Specification Clause 202.

Unit = running m

Taking output = 30 m

a) Labour

Mate day 0.15

Mazdoor (Unskilled) day 3.00

Blacksmith day 0.75

b) Machinery

Tractor with trolley hour 0.15

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost of 30 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/30

2.21 202 Dismantling of CI Water Pipe Line

Dismantling of CI water pipe line 600 mm dia including disposal


with all lifts and lead upto 1000 m and stacking of serviceable
material and unserviceable material separately under supervision
of concerned department as per Technical Specification Clause
202.

Unit = running m

Taking output = 10 m

2 - 183
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Labour

Mate day 0.09

Mazdoor (Unskilled) day 2.00

Plumber day 0.21

b) Machinery

Truck 10 t capacity hour 0.25

Crane upto 8 t capacity hour 0.24

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/10

Note: The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and
paid separately.

2.22 202 Removal of Cement Concrete Pipe of Sewer Gutter

Removal of cement concrete pipe of sewer gutter 1500 mm dia


under the supervision of concerned department including
disposal with all lifts and upto a lead of 1000 m and stacking of
serviceable and unserviceable material separately but excluding
earth excavation and dismantling of masonry works as per
Technical Specification Clause 202.

Unit = running m

Taking output = 10 m

a) Labour

Mate day 0.10

Mazdoor (Unskilled) day 2.50

b) Machinery

Crane upto 8 t capacity hour 0.30

Truck flat body 10 t hour 1.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

2 - 184
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Cost for 10 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/10

Note: The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and
paid separately.

2.23 202 Removal of Telephone/Electric Poles and Lines

Removal of telephone/electric poles with wires including


excavation and dismantling of foundation concrete and lines
under the supervision of concerned department, disposal with all
lifts and upto a lead of 1000 m and stacking the serviceable and
unserviceable material separately as per Technical Specification
Clause 202.

Unit = each

Taking output = 30 Nos.

a) Labour

Mate day 0.48

Mazdoor (Unskilled) day 10.00

Electrician/Lineman day 2.00

b) Machinery

Tractor with trolley hour 1.20

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 30 poles = a+b+c+d+e

Rate per pole = (a+b+c+d+e)/30

2 - 185
Chapter 2

SITE CLEARANCE
Rate Amount
(Rs.) (Rs.)

356.65 570.64

244.56 9,782.40

1,294.13

11,647.17

356.65 2,853.20

244.56 34,238.40

409.00 818.00

2 - 186
Rate Amount
(Rs.) (Rs.)
4,738.70

42,648.30

356.65 2,853.20

244.56 47,689.20

409.00 818.00

6,420.05

3,466.83

61,247.28

356.65 57.06

244.56 978.24

1,965.00 19,650.00

409.00 409.00

2,629.66

23,723.96

2 - 187
Rate Amount
(Rs.) (Rs.)
356.65 85.60

244.56 1,467.36

1,965.00 23,580.00

409.00 613.50

3,207.61

28,954.06

356.65 8.56

244.56 146.74

409.00 28.63

22.99

206.92

2 - 188
Rate Amount
(Rs.) (Rs.)

356.65 12.84

244.56 220.10

409.00 85.89

39.85

358.69

356.65 28.53

244.56 489.12

409.00 114.52

79.02

711.19

356.65 57.06

244.56 978.24

409.00 171.78

150.89

2 - 189
Rate Amount
(Rs.) (Rs.)
1,357.97

356.65 114.13

244.56 1,956.48

409.00 409.00

309.95

2,789.56

356.65 356.65

244.56 6,114.00

409.00 818.00

911.08

8,199.73

356.65 8.56

244.56 146.74

2 - 190
Rate Amount
(Rs.) (Rs.)
409.00 40.90

24.52

220.72

356.65 12.84

244.56 220.10

409.00 122.70

44.46

400.10

356.65 28.53

244.56 489.12

409.00 163.60

85.16

766.41

356.65 57.06

2 - 191
Rate Amount
(Rs.) (Rs.)
244.56 978.24

409.00 245.40

160.09

1,440.79

356.65 114.13

244.56 1,956.48

409.00 490.80

320.18

2,881.58

356.65 356.65

244.56 6,114.00

409.00 1,022.50

936.64

8,429.79

2 - 192
Rate Amount
(Rs.) (Rs.)

356.65 5.71

244.56 97.82

409.00 7.36

13.86

124.75

356.65 8.56

244.56 146.74

409.00 20.45

21.97

197.71

356.65 18.90

244.56 325.26

2 - 193
Rate Amount
(Rs.) (Rs.)

409.00 28.63

46.60

419.40

356.65 39.23

244.56 650.53

409.00 44.99

91.84

826.59

356.65 74.90

244.56 1,303.50

409.00 102.25

185.08

1,665.73

356.65 213.99

2 - 194
Rate Amount
(Rs.) (Rs.)
244.56 3,668.40

409.00 306.75

523.64

4,712.78

356.65 5.71

244.56 97.82

409.00 10.23

14.22

127.97

356.65 8.56

244.56 146.74

409.00 30.68

23.25

2 - 195
Rate Amount
(Rs.) (Rs.)
209.22

356.65 18.90

244.56 325.26

409.00 40.90

48.13

433.20

356.65 39.23

244.56 650.53

409.00 61.35

93.89

845.00

356.65 74.90

244.56 1,303.50

409.00 122.70

187.64

2 - 196
Rate Amount
(Rs.) (Rs.)
-

1,688.74

356.65 213.99

244.56 3,668.40

409.00 409.00

536.42

4,827.81

356.65 14.27

244.56 195.65

409.00 110.43

40.04

2 - 197
Rate Amount
(Rs.) (Rs.)
-

360.39

288.31

356.65 17.83

244.56 298.36

409.00 89.98

50.77

456.95

365.56

356.65 53.50

458.55 114.64

244.56 855.96

409.00 110.43

141.82

1,222.84

978.27

2 - 198
Rate Amount
(Rs.) (Rs.)

356.65 7.13

244.56 48.91

435.00 252.30

409.00 110.43

52.35

471.12

376.90

356.65 17.83

244.56 222.55

458.55 114.64

435.00 191.40

409.00 110.43

82.11

738.96

591.16

2 - 199
Rate Amount
(Rs.) (Rs.)

356.65 7.13

244.56 73.37

409.00 110.43

23.87

214.80

171.84

356.65 10.70

244.56 134.51

409.00 106.34

31.44

282.99

226.39

2 - 200
Rate Amount
(Rs.) (Rs.)

356.65 5.71

244.56 61.14

409.00 106.34

21.65

194.83

155.87

356.65 4.99

244.56 48.91

409.00 106.34

20.03

180.28

144.22

2 - 201
Rate Amount
(Rs.) (Rs.)

356.65 8.56

244.56 146.74

409.00 89.98

30.66

275.94

220.75

356.65 10.70

244.56 73.37

409.00 110.43

24.31

218.81

175.05

356.65 7.13

244.56 73.37

409.00 110.43

2 - 202
Rate Amount
(Rs.) (Rs.)
23.87

214.80

171.84

356.65 6.42

244.56 61.14

409.00 110.43

22.25

200.24

160.19

356.65 5.71

244.56 73.37

409.00 98.16

22.15

199.39

159.51

2 - 203
Rate Amount
(Rs.) (Rs.)

356.65 7.13

244.56 122.28

409.00 89.98

27.42

246.82

197.45

356.65 21.40

458.55 229.28

244.56 215.21

409.00 110.43

72.04

626.96

501.57

2 - 204
Rate Amount
(Rs.) (Rs.)

356.65 49.93

458.55 458.55

244.56 611.40

28.00

409.00 69.53

152.18

1,341.59

356.65 35.67

244.56 489.12

458.55 229.28

18.85

409.00 69.53

105.31

2 - 205
Rate Amount
(Rs.) (Rs.)
947.75

356.65 3.57

458.55 59.61

244.56 31.79

11.87

106.84

10.68

356.65 49.93

244.56 855.96

113.24

1,019.13

2 - 206
Rate Amount
(Rs.) (Rs.)

356.65 21.40

244.56 342.38

45.47

0.00

409.26

356.65 57.06

244.56 978.24

409.00 130.88

145.77

0.00

1,311.96

13.12

2 - 207
Rate Amount
(Rs.) (Rs.)
356.65 7.13

244.56 127.17

16.79

151.09

356.65 10.70

244.56 171.19

22.74

204.63

356.65 17.83

244.56 293.47

38.91

350.22

2 - 208
Rate Amount
(Rs.) (Rs.)

356.65 21.40

244.56 295.92

409.00 155.42

59.09

531.83

356.65 14.27

244.56 195.65

409.00 134.97

43.11

387.99

2 - 209
Rate Amount
(Rs.) (Rs.)

356.65 3.57

244.56 61.14

409.00 130.88

440.00 5.72

25.16

226.47

356.65 10.70

285.32 142.66

244.56 122.28

435.00 308.85

409.00 163.60

150.00 150.00

112.26

0.00

2 - 210
Rate Amount
(Rs.) (Rs.)

1,010.35

356.65 2.14

244.56 29.35

409.00 20.45

6.49

0.00

58.43

356.65 2.14

244.56 29.35

2 - 211
Rate Amount
(Rs.) (Rs.)
409.00 69.53

12.63

0.00

113.64

11.36

356.65 4.64

244.56 48.91

409.00 102.25

19.47

0.00

175.27

17.53

2 - 212
Rate Amount
(Rs.) (Rs.)

356.65 10.70

244.56 183.42

409.00 61.35

31.93

0.00

287.40

356.65 7.13

244.56 122.28

409.00 30.68

20.01

0.00

180.10

356.65 1.43

244.56 22.01

409.00 8.18

2 - 213
Rate Amount
(Rs.) (Rs.)
3.95

0.00

35.57

356.65 53.50

244.56 733.68

458.55 343.91

409.00 61.35

149.06

0.00

1,341.50

44.72

2 - 214
Rate Amount
(Rs.) (Rs.)

356.65 32.10

244.56 489.12

458.55 96.30

825.00 206.25

685.00 164.40

123.52

0.00

1,111.68

111.17

356.65 35.67

244.56 611.40

685.00 205.50

825.00 825.00

209.70

0.00

2 - 215
Rate Amount
(Rs.) (Rs.)

1,887.26

188.73

356.65 171.19

244.56 2,445.60

458.55 917.10

409.00 490.80

503.09

0.00

4,527.78

150.93

2 - 216
Chapter 3

EARTHWORK, EROSION CONTROL AND DRAINAGE


Sr. Reference to
Description Unit Quantity
No. MORD Spec
3.1 Preparation of Foundation for Embankment

A 301.4 Scarifying Existing Granular Surface to a Depth of 50 mm by


Manual Means

Scarifying existing granular surface to a depth of 50 mm and


disposal of scarified material with a lift upto 3 m and leads upto
1000 m as per Technical Specification Clause 301.4.

Unit = sqm

Taking output = 100 sqm

a) Labour

Mate day 0.16

Mazdoor (Unskilled) day 4.00

b) Machinery

Tractor with trolley hour 1.50

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 100 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d+e)/100

B 301.4 Scarifying Existing Granular Surface to a Depth of 50 mm by


Mechanical Means

Scarifying existing granular surface to a depth of 50 mm and


disposal of scarified material with a lift upto 3 m and leads upto
1000 m as per Technical Specification Clause 301.4.

Unit = sqm

Taking output = 100 sqm

a) Labour

Mate day 0.01

Mazdoor (Unskilled) day 0.25

b) Machinery

Tractor with trolley hour 0.90

3 - 217
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Front end-loader 1 cum bucket capacity @ 45 cum/hour hour 0.15

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 100 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d+e)/100

Note: In case material is to be reused at site, transportation cost catered


above (Sub-item b) for disposal shall be deleted.

3.2 Preparation of Foundation for Embankment

301.4 Scarifying Existing Bituminous Surface to a Depth of 150 mm


by Mechanical Means

Scarifying the existing bituminous road surface to a depth of 150


mm and disposal of scarified material with a lift upto 3 m and lead
upto 1000 m as per Technical Specification Clause 301.4.

Unit = sqm

Taking output = 100 sqm

a) Labour

Mate day 0.01

Mazdoor (Unskilled) day 0.18

b) Machinery

Tractor with ripper attachment @ 60 cum per hour hour 0.20

Front end loader 1 cum bucket capacity @ 50 cum per hour hour 0.20

Tipper 5.5 cum capacity, 4 trips per hour hour 0.20

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 100 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d+e)/100

3.3 301.5 Construction of Embankment with Material Obtained from


Roadway Cutting

3 - 218
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Construction of embankment with approved materials deposited
at site from roadway cutting and excavation from drain and
foundation of other structures graded and compacted to meet
requirement of Tables 300.1 and 300.2 as per Technical
Specification Clause 301.5

Unit = cum

Taking output = 100 cum

a) Labour

Mate day 0.02

Mazdoor (Unskilled) day 0.50

b) Machinery

Dozer D-50 for spreading @ 200 cum per hour hour 0.50

Motor grader for grading @ 200 cum per hour hour 4.00

Water tanker 6 kl capacity hour 2.00

Three wheel 80-100 kN Static Roller hour 1.25

c) Material

Water kl 12.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate for 100 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/100

Note: In case the earth cutting is done by dozer and pushed for filling in
the embankment, the input of dozer in the cost of embankment
shall be deleted as the same is already provided in the cost of
excavation. However, if the earth is dumped by tippers from
roadway cutting, the input of dozer for spreading is required to be
provided.

3.4 301.5 Construction of Embankment with Material Obtained from


Borrow Pits

Construction of embankment with approved material obtained


from borrow pits with a lift upto 1.5 m, transporting to site,
spreading, grading to required slope and compacting to meet
requirement of Tables 300.1 and 300.2 with a lead upto 1000 m
as per Technical Specification Clause 301.5

Unit = cum

3 - 219
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Taking output = 100 cum

a) Labour

Mate day 0.04

Mazdoor (Unskilled) day 1.00

b) Machinery

Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum per hour 1.67
hour

Tipper 5.5 cum with 10 t capacity hour 4.50

Loading & unloading of earth cum 100.00

Dozer D-50 for spreading @ 200 cum per hour hour 0.50

Motor grader for grading @ 200 cum per hour hour 0.50

Water tanker 6 kl capacity hour 2.00

Three wheel 80-100 kN Static Roller @ 80 cum per hour hour 1.25

c) Material

Water kl 12.00

Compensation for earth taken from private land/ Forest Royal cum 100.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 100 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/100

ii From Govt. land

Note: Compensation for earth will vary from place to place and will have
to be assessed realistically as per particular ground situation. In
case earth is available from Govt. land, compensation for earth
will not be required. The position is required to be clearly stated
in the cost estimate.

3.5 302 (i) Excavation in Cutting in Soil by manual means with


lead upto 50 m
Excavation for roadway in soil using manual means for
carrying of cut earth to embankment site with a lift upto 1.5
m and lead upto 50 m as per Technical Specification Clause
302.3 (Manual should be use where machines can not be
deployed due to site condition)

3 - 220
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = cum

Taking output = 120 cum

a) Labour

Mate day 1.80

Mazdoor (Unskilled) day 45.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost of 120 cum = a+b+c+d

Rate per cum = (a+b+c+d)/120

(ii) Excavation in Soil with Dozer with lead upto 100 m

Excavation for roadway in soil by mechanical means


including cutting and pushing the earth to site of
embankment upto a distance of 100 m, including trimming
bottom and side slopes in accordance with requirements of
lines, grades and cross-sections.

Unit = cum

Taking output = 180 cum

a) Labour

Mate day 0.08

Mazdoor (Unskilled) day 2.00

b) Machinery

Dozer D-50 @ 50 cum per hour (cutting with pushing) hour 3.60

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 180 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/180

(iii) Excavation in Soil using Hydraulic Excavator and


Tippers with disposal upto 1000 m

3 - 221
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance
with requirements of lines, grades and cross-sections, and
transporting to the embankment location with a lift upto 1.5
m and lead upto 1000 m as per Technical Specification
Clause 302.3

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.08

Mazdoor (Unskilled) day 2.00

b) Machinery

Hydraulic excavator 0.9 cum bucket capacity @ 100 hour 3.60


cum per hour

Tipper 5.5 cum capacity, 4 trips per hour hour 15.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 360 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/360

3.6 302.3.6 Excavation in Marshy Soil

Excavation for roadway in marshy soil with hydraulic excavator


0.9 cum bucket capacity including cutting and loading in tippers
and disposal with a lift upto 1.5 m and lead upto 1000 m, trimming
of bottom and side slopes in accordance with requirements of
lines, grades and cross- sections as per Technical Specification
Clause 302.3.6.

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.08

Mazdoor (Unskilled) day 2.00

b) Machinery

3 - 222
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Hydraulic excavator 0.90 cum bucket capacity @ 50 cum hour 6.00
per hour

Tipper 5.5 cum capacity, 4 trips per hour. hour 12.50

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 300 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/300

3.7 302.3.11 Removal of Unsuitable Soil with Disposal upto 1000 m

Removal of unsuitable soil including excavation, loading and


disposal upto 1000 m lead but excluding compaction ground
supporting embankment subgrade replacement by suitable soil,
which shall be paid separately as per Clause 303.5.2 as per
Technical Specification Clause 302.3.11

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.08

Mazdoor day 2.00

b) Machinery

Excavator 0.90 cum bucket capacity @ 100 cum per hour hour 3.60

Tipper 5.5 cum capacity, 4 trips per hour hour 15.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 360 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/360

Note: This item does not include replacement of unsuitable soil by


suitable soil. Replacement, where required, is to be provided and
paid separately under Clause 303.5.2.

3.8 302.3.5 (i) Excavation in ordinary Rock by manual means

3 - 223
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Excavation in ordinary rock using manual means including
loading in a truck and carrying of excavated material to
embankment site with a lift upto 1.5 m and lead upto 50 m
as per Technical Specification Clause 302.3.5. (Manual
means should be use where machines can not be deployed
due to site condition)

Unit = cum

Taking output = 120 cum

Mate day 2.80

Mazdoor (Unskilled) day 70.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 120 cum = a+b+c+d

Rate per cum = (a+b+c+d)/120

(ii) Excavation in Ordinary Rock with Dozer with lead upto


100 m

Excavation for roadway in ordinary rock by deploying a


dozer D-50 including cutting and pushing the cut earth to
site of embankment upto a distance of 100 m (average lead
50 m), trimming bottom and side slopes in accordance with
the requirements of lines, grades and cross-sections with lift
upto 1.5 m.

Unit = cum

Taking output = 108 cum

a) Labour

Mate day 0.12

Mazdoor (Unskilled) day 3.00

b) Machinery

Dozer D-50 @ 50% of 100 cum per hour hour 2.16

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 108 cum = a+b+c+d+e

3 - 224
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate per cum = (a+b+c+d+e)/108

(iii) Excavation in Ordinary Rock using Hydraulic Excavator


and Tippers with disposal upto 1000 m

Excavation for roadway in ordinary rock with hydraulic


excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site with a lift
upto 1.5 m and lead upto 1000 m, trimming bottom and side
slopes in accordance with requirements of lines, grades and
cross-sections as per Technical Specification Clause
302.3.5

Unit = cum

Taking output = 240 cum

a) Labour

Mate day 0.08

Mazdoor (Unskilled) day 2.00

b) Machinery

Hydraulic Excavator 0.90 cum bucket capacity @ 40 hour 6.00


cum per hour

Tipper 5.5 cum capacity, 4 trips per hour. hour 10.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 240 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/240

3.9 302.3.5 (i) Excavation in Hard Rock (requiring blasting) with


disposal upto 1000 m

Excavation for roadway in hard rock (requiring blasting) by


drilling, blasting and breaking, trimming of bottom and side
slopes in accordance with requirements of lines, grades and
cross-sections, loading and disposal of cut rock with a lift
upto 1.5 m and leads upto 1000 m as per Technical
Specification Clause 302.3.5

Unit = cum

Taking 0utput = 180 cum

a) Labour

Mate day 0.22

3 - 225
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Unskilled) day 3.00

Driller day 2.00

Blaster day 0.25

b) Machinery

Dozer D-50 @ 30 cum per hour hour 6.00

Air compressor, 210 cfm with 2 jack hammers hour 6.00

Front end loader 1 cum bucket capacity hour 6.00

Tipper 5.5 cum capacity, 2 trips per hour hour 10.00

c) Materials

Gelatine 80 per cent kg 65.00

Electric Detonators @ 1 detonator for 2 gelatine sticks each 242.00


of 285 gm each

Credit for excavated rock found suitable for use @ cum 150.00
50 per cent quantity blasted

d) Contractor’s profit & Overheads @ 12.5% on (a+b)

e) Add GST, LWC etc. @ 0 on (a+b)

Cost for 180 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/180

Note: 1 The quality and availability of rock shall be checked before


affording credit.

2 In case some rock is issued to the contractor at site, the


item of carriage shall be reduced/restricted to that extent.

3 Credit for useful material received as per site conditions


shall be taken into account. This has been assumed to be
50 per cent for the purpose of analysis.

(ii) Excavation in Hard Rock (blasting prohibited)

Excavation for roadway in hard rock (blasting prohibited)


with rock breakers including breaking rock, loading in tippers
and disposal with a lift upto 1.5 m and lead upto 200 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross- sections as per
Technical Specification Clause 302.3.5

(A) Manual Means

3 - 226
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = cum

Taking output = 16 cum

a) Labour

Mate day 1.60

Mazdoor (Unskilled) day 16.00

Chiseller day 23.00

Blacksmith day 1.00

ContMachinery

Tipper 5.5 cum capcity, 1 trip per hour hour 2.90

Credit for excavated rock found suitable for cum 20.00


use @ 50 per cent of excavated quantity
c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 16 cum = a+b+c+d+e

Rate per cum = (a+b+c)/16

Note: 1 Credit is considered for 50 per cent of quantity of work.

2 Loading for disposal will be done manually, being small


quantity.

3 In case some rock is issued to contractor at site, the item of


carriage shall be omitted to the extent of quantity issued to
the Contractor.

(B) Mechanical Means

Unit = cum

Taking output = 36 cum

a) Labour

Mate day 0.35

Mazdoor (Unskilled) day 10.00

b) Machinery

Hydraulic excavator 0.9 cum with rock breaker hour 6.00


attachment @ 6 cum per hour

3 - 227
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Tipper 5.5 cum capcity, 1 trip per hour hour 6.50

Credit for excavated rock found suitable for cum 18.00


use @ 50 per cent of excavated quantity

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 36 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/36

Note: 1 The quality and availability of rock shall be checked before


affording credit.

2 In case some rock is issued to the contractor at site, the


item of carriage shall be restricted/reduced to that extent.

3 Being small quantity, manual loading will be economical in


this case and has been provided accordingly.

(iii) Excavation in Hard Rock (controlled blasting) with


disposal upto 1000 m

Excavation for roadway in hard rock with controlled


blasting by drilling, blasting and breaking, trimming of
bottom and side slopes in accordance with requirements of
lines, grades and cross-sections, loading and disposal of cut
rock with a lift upto 1.5 m and leads upto 1000 m as per
Technical Specification Clause 302.3.5

Unit = cum

Taking output = 180 cum

a) Labour

Mate day 0.22

Mazdoor (Unskilled) day 3.00

Driller day 2.00

Blaster day 0.50

b) Machinery

Dozer D-50 @ 30 cum per hour hour 6.00

Air compressor, 210 cfm with 2 jack hammers hour 6.00

Front end loader 1 cum bucket capacity hour 6.00

3 - 228
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Tipper 5.5 cum capacity, 4 trips per hour hour 8.20

c)

Gelatine 80 per cent kg 70.00

Electric detonators @ 1 detonator for 2 gelatine stick of each 1,008.00


285 gm each

Credit for excavated rock found suitable for use @ cum 90.00
50 per cent quantity blasted

d) Contractor’s profit & Overheads @ 12.5% on (a+b)

e) Add GST, LWC etc. @ 0 on (a+b)

Cost for 180 cum =a+b+c+d+e

Rate per cum = (a+b+c+d+e)/180

Note: 1 Credit is considered for 50 per cent of quantity of blasted


rock, if found suitable for construction.

2 In case some rock is issued to the Contractor at site, the


item of carriage shall be reduced to that extent.

3.10 302.3.2 Stripping, Storing and Relaying Top Soil from Right-of-Way
(R.O.W)

Stripping, storing and preservation of top soil by keeping it damp


in stock piles and keep wet till it is used by road side at 15 m
internal and re-application on embankment slopes, cut slopes and
other areas in localities where the available embankment material
is not conducive to plant growth as per Technical Specification
Clause 302.3.2

Unit = cum

Taking output = 10 cum

a) Labour

Mate day 0.20

Mazdoor (Unskilled) day 5.00

b) Machinery

Dozer D-50 @ 100 cum per hour hour 0.10

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

3 - 229
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Cost for 10 cum = (a+b+c+d+e)

Rate per cum = (a+b+c+d+e)/10

3.11 302.3.2 Stripping, Storing and Relaying Top Soil from Borrow Areas
in Agricultural Fields

Stripping of top soil from borrow areas located in agriculture fields,


storing at a suitable place, spreading and relaying after taking the
borrow earth to maintain fertility of the agricultural field, finishing it
to the required levels to the satisfaction of the farmer/land owner
as per Technical Specification Clause 302.3.2.

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 4.00

Mazdoor (Unskilled) day 63.00

b) Machinery

Dozer D-50 with 100 cum per hour output (Initially stacking hour 6.00
and relaying)

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 300 cum = a+b+c+d+e

Rate per sqm = (a+b+c)/300

3.12 309 Turfing with Sods

Furnishing and laying of the live sods of perennial turf forming


grass on embankment slope, verges or other locations shown on
the drawing or as directed by the Engineer including preparation
of ground, fetching of sods and watering as per Technical
Specification Clause 309.

Unit = sqm

Talking output = 100 sqm

a) Labour

Mate day 0.12

Mazdoor (Unskilled) day 3.00

b) Machinary

3 - 230
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Water tanker including watering for 3 months

Tractor with Trolley hour 1.00

c) Material

Farmyard manure @ 0.18 cum per 100 sqm at site of work cum 0.18

Water kl 14.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 100 sqm = a+b+c+d+e+f

Rate per sqm = (a+b+c+d+e+f)/100

3.13 310 Seeding and Mulching

Preparation of seed bed on previously laid top soil, furnishing and


placing of seeds, fertilizer, mulching material, applying bituminous
emulsion @ 0.23 litre per sqm and laying and fixing jute netting,
including watering for 3 months all as per Technical Specification
Clause 310.

Unit = sqm

Taking output = 240 sqm

a) Labour

Mate day 0.40

Mazdoor (Unskilled) day 10.00

b) Machinery

Water tanker 6 kl capacity including watering for 3 months hour 14.00

Tractor with Trolley hour 2.40

c) Material

Seeds kg 3.60

Sludge/Farmyard manure @ 0.18 cum per 100 sqm cum 0.43

Bitumen Emulsion t 0.052

Jute netting sqm 264.00

Water for 3 months kl 84.00

3 - 231
Sr. Reference to
Description Unit Quantity
No. MORD Spec
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 240 sqm = a+b+c+d+e+f

Rate per sqm = (a+b+c+d+e+f)/240

3.14 303.1 Construction of Subgrade and Earthen Shoulders

Construction of subgrade and earthen shoulders with approved


material obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope and
compacted to meet requirement of Table 300.2 with lead upto
1000 m as per Technical Specification Clause 303.1.

Unit = cum

Taking output = 100 cum

a) Labour

Mate day 0.04

Mazdoor (Unskilled) day 1.00

b) Machinery

Hydraulic excavator 0.9 cum bucket capacity @ 100 cum hour 1.00
per hour

Tipper 5.5 cum capacity, 4 trips per hour hour 4.50

Add for loading & Unloading @ 10% of excavator & tipper

Dozer D-50 for spreading @ 200 cum per hour hour 0.50

Tractor mount grader for grading @ 25cum per hour hour 4.00

Water tanker with 6 kl capacity hour 2.00

Three wheel 80-100 kN Static Roller @ 70 cum per hour hour 1.43

c) Material

Water kl 12.00

Compensation for earth taken from private land cum 100.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

3 - 232
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Cost for 100 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e)/100

ii From Govt. land

3.15 301.4 Compacting Original Ground

(i) Compacting original ground supporting embankment

Loosening, Levelling and Compacting original ground


supporting embankment to facilitate placement of first layer
of embankment, scarified to a depth of 150 mm, mixed with
water at OMC and then compacted by rolling so as to
achieve minimum dry density as given in Tables 300.1 and
300.2 for embankment construction as per Technical
Specification Clause 301.4.1.

Unit = cum

Taking output = 600 cum

a) Labour

Mate day 0.08

Mazdoor (Unskilled) day 2.00

b) Machinery

Tractor with ripper attachment hour 6.00

Three wheel 80-100 kN Static Roller hour 7.50

Water tanker 6 kl capacity hour 4.00

c) Material

Water kl 24.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 600 cum = a+b+c+d+e+f

Rate per sqm = (a+b+c+d+e+f)/600

303 (ii) Compacting original ground supporting subgrade

3 - 233
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Loosening of the ground upto a level of 300 mm below the
subgrade level, watered, graded and compacted in layers to
meet requirement of Tables 300.1 and 300.2 for subgrade
construction as per Technical Specification Clause 303.5.2.

Unit = cum

Taking output = 600 cum

a) Labour

Mate day 0.24

Mazdoor (Unskilled) day 6.00

b) Machinery

Tractor with ripper attachment hour 10.00

Tractor mount grader for grading hour 6.00

Water tanker 6 kl capacity hour 4.00

Three wheel 80-100 kN Static Roller @ 70 cum per hour hour 8.60

c) Material

Water kl 24.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 600 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/600

3.16 301.5.5.1 Repairs of damages caused by rain/spillage of water

Preparation and surface treatment of formation by removing mud


and slurry, watering to the extent needed to maintain the desired
moisture content, trimming to the required line, grade, profile and
rolling with three wheel 80-100 kN static roller, complete as per
Technical Specification Clause 301.5.5.1

Unit = sqm

Taking output = 3500 sqm

a) Labour

Mate day 0.28

Mazdoor (Unskilled) day 6.00

3 - 234
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor skilled day 1.00

b) Machinery

Three wheel static roller 80-100 kN hour 3.00

Water tanker 6 kl, one trip per hour hour 2.00

c) Material

Water kl 12.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3500 sqm = a+b+c+d+e+f

Rate per sqm = (a+b+c+d+e+f)/3500

3.17 304.3 Presplitting Rock Excavation Slopes

Carrying out excavation in hard rock to achive a specified slope of


the rock face by controlled use of explosives and blasting
accessories in properly aligned and spaced drill holes, collection
of the excavated rock by a D-50 dozer, loading in tipper by a front
end loader and disposing of the material with a lift upto 1.5 m and
lead upto 1000 m as per Technical Specification Clause 304.3

Unit = sqm

Taking output = 400 sqm (120 cum considering 300 mm average


depth of excavation over the existing rock face)

a) Labour

Mate day 0.60

Mazdoor (Unskilled) day 16.00

b) Machinery

Air compressor 210 cfm with 2 leads @ 20 cum per hour hour 6.00

Dozer D-50 hour 6.00

Front end loader 1 cum bucket capacity hour 6.00

Tipper 5.5 cum capacity 2 trip per hour hour 11.00

c) Material

Gelatine 80 per cent kg 42.00

3 - 235
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Electric detonators @ 1 detonator for 2 gelatine sticks of each 672.00
285 gm each

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 400 sqm = a+b+c+d+e+f

Rate per sqm = (a+b+c+d+e+f)/400

Note: In case blasted rock is issued to the Contractor against payment


for construction work, the cost of carriage shall be reduced to that
extent.

3.18 306 Construction of Embankment with Flyash/Pond ash available


from Coal or Lignite Burning Thermal Plants as Waste
Material

Construction of embankment with flyash conforming to Table 1 of


IRC:SP:58 obtained from coal or lignite burning thermal power
stations as waste material, spread and compacted in layer of 200
mm thickness each at OMC, all as specified in IRC:SP:58 and as
per approved plans with lead upto 1000 m as per Technical
Specification Clause 306.

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.16

Mazdoor (Unskilled) day 4.00

b) Machinery

Hydraulic excavator 0.9 cum bucket capacity @ 60 cum per hour 6.00
hour

Tipper 5.5 cum capacity, flyash 360 x 1.2 = 432 t hour 15.00

Loading as per item 1.1 (ii) cum 340.00

Unloading as per item 1.1 (iv) cum 340.00

Dozer D-50 for spreading @ 200 cum per hour hour 0.70

Tractor mount grader for grading @ 25cum per hour hour 5.60

Water tanker 6 kl capacity hour 5.00

Three wheel 80-100 kN Static Roller hour 4.50

c) Material

3 - 236
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Water kl 54.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

Note: 1 As flyash is available free of cost as waste material from


Thermal Plants, cost of material has not been added.

2 The earthcover on sides and intermediate layers of earth


sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced seperately as embankment
construction.

3.19 307 (i) Surface Drains in Soil

Construction of unlined surface drains of average cross-


sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions. Excavated material to be used in
embankment with a lift upto 3m and lead of 50 m (average
lead 25 m) as per Technical Specification Clause 307.

Unit = m

Taking output = 10 m

(A) Manual Means

a) Labour

Mate day 0.08

Mazdoor (Unskilled) day 2.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 m = a+b+c+d

Rate per m = (a+b+c+d)/10

Note: Where lining of drain is provided, quantity shall be worked out


based on approved design and drawing and priced on rate of
cement concrete of approved grade or stone/brick masonary as
the case may be.

(B) Mechanical Means

3 - 237
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Labour

Mate day 0.01

Mazdoor day 0.25

b) Machinery

Hydraulic excavator 0.9 cum bucket capacity @ hour 0.10


100 cum per hour

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10 m = a+b+c

Rate per m = (a+b+c+d+e)/10

(ii) Surface Drains in Ordinary Rock

Construction of unlined surface drain of average cross-


sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
Technical Specification Clause 307. Excavated material to
be used in embankment at site.

Unit = m

Taking output = 10 m

(A) Manual Means

a) Labour

Mate day 0.12

Mazdoor (Unskilled) day 3.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 m = a+b+c+d

Rate per m = (a+b)/10

(B) Mechanical Means

a) Labour

Mate day 0.02

3 - 238
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Unskilled) day 0.50

b) Machineries

Hydraulic excavator 0.9 cum bucket capacity @ hour 0.10


40 m per hour

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/10

(iii) Surface Drains in Hard Rock

Rate per m may be worked out based on quantity of hard


rock as per design.

For rate of hard rock cutting, refer relevant item in this


Chapter
3.20 307 Chute Drains

A. Providing chute drains across embankment slopes in


approches of bridges and on horizontal curves as per
drawings.

Unit = 1 m

(a) Earthwork in excavation for foundations of structures as per


drawings and technical specifications Clause 307 including
setting out construction of shoring and bracing deleterious
matter, dressings of sides and bottom and backfilling with
approved material (By manual means).

Rate as per item No.11.1 of Chapter 11. cum

(b) Providing and laying plain cement concrete M15 grade.

Rate as per item No.12.5 of Chapter 12. cum

(c) Brick Masonry in cement mortar 1:5.

Rate as per item No. 12.1(III) of Chapter 12. cum

(d) Plastering with cement mortar 1:4.

Rate as per item No. 12.3 of Chapter 12. sqm

(e) Providing P.C.C. M.20 coping on the top of chute walls.

As per item No. 12.13 of Chapter 12. m

3 - 239
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate per m = a+b+c+d+e

B. Providing chute drains across embankment slopes in


approches of bridges and on horizontal curves as per
drawings.

Unit = 1 m

(a) Earthwork in excavation for foundations of structures as per


drawings and technical specifications Clause 307 including
setting out construction of shoring and bracing deleterious
matter, dressings of sides and bottom and backfilling with
approved material (By manual means).

Rate as per item No.11.1 of Chapter 11. cum

(b) Providing and laying plain cement concrete M15 grade.

Rate as per item No.12.5 of Chapter 12. cum

(c) Coursed rubble stone masonry (2nd Sort) in cement mortar


1:4

Rate as per item No. 12.4 II (ii) of Chapter 12. cum

(d) Plastering with cement mortar 1:4.

Rate as per item No. 12.3 of Chapter 12. sqm

(e) Providing P.C.C. M.20 coping on the top of chute walls.

As per item No. 12.13 of Chapter 12. m

Rate per m = a+b+c+d+e

Note: Quantities are to be taken as per the designs and drawings.

3 - 240
Chapter 3

EROSION CONTROL AND DRAINAGE


Rate
Amount (Rs.)
(Rs.)

356.65 57.06

244.56 978.24

409.00 613.50

206.10

0.00

1,854.90

18.55

356.65 3.57

244.56 61.14

409.00 368.10

3 - 241
Rate
Amount (Rs.)
(Rs.)
1,341.00 201.15

79.24

0.00

713.20

7.13

356.65 3.57

244.56 44.02

440.00 88.00

1,341.00 268.20

850.00 170.00

71.72

0.00

645.51

6.46

3 - 242
Rate
Amount (Rs.)
(Rs.)

356.65 7.13

244.56 122.28

2,260.00 1,130.00

431.00 1,724.00

440.00 880.00

652.00 815.00

40.00 480.00

644.80

0.00

5,803.21

58.03

3 - 243
Rate
Amount (Rs.)
(Rs.)

356.65 14.27

244.56 244.56

1,635.00 2,730.45

850.00 3,825.00

55.42 5,542.29

2,260.00 1,130.00

3,075.00 1,537.50

440.00 880.00

652.00 815.00

40.00 480.00

33.00 3,300.00

2,562.38

0.00

23,061.45

230.60

230.60

3 - 244
Rate
Amount (Rs.)
(Rs.)

356.65 641.97

244.56 11,005.20

1,455.90

0.00

13,103.07

109.19

356.65 28.53

244.56 489.12

2,260.00 8,136.00

1,081.71

0.00

9,735.36

54.09

3 - 245
Rate
Amount (Rs.)
(Rs.)

356.65 28.53

244.56 489.12

1,635.00 5,886.00

850.00 12,750.00

2,394.21

0.00

21,547.86

59.86

356.65 28.53

244.56 489.12

3 - 246
Rate
Amount (Rs.)
(Rs.)
1,635.00 9,810.00

850.00 10,625.00

2,619.08

0.00

23,571.73

65.48

356.65 28.53

244.56 489.12

1,635.00 5,886.00

850.00 12,750.00

2,394.21

0.00

21,547.86

59.86

3 - 247
Rate
Amount (Rs.)
(Rs.)

356.65 998.62

244.56 17,119.20

2,264.73

0.00

20,382.55

169.85

356.65 42.80

244.56 733.68

2,260.00 4,881.60

707.26

0.00

6,365.34

3 - 248
Rate
Amount (Rs.)
(Rs.)
58.94

356.65 28.53

244.56 489.12

1,635.00 9,810.00

850.00 8,500.00

2,353.46

0.00

21,181.11

88.25

356.65 78.46

3 - 249
Rate
Amount (Rs.)
(Rs.)
244.56 733.68

356.65 713.30

356.65 89.16

2,260.00 13,560.00

435.00 2,610.00

1,341.00 8,046.00

850.00 8,500.00

120.00 7,800.00

5.00 1,210.00

-60.00 -9,000.00

4,292.58

0.00

38,633.18

215.00

3 - 250
Rate
Amount (Rs.)
(Rs.)

356.65 570.64

244.56 3,912.96

285.32 6,562.36

458.55 458.55

850.00 2,465.00

-60.00 -1,200.00

1,596.19

0.00

14,365.70

897.86

356.65 124.83

244.56 2,445.60

1,635.00 9,810.00

3 - 251
Rate
Amount (Rs.)
(Rs.)
850.00 5,525.00

-200.00 -3,600.00

1,788.18

0.00

16,093.61

447.04

356.65 78.46

244.56 733.68

356.65 713.30

356.65 178.33

2,260.00 13,560.00

435.00 2,610.00

1,341.00 8,046.00

3 - 252
Rate
Amount (Rs.)
(Rs.)
850.00 6,970.00

120.00 8,400.00

5.00 5,040.00

-100.00 -9,000.00

4,666.22

0.00

41,995.99

233.31

356.65 71.33

244.56 1,222.80

2,260.00 226.00

190.02

0.00

3 - 253
Rate
Amount (Rs.)
(Rs.)
1,710.15

171.01

356.65 1,426.60

244.56 15,407.28

2,260.00 13,560.00

3,799.24

0.00

34,193.12

113.98

356.65 42.80

244.56 733.68

3 - 254
Rate
Amount (Rs.)
(Rs.)

409.00 409.00

56.00 10.08

40.00 560.00

219.44

0.00

1,975.00

19.75

356.65 142.66

244.56 2,445.60

440.00 6,160.00

409.00 981.60

30.00 108.00

56.00 24.08

27,509.00 1,430.47

20.00 5,280.00

40.00 3,360.00

3 - 255
Rate
Amount (Rs.)
(Rs.)
2,491.55

0.00

22,423.96

93.43

356.65 14.27

244.56 244.56

1,635.00 1,635.00

850.00 3,825.00

10% 546.00

2,260.00 1,130.00

3,075.00 12,300.00

440.00 880.00

652.00 932.36

40.00 480.00

0.00

3,181.28

0.00

3 - 256
Rate
Amount (Rs.)
(Rs.)
28,631.48

286.31

286.00

356.65 28.53

244.56 489.12

409.00 2,454.00

652.00 4,890.00

440.00 1,760.00

40.00 960.00

1,322.71

0.00

11,904.36

19.84

3 - 257
Rate
Amount (Rs.)
(Rs.)

356.65 85.60

244.56 1,467.36

409.00 4,090.00

431.00 2,586.00

440.00 1,760.00

652.00 5,607.20

34.00 816.00

2,051.52

0.00

18,463.68

30.77

356.65 99.86

244.56 1,467.36

3 - 258
Rate
Amount (Rs.)
(Rs.)
356.65 356.65

652.00 1,956.00

440.00 880.00

34.00 408.00

645.98

0.00

5,813.86

1.66

356.65 213.99

244.56 3,912.96

435.00 2,610.00

2,260.00 13,560.00

1,341.00 8,046.00

850.00 9,350.00

120.00 5,040.00

3 - 259
Rate
Amount (Rs.)
(Rs.)
5.00 3,360.00

5,761.62

0.00

51,854.57

129.64

356.65 57.06

244.56 978.24

1,635.00 9,810.00

850.00 12,750.00

55.42 18,843.79

34.63 11,774.27

0.00

431.00 2,413.60

440.00 2,200.00

652.00 2,934.00

3 - 260
Rate
Amount (Rs.)
(Rs.)
25.00 1,350.00

7,888.87

0.00

70,999.84

197.22

356.65 28.53

244.56 489.12

64.71

582.36

58.24

3 - 261
Rate
Amount (Rs.)
(Rs.)

356.65 3.57

244.56 61.14

1,635.00 163.50

28.53

256.73

25.67

356.65 42.80

244.56 733.68

97.06

873.54

87.35

356.65 7.13

3 - 262
Rate
Amount (Rs.)
(Rs.)
244.56 122.28

1,635.00 163.50

36.61

329.53

32.95

102.00 0.00

5,379.01 0.00

6,888.23 0.00

121.17 0.00

1,797.00 0.00

3 - 263
Rate
Amount (Rs.)
(Rs.)
0.00

102.00 0.00

5,379.01 0.00

4,443.66 0.00

1,211.68 0.00

1,797.00 0.00

0.00

3 - 264
Chapter 4

GRANULAR SUB-BASES, BASES (NON-BITUMINOUS) AND SHOULDERS


Sr. Reference to
Description Unit Quantity
No. MORD Spec
4.1 401 Granular Sub-base with Well Graded Material (Table 400.1)

(A) By Mix in Place Method

Construction of granular sub-base by providing well graded


material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with
rotavator at OMC, and compacting with smooth wheel
roller to achieve the desired density, complete as per
Technical Specification Clause 401.

(i) For Grading I Material

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.48

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 10.00

b) Machinery

Tractor mount grader @25cum per hour hour 12.00

Three wheel 80-100 kN static roller @ 10 cum per hour 30.00


hour

Tractor with Rotavator 25 cum per hour hour 12.00

Water tanker 6 kl capacity hour 5.00

c) Material

Well graded granular sub-base material as per


Table 400.1

53 mm to 9.5 mm @ 50 per cent cum 192.00

9.5 mm to 2.36 mm @ 20 per cent cum 77.00

2.36 mm below @ 30 per cent cum 115.00

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

4 - 265
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d)/300

(ii) For Grading II Material

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.48

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 10.00

b) Machinery

Tractor mount grader @25 per hour hour 12.00

Three wheel 80-100 kN static roller @ 10 cum per hour 30.00


hour

Tractor with Rotavator 25 cum per hour hour 12.00

Water tanker 6 kl capacity hour 5.00

c) Material

Well graded granular sub-base material as per


Table 400.1

26.5 mm to 9.5 mm @ 35 per cent cum 134.00

9.5 mm to 2.36 mm @ 25 per cent cum 96.00

2.36 mm below @ 40 per cent cum 153.00

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d

Rate per cum = (a+b+c+d)/300

(iii) For Grading III Material

Unit = cum

4 - 266
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Taking output = 300 cum

a) Labour

Mate day 0.48

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 10.00

b) Machinery

Tractor mount grader @25 cum per hour hour 12.00

Three wheel 80-100 kN static roller @ 10 cum per hour 30.00


hour

Tractor with Rotavator 25 cum per hour hour 12.00

Water tanker 6 kl capacity hour 5.00

c) Material

Well graded granular sub-base material as per


Table 400.1

9.5 mm to 4.75 mm @ 35 per cent cum 134.00

4.75 mm to 2.36 mm @ 12.5 per cent cum 48.00

2.36 mm below @ 52.5 per cent cum 201.60

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/300

401 (B) Plant Mix Method

Construction of granular sub-base by providing well graded


material, mixing in a mechanical mix plant at OMC, carriage
of mixed material to work site upto lead of 1000 m
spreading in uniform layers with motor grader on prepared
surface and compacting with smooth wheel roller to achieve
the desired density, complete as per Technical Specification
Clause 401

(i) For Grading I Material

4 - 267
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = cum

Taking output = 225 cum (450 t)

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

b) Machinery

Wet mix plant @ 60 t capacity per hour hour 7.50

Water tanker 6 kl capacity 5 km lead with one trip hour 4.00


per hour

Front end loader 0.9 cum bucket capacity 25 cum hour 9.00
per hour

Tipper 5.5 cum @ 3 trips per hour hour 13.60

Motor grader 110 HP @ 50 cum per hour hour 4.50

Three wheel 80-100 kN static roller 10 cum per hour 22.50


hour

c) Material

Well graded granular sub-base material as per


Table 400.1

53 mm to 9.5 mm @ 50 per cent cum 144.00

9.5 mm to 2.36 mm @ 20 per cent cum 57.00

2.36 mm below @ 30 per cent cum 86.40

Water kl 24.00

d) Contractor’s profit& overheads @ 12.5%on (a+b+c)

Cost for 225 cum = a+b+c+d

Rate per cum = (a+b+c+d)/225

(ii) For Grading II Material

Unit = cum

Taking output = 225 cum (450 t)

a) Labour

Mate day 0.40

4 - 268
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

b) Machinery

Wet mix plant @ 60 t capacity per hour hour 7.50

Water tanker 6 kl capacity 5 km lead with one trip hour 4.00


per hour

Front end loader 0.9 cum bucket capacity 25 cum hour 9.00
per hour

Tipper 5.5 cum, 3 trips per hour hour 13.60

Motor grader 110 HP @ 50 cum per hour hour 4.50

Three wheel 80-100 kN static roller 10 cum output hour 22.50

c) Material

Well graded granular sub-base material as per


Table 400.1

26.5 mm to 9.5 mm @ 35 per cent cum 100.80

9.5 mm to 2.36 mm @ 25 per cent cum 72.00

2.36 mm below @ 40 per cent cum 115.20

Water kl 24.00

d) Contractor’s profit & overheads @ 12.5% on (a+b+c)

Cost for 225 cum = a+b+c+d

Rate per cum = (a+b+c+d)/225

(iii) For Grading III Material

Unit = cum

Taking output = 225 cum (450 t)

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

4 - 269
Sr. Reference to
Description Unit Quantity
No. MORD Spec
b) Machinery

Wet mix plant @ 60 t capacity per hour hour 7.50

Water tanker 6 kl capacity 5 km lead with one trip hour 4.00


per hour

Front end loader 0.9 cum bucket capacity 25 cum hour 9.00
per hour

Tipper 5.5 cum, 3 trips per hour hour 13.60

Motor grader 110 HP @ 50 cum per hour hour 4.50

Three wheel 80-100 kN static roller 10 cum output hour 22.50

c) Material

Well graded granular sub-base material as per


Table 400.1

9.5 mm to 4.75 mm @ 35 per cent cum 100.80

4.75 mm to 2.36 mm @ 12.5 per cent cum 36.00

2.36 mm below @ 52.5 per cent cum 151.20

Water kl 24.00

d) Contractor’s profit & overheads @ 12.5%on (a+b+c)

Cost for 225 cum = a+b+c+d

4.2 402 i) Gravel/Soil-Aggregate Base (Table 400.2) Grading A

Construction of gravel/soil-aggregate base by providing


well graded material, spreading in uniform layers with motor
grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with three wheel
80-100 kN static roller to achieve the desired density,
complete as per Technical Specifications Clause 402

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

b) Machinery

4 - 270
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Tractor mount grader @25cum per hour hour 12.00

Three wheel 80-100 kN static roller @ 10 cum per hour 30.00


hour

Water tanker 6 kl capacity hour 5.00

Tractor with Rotavator 25 cum per hour hour 12.00

c) Material

For well graded granular sub-base materials as per


Table 400.2

For Grading A Material

53 mm to 26.5 mm @ 35 per cent cum 134.40

26.5 mm to 4.75 mm @ 45 per cent cum 172.80

2.36 mm below @ 20 per cent cum 76.80

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/300

ii) Gravel/Soil-Aggregate Base (Table 400.2) Grading B

Construction of granular sub-base by providing well graded


material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with
rotavator at OMC, and compacting with three wheel 80-100
kN static roller capacity to achieve the desired density,
complete as per Technical Specification Clause 402

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

4 - 271
Sr. Reference to
Description Unit Quantity
No. MORD Spec
b) Machinery

Tractor mount grader @25 cum per hour hour 12.00

Three wheel 80-100 kN static roller @ 10 cum per hour 30.00


hour
Water tanker 6 kl capacity hour 5.00

Tractor with Rotavator 25 cum per hour hour 12.00

c) Material

For well graded granular sub-base materials as per


Table 400.2
For Grading B Material

26.5 mm to 4.75 mm @ 75 per cent cum 288.00

2.36 mm below @ 25 per cent cum 96.00

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/300

iii) Gravel/Soil-Aggregate Base (Table 400.2) Grading C

Construction of granular sub-base by providing well graded


material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with
rotavator at OMC, and compacting with three wheel 80-100
kN static roller capacity to achieve the desired density,
complete as per Technical Specification Clause 402

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

b) Machinery

4 - 272
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Tractor mount grader @25cum per hour hour 12.00

Three wheel 80-100 kN static roller @ 10 cum per hour 30.00


hour
Water tanker 6 kl capacity hour 5.00

Tractor with Rotavator 25 cum per hour hour 12.00

c) Material

For well graded granular sub-base materials as per


Table 400.2

For Grading C Material

9.5 mm to 4.75 mm @ 66 per cent cum 255.00

2.36 mm below @ 34 per cent cum 129.00

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/300

iv) Gravel/Soil Aggeregate Base/Sub-Base Nominal


Maximum size Grading 80 mm (Table 2.3 of IRC SP 77-
2008

Unit = cum

Taking Output = 300 cum

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

b) Machinery

Tractor Mount Grader @ 25 cum per hour hour 12.00

Three wheel 80-100 Kn static Roller @ 10 cum per hourhour 30.00

Water Tanker 6 Kl capacity hour 5.00

Tractor with Rotavator 25 cum per hour hour 12.00

4 - 273
Sr. Reference to
Description Unit Quantity
No. MORD Spec
c) Material

Well graded gravel/ soil aggrerate base material of cum 360


nominal maximum size 80mm as per table 2.3 of IRC
SP 77-2008

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost of 300 cum = a+b+c+d+e

Rate per cum = a+b+c+d+e/300

v) Gravel/Soil Aggeregate Base/Sub-Base Nominal


Maximum size Grading 40 mm (Table 2.3 of IRC SP 77-
2008

Unit = cum

Taking Output = 300 cum

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

b) Machinery

Tractor Mount Grader @ 25 cum per hour hour 12.00

Three wheel 80-100 Kn static Roller @ 10 cum per hourhour 30.00

Water Tanker 6 Kl capacity hour 5.00

Tractor with Rotavator 25 cum per hour hour 12.00

c) Material

Well graded gravel/ soil aggrerate base material of cum 360


nominal maximum size 40mm as per table 2.3 of IRC
SP 77-2008

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

4 - 274
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Cost of 300 cum = a+b+c+d+e+f

Rate per cum = a+b+c+d+e/300

vi) Gravel/Soil Aggeregate Base/Sub-Base Nominal


Maximum size Grading 20 mm (Table 2.3 of IRC SP 77-
2008

Unit = cum

Taking Output = 300 cum

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

b) Machinery

Tractor Mount Grader @ 25 cum per hour hour 12.00

Three wheel 80-100 Kn static Roller @ 10 cum per hourhour 30.00

Water Tanker 6 Kl capacity hour 5.00

Tractor with Rotavator 25 cum per hour hour 12.00

c) Material

Well graded gravel/ soil aggrerate base material of cum 360


nominal maximum size 20mm as per table 2.3 of IRC
SP 77-2008

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost of 300 cum = a+b+c+d+e+f

Rate per cum = a+b+c+d+e/300

vii) Gravel/Soil Aggeregate Base/Sub-Base Nominal


Maximum size Grading 10 mm (Table 2.3 of IRC SP 77-
2008

Unit = cum

4 - 275
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Taking Output = 300 cum

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

b) Machinery

Tractor Mount Grader @ 25 cum per hour hour 12.00

Three wheel 80-100 Kn static Roller @ 10 cum per hourhour 30.00

Water Tanker 6 Kl capacity hour 5.00

Tractor with Rotavator 25 cum per hour hour 12.00

c) Material

Well graded gravel/ soil aggrerate base material of cum 360


nominal maximum size 10mm as per table 2.3 of IRC
SP 77-2008

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost of 300 cum = a+b+c+d+e

Rate per cum = a+b+c+d+e/300

viii) Gravel/Soil Aggeregate Base/Sub-Base Nominal


Maximum size Grading 5 mm (Table 2.3 of IRC SP 77-
2008

Unit = cum

Taking Output = 300 cum

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

b) Machinery

4 - 276
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Tractor Mount Grader @ 25 cum per hour hour 12.00

Three wheel 80-100 Kn static Roller @ 10 cum per hourhour 30.00

Water Tanker 6 Kl capacity hour 5.00

Tractor with Rotavator 25 cum per hour hour 12.00

c) Material

Well graded gravel/ soil aggrerate base material of cum 360


nominal maximum size 5 mm as per table 2.3 of IRC
SP 77-2008

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost of 300 cum = a+b+c+d+e+f

Rate per cum = a+b+c+d+e+f/300

4.3 403 Gravel/Soil-Aggregate Surface Course (Table 400.3)

Construction of granular surface course by providing well graded


material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator at
OMC, and compacting with three wheel 80-100 kN static roller
capacity to achieve the desired density, complete as per
Technical Specification Clause 402

Unit = cum

Taking output = 300 cum

a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

b) Machinery

Tractor mount grader @25cum per hour hour 12.00

Three wheel 80-100 kN static roller @ 10 cum per hour hour 30.00

Water tanker 6 kl capacity hour 5.00

4 - 277
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Tractor with Rotavator 25 cum per hour hour 12.00

c) Material

For well graded granular sub-base materials as per Table


400.3

4.75 to 2.36 mm 40 per cent cum 153.60

2.36 mm below @ 60 per cent cum 210.40

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/300

4.4 402 Lime Stabilisation for Improving Subgrade

Laying and spreading available soil in the subgrade on a prepared


surface, pulverising, mixing the spread soil in place with rotavator
with 2 per cent slaked lime having minimum 70 per cent of
contents of CaO, grading with motor grader and compacting with
the smooth wheel road roller at OMC to the desired density to
form a layer of improved Sub-grade as per Technical Specification
Cluase 403.

(A) By Manual Means

Unit = cum

Taking output = 150 cum (263 t)

a) Labour

Mate day 1.44

Mazdoor (Skilled) day 1.00

Mazdoor (Unskilled) day 35.00

b) Machinery

Three wheel 80-100 kN Static roller @ 70 cum per hour 2.15


hour

Water tanker 6 kl capacity hour 3.00

c) Material

4 - 278
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Lime t 5.26

Water kl 18.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 150 cum = a+b+c+d+e+f

Rate per cum = ( a+b+c+d)/150

(B) By Mechanical Means

Unit = cum

Taking output = 300 cum (525 t)

a) Labour

Mate day 0.36

Mazdoor (Skilled) day 1.00

Mazdoor (Unskilled) day 8.00

b) Machinery

Tractor with ripper and rotavator attachments @ 60 hour 12.00


cum per hour for ripping and 25 cum per hour for
mixing
Tractor mount grader @25cum per hour hour 6.00

Three wheel 80-100 kN static roller @ 70 cum per hour 4.30


hour

Water tanker 6 kl capacity hour 5.00

c) Material

Lime t 10.50

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/300

4 - 279
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Note: The exact quantity of lime shall be as per design.

4.5 403 Lime Treated Soil for Sub-Base

Providing, laying and spreading soil on a prepared sub-grade,


pulverising, mixing the spread soil in place with rotavator with 4
per cent slaked lime with minimum content of 70 per cent of CaO,
grading with motor grader and compacting with the road roller at
OMC to achieve atleast 98 per cent of the max dry density to
form a layer of sub-base as per Technical Specification Clause
403.

Unit = cum

Taking output = 300 cum (525 t)

a) Labour

Mate day 0.48

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 10.00

b) Machinery

Hydraulic Excavator 0.90 cum bucket capacity hour 5.00

Tipper 5.5 cum 4 trips per hour hour 14.00

Tractor mount grader @25cum per hour hour 6.00

Three wheel 80-100 kN Static roller @ 70 cum per hour hour 4.30

Tractor with rotavator and blade @ 25 cum per hour hour 12.00

Water tanker 6 kl capacity hour 4.00

c) Material

Lime t 18.00

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/300

Note: The exact quantity of lime shall be as per design.

4 - 280
Sr. Reference to
Description Unit Quantity
No. MORD Spec
4.6 404 Cement Treated Soil Sub-Base/Base

Providing, laying and spreading soil on a prepared sub-grade,


pulverising, adding the designed quantity of cement to the spread
soil, mixing in place with rotavator, grading with the motor grader
and compacting with the road roller at OMC to achieve the
desired unconfined compressive strength and to form a layer of
sub-base/base as per Technical Specification Clause 404.

Unit = cum

Taking output = 300 cum (525 t)

For 4 per cent quantity of cement by weight of soil

a) Labour

Mate day 0.48

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 10.00

b) Machinery

Hydraulic Excavator 0.90 cum bucket capacity hour 5.00

Tipper 5.5 cum hour 14.00

Tractor mount grader @25cum per hour hour 6.00

Three wheel 80-100 kN static roller @ 70 cum per hour hour 4.30

Tractor with rotavator and blade @ 25 cum per hour hour 12.00

Water tanker 6 kl capacity hour 5.00

c) Material

Cement at site @ 4% (of 525 t) t 21.00

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

4 - 281
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate per cum =(a+b+c+d+e+f)/300

Note: The exact quantity of cement shall be as per design.

4.7 405 Water Bound Macadam Sub-base/base

1) WBM Grading 1

Providing, laying, spreading and compacting stone


aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in
stages to proper grade and camber, applying and brooming,
stone screening/binding materials to fill-up the interstices of
coarse aggregate, watering and compacting to the required
density Grading 1 as per Technical Specification Clause
404.

(A) By Manual Means

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 10.08

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 250.00

b) Machinery

Three wheel 80-100 kN static roller @ 10 cum per hour 36.00


hour

Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 1 90 mm to 45 mm @ 1.21 cum per 10 cum 435.60


sqm for compacted thickness of 100 mm

Stone Screenings

Type A 13.2 mm for Grading-1 @ 0.27 cum per cum 97.20


10 sqm

Binding Material

Binding Material @ 0.08 cum per 10 sqm for cum 28.80


grading 1 material

4 - 282
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

(B) By Mechanical Means

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.68

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 15.00

b) Machinery

Tractor mount grader @25cum per hour hour 7.20

Three wheel 80-100 kN static roller @ 10 cum per hour 36.00


hour

Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 1 90 mm to 45 mm @ 1.21 cum per 10 cum 485.00


sqm for compacted thickness of 100 mm

Stone Screening

Type A 13.2 mm for Grading-1 @ 0.27 cum per cum 97.20


10 sqm

Binding Material

Binding Material @ 0.08 cum per 10 sqm for cum 28.80


Grading 2 material

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

4 - 283
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Cost for 360 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/360

2) WBM Grading 2

Providing, laying, spreading and compacting stone


aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with smooth wheel roller 80-100 kN in
stages to proper grade and camber, applying and brooming,
stone screening/binding materials to fill-up the interstices of
coarse aggregate, watering and compacting to the required
density grading 2 as per Technical Specification Clause 405.

(A) By Manual Means

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 10.08

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 250.00

b) Machinery

Three wheel 80-100 kN static roller @ 8 cum per hour 45.00


hour

Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate
Grading 2 63 mm to 45 mm @ 0.91 cum per 10 cum 445.00
sqm for compacted thickness of 75 mm

Stone Screening

Type B 11.2 mm for Grading 2 @ 0.20 cum per cum 96.01


10 sqm

Binding Material

Binding Material @ 0.06 cum per 10 sqm for cum 28.80


Grading 2 material

Water kl 144.00

4 - 284
Sr. Reference to
Description Unit Quantity
No. MORD Spec
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

(B) By Mechanical Means

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.68

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 15.00

b) Machinery

Tractor mount grader @25cum per hour hour 7.20

Three wheel 80-100 kN static roller @ 8 cum per hour 45.00


hour

Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 2 63 mm to 45 mm @ 0.91 cum per 10 cum 425.00


sqm for compacted thickness of 75 mm

Stone Screening

Type B 11.2 mm for Grading 2 @ 0.20 cum per cum 96.01


10 sqm

Binding Material

Binding Material @ 0.06 cum per 10 sqm for cum 28.80


Grading 2 material

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

4 - 285
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

Note: Type A Screening can be used in Grading 2

3) WBM Grading 3

Providing, laying, spreading and compacting stone


aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with smooth wheel roller 80-100 kN in
stages to proper grade and camber, applying and brooming,
stone screening to fill-up the interstices of coarse aggregate,
watering and compacting to the required density Grading 3
as per Technical Specification Clause 405.

(A) By Manual Means

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 10.08

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 250.00

b) Machinery
Three wheel 80-100 kN static roller @ 8 cum per hour 45.00
hour

Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 3 53 mm to 22.4 mm @ 0.91 cum per 10 cum 435.60


sqm for compacted thickness of 75 mm
Stone Screening

Type B 11.2 mm for Grading 3 @ 0.18 cum per cum 86.40


10 sqm

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

4 - 286
Sr. Reference to
Description Unit Quantity
No. MORD Spec
e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d

Rate per cum = (a+b+c+d+e+f)/360

(B) By Mechanical Means

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.68

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 15.00

b) Machinery

Tractor mount grader @25cum per hour hour 7.20

Three wheel 80-100 kN static roller @ 8 cum per hour 45.00


hour

Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 3 53 mm to 22.4 mm @ 0.91 cum per cum 435.00


10 sqm for compacted thickness of 75 mm

Stone Screening

Type B 11.2 mm for Grading 3 @ 0.18 cum per cum 86.40


10 sqm

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

4.8 405 Water Bound Macadam with Crushable Screenings

1) WBM Grading 1

4 - 287
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in
stages to proper grade and camber, applying and brooming,
crushable screening to fill-up the interstices of coarse
aggregate, watering and compacting to the required density
Grading 1 as per Technical Specification Clause 405.

(A) By Manual Means

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 10.08

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 250.00

b) Machinery

Three wheel 80-100 kN static roller @ 10 cum per hour 36.00


hour
Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 1 90 mm to 45 mm @ 1.21 cum per 10 cum 430.00


sqm for compacted thickness of 100 mm

Crushable type such as moorum or Gravel for cum 108.00


grading 1 @ 0.30 cum per 10 sqm

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

(B) By Mechanical Means

Unit = cum

4 - 288
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Taking output = 360 cum

a) Labour

Mate day 0.68

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 15.00

b) Machinery

Tractor mount grader @25cum per hour hour 7.20

Three wheel 80-100 kN static roller @ 10 cum per hour 36.00


hour
Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 1 90 mm to 45 mm @ 1.21 cum per 10 cum 410.00


sqm for compacted thickness of 100 mm

Crushable type such as Moorum or gravel for cum 108.00


Grading 2 @ 0.30 cum per 10 sqm

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

2) WBM Grading 2

Providing, laying, spreading and compacting stone


aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in
stages to proper grade and camber, applying and brooming,
crushable screening to fill-up the interstices of coarse
aggregate, watering and compacting to the required density
Grading 2 as per Technical Specification Clause 405.

(A) By Manual Means

Unit = cum

4 - 289
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Taking output = 360 cum

a) Labour

Mate day 10.08

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 250.00

b) Machinery

Three wheel 80-100 kN static roller @ 8 cum per hour 45.00


hour

Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 2 63 mm to 45 mm @ 0.91 cum per 10 cum 400.00


sqm for compacted thickness of 75 mm

Crushable type such as Moorum or gravel for cum 105.59


Grading 2 @ 0.22 cum per 10 sqm

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

(B) By Mechanical Means

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.68

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 15.00

b) Machinery

Tractor mount grader @25cum per hour hour 7.20

4 - 290
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Three wheel 80-100 kN @ static roller 8 cum per hour 45.00
hour

Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 2 63 mm to 45 mm @ 0.91 cum per 10 cum 400.00


sqm for compacted thickness of 75 mm

Crushable type such as Moorum or gravel for cum 105.59


Grading 2 @ 0.22 cum per 10 sqm

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

3) WBM Grading 3

Providing, laying, spreading and compacting stone


aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in
stages to proper grade and camber, applying and brooming,
crushable screening to fill-up the interstices of coarse
aggregate, watering and compacting to the required density
Grading 3 as per Technical Specification Clause 405.

(A) By Manual Means

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 10.08

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 250.00

b) Machinery

Three wheel 80-100 kN static roller @ 8 cum per hour 45.00


hour

4 - 291
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 3 53 mm to 22.4 mm @ 0.91 cum per cum 400.00


10 sqm for compacted thickness of 75 mm

Crushable type such as Moorum or gravel for cum 105.59


Grading 3 @ 0.22 cum per 10 sqm

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

(B) By Mechanical Means

Unit = cum

Taking output = 360 cum

a) Labour

Mate day 0.68

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 15.00

b) Machinery

Tractor mount grader @25cum per hour hour 7.20

Three wheel 80-100 kN @ Static roller 8 cum per hour 45.00


hour

Water tanker 6 kl capacity hour 24.00

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate

Grading 3 53 mm to 22.4 mm @ 0.91 cum per 10 cum 392.00


sqm for compacted thickness of 75 mm

Crushable type such as Moorum or gravel for cum 105.59


Grading 3 @ 0.22 cum per 10 sqm

4 - 292
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

4.9 406 Wet Mix Macadam

Providing, laying, spreading and compacting graded stone


aggregate to wet mix macadam specification including premixing
the material with water at OMC in mechanical mixer (Pug Mill),
carriage of mixed material by tipper to site, laying in uniform
layers in sub-base/base course on a well prepared sub-base and
compacting with smooth wheel roller of 80 to 100kN weight to
achieve the desired density including lighting, barricading and
maintenance of diversion, etc as per Tables 400.11 & 400.12 and
Technical Specification Clause 406.

By Mechanical Means with 1 km lead

Unit = cum

Taking output = 100 cum

a) Labour

Mate day 0.40

Dresser (Skilled) for alignment day 8.00

Mazdoor (Skilled) day 2.00

b) Machinery

Front end loader 1 cum capacity hour 4.00

Wet mix plant (Pug Mill) hour 4.00

Tipper/Dumper (10-t) capacity hour 5.00

Tractor mount grader @25cum per hour hour 2.00

Water tanker 6 kl capacity hour 1.33

Three wheel 80-100 kN static roller @ 16 cum per hour hour 6.25

c) Material

Coarse aggregate 45 mm to 22.4 mm @ 30 per cent cum 39.90

4 - 293
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Aggregates 22.4 mm to 2.36 mm @ 40 per cent cum 51.20

Fine aggregate/Crushed sand 2.36 mm to 75 micron @ 30 cum 39.90


per cent
Water kl 8.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 100 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/100

4.10 407 Construction of Shoulders as per Technical Specification


Clause 407.

A. Earthen Shoulders

The rate as applicable for sub-grade construction may be


adopted.

B. Hard Shoulders

Rate as applicable for sub-base and/or base may be


adopted as per approved design.

C. Paved Shoulders

The rates may be adopted as applicable for different layers


of pavement depending upon approved design of paved
shoulders.

4.11 408 Granular sub-base/base/surface course with local materials


(Table 400.13) by mix in place method normal Construction of
granular sub-base by providing local material spreading in
uniform layers with motor grader on prepared surface, mixing
by mix in place method with rotavator at once and
compacting with smooth wheel roller to achieve the desired
density complete as per Clause 401.4 as per Technical
Specification Clause 408.

(i) Using naturally occuring gravel

Unit = cum

Taking output = 300 cum

(a) Labour

Mate day 0.48

4 - 294
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 10.00

(b) Machinery

Tractor mount grader @25cum per hour hour 6.00

Three wheel 80-100 kN static roller @10 cum per hour hour 30.00

Tractor with rotavator 25 cum per hour hour 12.00

Water tanker 6 kl capacity hour 5.00

(c) Material

Naturally occurring gravel (Local materials as per Table


400.13)
Quantity as per Item No.4.1 of Chapter 4 cum 192.00

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = a+b+c+d+e+f/300

(ii) Using Gravel mix soil using

Unit = cum

Taking output = 300 cum

(a) Labour

Mate day 0.40

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 8.00

(b) Machinery

Tractor mount grader @25cum per hour hour 6.00

Three wheel 80-100 kN static roller @10 cum per hour hour 30.00

Water tanker 6 kl capacity hour 5.00

Tractor with Rotavator 25 cum per hour hour 12.00

4 - 295
Sr. Reference to
Description Unit Quantity
No. MORD Spec
(c) Material

Soil gravel mixture/quarry waste (Local material as per


Table 400.13)
As per Item No.4.2 of Chapter 4 cum 134.40

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/300

4.12 408 Construction of Water Bound Macadam using locally


available material (Table 400.13)

Providing, laying spreading and compacting local material in block


or large discrete particles, such as kankar, Laterite, Dhandla etc.
as per Table 400.13 to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with three wheel 80-100 kN static roller in stages to proper grade
and camber, applying and brooming requisite type of screening
/binding materials to fill-up the interstices of laid material watering
and compacting to the required density as per Clause 405.3 and
Technical Specification Cluase 408.

Unit = cum

Taking output = 360 cum

(a) Labour

Mate day 0.68

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 15.00

(b) Machinery

Tractor mount grader @25cum per hour hour 7.20

Three wheel 80-100 kN @ static roller 8 cum per hour hour 45.00

Water tanker 6 kl capacity hour 24.00

(c) Material

4 - 296
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Low Grade Aggregate such as Kankar, Laterite, Dhandla cum 435.60
and naturally occuring gravels, quarry waste as per Table
400.13 @ 1.21 cum per 10 sqm compacted thickness 100
mm

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

4.13 409 Lime-Flyash Stablised Soil Sub-base

Construction of sub-base using lime-flyash admixture with


granular soil, free from organic matter/deleterious material or
clayey silts and low plasticity clays having PI between 5 and 20
and liquid limit less than 25 and commercial dry lime, slaked at
site or pre-slaked with CaO content not less than 50 per cent,
flyash to conform to gradation as per Clause 4.3 of IRC:SP:20,
lime+flyash content ranging between 10 to 30 per cent, the
minimum un-confined compressive strength and CBR value after
28-days curing and 4-days soaking to be 0.75 MPa and 25 per
cent respectively, all as specified in IRC:88 including a lead upto
1000 m as per Technical Specification Cluase 409.

Unit = cum

Taking output = 480 cum (720 t, density 1.50 t/cum)

Assumptions made

Total mass taken for analysis = 720 t

Lime+Flyash admixture

@ 20% = 0.2 x 720=144 t

Soil = 720-144 = 578 t

(578/1.6 = 360 cum)

Lime + Flyash = 144 t

Ratio Lime 4 : Flyash 16

Lime = 29 t

Flyash = 115 t

4 - 297
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Labour

Mate day 0.28

Mazdoor (Unskilled) day 6.00

Mazdoor (Skilled) day 1.00

b) Machinery

Hydraulic Excavator 0.90 cum bucket capacity @ 60 cum hour 6.00


per hour for 360 cum soil

Tipper 10 t capacity for carriage of soil 578 t hour 16.00

Tipper 10 t capacity for carriage of 115 t flyash hour 5.50

Tipper 10 t capacity for carriage of 29 t of lime from store to hour 3.80


work site
Loading as per item 1.1 (ii) cum 480.00

Unloading as per item 1.1 (iv) cum 480.00

Tractor with disc harrows for pulverisation hour 6.00

Tractor mount grader @25cum per hour hour 3.20

Three wheel 80-100 kN static roller hour 12.00

Water tanker 6 kl capacity hour 12.00

c) Material

Lime (Slaked) t 22.00

Compensation for earth taken from private source cum 360.00

Water kl 72.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 480 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/480

From govt land

4 - 298
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Note: 1 Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.

2 Cost of flyash has not been considered as same will be


available free of cost. Only carriage of flyash has been
provided.

3 Lime + Flyash has been taken as 20 per cent of total mass


and ratio of lime and flyash as 1:4 for estimating purposes.
Total quantities will be as per approved design.

4.14 410 Construction of Sub-base/Course Using Crushed Slag as per


Table 400.19

Construction of Sub-base by providing crushed slag spreading in


uniform layer with motor grader on prepared surface mixing by
mix-in-place method with Rotavator @ OMC, and compacting with
three wheel 80-100 kN static roller to achieve the desired density
complete as per Technical Specifications Cluase 402.4 and
410.3.2

Unit = cum

Taking output = 300 cum

(a) Labour

As per Item No.4.1 of Chapter 4

(b) Machinery

As per Item No.4.1 of Chapter 4

(c) Material

Crushed slag as per Clause 410.4.2 (i)

As per Item No.4.2 of Chapter 4 cum 384.00

Water kl 30.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/300

4.15 410 Water Bound Macadam using crushed slag

4 - 299
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Providing, laying, spreading and compacting crushed slag to
water Bound Macadam specification including spreading in
uniform thickness, hand packing rolling with smooth wheel roller
80-100 kN in stages to proper grade and camber, applying and
brooming requisite type of screening/binding materials to fill up
the interstees of crushed slag watering and compacting to the
required density as per Clause 405.3 and Technical Specification
Cluase 410.3.2.

Unit = cum

Taking output = 360 cum

(a) Labour

As per Item No. 4.7 of Chapter 4

(b) Machinery

As per Item No.4.7 of Chapter 4

(c) Material

As per Item No.4.8 (1)(A)© of Chapter 4

Crushed slag as per Clause 410.4.2 (ii) cum 435.60

Crushable screening cum 108.00

Water kl 144.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e

Rate per cum = (a+b+c+d)/360

4.16 410 Cement Bound Granular Material sub-base/base

Providing laying and spreading granulated blast furnace slag on


a prepared sub-grade pulverising adding the designed quantitity
of cement to the spread granulated blast furnace slag mixing in
place with rotavator grading with the mortar grader and
compacting with smooth wheel roller 80-100 kN at OMC to
achieve the desired unconfined compressive strength and to form
a layer of sub-base/base as per Technical Specification Clauses
404.3 and 410.4.2.

Unit = cum

Taking output = 300 cum (525 t)

4 - 300
Sr. Reference to
Description Unit Quantity
No. MORD Spec
For 4 per cent quantity of cement by wt of granulated blast
furnace slag

(a) Labour

Mate day 0.48

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 10.00

(b) Machinery

5.50 cum Tipper for carriage of GBFS add 10 per cent of hour 15.00
cost of carriage of cover cost of loading and unloading

Motor grader 110 HP @ 50 cum per hour hour 6.00

Three wheel 80-100 kN static roller @ 70 cum per hour hour 4.30

Tractor with rotavator and blade @ 25 cum per hour hour 12.00

Water tanker 6 kl capacity hour 7.00

(c) Material

Cement (4%) t 21.00

Water kl 42.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 300 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/300

Note: (i) The exact quantity of cement shall be as per design

(ii) Granulated ballast slag will be available free of cost

4.17 411 Crusher Run Macadam Base

Providing crushed run stone aggregate greading conforming to


table 400.20 depositing on a prepared surface by hauling
vehicles, spreading and mixing with a motor grader, watering and
compacting with a three wheel 80-100 kN static roller as per
Technical Specification Clause 411 to form a layer of sub-
base/base

A) By mix-in-place method

(i) With 53 mm maximum size of aggregates

4 - 301
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = cum

Taking output = 360 cum

(a) Labour

Mate day 0.48

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 10.00

(b) Machinery

Tractor attached with rotavator @ 25 cum per hour hour 14.00

Tractor mount grader @25cum per hour hour 6.00

Three wheel 80-100 kN static roller @ 8 cum per hour 45.00


hour
Water tanker 6 kl capacity hour 6.00

(c) Material

Aggregate at site

For 53 mm maximum size

63 mm to 45 mm @ 33 per cent cum 159.46

22.5 mm to 5.6 mm @ 32 per cent cum 151.06

Below 5.6 mm @ 35 per cent cum 116.68

Water kl 36.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

(ii) With 37.5 mm maximum size of aggregates

Unit = cum

Taking output = 360 cum

(a) Labour

4 - 302
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mate day 0.48

Mazdoor (Skilled) day 2.00

Mazdoor (Unskilled) day 10.00

(b) Machinery

Tractor attached with rotavator @ 25 cum per hour hour 14.00

Tractor mount grader @25cum per hour hour 6.00

Three wheel 80-100 kN static roller @ 8 cum per hour 45.00


hour
Water tanker 6 kl capacity hour 6.00

(c) Material

Aggregate at site

For 37.5 mm maximum size

45 mm to 22.5 mm @ 5 per cent cum 24.12

22.4 mm to 5.6 mm @ 50 per cent cum 217.60

Below 5.6 mm @ 45 per cent cum 213.48

Water kl 36.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 360 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/360

B) By mixing plant method

(i) With 53 mm maximum size of aggregates

Unit = cum

Taking output = 225 cum (450 t)

(a) Labour

Mate day 0.28

Mazdoor (Skilled) day 1.00

Mazdoor (Unskilled) day 6.00

4 - 303
Sr. Reference to
Description Unit Quantity
No. MORD Spec
(b) Machinery

Wet mix plant @ 75 t per hour hour 6.00

Electric generator set, 125 KVA hour 6.00

Front end loader 1 cum bucket capacity hour 6.00

Tractor mount grader @25cum per hour hour 12.00

Three wheel roller 80-100 kN @ 8 cum per hour hour 28.13

Water tanker hour 3.00

Tipper hour 10.00

(c) Material

Aggreate at site

For 53 mm maximum size

63 mm to 45 mm @ 33 per cent cum 98.40

22.4 mm to 5.6 mm @ 32 per cent cum 94.41

Below 5.6 mm @ 35 per cent cum 84.18

Water kl 18.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 225 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/225

(ii) With 37.5 mm maximum size of aggregates

Unit = cum

Taking output = 225 cum (450 t)

(a) Labour

Mate day 0.28

Mazdoor (Skilled) day 1.00

Mazdoor (Unskilled) day 6.00

(b) Machinery

4 - 304
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Wet mix plant @ 75 t per hour hour 6.00

Electric generator set, 125 KVA hour 6.00

Front end loader 1 cum bucket capacity hour 6.00

Tractor mount grader @25cum per hour hour 12.00

Three wheel roller 80-100 kN @ 8 cum per hour hour 28.13

Water tanker hour 3.00

Tipper hour 10.00

(c) Material

Aggreate at site

For 37.5 mm maximum size

45 mm to 22.5 mm @ 5 per cent cum 15.06

22.4 mm to 5.6 mm @ 50 per cent cum 127.00

Below 5.6 mm @ 45 per cent cum 127.00

Water kl 18.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 225 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/225

4.18 412 Brick Soling

Laying brick soling layer on prepared sub-grade with brick on end


edging according to lines, graded and cross-section shown on the
drawing filling joints with sand and earth, spreading 25 mm thick
layer of earth over brick soling, watering and rolliing the same with
three wheel road roller 80-100 kN as per Technical Specification
Clause 412

Unit = sqm

Taking ouput = 150 sqm

(a) Labour

Mate day 0.52

4 - 305
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Unskilled) day 10.00

Mason 1st Class day 3.00

(b) Machinery

Three wheel 80-100 kN static roller hour 1.00

Water tanker hour 1.00

(c) Material

Brick 1st Class No. 8,160.00

Brick 1st Class on edging No. 1,100.00

Fine Sand cum 5.66

Water kl 6.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 150 sqm = a+b+c+d+e+f

Rate per sqm = (a+b+c+d+e+f)/150

4.19 413 Stone Set Pavement

Providing and laying stone set pavement on prepared surface


with sub-base 100 mm thick compacted Granular Sub-base as
per Clause 401.4 and base 75 mm thick compacted water bound
macadam grading 2 as per Clause 405.3. The 150 mm thick
hammer desired stones are laid in the herring one or stretched
bond pattern. The stones are compacted into the bedding sand of
40 mm over the WBM base bounded by edge stone using suitable
compacting device. The gaps are filled with fine sand stone dust
as per Technical Specification Clause 413.4

Unit = sqm

Taking output = 360 sqm

(a) Labour

Mate day 2.16

Mazdoor (Unskilled) day 51.00

Mason 2nd class for laying sett stone and edge stone day 13.00

(b) Machinery

Three wheel 80-100 kN static roller hour 2.00

4 - 306
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Water tanker 6 kl capacity hour 1.00

(c) Material

(1) Collection of fine sand

3.4x0.285x0.150x1.20 = 0.174 cum 0.174

(2) Coarse sand

96x3.35x0.04x1.20 = 15.437 cum cum 15.437

(3) Collection of stone sett stone


300 mmx200 mmx150 mm Nos 5,168.00
17x304 = 5168 nos.
(4) Collection of edge stone

450 mmx200 mmx350 mm Nos 464.00


2x232 = 464 nos.
(5) Water kl 6.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost of 360 sqm = a+b+c+d+e+f

Rate per sqm = (a+b+c+d+e+f)/360

4 - 307
Chapter 4

BASES (NON-BITUMINOUS) AND SHOULDERS


Rate
Amount (Rs.)
(Rs.)

356.65 171.19

356.65 713.30

244.56 2,445.60

431.00 5,172.00

652.00 19,560.00

431.00 5,172.00

440.00 2,200.00

1,119.00 214,848.00

1,041.50 80,195.50

698.00 80,270.00

40.00 1,200.00

51,493.45

0.00

4 - 308
Rate
Amount (Rs.)
(Rs.)
463,441.04

1,544.80

356.65 171.19

356.65 713.30

244.56 2,445.60

431.00 5,172.00

652.00 19,560.00

431.00 5,172.00

440.00 2,200.00

1,101.00 147,534.00

1,041.50 99,984.00

698.00 106,794.00

40.00 1,200.00

48,868.26

0.00

439,814.35

1,466.05

4 - 309
Rate
Amount (Rs.)
(Rs.)

356.65 171.19

356.65 713.30

244.56 2,445.60

431.00 5,172.00

652.00 19,560.00

431.00 5,172.00

440.00 2,200.00

1,041.50 139,561.00

1,029.00 49,392.00

698.00 140,716.80

40.00 1,200.00

45,787.99

0.00

412,091.88

1,373.64

4 - 310
Rate
Amount (Rs.)
(Rs.)

356.65 142.66

356.65 713.30

244.56 1,956.48

1,149.00 8,617.50

432.00 1,728.00

1,341.00 12,069.00

850.00 11,560.00

3,075.00 13,837.50

652.00 14,670.00

491.58 70,787.52

377.25 21,503.25

348.67 30,125.09

25.00 600.00

23,538.79

211,849.09

941.55

356.65 142.66

4 - 311
Rate
Amount (Rs.)
(Rs.)
356.65 713.30

244.56 1,956.48

1,149.00 8,617.50

432.00 1,728.00

1,341.00 12,069.00

850.00 11,560.00

3,075.00 13,837.50

652.00 14,670.00

411.55 41,484.24

377.25 27,162.00

348.67 40,166.78

25.00 600.00

21,838.43

196,545.90

873.54

356.65 142.66

356.65 713.30

244.56 1,956.48

4 - 312
Rate
Amount (Rs.)
(Rs.)

1,149.00 8,617.50

440.00 1,760.00

1,341.00 11,560.00

850.00 1,156.00

3,075.00 13,837.50

652.00 14,670.00

377.25 38,026.80

377.25 13,581.00

348.67 52,718.90

25.00 600.00

19,917.52

179,257.66

356.65 142.66

356.65 713.30

244.56 1,956.48

4 - 313
Rate
Amount (Rs.)
(Rs.)
431.00 5,172.00

652.00 19,560.00

440.00 2,200.00

431.00 5,172.00

1,124.00 151,065.60

1,089.00 188,179.20

698.00 53,606.40

40.00 1,200.00

53,620.96

0.00

482,588.60

1,608.60

356.65 142.66

356.65 713.30

244.56 1,956.48

4 - 314
Rate
Amount (Rs.)
(Rs.)

431.00 5,172.00

652.00 19,560.00

440.00 2,200.00

431.00 5,172.00

1,089.00 313,632.00

698.00 67,008.00

40.00 1,200.00

52,094.56

0.00

468,851.00

1,562.84

356.65 142.66

356.65 713.30

244.56 1,956.48

4 - 315
Rate
Amount (Rs.)
(Rs.)
431.00 5,172.00

652.00 19,560.00

440.00 2,200.00

431.00 5,172.00

1,084.00 276,420.00

698.00 90,042.00

40.00 1,200.00

50,322.31

0.00

452,900.75

1,509.67

356.65 142.66

356.65 713.3

244.56 1956.48

431.00 5172.00

652.00 19560

440.00 2200.00

431.00 5172

4 - 316
Rate
Amount (Rs.)
(Rs.)

719.82 259136.64

40.00 1200.00

36,906.64

0.00

332159.72

1107.20

356.65 142.66

356.65 713.30

244.56 1956.48

431.00 5172.00

652.00 19560.00

440.00 2200.00

431.00 5172.00

684.43 246394.80

40.00 1200.00

35,313.91

0.00

4 - 317
Rate
Amount (Rs.)
(Rs.)
317825.15

1059.40

356.65 142.66

356.65 713.30

244.56 1956.48

431.00 5172.00

652.00 19560.00

440.00 2200.00

431.00 5172.00

653.52 235267.20

40.00 1200.00

33,922.96

0.00

305306.60

1017.70

4 - 318
Rate
Amount (Rs.)
(Rs.)

356.65 142.66

356.65 713.30

244.56 1956.48

431.00 5172.00

652.00 19560.00

440.00 2200.00

431.00 5172.00

589.68 212284.80

40.00 1200.00

31,050.16

0.00

279451.40

931.5

356.65 142.66

356.65 713.30

244.56 1956.48

4 - 319
Rate
Amount (Rs.)
(Rs.)
431.00 5172.00

652.00 19560.00

440.00 2200.00

431.00 5172.00

558.77 201157.20

40.00 1200.00

29,659.21

0.00

266932.85

889.80

356.65 142.66

356.65 713.30

244.56 1,956.48

431.00 5,172.00

652.00 19,560.00

440.00 2,200.00

4 - 320
Rate
Amount (Rs.)
(Rs.)
431.00 5,172.00

1,029.00 158,054.40

698.00 146,859.20

40.00 1,200.00

42,628.76

0.00

383,516.14

1,278.39

356.65 513.58

356.65 356.65

244.56 8,559.60

652.00 1,401.80

440.00 1,320.00

4 - 321
Rate
Amount (Rs.)
(Rs.)
6,608.00 34,758.08

34.00 612.00

5,940.21

0.00

53,461.92

356.41

356.65 128.39

356.65 356.65

244.56 1,956.48

440.00 5,280.00

431.00 2,586.00

652.00 2,803.60

440.00 2,200.00

6,608.00 69,384.00

34.00 1,020.00

10,714.39

0.00

96,429.51

321.43

4 - 322
Rate
Amount (Rs.)
(Rs.)

356.65 171.19

356.65 713.30

244.56 2,445.60

1,635.00 8,175.00

850.00 11,900.00

431.00 2,586.00

652.00 2,803.60

431.00 5,172.00

440.00 1,760.00

6,608.00 118,944.00

40.00 1,200.00

19,483.84

0.00

175,354.53

584.52

4 - 323
Rate
Amount (Rs.)
(Rs.)

356.65 171.19

356.65 713.30

244.56 2,445.60

1,635.00 8,175.00

850.00 11,900.00

431.00 2,586.00

652.00 2,803.60

431.00 5,172.00

440.00 2,200.00

6,200.00 130,200.00

40.00 1,200.00

20,945.84

0.00

188,512.53

4 - 324
Rate
Amount (Rs.)
(Rs.)
628.38

356.65 3,595.03

356.65 713.30

244.56 61,140.00

652.00 23,472.00

440.00 10,560.00

1,461.00 636,411.60

799.50 77,711.40

220.00 6,336.00

4 - 325
Rate
Amount (Rs.)
(Rs.)
40.00 5,760.00

103,212.42

0.00

928,911.75

2,580.31

356.65 242.52

356.65 713.30

244.56 3,668.40

431.00 3,103.20

652.00 23,472.00

440.00 10,560.00

1,461.00 708,585.00

799.50 77,711.40

220.00 6,336.00

40.00 5,760.00

105,018.98

0.00

4 - 326
Rate
Amount (Rs.)
(Rs.)

945,170.80

2,625.47

356.65 3,595.03

356.65 713.30

244.56 61,140.00

652.00 29,340.00

440.00 10,560.00

1,548.00 688,860.00

710.00 68,167.10

220.00 6,336.00

40.00 5,760.00

4 - 327
Rate
Amount (Rs.)
(Rs.)
109,308.93

0.00

983,780.36

2,732.72

356.65 242.52

356.65 713.30

244.56 3,668.40

431.00 3,103.20

652.00 29,340.00

440.00 10,560.00

1,548.00 657,900.00

710.00 68,167.10

220.00 6,336.00

40.00 5,760.00

98,223.82

0.00

4 - 328
Rate
Amount (Rs.)
(Rs.)

884,014.34

2,455.60

356.65 3,595.03

356.65 713.30

244.56 61,140.00

652.00 29,340.00

440.00 10,560.00

1,635.00 712,206.00

710.00 61,344.00

40.00 5,760.00

110,582.29

4 - 329
Rate
Amount (Rs.)
(Rs.)
0.00

995,240.62

2,764.56

356.65 242.52

356.65 713.30

244.56 3,668.40

431.00 3,103.20

652.00 29,340.00

440.00 10,560.00

1,635.00 711,225.00

710.00 61,344.00

40.00 5,760.00

103,244.55

0.00

929,200.97

2,581.11

4 - 330
Rate
Amount (Rs.)
(Rs.)

356.65 3,595.03

356.65 713.30

244.56 61,140.00

652.00 23,472.00

440.00 10,560.00

1,461.00 628,230.00

400.00 43,200.00

40.00 5,760.00

97,083.79

0.00

873,754.12

2,427.09

4 - 331
Rate
Amount (Rs.)
(Rs.)

356.65 242.52

356.65 713.30

244.56 3,668.40

431.00 3,103.20

652.00 23,472.00

440.00 10,560.00

1,461.00 599,010.00

400.00 43,200.00

40.00 5,760.00

86,216.18

0.00

775,945.60

2,155.40

4 - 332
Rate
Amount (Rs.)
(Rs.)

356.65 3,595.03

356.65 713.30

244.56 61,140.00

652.00 29,340.00

440.00 10,560.00

1,548.00 619,200.00

400.00 42,236.00

40.00 5,760.00

96,568.04

0.00

869,112.37

2,414.20

356.65 242.52

356.65 713.30

244.56 3,668.40

431.00 3,103.20

4 - 333
Rate
Amount (Rs.)
(Rs.)
652.00 29,340.00

440.00 10,560.00

1,548.00 619,200.00

400.00 42,236.00

40.00 5,760.00

89,352.93

0.00

804,176.35

2,233.82

356.65 3,595.03

356.65 713.30

244.56 61,140.00

652.00 29,340.00

4 - 334
Rate
Amount (Rs.)
(Rs.)
440.00 10,560.00

1,635.00 654,000.00

400.00 42,236.00

40.00 5,760.00

100,918.04

0.00

908,262.37

2,522.95

356.65 242.52

356.65 713.30

244.56 3,668.40

431.00 3,103.20

652.00 29,340.00

440.00 10,560.00

1,635.00 640,920.00

400.00 42,236.00

4 - 335
Rate
Amount (Rs.)
(Rs.)
40.00 5,760.00

92,067.93

0.00

828,611.35

2,301.70

356.65 142.66

356.65 2,853.20

356.65 713.30

1,341.00 5,364.00

1,149.00 4,596.00

850.00 4,250.00

431.00 862.00

440.00 585.20

652.00 4,075.00

1,623.00 64,757.70

4 - 336
Rate
Amount (Rs.)
(Rs.)
1,440.50 73,753.60

642.00 25,615.80

40.00 320.00

23,486.06

0.00

211,374.52

2,113.75

356.65 171.19

4 - 337
Rate
Amount (Rs.)
(Rs.)
356.65 713.30

244.56 2,445.60

431.00 2,586.00

652.00 19,560.00

431.00 5,172.00

440.00 2,200.00

698.00 134,016.00

40.00 1,200.00

21,008.01

0.00

189,072.10

630.24

356.65 142.66

356.65 713.30

244.56 1,956.48

431.00 2,586.00

652.00 19,560.00

440.00 2,200.00

431.00 5,172.00

4 - 338
Rate
Amount (Rs.)
(Rs.)

698.00 93,811.20

40.00 1,200.00

15,917.71

0.00

143,259.35

477.53

356.65 242.52

356.65 713.30

244.56 3,668.40

431.00 3,103.20

652.00 29,340.00

440.00 10,560.00

4 - 339
Rate
Amount (Rs.)
(Rs.)
698.00 304,048.80

40.00 5,760.00

44,679.53

0.00

402,115.75

1,116.99

4 - 340
Rate
Amount (Rs.)
(Rs.)

356.65 99.86

244.56 1,467.36

356.65 356.65

1,635.00 9,810.00

850.00 13,600.00

850.00 4,675.00

850.00 3,230.00

55.42 26,603.00

34.63 16,622.50

431.00 2,586.00

431.00 1,379.20

652.00 7,824.00

440.00 5,280.00

6,608.00 145,376.00

0.00

40.00 2,880.00

30,223.70

0.00

272,013.27

566.69

522.00

4 - 341
Rate
Amount (Rs.)
(Rs.)

3,330.09

26,932.00

550.00 211,200.00

40.00 1,200.00

30,332.76

0.00

272,994.85

910.00

4 - 342
Rate
Amount (Rs.)
(Rs.)

65,448.33

34,032.00

550.00 239,580.00

400.00 43,200.00

40.00 5,760.00

48,502.54

0.00

436,522.87

1,212.60

4 - 343
Rate
Amount (Rs.)
(Rs.)

356.65 171.19

356.65 713.30

244.56 2,445.60

850.00 12,750.00

3,075.00 18,450.00

652.00 2,803.60

431.00 5,172.00

440.00 3,080.00

6,200.00 130,200.00

40.00 1,680.00

22,183.21

0.00

199,648.90

665.50

4 - 344
Rate
Amount (Rs.)
(Rs.)

356.65 171.19

356.65 713.30

244.56 2,445.60

431.00 6,034.00

431.00 2,586.00

652.00 29,340.00

440.00 2,640.00

1,936.00 308,714.56

1,440.50 217,601.93

1,104.00 128,814.72

40.00 1,440.00

87,562.66

0.00

788,063.96

2,189.07

4 - 345
Rate
Amount (Rs.)
(Rs.)
356.65 171.19

356.65 713.30

244.56 2,445.60

431.00 6,034.00

431.00 2,586.00

652.00 29,340.00

440.00 2,640.00

1,623.00 39,146.76

1,440.50 313,452.80

1,104.00 235,681.92

40.00 1,440.00

79,206.45

0.00

712,858.02

1,980.16

356.65 99.86

356.65 356.65

244.56 1,467.36

4 - 346
Rate
Amount (Rs.)
(Rs.)

1,149.00 6,894.00

2,073.00 12,438.00

1,341.00 8,046.00

431.00 5,172.00

652.00 18,340.76

440.00 1,320.00

850.00 8,500.00

1,936.00 190,502.40

1,440.50 135,997.61

1,104.00 92,934.72

40.00 720.00

60,348.67

0.00

543,138.03

2,413.95

356.65 99.86

356.65 356.65

244.56 1,467.36

4 - 347
Rate
Amount (Rs.)
(Rs.)
1,149.00 6,894.00

2,073.00 12,438.00

1,341.00 8,046.00

431.00 5,172.00

652.00 18,340.76

440.00 1,320.00

850.00 8,500.00

1,623.00 24,442.38

1,440.50 182,943.50

1,104.00 140,208.00

40.00 720.00

51,368.56

0.00

462,317.08

2,054.74

356.65 185.46

4 - 348
Rate
Amount (Rs.)
(Rs.)
244.56 2,445.60

458.55 1,375.65

652.00 652.00

440.00 440.00

8.00 65,280.00

8.00 8,800.00

850.00 4,811.00

40.00 240.00

10,528.71

0.00

94,758.42

631.72

356.65 770.36

244.56 12,472.56

285.32 3,709.16

652.00 1,304.00

4 - 349
Rate
Amount (Rs.)
(Rs.)
440.00 440.00

850.00 147.90

950.00 14,665.15

35.00 180,880.00

80.00 37,120.00

40.00 240.00

31,468.64

0.00

283,217.78

786.72

4 - 350
Chapter 5

BASES AND SURFACE COURSES (BITUMINOUS)


Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
5.1 502 Prime Coat

(i) Low porosity

Providing and applying primer coat with bitumen emulsion (SS-


1) on prepared surface of granular base including cleaning of
road surface and spraying primer at the rate of 0.70-1.0
kg/sqm using mechanical means as per Technical
Specification Clause 502

Unit = sqm

Taking output = 1750 sqm

a) Labour

Mate day 0.04 356.65 14.27

Mazdoor (Unskilled) day 1.00 244.56 244.56

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 1.40 337.00 471.80

Air compressor 210 cfm hour 1.40 435.00 609.00

Bitumen emulsion pressure distributor @ 1750 sqm per hour 1.00 954.00 954.00
hour

Water tanker 6 kl capacity 1 trip per hour hour 0.50 440.00 220.00

c) Material

Bitumen emulsion (SS-1) @ 0.85 kg per sqm t 1.48 27,509.00 40,713.32

Water kl 3.00 40.00 120.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 5,418.37

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1750 sqm = a+b+c+d+e+f 48,765.31

Rate per sqm = (a+b+c+d+e+f)/1750 27.87

(ii) Medium porosity

Providing and applying primer coat with Bitumen emulsion


(SS-1) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of
0.90- 1.2 kg/sqm using mechanical means as per Technical
Specification Clause 502.

Unit = sqm

Taking output = 1750 sqm

a) Labour

Mate day 0.10 356.65 35.67

Mazdoor (Unskilled) day 2.00 244.56 489.12

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 1.40 337.00 471.80

5 - 351
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Air compressor 210 cfm hour 1.40 435.00 609.00

Bitumen emulsion pressure distributor @ 1750 sqm per hour 1.00 954.00 954.00
hour

Water tanker 6 kl capacity 1 trip per hour hour 0.50 440.00 220.00

c) Material

Bitumen emulsion (SS-1) @ 1.05 kg per sqm t 1.83 27,509.00 50,341.47

Water kl 3.00 40.00 120.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 6,655.13

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1750 sq m =a+b+c+d+e+f 59,896.19

Rate per sqm = (a+b+c+d+e)/1750 34.23

(iii) High porosity

Providing and applying primer coat with Bitumen emulsion


(SS-1) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of 1.2-
1.5 kg/sqm using mechanical means as per Technical
Specification Clause 502.

Unit = sqm

Taking output = 1750 sqm

a) Labour

Mate day 0.12 356.65 42.80

Mazdoor (Unskilled) day 3.00 244.56 733.68

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 1.40 337.00 471.80

Air compressor 210 cfm hour 1.40 435.00 609.00

Bitumen emulsion pressure distributor @ 1750 sqm per hour 1.00 954.00 954.00
hour

Water tanker 6 kl capacity 1 trip per hour hour 0.50 440.00 220.00

c) Material

Bitumen emulsion (SS-1) @ 1.35 kg per sqm t 2.36 27,509.00 64,921.24

Water kl 3.00 40.00 120.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,509.06

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1750 sqm = (a+b+c+d+e+f) 76,581.58

Rate per sqm = a+b+c+d+e+f/1750 43.76

5.2 503 Tack Coat

5 - 352
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
(i) Providing and applying tack coat with Bitumen emulsion (RS-1)
using emulsion distributor at the rate of 0.20 to 0.25 kg per
sqm on the prepared bituminous surface cleaned with
Hydraulic broom as per Technical Specification Clause 503.

Unit = sqm

Taking output = 1750 sqm

a) Labour

Mate day 0.04 356.65 14.27

Mazdoor (Unskilled) day 1.00 244.56 244.56

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 1.40 337.00 471.80

Air compressor 210 cfm hour 1.40 435.00 609.00

Emulsion pressure distributor @1750 sqm per hour hour 1.00 954.00 954.00

c) Material

Bitumen emulsion (RS-1) @ 0.225 kg per sqm t 0.39 28,229.00 11,009.31

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 1,662.87

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1750 sqm = a+b+c+d+e+f 14,965.80

Rate per sqm = (a+b+c+d+e+f)/1750 8.55

(ii) Providing and applying tack coat with Bitumen emulsion (RS-1)
using emulsion distributor at the rate of 0.25 to 0.30 kg per
sqm on the prepared dry and hungry bituminous surface
cleaned with Hydraulic broom as per Technical Specification
Clause 503.

Unit = sqm

Taking output = 1750 sqm

a) Labour

Mate day 0.04 356.65 14.27

Mazdoor (Unskilled) day 1.00 244.56 244.56

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 1.40 337.00 471.80

Air compressor 210 cfm hour 1.40 435.00 609.00

Emulsion pressure distributor @1750 sqm per hour hour 1.00 954.00 954.00

c) Material

Bitumen emulsion (RS-1) @ 0.275 kg per sqm t 0.48 28,229.00 13,549.92

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 1,980.44

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1750 sqm = a+b+c+d 17,823.99

5 - 353
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Rate per sqm = (a+b+c+d+e+f)/1750 10.19

(iii) Providing and applying tack coat with Bitumen emulsion (RS-1)
using emulsion distributor at the rate of 0.25 to 0.30 kg per
sqm on the prepared granular surfaces treated with primer &
cleaned with Hydraulic broom as per Technical Specification
Clause 503.

Unit = sqm

Taking output = 1750 sqm

a) Labour

Mate day 0.04 356.65 14.27

Mazdoor (Unskilled) day 1.00 244.56 244.56

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 1.40 337.00 471.80

Air compressor 210 cfm hour 1.40 435.00 609.00

Emulsion pressure distributor @1750 sqm per hour hour 1.00 954.00 954.00

c) Material

Bitumen emulsion (RS-1) @ 0.275 kg per sqm t 0.48 28,229.00 13,549.92

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 1,980.44

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1750 sqm = a+b+c+d+e+f 17,823.99

Rate per sqm = (a+b+c+d+e+f)/1750 10.19

(iv) Providing and applying tack coat with Bitumen emulsion (RS-1)
using emulsion pressure distributor at the rate of 0.30 to 0.35
kg per sqm on the prepared non-bituminous surfaces (cement
concrete pavement) cleaned with Hydraulic broom as per
Technical Specification Clause 503.

Unit = sqm

Taking output = 1750 sqm

a) Labour

Mate day 0.04 356.65 14.27

Mazdoor (Unskilled) day 1.00 244.56 244.56

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 1.40 337.00 471.80

Air compressor 210 cfm hour 1.40 435.00 609.00

Emulsion pressure distributor @1750 sqm per hour hour 1.00 954.00 954.00

c) Material

Bitumen emulsion (RS-1) @ 0.325 kg per sqm t 0.57 28,229.00 16,090.53

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 2,298.02

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

5 - 354
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

Cost of 1750 sqm = a+b+c+d+e+f 20,682.18

Rate per sqm = (a+b+c+d+e+f) / 1750 11.82

Note: (i) An output of 1750 sqm has been considered in case of tack
coat which can be covered by bituminous courses on the same
day.

(ii) The use of cutback bitumen (Medium Curing grade) as per


IS:217 shall be restricted only for sites at sub-zero temperature
or for emergency applications as directed by the Engineer.

5.3 504 Bituminous Macadam

i) Providing and laying bituminous macadam with hot mix plant using
crushed aggregates of grading as per Table 500.4 premixed with
bituminous binder, transported to site upto a lead of 1000 m laid over
a previously prepared surface with paver finisher to the required
grade, level and alignment and rolled to achieve the desired
compaction as per Technical Specification Clause 504.

Unit = cum
Taking output = 102.5 cum (225 t)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

Batch mix HMP 40-60 THP @ 40 t per hour actual output hour 6.00 12,379.00 74,274.00

Hydraulic broom @ 1250 sqm per hour hour 1.10 337.00 370.70

Air compressor 210 cfm hour 1.10 435.00 478.50

Paver finisher hour 6.00 883.00 5,298.00

Generator 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 cum, 10 t capacity hour 6.21 850.00 5,278.50

Three wheel 80-100 kN static roller for intial break down hour 12.00 652.00 7,824.00
rolling, final and finishing rolling

Vibratory roller 80-100 kN for intermediate rolling hour 6.00 1,687.00 10,122.00
c) Material

i) Bitumen @ 3.3 per cent of mix t 7.425 38,826.00 288,283.05


(Weight of mix = 102.5 x 2.2 = 225 t)

ii) Aggregate

Total weight of mix = 225 t

Weight of bitumen = 7.425 t

Weight of aggregate = 225 – 7.425 = 217.575 t

Taking density of aggregate = 1.5 t/cum

Volume of aggregate = 145.05 cum

5 - 355
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
(19 mm nominal size)

25 -10 mm - 40 per cent cum 58.02 1,827.00 106,002.54

10– 5 mm - 40 per cent cum 58.02 1,846.50 107,133.93

5 mm and below - 20 per cent cum 29.01 1,104.00 32,027.04

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 82,659.66

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 102.5 cum = a+b+c+d+e+f 743,936.93

Rate per cum = a+b+c+d+e+f/102.5 7,257.92

Note: 1 Although the rollers are required only for 3 hours as per norms
of output, but the same have to be available at site for six
hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 225 t considered in these
analysis. To cater for the idle period of these rollers, their
usage rates may be multiplied by a factor of 0.65.

2 Quantity of bitumen has been taken for analysis purpose. The


actual quantity will depend upon job mix formula.

3 Labour for traffic control, watch and ward and other


miscellaneous duties at site, including sundries have been
included in administrative overheads of the contractor.

4 In case BM is laid over freshly laid tack coat, provision of


Hydraulic broom and 2 mazdoor for the same shall be
detected as the same has been included in the cost of tack
coat.

5 Analysis is based on 1000 m lead of mixed material. Cost of


additional cartage may be added as per site requirements.

ii) Providing and laying Cold Mix bituminous macadam with Drum mix
plant using crushed aggregates of grading as per Table 500.4
premixed with Cold mix binder, transported to site upto a lead of
1000 m laid over a previously prepared surface with paver finisher to
the required grade, level and alignment and rolled to achieve the
desired compaction as per Technical Specification (IRC:SP:100-
2014).

Unit = cum
Taking output = 102.5 cum (225 t)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

Drum mix plant for cold mixes of appropriate capacity but hour 6.00 1,859.00 11,154.00
not less than 75 tonnes/hour.
Hydraulic broom @ 1250 sqm per hour hour 1.10 337.00 370.70

Air compressor 210 cfm hour 1.10 435.00 478.50

Paver finisher hour 6.00 883.00 5,298.00

5 - 356
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Generator 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 cum, 10 t capacity hour 6.21 850.00 5,278.50

Three wheel 80-100 kN static roller for intial break down hour 12.00 652.00 7,824.00
rolling, final and finishing rolling

Vibratory roller 80-100 kN for intermediate rolling hour 6.00 1,687.00 10,122.00
c) Material

i) Cold mix binder @ 5.5 per cent of mix t 12.375 42,494.00 525,863.25
(Weight of mix = 102.5 x 2.2 = 225 t)

ii) Aggregate

Total weight of mix = 225 t

Weight of bitumen = 7.425 t

Weight of aggregate = 225 – 12.375 = 212.625 t

Taking density of aggregate = 1.5 t/cum

Volume of aggregate = 141.75 cum

(19 mm nominal size)

25 -10 mm - 40 per cent cum 58.02 1,827.00 106,002.54

10– 5 mm - 40 per cent cum 58.02 1,846.50 107,133.93

5 mm and below - 20 per cent cum 25.71 1,104.00 28,383.84

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 104,011.78

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 102.5 cum = a+b+c+d+e+f 936,106.05

Rate per cum = a+b+c+d+e+f/102.5 9,132.74

5.4 505 Built-Up Spray Grout

Providing, laying and rolling of built-up spray grout layer over


prepared base consisting of a two layer composite construction of
crushed coarse aggregates using motor grader for aggregates. Key
stone chips spreader may be used with application of bituminous
binder after each layer, and with key aggregates placed on top of the
second layer to serve as a base, conforming to the line, grades and
cross-section specified, the compacted layer thickness being 75 mm
as per Technical Specification Clause 505.

(A) By Manual Means

Unit = sqm

Taking output = 800 sqm (60 cum)

(I) Bitumen (S-90)

a) Labour

Mate day 5.50 356.65 1,961.58

Mazdoor (Unskilled) day 100.50 244.56 24,578.28

Chips spreader day 10.00 244.56 2,445.60

5 - 357
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Bitumen Sprayer day 2.50 244.56 611.40

Mazdoor (Semi-Skilled) day 25.50 285.32 7,275.66

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 6.00 2,120.00 12,720.00
spray set
Three wheel 80-100 kN static Roller hour 6.00 652.00 3,912.00

c) Material

Bitumen 30 kg per 10 sqm @ 15 kg per 10 sqm for each t 2.40 38,826.00 93,182.40
layer

Crushed stone coarse aggregate passing 53 mm and cum 80.00 1,174.50 93,960.00
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for each
layer

Key aggregates passing 22.4 mm and retained on 2.8 cum 10.40 1,440.50 14,981.20
mm sieve @ 0.13 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 31,953.51

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 800 sqm = a+b+c+d+e+f 287,581.63

Rate per sqm = (a+b+c+d+e+f)/800 359.48

(II) Bitumen (S-65)

a) Labour

Mate day 5.50 356.65 1,961.58

Mazdoor (Unskilled) day 100.50 244.56 24,578.28

Chips spreader day 10.00 244.56 2,445.60

Bitumen Sprayer day 2.50 244.56 611.40

Mazdoor (Semi-Skilled) day 25.50 285.32 7,275.66

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 6.00 2,120.00 12,720.00
spray set

Three wheel 80-100 kN static Roller hour 6.00 652.00 3,912.00

c) Material
Bitumen 30 kg per 10 sqm @ 15 kg per 10 sqm for each t 2.40 39,783.00 95,479.20
layer

Crushed stone coarse aggregate passing 53 mm and cum 80.00 1,174.50 93,960.00
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for each
layer

Key aggregates passing 22.4 mm and retained on 2.8 cum 10.40 1,440.50 14,981.20
mm sieve @ 0.13 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 32,240.61

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

5 - 358
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Cost of 800 sqm = a+b+c+d+e+f 290,165.53

Rate per sqm = (a+b+c+d+e+f)/800 362.71

(B) By Mechanical Means(S90)

Unit = sqm

Taking output = 3000 sqm (225 cum)

a) Labour

Mate day 0.40 356.65 142.66

Mazdoor (Unskilled) day 8.00 244.56 1,956.48

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic self propelled chip spreader both for hour 6.00 2,380.00 14,280.00
aggregates and key aggregates @ 1500 sqm per hour for
3000 x 3 sqm

Bitumen presssure distributor for 3000x 2 sqm @ 1750 hour 3.43 954.00 3,272.22
sqm per hour

Tipper 5.5 cum capacity hour 10.00 850.00 8,500.00

Three wheel 80-100 kN Static Roller @ 10 cum per hour hour 22.50 652.00 14,670.00

Front end loader 1 cum bucket capacity hour 5.00 1,341.00 6,705.00

c) Material

Bitumen 30 kg per 10 sqm @ 15 kg per 10 sqm for each t 9.00 38,826.00 349,434.00
layer (S90)

Crushed stone coarse aggregate passing 53 mm and cum 300.00 1,174.50 352,350.00
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for each
layer

Key aggregates passing 22.4 mm and retained on 2.8 cum 39.00 1,440.50 56,179.50
mm sieve @ 0.13 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 101,025.40

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 3000 sqm = a+b+c+d+e+f 909,228.56

Rate per sqm = (a+b+c+d+e+f)/3000 303.08

Note: 2 tippers will be needed to match the capacity of hydraulic chip


spreader and front end loader.

5.5 506 Modified Penetration Macadam

Construction of penetration macadam over prepared base by


providing a layer of compacted crushed coarse aggregate using
chips spreader with alternate applications of bituminous binder and
key aggregates and rolling with a three wheel 80-100 kN static roller
to achieve the desired degree of compaction as per Technical
Specification Clause 506.

(A) 50 mm thick

Unit = sqm

5 - 359
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Taking output = 4500 sqm (225 cum)

(I) Bitumen (S-90)

a) Labour

Mate day 0.32 356.65 114.13

Mazdoor (Unskilled) day 6.00 244.56 1,467.36

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic self propelled chip spreader both for hour 6.00 2,380.00 14,280.00
aggregates and key aggregates @ 1500 sqm per hour for
4500 x 2 sqm = 9000 sqm

Bitumen pressure distributor for @ 1750 sqm per hour hour 2.57 954.00 2,451.78

Tipper 5.5 cum capacity for carriage of aggregates from hour 10.00 850.00 8,500.00
stockpile to chip spreader

Three wheel 80-100 kN Static Roller hour 22.50 652.00 14,670.00

Front end loader 1 cum bucked capacity hour 6.00 1,341.00 8,046.00

c) Material

Bitumen @ 1.75 kg per sqm t 7.87 38,826.00 305,560.62

40 mm size hand broken metal @ 0.06 cum per sqm cum 270.00 1,500.00 405,000.00

12 mm size stone chips @ 0.018 cum per sqm cum 81.00 1,510.00 122,310.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 110,389.15

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4500 sqm = a+b+c+d+e+f 993,502.34

Rate per sqm = (a+b+c+d+e+f)/4500 220.78

(B) 75 mm thick

Unit = sqm

Taking output = 4500 sqm (337.5 cum)

(I) Bitumen (S-90)

a) Labour

Mate day 0.40 356.65 142.66


Mazdoor (Unskilled) day 8.00 244.56 1,956.48

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic self propelled chips spreader both for hour 6.00 2,380.00 14,280.00
aggregates and key aggregates @ 1500 sqm per hour for
4500 x 2 sqm

Bitumen presssure distributor for @ 1750 sqm per hour hour 2.57 954.00 2,451.78

Tipper 5.5 cum capacity for carriage of aggregates from hour 10.00 850.00 8,500.00
stockpile to chip spreader

Three wheel 80-100 kN static roller hour 33.75 652.00 22,005.00

5 - 360
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

c) Material

Bitumen @ 2 kg per sqm t 9.00 38,826.00 349,434.00

40 mm size hand broken metal @ 0.09 cum per sqm cum 405.00 1,500.00 607,500.00

12 mm size stone chips @ 0.018 cum per sqm cum 81.00 1,510.00 122,310.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 142,167.40

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4500 sqm = a+b+c+d 1,279,506.62

Rate per sqm = (a+b+c+d+e+f)/4500 284.33

(II) Bitumen (S-65)

a) Labour

Mate day 0.40 356.65 142.66

Mazdoor (Unskilled) day 8.00 244.56 1,956.48

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic self propelled chips spreader both for hour 6.00 2,380.00 14,280.00
aggregates and key aggregates @ 1500 sqm per hour for
4500 x 2 sqm

Bitumen presssure distributor for @ 1750 sqm per hour hour 2.57 954.00 2,451.78

Tipper 5.5 cum capacity for carriage of aggregates from hour 10.00 850.00 8,500.00
stockpile to chip spreader

Three wheel 80-100 kN static roller hour 33.75 652.00 22,005.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

c) Material

Bitumen @ 2 kg per sqm t 9.00 39,783.00 358,047.00

40 mm size hand broken metal @ 0.09 cum per sqm cum 405.00 1,500.00 607,500.00

12 mm size stone chips @ 0.018 cum per sqm cum 81.00 1,510.00 122,310.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 143,244.03

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4500 sqm = a+b+c+d+e+f 1,289,196.25

Rate per sqm = (a+b+c+d+e+f)/4500 286.49

5.6 507 Surface Dressing using Bituminous (Penetrations grade /


modified bitumen) Binder

5 - 361
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Providing and laying surface dressing as wearing course consisting
of a layer of bituminous binder laid on the prepared surface, followed
by a cover of crushed stone aggregates of specified size and rolling
with three wheel 80-100 kN static roller including cleaning the road
surface as per Technical Specification Clause 507.

(A) By Manual Means

Case – I: Nominal chipping size 13.2 mm

(I) Bitumen (S-90)


Unit = sqm

Taking output = 900 sqm

a) Labour

Mate day 2.60 356.65 927.29

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.25 2,120.00 4,770.00
spray set

Three wheel 80-100 kN static roller hour 2.25 652.00 1,467.00

Add: 0.5 per cent of (a) Labour for sundries L.S. 85.34

c) Material

Bitumen (S-90) @ 1.00 kg per sqm t 0.90 38,826.00 34,943.40

Crushed stone chipping, 13.2 mm nominal size @ cum 9.00 1510.00 13,590.00
0.010 cum per sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,990.50

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 900 sqm = a+b+c+d+e+f 80,914.49

Rate per sqm = (a+b+c+d+e+f)/900 89.90

(II) Bitumen (S-65)

Unit = sqm

Taking output = 900 sqm

a) Labour

Mate day 2.60 356.65 927.29

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.25 2,120.00 4,770.00
spray set

5 - 362
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Three wheel 80-100 kN static roller hour 2.25 652.00 1,467.00

Add: 0.5 per cent of (a) Labour for sundries L.S. 85.34125

c) Material

Bitumen (S-65) @ 1.00 kg per sqm t 0.90 39,783.00 35,804.70

Crushed stone chipping, 13.2 mm nominal size @ cum 9.00 1,510.00 13,590.00
0.010 cum per sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 9,098.16

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 900 sqm = a+b+c+d+e+f 81,883.45

Rate per sqm = (a+b+c+d+e+f)/900 90.98

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 900 sqm

a) Labour

Mate day 2.60 356.65 927.29

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.25 2,120.00 4,770.00
spray set

Three wheel 80-100 kN static roller hour 2.25 652.00 1,467.00

Add: 0.5 per cent of (a) Labour for sundries L.S. 85.34125

c) Material

Polymer Modified Bitumen @ 1.00 kg per sqm t 0.90 32,880.00 29,592.00

Crushed stone chipping, 13.2 mm nominal size @ cum 9.00 1,510.00 13,590.00
0.010 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,321.57

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 900 sqm = a+b+c+d+e+f 74,894.17

Rate per sqm = (a+b+c+d+e+f)/900 83.22

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 900 sqm

a) Labour

Mate day 2.60 356.65 927.29

5 - 363
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.25 2,120.00 4,770.00
spray set

Three wheel 80-100 kN static roller hour 2.25 652.00 1,467.00

Add: 0.5 per cent of (a) Labour for sundries L.S. 85.34125

c) Material

Crumb Rubber Modified Bitumen @ 1.00 kg per sqm t 0.90 36,420.00 32,778.00

Crushed stone chipping, 13.2 mm nominal size @ cum 9.00 1,510.00 13,590.00
0.010 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,719.82

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 900 sqm = a+b+c+d+e+f 78,478.42

Rate per sqm = (a+b+c+d+e+f)/900 87.20

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 900 sqm

a) Labour

Mate day 2.60 356.65 927.29

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.25 2,120.00 4,770.00
spray set

Three wheel 80-100 kN static roller hour 2.25 652.00 1,467.00

Add: 0.5 per cent of (a) Labour for sundries L.S. 85.34

c) Material

Natural Rubber Modified Bitumen @ 1.00 kg per sqm t 0.90 0.00 0.00

Crushed stone chipping, 13.2 mm nominal size @ cum 9.00 1,599.50 14,395.50
0.010 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 4,723.26

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 900 sqm = a+b+c+d 42,509.35

Rate per sqm = (a+b+c+d)/900 47.23

5 - 364
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Case – II: Nominal chipping size 9.5 mm

(I) Bitumen (S-90)

Unit = sqm

Taking output = 1000 sqm

a) Labour

Mate day 2.60 356.65 927.29

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.00 2,120.00 4,240.00
spray set

Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

Bitumen (S-90) @ 0.90 kg per sqm t 0.90 38,826.00 34,943.40

Crushed stone chipping, 9.5 mm nominal size @ cum 8.00 1,510.00 12,080.00
0.008 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,704.46

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1000 sqm = a+b+c+d+e+f 78,340.11

Rate per sqm = (a+b+c+d+e+f)/1000 78.34

(II) Bitumen (S-65)

Unit = sqm

Taking output = 1000 sqm

a) Labour

Mate day 2.60 356.65 927.29

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92


b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.00 2,120.00 4,240.00
spray set

Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

5 - 365
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Bitumen (S-65) @ 0.90 kg per sqm t 0.90 39,783.00 35,804.70

Crushed stone chipping, 9.5 mm nominal size @ cum 8.00 1,510.00 12,080.00
0.008 cum per sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,812.12

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1000 sqm = a+b+c+d+e+f 79,309.07

Rate per sqm = (a+b+c+d+e+f)/1000 79.31

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 1000 sqm

a) Labour

Mate day 2.60 356.65 927.29

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

Mazdoor (Semi-Skilled) day 6.00 244.56 1,467.36

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.00 2,120.00 4,240.00
spray set

Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

Polymer Modified Bitumen @ 0.90 kg per sqm t 0.90 32,880.00 29,592.00

Crushed stone chipping, 9.5 mm nominal size @ cum 8.00 1,510.00 12,080.00
0.008 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,004.96

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1000 sqm = a+b+c+d+e+f 72,044.65

Rate per sqm = (a+b+c+d+e+f)/1000 72.04

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 1000 sqm

a) Labour

Mate day 2.60 356.65 927.29

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

5 - 366
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.00 2,120.00 4,240.00
spray set
Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

Crumb Rubber Modified Bitumen @ 0.90 kg per sqm t 0.90 36,420.00 32,778.00

Crushed stone chipping, 9.5 mm nominal size @ cum 8.00 1,510.00 12,080.00
0.008 cum per sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,433.78

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1000 sqm = a+b+c+d+e+f 75,904.03

Rate per sqm = (a+b+c+d+e+f)/1000 75.90

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 1000 sqm

a) Labour

Mate day 2.60 356.65 927.29

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.00 2,120.00 4,240.00
spray set
Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

Natural Rubber Modified Bitumen @ 0.90 kg per sqm t 0.90 0.00 0.00

Crushed stone chipping, 9.5 mm nominal size @ cum 8.00 1,510.00 12,080.00
0.008 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 4,336.53

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1000 sqm = a+b+c+d 39,028.78

Rate per sqm = (a+b+c+d)/1000 39.03

(B) By Mechanical Means

Case – I: Nominal chipping size 13.2 mm

(I) Bitumen (S-90)

Unit = sqm

Taking output = 7500 sqm

5 - 367
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chip spreader @ 1500 sqm hour 6.00 2,380.00 14,280.00
per hour

Tipper 5.5 10 t capacity for carriage of stone chips hour 6.00 850.00 5,100.00
from stockpile on road side to chip spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller weight hour 18.75 652.00 12,225.00

c) Material

Bitumen (S-90) @ 1.00 kg per sqm t 7.50 42,136.00 316,020.00

Crushed stone chipping, 13.2 mm nominal size @ cum 75.00 1,510.00 113,250.00
0.010 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 60,293.53

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 542,641.80

Rate per sqm = (a+b+c+d+e+f)/7500 72.35

(II) Bitumen (S-65)

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chip spreader @ 1500 sqm hour 6.00 2,380.00 14,280.00
per hour
Tipper 5.5 10 t capacity for carriage of stone chips hour 6.00 850.00 5,100.00
from stockpile on road side to chip spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

5 - 368
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller weight hour 18.75 652.00 12,225.00

c) Material

Bitumen (S-65) @ 1.00 kg per sqm t 7.50 39,783.00 298,372.50

Crushed stone chipping, 13.2 mm nominal size @ cum 75.00 1,510.00 113,250.00
0.010 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 58,087.60

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 522,788.36

Rate per sqm = (a+b+c+d+e+f)/7500 69.71

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chip spreader @ 1500 sqm hour 6.00 2,380.00 14,280.00
per hour

Tipper 5.5 10 t capacity for carriage of stone chips hour 6.00 850.00 5,100.00
from stockpile on road side to chip spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller weight hour 18.75 652.00 12,225.00

c) Material

Polymer Modified Bitumen @ 1.00 kg per sqm t 7.50 32,880.00 246,600.00

Crushed stone chipping, 13.2 mm nominal size @ cum 75.00 1,510.00 113,250.00
0.010 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 51,616.03

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 464,544.30

Rate per sqm = (a+b+c+d+e+f)/7500 61.94

5 - 369
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chip spreader @ 1500 sqm hour 6.00 2,380.00 14,280.00
per hour

Tipper 5.5 10 t capacity for carriage of stone chips hour 6.00 850.00 5,100.00
from stockpile on road side to chip spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller weight hour 18.75 652.00 12,225.00

c) Material

Crumb Rubber Modified Bitumen @ 1.00 kg per sqm t 7.50 36,420.00 273,150.00

Crushed stone chipping, 13.2 mm nominal size @ cum 75.00 1,510.00 113,250.00
0.010 cum per sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 54,934.78

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 494,413.05

Rate per sqm = (a+b+c+d+e)/7500 65.92

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

5 - 370
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chip spreader @ 1500 sqm hour 6.00 2,380.00 14,280.00
per hour

Tipper 5.5 10 t capacity for carriage of stone chips hour 6.00 850.00 5,100.00
from stockpile on road side to chip spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller weight hour 18.75 652.00 12,225.00

c) Material

Natural Rubber Modified Bitumen @ 1.00 kg per sqm t 7.50 0.00 0.00

Crushed stone chipping, 13.2 mm nominal size @ cum 75.00 1,510.00 113,250.00
0.010 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 20,791.03

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c 187,119.30

Rate per sqm = (a+b+c+d)/7500 24.95

Case – II: Nominal chipping size 9.5 mm

(I) Bitumen (S-90)

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chips spreader @ 1500 sqm hour 6.00 2,380.00 14,280.00
per hour

Tipper 5.5 10 t capacity for carriage of stone chips hour 6.00 850.00 5,100.00
from stockpile on road side to chips spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor @ 1750 sqm per hour hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller weight hour 15.00 652.00 9,780.00

c) Material

Bitumen (S-90) @ 0.90 kg per sqm t 6.75 38,826.00 262,075.50

Crushed stone chipping, 9.5 mm nominal size @ cum 60.00 1,510.00 90,600.00
0.008 cum per sqm

5 - 371
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 50,413.60

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 453,722.36

Rate per sqm = (a+b+c+d+e+f)/7500 60.50

(II) Bitumen (S-65)

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chips spreader @ 1500 sqm hour 6.00 2,380.00 14,280.00
per hour
Tipper 5.5 10 t capacity for carriage of stone chips hour 6.00 850.00 5,100.00
from stockpile on road side to chips spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor @ 1750 sqm per hour hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller weight hour 15.00 652.00 9,780.00

c) Material

Bitumen (S-65) @ 0.90 kg per sqm t 6.75 39,783.00 268,535.25

Crushed stone chipping, 9.5 mm nominal size @ cum 60.00 1,510.00 90,600.00
0.008 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 51,221.06

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 460,989.58

Rate per sqm = (a+b+c+d+e+f)/7500 61.47

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

5 - 372
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chips spreader @ 1500 sqm hour 6.00 2,380.00 14,280.00
per hour

Tipper 5.5 10 t capacity for carriage of stone chips hour 6.00 850.00 5,100.00
from stockpile on road side to chips spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor @ 1750 sqm per hour hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller weight hour 15.00 652.00 9,780.00

c) Material

Polymer Modified Bitumen @ 0.90 kg per sqm t 6.75 32,880.00 221,940.00

Crushed stone chipping, 9.5 mm nominal size @ cum 60.00 1,510.00 90,600.00
0.008 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 45,396.66

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 408,569.92

Rate per sqm = (a+b+c+d+e+f)/7500 54.48

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chips spreader @ 1500 sqm hour 6.00 2,380.00 14,280.00
per hour

Tipper 5.5 10 t capacity for carriage of stone chips hour 6.00 850.00 5,100.00
from stockpile on road side to chips spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

5 - 373
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Bitumen pressure distributor @ 1750 sqm per hour hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller weight hour 15.00 652.00 9,780.00

c) Material

Crumb Rubber Modified Bitumen @ 0.90 kg per sqm t 6.75 36,420.00 245,835.00

Crushed stone chipping, 9.5 mm nominal size @ cum 60.00 1,510.00 90,600.00
0.008 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 48,383.53

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 435,451.80

Rate per sqm = (a+b+c+d+e+f)/7500 58.06

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chips spreader @ 1500 sqm hour 6.00 2,380.00 14,280.00
per hour

Tipper 5.5 10 t capacity for carriage of stone chips hour 6.00 850.00 5,100.00
from stockpile on road side to chips spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor @ 1750 sqm per hour hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller weight hour 15.00 652.00 9,780.00

c) Material

Natural Rubber Modified Bitumen @ 0.90 kg per sqm t 6.75 0.00 0.00

Crushed stone chipping, 9.5 mm nominal size @ cum 60.00 1,510.00 90,600.00
0.008 cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 17,654.16

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

5 - 374
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Cost of 7500 sqm = a+b+c+d 158,887.42

Rate per sqm = (a+b+c+d)/7500 21.18

5.7 507 Surface Dressing using Bitumen Emulsion

Providing and laying surface dressing as wearing course consisting


of a layer of bitumen emulsion laid on the prepared surface, followed
by a cover of crushed stone chippings of specified size and rolling
with 80-100 kN roller including cleaning the road surface as per
Technical Specification Clause 507.

