ONE MONTH LOOK AHEAD - MARCH 2019

ID Task Name Duration Start Finish Predecessors Successors May '19 Ju


28 5 12 19 26
1 RIVER OF LIFE 1C1D ‐ EOT PROGRAMME 2 1009 days 1/12/16 18/3/20
3 PRELIMINARIES & GENERAL ITEMS 1009 days 1/12/16 18/3/20
21 CONDITION OF CONTRACT 1002 days 9/12/16 18/3/20
31 As‐Built Drawings 312 days 1/3/19 18/3/20
39 COMBINED RECURRING PRELIM ITEM IN BQ 897 days 1/12/16 1/11/19
69 Preliminaries works / Recurring Activities 1 day 2/5/19 2/5/19
76 PACKAGE 1D 853 days 1/6/17 18/3/20
77 JALAN TAR 683 days 1/6/17 21/8/19 32FF
78 HARDSCAPE WORKS 683 days 1/6/17 21/8/19
133 Road Ramp crossing at Kamdar ‐ Lorong TAR 3 78 days 16/5/19 21/8/19
134 Road Milling work 6 days 16/5/19 24/5/19 136
135 Stretch 1 24 days 25/5/19 24/6/19
136 Slab construction 12 days 25/5/19 10/6/19 134 137
178 FURNITURE & FIXTURE 5 days 7/5/19 11/5/19
179 Bin (Type 02) 5 days 7/5/19 11/5/19 207FF‐24 days
180 Tactile 5 days 7/5/19 11/5/19 207FF‐24 days
181 Bollard 5 days 7/5/19 11/5/19 207FF‐24 days
182 Bench (Type 32 & Type 19) 5 days 7/5/19 11/5/19 207FF‐24 days
191 ROAD RAMP CROSSING 48 days 16/5/19 15/7/19
192 Pedestraian walk at Dang Wangi Intersection 18 days 16/5/19 10/6/19
193 Side A 6 days 16/5/19 24/5/19 113 194
194 Side B 6 days 25/5/19 31/5/19 193 195
300 JALAN MASJID INDIA 304 days 28/1/19 8/2/20 34FF
301 HARDSCAPE WORKS 278 days 28/1/19 6/1/20
307 Lorong TAR 5 ‐ Jalan Bunus (85m) 56 days 13/4/19 22/6/19
308 Demolition/relocation of existing structure 24 days 13/4/19 11/5/19 306 309SS+6 days,311FF
309 Laying Services Ducting & Piping works (M&E) 24 days 20/4/19 18/5/19 308SS+6 days 310SS+12 days,311FF
310 Kerb construction 24 days 6/5/19 4/6/19 309SS+12 days 311FF+14 days
311 Paving works 30 days 15/5/19 22/6/19 310FF+14 days,306FF,3316,335,313
332 ELECTRICAL WORKS 242 days 13/4/19 8/2/20
333 Street lighting footing 222 days 13/4/19 13/1/20
340 Cabling pulling works 214 days 27/4/19 17/1/20
341 Lorong Bunus 6 ‐ Lorong TAR 5 (80m) 6 days 27/4/19 4/5/19 334 342,348,366
347 Installation of electrical pole 214 days 6/5/19 24/1/20
348 Lorong Bunus 6 ‐ Lorong TAR 5 (80m) 6 days 6/5/19 11/5/19 341 349,355
354 Installation of light fitting 211 days 13/5/19 30/1/20
355 Lorong Bunus 6 ‐ Lorong TAR 5 (80m) 3 days 13/5/19 15/5/19 348 399
365 SOFTSCAPE 223 days 6/5/19 7/2/20
366 Lorong Bunus 6 ‐ Lorong TAR 5 (80m) 5 days 6/5/19 10/5/19 341 367
400 JALAN BUNUS 619 days 1/3/18 18/3/20 35FF
401 HARDSCAPE WORKS 597 days 1/3/18 21/2/20
409 Boardwalk 170 days 2/1/19 31/7/19
412 Installation of streel structure 30 days 16/5/19 24/6/19 411SS+24 days 413SS+18 days,414FF
