You are on page 1of 36

  McMAHON ASSOCIATES, INC.

835 Springdale Drive, Suite 200 
Exton, PA 19341 
p 610‐594‐9995 | f 610‐594‐9565 

PRINCIPALS
Joseph J. DeSantis, P.E., PTOE 
John S. DePalma 
Casey A. Moore, P.E. 
Gary R. McNaughton, P.E., PTOE 
March 28, 2019  Christopher J. Williams, P.E. 
  ASSOCIATES
John J. Mitchell, P.E. 
 
R. Trent Ebersole, P.E. 
  Matthew M. Kozsuch, P.E. 
Mr. John Nagel, ICMA‐CM, Township Manager  Maureen Chlebek, P.E., PTOE 
Dean A. Carr, P.E. 
East Whiteland Township  Jason T. Adams, P.E., PTOE 
209 Conestoga Road  Christopher K. Bauer, P.E., PTOE 

Frazer, PA  19355‐1699  FOUNDER
Joseph W. McMahon, P.E. 
 
Mr. Rick Smith, Township Manager 
East Goshen Township 
1580 Paoli Pike 
West Chester, PA 19380‐6199 
 
 
RE:   Sproul Road (S.R. 0352) and King Road (S.R. 2022) Improvement Feasibility Study 
  East Whiteland and East Goshen Townships, Chester County, PA 
  McMahon Project No. 817294.11 
 
 
Dear Mr. Nagel and Mr. Smith: 
 
McMahon Associates, Inc. has completed a traffic evaluation of the intersection of Sproul Road (S.R. 0352) and 
King Road (S.R. 2022).  The purpose of this evaluation is to determine the traffic improvements necessary to 
achieve acceptable traffic operations at this intersection.  In order to complete this evaluation, our office analyzed 
existing and future traffic operations at this intersection.  In addition, our office prepared conceptual roadway 
improvement plans for two traffic improvement options, which include a traffic signal with widening for left‐turn 
lanes, and reconfiguring the intersection for a roundabout.   
 
 
Existing Traffic Conditions Analysis  
 
For the traffic analysis, our office used recently (November 2016) completed manual turning movement traffic 
counts conducted during the weekday morning (7:00 AM to 9:00 AM) and weekday afternoon (4:00 PM to 6:00 
PM) commuter peak periods.  The existing peak hour traffic volumes are shown on Figure 1, and the traffic 
counts are included in Appendix A.   These traffic volumes were then analyzed to determine the existing 
operating conditions, and the results of this analysis are also shown in Figure 1.  The detailed capacity/level‐of‐
service analysis worksheets are provided in Appendix B.  
 
As shown in Figure 1, the intersection currently operates with some delay during both the weekday morning and 
weekday afternoon peak hours, especially on the King Road approaches to the intersection.  Furthermore, due to 

  

Engineering | Planning | Design | Technology mcmahonassociates.com


Mr. John Nagel
Mr. Rick Smith
March 28, 2019
Page 2 of 6

the skewed and offset alignment of King Road through the intersection, northbound and southbound S.R. 0352 
left‐turn traffic cannot turn simultaneously, which further negatively affects the operations of the intersection.   
 
 
Future Traffic Conditions Analysis  
 
In order to evaluate future traffic conditions, the existing traffic volumes were projected to the future 2028 design 
year.  To account for regional traffic growth, the existing traffic volumes were increased by an annual traffic 
growth rate of 1.71 percent per year compounded for ten years to 2028, or 22.6 percent total.  This growth rate 
exceeds the traffic growth rate recommended by the PennDOT Bureau of Planning and Research Growth Factors 
for August 2018 to July 2019 for similar, Urban Non‐Interstate roadways in Chester County, and was selected to 
reflect increased growth in the area, as well as potential added traffic from specific future developments.  The 
future 2028 future peak hour traffic volumes are shown on Figure 2.   These traffic volumes were then analyzed to 
determine the existing operating conditions, and the results of this analysis are also shown in Figure 2.  The 
detailed capacity/level‐of‐service analysis worksheets are provided in Appendix C.  
 
As shown in Figure 2, in the future without any capacity improvements, the intersection will operate with further 
delay, especially during the weekday afternoon peak hour.  In order to improve conditions at the intersection, it 
would be necessary to install one of the following improvement scenarios: 
 
 Scenario 1 – Conventional Signalized Improvements 
 
- Widen Sproul Road/North Chester Road (S.R. 0352) to provide separate left‐turn lanes on each 
approach.   
 
- Widen King Road (S.R. 2022) to provide separate left‐turn lanes on each approach, and convert the 
existing westbound King Road right‐turn lane to a shared through/right‐turn lane. 
 
- Install a new traffic signal to include updated signal equipment, and optimized timings and phasing. 
 
 Scenario 2 – Roundabout 
 
- Reconfigure the intersection to install a single lane roundabout. 
 
 
Improvement Scenario Comparison  
 
In order to provide a comparison between the conventional signalized intersection and roundabout 
improvements, Tables 1 and 2 show a comparison of the levels of service and queuing results for each scenario.  
As shown in Tables 1 and 2, the roundabout option provides better overall intersection and individual movement 
levels of services and shorter approach queues than the conventional signalized intersection improvement option.    
 
   
Mr. John Nagel
Mr. Rick Smith
March 28, 2019
Page 3 of 6

Table 1. Level‐of‐Service Comparison  
Conventional Signalized Intersection vs. Roundabout 
Level‐of‐Service
(Delay in Seconds) 
Approach  Movement  Weekday Morning Peak Hour  Weekday Afternoon Peak Hour 

Signalized   Roundabout  Signalized   Roundabout 


D  D 
Left 
Eastbound  (43.2)  B  (38.6)  B 
King Road  D  (10.8)  D  (13.4) 
Thru‐Right 
(35.9)  (46.1) 
D  D 
Left 
Westbound  (42.9)  C  (39.3)  C 
King Road  D  (20.9)  D  (15.0) 
Thru‐Right 
(46.2)  (45.5) 
B  B 
Left 
Northbound  (17.8)  B  (17.4)  B 
S.R. 0352  C  (14.4)  C  (11.1) 
Thru‐Right 
(30.2)  (25.6) 
B  B 
Left 
Southbound  (19.6)  B  (16.9)  B 
S.R. 0352  C  (10.1)  C  (14.5) 
Thru‐Right 
(24.2)  (27.4) 
C  B  C  B 
Overall 
(34.2)  (14.7)  (34.4)  (13.6) 
 
Table 2. Queue Comparison 
Conventional Signalized Intersection vs. Roundabout 
Queues 
(Feet) 
Approach  Movement  Weekday Morning Peak Hour  Weekday Afternoon Peak Hour 

Signalized   Roundabout  Signalized   Roundabout 


Eastbound  Left  55  40 
75  75 
King Road  Thru‐Right  358  320 
Westbound  Left  65  85 
150  125 
King Road  Thru‐Right  410  375 
Northbound  Left  55  40 
125  75 
S.R. 0352  Thru‐Right  325  260 
Southbound  Left  40  45 
50  125 
S.R. 0352  Thru‐Right  193  298 
 
Mr. John Nagel
Mr. Rick Smith
March 28, 2019
Page 4 of 6

 
Based on the traffic analysis and current design criteria, McMahon updated the conceptual design exhibit that 
was previously prepared for the signalized intersection, and also prepared a second conceptual design exhibit for 
the roundabout option.  The proposed design criteria for both scenarios is based on the current  Functional 
Classification System Guidelines within PennDOT’s “Publication 13M – Design Manual Part 2” (DM‐2), which are 
included in Appendix D, designate both Sproul Road/North Chester Road (S.R. 0352) and King Road (S.R. 2022) 
as Community Arterials within Suburban Neighborhoods.   
 
 
Conceptual Roadway Improvement Plans Scenario 1 – Conventional Signalized Intersection  
 
The revised traffic analysis and current PennDOT design criteria, resulted in the following changes to the 
roadway improvements that were previously depicted on the original conceptual design exhibit from 2005: 
 
 The proposed 100‐foot eastbound and 100‐foot westbound S.R. 0352 left‐turn lanes were increased to 
175‐feet and 225‐feet, respectively.   
 The proposed 14‐foot wide through lanes along S.R. 0352 were revised to provide 11’ through lanes 
with 4‐foot shoulders.   
 The proposed 14‐foot‐wide through lanes along King Road were revised to provide 11‐foot through 
lanes with 5‐foot shoulders.  The additional shoulder width can provide room for a bike lane in the 
future.   
 The proposed intersection curb radii were modified to accommodate tractor trailers (WB‐62) along all 
legs of the intersection, except trucks turning onto or from the western leg of King Road, which is 
difficult due to the existing skewed alignment.   
 Pedestrian facilities were provided at the southern and eastern legs of the intersection.  Based on the 
preliminary design evaluation, installing curb ramps and crosswalks on the western and northern 
legs of the intersection was determined to be infeasible due to the grade difference at the northwest 
corner, the existing driveway configuration at the northeast corner, and the right‐of‐way and/or 
easement impact, which would be required from the Three Tuns Tavern Property for a sidewalk 
connection.  This property is likely considered historic, which will require a detailed evaluation 
during preliminary engineering.   
 Stormwater management facilities are proposed to offset the increase in runoff due to the proposed 
roadway improvements.  The stormwater management facilities are a requirement of the 
Pennsylvania DEP and Chester County Conservation District, due to the estimated earth disturbance 
that will likely exceed one (1) acre.   
 
As a result of these updates, in addition to the benefits identified in the traffic analysis results, the conventional 
signalized intersection improvements will provide stormwater runoff management, improved pedestrian 
facilities, improved turning accommodations for trucks, and better overall ride quality through the intersection.   
 
The improvements will require right‐of‐way from thirteen (13) different properties, totaling an estimated 0.51 
acres.  Temporary construction easements will be identified during preliminary design; however, it is likely they 
will be required from several properties for driveway adjustments and grading.  Additionally, it is anticipated 
that nine (9) utility pole relocations will be required.  Impacts to existing underground utilities will need to be 
explored during the preliminary engineering phase of the project through subsurface utility engineering.   
Mr. John Nagel
Mr. Rick Smith
March 28, 2019
Page 5 of 6

 
As shown in Appendix E, the estimated opinion of cost for the conventional signalized intersection 
improvements is $2,525,503.  
 
 
Conceptual Roadway Improvement Plan: Scenario 2 – Roundabout  
 
The roundabout conceptual design exhibit was primarily developed in accordance with the National Cooperative 
Highway Research Programs (NHRCP), Report 672, “Roundabouts: An Informational Guide”.  This option was 
developed not only because of its traffic operations benefits, but also for the following reasons: 
 
 Improved pedestrian accommodations at the intersection. 
 Improved accommodations for tractor trailers (WB‐62) on all legs of the intersection. 
 Improved intersection geometry and overall safer operating speeds.  
 Reduced long term maintenance costs. 
   