(A) By Manual Means

Case – I: Nominal aggregate size 13.2 mm

Unit = sqm

Taking output = 900 sqm

a) Labour

Mate day 2.36 356.65 841.69

Bitumen Emulsion Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

b) Machinery

Emulsion sprayer, capacity 1000 litre fitted with spray set hour 2.25 954.00 2,146.50

Three wheel 80-100 kN static roller hour 2.25 652.00 1,467.00

Add: 0.5 per cent of (a) Labour for sundries L.S. 0.5/100 36.19

c) Material

Bitumen Emulsion (RS-1) @ 1.50 kg per sqm t 1.35 28,229.00 38,109.15

Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum 9.00 1,510.00 13,590.00
cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,827.45

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 900 sqm = a+b+c+d+e+f 79,447.02

Rate per sqm = (a+b+c+d)/900 88.27

Case – II: Nominal chipping size 9.5 mm

Unit = sqm

Taking output = 1000 sqm

a) Labour

Mate day 2.36 356.65 841.69

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 58.00 244.56 14,184.48

b) Machinery

5 - 375
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Emulsion sprayer, capacity 1000 litre fitted with spray set hour 2.00 954.00 1,908.00

Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

Bitumen Emulsion (RS-1) @ 1.40 kg per sqm t 1.40 28,229.00 39,520.60

Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum 8.00 1,510.00 12,080.00
cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,760.42

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1000 sqm = a+b+c+d+e+f 78,843.75

Rate per sqm = (a+b+c+d+e+f)/1000 78.84

(B) By Mechanical Means

Case – I: Nominal chipping size 13.2 mm

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.00 2,380.00 14,280.00
hour

Tipper 5.5 10 t capacity for carriage of stone chips from hour 6.00 850.00 5,100.00
stockpile on road side to chip spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen Emulsion pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller hour 18.75 652.00 12,225.00

c) Material

Bitumen Emulsion (RS-1) @ 1.50 kg per sqm t 11.25 28,229.00 317,576.25

Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum 75.00 1,510.00 113,250.00
cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 60,488.06

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 544,392.58

5 - 376
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Rate per sqm = (a+b+c+d)/7500 72.59

Case – II: Nominal chipping size 9.5 mm

Unit = sqm

Taking output = 7500 sqm

a) Labour

Mate day 0.44 356.65 156.93

Mazdoor (Unskilled) day 9.00 244.56 2,201.04

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Hydraulic broom @ 1250 sqm per hour hour 6.00 337.00 2,022.00

Air compressor 210 cfm hour 6.00 435.00 2,610.00

Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.00 2,380.00 14,280.00
hour

Tipper 5.5 10 t capacity for carriage of stone chips from hour 6.00 850.00 5,100.00
stockpile on road side to chip spreader

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen emulsion pressure distributor @ 1750 sqm per hour 6.00 954.00 5,724.00
hour

Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Bitumen Emulsion (RS-1) @ 1.40 kg per sqm t 10.50 28,229.00 296,404.50

Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum 60.00 1,510.00 90,600.00
cum per sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 54,704.72

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 492,342.49

Rate per sqm = (a+b+c+d+e+f)/7500 65.65

Note: Where the proposed aggregate fails to pass the stripping value
test, an approved adhesion agent may be added to the binder
as per Clause 507.24. Alternatively, chips may be pre-coated
as per Clause 507.25.

5.8 507.2.5 Pre-coating Chips

Pre-coating of chips with 1 per cent of paving bitumen by weight of


chips in a suitable mixer duly heated to 160 degree C as per
Technical Specification Clause 507.2.5

Unit = cum

Taking output = 30 cum

(I) Bitumen (S-90)

a) Labour

5 - 377
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Mate day 0.60 356.65 213.99

Mazdoor (Unskilled) day 15.00 244.56 3,668.40

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre itre hour 6.00 2,120.00 12,720.00

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

c) Material

Bitumen @1 per cent by weight of chips (30x1.6)/100 t 0.48 38,826.00 18,636.48

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 5,669.36

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 30 cum = a+b+c+d+e+f 51,024.23

Rate per cum = (a+b+c+d)/30 1,700.81

(II) Bitumen (S-65)

a) Labour

Mate day 0.60 356.65 213.99

Mazdoor (Unskilled) day 15.00 244.56 3,668.40

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre itre hour 6.00 2,120.00 12,720.00

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

c) Material

Bitumen @1 per cent by weight of chips (30x1.6)/100 t 0.48 39,783.00 19,095.84

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 5,726.78

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 30 cum = a+b+c+d+e+f 51,541.01

Rate per cum = (a+b+c+d)/30 1,718.03

5.9 508 20mm thick Open-Graded Premix Carpet using Bituminous


(penetration grade/modified bitumen) Binder

Providing, laying and rolling of open-graded premix carpet of 20 mm


thickness composed of 13.2 mm to 5.6 mm aggregates either using
penetration grade bitumen or emulsion to required line, grade and
level to serve as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling with a three
wheel 80-100 kN static roller capacity, finished to required level and
grades to be followed by seal coat of either Type A or Type B or Type
C as per Technical Specification Clause 508.

Case - I By Manual Means

(I) Bitumen (S-90)

5 - 378
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Unit = sqm

Taking output = 500 sqm (10 cum)

a) Labour

Mate day 1.08 356.65 385.18

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Mixall 6/10 t capacity hour 4.00 1,686.00 6,744.00

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 4.00 2,120.00 8,480.00
set

Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

Bitumen (S-90) @ 14.60 kg per 10 sqm t 0.73 38,826.00 28,342.98

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 13.50 1,599.50 21,593.25
per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 9,212.14

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d+e+f 82,909.23

Rate per sqm = (a+b+c+d+e+f)/500 165.82

(II) Bitumen (S-65)

Unit = sqm

Taking output = 500 sqm (10 cum)

a) Labour

Mate day 1.08 356.65 385.18

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Mixall 6/10 t capacity hour 4.00 1,686.00 6,744.00

Bitumen boiler oil fired1000 litre capacity fitted with spray hour 4.00 2,120.00 8,480.00
set

Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

Bitumen (S-65) @ 14.60 kg per 10 sqm t 0.73 39,783.00 29,041.59

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 13.50 1,510.00 20,385.00
per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 9,148.43

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

5 - 379
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Cost of 500 sqm = a+b+c+d+e+f 82,335.88

Rate per sqm = (a+b+c+d+e+f)/500 164.67

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 500 sqm (10 cum)

a) Labour
Mate day 1.08 356.65 385.18

Mazdoor (Skilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Mixall 6/10 t capacity hour 4.00 1,686.00 6,744.00

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 4.00 2,120.00 8,480.00
set

Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

Polymer Modified Bitumen @ 14.60 kg per 10 sqm t 0.73 32,880.00 24,002.40

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 13.50 1,510.00 20,385.00
per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,518.53

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d+e+f 76,666.79

Rate per sqm = (a+b+c+d+e+f)/500 153.33

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 500 sqm (10 cum)

a) Labour

Mate day 1.08 356.65 385.18

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 6.00 244.56 1,467.36

b) Machinery

Mixall 6/10 t capacity hour 4.00 1,686.00 6,744.00

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 4.00 2,120.00 8,480.00
set

Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

Crumb Rubber Modified Bitumen @ 14.60 kg per 10 sqm t 0.73 36,420.00 26,586.60

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 13.50 1,510.00 20,385.00
per 10 sqm

5 - 380
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,810.99

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d+e+f 79,298.89

Rate per sqm = (a+b+c+d+e+f)/500 158.60

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 500 sqm (10 cum)

a) Labour

Mate day 1.08 356.65 385.18

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 6.00 244.56 1,467.36

b) Machinery

Mixall 6/10 t capacity hour 4.00 1,686.00 6,744.00

Bitumen boiler oil fired1000 litre capacity fitted with spray hour 4.00 2,120.00 8,480.00
set

Three wheel 80-100 kN static roller hour 2.00 652.00 1,304.00

c) Material

Natural Rubber Modified Bitumen @ 14.60 kg per 10 sqm t 0.73 0.00 0.00

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 13.50 1,510.00 20,385.00
per 10 sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 5,487.66

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d 49,388.96

Rate per sqm = (a+b+c+d)/500 98.78

Case - II By Mechanical Means

(I) Bitumen (S-90)

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP 30/40 t per hour hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

5 - 381
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Tipper 5.5 10 t capacity hour 3.64 850.00 3,094.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 16.00 652.00 10,432.00

c) Material

Bitumen (S-90) @ 14.60 kg per 10 sqm t 5.84 38,826.00 226,743.84

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 108.00 1,510.00 163,080.00
per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 59,042.11

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 531,378.95

Rate per sqm = (a+b+c+d+e+f)/4000 132.84

(II) Bitumen (S-65)

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP 30/40 t per hour hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.64 850.00 3,094.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 16.00 652.00 10,432.00

c) Material

Bitumen (S-65) @ 14.60 kg per 10 sqm t 5.84 39,783.00 232,332.72

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 108.00 1,510.00 163,080.00
per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 59,740.72

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 537,666.44

Rate per sqm = (a+b+c+d+e+f)/4000 134.42

(III) Polymer Modified Bitumen

Unit = sqm

5 - 382
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor skilled for checking line and levels day 3.00 356.65 1,069.95

b) Machinery

HMP 30/40 t per hour hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.64 850.00 3,094.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 16.00 652.00 10,432.00

c) Material

Polymer Modified Bitumen @ 14.60 kg per 10 sqm t 5.84 32,880.00 192,019.20

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 108.00 1,510.00 163,080.00
per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 54,701.53

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 492,313.73

Rate per sqm = (a+b+c+d+e+f)/4000 123.08

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP 30/40 t per hour hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.64 850.00 3,094.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 16.00 652.00 10,432.00

5 - 383
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
c) Material

Crumb Rubber Modified Bitumen @ 14.60 kg per 10 sqm t 5.84 36,420.00 212,692.80

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 108.00 1,510.00 163,080.00
per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 57,285.73

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 515,571.53

Rate per sqm = (a+b+c+d+e+f)/4000 128.89

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP 30/40 t per hour hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.64 850.00 3,094.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 16.00 652.00 10,432.00

c) Material

Natural Rubber Modified Bitumen @ 14.60 kg per 10 sqm t 5.84 0.00 0.00

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 108.00 1,510.00 163,080.00
per 10 sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 30,699.13

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d 276,292.13

Rate per sqm = (a+b+c+d)/4000 69.07

5.10 508.2 20 mm thick Open Graded Premix Carpet using Bitumen


Emulsion as per Technical Specification Clause 508.2

Unit = sqm

Taking output = 900 sqm (24.3 cum)

a) Labour

Mate day 0.80 356.65 285.32

5 - 384
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Mazdoor (Unskilled) day 18.00 244.56 4,402.08

Mazdoor (Skilled) day 2.00 356.65 713.30

b) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 6.00 188.00 1,128.00

Three wheel 80-100 kN static roller hour 3.60 652.00 2,347.20

c) Material

Bitumen emulsion (RS-1) @ 21.50 kg per 10 sqm t 1.94 28,229.00 54,764.26

Crushed stone aggregates 13.2 mm to 5.6 mm @ 0.27 cum cum 24.30 1,510.00 36,693.00
per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 12,541.65

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 900 sqm = a+b+c+d+e+f 112,874.81

Rate per sqm = (a+b+c+d)/900 125.00

5.11 509 Mix Seal Surfacing

Providing, laying and rolling of close-graded premix surfacing


material of 20 mm thickness composed of 11.2 mm to 0.9 mm (Type-
A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration
grade bitumen to required line, grade and level to serve as wearing
course on a previously prepared base, including mixing in a suitable
plant, laying and rolling with a three wheel 8-10 kN static roller and
finishing to required level and grades as per Technical Specification
Clause 509

By Manual Means

Type A

(I) Bitumen (S-90)

Unit = sqm

Taking output = 500 sqm

a) Labour

Mate day 1.40 356.65 499.31

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 7.00 285.32 1,997.24

b) Machinery

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

Oil fired bitumen boiler 1000 litre capacity fitted with spray hour 6.00 2,120.00 12,720.00
set

Three wheel 80-100 kN static roller hour 6.00 652.00 3,912.00

c) Material

5 - 385
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Bitumen (S-90) @ 22 kg per 10 sqm t 1.10 38,826.00 42,708.60

Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum 13.50 1,510.00 20,385.00
cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 12,184.24

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d+e+f 109,158.84

Rate per sqm = (a+b+c+d+e+f)/500 218.32

(II) Bitumen (S-65)

Unit = sqm

Taking output = 500 sqm

a) Labour

Mate day 1.40 356.65 499.31

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 7.00 285.32 1,997.24

b) Machinery

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

Oil fired bitumen boiler 1000 litre capacity fitted with spray hour 6.00 2,120.00 12,720.00
set

Three wheel 80-100 kN static roller hour 6.00 652.00 3,912.00

c) Material

Bitumen (S-65) @ 22 kg per 10 sqm t 1.10 39,783.00 43,761.30

Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum 13.50 1,510.00 20,385.00
cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 12,315.83

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d+e+f 110,343.13

Rate per sqm = (a+b+c+d+e+f)/500 220.69

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 500 sqm

a) Labour

Mate day 1.40 356.65 499.31

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 7.00 285.32 1,997.24

5 - 386
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
b) Machinery

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

Oil fired bitumen boiler 1000 litre capacity fitted with spray hour 6.00 2,120.00 12,720.00
set

Three wheel 80-100 kN static roller hour 6.00 652.00 3,912.00

c) Material

Polymer Modified Bitumen @ 22 kg per 10 sqm t 1.10 32,880.00 36,168.00

Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum 13.50 1,510.00 20,385.00
cum per 10 sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 11,366.66

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d+e+f 101,800.66

Rate per sqm = (a+b+c+d+e+f)/500 203.60

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 500 sqm

a) Labour

Mate day 1.40 356.65 499.31

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 7.00 285.32 1,997.24

b) Machinery

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

Oil fired bitumen boiler 1000 litre capacity fitted with spray hour 6.00 2,120.00 12,720.00
set

Three wheel 80-100 kN static roller hour 6.00 652.00 3,912.00

c) Material

Crumb Rubber Modified Bitumen @ 22 kg per 10 sqm t 1.10 36,420.00 40,062.00

Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum 13.50 1,510.00 20,385.00
cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 11,853.41

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d+e+f 106,181.41

Rate per sqm = (a+b+c+d+e+f)/500 212.36

(V) Using Cold mix Binder (Tailor made as per IRC:SP:100-2014)

Unit = sqm

5 - 387
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Taking output = 500 sqm

a) Labour

Mate day 1.40 356.65 499.31

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 7.00 285.32 1,997.24

b) Machinery

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

Oil fired bitumen boiler 1000 litre capacity fitted with spray hour 6.00 2,120.00 12,720.00
set

Three wheel 80-100 kN static roller hour 6.00 652.00 3,912.00

c) Material

Using Cold mix Binder (Tailor made as per IRC:SP:100- t 1.10 42,494.00 46,743.40
2014) @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum 13.50 1,510.00 20,385.00
cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 12,688.59

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d 113,697.99

Rate per sqm = (a+b+c+d)/500 227.40

Type B

(I) Bitumen (S-90)

Unit = sqm

Taking output = 500 sqm

a) Labour

Mate day 1.40 356.65 499.31

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 7.00 285.32 1,997.24

b) Machinery

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

Oil fired bitumen boiler 1000 litre capacity fitted with spray hour 6.00 2,120.00 12,720.00
set

Three wheel 80-100 kN static roller hour 6.00 652.00 3,912.00

c) Material

Bitumen (S-90) @ 19 kg per 10 sqm t 0.95 38,826.00 36,884.70

Stone crushed aggregates 13.2 mm to 0.09 mm @ cum 13.50 1,510.00 20,385.00


0.27cum per 10 sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 11,456.25

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

5 - 388
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

Cost of 500 sqm = a+b+c+d+e+f 102,606.95

Rate per sqm = (a+b+c+d+e+f)/500 205.21

(II) Bitumen (S-65)

Unit = sqm

Taking output = 500 sqm

a) Labour

Mate day 1.40 356.65 499.31

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 7.00 285.32 1,997.24

b) Machinery

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

Oil fired bitumen boiler 1000 litre capacity fitted with spray hour 6.00 2,120.00 12,720.00
set
Three wheel 80-100 kN static roller hour 6.00 652.00 3,912.00

c) Material

Bitumen (S-65) @ 19 kg per 10 sqm t 0.95 39,783.00 37,793.85

Stone crushed aggregates 13.2 mm to 0.09 mm @ cum 13.50 1,510.00 20,385.00


0.27cum per 10 sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 11,569.90

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d+e+f 103,629.75

Rate per sqm = (a+b+c+d+e+f)/500 207.26

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 500 sqm

a) Labour

Mate day 1.40 356.65 499.31

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 7.00 285.32 1,997.24

b) Machinery

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

Oil fired bitumen boiler 1000 litre capacity fitted with spray hour 6.00 2,120.00 12,720.00
set
Three wheel 80-100 kN static roller hour 6.00 652.00 3,912.00

c) Material
Polymer Modified Bitumen @ 19 kg per 10 sqm t 0.95 32,880.00 31,236.00

5 - 389
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Stone crushed aggregates 13.2 mm to 0.09 mm @ cum 13.50 1,510.00 20,385.00
0.27cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 10,750.16

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d+e+f 96,252.16

Rate per sqm = (a+b+c+d+e+f)/500 192.50

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 500 sqm

a) Labour

Mate day 1.40 356.65 499.31

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 7.00 285.32 1,997.24

b) Machinery

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

Oil fired bitumen boiler 1000 litre capacity fitted with spray hour 6.00 2,120.00 12,720.00
set
Three wheel 80-100 kN static roller hour 6.00 652.00 3,912.00

c) Material

Crumb Rubber Modified Bitumen @ 19 kg per 10 sqm t 0.95 36,420.00 34,599.00

Stone crushed aggregates 13.2 mm to 0.09 mm @ cum 13.50 1,510.00 20,385.00


0.27cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 11,170.54

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d+e+f 100,035.54

Rate per sqm = (a+b+c+d+e+f)/500 200.07

(V) Using Cold mix Binder (Tailor made as per IRC:SP:100-2014)

Unit = sqm

Taking output = 500 sqm

a) Labour

Mate day 1.40 356.65 499.31

Mazdoor (Unskilled) day 21.00 244.56 5,135.76

Mazdoor (Semi-Skilled) day 7.00 285.32 1,997.24

b) Machinery

Mixall 6-10 t capacity hour 6.00 1,686.00 10,116.00

Oil fired bitumen boiler 1000 litre capacity fitted with spray hour 6.00 2,120.00 12,720.00
set

5 - 390
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Three wheel 80-100 kN static roller hour 6.00 652.00 3,912.00

c) Material

Using Cold mix Binder (Tailor made as per IRC:SP:100- t 0.95 42,494.00 40,369.30
2014) @ 19 kg per 10 sqm

Stone crushed aggregates 13.2 mm to 0.09 mm @ cum 13.50 1,510.00 20,385.00


0.27cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 11,891.83

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 500 sqm = a+b+c+d 106,527.13

Rate per sqm = (a+b+c+d)/500 213.05

By Mechanical Means

Type A

(I) Bitumen (S-90)

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP of appropriate capacity hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.60 850.00 3,060.00


Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 18.00 652.00 11,736.00

c) Material

Bitumen (S-90) @ 22 kg per 10 sqm t 8.80 38,826.00 341,668.80

Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum 108.00 1,510.00 163,080.00
cum per 10 sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 73,566.48

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 662,098.28

Rate per sqm = (a+b+c+d+e+f)/4000 165.52

(II) Bitumen (S-65)

Unit = sqm

5 - 391
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP of appropriate capacity hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.60 850.00 3,060.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 18.00 652.00 11,736.00

c) Material

Bitumen (S-65) @ 22 kg per 10 sqm t 8.80 39,783.00 350,090.40

Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum 108.00 1,510.00 163,080.00
cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 74,619.18

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 671,572.58

Rate per sqm = (a+b+c+d+e+f)/4000 167.89

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP of appropriate capacity hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.60 850.00 3,060.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 18.00 652.00 11,736.00

c) Material

5 - 392
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Polymer Modified Bitumen @ 22 kg per 10 sqm t 8.80 32,880.00 289,344.00

Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum 108.00 1,510.00 163,080.00
cum per 10 sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 67,025.88

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 603,232.88

Rate per sqm = (a+b+c+d+e+f)/4000 150.81

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP of appropriate capacity hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.60 850.00 3,060.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 18.00 652.00 11,736.00

c) Material

Crumb Rubber Modified Bitumen @ 22 kg per 10 sqm t 8.80 36,420.00 320,496.00

Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum 108.00 1,510.00 163,080.00
cum per 10 sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 70,919.88

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 638,278.88

Rate per sqm = (a+b+c+d)/4000 159.57

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

5 - 393
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP of appropriate capacity hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.60 850.00 3,060.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 18.00 652.00 11,736.00

c) Material

* Natural Rubber Modified Bitumen @ 22 kg per 10 sqm t 8.80 0.00 0.00

Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum 108.00 1,510.00 163,080.00
cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 30,857.88

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d 277,720.88

Rate per sqm = (a+b+c+d)/4000 69.43

Type B

(I) Bitumen (S-90)

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP of appropriate capacity hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.60 850.00 3,060.00

Add 10 per cent of cost of carriage to cover cost of 306.00


loading and unloading

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 18.00 652.00 11,736.00

c) Material

5 - 394
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Bitumen (S-90) @ 19 kg per 10 sqm t 7.60 38,826.00 295,077.60

Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum 108.00 1,510.00 163,080.00
cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 67,780.83

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 610,027.43

Rate per sqm = (a+b+c+d+e+f)/4000 152.51

(II) Bitumen (S-65)

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP of appropriate capacity hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.60 850.00 3,060.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 18.00 652.00 11,736.00

c) Material

Bitumen (S-65) @ 19 kg per 10 sqm t 7.60 39,783.00 302,350.80

Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum 108.00 1,510.00 163,080.00
cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 68,651.73

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 617,865.53

Rate per sqm = (a+b+c+d+e+f)/4000 154.47

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

5 - 395
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP of appropriate capacity hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.60 850.00 3,060.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 18.00 652.00 11,736.00

c) Material

Polymer Modified Bitumen @ 19 kg per 10 sqm t 7.60 32,880.00 249,888.00

Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum 108.00 1,510.00 163,080.00
cum per 10 sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 62,093.88

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 558,844.88

Rate per sqm = (a+b+c+d+e+f)/4000 139.71

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP of appropriate capacity hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.60 850.00 3,060.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 18.00 652.00 11,736.00

c) Material

Crumb Rubber Modified Bitumen @ 19 kg per 10 sqm t 7.60 36,420.00 276,792.00

5 - 396
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum 108.00 1,510.00 163,080.00
cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 65,456.88

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d+e+f 589,111.88

Rate per sqm = (a+b+c+d+e+f)/4000 147.28

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 4000 sqm (80 cum)

a) Labour

Mate day 0.52 356.65 185.46

Mazdoor (Unskilled) day 10.00 244.56 2,445.60

Mazdoor (Skilled) day 3.00 356.65 1,069.95

b) Machinery

HMP of appropriate capacity hour 6.00 6,584.00 39,504.00

Electric generator set 125 KVA hour 6.00 2,073.00 12,438.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Tipper 5.5 10 t capacity hour 3.60 850.00 3,060.00

Paver finisher hour 6.00 883.00 5,298.00

Three wheel 80-100 kN static roller hour 18.00 652.00 11,736.00

c) Material

Natural Rubber Modified Bitumen @ 19 kg per 10 sqm t 7.60 0.00 0.00

Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum 108.00 1,510.00 163,080.00
cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 30,857.88

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 4000 sqm = a+b+c+d 277,720.88

Rate per sqm = (a+b+c+d)/4000 69.43

* Any one of the above alternatives may be adopted.

5.12 510 Seal Coat

Providing and laying seal coat sealing the voids in a bituminous


surface laid to the specified levels, grade and cross fall using Type
A, Type B and Type C as per Technical Specification Clause 510

A. By Manual Means

Case - I : Type A

5 - 397
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
(I) Bitumen (S-90)

Unit = sqm

Taking output = 1100 sqm

a) Labour

Mate day 1.15 356.65 410.15

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 22.00 244.56 5,380.32

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.20 212.00 466.40
spray set
Three wheel 80-100 kN static roller hour 2.20 652.00 1,434.40

c) Material

Bitumen (S-90) @ 9.80 kg per 10 sqm t 1.078 38,826.00 41,854.43

Crushed stone chipping of 6.7 mm size 100 per cent cum 9.90 1,510.00 14,949.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,306.40

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1100 sqm = a+b+c+d+e+f 74,757.57

Rate per sqm = (a+b+c+d+e+f)/1100 67.96

(II) Bitumen (S-65)

Unit = sqm

Taking output = 1100 sqm

a) Labour

Mate day 1.15 356.65 410.15

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 22.00 244.56 5,380.32

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.20 212.00 466.40
spray set
Three wheel 80-100 kN static roller hour 2.20 652.00 1,434.40

c) Material

Bitumen (S-65) @ 9.80 kg per 10 sqm t 1.078 39,783.00 42,886.07

Crushed stone chipping of 6.7 mm size 100 per cent cum 9.90 1,510.00 14,949.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

5 - 398
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 8,435.35

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1100 sqm = a+b+c+d+e+f 75,918.17

Rate per sqm = (a+b+c+d)/1100 69.02

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 1100 sqm

a) Labour

Mate day 1.15 356.65 410.15

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 22.00 244.56 5,380.32

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.00 212.00 424.00
spray set

Three wheel 80-100 kN static roller hour 2.20 652.00 1,434.40

c) Material

Polymer Modified Bitumen @ 9.80 kg per 10 sqm t 1.078 32,880.00 35,444.64

Crushed stone chipping of 6.7 mm size 100 per cent cum 9.90 1,510.00 14,949.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 7,499.87

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1100 sqm = a+b+c+d+e+f 67,498.86

Rate per sqm = (a+b+c+d+e+f)/1100 61.36

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 1100 sqm


a) Labour

Mate day 1.15 356.65 410.15

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 22.00 244.56 5,380.32

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

5 - 399
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.20 212.00 466.40
spray set
Three wheel 80-100 kN static roller hour 2.20 652.00 1,434.40

c) Material

Crumb Rubber Modified Bitumen @ 9.80 kg per 10 sqm t 1.078 36,420.00 39,260.76

Crushed stone chipping of 6.7 mm size 100 per cent cum 9.90 1,510.00 14,949.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 7,982.19

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1100 sqm = a+b+c+d+e+f 71,839.70

Rate per sqm = (a+b+c+d+e+f)/1100 65.31

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 1100 sqm

a) Labour

Mate day 1.15 356.65 410.15

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 22.00 244.56 5,380.32

Mazdoor (Semi-Skilled) day 6.00 285.32 1,711.92

b) Machinery

Bitumen boiler oil fired, capacity 1000 litre fitted with hour 2.20 212.00 466.40
spray set

Three wheel 80-100 kN static roller hour 2.20 652.00 1,434.40

c) Material

Natural Rubber Modified Bitumen @ 9.80 kg per 10 sqm t 1.078 0.00 0.00

Crushed stone chipping of 6.7 mm size 100 per cent cum 9.90 1,510.00 14,949.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 3,074.59

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1100 sqm = a+b+c+d 27,671.34

Rate per sqm = (a+b+c+d+e)/1100 25.16

Case - II : Type B

(I) Bitumen (S-90)

Unit = sqm

Taking output = 1250 sqm

a) Labour

5 - 400
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Mate day 0.85 356.65 303.15

Mazdoor (Unskilled) day 15.00 244.56 3,668.40

Mazdoor (Semi-Skilled) day 2.00 285.32 570.64

b) Machinery

Mixall 6/10 t capacity hour 2.50 1,686.00 4,215.00

Three wheel 80-100 kN static roller hour 3.50 652.00 2,282.00

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 2.50 2,120.00 5,300.00
set

c) Material

Bitumen (S-90) @ 6.80 kg per 10 sqm t 0.85 38,826.00 33,002.10

Crushed sand or grit as passing 2.36 mm sieve and cum 7.50 6,375.00
retained on 180 micron sieve applied @ 0.06 cum per 10
sqm 850.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 6,964.54

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1250 sqm = a+b+c+d+e+f 62,680.83

Rate per sqm = (a+b+c+d+e+f)/1250 50.14

(II) Bitumen (S-65)

Unit = sqm

Taking output = 1250 sqm

a) Labour

Mate day 0.85 356.65 303.15

Mazdoor (Unskilled) day 15.00 244.56 3,668.40

Mazdoor (Semi-Skilled) day 2.00 285.32 570.64

b) Machinery

Mixall 6/10 t capacity hour 2.50 1,686.00 4,215.00

Three wheel 80-100 kN static roller hour 2.50 652.00 1,630.00

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 2.50 2,120.00 5,300.00
set

c) Material

Bitumen (S-65) @ 6.80 kg per 10 sqm t 0.85 39,783.00 33,815.55

Crushed sand or grit as passing 2.36 mm sieve and cum 7.50 850.00 6,375.00
retained on 180 micron sieve applied @ 0.06 cum per 10
sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 6,984.72

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1250 sqm = a+b+c+d+e+f 62,862.46

5 - 401
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Rate per sqm = (a+b+c+d+e+f)/1250 50.29

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 1250 sqm

a) Labour

Mate day 0.85 356.65 303.15

Mazdoor (Unskilled) day 15.00 244.56 3,668.40

Mazdoor (Semi-Skilled) day 2.00 285.32 570.64

b) Machinery

Mixall 6/10 t capacity hour 2.50 1,686.00 4,215.00

Three wheel 80-100 kN static roller hour 2.50 652.00 1,630.00

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 2.50 2,120.00 5,300.00
set

c) Material

Polymer Modified Bitumen @ 6.80 kg per 10 sqm t 0.85 32,880.00 27,948.00

Crushed sand or grit as passing 2.36 mm sieve and cum 7.50 850.00 6,375.00
retained on 180 micron sieve applied @ 0.06 cum per 10
sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 6,251.27

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1250 sqm = a+b+c+d+e+f 56,261.47


Rate per sqm = (a+b+c+d+e+f)/1250 45.01

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 1250 sqm

a) Labour

Mate day 0.85 356.65 303.15

Mazdoor (Unskilled) day 15.00 244.56 3,668.40

Mazdoor (Semi-Skilled) day 2.00 285.32 570.64

b) Machinery

Mixall 6/10 t capacity hour 2.50 1,686.00 4,215.00

Three wheel 80-100 kN static roller hour 2.50 652.00 1,630.00

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 2.50 2,120.00 5,300.00
set

c) Material

Crumb Rubber Modified Bitumen @ 6.80 kg per 10 sqm t 0.90 36,420.00 32,778.00

5 - 402
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Crushed sand or grit as passing 2.36 mm sieve and cum 12.00 850.00 10,200.00
retained on 180 micron sieve applied @ 0.06 cum per 10
sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 7,333.15

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1250 sqm = a+b+c+d+e+f 65,998.34

Rate per sqm = (a+b+c+d+e+f)/1250 52.80

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 1250 sqm

a) Labour

Mate day 0.85 356.65 303.15

Mazdoor (Unskilled) day 15.00 244.56 3,668.40

Mazdoor (Semi-Skilled) day 2.00 285.32 570.64

b) Machinery

Mixall 6/10 t capacity hour 2.50 1,686.00 4,215.00

Three wheel 80-100 kN static roller hour 2.50 652.00 1,630.00

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 2.50 2,120.00 5,300.00
set

c) Material

Natural Rubber Modified Bitumen @ 6.80 kg per 10 sqm t 0.85 0.00 0.00

Crushed sand or grit as passing 2.36 mm sieve and cum 7.50 698.00 5,235.00
retained on 180 micron sieve applied @ 0.06 cum per 10
sqm
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 2,615.27

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1250 sqm = a+b+c+d 23,537.47

Rate per sqm = (a+b+c+d)/1250 18.83

Case - III : Type C

(I) Bitumen (S-90)

Unit = sqm

Taking output = 1100 sqm

a) Labour

Mate day 1.15 356.65 410.15

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) for carrying of chips & spraying day 22.00 244.56 5,380.32

Mazdoor (Semi-Skilled) day 5.00 285.32 1,426.60

b) Machinery

5 - 403
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 2.20 2,120.00 4,664.00
set

Three wheel 80-100 kN static roller hour 2.20 652.00 1,434.40

c) Material

Bitumen (S-90) @ 6.50 kg per 10 sqm t 0.715 38,826.00 27,760.59

Crushed stone chipping of 6.7 mm size defined as 100% cum 9.90 1,807.00 17,889.30
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 7,401.24

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1100 sqm = a+b+c+d+e+f 66,611.16

Rate per sqm = (a+b+c+d+e+f)/1100 60.56

(II) Bitumen (S-65)

Unit = sqm

Taking output = 1100 sqm

a) Labour

Mate day 1.15 356.65 410.15

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 22.00 244.56 5,380.32

Mazdoor (Semi-Skilled) day 5.00 285.32 1,426.60

b) Machinery

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 2.20 2,120.00 4,664.00
set
Three wheel 80-100 kN static roller hour 2.20 652.00 1,434.40

c) Material

Bitumen (S-65) @ 6.50 kg per 10 sqm t 0.715 39,783.00 28,444.85

Crushed stone chipping of 6.7 mm size defined as 100% cum 9.90 1,807.00 17,889.30
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 7,486.77

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1100 sqm = a+b+c+d+e+f 67,380.94

Rate per sqm = (a+b+c+d+e+f)/1100 61.26

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 1100 sqm

a) Labour

5 - 404
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Mate day 1.15 356.65 410.15

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 22.00 244.56 5,380.32

Mazdoor (Semi-Skilled) day 5.00 285.32 1,426.60

b) Machinery

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 2.10 2,120.00 4,452.00
set

Three wheel 80-100 kN static roller hour 2.10 652.00 1,369.20

c) Material

Polymer Modified Bitumen @ 6.50 kg per 10 sqm t 0.715 32,880.00 23,509.20

Crushed stone chipping of 6.7 mm size defined as 100% cum 9.90 1,807.00 17,889.30
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 6,835.17

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1100 sqm = a+b+c+d+e+f 61,516.49

Rate per sqm =(a+b+c+d+e+f)/1100 55.92

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 1100 sqm

a) Labour

Mate day 1.15 356.65 410.15

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor Unskilled) day 22.00 244.56 5,380.32

Mazdoor (Semi-Skilled) day 5.00 285.32 1,426.60

b) Machinery

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 2.20 2,120.00 4,664.00
set

Three wheel 80-100 kN static roller hour 2.20 652.00 1,434.40

c) Material

Crumb Rubber Modified Bitumen @ 6.50 kg per 10 sqm t 0.715 36,420.00 26,040.30

Crushed stone chipping of 6.7 mm size defined as 100% cum 9.90 1,807.00 17,889.30
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 7,186.20

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

5 - 405
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Cost of 1100 sqm = a+b+c+d+e+f 64,675.83

Rate per sqm = (a+b+c+d+e+f)/1100 58.80

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 1100 sqm

a) Labour

Mate day 1.15 356.65 410.15

Bitumen Sprayer day 1.00 244.56 244.56

Mazdoor (Unskilled) day 22.00 244.56 5,380.32

Mazdoor (Semi-Skilled) day 5.00 285.32 1,426.60

b) Machinery

Bitumen boiler oil fired 1000 litre capacity fitted with spray hour 2.20 2,120.00 4,664.00
set
Three wheel 80-100 kN static roller hour 2.20 652.00 1,434.40

c) Material

Natural Rubber Modified Bitumen @ 6.50 kg per 10 sqm t 0.715 0.00 0.00

Crushed stone chipping of 6.7 mm size defined as 100% cum 9.90 1,510.00 14,949.00
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 3,563.63

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 1100 sqm = a+b+c+d 32,072.66

Rate per sqm = (a+b+c+d)/1100 29.16

Note: Since seal coat is provided immediately over the bituminous layers,
hydraulic broom for cleaning has not been catered.

B. By Mechanical Means

Case - I : Type A

(I) Bitumen (S-90)

Unit = sqm

Taking output = 7500 sqm (67.5 cum)

a) Labour

Mate day 0.24 356.65 85.60

Mazdoor (Unskilled) day 6.00 244.56 1,467.36

b) Machinery

Hydraulic self propelled chips spreader hour 6.00 2,380.00 14,280.00

Tipper 5.5 cum capacity hour 6.00 850.00 5,100.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

5 - 406
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Bitumen (S-90) @ 9.80 kg per 10 sqm t 7.35 38,826.00 285,371.10

Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 1,510.00 101,925.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 53,972.38

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 485,751.44

Rate per sqm = (a+b+c+d+e+f)/7500 64.77

(II) Bitumen (S-65)

Unit = sqm

Taking output = 7500 sqm (67.5 cum)

a) Labour

Mate day 0.24 356.65 85.60

Mazdoor (Unskilled) day 6.00 244.56 1,467.36

b) Machinery

Hydraulic self propelled chips spreader hour 6.00 2,380.00 14,280.00

Tipper 5.5 cum capacity hour 6.00 850.00 5,100.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Bitumen (S-65) @ 9.80 kg per 10 sqm t 7.35 39,783.00 292,405.05

Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 1,510.00 101,925.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 54,851.63

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 493,664.63

Rate per sqm = (a+b+c+d+e+f)/7500 65.82

(III) Polymer Modified Bitumen

Unit = sqm

5 - 407
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Taking output = 7500 sqm (67.5 cum)

a) Labour

Mate day 0.24 356.65 85.60

Mazdoor (Unskilled) day 6.00 244.56 1,467.36

b) Machinery

Hydraulic self propelled chips spreader hour 6.00 2,380.00 14,280.00

Tipper 5.5 cum capacity hour 6.00 850.00 5,100.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Polymer Modified Bitumen @ 9.80 kg per 10 sqm t 7.35 32,880.00 241,668.00

Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 1,510.00 101,925.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 48,509.49

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 436,585.45

Rate per sqm = (a+b+c+d+e+f)/7500 58.21

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 7500 sqm (67.5 cum)

a) Labour

Mate day 0.24 356.65 85.60

Mazdoor (Unskilled) day 6.00 244.56 1,467.36

b) Machinery

Hydraulic self propelled chips spreader hour 6.00 2,380.00 14,280.00

Tipper 5.5 cum capacity hour 6.00 850.00 5,100.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Crumb Rubber Modified Bitumen @ 9.80 kg per 10 sqm t 7.35 36,420.00 267,687.00

5 - 408
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 1,510.00 101,925.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 51,761.87

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 465,856.83

Rate per sqm = (a+b+c+d+e+f)/7500 62.11

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 7500 sqm (67.5 cum)

a) Labour

Mate day 0.24 356.65 85.60

Mazdoor (Unskilled) day 6.00 244.56 1,467.36

b) Machinery

Hydraulic self propelled chips spreader hour 6.00 2,380.00 14,280.00

Tipper 5.5 cum capacity hour 6.00 850.00 5,100.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Natural Rubber Modified Bitumen @ 9.80 kg per 10 sqm t 7.35 0.00 0.00

Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 1,510.00 101,925.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 18,300.99

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d 164,708.95

Rate per sqm = (a+b+c+d)/7500 21.96

Note: Since seal coat is provided immediately over the bituminous layers,
Hydraulic broom for cleaning has not been catered.

510 Case - II : Type B

(I) Bitumen (S-90)

Unit = sqm

Taking output = 5000 sqm (30 cum)

a) Labour

Mate day 0.16 356.65 57.06

Mazdoor (Unskilled) day 4.00 244.56 978.24

5 - 409
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
b) Machinery

HMP of 30/40 t per hour hour 2.00 6,584.00 13,168.00

Electric generator set 125 KVA hour 2.00 2,073.00 4,146.00

Front end loader 1 cum bucket capacity hour 2.00 1,341.00 2,682.00

Tipper 5.5 10 t capacity hour 1.36 850.00 1,156.00

Paver finisher hour 2.00 883.00 1,766.00

Three wheel 80-100 kN static roller hour 10.00 652.00 6,520.00

c) Material

Bitumen (S-90) @ 6.80 kg per 10 sqm t 3.40 38,826.00 132,008.40

Crushed sand defined as passing 2.36 mm sieve and cum 30.00 850.00 25,500.00
retained on 180 micron sieve applied @ 0.06 cum per 10
sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 23,497.71

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 5000 sqm = a+b+c+d+e+f 211,479.42

Rate per sqm = (a+b+c+d+e+f)/5000 42.30

(II) Bitumen (S-65)

Unit = sqm

Taking output = 5000 sqm (30 cum)

a) Labour

Mate day 0.16 356.65 57.06

Mazdoor (Unskilled) day 4.00 244.56 978.24

b) Machinery

HMP of 30/40 t per hour hour 2.00 6,584.00 13,168.00

Electric generator set 125 KVA hour 2.00 2,073.00 4,146.00

Front end loader 1 cum bucket capacity hour 2.00 1,341.00 2,682.00

Tipper 5.5 10 t capacity hour 1.36 850.00 1,156.00

Paver finisher hour 2.00 883.00 1,766.00

Three wheel 80-100 kN static roller hour 10.00 652.00 6,520.00

c) Material

Bitumen (S-65) @ 6.80 kg per 10 sqm t 3.40 39,783.00 135,262.20

Crushed sand defined as passing 2.36 mm sieve and cum 30.00 850.00 25,500.00
retained on 180 micron sieve applied @ 0.06 cum per 10
sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 23,904.44

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

5 - 410
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)

Cost of 5000 sqm = a+b+c+d+e+f 215,139.94

Rate per sqm = (a+b+c+d+e+f)/5000 43.03

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 5000 sqm (30 cum)

a) Labour

Mate day 0.16 356.65 57.06

Mazdoor (Unskilled) day 4.00 244.56 978.24

b) Machinery

HMP of 30/40 t per hour hour 2.00 6,584.00 13,168.00

Electric generator set 125 KVA hour 2.00 2,073.00 4,146.00

Front end loader 1 cum bucket capacity hour 2.00 1,341.00 2,682.00

Tipper 5.5 10 t capacity hour 1.36 850.00 1,156.00

Paver finisher hour 2.00 883.00 1,766.00

Three wheel 80-100 kN static roller hour 10.00 652.00 6,520.00

c) Material

Polymer Modified Bitumen @ 6.80 kg per 10 sqm t 3.40 32,880.00 111,792.00

Crushed sand defined as passing 2.36 mm sieve and cum 30.00 850.00 25,500.00
retained on 180 micron sieve applied @ 0.06 cum per 10
sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 20,970.66

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 5000 sqm = a+b+c+d+e+f 188,735.97

Rate per sqm = (a+b+c+d+e+f)/5000 37.75

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 5000 sqm (30 cum)

a) Labour

Mate day 0.16 356.65 57.06

Mazdoor (Unskilled) day 4.00 244.56 978.24

b) Machinery

HMP of 30 / 40 t per hour hour 2.00 6,584.00 13,168.00

Electric generator set 125 KVA hour 2.00 2,073.00 4,146.00

Front end loader 1 cum bucket capacity hour 2.00 1,341.00 2,682.00

Tipper 5.5 10 t capacity hour 1.36 850.00 1,156.00

5 - 411
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Paver finisher hour 2.00 883.00 1,766.00

Three wheel 80-100 kN static roller hour 10.00 652.00 6,520.00

c) Material

Crumb Rubber Modified Bitumen @ 6.80 kg per 10 sqm t 3.70 36,420.00 134,754.00

Crushed sand defined as passing 2.36 mm sieve and cum 30.00 850.00 25,500.00
retained on 180 micron sieve applied @ 0.06 cum per 10
sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 23,840.91

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 5000 sqm = a+b+c+d+e+f 214,568.22

Rate per sqm = (a+b+c+d+e+f)/5000 42.91

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 5000 sqm (30 cum)

a) Labour

Mate day 0.16 356.65 57.06

Mazdoor (Unskilled) day 4.00 244.56 978.24

b) Machinery

HMP of 30/40 t per hour hour 2.00 6,584.00 13,168.00

Electric generator set 125 KVA hour 2.00 2,073.00 4,146.00


Front end loader 1 cum bucket capacity hour 2.00 1,341.00 2,682.00

Tipper 5.5 10 t capacity hour 1.36 850.00 1,156.00

Paver finisher hour 2.00 883.00 1,766.00


Three wheel 80-100 kN static roller hour 10.00 652.00 6,520.00

c) Material

Natural Rubber Modified Bitumen @ 6.80 kg per 10 sqm t 3.40 0.00 0.00

Crushed sand defined as passing 2.36 mm sieve and cum 30.00 698.00 20,940.00
retained on 180 micron sieve applied @ 0.06 cum per 10
sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 6,426.66

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 5000 sqm = a+b+c+d 57,839.97

Rate per sqm = (a+b+c+d)/5000 11.57

Note: Since seal coat is required to be provided over the premix carpet on
the same day, out of the 6 working hours of the HMP, 4.00 hours are
proposed to be utilised for the premix carpet and the balance 2.00
hours have been considered for this case.

Case - III : Type C

(I) Bitumen (S-90)

5 - 412
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Unit = sqm

Taking output = 7500 sqm (67.5 cum)

a) Labour

Mate day 0.20 356.65 71.33

Mazdoor (Unskilled) day 5.00 244.56 1,222.80

b) Machinery

Hydraulic self propelled chips spreader hour 6.00 2,380.00 14,280.00

Tipper 5.5 cum capacity hour 6.00 850.00 5,100.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Bitumen (S-90) @ 6.50 kg per 10 sqm t 4.88 38,826.00 189,470.88

Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 1,807.00 121,972.50
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 44,458.44

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 400,125.95

Rate per sqm = (a+b+c+d+e+f)/7500 53.35

(II) Bitumen (S-65)

Unit = sqm

Taking output = 7500 sqm (67.5 cum)

a) Labour

Mate day 0.20 356.65 71.33

Mazdoor (Unskilled) day 5.00 244.56 1,222.80

b) Machinery

Hydraulic self propelled chips spreader hour 6.00 2,380.00 14,280.00

Tipper 5.5 cum capacity hour 6.00 850.00 5,100.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Bitumen (S-65) @ 6.50 kg per 10 sqm t 4.88 39,783.00 194,141.04

Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 1,807.00 121,972.50
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

5 - 413
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 45,042.21

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 405,379.88

Rate per sqm = (a+b+c+d+e+f)/7500 54.05

(III) Polymer Modified Bitumen

Unit = sqm

Taking output = 7500 sqm (67.5 cum)

a) Labour

Mate day 0.20 356.65 71.33

Mazdoor (Unskilled) day 5.00 244.56 1,222.80

b) Machinery

Hydraulic self propelled chips spreader hour 6.00 2,380.00 14,280.00

Tipper 5.5 cum capacity hour 6.00 850.00 5,100.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Polymer Modified Bitumen @ 6.50 kg per 10 sqm t 4.88 32,880.00 160,454.40

Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 1,807.00 121,972.50
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 40,831.38

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d 367,482.41

Rate per sqm = (a+b+c+d)/7500 49.00

(IV) Crumb Rubber Modified Bitumen

Unit = sqm

Taking output = 7500 sqm (67.5 cum)

a) Labour

Mate day 0.20 356.65 71.33

Mazdoor (Unskilled) day 5.00 244.56 1,222.80

b) Machinery

Hydraulic self propelled chips spreader hour 6.00 2,380.00 14,280.00

5 - 414
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Tipper 5.5 cum capacity hour 6.00 850.00 5,100.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Crumb Rubber Modified Bitumen @ 6.50 kg per 10 sqm t 4.88 36,420.00 177,729.60

Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 1,807.00 121,972.50
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 42,990.78

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d+e+f 386,917.01

Rate per sqm =(a+b+c+d+e+f)/7500 51.59

(V) Natural Rubber Modified Bitumen

Unit = sqm

Taking output = 7500 sqm (67.5 cum)

a) Labour

Mate day 0.20 356.65 71.33

Mazdoor (Unskilled) day 5.00 244.56 1,222.80

b) Machinery

Hydraulic self propelled chips spreader hour 6.00 2,380.00 14,280.00

Tipper 5.5 cum capacity hour 6.00 850.00 5,100.00

Front end loader 1 cum bucket capacity hour 6.00 1,341.00 8,046.00

Bitumen pressure distributor hour 6.00 954.00 5,724.00

Three wheel 80-100 kN static roller hour 15.00 652.00 9,780.00

c) Material

Natural Rubber Modified Bitumen @ 6.50 kg per 10 sqm t 4.88 0.00 0.00

Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 1,807.00 121,972.50
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c) 20,774.58

e) Add GST, LWC etc. @ 0 on (a+b+c) 0.00

Cost of 7500 sqm = a+b+c+d 186,971.21

Rate per sqm = (a+b+c+d)/7500 24.93

5 - 415
Sr. Reference to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spec (Rs.)
Note: Since seal coat is provided immediately over the bituminous layers,
Hydraulic broom for cleaning has not been catered.

5.13 511 Supply of Stone Aggregates for Pavement Courses

Supply of stone aggregates from approved sources conforming to


the physical requirement, specified in the respective clauses,
including royalties, fees rents, collection, transportation, stacking
and testing and measured in cum as per Clause 511.5.

Note: Competitive market rates to be ascertained. Alternatively, rates for


stone crushing given in Chapter 1 may be adopted, if found
economical. In case for supply of aggregates at site are not
available, nearest crusher site may be ascertained. Loading and
unloading charges and cost of carriage may be added to these rates
to arrive at the cost at site.

5 - 416
Chapter 6

CEMENT CONCRETE PAVEMENT

Sr. Reference to Rate


Description Unit Quantity
No. MORD Spec (Rs.)

6.1 400 Granual Sub-base

Rate as per item No.4.1 of Chapter 4

6.2 400 Lime Treated Soil

Rate as per item No.4.5 of Chapter 4

6.3 1500 & 400 Water Bound Macadam (WBM) - Sub-base

(A) By Manual Means

As per item No.4.7 of Chapter 4


(B) By Mechnical Means
As per item No.4.7 of Chapter 4
6.4 1500 Cement concrete pavement

Construction of un reinforced, dowel jointed at expansion


and construction joint only,plain cement concrete
pavement, thickness as per design,over a prepared sub
base,with 43 grade cement or any other type as per
clause 1501.2.2 M30 grade ,coarse and fine aggregrette
conforming to is:383,maximum size of coarse aggregate
not exceeding 25 mm,mixed in a concrete mixer of not
less than 0.2 cum capacity and appropriate weigh
batcher using approved mix design, laid in approved
fixed side formwork (steel channel,laying and fixing of
125 micron thick polythene film,wedges,steel plates
including levelling the formwork as per drawing)
spreading the concrete with shovels,rakes,compacted
using needle,screed and plate vibrator and finished in
continuous operation including provision of contraction
and expansion,construction joints,applying debonding
strips,primer,sealant,dowelbars,near approaches to
bridge/culverts and construction joints,admixture as
approved,curingof concrete slabs for 14 days.

Unit = cum

Taking output = 75 cum (i.e for 100.00m x 3.75m x 0.20m)

a) Labour
(i) Mate day 7.00 356.65

(ii) Mazdoor (Unskilled) day 129.00 244.56

6 - 417
Sr. Reference to Rate
Description Unit Quantity
No. MORD Spec (Rs.)

(iii) Mason (1st class) day 5.00 458.55

(iv) Mason (2nd class) day 5.00 285.32

(v) Mazdoor (skilled) day 6.00 356.65

(vi) Surveyor day 2.00 458.55

(vii) Mazdoor (semi-skilled) day 6.00 285.32

(viii) Bhisti day 14.00 244.56

(ix) Blacksmith for cutting, fabriction & fixing day 1.00 458.55
dowel bar

b) Machinery

(i) Concrete mixer 0.28 / 0.04 cum capacity hour 36.00 188.00
(6 mixers) with weigh batcher and
suitable capacity calibrated water tank

(ii) Needle vibrator hour 9.00 101.00

(iii) Screed Vibrator hour 9.00 0.00

(iv) Plate Vibrator hour 9.00 218.00

(v) Concrete joint cutting machine for day’s hour 4.00 150.00
end work and regular joint cutting.

(vi) Water tanker 6 kl capacity hour 5.00 440.00

(vii) Air compressor (1 hour initial + 1 hour hour 2.00 435.00


final)

c) Material

(i) Crushed stone coarse aggregates cum 67.50 1,599.50


grading as per Clause 1501.2.4.1
(Table 1500.1) @ 0.90 cum/cum of
concrete conforming to Clause 600.4.4

(ii) Sand as per IS:383 and conforming to cum 33.75 950.00


Clause 1501.2.4.2 @ 0.45 cum/cum of
concrete

(iii) Cement @ 310 kg/cum of concrete t 26.25 6,200.00

(iv) Polythene sheet 125 micron sqm 412.50 12.00

6 - 418
Sr. Reference to Rate
Description Unit Quantity
No. MORD Spec (Rs.)

(v) Mild steel dowel bar 25mm dia of grade kg 117.60 47.00
Fe-500 (20 nos of 200mm long at
culvert/ bridge slab and at construction
joints including 5 percent wastage = 42
m @ 2.8kg per m = 117.6kg

(vi) Bitminous primer @ 200 ml per joint for t 0.005 27,509.00


23 joints

(vii) Jute rope 12 mm dia including 5 per m 90.00 90.00


cent wastage

(viii) Bituminous sealant @ 800 ml per joint kg 19.00 18.36


for 21 joints

(ix) Debonding strip 3.75 length x 10mm x no 483.00 15.00


5mm cut or rubber filler board or similar
material including 5percent polythene
sheet covering 2/3 dowel bar etc.
including 5 per cent wastage.

(x) Plasticizer 0.5 percent by weight of litre 122.00 102.00


cement
(xi) Curing compound @ 0.33 litre per sqm l 131.25 0.00

(xii) Water for mixing and curing for 14-days day 18.00 40.00

d) Formwork @ 2% of (a+b+c)

e) Contractor’s profit & Overheads @ 12.5% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Cost for 75 cum = a+b+c+d+e+f+g

Rate per cum = (a+b+c+d+e+f+g)/75

Note: When curing compound is used 4-days water curing will be done

6.4 1500 Roller Compacted Concrete Pavement

6 - 419
Sr. Reference to Rate
Description Unit Quantity
No. MORD Spec (Rs.)

Construction of Roller Compacted Concrete Pavement


(RCCP) with coarse and fine aggregates conforming to
IS:383, the size of coarse aggregate not exceeding 25
mm with minimum aggregate cement ratio of 5:1 mm and
with minimum cemnt content of 310 kg per cum,
aggregate gradation to be as per Table 602.2 after
blending, mixing in concrete mixer at optimum moisture
content, transporting to site, laying with wheel barrows or
steel pans or with mechanical paver, compacting with 80-
100 kN smooth wheel, tandem vibratory roller, to
achieve, the designed flexural strength, finishing and
curing as per drawings and Technical Specification
Clause 1502

Unit = cum

Taking output = 75 cum

a) Labour
(i) Mate day 6.00 356.65

(ii) Mazdoor (Unskilled) day 132.00 244.56

(iii) Mason (1st class) day 4.00 458.55

(iv) Mason (2nd class) day 4.00 285.32

(v) Surveyor day 2.00 458.55

(vi) Bhisti day 14.00 244.56

b) Machinery

(i) Concrete mixer 0.28 / 0.04 cum capacity hour 36.00 188.00
(6 mixers) with weigh batcher and
suitable capacity calibrated water tank

(ii) Vibratory/80-100 kN Static Roller hour 6.00 1,687.00

(iii) Concrete joint cutting machine for day’s hour 6.00 150.00
end work and regular joint cutting.

(iv) Water tanker 6 kl capacity hour 6.00 440.00

(v) Air compressor (1 hour initial + 1 hour fina hour 2.00 435.00

c) Material

6 - 420
Sr. Reference to Rate
Description Unit Quantity
No. MORD Spec (Rs.)

(i) Crushed stone coarse aggregates cum 67.50 1,599.50


grading as per Clause 1501.2.4.1
(Table 1500.3) @ 0.90 cum/cum of
concrete conforming to Clause 600.4.4

(ii) Sand as per IS:383 and conforming to cum 33.75 950.00


Clause 1501.2.4.2 @ 0.45 cum/cum of
concrete

(iii) Cement @ 310 kg/cum of concrete t 23.25 6,200.00

(iv) Bitminous primer @ 200 ml per joint for 21 t 0.004 27,509.00

(v) Jute rope 10 mm dia including 5 per cent m 90.00 90.00

(vi) Bituminous sealant @ 800 ml per joint for kg 16.80 18.36

(vii) Curing compound @ 0.33 litre per sqm l 131.25 0.00

(viii) Water for mixing and curing for 14-days day 18.00 40.00

d) Formwork @ 2% of (a+b+c)

e) Contractor’s profit & Overheads @ 12.5% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Cost for 75 cum = a+b+c+d+e+f+g

Rate per cum = (a+b+c+d+e+f+g)/75

Note: When curing compound is used 4-days water curing will be done

6.5 1500 Rectangular Concrete Block Pavement

Manufacturing, laying of cement concrete blocks of size


0.450 m x 0.300 m x 0.15 m of Cement Concrete (C.C.)
M30 garde and spreading 25 mm thick sand under neath
and filling joints with sand on existing W.B.M. base as per
Technical Specification Clause 1503.

Unit = sqm

Taking output = 375 sqm (i.e for 100.00m x 3.75m of 0.15m thk. = 56.25 cum)

a) Labour

Labour for Manufacturing the Cement Concrete Block :

6 - 421
Sr. Reference to Rate
Description Unit Quantity
No. MORD Spec (Rs.)

(i) Mate day 4.48 356.65

(ii) Mazdoor (Unskilled) day 96.30 244.56

(iii) Mason (2nd class) day 3.75 285.32

(iv) Bhisti day 10.45 244.56

b) Machinery

Concrete mixer 0.28 / 0.4 cum hour 22.50 188.00

Plate vibrator hour 6.75 218.00

Water tanker 6 kl capacity hour 3.00 440.00

c) Material

(i) Coarse aggregates (9.450 x 0.84) cum 25.20 670.00

(ii) Sand (9.450 x 0.42) cum 12.60 950.00

(iii) Cement t 18.60 6,200.00

(iv) Sand as per Table 1500.5 cum 13.125 950.00

Bed = 375*0.025 = 9.375 cum

Joints = 7.5*0.15 = 3.75 cum

(v) Cost of water kl 14.00 40.00

d) Formwork @ 3% of (a+b+c)

e) Contractor’s profit & Overheads @ 12.5% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Cost for 112.5 sqm = a+b+c+d+e+f+g

Rate per sqm = (a+b+c+d+e+f+g)/112.5

Note: i. In case curing compound is used in places where


there is scarcity of water, the water curing will be
used for 4-days and rate analysis will be
amended accordingly

ii. Carriage of C.C. block to site of is payable


seperately as per Chapter of carriage of material
from manufacturing site to the site of work.

6 - 422
Sr. Reference to Rate
Description Unit Quantity
No. MORD Spec (Rs.)

6.7 1500 Interlocking Concrete Block Pavement

(A) Interlocking pavement block

(i) Providing and laying interlocking concrete block


pavement (M40) having thickness 80mm as per technical
specification clause 1504 complete including carriage.

a) Including Edge block/ Edge restraints

Unit=sqm

Taking output = 375 sqm (i.e for 60.00m x 3.75m)

a) Labour

(i) Mate day 1.00 356.65

(ii) Mazdoor(Unskilled) day 17.00 244.56

(iii) Mason(2nd class) day 8.00 285.32

b) Machinary

(i) Water tanker 6 Kl capacity hour 2.00 440.00

c) Material

(i) Providing interlocking blocks sqm 225.00 578.00

(ii) Edge block (= 60m x 2) m 120.00 325.17

(iii) Sand as per table 1500.5 cum 7.23 950.00


(Bed = 603 x 75 x 0.03 = 6.75cum +
Joints = 60 x.08 = 0.48cum)

(iv) water for wetting sand Kl 3 40.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 225 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d+e)/225

b) Excluding Edge block/ Edge restraints

Unit=sqm

Taking output = 375 sqm (i.e for 60.00m x 3.75m)

6 - 423
Sr. Reference to Rate
Description Unit Quantity
No. MORD Spec (Rs.)

a) Labour

(i) Mate day 1.00 356.65

(ii) Mazdoor(Unskilled) day 17.00 244.56

(iii) Mason(2nd class) day 8.00 285.32

b) Machinary

(i) Water tanker 6 Kl capacity hour 2.00 440.00

c) Material

(i) Providing interlocking blocks sqm 225.00 578.00

(ii) Sand as per table 1500.5 cum 7.23 950.00


(Bed = 603 x 75 x 0.03 = 6.75cum +
Joints = 60 x.08 = 0.48cum)

(iii) water for wetting sand Kl 3 40.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 225 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d+e)/225

(ii) Providing and laying interlocking concrete block


pavement (M40) having thickness 60mm as per technical
specification clause 1504 complete including carriage.

a) Including Edge block/ Edge restraints

Unit=sqm

Taking output = 375 sqm (i.e for 60.00m x 3.75m)

a) Labour

(i) Mate day 0.90 356.65

(ii) Mazdoor(Unskilled) day 15.00 244.56

(iii) Mason(2nd class) day 7.00 285.32

b) Machinary

(i) Water tanker 6 Kl capacity hour 2.00 440.00

6 - 424
Sr. Reference to Rate
Description Unit Quantity
No. MORD Spec (Rs.)

c) Material

(i) Providing interlocking blocks sqm 225.00 433.56

(ii) Edge block (= 60m x 2) m 120.00 325.17

(iii) Sand as per table 1500.5 cum 5.42 950.00


(Bed = 603 x 75 x 0.03 = 6.75cum +
Joints = 60 x.08 = 0.48cum)

(iv) water for wetting sand Kl 3 40.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 225 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d+e)/225

b) Excluding Edge block/ Edge restraints

Unit=sqm

Taking output = 375 sqm (i.e for 60.00m x 3.75m)

a) Labour

(i) Mate day 0.90 356.65

(ii) Mazdoor(Unskilled) day 15.00 244.56

(iii) Mason(2nd class) day 7.00 285.32

b) Machinary

(i) Water tanker 6 Kl capacity hour 2.00 440.00

c) Material

(i) Providing interlocking blocks sqm 225.00 433.56

(ii) Sand as per table 1500.5 cum 5.42 950.00


(Bed = 603 x 75 x 0.03 = 6.75cum +
Joints = 60 x.08 = 0.48cum)

(iii) water for wetting sand Kl 3 40.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

6 - 425
Sr. Reference to Rate
Description Unit Quantity
No. MORD Spec (Rs.)

Cost for 225 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d+e)/225

(B) Interlocking Edge block/ Edge restraints

(i) Providing and laying Concrete Edge block/ Edge


restraints (M40 Grade) of size 300mm x 300mm x
150mm including carriage complete as per Technical
specification clause 1504.

Unit= No.

Taking output = 1 cum (= 1 / 0.3 x 0.3 x 0.15 = 74 Nos.)

a) Labour

(i) Mate day 0.08 356.65

(ii) Mason (1st Class) day 0.10 458.55

(iii) Mazdoor (Unskilled) day 1.63 244.56

(iv) Bhisti day 0.27 244.56

For Laying:

(i) Mate day 0.05 356.65

(ii) Mason (2nd Class) day 0.44 285.32

(iii) Mazdoor (Unskilled) day 0.94 244.56

b) Machinary

(i) Concrete mixer 0.28 / 0.4 cum hour 0.40 188.00

(ii) Water tanker 6 Kl capacity hour 2.00 440.00

c) Material

(i) Cement t 0.44 6200.00

(ii) Sand cum 0.41 950.00

(iii) 40 mm aggregate cum 0.33 1500.00

(iv) 20 mm aggregate cum 0.33 1777.00

(v) 10 mm aggregate cum 0.18 1916.00

6 - 426
Sr. Reference to Rate
Description Unit Quantity
No. MORD Spec (Rs.)

d) Formwork @ 2% of (a+b+c)

e) Contractor’s profit & Overheads @ 12.5% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

g) Cost for carriage for 50KM @ Rs.14.9 cum/km (as per item no. 1.10)

Cost for 1 cum including carriage = a+b+c+d+e+f+g

Rate per no. of block = (a+b+c+d+e+f+g)/74

6 - 427
Chapter 6

NT CONCRETE PAVEMENT

Amount (Rs.)

2,496.55

31,548.24

6 - 428
Amount (Rs.)

2,292.75

1,426.60

2,139.90

917.10

1,711.92

3,423.84

458.55

6,768.00

909.00

0.00

1,962.00

600.00

2,200.00

870.00

107,966.25

32,062.50

162,750.00

4,950.00

6 - 429
Amount (Rs.)

5,527.20

137.55

8,100.00

348.84

7,245.00

12,444.00

0.00

720.00

8,039.52

51,251.91

0.00

461,267.21

6,150.23

6 - 430
Amount (Rs.)

2,139.90

32,281.92

1,834.20

1,141.28

917.10

3,423.84

6,768.00

10,122.00

900.00

2,640.00

870.00

6 - 431
Amount (Rs.)

107,966.25

32,062.50

144,150.00

110.04

8,100.00

308.45

0.00

720.00

7,129.11

45,448.07

0.00

409,032.66

5,453.77

6 - 432
Amount (Rs.)

1,597.79

23,551.13

1,069.95

2,555.65

4,230.00

1,471.50

1,320.00

16,884.00

11,970.00

115,320.00

12,468.75

560.00

5,789.96

24,848.59

0.00

223,637.33

1,987.89

6 - 433
Amount (Rs.)

356.65

4,157.52

2,282.56

880.00

130,050.00

39,020.40

6,868.50

120.00

22,966.95

0.00

206,702.58

918.70

6 - 434
Amount (Rs.)

356.65

4,157.52

2,282.56

880.00

130,050.00

6,868.50

120.00

18,089.40

0.00

162,804.63

723.60

320.99

3,668.40

1,997.24

880.00

6 - 435
Amount (Rs.)

97,551.00

39,020.40

5,149.00

120.00

18,588.38

0.00

167,295.40

743.50

320.99

3,668.40

1,997.24

880.00

97,551.00

5,149.00

120.00

13,710.83

0.00

6 - 436
Amount (Rs.)

123,397.45

548.40

28.53

45.86

398.63

66.03

17.83

125.54

229.89

75.20

880.00

2,728.00

389.50

495.00

586.41

344.88

6 - 437
Amount (Rs.)

128.23

817.44

0.00

745.00

8,101.97

109.50

6 - 438
Chapter 7

CAUSEWAY AND SUBMERSIBLE BRIDGES

Sr. Reference to
Description Unit Quantity
No. MORD Spec

7.1 1400, 300, 600 Construction of Cut-off Walls/Head Walls


700 & 800
(i) Earthwork in excavation for structures as per drawing and
technical specification Clause 305.

Rate as per item No.11.1 of Chapter 11 cum

(ii) Plain cement concrete M15 grade

Rate as per item No.11.4 (ii) of Chapter 11 cum

(iii) Brick masonry in cement mortar 1:4

Rate as per item No.11.5 (ii) of Chapter 11 cum

(iv) Stone masonry in cement mortar 1:4

Rate as per item No.11.6 (ii) of Chapter 11 cum

(v) Providing P.C.C M20 architectural coping on top of wall

Rate as per item No.12.13 of Chapter 12 m

Note: Rate as appropriate for the type of soil/rock are to be taken in (i)

7.2 300 Preparation of Subgrade

Rate as per item No.3.15 of Chapter 3 cum

7.3 400 Granular Sub-base

Rate as per item No.4.1 of Chapter 4 cum

7.4 400 W.B.M. Base Course

Rate as per item No.4.7 of Chapter 4 cum

7.5 1500 Cement Concrete Slab

Rate as per item No.6.4 of Chapter 6 cum

7.6 1400 & 1300 (i) Providing and Laying Apron with Stone Boulders as
per Drawings & Technical Specification Clause 1301

Rate as per item No.14.1 of Chapter 14 cum

(ii) Providing and Laying of Boulder Apron Laid in Wire


Crates as per Drawing and Technnical Specification
Clause 1301

Rate as per item No.14.2 of Chapter 14 cum

7 - 439
Sr. Reference to
Description Unit Quantity
No. MORD Spec

(iii) Providing and Laying of Apron with Cement Concrete


Blocks as per Drawing and Technical Specification
Clause 1301

Rate as per item No.14.3 of Chapter 14 cum

Note Any one of the items appropriate may be taken

7.7 1400 & 1600 Guide Posts

Construction of R.C.C. guide posts of 250 mm dia, M25 grade


as per drawing and technical specification Clause 1401.6

Rate as per item No.8.8 of Chapter 8 cum

7.8 1400, 1100 & Bedding for Causeway


800

(i) Type A (concrete cradle) Bedding Clause 1402.5

As per item No.9.2 of Chapter 9 cum

(ii) Type B (first class) Bedding Clause 1402.5

As per item No.9.2 of Chapter 9 cum

7.9 1400 & 1100 Laying Reinforced Cement Concrete Pipe NP3 as per
drawing and technical specification Clause 1402.6

As per item No.9.3 of Chapter 9 m

7.10 1400 & 1100 Laying Reinforced Cement Concrete Pipe NP4 as per
technical specification Clause 1402.6

As per item No.9.4 of Chapter 9 m

7 - 440
Chapter 7

AY AND SUBMERSIBLE BRIDGES

Rate Amount
(Rs.) (Rs.)

7 - 441
Rate Amount
(Rs.) (Rs.)

7 - 442
Chapter 8

HILL ROADS

Sr. Reference to
Description Unit Quantity
No. MORD Spec

8.1 200 Site Clearance

As per Chapter 2

8.2 1600 Setting Out

Unit = 1km

The analysis of rate per km shall account for the following:

(1) Construction of reference pillars (burjee) @ 20 m on


both sides as per Fig. 1600.1 (b) and @ 8.33 m interval
on curves
(2) Construction of back pillars in front of each reference
pillar as per Fig. 1600.1 (c )

(3) Construction of job pillars as per Fig. 1600.1 (d)

(1) Construction of reference pillars as per Fig. 1600.1


(b) as per drawing and Technical Specification
Clause 1602.1
(a) Earthwork in excavation for foundation as per
drawing and technical specifications.

Rate as per item No.11.1 of Chapter 11 cum 1.20

(b) Stone masonry work in cement mortar 1:4 in


foundation complete as per drawing and
technical specifications

Rate as per item No.11.6 of Chapter 11 cum 1.20

(c) Plaster with cement mortar 1:4 as per technical


specifications

Rate as per item No.12.3 of Chapter 12 sqm 4.00

Add 5% of (a+b+c) for white washing, lettering and


painting, etc.

Total Cost for each Reference Pillar

(2) Construction of back piller as per Fig. 1600.1( c) as


per drawing and Technical Specification Clause
1602.3
(a) Earthwork in excavation for foundation as per
drawing and technical specifications

Rate as per item No. 11.1 of Chapter 11 cum 3.60

8 - 443
Sr. Reference to
Description Unit Quantity
No. MORD Spec

(b) Stone masonary work in cement mortar 1:4 in


foundation complete as per drawing and
technical specifications
Rate as per itme No. 11.6 Chapter 11 cum 3.10

(c) Plaster with cement mortar 1:4 as per technical


specifications
Rate as per item No. 12.3 of Chapter 12 sqm 0.45
Add 5% of (a+b+c) for white washing, lettering and
painting, etc.

Total Cost for each back Pillar

(3) Construction of Job pillers as per Fig. 1600.1 (d)


and Technical Specification Clause 1602.4

(a) Earthwork in excavation for foundation as per


drawing and technical specification

Rate as per item No.11.1 of Chapter cum 0.096


(b) Stone masonary work in cement mortar in
foundation complete as per drawing and
technical specification

Rate as per item No. 11.6 of Chapter 11 cum 0.096


(c) Plaster with cement mortar 1:4 as per drawing
and technical specification
Rate as per Item No.12.3 of Chapter 12 sqm 0.96
Add 5% of (a+b+c) for white washing, lettering and
painting, etc.

Total Cost for each Job Pillar

Note: (i) The dimensions of reference pillars, back pillars and job
pillars are as per figure/site conditions. The above items
are covered under different Chapters of MORD
Specifications for payment.

(ii) The marking of centre line, setting out, curves, recording


of levels, etc. by the surveyor will be incidental to work
and no extra payment shall be made for the same.

8.3 1600 & 300 Earthwork in Hill Road

(i) Excavation in Hilly Areas in Soil by manual means.

A) Excavation in soil in Hilly Area by manual


means including cutting and trimming of side
slopes and disposing of excavated earth with a
lift upto 1.5 m and a lead upto 20 m as per
drawing and Technical Specification Clause
1603.1 (Manual means should be use where
machines can not be deployed due to site
condition)

8 - 444
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Unit = cum

Taking output = 120 cum

a) Labour

Mate day 2.40

Mazdoor (Unskilled) day 60.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 120 cum = (a+b+c+d

Rate per cum = (a+b+c+d)/120

B) Extra for Every Additional Lift of 1.5 m or Part


thereof

Excavation in Soil

Unit = cum

Taking output = 10 cum

a) Labour

Mazdoor (Unskilled) day 0.55

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 cum = (a+b+c+d)

Rate per cum = (a+b+c+d)/10

(ii) Excavation in Hilly Areas in Soil by mechanical means

A) Excavation in soil in Hilly Area by mechanical


means including cutting and trimming of side
slopes and disposing of excavated earth with a
lift upto 1.5 m and a lead upto 20 m as per
Technical Specification Clause 1603.1

Unit = cum

Taking output = 260 cum

8 - 445
Sr. Reference to
Description Unit Quantity
No. MORD Spec

a) Labour

Mate day 0.80

Mazdoor (Unskilled) for trimming slopes and day 20.00


helping in excavation, etc.

b) Machinery

Dozer D-50 @ 43.28 cum per hour (40% of the hour 4.80

Excavator @100cm per km (6% of the output) hour 3.60

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 260 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/260

B) Extra for Every Additional Lift of 1.5 m or Part


thereof
Excavation in Soil

Unit = cum
Taking output = 10 cum

a) Labour

Mazdoor (Unskilled) day 0.55

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 cum = (a+b+c+d)

Rate per cum = (a+b+c+d)/10

Note: (i) In case the land on the valley side is barren and there is
no objection for disposing of excavated earth on the
valley side, the provision of front end loader and tipper
shall be deleted as excavated earth shall be disposed off
on the valley side.

(ii) For disposal of excavated surplus earth beyond 20 m,


the relevant items of carriage be followed

(iii) In case, alternative machine like hydraulic excavator 0.9


cum bucket capacity is necessited because of site
conditions, the same can be used.

8 - 446
Sr. Reference to
Description Unit Quantity
No. MORD Spec

(iii) Excavation in Hilly Area in Ordinary Rock by manual


means

A) Excavation in ordinary rock using manual


means including loading in a truck and carrying
of excavated material to embankment site with
a lift upto 1.5 m and lead upto 20 m as per
Clause 1603.2. (Manual means should be use
where machines can not be deployed due to
site condition)

Unit = cum

Taking output = 120 cum

a) Labour

Mate day 5.28

Mazdoor (Unskilled) day 132.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 120 cum = a+b+c+d

Rate per cum = (a+b+c+d)/120

B) Extra for Every Additional Lift of 1.5 m or Part


thereof
For Ordinary Rock

Unit = cum
Taking output = 10 cum

a) Labour
Mazdoor (Unskilled) day 0.86

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 cum = a+b+c+d

Rate per cum = (a+b+c+d)/10

(iv) Excavation in Hilly Areas in Ordinary Rock by


mechanical means not requiring blasting

8 - 447
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Excavation in hilly area in ordinary rock not requiring


blasting by mechanical means including cutting and
trimming of slopes and disposal of cut material with a lift
upto 1.5 m and lead upto 20 m as per Clause 1603.2.

Unit = cum
Taking output = 170 cum

a) Labour

Mate day 0.68

Mazdoor (Unskilled) day 17.00

Mazdoor for disposing of earth upto 20 m day 9.00

b) Machinery

Dozer D-50 @ 28.32 cum per hour (40% of the outp hour 4.00

Hydraulic Excavator 0.9 cum bucket capacity @ 40 hour 4.00


cum per hour (60% of the output)

c) Contractor’s profit & Overheads @ 12.5% on (a+b)


d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 170 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/170

Note: (i) In case the land on the valley side is barren and there is
no objection for disposing of excavated earth on the
valley side, the provision of front end loader and tipper
shall be deleted as excavated earth shall be disposed off
on the valley side.

(ii) In case, alternative machine like hydraulic excavator 0.9


cum bucket capacity is necessited because of site
conditions, the same can be used.

(v) Excavation in Hilly Areas in Hard Rock requiring


blasting

A) Excavation in hilly areas in hard rock requiring


blasting, by mechanical means, lift upto 1.5 m
and disposal of excavated rock upto a lead of
20 m as per Clause 1603.2.

Unit = cum

Taking output = 170 cum


a) Labour

8 - 448
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Mate day 1.36

Mazdoor (Unskilled) day 22.00

Driller day 2.00

Blaster day 10.00

b) Machinery

Dozer D-50 @ 56.67 cum per hour (blasted rockhour 3.00

Hydraulic Excavator 0.9 cum bucket capacity hour 5.00


@ 34 cum per hour

Air compressor 210 cfm with two jack hammer hour 28.00
@ 6 cum per hour

c) Materials

Gelatine 80 per cent kg 67.00

Electric detonators @ 1 detonator for 1 nos 235.00


Gelatine stick of 285 gm each
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 170 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/170

B) Extra for Every Additional Lift of 1.5 m or Part


thereof

For Hard Rock

Unit = cum

Taking output = 10 cum

a) Labour

Mazdoor (Unskilled) day 1.08

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 cum = a+b+c+d

8 - 449
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Rate per cum = (a+b+c+d)/10


Note: (1) In case the land on the valley side is barren and there is
no objection for disposing of excavated earth on the
valley side, the provision of front end loader and tipper
shall be deleted as excavated earth shall be disposed off
on the valley side.

(2) In case of hill roads, the altitude effect comes into play.
The output of men and machines decreases
progressively after 2100 m elevation leading to increase
in cost. High altitude effect has been explained in the
basic approach.

(3) The arrangement for igniting the detonator is covered


under overheads

(vi) Excavation in Hard Rock (blasting prohibited)

Excavation for roadway in hard rock (blasting prohibited)


with rock breakers including breaking rock, loading in
tippers and disposal with a lift upto 1.5 m and lead upto
200 metres, trimming bottom and side slopes in
accordance with requirements of lines, grades and
cross- sections as per Technical Specification Clause
302.3.5
(A) Manual Means

Unit = cum

Taking output = 16 cum

a) Labour

Mate day 1.64

Mazdoor (Unskilled) day 16.00

Chiseller day 24.00

Blacksmith day 1.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 16 cum = a+b+c+d

Rate per cum = (a+b+c+d)/16

Note: 1 Credit is considered for 50 per cent of quantity of work.

2 Loading for disposal will be done manually, being small


quantity.

8 - 450
Sr. Reference to
Description Unit Quantity
No. MORD Spec

3 In case some rock is issued to contractor at site, the item


of carriage shall be omitted to the extent of quantity
issued to the Contractor.

(B) Mechanical Means

Unit = cum

Taking output = 36 cum

a) Labour

Mate day 0.40

Mazdoor (Unskilled) day 10.00

Mazdoor (Unskilled) for disposal of loose rock day 15.00

b) Machinery

Hydraulic excavator 0.9 cum with rock breaker hour 5.00


attachment @ 6 cum per hour

Bulldozer D 56.67 cum/hour hour 0.64

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 36 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/36

Note: 1 The quality and availability of rock shall be checked


before affording credit.

2 In case some rock is issued to the contractor at site, the


item of carriage shall be restricted/reduced to that
extent.

3 Being small quantity, manual loading will be economical


in this case and has been provided accordingly.

8.4 1600, 600 & Retaining Walls / Breast Walls


700
Construction of retaining walls/breast walls in cement mortar
1:5 as per drawing and technical specifications Clause 1604

(i) Earthwork in excavation for structures

8 - 451
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Rate as per item No.11.1 of Chapter 11 cum

(ii) Plain cement concrete M 10 grade

Rate as per item No.11.4 of Chapter 11 cum

(iii) Stone masonry in cement mortar 1:5

Rate as per item No. 12.4 (III) (iii) of Chapter 12 cum

(iv) Pointing with cement mortar 1:3

Rate as per item No.12.2 of Chapter 12 sqm

(v) Providing P.C.C. M 20 architectural coping on top of


retaining wall/breast wall

Rate as per item No.12.13 of Chapter 12 m

(vi) Filter material behind retaining wall / breast wall as


per Specification 1204.3.8 in a width of 600 m

Rate as per item No. 12.11 of Chapter 12 cum


(vii) Back filling behind retaining wall/breast wall

Rate as per item No. 12.10 of Chapter 12 cum

Note: 1 Quantities of material/work shall be as per design and


drawings
2 Earth work in excavation may be taken as per site
conditions. It may comprise of a number of sub-items
depending upon the type of soil/rock encountered.
8.7 1600, 300 & 700Construction of Scupper

Construction of scupper with dry stone masonry as per


drawing and technical specifications as per Clause 1606.5.

Unit = 1 m

Taking output = 6 m

(i) Earthwork in excavation for structures as per


drawing and technical specifications

Quantity for 6 m formation width of hill side rock cutting


and foundation as per plate No. 7.27 of Rural Road
Manual

Rate as per item No.11.1 of Chapter 11 cum 115.00

Rate per m = a/6

(ii) Random rubble dry stone masonry

Quantity for 6 m formation width = 38 cum

8 - 452
Sr. Reference to
Description Unit Quantity
No. MORD Spec

a) Labour

Mate day 3.80

Mason (1st Class) day 38.00

Mazdoor (Unskilled) day 57.00

b) Materials

Stone for RR masonary cum 38.00

Bond stone nos 266.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 6 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/6

(iii) Random course rubble dry stone masonry in corbelling

Quantity for 6 m formation width = 9 cum

a) Labour

Mate day 0.72

Mason (2nd class) day 6.00

Mazdoor (Unskilled) day 12.00

b) Materials

Corbelling Stones size 300 mm x 150 mm x 150 nos 1,235.00


mm including wastage

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 6 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/6

(iv) Stone filling in foundation trenches as per drawing


and technical specification

8 - 453
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Quantity for 6 m formation width = 10 cum

a) Labour

Mate day 0.12

Mazdoor (Unskilled) day 3.00

b) Materials

Loose stone cum 12.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 6 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/6

Rate per m length= (i + ii + iii + iv)

Note: 1 Quantities of parapet are not included in the quantities of


scupper.

2 The above analysis is based on plate No.7.27 of Rural


Roads Manual.

3 Rates for earth work are to be taken appropriate to the


type of soil/rock

8.8 1400, 1700 & Construction of RCC guide posts of 250 mm dia M15
800 grade cast-in-situ with 20 mm nominal size aggregate,
true to line and grade, tolerance of vertical RCC posts not
to exceed 1 in 500 as per drawing and Technical
Specification Clause 1608.2

(i) Earth work in excavation for structures

Unit = cum

Rates as per item No. 11.1 of Chapter 11 cum


(ii) RCC M15 grade
Unit = cum

Rate as per item No. 11.4 of Chapter 11 cum

(iii) HYSD steel bars

Unit = t

Rate as per item No. 12.6 of Chapter 12 t

8 - 454
Sr. Reference to
Description Unit Quantity
No. MORD Spec

(iv) Painting two coats including prime coat on new


concrete surface

Unit = sqm

Rate as per item No.10.5 of Chapter 10 sqm

Note: Quantities are to be taken as per drawing

8.9 1600 Providing edge stones on valley side of formation as per


drawing and Technical Specification Clause 1608.2.6

Unit = 1 m

Taking Output = 45 m (100 no of edge stones of size 450 mm


x 300 mm x 100 mm)
a) Labour

Mate day 0.18

Mazdoor (Unskilled) day 3.00


Mason (2nd class) day 1.50

b) Materials
Stones of size 450 mmx300 mmx100 mm nos 100.00

c) Painting two coats including priming coat on new


concrete/stone surfaces
45 x 0.500 = 22.50

Rate as per item No.10.5 of Chapter 10 sqm 22.50

d) Contractor’s profit & Overheads @ 12.5% on (a+b)

e) Add GST, LWC etc. @ 0 on (a+b)

Cost for 45 m = a+b+c+d+e+f

Rate per m = (a+b+c+d+e+f)/45

8.10 1600 & 309 Turfing with Sods

Furnishing and laying of the live sods of perennial turf forming


grass on embankment slope, verges or other locations shown
on the drawing or as directed by the Engineer including
preparation of ground, stacking the sods and watering as per
Clause 309

Unit = sqm

8 - 455
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Taking output = 100 sqm

a) Labour

Mate day 0.16

Mazdoor (Unskilled) day 4.00

b) Machinery

Water tanker including watering for 3 months hour

Tractor with Trolley hour 1.00

c) Materials

Farmyard manure @ 0.18 cum per 100 sqm at site of wor cum 0.18

Water kl 10.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 100 sqm = a+b+c+d+e+f

Rate per sqm = (a+b+c+d+e+f)/100

8.11 1600 & 300 Seeding and Mulching

Preparation of seed bed on previously laid top soil, furnishing


and placing of seeds, fertilizer, multching material, applying
bituminous emulsion at the rate of 0.23 l per sqm and laying
and fixing jute netting, including watering for 3 months all as
per Clause 310.

Unit = sqm

Taking output = 240 sqm

a) Labour

Mate day 0.60

Mazdoor (Unskilled) day 15.00

b) Machinery

Water tanker 6 kl capacity including watering for 3 hour 13.00


months (for one hour per week)
Tractor with Trolley hour 2.40

c) Materials

8 - 456
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Seeds kg 3.60

Sludge/Farm yard manure @ 0.18 cum per 100 sqm cum 0.43

Bitumen Emulsion t 0.055

Jute netting, open weave, 25 mm square opening sqm 264.00

Water for 3 months kl 84.00

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 240 sqm = a+b+c+d

Rate per sqm = (a+b+c+d)/240

8 - 457
Chapter 8

HILL ROADS

Rate
Amount (Rs.)
(Rs.)

102.00 122.40

4,160.15 4,992.18

121.17 484.67

279.96

5,879.22

102.00 367.20

8 - 458
Rate
Amount (Rs.)
(Rs.)

4,160.15 12,896.47

124.85 56.18
665.99

13,985.85

102.00 9.79

4,160.15 399.37

119.94 115.14
26.22

550.52

8 - 459
Rate
Amount (Rs.)
(Rs.)

356.65 855.96

244.56 14,673.60

1,941.20

17,470.76

145.59

244.56 134.51

16.81

151.32

15.13

8 - 460
Rate
Amount (Rs.)
(Rs.)

356.65 285.32

244.56 4,891.20

2,260.00 10,848.00

1,635.00 5,886.00

2,738.82

0.00

24,649.34

94.81

244.56 134.51

16.81

151.32

15.13

8 - 461
Rate
Amount (Rs.)
(Rs.)

356.65 1,883.11

244.56 32,281.92

4,270.63

38,435.66

320.30

244.56 210.32

26.29

236.61

23.66

8 - 462
Rate
Amount (Rs.)
(Rs.)

356.65 242.52

244.56 4,157.52

244.56 2,201.04

2,260.00 9,040.00

1,635.00 6,540.00

2,772.64
0.00

24,953.72

146.79

8 - 463
Rate
Amount (Rs.)
(Rs.)

356.65 485.04

244.56 5,380.32

356.65 713.30

356.65 3,566.50

2,260.00 6,780.00

1,635.00 8,175.00

435.00 12,180.00

120.00 8,040.00

15.00 3,525.00

6,105.65

0.00

54,950.81

323.24

244.56 264.12

33.02

297.14

8 - 464
Rate
Amount (Rs.)
(Rs.)

29.71

356.65 584.91

244.56 3,912.96

285.32 6,847.68

458.55 458.55

1,475.51

13,279.61

829.98

8 - 465
Rate
Amount (Rs.)
(Rs.)

356.65 142.66

244.56 2,445.60

244.56 3,668.40

1,635.00 8,175.00

2,260.00 1,446.40

1,984.76

0.00

17,862.82

496.19

8 - 466
Rate
Amount (Rs.)
(Rs.)

102.00 11,730.00

1,955.00

8 - 467
Rate
Amount (Rs.)
(Rs.)

356.65 1,355.27

458.55 17,424.90

244.56 13,939.92

1,135.00 43,130.00

54.00 14,364.00

11,276.76

0.00

101,490.85

16,915.14

356.65 256.79

285.32 1,711.92

244.56 2,934.72

30.00 37,050.00

5,244.18

0.00

47,197.61

7,866.27

8 - 468
Rate
Amount (Rs.)
(Rs.)

356.65 42.80

244.56 733.68

1,500.00 18,000.00

2,347.06

0.00

21,123.54

3,520.59

30,257.00

8 - 469
Rate
Amount (Rs.)
(Rs.)

356.65 64.20

244.56 733.68
285.32 427.98

80.00 8,000.00

65.36 1,470.70

1,153.23

0.00

11,849.79

263.33

8 - 470
Rate
Amount (Rs.)
(Rs.)

356.65 57.06

244.56 978.24

440.00 0.00

409.00 409.00

56.00 10.08

40.00 400.00

231.80

0.00

2,086.18

20.86

356.65 213.99

244.56 3,668.40

440.00 5,720.00

409.00 981.60

8 - 471
Rate
Amount (Rs.)
(Rs.)

31.00 111.60

56.00 24.08

27,509.00 1,513.00

160.00 42,240.00

40.00 3,360.00

7,229.08

0.00

65,061.75

271.09

8 - 472
Chapter 9

PIPE CULVERTS
Sr. Reference to
Description Unit Quantity
No. MORD Spec
9.1 1100 & 300 Excavation for Structures

Earthwork in excavation for foundation of structures upto 3 m depth


as per drawing and technical specification Clause 1104 includding
setting out, construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and bottom and
backfilling with approved material.

Unit = cum

Rate as per item No.11.1 of Chapter 11

Rate as applicable for the type of soil/rock are to be taken

9.2 1100 & 800 Bedding for Pipe

(A) Type A (Concrete Cradle) Bedding

Laying concrete cradle bedding with M15 Grade Cement


Concrete as per Clause 1105 (i)
Unit = cum

Rate as per Item No.11.4 (II)(i) of Chapter 11 cum 1.00

(B) Type B (First Class) Bedding

i. Laying (First Class) bedding on well compacted sand, moorum


as per Clause 1105 (ii)

Unit = cum

Rate as per Item No.11.2 of Chapter 11 cum 0.80

ii Laying (First Class) bedding on well compacted approved


granular material as per Clause 1105 (ii)

Unit = cum

a) Labour
i mate day 0.01
ii Mazdoor day 0.30
b) Material
i Sand(assuming 20 percent voids) cum 1.20
c) Contractor’s profit & Overheads @ 12.5% on (a+b)
d) Add GST, LWC etc. @ 0 on (a+b)

Rate per Cum = a+b+c+d

9 - 473
Sr. Reference to
Description Unit Quantity
No. MORD Spec

9.3 1100 Providing and Laying Reinforced Cement Concrete Pipe NP3 as
per design in Single Row

Providing and laying reinforced cement concrete pipe NP3 for


culverts on first class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets Clause 1106.

Unit = m

Taking output = 7.5 m

(3 pipes of 2.5 m length each)

(A) 1200 mm dia

a) Labour

Mate day 0.14

Mason (1st Class) day 0.50

Mazdoor (Unskilled) day 3.00

b) Material

Sand at site cum 0.05

Cement at site t 0.07

RCC pipe NP3 pipe including collar at site m 7.50

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

(B) 1000 mm dia

a) Labour

Mate day 0.09

Mason (1st Class) day 0.25

Mazdoor (Unskilled) day 2.00

b) Material

Sand at site cum 0.04

9 - 474
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Cement at site t 0.03

RCC pipe NP3 concrete pipe including collar at site m 7.10

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

(C) 600 mm dia

a) Labour

Mate day 0.07

Mason (1st Class) day 0.20

Mazdoor (Unskilled) day 1.60

b) Material

Sand at site cum 0.03

Cement at site t 0.02

RCC pipe NP3 concrete pipe including collar at site m 7.10

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

Note: The labour rate for 600 mm dia Hume pipe may be derived from the
rates for 750 dia by decreasing 20 per cent

9.4 1100 Providing and Laying Reinforced Cement Concrete Pipe NP4 as
per design in Single Row

Providing and laying reinforced cement concrete pipe NP4 for


culverts on first class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets Clause 1106.

Unit = m
Taking output = 7.5 m

(3 pipes of 2.5 m length each)


(A) 1200 mm dia

9 - 475
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Labour

Mate day 0.14

Mason (1st Class) day 0.50

Mazdoor (Unskilled) day 3.00

b) Material

Sand at site cum 0.05

Cement at site t 0.07

RCC pipe NP4 pipe including collar at site m 7.50

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

(B) 1000 mm dia

a) Labour

Mate day 0.09

Mason (1st Class) day 0.25

Mazdoor (Unskilled) day 2.00

b) Material

Sand at site cum 0.04

Cement at site t 0.03

RCC pipe NP4 concrete pipe including collar at site m 7.10

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

9 - 476
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Cost for 7.5 m = a+b+c+d+e+

Rate per m = (a+b+c+d+e)/7.5

Note: The labour rate for 600 mm dia Hume pipe may be derived from the
rates for 750 dia by decreasing 20 per cent

9.5 1100 Providing and Laying Reinforced Cement Concrete Pipe NP3
as per Design in Double Row

Providing and laying reinforced cement concrete pipe NP3 for


culverts on first class bedding of granular material in double row
including fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets as per Clause 1106.

Unit = m

Taking output = 7.5 m

(6 pipes of 2.5 m length each in two rows)

(A) 1200 mm dia

a) Labour

Mate day 0.34

Mason (1st Class) day 1.20

Mazdoor (Unskilled) day 7.20


b) Material

Sand at site cum 0.11

Cement at site t 0.14


RCC pipe NP3 concrete pipe including collar at site m 15.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

(B) 1000 mm dia

a) Labour

Mate day 0.22

Mason 1st Class day 0.60

9 - 477
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Unskilled) day 4.80

b) Material

Sand at site cum 0.08

Cement at site t 0.06

RCC pipe NP3 concrete pipe including collar at site m 15.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

9.6 1100 Providing and Laying Reinforced Cement Concrete Pipe NP4
as per Design in Double Row
Providing and laying reinforced cement concrete pipe NP4 for
culverts on first class bedding of granular material in double row
including fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets as per Clause 1106.

Unit = m

Taking output = 7.5 m

(6 pipes of 2.5 m length each in two rows)

(A) 1200 mm dia

a) Labour

Mate day 0.34

Mason (1st Class) day 1.20

Mazdoor (Unskilled) day 7.20

b) Material

Sand at site cum 0.11

Cement at site t 0.14

RCC pipe NP4 concrete pipe including collar at site m 15.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

9 - 478
Sr. Reference to
Description Unit Quantity
No. MORD Spec
d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

(B) 1000 mm dia

a) Labour

Mate day 0.22

Mason 1st Class day 0.60

Mazdoor (Unskilled) day 4.80

b) Material

Sand at site cum 0.08

Cement at site t 0.06

RCC pipe NP4 concrete pipe including collar at site m 15.00

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

9.7 1100 & 800 Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling
course below open foundation of Head walls as per drawings &
Technical Specification Clause 1109

Rate as per item No.11.4 of Chapter 11 cum

9.8 1100 & 600 Brick Masonry Work in cement mortar in foundation of Head
walls complete exculding pointing and plastering as per
drawing and technical specification Clause 1109

(A) Brick Masonry in 1:4 cement mortar

Rate as per item No.11.5 (ii) Chapter 11 cum

(B) Brick Masonry in cement-lime mortar (1:0.5:4.5)

Rate as per item No.11.5 (iii) Chapter 11 cum

9 - 479
Sr. Reference to
Description Unit Quantity
No. MORD Spec
9.9 1100 & 700 Stone Masonry Work in cement mortar in foundation of Head
walls complete as per drawing and technical specification
Clasue 1109

(A) In 1:4 cement mortar

Rate as per item No.11.6 (II) (ii) Chapter 11 cum

(B) In cement-lime mortar (1:0.5:4.5)

Rate as per item No.11.6 (II) (iii) Chapter 11 cum

9.10 1100 & 600 Pointing with Cement Mortar (1:3) on brickwork as per
technical specification Clause 613.3

Rate as per item No.12.2 of Chapter 12 10


sqm
9.11 1100 & 600 Plastering with Cement Mortar (1:4), 15 mm thick on brickwork
in substructure as per technical specification

Rate as per item No.12.3 of Chapter 12 10


sqm
9.12 1100 & 300 Backfilling in Foundation Trenches as per drawing and
technical specification Clause 1108
Rate as per Item No.11.2 of Chapter 11 cum

9.13 1100, 600, 700 Providing PCC M20 Architectural Coping on the top of wing
& 1200 wall, return wall etc. complete as per drawing and technical
specification Clause 615

Rate as per Item No.12.13 of Chapter 12 m

9 - 480
Chapter 9

PIPE CULVERTS
Rate
Amount (Rs.)
(Rs.)

5,085.61 5,085.61

1,411.79 1,129.00

356.65 3.57
244.56 73.37

950.00 1,140.00
152.12
0.00

1,369.05

9 - 481
Rate
Amount (Rs.)
(Rs.)

356.65 49.93

458.55 229.28

244.56 733.68

850.00 42.50

6,200.00 434.00

8,570.00 64,275.00

8,220.55

0.00

73,984.93

9,864.66

356.65 32.10

458.55 114.64

244.56 489.12

850.00 34.00

9 - 482
Rate
Amount (Rs.)
(Rs.)
6,200.00 186.00

6,340.00 45,014.00

5,733.73

0.00

51,603.59

6,880.48

356.65 24.97

458.55 91.71

244.56 391.30

850.00 25.50

6,200.00 124.00

2,618.00 18,587.80

2,405.66

0.00

21,650.93

2,886.79

9 - 483
Rate
Amount (Rs.)
(Rs.)

356.65 49.93

458.55 229.28

244.56 733.68

850.00 42.50

6,200.00 434.00

10,370.00 77,775.00

9,908.05

0.00

89,172.43

11,889.66

356.65 32.10

458.55 114.64

244.56 489.12

850.00 34.00

6,200.00 186.00

8,579.00 60,910.90

7,720.84

0.00

9 - 484
Rate
Amount (Rs.)
(Rs.)
69,487.60

9,265.01

356.65 121.26

458.55 550.26

244.56 1,760.83

850.00 93.50

6,200.00 868.00
8,570.00 128,550.00

16,492.98

0.00

148,436.83

19,791.58

356.65 78.46

458.55 275.13

9 - 485
Rate
Amount (Rs.)
(Rs.)
244.56 1,173.89

850.00 68.00

6,200.00 372.00

6,340.00 95,100.00

12,133.44

0.00

109,200.92

14,560.12

356.65 121.26

458.55 550.26

244.56 1,760.83

850.00 93.50

6,200.00 868.00

10,370.00 155,550.00

19,867.98

9 - 486
Rate
Amount (Rs.)
(Rs.)
0.00

178,811.83

23,841.58

356.65 78.46

458.55 275.13

244.56 1,173.89

850.00 68.00

6,200.00 372.00

8,579.00 128,685.00

16,331.56

0.00

146,984.04

19,597.87

9 - 487
Rate
Amount (Rs.)
(Rs.)

9 - 488
Chapter 10

TRAFFIC SIGNS, MARKINGS AND OTHER ROAD APPURTENANCES


Sr. Reference to
Description Unit
No. MORD Spec
10.1 1700 Printing New Letters and Figures of any Shade

Printing new letter and figures of any shade with synthetic


enamel paint black or any other approved colour to give an even
shade as per drawings and Technical Specification Clause 1701

i) Hindi (Matras commas and the like not to be measured


and paid for. Half letters shall be counted as half only)

Details for 100 letters of 160 mm height, i.e., 1600 cm

Unit = per cm height per letter

a) Labour

Mate day

Painter 1st Class day

Mazdoor (Unskilled) day

b) Material

Paint litre

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1600 cm = a+b+c+d+e

Rate per cm height per letter = (a+b+c+d+e)/1600

ii) English and Roman

Hyphens, commas and the like not to be measured and


paid for. Detail for 100 letters of 160 mm height, i.e., 1600
cm

Unit = per cm height per letter

a) Labour

Mate day

Painter Ist class day

Mazdoor day

10 - 489
Sr. Reference to
Description Unit
No. MORD Spec
b) Material

Paint litre

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 1600 cm = a+b+c+d+e

Rate per cm height per letter = (a+b+c+d+e )/1600

10.2 1700, 300, 800 Traffic Signs

A. Retro-reflectorised Traffic Signs

I Providing and fixing of retro-reflectorised cautionary,


mandatory and informatory sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause
1701.2.3 fixed over aluminium sheeting, 1.5 mm thick
supported on a mild steel angle iron post 75 mm x 75 mm x
6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 450
mm x 450 mm x 600 mm, 600 mm below ground level as
per drawings and Technical Specification Clause 801

Unit = each

Taking output = one traffic sign

i) Excavation for foundation

As per item No.11.1 of Chapter 11 cum

ii) Cement concrete M15 grade

As per item No.11.4 of Chapter 11 cum

iii) Painting Angle Iron Post with Primer and two


coats of Epoxy Paint as per specifications

As per item No.10.7 of this Chapter sqm

a) labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

Mild steel angle iron 75 x 75 x 6 mm kg

10 - 490
Sr. Reference to
Description Unit
No. MORD Spec
Aluminium sheeting fixed with encapsulated lens
type reflective sheeting of size including lettering
and signs as applicable background with epoxy
paint

Add 3 per cent of cost of angle iron towards cost


of fabrication, drilling holes, nuts, bolts, etc.

i) 900 mm equilateral triangle sqm

OR

ii) 600 mm equilateral triangle sqm

OR

iii) 600 mm circular sqm

OR

iv) 800 mm x 600 mm rectangular sqm

OR

v) 600 mm x 450 mm rectangular sqm

OR

vi) 600 mm x 600 mm square sqm

OR

vii) 900 mm side octagon sqm

c) Machinery

Tractor with trolley hour

i 900mm equilateral triangle

d) Contractor’s profit & Overheads @ 12.5% on (a+b i+c)

e) Add GST, LWC etc. @ 0 on (a+b i+c)

Rate per traffic sign = (i+ii+iii+a+b i+c+d+e)

ii 600mm equilateral triangle

d) Contractor’s profit & Overheads @ 12.5% on (a+b ii+c)

10 - 491
Sr. Reference to
Description Unit
No. MORD Spec
e) Add GST, LWC etc. @ 0 on (a+b ii+c)

Rate per traffic sign = (i+ii+iii+a+b ii+c+d+e)

iii 600mm circular

d) Contractor’s profit & Overheads @ 12.5% on (a+b iii+c)

e) Add GST, LWC etc. @ 0 on (a+b iii+c)

Rate per traffic sign = (i+ii+iii+a+b iii+c+d+e)

iv 800mm x 600mm rectangular

d) Contractor’s profit & Overheads @ 12.5% on (a+b iv+c)

e) Add GST, LWC etc. @ 0 on (a+b iv+c)

Rate per traffic sign = (i+ii+iii+a+b iv+c+d+e)

v 600mm x 450mm rectangular

d) Contractor’s profit & Overheads @ 12.5% on (a+b v+c)

e) Add GST, LWC etc. @ 0 on (a+b v+c)

Rate per traffic sign = (i+ii+iii+a+b v+c+d+e)

vi 600mm x 600mm square

d) Contractor’s profit & Overheads @ 12.5% on (a+b vi+c)

e) Add GST, LWC etc. @ 0 on (a+b vi+c)

Rate per traffic sign = (i+ii+iii+a+b vi+c+d+e)

10 - 492
Sr. Reference to
Description Unit
No. MORD Spec
vii 900mm side octagon

d) Contractor’s profit & Overheads @ 12.5% on (a+b vii+c)

e) Add GST, LWC etc. @ 0 on (a+b vii+c)

Rate per traffic sign = (i+ii+iii+a+b vii+c+d+e)

II Providing and fixing of retro-reflectorised cautionary,


mandatory and informatory sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 1.5 mm thick
supported on GI pipe 50 mm dia firmly fixed to the ground
by means of properly designed foundation with M-15 grade
cement concrete 450 mm x 450 mm x 600 mm, 600 mm
below ground level as per drawings and Technical
Specification Clause 1701

Unit = each

Taking output = one traffic sign

i) Excavation for foundation

As per item No.11.1 of Chapter 11 cum

ii) Cement concrete M15 grade

As per item No.11.4 of Chapter 11 cum

a) Labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

50 mm dia GI Pipe 2.85 m long including 5 per m


cent wastage

Aluminium sheeting fixed with encapsulated lens sqm


type reflective sheeting of size including lettering
and signs as applicable background with epoxy
paint

Add 3 per cent of cost of GI Pipe towards cost of


fabrication, drilling holes, nuts, bolts etc.

i) 900 mm equilateral triangle sqm

OR

10 - 493
Sr. Reference to
Description Unit
No. MORD Spec
ii) 600 mm equilateral triangle sqm

OR

iii) 600 mm circular sqm

OR

iv) 800 mm x 600 mm rectangular sqm

OR

v) 600 mm x 450 mm rectangular sqm

OR

vi) 600 mm x 600 mm square sqm

OR

vii) 900 mm sides octagon sqm

c) Machinery

Tractor with trolley hour

i 900mm equilateral triangle

d) Contractor’s profit & Overheads @ 12.5% on (a+b i+c)

e) Add GST, LWC etc. @ 0 on (a+b i+c)

Rate per traffic sign = (i+ii+iii+a+b i+c+d+e)

ii 600mm equilateral triangle

d) Contractor’s profit & Overheads @ 12.5% on (a+b ii+c)

e) Add GST, LWC etc. @ 0 on (a+b ii+c)

Rate per traffic sign = (i+ii+iii+a+b ii+c+d+e)

iii 600mm circular

d) Contractor’s profit & Overheads @ 12.5% on (a+b iii+c)

10 - 494
Sr. Reference to
Description Unit
No. MORD Spec
e) Add GST, LWC etc. @ 0 on (a+b iii+c)

Rate per traffic sign = (i+ii+iii+a+b iii+c+d+e)

iv 800mm x 600mm rectangular

d) Contractor’s profit & Overheads @ 12.5% on (a+b iv+c)

e) Add GST, LWC etc. @ 0 on (a+b iv+c)

Rate per traffic sign = (i+ii+iii+a+b iv+c+d+e)

v 600mm x 450mm rectangular

d) Contractor’s profit & Overheads @ 12.5% on (a+b v+c)

e) Add GST, LWC etc. @ 0 on (a+b v+c)

Rate per traffic sign = (i+ii+iii+a+b v+c+d+e)

vi 600mm x 600mm square

d) Contractor’s profit & Overheads @ 12.5% on (a+b vi+c)

e) Add GST, LWC etc. @ 0 on (a+b vi+c)

Rate per traffic sign = (i+ii+iii+a+b vi+c+d+e)

vii 900mm side octagon

d) Contractor’s profit & Overheads @ 12.5% on (a+b vii+c)

e) Add GST, LWC etc. @ 0 on (a+b vii+c)

Rate per traffic sign = (i+ii+iii+a+b vii+c+d+e)

10 - 495
Sr. Reference to
Description Unit
No. MORD Spec
III Providing and fixing of retro-reflectorised cautionary,
mandatory and informatory sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 1.5 mm thick
supported on RCC Post 100 mm x 100 mm firmly fixed to
the ground by means of properly designed foundation with
M15 grade cement concrete 450 mm x 450 mm x 600 mm,
600 mm below ground level as per approved drawing
Clause 1701

Unit = each

Taking output = one traffic sign

i) Excavation for foundation

As per item No.11.1 of Chapter 11 cum

ii) Cement concrete M15 grade

As per item No.11.4 of Chapter 11 cum

iii) RCC M15 Grade in Sub-structure

As per item No.12.5 of Chapter 12 cum

iv) Steel reinforcement HYSD bars

As per item No.12.6 of Chapter 12 t

v) Painting two coats including prime coat on


concrete surface with Epoxy Paint as per
specifications

As per item No.10.7 of this Chapter sqm

a) labour (For fixing at site)

Mate day

Mazdoor day

b) Material

Aluminium sheeting fixed with encapsulated lens


type reflective sheeting of size including lettering
and signs as applicable background with epoxy
paint

Add 3 per cent of cost of RCC Post towards cost


of drilling holes, nuts, bolts, etc.

i) 900 mm equilateral triangle sqm

OR

ii) 600 mm equilateral triangle sqm

10 - 496
Sr. Reference to
Description Unit
No. MORD Spec
OR

iii) 600 mm circular sqm

OR

iv) 800 mm x 600 mm rectangular sqm

OR

v) 600 mm x 450 mm rectangular sqm

OR

vi) 600 mm x 600 mm square sqm

OR

vii) 900 mm sides octagon sqm

c) Machinery

Tractor with trolley hour

i 900mm equilateral triangle

d) Contractor’s profit & Overheads @ 12.5% on (a+b i+c)

e) Add GST, LWC etc. @ 0 on (a+b i+c)

Rate per traffic sign = (i+ii+iii+iv+v+a+b i+c+d+e)

ii 600mm equilateral triangle

d) Contractor’s profit & Overheads @ 12.5% on (a+b ii+c)

e) Add GST, LWC etc. @ 0 on (a+b ii+c)

Rate per traffic sign = (i+ii+iii+iv+v+a+b ii+c+d+e)

iii 600mm circular

d) Contractor’s profit & Overheads @ 12.5% on (a+b iii+c)

e) Add GST, LWC etc. @ 0 on (a+b iii+c)

10 - 497
Sr. Reference to
Description Unit
No. MORD Spec

Rate per traffic sign = (i+ii+iii+iv+v+a+b iii+c+d+e)

iv 800mm x 600mm rectangular

d) Contractor’s profit & Overheads @ 12.5% on (a+b iv+c)

e) Add GST, LWC etc. @ 0 on (a+b iv+c)

Rate per traffic sign = (i+ii+iii+iv+v+a+b iv+c+d+e)

v 600mm x 450mm rectangular

d) Contractor’s profit & Overheads @ 12.5% on (a+b v+c)

e) Add GST, LWC etc. @ 0 on (a+b v+c)

Rate per traffic sign = (i+ii+iii+iv+v+a+b v+c+d+e)

vi 600mm x 600mm square

d) Contractor’s profit & Overheads @ 12.5% on (a+b vi+c)

e) Add GST, LWC etc. @ 0 on (a+b vi+c)

Rate per traffic sign = (i+ii+iii+iv+v+a+b vi+c+d+e)

vii 900mm side octagon

d) Contractor’s profit & Overheads @ 12.5% on (a+b vii+c)

e) Add GST, LWC etc. @ 0 on (a+b vii+c)

Rate per traffic sign = (i+ii+iii+iv+v+a+b vii+c+d+e)

10 - 498
Sr. Reference to
Description Unit
No. MORD Spec
Note: 1 Any one area of aluminium sheeting given at (i) to (vii) may
be adopted as per site requirement and in accordance with
IRC:67.

2 The rate for excavation, cement concrete M-15, RCC M-15


in Sub-structure, steel re-inforcement and painting may be
taken from respective Chapters.

3 The depth of foundation and quantity of cement concrete in


the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas.
This is applicable to all road signs and directions boards.

B. Semi Reflective Traffic Signs

Providing and fixing of semi reflective cautionary,


mandatory and informatory sign board as per IRC:67 made
of 1.5 mm thick MS Sheet duly stove white colour in front
and gray colour on back with red reflective border of 65 mm
width and required letters and figures with reflective tape
engineering grade as per Clause 1701.3.9 of MORD for
Rural Roads of required shade and colour supported and
welded on 47mm x 47 mm x 12 SWG sheet tube firmly
fixed to the ground by mean of properly designed
foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per
approved drawing Clause 1701.2.2

Unit = Each

Taking output = one traffic sign

(i) Excavation foundations

As per Item No. 1 to 11.1 of Chapter 11 cum

(ii) Cement concrete M-15 Grade

As per item no. 11.4 of Chapter 11 cum

(iii) Painting steel tube posts with primer and two coats of
epoxy paint as per specifications

As per item no 10.7 of Chapter 11 sqm

a) Labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

Support of M.S. Sheet tube

10 - 499
Sr. Reference to
Description Unit
No. MORD Spec
(I) 47 mm x 47 mm x 12 SWG Sheet kg

3050 mm long

(II) Angle iron 50 x 50 x 6 mm for hold fast including kg


5% wastage

(III) 1.5 mm thick M.S. Sheet duly painted with stove


enamelled paint including lettering, signs,
border, message with reflective tape of
engineering grade required size, shade and
colour as per Technical Specifications

Add 3% cost of MS Sheet tube 12 SWG and


angle irons towards the cost of fabrication,
drilling holes, nuts and bolts etc.

i) 900 mm equilateral & triangle sqm

OR

ii) 600 mm equilateral & triangle sqm

OR

iii) 600 mm circular sqm

OR

iv) 800 mm x 600 mm rectangular sqm

OR

v) 600 mm x 450 mm rectangular sqm

OR

vi) 600 mm x 600 mm sqm

OR

vii) 900 mm side octagon sqm

c) Machinery

Tractor with Trolley hour

i 900mm equilateral triangle

d) Contractor’s profit & Overheads @ 12.5% on (a+b i+c)

e) Add GST, LWC etc. @ 0 on (a+b i+c)

10 - 500
Sr. Reference to
Description Unit
No. MORD Spec
Rate per traffic sign = (i+ii+iii+a+b i+c+d+e)

ii 600mm equilateral triangle

d) Contractor’s profit & Overheads @ 12.5% on (a+b ii+c)

e) Add GST, LWC etc. @ 0 on (a+b ii+c)

Rate per traffic sign = (i+ii+iii+a+b ii+c+d+e)

iii 600mm circular

d) Contractor’s profit & Overheads @ 12.5% on (a+b iii+c)

e) Add GST, LWC etc. @ 0 on (a+b iii+c)

Rate per traffic sign = (i+ii+iii+a+b iii+c+d+e)

iv 800mm x 600mm rectangular

d) Contractor’s profit & Overheads @ 12.5% on (a+b iv+c)

e) Add GST, LWC etc. @ 0 on (a+b iv+c)

Rate per traffic sign = (i+ii+iii+a+b iv+c+d+e)

v 600mm x 450mm rectangular

d) Contractor’s profit & Overheads @ 12.5% on (a+b v+c)

e) Add GST, LWC etc. @ 0 on (a+b v+c)

Rate per traffic sign = (i+ii+iii+a+b v+c+d+e)

vi 600mm x 600mm square

d) Contractor’s profit & Overheads @ 12.5% on (a+b vi+c)

10 - 501
Sr. Reference to
Description Unit
No. MORD Spec
e) Add GST, LWC etc. @ 0 on (a+b vi+c)

Rate per traffic sign = (i+ii+iii+a+b vi+c+d+e)

vii 900mm side octagon

d) Contractor’s profit & Overheads @ 12.5% on (a+b vii+c)

e) Add GST, LWC etc. @ 0 on (a+b vii+c)

Rate per traffic sign = (i+ii+iii+a+b vii+c+d+e)

Note: 1 Any one area of M.S. Sheet given at (i) to (viii) may be
adopted as per site requirement and in accordance with
IRC-67.

2 The rate for excavation, cement concrete M-15, and


painting may be taken from respective Chapters.

3 The depth of foundation and quantity of cement in the


foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal area.
This is applicable to all road signs and direction boards.

10.3 1700, 800 & 300 Direction and Place Identification signs upto 0.9 sqm size
board

A. Retro-reflectorised Traffic Signs

(i) Providing and erecting direction and place identification


retro-reflectorised sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 2 mm thick with
area not exceeding 0.9 sqm supported on a mild steel
single angle iron post 75 x 75 x 6 mm firmly fixed to the
ground by means of properly designed foundation with M-
15 grade cement concrete 450 x 450 x 600 mm, 600 mm
below ground level as per approved drawing and Technical
Specification Clause 1701

Unit = sqm

Taking output = 0.9 sqm

i) Excavation for foundation

As per item No.11.1 of Chapter 11 cum

10 - 502
Sr. Reference to
Description Unit
No. MORD Spec
ii) Cement concrete M-15 grade

As per item No.11.4 of Chapter 11 cum

iii) Painting Angle Iron Post with Primer and two


coats of Epoxy Paint as per specifications

Rate as per item No.10.7 of this Chapter sqm

a) Labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

Mild steel angle iron 75 x 75 x 6 mm kg

Aluminium sheeting fixed with encapsulated lens type sqm


reflective sheeting of size 0.90 sqm including lettering
and signs as applicable background with epoxy paint

Add 3 per cent of cost of angle iron towards cost of


fabrication, drilling holes, nuts, bolts, etc.

c) Machinery

Tractor with trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 0.9 sqm = (i+ii+iii+a+b+c+d)

Rate per sqm (for sign having area upto 0.9 sqm) =
(i+ii+iii+a+b+c+d)/0.90

(ii) Providing and erecting direction and place identification


retro-reflectorised sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 2 mm thick with
area not exceeding 0.9 sqm supported on 2 inch dia GI
Pipe firmly fixed to the ground by means of properly
designed foundation with M-15 grade cement concrete 450
x 450 x 600 mm, 600 mm below ground level as per
approved drawing and Tehnical Specification Clause 1701.

Unit = sqm

Taking output = 0.9 sqm

10 - 503
Sr. Reference to
Description Unit
No. MORD Spec
i) Excavation for foundation

As per item No.11.1 of Chapter 11 cum

ii) Cement concrete M-15 grade

As per item No.11.4 of Chapter 11 cum

a) Labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

50mm dia GI Pipe 2.85 m long including 5 per cent m


wastage

Aluminium sheeting fixed with encapsulated lens type sqm


reflective sheeting of size including lettering and signs
as applicable background with epoxy paint

Add 3 per cent of cost of GI Pipe towards cost of


fabrication, drilling holes, nuts, bolts etc.

c) Machinery

Tractor with trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 0.9 sqm = a+b+c+d

Rate per sqm (for sign having area upto 0.9 sqm) =
(a+b+c+d)/0.90

(iii) Providing and erecting direction and place identification


retro-reflectorised sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 2 mm thick with
area not exceeding 0.9 sqm supported on RCC Post 100
mm x 100 mm firmly fixed to the ground by means of
properly designed foundation with M-15 grade cement
concrete 450 x 450 x 600 mm, 600 mm below ground level
as per approved drawing and Technical Specification
Clause 1701

Unit = sqm

Taking output = 0.9 sqm

i) Excavation for foundation

10 - 504
Sr. Reference to
Description Unit
No. MORD Spec
As per item No.11.1 of Chapter 11 cum

ii) Cement concrete M-15 grade

As per item No.11.4 of Chapter 11 cum

iii) RCC M-15 Grade in Sub-structure

As per item No.12.5 of Chapter 12 cum

iv) Steel re-inforcement HYSD bars

As per item No.12.6 of Chapter 12 t

v) Painting two coats including prime coat on


concrete surface with Epoxy Paint as per
specifications

As per item No.10.7 of Chapter 10 sqm

a) Labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

Aluminium sheeting fixed with encapsulated lens type sqm


reflective sheeting of size including lettering and signs
as applicable background with epoxy paint

Add 3 per cent of cost of RCC Post towards cost of


drilling holes, nuts, bolts etc.

c) Machinery

Tractor with trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 0.9 sqm = i+ii+iii+iv+v+a+b+c+d+e

Rate per sqm (for sign having area upto 0.9 sqm) =
(a+b+c+d+e+f)/0.90

Note: 1 Lettering and arrow markings on sign board to be provided


separately as per actual requirement. Rates for these items
have been analysed separately.

10 - 505
Sr. Reference to
Description Unit
No. MORD Spec
2 The rate for excavation, cement concret M15, RCC M15 in
Sub-structure, steel re-inforcement and painting may be
taken from respective Chapters.

3 The depth of foundation and quantity of cement concrete in


the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas.
This is applicable to all road signs and directions boards.

B. Semi-Reflective Traffic signs

Direction and place indentification signs up to 0.9 sqm


size board

Providing and erecting direction and place identifications of


semi reflective sign boards as per IRC:67 made of 2 mm
thick M.S. Sheet duly stove enameled paint in white colour
in front and grey colour on back with red reflective border of
70 mm width and required message, letters, figures with
reflective engineering grade tape as per MORD
specifications of required shade and colour. Supported and
welded on 47 mm x 47mm of 12 SWG Square tube of
3050 mm height duly strengthened by 25 mm x 5 mm M/s
flat iron on edges on back firmly fixed to the ground by
means of properly designed foundations with M-15 grade
cement concrete 450 mm x 450 mm x 600 mm, 600 mm
below ground level as per approved drawing and Technical
Specification Clause 1701

Unit = each

Take Output = 0.9 sqm

(i) Excavation for foundations

As per Item No. 11.1 of Chapter 11 cum

(ii) Cement Concrete M-15 grade

As per Item No. 11.4 of Chapter 11 cum

(iii) Painting on M.S. tube post with primer and two coat of
epoxy paint as per specifications

As per item No.10.7 of Chapter 10 sqm

a) Labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Materials

10 - 506
Sr. Reference to
Description Unit
No. MORD Spec
i) Support of MS sheet tube

47 mm x 47 mm of 12 SWG sheet 3050 mm long kg

ii) Angle iron 50 x 50 x 6 mm for lugs including 5% kg


wastage

iii) 2 mm thick MS sheet strengthened by 25 mm x 5 mm sqm


MS flat iron & painted with stove enameled paint
including lettering, signs, message, border with
reflective tape of engineering grade of required shade
and colour as per Technical Specifications.

Add 3% cost of MS sheet angle iron towards the cost


of fabrications, drilling, holes, nuts, bolts, etc.

c) Machinery

Tractor with Trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 0.9 sqm = (i+ii+iii+a+b+c+d)

Rate per sqm = (i+ii+iii+a+b+c+d) / 0.9

Note: Rate for excavation, cement concrete M15 and painting may be
taken from respective Chapters.

