You are on page 1of 13

CRONOGRAMA VALORIZADO

PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
Inicio de obra
01 ARQUITECTURA 7,958,691.50 0.00 0.00 1,203,179.99 3,303,654.94 2,135,478.61 1,149,550.09 166,827.81
01.01 ESTADIO 3,041,864.82 0.00 0.00 1,123,606.03 146,651.83 1,114,232.30 490,546.80 166,827.81
01.01.01 MUROS Y TABIQUES 220,804.44 0.00 0.00 105,776.27 55,608.16 55,608.16 3,811.85 0.00
01.01.01.01 MURO DE LADRILLO DE ARCILLA KING KONG DE SOGA m2 2,015.39 83.89 169,071.07 81,123.96 42,516.34 42,516.34 2,914.43
01.01.01.02 MURO DE LADRILLO DE ARCILLA KING KONG DE CABEZA m2 372.40 138.51 51,581.12 24,566.43 13,059.73 13,059.73 895.22
01.01.01.03 MURO DE LADRILLO DE ARCILLA PANDERETA DE SOGA m2 2.07 73.55 152.25 85.88 32.09 32.09 2.20
01.01.02 REVOQUES Y ENLUCIDOS 219,999.88 0.00 0.00 69,449.02 91,043.67 0.00 54,136.92 5,370.25
01.01.02.01 TARRAJEO DE MUROS EXTER. MZC. C:A. 1:5, E=1.5CM m2 1,338.36 27.70 37,072.57 14,651.27 21,416.98 1,004.32
01.01.02.02 TARRAJEO DE MUROS INTER. MZC. C:A. 1:5, E=1.5CM m2 5,853.29 21.55 126,138.40 36,382.58 52,052.91 35,208.94 2,493.97
01.01.02.03 TARRAJEO DE COLUMAS MZC. C:A. 1:5, E=1.5CM m2 551.32 24.92 13,738.89 4,200.72 5,185.00 4,065.22 287.95
01.01.02.04 TARRAJEO DE VIGAS MZC. C:A. 1:5, E=1.5CM m2 194.97 24.92 4,858.65 1,485.55 1,833.63 1,437.63 101.83
01.01.02.05 TARRAJEO EN MUROS DE CONCRETO MZC. C:A. 1:5, E=1.5CM m2 436.58 24.92 10,879.57 3,326.47 4,105.90 3,219.17 228.02
01.01.02.06 VESTIDURA DE FONDO DE GRADAS Y ESCALERAS m2 25.93 26.76 693.89 167.48 352.86 162.07 11.48
01.01.02.07 ENLUCIDO DE ESTUCO GRIS CLARO EXTERIORES m2 148.56 27.19 4,039.35 1,346.45 1,346.45 1,346.45
01.01.02.08 VESTIDURA DE DERRAME MZC. C:A. 1:5, E=1.5CM m 724.04 10.12 7,327.28 1,831.82 1,831.82 1,831.82 1,831.82
01.01.02.09 BRUÑAS m 2,673.00 4.70 12,563.10 5,154.63 2,066.77 4,988.35 353.34
01.01.02.10 TAPAJUNTA DE CAUCHO m 108.90 7.56 823.28 249.41 315.40 241.37 17.10
01.01.02.11 SELLANTE ASFÁLTICO BITUMINOSO COLOR NEGRO m 170.10 5.81 988.28 361.50 252.17 349.83 24.78
01.01.02.12 RECUBRIMIENTO DE CUARZO CERAMIZADO COLOR NEGRO PARA BORDES m DE ESCALERAS
53.00 E=5MM
16.54 876.62 291.14 283.78 281.75 19.96
01.01.03 CIELO RASOS 65,122.86 0.00 0.00 0.00 0.00 62,071.62 2,172.99 878.25
01.01.03.01 CIELORASO CON MZC. C.A. 1:5 CON CINTAS E=1.5CM m2 161.32 29.71 4,792.82 2,544.06 1,601.49 647.27
01.01.03.02 FALSO CIELORASO DE SISTEMA DRYWALL m2 849.36 71.03 60,330.04 59,527.56 571.50 230.98
01.01.04 PISOS Y PAVIMENTOS 1,361,357.46 0.00 0.00 948,380.74 0.00 0.00 292,087.00 120,889.71
01.01.04.01 CONTRAPISO CON MZC. 1:5, ACAB. 1CM. PASTA 1:2 m2 1,025.08 48.86 50,085.41 46,310.17 2,688.60 1,086.64
01.01.04.02 PISO DE CERÁMICO 60x60 GRANITE GREY ANTIDESLIZANTE m2 477.31 60.68 28,963.17 26,069.24 2,060.96 832.97
01.01.04.03 PISO DE CERÁMICO 60x60 CEMENTO GRIS ANTIDESLIZANTE m2 179.86 61.37 11,038.01 9,418.24 1,153.55 466.22
01.01.04.04 PISO DE CERÁMICO 60x60 AURA ANTIDESLIZANTE m2 133.80 54.89 7,344.28 5,553.54 1,275.30 515.44
01.01.04.05 PISO DE GRANITO 30X40CM m2 113.79 125.57 14,288.61 4,762.87 4,762.87 4,762.87
01.01.04.06 PISO CEMENTO SEMIPULIDO m2 137.16 48.00 6,583.68 5,173.13 1,004.54 406.00
01.01.04.07 PISO CEMENTO ESCOBILLADO m2 121.00 48.97 5,925.37 4,610.38 936.49 378.50
01.01.04.08 PISO DE LINÓLEO m2 33.77 54.04 1,824.93 1,241.93 415.19 167.81
01.01.04.09 PISO ARTIFICIAL SUPER STEM GRASS m2 7,182.00 172.00 1,235,304.00 845,241.24 277,789.50 112,273.26
01.01.05 CONTRAZOCALOS 11,505.70 0.00 0.00 0.00 0.00 7,659.41 2,432.46 1,413.82
01.01.05.01 CONTRAZÓCALO DE CEMENTO PULIDO H=30CM m 126.09 11.32 1,427.34 634.35 564.74 228.25
01.01.05.02 CONTRAZÓCALO DE CERÁMICO AURA H=10CM m 70.78 22.19 1,570.61 819.66 534.80 216.15
01.01.05.03 CONTRAZÓCALO DE CERÁMICO GRANITE GREY H=10CM m 68.73 24.94 1,714.13 867.05 603.26 243.82
01.01.05.04 CONTRAZOCALO DE CERAMICO CEMENTO GRIS h=0.10 m m 86.95 24.94 2,168.53 722.84 722.84 722.84
01.01.05.05 CONTRAZOCALO DE GRANITO H=0.30m m 163.20 28.34 4,625.09 4,615.51 6.82 2.76
01.01.06 ZOCALOS, ENCHAPES Y REVESTIMIENTOS 93,698.24 0.00 0.00 0.00 0.00 66,154.76 19,615.53 7,927.95
01.01.06.01 ZÓCALO CERÁMICO GRANITE GREY 60 X 60 CM m2 629.42 28.97 18,234.30 14,185.55 2,883.38 1,165.37
01.01.06.02 ZÓCALO CERÁMICO AURA 60 X 60 CM m2 38.25 30.96 1,184.22 959.81 159.82 64.59
01.01.06.03 REVESTIMIENTO DE GRADAS MZC. C.A: 1:4 m2 3,630.40 16.64 60,409.86 40,995.97 13,825.91 5,587.97
01.01.06.04 REVESTIMIENTO DE CERÁMICO EN ESCALERAS m2 24.21 37.68 912.23 738.77 123.53 49.93
01.01.06.05 REVESTIMIENTO DE GRANITO GRIS EN TABLEROS DE BAÑO m 47.87 116.10 5,557.71 5,557.71 0.00 0.00
01.01.06.06 REVESTIMIENTO DE CEMENTO PULIDO COLOREADO m2 15.96 11.26 179.71 107.67 51.31 20.74
01.01.06.07 TAPA CANTO DE ALUMINIO m 160.20 45.07 7,220.21 3,609.28 2,571.58 1,039.35
01.01.07 CUBIERTAS 427,816.41 0.00 0.00 0.00 0.00 322,381.15 75,087.42 30,347.83
01.01.07.01 FLEXILONA PRECONTRAINT 702 S2 BLANCO TRASLÚCIDO m2 2,499.84 170.28 425,672.76 321,221.34 74,386.77 30,064.65
01.01.07.02 CUBIERTA DE LADRILLO PASTELERO m2 36.50 58.73 2,143.65 1,159.81 700.65 283.18
01.01.08 CARPINTERIA DE MADERA 40,049.82 0.00 0.00 0.00 0.00 35,615.57 4,434.25 0.00
01.01.08.01 PUERTA DE MADERA CONTRAPLACADA P-1 / 0.70MX2.10M CON MARCOmDE CEDRO 14.00 1/2"X6" 623.39 2,493.56 2,249.01 244.55
01.01.08.02 PUERTA DE MADERA CONTRAPLACADA P-2 / 0.70MX2.10M CON MARCOund DE CEDRO 15.00
1/2"X6" CON
672.49
REJILLA 3,362.45 3,056.77 305.68
01.01.08.03 PUERTA DE MADERA CONTRAPLACADA P-4 / 0.80MX2.10M CON MARCOund DE CEDRO 11.00
1/2"X6" 656.09 656.09 595.33 60.76
01.01.08.04 PUERTA DE MADERA CONTRAPLACADA P-5 / 0.80MX2.10M CON MARCOund DE CEDRO 16.00
1/2"X6" PARA
636.26
EXTERIORES 3,817.56 3,462.07 355.49
01.01.08.05 PUERTA DE MADERA CONTRAPLACADA P-6 / 0.90MX2.10M CON MARCOund DE CEDRO 15.00
1/2"X6" 689.06 3,445.30 3,143.52 301.78
01.01.08.06 PUERTA DE MADERA CONTRAPLACADA P-7 / 0.90MX2.10M CON MARCOund DE CEDRO 19.00
1 1/2"X6" PARA
724.06
EXTERIORES 13,757.14 12,373.47 1,383.67
01.01.08.07 PUERTA DE MADERA CONTRAPLACADA P-8 / 1.00MX2.10M CON MARCOund DE CEDRO 14.00
1/2"X6" 721.94 2,887.76 2,647.98 239.78
01.01.08.08 PUERTA DE MADERA CONTRAPLACADA 2 HOJAS, P-9 / 1.80MX2.10M CON undMARCO DE4.00
CEDRO 1 889.84
1/2"X6" 3,559.36 3,337.78 221.58
01.01.08.09 MUEBLE ESCRITORIO CORRIDO DE MELAMINE EN CABINA DE LOCUCIÓN undA=0.50M 6.90 237.55 1,639.10 1,254.51 384.59
01.01.08.10 MUEBLE DE MELAMINE EN TIENDAS CON PUERTAS A=0.80M und 16.80 263.78 4,431.50 3,495.13 936.37
01.01.09 CARPINTERIA METALICA Y HERRERIA 177,823.18 0.00 0.00 0.00 0.00 168,687.68 9,135.50 0.00
01.01.09.01 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-1 DE 0.50X0.50 CON VIDRIO
und TEMPLADO27.00 DE 6MM252.73 6,823.71 5,696.21 1,127.50
01.01.09.02 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-2 DE 1.00X0.50 CON VIDRIO
und TEMPLADO39.00 DE 6MM312.57 12,190.23 10,549.62 1,640.61
01.01.09.03 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-3 DE 1.00X1.30 CON VIDRIO
und TEMPLADO 9.00 DE 6MM477.23 4,295.07 3,913.06 382.01
01.01.09.04 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-8 DE 3.80X1.10 CON VIDRIO
und TEMPLADO 1.00 DE 6MM385.17 385.17 288.85 96.32
01.01.09.05 MAMPARA ESTRUCTURA METÁLICA M-1 DE 3.80X2.30 CON VIDRIO TEMPLADO
und DE 8MM
1.00 1,389.88 1,389.88 1,247.88 142.00
01.01.09.06 MAMPARA ESTRUCTURA METÁLICA M-2 DE 5.75X4.50 CON VIDRIO TEMPLADO
und DE 8MM
1.00 2,605.16 2,605.16 1,946.45 658.71
01.01.09.07 REJA METÁLICA DE ACERO NEGRO 2 HOJAS R-1 DE 2.40X3.50 und 8.00 1,456.35 11,650.80 10,452.07 1,198.73
01.01.09.08 CORTINA ENROLLABLE METÁLICA V-9 DE 4.20X1.30 und 4.00 1,412.29 5,649.16 5,604.34 44.82
01.01.09.09 MUEBLE BAJO DE COCINA ACERO INOXIDABLE m 26.00 569.16 14,798.16 14,375.08 423.08
01.01.09.10 PASAMANOS DE ACERO INOXIDABLE 2" ADOSADO m 26.90 220.90 5,942.21 5,843.26 98.95
01.01.09.11 BARANDAS DE ACERO INOXIDABLE DE 2" m 16.60 240.58 3,993.63 3,858.51 135.12
01.01.09.12 BARANDAS DE ACERO NEGRO DE 2" m 500.00 216.20 108,100.00 104,912.35 3,187.65
01.01.10 CERRAJERIA 9,110.72 0.00 0.00 0.00 0.00 8,250.50 860.22 0.00
01.01.10.01 CERRADURA PARA PUERTAS DE MADERA CON MANIJA und 35.00 52.79 1,847.65 1,660.27 187.38
01.01.10.02 CERRADURA PARA PUERTAS DE MADERA CON PERILLA und 9.00 46.69 420.21 372.03 48.18
01.01.10.03 CERRADURA PARA MAMPARA Y PUERTA DE VIDRIO und 2.00 70.79 141.58 130.87 10.71
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
01.01.10.04 CERRADURA PARA VENTANA und 154.00 19.58 3,015.32 2,740.87 274.45
01.01.10.05 CERRADURA PICARPORTE PARA REJAS und 8.00 51.79 414.32 371.49 42.83
01.01.10.06 CERRADURA DE ALUMINIO A PISO und 2.00 187.79 375.58 364.87 10.71
01.01.10.07 TIRADORES PARA PUERTA DE VIDRIO und 2.00 51.65 103.30 98.55 4.75
01.01.10.08 BISAGRA CAPUCHINA ALUMINIZADA und 208.00 13.19 2,743.52 2,465.06 278.46
01.01.10.09 JUEGO DE BISAGRAS ALTA Y BAJA und 2.00 24.62 49.24 46.49 2.75
01.01.11 VIDRIOS 2,771.11 0.00 0.00 0.00 0.00 2,626.90 144.21 0.00
01.01.11.01 ESPEJOS EMPOTRADOS m2 43.11 64.28 2,771.11 2,626.90 144.21
01.01.12 PINTURAS 108,416.04 0.00 0.00 0.00 0.00 85,579.32 22,836.72 0.00
01.01.12.01 PINTURA LÁTEX EN MUROS INTERIORES m2 5,853.29 10.56 61,810.74 48,712.43 13,098.31
01.01.12.02 PINTURA LÁTEX EN COLUMNAS m2 551.32 12.45 6,863.93 5,098.35 1,765.58
01.01.12.03 PINTURA LATEX EN MUROS EXTERIORES m2 1,338.36 10.69 14,307.07 13,557.35 749.72
01.01.12.04 PINTURA EN CIELO RASO m2 161.32 12.45 2,008.43 1,491.81 516.62
01.01.12.05 PINTURA EN VIGAS m2 194.97 10.78 2,101.78 1,643.59 458.19
01.01.12.06 PINTURA DE FONDO DE ESCALERA m2 25.93 11.67 302.60 188.59 114.01
01.01.12.07 PINTURA ESMALTE SINTETICO m2 1,372.16 15.32 21,021.49 14,887.20 6,134.29
01.01.13 APARATOS SANITARIOS 99,510.73 0.00 0.00 0.00 0.00 95,719.00 3,791.73 0.00
01.01.13.01 INODORO CON FLUXOMETRO und 68.00 883.83 60,100.44 58,486.47 1,613.97
01.01.13.02 INODORO DISCAPACITADOS und 4.00 405.60 1,622.40 1,527.46 94.94
01.01.13.03 LAVAMANOS MÁNCORA BLANCO und 3.00 265.26 795.78 740.80 54.98
01.01.13.04 LAVAMANOS MÁNCORA PARA DISCAPACITADOS und 4.00 322.46 1,289.84 1,218.63 71.21
01.01.13.05 LAVAMANOS MAXBELL und 59.00 224.66 13,254.94 12,204.63 1,050.31
01.01.13.06 LAVADERO DE ACERO INOXDABLE SIMPLE und 2.00 438.26 876.52 839.87 36.65
01.01.13.07 LAVADERO DE ACERO INOXDABLE DOBLE und 4.00 554.26 2,217.04 2,143.74 73.30
01.01.13.08 URINARIO BAMBI BLANCO und 29.00 464.36 13,466.44 12,950.19 516.25
01.01.13.09 PLATO DE DUCHA 80X80 CM und 8.00 299.36 2,394.88 2,248.27 146.61
01.01.13.10 PLATO DE DUCHA 90x90 cm und 15.00 232.83 3,492.45 3,358.94 133.51
01.01.14 GRIFERIAS 23,144.45 0.00 0.00 0.00 0.00 23,144.45 0.00 0.00
01.01.14.01 GRIFERÍA TEMPORIZADA TENDRA DE BRONCE und 7.00 245.19 1,716.33 1,716.33
01.01.14.02 GRIFERÍA TEMPORIZADA THUNDER DE PICO MEDIO DE BRONCE und 59.00 240.95 14,216.05 14,216.05
01.01.14.03 MEZCLADORA EMPOTRADA REGULABLE THUNDER DE BRONCE PARA und
DUCHA 23.00 262.13 6,028.99 6,028.99
