Professional Documents
Culture Documents
.
Prepared for the electrical repair industry by
The Association of Electrical and Mechanical Trades
The representative body for the electrical repairer and merchant
IMPORTANT NOTE
This Code of Practice for Safety and Technical Advice which has been
prepared in consultation with the Health and Safety Executive should be
t·ead in conjunction with and does take precedence ove r the
t·equiremcnts of the Hea lth and Safety at Work etc Act 1974 and the
Electricity at Work Regulations 19 9.
The Code was first published in 1984 and has now been revised to take
account of experience in its use and especially to take account of
significant changes in legislation which have invalidated the origi nal
edition.
This document must not be copied in whole or in part except with the
express permission of the publishers.
ISBN 0 9509409 0 9
CONTENTS
PAGE
ACKNOWLEDGEMENTS IV
SCOPE 1
2. 1 INTRODUCTION 21
2.2 LEGAL REQUIREMENTS 21
2.:3 COMPLIANCE 22
2.4 DERIVATION OF HV SUPPLIES 22
2.5 EQUIPMENT AND SAFETY PROCEDURES 24
2.6 I SULATION TESTrNG OF HIGH VOLTACE
EQU!Pl\1ENT 25
2.6. 1 1!\SULATION TESTS AND SAFETY PRECALITIONS 25
2.6.2 HV PRESSURE TESTS AND S PECIAL TESTS ON HV
COILS 26
2.6.3 SAFETY PRECAUTIONS 26
2.6.4 EARTHING AND OVERLOAD PROTECTION OF
PRESSURE TEST SETS 28
2.6.5 VOLTMETERS FOR HV MEASUREMENTS 28
2.6.6 TAN DELTA, DIELECTRIC LOSS ANGU: ANO
IMPULSE TESTS 29
2.6.7 ACCOMPANIED WORKING 29
II
PAGE
3.1 INTRODUCTION 31
3.2 LEGAL REQUIREMENTS 31
3.3 SAFE WORKING PRACTICE ON SITE 31
3.3.1 GENERAL RECOMMENDATIONS 31
3.3.2 ELECTRICAL SAFETY PROCEDURES 33
APPENDICES
1 DEFINITIONS 35
2 REFERENCES 37
3 NOTE ON ACCOMPANIED WORKING 39
4 NOTES ON THE HEALTH AND SAFETY AT WORK ETC
ACT 1974 41
5 MECHANICAL HANDLING EQUIPMENT, MECHANICAL
AND OTHER RISKS ASSOCIATED WITH TESTING 42
6 EXAMPLES OF OTHER SAFETY, HEALTH AND WELFARE
CONSIDERATIONS APPLYING TO WORK ON SITE 43
7 ABBREVIATIONS 43
8 COMMUTATOR AND SLIPRING MAINTENANCE BY THE
USE OF HAND HELD STONES OR GRINDI NG TOOLS 44
FIGURES
NOTE: Words and phrases which are in bold, non-italic type in the text (as distinct from
headings) are de fined for the purpose of this Code of Practice in appe ndix 1,
Defmi tions.
ACKNOW1EDGEMENTS
References in this document to "h e" and "his" a lso include "she" and
"hers".
Whilst every care has been taken in the preparation of t his document,
the AEMT does not accept responsibility for any omissions or any errors
contained herein.
iv
CODE OF PRACTICE:
SAFETY IN ELECTRICAL TESTING
OBJECTIVES AND PRINCIPLES
The purpose of this Code of Practice is t,o give guidance on the tes ting of
electrical machinery in the repair industries. The recommendations a rc
directed to employers, e mployees a nd oth er duty h olders in order to
facilitate safe testing in compliance with the requi rements of the Hea lth
and Safety at Work etc Act 1974 (the HSW Act) and the Electricity at
Work Regulations 1989 (the EA W Regulations). I n addition to this Code
a copy of the Memorandum of guidance on the EA W Regulations (see
a ppendix 2) should be available in premises where electrical repairs a nd
testing are undertaken. Manufacturers' test departments will a lso find
relevant safety advice in this Code.
SCO PE
Part I deals with common requirements and the testing of low voltage
electrital equipment (see Appendix 1J.
Part. 2 deals with high voltage electrical equipment (see Appendjx 1).
INTRODUCTION Test a reas, if not designed and managed safely, can be a source of
danger. It is important, therefore, for careful thought be given to every
aspect of a test ar ea, from its initial design to its management and to the
operation of safe working procedures, whether in the works or on site.
Danger in a test area can t·es ult not only from voltages capable of
causi ng electric shock but also from circuits carrying high currents,
under normal or fault condition s, that could cause burns due to arcing or
overheating. It should be noted also that, in addition to electrical danger,
equipmen t under test may also be a source of danger from acciden tal
contact with moving parts.
A safe lest area will result from good design a nd strict management of
safe working practice to ensure that:
a) Lest engineers oper a te with in a sa fely equi pped well mana ged
environment;
b) persons in t he tes t a rea and the vicinity are not exposed to danger
when equipment is under test; and
ADEQUATE Test areas s hould a ll ow free and unrestri cted movemen t to the test
SPACE engineers in the performance of t heir duties. There s hou ld be adequate
s pace around equipment for persons to gain safe access to the test
switchboard controls at all times.
LIGHTING Particular attention s hould be paid lo both general and local lighting in
OF TEST the test a rea. A level of 500 lux at work s urfaces is recommended. Work
AREAS s urfaces s hould not glare Lobe a problem for the lest engineer (sec
appendix 2).
3
Positioning of the test area general lighting s hould be so arranged as to
minimise shadows. Account s hould be taken of overhead cranes or other
passing traffic that may cause lighting problems for the test engineer.
Local or temporary lighting should not cause obstructions for the test
engineer and lights should be placed where they are not lia ble to damage.
FLOOR The floor where testing is carried out, and in front of switchboards,
SURFACES should be dry, firm and even and kept free from obstructions.
RUBBER MATS When the safety precautions and working practices recommended in this
Code are adopted, rubber mats should not generally need to serve as a
primary protection against the risk of electric s hock in the course of
djagnostic, proving and performance tests undet·taken by r·epai rers. For
example, the majority of enclosures of equipment under lest, the
installed test equipment and faciliti es \viii be at earth potential and
indiscriminate use of rubber mats would serve little, if any, purpose.
Cbl in the immediate working area in front of test benches which have
a non-conducting work surface;
BENCH Benches used for Lc>sting should be of sound construction with durable
CONSTRUCTION non-conduc.ting work s urfaces. Thet·e s hould be adequate separation
bel-ween adjacent a reas.