The roundabout improvements identified in the conceptual design exhibit will require right‐of‐way from seven 
(7) different properties, totaling an estimated 0.64 acres, which includes the acquisition of the entire property 
currently owned by Thomas A. Stuart & Christine M. Stefanou.  This option will also have slightly larger impacts 
to the majority of the properties within the immediate area of the intersection, when compared with to the 
conventional signalized intersection improvements.  However, the roundabout option eliminates many of the 
impacts to the properties along the approach legs of the intersection and the potentially large easement 
acquisition required from the Pierre Property and Jackson Property for stormwater management facilities.  In 
order to mitigate some of these larger impacts to properties within the immediate area of the intersection, 
landscaping and small retaining walls are proposed on the affected properties.  Providing pedestrian 
accommodations across the entire intersection, will require right‐of‐way from the historically eligible Three Tuns 
Tavern Property.  Further investigation will need to be completed during preliminary engineering to mitigate 
impacts to the property.      
 
Similar to the conventional intersection improvements, temporary construction easements will likely be required 
from several properties for driveway adjustments and grading, which will be identified during preliminary 
design.  It is anticipated the roundabout will require only five (5) utility pole relocations.  Impacts to existing 
underground utilities will need to be explored during the preliminary engineering phase of the project through 
subsurface utility engineering.   
 
As shown in Appendix E, the estimated opinion of cost for the roundabout is $3,127,098.  
 
 
Improvement Option Comparison  
 
In order to summarize the results of the technical evaluation summarized above, Table 3 provides a summary of 
the impacts of both the conventional signalized intersection improvements and the roundabout improvements. 
 
   
Mr. John Nagel
Mr. Rick Smith
March 28, 2019
Page 6 of 6

Table 3. Intersection Improvements Impact Matrix 
 
Scenario 1 – Conventional Signalized 
Category  Scenario 2 – Roundabout 
Intersection  Improvements 

Overall Level‐of‐Service  
AM(PM) 
C(C)    B(B)   
Maximum Approach Queue 
EB King Road, WB King Road, 
NB Rt. 352, SB Rt. 352 
358 feet, 410 feet, 325 feet, 298 feet    75 feet, 150 feet, 125 feet, 125 feet   
Properties Affected   13 Properties    7 Properties   
Total Property Acquisitions   0 Properties    1 Property   

Right‐of‐Way Required  0.51 Acres    0.64 Acres   

Utility Pole Relocations  9 Poles    5 Poles   


Estimated Cost   $2,525,503    $3,127,098   

 
 
If you should have any questions, or require further information, please feel free to contact our office. 
 
Sincerely, 

 
Christopher J. Williams, P.E. 
Vice President & Regional Manager – Mid‐Atlantic 
 
 

 
James J. Kouch, P.E. 
Senior Project Manager 
I:\eng\817294 ‐ 352 King Feasibility\correspondence\out\client\2019-03-28_Nagel_ Smith_Feasibility.docx 

 
 
SR0352NORTHCHESTERROAD/SPROULROAD
ANDSR2022KINGROADIMPROVEMENTS
ESTIMATEDPROJECTIMPACTSTATISTICS

IMPACT QUANTITY

2 LARGE
UTILITY POLE
( ) 7 MEDIUM
RELOCATIONS
1 SMALL
AFFECTED
(#) 13
PROPERTIES*
ESTIMATED TOTAL
REQUIRED (AC.) 0.51 AC.
RIGHT-OF-WAY*

*PROPERTIES WHERE IT IS ESTIMATED THAT PERMANENT RIGHT-OF-WAY,


PERMANENT EASEMENTS, OR TEMPORARY CONSTRUCTION EASEMENTS
WILL BE NECESSARY.

IP
NSH
IP
NSH
OW
TOW
DT
LAN
EN
ITE
OSH
WH
TG
T
EAS
EAS

CONCEPTUAL DESIGN EXHIBIT


(NOT FOR CONSTRUCTION)
SR0352NORTHCHESTERROAD/SPROULROAD
ANDSR2022KINGROADIMPROVEMENTS
ESTIMATEDPROJECTIMPACTSTATISTICS

IMPACT QUANTITY

2 LARGE
UTILITY POLE
( ) 1 MEDIUM
RELOCATIONS
1 SMALL
AFFECTED
(#) 7
PROPERTIES*
ESTIMATED TOTAL
REQUIRED (AC.) 0.64 AC.**
RIGHT-OF-WAY*

IP
NSH
IP
NSH
OW
TOW
DT
LAN
EN
ITE
OSH
WH
TG
T
EAS
EAS

CONCEPTUAL DESIGN EXHIBIT


(NOT FOR CONSTRUCTION)
 

   

Appendix A

Manual Turning Movement Counts

 
Transportation Solutions Building Better Communities mcmahonassociates.com
 
McMahon Associates, Inc.
425 Commerce Drive, Suite 200
Fort Washington, P A 19034
Municipality: East Whiteland Township File Name : ewhiteact20w
Location: King Road & Site Code : 81661120
Sproul Road Start Date : 11/2/2016
Counter/Board #: RS Page No :1
Groups Printed- Passenger Vehicles - Heavy Vehicles
Sproul Rd King Rd Sproul Rd King Rd
Southbound Westbound Northbound Eastbound
Start Time Left Thru ROR Right Left Thru ROR Right Left Thru ROR Right Left Thru ROR Right Int. Total
07:00 12 29 0 1 11 24 0 33 4 60 0 7 6 57 0 8 252
07:15 15 47 0 0 11 35 0 50 9 71 0 9 14 53 0 13 327
07:30 10 44 0 2 16 51 0 30 24 67 0 2 8 53 0 17 324
07:45 15 51 0 0 6 74 0 26 17 87 0 13 15 55 0 18 377
Total 52 171 0 3 44 184 0 139 54 285 0 31 43 218 0 56 1280

08:00 8 45 0 0 13 63 0 26 20 72 0 10 11 57 0 10 335
08:15 21 56 0 5 13 50 0 30 13 79 0 6 7 54 0 14 348
08:30 8 38 0 2 17 47 0 36 14 75 0 9 7 42 0 17 312
08:45 10 46 0 2 14 37 0 29 18 72 0 12 4 44 0 14 302
Total 47 185 0 9 57 197 0 121 65 298 0 37 29 197 0 55 1297

16:00 5 71 0 5 7 53 0 32 18 67 0 9 6 34 0 23 330
16:15 16 73 0 3 15 82 0 23 18 67 0 12 5 44 0 15 373
16:30 14 82 0 7 10 59 0 25 17 57 0 13 8 53 0 22 367
16:45 14 67 0 5 24 62 0 34 21 60 0 14 5 52 0 17 375
Total 49 293 0 20 56 256 0 114 74 251 0 48 24 183 0 77 1445

17:00 17 91 0 9 17 66 0 17 20 65 0 3 13 61 0 20 399
17:15 19 81 0 6 17 60 0 31 10 82 0 11 6 52 0 22 397
17:30 23 89 0 5 16 53 0 31 15 74 0 12 11 49 0 14 392
17:45 13 86 0 3 14 55 0 12 12 74 0 10 6 36 0 14 335
Total 72 347 0 23 64 234 0 91 57 295 0 36 36 198 0 70 1523

Grand Total 220 996 0 55 221 871 0 465 250 1129 0 152 132 796 0 258 5545
Apprch % 17.3 78.4 0 4.3 14.2 55.9 0 29.9 16.3 73.7 0 9.9 11.1 67.1 0 21.8
Total % 4 18 0 1 4 15.7 0 8.4 4.5 20.4 0 2.7 2.4 14.4 0 4.7
Passenger Vehicles 213 982 0 54 209 836 0 443 244 1110 0 146 130 763 0 249 5379
% Passenger Vehicles 96.8 98.6 0 98.2 94.6 96 0 95.3 97.6 98.3 0 96.1 98.5 95.9 0 96.5 97
Heavy Vehicles 7 14 0 1 12 35 0 22 6 19 0 6 2 33 0 9 166
% Heavy Vehicles 3.2 1.4 0 1.8 5.4 4 0 4.7 2.4 1.7 0 3.9 1.5 4.1 0 3.5 3

Zero Pedestrians were observed during this study.


McMahon Associates, Inc.
425 Commerce Drive, Suite 200
Fort Washington, P A 19034
Municipality: East Whiteland Township File Name : ewhiteact20w
Location: King Road & Site Code : 81661120
Sproul Road Start Date : 11/2/2016
Counter/Board #: RS Page No :2

Sproul Rd King Rd Sproul Rd King Rd


Southbound Westbound Northbound Eastbound
Thr RO Rig App. Thr RO Rig App. Thr RO Rig App. Int.
Start Time Left Thru ROR Right App. Total Left Left Left
u R ht Total u R ht Total u R ht Total Total
Peak Hour Analysis From 07:00 to 11:45 - Peak 1 of 1
Peak Hour for Entire Intersection Begins at 07:30
07:30 10 44 0 2 56 16 51 0 30 97 24 67 0 2 93 8 53 0 17 78 324
07:45 15 51 0 0 66 6 74 0 26 106 17 87 0 13 117 15 55 0 18 88 377
08:00 8 45 0 0 53 13 63 0 26 102 20 72 0 10 102 11 57 0 10 78 335
08:15 21 56 0 5 82 13 50 0 30 93 13 79 0 6 98 7 54 0 14 75 348
Total Volume 54 196 0 7 257 48 238 0 112 398 74 305 0 31 410 41 219 0 59 319 1384
% App. Total 21 76.3 0 2.7 12.1 59.8 0 28.1 18 74.4 0 7.6 12.9 68.7 0 18.5
PHF .643 .875 .000 .350 .784 .750 .804 .000 .933 .939 .771 .876 .000 .596 .876 .683 .961 .000 .819 .906 .918
Passenger Vehicles

% Passenger Vehicles 98.1 95.9 0 100 96.5 93.8 92.4 0 96.4 93.7 95.9 99.3 0 90.3 98.0 97.6 91.8 0 94.9 93.1 95.4
Heavy Vehicles
% Heavy Vehicles 1.9 4.1 0 0 3.5 6.3 7.6 0 3.6 6.3 4.1 0.7 0 9.7 2.0 2.4 8.2 0 5.1 6.9 4.6