01.01.14.04 GRIFERÍA DE LAVADERO STANDAR DE 1/2" MANIJA T und 6.00 197.18 1,183.08 1,183.08
01.01.15 ACCESORIOS SANITARIOS 19,275.08 0.00 0.00 0.00 0.00 19,275.08 0.00 0.00
01.01.15.01 GANCHO PARA CABINA und 23.00 147.23 3,386.29 3,386.29
01.01.15.02 SECADORA DE MANOS und 18.00 465.81 8,384.58 8,384.58
01.01.15.03 DISPENSADOR DE PAPEL HIGIENICO und 72.00 34.37 2,474.64 2,474.64
01.01.15.04 DISPENSADOR DE PAPEL TOALLA und 23.00 158.82 3,652.86 3,652.86
01.01.15.05 DISPENSADOR DE JABON und 31.00 44.41 1,376.71 1,376.71
01.01.16 LIMPIEZA Y JARDINERIA 287.39 0.00 0.00 0.00 0.00 287.39 0.00 0.00
01.01.16.01 SIEMBRA DE GRASS m2 3.91 73.50 287.39 287.39
01.01.17 MOBILIARIO DEPORTIVO 113,316.79 0.00 0.00 0.00 0.00 113,316.79 0.00 0.00
01.01.17.01 BANCOS CORRIDOS DE MADERA PARA VESTUARIOS und 31.50 139.09 4,381.34 4,381.34
01.01.17.02 ASIENTOS PARA SUPLENTES PARA 12 DEPORTISTAS und 2.00 759.54 1,519.08 1,519.08
01.01.17.03 CASILLEROS-LOCKERS 4X2 (8 PUERTAS) und 9.00 650.79 5,857.11 5,857.11
01.01.17.04 CASILLEROS-LOCKERS 1X2 (2 PUERTAS) und 22.00 650.79 14,317.38 14,317.38
01.01.17.05 MESA DE PING PONG und 1.00 3,218.00 3,218.00 3,218.00
01.01.17.06 ARCO EMPOTRADO METALICO DE FUTBOL und 2.00 4,784.85 9,569.70 9,569.70
01.01.17.07 BANDERINES DE CORNER und 4.00 18.15 72.60 72.60
01.01.17.08 MARCADOR ELECTRÓNICO ESTADIO und 2.00 37,190.79 74,381.58 74,381.58
01.01.18 MOBILIARIO ADMINISTRATIVO 15,043.69 0.00 0.00 0.00 0.00 15,043.69 0.00 0.00
01.01.18.01 ESCRITORIO und 6.00 686.38 4,118.28 4,118.28
01.01.18.02 SILLA DE ESPERA und 29.00 254.77 7,388.33 7,388.33
01.01.18.03 SILLA DE ESCRITORIO und 7.00 254.77 1,783.39 1,783.39
01.01.18.04 ESTANTERÍA DE MADERA m 3.40 515.79 1,753.69 1,753.69
01.01.19 OTROS 32,810.83 0.00 0.00 0.00 0.00 32,810.83 0.00 0.00
01.01.19.01 TACHOS PEDAL und 68.00 44.63 3,034.84 3,034.84
01.01.19.02 TACHOS MEDIANOS und 16.00 64.63 1,034.08 1,034.08
01.01.19.03 SEPARADOR DE TABLERO FENOLICO - URINARIO und 24.00 284.63 6,831.12 6,831.12
01.01.19.04 CAMILLAS und 7.00 201.86 1,413.02 1,413.02
01.01.19.05 COMPUTADORA und 5.00 1,507.41 7,537.05 7,537.05
01.01.19.06 TELEFONOS und 4.00 89.26 357.04 357.04
01.01.19.07 CABINAS SANITARIAS TIPO 1(SANITARIOS) und 24.00 466.46 11,195.04 11,195.04
01.01.19.08 CABINAS SANITARIAS TIPO 2(DUCHAS) und 4.00 352.16 1,408.64 1,408.64
01.02 COLISEO 2,913,952.02 0.00 0.00 79,573.96 1,503,519.51 671,855.25 659,003.29 0.00
01.02.01 MUROS Y TABIQUES 155,316.23 0.00 0.00 79,573.96 47,796.64 27,945.62 0.00 0.00
01.02.01.01 MURO DE LADRILLO DE ARCILLA KING KONG DE SOGA m2 1,447.54 83.89 121,434.13 60,944.87 38,171.34 22,317.92
01.02.01.02 MURO DE LADRILLO DE ARCILLA PANDERETA DE SOGA m2 285.48 73.55 20,997.05 12,232.32 5,530.92 3,233.81
01.02.01.03 PARAPETOS DE LADRILLO KING KONG DE SOGA m2 166.84 77.23 12,885.05 6,396.77 4,094.38 2,393.89
01.02.02 REVOQUES Y ENLUCIDOS 151,872.38 0.00 0.00 0.00 95,494.26 56,378.12 0.00 0.00
01.02.02.01 TARRAJEO DE MUROS EXTER. MZC. C:A. 1:5, E=1.5CM m2 1,297.38 27.70 35,937.43 23,223.76 12,713.67
01.02.02.02 TARRAJEO DE MUROS INTER. MZC. C:A. 1:5, E=1.5CM m2 2,565.56 21.55 55,287.82 33,585.92 21,701.90
01.02.02.03 TARRAJEO DE COLUMAS MZC. C:A. 1:5, E=1.5CM m2 436.64 24.92 10,881.07 6,353.49 4,527.58
01.02.02.04 TARRAJEO DE VIGAS MZC. C:A. 1:5, E=1.5CM m2 373.44 24.92 9,306.12 5,433.87 3,872.25
01.02.02.05 TARRAJEO EN MUROS DE CONCRETO MZC. C:A. 1:5, E=1.5CM m2 251.60 24.92 6,269.87 3,661.00 2,608.87
01.02.02.06 VESTIDURA DE FONDO DE GRADAS Y ESCALERAS m2 255.98 26.76 6,850.02 4,600.06 2,249.96
01.02.02.07 ENLUCIDO DE MICROCEMENTO GRIS INTERIORES m2 217.59 51.31 11,164.54 7,036.18 4,128.36
01.02.02.08 VESTIDURA DE DERRAME MZC. C:A. 1:5, E=1.5CM m 851.38 10.12 8,615.97 8,130.35 485.62
01.02.02.09 BRUÑAS m 1,493.70 4.70 7,020.39 3,100.41 3,919.98
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
01.02.02.10 TAPAJUNTA DE CAUCHO m 31.20 7.56 235.87 138.63 97.24
01.02.02.11 SELLANTE ASFÁLTICO BITUMINOSO COLOR NEGRO m 52.20 5.81 303.28 230.59 72.69
01.02.03 CIELO RASOS 26,466.49 0.00 0.00 0.00 26,100.87 365.62 0.00 0.00
01.02.03.01 FALSO CIELORASO DE SISTEMA DRYWALL m2 372.61 71.03 26,466.49 26,100.87 365.62
01.02.04 PISOS Y PAVIMENTOS 269,675.62 0.00 0.00 0.00 171,156.64 98,518.98 0.00 0.00
01.02.04.01 CONTRAPISO CON MZC. 1:5, ACAB. 1CM. PASTA 1:2 m2 764.62 48.86 37,359.33 34,434.71 2,924.62
01.02.04.02 PISO DE CERÁMICO 60x60 GRANITE GREY ANTIDESLIZANTE m2 196.96 60.68 11,951.53 10,711.30 1,240.23
01.02.04.03 PISO DE CERÁMICO 60x60 CEMENTO GRIS ANTIDESLIZANTE m2 34.56 61.37 2,120.95 1,797.70 323.25
01.02.04.04 PISO DE CERÁMICO 60x60 AURA ANTIDESLIZANTE m2 70.40 54.89 3,864.26 2,885.70 978.56
01.02.04.05 PISO DE GRANITO 30X40CM m2 89.87 125.57 11,284.98 7,167.59 4,117.39
01.02.04.06 PISO CEMENTO SEMIPULIDO m2 450.27 48.00 21,612.96 16,803.77 4,809.19
01.02.04.07 PISO CEMENTO ESCOBILLADO m2 172.56 48.97 8,450.26 6,502.59 1,947.67
01.02.04.08 PISO DE MICROCEMENTO GRIS m2 142.60 151.63 21,622.44 13,448.60 8,173.84
01.02.04.09 PISO VINÍLICO HOMOGÉNEO EN ROLLO m2 800.00 84.11 67,288.00 17,945.25 49,342.75
01.02.04.10 PISO CEMENTO FROTACHADO PARA CANCHA DE COLISEO m2 1,444.88 58.22 84,120.91 59,459.43 24,661.48
01.02.05 CONTRAZOCALOS 6,285.81 0.00 0.00 0.00 3,387.70 2,898.11 0.00 0.00
01.02.05.01 CONTRAZÓCALO DE CEMENTO PULIDO H=30CM m 79.01 11.32 894.39 378.32 516.07
01.02.05.02 CONTRAZÓCALO DE CERÁMICO AURA H=10CM m 36.32 22.19 805.94 405.73 400.21
01.02.05.03 CONTRAZÓCALO DE CERÁMICO GRANITE GREY H=10CM m 73.48 24.94 1,832.59 892.03 940.56
01.02.05.04 CONTRAZOCALO DE CERAMICO CEMENTO GRIS h=0.10 m m 55.70 24.94 1,389.16 522.46 866.70
01.02.05.05 CONTRAZOCALO MICROCEMENTO GRIS H=0.30m m 21.14 16.61 351.14 178.75 172.39
01.02.05.06 CONTRAZOCALO DE GRANITO H=0.30m m 35.73 28.34 1,012.59 1,010.41 2.18
01.02.06 ZOCALOS, ENCHAPES Y REVESTIMIENTOS 138,643.23 0.00 0.00 0.00 113,699.14 24,944.09 0.00 0.00
01.02.06.01 ZÓCALO CERÁMICO GRANITE GREY 60 X 60 CM m2 264.80 28.97 7,671.26 5,902.23 1,769.03
01.02.06.02 ZÓCALO CERÁMICO AURA 60 X 60 CM m2 50.34 30.96 1,558.53 1,251.80 306.73
01.02.06.03 ZOCALO CERAMICO CEMENTO GRIS 60x60 m2 16.95 37.64 638.00 -2,089.32 2,727.32
01.02.06.04 REVESTIMIENTO DE GRADAS MZC. C.A: 1:4 m2 2,476.36 16.64 41,206.63 27,453.24 13,753.39
01.02.06.05 REVESTIMIENTO DE GRANITO GRIS EN TABLEROS DE BAÑO m 44.08 116.10 5,117.69 5,117.69 0.00
01.02.06.06 REVESTIMIENTO DE CEMENTO PULIDO COLOREADO m2 7.20 11.26 81.07 47.32 33.75
01.02.06.07 MCM FLEXIPANEL m2 359.04 220.53 79,179.09 74,482.62 4,696.47
01.02.06.08 TAPA CANTO DE ALUMINIO m 70.80 45.07 3,190.96 1,533.56 1,657.40
01.02.07 CUBIERTAS 1,126,402.20 0.00 0.00 0.00 1,045,884.26 80,517.94 0.00 0.00
01.02.07.01 FLEXILONA PRECONTRAINT 902 S2 BLANCO TRASLÚCIDO m2 3,465.00 325.08 1,126,402.20 1,045,884.26 80,517.94
01.02.08 CARPINTERIA DE MADERA 36,005.44 0.00 0.00 0.00 0.00 0.00 36,005.44 0.00
01.02.08.01 PUERTA DE MADERA CONTRAPLACADA P-1 / 0.70MX2.10M CON MARCOmDE CEDRO 16.00 1/2"X6" 623.39 3,740.34 3,740.34
01.02.08.02 PUERTA DE MADERA CONTRAPLACADA P-2 / 0.70MX2.10M CON MARCOund DE CEDRO 12.00
1/2"X6" CON
672.49
REJILLA 1,344.98 1,344.98
01.02.08.03 PUERTA DE MADERA CONTRAPLACADA P-4 / 0.80MX2.10M CON MARCOund DE CEDRO 14.00
1/2"X6" 656.09 2,624.36 2,624.36
01.02.08.04 PUERTA DE MADERA CONTRAPLACADA P-5 / 0.80MX2.10M CON MARCOund DE CEDRO 14.00
1/2"X6" PARA
636.26
EXTERIORES 2,545.04 2,545.04
01.02.08.05 PUERTA DE MADERA CONTRAPLACADA P-7 / 0.90MX2.10M CON MARCOund DE CEDRO 30.00
1 1/2"X6" PARA
724.06
EXTERIORES 21,721.80 21,721.80
01.02.08.06 PUERTA DE MADERA CONTRAPLACADA P-8 / 1.00MX2.10M CON MARCOund DE CEDRO 12.00
1/2"X6" 721.94 1,443.88 1,443.88
01.02.08.07 MUEBLE DE MELAMINE EN TIENDAS CON PUERTAS A=0.80M und 9.80 263.78 2,585.04 2,585.04
01.02.09 CARPINTERIA METALICA Y HERRERIA 617,416.99 0.00 0.00 0.00 0.00 0.00 617,416.99 0.00
01.02.09.01 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-1 DE 0.50X0.50 CON VIDRIO
und TEMPLADO2.00 DE 6MM252.73 505.46 505.46
01.02.09.02 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-2 DE 1.00X0.50 CON VIDRIO
und TEMPLADO
19.00 DE 6MM312.57 5,938.83 5,938.83
01.02.09.03 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-4 DE 2.20X0.50 CON VIDRIO
und TEMPLADO
14.00 DE 6MM447.65 6,267.10 6,267.10
01.02.09.04 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-5 DE 2.60X0.50 CON VIDRIO
und TEMPLADO
12.00 DE 6MM530.18 6,362.16 6,362.16
01.02.09.05 TEJIDO METALICO PARA FACHADA m2 735.00 650.00 477,750.00 477,750.00
01.02.09.06 REJA METÁLICA PLEGABLE DE ACERO NEGRO 4 HOJAS R-2 DE 4.60X3.50und 8.00 1,675.08 13,400.64 13,400.64
01.02.09.07 CORTINA ENROLLABLE METÁLICA V-10 DE 3.60X1.30 und 2.00 851.82 1,703.64 1,703.64
01.02.09.08 CORTINA ENROLLABLE METÁLICA V-11 DE 2.60X1.30 und 1.00 750.66 750.66 750.66
01.02.09.09 MUEBLE BAJO DE COCINA ACERO INOXIDABLE m 13.05 569.16 7,427.54 7,427.54
01.02.09.10 PASAMANOS DE ACERO INOXIDABLE 2" ADOSADO m 96.00 220.90 21,206.40 21,206.40
01.02.09.11 BARANDAS DE ACERO NEGRO DE 2" m 352.01 216.20 76,104.56 76,104.56
01.02.10 CERRAJERIA 5,580.86 0.00 0.00 0.00 0.00 0.00 5,580.86 0.00
01.02.10.01 CERRADURA PARA PUERTAS DE MADERA CON MANIJA und 10.00 52.79 527.90 527.90
01.02.10.02 CERRADURA PARA PUERTAS DE MADERA CON PERILLA und 38.00 46.69 1,774.22 1,774.22
01.02.10.03 CERRADURA PARA VENTANA und 118.00 19.58 2,310.44 2,310.44
01.02.10.04 CERRADURA PICARPORTE PARA REJAS und 8.00 51.79 414.32 414.32
01.02.10.05 BISAGRA CAPUCHINA ALUMINIZADA und 42.00 13.19 553.98 553.98
01.02.11 VIDRIOS 3,007.02 0.00 0.00 0.00 0.00 3,007.02 0.00 0.00
01.02.11.01 ESPEJOS EMPOTRADOS m2 46.78 64.28 3,007.02 3,007.02
01.02.12 PINTURAS 107,967.21 0.00 0.00 0.00 0.00 107,967.21 0.00 0.00
01.02.12.01 PINTURA LÁTEX EN MUROS INTERIORES m2 394.72 10.56 4,168.24 4,168.24
01.02.12.02 PINTURA LÁTEX EN COLUMNAS m2 436.64 12.45 5,436.17 5,436.17
01.02.12.03 PINTURA LATEX EN MUROS EXTERIORES m2 1,297.40 10.69 13,869.21 13,869.21
01.02.12.04 PINTURA EN CIELO RASO m2 255.98 12.45 3,186.95 3,186.95
01.02.12.05 PINTURA EN VIGAS m2 373.44 10.78 4,025.68 4,025.68
01.02.12.06 PINTURA ESMALTE SINTETICO m2 2,038.00 37.92 77,280.96 77,280.96
01.02.13 APARATOS SANITARIOS 78,146.83 0.00 0.00 0.00 0.00 78,146.83 0.00 0.00
01.02.13.01 INODORO CON FLUXOMETRO und 44.00 883.83 38,888.52 38,888.52
01.02.13.02 INODORO ONE PIECE und 7.00 536.22 3,753.54 3,753.54
01.02.13.03 INODORO DISCAPACITADOS und 4.00 405.60 1,622.40 1,622.40
01.02.13.04 LAVAMANOS MÁNCORA BLANCO und 6.00 265.26 1,591.56 1,591.56
01.02.13.05 LAVAMANOS MÁNCORA PARA DISCAPACITADOS und 4.00 322.46 1,289.84 1,289.84
01.02.13.06 LAVAMANOS MAXBELL und 45.00 224.66 10,109.70 10,109.70
01.02.13.07 LAVADERO DE ACERO INOXDABLE SIMPLE und 2.00 438.26 876.52 876.52
01.02.13.08 LAVADERO DE ACERO INOXDABLE DOBLE und 3.00 554.26 1,662.78 1,662.78
01.02.13.09 URINARIO BAMBI BLANCO und 32.00 464.36 14,859.52 14,859.52
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
01.02.13.10 PLATO DE DUCHA 90x90 cm und 15.00 232.83 3,492.45 3,492.45