10.4 1700, 800 & 300 Direction and Place Identification signs with size more than
0.9 sqm size board

A. Retro-reflectorised Traffic Signs

(i) Providing and erecting direction and place identification


retro-\reflectorised sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 2 mm thick with
area exceeding 0.9 sqm supported on mild steel angle iron
posts 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the
ground by means of properly designed foundation with M-
15 grade cement concrete 450 mm x 450 mm x 600 mm,
600 mm below ground level as per approved drawing and
Technical Specification Clause 1701

Unit = sqm

Taking output = 1.50 sqm

i) Excavation for foundation

10 - 507
Sr. Reference to
Description Unit
No. MORD Spec
As per item No.11.1 of Chapter 11 cum

ii) Cement concrete M-15 grade

As per item No.11.4 of Chapter 11 cum

iii) Painting Angle Iron Post with Primer and two


coats of Epoxy Paint specifications

As per item No.10.7 of Chapter 10 sqm

a) Labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 m kg


long, 2 nos. with 5 per cent wastage

Aluminium sheeting fixed with encapsulated lens type sqm


reflective sheeting of size including lettering and signs
as applicable background with epoxy paint

Add 3 per cent of cost of angle iron towards cost of


fabrication, drilling holes, nuts, bolts, etc.

c) Machinery

Tractor with trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 1.5 sqm = i+ii+iii+a+b+c+d

Rate per sqm (for sign having area more than 0.9 sqm)
= (i+ii+iii+a+b+c+d)/1.50

(ii) Providing and erecting direction and place identification


retro-reflectorised sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 2 mm thick with
area exceeding 0.9 sqm supported on dia GI Pipe firmly
fixed to the ground by means of properly designed
foundation with M-15 grade cement concrete 450 mm x 450
mm x 600 mm, 600 mm below ground level as per
approved drawing and Technical Specification Clause 1701

Unit = sqm

10 - 508
Sr. Reference to
Description Unit
No. MORD Spec
Taking output = 1.50 sqm

i) Excavation for foundation

As per item No.11.1 of Chapter 11 cum

ii) Cement concrete M15 grade

As per item No.11.4 of Chapter 11 cum

a) Labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

50 mm dia GI Pipe 2.85 m long including 5 per m


cent wastage

Aluminium sheeting fixed with encapsulated lens sqm


type reflective sheeting of size including lettering
and signs as applicable background with epoxy
paint

Add 3 per cent of cost of GI Pipe towards cost of


fabrication, drilling holes, nuts, bolts, etc.

c) Machinery

Tractor with trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 1.50 sqm = i+ii+a+b+c+d+e+f

Rate per sqm ( for sign having area more than 0.9
sqm) = (i+ii+a+b+c+d+e+f)/1.50

(iii) Providing and erecting direction and place identification


retro- reflectorised sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 2 mm thick with
area exceeding 0.9 sqm supported on RCC Posts 100 mm
x 100 mm firmly fixed to the ground by means of properly
designed foundation with M 15 grade cement concrete 450
mm x 450 mm x 600 mm, 600 mm below ground level as
per approved drawing and Technical Specification Clause
1701

Unit = sqm

10 - 509
Sr. Reference to
Description Unit
No. MORD Spec
Taking output = 1.50 sqm

i) Excavation for foundation

As per item No.11.1 of Chapter 11 cum

ii) Cement concrete M15 grade

As per item No.11.4 of Chapter 11 cum

iii) RCC M-15 Grade in Sub-structure

As per item No.12.5 of Chapter 12 cum

iv) Steel re-inforcement HYSD bars

As per item No.12.6 of Chapter 12 t

v) Painting two coats including prime coat on


concrete surface with Epoxy Paint as per
specifications

As per item No.10.7 of Chapter 10 sqm

a) Labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

Aluminium sheeting fixed with encapsulated lens type sqm


reflective sheeting of size including lettering and signs
as applicable background with epoxy paint

Add 3 per cent of cost of RCC Post towards cost of


drilling holes, nuts, bolts, etc.

c) Machinery

Tractor with trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 1.5 sqm = a+b+c+d+e+f

Rate per sqm (for sign having area more than 0.9 sqm)
= (a+b+c+d+e+f)/1.50

Note: 1 Lettering and arrow markings on sign boards to be provided


separately as per actual requirement. Rates for these items
have been analysed separately.

10 - 510
Sr. Reference to
Description Unit
No. MORD Spec
2 The rate for excavation, cement concrete M15, RCC M15 in
Sub-structure, steel re-inforcement and painting may be
taken from respective Chapters.

3 The depth of foundation and quantity of cement concrete in


the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas.
This is applicable to all road signs and directions boards.

B. Semi-Reflective Traffic signs

Direction and place identification signs more than 0.90


sqm sign board

Providing and erecting direction and place identification of


semi reflective sign boards as per IRC-67 made of 2 mm
thick M.S. Sheet duly stove enameled paint white colour in
front and grey colour on back with reflective border of 70
mm width and required message, letters, figures with
reflective tape of engineering grade as per MORD
specifications of required shade and colour. Supported and
welded on two nos. 47 mm x 47 mm of 12 SWG square
tube of 3050 mm height duly strengthened by 25 mm x 5
mm MS flat iron on edges on back firmly fixed to the ground
by means of properly designed foundations with M-15
grade cement concrete 450 mm x 450 mm x 600 mm, 600
mm below ground level as per approved drawing and
Technical Specification Clause 1701

Unit = each

Taking output = 1.5 sqm

(i) Excavation for foundations as

As per item no. 11.1 Chapter 11 cum

(ii) Cement Concrete M15 grade

As per item No.11.4 of Chapter 11 cum

(iii) Painting M.S. tube posts with primer and two


coats of epoxy paint as per specification

As per item No. 10.7 of chapter 10 sqm

a) Labour (fox fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

10 - 511
Sr. Reference to
Description Unit
No. MORD Spec
i) Support of MS Sheet tubes 47 mm x 47 mm x kg
12 SWG sheet 3050 mm long

ii) Angle iron 50 mm x 50 mm x 6 mm for lugs kg

iii) 2 mm thick MS Sheet strengthened by 25 mm x sqm


5 mm M.S. flat iron and painted with stove
enameled paint including lettering, signs,
messages, border with reflective tape of
engineering grade of required size, shade and
colour as per MORD specifications

Add 3% cost of MS sheet and angle iron


towards the cost of fabrications, drilling, holes,
nuts, bolts etc.

c) Machinery

Tractor with trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 1.5 sqm board = (i+ii+iii+a+b+c+d+e+f)

Rate per sqm = (i+ii+iii+a+b+c+d) / 1.5

Note: Rate for excavation cement concrete M15 and painting may be
taken from respective chapter

10.5 1700 Painting Two Coats on New Concrete Surfaces

Painting two coats including primer coat after filling the surface
with synthetic enamel paint in all shades on new, plastered /
concrete surfaces as per drawing and Technical Specification
Clause 1701

Unit = sqm

Taking output = 40 sqm

a) Labour

Mate day

Painter (1st Class) day

Mazdoor (Unskilled) day

b) Material

Cement Primer as per specifications litre

Paint conforming to requirement of Clause 1701.3.8 litre

10 - 512
Sr. Reference to
Description Unit
No. MORD Spec
Add for scaffolding @ 1 per cent of labour cost where
required

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 40 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d+e)/40

10.6 1700 Painting on Steel Surfaces

Providing and applying two coats of ready mix paint including


primer coat of approved brand on steel surface after through
cleaning of surface to give an even shade as per drawing and
Technical Specification Clause 1701

Unit = sqm

Taking output = 10 sqm

a) Labour

Mate day

Painter (1st Class) day

Mazdoor (Unskilled) day

b) Material

Red-oxide Primer as per specifications litre

Paint ready mixed approved brand litre

Add @ 1 per cent on cost of material for scaffolding


wherever required

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10 sqm = a+b+c+d+e

Rate per sqm = (a+b+c)/10

10.7 1700 Painting on Concrete/Steel Surfaces with Epoxy

Painting two coats including prime coat with epoxy paint of


approved brand on concrete/steel surfaces after through cleaning
of surface to give an even shade as per drawing and Technical
Specification Clause 1701

10 - 513
Sr. Reference to
Description Unit
No. MORD Spec
Unit = sqm

Taking output = 10 sqm

a) Labour

Mate day

Painter (1st Class) day

Mazdoor (Unskilled) day

b) Material

Epoxy primer/Red-oxide litre

Epoxy paint litre

Add @ 1 per cent on cost of material for scaffolding


wherever required

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10 sqm = (a+b+c+d+e)

Rate per sqm = (a+b+c+d+e)/10

10.8 1700 Painting lines, Dashes, Arrows, etc. on Road in Two Coats
on New Work

Painting lines, dashes, arrows, etc. on roads in two coats on new


work with ready mixed road marking paint conforming to IS:164
on bituminous/concrete surface, including cleaning the surface of
all dirt, dust and other foreign matter, demarcation at site and
traffic control as per drawing and Technical Specification Clause
1702

Assuming 100 mm width

Unit = sqm

Taking output = 10 sqm

a) Labour

Mate day

Painter 1st Class day

Mazdoor (Unskilled) day

b) Material

10 - 514
Sr. Reference to
Description Unit
No. MORD Spec
Road marking paint as per IS:164 litre

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d+e)/10

10.9 1700 Painting lines, Dashes, Arrows, etc. on Roads in Two Coats
on Old Work

Painting lines, dashes, arrows, etc. on roads in two coats on old


work with ready mixed road marking paint conforming to IS:164
on bituminous/concrete surface, including cleaning the surface of
all dirt, dust and other foreign matter, demarcation at site and
traffic control as per drawing and technical specification Clause
1702

Assuming 100 cm width

Unit = sqm

Taking output = 10 sqm

a) Labour

Mate day

Painter (Ist class) day

Mazdoor (Unskilled) day

b) Material

Road marking paint litre

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d+e)/10

10.10 1700 Kilometre Stone

Reinforced cement concrete M15 grade kilometre stone/local


stone of standard design as per IRC:8 fixing in position including
painting and printing, etc as per drawing and Technical
Specification Clause 1703

10 - 515
Sr. Reference to
Description Unit
No. MORD Spec
i) 5th Kilometre Stone (precast)

Unit = each

Taking output = 6 Nos.

a) M-15 grade of concrete

As per item No.12.5 of Chapter 12 cum

b) Steel reinforcement @ 5 kg per sqm

As per item No.12.6 of Chapter 12 kg

c) Excavation in soil for foundation

As per item No.11.1 of Chapter 11 cum

d) Painting two coats on concrete surface

As per item No.10.5 of Chapter 10 sqm

e) lettering on km post (average 30 letters of 10 cm


height each)

As per item No.10.1 of Chapter 10 per cm


high per
litre

Transportation and fixing

f) Labour

Mate day

Mason (1st Class) day

Mazdoor (Unskilled) day

g) Machinery

50 HP Tractor with trolley hour

h) Contractor’s profit & Overheads @ 12.5% on (f+g)

i) Add GST, LWC etc. @ 0 on (f+g)

Cost for 6 Nos. 5th km stone = a+b+c+d+e+f+g+h+I+j

Rate for each 5th km stone = (a+b+c+d+e+f+g+h+I+j)/6

ii) Ordinary Kilometer Stone (Precast)

Unit = each

10 - 516
Sr. Reference to
Description Unit
No. MORD Spec
Taking output = 14 Nos.

a) M15 grade of concrete

As per item No.12.5 of Chapter 12 cum

b) Steel reinforcement @ 5 kg per sqm

As per item No.12.6 of Chapter 12 kg

c) Excavation in soil for foundation

As per item No.11.1 of Chapter 11 cum

d) Painting two coats on concrete surface

As per item No.10.5 of Chapter 10 sqm

e) lettering on km post (average 12 letters of 10 cm


height each)

As per item No.10.1 of Chapter 10 per cm


high per
letter

Transportation and fixing

f) Labour

Mate day

Mason (1st Class) day

Mazdoor (Unskilled) day

g) Machinery

50 HP Tractor with trolley hour

h) Contractor’s profit & Overheads @ 12.5% on (f+g)

i) Add GST, LWC etc. @ 0 on (f+g)

Cost for 14 Nos. ordinary km stone =


(a+b+c+d+e+f+g+h+I+j)

Rate for each ordinary km stone =


(a+b+c+d+e+f+g+h+I+j)/14

iii) 200 m stone (precast)

Unit = each

Taking output = 33 Nos.

10 - 517
Sr. Reference to
Description Unit
No. MORD Spec
a) M15 grade of concrete

As per item No.12.5 of Chapter 12 cum

b) Steel reinforcement @ 5 kg per sqm

As per item No.12.6 of Chapter 12 kg

c) Excavation in soil for foundation

As per item No.11.1 of Chapter 11 cum

d) Painting two coats on concrete surface

As per item No.10.5 of Chapter 10 sqm

e) lettering on km post (average 1 letter of 10 cm height


each)

As per item No. 10.1 of Chapter 10 per cm


per
Transportation and fixing litreetter

f) Labour

Mate day

Mason (1st Class) day

Mazdoor (Unskilled) day

g) Machinery

50 HP Tractor with trolley hour

h) Contractor’s profit & Overheads @ 12.5% on (f+g)

i) Add GST, LWC etc. @ 0 on (f+g)

Cost for 33 Nos. 200 m stone = (a+b+c+d+e+f+g+h+I+j)

Rate for each 200 m stone = (a+b+c+d+e+f+g+h+I+j)/33

Note: 1 The rate for excavation, cement concrete, steel


reinforcement, painting and lettering may be taken from
respective Chapters.

2 In case local stone is to be used in place of precast RCC


stones, then rate of cement concrete and steel
reinforcement may be deleted.

10.11 1700 Boundary Pillar

10 - 518
Sr. Reference to
Description Unit
No. MORD Spec
Reinforced cement concrete M15 grade boundary pillars/local
stone of standard design as per IRC:25, fixed in position
including finishing and lettering but excluding painting as per
drawing and Technical Specification Clause 1704

Unit = each

Taking output = 57 Nos.

a) M-15 grade of Concrete

As per Item No. 12.5 of Chapter 12 cum

b) Steel reinforcement

As per Item No. 12.6 of Chapter 12 kg

c) Excavation in soil

As per Item No. 11.1 of Chapter 11 cum

d) lettering, each 10 cm high

As per Item No. 10.1 of Chapter 10 per litre


per cm
high

Transportation and fixing

e) Labour

Mate day

Mazdoor (Unskilled) day

f) Machinery

Tractor with trolley hour

g) Material

Stone spall cum

h) Contractor’s profit & Overheads @ 12.5% on (e+f+g)

i) Add GST, LWC etc. @ 0 on (e+f+g)

Cost for 57 Nos. boundary pillar = a+b+c+d+e+f+g+h+I+j

Rate for each boundary pillar = (a+b+c+d+e+f+g+h+I+j)/57

10 - 519
Sr. Reference to
Description Unit
No. MORD Spec
Note: 1 In case of soft ground, a proper foundation may be
provided as per approved design. In case foundation is
required to be provided, the items of excavation and
foundation concrete are required to be measured and paid
separately.

2 In case local stone is to be used in place of precast RCC


stones, then rate of cement concrete and steel
reinforcement may be deleted.

10.12 1700, 800 & 300 G.I Barbed Wire Fencing 1.2 m high

Providing and fixing 1.2 m high GI barbed wire fencing with 1.8 m
RCC posts 150 mm x 150 mm placed every 3 m centre-to-centre
founded in M15 grade cement concrete, 0.6 m below ground
level, every 15th post, last but one end post and corner post shall
be strutted on both sides and end post on one side only and
provided with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc. complete
as per Clause 1705.

Unit = per running m

Taking output = 30 m

a) R.C.C. Post 150 mm x 150 mm x 1.80 m

i) M15 Grade concrete

13 x 150 mm x 150 mm x 1.8 m

Rate as per item No.12.5 of Chapter 12 cum

Add 5 per cent extra cost for formwork of M-15

ii) Supply of HYSD Bars including cutting, bending, tying &


placing in position.

10 mm dia HYSD bars for posts

13 x 4 x 1.8 = 93.6 m @ 0.62 kg/mt = 43.60 kg

8 mm dia HYSD bars for rings

13 x 10 x 0.6 = 78 m @ 0.39 kg/mt = 30.42 kg

Total 74.02 kg

As per item No.12.6 of Chapter 12 t

b) Labour

Mate day

Blacksmith day

Mazdoor (Unskilled) day

10 - 520
Sr. Reference to
Description Unit
No. MORD Spec
c) Material

Barbed wire 335 m length @ 9.38 kg per 100 m kg

Add for GI staple binding wire, drilling holes, etc. @ 2 per


cent of the cost of material

d) Painting

Applying two coats of painting including primer coat on


exposed surface of RCC posts

As per item No.10.5 of this Chapter sqm

e) Contractor’s profit & Overheads @ 12.5% on (b+c+d)

f) Add GST, LWC etc. @ 0 on (b+c+d)

Cost for 30 m fencing = a+b+c+d+e+f

Rate per m = (a+b+c+d+e+f)/30

Note: Cost of excavation for foundation and foundation concrete to be


added separately in the cost estimate as per approved design.
The rate for these items may be taken from respective Chapters.

10.13 1700, 800 & 300 G.I Barbed Wire Fencing 1.8 m high

Providing and fixing 1.8 m high GI barbed wire fencing with 2.4 m
RCC M15 grade 150 mm x 150 mm concrete post placed every 3
m centre-to-centre founded in M15 grade cement concrete, 0.6 m
below ground level, every 15th post, last but one end post and
corner post shall be strutted on both sides and end post on one
side only and provided with 12 horizontal lines and 2 diagonals
interwoven with horizontal wires, fixed with GI staples, turn
buckles etc. complete as per Clause 1705.

Unit = per running m

Taking output = 30 m

a) R.C.C. Post 150 mm x 150 mm x 2.4 m

i) High M-15 Grade

13 x 150 mm x 150 mm x 2.4 m

As per item No.12.5 of Chapter 12 cum

Add 5 per cent extra cost of C.C. for formwork of M-15

ii) Supply of HYSD Bars including cutting, bending, tying &


placing in position.

10 - 521
Sr. Reference to
Description Unit
No. MORD Spec
10 mm dia HYSD bars for posts

13 x 4 x 2.4 = 124.80 m

@ 0.62 kg/mt = 77.38 kg

8 mm dia HYSD bars for rings

13 x 11 x 0.6 = 85.80 m

@ 0.39 kg/m = 33.46 kg

Total 110.84 kg

As per item No.12.6 of Chapter 12 t

b) Labour

Mate day

Blacksmith day

Mazdoor (Unskilled) day

c) Material

Barbed wire 428 m length @ 9.38 kg per 100 m kg

Add for GI staple, binding wire, drilling holes etc. @ 2 per


cent of the cost of material

d) Painting

Applying two coats of painting including prime coat on


exposed surface of RCC posts

As per item No.10.5 of this Chapter sqm

e) Contractor’s profit & Overheads @ 12.5% on (b+c+d)

f) Add GST, LWC etc. @ 0 on (b+c+d)

Cost for 30 m fencing = a+b+c+d+e+f

Rate per m fencing = (a+b+c+d)/30

Note: Cost of excavation for foundation and foundation concrete to be


added separately in the cost estimate as per approved design.
The rate for these items may be taken from respective Chapters.

10.14 1700, 800 &300 Tubular Steel Railing on Medium Weight Steel Channel (ISMC
series) 100 mm x 50 mm

10 - 522
Sr. Reference to
Description Unit
No. MORD Spec
Providing, fixing and erecting 50 mm dia steel pipe railing in 3
rows duly painted on medium weight steel channels (ISMC
series) 100 mm x 50 mm, 1.2 m high above ground, 2 m centre-
to-centre, complete as per approved drawings Clause 1706

Unit = Running m

Taking output = 10 m

i) Excavation for foundation (6 Nos.) 6 x 0.6 x 0.6 x 0.6

As per item No.11.1 of Chapter 11 cum

ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 0.6 x 0.3

As per item No. 11.4 of Chapter 11 cum

iii) Painting of pipe

As per item No.10.6 of this Chapter sqm

iv) Painting of channel section (6 nos.)


1.8 m each 0.2 x 1.8 x 1.6 = 2.16

As per item No.10.6 of this Chapter sqm

a) labour (For fixing at site)

Mate day

Mazdoor (Unskilled) day

Plumber day

b) Material

Steel pipe 50 mm external dia as per IS:1239 m

Medium weight steel channel (ISMC series) 100 mm x kg


50 mm, 10.8 m length @ 9.2 kg per m including 5 per
cent wastage

Add for drilling holes @ 3 per cent of cost of channels

c) Machinery

50 HP Tractor with trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 10 m = a+b+c+d+e+f

10 - 523
Sr. Reference to
Description Unit
No. MORD Spec
Rate per m = (a+b+c+d+e+f)/10

10.15 1700, 800 & 300 Tubular Steel Railing on Precast RCC posts, 1.2 m high
above Ground Level

Providing, fencing and erecting 50 mm dia painted steel pipe


railing in 3 rows on precast M-20 grade RCC vertical posts 175
mm x 175 mm x 1.8 m high (1.2 m above Gl) with 3 holes 50 mm
dia for pipe, fixed 2 m centre-to- centre complete as per
approved drawings Clause 1706

Unit = Running m

Taking output = 10 m

i) Excavation for foundation (6 Nos.) 6 x 0.6 x 0.6 x 0.6

As per item No.11.1 of Chapter 11 cum

ii) Foundation concrete M15 grade PCC 6 x 0.6 x 0.6 x 0.3

As per item No. 11.4 of Chapter 11 cum

iii) RCC M20 for precast posts (6 nos.) of 1.8 m each

As per item No.12.5 of Chapter 12 sqm

iv) Painting of pipe

As per item No.10.6 of this Chapter sqm

a) Labour

Mate day

Mazdoor (Unskilled) day

Plumber day

b) Material

Steel pipe 50 mm dia as per IS:1239 m

HYSD steel bars as per item No.12.6 of Chapter 12 t

c) Machinery

50 HP Tractor with trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

10 - 524
Sr. Reference to
Description Unit
No. MORD Spec
Cost for 10 m = a+b+c+d

Rate per m = (a+b+c+d)/10

10.16 1700 Providing and Fixing 'Logo' of PMGSY Project

Providing and fixing of typical PMGSY informatory sign board


with Logo as per MORD specifications and drawing. Three MS
Plates of 1.6 mm thick, top and middle plate duly welded with MS
flat iron 25mm x 5m size on back on edges. The lower plate will
be welded with MS angle iron frame of 25mm x 25mm x 5mm.
The angle iron frame of the lower most plate and flat iron frame
of middle plate will be welded to 2 nos. 75mm x 75 mm of 12
SWG sheet tubes posts duly embedded in cement concrete M-15
grade blocks of 450mm x 450mm x 600mm, 600mm below
ground level. The top most diamond plate will be welded to
middle plate by 47mm x 47mm of 12 SWG steel plate tube. All
M.S. will be stove enameled on both sides. Lettering and printing
arrows, border etc. will be painted with ready mixed synthetic
enamel paint of superior quality in required shade and colour. All
sections of framed posts and steel tube will be painted with
primer and two coats of epoxy paint as per drawing Clause 1701
and Annexure 1700.1

Unit = Each

Taking out put = one typical board

(i) Excavation for foundations

As per item No. 11.1 of Chapter 11 cum

(ii) Cement Concrete M15 grade

As per item No. 11.4 of Chapter 11 cum

(iii) Painting on MS Steel tubes with primer and two coats


of epoxy paint

2x2.05x.30 = 1.23

1x1.10x188 = 0.21

As per item no. 10.7 of Chapter 10 sqm

iv) Printing new letters and figures of any shade with


synthetic enamel paint black or any other approved
colour to give an even shade.

Logo Border 60x4x5 = 1200 per cm height per letter

Figure 60x10 = 600 per cm height per letter

Middle plate words 28x5 = 140 per cm height per letter

Bottom plate border 150x2x5 = 1500 per cm height per letter

10 - 525
Sr. Reference to
Description Unit
No. MORD Spec
Bottom plate border 60x2x5 = 600 per cm height per letter

Words 101x2.5 = 252.5

Words 80x3 = 240.00

Total 4532.5 per cm height per letter

As per item No.10.1 of Chapter 10 per cm


height
per litre

a) Labour (for fixing at site)

Mate day

Mazdoor (Unskilled) day

b) Material

2 nos. MS tubes 75mx75mm of 12 SWG sheet 2650 kg


mm long

1 No. MS tube 47mm x 47mm of 12 SWG 1100 mm kg


long

Angle iron 50mm x 50mm x 5 mm for lugs kg

1.6 mm thick MS sheet strengthened by 25mm x 5 MS sqm


flat iron on logo and middle plate angle iron 25mm x
25mm x 5mm on bottom plate painting with stove
enameled paint on both sides as per MORD
specifications

Add 3% cost of MS tube and angle iron towards the


cost of fabrications, drilling holes, nuts, bolts, etc.

c) Machinery

Tractor with trolley hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for one Board= (i+ii+iii+iv+a+b+c+d)

Note: Printing and lettering for blank spaces on the lower plate will be
written as required and paid seperately.

10.17 Suggestive Traffic Cone

10 - 526
Sr. Reference to
Description Unit
No. MORD Spec
Provision of red fluorescent with white reflective sleeve traffic
cone made of Low Density Polyethylene (LDPE) material with a
square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg
in weight, placed at 1.5 m interval, all as per BS:873

Unit = Each

Taking output = 68 Nos.

a) Labour

Mate day

Mazdoor (Unskilled) day

b) Material

Traffic cones with 150 mm reflective sleeve Nos.

c) Machinery

50 HP Tractor with trolley Hour

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 68 Nos. = a+b+c+d+e+f

Rate for each cone = (a+b+c+d+e+f)/68

10.18 Suggestive Rumble Strips

Provision of 15 nos. rumble strips covered with premix


bituminous carpet, 15-20 mm high at centre, 250 mm wide
placed at 1 m centre-to-centre at approved locations to control
speed, marked with white strips of road marking paint.

Unit = sqm

Taking output = 100 sqm (including gaps)

The rate per sqm of premix carpet and road marking may be
adopted from Chapters 5 & 10 respectively for the quantities
calculated from approved drawings.

10.19 Suggestive Safety Devices and Signs in Construction Zones

10 - 527
Sr. Reference to
Description Unit
No. MORD Spec
Provision and fixing of traffic signs for limited period at suitable
locations in construction zone comprising of warning zone,
approach transition zone, working zone and terminal transition
zone with a minimum distance of 2-3 m from the edge of the
carriageway. The bottom edge of the lowest sign plate to be not
less than 2 m above the road level, fixed on 600 mm x 600 mm x
6 mm angle iron post, founded and installed as per approved
design and drawings, removed and disposed of after completion
of construction work, all as per IRC:SP:55-2001.

Unit = each

Taking output = one sign post

Following types of signs are required to be fixed in construction


zones for safety of traffic:

a) Diversion one km ahead

b) Traffic sign ahead

c) Road ahead closed

d) Men at work

e) Road narrow

f) Un-even road

g) Slippery road

h) Loose chippings

i) Diversion

j) Do not enter

k) Road closed

l) Stop

m) Slow

n) Speed limit

Note: The rate for traffic signs are already worked out and given
elsewhere in this Chapter. The same may be adopted.

10.20 Suggestive Road Markers/Road Stud with Lens Reflector

Providing and fixing of road stud 100 x 100 mm die cast in


aluminium, resistant to corrosive effect of salt and grit, fitted with
lense reflectors, installed in concrete or asphaltic surface by
drilling holes 30 mm upto a depth of 600 mm and bedded in a
suitable bituminous grout or epoxy mortar, all as per BS:873 (Part
4) 1973.

10 - 528
Sr. Reference to
Description Unit
No. MORD Spec
Unit = each

Taking output = 50 Nos.

(a) Labour

Mate day

Mazdoor (Unskilled) day

(b) Material

Aluminium studs 100x100 mm fitted with lense reflectors Nos.

Add 10 per cent of cost of material for fixing and installation.

c) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

d) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 50 studs = a+b+c+d+e

Rate per stud = (a+b+c+d+e)/50

10 - 529
Chapter 10

ARKINGS AND OTHER ROAD APPURTENANCES


Rate
Quantity Amount (Rs.)
(Rs.)

0.12 356.65 42.80

2.00 458.55 917.10

1.00 244.56 244.56

0.40 250.00 100.00

163.06

0.00

1,467.52

0.92

0.07 356.65 24.97

1.25 458.55 573.19

0.50 244.56 122.28

10 - 530
Rate
Quantity Amount (Rs.)
(Rs.)

0.50 250.00 125.00

105.68

0.00

951.11

0.59

0.126 102.00 12.85

0.126 5,085.61 640.79

0.887 121.47 107.74

0.01 356.65 3.57

0.25 244.56 61.14

20.00 60.00 1,200.00

10 - 531
Rate
Quantity Amount (Rs.)
(Rs.)

36.00

0.35 8,330.00 2,915.50

0.156 8,330.00 1,299.48

0.283 8,330.00 2,357.39

0.48 8,330.00 3,998.40

0.27 8,330.00 2,249.10

0.36 8,330.00 2,998.80

0.672 8,330.00 5,597.76

0.08 409.00 32.72

r’s profit & Overheads @ 12.5% on (a+b i+c) 531.12

0.00

5,541.43

r’s profit & Overheads @ 12.5% on (a+b ii+c) 329.11

10 - 532
Rate
Quantity Amount (Rs.)
(Rs.)
0.00

3,723.40

r’s profit & Overheads @ 12.5% on (a+b iii+c) 461.35

0.00

4,913.55

r’s profit & Overheads @ 12.5% on (a+b iv+c) 666.48

0.00

6,759.69

r’s profit & Overheads @ 12.5% on (a+b v+c) 447.82

0.00

4,791.73

r’s profit & Overheads @ 12.5% on (a+b vi+c) 541.53

0.00

5,635.14

10 - 533
Rate
Quantity Amount (Rs.)
(Rs.)

r’s profit & Overheads @ 12.5% on (a+b vii+c) 866.40

0.00

8,558.97

0.126 102.00 12.85

0.126 5,085.61 640.79

0.01 356.65 3.57

0.25 244.56 61.14

3.00 450.00 1,350.00

40.50

0.35 8,330.00 2,915.50

10 - 534
Rate
Quantity Amount (Rs.)
(Rs.)
0.156 8,330.00 1,299.48

0.283 8,330.00 2,357.39

0.48 8,330.00 3,998.40

0.27 8,330.00 2,249.10

0.36 8,330.00 2,998.80

0.772 8,330.00 6,430.76

0.08 409.00 32.72

r’s profit & Overheads @ 12.5% on (a+b i+c) 550.43

0.00

5,607.49

r’s profit & Overheads @ 12.5% on (a+b ii+c) 348.43

0.00

3,789.47

r’s profit & Overheads @ 12.5% on (a+b iii+c) 480.66

10 - 535
Rate
Quantity Amount (Rs.)
(Rs.)
0.00

4,979.62

r’s profit & Overheads @ 12.5% on (a+b iv+c) 685.79

0.00

6,825.76

r’s profit & Overheads @ 12.5% on (a+b v+c) 467.13

0.00

4,857.79

r’s profit & Overheads @ 12.5% on (a+b vi+c) 560.84

0.00

5,701.21

r’s profit & Overheads @ 12.5% on (a+b vii+c) 989.84

0.00

9,562.16

10 - 536
Rate
Quantity Amount (Rs.)
(Rs.)

0.126 102.00 12.85

0.126 5,085.61 640.79

0.0285 5,379.01 153.30

0.0077 55,090.98 424.20

0.90 121.47 109.32

0.01 356.65 3.57

0.25 244.56 61.14

22.55

0.35 8,330.00 2,915.50

0.156 8,330.00 1,299.48

10 - 537
Rate
Quantity Amount (Rs.)
(Rs.)

0.283 8,330.00 2,357.39

0.48 8,330.00 3,998.40

0.27 8,330.00 2,249.10

0.36 8,330.00 2,998.80

0.672 8,330.00 5,597.76

0.08 409.00 32.72

r’s profit & Overheads @ 12.5% on (a+b i+c) 379.43

0.00

4,755.37

r’s profit & Overheads @ 12.5% on (a+b ii+c) 177.43

0.00

2,937.35

r’s profit & Overheads @ 12.5% on (a+b iii+c) 309.67

0.00

10 - 538
Rate
Quantity Amount (Rs.)
(Rs.)

4,127.50

r’s profit & Overheads @ 12.5% on (a+b iv+c) 514.80

0.00

5,973.63

r’s profit & Overheads @ 12.5% on (a+b v+c) 296.13

0.00

4,005.67

r’s profit & Overheads @ 12.5% on (a+b vi+c) 389.85

0.00

4,849.08

r’s profit & Overheads @ 12.5% on (a+b vii+c) 714.72

0.00

7,772.91

10 - 539
Rate
Quantity Amount (Rs.)
(Rs.)

0.126 102.00 12.85

0.126 5,085.61 461.03

0.46 121.47 55.88

0.01 356.65 3.57

0.25 244.56 61.14

10 - 540
Rate
Quantity Amount (Rs.)
(Rs.)
12.40 83.00 1,029.20

1.06 60.00 63.60

32.78

0.35 5,992.00 2,097.20

0.156 5,992.00 934.75

0.283 5,992.00 1,695.74

0.48 5,992.00 2,876.16

0.27 5,992.00 1,617.84

0.36 5,992.00 2,157.12

0.772 5,992.00 4,625.82

0.08 409.00 32.72

r’s profit & Overheads @ 12.5% on (a+b i+c) 415.03

0.00

10 - 541
Rate
Quantity Amount (Rs.)
(Rs.)
4,264.99

r’s profit & Overheads @ 12.5% on (a+b ii+c) 269.72

0.00

2,957.24

r’s profit & Overheads @ 12.5% on (a+b iii+c) 364.84

0.00

3,813.35

r’s profit & Overheads @ 12.5% on (a+b iv+c) 512.40

0.00

5,141.32

r’s profit & Overheads @ 12.5% on (a+b v+c) 355.11

0.00

3,725.71

r’s profit & Overheads @ 12.5% on (a+b vi+c) 422.52

10 - 542
Rate
Quantity Amount (Rs.)
(Rs.)
0.00

4,332.40

r’s profit & Overheads @ 12.5% on (a+b vii+c) 731.10

0.00

7,109.70

0.126 102.00 12.85

10 - 543
Rate
Quantity Amount (Rs.)
(Rs.)

0.126 5,085.61 640.79

0.887 121.47 107.74

0.01 356.65 3.57

0.25 244.56 61.14

20.00 60.00 1,200.00

0.90 8,330.00 7,497.00

260.91

0.08 409.00 32.72

1,131.92

0.00

10,948.64

12,165.15

10 - 544
Rate
Quantity Amount (Rs.)
(Rs.)

0.126 102.00 12.85

0.126 5,085.61 640.79

0.01 356.65 3.57

0.25 244.56 61.14

3.00 450.00 1,350.00

0.90 8,330.00 7,497.00

40.50

0.08 409.00 32.72

1,123.12

0.00

10,108.04

11,231.16

10 - 545
Rate
Quantity Amount (Rs.)
(Rs.)
0.126 102.00 12.85

0.126 5,109.14 643.75

0.0285 5,379.01 153.30

0.0077 55,090.98 424.20

0.90 121.47 109.32

0.01 356.65 3.57

0.25 244.56 61.14

0.90 8,330.00 7,497.00

0.08 409.00 32.72

949.30

0.00

9,887.16

10,985.73

10 - 546
Rate
Quantity Amount (Rs.)
(Rs.)

0.126 102.00 12.85

0.126 5,085.61 640.79

0.59 121.47 71.67

0.01 356.65 3.57

0.25 244.56 61.14

10 - 547
Rate
Quantity Amount (Rs.)
(Rs.)

12.40 40.00 496.00

1.06 60.00 63.60

0.90 5,992.00 5,392.80

178.57

0.08 409.00 32.72

778.55

0.00

7,732.25

8,591.39

10 - 548
Rate
Quantity Amount (Rs.)
(Rs.)
0.252 102.00 25.70

0.252 5,085.61 1,281.57

1.774 121.47 215.49

0.02 356.65 7.13

0.50 244.56 122.28

40.00 60.00 2,400.00

1.50 8,330.00 12,495.00

446.85

0.12 409.00 49.08

1,940.04

0.00

18,983.15

12,655.43

10 - 549
Rate
Quantity Amount (Rs.)
(Rs.)

0.252 102.00 25.70

0.252 5,085.61 1,281.57

0.02 356.65 7.13

0.50 244.56 122.28

6.00 450.00 2,700.00

1.50 8,339.00 12,508.50

456.26

0.12 409.00 49.08

1,980.41

0.00

19,130.93

12,753.96

10 - 550
Rate
Quantity Amount (Rs.)
(Rs.)

0.252 102.00 25.70

0.252 5,085.61 1,281.57

0.057 5,379.01 306.60

0.0154 55,090.98 848.40

1.84 121.47 223.50

0.02 356.65 7.13

0.50 244.56 122.28

1.50 8,330.00 12,495.00

9.20

0.12 409.00 49.08

1,585.34

0.00

16,953.82

11,302.54

10 - 551
Rate
Quantity Amount (Rs.)
(Rs.)

0.252 102.00 25.70

0.252 5,085.61 1,281.57

0.92 121.47 111.75

0.02 356.65 7.13

0.50 244.56 122.28

10 - 552
Rate
Quantity Amount (Rs.)
(Rs.)
24.80 83.00 2,058.40

2.12 60.00 127.20

1.50 5,992.00 8,988.00

335.21

0.16 409.00 65.44

1,462.96

0.00

14,585.65

9,723.77

0.12 356.65 42.80

2.50 458.55 1,146.38

1.00 244.56 244.56

100.00 0.00

6.00 146.00 876.00

10 - 553
Rate
Quantity Amount (Rs.)
(Rs.)
14.34

290.51

0.00

2,614.58

65.36

0.25 356.65 89.16

0.20 458.55 91.71

0.40 244.56 97.82

165.00 0.00

1.25 250.00 312.50

3.13

74.29

0.00

668.61

66.86

10 - 554
Rate
Quantity Amount (Rs.)
(Rs.)

0.25 356.65 89.16

0.60 458.55 275.13

0.40 244.56 97.82

0.60 165.00 99.00

1.25 410.00 512.50

6.12

134.97

0.00

1,214.70

121.47

0.07 356.65 24.97

0.35 458.55 160.49

1.55 244.56 379.07

10 - 555
Rate
Quantity Amount (Rs.)
(Rs.)
1.48 90.00 133.20

87.22

0.00

784.94

78.49

0.06 356.65 21.40

0.30 458.55 137.57

1.25 244.56 305.70

0.90 90.00 81.00

68.21

0.00

613.87

61.39

10 - 556
Rate
Quantity Amount (Rs.)
(Rs.)

2.35 5,379.01 12,640.68

22.08 55.09 1,216.41

1.68 102.00 171.36

9.85 65.36 643.84

1,800.00 0.92 1,650.95

0.26 356.65 92.73

0.60 458.55 275.13

6.00 244.56 1,467.36

6.00 409.00 2,454.00

536.15

0.00

21,148.62

3,524.77

10 - 557
Rate
Quantity Amount (Rs.)
(Rs.)

3.77 5,379.01 20,278.88

26.32 55.09 1,449.99

2.77 102.00 282.54

11.41 65.36 745.81

1,680.00 0.92 1,540.89

0.32 356.65 114.13

1.00 458.55 458.55

7.00 244.56 1,711.92

6.00 409.00 2,454.00

592.32

0.00

29,629.04

2,116.36

10 - 558
Rate
Quantity Amount (Rs.)
(Rs.)

1.58 5,379.01 8,498.84

66.00 55.09 3,636.00

1.39 102.00 141.78

6.27 65.36 409.84

330.00 0.92 302.68

0.34 356.65 121.26

1.50 458.55 687.83

7.00 244.56 1,711.92

6.00 409.00 2,454.00

621.88

0.00

18,586.02

563.21

10 - 559
Rate
Quantity Amount (Rs.)
(Rs.)

1.25 5,379.01 6,723.77

79.80 55.09 4,396.26

10.72 102.00 1,093.44

2,280.00 0.92 2,091.21

0.57 356.65 203.29

14.25 244.56 3,484.98

6.00 409.00 2,454.00

11.97 987.00 11,814.39

2,244.58

0.00

34,505.92

605.37

10 - 560
Rate
Quantity Amount (Rs.)
(Rs.)

0.526 5,379.01 2,829.36

141.47

0.004 55,090.98 220.36

0.09 356.65 32.10

0.25 458.55 114.64

2.00 244.56 489.12

10 - 561
Rate
Quantity Amount (Rs.)
(Rs.)

31.42 78.00 2,450.76

49.02

8.14 65.36 532.07

458.46

0.00

7,317.35

243.91

0.702 5,379.01 3,776.07

188.80

10 - 562
Rate
Quantity Amount (Rs.)
(Rs.)

0.050 55,090.98 2,754.55

0.12 356.65 42.80

0.40 458.55 183.42

2.50 244.56 611.40

40.15 78.00 3,131.70

62.63

12.10 65.36 790.91

602.86

0.00

12,145.14

404.84

10 - 563
Rate
Quantity Amount (Rs.)
(Rs.)

1.296 102.000 132.19

0.648 5,109.143 3,310.72

4.71 66.861 314.92

2.16 66.861 144.42

0.01 356.65 3.57

0.25 244.56 61.14

0.01 458.55 4.59

30.00 131.00 3,930.00

104.33 60.00 6,259.80

305.69

0.06 409.00 24.54

1,323.67

0.00

15,815.24

10 - 564
Rate
Quantity Amount (Rs.)
(Rs.)
1,581.52

1.296 102.000 132.19

0.648 5,109.143 3,310.72

0.33 Err:509 Err:509

4.71 66.861 314.92

0.014 356.65 4.99

0.35 244.56 85.60

0.01 458.55 4.59

30.00 127.00 3,810.00

0.020 55,090.98 1,101.82

0.25 409.00 102.25

638.66

0.00

10 - 565
Rate
Quantity Amount (Rs.)
(Rs.)
Err:509

Err:509

0.252 102.000 25.70

0.252 5,109.143 1,287.50

1.80 121.47 218.65

10 - 566
Rate
Quantity Amount (Rs.)
(Rs.)

4,532.50 0.92 4,157.20

0.03 356.65 10.70

0.75 244.56 183.42

63.15 83.00 5,241.45

4.47 83.00 371.01

2.12 35.15 74.52

1.44 5,304.00 7,637.76

399.74

0.24 409.00 98.16

1,752.09

0.00

21,457.90

10 - 567
Rate
Quantity Amount (Rs.)
(Rs.)

0.02 356.65 7.13

0.50 244.56 122.28

66.00 1,229.00 81,114.00

0.10 409.00 40.90

10,160.54

0.00

91,444.85

1,344.78

10 - 568
Rate
Quantity Amount (Rs.)
(Rs.)

10 - 569
Rate
Quantity Amount (Rs.)
(Rs.)

0.04 356.65 14.27

1.00 244.56 244.56

50.00 438.00 21,900.00

2,190.00

3,043.60

0.00

27,392.43

547.85

10 - 570
Chapter 11

FOUNDATION
Sr. Reference to
Description Unit Quantity
No. MORD Spec
11.1 300 Excavation for Structures

Earthwork in excavation for structures as per drawing and technical


specifications Clause 305.1 including setting out, construction of
shoring and bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50 m, dressing of sides and
bottom and backfilling in trenches with excavated suitable material.

I. Ordinary soil

(i) Upto 3 m depth

Unit = cum

Taking output = 10 cum

a) Labour

Mate day 0.32

Mazdoor (Unskilled) day 3.00

b) Contractor’s profit & Overheads @ 20% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 cum = a+b+c+d

Rate per cum = (a+b+c+d)/10

Note: 1 Cost of dewatering may be added, where required, up to 10


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions.

2 The cost of shoring and shuttering, where needed, may be


added @ 3 per cent on cost of excavation for open foundation.

3 The excavated earth if found suitable, can be used partly for


backfilling in trenches & partly for road work. Hence cost of
disposal has not been added except for marshy soil. This
note is common to all cases of item 11.1 excluding 11.1 V

(ii) 3 m to 6 m depth

Unit = cum

a) Labour

11 - 571
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mate day 0.38

Mazdoor (Unskilled) day 4.50

b) Contractor’s profit & Overheads @ 20% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 cum = a+b+c+d

Rate per cum = (a+b+c+d)/10

Note: 1 Cost of dewatering may be added, when needed, up to 15 per


cent of labour cost.

2 Cost of shoring and shuttering, where needed, may be taken


@ 10 per cent on cost of excavation for open foundation.

II. Ordinary rock (not requiring blasting)

Upto 3 m depth

Unit = cum

Taking output = 10 cum

a) Labour

Mate day 0.40

Mazdoor (Unskilled) day 5.00

b) Contractor’s profit & Overheads @ 20% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 cum = a+b+c+d

Rate per cum = (a+b+c+d)/10

Note: Cost of dewatering upto 10 per cent of labour cost may be added,
where required as per site condition.

III. Hard rock (requiring blasting)

Upto 3 m depth including 1.5 m depth in hard rock

Unit = cum

Taking output = 10 cum

a) Labour

11 - 572
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mate day 0.53

Driller day 0.84

Blaster day 0.40

Mazdoor (Unskilled) day 6.50

b) Machinery

Air compressor 210 cfm with 2 jack hammers for drilling hour 1.00

c) Material

Gelatin 80% kg 3.50

Detonator electric Nos. 12.00

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 10 cum = a+b+c+d+e+f

Rate per cum = (a+b+c+d+e+f)/10

Note: Cost of dewatering @ 10 per cent of (a+b) may be added, where


required as per site condition.

IV. Hard rock (blasting prohibited)

Upto 3 m depth including 1.5 m depth in hard rock

Unit = cum

Taking output = 10 cum

a) Labour

Mate day 0.20

Mazdoor (Unskilled) day 4.00

b) Machinery

Air compressor 210 cfm with 2 jack hammers of hour 5.00


pneumatic breaker

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

11 - 573
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Cost for 10 cum = a+b+c+d+e

Rate per cum = a+b+c+d+e/10

Note: Cost of dewatering up to 10 per cent of (a+b) may be added, where


required as per site conditions.

V. Marshy soil

Unit = cum

Taking output = 10 cum

a) Labour

Mate day 0.60

Mazdoor (Unskilled) day 15.00

b) Contractor’s profit & Overheads @ 20% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 cum = a+b+c+d

Rate per cum = (a+b+c+d)/10

Note: 1 Cost of dewatering @ 30 per cent of (a) may be added.

2 Shoring and shuttering @ 15 per cent of (a) may be added


where required.

3 Since marshy soil cannot be used in filling in trenches, it shall


be removed and replaced by approved quality of soil. The
labour cost includes labour input for disposal of marshy soil
from excavated pit with a lead upto 50 m lead.

4 Marshy soil is generaly available upto 3 m depth. The rate


has, therefore, been done upto 3 m depth of excavation. For
deeper excavation refer analysis in item 11.1.

11.2 300 & 1200 Fillling in foundation trenches as per drawing and technical
specification Clause 305.3.9

I. Sand filling

Unit = cum

a) Labour

Mate day 0.01

Mazdoor (Unskilled) day 1.30

11 - 574
Sr. Reference to
Description Unit Quantity
No. MORD Spec
b) Material

Sand (assuming 20 per cent voids) cum 0.90

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

II. Earth filling (For marshy soil)

Unit = cum

Taking output = 6 cum

a) Labour

Mate day 0.20

Mazdoor (Unskilled) day 3.00

b) Contractor’s profit & Overheads @ 20% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 6 cum = a+b+c+d

Rate per cum = (a+b+c+d)/6

Note: 1 Cost of transportation of good quality earth has not been


included. Only labour for carrying carted earth with a lead of
50 m to the foundation pits has been taken in the rate. The
cost of carted earth may be worked out separately if the same
is not available from the adjoining area.

2 Backfilling of foundation trenches shall normally be done with


excavated earth. The cost of this operation is included in item
11.1. Only in case the excavated earth is not of suitable
quality, sand filling or backfilling with carted earth may be
resorted to

11.3 300 & 1200 Filling annular space around footing in rock as per technical
specification Clause 1203.4.3.

Unit = cum

P.C.C grade M 15

Nominal mix 1:2.5:5

11 - 575
Sr. Reference to
Description Unit Quantity
No. MORD Spec
A With crushed Stone

Unit = cum

a) Material

Cement t 0.265

Coarse sand cum 0.48

40 mm aggregate cum 0.38

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 4% on (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

B With natural Gravel

Unit = cum

a) Material

Cement t 0.265

Coarse sand cum 0.48

40 mm aggregate cum 0.38

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.09

11 - 576
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 4% on (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

11.4 800 & 1200 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203

I. P.C.C grade M 10

A With crushed Stone

(i) Nominal mix 1:3:6


Unit = cum

a) Material

Cement t 0.250

Coarse sand cum 0.48

40 mm aggregate cum 0.576

20 mm aggregate cum 0.288

10 mm aggregate cum 0.096


b) Labour

Mate day 0.08

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Mechnical concrete mixer 0.4/0.28 cum capacity hour 0.40


fitted with water measuring device and preferably
also with load cell.

d) Formwork @ 4% on cost of material, labour and


machinery (a+b+c)

11 - 577
Sr. Reference to
Description Unit Quantity
No. MORD Spec
e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

(ii) Nominal mix 1:3.6 (Hand mixing)

Unit = cum

a) Material

Cement t 0.250

Coarse sand cum 0.48

40 mm aggregate cum 0.576

20 mm aggregate cum 0.288

10 mm aggregate cum 0.096

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 4% on cost of material (a) and


labour (b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

II. P.C.C grade M 15

(i) Nominal mix (1:2.5:5)

Unit = cum

a) Material

Cement t 0.275

Coarse sand cum 0.48

11 - 578
Sr. Reference to
Description Unit Quantity
No. MORD Spec
40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.08

Mason (1st Class0 day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 4% on cost of material, labour and


machinery (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

(ii) Nominal mix 1:2.5:5 (Hand mixing)

Unit = cum

a) Material

Cement t 0.275

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

11 - 579
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Bhisti day 0.27

c) Formwork @ 4% on (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

III. P.C.C. grade M 20

(i) Nominal mix (1:2:4)

Unit = cum

a) Material

Cement t 0.33

Sand cum 0.45

40 mm aggregate cum 0.36

20 mm aggregate cum 0.36

10 mm aggregate cum 0.18

b) Labour

Mate day 0.08

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 4% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

(ii) Nominal mix 1:2:4 (Hand mixed)

Unit = cum

11 - 580
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Material

Cement t 0.33

Sand cum 0.45

40 mm aggregate cum 0.36

20 mm aggregate cum 0.36

10 mm aggregate cum 0.18

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 4% out of material and labour (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

IV. R.C.C grade M 20

Unit = cum

a) Material

Cement t 0.35

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

11 - 581
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 4% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = (a+b+c+d+e+f+g)

V. R.C.C. grade M 25

Unit = cum

a) Material

Cement t 0.404

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 3.75% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

B With natural Gravel

11 - 582
Sr. Reference to
Description Unit Quantity
No. MORD Spec
(i) Nominal mix 1:3:6
Unit = cum

a) Material

Cement t 0.250

Coarse sand cum 0.48

40 mm aggregate cum 0.576

20 mm aggregate cum 0.288

10 mm aggregate cum 0.096


b) Labour

Mate day 0.08

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Mechnical concrete mixer 0.4/0.28 cum capacity hour 0.40


fitted with water measuring device and preferably
also with load cell.

d) Formwork @ 4% on cost of material, labour and


machinery (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

(ii) Nominal mix 1:3.6 (Hand mixing)

Unit = cum

a) Material

Cement t 0.250

Coarse sand cum 0.48

40 mm aggregate cum 0.576

20 mm aggregate cum 0.288

10 mm aggregate cum 0.096

11 - 583
Sr. Reference to
Description Unit Quantity
No. MORD Spec
b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 4% on cost of material (a) and


labour (b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

II. P.C.C grade M 15

(i) Nominal mix (1:2.5:5)

Unit = cum

a) Material

Cement t 0.275

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.08

Mason (1st Class0 day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 4% on cost of material, labour and


machinery (a+b+c)

11 - 584
Sr. Reference to
Description Unit Quantity
No. MORD Spec
e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

(ii) Nominal mix 1:2.5:5 (Hand mixing)

Unit = cum

a) Material

Cement t 0.275

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 4% on (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

III. P.C.C. grade M 20

(i) Nominal mix (1:2:4)

Unit = cum

a) Material

Cement t 0.33

Sand cum 0.45

11 - 585
Sr. Reference to
Description Unit Quantity
No. MORD Spec
40 mm aggregate cum 0.36

20 mm aggregate cum 0.36

10 mm aggregate cum 0.18

b) Labour

Mate day 0.08

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 4% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

(ii) Nominal mix 1:2:4 (Hand mixed)

Unit = cum

a) Material

Cement t 0.33

Sand cum 0.45

40 mm aggregate cum 0.36

20 mm aggregate cum 0.36

10 mm aggregate cum 0.18

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 4% out of material and labour (a+b)

11 - 586
Sr. Reference to
Description Unit Quantity
No. MORD Spec
d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

IV. R.C.C grade M 20

Unit = cum

a) Material

Cement t 0.35

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 4% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = (a+b+c+d+e+f+g)

V. R.C.C. grade M 25

Unit = cum

a) Material

Cement t 0.404

Coarse sand cum 0.45

20 mm aggregate cum 0.54

11 - 587
Sr. Reference to
Description Unit Quantity
No. MORD Spec
10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 3.75% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

11.5 600 & 1200 Brick masonry work in cement mortar in foundation complete
excluding pointing and plastering as per drawing and technical
specifications Clauses 600, 1202 & 1203

Unit = cum

I. Brick masonry in 1:3 cement mortar

a) Material

Brick Nos. 500.00

Cement mortar 1:3 cum 0.20

(Rate as per Sub-analysis)

b) Labour

Mate day 0.09

Mason (1st Class) day 0.80

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20

c) Contractor’s profit & Overheads @ 20% on (a+b)

11 - 588
Sr. Reference to
Description Unit Quantity
No. MORD Spec
d) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e

Sub-analysis

Cement mortar 1:3 (1 cement : 3 sand)

Unit = cum

a) Material

Cement t 0.38

Sand cum 1.05

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 0.90

Bhisti day 0.08

Total material and labour = (a+b)

II. Brick masonry in 1:4 cement mortar

Unit = cum

a) Material

Brick Nos. 500.00

Cement mortar 1:4 cum 0.20

Rates as per sub-analysis

b) Labour

Mate day 0.09

Mason (1st Class) day 0.80

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

11 - 589
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate per cum = a+b+c+d+e

Sub-analysis

Cement mortar 1:4 (1 cement : 4 sand)

Unit = cum

a) Material

Cement t 0.24

Sand cum 1.05

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 0.90

Bhisti day 0.08

Total material and labour = (a+b)

III. Brick masonry in 1:6 cement mortar

Unit = cum

a) Material

Brick Nos. 500.00

Cement mortar 1:6 cum 0.20

b) Labour

Mate day 0.09

Mason (1st Class) day 0.80

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20


c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e

Sub-analysis

Cement mortar 1:6 (1 cement : 6 sand)

11 - 590
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = cum

a) Material

Cement t 0.18

Sand cum 1.05

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 0.90

Bhisti day 0.08

Total material and labour = (a+b)

11.6 700 & 1200 Stone masonry work in cement mortar in foundation complete
as per drawing and technical specifications Clauses 702, 704,
1202 & 1203.

Unit = cum

I. Coursed rubble masonry (1st sort)

(i) In 1:3 cement mortar

Unit = cum

a) Material

Stone for C.R. masonry 1st sort cum 0.95

Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00
cum)

Cement mortar (1:3) (Rate as in item 11.5 I) cum 0.27

b) Labour

Mate day 0.14

Mason 1st Class day 1.50

Mazdoor (Unskilled) day 2.10

Bhisti day 0.08

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

11 - 591
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Rate per cum = a+b+c+d+e

(ii) In 1:4 cement mortar

Unit = cum
a) Material

Stone for C.R. masonry 1st sort cum 0.95

Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00
cum)

Cement mortar 1:4 (Rate as in item 11.5 II) cum 0.27

b) Labour

Mate day 0.14

Mason (1st Class) day 1.50

Mazdoor (Unskilled) day 2.10

Bhisti day 0.08

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = (a+b+c+d+e)

(iii) In 1:6 cement mortar

Unit = cum
a) Material

Stone for C.R. masonry 1st sort cum 0.95

Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00
cum)

Cement mortar 1:4 (Rate as in item 11.5 II) cum 0.27

b) Labour

Mate day 0.14

Mason (1st Class) day 1.50

Mazdoor (Unskilled) day 2.10

11 - 592
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Bhisti day 0.08

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = (a+b+c+d+e)

Note: Quantity of required chips has not been provided for separately as it
is assumed that the same will be availble from dressing of stones

II. Coursed rubble masonry (2nd sort)

(i) In 1:3 cement mortar

Unit = cum

a) Material

Stone for C.R. masonry 2nd sort cum 0.34

Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00
cum)

Spalls/blasted rubble cum 0.61

Cement mortar (Rate as in item 11.5 I.) cum 0.55

b) Labour

Mate day 0.14

Mason (1st Class) day 1.30

Mazdoor (Unskilled) day 2.00

Bhisti day 0.08

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e

(ii) In 1:4 cement mortar

Unit = cum

a) Material

11 - 593
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Stone for C.R. masonry 2nd sort cum 0.90

Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00
cum)

Spalls/Blasted rubble cum 0.50

Cement mortar (Rate as in item 11.5 II) cum 0.35

b) Labour

Mate day 0.14

Mason (1st Class) day 1.30

Mazdoor (Unskilled) day 2.00

Bhisti day 0.08

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e

(iii) In 1:6 cement mortar

Unit = cum

a) Material

Stone for C.R. masonry 2nd sort cum 0.90

Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00
cum)

Spalls/Blasted rubble cum 0.50

Cement mortar (1:6) (Rate as in item 11.5 III) cum 0.35

b) Labour

Mate day 0.14

Mason (1st Class) day 1.30

Mazdoor (Unskilled) day 2.00

Bhisti day 0.08

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

11 - 594
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate per cum = a+b+c+d+e

III. Random Rubble Masonry

(i) In 1:3 cement mortar

Unit = cum

a) Material

Stone for R.R. masonry cum 1.00

Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00
cum)

Cement mortar (1:3) (Rate as in item 11.5 I) cum 0.60

b) Labour

Mate day 0.12

Mason (1st Class) day 1.19

Mazdoor (Unskilled) day 1.80

Bhisti day 0.08

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e

(ii) In cement mortar 1:4

a) Material

Stone for R.R. masonry cum 1.00

Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00
cum)

Cement mortar (1:4) (Rate as in item 11.5 II) cum 0.27

b) Labour

Mate day 0.12

Mason (1st Class) day 1.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.12

11 - 595
Sr. Reference to
Description Unit Quantity
No. MORD Spec
c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e

(iii) In cement mortar 1:6

a) Material

Stone for R.R. masonry cum 1.00

Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 Nos. 7.00
cum)

Cement mortar (1:6) (Rate as in item 11.5 III) cum 0.27

b) Labour

Mate day 0.12

Mason (1st Class) day 1.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.12

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e

Note: Quantity of required chips has not been provided for separately as it
is assumed that the same will be availble from dressing of stones

11.7 1000 & 1200 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar
(From Primary Producer: TATA/SAIL/Esser Steel/ Jindal
steel/Shyam steel/RINL) in foundation complete as per
drawings and technical specifications Clauses 1000 and 1202

Unit = t

a) Material

TMT bars including 5 per cent for overlaps and wastage t 1.05

Binding wire kg 6.00

11 - 596
Sr. Reference to
Description Unit Quantity
No. MORD Spec
b) Labour for cutting, bending, shifting to site, tying and
placing in position

Mate day 0.40

Blacksmith day 2.00

Mazdoor (Unskilled) day 6.00

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per t = a+b+c+d+e

11.8 1000 & 1200 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar
(Other ISI approved TMT reinforcement bar
(SAI/BISCON/THERMAX or equivalent)) in foundation complete
as per drawings and technical specifications Clauses 1000 and
1202

Unit = t

a) Material

TMT bars including 5 per cent for overlaps and wastage t 1.05

Binding wire kg 6.00

b) Labour for cutting, bending, shifting to site, tying and


placing in position

Mate day 0.40

Blacksmith day 2.00

Mazdoor (Unskilled) day 6.00

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per t = a+b+c+d+e

11.9 1000 & 1200 Supplying, fitting and placing MS bar (Fe-500 ) reinforcement
bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal
steel/Shyam steel/RINL) in foundation complete as per
drawings and technical specifications Clauses 1000 and 1202
Unit = t

a) Material

11 - 597
Sr. Reference to
Description Unit Quantity
No. MORD Spec
TMT bars including 5 per cent for overlaps and wastage t 1.05

Binding wire kg 6.00

b) Labour for cutting, bending, shifting to site, tying and


placing in position

Mate day 0.40

Blacksmith day 2.00

Mazdoor (Unskilled) day 6.00

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per t = a+b+c+d+e

11 - 598
Chapter 11

FOUNDATION
Rate
Amount (Rs.)
(Rs.)

356.65 114.13

244.56 733.68

169.56

0.00

1,017.37

102.00

11 - 599
Rate
Amount (Rs.)
(Rs.)
356.65 135.53

244.56 1,100.52

247.21

0.00

1,483.26

148.33

356.65 142.66

244.56 1,222.80

273.09

0.00

1,638.55

163.86

11 - 600
Rate
Amount (Rs.)
(Rs.)
356.65 189.02

356.65 299.59

356.65 142.66

244.56 1,589.64

435.00 435.00

120.00 420.00

15.00 180.00

651.18

0.00

3,907.09

390.71

356.65 71.33

244.56 978.24

435.00 2,175.00

644.91

0.00

11 - 601
Rate
Amount (Rs.)
(Rs.)
3,869.48

386.95

356.65 213.99

244.56 3,668.40

776.48

0.00

4,658.87

465.89

356.65 3.57

244.56 317.93

11 - 602
Rate
Amount (Rs.)
(Rs.)

950.00 855.00

235.30

0.00

1,411.79

356.65 71.33

244.56 733.68

161.00

0.00

966.01

161.00

11 - 603
Rate
Amount (Rs.)
(Rs.)

6,200.00 1,643.00

950.00 456.00

1,500.00 570.00

1,777.00 426.48

1,916.00 153.28

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

155.27

807.43

0.00

4,844.57

6,200.00 1,643.00

950.00 456.00

1,221.00 463.98

1,463.00 351.12

1,364.00 109.12

356.65 32.10

11 - 604
Rate
Amount (Rs.)
(Rs.)
458.55 45.86

244.56 489.12

244.56 66.03

146.25

760.52

0.00

4,563.09

6,200.00 1,550.00

950.00 456.00

1,500.00 864.00

1,777.00 511.78

1,916.00 183.94

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

167.20

11 - 605
Rate
Amount (Rs.)
(Rs.)
869.43

0.00

5,216.59

6,200.00 1,550.00

950.00 456.00

1,500.00 864.00

1,777.00 511.78

1,916.00 183.94

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

167.95

873.35

0.00

5,240.12

6,200.00 1,705.00

950.00 456.00

11 - 606
Rate
Amount (Rs.)
(Rs.)
1,500.00 720.00

1,777.00 426.48

1,916.00 153.28

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

163.00

847.60

0.00

5,085.61

6,200.00 1,705.00

950.00 456.00

1,500.00 720.00

1,777.00 426.48

1,916.00 153.28

356.65 32.10

458.55 45.86

244.56 489.12

11 - 607
Rate
Amount (Rs.)
(Rs.)
244.56 66.03

163.75

851.52

0.00

5,109.14

6,200.00 2,046.00

950.00 427.50

1,500.00 540.00

1,777.00 639.72

1,916.00 344.88

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

184.49

959.37

0.00

5,756.21

11 - 608
Rate
Amount (Rs.)
(Rs.)

6,200.00 2,046.00

950.00 427.50

1,500.00 540.00

1,777.00 639.72

1,916.00 344.88

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

185.25

963.29

0.00

5,779.74

6,200.00 2,170.00

950.00 427.50

1,777.00 959.58

1,916.00 689.76

356.65 28.53

458.55 55.03

244.56 423.09

11 - 609
Rate
Amount (Rs.)
(Rs.)
244.56 66.03

188.00 75.20

196.00

1,018.14

0.00

6,108.86

6,200.00 2,504.80

950.00 427.50

1,777.00 959.58

1,916.00 689.76

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

196.11

1,085.12

0.00

6,510.75

11 - 610
Rate
Amount (Rs.)
(Rs.)

6,200.00 1,550.00

950.00 456.00

1,221.00 703.30

1,463.00 421.34

1,364.00 130.94

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

155.03

806.17

0.00

4,837.04

6,200.00 1,550.00

950.00 456.00

1,221.00 703.30

1,463.00 421.34

1,364.00 130.94

11 - 611
Rate
Amount (Rs.)
(Rs.)

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

155.79

810.10

0.00

4,860.57

6,200.00 1,705.00

950.00 456.00

1,221.00 586.08

1,463.00 351.12

1,364.00 109.12

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

152.86

11 - 612
Rate
Amount (Rs.)
(Rs.)
794.89

0.00

4,769.32

6,200.00 1,705.00

950.00 456.00

1,221.00 586.08

1,463.00 351.12

1,364.00 109.12

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

153.62

798.81

0.00

4,792.85

6,200.00 2,046.00

950.00 427.50

11 - 613
Rate
Amount (Rs.)
(Rs.)
1,221.00 439.56

1,463.00 526.68

1,364.00 245.52

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

171.98

894.30

0.00

5,365.79

6,200.00 2,046.00

950.00 427.50

1,221.00 439.56

1,463.00 526.68

1,364.00 245.52

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

172.73

11 - 614
Rate
Amount (Rs.)
(Rs.)
898.22

0.00

5,389.32

6,200.00 2,170.00

950.00 427.50

1,463.00 790.02

1,364.00 491.04

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

181.00

941.49

0.00

5,648.93

6,200.00 2,504.80

950.00 427.50

1,463.00 790.02

11 - 615
Rate
Amount (Rs.)
(Rs.)
1,364.00 491.04

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

182.30

1,008.71

0.00

6,052.24

8.00 4,000.00

3,607.43 721.49

356.65 32.10

458.55 366.84

244.56 391.30

244.56 48.91

1,112.13

11 - 616
Rate
Amount (Rs.)
(Rs.)
0.00

6,672.76

6,200.00 2,356.00

950.00 997.50

356.65 14.27

244.56 220.10

244.56 19.56

3,607.43

8.00 4,000.00

2,739.43 547.89

356.65 32.10

458.55 366.84

244.56 391.30

244.56 48.91

1,077.41

0.00

11 - 617
Rate
Amount (Rs.)
(Rs.)
6,464.44

6,200.00 1,488.00

950.00 997.50

356.65 14.27

244.56 220.10

244.56 19.56

2,739.43

8.00 4,000.00

2,367.43 473.49

356.65 32.10

458.55 366.84

244.56 391.30

244.56 48.91
1,062.53

0.00

6,375.16

11 - 618
Rate
Amount (Rs.)
(Rs.)

6,200.00 1,116.00

950.00 997.50

356.65 14.27

244.56 220.10

244.56 19.56

2,367.43

1,135.00 1,078.25

54.00 378.00

3,607.43 974.01

356.65 49.93

458.55 687.83

244.56 513.58

244.56 19.56

740.23

0.00

11 - 619
Rate
Amount (Rs.)
(Rs.)

4,441.39

1,135.00 1,078.25

54.00 378.00

2,739.43 739.65

356.65 49.93

458.55 687.83

244.56 513.58

244.56 19.56

693.36

0.00

4,160.15

1,135.00 1,078.25

54.00 378.00

2,367.43 639.21

356.65 49.93

458.55 687.83

244.56 513.58

11 - 620
Rate
Amount (Rs.)
(Rs.)
244.56 19.56

673.27

0.00

4,039.63

1,135.00 385.90

54.00 378.00

650.00 396.50

3,607.43 1,984.09

356.65 49.93

458.55 596.12

244.56 489.12

244.56 19.56

859.84

0.00

5,159.06

11 - 621
Rate
Amount (Rs.)
(Rs.)
1,135.00 1,021.50

54.00 378.00

987.00 493.50

2,739.43 958.80

356.65 49.93

458.55 596.12

244.56 489.12

244.56 19.56

801.31

0.00

3,786.34

1,135.00 1,021.50

54.00 378.00

987.00 493.50

2,367.43 828.60

356.65 49.93

458.55 596.12

244.56 489.12

244.56 19.56

775.27

0.00

11 - 622
Rate
Amount (Rs.)
(Rs.)
3,630.10

1,135.00 1,135.00

54.00 378.00

3,607.43 2,164.46

356.65 42.80

458.55 545.67

244.56 440.21

244.56 19.56

945.14

0.00

5,670.85

1,135.00 1,135.00

54.00 378.00

2,739.43 739.65

356.65 42.80

458.55 550.26

244.56 440.21

244.56 29.35

11 - 623
Rate
Amount (Rs.)
(Rs.)
663.05

0.00

3,978.31

1,135.00 1,135.00

54.00 378.00

2,367.43 639.21

356.65 42.80

458.55 550.26

244.56 440.21

244.56 29.35

642.96

0.00

3,857.78

40,763.00 42,801.15

80.00 480.00

11 - 624
Rate
Amount (Rs.)
(Rs.)

356.65 142.66

458.55 917.10

244.56 1,467.36

9,161.65

0.00

54,969.92

34,492.00 36,216.60

80.00 480.00

356.65 142.66

458.55 917.10

244.56 1,467.36

7,844.74

0.00

47,068.46

11 - 625
Rate
Amount (Rs.)
(Rs.)
41,525.00 43,601.25

80.00 480.00

356.65 142.66

458.55 917.10

244.56 1,467.36

9,321.67

0.00

55,930.04

11 - 626
Chapter 12

SUBSTRUCTURE

Sr. Reference to
Description Unit Quantity
No. MORD Spec

12.1 600 Brick masonry work in cement mortar in substructure


complete excepting pointing and plastering, as per drawing
and technical specification Clauses 602, 603, 604, 1202 &
1204

I. In 1:3 cement mortar

Unit = cum

a) Material

Bricks Nos. 500.00

Cement mortar (Rate as in item 11.5 I) cum 0.24

b) Labour

Mate day 0.09

Mason 1st Class day 0.80

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20

Add for scaffolding @ 5 per cent of cost of materials


and labour (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

II. In 1:4 Cement mortar

Unit = cum

a) Material

Bricks Nos. 500.00

Cement mortar (Rate as in item 11.5 II) cum 0.24

b) Labour

Mate day 0.09

Mason 1st Class day 0.80

12 - 627
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20

Add for scaffolding @ 5 per cent of cost of materials


and labour (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

III. In 1:5 cement mortar

Unit = cum

a) Material

Bricks 1st class Nos. 500.00

Cement mortar cum 0.24

b) Labour

Mate day 0.09

Mason 1st Class day 0.80

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20

Add for scaffolding @ 5 per cent of cost of materials


and labour (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

Sub-analysis

Cement mortar 1:5 (1 cement, 5 sand)

a) Material

Cement t 0.22

Sand cum 1.05

12 - 628
Sr. Reference to
Description Unit Quantity
No. MORD Spec

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 0.90

Bhisti day 0.08

Total material and labour = (a+b)

IV. In 1:6 cement mortar

Unit = cum

a) Material

Brick first class Nos. 500.00

Cement lime mortar (Rate as in item 11.5 III) cum 0.24

b) Labour

Mate day 0.09

Mason 1st Class day 0.80

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20

Add for scaffolding @ 5 per cent of cost of materials


and labour (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

12.2 600 Pointing with cement mortar (1:3) on brickwork as per


drawing and technical specification Clauses 613.3 and 1204

Unit = 10 sqm

Taking output = 10 sqm

a) Material

Cement mortar 1.3 (Rate as in item 11.5. I) cum 0.03

b) Labour

12 - 629
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Mate day 0.04

Mason 1st Class day 0.50

Mazdoor (Unskilled) day 0.35

Bhisti day 0.20

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per 10 sqm = (a+b+c+d+e)

Note: Scaffolding is already included in item 12.1

12.3 600 Plastering with cement mortar (1:4), 15 mm thick on


brickwork in substructure as per technical specification
Clauses 613.4 & 1204

Unit = 10 sqm

Taking output = 10 sqm

a) Material

Cement mortar 1:4 (Rate as in item 11.5 II ) cum 0.18

b) Labour

Mate day 0.06

Mason 1st Class day 0.60

Mazdoor (Unskilled) day 0.60

Bhisti day 0.30

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per 10 sqm = a+b+c+d+e

Note: 1 Scaffolding is already included in item 12.1

2 Though cement mortar of leaner mix has been included in


item 12.1, for cement plaster mix of 1:4 has been
proposed for better finishing

12 - 630
Sr. Reference to
Description Unit Quantity
No. MORD Spec

3 If cement plaster 12 mm or 18 mm thick is required


elsewhere only the quantity of cement mortar may be
changed on prorata basis without any change in the
labour.

12.4 700 Stone masonry in cement mortar for substructure complete


as per drawing & technical specification Clauses 702, 704,
1202 and 1204

I. Coursed rubble masonry (1st sort)

(i) In 1:3 cement mortar

Unit = cum

a) Material

Stone for CR masonry 1st sort cum 1.10

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Cement mortar (Rate as in item 11.5. I) cum 0.27

b) Labour

Mate day 0.14

Mason 1st Class day 1.50

Mazdoor (Unskilled) day 2.10

Bhisti day 0.08

Add for scaffolding @ 5 per cent of cost of


material (a) and labour (b) (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

(ii) In 1:4 cement mortar

Unit = cum

a) Material

Stone for CR masonry 1st sort cum 1.10

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

12 - 631
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Cement mortar (Rate as in item 11.5 II) cum 0.27

b) Labour

Mate day 0.14

Mason 1st Class day 1.50

Mazdoor (Unskilled) day 2.10

Bhisti day 0.08

Add for scaffolding @ 5 per cent of cost of


material (a) and labour (b) 5% on (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

(iii) In cement mortar (1:5)

Unit = cum

a) Material

Stone for CR masonry 1st sort cum 1.10

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Cement mortar (Rate same as in item 12.1 III) cum 0.27

b) Labour

Mate day 0.14

Mason 1st Class day 1.30

Mazdoor (Unskilled) day 2.00

Bhisti day 0.08

As for scaffolding @ 5% on (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

12 - 632
Sr. Reference to
Description Unit Quantity
No. MORD Spec

(iv) In cement mortar (1:6)

Unit = cum

a) Material

Stone for CR masonry 1st sort cum 1.10

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Cement mortar (Rate as in item 11.5. III) cum 0.27

b) Labour

Mate day 0.14

Mason 1st Class day 1.30

Mazdoor (Unskilled) day 2.00

Bhisti day 0.08

Add for scaffolding @ 5% of (a) and (b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

II. Coursed Rubble masonry (2nd sort)

(i) In cement mortar (1:3)

Unit = cum

a) Material

Stone for CR masonry 2nd sort cum 0.60

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Spalls/blasted rubbles cum 0.50

Cement mortar (Rate as in item 11.5 I) cum 0.38

b) Labour

Mate day 0.14

Mason 1st Class day 1.30

12 - 633
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Mazdoor (Unskilled) day 2.00

Bhisti day 0.08

Add for scaffolding @ 5 per cent of cost of


material (a) and labour (b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

(ii) In 1:4 cement mortar

Unit = cum

a) Material

Stone for CR masonry 2nd sort cum 0.60

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Spall/blasted rubble cum 0.50

Cement mortar (Rate same as in item 11.5 II) cum 0.38

b) Labour

Mate day 0.14

Mason 1st Class day 1.30

Mazdoor (Unskilled) day 2.00

Bhisti day 0.08

Add for scaffolding @ 5 per cent of cost of


material (a) and labour (b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

(iii) In cement mortar (1:5)

Unit = cum

12 - 634
Sr. Reference to
Description Unit Quantity
No. MORD Spec

a) Material

Stone for CR masonry 2nd sort cum 0.60

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Spall/blasted rubble cum 0.50

Cement mortar (Rate same as in item 12.1 III) cum 0.38

b) Labour

Mate day 0.14

Mason 1st Class day 1.30

Mazdoor (Unskilled) day 2.00

Bhisti day 0.08

Add for scaffolding @ 5 per cent on (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

(iv) In cement mortar (1:6)

Unit = cum

a) Material

Stone for CR masonry 2nd sort cum 0.60

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Spalls/blasted rubbles cum 0.50

Cement lime mortar (Rate as in item 11.5 III) cum 0.38

b) Labour

Mate day 0.14

Mason 1st Class day 1.30

Mazdoor (Unskilled) day 2.00

Bhisti day 0.08

12 - 635
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Add for scaffolding @ 5 per cent on (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

III. Random rubble masonry

(i) In cement mortar (1:3)

Unit = cum

a) Material

Stone for RR masonry cum 1.00

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Cement mortar (Rate as in item 11.5 I) cum 0.48

b) Labour

Mate day 0.12

Mason 1st Class day 1.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.08

Add for scaffolding @ 5 per cent of cost of


material (a) and labour (b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

(ii) In 1:4 cement mortar

Unit = cum

a) Material

Stone for RR masonry cum 1.00

12 - 636
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Cement mortar (Rate same as in item 11.5 II) cum 0.48

b) Labour

Mate day 0.12

Mason 1st Class day 1.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.08

Add for scaffolding @ 5 per cent of cost of


material (a) and labour (b) 5% on (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

(iii) In cement mortar (1:5)

Unit = cum

a) Material

Stone for RR masonry cum 1.00

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Cement mortar (Rate same as in item 12.1 III) cum 0.48

b) Labour

Mate day 0.12

Mason 1st Class day 1.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.08

Add for scaffolding @ 5 per cent on (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

12 - 637
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Rate per cum = a+b+c+d+e

(iv) In cement mortar (1:5)

Unit = cum

a) Material

Stone for RR masonry cum 1.00

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

Cement lime mortar (Rate as in item 11.5 III) cum 0.48

b) Labour

Mate day 0.12

Mason 1st Class day 1.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.08

Add for scaffolding @ 5 per cent on (a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

12.5 800 Plain/reinforced cement concrete in substructure complete


as per drawings and technical specification Clauses 802,
804, 805, 806, 807, 1202 ans 1204

A With Crushed Stone

For height upto 5 m

Unit = cum

I. P.C.C grade M 15

(i) Nominal mix (1:2.5:5)

Unit = cum

12 - 638
Sr. Reference to
Description Unit Quantity
No. MORD Spec

a) Material

Cement t 0.275

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.08

Mason (1st Class0 day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 10% on cost of material, labour


and machinery (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e

(ii) Nominal mix 1:2.5:5 (Hand mixing)

Unit = cum

a) Material

Cement t 0.275

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

12 - 639
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 10% on (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

II. P.C.C. grade M 20

(i) Nominal mix (1:2:4)

Unit = cum

a) Material

Cement t 0.33

Sand cum 0.45

40 mm aggregate cum 0.36

20 mm aggregate cum 0.36

10 mm aggregate cum 0.18

b) Labour

Mate day 0.08

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 10% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

12 - 640
Sr. Reference to
Description Unit Quantity
No. MORD Spec

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

(ii) Nominal mix 1:2:4 (Hand mixed)

Unit = cum

a) Material

Cement t 0.33

Sand cum 0.45

40 mm aggregate cum 0.36

20 mm aggregate cum 0.36

10 mm aggregate cum 0.18

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 10% out of material and labour


(a+b)
d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

III. R.C.C grade M 20

Unit = cum

a) Material

Cement t 0.35

Coarse sand cum 0.45

20 mm aggregate cum 0.54

12 - 641
Sr. Reference to
Description Unit Quantity
No. MORD Spec

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

i) For Height upto 5m

d) Formwork @ 10% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

ii) For Height above 5m upto 10m

d) Formwork @ 12% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = (a+b+c+d+e+f+g)

IV. R.C.C. grade M 25

Unit = cum

a) Material

Cement t 0.404

Coarse sand cum 0.45

20 mm aggregate cum 0.54

12 - 642
Sr. Reference to
Description Unit Quantity
No. MORD Spec

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

i) For Height upto 5m

d) Formwork @ 10% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

ii) For Height above 5m upto 10m

d) Formwork @ 12% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = (a+b+c+d+e+f+g)

B With Natural Gravel

For height upto 5 m

Unit = cum

I. P.C.C grade M 15

(i) Nominal mix (1:2.5:5)

12 - 643
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Unit = cum

a) Material

Cement t 0.275

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.08

Mason (1st Class0 day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 10% on cost of material, labour


and machinery (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e

(ii) Nominal mix 1:2.5:5 (Hand mixing)

Unit = cum

a) Material

Cement t 0.275

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

12 - 644
Sr. Reference to
Description Unit Quantity
No. MORD Spec

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 10% on (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

II. P.C.C. grade M 20

(i) Nominal mix (1:2:4)

Unit = cum

a) Material

Cement t 0.33

Sand cum 0.45

40 mm aggregate cum 0.36

20 mm aggregate cum 0.36

10 mm aggregate cum 0.18

b) Labour

Mate day 0.08

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 10% on (a+b+c)

12 - 645
Sr. Reference to
Description Unit Quantity
No. MORD Spec

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

(ii) Nominal mix 1:2:4 (Hand mixed)

Unit = cum

a) Material

Cement t 0.33

Sand cum 0.45

40 mm aggregate cum 0.36

20 mm aggregate cum 0.36

10 mm aggregate cum 0.18

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Formwork @ 10% out of material and labour


(a+b)
d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

III. R.C.C grade M 20

Unit = cum

a) Material

Cement t 0.35

Coarse sand cum 0.45

12 - 646
Sr. Reference to
Description Unit Quantity
No. MORD Spec

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

i) For Height upto 5m

d) Formwork @ 10% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = (a+b+c+d+e+f+g)

ii) For Height above 5m upto 10m

d) Formwork @ 12% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = (a+b+c+d+e+f+g)

IV. R.C.C. grade M 25

Unit = cum

a) Material

Cement t 0.404

Coarse sand cum 0.45

12 - 647
Sr. Reference to
Description Unit Quantity
No. MORD Spec

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

i) For Height upto 5m

d) Formwork @ 10% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

ii) For Height above 5m upto 10m

d) Formwork @ 12% on (a+b+c)

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = (a+b+c+d+e+f+g)

Note: 1 For height above 5 m upto 10 m same as above with


following changes:

a. Add 2 per cent of cost of material, labour and


machinery to cater for extra lift.

b. The provision of formwork shall be 12 per cent


instead of 10 per cent of cost of material, labour and
machinery

12 - 648
Sr. Reference to
Description Unit Quantity
No. MORD Spec

2 The cost of formwork has been increased for more height


to account for cost of side support to formwork.

3 Extra expenditure on structures which are more than 5 m


height is to cater for cost involved for approaching the
work spot by providing ramp for use by labour.

12.6 1000 Supplying, fitting and placing TMT (Fe-500 D) reinforcement


bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal
steel/Shyam steel/RINL) in substructrue complete as per
drawings and technical specification Clauses 1002, 1005,
1010 & 1202

Unit = t

a) Material

TMT bars including 5 per cent overlaps and wastage t 1.05

Binding wire kg 6.00

b) Labour for cutting, bending, shifting to site, tying, and


placing in position

Mate day 0.34

Blacksmith day 2.00

Mazdoor (Unskilled) day 6.50

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per t = a+b+c+d+e

12.7 1000 Supplying, fitting and placing TMT (Fe-500 D) reinforcement


bar (Other ISI approved TMT reinforcement bar
(SAI/BISCON/THERMAX or equivalent)) in substructrue
complete as per drawings and technical specification
Clauses 1002, 1005, 1010 & 1202

Unit = t

a) Material

TMT bars including 5 per cent overlaps and wastage t 1.05

12 - 649
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Binding wire kg 6.00

b) Labour for cutting, bending, shifting to site, tying, and


placing in position

Mate day 0.34

Blacksmith day 2.00

Mazdoor (Unskilled) day 6.50

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per t = a+b+c+d+e

12.8 1000 Supplying, fitting and placing MS Bar (Fe-500 )


reinforcement bar (From Primary Producer:
TATA/SAIL/Esser Steel/ Jindal steel/Shyam steel/RINL) in
substructrue complete as per drawings and technical
specification Clauses 1002, 1005, 1010 & 1202

Unit = t

a) Material

MS bars including 5 per cent overlaps and wastage t 1.05

Binding wire kg 6.00

b) Labour for cutting, bending, shifting to site, tying, and


placing in position

Mate day 0.34

Blacksmith day 2.00

Mazdoor (Unskilled) day 6.50

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per t = a+b+c+d+e

12 - 650
Sr. Reference to
Description Unit Quantity
No. MORD Spec

12.9 600 Providing weepholes in brick masonry/stone masonry,


plain/reinforced concrete abutment, wing wall, return wall
with 100 mm dia AC pipe extending through the full width of
the structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification
Clauses 614, 709, 1204.3.7

Unit = Nos

Taking output = 30 Nos

a) Material

AC pipe 100 mm dia including wastage @ 5 per cent. m 31.50


Average length of weep hole is taken as one metre for the
purpose of estimating

MS clamps Nos. 30.00

Cement mortar 1:3 (For rate refer to item 11.5 I) cum 0.05

b) Labour

Mate day 0.03

Mason 1st Class day 0.50

Mazdoor (Unskilled) day 0.25

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 30 Nos = (a+b+c)

Rate per No = (a+b+c+d+e)/30

12.10 1200 Backfilling behind abutment, wing wall and return wall
complete as per drawings & technical specification Clause
1204.3.8

Unit = cum

Taking output = 10 cum

I) Granular material

a) Material

Granular material cum 11.50

b) Labour

12 - 651
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Mate day 0.28

Mazdoor (Unskilled) day 10.00

Bhisti day 0.40

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10 cum of granular backfill = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/10

II) Sandy material

Unit = cum

Taking output = 10 cum

a) Material

Sand cum 11.00

b) Labour

Mate day 0.40

Mazdoor (Unskilled) day 10.00

Bhisti day 0.40

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10 cum of sand backfill = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/10

12.11 1200 Providing and laying filter media with granular crushed
aggregates as per specification to a thickness of not less
than 600 mm with smaller size towards the soil and bigger
size towards the wall and providing over the entire surface
behind abutment, wing wall, return wall to the full height,
compacted to firm condition complete as per drawing and
technical specification Clause 1204.3.8

Unit = cum

12 - 652
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Taking output = 10 cum

a) Material

Filter media as per specification cum 12.00

b) Labour

Mate day 0.40

Mazdoor (Unskilled) day 9.00

Mazdoor (Skilled) day 1.00

Bhisti day 0.50

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10 cum of filter media = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/10

12.12 1200 Supplying, fitting and fixing in position true to line and level
elastomeric bearing conforming to IRC:83 (Part-II) Section
IX complete, including all accessories as per drawings and
technical specification Clause 1207.1

Unit = cubic centimetre

Considering an elastomeric bearing of size 500 x 400 x 96 mm


for this analysis,

Overall volume = 19200 cu.cm

Volume of 6 Nos 488x388x4 mm size reinforcing steel plates =


4545 cu.cm.

Hence volume of elastomer = 14655 cu. cm.

a) Labour

Mate day 0.06

Mazdoor (Unskilled) day 1.00

Mazdoor Skilled day 0.50

b) Material

12 - 653
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Elastomeric bearing assembly consisting of 7 internal cu.cm. 1.00


layers of elastomer bonded to 6 nos. internal reinforcing
steel laminates by the process of vulcanisation, complete
with all components as per drawing and technical
specification

Add for anchorage bolts if required and consumables @ 1


per cent on (a+b)

Add 20% on(a+b)

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 19200 cu.cm. of elastomeric bearing = a+b+c+d+e

Rate per cu.cm of elastomeric bearing = (a+b+c)/19200

Note: For such type of manufactured item, the overhead cost is taken
as 30 per cent instead of 20 per cent

12.13 600 Providing PCC M-20 architectural coping on the top of wing
wall, return wall etc. complete as per drawing and technical
specification Clauses 615, 710 and 1204.3.11

A With Crushed Stone

Unit = Running m

Taking output = 1 m

Assume wall thickness = 345 mm

Projection of the coping will be 25 mm wide on both side of the


wall = 345 + 50 = 395 mm

Quantity = 1 x 0.395 x 0.150 = 0.059

PCC M-20 Grade (1:2:4) Nominal Mix

As per item No. 12.5 (II)(i) cum 0.059

Add 10 per cent extra of cost of (a) being architectural coping

Cost of 1 m = a

Rate per m = a

12 - 654
Sr. Reference to
Description Unit Quantity
No. MORD Spec

B With Natural Gravel

Unit = Running m

Taking output = 1 m

Assume wall thickness = 345 mm

Projection of the coping will be 25 mm wide on both side of the


wall = 345 + 50 = 395 mm

Quantity = 1 x 0.395 x 0.150 = 0.059

PCC M-20 Grade (1:2:4) Nominal Mix

As per item No. 12.5 (II)(i) cum 0.059

Add 10 per cent extra of cost of (a) being architectural coping

Cost of 1 m = a

Rate per m = a

12.14 1200 Providing pressure relief pipes 100 mm dia in bottom slab
of box cell on a filter media base of 500 mm x 500 mm as
per drawing and technical specification Clause 1205.5.7

Unit = Nos

a) Material

AC pipe 100 mm dia i/c wastage of 5 per cent 600 mm m 0.63


long upto the bottom of levelling course

Filter media base with stone aggregate 0.5 m x 0.5 m area cum 0.25
1 m deep

b) Labour

Mate day 0.031

Mason 1st Class day 0.016

Mazdoor (Unskilled) day 0.80


c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per No = (a+b+c+d+e)

12 - 655
Chapter 12

SUBSTRUCTURE

Rate
Amount (Rs.)
(Rs.)

8.00 4,000.00

3,607.43 865.78

356.65 32.10

458.55 366.84

244.56 391.30

244.56 48.91

243.29

1,189.64

0.00

7,137.86

8.00 4,000.00

2,739.43 657.46

356.65 32.10

458.55 366.84

12 - 656
Rate
Amount (Rs.)
(Rs.)

244.56 391.30

244.56 48.91

274.83

1,154.29

0.00

6,925.73

8.00 4,000.00

2,615.43 627.70

356.65 32.10

458.55 366.84

244.56 391.30

244.56 48.91

273.34

1,148.04

0.00

6,888.23

6,200.00 1,364.00

950.00 997.50

12 - 657
Rate
Amount (Rs.)
(Rs.)

356.65 14.27

244.56 220.10

244.56 19.56

2,615.43

8.00 4,000.00

2,367.43 568.18

356.65 32.10

458.55 366.84

244.56 391.30

244.56 48.91

270.37

1,135.54

0.00

6,813.24

3,607.43 108.22

12 - 658
Rate
Amount (Rs.)
(Rs.)

356.65 14.27

458.55 229.28

244.56 85.60

244.56 48.91

97.25

0.00

583.53

2,739.43 493.10

356.65 21.40

458.55 275.13

244.56 146.74

244.56 73.37

201.95

0.00

1,211.68

12 - 659
Rate
Amount (Rs.)
(Rs.)

1,135.00 1,248.50

54.00 378.00

3,607.43 974.01

356.65 49.93

458.55 687.83

244.56 513.58

244.56 19.56

193.57

812.99

0.00

4,877.97

1,135.00 1,248.50

54.00 378.00

12 - 660
Rate
Amount (Rs.)
(Rs.)

2,739.43 739.65

356.65 49.93

458.55 687.83

244.56 513.58

244.56 19.56

181.85

763.78

0.00

4,582.68

1,135.00 1,248.50

54.00 378.00

2,615.43 706.17

356.65 49.93

458.55 596.12

244.56 489.12

244.56 19.56

174.37

732.35

0.00

4,394.12

12 - 661
Rate
Amount (Rs.)
(Rs.)

1,135.00 1,248.50

54.00 378.00

2,367.43 639.21

356.65 49.93

458.55 596.12

244.56 489.12

244.56 19.56

171.02

718.29

0.00

4,309.75

1,135.00 681.00

54.00 378.00

544.00 272.00

3,607.43 1,370.83

356.65 49.93

458.55 596.12

12 - 662
Rate
Amount (Rs.)
(Rs.)

244.56 489.12

244.56 19.56

192.83

809.88

0.00

4,859.26

1,135.00 681.00

54.00 378.00

544.00 272.00

2,739.43 1,040.99

356.65 49.93

458.55 596.12

244.56 489.12

244.56 19.56

176.34

740.61

0.00

4,443.66

12 - 663
Rate
Amount (Rs.)
(Rs.)

1,135.00 681.00

54.00 378.00

544.00 272.00

2,615.43 993.87

356.65 49.93

458.55 596.12

244.56 489.12

244.56 19.56

173.98

730.72

0.00

4,384.29

1,135.00 681.00

54.00 378.00

544.00 272.00

2,367.43 899.63

356.65 49.93

458.55 596.12

244.56 489.12

244.56 19.56

12 - 664
Rate
Amount (Rs.)
(Rs.)

169.27

710.92

0.00

4,265.55

1,135.00 1,135.00

54.00 378.00

3,607.43 1,731.57

356.65 42.80

458.55 550.26

244.56 440.21

244.56 19.56

214.87

902.45

0.00

5,414.72

1,135.00 1,135.00

12 - 665
Rate
Amount (Rs.)
(Rs.)

54.00 378.00

2,739.43 1,314.93

356.65 42.80

458.55 550.26

244.56 440.21

244.56 19.56

194.04

814.96

0.00

4,889.76

1,135.00 1,135.00

54.00 378.00

2,615.43 1,255.41

356.65 42.80

458.55 550.26

244.56 440.21

244.56 19.56

191.06

802.46

0.00

12 - 666
Rate
Amount (Rs.)
(Rs.)

4,814.76

1,135.00 1,135.00

54.00 378.00

2,367.43 1,136.37

356.65 42.80

458.55 550.26

244.56 440.21

244.56 19.56

185.11

777.46

0.00

4,664.77

12 - 667
Rate
Amount (Rs.)
(Rs.)

6,200.00 1,705.00

950.00 456.00

1,500.00 720.00

1,777.00 426.48

1,916.00 153.28

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

407.50

896.50

0.00

5,379.01

6,200.00 1,705.00

950.00 456.00

1,500.00 720.00

1,777.00 426.48

1,916.00 153.28

12 - 668
Rate
Amount (Rs.)
(Rs.)

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

409.39

900.65

0.00

5,403.90

6,200.00 2,046.00

950.00 427.50

1,500.00 540.00

1,777.00 639.72

1,916.00 344.88

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

461.24

1,014.72

12 - 669
Rate
Amount (Rs.)
(Rs.)

0.00

6,088.30

6,200.00 2,046.00

950.00 427.50

1,500.00 540.00

1,777.00 639.72

1,916.00 344.88

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

463.12

1,018.87

0.00

6,113.19

6,200.00 2,170.00

950.00 427.50

1,777.00 959.58

12 - 670
Rate
Amount (Rs.)
(Rs.)

1,916.00 689.76

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

489.47

1,076.84

0.00

6,461.00

587.37

1,096.42

0.00

6,578.50

6,200.00 2,504.80

950.00 427.50

1,777.00 959.58

12 - 671
Rate
Amount (Rs.)
(Rs.)

1,916.00 689.76

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

522.95

1,150.49

0.00

6,903.00

627.54

1,171.41

0.00

7,028.47

12 - 672
Rate
Amount (Rs.)
(Rs.)

6,200.00 1,705.00

950.00 456.00

1,221.00 586.08

1,463.00 351.12

1,364.00 109.12

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

382.16

840.75

0.00

5,044.47

6,200.00 1,705.00

950.00 456.00

1,221.00 586.08

1,463.00 351.12

1,364.00 109.12

12 - 673
Rate
Amount (Rs.)
(Rs.)

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

384.04

844.89

0.00

5,069.36

6,200.00 2,046.00

950.00 427.50

1,221.00 439.56

1,463.00 526.68

1,364.00 245.52

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

429.95

12 - 674
Rate
Amount (Rs.)
(Rs.)

945.89

0.00

5,675.35

6,200.00 2,046.00

950.00 427.50

1,221.00 439.56

1,463.00 526.68

1,364.00 245.52

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

431.84

950.04

0.00

5,700.24

6,200.00 2,170.00

950.00 427.50

12 - 675
Rate
Amount (Rs.)
(Rs.)

1,463.00 790.02

1,364.00 491.04

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

452.64

995.82

0.00

5,975.00

543.17

1,013.92

0.00

6,083.53

6,200.00 2,504.80

950.00 427.50

12 - 676
Rate
Amount (Rs.)
(Rs.)

1,463.00 790.02

1,364.00 491.04

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

486.12

1,069.47

0.00

6,417.00

583.35

1,088.92

0.00

6,533.50

12 - 677
Rate
Amount (Rs.)
(Rs.)

40,763.00 42,801.15

80.00 480.00

356.65 121.26

458.55 917.10

244.56 1,589.64

9,181.83

0.00

55,090.98

34,492.00 36,216.60

12 - 678
Rate
Amount (Rs.)
(Rs.)

80.00 480.00

356.65 121.26

458.55 917.10

244.56 1,589.64

7,864.92

0.00

47,189.52

41,525.00 43,601.25

80.00 480.00

356.65 121.26

458.55 917.10

244.56 1,589.64

9,341.85

0.00

56,051.10

12 - 679
Rate
Amount (Rs.)
(Rs.)

60.00 1,890.00

19.00 570.00

3,607.43 180.37

356.65 10.70

458.55 229.28

244.56 61.14

588.30

0.00

3,529.78

117.66

698.00 8,027.00

12 - 680
Rate
Amount (Rs.)
(Rs.)

356.65 99.86

244.56 2,445.60

244.56 97.82

2,134.06

0.00

12,804.34

1,280.43

950.00 10,450.00

356.65 142.66

244.56 2,445.60

244.56 97.82

2,627.22

0.00

15,763.30

1,576.00

12 - 681
Rate
Amount (Rs.)
(Rs.)

1,013.00 12,156.00

356.65 142.66

244.56 2,201.04

356.65 356.65

244.56 122.28

2,995.73

0.00

17,974.36

1,797.00

356.65 21.40

244.56 244.56

356.65 178.33

12 - 682
Rate
Amount (Rs.)
(Rs.)

20,600.00 20,600.00

210.44

4,250.95

5,101.13

0.00

30,606.81

1.59

6,088.30 359.21

35.92

395.13

395.13

12 - 683
Rate
Amount (Rs.)
(Rs.)

5,675.35 334.85

33.48

368.33

368.33

60.00 37.80

1,013.00 253.25

356.65 11.06

458.55 7.34

244.56 195.65
101.02

0.00

606.11

12 - 684
Chapter 13

SUPERSTRUCTURE
Sr. Reference to
Description Unit Quantity
No. MORD Spec
13.1 800 Providing and laying reinforced cement concrete in
superstructure as per drawing and technical specifications
Clauses 800, 1205.4 and 1205.5

A With Crushed Stone

I. R.C.C grade M 20

(i) For nominal mix 1:2:4

Unit = cum

a) Material

Cement t 0.35

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Add for formwork and staging

i Height upto 5 m @ 20% of (a+b+c)

ii Height from 5m to 10m @ 25% of (a+b+c)

iii Height above 10m @ 30% of (a+b+c)

a) Height upto 5 m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i)

f) Add GST, LWC etc. @ 0 on (a+b+c+d i)

13 - 685
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate per cum = a+b+c+d i+e+f

b) Height from 5m to 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii)

Rate per cum = a+b+c+d ii+e+f

c) Height above 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii)

Rate per cum = a+b+c+d iii+e+f

(ii) For nominal mix 1:2:4 (Hand mixed)

Unit = cum

a) Material

Cement t 0.35

Coarse aggregate cum 0.45

20 cum aggregates cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) For formwork and staging add the following


percentage of (a+b)

i Height upto 5 m @ 20% of (a+b+c)

ii Height from 5m to 10m @ 25% of (a+b+c)

iii Height above 10m @ 30% of (a+b+c)

13 - 686
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Height upto 5 m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i)

f) Add GST, LWC etc. @ 0 on (a+b+c+d i)

Rate per cum = a+b+c+d i+e+f

b) Height from 5m to 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii)

Rate per cum = a+b+c+d ii+e+f

c) Height above 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii)

Rate per cum = a+b+c+d iii+e+f

(iii) For design mix RCC M 20

a) Material

Cement t 0.33

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) For formwork and staging add the following


percentage of (a+b+c):

i Height upto 5 m @ 20% of (a+b+c)

13 - 687
Sr. Reference to
Description Unit Quantity
No. MORD Spec
ii Height from 5m to 10m @ 25% of (a+b+c)

iii Height above 10m @ 30% of (a+b+c)

a) Height upto 5 m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i)

f) Add GST, LWC etc. @ 0 on (a+b+c+d i)

Rate per cum = a+b+c+d i+e+f

b) Height from 5m to 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii)

Rate per cum = a+b+c+d ii+e+f

c) Height above 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii)

Rate per cum = a+b+c+d iii+e+f

II. R.C.C M 25

Unit =cum

a) Material

Cement t 0.40

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

13 - 688
Sr. Reference to
Description Unit Quantity
No. MORD Spec
e) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) For formwork and staging refer to sub-item (c) of I


(ii) above

i Height upto 5 m @ 20% of (a+b+c)

ii Height from 5m to 10m @ 25% of (a+b+c)

iii Height above 10m @ 30% of (a+b+c)

a) Height upto 5 m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i)

f) Add GST, LWC etc. @ 0 on (a+b+c+d i)

Rate per cum = a+b+c+d i+e+f

b) Height from 5m to 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii)

Rate per cum = a+b+c+d ii+e+f

c) Height above 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii)

Rate per cum = a+b+c+d iii+e+f

Note: This analysis will hold good for concrete of nominal mix 1:1½:3
also

III. R.C.C. Grade M 30

Unit =cum

a) Material

Cement t 0.43

Sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

13 - 689
Sr. Reference to
Description Unit Quantity
No. MORD Spec
b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) For formwork and staging refer to sub-item (d) of I


(II) above

i Height upto 5 m @ 20% of (a+b+c)

ii Height from 5m to 10m @ 25% of (a+b+c)

iii Height above 10m @ 30% of (a+b+c)

a) Height upto 5 m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i)

f) Add GST, LWC etc. @ 0 on (a+b+c+d i)

Rate per cum = a+b+c+d i+e+f

b) Height from 5m to 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii)

Rate per cum = a+b+c+d ii+e+f

c) Height above 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii)

Rate per cum = a+b+c+d iii+e+f

A With Crushed Stone

I. R.C.C grade M 20

(i) For nominal mix 1:2:4

13 - 690
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = cum

a) Material

Cement t 0.35

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Add for formwork and staging

i Height upto 5 m @ 20% of (a+b+c)

ii Height from 5m to 10m @ 25% of (a+b+c)

iii Height above 10m @ 30% of (a+b+c)

a) Height upto 5 m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i)

f) Add GST, LWC etc. @ 0 on (a+b+c+d i)

Rate per cum = a+b+c+d i+e+f

b) Height from 5m to 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii)

Rate per cum = a+b+c+d ii+e+f

c) Height above 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii)

13 - 691
Sr. Reference to
Description Unit Quantity
No. MORD Spec
f) Add GST, LWC etc. @ 0 on (a+b+c+d iii)

Rate per cum = a+b+c+d iii+e+f

(ii) For nominal mix 1:2:4 (Hand mixed)

Unit = cum

a) Material

Cement t 0.35

Coarse aggregate cum 0.45

20 cum aggregates cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) For formwork and staging add the following


percentage of (a+b)

i Height upto 5 m @ 20% of (a+b+c)

ii Height from 5m to 10m @ 25% of (a+b+c)

iii Height above 10m @ 30% of (a+b+c)

a) Height upto 5 m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i)

f) Add GST, LWC etc. @ 0 on (a+b+c+d i)

Rate per cum = a+b+c+d i+e+f

b) Height from 5m to 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii)

13 - 692
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate per cum = a+b+c+d ii+e+f

c) Height above 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii)

Rate per cum = a+b+c+d iii+e+f

(iii) For design mix RCC M 20

a) Material

Cement t 0.33

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) For formwork and staging add the following


percentage of (a+b+c):

i Height upto 5 m @ 20% of (a+b+c)

ii Height from 5m to 10m @ 25% of (a+b+c)

iii Height above 10m @ 30% of (a+b+c)

a) Height upto 5 m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i)

f) Add GST, LWC etc. @ 0 on (a+b+c+d i)

Rate per cum = a+b+c+d i+e+f

13 - 693
Sr. Reference to
Description Unit Quantity
No. MORD Spec
b) Height from 5m to 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii)

Rate per cum = a+b+c+d ii+e+f

c) Height above 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii)

Rate per cum = a+b+c+d iii+e+f

II. R.C.C M 25

Unit =cum

a) Material

Cement t 0.40

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

e) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) For formwork and staging refer to sub-item (c) of I


(ii) above

i Height upto 5 m @ 20% of (a+b+c)

ii Height from 5m to 10m @ 25% of (a+b+c)

iii Height above 10m @ 30% of (a+b+c)

13 - 694
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Height upto 5 m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i)

f) Add GST, LWC etc. @ 0 on (a+b+c+d i)

Rate per cum = a+b+c+d i+e+f

b) Height from 5m to 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii)

Rate per cum = a+b+c+d ii+e+f

c) Height above 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii)

Rate per cum = a+b+c+d iii+e+f

Note: This analysis will hold good for concrete of nominal mix 1:1½:3
also

III. R.C.C. Grade M 30

Unit =cum

a) Material

Cement t 0.43

Sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

13 - 695
Sr. Reference to
Description Unit Quantity
No. MORD Spec
d) For formwork and staging refer to sub-item (d) of I
(II) above

i Height upto 5 m @ 20% of (a+b+c)

ii Height from 5m to 10m @ 25% of (a+b+c)

iii Height above 10m @ 30% of (a+b+c)

a) Height upto 5 m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i)

f) Add GST, LWC etc. @ 0 on (a+b+c+d i)

Rate per cum = a+b+c+d i+e+f

b) Height from 5m to 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii)

Rate per cum = a+b+c+d ii+e+f

c) Height above 10m

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii)

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii)

Rate per cum = a+b+c+d iii+e+f

Note: 1 Quantity of cement provided for various components of the


superstructure is for estimating purpose only. Actual quantity
of cement will be as per approved mix design. Similarly
quantity for corase and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design use of design mix in place of nominal mix of concrete
of M 20 and higher grader shall be prepared. Nominal mix of
grades M 20 and M 25 is to be used with adequate
supervision and quality control requirements Clause 803
technical specificatiosn

2 For higher grades like M 25 and M 30, if adopted, design mix


is recommended.

13.2 1000 Supplying, fitting and placing TMT (Fe-500 D) reinforcement


bar . (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal
steel/Shyam steel/RINL) in superstructure complete as per
drawing and technical specifications Clauses 1002, 1010 and
1202

13 - 696
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = t

a) Material

HYSD bars including 5 per cent for laps and wastage t 1.05

Binding wire kg 8.00

b) Labour for cutting, bending, tying and placing in


position

Mate day 0.44

Blacksmith day 3.00

Mazdoor (Unskilled) day 8.00

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per t = a+b+c+d+e

13.3 1000 Supplying, fitting and placing TMT (Fe-500 D) reinforcement


bar . (Other ISI approved TMT reinforcement bar
(SAI/BISCON/THERMAX or equivalent)) in superstructure
complete as per drawing and technical specifications
Clauses 1002, 1010 and 1202

Unit = t

a) Material

TMT bars including 5 per cent for laps and wastage t 1.05

Binding wire kg 8.00

b) Labour for cutting, bending, tying and placing in


position

Mate day 0.44

Blacksmith day 3.00

Mazdoor (Unskilled) day 8.00

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per t = a+b+c+d+e

13 - 697
Sr. Reference to
Description Unit Quantity
No. MORD Spec
13.4 1000 Supplying, fitting and placing MS Bar (Fe-500) reinforcement
bar (From Primary Producer: TATA/SAIL/Esser Steel/ Jindal
steel/Shyam steel/RINL) . in superstructure complete as per
drawing and technical specifications Clauses 1002, 1010 and
1202

Unit = t
a) Material

MS bars including 5 per cent for laps and wastage t 1.05

Binding wire kg 8.00

b) Labour for cutting, bending, tying and placing in


position

Mate day 0.44

Blacksmith day 3.00


Mazdoor (Unskilled) day 8.00

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per t = a+b+c+d+e

13.5 800 Providing and laying cement concrete wearing course M 30


grade including reinforcement complete as per drawing and
technical specifications Clauses 800 and 1206.3

A With crushed stone

Unit = cum

a) Material

Cement t 0.43

Sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

HYSD bar reinforcement (Rate as per item 13.2) t 0.075

Binding Wire kg 0.01

b) Labour

Mate day 0.10

13 - 698
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 3.00

Bhisti day 0.27

Blacksmith day 0.30

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 3% of cost of concrete

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f

B With Natural Gravel

Unit = cum

a) Material

Cement t 0.43

Sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

HYSD bar reinforcement (Rate as per item 13.2) t 0.075

Binding Wire kg 0.01

b) Labour

Mate day 0.10

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 3.00

Bhisti day 0.27

Blacksmith day 0.30

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

13 - 699
Sr. Reference to
Description Unit Quantity
No. MORD Spec
d) Formwork @ 3% of cost of concrete

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d)

f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f

13.6 800 Construction of R.C.C. railing of M 25 grade in cast-in-situ


with 20 mm nominal size aggregate, true to line and grade,
tolerance of vertical railing post not to exceed 1 in 500,
centre-to-centre spacing between vertical posts not to
exceed 2000 mm as per drawing and technical specifications
Clauses 800, 900 and 1208.3

Unit = Runing m
Taking output = 4x12 m

Span = 48 m

a) M 25 grade R.C.C.

No. of vertical posts = (6+1) 4 = 28 nos

Cross-sectional area of vertical post = 0.25x0.275 =


0.069 sqm

Concrete in vertical posts = 0.069 x28x1.00 = 1.932


cum

Hand rail in 3 tiers = 3x48 = 144 m

Cross-sectional area = 0.17x0.175 = 0.03 sqm

Concrete in hand rails = 0.03 x 144 = 4.32 cum

Total concrete = 1.932+4.32 = 6.252 cum cum 6.25

b) HYSD bar reinforcement (Rate as per item 13.2) t 1.40

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 48 m = (a+b+c+d+e)

Rate per m = (a+b+c+d+e)/48

Sub Analysis for Rate of Concrete

a) Material

13 - 700
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Cement t 0.40

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.12

Mazdoor (Unskilled) day 1.73

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Formwork @ 12%

Total (a+b+c+d)

Note: 1 48 m length is the total linear length adding both sides of


2x12 m span
2 Quantities of material have been adopted from standard
plans of MORTH vide drawing No SD/202

13.7 1200 Providing fitting and fixing mild steel railing complete as per
drawing and technical specifications Clause 1208.2

Unit = Runing m

Taking output = 100 m

a) Material

1) IS MC 100=2.806x1.05=2.946 t t 2.946

2) MS Flats = 0.964x1.05 =1.012 t t 1.012

3) MS bars = 0.17x1.05=0.18 t t 0.18

4) MS bolts, nuts and washers t 0.15

b) Labour

Mate day 2.80

Blacksmith day 30.00

Mazdoor (Unskilled) day 40.00

13 - 701
Sr. Reference to
Description Unit Quantity
No. MORD Spec
c) Add 5 per cent of (a) for painting one shop coat with red
oxide primer and three coats of synthetic enamel paint
and consumables @ 5% on (a)

d) Add for cost of concrete for fixing vertical post in the


preformed recess @ 1 per cent of (a)

e) Add for electricity charges, welding and drilling


equipment, electrodes and other consumables @ 1 per
cent of (a)
f) Contractor’s profit & Overheads @ 20% on (a+b+c+d+e)

g) Add GST, LWC etc. @ 0 on (a+b+c+d+e)

Rate per m = (a+b+c+d+e+f)/100

Note: A typical drawing for MS railing has been followed for estimate
purpose. Rate may be worked out as per design to be followed

13.8 1200 Providing and fixing in position pipe railing consisting of IS


Rolled steel joist posts designation IS MB 100 (100x75) at 2.5
m interval and three rows of 50 mm dia steel pipes (light)
including fixing in position on bridge deck complete as per
drawing and technical specifications Clause 1208.2

Unit = Running m

Taking output = 2 x 10 m = 20 m

a) Material

i) Steel posts IS MB 100 (100 x 75) t 0.13

5 x 2 x 11.5 x 1.1 x 1.05 = 130 kg

ii) 50 mm dia steel pipes m 60.00

20 x 3 = 60 m

iii) M.S Bolts, nuts and washers t 0.05

Add @ 5 per cent of (a) for painting one shop coat with
red oxide primer and three coats of synthetic enamel
paint and consumables

Add for electricity charges, welding and drilling


equipment, electrodes and other consumables @ 1 per
cent of (a)

b) Labour

Mate day 0.56

Blacksmith day 6.00

13 - 702
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Unskilled) day 8.00

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 20 m steel railing = a+b+c+d+e

Rate per metre = (a+b+c+d+e)/20

13.9 600 Brick masonry work in cement mortar 1:3 in parapet


excluding pointing and plastering as per drawing and
technical specifications Clauses 600, 900 and 1208.4

Unit = cum

a) Material

Bricks Nos. 500.00

Cement mortar (Rate as in item 11.5 I) cum 0.21

b) Labour

Mate day 0.09

Mason 1st Class day 0.80

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

13.10 1200 Drainage spouts complete as per drawing and technical


specifications Clause 1209

Unit = 1 No
a) Material

i) Corrosion resistant structural steel grating including 5 kg 4.00


per cent wastage

ii) G I pipe 100 mm dia m 1.00


b) Labour
For fabrication

13 - 703
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mate day 0.02

Blacksmith, Welder etc. (Skilled) day 0.02

Mazdoor (Unskilled) day 0.20

For fixing in position

Mate day 0.01

Mason (1st Class) day 0.01

Mazdoor (Unskilled) day 0.20

Add @ 5 per cent of cost of material and labour (a+b) for


electrodes, gas cutting, sealant, anti-corrrosive bituminous
paint, mild steel grating etc.

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per m = a+b+c+d+e

13.11 800 P.C.C. M 15 ordinary grade (1:2.5:5) levelling course below


approach slab complete as per drawing and technical
specifications Clauses 800 and 1211

A With crushed stone

(i) Nominal mix (1:2.5:5)

Unit = cum

a) Material

Cement t 0.275

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.08

Mason (1st Class0 day 0.10

Mazdoor (Unskilled) day 1.63

13 - 704
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e

(ii) Nominal mix 1:2.5:5 (Hand mixing)

Unit = cum

a) Material

Cement t 0.270

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

Bhisti day 0.27

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

B With Natural Gravel

(i) Nominal mix (1:2.5:5)

Unit = cum

a) Material

13 - 705
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Cement t 0.275

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.08

Mason (1st Class0 day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e

(ii) Nominal mix 1:2.5:5 (Hand mixing)

Unit = cum

a) Material

Cement t 0.270

Coarse sand cum 0.48

40 mm aggregate cum 0.48

20 mm aggregate cum 0.24

10 mm aggregate cum 0.08

b) Labour

Mate day 0.09

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 2.00

13 - 706
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Bhisti day 0.27

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

13.12 800 Reinforced Cement Concrete M 25 grade approach slab


including reinforcement and formwork complete as per
drawing and technical specifications Clauses 800 and 1211

A With crushed stone

Unit = cum

a) Material

Reinforced cement concrete M 25 grade

Rate as per Item 13.1 II cum 1.00

HYSD reinforcement

Rate per item 13.2 t 0.05

Rate per cum = (a)

B With Natural Gravel

Unit = cum

a) Material

Reinforced cement concrete M 25 grade

Rate as per Item 13.1 II cum 1.00

HYSD reinforcement

Rate per item 13.2 t 0.05

Rate per cum = (a)

13.13 1200 Providing and laying of an elastomeric slab seal expansion


joint compleate as per approved drawing and approved
specification to be installed by manufacturer/ supplier or
their authorised representative ensuring compliance to the
manufacturers instructuion for instalation and as per
technical specification clause 1207.2.5

Unit = Running m

13 - 707
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Taking output = 7.5 m

a) Material

Elastomeric slab seal expansion joint assembly m 7.50

Add 6% anchorage reinforcement

b) Labour

Mate day 0.04

Mazdoor (Skilled) day 0.40

Mazdoor (Unskilled) day 0.70

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

13.14 1200 Providing and laying of a compression seal consisting of


steel armoured nosing at two edges of the joint gap suitably
anchored to the deck concrete and a preformed chloroprene
elastomer or closed cell foam joint sealer compressed and
formed intothe joint gap with special adhesive binder as per
drawing and technical specification Clause 1207.2.4

Unit = Running m

Taking output = 7.5 m

a) Material

Galvanised angle section 100mmx100mm of 12mm kg 278.78


thickness weldable structural steel as per IS 2062. (2 nos of
7.5 length each @17.7 Kg/m and 5 percent wastage).

Add 6% anchorage reinforcement

Performed continuous elastomer……etc. m 7.50

Add 1% for cost of sealing

b) Labour

Mate day 0.02

13 - 708
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Skilled) day 0.20

Mazdoor (Unskilled) day 0.40

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

13.15 1200 Providing and laying a buried expansion joint, covered with
12 mm thick, 200 mm wide galvanised weldable structrual
steel plate as per IS:2062, placed symmetrical to centre line
of the joint, resting freely over the top surface of the deck
concrete, welding of 8 mm dia, 100 mm long galvanised nails
spaced 300 mm c/c along the centre line of the plate, as per
technical specifications Clauses 1207.2.3

Unit = Running m

Taking output = 7.5 m

a) Material

Galvanised M.S. plate 200 mm wide 12 mm thick @ 94.20 kg 150.00


kg/sqm including 5 per cent wastage.

Add 1 per cent of cost of steel plate for cutting, welding,


consumables and galvanised nails.
b) Labour

Mate day 0.01

Mazdoor (Skilled) day 0.25

Mazdoor (Unskilled) day 0.15

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

13.16 1200 Filler Joint

I) Providing and fixing 2 mm thick corrugated copper plate


in expansion joint as per drawing and technical
specifications Clause 1207.2.2

13 - 709
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = Running m

Taking output = 7.5 m

a) Material

Copper plate - 7.5 m long x 250 mm wide kg 34.00

Area = 7.5 x 0.25 = 1.875 sqm

Weight = 1.875 x 0.002 x 8900 = 33.4 kg.

Wastage @ 2.5% = 0.83 kg.

Total weight = 34 kg

b) Labour

For cutting, bending, carrying and fixing etc.

Mate day 1.00

Mazdoor (Unskilled) day 0.20

Mazdoor (Skilled) day 0.20

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 7.5 m = (a+b+c+d+e+f)

Rate per m = (a+b+c+d+e+f)/7.5

II) Providing and fixing 20 mm thick compressible fibre


board in expansion joint complete as per drawing and
technical specifications

Unit = Running m

Taking output = 7.5 m

a) Material

20 mm thick compressible fibre board 7.5 m long sqm 1.875


and 250 mm deep

Area = 7.5 x 0.25 = 1.875 sqm

b) Labour

For carrying, placing and fixing

13 - 710
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mate day 0.01

Mazdoor (Unskilled) day 0.10

Mazdoor (Skilled) day 0.10

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

III) Providing and fixing 20 mm thick premoulded joint filler


in expansion joint for fixed ends of simply supported
spans, covered with sealant complete as per drawing
and technical specification.

Unit = Running m

Taking output = 7.5 m

a) Material

Premoulded joint filler 7.5 m long, 20 mm thick and sqm 2.250


300 mm deep

Area = 7.5 x 0.30 = 1.875 sqm

b) Labour

For carrying, placing and fixing

Mate day 0.01

Mazdoor (Unskilled) day 0.13

Mazdoor (Skilled) day 0.07

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m = a+b+c+d+e

Rate per m = (a+b+c+d+e)/7.5

IV) Providing and fillling joint sealing compound as per


drawings and technical specifications with coarse sand
and 6 per cent bitumen by weight.

13 - 711
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = Running m

Taking output = 7.5 m

7.5 m long x 100 mm wide x 10 mm deep recess

a) Material

Sand cum 0.008

Volume = 7.5 x 0.1 x 0.01 = 0.008 cum

Weight = 0.008 x 1400 = 11.2 kg

Bitumen-11.2 x 0.06 = 0.672 kg t 0.0001

b) Labour

Mate day 0.02

Mazdoor (Skilled) day 0.25

Mazdoor (Unskilled) day 0.10

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 7.5 m with 10 mm depth =a+b+c+d+e

Rate per m with 1 cm depth = (a+b+c)/7.5

Note: For arriving at the final rate for filler joints per m length and per cm
depth of joint filling compound, the rates of Sr. Nos (i), (ii), (iii) and
(iv) shall be added.

13.17 700 Stone masonry in cement mortar 1:3 for parapet complete as
per drawing and technical specifications Clauses 700 and
1208.4

I. Random rubble masonry

Rate same as in item 12.4 III (i) cum

II. Coursed rubble masonry (1st sort)

Rate same as in item 12.4 I (i) cum

13.18 600 Pointing with cement mortar (1:3) on brickwork in parapet as


per technical specifications Clauses 613.3 and 1208.4

Rate same as in item 12.2 sqm

13 - 712
Sr. Reference to
Description Unit Quantity
No. MORD Spec
13.19 600 Plastering with cement mortar (1:3) 15 mm thick on brickwork
in parapet as per technical specifications Clauses 613.4 and
1208.4

Rate same as in item 12.3 sqm

13.20 800 Providing and laying parapet with PCC M 15 as per drawing &
technical specifications Clauses 800 and 1208.4

A. With crushed stone

I. Nominal mix 1:2.5:5 (Hand mixing)

Rate same as in item 12.5 II (ii) cum

II. Nominal mix (1:2.5:5)

Rate same as in item 12.5 II (i) cum

B. With Natural gravel

I. Nominal mix 1:2.5:5 (Hand mixing)

Rate same as in item 12.5 II (ii) cum

II. Nominal mix (1:2.5:5)

Rate same as in item 12.5 II (i) cum

13.21 1200 Providing bituminous wearing coat comprising of 20 mm


thick premix carpet with 5 mm thick seal coat Type B for
culverts as per drawing and technical specifications Clauses
1206.2 and 500

i. Rate for wearing coat as per item No. 5.9 of Chapter 5 sqm

ii. Rate for seal coat Type B as per item No. 5.12 of Chapter 5 sqm

Note: This type of wearing coat may be adopted where a cushion is


provided over the culvert and the adjoining road pavement is
continued over it.

13.22 1200 Providing bituminous wearing coat comprising of 50 mm


thick bituminous macadam overlaid by 20 mm thick premix
carpet with 5 mm thick seal coat Type B

i. Rate for BM layer may be analysed as per item No 5.3 of cum


Chapter 5
ii. Rate of 20 mm premix carpet wearing course as per item sqm
No.5.9 of Chapter 5

iii. Rate of seal coat Type B as per item No. 5.12 of Chapter 5 sqm

13 - 713
Sr. Reference to
Description Unit Quantity
No. MORD Spec
13.23 600 Brickwork in arches in cement mortar 1:4 complete including
centering and shuttering excluding pointing and plastering
as per drawing and technical specifications Clauses 606 and
1205.1

Unit = cum
a) Material

Brick 1st class Nos. 525.00

Cement mortar (1:4) (Rate same as for item 11.5 II) cum 0.17

b) Labour

Mate day 0.20

Mazdoor (Unskilled) day 1.60

Mason (1st Class) day 2.00


Bhisti day 0.08

c) Add for centering and shuttering @ 110% of (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)


e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f+g

Note: 1 In case cement mortar 1:3 is used, rate as in item 11.5 I. will
hold good.

2 Quantity of bricks for arches will be about 10 per cent more


than that for ordinary brickwork .

3 In case special arch bricks are used, the quantity of bricks


per cum shall be taken as 580 Nos.

4 Rates for spandrel walls shall be taken same as for


brickwork in substructure.

5 Rate for spandrel filling will depend on the filling material


adopted

13.24 700 Coursed rubble stone masonry arch (Ist sort) in cement
mortar (1:4) complete including centering etc. complete as
per drawing and technical specifications Clauses 706 and
1205.1

Unit = cum

a) Material

Stone for CR masonry 1st sort cum 1.10

13 - 714
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Through and bond stone (7 Nos 0.24x0.24x0.39 = 0.16 cum) Nos. 7.00

Cement mortar (Rate as in item 11.5 II) cum 0.30


b) Labour

Mate day 0.25

Mason (1st Class) day 3.00

Mazdoor (Unskilled) day 2.10

Bhisti day 0.08

i For arch above 6m span

c i) Add for centering and shuttering @ 100 % of (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

ii For arch 4m to 6m span

c ii) Add for centering and shuttering @ 80 % of (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Rate per cum = a+b+c+d+e+f

iii) For arch less than 4m span

c iii) Add for centering and shuttering @ 50 % of (a+b)

d) Contractor’s profit & Overheads @ 20% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

13 - 715
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Rate per cum = a+b+c+d+e+f

Note: 1 In case cement mortar 1:3 is used, rate for the same shall be
as per item 11.5 I.

2 The addition for centering and sluttering at (c) above is for


arch above 6 m span. For lesser span length the addition
shall be 80 per cent for span above 4 m length and 50 per
cent for spans less than 4 m.