415 Lorong Bunus 1 128 days 16/1/19 24/6/19
419 Slab construction 77 days 4/3/19 4/6/19 417SS+24 days 420FF+6 days
420 Paver works 30 days 16/5/19 24/6/19 419FF+6 days,418FF,41486,437
427 Jalan Bunus (Walkway) 102 days 29/4/19 4/9/19
428 Demolition/relocation of existing structure 9 days 29/4/19 9/5/19 416 429SS+24 days,432FF
429 Laying Services Ducting & Piping works (M&E) 30 days 29/4/19 7/6/19 428SS+24 days 430SS+24 days,432FF
430 Kerb construction 30 days 30/5/19 5/7/19 429SS+24 days 431SS+24 days,432FF
433 ELECTRICAL WORKS 336 days 29/1/19 18/3/20
434 Street lighting footing 313 days 29/1/19 20/2/20
440 Cabling pulling works 304 days 15/2/19 24/2/20
443 Lorong Bunus 1 6 days 29/4/19 6/5/19 437 449
446 Installation of electrical pole 303 days 22/2/19 29/2/20
449 Lorong Bunus 1 5 days 7/5/19 11/5/19 443 455
452 Installation of light fitting 301 days 28/2/19 4/3/20
455 Lorong Bunus 1 3 days 13/5/19 15/5/19 449 457,464,475
461 SOFTSCAPE 304 days 4/3/19 11/3/20
464 Lorong Bunus 1 6 days 16/5/19 24/5/19 455 487
472 SIGNAGES 304 days 4/3/19 11/3/20
475 Lorong Bunus 1 6 days 16/5/19 24/5/19 455 487
488 ANCILLARY BUILDINGS AT PACKAGE 1D 643 days 2/10/17 11/11/19
540 Malaysian Kite 144 days 15/5/19 11/11/19
541 Engineering 60 days 15/5/19 31/7/19
542 Material Submission 0 days 15/5/19 15/5/19 546SF‐90 days 15/5
550 Canopy at Jalan Masjid India 164 days 17/12/18 8/7/19
555 Construction 80 days 1/4/19 8/7/19
557 Fabrication & Installation of steel column 30 days 14/5/19 21/6/19 556FS+12 days 558,554SF‐30 days,553
562 PACKAGE 1C 651 days 1/9/17 18/10/19
563 DATARAN MERDEKA 559 days 1/9/17 27/6/19 36FF
591 SECTION C 311 days 18/6/18 27/6/19
592 Section C (Zone A) 287 days 18/6/18 28/5/19
593 Hardscape Works 275 days 18/6/18 11/5/19
597 Paving works 30 days 6/4/19 11/5/19 596 599FF,602,603
598 Electrical Works 18 days 6/5/19 28/5/19
599 Street lighting footing 6 days 6/5/19 11/5/19 597FF 600
600 Cable pulling works 6 days 13/5/19 18/5/19 599 601
601 Installation of light fitting 6 days 21/5/19 28/5/19 600 677
602 Softscape 10 days 13/5/19 25/5/19 597 677
603 Furniture and fixture 10 days 13/5/19 25/5/19 597 677
616 Section C (Zone C) 139 days 23/11/18 11/5/19
622 Electrical Works 18 days 20/4/19 11/5/19
624 Cable pulling works 6 days 27/4/19 4/5/19 623 625
625 Installation of light fitting 6 days 6/5/19 11/5/19 624 677

Page 1
ONE MONTH LOOK AHEAD - MARCH 2019
ID Task Name Duration Start Finish Predecessors Successors May '19 Ju
28 5 12 19 26
626 Softscape 12 days 27/4/19 11/5/19 621 677
627 Furniture and fixture 12 days 27/4/19 11/5/19 621 677
