You are on page 1of 3

50  Application

High voltage from


the socket outlet
On-site insulation testing of gas-insulated switchgear systems (GIS)
SIEMENS Transmission & Distribution (T&D) from Grenoble in France, has many years of experience
in constructing gas-insulated switchgear (GIS) systems. However, remaining successful in the face
of ever shorter project times, in a market with strong competition using high-level solutions, re-
quires constant improvements to project processes and use of the latest technology. SIEMENS T&D
has been using OMICRON testing devices for years to ensure efficient testing of its primary and
secondary equipment. Experts from SIEMENS T&D and OMICRON recently got together to try out a
new method for optimizing the high-voltage insulation testing of GIS. Following successful tests in
the Grenoble factory, the multifunctional CPC 100 primary testing system and the new CP RC reso-
nance circuit are now proven for use throughout the world.

By Marina Pajak and Renaud Verjus, Siemens T&D France


Till Welfonder, OMICRON

High-voltage testing of GIS systems can also get into the system during on-site
Gas-insulated switchgear systems are assembly. As such, an on-site insulation
made up of many encapsulated elements. test needs to be performed. For this "stress
The internal high-voltage conductor is test", a voltage higher than 1.5 times the
insulated from the metallic wall of the nominal voltage is applied.
capsule, which is at ground potential,
using pressurized SF6 gas. The dielectric Previous method of testing
strength of the system is optimally dimen- To date, a high-voltage generator and a
sioned based on the respective voltage special coupling mechanism (filled with
level, as the size of the system has a direct SF6 gas and connected to the respective
influence on its costs. Sharp edges, metal busbar) have typically been used for on-
shavings, or impurities which find their site testing. The equipment in this set-up
way into the system during installation weighs around 2.5 tons and needs to be
can lead to electrical breakdown of the transported from one construction site
Time-consuming: To date, a high-voltage insulation at high voltages. GIS bays which to the next in a 15 cubic meter container,
generator and a special coupling mechanism
are prefabricated as a unit, are already often via a cargo flight, frequently hav-
(filled with SF6 gas and connected to the respec-
tive busbar) have typically been used for on-site provisionally filled with gas and subjected ing to take into account the often strict
testing of a gas-insulated switchgear system. to a dielectric strength test in the factory. customs regulations. This has always
They are then sealed and transported to required precise logistics and often cre-
the construction site. However, impurities ated considerable costs. Once on-site, the

OMICRON  Magazine | Volume 2 Issue 2 2011


Application  51

First project assignment in Peru: A new 72.5 kV type 8DN8-4 GIS is tested with
the CPC 100 primary testing system and the new CP RC resonance circuit.

»Our on-site engineer was particularly impressed by the


simplicity of the approach and its ease of use.«

assembly of the system takes up a lot of up to 200 kV to be generated on the GIS


valuable space, and is both difficult and side. The system is portable and, depend-
time-consuming – requiring a crane and ing on capacity, can be ideally matched to
the careful precautions which are essential the GIS using one or more CP RC units.
when working with gas. Marina Pajak
Specially adapted voltage transformers Project manager,
The new OMICRON CPC 100 + CP RC system Unlike a regular voltage transformers (VT), Siemens T&D France
The CP RC resonance system is coupled this one is not only used for measure-
to the GIS via a specially designed volt- ment purposes, it also serves as a test
age transformer for secondary injection, transformer. The VT must be specifically
together they form a parallel resonant cir- designed for this, as the power required
cuit. Controlled by the CPC 100, this circuit for the high-voltage test is supplied on
can be excited at its resonant frequency. the low-voltage side. SIEMENS T&D now
Operating from the low-voltage supply of integrates these special power VTs in to its
the CPC 100, this allows a high voltage of new GIS systems in the factory. This allows

OMICRON  Magazine | Volume 2 Issue 2 2011


52  Application

the systems to be tested by simply con-


necting the CPC 100 and the CP RC. Since
the transformers remain a permanent part Renaud Verjus
of the system, it is also easy to repeat the
Expert for dielectrical GIS testing
tests for maintenance purposes. and commissioning,
Siemens T&D France

Initial testing at the


SIEMENS T&D facility
Experts from SIEMENS and OMICRON
got together in March 2011 to perform The material was dispatched on time and remains sealed, as the transformers are
successful tests in SIEMENS T&D's high- there were no issues with customs. The already pre-installed in the factory. This
voltage laboratory. Once completed, these test set-up was soon ready for use, the eliminates the risk of dust getting into the
proved the suitability of the equipment for resonance point was found, and all tests system and the need for gas work."
on-site application. were accepted by the end customer. Just
a few hours after completion, the project The slightly higher costs of the transformer
First project deployment leader Marina Pajak called us to confirm: are easily compensated by the many
The first deployment took place at the be- "The application was a resounding success. advantages it offers. The old method
ginning of April 2011 for a project in Peru. The tests were all performed quickly and also required a great deal of space to be
A new 72.5 kV type 8DN8-4 GIS from with no problems. Our on-site engineer allocated for the test equipment during
SIEMENS was tested with 120 kV. It was was particularly impressed by the simplicity construction of the building, which also
possible to successfully test the system, of the approach and its ease of use." had an effect on costs. "None of this is
which is made up of three panels (1.2 nF necessary with the new approach, as we
per panel) and a single busbar, in under Comparison of the methods from a can simply position the testing device
two days – including the preparations testing engineer's perspective directly in front of the busbar," confirms
and the customer acceptance tests. Using "For a comparable system, we used to Renaud Verjus.
standard systems, these tests used to take require twice as much time and more than
more than twice as long. twice the staff. This system allows not Looking ahead
only that one person alone can now do SIEMENS has purchased two of the new
OMICRON Product Manager Lutz Hulka this test, but the whole process is signifi- systems and is already planning further
accompanied French testing engineer cantly faster," was the conclusion drawn applications in other countries. To make
Renaud Verjus from SIEMENS T&D for this by Renaud Verjus. He also considers the the modular system even more versatile,
first project. The goal here was to gain new method superior in terms of safety, collaborative work has also begun on
some on-site experience under real-world environmental friendliness, and the risks further improvements. Consideration
conditions. involved: "Modification work is no longer has even been given to a business idea
needed just to perform the tests. And we in a completely different field; using the
no longer need a crane. Yet perhaps the CPC 100 + CP RC in the service business
most important benefit is that the system to maintain worldwide parks with aging
systems installed.

With the multifunctional primary testing


system CPC 100 and the new CP RC resonance
circuit, it is possible to test high-voltage gas
insulated switchgear systems with a maximum
test voltage of 235 kV suitable for equipment
rated at 132 kV.
OMICRON  Magazine | Volume 2 Issue 2 2011

You might also like