MACHINE Test beds, comprised of, for example, g rid irons, tee s lots or s lide rails
TEST BEDS mounted on a fixture, s hould be of sound construction and suitably
designed for the "''ork tn hand. Adequate working space s hould be
provided around the Lest bed lo e nable the test engineer unimpeded
access to the machme under test. (see also second para of 1.4.:!)
4
1.2 PERMANENTLY DESIGNATED TEST AREAS
The number of doors, gates or hatches giving access to a Lest area should
be kept to the minimum consistent with safe means of entry and exjt of
the testing staff and the safe handling of materials. Where reasonably
practicable doors and gates should open outwards and be made self-
closing. Means should be provided to enable doors, gates and hatches
which give access to a permanently designated test area Lo be secured
when it is necessary for reasons of safety to conduct a test from an
e xLe rnal posi tion:
SIGNS AND All safety signs should comply with the Safety Sign Regulations 1980
NOTICES obtainable from Government B ookshops and BS5378 obtainable from
BSI (see appendix 2 ).
The location of F irst Aid Station, Company First Aider and emergency
services numbers.
5
temporary barriers and warning notices . Such an area s h ould be
dismantled as soon as possible after the test has been completed.
Temporary baiTiers may include por table fencing or firmly secured tapes
or ropes but the use of the latter will require a correspondingly higher
degree of test area supervision. When setting out a tempora r ily
designated test area the authorised person shoul d ensure safe
clearance distances of plant and test equi pment including any live
conductors from adjacent working areas, depending on the test to be
undertaken. If metallic fencing is used it should be earthed.
ENCLOSURE The use of enclosed LV test switchboards having no bare live conductors
which can be touched is strongly recommended. Enclosed switchboards
should be installed whenever older equipment is replaced. When open
type switchboards are still used in test areas, then a barrier or railing at
a height of approximately one met re s hould be erected one metre in front
of s uch s witchboards with bare live conductors, for example knife
switches and terminals, in order to prevent accidental contact with live
parts. Su itable precautions should also be taken to prevent s imilar
contact at the rear of switchboards e.g. by enclosur·e.
OUTPUT The following methods may be used in order to achieve variable voltage
SUPPLIES outputs from t he test switchboard:
(c) A single phase and neutral s upply from the test transformer Lo
socket outlets via a variable induct ion regulator:
6
LOCKABLE
SWITCH OR VOLTAGE RCO s
FUSESWITCH CONTACTOR REGULATOR !IF T"ITTEOI
SOOA V'RIABLE
-X VOLTAGE AC
IOOA FI XED
,.< VOLTAGE AC
IOOA VARIA.BLE
EMERGENCY X VOLTAGE AC
TRIP
25A FIXED
VOLTAGE AC
?5A VARIABLE
VOLTAGE AC
--0><0-- OVERLOAD DEVICES TO PROVIDE SHORT CIRCUIT PROTEC TION FOR BS88 FUSES
8 000 0881
8 ffi (j)
I
9 h
d @d liDnJ IWmm 9
0
OJ!
0
0
k
0
00
b
0
00
0
b
0
0
k
0
.
0
0 0 [J
0
s
a bo
[J [J
0
I<
0
0
' [J
co
0
b ..
0 0
c: ' 0
• • • • • •
[J
@
M
00
:::'0
0 0 0
E E E
7
(d) A transformer with a tapped secondary winding whose output is
rectified and connected to two socket outlets, positive (red) and
negative (black);
Figl (page 7) s hows the basic diagram for a typical test switchboard
SUPPLY FOR The test facilities should include provision for an unearthed s upply at a
CONTINUITY voltage not exceeding 25V ac or 60V de (see lEE Regulation 411-13). This
TESTING may be derived from either a safety isolating transformer, a
motor/generator set or batteries and s hould be u sed for continuity
tes ting if proprietary continuity meters are not available or s uitable.
8
ONE POLE FUSED
Figure 3: Schemuttc d1ngram showing correcl connection of basic conlrol ctrcuit components
BS 88 FUSES
INCOMING
liVE TERMINALS
WELL SHROUDED
0
TEST SUPPLY ANU
EARTH TERMINALS
l HE DOOR CANNOl B£
OPENED UNTIL THC SWifCH
IS IN THE OFF POSIT ION
ACCESS TO TESI TERMINALS
C ANNOT BE OB TAINlD UNTIL
THE DOOR IS OPE N
TEST CABLES
9
JNDTCATIONS Duplicated red indication lights placed in a prominent position should be
used to indicate that the main isolating switch of the tes t switchboard is
'ON.
POWER All outlets should include a means for screening terminals, to pre vent
OUTLETS accidental contact with live parts.
All leads from a test panel to equipment under Lest should have a means
of disconnection at the panel but unprotected bolted connections should
not be used.
(a) a recessed socket for use with an insulated rubber moulded plug.
The sockets should be protected by covers which, on removing the
plug, screen any exposed conductm·s automatically.
(b) 3 phase or single phase plugs and sockets complying with BS 4343
(see appendix 2).
RESIDUAL R CD's with a rated t ripping current of 30mA sh ould be included in the
CURRENT Lest. switchboard for low voltage ac outpu t circuits. It is important to
DEVICES remember that R CD 's are designed to trip a circuit only when earth
(EARTH LEAKAGE fault currents flow. They do not prevent, el ectric shock but. can provide
CIRCUIT supplementary protection by limiting the duration of eart.h fault current
BREAKERS) capable of causing electric shock.
The choice of rated tripping currents depends on Lhe purpose for which
an R CD is fitted. For example, a tripping current of 300mA is likely to
protect. against fire 1·isks but a lower va lu e (see t he note to lEE
Regulation 471-14 of lhe 15th Edition ) would be t·equired to minimise
shock risk fTom earth fault currents. It is important Lo note that the
performance of some R CD's may be adversely affected by the presence of
a de component in the protected ac circuit. The R CD manufacturer's
technical department s hould be consulted for advice on this subject 01· on
nuisance tripping or discrimination problems.
CONTROL A clearly marked means of switching on and off the equipment under
SWITCHING test. should be provided on the test switchboard. [f the switching device
on the switchboard is not immediately accessible because Lhe Lesl
engineer may be some distance from it, a remote control should be
provided. A suitable number of fixed emergency trip buttons should also
be provided and connected so U1at operation of any one trip button will
make ALL test cir cuits dead . These should be easily accessible for
operation from inside and out.side the test area. Recommended positions
are al the entrance to t.he test area and in front of test suppl y
s witchboards. Trip but.tons should be of the type requiring a positive
action to reset.