Sproul Rd
Out In Total
451 248 699
7 9 16
458 257 715

7 188 53
0 8 1
7 196 54
Right Thru Left

Peak Hour Data


43
595

638
Total

Out
304

282
1
40

41

Right Thru

22
Left

112

108

North
4
22
297

319

King Rd
King Rd

Peak Hour Begins at 07:30


18
201

219
Right Thru
In

In
238

220

398

373
18

25

Passenger Vehicles
Heavy Vehicles
3
56

59

Left
298

319
21
Out

Total
48

45
3

702

655
47

Left Thru Right


71 303 28
3 2 3
74 305 31

289 402 691


14 8 22
303 410 713
Out In Total
Sproul Rd
McMahon Associates, Inc.
425 Commerce Drive, Suite 200
Fort Washington, P A 19034
Municipality: East Whiteland Township File Name : ewhiteact20w
Location: King Road & Site Code : 81661120
Sproul Road Start Date : 11/2/2016
Counter/Board #: RS Page No :3

Sproul Rd King Rd Sproul Rd King Rd


Southbound Westbound Northbound Eastbound
Start Time Left Thru ROR Right App. Total Left Thru ROR Right App. Total Left Thru ROR Right App. Total Left Thru ROR Right App. Total Int. Total
Peak Hour Analysis From 12:00 to 17:45 - Peak 1 of 1
Peak Hour for Entire Intersection Begins at 16:45
16:45 14 67 0 5 86 24 62 0 34 120 21 60 0 14 95 5 52 0 17 74 375
17:00 17 91 0 9 117 17 66 0 17 100 20 65 0 3 88 13 61 0 20 94 399
17:15 19 81 0 6 106 17 60 0 31 108 10 82 0 11 103 6 52 0 22 80 397
17:30 23 89 0 5 117 16 53 0 31 100 15 74 0 12 101 11 49 0 14 74 392
Total Volume 73 328 0 25 426 74 241 0 113 428 66 281 0 40 387 35 214 0 73 322 1563
% App. Total 17.1 77 0 5.9 17.3 56.3 0 26.4 17.1 72.6 0 10.3 10.9 66.5 0 22.7
PHF .793 .901 .000 .694 .910 .771 .913 .000 .831 .892 .786 .857 .000 .714 .939 .673 .877 .000 .830 .856 .979
Passenger Vehicles

% Passenger Vehicles 100 100 0 96.0 99.8 98.6 99.2 0 96.5 98.4 100 99.6 0 100 99.7 97.1 97.2 0 100 97.8 99.0
Heavy Vehicles
% Heavy Vehicles 0 0 0 4.0 0.2 1.4 0.8 0 3.5 1.6 0 0.4 0 0 0.3 2.9 2.8 0 0 2.2 1.0

Sproul Rd
Out In Total
423 425 848
6 1 7
429 426 855

24 328 73
1 0 0
25 328 73
Right Thru Left

Peak Hour Data


10
644

654
Total

Out
327

321
1
34

35

Right Thru
Left

113

109

North
4
7
315

322

King Rd
King Rd

Peak Hour Begins at 16:45


6
208

214
Right Thru
In

In
241

239

428

421
2

Passenger Vehicles
Heavy Vehicles
0
73

73

Left
3
329

332
Out

Total
74

73
1

755

742
13

Left Thru Right


66 280 40
0 1 0
66 281 40

474 386 860


1 1 2
475 387 862
Out In Total
Sproul Rd
 

    

Appendix B

Existing (2016) Capacity/Level-of-Service


Analysis Worksheets

 
Transportation Solutions Building Better Communities mcmahonassociates.com
 
McMahon Associates, Inc. King Road and 352 Imprvt Feasibility McMahon Associates, Inc. King Road and 352 Imprvt Feasibility
1: Sproul Road (S.R. 0352) & West King Road 2016 Existing Weekday AM Peak Hour 1: Sproul Road (S.R. 0352) & West King Road 2016 Existing Weekday AM Peak Hour

Splits and Phases: 1: Sproul Road (S.R. 0352) & West King Road

Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (vph) 41 219 59 48 238 112 74 305 31 54 196 7
Future Volume (vph) 41 219 59 48 238 112 74 305 31 54 196 7
Ideal Flow (vphpl) 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800
Lane Width (ft) 10 10 10 12 12 12 14 14 14 10 10 10
Grade (%) 4% -2% -2% 2%
Storage Length (ft) 0 0 125 0 0 0 0 0
Storage Lanes 0 0 1 0 0 0 0 0
Taper Length (ft) 25 25 25 25
Lane Util. Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Frt 0.975 0.952 0.990 0.996
Flt Protected 0.994 0.950 0.991 0.990
Satd. Flow (prot) 0 1496 0 1629 1622 0 0 1861 0 0 1585 0
Flt Permitted 0.994 0.950 0.882 0.813
Satd. Flow (perm) 0 1496 0 1629 1622 0 0 1656 0 0 1302 0
Right Turn on Red Yes Yes Yes Yes
Satd. Flow (RTOR) 13 26 6 2
Link Speed (mph) 35 40 40 35
Link Distance (ft) 2002 907 900 1892
Travel Time (s) 39.0 15.5 15.3 36.9
Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92
Heavy Vehicles (%) 2% 8% 5% 6% 8% 4% 4% 1% 10% 2% 4% 0%
Adj. Flow (vph) 45 238 64 52 259 122 80 332 34 59 213 8
Shared Lane Traffic (%)
Lane Group Flow (vph) 0 347 0 52 381 0 0 446 0 0 280 0
Turn Type Split NA Split NA Perm NA Perm NA
Protected Phases 4 4 8 8 2 6
Permitted Phases 2 6
Detector Phase 4 4 8 8 2 2 6 6
Switch Phase
Minimum Initial (s) 5.0 5.0 5.0 5.0 28.0 28.0 28.0 28.0
Minimum Split (s) 23.0 23.0 22.0 22.0 34.0 34.0 34.0 34.0
Total Split (s) 25.0 25.0 21.0 21.0 34.0 34.0 34.0 34.0
Total Split (%) 31.3% 31.3% 26.3% 26.3% 42.5% 42.5% 42.5% 42.5%
Yellow Time (s) 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0
All-Red Time (s) 3.0 3.0 2.0 2.0 2.0 2.0 2.0 2.0
Lost Time Adjust (s) -1.0 -1.0 -1.0 -1.0 -1.0
Total Lost Time (s) 6.0 5.0 5.0 5.0 5.0
Lead/Lag
Lead-Lag Optimize?
Recall Mode None None None None Min Min Min Min
Intersection Summary
Area Type: Other
Cycle Length: 80
Actuated Cycle Length: 80
Natural Cycle: 90
Control Type: Semi Act-Uncoord
Description: 8A

Lanes, Volumes, Timings 2016 Existing Weekday AM Peak Hour Lanes, Volumes, Timings 2016 Existing Weekday AM Peak Hour
I:\eng\817294 - 352 King Feasibility\Traffic\analysis\Existing\Weekday AM.syn Synchro 8 I:\eng\817294 - 352 King Feasibility\Traffic\analysis\Existing\Weekday AM.syn Synchro 8
McMahon Associates, Inc. King Road and 352 Imprvt Feasibility
1: Sproul Road (S.R. 0352) & West King Road 2016 Existing Weekday AM Peak Hour

Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (veh/h) 41 219 59 48 238 112 74 305 31 54 196 7
Future Volume (veh/h) 41 219 59 48 238 112 74 305 31 54 196 7
Number 7 4 14 3 8 18 5 2 12 1 6 16
Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0
Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Adj Sat Flow, veh/h/ln 1764 1654 1764 1715 1704 1818 1891 1850 1891 1782 1722 1782
Adj Flow Rate, veh/h 45 238 64 52 259 122 80 332 34 59 213 8
Adj No. of Lanes 0 1 0 1 1 0 0 1 0 0 1 0
Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92
Percent Heavy Veh, % 8 8 8 6 8 8 1 1 1 4 4 4
Cap, veh/h 49 259 70 327 219 103 140 489 47 135 443 15
Arrive On Green 0.24 0.24 0.24 0.20 0.20 0.20 0.36 0.36 0.36 0.36 0.36 0.36
Sat Flow, veh/h 206 1092 294 1633 1096 516 239 1348 131 223 1222 42
Grp Volume(v), veh/h 347 0 0 52 0 381 446 0 0 280 0 0
Grp Sat Flow(s),veh/h/ln 1592 0 0 1633 0 1612 1717 0 0 1487 0 0
Q Serve(g_s), s 17.0 0.0 0.0 2.1 0.0 16.0 6.5 0.0 0.0 0.0 0.0 0.0
Cycle Q Clear(g_c), s 17.0 0.0 0.0 2.1 0.0 16.0 17.5 0.0 0.0 10.9 0.0 0.0
Prop In Lane 0.13 0.18 1.00 0.32 0.18 0.08 0.21 0.03
Lane Grp Cap(c), veh/h 378 0 0 327 0 322 676 0 0 594 0 0
V/C Ratio(X) 0.92 0.00 0.00 0.16 0.00 1.18 0.66 0.00 0.00 0.47 0.00 0.00
Avail Cap(c_a), veh/h 378 0 0 327 0 322 676 0 0 594 0 0
HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Upstream Filter(I) 1.00 0.00 0.00 1.00 0.00 1.00 1.00 0.00 0.00 1.00 0.00 0.00
Uniform Delay (d), s/veh 29.7 0.0 0.0 26.4 0.0 32.0 21.7 0.0 0.0 19.5 0.0 0.0
Incr Delay (d2), s/veh 27.7 0.0 0.0 0.5 0.0 108.9 2.4 0.0 0.0 0.6 0.0 0.0
Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
%ile BackOfQ(95%),veh/ln 15.6 0.0 0.0 1.8 0.0 30.3 13.8 0.0 0.0 8.4 0.0 0.0
LnGrp Delay(d),s/veh 57.5 0.0 0.0 26.9 0.0 140.9 24.0 0.0 0.0 20.1 0.0 0.0
LnGrp LOS E C F C C
Approach Vol, veh/h 347 433 446 280
Approach Delay, s/veh 57.5 127.2 24.0 20.1
Approach LOS E F C C
Timer 1 2 3 4 5 6 7 8
Assigned Phs 2 4 6 8
Phs Duration (G+Y+Rc), s 34.0 25.0 34.0 21.0
Change Period (Y+Rc), s 6.0 7.0 6.0 6.0
Max Green Setting (Gmax), s 28.0 18.0 28.0 15.0
Max Q Clear Time (g_c+I1), s 19.5 19.0 12.9 18.0
Green Ext Time (p_c), s 0.9 0.0 0.7 0.0
Intersection Summary
HCM 2010 Ctrl Delay 60.7
HCM 2010 LOS E

HCM 2010 Signalized Intersection Summary 2016 Existing Weekday AM Peak Hour
I:\eng\817294 - 352 King Feasibility\Traffic\analysis\Existing\Weekday AM.syn Synchro 8
McMahon Associates, Inc. King Road and 352 Imprvt Feasibility McMahon Associates, Inc. King Road and 352 Imprvt Feasibility
1: Sproul Road (S.R. 0352) & West King Road 2016 Existing Weekday PM Peak Hour 1: Sproul Road (S.R. 0352) & West King Road 2016 Existing Weekday PM Peak Hour

