No: EEEPL - 01
Confirm location of
all utilities within
excavation area by
hand digging
Keep non-essential
personnel away
from work activities
Wear proper PPE.
Removed soil to
Soil collapse
Removed soil to be be 1 m keept if Site Engineer &
cleared in the area by from foundation Safety officer
manually.
Provide dust
By hand mix the concrete Inhalation mask
hazards
will be poured in the Full hand rupper
foundation dermatitis gloves Site Engineer &
hazards Safety officer
Frequent break
Slip and trip
hazards
Poor posture