13.25 800 Providing & Laying reinforced cement concrete arch


complete including centering and shuttering excluding
reinforcement as per drawings and technical specifications
Clauses 800, 900 and 1205.1

Unit = cum
A With crushed stone

I. RCC grade M20 (1:2.4) nominal mix

a) Material

Cement t 0.35

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

i For arch above 6m span

d i) Add for cost of centering and shuttering @ 50 per


cent of (a+b) per sqm of surface of arch soffit

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i))

f) Add GST, LWC etc. @ 0 on (a+b+c+d i))

13 - 716
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Rate per cum = a+b+c+d+e+f

ii Arch 4m to 6m span

d ii) Add for cost of centering and shuttering @ 40 per


cent of (a+b) per sqm of surface of arch soffit

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii))

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii))

Rate per cum = a+b+c+d+e+f

iii) Arch less than 4m span(30%)

d iii) Add for cost of centering and shuttering @ 30 per


cent of (a+b) per sqm of surface of arch soffit

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii))

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii))

Rate per cum = a+b+c+d+e+f

II. RCC Grade M 25

a) Material

Cement t 0.40

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.27

13 - 717
Sr. Reference to
Description Unit Quantity
No. MORD Spec
c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

i For arch above 6m span

d i) Add for cost of centering and shuttering @ 50 per


cent of (a+b) per sqm of surface of arch soffit

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i))

f) Add GST, LWC etc. @ 0 on (a+b+c+d i))

Rate per cum = a+b+c+d+e+f

ii Arch 4m to 6m span

d ii) Add for cost of centering and shuttering @ 40 per


cent of (a+b) per sqm of surface of arch soffit

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii))

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii))

Rate per cum = a+b+c+d+e+f

iii) Arch less than 4m span(30%)

d iii) Add for cost of centering and shuttering @ 30 per


cent of (a+b) per sqm of surface of arch soffit

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii))

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii))

Rate per cum = a+b+c+d+e+f

B With Natural Gravel

I. RCC grade M20 (1:2.4) nominal mix

a) Material

Cement t 0.35

13 - 718
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

i For arch above 6m span

d i) Add for cost of centering and shuttering @ 50 per


cent of (a+b) per sqm of surface of arch soffit

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i))

f) Add GST, LWC etc. @ 0 on (a+b+c+d i))

Rate per cum = a+b+c+d+e+f

ii Arch 4m to 6m span

d ii) Add for cost of centering and shuttering @ 40 per


cent of (a+b) per sqm of surface of arch soffit

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii))

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii))

Rate per cum = a+b+c+d+e+f

iii) Arch less than 4m span(30%)

d iii) Add for cost of centering and shuttering @ 30 per


cent of (a+b) per sqm of surface of arch soffit

13 - 719
Sr. Reference to
Description Unit Quantity
No. MORD Spec
e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii))

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii))

Rate per cum = a+b+c+d+e+f

II. RCC Grade M 25

a) Material

Cement t 0.40

Coarse sand cum 0.45

20 mm aggregate cum 0.54

10 mm aggregate cum 0.36

b) Labour

Mate day 0.08

Mason (1st Class) day 0.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.27

c) Machinery

Concrete mixer 0.4/0.28 cum capacity hour 0.40

i For arch above 6m span

d i) Add for cost of centering and shuttering @ 50 per


cent of (a+b) per sqm of surface of arch soffit

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d i))

f) Add GST, LWC etc. @ 0 on (a+b+c+d i))

Rate per cum = a+b+c+d+e+f

ii Arch 4m to 6m span

d ii) Add for cost of centering and shuttering @ 40 per


cent of (a+b) per sqm of surface of arch soffit

13 - 720
Sr. Reference to
Description Unit Quantity
No. MORD Spec
e) Contractor’s profit & Overheads @ 20% on (a+b+c+d ii))

f) Add GST, LWC etc. @ 0 on (a+b+c+d ii))

Rate per cum = a+b+c+d+e+f

iii) Arch less than 4m span(30%)

d iii) Add for cost of centering and shuttering @ 30 per


cent of (a+b) per sqm of surface of arch soffit

e) Contractor’s profit & Overheads @ 20% on (a+b+c+d iii))

f) Add GST, LWC etc. @ 0 on (a+b+c+d iii))

Rate per cum = a+b+c+d+e+f

Note: The additional cost of centering and shuttering @ 50 per


cent of cost of material and labour shall hold good for arch
spans of 6 m and above. For lesser length of spans, the
corresponding additional cost can be taken as 40 per cent
for spans above 4 m length and 30 per cent for spans less
than 4m.

13.26 1200 Providing steel R.S.Jst/ built-up steel sections including


cutting, welding/ rivetting, hoisting, fixing in position for
composite girders with shear connectors complete with
painting as per drawing and technical specifications Clause
1205.6

A) Steel section

Unit = quintal

Taking output for a typical 6 m long built up section


comprising of of R.S.Js, with connecting plates with shear
connectors

a) Material

R.S.Js 350 m x 200 mm @ 56.9 kg/m

6.0 m x 56.9 kg = 341.4 kg

Add 5 per cent for wastage = 17.87 kg

Total = 358.47 kg

25 cm wide x 12 mm thick plate

13 - 721
Sr. Reference to
Description Unit Quantity
No. MORD Spec
4x6x8.25 = 565.25 kg

Wastage 5 per cent = 28.3 kg

Total = 593.54 kg

Add shear connectors @ 10% = 59 kg

Total = 358.47 +593.5+59 =

1011 kg

Steel fabricated section q 10.11

Rivets 22 mm dia = 240 Nos

Wastage @ 5 per cent = 12 Nos

Total = 252 Nos

Quantity of rivetting @ 1.8 kg per 10 rivets = 45.35 kg q 0.454

Add 5 per cent of cost of material for painting one shop


coat with red oxide primer and three coats of synthetic
enamel and consumables

b) Labour
Fitter day 6.00
Blacksmith day 6.00

Mazdoor (Unskilled) day 12.00

c) Contractor’s profit & Overheads @ 20% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 10.11 q = a+b+c+d+e

Rate per quintal = (a+b+c+d+e)/10.11

Note: i) In case of welded section, welding charges per cm length of


welding shall substitute cost of rivetting

ii) Shear connectors should always be welded to the top flange

iii) The analysis of R.C.C. deck slab for the composite girder to
be adopted from the item 13.1 of concrete superstructure

iv) In the analysis of deck slab for composite girder


superstructure, the component of formwork for the same
shall be 20 per cent of cost of materials, labour and
machinery for deck slab.
v) For spans upto 6 m with height above 5 m extra labour of
mazdoor @ 3.0 days per quintal may be added

13 - 722
Sr. Reference to
Description Unit Quantity
No. MORD Spec
vi) For higher span lengths of different heights following
additional labour for erection of steel girders on
pier/abutment caps may be provided:

Mate day 0.01

Mazdoor (Skilled) day 0.06

Mazdoor (Unskilled) day 0.24

However, it is preferable to analyse the cost of erection of


composite girder type of superstructure for required span
range and height range with a project - specific methodology.

vii) The provision of 10 per cent for shear connectors in the


typical case is tentative. The quantity shall be worked out as
per design.
viii) The cost of painting can also be analysed in detail in
accordance with item 10.6 of Chapter 10

13 - 723
Chapter 13

SUPERSTRUCTURE
Rate
Amount (Rs.)
(Rs.)

6,200.00 2,170.00

950.00 427.50

1,777.00 959.58

1,916.00 689.76

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 40.00

971.90

1,214.88

1,457.86

1,166.28

0.00

13 - 724
Rate
Amount (Rs.)
(Rs.)
6,997.71

1,214.88

0.00

7,289.28

1,263.47

0.00

7,580.85

6,200.00 2,170.00

950.00 427.50

1,777.00 959.58

1,916.00 689.76

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

975.99

1,219.99

1,463.98

13 - 725
Rate
Amount (Rs.)
(Rs.)

1,171.19

0.00

7,027.12

1,219.99

0.00

7,319.92

1,268.79

0.00

7,612.71

6,200.00 2,046.00

950.00 427.50

1,777.00 959.58

1,916.00 689.76

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

954.14

13 - 726
Rate
Amount (Rs.)
(Rs.)
1,192.68

1,431.22

1,144.97

0.00

6,869.83

1,192.68

0.00

7,156.08

1,240.39

0.00

7,442.32

6,200.00 2,480.00

950.00 427.50

1,777.00 959.58

1,916.00 689.76

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

13 - 727
Rate
Amount (Rs.)
(Rs.)

188.00 75.20

1,040.94

1,301.18

1,561.42

1,249.13

0.00

7,494.79

1,301.18

0.00

7,807.08

1,353.23

0.00

8,119.36

6,200.00 2,666.00

950.00 427.50

1,777.00 959.58

1,916.00 689.76

13 - 728
Rate
Amount (Rs.)
(Rs.)

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

1,078.14

1,347.68

1,617.22

1,293.77

0.00

7,762.63

1,347.68

0.00

8,086.08

1,401.59

0.00

8,409.52

13 - 729
Rate
Amount (Rs.)
(Rs.)

6,200.00 2,170.00

950.00 427.50

1,463.00 790.02

1,364.00 491.04

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 40.00

898.25

1,122.81

1,347.37

1,077.90

0.00

6,467.38

1,122.81

0.00

6,736.86

1,167.72

13 - 730
Rate
Amount (Rs.)
(Rs.)
0.00

7,006.33

6,200.00 2,170.00

950.00 427.50

1,463.00 790.02

1,364.00 491.04

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

902.33

1,127.92

1,353.50

1,082.80

0.00

6,496.80

1,127.92

0.00

13 - 731
Rate
Amount (Rs.)
(Rs.)
6,767.50

1,173.03

0.00

7,038.20

6,200.00 2,046.00

950.00 427.50

1,463.00 790.02

1,364.00 491.04

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

880.49

1,100.61

1,320.73

1,056.59

0.00

6,339.51

13 - 732
Rate
Amount (Rs.)
(Rs.)

1,100.61

0.00

6,603.66

1,144.63

0.00

6,867.80

6,200.00 2,480.00

950.00 427.50

1,463.00 790.02

1,364.00 491.04

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

967.29

1,209.11

1,450.93

13 - 733
Rate
Amount (Rs.)
(Rs.)

1,160.75

0.00

6,964.47

1,209.11

0.00

7,254.66

1,257.47

0.00

7,544.84

6,200.00 2,666.00

950.00 427.50

1,463.00 790.02

1,364.00 491.04

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

13 - 734
Rate
Amount (Rs.)
(Rs.)

1,004.49

1,255.61

1,506.73

1,205.39

0.00

7,232.31

1,255.61

0.00

7,533.66

1,305.83

0.00

7,835.00

13 - 735
Rate
Amount (Rs.)
(Rs.)

40,763.00 42,801.15

80.00 640.00

356.65 156.93

458.55 1,375.65

244.56 1,956.48

9,386.04

0.00

56,316.25

34,492.00 36,216.60

80.00 640.00

356.65 156.93

458.55 1,375.65

244.56 1,956.48

8,069.13

0.00

48,414.79

13 - 736
Rate
Amount (Rs.)
(Rs.)

41,525.00 43,601.25

80.00 640.00

356.65 156.93

458.55 1,375.65
244.56 1,956.48

9,546.06

0.00

57,276.37

6,200.00 2,666.00

950.00 427.50

1,777.00 959.58

1,916.00 689.76

56,316.25 4,223.72

80.00 0.80

356.65 35.67

13 - 737
Rate
Amount (Rs.)
(Rs.)
458.55 55.03

244.56 733.68

244.56 66.03

458.55 137.57

188.00 75.20

269.02

2,067.91

0.00

12,407.46

6,200.00 2,666.00

950.00 427.50

1,463.00 790.02

1,364.00 491.04

56,316.25 4,223.72

80.00 0.80

356.65 35.67

458.55 55.03

244.56 733.68

244.56 66.03

458.55 137.57

188.00 75.20

13 - 738
Rate
Amount (Rs.)
(Rs.)
257.97

1,992.04

0.00

11,952.26

5,751.54 35,958.62

42,801.15 59,921.61

19,176.05

0.00

115,056.28

2,397.01

13 - 739
Rate
Amount (Rs.)
(Rs.)
6,200.00 2,480.00

950.00 427.50

1,777.00 959.58

1,916.00 689.76

356.65 28.53

458.55 55.03

244.56 423.09

244.56 66.03

188.00 75.20

546.82

5,751.54

60,000.00 176,760.00

60,000.00 60,720.00

41,525.00 7,474.50

80,000.00 12,000.00

356.65 998.62

458.55 13,756.50

244.56 9,782.40

13 - 740
Rate
Amount (Rs.)
(Rs.)
12,847.73

2,569.55

2,569.55

59,895.77

0.00

3,593.75

60,000.00 7,800.00

131.00 7,860.00

80,000.00 4,000.00

983.00

196.60

356.65 199.72

458.55 2,751.30

13 - 741
Rate
Amount (Rs.)
(Rs.)
244.56 1,956.48

5,149.42

0.00

30,896.52

1,544.83

8.00 4,000.00

3,607.43 757.56

356.65 32.10

458.55 366.84

244.56 391.30

244.56 48.91

1,119.34

0.00

6,716.05

70.00 280.00

900.00 900.00

13 - 742
Rate
Amount (Rs.)
(Rs.)
356.65 7.13

458.55 9.17

244.56 48.91

356.65 3.57

458.55 4.59

244.56 48.91

65.11

273.48

0.00

1,640.87

6,200.00 1,705.00

950.00 456.00

1,500.00 720.00

1,777.00 426.48

1,916.00 153.28

356.65 28.53

458.55 45.86

244.56 398.63

13 - 743
Rate
Amount (Rs.)
(Rs.)
244.56 66.03

188.00 75.20

815.00

0.00

4,890.01

6,200.00 1,674.00

950.00 456.00

1,500.00 720.00

1,777.00 426.48

1,916.00 153.28

356.65 32.10

458.55 45.86

244.56 489.12

244.56 66.03

812.57

0.00

4,875.44

13 - 744
Rate
Amount (Rs.)
(Rs.)
6,200.00 1,705.00

950.00 456.00

1,221.00 586.08

1,463.00 351.12

1,364.00 109.12

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

188.00 75.20

764.31

0.00

4,585.89

6,200.00 1,674.00

950.00 456.00

1,221.00 586.08

1,463.00 351.12

1,364.00 109.12

356.65 32.10

458.55 45.86

244.56 489.12

13 - 745
Rate
Amount (Rs.)
(Rs.)
244.56 66.03

761.88

0.00

4,571.31

7,494.79 7,494.79

56,316.25 2,815.81

10,310.61

6,964.47 6,964.47

56,316.25 2,815.81

9,780.28

13 - 746
Rate
Amount (Rs.)
(Rs.)

12,300.00 92,250.00

5,535.00

356.65 14.27

356.65 142.66

244.56 171.19

19,622.62

0.00

117,735.74

15,698.10

350.00 97,573.00

5,854.38

9.21 69.08

0.69

356.65 8.56

13 - 747
Rate
Amount (Rs.)
(Rs.)
356.65 71.33

244.56 97.82

20,734.97

0.00

124,409.83

16,587.98

70.00 10,500.00

105.00

356.65 3.57

356.65 89.16

244.56 36.68

2,146.88

0.00

12,881.30

1,717.51

13 - 748
Rate
Amount (Rs.)
(Rs.)

160.00 5,440.00

356.65 356.65

244.56 48.91

356.65 71.33

1,183.38

0.00

7,100.27

946.70

976.00 1,830.00

13 - 749
Rate
Amount (Rs.)
(Rs.)
356.65 3.57

244.56 24.46

356.65 35.67

12.74

0.00

1,906.43

254.19

732.00 1,647.00

356.65 3.57

244.56 31.79

356.65 24.97

12.06

0.00

1,719.39

229.25

13 - 750
Rate
Amount (Rs.)
(Rs.)

850.00 6.80

39,783.00 3.98

356.65 7.13

356.65 89.16

244.56 24.46

26.31

0.00

157.84

21.04

5,414.72

4,877.97

583.53

13 - 751
Rate
Amount (Rs.)
(Rs.)

1,211.68

5,379.01

5,403.90

5,069.36

5,044.47

13 - 752
Rate
Amount (Rs.)
(Rs.)

8.00 4,200.00

2,739.43 465.70

356.65 71.33

244.56 391.30

458.55 917.10
244.56 19.56

6,671.49

2,547.30
0.00

15,283.79

1,135.00 1,248.50

13 - 753
Rate
Amount (Rs.)
(Rs.)
54.00 378.00

2,739.43 821.83

356.65 89.16

458.55 1,375.65

244.56 513.58

244.56 19.56

4,446.28

1,778.51

0.00

10,671.08

3,557.03

1,600.66

0.00

9,603.97

2,223.14

1,333.89

0.00

13 - 754
Rate
Amount (Rs.)
(Rs.)

8,003.31

6,200.00 2,170.00

950.00 427.50

1,777.00 959.58

1,916.00 689.76

356.65 28.53

458.55 91.71

244.56 440.21

244.56 66.03

188.00 75.20

2,474.26

1,484.56

0.00

13 - 755
Rate
Amount (Rs.)
(Rs.)

8,907.34

1,979.41

1,385.59

0.00

8,313.52

1,484.56

1,286.62

0.00

7,719.69

6,200.00 2,504.80

950.00 427.50

1,777.00 959.58

1,916.00 689.76

356.65 28.53

458.55 91.71

244.56 440.21

244.56 66.03

13 - 756
Rate
Amount (Rs.)
(Rs.)

188.00 75.20

2,641.66

1,585.00

0.00

9,509.98

2,113.33

1,479.33

0.00

8,875.98

1,585.00

1,373.66

0.00

8,241.98

6,200.00 2,170.00

13 - 757
Rate
Amount (Rs.)
(Rs.)
950.00 427.50

1,463.00 790.02

1,364.00 491.04

356.65 28.53

458.55 91.71

244.56 440.21

244.56 66.03

188.00 75.20

2,290.12

1,374.07

0.00

8,244.43

1,832.10

1,282.47

0.00

7,694.81

1,374.07

13 - 758
Rate
Amount (Rs.)
(Rs.)
1,190.86

0.00

7,145.18

6,200.00 2,504.80

950.00 427.50

1,463.00 790.02

1,364.00 491.04

356.65 28.53

458.55 91.71

244.56 440.21

244.56 66.03

188.00 75.20

2,457.52

1,474.51

0.00

8,847.07

1,966.02

13 - 759
Rate
Amount (Rs.)
(Rs.)
1,376.21

0.00

8,257.27

1,474.51

1,277.91

0.00

7,667.46

13 - 760
Rate
Amount (Rs.)
(Rs.)

6,000.00 60,660.00

8,000.00 3,632.00

3,214.60

458.55 2,751.30
458.55 2,751.30

244.56 2,934.72

15,188.78

0.00

91,132.70

9,014.12

13 - 761
Rate
Amount (Rs.)
(Rs.)

356.65 3.57

356.65 21.40

244.56 58.69

13 - 762
Chapter 14

PROTECTION WORKS
Sr. Reference to
Description Unit Quantity
No. MORD Spec
14.1 1300 Providing and laying boulder apron for bed protection with
stone boulders of minimum size and weight as per Table
1300.1, no fragment weighing less than 25 kg laid dry complete
as per drawing and technical specifications Clause 1301

Unit = cum

a) Material

Stone boulder (25 kg minimum) cum 1.00

Stone spalls cum 0.20

b) Labour

Mate day 0.04

Mason 1st Class day 0.35

Mazdoor (Unskilled) day 0.75

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

Note: Nominal excavation required for preparation of bed has been taken
into account while making provisions for labour.

14.2 1300 Providing and laying of boulder apron laid in wire crates with 4
mm dia GI wire conforming to IS:280 and IS:4826 in 100 mm x
100 mm mesh (woven diagonally) including 10 per cent extra
for laps and joints laid with stone boulders weighing not less
than 25 kg each as per drawing and technical specifications
Clause 1301

Unit = cum

Taking ouput = 3 m x 1.5 m x 1.25 m = 5.63 cum

a) Material

Stone boulder (25 kg minimum) cum 5.63

Stone spalls cum 1.13

GI wires 4 mm dia @ 32 kg/10 sqm kg 64.00

14 - 763
Sr. Reference to
Description Unit Quantity
No. MORD Spec
b) Labour

Mate day 0.18

Mazdoor (Skilled) day 1.50

Mazdoor (Unskilled) day 3.00

Add for labour for weaving the wire crates @ 2 per cent of cost
of GI wire

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 5.63 cum = a+b+c+d+e

Rate per cum = (a+b+c+d+e)/5.63

Note: 1 Nominal cost of trimming for preparation of bed has been


included in the cost of labour

2 The analysis will by & large hold good for gabions

14.3 1300 Providing and laying of apron with cement concrete blocks of
size as per Table 1300.1 cast-in-situ and made with nominal mix
of M-15 grade cement concrete as per drawing and technical
specifications Clause 1301

Unit = cum

a) Concrete grade M 15

(Rate as per item No 11.4 II (i) cum 0.98

Add 2 per cent of cost to account for excavation for


preparation of bed, nominal surface reinforcement and filling
of granular material in recesses between blocks.

Rate per cum = (a)

14.4 1300 Single bamboo palasiding / walling of whole 2nd class bamboo
(Jati or Bethua) 75mm dia and closely packed & driven
including fitting fixing with half bamboo kamis horizontally in
three rows with cane or tying with wire complete and struts 1.5
m apart longitudinally and providing brush wood as per
drawing and technical specifications Clause 1302.5

A) Driven at least 900 mm below ground and 1200 mm above


ground

Unit = Running metre

Taking Output = 3.00 metre

14 - 764
Sr. Reference to
Description Unit Quantity
No. MORD Spec
a) Materials

2nd Class Bamboo 65 mm to 75 mm dia, (1.2 m to 3.0 nos. 15.00


m)
Binding Wire kg 0.15

Brush Wood (LS Rs.10.00) LS

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 1.00

c) Sundries (LS Rs.5.00) LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3 metre = a+b+c+d+e+f

Rate per metre = (a+b+c+d+e+f) / 3.00

B) Driven at least 900 mm below ground and 900 mm above


ground on average

a) Materials

2nd Class Bamboo 65 mm to 75 mm dia, (1.8 m-2.5 m) nos. 14.00


long

Binding Wire kg 0.15

Brush Wood (LS Rs.10.00) LS

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 1.00

c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3 m = a+b+c+d+e+f

Rate per m = (a+b+c+d+e+f) / 3.00

14 - 765
Sr. Reference to
Description Unit Quantity
No. MORD Spec
14.5 1300 Providing and laying pitching on slopes laid over prepared
filter media as per drawing and technical specifications Clause
1302

I. Stone/Boulder

Unit = cum

a) Material

Stone boulder (25 kg minimum) cum 1.00

Stone spalls of minimum 25 mm size cum 0.20

b) Labour

Mate day 0.04

Mason 1st Class day 0.35

Mazdoor (Unskilled) day 0.75

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = (a+b+c+d+e)

II. Cement concrete blocks of size as per Table 1300.2 cast


in cement concrete of grade M 15

a) Concrete grade M 15

(Rate as per item No. 11.4 II (i)except that the size of cum 1.00
aggregate shall be 20 mm & down

Add 2 per cent of cost to account for surface


reinforcement and filling of granular material in recesses
between blocks

Rate per cum = (a)

III. Brick pitchng set in cement mortar 1:4

Unit = cum

a) Material

Bricks Nos. 500.00

Cement mortar 1:4 (Rate as in item 11.5 II) cum 0.13

b) Labour

14 - 766
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mate day 0.10

Mason 1st Class day 0.80

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = (a+b+c+d+e)

14.6 1300 Providing and laying filter material underneath pitching in


slopes complete as per drawing and technical specifications
Clause 1302

Unit = cum

a) Material

Graded stone aggregate of required size cum 1.20

b) Labour

Mate day 0.05

Mazdoor (Skilled) day 0.25

Mazdoor (Unskilled) day 1.02

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

Note: Labour cost includes labour required for trimming of slope to proper
profile and preparation of bed.

14.7 1300 Providing and laying flooring laid over cement concrete
bedding complete as per drawing and technical specification
Clause 1303

I. Rubble stone laid in cement mortar 1:3

Unit = cum

a) Material

i. Cement mortar (1:3) (For rate refer to item 11.5 (I) cum 0.13

14 - 767
Sr. Reference to
Description Unit Quantity
No. MORD Spec
ii. Add for cement concrete bedding (M 10) nominal cum 0.2
mix) (For rate refer to item 11.4 I (i)

* Quantity shall be adopted as per design.

Add 1 per cent of cost to account for excavation for


preparation of bed

iii. Stone for rubble flooring 150 mm thick cum 1.00

iv. Stone spalls cum 0.20

b) Labour

Mate day 0.08

Mason 1st Class day 0.50

Mazdoor (Unskilled) day 1.50

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

Note: Quantity of cement mortar is inclusive of mortar for laying and filling
of joints.

II. Cement conrete blocks grade M 15

Cement concrete blocks grade M 15 cum 0.90


(Rate as per item 11.4 (II) (i)

Add for cement concrete bedding cum 0.20


Rate as per item 11.4 (II) (i)

* Quantity shall be adopted as per design.

Add 1 per cent of cost to account for excavation for


preparation of bed.

Rate per cum

III. Brick on edge laid in cement mortar (1:3)

Unit=cum

a) Material

i Bricks Nos 300.00

ii Cement mortar (1:3) [(Rate as in item 11.5 (i)] cum 0.15

iii Cement mortar bedding (1:5) [(Rate as in itm 12.1 (iii)] cum 0.25

14 - 768
Sr. Reference to
Description Unit Quantity
No. MORD Spec
b. Labour

Mate day 0.10

Mason 1st Class day 0.80

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20

c) Contractor’s profit & Overheads @ 12.5% on (a i+b)

d) Add GST, LWC etc. @ 0 on (a i+b)

Rate per cum = a+b+c+d+e

14.8 1303 Providing and laying of dry rubble flooring complete as per
drawings and technical specifications Clause 1303.3

Unit = cum

a) Material

Stone for rubble flooring 150 mm thick cum 1.00

Stone spalls cum 0.20

b) Labour

Mate day 0.10

Mason 1st Class day 0.50

Mazdoor (Unskilled) day 1.50

Add 1 per cent of (b) for trimming and preparation of base

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

14.9 1300 Providing and laying curtain walls complete as per drawing and
technical specification Clause 1304

Unit = cum

I. Brick masonry in cement mortar (1:4)

(Rate same as per item 11.5 (II) cum 1.10

14 - 769
Sr. Reference to
Description Unit Quantity
No. MORD Spec
II. Coursed rubble masonary (2nd sort) in cement mortar (1:4)

(Rate same as per item 12.4 II (ii) ) cum 1.00

III. Cement concrete grade M 10

(Rate same as per item 11.4 I (i) cum 0.95

Note: 1 Other items like excavation for foundation, filling behind wall,
filter media, weep holes, etc. shall be added separately as per
approved design.

2 For this item, where reference has been made to items


analysed in other Chapters, i.e., 11, 12 & 13, the overheads
shall be taken as 15 per cent instead of 20 per cent

14.10 1300 Construction of flexible apron 1 m thick comprising of loose


stone boulders weighing not less then 25 kg beyond curtain
wall

Unit = cum

a) Material

Stone boulder cum 0.65

Stone spalls cum 0.20

b) Labour

Mate day 0.05

Mason 1st Class day 0.25

Mazdoor (Unskilled) day 1.00

Add: 1 per cent of cost of (a+b) for trimming and preparation


of bed

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

14.11 1300 Construction of toe walls for protection of slopes as per


drawing and technical specifications Clause 1302.5

I. Random rubble masonry in case of stone pitching laid


with cement mortar (1:5)

(iii) In cement mortar (1:5)

Unit = cum

a) Material

14 - 770
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Stone for RR masonry cum 1.00

Through and bond stone Nos. 7.00


(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate same as in item 12.1 III) cum 0.31

b) Labour

Mate day 0.12

Mason 1st Class day 1.20

Mazdoor (Unskilled) day 1.80

Bhisti day 0.08

Add for scaffolding @ 5 per cent on (a+b)

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c

Note: For height less than 3 m, dry rubble masonry can also be used. In
that case, the sub-item of cement mortar may be omitted in the
analysis.

II. Brick masonry in cement mortar 1:4 in case of brick


pitching

Unit = cum
a) Material
Brick Nos. 450.00
Cement mortar 1:4 cum 0.19

Rates as per sub-analysis


b) Labour
Mate day 0.09
Mason (1st Class) day 0.80

Mazdoor (Unskilled) day 1.60

Bhisti day 0.20


c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per cum = a+b+c+d+e

Sub-analysis

14 - 771
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Cement mortar 1:4 (1 cement : 4 sand)
Unit = cum

a) Material
Cement t 0.38

Sand cum 1.05


b) Labour
Mate day 0.04
Mazdoor (Unskilled) day 0.90

Bhisti day 0.08

Total material and labour = (a+b)

III. Cement concrete grade M 10 in case of concrete block


pitching
Unit = cum

I. P.C.C grade M 20

(i) Nominal mix 1:3:6

Unit = cum

a) Material

Cement t 0.250

Coarse sand cum 0.48

40 mm aggregate cum 0.576

20 mm aggregate cum 0.288

10 mm aggregate cum 0.096

b) Labour

Mate day 0.08

Mason (1st Class) day 0.10

Mazdoor (Unskilled) day 1.63

Bhisti day 0.27

c) Machinery

14 - 772
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mechnical concrete mixer 0.4/0.28 cum capacity hour 0.40
fitted with water measuring device and preferably
also with load cell.

d) Formwork @ 4% on cost of material, labour and


machinery (a+b+c)
e) Contractor’s profit & Overheads @ 12.5% on (a+b+c+d)
f) Add GST, LWC etc. @ 0 on (a+b+c+d)

Rate per cum = a+b+c+d+e+f+g

14.12 1300 Single bamboo spur and palisading of whole 2nd class bamboo
(jati or Bethua) 65 mm to 75 mm dia and closely packed &
driven, including fitting, fixing with half bamboo kamis
horrizontally in three rows with cane or tying wire complete and
struts 1500 mm apart longitudinally and providing brush wood
as per drawing and technical specifications Clause 1302.5

A) Driven at least 900 mm below ground and 1800 mm above


ground on average
Unit = Running metre
Taking output = 3.00 metre

a) Materials

2nd class bamboo (65 mm to 75 mm dia 3 m long) Nos 18.00

Binding wire Kg. 0.15

Brush Wood (LS Rs.10.00) LS

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 1.00

c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3 metre = a+b+c+d+e+f

Rate per metre = (a+b+c+d+e+f)/3

B) Driven at least 900 mm below ground and 900 mm above


ground on average

14 - 773
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = Running metre

Taking output = 3.00 metre

a) Materials

2nd class bamboo (65 mm to 75 mm dia 2 m long) Nos 14.00

Binding wire Kg. 0.15

Brush Wood (LS Rs.10.00) LS

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 1.00

c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3.00 metre = a+b+c+d+e+f

Rate per metre = (a+b+c+d+e+f)/3

14.13 Suggestive Single bamboo spur and palisading of whole 1st class bamboo
(Bholuka or Barua) 85 mm to 100 mm dia. Closely packed &
driven including fitting, fixing with half 2nd class bamboo (jati
or Bethua) horizontally in three rows with cane or tying wire
complete and struts 1500 mm apart longitudinally and
providing brush wood in the spur as per drawings and
technical specifications

A) Driven at least 900 mm below ground and 1800 mm above


ground
Unit = Running metre
Taking output = 3.00 metre

a) Materials

1st class bamboo (85 mm - 100 mm dia) 3.0 long Nos 15.00

2nd class bamboo (85-100 mm dia 3.0 long) Nos 2.00

Binding wire Kg. 0.15

14 - 774
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Brush Wood (LS Rs.10.00) LS

b) Labour

Mate day 0.05

Mazdoor (Unskilled) day 1.20

c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3 metre = a+b+c+d+e+f

Rate per metre = (a+b+c+d+e+f)/3

B) Driven at least 900 mm below ground and 900 mm above


ground on average

Unit = Running metre

Taking output = 3.00 metre

a) Materials

1st class bamboo (85-100 m dia, 2.0m long) Nos 10.00

2nd class bamboo (85-100 mm dia, 2.0 m long) Nos 1.50

Binding wire Kg. 0.15

Brush Wood (LS Rs.10.00) LS

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 1.00

c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3.00 metre = a+b+c+d+e+f

Rate per metre = (a+b+c+d+e+f)/3.00

14 - 775
Sr. Reference to
Description Unit Quantity
No. MORD Spec
C) Driven at least 600 mm below ground and 1200 mm above
ground on average.

Unit = Running metre

Taking output = 3.00 metre

a) Materials

1st class bamboo (85-100 m dia, 2.0m long) Nos 9.00

2nd class bamboo (85-100 mm dia, 2 m long0 Nos 1.50

Binding wire Kg. 0.15

Brush Wood (LS Rs.10.00) LS

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 1.00

c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3 m = a+b+c+d+e+f

Rate per m = (a+b+c+d+e+f)/3

14.14 Suggestive Bamboo spur 'A' type with whole bamboo 85mm-100mm dia,
placed 230 mm centre to centre driven 900 mm below ground
and 1200 mm to 1500 mm above ground tied with 2nd class
bamboo (jati or Bethua) on either side at 450 mm apart
horizontally with galvanised wire etc. complete as per drawings
and technical specifications

A) 2nd class bamboo (jati or Bethua) 75 mm dia

Unit= Running metre

Taking output = 3.00 metre

a) Materials

2nd class bamboo (85-100 mm dia, 2.5 m long) Nos 14.00

2nd class bamboo (85-100 mm dia, 2.5 long) Nos 4.00

14 - 776
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Binding wire Kg. 0.75

b) Labour

Mate day 0.04

Mazdoor (Unskilled) day 1.00

c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3 m = a+b+c+d+e+f

Rate per metre = (a+b+c+d+e+f)/3

B) 1st class bamboo (Bholuka or Barua ) 85 mm to 100 mm dia


Unit = Running metre

Taking output = 3.00 metre

a) Materials

1st class bamboo (85-100 mm dia, 2.5 m long) Nos 7.00

2nd class bamboo (85-100 mm dia, 2.5 long) Nos 4.00

Binding wire Kg. 1.00

Brush Wood (LS Rs.10.00) LS

b) Labour

Mate day 0.06

Mazdoor (Unskilled) day 1.40

c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3 m = a+b+c+d+e+f

Rate per metre = (a+b+c+d+e+f)/3

14 - 777
Sr. Reference to
Description Unit Quantity
No. MORD Spec
14.15 Suggestive Providing 'A' type single spur with 1st class bamboo (Bholuka
or Barua) 85 mm to 100 mm dia. Driven closely placed 3m to 4m
above ground and 1200 mm to 1500 mm below ground tied
with cane or coir string, half 2nd class bamboo (jati or Bethua)
horizontally on both face placed not more than one metre apart
including whole bamboo struts inside one metre apart and 2
nos. of purlin at top and bottom fitted with vertical struts at
1500 mm apart and filling with brushwood or jungle wood
inside the spur complete as per drawing and technical
specifications

Unit= Running metre

Taking output = 3.00 metre


a) Materials

1st class bamboo (85-100 mm dia, 4.5-5.5 m long) Nos 15.00

2nd class bamboo (85-100 mm dia, 3.0 m long) Nos 6.00

Binding wire Kg. 2.00

Brush wood (LS Rs.10.00) LS

b) Labour

Mate day 0.06

Mazdoor (Unskilled) day 1.50

c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 3 metre = a+b+c+d+e+f

Rate per metre = (a+b+c+d+e+f)/3

14.16 1300 Providing close bamboo toe walling consisting of 65mm to


75mm dia bamboos of length ranging from 1.2 m to 3m driven
at 150 mm centre to centre and provided with three horizontal
split bamboo runner fixed with nails. All bamboos to be duly
protected by coal tar painting.

Unit = Running Metre

Taking output = 10.00 running metre

a) Materials

2nd class bamboo (65mm-75mm dia and average 2.1 m Nos 67.00
length)

14 - 778
Sr. Reference to
Description Unit Quantity
No. MORD Spec
2nd class bamboo (65mm-75mm dia and 3 m length) Nos 6.00

Coal tar kg 10.00

b) Labour

Mate day 0.06

Mazdoor (Unskilled) day 1.50


c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 10 Running Metre = a+b+c+d+e+f

Rate per Sqm = (a+b+c+d+e+f)/10

14.17 Suggestive Double timber spur with two rows at 800 mm c/c apart of 1st
class local wood piles with timber of Azar/Nahar/Nageswar /
Zarul wood 150 mm to 200 mm dia driven 2000 mm minimum
below ground and 3600 mm above ground average placed at
800 mm belts, bracings etc. of 100 mm x 75 mm size 1st class
local wood longitudinally & crosswiswe at ends fitted with 10
mm dia bolts and nuts etc. including coaltarring of timber
members and cost of necessary bamboo stagings etc. as
directed by the Engineer as per drawing and technical
specifications

Unit =RM

Taking output = 4.00 RM

a) Material

1st class local wood piles 150-200 mm dia, 6m long nos 68.00

1st class local wood (100 mm x 75 mm) for collar, bracing and cum 0.404
belt

Nuts and Bolts Kg 10.00

1st Class Bamboo Nos 5.00

2nd class bamboo Nos 5.00

Coir rope LS

Coal tar LS

b) Labour

14 - 779
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Carpenter 1st Class Nos 1.20

Mate Nos 1.20

Mazdoor (Unskilled) Nos 30.00

c) Sundries LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 4 RM = (a+b+c+d+e+f)

Rate per metre = (a+b+c+d+e+f)/4

14.18 Suggestive Supplying and filling up hollows of the timber spur to an


average height of 3600 mm above ground with jungle wood
branches as per drawing and technical specifications as
directed by the Engineer.

Unit = RM

Taking output = 20.00 RM

a) Labour

Mazdoor (Unskilled) day 5.00

b) Sundries LS

c) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

d) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 20 RM = (a+b+c+d+e)

Rate per metre = (a+b+c+d+e)/20

14 - 780
Chapter 14

ROTECTION WORKS
Rate
Amount (Rs.)
(Rs.)

644.00 644.00

987.00 197.40

356.65 14.27

458.55 160.49

244.56 183.42

149.95

0.00

1,349.53

644.00 3,625.72

987.00 1,115.31

75.00 4,800.00

14 - 781
Rate
Amount (Rs.)
(Rs.)

356.65 64.20

356.65 534.98

244.56 733.68

26.66

1,362.57

0.00

12,263.11

2,178.17

5,085.61 4,963.56

99.27

5,062.83

14 - 782
Rate
Amount (Rs.)
(Rs.)

120.00 1,800.00

80.00 12.00

10.00

356.65 14.27

244.56 244.56

5.00

260.73

0.00

2,346.55

782.18

120.00 1,680.00

80.00 12.00

10.00

0.00

356.65 14.27

244.56 244.56

5.00

245.73

0.00

2,211.55

737.18

14 - 783
Rate
Amount (Rs.)
(Rs.)

644.00 644.00

987.00 197.40

356.65 14.27

458.55 160.49

244.56 183.42

149.95

0.00

1,349.53

5,085.61 5,085.61

101.71

5,187.33

8.00 4,000.00

2,739.43 356.13

14 - 784
Rate
Amount (Rs.)
(Rs.)
356.65 35.67

458.55 366.84

244.56 391.30

244.56 48.91

649.85

0.00

5,848.69

1,013.00 1,215.60

356.65 17.83

356.65 89.16

244.56 249.45

196.51

0.00

1,768.55

3,607.43 468.97

14 - 785
Rate
Amount (Rs.)
(Rs.)
5,216.59 1,043.32

15.12

1,135.00 1,135.00

987.00 197.40

356.65 28.53

458.55 229.28

244.56 366.84

246.52

0.00

3,730.98

5,085.61 4,577.05

5,085.61 1,017.12

55.94

5,650.12

8.00 2,400.00

3,607.43 541.12

2,615.43 653.86

14 - 786
Rate
Amount (Rs.)
(Rs.)

356.65 35.67

458.55 366.84

244.56 391.30

244.56 48.91

405.34

0.00

4,843.03

1,135.00 1,135.00

987.00 197.40

356.65 35.67

458.55 229.28

244.56 366.84

6.32

246.31

0.00

2,216.81

6,464.44 7,110.88

14 - 787
Rate
Amount (Rs.)
(Rs.)

4,443.66 4,443.66

5,216.59 4,955.76

644.00 418.60

987.00 197.40

356.65 17.83

458.55 114.64

244.56 244.56

9.93

125.37

0.00

1,128.33

14 - 788
Rate
Amount (Rs.)
(Rs.)
1,135.00 1,135.00

54.00 378.00

2,615.43 810.78

356.65 42.80

458.55 550.26

244.56 440.21

244.56 19.56

168.83

443.18

0.00

3,988.63

8.00 3,600.00
3,502.43 665.46

356.65 32.10
458.55 366.84

244.56 391.30

244.56 48.91
638.08

0.00

5,742.69

14 - 789
Rate
Amount (Rs.)
(Rs.)

6,200.00 2,356.00

850.00 892.50

356.65 14.27
244.56 220.10

244.56 19.56

3,502.43

6,200.00 1,550.00

950.00 456.00

1,500.00 864.00

1,777.00 511.78

1,916.00 183.94

356.65 28.53

458.55 45.86

244.56 398.63

244.56 66.03

14 - 790
Rate
Amount (Rs.)
(Rs.)
188.00 75.20

167.20

543.40
293.43

5,183.99

120.00 2,160.00

80.00 12.00

10.00

356.65 14.27

244.56 244.56

5.00

305.73

0.00

2,751.55

917.18

14 - 791
Rate
Amount (Rs.)
(Rs.)

120.00 1,680.00

80.00 12.00

10.00

356.65 14.27

244.56 244.56

15.00

246.98

0.00

2,222.80

740.93

200.00 3,000.00

120.00 240.00

80.00 12.00

14 - 792
Rate
Amount (Rs.)
(Rs.)
10.00

356.65 17.83

244.56 293.47

10.00

447.91

0.00

4,031.22

1,343.74

200.00 2,000.00

120.00 180.00

80.00 12.00

10.00

356.65 14.27

244.56 244.56

10.00

308.85

0.00

2,779.68

926.56

14 - 793
Rate
Amount (Rs.)
(Rs.)

200.00 1,800.00

120.00 180.00

80.00 12.00

10.00

356.65 14.27

244.56 244.56

10.00

283.85

0.00

2,554.68

851.56

120.00 1,680.00

120.00 480.00

14 - 794
Rate
Amount (Rs.)
(Rs.)
80.00 60.00

356.65 14.27

244.56 244.56

50.00

316.10

0.00

2,844.93

948.31

200.00 1,400.00

120.00 480.00

80.00 80.00

10.00

356.65 21.40

244.56 342.38

50.00

297.97

0.00

2,681.76

893.92

14 - 795
Rate
Amount (Rs.)
(Rs.)

200.00 3,000.00

120.00 720.00

80.00 160.00

356.65 21.40

244.56 366.84

50.00

539.78

0.00

4,858.02

1,619.34

120.00 8,040.00

14 - 796
Rate
Amount (Rs.)
(Rs.)
120.00 720.00

39.78 397.83

356.65 21.40

244.56 366.84
50.00

1,199.51

0.00

10,795.58

1,079.56

1,000.00 68,000.00

13,992.00 5,652.77

80.00 800.00

200.00 1,000.00

120.00 600.00

50.00

50.00

14 - 797
Rate
Amount (Rs.)
(Rs.)
458.55 550.26

356.65 427.98

244.56 7,336.80

50.00

10,564.73

0.00

95,082.53

23,770.63

244.56 1,222.80

20.00

155.35

0.00

1,398.15

69.91

14 - 798
Chapter 15

MAINTENANCE OF ROADS
Sr. Reference to
Description Unit Quantity
No. MORD Spec
15.1 1900 Restoration of Rain Cuts

Restoration of rain cuts with soil, moorum gravel or a mixture


of these, clearing the loose soil, benching for 300mm width
laying fresh material in layers not exceeding 250 mm and
compaction with plate compactor or power rammer to restore
the original alignment, level and slopes as per drawings and
technical specifications Clause 1902

A. Manual Means

Unit = cum

Taking output = 10 cum

a) Labour

Mate day 0.24

Mazdoor (Unskilled) day 3.50

b) Machinery

Plate compactor hour 1.00

c) Materials

Compensation for earth Taken from private land cum

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 10 cum = a+b+c+d+e+f

Rate per cum = a+b+c+d+e+f/10

B. Mechanical Means

Unit = cum

Taking output = 50 cum


a) Labour

Mate day 0.40

Mazdoor (Unskilled) day 5.00

b. Machinery

15 - 799
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Hydraulic Excavator 0.9 cum bucket capacty @ 60 hour 0.73
cum/h

Tipper 5.5 cum, 10 t capacity hour 2.27


Add 10% cost of carriage towards loading and
unloading charges

Plate compactor hour 1.00

c. Materials

Compensation for earth taken from private land cum 37.50

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 50 cum = a+b+c+d+e+f

Rate per cum a+b+c+d+e+f/50

Note: Only 75% of fresh material has been provided as 25% can be
retrieved from site from earth i.e. flown down the slop in the form of
slurry and deposited at the foot of rain cuts.

15.2 1900 1. Maintenance of Earthen shoulder (filling with fresh


selected soil)
Making up loss of material/irregularities on shoulders to the
design level by adding fresh approved selected soil and
compacting it with appropriate equipment at OMC upto a lead
of 1000 m as per technical specification Clause 1903

Unit = sqm

Taking output = 100 sqm

Assuming average thickness of filling to be 150 mm

Quality of fresh material = 15 cum

a. Labour

Mate day 0.20

Mazdoor (Unskilled) day 5.00

b. Machinery

Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum hour 0.25


per hour

Tipper 5.5 cum hour 4.10


Add 10% cost of transportation to cover cost of loading
and unloading

15 - 800
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Plate compactor @ 25 sqm per hour hour 4.00

c. Material

Compensation of earth cum

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 100 sqm = a+b+c+d+e+f

Rate per sqm = (a+b+c+d+e+f)/100

2. Maintenance of Earhen shoulder (stripping of excess soil)

Stripping excess soil from the shoulder surface to achieve the


approved level and compacting with plate compactor at OMC
as per drawings and Technical Specification Clause 1903

Unit = sqm
Taking output = 100 sqm

Assuming height of stripping as 75 mm

Quantity of earth cutting involved = 7.5 cum

a. Labour

Mate day 0.10

Mazdoor (Unskilled) day 2.50

b. Machinery

Plate compactor hour 3.40

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 100 sqm = a+b+c+d+e

Rate per sqm = a+b+c+d+e/100

Note: Earth stripped from earthen shoulders to be used as shoulders or


dumped on the side slopes locally for disposal.
15.3 1900 Maintenace of bituminous surface road

15 - 801
Sr. Reference to
Description Unit Quantity
No. MORD Spec
i. Repair to pot holes by removal of failed material, trimming the
sides to vertical and levelling the bottom, cleaning the same
with compressed air or any appropriate method filled with
75mm B.M, applying bitumen emulsion prime coat at the
bottom and bitumen emulsion tack coat on sides and on
bottom as per technical specifications Clauses 502 and 503.

Unit = cum

Taking output = 187.5x0.075 = 14.06 cum = (30.94 Tonne)

(5% area of one km)

a) Labour

Mate day 0.80

Mazdoor (Unskilled) day 20.00

b) Machinery

Jack hammer 25 kg with tractor hour 4.00

Compressor 210 cfm with tractor hour 2.00

Emulsion pressure distributor hour 4.00

Mixall 6/10 t capacity hour 4.00

Three wheeled 80-100 kN Static Roller hour 4.00

c) Material

Primer with bitumen emulsion @ 9 kg/10 sqm 187.5x9 = Tonne 0.090


168.75 kg.

Tack coat with bitumen emulsion @ 3.0 kg/ 10 sqm

Bottom = 187.5

Sides = 28.27 Tonne 0.030

Total = 215.77

Bitumen for BM @ 3.5% by weight of mix Tonne 1.040


= 30.94 x 3.5 / 100 = 1.082
Weight of mix (BM) 14.06 cum = (30.94 tonne)
Weight of Bitumen = 1.082

Weight of aggregate 30.94 -1.082 = 29.86

Taking density of aggregate 1.5 t per cum

Volume of aggregate 29.86 / 1.5 = 19.90 cum

15 - 802
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Grading (1) (40 mm nominal size)

37.5 - 25 mm 15% cum 2.985

25 - 10 mm 45% cum 8.96

10 - 5 mm 25% cum 4.900

5 mm and below 15% cum 2.99

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost of 14.06 cum = a+b+c+d+e+f

Rate per cum = a+b+c+d+e+f/14.06

ii. Patch repair on already filled pot holes with 75 mm BM with 20


mm premix carpet and seal coat Type B as per drawings and
technical specification Clause 1904.2

Unit = sqm

Takign output = 200 sqm

a) Labour

Mate day 0.64

Mazdoor (Unskilled) day 16.00

b) Machinery

Mixall 6/10 tonne hour 2.00

Bitumen pressure distributior hour 2.00

Three wheeled 80-100 kN Static Roller hour 4.00

c) Material

Bitumen for pre-mix carpet @ 14.60 kg/10 sqm tonne 0.122


200x14.60/10 =292 kg

Bitumen for tack coat @ 2 kg per 10 sqm 200 x 2 / 10 = tonne 0.04


40 kg

Bitumen for seal coat @ 6.8 kg per 10 sqm tonne 0.100


200 x 6.8 / 10 = 136 kg

Crushed stone aggregate @ 0.27 cum per 10 sqm cum 5.40


= 200 x 0.27 / 10 = 5.4 cum

15 - 803
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Crushed sand passing 2.36 mm sieve and retained on cum 1.20
180 mircon sieve @ 0.06 cum per 10 sqm

200 x 0.06 / 10 = 1.20 cum

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost of 200 sqm = a+b+c+d+e+f

Rate/sqm = a+b+c+d+e+f/200

iii. Repair to pot holes and removal of loose material, trimming of


sides, cleaning of surface by providing tack coat, 20 mm thick
pre-mix carpet and seal coat type B specification Clause
1904.2

Unit = sqm
Taking output = 200 sqm

a) Labour

Mate day 0.80

Mazdoor (Unskilled) day 20.00

b) Machinery

Air compressor 210 cfm with tractor hour 2.00

Bitumen pressure distributor hour 2.00

Mixall 6/10t capacity hour 2.00

Three wheeled 80-100 kN Static Roller hour 4.00

c) Material

Bitumen for tack coat @ 3kg per 10 sqm 200 x 3 / 10 = tonne 0.034
60 kg
Bitumen for pre-mix carpet @ 14.60 kg per 10 sqm = 200 tonne 0.12
x 14.6 / 10 = 292 kg

Bitumen for seal coat @ 6.8 kg per 10 sqm tonne 0.14


= 200 x 6.8 / 10 = 136 kg

Crushed stone aggregate @ 0.27 cum per 10 sqm cum 3.40


= 200 x 0.27 / 10 = 5.4 cum

Crushed sand passing 2.36 mm sieve and retained on cum 1.20


180 micron sieve @ 0.06 cum per 10 sqm
200 x 0.06 / 10 = 1.20 cum

15 - 804
Sr. Reference to
Description Unit Quantity
No. MORD Spec
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 200 sqm = a+b+c+d+e+f

Rate per sqm = a+b+c+d+e+f/200

iv. Repair to pot holes and removal of loose material, trimming of


sides, cleaning of surface by providing tack coat with bitumen
emulsion, 20 mm thick pre-mix carpet using catonic bitumen
emulsion and seal coat type B with bitumen emulsion

Unit = sqm
Taking output = 200 sqm

a) Labour

Mate day 0.64

Mazdoor (Unskilled) day 16.00

b) Machinery

Concrete mixer 0.4 / 0.28 cum capacity hour 2.50

Air compressor 210 CFM with tractor hour 2.00

Emulsion pressur distributor hour 2.00

Three wheeled 80-100 kN Static Roller hour 4.00

c) Materials

Emulsion for tack coat @ 3 kg per 10 sqm tonne 0.06


200 x 3 / 10 = 60 kg

Emulsion for premix carpet @ 21.50 kg per 10 sqm tonn 0.11


200 x 21.50 / 10 = 430 kg

Emulsion for seal coat @ 10 kg per 10 sqm tonn 0.20


= 200 x 10 / 10 = 200 kg

Crushed stone aggregate @ 0.27 cum per 10 sqm = cum 5.40


200 x 0.27 / 10 = 5.4 cum

Crushed sand passing 2.36 mm sieve and retained on cum 1.20


180 micron sieve @ 0.06 cum per 10 sqm =
200 x 0.06 / 10 = 1.20

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

15 - 805
Sr. Reference to
Description Unit Quantity
No. MORD Spec

Cost for 200 sqm = a+b+c+d+e+f

Rate per sqm = a+b+c+d+e+f/200

15.4 1900 Maintenance of Gravel Road

Maintenance of gravel road including making up the loss of profile,


rectifying corrugated surface, filling up of depressions, pot holes and
erosion gullies by adding fresh material and compacting it with
appropriate equipment or to strip excess of material from the road
surface as per drawings and technical specification Clause 1905

Unit = sqm

Taking out put @ 5% of the area in one km. as affected:


= 1000 x 3.75x0.05 / 100 = 187.5 Sqm

Quantity = 187.5 x 0.15 = 28.12 cum

a) Rate as per item 4.1 of Chapter 4 cum 28.12

b) Add 50% for extra efforts involved as maintenance is to be


done in small reaches

Cost of 187.5 Sqm = a+b

Rate per sqm = a+b/187.5

Note: The cost of 25% retrived material may be deducted from rates.

15.5 1900 Maintenance of WBM Road

Maintenance of WBM road including filling up of pot holes, ruts and


rectifying corrugated surface, damaged edges and ravelling as per
technical specification Clause 1906.

Unit = Sqm

Output - Taking affected area @ 5% in 1 km


= 1000 x 3.75 x 0.05 = 187.5 sqm

Quantity 187.5 x 0.075 = 14.06 cum


a) Rate as per item No. 4.7 of Chapter 4 cum 14.06

b) Add 50% for Extra Efforts involved on maintenance to be done


in Small reachs

Cost of 187.5 Sqm = a+b

Rate of per sqm a+b/187.5

Note: The cost of 25% retrived material may be deducted from rates.

15.6 1900 Maintenance of Drains

15 - 806
Sr. Reference to
Description Unit Quantity
No. MORD Spec
The maintenance of drains include erosion, repair, clearing,
cleaning, reshaping, regrading, deepening of side drains as well as
catch water drains as per technical specification Clause 1907.

Unit - Per Metre

Taking output one km = 1000 metre

a) Labour

Mate day 0.32

Mazdoor (Unskilled) day 8.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 1000 metre = a+b+c+d

Rate per Metre = a+b+c+d/1000

15.7 1900 (I) Maintenance of Culverts

Maintenance of Hume pipe Culvert by way of Clearing,


Cleaning, Erosion repair, repairs to cracks, parapet wall and
protection work as per drawing and technical specification
Clause 1908

Unit = One No. Hume pipe (1000 mm dia)

Taking output = One No.H.P. Culvert

a) Labour

Mate day 0.10

Mazdoor (Unskilled) day 1.00

Mason 2nd Class day 1.40

b) Material

Cement, Sand, Brick, Boulder etc. L.S

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for one No. Hume pipe culvert = a+b+c+d+e

15 - 807
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate per hume pipe Culvert = a+b+c+d+e

(II) Maintenance of Culverts Slab type

Maintenance of Slab type Culverts by way of clearing,


Cleaning, Erosion repair, repairs to cracks, parapet walls and
Protection works as per drawing and technical specification
Clasue 1908

Unit = One No. Culvert (2 m span)

Taking output = one No. Slab Culvert

a) Labour

Mate day 0.20

Mazdoor (Unskilled) day 4.00

Mason 2nd Class day 1.00

b) Material

Cement, Sand, Bricks, Stone Boulder etc. L.S

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for One Slab Culverts =a+b+c+d+e

Rate per Culvert = a+b+c+d+e

15.8 1900 Maintenance of Causeway

Maintenance of Causeway by way of minor Surface repairs,


replacing Guide Posts, repair of flood gauges, removal of debris,
providing boulders and protection work and painting as per technical
specification Clause 1909

Unit = One metre

Taking output = 50 metre causeway

a) Labour

Mate day 0.80

Mazdoor (Unskilled) day 1.60

Mason 1st Class/Painter 1st Class day 4.00

b) Material

15 - 808
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Supply of cement, paint, sand, aggregate, boulder etc. LS

(LS Rs.350.00)
c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 50 metre = a+b+c+d+e

Rate per metre = a+b+c+d+e/50

15.9 1900 Maintenance of Road Signs

Maintenance of road signs by way of cleaning and repainting of


mandatory / requlatory / cautionary / informatory and place
identifications sign board as perdrawings and technical specification
Clause 1910

Unit = 1 km
Taking output = one km

All types of signs in one Km

a) Labour

Mate day 0.09

Mazdoor (Unskilled) day 2.00

Painter 1st Class day 0.125

b) Material

Synthetic Enamel Paint, Engineering grade tape, welding LS


machine etc. (LS Rs.300)

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for one Km = a+b+c+d+e

Rate per km = a+b+c+d+e

15.10 1900 Maintenance of steel and RCC Railing

(i) Repair of steel railing to bring it to original shape cleaning and


repainting as per drawing and technical specification Clause
1911
Steel Railing

15 - 809
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = Running metre

Taking output = 10 metre

It is assumed that damage is to the extent of 10%

a) Labour

Mate day 0.024

Mazdoor (Unskilled) day 0.30

Painter 1st Class day 0.10

Blacksmith day 0.20

b) Materials

Mild steel (structural steel) t 0.039

ISMC = 0.029T

MS plate = 0.01

Nuts and bolts t 0.001

c) Machinery

Welding set (LS Rs.100.00) LS

d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)

e) Add GST, LWC etc. @ 0 on (a+b+c)

Cost for 10 metre = a+b+c+d+e+f

Rate per metre = a+b+c+d+e+f/10

(ii) Repair of RCC railing to bring it to the original shape, cleaning


and repainting as per drawings and technical specification
Clause 1911

RCC Railing
Unit = running metre

Taking output = 1 metre

It is assumed that damage is to the extent of 10%

a) Labour

Mate day 0.012

15 - 810
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Mazdoor (Unskilled) day 0.20

Mason 1st Class day 0.10

b) Materials

M 30 grade cement concrete

Rate as per item no. 13.1 (III) of Chapter 13 cum 0.05

Steel bars reinforcement

Rate as per item no.13.2 of Chapter 13 t 0.013

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Rate per metre = a+b+c+d+e/10

15.11 1900 Maintenance of 200 metre and km stones

Maintenance of 200 metre km stone by way of refiting of tilted


stones repairing with cement mortar, cleaning, repairing and
lettering on 200 metre km stone and 5 th km stone as per drawing
and technical specification Clause 1912

Unit = 1 km

Assuming 1 km stone, 4 nos 200 metre stone and 1/5th 5km stone

(i) Painting two coats with synthetic enamel paint

200 m stone 4 nos = 0.760 sqm.

One km stone = 0.815 sqm.

5th km stone 1x1/5 = 0.320 sqm.

Total = 1.895 sqm.

As per item No. 10.5 of chapter 10 sqm 1.895

(ii) Printing letters and figures of any shade with synthtic enamel
paint of any approved colour to give an even shade

200 m stone 4 Nos. = 40 per cm height per letter

One no km stone = 120 per cm height per letter

5th km stones 1/5th = 60 per cm height per letter

Total = 220 per cm height per letter

15 - 811
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate as per item no 10.1 of chapter 10 per cm 220.00
height
per
letter

a) Labour

Mate day 0.024

Mazdoor day 0.50

Mason 1st Class day 0.10

b) Materials

Cement, sand, aggregates etc. LS

(LS = Rs.100.00)

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for one km = (i+ii+a+b+c+d+e)

Rate per/km = (i+ii+a+b+c+d+e)

15.12 1900 Cutting of branches of trees shrubs and trimming of grass and
weeds

(i) Cutting of branches of trees and shrubs from the road way or
with in R.O.W including disposal of wood and leaves to
suitable location as per technical specification Clause 1914

Unit = one tree

Taking output = 10 trees of 900 mm average girth

a) Labour

Mate day 0.12

Mazdoor (Skilled) day 1.00

Mazdoor (Unskilled) day 2.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 10 trees = (a+b+c+d)

15 - 812
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rate per tree = (a+b+c+d)/10

(ii) Cutting of shrubs from the road way or with in R.O.W and
disposal of shrubs to suitable locations as per technical
specifications Clause 1914

Unit=Each

Taking output = 100 nos shrubs

a) Labour

Mate day 0.08

Mazdoor (Unskilled) day 2.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 100 shurbs = a+b+c+d

Rate per shurb = a+b+c+d/100

(iii) Trimming of grass and weeds from the shoulders/berms and


disposing off the same to suitable locations as per technical
specifications Clause 1914

Unit = sqm

Taking output = 1500 sqm

a) Labour

Mate day 0.40

Mazdoor (Unskilled) day 10.00

b) Contractor’s profit & Overheads @ 12.5% on (a)

c) Add GST, LWC etc. @ 0 on (a)

Cost for 1500 sqm = a+b+c+d

Rate per sqm = a+b+c+d/1500

15.13 1900 White washing of parapet walls of CD work and tree truncks

White washing two coats on parapet walls and tree trunks including
preparation of surface by cleaning scraping etc. as per technical
specifications Clause 1915

15 - 813
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Unit = sqm
Taking output = 9 sqm

a) Labour

Mate day 0.01

Mazdoor (Unskilled) day 0.143

White washer day 0.143

b) Materials

Lime quintel 0.045

Fevicol adhesive kg 0.10

Indigo kg 0.013

c) Contractor’s profit & Overheads @ 12.5% on (a+b)

d) Add GST, LWC etc. @ 0 on (a+b)

Cost for 9 sqm = a+b+c+d+e

Rate per sqm = a+b+c+d+e/9

Note: For analysis of rates for maintenance works bitumen grade S-90
has been taken. User may modify as per site requirement

15.14 1900 Periodical Renewal to existing bituminous surface

1 Open graded Premix carpet 20 mm thick

Unit = sqm

(i) Tack coat


With bituminous Emulsion (RS-1)
Rates as per item 5.2 (ii) sqm

(ii) Pre-mix carpet using bituminous (penetration grade


modified bitumen) binder

Rates as per item No. 5.9 sqm


as relevant
Or
(iii) Premix carpet using bitumen Emulsion

Rates as per item No. 5.10 sqm

(iv) Seal coat Type A, B or C

15 - 814
Sr. Reference to
Description Unit Quantity
No. MORD Spec
Rates as per item No. 5.11

2 Surface dressing single coat/first coat or 2nd coat

Rates as per item No. 5.6 sqm

15 - 815
Chapter 15

NTENANCE OF ROADS
Rate Amount
(Rs.) (Rs.)

356.65 85.60

244.56 855.96

218.00 218.00

0.00 0.00

144.94

0.00

1,304.50

130.45

356.65 142.66

244.56 1,222.80

15 - 816
Rate Amount
(Rs.) (Rs.)
1,635.00 1,193.55

850.00 1,929.50
192.95

218.00 218.00

0.00

612.43

0.00

5,511.89

110.24

356.65 71.33

244.56 1,222.80

1,635.00 408.75

850.00 3,485.00
348.50

15 - 817
Rate Amount
(Rs.) (Rs.)
218.00 872.00

0.00 0.00

801.05

0.00

7,209.43

72.09

356.65 35.67

244.56 611.40

218.00 741.20

173.53

0.00

1,561.80

15.62

15 - 818
Rate Amount
(Rs.) (Rs.)

356.65 285.32

244.56 4,891.20

450.00 1,800.00

435.00 870.00

954.00 3,816.00

1,686.00 6,744.00

652.00 2,608.00

27,509.00 2,475.81

27,509.00 825.27

38,826.00 40,379.04

15 - 819
Rate Amount
(Rs.) (Rs.)

765.94 2,286.33

1,827.00 16,360.79

1,510.00 7,399.00

1,104.00 3,295.44

11,754.52

0.00

103,990.72

7,396.21

356.65 1,079.04

244.56 3,912.96

1,686.00 3,372.00

954.00 1,908.00

652.00 2,608.00

27,509.00 3,356.10

27,509.00 1,100.36

27,509.00 2,750.90

1,827.00 9,865.80

15 - 820
Rate Amount
(Rs.) (Rs.)
698.00 837.60

3,848.84

0.00

34,639.60

173.20

356.65 285.32

244.56 4,891.20

435.00 870.00

954.00 1,908.00

1,686.00 3,372.00

652.00 2,608.00

27,509.00 935.31

27,509.00 3,301.08

27,509.00 3,741.22

1,827.00 6,211.80

698.00 837.60

15 - 821
Rate Amount
(Rs.) (Rs.)
3,620.19

0.00

32,581.72

162.91

356.65 228.26

244.56 3,912.96

188.00 470.00

435.00 870.00

954.00 1,908.00

652.00 2,608.00

27,509.00 1,650.54

27,509.00 3,025.99

27,509.00 5,501.80

1,827.00 9,865.80

698.00 837.60

3,859.87

0.00

15 - 822
Rate Amount
(Rs.) (Rs.)

34,738.81

173.69

1,544.80 43,439.87

21,719.94

65,159.81

347.52

2,580.31 36,279.16

18,139.58

54,418.75

290.23

15 - 823
Rate Amount
(Rs.) (Rs.)

356.65 114.13

244.56 1,956.48

258.83

0.00

2,329.43

2.33

356.65 35.67

244.56 244.56

285.32 399.45

600.00

159.96

0.00

1,439.63

15 - 824
Rate Amount
(Rs.) (Rs.)
1,439.63

356.65 71.33

244.56 978.24

285.32 285.32

1,200.00

316.86

0.00

2,851.75

2,851.75

356.65 285.32

244.56 391.30

458.55 1,834.20

15 - 825
Rate Amount
(Rs.) (Rs.)
400.00

363.85

0.00

3,274.67

65.49

356.65 32.10

244.56 489.12

458.55 57.32

400.00

122.32

0.00

1,100.85

1,100.85

15 - 826
Rate Amount
(Rs.) (Rs.)

356.65 8.56

244.56 73.37

458.55 45.86

458.55 91.71

60,000.00 2,340.00

80,000.00 80.00

200.00

354.94

0.00

3,194.43

319.44

356.65 4.28

15 - 827
Rate Amount
(Rs.) (Rs.)
244.56 48.91

458.55 45.86

7,762.63 388.13

56,316.25 732.11

152.41

0.00

137.17

65.36 123.87

15 - 828
Rate Amount
(Rs.) (Rs.)
0.92 201.78

356.65 8.56

244.56 122.28

458.55 45.86

22.09

0.00

524.43

524.43

356.65 42.80

356.65 356.65

244.56 489.12

111.07

0.00

999.64

15 - 829
Rate Amount
(Rs.) (Rs.)
99.96

356.65 28.53

244.56 489.12

64.71

0.00

582.36

5.82

356.65 142.66

244.56 2,445.60

323.53

0.00

2,911.79

1.94

15 - 830
Rate Amount
(Rs.) (Rs.)

356.65 3.57

244.56 34.94

285.32 40.76

660.80 29.74

230.00 23.00

100.00 1.30

16.66

0.00

148.66

16.52

15 - 831
Rate Amount
(Rs.) (Rs.)

15 - 832
Chapter 16
MISCELLENEOUS ITEMS
Construction of dry lean cement concrete Sub- base over a prepared sub-
grade with coarse and fine aggregate conforming to IS: 383, the size of coarse
aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1,
aggregate gradation after blend
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.12 356.65
Mazdoor skilled day 6.00 356.65
Mazdoor day 22.00 244.56
b) Machinery
Front end loader 1 cum bucket capacity hour 6.00 1341.00
Cement concrete batch mix plant @ 75 cum per hour hour 6.00 6584.00
Electric generator 100 KVA hour 6.00 2073.00
Paver with electronic sensor hour 6.00 883.00
Vibratory roller 8-10 t capacity hour 8.00 1687.00
Water tanker6 KL capacity hour 8.00 440.00
Tipper tonne.km 990 x L 3.50
Add 10 per cent of cost of carriage to cover cost of loading and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and 12.5 mm nominal cum 405.00 1132.00
sizes graded as per table 600-1 @ 0.90 cum/cum of concrete
conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of concrete cum 203.00 950.00
Cement @ 150 kg/cum of concrete tonne 67.50 6200.00
Cost of water KL 48.00 40.00
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)
e) Add GST, LWC etc. @ 0 on (a+b+c)
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/450
say
4.6 403 Cement Treated Crushed Rock or combination as per clause 403.2 and
table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub grade, adding the
designed quantity of cement to the spread Material, mixing in place with
rotavator, grading with the motor grader and compacting with the road roller at
OMC to achieve the desire
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity of crushed rock
by weight.
a) Labour
Mate day 0.480 356.65
Mazdoor skilled day 2.000 356.65
Mazdoor day 10.000 244.56
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.000 3075.00
Vibratory roller 8 - 10 tonne hour 6.000 1687.00
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 431.00
Water tanker 6 KL capacity hour 10.000 440.00
c) Material
Cement at site @ 4 per cent by weight of crushed aggregate (600 tonne 24.000 6200.00
tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.200 1101.00
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 1041.50
4.75 mm to 75 micron @ 25 per cent cum 96.000 1029.00
Cost of water KL 60.000 40.00
or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent cum 124.800 1089.00
9.5 mm to 4.75 mm @ 5 per cent cum 19.200 1084.00
4.75 mm to 75 micron @ 62.5 per cent cum 240.000 698.00
Cost of water KL 60.000 40.00
4.6 (i) For Sub-Base course
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)
e) Add GST, LWC etc. @ 0 on (a+b+c)
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
say
4.6 (ii) For Base course
d) Contractor’s profit & Overheads @ 12.5% on (a+b+c)
e) Add GST, LWC etc. @ 0 on (a+b+c)
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
say

Construction of cold weather Bamboo bridge overall width of 3.70m and clear
road way 3m with jungle wood post 20cm to 25cm dia 5nos. In each rows and
rows being 2.1m. apart except for the navigable span which should be 3m.
Post to be driven at least 180cm. or more below ground level including
providing 20cm to 25cm center to center and placed over 20 cm dia, jungle
wood dham, 15cm dia. jungle wood bracing collar fixed by bolts and nuts,
straps etc. mature bholuka Bamboo cross groth all closely packed and tied
75cm wide track way made from 38mm thick 1st class local plank fixed on
75mmx100mm first class local wood battens 120cm apart and 3 lines of jati
bamboo horizantal railing fixed in bholuka bamboo post placed at 210cm apart
and white washed including all necessary nuts and bolts, coir ropes, struts,
nails etc. complete with a layer of brushwood to exposed portion out-side
trackway with earth topping complete as per direction of the department.

Unit ----- RM
Analysis for 30.00 RM

A. Materials unit Qty Rate


i Jungle wood post/dham/beam/diognal bracing/strut/collar. RM 680.00 150.00
ii Bholuka Bamboo for Gorah/cross gorah/rail post NO 255.00 85.00
iii Jati Bamboo for rail bar no 32.00 70.00
iv Sal Wood for collarand/batten/tie cum 0.93 25538.00
v Trackway Plank cum 1.80 30473.00
vi Brushwood bundles 700.00 100.00
vii Cane cap 20.00 500.00
viii Spreading Earth L/S
ix White washing L/S
x Patent Nail kg 4.00 45.00
xi Bolts & Nuts kg 10.00 80.00
xii Nails kg 2.00 60.00

B. Labour
i Carpentar nos 10.00 458.55
ii Skilled Labour nos 20.00 356.65
iii Ordinary labour nos 60.00 244.56

Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

Item 1. (b) Construction of Temporary bridge of 3.70 m clear Road Road way.

Unit ----- RM
Considering 30 RM
unit qty Rate

A. Materials
I. Bholuka Bamboo post Nos 220.00 85.00
II. Jati Bamboo Nos 280.00 70.00
III. Brushwood bundles 300.00 100.00
IV. Cane cap 10.00 500.00
B. Labour
I. Skilled Labour Nos 5.00 356.65
II. Ordinary labour Nos 15.00 244.56

C. Sundaries L/S
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/m

Item 1. Making 120cm wide bamboo foot bridge….

Unit ----- RM
Considering 3 RM

A. Materials:-
I. Bholuka Bamboo post/rail post/dham/strut.(5nos+5nos) Nos 5.00 85.00
II. bholukaRail post dham Nos 5.00 85.00
III. Jati Bamboo/long gorah/mat/railing Nos 6.00 70.00
IV. Gelv. Wire gms 0.50 80.00
V. Brush wood L/S
VI. Wear & Tear of T & P L/S 10.00

B. Labour
I. Skilled Labour Nos 1.00 356.65
II. Ordinary labour Nos 1.00 244.56

C. Sundaries L/S
Total = A+B+C
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/Rm
Say

16.4 Item No. 2. (a) (i) Supplying & Driving Sal Piles 25 cm to 30 cm

(a) With pile engine


(b) Portion of pile actually driven underground

Unit ----- RM
Considering 8 Nos of pile of 8RM length

A. Materials:-

I. Sal pile 25 cm to 30 cm dia 8 RM RM 8.00 4000.00


II. Jati Bamboo for one bridge of 8 Post(100x70)/8 Nos 90.00 70.00
III.
IV. Cost of Coir rope tying wire for plateform kg 10 60
V Sundries L/S
B. Hire Charge of pile Engine for 2 days

C. Labour:-

I. Carpenter for dressing / marking Nos 1.87 458.55


II. Unskilled labour for coal tarring, dressing Nos 1.87 244.56
III. Unskilled labour for machine Nos 5.50 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

T0tal A+B+C+D+E
Rate/RM =

16.4(ii) Item No. 2 (a) (ii)


Portion of pile remaining above ground
Unit =8 RM
A)Material:-
Same as that of Item No. 2 (a) (i) except hire charge of pile engine

B)Lobour:-
i)Carpenter 0.31 458.55
ii)Unskilled 0.31 244.56

Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

b Item No. 2 (b) Using labour


(i) Portion of pile actually driven under ground
Unit = RM
Analysis for 3 RM

A. Materials:-

I. Sal pile 25 cm to 30 cm dia 3RM RM 3.00 4000.00


II. Bholuka Bamboo Nos 3.00 85.00
III.
IV. Coir Rope Kg 1.00 60.00
V. Coal Tar gms 0.50 40.00
B. Labour:-
I. Carpenter for dressing / marking Nos 0.75 458.55
II. Unskilled labour for coal tarring, ranoling Nos 2.50 244.56
D. Sundaries L/S
Total = (A+B+C)
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/Rm

Item No. 2 (b)(ii) Using labour


(i) Portion of pile remaining above ground
Unit = RM
Considering 2 RM length

A. Materials:-

I. Sal pile 25 cm to 30 cm dia RM 2.0 4000.00


II. Jati Bamboo for Machine Nos 2.0 70.00
III. Coir Rope Kg 0.75 60.00
IV. Coal Tar ltre 0.50 40.00
B. Labour:-
i Carpenter no 0.5 458.55
ii Unskilled labour no 1 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate /Rm

16.5 Item No. 3. (a) (i) Supplying & Driving Azar/Nahar/Nageswar/Zarul Piles 25 cm to 30 cm dia
dressed to Heart wood

(a) With pile engine


(b) Portion of pile actually driven underground

Unit ----- RM
Considering pile of 8.00 M length

A. Materials:-
I. Azar/Nahar/Nageswar/Zarul pile 25 cm to 30 cm dia Rm 8.00 3300.00
II. Jati Bamboo for one bridge of 8 N0 of post=100 nos 90.00 70.00
Cost/post=(ii)/8
III. Bholuka Bamboo for post & Dham Nos
IV. Cost of Coir rope tying wire for plateform/coal tar kg 10.00 60.00
V Sundries L/S 20.00
B. Hire Charge of pile Engine for2 days 1000.00
T0tal
C. Labour:-
I. Carpenter for dressing / marking Nos 1.87 458.55
II. Mazdoor for coal tarring, carrying Nos 1.87 244.56
III. Unskilled Nos 5.50 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/m

Item No. 3 (a)(ii) Portion of pile above ground

Unit =8RM
A)Materials
same as that of item No. 3. (a) (i) except Hire
Charge of Machinery and labour for Handling pile engine.

B) Labour
carpenter no 0.31 458.55
Unskilled labour no 0.31 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

16.5(b) I)Using labour


Portion of pile driven underground
unit=Rm
Analysis for 3 RM
A) Matrerials
i)Azar or Nahar piles 25cm or 30cm dia Rm 3.00 800.00
ii)Cost of bamboo no 12.00 70.00
iii)coir rope kg 10.00 60.00
iv)costof coal tar kg 0.50 40.00
v)Sundries L/S
B)Labour
i)Carpenter No 0.75 458.55
ii)Unskilled N0 6.00 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

II)Portion of pile above ground


unit=Rm
Analysis for 2 RM
A) Matrerials
i)Azar or Nahar piles 25cm or 30cm dia Rm 2.00 800.00
ii)Cost of bamboo no 8.00 70.00
iii)coir rope kg 8.00 60.00
iv)costof coal tar kg 0.50 40.00
v)Sundries L/S 20.00
B)Labour
i)Carpenter No 0.75 458.55
ii)Unskilled N0 1.25 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

16.6(a) Sal wood works…………….supplying ,fitting,fixing.

Unit=cum

A)Materials
i)Sal timber(undressed) cum 1.02 22473.00
ii)coal tar kg 0.50 40.00
iii)cost of bolts and nuts,spikes,nails. kg 5.00 80.00
iv)sundries
B)Labour
i)Carpenter no 2.50 458.55
ii)Skilled labour n0 1.25 244.56
iii)Unskilled N0 2.50 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

b) In trackway planks

Unit=cum

A)Materials
i)Sal timber(undressed) cum 1.02 22473.00
ii)coal tar kg 1 40.00
iii)cost of bolts and nuts,spikes,nails. kg 2.5 80.00
iv)sundries
B)Labour
i)Carpenter no 2.5 458.55
ii)Skilled labour n0 1.25 244.56
iii)Unskilled N0 2.5 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

16.7(a) Azar nahar……supplying ,fitting etc

Unit=cum

A)Azar/Nahar…..(Undressed) cum 1.02 15784.00


ii)coaltar kg 1.00 40.00
iii)cost of bolts,nuts, spikes kg 3.00 80.00
iv)sundries
B)Labour
i)Carpenter no 2.50 458.55
ii)Skilled labour n0 1.25 244.56
iii)Unskilled N0 2.50 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

b) Intrack way planks


Unit=cum

A)Azar/Nahar…..(Undressed) cum 1.02 14774.00


ii)coaltar kg 1 40.00
iii)cost of bolts,nuts, spikes kg 1 80.00
iv)sundries
B)Labour
i)Carpenter no 3.25 458.55
ii)Skilled labour n0 1.25 244.56
iii)Unskilled N0 2.5 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

16.8(a) Supplying…..Timber beamand bearing beam…..etc


(a)Using sal timber

Unit=cum

A)Sal timber cum 1 23038.00


ii)coaltar kg 1 40.00
iii)cost of bolts,nuts, spikes kg 1 80.00
iv)sundries
B)Labour
i)Carpenter no 3.25 458.55
ii)Skilled labour n0 1.25 244.56
iii)Unskilled N0 2.5 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

b) using Azar,nahar…….etc
Unit=cum

A)Azar/Nahar…..(Undressed) cum 1.00 18726.00


ii)coaltar kg 1.00 40.00
iii)cost of bolts,nuts, spikes kg 1.00 60.00
iv)sundries
B)Labour
i)Carpenter no 2.50 458.55
ii)Skilled labour n0 2.50 244.56
iii)Unskilled N0 1.25 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =
16.9 Supplying 25cm to30salwood log beam….etc

Unit=RM
Analysis for= 5RM
A)Sal beam RM 5.00 4700.00
ii)coaltar kg 1.00 40.00
iii)cost of bolts,nuts, spikes kg 1.00 60.00
iv)sundries
B)Labour
i)Carpenter no 1.25 458.55
ii)Skilled labour n0 1.00 244.56
iii)Unskilled N0 4 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

(b) Unit=RM
Analysis for= 5RM RM 5.00 4000.00
A)Azar/Nageswar/zarul……..beam kg 1.00 40.00
ii)coaltar kg 1.00 60.00
iii)cost of bolts,nuts, spikes
iv)sundries
B)Labour
i)Carpenter n0 1.25 458.55
ii)Skilled labour N0 1.00 244.56
iii)Unskilled No 4.00 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

16.12 Labour for Scarfing and joining piles 25cm to 30 cm dia…

Unit=Each

(A)Materials
i)Flat Iron including making clamp Kg 7.79 70.00
ii)Cost of bolts,nuts,spikes,washer etc kg 1.00 80.00
iii)Sundries L/S
B)Labour
i)Carpenter no 0.625 458.55
ii)un Skilled labour no 0.625 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

16.13 Labour for taking out old piles…….

Unit=Each
Considering Pile =8Nos
A) materials
i)Jumper,rope etc kg 10 60
ii)Jati bamboo n0 20 70.00
iii)Scaffolding L/s
B)Labour
i)Carpenter no 5 458.55
ii)un Skilled labour no 20 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

16.14 Labour for dismantling all members of bridge(EXCEPT PILE)

Unit=Metre
Considering=6M

A) materials
i)Jumper,rope etc kg 10.00 60.00
ii)Jati bamboo n0 5.00 70.00
iii)Scaffolding L/s
B)Labour
i)Carpenter no 1.88 458.55
ii)un Skilled labour no 15.0 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

16.15 Labour for driving piles 25 cm to 30 cm dia…

a)with Pile engine


i)Portion of pile actually driven

Unit=Metre
Analysis for=8Rm
A)Materials
i)Jati bamboo (100*70)/8 no 100 70.00
ii)Rope Kg 10 60
iii)Sundries L/S
iv)Hire charge of Pile engine=2days hour
v)Carriage of pile 2% of cost of material
Total
B) Labour
i)Carpenter n0 1.875 458.55
ii)Unskilled Labour no 1.875 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

ii)portion of pile above ground


Analysis for=8Rm
Unit=Metre

A)Materials

Same as above except hire charge of pile engine

B) Labour
i)Carpenter n0 0.31 458.55
ii)Unskilled Labour no 0.31 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)
Rate/RM =

b) By use of labour
i)Portion of pile actually driven undreground
Analysis for 3 RM
A)Materials
i)Coal tar kg 1 40
ii)Rope kg 3 60
iii)bamboo no 3 70.00
iv)carriage of pile
B) Labour
i)Carpenter no 0.75 458.55
ii)Unskilled Labour no 6 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

i)Portion of pile aboveground


A)Material
Analysis for 2 RM
A)Materials
i)Coal tar kg 0.5 40
ii)Rope kg 1.5 60
iii)bamboo no 3 70.00
iv) carriage of pile
B) Labour
i)Carpenter no 0.75 458.55
ii)Unskilled Labour no 1.25 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM =

16.16 Labour for fitting RSJ beam CI sadde…….

Unit=Quintel
Analysis for 10 qtl

A)Materials
i)Jati bamboo no 20.00 70.00
ii)Bolts and nuts Kg 5.00 80.00
iii)Carriage to average distance 25 KM 25.00 4.00
iv)Rope kg 1.00 60.00
v)Paint lit 4.50 146.00
B) Labour
i)Carpenter no 1.25 458.55
ii)Unskilled Labour no 10.0 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/Qtl =

16.17 Labour for fitting OLD RSJ beam CI sadde…….

Unit=Quintel
Analysis for 10 qtl
A)Materials
i)Jati bamboo no 20.00 70.00
ii)Bolts and nuts Kg 5.00 80.00

iv)Rope kg 1.00 60.00


v)Paint lit 4.50 146.00
B) Labour
i)Carpenter no 0.75 458.55
ii)Unskilled Labour no 8.00 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/Qtl =
16.18 Labour for fitting FI strap and Cleat

Unit=Quintel

A)Materials
i)Wear and tear of T&P L/S
ii)carriage from godown km 25 4
iii)Sundries
B)Labour
i)Carpenter n0 1.25 458.55
ii)Unskilled no 1.25 244.56
iii)Blacksmith no 2.75 160
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/Qtl =

16.19 Supplying fitting fixing U shaped strap…..

Unit=Each
A)Material
i)U shape iron strap with hole Nos 10.00 45.00
ii)Bolts,nuts washer kg 5.00 80.00
iii)carriage km 25.00 4.00
B)Lobour
i)Carpenter Nos 0.25 458.55
ii)Skilled lanour Nos 0.25 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/each

16.20 Labour for fitting wood work….with new bolt,nuts etc.

Unit=Cum
A)Material
i)Bolts,nuts washer kg 1.00 80.00
ii)Coal tar kg 1.00 40.00
iii)wear & tear of T&P
B)Lobour
i)Carpenter no 2.25 458.55
ii)Skilled lanour 4.00 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)
Rate/cum a)
b)

16.21 Labour for fitting 25cm to 30cm log beam…

Unit=Rm
Analysis for 5 RM

A)Material
i)Bolts,nuts washer kg 5 80.00
ii)Coal tar kg 1 40
iii)Sundries
B)Lobour
i)Carpenter no 1.25 458.55
ii)Skilled lanour no 5 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/Rm a)
b)

16.22 Labour for taking out old woodwork of bridge….

Unit=cum
A)Material
i)Bolts,nuts washer kg 10 80.00
ii)Coal tar kg 1 40
iii)wear&tear T&P
B)Lobour
i)Carpenter no 1.75 458.55
ii)Skilled labour no 4.5 244.56
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/cum

16.23 Labour for taking out old LOG BEAM…….

unit=RM

Analysis for 5 RM

Log beam=5x3.143x(.30x.30)=0.35cum
(Rate as per item no 17.22 above) cum 0.35 3097.00
Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/RM

16.52 Labour for spreading gravel

Unit=cum

A)Sundries,Wear&T&P

ii)Labour for spreading NO 0.55 244.56


Contractor’s profit & Overheads @ 12.5% on (a+b+c)
Rate/cum

b) Sand gravel

Unit=cum

A)Sundries,Wear&T&P

ii)Labour for spreading NO 0.23 244.56


Contractor’s profit & Overheads @ 12.5% on (a+b+c)

Rate/cum
399.45
2139.90
5380.32

8046.00
39504.00
12438.00
5298.00
13496.00
3520.00
34650.00
3465.00

458460.00

192850.00
418500.00
1920.00
150,008.33
0.00
1350075.00
3000.17
3000.00

171.19
713.30
2445.60

18450.00
10122.00
5172.00
4400.00

148800.00
232531.20
79987.20
98784.00
2400.00

135907.20
20812.80
167520.00
2400.00

75,497.06
0.00
679473.55
2264.91
2265.00

64614.26
0.00
581528.35
1938.43
1938.00

Total
102000.00
21675.00
2240.00
23750.34
54851.40
70000.00
10000.00
80.00
100.00
180.00
800.00
120.00

4585.50
7133.00
14673.60

39023.605

11707.00

34437.50

Total

37097.40
18700.00
19600.00
30000.00
5000.00
0.00
1783.25
3668.40

100.00
9856.45625

2957.00

425.00
425.00
420.00
40.00
300.00
50.00

356.65
244.56

10.00
283.90
35.49

864.00

32000.00
787.50

600.00
50.00
1000.00

857.49
457.3272
1345.08
4637.17

41734.57
5217.00

36097.40

142.15
75.8136
36315.36
4539.42

5107.00
12000.00
255.00

60.00
20.00

343.91
611.40
20.00
13310.31
1663.79

4991.00

8000.00
140.00
45.00
20.00

229.28
244.56
1084.85

4882.00
26400.00
787.50

0.00
600.00
20.00
1000.00

857.49
457.3272
1345.08
3933.42

4425.00

30467.40

142.15
75.8136
3835.67

4315.00

2400.00
840.00
600.00
20.00
20.00

343.91
1467.36
711.41

2134.00
1600.00
560.00
480.00
20.00
0.00
0.00
343.91
305.70
413.70

1862.00

22922.46
20.00
400.00
100.00

1146.38
305.70
611.40
3188.24

28132.00

22922.46
40.00
200.00
50

1146.38
305.70
611.40
3159.49

27878.00

16099.68
40.00
240.00
50

1146.38
305.70
611.40
2311.64

20805.00

15069.48
40.00
80.00
50

1490.29
305.70
611.40
2205.86

19853.00

23038.00
40.00
80.00
0.00
0.00
1490.29
305.70
611.40
3195.67

28761.00

18726.00
40.00
60.00
0.00
0.00
1146.38
611.40
305.70
2611.18

23501.00
23500.00
40.00
60.00
50.00

573.19
244.56
978.24
3180.75

5725.00

20000.00
40.00
60.00

573.19
244.56
978.24
2737.00

4927.00

545.30
80.00
10.00

286.59
152.85
134.34

1209.00

600.00
1400.00
100
2292.75
4891.20
1160.49

1306.00

600.00
350.00
100.00

859.78
3668.40
697.27

1046.00

875.00
600.00
10.00
1000.00
20.00

859.78
458.55
477.92

538.00

2823.33

142.15
75.81
380.16
428.00

40.00
180.00
210.00
20.00

343.91
1467.36
282.66

848.00

20.00
90.00
210.00
20.00

343.91
305.70
123.70

557.00

1400.00
400.00
100.00
60.00
657.00
0.00
573.19
2445.60
704.47

634.00
1400.00
400.00

60.00
657.00
0.00
343.91
1956.48
602.17

542.00

20.00
100.00
10.00

573.19
305.70
440.00
181.11

1630.00

450.00
400.00
100.00

114.64
61.14
140.72

1266.00

80.00
40.00
10

1031.74
978.24
267.50
2407.00
1350.00

400.00
40.00
10.00

573.19
1222.80
280.75

505.00
238.00

800.00
40.00
10.00

802.46
1100.52
344.12

3097.00

1083.95
135.49

244.00

1.00

134.51
16.94
152.00

1.00

56.25
7.16

64.00
(A) Usage Rates of Plant and Machinery
P&M-001 Air Compressor General Purpose

P&M-002 Batching and Mixing Plant (a) 30 cum capacity Concrete Mixing

P&M-003 Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing

P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat

P&M-005 Bitumen Boiler oil fired Bitumen Spraying

P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface

P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete

P&M-008 Concrete Bucket For Pouring concrete

P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing

P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing

P&M-011 Crane (a) 80 tonnes Lifting Purpose

P&M-012 Cranes b) 35 tonnes Lifting Purpose

P&M-013 Cranes c) 3 tonnes Lifting Purpose

P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing

P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing

P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat

P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading

P&M-018 Generator (a) 125 KVA Genration of electric Energy

P&M-019 Generator( b) 63 KVA Genration of electric Energy

P&M-020 GSB Plant 50 cum Producing GSB

P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix

P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix

P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix

P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix

P&M-025 Hydraulic Chip Spreader Surface Dressing

P&M-026 Hydraulic Excavator of 1 cum bucket Soil Ordinary/Soil Marshy / Soil Unsuitable

P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls

P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls

P&M-029 Kerb Casting Machine

P&M-030 Mastic Cooker Mastic Wearing coat

Page 1 of 1351
P&M-031 Mechanical Broom Hydraulic Surface Cleaning

P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM

P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal

P&M-034 Paver Finisher Hydrostatic with sensor control 100 TPH Paving of DBM/ BM/SDC/ Premix

P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC

P&M-036 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Boring attachment

P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface

P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells

P&M-039 Pot Hole Repair Machine Repair of potholes

P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands

P&M-041 Ripper Scarifying

P&M-042 Rotavator Scarifying

P&M-043 Road marking machine Road marking

P&M-044 Smooth Wheeled Roller 8 tonne Soil Compaction /BM Compaction

P&M-045 Tandem Road Roller Rolling of Aspalt Surface

P&M-046 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc.

P&M-047 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc.

P&M-048 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc.

P&M-049 Transit Mixer 4.0/4.5 cum Transportation of Concrete Mix to site

P&M-050 Transit Mixer 4/4.5 cum Transportation of Concrete Mix to site

P&M-051 Transit Mixer 3.0 cum Transportation of Concrete Mix to site

P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site

P&M-053 Tractor Pulling

P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator

P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper

P&M-056 Truck 5.5 cum per 10 tonnes Material Transport

P&M-057 Truck 5.5 cum per 10 tonnes Material Transport

P&M-058 Truck 5.5 cum per 10 tonnes Material Transport

P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM

P&M-060 Water Tanker Water Transport

Page 2 of 1351
P&M-061 Water Tanker Water Transport

P&M-062 Wet Mix Plant 60 TPH Wet Mix

P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay.

P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour

P&M-065 Belt conveyor system

P&M-066 Boat to carry atleast 20 persons

P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output)

P&M-068 Cement concrete batch mix plant @ 75 cum per hour

P&M-069 Cold milling machine @ 20 cum per hour

P&M-070 Crane 5 tonne capacity

P&M-071 Crane 10 tonne capacity

P&M-072 Crane 15 tonne capacity

P&M-073 Crane 20 tonne capacity

P&M-074 Crane 40 T capacity

P&M-075 Crane with grab 0.75 cum capacity

P&M-076 Compressor with guniting equipment along with accessories

P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour.

P&M-078 Epoxy Injection gun

P&M-079 Generator 33 KVA

P&M-080 Generator 100 KVA

P&M-081 Generator 250 KVA

P&M-082 Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of

P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement)

P&M-084 Jack for Lifting 40 tonne lifting capacity.

P&M-084_1 Jack for Lifting 150 tonne lifting capacity.

P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig)

P&M-086 Plate compactor

P&M-087 Snow blower equipment 140 HP @ 600 cum per hour

P&M-088 Texturing machine (for rigid pavement)

P&M-089 Truck Trailor 30 tonne capacity

P&M-090 Truck Trailor 30 tonne capacity

P&M-091 Tunnel Boring machine

P&M-092 Vibrating Pile driving hammer complete with power unit and accessories.

Page 3 of 1351
P&M-093 Wet Mix Plant 100 TPH

P&M-094 Wet Mix Plant 75 TPH

Page 4 of 1351
ge Rates of Plant and Machinery
capacity in cfm 170/250 hour 354.00

cum/hour 20 hour 1957.00

cum/hour 13 hour 1590.00

sqm/hour 1750 hour 954.00

capacity in litre 1500 hour 1,590.00

cum / hour 20 hour 954.00

cum / hour 33 / 22 hour 234.00


capacity in
1 hour 15.00
cum
cum/hour 2.5 hour 188.00

cum/hour 7.5 hour 188.00

hour 1136.00

hour 759.00

hour 318.00

300/
cum/hour hour 3194.00
150/250
200/
cum/hour hour 1965.00
120/150
sqm/hour 1750 hour 717.00

cum/hour 60 /25 hour 882.00

KVA 100 hour 1388.00

KVA 50 hour 514.00

cum/hour 40 hour 1140.00

cum/hour 40 hour 22823.00

cum/hour 30 hour 16575.00

cum/hour 25 hour 14115.00

cum/hour 17 hour 12379.00

sqm/hour 1500 hour 2380.00

60 /60 /60 hour 1365.00

TPH 100 hour 7220.00

TPH 200 hour 14389.00

Rm/hour 80 hour 284.00


capacity in
1 hour 56.00
tonne

Page 5 of 1351
sqm/hour 1250 hour 337.00
200/200/50/
cum/hour hour 2795.00
50
sqm/hour 2700 hour 2072.00

cum/hour 40 hour 1129.00

cum/hour 40/30 hour 853.00

Rm/hour 2 to 3 hour 4665.00

cum/hour 25 hour 652.00

cum/hour 1.5 to 2.00 hour 3453.00

cum/hour 4 hour 884.00

hour 113.00

cum/hour 60 hour 31.00

cum/hour 25 hour 22.00

Sqm/hour 100 hour 192.00

cum/hour 70/25 hour 652.00

cum/hour 30 hour 652.00


Capacity in
5.5 km 12.75
cum
Capacity in
5.5 tonne.km 7.00
cum
Capacity in
5.5 hour 680.00
cum

cum/hour 4.5 hour 828.00

cum/hour 4.5 tonne.km 7.00

cum/hour 3 hour 759.00

cum/hour 3 tonne.km 7.00

capacity in HP 50 hour 323.00

hour 431.00

hour 440.00

capacity/cum 4.5 km 325.00

capacity/cum 4.5 hour 717.00

capacity/cum 4.5 tonne.km 7.00

cum/hour 100/60/60 hour 1421.00

capacity in KL 6 hour 440.00

Page 6 of 1351
capacity in KL 6 km 17.60

cum/hour 25 hour 1149.00

cutting hard clay. hour 284.00

roducing an average output of 75 tonne per hour hour 2000.00

hour 2100.00

hour 200.00

ur (effective output) hour 5229.00

hour 4000.00

hour 685.00

hour 725.00

hour 750.00

hour 775.00

hour 800.00

hour 845.00

hour 1185.00

ssories hour 400.00

but not less than 75 tonnes/hour. hour 1859.00

hour 300.00

hour 311.00

hour 621.00

hour 1500.00

pment including all components and accessories for pneumatic method of well sinking. hour input

ment) hour 150.00

day 200.00

day 1500.00

(Hydraulic rig) hrs 1000.00

hour 218.00

r hour 1000.00

hour 800.00

hour 300.00

t.km input

hour input

nit and accessories. hour 850.00

Page 7 of 1351
hour 1672.00

1353.00

Page 8 of 1351
(B) Labour

Description of Labour
Blacksmith (IInd class)

Blacksmith (Ist class)/ Welder/ Plumber/ Electrician

Blaster (Stone cutter)

Carpenter I Class

Chiseller (Head Mazdoor)

Driller (Jumper)

Diver

Electrician

Fitter

Mali

Mason (IInd class)

Mason (Ist class)

Mate / Supervisor

Mazdoor

Mazdoor/Dresser (Semi Skilled)

Mazdoor/Dresser/Sinker (Skilled)

Medical Officer

Operator(grouting)

Painter I class

Para medical personnel

Page 9 of 1351
(C) Materials

Description

Stone Boulder of size 150 mm and below at Cruser Plant

Supply of quarried stone 150 - 200 mm size for Hand Broken at site

Boulder with minimum size of 300 mm for Pitching at Site

Coarse sand at Mixing Plant

Coarse sand at Site

Fine sand at Site

Moorum at Site

Gravel/Quarry spall at Site

Granular Material or hard murrum for GSB works at Site

Granular Material or hard murrum for GSB works at Mixing Plant

Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant/Binding material

Filter media/Filter Material as per Table 300-3 (MoRT&H Specification)

Page 10 of 1351
Close graded Granular sub-base Material 53 mm to 9.5 mm

Close graded Granular sub-base Material 37.5 mm to 9.5 mm

Close graded Granular sub-base Material 26.5 mm to 9.5 mm

Close graded Granular sub-base Material 9.5 mm to 4.75 mm

Close graded Granular sub-base Material 9.5 mm to 2.36 mm

Close graded Granular sub-base Material 4.75mm to 2.36 mm

Close graded Granular sub-base Material 4.75mm to 75 micron mm

Close graded Granular sub-base Material 2.36 mm

Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve.

Coarse graded Granular sub-base Material 2.36 mm & below

Coarse graded Granular sub-base Material 4.75mm to 75 micron mm

Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm

Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm

Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm

Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm

Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm

Coarse graded Granular sub-base Material 53 mm to 26 .5mm

Aggregates below 5.6 mm

Aggregates 22.4 mm to 2.36 mm

Aggregates 22.4 mm to 5.6 mm

Aggregates 45 mm to 2.8 mm

Aggregates 45 mm to 22.4 mm

Aggregates 53 mm to 2.8 mm

Aggregates 53 mm to 22.4 mm

Aggregates 63 mm to 2.8 mm

Aggregates 63 mm to 45 mm

Aggregates 90 mm to 45 mm

Aggregates 10 mm to 5 mm

Aggregates 11.2 mm to 0.09 mm

Aggregates 13.2 mm to 0.09 mm

Aggregates 13.2 mm to 5.6 mm

Page 11 of 1351
Aggregates 13.2 mm to 10 mm

Aggregates 20 mm to 10 mm

Aggregates 25 mm to 10 mm

Aggregates 19 mm to 6 mm

Aggregates 37.5 mm to 19 mm

Aggregates 37.5 mm to 25 mm

Aggregates 6 mm nominal size

Aggregates 10 mm nominal size

Aggregates 13.2/12.5 mm nominal size

Aggregates 20 mm nominal size

Aggregates 25 mm nominal size


Aggregates 40 mm nominal size

Page 12 of 1351
G.I. pipe 100 mm dia

Acrylic polymer bonding coat

Alluminium Paint

Aluminium alloy plate 2mm Thick

Aluminium alloy/galvanised steel


Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of drilling
holes, nuts, bolts etc.and signs as applicable
Aluminium studs 100 x 100 mm fitted with lense reflectors

Barbed wire

Bearing (Cost of parts)

Bearing (Cast steel rocker bearing assembly of 250 tonne )


Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by
the process of vulcanisation,)
Bearing (Forged steel roller bearing of 250 tonne)

Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against
stainless steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all comp

Bearing (PTFE sliding plate bearing assembly of 80 tonnes )

Bearing (Supply of sliding plate bearing of 80 tonne)

Bentonite

Binding wire

Bitumen ( Cationic Emulsion ) ( CSS-1h)

Bitumen ( Cationic Emulsion ) ( CSS-1)(IS:8887-2004)

Bitumen ( Cationic Emulsion ) ( CSS-2)

Bitumen ( Cationic Emulsion ) ( CSS-1)

Bitumen ( Cationic Emulsion ) ( RS-1)

Bitumen ( Cationic Emulsion ) ( RS-2)

Bitumen ( Cationic Emulsion ) ( MS)

Bitumen (60-70 grade OR VG-30)

Bitumen (80-100 grade OR VG-10 )

Bitumen (CRMB-55 )
Bitumen( Penetration at 25 deg C=15+/- 5

Bitumen (Polymer modified graded) PMB

Brick

C.I.shoes for the pile

Page 13 of 1351
Cement

TMT - IS 1786 (Fe-500 D) Primary Producer

TMT - IS 1786 (Fe-500 D) Secondary Producer with other make.

Coller for joints 300 mm dia

Compressible Fibre Board(20mm thick)

Connectors/ Staples

Copper Plate(12m long x 250mmwide)

Corrosion resistant Structural steel

Corrugated sheet, 3 mm thick, "Thrie" beam section railing

Credit for excavated rock found suitable for use

Curing compound

Delineators from ISI certified firm as per the standard drawing given in IRC - 79

Earth Cost or compensation for earth taken from private land


Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to
clause 915.1 of IRC: 83 (part II),
Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each

Epoxy resin-hardner mix for prime coat

Epoxy compound with accessories for preparing epoxy mortar

Epoxy mortar

Epoxy primer

Flag of red color cloth 600 x 600 mm

Flowering Plants

Galvanised MS flat clamp

Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size.

Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long


Gelatin 80%
Geo grids(TGB-40)

Geomembrane(1.5mm thick)
Geonets(Geonet 121)
Geotextile(GNW-280)

Geotextile filter fabric(GNW-280)

GI bolt 10 mm Dia

Grouting pump with agitator

Grass (Doob)

Page 14 of 1351
Grass (Fine)

HDPE pipes 75mm dia

HDPE pipes 90mm dia

Hedge plants

Helical pipes 600mm diameter

Hot applied thermoplastic compound

HTS strand

Joint Sealant Compound

Jute netting, open weave, 2.5 cm square opening for seeding and Mulching

LDO for steam curing

M.S. Clamps

M.S. Clamps

M.S.shoes @ 35 Kg per pile of 15 m

super ductile IS 1786 ( Fe-500)reinforcement bar.

Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm assembly
comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel

Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint assembly
containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and

Nipples 12mm

Nuts and bolts

Paint

Pavement Marking Paint

Paving Fabric(1.5mmthick)

Perforated geosynthetic pipe 150 mm dia

Perforated pipe of cement concrete, internal dia 100 mm

Pesticide

Pipes 200 mm dia, 2.5 m long for drainage

Plastic sheath, 1.25 mm thick for dowel bars

Plastic tubes 50 cm dia, 1.2 m high

Polymer braids

Pre moulded Joint filler,25 mm thick for expansion joint.

Pre-coated stone chips of 13.2 mm nominal size

Pre-moulded asphalt filler board

Page 15 of 1351
Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days

Primer

Quick setting compound

Random Rubble Stone

RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia

RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia

RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia

Reflectorising glass beads

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips)

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips)

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips)

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips)

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips)

Rivets

Sand bags (Cost of sand and Empty cement bag)

Sapling 2 m high 25 mm dia

Scrap tyres of size 900 x 20

Seeds

Selected earth

Separation Membrane of impermeable plastic sheeting 125 micron thick

Sheathing duct

Shrubs

Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing

Well decayedFarm yard manure @ 0.18 cum per 100 sqm at site of work for turfing

Sodium vapour lamp ( 250 Watts )

Square Rubble Coursed Stone

Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level

Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level

Steel drum 300 mm dia 1.2 m high/empty bitumen drum

Page 16 of 1351
Steel helmet and cushion block on top of pile head during driving.

Steel pipe 25 mm external dia as per IS:1239

Steel pipe 50 mm external dia as per IS:1239

Steel wire rope 20 mm

Steel wire rope 40 mm

Strip seal expansion join

Structural Steel

Super plastisizer admixture IS marked as per 9103-1999

Synthetic Geogrids as per clause 3102.8 and approved design and specifications.(TGU-150)

Through and bond stone

Tie rods 20mm diameter

Tiles size 300 x 300 mm and 25 mm thick

Timber

Traffic cones with 150 mm reflective sleeve

Tube anchorage set complete with bearing plate, permanent wedges etc

Unstaked lime

Water

Anti stripping agent

Water based cement paint

Welded steel wire fabric

Wire mesh 50mm x 50mm size of 3mm wire

Wooden ballies 2" Dia for bracing

Wooden ballies 8" Dia and 9 m long

Wooden packing

Wooden staff for fastening of flag 25 mm dia, one m long

Bamboo Bholuka or Barua 55mm to 100mm dia and 6m long

Bamboo Jati or Bethua 50mm to mm dia and 6m long

Wood local first class piles 25cm to 30cm

Wood local first class planks 25cm to 38cm thick

Wood local first class small section

Wood local first class scantling up to 15cmx15cm

Wood local first class heavy section above 15cmx15cm

Wood sal piles 25cm to 30cm dia

Wood sal planks 25cm to 38cm dia thick

Page 17 of 1351
Wood sal scantling heavy section above 15cm to 15cm

Wood sal scantling upto15x15cm


Admixture ( Masterplast Pl-1 or equivalent )

Admixture ( Masterplast SPl-2 or equivalent )

Air entraining and water reducing plasticiser conforming to IS-9103-1999


( Masterplast PAE or equivalent)
Accelerating plasticiser conforming to IS-9103-1999
( Masterplast APCL or equivalent )

PVC rain water pipe 100mm Dia

Page 18 of 1351
Overheads for Road Works 2.5 %

Contractors profit for Road Works @ 10%+GST


10 %
@12+Labour Welfare cess@1%)
for input of Overheads or Con
Overheads for Bridge Works 10 %
type in collum C as
Type symble of apostrope(') the
Overheads for Bridge Works (Rehabilitation) 10 % space then symble of percentag
%
Contractors profit for Bridge Works 10 %

Lead from Mixing Plant to working site 10 km

Lead for E/W borow area to site 3 km

Lead for fly ash from source to site km

Page 19 of 1351
Summary of Rates calculated and used for analysis of rates of other items

Printing new letter and figures of any shade (ii) English Roman

Painting Two Coats on New Concrete Surfaces


Painting angle iron post two coats
Cement mortor 1:2 (Excluding OH & CP)
Cement mortor 1:3 (Excluding OH & CP)
Cement mortor 1:6 (Excluding OH & CP)

Course Rubble masonary in cement mortor 1:3 (including OH & CP)

Random Rubble masonary in cement mortor 1:6 (including OH & CP)

(A) Without plasticiser

PCC Grade M15 including OH & CP for Open Foundation by Mixer

PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M20 including OH & CP for Open Foundation by Batching Plant

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

PCC Grade M25 including OH & CP for Open Foundation by Batching Plant
PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

Page 20 of 1351
RCC Grade M35 including OH & CP for Open Foundation by Batching Plant

RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant
RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant
(B) With Plasticiser

PCC Grade M15 including OH & CP for Open Foundation by Mixer

PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M20 including OH & CP for Open Foundation by Batching Plant

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

PCC Grade M25 including OH & CP for Open Foundation by Batching Plant
PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

RCC Grade M35 including OH & CP for Open Foundation by Batching Plant

RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant
RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching
Plant
(A) Without plasticiser

PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Mixer

PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

Page 21 of 1351
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Mixer
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Mixer
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Mixer

PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant

(B) With Plasticiser

PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Mixer

PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Mixer
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Mixer
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Mixer

PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant

Excavation for Structures (Manual Means)


Excavation for Structures (Mechenical Meanse)
RCC Grade M20 for super-structure including OH & CP by Batching Plant
RCC Grade M20 for super-structure including OH & CP by Batching Plant
RCC Grade M20 for super-structure including OH & CP by Batching Plant

RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant

RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant

Supplying ,fitting and placing TMT/HYSD bar reinforcement in super-structure excluding OH & CP

Page 22 of 1351
with TMT CRS (Fe-500) Rebar
with TMT Rebar
With other make ISI marked TMT rebar
Supplying, fitting and placing HYSD/TMT including OH & CP for sub-structure
with TMT CRS (Fe-500) Rebar
with TMT Rebar
With other make ISI marked TMT rebar
Fog Seal
Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm
Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm
Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked
area above 50 %
Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile
Slurry Seal Case-I 5 mm thickness
Slurry Seal Case-II 3 mm thickness
Slurry Seal Case III 1.5 mm thickness
Surface Dressing Case-I 19 mm nominal chipping size
Surface Dressing Case-II 13 mm nominal size chipping

Page 23 of 1351
(B) Labour

Unit Rate
day 356.65
day 458.55
day 356.65
day 458.55
day 285.32
day 356.65
day 356.65
day 458.55
day 458.55
day 244.56
day 285.32
day 458.55
day 356.65
day 244.56
day 285.32
day 356.65
day 1045.00
day 285.32
day 458.55
day 475.00

Page 24 of 1351
(C) Materials

Rate
Description Unit

cum 1055.00
at site cum 1030.00
cum 1001.00
cum 792.00
cum 792.00
cum 792.00

cum 698.00
Cum 987.00
Cum 1029.00
ant Cum 1029.00

tching Plant / Crushing Plant/Binding material Cum 410.00

cification) Cum 1013.00

Page 25 of 1351
cum 1119.00###

cum 1107.00###

cum 1101.00###

cum 1084.00###

cum 1041.50###

cum 1029.00###

cum 1029.00###

cum 698.00###

cum 698.00###

cum 698.00###

cum 1029.00###

cum 1029.00###

cum 1084.00###

cum 1089.00###

cum 1056.00###

cum 1107.00###

cum 1124.00###

cum 1104.00###

cum 1440.50###

cum 1440.50###

cum 1204.50###

cum 1623.00###

cum 1174.50###

cum 2035.00###

cum 1593.00###

cum 1936.00###

cum 1837.00###

cum 1510.00###

cum 1510.00###

cum 1599.50###

cum 1599.50###

Page 26 of 1351
cum 2006.00###

cum 1554.00###

cum 1827.00###

cum 1846.50###

cum 1639.00###

cum 1619.00###

cum 1807.00###

cum 1916.00###

cum 2095.00###

cum 1777.00###

cum 1738.00###
cum 1500.00###

Page 27 of 1351
metre 680.00

litre 185.00

litre 260.00

sqm 6396.00

tonne 52920.00
ve sheeting including 2% towards lettering, cost of angle iron, cost of drilling
sqm 438.00

nos 438.00

kg 78.00

nos 126000.00
nos 103840.00
al layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by
nos 13500.00

nos 120360.00

on supported by a disc, PTFE pads providing sliding surfaces against


nos 37672.00
ricated structural steel assemblies duly painted with all comp

nos 14042.00

nos 13794.00
C
kg 11.00 o
m
kg 70.00 p
S
ha
tonne 39800.00 en
S
ly
hl
tonne 39183.00 e
S
l
hl
tonne 36400.00 S e
hl
tonne 37900.00 S el
hl
tonne 35400.00 el
l
tonne 40642.00 l
I
tonne 30939.00 O
C
I
tonne 33854.00 O
C
I
tonne 32910.00 O S
C
h
tonne 37323.00 e
l
tonne 40572.00 S
l
h
tonne 46400.00 e
l
each 8.00 l
kg 96.00

Page 28 of 1351
tonne 6200.00

tonne 40763.00

tonne 41525.00

nos 484.00

sqm 976.00

each 67.00

kg 174.00

tonne 60000.00

kg 79.00

cum 168.00

liter 87.00

g given in IRC - 79 each 0.00

d cum 0.00
d by using chloroprene, elastomer for elastomeric slab unit conforming to
metre 16400.00

gms each 100 nos 392.00

kg 800.00

r kg 575.00

kg 186.00

kg 373.00

each 9.00

each 28.00

nos 262.00

woven with 4mm dia. GI wire in rolls of required size. sqm 247.00

4 m long kg 55.00
kg 120.00
sqm 216.00

sqm 301.00
sqm 280.00
sqm 104.00

sqm 122.00

nos 13.00
hour 280.00

kg 20.00

Page 29 of 1351
kg 24.00

metre 113.00

metre 162.00

each 10.00

metre 78.00

litre 80.00

tonne 140420.00

kg 585.00

and Mulching sqm 76.00

litre 30.00

nos 19.00

kg 90.00

kg 38.00

tonne 40100.00

atering to a horizontal movement beyond 70 mm and upto 140mm assembly


metre 76700.00
ene seal, anchorage elements, support and control system, all steel

al movement beyond 140mm and upto 210mm box/box seal joint assembly
metre 129800.00
wo central beams, chloroprene seal, anchorage elements, support and

nos 160.00

kg 90.00

litre 245.00

litre 60.00

sqm 286.00

metre 465.00

metre 95.00

kg 455.00

metre 565.00

sqm 22.00

nos 52.00

metre 22.00

sqm 672.00

cum 3528.00

sqm 616.00

Page 30 of 1351
pa at 28 days kg 43.00

kg 214.00

kg 30.00

cum 1135.00

metre 7799.00
metre 9427.00
metre 1052.00

kg 73.00

102. (Copper Strips) metre 1150.00

102. (Galvanised carbon steel strips) metre 254.00

102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips) metre 678.00

102. (Stainless steel strips) metre 681.00

102. Aluminium strips) metre 458.00

each 5.00

nos 15.00

each 39.00

nos 28.00

kg 31.00

cum 176.00

micron thick sqm 34.00


metre 85.00

each 11.00

of work for turfing cum 56.00

site of work for turfing cum 157.00

each 7500.00

cum 560.00

ghting to mount light at 5 m height above deck level each 7000.00

ghting to mount light at 9 m height above road level each 10000.00

nos 62.00

Page 31 of 1351
ving. kg 55.00

metre 68.00
metre 131.00

kg 159.00

kg 96.00

metre 4602.00

tonne 56160.00

kg 103.00

n and specifications.(TGU-150) sqm 345.00

each 8.00

nos 52.00

each 54.00

cum 32400.00

nos 1229.00

wedges etc nos 1420.00

tonne 6608.00

KL 40.00

Kg 224.00
litre 40.00

kg 47.00

kg 47.00

each 234.00

each 3658.00

cum 28320.00

each 56.00

each 85.00
each 70.00
metre 4020.00
cum 32754.00
cum 25215.00
cum 36743.00
cum 29750.00
metre 4493.00
cum 35958.00

Page 32 of 1351
cum 30135.00
cum 29545.00
Lit 128.00
Lit
59.00
-9103-1999 Lit
59.00

Lit
94.00

RM 183.00

Page 33 of 1351
for input of Overheads or Contractors profit please
type in collum C as like below
Type symble of apostrope(') then input value then one
space then symble of percentage (%) for example '08
%

Page 34 of 1351
for analysis of rates of other items Unit Rate
per cm
English Roman height per 0.70
letter
s sqm 54.00
sqm 80.00
cum 6,081.00
cum 4,942.00
cum 3,374.00

(including OH & CP) cum 4,972.00

6 (including OH & CP) cum 5,055.00

Foundation by Mixer cum 7,119.00

m Basic Cost of Labour, Material & Mechinery by Mixer cum 4,585.00

m Basic Cost of Labour, Material & Mechinery by Mixer cum 5,088.00

um Basic Cost of Labour, Material & Mechinery by Mixer cum 5,238.00

Foundation by Batching Plant cum 8,010.00

um Basic Cost of Labour, Material & Mechinery by Batching


cum 5,159.00

m Basic Cost of Labour, Material & Mechinery by Mixer cum 5,508.00

Foundation by Batching Plant cum 8,547.00


m Basic Cost of Labour, Material & Mechinery by Batching
cum 5,518.00

um Basic Cost of Labour, Material & Mechinery by Mixer cum 5,664.00

um Basic Cost of Labour, Material & Mechinery by Batching


cum 5,584.00

m Basic Cost of Labour, Material & Mechinery by Mixer cum 5,554.00

m Basic Cost of Labour, Material & Mechinery by Batching


cum 5,473.00

um Basic Cost of Labour, Material & Mechinery by Mixer cum 5,689.00

um Basic Cost of Labour, Material & Mechinery by Batching


cum 5,611.00

um Basic Cost of Labour, Material & Mechinery by Mixer cum 5,805.00

Page 35 of 1351
Foundation by Batching Plant cum 8,808.00

Foundation by Batching Plant cum 5,899.00


um Basic Cost of Labour, Material & Mechinery by Batching
cum 5,727.00

Foundation by Mixer cum 7,936.00

m Basic Cost of Labour, Material & Mechinery by Mixer cum 5,111.00

m Basic Cost of Labour, Material & Mechinery by Mixer cum 5,614.00

um Basic Cost of Labour, Material & Mechinery by Mixer cum 5,764.00

Foundation by Batching Plant cum 8,827.00

um Basic Cost of Labour, Material & Mechinery by Batching


cum 5,685.00

m Basic Cost of Labour, Material & Mechinery by Mixer cum 6,152.00

Foundation by Batching Plant cum 9,412.00


m Basic Cost of Labour, Material & Mechinery by Batching
cum 6,076.00

um Basic Cost of Labour, Material & Mechinery by Mixer cum 6,313.00

um Basic Cost of Labour, Material & Mechinery by Batching


cum 6,234.00

m Basic Cost of Labour, Material & Mechinery by Mixer cum 6,207.00

m Basic Cost of Labour, Material & Mechinery by Batching


cum 6,126.00

um Basic Cost of Labour, Material & Mechinery by Mixer cum 6,344.00

um Basic Cost of Labour, Material & Mechinery by Batching


cum 6,266.00

um Basic Cost of Labour, Material & Mechinery by Mixer cum 6,485.00

Foundation by Batching Plant cum 9,854.00

Foundation by Batching Plant cum 6,599.00


um Basic Cost of Labour, Material & Mechinery by Batching
cum 6,407.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 5,414.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 5,314.00

Page 36 of 1351
m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
cum 5,637.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 5,534.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 5,682.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 5,582.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 5,789.00

oundation (Bottom Plug) by Batching Plant cum 8,881.00


m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
cum 5,686.00

oundation (Well Cap) by Batching Plant cum 8,881.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 6,005.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 5,905.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 6,280.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 6,177.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 6,335.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 6,253.00

m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by


cum 6,464.00

oundation (Bottom Plug) by Batching Plant cum 9,940.00


m Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
cum 6,361.00

oundation (Well Cap) by Batching Plant cum 9,854.00

cum 283.00
) cum 47.00
OH & CP by Batching Plant cum 9,304.00
OH & CP by Batching Plant cum 10,104.00
OH & CP by Batching Plant cum 10,351.70

ormwork and excluding OH & CP by Batching Plant cum


6,836.00

formwork and excluding OH & CP by Batching Plant cum


5,697.00

einforcement in super-structure excluding OH & CP

Page 37 of 1351
tonne 47,001.00
tonne 47001.00

tonne 46155.00

ding OH & CP for sub-structure


tonne 68,685.00
tonne 79,808.00
tonne 4,551.00
sqm 49.00
rbing Membrane (SAM) crack width less than 6 mm sqm 86.00
orbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 100.00
orbing Membrane (SAM) crack width above 9 mm and cracked
sqm 131.00

mpregnated Geotextile sqm 207.00


sqm 79.00
sqm 55.00
sqm 33.00
ing size sqm 98.00
chipping sqm 82.00

Page 38 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

CHAPTER-16-A

FOUNDATIONS

Sr No Description Unit Quantity Rate Rs Cost Rs


16.66 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(I) Without dewatering
16.66 (i) Depth upto 3 m
a) Labour
Mate day 0.14 356.65 49.93
Mazdoor day 3.50 244.56 855.96
b) Overhead charges @ 10 % on (a) 90.59
c) Contractor's profit @ 10 % on (a+b) 99.65
Cost for 10 cum = a+b+c 1096.13
Rate per cum = (a+b+c)/10 109.61
say 110.00
1. Cost of dewatering may be added where required upto,
10 per cent of labour cost Assessment for dewatering shall
be made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding mars
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
16.66 A (I) Depth 3 m to 6 m
(ii)
a) Labour
Mate/Supervisor day 0.26 356.65 92.73
Mazdoor day 4.50 244.56 1100.52
b) Overhead charges @ 10 % on (a) 119.32
c) Contractor's profit @ 10 % on (a+b) 131.26
Cost for 10 cum = a+b+c 1443.83
Rate per cum = (a+b+c)/10 144.38
say 144.00
Cost of dewatering may be added where required upto 15
per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.
16.66 A (I) Depth above 6 m
(iii)
a) Labour
Mate/Supervisor day 0.24 356.65 85.60
Mazdoor day 6.00 244.56 1467.36
b) Overhead charges @ 10 % on (a) 155.30

Page 1 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

c) Contractor's profit @ 10 % on (a+b) 170.83


Cost for 10 cum = a+b+c 1879.08
Rate per cum = (a+b+c)/10 187.91
say 188.00
(II) With dewatering
16.66 A (II) Depth upto 3 m
(i)
a) Labour
Mate day 0.14 356.65 49.93
Mazdoor day 3.50 244.56 855.96
Cost of dewatering @ 10% of labour cost 90.59
b) Overhead charges @ 10 % on (a) 99.65
c) Contractor's profit @ 10 % on (a+b) 109.61
Cost for 10 cum = a+b+c 1205.74
Rate per cum = (a+b+c)/10 120.57
say 121.00
1. Cost of dewatering may be added where required upto,
10 per cent of labour cost Assessment for dewatering shall
be made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding mars
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
16.66A (II) Depth 3 m to 6 m
(ii)
a) Labour
Mate/Supervisor day 0.18 356.65 64.20
Mazdoor day 4.50 244.56 1100.52
Cost of dewatering @ 15% of labour cost 174.71
b) Overhead charges @ 10 % on (a) 133.94
c) Contractor's profit @ 10 % on (a+b) 147.34
Cost for 10 cum = a+b+c 1620.70
Rate per cum = (a+b+c)/10 162.07
say 162.00
Cost of dewatering may be added where required upto 15
per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.
16.66 A (II) Depth above 6 m
(iii)
a) Labour
Mate/Supervisor day 0.24 356.65 85.60
Mazdoor day 6.00 244.56 1467.36
Cost of dewatering @ 20% of labour cost 155.30
b) Overhead charges @ 10 % on (a) 170.83
c) Contractor's profit @ 10 % on (a+b) 187.91
Cost for 10 cum = a+b+c 2066.98
Rate per cum = (a+b+c)/10 206.70
say 207.00

Page 2 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

1. Cost of dewatering may be added where required upto 20


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
B Mechanical Means
(I) Without dewatering
16.66 B (I) Depth upto 3 m
(i)
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 356.65 114.13
Mazdoor day 8.00 244.56 1956.48
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00
c) Overhead charges @ 10 % on (a+b) 1026.06
d) Contractor's profit @ 10 % on (a+b+c) 1128.67
Cost for 240 cum = a+b+c+d 12415.34
Rate per cum = (a+b+c+d)/240 51.73
say 52.00
Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made
as per site conditions..
16.66 B (I) Depth 3 m to 6 m
(ii)
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 356.65 114.13
Mazdoor day 8.00 244.56 1956.48
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00
c) Overhead charges @ 10 % on (a+b) 1026.06
d) Contractor's profit @ 10 % on (a+b+c) 1128.67
Cost for 210 cum = a+b+c+d 12415.34
Rate per cum = (a+b+c+d)/210 59.12
say 59.00
Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
16.66B (I) Depth above 6m
(iii)
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 356.65 142.66
Mazdoor day 10.00 244.56 2445.60
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00
c) Overhead charges @ 10 % on (a+b) 1077.83
d) Contractor's profit @ 10 % on (a+b+c) 1185.61

Page 3 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Cost for 180 cum = a+b+c+d 13041.69


Rate per cum = (a+b+c+d)/180 72.45
say 72.00
1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.
(II) With dewatering
16.66 B (II) Depth upto 3 m
(i)
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 356.65 114.13
Mazdoor day 8.00 244.56 1956.48
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00
Cost of dewatering @ 5% of (a+b) 513.03
c) Overhead charges @ 10 % on (a+b) 1077.36
d) Contractor's profit @ 10 % on (a+b+c) 1185.10
Cost for 240 cum = a+b+c+d 13036.10
Rate per cum = (a+b+c+d)/240 54.32
say 54.00
Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made
as per site conditions..
16.66 B (II) Depth 3 m to 6 m
(ii)
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 356.65 114.13
Mazdoor day 8.00 244.56 1956.48
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00
Cost of dewatering @ 7.5% of (a+b) 769.55
c) Overhead charges @ 10 % on (a+b) 1103.02
d) Contractor's profit @ 10 % on (a+b+c) 1213.32
Cost for 210 cum = a+b+c+d 13346.49
Rate per cum = (a+b+c+d)/210 63.55
say 64.00
Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
16.66 B (II) Depth above 6m
(iii)
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 356.65 142.66

Page 4 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Mazdoor day 10.00 244.56 2445.60


b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00
Cost of dewatering @ 10% of (a+b) 1077.83
c) Overhead charges @ 10 % on (a+b) 1077.83
d) Contractor's profit @ 10 % on (a+b+c) 1293.39
Cost for 180 cum = a+b+c+d 14227.30
Rate per cum = (a+b+c+d)/180 79.04
say 79.00
1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.