Control Type: Semi Act-Uncoord


Description: 8A
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations Splits and Phases: 1: Sproul Road (S.R. 0352) & West King Road
Traffic Volume (vph) 35 214 73 74 241 113 66 281 40 73 328 25
Future Volume (vph) 35 214 73 74 241 113 66 281 40 73 328 25
Ideal Flow (vphpl) 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800
Lane Width (ft) 10 10 10 12 12 12 14 14 14 10 10 10
Grade (%) 4% -2% -2% 2%
Storage Length (ft) 0 0 125 0 0 0 0 0
Storage Lanes 0 0 1 0 0 0 0 0
Taper Length (ft) 25 25 25 25
Lane Util. Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Frt 0.970 0.952 0.986 0.992
Flt Protected 0.995 0.950 0.992 0.992
Satd. Flow (prot) 0 1553 0 1710 1698 0 0 1897 0 0 1633 0
Flt Permitted 0.995 0.950 0.834 0.842
Satd. Flow (perm) 0 1553 0 1710 1698 0 0 1595 0 0 1386 0
Right Turn on Red Yes Yes Yes Yes
Satd. Flow (RTOR) 17 26 8 4
Link Speed (mph) 35 40 40 35
Link Distance (ft) 2002 907 900 1892
Travel Time (s) 39.0 15.5 15.3 36.9
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
Heavy Vehicles (%) 3% 3% 0% 1% 1% 4% 0% 0% 0% 0% 0% 4%
Adj. Flow (vph) 36 218 74 76 246 115 67 287 41 74 335 26
Shared Lane Traffic (%)
Lane Group Flow (vph) 0 328 0 76 361 0 0 395 0 0 435 0
Turn Type Split NA Split NA Perm NA Perm NA
Protected Phases 4 4 8 8 2 6
Permitted Phases 2 6
Detector Phase 4 4 8 8 2 2 6 6
Switch Phase
Minimum Initial (s) 5.0 5.0 5.0 5.0 28.0 28.0 28.0 28.0
Minimum Split (s) 23.0 23.0 22.0 22.0 34.0 34.0 34.0 34.0
Total Split (s) 25.0 25.0 21.0 21.0 34.0 34.0 34.0 34.0
Total Split (%) 31.3% 31.3% 26.3% 26.3% 42.5% 42.5% 42.5% 42.5%
Maximum Green (s) 18.0 18.0 15.0 15.0 28.0 28.0 28.0 28.0
Yellow Time (s) 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0
All-Red Time (s) 3.0 3.0 2.0 2.0 2.0 2.0 2.0 2.0
Lost Time Adjust (s) -1.0 -1.0 -1.0 -1.0 -1.0
Total Lost Time (s) 6.0 5.0 5.0 5.0 5.0
Lead/Lag
Lead-Lag Optimize?
Vehicle Extension (s) 5.0 5.0 5.0 5.0 3.0 3.0 3.0 3.0
Recall Mode None None None None Min Min Min Min
Intersection Summary
Area Type: Other
Cycle Length: 80
Actuated Cycle Length: 79.8
Natural Cycle: 90

Lanes, Volumes, Timings 2016 Existing Weekday PM Peak Hour Lanes, Volumes, Timings 2016 Existing Weekday PM Peak Hour
I:\eng\817294 - 352 King Feasibility\Traffic\analysis\Existing\Weekday PM.syn Synchro 8 I:\eng\817294 - 352 King Feasibility\Traffic\analysis\Existing\Weekday PM.syn Synchro 8
McMahon Associates, Inc. King Road and 352 Imprvt Feasibility
1: Sproul Road (S.R. 0352) & West King Road 2016 Existing Weekday PM Peak Hour

Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (veh/h) 35 214 73 74 241 113 66 281 40 73 328 25
Future Volume (veh/h) 35 214 73 74 241 113 66 281 40 73 328 25
Number 7 4 14 3 8 18 5 2 12 1 6 16
Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0
Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Adj Sat Flow, veh/h/ln 1764 1724 1764 1800 1783 1818 1891 1891 1891 1782 1778 1782
Adj Flow Rate, veh/h 36 218 74 76 246 115 67 287 41 74 335 26
Adj No. of Lanes 0 1 0 1 1 0 0 1 0 0 1 0
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
Percent Heavy Veh, % 3 3 3 1 1 1 0 0 0 0 0 0
Cap, veh/h 42 253 86 346 232 108 125 463 62 127 472 35
Arrive On Green 0.23 0.23 0.23 0.20 0.20 0.20 0.37 0.37 0.37 0.37 0.37 0.37
Sat Flow, veh/h 181 1096 372 1714 1150 538 198 1267 170 201 1291 95
Grp Volume(v), veh/h 328 0 0 76 0 361 395 0 0 435 0 0
Grp Sat Flow(s),veh/h/ln 1649 0 0 1714 0 1688 1634 0 0 1587 0 0
Q Serve(g_s), s 15.1 0.0 0.0 2.9 0.0 16.0 0.0 0.0 0.0 3.1 0.0 0.0
Cycle Q Clear(g_c), s 15.1 0.0 0.0 2.9 0.0 16.0 15.8 0.0 0.0 18.9 0.0 0.0
Prop In Lane 0.11 0.23 1.00 0.32 0.17 0.10 0.17 0.06
Lane Grp Cap(c), veh/h 381 0 0 346 0 340 650 0 0 633 0 0
V/C Ratio(X) 0.86 0.00 0.00 0.22 0.00 1.06 0.61 0.00 0.00 0.69 0.00 0.00
Avail Cap(c_a), veh/h 395 0 0 346 0 340 650 0 0 633 0 0
HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Upstream Filter(I) 1.00 0.00 0.00 1.00 0.00 1.00 1.00 0.00 0.00 1.00 0.00 0.00
Uniform Delay (d), s/veh 29.3 0.0 0.0 26.5 0.0 31.7 20.6 0.0 0.0 21.7 0.0 0.0
Incr Delay (d2), s/veh 18.4 0.0 0.0 0.7 0.0 65.6 1.6 0.0 0.0 3.1 0.0 0.0
Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
%ile BackOfQ(95%),veh/ln 13.6 0.0 0.0 2.6 0.0 24.4 11.9 0.0 0.0 13.6 0.0 0.0
LnGrp Delay(d),s/veh 47.7 0.0 0.0 27.1 0.0 97.3 22.2 0.0 0.0 24.8 0.0 0.0
LnGrp LOS D C F C C
Approach Vol, veh/h 328 437 395 435
Approach Delay, s/veh 47.7 85.1 22.2 24.8
Approach LOS D F C C
Timer 1 2 3 4 5 6 7 8
Assigned Phs 2 4 6 8
Phs Duration (G+Y+Rc), s 34.0 24.3 34.0 21.0
Change Period (Y+Rc), s 6.0 7.0 6.0 6.0
Max Green Setting (Gmax), s 28.0 18.0 28.0 15.0
Max Q Clear Time (g_c+I1), s 17.8 17.1 20.9 18.0
Green Ext Time (p_c), s 0.8 0.2 0.8 0.0
Intersection Summary
HCM 2010 Ctrl Delay 45.4
HCM 2010 LOS D

HCM 2010 Signalized Intersection Summary 2016 Existing Weekday PM Peak Hour
I:\eng\817294 - 352 King Feasibility\Traffic\analysis\Existing\Weekday PM.syn Synchro 8
 

    

Appendix C

Future (2028) Capacity/Level-of-Service


Analysis Worksheets

 
Transportation Solutions Building Better Communities mcmahonassociates.com
 
 

Scenario 1  
McMahon Associates, Inc. King Road and 352 Imprvt Feasibility McMahon Associates, Inc. King Road and 352 Imprvt Feasibility
1: Sproul Road (S.R. 0352) & West King Road 2016 Existing Weekday AM Peak Hour with Impvts - Phasing 1 1: Sproul Road (S.R. 0352) & West King Road 2016 Existing Weekday AM Peak Hour with Impvts - Phasing 1

Control Type: Semi Act-Uncoord


Description: 8A
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations Splits and Phases: 1: Sproul Road (S.R. 0352) & West King Road
Traffic Volume (vph) 41 219 59 48 238 112 74 305 31 54 196 7
Future Volume (vph) 41 219 59 48 238 112 74 305 31 54 196 7
Ideal Flow (vphpl) 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800
Lane Width (ft) 10 14 14 10 14 14 10 12 12 10 14 14
Grade (%) 4% -2% -2% 2%
Storage Length (ft) 80 0 125 0 100 0 100 0
Storage Lanes 1 0 1 0 1 0 1 0
Taper Length (ft) 25 25 25 25
Lane Util. Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Frt 0.968 0.952 0.986 0.995
Flt Protected 0.950 0.950 0.950 0.950
Satd. Flow (prot) 1533 1696 0 1521 1730 0 1550 1760 0 1549 1821 0
Flt Permitted 0.950 0.950 0.531 0.408
Satd. Flow (perm) 1533 1696 0 1521 1730 0 866 1760 0 665 1821 0
Right Turn on Red Yes Yes Yes Yes
Satd. Flow (RTOR) 13 23 5 2
Link Speed (mph) 35 40 40 35
Link Distance (ft) 2002 907 900 1892
Travel Time (s) 39.0 15.5 15.3 36.9
Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92
Heavy Vehicles (%) 2% 8% 5% 6% 8% 4% 4% 1% 10% 2% 4% 0%
Adj. Flow (vph) 45 238 64 52 259 122 80 332 34 59 213 8
Shared Lane Traffic (%)
Lane Group Flow (vph) 45 302 0 52 381 0 80 366 0 59 221 0
Turn Type Prot NA Prot NA pm+pt NA pm+pt NA
Protected Phases 7 4 3 8 5 2 1 6
Permitted Phases 2 6
Detector Phase 7 4 3 8 5 2 1 6
Switch Phase
Minimum Initial (s) 5.0 5.0 5.0 5.0 4.0 26.0 4.0 26.0
Minimum Split (s) 23.0 23.0 22.0 22.0 10.0 32.0 10.0 32.0
Total Split (s) 23.0 32.0 23.0 32.0 13.0 32.0 13.0 32.0
Total Split (%) 23.0% 32.0% 23.0% 32.0% 13.0% 32.0% 13.0% 32.0%
Maximum Green (s) 17.0 26.0 17.0 26.0 7.0 26.0 7.0 26.0
Yellow Time (s) 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0
All-Red Time (s) 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0
Lost Time Adjust (s) -1.0 -1.0 -1.0 -1.0 -1.0 -1.0 -1.0 -1.0
Total Lost Time (s) 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
Lead/Lag Lead Lag Lead Lag Lead Lag Lead Lag
Lead-Lag Optimize?
Vehicle Extension (s) 5.0 5.0 5.0 5.0 3.0 3.0 3.0 3.0
Recall Mode None None None None None Min None Min
Intersection Summary
Area Type: Other
Cycle Length: 100
Actuated Cycle Length: 81.5
Natural Cycle: 90