10
1.6 TEST AREAS, DUTIES, TRAINING, SUPERVISION,
ACCESS AND RECORDS
EMPLOYER AND Sections 2, 3 and 7 of the H SW Act (sec appendix 2) set down the general
EMPLOYEE duties of employers and employees, which are summarised in appendix
DUTIES 4 , together with other sections of the HSW Act relevan t to this Code of
Practice.
SUPE RVISION A test area should at all limes be in lhe c harge of an a uthoris ed and
compe t e nt e mployee, appointed by the e mployer because it is a place
set apart where electrical danger may be present.
ACCESS AFTER No person, whether or not electrically skj JJed , should be permitted Lo
SUPP LY work alone in a test area to clean or pain l , to handle materials, to rig
ISOLATION equipment, to curry out assembly or filling work, or for any si mil ar
purpose, until all sources of supply have been secw·ely isolated and the
area made safe by the tesl engineer.
SUB DMSION If necessary, a large Lest area may be temporarily subdivided into a parl
OF TEST AREAS where testing is being performed and where electrica l danger may be
pr·cscnl and a parl where other persons, for· example e rectors and filters,
may have access to dead equipment only. Temporary internal barriers
and notices should be used for this purpose and an authorised p e r son
!>hould keep arrangements under his direct control.
11
1.7 AUXILIARY EQUIPMENT
The use of makeshift devices which are likely to be unsafe should not be
permitted.
TEST CABLES To encourage a tidy test area a rack with hooks should be provided on
which to hang unused test cables. All lest cables s hould be nexible,
durably insulated, oversheathed and adequate for the intended use. It is
good practice for cables to have their maximum voltage and current
s hown by attached labels so that they may be identified easily.
Cables which are too long or too s horl may constit.ute a hazard and the
cable length should be s uitabl e fo1· the sa fe route chosen for test
connections.
12
there a r e signs of damage to cables, connectors, plugs or cord grips.
DefecLive mains voltage portable and transportable electrical equipment.
has been the cause of many accidents.
BEFORE A visual check s hould be made by t.he test. engineer before testing
TESTING commences, to include the following:
(d) all main circuit connections together with any necessary control,
protection, indication and aiMm circuits; and
PERIODIC The complete test facilities shoul d be regu larly exam ined by a
EXAMINATION competent p e r son at intervals that will ensu re the maintenance of all
AND RECORDS equipment. in a safe condi tion, a nd at least. once in ever·y period of 12
months. Records s hould be ke pt of ins pection dates. faults found and
remedial action taken. The following list gives examples of items to be
checked which should include:
(4) measurement of ins ulation resis tances ttnd earth loop impedances;
181 cleanliness of lhe inside and outside of the t.esl swttchboard and
connection panels;
13
renewed as soon as damage or deterioration is observed; and
STORAGE Equipment awaiting test should norma lly be kept outside the designated
area.
CONNECTIONS In ordet· that live conductors shall not present a shock or burn hazard,
TO UNIT terminal covers s hould be replaced or temporary insulation or screens
UNDER TEST fitted after connecting the test. supply leads at the terminal box. The
types of termination at equipment under test may include:
J OINTS AN D All joints and co nn ections sho uld hav e adequate conductivity.
CONNECTI ONS mechanical strength, electrical insulation and protection.
WORKING There s hould be adequate space around equipment under lest for tes ts Lo
SPACE AND be carded out safely wilh unobstructed access Lo swit.ches and conLrols
ACCESS and a clear way Lo enler or leave the Lest a rea at all limes.
14
is e nergised. After testi ng has been completed the a uthorised p e r son
in charge should securely isolate all sources of s upply.
ACCOMPANIED If a second person can s igni fi cantly contribute to safe working practice
WORKING then he should accompany t he per·son carrying out the test. He should be
t ra ined to recognise danger and, if necessary, to render assistance in the
event of an emergency {sec appendix 3).
ADJUSTMENTS 8quipment under test s hould be isolated whenever possible before any
AND adjustments or modificat.ions are made . If it is necessary to remove
MODIFICATIONS inspection covers or make internal adjustments whils t equipment is live,
for· example to set brushgear, then s uitable precautions s hould be taken
lo prevent injury. I nsulated tools and tempora ry insulated screens
s hould be used where necessary for· this purpose. The advant ages of
accompanied working s hould be taken into account.
Work on or near live hig h voltage systems with bare conductors is not
permitted. ·
BENCH When testing motors nfler repa ir on a work bench with integral s upplies
TESTING OF unci contro ls the herH'h and working area lwcome a tempo r arily
SMALL MOTORS d«?signated Lest area for the duration of the lest. Permanent or
temporary barriers are needed and unauthorised persons should nol
approach whilst testing is in progress. Suitably placed e mergency trip
butlons should be pro,•idccl at. each work bench used for this purpose. It
is preferable to treat such combined repair and test areas as
pernu1ncntly designat('d lest ar·eas staffed by c ompetent p erson s
undt•r the supervision of an authorised person .
lfi
CONTINUITY Subject to the exception noted below the practice of using mains leads in
TESTING series with a test lamp for testing commutators and winding continuity,
or for a ny other forms of continuity testing, s hould not be permitted.
Proprietary instruments or extra low voltage testers s hould be used
unless customers test specifications demand otherwise.
240VPROOF When these tests a re required, e.g. by contract s pecification , the test
TEST equipment should be constructed so that:
the test leads are adequately insulated and over s heathed and t he test
probes are fitted with s pring mounted retractable s heaths.
1.9.2 DC TESTS
ARMATURE The purpose of the Lest is Lo compare voltage drops across a rm atu re
DROP TEST coils. This may mean passing substant ial curren t, which may approach
load current val ues, t hrough a winding circuit so that voltage drops
between commuLators bars can be measured. The voltage measured will
depend on the cu rren t and on t he winding resistance. Care s hould be
taken to avoid contact wit h exposed commulaLor segments when drop
testing armatures. Variable voltages used for the Lest should be derived
from an unearthed somce and should be as low a magn itude as possible
consistent with the Lest current.
16
WINDING The foregoing advice also applies to the use of de s uppl ies for testing the
POLARITY polarity of field and stator windings and wound rotors. When shunt
TESTS windings are iest.ed it may be necessary io carry out drop tests at the
rated voltage of the machine in order lo si mulate service conditions.
Steps should be taken to discharge stored energy safely, for example by
gradually reducing the applied voltage.
GROWLER The growler induces a voltage into stator, armature or rotor windings in
order to enable s hort circuited turns to be identified by transformer
action. The magnitude of the induced voltage depends upon the winding
design of both the growler and the equipment under iesi. Contact with
bare cable ends and other exposed conductors, for example sLator lead
connections, commutator s and rotor slip rings, s hould be avoided.
