CRONOGRAMA VALORIZADO DE OBRA

BRA: "MEJORAMIENTO Y ACONDICIONAMIENTO DE LOS SERVICIOS RECREATIVOS Y PASIVOS EN LA PLAZA CONSTITUCION DEL DISTRITO DE YAUYOS, PROVINCIA DE YAUYOS - LIMA

MES 1 MES 2 MES 3 MES 4

N° Partidas Unid. Metrado C.U. Precios Parcial


Valorizacion Valorizacion Valorizacion Valorizacion
Metrado % de Avance Metrado % de Avance Metrado % de Avance Metrado % de Avance
Mensual S/. Mensual S/. Mensual S/. Mensual S/.

01 OBRAS PROVISIONALES 4,233.11


01.01 CARTEL DE OBRA EN MADERA DE 3.60M X 2.40M und 1.00 1,054.15 1,054.15 1.00 1,054.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.02 ALQUILER DE LOCAL PARA LA OBRA mes 4.00 300.00 1,200.00 1.00 300.00 25.00% 1.00 300.00 25.00% 1.00 300.00 25.00% 1.00 300.00 25.00%
01.03 CERCO PERIMETRICO DE MALLA RASCHEL Y POSTE DE EUCALIPTO m 167.55 10.71 1,794.46 167.55 1,794.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04 SEÑALIZACION EN OBRA DURANTE EJECUCION m 123.00 1.50 184.50 30.75 46.13 25.00% 30.75 46.13 25.00% 30.75 46.13 25.00% 30.75 46.13 25.00%
02 TRABAJOS PRELIMINARES 4,747.47
02.01 LIMPIEZA MANUAL DE TERRENO CON PRESENCIA DE MALEZA Y VEGE m2 1,677.28 0.42 704.46 1,677.28 704.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02 TRAZO, NIVELACION Y REPALNTEO CON EQUIPO (ESTACION) m2 1,677.28 1.13 1,895.33 1,677.28 1,895.33 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03 DEMOLICIÓN DE ESTRUCTURA DE CONCRETO C/MAQUINARIA PESADAm3 27.61 62.66 1,730.04 27.61 1,730.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04 REMOCION DE ADOQUINES DE CONCRETO m2 503.18 0.83 417.64 503.18 417.64 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03 EXPLANADA PRINCIPAL 52,171.16
03.01 TRABAJOS PRELIMINARES 534.15
03.01.01 TRAZO, NIVELACION Y REPALNTEO CON EQUIPO (ESTACION) m2 472.70 1.13 534.15 472.70 534.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02 MOVIMIENTO DE TIERRAS 2,519.91 0.00
03.02.01 NIVELACIÓN Y COMPACTACIÓN DE SUBRASANTE CON EQUIPO LIVIA m2 472.70 0.91 430.16 472.70 430.16 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.02 EXCAVACIÓN DE ZANJAS PARA SARDINEL m3 5.41 20.00 108.20 5.41 108.20 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.03 ACARREO INTERNO MATERIAL PROCEDENTE DE EXCAVACIONES m3 6.49 12.50 81.13 6.49 81.13 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.04 EXTENDIDO, RIEGO Y COMPACTACION DE MATERIAL GRANULAR PARm3 113.45 15.73 1,784.57 113.45 1,784.57 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.05 CARGUIO, TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 6.49 17.85 115.85 6.49 115.85 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.03 CONCRETO SIMPLE 49,117.10
03.03.01 SARDINELES 3,955.12
03.03.01.0 SARDINELES - CONCRETO F'C = 175 KG/CM2 C/MEZCLADORA m3 5.68 450.09 2,556.51 0.00 0.00 0.00% 5.68 2,556.51 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
03.03.01.0 SARDINELES - ENCOFRADO Y DESENCOFRADO m2 75.97 18.41 1,398.61 0.00 0.00 0.00% 75.97 1,398.61 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
03.03.02 PISOS Y ACABADOS 45,161.98
03.03.02.0 FALSO PISO - MEZCLA C:H 1:8 E=4" PREPARACION C/MEZCLADOm2 496.34 42.26 20,975.33 0.00 0.00 0.00% 496.34 20,975.33 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