01.02.14 GRIFERIAS 18,212.50 0.00 0.00 0.00 0.00 18,212.50 0.00 0.00
01.02.14.01 GRIFERÍA TEMPORIZADA TENDRA DE BRONCE und 10.00 245.19 2,451.90 2,451.90
01.02.14.02 GRIFERÍA TEMPORIZADA THUNDER DE PICO MEDIO DE BRONCE und 45.00 240.95 10,842.75 10,842.75
01.02.14.03 MEZCLADORA EMPOTRADA REGULABLE THUNDER DE BRONCE PARA und
DUCHA 15.00 262.13 3,931.95 3,931.95
01.02.14.04 GRIFERÍA DE LAVADERO STANDAR DE 1/2" MANIJA T und 5.00 197.18 985.90 985.90
01.02.15 ACCESORIOS SANITARIOS 25,824.43 0.00 0.00 0.00 0.00 25,824.43 0.00 0.00
01.02.15.01 GANCHO PARA CABINA und 59.00 147.23 8,686.57 8,686.57
01.02.15.02 SECADORA DE MANOS und 20.00 465.81 9,316.20 9,316.20
01.02.15.03 DISPENSADOR DE PAPEL HIGIENICO und 55.00 34.37 1,890.35 1,890.35
01.02.15.04 DISPENSADOR DE PAPEL TOALLA und 27.00 158.82 4,288.14 4,288.14
01.02.15.05 DISPENSADOR DE JABON und 37.00 44.41 1,643.17 1,643.17
01.02.16 MOBILIARIO DEPORTIVO 93,044.56 0.00 0.00 0.00 0.00 93,044.56 0.00 0.00
01.02.16.01 BANCOS CORRIDOS DE MADERA PARA VESTUARIOS und 35.45 139.09 4,930.74 4,930.74
01.02.16.02 ASIENTOS PARA SUPLENTES PARA 7 DEPORTISTAS und 2.00 463.77 927.54 927.54
01.02.16.03 CASILLEROS-LOCKERS 4X2 (8 PUERTAS) und 4.00 650.79 2,603.16 2,603.16
01.02.16.04 CASILLEROS-LOCKERS 1X2 (2 PUERTAS) und 4.00 650.79 2,603.16 2,603.16
01.02.16.05 TABLEROS MOVILES DE BASKETBOL DE CRISTAL TEMPLADO und 2.00 25,000.00 50,000.00 50,000.00
01.02.16.06 ARCOS MOVILES DE ACERO PARA FUTSAL und 2.00 3,721.55 7,443.10 7,443.10
01.02.16.07 NET DE VOLEY CON POSTE DE ACERO und 1.00 3,500.00 3,500.00 3,500.00
01.02.16.08 MARCADOR ELECTRÓNICO COLISEO und 2.00 10,518.43 21,036.86 21,036.86
01.02.17 MOBILIARIO ADMINISTRATIVO 9,879.08 0.00 0.00 0.00 0.00 9,879.08 0.00 0.00
01.02.17.01 ESCRITORIO und 4.00 686.38 2,745.52 2,745.52
01.02.17.02 SILLA DE ESPERA und 21.00 254.77 5,350.17 5,350.17
01.02.17.03 SILLA DE ESCRITORIO und 7.00 254.77 1,783.39 1,783.39
01.02.18 OTROS 44,205.14 0.00 0.00 0.00 0.00 44,205.14 0.00 0.00
01.02.18.01 TACHOS PEDAL und 55.00 44.63 2,454.65 2,454.65
01.02.18.02 TACHOS MEDIANOS und 16.00 64.63 1,034.08 1,034.08
01.02.18.03 TACHOS GRANDES und 3.00 461.04 1,383.12 1,383.12
01.02.18.04 SEPARADOR DE TABLERO FENOLICO - URINARIO und 28.00 284.63 7,969.64 7,969.64
01.02.18.05 CAMILLAS und 2.00 201.86 403.72 403.72
01.02.18.06 COMPUTADORA und 4.00 1,507.41 6,029.64 6,029.64
01.02.18.07 TELEFONOS und 4.00 89.26 357.04 357.04
01.02.18.08 CABINAS SANITARIAS TIPO 1(SANITARIOS) und 42.00 466.46 19,591.32 19,591.32
01.02.18.09 CABINAS SANITARIAS TIPO 2(DUCHAS) und 14.00 352.16 4,930.24 4,930.24
01.02.18.10 CANALETA DE DRENAJE SUSPENDIDA und 1.00 51.69 51.69 51.69
01.03 OBRAS EXTERIORES 2,002,874.66 0.00 0.00 0.00 1,653,483.60 349,391.06 0.00 0.00
01.03.01 MUROS Y TABIQUES 13,399.48 0.00 0.00 0.00 10,128.88 3,270.60 0.00 0.00
01.03.01.01 MURO DE LADRILLO DE ARCILLA KING KONG DE SOGA m2 117.53 83.89 9,859.59 7,443.52 2,416.07
01.03.01.02 MURO DE LADRILLO DE ARCILLA KING KONG DE CABEZA m2 22.27 138.51 3,084.62 2,323.58 761.04
01.03.01.03 MURO DE LADRILLO DE ARCILLA PANDERETA DE SOGA m2 6.19 73.55 455.27 361.78 93.49
01.03.02 REVOQUES Y ENLUCIDOS 58,359.35 0.00 0.00 0.00 37,579.26 20,780.09 0.00 0.00
01.03.02.01 TARRAJEO DE MUROS EXTER. MZC. C:A. 1:5, E=1.5CM m2 164.07 27.70 4,544.74 2,758.29 1,786.45
01.03.02.02 TARRAJEO DE MUROS INTER. MZC. C:A. 1:5, E=1.5CM m2 116.61 21.55 2,512.95 1,611.80 901.15
01.03.02.03 TARRAJEO DE COLUMAS MZC. C:A. 1:5, E=1.5CM m2 47.44 24.92 1,182.20 732.80 449.40
01.03.02.04 TARRAJEO DE VIGAS MZC. C:A. 1:5, E=1.5CM m2 7.59 24.92 189.14 117.24 71.90
01.03.02.05 TARRAJEO EN MUROS DE CONCRETO MZC. C:A. 1:5, E=1.5CM m2 520.31 24.92 12,966.13 8,037.21 4,928.92
01.03.02.06 ENLUCIDO DE ESTUCO GRIS CLARO EXTERIORES m2 74.31 27.19 2,020.49 1,208.54 811.95
01.03.02.07 VESTIDURA DE DERRAME MZC. C:A. 1:5, E=1.5CM m 63.20 10.12 639.58 606.64 32.94
01.03.02.08 SOLAQUEADO EN EXTERIORES m2 1,578.58 14.40 22,731.55 15,992.14 6,739.41
01.03.02.09 BRUÑAS m 382.05 4.70 1,795.64 879.65 915.99
01.03.02.10 SELLANTE ASFÁLTICO BITUMINOSO COLOR NEGRO m 431.60 5.81 2,507.60 1,367.22 1,140.38
01.03.02.11 RECUBRIMIENTO DE CUARZO CERAMIZADO COLOR NEGRO PARA BORDES
m DE ESCALERAS
439.50 E=5MM
16.54 7,269.33 4,267.73 3,001.60
01.03.03 CIELO RASOS 3,363.49 0.00 0.00 0.00 2,055.10 1,308.39 0.00 0.00
01.03.03.01 CIELORASO CON MZC. C.A. 1:5 CON CINTAS E=1.5CM m2 105.13 29.71 3,123.41 1,817.86 1,305.55
01.03.03.02 FALSO CIELORASO DE SISTEMA DRYWALL m2 3.38 71.03 240.08 237.24 2.84
01.03.04 PISOS Y PAVIMENTOS 704,487.43 0.00 0.00 0.00 492,649.74 211,837.69 0.00 0.00
01.03.04.01 CONTRAPISO CON MZC. 1:5, ACAB. 1CM. PASTA 1:2 m2 32.53 48.86 1,589.42 1,482.69 106.73
01.03.04.02 PISO DE CERÁMICO 60x60 GRANITE GREY ANTIDESLIZANTE m2 8.31 60.68 504.25 459.37 44.88
01.03.04.03 PISO DE CERÁMICO 60x60 CEMENTO GRIS ANTIDESLIZANTE m2 24.22 61.37 1,486.38 1,292.07 194.31
01.03.04.04 PISO CEMENTO SEMIPULIDO m2 510.71 48.00 24,514.08 19,835.13 4,678.95
01.03.04.05 PISO CEMENTO ESCOBILLADO m2 5,365.21 48.97 262,734.33 210,790.06 51,944.27
01.03.04.06 PISTA ATLÉTICA DE TARTAN PARA TROTE glb 3,047.80 78.00 237,728.40 124,740.10 112,988.30
01.03.04.07 PISO CEMENTO FROTACHADO PARA LOSA DEPORTIVA 4X4M m2 973.60 58.22 56,682.99 42,428.79 14,254.20
01.03.04.08 PISO ADOQUIN DE CONCRETO m2 1,416.51 68.41 96,903.45 71,015.27 25,888.18
01.03.04.09 SARDINELES E= 15CM, H=20CM m 289.92 77.07 22,344.13 20,606.26 1,737.87
01.03.05 CONTRAZOCALOS 4,972.22 0.00 0.00 0.00 2,476.58 2,495.64 0.00 0.00
01.03.05.01 CONTRAZÓCALO DE CEMENTO PULIDO H=30CM m 363.10 11.32 4,110.29 2,075.93 2,034.36
01.03.05.02 CONTRAZOCALO DE CERAMICO CEMENTO GRIS h=0.10 m m 34.56 24.94 861.93 400.65 461.28
01.03.06 ZOCALOS, ENCHAPES Y REVESTIMIENTOS 60,583.44 0.00 0.00 0.00 48,881.00 11,702.44 0.00 0.00
01.03.06.01 ZÓCALO CERÁMICO GRANITE GREY 60 X 60 CM m2 20.78 28.97 602.00 482.92 119.08
01.03.06.02 REVESTIMIENTO DE GRADAS MZC. C.A: 1:4 m2 203.21 16.64 3,381.41 2,413.32 968.09
01.03.06.03 REVESTIMIENTO DE CONCRETO ESTAMPADO TEXTURA PIEDRA PIZARRA
m2 NATURAL699.31 66.69 46,636.98 39,108.83 7,528.15
01.03.06.04 REVESTIMIENTO CON IMPERMEABILIZANTE m2 183.07 41.11 7,526.01 4,615.66 2,910.35
01.03.06.05 REVESTIMIENTO CON FACHALETAS EN EXTERIOR m2 2.34 879.68 2,058.45 2,050.36 8.09
01.03.06.06 TAPA CANTO DE ALUMINIO m 8.40 45.07 378.59 209.91 168.68
01.03.07 CUBIERTAS 2,488.98 0.00 0.00 0.00 1,471.32 1,017.66 0.00 0.00
01.03.07.01 CUBIERTA DE LADRILLO PASTELERO m2 42.38 58.73 2,488.98 1,471.32 1,017.66
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
01.03.08 CARPINTERIA DE MADERA 4,063.04 0.00 0.00 0.00 3,812.11 250.93 0.00 0.00
01.03.08.01 PUERTA DE MADERA CONTRAPLACADA P-1 / 0.70MX2.10M CON MARCOmDE CEDRO 13.00 1/2"X6" 623.39 1,870.17 1,763.99 106.18
01.03.08.02 PUERTA DE MADERA CONTRAPLACADA P-3 / 0.70MX2.10M CON MARCOund DE CEDRO 11.00
1/2"X6" PARA
744.75
EXTERIORES 744.75 684.32 60.43
01.03.08.03 PUERTA DE MADERA CONTRAPLACADA P-7 / 0.90MX2.10M CON MARCOund DE CEDRO 12.00
1/2"X6" PARA
724.06
EXTERIORES 1,448.12 1,363.80 84.32
01.03.09 CARPINTERIA METALICA Y HERRERIA 668,132.24 0.00 0.00 0.00 577,773.06 90,359.18 0.00 0.00
01.03.09.01 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-1 DE 0.50X0.50 CON VIDRIO
und TEMPLADO 3.00 DE 6MM252.73 758.19 685.66 72.53
01.03.09.02 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-6 DE 1.55X1.10 CON VIDRIO
und TEMPLADO 2.00 DE 6MM374.67 749.34 698.61 50.73
01.03.09.03 MARCO DE ALUMINIO 21/2"X1" PARA VENTANA V-7 DE 0.60X0.80 CON VIDRIO
und TEMPLADO 6.00 REFLEJANTE
374.67 DE 6MM 2,248.02 2,095.83 152.19
01.03.09.04 PANEL DE MALLA METÁLICA PARA MURO VEGETAL m2 120.12 267.28 32,105.67 30,316.54 1,789.13
01.03.09.05 REJA METÁLICA DE ACERO NEGRO 2 HOJAS R-3 DE 1.95X3.50 und 4.00 1,967.77 7,871.08 7,525.32 345.76
01.03.09.06 REJA METÁLICA DE ACERO NEGRO 2 HOJAS R-4 DE 2.40X2.70 und 8.00 1,114.43 8,915.44 8,221.44 694.00
01.03.09.07 REJA METALICA DE ACERO NEGRO 2 HOJAS, R-5 DE 3.00X2.70 und 1.00 1,667.85 1,667.85 1,581.10 86.75
01.03.09.08 REJA METALICA DE ACERO NEGRO 2 HOJAS, R-6 DE 6.00X2.70 und 1.00 1,791.82 1,791.82 1,692.00 99.82
01.03.09.09 PUERTA METALICA EN SUELO P-15 - 1.00x1.00m und 3.00 340.18 1,020.54 1,016.89 3.65
01.03.09.10 PASAMANOS DE ACERO INOXIDABLE 2" m 36.00 569.16 20,489.76 20,150.61 339.15
01.03.09.11 PASAMANOS DE ACERO INOXIDABLE 2" ADOSADO A MURO m 60.40 220.90 13,342.36 13,213.73 128.63
01.03.09.12 BARANDAS DE ACERO NEGRO DE 2" m 32.86 216.20 7,104.33 6,983.04 121.29
01.03.09.13 CERCO METÁLICO DE TUBOS RECTANGULARES. m 342.21 661.25 226,286.36 188,640.43 37,645.93
01.03.09.14 CERCO METÁLICO DE MALLA ELECTROSOLDADA m 351.14 624.40 219,251.82 174,031.13 45,220.69
01.03.09.15 CERCO METÁLICO DE PROTECCIÓN DEPORTIVA m2 82.40 229.33 18,896.79 16,200.95 2,695.84
01.03.09.16 PERFILES DE ACERO H=8.5M PARA PROTECCION DEPORTIVA und 15.00 6,036.33 90,544.95 90,440.60 104.35
01.03.09.17 PERFILES DE ACERO PARA CERRAMIENTO und 41.00 121.70 4,989.70 4,180.96 808.74
01.03.09.18 ESTRUCTURA METÁLICA PARA CUBIERTA DE INGRESO glb 1.00 10,098.22 10,098.22 10,098.22 0.00
01.03.10 CERRAJERIA 1,112.50 0.00 0.00 0.00 1,112.50 0.00 0.00 0.00
01.03.10.01 CERRADURA PARA PUERTAS DE MADERA CON MANIJA und 3.00 52.79 158.37 158.37
01.03.10.02 CERRADURA PARA PUERTAS DE MADERA CON PERILLA und 3.00 46.69 140.07 140.07
01.03.10.03 CERRADURA PARA VENTANA und 3.00 19.58 58.74 58.74
01.03.10.04 CERRADURA PICARPORTE PARA REJAS und 10.00 51.79 517.90 517.90
01.03.10.05 BISAGRA CAPUCHINA ALUMINIZADA und 18.00 13.19 237.42 237.42
01.03.11 PINTURAS 10,435.04 0.00 0.00 0.00 4,066.60 6,368.44 0.00 0.00
01.03.11.01 PINTURA LÁTEX EN MUROS INTERIORES m2 116.61 10.56 1,231.40 776.08 455.32
01.03.11.02 PINTURA LÁTEX EN COLUMNAS m2 23.40 12.45 291.33 160.57 130.76
01.03.11.03 PINTURA LATEX EN MUROS EXTERIORES m2 109.07 10.69 1,165.96 1,059.35 106.61
01.03.11.04 PINTURA EN CIELO RASO m2 32.53 12.45 405.00 223.22 181.78
01.03.11.05 PINTURA EN VIGAS m2 1.97 10.78 21.24 13.16 8.08
01.03.11.06 PINTURA ESMALTE PARA PISO DE ALTO TRÁNSITO m2 172.32 37.89 6,529.20 1,694.73 4,834.47
01.03.11.07 PINTURA PARA LOSA DEPORTIVA m 31.93 24.77 790.91 139.49 651.42
01.03.12 APARATOS SANITARIOS 2,404.44 0.00 0.00 0.00 2,404.44 0.00 0.00 0.00
01.03.12.01 INODORO ONE PIECE und 3.00 536.22 1,608.66 1,608.66
01.03.12.02 LAVAMANOS MÁNCORA BLANCO und 3.00 265.26 795.78 795.78
01.03.13 GRIFERIAS 1,314.84 0.00 0.00 0.00 1,314.84 0.00 0.00 0.00
01.03.13.01 GRIFERÍA TEMPORIZADA TENDRA DE BRONCE und 3.00 245.19 735.57 735.57
01.03.13.02 GRIFERÍA LLAVE DE BRONCE DE 1/2" und 3.00 193.09 579.27 579.27
01.03.14 ACCESORIOS SANITARIOS 236.34 0.00 0.00 0.00 236.34 0.00 0.00 0.00
01.03.14.01 DISPENSADOR DE PAPEL HIGIENICO und 3.00 34.37 103.11 103.11
01.03.14.02 DISPENSADOR DE JABON und 3.00 44.41 133.23 133.23
01.03.15 LIMPIEZA Y JARDINERIA 137,167.07 0.00 0.00 0.00 137,167.07 0.00 0.00 0.00
01.03.15.01 SIEMBRA DE GRASS m2 1,703.81 73.50 125,230.04 125,230.04