16.66 II Ordinary Rock (not requiring blasting)


(I) Without dewatering
Manual Means
Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.26 356.65 92.73
Mazdoor day 5.00 244.56 1222.80
b) Overhead charges @ 10 % on (a) 131.55
c) Contractor's profit @ 10 % on (a+b) 144.71
Cost for 10 cum = a+b+c 1591.79
Rate per cum = (a+b+c)/10 159.18
say 159.00
(I) With dewatering
Manual Means
Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 356.65 71.33
Mazdoor day 5.00 244.56 1222.80
Cost of dewatering @ 10% of labour cost 129.41
b) Overhead charges @ 10 % on (a) 142.35
c) Contractor's profit @ 10 % on (a+b) 156.59
Cost for 10 cum = a+b+c 1722.49
Rate per cum = (a+b+c)/10 172.25
say 172.00
Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
16.66(II) Mechanical Means

Page 5 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


(I) Without dewatering
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 356.65 85.60
Mazdoor day 6.00 244.56 1467.36
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00
c) Overhead charges @ 10 % on (a+b) 974.30
d) Contractor's profit @ 10 % on (a+b+c) 1071.73
Cost for 180 cum = a+b+c+d 11788.98
Rate per cum = (a+b+c+d)/180 65.49
say 65.00
(ii) With dewatering
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 356.65 85.60
Mazdoor day 6.00 244.56 1467.36
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00
Cost of dewatering @ 10% of (a+b) 974.30
c) Overhead charges @ 10 % on (a+b) 974.30
d) Contractor's profit @ 10 % on (a+b+c) 1169.15
Cost for 180 cum = a+b+c+d 12860.70
Rate per cum = (a+b+c+d)/180 71.45
say 71.00

1.Cost of dewatering upto 10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
16.66 (III) Hard Rock ( requiring blasting )
Manual Means
(I) Without dewatering
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 356.65 124.83
Driller day 0.50 356.65 178.33
Blaster day 0.25 356.65 89.16
Mazdoor day 8.00 244.56 1956.48
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for hour 1.00 354.00 354.00
drilling.
c) Material
Blasting Material kg 3.50 120.00 420.00
Detonator electric each 14.00 3.92 54.88
d) Overhead charges @ 10 % on (a+b+c) 317.77
e) Contractor's profit @ 10 % on (a+b+c+d) 349.54
Cost for 10 cum = a+b+c+d+e 3844.99

Page 6 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate per cum = (a+b+c+d+e)/10 384.50


say 384.00
(ii) With dewatering
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 356.65 124.83
Driller day 0.50 356.65 178.33
Blaster day 0.25 356.65 89.16
Mazdoor day 8.00 244.56 1956.48
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for hour 1.00 354.00 354.00
drilling.
c) Material
Blasting Material kg 3.50 120.00 420.00
Detonator electric each 14.00 3.92 54.88
Cost of dewatering @ 10% of (a+b) 270.28
d) Overhead charges @ 10 % on (a+b+c) 317.77
e) Contractor's profit @ 10 % on (a+b+c+d) 376.57
Cost for 10 cum = a+b+c+d+e 4142.29
Rate per cum = (a+b+c+d+e)/10 414.23
say 414.00

Cost of dewatering @ 10 per cent of (a+b) may be


added, where required Assessment for dewatering shall be
made as per site conditions.
16.66 (IV) Hard Rock ( blasting prohibited )
(I) Without dewatering
Unit = cum
Taking output = 10 cum
Mechanical Means
a) Labour
Mate day 0.20 356.65 71.33
Mazdoor day 5.00 244.56 1222.80
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 354.00 2124.00
breaker
c) Overhead charges @ 10 % on (a+b) 341.81
d) Contractor's profit @ 10 % on (a+b+c) 375.99
Cost for 10 cum = a+b+c+d 4135.94
Rate per cum = (a+b+c+d)/10 413.59
say 414.00
(ii) With dewatering
Unit = cum
Taking output = 10 cum
Mechanical Means
a) Labour
Mate day 0.20 356.65 71.33
Mazdoor day 5.00 244.56 1222.80
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 354.00 2124.00
breaker

Page 7 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Cost of dewatering @ 10% of (a+b) 341.81


c) Overhead charges @ 10 % on (a+b) 341.81
d) Contractor's profit @ 10 % on (a+b+c) 410.18
Cost for 10 cum = a+b+c+d 4511.93
Rate per cum = (a+b+c+d)/10 451.19
say 451.00
1. Cost of dewatering upto10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
16.66-V Marshy Soil
(I) Without dewatering
Unit = cum
Taking output = 10 cum
Depth upto 3 m
Manual means
a) Labour
Mate/Supervisor day 0.40 356.65 142.66
Mazdoor day 10.00 244.56 2445.60
b) Machinery
Tractor-trolley for removal. hour 2.67 323.00 862.41
c) Overhead charges @ 10 % on (a+b) 345.07
d) Contractor's profit @ 10 % on (a+b+c) 379.57
Cost for 10 cum = a+b+c+d 4175.31
Rate per cum = ( a+b+c+d)/ 10 417.53
say 418.00
(ii) With dewatering
Unit = cum
Taking output = 10 cum
Depth upto 3 m
Manual means
a) Labour
Mate/Supervisor day 0.40 356.65 142.66
Mazdoor day 10.00 244.56 2445.60
b) Machinery
Tractor-trolley for removal. hour 2.67 323.00 862.41
Cost of dewatering @ 30% of (a) 776.48
c) Overhead charges @ 10 % on (a+b) 345.07
d) Contractor's profit @ 10 % on (a+b+c) 457.22
Cost for 10 cum = a+b+c+d 5029.44
Rate per cum = ( a+b+c+d)/ 10 502.94
say 503.00

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required
may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1 (i) to (iv) for ordinary soil

Page 8 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


16.66-VI Mechanical Means
(I) Without dewatering
a) Labour
Mate day 0.08 356.65 28.53
Mazdoor for dressing sides, bottom and backfilling day 2.00 244.56 489.12
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.17 1365.00 232.05
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 680.00 306.00
c) Overhead charges @ 10 % on (a+b) 105.57
d) Contractor's profit @ 10 % on (a+b+c) 116.13
Cost for 10 cum = a+b+c+d 1277.40
Rate per cum = (a+b+c+d)/10 127.74
say 128.00
(ii) With dewatering
a) Labour
Mate day 0.08 356.65 28.53
Mazdoor for dressing sides, bottom and backfilling day 2.00 244.56 489.12
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.17 1365.00 232.05
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 680.00 306.00
Cost of dewatering @ 20% of (a+b) 211.14
c) Overhead charges @ 10 % on (a+b) 105.57
d) Contractor's profit @ 10 % on (a+b+c) 137.24
Cost for 10 cum = a+b+c+d 1509.65
Rate per cum = (a+b+c+d)/10 150.97
say 151.00
1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1 (i) to (iv) for ordinary soil
Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 356.65 42.80
Mazdoor for dressing sides, bottom and backfilling day 3.00 244.56 733.68
b) Machinery
Tractor-trolley for transportation hour 2.00 323.00 646.00
c) Overhead charges @ 10 % on (a+b) 142.25
d) Contractor's profit @ 10 % on (a+b+c) 156.47
Cost for 6 cum = a+b+c+d 1721.20
Rate per cum = (a+b+c+d)/6 286.87
say 287.00
16.67 Filling Annular Space Around Footing in Rock
Unit = cum
Taking out put = 1 cum

Page 9 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Lean cement concrete 1:3:6 nominal mix. Rate may be


taken as per item 12.4.
16.68 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 356.65 3.57
Mazdoor day 0.30 244.56 73.37
b) Material
Sand (assuming 20 per cent voids) cum 1.20 1251.00 1501.20
c) Overhead charges @ 10 % on (a+b) 157.81
d) Contractor's profit @ 10 % on (a+b+c) 173.59
Rate per cum = a+b+c+d 1909.54
say 1910.00
16.69 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 356.65 228.26
Mason day 1.00 458.55 458.55
Mazdoor day 15.00 244.56 3668.40
b) Material
40 mm Aggregate cum 13.50 1761.00 23773.50
coarse Sand cum 6.75 1251.00 8444.25
cement tonne 3.95 7600.00 30020.00
Cost of water KL 18.00 40.00 720.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Water tanker 6 KL capacity hour 2.00 440.00 880.00
d) Overhead charges @ 10 % on (a+b+c) 7118.70
e) Contractor's profit @ 10 % on (a+b+c+d) 7830.57
Cost for 15 cum = a+b+c+d+e 86136.22
Rate per cum = (a+b+c+d+e)/15 5742.41
say 5742.00
Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
16.70 Brick Masonry Work in Cement Mortar 1:3 in
Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 8.00 20000.00
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.20 1501.20 1801.44
analysis)
b) Labour

Page 10 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Mate day 0.48 356.65 171.19


Mason day 4.00 458.55 1834.20
Mazdoor day 8.00 244.56 1956.48
c) Overhead charges @ 10 % on (a+b) 2576.33
d) Contractor's profit @ 10 % on (a+b+c) 2833.96
Cost for 5 cum = a+b+c+d 31173.61
Rate per cum (a+b+c+d)/5 6234.72
say 6235.00
16.71 Cement Mortar 1:3 (1 cement : 3 sand)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 7600.00 3876.00
Sand cum 1.05 1251.00 1313.55
b) Labour
Mate day 0.04 356.65 14.27
Mazdoor day 0.90 244.56 220.10
Total Material and Labour = (a+b) say 5424.00
Cement Mortar1:2 (1cement :2 sand)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.67 7600.00 5107.20
Sand cum 0.93 1251.00 1163.43
b) Labour
Mate day 0.04 356.65 14.27
Mazdoor day 0.90 244.56 220.10
Total Material and Labour = (a+b) say 6505.00
Cement Mortar1:4 (1cement :4 sand)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 7600.00 3064.32
Sand cum 1.12 1251.00 1401.12
b) Labour
Mate day 0.04 356.65 14.27
Mazdoor day 0.90 244.56 220.10
Total Material and Labour = (a+b) say 4700.00
Cement Mortar1:6 (1cement :6 sand)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.29 7600.00 2188.80

Page 11 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Sand cum 1.34 1251.00 1672.77


b) Labour
Mate day 0.04 356.65 14.27
Mazdoor day 0.90 244.56 220.10
Total Material and Labour = (a+b) say 4096.00
16.72 Stone Masonry Work in Cement Mortar 1:3 in
Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.50 560.00 3080.00
Through and bond stone each 35.00 8.00 280.00
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.50 4942.00 7413.00
analysis)
b) Labour
Mate day 0.66 356.65 235.39
Mason day 7.50 458.55 3439.13
Mazdoor day 9.00 244.56 2201.04
c) Overhead charges @ 10 % on (a+b) 1664.86
d) Contractor's profit @ 10 % on (a+b+c) 1831.34
Cost for 5 cum = a+b+c+d 20144.75
Rate per cum (a+b+c+d)/5 4028.95
say 4029.00
Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 448.00 2464.00
Through and bond stone each 35.00 8.00 280.00
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.55 4942.00 7660.10
analysis)
b) Labour
Mate day 0.62 356.65 221.12
Mason day 6.00 458.55 2751.30
Mazdoor day 9.00 244.56 2201.04
c) Overhead charges @ 10 % on (a+b) 1557.76
d) Contractor's profit @ 10 % on (a+b+c) 1713.53
Cost for 5 cum = a+b+c+d 18848.85
Rate per cum (a+b+c+d)/5 3769.77
say 3770.00
The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
16.73 Plain/Reinforced Cement Concrete in Open
Foundation complete as per Drawing and Technical
Specifications cl. no. 1200,1500 & 1700

Page 12 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 7600.00 31388.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 8.10 1761.00 14264.10
20 mm Aggregate cum 4.05 2088.00 8456.40
10 mm Aggregate cum 1.35 2513.00 3392.55
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 4989.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 2993.00
of material, labour and machinery

e) Overhead charges @ 10 % on (a+b+c+d) 7781.80


f) Contractor's profit @ 10 % on (a+b+c+d+e) 8559.99
Cost for 15 cum = a+b+c+d+e+f 94159.84
Rate per cum = (a+b+c+d+e+f)/15 6277.32
say 6277.00
Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
16.74 PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 7600.00 39216.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 5608.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 3364.39
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 8747.41
f) Contractor's profit @ 10 % on (a+b+c+d+e) 9622.15
Cost for 15 cum = a+b+c+d+e+f 105843.64
Rate per cum = (a+b+c+d+e+f)/15 7056.24

Page 13 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

say 7056.00
16.75 RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 7600.00 39596.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 5827.00
(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 3496.12
e) Overhead charges @ 10 % on (a+b+c+d) 9089.91
f) Contractor's profit @ 10 % on (a+b+c+d+e) 9998.90
Cost for 15 cum = a+b+c+d+e+f 109987.93
Rate per cum = ( a+b+c+d+e+f )/15 7332.53
say 7333.00
16.76 With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 7600.00 316616.00
Coarse Sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00

Page 14 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Lead beyond 1 km, L-lead in km tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6 234.00 1404.00


Per Cum Basic Cost of Labour, Material & Machinery 5730.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 27499.73
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 71499.30
f) Contractor's profit @ 10 % on (a+b+c+d+e) 78649.24
Cost for 120 cum = a+b+c+d+e+f 865141.59
Rate per cum = ( a+b+c+d+e+f )/120 7209.51
say 7210.00
16.77 PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7600.00 45524.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 6028.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 3390.66
e) Overhead charges @ 10 % on (a+b+c+d) 9380.84
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10318.92
Cost for 15 cum = a+b+c+d+e+f 113508.11
Rate per cum = ( a+b+c+d+e+f )/15 7567.21
say 7567.00
16.78 With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 7600.00 364420.00
Coarse sand cum 54.00 1251.00 67554.00
40 mm Aggregate cum 43.20 1761.00 76075.20

Page 15 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

20 mm Aggregate cum 43.20 2088.00 90201.60


10 mm Aggregate cum 21.60 2513.00 54280.80
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer (300L)
Concrete Pump hour 6 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 5934.00
(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. 26699.66
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 73869.06
f) Contractor's profit @ 10 % on (a+b+c+d+e) 81255.96
cost of 120 cum = a+b+c+d+e+f 893815.60
Rate per cum = (a+b+c+d+e+f)/120 7448.46
say 7448.00
16.79 RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7600.00 45980.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 6253.00
(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c. 3517.01
e) Overhead charges @ 10 % on (a+b+c+d) 9730.40
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10703.44

Page 16 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

cost of 15 cum = a+b+c+d+e+f 117737.85


Rate per cum (a+b+c+d+e+f )/15 7849.19
say 7849.00
16.80 With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 7600.00 367688.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity 1 cum hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6155.00
(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 27696.20
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 76626.15
f) Contractor's profit @ 10 % on (a+b+c+d+e) 84288.77
cost of 120 cum = a+b+c+d+e+f 927176.43
Rate per cum (a+b+c+d+e+f )/120 7726.47
say 7726.00
16.81 PCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7600.00 46208.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
b) Labour

Page 17 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Mate day 0.86 356.65 306.72


Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 6074.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 3188.56
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 9429.03
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10371.93
cost of 15 cum = a+b+c+d+e+f 114091.21
Rate per cum (a+b+c+d+e+f )/15 7606.08
say 7606.00
16.82 Using Batching Plant, Transit Mixer and Concrete
Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 7600.00 369360.00
Coarse sand cum 54.00 1251.00 67554.00
40 mm Aggregate cum 43.20 1761.00 76075.20
20 mm Aggregate cum 43.20 2088.00 90201.60
10 mm Aggregate cum 21.60 2513.00 54280.80
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 5975.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 25092.58
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 74202.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 81622.58
cost of 120 cum = a+b+c+d+e+f 897848.43
Rate per cum (a+b+c+d+e+f )/120 7482.07

Page 18 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

say 7482.00
16.83 RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7600.00 46360.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 6278.00
(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. 3295.84
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 9746.28
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10720.91
cost of 15 cum = a+b+c+d+e+f 117930.03
Rate per cum = (a+b+c+d+e+f)/15 7862.00
say 7862.00
16.84 Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 7600.00 370880.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00

Page 19 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6182.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. 25961.51
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 76771.88
f) Contractor's profit @ 10 % on (a+b+c+d+e) 84449.07
cost of 120 cum = a+b+c+d+e+f 928939.77
Rate per cum (a+b+c+d+e+f )/120 7741.16
say 7741.00
16.85 RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7600.00 48108.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 6395.00
(a+b+c)
d) Formwork @ 3 per cent on a+b+c 2877.45
e) Overhead charges @ 10 % on (a+b+c+d) 9879.24
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10867.17
cost of 15 cum = a+b+c+d+e+f 119538.86
Rate per cum = (a+b+c+d+e+f)/15 7969.26
say 7969.00
16.86 H Using Batching Plant, Transit Mixer and Concrete
Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 7600.00 384864.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60

Page 20 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6298.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 3% 22672.24
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 10 % 77841.36
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10 % 85625.49
cost of 120 cum = a+b+c+d+e+f 941880.40
Rate per cum = (a+b+c+d+e+f)/120 7849.00
say 7849.00
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
16.87 Plain/Reinforced Cement Concrete in Open
Foundation complete as per Drawing and Technical
Specifications cl. no. 1200,1500 & 1700 including
providing plasticiser ( Masterplast PL-1/SPL-2 or
equivalent ), air entraining and water reducing
plasticiser ( Masterplast PAE or equivalent) and
accelerating plasticiser ( Masterplast ACPL or
equivalent) conforming to IS-9103-1999.

PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 7600.00 31388.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 8.10 1761.00 14264.10
20 mm Aggregate cum 4.05 2088.00 8456.40
10 mm Aggregate cum 1.35 2513.00 3392.55
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit Lit 16.52 128.00 2114.56
per Tonne of cement
Air entraining and water reducing plasticiser Lit 12.39 59.00 731.01
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3Lit per Tonne of cement

Page 21 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Accelerating plasticiser conforming to IS-9103-1999 Lit 57.82 94.00 5435.08


( Masterplast APCL or equivalent ) @ 14Lit per
Tonne of cement
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 5541.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 3324.23
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 8642.99
f) Contractor's profit @ 10 % on (a+b+c+d+e) 9507.29
Cost for 15 cum = a+b+c+d+e+f 104580.21
Rate per cum = (a+b+c+d+e+f)/15 6972.01
say 6972.00
Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
16.88 PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 7600.00 39216.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit Lit 20.64 128.00 2641.92
per Tonne of cement
Air entraining and water reducing plasticiser Lit 15.48 59.00 913.32
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3Lit per Tonne of cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 72.24 94.00 6790.56
( Masterplast APCL or equivalent ) @ 14Lit per
Tonne of cement
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 6298.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 3778.22
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 9823.37
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10805.71
Cost for 15 cum = a+b+c+d+e+f 118862.79

Page 22 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate per cum = (a+b+c+d+e+f)/15 7924.19


say 7924.00
16.89 RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 7600.00 39596.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit Lit 20.84 128.00 2667.52
per Tonne of cement
Air entraining and water reducing plasticiser Lit 15.63 59.00 922.17
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3Lit per Tonne of cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 72.94 94.00 6856.36
( Masterplast APCL or equivalent ) @ 14Lit per
Tonne of cement
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 6524.00
(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 3913.96
e) Overhead charges @ 10 % on (a+b+c+d) 10176.30
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11193.93
Cost for 15 cum = a+b+c+d+e+f 123133.24
Rate per cum = ( a+b+c+d+e+f )/15 8208.88
say 8209.00
16.90 C With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 7600.00 316616.00
Coarse Sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit Lit 166.64 128.00 21329.92
per tonne cement

Page 23 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Air entraining and water reducing plasticiser Lit 124.98 59.00 7373.82
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @3Lit per tonne cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 583.24 94.00 54824.56
( Masterplast APCL or equivalent ) @ 14Lit per
tonne cement
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 km, L-lead in km (300L) tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6 234.00 1404.00


Per Cum Basic Cost of Labour, Material & Machinery 6426.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 30840.86
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 80186.25
f) Contractor's profit @ 10 % on (a+b+c+d+e) 88204.87
Cost for 120 cum = a+b+c+d+e+f 970253.60
Rate per cum = ( a+b+c+d+e+f )/120 8085.45
say 8085.00
16.91 PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7600.00 45524.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 29.95 59.00 1767.05
per MT cement
Air entraining and water reducing plasticiser Lit 17.97 59.00 1060.23
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 94.00 7882.84
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72

Page 24 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Mason day 1.50 458.55 687.83


Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 6742.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 3792.29
e) Overhead charges @ 10 % on (a+b+c+d) 10492.01
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11541.21
Cost for 15 cum = a+b+c+d+e+f 126953.33
Rate per cum = ( a+b+c+d+e+f )/15 8463.56
say 8464.00
16.92 D With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 7600.00 364420.00
Coarse sand cum 54.00 1251.00 67554.00
40 mm Aggregate cum 43.20 1761.00 76075.20
20 mm Aggregate cum 43.20 2088.00 90201.60
10 mm Aggregate cum 21.60 2513.00 54280.80
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 239.75 59.00 14145.25
per MT cement
Air entraining and water reducing plasticiser Lit 143.85 59.00 8487.15
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 671.30 94.00 63102.20
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer (300L)
Concrete Pump hour 6 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6648.00
(a+b+c)

Page 25 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

d) Formwork @ 3.75 per cent of cost of concrete i.e. 29914.71


cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 82764.02
f) Contractor's profit @ 10 % on (a+b+c+d+e) 91040.42
cost of 120 cum = a+b+c+d+e+f 1001444.67
Rate per cum = (a+b+c+d+e+f)/120 8345.37
say 8345.00
16.93 RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7600.00 45980.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 30.25 59.00 1784.75
per MT cement
Air entraining and water reducing plasticiser Lit 18.15 59.00 1070.85
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 94.00 7961.80
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 6974.00
(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c. 3922.66
e) Overhead charges @ 10 % on (a+b+c+d) 10852.71
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11937.98
cost of 15 cum = a+b+c+d+e+f 131317.74
Rate per cum (a+b+c+d+e+f )/15 8754.52
say 8755.00
16.93 E With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 7600.00 367688.00
Coarse sand cum 54.00 1251.00 67554.00

Page 26 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

20 mm Aggregate cum 64.80 2088.00 135302.40


10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 241.90 59.00 14272.10
per MT cement
Air entraining and water reducing plasticiser Lit 145.14 59.00 8563.26
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 677.32 94.00 63668.08
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity 1 cum hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6876.00
(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 30940.08
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 85600.88
f) Contractor's profit @ 10 % on (a+b+c+d+e) 94160.97
cost of 120 cum = a+b+c+d+e+f 1035770.69
Rate per cum (a+b+c+d+e+f )/120 8631.42
say 8631.00
16.94 PCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7600.00 46208.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 30.40 59.00 1793.60
per MT cement
Air entraining and water reducing plasticiser Lit 18.24 59.00 1076.16
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement

Page 27 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Accelerating plasticiser conforming to IS-9103-1999 Lit 85.12 94.00 8001.28


( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 6799.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 3569.05
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 10554.18
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11609.60
cost of 15 cum = a+b+c+d+e+f 127705.55
Rate per cum (a+b+c+d+e+f )/15 8513.70
say 8514.00
16.95 F Using Batching Plant, Transit Mixer and Concrete
Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 7600.00 369360.00
Coarse sand cum 54.00 1251.00 67554.00
40 mm Aggregate cum 43.20 1761.00 76075.20
20 mm Aggregate cum 43.20 2088.00 90201.60
10 mm Aggregate cum 21.60 2513.00 54280.80
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 243.00 59.00 14337.00
per MT cement
Air entraining and water reducing plasticiser Lit 145.80 59.00 8602.20
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 680.40 94.00 63957.60
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00

Page 28 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6699.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 28133.97
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 83196.17
f) Contractor's profit @ 10 % on (a+b+c+d+e) 91515.79
cost of 120 cum = a+b+c+d+e+f 1006673.64
Rate per cum (a+b+c+d+e+f )/120 8388.95
say 8389.00
16.96 RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7600.00 46360.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 30.50 59.00 1799.50
per MT cement
Air entraining and water reducing plasticiser Lit 18.30 59.00 1079.70
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 94.00 8027.60
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 7005.00
(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. 3677.58
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 10875.14
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11962.65
cost of 15 cum = a+b+c+d+e+f 131589.17
Rate per cum = (a+b+c+d+e+f)/15 8772.61
say 8773.00
16.97 G Using Batching Plant, Transit Mixer and Concrete
Pump

Page 29 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 7600.00 370880.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 244.00 59.00 14396.00
per MT cement
Air entraining and water reducing plasticiser Lit 146.40 59.00 8637.60
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 683.20 94.00 64220.80
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6909.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. 29015.41
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 85802.71
f) Contractor's profit @ 10 % on (a+b+c+d+e) 94382.98
cost of 120 cum = a+b+c+d+e+f 1038212.82
Rate per cum (a+b+c+d+e+f )/120 8651.77
say 8652.00
16.98 RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7600.00 48108.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20

Page 30 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 31.65 59.00 1867.35


per MT cement
Air entraining and water reducing plasticiser Lit 18.99 59.00 1120.41
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 94.00 8330.28
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Per Cum Basic Cost of Labour, Material & Machinery 7149.00
(a+b+c)
d) Formwork @ 3 per cent on a+b+c 3216.99
e) Overhead charges @ 10 % on (a+b+c+d) 11045.00
f) Contractor's profit @ 10 % on (a+b+c+d+e) 12149.50
cost of 15 cum = a+b+c+d+e+f 133644.53
Rate per cum = (a+b+c+d+e+f)/15 8909.64
say 8910.00
16.99 H Using Batching Plant, Transit Mixer and Concrete
Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 7600.00 384864.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 253.20 59.00 14938.80
per MT cement
Air entraining and water reducing plasticiser Lit 151.92 59.00 8963.28
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 708.96 94.00 66642.24
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00

Page 31 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Loader1 cum capacity hour 6.00 882.00 5292.00


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 7053.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 25388.57
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 87167.42
f) Contractor's profit @ 10 % on (a+b+c+d+e) 95884.16
cost of 120 cum = a+b+c+d+e+f 1054725.79
Rate per cum = (a+b+c+d+e+f)/120 8789.38
say 8789.00
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
WELL FOUNDATION
16.99.1 Providing and Constructing Temporary Island 16 m
diameter for Construction of Well Foundation for 8m
dia. Well.
Assuming depth of water 1.0 m and height of island to
be 1.25 m.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 251.20 0.0 0.00
Sand bags each 750.00 15.00 11250.00
b) Labour
Mate day 0.40 356.65 142.66
Mazdoor for filling sand bags, stitching and placing day 15.00 244.56 3668.40
c) Machinery
Crane with grab 1 cum capacity hour 20.00 759.00 15180.00
Consumables @ 2.5 per cent of (c) above 379.50
d) Overhead charges @ 10 % on (a+b+c) 3062.06
e) Contractor's profit @ 10 % on (a+b+c+d) 3368.26
Rate per No. (a+b+c+d+e) 37050.88
say 37051.00
It is assumed that earth will be available within the working
space of crane with grab bucket.
16.99.2 Assuming depth of water 4.0 m and height of island
4.5 m.
Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 0.00 0.00
Sand bags each 6000.00 15.00 90000.00
Wooden ballies 8" Dia and 9 m long each 95.00 3658.00 347510.00
Wooden ballies 2" Dia for bracing metre 190.00 234.00 44460.00
b) Labour

Page 32 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Mate day 5.60 356.65 1997.24


Mazdoor for piling 8" dia ballies for piling 8" dia day 18.00 244.56 4402.08
ballies
Mazdoor for bracing with 2" dia ballies day 12.00 244.56 2934.72
Mazdoor for filling sand bags, stitching and placing day 110.00 244.56 26901.60
c) Machinery
Crane with grab 1 cum capacity hour 50.00 759.00 37950.00
Consumables and other arrangements for piling ballies @ 13903.89
2.5 per cent of (a+b+c).
d) Overhead charges @ 10 % on (a+b+c) 57005.95
e) Contractor's profit @ 10 % on (a+b+c+d) 62706.55
Rate per No. (a+b+c+d+e) 689772.03
say 689772.00
For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
16.99.3 Providing and constructing one span service road to
reach island location from one pier location to another
pier location
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth cum 450.00 0.00 0.00
Sand bags each 300.00 15.00 4500.00
b) Labour
Mate day 0.24 356.65 85.60
Mazdoor for filling sand bags, stitching and placing day 6.00 244.56 1467.36
c) Machinery
Front end Loader 1 cum capacity hour 27.00 882.00 23814.00
Tipper 5.5 cum capacity hour 28.00 680.00 19040.00
d) Overhead charges @ 10 % on (a+b+c) 4890.70
e) Contractor's profit @ 10 % on (a+b+c+d) 5379.77
Cost for 30 m (a+b+c+d+e) 59177.42
Rate per m (a+b+c+d+e)/30 1972.58
say 1973.00
16.99.4 Providing and Laying Cutting Edge of Mild Steel
weighing 40 kg per metre for Well Foundation
complete as per Drawing and Technical Specification.

Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per tonne 1.05 62000.00 65100.00
cent wastage
Nuts & bolts Kg 20.00 90.00 1800.00
b) Labour
(for cutting, bending, making holes, joining, welding
and erecting in position)
Mate day 1.32 356.65 470.78
Fitter day 5.50 356.65 1961.58

Page 33 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Blacksmith day 5.50 458.55 2522.03


Welder day 5.50 458.55 2522.03
Mazdoor day 16.50 244.56 4035.24
Electrodes, cutting gas and other consumables @ 10 per 6690.00
cent of cost of (a) above
c) Overhead charges @ 10 % on (a+b) 8510.16
d) Contractor's profit @ 10 % on (a+b+c) 9361.18
Rate per MT (a+b+c+d) 102972.99
say 102973.00
16.99.5 Plain/Reinforced cement concrete, in well foundation
complete as per drawing and technical specification and
steel shuttering formwork.

(A) Without plasticiser

Unit = 1 cum
Taking output = 1 cum
Well curb
RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5238.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1047.60
e) Overhead charges @ 10 % on (a+b+c+d) 628.56
f) Contractor's profit @ 10 % on (a+b+c+d+e) 691.42
Rate perm (a+b+c+d+e+f) 7605.58
say 7606.00
16.99.6 A (i) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5159.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1031.80
e) Overhead charges @ 10 % on (a+b+c+d) 619.08
f) Contractor's profit @ 10 % on (a+b+c+d+e) 680.99
Rate perm (a+b+c+d+e+f) 7490.87
say 7491.00
16.99.7 A RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5664.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1132.80
e) Overhead charges @ 10 % on (a+b+c+d) 679.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 747.65

Page 34 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate perm (a+b+c+d+e+f) 8224.13


say 8224.00
16.99.8 A With Batching Plant, Transit Mixer and Concrete Pump
(ii)
Per Cum Basic Cost of Labour, Material & Machinery 5584.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1116.80
e) Overhead charges @ 10 % on (a+b+c+d) 670.08
f) Contractor's profit @ 10 % on (a+b+c+d+e) 737.09
Rate perm (a+b+c+d+e+f) 8107.97
say 8108.00
16.99.9 A RCC M30 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5689.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1137.80
e) Overhead charges @ 10 % on (a+b+c+d) 682.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 750.95
Rate perm (a+b+c+d+e+f) 8260.43
say 8260.00
16.99.10 A With Batching Plant, Transit Mixer and Concrete Pump
(ii)
Per Cum Basic Cost of Labour, Material & Machinery 5611.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1122.20
e) Overhead charges @ 10 % on (a+b+c+d) 673.32
f) Contractor's profit @ 10 % on (a+b+c+d+e) 740.65
Rate perm (a+b+c+d+e+f) 8147.17
say 8147.00
16.99.11 A RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.0 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5805.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1161.00
e) Overhead charges @ 10 % on (a+b+c+d) 696.60
f) Contractor's profit @ 10 % on (a+b+c+d+e) 766.26
Rate perm (a+b+c+d+e+f) 8428.86
say 8429.00
16.99.12 A With Batching Plant, Transit Mixer and Concrete Pump
(iii)

Page 35 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery 5727.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1145.40
e) Overhead charges @ 10 % on (a+b+c+d) 687.24
f) Contractor's profit @ 10 % on (a+b+c+d+e) 755.96
Rate perm (a+b+c+d+e+f) 8315.60
say 8316.00
If curb concrete is carried out within steel liner, cost of
formwork shall be excluded.

16.99.13 Well steining


PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 4585.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 458.50
e) Overhead charges @ 10 % on (a+b+c+d) 504.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 554.79
Rate perm (a+b+c+d+e+f) 6102.64
say 6103.00
16.99.14 B PCC M20 Grade
Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5088.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 508.80
e) Overhead charges @ 10 % on (a+b+c+d) 559.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 615.65
Rate perm (a+b+c+d+e+f) 6772.13
say 6772.00
16.99.15 B RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5238.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 523.80
e) Overhead charges @ 10 % on (a+b+c+d) 576.18
f) Contractor's profit @ 10 % on (a+b+c+d+e) 633.80
Rate perm (a+b+c+d+e+f) 6971.78
say 6972.00

Page 36 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


16.99.16 B With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery 5159.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 515.90
e) Overhead charges @ 10 % on (a+b+c+d) 567.49
f) Contractor's profit @ 10 % on (a+b+c+d+e) 624.24
Rate perm (a+b+c+d+e+f) 6866.63
say 6867.00
16.99.17 B PCC M25 Grade
Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5508.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 550.80
e) Overhead charges @ 10 % on (a+b+c+d) 605.88
f) Contractor's profit @ 10 % on (a+b+c+d+e) 666.47
Rate perm (a+b+c+d+e+f) 7331.15
say 7331.00
16.99.18 B With Batching Plant, Transit Mixer and Concrete Pump
(iv)
Per Cum Basic Cost of Labour, Material & Machinery 5518.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 551.80
e) Overhead charges @ 10 % on (a+b+c+d) 606.98
f) Contractor's profit @ 10 % on (a+b+c+d+e) 667.68
Rate perm (a+b+c+d+e+f) 7344.46
say 7344.00
16.99.19 B RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5664.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 566.40
e) Overhead charges @ 10 % on (a+b+c+d) 623.04
f) Contractor's profit @ 10 % on (a+b+c+d+e) 685.34
Rate perm (a+b+c+d+e+f) 7538.78
say 7539.00
16.99.20 B With Batching Plant, Transit Mixer and Concrete Pump
(v)
Per Cum Basic Cost of Labour, Material & Machinery 5584.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 558.40

Page 37 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

e) Overhead charges @ 10 % on (a+b+c+d) 614.24


f) Contractor's profit @ 10 % on (a+b+c+d+e) 675.66
Rate perm (a+b+c+d+e+f) 7432.30
say 7432.00
16.99.21 B PCC M30 Grade
Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5554.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 555.40
e) Overhead charges @ 10 % on (a+b+c+d) 610.94
f) Contractor's profit @ 10 % on (a+b+c+d+e) 672.03
Rate perm (a+b+c+d+e+f) 7392.37
say 7392.00
16.99.23 B With Batching Plant, Transit Mixer and Concrete Pump
(vi)
Per Cum Basic Cost of Labour, Material & Machinery 5473.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 547.30
e) Overhead charges @ 10 % on (a+b+c+d) 602.03
f) Contractor's profit @ 10 % on (a+b+c+d+e) 662.23
Rate perm (a+b+c+d+e+f) 7284.56
say 7285.00
16.99.24 B RCC M30 Grade
Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5689.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 568.90
e) Overhead charges @ 10 % on (a+b+c+d) 625.79
f) Contractor's profit @ 10 % on (a+b+c+d+e) 688.37
Rate perm (a+b+c+d+e+f) 7572.06
say 7572.00
16.99.25 B With Batching Plant, Transit Mixer and Concrete Pump
(vii)
Per Cum Basic Cost of Labour, Material & Machinery 5611.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 561.10
e) Overhead charges @ 10 % on (a+b+c+d) 617.21
f) Contractor's profit @ 10 % on (a+b+c+d+e) 678.93
Rate perm (a+b+c+d+e+f) 7468.24
say 7468.00

Page 38 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


16.99.26 B RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5805.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 580.50
e) Overhead charges @ 10 % on (a+b+c+d) 638.55
f) Contractor's profit @ 10 % on (a+b+c+d+e) 702.41
Rate perm (a+b+c+d+e+f) 7726.46
say 7726.00
16.99.27B With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery 5727.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 572.70
e) Overhead charges @ 10 % on (a+b+c+d) 629.97
f) Contractor's profit @ 10 % on (a+b+c+d+e) 692.97
Rate perm (a+b+c+d+e+f) 7622.64
say 7623.00

16.99. 28B RCC M40 Grade


Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7600.00 392160.00
Coarse Sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.84 356.65 299.59
Meson day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Per Cum Basic Cost of Labour, Material & Machinery 50870.00
(a+b+c)

Page 39 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

d) Formwork @ 10 per cent on cost of concrete i.e. 76303.73


cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 83934.10
f) Contractor's profit @ 10 % on (a+b+c+d+e) 92327.52
cost of 120 cum = a+b+c+d+e+f 1015602.67
Rate per cum = (a+b+c+d+e+f)/120 8463.36
say 8463.00
16.99.29 B Bottom Plug
Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 7600.00 42180.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Machinery 5934.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4204.70
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 9320.07


e) Contractor's profit @ 10 % on (a+b+c+d) 10252.07
cost of 15 cum = a+b+c+d+e 112772.80
Rate per cum = (a+b+c+d+e)/15 7518.19
say 7518.00
16.99.30C Using Batching Plant, Transit Mixer and
(i) Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material

Page 40 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Cement tonne 44.40 7600.00 337440.00


Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 5903.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 32747.48
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 74107.91


e) Contractor's profit @ 10 % on (a+b+c+d) 81518.70
cost of 120 cum = a+b+c+d+e 896705.66
Rate per cum = (a+b+c+d+e)/120 7472.55
say 7473.00
16.99.31 C PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7600.00 45524.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00

Page 41 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6156.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4076.90
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 9641.69


e) Contractor's profit @ 10 % on (a+b+c+d) 10605.85
cost of 15 cum = a+b+c+d+e 116664.40
Rate per cum = (a+b+c+d+e)/15 7777.63
say 7778.00
16.99.32 C Using Batching Plant, Transit Mixer and
(ii) Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 7600.00 363888.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6124.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 34069.88
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 76884.95


e) Contractor's profit @ 10 % on (a+b+c+d) 84573.44
cost of 120 cum = a+b+c+d+e 930307.85
Rate per cum = (a+b+c+d+e)/120 7752.57
say 7753.00
16.99.33 C PCC Grade M30

Page 42 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7600.00 46208.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6202.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4406.10
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 9743.01


e) Contractor's profit @ 10 % on (a+b+c+d) 10717.31
cost of 15 cum = a+b+c+d+e 117890.37
Rate per cum = (a+b+c+d+e)/15 7859.36
say 7859.00
16.99.34 C Using Batching Plant, Transit Mixer and
(iii) Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 7600.00 369664.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00

Page 43 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Loader 1 cum capacity hour 6.00 882.00 5292.00


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6172.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 34358.68
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 77491.43


e) Contractor's profit @ 10 % on (a+b+c+d) 85240.57
cost of 120 cum = a+b+c+d+e 937646.26
Rate per cum = (a+b+c+d+e)/120 7813.72
say 7814.00
16.99.34-D PCC Grade M35
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 7600.00 47804.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6308.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4485.90
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 9910.59


e) Contractor's profit @ 10 % on (a+b+c+d) 10901.64
cost of 15 cum = a+b+c+d+e 119918.09
Rate per cum = (a+b+c+d+e)/15 7994.54
say 7995.00

Page 44 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


16.99.35 Using Batching Plant, Transit Mixer and
(iv) Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 7600.00 382128.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6276.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 34981.88
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 78800.15


e) Contractor's profit @ 10 % on (a+b+c+d) 86680.16
cost of 120 cum = a+b+c+d+e 953481.77
Rate per cum = (a+b+c+d+e)/120 7945.68
say 7946.00
16.99.36 Intermediate plug
Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5414.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 541.40
e) Contractor's profit @ 10 % on (a+b+c+d) 595.54
Rate per cum = (a+b+c+d+e) 6550.94
say 6551.00
16.99.36D Using Batching Plant, Transit Mixer and
(i) Crane/concrete pump

Page 45 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery 5314.00


(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 531.40
e) Contractor's profit @ 10 % on (a+b+c+d) 584.54
Rate per cum = (a+b+c+d+e) 6429.94
say 6430.00
16.99.36 E Grade M25 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5637.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 563.70
e) Contractor's profit @ 10 % on (a+b+c+d) 620.07
Rate per cum = (a+b+c+d+e) 6820.77
say 6821.00
16.99.37 D Using Batching Plant, Transit Mixer and
(ii) Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 5534.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 553.40
e) Contractor's profit @ 10 % on (a+b+c+d) 608.74
Rate per cum = (a+b+c+d+e) 6696.14
say 6696.00
16.99.38 D Grade M30 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5682.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 568.20
e) Contractor's profit @ 10 % on (a+b+c+d) 625.02
Rate per cum = (a+b+c+d+e) 6875.22
say 6875.00
12.11 D (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 5582.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 558.20
e) Contractor's profit @ 10 % on (a+b+c+d) 614.02
Rate per cum = (a+b+c+d+e) 6754.22
say 6754.00
12.11 Top plug
Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Using Concrete Mixer

Page 46 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery 4585.00


(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 458.50
e) Contractor's profit @ 10 % on (a+b+c+d) 504.35
Rate per cum = (a+b+c+d+e) 5547.85
say 5548.00
'12.11 E Grade M20 PCC
Same as Item 12.8(b) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5088.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 508.80
e) Contractor's profit @ 10 % on (a+b+c+d) 559.68
Rate per cum = (a+b+c+d+e) 6156.48
say 6156.00
'12.11 E Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5508.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 550.80
e) Contractor's profit @ 10 % on (a+b+c+d) 605.88
Rate per cum = (a+b+c+d+e) 6664.68
say 6665.00
12.11 E (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 5518.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 551.80
e) Contractor's profit @ 10 % on (a+b+c+d) 606.98
Rate per cum = (a+b+c+d+e) 6676.78
say 6677.00
'12.11 E Grade M30 PCC
Same as Item 12.8(f) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5554.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 555.40
e) Contractor's profit @ 10 % on (a+b+c+d) 610.94
Rate per cum = (a+b+c+d+e) 6720.34
say 6720.00
12.11 E (iv) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 5473.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 547.30

Page 47 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

e) Contractor's profit @ 10 % on (a+b+c+d) 602.03


Rate per cum = (a+b+c+d+e) 6622.33
say 6622.00
12.11 Well cap
RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7600.00 38912.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Form Work @ 4 per cent of a+b+c 3468.76
d) Overhead charges @ 10 % on (a+b+c) 9018.78
e) Contractor's profit @ 10 % on (a+b+c+d) 9920.65
cost of 15 cum = a+b+c+d+e 109127.18
Rate per cum = (a+b+c+d+e)/15 7275.15
say 7275.00
12.11 F (i) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7600.00 310992.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader (capacity 1 cum) hour 6.00 882.00 5292.00

Page 48 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Formwork @ 4 per cent of (a+b+c) 27274.77
d) Overhead charges @ 10 % on (a+b+c) 70914.41
e) Contractor's profit @ 10 % on (a+b+c+d) 78005.85
cost of 120 cum = a+b+c+d+e 858064.35
Rate per cum = (a+b+c+d+e)/120 7150.54
say 7151.00
12.11 F RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7600.00 45980.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Form Work @ 3.75 per cent of a+b+c 3517.01
d) Overhead charges @ 10 % on (a+b+c) 9730.40
e) Contractor's profit @ 10 % on (a+b+c+d) 10703.44
cost of 15 cum = a+b+c+d+e 117737.85
Rate per cum = (a+b+c+d+e)/15 7849.19
say 7849.00
12.11 F (ii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 7600.00 367840.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.84 356.65 299.59

Page 49 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Mason day 3.00 458.55 1375.65


Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader (capacity 1 cum) hour 6.00 882.00 5292.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Formwork @ 3.75 per cent of ( a+b+c) 27701.90
d) Overhead charges @ 10 % on (a+b+c) 76641.92
e) Contractor's profit @ 10 % on (a+b+c+d) 84306.11
cost of 120 cum = a+b+c+d+e 927367.25
Rate per cum = (a+b+c+d+e)/120 7728.06
say 7728.00
12.11 F RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7600.00 46360.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Formwork @ 3.5 per cent of (a+b+c) 3295.84
d) Overhead charges @ 10 % on (a+b+c) 9746.28
e) Contractor's profit @ 10 % on (a+b+c+d) 10720.91
cost of 15 cum = a+b+c+d+e 117930.03
Rate per cum = (a+b+c+d+e)/15 7862.00
say 7862.00
12.11 F (iii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material

Page 50 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Cement tonne 48.79 7600.00 370804.00


Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader (capacity 1 cum) hour 6.00 882.00 5292.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Formwork @ 3.5 per cent of (a+b+c) 25958.85
d) Overhead charges @ 10 % on (a+b+c) 76764.02
e) Contractor's profit @ 10 % on (a+b+c+d) 84440.42
cost of 120 cum = a+b+c+d+e 928844.60
Rate per cum = (a+b+c+d+e)/120 7740.37
say 7740.00
12.11 F RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7600.00 48108.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Formwork @ 3 per cent of (a+b+c) 2877.45
d) Overhead charges @ 10 % on (a+b+c) 9879.24
e) Contractor's profit @ 10 % on (a+b+c+d) 10867.17
cost of 15 cum = a+b+c+d+e 119538.86

Page 51 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate per cum = (a+b+c+d+e)/15 7969.26


say 7969.00
12.11 F (iv) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7600.00 384864.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader (capacity 1 cum) hour 6.00 882.00 5292.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Formwork @ 3 per cent of (a+b+c) 22672.24
d) Overhead charges @ 10 % on (a+b+c) 77841.36
e) Contractor's profit @ 10 % on (a+b+c+d) 85625.49
cost of 120 cum = a+b+c+d+e 941880.40
Rate per cum = (a+b+c+d+e)/120 7849.00
say 7849.00
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
'12.11 F RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 7600.00 396720.00
Coarse Sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
b) Labour

Page 52 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Mate day 0.84 356.65 299.59


Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Formwork @ 3 per cent on cost of concrete i.e. cost 23027.92
of material, labour and machinery
d) Overhead charges @ 10 % on (a+b+c) 79062.52
e) Contractor's profit @ 10 % on (a+b+c+d) 86968.78
cost of 120 cum = a+b+c+d+e 956656.53
Rate per cum = (a+b+c+d+e)/120 7972.14
say 7972.00
12.11 Plain/Reinforced cement concrete, in well foundation
complete as per drawing and technical specification
including providing plasticiser ( Masterplast PL-1/SPL-2 or
equivalent ), air entraining and water reducing plasticiser
( Masterplast PAE or equivalent) and accelerating
plasticiser ( Masterplast ACPL or equivalent) conforming to
IS-9103-1999.and steel shuttering formwork.

Unit = 1 cum
Taking output = 1 cum
Well curb
RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5764.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1152.80
e) Overhead charges @ 10 % on (a+b+c+d) 691.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 760.85
Rate perm (a+b+c+d+e+f) 8369.33
say 8369.00
12.11 A (i) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5685.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1137.00
e) Overhead charges @ 10 % on (a+b+c+d) 682.20

Page 53 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

f) Contractor's profit @ 10 % on (a+b+c+d+e) 750.42


Rate perm (a+b+c+d+e+f) 8254.62
say 8255.00
12.11 A RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6313.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1262.60
e) Overhead charges @ 10 % on (a+b+c+d) 757.56
f) Contractor's profit @ 10 % on (a+b+c+d+e) 833.32
Rate perm (a+b+c+d+e+f) 9166.48
say 9166.00
12.11 A (ii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6234.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1246.80
e) Overhead charges @ 10 % on (a+b+c+d) 748.08
f) Contractor's profit @ 10 % on (a+b+c+d+e) 822.89
Rate perm (a+b+c+d+e+f) 9051.77
say 9052.00
12.11 A RCC M30 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6344.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1268.80
e) Overhead charges @ 10 % on (a+b+c+d) 761.28
f) Contractor's profit @ 10 % on (a+b+c+d+e) 837.41
Rate perm (a+b+c+d+e+f) 9211.49
say 9211.00
12.11 A (ii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6266.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1253.20
e) Overhead charges @ 10 % on (a+b+c+d) 751.92
f) Contractor's profit @ 10 % on (a+b+c+d+e) 827.11
Rate perm (a+b+c+d+e+f) 9098.23
say 9098.00
12.11 A RCC M35 Grade

Page 54 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Same as for 12.8 (H) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.0 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6485.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1297.00
e) Overhead charges @ 10 % on (a+b+c+d) 778.20
f) Contractor's profit @ 10 % on (a+b+c+d+e) 856.02
Rate perm (a+b+c+d+e+f) 9416.22
say 9416.00
12.11 A (iii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6407.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1281.40
e) Overhead charges @ 10 % on (a+b+c+d) 768.84
f) Contractor's profit @ 10 % on (a+b+c+d+e) 845.72
Rate perm (a+b+c+d+e+f) 9302.96
say 9303.00
If curb concrete is carried out within steel liner, cost of
formwork shall be excluded.

12.11 Well steining


PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5111.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 511.10
e) Overhead charges @ 10 % on (a+b+c+d) 562.21
f) Contractor's profit @ 10 % on (a+b+c+d+e) 618.43
Rate perm (a+b+c+d+e+f) 6802.74
say 6803.00
12.11 B PCC M20 Grade
Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5614.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 561.40
e) Overhead charges @ 10 % on (a+b+c+d) 617.54
f) Contractor's profit @ 10 % on (a+b+c+d+e) 679.29
Rate perm (a+b+c+d+e+f) 7472.23

Page 55 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

say 7472.00
12.11 B RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5764.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 576.40
e) Overhead charges @ 10 % on (a+b+c+d) 634.04
f) Contractor's profit @ 10 % on (a+b+c+d+e) 697.44
Rate perm (a+b+c+d+e+f) 7671.88
say 7672.00
12.11 B (iii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5685.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 568.50
e) Overhead charges @ 10 % on (a+b+c+d) 625.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 687.89
Rate perm (a+b+c+d+e+f) 7566.74
say 7567.00
12.11 B PCC M25 Grade
Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6152.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 615.20
e) Overhead charges @ 10 % on (a+b+c+d) 676.72
f) Contractor's profit @ 10 % on (a+b+c+d+e) 744.39
Rate perm (a+b+c+d+e+f) 8188.31
say 8188.00
12.11 B (iv) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6076.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 607.60
e) Overhead charges @ 10 % on (a+b+c+d) 668.36
f) Contractor's profit @ 10 % on (a+b+c+d+e) 735.20
Rate perm (a+b+c+d+e+f) 8087.16
say 8087.00
'12.11 B RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Page 56 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6313.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 631.30
e) Overhead charges @ 10 % on (a+b+c+d) 694.43
f) Contractor's profit @ 10 % on (a+b+c+d+e) 763.87
Rate perm (a+b+c+d+e+f) 8402.60
say 8403.00
12.11 B (v) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6234.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 623.40
e) Overhead charges @ 10 % on (a+b+c+d) 685.74
f) Contractor's profit @ 10 % on (a+b+c+d+e) 754.31
Rate perm (a+b+c+d+e+f) 8297.45
say 8297.00
'12.11 B PCC M30 Grade
Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6207.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 620.70
e) Overhead charges @ 10 % on (a+b+c+d) 682.77
f) Contractor's profit @ 10 % on (a+b+c+d+e) 751.05
Rate perm (a+b+c+d+e+f) 8261.52
say 8262.00
12.11 B (vi) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6126.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 612.60
e) Overhead charges @ 10 % on (a+b+c+d) 673.86
f) Contractor's profit @ 10 % on (a+b+c+d+e) 741.25
Rate perm (a+b+c+d+e+f) 8153.71
say 8154.00
'12.11 B RCC M30 Grade
Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6344.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 634.40
e) Overhead charges @ 10 % on (a+b+c+d) 697.84

Page 57 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

f) Contractor's profit @ 10 % on (a+b+c+d+e) 767.62


Rate perm (a+b+c+d+e+f) 8443.86
say 8444.00
12.11 B (vii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6266.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 626.60
e) Overhead charges @ 10 % on (a+b+c+d) 689.26
f) Contractor's profit @ 10 % on (a+b+c+d+e) 758.19
Rate perm (a+b+c+d+e+f) 8340.05
say 8340.00
'12.11 B RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6485.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 648.50
e) Overhead charges @ 10 % on (a+b+c+d) 713.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 784.69
Rate perm (a+b+c+d+e+f) 8631.54
say 8632.00
12.11 B With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery 6407.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 640.70
e) Overhead charges @ 10 % on (a+b+c+d) 704.77
f) Contractor's profit @ 10 % on (a+b+c+d+e) 775.25
Rate perm (a+b+c+d+e+f) 8527.72
say 8528.00
'12.11 B RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7600.00 392160.00
Coarse Sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent) Lit 258.00 59.00 15222.00

Page 58 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Air entraining and water reducing plasticiser Lit 154.80 59.00 9133.20
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 722.40 94.00 67905.60
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59
Meson day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Per Cum Basic Cost of Labour, Material & Machinery 57020.00
(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. 85529.81
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 94082.79
f) Contractor's profit @ 10 % on (a+b+c+d+e) 103491.07
cost of 120 cum = a+b+c+d+e+f 1138401.79
Rate per cum = (a+b+c+d+e+f)/120 9486.68
say 9487.00
12.11 C Bottom Plug
Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 7600.00 42180.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
Admixture ( Masterplast Pl-1 or equivalent ) Lit 22.20 128.00 2841.60
Air entraining and water reducing plasticiser Lit 16.65 59.00 982.35
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 77.70 94.00 7303.80
( Masterplast APCL or equivalent )

Page 59 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6675.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4761.09
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 10488.48


e) Contractor's profit @ 10 % on (a+b+c+d) 11537.33
cost of 15 cum = a+b+c+d+e 126910.60
Rate per cum = (a+b+c+d+e)/15 8460.71
say 8461.00
12.11 C (i) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 7600.00 337440.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast Pl-1 or equivalent ) Lit 177.60 128.00 22732.80
Air entraining and water reducing plasticiser Lit 133.20 59.00 7858.80
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 621.60 94.00 58430.40
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer

Page 60 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Concrete Pump hour 6.00 234.00 1404.00


Per Cum Basic Cost of Labour, Material & Machinery 6645.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 37198.58
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 83455.22


e) Contractor's profit @ 10 % on (a+b+c+d) 91800.74
cost of 120 cum = a+b+c+d+e 1009808.11
Rate per cum = (a+b+c+d+e)/120 8415.07
say 8415.00
'12.11 C PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7600.00 45524.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
Admixture ( Masterplast SPl-2 or equivalent) Lit 29.95 59.00 1767.05
Air entraining and water reducing plasticiser Lit 17.97 59.00 1060.23
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 94.00 7882.84
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6871.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4907.40
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 10795.75


e) Contractor's profit @ 10 % on (a+b+c+d) 11875.32
cost of 15 cum = a+b+c+d+e 130628.56
Rate per cum = (a+b+c+d+e)/15 8708.57

Page 61 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

say 8709.00
12.11 C (ii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 7600.00 363888.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent) Lit 239.40 59.00 14124.60
Air entraining and water reducing plasticiser Lit 143.64 59.00 8474.76
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 670.32 94.00 63010.08
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6837.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 38350.35
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 85873.94


e) Contractor's profit @ 10 % on (a+b+c+d) 94461.33
cost of 120 cum = a+b+c+d+e 1039074.64
Rate per cum = (a+b+c+d+e)/120 8658.96
say 8659.00
'12.11 C PCC Grade M30
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7600.00 46208.00
Coarse sand cum 6.75 1251.00 8444.25

Page 62 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

40 mm Aggregate cum 5.40 1761.00 9509.40


20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.40 59.00 1793.60
Air entraining and water reducing plasticiser Lit 18.24 59.00 1076.16
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.12 94.00 8001.28
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6927.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4949.65
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 10884.47


e) Contractor's profit @ 10 % on (a+b+c+d) 11972.91
cost of 15 cum = a+b+c+d+e 131702.03
Rate per cum = (a+b+c+d+e)/15 8780.14
say 8780.00
12.11 C (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 7600.00 369664.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent) Lit 243.20 59.00 14348.80
Air entraining and water reducing plasticiser Lit 145.92 59.00 8609.28
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 680.96 94.00 64010.24
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65

Page 63 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Mazdoor day 18.00 244.56 4402.08


c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 6897.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 38707.10
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 86623.10


e) Contractor's profit @ 10 % on (a+b+c+d) 95285.41
cost of 120 cum = a+b+c+d+e 1048139.51
Rate per cum = (a+b+c+d+e)/120 8734.50
say 8734.00
'12.11 C PCC Grade M35
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 7600.00 47804.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm Aggregate cum 5.40 1761.00 9509.40
20 mm Aggregate cum 5.40 2088.00 11275.20
10 mm Aggregate cum 2.70 2513.00 6785.10
Admixture ( Masterplast SPl-2 or equivalent) Lit 31.45 59.00 1855.55
Air entraining and water reducing plasticiser Lit 18.87 59.00 1113.33
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.06 94.00 8277.64
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00
pipe

Page 64 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery 7058.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost 5048.22
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 11091.47


e) Contractor's profit @ 10 % on (a+b+c+d) 12200.62
cost of 15 cum = a+b+c+d+e 134206.79
Rate per cum = (a+b+c+d+e)/15 8947.12
say 8947.00
12.11 C (iv) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 7600.00 382128.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent) Lit 251.40 59.00 14832.60
Air entraining and water reducing plasticiser Lit 150.84 59.00 8899.56
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 703.92 94.00 66168.48
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00
lead in Kilometer
Concrete Pump hour 6.00 234.00 1404.00
Per Cum Basic Cost of Labour, Material & Machinery 7025.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 39476.91
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 88239.71


e) Contractor's profit @ 10 % on (a+b+c+d) 97063.68
cost of 120 cum = a+b+c+d+e 1067700.53

Page 65 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate per cum = (a+b+c+d+e)/120 8897.50


say 8898.00
12.11 Intermediate plug
Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6005.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 600.50
e) Contractor's profit @ 10 % on (a+b+c+d) 660.55
Rate per cum = (a+b+c+d+e) 7266.05
say 7266.00
12.11 D (i) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 5905.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 590.50
e) Contractor's profit @ 10 % on (a+b+c+d) 649.55
Rate per cum = (a+b+c+d+e) 7145.05
say 7145.00
'12.11 D Grade M25 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6280.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 628.00
e) Contractor's profit @ 10 % on (a+b+c+d) 690.80
Rate per cum = (a+b+c+d+e) 7598.80
say 7599.00
12.11 D (ii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6177.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 617.70
e) Contractor's profit @ 10 % on (a+b+c+d) 679.47
Rate per cum = (a+b+c+d+e) 7474.17
say 7474.00
'12.11 D Grade M30 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6335.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 633.50
e) Contractor's profit @ 10 % on (a+b+c+d) 696.85

Page 66 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate per cum = (a+b+c+d+e) 7665.35


say 7665.00
12.11 D (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6253.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 625.30
e) Contractor's profit @ 10 % on (a+b+c+d) 687.83
Rate per cum = (a+b+c+d+e) 7566.13
say 7566.00
12.11 Top plug
Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5111.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 511.10
e) Contractor's profit @ 10 % on (a+b+c+d) 562.21
Rate per cum = (a+b+c+d+e) 6184.31
say 6184.00
'12.11 E Grade M20 PCC
Same as Item 12.8(b) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5614.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 561.40
e) Contractor's profit @ 10 % on (a+b+c+d) 617.54
Rate per cum = (a+b+c+d+e) 6792.94
say 6793.00
'12.11 E Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6152.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 615.20
e) Contractor's profit @ 10 % on (a+b+c+d) 676.72
Rate per cum = (a+b+c+d+e) 7443.92
say 7444.00
12.11 E (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6076.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 607.60
e) Contractor's profit @ 10 % on (a+b+c+d) 668.36
Rate per cum = (a+b+c+d+e) 7351.96
say 7352.00

Page 67 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


'12.11 E Grade M30 PCC
Same as Item 12.8(f) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6207.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 620.70
e) Contractor's profit @ 10 % on (a+b+c+d) 682.77
Rate per cum = (a+b+c+d+e) 7510.47
say 7510.00
12.11 E (iv) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6126.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 612.60
e) Contractor's profit @ 10 % on (a+b+c+d) 673.86
Rate per cum = (a+b+c+d+e) 7412.46
say 7412.00
12.11 Well cap
RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7600.00 38912.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.48 128.00 2621.44
Air entraining and water reducing plasticiser Lit 15.36 59.00 906.24
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 71.68 94.00 6737.92
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Form Work @ 4 per cent of a+b+c 3879.38
d) Overhead charges @ 10 % on (a+b+c) 10086.40
e) Contractor's profit @ 10 % on (a+b+c+d) 11095.04
cost of 15 cum = a+b+c+d+e 122045.41
Rate per cum = (a+b+c+d+e)/15 8136.36

Page 68 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

say 8136.00
12.11 F (i) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7600.00 310992.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast Pl-1 or equivalent ) Lit 163.68 128.00 20951.04
Air entraining and water reducing plasticiser Lit 122.76 59.00 7242.84
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 572.88 94.00 53850.72
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader (capacity 1 cum) hour 6.00 882.00 5292.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Formwork @ 4 per cent of (a+b+c) 30556.56
d) Overhead charges @ 10 % on (a+b+c) 79447.05
e) Contractor's profit @ 10 % on (a+b+c+d) 87391.75
cost of 120 cum = a+b+c+d+e 961309.27
Rate per cum = (a+b+c+d+e)/120 8010.91
say 8011.00
12.11 F RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7600.00 45980.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.25 59.00 1784.75

Page 69 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Air entraining and water reducing plasticiser Lit 18.15 59.00 1070.85
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 94.00 7961.80
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Form Work @ 3.75 per cent of a+b+c 3922.66
d) Overhead charges @ 10 % on (a+b+c) 10852.71
e) Contractor's profit @ 10 % on (a+b+c+d) 11937.98
cost of 15 cum = a+b+c+d+e 131317.74
Rate per cum = (a+b+c+d+e)/15 8754.52
say 8755.00
12.11 F (ii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 7600.00 367840.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent ) Lit 242.00 59.00 14278.00
Air entraining and water reducing plasticiser Lit 145.20 59.00 8566.80
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 677.60 94.00 63694.40
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader (capacity 1 cum) hour 6.00 882.00 5292.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00

Page 70 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Formwork @ 3.75 per cent of ( a+b+c) 30947.12


d) Overhead charges @ 10 % on (a+b+c) 85620.36
e) Contractor's profit @ 10 % on (a+b+c+d) 94182.40
cost of 120 cum = a+b+c+d+e 1036006.40
Rate per cum = (a+b+c+d+e)/120 8633.39
say 8633.00
12.11 F RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7600.00 46360.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.50 59.00 1799.50
Air entraining and water reducing plasticiser Lit 18.30 59.00 1079.70
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 94.00 8027.60
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
Formwork @ 3.5 per cent of (a+b+c) 3677.58
d) Overhead charges @ 10 % on (a+b+c) 10875.14
e) Contractor's profit @ 10 % on (a+b+c+d) 11962.65
cost of 15 cum = a+b+c+d+e 131589.17
Rate per cum = (a+b+c+d+e)/15 8772.61
say 8773.00
16.11 F (iii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 7600.00 370804.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent ) Lit 243.95 59.00 14393.05

Page 71 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Air entraining and water reducing plasticiser Lit 146.37 59.00 8635.83
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 683.06 94.00 64207.64
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader (capacity 1 cum) hour 6.00 882.00 5292.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Formwork @ 3.5 per cent of (a+b+c) 29012.12
d) Overhead charges @ 10 % on (a+b+c) 85793.00
e) Contractor's profit @ 10 % on (a+b+c+d) 94372.30
cost of 120 cum = a+b+c+d+e 1038095.25
Rate per cum = (a+b+c+d+e)/120 8650.79
say 8651.00
16.11 F RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7600.00 48108.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent ) Lit 31.65 59.00 1867.35
Air entraining and water reducing plasticiser Lit 18.99 59.00 1120.41
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 94.00 8330.28
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 458.55 687.83
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00

Page 72 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Generator 33 KVA hour 6.00 311.00 1866.00


Formwork @ 3 per cent of (a+b+c) 3216.99
d) Overhead charges @ 10 % on (a+b+c) 11045.00
e) Contractor's profit @ 10 % on (a+b+c+d) 12149.50
cost of 15 cum = a+b+c+d+e 133644.53
Rate per cum = (a+b+c+d+e)/15 8909.64
say 8910.00
16.11 F (iv) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7600.00 384864.00
Coarse sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent ) Lit 253.20 59.00 14938.80
Air entraining and water reducing plasticiser Lit 151.92 59.00 8963.28
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 708.96 94.00 66642.24
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader (capacity 1 cum) hour 6.00 882.00 5292.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Formwork @ 3 per cent of (a+b+c) 25388.57
d) Overhead charges @ 10 % on (a+b+c) 87167.42
e) Contractor's profit @ 10 % on (a+b+c+d) 95884.16
cost of 120 cum = a+b+c+d+e 1054725.79
Rate per cum = (a+b+c+d+e)/120 8789.38
say 8789.00
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.

Page 73 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


16.11 F RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 7600.00 396720.00
Coarse Sand cum 54.00 1251.00 67554.00
20 mm Aggregate cum 64.80 2088.00 135302.40
10 mm Aggregate cum 43.20 2513.00 108561.60
Admixture ( Masterplast SPl-2 or equivalent ) Lit 261.00 59.00 15399.00
Air entraining and water reducing plasticiser Lit 156.60 59.00 9239.40
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 730.80 94.00 68695.20
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59
Mason day 3.00 458.55 1375.65
Mazdoor day 18.00 244.56 4402.08
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00
Generator 100 KVA hour 6.00 621.00 3726.00
Loader 1 cum capacity hour 6.00 882.00 5292.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 7.00 21000.00

Concrete Pump hour 6.00 234.00 1404.00


Formwork @ 3 per cent on cost of concrete i.e. cost 25827.93
of material, labour and machinery
d) Overhead charges @ 10 % on (a+b+c) 88675.88
e) Contractor's profit @ 10 % on (a+b+c+d) 97543.47
cost of 120 cum = a+b+c+d+e 1072978.20
Rate per cum = (a+b+c+d+e)/120 8941.49
say 8941.00
16.12 Sinking of 6 m external diameter well (other than
pneumatic method of sinking) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckon
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.

Page 74 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

a) Labour
Mate day 0.12 356.65 42.80
Sinker ( skilled ) day 1.00 356.65 356.65
Sinking helper ( semi-skilled ) day 2.00 285.32 570.64
b) Machinery
Hire & running charges of crane with grab bucket of hour 2.00 1304.00 2608.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 260.80
c) Overhead charges @ 10 % on (a+b) 383.89
d) Contractor's profit @ 10 % on (a+b+c) 422.28
Rate per metre = (a+b+c+d) 4645.05
say 4645.00
16.12 A Beyond 3m upto 10m depth
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 356.65 53.50
Sinker day 1.25 356.65 445.81
Sinking helper ( semi-skilled ) day 2.50 285.32 713.30
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1304.00 3912.00
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b) 391.20
c) Overhead charges @ 10 % on (a+b) 551.58
d) Contractor's profit @ 10 % on (a+b+c) 606.74
Rate per metre = (a+b+c+d) 6674.13
say 6674.00
16.12 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 7008.00
12th m 5% 7358.00
13th m 5% 7726.00
14th m 5% 8112.00
15th m 5% 8518.00
16th m 5% 8944.00
17th m 5% 9391.00
18th m 5% 9861.00
19th m 5% 10354.00
20th m 5% 10872.00
Total Cost from 10m upto 20m 88144.00 7504.00
Avg Rate per metre 8814.00 17.46
16.12 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 75 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 11687.00 14024.00


22nd m 7.5% 12564.00 15077.00
23rd m 7.5% 13506.00 16207.00
24th m 7.5% 14519.00 17423.00
25th m 7.5% 15608.00 18730.00
26th m 7.5% 16779.00 20135.00
27th m 7.5% 18037.00 21644.00
28th m 7.5% 19390.00 23268.00
29th m 7.5% 20844.00 25013.00
30th m 7.5% 22407.00 26888.00
Total Cost from 20m upto 30m 165341.00 198409.00 14076.00
Avg Rate per metre 16534.00 19841.00 17.46
16.12 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

31st m 10% 24648.00 29578.00


32nd 10% 27113.00 32536.00
33rd m 10% 29824.00 35789.00
34th m 10% 32806.00 39367.00
35th m 10% 36087.00 43304.00
36th m 10% 39696.00 47635.00
37th m 10% 43666.00 52399.00
38th m 10% 48033.00 57640.00
39th m 10% 52836.00 63403.00
40th m 10% 58120.00 69744.00
Total Cost from 30m upto 40m 392829.00 471395.00 33442.00
Avg Rate per metre 39283.00 47140.00 17.47
16.12 Clayey Soil ( 6m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 356.65 53.50
Sinker ( skilled ) day 1.50 356.65 534.98
Sinking helper ( semi-skilled ) day 2.25 285.32 641.97
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1304.00 3912.00
0.75 cum capacity and accessories

Page 76 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Consumables in sinking @ 10 per cent of (b) 391.20


c) Overhead charges @ 10 % on (a+b) 553.36
d) Contractor's profit @ 10 % on (a+b+c) 608.70
Rate per metre = (a+b+c+d) 6695.71
say 6696.00
16.12 B Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 356.65 107.00
Sinker day 3.00 356.65 1069.95
Sinking helper ( semi-skilled ) day 4.50 285.32 1283.94
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 2.00 284.00 568.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 839.20
c) Overhead charges @ 10 % on (a+b) 1169.21
d) Contractor's profit @ 10 % on (a+b+c) 1286.13
Rate per metre = (a+b+c+d) 14147.42
say 14147.00
16.12 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 14854.00 15597.00


12th m 5% 15597.00 16377.00
13th m 5% 16377.00 17196.00
14th m 5% 17196.00 18056.00
15th m 5% 18056.00 18959.00
16th m 5% 18959.00 19907.00
17th m 5% 19907.00 20902.00
18th m 5% 20902.00 21947.00
19th m 5% 21947.00 23044.00
20th m 5% 23044.00 24196.00
Total Cost from 10m upto 20m 186839.00 196181.00 16030.00
Avg Rate per metre 18684.00 19618.00 16.56
16.12 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering of the cost, if required

Page 77 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
21st m 7.5% 24772.00 30965.00 32513.00
22nd m 7.5% 26630.00 33288.00 34952.00
23rd m 7.5% 28627.00 35784.00 37573.00
24th m 7.5% 30774.00 38468.00 40391.00
25th m 7.5% 33082.00 41353.00 43421.00
26th m 7.5% 35563.00 44454.00 46677.00
27th m 7.5% 38230.00 47788.00 50177.00
28th m 7.5% 41097.00 51371.00 53940.00
29th m 7.5% 44179.00 55224.00 57985.00
30th m 7.5% 47492.00 59365.00 62333.00
Total Cost from 20m upto 30m 350446.00 438060.00 459962.00
Avg Rate per metre 35045.00 43806.00 45996.00
30201.00 37751.00 39639.00
16.0% 16.0% 16.0%
16.12 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 52241.00 62689.00 65823.00
32nd 10% 57465.00 68958.00 72406.00
33rd m 10% 63212.00 75854.00 79647.00
34th m 10% 69533.00 83440.00 87612.00
35th m 10% 76486.00 91783.00 96372.00
36th m 10% 84135.00 100962.00 106010.00
37th m 10% 92549.00 111059.00 116612.00
38th m 10% 101804.00 122165.00 128273.00
39th m 10% 111984.00 134381.00 141100.00
40th m 10% 123182.00 147818.00 155209.00
Total Cost from 30m upto 40m 832591.00 999109.00 1049064.00
Avg Rate per metre 83259.00 99911.00 104906.00
71752.00 86103.00 90408.00
16.0% 16.0% 16.0%
16.12 Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.

Page 78 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

a) Labour
Mate day 0.92 356.65 328.12
Sinker ( skilled ) day 3.00 356.65 1069.95
Sinking helper ( semi-skilled ) day 20.00 285.32 5706.40
Diver day 0.50 356.65 178.33
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1304.00 5216.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.50 284.00 994.00
Consumables in sinking @ 10 per cent of (b) 621.00
Add for dewatering @ of 5 per cent of (a+b), if 705.69
required
c) Overhead charges @ 10 % on (a+b) 1481.95
d) Contractor's profit @ 10 % on (a+b+c) 1630.14
Rate per metre = (a+b+c+d) 17931.57
say 17932.00
16.12 Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 120.00 480.00
Electric Detonators each 18.00 3.92 70.56
b) Labour
Mate day 1.56 356.65 556.37
Driller day 2.00 356.65 713.30
Blaster day 0.25 356.65 89.16
Mazdoor day 12.00 244.56 2934.72
Mazdoor (Skilled) day 4.00 356.65 1426.60
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 2.00 284.00 568.00
pneumatic breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if 705.61
required.
Consumables in sinking @ 10 per cent of cost of 839.20
d) (b).
Overhead charges @ 10 % on (a+b+c) 1620.75
e) Contractor's profit @ 10 % on (a+b+c+d) 1782.83
Rate per metre = (a+b+c+d+e) 19611.10
say 19611.00

Page 79 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


16.13 Sinking of 7 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is reck

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 7 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.15 356.65 53.50
Sinker ( skilled ) day 1.25 356.65 445.81
Sinking helper ( semi-skilled ) day 2.50 285.32 713.30
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.25 1304.00 4238.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 423.80
c) Overhead charges @ 10 % on (a+b) 587.44
d) Contractor's profit @ 10 % on (a+b+c) 587.44
Rate per metre = (a+b+c+d) 7049.29
say 7049.00
16.13 A Beyond 3m upto 10m depth
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 356.65 64.20
Sinker day 1.50 356.65 534.98
Sinking helper ( semi-skilled ) day 3.00 285.32 855.96
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1304.00 5868.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 586.80
c) Overhead charges @ 10 % on (a+b) 790.99
d) Contractor's profit @ 10 % on (a+b+c) 870.09
Rate per metre = (a+b+c+d) 9571.02
say 9571.00
16.13 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 10050.00
12th m 5% 10553.00
13th m 5% 11081.00
14th m 5% 11635.00
15th m 5% 12217.00

Page 80 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

16th m 5% 12828.00
17th m 5% 13469.00
18th m 5% 14142.00
19th m 5% 14849.00
20th m 5% 15591.00
Total Cost from 10m upto 20m 126415.00 11049.00
Avg Rate per metre 12642.00 14.20
16.13 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour). for Kentledge

21st m 7.5% 16760.00 20112.00


22nd m 7.5% 18017.00 21620.00
23rd m 7.5% 19368.00 23242.00
24th m 7.5% 20821.00 24985.00
25th m 7.5% 22383.00 26860.00
26th m 7.5% 24062.00 28874.00
27th m 7.5% 25867.00 31040.00
28th m 7.5% 27807.00 33368.00
29th m 7.5% 29893.00 35872.00
30th m 7.5% 32135.00 38562.00
Total Cost from 20m upto 30m 237113.00 284535.00 20726.00
Avg Rate per metre 23711.00 28454.00 14.40
16.13 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 35349.00 42419.00


32nd 10% 38884.00 46661.00
33rd m 10% 42772.00 51326.00
34th m 10% 47049.00 56459.00
35th m 10% 51754.00 62105.00
36th m 10% 56929.00 68315.00
37th m 10% 62622.00 75146.00
38th m 10% 68884.00 82661.00
39th m 10% 75772.00 90926.00
40th m 10% 83349.00 100019.00
Total Cost from 30m upto 40m 563364.00 676037.00 49243.00
Avg Rate per metre 56336.00 67604.00 14.40
16.13 Clayey Soil ( 7m dia. Well )
Unit = Running Meter.

Page 81 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Taking output = 1 cum


Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 356.65 64.20
Sinker ( skilled ) day 1.50 356.65 534.98
Sinking helper ( semi-skilled ) day 3.00 285.32 855.96
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1304.00 5868.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 586.80
d) Overhead charges @ 10 % on (a+b) 790.99
e) Contractor's profit @ 10 % on (a+b+c) 870.09
Rate per metre = (a+b+c+d) 9571.02
say 9571.00
16.13 B Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 356.65 92.73
Sinker day 2.00 356.65 713.30
Sinking helper ( semi-skilled ) day 4.00 285.32 1141.28
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.25 284.00 923.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 874.70
c) Overhead charges @ 10 % on (a+b) 1156.90
d) Contractor's profit @ 10 % on (a+b+c) 1272.59
Rate per metre = (a+b+c+d) 13998.50
say 13999.00
16.13 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 14698.00 15433.00


12th m 5% 15433.00 16205.00
13th m 5% 16205.00 17015.00
14th m 5% 17015.00 17866.00
15th m 5% 17866.00 18759.00
16th m 5% 18759.00 19697.00

Page 82 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

17th m 5% 19697.00 20682.00


18th m 5% 20682.00 21716.00
19th m 5% 21716.00 22802.00
20th m 5% 22802.00 23942.00
Total Cost from 10m upto 20m 184873.00 194117.00 16101.00
Avg Rate per metre 18487.00 19412.00 14.82
16.13 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 24512.00 30640.00 32172.00
32nd 7.5% 26350.00 32938.00 34585.00
33rd m 7.5% 28326.00 35408.00 37178.00
34th m 7.5% 30450.00 38063.00 39966.00
35th m 7.5% 32734.00 40918.00 42964.00
36th m 7.5% 35189.00 43986.00 46185.00
37th m 7.5% 37828.00 47285.00 49649.00
38th m 7.5% 40665.00 50831.00 53373.00
39th m 7.5% 43715.00 54644.00 57376.00
40th m 7.5% 46994.00 58743.00 61680.00
Total Cost from 30m upto 40m 346763.00 433456.00 455128.00
Avg Rate per metre 34676.00 43346.00 45513.00
30203.00 37754.00 39641.00
14.81 14.81 14.81
16.13 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 51693.00 62032.00 65134.00
32nd 10% 56862.00 68234.00 71646.00
33rd m 10% 62548.00 75058.00 78811.00
34th m 10% 68803.00 82564.00 86692.00
35th m 10% 75683.00 90820.00 95361.00
36th m 10% 83251.00 99901.00 104896.00
37th m 10% 91576.00 109891.00 115386.00
38th m 10% 100734.00 120881.00 126925.00
39th m 10% 110807.00 132968.00 139616.00

Page 83 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

40th m 10% 121888.00 146266.00 153579.00


Total Cost from 30m upto 40m 823845.00 988615.00 1038046.00
Avg Rate per metre 82385.00 98862.00 103805.00
71757.00 86108.00 90414.00
14.81 14.81 14.81
16.13 Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 356.65 206.86
Sinker ( skilled ) day 4.00 356.65 1426.60
Sinking helper ( semi-skilled ) day 10.00 285.32 2853.20
Diver day 0.75 356.65 267.49
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1304.00 5868.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 284.00 1065.00
Consumables in sinking @ 10 per cent of (b) 693.30
Add for dewatering @ of 5 per cent of (a+b), if 584.36
required
c) Overhead charges @ 10 % on (a+b) 1296.48
d) Contractor's profit @ 10 % on (a+b+c) 1426.13
Rate per metre = (a+b+c+d) 15687.41
say 15687.00
16.13 Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 7.00 120.00 840.00
Electric Detonators each 30.00 3.92 117.60
b) Labour
Mate day 1.60 356.65 570.64
Driller day 2.00 356.65 713.30
Blaster day 0.25 356.65 89.16
Mazdoor day 18.00 244.56 4402.08
Mazdoor (Skilled) day 4.00 356.65 1426.60
Diver day 0.50 356.65 178.33
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.

Page 84 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Hire & running charges of compressor with hour 2.00 284.00 568.00
pneumatic breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if 788.61
required.
Consumables in sinking @ 10 per cent of cost of 918.06
d) (b).
Overhead charges @ 10 % on (a+b+c) 1843.64
e) Contractor's profit @ 10 % on (a+b+c+d) 2028.00
Rate per metre = (a+b+c+d+e) 22308.01
say 22308.00
16.14 Sinking of 8 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is reck

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 8 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.18 356.65 64.20
Sinker ( skilled ) day 1.50 356.65 534.98
Sinking helper ( semi-skilled ) day 3.00 285.32 855.96
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1304.00 5216.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 521.60
c) Overhead charges @ 10 % on (a+b) 719.27
d) Contractor's profit @ 10 % on (a+b+c) 791.20
Rate per metre = (a+b+c+d) 8703.21
say 8703.00
16.14 A Beyond 3m upto 10m depth
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.25 356.65 89.16
Sinker day 1.75 356.65 624.14
Sinking helper ( semi-skilled ) day 3.50 285.32 998.62
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1304.00 6520.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 652.00
c) Overhead charges @ 10 % on (a+b) 888.39
d) Contractor's profit @ 10 % on (a+b+c) 977.23
Rate per metre = (a+b+c+d) 10749.54

Page 85 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

say 10750.00
16.14 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 11287.00
12th m 5% 11851.00
13th m 5% 12444.00
14th m 5% 13066.00
15th m 5% 13719.00
16th m 5% 14405.00
17th m 5% 15125.00
18th m 5% 15881.00
19th m 5% 16675.00
20th m 5% 17509.00
Total Cost from 10m upto 20m 141962.00 12331.00
Avg Rate per metre 14196.00 15.12%
16.14 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 18822.00 22586.00


22nd m 7.5% 20234.00 24281.00
23rd m 7.5% 21752.00 26102.00
24th m 7.5% 23383.00 28060.00
25th m 7.5% 25137.00 30164.00
26th m 7.5% 27022.00 32426.00
27th m 7.5% 29049.00 34859.00
28th m 7.5% 31228.00 37474.00
29th m 7.5% 33570.00 40284.00
30th m 7.5% 36088.00 43306.00
Total Cost from 20m upto 30m 266285.00 319542.00 23130.00
Avg Rate per metre 26629.00 31954.00 15.13
16.14 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 39697.00 47636.00


32nd 10% 43667.00 52400.00
33rd m 10% 48034.00 57641.00
34th m 10% 52837.00 63404.00
35th m 10% 58121.00 69745.00

Page 86 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

36th m 10% 63933.00 76720.00


37th m 10% 70326.00 84391.00
38th m 10% 77359.00 92831.00
39th m 10% 85095.00 102114.00
40th m 10% 93605.00 112326.00
Total Cost from 30m upto 40m 632674.00 759208.00 54952.00
Avg Rate per metre 63267.00 75921.00 15.13

16.14 Clayey Soil ( 8m dia. Well )


Unit = Running Meter.
Taking output = 1 meter
Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 356.65 78.46
Sinker ( skilled ) day 2.00 356.65 713.30
Sinking helper ( semi-skilled ) hour 3.50 285.32 998.62
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1304.00 7172.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 717.20
c) Overhead charges @ 10 % on (a+b) 967.96
d) Contractor's profit @ 10 % on (a+b+c) 1064.75
Rate per metre = (a+b+c+d) 11712.30
say 11712.00
16.14 B Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 356.65 114.13
Sinker day 2.50 356.65 891.63
Sinking helper ( semi-skilled ) day 4.50 285.32 1283.94
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.50 284.00 994.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 881.80
c) Overhead charges @ 10 % on (a+b) 1198.95
d) Contractor's profit @ 10 % on (a+b+c) 1318.84
Rate per metre = (a+b+c+d) 14507.29
say 14507.00
16.14 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 87 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Add for dewatering @ 5 per cent of cost, if required. Including for


dewatering @
5% of cost, if
required

11th m 5% 15233.00 15995.00


12th m 5% 15995.00 16795.00
13th m 5% 16795.00 17635.00
14th m 5% 17635.00 18517.00
15th m 5% 18517.00 19443.00
16th m 5% 19443.00 20415.00
17th m 5% 20415.00 21436.00
18th m 5% 21436.00 22508.00
19th m 5% 22508.00 23633.00
20th m 5% 23633.00 24815.00
Total Cost from 10m upto 20m 191610.00 201192.00 16833.00
Avg Rate per metre 19161.00 20119.00 13.83
16.14 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 25405.00 31756.00 33344.00
32nd 7.5% 27310.00 34138.00 35845.00
33rd m 7.5% 29358.00 36698.00 38533.00
34th m 7.5% 31560.00 39450.00 41423.00
35th m 7.5% 33927.00 42409.00 44529.00
36th m 7.5% 36472.00 45590.00 47870.00
37th m 7.5% 39207.00 49009.00 51459.00
38th m 7.5% 42148.00 52685.00 55319.00
39th m 7.5% 45309.00 56636.00 59468.00
40th m 7.5% 48707.00 60884.00 63928.00
Total Cost from 30m upto 40m 359403.00 449255.00 471718.00
Avg Rate per metre 35940.00 44926.00 47172.00
31574.00 39467.00 41441.00
13.83 13.83 13.83
16.14 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Page 88 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 53578.00 64294.00 67509.00
32nd 10% 58936.00 70723.00 74259.00
33rd m 10% 64830.00 77796.00 81686.00
34th m 10% 71313.00 85576.00 89855.00
35th m 10% 78444.00 94133.00 98840.00
36th m 10% 86288.00 103546.00 108723.00
37th m 10% 94917.00 113900.00 119595.00
38th m 10% 104409.00 125291.00 131556.00
39th m 10% 114850.00 137820.00 144711.00
40th m 10% 126335.00 151602.00 159182.00
Total Cost from 30m upto 40m 853900.00 1024681.00 1075916.00
Avg Rate per metre 85390.00 102468.00 107592.00
75013.00 90015.00 94516.00
13.83% 13.83% 13.83%
16.14 Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 356.65 242.52
Sinker ( skilled ) day 4.00 356.65 1426.60
Sinking helper ( semi-skilled ) day 12.00 285.32 3423.84
Diver day 1.00 356.65 356.65
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1304.00 6520.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 284.00 1065.00
Consumables in sinking @ 10 per cent of (b) 758.50
Add for dewatering @ of 5 per cent of (a+b), if 689.66
required
c) Overhead charges @ 10 % on (a+b) 1448.28
d) Contractor's profit @ 10 % on (a+b+c) 1593.10
Rate per metre = (a+b+c+d) 17524.15
say 17524.00
16.14 Hard Rock ( 8m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour

Page 89 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

a) Material
Gelatine 80 per cent Kg 8.00 120.00 960.00
Electric Detonators each 32.00 3.92 125.44
b) Labour
Mate day 1.09 356.65 388.75
Driller day 2.00 356.65 713.30
Blaster day 0.25 356.65 89.16
Mazdoor day 20.00 244.56 4891.20
Mazdoor (Skilled) day 4.00 356.65 1426.60
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 2.00 284.00 568.00
pneumatic breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if 795.05
required.
Consumables in sinking @ 10 per cent of cost of 750.90
d) (b).
Overhead charges @ 10 % on (a+b+c) 1853.24
e) Contractor's profit @ 10 % on (a+b+c+d) 2038.56
Rate per metre = (a+b+c+d+e) 22424.21
say 22424.00
16.15 Sinking of 9 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is reck

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 9 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.19 356.65 67.76
Sinker ( skilled ) day 1.50 356.65 534.98
Sinking helper ( semi-skilled ) day 3.25 285.32 927.29
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1304.00 5216.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 521.60
c) Overhead charges @ 10 % on (a+b) 726.76
d) Contractor's profit @ 10 % on (a+b+c) 799.44
Rate per metre = (a+b+c+d) 8793.83
say 8794.00
16.15 A Beyond 3m upto 10m depth

Page 90 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate of sinking @ 0.18 m/hour


a) Labour
Mate day 0.27 356.65 96.30
Sinker day 1.75 356.65 624.14
Sinking helper ( semi-skilled ) day 4.00 285.32 1141.28
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1304.00 7172.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 717.20
c) Overhead charges @ 10 % on (a+b) 975.09
d) Contractor's profit @ 10 % on (a+b+c) 1072.60
Rate per metre = (a+b+c+d) 11798.60
say 11799.00
16.15 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12389.00
12th m 5% 13008.00
13th m 5% 13658.00
14th m 5% 14341.00
15th m 5% 15058.00
16th m 5% 15811.00
17th m 5% 16602.00
18th m 5% 17432.00
19th m 5% 18304.00
20th m 5% 19219.00
Total Cost from 10m upto 20m 155822.00 13559.00
Avg Rate per metre 15582.00 14.92%
16.15 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 20660.43 24793.00


22nd m 7.5% 22210.00 26652.00
23rd m 7.5% 23876.00 28651.00
24th m 7.5% 25667.00 30800.00
25th m 7.5% 27592.00 33110.00
26th m 7.5% 29661.00 35593.00
27th m 7.5% 31886.00 38263.00
28th m 7.5% 34277.00 41132.00
29th m 7.5% 36848.00 44218.00
30th m 7.5% 39612.00 47534.00
Total Cost from 20m upto 30m 292289.43 350746.00 25430.00

Page 91 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Avg Rate per metre 29229.00 35075.00 14.94%


16.15 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 43573.20 52288.00


32nd 10% 47931.00 57517.00
33rd m 10% 52724.00 63269.00
34th m 10% 57996.00 69595.00
35th m 10% 63796.00 76555.00
36th m 10% 70176.00 84211.00
37th m 10% 77194.00 92633.00
38th m 10% 84913.00 101896.00
39th m 10% 93404.00 112085.00
40th m 10% 102744.00 123293.00
Total Cost from 30m upto 40m 694451.20 833342.00 60417.00
Avg Rate per metre 69445.00 83334.00 14.94%
16.15 Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 356.65 85.60
Sinker ( skilled ) day 2.25 356.65 802.46
Sinking helper ( semi-skilled ) day 3.75 285.32 1069.95
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1304.00 7498.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 749.80
c) Overhead charges @ 10 % on (a+b) 1020.58
d) Contractor's profit @ 10 % on (a+b+c) 1122.64
Rate per metre = (a+b+c+d) 12349.03
say 12349.00
16.15 B Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 356.65 121.26
Sinker day 2.50 356.65 891.63
Sinking helper ( semi-skilled ) day 5.00 285.32 1426.60
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1304.00 8476.00
0.75 cum capacity and accessories.

Page 92 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Air compressor with pneumatic chisel attachment for hour 3.75 284.00 1065.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 954.10
c) Overhead charges @ 10 % on (a+b) 1293.46
d) Contractor's profit @ 10 % on (a+b+c) 1422.80
Rate per metre = (a+b+c+d) 15650.85
say 15651.00
16.15 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 16434.00 17256.00


12th m 5% 17256.00 18119.00
13th m 5% 18119.00 19025.00
14th m 5% 19025.00 19976.00
15th m 5% 19976.00 20975.00
16th m 5% 20975.00 22024.00
17th m 5% 22024.00 23125.00
18th m 5% 23125.00 24281.00
19th m 5% 24281.00 25495.00
20th m 5% 25495.00 26770.00
Total Cost from 10m upto 20m 206710.00 217046.00 18194.00
Avg Rate per metre 20671.00 21705.00 13.61%
16.15 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 27407.00 34259.00 35972.00
32nd 7.5% 29463.00 36829.00 38670.00
33rd m 7.5% 31673.00 39591.00 41571.00
34th m 7.5% 34048.00 42560.00 44688.00
35th m 7.5% 36602.00 45753.00 48041.00
36th m 7.5% 39347.00 49184.00 51643.00
37th m 7.5% 42298.00 52873.00 55517.00
38th m 7.5% 45470.00 56838.00 59680.00
39th m 7.5% 48880.00 61100.00 64155.00
40th m 7.5% 52546.00 65683.00 68967.00

Page 93 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Total Cost from 30m upto 40m 387734.00 484670.00 508904.00


Avg Rate per metre 38773.00 48467.00 50890.00
34127.00 42659.00 44792.00
13.61% 13.61% 13.61%
16.15 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 57801.00 69361.00 72829.00
32nd 10% 63581.00 76297.00 80112.00
33rd m 10% 69939.00 83927.00 88123.00
34th m 10% 76933.00 92320.00 96936.00
35th m 10% 84626.00 101551.00 106629.00
36th m 10% 93089.00 111707.00 117292.00
37th m 10% 102398.00 122878.00 129022.00
38th m 10% 112638.00 135166.00 141924.00
39th m 10% 123902.00 148682.00 156116.00
40th m 10% 136292.00 163550.00 171728.00
Total Cost from 30m upto 40m 921199.00 1105439.00 1160711.00
Avg Rate per metre 92120.00 110544.00 116071.00
81083.00 97299.00 102165.00
13.61% 13.61% 13.61%
16.15 Soft Rock ( 9m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.76 356.65 271.05
Sinker ( skilled ) day 4.00 356.65 1426.60
Sinking helper ( semi-skilled ) day 14.00 285.32 3994.48
Diver day 1.20 356.65 427.98
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1304.00 8476.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 284.00 1136.00
Consumables in sinking @ 10 per cent of (b) 961.20
Add for dewatering @ of 5 per cent of (a+b), if 834.67
required
c) Overhead charges @ 10 % on (a+b) 1752.80
d) Contractor's profit @ 10 % on (a+b+c) 1928.08

Page 94 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate per metre = (a+b+c+d) 21208.86


say 21209.00
16.15 Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 120.00 1200.00
Electric Detonators each 40.00 3.92 156.80
b) Labour
Mate day 1.17 356.65 417.28
Driller day 2.00 356.65 713.30
Blaster day 0.25 356.65 89.16
Mazdoor day 22.00 244.56 5380.32
Mazdoor (Skilled) day 4.00 356.65 1426.60
Diver day 1.00 356.65 356.65
c) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1304.00 9128.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 2.50 284.00 710.00
pneumatic breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if 911.07
required.
Consumables in sinking @ 10 per cent of cost of 838.33
d) (b).
Overhead charges @ 10 % on (a+b+c) 2132.75
e) Contractor's profit @ 10 % on (a+b+c+d) 2346.03
Rate per metre = (a+b+c+d+e) 25806.29
say 25806.00
16.16 Sinking of 10 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is rec

Unit = Running Meter


Taking output = 1 m
Diameter of well - 10 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.20 356.65 71.33
Sinker ( skilled ) day 1.50 356.65 534.98
Sinking helper ( semi-skilled ) day 3.50 285.32 998.62
b) Machinery

Page 95 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Hire & running charges of crane with grab bucket of hour 5.00 1304.00 6520.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 652.00
c) Overhead charges @ 10 % on (a+b) 877.69
d) Contractor's profit @ 10 % on (a+b+c) 965.46
Rate per metre = (a+b+c+d) 10620.08
say 10620.00
16.16 A Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.31 356.65 110.56
Sinker day 2.00 356.65 713.30
Sinking helper ( semi-skilled ) day 4.25 285.32 1212.61
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1304.00 7498.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 749.80
c) Overhead charges @ 10 % on (a+b) 1028.43
d) Contractor's profit @ 10 % on (a+b+c) 1131.27
Rate per metre = (a+b+c+d) 12443.97
say 12444.00
16.16 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 13066.00
12th m 5% 13719.00
13th m 5% 14405.00
14th m 5% 15125.00
15th m 5% 15881.00
16th m 5% 16675.00
17th m 5% 17509.00
18th m 5% 18384.00
19th m 5% 19303.00
20th m 5% 20268.00
Total Cost from 10m upto 20m 164335.00 14223.00
Avg Rate per metre 16434.00 15.55%
16.16 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 21788.00 26146.00


22nd m 7.5% 23422.00 28106.00
23rd m 7.5% 25179.00 30215.00

Page 96 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

24th m 7.5% 27067.00 32480.00


25th m 7.5% 29097.00 34916.00
26th m 7.5% 31279.00 37535.00
27th m 7.5% 33625.00 40350.00
28th m 7.5% 36147.00 43376.00
29th m 7.5% 38858.00 46630.00
30th m 7.5% 41772.00 50126.00
Total Cost from 20m upto 30m 308234.00 369880.00 26678.00
Avg Rate per metre 30823.00 36988.00 15.54%
16.16 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 45949.00 55139.00


32nd 10% 50544.00 60653.00
33rd m 10% 55598.00 66718.00
34th m 10% 61158.00 73390.00
35th m 10% 67274.00 80729.00
36th m 10% 74001.00 88801.00
37th m 10% 81401.00 97681.00
38th m 10% 89541.00 107449.00
39th m 10% 98495.00 118194.00
40th m 10% 108345.00 130014.00
Total Cost from 30m upto 40m 732306.00 878768.00 63382.00
Avg Rate per metre 73231.00 87877.00 15.54%
16.16 Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 356.65 89.16
Sinker ( skilled ) day 2.50 356.65 891.63
Sinking helper ( semi-skilled ) day 5.50 285.32 1569.26
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 782.40
c) Overhead charges @ 10 % on (a+b) 1115.64
d) Contractor's profit @ 10 % on (a+b+c) 1227.21
Rate per metre = (a+b+c+d) 13499.30
say 13499.00

Page 97 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


16.16 B Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 356.65 142.66
Sinker day 3.00 356.65 1069.95
Sinking helper ( semi-skilled ) day 5.50 285.32 1569.26
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.00 284.00 1136.00
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 896.00
c) Overhead charges @ 10 % on (a+b) 1263.79
d) Contractor's profit @ 10 % on (a+b+c) 1390.17
Rate per metre = (a+b+c+d) 15291.82
say 15292.00
16.16 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 16056.00 16859.00


12th m 5% 16859.00 17702.00
13th m 5% 17702.00 18587.00
14th m 5% 18587.00 19516.00
15th m 5% 19516.00 20492.00
16th m 5% 20492.00 21517.00
17th m 5% 21517.00 22593.00
18th m 5% 22593.00 23723.00
19th m 5% 23723.00 24909.00
20th m 5% 24909.00 26154.00
Total Cost from 10m upto 20m 201954.00 212052.00 17383.00
Avg Rate per metre 20195.00 21205.00 16.18%
16.16 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 26777.00 33471.00 35145.00
32nd 7.5% 28785.00 35981.00 37780.00

Page 98 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

33rd m 7.5% 30944.00 38680.00 40614.00


34th m 7.5% 33265.00 41581.00 43660.00
35th m 7.5% 35760.00 44700.00 46935.00
36th m 7.5% 38442.00 48053.00 50456.00
37th m 7.5% 41325.00 51656.00 54239.00
38th m 7.5% 44424.00 55530.00 58307.00
39th m 7.5% 47756.00 59695.00 62680.00
40th m 7.5% 51338.00 64173.00 67382.00
Total Cost from 30m upto 40m 378816.00 473520.00 497198.00
Avg Rate per metre 37882.00 47352.00 49720.00
Previous SOR Rate 32607.00 40759.00 42797.00
% variation 16.18% 16.18% 16.18%
16.16 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 56472.00 67766.00 71154.00
32nd 10% 62119.00 74543.00 78270.00
33rd m 10% 68331.00 81997.00 86096.85
34th m 10% 75164.00 90197.00 94706.85
35th m 10% 82680.00 99216.00 104176.80
36th m 10% 90948.00 109138.00 114594.90
37th m 10% 100043.00 120052.00 126054.60
38th m 10% 110047.00 132056.00 138658.80
39th m 10% 121052.00 145262.00 152525.10
40th m 10% 133157.00 159788.00 167777.40
Total Cost from 30m upto 40m 900013.00 1080015.00 1134015.30
Avg Rate per metre 90001.00 108002.00 113402.00
Previous SOR Rate 77474.00 97614.00 92965.00
% variation 16.17% 10.64% 21.98%
16.16 Soft Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 356.65 306.72
Sinker ( skilled ) day 4.00 356.65 1426.60
Sinking helper ( semi-skilled ) day 16.00 285.32 4565.12
Diver day 1.40 356.65 499.31

Page 99 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

b) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1304.00 9128.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 284.00 1207.00
Consumables in sinking @ 10 per cent of (b) 1033.50
Add for dewatering @ 5 per cent of cost, if required 568.43
c) Overhead charges @ 10 % on (a+b) 1873.47
d) Contractor's profit @ 10 % on (a+b+c) 2060.81
Rate per metre = (a+b+c+d) 22668.96
say 22669.00
16.16 Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 120.00 1320.00
Electric Detonators each. 44.00 3.92 172.48
b) Labour
Mate day 1.27 356.65 452.95
Driller day 2.00 356.65 713.30
Blaster day 0.25 356.65 89.16
Mazdoor day 24.00 244.56 5869.44
Mazdoor (Skilled) day 4.00 356.65 1426.60
c) Machinery
Hire & running charges of crane with grab bucket of hour 8.50 1304.00 11084.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 3.00 284.00 852.00
pneumatic breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 596.80
Consumables in sinking @ 10 per cent of cost of 2108.42
(b+c).
d) Overhead charges @ 10 % on (a+b+c) 2468.52
e) Contractor's profit @ 10 % on (a+b+c+d) 2715.37
Rate per metre = (a+b+c+d+e) 29869.03
say 29869.00
16.17 Sinking of 11 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is rec

Unit = Running Meter


Taking output = 0.50 m
Diameter of well - 11 m.
Sandy Soil

Page 100 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Depth from bed level upto 3.0 M


Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.21 356.65 74.90
Sinker ( skilled ) day 1.50 356.65 534.98
Sinking helper (semi-skilled) day 3.30 285.32 941.56
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 782.40
d) Overhead charges @ 10 % on (a+b+c) 1015.78
e) Contractor's profit @ 10 % on (a+b+c+d) 1117.36
Cost for 0.5m = a+b+c+d 12290.97
Rate per metre = (a+b+c+d)/0.50 24581.94
say 24582.00
16.17 A Beyond 3m upto 10m depth
Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.32 356.65 114.13
Sinker day 2.00 356.65 713.30
Sinking helper (semi-skilled) day 4.50 285.32 1283.94
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1304.00 5216.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 521.60
c) Overhead charges @ 10 % on (a+b+c) 784.90
d) Contractor's profit @ 10 % on (a+b+c+d) 863.39
Cost for 0.5m = a+b+c+d 9497.25
Rate per metre = (a+b+c+d)/0.50 18994.50
say 18995.00
16.17 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 19944.00
12th m 5% 20941.00
13th m 5% 21988.00
14th m 5% 23087.00
15th m 5% 24241.00
16th m 5% 25453.00
17th m 5% 26726.00
18th m 5% 28062.00
19th m 5% 29465.00
20th m 5% 30938.00
Total Cost from 10m upto 20m 250845.00 20583.00

Page 101 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Avg Rate per metre 25085.00 21.87%


16.17 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 33258.00 39910.00


22nd m 7.5% 35752.00 42902.00
23rd m 7.5% 38433.00 46120.00
24th m 7.5% 41315.00 49578.00
25th m 7.5% 44414.00 53297.00
26th m 7.5% 47745.00 57294.00
27th m 7.5% 51326.00 61591.00
28th m 7.5% 55175.00 66210.00
29th m 7.5% 59313.00 71176.00
30th m 7.5% 63761.00 76513.00
Total Cost from 20m upto 30m 470492.00 564591.00 38608.00
Avg Rate per metre 47049.00 56459.00 21.86%
16.17 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 70137.00 84164.00


32nd 10% 77151.00 92581.00
33rd m 10% 84866.00 101839.00
34th m 10% 93353.00 112024.00
35th m 10% 102688.00 123226.00
36th m 10% 112957.00 135548.00
37th m 10% 124253.00 149104.00
38th m 10% 136678.00 164014.00
39th m 10% 150346.00 180415.00
40th m 10% 165381.00 198457.00
Total Cost from 30m upto 40m 1117810.00 1341372.00 91725.00
Avg Rate per metre 111781.00 134137.00 21.87%
16.17 Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate day 0.26 356.65 92.73
Sinker ( skilled ) day 2.50 356.65 891.63

Page 102 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Sinking helper (semi-skilled) day 4.00 285.32 1141.28


b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1304.00 6520.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 652.00
c) Overhead charges @ 10 % on (a+b) 929.76
d) Contractor's profit @ 10 % on (a+b+c) 1022.74
Cost for 0.5m = a+b+c+d 11250.14
Rate per metre = (a+b+c+d)/0.50 22500.27
say 22500.00
16.17 B Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 356.65 153.36
Sinker day 3.50 356.65 1248.28
Sinking helper (semi-skilled) day 5.75 285.32 1640.59
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.25 284.00 1207.00
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 903.10
c) Overhead charges @ 10 % on (a+b) 1297.63
d) Contractor's profit @ 10 % on (a+b+c) 1427.40
Cost for 0.5m = a+b+c+d 15701.35
Rate per metre = (a+b+c+d)/0.50 31402.71
say 31403.00
16.17 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 32973.00 34622.00


12th m 5% 34622.00 36353.00
13th m 5% 36353.00 38171.00
14th m 5% 38171.00 40080.00
15th m 5% 40080.00 42084.00
16th m 5% 42084.00 44188.00
17th m 5% 44188.00 46397.00
18th m 5% 46397.00 48717.00
19th m 5% 48717.00 51153.00
20th m 5% 51153.00 53711.00

Page 103 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Total Cost from 10m upto 20m 414738.00 435475.00 35315.00


Avg Rate per metre 41474.00 43548.00 17.44%
16.17 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 54989.00 68736.00 72173.00
32nd 7.5% 59113.00 73891.00 77586.00
33rd m 7.5% 63546.00 79433.00 83405.00
34th m 7.5% 68312.00 85390.00 89660.00
35th m 7.5% 73435.00 91794.00 96384.00
36th m 7.5% 78943.00 98679.00 103613.00
37th m 7.5% 84864.00 106080.00 111384.00
38th m 7.5% 91229.00 114036.00 119738.00
39th m 7.5% 98071.00 122589.00 128718.00
40th m 7.5% 105426.00 131783.00 138372.00
Total Cost from 30m upto 40m 777928.00 972411.00 1021032.00
Avg Rate per metre 77793.00 97241.00 102103.00
Previous SOR Rate 66242.00 82802.00 86942.00
% variation 17.44% 17.44% 17.44%
16.17 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 115969.00 139163.00 146121.00
32nd 10% 127566.00 153079.00 160733.00
33rd m 10% 140323.00 168388.00 176807.00
34th m 10% 154355.00 185226.00 194487.00
35th m 10% 169791.00 203749.00 213936.00
36th m 10% 186770.00 224124.00 235330.00
37th m 10% 205447.00 246536.00 258863.00
38th m 10% 225992.00 271190.00 284750.00
39th m 10% 248591.00 298309.00 313224.00
40th m 10% 273450.00 328140.00 344547.00
Total Cost from 30m upto 40m 1848254 2217904 2328798
Avg Rate per metre 184825.00 221790.00 232880.00
Previous SOR Rate 157381.00 188857.00 198300.00

Page 104 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

% variation 17.44% 17.44% 17.44%


16.17 Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 356.65 338.82
Sinker ( skilled ) day 4.25 356.65 1515.76
Sinking helper (semi-skilled) day 18.00 285.32 5135.76
Diver day 1.50 356.65 534.98
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.00 1304.00 10432.00
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 284.00 1278.00
Consumables in sinking @ 10 per cent of (b) 1171.00
Add for dewatering @ 5 per cent of cost, if required 644.05
c) Overhead charges @ 10 % on (a+b) 2105.04
d) Contractor's profit @ 10 % on (a+b+c) 2315.54
Cost for 0.5m = a+b+c+d 25470.94
Rate per metre = (a+b+c+d)/0.50 50941.88
say 50942.00
16.17 Hard Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 120.00 1440.00
Electric Detonators each. 48.00 3.92 188.16
b) Labour
Mate day 1.35 356.65 481.48
Driller day 2.00 356.65 713.30
Blaster day 0.25 356.65 89.16
Mazdoor day 26.00 244.56 6358.56
Mazdoor (Skilled) day 4.00 356.65 1426.60
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1304.00 13040.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 3.50 284.00 994.00
pneumatic breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 701.70
Consumables in sinking @ 10 per cent of cost of 2310.31
(b+c).

Page 105 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

d) Overhead charges @ 10 % on (a+b+c) 2774.33


e) Contractor's profit @ 10 % on (a+b+c+d) 3051.76
Cost for 0.5m = a+b+c+d 33569.36
Rate per metre = (a+b+c+d)/0.50 67138.71
say 67139.00
16.18 Sinking of 12 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is rec

Unit = Running Meter


Taking output = 0.25 m
Diameter of well - 12 m.
Sandy Soil
I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.22 356.65 78.46
Sinker ( skilled ) day 1.75 356.65 624.14
Sinking helper (semi-skilled) day 4.00 285.32 1141.28
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 782.40
c) Overhead charges @ 10 % on (a+b) 1045.03
d) Contractor's profit @ 10 % on (a+b+c) 1149.53
Cost for 0.25m = a+b+c+d 12644.84
Rate per metre = (a+b+c+d)/0.25 50579.36
say 50579.00
16.18 A Beyond 3m upto 10m depth
Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.37 356.65 131.96
Sinker day 2.50 356.65 891.63
Sinking helper (semi-skilled) day 4.75 285.32 1355.27
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1304.00 8476.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 847.60
c) Overhead charges @ 10 % on (a+b) 1170.25
d) Contractor's profit @ 10 % on (a+b+c) 1287.27
Cost for 0.25m = a+b+c+d 14159.97
Rate per metre = (a+b+c+d)/0.25 56639.88
say 56640.00

Page 106 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


16.18 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 59472.00
12th m 5% 62446.00
13th m 5% 65568.30
14th m 5% 68846.72
15th m 5% 72289.05
16th m 5% 75903.50
17th m 5% 79698.68
18th m 5% 83683.61
19th m 5% 87867.79
20th m 5% 92261.18
Total Cost from 10m upto 20m 748036.84 64463.00
Avg Rate per metre 74804.00 16.04%
16.18 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 99181.00 119017.00


22nd m 7.5% 106620.00 127944.00
23rd m 7.5% 114617.00 137540.00
24th m 7.5% 123213.00 147856.00
25th m 7.5% 132454.00 158945.00
26th m 7.5% 142388.00 170866.00
27th m 7.5% 153067.00 183680.00
28th m 7.5% 164547.00 197456.00
29th m 7.5% 176888.00 212266.00
30th m 7.5% 190155.00 228186.00
Total Cost from 20m upto 30m 1403130.00 1683756.00 120917.00
Avg Rate per metre 140313.00 168376.00 16.04%
16.18 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 209171.00 251005.00


32nd 10% 230088.00 276106.00
33rd m 10% 253097.00 303716.00
34th m 10% 278407.00 334088.00
35th m 10% 306248.00 367498.00
36th m 10% 336873.00 404248.00

Page 107 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

37th m 10% 370560.00 444672.00


38th m 10% 407616.00 489139.00
39th m 10% 448378.00 538054.00
40th m 10% 493216.00 591859.00
Total Cost from 30m upto 40m 3333654 4000385 287281.00
Avg Rate per metre 333365.00 400039.00 16.04%
16.18 Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate day 0.30 356.65 107.00
Sinker ( skilled ) day 3.00 356.65 1069.95
Sinking helper (semi-skilled) day 4.50 285.32 1283.94
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1304.00 8150.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 815.00
c) Overhead charges @ 10 % on (a+b) 1142.59
d) Contractor's profit @ 10 % on (a+b+c) 1256.85
Cost for 0.25m = a+b+c+d 13825.32
Rate per metre = (a+b+c+d)/0.25 55301.28
say 55301.00
16.18 B Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 356.65 171.19
Sinker day 3.75 356.65 1337.44
Sinking helper (semi-skilled) day 6.00 285.32 1711.92
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1304.00 10862.32
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 284.00 1278.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1214.03
c) Overhead charges @ 10 % on (a+b) 1657.49
d) Contractor's profit @ 10 % on (a+b+c) 1823.24
Cost for 0.25m = a+b+c+d 20055.63
Rate per metre = (a+b+c+d)/0.25 80222.52
say 80223.00
16.18 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 108 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Add for dewatering @ 5 per cent of cost, if required. Including for


dewatering @
5% of cost, if
required

11th m 5% 84234.00 88446.00


12th m 5% 88446.00 92868.00
13th m 5% 92868.00 97511.00
14th m 5% 97511.00 102387.00
15th m 5% 102387.00 107506.00
16th m 5% 107506.00 112881.00
17th m 5% 112881.00 118525.00
18th m 5% 118525.00 124451.00
19th m 5% 124451.00 130674.00
20th m 5% 130674.00 137208.00
Total Cost from 10m upto 20m 1059483.00 1112457.00 92747.00
Avg Rate per metre 105948.00 111246.00 14.23%
16.18 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 140475.00 175594.00 184374.00
32nd 7.5% 151011.00 188764.00 198202.00
33rd m 7.5% 162337.00 202921.00 213067.00
34th m 7.5% 174512.00 218140.00 229047.00
35th m 7.5% 187600.00 234500.00 246225.00
36th m 7.5% 201670.00 252088.00 264692.00
37th m 7.5% 216795.00 270994.00 284544.00
38th m 7.5% 233055.00 291319.00 305885.00
39th m 7.5% 250534.00 313168.00 328826.00
40th m 7.5% 269324.00 336655.00 353488.00
Total Cost from 30m upto 40m 1987313 2484143 2608350
Avg Rate per metre 198731.00 248414.00 260835.00
Previous SOR Rate 173969.00 217462.00 228335.00
% variation 14.23% 14.23% 14.23%
16.18 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Page 109 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 296256.00 355507.00 373282.00
32nd 10% 325882.00 391058.00 410611.00
33rd m 10% 358470.00 430164.00 451672.00
34th m 10% 394317.00 473180.00 496839.00
35th m 10% 433749.00 520499.00 546524.00
36th m 10% 477124.00 572549.00 601176.00
37th m 10% 524836.00 629803.00 661293.00
38th m 10% 577320.00 692784.00 727423.00
39th m 10% 635052.00 762062.00 800165.00
40th m 10% 698557.00 838268.00 880181.00
Total Cost from 30m upto 40m 4721563 5665874 5949166
Avg Rate per metre 472156.00 566587.00 594917.00
Previous SOR Rate 413328.00 495994.00 520794.00
% variation 14.23% 14.23% 14.23%
16.18 Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate day 1.06 356.65 378.05
Sinker ( skilled ) day 4.50 356.65 1604.93
Sinking helper (semi-skilled) day 20.00 285.32 5706.40
Diver day 1.75 356.65 624.14
b) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1304.00 13040.00
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.75 284.00 1349.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1438.90
Add for dewatering @ 5 per cent, if required 791.40
c) Overhead charges @ 10 % on (a+b) 2493.28
d) Contractor's profit @ 10 % on (a+b+c) 2742.61
Cost for 0.25m = a+b+c+d 30168.70
Rate per metre = (a+b+c+d)/0.25 120674.78
say 120675.00
16.18 Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in hard rock strata upto 3 m

Page 110 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate of sinking @ 0.020 m/hour


a) Material
Gelatine80 per cent Kg 14.00 120.00 1680.00
Electric detonator each. 56.00 3.92 219.52
b) Labour
Mate day 1.44 356.65 513.58
Driller day 2.00 356.65 713.30
Blaster day 0.25 356.65 89.16
Mazdoor day 28.00 244.56 6847.68
Mazdoor (Skilled) day 4.50 356.65 1604.93
c) Machinery
Hire & running charges of crane with grab bucket of hour 12.50 1304.00 16300.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 4.00 284.00 1136.00
pneumatic breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 871.80
Consumables in sinking @ 10 per cent of (c). 1830.78
d) Overhead charges @ 10 % on (a+b+c) 3180.67
e) Contractor's profit @ 10 % on (a+b+c+d) 3498.74
Cost for 0.25m = a+b+c+d+e 38486.16
Rate per metre = (a+b+c+d+e)/0.25 153944.64
say 153945.00
16.19 Sinking of Twin D Type well (other than pneumatic
method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from be

Unit = Running Meter


Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
Sandy Soil
Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.20 356.65 71.33
Sinker ( skilled ) day 1.25 356.65 445.81
Sinking helper (semi-skilled) day 3.75 285.32 1069.95
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1304.00 7172.00
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 717.20
c) Overhead charges @ 10 % on (a+b) 947.63

Page 111 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

d) Contractor's profit @ 10 % on (a+b+c) 1042.39


Rate per metre = (a+b+c+d) 11466.31
say 11466.00
16.19 A Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.30 356.65 107.00
Sinker day 1.50 356.65 534.98
Sinking helper (semi-skilled) day 4.00 285.32 1141.28
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.88 1304.00 7667.52
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 766.75
c) Overhead charges @ 10 % on (a+b) 1021.75
d) Contractor's profit @ 10 % on (a+b+c) 1123.93
Rate per metre = (a+b+c+d) 12363.20
say 12363.00
16.19 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12981.00
12th m 5% 13630.00
13th m 5% 14312.00
14th m 5% 15028.00
15th m 5% 15779.00
16th m 5% 16568.00
17th m 5% 17396.00
18th m 5% 18266.00
19th m 5% 19179.00
20th m 5% 20138.00
Total Cost from 10m upto 20m 163277.00 14384.00
Avg Rate per metre 16328.00 13.52%
16.19 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 21648.00 25978.00


22nd m 7.5% 23272.00 27926.00
23rd m 7.5% 25017.00 30020.00
24th m 7.5% 26893.00 32272.00
25th m 7.5% 28910.00 34692.00
26th m 7.5% 31078.00 37294.00
27th m 7.5% 33409.00 40091.00

Page 112 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

28th m 7.5% 35915.00 43098.00


29th m 7.5% 38609.00 46331.00
30th m 7.5% 41505.00 49806.00
Total Cost from 20m upto 30m 306256.00 367508.00 26981.00
Avg Rate per metre 30626.00 36751.00 13.51%
16.19 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 45656.00 54787.00


32nd 10% 50222.00 60266.00
33rd m 10% 55244.00 66293.00
34th m 10% 60768.00 72922.00
35th m 10% 66845.00 80214.00
36th m 10% 73530.00 88236.00
37th m 10% 80883.00 97060.00
38th m 10% 88971.00 106765.00
39th m 10% 97868.00 117442.00
40th m 10% 107655.00 129186.00
Total Cost from 30m upto 40m 727642.00 873171.00 64105.00
Avg Rate per metre 72764.00 87317.00 13.51%
16.19 Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 356.65 92.73
Sinker ( skilled ) day 2.50 356.65 891.63
Sinking helper (semi-skilled) day 4.00 285.32 1141.28
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1304.00 8150.00
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 815.00
c) Overhead charges @ 10 % on (a+b) 1109.06
d) Contractor's profit @ 10 % on (a+b+c) 1219.97
Rate per metre = (a+b+c+d) 13419.67
say 13420.00
16.19 B Beyond 3m upto 10m depth
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 356.65 160.49

Page 113 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Sinker day 3.25 356.65 1159.11


Sinking helper (semi-skilled) day 6.00 285.32 1711.92
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.67 1304.00 8697.68
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 284.00 1278.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 997.57
c) Overhead charges @ 10 % on (a+b) 1400.48
d) Contractor's profit @ 10 % on (a+b+c) 1540.53
Rate per metre = (a+b+c+d) 16945.78
say 16946.00
16.19 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 17793.00 18683.00


12th m 5% 18683.00 19617.00
13th m 5% 19617.00 20598.00
14th m 5% 20598.00 21628.00
15th m 5% 21628.00 22709.00
16th m 5% 22709.00 23844.00
17th m 5% 23844.00 25036.00
18th m 5% 25036.00 26288.00
19th m 5% 26288.00 27602.00
20th m 5% 27602.00 28982.00
Total Cost from 10m upto 20m 223798.00 234987.00 19320.00
Avg Rate per metre 22380.00 23499.00 15.84%
16.19 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 29672.00 37090.00 38945.00
32nd 7.5% 31897.00 39871.00 41865.00
33rd m 7.5% 34289.00 42861.00 45004.00
34th m 7.5% 36861.00 46076.00 48380.00
35th m 7.5% 39626.00 49533.00 52010.00
36th m 7.5% 42598.00 53248.00 55910.00

Page 114 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

37th m 7.5% 45793.00 57241.00 60103.00


38th m 7.5% 49227.00 61534.00 64611.00
39th m 7.5% 52919.00 66149.00 69456.00
40th m 7.5% 56888.00 71110.00 74666.00
Total Cost from 30m upto 40m 419770.00 524713.00 550950.00
Avg Rate per metre 41977.00 52471.00 55095.00
Previous SOR Rate 36239.00 45299.00 47563.00
% variation 15.83% 15.83% 15.84%
16.19 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 62577.00 75092.00 78847.00
32nd 10% 68835.00 82602.00 86732.00
33rd m 10% 75719.00 90863.00 95406.00
34th m 10% 83291.00 99949.00 104946.00
35th m 10% 91620.00 109944.00 115441.00
36th m 10% 100782.00 120938.00 126985.00
37th m 10% 110860.00 133032.00 139684.00
38th m 10% 121946.00 146335.00 153652.00
39th m 10% 134141.00 160969.00 169017.00
40th m 10% 147555.00 177066.00 185919.00
Total Cost from 30m upto 40m 997326.00 1196790.00 1256629.00
Avg Rate per metre 99733.00 119679.00 125663.00
Previous SOR Rate 86096.00 103315.00 108481.00
% variation 15.84% 15.84% 15.84%
16.19 Soft Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 356.65 306.72
Sinker ( skilled ) day 4.50 356.65 1604.93
Sinking helper (semi-skilled) day 15.00 285.32 4279.80
Diver day 1.50 356.65 534.98
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1304.00 10862.32
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 284.00 1704.00

Page 115 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Consumables in sinking @ 10 per cent of (b) 1256.63


Add for dewatering @ 5 per cent, if required 691.15
c) Overhead charges @ 10 % on (a+b) 2124.05
d) Contractor's profit @ 10 % on (a+b+c) 2336.46
Rate per metre = (a+b+c+d) 25701.03
say 25701.00
16.19 Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 120.00 1200.00
Electric detonators each. 40.00 3.92 156.80
b) Labour
Mate day 1.34 356.65 477.91
Driller day 2.00 356.65 713.30
Blaster day 0.25 356.65 89.16
Mazdoor day 25.00 244.56 6114.00
Mazdoor (Skilled) day 4.25 356.65 1515.76
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1304.00 13040.00
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 3.00 284.00 852.00
pneumatic breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if 1140.11
required.
Consumables in sinking @ 10 per cent of (b). 1503.21
d) Overhead charges @ 10 % on (a+b+c) 2680.23
e) Contractor's profit @ 10 % on (a+b+c+d) 2948.25
Rate per metre = (a+b+c+d+e) 32430.73
say 32431.00
16.21 Sand Filling in Wells complete as per Drawing and
Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids ) cum 1.20 1251.00 1501.20
b) Labour
Mate day 0.01 356.65 3.57
Mazdoor day 0.30 244.56 73.37
c) Overhead charges @ 10 % on (a+b) 157.81
d) Contractor's profit @ 10 % on (a+b+c) 173.59
Rate per cum (a+b+c+d) 1909.54
say 1910.00

Page 116 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs


16.22 Providing Steel Liner 10 mm thick for Curbs and 6 mm
thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.

Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 62000.00 65100.00
b) Labour
Mate day 1.24 356.65 442.25
Fitter day 6.00 356.65 2139.90
Blacksmith day 5.00 356.65 1783.25
Welder day 5.00 458.55 2292.75
Mazdoor day 10.00 244.56 2445.60
Electrodes, cutting gas and other consumables @ 5 3255.00
per cent on cost a (a) above.
c) Overhead charges @ 10 % on (a+b) 7745.87
d) Contractor's profit @ 10 % on (a+b+c) 8520.46
Rate for per MT (a+b+c+d) 93725.08
say 93725.00
16.23 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 6.62 8881.00 58792.22

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.30 882.00 264.60
Tipper 5.5 cum capacity for disposal of muck from hour 0.30 680.00 204.00
pile bore hole
Bentonite kg 300.00 11.00 3300.00
c) Labour
Mate/Supervisor day 0.14 356.65 49.93
Mazdoor day 3.50 244.56 855.96
d) Overhead charges @ 10 % on (b+c) 3282.35
e) Contractor's profit @ 10 % on (b+c+d) 3610.58
Cost for 15 m = a+b+c+d+d+e 98508.64

Page 117 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Rate per metre (a+b+c+d+e)/15 6567.24


say 6567.00
(A) With plasticiser
a) Materials
PCC Grade M35 cum 6.62 9940.00 65802.80

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.30 882.00 264.60
Tipper 5.5 cum capacity for disposal of muck from hour 0.30 680.00 204.00
pile bore hole
Bentonite kg 300.00 11.00 3300.00
c) Labour
Mate/Supervisor day 0.14 356.65 49.93
Mazdoor day 3.50 244.56 855.96
d) Overhead charges @ 10 % on (b+c) 3282.35
e) Contractor's profit @ 10 % on (b+c+d) 3610.58
Cost for 15 m = a+b+c+d+d+e 105519.22
Rate per metre (a+b+c+d+e)/15 7034.61
say 7035.00
16.24 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications cl. no. 1100,1600 & 1700and removal of
excavated earth with all lifts and lead upto 1000 m.

Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 7.85 8881.00 69715.85

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00
reinforcement cage

Page 118 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.40 882.00 352.80
Tipper 5.5 cum capacity for disposal of muck from hour 0.40 680.00 272.00
pile bore hole
Bentonite kg 350.00 11.00 3850.00
c) Labour
Mate/Supervisor day 0.16 356.65 57.06
Mazdoor day 4.00 244.56 978.24
d) Overhead charges @ 10 % on (b+c) 3365.91
e) Contractor's profit @ 10 % on (b+c+d) 3702.50
Cost for 10 m = a+b+c+d+d+e 110443.37
Rate per metre (a+b+c+d+e)/10 11044.34
say 11044.00
(B) With plasticiser
a) Materials
PCC Grade M35 cum 7.85 9940.00 78029.00

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.40 882.00 352.80
Tipper 5.5 cum capacity for disposal of muck from hour 0.40 680.00 272.00
pile bore hole
Bentonite kg 350.00 11.00 3850.00
c) Labour
Mate/Supervisor day 0.16 356.65 57.06
Mazdoor day 4.00 244.56 978.24
d) Overhead charges @ 10 % on (b+c) 3365.91
e) Contractor's profit @ 10 % on (b+c+d) 3702.50
Cost for 10 m = a+b+c+d+d+e 118756.52
Rate per metre (a+b+c+d+e)/10 11875.65
say 11876.00
16.25 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
(A) Without plasticiser
a) Materials

Page 119 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

PCC Grade M35 cum 10.17 8881.00 90319.77

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.50 882.00 441.00
Tipper 5.5 cum capacity for disposal of muck from hour 0.50 680.00 340.00
pile bore hole
Bentonite kg 385.00 11.00 4235.00
c) Labour
Mate/Supervisor day 0.18 356.65 64.20
Mazdoor day 4.50 244.56 1100.52
d) Overhead charges @ 10 % on (b+c) 3432.97
e) Contractor's profit @ 10 % on (b+c+d) 3776.27
Cost for 9 m = a+b+c+d+d+e 131858.73
Rate per metre (a+b+c+d+e)/9 14650.97
say 14651.00
(A) With plasticiser
a) Materials
PCC Grade M35 cum 10.17 9940.00 101089.80

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.50 882.00 441.00
Tipper 5.5 cum capacity for disposal of muck from hour 0.50 680.00 340.00
pile bore hole
Bentonite kg 385.00 11.00 4235.00
c) Labour
Mate/Supervisor day 0.18 356.65 64.20
Mazdoor day 4.50 244.56 1100.52
d) Overhead charges @ 10 % on (b+c) 3432.97
e) Contractor's profit @ 10 % on (b+c+d) 3776.27
Cost for 9 m = a+b+c+d+d+e 142628.76
Rate per metre (a+b+c+d+e)/9 15847.64

Page 120 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

say 15848.00
16.26 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 17.66 8881.00 156838.46

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00
iii) Steel helmet and cushion block on top of casing Kg 50.00 55.00 2750.00
head during driving
c) Machinery
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00
double acting pile driving hammer complete with
power unit and accessories..
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50
lifting capacity for lowering reinforcement and
handling steel casing.
d) Labour
Mate/Supervisor day 0.12 356.65 42.80
Mazdoor day 3.00 244.56 733.68
e) Overhead charges @ 10 % on (b+c+d) 3154.90
f) Contractor's profit @ 10 % on (b+c+d+e) 3470.39
Cost for 40 m = a+b+c+d+e 195012.72
Rate per metre (a+b+c+d+e)/40 4875.32
say 4875.00
(B) With plasticiser
a) Materials
PCC Grade M35 cum 17.66 9940.00 175540.40

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00
iii) Steel helmet and cushion block on top of casing Kg 50.00 55.00 2750.00
head during driving
c) Machinery
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00
double acting pile driving hammer complete with
power unit and accessories..
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50
lifting capacity for lowering reinforcement and
handling steel casing.