Lanes, Volumes, Timings 2016 Existing Weekday AM Peak Hour with Impvts - Phasing 1 Lanes, Volumes, Timings 2016 Existing Weekday AM Peak Hour with Impvts - Phasing 1
I:\eng\817294 - 352 King Feasibility\Traffic\analysis\Existing with Improvements\Pmt Prot Phasing\Weekday AM.syn Synchro 8 I:\eng\817294 - 352 King Feasibility\Traffic\analysis\Existing with Improvements\Pmt Prot Phasing\Weekday AM.syn Synchro 8
McMahon Associates, Inc. King Road and 352 Imprvt Feasibility
1: Sproul Road (S.R. 0352) & West King Road 2016 Existing Weekday AM Peak Hour with Impvts - Phasing 1

Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (veh/h) 41 219 59 48 238 112 74 305 31 54 196 7
Future Volume (veh/h) 41 219 59 48 238 112 74 305 31 54 196 7
Number 7 4 14 3 8 18 5 2 12 1 6 16
Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0
Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Adj Sat Flow, veh/h/ln 1729 1709 1835 1715 1772 1891 1748 1785 1818 1747 1784 1853
Adj Flow Rate, veh/h 45 238 64 52 259 122 80 332 34 59 213 8
Adj No. of Lanes 1 1 0 1 1 0 1 1 0 1 1 0
Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92
Percent Heavy Veh, % 2 8 8 6 8 8 4 1 1 2 4 4
Cap, veh/h 124 351 95 124 310 146 483 558 57 363 578 22
Arrive On Green 0.08 0.27 0.27 0.08 0.27 0.27 0.06 0.35 0.35 0.05 0.34 0.34
Sat Flow, veh/h 1647 1298 349 1633 1140 537 1665 1593 163 1664 1709 64
Grp Volume(v), veh/h 45 0 302 52 0 381 80 0 366 59 0 221
Grp Sat Flow(s),veh/h/ln 1647 0 1647 1633 0 1677 1665 0 1756 1664 0 1773
Q Serve(g_s), s 2.1 0.0 13.1 2.4 0.0 17.1 2.4 0.0 13.6 1.8 0.0 7.5
Cycle Q Clear(g_c), s 2.1 0.0 13.1 2.4 0.0 17.1 2.4 0.0 13.6 1.8 0.0 7.5
Prop In Lane 1.00 0.21 1.00 0.32 1.00 0.09 1.00 0.04
Lane Grp Cap(c), veh/h 124 0 446 124 0 456 483 0 615 363 0 600
V/C Ratio(X) 0.36 0.00 0.68 0.42 0.00 0.84 0.17 0.00 0.59 0.16 0.00 0.37
Avail Cap(c_a), veh/h 372 0 558 369 0 568 544 0 615 443 0 600
HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Upstream Filter(I) 1.00 0.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00
Uniform Delay (d), s/veh 35.1 0.0 26.0 35.2 0.0 27.4 15.3 0.0 21.3 16.4 0.0 19.9
Incr Delay (d2), s/veh 3.8 0.0 4.2 4.7 0.0 11.3 0.2 0.0 1.6 0.2 0.0 0.4
Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
%ile BackOfQ(95%),veh/ln 1.9 0.0 10.6 2.3 0.0 14.3 2.0 0.0 11.2 1.5 0.0 6.7
LnGrp Delay(d),s/veh 38.9 0.0 30.1 39.9 0.0 38.7 15.5 0.0 22.8 16.6 0.0 20.3
LnGrp LOS D C D D B C B C
Approach Vol, veh/h 347 433 446 280
Approach Delay, s/veh 31.3 38.8 21.5 19.5
Approach LOS C D C B
Timer 1 2 3 4 5 6 7 8
Assigned Phs 1 2 3 4 5 6 7 8
Phs Duration (G+Y+Rc), s 9.1 33.0 11.1 26.6 10.1 32.0 11.0 26.7
Change Period (Y+Rc), s 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0
Max Green Setting (Gmax), s 7.0 26.0 17.0 26.0 7.0 26.0 17.0 26.0
Max Q Clear Time (g_c+I1), s 4.3 15.6 4.9 15.1 4.9 9.5 4.6 19.1
Green Ext Time (p_c), s 0.0 0.7 0.2 1.6 0.0 0.4 0.1 1.6
Intersection Summary
HCM 2010 Ctrl Delay 28.4
HCM 2010 LOS C

HCM 2010 Signalized Intersection Summary 2016 Existing Weekday AM Peak Hour with Impvts - Phasing 1
I:\eng\817294 - 352 King Feasibility\Traffic\analysis\Existing with Improvements\Pmt Prot Phasing\Weekday AM.syn Synchro 8
McMahon Associates, Inc. King Road and 352 Imprvt Feasibility McMahon Associates, Inc. King Road and 352 Imprvt Feasibility
1: Sproul Road (S.R. 0352) & West King Road 2028 Future Weekday PM Peak Hour with Impvts - Phasing 1 1: Sproul Road (S.R. 0352) & West King Road 2028 Future Weekday PM Peak Hour with Impvts - Phasing 1

Splits and Phases: 1: Sproul Road (S.R. 0352) & West King Road

Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (vph) 43 262 89 91 295 138 81 344 49 89 402 31
Future Volume (vph) 43 262 89 91 295 138 81 344 49 89 402 31
Ideal Flow (vphpl) 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800
Lane Width (ft) 10 14 14 10 14 14 10 12 12 10 14 14
Grade (%) 4% -2% -2% 2%
Storage Length (ft) 80 0 125 0 100 0 100 0
Storage Lanes 1 0 1 0 1 0 1 0
Taper Length (ft) 25 25 25 25
Lane Util. Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Frt 0.962 0.952 0.981 0.989
Flt Protected 0.950 0.950 0.950 0.950
Satd. Flow (prot) 1519 1770 0 1596 1811 0 1612 1783 0 1580 1874 0
Flt Permitted 0.950 0.950 0.243 0.297
Satd. Flow (perm) 1519 1770 0 1596 1811 0 412 1783 0 494 1874 0
Right Turn on Red Yes Yes Yes Yes
Satd. Flow (RTOR) 17 25 8 4
Link Speed (mph) 35 40 40 35
Link Distance (ft) 2002 907 900 1892
Travel Time (s) 39.0 15.5 15.3 36.9
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
Heavy Vehicles (%) 3% 3% 0% 1% 1% 4% 0% 0% 0% 0% 0% 4%
Adj. Flow (vph) 44 267 91 93 301 141 83 351 50 91 410 32
Shared Lane Traffic (%)
Lane Group Flow (vph) 44 358 0 93 442 0 83 401 0 91 442 0
Turn Type Prot NA Prot NA pm+pt NA pm+pt NA
Protected Phases 7 4 3 8 5 2 1 6
Permitted Phases 2 6
Detector Phase 7 4 3 8 5 2 1 6
Switch Phase
Minimum Initial (s) 5.0 5.0 5.0 5.0 4.0 25.0 4.0 25.0
Minimum Split (s) 23.0 23.0 22.0 22.0 10.0 31.0 10.0 31.0
Total Split (s) 19.0 24.0 22.0 27.0 13.0 31.0 13.0 31.0
Total Split (%) 21.1% 26.7% 24.4% 30.0% 14.4% 34.4% 14.4% 34.4%
Yellow Time (s) 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0
All-Red Time (s) 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0
Lost Time Adjust (s) -1.0 -1.0 -1.0 -1.0 -1.0 -1.0 -1.0 -1.0
Total Lost Time (s) 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
Lead/Lag Lead Lag Lead Lag Lead Lag Lead Lag
Lead-Lag Optimize?
Recall Mode None None None None None Min None Min
Intersection Summary
Area Type: Other
Cycle Length: 90
Actuated Cycle Length: 81.2
Natural Cycle: 90
Control Type: Semi Act-Uncoord
Description: 8A

Lanes, Volumes, Timings 2028 Future Weekday PM Peak Hour with Impvts - Phasing 1 Lanes, Volumes, Timings 2028 Future Weekday PM Peak Hour with Impvts - Phasing 1
I:\eng\817294 - 352 King Feasibility\Traffic\analysis\2028 Build\Pmt Prot Phasing\Weekday PM.syn Synchro 8 I:\eng\817294 - 352 King Feasibility\Traffic\analysis\2028 Build\Pmt Prot Phasing\Weekday PM.syn Synchro 8
McMahon Associates, Inc. King Road and 352 Imprvt Feasibility
1: Sproul Road (S.R. 0352) & West King Road 2028 Future Weekday PM Peak Hour with Impvts - Phasing 1

Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (veh/h) 43 262 89 91 295 138 81 344 49 89 402 31
Future Volume (veh/h) 43 262 89 91 295 138 81 344 49 89 402 31
Number 7 4 14 3 8 18 5 2 12 1 6 16
Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0
Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Adj Sat Flow, veh/h/ln 1713 1794 1835 1800 1854 1891 1818 1818 1818 1782 1848 1853
Adj Flow Rate, veh/h 44 267 91 93 301 141 83 351 50 91 410 32
Adj No. of Lanes 1 1 0 1 1 0 1 1 0 1 1 0
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
Percent Heavy Veh, % 3 3 3 1 1 1 0 0 0 0 0 0
Cap, veh/h 123 324 110 170 331 155 324 509 72 345 561 44
Arrive On Green 0.08 0.25 0.25 0.10 0.28 0.28 0.06 0.33 0.33 0.07 0.33 0.33
Sat Flow, veh/h 1631 1281 437 1714 1196 560 1731 1557 222 1697 1693 132
Grp Volume(v), veh/h 44 0 358 93 0 442 83 0 401 91 0 442
Grp Sat Flow(s),veh/h/ln 1631 0 1717 1714 0 1756 1731 0 1779 1697 0 1825
Q Serve(g_s), s 2.0 0.0 15.7 4.1 0.0 19.4 2.4 0.0 15.6 2.7 0.0 17.0
Cycle Q Clear(g_c), s 2.0 0.0 15.7 4.1 0.0 19.4 2.4 0.0 15.6 2.7 0.0 17.0
Prop In Lane 1.00 0.25 1.00 0.32 1.00 0.12 1.00 0.07
Lane Grp Cap(c), veh/h 123 0 434 170 0 486 324 0 581 345 0 605
V/C Ratio(X) 0.36 0.00 0.83 0.55 0.00 0.91 0.26 0.00 0.69 0.26 0.00 0.73
Avail Cap(c_a), veh/h 287 0 434 366 0 486 385 0 581 397 0 605
HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Upstream Filter(I) 1.00 0.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00
Uniform Delay (d), s/veh 34.9 0.0 28.1 34.1 0.0 27.8 17.2 0.0 23.3 16.9 0.0 23.5
Incr Delay (d2), s/veh 3.7 0.0 13.6 5.7 0.0 22.0 0.4 0.0 3.4 0.4 0.0 4.5
Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
%ile BackOfQ(95%),veh/ln 1.9 0.0 13.9 4.0 0.0 18.0 2.1 0.0 12.8 2.3 0.0 14.2
LnGrp Delay(d),s/veh 38.7 0.0 41.6 39.8 0.0 49.8 17.7 0.0 26.7 17.3 0.0 27.9
LnGrp LOS D D D D B C B C
Approach Vol, veh/h 402 535 484 533
Approach Delay, s/veh 41.3 48.1 25.2 26.1
Approach LOS D D C C
Timer 1 2 3 4 5 6 7 8
Assigned Phs 1 2 3 4 5 6 7 8
Phs Duration (G+Y+Rc), s 10.5 31.0 12.9 25.1 10.2 31.4 11.0 27.0
Change Period (Y+Rc), s 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0
Max Green Setting (Gmax), s 7.0 25.0 16.0 18.0 7.0 25.0 13.0 21.0
Max Q Clear Time (g_c+I1), s 5.2 17.6 6.6 17.7 4.9 19.0 4.5 21.4
Green Ext Time (p_c), s 0.0 0.7 0.3 0.1 0.0 0.7 0.1 0.0
Intersection Summary
HCM 2010 Ctrl Delay 35.0
HCM 2010 LOS D