Similar conditions occur if one winding of a dual wound machine is
supplied from an ac source. Adequate precautions are necessary lo
prevent. inadvertent contact with the connections to the other windings
as dangerous voltages may be induced.
CORE TESTS As low an ac voltage as reasonably practicable should be used for this
test, consistent with the factors which innuence the desired magnetic
nux, for example core size, number of turns of t.esl cable and the
available current. output. Any joints in the test circui t. should be suitably
insu lated and the cable size shou ld be adequate to avoid overheating.
The core under test shou ld be e at"thed. Test. currents shou ld be
gradually lo a level below magnetic saturation while the core
is examined for areas of local overheating.
1.10.1 PURPOSE
17
1.10.3 HV PRESSURE TESTS ON LV EQUIPMENT
PRESSURE HV pressure test sets with maximum voltages of the order of SkV may
TEST SETS be portable or transportable. Other functions are often included in
sma ller equipment with lower output vollages. For example portable
appliance testers with a means for insulation resistance testing,
protective conductor continuity testing and pressure t esting have
output currents usually limited to 5mA or less. Larger equipment
intended only for pressure t esting may not be cWTent.limiLed to a safe
value. Such equipment is often available with substantially insulated
and screened test probes which designed to be hand held.
TEST SET HV pressure test sets should be provided with the following controls,
FITTINGS indication and protection:
HV TEST LEADS HV test probes should have insulated handles, finger guards and spring
AND PROBES loaded retractable screening sleeves covering the electrode tips as shown
in the adjoining illustration. The cable should enter on the side of the
gua rd which is remote from the operator's hand. Only insulat.ed and
sheathed flexible test leads suitable for the maximum operating voltage
of the test set shou ld be used. The leads should be t.erminated at the tesl
sel so that no bare conductors are exposed.
HANDLE
INSULATING DISC
l'tlftll'l' (): probe for use wtlh lt'st set output \'oil ages nut cxcl'f'dtng 1)()()1)\ ' ;tt
18
EARTH Pressure test set output voltage may or may not be referenced to eat·th
REFERENCE but a Lest probe which is normally connected to earth s hould be clearly
ident.ificd . IL is preferable that the HV s upply to hand held probes is not
referenced to earth.
PROCEDURE Pressure testing should be carried out only in a des ignated test area
unless HV outpu t curren ts are limited to 5mA or less. All pressure
tes ting s hould be car ried out by an authorised pers on or a
c ompe tent p e r son acting under hi s immediate s upervis ion. As an
additional safeguard, pressure test sets with an output current not
exceeding 5mA are recom mended for use in a ny Lest. where it is
reasonably practicable to perform the t.cst within this limitation.
The person carrying out a n HV pressure test s hould first check that.
the les t equipment is undamaged and safe for use, the insulation of test
leads and probes is intact and that the probe screening s leeves operate
correcUy. Any defects s hould be repa ired before the equipment is used.
FIXED Fixed pressure tes t sets generally do not incorporate hand held probes
PRESSURE but require HV test connections to t he equipment undet· test to be made
TESTS at the back of the test seL.
2> The use of an operator's spring loaded foot swi t ch located at the
control console
19
NOTES
20
PART2
TESTING OF E LECTRICAL E QUIPMENT WHOSE RATED
VOLTAGE EXCEEDS LOW VOLTAGE
2.1 INTRODUCTION
Many repair wor kshops have no provis ion for high voltage supplies and
are limited to proving machines by static tests, HV pressure tes t s and
by LV t·unning tests, these tests being carried out in a per manently or
temporarily designated test a rea.
Some companies have provis ion for high voltage running test supplies.
In addition to the recommendations in Part 1, the advice which follows is
directed to HV tests carried out on equipment with rated volLages in
excess of low vol tage.
Thi s means t hat all high voltage conductors which are within reach of a
person a t work s hall be p•·otected to prevent. danger.
( 1) proved Lo he d ead;
The pe1·son who then undertakes the wor k shall be fully conversant with
the safely measu res adopted and with the extent and limitations of lhc
work l.o be done.
21
2.3 COMPLIANCE
ACCESS (a) no live HV conductors are exposed where they may be touched;
AUTHORISED (b) all HV test equipment a nd the conduct of HV tes ts is under the
PERSON immediate s upervi s ion of an authoris ed p e r s on who has
technical knowledge a nd experience in this class of wor k. This will
include the preparati'on, carrying ou t the tests and making all
equipment sa fe at the end of the test;
PRESSURE (d) s uitable precautions are take n to achieve pe rsonal safely during
TESTING AND the use of both fixed a nd lrans portable high voltage pressure
SPECIAL t est sets by equipment and methods of work which ensure that t he
PURPOSEHV ope rator is s afely sepa rated at. all times from bare conductors
TESTS and/or dangerous voltages.
LOW VOLTAGE Variable high voltage Lest supplies a re required lo enable equipme nt to
STARTING be run up to speed without. drawing excessive sta rting currents and to
facil ita te the testing of equipment of various rated voltage.
MV CB FS
OA M CCB
0>;<0
---o
, REGUlATING
__/. - -- I BOX
!I SUPPLIES
IRANSFORMER
f'j - - -
0 HV TEST
SUPPLY
TERMINALS
0
: J
1 r
Cl
1 ! j
...
AND INOICAIION
-
t:NC LOSUR(
•
.---------------.
• WITH ACCESS D<lOI1 • MV SUPPLY • WITH 1l RMINAL
' EN1..LOSUIU ,
'------·--·-----
HV CIRCUI I BAt AK( R MAY BE CUBICLE rYPE Wllt1 THf TEST SUPPLY EARTHING &WI ICII AS SHOWN
OR WIIHDRAWA!!U IYP( Wlf>i TRAN SFER (ARTHING rACILITY THE EARTHING fACiliTY SttOULD
B£ INTrRNAll' INTff<L{)(;KfO SO THAT Itt( If .>T SUPPLY C IRCUIT CAN NOT 13( [ ARTHEO
UNLESS IH[ URC.UII OR£ AKER IS OPEN
SUPPLY (a) Means should be provided to isolate secu rely the source of LV
ISOLATION supply, for example by padlocking.
REMOTE (c) Means should be provided to switch the LV supply and to control
CONTROL the regulating tt·ansformer from a safe position.
INTERLOCKING (d) The door to the test supply substation should be key interlocked
with the incoming supply isolator so that access for the purpose of
changing off load vollage selection links is only possible after lhe
supply has been made dead.