03.03.02.0 COLOCACIÓN DE CAMA DE ARENA E=0.10M PARA ASENTADO DE m2 496.34 20.45 10,150.15 0.00 0.00 0.00% 0.00 0.00 0.00% 496.34 10,150.15 100.00% 0.00 0.00 0.00%
2
03.03.02.0 ASENTADO DE ADOQUINES DE CONCRETO E=6.00CM m2 496.34 28.28 14,036.50 0.00 0.00 0.00% 0.00 0.00 0.00% 496.34 14,036.50 100.00% 0.00 0.00 0.00%
3
04 ACCESO PRINCIPAL 18,958.31
04.01 TRABAJOS PRELIMINARES 150.70
04.01.01 TRAZO, NIVELACION Y REPALNTEO CON EQUIPO (ESTACION) m2 133.36 1.13 150.70 133.36 150.70 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.02 MOVIMIENTO DE TIERRAS 5,892.38
04.02.01 NIVELACIÓN Y COMPACTACIÓN DE SUBRASANTE CON EQUIPO LIVIA m2 133.36 0.91 121.36 133.36 121.36 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.02.02 RELLENO CON MATERIAL GRANULAR PARA SUB BASE m3 104.02 31.28 3,253.75 104.02 3,253.75 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.02.03 EXTENDIDO, RIEGO Y COMPACTACION DE MATERIAL GRANULAR PARm3 160.03 15.73 2,517.27 160.03 2,517.27 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.03 CONCRETO SIMPLE 12,915.23
04.03.01 PISOS Y ACABADOS 12,741.33
04.03.01.0 FALSO PISO - MEZCLA C:H 1:8 E=4" PREPARACION C/MEZCLADOm2 140.03 42.26 5,917.67 0.00 0.00 0.00% 140.03 5,917.67 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
04.03.01.0 COLOCACIÓN DE CAMA DE ARENA E=0.10M PARA ASENTADO DE m2 140.03 20.45 2,863.61 0.00 0.00 0.00% 0.00 0.00 0.00% 140.03 2,863.61 100.00% 0.00 0.00 0.00%
2
04.03.01.0 ASENTADO DE ADOQUINES DE CONCRETO E=6.00CM m2 140.03 28.28 3,960.05 0.00 0.00 0.00% 0.00 0.00 0.00% 140.03 3,960.05 100.00% 0.00 0.00 0.00%
3
04.03.02 GRADAS 173.90
04.03.02.0 GRADAS - CONCRETO F´C = 175KG/CM2 (ACABADO PULIDO) m3 0.24 467.62 112.23 0.00 0.00 0.00% 0.24 112.23 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
04.03.02.0 GRADAS - ENCOFRADO Y DESENCOFRADO m2 1.87 32.98 61.67 0.00 0.00 0.00% 1.87 61.67 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
05 ACCESOS SECUNDARIOS 33,549.10
05.01 TRABAJOS PRELIMINARES 312.74
05.01.01 TRAZO, NIVELACION Y REPALNTEO CON EQUIPO (ESTACION) m2 276.76 1.13 312.74 276.76 312.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.02 MOVIMIENTO DE TIERRAS 1,576.69
05.02.01 NIVELACIÓN Y COMPACTACIÓN DE SUBRASANTE CON EQUIPO LIVIA m2 276.76 0.91 251.85 276.76 251.85 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.02.02 EXCAVACIÓN DE ZANJAS PARA SARDINEL m3 8.05 20.00 161.00 8.05 161.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.02.03 ACARREO INTERNO MATERIAL PROCEDENTE DE EXCAVACIONES m3 9.66 12.50 120.75 9.66 120.75 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.02.04 EXTENDIDO, RIEGO Y COMPACTACION DE MATERIAL GRANULAR PARm3 55.35 15.73 870.66 55.35 870.66 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.02.05 CARGUIO, TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 9.66 17.85 172.43 9.66 172.43 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.03 CONCRETO SIMPLE 31,659.67
CRONOGRAMA VALORIZADO DE OBRA
BRA: "MEJORAMIENTO Y ACONDICIONAMIENTO DE LOS SERVICIOS RECREATIVOS Y PASIVOS EN LA PLAZA CONSTITUCION DEL DISTRITO DE YAUYOS, PROVINCIA DE YAUYOS - LIMA