628 Section C (Zone D) 169 days 9/11/18 4/6/19
629 Hardscape Works 157 days 9/11/18 18/5/19
633 Paving works 24 days 20/4/19 18/5/19 632 677,635FF,638,639,674
634 Electrical Works 18 days 13/5/19 4/6/19
635 Street lighting footing 6 days 13/5/19 18/5/19 633FF 636
636 Cable pulling works 6 days 21/5/19 28/5/19 635 637
637 Installation of light fitting 6 days 29/5/19 4/6/19 636 677
638 Softscape 12 days 21/5/19 4/6/19 633 677
639 Furniture and fixture 12 days 21/5/19 4/6/19 633 677
640 Water feature ‐ City Library Plaza 168 days 1/12/18 27/6/19
645 RC dome construction 18 days 27/4/19 18/5/19 644 646
646 Plastering works 12 days 21/5/19 4/6/19 645 647
649 SECTION D 96 days 2/3/19 27/6/19
650 Hardscape Works (Zone A) 54 days 2/3/19 4/5/19
654 Paving works 24 days 6/4/19 4/5/19 653FF+12 days 659FF
655 Hardscape Works (Zone B) 48 days 30/3/19 28/5/19
657 Laying Services Ducting & Piping works (M&E) 18 days 13/4/19 4/5/19 656SS+12 days 658SS+6 days,661SS+12
658 Construction of Slab & Planter Wall 24 days 20/4/19 18/5/19 657SS+6 days 659FF+6 days,667
659 Paving works 24 days 27/4/19 28/5/19 658FF+6 days,654FF 664
660 Hardscape works (Zone C) 48 days 27/4/19 27/6/19
661 Demolition/relocation of existing structure 18 days 27/4/19 18/5/19 657SS+12 days 662SS+12 days
662 Laying Services Ducting & Piping works (M&E) 18 days 13/5/19 4/6/19 661SS+12 days 663SS+6 days
663 Construction of Slab & Planter Wall 18 days 21/5/19 13/6/19 662SS+6 days 664FF+6 days,668,671F
664 Paving works 24 days 29/5/19 27/6/19 663FF+6 days,659 677
665 Electrical Works 53 days 20/4/19 26/6/19
667 Street lighting footing ‐ Zone B 2 days 21/5/19 23/5/19 658,666 668
671 Softscape 24 days 21/5/19 20/6/19 663FF+6 days 677
672 Furniture and fixture 24 days 21/5/19 20/6/19 663FF+6 days 677
673 ROAD RAMP CROSSING 24 days 21/5/19 20/6/19
674 Section C 12 days 21/5/19 4/6/19 633 675
678 JALAN TUN PERAK 608 days 2/10/17 28/9/19 37FF
704 HARDSCAPE WORKS ‐ Left Side 392 days 1/2/18 11/5/19
735 Maybank ‐ 3 Junction Pudu 60 days 2/3/19 11/5/19
740 Paving works 18 days 20/4/19 11/5/19 736FF,737FF,738FF,739841
741 HARDSCAPE WORKS ‐ Right Side 497 days 2/10/17 11/5/19
772 Jalan Raja Chulan‐ 3 Junction Pudu 60 days 2/3/19 11/5/19
777 Paving works 18 days 20/4/19 11/5/19 773FF,774FF,775FF,776848
827 SOFTSCAPE 428 days 25/12/17 15/5/19
835 Left Side 323 days 26/4/18 15/5/19
841 Jalan Raja Chulan ‐ 3 Junction Pudu 3 days 13/5/19 15/5/19 740 878
842 Right Side 428 days 25/12/17 15/5/19
848 Jalan Raja Chulan ‐ 3 Junction Pudu 3 days 13/5/19 15/5/19 777 878
849 FURNITURE & FIXTURE 271 days 25/9/18 21/8/19
858 ROAD RAMP CROSSING 63 days 13/4/19 1/7/19