Page 121 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

d) Labour
Mate/Supervisor day 0.12 356.65 42.80
Mazdoor day 3.00 244.56 733.68
e) Overhead charges @ 10 % on (b+c+d) 3154.90
f) Contractor's profit @ 10 % on (b+c+d+e) 3470.39
Cost for 40 m = a+b+c+d+e 213714.66
Rate per metre (a+b+c+d+e)/40 5342.87
say 5343.00
1.The quantity of concrete required to be removed above
the designed top level of concrete, if any, will be provided for
in the rate analysis.
2.In case steel lining is included in the design for driven
cast-in-situ pile and is planned to be retained, the same may
be included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost
16.27 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 23.55 8881.00 209147.55

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00
iii) Steel helmet and cushion block on top of casing Kg 50.00 55.00 2750.00
head during driving
c) Machinery
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00
double acting pile driving hammer complete with
power unit and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50
lifting capacity for lowering reinforcement and
handling steel casing.
Hire and running charges for light crane for lowering hour 0.50 318.00 159.00
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 356.65 57.06
Mazdoor day 4.00 244.56 978.24
e) Overhead charges @ 10 % on (b+c+d) 3196.68
f) Contractor's profit @ 10 % on (b+c+d+e) 3516.35
Cost for 30 m = a+b+c+d+e 247827.38
Rate per metre (a+b+c+d+e)/30 8260.91
say 8261.00
(B) With plasticiser
a) Materials

Page 122 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

PCC Grade M35 cum 23.55 9940.00 234087.00

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00
iii) Steel helmet and cushion block on top of casing Kg 50.00 55.00 2750.00
head during driving
c) Machinery
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00
double acting pile driving hammer complete with
power unit and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50
lifting capacity for lowering reinforcement and
handling steel casing.
Hire and running charges for light crane for lowering hour 0.50 318.00 159.00
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 356.65 57.06
Mazdoor day 4.00 244.56 978.24
e) Overhead charges @ 10 % on (b+c+d) 3196.68
f) Contractor's profit @ 10 % on (b+c+d+e) 3516.35
Cost for 30 m = a+b+c+d+e 272766.83
Rate per metre (a+b+c+d+e)/30 9092.23
say 9092.00
1.The quantity of concrete required to be removed above
the designed top level of concrete, if any, will be provided for
in the rate analysis.
2.In case steel lining is included in the design for driven
cast-in-situ pile and is planned to be retained, the same may
be included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost
16.28 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 22.61 8881.00 200799.41

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00
iii) Steel helmet on top of casing head during driving Kg 50.00 55.00 2750.00
c) Machinery

Page 123 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00
double acting pile driving hammer complete with
power unit and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50
lifting capacity for lowering reinforcement and
handling steel casing.
d) Labour
Mate/Supervisor day 0.18 356.65 64.20
Mazdoor day 4.50 244.56 1100.52
e) Overhead charges @ 10 % on (b+c+d) 3193.72
f) Contractor's profit @ 10 % on (b+c+d+e) 3513.09
Cost for 20 m = a+b+c+d+e 239443.44
Rate per metre (a+b+c+d+e)/20 11972.17
say 11972.00
(B) With plasticiser
a) Materials
PCC Grade M35 cum 22.61 9940.00 224743.40

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00
iii) Steel helmet on top of casing head during driving Kg 50.00 55.00 2750.00
c) Machinery
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00
double acting pile driving hammer complete with
power unit and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50
lifting capacity for lowering reinforcement and
handling steel casing.
d) Labour
Mate/Supervisor day 0.18 356.65 64.20
Mazdoor day 4.50 244.56 1100.52
e) Overhead charges @ 10 % on (b+c+d) 3193.72
f) Contractor's profit @ 10 % on (b+c+d+e) 3513.09
Cost for 20 m = a+b+c+d+e 263387.43
Rate per metre (a+b+c+d+e)/20 13169.37
say 13169.00
1.The quantity of concrete required to be removed above
the designed top level of concrete, if any, will be provided for
in the rate analysis.
2.In case steel lining is included in the design for driven
cast-in-situ pile and is planned to be retained, the same may
be included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost
16.37 Pile Load Test on single Vertical Pile in accordance
with IS:2911(Part-IV)
Unit = 1 MT
Taking output = 1 MT
a) Initial and routine load test tonne 1.00 330.00 330.00

Page 124 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

b) Lateral load test tonne 1.00 5500.00 5500.00


Although, this item is incidental to work and is not required
to be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.
16.38 Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification

RCC Grade M20


Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.12 7600.00 38912.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 285.32 427.98
Mazdoor for concreting day 20.00 244.56 4891.20
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00
Formwork @ 4 per cent on cost of concrete i.e. 3468.72
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 9018.67
e) Contractor's profit @ 10 % on (a+b+c+d) 9920.54
Cost for 15 cum = a+b+c+d+e 109125.90
Rate per metre (a+b+c+d+e)/15 7275.06
say 7275.00
16.38A Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.12 7600.00 38912.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.16 356.65 57.06
Mason day 0.38 285.32 108.42
Mazdoor for concreting day 2.50 244.56 611.40
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50
Generator 100 KVA hour 0.75 621.00 465.75
Loader (capacity 1 cum) hour 0.75 882.00 661.50
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00

Page 125 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 7.00 2625.00

Concrete Pump hour 0.75 234.00 175.50


Formwork @ 4 per cent on cost of concrete i.e. 3425.48
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 8906.24
e) Contractor's profit @ 10 % on (a+b+c+d) 9796.87
Cost for 15 cum = a+b+c+d+e 107765.53
Rate per metre (a+b+c+d+e)/15 7184.37
say 7184.00
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M25
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.99 7600.00 45524.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 285.32 427.98
Mazdoor for concreting day 20.00 244.56 4891.20
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00
Formwork @ 4 per cent on cost of concrete i.e. 3733.20
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 9706.32
e) Contractor's profit @ 10 % on (a+b+c+d) 10676.95
Cost for 15 cum = a+b+c+d+e 117446.44
Rate per metre (a+b+c+d+e)/15 7829.76
say 7830.00
16.38B Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.99 7600.00 45524.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.16 356.65 57.06
Mason day 0.38 285.32 108.42
Mazdoor for concreting day 2.50 244.56 611.40
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50

Page 126 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Generator 125 KVA hour 0.75 833.00 624.75


Loader (capacity 1 cum) hour 0.75 882.00 661.50
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00

Concrete Pump hour 0.75 234.00 175.50


Formwork @ 4 per cent on cost of concrete i.e. 4641.32
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 12067.43
e) Contractor's profit @ 10 % on (a+b+c+d) 13274.17
Cost for 15 cum = a+b+c+d+e 146015.86
Rate per metre (a+b+c+d+e)/15 9734.39
say 9734.00
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M30
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.10 7600.00 46360.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 285.32 427.98
Mazdoor for concreting day 20.00 244.56 4891.20
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00
Formwork @ 4 per cent on cost of concrete i.e. 3766.64
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 9793.26
e) Contractor's profit @ 10 % on (a+b+c+d) 10772.59
Cost for 15 cum = a+b+c+d+e 118498.46
Rate per metre (a+b+c+d+e)/15 7899.90
say 7900.00
'16.38C Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.10 7600.00 46360.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.16 356.65 57.06
Mason day 0.38 285.32 108.42
Mazdoor for concreting day 2.50 244.56 611.40

Page 127 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50
Generator 100 KVA hour 0.75 621.00 465.75
Loader (capacity 1 cum) hour 0.75 882.00 661.50
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00

Concrete Pump hour 0.75 234.00 175.50


Formwork @ 4 per cent on cost of concrete i.e. 4668.40
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 12137.83
e) Contractor's profit @ 10 % on (a+b+c+d) 13351.62
Cost for 15 cum = a+b+c+d+e 146867.80
Rate per metre (a+b+c+d+e)/15 9791.19
say 9791.00
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M35
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.33 7600.00 48108.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 285.32 427.98
Mazdoor day 20.00 244.56 4891.20
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00
Formwork @ 4 per cent on cost of concrete i.e. 3836.56
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 9975.05
e) Contractor's profit @ 10 % on (a+b+c+d) 10972.56
Cost for 15 cum = a+b+c+d+e 120698.15
Rate per metre (a+b+c+d+e)/15 8046.54
say 8047.00
'16.38D Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.33 7600.00 48108.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20

Page 128 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

b) Labour
Mate day 0.16 356.65 57.06
Mason day 0.38 285.32 108.42
Mazdoor for concreting day 2.50 244.56 611.40
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50
Generator 125 KVA hour 0.75 833.00 624.75
Loader (capacity 1 cum) hour 0.75 882.00 661.50
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00

Concrete Pump hour 0.75 234.00 175.50


Formwork @ 4 per cent on cost of concrete i.e. 4744.68
cost of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 12336.16
e) Contractor's profit @ 10 % on (a+b+c+d) 13569.78
Cost for 15 cum = a+b+c+d+e 149267.56
Rate per metre (a+b+c+d+e)/15 9951.17
say 9951.00
16.38 Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification
including providing plasticiser ( Masterplast PL-1/SPl-2
0r its equivalent ), air entraining and water reducing
plasticiser ( Masterplast PAE or its equivalent ) and
accelerating plasticiser ( Masterplast APCL or its
equuivalent)

RCC Grade M20


Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.12 7600.00 38912.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.48 92.00 1884.16
Air entraining and water reducing plasticiser Lit 15.36 59.80 918.53
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 71.68 75.00 5376.00
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 285.32 427.98
Mazdoor for concreting day 20.00 244.56 4891.20
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00

Page 129 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Generator (capacity 33 KVA) hour 6.00 311.00 1866.00


Formwork @ 4 per cent on cost of concrete i.e. 3795.87
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 9869.25
e) Contractor's profit @ 10 % on (a+b+c+d) 10856.18
Cost for 15 cum = a+b+c+d+e 119417.96
Rate per metre (a+b+c+d+e)/15 7961.20
say 7961.00
16.38A Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.12 7600.00 38912.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.48 92.00 1884.16
Air entraining and water reducing plasticiser Lit 15.36 59.80 918.53
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 71.68 75.00 5376.00
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06
Mason day 0.38 285.32 108.42
Mazdoor for concreting day 2.50 244.56 611.40
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50
Generator 100 KVA hour 0.75 621.00 465.75
Loader (capacity 1 cum) hour 0.75 882.00 661.50
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00

Concrete Pump hour 0.75 234.00 175.50


Formwork @ 4 per cent on cost of concrete i.e. 4697.63
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 12213.83
e) Contractor's profit @ 10 % on (a+b+c+d) 13435.21
Cost for 15 cum = a+b+c+d+e 147787.29
Rate per metre (a+b+c+d+e)/15 9852.49
say 9852.00
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M25
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.99 7600.00 45524.00
Coarse sand cum 6.75 1251.00 8444.25

Page 130 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

20 mm Aggregate cum 8.10 2088.00 16912.80


10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent ) Lit 29.95 76.40 2288.18
Air entraining and water reducing plasticiser Lit 17.97 59.80 1074.61
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 75.00 6289.50
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 285.32 427.98
Mazdoor for concreting day 20.00 244.56 4891.20
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00
Formwork @ 4 per cent on cost of concrete i.e. 4119.29
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 10710.16
e) Contractor's profit @ 10 % on (a+b+c+d) 11781.17
Cost for 15 cum = a+b+c+d+e 129592.88
Rate per metre (a+b+c+d+e)/15 8639.53
say 8640.00
16.38B Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.99 7600.00 45524.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent ) Lit 29.95 76.40 2288.18
Air entraining and water reducing plasticiser Lit 17.97 59.80 1074.61
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 75.00 6289.50
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06
Mason day 0.38 285.32 108.42
Mazdoor for concreting day 2.50 244.56 611.40
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50
Generator 125 KVA hour 0.75 833.00 624.75
Loader (capacity 1 cum) hour 0.75 882.00 661.50
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00

Concrete Pump hour 0.75 234.00 175.50

Page 131 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Formwork @ 4 per cent on cost of concrete i.e. 5027.41


cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 13071.26
e) Contractor's profit @ 10 % on (a+b+c+d) 14378.39
Cost for 15 cum = a+b+c+d+e 158162.30
Rate per metre (a+b+c+d+e)/15 10544.15
say 10544.00
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M30
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.10 7600.00 46360.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.50 76.40 2330.20
Air entraining and water reducing plasticiser Lit 18.30 59.80 1094.34
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 75.00 6405.00
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 285.32 427.98
Mazdoor for concreting day 20.00 244.56 4891.20
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00
Formwork @ 4 per cent on cost of concrete i.e. 4159.82
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 10815.53
e) Contractor's profit @ 10 % on (a+b+c+d) 11897.09
Cost for 15 cum = a+b+c+d+e 130867.96
Rate per metre (a+b+c+d+e)/15 8724.53
say 8725.00
'16.38C Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.10 7600.00 46360.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.50 76.40 2330.20
Air entraining and water reducing plasticiser Lit 18.30 59.80 1094.34
conforming to IS-9103-1999( Masterplast PAE or
equivalent)

Page 132 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 75.00 6405.00


( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06
Mason day 0.38 285.32 108.42
Mazdoor for concreting day 2.50 244.56 611.40
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50
Generator 100 KVA hour 0.75 621.00 465.75
Loader (capacity 1 cum) hour 0.75 882.00 661.50
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00

Concrete Pump hour 0.75 234.00 175.50


Formwork @ 4 per cent on cost of concrete i.e. 5061.58
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 13160.11
e) Contractor's profit @ 10 % on (a+b+c+d) 14476.12
Cost for 15 cum = a+b+c+d+e 159237.29
Rate per metre (a+b+c+d+e)/15 10615.82
say 10616.00
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M35
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.33 7600.00 48108.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent ) Lit 31.65 76.40 2418.06
Air entraining and water reducing plasticiser Lit 18.99 59.80 1135.60
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 75.00 6646.50
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99
Mason day 1.50 285.32 427.98
Mazdoor day 20.00 244.56 4891.20
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00
Formwork @ 4 per cent on cost of concrete i.e. 4244.57
cost of a) Material, b) Labour and c)
Machinery

Page 133 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

d) Overhead charges @ 10 % on (a+b+c) 11035.87


e) Contractor's profit @ 10 % on (a+b+c+d) 12139.46
Cost for 15 cum = a+b+c+d+e 133534.03
Rate per metre (a+b+c+d+e)/15 8902.27
say 8902.00
'16.38D Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.33 7600.00 48108.00
Coarse sand cum 6.75 1251.00 8444.25
20 mm Aggregate cum 8.10 2088.00 16912.80
10 mm Aggregate cum 5.40 2513.00 13570.20
Admixture ( Masterplast SPl-2 or equivalent ) Lit 31.65 76.40 2418.06
Air entraining and water reducing plasticiser Lit 18.99 59.80 1135.60
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 75.00 6646.50
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06
Mason day 0.38 285.32 108.42
Mazdoor for concreting day 2.50 244.56 611.40
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50
Generator 125 KVA hour 0.75 833.00 624.75
Loader (capacity 1 cum) hour 0.75 882.00 661.50
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00

Concrete Pump hour 0.75 234.00 175.50


Formwork @ 4 per cent on cost of concrete i.e. 5152.68
cost of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 13396.98
e) Contractor's profit @ 10 % on (a+b+c+d) 14736.68
Cost for 15 cum = a+b+c+d+e 162103.45
Rate per metre (a+b+c+d+e)/15 10806.90
say 10807.00
16.39 Levelling Course for Pile cap

Providing and laying of PCC M15 levelling course


100mm thick below the pile cap.
Unit = cum
Taking output = 15 cum
(A) Without plasticiser
a) Material
Cement tonne 4.13 7600.00 31388.00
Coarse sand cum 6.75 1251.00 8444.25
40 mm aggregate cum 8.10 1761.00 14264.10
20 mm Aggregate cum 4.05 2088.00 8456.40
10 mm Aggregate cum 1.35 2513.00 3392.55

Page 134 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

b) Labour
Mate day 0.86 356.65 306.72
Mason day 1.50 285.32 427.98
Mazdoor day 20.00 244.56 4891.20
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00
Generator 33 KVA hour 6.00 311.00 1866.00
d) Overhead charges @ 10 % on (a+b+c) 7456.52
e) Contractor's profit @ 10 % on (a+b+c+d) 8202.17
Cost for 15 cum = a+b+c+d+e 90223.89
Rate per metre (a+b+c+d+e)/15 6014.93
say 6015.00
16.40 Supplying, Fitting and Placing un-coated TMT bar
Reinforcement in Foundation complete as per Drawing
and Technical Specifications.

Unit = 1 MT
Taking output = 1 MT
(A) Using TMT Fe500 rebar
a) Material
TMT bars including5 per cent overlaps and wastage tonne 1.05 48380.00 50799.00
Binding wire Kg 6.00 70.00 420.00
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 356.65 142.66
Blacksmith day 2.00 458.55 917.10
Mazdoor day 6.00 244.56 1467.36
5374.61
5912.07
65032.81
say 65033.00
(C) Using TMT rebar Fe-500
a) Material
TMT bars including5 per cent overlaps and tonne 1.05 40763.00 42801.15
wastage
Binding wire Kg 6.00 70.00 420.00
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 356.65 142.66
Blacksmith day 2.00 458.55 917.10
Mazdoor day 6.00 244.56 1467.36
4574.83
5032.31
55355.41
say 55355.00
(D) Using other ISI marked TMT Fe 500 rebar
a) Material
TMT bars including5 per cent overlaps and wastage tonne 1.05 34492.00 36216.60
Binding wire Kg 6.00 70.00 420.00
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 356.65 142.66
Blacksmith day 2.00 458.55 917.10
Mazdoor day 6.00 244.56 1467.36

Page 135 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Sr No Description Unit Quantity Rate Rs Cost Rs

3916.37
4308.01
47388.10
say 47388.00
16.41 Supplying, fitting and placing un-coated TMT
reinforcement complete in foundation as per drawing
and technical specification
Unit = 1 MT
Taking output = 1 MT
a) Material
TMT bars including 5 per cent overlaps and tonne 1.08 41525.00 44847.00
wastage
Binding wire Kg 6.00 70.00 420.00
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.43 356.65 153.36
Blacksmith day 2.25 458.55 1031.74
Mazdoor day 6.50 244.56 1589.64
c) Overhead charges @ 10 % on (a+b) 4804.17
d) Contractor's profit @ 10 % on (a+b+c) 5284.59
Rate for per MT (a+b+c+d) 58130.50
say 58131.00

Page 136 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

CHAPTER-16-A

FOUNDATIONS

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.66 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(I) Without dewatering
16.66 (i) Depth upto 3 m
a) Labour
Mate day 0.14 356.65 49.93 L-12
Mazdoor day 3.50 244.56 855.96 L-13
b) Overhead charges @ 10 % on (a) 90.59
c) Contractor's profit @ 10 % on (a+b) 99.65
Cost for 10 cum = a+b+c 1096.13
Rate per cum = (a+b+c)/10 109.61 47.00
say 110.00 134.04
1. Cost of dewatering may be added where required upto,
10 per cent of labour cost Assessment for dewatering shall
be made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding mars
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
16.66 A (I) Depth 3 m to 6 m
(ii)
a) Labour
Mate/Supervisor day 0.26 356.65 92.73 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
b) Overhead charges @ 10 % on (a) 119.32
c) Contractor's profit @ 10 % on (a+b) 131.26
Cost for 10 cum = a+b+c 1443.83
Rate per cum = (a+b+c)/10 144.38 61.00
say 144.00 136.07
Cost of dewatering may be added where required upto 15
per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.
16.66 A (I) Depth above 6 m
(iii)
a) Labour
Mate/Supervisor day 0.24 356.65 85.60 L-12
Mazdoor day 6.00 244.56 1467.36 L-13
b) Overhead charges @ 10 % on (a) 155.30

Page 137 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
c) Contractor's profit @ 10 % on (a+b) 170.83
Cost for 10 cum = a+b+c 1879.08
Rate per cum = (a+b+c)/10 187.91 81.00
say 188.00 132.10
(II) With dewatering
16.66 A (II) Depth upto 3 m
(i)
a) Labour
Mate day 0.14 356.65 49.93 L-12
Mazdoor day 3.50 244.56 855.96 L-13
Cost of dewatering @ 10% of labour cost 90.59
b) Overhead charges @ 10 % on (a) 99.65
c) Contractor's profit @ 10 % on (a+b) 109.61
Cost for 10 cum = a+b+c 1205.74
Rate per cum = (a+b+c)/10 120.57 52.00
say 121.00 132.69
1. Cost of dewatering may be added where required upto,
10 per cent of labour cost Assessment for dewatering shall
be made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding mars
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
16.66A (II) Depth 3 m to 6 m
(ii)
a) Labour
Mate/Supervisor day 0.18 356.65 64.20 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
Cost of dewatering @ 15% of labour cost 174.71
b) Overhead charges @ 10 % on (a) 133.94
c) Contractor's profit @ 10 % on (a+b) 147.34
Cost for 10 cum = a+b+c 1620.70
Rate per cum = (a+b+c)/10 162.07 70.00
say 162.00 131.43
Cost of dewatering may be added where required upto 15
per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.
16.66 A (II) Depth above 6 m
(iii)
a) Labour
Mate/Supervisor day 0.24 356.65 85.60 L-12
Mazdoor day 6.00 244.56 1467.36 L-13
Cost of dewatering @ 20% of labour cost 155.30
b) Overhead charges @ 10 % on (a) 170.83
c) Contractor's profit @ 10 % on (a+b) 187.91
Cost for 10 cum = a+b+c 2066.98
Rate per cum = (a+b+c)/10 206.70 97.00
say 207.00 113.40

Page 138 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.

1. Cost of dewatering may be added where required upto 20


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
B Mechanical Means
(I) Without dewatering
16.66 B (I) Depth upto 3 m
(i)
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 356.65 114.13 L-12
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00 P&M-026
c) Overhead charges @ 10 % on (a+b) 1026.06
d) Contractor's profit @ 10 % on (a+b+c) 1128.67
Cost for 240 cum = a+b+c+d 12415.34
Rate per cum = (a+b+c+d)/240 51.73 50.00
say 52.00 4.00
Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made
as per site conditions..
16.66 B (I) Depth 3 m to 6 m
(ii)
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 356.65 114.13 L-12
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00 P&M-026
c) Overhead charges @ 10 % on (a+b) 1026.06
d) Contractor's profit @ 10 % on (a+b+c) 1128.67
Cost for 210 cum = a+b+c+d 12415.34
Rate per cum = (a+b+c+d)/210 59.12 57.00
say 59.00 3.51
Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
16.66B (I) Depth above 6m
(iii)
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 356.65 142.66 L-12
Mazdoor day 10.00 244.56 2445.60 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00 P&M-026
c) Overhead charges @ 10 % on (a+b) 1077.83
d) Contractor's profit @ 10 % on (a+b+c) 1185.61

Page 139 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for 180 cum = a+b+c+d 13041.69
Rate per cum = (a+b+c+d)/180 72.45 68.00
say 72.00 5.88
1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.
(II) With dewatering
16.66 B (II) Depth upto 3 m
(i)
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 356.65 114.13 L-12
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00 P&M-026
Cost of dewatering @ 5% of (a+b) 513.03
c) Overhead charges @ 10 % on (a+b) 1077.36
d) Contractor's profit @ 10 % on (a+b+c) 1185.10
Cost for 240 cum = a+b+c+d 13036.10
Rate per cum = (a+b+c+d)/240 54.32 52.00
say 54.00 3.85
Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made
as per site conditions..
16.66 B (II) Depth 3 m to 6 m
(ii)
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 356.65 114.13 L-12
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00 P&M-026
Cost of dewatering @ 7.5% of (a+b) 769.55
c) Overhead charges @ 10 % on (a+b) 1103.02
d) Contractor's profit @ 10 % on (a+b+c) 1213.32
Cost for 210 cum = a+b+c+d 13346.49
Rate per cum = (a+b+c+d)/210 63.55 61.00
say 64.00 4.92
Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
16.66 B (II) Depth above 6m
(iii)
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 356.65 142.66 L-12

Page 140 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor day 10.00 244.56 2445.60 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00 P&M-026
Cost of dewatering @ 10% of (a+b) 1077.83
c) Overhead charges @ 10 % on (a+b) 1077.83
d) Contractor's profit @ 10 % on (a+b+c) 1293.39
Cost for 180 cum = a+b+c+d 14227.30
Rate per cum = (a+b+c+d)/180 79.04 74.00
say 79.00 6.76
1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.

16.66 II Ordinary Rock (not requiring blasting)


(I) Without dewatering
Manual Means
Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.26 356.65 92.73 L-12
Mazdoor day 5.00 244.56 1222.80 L-13
b) Overhead charges @ 10 % on (a) 131.55
c) Contractor's profit @ 10 % on (a+b) 144.71
Cost for 10 cum = a+b+c 1591.79
Rate per cum = (a+b+c)/10 159.18 67.00
say 159.00 137.31
(I) With dewatering
Manual Means
Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 356.65 71.33 L-12
Mazdoor day 5.00 244.56 1222.80 L-13
Cost of dewatering @ 10% of labour cost 129.41
b) Overhead charges @ 10 % on (a) 142.35
c) Contractor's profit @ 10 % on (a+b) 156.59
Cost for 10 cum = a+b+c 1722.49
Rate per cum = (a+b+c)/10 172.25 74.00
say 172.00 132.43
Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
16.66(II) Mechanical Means

Page 141 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
(I) Without dewatering
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 356.65 85.60 L-12
Mazdoor day 6.00 244.56 1467.36 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00 P&M-026
c) Overhead charges @ 10 % on (a+b) 974.30
d) Contractor's profit @ 10 % on (a+b+c) 1071.73
Cost for 180 cum = a+b+c+d 11788.98
Rate per cum = (a+b+c+d)/180 65.49 65.00
say 65.00 0.00
(ii) With dewatering
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 356.65 85.60 L-12
Mazdoor day 6.00 244.56 1467.36 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1365.00 8190.00 P&M-026
Cost of dewatering @ 10% of (a+b) 974.30
c) Overhead charges @ 10 % on (a+b) 974.30
d) Contractor's profit @ 10 % on (a+b+c) 1169.15
Cost for 180 cum = a+b+c+d 12860.70
Rate per cum = (a+b+c+d)/180 71.45 71.00
say 71.00 0.00

1.Cost of dewatering upto 10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
16.66 (III) Hard Rock ( requiring blasting )
Manual Means
(I) Without dewatering
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 356.65 124.83 L-12
Driller day 0.50 356.65 178.33 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for hour 1.00 354.00 354.00 P&M-001
drilling.
c) Material
Blasting Material kg 3.50 120.00 420.00 M-104
Detonator electric each 14.00 3.92 54.88 M-097/100
d) Overhead charges @ 10 % on (a+b+c) 317.77
e) Contractor's profit @ 10 % on (a+b+c+d) 349.54
Cost for 10 cum = a+b+c+d+e 3844.99

Page 142 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum = (a+b+c+d+e)/10 384.50 212.00
say 384.00 81.13
(ii) With dewatering
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 356.65 124.83 L-12
Driller day 0.50 356.65 178.33 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 8.00 244.56 1956.48 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for hour 1.00 354.00 354.00 P&M-001
drilling.
c) Material
Blasting Material kg 3.50 120.00 420.00 M-104
Detonator electric each 14.00 3.92 54.88 M-097/100
Cost of dewatering @ 10% of (a+b) 270.28
d) Overhead charges @ 10 % on (a+b+c) 317.77
e) Contractor's profit @ 10 % on (a+b+c+d) 376.57
Cost for 10 cum = a+b+c+d+e 4142.29
Rate per cum = (a+b+c+d+e)/10 414.23 225.00
say 414.00 84.00

Cost of dewatering @ 10 per cent of (a+b) may be


added, where required Assessment for dewatering shall be
made as per site conditions.
16.66 (IV) Hard Rock ( blasting prohibited )
(I) Without dewatering
Unit = cum
Taking output = 10 cum
Mechanical Means
a) Labour
Mate day 0.20 356.65 71.33 L-12
Mazdoor day 5.00 244.56 1222.80 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 354.00 2124.00 P&M-001
breaker
c) Overhead charges @ 10 % on (a+b) 341.81
d) Contractor's profit @ 10 % on (a+b+c) 375.99
Cost for 10 cum = a+b+c+d 4135.94
Rate per cum = (a+b+c+d)/10 413.59 292.00
say 414.00 41.78
(ii) With dewatering
Unit = cum
Taking output = 10 cum
Mechanical Means
a) Labour
Mate day 0.20 356.65 71.33 L-12
Mazdoor day 5.00 244.56 1222.80 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 354.00 2124.00 P&M-001
breaker

Page 143 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost of dewatering @ 10% of (a+b) 341.81
c) Overhead charges @ 10 % on (a+b) 341.81
d) Contractor's profit @ 10 % on (a+b+c) 410.18
Cost for 10 cum = a+b+c+d 4511.93
Rate per cum = (a+b+c+d)/10 451.19 317.00
say 451.00 42.27
1. Cost of dewatering upto10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
16.66-V Marshy Soil
(I) Without dewatering
Unit = cum
Taking output = 10 cum
Depth upto 3 m
Manual means
a) Labour
Mate/Supervisor day 0.40 356.65 142.66 L-12
Mazdoor day 10.00 244.56 2445.60 L-13
b) Machinery
Tractor-trolley for removal. hour 2.67 323.00 862.41 P&M-053
c) Overhead charges @ 10 % on (a+b) 345.07
d) Contractor's profit @ 10 % on (a+b+c) 379.57
Cost for 10 cum = a+b+c+d 4175.31
Rate per cum = ( a+b+c+d)/ 10 417.53 248.00
say 418.00 68.55
(ii) With dewatering
Unit = cum
Taking output = 10 cum
Depth upto 3 m
Manual means
a) Labour
Mate/Supervisor day 0.40 356.65 142.66 L-12
Mazdoor day 10.00 244.56 2445.60 L-13
b) Machinery
Tractor-trolley for removal. hour 2.67 323.00 862.41 P&M-053
Cost of dewatering @ 30% of (a) 776.48
c) Overhead charges @ 10 % on (a+b) 345.07
d) Contractor's profit @ 10 % on (a+b+c) 457.22
Cost for 10 cum = a+b+c+d 5029.44
Rate per cum = ( a+b+c+d)/ 10 502.94 282.00
say 503.00 78.37

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required
may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1 (i) to (iv) for ordinary soil

Page 144 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.66-VI Mechanical Means
(I) Without dewatering
a) Labour
Mate day 0.08 356.65 28.53 L-12
Mazdoor for dressing sides, bottom and backfilling day 2.00 244.56 489.12 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.17 1365.00 232.05 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 680.00 306.00 P&M-048
c) Overhead charges @ 10 % on (a+b) 105.57
d) Contractor's profit @ 10 % on (a+b+c) 116.13
Cost for 10 cum = a+b+c+d 1277.40
Rate per cum = (a+b+c+d)/10 127.74 83.00
say 128.00 54.22
(ii) With dewatering
a) Labour
Mate day 0.08 356.65 28.53 L-12
Mazdoor for dressing sides, bottom and backfilling day 2.00 244.56 489.12 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.17 1365.00 232.05 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 680.00 306.00 P&M-048
Cost of dewatering @ 20% of (a+b) 211.14
c) Overhead charges @ 10 % on (a+b) 105.57
d) Contractor's profit @ 10 % on (a+b+c) 137.24
Cost for 10 cum = a+b+c+d 1509.65
Rate per cum = (a+b+c+d)/10 150.97 96.00
say 151.00 57.29
1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1 (i) to (iv) for ordinary soil
Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 356.65 42.80 L-12
Mazdoor for dressing sides, bottom and backfilling day 3.00 244.56 733.68 L-13
b) Machinery
Tractor-trolley for transportation hour 2.00 323.00 646.00 P&M-053
c) Overhead charges @ 10 % on (a+b) 142.25
d) Contractor's profit @ 10 % on (a+b+c) 156.47
Cost for 6 cum = a+b+c+d 1721.20
Rate per cum = (a+b+c+d)/6 286.87 209.00
say 287.00 37.32
16.67 Filling Annular Space Around Footing in Rock Item12.4
Unit = cum
Taking out put = 1 cum

Page 145 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Lean cement concrete 1:3:6 nominal mix. Rate may be
taken as per item 12.4.
16.68 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 356.65 3.57 L-12
Mazdoor day 0.30 244.56 73.37 L-13
b) Material
Sand (assuming 20 per cent voids) cum 1.20 1251.00 1501.20 M-006
c) Overhead charges @ 10 % on (a+b) 157.81
d) Contractor's profit @ 10 % on (a+b+c) 173.59
Rate per cum = a+b+c+d 1909.54 864.00
say 1910.00 121.06
16.69 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 356.65 228.26 L-12
Mason day 1.00 458.55 458.55 L-11
Mazdoor day 15.00 244.56 3668.40 L-13
b) Material
40 mm Aggregate cum 13.50 1761.00 23773.50 M-055
coarse Sand cum 6.75 1251.00 8444.25 M-005
cement tonne 3.95 7600.00 30020.00 M-084
Cost of water KL 18.00 40.00 720.00 M-189
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Water tanker 6 KL capacity hour 2.00 440.00 880.00 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 7118.70
e) Contractor's profit @ 10 % on (a+b+c+d) 7830.57
Cost for 15 cum = a+b+c+d+e 86136.22
Rate per cum = (a+b+c+d+e)/15 5742.41 3193.00
say 5742.00 79.83
Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
16.70 Brick Masonry Work in Cement Mortar 1:3 in
Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 8.00 20000.00 M-082
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.20 1501.20 1801.44 Item 12.6 (A)
analysis)
b) Labour

Page 146 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 0.48 356.65 171.19 L-12
Mason day 4.00 458.55 1834.20 L-11
Mazdoor day 8.00 244.56 1956.48 L-13
c) Overhead charges @ 10 % on (a+b) 2576.33
d) Contractor's profit @ 10 % on (a+b+c) 2833.96
Cost for 5 cum = a+b+c+d 31173.61
Rate per cum (a+b+c+d)/5 6234.72 3339.00
say 6235.00 86.73
16.71 Cement Mortar 1:3 (1 cement : 3 sand)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 7600.00 3876.00 M-084
Sand cum 1.05 1251.00 1313.55 M-005
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.90 244.56 220.10 L-13
Total Material and Labour = (a+b) say 5424.00 3269.00
Cement Mortar1:2 (1cement :2 sand) 65.92

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.67 7600.00 5107.20 M-084
Sand cum 0.93 1251.00 1163.43 M-005
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.90 244.56 220.10 L-13
Total Material and Labour = (a+b) say 6505.00 4052.00
Cement Mortar1:4 (1cement :4 sand) 60.54
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 7600.00 3064.32 M-084
Sand cum 1.12 1251.00 1401.12 M-005
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.90 244.56 220.10 L-13
Total Material and Labour = (a+b) say 4700.00 2749.00
Cement Mortar1:6 (1cement :6 sand) 70.97
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.29 7600.00 2188.80 M-084

Page 147 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Sand cum 1.34 1251.00 1672.77 M-005
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.90 244.56 220.10 L-13
Total Material and Labour = (a+b) say 4096.00 2258.00
16.72 Stone Masonry Work in Cement Mortar 1:3 in 81.40
Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.50 560.00 3080.00 M-169
Through and bond stone each 35.00 8.00 280.00 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.50 4942.00 7413.00 Item 12.6 (A)
analysis)
b) Labour
Mate day 0.66 356.65 235.39 L-12
Mason day 7.50 458.55 3439.13 L-11
Mazdoor day 9.00 244.56 2201.04 L-13
c) Overhead charges @ 10 % on (a+b) 1664.86
d) Contractor's profit @ 10 % on (a+b+c) 1831.34
Cost for 5 cum = a+b+c+d 20144.75
Rate per cum (a+b+c+d)/5 4028.95 2608.00
say 4029.00 54.49
Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 448.00 2464.00 M-148
Through and bond stone each 35.00 8.00 280.00 M-182
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.55 4942.00 7660.10 Item 12.6 (A)
analysis)
b) Labour
Mate day 0.62 356.65 221.12 L-12
Mason day 6.00 458.55 2751.30 L-11
Mazdoor day 9.00 244.56 2201.04 L-13
c) Overhead charges @ 10 % on (a+b) 1557.76
d) Contractor's profit @ 10 % on (a+b+c) 1713.53
Cost for 5 cum = a+b+c+d 18848.85
Rate per cum (a+b+c+d)/5 3769.77 2441.00
say 3770.00 54.44
The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
16.73 Plain/Reinforced Cement Concrete in Open
Foundation complete as per Drawing and Technical
Specifications cl. no. 1200,1500 & 1700

Page 148 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 7600.00 31388.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 8.10 1761.00 14264.10 M-055
20 mm Aggregate cum 4.05 2088.00 8456.40 M-053
10 mm Aggregate cum 1.35 2513.00 3392.55 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 4989.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 2993.00
of material, labour and machinery

e) Overhead charges @ 10 % on (a+b+c+d) 7781.80


f) Contractor's profit @ 10 % on (a+b+c+d+e) 8559.99
Cost for 15 cum = a+b+c+d+e+f 94159.84
Rate per cum = (a+b+c+d+e+f)/15 6277.32 Err:509
say 6277.00 Err:509
Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
16.74 PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 7600.00 39216.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5608.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 3364.39
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 8747.41
f) Contractor's profit @ 10 % on (a+b+c+d+e) 9622.15
Cost for 15 cum = a+b+c+d+e+f 105843.64
Rate per cum = (a+b+c+d+e+f)/15 7056.24 Err:509

Page 149 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 7056.00 Err:509
16.75 RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 7600.00 39596.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5827.00
(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 3496.12
e) Overhead charges @ 10 % on (a+b+c+d) 9089.91
f) Contractor's profit @ 10 % on (a+b+c+d+e) 9998.90
Cost for 15 cum = a+b+c+d+e+f 109987.93
Rate per cum = ( a+b+c+d+e+f )/15 7332.53 Err:509
say 7333.00 Err:509
16.76 With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 7600.00 316616.00 M-084
Coarse Sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049

Page 150 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Lead beyond 1 km, L-lead in km tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 5730.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 27499.73
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 71499.30
f) Contractor's profit @ 10 % on (a+b+c+d+e) 78649.24
Cost for 120 cum = a+b+c+d+e+f 865141.59
Rate per cum = ( a+b+c+d+e+f )/120 7209.51 Err:509
say 7210.00 Err:509
16.77 PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7600.00 45524.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6028.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 3390.66
e) Overhead charges @ 10 % on (a+b+c+d) 9380.84
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10318.92
Cost for 15 cum = a+b+c+d+e+f 113508.11
Rate per cum = ( a+b+c+d+e+f )/15 7567.21 Err:509
say 7567.00 Err:509
16.78 With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 7600.00 364420.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-005
40 mm Aggregate cum 43.20 1761.00 76075.20 M-055

Page 151 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
20 mm Aggregate cum 43.20 2088.00 90201.60 M-053
10 mm Aggregate cum 21.60 2513.00 54280.80 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer (300L) Lead= 10 km
Concrete Pump hour 6 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 5934.00
(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. 26699.66
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 73869.06
f) Contractor's profit @ 10 % on (a+b+c+d+e) 81255.96
cost of 120 cum = a+b+c+d+e+f 893815.60
Rate per cum = (a+b+c+d+e+f)/120 7448.46 Err:509
say 7448.00 Err:509
16.79 RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7600.00 45980.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6253.00
(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c. 3517.01
e) Overhead charges @ 10 % on (a+b+c+d) 9730.40
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10703.44

Page 152 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
cost of 15 cum = a+b+c+d+e+f 117737.85
Rate per cum (a+b+c+d+e+f )/15 7849.19 Err:509
say 7849.00 Err:509
16.80 With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 7600.00 367688.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity 1 cum hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6155.00
(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 27696.20
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 76626.15
f) Contractor's profit @ 10 % on (a+b+c+d+e) 84288.77
cost of 120 cum = a+b+c+d+e+f 927176.43
Rate per cum (a+b+c+d+e+f )/120 7726.47 Err:509
say 7726.00 Err:509
16.81 PCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7600.00 46208.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
b) Labour

Page 153 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6074.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 3188.56
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 9429.03
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10371.93
cost of 15 cum = a+b+c+d+e+f 114091.21
Rate per cum (a+b+c+d+e+f )/15 7606.08 Err:509
say 7606.00 Err:509
16.82 Using Batching Plant, Transit Mixer and Concrete
Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 7600.00 369360.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
40 mm Aggregate cum 43.20 1761.00 76075.20 M-055
20 mm Aggregate cum 43.20 2088.00 90201.60 M-053
10 mm Aggregate cum 21.60 2513.00 54280.80 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 5975.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 25092.58
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 74202.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 81622.58
cost of 120 cum = a+b+c+d+e+f 897848.43
Rate per cum (a+b+c+d+e+f )/120 7482.07 Err:509

Page 154 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 7482.00 Err:509
16.83 RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7600.00 46360.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6278.00
(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. 3295.84
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 9746.28
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10720.91
cost of 15 cum = a+b+c+d+e+f 117930.03
Rate per cum = (a+b+c+d+e+f)/15 7862.00 Err:509
say 7862.00 Err:509
16.84 Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 7600.00 370880.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049

Page 155 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6182.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. 25961.51
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 76771.88
f) Contractor's profit @ 10 % on (a+b+c+d+e) 84449.07
cost of 120 cum = a+b+c+d+e+f 928939.77
Rate per cum (a+b+c+d+e+f )/120 7741.16 Err:509
say 7741.00 Err:509
16.85 RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7600.00 48108.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6395.00
(a+b+c)
d) Formwork @ 3 per cent on a+b+c 2877.45
e) Overhead charges @ 10 % on (a+b+c+d) 9879.24
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10867.17
cost of 15 cum = a+b+c+d+e+f 119538.86
Rate per cum = (a+b+c+d+e+f)/15 7969.26 Err:509
say 7969.00 Err:509
16.86 H Using Batching Plant, Transit Mixer and Concrete
Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 7600.00 384864.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051

Page 156 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6298.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 3% 22672.24
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 10 % 77841.36
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10 % 85625.49
cost of 120 cum = a+b+c+d+e+f 941880.40
Rate per cum = (a+b+c+d+e+f)/120 7849.00 Err:509
say 7849.00 Err:509
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
16.87 Plain/Reinforced Cement Concrete in Open
Foundation complete as per Drawing and Technical
Specifications cl. no. 1200,1500 & 1700 including
providing plasticiser ( Masterplast PL-1/SPL-2 or
equivalent ), air entraining and water reducing
plasticiser ( Masterplast PAE or equivalent) and
accelerating plasticiser ( Masterplast ACPL or
equivalent) conforming to IS-9103-1999.

PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 7600.00 31388.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 8.10 1761.00 14264.10 M-055
20 mm Aggregate cum 4.05 2088.00 8456.40 M-053
10 mm Aggregate cum 1.35 2513.00 3392.55 M-051
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit Lit 16.52 128.00 2114.56 M-208
per Tonne of cement
Air entraining and water reducing plasticiser Lit 12.39 59.00 731.01 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3Lit per Tonne of cement

Page 157 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Accelerating plasticiser conforming to IS-9103-1999 Lit 57.82 94.00 5435.08 M-211
( Masterplast APCL or equivalent ) @ 14Lit per
Tonne of cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 5541.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 3324.23
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 8642.99
f) Contractor's profit @ 10 % on (a+b+c+d+e) 9507.29
Cost for 15 cum = a+b+c+d+e+f 104580.21
Rate per cum = (a+b+c+d+e+f)/15 6972.01 4389.00
say 6972.00 58.85
Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
16.88 PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 7600.00 39216.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit Lit 20.64 128.00 2641.92 M-208
per Tonne of cement
Air entraining and water reducing plasticiser Lit 15.48 59.00 913.32 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3Lit per Tonne of cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 72.24 94.00 6790.56 M-211
( Masterplast APCL or equivalent ) @ 14Lit per
Tonne of cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6298.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 3778.22
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 9823.37
f) Contractor's profit @ 10 % on (a+b+c+d+e) 10805.71
Cost for 15 cum = a+b+c+d+e+f 118862.79

Page 158 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum = (a+b+c+d+e+f)/15 7924.19 4369.00
say 7924.00 81.37
16.89 RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 7600.00 39596.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit Lit 20.84 128.00 2667.52 M-208
per Tonne of cement
Air entraining and water reducing plasticiser Lit 15.63 59.00 922.17 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3Lit per Tonne of cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 72.94 94.00 6856.36 M-211
( Masterplast APCL or equivalent ) @ 14Lit per
Tonne of cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6524.00
(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 3913.96
e) Overhead charges @ 10 % on (a+b+c+d) 10176.30
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11193.93
Cost for 15 cum = a+b+c+d+e+f 123133.24
Rate per cum = ( a+b+c+d+e+f )/15 8208.88 5101.00
say 8209.00 60.93
16.90 C With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 7600.00 316616.00 M-084
Coarse Sand cum 54.00 1251.00 67554.00 M-005
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast Pl-1 or equivalent ) @ 4Lit Lit 166.64 128.00 21329.92 M-208
per tonne cement

Page 159 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Air entraining and water reducing plasticiser Lit 124.98 59.00 7373.82 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @3Lit per tonne cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 583.24 94.00 54824.56 M-211
( Masterplast APCL or equivalent ) @ 14Lit per
tonne cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 km, L-lead in km (300L) tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6426.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 30840.86
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 80186.25
f) Contractor's profit @ 10 % on (a+b+c+d+e) 88204.87
Cost for 120 cum = a+b+c+d+e+f 970253.60
Rate per cum = ( a+b+c+d+e+f )/120 8085.45 5704.00
say 8085.00 41.74
16.91 PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7600.00 45524.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 29.95 59.00 1767.05 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 17.97 59.00 1060.23 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 94.00 7882.84 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72 L-12

Page 160 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6742.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 3792.29
e) Overhead charges @ 10 % on (a+b+c+d) 10492.01
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11541.21
Cost for 15 cum = a+b+c+d+e+f 126953.33
Rate per cum = ( a+b+c+d+e+f )/15 8463.56 Err:509
say 8464.00 Err:509
16.92 D With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 7600.00 364420.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
40 mm Aggregate cum 43.20 1761.00 76075.20 M-055
20 mm Aggregate cum 43.20 2088.00 90201.60 M-053
10 mm Aggregate cum 21.60 2513.00 54280.80 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 239.75 59.00 14145.25 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 143.85 59.00 8487.15 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 671.30 94.00 63102.20 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer (300L) Lead= 10 km
Concrete Pump hour 6 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6648.00
(a+b+c)

Page 161 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork @ 3.75 per cent of cost of concrete i.e. 29914.71
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 82764.02
f) Contractor's profit @ 10 % on (a+b+c+d+e) 91040.42
cost of 120 cum = a+b+c+d+e+f 1001444.67
Rate per cum = (a+b+c+d+e+f)/120 8345.37 6084.00
say 8345.00 37.16
16.93 RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7600.00 45980.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 30.25 59.00 1784.75 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 18.15 59.00 1070.85 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 94.00 7961.80 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6974.00
(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c. 3922.66
e) Overhead charges @ 10 % on (a+b+c+d) 10852.71
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11937.98
cost of 15 cum = a+b+c+d+e+f 131317.74
Rate per cum (a+b+c+d+e+f )/15 8754.52 5618
say 8755.00 55.84
16.93 E With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 7600.00 367688.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004

Page 162 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 241.90 59.00 14272.10 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 145.14 59.00 8563.26 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 677.32 94.00 63668.08 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity 1 cum hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6876.00
(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 30940.08
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 85600.88
f) Contractor's profit @ 10 % on (a+b+c+d+e) 94160.97
cost of 120 cum = a+b+c+d+e+f 1035770.69
Rate per cum (a+b+c+d+e+f )/120 8631.42 6219
say 8631.00 38.78
16.94 PCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7600.00 46208.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 30.40 59.00 1793.60 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 18.24 59.00 1076.16 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement

Page 163 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.12 94.00 8001.28 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 6799.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 3569.05
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 10554.18
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11609.60
cost of 15 cum = a+b+c+d+e+f 127705.55
Rate per cum (a+b+c+d+e+f )/15 8513.70 5522
say 8514.00 54.18
16.95 F Using Batching Plant, Transit Mixer and Concrete
Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 7600.00 369360.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
40 mm Aggregate cum 43.20 1761.00 76075.20 M-055
20 mm Aggregate cum 43.20 2088.00 90201.60 M-053
10 mm Aggregate cum 21.60 2513.00 54280.80 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 243.00 59.00 14337.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 145.80 59.00 8602.20 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 680.40 94.00 63957.60 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049

Page 164 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6699.00
(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 28133.97
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 83196.17
f) Contractor's profit @ 10 % on (a+b+c+d+e) 91515.79
cost of 120 cum = a+b+c+d+e+f 1006673.64
Rate per cum (a+b+c+d+e+f )/120 8388.95 6120
say 8389.00 37.08
16.96 RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7600.00 46360.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 30.50 59.00 1799.50 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 18.30 59.00 1079.70 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 94.00 8027.60 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 7005.00
(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. 3677.58
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 10875.14
f) Contractor's profit @ 10 % on (a+b+c+d+e) 11962.65
cost of 15 cum = a+b+c+d+e+f 131589.17
Rate per cum = (a+b+c+d+e+f)/15 8772.61 5635
say 8773.00 55.69
16.97 G Using Batching Plant, Transit Mixer and Concrete
Pump

Page 165 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 7600.00 370880.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 244.00 59.00 14396.00 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 146.40 59.00 8637.60 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 683.20 94.00 64220.80 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6909.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. 29015.41
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 85802.71
f) Contractor's profit @ 10 % on (a+b+c+d+e) 94382.98
cost of 120 cum = a+b+c+d+e+f 1038212.82
Rate per cum (a+b+c+d+e+f )/120 8651.77 6236
say 8652.00 38.74
16.98 RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7600.00 48108.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051

Page 166 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 31.65 59.00 1867.35 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 18.99 59.00 1120.41 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 94.00 8330.28 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 7149.00
(a+b+c)
d) Formwork @ 3 per cent on a+b+c 3216.99
e) Overhead charges @ 10 % on (a+b+c+d) 11045.00
f) Contractor's profit @ 10 % on (a+b+c+d+e) 12149.50
cost of 15 cum = a+b+c+d+e+f 133644.53
Rate per cum = (a+b+c+d+e+f)/15 8909.64 5750
say 8910.00 54.96
16.99 H Using Batching Plant, Transit Mixer and Concrete
Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 7600.00 384864.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent) @ 5 Lit Lit 253.20 59.00 14938.80 M-209
per MT cement
Air entraining and water reducing plasticiser Lit 151.92 59.00 8963.28 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent) @ 3 Lit per MT cement
Accelerating plasticiser conforming to IS-9103-1999 Lit 708.96 94.00 66642.24 M-211
( Masterplast APCL or equivalent) @ 14 Lit per MT
cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080

Page 167 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Loader1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 7053.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 25388.57
of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 87167.42
f) Contractor's profit @ 10 % on (a+b+c+d+e) 95884.16
cost of 120 cum = a+b+c+d+e+f 1054725.79
Rate per cum = (a+b+c+d+e+f)/120 8789.38 6348
say 8789.00 38.45
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
WELL FOUNDATION
16.99.1 Providing and Constructing Temporary Island 16 m
diameter for Construction of Well Foundation for 8m
dia. Well.
Assuming depth of water 1.0 m and height of island to
be 1.25 m.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 251.20 0.0 0.00 M-095
Sand bags each 750.00 15.00 11250.00 M-159
b) Labour
Mate day 0.40 356.65 142.66 L-12
Mazdoor for filling sand bags, stitching and placing day 15.00 244.56 3668.40 L-13
c) Machinery
Crane with grab 1 cum capacity hour 20.00 759.00 15180.00 P&M-012
Consumables @ 2.5 per cent of (c) above 379.50
d) Overhead charges @ 10 % on (a+b+c) 3062.06
e) Contractor's profit @ 10 % on (a+b+c+d) 3368.26
Rate per No. (a+b+c+d+e) 37050.88 42695
say 37051.00 (13.22)
It is assumed that earth will be available within the working
space of crane with grab bucket.
16.99.2 Assuming depth of water 4.0 m and height of island
4.5 m.
Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 0.00 0.00 M-095
Sand bags each 6000.00 15.00 90000.00 M-159
Wooden ballies 8" Dia and 9 m long each 95.00 3658.00 347510.00 M-194
Wooden ballies 2" Dia for bracing metre 190.00 234.00 44460.00 M-193
b) Labour

Page 168 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 5.60 356.65 1997.24 L-12
Mazdoor for piling 8" dia ballies for piling 8" dia day 18.00 244.56 4402.08 L-13
ballies
Mazdoor for bracing with 2" dia ballies day 12.00 244.56 2934.72 L-13
Mazdoor for filling sand bags, stitching and placing day 110.00 244.56 26901.60 L-13
c) Machinery
Crane with grab 1 cum capacity hour 50.00 759.00 37950.00 P&M-012
Consumables and other arrangements for piling ballies @ 13903.89
2.5 per cent of (a+b+c).
d) Overhead charges @ 10 % on (a+b+c) 57005.95
e) Contractor's profit @ 10 % on (a+b+c+d) 62706.55
Rate per No. (a+b+c+d+e) 689772.03 607670
say 689772.00 13.51
For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
16.99.3 Providing and constructing one span service road to
reach island location from one pier location to another
pier location
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth cum 450.00 0.00 0.00 M-095
Sand bags each 300.00 15.00 4500.00 M-159
b) Labour
Mate day 0.24 356.65 85.60 L-12
Mazdoor for filling sand bags, stitching and placing day 6.00 244.56 1467.36 L-13
c) Machinery
Front end Loader 1 cum capacity hour 27.00 882.00 23814.00 P&M-017
Tipper 5.5 cum capacity hour 28.00 680.00 19040.00 P&M-048
d) Overhead charges @ 10 % on (a+b+c) 4890.70
e) Contractor's profit @ 10 % on (a+b+c+d) 5379.77
Cost for 30 m (a+b+c+d+e) 59177.42
Rate per m (a+b+c+d+e)/30 1972.58 2007
say 1973.00 (1.69)
16.99.4 Providing and Laying Cutting Edge of Mild Steel
weighing 40 kg per metre for Well Foundation
complete as per Drawing and Technical Specification.

Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per tonne 1.05 62000.00 65100.00 M-179
cent wastage
Nuts & bolts Kg 20.00 90.00 1800.00 M-130
b) Labour
(for cutting, bending, making holes, joining, welding
and erecting in position)
Mate day 1.32 356.65 470.78 L-12
Fitter day 5.50 356.65 1961.58 L-07

Page 169 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Blacksmith day 5.50 458.55 2522.03 L-02
Welder day 5.50 458.55 2522.03 L-02
Mazdoor day 16.50 244.56 4035.24 L-13
Electrodes, cutting gas and other consumables @ 10 per 6690.00
cent of cost of (a) above
c) Overhead charges @ 10 % on (a+b) 8510.16
d) Contractor's profit @ 10 % on (a+b+c) 9361.18
Rate per MT (a+b+c+d) 102972.99 60374
say 102973.00 70.56
16.99.5 Plain/Reinforced cement concrete, in well foundation
complete as per drawing and technical specification and
steel shuttering formwork.

(A) Without plasticiser

Unit = 1 cum
Taking output = 1 cum
Well curb
RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5238.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1047.60
e) Overhead charges @ 10 % on (a+b+c+d) 628.56
f) Contractor's profit @ 10 % on (a+b+c+d+e) 691.42
Rate perm (a+b+c+d+e+f) 7605.58 5009
say 7606.00 51.85
16.99.6 A (i) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5159.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1031.80
e) Overhead charges @ 10 % on (a+b+c+d) 619.08
f) Contractor's profit @ 10 % on (a+b+c+d+e) 680.99
Rate perm (a+b+c+d+e+f) 7490.87 5704
say 7491.00 31.33
16.99.7 A RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5664.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1132.80
e) Overhead charges @ 10 % on (a+b+c+d) 679.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 747.65

Page 170 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate perm (a+b+c+d+e+f) 8224.13 5470
say 8224.00 50.35
16.99.8 A With Batching Plant, Transit Mixer and Concrete Pump
(ii)
Per Cum Basic Cost of Labour, Material & Machinery 5584.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1116.80
e) Overhead charges @ 10 % on (a+b+c+d) 670.08
f) Contractor's profit @ 10 % on (a+b+c+d+e) 737.09
Rate perm (a+b+c+d+e+f) 8107.97 6165
say 8108.00 31.52
16.99.9 A RCC M30 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5689.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1137.80
e) Overhead charges @ 10 % on (a+b+c+d) 682.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 750.95
Rate perm (a+b+c+d+e+f) 8260.43
say 8260.00
16.99.10 A With Batching Plant, Transit Mixer and Concrete Pump
(ii)
Per Cum Basic Cost of Labour, Material & Machinery 5611.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1122.20
e) Overhead charges @ 10 % on (a+b+c+d) 673.32
f) Contractor's profit @ 10 % on (a+b+c+d+e) 740.65
Rate perm (a+b+c+d+e+f) 8147.17
say 8147.00
16.99.11 A RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.0 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5805.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1161.00
e) Overhead charges @ 10 % on (a+b+c+d) 696.60
f) Contractor's profit @ 10 % on (a+b+c+d+e) 766.26
Rate perm (a+b+c+d+e+f) 8428.86 5623
say 8429.00 49.90
16.99.12 A With Batching Plant, Transit Mixer and Concrete Pump
(iii)

Page 171 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Per Cum Basic Cost of Labour, Material & Machinery 5727.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1145.40
e) Overhead charges @ 10 % on (a+b+c+d) 687.24
f) Contractor's profit @ 10 % on (a+b+c+d+e) 755.96
Rate perm (a+b+c+d+e+f) 8315.60 6320
say 8316.00 31.58
If curb concrete is carried out within steel liner, cost of
formwork shall be excluded.

16.99.13 Well steining


PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 4585.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 458.50
e) Overhead charges @ 10 % on (a+b+c+d) 504.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 554.79
Rate perm (a+b+c+d+e+f) 6102.64 4005
say 6103.00 52.38
16.99.14 B PCC M20 Grade
Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5088.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 508.80
e) Overhead charges @ 10 % on (a+b+c+d) 559.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 615.65
Rate perm (a+b+c+d+e+f) 6772.13 4458
say 6772.00 51.91
16.99.15 B RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5238.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 523.80
e) Overhead charges @ 10 % on (a+b+c+d) 576.18
f) Contractor's profit @ 10 % on (a+b+c+d+e) 633.80
Rate perm (a+b+c+d+e+f) 6971.78 4591
say 6972.00 51.86

Page 172 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.99.16 B With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery 5159.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 515.90
e) Overhead charges @ 10 % on (a+b+c+d) 567.49
f) Contractor's profit @ 10 % on (a+b+c+d+e) 624.24
Rate perm (a+b+c+d+e+f) 6866.63 4943
say 6867.00 38.92
16.99.17 B PCC M25 Grade
Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5508.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 550.80
e) Overhead charges @ 10 % on (a+b+c+d) 605.88
f) Contractor's profit @ 10 % on (a+b+c+d+e) 666.47
Rate perm (a+b+c+d+e+f) 7331.15 5229
say 7331.00 40.20
16.99.18 B With Batching Plant, Transit Mixer and Concrete Pump
(iv)
Per Cum Basic Cost of Labour, Material & Machinery 5518.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 551.80
e) Overhead charges @ 10 % on (a+b+c+d) 606.98
f) Contractor's profit @ 10 % on (a+b+c+d+e) 667.68
Rate perm (a+b+c+d+e+f) 7344.46 4876
say 7344.00 50.62
16.99.19 B RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5664.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 566.40
e) Overhead charges @ 10 % on (a+b+c+d) 623.04
f) Contractor's profit @ 10 % on (a+b+c+d+e) 685.34
Rate perm (a+b+c+d+e+f) 7538.78 5014
say 7539.00 50.36
16.99.20 B With Batching Plant, Transit Mixer and Concrete Pump
(v)
Per Cum Basic Cost of Labour, Material & Machinery 5584.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 558.40

Page 173 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
e) Overhead charges @ 10 % on (a+b+c+d) 614.24
f) Contractor's profit @ 10 % on (a+b+c+d+e) 675.66
Rate perm (a+b+c+d+e+f) 7432.30 5651
say 7432.00 31.52
16.99.21 B PCC M30 Grade
Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5554.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 555.40
e) Overhead charges @ 10 % on (a+b+c+d) 610.94
f) Contractor's profit @ 10 % on (a+b+c+d+e) 672.03
Rate perm (a+b+c+d+e+f) 7392.37 4921
say 7392.00 50.21
16.99.23 B With Batching Plant, Transit Mixer and Concrete Pump
(vi)
Per Cum Basic Cost of Labour, Material & Machinery 5473.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 547.30
e) Overhead charges @ 10 % on (a+b+c+d) 602.03
f) Contractor's profit @ 10 % on (a+b+c+d+e) 662.23
Rate perm (a+b+c+d+e+f) 7284.56 5558
say 7285.00 31.07
16.99.24 B RCC M30 Grade
Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5689.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 568.90
e) Overhead charges @ 10 % on (a+b+c+d) 625.79
f) Contractor's profit @ 10 % on (a+b+c+d+e) 688.37
Rate perm (a+b+c+d+e+f) 7572.06 5038
say 7572.00 50.30
16.99.25 B With Batching Plant, Transit Mixer and Concrete Pump
(vii)
Per Cum Basic Cost of Labour, Material & Machinery 5611.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 561.10
e) Overhead charges @ 10 % on (a+b+c+d) 617.21
f) Contractor's profit @ 10 % on (a+b+c+d+e) 678.93
Rate perm (a+b+c+d+e+f) 7468.24 5677
say 7468.00 31.55

Page 174 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.99.26 B RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5805.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 580.50
e) Overhead charges @ 10 % on (a+b+c+d) 638.55
f) Contractor's profit @ 10 % on (a+b+c+d+e) 702.41
Rate perm (a+b+c+d+e+f) 7726.46 5155
say 7726.00 49.87
16.99.27B With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery 5727.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 572.70
e) Overhead charges @ 10 % on (a+b+c+d) 629.97
f) Contractor's profit @ 10 % on (a+b+c+d+e) 692.97
Rate perm (a+b+c+d+e+f) 7622.64 5793
say 7623.00 31.59

16.99. 28B RCC M40 Grade


Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7600.00 392160.00 M-084
Coarse Sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Meson day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 50870.00
(a+b+c)

Page 175 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork @ 10 per cent on cost of concrete i.e. 76303.73
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 83934.10
f) Contractor's profit @ 10 % on (a+b+c+d+e) 92327.52
cost of 120 cum = a+b+c+d+e+f 1015602.67
Rate per cum = (a+b+c+d+e+f)/120 8463.36 5853
say 8463.00 44.59
16.99.29 B Bottom Plug
Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 7600.00 42180.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 5934.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4204.70
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 9320.07


e) Contractor's profit @ 10 % on (a+b+c+d) 10252.07
cost of 15 cum = a+b+c+d+e 112772.80
Rate per cum = (a+b+c+d+e)/15 7518.19 4597
say 7518.00 63.54
16.99.30C Using Batching Plant, Transit Mixer and
(i) Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material

Page 176 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cement tonne 44.40 7600.00 337440.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 5903.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 32747.48
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 74107.91


e) Contractor's profit @ 10 % on (a+b+c+d) 81518.70
cost of 120 cum = a+b+c+d+e 896705.66
Rate per cum = (a+b+c+d+e)/120 7472.55 4630
say 7473.00 61.40
16.99.31 C PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7600.00 45524.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079

Page 177 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6156.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4076.90
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 9641.69


e) Contractor's profit @ 10 % on (a+b+c+d) 10605.85
cost of 15 cum = a+b+c+d+e 116664.40
Rate per cum = (a+b+c+d+e)/15 7777.63 4809
say 7778.00 61.74
16.99.32 C Using Batching Plant, Transit Mixer and
(ii) Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 7600.00 363888.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6124.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 34069.88
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 76884.95


e) Contractor's profit @ 10 % on (a+b+c+d) 84573.44
cost of 120 cum = a+b+c+d+e 930307.85
Rate per cum = (a+b+c+d+e)/120 7752.57 5312
say 7753.00 45.95
16.99.33 C PCC Grade M30

Page 178 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7600.00 46208.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6202.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4406.10
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 9743.01


e) Contractor's profit @ 10 % on (a+b+c+d) 10717.31
cost of 15 cum = a+b+c+d+e 117890.37
Rate per cum = (a+b+c+d+e)/15 7859.36 4852
say 7859.00 61.97
16.99.34 C Using Batching Plant, Transit Mixer and
(iii) Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 7600.00 369664.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080

Page 179 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6172.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 34358.68
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 77491.43


e) Contractor's profit @ 10 % on (a+b+c+d) 85240.57
cost of 120 cum = a+b+c+d+e 937646.26
Rate per cum = (a+b+c+d+e)/120 7813.72 5358
say 7814.00 45.84
16.99.34-D PCC Grade M35
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 7600.00 47804.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6308.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4485.90
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 9910.59


e) Contractor's profit @ 10 % on (a+b+c+d) 10901.64
cost of 15 cum = a+b+c+d+e 119918.09
Rate per cum = (a+b+c+d+e)/15 7994.54 4953
say 7995.00 61.42

Page 180 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.99.35 Using Batching Plant, Transit Mixer and
(iv) Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 7600.00 382128.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6276.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 34981.88
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 78800.15


e) Contractor's profit @ 10 % on (a+b+c+d) 86680.16
cost of 120 cum = a+b+c+d+e 953481.77
Rate per cum = (a+b+c+d+e)/120 7945.68 5456
say 7946.00 45.64
16.99.36 Intermediate plug
Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5414.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 541.40
e) Contractor's profit @ 10 % on (a+b+c+d) 595.54
Rate per cum = (a+b+c+d+e) 6550.94 4400
say 6551.00 48.89
16.99.36D Using Batching Plant, Transit Mixer and
(i) Crane/concrete pump

Page 181 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Per Cum Basic Cost of Labour, Material & Machinery 5314.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 531.40
e) Contractor's profit @ 10 % on (a+b+c+d) 584.54
Rate per cum = (a+b+c+d+e) 6429.94 4909
say 6430.00 30.98
16.99.36 E Grade M25 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5637.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 563.70
e) Contractor's profit @ 10 % on (a+b+c+d) 620.07
Rate per cum = (a+b+c+d+e) 6820.77 4602
say 6821.00 48.22
16.99.37 D Using Batching Plant, Transit Mixer and
(ii) Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 5534.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 553.40
e) Contractor's profit @ 10 % on (a+b+c+d) 608.74
Rate per cum = (a+b+c+d+e) 6696.14 5108
say 6696.00 31.09
16.99.38 D Grade M30 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5682.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 568.20
e) Contractor's profit @ 10 % on (a+b+c+d) 625.02
Rate per cum = (a+b+c+d+e) 6875.22 4642
say 6875.00 48.10
12.11 D (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 5582.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 558.20
e) Contractor's profit @ 10 % on (a+b+c+d) 614.02
Rate per cum = (a+b+c+d+e) 6754.22 5152
say 6754.00 31.09
12.11 Top plug
Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Using Concrete Mixer

Page 182 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Per Cum Basic Cost of Labour, Material & Machinery 4585.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 458.50
e) Contractor's profit @ 10 % on (a+b+c+d) 504.35
Rate per cum = (a+b+c+d+e) 5547.85 3641
say 5548.00 52.38
'12.11 E Grade M20 PCC
Same as Item 12.8(b) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5088.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 508.80
e) Contractor's profit @ 10 % on (a+b+c+d) 559.68
Rate per cum = (a+b+c+d+e) 6156.48 4052
say 6156.00 51.92
'12.11 E Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5508.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 550.80
e) Contractor's profit @ 10 % on (a+b+c+d) 605.88
Rate per cum = (a+b+c+d+e) 6664.68 4433
say 6665.00 50.35
12.11 E (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 5518.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 551.80
e) Contractor's profit @ 10 % on (a+b+c+d) 606.98
Rate per cum = (a+b+c+d+e) 6676.78 5015
say 6677.00 33.14
'12.11 E Grade M30 PCC
Same as Item 12.8(f) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5554.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 555.40
e) Contractor's profit @ 10 % on (a+b+c+d) 610.94
Rate per cum = (a+b+c+d+e) 6720.34 4473
say 6720.00 50.23
12.11 E (iv) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 5473.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 547.30

Page 183 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
e) Contractor's profit @ 10 % on (a+b+c+d) 602.03
Rate per cum = (a+b+c+d+e) 6622.33 5053
say 6622.00 31.05
12.11 Well cap
RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7600.00 38912.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Form Work @ 4 per cent of a+b+c 3468.76
d) Overhead charges @ 10 % on (a+b+c) 9018.78
e) Contractor's profit @ 10 % on (a+b+c+d) 9920.65
cost of 15 cum = a+b+c+d+e 109127.18
Rate per cum = (a+b+c+d+e)/15 7275.15 4297
say 7275.00 69.30
12.11 F (i) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7600.00 310992.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 882.00 5292.00 P&M-017

Page 184 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 4 per cent of (a+b+c) 27274.77
d) Overhead charges @ 10 % on (a+b+c) 70914.41
e) Contractor's profit @ 10 % on (a+b+c+d) 78005.85
cost of 120 cum = a+b+c+d+e 858064.35
Rate per cum = (a+b+c+d+e)/120 7150.54 4898
say 7151.00 46.00
12.11 F RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7600.00 45980.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Form Work @ 3.75 per cent of a+b+c 3517.01
d) Overhead charges @ 10 % on (a+b+c) 9730.40
e) Contractor's profit @ 10 % on (a+b+c+d) 10703.44
cost of 15 cum = a+b+c+d+e 117737.85
Rate per cum = (a+b+c+d+e)/15 7849.19 4728
say 7849.00 66.01
12.11 F (ii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 7600.00 367840.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12

Page 185 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3.75 per cent of ( a+b+c) 27701.90
d) Overhead charges @ 10 % on (a+b+c) 76641.92
e) Contractor's profit @ 10 % on (a+b+c+d) 84306.11
cost of 120 cum = a+b+c+d+e 927367.25
Rate per cum = (a+b+c+d+e)/120 7728.06 5330
say 7728.00 44.99
12.11 F RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7600.00 46360.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Formwork @ 3.5 per cent of (a+b+c) 3295.84
d) Overhead charges @ 10 % on (a+b+c) 9746.28
e) Contractor's profit @ 10 % on (a+b+c+d) 10720.91
cost of 15 cum = a+b+c+d+e 117930.03
Rate per cum = (a+b+c+d+e)/15 7862.00 4740
say 7862.00 65.86
12.11 F (iii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material

Page 186 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cement tonne 48.79 7600.00 370804.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3.5 per cent of (a+b+c) 25958.85
d) Overhead charges @ 10 % on (a+b+c) 76764.02
e) Contractor's profit @ 10 % on (a+b+c+d) 84440.42
cost of 120 cum = a+b+c+d+e 928844.60
Rate per cum = (a+b+c+d+e)/120 7740.37 4341
say 7740.00 78.30
12.11 F RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7600.00 48108.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Formwork @ 3 per cent of (a+b+c) 2877.45
d) Overhead charges @ 10 % on (a+b+c) 9879.24
e) Contractor's profit @ 10 % on (a+b+c+d) 10867.17
cost of 15 cum = a+b+c+d+e 119538.86

Page 187 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum = (a+b+c+d+e)/15 7969.26 4826
say 7969.00 65.13
12.11 F (iv) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7600.00 384864.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3 per cent of (a+b+c) 22672.24
d) Overhead charges @ 10 % on (a+b+c) 77841.36
e) Contractor's profit @ 10 % on (a+b+c+d) 85625.49
cost of 120 cum = a+b+c+d+e 941880.40
Rate per cum = (a+b+c+d+e)/120 7849.00 5424
say 7849.00 44.71
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
'12.11 F RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 7600.00 396720.00 M-084
Coarse Sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
b) Labour

Page 188 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3 per cent on cost of concrete i.e. cost 23027.92
of material, labour and machinery
d) Overhead charges @ 10 % on (a+b+c) 79062.52
e) Contractor's profit @ 10 % on (a+b+c+d) 86968.78
cost of 120 cum = a+b+c+d+e 956656.53
Rate per cum = (a+b+c+d+e)/120 7972.14 5516
say 7972.00 44.53
12.11 Plain/Reinforced cement concrete, in well foundation
complete as per drawing and technical specification
including providing plasticiser ( Masterplast PL-1/SPL-2 or
equivalent ), air entraining and water reducing plasticiser
( Masterplast PAE or equivalent) and accelerating
plasticiser ( Masterplast ACPL or equivalent) conforming to
IS-9103-1999.and steel shuttering formwork.

Unit = 1 cum
Taking output = 1 cum
Well curb
RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5764.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1152.80
e) Overhead charges @ 10 % on (a+b+c+d) 691.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 760.85
Rate perm (a+b+c+d+e+f) 8369.33 5886
say 8369.00 42.18
12.11 A (i) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5685.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1137.00
e) Overhead charges @ 10 % on (a+b+c+d) 682.20

Page 189 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on (a+b+c+d+e) 750.42
Rate perm (a+b+c+d+e+f) 8254.62 6582
say 8255.00 25.42
12.11 A RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6313.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1262.60
e) Overhead charges @ 10 % on (a+b+c+d) 757.56
f) Contractor's profit @ 10 % on (a+b+c+d+e) 833.32
Rate perm (a+b+c+d+e+f) 9166.48 6499
say 9166.00 41.04
12.11 A (ii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6234.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1246.80
e) Overhead charges @ 10 % on (a+b+c+d) 748.08
f) Contractor's profit @ 10 % on (a+b+c+d+e) 822.89
Rate perm (a+b+c+d+e+f) 9051.77 7399
say 9052.00 22.34
12.11 A RCC M30 Grade
Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6344.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1268.80
e) Overhead charges @ 10 % on (a+b+c+d) 761.28
f) Contractor's profit @ 10 % on (a+b+c+d+e) 837.41
Rate perm (a+b+c+d+e+f) 9211.49
say 9211.00
12.11 A (ii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6266.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1253.20
e) Overhead charges @ 10 % on (a+b+c+d) 751.92
f) Contractor's profit @ 10 % on (a+b+c+d+e) 827.11
Rate perm (a+b+c+d+e+f) 9098.23
say 9098.00
12.11 A RCC M35 Grade

Page 190 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Same as for 12.8 (H) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.0 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6485.00
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1297.00
e) Overhead charges @ 10 % on (a+b+c+d) 778.20
f) Contractor's profit @ 10 % on (a+b+c+d+e) 856.02
Rate perm (a+b+c+d+e+f) 9416.22 6700
say 9416.00 40.54
12.11 A (iii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6407.00


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete 1281.40
e) Overhead charges @ 10 % on (a+b+c+d) 768.84
f) Contractor's profit @ 10 % on (a+b+c+d+e) 845.72
Rate perm (a+b+c+d+e+f) 9302.96 7397
say 9303.00 25.77
If curb concrete is carried out within steel liner, cost of
formwork shall be excluded.

12.11 Well steining


PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5111.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 511.10
e) Overhead charges @ 10 % on (a+b+c+d) 562.21
f) Contractor's profit @ 10 % on (a+b+c+d+e) 618.43
Rate perm (a+b+c+d+e+f) 6802.74 4809
say 6803.00 41.46
12.11 B PCC M20 Grade
Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5614.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 561.40
e) Overhead charges @ 10 % on (a+b+c+d) 617.54
f) Contractor's profit @ 10 % on (a+b+c+d+e) 679.29
Rate perm (a+b+c+d+e+f) 7472.23 5264

Page 191 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 7472.00 41.95
12.11 B RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 5764.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 576.40
e) Overhead charges @ 10 % on (a+b+c+d) 634.04
f) Contractor's profit @ 10 % on (a+b+c+d+e) 697.44
Rate perm (a+b+c+d+e+f) 7671.88 5396
say 7672.00 42.18
12.11 B (iii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5685.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 568.50
e) Overhead charges @ 10 % on (a+b+c+d) 625.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 687.89
Rate perm (a+b+c+d+e+f) 7566.74 6033
say 7567.00 25.43
12.11 B PCC M25 Grade
Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6152.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 615.20
e) Overhead charges @ 10 % on (a+b+c+d) 676.72
f) Contractor's profit @ 10 % on (a+b+c+d+e) 744.39
Rate perm (a+b+c+d+e+f) 8188.31 5811
say 8188.00 40.91
12.11 B (iv) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6076.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 607.60
e) Overhead charges @ 10 % on (a+b+c+d) 668.36
f) Contractor's profit @ 10 % on (a+b+c+d+e) 735.20
Rate perm (a+b+c+d+e+f) 8087.16 6451
say 8087.00 25.36
'12.11 B RCC M25 Grade
Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Page 192 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6313.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 631.30
e) Overhead charges @ 10 % on (a+b+c+d) 694.43
f) Contractor's profit @ 10 % on (a+b+c+d+e) 763.87
Rate perm (a+b+c+d+e+f) 8402.60 5958
say 8403.00 41.04
12.11 B (v) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6234.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 623.40
e) Overhead charges @ 10 % on (a+b+c+d) 685.74
f) Contractor's profit @ 10 % on (a+b+c+d+e) 754.31
Rate perm (a+b+c+d+e+f) 8297.45 6782
say 8297.00 22.34
'12.11 B PCC M30 Grade
Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6207.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 620.70
e) Overhead charges @ 10 % on (a+b+c+d) 682.77
f) Contractor's profit @ 10 % on (a+b+c+d+e) 751.05
Rate perm (a+b+c+d+e+f) 8261.52 5869
say 8262.00 40.77
12.11 B (vi) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6126.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 612.60
e) Overhead charges @ 10 % on (a+b+c+d) 673.86
f) Contractor's profit @ 10 % on (a+b+c+d+e) 741.25
Rate perm (a+b+c+d+e+f) 8153.71 6505
say 8154.00 25.35
'12.11 B RCC M30 Grade
Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6344.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 634.40
e) Overhead charges @ 10 % on (a+b+c+d) 697.84

Page 193 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on (a+b+c+d+e) 767.62
Rate perm (a+b+c+d+e+f) 8443.86 5990
say 8444.00 40.97
12.11 B (vii) With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6266.00


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 626.60
e) Overhead charges @ 10 % on (a+b+c+d) 689.26
f) Contractor's profit @ 10 % on (a+b+c+d+e) 758.19
Rate perm (a+b+c+d+e+f) 8340.05 6628
say 8340.00 25.83
'12.11 B RCC M35 Grade
Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery 6485.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 648.50
e) Overhead charges @ 10 % on (a+b+c+d) 713.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 784.69
Rate perm (a+b+c+d+e+f) 8631.54 6142
say 8632.00 40.54
12.11 B With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery 6407.00
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete 640.70
e) Overhead charges @ 10 % on (a+b+c+d) 704.77
f) Contractor's profit @ 10 % on (a+b+c+d+e) 775.25
Rate perm (a+b+c+d+e+f) 8527.72 6781
say 8528.00 25.76
'12.11 B RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 7600.00 392160.00 M-084
Coarse Sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 258.00 59.00 15222.00 M-209

Page 194 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Air entraining and water reducing plasticiser Lit 154.80 59.00 9133.20 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 722.40 94.00 67905.60 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.84 356.65 299.59 L-12
Meson day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 57020.00
(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. 85529.81
cost of material, labour and machinery
e) Overhead charges @ 10 % on (a+b+c+d) 94082.79
f) Contractor's profit @ 10 % on (a+b+c+d+e) 103491.07
cost of 120 cum = a+b+c+d+e+f 1138401.79
Rate per cum = (a+b+c+d+e+f)/120 9486.68 6859
say 9487.00 38.31
12.11 C Bottom Plug
Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 7600.00 42180.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 22.20 128.00 2841.60 M-208
Air entraining and water reducing plasticiser Lit 16.65 59.00 982.35 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 77.70 94.00 7303.80 M-211
( Masterplast APCL or equivalent )

Page 195 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6675.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4761.09
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 10488.48


e) Contractor's profit @ 10 % on (a+b+c+d) 11537.33
cost of 15 cum = a+b+c+d+e 126910.60
Rate per cum = (a+b+c+d+e)/15 8460.71 5416
say 8461.00 56.22
12.11 C (i) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 7600.00 337440.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 177.60 128.00 22732.80 M-208
Air entraining and water reducing plasticiser Lit 133.20 59.00 7858.80 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 621.60 94.00 58430.40 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km

Page 196 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6645.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 37198.58
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 83455.22


e) Contractor's profit @ 10 % on (a+b+c+d) 91800.74
cost of 120 cum = a+b+c+d+e 1009808.11
Rate per cum = (a+b+c+d+e)/120 8415.07 5922
say 8415.00 42.10
'12.11 C PCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 7600.00 45524.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 29.95 59.00 1767.05 M-209
Air entraining and water reducing plasticiser Lit 17.97 59.00 1060.23 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 94.00 7882.84 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6871.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4907.40
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 10795.75


e) Contractor's profit @ 10 % on (a+b+c+d) 11875.32
cost of 15 cum = a+b+c+d+e 130628.56
Rate per cum = (a+b+c+d+e)/15 8708.57 5700

Page 197 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 8709.00 52.79
12.11 C (ii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 7600.00 363888.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 239.40 59.00 14124.60 M-209
Air entraining and water reducing plasticiser Lit 143.64 59.00 8474.76 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 670.32 94.00 63010.08 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6837.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 38350.35
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 85873.94


e) Contractor's profit @ 10 % on (a+b+c+d) 94461.33
cost of 120 cum = a+b+c+d+e 1039074.64
Rate per cum = (a+b+c+d+e)/120 8658.96 6203
say 8659.00 39.59
'12.11 C PCC Grade M30
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 7600.00 46208.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005

Page 198 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.40 59.00 1793.60 M-209
Air entraining and water reducing plasticiser Lit 18.24 59.00 1076.16 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.12 94.00 8001.28 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe
Per Cum Basic Cost of Labour, Material & Machinery 6927.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 4949.65
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 10884.47


e) Contractor's profit @ 10 % on (a+b+c+d) 11972.91
cost of 15 cum = a+b+c+d+e 131702.03
Rate per cum = (a+b+c+d+e)/15 8780.14 5757
say 8780.00 52.51
12.11 C (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 7600.00 369664.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 243.20 59.00 14348.80 M-209
Air entraining and water reducing plasticiser Lit 145.92 59.00 8609.28 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 680.96 94.00 64010.24 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11

Page 199 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 6897.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 38707.10
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 86623.10


e) Contractor's profit @ 10 % on (a+b+c+d) 95285.41
cost of 120 cum = a+b+c+d+e 1048139.51
Rate per cum = (a+b+c+d+e)/120 8734.50 6263
say 8734.00 39.45
'12.11 C PCC Grade M35
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 7600.00 47804.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm Aggregate cum 5.40 1761.00 9509.40 M-055
20 mm Aggregate cum 5.40 2088.00 11275.20 M-053
10 mm Aggregate cum 2.70 2513.00 6785.10 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 31.45 59.00 1855.55 M-209
Air entraining and water reducing plasticiser Lit 18.87 59.00 1113.33 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.06 94.00 8277.64 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 318.00 1908.00 P&M-013
pipe

Page 200 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Per Cum Basic Cost of Labour, Material & Machinery 7058.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 5048.22
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 11091.47


e) Contractor's profit @ 10 % on (a+b+c+d) 12200.62
cost of 15 cum = a+b+c+d+e 134206.79
Rate per cum = (a+b+c+d+e)/15 8947.12 5889
say 8947.00 51.93
12.11 C (iv) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 7600.00 382128.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 251.40 59.00 14832.60 M-209
Air entraining and water reducing plasticiser Lit 150.84 59.00 8899.56 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 703.92 94.00 66168.48 M-211
( Masterplast APCL or equivalent)
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 3000.00 7.00 21000.00 P&M-050
lead in Kilometer Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Per Cum Basic Cost of Labour, Material & Machinery 7025.00
(a+b+c)
Add 5 per cent of cost of material and labour towards cost 39476.91
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

d) Overhead charges @ 10 % on (a+b+c) 88239.71


e) Contractor's profit @ 10 % on (a+b+c+d) 97063.68
cost of 120 cum = a+b+c+d+e 1067700.53

Page 201 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum = (a+b+c+d+e)/120 8897.50 6392
say 8898.00 39.21
12.11 Intermediate plug
Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6005.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 600.50
e) Contractor's profit @ 10 % on (a+b+c+d) 660.55
Rate per cum = (a+b+c+d+e) 7266.05 5180
say 7266.00 40.27
12.11 D (i) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 5905.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 590.50
e) Contractor's profit @ 10 % on (a+b+c+d) 649.55
Rate per cum = (a+b+c+d+e) 7145.05 5689
say 7145.00 25.59
'12.11 D Grade M25 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6280.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 628.00
e) Contractor's profit @ 10 % on (a+b+c+d) 690.80
Rate per cum = (a+b+c+d+e) 7598.80 5450
say 7599.00 39.43
12.11 D (ii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6177.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 617.70
e) Contractor's profit @ 10 % on (a+b+c+d) 679.47
Rate per cum = (a+b+c+d+e) 7474.17 5957
say 7474.00 25.47
'12.11 D Grade M30 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6335.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 633.50
e) Contractor's profit @ 10 % on (a+b+c+d) 696.85

Page 202 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum = (a+b+c+d+e) 7665.35 5504
say 7665.00 39.26
12.11 D (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6253.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 625.30
e) Contractor's profit @ 10 % on (a+b+c+d) 687.83
Rate per cum = (a+b+c+d+e) 7566.13 6038
say 7566.00 25.31
12.11 Top plug
Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5111.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 511.10
e) Contractor's profit @ 10 % on (a+b+c+d) 562.21
Rate per cum = (a+b+c+d+e) 6184.31 4372
say 6184.00 41.45
'12.11 E Grade M20 PCC
Same as Item 12.8(b) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 5614.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 561.40
e) Contractor's profit @ 10 % on (a+b+c+d) 617.54
Rate per cum = (a+b+c+d+e) 6792.94 4785
say 6793.00 41.96
'12.11 E Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6152.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 615.20
e) Contractor's profit @ 10 % on (a+b+c+d) 676.72
Rate per cum = (a+b+c+d+e) 7443.92 5283
say 7444.00 40.90
12.11 E (iii) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6076.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 607.60
e) Contractor's profit @ 10 % on (a+b+c+d) 668.36
Rate per cum = (a+b+c+d+e) 7351.96 5865
say 7352.00 25.35

Page 203 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
'12.11 E Grade M30 PCC
Same as Item 12.8(f) excluding formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery 6207.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 620.70
e) Contractor's profit @ 10 % on (a+b+c+d) 682.77
Rate per cum = (a+b+c+d+e) 7510.47 5335
say 7510.00 40.77
12.11 E (iv) Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery 6126.00
(a+b+c)
d) Overhead charges @ 10 % on (a+b+c) 612.60
e) Contractor's profit @ 10 % on (a+b+c+d) 673.86
Rate per cum = (a+b+c+d+e) 7412.46 5914
say 7412.00 25.33
12.11 Well cap
RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7600.00 38912.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.48 128.00 2621.44 M-208
Air entraining and water reducing plasticiser Lit 15.36 59.00 906.24 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 71.68 94.00 6737.92 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Form Work @ 4 per cent of a+b+c 3879.38
d) Overhead charges @ 10 % on (a+b+c) 10086.40
e) Contractor's profit @ 10 % on (a+b+c+d) 11095.04
cost of 15 cum = a+b+c+d+e 122045.41
Rate per cum = (a+b+c+d+e)/15 8136.36 5045

Page 204 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 8136.00 61.27
12.11 F (i) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 7600.00 310992.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 163.68 128.00 20951.04 M-208
Air entraining and water reducing plasticiser Lit 122.76 59.00 7242.84 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 572.88 94.00 53850.72 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 4 per cent of (a+b+c) 30556.56
d) Overhead charges @ 10 % on (a+b+c) 79447.05
e) Contractor's profit @ 10 % on (a+b+c+d) 87391.75
cost of 120 cum = a+b+c+d+e 961309.27
Rate per cum = (a+b+c+d+e)/120 8010.91 5646
say 8011.00 41.89
12.11 F RCC Grade M25
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 7600.00 45980.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.25 59.00 1784.75 M-209

Page 205 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Air entraining and water reducing plasticiser Lit 18.15 59.00 1070.85 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 84.70 94.00 7961.80 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Form Work @ 3.75 per cent of a+b+c 3922.66
d) Overhead charges @ 10 % on (a+b+c) 10852.71
e) Contractor's profit @ 10 % on (a+b+c+d) 11937.98
cost of 15 cum = a+b+c+d+e 131317.74
Rate per cum = (a+b+c+d+e)/15 8754.52 5618
say 8755.00 55.84
12.11 F (ii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 7600.00 367840.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 242.00 59.00 14278.00 M-209
Air entraining and water reducing plasticiser Lit 145.20 59.00 8566.80 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 677.60 94.00 63694.40 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007

Page 206 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Formwork @ 3.75 per cent of ( a+b+c) 30947.12
d) Overhead charges @ 10 % on (a+b+c) 85620.36
e) Contractor's profit @ 10 % on (a+b+c+d) 94182.40
cost of 120 cum = a+b+c+d+e 1036006.40
Rate per cum = (a+b+c+d+e)/120 8633.39 6220
say 8633.00 38.79
12.11 F RCC Grade M30
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 7600.00 46360.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.50 59.00 1799.50 M-209
Air entraining and water reducing plasticiser Lit 18.30 59.00 1079.70 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 94.00 8027.60 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Formwork @ 3.5 per cent of (a+b+c) 3677.58
d) Overhead charges @ 10 % on (a+b+c) 10875.14
e) Contractor's profit @ 10 % on (a+b+c+d) 11962.65
cost of 15 cum = a+b+c+d+e 131589.17
Rate per cum = (a+b+c+d+e)/15 8772.61 5635
say 8773.00 55.69
16.11 F (iii) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 7600.00 370804.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 243.95 59.00 14393.05 M-209

Page 207 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Air entraining and water reducing plasticiser Lit 146.37 59.00 8635.83 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 683.06 94.00 64207.64 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3.5 per cent of (a+b+c) 29012.12
d) Overhead charges @ 10 % on (a+b+c) 85793.00
e) Contractor's profit @ 10 % on (a+b+c+d) 94372.30
cost of 120 cum = a+b+c+d+e 1038095.25
Rate per cum = (a+b+c+d+e)/120 8650.79 6236
say 8651.00 38.73
16.11 F RCC Grade M35
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 7600.00 48108.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 31.65 59.00 1867.35 M-209
Air entraining and water reducing plasticiser Lit 18.99 59.00 1120.41 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 94.00 8330.28 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009

Page 208 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Formwork @ 3 per cent of (a+b+c) 3216.99
d) Overhead charges @ 10 % on (a+b+c) 11045.00
e) Contractor's profit @ 10 % on (a+b+c+d) 12149.50
cost of 15 cum = a+b+c+d+e 133644.53
Rate per cum = (a+b+c+d+e)/15 8909.64 5750
say 8910.00 54.96
16.11 F (iv) Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 7600.00 384864.00 M-084
Coarse sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 253.20 59.00 14938.80 M-209
Air entraining and water reducing plasticiser Lit 151.92 59.00 8963.28 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 708.96 94.00 66642.24 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader (capacity 1 cum) hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3 per cent of (a+b+c) 25388.57
d) Overhead charges @ 10 % on (a+b+c) 87167.42
e) Contractor's profit @ 10 % on (a+b+c+d) 95884.16
cost of 120 cum = a+b+c+d+e 1054725.79
Rate per cum = (a+b+c+d+e)/120 8789.38 6348
say 8789.00 38.45
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.

Page 209 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.11 F RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 7600.00 396720.00 M-084
Coarse Sand cum 54.00 1251.00 67554.00 M-004
20 mm Aggregate cum 64.80 2088.00 135302.40 M-053
10 mm Aggregate cum 43.20 2513.00 108561.60 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 261.00 59.00 15399.00 M-209
Air entraining and water reducing plasticiser Lit 156.60 59.00 9239.40 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 730.80 94.00 68695.20 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader 1 cum capacity hour 6.00 882.00 5292.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 828.00 12420.00 P&M-049
Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 3000.00 7.00 21000.00 P&M-050
Lead= 10 km
Concrete Pump hour 6.00 234.00 1404.00 P&M-007
Formwork @ 3 per cent on cost of concrete i.e. cost 25827.93
of material, labour and machinery
d) Overhead charges @ 10 % on (a+b+c) 88675.88
e) Contractor's profit @ 10 % on (a+b+c+d) 97543.47
cost of 120 cum = a+b+c+d+e 1072978.20
Rate per cum = (a+b+c+d+e)/120 8941.49 6469
say 8941.00 38.21
16.12 Sinking of 6 m external diameter well (other than
pneumatic method of sinking) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckon
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.

Page 210 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.12 356.65 42.80 L-12
Sinker ( skilled ) day 1.00 356.65 356.65 L-15
Sinking helper ( semi-skilled ) day 2.00 285.32 570.64 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 2.00 1304.00 2608.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 260.80
c) Overhead charges @ 10 % on (a+b) 383.89
d) Contractor's profit @ 10 % on (a+b+c) 422.28
Rate per metre = (a+b+c+d) 4645.05 3857
say 4645.00 20.43
16.12 A Beyond 3m upto 10m depth
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 356.65 53.50 L-12
Sinker day 1.25 356.65 445.81 L-15
Sinking helper ( semi-skilled ) day 2.50 285.32 713.30 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1304.00 3912.00 P&M-075
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b) 391.20
c) Overhead charges @ 10 % on (a+b) 551.58
d) Contractor's profit @ 10 % on (a+b+c) 606.74
Rate per metre = (a+b+c+d) 6674.13 5682
say 6674.00 17.46
16.12 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 7008.00
12th m 5% 7358.00
13th m 5% 7726.00
14th m 5% 8112.00
15th m 5% 8518.00
16th m 5% 8944.00
17th m 5% 9391.00
18th m 5% 9861.00
19th m 5% 10354.00
20th m 5% 10872.00
Total Cost from 10m upto 20m 88144.00 7504.00
Avg Rate per metre 8814.00 17.46
16.12 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 211 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 11687.00 14024.00 1.08


22nd m 7.5% 12564.00 15077.00
23rd m 7.5% 13506.00 16207.00
24th m 7.5% 14519.00 17423.00
25th m 7.5% 15608.00 18730.00
26th m 7.5% 16779.00 20135.00
27th m 7.5% 18037.00 21644.00
28th m 7.5% 19390.00 23268.00
29th m 7.5% 20844.00 25013.00
30th m 7.5% 22407.00 26888.00
Total Cost from 20m upto 30m 165341.00 198409.00 14076.00 16891
Avg Rate per metre 16534.00 19841.00 17.46 17.46
16.12 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

31st m 10% 24648.00 29578.00


32nd 10% 27113.00 32536.00
33rd m 10% 29824.00 35789.00
34th m 10% 32806.00 39367.00
35th m 10% 36087.00 43304.00
36th m 10% 39696.00 47635.00
37th m 10% 43666.00 52399.00
38th m 10% 48033.00 57640.00
39th m 10% 52836.00 63403.00
40th m 10% 58120.00 69744.00
Total Cost from 30m upto 40m 392829.00 471395.00 33442.00 40130.00
Avg Rate per metre 39283.00 47140.00 17.47 17.47
16.12 Clayey Soil ( 6m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 356.65 53.50 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 2.25 285.32 641.97 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1304.00 3912.00 P&M-075
0.75 cum capacity and accessories

Page 212 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Consumables in sinking @ 10 per cent of (b) 391.20
c) Overhead charges @ 10 % on (a+b) 553.36
d) Contractor's profit @ 10 % on (a+b+c) 608.70
Rate per metre = (a+b+c+d) 6695.71 5683
say 6696.00 17.83
16.12 B Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 356.65 107.00 L-12
Sinker day 3.00 356.65 1069.95 L-15
Sinking helper ( semi-skilled ) day 4.50 285.32 1283.94 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 2.00 284.00 568.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 839.20
c) Overhead charges @ 10 % on (a+b) 1169.21
d) Contractor's profit @ 10 % on (a+b+c) 1286.13
Rate per metre = (a+b+c+d) 14147.42 12190
say 14147.00 16.05
16.12 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 14854.00 15597.00


12th m 5% 15597.00 16377.00
13th m 5% 16377.00 17196.00
14th m 5% 17196.00 18056.00
15th m 5% 18056.00 18959.00
16th m 5% 18959.00 19907.00
17th m 5% 19907.00 20902.00
18th m 5% 20902.00 21947.00
19th m 5% 21947.00 23044.00
20th m 5% 23044.00 24196.00
Total Cost from 10m upto 20m 186839.00 196181.00 16030.00 16906.00
Avg Rate per metre 18684.00 19618.00 16.56 16.04
16.12 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering of the cost, if required

Page 213 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
21st m 7.5% 24772.00 30965.00 32513.00
22nd m 7.5% 26630.00 33288.00 34952.00
23rd m 7.5% 28627.00 35784.00 37573.00
24th m 7.5% 30774.00 38468.00 40391.00
25th m 7.5% 33082.00 41353.00 43421.00
26th m 7.5% 35563.00 44454.00 46677.00
27th m 7.5% 38230.00 47788.00 50177.00
28th m 7.5% 41097.00 51371.00 53940.00
29th m 7.5% 44179.00 55224.00 57985.00
30th m 7.5% 47492.00 59365.00 62333.00
Total Cost from 20m upto 30m 350446.00 438060.00 459962.00
Avg Rate per metre 35045.00 43806.00 45996.00
30201.00 37751.00 39639.00
16.0% 16.0% 16.0%
16.12 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 52241.00 62689.00 65823.00
32nd 10% 57465.00 68958.00 72406.00
33rd m 10% 63212.00 75854.00 79647.00
34th m 10% 69533.00 83440.00 87612.00
35th m 10% 76486.00 91783.00 96372.00
36th m 10% 84135.00 100962.00 106010.00
37th m 10% 92549.00 111059.00 116612.00
38th m 10% 101804.00 122165.00 128273.00
39th m 10% 111984.00 134381.00 141100.00
40th m 10% 123182.00 147818.00 155209.00
Total Cost from 30m upto 40m 832591.00 999109.00 1049064.00
Avg Rate per metre 83259.00 99911.00 104906.00
71752.00 86103.00 90408.00
16.0% 16.0% 16.0%
16.12 Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.

Page 214 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Labour
Mate day 0.92 356.65 328.12 L-12
Sinker ( skilled ) day 3.00 356.65 1069.95 L-15
Sinking helper ( semi-skilled ) day 20.00 285.32 5706.40 L-14
Diver day 0.50 356.65 178.33 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1304.00 5216.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.50 284.00 994.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 621.00
Add for dewatering @ of 5 per cent of (a+b), if 705.69
required
c) Overhead charges @ 10 % on (a+b) 1481.95
d) Contractor's profit @ 10 % on (a+b+c) 1630.14
Rate per metre = (a+b+c+d) 17931.57 12174
say 17932.00 47.30%
16.12 Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 120.00 480.00 M-104
Electric Detonators each 18.00 3.92 70.56 M-097/100
b) Labour
Mate day 1.56 356.65 556.37 L-12
Driller day 2.00 356.65 713.30 L-07
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 12.00 244.56 2934.72 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 2.00 284.00 568.00 P&M-063
pneumatic breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if 705.61
required.
Consumables in sinking @ 10 per cent of cost of 839.20
d) (b).
Overhead charges @ 10 % on (a+b+c) 1620.75
e) Contractor's profit @ 10 % on (a+b+c+d) 1782.83
Rate per metre = (a+b+c+d+e) 19611.10 15114
say 19611.00 29.75%

Page 215 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.13 Sinking of 7 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is reck

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 7 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.15 356.65 53.50 L-12
Sinker ( skilled ) day 1.25 356.65 445.81 L-15
Sinking helper ( semi-skilled ) day 2.50 285.32 713.30 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 3.25 1304.00 4238.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 423.80
c) Overhead charges @ 10 % on (a+b) 587.44
d) Contractor's profit @ 10 % on (a+b+c) 587.44
Rate per metre = (a+b+c+d) 7049.29 6019
say 7049.00 17.11%
16.13 A Beyond 3m upto 10m depth
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 356.65 64.20 L-12
Sinker day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 3.00 285.32 855.96 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1304.00 5868.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 586.80
c) Overhead charges @ 10 % on (a+b) 790.99
d) Contractor's profit @ 10 % on (a+b+c) 870.09
Rate per metre = (a+b+c+d) 9571.02 8366
say 9571.00 14.40%
16.13 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 10050.00
12th m 5% 10553.00
13th m 5% 11081.00
14th m 5% 11635.00
15th m 5% 12217.00

Page 216 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16th m 5% 12828.00
17th m 5% 13469.00
18th m 5% 14142.00
19th m 5% 14849.00
20th m 5% 15591.00
Total Cost from 10m upto 20m 126415.00 11049.00
Avg Rate per metre 12642.00 14.20
16.13 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour). for Kentledge

21st m 7.5% 16760.00 20112.00


22nd m 7.5% 18017.00 21620.00
23rd m 7.5% 19368.00 23242.00
24th m 7.5% 20821.00 24985.00
25th m 7.5% 22383.00 26860.00
26th m 7.5% 24062.00 28874.00
27th m 7.5% 25867.00 31040.00
28th m 7.5% 27807.00 33368.00
29th m 7.5% 29893.00 35872.00
30th m 7.5% 32135.00 38562.00
Total Cost from 20m upto 30m 237113.00 284535.00 20726.00 24871.00
Avg Rate per metre 23711.00 28454.00 14.40 14.41
16.13 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 35349.00 42419.00


32nd 10% 38884.00 46661.00
33rd m 10% 42772.00 51326.00
34th m 10% 47049.00 56459.00
35th m 10% 51754.00 62105.00
36th m 10% 56929.00 68315.00
37th m 10% 62622.00 75146.00
38th m 10% 68884.00 82661.00
39th m 10% 75772.00 90926.00
40th m 10% 83349.00 100019.00
Total Cost from 30m upto 40m 563364.00 676037.00 49243.00 59092.00
Avg Rate per metre 56336.00 67604.00 14.40 14.40
16.13 Clayey Soil ( 7m dia. Well )
Unit = Running Meter.

Page 217 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Taking output = 1 cum
Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 356.65 64.20 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 3.00 285.32 855.96 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1304.00 5868.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 586.80
d) Overhead charges @ 10 % on (a+b) 790.99
e) Contractor's profit @ 10 % on (a+b+c) 870.09
Rate per metre = (a+b+c+d) 9571.02 8366.00
say 9571.00 14.40
16.13 B Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 356.65 92.73 L-12
Sinker day 2.00 356.65 713.30 L-15
Sinking helper ( semi-skilled ) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.25 284.00 923.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 874.70
c) Overhead charges @ 10 % on (a+b) 1156.90
d) Contractor's profit @ 10 % on (a+b+c) 1272.59
Rate per metre = (a+b+c+d) 13998.50 12191.00
say 13999.00 14.83
16.13 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 14698.00 15433.00


12th m 5% 15433.00 16205.00
13th m 5% 16205.00 17015.00
14th m 5% 17015.00 17866.00
15th m 5% 17866.00 18759.00
16th m 5% 18759.00 19697.00

Page 218 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
17th m 5% 19697.00 20682.00
18th m 5% 20682.00 21716.00
19th m 5% 21716.00 22802.00
20th m 5% 22802.00 23942.00
Total Cost from 10m upto 20m 184873.00 194117.00 16101.00 16907.00
Avg Rate per metre 18487.00 19412.00 14.82 14.82
16.13 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 24512.00 30640.00 32172.00
32nd 7.5% 26350.00 32938.00 34585.00
33rd m 7.5% 28326.00 35408.00 37178.00
34th m 7.5% 30450.00 38063.00 39966.00
35th m 7.5% 32734.00 40918.00 42964.00
36th m 7.5% 35189.00 43986.00 46185.00
37th m 7.5% 37828.00 47285.00 49649.00
38th m 7.5% 40665.00 50831.00 53373.00
39th m 7.5% 43715.00 54644.00 57376.00
40th m 7.5% 46994.00 58743.00 61680.00
Total Cost from 30m upto 40m 346763.00 433456.00 455128.00
Avg Rate per metre 34676.00 43346.00 45513.00
30203.00 37754.00 39641.00
14.81 14.81 14.81
16.13 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 51693.00 62032.00 65134.00
32nd 10% 56862.00 68234.00 71646.00
33rd m 10% 62548.00 75058.00 78811.00
34th m 10% 68803.00 82564.00 86692.00
35th m 10% 75683.00 90820.00 95361.00
36th m 10% 83251.00 99901.00 104896.00
37th m 10% 91576.00 109891.00 115386.00
38th m 10% 100734.00 120881.00 126925.00
39th m 10% 110807.00 132968.00 139616.00

Page 219 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
40th m 10% 121888.00 146266.00 153579.00
Total Cost from 30m upto 40m 823845.00 988615.00 1038046.00
Avg Rate per metre 82385.00 98862.00 103805.00
71757.00 86108.00 90414.00
14.81 14.81 14.81
16.13 Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 356.65 206.86 L-12
Sinker ( skilled ) day 4.00 356.65 1426.60 L-15
Sinking helper ( semi-skilled ) day 10.00 285.32 2853.20 L-14
Diver day 0.75 356.65 267.49 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1304.00 5868.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 284.00 1065.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 693.30
Add for dewatering @ of 5 per cent of (a+b), if 584.36
required
c) Overhead charges @ 10 % on (a+b) 1296.48
d) Contractor's profit @ 10 % on (a+b+c) 1426.13
Rate per metre = (a+b+c+d) 15687.41 11905.00
say 15687.00 31.77%
16.13 Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 7.00 120.00 840.00 M-104
Electric Detonators each 30.00 3.92 117.60 M-097/100
b) Labour
Mate day 1.60 356.65 570.64 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 18.00 244.56 4402.08 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
Diver day 0.50 356.65 178.33 L-07
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.

Page 220 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Hire & running charges of compressor with hour 2.00 284.00 568.00 P&M-063
pneumatic breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if 788.61
required.
Consumables in sinking @ 10 per cent of cost of 918.06
d) (b).
Overhead charges @ 10 % on (a+b+c) 1843.64
e) Contractor's profit @ 10 % on (a+b+c+d) 2028.00
Rate per metre = (a+b+c+d+e) 22308.01 16551.00
say 22308.00 34.78%
16.14 Sinking of 8 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is reck

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 8 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.18 356.65 64.20 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 3.00 285.32 855.96 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1304.00 5216.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 521.60
c) Overhead charges @ 10 % on (a+b) 719.27
d) Contractor's profit @ 10 % on (a+b+c) 791.20
Rate per metre = (a+b+c+d) 8703.21 7506.00
say 8703.00 15.95%
16.14 A Beyond 3m upto 10m depth
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.25 356.65 89.16 L-12
Sinker day 1.75 356.65 624.14 L-15
Sinking helper ( semi-skilled ) day 3.50 285.32 998.62 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1304.00 6520.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 652.00
c) Overhead charges @ 10 % on (a+b) 888.39
d) Contractor's profit @ 10 % on (a+b+c) 977.23
Rate per metre = (a+b+c+d) 10749.54 9337.00

Page 221 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 10750.00 15.13%
16.14 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 11287.00
12th m 5% 11851.00
13th m 5% 12444.00
14th m 5% 13066.00
15th m 5% 13719.00
16th m 5% 14405.00
17th m 5% 15125.00
18th m 5% 15881.00
19th m 5% 16675.00
20th m 5% 17509.00
Total Cost from 10m upto 20m 141962.00 12331.00
Avg Rate per metre 14196.00 15.12%
16.14 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 18822.00 22586.00


22nd m 7.5% 20234.00 24281.00
23rd m 7.5% 21752.00 26102.00
24th m 7.5% 23383.00 28060.00
25th m 7.5% 25137.00 30164.00
26th m 7.5% 27022.00 32426.00
27th m 7.5% 29049.00 34859.00
28th m 7.5% 31228.00 37474.00
29th m 7.5% 33570.00 40284.00
30th m 7.5% 36088.00 43306.00
Total Cost from 20m upto 30m 266285.00 319542.00 23130.00 27756.00
Avg Rate per metre 26629.00 31954.00 15.13 15.12
16.14 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 39697.00 47636.00


32nd 10% 43667.00 52400.00
33rd m 10% 48034.00 57641.00
34th m 10% 52837.00 63404.00
35th m 10% 58121.00 69745.00

Page 222 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
36th m 10% 63933.00 76720.00
37th m 10% 70326.00 84391.00
38th m 10% 77359.00 92831.00
39th m 10% 85095.00 102114.00
40th m 10% 93605.00 112326.00
Total Cost from 30m upto 40m 632674.00 759208.00 54952.00 65942.00
Avg Rate per metre 63267.00 75921.00 15.13 15.13

16.14 Clayey Soil ( 8m dia. Well )


Unit = Running Meter.
Taking output = 1 meter
Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 356.65 78.46 L-12
Sinker ( skilled ) day 2.00 356.65 713.30 L-15
Sinking helper ( semi-skilled ) hour 3.50 285.32 998.62 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1304.00 7172.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 717.20
c) Overhead charges @ 10 % on (a+b) 967.96
d) Contractor's profit @ 10 % on (a+b+c) 1064.75
Rate per metre = (a+b+c+d) 11712.30 10226.00
say 11712.00 14.53
16.14 B Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 356.65 114.13 L-12
Sinker day 2.50 356.65 891.63 L-15
Sinking helper ( semi-skilled ) day 4.50 285.32 1283.94 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.50 284.00 994.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 881.80
c) Overhead charges @ 10 % on (a+b) 1198.95
d) Contractor's profit @ 10 % on (a+b+c) 1318.84
Rate per metre = (a+b+c+d) 14507.29 12744.00
say 14507.00 13.83
16.14 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 223 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 15233.00 15995.00


12th m 5% 15995.00 16795.00
13th m 5% 16795.00 17635.00
14th m 5% 17635.00 18517.00
15th m 5% 18517.00 19443.00
16th m 5% 19443.00 20415.00
17th m 5% 20415.00 21436.00
18th m 5% 21436.00 22508.00
19th m 5% 22508.00 23633.00
20th m 5% 23633.00 24815.00
Total Cost from 10m upto 20m 191610.00 201192.00 16833.00 17674.00
Avg Rate per metre 19161.00 20119.00 13.83 13.83
16.14 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 25405.00 31756.00 33344.00
32nd 7.5% 27310.00 34138.00 35845.00
33rd m 7.5% 29358.00 36698.00 38533.00
34th m 7.5% 31560.00 39450.00 41423.00
35th m 7.5% 33927.00 42409.00 44529.00
36th m 7.5% 36472.00 45590.00 47870.00
37th m 7.5% 39207.00 49009.00 51459.00
38th m 7.5% 42148.00 52685.00 55319.00
39th m 7.5% 45309.00 56636.00 59468.00
40th m 7.5% 48707.00 60884.00 63928.00
Total Cost from 30m upto 40m 359403.00 449255.00 471718.00
Avg Rate per metre 35940.00 44926.00 47172.00
31574.00 39467.00 41441.00
13.83 13.83 13.83
16.14 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Page 224 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 53578.00 64294.00 67509.00
32nd 10% 58936.00 70723.00 74259.00
33rd m 10% 64830.00 77796.00 81686.00
34th m 10% 71313.00 85576.00 89855.00
35th m 10% 78444.00 94133.00 98840.00
36th m 10% 86288.00 103546.00 108723.00
37th m 10% 94917.00 113900.00 119595.00
38th m 10% 104409.00 125291.00 131556.00
39th m 10% 114850.00 137820.00 144711.00
40th m 10% 126335.00 151602.00 159182.00
Total Cost from 30m upto 40m 853900.00 1024681.00 1075916.00
Avg Rate per metre 85390.00 102468.00 107592.00
75013.00 90015.00 94516.00
13.83% 13.83% 13.83%
16.14 Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 356.65 242.52 L-12
Sinker ( skilled ) day 4.00 356.65 1426.60 L-15
Sinking helper ( semi-skilled ) day 12.00 285.32 3423.84 L-14
Diver day 1.00 356.65 356.65 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1304.00 6520.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 284.00 1065.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 758.50
Add for dewatering @ of 5 per cent of (a+b), if 689.66
required
c) Overhead charges @ 10 % on (a+b) 1448.28
d) Contractor's profit @ 10 % on (a+b+c) 1593.10
Rate per metre = (a+b+c+d) 17524.15 13195.00
say 17524.00 32.81%
16.14 Hard Rock ( 8m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour

Page 225 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Material
Gelatine 80 per cent Kg 8.00 120.00 960.00 M-104
Electric Detonators each 32.00 3.92 125.44 M-097/100
b) Labour
Mate day 1.09 356.65 388.75 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 20.00 244.56 4891.20 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 2.00 284.00 568.00 P&M-063
pneumatic breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if 795.05
required.
Consumables in sinking @ 10 per cent of cost of 750.90
d) (b).
Overhead charges @ 10 % on (a+b+c) 1853.24
e) Contractor's profit @ 10 % on (a+b+c+d) 2038.56
Rate per metre = (a+b+c+d+e) 22424.21 16053.00
say 22424.00 39.69%
16.15 Sinking of 9 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is reck

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 9 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.19 356.65 67.76 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 3.25 285.32 927.29 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1304.00 5216.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 521.60
c) Overhead charges @ 10 % on (a+b) 726.76
d) Contractor's profit @ 10 % on (a+b+c) 799.44
Rate per metre = (a+b+c+d) 8793.83 7541.00
say 8794.00 16.62%
16.15 A Beyond 3m upto 10m depth

Page 226 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.27 356.65 96.30 L-12
Sinker day 1.75 356.65 624.14 L-15
Sinking helper ( semi-skilled ) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1304.00 7172.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 717.20
c) Overhead charges @ 10 % on (a+b) 975.09
d) Contractor's profit @ 10 % on (a+b+c) 1072.60
Rate per metre = (a+b+c+d) 11798.60 10266.00
say 11799.00 14.93%
16.15 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12389.00
12th m 5% 13008.00
13th m 5% 13658.00
14th m 5% 14341.00
15th m 5% 15058.00
16th m 5% 15811.00
17th m 5% 16602.00
18th m 5% 17432.00
19th m 5% 18304.00
20th m 5% 19219.00
Total Cost from 10m upto 20m 155822.00 13559.00
Avg Rate per metre 15582.00 14.92%
16.15 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 20660.43 24793.00


22nd m 7.5% 22210.00 26652.00
23rd m 7.5% 23876.00 28651.00
24th m 7.5% 25667.00 30800.00
25th m 7.5% 27592.00 33110.00
26th m 7.5% 29661.00 35593.00
27th m 7.5% 31886.00 38263.00
28th m 7.5% 34277.00 41132.00
29th m 7.5% 36848.00 44218.00
30th m 7.5% 39612.00 47534.00
Total Cost from 20m upto 30m 292289.43 350746.00 25430.00 30516.00

Page 227 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Avg Rate per metre 29229.00 35075.00 14.94% 14.94%
16.15 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 43573.20 52288.00


32nd 10% 47931.00 57517.00
33rd m 10% 52724.00 63269.00
34th m 10% 57996.00 69595.00
35th m 10% 63796.00 76555.00
36th m 10% 70176.00 84211.00
37th m 10% 77194.00 92633.00
38th m 10% 84913.00 101896.00
39th m 10% 93404.00 112085.00
40th m 10% 102744.00 123293.00
Total Cost from 30m upto 40m 694451.20 833342.00 60417.00 72501.00
Avg Rate per metre 69445.00 83334.00 14.94% 14.94%
16.15 Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 356.65 85.60 L-12
Sinker ( skilled ) day 2.25 356.65 802.46 L-15
Sinking helper ( semi-skilled ) day 3.75 285.32 1069.95 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1304.00 7498.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 749.80
c) Overhead charges @ 10 % on (a+b) 1020.58
d) Contractor's profit @ 10 % on (a+b+c) 1122.64
Rate per metre = (a+b+c+d) 12349.03 10726.00
say 12349.00 15.13%
16.15 B Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 356.65 121.26 L-12
Sinker day 2.50 356.65 891.63 L-15
Sinking helper ( semi-skilled ) day 5.00 285.32 1426.60 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1304.00 8476.00 P&M-075
0.75 cum capacity and accessories.

Page 228 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Air compressor with pneumatic chisel attachment for hour 3.75 284.00 1065.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 954.10
c) Overhead charges @ 10 % on (a+b) 1293.46
d) Contractor's profit @ 10 % on (a+b+c) 1422.80
Rate per metre = (a+b+c+d) 15650.85 13777.00
say 15651.00 13.60%
16.15 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 16434.00 17256.00


12th m 5% 17256.00 18119.00
13th m 5% 18119.00 19025.00
14th m 5% 19025.00 19976.00
15th m 5% 19976.00 20975.00
16th m 5% 20975.00 22024.00
17th m 5% 22024.00 23125.00
18th m 5% 23125.00 24281.00
19th m 5% 24281.00 25495.00
20th m 5% 25495.00 26770.00
Total Cost from 10m upto 20m 206710.00 217046.00 18194.00 19104.00
Avg Rate per metre 20671.00 21705.00 13.61% 13.61%
16.15 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 27407.00 34259.00 35972.00
32nd 7.5% 29463.00 36829.00 38670.00
33rd m 7.5% 31673.00 39591.00 41571.00
34th m 7.5% 34048.00 42560.00 44688.00
35th m 7.5% 36602.00 45753.00 48041.00
36th m 7.5% 39347.00 49184.00 51643.00
37th m 7.5% 42298.00 52873.00 55517.00
38th m 7.5% 45470.00 56838.00 59680.00
39th m 7.5% 48880.00 61100.00 64155.00
40th m 7.5% 52546.00 65683.00 68967.00

Page 229 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Total Cost from 30m upto 40m 387734.00 484670.00 508904.00
Avg Rate per metre 38773.00 48467.00 50890.00
34127.00 42659.00 44792.00
13.61% 13.61% 13.61%
16.15 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 57801.00 69361.00 72829.00
32nd 10% 63581.00 76297.00 80112.00
33rd m 10% 69939.00 83927.00 88123.00
34th m 10% 76933.00 92320.00 96936.00
35th m 10% 84626.00 101551.00 106629.00
36th m 10% 93089.00 111707.00 117292.00
37th m 10% 102398.00 122878.00 129022.00
38th m 10% 112638.00 135166.00 141924.00
39th m 10% 123902.00 148682.00 156116.00
40th m 10% 136292.00 163550.00 171728.00
Total Cost from 30m upto 40m 921199.00 1105439.00 1160711.00
Avg Rate per metre 92120.00 110544.00 116071.00
81083.00 97299.00 102165.00
13.61% 13.61% 13.61%
16.15 Soft Rock ( 9m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.76 356.65 271.05 L-12
Sinker ( skilled ) day 4.00 356.65 1426.60 L-15
Sinking helper ( semi-skilled ) day 14.00 285.32 3994.48 L-14
Diver day 1.20 356.65 427.98 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1304.00 8476.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 284.00 1136.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 961.20
Add for dewatering @ of 5 per cent of (a+b), if 834.67
required
c) Overhead charges @ 10 % on (a+b) 1752.80
d) Contractor's profit @ 10 % on (a+b+c) 1928.08

Page 230 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per metre = (a+b+c+d) 21208.86 17121.00
say 21209.00 23.88%
16.15 Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 120.00 1200.00 M-104
Electric Detonators each 40.00 3.92 156.80 M-097/100
b) Labour
Mate day 1.17 356.65 417.28 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 22.00 244.56 5380.32 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
Diver day 1.00 356.65 356.65 L-07
c) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1304.00 9128.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 2.50 284.00 710.00 P&M-063
pneumatic breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if 911.07
required.
Consumables in sinking @ 10 per cent of cost of 838.33
d) (b).
Overhead charges @ 10 % on (a+b+c) 2132.75
e) Contractor's profit @ 10 % on (a+b+c+d) 2346.03
Rate per metre = (a+b+c+d+e) 25806.29 18731.00
say 25806.00 37.77%
16.16 Sinking of 10 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is rec

Unit = Running Meter


Taking output = 1 m
Diameter of well - 10 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.20 356.65 71.33 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper ( semi-skilled ) day 3.50 285.32 998.62 L-14
b) Machinery

Page 231 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Hire & running charges of crane with grab bucket of hour 5.00 1304.00 6520.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 652.00
c) Overhead charges @ 10 % on (a+b) 877.69
d) Contractor's profit @ 10 % on (a+b+c) 965.46
Rate per metre = (a+b+c+d) 10620.08 9295.00
say 10620.00 14.25%
16.16 A Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.31 356.65 110.56 L-12
Sinker day 2.00 356.65 713.30 L-15
Sinking helper ( semi-skilled ) day 4.25 285.32 1212.61 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1304.00 7498.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 749.80
c) Overhead charges @ 10 % on (a+b) 1028.43
d) Contractor's profit @ 10 % on (a+b+c) 1131.27
Rate per metre = (a+b+c+d) 12443.97 10769.00
say 12444.00 15.55%
16.16 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 13066.00
12th m 5% 13719.00
13th m 5% 14405.00
14th m 5% 15125.00
15th m 5% 15881.00
16th m 5% 16675.00
17th m 5% 17509.00
18th m 5% 18384.00
19th m 5% 19303.00
20th m 5% 20268.00
Total Cost from 10m upto 20m 164335.00 14223.00
Avg Rate per metre 16434.00 15.55%
16.16 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 21788.00 26146.00


22nd m 7.5% 23422.00 28106.00
23rd m 7.5% 25179.00 30215.00

Page 232 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
24th m 7.5% 27067.00 32480.00
25th m 7.5% 29097.00 34916.00
26th m 7.5% 31279.00 37535.00
27th m 7.5% 33625.00 40350.00
28th m 7.5% 36147.00 43376.00
29th m 7.5% 38858.00 46630.00
30th m 7.5% 41772.00 50126.00
Total Cost from 20m upto 30m 308234.00 369880.00 26678.00 32014.00
Avg Rate per metre 30823.00 36988.00 15.54% 15.54%
16.16 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 45949.00 55139.00


32nd 10% 50544.00 60653.00
33rd m 10% 55598.00 66718.00
34th m 10% 61158.00 73390.00
35th m 10% 67274.00 80729.00
36th m 10% 74001.00 88801.00
37th m 10% 81401.00 97681.00
38th m 10% 89541.00 107449.00
39th m 10% 98495.00 118194.00
40th m 10% 108345.00 130014.00
Total Cost from 30m upto 40m 732306.00 878768.00 63382.00 76059.00
Avg Rate per metre 73231.00 87877.00 15.54% 15.54%
16.16 Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 356.65 89.16 L-12
Sinker ( skilled ) day 2.50 356.65 891.63 L-15
Sinking helper ( semi-skilled ) day 5.50 285.32 1569.26 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 782.40
c) Overhead charges @ 10 % on (a+b) 1115.64
d) Contractor's profit @ 10 % on (a+b+c) 1227.21
Rate per metre = (a+b+c+d) 13499.30 11420.00
say 13499.00 18.20%

Page 233 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.16 B Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 356.65 142.66 L-12
Sinker day 3.00 356.65 1069.95 L-15
Sinking helper ( semi-skilled ) day 5.50 285.32 1569.26 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.00 284.00 1136.00 P&M-063
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 896.00
c) Overhead charges @ 10 % on (a+b) 1263.79
d) Contractor's profit @ 10 % on (a+b+c) 1390.17
Rate per metre = (a+b+c+d) 15291.82 13162.00
say 15292.00 16.18%
16.16 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 16056.00 16859.00


12th m 5% 16859.00 17702.00
13th m 5% 17702.00 18587.00
14th m 5% 18587.00 19516.00
15th m 5% 19516.00 20492.00
16th m 5% 20492.00 21517.00
17th m 5% 21517.00 22593.00
18th m 5% 22593.00 23723.00
19th m 5% 23723.00 24909.00
20th m 5% 24909.00 26154.00
Total Cost from 10m upto 20m 201954.00 212052.00 17383.00 18252.00
Avg Rate per metre 20195.00 21205.00 16.18% 16.18%
16.16 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 26777.00 33471.00 35145.00
32nd 7.5% 28785.00 35981.00 37780.00

Page 234 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
33rd m 7.5% 30944.00 38680.00 40614.00
34th m 7.5% 33265.00 41581.00 43660.00
35th m 7.5% 35760.00 44700.00 46935.00
36th m 7.5% 38442.00 48053.00 50456.00
37th m 7.5% 41325.00 51656.00 54239.00
38th m 7.5% 44424.00 55530.00 58307.00
39th m 7.5% 47756.00 59695.00 62680.00
40th m 7.5% 51338.00 64173.00 67382.00
Total Cost from 30m upto 40m 378816.00 473520.00 497198.00
Avg Rate per metre 37882.00 47352.00 49720.00
Previous SOR Rate 32607.00 40759.00 42797.00
% variation 16.18% 16.18% 16.18%
16.16 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 56472.00 67766.00 71154.00
32nd 10% 62119.00 74543.00 78270.00
33rd m 10% 68331.00 81997.00 86096.85
34th m 10% 75164.00 90197.00 94706.85
35th m 10% 82680.00 99216.00 104176.80
36th m 10% 90948.00 109138.00 114594.90
37th m 10% 100043.00 120052.00 126054.60
38th m 10% 110047.00 132056.00 138658.80
39th m 10% 121052.00 145262.00 152525.10
40th m 10% 133157.00 159788.00 167777.40
Total Cost from 30m upto 40m 900013.00 1080015.00 1134015.30
Avg Rate per metre 90001.00 108002.00 113402.00
Previous SOR Rate 77474.00 97614.00 92965.00
% variation 16.17% 10.64% 21.98%
16.16 Soft Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 356.65 306.72 L-12
Sinker ( skilled ) day 4.00 356.65 1426.60 L-15
Sinking helper ( semi-skilled ) day 16.00 285.32 4565.12 L-14
Diver day 1.40 356.65 499.31 L-07

Page 235 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1304.00 9128.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 284.00 1207.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 1033.50
Add for dewatering @ 5 per cent of cost, if required 568.43
c) Overhead charges @ 10 % on (a+b) 1873.47
d) Contractor's profit @ 10 % on (a+b+c) 2060.81
Rate per metre = (a+b+c+d) 22668.96 17535.00
say 22669.00 29.28%
16.16 Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 120.00 1320.00 M-104
Electric Detonators each. 44.00 3.92 172.48 M-097/100
b) Labour
Mate day 1.27 356.65 452.95 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 24.00 244.56 5869.44 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 8.50 1304.00 11084.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 3.00 284.00 852.00 P&M-063
pneumatic breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 596.80
Consumables in sinking @ 10 per cent of cost of 2108.42
(b+c).
d) Overhead charges @ 10 % on (a+b+c) 2468.52
e) Contractor's profit @ 10 % on (a+b+c+d) 2715.37
Rate per metre = (a+b+c+d+e) 29869.03 22931.00
say 29869.00 30.26%
16.17 Sinking of 11 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is rec

Unit = Running Meter


Taking output = 0.50 m
Diameter of well - 11 m.
Sandy Soil

Page 236 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.21 356.65 74.90 L-12
Sinker ( skilled ) day 1.50 356.65 534.98 L-15
Sinking helper (semi-skilled) day 3.30 285.32 941.56 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 782.40
d) Overhead charges @ 10 % on (a+b+c) 1015.78
e) Contractor's profit @ 10 % on (a+b+c+d) 1117.36
Cost for 0.5m = a+b+c+d 12290.97
Rate per metre = (a+b+c+d)/0.50 24581.94 21983.00
say 24582.00 11.82%
16.17 A Beyond 3m upto 10m depth
Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.32 356.65 114.13 L-12
Sinker day 2.00 356.65 713.30 L-15
Sinking helper (semi-skilled) day 4.50 285.32 1283.94 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1304.00 5216.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 521.60
c) Overhead charges @ 10 % on (a+b+c) 784.90
d) Contractor's profit @ 10 % on (a+b+c+d) 863.39
Cost for 0.5m = a+b+c+d 9497.25
Rate per metre = (a+b+c+d)/0.50 18994.50 15585.00
say 18995.00 21.88%
16.17 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 19944.00
12th m 5% 20941.00
13th m 5% 21988.00
14th m 5% 23087.00
15th m 5% 24241.00
16th m 5% 25453.00
17th m 5% 26726.00
18th m 5% 28062.00
19th m 5% 29465.00
20th m 5% 30938.00
Total Cost from 10m upto 20m 250845.00 20583.00

Page 237 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Avg Rate per metre 25085.00 21.87%
16.17 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 33258.00 39910.00


22nd m 7.5% 35752.00 42902.00
23rd m 7.5% 38433.00 46120.00
24th m 7.5% 41315.00 49578.00
25th m 7.5% 44414.00 53297.00
26th m 7.5% 47745.00 57294.00
27th m 7.5% 51326.00 61591.00
28th m 7.5% 55175.00 66210.00
29th m 7.5% 59313.00 71176.00
30th m 7.5% 63761.00 76513.00
Total Cost from 20m upto 30m 470492.00 564591.00 38608.00 46330.00
Avg Rate per metre 47049.00 56459.00 21.86% 21.86%
16.17 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 70137.00 84164.00


32nd 10% 77151.00 92581.00
33rd m 10% 84866.00 101839.00
34th m 10% 93353.00 112024.00
35th m 10% 102688.00 123226.00
36th m 10% 112957.00 135548.00
37th m 10% 124253.00 149104.00
38th m 10% 136678.00 164014.00
39th m 10% 150346.00 180415.00
40th m 10% 165381.00 198457.00
Total Cost from 30m upto 40m 1117810.00 1341372.00 91725.00 110071.00
Avg Rate per metre 111781.00 134137.00 21.87% 21.86%
16.17 Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate day 0.26 356.65 92.73 L-12
Sinker ( skilled ) day 2.50 356.65 891.63 L-15

Page 238 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Sinking helper (semi-skilled) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1304.00 6520.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 652.00
c) Overhead charges @ 10 % on (a+b) 929.76
d) Contractor's profit @ 10 % on (a+b+c) 1022.74
Cost for 0.5m = a+b+c+d 11250.14
Rate per metre = (a+b+c+d)/0.50 22500.27 19011.00
say 22500.00 18.35%
16.17 B Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 356.65 153.36 L-12
Sinker day 3.50 356.65 1248.28 L-15
Sinking helper (semi-skilled) day 5.75 285.32 1640.59 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.25 284.00 1207.00 P&M-063
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 903.10
c) Overhead charges @ 10 % on (a+b) 1297.63
d) Contractor's profit @ 10 % on (a+b+c) 1427.40
Cost for 0.5m = a+b+c+d 15701.35
Rate per metre = (a+b+c+d)/0.50 31402.71 26740.00
say 31403.00 17.44%
16.17 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 32973.00 34622.00


12th m 5% 34622.00 36353.00
13th m 5% 36353.00 38171.00
14th m 5% 38171.00 40080.00
15th m 5% 40080.00 42084.00
16th m 5% 42084.00 44188.00
17th m 5% 44188.00 46397.00
18th m 5% 46397.00 48717.00
19th m 5% 48717.00 51153.00
20th m 5% 51153.00 53711.00

Page 239 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Total Cost from 10m upto 20m 414738.00 435475.00 35315.00 37081.00
Avg Rate per metre 41474.00 43548.00 17.44% 17.44%
16.17 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 54989.00 68736.00 72173.00
32nd 7.5% 59113.00 73891.00 77586.00
33rd m 7.5% 63546.00 79433.00 83405.00
34th m 7.5% 68312.00 85390.00 89660.00
35th m 7.5% 73435.00 91794.00 96384.00
36th m 7.5% 78943.00 98679.00 103613.00
37th m 7.5% 84864.00 106080.00 111384.00
38th m 7.5% 91229.00 114036.00 119738.00
39th m 7.5% 98071.00 122589.00 128718.00
40th m 7.5% 105426.00 131783.00 138372.00
Total Cost from 30m upto 40m 777928.00 972411.00 1021032.00
Avg Rate per metre 77793.00 97241.00 102103.00
Previous SOR Rate 66242.00 82802.00 86942.00
% variation 17.44% 17.44% 17.44%
16.17 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 115969.00 139163.00 146121.00
32nd 10% 127566.00 153079.00 160733.00
33rd m 10% 140323.00 168388.00 176807.00
34th m 10% 154355.00 185226.00 194487.00
35th m 10% 169791.00 203749.00 213936.00
36th m 10% 186770.00 224124.00 235330.00
37th m 10% 205447.00 246536.00 258863.00
38th m 10% 225992.00 271190.00 284750.00
39th m 10% 248591.00 298309.00 313224.00
40th m 10% 273450.00 328140.00 344547.00
Total Cost from 30m upto 40m 1848254 2217904 2328798
Avg Rate per metre 184825.00 221790.00 232880.00
Previous SOR Rate 157381.00 188857.00 198300.00

Page 240 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
% variation 17.44% 17.44% 17.44%
16.17 Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 356.65 338.82 L-12
Sinker ( skilled ) day 4.25 356.65 1515.76 L-15
Sinking helper (semi-skilled) day 18.00 285.32 5135.76 L-14
Diver day 1.50 356.65 534.98 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.00 1304.00 10432.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 284.00 1278.00 P&M-063
Consumables in sinking @ 10 per cent of (b) 1171.00
Add for dewatering @ 5 per cent of cost, if required 644.05
c) Overhead charges @ 10 % on (a+b) 2105.04
d) Contractor's profit @ 10 % on (a+b+c) 2315.54
Cost for 0.5m = a+b+c+d 25470.94
Rate per metre = (a+b+c+d)/0.50 50941.88 39560.00
say 50942.00 28.77%
16.17 Hard Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 120.00 1440.00 M-104
Electric Detonators each. 48.00 3.92 188.16 M-097/100
b) Labour
Mate day 1.35 356.65 481.48 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 26.00 244.56 6358.56 L-13
Mazdoor (Skilled) day 4.00 356.65 1426.60 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1304.00 13040.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 3.50 284.00 994.00 P&M-063
pneumatic breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 701.70
Consumables in sinking @ 10 per cent of cost of 2310.31
(b+c).