TEST SUPPLIES (e) The use of a standard delta-star distribution transforme r used as a
TRANSFORMER Lest s upply transfo rme r by energising the lower vollage (star)
winding from the regulating transformer output is not
r ecommended because the HV delta winding sup plyi n g the
equipment under test cannot be readily earth r eferenced. Thus an
earth fault occurring either in the unit, under test or on associated
HV test connections would not be detected.
UNREFERENCED (f) A single earth fault on an unre ferenced de lta system is unlikely to
SECONDARY cause immediate danger to person nel , but the occurrence of a
second earth fault on a different phase v.riU cause a short circuil.
Al though insulation should be proved before a running test is
started and although testing may be of relatively short duration
a nd continuously monitored it. is better practice not to consider this
method as other than an expedient.
HVCIRCUIT (h ) The test supply circuits described so far do not provide for voltage
and em-rent indication, for HV "circuit e lectrical protection 01· for
application of HV safety earthing when work is Lobe carried out on
lhe e lectri cal conn ecti o ns to the equipme nt unde r test. It is
recommended that all these functions should be provid ed by
including in the insta llation an HV circuit breaker rather than
making unco-ordinated arrangements lor measurement, protection
and safety ea1·thin g functi o n s. An adequately rated circ ui t
breaker with voltage tra nsformers, current transformers and a
circuit earth ing fa c ility is advised. In new installation;;
consideration should be given to airbr·eak or vacuum switchgear lo
minjmise !ire risks.
23
the applied t.est voltage. Additional emergency trips s hould be
provided, if the layout of the test area and its enclosure require
them.
PROTECTION (I) The HV circuit breaker should be fitted with a p1·otective relay
comprising instantaneous overcurrent and earth fau lt elements.
The secondary circuits of Voltage Transformers and Current
Tranforme rs should be earthed. Care should be taken to ensure
that current transformer secondary circuits are not. open circuited
whenever primary cur rent is flowing.
RATING AND All HV equipment should be suitably rated for the maximum system
PROTECTION voltage and prospective faul t current. HV test terminals should be
located in an enclosure with a hinged cover and slots in the bottom
through which the test cable Jugs wiU pass. The cover should be capable
of being secured in the closed position by a padlock, the key of which is at
all times in the charge of the authorised p e rs on.
INTERLOCKING Preferably, the cover should be mechanically key inte rloc ke d with the
LV c ircuit breaker controlling the HV test supply as shown in figure 4
(page 9) so the cover may be opened only when the circuit breaker is
open and so that the circuit breake1· cannot be closed unless the cover is
clo:>ed.
CffiCUlT If an HV circuit breaker controls the test supply <lirecUy, then the
EARTHING ci rcuit breaker 5hould include a lest circuit earth ing facility. This
feature should be included in the safety interlockin g scheme to ensu re
that the HV test terminals cover can be opened only when the HV
c irc uit breaker is in the ci1·cuit earth position.
24
FLEXIBLE Fl exible HV conductors for connection between test terminals and t he
CABLES termina ls of equip me n t under test s hould be s ingl e co re cables to
min i mise the risk of sh ort circuits. T h ey s hould be insulated for the
working voltage and furthe r· efficiently protected by an abrasion resistant
oversheath. If cables wilh a metallic braid a re used the braiding should
be earthed at one point. Terminal box covers or equivalent temporary
protection s hould be securely fixed before equipment under test is
energised.
I.R. TESTS de I.R. tests at lOOOV, 2500V and occasionally 5000V may be used to
determine absolute va lues of ins ulation resistance. The instruments may
be motor dri ven and s hould have inherentli mitation of de output current
lo safe values, as described in Section 1.10.2.
POLARISATION de polari sation index tests us ing either an J.R. tester or an ionisation
INDEX TEST meter (an electronic instrument calibrated to read leakage current)
determine ins ulation integrity by comparative values of resis tance or
leakage current al interva ls of time.
25
TESTING OF allowed to de cay through the voltmeter b e fore t est leads are
INSULATING disconnected.
OILS
The dielectric stre ngth of insulation oil is an important indication of its
condition. Only equipment designed and manufactured for determining
the electric s tre ngth of ins ulating oils should be used and the tes t s hould
be carried out in accordance with BS 148: 1972 (198 1) (see appendix 2).
The test equipment used is usua lly tra nsportable and includes a double
wound trans forme1· with a high voltage seconda ry outpuL. This winding
s hould be centre tapped to earth. The ac input to the test set is normally
either llOV or 240V si ngle phase and output voltage adjustment is
obtained by a variable a u to-tran sform er. The test is ca rried out by
a pplying the test voltage between two metal s pheres immersed in the oil
sample contained in a covered glass test cell. In modern eq uipment the
cell is positioned under a transparent hinged cover which is inte rlocked
with the incoming ac s upply thus making it impossible to oper·at.e Lhe
equipment. unless the safety cover is in place.
The s phe re gap should be set us ing the gauge provided and there should
be s ufficient oil in the tes ting vessel to cover the s phe res. The voltage
s hould be raised slowly and evenly to 30kV for used oil and to 40kV for
new oi l.
Oil s pillage should be cleaned up immedia tely and oil which may collect
on the insulators, cables and the inner s urface of the hinged cover s hould
be removed after each test.
PRESSURE Pressure tests on HV equipment, us ing fi xed or t ra ns porta ble test sets,
TES'l'S prove ins ulation integriLy by Lhc application of a s pecified Lest voltage in
excess of Lhe working vo!Lagc. The rn ajoriLy CJ f HV distribution and
indusLrial equipme nt operates ut voltages between 3 a nd 36 kV ,
demanding test voltages ranging from about 5 to over 70kV.
HV COIL TESTS HV dielectric loss angle or tan della test:; a rc a ppl ied during HV coil
manufacture according Lo a specification agreed with the customer. HV
tmpulse t ests are a lso used duri ng HV cor! manufactu re to prove the
rnlegrily of inter-turn insulation a nd aflcr coils have hecn placed in
a stator core, braced and wedged bl•forc tntt•rc·onncctton.
PRESSURE Pressure test sets for teslmg HV equipmC'nl are therefon· lar·gpr and
TEST SETS more powerful than the test equipment dt'st•ribcd rn Pa rt I. Oulpul leads
from thts equipment a re not. designed or intended to be hand-held but
need to be connected before the lest set is c•rwrgist•d.
TEST AREAS Large equipment under test e.g. rl'WOltrHl machrnes or repaired
switchboards wrll require a permarwnt l:v or lt•rnporarily dt'signated lest
.u·ea. A pcrmancnlly destgnalcd ll'sl arPa ts rccomnwtHI<'ll for HV coil
tests after manufacture. Suhscqu<'nl lPsls on installed coils cilhC'r in
works or on site will r<'qum• lcmpora.nly dc•stgn:tl<'d Lest ar('aS.