859 Jalan TAR Junction 12 days 16/5/19 31/5/19 861
879 JALAN TUN TAN CHIN LOCK 444 days 1/5/18 18/10/19 38FF
880 HARDSCAPE ‐ LEFT SIDE OF TTCL 397 days 1/5/18 21/8/19 983FS‐20 days
905 Jalan Kasturi ‐ Klang River 78 days 16/5/19 21/8/19
906 Demolition/relocation of existing structure 18 days 16/5/19 10/6/19 904 907SS+12 days,910FF
911 HARDSCAPE ‐ RIGHT SIDE OF TTCL 422 days 21/5/18 12/10/19 989FS‐20 days
942 ELECTRICAL WORKS ‐ LEFT SIDE OF TTCL 229 days 27/11/18 6/9/19
943 Cable Pulling 221 days 27/11/18 26/8/19
946 Jalan Petaling ‐ Jalan Tun HS Lee 4 days 16/5/19 21/5/19 898,945 952,947
947 Jalan Tun HS Lee ‐ Jalan Hang Kasturi 4 days 23/5/19 27/5/19 904,946 953,948
949 Installation of pole 149 days 2/3/19 30/8/19
952 Jalan Petaling ‐ Jalan Tun HS Lee 4 days 23/5/19 27/5/19 946,951 953,958
953 Jalan Tun HS Lee ‐ Jalan Hang Kasturi 4 days 28/5/19 31/5/19 947,952 954,959
955 Installation of light fitting 149 days 7/3/19 6/9/19
958 Jalan Petaling ‐ Jalan Tun HS Lee 4 days 28/5/19 31/5/19 952,957 959
962 ELECTRICAL WORKS ‐ RIGHT SIDE OF TTCL 276 days 13/11/18 18/10/19
963 Cable Pulling 268 days 13/11/18 9/10/19
966 Jalan Petaling ‐ Jalan Tun HS Lee 4 days 16/5/19 21/5/19 929 972
967 Jalan Tun HS Lee ‐ Jalan Hang Kasturi 4 days 16/5/19 21/5/19 935 973
969 Installation of pole 267 days 19/11/18 14/10/19
972 Jalan Petaling ‐ Jalan Tun HS Lee 4 days 23/5/19 27/5/19 966 978
973 Jalan Tun HS Lee ‐ Jalan Hang Kasturi 4 days 23/5/19 27/5/19 967 979
975 Installation of light fitting 267 days 23/11/18 18/10/19
978 Jalan Petaling ‐ Jalan Tun HS Lee 4 days 28/5/19 31/5/19 972 1019
979 Jalan Tun HS Lee ‐ Jalan Hang Kasturi 4 days 28/5/19 31/5/19 973 1019
981 SOFTSCAPE 120 days 10/5/19 7/10/19
982 HARDSCAPE ‐ LEFT SIDE OF TTCL 15 days 10/5/19 29/5/19
983 Jalan Pudu ‐ Jalan Tun Tan Siew Sin 3 days 10/5/19 13/5/19 880FS‐20 days 984
984 Jalan Tun Tan Siew Sin ‐ Jalan Petaling  3 days 14/5/19 16/5/19 983 985
985 Jalan Petaling ‐ Jalan Tun HS Lee 3 days 17/5/19 21/5/19 984 986
986 Jalan Tun HS Lee ‐ Jalan Hang Kasturi 3 days 23/5/19 25/5/19 985 987
987 Jalan Kasturi ‐ Klang River 3 days 27/5/19 29/5/19 986 1019
1002 ROAD RAMP CROSSING 42 days 16/3/19 4/5/19
1004 Jalan Tun H.S Lee 12 days 20/4/19 4/5/19 1003
1005 ROAD RESURFACING WORKS 50 days 16/3/19 14/5/19
1012 Right side of road 25 days 15/4/19 14/5/19
1015 Jalan Petaling ‐ Jalan Tun HS Lee 5 days 26/4/19 2/5/19 1014 1016
1016 Jalan Tun HS Lee ‐ Jalan Hang Kasturi 5 days 3/5/19 8/5/19 1015 1017
1017 Jalan Kasturi ‐ Klang River 5 days 9/5/19 14/5/19 1016

Page 2
ONE MONTH LOOK AHEAD - MARCH 2019