HCM 2010 Signalized Intersection Summary 2028 Future Weekday PM Peak Hour with Impvts - Phasing 1
I:\eng\817294 - 352 King Feasibility\Traffic\analysis\2028 Build\Pmt Prot Phasing\Weekday PM.syn Synchro 8
 

Scenario 2  
McMahon Associates, Inc. King Road and 352 Imprvt Feasibility McMahon Associates, Inc. King Road and 352 Imprvt Feasibility
1: Sproul Road (S.R. 0352) & West King Road 2028 Future Weekday AM Peak Hour with Impvts - Roundabout 1: Sproul Road (S.R. 0352) & West King Road 2028 Future Weekday AM Peak Hour with Impvts - Roundabout

Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Intersection
Lane Configurations Intersection Delay, s/veh 14.7
Traffic Volume (vph) 50 268 72 59 292 137 91 374 38 66 240 9 Intersection LOS B
Future Volume (vph) 50 268 72 59 292 137 91 374 38 66 240 9 Approach EB WB NB SB
Ideal Flow (vphpl) 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800
Entry Lanes 1 1 1 1
Lane Width (ft) 10 14 14 10 14 14 10 12 12 10 14 14
Conflicting Circle Lanes 1 1 1 1
Grade (%) 4% -2% -2% 2%
Adj Approach Flow, veh/h 423 530 547 343
Lane Util. Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Demand Flow Rate, veh/h 451 565 559 354
Frt 0.975 0.962 0.990 0.996
Vehicles Circulating, veh/h 412 569 442 513
Flt Protected 0.994 0.994 0.991 0.990
Vehicles Exiting, veh/h 455 432 421 621
Satd. Flow (prot) 0 1709 0 0 1739 0 0 1745 0 0 1812 0
Ped Vol Crossing Leg, #/h 0 0 0 0
Flt Permitted 0.994 0.994 0.991 0.990
Ped Cap Adj 1.000 1.000 1.000 1.000
Satd. Flow (perm) 0 1709 0 0 1739 0 0 1745 0 0 1812 0
Approach Delay, s/veh 10.8 20.9 14.4 10.1
Link Speed (mph) 35 40 40 35
Approach LOS B C B B
Link Distance (ft) 2002 907 900 1892
Travel Time (s) 39.0 15.5 15.3 36.9 Lane Left Left Left Left
Peak Hour Factor 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 Designated Moves LTR LTR LTR LTR
Heavy Vehicles (%) 2% 8% 5% 6% 8% 4% 4% 1% 10% 2% 4% 0% Assumed Moves LTR LTR LTR LTR
Adj. Flow (vph) 54 291 78 64 317 149 99 407 41 72 261 10 RT Channelized
Shared Lane Traffic (%) Lane Util 1.000 1.000 1.000 1.000
Lane Group Flow (vph) 0 423 0 0 530 0 0 547 0 0 343 0 Follow-Up Headway, s 2.609 2.609 2.609 2.609
Sign Control Yield Yield Yield Yield Critical Headway, s 4.976 4.976 4.976 4.976
Entry Flow, veh/h 451 565 559 354
Intersection Summary
Cap Entry Lane, veh/h 906 772 879 818
Area Type: Other
Entry HV Adj Factor 0.937 0.937 0.978 0.968
Control Type: Roundabout
Flow Entry, veh/h 423 530 547 343
Cap Entry, veh/h 850 724 860 791
V/C Ratio 0.498 0.732 0.636 0.433
Control Delay, s/veh 10.8 20.9 14.4 10.1
LOS B C B B
95th %tile Queue, veh 3 6 5 2

Lanes, Volumes, Timings 2028 Future Weekday AM Peak Hour with Impvts - Roundabout HCM 6th Roundabout 2028 Future Weekday AM Peak Hour with Impvts - Roundabout
I:\eng\817294 - 352 King Feasibility\Traffic\analysis\2028 Build\Single Lane Roundabout\Weekday AM.syn Synchro 8 I:\eng\817294 - 352 King Feasibility\Traffic\analysis\2028 Build\Single Lane Roundabout\Weekday AM.syn Synchro 8
McMahon Associates, Inc. King Road and 352 Imprvt Feasibility McMahon Associates, Inc. King Road and 352 Imprvt Feasibility
1: Sproul Road (S.R. 0352) & West King Road 2028 Future Weekday PM Peak Hour with Impvts - Roundabout 1: Sproul Road (S.R. 0352) & West King Road 2028 Future Weekday PM Peak Hour with Impvts - Roundabout

Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Intersection
Lane Configurations Intersection Delay, s/veh 13.6
Traffic Volume (vph) 43 262 89 91 295 138 81 344 49 89 402 31 Intersection LOS B
Future Volume (vph) 43 262 89 91 295 138 81 344 49 89 402 31 Approach EB WB NB SB
Ideal Flow (vphpl) 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800
Entry Lanes 1 1 1 1
Lane Width (ft) 10 14 14 10 14 14 10 12 12 10 14 14
Conflicting Circle Lanes 1 1 1 1
Grade (%) 4% -2% -2% 2%
Adj Approach Flow, veh/h 402 535 484 533
Lane Util. Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Demand Flow Rate, veh/h 411 545 484 534
Frt 0.969 0.964 0.986 0.992
Vehicles Circulating, veh/h 595 479 411 481
Flt Protected 0.995 0.991 0.991 0.992
Vehicles Exiting, veh/h 420 416 595 543
Satd. Flow (prot) 0 1773 0 0 1820 0 0 1776 0 0 1866 0
Ped Vol Crossing Leg, #/h 0 0 0 0
Flt Permitted 0.995 0.991 0.991 0.992
Ped Cap Adj 1.000 1.000 1.000 1.000
Satd. Flow (perm) 0 1773 0 0 1820 0 0 1776 0 0 1866 0
Approach Delay, s/veh 13.4 15.0 11.1 14.5
Link Speed (mph) 35 40 40 35
Approach LOS B C B B
Link Distance (ft) 2002 907 900 1892
Travel Time (s) 39.0 15.5 15.3 36.9 Lane Left Left Left Left
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 Designated Moves LTR LTR LTR LTR
Heavy Vehicles (%) 3% 3% 0% 1% 1% 4% 0% 0% 0% 0% 0% 4% Assumed Moves LTR LTR LTR LTR
Adj. Flow (vph) 44 267 91 93 301 141 83 351 50 91 410 32 RT Channelized
Shared Lane Traffic (%) Lane Util 1.000 1.000 1.000 1.000
Lane Group Flow (vph) 0 402 0 0 535 0 0 484 0 0 533 0 Follow-Up Headway, s 2.609 2.609 2.609 2.609
Critical Headway, s 4.976 4.976 4.976 4.976
Intersection Summary
Entry Flow, veh/h 411 545 484 534
Area Type: Other
Cap Entry Lane, veh/h 752 847 907 845
Entry HV Adj Factor 0.978 0.982 1.000 0.998
Flow Entry, veh/h 402 535 484 533
Cap Entry, veh/h 736 831 907 843
V/C Ratio 0.546 0.644 0.533 0.632
Control Delay, s/veh 13.4 15.0 11.1 14.5
LOS B C B B
95th %tile Queue, veh 3 5 3 5

Lanes, Volumes, Timings 2028 Future Weekday PM Peak Hour with Impvts - Roundabout HCM 6th Roundabout 2028 Future Weekday PM Peak Hour with Impvts - Roundabout
I:\eng\817294 - 352 King Feasibility\Traffic\analysis\2028 Build\Single Lane Roundabout\Weekday PM.syn Synchro 8 I:\eng\817294 - 352 King Feasibility\Traffic\analysis\2028 Build\Single Lane Roundabout\Weekday PM.syn Synchro 8
 

    

Appendix D

PennDOT Design Criteria

 
Transportation Solutions Building Better Communities mcmahonassociates.com
 
Chapter 1 - General Design Publication 13M (DM-2)
TABLE 1.4 (METRIC) Change #1 - Revised 12/12
MATRIX OF DESIGN VALUES – COMMUNITY ARTERIAL
Community Suburban Suburban Suburban Town/Village Town/Village
Rural Urban Core
Arterial Neighborhood Corridor Center Neighborhood Center
Lane Width 1 3.3 m to 3.6 m 3.0 m to 3.6 m 3.3 m to 3.6 m 3.0 m to 3.6 m 3.0 m to 3.6 m 3.0 m to 3.6 m 3.0 m to 3.6 m
1.2 m to 2.4 m 1.2 m to 1.8 m 1.2 m to 1.8 m 1.2 m to 1.8 m 1.2 m to 1.8 m
Shoulder
2.4 m to 3.0 m (if No Parking 2.4 m to 3.0 m (if No Parking (if No Parking (if No Parking (if No Parking
Width 2, 3
or Bike Lane) or Bike Lane) or Bike Lane) or Bike Lane) or Bike Lane)
2.1 m to 2.4 m 2.1 m to 2.4 m 2.1 m to 2.4 m 2.1 m to 2.4 m
Parking Lane 16 NA NA 2.4 m Parallel
Parallel Parallel Parallel Parallel
1.5 m to 1.8 m 1.5 m to 1.8 m
Bike Lane 4 NA 1.5 m to 1.8 m 1.5 m to 1.8 m 1.5 m to 1.8 m 1.5 m to 1.8 m
(if No Shoulder) (if No Shoulder)
4.8 m to 5.4 m 4.8 m to 5.4 m 4.8 m to 5.4 m 4.8 m to 5.4 m 4.8 m to 5.4 m 4.8 m to 5.4 m
for Left Turn for Left Turn for Left Turn for Left Turn for Left Turn for Left Turn
Median 3.6 m to 5.4 m for 3.6 m to 5.4 m for 3.6 m to 5.4 m for 3.6 m to 5.4 m for 3.6 m to 5.4 m for 3.6 m to 5.4 m for
1.2 m to 1.8 m
(if needed) Left Turn; Left Turn; Left Turn; Left Turn; Left Turn; Left Turn;
1.8 m to 2.4 m for 1.8 m to 2.4 m for 1.8 m to 2.4 m for 1.8 m to 2.4 m for 1.8 m to 2.4 m for 1.8 m to 2.4 m for
Pedestrians Pedestrians Pedestrians Pedestrians Pedestrians Pedestrians
Roadway