MES 1 MES 2 MES 3 MES 4

N° Partidas Unid. Metrado C.U. Precios Parcial


Valorizacion Valorizacion Valorizacion Valorizacion
Metrado % de Avance Metrado % de Avance Metrado % de Avance Metrado % de Avance
Mensual S/. Mensual S/. Mensual S/. Mensual S/.

05.03.01 SARDINELES 5,217.97


05.03.01.0 SARDINELES - CONCRETO F'C = 175 KG/CM2 C/MEZCLADORA m3 8.46 450.09 3,807.76 0.00 0.00 0.00% 8.46 3,807.76 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
05.03.01.0 SARDINELES - ENCOFRADO Y DESENCOFRADO m2 76.60 18.41 1,410.21 0.00 0.00 0.00% 76.60 1,410.21 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
05.03.02 PISOS Y ACABADOS 26,441.70
05.03.02.0 FALSO PISO - MEZCLA C:H 1:8 E=4" PREPARACION C/MEZCLADOm2 290.60 42.26 12,280.76 0.00 0.00 0.00% 290.60 12,280.76 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
05.03.02.0 COLOCACIÓN DE CAMA DE ARENA E=0.10M PARA ASENTADO DE m2 290.60 20.45 5,942.77 0.00 0.00 0.00% 0.00 0.00 0.00% 290.60 5,942.77 100.00% 0.00 0.00 0.00%
2
05.03.02.0 ASENTADO DE ADOQUINES DE CONCRETO E=6.00CM m2 290.60 28.28 8,218.17 0.00 0.00 0.00% 0.00 0.00 0.00% 290.60 8,218.17 100.00% 0.00 0.00 0.00%
3
06 EXPLANADA SECUNDARIA 11,857.30
06.01 TRABAJOS PRELIMINARES 36.25
06.01.01 TRAZO, NIVELACION Y REPALNTEO CON EQUIPO (ESTACION) m2 32.08 1.13 36.25 32.08 36.25 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02 MOVIMIENTO DE TIERRAS 1,476.39
06.02.01 NIVELACIÓN Y COMPACTACIÓN DE SUBRASANTE CON EQUIPO LIVIA m2 32.08 0.91 29.19 32.08 29.19 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02.02 RELLENO CON MATERIAL GRANULAR PARA SUB BASE m3 25.02 31.28 782.63 25.02 782.63 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02.03 EXCAVACIÓN DE ZANJAS PARA SARDINEL m3 2.50 20.00 50.00 2.50 50.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02.04 EXCAVACIÓN MANUAL PARA CIMENTACION DE MASTIL m3 0.70 27.00 18.90 0.70 18.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02.05 ACARREO INTERNO MATERIAL PROCEDENTE DE EXCAVACIONES m3 3.00 12.50 37.50 3.00 37.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02.06 EXTENDIDO, RIEGO Y COMPACTACION DE MATERIAL GRANULAR PARm3 32.08 15.73 504.62 32.08 504.62 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02.07 CARGUIO, TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 3.00 17.85 53.55 3.00 53.55 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.03 CONCRETO SIMPLE 7,739.18
06.03.01 SARDINELES 1,617.03
06.03.01.0 SARDINELES - CONCRETO F'C = 175 KG/CM2 C/MEZCLADORA m3 2.62 450.09 1,179.24 0.00 0.00 0.00% 2.62 1,179.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
06.03.01.0 SARDINELES - ENCOFRADO Y DESENCOFRADO m2 23.78 18.41 437.79 0.00 0.00 0.00% 23.78 437.79 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
06.03.02 PISOS Y ACABADOS 6,032.96
06.03.02.0 FALSO PISO - MEZCLA C:H 1:8 E=4" PREPARACION C/MEZCLADOm2 32.08 42.26 1,355.70 0.00 0.00 0.00% 32.08 1,355.70 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
06.03.02.0 ASENTADO DE PISO DE BALDOSA TRAVERTINO E=10.00CM m2 32.08 145.80 4,677.26 0.00 0.00 0.00% 0.00 0.00 0.00% 32.08 4,677.26 100.00% 0.00 0.00 0.00%
2
06.03.03 GRADAS 89.19
06.03.03.0 GRADAS - CONCRETO F´C = 175KG/CM2 (ACABADO PULIDO) m3 0.08 467.62 37.41 0.00 0.00 0.00% 0.08 37.41 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
06.03.03.0 GRADAS - ENCOFRADO Y DESENCOFRADO m2 1.57 32.98 51.78 0.00 0.00 0.00% 1.57 51.78 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
06.04 CONCRETO ARMADO 910.48
06.04.01 MASTIL 910.48
06.04.01.0 MASTIL - CONCRETO F´C = 140KG/CM2 (ACABADO PULIDO) m3 1.00 498.87 498.87 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 498.87 100.00%
1
06.04.01.0 MASTIL - ENCOFRADO Y DESENCOFRADO m2 4.04 32.98 133.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.04 133.24 100.00%
2
06.04.01.0 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 41.86 6.65 278.37 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 41.86 278.37 100.00%
3
06.05 CARPINTERIA METALICA_x000D_ 1,695.00
06.05.01 SUMINISTRO E INSTALACION DE ASTA DE BANDERA C/TUBO NEGROund 3.00 565.00 1,695.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 1,695.00 100.00%
07 LOSA DEPORTIVA 215,298.53
07.01 TRABAJOS PRELIMINARES 631.44
07.01.01 TRAZO, NIVELACION Y REPALNTEO CON EQUIPO (ESTACION) m2 558.80 1.13 631.44 558.80 631.44 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.02 MOVIMIENTO DE TIERRAS 18,081.48
07.02.01 CORTE EN TERRENO NORMAL m3 223.40 8.87 1,981.56 223.40 1,981.56 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.02.02 EXCAVACIÓN DE ZANJAS PARA ZAPATAS Hmax 1.00m EN TERRENO m3 12.00 23.20 278.40 6.00 139.20 50.00% 6.00 139.20 50.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.02.03 EXCAVACIÓN DE ZANJAS PARA DRENAJE m3 16.58 27.00 447.66 16.58 447.66 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.02.04 NIVELACIÓN Y COMPACTACIÓN DE SUBRASANTE CON EQUIPO LIVIA m2 518.00 0.91 471.38 518.00 471.38 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.02.05 RELLENO COMPACTADO C/MAT. PRESTAMO (AFIRMADO) INC. PLAN m3 103.60 46.84 4,852.62 103.60 4,852.62 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.02.06 RELLENO CON GRAVA SELECCIONADA m3 103.60 47.39 4,909.60 103.60 4,909.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.02.07 CARGUIO, TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 287.97 17.85 5,140.26 287.97 5,140.26 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.03 CONCRETO SIMPLE 5,879.02
07.03.01 CONCRETO F'C= 175 KG/CM2 (C:H) CAJA DE REGISTRO m3 1.58 561.72 887.52 0.00 0.00 0.00% 1.58 887.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.03.02 SARDINELES - CONCRETO F'C = 175 KG/CM2 C/MEZCLADORA m3 11.09 450.09 4,991.50 0.00 0.00 0.00% 11.09 4,991.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.04 CONCRETO ARMADO 10,633.50
07.04.01 ZAPATAS 2,770.20
07.04.01.0 ZAPATAS - CONCRETO F'C= 210 KG/CM2 CON MEZCLADORA m3 4.80 468.43 2,248.46 0.00 0.00 0.00% 4.80 2,248.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
CRONOGRAMA VALORIZADO DE OBRA
BRA: "MEJORAMIENTO Y ACONDICIONAMIENTO DE LOS SERVICIOS RECREATIVOS Y PASIVOS EN LA PLAZA CONSTITUCION DEL DISTRITO DE YAUYOS, PROVINCIA DE YAUYOS - LIMA

MES 1 MES 2 MES 3 MES 4

N° Partidas Unid. Metrado C.U. Precios Parcial


Valorizacion Valorizacion Valorizacion Valorizacion
Metrado % de Avance Metrado % de Avance Metrado % de Avance Metrado % de Avance
Mensual S/. Mensual S/. Mensual S/. Mensual S/.