ID Task Name Duration Start Finish Predecessors Successors May '19 Ju
28 5 12 19 26
1020 ANCILLARY BUILDINGS AT PACKAGE 1C 430 days 2/4/18 30/8/19
1021  Cafe at Jalan Tun Perak 345 days 2/4/18 16/5/19
1030 Architectural works 139 days 27/11/18 15/5/19
1037 Rainwater downpipe 7 days 29/4/19 7/5/19 1036 1063
1038 Installation of External cladding 14 days 29/4/19 15/5/19 1036 1063
1039 Mechanical & Electrical 125 days 13/12/18 15/5/19
1040 Electrical works 125 days 13/12/18 15/5/19
1044 Testing and commisioning 21 days 20/4/19 15/5/19 1043 1064
1062 Completion 1 day 16/5/19 16/5/19
1063 Testing & inspection 1 day 16/5/19 16/5/19 1037,1038 1064
1064 Handover 0 days 16/5/19 16/5/19 1044,1049,1055,1061,1 16/5
1084 Bus Stop & Taxi stand at Jalan T.Tan Cheng Lock 430 days 2/4/18 30/8/19
1112 Kiosk at pocket park 73 days 2/3/19 29/5/19
1117 Installation of wall & roof covering 12 days 27/4/19 11/5/19 1116 1118
1118 Installation of decorative screen 6 days 13/5/19 18/5/19 1117 1119
1119 Installation of aluminum fin 6 days 21/5/19 28/5/19 1118 1120
1120 Painting works 1 day 29/5/19 29/5/19 1119
1122 CONSTRUCTION OF INTERCEPTOR 914 days 5/1/17 28/12/19
1123 PRELIMINARIES 841 days 5/1/17 1/10/19
1129 Environmental Management Plan 505 days 1/2/18 1/10/19
1131 Monthly Monitoring Data 481 days 1/3/18 1/10/19
1146 Monthly Monitoring Data 15 1 day 2/5/19 2/5/19
1153 SULLAGE WATER TREATMENT PLANT 600 days 1/1/18 21/12/19
1176  Sub‐Structure 268 days 16/10/18 10/9/19
1177 Zone A (P1‐P72) 72 points 214 days 16/10/18 4/7/19
1180 Construction of base slab 21 days 23/5/19 18/6/19 1179,1189 1181
1182 Zone B (P72‐P117) 45 points 167 days 23/1/19 16/8/19
1187 Zone C (P117‐P144) 27 points 117 days 17/4/19 10/9/19
1188 Excavation 14 days 17/4/19 3/5/19 1184 1189
1189 Micropile for foundation  14 days 4/5/19 21/5/19 1188 1190,1180
1241 PUMP SUMP 438 days 2/5/18 12/10/19
1242 Structure 231 days 1/10/18 9/7/19
1249 Structure ‐ CSO 44 days 1/4/19 24/5/19
1251 Construction of bases and slab 18 days 15/4/19 6/5/19 1250 1252
1252 Construction of wall & top slab 7 days 7/5/19 14/5/19 1251 1253,1255
1253 Installation of manhole & trash screen 7 days 15/5/19 24/5/19 1252 1294,1265
1254 Structure ‐ L2 44 days 15/5/19 9/7/19
1255 Excavation & Temporary works 12 days 15/5/19 30/5/19 1252 1256
1256 Construction of bases and slab 18 days 31/5/19 22/6/19 1255 1257
1259 Piping Works 382 days 2/5/18 5/8/19
1264 Force main works ‐ CSO 4 days 25/5/19 29/5/19
1265 Laying of pipe (DI/HDPE) 3 days 25/5/19 28/5/19 1253 1266
1266 Reinstatement work (drainage & kerb) 1 day 29/5/19 29/5/19 1265 1278,1279,1275