26
AUTHORISED All high voltage insulation testing should be under the direct control of a
PERSON trained and experienced person who is authorised to perform the test.
EQUIPMENT IN Equipment under test and conductors at hjgh voltage should be located
TEST AREAS inside a designated test area from which all persons should be excluded
AND CONTROL during the test. The press ure test set controls should be located outside
OF TEST the test area and should be arranged so that, when released, the test
VOLTAGE voltage is instantaneously cut off.
TEMPORARY TEST
SAFETY BARRIER '
I
SPRING LOADED
ANO VOLTAGE CONTACTS - -1--_ - -f----.L.._......_---11-
F iJ!III"I' 8 Basic prC'caut1 ons dunng HV p.-essure l t:>sung of HV m a clu n<> on ><lle
27
charge for safe systems of work and on employees who work in
s urroundings wher·e they are not protected by the safety featu res which
are recommended lfor permanent HV test areas.
EARTHING AND Pressure test sets for test voltages in excess of 5kV s hould normally
P ROTECTION have one pole permanently earth e d. The live and earth poles should be
OF PRESSURE clearly distinguished and the HV output overload protection should be
TEST SETS set to the lowest practicable value in all cases. It should be noted that
test set overload protection is provided Lo safeguard the test equipment
and does not provide protection from electric shock. A zero-volt
interlock on a spring-loaded voltage control is recommended. Release of
the control switch s hould cause the output voltage to fall to zero. The
addition of a s pring-loaded on-ofT button is recommended , thus requiring
the operator's two-hand control of the HV test set in order lo energise it
and regulate t.he applied voltage.
EARTHING fa) 'l'he base plate of the resistance column and therefor<' one terminal
of the indicating meter is normally connected to earth;
SAFETY The safeLy measures required for these tests do not vary from the safety
MEASURES FOR precautions already described above for testing HV eq uipment in
SPECIALHV general, the only difference being the type of test equipment used.
TESTS
For dielectric loss tests Lhis will include within the designated test area
Lhe equipment under test, a resistance column (with local or remote
voltmeter), a standard capacitor and a high voltage transformer. The
measuring bridges and LV variac for control of HV output voltage should
be located outside t h e designated test area at the test control position.
29
NOTES
PART3
WORK ON SI TE
3.1 INTRODUCTION
OTHER ln keeping with the purpose of the Code of Pt·actice, Par t 3 deals
HAZARDS principally with the minimising of electl'ical danget·. The nature of site
work also introduces other factors which m ay not be directly under the
control of a contractor working on site but may influence health and
safety generally. Examples of these other aspects, which may require
consideration and agreement. between the repairer and the customer on
any necessary precautionary measures, arc discussed in 3.3.1 and listed
in Appendix 6. Further advice on some of these subjects is obtainable
from area offices of the H ealth and Safety Executive.
HSWACT The provisions of the Health and Safety at Work etc Act (the H.S.W. Act,
see Appendix 4 ) apply lo all activities where persons a re at work.
RELEVANT Important requirements of the HSW Act are expressed in sections of the
SECTIONS OF Act which are described in appendix 4. These sections of the HSW Act
THEHSWACT are relevant to AEMT member com panies, both in companies' own works
and on site. The requirements of Section 3 have an obvious relevance to
site work and app ly mutually to the repaire r an d customer. The
requirements of Section 6 (3), dealing with erection and installation are
of direct concern to contractors working on s ite.
EAW l n addition to the duties imposed by lhe HSW Act, lhe E lectrici ty at
REGULATIONS Wor·k Regulations 1989 CEA W Regulations) place duties on the duty
holders in respect of electrical systems, equipment, conductors and in
respect of work on or neat· electrical equipment. in so far as they relate lo
matters within persons' control.
ELECTRICAL Measures wruch are taken for the protection of persons from contact with
TESTING live conductors, whether by barriers or systems of work or combinations
PROCEDURES of t hese methods need to be rigorous ly a pplied and maintained. Mis takes
made on site are likely to have more serious consequences than in the
established working environment of the r epair s hop.
WORKING Th e person represe ntin g the rep a irer s hould obt.ain all po ss ibl e
INFORMATION information about t.he job during initial discussions with the customer.
Th e fuller the inform ation the bet ter is t he repa ire r able to select
s uitable staff and equipment to complete t he job safely and efficiently.
PERSONS ON Repair personnel who work on s ite mus t be competent and r esponsible
SITE WORK persons who are capa ble of dea ling with problems outside their normal
place of work. The person in charge must. be capable of representing the
r e pairer on matter·s of safety and technique, must be conve rs ant with
s afe working practices and have su ffi cie nt technical knowledge a nd
expe rie nce to avoid dange r to himself or· others.
PERSON IN This t.it.le refe rs to the senior person on site work who is in charge of
CHARGE ca rry ing out the work in ha nd. The person in cha rge may not have a
s uperv isory title but. h as the r espon s ibility e.g. a s kill ed e ngineer
accompanied by an apprentice. On occasion a person may have to work
on s ite alone and therefore would be deftncd as the person in charge.
SITE On arri val at site t he re pair s taff should report to a designated member
PROCEDURES of the customer's staff who should continue to be res pons ible for the
organisation of a ll n eces!"ary cust omer/ repa ire r l iaison while th e
rcpa ir·er's staff are on s ite. At this time the repaire r s hould obtai n from
the customer , and unde rstand s ufficienlly !'or the purpose of his work ,
the s ite procedures for:
(b) t he s ummon ing of immediate ftrsl aid equipment and assist a nce. A
very worthwhile precaution is Lhe ins tallation of a ftrst aid outfit in
all service vehicles for possible usc on isolated or ill-equipped sites;
CdJ the applicat ion of site safely rui<'s, includi ng an) procedu r e!'
s pecific to.thc customer's industry; and
SEGREGATION Whe n necessa ry because of the proximity of other persons or plan t, lhe
OF WORKING working area shou ld be separated by barnl•rs filLed with notices warn111g
AREAS unauthorised perso ns lo keep out.
Th(• re paire r should make s ure that il rs rwnnissibh• Ln usc an) naked
namP or welding Pquipment which may IH' rwct•ssary .
ll is the cu stomer's res ponsibility to maintain guards fi tted to protect
moving parts of machinery which remain in service but the repairer is
advised to keep clear of any pla nt not involved with his own work.