Curb Return 5 7.5 m to 15.0 m 7.5 m to 10.5 m 7.5 m to 15.0 m 6.0 m to 12.0 m 4.5 m to 9.0 m 4.5 m to 10.5 m 4.5 m to 12.0 m
Travel Lanes 2 to 4 2 to 4 2 to 4 2 to 4 2 to 4 2 to 4 2 to 4
Cross Slopes
2.0% 2.0% 2.0% 2.0% 2.0% 2.0% 2.0%
(Minimum) 6, 7
Cross Slopes
8.0% 6.0% 6.0% 6.0% 6.0% 6.0% 6.0%
(Maximum) 8
Bridge Widths Lane Widths Plus Lane Widths Plus Lane Widths Plus Lane Widths Plus Lane Widths Plus Lane Widths Plus Lane Widths Plus
(Two-Lane Shoulders Each Shoulders Each Shoulders Each Shoulders Each Shoulders Each Shoulders Each Shoulders Each
Facilities) 9, 10, 17 Side Side Side Side Side Side Side
Bridge Widths Lane Widths Plus Lane Widths Plus Lane Widths Plus Lane Widths Plus Lane Widths Plus Lane Widths Plus Lane Widths Plus
(Four-Lane Shoulders Each Shoulders Each Shoulders Each Shoulders Each Shoulders Each Shoulders Each Shoulders Each
Facilities) 9, 10, 17 Side Side Side Side Side Side Side
Vertical Grades
0.5% 0.5% 0.5% 0.5% 0.5% 0.5% 0.5%
(Minimum) 11
Vertical Clearance 5.05 m, 5.05 m, 5.05 m, 5.05 m, 5.05 m, 5.05 m, 5.05 m,
(Minimum) See Chapter 2 See Chapter 2 See Chapter 2 See Chapter 2 See Chapter 2 See Chapter 2 See Chapter 2
Clear Sidewalk
NA 1.5 m 1.5 m to 1.8 m 1.8 m 1.8 m to 2.4 m 1.8 m to 3.0 m 2.4 m to 4.2 m
Width
Buffer 13 NA 1.8 m+ 1.5 m to 3.0 m 1.2 m to 1.8 m 1.2 m to 1.8 m 1.2 m to 1.8 m 1.2 m to 1.8 m
Roadside 12

Shy Distance NA NA NA 0 m to 0.6 m 0 m to 0.6 m 0.6 m 0.6 m


Total Sidewalk
NA 1.5 m 1.5 m to 1.8 m 3.0 m to 4.2 m 3.0 m to 4.8 m 3.6 m to 5.4 m 4.2 m to 6.6 m
Width
Clear Zone
See Chapter 12 See Chapter 12 See Chapter 12 See Chapter 12 See Chapter 12 See Chapter 12 See Chapter 12
Widths 14
Right-of-Way
Varies Varies Varies Varies Varies Varies Varies
Widths 15
Desired Operating
Speed 60-90 km/h 50-60 km/h 60-80 km/h 50 km/h 40-50 km/h 40-50 km/h 40-50 km/h
(Design Speed)
Stopping and
2004 AASHTO 2004 AASHTO 2004 AASHTO 2004 AASHTO 2004 AASHTO 2004 AASHTO 2004 AASHTO
Speed

Passing Sight
Green Book, Green Book, Green Book, Green Book, Green Book, Green Book, Green Book,
Distances
Exhibit 7-1 Exhibit 7-1 Exhibit 7-1 Exhibit 7-1 Exhibit 7-1 Exhibit 7-1 Exhibit 7-1
(Minimum)
2004 AASHTO 2004 AASHTO 2004 AASHTO 2004 AASHTO 2004 AASHTO 2004 AASHTO 2004 AASHTO
Vertical Grades
Green Book, Green Book, Green Book, Green Book, Green Book, Green Book, Green Book,
(Maximum)
Exhibit 7-2 Exhibit 7-10 Exhibit 7-10 Exhibit 7-10 Exhibit 7-10 Exhibit 7-10 Exhibit 7-10

1 - 16
Chapter 1 - General Design Publication 13M (DM-2)
Change #1 - Revised 12/12
TABLE 1.4 (METRIC) (CONTINUED)
MATRIX OF DESIGN VALUES – COMMUNITY ARTERIAL
1
3.6 m preferred for regular transit routes, and heavy truck volumes > 5%, particularly for design speeds of 60 km/h or greater. A 0.3 m to
0.6 m offset to the curb is desirable. 4.2 m for an outside lane with no shoulder or bike lane, if optimal accommodation for bicyclists is desired.
2
Shoulders should be installed in urban contexts only as part of a retrofit of wide travel lanes to accommodate bicyclists.
3
Paving for railroad grade crossings shall extend 0.6 m beyond the extreme rails for the full graded width of the highway.
4
Design of bike lanes should be considered when identified as part of the Engineering & Environmental (E&E) Scoping process. For additional
guidance, refer to Publication 10X, Design Manual, Part 1X, Appendices to Design Manuals 1, 1A, 1B, and 1C , Appendix S, Bicycle and Pedestrian
Checklist.
es - Notes (Community Arterial)

5
Curb Return radius should be as small as possible. Number of lanes, on street parking, bike lanes, and shoulders should be utilized to determine
effective radius.
6
Cross slopes of 3.0% are recommended for design speeds less than 60 km/h.
7
In curbed areas with longitudinal slopes of 1% or less, 3.0% cross slopes may be used on tangents.
8
For additional guidance, refer to Chapter 2, Sections 2.13.B, Rates of Superelevation and 2.13.C, Maximum Superelevation.
9
On curbed approaches, the minimum bridge width may equal the curb-to-curb width. Where pedestrian traffic is anticipated, provisions for a sidewalk,
preferably on the outside of the parapet, should be considered and shall meet the Department's Standards and requirements (see Chapter 6). Where
paved or curbed parking lanes exist or have been approved for construction on approaches, the clear roadway width of the proposed bridge in each
case shall be determined by the Central Office, Bureau of Project Delivery upon receipt of the District Executive’s recommendation.
10
For appropriate bridge widths, refer to the Minimum Width Criteria for Bridges.
Matrix of Design Value

11
Recommended minimum grade of 0.75% on curbed sections.
12
The Roadside design values should be considered and implemented as feasible and reasonable; however, Chapter 6, Pedestrian Facilities, should
still be used for minimum design criteria. ADA accommodations must be addressed in accordance with ADA policy.
13
Buffer is assumed to be planted area (grass, shrubs and/or trees) for suburban neighborhood and corridor contexts; street furniture/car door zone for
other land use contexts. Minimum of 1.8 m for transit zones.
14
Center piers are not desirable. Increase bridge span where necessary to provide for required horizontal stopping sight distance. Provide clearance for
guide rail in front of substructures if protection is required. For offset distances to substructure units, see Publication 15M, Design Manual, Part 4,
Structures .
15
No minimum right-of-way width is suggested. The procurement of sufficient right-of-way width should be based on the preferable dimensions for all
the elements of the composite highway cross section and should be adequate to accommodate the construction and proper maintenance of the highway
throughout the project. Future widening should be considered and, where needed for safety, additional right-of-way may be required for adequate sight
distance. For additional information on right-of-way widths, refer to the 2004 AASHTO Green Book.
16
2.1 m parking lanes on this roadway type to be considered in appropriate conditions.
17
For long bridges over 60 m in length, the shoulder width may be 1.2 m on each side.

1 - 17
 

    

Appendix E

Estimated Opinions of Cost

 
Transportation Solutions Building Better Communities mcmahonassociates.com
 
McMahon Aassociates, Inc. 3/25/2019
Engineer's Conceptual Opinion of Cost Prepared By: JWJ
Checked By: JJK

Municipality East Goshen & East Whiteland Townships, Chester County, PA


Project Name: Sproul Road/ North Chester Road (S.R. 0352) and King Road (S.R. 2022)
Project Number: 817294.11

Plan Title: Sproul Road/ North Chester Road (S.R. 0352) and King Road (S.R. 2022) Improvement Feasibility Study
Roadway(s): Sproul Road/ North Chester Road (S.R. 0352) and King Road (S.R. 2022)
Project Description: Roadway improvements including the addition of Left-turn lanes on all legs of the Sproul Road/ North Chester Road (S.R. 0352) and King Road
(S.R. 2022) intersection.
Unit Costs Last Revised: 3/25/2019
Source: ECMS Bid Price History and Similar Project Experience

Disclaimer: McMahon Associates, Inc. has provided this opinion of cost as requested by the client. Please note that opinions of cost are subject to change
based on plan/design revisions, fluctuations in unit costs, field conditions, and differences in locale. Opinions of cost are provided for use in budgeting, but in
no way intended to be construed as a final cost for the project. Final costs are contingent only on actual bids from contractors. McMahon Associates, Inc. will
not be held responsible for differences between this opinion of cost and contractor bid costs.

