Professional Documents
Culture Documents
Section #: CTRA
a) Draw a network diagram of this project and label the activities and events. [Use
AON convention]
End
Start
b) Calculate the total slack and scheduling times for all activities.
Activity ES LS EF LF TS
A 0 2 3 5 2
B 3 5 8 10 2
C 0 0 10 10 0
D 10 20 13 23 10
E 10 10 15 15 0
F 15 15 25 25 0
G 10 12 18 20 2
H 18 20 21 23 2
I 21 23 23 25 2
J 25 25 28 28 0
tCEFJ = tC + tE + tF + tJ = 10 + 5 + 10 + 3 = 28
d) When should team selection begin if the tournament is scheduled to start on the
morning of December 27? (Including Saturday and Sunday as working days).
The following activities have been identified by a consulting firm during the process
of developing an information system for an insurance firm. The purpose of the project is to
make a transition to a “paperless organization.”
Please note that this is a probabilistic problem and we will be using PERT technique
to solve this problem. Steps involved in the PERT techniques are essentially the same as
those involved in CPM.
a) Draw the network diagram, showing all the activities and their respective expected
times.
Start End
A 6 0 .5 .5
B 2 0 0 0 4/36
C 4 6 6.5 .5
D 5 6 7.5 1.5
E 10.5 2 2 0 81/36
F 9 2 3 1
G 2 10 10.5 .5
H 3.5 12.5 12.5 0 25/36
I 4 11 12 1
T = 16 110/36
𝒙−𝝁 𝟐𝟒−𝟏𝟔
𝐳= = = 𝟒. 𝟓𝟕
√𝝈𝟐 √𝟏𝟏𝟎/𝟑𝟔
The activities, listed below, are required for complete a project. The table provides a
list of these activities; their precedence relationships; and their respective activity
durations given in the form of “most optimistic time”; “most likely times”; and “most
pessimistic times.”
a) Draw a network diagram of this project showing the activities on nodes --- along
with their respective expected duration times.
C, 14 E, 11 H, 4
A, 7
Start
D, 5
F, 7 J, 1 End
B, 6
I, 18
G, 11
b) What are the critical path and the expected completion time of the project?
𝑥−𝝁 41 − 37
z= = = 0.8
√𝝈2 √25