07.04.01.0 ZAPATAS - ACERO DE REFUERZO FY = 4200 KG/CM2 kg 75.07 6.95 521.74 0.00 0.00 0.00% 75.07 521.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
07.04.02 COLUMNAS 7,863.30
07.04.02.0 COLUMNAS - CONCRETO F'C= 210 KG/CM2 CON MEZCLADORA I m3 3.43 533.61 1,830.28 0.00 0.00 0.00% 3.43 1,830.28 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
07.04.02.0 COLUMNAS - ENCOFRADO Y DESENCOFRADO m2 46.11 53.19 2,452.59 0.00 0.00 0.00% 46.11 2,452.59 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
07.04.02.0 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 538.41 6.65 3,580.43 0.00 0.00 0.00% 538.41 3,580.43 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
3
07.05 ACONDICIONAMIENTO Y EQUIPAMIENTO DE LOSA 4,424.24
07.05.01 DEMARCACION DE LOSA DEPORTIVA PINTURA DE TRAFICO m 155.22 2.95 457.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 155.22 457.90 100.00%
07.05.02 ARCO DE FULBITO CON TABLERO DE BASQUET und 2.00 1,580.45 3,160.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 3,160.90 100.00%
07.05.03 POSTES DE FIERRO Y NET PARA VOLEY und 2.00 402.72 805.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 805.44 100.00%
07.06 COBERTURA METALICA 175,648.85
07.06.01 HABILITACION Y MONTAJE DE COLUMNAS METALICAS 19,538.61
07.06.01.0 TUBO CIRCULAR DE 6", E=3MM m 211.40 91.06 19,250.08 0.00 0.00 0.00% 0.00 0.00 0.00% 211.40 19,250.08 100.00% 0.00 0.00 0.00%
1
07.06.01.0 ANCLAJE CON PLANCHA METALICA 3/4" (ANCLAJE AL PISO)_x000D_
m 3.40 31.56 107.30 0.00 0.00 0.00% 0.00 0.00 0.00% 3.40 107.30 100.00% 0.00 0.00 0.00%
2
07.06.01.0 ANCLAJE CON PLANCHA METALICA 3/8" (ANCLAJE A COLUMNA METm 7.02 21.50 150.93 0.00 0.00 0.00% 0.00 0.00 0.00% 7.02 150.93 100.00% 0.00 0.00 0.00%
3
07.06.01.0 ANCLAJE CON PLANCHA METALICA 3/8" (ANCLAJE A COLUMNA C m 0.96 31.56 30.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.96 30.30 100.00% 0.00 0.00 0.00%
4
07.06.02 HABILITACION Y MONTAJE DE VIGAS METALICAS METALICAS PRINCIPALES 13,761.22
07.06.02.0 ANGULOS DE 2"x2", E=3/16" m 602.40 12.22 7,361.33 0.00 0.00 0.00% 0.00 0.00 0.00% 602.40 7,361.33 100.00% 0.00 0.00 0.00%
1
07.06.02.0 ANGULOS DE 1"x1", E=3/16" m 927.52 6.90 6,399.89 0.00 0.00 0.00% 0.00 0.00 0.00% 927.52 6,399.89 100.00% 0.00 0.00 0.00%
2
07.06.03 HABILITACION Y MONTAJE DE VIGUETAS MATALICAS PRINCIPAES 88,396.86
07.06.03.0 ANGULOS DE 1"x1", E=3/16" m 973.35 6.90 6,716.12 0.00 0.00 0.00% 0.00 0.00 0.00% 973.35 6,716.12 100.00% 0.00 0.00 0.00%
1
07.06.03.0 BARRA LISA DE 3/8" m 1,347.20 60.63 81,680.74 0.00 0.00 0.00% 0.00 0.00 0.00% 1,347.20 81,680.74 100.00% 0.00 0.00 0.00%
2
07.06.04 HABILITACION Y MONTAJE DE CUBIERTA 27,710.28
07.06.04.0 COBERTURA DE ALUZINC TP5 PREPINTADO COLOR ROJO INC/ACC glb 1.00 27,206.92 27,206.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 27,206.92 100.00%
1
07.06.04.0 CANALETA DE ZINC DE 6" INC/ACCESORIOS m 34.50 14.59 503.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 34.50 503.36 100.00%
2
07.06.05 INSTALACION DE GRASS SINTETICO 26,241.88
07.06.05.0 SUMINISTRO E INSTALACION DE GRASS SINTETICO m2 518.00 50.66 26,241.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 518.00 26,241.88 100.00%
1
08 PERGOLA 117,213.79
08.01 TRABAJOS PRELIMINARES 102.05
08.01.01 TRAZO Y REPLANTEO EN TERRENO NORMAL m2 78.50 1.30 102.05 78.50 102.05 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.02 MOVIMIENTO DE TIERRAS 4,279.76
08.02.01 CORTE EN TERRENO NORMAL m3 132.41 8.87 1,174.48 132.41 1,174.48 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.02.02 EXCAVACIÓN DE ZANJAS PARA CIMIENTO HASTA 1.70M EN TERRE m3 38.75 43.20 1,674.00 38.75 1,674.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.02.03 EXCAVACIÓN DE ZANJAS PARA ZAPATA AISLADA DE 1.40 HASTA 1 m3 29.73 43.20 1,284.34 29.73 1,284.34 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m 8.90 16.51 146.94 8.90 146.94 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.03 CONCRETO SIMPLE 16,589.42
08.03.01 SOLADO E=2" MEZCLA 1:10 C:H m2 78.50 38.05 2,986.93 78.50 2,986.93 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.03.02 CIMIENTO CORRIDO - MEZCLA C:H 1:10+30% PG INC. PREPARAC m3 32.17 315.62 10,153.50 32.17 10,153.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.03.03 SOBRECIMIENTO DE 0.25m DE ANCHO MEZCLA C:H 1:8+25% PM ( m3 8.04 362.49 2,914.42 8.04 2,914.42 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.03.04 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO m2 10.97 48.73 534.57 10.97 534.57 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.04 CONCRETO ARMADO 66,409.45
08.04.01 ZAPATAS 8,465.53
08.04.01.0 ZAPATAS - CONCRETO F'C= 210 KG/CM2 CON MEZCLADORA m3 11.98 468.43 5,611.79 11.98 5,611.79 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
08.04.01.0 ZAPATAS - ENCOFRADO Y DESENCOFRADO m2 34.32 40.89 1,403.34 34.32 1,403.34 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
08.04.01.0 ZAPATAS - ACERO DE REFUERZO FY = 4200 KG/CM2 kg 208.69 6.95 1,450.40 208.69 1,450.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
3
08.04.02 COLUMNAS 10,208.39
08.04.02.0 COLUMNAS - CONCRETO F'C= 210 KG/CM2 CON MEZCLADORA I m3 2.77 533.61 1,478.10 2.77 1,478.10 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
08.04.02.0 COLUMNAS - ENCOFRADO Y DESENCOFRADO m2 74.69 53.19 3,972.76 74.69 3,972.76 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
08.04.02.0 COMUNAS - ACERO DE REFUERZO FY = 4200 KG/CM2 kg 694.53 6.85 4,757.53 694.53 4,757.53 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
3
08.04.03 MURO DE CONTENCION 47,735.53
08.04.03.0 MURO DE CONTENCIÓN - CONCRETO F'C=210 KG/CM2 m3 82.97 424.71 35,238.19 82.97 35,238.19 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
1
08.04.03.0 MURO DE CONTENCIÓN - ENCOFRADO Y DESENCOFRADO m2 165.94 56.89 9,440.33 165.94 9,440.33 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
08.04.03.0 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 459.70 6.65 3,057.01 459.70 3,057.01 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
3
CRONOGRAMA VALORIZADO DE OBRA
BRA: "MEJORAMIENTO Y ACONDICIONAMIENTO DE LOS SERVICIOS RECREATIVOS Y PASIVOS EN LA PLAZA CONSTITUCION DEL DISTRITO DE YAUYOS, PROVINCIA DE YAUYOS - LIMA