01.03.15.02 JARDINERÍAS-ÁRBOLES glb 1.00 2,218.40 2,218.40 2,218.40
01.03.15.03 PLANTAS-FLORES ARBUSTOS glb 92.40 105.18 9,718.63 9,718.63
01.03.16 MOBILIARIO URBANO 10,864.14 0.00 0.00 0.00 10,864.14 0.00 0.00 0.00
01.03.16.01 ALCORQUES und 2.00 1,504.77 3,009.54 3,009.54
01.03.16.02 BOTES ECOLÓGICOS DE BASURA und 8.00 60.90 487.20 487.20
01.03.16.03 BANCOS PARA EXTERIORES und 18.00 409.30 7,367.40 7,367.40
01.03.17 MOBILIARIO DEPORTIVO 7,443.10 0.00 0.00 0.00 7,443.10 0.00 0.00 0.00
01.03.17.01 ARCOS MOVILES DE ACERO PARA FUTSAL und 2.00 3,721.55 7,443.10 7,443.10
01.03.18 MOBILIARIO ADMINISTRATIVO 1,783.39 0.00 0.00 0.00 1,783.39 0.00 0.00 0.00
01.03.18.01 SILLA DE ESCRITORIO und 7.00 254.77 1,783.39 1,783.39
01.03.19 OTROS 310,264.13 0.00 0.00 0.00 310,264.13 0.00 0.00 0.00
01.03.19.01 TACHOS PEDAL und 3.00 44.63 133.89 133.89
01.03.19.02 CANALETA DE DRENAJE EN PISO und 508.00 61.69 31,338.52 31,338.52
01.03.19.03 PATE DE ESCALERA und 18.00 74.29 1,337.22 1,337.22
01.03.19.04 MALLA 8X8 HILO 3MM m2 455.00 606.77 276,080.35 276,080.35
01.03.19.05 ASTA DE BANDERAS INCLUIDO POYO DE CONCRETO und 1.00 374.15 374.15 374.15
01.03.19.06 MÓDULO DE ENTRENAMIENTO DE CONCRETO (BANCOS) und 1.00 500.00 500.00 500.00
01.03.19.07 MÓDULO DE ENTRENAMIENTO DE ACERO (BARRAS) und 1.00 500.00 500.00 500.00
02 ESTRUCTURAS 16,857,004.67 3,663,537.30 3,581,770.42 2,988,579.87 1,179,912.82 2,219,056.43 1,669,931.60 1,554,216.28
02.01 ESTADIO 6,191,393.67 1,644,054.36 1,202,754.89 875,290.43 704,991.82 1,467,745.08 164,574.05 131,983.05
02.01.01 MOVIMIENTO DE TIERRAS 1,447,894.83 947,098.42 491,767.79 9,028.62 0.00 0.00 0.00 0.00
02.01.01.01 EXCAVACIÓN DE ZAPATAS, VIGAS DE CIMENTACION, ZANJAS Y CIMIENTOS
m3 1,788.20 15.84 28,325.09 4,661.84 14,634.63 9,028.62
02.01.01.02 EXCAVACIONES DE PILOTES m 2,098.00 676.63 1,419,569.74 942,436.58 477,133.16
02.01.02 OBRAS DE CONCRETO SIMPLE 24,528.79 0.00 0.00 19,147.09 3,755.97 1,625.73 0.00 0.00
02.01.02.01 CONCRETO SIMPLE PARA SOLADO C:H 1:10 E=2" m2 87.58 9.24 809.24 460.39 220.14 128.71
02.01.02.02 SUBCIMIENTO/SUBZAPATA f'c=140k/cm² + 40% P.G m3 115.66 205.08 23,719.55 18,686.70 3,535.83 1,497.02
02.01.03 CONCRETO ARMADO 1,616,308.13 212,231.85 454,915.83 581,049.02 128,749.35 217,560.69 20,282.22 1,519.18
02.01.03.01 CONCRETO ARMADO PREMEZCLADO PARA ENCEPADOS Y ZAPATAS F'C m3=210 KG/CM2
801.72 288.19 231,047.69 203,647.60 16,295.50 11,104.59
02.01.03.02 CONCRETO ARMADO PREMEZCLADO PARA VIGAS DE CIMENTACIÓN F'C m3=210 KG/CM2
116.57 286.61 33,410.13 31,126.76 2,274.20 9.17
02.01.03.03 CONCRETO ARMADO PREMEZCLADO PARA COLUMNA f'c =210 kg/cm2 m3 176.50 288.66 50,948.49 45,871.87 4,356.41 720.21
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
02.01.03.04 CONCRETO ARMADO PREMEZCLADO PARA PLACA f'c =210 kg/cm2 m3 3.90 289.96 1,130.84 1,007.59 82.83 40.42
02.01.03.05 CONCRETO ARMADO PREMEZCLADO PARA VIGA f'c =210 kg/cm2 m3 391.58 279.59 109,481.85 99,069.89 8,892.78 1,519.18
02.01.03.06 CONCRETO ARMADO PREMEZCLADO PARA LOSA MACIZA f'c =210 kg/cm2 m3 373.38 293.17 109,463.81 99,118.26 10,345.55
02.01.03.07 CONCRETO ARMADO PREMEZCLADO PARA ESCALERA f'c =210 kg/cm2 m3 5.59 327.12 1,828.60 1,554.51 274.09
02.01.03.08 CONCRETO ARMADO PREMEZCLADO PARA PILOTES F'C =245 KG/CM2 m3 2,098.00 315.25 661,394.50 296,249.62 330,697.25 34,447.63
02.01.03.09 ENCOFRADO Y DESENCOFRADO DE ELEMENTOS DE HORMIGÓN m2 7,682.16 54.36 417,602.22 212,231.85 158,666.21 46,704.17
02.01.04 ACERO PARA OBRAS DE CONCRETO ARMADO 1,753,507.25 484,724.09 256,071.27 266,065.70 572,486.50 174,159.69 0.00 0.00
02.01.04.01 ACERO DE REFUERZO PARA ENCEPADOS Y ZAPATAS f´y=4200 Kg/cm2 kg 29,496.41 4.38 129,194.28 95,656.53 33,537.75
02.01.04.02 ACERO DE REFUERZO PARA VIGAS CENTRADORAS f´y=4200 Kg/cm2 kg 33,086.42 4.38 144,918.52 107,298.89 37,619.63
02.01.04.03 ACERO DE REFUERZO PARA COLUMNAS f´y=4200 Kg/cm2 kg 19,397.90 4.38 84,962.80 62,907.17 22,055.63
02.01.04.04 ACERO DE REFUERZO PARA PLACAS f´y=4200 Kg/cm2 kg 62.63 4.38 274.32 203.11 71.21
02.01.04.05 ACERO DE REFUERZO PARA VIGAS f´y=4200 Kg/cm2 kg 133,974.30 4.38 586,807.43 428,952.21 157,855.22
02.01.04.06 ACERO DE REFUERZO PARA LOSAS MACIZAS f´y=4200 Kg/cm2 kg 14,228.00 4.38 62,318.64 46,811.81 15,506.83
02.01.04.07 ACERO DE REFUERZO PARA ESCALERAS f´y=4200 Kg/cm2 kg 967.10 4.38 4,235.90 3,438.26 797.64
02.01.04.08 ACERO DE REFUERZO PARA PILOTES f´y=4200 Kg/cm2 kg 106,131.14 6.98 740,795.36 484,724.09 256,071.27
02.01.05 ESTRUCTURA METALICA 1,349,154.67 0.00 0.00 0.00 0.00 1,074,398.97 144,291.83 130,463.87
02.01.05.01 TIJERAL ESTADIO kg 86,818.19 15.54 1,349,154.67 1,074,398.97 144,291.83 130,463.87
02.02 COLISEO 6,612,809.93 1,466,595.81 2,105,609.41 1,616,716.46 474,921.00 751,311.35 140,282.59 57,373.34
02.02.01 MOVIMIENTO DE TIERRAS 2,204,870.59 724,190.62 761,046.25 715,419.35 4,214.39 0.00 0.00 0.00
02.02.01.01 EXCAVACIÓN DE ZAPATAS, VIGAS DE CIMENTACION, ZANJAS, CIMIENTOSm3 2,332.58 15.84 36,948.07 4,560.78 14,317.38 13,855.53 4,214.39
02.02.01.02 EXCAVACIONES DE PILOTES m 3,204.00 676.63 2,167,922.52 719,629.84 746,728.87 701,563.82
02.02.02 OBRAS DE CONCRETO SIMPLE 948.21 509.55 438.66 0.00 0.00 0.00 0.00 0.00
02.02.02.01 CONCRETO SIMPLE PARA SOLADO C:H 1:10 E=2" m2 102.62 9.24 948.21 509.55 438.66
02.02.03 CONCRETO ARMADO 1,898,889.32 184,337.63 688,516.43 544,805.20 360,499.24 119,635.57 1,095.25 0.00
02.02.03.01 CONCRETO ARMADO PREMEZCLADO PARA ENCEPADOS Y ZAPATAS F'C m3=210 KG/CM2
948.40 288.19 273,319.40 268,922.14 4,397.26
02.02.03.02 CONCRETO ARMADO PREMEZCLADO PARA VIGAS DE CIMENTACIÓN F'C m3=210 KG/CM2
115.44 286.61 33,086.26 33,086.26
02.02.03.03 CONCRETO ARMADO PREMEZCLADO PARA COLUMNA f'c =210 kg/cm2 m3 118.40 288.66 34,177.34 29,546.33 2,828.10 1,802.91
02.02.03.04 CONCRETO ARMADO PREMEZCLADO PARA PLACA f'c =210 kg/cm2 m3 138.21 289.96 40,075.37 34,517.85 4,261.36 1,296.16
02.02.03.05 CONCRETO ARMADO PREMEZCLADO PARA VIGA f'c =210 kg/cm2 m3 284.29 279.59 79,484.64 68,858.77 4,765.31 4,765.31 1,095.25
02.02.03.06 CONCRETO ARMADO PREMEZCLADO PARA LOSA MACIZA f'c =210 kg/cm2 m3 138.21 293.17 40,519.03 34,555.67 4,724.96 1,238.40
02.02.03.07 CONCRETO ARMADO PREMEZCLADO PARA PILOTES F'C =250 KG/CM2 m3 3,204.00 315.25 1,010,061.00 211,832.24 336,687.00 347,909.90 113,631.86
02.02.03.08 ENCOFRADO Y DESENCOFRADO DE ELEMENTOS DE HORMIGÓN m2 7,140.66 54.36 388,166.28 184,337.63 110,611.61 93,217.04
02.02.04 ACERO PARA OBRAS DE CONCRETO ARMADO 1,748,525.10 557,558.01 655,608.07 356,491.91 110,207.37 51,327.28 17,332.47 0.00
02.02.04.01 ACERO DE REFUERZO PARA ENCEPADOS Y ZAPATAS f´y=4200 Kg/cm2 kg 41,355.19 4.38 181,135.73 109,215.05 46,777.68 25,143.00
02.02.04.02 ACERO DE REFUERZO PARA VIGAS DE CIMENTACIÓN f´y=4200 Kg/cm2kg 36,036.52 4.38 157,839.96 96,485.21 50,952.04 10,402.71
02.02.04.03 ACERO DE REFUERZO PARA COLUMNAS f´y=4200 Kg/cm2 kg 45,731.66 4.38 200,304.67 116,875.32 21,553.33 22,271.78 22,271.78 17,332.47
02.02.04.04 ACERO DE REFUERZO PARA PLACAS f´y=4200 Kg/cm2 kg 6,648.00 4.38 29,118.24 17,556.72 7,519.69 4,041.83
02.02.04.05 ACERO DE REFUERZO PARA VIGAS f´y=4200 Kg/cm2 kg 28,144.30 4.38 123,272.03 73,641.04 27,413.11 22,217.88
02.02.04.06 ACERO DE REFUERZO PARA LOSAS MACIZAS f´y=4200 Kg/cm2 kg 16,120.00 4.38 70,605.60 42,833.04 20,934.94 6,837.62
02.02.04.07 ACERO DE REFUERZO PARA PILOTES f´y=4200 Kg/cm2 kg 141,296.40 6.98 986,248.87 557,558.01 315,475.77 113,215.09
02.02.05 ESTRUCTURA METALICA 759,576.71 0.00 0.00 0.00 0.00 580,348.50 121,854.87 57,373.34
02.02.05.01 TIJERAL COLISEO kg 48,878.81 15.54 759,576.71 580,348.50 121,854.87 57,373.34
02.03 OBRAS EXTERIORES 4,052,801.07 552,887.13 273,406.12 496,572.98 0.00 0.00 1,365,074.96 1,364,859.89
02.03.01 OBRAS PROVISIONALES 82,431.66 82,431.66 0.00 0.00 0.00 0.00 0.00 0.00
02.03.01.01 CASETA DE GUARDIANÍA, OFICINA Y ALMACÉN m2 50.00 81.36 4,068.00 4,068.00
02.03.01.02 SERVICIOS HIGIENICOS m2 100.00 65.81 6,581.00 6,581.00
02.03.01.03 VESTUARIO m2 120.00 55.66 6,679.20 6,679.20
02.03.01.04 CARTEL DE OBRA und 2.00 1,032.77 2,065.54 2,065.54
02.03.01.05 CERCO PROVISIONAL m 736.55 59.71 43,979.40 43,979.40
02.03.01.06 INSTALACIONES PROVISIONALES DE AGUA mes 12.00 797.21 9,566.52 9,566.52
02.03.01.07 INSTALACIONES PROVISIONALES DE ELECTRICIDAD mes 12.00 416.00 4,992.00 4,992.00
02.03.01.08 INSTALACIONES PROVISIONALES DE TELEFÒNIA Y COMUNICACIÓN mes 12.00 375.00 4,500.00 4,500.00
02.03.02 SEGURIDAD Y SALUD 172,208.41 171,580.87 627.54 0.00 0.00 0.00 0.00 0.00
02.03.02.01 ELABORACIÓN, IMPLEMENTACIÓN Y ADMINISTRACIÓN DEL PLAN DE SEGURIDAD
glb Y SALUD
1.00 EN16,734.43
EL TRABAJO 16,734.43 16,106.89 627.54
02.03.02.02 EQUIPOS DE PROTECCIÒN INDIVIDUAL glb 1.00 82,121.41 82,121.41 82,121.41
02.03.02.03 EQUIPOS DE PROTECCIÓN COLECTIVA glb 1.00 12,550.82 12,550.82 12,550.82
02.03.02.04 SEÑALIZACIÒN TEMPORAL DE SEGURIDAD glb 1.00 23,428.20 23,428.20 23,428.20
02.03.02.05 CAPACITACIÓN EN SEGURIDAD Y SALUD glb 1.00 33,468.85 33,468.85 33,468.85
02.03.02.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIA EN SEGURIDAD Yglb SALUD DURANTE
1.00 EL TRABAJO
3,904.70 3,904.70 3,904.70
02.03.03 TRABAJOS PRELIMINARES 71,987.09 57,908.28 14,078.81 0.00 0.00 0.00 0.00 0.00
02.03.03.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 1.00 20,000.00 20,000.00 20,000.00
02.03.03.02 TRAZO, NIVELES Y REPLANTEOS m2 28,311.20 1.80 50,960.16 36,881.35 14,078.81
02.03.03.03 DEMOLICIÓN DE ELEMENTOS DE CONCRETO m3 108.44 9.47 1,026.93 1,026.93
02.03.04 MOVIMIENTO DE TIERRAS 996,239.07 240,966.32 258,699.77 496,572.98 0.00 0.00 0.00 0.00
02.03.04.01 EXCAVACIÓN MASIVA CON MÁQUINA m3 31,630.40 15.83 500,709.23 240,966.32 258,699.77 1,043.14
02.03.04.02 EXCAVACIÓN DE ZAPATAS, VIGAS DE CIMENTACION, ZANJAS, CIMIENTOSm3 572.83 15.84 9,073.63 9,073.63
02.03.04.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO, AFIRMADO m3 224.64 60.46 13,581.73 13,581.73
02.03.04.04 ELIMINACIÓN DE MATERIAL EXCEDENTE CON MAQUINARIA m3 31,630.40 14.95 472,874.48 472,874.48
02.03.05 OBRAS DE CONCRETO SIMPLE 107,184.47 0.00 0.00 0.00 0.00 0.00 53,699.77 53,484.70
02.03.05.01 CONCRETO SIMPLE PARA SOLADO C:H 1:10 E=2" m2 97.64 9.24 902.19 902.19
02.03.05.02 CONCRETO EN PAVIMENTOS f'c=210 Kg/cm² e= 0.20 m m2 775.56 69.24 53,699.77 53,699.77
02.03.05.03 SUBCIMIENTO/SUBZAPATA f'c=140k/cm² + 40% P.G m3 256.40 205.08 52,582.51 52,582.51
02.03.06 CONCRETO ARMADO 2,320,957.74 0.00 0.00 0.00 0.00 0.00 1,160,478.87 1,160,478.87
02.03.06.01 CONCRETO EN CISTERNA (CEM TIPO IP) f'c=280 Kg/cm2 C/IMPERMEABILIZANTE
m3 130.17 317.05 41,270.40 20,635.20 20,635.20
02.03.06.02 CONCRETO ARMADO PREMEZCLADO PARA ENCEPADOS Y ZAPATAS F'C m3=210 KG/CM26.52 288.19 1,879.00 939.50 939.50
02.03.06.03 CONCRETO ARMADO PREMEZCLADO PARA VIGAS DE CIMENTACIÓN F'C m3=210 KG/CM24.22 286.61 1,209.49 604.75 604.75
02.03.06.04 CONCRETO ARMADO PREMEZCLADO PARA COLUMNA f'c =210 kg/cm2 m3 5.54 288.66 1,599.18 799.59 799.59
02.03.06.05 CONCRETO ARMADO PREMEZCLADO PARA VIGA f'c =210 kg/cm2 m3 4.32 279.59 1,207.83 603.92 603.92
