5-STOREY BUILDING

Site Preparation .................................................................................................................................3


Site Clearing .................................................................................................................................................. 3
Clearing & Grubbing...................................................................................................................................... 3
Trees & Shrubs removed............................................................................................................................... 3
Foundations 3
Earth Shaping ................................................................................................................................................ 3
Levelling &Grading ........................................................................................................................................ 3
Excavation & Fill ............................................................................................................................................ 3
Foundations .................................................................................................................................................. 3
Isolated Footing ............................................................................................................................................ 3
Structure 3
Columns , Beams & Slabs .............................................................................................................................. 3
Formwork Installation ................................................................................................................................... 3
Reinforcement ............................................................................................................................................. 3
Concreting ..................................................................................................................................................... 3
Interior Walls ................................................................................................................................................ 4
Exterior Walls ............................................................................................................................................... 4
Floors............................................................................................................................................................. 4
Openings 4
Doors ............................................................................................................................................................. 4
Windows ....................................................................................................................................................... 4
Services 4
Conveying...................................................................................................................................................... 4
Lifts & Elevators ............................................................................................................................................ 4
1 SITE PREPARATION

1.1 SITE CLEARING

1.1.1 CLEARING & GRUBBING

1.1.1.1 SELECTIVE CLEARING

1.1.2 TREES & SHRUBS REMOVED

1.1.2.1 TREES REMOVED

1.1.2.2 SHRUBS REMOVED

2 FOUNDATIONS

2.1 EARTH SHAPING

2.1.1 LEVELLING &GRADING

2.1.1.1 ROUGH LEVELLING

2.1.1.2 FINISH LEVELLING

2.1.2 EXCAVATION & FILL

2.1.2.1 EXCAVATION

2.1.2.2 FILL

2.1.2.3 COMPACTION

2.2 FOUNDATIONS

2.2.1 ISOLATED FOOTING

3 STRUCTURE

3.1 COLUMNS , BEAMS & SLABS

3.1.1 FORMWORK INSTALLATION

3.1.2 REINFORCEMENT

3.1.3 CONCRETING
3.2 INTERIOR WALLS

3.3 EXTERIOR WALLS

3.4 FLOORS

4 OPENINGS

4.1 DOORS

4.2 WINDOWS

5 SERVICES

5.1 CONVEYING

5.1.1 LIFTS & ELEVATORS

5.1.1.1 SHAFT PREPARATION

5.1.1.2 LIFTING SYSTEM