PROJECT: THOE READY MIX Ref No. CONC/10
PAGE 1 OF 4
SECTION: CONCRETE DATE OF ISSUE
Dec. 2017
SUBJECT: BY:
QA/QC ENGINEER
Batching Plant Method Statement APPROVED BY:
Plant Manager
ACTION VERIFY
1. SCOPE
Produce Concrete by Batching Plant. Plant Project
2. PROCEDUR manager Director
Summary
Mixing raw materials like cement, coarse aggregates, fine Plant
aggregates, chemicals and water inside plant and send to sites by operator/ Third party
truck-mixer to cast concrete by concrete pump or without concrete QC / Project
pump. engineer Director
.1 Checks Prior to Commencement of Activity:
Special care shall be taken for proper storage of basic Logistics Plant
materials in order to avoid contamination. Unless otherwise officer operator
specified, the following measures shall be taken for proper /store
handling and storage of these materials: keeper
Barge, Tipper and shovels will use for transfer materials. Plant
. Cement (in bulk): Logistics operator/la
Logistic and store team will handle cement tankers from Palm Diera officer b
to island until unloading finish in silo. /store technician
keeper
Plant
i) The silos shall be weatherproof and the mechanism will Maintena manager
be cleaned regularly. nce
ii) The air filter will be cleaned. superviso
iii) Care shall be taken to use stored cement in the order of r
delivery.
iv) Care shall be taken to minimise the contact of cement
with air.
v) The silo shall be painted.
PROJECT: PROJECT NAME Ref No. CONC/10
PAGE 2 OF 4
SECTION: DATE OF ISSUE
CONCRETING Dec. 2017
SUBJECT: BY:
QA/QC ENGINEER
BATCHING OF CONCRETE APPROVED BY:
Plant Manager
ACTION VERIFY
.4 Aggregates:
.5 Admixtures:
.6 Water:
.7 Plant:
i) Batching and mixing plant shall be painted white and kept Plant HSE
clean outside and inside mixer. helper/pla manager/
ii) If possible, mixing and batching plant shall be shaded nt Plant
from the sun. operator/ Manager
iii) Provision shall be made to prevent dust accumulating in HSE /project
the plant and immediately before it is used each day (or officer director
after any substantial interruption in concreting) it shall be
flushed out with water.
iv) Feed belts and weigh batchers shall be protected from
the wind so that cement can’t be blown away if screw not
using.
v) Calibration should done or Ensure the accuracy of all
weighing and measuring equipment falls within + 3%
unless specified otherwise calibrate plant as necessary.
3. DOCUMENTATION