MES 1 MES 2 MES 3 MES 4

N° Partidas Unid. Metrado C.U. Precios Parcial


Valorizacion Valorizacion Valorizacion Valorizacion
Metrado % de Avance Metrado % de Avance Metrado % de Avance Metrado % de Avance
Mensual S/. Mensual S/. Mensual S/. Mensual S/.

08.05 PERGOLA 18,540.00


08.05.01 SUMINISTRO E INSTALACION DE PERGOLA SEGUN DISEÑO glb 1.00 18,540.00 18,540.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 18,540.00 100.00%
08.06 ACABADOS 11,293.11
08.06.01 PERGOLA 9,606.86
08.06.01.0 PISO DE BALDOZA TRAVERTINO m2 64.58 137.27 8,864.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 64.58 8,864.90 100.00%
1
08.06.01.0 TARRAJEO DE COLUMNAS MEZCLA C:A 1:5 E=1.5CM m2 30.00 21.63 648.90 0.00 0.00 0.00% 30.00 648.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
2
08.06.01.0 TARRAJEO EN MUROS MORTERO C:A 1:5 E=1.5CM m2 5.24 17.76 93.06 0.00 0.00 0.00% 5.24 93.06 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
3
08.06.02 GRADAS 1,686.25
08.06.02.0 CERAMICA ANTIDESLIZANTE DE 30 X 30 CON PEGAMENTO - SSHHm2 7.13 54.28 387.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.13 387.02 100.00%
1
08.06.02.0 PISO DE BALDOZA TRAVERTINO m2 7.13 137.27 978.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.13 978.74 100.00%
2
08.06.02.0 TARRAJEO RAYADO O PRIMARIO MORTERO C:A 1:5 E=1.50 CM m2 13.88 23.09 320.49 0.00 0.00 0.00% 13.88 320.49 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
3
09 JARDINERIA 6,249.60
09.01 TRABAJOS PRELIMINARES 1,263.42
09.01.01 TRAZO Y REPLANTEO EN TERRENO NORMAL m2 971.86 1.30 1,263.42 0.00 0.00 0.00% 971.86 1,263.42 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09.02 SARDINELES 4,986.18
09.02.01 SARDINELES - CONCRETO F'C= 140 KG/CM2 C/MEZCLADORA m3 6.38 418.38 2,669.26 0.00 0.00 0.00% 6.38 2,669.26 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09.02.02 SARDINELES - ENCOFRADO Y DESENCOFRADO (H=0.50M), USO VIAm2 32.06 18.41 590.22 0.00 0.00 0.00% 32.06 590.22 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09.02.03 TIERRA DE CHACRA PARA RELLENO EN AREAS VERDES (MATERIAL m3 28.55 60.48 1,726.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 28.55 1,726.70 100.00%
10 SS - HH 24,137.09
10.01 TRABAJOS PRELIMINARES 40.78
10.01.01 TRAZO Y REPLANTEO EN TERRENO NORMAL m2 31.37 1.30 40.78 0.00 0.00 0.00% 31.37 40.78 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
10.02 MUROS Y TABIQUES DE ALBAÑILERIA 4,465.37
10.02.01 MURO DE LADRILLO KK 18H (9X13X24) SOGA MEZCLA C:A 1:5, E= m2 39.60 64.53 2,555.39 0.00 0.00 0.00% 39.60 2,555.39 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
10.02.02 SUMINISTRO E INSTALACIÓN DE TABIQUERIA DE SISTEMA DRYWALL m2 13.50 141.48 1,909.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.50 1,909.98 100.00%
10.03 PISOS Y PAVIMENTOS 3,929.09
10.03.01 FALSO PISO - MEZCLA C:H 1:8 E=4" PREPARACION MANUAL m2 31.37 46.28 1,451.80 0.00 0.00 0.00% 31.37 1,451.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
10.03.02 PISO DE CERAMICA DE 30 X 30 CON PEGAMENTO m2 64.58 38.36 2,477.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 64.58 2,477.29 100.00%
10.04 REVOQUES, ENLUCIDOS Y MOLDURAS 15,701.85
10.04.01 PAREDES DE CERAMICA DE 30 X 30 CON PEGAMENTO m2 284.60 38.36 10,917.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 284.60 10,917.26 100.00%