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
02.03.06.06 CONCRETO ARMADO PREMEZCLADO PARA LOSA MACIZA f'c =210 kg/cm2
m3 5.47 293.17 1,603.64 801.82 801.82
02.03.06.07 ENCOFRADO Y DESENCOFRADO DE ELEMENTOS DE HORMIGÓN m2 3,008.45 54.36 163,539.34 81,769.67 81,769.67
02.03.06.08 CONCRETO PREMEZCLADO MURO DE CONTENCION f'c=210 kg/cm2 m3 1,250.36 291.98 365,080.11 182,540.06 182,540.06
02.03.06.09 MURO DE GAVIONES m3 6,875.00 253.61 1,743,568.75 871,784.38 871,784.38
02.03.07 ACERO PARA OBRAS DE CONCRETO ARMADO 301,792.63 0.00 0.00 0.00 0.00 0.00 150,896.32 150,896.32
02.03.07.01 ACERO DE REFUERZO PARA ENCEPADOS Y ZAPATAS f´y=4200 Kg/cm2 kg 6,349.79 4.38 27,812.08 13,906.04 13,906.04
02.03.07.02 ACERO DE REFUERZO PARA VIGAS DE CIMENTACIÓN f´y=4200 Kg/cm2kg 522.44 4.38 2,288.29 1,144.15 1,144.15
02.03.07.03 ACERO DE REFUERZO PARA COLUMNAS f´y=4200 Kg/cm2 kg 9,025.20 4.38 39,530.38 19,765.19 19,765.19
02.03.07.04 ACERO DE REFUERZO PARA PLACAS f´y=4200 Kg/cm2 kg 20,523.34 4.38 89,892.23 44,946.12 44,946.12
02.03.07.05 ACERO DE REFUERZO PARA VIGAS f´y=4200 Kg/cm2 kg 3,018.60 4.38 13,221.47 6,610.74 6,610.74
02.03.07.06 ACERO DE REFUERZO PARA LOSAS MACIZAS f´y=4200 Kg/cm2 kg 4,216.06 4.38 18,466.34 9,233.17 9,233.17
02.03.07.07 ACERO DE REFUERZO PARA MURO DE CONTENCIÓN f´y=4200 Kg/cm2 kg 27,507.92 4.02 110,581.84 55,290.92 55,290.92
03 INSTALACIONES ELECTRICAS 1,728,097.89 0.00 0.00 0.00 0.00 2,801.92 536,638.52 1,188,657.44
03.01 ESTADIO 155,924.10 0.00 0.00 0.00 0.00 2,801.92 148,232.02 4,890.15
03.01.01 ALIMENTADORES ELÉCTRICOS INTERIORES 23,479.31 0.00 0.00 0.00 0.00 0.00 23,479.31 0.00
03.01.01.01 ALIMENTADOR NH-80 1x4 mm2 m 1,493.24 5.58 8,332.28 8,332.28
03.01.01.02 ALIMENTADOR NH-80 1x2.5 mm2 m 2,907.30 5.21 15,147.03 15,147.03
03.01.02 CABLES DE COBRE 5,514.38 0.00 0.00 0.00 0.00 0.00 5,514.38 0.00
03.01.02.01 COBRE BLANDO 4 mm2 m 1,062.50 5.19 5,514.38 5,514.38
03.01.03 TUBERÍA 10,606.07 0.00 0.00 0.00 0.00 2,629.42 5,479.80 2,496.84
03.01.03.01 TUBERIA PVC-SAP 21 mm m 1,121.32 8.78 9,845.19 2,440.79 5,086.68 2,317.72
03.01.03.02 TUBERÍA CORRUGADA FLEXIBLE 21 mm m 97.80 7.78 760.88 188.63 393.12 179.12
03.01.04 TABLEROS 28,337.81 0.00 0.00 0.00 0.00 0.00 28,337.81 0.00
03.01.04.01 TABLERO DISTRIBUCION ST-1 und 1.00 5,358.38 5,358.38 5,358.38
03.01.04.02 TABLERO DISTRIBUCION ST-2 und 1.00 7,171.81 7,171.81 7,171.81
03.01.04.03 TABLERO DISTRIBUCION ST-3 und 1.00 7,437.81 7,437.81 7,437.81
03.01.04.04 TABLERO DISTRIBUCION ST-4 und 1.00 8,369.81 8,369.81 8,369.81
03.01.05 SALIDAS 27,307.41 0.00 0.00 0.00 0.00 0.00 25,056.49 2,250.92
03.01.05.01 SALIDA ILUMINACION PARA TECHO pto 210.00 51.17 10,745.70 9,860.13 885.57
03.01.05.02 SALIDA ILUMINACION EN MURO pto 3.00 45.79 137.37 126.05 11.32
03.01.05.03 SALIDA TOMACORRIENTE EMERGENCIA pto 39.00 75.46 2,942.94 2,700.32 242.62
03.01.05.04 SALIDA TOMACORRIENTE DOBLE 0.30 M. pto 52.00 81.84 4,255.68 3,904.82 350.86
03.01.05.05 SALIDA TOMACORRIENTE DOBLE 1.10 M pto 8.00 81.84 654.72 600.75 53.98
03.01.05.06 SALIDA TOMACORRIENTE DOBLE A PRUEBA DE AGUA pto 16.00 129.84 2,077.44 1,906.12 171.32
03.01.05.07 SALIDA TOMACORRIENTE SECAMANOS 1.20 M pto 14.00 45.98 643.72 590.67 53.04
03.01.05.08 SALIDA TOMACORRIENTE SECAMANOS 0.70 M pto 4.00 45.98 183.92 168.76 15.16
03.01.05.09 SALIDA TOMACORRIENTE ACCESS POINT pto 4.00 75.46 301.84 276.96 24.88
03.01.05.10 SALIDA TERMA ELECTRICA pto 4.00 45.98 183.92 168.76 15.16
03.01.05.11 SALIDA TOMACORRIENTE REFRIGERADORA pto 4.00 76.23 304.92 279.78 25.14
03.01.05.12 SALIDA MARCADOR ELECTRÒNICO pto 2.00 48.44 96.88 88.89 7.99
03.01.05.13 SALIDA TOMACORRIENTE COMUNICACIONES, SONIDO pto 2.00 81.84 163.68 150.18 13.49
03.01.05.14 SALIDA TOMACORRIENTE CENTRAL DE ALARMA pto 2.00 45.98 91.96 84.38 7.58
03.01.05.15 SALIDA PARA SENSORES DE PRESENCIA pto 16.00 47.19 755.04 692.82 62.22
03.01.05.16 SALIDA PARA INTERRUPTOR SIMPLE pto 50.00 65.78 3,289.00 3,017.89 271.12
03.01.05.17 SALIDA PARA INTERRUPTOR DOBLE pto 1.00 71.78 71.78 65.86 5.92
03.01.05.18 SALIDA PARA INTERRUPTOR SIMPLE CONMUTADO 3 VÌAS pto 4.00 73.78 295.12 270.79 24.33
03.01.05.19 SALIDA PARA INTERRUPTOR SIMPLE CONMUTADO 4 VÌAS pto 1.00 111.78 111.78 102.56 9.22
03.01.06 CAJAS DE PASE 1,384.92 0.00 0.00 0.00 0.00 172.50 1,070.03 142.39
03.01.06.01 CAJAS DE PASE CUADRADAS DE 97x97x45 mm und 24.00 45.42 1,090.08 135.73 842.27 112.08
03.01.06.02 CAJAS DE PASE REDONDA DE Ø 108x40 mm und 7.00 42.12 294.84 36.77 227.76 30.31
03.01.07 SENSORES DE PRESENCIA 9,788.16 0.00 0.00 0.00 0.00 0.00 9,788.16 0.00
03.01.07.01 SENSOR DE TECHO und 16.00 611.76 9,788.16 9,788.16
03.01.08 LUMINARIAS INTERIORES 43,101.84 0.00 0.00 0.00 0.00 0.00 43,101.84 0.00
03.01.08.01 LUMINARIA 750 MINICOMFORT T5 (4x14w) und 31.00 120.84 3,746.04 3,746.04
03.01.08.02 LUMINARIA 750 MINICOMFORT T5 (2x14w) und 16.00 97.74 1,563.84 1,563.84
03.01.08.03 LUMINARIA 883 COMPACT und 121.00 106.28 12,859.88 12,859.88
03.01.08.04 LUMINARIA 784 COMPACT CRISTAL und 32.00 107.38 3,436.16 3,436.16
03.01.08.05 LUMINARIA FAGERHULT 64416 und 3.00 107.18 321.54 321.54
03.01.08.06 LUMINARIA AHORRADORA und 5.00 53.92 269.60 269.60
03.01.08.07 LUMINARIA EMERGENCIA und 39.00 536.02 20,904.78 20,904.78
03.01.09 POZO A TIERRA 3,466.08 0.00 0.00 0.00 0.00 0.00 3,466.08 0.00
03.01.09.01 POZO A TIERRA CON BENTONITA und 4.00 866.52 3,466.08 3,466.08
03.01.10 PRUEBAS ELECTRICAS 2,938.12 0.00 0.00 0.00 0.00 0.00 2,938.12 0.00
03.01.10.01 PRUEBAS DE AISLAMIENTO glb 1.00 662.53 662.53 662.53
03.01.10.02 PRUEBA ELÉCTRICA DE RESISTENCIA A TIERRA glb 1.00 662.53 662.53 662.53
03.01.10.03 PRUEBA ELECTRICA DE CONTINUIDAD glb 1.00 806.53 806.53 806.53
03.01.10.04 PRUEBA ELÉCTRICA DE CORRIENTE Y BALANCEO glb 1.00 806.53 806.53 806.53
03.02 COLISEO 208,970.80 0.00 0.00 0.00 0.00 0.00 89,809.59 119,161.21
03.02.01 ALIMENTADORES ELÉCTRICOS INTERIORES 29,281.24 0.00 0.00 0.00 0.00 0.00 29,281.24 0.00
03.02.01.01 ALIMENTADOR NH-80 1x4 mm2 m 2,959.84 5.58 16,515.91 16,515.91
03.02.01.02 ALIMENTADOR NH-80 1x2.5 mm2 m 2,450.16 5.21 12,765.33 12,765.33
03.02.02 CABLES DE COBRE 3,959.04 0.00 0.00 0.00 0.00 0.00 3,959.04 0.00
03.02.02.01 COBRE BLANDO 4 mm2 m 762.82 5.19 3,959.04 3,959.04
03.02.03 TUBERÍA 18,864.41 0.00 0.00 0.00 0.00 0.00 9,746.61 9,117.80
03.02.03.01 TUBERIA PVC-SAP 21 mm m 1,513.14 8.78 13,285.37 6,864.11 6,421.26
03.02.03.02 TUBERÍA CORRUGADA FLEXIBLE 21 mm m 717.10 7.78 5,579.04 2,882.50 2,696.54
03.02.04 TABLEROS 27,169.24 0.00 0.00 0.00 0.00 0.00 27,169.24 0.00
03.02.04.01 TABLERO DISTRIBUCION ST-5 und 1.00 5,170.21 5,170.21 5,170.21
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
03.02.04.02 TABLERO DISTRIBUCION ST-6 und 1.00 6,304.21 6,304.21 6,304.21
03.02.04.03 TABLERO DISTRIBUCION ST-7 und 1.00 9,390.61 9,390.61 9,390.61
03.02.04.04 TABLERO DISTRIBUCION ST-8 und 1.00 6,304.21 6,304.21 6,304.21
03.02.05 SALIDAS 28,595.74 0.00 0.00 0.00 0.00 0.00 19,126.44 9,469.30
03.02.05.01 SALIDA ILUMINACION PARA TECHO pto 219.00 51.17 11,206.23 7,493.94 3,712.29
03.02.05.02 SALIDA ILUMINACIÓN PARA LUMINARIA SUSPENDIDA pto 24.00 51.74 1,241.76 830.41 411.35
03.02.05.03 SALIDA TOMACORRIENTE EMERGENCIA pto 32.00 75.46 2,414.72 1,615.35 799.37
03.02.05.04 SALIDA TOMACORRIENTE DOBLE 0.30 M. pto 47.00 81.84 3,846.48 2,573.29 1,273.19
03.02.05.05 SALIDA TOMACORRIENTE DOBLE 1.10 M pto 6.00 81.84 491.04 328.50 162.54
03.02.05.06 SALIDA TOMACORRIENTE DOBLE A PRUEBA DE AGUA pto 22.00 129.84 2,856.48 1,911.45 945.03
03.02.05.07 SALIDA TOMACORRIENTE SECAMANOS 1.20 M pto 16.00 45.98 735.68 491.91 243.77
03.02.05.08 SALIDA TOMACORRIENTE SECAMANOS 0.70 M pto 4.00 45.98 183.92 122.98 60.94
03.02.05.09 SALIDA TOMACORRIENTE ACCESS POINT pto 1.00 75.46 75.46 50.48 24.98
03.02.05.10 SALIDA TERMA ELECTRICA pto 4.00 45.98 183.92 122.98 60.94
03.02.05.11 SALIDA TOMACORRIENTE REFRIGERADORA pto 3.00 76.23 228.69 152.99 75.70
03.02.05.12 SALIDA MARCADOR ELECTRÒNICO pto 2.00 48.44 96.88 64.86 32.02
03.02.05.13 SALIDA TOMACORRIENTE COMUNICACIONES, SONIDO pto 2.00 81.84 163.68 109.50 54.18
03.02.05.14 SALIDA TOMACORRIENTE CENTRAL DE ALARMA pto 1.00 45.98 45.98 30.74 15.24
03.02.05.15 SALIDA PARA SENSORES DE PRESENCIA pto 20.00 47.19 943.80 631.09 312.71
03.02.05.16 SALIDA PARA INTERRUPTOR SIMPLE pto 59.00 65.78 3,881.02 2,595.97 1,285.05
03.02.06 CAJAS DE PASE 1,485.66 0.00 0.00 0.00 0.00 0.00 527.02 958.64
03.02.06.01 CAJAS DE PASE CUADRADAS DE 97x97x45 mm und 29.00 45.42 1,317.18 467.23 849.95
03.02.06.02 CAJAS DE PASE REDONDA DE Ø 108x40 mm und 4.00 42.12 168.48 59.79 108.69
03.02.07 SENSORES DE PRESENCIA 12,235.20 0.00 0.00 0.00 0.00 0.00 0.00 12,235.20
03.02.07.01 SENSOR DE PARED und 8.00 611.76 4,894.08 4,894.08
03.02.07.02 SENSOR DE TECHO und 12.00 611.76 7,341.12 7,341.12
03.02.08 LUMINARIAS INTERIORES 80,976.07 0.00 0.00 0.00 0.00 0.00 0.00 80,976.07
03.02.08.01 LUMINARIA 750 MINICOMFORT T5 (4x14w) und 17.00 120.84 2,054.28 2,054.28
03.02.08.02 LUMINARIA 750 MINICOMFORT T5 (2x14w) und 8.00 97.74 781.92 781.92
03.02.08.03 LUMINARIA 883 COMPACT und 112.00 106.28 11,903.36 11,903.36
03.02.08.04 LUMINARIA 784 COMPACT CRISTAL und 6.00 107.38 644.28 644.28
03.02.08.05 LUMINARIA 1299 CILINDRO und 24.00 821.75 19,722.00 19,722.00
03.02.08.06 LUMINARIA AHORRADORA und 2.00 53.92 107.84 107.84
03.02.08.07 LUMINARIA EMERGENCIA und 32.00 536.02 17,152.64 17,152.64
03.02.08.08 LUMINARIA 1100 LUCENTE und 65.00 440.15 28,609.75 28,609.75
03.02.09 POZO PUESTA A TIERRA 3,466.08 0.00 0.00 0.00 0.00 0.00 0.00 3,466.08
03.02.09.01 POZO A TIERRA CON BENTONITA und 4.00 866.52 3,466.08 3,466.08
03.02.10 PRUEBAS ELECTRICAS 2,938.12 0.00 0.00 0.00 0.00 0.00 0.00 2,938.12
03.02.10.01 PRUEBAS DE AISLAMIENTO glb 1.00 662.53 662.53 662.53
03.02.10.02 PRUEBA ELÉCTRICA DE RESISTENCIA A TIERRA glb 1.00 662.53 662.53 662.53
03.02.10.03 PRUEBA ELECTRICA DE CONTINUIDAD glb 1.00 806.53 806.53 806.53
03.02.10.04 PRUEBA ELÉCTRICA DE CORRIENTE Y BALANCEO glb 1.00 806.53 806.53 806.53
03.03 OBRAS EXTERIORES 1,363,202.99 0.00 0.00 0.00 0.00 0.00 298,596.91 1,064,606.08
03.03.01 MOVIMIENTO DE TIERRAS 191,565.69 0.00 0.00 0.00 0.00 0.00 81,597.22 109,968.47
03.03.01.01 EXCAVACION DE ZANJA m3 892.89 41.97 37,474.59 11,658.76 25,815.83
03.03.01.02 EXCAVACIÓN PARA CIMIENTO DE POSTE m3 101.03 41.97 4,240.23 1,319.18 2,921.05
03.03.01.03 REFINE Y NIVELACION DEL FONDO DE ZANJA m 1,984.20 1.47 2,916.77 1,239.63 1,677.14
03.03.01.04 RELLENO Y COMPACTACION DE ZANJA m3 1,672.08 66.02 110,390.72 39,667.59 70,723.13
03.03.01.05 ELIMINACIÓN DE DESMONTE CON ACARREO m3 1,459.40 25.04 36,543.38 27,712.06 8,831.32
03.03.02 BUZONES 44,104.99 0.00 0.00 0.00 0.00 0.00 2,076.33 42,028.66
03.03.02.01 BUZÓN DE 0.7 m x 0.7 m x 0.8 m und 23.00 363.13 8,351.99 397.07 7,954.92
03.03.02.02 BUZÓN DE 0.5 m x 0.5 m x 0.8 m und 100.00 357.53 35,753.00 1,679.26 34,073.74
03.03.03 ALIMENTADORES ELÉCTRICOS EXTERIORES 167,226.98 0.00 0.00 0.00 0.00 0.00 167,226.98 0.00
03.03.03.01 ALIMENTADOR N2XOH 3x120 mm2 + 1x120 mm2 m 15.00 242.42 3,636.30 3,636.30