LIFTING AND An early decision should be made by the customer and the repairer as to
OTHER who will provide any required lifting tackle. If temporarily erected lifting
FACILITIES tackle is to be used the repai rer s hould consult the cus tomer and satisfy
himself regarding the adequacy of proposed anchorage or suspension
points.
Agreement should also be sought on the use of any other plant, tools or
workshop facilities thai may be made available by the cus tomer.
OTHER There a rc other non-electrical safety aspects which s hould be taken into
HAZARDS account when planning a safe system of work on a customer's site.
Further examples of these which may require joint consideration and
decisions a re listed in a ppendix 6.
LEAVING SITE Before leaving a work siLe, for example for meal breaks or at night, the
repai rer s hould ensure that barriers an d warni ng notices a re in place
and that there is no source of danger which might a ffect others in t he
vicinity of lhe working a rea fo r which he is responsible.
Afle1· more prolonged absences from t he site, for example over a weekend
or due lo an unforeseen delay, safety meas ures s uch as electrical
isolation should be checked before recommen cing work.
Before finally leaving site the repairer s hould ens ure t hat the working
area is left in a safe condi tion , s ubject to any particu la r agreements made
with the customer.
PO\VER The \'Oltage, f1·equency and power of electrical s upplies on site are fixed
SUPPLIES b) the design of the customer·s installation and the ty pes of plant which
the insta llation serves. The method of stas·ting ac or de motors will be
already det.ermined by t he type and size of machine, the conditions of
operation and the need to limit s tarting currents to acceptable values.
With the exception of s mall power supplies which may be controlled by a
va riable transformer Lhe repairer is unable to utilize t.he variable voltage
s upplies which a re norma lly avai lable in the works hop for Lesl purposes.
This consideration reinforc<.-s Lhe need for equipment under tesl with iLc;
control gear. electrical protection and connections to be restored to a safe
operational stale before energisation a fter repair.
CONTROL OF In cons ultation on site with the customer the repairer should note the
ELECTRICAL poi nts a t which all electrical s upplies to the plant on which he will be
SUPPLIES working can be made d ead, for exampl e al sockets, fuseboards,
switch es and circuit ba·eaker·s. If the repairer JH given sole control of
one or more sources of suppl.v he s hould a ppoint an authorised p e r·son
who unde rtakes respon sibility for t he control of d a nger from those
sources. If, on the other hand, the customer remains in control of the
danger , for example by the issue to the repairer of a pe rmit to work,
then h e s hould appoint an a uthorised p e r s on who unde r takes
responsibility for the con t rol of danger from sources under the customers
cont rol. A t hird possibility is that t he customer does not employ any
person s competent for more t han the routine work of opera ting the
plant, in which case the repaire r whom the cu stomer calls s hou ld
appoin t the authorised p er son.
ISOLATION Work on or nea r bare conductors should be performed only a fter the
PROCEDURES conductors have been first made d ead and appropriate measures taken
to prevent them being made inadvertently live. Measures will include
visible disconnection by withdrawing a plug, removal of fuses together
with the posting of caution notices, and locking ofT switches. Unless it is
self-evident that the isolation procedure will make the selected circuit.
dead, it is recommended that a verification test is carried out using a
safely constructed voltage indicator (preferably not a multimeler ), before
any assumptions a re made abou t safety. T he duty of carrying out safe
isolation procedures prior to work on or near conductors falls to the
authorised p e rs on.
CONTROL Repair personnel should pay attention to the possible presence of other
AUXILIARY AND circuits which may be a source of danger. These may incl ude control and
STANDBY interlocking circui ts, cubicle lighting, anti- condensation heate rs and
SUPPLIES emergency or stand-by s upplies. When referen ce to drawings or other
records is not poss ible, extra care s hould be taken by authori sed
p erso n s to ensure t h al s uch ci rcuits are initially made d ead and
securely isolated if they a re otherwise likely lobe a source of dangel'.
PERMITS TO P et·mits to w ork may be issued by some customers for work on the
WORK principal parts of LV supply systems, for example switchboard infeeds
and int.e rconnectors but, for LV work gene rally. implementing the
principles of safe and secure isolation meets the safety objective.
bonded connected together eleclrically, not normally for the purpose of carrying
current but so as to ensure a common potential.
circuit a mecha nical device for making and breaking an electrical ci rcuit u nder
breaker load, overload and short ci rcuit conditions.
d ead al or about zero potential and disconnected from any live system.
earthe d connected to the general mass of earth in s uch a manner as \vill en sure
at all times an immed iate discharge of electrical energy danger.
interlock a device which makes the operation of a switching device dependent upon
the position or operation of one or more other pieces of equipment..
NOTE A switch may br capable of mak1ng, but not breaking, short circu1t currents
35
extral.ow a voltage in a system not normally exceeding 50V ac or 120V de.
voltage
reduced a supply for UOV portable Loots etc., not exceeding 55V to earth in single
voltage supply phase systems (or 64V to earth in three phase systems).
HSWACT The provisions of the Health and Safety at Work etc. Act 1974 (the HSW
Acl, see appendix 2) apply to all activities where persons a re at work.
relevant Important requirements of the HSW Act are expressed in sections of the
sections of Act which are described in a ppendix 4. These sections of th e Act are
tbeHSWAct relevant to AEMT member companies, both in com panies' own works
and on site.
Electricity The Electricity at Work Regulations 1989 (the EAW Regulations, sec
at Work appendix 2) took effect from 1 April 1990, when the Electt-icit.y (Factories
Regulations Act) Special Regulations 1908 and 1944 were revoked.
The EA W Regul ations a pply wherever the HSW Act a pplies and are
directed to prevention of electr ic danger from s hock , burn , arci ng,
explosion or fire. Duties arc placed on employers, lhe self-employed and
employees to comply with the Regulations in relation to matters within
their control.
36
APPENDIX2
REFERENCES
lEE The current issue of regulations for Electrical Ins tallations published by
REGULATIONS the Institution of Electrical Engineers, obtainable from:
HSWACT The Health and Safety at Work etc. Act. 1974, obtainable from HMSO
bookshops.
MEMOR.A:NDUM Health and Safety Executive B-ooklet HS(R) 25, obtainable from HMSO
OF GUIDANCE bookshops (gives guidance on the relevant regulations, based on legal
ON THE requirements)
ELE CTRICITY
AT WORK
REGULATIONS
1989
BRITISH BS 88: Cartridge fuses for voltages up to and including 1000V a.c. and
STANDARDS 1500V d.c. (in several parts; see BSI Year Book or BSI Sectional List 26.
for further reference).