10.04.02 TARRAJEO DE COLUMNAS MEZCLA C:A 1:5 E=1.5CM m2 10.40 21.63 224.95 0.00 0.00 0.00% 10.40 224.95 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
10.04.03 TARRAJEO EN MUROS MORTERO C:A 1:5 E=1.5CM m2 103.25 17.76 1,833.72 0.00 0.00 0.00% 103.25 1,833.72 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
10.04.04 TARRAJEO DE CIELORRASO MEZCLA C:A 1:5 E=1.5CM CON CINTAS m2 64.58 42.21 2,725.92 0.00 0.00 0.00% 64.58 2,725.92 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11 INSTALACIONES ELECTRICAS 27,309.96
11.01 CONEXION A LA RED DE MEDIDORES 4.00
11.01.01 ACOMETIDA INSTALACIONES ELECTRICAS und 1.00 4.00 4.00 0.00 0.00 0.00% 1.00 4.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.02 SALIDAS 809.39
11.02.01 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE pto 1.00 27.43 27.43 0.00 0.00 0.00% 1.00 27.43 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.02.02 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE A PRUEBA DE INTE pto 2.00 27.43 54.86 0.00 0.00 0.00% 2.00 54.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.02.03 SALIDA PARA INTERRUPTOR SIMPLE pto 5.00 23.43 117.15 0.00 0.00 0.00% 5.00 117.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.02.04 SALIDA PARA INTERRUPTOR DOBLE pto 2.00 23.43 46.86 0.00 0.00 0.00% 2.00 46.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.02.05 SALIDA PARA CENTRO DE LUZ pto 11.00 51.19 563.09 0.00 0.00 0.00% 11.00 563.09 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03 TABLEROS, TUBERIAS Y CONDUCTORES 10,080.14
11.03.01 TABLERO GENERAL CAJA METALICA CON 18 POLOS pza 1.00 209.90 209.90 0.00 0.00 0.00% 1.00 209.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.02 TABLEROS DISTRIBUCION CAJA METALICA CON 8 POLOS und 2.00 69.90 139.80 0.00 0.00 0.00% 2.00 139.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.03 CAJA DE PASE DE F°G° CUADRADA 200X200 MM X 100 MM CON TAPund 16.00 23.90 382.40 0.00 0.00 0.00% 16.00 382.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.04 CAJA FSLA 3/4", SUMINISTRO DE TIRA LED (REFLECTORES) und 2.00 40.40 80.80 0.00 0.00 0.00% 2.00 80.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.05 CAJA FS 3/4" CONTANDO TIRA LED (REFLECTORES) und 1.00 36.10 36.10 0.00 0.00 0.00% 1.00 36.10 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.06 TUBERIA PVC SAP (ELECTRICAS) D=3/4" ALUMBRADO m 183.69 5.17 949.68 0.00 0.00 0.00% 183.69 949.68 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.07 TUBERIA PVC SAP (ELECTRICAS) D=3/4" SSHH m 60.87 5.17 314.70 0.00 0.00 0.00% 60.87 314.70 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.08 TUBERIA PVC SAP (ELECTRICAS) D=3/4" PERGOLA m 38.61 5.17 199.61 0.00 0.00 0.00% 38.61 199.61 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.09 TUBERIA PVC SAP (ELECTRICAS) D=3/4" CIRCUITO ALIMENTADOR m 30.76 5.17 159.03 0.00 0.00 0.00% 30.76 159.03 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.10 TUBERIA PVC SAP (ELECTRICAS) D=3/4" CIRCUITO EN CONDUCTO m 12.51 5.17 64.68 0.00 0.00 0.00% 12.51 64.68 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
CRONOGRAMA VALORIZADO DE OBRA
BRA: "MEJORAMIENTO Y ACONDICIONAMIENTO DE LOS SERVICIOS RECREATIVOS Y PASIVOS EN LA PLAZA CONSTITUCION DEL DISTRITO DE YAUYOS, PROVINCIA DE YAUYOS - LIMA