Page 241 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Overhead charges @ 10 % on (a+b+c) 2774.33
e) Contractor's profit @ 10 % on (a+b+c+d) 3051.76
Cost for 0.5m = a+b+c+d 33569.36
Rate per metre = (a+b+c+d)/0.50 67138.71 52440.00
say 67139.00 28.03%
16.18 Sinking of 12 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is rec

Unit = Running Meter


Taking output = 0.25 m
Diameter of well - 12 m.
Sandy Soil
I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.22 356.65 78.46 L-12
Sinker ( skilled ) day 1.75 356.65 624.14 L-15
Sinking helper (semi-skilled) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1304.00 7824.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 782.40
c) Overhead charges @ 10 % on (a+b) 1045.03
d) Contractor's profit @ 10 % on (a+b+c) 1149.53
Cost for 0.25m = a+b+c+d 12644.84
Rate per metre = (a+b+c+d)/0.25 50579.36 44473.00
say 50579.00 13.73%
16.18 A Beyond 3m upto 10m depth
Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.37 356.65 131.96 L-12
Sinker day 2.50 356.65 891.63 L-15
Sinking helper (semi-skilled) day 4.75 285.32 1355.27 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1304.00 8476.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 847.60
c) Overhead charges @ 10 % on (a+b) 1170.25
d) Contractor's profit @ 10 % on (a+b+c) 1287.27
Cost for 0.25m = a+b+c+d 14159.97
Rate per metre = (a+b+c+d)/0.25 56639.88 48810.00
say 56640.00 16.04%

Page 242 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.18 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 59472.00
12th m 5% 62446.00
13th m 5% 65568.30
14th m 5% 68846.72
15th m 5% 72289.05
16th m 5% 75903.50
17th m 5% 79698.68
18th m 5% 83683.61
19th m 5% 87867.79
20th m 5% 92261.18
Total Cost from 10m upto 20m 748036.84 64463.00
Avg Rate per metre 74804.00 16.04%
16.18 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 99181.00 119017.00


22nd m 7.5% 106620.00 127944.00
23rd m 7.5% 114617.00 137540.00
24th m 7.5% 123213.00 147856.00
25th m 7.5% 132454.00 158945.00
26th m 7.5% 142388.00 170866.00
27th m 7.5% 153067.00 183680.00
28th m 7.5% 164547.00 197456.00
29th m 7.5% 176888.00 212266.00
30th m 7.5% 190155.00 228186.00
Total Cost from 20m upto 30m 1403130.00 1683756.00 120917.00 145100.00
Avg Rate per metre 140313.00 168376.00 16.04% 16.04%
16.18 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 209171.00 251005.00


32nd 10% 230088.00 276106.00
33rd m 10% 253097.00 303716.00
34th m 10% 278407.00 334088.00
35th m 10% 306248.00 367498.00
36th m 10% 336873.00 404248.00

Page 243 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
37th m 10% 370560.00 444672.00
38th m 10% 407616.00 489139.00
39th m 10% 448378.00 538054.00
40th m 10% 493216.00 591859.00
Total Cost from 30m upto 40m 3333654 4000385 287281.00 344738.00
Avg Rate per metre 333365.00 400039.00 16.04% 16.04%
16.18 Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate day 0.30 356.65 107.00 L-12
Sinker ( skilled ) day 3.00 356.65 1069.95 L-15
Sinking helper (semi-skilled) day 4.50 285.32 1283.94 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1304.00 8150.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 815.00
c) Overhead charges @ 10 % on (a+b) 1142.59
d) Contractor's profit @ 10 % on (a+b+c) 1256.85
Cost for 0.25m = a+b+c+d 13825.32
Rate per metre = (a+b+c+d)/0.25 55301.28 47181.00
say 55301.00 17.21%
16.18 B Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 356.65 171.19 L-12
Sinker day 3.75 356.65 1337.44 L-15
Sinking helper (semi-skilled) day 6.00 285.32 1711.92 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1304.00 10862.32 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 284.00 1278.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1214.03
c) Overhead charges @ 10 % on (a+b) 1657.49
d) Contractor's profit @ 10 % on (a+b+c) 1823.24
Cost for 0.25m = a+b+c+d 20055.63
Rate per metre = (a+b+c+d)/0.25 80222.52 70226.00
say 80223.00 14.24%
16.18 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 244 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 84234.00 88446.00


12th m 5% 88446.00 92868.00
13th m 5% 92868.00 97511.00
14th m 5% 97511.00 102387.00
15th m 5% 102387.00 107506.00
16th m 5% 107506.00 112881.00
17th m 5% 112881.00 118525.00
18th m 5% 118525.00 124451.00
19th m 5% 124451.00 130674.00
20th m 5% 130674.00 137208.00
Total Cost from 10m upto 20m 1059483.00 1112457.00 92747.00 97384.00
Avg Rate per metre 105948.00 111246.00 14.23% 14.23%
16.18 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 140475.00 175594.00 184374.00
32nd 7.5% 151011.00 188764.00 198202.00
33rd m 7.5% 162337.00 202921.00 213067.00
34th m 7.5% 174512.00 218140.00 229047.00
35th m 7.5% 187600.00 234500.00 246225.00
36th m 7.5% 201670.00 252088.00 264692.00
37th m 7.5% 216795.00 270994.00 284544.00
38th m 7.5% 233055.00 291319.00 305885.00
39th m 7.5% 250534.00 313168.00 328826.00
40th m 7.5% 269324.00 336655.00 353488.00
Total Cost from 30m upto 40m 1987313 2484143 2608350
Avg Rate per metre 198731.00 248414.00 260835.00
Previous SOR Rate 173969.00 217462.00 228335.00
% variation 14.23% 14.23% 14.23%
16.18 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Page 245 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 296256.00 355507.00 373282.00
32nd 10% 325882.00 391058.00 410611.00
33rd m 10% 358470.00 430164.00 451672.00
34th m 10% 394317.00 473180.00 496839.00
35th m 10% 433749.00 520499.00 546524.00
36th m 10% 477124.00 572549.00 601176.00
37th m 10% 524836.00 629803.00 661293.00
38th m 10% 577320.00 692784.00 727423.00
39th m 10% 635052.00 762062.00 800165.00
40th m 10% 698557.00 838268.00 880181.00
Total Cost from 30m upto 40m 4721563 5665874 5949166
Avg Rate per metre 472156.00 566587.00 594917.00
Previous SOR Rate 413328.00 495994.00 520794.00
% variation 14.23% 14.23% 14.23%
16.18 Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate day 1.06 356.65 378.05 L-12
Sinker ( skilled ) day 4.50 356.65 1604.93 L-15
Sinking helper (semi-skilled) day 20.00 285.32 5706.40 L-14
Diver day 1.75 356.65 624.14 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1304.00 13040.00 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.75 284.00 1349.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1438.90
Add for dewatering @ 5 per cent, if required 791.40
c) Overhead charges @ 10 % on (a+b) 2493.28
d) Contractor's profit @ 10 % on (a+b+c) 2742.61
Cost for 0.25m = a+b+c+d 30168.70
Rate per metre = (a+b+c+d)/0.25 120674.78 95456.00
say 120675.00 26.42%
16.18 Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in hard rock strata upto 3 m

Page 246 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent Kg 14.00 120.00 1680.00 M-104
Electric detonator each. 56.00 3.92 219.52 M-097/100
b) Labour
Mate day 1.44 356.65 513.58 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 28.00 244.56 6847.68 L-13
Mazdoor (Skilled) day 4.50 356.65 1604.93 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 12.50 1304.00 16300.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 4.00 284.00 1136.00 P&M-063
pneumatic breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 871.80
Consumables in sinking @ 10 per cent of (c). 1830.78
d) Overhead charges @ 10 % on (a+b+c) 3180.67
e) Contractor's profit @ 10 % on (a+b+c+d) 3498.74
Cost for 0.25m = a+b+c+d+e 38486.16
Rate per metre = (a+b+c+d+e)/0.25 153944.64 124920.00
say 153945.00 23.23%
16.19 Sinking of Twin D Type well (other than pneumatic
method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from be

Unit = Running Meter


Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
Sandy Soil
Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.20 356.65 71.33 L-12
Sinker ( skilled ) day 1.25 356.65 445.81 L-15
Sinking helper (semi-skilled) day 3.75 285.32 1069.95 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1304.00 7172.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 717.20
c) Overhead charges @ 10 % on (a+b) 947.63

Page 247 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Contractor's profit @ 10 % on (a+b+c) 1042.39
Rate per metre = (a+b+c+d) 11466.31 10155.00
say 11466.00 12.91%
16.19 A Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.30 356.65 107.00 L-12
Sinker day 1.50 356.65 534.98 L-15
Sinking helper (semi-skilled) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 5.88 1304.00 7667.52 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 766.75
c) Overhead charges @ 10 % on (a+b) 1021.75
d) Contractor's profit @ 10 % on (a+b+c) 1123.93
Rate per metre = (a+b+c+d) 12363.20 10891.00
say 12363.00 13.52%
16.19 A Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12981.00
12th m 5% 13630.00
13th m 5% 14312.00
14th m 5% 15028.00
15th m 5% 15779.00
16th m 5% 16568.00
17th m 5% 17396.00
18th m 5% 18266.00
19th m 5% 19179.00
20th m 5% 20138.00
Total Cost from 10m upto 20m 163277.00 14384.00
Avg Rate per metre 16328.00 13.52%
16.19 A Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement and Labour. for Kentledge

21st m 7.5% 21648.00 25978.00


22nd m 7.5% 23272.00 27926.00
23rd m 7.5% 25017.00 30020.00
24th m 7.5% 26893.00 32272.00
25th m 7.5% 28910.00 34692.00
26th m 7.5% 31078.00 37294.00
27th m 7.5% 33409.00 40091.00

Page 248 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
28th m 7.5% 35915.00 43098.00
29th m 7.5% 38609.00 46331.00
30th m 7.5% 41505.00 49806.00
Total Cost from 20m upto 30m 306256.00 367508.00 26981.00 32378.00
Avg Rate per metre 30626.00 36751.00 13.51% 13.51%
16.19 A Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports, Including 20%
loading arrangement, and Labour etc. for Kentledge

31st m 10% 45656.00 54787.00


32nd 10% 50222.00 60266.00
33rd m 10% 55244.00 66293.00
34th m 10% 60768.00 72922.00
35th m 10% 66845.00 80214.00
36th m 10% 73530.00 88236.00
37th m 10% 80883.00 97060.00
38th m 10% 88971.00 106765.00
39th m 10% 97868.00 117442.00
40th m 10% 107655.00 129186.00
Total Cost from 30m upto 40m 727642.00 873171.00 64105.00 76927.00
Avg Rate per metre 72764.00 87317.00 13.51% 13.51%
16.19 Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 356.65 92.73 L-12
Sinker ( skilled ) day 2.50 356.65 891.63 L-15
Sinking helper (semi-skilled) day 4.00 285.32 1141.28 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1304.00 8150.00 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 815.00
c) Overhead charges @ 10 % on (a+b) 1109.06
d) Contractor's profit @ 10 % on (a+b+c) 1219.97
Rate per metre = (a+b+c+d) 13419.67 11656.00
say 13420.00 15.13%
16.19 B Beyond 3m upto 10m depth
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 356.65 160.49 L-12

Page 249 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Sinker day 3.25 356.65 1159.11 L-15
Sinking helper (semi-skilled) day 6.00 285.32 1711.92 L-14
b) Machinery
Hire & running charges of crane with grab bucket of hour 6.67 1304.00 8697.68 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 284.00 1278.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 997.57
c) Overhead charges @ 10 % on (a+b) 1400.48
d) Contractor's profit @ 10 % on (a+b+c) 1540.53
Rate per metre = (a+b+c+d) 16945.78 14628.00
say 16946.00 15.85%
16.19 B Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required. Including for
dewatering @
5% of cost, if
required

11th m 5% 17793.00 18683.00


12th m 5% 18683.00 19617.00
13th m 5% 19617.00 20598.00
14th m 5% 20598.00 21628.00
15th m 5% 21628.00 22709.00
16th m 5% 22709.00 23844.00
17th m 5% 23844.00 25036.00
18th m 5% 25036.00 26288.00
19th m 5% 26288.00 27602.00
20th m 5% 27602.00 28982.00
Total Cost from 10m upto 20m 223798.00 234987.00 19320.00 20286.00
Avg Rate per metre 22380.00 23499.00 15.84% 15.84%
16.19 B Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports, Including 25% Including 5%
loading arrangement and Labour ). for Kentledge for
dewatering, if
required
31st m 7.5% 29672.00 37090.00 38945.00
32nd 7.5% 31897.00 39871.00 41865.00
33rd m 7.5% 34289.00 42861.00 45004.00
34th m 7.5% 36861.00 46076.00 48380.00
35th m 7.5% 39626.00 49533.00 52010.00
36th m 7.5% 42598.00 53248.00 55910.00

Page 250 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
37th m 7.5% 45793.00 57241.00 60103.00
38th m 7.5% 49227.00 61534.00 64611.00
39th m 7.5% 52919.00 66149.00 69456.00
40th m 7.5% 56888.00 71110.00 74666.00
Total Cost from 30m upto 40m 419770.00 524713.00 550950.00
Avg Rate per metre 41977.00 52471.00 55095.00
Previous SOR Rate 36239.00 45299.00 47563.00
% variation 15.83% 15.83% 15.84%
16.19 B Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, Including 20% Including 5%
loading arrangement and Labour). for Kentledge for
dewatering, if
required
31st m 10% 62577.00 75092.00 78847.00
32nd 10% 68835.00 82602.00 86732.00
33rd m 10% 75719.00 90863.00 95406.00
34th m 10% 83291.00 99949.00 104946.00
35th m 10% 91620.00 109944.00 115441.00
36th m 10% 100782.00 120938.00 126985.00
37th m 10% 110860.00 133032.00 139684.00
38th m 10% 121946.00 146335.00 153652.00
39th m 10% 134141.00 160969.00 169017.00
40th m 10% 147555.00 177066.00 185919.00
Total Cost from 30m upto 40m 997326.00 1196790.00 1256629.00
Avg Rate per metre 99733.00 119679.00 125663.00
Previous SOR Rate 86096.00 103315.00 108481.00
% variation 15.84% 15.84% 15.84%
16.19 Soft Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 356.65 306.72 L-12
Sinker ( skilled ) day 4.50 356.65 1604.93 L-15
Sinking helper (semi-skilled) day 15.00 285.32 4279.80 L-14
Diver day 1.50 356.65 534.98 L-07
b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1304.00 10862.32 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 284.00 1704.00 P&M-063

Page 251 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Consumables in sinking @ 10 per cent of (b) 1256.63
Add for dewatering @ 5 per cent, if required 691.15
c) Overhead charges @ 10 % on (a+b) 2124.05
d) Contractor's profit @ 10 % on (a+b+c) 2336.46
Rate per metre = (a+b+c+d) 25701.03 20652.00
say 25701.00 24.45%
16.19 Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 120.00 1200.00 M-104
Electric detonators each. 40.00 3.92 156.80 M-097/100
b) Labour
Mate day 1.34 356.65 477.91 L-12
Driller day 2.00 356.65 713.30 L-06
Blaster day 0.25 356.65 89.16 L-03
Mazdoor day 25.00 244.56 6114.00 L-13
Mazdoor (Skilled) day 4.25 356.65 1515.76 L-15
c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1304.00 13040.00 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with hour 3.00 284.00 852.00 P&M-063
pneumatic breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if 1140.11
required.
Consumables in sinking @ 10 per cent of (b). 1503.21
d) Overhead charges @ 10 % on (a+b+c) 2680.23
e) Contractor's profit @ 10 % on (a+b+c+d) 2948.25
Rate per metre = (a+b+c+d+e) 32430.73 25485.00
say 32431.00 27.26%
16.21 Sand Filling in Wells complete as per Drawing and
Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids ) cum 1.20 1251.00 1501.20 M-006
b) Labour
Mate day 0.01 356.65 3.57 L-12
Mazdoor day 0.30 244.56 73.37 L-13
c) Overhead charges @ 10 % on (a+b) 157.81
d) Contractor's profit @ 10 % on (a+b+c) 173.59
Rate per cum (a+b+c+d) 1909.54 515.00
say 1910.00 270.87%

Page 252 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.22 Providing Steel Liner 10 mm thick for Curbs and 6 mm
thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.

Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 62000.00 65100.00 M-179
b) Labour
Mate day 1.24 356.65 442.25 L-12
Fitter day 6.00 356.65 2139.90 L-07
Blacksmith day 5.00 356.65 1783.25 L-01
Welder day 5.00 458.55 2292.75 L-02
Mazdoor day 10.00 244.56 2445.60 L-13
Electrodes, cutting gas and other consumables @ 5 3255.00
per cent on cost a (a) above.
c) Overhead charges @ 10 % on (a+b) 7745.87
d) Contractor's profit @ 10 % on (a+b+c) 8520.46
Rate for per MT (a+b+c+d) 93725.08 55457.00
say 93725.00 69.00%
16.23 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 6.62 8881.00 58792.22 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.30 882.00 264.60 P&M-017
Tipper 5.5 cum capacity for disposal of muck from hour 0.30 680.00 204.00 P&M-048
pile bore hole
Bentonite kg 300.00 11.00 3300.00 M-071
c) Labour
Mate/Supervisor day 0.14 356.65 49.93 L-12
Mazdoor day 3.50 244.56 855.96 L-13
d) Overhead charges @ 10 % on (b+c) 3282.35
e) Contractor's profit @ 10 % on (b+c+d) 3610.58
Cost for 15 m = a+b+c+d+d+e 98508.64

Page 253 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per metre (a+b+c+d+e)/15 6567.24 5171.00
say 6567.00 27.00%
(A) With plasticiser
a) Materials
PCC Grade M35 cum 6.62 9940.00 65802.80 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.30 882.00 264.60 P&M-017
Tipper 5.5 cum capacity for disposal of muck from hour 0.30 680.00 204.00 P&M-048
pile bore hole
Bentonite kg 300.00 11.00 3300.00 M-071
c) Labour
Mate/Supervisor day 0.14 356.65 49.93 L-12
Mazdoor day 3.50 244.56 855.96 L-13
d) Overhead charges @ 10 % on (b+c) 3282.35
e) Contractor's profit @ 10 % on (b+c+d) 3610.58
Cost for 15 m = a+b+c+d+d+e 105519.22
Rate per metre (a+b+c+d+e)/15 7034.61 5584.00
say 7035.00 25.98%
16.24 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications cl. no. 1100,1600 & 1700and removal of
excavated earth with all lifts and lead upto 1000 m.

Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 7.85 8881.00 69715.85 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage

Page 254 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.40 882.00 352.80 P&M-017
Tipper 5.5 cum capacity for disposal of muck from hour 0.40 680.00 272.00 P&M-048
pile bore hole
Bentonite kg 350.00 11.00 3850.00 M-071
c) Labour
Mate/Supervisor day 0.16 356.65 57.06 L-12
Mazdoor day 4.00 244.56 978.24 L-13
d) Overhead charges @ 10 % on (b+c) 3365.91
e) Contractor's profit @ 10 % on (b+c+d) 3702.50
Cost for 10 m = a+b+c+d+d+e 110443.37
Rate per metre (a+b+c+d+e)/10 11044.34 8505.00
say 11044.00 29.85%
(B) With plasticiser
a) Materials
PCC Grade M35 cum 7.85 9940.00 78029.00 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.40 882.00 352.80 P&M-017
Tipper 5.5 cum capacity for disposal of muck from hour 0.40 680.00 272.00 P&M-048
pile bore hole
Bentonite kg 350.00 11.00 3850.00 M-071
c) Labour
Mate/Supervisor day 0.16 356.65 57.06 L-12
Mazdoor day 4.00 244.56 978.24 L-13
d) Overhead charges @ 10 % on (b+c) 3365.91
e) Contractor's profit @ 10 % on (b+c+d) 3702.50
Cost for 10 m = a+b+c+d+d+e 118756.52
Rate per metre (a+b+c+d+e)/10 11875.65 8900.00
say 11876.00 33.44%
16.25 Bored cast-in-situ M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
(A) Without plasticiser
a) Materials

Page 255 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
PCC Grade M35 cum 10.17 8881.00 90319.77 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.50 882.00 441.00 P&M-017
Tipper 5.5 cum capacity for disposal of muck from hour 0.50 680.00 340.00 P&M-048
pile bore hole
Bentonite kg 385.00 11.00 4235.00 M-071
c) Labour
Mate/Supervisor day 0.18 356.65 64.20 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
d) Overhead charges @ 10 % on (b+c) 3432.97
e) Contractor's profit @ 10 % on (b+c+d) 3776.27
Cost for 9 m = a+b+c+d+d+e 131858.73
Rate per metre (a+b+c+d+e)/9 14650.97 10924.00
say 14651.00 34.12%
(A) With plasticiser
a) Materials
PCC Grade M35 cum 10.17 9940.00 101089.80 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 4665.00 27990.00 P&M-036
power unit and complete accessories including
shifting from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.50 882.00 441.00 P&M-017
Tipper 5.5 cum capacity for disposal of muck from hour 0.50 680.00 340.00 P&M-048
pile bore hole
Bentonite kg 385.00 11.00 4235.00 M-071
c) Labour
Mate/Supervisor day 0.18 356.65 64.20 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
d) Overhead charges @ 10 % on (b+c) 3432.97
e) Contractor's profit @ 10 % on (b+c+d) 3776.27
Cost for 9 m = a+b+c+d+d+e 142628.76
Rate per metre (a+b+c+d+e)/9 15847.64 11981.00

Page 256 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 15848.00 32.28%
16.26 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 17.66 8881.00 156838.46 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 55.00 2750.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00 P&M-085
double acting pile driving hammer complete with
power unit and accessories..
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and
handling steel casing.
d) Labour
Mate/Supervisor day 0.12 356.65 42.80 L-12
Mazdoor day 3.00 244.56 733.68 L-13
e) Overhead charges @ 10 % on (b+c+d) 3154.90
f) Contractor's profit @ 10 % on (b+c+d+e) 3470.39
Cost for 40 m = a+b+c+d+e 195012.72
Rate per metre (a+b+c+d+e)/40 4875.32 2995.00
say 4875.00 62.77%
(B) With plasticiser
a) Materials
PCC Grade M35 cum 17.66 9940.00 175540.40 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 55.00 2750.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00 P&M-085
double acting pile driving hammer complete with
power unit and accessories..
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and
handling steel casing.

Page 257 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Labour
Mate/Supervisor day 0.12 356.65 42.80 L-12
Mazdoor day 3.00 244.56 733.68 L-13
e) Overhead charges @ 10 % on (b+c+d) 3154.90
f) Contractor's profit @ 10 % on (b+c+d+e) 3470.39
Cost for 40 m = a+b+c+d+e 213714.66
Rate per metre (a+b+c+d+e)/40 5342.87 3186.00
say 5343.00 67.70%
1.The quantity of concrete required to be removed above
the designed top level of concrete, if any, will be provided for
in the rate analysis.
2.In case steel lining is included in the design for driven
cast-in-situ pile and is planned to be retained, the same may
be included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost
16.27 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 23.55 8881.00 209147.55 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 55.00 2750.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00 P&M-085
double acting pile driving hammer complete with
power unit and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and
handling steel casing.
Hire and running charges for light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 356.65 57.06 L-12
Mazdoor day 4.00 244.56 978.24 L-13
e) Overhead charges @ 10 % on (b+c+d) 3196.68
f) Contractor's profit @ 10 % on (b+c+d+e) 3516.35
Cost for 30 m = a+b+c+d+e 247827.38
Rate per metre (a+b+c+d+e)/30 8260.91 3186.00
say 8261.00 159.29%
(B) With plasticiser
a) Materials

Page 258 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
PCC Grade M35 cum 23.55 9940.00 234087.00 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet and cushion block on top of casing Kg 50.00 55.00 2750.00 M-173
head during driving
c) Machinery
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00 P&M-085
double acting pile driving hammer complete with
power unit and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and
handling steel casing.
Hire and running charges for light crane for lowering hour 0.50 318.00 159.00 P&M-013
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 356.65 57.06 L-12
Mazdoor day 4.00 244.56 978.24 L-13
e) Overhead charges @ 10 % on (b+c+d) 3196.68
f) Contractor's profit @ 10 % on (b+c+d+e) 3516.35
Cost for 30 m = a+b+c+d+e 272766.83
Rate per metre (a+b+c+d+e)/30 9092.23 5076.00
say 9092.00 79.12%
1.The quantity of concrete required to be removed above
the designed top level of concrete, if any, will be provided for
in the rate analysis.
2.In case steel lining is included in the design for driven
cast-in-situ pile and is planned to be retained, the same may
be included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost
16.28 Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
(A) Without plasticiser
a) Materials
PCC Grade M35 cum 22.61 8881.00 200799.41 Item 12.11 (C)
iv M35 PC
WBB
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet on top of casing head during driving Kg 50.00 55.00 2750.00 M-173
c) Machinery

Page 259 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00 P&M-085
double acting pile driving hammer complete with
power unit and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and
handling steel casing.
d) Labour
Mate/Supervisor day 0.18 356.65 64.20 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
e) Overhead charges @ 10 % on (b+c+d) 3193.72
f) Contractor's profit @ 10 % on (b+c+d+e) 3513.09
Cost for 20 m = a+b+c+d+e 239443.44
Rate per metre (a+b+c+d+e)/20 11972.17 5811.00
say 11972.00 106.02%
(B) With plasticiser
a) Materials
PCC Grade M35 cum 22.61 9940.00 224743.40 Item 12.11 (C)
iv M35 PC
WBB P
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 96.00 15360.00 M-083
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 90.00 6300.00 M-124
iii) Steel helmet on top of casing head during driving Kg 50.00 55.00 2750.00 M-173
c) Machinery
Hire and running charges of piling rig Including hour 6.00 1000.00 6000.00 P&M-085
double acting pile driving hammer complete with
power unit and accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 725.00 362.50 P&M-070
lifting capacity for lowering reinforcement and
handling steel casing.
d) Labour
Mate/Supervisor day 0.18 356.65 64.20 L-12
Mazdoor day 4.50 244.56 1100.52 L-13
e) Overhead charges @ 10 % on (b+c+d) 3193.72
f) Contractor's profit @ 10 % on (b+c+d+e) 3513.09
Cost for 20 m = a+b+c+d+e 263387.43
Rate per metre (a+b+c+d+e)/20 13169.37 7351.00
say 13169.00 79.15%
1.The quantity of concrete required to be removed above
the designed top level of concrete, if any, will be provided for
in the rate analysis.
2.In case steel lining is included in the design for driven
cast-in-situ pile and is planned to be retained, the same may
be included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost
16.37 Pile Load Test on single Vertical Pile in accordance
with IS:2911(Part-IV)
Unit = 1 MT
Taking output = 1 MT
a) Initial and routine load test tonne 1.00 330.00 330.00 300.00

Page 260 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Lateral load test tonne 1.00 5500.00 5500.00 5000.00
Although, this item is incidental to work and is not required
to be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.
16.38 Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification

RCC Grade M20


Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.12 7600.00 38912.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. 3468.72
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 9018.67
e) Contractor's profit @ 10 % on (a+b+c+d) 9920.54
Cost for 15 cum = a+b+c+d+e 109125.90
Rate per metre (a+b+c+d+e)/15 7275.06 4305.00
say 7275.00 68.99%
16.38A Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.12 7600.00 38912.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-004
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 100 KVA hour 0.75 621.00 465.75 P&M-080
Loader (capacity 1 cum) hour 0.75 882.00 661.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049

Page 261 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 7.00 2625.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. 3425.48
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 8906.24
e) Contractor's profit @ 10 % on (a+b+c+d) 9796.87
Cost for 15 cum = a+b+c+d+e 107765.53
Rate per metre (a+b+c+d+e)/15 7184.37 4922.00
say 7184.00 45.96%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M25
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.99 7600.00 45524.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. 3733.20
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 9706.32
e) Contractor's profit @ 10 % on (a+b+c+d) 10676.95
Cost for 15 cum = a+b+c+d+e 117446.44
Rate per metre (a+b+c+d+e)/15 7829.76 4719.00
say 7830.00 65.92%
16.38B Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.99 7600.00 45524.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-004
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003

Page 262 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Generator 125 KVA hour 0.75 833.00 624.75 P&M-018
Loader (capacity 1 cum) hour 0.75 882.00 661.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. 4641.32
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 12067.43
e) Contractor's profit @ 10 % on (a+b+c+d) 13274.17
Cost for 15 cum = a+b+c+d+e 146015.86
Rate per metre (a+b+c+d+e)/15 9734.39 5350.00
say 9734.00 81.94%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M30
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.10 7600.00 46360.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. 3766.64
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 9793.26
e) Contractor's profit @ 10 % on (a+b+c+d) 10772.59
Cost for 15 cum = a+b+c+d+e 118498.46
Rate per metre (a+b+c+d+e)/15 7899.90 4771.00
say 7900.00 65.58%
'16.38C Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.10 7600.00 46360.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-004
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13

Page 263 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 100 KVA hour 0.75 621.00 465.75 P&M-080
Loader (capacity 1 cum) hour 0.75 882.00 661.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. 4668.40
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 12137.83
e) Contractor's profit @ 10 % on (a+b+c+d) 13351.62
Cost for 15 cum = a+b+c+d+e 146867.80
Rate per metre (a+b+c+d+e)/15 9791.19 5388.00
say 9791.00 81.72%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M35
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.33 7600.00 48108.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. 3836.56
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 9975.05
e) Contractor's profit @ 10 % on (a+b+c+d) 10972.56
Cost for 15 cum = a+b+c+d+e 120698.15
Rate per metre (a+b+c+d+e)/15 8046.54 4880.00
say 8047.00 64.90%
'16.38D Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.33 7600.00 48108.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-004
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051

Page 264 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 125 KVA hour 0.75 833.00 624.75 P&M-018
Loader (capacity 1 cum) hour 0.75 882.00 661.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. 4744.68
cost of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 12336.16
e) Contractor's profit @ 10 % on (a+b+c+d) 13569.78
Cost for 15 cum = a+b+c+d+e 149267.56
Rate per metre (a+b+c+d+e)/15 9951.17 5512.00
say 9951.00 80.53%
16.38 Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification
including providing plasticiser ( Masterplast PL-1/SPl-2
0r its equivalent ), air entraining and water reducing
plasticiser ( Masterplast PAE or its equivalent ) and
accelerating plasticiser ( Masterplast APCL or its
equuivalent)

RCC Grade M20


Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.12 7600.00 38912.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.48 92.00 1884.16 4lit/Ton
Air entraining and water reducing plasticiser Lit 15.36 59.80 918.53 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 71.68 75.00 5376.00 14lit/Ton
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009

Page 265 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. 3795.87
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 9869.25
e) Contractor's profit @ 10 % on (a+b+c+d) 10856.18
Cost for 15 cum = a+b+c+d+e 119417.96
Rate per metre (a+b+c+d+e)/15 7961.20 5053.00
say 7961.00 57.55%
16.38A Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.12 7600.00 38912.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-004
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.48 92.00 1884.16 4lit/Ton
Air entraining and water reducing plasticiser Lit 15.36 59.80 918.53 3lit/Ton
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 71.68 75.00 5376.00 14lit/Ton
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 100 KVA hour 0.75 621.00 465.75 P&M-080
Loader (capacity 1 cum) hour 0.75 882.00 661.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. 4697.63
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 12213.83
e) Contractor's profit @ 10 % on (a+b+c+d) 13435.21
Cost for 15 cum = a+b+c+d+e 147787.29
Rate per metre (a+b+c+d+e)/15 9852.49 5670.00
say 9852.00 73.76%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M25
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 5.99 7600.00 45524.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005

Page 266 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 29.95 76.40 2288.18 M-209
Air entraining and water reducing plasticiser Lit 17.97 59.80 1074.61 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 75.00 6289.50 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. 4119.29
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 10710.16
e) Contractor's profit @ 10 % on (a+b+c+d) 11781.17
Cost for 15 cum = a+b+c+d+e 129592.88
Rate per metre (a+b+c+d+e)/15 8639.53 5602.00
say 8640.00 54.23%
16.38B Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 5.99 7600.00 45524.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-004
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 29.95 76.40 2288.18 M-209
Air entraining and water reducing plasticiser Lit 17.97 59.80 1074.61 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 83.86 75.00 6289.50 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 125 KVA hour 0.75 833.00 624.75 P&M-018
Loader (capacity 1 cum) hour 0.75 882.00 661.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007

Page 267 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Formwork @ 4 per cent on cost of concrete i.e. 5027.41
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 13071.26
e) Contractor's profit @ 10 % on (a+b+c+d) 14378.39
Cost for 15 cum = a+b+c+d+e 158162.30
Rate per metre (a+b+c+d+e)/15 10544.15 6234.00
say 10544.00 69.14%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M30
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.10 7600.00 46360.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.50 76.40 2330.20 M-209
Air entraining and water reducing plasticiser Lit 18.30 59.80 1094.34 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 75.00 6405.00 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor for concreting day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. 4159.82
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 10815.53
e) Contractor's profit @ 10 % on (a+b+c+d) 11897.09
Cost for 15 cum = a+b+c+d+e 130867.96
Rate per metre (a+b+c+d+e)/15 8724.53 5671.00
say 8725.00 53.85%
'16.38C Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.10 7600.00 46360.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-004
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 30.50 76.40 2330.20 M-209
Air entraining and water reducing plasticiser Lit 18.30 59.80 1094.34 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)

Page 268 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Accelerating plasticiser conforming to IS-9103-1999 Lit 85.40 75.00 6405.00 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 100 KVA hour 0.75 621.00 465.75 P&M-080
Loader (capacity 1 cum) hour 0.75 882.00 661.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. 5061.58
cost of a) Material, b) Labour and c)
d) Machinerycharges @ 10 % on (a+b+c)
Overhead 13160.11
e) Contractor's profit @ 10 % on (a+b+c+d) 14476.12
Cost for 15 cum = a+b+c+d+e 159237.29
Rate per metre (a+b+c+d+e)/15 10615.82 6288.00
say 10616.00 68.83%
The value of a, b and c may be taken as applicable i.e.
either using concrete mixer or batching plant.
16.38 RCC Grade M35
Unit = cum
Taking output = 15 cum
Using Concrete Mixer
a) Material
Cement tonne 6.33 7600.00 48108.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 31.65 76.40 2418.06 M-209
Air entraining and water reducing plasticiser Lit 18.99 59.80 1135.60 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 75.00 6646.50 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor day 20.00 244.56 4891.20 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator (capacity 33 KVA) hour 6.00 311.00 1866.00 P&M-079
Formwork @ 4 per cent on cost of concrete i.e. 4244.57
cost of a) Material, b) Labour and c)
Machinery

Page 269 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Overhead charges @ 10 % on (a+b+c) 11035.87
e) Contractor's profit @ 10 % on (a+b+c+d) 12139.46
Cost for 15 cum = a+b+c+d+e 133534.03
Rate per metre (a+b+c+d+e)/15 8902.27 5818.00
say 8902.00 53.01%
'16.38D Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement tonne 6.33 7600.00 48108.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-004
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
Admixture ( Masterplast SPl-2 or equivalent ) Lit 31.65 76.40 2418.06 M-209
Air entraining and water reducing plasticiser Lit 18.99 59.80 1135.60 M-210
conforming to IS-9103-1999( Masterplast PAE or
equivalent)
Accelerating plasticiser conforming to IS-9103-1999 Lit 88.62 75.00 6646.50 M-211
( Masterplast APCL or equivalent )
b) Labour
Mate day 0.16 356.65 57.06 L-12
Mason day 0.38 285.32 108.42 L-10
Mazdoor for concreting day 2.50 244.56 611.40 L-13
Mazdoor for breaking pile head, bending bars, day 1.00 244.56 244.56 L-13
cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1590.00 1192.50 P&M-003
Generator 125 KVA hour 0.75 833.00 624.75 P&M-018
Loader (capacity 1 cum) hour 0.75 882.00 661.50 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km hour 2.00 828.00 1656.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 375.00 70.00 26250.00 Lead =10 km &
P&M-050
Concrete Pump hour 0.75 234.00 175.50 P&M-007
Formwork @ 4 per cent on cost of concrete i.e. 5152.68
cost of a) Material, b) Labour and c) Machinery
d) Overhead charges @ 10 % on (a+b+c) 13396.98
e) Contractor's profit @ 10 % on (a+b+c+d) 14736.68
Cost for 15 cum = a+b+c+d+e 162103.45
Rate per metre (a+b+c+d+e)/15 10806.90 6445.00
say 10807.00 67.68%
16.39 Levelling Course for Pile cap

Providing and laying of PCC M15 levelling course


100mm thick below the pile cap.
Unit = cum
Taking output = 15 cum
(A) Without plasticiser
a) Material
Cement tonne 4.13 7600.00 31388.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
40 mm aggregate cum 8.10 1761.00 14264.10 M-055
20 mm Aggregate cum 4.05 2088.00 8456.40 M-053
10 mm Aggregate cum 1.35 2513.00 3392.55 M-051

Page 270 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 285.32 427.98 L-10
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
d) Overhead charges @ 10 % on (a+b+c) 7456.52
e) Contractor's profit @ 10 % on (a+b+c+d) 8202.17
Cost for 15 cum = a+b+c+d+e 90223.89
Rate per metre (a+b+c+d+e)/15 6014.93 4206.00
say 6015.00 43.01%
16.40 Supplying, Fitting and Placing un-coated TMT bar
Reinforcement in Foundation complete as per Drawing
and Technical Specifications.

Unit = 1 MT
Taking output = 1 MT
(A) Using TMT Fe500 rebar
a) Material
TMT bars including5 per cent overlaps and wastage tonne 1.05 48380.00 50799.00 M-085
Binding wire Kg 6.00 70.00 420.00 M-072
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 356.65 142.66 L-12
Blacksmith day 2.00 458.55 917.10 L-02
Mazdoor day 6.00 244.56 1467.36 L-13
5374.61
5912.07
65032.81 46725.00
say 65033.00 39.18%
(C) Using TMT rebar Fe-500
a) Material
TMT bars including5 per cent overlaps and tonne 1.05 40763.00 42801.15 M-085_1
wastage
Binding wire Kg 6.00 70.00 420.00 M-072
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 356.65 142.66 L-12
Blacksmith day 2.00 458.55 917.10 L-02
Mazdoor day 6.00 244.56 1467.36 L-13
4574.83
5032.31
55355.41 42978.00
say 55355.00 28.80%
(D) Using other ISI marked TMT Fe 500 rebar
a) Material
TMT bars including5 per cent overlaps and wastage tonne 1.05 34492.00 36216.60 M-085_2
Binding wire Kg 6.00 70.00 420.00 M-072
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 356.65 142.66 L-12
Blacksmith day 2.00 458.55 917.10 L-02
Mazdoor day 6.00 244.56 1467.36 L-13

Page 271 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-12

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
3916.37
4308.01
47388.10
say 47388.00
16.41 Supplying, fitting and placing un-coated TMT
reinforcement complete in foundation as per drawing
and technical specification
Unit = 1 MT
Taking output = 1 MT
a) Material
TMT bars including 5 per cent overlaps and tonne 1.08 41525.00 44847.00 M-126
wastage
Binding wire Kg 6.00 70.00 420.00 M-072
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.43 356.65 153.36 L-12
Blacksmith day 2.25 458.55 1031.74 L-02
Mazdoor day 6.50 244.56 1589.64 L-13
c) Overhead charges @ 10 % on (a+b) 4804.17
d) Contractor's profit @ 10 % on (a+b+c) 5284.59
Rate for per MT (a+b+c+d) 58130.50 42440.00
say 58131.00 36.97%

Page 272 of 1351


Analysisof SOR (Roads) 2009-10
Chapter-13

CHAPTER-16-B

SUB-STRUCTURE
Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
16.1 Brick masonry work in 1:3 in sub-structure complete
excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 8.00 4000.00 M-082
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.24 4942.00 1186.08 Item 12.6 (A)
analysis)
b) Labour
Mate day 0.06 356.65 21.40 L-12
Mason day 0.80 458.55 366.84 L-11
Mazdoor day 0.80 244.56 195.65 L-13
Add for scaffolding @ 5 per cent of cost of material 288.50
and labour
c) Overhead charges @ 10 % on (a+b) 605.85
d) Contractor's profit @ 10 % on (a+b+c) 666.43
Rate per cum (a+b+c+d) 7330.74 3392.00
say 7331.00 116.13%
16.2 Pointing with cement mortar (1:3 ) on brick work in
substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 ) cum 0.03 4942.00 148.26 Item 12.6 (A)

b) Labour
Mate day 0.04 356.65 14.27 L-12
Mason day 0.50 458.55 229.28 L-11
Mazdoor day 0.50 244.56 122.28 L-13
c) Overhead charges @ 10 % on (a+b) 51.41
d) Contractor's profit @ 10 % on (a+b+c) 56.55
Rate per 10 sqm (a+b+c+d) 622.04 30.00
Rate per sqm (a+b+c+d)/10 say 62.00 106.67%
Scaffolding is already included in item 13.1 288.50
say 288.00
16.3 Plastering with cement mortar (1:3 ) on brick work in
sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 4942.00 711.65 Item 12.6 (A)
b) Labour
Mate day 0.04 356.65 14.27 L-12
Mason day 0.50 458.55 229.28 L-11
Mazdoor day 0.50 244.56 122.28 L-13
c) Overhead charges @ 10 % on (a+b) 107.75
d) Contractor's profit @ 10 % on (a+b+c) 118.52
Rate per 10 sqm (a+b+c+d) 1303.74 72.00
Rate per sqm (a+b+c+d)/10 say 130.00 80.56%

Page 1 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
1.Scaffolding is already included in item no. 13.1 288.50
say 288.00
2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.
16.4 Stone masonry work in cement mortar 1:3 for
substructure complete as per drawing and Technical
Specifications
16.4 A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 1135.00 1135.00 M-148
Through and bond stone No 7.00 8.00 56.00 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 4942.00 1630.86 Item 12.6 (A)
b) Labour
Mate day 0.10 356.65 35.67 L-12
Mason day 1.20 458.55 550.26 L-11
Mazdoor day 1.20 244.56 293.47 L-13
Add for scaffolding @ 5 per cent of cost of a) 185.06
Material and b) Labour
c) Overhead charges @ 10 % on (a+b) 388.63
d) Contractor's profit @ 10 % on (a+b+c) 427.50
Rate per cum (a+b+c+d) 4702.45 2514.00
say 4702.00 87.03%
16.4 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 1135.00 1248.50 M-148
Through and bond stone each 7.00 8.00 56.00 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.30 4942.00 1482.60 Item 12.6 (A)
b) Labour
Mate day 0.12 356.65 42.80 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 1.50 244.56 366.84 L-13
Add for scaffolding @ 5 per cent of cost of material 194.23
and labour
c) Overhead charges @ 10 % on (a+b) 407.88
d) Contractor's profit @ 10 % on (a+b+c) 448.67
Rate per cum (a+b+c+d) 4935.34 2544.00
say 4935.00 93.99%
16.4 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 560.00 621.60 M-169
Through and bond stone each 7.00 8.00 56.00 M-182

Page 2 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 4942.00 1630.86 Item 12.6 (A)
b) Labour for masonry work
Mate day 0.20 356.65 71.33 L-12
Mason day 2.50 458.55 1146.38 L-11
Mazdoor day 2.50 244.56 611.40 L-13
Add for scaffolding @ 5 per cent of cost of a) 206.88
Material and b) Labour
c) Overhead charges @ 10 % on (a+b) 434.44
d) Contractor's profit @ 10 % on (a+b+c) 477.89
Rate per cum (a+b+c+d) 5256.78 3209.00
say 5257.00 63.82%
The labour already considered in the cement mortar have
been taken into account while providing these categories in
the stone masonry works.
16.5 Plain/Reinforced cement concrete in sub-structure
complete as per drawing and Technical Specifications

(N) Without Plasticiser


Unit = cum
Taking output = 1 cum
16.5 (N) A PCC Grade M15
Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 4585.00 Item 12.8 (A)
(a+b+c) of Item 12.8 (A) M15 PC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 458.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 504.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 554.79
Rate per cum (a+b+c+d+e+f) 6102.64 4005.00
say 6103.00 52.38%
16.5 (N) B PCC Grade M20
Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 5088.00 Item 12.8 (B)
(a+b+c) of Item 12.8 (B) M20 PC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 508.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 559.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 615.65
Rate per cum (a+b+c+d+e+f) 6772.13 4458.00
say 6772.00 51.91%
16.5 (N) C PCC Grade M25
a Height upto 5m

Page 3 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.

case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5508.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 550.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 605.88
f) Contractor's profit @ 10 % on (a+b+c+d+e) 666.47
Rate per cum (a+b+c+d+e+f) 7331.15 4875.00
say 7331.00 50.38%
case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5518.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 551.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 606.98
f) Contractor's profit @ 10 % on (a+b+c+d+e) 667.68
Rate per cum (a+b+c+d+e+f) 7344.46 5516.00
16.5 (N) C say 7344.00 33.14%
b Height 5m to 10m
Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5508.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM
d) formwork
Add 12 per cent of cost of material, labour and 12.00 660.96
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 110.16
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 627.91
f) Contractor's profit @ 10 % on (a+b+c+d+e) 690.70
Rate percum (a+b+c+d+e+f) 7597.74 5053.00
say 7598.00 50.37%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5518.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB
d) formwork
Add 12 per cent of cost of material, labour and 12.00 662.16
machinery (a+b+c) for Formwork

Page 4 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Add 2 per cent of cost of material, Labour and 2.00 110.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 629.05
f) Contractor's profit @ 10 % on (a+b+c+d+e) 691.96
Rate per cum (a+b+c+d+e+f) 7611.53 5717.00
16.5 (N) C say 7612.00 33.15%
c Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5508.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM
d) formwork
Add 15 per cent of cost of material, labour and 15.00 826.20
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 220.32
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 655.45
f) Contractor's profit @ 10 % on (a+b+c+d+e) 721.00
Rate per cum (a+b+c+d+e+f) 7930.97 5275.00
say 7931.00 50.35%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5518.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB
d) formwork
Add 15 per cent of cost of material, labour and 15.00 827.70
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 220.72
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 656.64
f) Contractor's profit @ 10 % on (a+b+c+d+e) 722.31
Rate per cum (a+b+c+d+e+f) 7945.37 5967.00
say 7945.00 33.15%
16.5 (N) D PCC Grade M30
a Height upto 5m
Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.

Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5554.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10% 555.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 610.94
f) Contractor's profit @ 10 % on (a+b+c+d+e) 672.03

Page 5 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Rate perm (a+b+c+d+e+f) 7392.37 4912.00
say 7392.00 50.49%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5473.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 547.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 602.03
f) Contractor's profit @ 10 % on (a+b+c+d+e) 662.23
Rate per cum (a+b+c+d+e+f) 7284.56 5558.00
16.5 (N) D say 7285.00 31.07%
b Height 5m to 10m
Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5554.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM
d) formwork
Add 12 per cent of cost of material, labour and 12.00 666.48
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 111.08
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 633.16
f) Contractor's profit @ 10 % on (a+b+c+d+e) 696.47
Rate percum (a+b+c+d+e+f) 7661.19 5100.00
say 7661.00 50.22%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5473.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB
d) formwork
Add 12 per cent of cost of material, labour and 12.00 656.76
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 109.46
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 623.92
f) Contractor's profit @ 10 % on (a+b+c+d+e) 686.31
Rate per cum (a+b+c+d+e+f) 7549.46 5760.00
16.5 (N) D say 7549.00 31.06%
c Height above 10m
Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
mater
Case I Using concrete Mixer

Page 6 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Per Cum Basic Cost of Labour, Material & Machinery 5554.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM
d) formwork
Add 15 per cent of cost of material, labour and 15.00 833.10
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 222.16
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 660.93
f) Contractor's profit @ 10 % on (a+b+c+d+e) 727.02
Rate percum (a+b+c+d+e+f) 7997.20 5323.00
say 7997.00 50.23%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5473.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB
d) formwork
Add 15 per cent of cost of material, labour and 15.00 820.95
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 218.92
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 651.29
f) Contractor's profit @ 10 % on (a+b+c+d+e) 716.42
Rate percum (a+b+c+d+e+f) 7880.57 6013.00
say 7881.00 31.07%
16.5 (N) E RCC Grade M20
a Height upto 5m
Case I Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5238.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 523.80
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 576.18
f) Contractor's profit @ 10 % on (a+b+c+d+e) 633.80
Rate percum (a+b+c+d+e+f) 6971.78 4591.00
say 6972.00 51.86%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5159.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 515.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 567.49
f) Contractor's profit @ 10 % on (a+b+c+d+e) 624.24
Rate percum (a+b+c+d+e+f) 6866.63 5229.00
16.5 (N) E say 6867.00 31.33%
b Height 5m to 10m

Page 7 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent
of cost of material, labour and machinery instead of 4 per
cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5238.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM
d) formwork
Add 12 per cent of cost of material, labour and 12.00 628.56
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 104.76
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 597.13
f) Contractor's profit @ 10 % on (a+b+c+d+e) 656.85
Rate percum (a+b+c+d+e+f) 7225.30 4758.00
say 7225.00 51.85%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5159.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB
d) formwork
Add 12 per cent of cost of material, labour and 12.00 619.08
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 103.18
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 588.13
f) Contractor's profit @ 10 % on (a+b+c+d+e) 646.94
Rate percum (a+b+c+d+e+f) 7116.32 5419.00
16.5 (N) E say 7116.00 31.32%
c Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material,
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5238.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM
d) formwork
Add 15 per cent of cost of material, labour and 15.00 785.70
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 209.52
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 623.32
f) Contractor's profit @ 10 % on (a+b+c+d+e) 685.65
Rate percum (a+b+c+d+e+f) 7542.20 4967.00
say 7542.00 51.84%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5159.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB

Page 8 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
d) formwork
Add 15 per cent of cost of material, labour and 15.00 773.85
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 206.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 613.92
f) Contractor's profit @ 10 % on (a+b+c+d+e) 675.31
Rate percum (a+b+c+d+e+f) 7428.44 5881.00
say 7428.00 26.31%
16.5 (N) F RCC Grade M25
a Height upto 5m
Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5664.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 566.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 623.04
f) Contractor's profit @ 10 % on (a+b+c+d+e) 685.34
Rate percum (a+b+c+d+e+f) 7538.78 5014.00
say 7539.00 50.36%
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 5584.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 558.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 614.24
f) Contractor's profit @ 10 % on (a+b+c+d+e) 675.66
Rate percum (a+b+c+d+e+f) 7432.30 5651.00
16.5 (N) F say 7432.00 31.52%
b Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5664.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 668.35
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 101.95
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 643.43
f) Contractor's profit @ 10 % on (a+b+c+d+e) 707.77
Rate percum (a+b+c+d+e+f) 7785.51 5178.00
say 7786.00 50.37%

Page 9 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5584.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 658.91
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 100.51
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 634.34
f) Contractor's profit @ 10 % on (a+b+c+d+e) 697.78
Rate percum (a+b+c+d+e+f) 7675.54 5836.00
16.5 (N) F say 7676.00 31.53%
c Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5664.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM
d) formwork
Add 15 per cent of cost of material, labour and 15.00 849.60
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 226.56
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 674.02
f) Contractor's profit @ 10 % on (a+b+c+d+e) 741.42
Rate percum (a+b+c+d+e+f) 8155.59 5424.00
say 8156.00 50.37%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5584.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB
d) formwork
Add 15 per cent of cost of material, labour and 15.00 837.60
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 223.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 664.50
f) Contractor's profit @ 10 % on (a+b+c+d+e) 730.95
Rate percum (a+b+c+d+e+f) 8040.40 6114.00
say 8040.00 31.50%
16.5 (N) G RCC Grade M30
a Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case I Using concrete Mixer

Page 10 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Per Cum Basic Cost of Labour, Material & Machinery 5689.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 568.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 625.79
f) Contractor's profit @ 10 % on (a+b+c+d+e) 688.37
Rate percum (a+b+c+d+e+f) 7572.06 5038.00
say 7572.00 50.30%
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 5611.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB
d) formwork
Add 10 per cent of cost of material, labour and 10.00 561.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 617.21
f) Contractor's profit @ 10 % on (a+b+c+d+e) 678.93
Rate percum (a+b+c+d+e+f) 7468.24 5677.00
16.5 (N) G say 7468.00 31.55%
b Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5689.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 654.24
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 91.02
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 643.43
f) Contractor's profit @ 10 % on (a+b+c+d+e) 707.77
Rate percum (a+b+c+d+e+f) 7785.45 5180.00
say 7785.00 50.29%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5611.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 645.27
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 89.78
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 634.60
f) Contractor's profit @ 10 % on (a+b+c+d+e) 698.06
Rate percum (a+b+c+d+e+f) 7678.71 5837.00
16.5 (N) G say 7679.00 31.56%
c Height above 10m

Page 11 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5689.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM
d) formwork
Add 15 per cent of cost of material, labour and 15.00 853.35
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 199.12
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 674.15
f) Contractor's profit @ 10 % on (a+b+c+d+e) 741.56
Rate percum (a+b+c+d+e+f) 8157.17 5382.00
say 8157.00 51.56%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5611.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB
d) formwork
Add 15 per cent of cost of material, labour and 15.00 841.65
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 196.39
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 664.90
f) Contractor's profit @ 10 % on (a+b+c+d+e) 731.39
Rate percum (a+b+c+d+e+f) 8045.33 6064.00
say 8045.00 32.67%

16.5 (N) H RCC Grade M35


a Height upto 5m
Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5805.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM
d) formwork
Add 10 per cent of cost of material, labour and 10.00 580.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 638.55
f) Contractor's profit @ 10 % on (a+b+c+d+e) 702.41
Rate percum (a+b+c+d+e+f) 7726.46 5155.00
say 7726.00 49.87%
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 5727.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB
d) formwork

Page 12 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Add 10 per cent of cost of material, labour and 10.00 572.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 629.97
f) Contractor's profit @ 10 % on (a+b+c+d+e) 692.97
Rate percum (a+b+c+d+e+f) 7622.64 5793.00
16.5 (N) H say 7623.00 31.59%
b Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5805.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM
d) formwork
Add 11 per cent of cost of material, labour and 11.00 638.55
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 81.27
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 652.48
f) Contractor's profit @ 10 % on (a+b+c+d+e) 717.73
Rate percum (a+b+c+d+e+f) 7895.03 5267.00
say 7895.00 49.90%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5727.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB
d) formwork
Add 11 per cent of cost of material, labour and 11.00 629.97
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 80.18
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 643.71
f) Contractor's profit @ 10 % on (a+b+c+d+e) 708.09
Rate percumm (a+b+c+d+e+f) 7788.95 5920.00
16.5 (N) H say 7789.00 31.57%
c Height above 10m
For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5805.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM
d) formwork
Add 13 per cent of cost of material, labour and 13.00 754.65
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 174.15
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 673.38
f) Contractor's profit @ 10 % on (a+b+c+d+e) 740.72
Rate percum (a+b+c+d+e+f) 8147.90 5436.00
say 8148.00 49.89%

Page 13 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5727.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB
d) formwork
Add 13 per cent of cost of material, labour and 13.00 744.51
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 171.81
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 664.33
f) Contractor's profit @ 10 % on (a+b+c+d+e) 730.77
Rate percum (a+b+c+d+e+f) 8038.42 6109.00
say 8038.00 31.58%
The basic components of this analysis are the same as
those of items 13.8 (A to H). The only changes are as under:

a) Ramps/Stairs: Extra expenditure on structures which


are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percent
(P) With plasticiser ( Masterplast PL-1 ), air entraining and
water reducing plasticiser ( Masterplast PAE )
conforming to IS: 1903-1999
Unit = cum
Taking output = 1 cum
16.5 (P) A PCC Grade M15
Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 5111.00 Item 12.8 (A)
(a+b+c) of Item 12.8 (A) M15 PC OBM P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 511.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 562.21
f) Contractor's profit @ 10 % on (a+b+c+d+e) 618.43
Rate percum (a+b+c+d+e+f) 6802.74 4809.00
say 6803.00 41.46%
16.5 (P) B PCC Grade M20
Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.

Page 14 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Per Cum Basic Cost of Labour, Material & Machinery 5614.00 Item 12.8 (B)
(a+b+c) of Item 12.8 (B) M20 PC OBM P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 561.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 617.54
f) Contractor's profit @ 10 % on (a+b+c+d+e) 679.29
Rate percum (a+b+c+d+e+f) 7472.23 5264.00
say 7472.00 41.95%
16.5 (P) C PCC Grade M25
a Height upto 5m
Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.

case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6152.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 615.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 676.72
f) Contractor's profit @ 10 % on (a+b+c+d+e) 744.39
Rate percum (a+b+c+d+e+f) 8188.31 5811.00
say 8188.00 40.91%
case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6076.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 607.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 668.36
f) Contractor's profit @ 10 % on (a+b+c+d+e) 735.20
Rate percum (a+b+c+d+e+f) 8087.16 6451.00
16.5 (P) C say 8087.00 25.36%
b Height 5m to 10m
Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6152.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM P
d) formwork
Add 12 per cent of cost of material, labour and 12.00 738.24
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 123.04
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 701.33

Page 15 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
f) Contractor's profit @ 10 % on (a+b+c+d+e) 771.46
Rate percum (a+b+c+d+e+f) 8486.07 6022.00
say 8486.00 40.92%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5518.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB P
d) formwork
Add 12 per cent of cost of material, labour and 12.00 662.16
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 110.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 629.05
f) Contractor's profit @ 10 % on (a+b+c+d+e) 691.96
Rate percum (a+b+c+d+e+f) 7611.53 6686.00
16.5 (P) C say 7612.00 13.85%
c Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6152.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I M25 PC OBM P
d) formwork
Add 15 per cent of cost of material, labour and 15.00 922.80
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 246.08
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 732.09
f) Contractor's profit @ 10 % on (a+b+c+d+e) 805.30
Rate percum (a+b+c+d+e+f) 8858.26 6286.00
say 8858.00 40.92%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6076.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II M25 PC OBB P
d) formwork
Add 15 per cent of cost of material, labour and 15.00 911.40
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 243.04
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 723.04
f) Contractor's profit @ 10 % on (a+b+c+d+e) 795.35
Rate percum (a+b+c+d+e+f) 8748.83 6979.00
say 8749.00 25.36%
16.5 (P) D PCC Grade M30
a Height upto 5m

Page 16 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.

Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6207.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM P
d) formwork
Add 10 per cent of cost of material, labour and 10% 620.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 682.77
f) Contractor's profit @ 10 % on (a+b+c+d+e) 751.05
Rate percum (a+b+c+d+e+f) 8261.52 5869.00
say 8262.00 40.77%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6126.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 612.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 673.86
f) Contractor's profit @ 10 % on (a+b+c+d+e) 741.25
Rate percum (a+b+c+d+e+f) 8153.71 6505.00
16.5 (P) D say 8154.00 25.35%
b Height 5m to 10m
Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of materi
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6207.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM P
d) formwork
Add 12 per cent of cost of material, labour and 12.00 744.84
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 124.14
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 707.60
f) Contractor's profit @ 10 % on (a+b+c+d+e) 778.36
Rate percum (a+b+c+d+e+f) 8561.94 6082.00
say 8562.00 40.78%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6126.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB P
d) formwork
Add 12 per cent of cost of material, labour and 12.00 735.12
machinery (a+b+c) for Formwork

Page 17 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Add 2 per cent of cost of material, Labour and 2.00 122.52
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 698.36
f) Contractor's profit @ 10 % on (a+b+c+d+e) 768.20
Rate percum (a+b+c+d+e+f) 8450.20 6742.00
16.5 (P) D say 8450.00 25.33%
c Height above 10m
Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
mater
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6207.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I M30 PC OBM P
d) formwork
Add 15 per cent of cost of material, labour and 15.00 931.05
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 248.28
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 738.63
f) Contractor's profit @ 10 % on (a+b+c+d+e) 812.50
Rate percum (a+b+c+d+e+f) 8937.46 6349.00
say 8937.00 40.76%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6126.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II M30 PC OBB P
d) formwork
Add 15 per cent of cost of material, labour and 15.00 918.90
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 245.04
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 728.99
f) Contractor's profit @ 10 % on (a+b+c+d+e) 801.89
Rate percum (a+b+c+d+e+f) 8820.83 7037.00
say 8821.00 25.35%
16.5 (P) E RCC Grade M20
a Height upto 5m
Case I Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5764.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM P

d) formwork
Add 10 per cent of cost of material, labour and 10.00 576.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 634.04
f) Contractor's profit @ 10 % on (a+b+c+d+e) 697.44

Page 18 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Rate percum (a+b+c+d+e+f) 7671.88 5396.00
say 7672.00 42.18%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5685.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 568.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 625.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 687.89
Rate percum (a+b+c+d+e+f) 7566.74 6033.00
16.5 (P) E say 7567.00 25.43%
b Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent
of cost of material, labour and machinery instead of 4 per
cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 5764.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM P

d) formwork
Add 12 per cent of cost of material, labour and 12.00 691.68
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 115.28
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 657.10
f) Contractor's profit @ 10 % on (a+b+c+d+e) 722.81
Rate percum (a+b+c+d+e+f) 7950.86 5592.00
say 7951.00 42.19%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5685.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB P
d) formwork
Add 12 per cent of cost of material, labour and 12.00 682.20
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 113.70
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 648.09
f) Contractor's profit @ 10 % on (a+b+c+d+e) 712.90
Rate percum (a+b+c+d+e+f) 7841.89 6252.00
16.5 (P) E say 7842.00 25.43%
c Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material,
Case I Using concrete Mixer

Page 19 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Per Cum Basic Cost of Labour, Material & Machinery 5764.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I M20 RC OBM P

d) formwork
Add 15 per cent of cost of material, labour and 15.00 864.60
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 230.56
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 685.92
f) Contractor's profit @ 10 % on (a+b+c+d+e) 754.51
Rate pecurm (a+b+c+d+e+f) 8299.58 5837.00
say 8300.00 42.20%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 5685.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II M20 RC OBB P
d) formwork
Add 15 per cent of cost of material, labour and 15.00 852.75
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 227.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 676.52
f) Contractor's profit @ 10 % on (a+b+c+d+e) 744.17
Rate percum (a+b+c+d+e+f) 8185.83 6527.00
say 8186.00 25.42%
16.5 (P) F RCC Grade M25
a Height upto 5m
Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6313.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM P

d) formwork
Add 10 per cent of cost of material, labour and 10.00 631.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 694.43
f) Contractor's profit @ 10 % on (a+b+c+d+e) 763.87
Rate percum (a+b+c+d+e+f) 8402.60 5958.00
say 8403.00 41.04%
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 6234.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 623.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 685.74
f) Contractor's profit @ 10 % on (a+b+c+d+e) 754.31
Rate percum (a+b+c+d+e+f) 8297.45 6782.00
16.5 (P) F say 8297.00 22.34%

Page 20 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
b Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6313.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM P

d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 744.93
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 113.63
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 717.16
f) Contractor's profit @ 10 % on (a+b+c+d+e) 788.87
Rate percum (a+b+c+d+e+f) 8677.60 6153.00
say 8678.00 41.04%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6234.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB P
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 735.61
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 112.21
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 708.18
f) Contractor's profit @ 10 % on (a+b+c+d+e) 779.00
Rate percum (a+b+c+d+e+f) 8569.01 7004.00
16.5 (P) F say 8569.00 22.34%
c Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6313.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I M25 RC OBM P

d) formwork
Add 15 per cent of cost of material, labour and 15.00 946.95
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 252.52
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 751.25
f) Contractor's profit @ 10 % on (a+b+c+d+e) 826.37
Rate percum (a+b+c+d+e+f) 9090.09 6445.00
say 9090.00 41.04%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6234.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II M25 RC OBB P

Page 21 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
d) formwork
Add 15 per cent of cost of material, labour and 15.00 935.10
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 249.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 741.85
f) Contractor's profit @ 10 % on (a+b+c+d+e) 816.03
Rate percum (a+b+c+d+e+f) 8976.34 7337.00
say 8976.00 22.34%
16.5 (P) G RCC Grade M30
a Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6344.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM P

d) formwork
Add 10 per cent of cost of material, labour and 10.00 634.40
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 697.84
f) Contractor's profit @ 10 % on (a+b+c+d+e) 767.62
Rate percum (a+b+c+d+e+f) 8443.86 5990.00
say 8444.00 40.97%
With Batching Plant, Transit Mixer and Concrete Pump

Case II Per Cum Basic Cost of Labour, Material & Machinery 6266.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB P
d) formwork
Add 10 per cent of cost of material, labour and 10.00 626.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 689.26
f) Contractor's profit @ 10 % on (a+b+c+d+e) 758.19
Rate percum (a+b+c+d+e+f) 8340.05 6628.00
16.5 (P) G say 8340.00 25.83%
b Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6344.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM P

d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 729.56
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 101.50
machinery excluding formwork to cater for extra lift

Page 22 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
e) Overhead charges @ 10 % on (a+b+c+d) 717.51
f) Contractor's profit @ 10 % on (a+b+c+d+e) 789.26
Rate percum (a+b+c+d+e+f) 8681.83 6158.00
say 8682.00 40.99%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6266.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB P
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 720.59
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 100.26
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 708.68
f) Contractor's profit @ 10 % on (a+b+c+d+e) 779.55
Rate percum (a+b+c+d+e+f) 8575.08 6615.00
16.5 (P) G say 8575.00 29.63%
c Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent
of cost of material, labour and machinery
Case I Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6344.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I M30 RC OBM P

d) formwork
Add 14 per cent of cost of material, labour and 14.00 888.16
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 222.04
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 745.42
f) Contractor's profit @ 10 % on (a+b+c+d+e) 819.96
Rate percum (a+b+c+d+e+f) 9019.58 6398.00
say 9020.00 40.98%
Case II With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6266.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II M30 RC OBB P
d) formwork
Add 14 per cent of cost of material, labour and 14.00 877.24
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 219.31
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 736.26
f) Contractor's profit @ 10 % on (a+b+c+d+e) 809.88
Rate percum (a+b+c+d+e+f) 8908.69 7080.00
say 8909.00 25.83%
RCC Grade M35
Height upto 5m
16.5 (P) H Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .

Page 23 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
a Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6485.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM P

Case I d) formwork
Add 10 per cent of cost of material, labour and 10.00 648.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 713.35
f) Contractor's profit @ 10 % on (a+b+c+d+e) 784.69
Rate percum (a+b+c+d+e+f) 8631.54 6142.00
say 8632.00 40.54%
With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6407.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB P
d) formwork
Case II Add 10 per cent of cost of material, labour and 10.00 640.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 10 % on (a+b+c+d) 704.77
f) Contractor's profit @ 10 % on (a+b+c+d+e) 775.25
Rate percum (a+b+c+d+e+f) 8527.72 6781.00
say 8528.00 25.76%
Height 5m to 10m
16.5 (P) H For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
b Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6485.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM P

Case I d) formwork
Add 11 per cent of cost of material, labour and 11.00 713.35
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 90.79
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 728.91
f) Contractor's profit @ 10 % on (a+b+c+d+e) 801.81
Rate percum (a+b+c+d+e+f) 8819.86 6276.00
say 8820.00 40.54%
With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6407.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB P
Case II d) formwork
Add 11 per cent of cost of material, labour and 11.00 704.77
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 89.70
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 720.15
f) Contractor's profit @ 10 % on (a+b+c+d+e) 792.16
Rate percum (a+b+c+d+e+f) 8713.78 6929.00

Page 24 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
say 8714.00 25.76%
Height above 10m
16.5 (P) H For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent
of cost of material, labour and machinery
c Using concrete Mixer

Per Cum Basic Cost of Labour, Material & Machinery 6485.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I M35 RC OBM P

Case I d) formwork
Add 13 per cent of cost of material, labour and 13.00 843.05
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 194.55
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 752.26
f) Contractor's profit @ 10 % on (a+b+c+d+e) 827.49
Rate percum (a+b+c+d+e+f) 9102.35 6477.00
say 9102.00 40.53%
With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery 6407.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II M35 RC OBB P
Case II d) formwork
Add 13 per cent of cost of material, labour and 13.00 832.91
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 192.21
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 10 % on (a+b+c+d) 743.21
f) Contractor's profit @ 10 % on (a+b+c+d+e) 817.53
Rate percum (a+b+c+d+e+f) 8992.87 7151.00
say 8993.00 25.76%
The basic components of this analysis are the same as
those of items 13.8 (A to H). The only changes are as under:

a) Ramps/Stairs: Extra expenditure on structures which


are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percent
13.6 (a)Supplying, fitting and placing TMT bar
reinforcement in sub-structure complete as per
drawing and Technical Specifications
Output: MT
Taking output = 1 MT
(a) TMT - IS 1786 (Fe-500 D) Primary Producer
a) Material

Page 25 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
TMT bars including 5 per cent overlaps and tonne 1.05 40763.00 42801.15 M-085
wastage
Binding wire kg 6.00 70.00 420.00 M-072
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 356.65 121.26 L-12
Blacksmith day 2.00 458.55 917.10 L-02
Mazdoor day 6.50 244.56 1589.64 L-13
c) Overhead charges @ 10 % on (a+b) 4584.92
d) Contractor's profit @ 10 % on (a+b+c) 5043.41
Rate for per MT (a+b+c+d) 55477.47 46779.00
say 55477.00 18.59%
Output: MT
Taking output = 1 MT
(b) TMT - IS 1786 (Fe-500 D) Secondary Producer with
other make.
a) Material
TMT bars including 5 per cent overlaps and tonne 1.05 34492.00 36216.60 M-085_1
wastage
With TATA rebar
Binding wire kg 6.00 70.00 420.00 M-072
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 356.65 121.26 L-12
Blacksmith day 2.00 458.55 917.10 L-02
Mazdoor day 6.50 244.56 1589.64 L-13
c) Overhead charges @ 10 % on (a+b) 3926.46
d) Contractor's profit @ 10 % on (a+b+c) 4319.11
Rate for per MT (a+b+c+d) 47510.17 43032.00
say 47510.00 10.41%
© Using othe ISI marked rebar
a) Material
(B) TMT bars including 5 per cent overlaps and tonne 1.05 41525.00 43601.25 M-085_2
wastage
With other ISI marked
Binding wire kg 6.00 70.00 420.00 M-072
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 356.65 121.26 L-12
Blacksmith day 2.00 458.55 917.10 L-02
Mazdoor day 6.50 244.56 1589.64 L-13
c) Overhead charges @ 10 % on (a+b) 4664.93
d) Contractor's profit @ 10 % on (a+b+c) 5131.42
Rate for per MT (a+b+c+d) 56445.59
say 56446.00

13.7 Supplying, fitting and placing TMT reinforcement


complete in sub-structure as per drawing and
Technical Specification
Unit = MT
Taking output = 1 MT
a) Material
TMT bars including 5 per cent overlaps and tonne 1.10 41525.00 45677.50 M-126
wastage
Binding wire kg 6.00 70.00 420.00 M-072

Page 26 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.28 356.65 99.86 L-12
Blacksmith day 1.50 458.55 687.83 L-02
Mazdoor day 5.50 244.56 1345.08 L-13
c) Overhead charges @ 10 % on (a+b) 4823.03
d) Contractor's profit @ 10 % on (a+b+c) 5305.33
Rate for per MT (a+b+c+d) 58358.62 42128.00
say 58359.00 38.53%
13.8 Providing weep holes in Brick masonry/Plain/
Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical

Unit = Nos.
Taking output = 30 Nos.
a) Material
PVC rain water pipe 100 mm dia. (including wastage metre 31.50 183.00 5764.50 M-212
@ 5 per cent )
Average length of weep hole is taken as one metre for the
purpose of estimating.
MS clamp each. 30.00 19.00 570.00 M-123
Joint for pipe (average) taking 10% of above pipe each. 10.00 18.30 183.00 M-212/10
rate
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.15 4942.00 741.30 Item 12.6 (A)
b) Labour
Mate day 0.03 356.65 10.70 L-12
Mason day 0.50 458.55 229.28 L-11
Mazdoor day 0.25 244.56 61.14 L-13
c) Overhead charges @ 10 % on (a+b) 755.99
d) Contractor's profit @ 10 % on (a+b+c) 831.59
Cost for 30 m = a+b+c+d 9147.50
Rate per no (a+b+c+d)/30 304.92 90.00
say 305.00 238.89%
1. In case of stone masonry, the size of the weep hole shall
be 150 mm x 80 mm or circular with 150 mm diameter.

2. For structure in stone masonry, the weep holes shall be


deemed to be included in the item of stone masonry work
and shall not be paid separately.
13.9 Back filling behind abutment, wing wall and return wall
complete as per drawing and Technical Specification

Unit = cum
Taking output = 10 cum
Granular material
a) Labour
Mate day 0.28 356.65 99.86 L-12
Mazdoor day 7.00 244.56 1711.92 L-13
b) Material
Granular material cum 12.00 1029.00 12348.00 M-009

Page 27 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
c) Machinery
Plate compactor/power rammer hour 2.50 218.00 545.00 P&M-086
Water Tanker hour 0.05 440.00 22.00 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 1472.68
e) Contractor's profit @ 10 % on (a+b+c+d) 1619.95
Cost for 10 cum of granular backfill = a+b+c+d+e 17819.41
Rate per cum = (a+b+c+d+e)/10 1781.94 897.00
say 1782.00 98.66%
13.9 Sandy material
a) Labour
Mate day 0.28 356.65 99.86 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 244.56 1711.92 L-13
b) Material
Sand cum 12.00 698.00 8376.00 M-006
c) Machinery
Plate compactor/power rammer hour 2.50 218.00 545.00 P&M-086
Water Tanker hour 0.06 440.00 26.40 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 1075.92
e) Contractor's profit @ 10 % on (a+b+c+d) 1183.51
Cost for 10 cum of sandy backfill = a+b+c+d+e 13018.61
Rate per cum = (a+b+c+d+e)/10 1301.86 992.00
say 1302.00 31.25%
13.10 Providing and laying of Filter media with granular
materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger si

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 356.65 114.13 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 244.56 1711.92 L-13
Mazdoor (Skilled) day 1.00 356.65 356.65 L-15
b) Material
Filter media of stone aggregate conforming to cum 12.00 1013.00 12156.00 M-012
clause 2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 440.00 26.40 P&M-060
d) Overhead charges @ 10 % on (a+b+c) 1436.51
e) Contractor's profit @ 10 % on (a+b+c+d) 1580.16
cost for 10 cum of Fiter Media = a+b+c+d+e 17381.77
Rate per cum = (a+b+c+d+e)/10 1738.18 1061.00
say 1738.00 63.81%
13.11 Supplying, fitting and fixing in position true to line and
level cast steel rocker bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 356.65 21.40 L-12
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15

Page 28 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Mazdoor day 1.00 244.56 244.56 L-13
b) Material
Cast steel rocker bearing assembly of 250 tonne each. 1.00 103840.00 103840.00 M-065
design load capacity duly painted complete with all
its components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 1038.40
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 10 % on (a+b) 10532.27
d) Contractor's profit @ 10 % on (a+b+c) 11585.50
cost for 250 tonnes capacity bearing = a+b+c+d 127440.45
Rate per tonne capacity = (a+b+c+d)/250 509.76 587.00
say 510.00 -13.12%
13.12 Supplying, fitting and fixing in position true to line and
level forged steel roller bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 356.65 21.40 L-12
Mazdoor day 1.00 244.56 244.56 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
Forged steel roller bearing of 250 tonne design load each. 1.00 120360.00 120360.00 M-067
capacity duly painted complete with all its
components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 1203.60
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 10 % on (a+b) 12200.79
d) Contractor's profit @ 10 % on (a+b+c) 13420.87
cost for 250 tonnes capacity bearing = a+b+c+d 147629.54
Rate per tonne capacity = (a+b+c+d)/250 590.52 507.00
say 591.00 16.57%
13.13 Supplying, fitting and fixing in position true to line and
level sliding plate bearing with PTFE surface sliding
on stainless steel complete including all accessories
as per drawing and Technical Specifications and BS:
5400, section 9.1 & 9.2 (for PTFE)

Unit: one tonne capacity


Considering a 80 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 356.65 21.40 L-12
Mazdoor day 1.00 244.56 244.56 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
PTFE sliding plate bearing assembly of 80 tonnes each. 1.00 14042.00 14042.00 M-069
design load capacity duly painted complete with all
its components as per drawing and Technical
Specifications

Page 29 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Add 1 per cent for foundation anchorage bolts and 140.42
consumables.
c) Overhead charges @ 10 % on (a+b) 1462.67
d) Contractor's profit @ 10 % on (a+b+c) 1608.94
cost for 80 tonnes capacity bearing = a+b+c+d 17698.31
Rate per tonne capacity = (a+b+c+d)/80 221.23 269.00
say 221.00 -17.84%
13.14 Supplying, fitting and fixing in position true to line and
level elastomeric bearing conforming to IRC: 83 (Part-
II) section IX and clause 2005 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655
cu.cm.xRs4.4/cucm=Rs64482/-
a) Labour
Mate day 0.06 356.65 21.40 L-12
Mazdoor day 1.00 244.56 244.56 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
Elastomeric bearing assembly consisting of 7 layers each. 1.14 13500.00 15390.00 M-066
of elastomer bonded to 6 nos. internal reinforcing
steel laminates by the process of vulcanisation,
complete with all components as per drawing and
Technical Specifications.
Add 1 per cent of cost of bearing assembly for 153.90
foundation anchorage bolts and consumables.
c) Overhead charges @ 10 % on (a+b) 1598.82
d) Contractor's profit @ 10 % on (a+b+c) 1758.70
cost for 19200cc of elastomeric bearing = a+b+c+d 19345.70
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 1.01 0.82

say 1.01 23.17%


13.15 Supplying, fitting and fixing in position true to line and
level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering the sliding bearing of 80 tonnes design capacity
for this analysis.
a) Labour
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.75 244.56 183.42 L-13
Mazdoor (Skilled) day 0.35 356.65 124.83 L-15
b) Material

Page 30 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-13

Remarks/ Input
Sr No Description Unit Quantity Rate Rs Cost Rs
ref.
Supply of sliding plate bearing of 80 tonne design each. 1.00 13794.00 13794.00 M-070
capacity complete as per drawings and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 137.94
foundation anchorage bolts and consumables.
c) Overhead charges @ 10 % on (a+b) 1425.45
d) Contractor's profit @ 10 % on (a+b+c) 1567.99
cost for 80 tonnes of capacity bearing = a+b+c+d 17247.89
215.60 152.00
say 216.00 42.11%
13.16 Supplying, fitting and fixing in position true to line and
level POT-PTFE bearing consisting of a metal piston
supported by a disc or unreinforced elastomer
confined within a metal cylinder, sealing rings, dust
seals, PTFE surface sliding against stainles

Unit: one tonne capacity 387.20


Considering a Pot bearing assembly of 250 tonne capacity
for this analysis.
a) Labour
Mate day 0.08 356.65 28.53 L-12
Mazdoor day 1.50 244.56 366.84 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
Pot type bearing assembly consisting of a metal each. 1.00 37672.00 37672.00 M-068
piston supported by a disc, PTFE pads providing
sliding surfaces against stainless steel mating
together with cast steel assemblies/fabricated
structural steel assemblies duly painted with all
components as
Add 1 per cent of cost of bearing assembly for 376.72
foundation anchorage bolts and consumables.
c) Overhead charges @ 10 % on (a+b) 3862.24
d) Contractor's profit @ 10 % on (a+b+c) 4248.47
cost for 250 tonnes capacity bearing = a+b+c+d 46733.12
Rate per tonne capacity = (a+b+c+d)/250 186.93 172.00
say 187.00 8.72%

Page 31 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

CHAPTER-16-C

SUPER-STRUCTURE
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
14.1 Furnishing and Placing Reinforced/ Prestressed
cement concrete in super-structure as per
drawing and Technical Specification

(N) Without Plasticiser


A RCC Grade M20
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 7600.00 38912.00 M-084
Coarse sand cum 6.75 1251.00 8444.25 M-005
20 mm Aggregate cum 8.10 2088.00 16912.80 M-053
10 mm Aggregate cum 5.40 2513.00 13570.20 M-051
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Basic Cost of Labour, Material & Machinery 86719.00
(a+b+c) for 15 cum
14.1 (N) For formwork and staging add the following:
Case I (i) For solid slab super-structure, 20-30 per cent
of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 86719.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 17343.80
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10406.28
f) Contractor's profit @ 10 % on 11446.91
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 125915.99
Rate per cum = (a+b+c+d+e+f)/15 8394.40
say 8394.00
14.1A (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 86719.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21679.75
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10839.88
f) Contractor's profit @ 10 % on 11923.86
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 131162.49
Rate per cum = (a+b+c+d+e+f)/15 8744.17
say 8744.00

Page 1 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
14.1A (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 86719.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 26015.70
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11273.47
f) Contractor's profit @ 10 % on 12400.82
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 136408.99
Rate per cum = (a+b+c+d+e+f)/15 9093.93
say 9094.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 86719.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21679.75
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10839.88
f) Contractor's profit @ 10 % on 11923.86
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 131162.49
Rate per cum = (a+b+c+d+e+f)/15 8744.17
say 8744.00
14.1A (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 86719.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 26015.70
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11273.47
f) Contractor's profit @ 10 % on 12400.82
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 136408.99
Rate per cum = (a+b+c+d+e+f)/15 9093.93
say 9094.00
14.1A (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 86719.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 30351.65
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11707.07
f) Contractor's profit @ 10 % on 12877.77
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 141655.49
Rate per cum = (a+b+c+d+e+f)/15 9443.70
say 9444.00
14.1A Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum

Page 2 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Taking output = 120 cum
a) Material
Cement tonne 40.92 6200.00 253704.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 553853.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 553853.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 110770.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 66462.36
f) Contractor's profit @ 10 % on 73108.60
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 804194.56
Rate per cum = (a+b+c+d+e+f)/120 6701.62
say 6702.00
14.1A (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 553853.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 138463.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 69231.63
f) Contractor's profit @ 10 % on 76154.79
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 837702.66
Rate per cum = (a+b+c+d+e+f)/120 6980.86
say 6981.00
14.1A (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 553853.00
for 120 cum

Page 3 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 30 per cent of 30.00 166155.90
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 72000.89
f) Contractor's profit @ 10 % on 79200.98
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 871210.77
Rate per cum = (a+b+c+d+e+f)/120 7260.09
say 7260.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 553853.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 138463.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 69231.63
f) Contractor's profit @ 10 % on 76154.79
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 837702.66
Rate per cum = (a+b+c+d+e+f)/120 6980.86
say 6981.00
14.1A (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 553853.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 166155.90
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 72000.89
f) Contractor's profit @ 10 % on 79200.98
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 871210.77
Rate per cum = (a+b+c+d+e+f)/120 7260.09
say 7260.00
14.1A (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 553853.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 193848.55
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 74770.16
f) Contractor's profit @ 10 % on 82247.17
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 904718.88
Rate per cum = (a+b+c+d+e+f)/120 7539.32
say 7539.00
14.1 B RCC Grade M25
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 6200.00 37138.00 M-084
Coarse sand cum 6.75 792.00 5346.00 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053

Page 4 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051

b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Basic Cost of Labour, Material & Machinery 76104.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 76104.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 15220.80
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9132.48
f) Contractor's profit @ 10 % on 10045.73
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 110503.01
Rate per cum = (a+b+c+d+e+f)/15 7366.87
say 7367.00
14.1B (b) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 76104.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 19026.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9513.00
f) Contractor's profit @ 10 % on 10464.30
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 115107.30
Rate per cum = (a+b+c+d+e+f)/15 7673.82
say 7674.00
14.1B (b) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 76104.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 22831.20
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9893.52
f) Contractor's profit @ 10 % on 10882.87
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 119711.59
Rate per cum = (a+b+c+d+e+f)/15 7980.77
say 7981.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m

Page 5 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Basic Cost of Labour, Material & Machinery (a+b+c) 76104.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 19026.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9513.00
f) Contractor's profit @ 10 % on 10464.30
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 115107.30
Rate per cum = (a+b+c+d+e+f)/15 7673.82
say 7674.00
14.1B (b) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 76104.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 22831.20
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9893.52
f) Contractor's profit @ 10 % on 10882.87
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 119711.59
Rate per cum = (a+b+c+d+e+f)/15 7980.77
say 7981.00
14.1B (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 76104.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 26636.40
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10274.04
f) Contractor's profit @ 10 % on 11301.44
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 124315.88
Rate per cum = (a+b+c+d+e+f)/15 8287.73
say 8288.00
14.1B Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 6200.00 297290.00 M-084
Coarse sand cum 54.20 792.00 42926.40 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049

Page 6 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 597597.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 597597.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 119519.40
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 71711.64
f) Contractor's profit @ 10 % on 78882.80
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 867710.84
Rate per cum = (a+b+c+d+e+f)/120 7230.92
say 7231.00
14.1B (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 597597.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 149399.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 74699.63
f) Contractor's profit @ 10 % on 82169.59
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 903865.46
Rate per cum = (a+b+c+d+e+f)/120 7532.21
say 7532.00
14.1B (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 597597.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 179279.10
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 77687.61
f) Contractor's profit @ 10 % on 85456.37
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 940020.08
Rate per cum = (a+b+c+d+e+f)/120 7833.50
say 7834.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 597597.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 149399.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 74699.63

Page 7 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on 82169.59
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 903865.46
Rate per cum = (a+b+c+d+e+f)/120 7532.21
say 7532.00
14.1B (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 597597.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 179279.10
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 77687.61
f) Contractor's profit @ 10 % on 85456.37
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 940020.08
Rate per cum = (a+b+c+d+e+f)/120 7833.50
say 7834.00
14.1B (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 597597.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 209158.95
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 80675.60
f) Contractor's profit @ 10 % on 88743.15
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 976174.70
Rate per cum = (a+b+c+d+e+f)/120 8134.79
say 8135.00
14.1 C RCC Grade M 30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 6200.00 37820.00 M-084
Coarse sand cum 6.75 792.00 5346.00 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 21.00 244.56 5135.76 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Basic Cost of Labour, Material & Machinery 77045.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 77045.00
for 15 cum

Page 8 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 20 per cent of 20.00 15409.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9245.40
f) Contractor's profit @ 10 % on 10169.94
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 111869.34
Rate per cum = (a+b+c+d+e+f)/15 7457.96
say 7458.00
14.1C (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 77045.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 19261.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9630.63
f) Contractor's profit @ 10 % on 10593.69
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 116530.56
Rate per cum = (a+b+c+d+e+f)/15 7768.70
say 7769.00
14.1C (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 77045.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 23113.50
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10015.85
f) Contractor's profit @ 10 % on 11017.44
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 121191.79
Rate per cum = (a+b+c+d+e+f)/15 8079.45
say 8079.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 77045.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 19261.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9630.63
f) Contractor's profit @ 10 % on 10593.69
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 116530.56
Rate per cum = (a+b+c+d+e+f)/15 7768.70
say 7769.00
14.1C (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 77045.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 23113.50
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10015.85

Page 9 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on 11017.44
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 121191.79
Rate per cum = (a+b+c+d+e+f)/15 8079.45
say 8079.00
14.1C (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 77045.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 26965.75
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10401.08
f) Contractor's profit @ 10 % on 11441.18
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 125853.01
Rate per cum = (a+b+c+d+e+f)/15 8390.20
say 8390.00
14.1C Case II Using Batching Plant, Transit Mixer and
Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 6200.00 302498.00 M-084
Coarse sand cum 54.60 792.00 43243.20 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 19.00 244.56 4646.64 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 603381.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 603381.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 120676.20
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 72405.72
f) Contractor's profit @ 10 % on 79646.29
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 876109.21

Page 10 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum = (a+b+c+d+e+f)/120 7300.91
say 7301.00
14.1C (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 603381.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 150845.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 75422.63
f) Contractor's profit @ 10 % on 82964.89
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 912613.76
Rate per cum = (a+b+c+d+e+f)/120 7605.11
say 7605.00
14.1C (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 603381.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 181014.30
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 78439.53
f) Contractor's profit @ 10 % on 86283.48
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 949118.31
Rate per cum = (a+b+c+d+e+f)/120 7909.32
say 7909.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 603381.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 150845.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 75422.63
f) Contractor's profit @ 10 % on 82964.89
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 912613.76
Rate per cum = (a+b+c+d+e+f)/120 7605.11
say 7605.00
14.1C (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 603381.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 181014.30
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 78439.53
f) Contractor's profit @ 10 % on 86283.48
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 949118.31
Rate per cum = (a+b+c+d+e+f)/120 7909.32
say 7909.00

Page 11 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
14.1C (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 603381.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 211183.35
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 81456.44
f) Contractor's profit @ 10 % on 89602.08
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 985622.86
Rate per cum = (a+b+c+d+e+f)/120 8213.52
say 8214.00
D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 6200.00 39246.00 M-084
Coarse sand cum 6.75 792.00 5346.00 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 21.00 244.56 5135.76 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Basic Cost of Labour, Material & Machinery 78471.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 78471.00
for 15 cum
d) Formwork and staging 18 per cent of 18.00 14124.78
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9259.58
f) Contractor's profit @ 10 % on 10185.54
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 112040.89
Rate per cum = (a+b+c+d+e+f)/15 7469.39
say 7469.00
14.1D (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 78471.00
for 15 cum
d) Formwork and staging 23 per cent of 23.00 18048.33
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9651.93
f) Contractor's profit @ 10 % on 10617.13
(a+b+c+d+e)

Page 12 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for 15 cum = a+b+c+d+e+f 116788.39
Rate per cum = (a+b+c+d+e+f)/15 7785.89
say 7786.00
14.1D (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 78471.00
for 15 cum
d) Formwork and staging 28 per cent of 28.00 21971.88
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10044.29
f) Contractor's profit @ 10 % on 11048.72
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 121535.88
Rate per cum = (a+b+c+d+e+f)/15 8102.39
say 8102.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 78471.00
for 15 cum
d) Formwork and staging 23 per cent of 23.00 18048.33
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9651.93
f) Contractor's profit @ 10 % on 10617.13
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 116788.39
Rate per cum = (a+b+c+d+e+f)/15 7785.89
say 7786.00
14.1D (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 78471.00
for 15 cum
d) Formwork and staging 28 per cent of 28.00 21971.88
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10044.29
f) Contractor's profit @ 10 % on 11048.72
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 121535.88
Rate per cum = (a+b+c+d+e+f)/15 8102.39
say 8102.00
14.1D (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 78471.00
for 15 cum
d) Formwork and staging 33 per cent of 33.00 25895.43
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10436.64
f) Contractor's profit @ 10 % on 11480.31
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 126283.38
Rate per cum = (a+b+c+d+e+f)/15 8418.89
say 8419.00

Page 13 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
14.1D (iii) For box girder and balanced cantilever, 38-58
Case I per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 78471.00
for 15 cum
d) Formwork and staging 38 per cent of 38.00 29818.98
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10829.00
f) Contractor's profit @ 10 % on 11911.90
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 131030.88
Rate per cum = (a+b+c+d+e+f)/15 8735.39
say 8735.00
14.1D (q) Height 5m to 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 78471.00
for 15 cum
d) Formwork and staging 48 per cent of 48.00 37666.08
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11613.71
f) Contractor's profit @ 10 % on 12775.08
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 140525.87
Rate per cum = (a+b+c+d+e+f)/15 9368.39
say 9368.00
14.1D (r) Height above 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 78471.00
for 15 cum
d) Formwork and staging 58 per cent of 58.00 45513.18
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 12398.42
f) Contractor's profit @ 10 % on 13638.26
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 150020.86
Rate per cum = (a+b+c+d+e+f)/15 10001.39
say 10001.00
Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 6200.00 313968.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 19.00 244.56 4646.64 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080

Page 14 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 614375.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 614375.00
for 120 cum
d) Formwork and staging 18 per cent of 18.00 110587.50
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 72496.25
f) Contractor's profit @ 10 % on 79745.88
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 877204.63
Rate per cum = (a+b+c+d+e+f)/120 7310.04
say 7310.00
14.1D (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 614375.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 141306.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 75568.13
f) Contractor's profit @ 10 % on 83124.94
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 914374.31
Rate per cum = (a+b+c+d+e+f)/120 7619.79
say 7620.00
14.1D (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 614375.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 172025.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 78640.00
f) Contractor's profit @ 10 % on 86504.00
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 951544.00
Rate per cum = (a+b+c+d+e+f)/120 7929.53
say 7930.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 614375.00
for 120 cum

Page 15 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 23 per cent of 23.00 141306.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 75568.13
f) Contractor's profit @ 10 % on 83124.94
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 914374.31
Rate per cum = (a+b+c+d+e+f)/120 7619.79
say 7620.00
14.1D (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 614375.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 172025.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 78640.00
f) Contractor's profit @ 10 % on 86504.00
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 951544.00
Rate per cum = (a+b+c+d+e+f)/120 7929.53
say 7930.00
14.1D (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 614375.00
for 120 cum
d) Formwork and staging 33 per cent of 33.00 202743.75
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 81711.88
f) Contractor's profit @ 10 % on 89883.06
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 988713.69
Rate per cum = (a+b+c+d+e+f)/120 8239.28
say 8239.00
14.1D (iii) For box girder and balanced cantilever, 38-58
Case II per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 614375.00
for 120 cum
d) Formwork and staging 38 per cent of 38.00 233462.50
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 84783.75
f) Contractor's profit @ 10 % on 93262.13
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1025883.38
Rate per cum = (a+b+c+d+e+f)/120 8549.03
say 8549.00
14.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 614375.00
for 120 cum
d) Formwork and staging 48 per cent of 48.00 294900.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 90927.50

Page 16 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on 100020.25
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1100222.75
Rate per cum = (a+b+c+d+e+f)/120 9168.52
say 9169.00
14.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 614375.00
for 120 cum
d) Formwork and staging 58 per cent of 58.00 356337.50
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 97071.25
f) Contractor's profit @ 10 % on 106778.38
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1174562.13
Rate per cum = (a+b+c+d+e+f)/120 9788.02
say 9788.00
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 6200.00 39990.00 M-084
Coarse sand cum 6.75 792.00 5346.00 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051

b) Labour
Mate day 0.96 356.65 342.38 L-12
Mason day 2.00 458.55 917.10 L-11
Mazdoor day 22.00 244.56 5380.32 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Basic Cost of Labour, Material & Machinery 79710.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 79710.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 15942.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9565.20
f) Contractor's profit @ 10 % on 10521.72
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 115738.92
Rate per cum = (a+b+c+d+e+f)/15 7715.93
say 7716.00
14.1E (q) Height 5m to 10m
Case I
(i)

Page 17 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Basic Cost of Labour, Material & Machinery (a+b+c) 79710.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 19927.50
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9963.75
f) Contractor's profit @ 10 % on 10960.13
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 120561.38
Rate per cum = (a+b+c+d+e+f)/15 8037.43
say 8037.00
14.1E (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 79710.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 23913.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10362.30
f) Contractor's profit @ 10 % on 11398.53
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 125383.83
Rate per cum = (a+b+c+d+e+f)/15 8358.92
say 8359.00
14.1E (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 79710.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 19927.50
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9963.75
f) Contractor's profit @ 10 % on 10960.13
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 120561.38
Rate per cum = (a+b+c+d+e+f)/15 8037.43
say 8037.00
14.1E (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 79710.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 23913.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10362.30
f) Contractor's profit @ 10 % on 11398.53
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 125383.83
Rate per cum = (a+b+c+d+e+f)/15 8358.92
say 8359.00
14.1E (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 79710.00
for 15 cum

Page 18 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 35 per cent of 35.00 27898.50
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10760.85
f) Contractor's profit @ 10 % on 11836.94
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 130206.29
Rate per cum = (a+b+c+d+e+f)/15 8680.42
say 8680.00
14.1E Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 6200.00 319920.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.94 356.65 335.25 L-12
Mason day 3.50 458.55 1604.93 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 620823.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1E (i) For solid/voided slab super-structure, 18-28 per
Case II cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 620823.00
for 120 cum
d) Formwork and staging 18 per cent of 18.00 111748.14
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 73257.11
f) Contractor's profit @ 10 % on 80582.83
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 886411.08
Rate per cum = (a+b+c+d+e+f)/120 7386.76
say 7387.00
14.1E (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 620823.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 142789.29
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 76361.23

Page 19 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on 83997.35
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 923970.87
Rate per cum = (a+b+c+d+e+f)/120 7699.76
say 7700.00
14.1E (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 620823.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 173830.44
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 79465.34
f) Contractor's profit @ 10 % on 87411.88
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 961530.66
Rate per cum = (a+b+c+d+e+f)/120 8012.76
say 8013.00
14.1E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 620823.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 142789.29
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 76361.23
f) Contractor's profit @ 10 % on 83997.35
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 923970.87
Rate per cum = (a+b+c+d+e+f)/120 7699.76
say 7700.00
14.1E (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 620823.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 173830.44
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 79465.34
f) Contractor's profit @ 10 % on 87411.88
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 961530.66
Rate per cum = (a+b+c+d+e+f)/120 8012.76
say 8013.00
14.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 620823.00
for 120 cum
d) Formwork and staging 33 per cent of 33.00 204871.59
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 82569.46
f) Contractor's profit @ 10 % on 90826.40
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 999090.45

Page 20 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum = (a+b+c+d+e+f)/120 8325.75
say 8326.00
14.1E (iii) For cast-in-situ box girder, segment
Case II construction and balanced cantilever, 38-58 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 620823.00
for 120 cum
d) Formwork and staging 38 per cent of 38.00 235912.74
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 85673.57
f) Contractor's profit @ 10 % on 94240.93
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1036650.25
Rate per cum = (a+b+c+d+e+f)/120 8638.75
say 8639.00
14.1E (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 620823.00
for 120 cum
d) Formwork and staging 48 per cent of 48.00 297995.04
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 91881.80
f) Contractor's profit @ 10 % on 101069.98
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1111769.83
Rate per cum = (a+b+c+d+e+f)/120 9264.75
say 9265.00
14.1E (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 620823.00
for 120 cum
d) Formwork and staging 58 per cent of 58.00 360077.34
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 98090.03
f) Contractor's profit @ 10 % on 107899.04
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1186889.41
Rate per cum = (a+b+c+d+e+f)/120 9890.75
say 9891.00
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 6200.00 345960.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.94 356.65 335.25 L-12
Mason day 3.50 458.55 1604.93 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery

Page 21 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 646863.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1F (i) For solid slab/voided slab super-structure, 16-
26 per cent of cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 646863.00
for 120 cum
d) Formwork and staging 16 per cent of 16.00 103498.08
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 75036.11
f) Contractor's profit @ 10 % on 82539.72
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 907936.91
Rate per cum = (a+b+c+d+e+f)/120 7566.14
say 7566.00
14.1F (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 646863.00
for 120 cum
d) Formwork and staging 21 per cent of 21.00 135841.23
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 78270.42
f) Contractor's profit @ 10 % on 86097.47
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 947072.12
Rate per cum = (a+b+c+d+e+f)/120 7892.27
say 7892.00
14.1F (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 646863.00
for 120 cum
d) Formwork and staging 26 per cent of 26.00 168184.38
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 81504.74
f) Contractor's profit @ 10 % on 89655.21
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 986207.33
Rate per cum = (a+b+c+d+e+f)/120 8218.39
say 8218.00
14.1F (ii) For T-beam & slab including launching of
precast girders by launching truss upto 40 m
span, 21-31 per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 646863.00
for 120 cum

Page 22 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 21 per cent of 21.00 135841.23
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 78270.42
f) Contractor's profit @ 10 % on 86097.47
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 947072.12
Rate per cum = (a+b+c+d+e+f)/120 7892.27
say 7892.00
14.1F (q) Height 5m to 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 646863.00
for 120 cum
d) Formwork and staging 26 per cent of 26.00 168184.38
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 81504.74
f) Contractor's profit @ 10 % on 89655.21
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 986207.33
Rate per cum = (a+b+c+d+e+f)/120 8218.39
say 8218.00
14.1F (r) Height above 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 646863.00
for 120 cum
d) Formwork and staging 31 per cent of 31.00 200527.53
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 84739.05
f) Contractor's profit @ 10 % on 93212.96
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1025342.54
Rate per cum = (a+b+c+d+e+f)/120 8544.52
say 8545.00
14.1F (iii) For cast-in-situ box girder, segmental
construction and balanced cantilever, 36-56 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 646863.00
for 120 cum
d) Formwork and staging 36 per cent of 36.00 232870.68
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 87973.37
f) Contractor's profit @ 10 % on 96770.70
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1064477.75
Rate per cum = (a+b+c+d+e+f)/120 8870.65
say 8871.00
14.1F (q) Height 5m to 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 646863.00
for 120 cum
d) Formwork and staging 46 per cent of 46.00 297556.98
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 94442.00
f) Contractor's profit @ 10 % on 103886.20
(a+b+c+d+e)

Page 23 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for 120 cum = a+b+c+d+e+f 1142748.18
Rate per cum = (a+b+c+d+e+f)/120 9522.90
say 9523.00
14.1F (r) Height above 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 646863.00
for 120 cum
d) Formwork and staging 56 per cent of 56.00 362243.28
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 100910.63
f) Contractor's profit @ 10 % on 111001.69
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1221018.60
Rate per cum = (a+b+c+d+e+f)/120 10175.15
say 10175.00
14.1 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 58.80 6200.00 364560.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.94 356.65 335.25 L-12
Mason day 3.50 458.55 1604.93 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 665463.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1G (i) For cast-in-situ box girder, segmental
construction and balanced cantilever, 35-55 per
cent of cost of concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 665463.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 232912.05
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 89837.51
f) Contractor's profit @ 10 % on 98821.26
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1087033.81
Rate per cum = (a+b+c+d+e+f)/120 9058.62
say 9059.00

Page 24 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
14.1G (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 665463.00
for 120 cum
d) Formwork and staging 45 per cent of 45.00 299458.35
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 96492.14
f) Contractor's profit @ 10 % on 106141.35
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1167554.83
Rate per cum = (a+b+c+d+e+f)/120 9729.62
say 9730.00
14.1G (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 665463.00
for 120 cum
d) Formwork and staging 55 per cent of 55.00 366004.65
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 103146.77
f) Contractor's profit @ 10 % on 113461.44
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1248075.86
Rate per cum = (a+b+c+d+e+f)/120 10400.63
say 10401.00
14.1 H PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 63.50 6200.00 393700.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
b) Labour
Mate day 0.94 356.65 335.25 L-12
Mason day 3.50 458.55 1604.93 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 694603.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1H (i) For cast-in-situ box girder, segmental
construction and balanced cantilever, 35-55 per
cent of cost of concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 694603.00
for 120 cum

Page 25 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 35 per cent of 35.00 243111.05
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 93771.41
f) Contractor's profit @ 10 % on 103148.55
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1134634.00
Rate per cum = (a+b+c+d+e+f)/120 9455.28
say 9455.00
14.1H (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 694603.00
for 120 cum
d) Formwork and staging 45 per cent of 45.00 312571.35
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 100717.44
f) Contractor's profit @ 10 % on 110789.18
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1218680.96
Rate per cum = (a+b+c+d+e+f)/120 10155.67
say 10156.00
14.1H (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 694603.00
for 120 cum
d) Formwork and staging 55 per cent of 55.00 382031.65
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 107663.47
f) Contractor's profit @ 10 % on 118429.81
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1302727.93
Rate per cum = (a+b+c+d+e+f)/120 10856.07
say 10856.00
Note 1.Where ever concrete is carried out using batching
plant, transit mixer, concrete pump, admixers
conforming IS: 9103 @ 0.4 per cent of weight of
cement may be added for achieving desired slump of
concrete.
2. Cement provided for various components of the
super structure is for estimating purpose only. Actual
quantity of cement will be as per approved mix
design. Similarly, the provision for coarse and fine
aggregates is for estimating purpose and the exact

3. The items like needle and surface vibrators are


part of minor T & P which is already covered under
the overhead charges. As such these items have not
been added separately in the rate analysis.

(P) With plasticiser ( Masterplast PL-1/SPL-2 or


equivalent ), air entraining and water reducing
plasticiser ( Masterplast PAE or equivalent) and
accelerating plasticiser ( Masterplast ACPL or
equivalent) conforming to IS-9103-1999.

A RCC Grade M20

Page 26 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 6200.00 31744.00 M-084
Coarse sand cum 6.75 792.00 5346.00 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 20.48 128.00 2621.44 M-208
@ 4Lit per MT cement
Air entraining and water reducing plasticiser Lit 15.36 59.00 906.24 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per MT cement
Accelerating plasticiser conforming to IS- Lit 71.68 94.00 6737.92 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Li per MT cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Basic Cost of Labour, Material & Machinery 80976.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 80976.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 16195.20
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 9717.12
f) Contractor's profit @ 10 % on 10688.83
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 117577.15
Rate per cum = (a+b+c+d+e+f)/15 7838.48 5821.00
say 7838.00 34.65%
14.1A (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 80976.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 20244.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10122.00
f) Contractor's profit @ 10 % on 11134.20
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 122476.20
Rate per cum = (a+b+c+d+e+f)/15 8165.08 6064.00
say 8165.00 34.65%
14.1A (r) Height above 10m
Case I
(i)

Page 27 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Basic Cost of Labour, Material & Machinery (a+b+c) 80976.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 24292.80
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10526.88
f) Contractor's profit @ 10 % on 11579.57
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 127375.25
Rate per cum = (a+b+c+d+e+f)/15 8491.68 6307.00
say 8492.00 34.64%
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 80976.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 20244.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10122.00
f) Contractor's profit @ 10 % on 11134.20
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 122476.20
Rate per cum = (a+b+c+d+e+f)/15 8165.08 6064.00
say 8165.00 34.65%
14.1A (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 80976.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 24292.80
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10526.88
f) Contractor's profit @ 10 % on 11579.57
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 127375.25
Rate per cum = (a+b+c+d+e+f)/15 8491.68 6307.00
say 8492.00 34.64%
14.1A (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 80976.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 28341.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10931.76
f) Contractor's profit @ 10 % on 12024.94
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 132274.30
Rate per cum = (a+b+c+d+e+f)/15 8818.29 6549.00
say 8818.00 34.65%
14.1A Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 6200.00 253704.00 M-084

Page 28 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast Pl-1 or equivalent ) Lit 163.68 128.00 20951.04 M-208
@ 4Lit per MT cement
Air entraining and water reducing plasticiser Lit 122.76 59.00 7242.84 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per MT cement
Accelerating plasticiser conforming to IS- Lit 572.88 94.00 53850.72 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Li per MT cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1166.00 6996.00 P&M-003
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 633353.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 633353.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 126670.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 76002.36
f) Contractor's profit @ 10 % on 83602.60
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 919628.56
Rate per cum = (a+b+c+d+e+f)/120 7663.57 6515.00
say 7664.00 17.64%
14.1A (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 633353.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 158338.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 79169.13
f) Contractor's profit @ 10 % on 87086.04
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 957946.41
Rate per cum = (a+b+c+d+e+f)/120 7982.89 6786.00
say 7983.00 17.64%

Page 29 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
14.1A (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 633353.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 190005.90
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 82335.89
f) Contractor's profit @ 10 % on 90569.48
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 996264.27
Rate per cum = (a+b+c+d+e+f)/120 8302.20 7058.00
say 8302.00 17.63%
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 633353.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 158338.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 79169.13
f) Contractor's profit @ 10 % on 87086.04
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 957946.41
Rate per cum = (a+b+c+d+e+f)/120 7982.89 6786.00
say 7983.00 17.64%
14.1A (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 633353.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 190005.90
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 82335.89
f) Contractor's profit @ 10 % on 90569.48
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 996264.27
Rate per cum = (a+b+c+d+e+f)/120 8302.20 7058.00
say 8302.00 17.63%
14.1A (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 633353.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 221673.55
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 85502.66
f) Contractor's profit @ 10 % on 94052.92
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1034582.13
Rate per cum = (a+b+c+d+e+f)/120 8621.52 7329.00
say 8622.00 17.64%
14.1 B RCC Grade M25
Case I Using Concrete Mixer
Unit = 1 cum

Page 30 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Taking output = 15 cum
a) Material
Cement tonne 5.99 6200.00 37138.00 M-084
Coarse sand cum 6.75 792.00 5346.00 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 29.95 59.00 1767.05 M-209
@ 5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 17.97 59.00 1060.23 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 83.86 94.00 7882.84 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement
b) Labour
Mate day 0.86 356.65 306.72 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Basic Cost of Labour, Material & Machinery 86814.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 86814.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 17362.80
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10417.68
f) Contractor's profit @ 10 % on 11459.45
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 126053.93
Rate per cum = (a+b+c+d+e+f)/15 8403.60 6455.00
say 8404.00 30.19%
14.1B (b) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 86814.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21703.50
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10851.75
f) Contractor's profit @ 10 % on 11936.93
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 131306.18
Rate per cum = (a+b+c+d+e+f)/15 8753.75 6724.00
say 8754.00 30.19%
14.1B (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 86814.00
for 15 cum

Page 31 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 30 per cent of 30.00 26044.20
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11285.82
f) Contractor's profit @ 10 % on 12414.40
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 136558.42
Rate per cum = (a+b+c+d+e+f)/15 9103.89 6993.00
say 9104.00 30.19%
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 86814.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21703.50
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10851.75
f) Contractor's profit @ 10 % on 11936.93
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 131306.18
Rate per cum = (a+b+c+d+e+f)/15 8753.75 6724.00
say 8754.00 30.19%
14.1B (b) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 86814.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 26044.20
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11285.82
f) Contractor's profit @ 10 % on 12414.40
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 136558.42
Rate per cum = (a+b+c+d+e+f)/15 9103.89 6993.00
say 9104.00 30.19%
14.1B (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 86814.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 30384.90
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11719.89
f) Contractor's profit @ 10 % on 12891.88
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 141810.67
Rate per cum = (a+b+c+d+e+f)/15 9454.04 7262.00
say 9454.00 30.18%
14.1B Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 6200.00 297290.00 M-084
Coarse sand cum 54.20 792.00 42926.40 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053

Page 32 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 239.75 59.00 14145.25 M-209
@ 5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 143.85 59.00 8487.15 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 671.30 94.00 63102.20 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement
b) Labour
Mate day 0.84 356.65 299.59 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 18.00 244.56 4402.08 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 683332.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 683332.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 136666.40
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 81999.84
f) Contractor's profit @ 10 % on 90199.82
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 992198.06
Rate per cum = (a+b+c+d+e+f)/120 8268.32 7156.00
say 8268.00 15.54%
14.1B (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 683332.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 170833.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 85416.50
f) Contractor's profit @ 10 % on 93958.15
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1033539.65
Rate per cum = (a+b+c+d+e+f)/120 8612.83 7454.00
say 8613.00 15.55%
14.1B (r) Height above 10m
Case II
(i)

Page 33 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Basic Cost of Labour, Material & Machinery (a+b+c) 683332.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 204999.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 88833.16
f) Contractor's profit @ 10 % on 97716.48
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1074881.24
Rate per cum = (a+b+c+d+e+f)/120 8957.34 7752.00
say 8957.00 15.54%
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 683332.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 170833.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 85416.50
f) Contractor's profit @ 10 % on 93958.15
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1033539.65
Rate per cum = (a+b+c+d+e+f)/120 8612.83 7454.00
say 8613.00 15.55%
14.1B (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 683332.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 204999.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 88833.16
f) Contractor's profit @ 10 % on 97716.48
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1074881.24
Rate per cum = (a+b+c+d+e+f)/120 8957.34 7752.00
say 8957.00 15.54%
14.1B (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 683332.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 239166.20
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 92249.82
f) Contractor's profit @ 10 % on 101474.80
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1116222.82
Rate per cum = (a+b+c+d+e+f)/120 9301.86 8050.00
say 9302.00 15.55%
14.1 C RCC Grade M 30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 6200.00 37820.00 M-084

Page 34 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Coarse sand cum 6.75 792.00 5346.00 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 30.50 59.00 1799.50 M-209
@ 5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 18.30 59.00 1079.70 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 85.40 94.00 8027.60 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 21.00 244.56 5135.76 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Basic Cost of Labour, Material & Machinery 87952.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 87952.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 17590.40
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10554.24
f) Contractor's profit @ 10 % on 11609.66
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 127706.30
Rate per cum = (a+b+c+d+e+f)/15 8513.75 6545.00
say 8514.00 30.08%
14.1C (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 87952.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21988.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10994.00
f) Contractor's profit @ 10 % on 12093.40
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 133027.40
Rate per cum = (a+b+c+d+e+f)/15 8868.49 6817.00
say 8868.00 30.09%
14.1C (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 87952.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 26385.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11433.76

Page 35 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on 12577.14
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 138348.50
Rate per cum = (a+b+c+d+e+f)/15 9223.23 7090.00
say 9223.00 30.08%
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 87952.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 21988.00
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10994.00
f) Contractor's profit @ 10 % on 12093.40
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 133027.40
Rate per cum = (a+b+c+d+e+f)/15 8868.49 6817.00
say 8868.00 30.09%
14.1C (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 87952.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 26385.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11433.76
f) Contractor's profit @ 10 % on 12577.14
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 138348.50
Rate per cum = (a+b+c+d+e+f)/15 9223.23 7090.00
say 9223.00 30.08%
14.1C (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 87952.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 30783.20
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11873.52
f) Contractor's profit @ 10 % on 13060.87
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 143669.59
Rate per cum = (a+b+c+d+e+f)/15 9577.97 7363.00
say 9578.00 30.08%
14.1C Case II Using Batching Plant, Transit Mixer and
Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 6200.00 302498.00 M-084
Coarse sand cum 54.60 792.00 43243.20 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 243.95 59.00 14393.05 M-209
@ 5Lit per Tonne cement

Page 36 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Air entraining and water reducing plasticiser Lit 146.37 59.00 8635.83 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 683.06 94.00 64207.64 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 19.00 244.56 4646.64 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 690617.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 690617.00
for 120 cum
d) Formwork and staging 20 per cent of 20.00 138123.40
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 82874.04
f) Contractor's profit @ 10 % on 91161.44
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1002775.88
Rate per cum = (a+b+c+d+e+f)/120 8356.47 7235.00
say 8356.00 15.49%
14.1C (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 690617.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 172654.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 86327.13
f) Contractor's profit @ 10 % on 94959.84
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1044558.21
Rate per cum = (a+b+c+d+e+f)/120 8704.65 7537.00
say 8705.00 15.50%
14.1C (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 690617.00
for 120 cum

Page 37 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 30 per cent of 30.00 207185.10
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 89780.21
f) Contractor's profit @ 10 % on 98758.23
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1086340.54
Rate per cum = (a+b+c+d+e+f)/120 9052.84 7838.00
say 9053.00 15.50%
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 690617.00
for 120 cum
d) Formwork and staging 25 per cent of 25.00 172654.25
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 86327.13
f) Contractor's profit @ 10 % on 94959.84
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1044558.21
Rate per cum = (a+b+c+d+e+f)/120 8704.65 7537.00
say 8705.00 15.50%
14.1C (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 690617.00
for 120 cum
d) Formwork and staging 30 per cent of 30.00 207185.10
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 89780.21
f) Contractor's profit @ 10 % on 98758.23
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1086340.54
Rate per cum = (a+b+c+d+e+f)/120 9052.84 7838.00
say 9053.00 15.50%
14.1C (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 690617.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 241715.95
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 93233.30
f) Contractor's profit @ 10 % on 102556.62
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1128122.87
Rate per cum = (a+b+c+d+e+f)/120 9401.02 8140.00
say 9401.00 15.49%
14.1 Furnishing and Placing Reinforced/ Prestressed
cement concrete in super-structure as per drawing
and Technical Specification including providing
plasticiser ( Masterplast SPl-2 or equivalent )
D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum

Page 38 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
a) Material
Cement tonne 6.33 6200.00 39246.00 M-084
Coarse sand cum 6.75 792.00 5346.00 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 31.65 59.00 1867.35 M-209
@ 5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 18.99 59.00 1120.41 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 88.62 94.00 8330.28 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement
b) Labour
Mate day 0.90 356.65 320.99 L-12
Mason day 1.50 458.55 687.83 L-11
Mazdoor day 21.00 244.56 5135.76 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Basic Cost of Labour, Material & Machinery 89789.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 89789.00
for 15 cum
d) Formwork and staging 18 per cent of 18.00 16162.02
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10595.10
f) Contractor's profit @ 10 % on 11654.61
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 128200.73
Rate per cum = (a+b+c+d+e+f)/15 8546.72 6598.00
say 8547.00 29.54%
14.1D (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 89789.00
for 15 cum
d) Formwork and staging 23 per cent of 23.00 20651.47
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11044.05
f) Contractor's profit @ 10 % on 12148.45
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 133632.97
Rate per cum = (a+b+c+d+e+f)/15 8908.86 6878.00
say 8909.00 29.53%
14.1D (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 89789.00
for 15 cum

Page 39 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 28 per cent of 28.00 25140.92
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11492.99
f) Contractor's profit @ 10 % on 12642.29
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 139065.20
Rate per cum = (a+b+c+d+e+f)/15 9271.01 7157.00
say 9271.00 29.54%
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 89789.00
for 15 cum
d) Formwork and staging 23 per cent of 23.00 20651.47
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11044.05
f) Contractor's profit @ 10 % on 12148.45
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 133632.97
Rate per cum = (a+b+c+d+e+f)/15 8908.86 6878.00
say 8909.00 29.53%
14.1D (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 89789.00
for 15 cum
d) Formwork and staging 28 per cent of 28.00 25140.92
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11492.99
f) Contractor's profit @ 10 % on 12642.29
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 139065.20
Rate per cum = (a+b+c+d+e+f)/15 9271.01 7157.00
say 9271.00 29.54%
14.1D (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 89789.00
for 15 cum
d) Formwork and staging 33 per cent of 33.00 29630.37
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11941.94
f) Contractor's profit @ 10 % on 13136.13
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 144497.44
Rate per cum = (a+b+c+d+e+f)/15 9633.16 7437.00
say 9633.00 29.53%
14.1D (iii) For box girder and balanced cantilever, 38-58
Case I per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 89789.00
for 15 cum
d) Formwork and staging 38 per cent of 38.00 34119.82
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 12390.88

Page 40 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on 13629.97
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 149929.67
Rate per cum = (a+b+c+d+e+f)/15 9995.31 7717.00
say 9995.00 29.52%
14.1D (q) Height 5m to 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 89789.00
for 15 cum
d) Formwork and staging 48 per cent of 48.00 43098.72
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 13288.77
f) Contractor's profit @ 10 % on 14617.65
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 160794.14
Rate per cum = (a+b+c+d+e+f)/15 10719.61 8276.00
say 10720.00 29.53%
14.1D (r) Height above 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 89789.00
for 15 cum
d) Formwork and staging 58 per cent of 58.00 52077.62
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 14186.66
f) Contractor's profit @ 10 % on 15605.33
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 171658.61
Rate per cum = (a+b+c+d+e+f)/15 11443.91 8835.00
say 11444.00 29.53%
Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 6200.00 313968.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 253.20 59.00 14938.80 M-209
@ 5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 151.92 59.00 8963.28 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 708.96 94.00 66642.24 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement
b) Labour
Mate day 0.88 356.65 313.85 L-12
Mason day 3.00 458.55 1375.65 L-11
Mazdoor day 19.00 244.56 4646.64 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080

Page 41 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 704920.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent
Case II of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 704920.00
for 120 cum
d) Formwork and staging 18 per cent of 18.00 126885.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 83180.56
f) Contractor's profit @ 10 % on 91498.62
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1006484.78
Rate per cum = (a+b+c+d+e+f)/120 8387.37 7274.00
say 8387.00 15.30%
14.1D (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 704920.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 162131.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 86705.16
f) Contractor's profit @ 10 % on 95375.68
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1049132.44
Rate per cum = (a+b+c+d+e+f)/120 8742.77 7582.00
say 8743.00 15.31%
14.1D (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 704920.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 197377.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 90229.76
f) Contractor's profit @ 10 % on 99252.74
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1091780.10
Rate per cum = (a+b+c+d+e+f)/120 9098.17 7891.00
say 9098.00 15.30%
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 704920.00
for 120 cum

Page 42 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 23 per cent of 23.00 162131.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 86705.16
f) Contractor's profit @ 10 % on 95375.68
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1049132.44
Rate per cum = (a+b+c+d+e+f)/120 8742.77 7582.00
say 8743.00 15.31%
14.1D (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 704920.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 197377.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 90229.76
f) Contractor's profit @ 10 % on 99252.74
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1091780.10
Rate per cum = (a+b+c+d+e+f)/120 9098.17 7891.00
say 9098.00 15.30%
14.1D (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 704920.00
for 120 cum
d) Formwork and staging 33 per cent of 33.00 232623.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 93754.36
f) Contractor's profit @ 10 % on 103129.80
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1134427.76
Rate per cum = (a+b+c+d+e+f)/120 9453.56 8199.00
say 9454.00 15.31%
14.1D (iii) For box girder and balanced cantilever, 38-58
Case II per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 704920.00
for 120 cum
d) Formwork and staging 38 per cent of 38.00 267869.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 97278.96
f) Contractor's profit @ 10 % on 107006.86
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1177075.42
Rate per cum = (a+b+c+d+e+f)/120 9808.96 8507.00
say 9809.00 15.31%
14.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 704920.00
for 120 cum
d) Formwork and staging 48 per cent of 48.00 338361.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 104328.16

Page 43 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on 114760.98
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1262370.74
Rate per cum = (a+b+c+d+e+f)/120 10519.76 9124.00
say 10520.00 15.30%
14.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 704920.00
for 120 cum
d) Formwork and staging 58 per cent of 58.00 408853.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 111377.36
f) Contractor's profit @ 10 % on 122515.10
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1347666.06
Rate per cum = (a+b+c+d+e+f)/120 11230.55 9740.00
say 11231.00 15.31%
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 6200.00 39990.00 M-084
Coarse sand cum 6.75 792.00 5346.00 M-005
20 mm Aggregate cum 8.10 1777.00 14393.70 M-053
10 mm Aggregate cum 5.40 1916.00 10346.40 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 32.25 59.00 1902.75 M-209
@ 5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 19.35 59.00 1141.65 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 90.30 94.00 8488.20 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement

b) Labour
Mate day 0.96 356.65 342.38 L-12
Mason day 2.00 458.55 917.10 L-11
Mazdoor day 22.00 244.56 5380.32 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 188.00 1128.00 P&M-009
Generator 33 KVA hour 6.00 311.00 1866.00 P&M-079
Basic Cost of Labour, Material & Machinery 91243.00
(a+b+c) for 15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent
Case I of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 91243.00
for 15 cum
d) Formwork and staging 20 per cent of 20.00 18248.60
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 10949.16

Page 44 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on 12044.08
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 132484.84
Rate per cum = (a+b+c+d+e+f)/15 8832.32 6816.00
say 8832.00 29.58%
14.1E (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 91243.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 22810.75
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11405.38
f) Contractor's profit @ 10 % on 12545.91
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 138005.04
Rate per cum = (a+b+c+d+e+f)/15 9200.34 7100.00
say 9200.00 29.58%
14.1E (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 91243.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 27372.90
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11861.59
f) Contractor's profit @ 10 % on 13047.75
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 143525.24
Rate per cum = (a+b+c+d+e+f)/15 9568.35 7384.00
say 9568.00 29.58%
14.1E (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 91243.00
for 15 cum
d) Formwork and staging 25 per cent of 25.00 22810.75
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11405.38
f) Contractor's profit @ 10 % on 12545.91
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 138005.04
Rate per cum = (a+b+c+d+e+f)/15 9200.34 7100.00
say 9200.00 29.58%
14.1E (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 91243.00
for 15 cum
d) Formwork and staging 30 per cent of 30.00 27372.90
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 11861.59
f) Contractor's profit @ 10 % on 13047.75
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 143525.24

Page 45 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum = (a+b+c+d+e+f)/15 9568.35 7384.00
say 9568.00 29.58%
14.1E (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 91243.00
for 15 cum
d) Formwork and staging 35 per cent of 35.00 31935.05
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 12317.81
f) Contractor's profit @ 10 % on 13549.59
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 149045.44
Rate per cum = (a+b+c+d+e+f)/15 9936.36 7668.00
say 9936.00 29.58%
14.1E Case II Using Batching Plant, Transit Mixer and
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 6200.00 319920.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 258.00 59.00 15222.00 M-209
@ 5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 154.80 59.00 9133.20 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 722.40 94.00 67905.60 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement
b) Labour
Mate day 0.94 356.65 335.25 L-12
Mason day 3.50 458.55 1604.93 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 713083.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1E (i) For solid/voided slab super-structure, 18-28 per
Case II cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 713083.00
for 120 cum

Page 46 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
d) Formwork and staging 18 per cent of 18.00 128354.94
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 84143.79
f) Contractor's profit @ 10 % on 92558.17
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 1018139.91
Rate per cum = (a+b+c+d+e+f)/120 8484.50 7361.00
say 8484.00 15.26%
14.1E (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 713083.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 164009.09
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 87709.21
f) Contractor's profit @ 10 % on 96480.13
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1061281.43
Rate per cum = (a+b+c+d+e+f)/120 8844.01 7673.00
say 8844.00 15.26%
14.1E (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 713083.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 199663.24
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 91274.62
f) Contractor's profit @ 10 % on 100402.09
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1104422.95
Rate per cum = (a+b+c+d+e+f)/120 9203.52 7985.00
say 9204.00 15.27%
14.1E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 713083.00
for 120 cum
d) Formwork and staging 23 per cent of 23.00 164009.09
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 87709.21
f) Contractor's profit @ 10 % on 96480.13
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1061281.43
Rate per cum = (a+b+c+d+e+f)/120 8844.01 7673.00
say 8844.00 15.26%
14.1E (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 713083.00
for 120 cum
d) Formwork and staging 28 per cent of 28.00 199663.24
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 91274.62

Page 47 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on 100402.09
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1104422.95
Rate per cum = (a+b+c+d+e+f)/120 9203.52 7985.00
say 9204.00 15.27%
14.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 713083.00
for 120 cum
d) Formwork and staging 33 per cent of 33.00 235317.39
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 94840.04
f) Contractor's profit @ 10 % on 104324.04
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1147564.47
Rate per cum = (a+b+c+d+e+f)/120 9563.04 8297.00
say 9563.00 15.26%
14.1E (iii) For cast-in-situ box girder, segment
Case II construction and balanced cantilever, 38-58 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 713083.00
for 120 cum
d) Formwork and staging 38 per cent of 38.00 270971.54
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 98405.45
f) Contractor's profit @ 10 % on 108246.00
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1190705.99
Rate per cum = (a+b+c+d+e+f)/120 9922.55 8609.00
say 9923.00 15.26%
14.1E (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 713083.00
for 120 cum
d) Formwork and staging 48 per cent of 48.00 342279.84
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 105536.28
f) Contractor's profit @ 10 % on 116089.91
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1276989.04
Rate per cum = (a+b+c+d+e+f)/120 10641.58 9233.00
say 10642.00 15.26%
14.1E (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 713083.00
for 120 cum
d) Formwork and staging 58 per cent of 58.00 413588.14
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 112667.11
f) Contractor's profit @ 10 % on 123933.83
(a+b+c+d+e)

Page 48 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for 120 cum = a+b+c+d+e+f 1363272.08
Rate per cum = (a+b+c+d+e+f)/120 11360.60 9857.00
say 11361.00 15.26%
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 6200.00 345960.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 279.00 59.00 16461.00 M-209
@ 5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 167.40 59.00 9876.60 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 781.20 94.00 73432.80 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement
b) Labour
Mate day 0.94 356.65 335.25 L-12
Mason day 3.50 458.55 1604.93 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 746633.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1F (i) For solid slab/voided slab super-structure, 16-
26 per cent of cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 746633.00
for 120 cum
d) Formwork and staging 16 per cent of 16.00 119461.28
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 86609.43
f) Contractor's profit @ 10 % on 95270.37
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1047974.08
Rate per cum = (a+b+c+d+e+f)/120 8733.12 7602.00
say 8733.00 14.88%
14.1F (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 746633.00
for 120 cum
d) Formwork and staging 21 per cent of 21.00 156792.93
(a+b+c)

Page 49 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
e) Overhead charges @ 10 % on (a+b+c+d) 90342.59
f) Contractor's profit @ 10 % on 99376.85
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1093145.38
Rate per cum = (a+b+c+d+e+f)/120 9109.54 7929.00
say 9110.00 14.89%
14.1F (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 746633.00
for 120 cum
d) Formwork and staging 26 per cent of 26.00 194124.58
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 94075.76
f) Contractor's profit @ 10 % on 103483.33
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1138316.67
Rate per cum = (a+b+c+d+e+f)/120 9485.97 8257.00
say 9486.00 14.88%
14.1F (ii) For T-beam & slab including launching of
precast girders by launching truss upto 40 m
span, 21-31 per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 746633.00
for 120 cum
d) Formwork and staging 21 per cent of 21.00 156792.93
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 90342.59
f) Contractor's profit @ 10 % on 99376.85
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1093145.38
Rate per cum = (a+b+c+d+e+f)/120 9109.54 7929.00
say 9110.00 14.89%
14.1F (q) Height 5m to 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 746633.00
for 120 cum
d) Formwork and staging 26 per cent of 26.00 194124.58
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 94075.76
f) Contractor's profit @ 10 % on 103483.33
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1138316.67
Rate per cum = (a+b+c+d+e+f)/120 9485.97 8257.00
say 9486.00 14.88%
14.1F (r) Height above 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) 746633.00
for 120 cum
d) Formwork and staging 31 per cent of 31.00 231456.23
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 97808.92
f) Contractor's profit @ 10 % on 107589.82
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1183487.97
Rate per cum = (a+b+c+d+e+f)/120 9862.40 8585.00

Page 50 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
say 9862.00 14.87%
14.1F (iii) For cast-in-situ box girder, segmental
construction and balanced cantilever, 36-56 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 746633.00
for 120 cum
d) Formwork and staging 36 per cent of 36.00 268787.88
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 101542.09
f) Contractor's profit @ 10 % on 111696.30
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1228659.26
Rate per cum = (a+b+c+d+e+f)/120 10238.83 8912.00
say 10239.00 14.89%
14.1F (q) Height 5m to 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 746633.00
for 120 cum
d) Formwork and staging 46 per cent of 46.00 343451.18
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 109008.42
f) Contractor's profit @ 10 % on 119909.26
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1319001.86
Rate per cum = (a+b+c+d+e+f)/120 10991.68 9568.00
say 10992.00 14.88%
14.1F (r) Height above 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 746633.00
for 120 cum
d) Formwork and staging 56 per cent of 56.00 418114.48
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 116474.75
f) Contractor's profit @ 10 % on 128122.22
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1409344.45
Rate per cum = (a+b+c+d+e+f)/120 11744.54 10223.00
say 11745.00 14.89%
14.1 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 58.80 6200.00 364560.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 294.00 59.00 17346.00 M-209
@ 5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 176.40 59.00 10407.60 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 823.20 94.00 77380.80 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement

Page 51 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
b) Labour
Mate day 0.94 356.65 335.25 L-12
Mason day 3.50 458.55 1604.93 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 770597.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1G (i) For cast-in-situ box girder, segmental
construction and balanced cantilever, 35-55 per
cent of cost of concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 770597.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 269708.95
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 104030.60
f) Contractor's profit @ 10 % on 114433.65
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1258770.20
Rate per cum = (a+b+c+d+e+f)/120 10489.75 9150.00
say 10490.00 14.64%
14.1G (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 770597.00
for 120 cum
d) Formwork and staging 45 per cent of 45.00 346768.65
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 111736.57
f) Contractor's profit @ 10 % on 122910.22
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1352012.44
Rate per cum = (a+b+c+d+e+f)/120 11266.77 9828.00
say 11267.00 14.64%
14.1G (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 770597.00
for 120 cum
d) Formwork and staging 55 per cent of 55.00 423828.35
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 119442.54
f) Contractor's profit @ 10 % on 131386.79
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1445254.67
Rate per cum = (a+b+c+d+e+f)/120 12043.79 10506.00
say 12044.00 14.64%

Page 52 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
14.1 H PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 63.50 6200.00 393700.00 M-084
Coarse sand cum 54.00 792.00 42768.00 M-004
20 mm Aggregate cum 64.80 1777.00 115149.60 M-053
10 mm Aggregate cum 43.20 1916.00 82771.20 M-051
Admixture ( Masterplast SPl-2 or equivalent) Lit 317.50 59.00 18732.50 M-209
@ 5Lit per Tonne cement
Air entraining and water reducing plasticiser Lit 190.50 59.00 11239.50 M-210
conforming to IS-9103-1999( Masterplast
PAE or equivalent) @ 3Lit per Tonne cement
Accelerating plasticiser conforming to IS- Lit 889.00 94.00 83566.00 M-211
9103-1999 ( Masterplast APCL or equivalent
) @ 14Lit per Tonne cement
b) Labour
Mate day 0.94 356.65 335.25 L-12
Mason day 3.50 458.55 1604.93 L-11
Mazdoor day 20.00 244.56 4891.20 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1590.00 9540.00 P&M-002
Generator 100 KVA hour 6.00 621.00 3726.00 P&M-080
Loader hour 6.00 882.00 5292.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 828.00 12420.00 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 7.00 21000.00 Lead =10 km
& P&M-050

Concrete Pump hour 6.00 234.00 1404.00 P&M-007


Basic Cost of Labour, Material & Machinery 808141.00
(a+b+c) for 120 cum
For formwork and staging add the following:
14.1H (i) For cast-in-situ box girder, segmental
construction and balanced cantilever, 35-55 per
cent of cost of concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 808141.00
for 120 cum
d) Formwork and staging 35 per cent of 35.00 282849.35
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 109099.04
f) Contractor's profit @ 10 % on 120008.94
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1320098.32
Rate per cum = (a+b+c+d+e+f)/120 11000.82 9626.00
say 11001.00 14.28%
14.1H (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 808141.00
for 120 cum
d) Formwork and staging 45 per cent of 45.00 363663.45
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 117180.45

Page 53 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
f) Contractor's profit @ 10 % on 128898.49
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1417883.38
Rate per cum = (a+b+c+d+e+f)/120 11815.69 10339.00
say 11816.00 14.29%
14.1H (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) 808141.00
for 120 cum
d) Formwork and staging 55 per cent of 55.00 444477.55
(a+b+c)
e) Overhead charges @ 10 % on (a+b+c+d) 125261.86
f) Contractor's profit @ 10 % on 137788.04
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1515668.45
Rate per cum = (a+b+c+d+e+f)/120 12630.57 11052.74
say 12631.00 14.28%
Note 1.Where ever concrete is carried out using batching
plant, transit mixer, concrete pump, admixers
conforming IS: 9103 @ 0.4 per cent of weight of
cement may be added for achieving desired slump of
concrete.
2. Cement provided for various components of the
super structure is for estimating purpose only. Actual
quantity of cement will be as per approved mix
design. Similarly, the provision for coarse and fine
aggregates is for estimating purpose and the exact

3. The items like needle and surface vibrators are


part of minor T & P which is already covered under
the overhead charges. As such these items have not
been added separately in the rate analysis.

