You are on page 1of 2

CHIONG, ANGELINE D.

EM 156 – Probset 2
2014-16900 Gabriel Pamintuan Jr., PhD

Given:
• Production drifts: 24.4m
• Production x-cuts: 12.2m
• Drift size: 4.2m x 4.1m
• Ore passes: 200m apart
• Caving rate: 0.30m/day

General Assumptions:
• Tramming distance is
minimized by assigning
draw points 1-8 to Ore
Pass 1 and draw points
9-16 to Ore Pass 2.
• Maximum tramming
distance = 100m
• Maximum truck speed =
10kph (up to 2nd gear)
• Available operating time
= 350min/shift for 3
shifts/day
• Loaded bucket maximum
capacity = 10 DMT

Time Motion Studies of Sandvik LH410-14

SEGMENT Seconds Minutes Hours


Fixed Times (After loading)
Back-out of draw point 0 0 0
Bucket to carry position 7.500 0.125 0.002
Maneuver 2.424 0.040 0.001
Travel to Dumping Point
Hauling 19.2 0.320 0.005
Fixed Times (Dumping Point)
Maneuver into dumping point 5.667 0.094 0.002
Lift bucket to dump 7.500 0.125 0.002
Dumping 2.200 0.037 0.001
Lower Bucket 4.000 0.067 0.001
Maneuver out of dumping point 5.667 0.094 0.002
Travel to Draw Point
Empty return 19.2 0.320 0.005
Fixed Times (Loading)
Maneuver into draw point 2.424 0 0
Lower bucket to digging position 4.000 0.067 0.001
Dig 7.500 0.125 0.002
TOTAL CYCLE TIME 87.281 1.455 0.024
CHIONG, ANGELINE D. EM 156 – Probset 2
2014-16900 Gabriel Pamintuan Jr., PhD

Other assumptions:
• 1st gear – driving speed for maneuvering
• 2nd gear – driving speed in production drifts
• No need to back out of draw point since the LHD will not enter the crosscuts anymore. Only
the buckets will maneuver towards the crosscuts.
• In maneuvering after loading, the turning angle of 42.5 degrees, and the average of the inner
and outer turning radius of 3.635m was used.
• In traveling to and from the dumping point, the average distance from drawpoint to ore passes
of 51.2m was used.
• Maneuvering in and out of the dumping point are done at 8.5m from the ore pass.
• Digging time is the same as the lifting of bucket.

Driving
kph mps
Speeds
1st gear 5.4 1.5
2nd gear 9.6 2.7

Draw Draw Distance to/from OP


Distance to/from OP (m)
point point (m)
1 8.5 9 93.9
2 20.7 10 81.7
3 32.9 11 69.5
4 45.1 12 57.3
5 57.3 13 45.1
6 69.5 14 32.9
7 81.7 15 20.7
8 93.9 16 8.5
AVERAGE 51.2

1. Production Capacity per LHD per day


𝑇𝑜𝑡𝑎𝑙 𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝑡𝑖𝑚𝑒 𝑡𝑜 ℎ𝑎𝑢𝑙 𝑝𝑒𝑟 𝑑𝑎𝑦 × 𝐵𝑢𝑐𝑘𝑒𝑡 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦
𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 =
𝑇𝑜𝑡𝑎𝑙 𝑐𝑦𝑐𝑙𝑒 𝑡𝑖𝑚𝑒
𝑚𝑖𝑛 ℎ𝑟 𝑠ℎ𝑖𝑓𝑡𝑠 1ℎ𝑟
(50 ×7 ×3 )× × 10 𝐷𝑀𝑇
ℎ𝑟 𝑠ℎ𝑖𝑓𝑡 𝑑𝑎𝑦 60 𝑚𝑖𝑛
=
0.024 ℎ𝑟
= 𝟕𝟐𝟏𝟖. 𝟏𝟎𝟓 𝑫𝑴𝑻 𝒑𝒆𝒓 𝑳𝑯𝑫 𝒑𝒆𝒓 𝒅𝒂𝒚

2. Number of units required based on tonnage requirement


𝑇𝑜𝑛𝑛𝑎𝑔𝑒 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡
𝑁𝑜. 𝑜𝑓 𝑢𝑛𝑖𝑡𝑠 =
𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦
25,000 𝐷𝑀𝑇/𝑑𝑎𝑦
=
7218.105 𝐷𝑀𝑇/𝐿𝐻𝐷/𝑑𝑎𝑦
= 𝟑. 𝟒𝟔𝟒 ≈ 𝟒 𝒖𝒏𝒊𝒕𝒔 𝒐𝒇 𝑳𝑯𝑫

3. Cost of hauling per ton


𝑁𝑜. 𝑜𝑓 𝑢𝑛𝑖𝑡𝑠 × 𝑃𝑜𝑤𝑒𝑟 𝑜𝑢𝑡𝑝𝑢𝑡 × 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑡𝑖𝑚𝑒 × 𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐𝑖𝑡𝑦 𝑟𝑎𝑡𝑒
𝐶𝑜𝑠𝑡 𝑝𝑒𝑟 𝑡𝑜𝑛 =
𝑇𝑜𝑛𝑛𝑎𝑔𝑒 𝑝𝑒𝑟 𝑑𝑎𝑦
ℎ𝑜𝑢𝑟𝑠 𝑃ℎ𝑝
4 𝑢𝑛𝑖𝑡𝑠 × 220 𝑘𝑊 × 17.5 × 5.84
𝑑𝑎𝑦 𝑘𝑊ℎ
=
25,000 𝐷𝑀𝑇/𝑑𝑎𝑦
= 𝑷𝒉𝒑 𝟑. 𝟓𝟗𝟕 𝒑𝒆𝒓 𝑫𝑴𝑻

You might also like