MES 1 MES 2 MES 3 MES 4

N° Partidas Unid. Metrado C.U. Precios Parcial


Valorizacion Valorizacion Valorizacion Valorizacion
Metrado % de Avance Metrado % de Avance Metrado % de Avance Metrado % de Avance
Mensual S/. Mensual S/. Mensual S/. Mensual S/.

11.03.11 TUBO CODUIT D=3/4" (REFLECTORES) m 73.47 9.93 729.56 0.00 0.00 0.00% 73.47 729.56 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.12 CODOS PVC 3/4" und 16.00 6.97 111.52 0.00 0.00 0.00% 16.00 111.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.13 CONDUCTOR DE COBRE N° 12 AWG ALUMBRADO PUBLICO m 183.69 5.87 1,078.26 0.00 0.00 0.00% 183.69 1,078.26 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.03.14 CABLE "CU" NYY-BAJA TENSION 2X1X6MM2 m 518.35 10.85 5,624.10 0.00 0.00 0.00% 518.35 5,624.10 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.04 INSTALACION DEL SISTEMA DE PUESTA A TIERRA 812.48 0.00%
11.04.01 POZO CONEXION A TIERRA und 1.00 812.48 812.48 0.00 0.00 0.00% 1.00 812.48 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.05 ARTEFACTOS DE ILUMINACION 13,775.95 0.00%
11.05.01 SUMINISTRO Y COLOCACIÓN DE FAROLA ORNAMENTAL EN PARQUE und 16.00 732.36 11,717.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.00 11,717.76 100.00%
11.05.02 TOMACORRIENTE DOBLE POLARIZADO CON TIERRA 15A-220V, (PL und 1.00 103.21 103.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 103.21 100.00%
11.05.03 TOMACORRIENTE DOBLE POLARIZADO CON TIERRA 15A-220V, (PL und 2.00 103.21 206.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 206.42 100.00%
11.05.04 INTERRUPTOR UNIPOLAR SIMPLE 10A, 220V, 60HZ (PLACA TERMOP und 5.00 90.75 453.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 453.75 100.00%
11.05.05 INTERRUPTOR UNIPOLAR DOBLE 10A, 220V, 60HZ (PLACA TERMOPLund 2.00 110.77 221.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 221.54 100.00%
11.05.06 ARTEFACTO SPOT LIGHT EQUIPO Y PROTECCION und 11.00 97.57 1,073.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 1,073.27 100.00%
11.05.07 REFLECTORES LED 100W PARA CAMPO DEPORTIVO und 8.00 228.50 1,828.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 1,828.00 100.00%
12 INSTALACIONES SANITARIAS 18,553.34
12.01 TRABAJOS PRELIMINARES 10,947.83
12.01.01 TRAZO Y REPLANTEO EN TERRENO NORMAL m2 110.81 1.30 144.05 0.00 0.00 0.00% 110.81 144.05 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.01.02 CORTE EN TERRENO NORMAL m3 55.41 8.87 491.49 0.00 0.00 0.00% 55.41 491.49 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.01.03 RELLENO COMPACTADO C/MAT. PRESTAMO (AFIRMADO) INC. PLAN m3 220.16 46.84 10,312.29 0.00 0.00 0.00% 220.16 10,312.29 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.02 APARATOS SANITARIOS 1,943.40
12.02.01 LAVATORIO DE PARED BLANCO DE 16" X 24" und 6.00 114.90 689.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 689.40 100.00%
12.02.02 INODORO TANQUE BAJO BLANCO und 6.00 209.00 1,254.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 1,254.00 100.00%
12.03 REDES DE ALIMENTACION 1,384.48
12.03.01 SUMINISTRO E INSTALACIÓN DE TUBERÍA DE PVC Ø 1/2" PARA AGUm 57.40 7.96 456.90 0.00 0.00 0.00% 57.40 456.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.03.02 SUMINISTRO E INSTALACIÓN DE TUBERÍA DE PVC Ø 1/2" PARA AGUm 116.53 7.96 927.58 0.00 0.00 0.00% 116.53 927.58 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.04 ACCESORIOS DE REDES DE AGUA 418.21
12.04.01 TEE PVC PARA RED DE AGUA POTABLE DE 20 mm (1/2") und 20.00 3.50 70.00 0.00 0.00 0.00% 20.00 70.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.04.02 YEE DE P.V.C. SAP 1/2" und 1.00 13.80 13.80 0.00 0.00 0.00% 1.00 13.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.04.03 CODOS PVC AGUA C-10 1/2" und 26.00 5.95 154.70 0.00 0.00 0.00% 26.00 154.70 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.04.04 VÁLVULA CHECK DE BRONCE DE 1/2" und 1.00 179.71 179.71 0.00 0.00 0.00% 1.00 179.71 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.05 SISTEMA DE DRENAJE PLUVIAL 1,408.75
12.05.01 TUBERIA DE PVC SAL 3" (EVACUACION PLUVIAL) m 126.80 11.11 1,408.75 0.00 0.00 0.00% 126.80 1,408.75 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.06 SALIDAS DE DESAGUE 1,297.56
12.06.01 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION F.G 2" P m 6.43 75.09 482.83 0.00 0.00 0.00% 6.43 482.83 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.06.02 TUBERIA DE PVC SAL 2" m 18.50 7.65 141.53 0.00 0.00 0.00% 18.50 141.53 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.06.03 TUBERIA DE PVC SAL 4" m 55.00 12.24 673.20 0.00 0.00 0.00% 55.00 673.20 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.07 ACCESORIOS DE REDES DE DESAGUE 1,153.11
12.07.01 REDUCCION PVC PARA RED DE DESAGUE DE 4" A 2" und 2.00 5.70 11.40 0.00 0.00 0.00% 2.00 11.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.07.02 YEE DE P.V.C. SAL SP, SIMPLE DE 2" und 7.00 14.65 102.55 0.00 0.00 0.00% 7.00 102.55 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.07.03 CODO PVC SAL 2"X90° und 12.00 27.62 331.44 0.00 0.00 0.00% 12.00 331.44 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.07.04 VÁLVULA CHECK DE BRONCE DE 2" und 1.00 289.64 289.64 0.00 0.00 0.00% 1.00 289.64 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.07.05 REGISTRO ROSCADO DE Ø 4" und 6.00 41.60 249.60 0.00 0.00 0.00% 6.00 249.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.07.06 TEE DE PVC SAL PARA DESAGUE DE 4" und 4.00 23.13 92.52 0.00 0.00 0.00% 4.00 92.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
12.07.07 CODO PVC SAL 4"X45° und 4.00 18.99 75.96 0.00 0.00 0.00% 4.00 75.96 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
13 KIT_x000D_ 14,971.00
13.01 KIT DE HERRAMIENTAS glb 1.00 7,801.00 7,801.00 0.50 3,900.50 50.00% 0.50 3,900.50 50.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
13.02 KIT DE IMPLEMENTOS DE SEGURIDAD glb 1.00 7,170.00 7,170.00 0.50 3,585.00 50.00% 0.50 3,585.00 50.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
14 ENSAYOS 1,797.50
14.01 ENSAYO DENSIDAD DE CAMPO_x000D_ und 8.00 85.00 680.00 0.00 0.00 0.00% 8.00 680.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
14.02 PRUEBA DE DISEÑO DE MEZCLAS DE CONCRETO und 3.00 105.00 315.00 0.00 0.00 0.00% 3.00 315.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
14.03 ENSAYO PRÓCTOR (COMPACTACIÒN DEL SUELO) und 2.00 151.25 302.50 0.00 0.00 0.00% 2.00 302.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
14.04 PRUEBA A LA COMPRENSION DEL CONCRETO_x000D_ und 20.00 25.00 500.00 0.00 0.00 0.00% 20.00 500.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
CRONOGRAMA VALORIZADO DE OBRA
BRA: "MEJORAMIENTO Y ACONDICIONAMIENTO DE LOS SERVICIOS RECREATIVOS Y PASIVOS EN LA PLAZA CONSTITUCION DEL DISTRITO DE YAUYOS, PROVINCIA DE YAUYOS - LIMA