03.03.03.02 ALIMENTADOR N2XOH 3x25mm2 +1x25mm2 m 432.00 79.86 34,499.52 34,499.52
03.03.03.03 ALIMENTADOR N2XOH 3x10mm2 + 1x10mm2 m 626.00 54.08 33,854.08 33,854.08
03.03.03.04 ALIMENTADOR N2XOH 3x16mm2 +1x16mm2 m 736.00 64.04 47,133.44 47,133.44
03.03.03.05 ALIMENTADOR N2XOH 3x4mm2 + 1x4mm2 m 597.00 13.67 8,160.99 8,160.99
03.03.03.06 ALIMENTADOR N2XOH 3x2.5 mm2 + 1x2.5 mm2 m 1,325.00 21.44 28,408.00 28,408.00
03.03.03.07 ALIMENTADOR N2XOH 1x10 mm2 + 1x10 mm2 m 148.00 14.19 2,100.12 2,100.12
03.03.03.08 ALIMENTADOR N2XOH 1X6 mm2 + 1x6 mm2 m 61.50 9.07 557.81 557.81
03.03.03.09 ALIMENTADOR N2XOH 1X4 mm2 + 1x4 mm2 m 230.00 7.89 1,814.70 1,814.70
03.03.03.10 ALIMENTADOR N2XOH 1x2.5 mm2 + 1x2.5 mm2 m 1,022.00 6.91 7,062.02 7,062.02
03.03.04 ALIMENTADORES ELÉCTRICOS INTERIORES 1,169.12 0.00 0.00 0.00 0.00 0.00 1,169.12 0.00
03.03.04.01 ALIMENTADOR NH-80 1x2.5 mm2 m 224.40 5.21 1,169.12 1,169.12
03.03.05 CABLES DE COBRE 92,182.94 0.00 0.00 0.00 0.00 0.00 0.00 92,182.94
03.03.05.01 COBRE BLANDO 70 mm2 m 15.00 52.03 780.45 780.45
03.03.05.02 COBRE BLANDO 16 mm2 m 1,216.00 37.54 45,648.64 45,648.64
03.03.05.03 COBRE BLANDO 10 mm2 m 774.00 35.86 27,755.64 27,755.64
03.03.05.04 COBRE BLANDO 6 mm2 m 61.50 12.69 780.44 780.44
03.03.05.05 COBRE BLANDO 4 mm2 m 1,067.00 5.19 5,537.73 5,537.73
03.03.05.06 COBRE BLANDO 2.5 mm2 m 2,403.30 4.86 11,680.04 11,680.04
03.03.06 TUBERÍA 60,893.84 0.00 0.00 0.00 0.00 0.00 25,879.88 35,013.96
03.03.06.01 TUBERÍA PVC-SAP 88.5 mm m 15.00 38.19 572.85 243.46 329.39
03.03.06.02 TUBERIA PVC-SAP 42 mm m 1,794.00 15.89 28,506.66 12,115.33 16,391.33
03.03.06.03 TUBERIA PVC-SAP 21 mm m 3,623.50 8.78 31,814.33 13,521.09 18,293.24
03.03.07 TABLEROS 35,411.24 0.00 0.00 0.00 0.00 0.00 0.00 35,411.24
03.03.07.01 TABLERO GENERAL (TG) und 1.00 6,960.21 6,960.21 6,960.21
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
03.03.07.02 TABLERO DE DISTRIBUCIÓN ST-9 ST-10 ST-11 und 3.00 2,036.21 6,108.63 6,108.63
03.03.07.03 TABLERO DE DISTRIBUCIÓN ST-12 und 1.00 8,648.42 8,648.42 8,648.42
03.03.07.04 TABLERO DE DISTRIBUCIÓN ST-13 und 1.00 9,712.04 9,712.04 9,712.04
03.03.07.05 TABLERO DE DISTRIBUCIÓN ST-14 und 1.00 2,172.81 2,172.81 2,172.81
03.03.07.06 TABLERO DE DISTRIBUCIÓN ST-15 ST-16 ST-17 ST-18 und 1.00 1,809.13 1,809.13 1,809.13
03.03.08 SALIDAS 53,106.81 0.00 0.00 0.00 0.00 0.00 20,647.38 32,459.43
03.03.08.01 SALIDA ILUMINACION PARA TECHO pto 13.00 51.17 665.21 430.08 235.13
03.03.08.02 SALIDA ILUMINACIÓN EXTERIOR pto 67.00 379.77 25,444.59 2,756.89 22,687.70
03.03.08.03 SALIDA ILUMINACIÓN EXTERIOR ESCALERAS Y RAMPAS pto 331.00 74.23 24,570.13 15,890.64 8,679.49
03.03.08.04 SALIDA TOMACORRIENTE EMERGENCIA pto 1.00 75.46 75.46 48.80 26.66
03.03.08.05 SALIDA TOMACORRIENTE DOBLE 0.30 M. pto 12.00 81.84 982.08 635.20 346.88
03.03.08.06 SALIDA TOMACORRIENTE DOBLE A PRUEBA DE AGUA pto 7.00 129.84 908.88 588.00 320.88
03.03.08.07 SALIDA PARA INTERRUPTOR SIMPLE pto 7.00 65.78 460.46 297.77 162.69
03.03.09 LUMINARIAS INTERIORES 2,264.34 0.00 0.00 0.00 0.00 0.00 0.00 2,264.34
03.03.09.01 LUMINARIA 750 MINICOMFORT T5 (4x14w) und 6.00 120.84 725.04 725.04
03.03.09.02 LUMINARIA 883 COMPACT und 3.00 106.28 318.84 318.84
03.03.09.03 LUMINARIA 921 HYDRO T8 und 4.00 171.11 684.44 684.44
03.03.09.04 LUMINARIA EMERGENCIA und 1.00 536.02 536.02 536.02
03.03.10 LUMINARIAS EXTERIORES 164,839.53 0.00 0.00 0.00 0.00 0.00 0.00 164,839.53
03.03.10.01 LUMINARIAS 1511 TORCIA 150W und 64.00 537.26 34,384.64 34,384.64
03.03.10.02 LUMINARIAS 1511 TORCIA 70W und 3.00 537.26 1,611.78 1,611.78
03.03.10.03 LUMINARIA 1156 FORUM FM und 36.00 1,635.76 58,887.36 58,887.36
03.03.10.04 LUMINARIA 1158 INDIO 400W und 8.00 569.81 4,558.48 4,558.48
03.03.10.05 LUMINARIA 1158 INDIO 250W und 8.00 559.59 4,476.72 4,476.72
03.03.10.06 LUMINARIA 1616 MIMI und 331.00 184.05 60,920.55 60,920.55
03.03.11 ALUMBRADO PUBLICO 399,174.99 0.00 0.00 0.00 0.00 0.00 0.00 399,174.99
03.03.11.01 POSTE DE 4m METÁLICO und 46.00 741.01 34,086.46 34,086.46
03.03.11.02 BRAZO DE 0.6m METALICO und 21.00 908.06 19,069.26 19,069.26
03.03.11.03 POSTE DE 28 M METALICO und 4.00 75,432.34 301,729.36 301,729.36
03.03.11.04 POSTE DE 12m METÁLICO und 4.00 3,479.03 13,916.12 13,916.12
03.03.11.05 CIMIENTO PARA POSTE m3 101.30 299.84 30,373.79 30,373.79
03.03.12 POZO PUESTA A TIERRA 8,665.20 0.00 0.00 0.00 0.00 0.00 0.00 8,665.20
03.03.12.01 POZO A TIERRA CON BENTONITA und 10.00 866.52 8,665.20 8,665.20
03.03.13 MEDIA TENSIÓN 133,782.96 0.00 0.00 0.00 0.00 0.00 0.00 133,782.96
03.03.13.01 SUB-ESTACION ELECTRICA und 1.00 105,415.44 105,415.44 105,415.44
03.03.13.02 EXCAVACION DE ZANJA m3 60.65 41.97 2,545.48 2,545.48
03.03.13.03 REFINE Y NIVELACION DEL FONDO DE ZANJA m 88.00 1.47 129.36 129.36
03.03.13.04 RELLENO Y COMPACTACION DE ZANJA m3 60.65 66.02 4,004.11 4,004.11
03.03.13.05 ELIMINACIÓN DE DESMONTE CON ACARREO m3 10.55 25.04 264.17 264.17
03.03.13.06 BUZÓN DE 1 m x 1 m x 1.2 m und 5.00 951.60 4,758.00 4,758.00
03.03.13.07 EXCAVACIÓN MASIVA CON MÁQUINA m3 12.86 15.83 203.57 203.57
03.03.13.08 CONCRETO ARMADO m3 3.35 286.04 958.23 958.23
03.03.13.09 ARENA DE RÍO LAVADA m3 2.01 194.09 390.12 390.12
03.03.13.10 CABLE SUBTERRANEO 50 MM² N2XSY m 120.00 97.07 11,648.40 11,648.40
03.03.13.11 POZO A TIERRA CON BENTONITA und 4.00 866.52 3,466.08 3,466.08
03.03.14 PRUEBAS ELECTRICAS 8,814.36 0.00 0.00 0.00 0.00 0.00 0.00 8,814.36
03.03.14.01 PRUEBAS DE AISLAMIENTO glb 3.00 662.53 1,987.59 1,987.59
03.03.14.02 PRUEBA ELÉCTRICA DE RESISTENCIA A TIERRA glb 3.00 662.53 1,987.59 1,987.59
03.03.14.03 PRUEBA ELECTRICA DE CONTINUIDAD glb 3.00 806.53 2,419.59 2,419.59
03.03.14.04 PRUEBA ELÉCTRICA DE CORRIENTE Y BALANCEO glb 3.00 806.53 2,419.59 2,419.59
04 INSTALACIONES SANITARIAS 556,006.48 0.00 0.00 0.00 0.00 0.00 276,664.34 279,342.15
04.01 ESTADIO 118,582.10 0.00 0.00 0.00 0.00 0.00 32,371.91 86,210.19
04.01.01 INSTALACIONES INTERIORES DE DESAGÜE Y VENTILACIÓN 60,906.03 0.00 0.00 0.00 0.00 0.00 18,186.85 42,719.18
04.01.01.01 SALIDAS DE DESAGÜE Y VENTILACIÓN 31,451.38 0.00 0.00 0.00 0.00 0.00 10,396.44 21,054.94
04.01.01.01.01 SALIDA DE DESAGÜE PVC Ø 2" pto 116.00 83.15 9,645.40 3,188.34 6,457.06
04.01.01.01.02 SALIDA DE DESAGÜE PVC Ø 3" pto 59.00 86.61 5,109.99 1,689.14 3,420.85
04.01.01.01.03 SALIDA DE DESAGÜE PVC Ø 4" pto 72.00 90.87 6,542.64 2,162.71 4,379.93
04.01.01.01.04 SALIDA DE VENTILACIÓN PVC Ø 2" pto 109.00 93.15 10,153.35 3,356.25 6,797.10
04.01.01.02 REDES COLECTORAS 23,567.62 0.00 0.00 0.00 0.00 0.00 7,790.41 15,777.21
04.01.01.02.01 TUBERIA PVC CP Ø 2" m 522.89 19.52 10,206.81 3,373.92 6,832.89
04.01.01.02.02 TUBERIA PVC CP Ø 3" m 95.12 26.93 2,561.58 846.74 1,714.84
04.01.01.02.03 TUBERIA PVC CP Ø 4" m 346.24 31.19 10,799.23 3,569.75 7,229.48
04.01.01.03 ACCESORIOS SANITARIOS 1,750.40 0.00 0.00 0.00 0.00 0.00 0.00 1,750.40
04.01.01.03.01 SUMIDERO DE BRONCE Ø 2" und 37.00 7.20 266.40 266.40
04.01.01.03.02 SUMIDERO DE BRONCE Ø 3" und 25.00 13.00 325.00 325.00
04.01.01.03.03 REGISTRO DE BRONCE Ø 3" und 5.00 13.00 65.00 65.00
04.01.01.03.04 REGISTRO DE BRONCE Ø 4" und 32.00 22.00 704.00 704.00
04.01.01.03.05 TRAMPA DE GRASA und 4.00 50.00 200.00 200.00
04.01.01.03.06 REJILLA DE VENTILACIÓN und 38.00 5.00 190.00 190.00
04.01.01.04 PRUEBA HIDRAULICA 4,136.63 0.00 0.00 0.00 0.00 0.00 0.00 4,136.63
04.01.01.04.01 PRUEBA DE ESTANQUEDAD Y ESCORRENTIA PARA TUBERIA m 964.25 4.29 4,136.63 4,136.63
04.01.02 INSTALACIONES INTERIORES DE AGUA FRIA 41,640.13 0.00 0.00 0.00 0.00 0.00 9,616.66 32,023.47
04.01.02.01 SALIDA DE AGUA FRÍA 17,712.21 0.00 0.00 0.00 0.00 0.00 5,854.87 11,857.34
04.01.02.01.01 SALIDAS DE AGUA FRIA Ø 1/2" pto 99.00 89.73 8,883.27 2,936.41 5,946.86
04.01.02.01.02 SALIDAS DE AGUA FRIA Ø 1" pto 97.00 91.02 8,828.94 2,918.46 5,910.48
04.01.02.02 REDES DE DISTRIBUCIÓN DE AGUA FRIA 11,380.17 0.00 0.00 0.00 0.00 0.00 3,761.79 7,618.38
04.01.02.02.01 TUBERIA PVC CLASE 10 Ø 1/2" m 220.88 14.22 3,140.91 1,038.25 2,102.66
04.01.02.02.02 TUBERIA PVC CLASE 10 Ø 3/4" m 41.20 13.74 566.09 187.12 378.97
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
04.01.02.02.03 TUBERIA PVC CLASE 10 Ø 1" m 269.22 14.44 3,887.54 1,285.05 2,602.49
04.01.02.02.04 TUBERIA PVC CLASE 10 Ø 1 1/4" m 39.85 14.69 585.40 193.51 391.89
04.01.02.02.05 TUBERIA PVC CLASE 10 Ø 1 1/2" m 60.18 14.98 901.50 298.00 603.50
04.01.02.02.06 TUBERIA PVC CLASE 10 Ø 2" m 88.36 19.52 1,724.79 570.14 1,154.65
04.01.02.02.07 TUBERIA PVC CLASE 10 Ø 2 1/2" m 23.62 20.27 478.78 158.26 320.52
04.01.02.02.08 TUBERIA PVC CLASE 10 Ø 3" m 4.69 20.29 95.16 31.46 63.70
04.01.02.03 VALVULAS 7,951.11 0.00 0.00 0.00 0.00 0.00 0.00 7,951.11
04.01.02.03.01 VÁLVULAS COMPUERTA Ø 1/2" und 4.00 106.20 424.80 424.80
04.01.02.03.02 VÁLVULAS COMPUERTA Ø 3/4" und 4.00 127.67 510.68 510.68
04.01.02.03.03 VÁLVULAS COMPUERTA Ø 1" und 16.00 126.18 2,018.88 2,018.88
04.01.02.03.04 VÁLVULAS COMPUERTA Ø 1 1/4" und 7.00 179.05 1,253.35 1,253.35
04.01.02.03.05 VÁLVULAS COMPUERTA Ø 1 1/2" und 4.00 202.53 810.12 810.12
04.01.02.03.06 VÁLVULAS COMPUERTA Ø 2" und 12.00 244.44 2,933.28 2,933.28
04.01.02.04 PRUEBA HIDROSTATICA PARA TUBERIA 4,596.64 0.00 0.00 0.00 0.00 0.00 0.00 4,596.64
04.01.02.04.01 PRUEBA DE ESTANQUEDAD Y ESCORRENTIA PARA TUBERIA m 627.10 4.29 2,690.26 2,690.26
04.01.02.04.02 PRUEBA DE DESINFECCIÓN Y LAVADO DE TUBERIAS m 627.10 3.04 1,906.38 1,906.38
04.01.03 INSTALACIONES INTERIORES DE AGUA CALIENTE 16,035.94 0.00 0.00 0.00 0.00 0.00 4,568.40 11,467.54
04.01.03.01 SALIDA DE AGUA CALIENTE 11,703.00 0.00 0.00 0.00 0.00 0.00 3,868.49 7,834.51
04.01.03.01.01 SALIDAS DE AGUA CALIENTE Ø 1/2" pto 30.00 390.10 11,703.00 3,868.49 7,834.51
04.01.03.02 REDES DE DISTRIBUCIÓN DE AGUA CALIENTE 2,117.37 0.00 0.00 0.00 0.00 0.00 699.91 1,417.46
04.01.03.02.01 TUBERIA CPVC Ø 1/2" m 72.44 16.90 1,224.24 404.68 819.56
04.01.03.02.02 TUBERIA CPVC Ø 3/4" m 9.62 18.35 176.53 58.35 118.18
04.01.03.02.03 TUBERIA CPVC Ø 1" m 28.65 21.55 617.41 204.09 413.32
04.01.03.02.04 TUBERIA CPVC Ø 1 1/4" m 4.55 21.80 99.19 32.79 66.40
04.01.03.03 EQUIPOS 2,215.57 0.00 0.00 0.00 0.00 0.00 0.00 2,215.57
04.01.03.03.01 CALENTADOR VERTICAL 15L und 1.00 65.00 65.00 65.00
04.01.03.03.02 CALENTADOR VERTICAL 50L und 2.00 691.27 1,382.54 1,382.54
04.01.03.03.03 CALENTADOR VERTICAL 80L und 1.00 768.03 768.03 768.03
04.02 COLISEO 101,759.22 0.00 0.00 0.00 0.00 0.00 27,295.90 74,463.32
04.02.01 INSTALACIONES INTERIORES DE DESAGÜE Y VENTILACIÓN 50,307.74 0.00 0.00 0.00 0.00 0.00 15,089.21 35,218.53
04.02.01.01 SALIDAS DE DESAGÜE Y VENTILACIÓN 28,477.14 0.00 0.00 0.00 0.00 0.00 9,413.28 19,063.86
04.02.01.01.01 SALIDA DE DESAGÜE PVC Ø 2" pto 96.00 83.15 7,982.40 2,638.63 5,343.77
04.02.01.01.02 SALIDA DE DESAGÜE PVC Ø 3" pto 58.00 86.61 5,023.38 1,660.51 3,362.87
04.02.01.01.03 SALIDA DE DESAGÜE PVC Ø 4" pto 78.00 90.87 7,087.86 2,342.93 4,744.93
04.02.01.01.04 SALIDA DE VENTILACIÓN PVC Ø 2" pto 90.00 93.15 8,383.50 2,771.21 5,612.29