Intersection 1: Sproul Road/ North Chester Road (S.R. 0352) and King Road (S.R. 2022)
Item No. Description Cost

1 Total Roadway Construction Cost $1,450,359.00

2 Construction Inspection $145,036.00

3 Total Roadway Construction + Inspection $1,595,395.00

4 Engineering and Permitting $435,108.00

5 Utility Relocations $315,000.00

6 Right-of-Way Acquisitions $180,000.00

7 Total Project Cost $2,525,503.00

General Notes:

1. The following costs are rough estimates for budgeting purposes only: Right-of-Way, Construction Inspection, Engineering and
Permitting and Utility Relocation. The costs associated with these items will need to be determined through the development of the
project. Contingency, Construction Inspection and Inflation are based on PennDOT Publication 352.
2. Refer to the intersection spreadsheet details relating to cost calculations and individual intersection assumptions.
3. The Engineer's Conceptual Opinion of Cost does not include relocating or resetting existing aboveground/ underground utilities
within the limits of the project. Impacts to existing utilities will need to be determined during the preliminary engineering of the
project through subsurface utility engineering. Due to visible evidence of subsurface utilities within the project area, it is
recommended (and likely required by law) that utility test pits be performed during the preliminary engineering of the
project.
4. Existing legal rights-of-way and existing property lines, as well as the size and location of any required rights-of-way (temporary
or permanent), will need to be determined during the preliminary engineering of the project.
5. The size, type and location of all required roadway drainage and SWM facilities will need to be determined during the preliminary
engineering of the project.
Engineer's Conceptual Opinion of Cost for 3/25/2019
Sproul Road/ North Chester Road (S.R. 0352) and Kind Road (S.R. 2022)
East Goshen & East Whiteland Townships, Chester County, PA

Item
No. Description Comment Unit Quantity Unit Cost Cost
Standard Items
1 Clearing and Grubbing LS 1 $20,000.00 $20,000.00
2 Class 1 Excavation For Widened Pavement CY 1,750 $45.00 $78,750.00
3 Foreign Borrow CY 600 $30.00 $18,000.00
4 Grading (includes topsoil and seeding) For Roadside Slopes & Restoration SY 2,150 $10.00 $21,500.00
Full Depth Bituminous Pavement Including Wearing Course
5 SY 3,950 $65.00 $256,750.00
(6" Bituminous Base Course & No. 2A Sub-base, 6" Depth)
6 Driveway Adjustments SY 225 $50.00 $11,250.00
7 Milling and Bituminous Overlay (including Tack Coat) SY 4,900 $17.50 $85,750.00
8 Plain Cement Concrete Curb LF 1,770 $30.00 $53,100.00
9 Drainage New Drainage Structures/Inlets LS 1 $140,000.00 $140,000.00
10 4" White Pavement Markings, Hot Thermoplastic Paint LF 4,100 $1.00 $4,100.00
11 4" Yellow Pavement Markings, Hot Thermoplastic Paint LF 4,800 $1.00 $4,800.00
12 6" White Pavement Markings, Hot Thermoplastic Paint LF 290 $1.50 $435.00
13 24" White Pavement Markings, Hot Thermoplastic Paint LF 90 $8.00 $720.00
14 24" Yellow Pavement Markings, Hot Thermoplastic Paint LF 300 $8.00 $2,400.00
15 Marking Legend, Hot Thermoplastic Paint EA 4 $150.00 $600.00
16 Post Mounted Signs LS 1 $3,000.00 $3,000.00
17 ADA Accessible Curb Ramp EA 4 $6,500.00 $26,000.00

Special Items
18 Stormwater BMPs LS 1 $100,000.00 $100,000.00
19 Traffic Signal Replacement of all Equipment LS 1 $220,000.00 $220,000.00
20 Privacy Fence 6' Height LF 460 $25.00 $11,500.00

21 Subtotal Roadway Construction Cost Items 1 - 20 $1,058,655.00


22 Maintenance and Protection of Traffic 12% of Item 21 $127,039.00
23 Erosion and Sediment Control 5% of Item 21 $52,933.00
24 Mobilization 5% of Item 21 $52,933.00
25 Contingency 15% of Item 21 $158,799.00
26 Total Roadway Construction Cost Items 21 - 25 $1,450,359.00
27 Construction Inspection 10% of Item 26 $145,036.00
28 Total Roadway Construction + Inspection Items 26 - 27 $1,595,395.00
29 Engineering and Permitting 30% of Item 26 $435,108.00
30 Utility Relocations (Poles) LS 1 $315,000.00 $315,000.00
31 Right-of-Way Acquisitions LS 1 $180,000.00 $180,000.00
32 Total Project Cost Items 28 - 31 $2,525,503.00

Assumptions:

-The Engineer's Conceptual Opinion of Cost includes a lump-sum estimate for roadway drainage and SWM facilities. The type, location and size of these facilities
must be determined during preliminary engineering of the project, based on existing topography and existing stormwater management facilities (if any).
McMahon Aassociates, Inc. 3/25/2019
Engineer's Conceptual Opinion of Cost Prepared By: JWJ
Checked By: JJK

Municipality East Goshen & East Whiteland Townships, Chester County, PA


Project Name: Roudnabout - Sproul Road/ North Chester Road (S.R. 0352) and King Road (S.R. 2022)
Project Number: 817294.11

Plan Title: Sproul Road/ North Chester Road (S.R. 0352) and King Road (S.R. 2022) Improvement Feasibility Study
Roadway(s): Sproul Road/ North Chester Road (S.R. 0352) and King Road (S.R. 2022)
Project Description: Convert existing signalized intersection of the Sproul Road/ North Chester Road (S.R. 0352) and King Road (S.R. 2022) to signle-lane roundabout.

Unit Costs Last Revised: 3/25/2019


Source: ECMS Bid Price History and Similar Project Experience

Disclaimer: McMahon Associates, Inc. has provided this opinion of cost as requested by the client. Please note that opinions of cost are subject to change
based on plan/design revisions, fluctuations in unit costs, field conditions, and differences in locale. Opinions of cost are provided for use in budgeting, but in
no way intended to be construed as a final cost for the project. Final costs are contingent only on actual bids from contractors. McMahon Associates, Inc. will
not be held responsible for differences between this opinion of cost and contractor bid costs.

Intersection 1: Roundabout - Sproul Road/ North Chester Road (S.R. 0352) and King Road (S.R. 2022)
Item No. Description Cost

1 Total Roadway Construction Cost $1,815,783.50

2 Construction Inspection $181,579.00

3 Total Roadway Construction + Inspection $1,997,362.50

4 Engineering and Permitting $544,736.00

5 Utility Relocations $135,000.00

6 Right-of-Way Acquisitions $450,000.00

7 Total Project Cost $3,127,098.50

General Notes:

1. The following costs are rough estimates for budgeting purposes only: Right-of-Way, Construction Inspection, Engineering and
Permitting and Utility Relocation. The costs associated with these items will need to be determined through the development of the
project. Contingency, Construction Inspection and Inflation are based on PennDOT Publication 352.
2. Refer to the intersection spreadsheet details relating to cost calculations and individual intersection assumptions.
3. The Engineer's Conceptual Opinion of Cost does not include relocating or resetting existing aboveground/ underground utilities
within the limits of the project. Impacts to existing utilities will need to be determined during the preliminary engineering of the
project through subsurface utility engineering. Due to visible evidence of subsurface utilities within the project area, it is
recommended (and likely required by law) that utility test pits be performed during the preliminary engineering of the
project.
4. Existing legal rights-of-way and existing property lines, as well as the size and location of any required rights-of-way (temporary
or permanent), will need to be determined during the preliminary engineering of the project.
5. The size, type and location of all required roadway drainage and SWM facilities will need to be determined during the preliminary
engineering of the project.
Engineer's Conceptual Opinion of Cost for 3/25/2019
Roundabout - Sproul Road/ North Chester Road (S.R. 0352) and Kind Road (S.R. 2022)
East Goshen & East Whiteland Townships, Chester County, PA

Item
No. Description Comment Unit Quantity Unit Cost Cost
Standard Items
1 Clearing and Grubbing LS 1 $70,000.00 $70,000.00
2 Class 1 Excavation For Reconstructed/Removed Pavement CY 3,000 $45.00 $135,000.00
3 Foreign Borrow CY 1,600 $30.00 $48,000.00
4 Grading (includes topsoil and seeding) For Roadside Slopes & Restoration SY 3,000 $10.00 $30,000.00
Full Depth Bituminous Pavement Including Wearing Course
5 SY 3,950 $75.00 $296,250.00
(6" Bituminous Base Course & No. 2A Sub-base, 8" Depth)
6 Reinforced Cement Concrete Pavement - 8" Depth Truck Apron SY 575 $140.00 $80,500.00
7 Driveway Adjustments SY 270 $50.00 $13,500.00
8 Milling and Bituminous Overlay (including Tack Coat) SY 350 $17.50 $6,125.00
9 Plain Cement Concrete Curb LF 1,975 $30.00 $59,250.00
10 Plain Cement Concrete Mountable Curb LF 950 $40.00 $38,000.00
11 Roudabout Truck Apron Curb LF 530 $60.00 $31,800.00
12 Plain Cement Concrete Pavement - 4" Depth Median Islands SY 270 $80.00 $21,600.00
13 Plain Cement Concrete Sidewalk SY 250 $80.00 $20,000.00
14 Guide Rail - Type 31 LF 250 $30.00 $7,500.00
15 End Treatement EA 1 $2,000.00 $2,000.00
16 Drainage New Drainage Structures/Inlets LS 1 $140,000.00 $140,000.00
17 4" White Pavement Markings, Hot Thermoplastic Paint LF 2,000 $1.00 $2,000.00
18 4" Yellow Pavement Markings, Hot Thermoplastic Paint LF 1,850 $1.00 $1,850.00
19 6" White Pavement Markings, Hot Thermoplastic Paint LF 275 $1.50 $412.50
20 24" Yellow Pavement Markings, Hot Thermoplastic Paint LF 50 $10.00 $500.00
21 Marking Legend, Hot Thermoplastic Paint Yield Line EA 4 $150.00 $600.00
22 Post Mounted Signs LS 1 $12,500.00 $12,500.00
23 ADA Accessible Curb Ramp EA 12 $6,500.00 $78,000.00

Special Items
24 Stormwater BMPs LS 1 $100,000.00 $100,000.00
25 Landscaping LS 1 $75,000.00 $75,000.00
26 Demolition LS 1 $40,000.00 $40,000.00
26 Grade Serperator/Barrier Wall LF 75 $200.00 $15,000.00

27 Subtotal Roadway Construction Cost Items 1 - 26 $1,325,387.50


28 Maintenance and Protection of Traffic 12% of Item 27 $159,047.00
29 Erosion and Sediment Control 5% of Item 27 $66,270.00
30 Mobilization 5% of Item 27 $66,270.00
31 Contingency 15% of Item 27 $198,809.00
32 Total Roadway Construction Cost Items 27 - 31 $1,815,783.50
33 Construction Inspection 10% of Item 32 $181,579.00
34 Total Roadway Construction + Inspection Items 32 - 33 $1,997,362.50
35 Engineering and Permitting 30% of Item 32 $544,736.00
36 Utility Relocations (Poles) LS 1 $135,000.00 $135,000.00
37 Right-of-Way Acquisitions LS 1 $450,000.00 $450,000.00
38 Total Project Cost Items 34 - 37 $3,127,098.50

Assumptions:

-The Engineer's Conceptual Opinion of Cost includes a lump-sum estimate for roadway drainage and SWM facilities. The type, location and size of these facilities
must be determined during preliminary engineering of the project, based on existing topography and existing stormwater management facilities (if any).

You might also like