37
BS 6626:1985 Code of P ractice for maintenance of electrical switchgear
and control gear for voltages above 650V and up to and including 36KV.
Sales Department.
British Standards I nstitution
Linford Wood
Milton Keynes
MK14 6LE
The current British Standard catalogue and com plete sets of British
Standards are kept for reference in the UK in the principal public
libraries.
HEALTH AND The regularly updated library listing of all Heallh and Safety Executive
SAFETY publications, known as t.he Publications in Series List, is available free of
EXECUTIVE charge from the offices of the Health and Safely Executive.
38
APPENDIX3
NOTE ON ACCOMPANIED WORKING
The former legal requirement for accompanied working in cer tain defined
circumstances no longer exists. In the Electricity At Work Regulations
1989, this subject is addressed in the guidance to Regulation 14 which
considers the need to take precautions in order to prevent injury.
This Code, written t.o guide the staff of AEMT member companies and
others concerned with s afety in testi ng, contains practical advice to
supplement. lhe Memorandum of guidance on the Electricity At Wor·k
Regulations. In circumstances such as any of the following the AEMT
recommend s accom panied working, without prejudice to the legal
requirement expressed in Regulation 14 :
3> where a s killed pe rson needs assistance to perform his task safely ,
e.g. with an accompanying perso n to hold in place temporary
ins u lation or screening to enable safe completion of the task;
81 where the working envi r onment e.g. fumes or poor lighl could
cause drowsiness or impair judgement. to the detriment of
performance;
39
9) when field activities such as vibration analysis and balancing arc
called for it may be advisable for the person car rying out t he work
to be accompanied in adverse working conditions;
NOTE2 Skilled persons who are sent on site have a res ponsibility to
work sa fely and to report back to their su pervisor in
circumstances where they see the need for the latter's safety
or technical advice, or foresee a need for assistance in order
to be able to continue their work safely.
NOTE3 It has been the custom for repairer personnel to work long
hours, so metimes in difficult site conditions, in order to
minimise the time required to repair urge ntly required
equipment..
[tis the res pon sibi lity of the employer or the person in
charge of the work to organise s uch w01·k and to allocate
sufficient labour to preclude excessive fatigue, maintain safe
working practices and minimise the risk of injury.
40
APPENDIX4
NOTES ON THE HEALTH AND SAFETY AT WORK ETC ACT 1974
Section 2 deals with particular duties of every employer. I l calls for the
provision and maintenance of plant and systems of work that are safe;
arrangemenLs for ensuring safety and absence of ris k to health from the
u se etc. of articles and substances; the provision of information ,
instruction, t raini ng and supervision necessary to ensure hea lth and
safely of employees; the maintenance of any place of work et.c. under the
employers' control in a condition that is safe and without r·is k lo health;
and finally lhe provision and maintenance of a working environment. that
is safe and wilhoul risk to health. Each part. of Section 2 is qualified by
the words 'so far as is reasonably practicable'.
I n brief, t his SecLion of the Act now includes a rt.icles of fai rground
equipment. as well as a rticles for use a t. work and t.he new wording of
Sectio n 6 ( l) (a) replaces "properly used" by "set, used, cleaned or
maintained by a person at work".
/I:OTE When neccssar-'. further referenct> be mnde to pnrttcular sccltons of the Act.
41
APPENDIX5
MECHANICAL HANDLING E Q UIPMENT, MECHANICAL AND
OTHER RISKS ASSOC IATED WITH TESTING
SAFETY RECOMMENDATIONS
TRUCKS Trucks used for loading and unloading in a test area s hould not be
operated during the test. If equipmen t is being tested on a pallet, the
truck sh ould be un loaded so that the pallet rests firmly on the ground.
HOISTS Mechanical hoists with long hand chains a nd slings s hou ld be kept
outside a test area when not in use.
OVERHEAD Overhead cranes should not be permitted to travel or park over a test
CRANES a rea except with the permission of the test engineer. The test engineer
shou ld be responsible for ensuring that. these conditions arc satisfied and
that, when necessary, t he passage of a cra ne over a test area or loading
or unloading within a test area is carried out under his direction.
LOAD Equipment s uch a s res istance banks used for starting or load testing,
RESISTANCES which are known t o get h ot, s h ould be adequately gu a r ded and
ventilated. Such equipment should, if possible, be permanently installed
and s uitably protected. (Arrangements s hould be made, when necessary,
for safe load switching).
UNGUARDE D All dangerous moving parts should be guarded unless safe by position or
MOVING PARTS constru ction. Exposed moving parts s uch as cooling fans s hould be fitted
only if they can be guarded. If unguarded fans must be fitted temporary
ba rrier s s hould be placed so as to prevent access. Unused s haft keys
s hould be removed from s hafts.
APPAREL Ties, loose clothing, rings, necklaces a nd loose bracelets s hould not be
worn in a tes t area. Long ha ir should be restrained.
MAGNETS It. s hould be noted that large electromagnets which a rc energised can
exct"l considerable a nd s udden forces on loose ferrous tools a nd materials
which may be i11 usc, being transported or lying in t he vicinity at the
workplace. Appropriate precautions s hould be taken by an a uthorised
person before high power lifting magnets or similar pl ant arc energised.
42
APPENDIX6
EXAMPLE S OF OTHER SAFETY, HEALTH AND WELFARE
CONS IDERATIONS APPLYING TO WORK ON SITE
The following list includes other examples of subjects which may require
joint considerations and decisions by the repaire1· a nd the customer when
planning for health safety and welfare:
APPENDIX 7
ABBREVIATION
ac Alternating cu1Tent HSW Act Health and Safely al
Work etc Act 1974
BS British Standard
HV High voltagt'
BSI British Standards
Tnsli lution lEE lnstituLion of Electrical
Engineers
CIBS Chartcrl.'d Institute of
Building Services k\' IGiovolt
43
APPENDIXS
COMMUTATOR AND SLIPRlNG MAINTENANCE BY THE USE
OF HAND HELD STONES OR GRINDING TOOLS
Although this process cannot be termed testi ng the following advice and
gujdance is included in this Code in the interest of safety.
AJso brush bedding s tones are often used to bed new carbon brushes to a
commutator surface. Both are referred to below as grinding processes.
Using rubber gloves and safely glasses as hand and eye protection
* Selecting stones with C01-rect size, shape and grit to suit the surface
and speed of the colleclor being restored
14
Remember-
Electric shock can be fatal. If safety
is in doubt, switch off and seek advice
AEMTLtd
St Saviours House
Published St Saviours Place
YORK YOI 7PJ
Tel: 01904 674899
Fax: 01904 674896
'!:> A£MT Fobru•ry 1991