04.02.01.02 REDES COLECTORAS 17,170.87 0.00 0.00 0.00 0.00 0.00 5,675.93 11,494.94
04.02.01.02.01 TUBERIA PVC CP Ø 2" m 483.59 19.52 9,439.68 3,120.34 6,319.34
04.02.01.02.02 TUBERIA PVC CP Ø 3" m 80.80 26.93 2,175.94 719.27 1,456.67
04.02.01.02.03 TUBERIA PVC CP Ø 4" m 178.11 31.19 5,555.25 1,836.32 3,718.93
04.02.01.03 ACCESORIOS SANITARIOS 1,474.40 0.00 0.00 0.00 0.00 0.00 0.00 1,474.40
04.02.01.03.01 SUMIDERO DE BRONCE Ø 2" und 57.00 7.20 410.40 410.40
04.02.01.03.02 SUMIDERO DE BRONCE Ø 3" und 15.00 13.00 195.00 195.00
04.02.01.03.03 REGISTRO DE BRONCE Ø 2" und 5.00 7.20 36.00 36.00
04.02.01.03.04 REGISTRO DE BRONCE Ø 4" und 29.00 22.00 638.00 638.00
04.02.01.03.05 REJILLA DE VENTILACIÓN und 39.00 5.00 195.00 195.00
04.02.01.04 PRUEBA HIDRAULICA 3,185.33 0.00 0.00 0.00 0.00 0.00 0.00 3,185.33
04.02.01.04.01 PRUEBA DE ESTANQUEDAD Y ESCORRENTIA PARA TUBERIA m 742.50 4.29 3,185.33 3,185.33
04.02.02 INSTALACIONES INTERIORES DE AGUA FRIA 36,934.98 0.00 0.00 0.00 0.00 0.00 8,068.50 28,866.48
04.02.02.01 SALIDA DE AGUA FRÍA 14,912.52 0.00 0.00 0.00 0.00 0.00 4,929.41 9,983.11
04.02.02.01.01 SALIDAS DE AGUA FRIA Ø 1/2" pto 82.00 89.73 7,357.86 2,432.18 4,925.68
04.02.02.01.02 SALIDAS DE AGUA FRIA Ø 1" pto 83.00 91.02 7,554.66 2,497.23 5,057.43
04.02.02.02 REDES DE DISTRIBUCIÓN DE AGUA FRIA 9,496.42 0.00 0.00 0.00 0.00 0.00 3,139.09 6,357.33
04.02.02.02.01 TUBERIA PVC CLASE 10 Ø 1/2" m 170.03 14.22 2,417.83 799.23 1,618.60
04.02.02.02.02 TUBERIA PVC CLASE 10 Ø 3/4" m 91.69 13.74 1,259.82 416.44 843.38
04.02.02.02.03 TUBERIA PVC CLASE 10 Ø 1" m 217.64 14.44 3,142.72 1,038.84 2,103.88
04.02.02.02.04 TUBERIA PVC CLASE 10 Ø 1 1/4" m 40.00 14.69 587.60 194.23 393.37
04.02.02.02.05 TUBERIA PVC CLASE 10 Ø 1 1/2" m 60.58 14.98 907.49 299.98 607.51
04.02.02.02.06 TUBERIA PVC CLASE 10 Ø 2" m 60.50 19.52 1,180.96 390.37 790.59
04.02.02.03 VALVULAS 7,831.61 0.00 0.00 0.00 0.00 0.00 0.00 7,831.61
04.02.02.03.01 VÁLVULAS COMPUERTA Ø 1/2" und 5.00 106.20 531.00 531.00
04.02.02.03.02 VÁLVULAS COMPUERTA Ø 3/4" und 13.00 127.67 1,659.71 1,659.71
04.02.02.03.03 VÁLVULAS COMPUERTA Ø 1" und 13.00 126.18 1,640.34 1,640.34
04.02.02.03.04 VÁLVULAS COMPUERTA Ø 1 1/4" und 6.00 179.05 1,074.30 1,074.30
04.02.02.03.05 VÁLVULAS COMPUERTA Ø 1 1/2" und 6.00 202.53 1,215.18 1,215.18
04.02.02.03.06 VÁLVULAS COMPUERTA Ø 2" und 7.00 244.44 1,711.08 1,711.08
04.02.02.04 PRUEBA HIDROSTATICA PARA TUBERIA 4,694.43 0.00 0.00 0.00 0.00 0.00 0.00 4,694.43
04.02.02.04.01 PRUEBA DE ESTANQUEDAD Y ESCORRENTIA PARA TUBERIA m 640.44 4.29 2,747.49 2,747.49
04.02.02.04.02 PRUEBA DE DESINFECCIÓN Y LAVADO DE TUBERIAS m 640.44 3.04 1,946.94 1,946.94
04.02.03 INSTALACIONES INTERIORES DE AGUA CALIENTE 14,516.50 0.00 0.00 0.00 0.00 0.00 4,138.19 10,378.31
04.02.03.01 SALIDA DE AGUA CALIENTE 11,703.00 0.00 0.00 0.00 0.00 0.00 3,868.49 7,834.51
04.02.03.01.01 SALIDAS DE AGUA CALIENTE Ø 1/2" pto 30.00 390.10 11,703.00 3,868.49 7,834.51
04.02.03.02 REDES DE DISTRIBUCIÓN DE AGUA CALIENTE 815.90 0.00 0.00 0.00 0.00 0.00 269.70 546.20
04.02.03.02.01 TUBERIA CPVC Ø 1/2" m 30.80 16.90 520.52 172.06 348.46
04.02.03.02.02 TUBERIA CPVC Ø 3/4" m 3.32 18.35 60.92 20.14 40.78
04.02.03.02.03 TUBERIA CPVC Ø 1" m 10.88 21.55 234.46 77.50 156.96
04.02.03.03 EQUIPOS 1,997.60 0.00 0.00 0.00 0.00 0.00 0.00 1,997.60
04.02.03.03.01 CALENTADOR VERTICAL 30L und 4.00 499.40 1,997.60 1,997.60
04.03 OBRAS EXTERIORES 335,665.16 0.00 0.00 0.00 0.00 0.00 216,996.53 118,668.64
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
04.03.01 REDES EXTERIORES COLECTORAS DE DESAGUE 147,922.33 0.00 0.00 0.00 0.00 0.00 107,381.34 40,540.99
04.03.01.01 EXCAVACIÓN 34,920.72 0.00 0.00 0.00 0.00 0.00 23,377.48 11,543.24
04.03.01.01.01 EXCAVACION DE ZANJA HASTA 1.00m m3 187.63 41.97 7,874.83 5,271.76 2,603.07
04.03.01.01.02 EXCAVACION DE ZANJA HASTA 1.50m m3 95.51 41.97 4,008.55 2,683.50 1,325.05
04.03.01.01.03 EXCAVACION DE ZANJA HASTA 2.00m m3 215.47 41.97 9,043.28 6,053.97 2,989.31
04.03.01.01.04 EXCAVACION DE ZANJA HASTA 3.00m m3 333.43 41.97 13,994.06 9,368.25 4,625.81
04.03.01.02 RELLENO Y COMPACTACIÓN DE ZANJA 46,310.27 0.00 0.00 0.00 0.00 0.00 28,444.63 17,865.64
04.03.01.02.01 REFINE Y NIVELACIÓN DE ZANJA PARA TUBERÍA m3 692.44 1.84 1,274.09 852.93 421.16
04.03.01.02.02 RELLENO COMPACTADO DE ZANJA PARA TUBERÍA m3 1,000.79 30.63 30,654.20 19,556.52 11,097.68
04.03.01.02.03 CAMA DE APOYO CON MATERIA DE PRESTAMO E=0.10M m 692.44 20.77 14,381.98 8,035.18 6,346.80
04.03.01.03 TUBERIAS DE RECOLECCIÓN 24,690.35 0.00 0.00 0.00 0.00 0.00 16,528.81 8,161.54
04.03.01.03.01 TUBERIA PVC CP Ø 4" m 128.09 31.19 3,995.13 2,674.52 1,320.61
04.03.01.03.02 TUBERIA PVC CP Ø 5" m 290.75 32.52 9,455.19 6,329.72 3,125.47
04.03.01.03.03 TUBERIA PVC CP Ø 6" m 134.67 36.16 4,869.67 3,259.97 1,609.70
04.03.01.03.04 TUBERIA PVC CP Ø 8" m 129.52 44.94 5,820.63 3,896.59 1,924.04
04.03.01.03.05 TUBERIA PVC CP Ø 10" m 9.41 58.42 549.73 368.01 181.72
04.03.01.04 CÁMARAS DE INSPECCIÓN 39,030.42 0.00 0.00 0.00 0.00 0.00 39,030.42 0.00
04.03.01.04.01 CAJA DE REGISTRO DE 0.25x0.50 m und 11.00 476.77 5,244.47 5,244.47
04.03.01.04.02 CAJA DE REGISTRO DE 0.30x0.60 m und 20.00 476.77 9,535.40 9,535.40
04.03.01.04.03 CAJA DE REGISTRO DE 0.45x0.60 m und 22.00 476.77 10,488.94 10,488.94
04.03.01.04.04 CAJA DE REGISTRO DE 0.60x0.60 m und 6.00 476.77 2,860.62 2,860.62
04.03.01.04.05 BUZON HASTA H=1.50m und 2.00 1,249.12 2,498.24 2,498.24
04.03.01.04.06 BUZON HASTA H=2.00m und 2.00 1,403.20 2,806.40 2,806.40
04.03.01.04.07 BUZON HASTA H=3.50m und 3.00 1,865.45 5,596.35 5,596.35
04.03.01.05 PRUEBA HIDRAULICA 2,970.57 0.00 0.00 0.00 0.00 0.00 0.00 2,970.57
04.03.01.05.01 PRUEBA DE ESTANQUEDAD Y ESCORRENTIA PARA TUBERIA m 692.44 4.29 2,970.57 2,970.57
04.03.02 REDES EXTERIORES DE AGUA POTABLE 48,427.39 0.00 0.00 0.00 0.00 0.00 34,179.21 14,248.18
04.03.02.01 EXCAVACIÓN 8,662.25 0.00 0.00 0.00 0.00 0.00 7,714.82 947.43
04.03.02.01.01 EXCAVACION DE ZANJA HASTA 0.60m m3 235.90 36.72 8,662.25 7,714.82 947.43
04.03.02.02 RELLENO Y COMPACTACIÓN DE ZANJA 22,342.81 0.00 0.00 0.00 0.00 0.00 13,213.08 9,129.73
04.03.02.02.01 REFINE Y NIVELACIÓN DE ZANJA PARA TUBERÍA m3 655.29 1.84 1,205.73 807.17 398.56
04.03.02.02.02 RELLENO COMPACTADO DE ZANJA PARA TUBERÍA m3 245.73 30.63 7,526.71 4,801.83 2,724.88
04.03.02.02.03 CAMA DE APOYO CON MATERIA DE PRESTAMO E=0.10M m 655.29 20.77 13,610.37 7,604.08 6,006.29
04.03.02.03 TUBERIAS DE DISTRIBUCIÓN 12,618.17 0.00 0.00 0.00 0.00 0.00 8,447.15 4,171.02
04.03.02.03.01 TUBERIA PVC CLASE 10 Ø 3/4" m 62.91 13.74 864.38 578.65 285.73
04.03.02.03.02 TUBERIA PVC CLASE 10 Ø 1 1/2" m 15.01 14.98 224.85 150.52 74.33
04.03.02.03.03 TUBERIA PVC CLASE 10 Ø 2" m 238.32 19.52 4,652.01 3,114.26 1,537.75
04.03.02.03.04 TUBERIA PVC CLASE 10 Ø 2 1/2" m 241.33 20.27 4,891.76 3,274.76 1,617.00
04.03.02.03.05 TUBERIA PVC CLASE 10 Ø 3" m 97.84 20.29 1,985.17 1,328.96 656.21
04.03.02.04 PRUEBA HIDROSTATICA PARA TUBERIA 4,804.16 0.00 0.00 0.00 0.00 0.00 4,804.16 0.00
04.03.02.04.01 PRUEBA DE ESTANQUEDAD Y ESCORRENTIA PARA TUBERIA m 655.41 4.29 2,811.71 2,811.71
04.03.02.04.02 PRUEBA DE DESINFECCIÓN Y LAVADO DE TUBERIAS m 655.41 3.04 1,992.45 1,992.45
04.03.03 SISTEMA DE AGUA CONTRA INCENDIO 136,665.28 0.00 0.00 0.00 0.00 0.00 74,767.07 61,898.22
04.03.03.01 EXCAVACIÓN 5,777.59 0.00 0.00 0.00 0.00 0.00 3,787.54 1,990.06
04.03.03.01.01 EXCAVACION DE ZANJA HASTA 0.40m m3 137.66 41.97 5,777.59 3,787.54 1,990.06
04.03.03.02 RELLENO Y COMPACTACIÓN DE ZANJA 16,922.20 0.00 0.00 0.00 0.00 0.00 11,836.32 5,085.88
04.03.03.02.01 REFINE Y NIVELACIÓN DE ZANJA PARA TUBERÍA m3 573.60 1.84 1,055.42 691.89 363.53
04.03.03.02.02 RELLENO COMPACTADO DE ZANJA PARA TUBERÍA m3 129.06 30.63 3,953.11 2,655.49 1,297.61
04.03.03.02.03 CAMA DE APOYO CON MATERIA DE PRESTAMO E=0.10M m 573.60 20.77 11,913.67 8,488.94 3,424.74
04.03.03.03 TUBERIAS DE DISTRIBUCIÓN 90,218.45 0.00 0.00 0.00 0.00 0.00 59,143.21 31,075.24
04.03.03.03.01 TUBERIA DE ACERO SHEDULE 40 DE Ø 2 1/2" m 123.15 116.44 14,339.59 9,400.40 4,939.19
04.03.03.03.02 TUBERIA DE ACERO SHEDULE 40 DE Ø 4" m 204.20 158.13 32,290.15 21,167.98 11,122.16
04.03.03.03.03 TUBERIA DE ACERO SHEDULE 40 DE Ø 5" m 246.25 177.01 43,588.71 28,574.83 15,013.89
04.03.03.04 VÁLVULAS 17,093.28 0.00 0.00 0.00 0.00 0.00 0.00 17,093.28
04.03.03.04.01 GABINETE CONTRA INCENDIOS (MANG. 30 M) und 8.00 1,065.71 8,525.68 8,525.68
04.03.03.04.02 VALVULA ANGULAR DE 2 1/2" und 8.00 364.39 2,915.12 2,915.12
04.03.03.04.03 VALVULA CHECK DE 4" und 4.00 858.22 3,432.88 3,432.88
04.03.03.04.04 VALVULA SIAMESA 4"x2 1/2" und 8.00 277.45 2,219.60 2,219.60
04.03.03.05 PRUEBA HIDROSTATICA PARA TUBERIA 6,653.76 0.00 0.00 0.00 0.00 0.00 0.00 6,653.76
04.03.03.05.01 PRUEBA HIDRAULICA EN RED DE AGUA CONTRA INCENDIOS m 573.60 11.60 6,653.76 6,653.76
04.03.04 INSTALACIONES INTERIORES DE DESAGÜE Y VENTILACIÓN 1,389.79 0.00 0.00 0.00 0.00 0.00 416.84 972.95
04.03.04.01 SALIDAS DE DESAGÜE Y VENTILACIÓN 801.51 0.00 0.00 0.00 0.00 0.00 264.94 536.57
04.03.04.01.01 SALIDA DE DESAGÜE PVC Ø 2" pto 3.00 83.15 249.45 82.46 166.99
04.03.04.01.02 SALIDA DE DESAGÜE PVC Ø 4" pto 3.00 90.87 272.61 90.11 182.50
04.03.04.01.03 SALIDA DE VENTILACIÓN PVC Ø 2" pto 3.00 93.15 279.45 92.37 187.08
04.03.04.02 REDES DE DESAGUE Y VENTILACIÓN 459.55 0.00 0.00 0.00 0.00 0.00 151.90 307.65
04.03.04.02.01 TUBERIA PVC CP Ø 2" m 4.56 19.52 89.01 29.42 59.59
04.03.04.02.02 TUBERIA PVC CP Ø 4" m 11.88 31.19 370.54 122.48 248.06
04.03.04.03 ACCESORIOS SANITARIOS 58.20 0.00 0.00 0.00 0.00 0.00 0.00 58.20
04.03.04.03.01 SUMIDERO DE BRONCE Ø 2" und 3.00 7.20 21.60 21.60
04.03.04.03.02 REGISTRO DE BRONCE Ø 2" und 3.00 7.20 21.60 21.60
04.03.04.03.03 REJILLA DE VENTILACIÓN und 3.00 5.00 15.00 15.00
04.03.04.04 PRUEBA HIDRAULICA 70.53 0.00 0.00 0.00 0.00 0.00 0.00 70.53
04.03.04.04.01 PRUEBA DE ESTANQUEDAD Y ESCORRENTIA PARA TUBERIA m 16.44 4.29 70.53 70.53
04.03.05 INSTALACIONES INTERIORES DE AGUA FRIA 1,260.37 0.00 0.00 0.00 0.00 0.00 252.07 1,008.30
04.03.05.01 SALIDA DE AGUA FRÍA 542.25 0.00 0.00 0.00 0.00 0.00 179.24 363.01
04.03.05.01.01 SALIDAS DE AGUA FRIA Ø 1/2" pto 3.00 89.73 269.19 88.98 180.21
04.03.05.01.02 SALIDAS DE AGUA FRIA Ø 1" pto 3.00 91.02 273.06 90.26 182.80
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
04.03.05.02 REDES DE AGUA FRIA 220.32 0.00 0.00 0.00 0.00 0.00 72.83 147.49
04.03.05.02.01 TUBERIA PVC CLASE 10 Ø 1/2" m 10.72 14.22 152.44 50.39 102.05
04.03.05.02.02 TUBERIA PVC CLASE 10 Ø 3/4" m 4.94 13.74 67.88 22.44 45.44
04.03.05.03 VALVULAS 383.01 0.00 0.00 0.00 0.00 0.00 0.00 383.01
04.03.05.03.01 VÁLVULAS COMPUERTA Ø 3/4" und 3.00 127.67 383.01 383.01
04.03.05.04 PRUEBA HIDROSTATICA PARA TUBERIA 114.79 0.00 0.00 0.00 0.00 0.00 0.00 114.79
04.03.05.04.01 PRUEBA DE ESTANQUEDAD Y ESCORRENTIA PARA TUBERIA m 15.66 4.29 67.18 67.18
04.03.05.04.02 PRUEBA DE DESINFECCIÓN Y LAVADO DE TUBERIAS m 15.66 3.04 47.61 47.61
05 INSTALACIONES ELECTROMECÁNICAS 86,053.92 0.00 0.00 824.74 0.00 0.00 42,614.59 42,614.59