14.2 Supplying, fitting and placing TMT bar


reinforcement in super-structure including
splicing complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
(a) With (Fe-500) rebar
a) Material
TMT CRS bars including 5 per cent for laps tonne 1.05 40763.00 42801.15 M-085
and wastage
Binding wire Kg 8.00 70.00 560.00 M-072
b) Labour for cutting, bending, tying and
placing in position
Mate day 0.44 356.65 156.93 L-12
Blacksmith day 3.00 356.65 1069.95 L-02
Mazdoor day 8.00 244.56 1956.48 L-13
Basic Cost of Labour & Material (a+b) 46545.00
c) Overhead charges @ 10 % on (a+b) 4654.45
d) Contractor's profit @ 10 % on (a+b+c) 5119.90
Rate per MT = a+b+c+d 56318.85 48991.00
say 56319.00 14.96%
Unit = 1 MT

Page 54 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Taking output = 1 MT
(b) TMT - IS 1786 (Fe-500 D) Secondary Producer
with other make.
a) Material
TMT bars including 5 per cent for laps and tonne 1.05 34492.00 36216.60 M-085_1
wastage
Binding wire Kg 8.00 70.00 560.00 M-072
b) Labour for cutting, bending, tying and
placing in position
Mate day 0.44 356.65 156.93 L-12
Blacksmith day 3.00 356.65 1069.95 L-02
Mazdoor day 8.00 244.56 1956.48 L-13
Basic Cost of Labour & Material (a+b) 39960.00
c) Overhead charges @ 10 % on (a+b) 3996.00
d) Contractor's profit @ 10 % on (a+b+c) 4395.60
Rate per MT = a+b+c+d 48351.55 45087.00
say 48352.00 7.24%
(c)
a) Material
TMT bars including 5 per cent for laps and tonne 1.05 41525.00 43601.25 M-085_2
wastage

Binding wire Kg 8.00 70.00 560.00 M-072


b) Labour for cutting, bending, tying and
placing in position
Mate day 0.44 356.65 156.93 L-12
Blacksmith day 3.00 356.65 1069.95 L-02
Mazdoor day 8.00 244.56 1956.48 L-13
Basic Cost of Labour & Material (a+b) 47345.00
c) Overhead charges @ 10 % on (a+b) 4734.46
d) Contractor's profit @ 10 % on (a+b+c) 4734.46
Rate per MT = a+b+c+d 56813.53
say 56814.00
14.3 High tensile steel wires/strands including all
accessories for stressing, stressing operations
and grouting complete as per drawing and
Technical Specifications
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable
(weight = 0.377 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per tonne 0.39 140420.00 54061.70 M-119
cent for wastage and extra length for
jacking
Sheathing duct ID 66 mm along with 5 per metre 42.00 85.00 3570.00 M-165
cent extra length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing each 2.00 1420.00 2840.00 M-187
plate, permanent wedges etc
Cement for grouting including 3 per cent tonne 0.125 6200.00 775.00 M-084
wastage @ 3.00 kg/m = 3 x 1.03 x 40 =
123.60 kg (say, = 125 kg)
Add 0.50 per cent cost of material for 3062.34
Spacers, Insulation tape and miscellaneous
items
b) Labour

Page 55 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
i) For making and fixing cables, anchorages
Mate day 0.16 356.65 57.06 L-12
Blacksmith day 1.00 458.55 458.55 L-02
Mazdoor day 3.00 244.56 733.68 L-13
ii) For prestressing
Mate/Supervisor day 0.05 356.65 17.83 L-12
Prestressing operator / Fitter day 0.25 458.55 114.64 L-08
Mazdoor day 1.00 244.56 244.56 L-13
iii) For grouting
Mate/Supervisor day 0.05 356.65 17.83 L-12
Mason day 0.25 458.55 114.64 L-11
Mazdoor day 1.00 244.56 244.56 L-13
c) Machinery
Stressing jack with pump hour 2.50 113.00 282.50 P&M-040
Grouting pump with agitator hour 1.00 280.00 280.00 M-111
Generator 33 KVA. hour 3.50 311.00 1088.50 P&M-079
d) Overhead charges @ 10 % on (a+b+c) 6796.34
e) Contractor's profit @ 10 % on (a+b+c+d) 7475.97

Cost for 0.377 MT (a+b+c+d+e) 82235.70


Rate per MT = (a+b+c+d+e)/0.377 218131.83 122271.00
say 218132.00 78.40%
Note Cost of HT steel has been taken for delivery at site.
Hence carriage has not been considered.
14.4 Providing and laying Cement concrete wearing
coat M-30 grade including reinforcement
complete as per drawing and Technical
Specifications
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant cum 1.00 5697.00 5697.00 Item 14.1(C)
item of concrete in Item 14.1 excluding
formwork
TMT bar reinforcement Rate as per item No tonne 0.075 47001.00 3525.08 Item 14.2
14.2(Excluding OH & CP)
b) Labour
Mazdoor for cleaning deck slab concrete day 0.15 244.56 36.68 L-13
surface.
c) Overhead charges @ 10 % on (a+b) 925.88
d) Contractor's profit @ 10 % on (a+b+c) 1018.46
Rate per cum (a+b+c+d) 11203.10 8841.00
say 11203.00 26.72%
14.5 Mastic Asphalt
(A) Providing and laying 12 mm thick mastic
asphalt wearing course on top of deck slab
excluding prime coat with paving grade bitumen
meeting the requirements given in table 500-29,
prepared by using mastic cooker and laid to
required level and slope after cl

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869
cum) assuming a density of 2.3 tonnes/cum.
a) Labour

Page 56 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 0.49 356.65 174.76 L-12
Mazdoor day 11.00 244.56 2690.16 L-13
Mazdoor (Skilled) day 1.25 356.65 445.81 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 337.00 20.22 P&M-031
Air compressor 250 cfm hour 0.06 354.00 21.24 P&M-001
Mastic cooker 1 tonne capacity hour 6.00 56.00 336.00 P&M-030
Bitumen boiler 1500 litres capacity hour 6.00 1590.00 9540.00 P&M-005
Tractor for towing and positioning of mastic hour 1.00 323.00 323.00 P&M-053
cooker and bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per
cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per
cent .
Proportion of material required for mastic asphalt
with coarse aggregates (based on mix design done
by CRRI for a specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 tonne 0.204 33854.00 6906.22 M-077
per cent by weight of mix. 2 x 10.2/100 =
0.204
ii) Crusher stone dust @ 31.9 per cent by cum 0.39 698.00 272.22 M-021
weight of mix = 2 x 31.9/100 = 0.638 tonnes
= 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium tonne 0.36 6608.00 2378.88 M-188
carbonate content not less than 80 per cent
by weight @ 17.92 per cent by weight of
mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm cum 0.55 1916.00 1053.80 M-051
size @ 40 per cent by weight of mix = 2 x
40/100 = 0.8 MT = 0.8/1.456 = 0.55
v) Pre-coated stone chips of 9.5 mm cum 0.036 3528.00 127.01 M-142
nominal size for skid resistance =
72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent kg 1.05 33.85 35.55 M-077/1000
by weight = 0.036 x 1.456 x 2/100 =
0.001048MT = 1.05kg
Per Sqm Basic Cost of Labour, Material & Mechinery (a+b+c) 336.00
d) Overhead charges @ 10 % on (a+b+c) 2432.49
e) Contractor's profit @ 10 % on (a+b+c+d) 2675.73

Cost for 72.46 sqm = a+b+c+d+e 29433.08


Rate per sqm = (a+b+c+d+e)/72.46 406.20 196.00
say 406.00 107.14%
Note 1.The rates for 6 mm or any other thickness may be
worked out on pro-rata basis.
2. Where tack coat is required to be provided before
laying mastic asphalt, the same is required to be
measured and paid separately.
3.The quantities of binder, filler and aggregates are
for estimating purpose. Exact quantities shall be as
per mix design.

Page 57 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
4.This rate analysis is based on design made by
CRRI for a specific case and is meant for estimating
purposes only. Actual design is required to be done
for each case.
5.The quantity of bitumen works out 17 per cent of
the mastic asphalt blocks without aggregates and
falls within the standards laid down by MoRTH
Specifications.
(B) Providing Bituminous wearing course
comprising of tack coat with bitumen emulsion
CSS-1h as per APWD SOR item no 5.2 &
MOSRT&H Specification Nos 503 0.6mm thick
mastic asphalt as per APWD SOR item no
14.5& MOSRT&H Specification Nos 515& 2702
and 2 layers of 25 mm thick Asphalt concrete
including of close Graded Premix
Surfacing(CGPS) materials with Type -a
aggregate as per APWD SOR tem no 5.11 &
MOSRT&H Specification Nos 512 including all
lead and lift as directed.

Unit = sqm
Taking output = 1 sqm
Take coat: (I)With Bitumen emulsion CSS-1h 10.00 Item No 5.2
Per Sqm Basic Cost of Labour, Material & Machinery (I)
(a+b+c) of Item 5.2 (I)
2x25 mm thick open graded premix sufacing 342.50 Item No 5.11
Per Sqm Basic Cost of Labour, Material & Machinery (a) (I)
(a+b+c) of Item 5.11 (a) (I) @ 2x25/20
6 mm thick Mastic Asphalt wearing coarse 168.00 Item No 14.5
Per Sqm Basic Cost of Labour, Material & Machinery (A)
(a+b+c) of Item 14.5(A) @ 0.5
d) Overhead charges @ 10 % on (a+b+c) 52.05
e) Contractor's profit @ 10 % on (a+b+c+d) 57.26

Cost for 1 sqm = a+b+c+d+e 629.81


Rate per sqm = (a+b+c+d+e)/72.46 629.81
say 630.00
Note 1.The rates for 6 mm or any other thickness may be
worked out on pro-rata basis.
2. Where tack coat is required to be provided before
laying mastic asphalt, the same is required to be
measured and paid separately.
3.The quantities of binder, filler and aggregates are
for estimating purpose. Exact quantities shall be as
per mix design.
4.This rate analysis is based on design made by
CRRI for a specific case and is meant for estimating
purposes only. Actual design is required to be done
for each case.
5.The quantity of bitumen works out 17 per cent of
the mastic asphalt blocks without aggregates and
falls within the standards laid down by MoRTH
Specifications.

Page 58 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
14.6 Construction of precast RCC railing of M30
Grade, aggregate size not exceeding 12 mm,
true to line and grade, tolerance of vertical RCC
post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed
2000 mm, leaving adequate spa
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concreteM30 Grade Refer relevant cum 4.09 5697.00 23312.12 Item 14.1(C)
item of concrete in Item 14.1(C) by using
batching plant, excluding formwork i.e. per
cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos.,
External area of vertical post 0.25x0.275 =
0.069sqm, Concrete in Vertical posts =
0.069 x 28 = 1.932 cum, Hand rail in 3 tiers
= 3 x 24 = 72 m, External area = 0.170 x
0.175 = 0.03 sqm, Concrete in hand rails
Add 5 per cent of above cost for form work 1165.61
for casting in casting yard.
HYSD bar reinforcement Rate as per item tonne 0.87 47001.00 40655.87 Item 14.2
No 14.2(Excluding OH & CP)
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and 3256.68
fixing of precast panels in position
b) Overhead charges @ 10 % on (a) 6839.03
c) Contractor's profit @ 10 % on (a+b) 7522.93
Rate for 48 m (a+b+c) 82752.23
Rate per metre (a+b+c)/48 1724.00 1391.00
say 1724.00 23.94%
Note 1.Quantities of material have been adopted from
standard plans of MoRTH vide drawing no. SD/202.

2.48 m length is the total linear length adding both


sides of 24 m span.
14.7 Construction of RCC railing of M30 Grade in-
situ with 20 mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post
not to exceed 1 in 500, centre to centre spacing
between vertical post not to exceed 2000 mm,
leaving adequate space
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concreteM30 Grade Refer relevant cum 4.092 5697.00 23312.12 Item 14.1(C)
item of concrete in Item 14.1(C) by using
batching plant, excluding formwork i.e. per
cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos.,
External area of vertical post 0.25x0.275 =
0.069sqm, Concrete in vehicle posts = 0.069
x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x
24 = 72 m, External area = 0.170 x 0.175 =
0.03 sqm, Concrete in hand rails =

Page 59 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Add 12 per cent of above cost for form 2797.45
work.
HYSD bar reinforcement Rate as per item tonne 0.87 47001.00 40655.87 Item 14.2
No 14.2(Excluding OH & CP)
refer MoRTH SD / 202.
b) Overhead charges @ 10 % on (a) 6676.54
c) Contractor's profit @ 10 % on (a+b) 7344.20
Rate for 48 m (a+b+c) 80786.19
Rate per metre (a+b+c)/48 1683.05 1356.00
say 1683.00 24.12%
Note 1. Quantities of material have been adopted from
standard plans of MoRTH vide drawing no. SD/202.

2. 48 m length is the total linear length adding both


sides of 24 m span.
14.8 Providing, fitting and fixing mild steel railing
complete as per drawing and Technical
Specification
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 3.50 56160.00 196560.00 M-179
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.01 56160.00 56833.92 M-179
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.18 56160.00 10108.80 M-179
4) MS bolts, nuts and washers tonne 0.15 90000.00 13500.00 M-130*1000
Add @ 5 per cent of cost of material for 13850.14
painting one shop coat with red oxide primer
and three coats of synthetic enamel paint
and consumables to safeguard against
weathering and corrosion.
Add for cost of concrete for fixing vertical 2770.03
posts in the performed recess @ 1 per cent
of cost of material.
Add for electricity charges, welding and 2770.03
drilling equipment, electrodes and other
consumables @ 1 per cent of cost of
b) material.
Labour
Mate day 2.80 356.65 998.62 L-12
Mazdoor (Skilled) day 30.00 356.65 10699.50 L-15
Mazdoor day 40.00 244.56 9782.40 L-13
c) Overhead charges @ 10 % on (a+b) 31787.34
d) Contractor's profit @ 10 % on (a+b+c) 34966.08
Cost for 100 m steel railing = a+b+c+d 384626.85
Rate per metre (a+b+c+d)/100 3846.27 2248.00
say 3846.00 71.09%
14.9 Drainage Spouts complete as per drawing and
Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including Kg 4.00 60.00 240.00 M-090/1000
5 per cent wastage
GI pipe 100mm dia metre 6.00 680.00 4080.00 M-056
GI bolt 10 mm Dia each 6.00 13.00 78.00 M-110
Galvanised MS flat clamp each 2.00 262.00 524.00 M-101
b) Labour

Page 60 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
For fabrication
Mate day 0.02 356.65 7.13 L-12
Skilled (Blacksmith, welder etc.) day 0.02 458.55 9.17 L-02
Mazdoor day 0.02 244.56 4.89 L-13
For fixing in position
Mate day 0.01 356.65 3.57 L-12
Mason day 0.01 458.55 4.59 L-11
Mazdoor day 0.20 244.56 48.91 L-13
Add @ 5 per cent of cost of material and 250.01
labour for electrodes, cutting gas, sealant,
anti-corrosive bituminous paint, mild steel
grating etc.
c) Overhead charges @ 10 % on (a+b) 525.03
d) Contractor's profit @ 10 % on (a+b+c) 577.53
Rate per metre (a+b+c+d) 6352.83 6445.00
say 6353.00 -1.43%
Note 1. In case of viaducts in urban areas, the drainage
spouts should be connected with suitably located
pipelines to discharge the surface run-off to drains
provided at ground level.
2. In case of bridges, sufficient length of G.I Pipe
shall be provided to ensure that there is no splashing
of water from the drainage spout on the structure.

14.10 PCC M15 Grade leveling course below


approach slab complete as per drawing and
Technical specification
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) cum 1.00 5548.00 5548.00 Item 12.8 (A)
excluding formworks M15 PC
OBM
Rate per cum say 5548.00 4372.00
16.11 Reinforced cement concrete approach slab 26.90%
including reinforcement and formwork complete
as per drawing and Technical specification

Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant cum 1.00 6266.00 6266.00 Item 12.8 (G)
item of concrete in item 12.8(G)by using M30 RC
batching plant, excluding formwork i.e. per OBB P
cum basic cost (a+b+c) (Excluding OH &
CP)
( Refer relevant item of concrete in item No. 125.32
13.8 (G) except that form work may be
added at the rate of 2 per cent of cost
against 3.5 per cent provided in the
foundation concrete.
Unit rate 6391.32
(a) With TMT (Fe-500) grade rebar
TMT bar reinforcement Rate as per item No tonne 0.05 47001.00 2350.05 Item 14.2 (a)
14.2(Excluding OH & CP)
b) Overhead charges @ 10 % on (a) 874.14
c) Contractor's profit @ 10 % on(a+b) 961.55

Page 61 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Rate per cum (a+b+c) 10577.06 8513.00
say 10577.00 24.25%
(b) With make TMT grade rebar
TMT bar reinforcement Rate as per item No tonne 0.05 47001.00 2350.05 Item 14.2 (b)
14.2(Excluding OH & CP)
b) Overhead charges @ 10 % on (a) 874.14
c) Contractor's profit @ 10 % on(a+b) 961.55
Rate per cum (a+b+c) 10577.06
say 10577.00
(c) With TMT grade rebar
TMT bar reinforcement Rate as per item No tonne 0.05 46155.00 2307.75 Item 14.2 (c)
14.2(Excluding OH & CP)
b) Overhead charges @ 10 % on (a) 869.91
c) Contractor's profit @ 10 % on(a+b) 956.90
Rate per cum (a+b+c) 10525.87
say 10526.00
Note The grade of reinforced cement concrete may be
adopted as M30 for severe conditions and M25 for
moderate conditions.
16.13 Precast - pretensioned Girders
Providing, precasting, transportation and
placing in position precast pretensioned
concrete girders as per drawing and technical
specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material
Cement tonne 0.47 6200.00 2914.00 M-084
Coarse sand cum 0.45 792.00 356.40 M-004
20 mm Aggregate cum 0.54 1777.00 959.58 M-053
10 mm Aggregate cum 0.36 1916.00 689.76 M-051
Admixture @ 0.4 per cent of cement Kg 1.88 103.00 193.64 M-180
TMT steel . ( CRS Fe-500) tonne 0.10 40763.00 4076.30 M-085
HT strand with 5 per cent as wastage and tonne 0.06 140420.00 8425.20 M-119
extra length for anchoring
LDO for steam curing Litre 37.00 30.00 1110.00 M-122
Add consumables such as binding wire, 2.25
foam, packing tape, shuttering oil, HDPE
pipe for unbonding of strand, bolt & nuts etc
@ 1 per cent of material cost
b) Labour
(i) Cutting, bending, making reinforcement
cage, placing in position, binding etc. complete

Taking quantity of steel 100 Kg/cum of concrete


including laps and wastage
Mate day 0.06 356.65 21.40 L-12
Mazdoor (Skilled) day 0.35 356.65 124.83 L-15
Mazdoor day 1.40 244.56 342.38 L-13
(ii) Cable cutting and threading in position
including binding by insulation tape with HDPE
pipes etc., prestessing and cutting of extra
length of HT strand after de-stressing.
Taking quantity of HT strand 60 Kg/cum

Page 62 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Mate day 0.02 356.65 7.13 L-12
Mazdoor (Skilled) day 0.14 356.65 49.93 L-15
Mazdoor day 0.50 244.56 122.28 L-13
(iii) Erection and dismantling of shuttering
Taking shuttering area 10 sqm/cum of concrete

Mate day 0.12 356.65 42.80 L-12


Mazdoor (Skilled) day 1.00 356.65 356.65 L-15
Mazdoor day 2.00 244.56 489.12 L-13
(iv) Concreting by Batching plant and stationary
concrete pump
Mate day 0.03 356.65 10.70 L-12
Mazdoor (Skilled) day 0.05 356.65 17.83 L-15
Mazdoor day 0.60 244.56 146.74 L-13
(v) Steam curing and manual curing
Mate day 0.01 356.65 3.57 L-12
Mazdoor day 0.35 244.56 85.60 L-13
(vi) Handling of precast girder, stacking in
stockyard and again loading in trailor
Mate day 0.01 356.65 3.57 L-12
Mazdoor day 0.25 244.56 61.14 L-13
(vii) Placement of girders in position over pier
caps including placement of sand jacks,
channel, levelling etc.
Mate day 0.01 356.65 3.57 L-12
Mazdoor (Skilled) day 0.06 356.65 21.40 L-15
Mazdoor day 0.24 244.56 58.69 L-13
c) Machinery
i) At casting yard
Generator 100 KVA hour 0.05 621.00 31.05 P&M-080
Batching Plant @ 20 cum/hour hour 0.05 1590.00 79.50 P&M-002
Transit Mixer 4 cum capacity hour 0.10 828.00 82.80 P&M-049
Concrete Pump stationary hour 0.05 234.00 11.70 P&M-007
Crane 35 tonne capacity hour 0.10 759.00 75.90 P&M-012
Trailor 30 tonne capacity hour 0.10 300.00 30.00 P&M-089
Loader hour 0.05 882.00 44.10 P&M-017
ii) For transportation and placement at site
Crane 35 tonne capacity hour 0.15 759.00 113.85 P&M-012
Trailer 30 tonne capacity for transporting to tonne.km 2.5xL 2.25 56.25 Lead =10 km
site. & P&M-090

(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement. hour 0.15 300.00 45.00 P&M-089
Cost of formwork, steam curing 1052.57
arrangement, pretensioning arrangement etc
@ 5 per cent of cost material, labour and
d) machinerycharges @ 10 % on (a+b+c)
Overhead 2231.92
e) Contractor's profit @ 10 % on (a+b+c+d) 2455.11

Rate per cum = (a+b+c+d+e) 27006.20 15214.00


say 27006.00 77.51%
16.16 Painting on concrete surface

Page 63 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Providing and applying 2 coats of water based
cement paint to unplastered concrete surface
after cleaning the surface of dirt, dust, oil,
grease, efflorescence and applying paint @ of 1
litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
(A) On Plain surface
a) Labour
Mate day 0.01 356.65 3.57 L-12
Painter day 0.25 458.55 114.64 L-18
Mazdoor (Skilled) day 0.25 356.65 89.16 L-15
b) Material
Water based paint of approved quality for Litres 5.00 40.00 200.00 M-190
cement concrete surface
c) Overhead charges @ 10 % on (a+b) 40.74
d) Contractor's profit @ 10 % on (a+b+c) 44.81
Cost for 10 sqm (a+b+c+d) 492.91
Rate per sqm (a+b+c+d)/10 49.29 28.00
say 49.00 75.00%
(B) On RCC Brdge Railing @ 3.56 times over Item 3.56 175.48
No 14.16 (A)
Rate per RM 175.48
say 175.00
16.17 Burried Joint
Providing and laying a burried expansion joint,
expansion gap being 20 mm, covered with 12
mm thick, 200 mm wide galvanised weldable
structural steel plate as per IS: 2062, placed
symmetrical to centre line of the joint, resting
freely over the top surfac
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.02 356.65 7.13 L-12
Mazdoor day 0.40 244.56 97.82 L-13
Mazdoor (Skilled) day 0.20 356.65 71.33 L-15
b) Material
Galvanised M.S plate 200 mm wide,12 mm kg 237.50 52.92 12568.50 M-060/1000
thick @ 94.20 kg/sqm including 5 per cent
wastage
Add 1 per cent of cost of steel plate cutting, 125.69
welding consumables and galvanised nails.
c) Overhead charges @ 10 % on (a+b) 1287.05
d) Contractor's profit @ 10 % on (a+b+c) 1415.75
Cost for 12 m = (a+b+c+d) 15573.27
Rate per m = (a+b+c+d)/12 1297.77 1194.00
say 1298.00 8.71%
Note Guidelines laid down vide the MoRTH circular No.
RW/NH-34059/1/96-S&R dated 30.11.2000 and
subsequent corrigendum dated 25.01.2001 may be
reffered for expansion joints.
16.18 Filler joint

Page 64 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
(i) Providing & fixing 2 mm thick corrugated copper
plate in expansion joint complete as per
drawing & Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.04 356.65 14.27 L-12
Mazdoor day 0.50 244.56 122.28 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
Copper plate - 12m long x 250 mm wide kg 60.00 174.00 10440.00 M-089
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55
kg.
c) Overhead charges @ 10 % on (a+b) 1075.49
d) Contractor's profit @ 10 % on (a+b+c) 1183.04
Cost for 12 m = (a+b+c+d) 13013.39
Rate per m = (a+b+c+d)/12 1084.45 949.00
say 1084.00 14.23%
16.18 (ii) Providing & fixing 20 mm thick compressible
fibre board in expansion joint complete as per
drawing & Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 356.65 2.85 L-12
Mazdoor day 0.10 244.56 24.46 L-13
Mazdoor (Skilled) day 0.10 356.65 35.67 L-15
b) Material
20 mm thick compressible fibre board 12 m sqm 3.00 976.00 2928.00 M-087
long x 25 cm deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 10 % on (a+b) 299.10
d) Contractor's profit @ 10 % on (a+b+c) 329.01
Cost for 12 m = (a+b+c+d) 3619.08
Rate per m = (a+b+c+d)/12 301.59 266.00
say 302.00 13.53%
16.18 (iii) Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for
fixed ends of simply supported spans not
exceeding 10 m to cater for a horizontal
movement upto 20 mm, covered with sealant
complete as per drawing and technical s
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.01 356.65 3.57 L-12
Mazdoor day 0.20 244.56 48.91 L-13
Mazdoor (Skilled) day 0.10 356.65 35.67 L-15
b) Material
Premoulded joint filler 12 m long,20 mm sqm 3.90 672.00 2620.80 M-141
thick and 300 mm deep.

Page 65 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
c) Overhead charges @ 10 % on (a+b) 270.89
d) Contractor's profit @ 10 % on (a+b+c) 297.98
Cost for 12 m = (a+b+c+d) 3277.82
Rate per m = (a+b+c+d)/12 273.15 241.00
say 273.00 13.28%
16.18 (iv) Providing and filling joint sealing compound as
per drawings and technical specifications with
coarse sand and 6 per cent bitumen by weight

Unit = Running meter


Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess
a) Labour
Mate day 0.02 356.65 7.13 L-12
Mazdoor day 0.50 244.56 122.28 L-13
Mazdoor (Skilled) day 0.10 356.65 35.67 L-15
b) Material
Sand cum 0.012 792.00 9.50 M-005
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg
Bitumen cum 0.001 33854.00 33.85 M-077
16.8 x 0.06 = 1 kg
c) Overhead charges @ 10 % on (a+b) 20.84
d) Contractor's profit @ 10 % on (a+b+c) 22.93
Cost for 12 m = (a+b+c+d) 252.21
Rate per m = (a+b+c+d)/12 21.02 10.00
say 21.00 110.00%
Note For arriving at the final rate of filler joints per m
length and per cm depth of joint filling compound,
the rates at Sl. No. i), ii), iii) & iv) shall be added
16.19 Asphaltic Plug joint
Providing and laying of asphaltic plug joint to
provide for horizontal movement of 25 mm and
vertical movement of 2 mm, depth of joint
varying from 75 mm to 100 mm, width varying
from 500 mm to 750 mm (in traffic direction),
covered with a closure plate o
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.052 356.65 18.55 L-12
Mazdoor day 1.00 244.56 244.56 L-13
Mazdoor (Skilled) day 0.30 356.65 107.00 L-15
b) Material
Crushed stone aggregate 12.5 mm nominal cum 0.75 2095.00 1571.25 M-052
size
Polymer modified bitumen kg 77.50 46.40 3596.00 M-081/ 1000

2.4 Galvanised structural steel plate 200 mm kg 113.00 55.00 6215.00 M-103
wide,6 mm thick, 12 m long (2.4 sqm) @
47.10 kg/sqm including 5 per cent wastage
Add 1 per cent for welding and foam 117.52
caulking/backer rod and other incidentals.
c) Machinery
Mastic cooker 1 tonne capacity hour 1.00 56.00 56.00 P&M-030

Page 66 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Smooth 3-wheeled steel roller 8-10 capacity hour 0.50 652.00 326.00 P&M-044
d) Overhead charges @ 10 % on (a+b+c) 1225.19
e) Contractor's profit @ 10 % on (a+b+c+d) 1347.71

Cost for 12 m asphalt plug joint = (a+b+c+d+e) 14824.77


Rate per m = (a+b+c+d+e)/12 1235.40 953.00
say 1235.00 29.59%
Note The nominal size of aggregates shall be 12.5 mm for
depth of joint upto 75 mm and 20 mm for joints of
depth more than 75 mm.
16.20 Elastomeric Slab Steel Expansion Joint
Providing and laying of an elastomeric slab
steel expansion joint, catering to right or skew
(less than 20 deg., moderately curved with
maximum horizontal movement upto 50 mm,
complete as per approved drawings and
standard specifications to be installed b
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.06 356.65 21.40 L-12
Mazdoor day 1.00 244.56 244.56 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
Supply of elastomeric slab seal expansion metre 12.00 16400.00 196800.00 M-096
joint assembly manufactured by using
chloroprene, elastomer for elastomeric slab
unit conforming to clause 915.1 of IRC: 83
(part II), complete as per approved drawings
and standard specification conforming to cla
Add 5 per cent of cost of material for 9840.00
anchorage reinforcement, welding and other
incidentals.
c) Overhead charges @ 10 % on (a+b) 20708.43
d) Contractor's profit @ 10 % on (a+b+c) 22779.27
Cost for 12 m = (a+b+c+d) 250571.98
Rate per m = (a+b+c+d)/12 20881.00 12664.00
say 20881.00 64.88%
16.21 Compression Seal Joint
Providing and laying of compression seal joint
consisting of steel armoured nosing at two
edges of the joint gap suitably anchored to the
deck concrete and a preformed chloroprene
elastomer or closed cell foam joint sealer
compressed and fixed into the jo
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.036 356.65 12.84 L-12
Mazdoor day 0.60 244.56 146.74 L-13
Mazdoor (Skilled) day 0.30 356.65 107.00 L-15
b) Material

Page 67 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
1. Galvanised angle sections 100mm x kg 446.00 55.00 24530.00 M-103
100mm of 12mm thickness weldable
structural steel as per IS: 2062, 2 nos. of 12
m length each @ 17.7 kg/m and 5 per cent
wastage.
Add 5 per cent of cost of above for 1239.83
structural steel for anchorage, welding and
other incidentals.
Preformed continuous chloroprene metre 12.00 8000.00 96000.00 Err:509
elastomer or closed cell foam sealing
element with high tear strength, vulcanised
in a single operation for the full length of a
joint to ensure water tightness.
Add 1 per cent of cost of sealing element for 960.00
lubricant-cum-adhesive and other
consumables.
c) Overhead charges @ 10 % on (a+b) 12299.64
d) Contractor's profit @ 10 % on (a+b+c) 13529.60
Cost for 12 m = (a+b+c+d) 148825.64
Rate per m = (a+b+c+d)/12 12402.14 12994.00
say 12402.00 -4.56%
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
16.22 Strip Seal Expansion Joint
Providing and laying of a strip seal expansion
joint catering to maximum horizontal movement
upto 70 mm, complete as per approved
drawings and standard specifications to be
installed by the manufacturer/supplier or their
authorised representative ensuring

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.05 356.65 17.83 L-12
Mazdoor day 1.00 244.56 244.56 L-13
Mazdoor (Skilled) day 0.25 356.65 89.16 L-15
b) Material
Supply of complete assembly of strip seal metre 12.00 4602.00 55224.00 M-178
expansion joint comprising of edge beams,
anchorage, strip seal element and complete
accessories as per approved specifications
and drawings.
Add 5 per cent of cost of material for 2778.78
anchorage reinforcement, welding and other
incidentals.
c) Overhead charges @ 10 % on (a+b) 5835.43
d) Contractor's profit @ 10 % on (a+b+c) 6418.98

Page 68 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Cost for 12 m = (a+b+c+d) 70608.74
Rate per m = (a+b+c+d)/12 5884.06 11103.00
say 5884.00 -47.01%
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
16.23 Modular Strip / Box Seal Joint
Providing and laying of a modular strip Box seal
expansion joint including anchorage catering to
a horizontal movement beyond 70 mm and upto
140mm, complete as per approved drawings
and standard specifications to be installed by
the manufacturer/supplier

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.056 356.65 19.97 L-12
Mazdoor day 1.00 244.56 244.56 L-13
Mazdoor (Skilled) day 0.40 356.65 142.66 L-15
b) Material
Supply of a modular strip/box seal joint metre 12.00 76700.00 920400.00 M-127
assembly comprising of edge beams, central
beam,2 modules chloroprene seal,
anchorage elements, support and control
system, all steel sections protected against
corrosion and installed by the manufacturer
or his au

c) Overhead charges @ 10 % on (a+b) 92080.72


d) Contractor's profit @ 10 % on (a+b+c) 101288.79
Cost for 12 m Modular strip/box seal joint = 1114176.70
(a+b+c+d)
Rate per m = (a+b+c+d)/12 92848.06 137296.00
say 92848.00 -32.37%
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
16.24 Modular Strip / Box Seal Joint
Providing and laying of a modular strip box seal
expansion joint catering to a horizontal
movement beyond 140mm and upto 210mm,
complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised

Page 69 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.07 356.65 24.97 L-12
Mazdoor day 1.25 244.56 305.70 L-13
Mazdoor (Skilled) day 0.50 356.65 178.33 L-15
b) Material
Supply of a modular box/box seal joint metre 12.00 129800.00 1557600.00 M-128
assembly containing 3 modules/cells and
comprising of edge beams, two central
beams, chloroprene seal, anchorage
elements, support and control system, all
steel sections protected against corrosion
and installed by t

c) Overhead charges @ 10 % on (a+b) 155810.90


d) Contractor's profit @ 10 % on (a+b+c) 171391.99
Cost for 12 m Modular strip/box seal joint = 1885311.88
(a+b+c+d)
Rate per m = (a+b+c+d)/12 157109.32 221120.00
say 157109.00 -28.95%
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
16.25 Extra for providing water proofing compound
( Providing and applying cement
mortar(1 cement 3 sand) with STRUCO LATEX or its
equivalent as per specification and as directed by
the Department
Unit = Per suare mtere
Taking output = 100(One hundred) square
metre.
a) Labour
Mazdoor day 22 97 2134.00
Mazdoor(Skilled) day 11 102 1122.00
b) Material
Cement tonne 0.6500 7600.00 4940.00 M-084
Sand cum 1.900 1251.00 2376.90 M-005
STRUCO LATEX Kg 15 82 1230.00
c) Overhead charges @ 10 % on (a+b) 2360.58
d) Contractor's profit @ 10 % on (a+b+c) 1416.35
Cost of providing 100 sqm of waterproofing 15579.83
=(a+b+c+d)
Rate per m2 = (a+b+c+d)/100 155.80 159.00
say 156.00 -1.89%

Page 70 of 1351
Analysisof SOR (Roads) 2009-10
Chapter-14

Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
16.26 Extra item for providing water proofing
compound
( clean the surfaces and applying two coats of
ARMOURCRETE as per specification or its
equivalent as per specification and as directed by
the Department
Unit = Per suare mtere
Taking output = 1 (One) square meter
a) Labour & Scafolding 40.00
b) Tools & tackles 12.00
c) Material
Cement tonne 0.0080 7600.00 60.80 M-084
ARMOURCRETE Kg 0.500 193.00 96.50
d) Profit & Overlays @ 15% on (a+b+c) 31.40
240.70 176.00
say 241.00 36.93%

Page 71 of 1351
Chapter 17
NEW TECHNOLOGY
Sr. Reference Rate
Description Unit Quantity
No. to Spec (Rs.)
17.1 Open - Graded Premix Surfacing (specially for
IRC SP: 100: shaded areas)
Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to
5.6 mm aggregates either using Bitumen Emulsion
With cold mix Binder Ezee PC (MS) (As per IRC : SP :
100 -2014) to required line, grade and level to serve as
wearing course on a per Technical Specification and
through credible technology partners duly licensed by
CRRI.

CRRI- Cold Mix Binder Ezee PC (Medium


Setting) (specially for shaded areas)
Unit = sqm
Taking output = 900 sqm (24.3 cum)
a) Labour
Mate day 0.800 356.65
Mazdoor day 18.000 244.56
Mazdoor skilled day 2.000 356.65
b) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 6.000 188.00
Smooth wheeled steel roller 8-10 tonne hour 6.000 652.00
c) Material
CRRI Cold Mix Binder Ezee PC (MS) Bitumen tonne 1.800 45500.00
Emulsion @ 20.00 kg per 10 sqm
Crushed stone aggregates 13.2 mm to 5.6 mm cum 24.300 1599.50
@ 0.27 cum per 10 sqm
TOTAL = (a+b+c)
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Cost for 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
say

17.2 Seal coat with Cold mix Binder (specially for


shaded areas) - Providing and laying seal coat
sealing the voids in a bituminous surface laid to the
specified levels grade and cross fall using Type A,Type
B and Type C as per Technical specification clause
510.With cold mix Binder Ezee PC (MS) (As per IRC :
SP : 100 -2014)and through credible technology
partners duly licensed by CRRI.
IRC SP: 100:
CRRI- Cold Mix Binder Ezee PC (Medium
Setting) (specially for shaded areas)
By mechanical means
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate day 1.15 356.65
Bitumen Sprayer day 1 356.65
Mazdoor (Unskilled) day 22 244.56
Mazdoor (Semi-Skilled) day 6 356.65
b) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 6 188
Three wheel 80-100 kN static roller hour 2.2 652

c) Material
Bitumen emulsion Ezee PC medium setting @ 10.00 t 0.11 45500.00
kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent cum 9.9 1807.00
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm
Total (a+b+c) =
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Cost of 1100 sqm = a+b+c+d+e

Rate per sqm = (a+b+c+d)/1100

Say

Since seal coat is provided immediately over the bituminous layers, Hydraulic broom for cleaning
has not been catered.
Note Since seal coat is required to be provided over the premix carpet on the same day, out of the 6
working hours of the HMP, 4.00 hours are proposed to be utilised for the premix carpet and the
balance 2.00 hours for the seal coat. Hence 2.00 hours have been

17.3 __ Construction of Sub-Base/Base of road pavement by


making use of EVOCRETE CCL Soil Modifier
(GERMAN) technology by re-using the existing/in-
situ soil. Profiling the road to the required design
standard followed by spreading of 7% of O.P.C. 43
Grade cement of stabilized soil (Variable depending
upon soil properties) , then spreading 2 % EVOCRETE
additive of 7 % OPC and pulverising the cement ,
additive & profiled soil/pavment material with help of
Recycler/Stabilizer including moisturing to OMC. On
completion of pulverisation re-garding, profiling to
required grade/camber with motor grader &
compacting simaltaneously with 14 tonne vibratory
roller to achieve 95% degree of compaction as
directed by the Engineer-in-charge & finally irrigating
the stabilized surface for next 48 hours.

20.0cm thick Sub-Base & Base with Evocrete and


Cement etc.
Unit = Cum
Taking output = 750 Cum
a) Labour
Mate day 1.000 356.65
Mazdoor day 15.000 244.56
Mazdoor skilled day 15.000 356.65
b) Machinery
Heavy Duty Stabilizer/Recycler with moisture hour 12.500 14405.00
controlling meter@ 60cum/hour
Motor Grader 110 HP @50 cum / hour hour 12.500 2795.00
Vibratory Road Roller @ 100 cum / hour hour 7.500 1421.00
Tandem Road Roller @ 30 cum / hour (considering hour 12.500 652.00
50% of thickness )
Water tanker 12 kl capacity hour 17.250 432.00
c) Material
Cement @ 126 kg/ cum tonne 94.500 7900.00
Evocrete at site @ 2.52 kg/ cum Kg 1890.000 630.00
Soil (Extra Lead as per schedule) cum/km
Water (For mixing during stabilization) kl 195.000 40.00
Water (Irrigating during curing) Kl 12.000 40.00
TOTAL = (a+b+c)
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Cost for 750 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/750
say
17.4 Bio Enzyme Soil Stabilizer Terrazyme under IRC
accredited new Technology
I 2503 Providing of 1st layer of Bioenyme based soil
stabilised layer to a required thickness as per
manufacture design with a existing soil, by ripping
open the existing road formation and treating it with
TerraZyme in the ratio 1L for 12.6 cum soil spreading
in uniform layer with motor grader on prepared surface
, mixing by mix in place method with rotavator at OMC
and compacting with smooth wheel roller to achieve
the desired density complete as per technical
specification incl all labour , equipments etc as per
direction of the Engineer -in -charge of the work. The
soil will have PI between 7 and 18% and clay % by
hydrometry should be more than 15% and less than
40%.

Unit = cum
Taking output = 300 cum
a) Material
Cost Bio Enzyme Litre 24.00 13500.00
Water KL 100.00 40.00
Cost of Soil Cum 0.00 155.00
Cost of Metal 37.5 mm to 22.5 mm Cum 0.00 1127.00
b) Labour
Mate day 0.04 356.65
Mason day 0.35 458.55
Mazdoor * day 0.75 244.56
c) Machinaries
(i) Pre TerraZyme Application
Tractor with a ripper @ 60 cum/hr hr 5.00 440.00
Tractor with a rotavator @ 25 Cum/ hr 12.00 431.00
Water tanker 6 Kl capacity hr 5.00 432.00
(ii) Post TerraZyme Application
Tractor mount grader @25 cum/hr hr 12.00 431.00
Vibromax soil compactor 100 cum/hr hr 5.00 1421.00
Tractor with a ripper @ 60 cum/hr hr 5.00 440.00
Tractor with a rotavator @ 25 Cum/ hr 12.00 431.00
Water tanker 6 Kl capacity hr 5.00 432.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d+e)/300
say
II Providing of 2nd layer of Bioenyme based soil
stabilised layer to a required thickness as per
manufacture design with local soil
material/gravel/murram, having CBR greater than 8%
and treating it with Terrazyme in the ratio 1L for 15.0
cum soil with 25% 40mm crusher broken metal in
design mix, spreading in uniform layer with tractor
grader on prepared surface, mixing by mix in place
method with rotavator at OMC and compacting with
smooth wheel roller to achieve the desired densiality
complete as per technical specification including all
labour, materials like soil and metal, equipments etc.
complete as per direction of the Engineer-in-charge of
the work. The soil will have PI between 7 and 13% and
clay % by hydrometry should be more than 15% and
less than 30%.

Unit = cum
Taking output = 300 cum
a) Material
Cost Bio Enzyme Litre 15.00 13500.00
Water KL 100.00 40.00
Cost of specified Soil 300*0.75 Cum 225.00 200.00
Cost of Metal 300*0.25 Cum 75.00 1127.00
b) Labour
Mate day 0.48 169.00
Mazdoor (Skilled) day 2.00 175.00
Mazdoor (Unskilled) day 10.00 169.00
c) Machinaries
(i) Pre TerraZyme Application
Tractor mount Grader @ 25 cum/hr hr 0.00 431.00
Vibromax soil compactor 100 cum/hr hr 0.00 1421.00
Tractor with a ripper @ 60 Cum/hr hr 5.00 440.00
Tractor with a rotavator @ 25 Cum/hr hr 12.00 431.00
Water tanker 6 Kl capacity hr 5.00 432.00
(ii) Post TerraZyme Application
Tractor mount grader @ 25 cum/hr hr 12.00 431.00
Vibromax soil compactor 100 cum/hr hr 5.00 1421.00
Tractor with a ripper @ 60 cum/hr hr 5.00 440.00
Tractor with a rotavator @ 25 Cum/hr hr 12.00 431.00
Water tanker 6 Kl capacity hr 5.00 432.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d+e)/300
say
17.5 Soil Stablized subbase/ base using Roadstab
I 2503 Providing of soil stabilized subase/base course by
providing,laying and spreading ordinary soil on a
prepared subgrade,palverising,adding the designed
quantity of Roadstab mixing compound adding 4%
cement, mixing at OMC,with rotavator grading with
motor grader and compacting with the road
roller/vibratory roller at OMC to acheive the desired
unconfined compression strength and to form a layer
of subbase and necessary curing

Unit = cum
Taking output = 300 cum
a) Material
100% Local soil Cum 300.00 79.00
RoadstaB Q Litre 40.00 18200.00
4% Cement Tonne 24.00 7900.00
Cost of water KL 30.00 40.00
b) Labour
Mate day 9.00 356.65
Mason day 0.00 458.55
Mazdoor * day 0.00 244.56
c) Machinaries
Hydraulic Excavator 0.9/1.0 cum Hrs 4.00 1485.00
Motor Grader Hrs 6.00 2795.00
Tipper 5.5 cum/10 tonne capacity Hrs 18.18 680.00
Tractor with roatavator Hrs 12.00 431.00
Vibratory Roller Hrs 3.90 1421.00
Water Tank 6 kl Capacity (Truck mounted) Hrs 3.00 432.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.6 RBI Grade 81 Treated Base Layer
A For Selected soil having CBR 5% to 6%
I Providing, laying, spreading and compacting Soil
conforming to engineering requirement and Aggregate
in base layer including in situ mixing of 30%
Aggregatesof size 22.4 mm to 2.56 mm (for WMM as
per page 154 of Assam SOR 2016-17 for rural road &
table 400.13 & technical specification clause 406 of
MORTH 5th Revision) + 20% Stone dust+46% in-situ
soil (CBR 5% to 6%) + 4% RBI Grade-81 (a soil
stabilizer cum pavement material) , speading in
uniform layers with motor grader on prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required
density at OMC for preparing the base layer including
all cost of materials , labour, HOM of machinery, etc.
complete as per specifications and EIC directions.

Composition 30% Aggregate + 20% Stone Dust + 46% Soil (CBR 5% to


6%) + 4% RBI Grade 81 (SRSPL) (by weight of Aggregate,
Stone Dust & In-Situ Soil Mix Material

Unit =Cum
Taking Output =300 Cum
a) Material
Agreegate 22.4 mm to 2.36 mm for WMM as Cum 108.90 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust (20%) Cum 69.00 700.00
In-situ Soil (CBR 5% to 6%) (46%) Cum 172.50 100.00
Quantity of RBI Grade 81 by weight (4%) Cum 25.20 35000.00
b) Labour
Mate day 0.48 356.65
Mazdoor (Skilled) (L-017) day 2.00 458.55
Mazdoor (Unskilled) (L-15) day 10.00 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity Hour 6.00 1485.00
Motor Grader Scarifier & Levelling Hour 6.00 2795.00
Single drum 10-12 tone Vibratory roller Hour 6.00 1421.00
Tractor with Rotavator and blade @ 25 cum Hour 12.00 431.00
per hour
Water tanker 6 KL capacity Hour 5.00 432.00
Tipper 5.5 cum /10T , 4 trip per hour Hour 13.64 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
B RBI Grade-81 FOR EXISTING IN-SITU SOIL HAVING
CBR 5% TO 6%
Providing, laying, spreading and compacting including
mixing of In-situ Soil (CBR 5% to 6%), Aggregate size
22.4 mm to 2.56 mm (for WMM as per page 154 of
ASSAM SOR 2016-17 for Rural Roads and Table
400.13 & Technocal Specification clause 406 of
MORT&H 5th Revision) and Stone Dust with Soil
Stabiliser and Pavement Material RBI Grade 81
(SRSPL), spreading in uniform layers with motor
grader on prepared sub-base / sub-grade including
watering and compacting with 10 to 12 tonne single
drum vibratory roller to achieve the desired density for
preparing the Base / Sub-base layer.

Including basic cost of


materials, labour, HOM of machinary, etc. as per
specifications and EIC directions.
The rate mentioned
here are exclusive of carriage charge of Aggregates / Stone
Dust / Selected Soil from quarry to site. The carriage charge
will be added to these rates to arrive at final rate.

Various combinations of Aggregates, Stone Dust Insitu


Soil and RBI grade 81 percentages have been given. The
optimum combination would depend upon the following
factors:
1. In Situ Soil CBR
and PI.
2. Traffic Catagory.

3. Distance of Quarry from Site


For further increasing the
durability of the road, out of the combinitations as bellow the
combination with higher percentage of RBI Grade-81 should
be prepared so long as commercial viability is maintained.
I Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base layer including in situ mixing of 30%
Aggregate of size 22.4 mm to 2.56 mm ( for WMM as
per page 154 of ASSAM SOR 2016-17 for rural roads
& Table 400.13 & technical specification clause 406 of
MORTH 5th Revision) + 30% Stone Dust + 36% In-
Situ Soil (CBR 5 % to 6 %) + 4 % RBI Grade-81 (a soil
stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including
all cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions

Composition: 30% Aggregate + 30% Stone Dust + 36% Soil


Unit =Cum (CBR 5% to 6%) + 4% RBI Grade 81 (SRSPL) (by
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as Cum 108.90 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust (30%) Cum 103.50 700.00
In-Situ Soil (CBR 5 % to 6 %) (36%) Cum 135.00 100.00
Quantity of RBI Grade-81 by weight (4%) MT 25.20 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2.00 458.55
Mazdoor (Unskilled) ( L-15) day 10.00 244.56
c) Machinery
Hydraulic Excavator 0.9 cum bucket capacity hour 6.00 1485.00
Motor Grader Scarifier & Levelling hour 6.00 2795.00
Single Drum 10-12 tonne Vibratory roller hour 6.00 1421.00
Tractor with Rotavator and blade @25 cum hour 12.00 431.00
per hour
Water tanker 6 KL capacity hour 5.00 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
II Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base layer including in situ mixing of 30%
Aggregate of size 22.4 mm to 2.56 mm ( for WMM as
per page 154 of ASSAM SOR 2016-17 for rural roads
& Table 400.13 & technical specification clause 406 of
MORTH 5th Revision) + 20% Stone Dust + 46% In-
Situ Soil (CBR 5 % to 6 %) + 4 % RBI Grade-81 (a soil
stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including
all cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions

Composition: 30% Aggregate + 20% Stone Dust + 46% Soil (CBR 5% to


Unit =Cum 6%) + 4% RBI Grade 81 (SRSPL) (by weight of Aggregate,
density = 2.1 gm/cc
Taking Output = 300 Cum
630 mt
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 108.90 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust (20%) cum 69.00 700.00
In-Situ Soil (CBR 5 % to 6 %) (46%) cum 172.50 100.00
Quantity of RBI Grade-81 by weight (4%) MT 25.20 35000.00
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2.00 458.55
Mazdoor (Unskilled) ( L-15) day 10.00 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6.00 1485.00
Motor Grader Scarifier & Levelling hour 6.00 2795.00
Single Drum 10-12 tonne Vibratory roller hour 6.00 1421.00
Tractor with Rotavator and blade @25 cum hour 12.00 431.00
per hour
Water tanker 6 KL capacity hour 5.00 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.64 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
III Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base layer including in situ mixing of 30%
Aggregate of size 22.4 mm to 2.56 mm ( for WMM as
per page 154 of ASSAM SOR 2016-17 for rural roads
& Table 400.13 & technical specification clause 406 of
MORTH 5th Revision) + 30% Stone Dust + 36.25 %
In-Situ Soil (CBR 5 % to 6 %) + 3.75 % RBI Grade-81
(a soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including
all cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions

Composition: 30% Aggregate + 30% Stone Dust + 36.25% Soil (CBR 5% to


Unit =Cum 6%) + 3.75% RBI Grade 81 (SRSPL) (by weight of Aggregate,
Taking Output =300 Cum
Density = 2.1 gm/cc
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 109 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust(30%) cum ### 700.00
In-Situ Soil (CBR 5 % to 6 %) (36.25%) cum 136 100.00
Quantity of RBI Grade-81 by weight (3.75%) MT 23.6 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1485
Motor Grader Scarifier & Levelling hour 6 2795
Single Drum 10-12 tonne Vibratory roller hour 6 1421
Tractor with Rotavator and blade @25 cum hour 12 431
per hour
Water tanker 6 KL capacity hour 5 432
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
IV Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base layer including in situ mixing of 30%
Aggregate of size 22.4 mm to 2.56 mm ( for WMM as
per page 154 of ASSAM SOR 2016-17 for rural roads
& Table 400.13 & technical specification clause 406 of
MORTH 5th Revision) + 20% Stone Dust + 46.25% In-
Situ Soil (CBR 5 % to 6 %) + 3.75 % RBI Grade-81 (a
soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including
all cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions

Composition: 30% Aggregate + 20% Stone Dust + 46.25% Soil (CBR 5% to


Unit =Cum 6%) + 3.75% RBI Grade 81 (SRSPL) (by weight of Aggregate,
Taking Output =300 Cum
Density = 2.1 gm/cc
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 109 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust(20%) cum ### 700.00
In-Situ Soil (CBR 5 % to 6 %) (46.25%) cum 173 100.00
Quantity of RBI Grade-81 by weight (3.75%) MT 23.6 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1485
Motor Grader Scarifier & Levelling hour 6 2795
Single Drum 10-12 tonne Vibratory roller hour 6 1421
Tractor with Rotavator and blade @25 cum hour 12 431
per hour
Water tanker 6 KL capacity hour 5 432
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
V Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base layer including in situ mixing of 30%
Aggregate of size 22.4 mm to 2.56 mm ( for WMM as
per page 154 of ASSAM SOR 2016-17 for rural roads
& Table 400.13 & technical specification clause 406 of
MORTH 5th Revision) + 30% Stone Dust + 36.5 % In-
Situ Soil (CBR 5 % to 6 %) + 3.5 % RBI Grade-81 (a
soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including
all cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions

Composition 30% Aggregate + 30% Stone Dust + 36.5 % In-Situ Soil (CBR
Unit =Cum 5 % to 6 %) + 3.5 % RBI Grade-81
Taking Output =300 Cum
Density = 2.1 gm/cc
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 109 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust(30%) cum ### 700.00
In-Situ Soil (CBR 5 % to 6 %) (36.5%) cum 137 100.00
Quantity of RBI Grade-81 by weight (3.5%) MT 22.1 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1485
Motor Grader Scarifier & Levelling hour 6 2795
Single Drum 10-12 tonne Vibratory roller hour 6 1421
Tractor with Rotavator and blade @25 cum hour 12 431
per hour
Water tanker 6 KL capacity hour 5 432
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
VI Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base layer including in situ mixing of 30%
Aggregate of size 22.4 mm to 2.56 mm ( for WMM as
per page 154 of ASSAM SOR 2016-17 for rural roads
& Table 400.13 & technical specification clause 406 of
MORTH 5th Revision) + 20% Stone Dust + 46.5% In-
Situ Soil (CBR 5 % to 6 %) + 3.5 % RBI Grade-81 (a
soil stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including
all cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions

Composition 30% Aggregate + 20% Stone Dust + 46.5% In-Situ Soil (CBR
Unit =Cum 5 % to 6 %) + 3.5 % RBI Grade-81
Taking Output =300 Cum
Density = 2.1 gm/cc
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 109 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust(20%) cum ### 700.00
In-Situ Soil (CBR 5 % to 6 %) (46.5%) cum 174 100.00
Quantity of RBI Grade-81 by weight (3.5%) MT 22.1 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1485
Motor Grader Scarifier & Levelling hour 6 2795
Single Drum 10-12 tonne Vibratory roller hour 6 1421
Tractor with Rotavator and blade @25 cum hour 12 431
per hour
Water tanker 6 KL capacity hour 5 432
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
RBI GRADE 81 - 2%
VII Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in sub base layer including in situ mixing of
30% Aggregate of size 22.4 mm to 2.56 mm ( for
WMM as per page 154 of ASSAM SOR 2016-17 for
rural roads & Table 400.13 & technical specification
clause 406 of MORTH 5th Revision) + 20% Stone
Dust + 48% In-Situ Soil (CBR 5 % to 6 %) + 2 % RBI
Grade-81 (a soil stabilizer cum pavement material),
spreading in uniform layers with motor grader on a
prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve
the required density at OMC for preparing the base
Layer Including all cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions

Composition 30% Aggregate + 20% Stone Dust + 48% In-Situ Soil (CBR 5
Unit =Cum % to 6 %) + 2 % RBI Grade-81
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 108.90 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust (20%) cum 69 700
In-Situ Soil (CBR 5 % to 6 %) (48%) cum 180 100
Quantity of RBI Grade-81 by weight (2%) MT 12 35000
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1485
Motor Grader Scarifier & Levelling hour 6 2795
Single Drum 10-12 tonne Vibratory roller hour 6 1421
Tractor with Rotavator and blade @25 cum hour 12 431
per hour
Water tanker 6 KL capacity hour 5 432
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
C For Selected Soil Having CBR 7% to 9%
RBI GRADE -81--4%
Providing , laying spreading and compacting
inncluding in situ mixing of selected soil (CBR 7% to
9%), Aggregate of size 22.4 mm to 2.56 mm (for WMM
as per page 154 of ASSAM SOR 2016-17 for rural
roads & Table 400.13 & technical specification clause
408 of MORTH 5th Revision) & Stone Dust with Soil
Stabilizer and PavementMaterial RBI Grade 81
(SRSPL) , spreading in uniform layers with Motor
grader on a prepared subbase including watering and
compacting with 10 to 12 tonne single drum vibratory
roller to achieve the desired density for preparing the
base layer including basic cost of materials,
labour,HOM of machinearyetc, complete as per
specification and EIC directions.
The rates mentioned here are Exclusive of carriage
charges for Agrregate/ Stone Dust/ Setected Soil from
quarry to site . The carriage charges will be added to
these rates to arrive at final rate.
Various combinations of in-situ soil/selected soil,
aggregate and RBI percentages have been given, The
optimum combination would depend upon the
following factors:
1. In-situ soil/selected soil (as applicable), CBR, and PI
2. Traffic Category
3. Distance of Quarry from site

I Providing, laying, spreading and compacting Soil


conforming to engineering requirements and
Aggregate in base course including in situ mixing of 45
% Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural
roads & Table 400.13 & technical specification clause
406 of MORTH 5th Revision) + 51 % Selected Soil
(CBR 7 % to 9 %) + 4 % RBI Grade-81 (a soil
stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including
all cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions

Composition 45 % Aggregate + 51 % Selected Soil (CBR 7 % to 9 %) + 4


Unit =Cum % RBI Grade-81
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 163 845
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (45%)
Stone Dust (0%) cum 0 700
Selected Soil (CBR 7 % to 9 %) (51%) cum 191 155
Quantity of RBI Grade-81 by weight (4%) MT 25.2 35000
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1485.00
Motor Grader Scarifier & Levelling hour 6 2795.00
Single Drum 10-12 tonne Vibratory roller hour 6 1421.00
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)

Rate per cum = (a+b+c+d)/300


say
II Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base course including in situ mixing of 30
% Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural
roads & Table 400.13 & technical specification clause
406 of MORTH 5th Revision) + 15 % Stone Dust + 51
% Selected Soil (CBR 7 % to 9 %) + 4 % RBI Grade-
81 (a soil stabilizer cum pavement material), spreading
in uniform layers with motor grader on a prepared
base including watering and compacting with 10 to 12
tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions

Composition 30% Aggregate+15% stone dust+ 51% Selected Soil(CBR7%


Unit =Cum to 9%)+4% RBI Grade -81(SRSPL)by weight of Aggregate ,
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 109 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust (15%) cum 51.8 700.00
Selected Soil (CBR 7 % to 9 %) (51%) cum 191 155.00
Quantity of RBI Grade-81 by weight (4%) MT ### ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
III Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base course including in situ mixing of 45
% Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural
roads & Table 400.13 & technical specification clause
406 of MORTH 5th Revision) + 51.25 % Selected Soil
(CBR 7 % to 9 %) + 3.75 % RBI Grade-81 (a soil
stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including
all cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions

Composition 45% Aggregate+ 51.25% Soil(CBR 7%to 9%)+3.75% RBI


Unit =Cum Grade -81(SRSPL)by weight of Aggregate , SelectedSoil Mix
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 163 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (45%)
Stone Dust (0%) cum 0 700.00
Selected Soil (CBR 7 % to 9 %) (51.25%) cum ### 155.00
Quantity of RBI Grade-81 by weight(3.75%) MT ### ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
D RBI GRADE 81-3.75%
I Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base course including in situ mixing of 30
% Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural
roads & Table 400.13 & technical specification clause
406 of MORTH 5th Revision) + 15 % Stone Dust +
51.25 % Selected Soil (CBR 7 % to 9 %) + 3.75 %
RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor
grader on a prepared base including watering and
compacting with 10 to 12 tonne single drum vibratory
roller to achieve the required density at OMC for
preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as
per specifications and EIC directions

Composition 30% Aggregate+15% stone dust +51.25% Soil(CBR 7%to 9%)


Unit =Cum +3.75% RBI Grade -81(SRSPL)by weight of Aggregate ,
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 109 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust (15%) cum 51.8 700.00
Selected Soil (CBR 7 % to 9 %) (51.25%) cum 192 155.00
Quantity of RBI Grade-81 by weight(3.75%) MT 23.6 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
II Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base course including in situ mixing of 45
% Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural
roads & Table 400.13 & technical specification clause
406 of MORTH 5th Revision) + 51.5 % Selected Soil
(CBR 7 % to 9 %) + 3.5 % RBI Grade-81 (a soil
stabilizer cum pavement material), spreading in
uniform layers with motor grader on a prepared base
including watering and compacting with 10 to 12 tonne
single drum vibratory roller to achieve the required
density at OMC for preparing the base Layer Including
all cost of materials, labour, HOM of machinery, etc
complete as per specifications and EIC directions

Composition 45% Aggregate+ 51.5% Selected soil (CBR7%to 9%)+3.5%


Unit =Cum RBI Grade -81
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 163 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (45%)
Stone Dust(0%) cum 0 700.00
Selected Soil (CBR 7 % to 9 %)(51.50%) cum ### 155.00
Quantity of RBI Grade-81 by weight(3.5%) MT 22.1 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
RBI GRADE 81-3.5%
III Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base course including in situ mixing of 30
% Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural
roads & Table 400.13 & technical specification clause
406 of MORTH 5th Revision) + 15 % Stone Dust +
51.5 % Selected Soil (CBR 7 % to 9 %) + 3.5 % RBI
Grade-81 (a soil stabilizer cum pavement material),
spreading in uniform layers with motor grader on a
prepared base including watering and compacting with
10 to 12 tonne single drum vibratory roller to achieve
the required density at OMC for preparing the base
Layer Including all cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions

Composition 30% Aggregate+15% Stone Dust+51.5% Selected Soil(CBR


Unit =Cum 7% to 9%)+3.5% RBI Grade -81
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 109 845
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust (15%) cum 51.8 700
Selected Soil (CBR 7 % to 9 %) (51.50%) cum ### 155
Quantity of RBI Grade-81 by weight (3.5%) MT 22.1 35000
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1485
Motor Grader Scarifier & Levelling hour 6 2795
Single Drum 10-12 tonne Vibratory roller hour 6 1421
Tractor with Rotavator and blade @25 cum hour 12 431
per hour
Water tanker 6 KL capacity hour 5 432
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
RB! GRADE 81-2%
IV Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base course including in situ mixing of 30
% Aggregate of size 22.4 mm to 2.56 mm ( for WMM
as per page 154 of ASSAM SOR 2016-17 for rural
roads & Table 400.13 & technical specification clause
406 of MORTH 5th Revision) + 15 % Stone Dust + 53
% Selected Soil (CBR 7 % to 9 %) + 2 % RBI Grade-
81 (a soil stabilizer cum pavement material), spreading
in uniform layers with motor grader on a prepared
base including watering and compacting with 10 to 12
tonne single drum vibratory roller to achieve the
required density at OMC for preparing the base Layer
Including all cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions

Composition 30% Aggregate+ 15% Stone Dust+53% Soil(CBR7%to 9%)


Unit =Cum +2% RBI Grade -81
Taking Output =300 Cum
a) Material
Aggregate 22.4 mm to 2.36 mm for WMM as cum 109 845.00
per Table 400.13 & Technical Specification
Clause 406 of MORTH 5th Revision (30%)
Stone Dust (15%) cum 51.8 700.00
Selected Soil (CBR 7 % to 9 %)(53%) cum 199 155.00
Quantity of RBI Grade-81 by weight(2%) MT 12 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
E 40% AGGREGATE 20MM + SOIL (CBR 7% TO 9%) +
RBI GRADE-81(SRSPL)
I Providing,laying,spreading and compacting including
in situ mixing of selected soil aggregate of size 20mm
with soil stabiliser and pavemebt material RBI Grade-
81 (SRSPL), spreading in uniform layers with Motor
grader on a prepared sub base icluding watering and
compacting with 10 to 12 tonne single drum vibratory
roller to achieve the desired density for preparing the
base layer. Including basic cost of materials, labour,
HOM machinery,etc complete as per specifications
and EIC directions. The rates mentioned here are
exclusive of carriage charges for aggregate/stone
dust/selected soil from quarry site. Various
combinations of in-situ soil/selected soil(as
applicable),aggregate and RBI percentages have been
given. The optimum combination would depend upon
the following factors : 1. In situ
soil/selected soil (as applicable) CBR and PI
2. Traffic
category
3. Distance
of quarry from site

II Providing, laying, spreading and compacting Soil


conforming to engineering requirements and
Aggregate in base course including in situ mixing of
40% Aggregate (20 mm) + 56% Soil (CBR 7% to 9%)
with 4 % RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor
grader on a prepared base including watering and
compacting with 10 to 12 tonne single drum vibratory
roller to achieve the required density at OMC for
preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as
per specifications and EIC directions

40% Aggregate (20 mm) + 56% Soil (CBR 7


Composition
% to 9 %) + 4 % RBI Grade-81
Unit =Cum
Taking Output =300 Cum
a) Material
20 mm Aggregate (40%) cum ### ###
Soil (CBR 7 % to 9 %) (56%) cum ### 155.00
Quantity of RBI Grade-81 by weight(4%) MT ### ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
III Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base course including in situ mixing of
40% Aggregate (20 mm) + 56.25% Soil (CBR 7% to
9%) with 3.75 % RBI Grade-81 (a soil stabilizer cum
pavement material), spreading in uniform layers with
motor grader on a prepared base including watering
and compacting with 10 to 12 tonne single drum
vibratory roller to achieve the required density at OMC
for preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as
per specifications and EIC directions

Composition 40% aggregate 20 mm + 56.25% selected soil (CBR


Unit =Cum
7% to 9%) + 3.75% RBI Grade-81 (SRSPL) (by
Taking Output =300 Cum
a) Material
20 mm Aggregate (40%) cum ### ###
Soil (CBR 7 % to 9 %) (56.25%) cum ### 155.00
Quantity of RBI Grade-81 by weight (3.75%) MT ### ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
IV Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in base course including in situ mixing of
40% Aggregate (20 mm) + 56.5% Soil (CBR 7% to
9%) with 3.5 % RBI Grade-81 (a soil stabilizer cum
pavement material), spreading in uniform layers with
motor grader on a prepared base including watering
and compacting with 10 to 12 tonne single drum
vibratory roller to achieve the required density at OMC
for preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as
per specifications and EIC directions

Composition 40% aggregate 20 mm + 56.5% selected soil (CBR 7% to 9%)


Unit =Cum + 3.5% RBI Grade-81 (SRSPL) (by weight of selected soil &
Taking Output =300 Cum
a) Material
20 mm Aggregate (40%) cum ### ###
Soil (CBR 7 % to 9 %)(56.50%) cum ### 155.00
Quantity of RBI Grade-81 by weight (3.5%) MT 22.1 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
V Providing, laying, spreading and compacting Soil
conforming to engineering requirements and
Aggregate in sub base layer including in situ mixing of
40% Aggregate (20 mm) + 58% Soil (CBR 7% to 9%)
with 2% RBI Grade-81 (a soil stabilizer cum pavement
material), spreading in uniform layers with motor
grader on a prepared base including watering and
compacting with 10 to 12 tonne single drum vibratory
roller to achieve the required density at OMC for
preparing the base Layer Including all cost of
materials, labour, HOM of machinery, etc complete as
per specifications and EIC directions

Composition 40% aggregate 20 mm + 58% selected soil (CBR 7% to 9%) +


Unit =Cum 2% RBI Grade-81 (SRSPL) (by weight of selected soil &
Taking Output =300 Cum
a) Material
20 mm Aggregate (40%) cum 145 ###
Soil (CBR 7 % to 9 %)(58.00%) cum 218 155.00
Quantity of RBI Grade-81 by weight (2%) MT 12 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.7 Providing, laying, spreading and compacting including
in situ mixing of In-Situ 94 % Soil + 4 % PI Reducing
Agent with 2 % RBI Grade-81 (a soil stabilizer cum
pavement material), spreading in uniform layers with
motor grader on a prepared including watering and
compacting with 10 to 12 tonne single drum vibratory
roller to achieve the desired density for preparing the
Sub Base/Subgrade.
Including basic cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions.

Composition 94 % Soil + 4 % PI Reducing Agent + 2 % RBI Grade-81


Unit =Cum
Taking Output =300 Cum
a) Material
Soil (94%) cum 353 155.00
PI Reducing Agent (4%) MT 21.6 ###
Quantity of RBI Grade-81 by weight (2%) MT 10.8 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.8 Providing, laying, spreading and compacting including
in situ mixing of In-Situ 93.5 % Soil + 4 % PI Reducing
Agent with 2.5 % RBI Grade-81 (a soil stabilizer cum
pavement material), spreading in uniform layers with
motor grader on a prepared including watering and
compacting with 10 to 12 tonne single drum vibratory
roller to achieve the desired density for preparing the
Sub Base/Subgrade.
Including basic cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions.

Composition 93.5 % Soil + 4 % PI Reducing Agent + 2.5 % RBI Grade-81


Unit =Cum
Taking Output =300 Cum
a) Material
Soil (93.5%) cum ### 155.00
PI Reducing Agent (4%) MT ### ###
Quantity of RBI Grade-81 by weight (2.5%) MT ### ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.9 Providing, laying, spreading and compacting including
in situ mixing of 98 % In-Situ Soil (PI < = 10) with 2 %
RBI Grade-81 (Soil Stabiliser and Pavement Material ),
spreading in uniform layers with Motor grader on a
prepared surface including watering and compacting
with 10 to 12 tonne single drum vibratory roller to
achieve the desired density for preparing the
Subgrade.
Including basic cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions .

Composition: 98 % In-Situ Soil (PI <= 10) + 2 % RBI Grade-81


Unit =Cum
Taking Output =300 Cum
a) Material
In-Situ Soil (PI <= 10) (98%) cum ### 155.00
Quantity of RBI Grade-81 by weight (2%) MT ### ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.10 Providing, laying, spreading and compacting including
in situ mixing of 97.5 % In-Situ Soil (PI < = 10) with 2.5
% RBI Grade-81 (Soil Stabiliser and Pavement
Material ), spreading in uniform layers with Motor
grader on a prepared surface including watering and
compacting with 10 to 12 tonne single drum vibratory
roller to achieve the desired density for preparing the
Subgrade.
Including basic cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions .

Composition: 97.5 % In-Situ Soil (PI <= 10) + 2.5 % RBI Grade-81
Unit =Cum
Taking Output =300 Cum
a) Material
In-Situ Soil (PI <= 10) (97.5%) cum ### 155.00
Quantity of RBI Grade-81 by weight (2.5%) MT ### ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 ###
Motor Grader Scarifier & Levelling hour 6 ###
Single Drum 10-12 tonne Vibratory roller hour 6 ###
Tractor with Rotavator and blade @25 cum hour 12 431.00
per hour
Water tanker 6 KL capacity hour 5 432.00
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.11 Providing, laying, spreading and compacting including
in situ mixing of 98 % Selected Soil (PI < = 10) with 2
% RBI Grade-81 (Soil Stabiliser and Pavement
Material ), spreading in uniform layers with Motor
grader on a prepared surface including watering and
compacting with 10 to 12 tonne single drum vibratory
roller to achieve the desired density for preparing the
Subgrade.
Including basic cost of materials, labour, HOM of
machinery, etc complete as per specifications and EIC
directions .

Composition 98 % Selected Soil (PI <= 10) + 2 % RBI Grade-81


Unit =Cum
Taking Output =300 Cum
a) Material
Selected Soil (PI <= 10) (98%) cum 368 155.00
Quantity of RBI Grade-81 by weight (2%) MT 10.8 ###
b) Labour
Mate ( L-14) day 0.48 356.65
Mazdoor (Skilled) ( L-017) day 2 458.55
Mazdoor (Unskilled) ( L-15) day 10 244.56
c) Machinaries
Hydraulic Excavator 0.9 cum bucket capacity hour 6 1485
Motor Grader Scarifier & Levelling hour 6 2795
Single Drum 10-12 tonne Vibratory roller hour 6 1421
Tractor with Rotavator and blade @25 cum hour 12 431
per hour
Water tanker 6 KL capacity hour 5 432
Tipper 5.5 cum/ 10 t, 4 trips per hour hour 13.6 717
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
17.12 ZYCOSOIL NANO TECHNOLOGY
A Water Proofing
I Waterproofing on top compacted ( as per relevant
MoRD specification) sub Grade soil base, shoulders
with Organosilane Nanotechnology & nano acrylic co-
polymer with water (<1000 ppm TDS) in the ratio of 1
kg Organosilane Nanotechnology:1 kg nano acrylic co-
polymer :200 liter water spray @ 3 liter /sqm in two
spray applications (1.5 liter + 1.5 liter) as per direction
of the Engineer-in-charge.

Unit = Sqm
Taking output = 7000 Sqm
a) Material
Organosilane Nanotechnology Kg 105 550.00
Nano acrylic co-polymer Kg 105 180.00
Water kl 21 40.00
b) Labour
mazdoor(Unskilled) day 3 244.56
mazdoor(Skilled) day 2 458.55
c) Machinery
Three wheel 80-100 KN Vibratory compactor hour 2.56 652.00
Water tanker 6 kl capacity truck mounted (4 hour 7.00 432.00
trips per day)
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/7000
say
II Stabilized Sub-base / Base: Providing, Laying,
Spreading and Compacting in-situ/borrow area soil of
CBR >5% mixed with / without 30% crushed aggregate
/ muruum / GSB Grade 1 as per mix design.
Application:
(1) Rip and loosen soil with excavator / tractor
operated ripper and scarify with tractor operated
rotavator upto depth of 200 mm. Mix aggregates as
per mix design.
(2) Apply 1 kg /cum organosilane Nanotechnology
mixed in OMC water (<1000 ppm TDS) on loose soil.
Scarify the treated and allow it to dry.
(2) Spread Cement 3% by weight of soil on the silane
treated and dry soil.
(3) Apply 1 kg/cum of nano acrylic Co-Polymer mixed
in OMC water (<1000 ppm TDS), on the above
treated soil mixed with cement. Scarify and grade the
soil.
(4) Spread 13.2 and down size aggregates on the
graded soil surface to form 20-25 mm thick soil-
aggregate layer.
(5).Compact the stabilized soil-aggregate base with 8
to 10 tonne vibratory roller to achieve stone embedded
layer with the desired density.
(6) Waterproof the top of the compacted stabilized
base with organosilane & nano acrylic Polymer in the
ratio of 1 kg organosilane :1 kg nano acrylic Co-
Polymer : 200 liter water (<1000 ppm TDS) @
3ltrs/sqm in two spray applications (1.5 ltrs. + 1.5 ltrs.).
Rates include all material, labour, hire charges of
machinery etc. as per MoRD specifications & direction
of Engineer-in-Charge.

Unit = cum
Taking output = 300 cum
a) Material
Cement % = 3% T 16.7 ###
Organosilane Nanotechnology Kg 325 550.00
Nano acrylic co- polymer Kg 325 180.00
Water kl 160 40.00
Soil cum 240 170.00
Aggregate (As per SOR Rate - For 53 mm cum 90 810.00
maximum size - below 5.6 mm / Muruum /
GSB Graded material /Aggregate - Crushable
type such as moorum or Gravel for Grading I -
quantity 30% of total volume
Graded chips 13.2 mm down (AP SOR Rate of cum 30 ###
10 mm chips)
b) Labour
Mate day 0.48 356.65
Mazdoor (Skilled) day 2 458.55
Mazdoor (Unskilled) day 14.7 244.56
c) Machinery
Hydraulic excavator 0.9 cum bucket capacity hour 3 1485.00
@ 100 cum / hour
Tipper 5.5 cum with 10t capacity (4 trips per hour 13.6 680.00
hour)
Dozer D-50 / Grader for spreading @ 200 cum hour 1.5 1965.00
per hour
Tractor with Mount Grader @ 25 cum per hour 8 431.00
hour
Three wheel 80-100 kN vibratory roller @ 100 3 652.00
hour
cum per hour
Water tanker 6 kl capacity truck mounted (4 6.69 3456.00
day
trip/day, Rs 535/hr)
Tractor with Rotavator @ 25 cum per hour hour 12 431.00
Tractor with Ripper @ 60 cum per hour hour 5 440.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/300
say
III Prime Coat (with silane Nanotechnology)
(i) Low porosity
Prime Coat : Preparing and applying of water
soluble organo silane nanotechnology (for bitumen
emulsion application, IRC approved) with cationic
bitumen emulsion CSS1 and water (<1000 ppm TDS)
in the ratio of 1 kg organo silane : 100 kg cationic
bitumen emulsion CSS1 : 200 liter water . Mixing &
Spraying : Take 1 kg of organo silane nanotechnology
and add in 200 liter water while filling water in
tanker/drum and then add 100 kg cationic bitumen
emulsion under circulation. Mix the solution
completely. Spray the solution @ 1 liter per sqm on
compacted stone base. Rates including all materials,
labour, hire Charges of machery etc. complete as per
MoRD specifications & direction of Engineer-in-
Charge.

Unit = sqm
Taking output = 1750 sqm
a) Material
Cationic Bitumen emulsion (CSS-1) = 1kg/sqm t 0.58 39183.00
Water kl 1.17 40.00
Organo silane nanotechnology kg 5.83 1200.00
b) Labour
Mate day 0.04 356.65
Mazdoor (Skilled) day 1 458.55
c) Machinery
Hydraulic broom with tractor @ 1250 sqm per hour 1.40 337.00
hour
Air compressor 210 cfm hour 1.40 354.00
Bitumen emulsion pressure distributor @ 1750 hour 1.00 717.00
sqm per hour
Water tanker 6 kl capacity truck mounted hour 0.50 432.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/1750
say
17.13 20mm thick Open-Graded Premix Carpet using
Bituminous (penetration grade) Binder Using
Nanotechnology.( Providing, laying and rolling of
open-graded premix carpet of 20 mm thickness
composed of 13.2 mm to 5.6 mm stone aggregates
using S-65 penetration grade bitumen mixed with
silane nanotechnology @ 0.1% by weight of bitumen
S-65 grade @ 14.6 kg/10 sqm to required line, grade
and level to serve as wearing course on a previously
prepared base, including mixing in a suitable hot mix
plant, laying and rolling with a three wheel 80-100 kN
static roller capacity, finished to required level and
grades to be followed by seal coat of Type D as per
Technical Specification Clause 508 of MoRD and as
per direction of Engineer-in-Charge.)

Case -II By Mechanical Means


Bitumen (S-90)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Material
Crushed stone chipping, 13.2 mm to 5.6 mm cum 108 1192.5
@ 0.27 cum per 10 sqm
Organosilane @ 0.1% by weight of S-90 kg 5.84 1350
Bitumen
Bitumen (S-90) @ 14.60 kg per 10 sqm t 5.84 38826
b) Labour
Mate day 0.52 356.65
Mazdoor (Unskilled) day 10 244.56
Mazdoor (Semi-Skilled) day 3 285.32
c) Machinery
HMP 30/40 t per hour hour 6 6584
Electric generator set 125 KVA hour 6 1388
Front end loader 1 cum bucket capacity hour 6 882
Tipper 5.5 10 t capacity hour 3.64 680
Paver finisher hour 6 883
Three wheel 80-100 kN static roller hour 16 652
d) Overhead charges @ 2.5 % on (a+b+c )
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/4000
say
17.14 Seal Coat( with Nanotechnology) (Providing and
laying seal coat sealing the voids in a bituminous
surface laid to the specified levels, grade and cross fall
using Type D as per Technical Specification Clause
510 of MORD with S-65grade bitumen mixed with
organosilane nanotechnology @ 0.1% by weight of S-
65 bitumen binder laid as per direction of Engineer-in-
Charge.)

A By Mechanical Means
I Case -3 : Type C: Bitumen (S-90)
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Material
Bitumen (S-90) t 4.88 38826
Organosilane @ 0.1% by weight of S-65 kg 4.88 1350
Bitumen
Crushed Stone Chipping 6.7 mm size 100% cum 67.5 1170
passing 11.2 mm and retained on 2.36 mm
a) Labour
Mate day 0.2 356.65
Mazdoor (Unskilled) day 5 244.56
c) Machinery
Front end loader 1cum bucket capacity hour 6 882.00
Hydraulic self propelled chip spreader hour 6 2380.00
Bitumen pressure distributor hour 6 954.00
Three wheel 80-100 kN Static Roller hour 15 652.00
Tipper 5.5 cum/10 ton capacity hour 6 680.00
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/7500
say
17.15 EVOCRETE TECHNOLOGY
A Stabilization/soil binding of in-situ soil of sub-
base/base course using EvocreteCCL soil
stabilizer (Construction of Sub-Base/Base of road
pavement by making use of EVOCRETE CCL Soil
Modifier (GERMAN) technology by re-using the
existing/in-situ soil. Profiling the road to the required
design standard followed by spreading of 7% of
O.P.C. 43 Grade cement of stabilized soil (Variable
depending upon soil properties) , then spreading 2 %
EVOCRETE additive of 7 % OPC and pulverising the
cement , additive & profiled soil/pavment material with
help of Recycler/Stabilizer including moisturing to
OMC. On completion of pulverisation re-garding,
profiling to required grade/camber with motor grader &
compacting simaltaneously with 14 tonne vibratory
roller to achieve 95% degree of compaction as
directed by the Engineer-in-charge & finally irrigating
the stabilized surface for next 48 hours)

I 20.0cm thick Sub-Base & Base with Evocrete and


Cement etc.
Unit = cum
Taking output = 750 Cum
a) Material
Cement @ 126 kg/ cum( Density 1800 gm , tonn 94.5 7900
cement 7% as per laboratory analysis = 126 e
kg/cum)
Evocrete at site @ 2.52 kg/ cum (considering Kg 1890 630
2% quantity of cement, as per laboratory
advice & results)
Water (For mixing during stabilization ) kl 195 40
Water (Irrigating during curing ) kl 12 40
b) Labour
Mate No. 1 356.65
Mazdoor (Unskilled) No. 15 244.56
Mazdoor (skilled) No. 15 458.55
c) Machinery
Heavy Duty Stabilizer/Recycler with moisture hour 12.5 14405.00
controlling meter@ 60cum/hour ( for in -situ
stabilization using existing material/soil with
evocrete soil modifier)
Motor Grader 110 HP @50 cum / hour (for hour 12.5 2795.00
cambering and super elevation)
Vibratory Road Roller @ 100 cum / hour (for hour 7.5 1421.00
extreme compaction)
Tandem Road Roller @ 30 cum / hour hour 12.5 652.00
(considering 50% of thickness ) (for achieving
smooth surface)
Water tanker 12 kl capacity ( for mixing with hour 17.3 432.00
soil + cement + additive + curing)
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/750
say
17.16 Cell Filled Concrete Pavement
I Construction of plastic cell filled cement concrete
pavement, thickness 100mm (as per design), over a
prepared sub base, with 53 grade Ordinary Portland
Cement(OPC) or any other type as per Clause
1501.2.4 M30 (Grade), coarse and fine aggregates
conforming to IS : 2386, mixing in a concrete mixer of
not less than 0.2 cum capacity and appropiate weigh
batcher using approved mix design (As per IRC:44-
2008), laid in the cells made of high density polythyne
sheets of thickness 0.22mm to about 0.25mm,side
150mm and depth 100mm of approximate weight of
1250 kg for a road of 3.75m wide and 1.00km , putting
iron spike of 200mm long at the end corners of the
cells and using nylon threads passing through the cells
10 mm below the top of the cells, in approved fixed
side formwork (steel channe, wedges, steel plates
including levelling the formwork as per
drawing),maitaining camber of about 3 to3.5%,
spreading the concrete with sholvels, rakes,
compacted using needle, scareed and plate vibrators
and finished in continuous operation, curing of
concrete slabs for 14- days, curing compound (where
specified) and water finishing to lines and grade as per
drawing and Technical Specification of Cell filled
Concrete Pavement Published by NRRDA
a Rate analysis is being carried out for Cell filled
concrete pavement of 3.75m and 25m in width and
length. As per the requirement of DIY on cell filled
concrete block, the following are the requirements for
a pavement of 3.75m and 25m in width and length that
can be constructed in one day:
*200 micron plastic sheet-1 kg=28 meter long of 10cm
width-(1.75 sq.m/kg-53.57 Kg for 3.75mx25m)
*Labour approximately
*Male workers 20
Female workers 7
Mason 4
1 number concrete mixer
Plate or screed vibrator - 1 no.
Mechanical trowelling - 1 no.
Max. 25meter length(of width 3.75meter) can be laid in
a day (about 10 Cum of CC)

Taking output =25x3.75= 93.75 sqm


unit=sqm
a) Material
Crushed stone coarse aggregates ( Grading cum 8.44 ###
will be as per Clause 1501.2.4.1 (Table
1500.1) of specifications @ 0.90 cum/cum of
concrete (25 mm & 12.5 mm blending))
Sand (As per IS:383 and conforming to Clause cum 4.22 749.00
1500.2.4.2 @ 0.45 cum/cum of concrete)
Cement ( 310 kg/cum of concrete) tonn 2.91 ###
Plastic cell (In full surface area ) eSqm 93.8 102.00
Curing compound (0.33 litre per sqm) litre 30.9 193.00
Water for curing Kl 2.4 40.00
b) Labour
Mason (1st class) No 4 458.55
Mazdoor (Unskilled) No 7 244.56
Mazdoor (Skilled) No 20 458.55
c) Machinery
Concrete mixer of one cum capacity (One hr 8 188.00
mixer) with weigh batcher and suitable
capacity calibrated water tank for 8 hrs
working
Plate period
vibrator hr 3 218.00
Water tanker 6 kl capacity hr 1 432.00
Formwork 3% of (a+b+c)
d) Overhead charges @ 2.5 % on (a+b+c)
e) Contractor's profit @ 10 % on (a+b+c+d)
Rate per cum = (a+b+c+d)/93.75
say

17.17 TENAX 3D GRID TECHNOLOGY


I Supplying and laying of Polypropylene extruded
Geogrid with a minimum stiffness (modulus) at 0.5%
strain according to ISO 10319 should be 350x550
Kn/m with apparaent coefficient of friction
soil/geosynthetics accroding to EN 13738 must be
atleast 1.70(us/gsy) at 10 KPa load and with a min
transversal rib thickness of 2.5 mm and longitudinal rib
thickness of 3.6 mm. Aperture of geogrid should be
30mm x 30 mm. Geogrid should not be made of
bonding of strands or punching and stretched sheets

Output= 1sqm
Unit = Sqm
Tenax 3 D Grid S
a) Material
Ex Italy Vigao Italy sqm 1 67.12
Freight from Italy to India sqm 1 12.96
Indian Custom Duty @30 percent sqm 1 30.02
Freight from Kolkata to Guwahati sqm 1 10.00
Cost of U-pins sqm 1 1.40
b) Labour
Skilled No 0.01 458.55
Unskilled labour No 0.02 244.56
c) Overhead charges @ 2.5 % on (a+b )
d) Contractor's profit @ 10 % on (a+b+c)
Rate per cum = (a+b+c)
say
17.18 517 Recycling of Bituminous Pavement with Central
Recycling Plant
Recycling pavement by cold milling of existing
bituminous layers, planning the surface after cold
milling, reclaiming excavated material to the extent of
30 per cent of the required quantity, hauling and
stock piling the reclaimed material near the cent
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate day 0.480 356.65
Mazdoor day 10.000 244.56
Mazdoor skilled day 2.000 356.65
b) Machinery
Cold milling machine @ 20 cum per hour hour 6.000 685.00
Mechanical broom @ 1250 sqm per hour hour 1.280 337.00
Air compressor 250 cfm hour 1.280 354.00
Bitumen pressure distributor @ 1750 sqm per hour 0.910 954.00
hour
Hot mix plant 100-120 TPH producing an hour 3.000 22823.00
average of 75 tonnes per hour
Electric generator set 250 KVA hour 3.000 1500.00
Front end loader 1.00 cum bucket capacity hour 3.000 882.00
Tipper 5.5 cum capacity hour 18.000 680.00
Smooth wheeled roller 8-10 tonnes hour 3.00x0.65* 652.00
Vibratory roller 8 tonnes hour 3.00x0.65* 1421.00
Smooth wheeled tandem roller 6-8 tonnes hour 3.00x0.65* 652.00
c) Material
i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of
mix. For reclaimed material, fresh bitumen will be
required to the extent of 60 per cent of normal
requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and
balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne 1.987 33854.00
tonne @ 60 per cent = 82.8 x 0.60 x0.04 =
1.99
Bitumen required for fresh mix of 193.2 tonnes tonne 7.728 33854.00
= 193.2 x 0.04 = 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per
cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.96 =
185.47 tonne
Taking average density of 1.5 tonnes/cum, total
volume of aggregate = 123.65 cum.
Size wise requirement of fresh aggregates
37.5 - 25 mm @ 23 per cent cum 28.440 1901.00
25 - 10 mm @ 15 per cent cum 18.550 2277.00
10- 5 mm @ 20 per cent cum 24.730 1747.00
Below 5 mm @40 per cent cum 49.460 981.00
Filler (cement) @ 2 per cent = 5.52tonnes of tonne 5.520 7600.00
276 tonne
c) Overhead charges @ 2.5 % on (a+b )
d) Contractor's profit @ 10 % on (a+b+c)
Cost for 120 cum of DBM = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
say
Although the total rolling time is only 4 hours as per
norms, all the three rollers have to be available at site
for 3 hours each to match with the output of re-cycling
plant. To cater for their idling time, these have been
multiplied with a factor of 0.6
17.19 Protective coatings to the structures,
equipments and machine parts with
performance guarantee for 3 years.
I
Application cost of two part highbuild 100%
solid content system of Cyclophat polyamino
based KRAYON KI30021 COROGARD to give
protective coating to the substract by giving
good bonding to the intermediate coat of
Krayon KI 30031 RUST CONVERTOR coat
giving the cured coat of crosslinked protective
coating from rust , corrosion and weathering
effect including cost of material, labour,
scafolding, cleaning over application of one
part primer fron three part system and two part
primer from three part system Krayon KI
30031 RUST CONVERTOR PRIMER and
consumable complete as directed by the
Engineer-incharge and conforming quality as
per IS / IRC Specifications.

Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.065 356.65
Painter day 0.800 458.55
Mazdoor day 0.450 244.56
b) Material
i) Providing & fixing Scaffolding up to 9.00 m
Sqm 10.000 22.00
height of structure
ii) Consumable and Cleaning of structures Sqm 10.000 40.00
iii) Material cost KI Krayon KI 30031 RUST
Sqm 1.780 390.00
CONVERTOR PRIMER single part
iv) Material cost two parts KI Krayon KI 30031 590.00
Sqm 2.500
RUST CONVERTOR PRIMER single part
v) Material cost of two part highbuild 100%
solid content system of Cyclophat polyamino
based KRAYON KI30021 COROGARD to give
protective coating to the substrate by giving
good bonding to the intermediate coat of kg 2.940 820.00
Krayon KI 30031 RUST CONVERTOR coat
giving the cured coat of crosslinked protective
coating from rust , corrosion and weathering
effect.
c) Overhead charges @ 2.5 % on (a+b )
d) Contractor's profit @ 10 % on (a+b+c)
Cost for 10 sqm = a+b+c
Rate per sqm= (a+b+c)/10
say
Amount
(Rs.)

285.32
4402.08
713.30

1128.00
3912.00

81900.00

38867.85

131208.55
3280.21 2.5 %
13120.86 10 %
147609.62
164.01
164.00

410.15
356.65
5380.32
2139.90

1128.00
1434.40

5005.00

17889.30

33743.72
843.59
3374.37
37961.68

34.51

35.00

356.65
3668.40
5349.75
180062.50

34937.50
10657.50
8150.00

7452.00

746550.00
1190700.00

7800.00
480.00
2196164.30
54904.11
219616.43
2470684.84
3294.25
3294.00

324000.00
4000.00

14.27
160.49
183.42

2200.00
5172.00
2160.00
5172.00
7105.00
2200.00
5172.00
2160.00
8992.48
36869.17
1351.87
1352.00

202500.00
4000.00
45000.00
84525.00

81.12
350.00
1690.00

0.00
0.00
2200.00
5172.00
2160.00

5172.00
7105.00
2200.00
5172.00
2160.00
9237.18
37872.43
1388.66
1389.00

23700.00
728000.00
189600.00
1200.00

3209.85
0.00
0.00

5940.00
16770.00
12362.40
5172.00
5541.90
1296.00
24819.80
101761.20
3731.24
3731.00
e Dust + 46% Soil (CBR 5% to
RSPL) (by weight of Aggregate,
Situ Soil Mix Material

92020.50

48300.00
17250.00
882000.00

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
27360.56
112178.28
4113.20
4113.00
tone Dust + 36% Soil
BI Grade 81 (SRSPL) (by

92020.50

72450.00
13500.00
882000.00

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9777.27
27870.49
114269.02
4189.86
4190.00

e Dust + 46% Soil (CBR 5% to


RSPL) (by weight of Aggregate,

92020.50

48300.00
17250.00
882000.00

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9777.27
27360.49
112178.02
4113.19
4113.00

Dust + 36.25% Soil (CBR 5% to


RSPL) (by weight of Aggregate,

92020.50

72450.00
13594.00
826875.00

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
26494.78
108628.61
3983.05
3983.00
Dust + 46.25% Soil (CBR 5% to
RSPL) (by weight of Aggregate,

92020.50

48300.00
17344.00
826875.00

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
25984.78
106537.61
3906.38
3906.00
Dust + 36.5 % In-Situ Soil (CBR
e-81

92020.50

72450.00
13688.00
771750.00

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
25119.01
102987.93
3776.22
3776.00
Dust + 46.5% In-Situ Soil (CBR
e-81

92020.50

48300.00
17438.00
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
24609.01
100896.93
3699.55
3700.00
Dust + 48% In-Situ Soil (CBR 5
1

92020.5

48300
18000
420000

171.192
917.1
2445.6

8910
16770
8526
5172

2160
9779.88
15829.31
64900.16
2379.67
2380.00
ted Soil (CBR 7 % to 9 %) + 4

138031

0
29643.75
882000
171.192
917.1
2445.6

8910
16770
8526
5172

2160
9779.88
27613.16
113213.94

4151.18
4151.00

ust+ 51% Selected Soil(CBR7%


SPL)by weight of Aggregate ,

92020.50

36225.00
29643.75
###

171.19
917.10
2445.60

8910
16770
8526
5172
2160
9779.88
27368.53
112210.95
4114.40
4114.00

CBR 7%to 9%)+3.75% RBI


of Aggregate , SelectedSoil Mix

###

0.00
29789.06
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
26238.66
107578.52
3944.55
3945.00
ust +51.25% Soil(CBR 7%to 9%)
SPL)by weight of Aggregate ,

92020.50

36225.00
29787.90
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
25998.38
106593.36
3908.42
3908.00
ted soil (CBR7%to 9%)+3.5%

###

0.00
29934.38
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
24864.17
101943.11
3737.91
3738.00
Dust+51.5% Selected Soil(CBR
% RBI Grade -81

92020.50

36225.00
29934.38
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
24619.54
100940.12
3701.14
3701.00
Dust+53% Soil(CBR7%to 9%)

92020.50

36225.00
30806.25
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
15847.59
64975.11
2382.42
2382.00
mm) + 56% Soil (CBR 7
Grade-81

###
32550.00
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
29255.33
119946.87
4398.05
4398.00

56.25% selected soil (CBR


BI Grade-81 (SRSPL) (by

###
32695.31
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
27880.84
114311.45
4191.42
4191.00

% selected soil (CBR 7% to 9%)


PL) (by weight of selected soil &
###
32840.63
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
26506.35
108676.03
3984.79
3985.00

selected soil (CBR 7% to 9%) +


) (by weight of selected soil &

200811.6
33712.5
420000

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
17734.40
72711.03
2666.07
2666.00

ng Agent + 2 % RBI Grade-81

54637.50
###
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
15967.23
65465.65
2400.41
2400.00

ng Agent + 2.5 % RBI Grade-81


54346.88
###
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
18322.47
75122.11
2754.48
2754.00

= 10) + 2 % RBI Grade-81

56962.50
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
12245.36
50205.96
1840.89
1841.00

= 10) + 2.5 % RBI Grade-81

56671.88
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
14600.59
59862.42
2194.96
2195.00

= 10) + 2 % RBI Grade-81

56962.50
###

171.19
917.10
2445.60

8910.00
16770.00
8526.00
5172.00

2160.00
9779.88
12245.36
50205.96
1840.89
1841.00

57750.00
18900.00
840.00

733.68
917.10

1669.12
3024.00

2095.85
8592.97
13.50
14.00
131535.00
178876.50
58541.40
6418.00
40800.00
72900.00

38400.00

171.19
917.10
3582.80

4455.00
9275.20

2947.50

3448.00
1956.00

23103.36

5172.00
2200.00
14617.48
59931.65
2197.49
2197.00

22843.69
46.80
6999.60

14.27
458.55

471.80

495.60
717.00

216.00
806.58
3306.99
20.79
21.00
128790.00

7884.00

226743.84

185.46
2445.60
855.96

39504.00
8328.00
5292.00
2475.20
5298.00
10432.00
10955.85
44918.99
123.53
124.00
189470.88
6588.00

78975.00

71.33
1222.80

5292.00
14280.00
5724.00
9780.00
4080.00
7887.10
32337.11
47.43
47.00

746550.00

1190700.00

7800.00
480.00
356.65
3668.40
6878.25

180062.50

34937.50

10657.50

8150.00

7452.00

54942.32
225263.51
3303.86
3304.00
11672.52

3160.78

22957.40
9562.50
5971.03
96.00

1834.20
1711.92
9171.00

1504.00

654.00
432.00
2061.82
1769.73
7255.89
851.36
851.00
67.12
12.96
30.02
10.00
1.40

4.59
4.89
3.27
13.43
147.68
148.00

171.19
2445.60
713.30

4110.00
431.36
453.12
868.14

68469.00

4500.00
2646.00
12240.00
1271.40
2770.95
1271.40

67274.67

261623.71

54064.44
42238.35
43203.31
48520.26
41952.00

16530.96
66123.82
743892.98
6199.11
6199.00
23.18
366.84
110.05

220.00

400.00

694.20

1475.00

2410.80

142.50
570.01
7801.99
780.20
780.00
Abbreviations
AC Asphaltic Concrete

BC Bituminous Concrete

BM Bituminous Macadam

BUSG Built-up Spray Grout

CI Cast Iron

cfm Cubic feet per minute

cm Centimetre

cum Cubic metre

Dia Diameter

e.g. For example

FE Loader Front End Loader

GBFS Granulated Blast Furnace Slag

GI Galvanised Iron

GL Ground Level

h Hours

HMP Hot Mix Plant

HP Hours Power

i.e. That is

IRC Indian Roads Congress

IS Indian Standards

kg Kilogram

kl Kilolitre

km Kilometre

kN Kilo Newton

lit Litre

m Metre

Max Maximum

Min Minimum

mm Millimetre

MORD Ministry of Road Development

MORTH Ministry of Road Transport & Highways

Nos. Numbers

NRRDA National Rural Roads Development Agency

OMC Optimum Moisture Content

PCC Plain Cement Concrete

Abbreviation - 144
Abbreviations
PQC Pavement Quality Concrete

q Quintal

RCC Reinforced Cement Concrete

RR Road Roller

Rs. Rupees

SDBC Semi-Dense Bituminous Concrete

sqm Square metre

SWL Standing Water Level

t Tonne

T&P Tools & Plants

t.km Tonne Kilometre

WBM Water Bound Macadam

WMM Wet Mix Macadam

Abbreviation - 145
L_Bhisti =Labour!$D$3
L_BitumenSprayer =Labour!$D$4
L_Blacksmith =Labour!$D$5
L_Blaster =Labour!$D$6
L_Carpenter_1stClass =Labour!$D$7
L_ChipsSpreader =Labour!$D$8
L_Chiseller =Labour!$D$9
L_Dresser_Skilled =Labour!$D$10
L_Driller =Labour!$D$11
L_Electrician_Lineman =Labour!$D$12
L_Fitter =Labour!$D$13
L_Mason_1stClass =Labour!$D$14
L_Mason_2ndClass =Labour!$D$15
L_Mate =Labour!$D$16
L_Mazdoor =Labour!$D$17
L_Mazdoor_Semi =Labour!$D$18
L_Mazdoor_Skilled =Labour!$D$19
L_Painter_1stClass =Labour!$D$20
L_Plumber =Labour!$D$21
L_Surveyor =Labour!$D$22
L_WhiteWasher =Labour!$D$23
M_ACPipe_100 =Material!$D$3
M_Aggregate_10 =Material!$D$17
M_Aggregate_20 =Material!$D$18
M_Aggregate_224_236m_WMM =Material!$D$26
M_Aggregate_375mmMaximum_224_56mm =Material!$D$4
M_Aggregate_375mmMaximum_45_225mm =Material!$D$5
M_Aggregate_375mmMaximum_Below_56mm =Material!$D$6
M_Aggregate_40 =Material!$D$19
M_Aggregate_45_224m_WMM =Material!$D$27
M_Aggregate_53mmMaximum_225_56mm =Material!$D$7
M_Aggregate_53mmMaximum_63_45mm =Material!$D$8
M_Aggregate_53mmMaximum_below_56mm =Material!$D$9
M_Aggregate_Crushable_GradeI =Material!$D$20
M_Aggregate_Crushable_GradeII =Material!$D$21
M_Aggregate_Crushable_GradeIII =Material!$D$22
M_Aggregate_GradeI_40mmNominal_10_5mm =Material!$D$10
M_Aggregate_GradeI_40mmNominal_25_10mm =Material!$D$11
M_Aggregate_GradeI_40mmNominal_3725_25mm =Material!$D$12
M_Aggregate_GradeI_40mmNominal_5mm =Material!$D$13
M_Aggregate_GradeI_90_45mm =Material!$D$23
M_Aggregate_GradeII_19mmNominal_10_5mm =Material!$D$14
M_Aggregate_GradeII_19mmNominal_25_10mm =Material!$D$15
M_Aggregate_GradeII_19mmNominal_5mm_below =Material!$D$16
M_Aggregate_GradeII_63_45mm =Material!$D$24
M_Aggregate_GradeIII_53_224mm =Material!$D$25
M_AluminiumSheeting_15mm =Material!$D$28
M_AluminiumStuds_100_100_Lense =Material!$D$29
M_Bamboo_1stClass_85_100mm_25m_long =Material!$D$31
M_Bamboo_1stClass_85_100mm_2m_long =Material!$D$30
M_Bamboo_1stClass_85_100mm_3m_long =Material!$D$32
M_Bamboo_1stClass_85_100mm_45_55m_long =Material!$D$33
M_Bamboo_2ndClass_75mm_18_25m_long =Material!$D$34
M_Bamboo_2ndClass_75mm_21_30m_long =Material!$D$35
M_BarbedWire =Material!$D$36
M_BindingMaterial =Material!$D$37
M_BindingWire =Material!$D$38
M_Bitumen_CRM =Material!$D$39
M_Bitumen_NRM =Material!$D$40
M_Bitumen_PM =Material!$D$41
M_Bitumen_S65 =Material!$D$42
M_Bitumen_S90 =Material!$D$43
M_BitumenEmulsion_RS1 =Material!$D$44
M_BitumenEmulsion_SS1 =Material!$D$45
M_BitumenSealant =Material!$D$46
M_Blasted_Rubble =Material!$D$47
M_BlastingMaterial =Material!$D$48
M_BondStone_400_150_150mm =Material!$D$49
M_Brick_1stClass =Material!$D$50
M_Cement =Material!$D$51
M_CementPrimer =Material!$D$52
M_ChlorpreneElastomer_OR_ClosedCellFoamSealingElement =Material!$D$53
M_CompensationForEarthTakenFromPrivateLand =Material!$D$54
M_CompressibleFibreBoard =Material!$D$55
M_CopperPlate =Material!$D$56
M_CorbellingStones_300_150_150mm =Material!$D$57
M_CorrosionResistantStructuralSteelGrating =Material!$D$58
M_CreditForExcavatedRock =Material!$D$59
M_CrowBars_40mm =Material!$D$60
M_CrushedSand_OR_Grit =Material!$D$61
M_CrushedSlag =Material!$D$62
M_CrushedStoneAggregate_265_75 =Material!$D$63
M_CrushedStoneChipping_132 =Material!$D$64
M_CrushedStoneChipping_67mm_100Passing_112mm =Material!$D$65
M_CrushedStoneChipping_67mm_100Passing_95mm =Material!$D$66
M_CrushedStoneChipping_95 =Material!$D$67
M_CrushedStoneCoarseAggregatePassing_53mm =Material!$D$68
M_CuringCompound =Material!$D$69
M_DebondingStrips =Material!$D$70
M_EdgeStone_450_350_100mm =Material!$D$71
M_EdgeStone_450_350_200mm =Material!$D$72
M_ElastomericBearingAssembly =Material!$D$73
M_ElectricDetonator =Material!$D$74
M_EpoxyPaint =Material!$D$75
M_EpoxyPrimer =Material!$D$76
M_FarmyardManure =Material!$D$77
M_FevicolAdhesive =Material!$D$78
M_FilterMedia =Material!$D$79
M_FineAggregate_CrushedSand =Material!$D$80
M_GalvanisedAngle =Material!$D$81
M_GalvanisedAngleSection_100_100mm_12mm =Material!$D$82
M_Gelatine_80 =Material!$D$83
M_GIPipe_100mm =Material!$D$84
M_GIPipe_50mm =Material!$D$85
M_GIWires =Material!$D$86
M_GradedStoneAggregate =Material!$D$87
M_GranularMaterial =Material!$D$88
M_HandBrokenMetal_40mm =Material!$D$89
M_Indigo =Material!$D$90
M_InterlockingBlocks_60mm =Material!$D$91
M_InterlockingBlocks_80mm =Material!$D$92
M_JointFillerBoard =Material!$D$93
M_JuteNetting_OpenWeave_25mm =Material!$D$94
M_JuteRope_12mm =Material!$D$95
M_KeyAggregatesPassing_224mm =Material!$D$96
M_Lime =Material!$D$97
M_LimePutty =Material!$D$98
M_LocalWoodPiles_1stClass =Material!$D$99
M_LocalWoodPiles_1stClass_100_75mm =Material!$D$100
M_LooseStone =Material!$D$101
M_MS_Sheet_15mm =Material!$D$105
M_MS_Sheet_2mm =Material!$D$106
M_MSClamps =Material!$D$102
M_MSFlat_StructuralSteel =Material!$D$103
M_MSSheetTube_47_47mm_12_SWG =Material!$D$104
M_Nuts_Bolts_Rivets =Material!$D$107
M_Paint_SyntheticEnamel =Material!$D$108
M_Plasticizer =Material!$D$109
M_PolytheneSheet_125 =Material!$D$110
M_PolytheneSheething =Material!$D$111
M_QuarriedStone_150_200mm =Material!$D$112
M_RCCPipeNP3_1000mm =Material!$D$114
M_RCCPipeNP3_1200mm =Material!$D$113
M_RCCPipeNP3_500mm =Material!$D$117
M_RCCPipeNP3_600mm =Material!$D$121
M_RCCPipeNP3_750mm =Material!$D$115
M_RCCPipeNP4_1000mm =Material!$D$119
M_RCCPipeNP4_1200mm =Material!$D$118
M_RCCPipeNP4_500mm =Material!$D$122
M_RCCPipeNP4_750mm =Material!$D$120
M_RedOxidePrimer =Material!$D$123
M_RoadMarkingPaint =Material!$D$124
M_Sand_Coarse =Material!$D$125
M_Sand_Fine =Material!$D$126
M_Seeds =Material!$D$127
M_SteelPipe_500mm =Material!$D$128
M_SteelReinforcement_HYSDBars =Material!$D$129
M_SteelReinforcement_MSRoundBars =Material!$D$130
M_SteelReinforcement_TMTBars =Material!$D$131
M_StoneBoulder_150mm_below =Material!$D$132
M_StoneChips_12mm =Material!$D$133
M_StoneChips_132_56mm =Material!$D$134
M_StoneCrushedAggregate_112_009mm =Material!$D$135
M_StoneForCoarseRubbleMasonry_1stSort =Material!$D$136
M_StoneForCoarseRubbleMasonry_2ndSort =Material!$D$137
M_StoneForRandomRubbleMasonry =Material!$D$138
M_StoneForStoneSetPavement =Material!$D$139
M_StoneScreening_TypeA_132mm_Grade1 =Material!$D$140
M_StoneScreening_TypeA_132mm_Grade2 =Material!$D$141
M_StoneScreening_TypeB_112mm_Grade2 =Material!$D$142
M_StoneScreening_TypeB_112mm_Grade3 =Material!$D$143
M_StoneSpalls =Material!$D$144
M_TrafficCones =Material!$D$145
M_Water =Material!$D$146
M_WellGradedGranularBaseMaterial_GradeA_236mm =Material!$D$147
M_WellGradedGranularBaseMaterial_GradeA_265_475mm =Material!$D$148
M_WellGradedGranularBaseMaterial_GradeA_53_265mm =Material!$D$149
M_WellGradedGranularBaseMaterial_GradeB_236mm_below =Material!$D$150
M_WellGradedGranularBaseMaterial_GradeB_265_475mm =Material!$D$151
M_WellGradedGranularBaseMaterial_GradeC_236mm_below =Material!$D$152
M_WellGradedGranularBaseMaterial_GradeC_95_475mm =Material!$D$153
M_WellGradedMateralForSubbase_GradeI_236mm_below =Material!$D$154
M_WellGradedMateralForSubbase_GradeI_53_95mm =Material!$D$155
M_WellGradedMateralForSubbase_GradeI_95_236mm =Material!$D$156
M_WellGradedMateralForSubbase_GradeII_236mm_below =Material!$D$157
M_WellGradedMateralForSubbase_GradeII_265_95mm =Material!$D$158
M_WellGradedMateralForSubbase_GradeII_95_236mm =Material!$D$159
M_WellGradedMateralForSubbase_GradeIII_236mm_below =Material!$D$160
M_WellGradedMateralForSubbase_GradeIII_475_236mm =Material!$D$161
M_WellGradedMateralForSubbase_GradeIII_95_475mm =Material!$D$162
M_WoodenSleepers =Material!$D$163
PM_AirCompressor_210cfm ='Plant & Machinery'!$G$4
PM_BatchMixHMP_46_60THP ='Plant & Machinery'!$G$5
PM_BatchTypeHMP_30_40 ='Plant & Machinery'!$G$6
PM_BitumenBoilerOilFired_1000 ='Plant & Machinery'!$G$9
PM_BitumenBoilerOilFired_200 ='Plant & Machinery'!$G$8
PM_BitumenEmulsionPressureDistributor ='Plant & Machinery'!$G$10
PM_ConcreteMixer ='Plant & Machinery'!$G$11
PM_Crane ='Plant & Machinery'!$G$12
PM_Dozer_D50 ='Plant & Machinery'!$G$13
PM_Dozer_D50_1 ='Plant & Machinery'!$G$14
PM_ElectricGeneratorSet_125 ='Plant & Machinery'!$G$15
PM_EmulsionSprayer ='Plant & Machinery'!$G$16
PM_FrontEndLoader_1cum ='Plant & Machinery'!$G$17
PM_FrontEndLoader_1cum_Soil ='Plant & Machinery'!$G$18
PM_HydraulicBroom ='Plant & Machinery'!$G$19
PM_HydraulicExcavator_09cum ='Plant & Machinery'!$G$20
PM_HydraulicSelfPropelledChipSpreader ='Plant & Machinery'!$G$21
PM_JackHammer ='Plant & Machinery'!$G$22
PM_JointCuttingMachine ='Plant & Machinery'!$G$23
PM_Mixall_6_10t ='Plant & Machinery'!$G$24
PM_MotorGrader ='Plant & Machinery'!$G$25
PM_MotorGrader_1 ='Plant & Machinery'!$G$26
PM_NeedleVibrator ='Plant & Machinery'!$G$27
PM_PaverFinisher ='Plant & Machinery'!$G$28
PM_PlateCompactor ='Plant & Machinery'!$G$29
PM_PlateVibrator ='Plant & Machinery'!$G$30
PM_ScreedVibrator ='Plant & Machinery'!$G$31
PM_SmoothWheeled_80_100kN_TandemRoller ='Plant & Machinery'!$G$32
PM_StoneCrusher_200TPH ='Plant & Machinery'!$G$33
PM_ThreeWheeled_80_100kN_StaticRoller ='Plant & Machinery'!$G$34
PM_Tipper_55 ='Plant & Machinery'!$G$45
PM_Tractor_DiscHarrows ='Plant & Machinery'!$G$46
PM_Tractor_Ripper ='Plant & Machinery'!$G$47
PM_Tractor_Rotavator ='Plant & Machinery'!$G$49
PM_Tractor_Trolley ='Plant & Machinery'!$G$48
PM_Truck ='Plant & Machinery'!$G$50
PM_VibratoryRoller_80_100kN ='Plant & Machinery'!$G$51
PM_VibratoryRoller_80_100kN_1 ='Plant & Machinery'!$G$52
PM_WaterTanker_6kl ='Plant & Machinery'!$G$53
PM_WetMixPlant_or_PugMill ='Plant & Machinery'!$G$54

You might also like