MES 1 MES 2 MES 3 MES 4

N° Partidas Unid. Metrado C.U. Precios Parcial


Valorizacion Valorizacion Valorizacion Valorizacion
Metrado % de Avance Metrado % de Avance Metrado % de Avance Metrado % de Avance
Mensual S/. Mensual S/. Mensual S/. Mensual S/.

15 PLACA RECORDATORIA 580.00


15.01 SUMINISTRO E INSTALACION DE PLACA RECORDATORIA DE METAL Y Vund 1.00 580.00 580.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 580.00 100.00%
16 INSTALACION DE AREAS VERDES 1,114.65
16.01 SIEMBRA DE ARBUSTOS und 3.00 52.50 157.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 157.50 100.00%
16.02 SIEMBRA DE CÉSPED m2 35.45 27.00 957.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.45 957.15 100.00%
17 VARIOS 838.64
17.01 LIMPIEZA FINAL DE OBRA m2 1,677.28 0.50 838.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,677.28 838.64 100.00%
18 FLETE 12,997.00
18.01 FLETE TERRETRE glb 1.00 12,997.00 12,997.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 12,996.98 100.00%
Total Costo directo 566,577.55 ### ### ### ###
Gastos Generales 60,454.00 ### ### ### ###
COSTO TOTAL DE OBRA 627,031.55 ### ### ### ###
% AVANCE MENSUAL 23.63% 21.29% 30.34% 24.75%
% AVANCE ACUMULADO 23.63% 44.92% 75.25% 100.00%