05.01 OBRAS EXTERIORES 86,053.92 0.00 0.00 824.74 0.00 0.00 42,614.59 42,614.59
05.01.01 MOVIMIENTO DE TIERRAS 1,099.18 0.00 0.00 0.00 0.00 0.00 549.59 549.59
05.01.01.01 EXCAVACION DE ZANJA m3 9.90 41.97 415.50 207.75 207.75
05.01.01.02 REFINE Y NIVELACION DEL FONDO DE ZANJA m 20.00 1.47 29.40 14.70 14.70
05.01.01.03 RELLENO Y COMPACTACION DE ZANJA m3 9.00 66.02 594.18 297.09 297.09
05.01.01.04 ELIMINACIÓN DE DESMONTE CON ACARREO m3 2.40 25.04 60.10 30.05 30.05
05.01.02 ALIMENTADORES ELÉCTRICOS INTERIORES 2,470.89 0.00 0.00 0.00 0.00 0.00 1,235.45 1,235.45
05.01.02.01 ALIMENTADOR NH-80 1x25 mm2 m 16.80 34.68 582.62 291.31 291.31
05.01.02.02 ALIMENTADOR NH-80 1x4 mm2 m 338.40 5.58 1,888.27 944.14 944.14
05.01.03 CABLES DE COBRE 616.99 0.00 0.00 0.00 0.00 0.00 308.50 308.50
05.01.03.01 COBRE BLANDO 16 mm2 m 4.20 37.54 157.67 78.84 78.84
05.01.03.02 COBRE BLANDO 4 mm2 m 88.50 5.19 459.32 229.66 229.66
05.01.04 TUBERÍAS 879.68 0.00 0.00 327.13 0.00 0.00 276.28 276.28
05.01.04.01 TUBERIA PVC-SAP 48 mm m 4.20 24.44 102.65 38.17 32.24 32.24
05.01.04.02 TUBERIA PVC-SAP 21 mm m 88.50 8.78 777.03 288.96 244.04 244.04
05.01.05 SALIDAS 1,338.10 0.00 0.00 497.61 0.00 0.00 420.25 420.25
05.01.05.01 SALIDA DE FUERZA BOMBAS pto 10.00 133.81 1,338.10 497.61 420.25 420.25
05.01.06 EQUIPOS 61,041.33 0.00 0.00 0.00 0.00 0.00 30,520.67 30,520.67
05.01.06.01 ELECTROBOMBA PRINCIPAL CONTRA INCENDIOS POTENCIA 45HP ADTund 62.03 m 1.00 28,470.82 28,470.82 14,235.41 14,235.41
05.01.06.02 ELECTROBOMBA JOCKEY CONTRA INCENDIOS POTENCIA 3HP ADT 73.04 undm 1.00 2,150.29 2,150.29 1,075.15 1,075.15
05.01.06.03 ELECTROBOMBA EJE VERTICAL POTENCIA 3.0HP V VARIABLE Y P CTE und
Q 6.38 l/s LPS 2.00
ADT 21.71m
3,633.78 7,267.56 3,633.78 3,633.78
05.01.06.04 ELECTROBOMBA EJE VERTICAL POTENCIA 4.5HP V VARIABLE Y P CTEund
Q 7.30 l/s LPS2.00
ADT 25.31m
4,607.78 9,215.56 4,607.78 4,607.78
05.01.06.05 ELECTROBOMBA SUMERGIBLE 1.14PS, HDT 3.5m, P 1.5HP und 2.00 1,963.68 3,927.36 1,963.68 1,963.68
05.01.06.06 ELECTROBOMBA SUMERGIBLE 19.9LPS, HDT 5.7m, P 2.5HP und 2.00 5,004.87 10,009.74 5,004.87 5,004.87
05.01.07 PUESTA EN MARCHA 18,607.75 0.00 0.00 0.00 0.00 0.00 9,303.88 9,303.88
05.01.07.01 SISTEMA DE BOMBEO CONTRA INCENDIOS glb 1.00 3,721.55 3,721.55 1,860.78 1,860.78
05.01.07.02 SISTEMA DE BOMBEO PARA AGUA FRIA glb 2.00 3,721.55 7,443.10 3,721.55 3,721.55
05.01.07.03 SISTEMA DE BOMBEO PARA LIMPIA DE CISTERNA Y ELIMACIÓN DE RESIDUOS
glb SÓLIDOS
2.00 3,721.55 7,443.10 3,721.55 3,721.55
06 INSTALACIONES ESPECIALES 271,095.28 0.00 0.00 0.00 0.00 0.00 144,516.11 126,579.17
06.01 ESTADIO 147,560.40 0.00 0.00 0.00 0.00 0.00 77,640.04 69,920.36
06.01.01 BUZONES 4,230.32 0.00 0.00 0.00 0.00 0.00 2,115.16 2,115.16
06.01.01.01 BUZÓN DE 0.25 x 0.25 x 0.5 m und 4.00 1,057.58 4,230.32 2,115.16 2,115.16
06.01.02 CABLEADO TELECOMUNICACIONES 35,042.96 0.00 0.00 0.00 0.00 0.00 17,521.48 17,521.48
06.01.02.01 CABLE F/UTP CAT.6 LSZH m 379.20 5.92 2,244.86 1,122.43 1,122.43
06.01.02.02 COBRE BLANDO 1x1.5 mm2 m 392.10 34.19 13,405.90 6,702.95 6,702.95
06.01.02.03 CABLE BAJA IMPEDANCIA m 565.70 34.28 19,392.20 9,696.10 9,696.10
06.01.03 TUBERIAS TELECOMUNICACIONES 13,869.28 0.00 0.00 0.00 0.00 0.00 9,513.46 4,355.82
06.01.03.01 TUBERIA PVC-SAP 42 mm m 379.20 15.89 6,025.49 4,133.11 1,892.38
06.01.03.02 TUBERIA PVC-SAP 21 mm m 392.10 8.78 3,442.64 2,361.44 1,081.21
06.01.03.03 TUBERÍA CORRUGADA FLEXIBLE 21 mm m 565.70 7.78 4,401.15 3,018.92 1,382.24
06.01.04 SALIDAS 6,889.49 0.00 0.00 0.00 0.00 0.00 4,725.77 2,163.73
06.01.04.01 SALIDA PARA DATOS Y TELEFONOS pto 7.00 146.96 1,028.72 705.64 323.08
06.01.04.02 SALIDA PARA DATOS SIMPLE pto 4.00 135.96 543.84 373.04 170.80
06.01.04.03 SALIDA PARA SENSORES DE HUMO pto 41.00 81.65 3,347.65 2,296.28 1,051.37
06.01.04.04 SALIDA PARA PULSADOR pto 12.00 57.25 687.00 471.24 215.76
06.01.04.05 SALIDA PARA LUCES ESTROBOSCÓPICAS pto 12.00 75.35 904.20 620.23 283.98
06.01.04.06 SALIDA PARA PARLANTES pto 8.00 47.26 378.08 259.34 118.74
06.01.05 CAJAS DE PASE 458.28 0.00 0.00 0.00 0.00 0.00 229.14 229.14
06.01.05.01 CAJAS DE PASE CUADRADAS DE 243x180x70 mm und 8.00 52.02 416.16 208.08 208.08
06.01.05.02 CAJAS DE PASE REDONDA DE Ø 108x40 mm und 1.00 42.12 42.12 21.06 21.06
06.01.06 EQUIPOS 87,070.07 0.00 0.00 0.00 0.00 0.00 43,535.04 43,535.04
06.01.06.01 CENTRAL DE VOZ Y DATOS und 1.00 6,426.56 6,426.56 3,213.28 3,213.28
06.01.06.02 ACCESS POINT und 4.00 593.73 2,374.92 1,187.46 1,187.46
06.01.06.03 CENTRAL DE ALARMA und 2.00 2,593.72 5,187.44 2,593.72 2,593.72
06.01.06.04 DETECTOR DE HUMO und 41.00 175.00 7,175.00 3,587.50 3,587.50
06.01.06.05 PULSADOR und 12.00 195.00 2,340.00 1,170.00 1,170.00
06.01.06.06 LUCES ESTROBOSCÓPICAS und 12.00 220.00 2,640.00 1,320.00 1,320.00
06.01.06.07 AMPLIFICADOR und 4.00 5,282.43 21,129.72 10,564.86 10,564.86
06.01.06.08 PARLANTE 60 WRMS und 8.00 4,950.00 39,600.00 19,800.00 19,800.00
06.01.06.09 MICROFONO und 1.00 196.43 196.43 98.22 98.22
06.02 COLISEO 92,430.17 0.00 0.00 0.00 0.00 0.00 51,323.72 41,106.46
06.02.01 CABLEADO TELECOMUNICACIONES 21,383.52 0.00 0.00 0.00 0.00 0.00 10,691.76 10,691.76
06.02.01.01 CABLE F/UTP CAT.6 LSZH m 195.32 5.92 1,156.29 578.15 578.15
06.02.01.02 COBRE BLANDO 1x1.5 mm2 m 259.40 34.19 8,868.89 4,434.45 4,434.45
06.02.01.03 CABLE BAJA IMPEDANCIA m 331.34 34.28 11,358.34 5,679.17 5,679.17
06.02.02 TUBERIAS TELECOMUNICACIONES 7,958.99 0.00 0.00 0.00 0.00 0.00 6,939.24 1,019.75
06.02.02.01 TUBERIA PVC-SAP 42 mm m 195.32 15.89 3,103.63 2,705.98 397.66
06.02.02.02 TUBERIA PVC-SAP 21 mm m 259.40 8.78 2,277.53 1,985.72 291.81
06.02.02.03 TUBERÍA CORRUGADA FLEXIBLE 21 mm m 331.34 7.78 2,577.83 2,247.55 330.29
CRONOGRAMA VALORIZADO
PROY: “CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA”
FECHA : 01/04/2019
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7
Item Descripción Und. Metrado Precio S/. Parcial S/.
PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL PARCIAL
CREACIÓN DEL COMPLEJO POLIDEPORTIVO MUNICIPAL DE HUAYCAN, DISTRITO DE ATE - LIMA - LIMA 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
06.02.03 SALIDAS 5,778.51 0.00 0.00 0.00 0.00 0.00 5,038.14 740.37
06.02.03.01 SALIDA PARA DATOS Y TELEFONOS pto 6.00 146.96 881.76 768.79 112.98
06.02.03.02 SALIDA PARA DATOS SIMPLE pto 1.00 135.96 135.96 118.54 17.42
06.02.03.03 SALIDA PARA SENSORES DE HUMO pto 43.00 81.65 3,510.95 3,061.11 449.84
06.02.03.04 SALIDA PARA PULSADOR pto 8.00 57.25 458.00 399.32 58.68
06.02.03.05 SALIDA PARA LUCES ESTROBOSCÓPICAS pto 8.00 75.35 602.80 525.57 77.24
06.02.03.06 SALIDA PARA PARLANTES pto 4.00 47.26 189.04 164.82 24.22
06.02.04 CAJAS DE PASE 676.26 0.00 0.00 0.00 0.00 0.00 338.13 338.13
06.02.04.01 CAJAS DE PASE CUADRADAS DE 243x180x70 mm und 13.00 52.02 676.26 338.13 338.13
06.02.05 EQUIPOS 56,632.89 0.00 0.00 0.00 0.00 0.00 28,316.45 28,316.45
06.02.05.01 CENTRAL DE VOZ Y DATOS und 1.00 6,426.56 6,426.56 3,213.28 3,213.28
06.02.05.02 ACCESS POINT und 1.00 593.73 593.73 296.87 296.87
06.02.05.03 CENTRAL DE ALARMA und 1.00 2,593.72 2,593.72 1,296.86 1,296.86
06.02.05.04 DETECTOR DE HUMO und 43.00 175.00 7,525.00 3,762.50 3,762.50
06.02.05.05 PULSADOR und 8.00 195.00 1,560.00 780.00 780.00
06.02.05.06 LUCES ESTROBOSCÓPICAS und 8.00 220.00 1,760.00 880.00 880.00
06.02.05.07 EQUIPO DE SONIDO und 1.00 3,558.36 3,558.36 1,779.18 1,779.18
06.02.05.08 LINE ARRAY VT4886 und 24.00 104.21 2,501.04 1,250.52 1,250.52
06.02.05.09 SUBWOOFER VT4883 und 8.00 3,764.31 30,114.48 15,057.24 15,057.24
06.03 OBRAS EXTERIORES 31,104.71 0.00 0.00 0.00 0.00 0.00 15,552.36 15,552.36
06.03.01 MOVIMIENTO DE TIERRAS 7,142.02 0.00 0.00 0.00 0.00 0.00 3,571.01 3,571.01
06.03.01.01 EXCAVACION DE ZANJA m3 57.65 41.97 2,419.57 1,209.79 1,209.79
06.03.01.02 REFINE Y NIVELACION DEL FONDO DE ZANJA m 230.60 1.47 338.98 169.49 169.49
06.03.01.03 RELLENO Y COMPACTACION DE ZANJA m3 57.65 66.02 3,806.05 1,903.03 1,903.03
06.03.01.04 ELIMINACIÓN DE DESMONTE CON ACARREO m3 23.06 25.04 577.42 288.71 288.71
06.03.02 BUZONES 12,690.96 0.00 0.00 0.00 0.00 0.00 6,345.48 6,345.48
06.03.02.01 BUZÓN DE 0.25 x 0.25 x 0.5 m und 12.00 1,057.58 12,690.96 6,345.48 6,345.48
06.03.03 TUBERIAS TELECOMUNICACIONES 11,271.73 0.00 0.00 0.00 0.00 0.00 5,635.87 5,635.87
06.03.03.01 TUBERIA PVC-SAP 48 mm m 461.20 24.44 11,271.73 5,635.87 5,635.87
07 ESTUDIO DE IMPACTO AMBIENTAL 150,260.00 0.00 0.00 0.00 0.00 0.00 75,130.00 75,130.00
07.01 PROGRAMA DE MONITOREO AMBIENTAL 22,100.00 0.00 0.00 0.00 0.00 0.00 11,050.00 11,050.00
07.01.01 Monitoreo de la Calidad Ambiental del Aire mes 3.00 2,400.00 7,200.00 3,600.00 3,600.00
07.01.02 Monitoreo de la Calidad Ambiental del Ruido mes 5.00 400.00 2,000.00 1,000.00 1,000.00
07.01.03 Monitoreo de la Calidad Ambiental del Suelo mes 3.00 800.00 2,400.00 1,200.00 1,200.00
07.01.04 Informe Ambiental mes 7.00 1,500.00 10,500.00 5,250.00 5,250.00
07.02 PROGRAMA DE MANEJO DE RRSS 110,360.00 0.00 0.00 0.00 0.00 0.00 55,180.00 55,180.00
07.02.01 Especialista en Medio Ambiente y Seguridad Ocupacional mes 7.00 10,000.00 70,000.00 35,000.00 35,000.00
07.02.02 Servicios Higiénicos portátiles glb 1.00 32,480.00 32,480.00 16,240.00 16,240.00
07.02.03 Contenedores de RR.SS. glb 1.00 2,880.00 2,880.00 1,440.00 1,440.00
07.02.04 Transporte y disposición final de residuos sólidos peligrosos glb 1.00 5,000.00 5,000.00 2,500.00 2,500.00
07.03 PROGRAMA DE SEÑALIZACIÓN 17,800.00 0.00 0.00 0.00 0.00 0.00 8,900.00 8,900.00
07.03.01 Movilidad y Logística glb 1.00 5,000.00 5,000.00 2,500.00 2,500.00
07.03.02 Señales Temporales glb 1.00 9,600.00 9,600.00 4,800.00 4,800.00
07.03.03 Señales Permanentes glb 1.00 1,200.00 1,200.00 600.00 600.00
07.03.04 Mantenimiento de las Señales glb 1.00 2,000.00 2,000.00 1,000.00 1,000.00

COSTO DIRECTO 27,607,209.74 3,663,537.30 3,581,770.42 4,192,584.60 4,483,567.76 4,357,336.96 3,895,045.25 3,433,367.44
GASTOS GENERALES (10)% 10.00% 2,760,720.97 366,353.73 358,177.04 419,258.46 448,356.78 435,733.70 389,504.52 343,336.74
UTILIDAD (10)% 10.00% 2,760,720.97 366,353.73 358,177.04 419,258.46 448,356.78 435,733.70 389,504.52 343,336.74
SUB TOTAL 33,128,651.69 4,396,244.76 4,298,124.50 5,031,101.52 5,380,281.31 5,228,804.36 4,674,054.30 4,120,040.93
IGV (18)% 18.00% 5,963,157.30 791,324.06 773,662.41 905,598.27 968,450.64 941,184.78 841,329.77 741,607.37
COSTO DE OBRA 39,091,808.99 5,187,568.82 5,071,786.91 5,936,699.79 6,348,731.95 6,169,989.14 5,515,384.07 4,861,648.29
EXPEDIENTE TÉCNICO (3.5)% 3.50% 1,368,213.31 181,564.91 177,512.54 207,784.49 222,205.62 215,949.62 193,038.44 170,157.69
SUPERVISIÓN (3.5)% 3.50% 1,368,213.31 181,564.91 177,512.54 207,784.49 222,205.62 215,949.62 193,038.44 170,157.69
COSTO DE FINANCIAMIENTO 41,828,235.62 5,550,698.63 5,426,812.00 6,352,268.78 6,793,143.18 6,601,888.38 5,901,460.96 5,201,963.67
VALORIZADO ACUMULADO
PORCENTAJE PARCIAL (%) 13.27% 12.97% 15.19% 16.24% 15.78% 14.11% 12.44%
PORCENTAJE ACUMULADO (%) 13.27% 26.24% 41.43% 57.67% 73.45% 87.56% 100.00%