1. Design a chart base on the given activities

Activity Description Immediate predecessors


A Buy Robot Components -
B Design Robot -
C Check all parts B
D Assemble robot A,C

2. Create a network diagram from the following activities.

Activity Immediate Predecessors


A -
B A
C B
D B
E D
F D
G D
H C,E,F,G
I H
J H
K I
L J
M K,L

3. Create a critical path of the following activities


Activity TIME REQUIRED Immediate Predecessors
A 3 -
B 4 A
C 3 B
D 10 B
E 8 D
F 4 D
G 6 D
H 8 C, E, F, G
Course Code MIT422

Technology and Project


Description
Management
College / Department:
Assignment 4
Online Education Department

ASSIGNMENT Page 2 of 2

I 5 H
J 5 H
K 4 I
L 2 J
M 4 K, L